Expansion of Industrial building project FORM-I Village- Mohammadpur Pace 2 Sector-36 ,

FORM- I

S. No. Item Details 1. Name of the project/s Expansion of Industrial Building Project 2. S. No. in the schedule 8 (a) 3. Proposed Plot Area = 39188.96 m2 capacity/area/length/tonnage to be Existing FAR = 19057.11 m2 handled/command area/lease Proposed FAR = 10432.18 m2 area/number of wells to be drilled Demolish FAR = 638.150 m2 Total FAR = 28851.14 m2

Existing BUA = 19224.27 m2 Proposed BUA = 11240.71 m2 Demolish BUA = 638.150 m2 Total BUA = 29826.83 m2 4. New/Expansion/Modernization Expansion 5. Existing Capacity/Area etc. Nil 6. Category of Project i.e. ‘A’ or ‘B’ Category B 7. Does it attract the general condition? No If yes, please specify. 8. Does it attract the specific No condition? If yes, please specify. 9. Location CLU is attached as Annexure II. Plot/Survey/Khasra No.

Village Mohammadpur Jharsa Tehsil Gurgaon Gurgaon State Haryana 10. Nearest railway station/airport along Nearest Railway Station: Garhi Harsaru with distance in kms. Railway Station (Approx. 6.09km, WNW) Nearest Airport: IGI Airport (Approx. 19.49 km, NNE) (Source of information:- Google Image) 11. Nearest Town, city, District Nearest City: Gurgaon Headquarters along with distance in District Headquarters: Gurgaon kms. 12. Village Panchayats, Zilla Parishad, Municipal Corporation Gurgaon, Municipal Corporation, Local body C-1 Info City Sector 34, Gurgaon

M/ s Honeywell International () Pvt. Ltd. 1

Expansion of Industrial building project FORM-I Village- Mohammadpur Jharsa Pace city 2 Sector-36 Gurgaon, Haryana

(complete postal addresses with Phone No. : 18001801817 telephone nos. to be given) e-mail : [email protected] 13. Name of applicant Honeywell International (India ) Pvt. Ltd. 14. Registered Address 17, Ground Floor, Amrit House, Sant Nagar, New -110065 15. Address for correspondence : Name ______Designation (Owner/Partner/CEO) Honeywell International (India) Pvt. Ltd. Address Village- Mohammadpur Jharsa Pace city 2 Sector-36 Telephone No. Gurgaon, Haryana E-mail honeywell.com/sites/acs-India/Pages/contact- us.aspx 16. Details of Alternative Sites No examined, if any. Location of these sites should be shown on a toposheet. 17. Interlinked Projects No 18. Whether separate application of No interlinked project has been submitted? 19. If yes, date of submission Not Applicable 20. If no, reason Not Applicable 21. Whether the proposal involves No approval/ clearance under: if yes, details of the same and their status to be given. (a)The forest (Conservation) act, Applicable. 1980? N.A.

(b) The wildlife (Protection) act, N.A. 1972? (C) The C.R.Z Notification, 1991? 22. Whether there is any Government 1. NBC Guidelines 2005 Order/Policy relevant/relating to the 2. Haryana Bye laws 2010 site? 23. Forest land involved (hectares) No 24. Whether there is any litigation No pending against the project and /or

M/ s Honeywell International (India) Pvt. Ltd. 2

Expansion of Industrial building project FORM-I Village- Mohammadpur Jharsa Pace city 2 Sector-36 Gurgaon, Haryana

land in which the project is propose to be set up? (a) Name of the Court (b) Case No. (c) Orders/directions of the Court, if any and its relevance with the proposed project.

(II) Activity

1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)

Details thereof (with approximate S. No. Information/Checklist confirmation Yes/No quantities /rates, wherever possible) with source of information data 1.1 Permanent or temporary change in land Yes The Industrial project will be developed use, land cover or topography including as per the CLU memo no. 0-1170-10DP- increase in intensity of land use (with 98/7867 dated: 02/06/1998. respect to local land use plan) 1.2 Clearance of existing land, vegetation No The construction of industrial project and buildings? does not require any clearance of existing land, vegetation & building as this is an expansion project of the already operational Industrial project (CTO Accorded.). 1.3 Creation of new land uses? Yes The Industrial project will be developed per the CLU memo no. 0-1170-10DP- 98/7867 dated: 02/06/1998. Hence, there is creation of land uses. 1.4 Pre-construction investigations e.g. bore Yes Soil & water testing is carried out in the houses, soil testing? vicinity of project site during the pre- construction phase of the project development of the expansion part of the project. 1.5 Construction works? Yes All construction activities will be confined within the project premises; there will be no physical changes outside the project boundary. 1.6 Demolition works? Yes The project is an expansion project which includes the demolition of the existing Porte cabin of area 638.15 m2. 1.7 Temporary sites used for construction No All the construction activity including

