<<

E425 Volume 14 Public Disclosure Authorized

People' s Republic of

World Bank Financed No. 2 Highway Project

Taihe- Expressway Mainline, the Inter-connecting Roads,

and the Rural Roads Improvement Program (RRIP) Public Disclosure Authorized Environmental Assessment Summary

(Fourth Edition) Public Disclosure Authorized

FILECOPYf

Public Disclosure Authorized Research Institute of Highway, MOC

January, 2001 SCANNED People ' s Republic of China

World Bank Financed Jiangxi No. 2 Highway Project

Taihe-Ganzhou Expressway Mainline, the Inter-connecting Roads,

and the Rural Roads Improvement Program (RRIP)

Environmental Assessment Summary

(Fourth Edition)

Research Institute of Highway, MOC

January, 2001 Contents

A. Project Background .1 B. Project overview ...... 3 C. Current Environmental Description ...... 4 D. Predicted Environmental Impacts and Mitigation Measures. 8 E. Environmental Monitoring .20 F. EnvironmentalManagement Organization .*------20 G. Ability Development and EnvironmentalProtection Training Plan.23 H. Public Participation and Information Disclosure .23 I. Resettlement .**-----..------..------*------*------*------.*--25 J. Conclusion . 25

Annex I EAP Key Factors .27 Annex II Environmental Monitoring Plan .------30 Annex III Environmental Supervision Plan . 1I3 Annex IV Investment for Environmental Protection ...... -..--- 32 Annex V Public Investigation summary .*...... 35 Annex VI The People' Republic of China Environmental and Resettlement Bulletin for the Jiangxi No.2 Highway Project ...... 37 Annex VII Environmental Standards (Air, Noise, Water) .*------38 Annex VIII Relevant documents List . ---...... 39

Attached Figure 1: Geographic Position of the Proposed Road Attached Figure 2: Alignment of Taihe-GanzhouExpressway Attached Figure 3: Culture Relics DistributionMap of the Main line and connecting roads Attached Figure 4: Culture Relics DistributionMap of the RRIP Attached Figure 5: Alignment schemes of the main line in west ganjiang in pre- feasibility study phase A. Project Background and Legal Basis of EA 1. Jiangxi No.2 highway project financed by the World Bank loan includes the Taihe- Ganzhou Expresway Mainline, three inter-connectingroads in Wan' an, Suichuan and Ganzhou and four Rural Road improvement program (RRIP) as Suichuan-Chezi' ao, Yutian-, Shashibu-Wangmudu and Tangjiang-Dongshan.The study of the Taihe-Ganzhouexpressway main line was started from Sept. 1994. In Dec. 1999, the Feasibility Study Reportfor the Gan-Yue Expressway (Taihe-Ganzhou Section was compiled and its supplementary report was compiled in May 2000. By July 2000, the two-stage preliminary design was completed. As to the three connecting roads, Feasibility Study Report for Wan' an, Suichuang and Ganzhou were completed in February 2000 and their Two-Stage Preliminary Design were finished in September, 2000. The study for the RRIP started from April, 2000 and their Feasibility Study Report was completed in the same year.

2. The Research Institute of Highway under the Ministry of Communications (MOC), a holder of class A environmental assessment certificate issued by the China National Environmental Protection Agency (SEPA), was entrusted by the Jiangxi Provincial Communications Department (JPCD) in Dec. 1999 to undertake the environmental assessment for this project. In March 2000, the Terms of Reference (TOR) for this project was reviewed and approved by SEPA. In June 2000, the environmental impact assessment (EIA) report for this project has passed the experts' reviewing sponsored by the MOC environmental office, now it is waiting for the SEPA' s approval. Jiangxi Provincial Environmental Protection Research Institute (holding class A environmental assessment certificate issued by the SEPA) was entrusted by the Jiangxi Provincial High-Class Highway Administration in Dec. 1999 to undertake the environmental assessment for the four RIP roads.

3. The EIA and EAP (first version) of Gan-Yue Expressway Taihe-Ganzhou Section (including the Wan' an, Suichuan and Ganzhou connecting roads) were completed in March 2000. In May 2000, the World Bank environmental experts have reviewed the documents in . In June 2000, according to the options of the World Bank experts, the assessment unit and the JPCD revised these environmental documents and compiled the EIA and EAP (second version) for the main line, and compiled separate EIA and EAP (first version) for the three connecting roads. In July 2000, World Bank experts reviewed them in Nanchang and presented revising opinions. In Sep. 2000, the assessment unit finished the EIA, EAP (third edition) for the main line and the EIA, EAP (second version ) for the connecting roads. The EIA, EAP (first version) for the RIP were compiled by Jiangxi Provincial Environmental Protection Research Institute in November, 2000. In November 2000, the World Bank experts reviewed these documents in Nanchang and presented revising opinions. In December 2000, the assessmentunit finished the EIA, EAP (fourth version) for the main line and the EIA, EAP (third version) for the connecting road; the EIA, EAP (second version) for the RIP projects and the environmentalassessment summary (EAS, third version).

4. Concerned departments in Jiangxi province have participated in the reviewing of the reports, including environmental protection department and research institutes, etc. Opinions have been extensively solicited from some units and non- governmental organizations that may be impacted and particularly from people who will be land acquired, removed and resettled.

5. The Environmental Impact Assessment was compiled and inspected in accordance with the Chinese policies and regulations regarding project environmental assessment as well as the WVorldBank Working Handbook OP/BP/GP4.01 Environment Assessment, March 1999. The followings are the major laws and regulations applied to this assessment. (1) Law on Environmental Protection of People I s Republic of China (26 Dec., 1989); (2) Law on Water and Soil Conservation of People' s Republic of China (29 June.1991) (3) Law on Land MWanagementof People' s Republic of China (29 Aug.,1998) (4) Law on Ambient Noise Pollution Controlof People ' s Republic of China (29 Oct., 1996); (5) Lawvon WVaterPollution Control of People' s Republic of China (15 May, 1996) (6) Lawvon Atmospheric Pollution Control of People ' s Republic of China (29 Dec., 1995) (7) Lawt,on Solid WastePollution Control of People ' s Republic of China (Oct. 30.1995) (8) Law on Highways of People ' s Republic of China.(July 3,1997) (9) Environmental Protection and Management Regulation for Construction Projects [The State Council, C. 253] (Nov. 18., 1998); (10)Environmental Protection and Management Measures for Construction Projects of Communications (The Ministryof Communications,C.(90) 17);

2 (1 l)Announcement on Further StrengtheningEnvironmental Impact Assessment of Construction Project Financed by International Financial Institution [(1993) No.324 Document on Environmental Supervision, issued by China National EnvironmentalProtection Agency etc.]; (12) World Bank Working Handbook OP/BP/GP4.01 Environment Assessment, March 1999 (13)Technical Guidelines for Environmental Assessment (HJ/T2.1-2.3-93, HJ/T2.4-1995,HJ/T19-1997, SEPA) (14)Management Category of Environmental Protection Classification for ConstructionProjects (tentative), SEPAdocument (1 999)No. 99 (15) EnvironmentalAssessment Codefor Road Construction Project (tentative), (JTJO050-96,MOC) (16) Environmental Protection Regulation for Construction Projects in Jiangxi Province (April 29,1995);

6. The environmental standards applied to this assessment are as follows, their specific standard limits are listed in Annex VI.I (1) GHZBI -1999 SurfcaceWater Environmental Quality Standard (2) GB8979-1996Sewage DischargingStandard (3) GB5084-92 Farmland Irrigation WaterQuality Standard (4) GB 12523-90Construction Site Noise Limits (5) GB3096-93 UrbanArea Ambient Noise Standard (6) GB3095-1996 Ambient Air Quality Standard (7) GB 16297-1996Atmospheric Pollutant comprehensiveDischarging Standard (8) JTJO25-90Industry Standard of P.R.C Design Specifications for Highway Tunnels

B. Project Description 7. With design speed of 100km/h, 4 lanes and subgrade width of 26.0m, the Gan-Yue Expressway Taihe-Ganzhou Section is 128.4454km in length with 4 interchanges (another for reserve). 53 grade separations and 9 extra-large/large bridges and 2 tunnels. The whole line also sets up relatively perfect traffic engineering facilities, of which there are two service areas, two parking lots and 5 tollgates. It will take up a land of 13137.69 mu.. The estimated total investment is 3,562.713638 million yuan. The project has three connecting roads totaling 48.615km (including Wan' an Ganjiang extra-large bridge ). The four RIP roads totals 179.81km.

8. With a total length of 13.860km, the Wan' an connecting road is a class II road

3 with its design speed of 80km/h, subgrade width of 12.Om and one huge bridge. The total investment is 102.480873 million yuan.

9. With a total length of 20.598km, the Suichuan connecting road is a class II road with its design speed of 80km/h, subgrade width of 12.Om and four medium bridges. The total investment is 98.373143 million yuan.

10. With a total length of 14.157km, the Ganzhou connecting road is a class II road with its design speed of 80km/h, subgrade width of 17.Om and 2 grade separations. The total investment is 103.846558 million yuan.

11. The total length of the RIP road no.1 Suichuan-Chezi' ao is 79.0km, of which, 18.3km of class II road in hilly area is designed with speed of 80km/h, 12.Om for subgrade width and one bridge; 7.7km of class II road in heavy rolling area is designed with 40km/h. 8.5m for subgrade width; 53km of class III road in heavy rolling area is designed with 30km/h, 8.5/7.5m for subgrade width. The total investment is 99.8068 million yuan.

12. With a total length of 45.8455km, the RIP road no.2 Yutian-Xinjiang is a class III road with its design speed of 30km/h, subgrade width of 8.5m, one bridge and one tunnel. The total investment is 95.195 million yzian.

13. With a total length of 26.251km, the RIP road no.3 Shashibu-Wangmudu is a class II road with its design speed of 40km/h, subgrade width of 12.0m. 2 medium bridges . The total investment is 96.069885 millionyuan.

14. With a total length of 28.7157km, the RIP road no.4 Tangjiang-Dongshan is a class II road with its design speed of 40km/h, subgrade width of 12.0m, one bridge. The total investment is 81.4949 millionyuian.

C. Current Environmental

15. Topgraphy and Landform (1) The Gan-Yue Expressway Taihe-Ganzhou section main line lies in the south part of Jiangxi province. basically strikes from north to south at the west bank of the Ganjiang river. The area is high in the south and low in the north. The starting section Mashi (Taihe)- Luomukeng(Nankang) is hilly area with sharp undulation in landform, steep mountains and numerous gullies. The section from Luomukeng- Lijiashan(destination, Nankang) is low hilly flat terrain with partial

4 alluvial plain of Shangyoujiang river and Zhangjiang river. (2)The Wan' an connecting road lies in a rising and falling terrain from its origin to Shaokou and from Baijia to destination, and lies in the alluvial plain of Ganjiang river from Shaokou to Baijia. (3)The Suichuan connecting road lies in a rising and falling terrain from its origin to Dongtang, and lies in the alluvial plain of Suizhoujiang river from Dongtang to destination with flat and open landform, but low terrain. (4) The Ganzhou connecting road lies in the Ganzhou region in the south part of Jiangxi province, where the landform is relatively flat and the topography is mainly hills, followed by plains and hilly-lands. (5) The RIP road Suichuang-Chezi' ao is featured with hilly and low mountain topography, with a terrain strikes from southeast upward gradually to northwest. (6) The RIP road Yutian-Xinjiang lies between the Jinggansha and Yushan mountains, hilly terrain interval with low hilly land. It is featured with hilly land, downs, plains, etc but dominated by hilly land. (7) The RIP road Shashibu-Wangmudu goes along the low hilly land. (8) The RIP road Tangjiang-Dongshan goes along the Luoxiao Mountains. The route in the middle hilly area is aligned along the river valley, flat terrain.

16. Climates and Hydrology (I)The project area belongs to subtropical monsoon climate characteristic of cold winter and spring, hot summer and dry autumn, rainy early summer, rich clouds and little sunshine, long frost-free days sufficient heat, large temperature difference, abundant but uneven rainfall. The annual average temperature is 17.7-19.2°C, the annual average rainfall is 1372-1595mm. Summer prevails south wind, other seasons prevail north wind with annual average wind speed of 1.9m/s. The climate for the four RIP roads is similar to the above. (2) Rivers within the project area mostly belong to the Ganjiang river water system, they all enter into the Ganjiang river which pours into the . Runoff mainly comes from rain, centering in April-June. River flow has big changes in every season. (3)The quality of major water bodies is good, is the major water source for agricultural and industrial production. The underground water along the road is relatively developed and of good quality, it is the main source for drinking.

