CENTRAL ANNUAL PLAN 2020-21 ID Workstream Task Name Stages Scheme Road Name Parish Ward Area Scheme Description Allocation Month LA Start Finish Status expected in 1 ANNUAL PLAN 2020-21 Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

2 CAPITAL PROGRAMME Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

3 STRUCTURAL STRUCTURAL Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 MAINTENANCE MAINTENANCE

4 C/W RESURFACING C/W RESURFACING Q1,2,3 Q1,2,3 Wed 01/04/20 Mon 03/08/20

5 C/W Resurfacing Station road CONSTRUCTION Station road Langford & Langford 1 Whole Road RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20

6 C/W Resurfacing HIGH STREET CONSTRUCTION HIGH STREET Langford Stotfold & Langford 1 O/S 41A to joint Mini Rabt RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20

7 C/W Resurfacing Fildyke Road CONSTRUCTION Fildyke Road Shefford 1 Full length RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20

8 C/W Resurfacing Road CONSTRUCTION Bedford Road 1 From Bedford Boundary To Red Panel RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20 30MPH 9 C/W Resurfacing Road CONSTRUCTION Ickwell Road Northill Northill 1 second half RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20

10 C/W Resurfacing Campton Road CONSTRUCTION Campton Road Shefford Shefford 1 Cemetery entrance RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20

11 C/W Resurfacing Bedford Road CONSTRUCTION Bedford Road Shefford Shefford 1 Mini roundabout Stanford Road to RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20 Shefford Hardwick 12 C/W Resurfacing Hanscombe End Road CONSTRUCTION Hanscombe End Shillington & Shillington 1 From bend to O/S 36 RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20 Road 13 C/W Resurfacing High Road CONSTRUCTION High Road Southill Northill 1 T junction Sandy Lane RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20

15 C/W Resurfacing Rook Tree Lane CONSTRUCTION Rook Tree Lane Stotfold Stotfold & Langford 1 The Green to Brayes Manor RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20

16 C/W Resurfacing Park Street CONSTRUCTION Park Street Ampthill 2 Whole of road RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20

17 C/W Resurfacing Orchard Estate CONSTRUCTION Orchard Estate Heath & Reach 2 Leighton Road to High Street RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20

18 C/W Resurfacing Leighton Road CONSTRUCTION Leighton Road Eggington Heath & Reach 2 O/S 12 to O/S 16 resurfacing, patching RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20 and SD A4012 to O/S 12 19 C/W Resurfacing A5120 Ampthill Road CONSTRUCTION A5120 Ampthill Flitwick 2 A507 to Williams Way including junction RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20 Road 20 C/W Resurfacing Plantation Road CONSTRUCTION Plantation Road Leighton Buzzard North 2 Deer Walk to Sandy Lane (inlcuding Jct RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20 Sandy Lane) 21 C/W Resurfacing Finch Crescent CONSTRUCTION Finch Crescent Leighton Buzzard 2 Full length RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20

22 C/W Resurfacing Heath Road CONSTRUCTION Heath Road Leighton Buzzard Leighton Buzzard North 2 Shenley Hill Junc incl to Heath Park Rd RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20 including Jct 23 C/W Resurfacing Sandhill Close CONSTRUCTION Sandhill Close Millbrook & Marston 2 Whole length RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20 Moretaine 24 C/W Resurfacing Speedwell CONSTRUCTION Speedwell Woburn Aspley & Woburn 2 Whole of road Speedwell junction RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20

25 C/W Resurfacing Church Walk CONSTRUCTION Church Walk Cranfield Cranfield & Marston 2 Full length RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20 Moretaine 26 C/W Resurfacing Bedford Road / Hexton Road / CONSTRUCTION Bedford Road / Barton-Le-Clay Barton-Le-Clay 3 T Junction Resurfacing RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20 Luton Road Hexton Road / Luton 27 C/W Resurfacing Spinney Crescent CONSTRUCTION SpinneyRoad Crescent Dunstable Northfields 3 Full Length RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20

28 C/W Resurfacing Jeansway CONSTRUCTION Jeansway Dunstable Dunstable Icknield 3 Liscombe Road to Kingsbury Gardens RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20

29 C/W Resurfacing High Street CONSTRUCTION High Street Eaton Bray 3 Whole RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20

30 C/W Resurfacing Barton Road CONSTRUCTION Barton Road Harlington Toddington 3 From O/S 101 joint at T Junct RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20 resurfacing to O/S 13. 31 C/W Resurfacing Road CONSTRUCTION Sharpenhoe Road Streatley Toddington 3 from Church Road joint to Sundon Road RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20 joint (inlcuding junction at Church Road) 32 C/W Resurfacing Mount Pleasant CONSTRUCTION Mount Pleasant Aspley & Woburn 2 C/W Resurfacing RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20

33 C/W Resurfacing Salford Road CONSTRUCTION Salford Road Aspley Guise Aspley & Woburn 2 C/W Resurfacing RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20

34 C/W Resurfacing Bedford Road T Junction CONSTRUCTION Bedford Road T Aspley Guise Aspley & Woburn 2 C/W Resurfacing RJ Q1,2,3 Wed 01/04/20 Mon 03/08/20 Junction 35 F/W RESURFACING F/W RESURFACING Q1,2,3,4 Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

36 F/W RESURFACING Cedar Avenue CONSTRUCTION Cedar Avenue Biggleswade North 1 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

37 F/W RESURFACING Bilberry Road CONSTRUCTION Bilberry Road Clifton 1 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

39 F/W RESURFACING High Street CONSTRUCTION High Street Arlesey 1 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

40 F/W RESURFACING Station Road CONSTRUCTION Station Road Langford Stotfold & Langford 1 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

42 F/W RESURFACING Orchard Close CONSTRUCTION Orchard Close Meppershall Shefford 1 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

43 F/W RESURFACING Victoria Road CONSTRUCTION Victoria Road Shefford Shefford 1 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

45 F/W RESURFACING Elm Road CONSTRUCTION Elm Road Shefford Shefford 1 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

46 F/W RESURFACING Hillside Close CONSTRUCTION Hillside Close Shillington Silsoe & Shillington 1 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

47 F/W RESURFACING Church View Avenue CONSTRUCTION Church View Avenue Shillington Silsoe & Shillington 1 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

48 F/W RESURFACING The Green CONSTRUCTION The Green Stotfold Stotfold & Langford 1 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

49 F/W RESURFACING Church Street CONSTRUCTION Church Street 1 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

50 F/W RESURFACING Queen's Road CONSTRUCTION Queen's Road Ampthill Ampthill 2 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

51 F/W RESURFACING Saunders Piece CONSTRUCTION Saunders Piece Ampthill Ampthill 2 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

52 F/W RESURFACING Orchard Way CONSTRUCTION Orchard Way Flitwick Flitwick 2 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

53 F/W RESURFACING Bluebell Close CONSTRUCTION Bluebell Close Flitwick Flitwick 2 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

54 F/W RESURFACING Waterloo Road CONSTRUCTION Waterloo Road Leighton Buzzard Linslade 2 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

55 F/W RESURFACING Tamar Walk CONSTRUCTION Tamar Walk Leighton Buzzard Leighton Buzzard North 2 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

56 F/W RESURFACING Avon Walk CONSTRUCTION Avon Walk Leighton Buzzard Leighton Buzzard North 2 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

57 F/W RESURFACING Meadow Way CONSTRUCTION Meadow Way Leighton Buzzard Leighton Buzzard North 2 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

58 F/W RESURFACING Dunstall Road CONSTRUCTION Dunstall Road Barton-Le-Clay Barton-Le-Clay 3 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

59 F/W RESURFACING Leighton Road CONSTRUCTION Leighton Road Billington Eaton Bray 3 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

60 F/W RESURFACING Lockington Crescent CONSTRUCTION Lockington Crescent Dunstable Dunstable Icknield 3 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

61 F/W RESURFACING Markham Crescent CONSTRUCTION Markham Crescent Dunstable Dunstable Icknield 3 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

62 F/W RESURFACING Downs Road CONSTRUCTION Downs Road Dunstable Dunstable Manshead 3 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

63 F/W RESURFACING Hillyfields CONSTRUCTION Hillyfields Dunstable Dunstable Watling 3 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

64 F/W RESURFACING Borough Road CONSTRUCTION Borough Road Dunstable Dunstable Manshead 3 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

65 F/W RESURFACING Clifton Road CONSTRUCTION Clifton Road Dunstable Dunstable Northfields 3 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

66 F/W RESURFACING Appleby Gardens CONSTRUCTION Appleby Gardens Dunstable Dunstable Central 3 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

67 F/W RESURFACING Medley Close CONSTRUCTION Medley Close Eaton Bray Eaton Bray 3 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

68 F/W RESURFACING Enfield Close CONSTRUCTION Enfield Close Parkside 3 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

69 F/W RESURFACING Watling Place CONSTRUCTION Watling Place Houghton Regis Houghton Hall 3 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

70 F/W RESURFACING Bradford Road CONSTRUCTION Bradford Road Toddington Toddington 3 Footway Resurfacing RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

71 C/W SURFACE C/W SURFACE DRESSING 2020 Q2 Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 72 C/W SURFACE Road CONSTRUCTION Astwick Road Astwick Stotfold & Langford 1 From Fen End to the A1 RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 73 C/W SURFACE Dunton Lane CONSTRUCTION Dunton Lane Biggleswade Biggleswade South 1 From Saxon Drive Rbt to Sutton Lane RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 Rbt 74 C/W SURFACE C136 Greenways CONSTRUCTION C136 Greenways Campton and Chicksands Shefford 1 from A507 red panel to O/S 18 RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 75 C/W SURFACE Sutton Road CONSTRUCTION Sutton Road Dunton Potton 1 From Biggleswade Rd Rbt to Sutton - RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 High St Xrds 76 C/W SURFACE C184 CONSTRUCTION C184 Potton 1 From last left hand turn before A1 to RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 30mph at Millow 77 C/W SURFACE Hinxworth Road CONSTRUCTION Hinxworth Road Edworth Potton 1 From C184 to county boundary RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 78 C/W SURFACE Tempsford Road CONSTRUCTION Tempsford Road Everton Potton 1 From Sandy Road junc to Little Barford RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 Road junc 79 C/W SURFACE Thrupp End CONSTRUCTION Thrupp End Cranfield & Marston 1 Full Length Sheeptick to Woburn Road RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 Moretaine 80 C/W SURFACE Thorncote Road CONSTRUCTION Thorncote Road Northill Northill 1 Junction of Road to junction with RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 Bedford Road 81 C/W SURFACE Sutton Road CONSTRUCTION Sutton Road Potton Potton 1 Sutton - High St Xrds to Junc Bury Hill RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 82 C/W SURFACE B658 Stanford Road CONSTRUCTION B658 Stanford Road Shefford Shefford 1 Roundabout to Shefford Road Stanford RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 83 C/W SURFACE Shefford Road CONSTRUCTION Shefford Road Southill Northill 1 From junction with Bedford Road to RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 junction with UC147 Yew Tree Lodge 84 C/W SURFACE Clifton Road CONSTRUCTION Clifton Road Stanford Northill 1 From 30mph to The Crescent - Stanford RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 85 C/W SURFACE B658 Shefford Road CONSTRUCTION B658 Shefford Road Stanford Northill 1 Stanford Road Shefford to Stanford RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 Road Southill Junction 86 C/W SURFACE A507 Stotfold Bypass CONSTRUCTION A507 Stotfold Stotfold Stotfold & Langford 1 From Norton Road rbt to Hitchin Road RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 Bypass rbt 87 C/W SURFACE Astwick Road CONSTRUCTION Astwick Road Stotfold Stotfold & Langford 1 From Astwick Rd,Astwick to Fen End, RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 Stotfold 88 C/W SURFACE Bourne End Road CONSTRUCTION Bourne End Road Cranfield Cranfield & Marston 2 Astwood Road to Partridge Piece RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 Moretaine 89 C/W SURFACE Mill Road CONSTRUCTION Mill Road Eggington Heath & Reach 2 From A4012 to High Street including RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 High Street (bend resurfacing) 90 C/W SURFACE Church Road CONSTRUCTION Church Road Flitwick Flitwick 2 Manor Way to End Jcn UC106 RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 91 C/W SURFACE Harlington Road CONSTRUCTION Harlington Road Harlington Toddington 2 From Barton Road to Harlington Road RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 Sharpenhoe 92 C/W SURFACE Station Lane CONSTRUCTION Station Lane Millbrook Cranfield & Marston 2 Prooving Ground to Joint new surface RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 Moretaine Railway Crossing 93 C/W SURFACE Harlington Road CONSTRUCTION Harlington Road Sharpenhoe Toddington 2 Harlington Road Harlington to RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 Sharpenhoe 30MPH 94 C/W SURFACE Pedley Hill CONSTRUCTION Pedley Hill 3 From junc. Clements End Road to RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 Leighton Road 95 C/W SURFACE Dunstable Road CONSTRUCTION Dunstable Road Studham Caddington 2 From junc. Buckwood Lane to start of RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 30mph for village 96 C/W SURFACE B5120 Dunstable Road CONSTRUCTION B5120 Dunstable Heath & Reach 3 From Road Junction to RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 Road Dunstable Road Toddington

