Technical Memorandum

To: Jacques Dean, Kitsap County Public Works

From: Jeff Massie, Otak, Inc.

Copies: File

Date: August 4, 2021

Subject: North Kitsap Service Center Alternative Analysis — DRAFT

Project No.: 33305

Purpose and Need This memorandum provides a project overview, a description of existing site conditions, programming validation, an alternative discussion by discipline and a multi-criteria decision matrix comparing two site plan alternatives, and recommendation of the preferred site alternative. Once Kitsap County has selected the preferred alternative, the Otak team will provide environmental review documentation, permit assistance, and final plans, specifications, and estimates in preparation for construction. Refinements to the preferred site plan will be made throughout the final design phase.

As this memorandum is intended to address the various differences between the two site plan alternatives, it will not cover all technical aspects of the project, leaving that discussion for the forthcoming design report.

Project Overview Otak was selected to provide professional services for the design of a new road maintenance shop on 16 acres of recently purchased undeveloped property located south of NE Rova Road, and east of State Route 307/Bond Road NE, in north Kitsap County (Parcel No. 062602-2-064-2007). The new road maintenance shop will provide administrative offices for three (3) supervisory personnel; crew dispatch, training, locker and washroom areas for thirty (30) operation employees; vehicle maintenance bays; outdoor covered canopy parking for selected maintenance equipment and vehicles; uncovered parking for private vehicles; yard storage areas for maintenance materials; equipment and vehicle wash bay; and a vehicle and equipment fueling station.

A Moderate Risk Waste Facility (MRWF) will also be located on the parcel. It is probable that additional office space for a Sheriff’s Department employee will also be required. It is expected that, where feasible, use of common facilities will be considered.

Collectively, the road maintenance shop and MRWF have been designed as the North Kitsap Service Center for the purpose of improving public outreach communication.

k:\project\33300\33305\projectdocs\site planning\20210801 alternatives analysis tech memo.docx

11241 Willows Road NE, Suite 200 . Redmond, WA 98052 . Phone 425.822.4446 . otak.com North Kitsap Service Center Page 2 of 11 Alternative Analysis — DRAFT August 4, 2021

Most utility services are available to the site including power, water, and cable. Natural gas is not available; neither is sanitary sewer which will require design of an on-site septic system (OSS). Environmentally sensitive areas exist on, or adjacent to the parcel. Of the 16 acres, approximately six (6) acres exist within critical area setbacks.

Kitsap County completed preliminary programming for the project, of which the following building space metrics were determined:

. Administration/Crew Space 4,500 square feet . Vehicle/Equipment Maintenance Bays 14,000 square feet . Covered Canopy Equipment/Vehicle Storage 9,600 square feet . Fueling Station/Vehicle Wash 5,880 square feet . Salt Storage 2,520 square feet . MRWF 3,650 square feet, minimum

Existing Site Conditions The site is generally flat to gently sloping with rolling hills. The topography within the northeast third of the site gradually slopes to an existing drainage channel. A stream channel crosses the site from north to south, beginning at NE Rova Road and extends to the southeastern corner of the site. The remaining site generally slopes towards the south. Ground surface elevation of the site ranges between 220 and 244 feet NAVD88.

The site is heavily vegetated and forested with young to mature conifer that are up to 44-inch diameter at breast height (DBH); young to mature deciduous trees ranging up to 45-inch DBH; and groundcover consisting of ferns, ivy, woody shrubs, and herbaceous ground cover.

Subsurface soil conditions consist of topsoil 1 to 1.5 feet below ground surface (bgs), underlain by weathered and un-weathered Vashon till ranging in depths of 18 to 26.5 feet bgs. There is perched groundwater; static groundwater is near 18 feet bgs.

The site is located in a Type III Limited Area of More Intensive Rural Development (LAMIRD) land use overlay. A Type III LAMIRD is a land use type designated in the comprehensive plan that is an unincorporated commercial and industrial node containing isolated cottage industries and other small businesses. A commercial tree farm and the Arness Septic Pumping business are located south of the subject property. Adjacent properties immediately to the north and east are either developed as rural residential or are undeveloped. The subject property is over 15 acres in size and is currently undeveloped. The property was created through a binding site plan initiated by Arness Tree Farms, the previous owner.

The site is accessed via a driveway from SR 307/Bond Road NE; this driveway currently allows unrestricted turning movements (right/left in and right/left out). A second driveway from NE Gunderson Road is accessed by internal roadways.

Existing stormwater facilities are present adjacent to the site. Two state owned stormwater conveyance pipes run under SR 307/Bond Road NE from the west property line.

k:\project\33300\33305\projectdocs\site planning\20210801 alternatives analysis tech memo.docx North Kitsap Service Center Page 3 of 11 Alternative Analysis — DRAFT August 4, 2021

Programming Validation Otak and stakeholders vetted and verified the preliminary program, space metrics, and plans generated by TCF Architecture of Appendix A. The team reviewed the preliminary programming for the project providing general building space metrics.

The provided program and space allocation matrix was compiled, updated and reviewed. This has been preliminarily reviewed by Jacques Dean at Kitsap County. Some program elements have been removed and consolidated. Refer to Appendix B.

Concerns that the subject facility programming adequately accommodates future service level demands for the road maintenance shop in terms of materials and equipment storage, building space for staff needs, and vehicle and equipment parking are addressed in the memo of Appendix C. Programming the Moderate Risk Waste Facility for current and anticipated waste streams is covered by the July 14, 2021 Final Kitsap County HHW Programming Report prepared by Special Waste Associates.

Building program and site relationships were reviewed, refined and applied through the development of schematic building floor plans and site plans. Site observation and feedback through on-site meetings with the client team and stakeholders have been integrated into the current site and building plan alternatives.

The design team leveraged the findings from field trips to the existing Kitsap County Household Hazardous Waste Facility, Public Works Annex, and South and North Road Maintenance Shops on April 22, 2021; as well as a June 2, 2021 field trip to the Pierce County Central Maintenance Facility (refer to Appendix D). These lessons learned and best management practice ideas are proposed to be integrated into the site plan alternatives and buildings of the North Kitsap Service Center

In March, Otak held a conference call with Keith Swearingen and Jacques Dean to review and coordinate plan elements and reorganize program elements for greater efficiency.

A conference call with Darren Schwend from Notkin a P2S Inc. Company (P2S) and a potential maintenance consultant provided key input to assist the design team with refinement of the proposed maintenance bay to improve functionality.

Floor plans of the Moderate Risk Waste Facility and Road Maintenance Shop were developed based on the preliminary program, program validation, and field trip observations. These floor plans are developed as a first stage of architectural design, and to establish building footprints to use in the site planning process. Opportunities for facility growth and expansion have been incorporated into the floor plan, including flexible meeting and storage rooms and second level MEP spaces that could grow in size internally. The fabrication shop on the end is configured to convert to a heavy maintenance bay if additional growth is required.

Alternatives Description Site plan Alternatives A and B were developed as shown in Figure 1. Alternative A which impacts no critical areas was developed as a baseline to fully understand if there is sufficient room to store materials and maneuver about the site with vehicles and equipment amongst all the required program elements. Significant similarities and differences are summarized in the tables below, and described in further detail in the subsequent Site Planning Discipline Discussion section of this memo.

k:\project\33300\33305\projectdocs\site planning\20210801 alternatives analysis tech memo.docx North Kitsap Service Center Page 4 of 11 Alternative Analysis — DRAFT August 4, 2021

Similarities The Moderate Risk Waste Facility and Administration Building/Maintenance Shop are placed in the southwest and northern margins of the site, respectively, with the same floorplan footprints Avoids impacting Wetland A, the unnamed stream, and their 150-foot buffer

Differences Alternative A Alternative B Wetland C and its 50-foot buffer Avoids impacts Impacts Usable space 10.54 acres outside Wetland A 11.88 acres outside Wetland A, and C, stream, and buffers stream, and buffers Moderate Risk Waste customer Clockwise rotation* Counterclockwise rotation* vehicle approach queuing * These sub-alternatives were developed for discussion purposes; later thinking was a counterclockwise rotation places drivers closer to building and staff

Alternatives Discussion by Discipline Site Planning Common to Both Alternatives A & B The site layout places the Moderate Risk Waste Facility at the south/west corner of the site at the future intersection of the proposed LAMIRD road and Bond Road NE. This will allow the waste facility to be easily viewable and accessed by the public. This facility will be fenced separately and accessed from the adjacent Kitsap Service Center. Residents will queue up in two parallel vehicle lanes and circulate to the waste drop-off area, then exit the facility through the same entrance as their arrival.

The Administration & Crew Building / Vehicle Maintenance Shop is sited at the north end of the site, east of Bond Road NE and south of NE Rova Road. It is anticipated the building creates minimal noise compared with other activities on the site, and is therefore more compatible with residential areas to the north and east. The Administration & Crew portion of the building is located at the center of the site, along with an employee parking area to the south of the building. Additional covered vehicle parking is provided in this central portion of the site as well.

At the central axis of the maintenance facility is the main vehicle circulation route that heads north from the new site entrance at the southeast corner of the site. This alignment provides immediate access to the fueling station and vehicle wash. A traffic circle is located at the center of the site, south of the Administration & Crew Building to allow for vehicles to turn around and exit the site without the need to circulate around the vehicle maintenance shop. Vehicles to be maintained can circulate around the maintenance facility and enter and exit through the maintenance bays.

The bulk materials storage area is located along the eastern margin of the site away from residential areas. This portion of the site has the most activity due to vehicle traffic and noise generated by road maintenance vehicles coming and going from the site. Dump trucks and pups entering the bulk materials area can make a complete U-turn within this area; semi-truck and trailer can exit via the adjacent traffic circle.

The perimeter of the Moderate Risk Waste Facility will be fully fenced along the road frontages and along the 150-foot stream buffer. All vehicle access points will have locking gates.

k:\project\33300\33305\projectdocs\site planning\20210801 alternatives analysis tech memo.docx North Kitsap Service Center Page 5 of 11 Alternative Analysis — DRAFT August 4, 2021

Unique to Alternative A Wetland C Buffer averaging is proposed in this area in which up to 25% of the buffer width can be decreased as long as the net area of buffer is compensated for at other location along the buffer. This wetland provides a significant natural vegetation buffer between the publicly accessed MRWF, and the road maintenance and operations functions.

Unique to Alternative B Alternative B eliminates Wetland C. Corresponding wetland impacts are proposed to be mitigated off site. As a result, this alternative provides more opportunity to expand buildings and site features for future demands.

Site Landscape / Buffers A 20′ landscape buffer is required at the northwest and southern project boundary. For both alternatives, the proposed buffer for the project has been expanded to 40 feet along Bond Road NE and Rova Road, to maintain as many existing trees as possible to aid in the vegetated screening for the project, and to comply with Kitsap County staff input to emulate the look and feel of the Public Works Annex yard located outside Bremerton. This buffer screening will be designed to provide a site barrier where the project abuts adjacent roadways. Existing trees in this area will be supplemented with additional native trees and groundcover per Kitsap County Code requirements. All existing vegetation within the 150′ stream buffer setback is maintained.

Vehicle Maneuverability Autoturn software vehicle path simulations were run for both site plan alternatives for an American Association of State Highway Transportation Officials (AASHTO) WB-67 vehicle, an Interstate Semitrailer (see Figure 2.) Please note that the simulation includes routing to the Moderate Risk Waste Facility loading dock, and through the road maintenance and operations portion of the site. An Autoturn vehicle simulation that matches dump truck and pup trailer is not available, therefore the analysis also includes depicting Kitsap County provided dump truck and pup turn radii to test the space for vehicle maneuverability in the bulk storage area. Vehicle maneuverability appears to be sufficient for both Alternatives A and B.

Buffer averaging is utilized at portions of each site plan alternative to locate the edge of pavement to aid in more efficient vehicle maneuverability and program element arrangement. See the section titled “Environmental and Permitting” for more details on buffer averaging.

Architectural The design team used the preliminary programming documents provided by the County to initiate the design of the facility. After reviews and meetings with consultants, the County, and with internal stakeholder engagement, the current plans were developed and have been evolving as new information comes to light.

Maintenance Building The maintenance building is comprised of three basic parts; road maintenance administrative offices and crew space, Equipment Services Department (ESD) offices, and the ESD maintenance shop (refer to Figure 3). The office portion includes the entry, lobby restroom and locker room. Offices and the training/conference room are on the second floor, along with storage and mechanical/electrical/plumbing (MEP) spaces that can grow in size. The ESD portion has two levels with some open to above space, and

k:\project\33300\33305\projectdocs\site planning\20210801 alternatives analysis tech memo.docx North Kitsap Service Center Page 6 of 11 Alternative Analysis — DRAFT August 4, 2021

the four heavy maintenance bays have double high spaces open to the sawtooth roof form. This provides a north facing roof for light and a south facing roof for solar panels.

Maintenance Building Areas: Level 1: 14,989 sf, Level 2: 4,534 sf – Total: 16,523 sf

Household Waste (HHW) Building (refer to Figure 3) The HHW building provides double high open spaces for sorting and storage, and a two-level volume to accommodate the office and general functions with MEP and storage on the second floor.

The program and functionality of the HHW building was discussed in a meeting with David Nightingale, Rick Gilbert and Darren Schwend, and several adjustments made in plan. Note: as a topic of discussion, the reverse flow of traffic at the moderate waste facility illustrated on the site option B stemmed from a recent comment from a coordination call. This needs to be discussed and studied further to accommodate clear site circulation and adequate queuing.

The sheriff’s office has been proposed to be located in the HHW facility to be grouped with the other public facing building elements at the street. The team would like to confirm the hours of operation and access to the HHW grounds as there may be security.

Household Waste: Level 1: 8,600 sf, Level 2: 1,431 sf – Total 10,031 sf

There are no significant differences between the building plans on the different site options.

Civil Engineering and Utilities Grading The site grading is intended to match the elevations of the proposed LAMIRD road along the south edge of the project area. Otak has contacted the road design engineer, Map Ltd., requesting their vertical datum. Once received, we will apply a datum equation to refine the profile of the project site approach road.

Preliminary grading plans have been developed as shown in Figure 4. Otak is confident the grading for either alternative can be refined and optimized during the 30% design to evaluate cost tradeoffs associated with stormwater conveyance and flow control, retaining walls, and the minimization of imported and exported grading materials.

There is a substantial hill in the northeast portion of the project area that will need to be leveled to accommodate the proposed facilities. This material will be used as fill in existing low areas throughout the site to provide a relatively flat surface throughout. Grading has been designed to encroach on the critical area buffers as little as possible, however using buffer averaging there are some areas where cut and fill slopes can impinge on these buffers (see Environmental and Permitting section for further information on buffer averaging). It is assumed because both grading and retaining walls will be optimized, the anticipated cost estimate is of negligible difference, and is therefore not included in the relative cost estimate of Appendix F.

Both cut and fill retaining walls are proposed on the west side of the site in order to minimize disturbance and maintain the existing wooded buffer along Bond Road NE as much as possible.