17. Social Economy The project area are all within JiI an city and Ganzhou city which are strong in industry, especially the power, machinery, chemical and textile are of some important

5 position in Jiangxi province. Fertile in land and rich in produce, the agriculture is well developed. According to 1999year-end statistics, the population in the region is 2.999 million people, a density of 228persons/km2. The Ganzhou prefecturewhere the project lies in is very rich in natural resources; it is one of the key non-ferrous metal production bases in China, with strong industrial power and great development potential for agriculture.

18. Ecological environment The project area lies in subtropical zone with its major plants are evergreen broadleaf trees, subtropical coniferous trees, subtropical broadleaf and coniferous mixed trees, subtropical bamboo trees. The forest coverage rate is 49.0-67.5%. Along the road there are mostly cultivated vegetation and a few amount of bushes or natural grass. The farmland vegetation is mainly rice, cotton, and sugar cane or cash crops. Along the assessment scope there are mostly distributed by masson pines, citrus and oil trees. There are no endangered or rare species of animals and plants 500m within the roadside (including the three connecting roads and the four RIP roads), nor natural reserve zones.

19. Tourism and Cultural Relics (1)Tourism resources in the area are very rich. In the Ji' an prefecture, there are 3 scenery spots such as Jinggangshan Mountain, Qingyuanshan Mountain and Yusishan Monutain. and 9 national revolution remains. The south Ganzhou prefecture is rich in natural and historical interests; the Ganzhou City is a national historical and cultural city, endowed with many sceneries of the . The above sceneries are all more than lOkm away from the proposed highway. (2)According to the Cultuiral Relics Sutrvey Report for the Taihe-Ganzhou Expressway of the Jiangxi No. 2 Highway Projectfinanced by the World Bank, provided Jiangxi Provincial Cultural Relics Archeology Institute, a total of 21 relics found along the road are 0.7-2km away from the road, which are at city and county protection level. Since the RIP projects only involve improvement on the existing roads along which the culture relics have been properly handled before.

20. Air Quality Along the proposed road (including the three connecting roads), 8 representative points were monitored for their current ambient air quality (NOx, TSP), 5 points

6 were monitored for the four RIP road project. The results show that only Huangsha Middle School along the Tangjiang-Dongshan road has exceedance in TSP as the school was having the sports meeting at the monitoring time, the NOx and TSP concentrations in other 12 points all comply with class II standard, and the NOx has a large tolerance margin, providing good conditions to the road construction.

21. Acoustic Quality The monitored results show that except individual village that exceeds class I noise standard but complies with class II standard, most of the ambient noise complies with class I even class zero standard. The monitored results of current noise conditions of schools, Kangfucun and dermatophyte clinic comply with class I standard. The monitoring results for the three connecting roads comply with theclass I standard. As to the RIP project, Suichuang-Chezi' ao road, schools and clinic meet class I standard; the rest meet class II standard. Half of the points in daytime and two third of the points at nighttime in villages along the Shashibu-Wangmodu road section meet class II standard. While the monitoring points along Tangjiang-Dongshan road have noise exceedance. For Yutian-Xinjiang road, 2 schhols have slight noise exceedance in daytime, the rest all meet class II standard. According tot he monitored results, generally speaking, the acoustic environment either for the main line project or the connecting roads are quite good, able to meet the requirements of each sensitive location to acoustic environment. However, the acoustic environment for the RIP roads is not good.

22. Water Resources and Water Quality The project area belongs to Ganjiang river system with the major rivers are Ganjiang river. Suiehuan river, Shangyoujiang river, Zhangjiang river and their tributaries. The monitored results of current condition show that each water quality indicator is 100% compliant, indicating a good water quality and ability to meet water requirement (class III).

23. Soil Erosion Within the four cities or counties of the project area, except that is slight in soil erosion, the other three counties have a higher soil erosion level than the provincial average. But most sections of the main line are slightly and mildly eroded area; very few are heavily eroded area. Of the three connecting roads, the areas along the Wan' an and Suichuan connecting roads are slightly eroded, while the area along the Ganzhou connecting

7 road is heavily eroded area. The RIP road Suichuang-Chezi' ao and Yutian-Xinjiangroads are slightly eroded; Tangjiang-Dongshanroad and Nankang have heavy soil erosion, being the strong eroded area; territory have slight soil erosion, being lightly eroded area. While Shashibu-Wangmoduroad is medium eroded area. The on-the-line areas are of slight soil erosion areas and heavily eroded area.

24. Traffic and Transportation Transportation infrastructure in Jiangxi province is relatively backward. Today a comprehensive transportation system was formed that combines railway, roadway, waterway, airway, and pipeline. In recent years, with rapid economic growth and increasing traffic volume, the original roads can not meet the economic demand, leading to steady deterioration of traffic condition, especially road transportation have many problems.

D. Environmental Impacts due to the project and Mitigation

Measures 25. The environmental impacts and their mitigation measures for this project are stated and implemented in three stages. The EAP key factors for this project are summarized in Annex I.

26. Design Stage (1) Selection of the Alignment The selection of the alignment for this project has been discussed and consulted many times among the design unit, environmental unit and the employer on the principle of rationality and lower cost together with the full consideration to factors such as protection of farm arable land, schools, residential quarters, cultural relics, flood control and discharge, urban development program, building materials source and quarries, etc. The current alignment has been finally chosen after wide consultation with relevant experts, local governments on the line and the people from every field. The mainline alignment is selected after comparison and optimization in three stages as pre-feasibility study (Pre.F/S), feasibility study (F/S), and design (as shown in figure D-l). T In pre-feasibility study phase, after excluding the impossibility of upgrading national road 105 to high-class highway and refusing to the East Ganjiang alignment for the main line, the west Ganjiang alignment is decided. Three schemes in the

8 Upgradin|naioajg EatGnin WestGanAjiantg ...... highwvay105 alignment alignment

| WestG anj iang aligNnment

Scheme I in Pre-F/S Scheme11 in Pre-F/S | Scheme III in Pre-F/S

Scheme I in Pre-FIS

Taihe alternative Suichuan Fuziling Mashuang section alternative section alternative section alternative section

Taihe Altemative Suichuan Fuziling Mashuang 1 | Alternative I Alternative I Alternative 11 It

Add Wa, an Add Fenggang Adjust Fuziling alternative section alternative section alternative section D

| a an a termative I Fenggang al ernative It Fuzilinng alternative 1|

Taihe a an Suichuan Fuziling~ Mashuang FeFnggarig [ternative 11| alternative I alte[ ative I alternative 11 alternative 11 alternative It I I I I ~ ~ ~I ~ ~~~II o

The preliminarydesign alignmenthas been optimizedfor 9 sectionsin total, the optimized length is about 40km.

FigureD-1 Alignment Selection Procedure of Taihe-Ganzhou Expressway

west Ganjiang were compared in the respect of engineering and environmental protection (as shown in table D-1). Table D-1 Three scheme comparison in pre-feasibility study Scheme I Scheme11 SchemetII 1. Occupymore farmland. targe I Occupyless farmland. small quantities of I largestquantities of land quantitiesof resettlement land acquisitionand resettlement acquisitionand resettlement 2 far wva%from highwa%105, less 2 shorimileage to Jinggangshan,good to 2. Adjustmentis requiredfor the interruptionduring construction tourismdevelopment airportprogram-ed by Ganzhou Efviron 3. alleviate the pollution along the 3. close to highway 105, so much interruption municipality comparison highway 105 in constructionphase, and increasethe air 3. Beneficialto the development 4.good to Wa' an and Suichuan pollutionand noise whichprovide model etTect to counties.conformitv kvith the local 5. not in line withthe localgovemment and east Ganjiang govemmentand public opinion publicopinion

9 Scheme III is not as good as other two alternatives no matter in terms of engineering and environment. Scheme II is put forward in comparison with scheme III in farmland occupation, however it arouse many other environmentaland social problems. Scheme I is most superior in engineering though not perfect in environmentalaspects, but no severe environmental impact. Therefore,Alternative I is recommended.

(©) In the feasibility study phase, alternatives are compared and optimized in 6 partial sections (as shown in table D-2). TableD-2 Comparisonsand selectionof the sectionalalternatives

Section tine Advantagesand disadvantages Recommendedby environmentalfactor

I. shorter mileage, and lessland occupation, The tvo alternatives have no obvious 2. some impact on Taihe airport. 3km further away from Taihe difference and no big irreversible Taihe county urban areacomparing with altemative 11. Section I. lessbridge and interchangesand lessresettlement: enironmental changes.Considering the 11 2 3km shorter to TaihecoUnty Lurban area comparing to altemative l local governmentalong wvith the public 3 more land and paddyland occupation opinions,alternative 11 is recommended I shorter mileage,and occupYless land, l 2 no interrupted ba Guanmingreservoire and Luotangming Posser After comparison of enivironmental Wanr an station factors.alternative I is obviouslx superior Section I high level.vertical indicators than altemative 11 thereforealtemative I 11 2 more protectionand bridge %orks is recommended 3 close to GLianmingreservoire and Luotanemine Povwerstation lo.over cost. 2. longer tlais schemietI but enigineering vork is less thall Altematixe I thoLigh has large

S.IiChUan altematise 11. quantities of resettlement. but superior Stichlan 3 construction conditions is better than alternative II. than alternatis e 11 in other ens ironmental

Ih igh cost. factors therefore alternativ e I is It 2. difficult construction vork v%ith large quiantities, recommended 3 geological conditions is not so good as altemativ e 1.

I lower cost. 2 greater resettlement svork Altematie 11 is obviously superior

Fulzi in I high cost than altemative I. therefobre alterative i FLIZimln 1 2 more difFicult in tuinnel constrtiction, higher maintenance cost in .

operatson period, is recortisietided 3 shorter than that of alternative I

I less paddy land occuipation though more land occtipation: There is no big environmental changes 1 2 greater resettlement work: 3 one more viaduct with great vork amount. among the tow altematives, but Mlashuang I shorter mileage usith one viaduct less, altemative 11 is superior than alternative

2 more protection wvork amount. 1 so altemative 11is recommended. I short connection line. I 2 more land occupation. There is no big environmental changes 3 large rescttlement. among the tow alternai\ es. but eniggang I slhort mileage but long connection line: alternative 11 is stiperior than alternative

11 2 great amount of protection \\ork. 1 so alternative ll is recommended 3 more paddy land occupation

) Partial alignment optimization has been done among 9 sections in construction design phase with a total distance of 40krn, equivalent to 30 percent of the total mileage of the main line. According to the survey, there are no major environmental factors among the 9 optimized sections (as shown in table D-3).

10 Table D-3 Optimization of environmental factors after 9 partial Section adjustment

Section no. Origin-end stakeNo. after Changesof environmental factors adjustment

I K148+600-K 153+160 I. Thenegative impact of land occupationand resettlement difficult will increase 2. Impacton thesensitive locations has no change

ll K 161+400- K168+800 I. Reduce the negative impact of land occupationand resettlement difficult 2. Increasethe Impact on the sensitive locations

III K 177+500 -- K185+900 I. Reducethe negative impact of landoccupation 2. Reducethe negative impact on thesensitive locations I. Thenegative impact of landoccupation and resettlement difficult will increase RI K196+500 K201+400 2. Longitudinalgradient reduced, alleviate the vehicle tail gasexhaust 3. Impacton thesensitive locations reduced I. Reducethe negative impact of landoccupation V K204+638-K207+200 2. Soilerosion reduced 3. Increasethe Impact on the sensitivelocations

%I K209+720-K211+620 1. Increaseethe negative impact of landoccupation as well as resettlementdifficult 2. Reducethe negative impact on thesensitive locations

s'Vil K217+600- K221+300 I. Reducethe negative impact of landoccupation and resettlement ditficult 2. Impacton thesensitive locations has no big change

Vol K263+000- K270+000 I . Reducethe negative impact of landoccupation and resettlement difficult 2. Reducethe impact on the sensitivelocations. avoid one school

IX K273+000- K276+000 I Increaseethe negative impact of land occupation 2. Stight increasc of the negative impact on the sensitive locations

The Ganzhou connecting road designed 2 proposals to match the main line Fenggang proposal; the Wan' an connecting road designed 2 proposals aiming at the Ganjiang river bridge. The current proposals are determined from the viewpoint of reduced land acquisition and resettlement, diversion from schools and residences as well as other engineering, environmental and social considerations.

