M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
CHAPTER – 1 INTRODUCTION
1.1 Preamble
M/s. Paragon Poly Resins LLP is proposing to establish a greenfield project to manufacture different types of Resins at Survey No.: 782, Village : Jakhwada, Taluka : Viramgam, District : Ahmedabad, Gujarat. A detail of proposed product is as given below:
Table 1.1: Details of Proposed Product Production Capacity Sr. No. Name of Product (MT/Month)
1. Alkyd Resin 2000
2. Polyamide Resin 1500
3. Polyester Resin 2000
4. Acrylic Resin 2500
5. Rosin Ester 500
6. Epoxy Resin 1500
7. Phenol Formaldehyde Resin 25
8. Melamine Formaldehyde Resin 25
9. Urea Formaldehyde Resin 25
10. Ketonic Resin 5
Total 10080
Note: Please note that above stated Resins will be used for sale purpose.
T. R. Associates (Ahmedabad) Chapter-1: Introduction NABET Accredited 1.1
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
M/s. Paragon Poly Resins LLP has a total land area of 16,532 m2. Out of the stated land area approximately 5,546 m2 is green belt area (approx. 33.55 % of the total land area). Land documents such as Dastavej copy is attached as Annexure – 2 A. The unit has already applied for Non Agricultural (NA) permission and the same is attached as Annexure – 2 B.
The total estimated cost of the proposed project is Rs. 9.50 Crores. Total budget allocation towards Environmental Management Facilities will be approx. Rs. 82 Lakhs.
1.2 Purpose of the EIA Report
The proposed product Resin, being synthetic organic chemicals falls under Category 5(f) as stated in Environment Impact Assessment Notification Published on 14th September, 2006. Further, the location of proposed project is outside the notified industrial estate and fall in Small Scale Industrial Unit criteria as per the Notification dated 25th June 2014. Undertaking stating that unit will comply all these three conditions is attached as Annexure - 5. Hence, project proponent has to obtain the Environmental Clearance from the State Environmental Impact Assessment Authority (SEIAA), Gujarat. As per the requirements of the notification, an application was submitted to on 9th August 2018 along with Form-1, Pre-Feasibility Report and draft Terms of Reference (TOR). The SEIAA has issued the TOR wide letter no. SEIAA/GUJ/TOR/5(f)/1389/2018 dated 31st December 2018 (refer Annexure – 1). Based on the TOR letter issued by the SEIAA, an Environmental Impact Assessment (EIA) report has been prepared covering all aspects of the TOR.
The purpose of the preparation of Environment Impact Assessment (EIA) report is not only to obtain Environment Clearance from State Environmental Impact Assessment Authority (SEIAA), Gujarat, but also to understand the likely impacts and to take Environment Protection/Management measures during and after commissioning of the project.
T. R. Associates (Ahmedabad) Chapter-1: Introduction NABET Accredited 1.2
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
1.3 Promoters and their Background Table 1.2: Promoters and their Background Sr. Educational Name of Directors Contact No. Address Experience No. Qualification ȀͻͲ͵ǡǡǤ 1 Ǥ ͻͺͻͺͲ͵ʹ͵ͺ ǤǤȋȌ ǡǡǤ ͳͷ
ͷȀǡǡǤ Ǥ 2 ͻͺͻͺͲ͵ͲͻͲ ǡǡ ͳͷ
ȀͲ͵ǡǡ 3 ͻͶʹͲͲʹͺʹ ǤǤ ǡ ͳͷ
ͷǡ ǡǤǤǤǡ 4 ͻͺʹͷʹʹʹ͵Ͳʹ ǤǤ ǡ Ǥ Ƭ ͳͷ
ȀͲʹǡǡǤ 5 ͻͺͻͺ͵ʹ͵ͺ ǤǤ ǡǡǤ ͳͷ ȀͶͲͷǡ ǡǤ 6 ͻʹͶͳͳͲͳ Ǥ ǤȋȌ ǡǦǡ ͳͲ ǡǤ ȀͲʹǦͲ͵ǡ ǤǦͳǡǤ Ƭ 7 ͻͺʹͶʹͺͶͺͻ͵ ǤǤ ǡ ǡ Ǥ ʹͲͳͳ ʹǡ ǡ 8 ΪͳǦͷͶͲǦͷʹͲͻͲͷͺ ǤǤ ǡǤ
T. R. Associates (Ahmedabad) Chapter-1: Introduction NABET Accredited 1.3
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
1.4 Need of the Project and its Importance to the Country
Resins are predominantly used in the wood based product manufacturing industry as adhesives. Growth of the resin market is strongly correlated to construction/ remodeling activity (which accounts for over 50% of consumption), and to a lesser degree, to the automotive industry.
The proposed products like different types of Resins mainly used to manufacture Laminated Sheets, paints, thickener, roofs etc. Different uses of different types of resins are shown below :
Sr. Name of CAS NO. End Use No. Product
Paints, Pigment paste, Ink, 1 Alkyd Resin 68333620 Varnish, etc. Polyamide 2 63428842 Ink, Pigment paste, etc. Resin Lamination sheet, Mold, roof, 3 Polyester Resin Not available general purpose, etc.
4 Acrylic Resin 028262-63-7 Paints, Emulsion, Thickener, etc.
5 Rosin Ester 8050315 Paints, varnish, Ink, etc.
Lamination sheet, Varnish, 6 Epoxy Resin 25068386 Pigment paste, etc. Phenol 7 Formaldehyde 9003354 Lamination sheet, roof, mold, etc. Resin Melamine Lamination sheet, roof, paints, 8 Formaldehyde 9003081 varnish, etc. Resin Urea Lamination sheet, roof, paints, 9 Formaldehyde 27967299 varnish, etc. Resin
10 Ketonic Resin 25054062 Lamination adhesive, etc.
T. R. Associates (Ahmedabad) Chapter-1: Introduction NABET Accredited 1.4
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
Good quality raw materials are available at cheap rates in India, enabling the manufacturing at low cost. This increases the profit margin as compared to other players in the world. To meet the current and future market demand, the project proponent intends to start a new unit.
The proposed project will contribute revenue to the Central & State exchequer in the form of applicable taxes. Indirect contribution to the Central & State exchequer will be there due to Income by way of registration of trucks, payment of road tax, income tax from individual as well as taxes from associated units. Thus, the proposed project will help the Government by paying different taxes from time to time, which is a part of revenue and thus, will help in development of economy as well as local physical infrastructure for further boosting of industrial development with sustainable approach as the industries need to maintain good environment & safety condition to get better market place.
1.5 Location of the Proposed Project and Siting Criteria
The proposed project is to be located at Survey No.: 782, Village: Jakhwada, Taluka: Viramgam, District: Ahmedabad, Gujarat. It is situated at Latitude: 23° 4' 13.09" N and Longitude: 72° 8' 44.72"E. Nearest major city is Viramgam which is about 9.50 km far from the project site in WNW direction. National Highway 947/ State Highway SH - 17 is approx. 1.32 km away from the project site in North direction.
Co-ordinates of all corners of the site
Point Latitude Longitude A 23.070817° N 72.146333° E B 23.070769° N 72.144996° E C 23.069688° N 72.145182° E D 23.069960° N 72.146578° E
T. R. Associates (Ahmedabad) Chapter-1: Introduction NABET Accredited 1.5
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
Figure: 1.1 Location of the Project Site
1
Source : Google Earth
Figure: 1.2 A Photograph of the Project site with surrounding area
1HDUWR%RXQGDU\$' $W%RXQGDU\&'
T. R. Associates (Ahmedabad) Chapter-1: Introduction NABET Accredited 1.6
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
1HDUWR%RXQGDU\%& $W%RXQGDU\$%
Figure: 1.2 B Photograph of the Project site
The proposed site has been selected due to its proximity to availability of raw materials, consumer centers and infrastructure facilities like power, water, communication etc. The siting criteria described in Section 4.2.4 of Technical EIA Guidance Manual (TGM) for Synthetic Organic Chemical Industry has been considered and the same are given in the following table.
While siting industries, care is taken to minimize the adverse impact of the industries on immediate neighborhood as well as distant places. Some of the natural life sustaining systems and some specific land uses are sensitive to
T. R. Associates (Ahmedabad) Chapter-1: Introduction NABET Accredited 1.7
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
industrial impacts because of the natural and extent of fragility. With a view to protect such sites, the industries may maintain the following distances, as far as possible, from the specific area listed below, also there is general siting factor including as follows;
Table 1.3: General Siting Criteria
Details Requirement Compliance No forest land shall be No forest land is involved in converted into non-forest the proposed project site Forest activity for the sustenance of the industry. No prime agricultural land NA permission application shall be converted into is submitted to respective Agricultural industrial site. authority for this project. Land NA permission application is attached as Annexure–2B. Enough space should be The total acquired land is provided for storage area, 16,532 m2. Enough space plant area, greenbelt area, will be provided according Utilities, Raw material to the requirement. This can Layout storage, Fly ash, other storage be verified from the Lay-out like solid wastes so that these given in the Chapter-2. could be available for possible reuse.
At the time of siting of the Nearest major habitation is industry, if the notified limit Ahmedabad which is about of any major settlement is 30.35 km far from the Major settlements found to be within 50 km project site in ESE direction. (3,00,000 from the project boundary, population): the spatial direction of growth of the settlement for at least a decade must be assessed.
T. R. Associates (Ahmedabad) Chapter-1: Introduction NABET Accredited 1.8
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
Details Requirement Compliance Preferably 5 km depending on Ecologically the geo-climatic conditions No ecologically sensitive and/or otherwise the requisite distance may be area falls within 5 km radius Sensitive areas decided appropriately by the distance. Environmental agency. National Highway 947/ Preferably ½ km. away from Transport / State Highway 17 are highway and railway line. Communication approx. 1.32 km away from system the project site in North direction. Preferably ½ km away from None within 10 km radius Coastal areas high tide line (HTL) of the project site. Preferably ½ km away from None within 10 km radius flood plain or modified flood of the project site. Flood plain of the plain affected by dam in river line system upstream or flood control system.