Utilities Alternatives A and B are not materially different in the placement of utilities to service the site, so for the purposes of this analysis, they were not evaluated for differences between the two alternatives. k:\project\33300\33305\projectdocs\site planning\20210801 alternatives analysis tech memo.docx North Kitsap Service Center Page 7 of 11 Alternative Analysis — DRAFT August 4, 2021

Stormwater Engineering . Development of the Kitsap County North Road Facility will require compliance with Kitsap County Code, and Minimum Requirements 1 through 9 in the 2021 Kitsap County Stormwater Design Manual and 2019 Ecology Stormwater Management Manual for Western Washington. The minimum requirements will require stormwater facilities to meet the runoff treatment, flow control, and wetlands protection requirements. On-site stormwater management best management practices (BMPs) are required to be evaluated for feasibility. Due to the required space for the County’s operations, there will not be large, forested areas outside of the critical areas on site to allow for full dispersion of runoff without stormwater facilities. Infiltration of stormwater is also considered infeasible due to glacial till soils underlying the project site. Therefore, on-site stormwater management BMPs are considered to be infeasible at the site. . Runoff treatment will be required to include pretreatment, oil control, as well as enhanced runoff treatment facilities due to the intended use of the project site. The recommended types of runoff treatment facilities included limited areas with bioretention with underdrains, and underground biofiltration vaults. The recommended flow control facilities consist of underground detention vaults.

Alternative A consists of approximately 7.8 acres of impervious area, while Alternative B consists of approximately 9.4 acres of impervious area. Alternative A presents a reduction in the amount of new impervious area, and preservation of native vegetation and critical areas to the extent feasible, relative to Alternative B, and therefore Alternative A uses a site planning approach consistent with Low Impact Development (LID) principles. Alternative B would allow the County expanded use of the site but results in additional impervious area and stormwater runoff requiring treatment and detention.

The size, and number of stormwater facilities would vary between Alternatives A and B. Due to the wetland near the middle of the site in Alternative A, potentially separate stormwater facilities could be required for the western and eastern portions of the site. Stormwater pipes may not have adequate slope to drain from the western portion of the site around the wetland to the eastern portion, and therefore, separate enhanced runoff treatment and flow control facilities could be required. For Alternative B, it is assumed that the majority of the runoff will drain to one set of runoff treatment and flow control facilities.

A preliminary analysis of the stormwater facility sizing for Alternatives A and B is documented in the DRAFT Preliminary Stormwater Technical Memorandum, July, 2021. The preliminary sizes for the flow control facilities are based on an assumed live storage depth of approximately five feet of drop from the inlet to outlet of the detention facility.

The live storage depth is constrained by the outfall elevation of approximately 222 feet in elevation at the south side of the site. A minimum finished grade surface of approximately 230 feet in elevation is therefore required for stormwater to drain into catch basins and pipes, and be conveyed through runoff treatment and a detention facility prior to the outfall. Fill from excavated native material or imported material would be required to achieve roughly the 230 feet elevation at the lower end of the site. Options for reducing the required grade over the vault include a lower live storage depth (and increased vault area), or utilizing some space on site for open ponds or stormwater wetlands.

Another alternative to raising the grade with fill would be to evaluate constructing a stormwater trunkline extending off site far enough to connect at a lower elevation, thereby lowering the outfall elevation and allowing the detention vault live storage to operate at a lower elevation. Compliance with critical areas ordinances, potential easement acquisition, and permitting would need to be evaluated as a part of this option for a stormwater trunkline.

k:\project\33300\33305\projectdocs\site planning\20210801 alternatives analysis tech memo.docx North Kitsap Service Center Page 8 of 11 Alternative Analysis — DRAFT August 4, 2021

Table 1 Summary Preliminary Stormwater Facility Data

Alternative A Alternative B Site Plan Site Plan Target Impervious Area (acres) 7.75 acres 9.37 acres Water Quality Flow (cfs) 0.71 cfs 0.86 cfs Preliminary Enhance Runoff Two Enhanced runoff facilities, 12′ x 24′ Treatment Facility 8′ x 24′ biofiltration vault, and Biofiltration Vault 4′ x 12′ biofiltration vault, or stormwater treatment wetland/pond (8pprox.. 12,100 ft2) Detention Facility Total Height (ft) 7 7 Detention Facility Live Storage Height (ft) 5 5 Detention Facility Approximate Interior Two Flow Control Facilities, 40,800 ft2 Length and Width (ft) 27,225 ft2 Detention Vault, and Detention Vault either a 12,100 ft2 Detention Vault, or Stormwater Treatment Wetland and Pond (Approx. 12,100 ft2) Assumed Outlet Pipe Elevation 222′ elevation 222′ elevation (feet NAVD88)

The preliminary cost estimate of the above facilities is of negligible difference, and is therefore not included in the relative cost estimate of Appendix F.

Structural The buildings will be steel framed structures with concrete spread footing foundations; this framing style will provide open space in the garage bays without the need for columns. Foundations will extend approximately two feet below grade to meet frost depth. The floors will be concrete slab on grade, with a thickened slab at the garage bays. The infill walls will be light gauge steel framing members. The lateral force resisting system for both wind and seismic will be steel moment frames and/or tension only cross ties.

The structural systems for both alternatives will be similar to each other and no appreciable cost difference will exist between the structural elements for either option.

Retaining walls in fill areas will utilize gravity walls (rockery or block) for walls less than six feet overall height; taller walls will utilize mechanically stabilized earth walls with block or rockery facing to match the shorter walls. These two wall types are the most economical options for these ranges of wall heights, and provide some flexibility in choosing the final appearance of the wall.

Geotechnical Engineering (contributed by Aspect Consulting) The site conditions are conducive to the grading, structure support, roadways and pavements, and retaining walls proposed by both alternatives. Re-use of the on-site soil for structural fill will require dry weather, careful control of moisture, and likely moisture conditioning (drying). Structures that span areas

k:\project\33300\33305\projectdocs\site planning\20210801 alternatives analysis tech memo.docx North Kitsap Service Center Page 9 of 11 Alternative Analysis — DRAFT August 4, 2021

of cut and fill will require foundation subgrade preparation strategies like fill cushions or over-excavation and replacement to reduce the risk of differential settlement.

Alternative B will require the placement of fill in the Wetland C depression. At the time of construction, clearing and grubbing will need to be performed, and the wetland area soils should be inspected to understand if the over-excavation of unsuitable soils is necessary prior to placing structural fill for the support of overlying pavements and structures. Otherwise, there are no other significant differences between Alternatives A and B from a geotechnical perspective.

Mechanical and Electrical Engineering (contributed by P2S) P2S is responsible for designing the Vehicle Wash and Fuel Station, as well as mechanical/electrical/ communication systems within the Moderate Risk Waste Facility and Administration and Crew Building/Vehicle Maintenance Shop. Therefore, there are no significant advantages from an M/E standpoint of one alternative over another, other than better vehicle maneuverability of Alternative B as addressed in the above “Vehicle Maneuverability” sub-section.

On-site Sewer System (OSS) (contributed by Allied Design) Both alternatives have the Moderate Risk Waste Facility and Administration and Crew Building/Vehicle Maintenance shop in the same locations. It is assumed because of their locations on opposite sides of the site, that it is more cost effective to have separate OSS facilities for each building, and sufficient space exists to place them between the paved areas and the critical area buffers. The final locations and layout will be determined in the subsequent 30% design effort. There are no significant differences between Alternatives A and B from an OSS perspective.

Environmental and Permitting Alternative A largely avoids impacts to Wetland C, streams and associated buffers on site. Minor buffer impacts may require buffer averaging as allowed per Kitsap County Code (KCC) Title 19 (Critical Areas Ordinance). Buffer averaging allows a portion of stream or wetland buffer to be reduced to accommodate site development while expanding other portions of the buffer that result in no net decrease in total buffer area. A critical area tract or similar covenant would need to be filed during the land use approval process to document the amended buffer boundaries in perpetuity. Alternative A maximizes protection of regulated environmental areas, and as such would be expected to have a minimal environmental review and compliance process with Kitsap County Department of Community Development.

Alternative B includes filling Wetland C, a forested wetland centrally located on the property. It is recommended that an Approved Jurisdictional Determination be submitted to the United States Army Corps of Engineers (USACE) to determine if Wetland C is regulated under the federal Clean Water Act (CWA). If Wetland C is regulated under the CWA then impacts to it will require authorization from the USACE, including wetland mitigation. Regardless of whether the USACE does or does not regulate Wetland C, it is regulated under KCC Title 19 and impacts to it will require a variance process and compensatory wetland mitigation per KCC 19.200.230. Off-site mitigation options include the use of a mitigation bank or in-lieu fee program. The Canal Coordinating Council (HCCC) In-Lieu Fee Program has credits available to offset the wetland impacts for the proposed project. In consultation with HCCC staff, cost estimates of these credit purchases vary from $467,968 to $923,968 as shown in the tables below.

k:\project\33300\33305\projectdocs\site planning\20210801 alternatives analysis tech memo.docx North Kitsap Service Center Page 10 of 11 Alternative Analysis — DRAFT August 4, 2021

Table 2: Low Range of Fee-in-lieu Wetland Mitigation Cost Temporal Basic Loss Factor Cost per Impacts Mitigation Req (Concurrent) Acre-Points Acre-Point Cost 0.32 evergreen 1.6 (WQ) 2.5 4 $38k $152.0k forest wetland 0.32 evergreen 1.28 (Hydrologic) 2.5 3.2 $38k $121.6k forest wetland 0.32 evergreen 1.92 (Habitat) 2.5 4.8 $38k $182.4k forest wetland Sub Total $456,000

Land Fee* $11,968

TOTAL $467,968

* Calculated as $37,400 multiplied by the area of impact (0.32 acre). Land Fee is based on the Residential Value in Kitsap County per Interagency Review Team in 2016.

Table 3: High Range of Fee-in-lieu Wetland Mitigation Cost Temporal Impacts Basic Loss Factor Cost per (acre) Mitigation Req (Delayed) Acre-Points Acre-Point Cost 0.32 evergreen 1.6 (WQ) 5 8 $38k $304.0k forest wetland 0.32 evergreen 1.28 (Hydrologic) 5 6.4 $38k $243.2k forest wetland 0.32 evergreen 1.92 (Habitat) 5 9.6 $38k $364.8k forest wetland Sub Total $912,000

Land Fee $11,968

TOTAL $923,968

* Calculated as $37,400 multiplied by the area of impact (0.32 acre). Land Fee is based on the Residential Value in Kitsap County per Interagency Review Team in 2016.

The main cost difference is a result of different temporal loss factors applied to the credit purchase. The HCCC In Lieu Fee Program has identified a wetland restoration site in the Gamble Creek watershed that is near the anticipated project impacts, which makes purchase of the credits highly favorable by regulatory agencies. However, the construction of the HCCC’s restoration site has not begun and currently does not have a construction schedule. If credits are purchased before the HCCC goes to construction, then the mitigation for the impacts to Wetland C on site will be considered “delayed,” and thus have a multiplier of five as shown. If project impacts to Wetland C are “concurrent” with construction of the HCCC wetland restoration site, then fewer credits would have to be purchased and thus a lower wetland mitigation cost. Per personal communication with Patty Munchak at the HCCC In Lieu Fee

k:\project\33300\33305\projectdocs\site planning\20210801 alternatives analysis tech memo.docx North Kitsap Service Center Page 11 of 11 Alternative Analysis — DRAFT August 4, 2021

Program, the HCCC’s Gamble Creek restoration site is planned for construction in the next two years. Approval of the mitigation plan would be required by the federal, state, and local agencies.

Multi-criteria Analysis To assist the Otak team with providing a recommendation, and to aid the County in making a decision on the preferred site alternative, the Multi-criteria Design Matrix of Appendix E was prepared. It summarizes qualitative, and relative cost estimate quantitative, advantages and challenges of each alternative. Refer to the Relative Cost Estimate of Appendix F for the estimate range shown in the cost criteria in the matrix.

Recommendation Otak recommends Alternative A. Now that the program elements have been validated, the critical areas confirmed, the site planning has been performed to place program elements and perform vehicle wheelpath simulation modelling to test vehicle maneuverability, it appears that Alternative A has no apparent significant flaws, and has distinct cost, environmental, and community support advantages.

k:\project\33300\33305\projectdocs\site planning\20210801 alternatives analysis tech memo.docx Appendices . Appendix A Preliminary Programming Report, 2016 by TCF Architects

. Appendix B Programming Validation, June 18, 2021 by Otak, Inc.

. Appendix C Expected Kitsap County Population Growth and Transportation Facilities Demand Memo, August 1, 2021 by Otak, Inc.

. Appendix D  Existing HHWC and Road Maintenance Facilities and North Kitsap Service Center, April 22, 2021 Field Trip Notes, Otak, Inc.  Pierce County Central Maintenance Facility, June 2, 2021 Field Trip Summary, Otak, Inc.  Field Investigation Summary, June 2, 2021 by Notkin a P2S Inc. Company

. Appendix E Multi-criteria Decision Matrix, August 3, 2021 by Otak, Inc.

. Appendix F Relative Cost Estimate, August 3, 2021 by Otak, Inc.