(2) Personal Interconnection Road construction will separate villages, causing some inconvenience to people' s traveling and farming. For this, the proposed highway has designed 53 grade separations and 328 passageways. In addition, the project will build a number of large, medium or small bridges to meet the traveling requirements of local people and vehicles. The Wan' an connecting road intends to build a huge bridge to meet people' s travelling demand crossing the river. (3) Soil Erosion Aimed at the current soil erosion of the project area, and road construction will produce new erosion, so prevention measures are required. The main measures are: transit and rationalization of earth and stone works, road planting design, planting arbor, bush, grass and climbing vegetation on slopes, skeleton turfing, face wall and mortar pitching. Subgrade protection works will be designed such as intercepting ditch, side ditch, face wall, berm, retaining wall and grid fence. Cut sections are designed with drainage works. The above measures also apply to the three connecting

11 roads and the RIP roads as well. (4) Reduction of Land Acquisition The selection of earth borrowing and waste disposal areas for this project adheres to the principle of "local borrowing and reclaiming land", so as to be economical and reduce land occupation. The earth borrowing sites are mostly located in barren hills, the waste disposal sites are in barren hills or sterile fields. Partial sections of the main line lies at hilly area with more cut than fill, so there will be a waste disposal of 2,081,171m3. The main line has 26 earth borrowing sites and 20 waste disposal sites. The Wan, an and Ganzhou connecting roads have more cut than fill, while the Suichuan connecting road has more fill than cut. Their earth borrowing and waste disposal areas will be selected by the above principle. The RIP road Suichuang- Chezi' ao has more fill than cut; the rest three roads have more cut than fill.

(5) Land Acquisition and Resettlement In selection of alignment, efforts have been made to divert from villages and fertilc farmlands so to minimize removal and land occupation. The quantities of the land acquisition and resettlement are presented in Table D-4. The project owner has established resettlement offices at city, county and village level to ensure completion of resettlement before the contractorsenter into the site. Refer to RAP for details. Table D-4 The Quantities of the Land Acquisition and Resettlement 2 Name of the roads Land acquired (niu) Remo%ed buildings (m ) Taihe-Ganzhou Expresswvay main line 11.218.8 129.335.0 Wan' an connecting road 649.6 7.068.6 Suichuang connecting road 818.4 25.549.5 Ganzhou connecting road 721.2 9.803.1 RRIPI: Suichiuan-Chezi' ao 765.97 27,086.88 RRIP2: Yutian-Xinjiang 606.26 10M548.3 RRIP3: Shashibu-Wangmodu 601.5 8,379.6 RRIP4: Tangjiang-Dongshanzhen 461.76 21.294 (6) Noise Pollution According to forecasting, the schools and residences and other sensitive locations along the road during operation stage will be impacted by traffic noise to various extent, so noise mitigation measures will be taken and be incorporatedinto the design and tendering documents. As optimization has been done for most of the sensitive locations, the rest schools hospitals won, t be impacted by the project. The mitigation measures for both the main line and the connecting roads are presented in Table D-5 , which will be implementedprior to the operation of the roads. The noise mitigation measures for the RIP roads are presented in Table D-6. In addition to the noise mitigation measures taken for the above sensitive

12 locations with large noise excess, monitoring will be enhanced for other sensitive locations with small noise excess, and suitable measures will be taken according to the monitored results. TableD-5 The mitigationmeasures for the main line and the connectingroads Name of the roads Mitigation measures Location Work Remark Quantities Mashuang middle school, Qiubian primary school, Kangfueun, Nakang Skin Sound barrier Disease Treatment clinic, 1480m Nitangeun, Zihecun, Pang' aneun, Dayingli, etc Taihe-Ganzhou Expresswav Removal Main Line Daping Olds' Home required by road Resettlement Zhuhu primarv school wborks

villagc residents 56 households

Install soundproof village residents 2o3 windolws households Suichuang connecting road Simple sound barrier Zhangtangprimary school 150mx2.5m Wan' an connecting road Simple sound barrier Tianbei 150mx2.5m Ganzhou connecting road Simple sound barrier Heshanxia I 50mx2.5m

Table D-6 Mitigation Measures for the RIP Roads Name of the roads Mitigation Location Work Remark measures Quantities Install soundproof RIPI: windo\s Nanjiang hospital 60 m- Suichuan-Cheziao Zhutian hospital. youdian 360 hope school. 7uoan high school Removal A two-floor teaching building of the RIP2: Removal Hengling Central primary school Yutian-Xinjiang Buildwall Shangwu primary school, Xiniiang 140m- middle school RIP3: Install soundproof Bushangcun,Wumudu 100 m2 Shashibu-Wangmodu wvindows Install soundproof Tangiang town. Shangping. 145 m RIP4: windows Laowvuchang.Laoshuzui. Tiantou Tangjiang-Dongshan Build \wall fluangsha middle school 30 m2

(7) Atmospheric Pollution According to forecasting, the NOx and CO concentration at all sensitive locations along the main line, its three connecting roads and the RIP roads meet class II standard during operation stage. Under bad climate, the NOx concentration at Fanwvu and Zihecun may exceed the standard. The auto emission pollution will be controlled by improving auto emission technique, enhancing tail gas inspection and reducing NOx and other exhaust. The living facility of road service area is set up 1OOm beyond road center and the road management station is set up 200m beyond the interchange. To prevent impacts on residences and schools by stone quarries, earth borrowing and waste disposal sites,

13 stabilizing earth and bitumen mixing plants, the above sites are located to divert from residences and schools. (8) Water Pollution In designing, each road encompasses and builds sufficient permanent and temporary drainage systems, such as to rebuild ponds and canals so as to minimize surface water pollution and interference with existing irrigation and drainage system. In the Suichuan and Ganzhou service areas of the main line, sewage treatment facilities will be installed, sewage must be treated before discharging. The pavement drainage ditch for large bridges is designed by the historical max. rainfall. (9) Cultural Relics Protection The Jiangxi Provincial Cultural Relics Archeological Institute were entrusted to make cultural relics investigation along the roads, which shows that the main line, its three connecting roads and the four RIP roads are all far away from the discovered relics. (10) Flood Control The project has designed complete drainage system for subgrade and pavement as well as enough bridges and culverts. For example, the main line has designed 9 huge and large bridges, 22 small bridges and 10 middle bridges as well as 382 culverts. Their design flood frequency is one big flood in 300 years for large bridge and 100 years for medium and small bridges. The design flood frequency for the three connecting roads is one big flood in 100 years for huge bridge and 50 years for middle and small bridges. Also there are a number of passageways. These works can meet flood requirement for safe discharging.

27 Construction stage (1) Ambient Air Pollution The major pollution sources during construction stage come from the dust produced from stabilizing earth mixing, construction machines. road building machines. Bitumen and concrete mixing and the paving can also produce a small amount of bituminous smoke. The following measures will be taken: a. The stabilized soil and bitumen mixing plants would be set up at the leeward side 300m away from the sensitive locations of residences, hospitals and schools. The mixing plant would be equipped with sealing device, shock absorber and dust remover. Labor protection measures would be provided to the operators of the construction machine such as eye mask and mouth mask. b. Bulk construction materials transported by truck would be covered to prevent spillage as much as possible. c. Hauling roads and construction site, particularly the stabilized soil mixing plant, would be sprayed from time to time to prevent secondary dust flying.

14 d. In the process of subgrade filling, spraying would be made according to the need of compaction. After the compaction, the contractor would spray the compacted ground from time to time to prevent flying dust. e. The storage of the bulk construction materials would be covered and over 300m away from the school and village sensitive locations

(2) Noise Pollution Noise during construction stage mainly comes from construction machines and hauling vehicles. Strong noise, if persistently imposed on human body, can induce various diseases and noise deafness. The following measures will be taken: a. When the construction site is close to school, no construction work with heavy noise machines would be arranged at school time; when the construction site is close to densely populated residence, construction work with strong noise machines would not be arranged at nighttime (22:00-6:00). b. To use construction machines with low noise level as much as possible. For construction machines with high noise level, temporary sound barrier would be adopted to mitigate the noise impact. The construction materials storage site and the mixing plant would be set at places 300m away from the acoustic sensitive locations. c. The construction operator' s work time would be arranged in accordancewith the labor hygiene standard, and personal protection measures such as wearing ear- plugs and helmets,etc. would be provided to the operators. d. The excess roads for the highway construction would be selected away from such sensitive locations as schools, residences and hospitals. When dense residences exist 50m within excess road, transportation of building materials is forbidden in such excess road at night. e. If the transportation of building materials does make the acoustic environmentof residences along the existing national highway (105) deteriorating, supervisory engineer is required to enhance noise monitoring. Monitoring points have been set up at places as: For main line, Gaopo town of Wan' an county, Jigongduancun of Shaokou township, Quanjiang of Suichuang county, Luowencun of Jinshi township, Changshengcunof Fenggang town, Bazicun of Mushuang town; For wan' an connecting road, Xiaketang; For Suichuan connecting road, Naxi of Taihe; For Ganzhou connectingroad. lingzinao. If necessary, the hauling route may be considered for a change or some economic compensation may be made to local residents.

15 (3) Protection of Ecological Resources a. To enhance workers, awareness of environmentalprotection of natural resources and not to damagewild life and not to cut trees. b. Sewage and garbage from construction camp shall be collectively treated or made into family fertilizers. c. Earth borrowing and waste disposal shall be conducted strictly in accordance with design requirementsso to well protect and to restore the surrounding envirornment. The top soil (30cm) of the acquired land shall be kept for reclaiming and compensation. d. Construction vehicles shall run in excess roads, not in agricultural fields and woodlands. The above measures will be specified in the contracts to be sighed with the contractors. In case of offence, penalty shall be given to the contractors.

(4) Water Conservation To prevent soil erosion during construction stage, the following measures are required: a. Engineering measures (0 To reduce the area and number of construction sites as much as possible; construction shall be carried out in designed site, the earth borrowing and waste arca would not be enlargedcasually so to reduce the exposed area of cutting. Don' t enter the site so earlier if construction is not ready. 02 For road sections with deep cutting/filling (such as the section of K192+900- K199+660.547. K221+000'-K260+000), the engineering measures such as earth retaining wall, protection wall, concrete anchoring would be taken combined with side slope grass planting to make it stable and to prevent sliding. Terrace would be arranged for deep cutting section; interceptingditch shall be set 5m away from the top of the cut to discharge the run-off from the top surface of the side slope. ( When it is raining, sand bag or straw mat may be used to cover the slope surface to reduce soil erosion; and cutting would be avoided in rainy season. 40 As required by the design, water drainage ditch and intercepting ditch would be built for the earth borrowing sites to reduce rainfall eroding force; surface of the earth borrowing site would be flat as much as possible. If the borrowing is to be made from a site with big slope, check dam and sediment control dam would be built together with proper drainage system.

b. Planting measures O Planting works would be carried out in accordance with the planting design.

16 The turf selected for the slope protection when planting and covering vegetation on the slopes in a lump would have the following features: fast growing and fully covering the ground surface; strong bonding force with the soil to prevent surface soil erosion; perennial plant in harnony with the environment. © To get the best effect, the side slope plantation would be completed one month in advance to the rainy season. c. Land Reclaiming (: Reclaiming and planting measures would be taken after completion of the borrowing and waste sites to prevent soil erosion by rainfall. ( Forestation or agriculture reclaiming will be considered respectively based on the location (whether in hilly or farmland areas) of the waste areas. ( As required by the local needs, the deep cutting areas may be built into reservoir or fishpond; and some waste sites may be used for resettlement or industrial buildings.

(5) Water Pollution Prevention a. Septic tank and garbage tank would be provided by the contractor at the construction camp and shall clean the wastes in time. b. Sand sendimenting tank shall be set up in construction site near river or reservoir to prevent mud from directly entering into water body.

(6) Construction Camp a. Septic tank and garbage tank shall be set up at construction camp, which are to be cleared by the contractor periodically so to prevent outbreak of disease. Drinking water that complies with hygiene standard shall be provided at the site. b. Contractors must adhere to labor protection regulations to provide helmets, earplugs and periodic physical examination to workers. c. the construction camp shall be staffed with a full-time health worker who provides medical treatment and give periodic hygienic education to the construction workers.

(7) Cultural Relics During construction, if underground cultural relics are found, then construction would stop and the supervisory engineer will protect the site, and concerned department will be notified to handle it.