Page 1 ANNUAL PLAN 2020-21 ID Workstream Task Name Stages Scheme Road Name Parish Ward Area Scheme Description Allocation Month LA Start Finish Status expected in 97 C/W SURFACE Sharpenhoe Road CONSTRUCTION Sharpenhoe Road Streatley Toddington 3 From junc. Sundon Road to Sharpenhoe RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 98 C/W SURFACE Byslips Road CONSTRUCTION Byslips Road Studham Caddington 3 From junc. Buckwood Road to Clements RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 End Road 99 C/W SURFACE Road CONSTRUCTION Kensworth Road Studham Caddington 3 From junc. Dunstable Road to junc. RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 Byslips Road 100 C/W SURFACE B5120 Dunstable Road CONSTRUCTION B5120 Dunstable Toddington Toddington 3 From Dunstable Road Chalgrave to RJ Q2 Wed 01/07/20 Wed 30/09/20 DRESSING 2020 Road 30MPH including the red panel 101 C/W RETEXTURING C/W RETEXTURING Q3 Q3 Tue 04/08/20 Fri 30/10/20

102 C/W RETEXTURING Everton Road/Potton Road CONSTRUCTION Everton Road/Potton Potton Potton 1 From Everton Road join with Myers RJ Q3 Tue 04/08/20 Tue 03/11/20 Road Road, Potton to Potton Road Join with 103 C/W RETEXTURING Northill Road/Warden Road CONSTRUCTION Northill Ickwell Northill 1 FromSandy Ickwell Road, RoadEverton through Ickwell to Hill RJ Q3 Tue 04/08/20 Tue 03/11/20 Road/Warden Road Lane Junction 105 C/W RETEXTURING Biggleswade Road CONSTRUCTION Biggleswade Road Northill Northill 1 From Junction with Hitchin Road to RJ Q3 Tue 04/08/20 Tue 03/11/20 national speed limit signs/red panel 106 C/W RETEXTURING High Street CONSTRUCTION High Street Southill Northill 1 From High Street join with Howards RJ Q3 Tue 04/08/20 Tue 03/11/20 Close to B658 107 C/W RETEXTURING Southill Road CONSTRUCTION Southill Road Biggleswade Biggleswade South 1 From B658 to Jordans Mill RJ Q3 Tue 04/08/20 Tue 03/11/20 Northill 109 C/W RETEXTURING B1042 potton Road CONSTRUCTION B1042 potton Road Potton Potton 2 Potton to High Street RJ Q3 Tue 04/08/20 Tue 03/11/20

110 C/W RETEXTURING Station Road CONSTRUCTION Station Road Temspford Potton 2 Kier Entrance to Level Crossing RJ Q3 Tue 04/08/20 Tue 03/11/20

111 C/W RETEXTURING Chalgrave Road CONSTRUCTION Chalgrave Road Tebworth Heath & Reach 3 Sections along Chalgrave Road from RJ Q3 Tue 04/08/20 Tue 03/11/20 B5120 to Toddington Road 112 C/W RETEXTURING Tebworth Road CONSTRUCTION Tebworth Road Tebworth Heath & Reach 3 Sections along Tebworth Road from RJ Q3 Tue 04/08/20 Tue 03/11/20 B5120 to Wingfield Road 113 C/W RETEXTURING Eaton Bray Road CONSTRUCTION Eaton Bray Road Eaton Bray 3 EATON BRAY ROAD RJ Q3 Tue 04/08/20 Tue 03/11/20

114 C/W RETEXTURING B4540 Dunstable Road CONSTRUCTION B4540 Dunstable Eaton Bray Eaton Bray 3 From B4540 to county border RJ Q3 Tue 04/08/20 Tue 03/11/20 Road 115 C/W RETEXTURING B4540 CONSTRUCTION B4540 Kensworth Caddington 3 Sections along B4540 from Dagnall RJ Q3 Tue 04/08/20 Tue 03/11/20 Road to Common Road 116 C/W RETEXTURING Byslips Road CONSTRUCTION Byslips Road Studham Caddington 3 From Kensworth Road to the crossroads RJ Q3 Tue 04/08/20 Tue 03/11/20 of Buckwood Lane and Buckwood Road 117 C/W RETEXTURING Common Road CONSTRUCTION Common Road Studham Caddington 3 From Valley Road to crossroads of RJ Q3 Tue 04/08/20 Tue 03/11/20 Clements End Road and Byslips Road 118 C/W RETEXTURING Clements End Road CONSTRUCTION Clements End Road Studham Caddington 3 From Dunstable Road to county border RJ Q3 Tue 04/08/20 Tue 03/11/20

119 C/W RETEXTURING Road CONSTRUCTION Chiltern Green Road Hyde Caddington 3 From B653 to Chiltern Green RJ Q3 Tue 04/08/20 Tue 03/11/20

120 C/W RETEXTURING Icknield Way CONSTRUCTION Icknield Way Eaton Bray Eaton Bray 3 From Roundabout to County Border RJ Q3 Tue 04/08/20 Tue 03/11/20

121 C/W RETEXTURING West Hyde Road CONSTRUCTION West Hyde Road Hyde Caddington 3 A1081 to B653 RJ Q3 Tue 04/08/20 Tue 03/11/20

122 C/W REGEN C/W REGEN Q2 Q2 Mon 03/08/20 Mon 30/11/20

123 C/W REGEN Woodcock Lane CONSTRUCTION Woodcock Lane Heath & Reach 2 From Leighton Road To End Of Road RJ Q2 Mon 03/08/20 Mon 30/11/20

124 C/W REGEN Zuc192 From Hockliffe Road CONSTRUCTION Zuc192 From Aspley & Woburn 2 Zuc192 From Hockliffe Road Near RJ Q2 Mon 03/08/20 Mon 30/11/20 Near Watergate Farm To Hockliffe Road Near Watergate Farm To Hockliffe Road Via 125 C/W REGEN ChurchHockliffe Lane Road Via Battlesden CONSTRUCTION ChurchWatergate Lane Farm To Battlesden Aspley & Woburn 2 FromBattlesden Zuc192 From Hockliffe Road Near RJ Q2 Mon 03/08/20 Mon 30/11/20 Watergate Farm To Hockliffe Road Via 126 C/W REGEN Sandhouse Lane CONSTRUCTION Sandhouse Lane Heath & Reach 2 FromBattlesdon Woburn To RoadEnd Of To Road Watling Street RJ Q2 Mon 03/08/20 Mon 30/11/20

127 C/W REGEN Copt Hall Road CONSTRUCTION Copt Hall Road Hyde Caddington 3 Full Length RJ Q2 Mon 03/08/20 Mon 30/11/20

128 C/W REGEN Causeway CONSTRUCTION Causeway Ampthill 2 High Street to A507 RJ Q2 Mon 03/08/20 Mon 30/11/20

129 C/W REGEN Road CONSTRUCTION How End Road Houghton Conquest & 1 Full length RJ Q2 Mon 03/08/20 Mon 30/11/20 Haynes 130 C/W REGEN Sand lane CONSTRUCTION Sand lane Sandy Sandy 1 From Swaden to end RJ Q2 Mon 03/08/20 Mon 30/11/20

131 C/W REGEN Northfield Road CONSTRUCTION Northfield Road Potton 1 High Street to County Border RJ Q2 Mon 03/08/20 Mon 30/11/20

132 C/W REGEN Wood End CONSTRUCTION Wood End Marston Moretaine Cranfield & Marston 2 From Marston Thrift Car Park to jctn with RJ Q2 Mon 03/08/20 Mon 30/11/20 Moretaine old A421 133 C/W PRE-PATCHING C/W PRE-PATCHING FOR SD SC to provide data by Q3 Q2 Wed 01/04/20 Wed 01/04/20 FOR SD 2021 2021 end of March 134 C/W Pre-patching for SD 2021 CONSTRUCTION RJ Q2 Wed 01/04/20 Wed 01/04/20

135 STRUCTURAL County Wide County Wide CBC Q1 Mon 13/04/20 Mon 13/04/20 MAINTENANCE 136 SM TRIAL HOLES / CORRING DESIGN County Wide CBC Q1 Mon 13/04/20 Mon 13/04/20

137 STRUCTURAL RESERVE LIST 2020-21 Mon 03/08/20 Thu 31/12/20 MAINTENANCE

138 C/W RESURFACING Bedford Road CONSTRUCTION Bedford Road Moggerhanger Northill 1 From Bedford Boundary To Red Panel RJ Dates tbc once Mon 03/08/20 Thu 31/12/20 30MPH funding is 139 C/W RESURFACING Drove Road CONSTRUCTION Drove Road Biggleswade Biggleswade North 1 From London Road To Edward Rd Jct RJ Dates tbc once Mon 03/08/20 Thu 31/12/20 incl Jct funding is 140 C/W RESURFACING Way CONSTRUCTION Stewartby Way Houghton Conquest Houghton Conquest & 1 T Junction with B530 RJ Dates tbc once Mon 03/08/20 Thu 31/12/20 Haynes funding is 141 C/W RESURFACING Norton Road CONSTRUCTION Norton Road Stotfold Stotfold & Langford 1 A507 Roundabout join to county border RJ Datesdetermined tbc once Mon 03/08/20 Thu 31/12/20 funding is 142 C/W RESURFACING High Street CONSTRUCTION High Street Stotfold Stotfold & Langford 1 From Baldock Road before the RJ Datesdetermined tbc once Mon 03/08/20 Thu 31/12/20 roundabout to table by The Avenue funding is 143 C/W RESURFACING Myers Road CONSTRUCTION Myers Road Potton Potton 1 Everton Road to Everton Road RJ Datesdetermined tbc once Mon 03/08/20 Thu 31/12/20 funding is 144 C/W RESURFACING Hatley Road / Sutton Road CONSTRUCTION Hatley Road / Sutton Potton Potton 1 T Junction RJ Datesdetermined tbc once Mon 03/08/20 Thu 31/12/20 Road funding is 145 C/W RESURFACING Potton Road / High Street CONSTRUCTION Potton Road / High Wrestlingworth Potton 1 T Junction RJ Datesdetermined tbc once Mon 03/08/20 Thu 31/12/20 Street funding is 146 C/W RESURFACING West Hill CONSTRUCTION West Hill Aspley Guise Aspley & Woburn 2 Woodside to Bedford Road RJ Datesdetermined tbc once Mon 03/08/20 Thu 31/12/20 funding is 147 C/W RESURFACING High Street CONSTRUCTION High Street Cranfield Cranfield & Marston 2 From Lodde Road Rabt to Court Road RJ Datesdetermined tbc once Mon 03/08/20 Thu 31/12/20 Moretaine funding is 148 C/W RESURFACING Dunstable Road CONSTRUCTION Dunstable Road Flitwick Flitwick 2 From joint at roundabout to before RJ Datesdetermined tbc once Mon 03/08/20 Thu 31/12/20 junction at temple way funding is 149 C/W RESURFACING Hillside Road CONSTRUCTION Hillside Road Dunstable Dunstable Manshead 3 Full Length RJ Datesdetermined tbc once Mon 03/08/20 Thu 31/12/20 funding is 150 C/W RESURFACING CARRY OVER SCHEMES FROM Datesdetermined tbc once Mon 03/08/20 Mon 03/08/20 2019-20 funding is 151 C/W RESURFACING TBC-Jan-Feb 2020 Datesdetermined tbc once Mon 03/08/20 Mon 03/08/20 funding is 152 DRAINAGE DRAINAGE Q1,2,3,4determined Wed 01/04/20 Wed 31/03/21

