Project Details Project Name: IT Procurement Project Team Leads: Tim Evans, Patrick Delin : Kirk Corey TeamDynamix Project Number: 241122

Project Overview (What is going to be accomplished) This project will:  Create ways to reduce the cost of procuring and managing end user devices  Identify use cases and cost models for VDI  Develop and implement a process that gives the University CIO oversight of all IT-related purchases  Centralize and improve the procurement of IT software licenses to assure best pricing and terms

Project Staffing (Who will perform the work)

Who Skill Set Estimated Time Commitment Tim Evans ITS Senior Director, Project Co-Lead 80 hours Patrick Delin Athletics IT Director, Project Co- 80 hours Lead Kirk Corey 100 hours

Tom Neese VDI Subject Matter Expert, 50 hours Subproject Lead Tim Wolf Procurement Subject Matter 50 hours Expert, Subproject Lead John Watkins Purchasing Subject Matter Expert, 40 hours Subproject Lead Tracy Scott Software Subject Matter Expert, 50 hours Subproject Lead Dan Mentzer VDI Subject Matter Expert 30 hours Tracey Schmidt Software Subject Matter Expert 30 hours

Additional subproject team VDI and software interest and 10-15 hours each members expertise

DRAFT Project Plan Page 1 of 5

IT Procurement

Project Schedule (When will the work be started/completed) Subproject 1 – VDI Task When Who Status Notes Review work already started and define Fall 2015 Entire subproject Complete Review information from Deloitte, as well as previous cost estimates and models use cases team from UI and ISU. Discuss potential use cases for deployment

Draft report Spring- Tom, Dan, Kirk In Summer progress 2016

Review and finalize draft; publish Fall 2016 Entire subproject Not results. team started

DRAFT Project Plan Page 2 of 5

IT Procurement

Subproject 2 – Standardization of devices and strategic sourcing Task When Who Status Notes Solicit input on standard configurations Fall 2015- Tim, Tracy, In Standard Dell configurations defined and currently being purchased and negotiate pricing Spring Purchasing, Progress 2016 interested stakeholders Review purchase numbers and identify Summer Tim, Tracy, In Currently looking at additional laptop options additional opportunities 2016 Purchasing, Progress interested stakeholders Define next steps Fall 2016 Tim, Tracy, Not Purchasing, started interested stakeholders

Subproject 3 – Transform software office Task When Who Status Notes Define and review current state Fall 2015 Subproject team Complete

Design future state Spring Subproject team In 2016 Progress

Subproject 4 – CIO oversight Task When Who Status Notes Gather requirements Fall 2015 Kirk, Tim, Steve F. Complete

Changes to procurement software TBD TBD Not Start and duration pending availability and sequencing with other changes to started procurement software

DRAFT Project Plan Page 3 of 5

IT Procurement

Project Budget This project does not involve any equipment expenses. The proposed project relies primarily on staff time.

Change Control Plan Substantial changes to project scope will be brought to the OneIT Steering Committee for evaluation and resolution. Minor changes will be handled by project leadership. The project manager and leadership will determine the scale of changes.

Communications Plan

Primary Communication Purpose/Description Target Audience Frequency Owner Contact Mechanism of Communication OneIT Steering Program Email, meeting Updates on project, As needed Kirk Corey Committee Office discussion feedback, change mgmt

Email, meeting, Ad hoc as Project Updates, vetting OneIT Leaders Chris Clark Kirk Corey sharepoint, website needed proposed plans

Boyd Email, meeting, Ad hoc as Project Updates, vetting Collegiate IT Leaders Kirk Corey Knosp sharepoint, website needed proposed plans

Nicole Ad hoc as Project Updates, vetting OneIT Community Email, website Kirk Corey Riehl needed proposed plans ITADmin Jessica Email, Meeting, Ad hoc as Project Updates, vetting Tracy/Tim W. Community Church website needed proposed plans Lynette Email, Meeting, Ad hoc as ITAC Project Updates Kirk Corey Racevskis website needed Associate Deans Email, Meeting, Ad hoc as Project Updates, vetting Chris Clark Kirk Corey Group website needed proposed plans UI Faculty Laura Email, Meeting, Ad hoc as Project Updates, vetting Kirk Corey Governance McLaren website needed proposed plans

DRAFT Project Plan Page 4 of 5

IT Procurement Plan

Risk Likelihood Impact Risk Description Mitigation Strategy Number (H,M,L) (H,M,L) 1 Logistical challenge of H H The current software review process handling legal and regulatory is complex; mitigating this risk is part review, identifying of the purpose of the project. functionality and duplicate Achieved by better balancing the use and providing self-service workload among groups, to avoid capability for all software bottlenecks. titles across campus. 2 Resistance of users to go H M Well-designed controls should through a central process. minimize workarounds. 3 Lack of resources to M L Primarily affects CIO oversight implement and maintain the because of dependence on work outlined in this project. programming.