1.6 Scope of EIA Study
The EIA study includes determination of baseline conditions, assessment of the Impacts on the environment due to the construction and operation of the project and making recommendations on the preventive measures to be taken, to minimize the impact on the environment to acceptable levels. A suitable post-study monitoring program will be outlined. Environment Management Plan will be given based on the emissions and feasibility report. As per the guidelines, the generic structure of EIA is given in EIA notification dated 14th September, 2006 is maintained. The scope of study based on ToR/ MoEFCC / CPCB guidelines is tabulated below;
Table 1.4: Scope of the Study
Environmental No. of Explanations Aspects Locations Meteorology 1 One season site specific meteorological status of the study was carried out for prediction of
T. R. Associates (Ahmedabad) Chapter-1: Introduction NABET Accredited 1.9
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
Environmental No. of Explanations Aspects Locations ground level concentration in downwind direction. Ambient Air 8 The prevailing ambient air quality status was Quality established through a network of stations monitored during the period of October - 2018 to December - 2018. The ambient air quality monitoring as per the parameters prescribed in TOR was carried out within the study area of 10 km. Prediction of impacts on air quality due to proposed operations were carried out through application of air quality models. Water Surface The water quality data as per CPCB Water (8) guidelines were analyzed to established & baseline water quality of study area of 10 km. Ground The wastewater generation, its Water (8) characterization and management were carried out which was used in assessing the impact of the project on water environment. Noise 8 Noise level measurements were carried out around the project site, data were also analyzed for establishing baseline status of noise and it was used in assessing the impact of the project on noise & vibration environment. Soil 8 Soil samples were collected and have been analyzed to understand nutrient status as well as assessing the impact of the project on soil environment. Ecology -- Flora and fauna species was listed based on the available secondary information. Field based primary data collection for biodiversity related data was carried out within 10 km radius around the proposed project.
T. R. Associates (Ahmedabad) Chapter-1: Introduction NABET Accredited 1.10
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
Environmental No. of Explanations Aspects Locations Geology & -- Geological and geo-hydrological Geo-hydrology investigation work has been carried out in and around the study area to know the status of the study area. Risk and -- Risk assessment study has been carried out to Hazard evaluate risk, assess its impact associated to Analysis the proposed project activity and plan the appropriate action to control risk by the most economical means. Socio-economic - Existing baseline status of the socio-economic data profile of the study area with reference to demographic structure, provision of basic amenities, health status incorporating economic pattern in the nearby rural areas (10 km radius) were undertaken, it was used in assessing the impact of the project on socio- economic environment.
1.7 Regulatory Frame Work
The proposed project will abide and function under the purview of the following Rules, Acts & Regulations which are formulated by the government to protect environment and maintain good environmental conditions.
T. R. Associates (Ahmedabad) Chapter-1: Introduction NABET Accredited 1.11
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
Table 1.5: Regulatory Frame Work
Sr. Legal Instrument Concern Authority or Bodies Applicability No. (Type, Ref., Year)
1 Air (Prevention and CPCB and SPCB/UTPCC Air emission from Control of Pollution) stack attached to TFH Act, 1981 and its & D.G. Set subsequent
amendments
2 Water (Prevention and CPCB and SPCB/UTPCC Wastewater generation Control of Pollution) from industrial Act, 1974 and its activities as well as subsequent from domestic amendments activities.
3 Water (Prevention and CPCB and SPCB/UTPCC Wastewater generation Control of Pollution) from industrial Rules, 1975 and its activities as well as subsequent from domestic amendments activities.
4 The Environment Ministry of Environment and Production of (Protection) Act, 1986 & Forests, & Climate Change Synthetic Organic Environmental (MoEF&CC), CPCB and Chemicals (Different (Protection) Rules, 1986 SPCB/UTPCC. types of Resins)
and their subsequent amendments
5 Hazardous and Other MoEF&CC, CPCB, SPCB/UTPCC, Generation of Solid & Wastes (Management DGFT, Port Authority and Hazardous Wastes and Transboundary Customs Authority from industrial Movement) Rules, 2016 activities.
6 Manufacture Storage MoEFCC, Chief Controller of Storage of hazardous and Import of Imports and Exports, CPCB, chemicals within the Hazardous Chemicals SPCB/UTPCC, Chief Inspector of plant premises. Rules, 1989 amended Factories, Chief Inspector of Dock
T. R. Associates (Ahmedabad) Chapter-1: Introduction NABET Accredited 1.12
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
Sr. Legal Instrument Concern Authority or Bodies Applicability No. (Type, Ref., Year) 2000 Safety, Chief Inspector of Mines, AERB, Chief Controller of Explosives, District Collector or District Emergency Authority, CEES under DRDO
7 Chemical Accidents Ministry of Environment & Storage of hazardous (Emergency Planning, Forests &Climate Change, Chief chemicals within the Preparedness and Controller of Imports and plant premises. Response) Rules, 1996 Exports, CPCB, SPCB/UTPCC, Chief Inspector of Factories, Chief Inspector of Dock Safety, Chief Inspector of Mines, AERB, Chief Controller of Explosives, District Collector or District Emergency Authority, CEES under DRDO.
8 EIA Notification, 2006 MoEF&CC, SPCB/UTPCC Production of and its subsequent Synthetic Organic amendments Chemicals
9 Public Liability MoEF&CC, District Collector Industrial units Insurance Act, 1991 manufacturing amended 1992 & Public chemical products and Liability Insurance requirement of 70 Rules, 1991 and its workers subsequent amendments
10 The Factories Act, 1948 Ministry of Labour, DGFASLI Industrial units and Directorate of Industrial manufacturing Safety and Health/Factories chemical products and Inspectorate requirement of 70 workers
T. R. Associates (Ahmedabad) Chapter-1: Introduction NABET Accredited 1.13
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
Sr. Legal Instrument Concern Authority or Bodies Applicability No. (Type, Ref., Year)
11 The Explosive Act ,1884 Ministry of Commerce and Storage of explosive Industry (Department of materials Explosives)
12 Noise Pollution CPCB and SPCB/UTPCC Noise may be (Regulation and generated due to Control) Rules, 2000 industrial activities and its amendments
M/s. T. R. Associates (NABET Accredited EIA Consultant) was appointed by M/s. Paragon Poly Resins LLP to carry out the Environmental Impact Assessment study for their proposed project of manufacturing of different types of Resin.
T. R. Associates (Ahmedabad) Chapter-1: Introduction NABET Accredited 1.14
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. CHAPTER – 2 PROJECT DESCRIPTION
2.1 Introduction
M/s. Paragon Poly Resins LLP is proposing to manufacture different types of Resin at Survey No.: 782, Village: Jakhwada, Taluka: Viramgam, District: Ahmedabad, Gujarat. Manufacturing of Resin is covered under Category 5(f) ‘B’ as per the EIA Notification 2006 and its subsequent amendments.
2.2 Project Location
The proposed site is located at Survey No.: 782, Village: Jakhwada, Taluka: Viramgam, District: Ahmedabad, Gujarat. Co-ordinates of the proposed project site are: Latitude: 23° 4' 13.09"N and Longitude: 72° 8' 44.72"E.
The index map is given in Figure 2.1.
Google map showing surrounding area in 0.5 km radius, 1 km radius, 5 km radius and 10 km radius from the project site are given as Figure 2.2.
Topo sheet showing surrounding area in 10 km radius from project site is given as Figure 2.3.
Site History
The selected site for the proposed project was earlier an agricultural field. Different types of agriculture crops such as Bajri, Wheat, Vegetables and Groundnut etc. were grown before the Non Agriculture (NA) permission obtained by the project proponent. Land possession document is attached as Annexure – 2 A and NA Application is attached as Annexure – 2 B.
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.1
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. Figure 2.1: Index Map
India Map Gujarat State Map
Google Image showing Project Site Ahmedabad District Map
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.2
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. Figure 2.2: Google Image showing surrounding 0.5, 1, 5 & 10 km radius area from the project site
1
White circle – 0.5 km radius
1
Blue circle – 1 km, Red circle – 5 km, White circle – 10 km
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.3
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. Figure 2.3: Topo sheet showing surrounding 10 km radius area from the project site
1
ϮϯΣϰΖϭϯ͘ϬϵΗE ϳϮΣϴΖϰϰ͘ϳϮΗ
3URSRVHG3URMHFW6LWH0V3DUDJRQ3RO\5HVLQV//3
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.4
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. 2.2.1 Justification of Site Selection
The unit is to be located at Jakhwada Village in Viramgam Taluka & Ahmedabad District and site selection was guided by many factors like infrastructure, availability of land, water sources, fuel, transportation, power availability etc. Specific site selection criteria for the proposed project are given below;
x The project site is highly developed with all basic infrastructure facilities such as proximity to man power, electricity, water supply, transportation, telecommunication systems etc. x Proposed project site is approximately 1.32 km away from National Highway No. 947 / State highway No. 17 which is well connected to other state highways as well as national highway. Transport facilities for all over India are sound at project site. x The project site is intended for the industrial purpose and thus no displacement of population will take place. x There is no protected area notified under the Wild Life (Protection) Act (1972) & Eco-sensitive area notified under the Environment (Protection) Act- 1986 exists within 10 km radius areas from the project site. x Availability of requisite skilled, semi-skilled and unskilled labour from local area.