153 DRAINAGE Langdale Road SuDS (Possibly CONSTRUCTION UNDER Langdale Road Dunstable Dunstable Watling 3 Construction of 19/20 design. Verge External Q1,2 Wed 01/04/20 Tue 04/08/20 funded by AW) REVIEW SuDs scheme as part of Dunstable 154 DRAINAGE Westfield Road SuDS (Possibly CONSTRUCTION UNDER Westfield Road Dunstable Dunstable Northfields 3 ConstructionFlood Study measures of 19/20 design. Verge External Q1,2 Wed 01/04/20 Tue 04/08/20 funded by AW) REVIEW SuDs scheme as part of Dunstable 155 DRAINAGE W&T Drainage Package W&T C/ OVER Bedford Road, , Heath 1 ConstructionFlood Study measures of 19/20 design RJ Q1,2 Fri 01/05/20 Thu 03/09/20 SCHEME Glebe Avenue, & Reach, Henlow Eastern Way, Brook Close, Chiltern 156 DRAINAGE 5 Bells Stanbridge MillClose Road Stanbridge Heath & Reach 2 Construction of 19/20 design - flood RJ Q1,2 Wed 01/04/20 Tue 08/12/20 alleviation 157 DRAINAGE 5 Bells Stanbridge DESIGN/ Mill Road Stanbridge Heath & Reach 2 Construction of 19/20 design - flood RJ Q1,2,3 Wed 01/04/20 Tue 30/06/20 INVESTIGATION alleviation 158 DRAINAGE 5 Bells Stanbridge CONSTRUCTION Mill Road Stanbridge Heath & Reach 2 Construction of 19/20 design - flood RJ Q1 Wed 05/08/20 Tue 08/12/20 alleviation 159 DRAINAGE A507 Ampthill- Bypass - CONSTRUCTION ON HOLD Ampthill to Maulden Ampthill Ampthill 2 Ditch Maintenance, Arb works. RJ Q2,3 Wed 01/04/20 Tue 04/08/20 Pennyfathers Moor Bypass 160 DRAINAGE Hornes End Road Flitwick CONSTRUCTION Hornes End Road Flitwick Flitwick 2 Construction of 19/20 design - replace RJ Q1,2 Wed 01/04/20 Tue 04/08/20 broken pipe causing flooding on private 161 DRAINAGE Pipers Croft CONSTRUCTION Pipers Croft Dunstable Dunstable Watling 3 Constructionland of 19/20 design. Design to RJ Q1,2 Wed 01/04/20 Tue 04/08/20 be completed on the 17th Jan. 162 DRAINAGE High Street, Henlow High Street Henlow Arlesey Q1,2 Wed 01/04/20 Tue 04/08/20

163 DRAINAGE High Street Henlow CONSTRUCTION High Street Henlow Arlesey 1 Pipe works into a stream. Related to a RJ Q1,2 Wed 01/04/20 Tue 04/08/20 new run. Design due by end of Jan 20 164 DRAINAGE High Street, High Street Blunham Sandy Q1,2,3,4 Wed 01/04/20 Mon 07/12/20

165 DRAINAGE High Street, Blunham DESIGN/ High Street Blunham Sandy 1 Design/ Investigation RJ Q1,2,3 Wed 01/04/20 Tue 04/08/20 INVESTIGATION 166 DRAINAGE High Street, Blunham CONSTRUCTION High Street Blunham Sandy 1 Construction RJ Q3,4 Tue 01/09/20 Mon 04/01/21

167 DRAINAGE road Marston Lower Shelton Marston Moretaine Cranfield & Marston Q1,2 Fri 01/05/20 Wed 06/01/21 Road Moretaine 168 DRAINAGE Lower Shelton road Marston DESIGN/ Lower Shelton Road Marston Moretaine Cranfield & Marston 2 Design /Investigation Capacity, and RJ Q1,2 Mon 04/05/20 Fri 04/09/20 INVESTIGATION Moretaine washout of road foundation 169 DRAINAGE Lower Shelton road Marston CONSTRUCTION Lower Shelton Road Marston Moretaine Cranfield & Marston 2 Construction RJ Q3,4 Mon 05/10/20 Fri 05/02/21 Moretaine 170 DRAINAGE Rook Tree Lane Stotfold Rook Tree Lane Stotfold Stotfold & Langford Q1,2,3,4 Mon 01/06/20 Thu 04/02/21

171 DRAINAGE Rook Tree Lane Stotfold DESIGN/ Rook Tree Lane Stotfold Stotfold & Langford 1 Design/Investigation - reported ponding RJ Q1,2,3 Mon 01/06/20 Fri 02/10/20 INVESTIGATION 173 DRAINAGE Dunstable verge SuDS ph2 Town-wide Dunstable Dunstable Design/Investigation for future Q2,3 Wed 01/07/20 Tue 03/11/20 programme based on 174 DRAINAGE Dunstable verge SuDS DESIGN Town-wide Dunstable Dunstable 3 Design/Investigationrecommendations of for Jacobs future Study RJ Q2,3 Wed 01/07/20 Tue 03/11/20 ph2-site 1 programme based on recommendations 175 DRAINAGE Dunstable verge SuDS DESIGN Town-wide Dunstable Dunstable 3 Design/Investigationof Jacobs Study - site for 1 future RJ Q2,3 Wed 01/07/20 Tue 03/11/20 ph2-site 2 programme based on recommendations 176 DRAINAGE Dunstable verge SuDS DESIGN Town-wide Dunstable Dunstable 3 Design/of Jacobs Investigation Study - site for 2 future RJ Q2,3 Wed 01/07/20 Tue 03/11/20 ph2-site 3 programme based on recommendations 177 DRAINAGE Dunstable verge SuDS DESIGN Town-wide Dunstable Dunstable 3 Design/Investigationof Jacobs Study - site for 3 future RJ Q2,3 Wed 01/07/20 Tue 03/11/20 ph2-site 4 programme based on recommendations 178 DRAINAGE Ampthill soakaway system Town-wide Ampthill Ampthill Investigationof Jacobs Study and - site Design 4 Q1,2,3,4 Wed 01/04/20 Mon 07/12/20 improvements 179 DRAINAGE Ampthill soakaway system DESIGN/ Town-wide Ampthill Ampthill 2 Investigation and Design Q1,2 Wed 01/04/20 Tue 04/08/20 improvements INVESTIGATION 180 DRAINAGE Ampthill soakaway system CONSTRUCTION Town-wide Ampthill Ampthill 2 Construction RJ Q2,3,4 Tue 01/09/20 Mon 04/01/21 improvements 181 DRAINAGE Aspley Guise Flood Mitigation- Village wide Aspley Guise Aspley & Woburn Investigation and Design Q2,3 Fri 01/05/20 Wed 06/01/21 Flood Risk Team 182 DRAINAGE Aspley Guise Flood Mitigation- DESIGN/ Village wide Aspley Guise Aspley & Woburn 2 Design RJ Q2,3 Mon 03/08/20 Fri 04/12/20 Flood Risk Team INVESTIGATION 183 DRAINAGE Aspley Guise Flood Mitigation- CONSTRUCTION Village wide Aspley Guise Aspley & Woburn 2 Construction RJ Q2,3 Fri 01/01/21 Wed 31/03/21 Flood Risk Team 184 DRAINAGE Broken Gully Connections INVESTIGATION Countywide Countywide Countywide 1,2,3 Improvements recommended by cyclic RJ Q1,2 Wed 01/04/20 Tue 04/08/20 gully reports 185 DRAINAGE Grips/Offlets improvements CONSTRUCTION Countywide Countywide Countywide 1,2,3 Ongoing asset maintenance/upgrade External Q1,2 Mon 06/04/20 Fri 07/08/20

186 DRAINAGE Survey and Inventory Work SURVEY Countywide Countywide Countywide 1,2,3 Inventory updates for asset RJ Q2,3,4 Wed 01/07/20 Wed 31/03/21 management work 187 DRAINAGE Engineering Input / Ad Hoc CONSTRUCTION Countywide Countywide Countywide 1,2,3 To assist flood risk team and other RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 council departments 188 DRAINAGE Blackburn Road DESIGN ADDED Houghton Regis Countywide 3 To assist flood risk team and other RJ Q1 Wed 01/04/20 Wed 31/03/21 council departments 189 DRAINAGE CARRY OVER SCHEMES Q1 Wed 01/04/20 Wed 01/04/20 2019-20 190 DRAINAGE TBC-Jan-Feb 2020 Q1 Wed 01/04/20 Wed 01/04/20

Page 2 CENTRAL BEDFORDSHIRE ANNUAL PLAN 2020-21 ID Workstream Task Name Stages Scheme Road Name Parish Ward Area Scheme Description Allocation Month LA Start Finish Status expected in 191 STREET LIGHTING STREET LIGHTING Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

192 STREET LIGHTING Structural & Electrical Testing SURVEY Various locations Countywide Countywide Countywide Testing Surveys External Q1 Wed 01/04/20 Tue 30/06/20 20/21 193 STREET LIGHTING Private Cable Network Survey SURVEY Various locations Countywide Countywide Countywide Cable Surveys External Q1 Wed 01/04/20 Tue 30/06/20

194 STREET LIGHTING Structural Column Various locations Countywide Countywide Countywide Column Replacements. RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 Replacements Following 19/20 Results 1000 Cols 195 STREET LIGHTING Structural Column CONSTRUCTION Various locations Countywide Countywide Countywide Column Replacements. RJ Q1,2,3,4 Wed 01/04/20 Tue 01/09/20 Replacements Following 19/20 196 STREET LIGHTING StructuralResults 1000 Column Cols MATERIALS Various locations Countywide Countywide Countywide Lanterns RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 Replacements Following 19/20 197 STREET LIGHTING StructuralResults 1000 Column Cols MATERIALS Various locations Countywide Countywide Countywide Columns External Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 Replacements Following 19/20 Results 1000 Cols 198 STREET LIGHTING New Schemes CONSTRUCTION Various locations Countywide Countywide RJ Q1,2,3,4 Wed 01/04/20 Tue 30/06/20

199 STREET LIGHTING Porz Avenue CONSTRUCTION Porz Avenue Countywide Countywide Countywide New Lighting Scheme RJ Q1 Wed 01/07/20 Tue 29/09/20

200 STREET LIGHTING Husborne Crawley, jctn 13 CONSTRUCTION Bedford Road Husborne Crawley Aspley & Woburn 2 LRP - Lantern Replacement Programme TBC Q1 Wed 01/04/20 Tue 30/06/20 truck stop 201 STREET LIGHTING Leighton Buzzard Town Centre CONSTRUCTION High Street Leighton Buzzard Leighton Buzzard 2 LRP - Lantern Replacement Programme TBC Q1 Wed 01/04/20 Tue 30/06/20 South 202 STREET LIGHTING Leighton Buzzard Induction CONSTRUCTION Lake Street Leighton Buzzard Leighton Buzzard 2 LRP - Lantern Replacement Programme TBC Q1 Wed 01/04/20 Tue 30/06/20 South 203 STREET LIGHTING Shefford, North & South Bridge CONSTRUCTION North & South Shefford Shefford 1 LRP - Lantern Replacement Programme TBC Q1 Wed 01/04/20 Tue 30/06/20 Street Bridge Street 204 STREET LIGHTING Leighton Buzzard, Heritage CONSTRUCTION Mkt Square, High Leighton Buzzard Leighton Buzzard 2 LRP - Lantern Replacement Programme TBC Q1 Wed 01/04/20 Tue 30/06/20 Street, Church South Square

205 STREET LIGHTING A6 CONSTRUCTION Whole of A6. From Houghton Conquest Houghton Conquest & 2,3 LRP - Lantern Replacement Programme TBC Q2,3 Wed 01/04/20 Tue 30/06/20 Bedford Road to Luton Haynes, Ampthill, Silsoe & Shillington, Barton-Le-Clay, Toddington 206 CRSF CO-ORDINATED Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 REPLACEMENT STREET 207 STREET LIGHTING FURNITURECRSF Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

208 STREET LIGHTING Co-ordinated Replacement CONSTRUCTION Various locations Countywide Countywide Emergency disconnections & removal of RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 Street Furniture columns/lanterns 209 STREET LIGHTING CARRY OVER SCHEMES Q1 Wed 01/04/20 Fri 01/05/20 2019-20 210 STREET LIGHTING Structural Column CONSTRUCTION C/ OVER Various locations Countywide Countywide Countywide Column Replacements. RJ Q1 Wed 01/04/20 Fri 01/05/20 Replacement Scheme to SCHEME replace 877 column that have been identified following the Structural Testing Programme 211 STREET LIGHTING TBC-Jan-Feb 2020 Q1 Wed 01/04/20 Wed 01/04/20

212 STREET LIGHTING CMS Works Q2,3 Wed 01/07/20 Thu 31/12/20

213 STREET LIGHTING CMS Base Stations/Nodes CONSTRUCTION Various locations Countywide Countywide Countywide External Q2,3 Wed 01/07/20 Thu 31/12/20