Appendix A Preliminary Programming Report, 2016 by TCF Architects

Kitsap County Public Works• Strategic Facilities Plan North Shop Vehicle Parking Analysis

VEHl,'.LEPARKING ANALYSIS L = 12' x40' S= lO'x 20' M=10'x30' XS =8' x8'

Size Heated Covered Asset No Description Department Qty. Rem.irks (L,M,S,XS) M s XS M s XS

North Shop Vehicles and Mobile Equipment 307 Chevrolet P30 STEP VAN TRUCK, SERVICE [T35] ESD 1 5 0 0 1 0 0 0 0 0 3702 Caterpillar 120M2 MOTOR GRADER MOTOR GRADER [M03] Roads Maintenance 1 L 0 0 0 0 1 0 0 0 158· Ford F150 EXTCAB 4X4 PU 1/2T EXT CAB 4X4 [A29] Roads Maintenance 1 s 0 0 0 0 0 0 1 0 159, 180, 3000 Ford F250 REG CAB 4X2 PU 3/4T REG CAB 4X2 A [A31] Roads Maintenance 3 5 0 0 0 0 0 0 3 0 304 Chevrolet K30 PU 3/4T REG CAB 4X2 A [A31) Roads Maintenance 1 M 0 0 0 0 0 0 0 366 Ford F650 VERSALIFT TRUCK, BUCKET (MANLIFT)[T30] Roads Maintenance 1 M 0 0 0 0 0 1 0 0 319 Ford F550 SD 4X4 W/HOOK LOADER TRUCK, HOOK LOADER (LIGHn [T32) Roads Maintenance 1 s 0 0 0 0 0 0 0 3SOO. 5501 IHC 7600SFA Pup Trk W/10-12 DUMP TRUCK, PUP W/10-12YRD DUMP (T34) Roads Maintenance 2 M 0 0 0 0 0 2 0 0 327 GMC TOPKICK C8500 TRUCK, SINGLE AXLE, W/HOOK LOADER Roads Maintenance 1 M 0 0 0 0 0 1 0 0 321 IHC 4400 4X2 W/PB PATCHER TRUCK, SINGLE AXLE, W/PATCHER [T43], Roads Maintenance 1 M 0 0 0 0 0 1 0 0 446,455, 461 IHC 2574 W/10-12 DUMP TRUCK, W/10-12YRD DUMP (T48) Roads Maintenance 3 M 0 3 0 0 0 0 0 0 3501, 3503 IHC 7600SFA Plow Trk W/10-12 DUMP TRUCK, W/10-12YRD DUMP [T48] Roads Maintenance 2 s 0 0 0 0 0 0 2 0 669 IHC 500X TYMCOSWEEPER SWEEPER, TRUCK STREET (509) Roads Maintenance 1 M 0 0 0 0 0 1 0 0 3504 Freightliner 114SD Plow Trk W/10-12 DUMP TRUCK, W/10-12YRD DUMP (T48) Roads Maintenance 1 M 0 0 0 0 0 0 0 3612 Dynapac CC800 Plus, Small Vibrato!)'.Roller ROLLER [ROl) Roads Maintenance 1 XS 0 0 0 0 0 0 0 1 646 Caterpillar C8334E ROLLER ROLLER, STEEL DRUM [R02] Roads Maintenance 1 s 0 0 0 0 0 0 1 0 0319-2/4 Universal Sander SANDER, IRON [S02) Roads Maintenance 2 s 0 0 0 0 0 0 2 0 Cover not required 487 Hi-Way P7 SANDER HYO PWRD 1.5 YD SANDER, IRON [S02) Roads Maintenance 1 s 0 0 0 0 0 0 1 0 Cover not required 0431-2, 0455-2, 0461-2, 3501-3, 350,:.2 Monroe MV-132-84-56-DD-WA SANDER SANDER, STAINLESS STEEL [S03] Roads Maintenance 5 s 0 0 0 0 0 0 5 0 Cover not required 0446-2 Swenson EV-100-13-54 SANDER SANDER, STAINLESS STEEL [S03] Roads Maintenance 1 s 0 0 0 0 0 0 1 0 Cover not required 502 New Holland T6030 / MM23 / 50URCM MOWER TRACTOR, MOWER [TOl] Roads Maintenance 1 s 0 0 0 0 0 0 1 0 503 New Holland T6030 / MM23 / 50URCM MOWER TRACTOR, MOWER [TOl] Roads Maintenance 1 s 0 0 0 0 0 0 1 0 3704 New Holland TS6.125 / Diamond / 50" MOWER TRACTOR, MOWER [TOl] Roads Maintenance 1 s 0 0 0 0 0 0 0 501 John Deere Tractor 6420 W /Sweepster 96" TRACTOR, MOWER [TOl] Roads Maintenance 1 s 0 0 0 0 0 0 1 0 582 Caterpillar 928F LOADER LOADER [LOl) Roads Maintenance 1 M 0 0 0 0 0 1 0 0 583 Caterpillar 936E LOADER LOADER [LOl) Roads Maintenance 1 M 0 0 0 0 0 1 0 0 0327:1 Universal FLAT BED Misc [MOl) Roads Maintenance 1 s 0 0 0 0 0 0 1 0 0327-2 Universal DUMP BOX Misc [MOl) Roads Maintenance 1 s 0 0 0 0 0 0 1 0 0319-3 Universal SPRAYER MISC SMALL EQUIPMENT [M02] Roads Maintenance 1 s 0 0 0 0 0 0 1 0 3611. Vermeer 8C1200XL BRUSH CHIPPER CHIPPER/BLOWER [CO2) Roads Maintenance 1 XS 0 0 0 0 0 0 0 1 643 Suermann CONVEYOR HYO. SHOULDER-8 CONVEYOR, SHOULDER (C03) Roads Maintenance 1 s 0 0 0 0 0 0 1 0 3703 caterpillar 314D LCR EXCAVATOR EXCAVATOR, LARGE [EOl) Roads Maintenance 1 s 0 0 0 0 0 0 1 0 3701 Kubota KX057 EXCAVATOR, SMALL [E04) Roads Maintenance 1 s 0 0 0 0 0 0 1 0 3705 Toyota 8FGU35U FORKLIFT FORKLIFT [FOl) Roads Maintenance s 0 0 0 0 0 0 1 0 0327-3 Universal WATER TANK-U Hook Loader [L04) Roads Maintenance s 0 0 0 0 0 0 1 0 0327-5 Universal CHIP BOX Hook Loader [L04) Roads Maintenance s 0 0 0 0 0 0 0 267 Trail Max TRAILER-TILT BED 16' 16000GVW TRAILER [TlO) Roads Maintenance s 0 0 0 0 0 0 0 Cover not rcQulrcd 3852 Columbia Body Mfg 3 Axle Pup Trailer TRAILER, PUP (T14] Roads Maintenance 0 0 0 0 1 0 0 0 Cover not required 3851 Olympic 30TDT-3 3 AXLE TRAILER TRAILER, TILT BED [T17) Roads Maintenance M 0 0 0 0 0 1 0 0 Cover not required Total North Shop Vehicles and Mobile Equipment so 0 4 1 0 2 10 31 2

Note: Vehicle Count and Program type is translated to building program areas in the Space Program. A 15% increase will be added to account for possible future growth in vehicles in the Space Program.

TCF Architecture, pile Page 1 of 5 DRAFT 6-3-16 Appendix B Programming Validation, June 18, 2021 by Otak, Inc. MWR - moderate waste facility Space Description NO. Proposed Space 20 Year Program General Space Purpose and Design Criteria Adjacencies Clear Other Criteria/Equip./Furnishing Needs Notes: Standard Area (SF) Qty. Total Area Height occupancy and use ENCLOSED/HEATED FACILITIES (HHW) Staff Entry Lobby E1 5x8 40 1 40 Entry area for staff Staff Parking 9' Office E2 12x16 192 1 192 Enclosed office for multiple staff Lobby 3 workstations, attendant for recyling will use office 15 net

Conf. / Break Room E3 12x16 192 1 192 Break room for staff Office Kitchenette 15 net Locker Room/Shower E4 6x14 84 1 84 Provide 5 full height lockers, shower stall, ADA accessible Break Room 9' Storage of coveralls, tile, shower accessories, floor drain Unisex Toilet Rm E5 8x8 64 1 64 Toilet room for use by staff Break Room 9' 1 toilet and sink, lockable door determine staff Processing Area E6 45x45 2025 1 2025 Take in materials from public, test, sort and place in Receiving canopy, offices, staging and storage 16' Overhead door at receiving canopy. Confirm clear storage containers height required inside and at overhead door, exhaust system, eye wash safety shower, lab area, storage racks, slope floor in center of space, containment all around. Occasional use of forklift. Similar layout to existing facility. Bulking Room E7 6x6 36 1 36 Within processing area 9 Increased ventilation Staging/Storage Room E8 45x45 2025 2 Staging and storage of materials in proper containers Processing area 16' Slope floor in center of space, containment all around. Original document does not Overhead door to processing and to loading dock. count this square footage in total Occasional use of forklist. Similar layout to existing area facility. Process batteries. Custodial Room E9 6x8 48 1 48 Mop sink/rack Centrally located 9 Mechanical / Elec / IT Room E10 12x20 240 1 240 Primary hub for communications and data systems, Centrally located 12' electrical panels, and mechanical distribution

Subtotal 2921 Circulation/Walls/Misc 25% 730 Total Heated/Enclosed 3651

COVERED/UNHEATED FACILITIES Recycle Bins C1 10x25 250 4 1000 Canopy covered 40 and 50 yard dump bins, at lower Unloading area 20' 7' below grade with PUC flap between bin and edge of grade for ease of placing materials in bins by public concrete. Metals (1), Cardboard (2), TBD (1). 42" guardrail required concrete, bar railing or jersey barrier. North shop only. Loading Dock C2 10x25 250 1 250 Area to load collected HHW material by vendors HHW staging/storage/room 16' 4' below grade, semi trailer will need the ability to back in. North shop only. Public Unloading Area C3 10x25 250 4 1000 Canopy cover for unloading of recyclables from public Recycle bins 16' Also include 350 gallon oil recycle bin, antifreeze vehicle recycle bin, cooking oil recycle bin, and battery bins. North shop only. HHW Receiving Area C4 20x20 400 1 400 Canopy cover for unloading of HHW from public vehicle Processing Area 16' Ability to close off when not occupied

White Goods Storage C5 15x15 225 1 225 Storage of "white goods" or appliances HHW Office 16' Fenced in area. North shop only. Subtotal 2875 MAY BE INCORRECT Circulation/Walls/Misc 100% 2875 C Total Heated/Enclosed 5750

Area as noted in Contract: 3650

Total Building Area 9401

SITE FACILITIES Staff Parking S1 10x20 200 5 1000 HHW Queuing S2 10x20 200 10 2000 Control arm to regulate traffic, controlled by HHW staff

Empty Container Staging S3 10x50 500 1 500 Full Container Staging S4 10x50 500 1 500 Subtotal 4000 Circulation/Walls/Misc 100% 4000 Total Site Facilities 8000 Not including Structures, drive yard, landscaping, stormwater facilities, setbacks, etc. MWR - moderate waste facility Space Description NO. Proposed Space 20 Year Program General Space Purpose and Design Criteria Adjacencies Clear Other Criteria/Equip./Furnishing Needs Notes: Standard Area (SF) Qty. Total Area Height occupancy and use ENCLOSED/HEATED FACILITIES (HHW)

MRW 10,000 recommended by SWA (not less thatn 7000 sf)

100 per square foot per person is used for offices, plus a 1.3 multiplier for gross One Separate Room for Flammable Liquids with Safety Features H occupancy flammable liquids consolidation and storage area in one separate room in MRW building electrical system and equipment needs to be explosion-proof flammable gas monitoring and alarm system Administration / Crew Space

Proposed Space 20 Year Program Clear Notes: Checked against K:\Project\33300\33305\ProjectDocs\Site Planning\20210608 site plans JM.pdf Space Description NO. Standard Area (SF) Qty. Total Area General Space Purpose and Design Criteria Adjacencies Height Other Criteria/Equip./Furnishing Needs occupancy and use use

Assume the buildings will require occasional 2-3 guest chairs and small table. Phone or access by public visitors, as well as internal Visitor and crew buzzer to notify Shop of visitor, Secure Lobby/Reception A1 10X12 120 1 120 staff from other departments parking 9 space with sliding window. Office

Provides space to meet with vendors up to 4 Small Conference Room A2 12X14 168 1 168 people. Could become future office space Lobby 9 Table with chairs, white board 15 net Office Temp/Float Office A3 12X14 168 1 168 Private office 9 Work station bookshelves, white board Office Future Sherriff, possible right in right out from Bond Adjacent to crew Supervisor Office A4 12X14 168 1 168 Private office areas 9 Work station bookshelves, white board Office Adjacent to crew Work station bookshelves, white board, Asst. Supervisor Offices A5 12X18 216 1 216 2 Assistant Supervisors share private office areas 9 charging and storage of tablets Office

Tables & chairs / (2) flat screens, country Kitchenette, maps, posting space, 10' of white board, Seating for 25-30 people at chairs and tables. convenient access to projector and projector screen, 3 shared Multi Purpose / Training / Crew Rm A6 26X34 884 1 884 All hands meetings and training sessions locker rooms, offices 12 PC's on desks or built in counter Office

Full size refrigerator (1, 2 if space allows), Included in Part included in Multi microwave (2), double sink, lower and Kitchenette (Part of multi-purpose) A7 5X20 100 1 Multi-purpose Kitchen area shared by all staff and crew Purpose Room 9 upper cabinets, vending machine (2) Provide space for up to (32) 18" wide full Private men's locker and toilet room. Toilets, Adjacent to mud height cage lockers, benches, floor drains Men's Locker Room A8 20x34 680 1 680 sinks per plumbing code, (minimum 2 urinals) room, wellness room 9+ and under-locker boot dryers 50 gross - determine count

Adjacent to or within Men's Shower A9 6x8 48 1 48 Private shower stall, ADA accessible Men's Locker/Toilet 9 Tile, shower accessories, floor drain Provide space for up to (5) 18" wide full Private women's locker and toilet room. Adjacent to mud height cage lockers, benches, floor drains Women's Locker Room A10 14x20 280 1 280 Toilets, sinks per plumbing code. room, wellness room 9+ and under-locker boot dryers 50 gross - determine count Adjacent to or within Women's Women's Shower A11 3x8 48 1 48 Private shower stall, ADA accessible Locker/Toilet 9 Tile, shower accessories, floor drain Locker room, near Hanging rack system, stacking Drying Room A12 10x10 100 1 100 Drying and storage of boots and coveralls exterior door 9 washer/dryer, deep sink Cleaning of boots before entering the building, Mud room, near covered / partial enclosure / Boot Wash A13 4x4 16 - Outside exterior space with canopy exterior door 9 Hose bib, sump, grating, boot scrubber bench Copier, shelves for paper storage, counter Small area for printer/copier and counter work Near office, multi- 6' - 8' linear feet, recycle bins, mail box with Copy/Print Alcove A14 6x10 60 1 60 space purpose and mailbox 9 40 slots Custodial Room A15 6x8 48 1 48 Mop sink/rack Centrally located 9 Storage of documents that are not regularly Could be part of a Archive Storage A16 10x10 100 1 100 accessed mezzanine space 9 IT Room A17 10x10 100 1 100 Primary hub for communication and data Centrally located 9 Could be part of a Electrical Room A18 10x10 100 1 100 Primary hub for electrical equipment mezzanine space 9 Centrally located, Mechanical Room A19 10x14 140 1 140 Primary hub for mechanical equipment mezzanine space 9 Subtotal 3428 Circulation/Walls/Misc 30% 1028 Total Admin/Crew 4456

Area as noted in Contract: 4500 YES Covered Canopy Equipment / Vehicle Storage

Space Description NO. Proposed Space 20 Year Program General Space Purpose and Adjacencies Clear Other Criteria/Equip./Furnishing Needs Notes: Checked against K:\Project\33300\33305\ProjectDocs\Site Planning\20210608 site plans JM.pdf Standard Area (SF) Qty. Total Area Design Criteria Height occupancy and use ESD Managers/Lead Mech Office M1 12x12 144 2 288 Enclosed office Break Room 9' View to Maintenance Bays by Lead Mech at minimum ESD Manual Library M2 12x12 144 1 144 Manual library for ESD crew Offices 9' Bokshelf, tables and chairs, manual library, 50 net / 100 gross computer with manuals Heavy Maintenance Bays M3 20x55 1100 4 4400 Major vehicle maintenance/repair, Fabrication and General Shops 30' Vehicle exhaust, floor drain, light colored 300 gross larger vehicles walls and floor, natural daylight, bridge crane with 24' hook height and/or job. 16' clear OHD. Mobile hydraulic wheel lifts, 3 cage lockers 24"x18" in bays or in main locker room. Floor sloped to slotted drains near large vehicle doors.