2.2.2 Salient Features of the Proposed Project Site
Salient features in the surroundings area of the proposed site as well as infrastructure availability with approximate aerial distance and direction are as given below:
Table 2.1: Salient Features of the Proposed Project Site Sr. Important Features Description No. 1 Location Survey No.: 782, Village: Jakhwada, Taluka: Viramgam, District: Ahmedabad, Gujarat. 2 Project Site Co-ordinates Latitude: 23° 4' 13.09" N
Longitude: 72° 8' 44.72" E
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.5
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. Sr. Important Features Description No. 3 Temperature Range ʹͲͶͳǤͺͲ
4 Mean Sea Level 30 m
5 Annual Rain Fall 736 mm (Dependable)
6 Nearest Railway Station Ȃ ͳͳǤͶͳ 7 Nearest Airport ȂͶͺǤͷ
8 Nearest City Ahmedabad – 30.35 km in ESE direction
9 Nearest Village Jakhwada – 1.54 km in NW direction
10 Nearest National Highway NH 947 – 1.32 km in North direction
11 Nearest State Highway SH 17 – 1.32 km in North direction
12 Nearest School Shiyal Village Primary School – 1.57 km in
South direction
13 Nearest River/ Water Jakhwada Village Pond – 1.56 km in NNW
Body/ Canal direction
Narmada Canal – 6.0 km in West direction
14 Nearest Notified National ͳͲǤ Parks/ Sanctuary/ Eco ǡ Ȃ ʹͲǤͺ͵ Sensitive Zone ȂʹǤʹ
2.3 Details of Project Land & Plant Lay-Out
Total available land area of premises is 16,532 m2, out of which 5,546 m2 (33.55%) area will be developed for greenbelt. Detailed break-up of land area is given in Table 2.2 and Plant Lay-out is shown in Figure 2.4.
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.6
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. Table 2.2: Area Break-up of Project Site
Sr. No. Particular Area (m2) % of Total Land 1 Built-up area 6,017 36.40 %
2 Greenbelt area 5,546 33.55 % 3 Open/ Road area 4,969 30.05 %
Total 16,532 100 %
2.4 Capital Cost of the Proposed Project
Proposed manufacturing unit is a Medium Scale Unit having total investment of about Rs. 9.50 Crores. The break-up of the total capital cost is given in Table 2.3.
Table 2.3: Break-up of Capital Cost for Proposed Project
Sr. No. Particular Cost (INR in Crores)
1 Land & site development 0.74
2 Site development & Factory Building 3.0
3 Plant & Machineries 4.2
4 Environmental protection measures 0.82
5 Miscellaneous 0.74
Total 9.5
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.7
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. Figure 2.4: Plant Lay-out
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.8
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
2.5 Details of Product and Raw Material Consumption
Details of proposed products are given below in Table 2.4.
Table 2.4: Details of Product
Sr. Name of the Product Production Capacity No. (MT/Month) Alkyd Resin 1 2000
Polyamide Resin 2 1500
Polyester Resin 3 2000
Acrylic Resin 4 2500
Rosin Ester 5 500
Epoxy Resin 6 1500
Phenol Formaldehyde Resin 7 25
Melamine Formaldehyde Resin 8 25
Urea Formaldehyde Resin 9 25 Ketonic Resin 10 5
Total 10080 (MT/Month)
For manufacturing of proposed products various raw materials will be required which are listed along with its consumption quantity in below given Table 2.5
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.9
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. Table 2.5: Details of Raw Material Consumption
Name of the Name of Raw Quantity Sr. CAS No. No. Product Material (MT/Month) Vegetable Fatty ͺͲͲͳʹͷͲ 572.00 Acid Phthalic Anhydride* ͺͷͶͶͻ 726.00 1 Alkyd Resin Glycerine ͷͺͳͷ 276.80 Toluene/Xylene* ͳ͵͵ͲʹͲȀ 500.00 ͳͲͺͺͺ͵ Di Acid ͺͲͲͳʹͷͲ 902.40 Vegetable Fatty ͺͷͶͶͻ 150.40 2 Polyamide Resin Acid Ethylene Diamine ͷͺͳͷ 541.50 Phthalic Anhydride* ͺͷͶͶͻ 500.00 Mono Acid* ǦǦ 200.00 Butyl Glycol ͳͳͳʹʹ 700.00 3 Polyester Resin Glycerine ͷͺͳͷ 600.00 Styrene* ͳͲͲͶʹͷ 100.00
ͺͲʹ 750.00 Methacrylate * ͻ͵͵͵ 950.00 4 Acrylic Resin Acrylates ͳͲͲͶʹͷ 800.00 Styrene* Rosin ͺͲͷͲͲͻ 438.50 ͷͺͳͷ 109.20 5 Rosin Ester Glycerine Phthalic Anhydride* ͺͷͶͶͻ 0.42
ʹͷͲͺ͵ͺ 846.00 Epoxy Resin ͺͲͲͷ 283.80 6 Epoxy Resin Bis Phenol A* ͳ͵͵ͲʹͲȀ 374.12 Xylene/Toluene*
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.10
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
Name of the Name of Raw Quantity Sr. CAS No. No. Product Material (MT/Month) ͳͲͺͺͺ͵
Phenol Phenol * ͳͲͺͻͷʹ 13.92 Formaldehyde Formaldehyde ͷͲͲͲͲ 16.17 7 Resin (37%)* Caustic Soda* ͳ͵ͳͲ͵ʹ 0.15 Melamine Melamine ͳͲͺͺͳ 10.80 Formaldehyde Formaldehyde ͷͲͲͲͲ 16.08 8 Resin (37%)* Caustic Soda* ͳ͵ͳͲ͵ʹ 0.12 Urea Urea ͷͳ͵ 10.56 Formaldehyde Formaldehyde ͷͲͲͲͲ 15.58 Resin 9 (37%)* Caustic Soda* ͳ͵ͳͲ͵ʹ 0.13 Acetic Acid* Ͷͳͻ 0.13 Ketonic Resin Cyclo hexanone* ͳͲͺͻͶͳ 2.80 Formaldehyde 10 ͷͲͲͲͲ 5.60 (37%)*
Note: * The stated chemicals are considered as Hazardous Chemicals as per the Manufacture, Storage & Import of Hazardous Chemicals (MSIHC) Rules, 2000.
2.6 Manufacturing Process
Manufacturing process of all different types of Resin including chemical reaction, mass balance and process flow diagram is described here below:
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.11
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. 1. ALKYD RESIN
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.12
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. 2. POLYAMIDE RESIN
3. POLYESTER RESIN
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.13
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. 4. ACRYLIC RESIN
5. ROSIN ESTER
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.14
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
6. EPOXY RESIN
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.15
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
7. MELAMINE FORMALDEHYDE RESIN
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.16
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. 8. PHENOL FORMALDEHYDE RESIN
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.17
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
9. UREA FORMALDEHYDE RESIN
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.18
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. 10. KETONIC RESIN
Detailed manufacturing process with chemical reaction and mass balance is attached as separate Annexure – 4.
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.19
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. 2.7 Storage details of Raw Materials and Products
Mostly all raw materials are available in local market so, they will be purchased from local market. The convenient transportation medium will be used for the transportation of raw materials. Storage detail of products and raw materials are given in Table 2.6 and 2.7 respectively.
Table 2.6 : Storage Details of Proposed Products
Sr. Product name Capacity Capacity MOC of storage Nos. of storage Capacity (MT) Total Capacity No. MT/Month MT/Day (MT) Fiber drum / 1 Alkyd Resin 2000 80 364 0.220 80 Plastic drum
Fiber drum / 2 Polyamide Resin 1500 60 273 0.220 60 Plastic drum Fiber drum / 3 Polyester Resin 2000 80 364 0.220 80 Plastic drum Fiber drum / 4 Acrylic Resin 2500 100 455 0.220 100 Plastic drum Fiber drum / 5 Rosin Ester 500 20 91 0.220 20 Plastic drum Fiber drum / 6 Epoxy Resin 1500 60 273 0.220 60 Plastic drum Phenol Formaldehyde Fiber drum / 7 25 1 5 0.220 1 Resin Plastic drum
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.20
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. Sr. Product name Capacity Capacity MOC of storage Nos. of storage Capacity (MT) Total Capacity No. MT/Month MT/Day (MT) Melamine Fiber drum / 8 25 1 5 0.220 1 Formaldehyde Resin Plastic drum Urea Formaldehyde Fiber drum / 9 25 1 5 0.220 1 Resin Plastic drum Fiber drum / 10 Ketonic Resin 5 -- 4 0.220 0.8 Plastic drum
Table 2.7 : Storage Details of Proposed Raw Materials
Sr. Raw Material Capacity MT/ Day MOC of storage Nos. of Capacity Total Storage No. MT/M storage Capacity Inventory Days
572.0 + 150.40 MS/SS Cladding 1 Vegetable Fatty Acid 28.89 3 tank 50 MT 150 MT 5 days = 722.4 Tank
726.0 + 500.0 + 2 Phthalic Anhydride 49.06 HDPE Bag 9800 bag 25 kg 245 MT 5 days 0.42 = 1226.42
276.80 + 600.0 MS/SS Cladding 3 Glycerine + 109.20 = 39.44 3 tank 50 MT 150 MT 5 days Tank 986.0
500 .0 + 374.12 MS/SS Cladding 4 Toluene/Xylene 34.96 3 tank 50 MT 150 MT 5 days = 874.12 Tank
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.21
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. Sr. Raw Material Capacity MT/ Day MOC of storage Nos. of Capacity Total Storage No. MT/M storage Capacity Inventory Days
5 Di Acid 902.40 36.09 HDPE Bag 7200 bag 25 kg 180 MT 5 days
6 Ethylene Diamine 541.50 21.66 HDPE Drum 500 drums 220 L 110 MT 5 days
7 Mono Acid 200.00 8.0 HDPE Bag 1600 bag 25 kg 40 MT 5 days
MS/SS Cladding 8 Butyl Glycol 700.00 28.0 3 tank 50 MT 150 MT 5 days Tank
100.00 + 800.00 MS/SS Cladding 9 Styrene 36.0 3 tank 50 MT 150 MT 5 days = 900.0 Tank
10 Methacrylate 750.00 30.0 HDPE Drum 682 drums 220 L 150 MT 5 days
11 Acrylates 950.00 38.0 HDPE Drum 864 drums 220 L 190 MT 5 days
12 Rosin 438.50 17.54 HDPE Drum 409 drums 220 L 90 MT 5 days
MS/SS Cladding 13 Epoxy Resin 846.00 33.84 3 tank 50 MT 150 MT 5 days Tank
14 Bis Phenol A 283.80 11.35 HDPE Bag 2400 bags 25 kg 60 MT 5 days
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.22
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. Sr. Raw Material Capacity MT/ Day MOC of storage Nos. of Capacity Total Storage No. MT/M storage Capacity Inventory Days
MS/SS Cladding 15 Phenol 13.92 0.56 1 tank 20 MT 20 MT 30 days Tank
16.17 + 16.08 + MS/SS Cladding 16 Formaldehyde (37%) 15.58 + 5.60 = 2.14 1 tank 4.0 MT 4.0 MT 2 days Tank 53.43
0.15 + 0.12 + 17 Caustic Soda 0.016 HDPE Bag 8 bags 25 kg 0.2 MT 12.5 days 0.13 = 0.4
18 Melamine 10.80 0.43 HDPE Bag 120 bags 25 kg 3 MT 7 days
19 Urea 10.56 0.42 HDPE Bag 120 bags 25 kg 3 MT 7 days
20 Acetic Acid 0.13 0.0052 HDPE Bag 2 bags 25 kg 0.05 MT 9.5 days
21 Cyclo Hexanone 2.80 0.112 HDPE Drum 4 drums 220 L 0.88 MT 7.8 days
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.23
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. 2.8 Requirement of Resources
There will be requirement of resources like water, power, fuel, manpower, plant & machineries, utilities etc. Details of requirement of such resources for proposed project are described in subsequent sections under respective headings.