214 A5 De- Trunking A5 De-Trunking Q1 Wed 01/04/20 Wed 24/06/20

215 STREET LIGHTING A5 De-Trunking CONSTRUCTION A5 Dunstable Dunstable Watling 3 Replacement of Columns, Lanterns & External Q1 Wed 01/04/20 Wed 01/04/20 signs 216 STRUCTURAL A5 De-Trunking CONSTRUCTION A5 Dunstable Dunstable Watling 3 Re-instatement of kerbs, repairs of RJ Q1 Wed 01/04/20 Wed 31/03/21 MAINTENANCE several defects to bring the road to 217 INTEGRATED INTEGRATED TRANSPORT adoptable standard. Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 TRANSPORT 218 INTEGRATED RMF Small Schemes Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 TRANSPORT 219 INTEGRATED Bedford Road CONSTRUCTION Bedford Road Northill 1 Gateways and lining etc at various roads RJ Q1,2 Wed 01/04/20 Wed 30/09/20 TRANSPORT surrounding village 220 INTEGRATED Church Road CONSTRUCTION Church Road Totternhoe Eaton Bray 3 Lining and signing works, o/s School. To RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT be done in school holidays 222 INTEGRATED Norton Road CONSTRUCTION Norton Road Stotfold Stotfold & Langford 1 Table and associated works RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT 223 INTEGRATED Woodside Road CONSTRUCTION Woodside Road Woodside Caddington 3 Calming feature- subject to TM mid RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT March Confirmation 224 INTEGRATED Station Road CONSTRUCTION Station Road Tempsford Potton 1 Surfacing to provide parking area. W&T Q2,3 Tue 01/09/20 Mon 30/11/20 TRANSPORT to advise on scope and BOQ's to 225 INTEGRATED The Green DESIGN The Green Clophill Ampthill 2 Designhappen. to alter the current layout to RJ Q1 Wed 01/04/20 Tue 30/06/20 TRANSPORT enabke buses to pass. 226 INTEGRATED Dunstable Rd Dunstable Road Heath & Reach 2 Gateway treatment RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 TRANSPORT 227 INTEGRATED Dunstable Rd DETAILED DESIGN Dunstable Road Tilsworth Heath & Reach 2 Gateway treatment RJ Q1,2,3,4 Wed 01/04/20 Tue 30/06/20 TRANSPORT 228 INTEGRATED Dunstable Rd CONSTRUCTION Dunstable Road Tilsworth Heath & Reach 2 Gateway treatment RJ Q1,2,3,4 Thu 01/10/20 Wed 31/03/21 TRANSPORT 229 INTEGRATED Local Safety Schemes Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 TRANSPORT 230 INTEGRATED Marston Bypass Marston Marston Moretaine Cranfield & Marston 2 Overshooting of roundabout, signage Q1,2,3,4 Wed 01/04/20 Mon 01/03/21 TRANSPORT Moretaine improvements in surrounding area 231 INTEGRATED Marston Bypass DESIGN Marston Marston Moretaine Cranfield & Marston 2 Overshooting of roundabout, signage RJ Q1 Wed 01/04/20 Fri 19/06/20 TRANSPORT Moretaine improvements in surrounding area 232 INTEGRATED Marston Bypass CONSTRUCTION Marston Marston Moretaine Cranfield & Marston 2 Overshooting of roundabout, signage Q2,3,4 Fri 17/07/20 Mon 01/03/21 TRANSPORT Moretaine improvements in surrounding area 233 INTEGRATED Sheep Lane CONSTRUCTION Sheep Lane Woburn Aspley & Woburn 2 Lining and signing works. HIGH RJ Q1,2 Wed 01/04/20 Fri 31/07/20 TRANSPORT PRIORITY 234 INTEGRATED Langford Road CONSTRUCTION Langford Road Langford Stotfold & Langford 1 Speed management, pair of cushions. RJ Q2,3 Wed 01/07/20 Mon 30/11/20 TRANSPORT TM required. 238 INTEGRATED Cedars Way DESIGN Wing Road/ Cedars Leighton Buzzard Linslade 2 Collision reduction RJ Q1,2,3 Wed 01/04/20 Thu 31/12/20 TRANSPORT Way junction 239 INTEGRATED High Street South DESIGN A5183 Kensworth Caddington 3 Collision reduction RJ Q1,2,3 Wed 01/04/20 Thu 31/12/20 TRANSPORT 240 INTEGRATED Broughton Road Broughton Road Salford Cranfield & Marston 2 40mph limit signage RJ Q1 Wed 01/04/20 Thu 30/04/20 TRANSPORT Moretaine 241 INTEGRATED Broughton Road DETAILED DESIGN C/ OVER Broughton Road Salford Cranfield & Marston 2 40mph limit signage RJ Q1 Wed 01/04/20 Thu 30/04/20 TRANSPORT SCHEME Moretaine 242 INTEGRATED Broughton Road CONSTRUCTION Broughton Road Salford Cranfield & Marston 2 40mph limit signage External Q1 Mon 03/08/20 Tue 05/01/21 TRANSPORT Moretaine 243 INTEGRATED Ampthill Road High Street Clophill Ampthill 1 WARREN LANE JUNCT TO PRIORY RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 TRANSPORT RD RBT- 244 INTEGRATED Ampthill Road FEE PROPOSAL High Street Clophill Ampthill 1 WARREN LANE JUNCT TO PRIORY RJ Q1 Wed 01/04/20 Fri 17/04/20 TRANSPORT RD RBT 245 INTEGRATED Ampthill Road OUTLINE DESIGN High Street Clophill Ampthill 1 WARREN LANE JUNCT TO PRIORY RJ Q1,2 Wed 01/04/20 Wed 30/09/20 TRANSPORT RD RBT 246 INTEGRATED Ampthill Road DETAILED DESIGN High Street Clophill Ampthill 1 WARREN LANE JUNCT TO PRIORY RJ Q4 Mon 15/03/21 Wed 31/03/21 TRANSPORT RD RBT 247 INTEGRATED Bridleway Luton Road Toddington Toddington 2 Speed reduction, speed limit change, RJ Q1,2,3,4 Mon 03/08/20 Wed 31/03/21 TRANSPORT HGV prevention measures 248 INTEGRATED Fancott Bridleway DETAILED DESIGN Luton Road Toddington Toddington 2 Speed reduction, speed limit change, RJ Q1 Mon 03/08/20 Mon 30/11/20 TRANSPORT HGV prevention measures 249 INTEGRATED Fancott Bridleway CONSTRUCTION Luton Road Toddington Toddington 2 Speed reduction, speed limit change, RJ Q2,3 Fri 01/01/21 Wed 31/03/21 TRANSPORT HGV prevention measures 250 INTEGRATED Public Transport Q1,2,3 Wed 01/04/20 Fri 04/09/20 TRANSPORT 252 INTEGRATED Ampthill Road CONSTRUCTION Ampthill Road Ampthill / Flitwick Ampthill / Flitwick 2 Bus Stop Improvements RJ Q1,2 Wed 01/04/20 Fri 04/09/20 TRANSPORT 253 INTEGRATED Highways Capacity & Traffic Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 TRANSPORT Management 254 INTEGRATED Leighton Road DESIGN Leighton Road Heath & Reach Heath & Reach 2 Traffic calming & review speed limits RJ Q1 Wed 01/04/20 Tue 30/06/20 TRANSPORT from Shenley Hill Rd to Woburn Rd/ 255 INTEGRATED Byslips Road CONSTRUCTION Byslips Road Studham Caddington 2 Rd-Brickhill Brckill Jctn. road Bus junction Stop upgrades to be RJ Q1,2 Fri 01/05/20 Wed 30/09/20 TRANSPORT 256 INTEGRATED Beech Road CONSTRUCTION Beech Road Dunstable Dunstable Watling, 3 any upgrades to bus stops also-cd to RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT Caddington confirm with public transport re future of 257 INTEGRATED Bedford Road CONSTRUCTION Bedford Rd Marston Moretaine Cranfield & Marston 2 90services deg parking here area, raised kerbing RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT Moretaine works. 258 INTEGRATED A507/Sandhill's Junction CONSTRUCTION A507 junction with Millbrook Cranfield & Marston 2 Junction changes RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT Sandhill Close Moretaine 259 INTEGRATED Bideford Green CONSTRUCTION Bideford Green Leighton Buzzard Linslade 2 20mph works outside of school. Raised EHA Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT tables, and cycle ways. To be done in 260 INTEGRATED Friars Walk CONSTRUCTION Friars Walk Dunstable Dunstable Central 3 Trafficschool Calmingsummer &holidays. footway works, to be RJ Q1,2 Wed 01/04/20 Fri 07/08/20 TRANSPORT done in school holidays. Subject to 261 INTEGRATED Harlington Road (To be CONSTRUCTION Harlington Road Sharpenhoe Toddington 3 TrafficTMM. LiaisonCalming with & footway SP required works, to be RJ Q2,3,4 Wed 01/07/20 Wed 31/03/21 TRANSPORT Patched in 19/20 FY and SD in combined w/ SM works. Lighting & 262 INTEGRATED CliftonQ2 20/21) Rd CONSTRUCTION Mill Road Stanford Northill 1 SpeedSignage Limit works Change also to happen. 30K RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT 263 INTEGRATED Heath Road DESIGN Heath Road Leighton Buzzard Leighton Buzzard North 2 From Shenley Hill to North Court F/W RJ Q1,2 Wed 01/04/20 Fri 31/07/20 TRANSPORT widening 264 INTEGRATED Lowther Road Lowther Road Dunstable Dunstable Watling 3 Calming RJ Q1,2,3,4 Wed 01/04/20 Fri 29/01/21 TRANSPORT 265 INTEGRATED Lowther Road FEE PROPOSAL Lowther Road Dunstable Dunstable Watling 3 Calming RJ Q1,2,3,4 Wed 01/04/20 Fri 29/01/21 TRANSPORT 266 INTEGRATED Common Road DETAILED DESIGN Common Road Kensworth Caddington 3 Speed Management. Outside school. RJ Q1,2,3,4 Wed 01/04/20 Fri 29/01/21 TRANSPORT 267 INTEGRATED Old Hill OUTLINE DESIGN Old Hill Dunstable Dunstable Watling 3 Traffic Calming measures RJ Q1 Wed 01/04/20 Fri 12/06/20 TRANSPORT 268 INTEGRATED Old Hill CONSULTATION Old Hill Dunstable Dunstable Watling Traffic Calming measures RJ Q1 Wed 01/04/20 Fri 12/06/20 TRANSPORT 269 INTEGRATED Drovers Way/Brewers Hill OUTLINE DESIGN C/ OVER Drovers Way / Dunstable Dunstable Northfields 3 Speed limit review RJ Q1 Wed 01/04/20 Tue 30/06/20 TRANSPORT SCHEME Brewers Hill Road / 270 INTEGRATED Drovers Way/Brewers Hill CONSULTATION C/ OVER Drovers Way / Dunstable Dunstable Northfields 3 Speed limit review RJ Q1 Wed 01/04/20 Tue 30/06/20 TRANSPORT SCHEME Brewers Hill Road / 271 INTEGRATED Linslade Road DESIGN Linslade Road Heath & Reach Heath & Reach 3 Traffic Calming and speed limit review. RJ Q1,2,3 Wed 01/04/20 Thu 31/12/20 TRANSPORT 272 INTEGRATED Windsor Drive OUTLINE DESIGN Windsor Drive Houghton Regis Houghton Hall 3 Traffic Calming RJ Q1,2 Wed 01/04/20 Fri 17/07/20 TRANSPORT 273 INTEGRATED Windsor Drive CONSULTATION Windsor Drive Houghton Regis Houghton Hall 3 Traffic Calming RJ Q1,2 Wed 01/04/20 Fri 17/07/20 TRANSPORT 274 INTEGRATED Boscombe Road OUTLINE DESIGN Boscombe Road Dunstable Dunstable Icknield 3 Junction capacity improvement RJ Q1 Wed 01/04/20 Tue 30/06/20 TRANSPORT 275 INTEGRATED Boscombe Road CONSULTATION Boscombe Road Dunstable Dunstable Icknield 3 Junction capacity improvement RJ Q1 Wed 01/04/20 Tue 30/06/20 TRANSPORT 276 INTEGRATED Grovebury Road, Leighton OUTLINE DESIGN Grovebury Road Leighton Buzzard Leighton Buzzard 2 Junction capacity improvement RJ Q1,2 Wed 01/04/20 Fri 24/07/20 TRANSPORT Buzzard (retail park) South 277 INTEGRATED Shenley Hill Road DESIGN Shenley Hill Road Dunstable Leighton Buzzard North 3 Traffic calming & Possible speed limit RJ Q1 Wed 01/04/20 Tue 30/06/20 TRANSPORT alteration 278 INTEGRATED Mill Road CONSTRUCTION Mill Road Stanbridge Heath & Reach 2 Traffic Calming measures. – RJ Q1,2 Wed 01/04/20 Fri 31/07/20 TRANSPORT construction to be aligned with Structural 279 INTEGRATED Church Road CONSTRUCTION Church Road Studham Caddington 3 WorksMaintenance in school resurfacing, area to build Silv footwayis to (to RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT be carried out in holidays.)