17 (8) Transportation Management Plan a. To ensure a smooth operation of the expressway, construction excess roads must be set up at the intersection of the expressway and other existing roads, which would be generally located at one side of the original road and built into subgrade after the interchange is completed. b.Traffilc and transportation management over the National Highway 105 would be enhanced. Passing time will be limited such as to avoid transporting building materials at rush hours. Also contractors are required to make a good transportation plan. c. Materials will be prepared in advance. Sand and stone will be stored at less traffic time. d. Local public security and transportation management departments shall be well coordinated with to mobilize traffic jam and to handle traffic accident so as to ensure a smooth running. e. Contractors are required to make measures to cover the bulky materials so as to prevent spill and leakage in transportation.

(9) Accident risk To ensure safety. the excess roads shall be installed with lighting devices and safety marks, and traffic laws and regulation shall be strictly enforced.

(10) Public Participation Complaint telephone number for environmental complains would be conspicuously marked at the construction camp. For complaint problems, the owner and the contractors shall contact the local environmental department and solve such problem within 48 hours.

28 Operation stage (1) Traffic Noise Control a. To strengthen highway transportation and maintenance. Vehicles that make noise over the limit standards are prohibited to run on the highway. b.According to the predicted results, sensitive locations with excessive noise level will be protected by sound barriers, resettlement, and installation of soundproof windows. c. Construction planning department is suggested not to plan schools and hospitals within 200m from the road center for the main road, 100m for the connecting roads and 40m for the four RIP roads, nor plan residences within 150m from the road center for the main road, 50m for the connecting roads and 20m for the four

18 RIP roads. d. For households with non-excessive but increasing noise, due to their relatively long distances to the road (generally over 60m), so the existing noise reduction effect is not good. By consulting with and agreed by the households that may possibly be affected, noise monitoring will be enhanced during operation stage to decide whether to remove, to install sound-proofing windows or to give economic compensation according to the monitored results. e. Noise monitoring plan will be implemented to decide supplementary acoustic environmental protection measures according to the monitored results.

(2) Ambient Air Pollution control a. Inspection shall be given at the highway entrance to those vehicles hauling bulky materials such as coal. cement, sand and stone, and easily packaged fertilizers and pesticides. Vehicles hauling the above materials would be covered. b. Tunnel fans would be maintained to ensure good ventilation within the tunnels. c. Planting would be set up at both sides of the road, which is good to absorb the flying dust and to protect the ambient air quality. d. Ambient air monitoring plan would be implemented to decide supplementary environmental protection measures according to the monitored results. (3) Ecological Restoration and Watcr Conservation a. Maintenance shall be continued for the planting areas as side slope, central belt, interchange, service area so as to recover the vegetation, to protect the subgrade, and to reduce soil erosion. b. The culverts would be cleared in time to ensure a smooth running of water in the irrigation system. c. Further improve the soil & water conservation works, planting works, and land reclaiming works according to design requirements. A combination of grass, flowers, bushes, and arbors may be used to form a stereo planting pattem. In the later operation stage, planting would be prompt so as to protect the subgrade stability and to reduce soil erosion.

(4) Water Pollution Control a. The sewage treatment facility at the service area would be maintained so as to ensure the sewage meet the discharging standard. b. Execute the water- quality- monitoring plan and supplementary environmental protection measures will be taken according to monitored results.

(5) Transportation of Hazardous Substances

19 a. Declaration system is enforced for vehicles transporting hazardous substance. Drivers need to fill a declaration form, including certificate number of the carrier, code of the hazardous cargo, names of consignor and consignee, loading and unloading place, characters of the cargo, etc. b. At the entrance and exit of the expressway, the driver' s three licenses would be inspected, and the route bill would be accepted. After safety inspection, the cargo is allowed to go. c. Usually the hazardous cargo transport is arranged at off peak hours (12:30-15:00). When the weather condition is bad, it is not allowed to be on road. d. At the entrance of the expressway, the Safe Driving guideline for Gan-Yue Expressway will be distributed to drivers, which prepared by traffic safety experts, includes emergency handling, safety committee, s address and telephone. e. The declaration and inspection of vehicles transporting hazardous substance at the expressway entrance are to be made by the tollgate charger. Relevant persons will be trained on the management, declaration, safety inspection, work procedure and firefighting, which will be incorporated into the training plan. fi When the vehicles loaded with hazardous cargo as blasting cap. dynamite, etc. will pass through the tunnel, the toll station staff shall notify in time the staff in the tunnel who shall send specific person to escort the vehicle (s) passing through the tunnel.

E. Environmental Monitoring

29. In order to ascertain the accuracy of EIA and to take remedial measures in time, we prepared the environmental monitoring plan. According to the plan, the environmental supervising engineer will conduct construction noise monitoring; other monitoring work will be undertaken by local monitoring stations entrusted by the project owner. The monitoring plan refers to Annex II.

F. Environmental Management Organization

30. The environmental management will be organized by the Planning Division of Jianxi Provincial Communications Department (JPCD), and will be implemented by the Project Office of JPCD which has set up an Environmental Protection Section. Each supervising station will be staffed with one supervising engineer. The organizations of the environmental management and supervision for the main line and the inter-connecting roads are shown in Fig.F-l Fig.F-3.

20 Planning Division, JPCD (6 persons)

Project Office of JPCD

EnvironmentalProtection Section (4persons) of Project Office, JPCD

es gner Environmental Contractor Provincial Protection Supervision (over I person ) Environmental Engineer (9 persons) Monitoring Cente

| Jian EMS || Ganzhou EMS| Note EMS refers to Environ. MonitoringStation

Fig. F-I Environ. management organ. for main line and connecting roads in construction period

Planing Division of JPCD (6 persons)

Jiangxi Provincial High-Class Highway Administration (JPHCHA)

Environmental Protection Section of JPHCHA (4persons)

Environmental staff of Environ.staff of Environmentalstaff of Taihe Manaage-ment Wan an Manage-mnent Ganzhou Management Agency (Iperson) Agericy (I person) Agency (Iperson)

Fig. F-2 Environ. management organ. for mainline and connecting roads in operation phase

SEPA EPO of MOC World Bank

JPEPl JPCD

LocalEPB |- Entrusted Unit JPHCHA

Ji' an EMS Ganzhou EMS

Figure F-3 Environ. supervision organ. for mainline and connecting roads

The environmental management and supervision organizations for RRIP during construction and operation stages are shown in Fig. F-4 - Fig.F-6.

21 Planing Division of Jiangxi Provincial Communication Department (6 persons)

Jiangxi Provincial ExpresswaysAdministration Bureau

Project Office, Suichuan County TransportationBureau (RRIPI. RRIP2) or Ganzhou Municipal TransportationBureau (RRIP3. RRIP4)(3-6 persons)

DesignerI | | Environmental Contractor' s Environ. liangxi Provincial Construction Personnel (I person) Environ. Monitoring Inspectors Central Station

Jian Prefecture EnvironmentalMonitoring Station(RRIPI.RRIP2) Ganzhou Niunicipal Environm[iienitalMonitoring Station (RRIP3.RRIP4)

Fig.F-4 Environmental Management Organization for RRIP in Construction Stage

Planing Division of Jian2xi Provincial Communication Department(6 persons)

Jiangxi Provincial Expresswa\s Administration Bureau

Jiangxi Provincial Express,sa nImestment & Development. Co.Ltd,(3 persons)

Suichuan County Transportation Bureau (RRIPI. RRIP2) orGanzhou Mlunicipal Transportation Bureau (RRIP3. RRIP4)(Iperson)

Fig.F-5 Environmental Management Organization for RRIP in Operation Stage

Jiangxi Provincial Environmental Protection Bureau (JPEPB)

JiI an Municipal Environmental Protection Bureaui (JMIEPB) for RRtPI. RRIP2 Ganzhou Municipal Environmental Protection Bureau (GMEPB) for RRIp3. RRIP2

Suichuan County Environmental Protection Bureau for RRIPI.RRIP2 Zhang Gong and Gan Counts Environmental Protection Bureau for RRIP3 Nankang Municipal and Environmental Protection Bureau for RRIP

Fig.F-6 Organization of Environmental Supervision for RRIP

JPEPB, JMEPB and GMEPB are obliged to supervise the implementation of the EAP and in accordance with the laws and regulations. The supervising plan refer to Annex III.

22 G. Ability Development and Environmental Protection Training Plan

31. To enhance the organizational management ability for this project, a training plan has been worked out (see Table G-1).

Table G-1 EnvironmentalTraining Plan for main line

No.N. personnelTraining Training content Time Place Size cs(RMB Remarks

State regulations and standards, the Environmental main environmentalissues of this 2 months before the 20 persons I supervision project the responsibilities of construction Nanchang for a period 10 00 engineer supervision engineer, use of noise of 15 davs monitor instrument. etc. Environmental Share the overseas advancc Within six months to Executedin 2Emanvrmental experience in environmental 12 months after the O persons for Executin personnagele management and apply to this commencement of half month strtheing project the construction State regulations and standards and the main environmental issues, Within I months Training Environmental environmental points to be b content and 3 wvorkstaff of mentioned in construction and before the Nanchang 0 persons 10 00 cost Contractors actions to be taken. the construction for IS das incorporated responsibilities of environmental commencement separately stafT member Statc regulations and rules All persons concerning the transport of from toll Incorporated Inspectors of hazardous subjects. basic 4 hiazardous kinowledgeabout hazardous Within 2 months Nanchanm stations. 7 00 into the normal subjects tranisport sutbjects, vehicle application before its opcration _tunel operational procedure. emergency plan and fire dava lfightknowxledge Total 42 56

The training for the connecting roads and the RIP roads will be conducted along with that for the main line project. The total cost for training is 655.600 yuan; of which, 425,600 yuan is for the main line, 30,000 yuan is for the connecting roads; 200.000 yuan is for the RIP roads.

H. Public Consultation and Information Release 32. In order to fully comprehend the public opinions and to really protect the interests of influenced people, the concerned departments of construction, design, resettlement and environmental assessment unit have made four public participation surveys and consultation on Dec. 10-15, 1999, April 12-20, 2000, and May 18-June 5, 2000 and Nov. 20-28,2000 respectively. The latest (the fourth on Nov. 20-28,2000) public survey was carried out for those impacted by the optimized alignment (40km) in the construction design for the recommended scheme. The survey places are cities, counties and townships along the proposed line. The public participation survey was carried out in three different forms:(l)Family or individual interview; (2) group interview; (3) discuss meetings attended by governmental and non-governmental organizations For the main line, the survey involved 586 persons (based on the family), 75 villages/towns, 12 organizations. For the three connecting roads, seven group

23 interviews have been conducted, involving 178 families and three discussing meetings have held for governrnental and non-governmental organizations. For the four RIP roads, five group interviews have been carried out . The public survey contents include: 0 Introduction of the necessity, construction scale, technical standard and the basic principles of the alignment selection for the proposed expressway . ® Environmental assessment unit explain to the public the major environmental issues and the protection measures to be taken. () Introduction of the state policies on the compensation for the highway land acquisition, removal and resettlement, etc. (®) To understand the publics, opinions about the environmental impact brought by the expressway construction, their suggestions for mitigation measures as well as their requirements. The public participation results are summarized in Annex V. The public' s opinions are summarized as follows: (1) Hope the proposed expressway be completed and open to traffic as early as possible (2) The directly impacted people along the line are mainly farmers, therefore, after the land acquisition; timely adjustment for arable land is necessary. Meanwhile, the land compensation fee shall be drawn down to the village and paid to the impacted households in full amount, no reduction. (3) As to the negative impacts as dust, tail gas and traffic noise, mitigation measures such as planting, removal, resettlement, soundproof measures, etc. shall be taken into consideration. (4) The owner shall keep close contact during the project design and construction phase. proper number of culverts, bridges and passageways shall be set up .

33. Full consultation and exchange have been rmade with the local governrments, relevant departments. village committee, collectives and individuals in respect of alignment selection, setting of interchange and connecting roads, environmental protection and resettlement. Therefore this project has received wide support from the public. The World Bank Loan Project office of JPCD released the bulletin concerning the environmental and resettlement in Nanchang Evening. Jingangshan Daily and Ganzhou DailY dated Oct.10-11 (Refer to Annex VI). The Owner has put all environmental documents in the Reference Room and the Resettlement Offices of the concerned cities and counties for the availability of public consulting. Rclevant information will be released in the above-mentioned newspapers in the future. The owner has taken the public opinions into full consideration in the project design, such as a special lane for farming-vehicle will be set up on one side of the Shangyoujiang bridge, and one interchange will be set up for each of the counties, a number of alternative schemes has be taken for comparison and selection. After the alignment optimization. Wuling school is 100m further away from the road center line (nowI80m in total), Mashuang school is 20m further away from the road center line (now 40 in total).