2.8.1 Electricity / Power
Total power requirement for the proposed project will be about 250 HP which will be procured from Uttar Gujarat Vij Company Limited (UGVCL). In addition to this, unit will install D. G. Set (250 HP) as stand-by to the main source and the same will be utilized only in case of non-availability of power from DGVCL.
2.8.2 Manpower
There will be requirement of about 70 persons, skilled & unskilled, for the operation and maintenance of the proposed project in efficient way. Preference will be given to the local people from nearby villages based on their skills as well as our requirements. During the construction stage, there will be requirement of workers. However, the same will be of contractor’s persons and utilized according to the requirements and type of construction activities. Details of proposed manpower are given in Table 2.8.
Table 2.8: Manpower Requirement
Particulars Skilled Unskilled
Male 15 55 Total 70 Local – 60 & Resident - 10
2.8.3 Water
For the proposed project, water will be required for domestic activities, greenbelt development and industrial operations. Total water requirement will be 10 kl/day which will be fulfilled by Borewell.
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.24
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. 2.8.4 Fuel
Fuel will be required for Themic Fluid Heater and D. G. Set (Stand-by). Bio- coal & Coal will be used in Themic Fluid Heater and Diesel will be utilized for D. G. Set. Fuel will be purchased from local trader. Details of fuel requirement are given in Table 2.9.
Table 2.9: Fuel Requirement
Sr. Particular Type of Fuel Fuel Requirement No. Thermic Fluid Heater – 1 1 (8 Lakh Kcal./hr.) Thermic Fluid Heater – 2 5 MT/Day + 2 Bio Coal + Coal (8 Lakh Kcal./hr.) 3.5 MT/Day Thermic Fluid Heater * - 3 3 (6 Lakh Kcal./hr.) 4 D.G. set (75 KVA) HSD 43.33 Liters/hr.
Note : * - TFH – 3 will be stand-by unit.
2.8.5 Plant, Machineries & Utilities
List of plant machineries required for the proposed project is given in Table 2.10. The actual requirements of utilities and machineries & equipment are not limited to the list given below as some additional minor requirements can also be cited depending up on necessity noticed during installation & operations.
Table 2.10: List of Plant, Machineries and Utilities
Sr. Utilities / Machineries Working Hours/Day No. 1 Cooling Tower (100 TR × 3 Nos.) 24 hrs. any one or two Thermic Fluid heater (8 Lakh Kcal/hr. × 2 Nos.) 2 24 hrs. any one or two (6 Lakh Kcal/hr. × 1 No.) 3 Chilling plant (40 TR × 2 Nos.) 15 hrs. 4 D. G. Set (1 No. 250 HP) When failure of electricity
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.25
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. 2.9 Energy Balance
Major equipment’s to be utilized in proposed unit for thermal energy requirement are Thermic Fluid Heater. Thus, energy balance of this equipment have been carried out and presented below in Table 2.11.
Table 2.11: Energy Balance
THERMIC FLUID HEATER Particular Unit Thermic Fluid Heater Installed Capacity Kcal/hr 1600000 Kcal/hr Rated Fuel (Bio - coal / Coal) Kg/day 8500 Gross Calorific Value per kg of Fuel Kcal 4000 Moisture content % 10 Efficiency on Gross Calorific Value % 75 Energy Produced Kcal/day 25500000 Moisture content Kcal/day 2550000 Losses through Flue gas 0.4% Kcal/day 102000 Net Energy output Kcal/day 22848000 Production TPD 403.2 Energy consumption per MT production Kcal/MT 56667
2.10 Pollution Potential and Proposed Control Measures
There will be possibility of pollution from the proposed project due to domestic & industrial wastewater generation & disposal; gaseous emission from process, flue gas emission from utilities, fugitive emission, noise and hazardous waste generation & disposal. The said probable pollutions are described below under respective heading with necessary details and mitigation measures.
2.10.1 Water Pollution
Total fresh water requirement for the proposed project will be 10.0 kl/day which will be fulfilled by Borewell. For domestic activities 4.5 kl/day fresh water, for industrial activities 14.2 kl/day recycle water and for greenbelt development 5.5 kl/day fresh water will be required.
Domestic Wastewater: Total 3.8 kl/day domestic wastewater will be generated which will be disposed off through septic tank/soak pit system.
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.26
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. Industrial Wastewater:
Total 16 kl/day industrial wastewater will be generated from proposed project activities. Stream-wise water consumption and wastewater generation is given in Table 2.12 and detailed water balance is given in Figure 2.6.
Table 2.12: Stream-wise Water Consumption & Wastewater Generation
Sr. Water Requirement Wastewater Generation Particular No. (kl/day) (kl/day) 1 Domestic activities 4.5 3.8 2 Greenbelt development 5.5 -- Industrial activities 3 Washing 1.2 1.1 Cooling Tower 13.0 1.3 Process 0 13.6 Total Industrial 14.2 (Recycled) 16 TOTAL (Domestic + Industrial + Greenbelt 10.0 19.8 development)
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.27
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. Figure 2.5: Water Balance Diagram 7RWDO ZDWHU FRQVXPSWLRQ ./' )UHVKZDWHU./' 5HXVHZDWHU
2.10.1.1 INDUSTRIAL WASTEWATER TREATMENT AND DISPOSAL
Industrial wastewater will be generated from process, cooling tower (blow-down) & washing.
Wastewater generated from washing and process will be collected in collection cum neutralization tank. Then wastewater will be given Chemical Oxidation treatment.
After completion of Chemical Oxidation Treatment, wastewater will be taken to Nutch Filter/Settling Tank for chemical sludge separation.
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.28
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. Treated wastewater and cooling tower blow down will be collected in holding tank. After that it will be sent to Evaporator followed by Condenser. Condensate water will be reused for industrial process.
ETP sludge along with evaporation residue from Evaporator will be disposed off at TSDF site. Thus, unit will maintain ZERO LIQUID DISCHARGE.
Schematic flow diagram of ETP is given in Figure 2.6 and Stream-wise effluent quality is given in Table 2.15.
Figure 2.6: Schematic Flow Diagram of Effluent Treatment Plant
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.29
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
Table 2.13: Details of Effluent Treatment Plant Units
Name of the Units Capacity No. of Units Collection cum Neutralization Tank 20 KL 2 Chemical Oxidation Tank 20 KL 1 Nutsche Filter / Settling Tank 20 KL 1 Holding Tank 20 KL 1 Evaporator 1.5 kl/hr. 1
Table 2.14: Technical Details of Evaporator
Particulars Volume Capacity 1.5 kl/hr.
Quantity of Effluent to be evaporated 16 kl/day
Working hours per day approx. 11 hrs.
MOC Mild Steel (MS)
Heat requirement 360102.37 kcal/hr.
Capacity of TFH (Common) 8,00,000 kcal/hr. x 2 nos.
Cost of operating ETP & Evaporator Rs. 16,000/Month
Table 2.15: Stream-wise Quality of Effluent
Composite Composit Cooling to Washing e to ETP Particular Unit (blow Process Evaporator Effluent before down) after treatment treatment KL/ Quantity 1.1 1.3 13.6 16.0 16.0 Day
pH -- 6.0 - 7.0 6.5 - 7.5 3.0 – 5.0 4.0 - 7.0 6.0 - 7.0
TSS mg/l 200 - 300 70 - 80 100 – 200 100 - 200 20 - 23
TDS mg/l 700 - 800 1000 - 1200 6000 – 5200 - 1150 - 1200
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.30
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. Composite Composit Cooling to Washing e to ETP Particular Unit (blow Process Evaporator Effluent before down) after treatment treatment 8000 7000
10000 - 8400 - COD mg/l 100 - 150 40 - 50 100-200 15000 13000
2.10.2 Air Pollution
In this proposed project flue gas emission will be the main source of air pollution. There will be chances of fugitive emission due to raw material handling and transportation and manufacturing activity.
2.10.2.1 Flue Gas Emission
The details of flue gas stack & technical specifications of Air Pollution Control Measures are given in Table 2.16 & Table 2.17 respectively.
Table 2.16: Details of Flue Gas Emissions
Sr. Stack Fuel APC Expected Stack attached to No. Height Requirement System Pollutant Thermic Fluid 1 Heater - 1 (8 Lakh Kcal/hr) Multi- Thermic Fluid Bio-coal – 5 Cyclone 2 Heater - 2 MT/Day + 30 m Separator SPM d 150 (8 Lakh Kcal/hr) Coal followed by mg/Nm3 Thermic Fluid 3.5 MT/day Bag Filter SO2 d 100 ppm Heater – 3 3 NO2 d 50 ppm (Stand-by) (6 Lakh Kcal/hr) 4 D.G. set* HSD Adequate (75 KVA) 5 m 43.33 stack height Liters/Hr.
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.31
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. Note: * D. G. set will be used as back-up when power failure and HSD is considered as clean fuel.