Page 3 CENTRAL BEDFORDSHIRE ANNUAL PLAN 2020-21 ID Workstream Task Name Stages Scheme Road Name Parish Ward Area Scheme Description Allocation Month LA Start Finish Status expected in 280 INTEGRATED Hitchin Road () DESIGN Hitchin Road Arlesey 1 Measures to deter HGV/traffic from rat RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT running (past the RAF Base) Design 281 INTEGRATED Brewers Hill Road DESIGN Brewers Hill Road Leighton Buzzard Leighton Buzzard North 3 designorder issued of traffic April calming – end date per rough RJ Q3,4 Thu 01/10/20 Wed 31/03/21 TRANSPORT 283 INTEGRATED Ad Hoc advice DESIGN Thorn Road various 3 300 hrs RJ Q1 Wed 01/04/20 Tue 30/06/20 TRANSPORT 284 INTEGRATED ATC: Various DESIGN Thorn Road various Numerous ATC counts as listed in box RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 TRANSPORT throughout the year. 285 INTEGRATED Active Travel (Walking & Q1,2 Wed 01/04/20 Wed 30/09/20 TRANSPORT Cycling inc. Safer Routes to 287 INTEGRATED Schools)Dunton Lane CONSTRUCTION Dunton Lane Biggleswade Biggleswade South 1 Uncontrolled crossing Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT 289 INTEGRATED Dunton Lane CONSTRUCTION Dunton Lane Biggleswade Biggleswade South 1 Uncontrolled crossing Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT 291 INTEGRATED College Road CONSTRUCTION College Road Cranfield Cranfield & Marston 2 Raised junction- To be constructed in Q2 Wed 01/07/20 Wed 30/09/20 TRANSPORT Moretaine spring/ summer when University is not 292 INTEGRATED Church Road CONSTRUCTION Church Road Studham Caddington 3 Footwaysfunctioning construction close to school. Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT Road closure needed. To be done on 293 INTEGRATED Clayhall Road CONSTRUCTION C/ OVER Clayhall Road Kensworth Caddington 3 LiningSummer and hols.Subject signing works to consultation& speed limit RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT SCHEME change. To be programmed for school 294 INTEGRATED Potton Road DESIGN Potton Road Sandy Sandy 1 Constructionholidays. of Cycle Innovation RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT scheme, signing and lining along route 295 INTEGRATED Potton Road CONSTRUCTION Potton Road Sandy Sandy 1 Construction of Cycle Innovation RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT scheme, signing and lining along route 296 INTEGRATED Grovebury Road Footpath Grovebury Road Leighton Buzzard Leighton Buzzard New footway connecting to Retail Q1 Wed 01/04/20 Tue 30/06/20 TRANSPORT South Park 297 INTEGRATED Grovebury Road Footpath CONSTRUCTION Grovebury Road Leighton Buzzard Leighton Buzzard 2 New footway connecting to Retail Park Q1 Wed 01/04/20 Tue 30/06/20 TRANSPORT South 298 INTEGRATED Tottenhoe Road Dunstable ON HOLD Totternhoe Road Dunstable Dunstable Watling 3 Construction of crossing - TO BE IN Q1 Wed 01/04/20 Tue 30/06/20 TRANSPORT SCHOOL HOLIDAYS. Awaiting school 299 INTEGRATED Tottenhoe Road Dunstable DETAILED DESIGN ON HOLD Totternhoe Road Dunstable Dunstable Watling 3 ConstructionTravel Plans. of crossing - TO BE IN Q1 Wed 01/04/20 Tue 30/06/20 TRANSPORT SCHOOL HOLIDAYS. Awaiting school 300 INTEGRATED Tottenhoe Road Dunstable CONSTRUCTION ON HOLD Totternhoe Road Dunstable Dunstable Watling 3 ConstructionTravel Plans. of crossing - TO BE IN Q1 Wed 01/04/20 Tue 30/06/20 TRANSPORT SCHOOL HOLIDAYS. Awaiting school 301 INTEGRATED A5120 Park Road A5120 Westoning, & 2 ConstructionTravel Plans. of Zebra Xing Q1,2,3,4 Wed 01/04/20 Fri 29/01/21 TRANSPORT Greenfield 302 INTEGRATED A5120 Park Road CONCEPT DESIGN A5120 Westoning Westoning, Flitton & 2 Construction of Zebra Xing Q1,2,3 Wed 01/04/20 Fri 29/01/21 TRANSPORT Greenfield 303 INTEGRATED A5120 Park Road CONSTRUCTION A5120 Westoning Westoning, Flitton & 2 Construction of Zebra Xing Q4 Wed 01/04/20 Fri 29/01/21 TRANSPORT Greenfield 304 INTEGRATED Hexton Road Hexton Road Barton-Le-Clay Barton-Le-Clay 2 alterations to junction - crosisng RJ Q1,2,3,4 Wed 01/04/20 Fri 29/01/21 TRANSPORT point 305 INTEGRATED Hexton Road DESIGN Hexton Road Barton-Le-Clay Barton-Le-Clay 2 alterations to junction - crossing point RJ Q1 Wed 01/04/20 Fri 19/06/20 TRANSPORT 306 INTEGRATED Hexton Road CONSTRUCTION Hexton Road Barton-Le-Clay Barton-Le-Clay 2 alterations to junction - crossing point. RJ Q1,2,3,4 Wed 01/04/20 Fri 29/01/21 TRANSPORT Site construction to be co-ordinated with 309 INTEGRATED Sandy Road DESIGN Sandy Road Potton Potton 1 (sectionjunction resurfacingfrom Sandy into 2020. RSPB) RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT completion of f/w widening at various 310 INTEGRATED Meadow Way DESIGN Meadow Way Leighton Buzzard Leighton Buzzard North 2 design/siteareas to +/- clearance 2.5m. Design for footway order issued from RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT Danes Field - Appenine Way some 311 INTEGRATED Woodman Close DESIGN Woodman Close Leighton Buzzard Leighton Buzzard 2 Woodmanworks are offClose highway (alongside brook then RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT South across greenspace and in front of 312 INTEGRATED Leopold Road DESIGN Leopold Road Linslade Linslade 2 Cyclesubstation contraflow with pedestrian in Leopold route Road behind RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT widening of alleyway to be shared use 313 ROW Half Moon Lane. (Company CONSTRUCTION Half Moon Lane Dunstable Dunstable Manshead 3 3-4mdesign wide to be footway 2020/21 to be installed on RJ Q1 Wed 01/04/20 Tue 30/06/20 doing vegetation clearance ROW route. Requested by Police. 314 INTEGRATED Trafficaspires Managementto deliver the scheme. Provision for lighting to be included in Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 TRANSPORT Implementation 315 INTEGRATED Scheme 1 DESIGN TBC TBC TBC Schemes to be added as per TMM RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 TRANSPORT outcome 316 INTEGRATED Scheme 2 DESIGN TBC TBC TBC Schemes to be added as per TMM RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 TRANSPORT outcome 317 CARRY OVER SCHEMES Q1,2 Wed 01/04/20 Mon 31/08/20 2019-20 318 INTEGRATED Bedford Road DESIGN C/ OVER Bedford Road Cranfield & Marston 2 937127 BEDFORD ROAD RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT SCHEME Moretaine BROGBOROUGH completion of 319 INTEGRATED Bedford Road CONSTRUCTION C/ OVER Bedford Road Barton Le-Clay Barton Le-Clay 2 A6scheme Speed from the 19/20Plough AgreedJucntion Target RJ Q1 Wed 01/04/20 Tue 30/06/20 TRANSPORT SCHEME Constrction of scheme as per designs, lining signing and wescotec signs (electronic) 320 INTEGRATED Everton Road DETAILED DESIGN C/ OVER Everton Road Potton Potton 1 RJ Q1 Wed 01/04/20 Tue 30/06/20 TRANSPORT SCHEME

321 INTEGRATED RESERVE LIST 2020-21 Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 TRANSPORT 322 INTEGRATED Sunderland Road CONSTRUCTION Sunderland Road Sandy Sandy 1 Construction of footway widening in RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT sundeland road value to be increased 323 INTEGRATED Everton Road CONSTRUCTION C/ OVER Everton Road Potton Potton 1 1xonce Cushions target agreed. as calming. Dates Outside to be RJ Q1,2,3 Wed 01/04/20 Thu 24/12/20 TRANSPORT SCHEME School. To be done uin summer hols. 324 INTEGRATED Wrestlingworth Road CONSTRUCTION Wrestlingworth Road Potton Potton 1 Lining works RJ Q1,2,3 Wed 01/04/20 Mon 30/11/20 TRANSPORT 325 INTEGRATED Woburn Road CONSTRUCTION Woburn Road Millbrook Cranfield & Marston 2 938296 Woburn Road Amphthill RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT Moretaine Construction of 2x bus laybys on A507 326 INTEGRATED South Street DESIGN South Street / Leighton Buzzard Leighton Buzzard 2 One-Waynear roundabout @ Millbrook TO was RJ Q2,3,4 Wed 01/07/20 Mon 01/03/21 TRANSPORT Brooklands Avenue South 327 INTEGRATED Regent Street DESIGN Regent Street / Leighton Buzzard Leighton Buzzard North 2 One-Way RJ Q2,3,4 Wed 01/07/20 Mon 01/03/21 TRANSPORT George Street 328 INTEGRATED Lowther Road DETAILED DESIGN Lowther Road Dunstable Dunstable Watling 3 Calming RJ Q1,2,3,4 Wed 01/04/20 Fri 29/01/21 TRANSPORT 329 INTEGRATED Langdale Road DETAILED DESIGN Langdale Road Dunstable Dunstable Watling 3 Concept Design of speed measures on RJ Q3,4 Thu 01/10/20 Wed 31/03/21 TRANSPORT Langdale Road Dunstable in anticipation 330 INTEGRATED Clophill Road CONSTRUCTION Clophill Road Gravenhurst Silsoe & Shillington 1 Buildof speed out cameraand lining removal. works for gateways RJ Q1,2 Wed 01/04/20 Mon 31/08/20 TRANSPORT 331 INTEGRATED Hillside Road CONSTRUCTION Hillside Road Dunstable Dunstable Manshead 3 Speed management, construction of no RJ Q2,3,4 Fri 21/08/20 Mon 01/03/21 TRANSPORT through route. Consultation to be carried out.

332 INTEGRATED Bridge End Road CONSTRUCTION Arlesey Station Arlesey Arlesey 1 Cycle / Pedestrian Access RJ Q1,2,3 Wed 01/04/20 Mon 30/11/20 TRANSPORT Improvements. May need night work.

333 BRIDGES & BRIDGES & STRUCTURES Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 STRUCTURES 336 BRIDGES & Abbey Farm Railway Bridge CONSTRUCTION Old Warden Old Warden Northill 1 Strengthening RJ Q1 Mon 27/04/20 Fri 12/06/20 STRUCTURES 337 BRIDGES & Blunham Railway Ret. Walls DESIGN Station Road Blunham Sandy 1 Design for Demolition & regrading of RJ Q2,3 Mon 05/10/20 Fri 06/11/20 STRUCTURES (UC020) embankments 338 BRIDGES & Blunham Railway Ret. Walls DESIGN Station Road Blunham Sandy 1 Design for Demolition & regrading of RJ Q2,3 Mon 05/10/20 Fri 06/11/20 STRUCTURES (UC020) embankments 339 BRIDGES & A507 Armco Culverts Q1 Mon 20/04/20 Fri 15/05/20 STRUCTURES 341 BRIDGES & CARRY OVER SCHEMES Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 STRUCTURES 2019-20 342 BRIDGES & Hulcote Mill Culvert (478) DETAILED DESIGN C/ OVER Mill Lane Hulcote & Salford Cranfield & Marston 2 Strengthening RJ Q1 Mon 13/04/20 Fri 08/05/20 STRUCTURES SCHEME Moretaine 343 BRIDGES & Bridge Farm Culvert (103) CONSTRUCTION C/ OVER Bedford Road Moggerhanger Northill 1 Strengthening RJ/ External Q1 Mon 27/04/20 Fri 22/05/20 STRUCTURES SCHEME 344 BRIDGES & Bridge Farm Cul CONSTRUCTION C/ OVER Bedford Road Sandy Sandy 1 Construction of brick Parapet and wing Q1 Wed 01/04/20 Wed 01/04/20 STRUCTURES A603,(103)(Construction) SCHEME walls & foundations and any ancillary 345 BRIDGES & Bridge Farm Cul A603,(103)( CONSTRUCTION C/ OVER Bedford Road Sandy Sandy Investigateassociated works.for backing & re-assess. If Q1 Wed 01/04/20 Fri 01/05/20 STRUCTURES Civils) SCHEME NO backing found then Strengthen brick 347 BRIDGES & Hollington Basin Bridge (268)- CONSTRUCTION C/ OVER Ampthill Road Flitton Westoning, Flitton & 2 Hollingtonarch carrying Basin the Bridgec/way &(268)- east Designverge Q1 Wed 01/04/20 Wed 01/04/20 STRUCTURES Construction SCHEME Greenfield -Strengthening of the structure in 348 BRIDGES & Hollington Basin Bridge (268)- CONSTRUCTION C/ OVER Ampthill Road Flitton Westoning, Flitton & 2 Hollingtonaccordance Basin with theBr, Ampthillagreed Target Road, Cost Q1 Wed 01/04/20 Wed 01/04/20 STRUCTURES Civils SCHEME Greenfield Flitton: (See notes) 350 BRIDGES & Abbey Farm Railway Bridge SURVEY C/ OVER Northill Northill 1 Carry out Environmental surveys to the Q1 Mon 27/04/20 Fri 12/06/20 STRUCTURES (HIB23) U148 (9023) SCHEME agreed Target Cost including relocation 354 ROW Mardle Road CONSTRUCTION Mardle Road Linslade Linslade 2 Addof badger non slip setts. surface to both Black RJ/ External Q2,3,4 Wed 01/07/20 Wed 31/03/21 bridge on cycleway off Grovebury Road 355 ROW Park Avenue CONSTRUCTION Park Avenue Silsoe Silsoe & Shillington 1 Replaceand White Parapets Bridge at end of Mardle RJ Q1,2,3 Wed 01/04/20 Fri 13/11/20