24 As to the possible environmental issues arising from this project, the assessment and design units have proposed corresponding protection measures as shown in Table D-5 and Table D-6, which have been agreed by the influenced people. During its preliminary preparation and design, full consultation and exchange have been made with local governments, social associations and the public; and the public opinions have been fully exemplified in the selection of alignment, setting of interchange and connecting roads, environmental protection and resettlement. Therefore this project has received wide support from the public.

I. Resettlement

34. The design of the project has always emphasized the principle of diversion from villages, towns and few removal and land occupation. Hierarchical resettlement offices were set up, and RAP was formulated, and the Jiangxi Normal University City and Population Institute was hired as an independent supervisor. Details refer to the RAP.

35. The reallocation of land and the reform of the original arable lands shall China related policies. The Village committee will allocate the residential lot for house building. The land and resettlement compensation fee can be used to develop agriculture, industry, commerce and other servicing. Villagers' life and production shall be well settled.

J. Conclusions

36. After the implementation of the environmental protection measures specified in the EAP, adverse impacts can be minimized to an acceptable level or eliminated. so it won' t produce significant, irreversible environmental damage.

37. With cooperation from relics department, this project has made investigation for relics. During construction, national law on relics will be enforced. So, this project will not damage cultural relics.

38. The risk for hazardous substance transportation of this project is not big, and will not exert important impact on flood control along the road.

39. Removal, land occupation and resettlement will be settled locally, so will not result in large number of farmers rushing into city.

25 40. The project will not impact wildlife; it is beneficial to tourism development and utilization along the road.

41. The proposed expressway involves an investment of 14.96082 million yuan for environmental protection, accounting for 0.42 percent of the total. Wan' an connecting road costs 854.700 yuan, accounting for 0.74 percent of the total. Ganzhou connecting road costs 777,000 yuan, accounting for 0.75 percent of the total. The environmental benefit is larger than its loss. The adverse impacts produced by the project development are acceptable to the environment.

42. In order to finalize each environmental protection work, a special environmental protection organization was established which will be gradually perfected through ability development and training.

43. The environmental action plan (EAP), environmental monitoring plan and resettlement action plan (RAP) have been worked out and will be implemented as part of the project.

26 Annex I: EAP Factors for Taihe-GanzhouExpressway, Wan' an, Suichuan, Ganzhou connectingRoads and the RIP Roads Environment Environmentalprotection action taken or to be taken Organization Organ in issues for action charge* A. Design stage 1. Route The alignment is selected on the basis of 3 overall programs and Design unit, JPCD selection further comparison under 6 sectional alternatives to minimize the environmental and social impacts, and to avoid poor geological condition and cultural relics 2. Partition 328 passage ways have been designed for the convenience of local Design unit JPCD people 3. Soil erosion - at proper road area and slope, plant shrubs, grass and build earth retaining wall, intercept ditch, mortar pitching to prevent soil erosion. Design unit JPCD -design permanent drainage system replace the impacted irrigation pond by re-excavation so as to minimize the impact on irrigation system -protection works have been designed for the 26 earth borrowing and 20 waste areas. 4. Dust/air in addition to the item I mentioned above, places as earth Design unit JPCD pollution borrowving.wvaste banks. stabilizing earth & asphalt mixing plants are identified to take into consideration of the dust impact on the residential quarters. cultural and education areas. 5. Water sewNagetreatment facility is designed in service area for the pre- Design unit JPCD pollution treatment before being discharged into public water body: 6. Noise in addition to the item I mentioned above. enough measure as Design unit JPCD resettlement. sound barrier etc. are confirmed and incorporated into the design and tender document 7. Cultural survey has been made, so far no cultural relics have been discovered: JPCRAI JPCRB relics 8. Flood & - enough design has been done for the bridges and culverts so as to Design unit JPCD meet the needs of flood discharge ( large bridges are designed for I frequency/ 300 years and I frequency/ 100years for others) 9 Hazardous- Design drainage sNstem. formulate emergency plan to prevent from Design unit JPCD goods transport the impact on water source resulted from the hazardous subjects transport accidents. B. Construction stage 1. Dust/Air - sprinkle water during construction. in particular at places as pollution stabilizing earth mixing . asphalt concrete mixing plants and temporary roads. While filling subgrade. sprinkling is necessary for materials impacting. after that, sprinkling periodically to prevent dusting -wNarehouseand materials bank vards shall be properly covered unless for prompt use - hauling vehicles shall also be covered properly to reduce spillover WBLPO - proper arrangement of stabilizing earth mixing, asphalt concrete mixing plants at least 300m leewardthe residential areas. - mixing equipment shall be wNellsealed. the vibrating facilities shall be equipped wNithdust remover, and the workers shall take care of protection. JPCD - JiangmiProrince ConttmnicationDeparztment JPHCHA - Jangwi ProvincialHigh-Class Highwnay .Administration ii BLPO-The oibrldBank LoanProject Office of JPCD JPCRB-Jiangxi CulturalRelics Bureau JPCRAI-Jiangxi ProvincialCultural Relics ArchaeologicalInstitute

(To be continued)

27 The Key Factors in the EAP Environment Environmentalprotection action taken or to be taken Organ for Organ in issues action charge* 2. Soil erosion, - Plant trees and grass at proper road area and slope, in particular stone water pollution walls and grass are necessary at high fillingand deep cutting slopes. - timely restoration of damaged drainage & irrigation system and ponds if damaged. -lime shall be piled together and fenced with bricks or earth, awva) from water source. JPHCHA -when building permanent drainage system, temporary WBLPO irrigation .drainage and culvert shall be built. -take necessarv action to prevent earth -stone from blocking river path or existing irrigation and drainage system --take all rational measures to prevent direct discharge of wastes into water body. 3. Labor camp - garbage tank & septic tank would be provided in the labor camp. periodic treatment and cleaning: CPIICIIA -drinking water would meet the national drinking water standard Contractor WBLPO - give sanitary education periodicallv to the construction workers 4. Noise - abide by the industrial noise standard, to protect workers from noise pollution impact: wnorkersclose to high noise shall wvearearplugs and helmet. limiting the working time - stop machine work at night when there is resident area xvithin150m form 22:00 to 6:00 next morning: JPHCHA - strengthen maintenance ot xchicles & machine to minimize noise Contractor level: - mobile noise barrier are necessar\ for schools at dax timc construction when it exerts impact: - no night hauling wehenthere is large resident areas wNithin50m from excess road. 5. Ecological - earth borroNwing. materials stacking and temporary camp are not environment allowzed in wood land area: protection - to avoid earth borro%Ning on farm land. if it has to do so. the surface soil (30cm) wvould be set aside and to be put back when the borrowing JPHCHA is finished to minimize negative impact: Contractor JCBLPO - strengthening education and training of the workers to be conscious of protection of wvildlife and natural resources. hunting is prohibited: - working vehicles shall run on hauling road to avoid damage on farm land and vegetation. 6. Accident risk - lighting & safety sign for temporary road. implementation of traffic rule: - safety and warning measures for quarry explosion area and strict managcment of the explosives according to the rules of the PSB w-ith proper time schedule for the explosion. JPHCHA -careful check before blastin- c Contractor ~~~~~~~W'BLPO -set up a safety watcher to prevent people and vehicles passing by' before the blasting is over. Blasting is not allowed at peak hours to avoid traffic jam and inJury - the use and management of blasting materials wvillfollow the security rcquirements of the Ministry of Public Security

JPCD - Jang.x Prov ince Comm ein,cation Departmene JPHCH.- Jangxi Prov incial High-Class HighnmAd.ndmimstra,ion

IVBLPO The obr-ldBank Loan Projecr Office of JPCD JPCRB -Jiangxi CnItural Relics Btiureazu

JPCRAI-Jiangxi Pros inciat Cultural Relics Archaeological Institute

(To be continued)

28 The Key Factors in the EAP Environment Environmentalprotection action taken or to be taken Organization Organ in charge* issues for action - in case any relics to be discovered, it would be reported immediately to the cultural relics protection Contractor, JPCRB 7. Cultural relics departmentand the construction would stop and not CRAI JPHCHA proceed until proper treatment having been done by JPCRAI WBLPO the archaeologicalprofessionals; - use the local materials as much as possible to avoid 8. Traffic and long-distancetransport, in particularly, the earth & transport stone work. management - in cooperation with the local communications & Contractor JPHCHA public security bureau (PSB) to guide the traffic to WBLPO prevent traffic congestion; - to build temporary road for highway interchanges; - Preparation for materials in less traffic season (Jan./Feb. and Sept./Oct.) -make a proper materials transport plan to avoid the peak hour of the existing traffic road. C. Operation stage - prefecture or municipal communication I.Risk of danger- administration shall set up an organization to ous materials coordinate the harmful chemicals transportation Local Communication spillover - harmful chemicals transport requires three bureaus. Public Security certificates (Permission certificate. driving license JPHCH & Fire Fighting and escort certificate) issued by MOC. All the Administration concerned vehicles have an uniform sign in LEPB accordancewvith the regulation of the MOC. JPI-ICHA vehicles with hazardous goods shall followx the designated route by public security. transport management agency and fire fighting department. park in designated place: -Registration system will be applied to the transport of hazardouscargo for this project - in case there is any dangerous goods spillage. report to conceriled departmenits and wNorkout an emergencyplane and handle it promptly. - to strengthen vehicle noise and tail gas check. 2. Vehicle vehicles not meeting the requirements shall not be management allowNedon expresswva%: JPHCH JPHCH - strengthen education and publicity of environmental protection to reduce vehicle emission pollutants and relevant regulations: - check of trucks loaded wvithbulk materials at the entrance of expresswav. such as coal. cement. sand. simple package fertilizer, agricultural chemicals. to prevent spillage on road. In accordance with the monitoring results. noise JPHCH JPHCH 3. Noise barriers and other mitigation measures shall be taken for the noise interrupted locations 4. Drainage Periodical cleaning of the drainage system to JPHCH JPHCH system ensures functioningof the system

No more new buildings allownedon the road side Land 5. Others area within00rm: no schools/ hospitals are allowNed aur Land authority wxithin 200m D Environmental Refer to Annex 11:Ensvironmental monitoring plan monitoring JPCD - Jiangxi Protince CominimnicationDepartmenit JPHCHA - Jangpi ProvincialHigh-Class HighmpavAdministration

I VBLPO- 7he Ior/d Balk LoanProject Office ofjJPCD JPCRB-Jiang.vi Ciilti, -al Relics Buro-eau

JPCRAI-JiangxiProvincial CulturalRelics Archaeological Institute

29 Annex 11 Environmental Monitoring Plan Environment Environmentalprotection action takenor to be taken Organ tbr Organ in issues action charge* (I) Constructionperiod I Ambient air a. Monitored item: TSP, bitumen smoke b. Monitoring frequency: once/weekor random c. Monitoring time: one day Environment d. Monitoring sites: stabilizing earth mixing plant, residentialquarters, schools LEMS Supervision close to unpavedhauling road, bitumen concretemixingplant Company (2) Operationperiod (ESC) a. Monitored item: NOx (CO for tunnels) JPHCH b. Monitoring frequency: once/year(wvinter) c. Monitoring time: 1 -2 days. 24 hours continuousmonitoring d. Monitoring sites Yanggongshantunnel, Fanwu, Zihecun

2 Noise (I ) Monitoring frequency a. Constructionperiod once/month,& any time when necessary b. Operationperiod: 4 times / year c. Timesmonitoring twice / dar (2) Monitoring sitc a.Construction period construction sites where there are sensitive spots and residential quaners v,ithin 1O0m of the main line. connecting roads and the RIP roads. National highwaN 105, access roads. Gaopo town of Wan' an countv.JigonEduancun of ShaokoLItovnship. Quanjiang of Environ- Suichuang countr, Luo%sencunof Jinshi township. Changshengcun of mental [SC Fcnggang town. Bazicun of Ntashuiangtonship. Wan, an Xiaketanig. Supervision JPHCHA Taihe Nanxi . GanzhouLaoziling Engineer b Operationperiod: JPHCHA Main line Mashuang school. Wuling middle school. QlLibian primarvschool Kangfucin. Pijiazhou. Laoju. FlUangzhangduan Qiaotou Pang, an. ZhangwsL.Huangshanit Fanghenegi.Jiezishimia. Fengxingpai. Zihecun Shanzixia. Fangwu. Qiubian Wals aniconiiectinig road. Yuanbei.Tianibet. LiuJiLacin Suichuanconnectingroad:Dongtang. Mcijiang.XitoUcun GanzhoLuconnecting road Shangxinrtang.Sheqiancun. Heshanria. Lingzilao