Table 2.17: Details of Air Pollution Control System
Type of Source Thermic Fluid Heater Capacity 8 lakh kilo cal/hr. x 2 nos. Fuel used Bio-coal & Coal Multi cyclone separator Temperature at Inlet 160 oC Gas flow rate 4.53 m3/sec Input SO2 load 0.81 gm/sec Input NO2 load 3.94 gm/sec Input dust load 19.0 gm/sec Efficiency 60 % Output dust load 7.6 gm/sec Pressure Drop 110 mm WC No./Size of cylinder 1 no. No. of Ash discharge cone 1 no. Ash discharge Air lock rotary valve Bag Filter Temperature at Inlet 120 oC Specific Gravity of Dust 1.29 Input Dust Load 7.6 gm/sec Efficiency 92 % Output dust load 0.6 gm/sec Pressure Drop 110 mm WC Type of Cleaning Mechanism Solenoid Operated Pulsing Valve Ash Discharge Air Lock Rotary Valve Air to Cloth ratio 1.02 m3/min/m2 Type of Bags Woven Needle Felt Imported Woven Fiber Glass Water Filter Fabrics Repellent
2.10.2.2 Fugitive Emission
Fugitive emissions are expected to be generated during construction and operational stages of the project. During construction stage, main source of fugitive emission is dust which is expected mainly due to the movement of vehicles carrying construction material and vehicles used for construction.
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.32
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. During operation stage, leakage through valves, pumps, emission from open drum containing chemicals, open feeding; storage tanks, etc. are the major sources of fugitive emissions of VOCs. Following measures will be adopted to prevent and control fugitive emissions:
x All the raw materials will be stored in isolated storage area and containers will be kept tightly closed. x Entire manufacturing activity will be carried out in closed reactors / vessels and regular checking and maintenance of the same will be carried out to avoid any leakages. x All the motors of pumps for the handling of hazardous chemicals will be flame proof and provided with suitable mechanical seal with stand-by arrangement. x The control of all parameters on a continuous basis will be done by adequate control valves, pressure release valves and safety valves etc. x All the flange joints of the pipe lines will be covered with flange guards. x The spillages / leakages of specific chemical will be collected and use or it will be drained to effluent treatment plant. x Precautionary measures will be taken while handling various hazardous chemicals. x There will also provision of adequate ventilation system such as turbo ventilators in process plant and hazardous chemical storage area. x A regular preventive maintenance will be planned to replace or rectify all gaskets, joints etc. x Transporters will be instructed to cover the trucks by tarpaulin sheets. x TREM card will be provided to the driver during the transportation of Hazardous raw materials/products. x Sufficient information and training regarding characteristics and immediate actions in case of any spillage or accident during transportation of hazardous chemical will be provided to the driver x The unit will also develop green belt area within the factory premises to control the fugitive emissions from spreading into surrounding environment. x Unit will install portable detection system VOCs in the process area. x Moreover, Unit will carry out regular work place monitoring.
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.33
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. 2.10.3 Solid / Hazardous Waste
The details of hazardous waste generation and handling / management are given in Table 2.18. Unit will provide storage area for hazardous wastes having roof, pucca flooring with leachate collection system. Leachate, if any will be collected and treated in effluent treatment plant. Unit will take membership of TSDF site after commencement of proposed project.
Table 2.18: Details of Hazardous Waste Management
Sr. Description Category Quantity Mode of Disposal No. ETP Sludge + 0.98 Collection, storage and disposal 1 Evaporation 35.3 MT/Month at approved TSDF site Residue Collection, storage and used 0.125 MT/ 2 Used Oil 5.1 within premises as a lubricant / Month sold to registered recycler. Discarded 105 Collection, storage & sold to 3 Plastic Bags / 33.1 MT/ Month authorized vendor. Barrels
2.10.3.1 Fly Ash Management:
Proposed fuel for Boiler : Bio-Coal (5 MT/day) & Coal (3.5 MT/day)
Fly ash generation has been calculated considering maximum ash generation scenario considering use of both the fuel :
Bio-Coal Coal Fuel consumption 5 MT/day 3.5 MT/day Ash content 2 – 10 % 38 % Total Ash generation 0.1 x 5 MT/day 0.38 x 3.5 MT/day 0.5 MT/day 1.33 MT/day Considering 50% Ash to be collected from bottom, Bottom Ash 0.5 x 0.5 MT/day 0.5 x 1.33 MT/day 0.25 MT/day (A) 0.665 MT/day (A) Considering 50 % Ash to be carried away with flue gas as fly ash which will be further trapped in bag filter (Bag filter Efficiency: 92 % & Multi cyclone dust collector efficiency : 60 %) Fly ash trapped in Air 0.92 x 0.4 x 0.25 0.92 x 0.4 x 0.665
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.34
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. pollution control units MT/day MT/day 0.092 MT/day (B) 0.24472 MT/day (B) Total Maximum Ash to be A + B A + B generated using fuel 0.25 + 0.092 = 0.342 0.665 + 0.24472 = 0.90972 Approximately 0.3 Approximately 0.9 MT/day MT/day
Total Ash to be generated will be stored into silo with proper care and sold to cement/ RMC/ paver blocks/ building bricks manufacturer units and also will be supplied to the other companies for land levelling, conditioning, road construction, etc.
2.10.4 Noise & Vibration
Noise may be generated due to the operation of D. G. set after the proposed project. However, D. G. set will be kept as standby and no other source of noise and vibration from the proposed manufacturing activity except plant machineries. However, unit will take following adequate precautionary measure for noise and vibration control;
x Latest technology based low noise D.G. set with acoustic enclosures will be installed.
x All the vibrating parts will be checked periodically and serviced to reduce the noise generation. The equipment, which generates excessive noise, will be provided with enclosures etc.
x Proper and timely oiling, lubrication and preventive maintenance will be carried out for the machineries and equipment to reduce noise generation.
x Ear muffs/ earplugs will be provided to the workers working under high noise area to minimize the adverse effect on the health.
x To reduce the noise generation during the transportation activities; the transport contractor will be instructed kept vehicle periodically serviced and maintain as per the requirement of latest trend in automobile industry. Only those vehicles with PUC’s will be allowed for the transportation.
x The transport contractor will be informed to avoid unnecessary speeding of vehicles inside the premises.
x Noise monitoring will be done regularly at prominent places in the plant.
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.35
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad. x Proposed greenbelt area will help to prevent the noise pollution outside the premises.
2.11 Pollution Potential Impacts & Mitigation measures
Attributes Activities, Impacts and its Mitigation Measures
Land Use During operation activity of the plant, the impact of air, water and solid waste pollution on soil causes direct/indirect effect on soil.
Operation activity :
1. Due to TFH operation, flue gas emission will be done & dispersed in the atmosphere. 2. Wastewater generated from the industry. 3. Solid & hazardous waste generation.
Impacts :
1. Due to dispersion of air pollutants in the atmosphere, nearby villagers may get disease of lung & health issues. There may also be decrease in productivity of crops & disease in plants. 2. Wastewater generated from the industry if discharged on the ground, it may deteriorate ground water quality. Secondarily it may also deteriorate surface water quality in rainy season. There may be health problems due to drinking of this ground & surface water. 3. Solid / hazardous waste generated from the process if collected loose form, it may pollute the soil. 4. Solid waste will be run away with the rainwater in rainy season if they will not properly collected in bags & stored in storage area under shed.
Mitigation Measures :
1. As all necessary air pollution control steps will be provided and based on the results of the dispersion model for the Ground Level Concentrations of various pollutants after the commissioning of the proposed activity, there will not be any adverse impact on soil. 2. There will be no adverse effect of wastewater on soil since the treated effluent emanating from the ETP will be evaporated in an
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.36
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
Attributes Activities, Impacts and its Mitigation Measures
evaporator. Thus, there will not be any significant impact on land environment. 3. All necessary control steps/measures will be provided for handling, storage and disposal of solid/ hazardous waste generated. All solid / hazardous waste should be properly collected in bags & stored in storage area under shed. Industry has also developed adequate greenbelt within the premises which not only increase the aesthetic of that area but also prevent soil erosion which may change the land use pattern of that area. Thus, there will not be any significant impact on land environment.
Thus, there will not be any adverse impact on the land use & soil environment during operation phase of the proposed project.
Water Water requirement is to be met through Borewell. Quality Operation activity :
1. Water consumption for various activities like domestic, gardening & industrial. 2. Waste water generation from the industrial premises.
Impact :
1. Ground water depletion 2. Surrounding villagers may not get enough water for their uses. 3. Wastewater generated from the industry if discharged on the ground, it may deteriorate ground water quality. Secondarily it may also deteriorate surface water quality in rainy season. There may be health problems due to drinking of this polluted ground & surface water. Crops may get disease by using this polluted ground water & surface water. Surrounding villagers, birds, animals may get disease by consuming these polluted crops.
Mitigation Measures :
1. Industry will consume fresh water with the quantity of 10 KL/day. Even though the industry will provide rain water storage tank in the premises so that fresh water consumption will be reduced. 2. Domestic wastewater generated will be disposed off through septic
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.37
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
Attributes Activities, Impacts and its Mitigation Measures
tank /soak pit system. 3. The final treated industrial effluent from effluent treatment plant will be evaporated in an evaporator. Therefore, no effluent will be required to be discharged and the stated process would be a ZERO DISCHARGE process.
Thus, there will not be any adverse impact on the quantity and quality of ground water as well surface water during operation phase.
Air Quality The operational activities are usually expected to have long-term impacts on air quality.
Operation activity :
1. The major source of air pollution due to proposed activity will be flue gas emissions from the TFH. 2. The fugitive emissions of Particulate Matter (PM) will likely to arise during various stages of operations such as material unloading, material transfer and storage etc.
Impacts :
1. Due to dispersion of air pollutants in the atmosphere, nearby villagers may get disease of lung & health issues. 2. Secondarily there may also be decrease in productivity of crops & disease in plants. 3. The concentrations of pollutants at the ground levels have been computed using computer simulation model to assess the impact of emissions for the proposed activity. 4. Impacts of emissions on air quality have been evaluated using dispersion model (AERMOD VIEW) which are described in Section 4.8 of this Chapter.