356 BRIDGES & RESERVE LIST 2020-21 Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 STRUCTURES 357 BRIDGES & Church End Farm (135) CONSTRUCTION ON HOLD School Lane Husborne Crawley Aspley & Woburn 2 Replacement RJ/ External Q2,3 Mon 20/07/20 Fri 09/10/20 STRUCTURES 358 BRIDGES & Flitwick Mill Br (262) CONSTRUCTION ON HOLD Greenfield Road Flitwick Flitwick 2 Civils/Brick work/ Strenghtning RJ/ External Q2 Mon 08/06/20 Fri 17/07/20 STRUCTURES

359 BRIDGES & Flitwick Mill Br (262) CONSTRUCTION ON HOLD Greenfield Road Flitwick Flitwick 2 Lining RJ/ External Q2 Mon 20/07/20 Fri 28/08/20 STRUCTURES

360 BRIDGES & Hulcote Mill Culvert (478) CONSTRUCTION ON HOLD Mill Lane Hulcote & Salford Cranfield & Marston 2 Strengthening External Q3 Mon 05/10/20 Fri 30/10/20 STRUCTURES Moretaine

361 BRIDGES & A507 Armco Culverts CONSTRUCTION ON HOLD A507 - Maulden - Clophill/Ampthill Ampthill 2 Design/ const. (2 Structures) RJ Q2 Mon 31/08/20 Fri 25/09/20 STRUCTURES Ampthill 362 BRIDGES & Blunham Railway Ret. Walls CONSTRUCTION ON HOLD Station Road Blunham Sandy 1 Construction for Demolition & regrading RJ Q4 Mon 11/01/21 Fri 19/02/21 STRUCTURES (UC020) of embankments 363 ROW ROW 2020-21 Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

364 ROW ROW Capital budget CONSTRUCTION 1,2,3,4 RJ Q1,2 Fri 01/05/20 Fri 28/08/20

365 ROW Green Lane CONSTRUCTION Green Lane Stewartby Cranfield & Marston 2 Construction works as per Design LA RJ Q1,2,3 Wed 01/04/20 Fri 27/11/20 Moretaine 223065 366 ROW New Road CONSTRUCTION New Road Maulden Ampthill 2 Build bank stabilization along Footpath 4 External Q1,2,3,4 Fri 01/05/20 Thu 28/01/21 off New Road Maulden. The bank is 367 ROW ROW: OTHER FUNDING 25m long behind a brick building and Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

368 ROW High Street High Street Cranfield Cranfield & Marston 2 50x2 m of DBM overlay RJ Q1,2,3,4 Fri 01/05/20 Fri 29/01/21 Moretaine 369 ROW High Street W&T High Street Cranfield Cranfield & Marston 2 50x2 m of DBM overlay RJ Q1 Fri 01/05/20 Mon 01/06/20 Moretaine 370 ROW High Street CONSTRUCTION High Street Cranfield Cranfield & Marston 2 50x2 m of DBM overlay RJ Q1,2,3,4 Fri 01/05/20 Fri 29/01/21 Moretaine 371 ROW Potton Road (Around Edward CONSTRUCTION Potton Road Biggleswade Biggleswade North 1 Installation of Light Columns RJ Q1,2,3 Fri 01/05/20 Wed 04/11/20 Peake School -S106) 372 ROW Potton Road (Around Edward CONSTRUCTION Potton Road Biggleswade Biggleswade North 1 Construction based on Walk, Talk to RJ Q1 Wed 01/04/20 Tue 30/06/20 Peake School -S106) agree specification. 413m x 2m wide of footway surfacing Excavate and tip existing material to half construction depth Option 1 footway DBM spec Option 2 Screened road arising blinded with limestone 6mm to dust

374 ROW Dunton Lane (Ph2) Biggleswade Biggleswade South 1 Q1,2,3 Wed 01/04/20 Fri 23/10/20

375 ROW Dunton Lane (Ph1&2) W&T Dunton Lane Biggleswade Biggleswade South 1 Section2 to be completed with a RJ Q1 Wed 01/04/20 Thu 02/04/20 separate LA Code and in 2020… See 376 ROW Dunton Lane (Ph2) CONSTRUCTION Dunton Lane Biggleswade Biggleswade South 1 Section2Notes for tofull be description completed with a RJ Q1,2 Wed 01/04/20 Mon 31/08/20 separate LA Code and in 2020… See 377 ROW Dunton Lane (Ph1) CONSTRUCTION Dunton Lane Biggleswade Biggleswade South 1 Section2Notes for tofull be description completed with a RJ Q1,2,3 Fri 01/05/20 Fri 23/10/20 separate LA Code and in 2020… See Notes for full description

Page 4 CENTRAL BEDFORDSHIRE ANNUAL PLAN 2020-21 ID Workstream Task Name Stages Scheme Road Name Parish Ward Area Scheme Description Allocation Month LA Start Finish Status expected in 378 ROW Froghall Road/ Fordefield Road CONSTRUCTION Froghall Road Ampthill Ampthill 2 1.1km x 2.5m of public cycleway to be RJ Q1,2,3 Fri 01/05/20 Fri 23/10/20 created. Excavate 75mm depth and put 379 ROW Mill Lane CONSTRUCTION Mill Lane Flitton & Greenfield Westoning, Flitton & 2 Replaceto both sides.Lay existing bridgeand compact with new 150mm External Q1 Wed 01/04/20 Tue 23/06/20 Greenfield bridleway Bridge 380 ROW Curlew Croft CONSTRUCTION Curlew Croft Leighton Buzzard Leighton Buzzard 2 Replace existing bridge with new External Q1,2,3,4 Fri 01/05/20 Thu 28/01/21 South bridleway Bridge 381 ROW Park Road CONSTRUCTION Park Road Westoning Westoning, Flitton & 2 Replace Bridge External Q4 Thu 05/11/20 Fri 04/12/20 Greenfield 382 ROW Bedford Road CONSTRUCTION C/ OVER Bedford Road Silsoe Silsoe & Shillington 1 Supply and install 6m long x 1.5m External Q1 Fri 01/05/20 Mon 01/06/20 SCHEME pedestrian kit bridge galvanised steel 383 ROW Baden Powell Way CONSTRUCTION C/ OVER Baden Powell Way Biggleswade Biggleswade North 1 Supplybeam with and timber install deck.5m long x 1.5m External Q1 Fri 01/05/20 Mon 01/06/20 SCHEME Biggleswade South pedestrian kit bridge galvanised steel 384 ROW Gypsy Lane CONSTRUCTION C/ OVER Gypsy Lane Old Warden Northill 1 Supplybeam with and timber install deck.8m long x 1.2m External Q1 Fri 01/05/20 Mon 01/06/20 SCHEME pedestrian kit bridge galvanised steel 385 ROW Girtford Bridge Slip Road CONSTRUCTION A603 Slip Road Sandy Sandy 1 Deliverybeam with of timbera surfaced deck cycleway 2m x RJ Q1,2,3,4 Fri 01/05/20 Thu 28/01/21 1.5km long from Girtford Bridge to the 386 ROW Watling Street Houghton Regis Houghton Hall 3 Q1,2 Wed 01/04/20 Tue 04/08/20 387 ROW Half Moon Lane. (Company doing W&T ADDED Half Moon Lane Dunstable Dunstable Manshead 3 WT for screened plannings surfacing RJ Q1 Wed 01/04/20 Tue 30/06/20 vegetation clearance aspires to 388 ROW Parkdeliver Avenue the scheme. TBC) W&T ADDED Park Avenue Silsoe Silsoe & Shillington 1 Replace Parapets RJ Q1,2,3 Wed 01/04/20 Fri 13/11/20

389 ROW Mardle Road W&T ADDED Mardle Road Linslade Linslade 2 Add non slip surface to both Black RJ/ External Q2,3,4 Wed 01/07/20 Wed 31/03/21 bridge on cycleway off Grovebury Road 390 ROW High Street W&T ADDED High Street Arlesey Arlesey 1 DBMand White repair Bridge 80x4m at Arlesey end of Mardlefootpath 1. RJ Q1,2 Mon 01/06/20 Fri 21/08/20 Near School, preferrably during school 391 ROW Church Road W&T ADDED Church Road Stotfold Stotfold & Langford 1 36m2hols. of new footway construction. RJ Q1 Mon 06/04/20 Fri 17/04/20 105m2 of Overlay. Paths around St 392 ROW Hitchin Street W&T ADDED Hitchin Street Biggleswade Biggleswade South 1 InstallationMarys Church of x6 Light Columns RJ Q2 Mon 03/08/20 Fri 07/08/20

393 ROW Sundon Road W&T ADDED Sundon Road Chalton Toddington 3 Flight of steps RJ Q1 Fri 01/05/20 Tue 30/06/20

394 ROW Hollicks Lane W&T ADDED Hollicks Lane Kensworth Caddington 3 Flight of steps RJ Q1,2 Fri 01/05/20 Mon 31/08/20

395 ROW Watling Street W&T ADDED BUT Watling Street Houghton Regis Houghton Hall 3 The walk, talk build of three sets of RJ Q4 Fri 29/01/21 Thu 29/04/21 ON HOLD steps in Houghton Regis. Two steps on 396 ROW Woburn Road CONSTRUCTION Woburn Road Lidlington Cranfield & Marston 2 1500m2Watling StreetPlacement South of of normal the roundabout aggregate RJ Q1,2 Wed 01/04/20 Fri 28/08/20 Moretaine and recycling material (plannings) & 397 ROW RESERVE LIST 2020-21 granite dust. Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

398 ROW Mill Lane CONSTRUCTION ON HOLD Mill Lane Biggleswade Biggleswade South 1 Rebuild, Refurb or replacement of External Q3 Thu 05/11/20 Wed 18/11/20 motorway crash barrier bridge 399 ROW Church Road CONSTRUCTION ON HOLD Church Road Flitwick Flitwick 2 Replace Bridge External Q3 Thu 05/11/20 Fri 04/12/20

400 ROW Road (Opp Jctn w/ CONSTRUCTION ON HOLD Steppingley Road Flitwick Flitwick 2 1000x2m Screen planning surfacing RJ Q1,2 Tue 23/06/20 Fri 21/08/20 Windmill Rd) 401 ROW The Ridgeway (Girtford Bridge CONSTRUCTION ON HOLD The Ridgeway Moggerhanger Northill 1 Construction of a 1.5km x 2m cycleway RJ Q1,2,3,4 Fri 01/05/20 Thu 28/01/21 Main Section) over an existing footpath from The 402 ROW Greenfields CONSTRUCTION ON HOLD Greenfields Shillington Silsoe & Shillington 1 18x3mRidgeway, slope Moggerhanger to be surfaced. to GirtfordPossible RJ Q1,2,3,4 Fri 01/05/20 Thu 28/01/21 brusheed concrete finished. 403 ROW Kimberwell Close (path off) CONSTRUCTION ON HOLD Kimberwell Close Toddington Toddington 3 40mx3m of concrete slabs RJ Q1,2,3,4 Fri 01/05/20 Fri 29/01/21

404 ROW Girtford Bridge Cycleway Culvert DESIGN ON HOLD The Ridgeway Moggerhanger Northill 1 Deliver the widening of an existing RJ Q2,3,4 Mon 31/08/20 Thu 28/01/21 culvert close to the DS Smith Packaging 405 ROW Girtford Bridge Cycleway Culvert CONSTRUCTION ON HOLD The Ridgeway Moggerhanger Northill 1 Deliverfactory the widening of an existing RJ Q1 Fri 01/05/20 Fri 28/05/21 culvert close to the DS Smith Packaging 406 ROW Watling Street FEE PROPOSAL ON HOLD Watling Street Houghton Regis Houghton Hall 3 Feefactory Proposal for a design scheme for a RJ Q1,2,3 Thu 04/06/20 Wed 07/10/20 pegasus Xing. Near Sewell Lane 407 ROW Watling Street DESIGN ON HOLD Watling Street Houghton Regis Houghton Hall 3 Design scheme for a pegasus Xing. RJ Q1,2,3 Thu 04/06/20 Wed 07/10/20 Near Sewell Lane 408 ROW Watling Street CONSTRUCTION ON HOLD Watling Street Houghton Regis Houghton Hall 3 Construction scheme for a pegasus RJ Q1,2,3,4 Fri 01/05/20 Thu 28/01/21 Xing. Near Sewell Lane 409 ROW High Street CONSTRUCTION ON HOLD High Street Cranfield Cranfield & Marston 2 See notes for further description. RJ Q4 Fri 01/01/21 Wed 31/03/21 Moretaine 410 ROW Woburn Road W&T ON HOLD Woburn Road Lidlington Cranfield & Marston 2 Walk, Talk to be repeated with sub RJ Q2,3 Wed 01/07/20 Fri 27/11/20 Moretaine contractor WT Screened road plannings surfacing 411 ROW Woburn Road CONSTRUCTION ON HOLD Woburn Road Lidlington Cranfield & Marston 2 1500m2 Placement of normal aggregate RJ Q1,2,3 Wed 01/04/20 Fri 27/11/20 Moretaine and recycling material (plannings) & 412 ROW Mill Lane CONSTRUCTION Mill Lane Biggleswade Biggleswade South 1 Constructiongranite dust. of Stage 1a Concept RJ Q1,2,3,4 Fri 01/05/20 Fri 29/01/21 Design of a series of discrete bank 413 HIGHWAYS HIGHWAYS PLANNED repairs along Footpath Biggleswade 21 Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 PLANNED MAINTENANCE 414 MAINTENANCEHIGHWAYS PLANNED Highways Planned Maintenance REACTIVE various locations various locations various locations 1,2,3 Reactive works. A single budget line Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 MAINTENANCE Area 1 is required per areas 1,2,3 415 ROW Hitchin Street CONSTRUCTION Hitchin Street Biggleswade Biggleswade South 1 Installation of x6 Light Columns RJ Q2 Mon 03/08/20 Fri 07/08/20