Lube/Comp. Room M4 12x20 240 1 240 Store lube and fluid tanks, Maintenance Bays 10' Sound attenuation compressor Specialty Tool Storage M5 20x20 400 1 800 Small Power Tool storage Maintenance Bays 10' Heavy duty storage racks and cabinets, lockable cabinets, shelving for small tools

Large Tool/Equipment Storage M5 20x20 400 1 800 Storage of oversized tools and Maintenance Bays 10' Heavy duty storage racks and cabinets, equipment lockable cabinets, shelving for small tools

Tire Shop combined with storage Tire Storage M6 20x55 1100 1 1100 Store Maintenance Bays 16' Tire storage racks, confirm quanitty and sizes General Purpose Shop 20x40 800 1 800 items bit included in fabrication Fabrication and General Shops

Fabrication Shop M7 26x40 1040 1 1040 Fabrication for use by ESD, locate Vehicle Maintenance Bays 12' Welding table, welding/fab equipment. at end of building, to be used for Ventilation boom. Welding curtain future expansion of maintenance bays Misc Storage Bay M8 C 960 1 960 Equipment staging and temporary Enclosed vehicle parking 16' storage, especially during winter months, storm division, temporarily store (2) sanders, (1) vactor and (1) sweeper, paint totes Survey Crew Storage M9 12x12 144 1 144 Storage of survey equipment, on Adjacent to other storage 9' Horizontal and vertical storage systems mezzanine if space is available

Hazmat Storage M10 12x16 192 1 192 Provide sump containment and Other storage spaces 12' Confirm quantities and types of materials ventilation per code stored, exterior access, cabinets and shelving Tool Repair/Tool Room M11 20x24 480 2 960 Secure tool storage for power Vehicle storage. Provide interior 16' Check-out window 960 sf proposed tools, specialty tools. access and direct access to Maintenance and repair area for exterior. tools. Large Vehicle Parking Bays M12 12x45 540 2 1080 See complete vehicle analysis 16' document Medium Vehicle Parking Bays M13 12x35 420 2 840 See complete vehicle analysis 2,800 sf proposed 16' (up to (10) 12" half hieght lockers for document seasonals) Small Vehicle Parking Bays M14 10x25 250 0 - See complete vehicle analysis 16' document X-Small Vehicle/Equipment Parking Bays M15 8x8 64 0 - See complete vehicle analysis 16' document Wash Bay Equipment Room M16 18x50 900 1 900 Space for water reclaim Wash Bay 12' Can be open to structure. 8x8 overhead equipment doors Mezzanine M17 - - 1 Mechanical area, electrical room, 12' 12' top of floor, bridge crane access if Maximize space. Tool rooms, tire storage IT room, and bulk storage to possible. SF determined during design below mezzanine…? optimum foot print Subtotal 14688 Circulation/Walls/Misc 25% 3672 Total Maintenance/Shops/Vehicles & Equipment 18360 ??? Total Enclosed/Heated Facilities 22816 ???

Area as noted in Contract: 14000 YES

herbiside and storage Space Description NO. Proposed 20 Year Program General Space Purpose and Adjacencies Clear Other Criteria/Equip./Furnishing Needs Notes: Checked against K:\Project\33300\33305\ProjectDocs\Site Planning\20210608 site plans JM.pdf Space Area (SF) Qty. Total Area Design Criteria Height Fuel Island C1 18x60 1080 2 2160 Fueling of all vehicles, 4 Reuse existing equipment and 16' Locate near entry for easy in and out access. Above positions maintain location if feasible and ground tanks. (2) dispensers 20' apart, (1) for unleaded functional with new site layout, and (1) for diesel, with two hoses each. Fuel card reader near fuel tanks pedestal between dispensers. Open to other County departments Wash Bay C2 24x60 1440 2 2880 Wash down of all vehicles, Located as an end bay adjacent to 26' Manual pressure wash system with heated water, provide 1-1/2" hose connection, fueling catwalks both sides of one bay, need clear height to trench drain. Water reclaim allow street sweepers with buckets up, confirm height. system tha can remove salt. Can 1 1/2" and 2" hose for cleaning out sweeper. (1) bay to reduce to (1) bay if needed. have steam clean ability

Ice Machine Niche C3 5x5 25 1 25 Ice machine for use by crews 9' Covered Large Vehicle Parking C4 12x45 540 0 - See complete vehicle analysis 16' Vehicle inventory showed 1 large document vehicle to be covered. Vehicle Parking size is larger than vehicle inventory. Medium Vehicle Parking C5 12x35 420 7 2450 See complete vehicle analysis 16' Vehicle inventory showed 9 document medium vehicles to be covered. Vehicle Parking size is larger than See Vehicle Inventory Tab vehicle inventory. Small Vehicle Parking C6 10x25 250 14 3500 See complete vehicle analysis 16' Vehicle inventory showed 21 small document vehicles to be covered. Vehicle Parking size is larger than vehicle inventory. X-Small Vehicle/Equipment Parking C7 8x8 64 1 64 See complete vehicle analysis 16' Vehicle inventory showed 2 x- document small vehicles to be covered Working Stock/Bulk Storage C8 24x50 1200 1 1200 Storage of materials that can End of vehicle storage building 16' Pallet racks, straw storage, fabric, chains, miscellaneous not be put back into inventory items, could be drive through and other bulk material

Street Sweepings C9 24x30 720 1 720 Street sweeping tailing storage Salt storage 24' Confirm clear height required and if existing structure is in our existing fabric structure to be reused

Salt Storage C10 24x30 720 2 1440 Store Salt in new fabric canopy Brine operation 24' Use fabric canopy structure. Located away from main structure structures, confirm clear height required, ecology blocks at back and sides. Fully enclosed with scrim/curtain to protect against weather, confirm clear height required

Subtotal 14439 Circulation/Walls/Misc 15% 2166 Total Covered/Unheated 16605

Area as noted in Contract: 9600 Space Description NO. Proposed 20 Year Program General Space Purpose and Adjacencies Other Criteria/Equip./Furnishing Needs Notes: Space Area (SF) Qty. Total Area Design Criteria PARKING Employee Parking S1 10x20 200 30 6000 Main entry, crew entry Enclosed fencing, EV charging Visitor Parking S2 10x20 200 5 1000 Subtotal 7000 Circulation/Walls/Misc 100% 7000 Total Covered/Unheated 14000 Does not have to be covered.

Bulk Materials/Miscellaneous Site Items Large Vehicle Parking S3 12x45 540 2 1080 See complete vehicle analysis Other vehicles Vehicle inventory showed 1 large vehicle to document be uncovered. Vehicle Parking size is larger than vehicle inventory.

Medium Vehicle Parking S4 10x35 350 1 350 See complete vehicle analysis Other vehicles pl document See vehicle Inventory tab Small Vehicle Parking S5 10x25 250 20 5000 See complete vehicle analysis Other vehicles Vehicle inventory showed 10 small vehicles document to be covered. Vehicle Parking size is larger than vehicle inventory.

X-Small Vehicle/Equipment Parking S6 8x8 64 1 64 See complete vehicle analysis Other vehicles Vehicle inventory showed 0 x-small vehicles document to be covered Brine Production/Tank S7 15x20 300 1 300 Produce brine for road de-icing Salt storage 8,000 gallon tank and 4,000 tank reuse existing if possible, 200 gallon mixing tank

Laydown Area S8 50x100 5000 1 5000 Laydown area for large Yard dock inventories items, can be on racks

Yard Dock S9 15x55 825 1 825 Access to back of semi trailer if Laydown area 4' grade difference off loading from the back with forklift access Sand S10 40x40 1600 2 3200 Bulk storage Bulk storage Confirm quantity and types 10 each, 20'x15' eco block bins Gravel S11 40x40 1600 2 3200 Bulk storage Bulk storage Confirm quantity and types Road Striping Storage S12 20x30 600 1 600 20 paint totes and 20 beads, Bulk storage during summer season misc sign storage on pallets Bulk Storage S13 40x80 3200 1 3200 Storage of bulk items that are not Sand/Gravel Pipes (plastic u pto 20' lengths), culverts, inventory controlled or cannot fit used concrete pipes, catch basins, guard within warehouse rails, grames and grates Fuel Tanks S14 8x32 256 3 768 Fueling of vehicles and Reuse existing tanks and Above ground 12,000 gallon unleaded with equipment maintain location if ingrastructure for E85, 12,000 gallon diesel feasible and functional (B20), 1,000 gallon propane. Bollards to with new site layout, near protect tanks, on curb. fueling island Bulk Oil Storage Tanks S15 15x30 450 2 900 Storage of bulk oil for chip and Yard dock Chip Seal 10,000 Gallons (CRS2P), Tack Seal May not be a good idea, given proximity to tack seal operations 5,000 Gallons (CSS1). Heated oscillating critical areas

Dumpsters/Recycling Containers S16 10x20 200 4 800 Elevated tipping wall Yard dock 40 yard Metal recycling, organics and garbage and cardboard. Sander Boxes S17 10x20 200 10 2000 Vertical hanging structure for Bulk storage Provide high pressure/volume water to Provide cat walks between bays for storage of sander boxes clean under box while hanging employee access Space Description NO. Proposed 20 Year Program General Space Purpose and Adjacencies Other Criteria/Equip./Furnishing Needs Notes: Space Area (SF) Qty. Total Area Design Criteria DownPARKING Ready Line S18 10x30 300 12 3600 Maintenance Shop not sure what this is? It is area for vehicles in schedule for maintenance Generator S19 10x15 150 1 150 Back up power for full site operation with load shedding Subtotal 31037 Square footage sum does not match that of original spreadsheet - likely a formula omission Circulation/Walls/Misc 100% 31037 Total Covered/Unheated 62074

Total Programmed Site Area 76074 Not including Structures, drive yard, landscaping, stormwater facilities, setbacks, etc.

Area as noted in Contract: x Vehicle Inventory

Kitsap County PubIic Works - Strategic Facilities Plan

North Shop Vehicle Parking Analysis VEHICLE PARKING ANALYSIS L = 12' x 40’ 480 M = 10’ x 30’ 300 S = 10' x 20' 200 XS = 8' x 8' 64

HEATED COVERED UNCOVERED COMMENTS ASSET NO DESCRIPTION DEPARTMENT QTY. SIZE L M S XS L M S XS L M S XS 307 Chevrolet P30 STEP VAN TRUCK, SERVICE [T35] ESD 1 S 0 0 1 0 0 0 0 0 0 0 0 0 Stored in Mechanic Bay at night 3702 Caterpillar 120M2 MOTOR GRADER MOTOR GRADER [M03] Roads Maintenance 1 L 0 0 0 0 0 0 0 0 1 0 0 0 134 Chevrolet COLORADO EXT CAB 4X4 PU 1/4T EXT CAB 4X4 [A38] ESD 1 S 0 0 0 0 0 0 1 0 0 0 0 0 Cantileverd conver adj to bldg 3005 Ford Expolrer SUV [A50] Roads Maintenance 1 S 0 0 0 0 0 0 1 0 0 0 0 0 Cantileverd conver adj to bldg 158, 3001, 3003, 3004 Ford F150 EXT CAB 4X4 PU 1/2T EXT CAB 4X4 [A29] Roads Maintenance 4 S 0 0 0 0 0 0 4 0 0 0 0 0 Cantileverd conver adj to bldg 159, 3000, 3002 Ford F250 REG CAB 4X2 PU 3/4T REG CAB 4X2 A [A31] Roads Maintenance 3 S 0 0 0 0 0 0 3 0 0 0 0 0 Cantileverd conver adj to bldg 196 Ford F250 SD CREW CAB 4X2 PU 3/4T CREW CAB 4X2 [A36] Roads Maintenance 1 S 0 0 0 0 0 0 1 0 0 0 0 0 Cantileverd conver adj to bldg 3400 Ford F350 SD Ext Cab 4x2 DRW, Flatbed Cone Truck PU 1T [A40] Roads Maintenance 1 M 0 0 0 0 0 1 0 0 0 0 0 0 3401 Ford F350 REG CAB 4x4 FLATBED PU 1T [A40] Roads Maintenance 1 M 0 0 0 0 0 1 0 0 0 0 0 0 3403 Freightliner M2-106 ALTEC TA55 BUCKET TRUCK TRUCK, BUCKET (MANLIFT) [T30] Roads Maintenance 1 M 0 0 0 0 0 1 0 0 0 0 0 0 319 Ford F550 SD 4X4 W/HOOK LOADER TRUCK, HOOK LOADER (LIGHT) [T32] Roads Maintenance 1 S 0 0 0 0 0 0 1 0 0 0 0 0 3500, 5501 IHC 7600SFA Pup Trk W/10-12 DUMP TRUCK, PUP W/10-12YRD DUMP [T34] Roads Maintenance 2 M 0 0 0 0 0 2 0 0 0 0 0 0 3404 Freightliner 108SD w/Hook Loader TRUCK, SINGLE AXLE, W/HOOK LOADER Roads Maintenance 1 M 0 0 0 0 0 1 0 0 0 0 0 0 321 IHC 4400 4X2 W/PB PATCHER TRUCK, SINGLE AXLE, W/PATCHER [T43] Roads Maintenance 1 M 0 0 0 0 0 1 0 0 0 0 0 0 461 IHC 2574 W/1O-12 DUMP TRUCK, W/10-12YRD DUMP [T48] Roads Maintenance 1 M 0 0 0 0 0 1 0 0 0 0 0 0 3501, 3503 IHC 7600SFA Plow Trk W/10-12 DUMP TRUCK, W/10-12YRD DUMP [T48] Roads Maintenance 2 M 0 2 0 0 0 0 0 0 0 0 0 0 3402 Freightliner 500X TYMCO SWEEPER SWEEPER, TRUCK STREET [S09] Roads Maintenance 1 M 0 0 0 0 0 1 0 0 0 0 0 0 3600 Superior Broom SM80K Front Mounted Push SWEEPER [S07] Roads Maintenance 1 M 0 0 0 0 0 0 0 0 0 0 1 0 3504, 3505, 3506 Freightliner 114SD Plow Trk W/10-12 DUMP TRUCK W/10-12YRD DUMP [T48] Roads Maintenance 3 M 0 3 0 0 0 0 0 0 0 0 0 0 3610 Bobcat T770 COMPACT TRACK LOADER L05 [Loader, Track] Roads Maintenance 1 S 0 0 0 0 0 0 0 0 0 0 1 0 3709 Caterpillar CB34B ROLLER ROLLER, STEEL DRUM [R02] Roads Maintenance 1 S 0 0 0 0 0 0 0 0 0 0 1 0 0319-2/4, 0327-4 Universal Sander SANDER, IRON [S02] Roads Maintenance 2 S 0 0 0 0 0 0 0 0 0 0 2 0 Cover not required 487 Hi-Way P7 SANDER HYD PWRD 1.5 YD SANDER, IRON [S02] Roads Maintenance 1 S 0 0 0 0 0 0 0 0 0 0 1 0 Cover not required 0461-2, 3501-3, 3504-2,3506-2 Monroe MV-132-84-56-DD-WA SANDER SANDER, STAINLESS STEEL [S03] Roads Maintenance 4 S 0 0 0 0 0 0 0 0 0 0 4 0 Cover not required 0446-2 Swenson EV-100-13-54 SANDER SANDER, STAINLESS STEEL [S03] Roads Maintenance 1 S 0 0 0 0 0 0 0 0 0 0 1 0 Cover not required 3707, 3708 New Holland TS6.145 / Diamond / 50" MOWER TRACTOR. MOWER [T01] Roads Maintenance 2 S 0 0 0 0 0 0 2 0 0 0 0 0 3704 New Holland TS6.T2S / Diamond / 50“ MOWER TRACTOR. MOWER [T01] Roads Maintenance 1 S 0 0 0 0 0 0 1 0 0 0 0 0 3706 John Deere 544K LOADER LOADER [L01] Roads Maintenance 1 M 0 0 0 0 0 0 0 0 0 1 0 0 3710 John Deere 544L LOADER LOADER [L01] Roads Maintenance 1 M 0 0 0 0 0 0 0 0 0 1 0 0 0327-1 Universal FLAT BED Misc [M01] Roads Maintenance 1 S 0 0 0 0 0 0 1 0 0 0 0 0 0327-2 Universal DUMP BOX Misc [M01] Roads Maintenance 1 S 0 0 0 0 0 0 0 0 0 0 1 0 0319-3 Universal SPRAYER MISC SMALL EQUIPMENT [M02] Roads Maintenance 1 S 0 0 0 0 0 0 1 0 0 0 0 0 3611 Vermeer BC1200XL BRUSH CHIPPER CHIPPER/BLOWER [C02] Roads Maintenance 1 XS 0 0 0 0 0 0 0 0 0 0 0 1 643 Buermann CONVEYOR HYD. SHOULDER-B CONVEYOR, SHOULDER [CO3] Roads Maintenance 1 S 0 0 0 0 0 0 1 0 0 0 0 0 3703 Caterpillar 314D LCR EXCAVATOR EXCAVATOR, LARGE [E01] Roads Maintenance 1 S 0 0 0 0 0 0 0 0 0 0 1 0 3701 Kubota KX057 EXCAVATOR, SMALL [E04] Roads Maintenance 1 S 0 0 0 0 0 0 0 0 0 0 1 0 Vehicle Inventory