Mitigation measures :
1. All necessary air pollution control steps will be provided like Multi cyclone separator followed by Bag filter to control air pollution. 2. Based on the results of the dispersion model for the Ground Level Concentrations of various pollutants after the commissioning of the
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.38
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
Attributes Activities, Impacts and its Mitigation Measures
proposed activity, it is concluded that all the pollutants will be within the NAAQ standards. 3. Entire manufacturing activity will be carried out in closed reactors / vessels and regular checking and maintenance of the same will be carried out to avoid any leakages. All the motors of pumps for the handling of hazardous chemicals will be flame proof and provided with suitable mechanical seal with stand-by arrangement. Thus, there will not be any adverse impact on the quality of air during operation phase of the proposed project.
Noise The operational activities are usually expected to have long-term impacts on Noise.
Operation activity :
1. Thermic fluid heater operation, D. G. Set operation & pump & other machineries operation.
Impacts :
1. The workers working in the process area / TFH area & D. G. set area may get deafness after long time.
Mitigation measures :
1. The specifications for procuring major noise generating machines/equipment shall include built in design requirements to have minimum noise levels meeting Occupational Safety and Health Association (OSHA) requirement. 2. Appropriate noise barriers/shields, silencers etc. shall be provided in the equipment wherever feasible. Noise emanating from noisy equipment shall be adequately attenuated by enclosure, insulation etc. 3. Green belt area will be provided to prevent noise pollution at boundary of the industrial premises.
Thus, there will not be any adverse impact anticipated on surrounding environment due to noise pollution of the proposed project.
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.39
M/s. Paragon Poly Resins LLP Environmental Impact Assessment Report Survey No. 782, Village : Jakhwada,
Taluka : Viramgam, District : Ahmedabad.
Attributes Activities, Impacts and its Mitigation Measures
Soil Operation activity :
1. Industrial process activity 2. Raw material storage & solid / hazardous waste storage 3. TFH operation
Impacts :
1. There are minimal chances that air borne fugitive dust from the project may likely get deposited in the immediate vicinity. 2. Spillage & leakage from storage of raw materials & solid / hazardous waste may contaminate the soil & simultaneously ground water .
Mitigation measures :
1. The flue gas emissions will be controlled by an effective dust extraction and suppression system and source emission by installing highly efficient bag filter/ other pollution control facilities at suitable locations. 2. The storage and handling of raw materials shall be done properly to prevent any spillage & leakage. 3. Hazardous wastes will be stored at earmarked area with impervious flooring, shed and spillage/leakage collection system to eliminate rainwater contamination, chances of overflow / spillages going on to the land and thus land/ soil contamination. 4. The hazardous waste generated during the operation phase, will be properly disposed so that there is no spill and contamination of land. The hazardous waste will be sent for disposal to authorized TSDF on regular basis as per the Hazardous Waste Rules.
Thus, there will not be any adverse impact anticipated on surrounding geology & soil due to the proposed project.
T. R. Associates (Ahmedabad) Chapter-2: Project Description NABET Accredited 2.40
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
CHAPTER - 3 DESCRIPTION OF ENVIRONMENT
3.1 Introduction
Preparation of Environmental Impact Assessment (EIA) needs a datum on which the evaluation can be done. It is necessary to collect data about different environmental components like air, noise, water, land, flora and fauna and socio-economic factors that are being affected by the operation of any project activity, which, in turn, defines an existing environmental quality to serve as the datum.
Base line data requirement is also necessary to identify environmentally significant issues as well as to enumerate the critical environmental change that is likely to occur due to the project activity. Here an attempt has been made to collect the information about an existing environment on the below mentioned six major environmental attributes: 9 Air Environment 9 Water Environment 9 Noise Environment 9 Land & Soil Environment 9 Biologcal Environment 9 Socio – Economic Environment
An effective methodology is important for baseline data collection and impact prediction to develop an efficient environment management plan. In this regard, it is important to understand the ground realities of the site and surrounding by the experts involved in preparation of EIA. Accordingly, a team of experts visited the proposed site to understand the site surrounding and possible impacts from the activities of the proposed project. The EIA coordinators in consultation with the respective functional area experts selected the sampling locations as per the TORs prescribed by the SEAC/SEIAA.
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.1
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
Subsequently, the field monitoring was undertaken during October 2018 to December 2018 by the T. R. Associates Laboratory. The collected data were analysed and interpreted.
3.2 Air Environment
Dispersion of different air pollutants released into the atmosphere have significant impacts on the neighborhood air environment of an industrial project and forms an important part of impact assessment studies. The ambient air quality status with respect to the study area of 10 km radius from the plant site will form the base line information over which the predicted impacts due to the proposed plant can be super imposed to find out the net (final) impacts on air environment. From the final impacts a viable Environmental Management Plan (EMP) can be prepared based on the impact statement for the air environment. The baseline status of the ambient air quality can be assessed thorough scientifically designed ambient air quality monitoring network. The design of monitoring network in the air quality surveillance program has to be based on the following considerations. x Meteorological conditions on synoptic scale. x Topography of the study area. x Representation of regional background levels. x Representation of plant site. x Representation of cross sectional distribution in the downward direction. x Influence of the existing sources if any, are to be kept at minimum. x Inclusion of major distinct villages to collect the baseline status.
3.2.1 Micrometeorological Data
Micro-meteorological data within the project area during the air quality monitoring period is an indispensable part of air pollution study. The meteorological data recorded during monitoring period is very useful for proper interpretation of the baseline information as well as serves as an input, to predictive models for air quality impacts.
To understand meteorological scenario primary and secondary data are collected. This data is used in the interpretation of wind scenario. The data collected from the both sources are summarized as follows:
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.2
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
Table 3.1: Period of Meteorological Data Collection
Primary data (October 2018 to December 2018): Parameters like Wind Speed, Wind Direction, Temperature, Humidity and Precipitation collected for project site using Automatic Weather Meteorological Station. Data Secondary data (Entire Year): Secondary data has been collected from the nearest IMD source (Ahmedabad) for Temperature, Humidity, Rainfall, Wind Speed.
3.2.1.1 Meteorological Data from Secondary Sources
The climate of the Ahmedabad district is characterised by hot summer and general dryness except during the southwest monsoon seasons. The year can be divided into four seasons. The period from March to May is the hot season (summer) followed by southwest monsoon from June to September. October and November constitute the post-monsoon or retreating monsoon season. The cold season (winter) starts from December and ends in February.
The mean maximum temperature ranges between 28.4 ºC (during January) to 41.8 ºC (during May) and the mean minimum temperatures vary between 11.7 ºC (during January) to 27 ºC (during June). The relative humidity varies between 32 % (March) and 79 % (August). The mean wind speed varies from 0.86 m/s (October) and 2.02 m/s (June). Long-term average annual rainfall recorded by IMD station at Ahmedabad is 66.33 mm. Most of the rainfall (about 765.7 mm) is received between June to September. Climatological data of nearest IMD station i.e. Ahmedbad is given in the Table 3.2.
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.3
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
Table 3.2: Monthly Mean Values of Meteorological Data (Secondary Data) Month Air Temperature Relative Mean Wind Rainfall (°C) Humidity (%) Speed (mm) Max. Mini. (meter/sec.) January 28.4 11.7 43.0 1.16 2.6 February 31.3 13.8 36.0 1.18 1.1 March 36.0 18.8 32.0 1.27 1.0 April 39.9 23.4 34.5 1.40 0.9 May 41.8 26.2 42.5 1.84 6.0 June 38.4 27.0 59.5 2.02 108.7 July 33.3 25.7 76.0 1.74 265.3 August 31.9 24.8 79.0 1.44 219.8 September 33.4 24.1 71.0 1.20 171.9 October 35.8 20.9 50.5 0.86 10.8 November 33.2 16.5 43.0 0.92 8.9 December 29.8 13.0 45.0 1.06 2.6 TOTAL 413.2 245.9 612 16.09 799.6 Annual Mean 34.4 20.5 51.0 1.34 66.63
Source: As per Climatological Table – IMD, Ahmedabad Station (1981-2010), CGWB-Ahmedabad
The wind rose diagram obtained from meteoblue organization for the entire year based on 30 years of hourly historical weather data for Ahmedabad location is presented in Figure 3.1.
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.4
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
Figure 3.1: Wind Rose Diagram of Entire Year (Secondary Source)
Source : https://www.meteoblue.com/en/weather/forecast/modelclimate/ahmedabad_india_1279233
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.5
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
3.2.1.2 Meteorology-Data generated at project site (Duration: October 2018 to December 2018)
Meteorology of the study area plays an important role in the study of air pollution. Micrometeorological conditions at the project site regulate the dispersion and dilution of air pollutants in the atmosphere. For this purpose a weather station was installed near the project site for the period October 2018 to December 2018 and recorded hourly observations for the parameters like Temperature, Relative Humidity, Wind Speed, Wind Direction and Rainfall.
Meteorological conditions, of the site, regulates the transport and diffusion of air- pollutants released into the atmosphere. Ambient temperature, wind speed, wind direction and atmospheric stability are called primary or basic meteorological parameters because the dispersion and diffusion of pollutants depend mainly on these Parameters. Humidity, precipitation, pressure and visibility are secondary meteorological parameters as this control the dispersion of the pollutants indirectly by affecting primary parameters.
The hourly-recorded observations during above stated study period are used in computing percentage frequencies and are depicted in the form of ‘wind roses’ in Figure 3.2. Primary meteorological data are shown in Annexure - 9.
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.6
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
Figure 3.2 A : Wind Rose Diagram of Baseline Monitoring Period (October 2018 to December 2018) (Primary Source)
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.7
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
Figure 3.2: Wind Rose Diagram for Primary Data Collected for October 2018 to December 2018 on Google Image
Note : Blue circle – 1 km radius, Red circle – 5 km radius, White circle – 10 km radius.
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.8
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
3.2.2 Selection of AAQ Stations
A network of eight (8) ambient air-sampling locations has been selected for assessment of the existing status of air environment within the study zone. The heights of the sampling locations were kept between 3 to 6 m in all the locations. After reconnaissance of the area and observing the topographical features and review of the available meteorological data and local conditions the sampling sites were chosen which will be the representative of the local areas under study.