416 ROW High Street CONSTRUCTION High Street Arlesey Arlesey 1 DBM repair 80x4m Arlesey footpath 1. RJ Q1,2 Mon 01/06/20 Fri 21/08/20 Near School, preferrably during school 417 ROW Warden Road CONSTRUCTION Warden Road Northill Northill 1 Vegetationhols. clearance; (Trees) External Q1,2,3,4 Fri 01/05/20 Thu 28/01/21

418 HIGHWAYS PLANNED Highways Planned Maintenance REACTIVE various locations various locations various locations 1,2,3 Reactive works. A single budget line is Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 MAINTENANCE Area 2 required per areas 1,2,3 419 HIGHWAYS PLANNED Highways Planned Maintenance REACTIVE various locations various locations various locations 1,2,3 Reactive works. A single budget line Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 MAINTENANCE Area 3 is required per areas 1,2,3 420 ROW Harlington 1 DBM Wingate Road Harlington Toddington 3 RJ Q1 Wed 01/04/20 Tue 30/06/20

421 ROW Harlington 1 DBM W&T Wingate Road Harlington Toddington 3 repair the surface of existing DBM RJ Q1 Wed 01/04/20 Tue 05/05/20 footway between Robinson Crescent 422 ROW Harlington 1 DBM CONSTRUCTION Wingate Road Harlington Toddington 3 repairand Churchills the surface passing of existing across DBM Wingate RJ Q1 Mon 27/04/20 Tue 30/06/20 footway between Robinson Crescent 423 ROW Half Moon Lane. (Company doing CONSTRUCTION Half Moon Lane Dunstable Dunstable Manshead 3 Fencingand Churchills works. passing across Wingate RJ Q1,2 Mon 01/06/20 Fri 28/08/20 vegetation clearance aspires to deliver the scheme. TBC) 424 ROW Hillyfields CONSTRUCTION Hillyfields Dunstable Dunstable Watling 3 DBM surfacing on Dunstable 11 RJ Q1 Wed 01/04/20 Mon 01/06/20

425 POTHOLE ACTION POTHOLE ACTION FUND Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 FUND

426 POTHOLE ACTION PAF Area 1 REACTIVE various locations various locations various locations 1,2,3 Budget to be confirmed Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 FUND 427 POTHOLE ACTION PAF Area 2 REACTIVE various locations various locations various locations 1,2,3 Budget to be confirmed Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 FUND 428 POTHOLE ACTION PAF Area 3 REACTIVE various locations various locations various locations 1,2,3 Budget to be confirmed Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 FUND 429 HIGHWAYS HIGHWAYS TRAFFIC Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 TRAFFIC SIGNALS SIGNALS 430 REVENUE REVENUE PROGRAMME Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

431 REVENUE MISCELLANEOUS various locations various locations Central Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 Beds 432 REVENUE Crown Damage Repairs REACTIVE various locations various locations various locations Central Beds Ad hoc, reactive works Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

433 REVENUE Private Vehicle Crossovers REACTIVE various locations various locations various locations Central Beds Ad hoc, reactive works Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

434 REVENUE Fixed Cost Services REACTIVE various locations various locations various locations Central Beds Ad hoc, reactive works Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

435 REVENUE Busway Maint. Of Segregated REACTIVE various locations various locations various locations Central Beds Ad hoc, reactive works Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 Sections 436 REVENUE Commuted Sums REACTIVE various locations various locations various locations Central Beds Ad hoc, reactive works Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

437 REVENUE Rechargeable works REACTIVE various locations various locations various locations Central Beds Ad hoc, reactive works Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

438 REVENUE Emergency Response REACTIVE various locations various locations various locations Central Beds Ad hoc, reactive works Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

439 REVENUE Drainage works REACTIVE various locations various locations various locations Central Beds Ad hoc, reactive works Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

440 REVENUE WINTER MAINTENANCE various locations various locations Central Q2,3,4 Tue 01/09/20 Wed 31/03/21 Beds 441 REVENUE Winter Maintenance-lump sum REACTIVE various locations Winter Maintenance Works Q2,3,4 Tue 01/09/20 Wed 31/03/21

442 REVENUE Winter Maintenance-ad-hoc REACTIVE various locations Winter Maintenance Works; Ad Hoc/ Q2,3,4 Tue 01/09/20 Wed 31/03/21 Reactive 443 REVENUE HIGHWAYS AREA TEAM various locations various locations Central Ad hoc, reactive works Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 Beds 444 HIGHWAYS AREA Highways Area Team 1 REACTIVE various locations various locations various locations Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 TEAMS 445 HIGHWAYS AREA Highways Area Team 2 REACTIVE various locations various locations various locations Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 TEAMS 446 HIGHWAYS AREA Highways Area Team 3 REACTIVE various locations various locations various locations Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 TEAMS 447 REVENUE Highways Traffic Signals REACTIVE various locations various locations various locations Central Beds Ad hoc, reactive works Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

448 REVENUE HIGHWAYS BRIDGES various locations various locations Central Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 Beds 449 Safety Fencing (Structures & County Wide CBC Wide CBC Wide Central Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 Highways) Beds 450 INSPECTIONS & Safety Barriers – replacement/ CONSTRUCTION Central Beds Budget dependant Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 APPRAISALS removal 451 BRIDGE Bridge Joints Replacements County Wide CBC Wide CBC Wide 1 Budget dependant Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 STRENGTHENING 452 BRIDGE Sandy Bridge A603 (120) CONSTRUCTION Sandy Road Sandy Sandy 1 Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 STRENGTHENING 453 BRIDGE Braystone House Culver C70 Braystone 2 Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 STRENGTHENING 454 BRIDGE Braystone House Culver C70 CONSTRUCTION Central Beds Braystone 2 External Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 STRENGTHENING 455 BRIDGE Braystone House Culver C70 CONSTRUCTION Central Beds Braystone 2 External Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 STRENGTHENING 456 BRIDGES & Assessments & Reports County Wide CBC Wide Q1 Mon 06/04/20 Thu 28/05/20 STRUCTURES 457 BRIDGES & Stanbridgeford Cul (312) Stanbridgeford Stanbridge/ Totternhoe Heath & Reach/ Eaton 3 Assessment & Reports RJ Q1 Mon 06/04/20 Fri 24/04/20 STRUCTURES Road Bray 458 BRIDGES & Stanbridgeford Cul (312) DESIGN Stanbridgeford Road Stanbridge/ Totternhoe Heath & Reach/ Eaton 3 Assessment & Reports for Parapet RJ Q1 Mon 06/04/20 Fri 24/04/20 STRUCTURES Bray Design 459 BRIDGES & Stanbridgeford Cul (312) CONSTRUCTION Stanbridgeford Road Stanbridge/ Totternhoe Heath & Reach/ Eaton 3 Assessment & Reports RJ Q1 Mon 06/04/20 Fri 24/04/20 STRUCTURES Bray 460 BRIDGES & Holwelbury Culvert DESIGN A600 Stondon Arlesey 1 Assessment & Reports RJ Q1 Mon 18/05/20 Thu 28/05/20 STRUCTURES 462 BRIDGES & Park Bridge DESIGN Hill Lane (U158) Old Warden Northill 1 Assessment (Skew End) RJ Q1 Mon 18/05/20 Thu 28/05/20 STRUCTURES 463 BRIDGES & Inspections County Wide County Wide Q1 Wed 01/04/20 Fri 15/05/20 STRUCTURES 464 BRIDGES & General Inspections Conty Wide County Wide 3 cyclic schemes carried out throughout RJ Q1 Wed 01/04/20 Tue 21/04/20 STRUCTURES the year on a Rolling Programme 465 BRIDGES & Principle Inspections Conty Wide County Wide 3 cyclic schemes carried out throughout RJ Q1 Mon 06/04/20 Fri 24/04/20 STRUCTURES the year on a Rolling Programme 467 BRIDGES & Confined Space Inspections Conty Wide County Wide 3 cyclic schemes carried out throughout RJ Q1 Mon 06/04/20 Fri 24/04/20 STRUCTURES the year on a Rolling Programme 468 BRIDGES & Harlington Rd. Embankment - CONSTRUCTION ON HOLD Harlington Road Toddington Toddington 2 Embankment Stabilisation & Footpath External Q1 Mon 20/04/20 Fri 15/05/20 STRUCTURES Stabilisation- to stay in capital (B5120) reconstruction - (provisional), budget although works are to be done by dependant Page 5 CENTRAL BEDFORDSHIRE ANNUAL PLAN 2020-21 ID Workstream Task Name Stages Scheme Road Name Parish Ward Area Scheme Description Allocation Month LA Start Finish Status expected in 469 STRUCTURES General Ad-Hoc advice County Wide County Wide Q1 Wed 01/04/20 Thu 07/05/20 470 HIGHWAYS STREET HIGHWAYS STREET LIGHTING County Wide County Wide Central Inspect & Repair various locations Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 LIGHTING Beds 471 CAR PARK CAR PARK MAINTENANCE Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 MAINTENANCE 472 Car Park Maintenance REACTIVE Various 1,2,3 Inspect & Repair various locations RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

473 Car Park Lines REACTIVE Various 1,2,3 Inspect & Repair various locations RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

474 Car Park Schemes REACTIVE Various 1,2,3 Inspect & Repair various locations RJ Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

475 EXTERNALLY FUNDED Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 SCHEMES 476 INTERDEPARTMENTAL INTERDEPARTMENTAL FUNDING Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 FUNDING 478 INTERDEPARTMENTAL St Andrew's (West) Biggleswade Biggleswade North 1 Shotmead street. School expansion. Q1,2,3,4 Tue 01/12/20 Wed 31/03/21 FUNDING Signs and lines and crossing points. 479 INTERDEPARTMENTAL Lancot Challenger Academy Dunstable Dunstable Watling 3 move to school programme Q3 Thu 01/10/20 Thu 31/12/20 FUNDING 480 INTERDEPARTMENTAL Lancot Challenger Academy DESIGN Lancot Drive Dunstable Dunstable Watling 3 Parking on verges outside school which RJ Q3 Thu 01/10/20 Thu 31/12/20 FUNDING is causing blocking access to Lancot 481 INTERDEPARTMENTAL New Fairfield Park Lower CONSTRUCTION Dickens Boulevard Stotfold Stotfold & Langford 1 MeasuresPlace - Extend to mitigate SKCs the+TRO. impact Budget of the will RJ Q3 Thu 01/10/20 Thu 31/12/20 FUNDING school expansion. Possibility of 482 INTERDEPARTMENTAL Church End Lower New Site (Forrest DESIGN Church Walk Marston Moretaine Cranfield & Marston 2 Measuresintegration toin mitigatethe Schools the impactfor the ofFuture the RJ Q3 Thu 01/10/20 Thu 31/12/20 FUNDING End) Moretaine school expansion. Possibility of 483 INTERDEPARTMENTAL Snow Hill CONSTRUCTION Snow Hill Maulden Ampthill 2 Lightingintegration and in or the footway Schools widening for the Futureon RJ Q1,2 Wed 01/04/20 Fri 31/07/20 FUNDING snow hill btween Ampthill and Maulden 484 INTERDEPARTMENTAL Engayne Avenue DETAILED DESIGN C/ OVER Engayne Avenue Sandy Sandy 2 design(upgrades) costs to for help carry with over children scheme walking for RJ Q1 Thu 23/04/20 Mon 25/05/20 FUNDING SCHEME cbc external 485 INTERDEPARTMENTAL Housing Parking Schemes Q2,3,4 Wed 01/07/20 Thu 31/12/20 FUNDING 486 INTERDEPARTMENTAL Benetts Close DESIGN Benetts Close Dunstable Dunstable Central 3 Creation of adaptions for housing RJ Q2,3,4 Wed 01/07/20 Thu 31/12/20 FUNDING parking area 487 INTERDEPARTMENTAL Priory Road DESIGN Priory Road Dunstable Dunstable Central 3 Creation of adaptions for housing RJ Q2,3,4 Wed 01/07/20 Thu 31/12/20 FUNDING parking area 488 INTERDEPARTMENTAL Park Avenue DESIGN Park Avenue Totternhoe Eaton Bray 3 Creation of adaptions for housing RJ Q2,3,4 Wed 01/07/20 Thu 31/12/20 FUNDING parking area 489 INTERDEPARTMENTAL Chartmoor Road CONSTRUCTION Chartmoor Road Leighton Buzzard Leighton Buzzard 3 300 linear mtrs footways widening RJ Q1,2,3 Wed 01/04/20 Fri 30/10/20 FUNDING South 490 INTERDEPARTMENTAL Sunderland Road CONSTRUCTION Sunderland Road Sandy Sandy 1 Shared use path Q1,2 Wed 01/04/20 Mon 31/08/20 FUNDING 491 INTERDEPARTMENTAL A 507 Millbrook CONSTRUCTION Woburn Aspley & Woburn 2 Bus Stop works. RJ Q1,2,3 Wed 01/04/20 Fri 30/10/20 FUNDING 492 INTERDEPARTMENTAL RESERVE LIST 2020-21 Wed 01/04/20 Wed 31/03/21 FUNDING 493 INTERDEPARTMENTAL St Andrew's (West) DESIGN ON HOLD Shortmead Street Biggleswade Biggleswade North 1 RJ Q1,2,3 Wed 01/04/20 Thu 30/07/20 FUNDING 494 INTERDEPARTMENTAL Spinney Crescent DESIGN ON HOLD Spinney Crescent Dunstable Dunstable Northfields 3 Creation of adaptions for housing RJ Q1,2,3 Wed 01/04/20 Thu 01/10/20 FUNDING parking area 495 INTERDEPARTMENTAL Housing Parking Schemes 5 DESIGN ON HOLD Ad hoc 2,3 More information available once CO Q1,2,3 Wed 01/04/20 Thu 01/10/20 FUNDING receives data from third party 496 INTERDEPARTMENTAL Old Oak Close CONSTRUCTION ON HOLD Arlesey Station Arlesey Arlesey 1 Interchange Facilities Q1,2,3 Wed 01/07/20 Fri 30/10/20 FUNDING 497 S106 S106 PROGRAMME Wed 01/04/20 Wed 31/03/21