Kitsap County PubIic Works - Strategic Facilities Plan 3705 Toyota 8FGU35U FORKLIFT FORKLIFT [FO1] Roads Maintenance 1 S 0 0 0 0 0 0 1 0 0 0 0 0 0327-3 Universal WATER TANK-U Hook Loader [L04] Roads Maintenance 1 S 0 0 0 0 0 0 1 0 0 0 0 0 0327-5 Universal CHIP BOX Hook Loader [L04] Roads Maintenance 1 S 0 0 0 0 0 0 0 0 0 0 1 0 5710 Wirtgen W-100CFi GRINDER (JOINT) GRINDER [G02] Roads Maintenance 1 L 0 0 0 0 1 0 0 0 0 0 0 0 4708 Volvo PF4410 PAVER (JOINT) PAVER, POWER [P02] Roads Maintenance 1 M 0 0 0 0 0 0 0 1 0 0 0 0 249 Trail King 30TDT-3 3 AXLE PAVER TRAILER (JOINT) TRAILER, TILT BED [T17] Roads Maintenance 1 L 0 0 0 0 0 0 0 0 1 0 0 0 Cover not required 4852 Trail King TK110HDG LO-BOY GRINDERTRAILER (JOINT) TRAILER, TILT BED [T17] Roads Maintenance 1 L 0 0 0 0 0 0 0 0 1 0 0 0 Cover not required 267 Trail Max TRAILER-TILT BED 16' 1600DGVW TRAILER [T10] Roads Maintenance 1 S 0 0 0 0 0 0 0 0 0 0 1 0 Cover not required 3852, 5851 Columbia Body Mfg 3 Axle Pup Trailer TRAILER, PUP [T14] Roads Maintenance 2 L 0 0 0 0 0 0 0 0 2 0 0 0 Cover not required 3851 Olympic 30TDT-3 3 AXLE TRAILER TRAILER, TILT BED [T17] Roads Maintenance 1 M 0 0 0 0 0 0 0 0 0 1 0 0 Cover not required Total North Shop Vehicles and Mobile Equipment 50 0 5 1 0 1 9 19 1 5 3 16 1 Square footage of Cover 0 1500 200 0 480 2700 3800 64 2400 900 3200 64 15308 Area as noted in Contract: HEATED COVERED UNCOVERED Note: Vehicle Count and Program type is translated to building program areas in the Space Program. A 5K increase 1700 ** 7044 ** 6564 will be added to account for possible future growth in vehicles Tn the Space Program. ** 9600 SF allows for material storage under canopy (2 bays) Vehicle Description VEHICLE PARKING ANALYSIS L 12' x 40’ 480 M 10’ x 30’ 300 S 10' x 20' 200 XS 8' x 8' 64

Vehicle Discription Qty size Image for Reference Sketchup / Revit File Yes No

TRUCK, SERVICE Chevrolet P30 STEP VAN 1 S [T35] < =

120M2 MOTOR MOTOR GRADER Caterpillar 1 L GRADER [M03]

PU 1/2T EXT CAB Ford F150 EXT CAB 4X4 1 S 4X4 [A29]

PU 3/4T REG CAB Ford F250 REG CAB 4X2 3 S 4X2 A [A31] PU 3/4T REG CAB Chevrolet K30 1 M 4X2 A [A31] TRUCK, BUCKET Ford F650 VERSALIFT 1 M (MANLIFT) [T30] TRUCK, HOOK F550 SD 4X4 W/HOOK Ford LOADER (LIGHT) 1 S LOADER [T32]

7600SFA Pup Trk W/10- TRUCK, PUP W/10- IHC 2 M 12 DUMP 12YRD DUMP [T34] Vehicle Description VEHICLE PARKING ANALYSIS L 12' x 40’ 480 M 10’ x 30’ 300 S 10' x 20' 200 XS 8' x 8' 64

Vehicle Discription Qty size Image for Reference Sketchup / Revit File TRUCK, SINGLE GMC TOPKICK C8500 AXLE, W/HOOK 1 M LOADER

TRUCK, SINGLE 4400 4X2 W/PB IHC AXLE, W/PATCHER 1 M PATCHER [T43]

TRUCK, W/10- IHC 2574 W/1O-12 DUMP 3 M 12YRD DUMP [T48]

7600SFA Plow Trk TRUCK, W/10- IHC 2 S W/10-12 DUMP 12YRD DUMP [T48] 500X TYMCO SWEEPER, TRUCK IHC 1 M SWEEPER STREET [S09] 114SD Plow Trk W/10- TRUCK W/10-12YRD Freightliner 1 M 12 DUMP DUMP [T48] CC800 Plus, Small Dynapac ROLLER [R01] 1 XS Vibratory Roller

ROLLER, STEEL Caterpillar CB334E ROLLER 1 S DRUM [R02]

Universal Sander SANDER, IRON [S02] 2 S P7 SANDER HYD Hi-Way SANDER, IRON [S02] 1 S PWRD 1.5 YD Vehicle Description VEHICLE PARKING ANALYSIS L 12' x 40’ 480 M 10’ x 30’ 300 S 10' x 20' 200 XS 8' x 8' 64

Vehicle Discription Qty size Image for Reference Sketchup / Revit File SANDER, MV-132-84-56-DD-WA Monroe STAINLESS STEEL 5 S SANDER [S03] SANDER, Swenson EV-100-13-54 SANDER STAINLESS STEEL 1 S [S03] T6030 / MM23/ TRACTOR. MOWER New Holland 1 S 50URCM MOWER [T01] T6030 / MM23/ TRACTOR. MOWER New Holland 1 S 50URCM MOWER [T01] TS6.T2S / Diamond / TRACTOR. MOWER New Holland 1 S 50“ MOWER [T01] Tractor 6420 TRACTOR. MOWER John Deere 1 S W/Sweepster 96" [T01]

Caterpillar 928F LOADER LOADER [L01] 1 M

Caterpillar 936E LOADER LOADER [L01] 1 M

Universal FLAT BED Misc [M01] 1 S

Universal DUMP BOX Misc [M01] 1 S MISC SMALL Universal SPRAYER 1 S EQUIPMENT [M02]

BC1200XL BRUSH CHIPPER/BLOWER Vermeer 1 XS CHIPPER [C02] Vehicle Description VEHICLE PARKING ANALYSIS L 12' x 40’ 480 M 10’ x 30’ 300 S 10' x 20' 200 XS 8' x 8' 64

Vehicle Discription Qty size Image for Reference Sketchup / Revit File

CONVEYOR HYD. CONVEYOR, Buermann 1 S SHOULDER-B SHOULDER [CO3]

314D LCR EXCAVATOR, Caterpillar 1 S EXCAVATOR LARGE [E01]

EXCAVATOR, Kubota KX057 1 S SMALL [E04]

Toyota 8FGU35U FORKLIFT FORKLIFT [FO1] 1 S Universal WATER TANK-U Hook Loader [L04] 1 S Universal CHIP BOX Hook Loader [L04] 1 S

TRAILER-TILT BED Trail Max TRAILER [T10] 1 S 16' 1600DGVW Vehicle Description VEHICLE PARKING ANALYSIS L 12' x 40’ 480 M 10’ x 30’ 300 S 10' x 20' 200 XS 8' x 8' 64

Vehicle Discription Qty size Image for Reference Sketchup / Revit File

Columbia Body Mfg 3 Axle Pup Trailer TRAILER, PUP [T14] 1 L

30TDT-3 3 AXLE TRAILER, TILT BED Olympic 1 M TRAILER [T17] Appendix C Expected Kitsap County Population Growth and Transportation Facilities Demand Memo, August 1, 2021 by Otak, Inc. Technical Memorandum

To: Jacques Dean, Kitsap County From: Cristina Haworth, AICP; Jeff Massie, PE Copies: File Date: August 1, 2021 Subject: Expected Kitsap County Population Growth and Transportation Facilities Demand Project No.: 33305

This memorandum evaluates Kitsap County population growth projections to address concerns that the North Kitsap Service Center (NKSC) program will adequately accommodate future service level demands. The NKSC is a proposed road maintenance and operations shop with collocated household hazardous (moderate risk) waste collection facility. The road shop portion should provide adequate space for materials and equipment storage, building space for staff needs, and vehicle and equipment parking for anticipated future service needs.

Background There is some inherent difficulty when anticipating changes in future road maintenance needs. Assets (e.g., bridges, lane miles of pavement, striping and signage, etc.) typically increase over time due to population growth, associated land development and densification, and transportation level-of-service concurrency requirements. As development within Kitsap County increases, however, ownership of many assets will be transferred to municipalities through future annexations of designated urban growth areas that are currently unincorporated.1

This memo analyzes Kitsap County’s adopted Comprehensive Plan to provide perspective on the adequacy of the North Kitsap Service Center site and building program and its ability to serve potential future growth. This memo does not address any possible future agreements between municipalities to have the County maintain and operate their transportation assets.

Public Works Projected Staff Growth The 2016 Kitsap County Public Works Strategic Facilities Plan developed a site and building program in 2016 and 2017. This formed the basis for establishing minimum criteria for facility sizing in preliminary planning scenarios. The Plan assumes very little growth in maintenance needs. The Plan’s preliminary space program assumes a 15 percent growth for full-time operations crew and no growth in administrative or supervisory staff.

Programming for the Moderate Risk Waste Facility for current and anticipated waste streams is covered by the July 14, 2021 Final Kitsap County HHW Programming Report prepared by Special Waste Associates.

Expected Kitsap County Population Growth and Transportation Facilities Demand The 2016 Kitsap County Comprehensive Plan projects the County to grow to 331,571 residents by 2036.2 The 2017 estimate published by the Washington Office of Financial Management (OFM) predicts growth to between

1 Washington’s Growth Management Act requires growth to occur at an urban density only inside the Urban Growth Boundary. The Urban Growth Boundary contains incorporated cities and designated Urban Growth Areas that will eventually be annexed. Growth outside the Urban Growth Boundary will occur at a rural level consistent with existing zoning standards. 2 This is assumed to be the high projection series population estimate published by OFM in 2012. k:\project\33300\33305\projectdocs\site planning\alt analysis tech memo figures and appendices\appendix c_expected kitsap county population growth and transp facilites demand memo july 26, 2021 by otak, inc.docx

11241 Willows Road NE, Suite 200 . Redmond, WA 98052 . Phone 425.822.4446 . otak.com Page 2 Expected Kitsap County Population Growth and Transportation Facilities Demand August 1, 2021

315,437 and 400,231 people by 2036.3 This rapid growth is expected to be concentrated in existing incorporated areas or designated urban growth areas to be annexed based on the Kitsap County future land use map and zoning map.

Numeric Total Percent Avg. Annual Year Population Change Change Growth Rate 2010 (baseline) 251,133 2011 (est.) 253,900 2,767 1% 1% 2021 (est.) 275,600 21,700 9% 1% 2036 (est.) 315,437-400,231 39,837-124,631 14%-45% 1%-2%

The Comprehensive Plan estimates that approximately 23 percent of the projected growth will live in unincorporated areas outside of the urban growth boundary. Applied to the current OFM projections, the County can expect population growth in unincorporated areas of approximately 9,163 to 28,666 new people by 2036. Based on Census-estimated 2.48 persons per household, this translates to 3,684 to 11,559 new housing units in all of unincorporated Kitsap County.

Unincorporated Kitsap County is intended to be developed at a rural level of density, typically between one unit per five acres and one unit per 40 acres,4 indicating that development and associated traffic impacts will be relatively low. Urban levels of density are anticipated in existing incorporated jurisdictions and adjacent designated urban growth areas. For the purposes of planning for roadway maintenance and operations, roadways in incorporated cities or urban growth areas are assumed to be maintained by those jurisdictions. Based on projected population growth, estimated number of housing units, allowable density in unincorporated Kitsap County, and the current Capital Improvement Plan/Transportation Improvement Plan documents, this memo assumes no significant expansion of the roadway network will occur. Ongoing maintenance of the existing network may increase due to a greater volume of traffic and associated wear and tear in the North District due to increased development.

System Deficiencies and Planned Improvements Kitsap County adopts level of service (LOS) standards for its roadways and intersections and is responsible for maintaining its roadways and intersections at those LOS standards. The County allows up to 15 percent of lane- miles to temporarily exceed LOS standards for determining concurrency. The County assessed its roadways in 2015 and determined that the North County region has four road sections totaling 7.9 lane-miles that are deficient from the adopted LOS standards. Deficiencies are in WSDOT rights-of-way. After implementing planned transportation improvements, Kitsap County will still have 7.2 lane-miles of deficient roadways in the North County region in 2036, and deficiencies remain in WSDOT rights-of-way. No significant expansions in the roadway network are planned.

Summary By 2036, unincorporated Kitsap County will remain rural in population density. The number of road assets are not anticipated to increase significantly and may be offset by municipality annexations. It is anticipated that the programming prepared by TCF Architects, and program validation prepared by Otak, is adequate to address growth needs through 2036 and indefinitely beyond.