RIP roocds SuichLuan-Chezi'ao Huangao.Youdian FIlopeschool. Zhutian hospitaletc Yutian-Xinjiang Yutian. Hengling centerprimar\ school.Xinjiang high school. etc Shashibu-Wangmodu Shashibu.Xirxing%sei. Wangmudu, etc Tangjiang-Dongshan:Taneiiang. Shanaping. HLiangshahigh school. Beitian primar school. etc

3. Waterqual it (I ) Constructionperiod a. Monitoreditem pH. CODcr. SS.oil b. Monitoring freqUency accordingto the requirementsin constructionphase c. Monitoring time: one das d Monitoring site , 100m up-stream of SUiichuanjiang,ShangyouJiang Ganjiang LEMS ESC (Wan' an connecting road) bridge site and 200m down streamof the bridge site JPHCHA (2) Operationperiod a Monitoreditem pH. CODcr. SS.oil

b. Monitoring frequency 2 times \ ecar. c Monitoring time 2 da\s d. Monitoring site , Ses\aueoutlet of SuichLianand GanZhouser ice areas S0mdossn stream of Suichuan.Ganzhou (connecting road) riner bridge site

JPHCHA -Jangxi Provincial High-Class Highsavr Administration JPCD - Jiangxi Province Communication Depanment

ESC-Environmental supernisionCorp. LEMS-Local Environmentalmonitoring station

30 Annex III: EnvironmentalSupervision Plan Stage Agency Work content Purpose 1. Review TOR 1. Guarantee a complete environmental and Feasibility SEPA appropriate assessment, and subject Feasibility SEPA identification,emphasize the key points. study JPEPB 2. Review EIA 2. Make sure it reflects the possible. significant World Bank potential problems which might be produced by this project 3. Review EAP draft 3. Guarantee a concrete practicable action plan of mitigationmeasures World Bank I.Review the preliminary design of 1. Strictiv execute three simultaneousness and environmental protection and EAP EAP SEPA 2.Check if the EP investment in 2. Secure sufficient EP investment in place JPEPB place 3.1nspect the appropriateness of 3. Ascertain these sites in compliance with material yard. and lime-earth environment protection requirements mixing site JPEPB 4..Inspect dust and noise pollution 4. Minimize the environmental impacts by Local EPB control, decide on constniction time construction, enforce applicable regulations and laws governing environmental protection 5. Inspect the pilling and 5. Minimize the impacts on surrounding loading/unloading of hazardous environment by construction. enforce applicable Design substances. inspect whether the regulations and lawxs governing environmental And discharge of atmospheric pollutants protection construction meet the requirements 6.1nspect the discharge and 6. Guarantee the surface and underground w%ater stage treatment of daily sewNa2eand waste uncontaminated machine oil in construction site 7.Reclaim and handle earth 7. Guarantee the landscape and land resources borrowvingsites and waste disposing not seriously damaged sitcs JPEPB 8.1nspect the "three 8. Guarantee the 'three simultaneousness" simultaneousness" of EP facilities. finalize the completion date 9.1nspect whether the environment 9.Certitf the environmental protection facilities SEPA protection facilities meet standard JPEPB 10. Check underground cultural 10. To protect the cultural relics JPCRB relics I. Inspect the implementation o I.To ensure the requirements stated in the EAP in EAP in operation stage place JPEPB 2. Verify the implementation o 2. To ensure the contents in the mnonitoringplan monitoring plan in place 3. Verify the necessity to take 3. Protect the environment. minimize the ftirther measures for unforeseen environmental impact during construction and environmental problem operation phase 4.lnspect wvhetherthe environmental 4. Enforce environment management. safeguard quality of sensitive location meet people health relevant standard Operation JPEPB 5. Inspect wvhether the sewage in 5.Guarantee the sewage disposal meet the Local EPB living and servicine areas meet standard stage discharging standard in service areas 6. Inspect w%hetherpanement runoff 6.to guarantee the drinking wvatersource free discharged into drinking water from being polluted. JPEPB . . . 7. Eliminatc accidental risks. avoid accidental .EP. 7. Intensifv supervision over spill of hazardous substances Public unexpected accidents to eliminate Security risk. Set forth in advance an and Fire emergency handling program so as Fighting to eliminate leakage of dangerous Dertmentsubstances in case it happens Departm______ent ______3

31 Annex IV: Table 1 List of Environmental Investment Project Name Investment(10,000 Yuan) Percentageof total invest (%) Schedule

Taihe-Ganzhouexpressway main line 1496 082 0 42 2001-2004

Ganzhouconnecting road 77.70 0.75 2001-2003

Suichuanconnecting road 72 56 0 74 2002-2004

Wan' anconnecting road 85 67 0 83 2001-2004

RIPI: Suichuan-Chezi ao 331.55 3.32 2003-2005

RIP2 Yutian-Xinjiang 373 26 3 92 2001-2003

RIP3 Shashibu-Wangmodu 160.36 1 67 2001-2003

RIP4: Tangjiang-Dongshan 194.02 2 38 2001-2003

Total 2791 202 Table2 Cost of environmentalprotection for the main line

No. Protection measure Mieasure description Quantity lJnit cost Cost (10.000 Remarks ______Yuan____ ) I Planting and vegetation Plantitig in the earth borrow%ing 46 places ;0 000 230 0 recoxcry sites and 'sasteareas 2 Soundbarrier Acoustic protection for 1480m 1800/m 266 4 MashuangHigh School etc. Removaland resettlementfor 56 families i, 1680 RemoNaland acoustic cns ironmental 3 resettlemenit protection Dapingolds hiome 100.000 I cintr 100 ZhLhulschool 40 0 400 4 Installation of Protection ofacoustic 2_3 famlics5 00 126.5 soundproofssindo%ss environment 111an7/1ami k Environ protection and Septic tank.garbage tank %%illbe 40-000 S managementdUring setLip in construction camp 9 bid sections Itonunbid 36 0 constructionstage Operatorsworking securics section 6 Se\\age treatmcnt Se\sagetreatment in the ser ice 8 places 4O0.060 320.0 faciliytt areasand parking lots t ian/place 7 CLiltural relics protection Sutrve and exca%aenon 120 0 8 En%ironmental Completionof environmental 480 IncludingRoad 105 monitoring monitoring plan and temporarr road 9 Training for EP Seethe EP training plan 42 56

Fire extinguishersin the tunnel 66 groupstotaling 150 1 9 10 Equipment procurement 132extinguishers Y 0ioneach 9 Hand automaticnoise monitor yuan/eachy

Yellow board for careful dri%ing. 1000 I I Sign board red board for speedlimit and 54 Uan/each 5 4 blue board for remindine 12 Conttingencs 5/o of the aboue total 71 242

13 Total 1496.082 Table3 Cost of environmentalprotection for the Ganzhouconnecting road No. Protectionmeasure Contents Quantit) Unit price Cost(10O000vIan)

I Planting Plantingon 5 ssastesites 5 places 25 0

2 Environ protection cost staterspra\. hNinggarbage disposal cloth- 4 months 10.000 during constr stage co ering of hauling vehicles Slagdisposal. zi an/month 240 imuddelivers and treatment Ensironmental Noise. TSP in construction 3 sears 25.00D-vtion/vear 60 monitoring Noise. Nox in operation 3 years I 0.00 uan/vear 3 0

4 Sound barrier Heshanxia(K4+630) I Om 1.000Otanim 15.0

5 EP training Participatein training ofthe main line 2 persons I 0

6 Contingency 5%of the above 3.70

Total 77 70

32 Table 4 Cost of environmental protection for the Suichuan connecting road No. Protectionmeasure Contents Quantity Unit Cost ( Cost

1 Planting Planting of earth borrow 56.25 mu 4,000 yuan /mu 22 5 Water spraying, wastes 2 Environ, protection cost and sewage treatment, 3 years 50,000yuaniyear 15.0 during construction vehicle cover during construction: Environ Monitoring TSP,noise, water quality 2 years 20,000 yuan/year 60 during operation: Noise, 3 years 20,000 yuan/vear 6 0 ambient air, vater quality .

4 school place Make sign board 6 places 1.000yuan/place 0.6 a Sound barrier building Zhangtangschool 150m 1 200vuanim 18.0 during operationphase 6 Training Training tor environ0 managementpersonnel 2 persons 7 Contingencs (5%) 3.46

Total 72.56

Table 5 Cost of environmental protection for the Wan' an connecting road

No. Item Content Quantity t'nit price Cost (10.000yuan) I Planting Planting at 3 w\aste areas 4 places 50.000X ianplace 20 0 and one borro ing site Ensiron,. protection cost prysae.lvnpray water. li;viia garbageabge 2 duringon protction cosL disposal, transportation 36 months I 0,000 yuan /month 36.0 tnicks tarpaulin etc 3 Sound barrier Tianbei (K5 300) 150m I 000/m I; O Construction phase: 4Environmental noise, TSP, waterquality 3 Near 20.000nLian/,vear 6 0 Monitoring Operatioii phasc: noise, 3 Xcar I0.u000 san/%Iear 3.0 air, xater qUalirty 5 Warnint board Remindinizdrivers of 4 pieces 1.000ipiece 0 4 securit% 6 Environment protection Participating in training 2 persons training the main line 7 Contingency 5 %, of the above 4.07

Total 85.47

Table 6 Cost of environmental protection for For the RRIP1

No Items Amount Unit Price Total | 1 0000 yuan) Nt I Side slope Greeningand GradeCrossing 79 Okm 20.000yuan/km 158 Beauttlication 2 ConstmrctionMonitoring 3 Years 15000yuian /year 4.S

Operation Moniitoring 3 Years 10000yuan year 3

HIeihtening oflEncirclementor ImplemenraiionDep 4 InstallationofNoiseIsolation Window 4210 m 200 yuani'm 84.2 endingon the actual monitoring Installation of simple noise isolationi 5 barrier, designedand arrangedin 3GOm- 200 6 combination with the encirclement 6 The Environmental 0 Protection Cost in Construction 7 Reclamationof Temporarily-UsedLand 45

S Plan of EnvironmentalTraining 10 persons

9 Other UnexpectedCost 15.85

10 Total 331.55

33 Table 7 Cost of environmental protection for For the RRIP2

No. Items Amount Unit Price Total Note (10000 yuan) Side slope Greening and Grade Crossing 45.845km 20,000 yuan/km 91.69 Beautifcation 2 Construction 3 Years 10000 yuan 'year 3 Monitoring

3 Operation Monitoring 3 Years 6000 yuan /year I 8 Implementation 4 Heighteningof Encirclementor 101m 20yunm062 Dpdigoth Installation of Noise Isolation Window 10310 m 200 yuan /m 206 2 plmendingonithe Actual Monitoring Installation of simple noise isolation 2 2 5 barrier, designed and arranged in 140m 200 yuan/rn 2.8 combination with the encirclement

6 Environ Protection in Construction 10

7 Reclamation of Temporarily-Used Land 35

8 Plan of Environmental Training 10 persons 5

9 Other Unexpected Cost 17 77

10 Total 373.26

Table 8 Cost of environmental protection for For the RRIP3 No Items Amount Unit Price Total Note 110000 yuan) I Side slope Greening and Grade Crossing 26.251 km 25.000 xuan!km 65 63 Beauti rcation 2 Conistruction Monitoring 2 Years 8000 yuan /ear 1 6

3 Operation Monitoring 3 Years 5000 Luan/hear 1 5

Heir htenine of Ercirclement or Implementabon 4 Installation of Noise Isolation Wlndoss 2200meters 200 Xuan /m 44 Depending on the actualMonitornin The Env ironmental Protection Cost in Construction Reclamation of Temporarilnk-Used 6 Lend _ _ 30 7 Environmental Training 10 persons 5

8 Other UnexpectedCost 7 63

9 Total 160 36

Table 9 Cost of environmental protection for For the RRIP

No Items Amount Unit Price Total Note If'OOOs%uan) I Side slopeGreening and Grade Crossing 28717km i 15000 VLan./km 4308 Beautification

2 Mlonitoring in Constructioti 2 Years 12000 vuan / ear 2 4

3 Monitoring in Operation Stage 3 Years 6000 VUan /vear 1 8

4 tlciihtenine of Encirclement!additional 4625 m 200 925-uan Acual Monitoringg 5 Ens ironinemital Protectioti in Construction I 5