498 S106 Taylors & Astwick Roads, Stotfold Astwick Road Stotfold Stotfold & Langford 1 Junction improvements - Astwick Q2 Fri 07/08/20 Wed 30/09/20 Road j/w The Green and Taylors Road j/w Astwick Road 499 S106 Taylors & Astwick Roads, CONSTRUCTION Astwick Road Stotfold Stotfold & Langford 1 Junction improvements - Astwick Road Q2 Fri 07/08/20 Wed 30/09/20 Stotfold j/w The Green and Taylors Road j/w 500 S106 Orchard Close j/w Hitchmead Rd, Orchard Close Biggleswade Biggleswade North 1 JunctionAstwick Road improvements incl. new Q2 Mon 24/08/20 Fri 11/09/20 Biggleswade Biggleswade South crossing and DYLs 501 S106 Orchard Close j/w Hitchmead Rd, CONSTRUCTION Orchard Close Biggleswade Biggleswade North 1 Junction improvements incl. new Q2 Mon 24/08/20 Fri 11/09/20 Biggleswade Biggleswade South crossing and DYLs 502 S106 Potton Road Crossing ON HOLD Potton Road Biggleswade Biggleswade North 1 Toucan crossing Q1,3,4 Mon 06/04/20 Fri 11/12/20

503 S106 Potton Road Crossing DETAILED DESIGN ON HOLD Potton Road Biggleswade Biggleswade North 1 Toucan crossing Q1 Mon 06/04/20 Fri 26/06/20

504 S106 Potton Road Crossing CONSTRUCTION ON HOLD Potton Road Biggleswade Biggleswade North 1 Toucan crossing Q3,4 Mon 05/10/20 Fri 11/12/20

505 S106 Dunstable Road, Caddington Dunstable Road Dunstable Caddington 3 Footway widening Q2,4 Mon 10/08/20 Wed 31/03/21

506 S106 Dunstable Road, Caddington DETAILED DESIGN Dunstable Road Caddington Caddington 3 Footway widening Q2,3 Mon 10/08/20 Fri 30/10/20

507 S106 Dunstable Road, Caddington CONSTRUCTION Dunstable Road Caddington Caddington 3 Footway widening Q4 Mon 08/02/21 Wed 31/03/21

508 S106 Crab Lane jw Lawrence Road Crab Lane Biggleswade Biggleswade North 1 Shared use footpath and signage, Q1,2 Mon 15/06/20 Fri 21/08/20 and uncontrolled crossing. 513 S106 Stanford Lane, Clifton New Road Clifton Arlesey 1 New shared use footway, crossing Q2,3 Mon 20/07/20 Fri 05/02/21 and traffic calming measures. 514 S106 Stanford Lane, Clifton DETAILED DESIGN New Road Clifton Arlesey 1 New shared use footway, crossing and Q2,3 Mon 20/07/20 Fri 09/10/20 traffic calming measures. 515 S106 Stanford Lane, Clifton CONSTRUCTION New Road Clifton Arlesey 1 New shared use footway, crossing and Q4 Mon 04/01/21 Fri 05/02/21 traffic calming measures. 516 S106 Millbrook Station Cycle Hangar Station Road Marston Moretaine Cranfield & Marston 2 New cycle hangar Q2 Mon 27/07/20 Fri 07/08/20 Moretaine 517 S106 Millbrook Station Cycle Hangar CONSTRUCTION Station Road Marston Moretaine Cranfield & Marston 2 New cycle hangar Q2 Mon 27/07/20 Fri 07/08/20 Moretaine 518 S106 Drakes Avenue Lighting Columns Drakes Avenue Leighton Buzzard Leighton Buzzard 2 Installation of lighting columns Q1,3 Mon 29/06/20 Fri 21/08/20 North 519 S106 Drakes Avenue Lighting Columns CONSTRUCTION Drakes Avenue Leighton Buzzard Leighton Buzzard North 2 Installation of lighting columns Q1,3 Mon 29/06/20 Fri 21/08/20

520 S106 Grovebury Road Vehicle Grovebury Road Leighton Buzzard Leighton Buzzard 2 Footway and vehicle crossover Q3,4 Mon 14/09/20 Fri 13/11/20 Accesses South improvements

521 S106 Grovebury Road Vehicle CONSTRUCTION Grovebury Road Leighton Buzzard Leighton Buzzard 2 Footway and vehicle crossover Q3,4 Mon 14/09/20 Fri 13/11/20 Accesses South improvements

522 S106 High Street Crossing, High Street Biggleswade Biggleswade North 1 Footway improvements, buildouts Q2,3 Mon 03/08/20 Fri 02/10/20 Biggleswade Biggleswade South and zebra crossing 523 S106 High Street Crossing, CONSTRUCTION High Street Biggleswade Biggleswade North 1 Footway improvements, buildouts and Q2,3 Mon 03/08/20 Fri 02/10/20 Biggleswade Biggleswade South zebra crossing 524 S106 French's Avenue, Dunstable Frenchs Avenue Dunstable Dunstable Northfields 3 Improvements to cycle and Q1 Mon 27/04/20 Fri 19/06/20 pedestrain routes and poublic 525 S106 French's Avenue, Dunstable CONSTRUCTION Frenchs Avenue Dunstable Dunstable Northfields 3 Improvementstransport including: to cycle buildout and pedestrain at Q1 Mon 27/04/20 Fri 19/06/20 routes and poublic transport including: 526 S106 Vimy Road, Linslade Vimy Road Leighton Buzzard Linslade 2 Solarbuildout floor-level at southern lighting footway, and pedestrian Q1,2 Mon 08/06/20 Fri 10/07/20 post&rail fencing along river footpath 527 S106 Vimy Road, Linslade CONSTRUCTION ON HOLD Vimy Road Leighton Buzzard Linslade 2 Solar floor-level lighting and post&rail Q1,2 Mon 08/06/20 Fri 10/07/20 fencing along river footpath 528 S106 Land off Swaffield Close, Ampthill Woburn Road Ampthill Ampthill 2 Shared-use footpath along verge of Q2,3,4 Mon 22/06/20 Fri 12/02/21 Woburn Road 529 S106 Land off Swaffield Close, Ampthill DETAILED DESIGN Woburn Road Ampthill Ampthill 2 Shared-use footpath along verge of Q2 Mon 22/06/20 Fri 11/09/20 Woburn Road 530 S106 Land off Swaffield Close, Ampthill CONSTRUCTION Woburn Road Ampthill Ampthill 2 Shared-use footpath along verge of Q4 Mon 25/01/21 Fri 12/02/21 Woburn Road 531 S106 Red Lion Close, Cranfield Red Lion Close Cranfield Cranfield & Marston 2 Buildout, bollards and road markings Q2 Mon 14/09/20 Fri 16/10/20 Moretaine 532 S106 Red Lion Close, Cranfield CONSTRUCTION Red Lion Close Cranfield Cranfield & Marston Buildout, bollards and road markings Q2 Mon 14/09/20 Fri 16/10/20 Moretaine 533 S106 Church Lane Church Lane Arlesey Arlesey 1 Crossing Installation Q2 Wed 01/07/20 Wed 30/09/20

534 S106 Church Lane CONSTRUCTION Church Lane Arlesey Arlesey 1 Crossing Installation Q2 Wed 01/07/20 Wed 30/09/20

535 S106 Windmill Road Phase 3 Windmill Road Flitwick Flitwick 1 Footpath 15 culvert and approaches Q2 Wed 01/07/20 Wed 30/09/20

536 S106 Windmill Road Phase 3 CONSTRUCTION Windmill Road Flitwick Flitwick 1 Footpath 15 culvert and approaches Q2 Wed 01/07/20 Wed 30/09/20

537 INTEGRATED High Street CONSTRUCTION High Street Langford Stotfold & Langford 1 Bus Stop Improvements RJ Q1,2 Wed 01/04/20 Wed 30/09/20 TRANSPORT 538 MAJORS MAJORS PROGRAMME Wed 01/04/20 Wed 31/03/21

539 MAJORS MAJOR ROAD SCHEMES Steve Lakin to submit data Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

540 MAJORS A421 Dualling M1 J13 to Milton CONSTRUCTION C/ OVER A 421 Aspley Guise 2 The existing A421 is to be upgraded to a Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 Keynes -Construction to continue SCHEME dual 2-lane carriageway from M1 541 MAJORS M1-A6-J11ainto next year. to To Sundon be completed Park Rd M1-A6 Chalton, Sundon 3 Junction 13 to Milton Keynes Magna Q1,2,3,4 Wed 01/04/20 Wed 31/03/21

542 MAJORS M1-A6-J11a to Sundon Park DESIGN C/ OVER M1-A6 Chalton, Sundon, 3 New bypass. Bid submitted to Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 Rd -Design to continue into SCHEME Sundon, Streatley DfT/LEP.TO issued in 2018/19 543 MAJORS M1-A6next year. Link To Rd be Scheme completed by C/ OVER M1-A6 Chalton, Sundon 3 Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 Development SCHEME 544 MAJORS M1-A6 Link Rd Transport C/ OVER M1-A6 Chalton, Sundon 3 Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 Planning SCHEME 545 MAJORS A 507 Junction capacity OUTLINE DESIGN A507 Various Junction capacity assessments Q1,2,3,4 Wed 01/04/20 Wed 31/03/21 assessments 546 MAJORS Dunstable High Street( Ph2 a to CONSTRUCTION Dunstable 3 Q2 Wed 01/07/20 Fri 29/10/21 e) 547 MAJORS Dunstable High Street( Ph2 a) CONSTRUCTION High Street South Dunstable Dunstable Watling 3 Construction for the DUNSTABLE HIGH External Q2,3 Wed 01/07/20 Fri 29/10/21 Dunstable Central STREET SOUTH PHASE 2A Bus stand 548 MAJORS Dunstable High Street( Ph2 b) CONSTRUCTION Queensway Dunstable Dunstable Icknield 3 Queenswayarea. & Northern Gateway External Q2,3 Wed 01/07/20 Fri 29/10/21

549 MAJORS Dunstable High Street( Ph2 c) CONSTRUCTION Dog Kennel Path Houghton Regis Houghton Hall 3 Dog Kennel Path External Q2,3 Wed 01/07/20 Fri 29/10/21

550 MAJORS Dunstable High Street( Ph2 d) CONSTRUCTION Court Drive Dunstable Dunstable Icknield 3 Court Drive External Q2,3 Wed 01/07/20 Fri 29/10/21

551 MAJORS Dunstable High Street( Ph2 e) CONSTRUCTION Dukeminster Road Dunstable Dunstable Icknield 3 Luton & Dunstable Busway Lighting External Q2,3 Wed 01/07/20 Fri 29/10/21

552 THIRD PARTY SCHEMES Wed 01/04/20 Wed 31/03/21

553 S38/278 Wed 01/04/20 Wed 31/03/21