3 These estimates are from the moderate and high projection series. Kitsap County surpassed the low projection series and that is not considered an appropriate projection. 4 Limited exceptions apply in specific Rural Village areas. k:\project\33300\33305\projectdocs\site planning\alt analysis tech memo figures and appendices\appendix c_expected kitsap county population growth and transp facilites demand memo july 26, 2021 by otak, inc.docx Appendix D Existing HHWC and Road Maintenance Facilities and North Kitsap Service Center, April 22, 2021 Field Trip Notes, Otak, Inc.

Pierce County Central Maintenance Facility, June 2, 2021 Field Trip Summary, Otak, Inc.

Field Investigation Summary, June 2, 2021 by Notkin a P2S Inc. Company Meeting Summary

Meeting: Existing HHWC and Road Maintenance Facilities, and N Kitsap Svc. Ctr. Field Trip Project No.: 33305 Project Name: North Kitsap Service Center Meeting Date: April 22, 2021 Meeting Time: 9:00 AM to 4:00 PM Locations: Stop 1: 5551 SW Imperial Way, Bremerton Stop 2: 2339 SE Cedar Road, Port Orchard Stop 3: 301 NE Bernt Road, Poulsbo Stop 4: 2300 Bond Road NE, Poulsbo Attendees: Kitsap County: Jacques Dean, Rick Gilbert, Chris Piercy ,Keith Swearingen, Frank Hiller, Dave Myrick Otak: Jeff Massie, Mark Shelby, Michael Payne, Liz Wertz, Sierra Carson, Cristina Haworth, Dave Stewart, Jeff Gray, Lori McFarland Special Waste Associates: David Nightingale P2S: Akshay Prabhu

Stop 1 - 5551 SW Imperial Way, Bremerton; HHW moderate risk waste facility ▪ Site is .27 acre and was opened in 1996 serving 4,000 customers a year, currently serving 10,000 per year. Site mostly serves individual homeowners and some small business waste is accepted. ▪ Operates with a staff of 5, hours are 10-4 Thurs/Fri/Sat, new facility scheduling may be offset days. ▪ Currently accepting corrosive and flammable and toxic substances, paint, batteries, fluorescent bulbs, etc. WSP takes all explosives that inadvertently make it through screening.. WA State Department of Health takes radioactive material that also bypass screening. ▪ A new recycling program is launching 7/1, resulting in the removal of the paint crusher. A crusher will likely not be included in new site ▪ Currently the operation is 3,900 Sq Feet. A larger space is necessary with additional indoor/covered storage required to maintain standard operations and flow. ▪ Adjacent or connected Re-Use shed is required, easy staff access and within line of sight is required ▪ Need a semi-truck loading dock to accommodate a max of 53’ truck/trailer combinations ▪ Desire lift gate at loading dock for business and residential drop-off in case large pallet loading/offloading is needed. ▪ Desire to maintain an /protected drive through 2 lane (minimum) drop off location and add a wind screen cover for awning. Current width of pavement works well, no sidewalk or striping. Bollards will be necessary as well as a manually controlled remote traffic arm. ▪ Wind and wind-blown-rain protection should be provided. ▪ Current spill containment is a curb and drain. Could potentially use curb/swale/drain. The opportunity for spill is limited to 55 gallon drums as that is max size. But since the team controls the flow of vehicles someone is always present so even then the entire drum would not have enough time to empty fully ▪ Break area should connect to the outdoors

Inside Facility: ▪ Staff intakes items on carts, sorts and processes

k:\project\33300\33305\admin\meetings\2021-04-22_nksc field trip notes_kcpw review final changes accepted.docx Existing HHWC and Road Maintenance Facilities, and North Kitsap Service Center Field Trip April 22, 2021

▪ A scale is currently by the front sorting area.. Current scale is a trip hazard, staff wants something more integrated flush-mounted in the floor. Scale location could be moved to the storage areas, or adjacent to them. ▪ A more ergonomically located fume hood is desired, used for identification of unknown substances ▪ Flammable liquid processing involves the most routine potential exposure contact for staff. It is mitigated by ventilation and respiratory protection. ▪ Some spot ventilation is currently insufficient ▪ Fugitive dust lab packing operations is a new system to collect dust and puts absorbents into drums ▪ LED lighting installed in 2009/2010 via federal project works very well. Natural light should be factored into new facility design. ▪ Fire suppression system is a dry chemical powder system which is very expensive to maintain ▪ Explore the idea of the entire facility being all sprinkler and having location to store water reactive chemicals, and limited dry chemical use - review code impact ▪ Floors are double coated epoxy impermeable surface which is very expensive to maintain and update. Best practice should be a coated floor with secondary containment in specific areas where it’s needed. Need a cleanable concrete floor with coating ▪ Area for Reuse storage and sorting. No pesticides or toxic items stored, just motor oil, paint, less toxic cleaners and misc. aerosols for customers to pick up at no charge. ▪ Flammable bulking room (5’x10’) needs to be at least twice as large, maybe three times. Need additional storage of bulk materials, drum staging. Room has/needs enhanced ventilation and LEL meter with visual and audible alarm ▪ Fugitive Dust system may need an upgrade. Mezzanine storage is needed – current space is difficult to access ▪ Roll up doors separate each area of the facility, in an emergency they automatically close. There is a trench/sunk drain to capture any sprinkler liquids and they go to an underground vault outside which gets cleaned and pumped/serviced ▪ Need doors wide enough for easier movement (with drums) in and out ▪ Site could use a smaller dumpster, a 10 yard is good ▪ Facility should have additional storage so empty 55 gallon drums don’t need to be stored outside. This area should be protected from rain (snow). At a minimum empty drum storage could be outdoors but under cover. ▪ Facility should have security and visual fencing around outdoor storage ▪ Current office is for 4 work stations – it’s very cramped, should probably be double in size ▪ Break room should be larger and adjacent to outdoor area for staff. Staff all take lunch at the same time current break room is too small. Break area should connect to the outdoors ▪ Emergency shower is located in the middle of operational area. Shower should have privacy curtains and be very easily accessible to facility operations. It should also be plumbed for warm water and in compliance with OSHA/WISHA regulations for GPM water flow. ▪ Single unisex bathroom does not connect well to shower/ dressing/ locker area. ▪ Some of the office space isn’t in compliance with ADA regulations, so this should be corrected. Task – review and incorporate best practice recommendations from Special Waste

Admin Annex – Kitsap County Public Works Annex ▪ Use similar layout, where facility buildings and covered parking is surrounded by trees and that the exterior design integrates well with surroundings in color and style ▪ New location will be Road shop so needs space for 3-4 offices for supervisors. Needs a crew room/multipurpose room for meetings, breaks. Restroom and locker room all required ▪ Need street sweepers parked indoors as water is stored on board; don’t want it to freeze/ ▪ Need concrete stem walls and/or bollards in the bays ▪ Mezzanine storage is very desirable to minimize building footprint, and to maximize space ▪ As much natural light as possible is desired, high windows or skylights

Stop 2 - 2339 SE Cedar Road, Port Orchard; South Shop

k:\project\33300\33305\admin\meetings\2021-04-22_nksc field trip notes_kcpw review final changes accepted.docx Existing HHWC and Road Maintenance Facilities, and North Kitsap Service Center Field Trip April 22, 2021

▪ This location is in the best shape of all the facilities. Sits on 25 acres, only ½ is in use ▪ Wash bay, self-contained loop system, pressure washier. Vactor trucks sucks out sump weekly ▪ Salt bins under spring structures works well, and are covered by a tarp on the end to eliminate rain from forming a crust on stockpile; should be located away from vehicle storage and equipment as much as practical as its highly corrosive; orient the cover opening to the north, if possible, to limit inclement weather impact ▪ Additional bins are necessary for a total of 10-12 bins which are typically 20’x20’ ▪ Area for stock piles (aside from bins) is needed as well ▪ Need additional barn storage for covered parking of vehicles ▪ Racks for sanders with ladder/stairs and a catwalk is necessary to load. Currently staff use a ladder across the top which is very dangerous. An easily accessible system is needed ▪ Site lacks a strategic flow of access ▪ Fuel station is in a flow blocking location. A covered fuel station is desired, would need a height to allow for largest type of trucks through; if the North Road Shop fuel station has a canopy, there will be a desire for the other shops to follow suit, so it is not a definitive requirement at this time ▪ Flow through maintenance bays for are necessary, at least ½ of all bays should be flow through ▪ Overhead (gantry) crane access engine side, reaching across all bays to at least the front half depth, but must NOT prohibit us of bay as a vehicle repair station. ▪ A bay could be used with built-it storage racks to help with inventory control ▪ Needs to have capacity to store vehicles that rotate around the county’s various locations throughout the year ▪ Chip spreader & paving machines needs cover (not heated) due to abundance of hydraulic hoses ▪ Grinder is sensitive to heat. Roller and sweepers need a covered/ heated space ▪ A cantilevered overhang is highly desirable where it makes design sense along buildings; charging stations may be a good application for cantilevered parking ▪ Solar infrastructure on top of structures could be an option and could support future requirements. There may be grant money; since the County is not taxed, they are not eligible for federal tax credit ▪ Need to at least add electrical conduits for future electric vehicle charging; Keith stated that the conversion of light duty vehicles to electric will be implemented quickly once in production (likely 2022) following other vehicles; There are 3 office spaces and 1 cubicle and currently needs more office space ▪ Need to ensure new space has good internet, Wi-Fi and computer/tablets for staff to do timecards and mandatory trainings; currently all timesheet entries are on 3 standing stations adjacent to each other ▪ All county sheriff vehicles are upfitted at this location but all locations should expect to see sheriff vehicles onsite ▪ KONI Lift required at new site, fits around tires, automatically adjusts, works off charge; they are portable, requiring no flush or surface mounting to floor ▪ Single, 4-post auto lift needed for truck maintenance (fleet pickups) in single bay, drive thru not required ▪ No service pit’s are required ▪ Need air and electricity for every 2 bays ▪ Oils and fluids for every 4 bays ▪ Need a plug just inside the door for access to power equipment if people pull up an the bays are full ▪ Desire power for welding outside of maintenance bay doors for flexibility ▪ Emergency generator required as this is emergency operation center ▪ Grader. Loader, dump truck - need 7 full time, 1 is floater ▪ Vehicles on site for: Gravel, mower, paver, bridge work, chip spreader, roller, sweeper, push, grader, loader, dump

Stop 3: 301 NE Bernt Road, Poulsbo Feedback on overall flow od site: ▪ Problem - limited buildings and space so things are put wherever there us space regardless of functionality ▪ One truck in one truck out is all that can be accommodated at this location ▪ Not having to wind through areas with large vehicles would be ideal ▪ Need a wide berth to drive through, load/unload, hit fuel island along the route ▪ Ingress/egrees is important.

k:\project\33300\33305\admin\meetings\2021-04-22_nksc field trip notes_kcpw review final changes accepted.docx Existing HHWC and Road Maintenance Facilities, and North Kitsap Service Center Field Trip April 22, 2021

▪ Referring to N Kitsap Service Center conceptual site layout, talked about rotating HHW facility 90 degrees to separate public access to it from road operations facility access to create better flow and less conflict ▪ Allowing 53’ truck/trailers combinations within footprint of HHW Facility would require lots of pavement space to maneuver. Discussed the potential internal gate to allow HHW Facility delivery truck/trailers to maneuver in road operations yard to provide egress maneuverability to reduce foot print for HHW facility.

Grouping of materials ▪ Materials that can’t be outside: Glass beads for paint striping in 4’x4’ totes, 25 each, not stackable; cold mix pavement and Salt in non-corrosive covered shelters; paint that has to be placed under cover, away from direct sunlight - bay(s) under vehicle canopy would be sufficient. ▪ Snow plowing and sanding operations: sand stockpiles are located on the west end of the parcel. Currently drivers drive though whole yard for loading and unloading materials; if there are broken down trucks they have to turn around;if Sheriff vehicles are fueling they can’t pass through; drivers can’t get in and out to just get sand and move out; roughly half the trucks will go each direction. ▪ Rename Dirty Ops in describing these uses in project development to Bulk Ops to avoid possible negative connotation ▪ Area of stockpiling. Typical bins are 20x20 and uncovered. Is there a need to stockpile more than that? Just using additional bins (asphalt grindings, sand) Salt needs to be stored away from all equipment. ▪ Guardrail parts. (15 units that have different part numbers, stocked and stacked) Jacques would like to reference the Pierce County facility has allocated bays for within the covered vehicle canopy for these types of materials, including erosion control products and pipe are placed storage racks and shelves are built into the structure; i ▪ Drainage parts – grates, catch basins taking up a fairly large area. 20’ sections of pipe (seasonal storage for emergent projects) ▪ Only the brine machine under cover, where employees operate; the brine storage tank does not need to be placed under cover.

▪ Designing sand boxes with catwalks for safety for loading/unloading; there is a specific sequence of mounting sand boxes in dump truck beds that is shown on signs for staff.

Fleet maintenance ▪ 4 bays is good with additional cantilevered coverage ▪ Parking is generally placed after space and building placement as an afterthought ▪ Being able to have multi directional flow is essential in two of the four bays ▪ Design the site to accommodate for low-boy and truck/pups, that will cover all other vehicles.

▪ TVac and grinder trucks are the largest (tractor low boy) - **Jacques provided turning radius map at beginning of project ▪ Employee parking can be up to 35 spots. Typically 21 Road employees and 1 mechanic, but in summer we have 8 additional employees. 2 sheriffs vehicles at all times, 1 DCD. ▪ Targeting 30 employees (future growth). This programming was based on 30 for future needs. ▪ Fuel and wash close together, separated and in a sequential line. Convenience of cleaning. (largest vehicle would be dump) Currently located about halfway in. Would be best to get it close to the daily workflow. Topping off vehicles is part of the daily tasks. Stacked side by side is not beneficial ▪ Need lots of efficient/bright overhead lighting over the Fleet Shop working area due to low light half of year.Automotive tire shop space is desired for tire storage and mounting equipment. 10x20 area moderate sized tire shop in fleet maintenance ▪ Additional insulation would be good ▪ Radiant floors (? Wishlist item) ▪ Rolling doors are currently 14’high by14’ tall; desire doors to be 16’ high; Need electric openers. If they are panel doors, strongly consider light panels for more natural light. ▪ As much natural light in the shop. Exposure on the top/sides. Super light or white ceilings and walls for mechanic areas. ▪ Floors need to slope to doors. Grates will be right in front of doors, unobstructed as in the winter its wet and need the water to move out ▪ Concrete floors – smooth solid finish (review slip resistance requirements)

k:\project\33300\33305\admin\meetings\2021-04-22_nksc field trip notes_kcpw review final changes accepted.docx Existing HHWC and Road Maintenance Facilities, and North Kitsap Service Center Field Trip April 22, 2021

Security ▪ Sliding gates ▪ Key card access ▪ Video inside and out, full coverage, and must pickup the fuel station (regulatory requirement for HHW Facility)

Other considerations: ▪ Summer time night paving – truck noise, dumping, hauling etc. Some sort of wall near /at bulk storage ▪ Potentially move admin building closer to residential areas and moving bulk storage further away. 53’ trailer need to accommodate 180 degree turn; 74’ design vehicle. See turning radius diagram.