Figure 3.3: Map showing Ambient Air Quality Locations
1
Source : Google Earth
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.9
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
3.2.2.1 Existing AAQ Status
Ambient levels of pollutants such as PM10, PM2.5, SO2, NO2, CO, and VOC are selected for the sampling. The methodology of sampling and analysis in detail is given in the following Tables 3.4 & 3.5.
Table 3.3: Ambient Air Monitoring Locations
Station Ambient Air Located in Distance in Direction GPS Coordinates Code Location km 23° 4' 12.62"N 1 Project Site -- 0 -- 72° 8' 47.10"E 23° 7' 5.18"N 2 Kalyanpura DW(P) 7.56 NE 72°11' 18.69"E 23° 4' 48.04"N 3 Sachana DW 2.69 ENE 72° 10' 24.89"E 23° 3' 11.77"N 4 Karakthal UW 3.4 WSW 72° 6' 42.70"E 23° 0' 40.99"N 5 Liya UW 8.18 SW 72° 5' 24.33"E 23° 5' 4.79"N 6 Jakhwada CW 1.55 NW 72° 8' 7.18"E Kalyanpur 23° 3' 26.02"N 7 CW 1.32 SSE (Shiyal) 72° 8' 59.65"E Hansalpur 23° 5' 19.88"N 8 CW 8.16 WNW Sareshwar 72° 3' 54.88"E
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.10
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
Figure 3.4: Photograph showing Ambient Air Monitoring
Location : Karakthal Location : Hansalpur (Sareshwar) Latitude : 23° 3'11.77"N, Latitude : 23° 5' 19.88"N Longitude : 72° 6'42.70"E Longitude : 72° 3' 54.88"E Date : 14-9-2018 Date : 14-9-2018
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.11
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
Table 3.4: Air – Parameters Analyzed and Sampling Duration
Attribute Parameter Frequency of Monitoring
24 hrs. Sampling for PM10, PM2.5, SO2, NO2, CO & VOC - Two days per week during the study period
PM10, PM2.5, (October 2018 to December 2018). This was carried
AAQ SO2, NO2, CO & out in accordance with the guidelines of Central
VOC at 8 locations Pollution Control Board (CPCB), Scientific Manual of GPCB and National Ambient Air Quality Standard (NAAQS) of CPCB.
Table 3.5: Ambient Air Quality - Methodology
Method of Analysis
PM10 IS 5182 (Part 23): 2006 (RA 2017)
Dust PM2.5 TRA/STP/AA/02 D/I 27/10/2014
SO2 IS 5182 (Part 2): 2001 (RA 2017)
NO2 IS 5182 (Part 6): 2006 (RA 2017) Variables CO TRA/STP/AA/08 Gases VOC TRA/STP/AA/07
Various statistical parameters like standard deviation, geometric mean, minimum; maximum concentrations and different percentiles have been computed from the data generated during sampling in all sampling stations.
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.12
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
Table 3.6: Ambient Air Monitoring Results
AAQ Monitoring Location NAAQ Parameter Value Standards Project site Shiyal Jakhwada Karakthal Liya Hansalpur Sachana Kalyanpura (24 hrs.) Min ϯϮ͘ϲϴ ϯϬ͘ϱϮ ϯϳ͘ϭϴ ϯϯ͘ϰϱ Ϯϵ͘ϱϲ ϰϬ͘ϵϯ ϰϭ͘Ϯϱ ϰϯ͘ϲϱ PM 2.5 Max. ϰϭ͘Ϯϭ ϯϳ͘ϱϰ ϰϰ͘ϲϮ ϰϮ͘ϴϵ ϯϲ͘ϳϭ ϰϵ͘ϬϮ ϱϬ͘Ϭϭ ϱϮ͘ϮϬ (ΐg/m3) 60 ΐg/m3 Mean ϯϲ͘ϱϯ ϯϯ͘ϵϰ ϰϬ͘ϵϰ ϯϴ͘ϳϮ ϯϮ͘ϲϯ ϰϱ͘Ϯϵ ϰϱ͘Ϭϲ ϰϴ͘Ϯϭ
98th Percentile ϰϬ͘ϴϵ ϯϳ͘ϰϭ ϰϰ͘ϰϳ ϰϮ͘ϴϰ ϯϲ͘ϰϮ ϰϴ͘ϴϬ ϰϵ͘ϳϭ ϱϮ͘Ϭϲ Min ϲϰ͘Ϯϵ ϲϭ͘Ϭϰ ϳϬ͘ϴϲ ϲϲ͘Ϯϭ ϱϴ͘ϵϰ ϳϯ͘ϴϰ ϳϴ͘ϱϮ ϴϬ͘ϵϰ PM 10 Max. ϳϱ͘ϲϲ ϳϮ͘ϰϭ ϳϵ͘ϴϭ ϳϲ͘ϰϴ ϲϴ͘ϳϱ ϴϮ͘ϰϴ ϴϱ͘ϰϲ ϴϵ͘ϰϰ (ΐg/m3) 100 ΐg/m3 Mean ϳϬ͘ϯϯ ϲϳ͘ϯϳ ϳϱ͘ϭϮ ϳϭ͘ϯϯ ϲϰ͘ϱϯ ϳϴ͘ϭϲ ϴϭ͘ϵϴ ϴϰ͘ϱϭ
98th Percentile ϳϱ͘ϯϳ ϳϮ͘Ϯϲ ϳϵ͘ϰϰ ϳϲ͘Ϯϰ ϲϴ͘ϰϰ ϴϮ͘ϯϯ ϴϱ͘ϰϬ ϴϵ͘Ϯϰ Min ϲ͘ϬϮ ϭϮ͘ϰϮ ϴ͘ϬϮ ϱ͘ϰϬ ϵ͘ϭϳ ϳ͘Ϯϭ ϭϰ͘ϭϮ ϭϯ͘ϭϵ SO2 Max. ϭϭ͘ϳϵ ϭϳ͘ϳϰ ϭϯ͘ϮϮ ϭϬ͘ϵϲ ϭϱ͘ϴϴ ϭϮ͘ϴϱ Ϯϭ͘ϳϰ ϭϵ͘ϴϴ (ΐg/m3) 80 ΐg/m3 Mean ϴ͘ϴϬ ϭϱ͘Ϯϰ ϭϬ͘ϰϱ ϴ͘ϰϰ ϭϮ͘ϰϳ ϵ͘ϵϰ ϭϳ͘ϵϬ ϭϲ͘Ϯϱ
98th Percentile ϭϭ͘ϲϳ ϭϳ͘ϲϭ ϭϯ͘Ϭϳ ϭϬ͘ϵϰ ϭϱ͘ϲϱ ϭϮ͘ϲϬ Ϯϭ͘ϯϯ ϭϵ͘ϱϮ
NO2 Min ϭϳ͘Ϭϱ ϭϲ͘ϭϮ ϭϵ͘Ϯϭ ϭϱ͘ϭϰ ϵ͘ϭϱ ϮϬ͘Ϭϳ ϮϮ͘ϰϰ Ϯϲ͘Ϭϯ (ΐg/m3) Max. Ϯϱ͘Ϯϭ Ϯϳ͘ϴϱ Ϯϲ͘ϴϬ Ϯϰ͘ϳϮ ϭϱ͘ϱϴ Ϯϴ͘ϵϯ Ϯϵ͘ϯϴ ϯϮ͘ϵϴ 80 ΐg/m3 Mean ϮϬ͘ϵϳ Ϯϭ͘ϳϰ ϮϮ͘ϴϯ ϮϬ͘ϲϭ ϭϭ͘ϵϳ Ϯϯ͘ϵϲ Ϯϱ͘ϳϱ Ϯϵ͘ϱϮ 98th Percentile Ϯϱ͘ϬϬ Ϯϳ͘ϲϴ Ϯϲ͘ϳϬ Ϯϰ͘ϳϬ ϭϱ͘ϰϭ Ϯϴ͘ϯϭ Ϯϵ͘Ϯϳ ϯϮ͘ϴϴ VOC B.D.L. B.D.L. B.D.L. B.D.L. B.D.L. B.D.L. B.D.L. B.D.L. Not -- (ppm) (D.L.= 0.1) (D.L.= 0.1) (D.L.= 0.1) (D.L.= 0.1) (D.L.= 0.1) (D.L.= 0.1) (D.L.= 0.1) (D.L.= 0.1) Specified CO B.D.L. B.D.L. B.D.L. B.D.L. B.D.L. B.D.L. B.D.L. B.D.L. 4 mg/m3 (ppm) -- (D.L.=1) (D.L.=1) (D.L.=1) (D.L.=1) (D.L.=1) (D.L.=1) (D.L.=1) (D.L.=1) Note: BDL – Below Detectable Limit
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.13
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
3.2.2.2 Interpretaion of AAQ results of Study Area Interpretation of AAQ results of the study area is presented in Table- 3.7.
Table 3.7: Baseline Staus of Ambient Air Quality
Sr. No. Parameters Baseline Status
PM2.5 concentrations in the study area were ranging from 29.56 to 52.20 ΐg/m3. Whereas 98th percentile values are in the range of 36.42 to 52.06 ΐg/m3 which are within the stipulated 1 PM2.5 NAAQS values. PM2.5 concentration is observed at village Kalyanpura with the result of 52.20 ΐg/m3.
PM10 concentrations in the study area were ranging from 58.94 to 89.44 ΐg/m3. Whereas 98th percentile values are in the range of 68.44 to 89.24 ΐg/m3 which are within the stipulated 2 PM10 NAAQS values. PM10 concentration is observed at village Kalyanpura with the result of 89.44 ΐg/m3.
3 th SO2 concentrations in the study area were ranging from 5.40 to 21.74 ΐg/m . Whereas 98
3 SO2 percentile values in the range of 10.94 to 21.33 ΐg/m3 which are within the stipulated NAAQS 3 values. SO2 concentration is observed at village Sachana with the result of 21.74 ΐg/m .