6 Reclamation ofTemporanls-Used Land 35

7 Plan of Enx ironmental Training 10 persons 5

8 Other Unexpected Cost 9 24

9 Total 194.02

34 Annex V: Summaryof the public participation SLurveydate I ocatiOnIol surve) NumbeI ot)Cspontdctnis ltrinoatiotnprovided to thc pIb!Lic ISStICSol public concern Responseto the public concem Yizicunll, Sanjitag, Wuling lligh School, I hope to biild the proposed expressway as 1. To expeditepreliminary work and to start Iblagnlh1tCaIIInSheShangCU1a. SleSh1t11ig I tIBrilang iOl the proposed project, sooI1as possible, and agree wvith the proposedconstructioi asearly as possible; Primnary School, Sliaoxiccin & primary 48 persoiis(based tn inctudinlg its necessity, ztligilineit environitieital protectiol measures; 2. Setup detailed RAP; 10/12/1999 schlool, Meipantgsianig,ZbhagtallgCUll & hlitlilics), anid alliglningprilacipIe, coinstruction 2. Follow the govenimnentpolicy for land 3. Auxiliary bridge to be set at the two sides Zhanlgta'igprimary school, I viillages/towntships, scale,aiid technicali tidicators, compeonsationand resettleineit, of the Shangyoujianig bridge to solve Iloigshliatian & I lotigshianiprimary scilool, 511tiits 2 Scttiag-up tit coicctinig roads. 3 Solittioni to the traveliig of local people people s crossingover the river; l15/12/1999 Lianggttltgcuil, 3aitia,Quanj iiiigzilcig , etc. isterciaLtiges,pttssages; livittg ott the batiks ol Shangyolnjiang river 4. Irallic safety etc. has been takeln itito 3 Possiblepositive impactsbrought by coticeriiedby Sanjiangtowniship govemrnment; account in the designdocument. the priposed project, stCIc as 4 To avoid Wuliig higlt school improvcd trantisportcotiditiotis and 5 TrafTicsafcty. NitatgcUlt, llUaltgZhlIalgdIltllcLllt,ZhUhUcUll, ecoI)oI11tcdevelopmenit, atid nlegitive I Wish to build the expressway as soon as I . To expeditepreliminary work and to start Kattgsitcti.ii Nankang derma. clinic, itpacts stici as land acquisitionand possible to help peoplebecome rich, construction as early as possible; YizititancLItI, WVc1hcctlil, M3tveicUn1,3 17 persons(based oi resettletieait,trillic iloise and etc.; 2 Follow lte govenmmetntpolicy for latid 2. Set tip detailed RAP; 12/A)4/2tl()1) Baijiacullt ziatgtltngCutl, ShtttxicuLII.tIt1il ies), 4. PIroposedIlsitigtltiOttll tsIcsres to coinpetisatioi antdresettlement, 3. To make thte alignment further away Xitottctii, SlictoCitAtiI, D)ingkouciun, 18villtges/towliships, reduce the negative ilpact, SuICtias 3. Keep the original passages, agree the from Mashuanghigh school in next design; Masulitanig Itigi schiool, Beitatlgctti, 7 itliits resettlement, installatioti of soulid proposalsIlorenivironimental protection; 4. Passageways,traltic safety issues have 20/04/200t0 SlShaigxicuLII,ZlesitancLIFI, Neichaoxiang, barriers, sound prool vitildows, 4 Ithe road shoLildbe 20-S50m firther away beenconsidered in the design documents; Xiawsanctll, etc. greeniing,atid compensatioi ol lland west froin Mashuatighigh schlool; 5. Sound barrier, planting design to be atcqltisititotn,reclaimiritig, etc., 5 Tratlic safety done. S Outtomcs fromii co01slUtatoll nWitll Zhiunl(lcLIII,JingshicItItt XiaWnIcttIn (JieZi), local goveritutteiits I. lo build the expresswayas soonas possible; I. To expeditepreliminiary work and to start Xini anilil, ItilgcLlat, Xiaoyuan, 2 Itollowv the goveniineit policy for land construction as early as possible; Dapitgxiang, L.UOtangcL11i, NUhuctCIl, compentsationanid resettlemeit, hope resettled 2. Setup detailed RAP; QianohualngCLIII, Q1ilgiiatgcUn, locally attd provided with land for housing; 3. Passageways, irrigationi system 18/05/200()( Zhongpenigctin, GaobeiciLti, Zengkerigctirt,1 26 peismtis(bascd till 3 Protectioti of irrigationi system to prevent protectiotn and soil conservation, etc. have _ BIazicUn, DollgpaicuL11, Mashuangcun,tibmili ies), soil erosion; been taken into account in the design 05/06/21100 Etfltgcttl, itliafengctn, l.otxiacUll, 26 villages/tosvns, 4 More passages or at least retention of document; TianxiniCtU, Yizictlli, AoliaLInl, origital passagew,ayand culverts, 4. Sound barrier, planting design to be Zongininxiazi, Dapitgctiti, Slutiditictut 5 Employmenitof those who lose farm land; done. 6 Soundproff lecilities, agree the proposed tlleaislres. ZhOlIgNltcunII, 'litttsXittlil, .litingHiitt, I li build the cxprcsssvayas soot as possible; I . After the alignmnenitoptimization, Wulitug M'cnxiatngciut, Raoji,lpocuit I.ibitIcLIFt, 2. hloperesettled localtlyand provided with land school is lOOm and MashUtangschool is LAontgltigitlt, NiliucaIII Nittngcut., tforhouising; 20m further away from the road center 1 5/11i/20(1( (iaosshatttctitt, Xiictitictiin itaopo town, persots (btsed oit tle 33. Se tilp)ofIore passagewaysaitd culverts line. - .1igolngdiuaictticn, Quttajniangg, Luowenilckl, family), 20 villstges 4. Rebuild the irrigatioil tacilities for the section 3. Set up detailed RAP; 25/11/2()00) Chlingshiengcun, liazicuLII, XiawarctLI,I wherefarmland are acquired 4. Sound barrier,planting design to be done. Zhtltucuri-,.Xin ancun 5. Pay great attentiojnto the noise pollution in 6. Enhance the noise monitoring on the colistuictiotl phase highway 105and accessroad .

35t Summary of the statistics of the public participation survey* No Survey content Optional answers Percentage Remarks Yes 92.08% 0 Do vou support the constructionof the No 1.02 /o 3 highway No idea 3.5% No answer 2.21%- State 96.03%

Who will be benefited from the Collectives 58.13% more than 2 highway' Private person 55.47% one choice

No answer 0.81%/-

Some of the farmlands are going to be No 77.30% occupied and some households to be Yes 8 93% resettled, do you ha; e any comments No idea 10.10% on the laind occupation' No answver -4.29%

Yes 12.37% Do Xyou know%the compensation pol icy for K l . ~~~~~~~~~~a litle ~ ~~Know31.9%/ 4 land acquisition and Do not knowv 47 47%/ Resettlement" No anss er 1 6%- Yes 62.98%0 Do you follo%%the land acquisition and Yes, but conditionjally 33 41% resettlement arrangement' No 0 61%- No answer -2 59% Noise 60 61% Vehicle tail gas 27.2% more than Which is the most serioLs impact on you 6 Dusts 41 3 I % onechoice arising from the highssa cornstruction' Other 2.940/0 No ansNer 5 42 Planting 76.570/% Sound barrier 20.80% more than 7 Suggestioits tbr mtitigation measuires' Aw%asfrom villa2e 11 82% one choice Other -1 9%D No anstser -10 66%o Note the figures in the table are derised from the statistics data ofthe main huieproject. three connecting roads and the four RIP roads.

36 Annex VI:

The People' s Republic of China Environmental and Resettlement Bulletin for the Jiangxi No.2 Highway Project

For the environment and resettlement information of the Jiangxi No.2 Highway Project to be inquired by the public, increasing the openness of the work, the TGEPCO has placed the following complete reports respectively in the resettlement offices and libraries of Nanchang city, Ji' an city, Ganzhou City, Taihe county, Suichuan county, Wan' an county, Nankang city, in Sep.10, 2000.

(1) Resettlement Action Plan for the Taihe-Ganzhou Expressway of the Jiangxi No. 2 HighwayProjectfinanced by the World Bank, Tanhe-Ganzhou Expressway Project Construction Office (TGEPCO); (2) Environmental Action Plan for the Taihe-GanZhou Expressway of the Jiangxi No. 2 HighwayProject financed by the World Bank, Tanhe-Ganzhou Expressway Project Construction Office (TGEPCO); (3) Environmental Action Plan for the Ganzhou Connecting Road of the Jiangxi NVo.2 Highway Project (Taihe-Ganzhou Highway) financed by the WVorld Bank, TGEPCO: (4) Environmentacl Action Plan for the Suichuan Connecting Road of the Jiangxi No. 2 Road Project(Taihe-Ganzhou Highway) financed by the World Bank, TGEPCO; (5) Environmental Action Plan for the Wan ' an Connecting Road of the Jiangxi iVo. 2 Highway Project(Taihe-Ganzhou Highway) financed by the World Bank, TGEPCO. Dec.2000

The above reports will be modified according to the suggestion of World Bank delegation and public, and then be placed in the above resettlement office and libraries.

Tanhe-Ganzhou Expressway Project Construction Office (TGEPCO) Sep.22, 2000

37 Annex VII: Environmental Standard Limits

Table 1 GB3095-1996 Ambient Air Quality Standard (Abstract)

Pollutant Sampling time Concentration Limit mg m3 Class I Class 11 Class IlI TSP Daily average 0.12 0.30 0.50 NOx Daily average 0.10 0.10 0.15 One hour average 0.15 0.15 0.30

CO Daily average 4.00 4.00 6.00 One hour average 10.00 10.00 20.00

Table 2 GB16297-1996 Air Pollution Comprehensive Discharging Standard (Abstract) Pollutant Production techniology Maximumallowable limit Concentration limit for . mg/rm unorganizeddischarge Bitumen smoke Asphalt melting. mixing 40 75 Conspicuousunorranized . discharge is not allo%\ed

Table 3 GB12523-90 Standard of Noise Limit for Construction Work Site Noise limit ( dBj Construction phase NMainsources of noise Dav time Night time Earth & stone ccork BulIdozer. excavator. loader. etc. 75 55 Piling Various piling machines 85 WVorkprohibited Structure Concrete mixer. vibrating spear. electric saxN.etc. 70 55 Finishing Crane. lifter. etc. 65 5

Table 4 GB3096 Noise Standard for Urban Areas (Abstract) LAeq:dB Class DaNtimc Nighttime Applicable area Residential quarters. cultural and education areas IV 70 55 Sides of the traffic trunk roads

Table 5 GHZB1-1999 Standard Limits for Ground Water Quality (Abstract) mg/ m3 (except pH

Indicator Class Class I Class 11 Class Ill Class IV Class V PH 6.5-8.5 6-9 COD, Beloa%15 <_I:5 S20 30 S40 Total lead -<0 01 sl0. 03 s<0. 05 <0. 05 s10.1 Petrol-oil -0.05 0. 05 -0. 05 <-. 5 _

Table 6 GB8978-1996 Standard Limits for Sewage Discharge (Abstract) mg/m3 (except pH

Indicator Class Class I Class It Class III PH 6|-9 COD,, S 100 |10 .00 Petrol-oil | 10 20 SS 70 150 400