▪ 3 very vocal neighbors on the northeast side of property line ▪ If the Sherriff’s is located onsite, it was stated it would need to potentially have access by public for filing reports, etc. If so, having the office located in the road operations administration office could be problematic due to security gates. Discussed the possibility of locating near or in the HHW facility (say on the 2nd floor) due to the public accessibility to the HHW facility.

Flip Chart Notes at noon Work Session: ▪ Site Planning - Generic site concept and test to fit scheme. Building blocks for NE site concept on PW Property ▪ Site Issues o Stream 150’ buffer o Wetlands – one in middle of property and one along stream ▪ Feedback on site concept: o Ingress/egress is a major consideration o Avoid confined areas o Avoid winding routes o Sequence stops in order of operations (enter, pick up trailer, load materials, fuel up, etc) o Bond Road traffic is a major challenge. Every 35 minute rush cycles from ferry riders o Separate ingress/egress required between HHW & Road Operations facilities. HHW Facility must accommodate semi truck/trailer deliveries. ▪ Materials o Salt stored outside covered (non corrosive) o Glass beads stored inside o Cold mix stored outside and covered o Other materials stored outside and uncovered ▪ On site congestion is an issue with current site ▪ Minor storage for catch basins and guard rails; rail components could be stored on a rack system. ▪ Parking for up to 35 vehicles (21 employees, temp summer employees, sheriff, DCD, and future growth to 30 employees ▪ Snow falling/sliding from roofs onto staff at exterior doors has never been an issue; this however was an issue at the new Pierce Co. facility. Awning over sidewalk adjacent to building was damaged by snow fall. ▪ Tire shop 10x20 is desirable ▪ Insulated shop desirable. Radiant floors? ▪ Rolling doors must be at least 14’ tall, preferably 16’ ▪ Electric door openers are desirable ▪ Glazing in doors/. High walls could be an option for natural light ▪ Natural light is best, white/light walls ceiling ▪ Buildings must drain unobstructed, and be smooth and cleanable ▪ Fuels and wash separated for convenience. No u turns or side by side station, should be linear ▪ Consider a small decant holding facility; the decant ultimate disposal is at a wastewater treatment plant ▪ Sliding gates, key cards, video surveyance inside and out ▪ HHW to cover drums or store inside ▪ Consider showcasing an educational opportunity for natural features, visible from highway. Stormwater or aesthetic ▪

k:\project\33300\33305\admin\meetings\2021-04-22_nksc field trip notes_kcpw review final changes accepted.docx Existing HHWC and Road Maintenance Facilities, and North Kitsap Service Center Field Trip April 22, 2021

Stop 4: 2300 Bond Road NE, Poulsbo

Jeff Massie started the discussion • The geotechnical investigations are completed; the borings and test pits show shallow topsoils, with Vashon Till to depths exceeding the 50’ deep borings • The site has recently been mapped; Mark displayed the topo map, which did not clearly show the critical areas and their buffers boundaries, however all trees within critical areas have been located – if there is a tag on a tree, that means it’s in the critical area or buffer

Jeff Gray led the discussion regarding critical areas: ▪ 2015 ELS critical areas report commissioned by previous property owner has been field verified by Otak. A subsequent critical areas report which references ELS report will be prepared. ▪ Wetland C should not be regulated by the U.S. Army Corps of Engineers as it is not hydraulically connected to a water of the state. ▪ The onsite stream has been upgraded to a fish bearing stream and buffer updated to 150’; there are no hydraulic jumps or other elevation impediments within the reach which was traced hundreds of yards downstream ▪ Discussed strategy of possibly impacting Wetland C and buffers if site planning shows that it may be impractical to avoid impacts. o There are not known wetland banks in which the County could simply purchase credits to mitigate impacts o Would like to have discussions with County departments about the possibility of mitigating wetland impacts on County property; enhancing or creating wetlands on Parks and Recreation-owned properties is viable – Otak did that on an Island County project o On the adjacent parcel, the property owner has committed to daylighting the stream as a condition of interior road construction after negotiating a reduced buffer; perhaps an arrangement could be made to enhance the stream or impound additional flow; mitigating near the impacts has advantages o Jacques asked about the possibility of mitigating on-site; Jeff Gray replied that it’s difficult to justify removing forest in the 150’ stream buffer in order to do this.

Cristina Haworth lead the discussion regarding land use code • Discussed building setback requirements around property; including enhanced setbacks on the NE side of property where residential land uses abut to this use in the Local Area of More Intense Rural Development (LAMRID). • General discussion about landscaping requirements. • There was discussion regarding possible Wetland C impacts, and associated variance requirements. o Cristina said they may be administratively issued, or possibly required a public process such as a hearing. o Under such a scenario, go ahead and issue SEPA threshold determination following 30% design, then go through variance process during County land use/construction permitting process.

Dave Stewart led the discussion regarding onsite stormwater • Code requires evaluating flow control solutions: o Dispersion into forested land – generally requires to be spread laterally, a minimum of 100’ from streams; it may be able to be fit in 150’ stream buffer, but need to evaluate flow path length based on size of impervious area. o Also can/need to evaluate infiltration; as the site is underlain with Vashon Till with low permeability, this may not be feasible o If dispersion or infiltration are not viable, will look at more conventional flow control such as below grade vaults, or open ponds

k:\project\33300\33305\admin\meetings\2021-04-22_nksc field trip notes_kcpw review final changes accepted.docx Existing HHWC and Road Maintenance Facilities, and North Kitsap Service Center Field Trip April 22, 2021

• Water quality treatment will likely need to be enhanced; will consider proprietary filter vaults or biofiltration • There was some discussion should Wetland C need to be impacted, it could be converted to a stormwater pond; if it was to be lost for ecological function, a reasonable alternative use would be to impound water, possibly provide opportunity for educational interpretive signage, and possibly provide a boundary between public HHW facility and staff accessed Road Operations facility

The team walked into the site to the central area wetland

k:\project\33300\33305\admin\meetings\2021-04-22_nksc field trip notes_kcpw review final changes accepted.docx Field Trip Summary

Meeting: Pierce County Central Maintenance Facility Project No.: 33305 Project Name: North Kitsap Service Center Meeting Date: June 2, 2021 Meeting Time: 10:00 AM to 11:30 AM

Attendees: Kitsap County: Jacques Dean Otak: Jeff Massie, Mark Shelby, Michael Payne

This summary supplements the Notkin (a P2S Company) June 3, 2021 Field Investigation Report.

Office Building • The building is primarily a steel framed structure with board form concrete based, window wall and horizontal corrugated metal above (not ideal as it holds dust and dirt) sun shades and a lower canopy system has been damaged • The foyer is dramatic including polished concrete floors, exterior siding, and overhead art • Interior materials are: open metal staircases with perf riser, perf metal ceiling, concrete floor, metal mesh ceiling panels, some gyp board walls/ soffits and frosted glass window wall system at offices • Central corridor with offices and conference areas with operable windows and available light • Sustainable Design interpretive signage greets visitors – project is LEED 2.1 Silver • Meeting rooms have mobile furniture, stacking chairs LED lighting, small kitchenettes and movable partitions to expand meeting spaces, open ceilings • The rain gear drying room looks like an oversized toilet stall with a single rod to support rainwear; good concept, but could have a better rack system • The locker room is unisex, as are at least some of the bathrooms; if staff need to change clothes, they need to go to the restrooms – open ceiling, bolted benches, vented locker, available light, boot drier on concrete pedestal • Laundry facilities are available to staff – 1 washer/ 3 driers and mop sink • Vending machines outside restroom area • Confirmed the workout room upstairs goes mostly unused primarily due to physical nature of the jobs that operate out of the facility • (2) boot cleaning areas with a hose and metal grate are located outside at locker room entrance for washing boots – boot scraper, handrail • Entries have metal walk-off matts and key entry

Central Maintenance Building: Building C • Buildings are open metal structures with white metal (open) ceilings, standing seam metal roof, smooth concrete floors with area striping. There is a 6’ CMU base with horizontal corrugated metal siding above and some gyp infill walls. Metal doors are used thorough-out with lower half kickplate in many places • Mezzanine above (storage?) • Supplies (e.g. guardrail PT wood for railing repairs) are covered at North end • Equipment is checked out from secure structures with roll up doors - hand held power equipment (e.g. string trimmers, chain saws) are accessible via an internal drive aisle through the middle of the structure • Tool repair is in the secure room. Manual checkout with tag system is used to track and maintain tools. k:\project\33300\33305\admin\meetings\2021-06-02_pierce co central maint facility field trip notes - mjp.docx Pierce County Central Maintenance Facility Field Trip Summary June 2, 2021

• Open bays are used for some repair and projects • Metals storage rack could be useful at open bays • Eye wash, mop sink with metal grate station is located near tool checkout • Compressed air and power outlets are provided at each perimeter column (East side)

East Maintenance Buildings: • The plows are in covered parking as are the sand spreaders, accessible by overhead rail cranes; dump truck sand bed inserts are stored on uncovered racks elsewhere • Small gantry crane provided at the inside of each parking stall for installing equipment • Tool boxes flank the center aisle

Enclosed heated parking - South end of the building • Paving and BST equipment, plus vac trucks and street sweepers are in the heated parking on the; the windows were covered to help with security • Additional storage and glass beads are in open bays • Trench drain at center of each drive thru bay • Extended canopy at each drive bay at West side

Salt Storage: • Fabric covered steel frame mounted to concrete foundation; the bins are lined with ecology blocks presumably to help protect the structure

Fuel Tank: • Above ground

Rock, sand and gravel: • Is on-site

Wash Rack: • It has a raised steel walkway which reportedly is rarely used; there have been issues with water freezing in the pipes • An enclosed wash bay is located between fuel and the open wash rack – it was mentioned that the room needed cleaning after a vehicle wash.

Fuel Dispensing: • The tanks are located outdoors • Fuel pumps are located under cover – this was connected to the wash rack

Fleet Maintenance Building: Building B • There is a 10 ton north/south running Gantry crane on the west bay • The fabrication shop has a jib crane, which does not get used that often • The welding exhaust system is inadequate, possibly limited in size due to the space required by the jib crane • The welding table is very useful; the lathe not so much • A sturdy metals storage rack is very useful • The vehicle exhaust system between maintenance stalls works well, it’s located on the same rack as the oil dispensary hoses (every 2 bays) It was suggested to relocate these to the head of the stall where pull through stalls are not needed • One fixed lift was in one bay • Utility sink with metal grate was provided at about (3) locations • Trench drains were located inside each OH door • Mezzanine area is used for storage, but may be underutilized and the gantry crane does not have good access • Mechanic tool boxes tend to be very large; each station has computer work station

k:\project\33300\33305\admin\meetings\2021-06-02_pierce co central maint facility field trip notes - mjp.docx Pierce County Central Maintenance Facility Field Trip Summary June 2, 2021

• All vehicle lifts are portable; they are hooked together so the raise/lower controls work in unison with other lifts • Tire storage is located outdoors; the tire shop is located inside, but all large tires are mounted by outside vendors • A small kitchenette is located in the resource library • Gender specific restrooms are adjacent the resource library • Several offices and parts room were at one end of the building • Exterior roll-up door access was provided for the bulk fluids room – metal grate for cleanout access, and mezzanine was provided with mechanical space available • Horizontally-oriented corrugated metal siding clads the outside of the building above the CMU stem wall, in addition to some interior walls; it holds a lot of dust, and can be a bit unsightly

k:\project\33300\33305\admin\meetings\2021-06-02_pierce co central maint facility field trip notes - mjp.docx June 3, 2021

Field Investigation Report

Date of Visit: June 2, 2021 Visit No. one Time of Visit: Noon Project: Kitsap County North Road Maintenance Facility Weather: Sunny Notkin/P2S Project No.: 2021-0086 Attendees: Darren Schwend

Description of Work Performed:

Darren Schwend toured the Pierce County Road Maintenance Facility to observe the best practices that can be applied to the Kitsap County Facility.

I. Site Observations

Office building: 1. The locker room is equipped with integral boot dryers below the lockers that are supplied with ventilation air from the HVAC system. The boot dryers consist of 1-inch hoses blowing air. 2. A drying room is equipped with hander racks and sealed floor for drying wet gear in the open air. 3. The building is equipped with a VAV HVAC system. 4. Walk way roof damaged by falling snow.

Maintenance building: 1. There is room for improvement in the storage and office heating and cooling system. 2. Natural lighting through high bay windows is a favorite feature. 3. Radiant heaters between bay doors provide heat. 4. The lighting is troublesome, and the operators would prefer LED. 5. The air compressor is large rotary screw which provides reliable service but it’s complex and requires service from select vendors. 6. The ventilation system for offices is heating only and seems to pull in dust and dirt from the shop. They recommend enhanced filtration and cooling for offices in a new building. 7. Centrally located part storage would limit the time walking for parts. 8. The bulk lubricant storage is adequate, but they could have used even more space. 9. The operators recommend siting the maintenance building to maximize natural ventilation. 10. They like the carbon monoxide exhaust reels from the floor because they’re accessible and simple to operate as compared to an overhead system. 11. They would have preferred lube guns between every other maintenance bay for better access. 12. Circuit labeling for electrical outlets would be a huge improvement. There are no labels in the facility. 13. The mechanics like the facility but could use more room to maneuver trucks with trailers.

Wash Rack: 1. Ensure the pressure washers or washing system is automated to prevent inadvertent damage from users. There are gas fired steam pressure washers that can overhead and are damaged if not shut down properly. 2. The facility does not recirculate water. Kitsap County North Road Maintenance Facility Field Investigation Report-June 3, 2021 Page 2 of 3

3. Central vacuum system works well.

Fuel dispensing: 1. The bulk fuel tanks have condensation issues that may be preventable if they were covered or indoors. 2. Fuel tanks are corroding, and staff suggested a roof to limit rust and corrosion. 3. We should include a bulk DEF (Diesel Exhaust Fluid) tank.

Covered parking areas: 1. Uninsulated roof will condense water below the roof and essentially rain under the enclosure at times. 2. Birds nest in the structure. Nets or other prevention is recommended.

Rainwater capture: 1. Rainwater used for toilet flushing. 2. Stormwater capture used for water in sweeper trucks and tanker trucks for dust control.

Darren M. Schwend, P.E., HFDP, LEED BD+C Credentials Associate Principal DMS:yy V:\Projects\21 0001-0100\21-0086 Kitsap Cty N Rd Maint Shop Fac\Design Phase\Field Survey\Mechanical\Field notes - Pierce County Maintenance.docx

P2S Inc.

920 5th Avenue, Suite 2300 206.448.1911 P2SINC.COM Seattle, WA 98104 Kitsap County North Road Maintenance Facility Field Investigation Report-June 3, 2021 Page 3 of 3

______[Name], [Credentials] [Title]

[AUTHOR INITIALS]:[typist initials]

S:\MASTER\Notkin-P2S Templates\Field Investigation Report.docx

P2S Inc.