NO2 concentrations in the study area were ranging from 9.15 to 32.98 ΐg/m3 with 98th percentile
4 NO2 values in the range of 15.41 to 32.88 ΐg/m3 which are within the stipulated NAAQS values. NO2 concentration is observed at village Kalyanpura with the result of 32.98 ΐg/m3. 5 VOC B.D.L. (D.L.= 0.1 ppm) 6 CO B.D.L. (D.L.= 1 ppm)
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.14
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
3.3 Noise Environment
Noise word come from the Latin word ‘nauseas’, it is a loud outcry or commotion that is unpleasant, unexpected, or undesired with various frequencies over the audible range due to the regular activities of the mankind primarily noise pollution (or environmental noise) is displeasing human, animal or machine-created sound that disrupts the activity or balance of humans or animals life. The source of most outdoor noise worldwide is mainly evolved from Industries, constructions and transportation systems, including motor vehicle noise, aircraft noise and rail noise, poor urban planning may give rise to noise pollution.
Industrial noise resulting to noise pollution has many reasons such as industries being close to human habitats which prevent the noise from decaying before it reaches human ear.
A determination is made of the micro scale impact by predicting anticipated noise levels for each alternative during both construction and operational phases. Predicted noise levels are compared with applicable standards or criteria in order to assess the impact.
The physical description of sound concerns its loudness as a function of frequency. Noise in general sound which comprises of many frequency components with different variations in loudness over the audible frequency range.
Various noise scales have been introduced to describe, a single number, the response of an average human to a complex sound made up of various frequencies at different loud levels, the response of the human ear to sound is dependent on the frequency of the sound and this has led to the concept of weighting scales. In the "A-weighting" scale, the sound pressure levels for the lower frequencies and higher frequencies are reduced by certain amounts before they are being combined together to give one single sound pressure level value. This value is designated as dB (A). The dB (A) is often used as it reflects more accurately the frequency response of the human ear. A perceived loud noise has a high dB or dB (A) value and a soft noise has a low one. The
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.15
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
human ear has peak response around 2,500 to 3,000 Hz and has a relatively low response at low frequencies.
3.3.1 Existing Noise Levels
Pre-project noise levels have been monitored at different points within the study zone and on the spot measurement device manufactured by LUTRON SL 4033-SD was used for this purpose. Keeping in view of various local activities such as residential and Industrial activities 8 noise level measurement locations were identified and the sites are depicted in the Figure 3.5 & Table 3.8. Photographs showing noise sampling is shown in Figure 3.6. Results of monitoring are shown in Table 3.9.
Figure 3.5: Map Showing Noise Sampling Locations
1
Source : Google Earth
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.16
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
Table 3.8: Noise Monitoring Locations
Located Distance Code Location Name Direction GPS Coordinates in in km 23Σ4.224' N 1 Project site Centre -- -- 72Σ8.788' E 23Σ5.142' N 2 Jakhwada CW 1.55 NW 72Σ8.180' E 23Σ3.433' N 3 Kalyanpur (Shiyal) CW 1.32 SSE 72Σ9.093' E 23Σ4.913' N 4 Sachana DW 2.69 ENE 72Σ10.416' E 23Σ3.385' N 5 Karakthal UW 3.4 WSW 72Σ6.746' E Sanand-Viramgam 23Σ5.832' N 6 Highway Intersection CW 4.16 NW 72Σ6.456' E near Sokali Bhojnipura Sanand-Viramgam 23Σ4.579' N 7 CW 4.24 NNE Highway Intersection 72Σ10.479' E near Sachana 23Σ6.356' N 8 Narsinhpura CW 3.83 N 72Σ8.908' E
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.17
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
Figure 3.6: Photograph showing Noise Measurement
Location : Jakhwada Location : Sanand-Viramgam Highway Intersection near Sachana Latitude : 2305.142' N Latitude : 23Σ4.579' N Longitude : 7208.180' E Longitude : 72Σ10.479' E Date : 14-9-2018 Date : 14-9-2018
Table 3.9: Noise Level Monitoring Data [Day and Night timings in Leq dB (A)]
Day Time Monitoring Recorded level in dB(A) Sampling Limits Leq Sampling Date Category Location Minimum Maximum Leq [dB(A)]
Project Site 14.10.18 To 15.10.18 Industrial 48.1 71.1 65.6 75 Jakhwada 15.10.18 To 16.10.18 Residential 46.9 61.0 54.4 55 Kalyanpur (Shiyal) 16.10.18 To 17.10.18 Residential 46.1 57.1 53.4 55 Sachana 17.10.18 To 18.10.18 Residential 49.1 58.1 52.2 55 Karakthal 18.10.18 To 19.10.18 Residential 46.9 57.1 50.9 55 Sanand-Viramgam Highway 19.10.18 To 20.10.18 Residential 46.6 55.1 51.9 55 Intersection near Sokali Sanand-Viramgam Highway 20.10.18 To 21.10.18 Residential 46.9 61.2 54.2 55 Intersection near Sachana
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.18
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
Day Time Monitoring Recorded level in dB(A) Sampling Limits Leq Sampling Date Category Location Minimum Maximum Leq [dB(A)]
Narsinhpura 21.10.18 To 22.10.18 Residential 45.1 52.7 49.6 55
Night Time Monitoring Recorded level in dB(A) Limits Sampling Sampling Date Category Leq Location Minimum Maximum Leq [dB(A)] Project Site 14.10.18 To 15.10.18 Industrial 45.2 49.3 47.2 70 Jakhwada 15.10.18 To 16.10.18 Residential 40.2 45.2 43.7 45 Kalyanpur 16.10.18 To 17.10.18 Residential 35.0 41.3 38.7 45 (Shiyal) Sachana 17.10.18 To 18.10.18 Residential 36.3 44.7 42.1 45 Karakthal 18.10.18 To 19.10.18 Residential 35.0 42.8 39.3 45 Sanand- Viramgam Highway 19.10.18 To 20.10.18 Residential 37.2 52.2 44.8 45 Intersection near Sokali Sanand- Viramgam Highway 20.10.18 To 21.10.18 Residential 35.3 39.0 37.4 45 Intersection near Sachana Narsinhpura 21.10.18 To 22.10.18 Residential 36.5 44.1 40.4 45
3.3.2 Baseline Status of Ambient Noise Quality
Sound levels had been recorded according to IS: 9989:1991 (Reaffirmed 2001). The maximum noise level measured in the study area in day time was 71.1 dB (A) at project site which was below the stipulated standards. The maximum noise level measured in the study area in night time was 52.2 dB (A) at Sanand-Viramgam Highway Intersection near Sokali. The noise levels (Leq) of the residential area within the impact zone varied from 49.6 – 54.4 dB (A) in the daytime and 38.7 – 44.8 dB (A) in the night time, which are also below the specified limits.
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.19
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
3.4 Water Environment
Studies on Water Environment aspects of ecosystem is important for Environmental Impact Assessment to identify sensitive issues and take appropriate action by maintaining ‘ecological homeostasis’ in the early stages of development of the project. The objective of this report is to define the present environment in which the proposed action is to occur, to evaluate all possible eventualities, to ensure that all negative impacts are minimized, and to demonstrate that proposed project has been appropriately announced to all interested parties so that their concerns can be considered.
Water quality studies have been carried out in the study area to understand the availability of water resources, possibility of water contamination and existing water quality.
3.4.1 Water Quality
Water of high quality is essential to human life, and water of acceptable quality is essential for agricultural, industrial, domestic and commercial uses; in addition, most recreation is water based; therefore, major activities having potential effects on surface water are certain to be of appreciable concern to the consumers.
3.4.1.1 Sample Collection and Analysis
The water resources in the study area may be classified into two major categories i.e. Surface and Ground water sources
Water samples were collected at 16 locations, out of which 8 samples were selected from surface sources and 8 samples selected from ground water sources for physico- chemical and biological parameters. Parameters like pH, Temperature and TDS analysed at the time of sampling. For other Parameter analysis the samples were preserved as per the recommended techniques for various Elemental determinations as per `IS: 3025 (part I) 1987’. These parameters were analyzed as per the procedures specified in ‘Standard Methods for Examination of Water and Wastewater’ Published
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.20
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
by American Public Health Association (APHA) / IS 3025. Ground water & Surface water samples results were compared with IS: 10500 specifications.
Method of Water Sampling
The following procedures were used while sampling:
9 Washing the bottles/cans with distilled water prior to the sampling 9 Before collection of water the bottles/cans are again washed 2-3 times with the same water. 9 For surface water, bottles were lowered to a minimum depth of 30 cm below water surface. 9 At each point different sets of water samples were collected so as cover all the parameters. 9 Proper attention is taken in proper numbering at the site. 9 Sterilized bottles were used for the samples that are to be analyzed for bacteria. 9 Civil supply water pipeline taps are sterilized before collection for bacteriological analysis 9 Parameters like pH, conductivity and temperature were analyzed in the field conditions and the results were reconfirmed after getting to the laboratory. DO is fixed in the field itself. Appropriate preservatives are added, depending upon the elements to be analyzed and marked accordingly (IS: 3025 (part I) 1987) 9 All the water samples collected in the ice box, were immediately transported to the laboratory and freezed at <5oC analysis 9 Field observations were noted in the field notebook 9 As far as possible photographs were taken in almost all sampling points. Sampling & analysis of all the parameters are as per APHA, 22nd Edition & IS: 3025.
Ground water & surface water sampling location is shown in Figure 3.7 A & 3.7 B, & Table 3.10. Photographs showing ground water & surface water sampling is shown in Figure 3.8. Results of monitoring are shown in Table 3.11 & 3.12.
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.21
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
Figure 3.7 A: Map showing Ground water monitoring locations
1
Source : Google Earth
T. R. Associates (Ahmedabad) Chapter-3: Description of Environment NABET Accredited 3.22
M/s. Paragon Poly Resins LLP. Environmental Impact Assessment Report Survey No. 782,Village : Jakhwada,
Taluka :Viramgam, District : Ahmedabad.
Figure 3.7 B: Map showing Surface water monitoring locations