38 Annex VIII: List of Relevant Reports

(I) Environmental Impact Assessment Report for the Taihe-Ganzhou Expressway of the Jiangxi No. 2 Highway Project financed by the World Bank, Research Institute of Highway of MOC, Dec.2000 (2) Environmental Action Plan for the Taihe-Ganzhou Expressway of the Jiangxi No. 2 HighwayProject financed by the World Bank, Tanhe-Ganzhou Expressway Project ConstructionOffice (TGEPCO), Dec.2000 (3) Environmental Impact Assessment Report for the Ganzhou Connecting Road of the Jiangxi No. 2 Highway Project(Taihe-Ganzhou Highway) financed by the World Bank, Research Institute of Highwayof MOC, Dec.2000 (4) Environmental Action Plan for the Ganzhou Connecting Road of the Jiangxi No. 2 Highway Project (Taihe-Ganzhou lHighway) financed by the World Bank, TGEPCO, Dec.2000 (5) Environmental Impact Assessment Report for the Suiichuan Connecting Road of the Jiangxi No. 2 HIighwvayProject(Taihe-Ganzhou Highwavy)finan7ced by the World Bank, Research Instituteof Highwayof MOC , Dec.2000 (6) Environmental Action Plan for the SaiichzianConnecting Road of the Jiangxi No. 2 Road Project(Taihe-GanzhouiHighwvy) financed by the WhorldBank, TGEPCO. Dec.2000 (7) Environmental Impact Assessment Report for the [an e an Connecting Road of the Jiangxi No. 2 Highway Project(Taihe-Ganzhou Highwayv)financed by the WVorldBank, Research instituteof Highwayof MOC , Dec.2000 (8) Environmental Action Plan for the Win' an Connecting Road of the Jiangxi Vo. 2 Highwayv Project(Taihe-GunnzhouHighway) financed by the World Bank, TGEPCO. Dec.2000 (9) Environmental Impact AssessmnentReport for Suichitan-Chezi , ao road, Jiangxi Provincial EnvironmentalProtection Sciences Institute, Dec.2000 (I O)Environmental linpact Assessment Report for Yittian--Xinjiang road, Jiangxi Provincial EnvironmentalProtection Sciences Institute, Dec.2000 (I ])Environmental Impact Assessment Report for Shatianhu-TK7ngmu1du road, Jiangxi Provincial Environmental Protection Sciences Institute, Dec.2000 (1 2)Environmental Impact Assessment Report for Tangjiang-Dongshanzhen road, Jiangxi Provincial Environmental Protection Sciences Institute, Dec.2000 (13)Environmental Action Plan for RRIP. Jiangxi Provincial Environmental Protection Sciences Institute. Dec.2000 (14)Environnental Assessment Summary for the Taihe-Ganzhout Expresswaay main line, the Connecting Roads and RRIP project of the Jiangxi No. 2 Highway Project financed by the World Bank, Research Institute of Highwayof MOC , Jan.2001

39 a d1er3Rit, t Itte$£imk a1m Figure 1 Geographical position of the proposed road in Jiangxi province

Hubeiprovince Anhuiprovince

/ SI Dean } Vt^'Fj/h

i ongxiuY z s _ J {rovinc

Hu'nan 8 e t} province Gaoan Nanchani \ Hengfeng Shan

Wanzai - QianshQj hanj 'M A*; "XinginV 9 MADFIX - C Yujia N

Pin ionXEinc ra ind

/ 11," Wan'an\ \_ ~~~ ~~/AtcJ JAiEi

Seatof provincial governtnent

ai -Ganz sanzhou connection roauanca

! I roalRtiono.4zj NingNational Ng:3 road

--- ~~~ X . jXinfeng National trunk built

| r /~ --- 3t- tg /l- I - t~~~ Nationaltrunk to bebuilt , 'd u * RIP~~~~~~~~~~~~~~~Noatii a onasll road. province Long heproposedWana

1-. ( s 2 W;_- '.SRoadt mprovemict Provan(RIP) _ _ | ! ~~~~~~~~~~~~~~~~~~~~~Note:rAPNo. I it SoicbuanJvmgg ng3hoo ro*d. ection roa 50km RIPNo.2 ii YunXinj-g rood ShanGano * RIPNo.4 i aadro AI845 -- Nntaf~meium bridg Soshngs iafang separated ei ~ ~ i ong crossing bridge 4150(11 \~~~~~~~~~ V~~~ ~~~ ~~- edium ~~~~~~~~~~~~edcr .... uri~ ~ ustiagb g

43-3M~ ~~ ~ ~ ~ ~ ~ ZuzOIP eium bridgr h ~~ ~ ~ ~ ~

-raih. ~..... ~~~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~~~~~~~~~~~~~~~~atdcosio

5 g X gtan sepa 1 crsep nz~~~~nt-L

1:1000~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~j~~~~0 4R #~~~~~~~~~~~~~~~~~~~~~~~~~~~~~±k #0~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~K 120~~~~~~~~~~~~~~~~~ -r-A~~~~~ 2 2-4)~~~~± ~ ~ I 2 4~~~~±th Jt{~9

K4 14 K 45= K16 K4 14 19 K5 I O 3 14 K3 16 K3 18 K3 10 K4 12 FFFoure-2 The Alignment of the Gan-Yue Expressway (Taihe-,Ganzhou Section) 45 jContinuing igure

kxiaosriam pengy-I Dalongkeng separated cr d -rossIng iterch

ne

sepai

41 AA

W, Q I VOK ial opt

A11A

< 06ik-

c crossing rA Long,li separated crossi an ta d cro rivOunrnedium b ianxi s parate y lbolig 7 pafatcd er gei. se w 7 4* .- 200 va 41E V 74off *ff Of 5 tz-R 44 _ti2: 4w S

ISO ME Z! IN E- *4? 160 tz 11, +I:z 140 '.7 7 X

h -A 1:50000100

1:2000 80

Tianxi FanjiaUan Fanxia Xiaosliantang Zhongyuantaiig 60 Songshubei Dalongkeng Beigaiig JZL EEI StAti T -W A

K16J K162 K10 K164 M5 K16 U617K168 I _j & K151 K12 K1513 K15.4 K1515 K16 K17 K18 K19 K10 ontinuing Figure2 The Alignment of the Gan-Yue Expressway(Taihe-Ganzhou Section) ' W t _-,- g

.t , _T~l?(SA - _ )

Jnxii~~~~~~~~~~~. sepiarated crossing ?l.()( -Ž rA X arated crossing agebrng'/~ . / Caoxia~~~~~~~~sepacrosiatrn V'~~~~~~~~~~~~~~~-'

/ 5A 6ia ii< ilg g E 7 v/ 0A

ui X t g3X '

psramedcK168K17,4 K16,9 K17,5 Kl7p K17,1K176 K17r2 K17,3 K17,7 K17,8 K17,9 K18,0 K18,1 K18,2 K18,3 K18,4araed5

/5 V~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

180

160-

1:50000

1:2000

K183 K184 K185 I <168 K169 K170 K17,1 K172 K173 K14 K7 16 K17.7 K17.8 K1719 K18B0 K181 K182 LContinuingFigure 2 The Alignment of the Gan-Yue Expressway (Taihe-Ganzhou Section) |

aSo - C-l

Daqtlan Gui.Dingdib ZhuhuL 60Kulanglang - Nanpuzhouw Shizaixia

m r . ,md

K,193K19,4 K19,5 K19,6 K197 (1918 (19t9 ______g K28.6 K18,7 K18,8 K1829 K1910 (19,1 K19,2 (Taihe-Ganzhou Section) {ContinuingFigure 2 The Alignment of the Gan-Yue Expressway

, ,Y ,j 260~~~~~~~~~~~~~~~~~~ STA2135, ; Maji11 mediLanSTA203+5405Rg,pbridge '

/ I S" p204+ 35. 00 ,,

240-. /j 22 220-

I:eOOOOe 41J JJIl;}Saichuang ceunt\ X gi akn h Suichuancounty

§ rii Nakuag cit ; : 1- g | ; | g a Jt Wig$ § § 0 g 0 a sK220 K210 K215 | s lt l b ~~~KZ05 Conti.ni.g Figure 2 The Alignment of the Gan-Yue Expressway (Taihe-Ganzhon Section)

eSHAt 0 05bd,~~~~~~~~~~~~~~~~~~~ob,,~ ~ ~ ~ ~ ~~~~ -~~20 0,10 iek Sr~~ A

t ,5 SOhtatn ~~~~ wO ~bgln HlMt5, i~ ~~~~~~~~~

260-~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~2

320-220 1

Dspg~~~~~~~~~~~~~~

M.,h-g hisIn 1:50000 ~~~~~~~~~~~~~~~~~~HOg,M50ag±h-

9 K24 <2 0 1#~*22JI~2 2 K293 K? -4 K2, 5 K2 6 K227 K2g8 K2?9 K230 <231 K232 K233 K234 K3 K36_K237 K238 KP39 K24U K? 11. K2.42 K243 K244 K245 K246 K2,47 K2,48 onfi.uieg Figure22,2 The Alignu,entofthe Gan-Yue Exp-essay (Taihe-Gnziou Setiou)

240 AAApp-f

A~~~~~~~~~~~~~~ *e

'Ea- fm:1:50000 f0 ~ 0 4

~~*IK251 K252 K253 K254 <255 K25L6 <2~57 K258 K259 K260 K2651 K2652 K263 K264 <26S5 K2~66 <267 K268 <269 K270 KE.71 K272 <273 K274 K .275QK26 K2,7 8<7 ri K2LC " - 41t* -ff

Figure 3 Illustrated map of the cultural relics and historical sites along the alignment

Taihe county _ - f / ~~~~~GanxianP LjI-i ~~y MGanzhou city Wan'an county 0 bGanxian county ,

ktAtA |ongxilingn\

(DYaotou FGh, ncto li::.1 4t,XIaba Mash<-' ~ ~ ~~3vFit Wana Taihe-GanzhotuExp:re=ssway| <33AIAqFenggangOPU

/\ N:l Suichun confecong/ line-;tLongling 8t3Mmaymggng S Shaoko . /W/ itDnga X k_-s~ ~ ~ ~ A i /S Jish /1 N ' B,Mji~~~~~~~~~~~~AD Dnglin.i 19 /ijSAngu Nankangcil Y / G GLuotang I// _n 16 17

"gs EELuTtia Yunian - / -~ ~ / -,Sh -i,ESnjiaRN ,BizhouAAhang

| wan'anconectionlin // EOIYane lzt\ ZA IItcA -F'MMhXiahu t Legendwall Hirical city Historical tomb Jinshi I YuDrann r fslsil Note:Thenumberis the serialnumber of thecMuEtu gLutiand site Mhitrac

/ , / \ /- ~~ ~~~~~~~~Suichuan f >g

> ~~~~~Shangyoucounty

Historical biulding A3 Cuilturalrelics

Legend 21 Historicalcity wall U4 Historical tomb tl Dinosaurianfossil

RE)$Rr*4-51Wr-iibt@F: IL, to 20km Note:The nurnber is the serial nuniber of the cultural relics and historical sites. Figure 4 Cultural Relics Distribution Map

of Road ImprovementProject (RIP) (to be continued)

Suichuan 1

Zhutian

(^i . _ w § U E;-3XnKengkou

- Z.. 1 Nanjiang

'-. --... jr < Nankangcity

Cheziao < Zuoan / / Cheziao Tanghu /DL

, I Shangyoucounty

LmI Legend tyJ

.. iii- Historicalbuilding

1- 'YA0p Tomb

i i X ALi

of Road Improvement Project (RIP) (to be continued)

Xinjiang

Fuxi

Yaqian Wan'W ancountY

, ~~~~~QuchikengR It,

Suichuancounty IengXtling

Yutian _

LE Legend 1fIJ -r'. R.' Historicalbuilding

-^ l,'Wt- Tomb

_ l QfLiUtJ11: Cultural relics Figure 4 Cultural Relics Distribution Map

of Road Improvement Project (RIP) (to be continued)

Ganzhoucity

* Shashibu

g ! i c8~~~Mashan ,

Nankang city /

*^-' Xikeng

RiP3: Shashibu-Wangmuduroad

1 / ^(3 Wangmudu

1S Legend VI] AL. I-'JA4; Historicalbuilding

Ant r'r-^ Tomb

A r1i }C1LIM11d Cultural relics Figure 4 Cultural Relics Distribution Map

of Road Improvement Project (RIP)

) Longhua \ Shangyoucounty i ( Huangbuj Dongshan 0 lwQaotouwei Tangjiang

RIP4: Tangjiang-Dongshanzhen road Nankang city

/ )

I | Legend 19J Ah.- 'KJ-VI Historical building

-j r- Tomb

i f Ri.I&ICultural relics ganjiang in pre-feasibility study phase Y '~ Figure 5 Alignment schemes of main line in west (to be contitnued) ~

~ ,- ' _

t~~~~~~~~~~~~~ Y-Z~

Chan~~fT Jingt J KaiiwaS

~~~~~~~~~~~4~v

~~~~?SCfJeme jj,~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~, &~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~''

~~~~~~~~~~r~~~~~~~~~~~~~~~~Yn in west ganjiang in pre-feasibility study phas Figure 5: Alignment schemes of main line

:;~~~~~.< IalWI Shangvoujiang - ____ v -arig

-~~~~~~~~~~N s~ k .44,~ - 'olUt" ~ ~ ~ ~ ~ ~

WL17~~~*-> ~ ~~~~~~V ~ ~ ~ ~ ~ ~~~~~~~ - ~~~~~~~~~~~Scbe~~~~~~~~~~~~~~~~~~~"~ ~

'j xI -721~ .