920 5th Avenue, Suite 2300 206.448.1911 P2SINC.COM Seattle, WA 98104 Appendix E Multi-criteria Decision Matrix, August 3, 2021 by Otak, Inc. NORTH KITSAP SERVICE CENTER MULITI-CRITERIA DECISION MATRIX Criteria Site Alternative A Site Alternative B

Building Layout Advantages: Advantages: & Site • Wetland C and its buffer provide a good natural vegetation • Impacting and mitigating Wetland C and buffer offers superior Utilization buffer between the publicly accessed Moderate Risk Waste maneuverability and storage space Facility and the remaining Road Maintenance & Operations functions • Provides adequate space to locate all the program elements Challenges: • Less space for materials storage Vehicle Advantages: Advantages: Maneuverability • Provides sufficient maneuverability for large vehicles and • Better circulation and maneuverability compared to Alternative A equipment to buildings and materials storage Challenges: • Less room to maneuver than Alternative B County Permit Advantages: Advantages: Requirements • No purpose/need statement or variance process needed • Can better meet Kitsap County Code land use requirements of the regarding wetland impact other parts of the site development Challenges: • The County will need to justify any wetland fill through the purpose/need statement and the variance process Natural Advantages: Challenges: Resource • Maintains Wetland C and its buffer • Displaces Wetland C and its buffer Conservation Challenges: • Less opportunity to leave natural vegetation buffers on the remainder of the site Expandability Challenges: Advantages: • Not as much flexibility for expansion • Better ability to expand buildings and site features • Impacting Wetland C and its buffer is assumed to be more difficult to perform in the future if necessary Public Advantages: Challenges: Interpretation • Wetland C and buffer are located near the Moderate Risk • Since it’s more ideal to have interpretive signage adjacent to critical Advantages Waste Facility (MRWF), offering a good opportunity to have areas and buffers, there is less opportunity with Alternative B for this interpretive signage adjacent to the publicly accessed to be located convenient to the MRWF MRWF Cost Advantages: Challenges: • $950K to $1,406K less expensive than Alternative B • $950K to $1,406K more expensive than Alternative A

K:\Project\33300\33305\ProjectDocs\Site Planning\20210706 site analysis multi criteria decision matrix.docx Appendix F Relative Cost Estimate, August 3, 2021 by Otak, Inc. North Kitsap Service Center Relative Cost Estimate

Item Description Unit Unit Price Site Alternative B No Site Alternative A Wetland C and buffer filled in and mitigated Wetland C and buffer intact offsite

Quantity Total Amount Quantity Total Amount

PREPARATION Site clearing AC $15,000.00 $8 120,900 10.4 $156,600

SURFACING AND PAVEMENTS Hot Mix Asphalt Pavement TON $125.00 $8,588 1,073,500 11,120 $1,390,000 Crushed Surfacing Base Course TON $30.00 $17,176 515,280 22,240 $667,200 Concrete Sidewalks SY $43.00 $3,820 164,260 3,314 $142,502

OTHER ITEMS Fee in Lieu Wetland Mitigation (low range) $468,000 Fee in Lieu Wetland Mitigation (high range) $924,000

TOTAL (low range) $1,873,940.00 $2,824,302.00 TOTAL (high range) $3,280,302.00 DELTA (low range) $950,362.00 DELTA (high range) $1,406,362.00

K:\Project\33300\33305\ProjectDocs\CostEstim\20210731 Alternatives Analysis Cost Est.xlsx Figures . Figure 1 DRAFT Preliminary Site Plans, July 22, 2021 by Otak, Inc.

. Figure 2 Vehicle Turning Movement Simulations, July 23, 2021 by Otak, Inc.

. Figure 3 Floor Plans, July 7, 2021 by Otak, Inc.

. Figure 4 Grading Plans, July 13, 2021 by Otak, Inc. Figure 1 DRAFT Preliminary Site Plans, July 22, 2021 by Otak, Inc. KEY NE ROVA RD

1 Admin. & Crew Building / 12 Wash bays Vehicle Maintenance Shop 13 Fuel bays 2 Moderate Risk Waste Facility 14 Stream 3 Sander boxes 15 Working stock / bulk storage 4 Medium vehicle parking 16 Site access / drive aisle 5 Small vehicle parking 150’ 17 Vehicular sliding gate 6 X-small vehicle parking 18 Vehicular swing gate 40’ 7 Gravel & sand storage 19 Trash 8 Septic vault & drain field 20 Generator 9 Laydown area 1 6 10 Bulk storage 11 Material bins 20 5 8 14 Buildings Covered parking Covered storage Wetland 5 Uncovered storage Septic 4 Fuel & wash bays Fencing & gates 7 Landscape Critical area buffer 17 3 15 SITE DATA 16 9

8 Total Site Area = 699,095 sf = 16.05 acres

12 Alternative A Usable Space = 459,065 sf = 10.54 acres BOND RD NE 11 10 Stream, Wetland C and associated buffers protected 2 Wetland C 20 19 13 50’ Preliminary Site Plan - Alternative A LAMRID RD DRAFT 18 NORTH KITSAP 60 0 60 120 18 SERVICE CENTER SCALE IN FEET

PRELIMINARYDRAFT PRELIMINARY SITE PLAN - ALTERNATIVE 1 JULY 20, 2021 North Kitsap Service Center KEY NE ROVA RD

1 Admin. & Crew Building / 12 Wash bays Vehicle Maintenance Shop 13 Fuel bays 2 Moderate Risk Waste Facility 14 Stream 3 Sander boxes 15 Working stock / bulk storage 4 Medium vehicle parking 16 Site access / drive aisle 5 Small vehicle parking 150’ 17 Vehicular sliding gate 6 X-small vehicle parking 18 Vehicular swing gate 40’ 7 Gravel & sand storage 19 Trash 8 Septic vault & drain field 20 Generator 9 Laydown area 1 10 Bulk storage 20 11 Material bins 10 14 8 Buildings Covered parking 10 Covered storage Wetland Uncovered storage Septic Fuel & wash bays Fencing & gates 15 Landscape Critical area buffer 17 7 5 SITE DATA 16 6 3 9 Total Site Area = 699,095 sf = 16.05 acres

BOND RD NE Alternative B Usable Space = 517,608 sf = 11.88 acres Stream and associated buffer protected, Wetland C eliminated 11 2 and mitigated off-site 13 20 19 4

LAMRID RD 8 Preliminary Site Plan - Alternative B 18 12 DRAFT NORTH KITSAP 60 0 60 120 18 SERVICE CENTER SCALE IN FEET

PRELIMINARYDRAFT PRELIMINARY SITE PLAN - ALTERNATIVE 1 JULY 20, 2021 North Kitsap Service Center Figure 2 Vehicle Turning Movement Simulations, July 23, 2021 by Otak, Inc. North Kitsap Service Center

IS STORAGE ALTERNATIVE A TURNING MOVEMENTS WB-67 IS STORAGE RR/

BREAK PARKING TIRE & SHOP STORAGE OUTDOOR COVERED AREA SHOP GENERAL FABRICATION PURPOSE SHOP HEAVY MAINTENANCE BAY HEAVY MAINTENANCE BAY HEAVY MAINTENANCE BAY HEAVY MAINTENANCE BAY MEZZANINE CHG RR/ SHR RR/ CHG ENTRY

DRYING

W CUSTODIAL SHR CHG RR/ D STORAGE PARKING OFFICE ESD MANAGERS/ LEAD MECH OFFICE LARGE TOOL/ EQUIPMENT RECYCLE LUBE/COMP. COMP X SMALL VEHICLE

SMALL VEHICLE WB IST

PARKING LOCKERS HAZMAT STORAGE AREA BREAK REST ROOMS SURVEY CREW STORAGE

53 SMALL VEHICLE ENTRY PARKING glass beads SMALL VEHICLE

27.9 ROAD: TOOL REPAIR/ TOOL ROOM ELEV PARKING RR/ RR/ LOBBY SMALL VEHICLE

PARKING MISC STORAGE BAY

SMALL VEHICLE SEPTI SEPTIC PARKING VAULT GENERATOR SMALL VEHICLE PARKING

SMALL VEHICLE DRAIN FIELD PARKING

MEDIUM VEHICLE PARKING SMALL VEHICLE MEDIUM VEHICLE PARKING PARKING SMALL VEHICLE MEDIUM VEHICLE PARKING PARKING SMALL VEHICLE MEDIUM VEHICLE PARKING PARKING SMALL VEHICLE MEDIUM VEHICLE PARKING Max 68.5° Horiz PARKING SMALL VEHICLE MEDIUM VEHICLE PARKING 23.5 Max 10° Vert PARKING SMALL VEHICLE 4 17.4 4.2 MEDIUM VEHICLE PARKING PARKING SMALL VEHICLE PARKING 43.5 4 2.5 MEDIUM VEHICLE PARKING

MEDIUM VEHICLE PARKING WB-67 - Interstate Semi-Trailer Overall Length 73.501ft IS Overall Width 8.500ft STORAGE GRAVEL SAND Overall Body Height 13.500ft GATE Min Body Ground Clearance 1.334ft SANDER BOX SANDER BOX SANDER BOX SANDER BOX SANDER BOX SANDER BOX SANDER BOX SANDER BOX SANDER BOX SANDER BOX

Max Track Width 8.500ft BRINE PRODUCTION/ BUFFER TANK Lock-to-lock time 6.00s AVERAGING

Max Steering Angle (Virtual) 28.40° WORKING STOCK/ BULK STORAGE

SALT STORAGE LAYDOWN AREA

SEPTI MACHINE NICHE ICE DRAIN FIELD SEPTIC VAULT ATERIAL COVERED STORAGE BINS

LOADING WASH BAY WASH BAY DOCK WASH BAY EQUIPMENT BUFFER ROOM STORAGE AVERAGING BULK

40 yard recycle bin

STORAGE

SORTING

RR

RR

SHOWER DRESSING JAN REUSE PRODUCT OUTDOOR BREAK GENERATOR CONF FLEX OFFICE STREET SWEEPINGS STOR

IT ROOM FUEL TANKS

SHERIFF

FUEL FUEL TRAS FUEL ISLAND FUEL TANKS

FUEL FUEL ROAD STRIPING STORAGE

50197 243.60 OHL-POL

BUFFER AVERAGING

WB I ST

WB I ST

WB I ST North Kitsap Service Center ALTERNATIVE A TURNING MOVEMENTS TRUCK AND PUP

TRUCK AND PUP TURNING ENVELOPE

60' North Kitsap Service Center

STORAGE ALTERNATIVE B TURNING MOVEMENTS SHOP & TIRE

AREA COVERED OUTDOOR

SHOP

FABRICATION

WB-67 GENERAL PURPOSE SHOP PURPOSE

BAY MAINTENANCE HEAVY

BAY MAINTENANCE HEAVY

BAY MAINTENANCE HEAVY

DEPARTMENT SERVICE EQUIPMENT ESD: BAY MAINTENANCE HEAVY

MEZZANINE

STORAGE EQUIPMENT LARGE TOOL/ LARGE

OFFICE LEAD MECH LEAD MANAGERS/ ESD

OFFICE

STORAGE HAZMAT

ROOMS REST

COMP LUBE/COMP. RECYCLE TOOL ROOM TOOL TOOL REPAIR/ TOOL ROAD: beads glass

STORAGE CREW SURVEY STREAM

GENERATOR

BAY MISC STORAGE MISC

M H M V 27.9

WB I ST RR/ O L CHG CHG CHG O W O B H M B G C M T W RR/ L

M S A V LOCKERS SHR SHR RR/ RR/

D W BOOT CUSTODIAL

WORKING STOCK/ BULK STORAGE BOOT DRYING ENTRY LOBBY/ RR/ CUSTODIAL SEPTIC WB-67 - Interstate Semi-Trailer VAULT Overall Length 73.501ft Overall Width 8.500ft DRAIN FIELD Overall Body Height 13.500ft Min Body Ground Clearance 1.334ft BULK STORAGE Max 68.5° Horiz 23.5 Max 10° Vert 4 17.4 4.2 STREAM 43.5 4 2.5 WB-67 - Interstate Semi-Trailer

Overall Length 73.501ft

Overall Width 8.500ft STORAGE BULK STOCK/ WORKING PARKING SMALL VEHICLE SMALL

Overall Body Height 13.500ft PARKING

SMALL VEHICLE SMALL PARKING

SMALL VEHICLE SMALL

PARKING

SMALL VEHICLE SMALL

Min Body Ground Clearance 1.334ft PARKING GRAVEL SAND

SMALL VEHICLE SMALL

PARKING

SMALL VEHICLE SMALL

PARKING

Max Track Width 8.500ft VEHICLE SMALL

PARKING

SMALL VEHICLE SMALL PARKING SMALL VEHICLE SMALL

Lock-to-lock time 6.00s PARKING

SMALL VEHICLE SMALL PARKING

SMALL VEHICLE SMALL

PARKING

SMALL VEHICLE SMALL

Max Steering Angle (Virtual) 28.40° PARKING

SMALL VEHICLE SMALL

PARKING SMALL VEHICLE SMALL SANDER BOX SANDER BOX

SALT STORAGE

X SMALL

VEHICLE SANDER BOX SANDER BOX PARKING LAYDOWN AREA SANDER BOX SANDER BOX

BRINE PRODUCTION/ TANK SANDER BOX SANDER BOX COVERED STORAGE WB I ST

LOADING DOCK SANDER BOX SANDER BOX

40 yard recycle bin STREET

STORAGE SWEEPINGS FUEL TANKS SORTING FUEL FUEL ROAD RR

RR STRIPING

SHOWER FUEL ISLAND MEDIUM VEHICLE STORAGE DRESSING PARKING JAN FUEL TANKS REUSE PRODUCT FUEL FUEL MEDIUM VEHICLE OUTDOOR BREAK PARKING CONF

FLEX GENERATOR OFFICE STOR MEDIUM VEHICLE PARKING IT ROOM

SHERIFF MEDIUM VEHICLE PARKING

MEDIUM VEHICLE PARKING

MEDIUM VEHICLE PARKING

MEDIUM VEHICLE PARKING

MEDIUM VEHICLE PARKING

MEDIUM VEHICLE PARKING MACHINE NICHE ICE

WASH BAY WASH BAY SEPTIC VAULT WASH BAY EQUIPMENT DRAIN FIELD ROOM

WB-67 - Interstate Semi-Trailer North Kitsap Service Center ALTERNATIVE A TURNING MOVEMENTS TRUCK AND PUP

TRUCK AND PUP TURNING ENVELOPE

60' Figure 3 Floor Plans, July 7, 2021 by Otak, Inc.

Figure 4 Grading Plans, July 13, 2021 by Otak, Inc.

I I S �AINTAIN EXI TING /; R O ADE/VEG E ATI N AS O T MUCH AS P SSIBLE l/ f;/

RETAININGW ( • I I

111 / 1 ;p� 0. 1 fK I * ·. AINTAIN EXISTI M R G ADE/VEG ETA O MUCH AS P SSI ·*

€ 00 w •

0 0 • 0

0 •

;l- f

�"

L

..