M/ s Honeywell International (India) Pvt. Ltd. 3

Expansion of Industrial building project FORM-I Village- Mohammadpur Jharsa Pace city 2 Sector-36 Gurgaon, Haryana

works or housing of construction stocking of raw materials will be confined workers? within the project site only. Temporary labour hutments are proposed. Local labourers from nearby area will be hired. Sanitation facilities will be developed at site in addition to the already existed sanitation at the site. As there is already operational existing part at the project site. 1.8 Above ground buildings, structures or Yes Excavation will be carried out for earthworks including linear structures, foundation of buildings and basements. cut and fill or excavations The total excavated quantity of earth material will be approx. 44,740.245 m3. The excavated soil will be used in backfilling and other landscape development. 1.9 Underground works including mining or No Open excavation would be done for tunneling? laying sewerage system, storm water drainage and water supply system etc. There would not be any mining or tunneling. 1.10 Reclamation works? No No reclamation work required. 1.11 Dredging? No No dredging required. 1.12 Offshore structures? No No offshore structures required. 1.13 Production and manufacturing yes Manufacturing process is involved in the processes? Industrial project which includes the raw material as polymers, fibers etc. 1.14 Facilities for storage of goods or Yes Raw material will be stored at site in a materials? covered area. Cement will be separately stored under cover in bales. Sand will be stacked neatly under tarpaulin cover. Bricks and steel will be laid in open. 1.15 Facilities for treatment or disposal of Yes Solid Waste: solid waste or liquid effluents? The solid waste generated from the project will be in the form of:

Construction Waste: Left over cement and mortars, cement concrete blocks, aggregate, sand and other inorganic material will be recycled and reused as granular subbase (GSB) layer of pavement. Earth rendered surplus from the excavation will be utilized in the embankment works.

M/ s Honeywell International (India) Pvt. Ltd. 4

Expansion of Industrial building project FORM-I Village- Mohammadpur Jharsa Pace city 2 Sector-36 Gurgaon, Haryana

Operational Phase: The solid waste generated from project will be mainly mixed in nature and the quantity of the waste will be 336 kg/day. The treatment of the solid waste generated from the Industrial project will be done at the project level for ex: hazardous and non hazardous waste will be handled by government approved vendor according to the Municipal Solid Wastes (Management and Handling) Rules, 2000 and Hazardous Waste used will be disposed through Hazardous Waste Management & Handling Rules, 2008.

Liquid effluents: During construction phase of the expansion part, sewage will be treated and disposed through nearby construction sites. The waste water in operation phase is being treated up to tertiary level in a STP of 100 KLD capacity and the treated sewage is being reused for toilet flushing and horticulture. Same will be done for the expansion part as well. Surplus treated water will be sent to public sewer. Dewatered/dried sludge generated from the STP plant will be used as manure for green belt development. ETP of 5 KLD is already being used for treating wastewater from Labs. 1.16 Facilities for long term housing of No Local labourers will be hired from nearby operational workers? areas during construction phase. So, there will be no need to create permanent facilities for long-term housing of operational workers. 1.17 New road, rail or sea traffic during No The site has good connectivity to Delhi construction or operation? Jaipur Express way (NH-8) and village road to nearby areas. Only internal roads, paths will be developed for vehicular movements for transportation of construction material during construction

M/ s Honeywell International (India) Pvt. Ltd. 5

Expansion of Industrial building project FORM-I Village- Mohammadpur Jharsa Pace city 2 Sector-36 Gurgaon, Haryana

phase whereas internal tracks and paths will be developed for traffic circulation (to avoid any congestion) during operational phase. 1.18 New road, rail, air waterborne or other No The site is well connected through the transport infrastructure including new or road network. The nearest roads are Delhi altered routes and stations, ports, airports Jaipur Express way (NH-8) and Khandsa etc? village road to nearby areas. 1.19 Closure or diversion of existing No Since the site is very close to major transport routes or infrastructure leading expressway and state highway, there will to changes in traffic movements? be no need for diversion or closure of existing traffic routes. 1.20 New or diverted transmission lines or No There will not be any new/diverted pipelines? transmission lines or pipelines around the proposed project. 1.21 Impoundment, damming, culverting, No No impoundment, damming, culverting, realignment or other changes to the realignment or other changes to the hydrology of watercourses or aquifers? hydrology of surface watercourses is proposed. 1.22 Stream crossings? No There are no streams running across the site. 1.23 Abstraction or transfers of water form Yes During construction phase, approx. 60 ground or surface waters? ML (approx.) amount of water will be required which will be provided by recycled water from STP. During operation phase, source of water ground water. About 73 KLD of fresh water will be required during operation phase of the project. 1.24 Changes in water bodies or the land Yes Runoff will increase due to increased surface affecting drainage or run-off? paved surface. However, increased runoff will be managed by well-designed rainwater harvesting system and storm water management plan. Storm water runoff is proposed to be drained off in the master storm water drains to be laid down by HUDA. Surface flow will also be used for recharging ground water. 1.25 Transport of personnel or materials for Yes During the construction phase, the trucks construction, operation or with PUC will be permitted to go within decommissioning? the site. The parking areas are planned according to the requirements includes parking for vehicles, and other public utilities. Thus, overall, 289 ECS is

M/ s Honeywell International (India) Pvt. Ltd. 6

Expansion of Industrial building project FORM-I Village- Mohammadpur Jharsa Pace city 2 Sector-36 Gurgaon, Haryana

reserved for parking in the project site for both existing (CTO accorded) and expansion of the project. 1.26 Long-term dismantling or No No Long term dismantling or decommissioning or restoration works? decommissioning or restoration works will be involved. 1.27 Ongoing activity during Yes There will be negligible disturbance from decommissioning which could have an the demolition of the Porte cabin, waste impact on the environment? of which will be reused within the project site during the construction phase 1.28 Influx of people to an area in either Yes Local labourers from nearby area will be temporarily or permanently? employed during the construction phase. In the operation phase, the project being an Industrial Building will see influx of people but only temporarily. 1.29 Introduction of alien species? No The landscaping will be carried out with mainly local species with a few ornamental varieties of flora that are well suited to the local conditions like Champa, silver palm, khajur etc. 1.30 Loss of native species or genetic No There will be no significant impact on the diversity? native species or genetic diversity. 1.31 Any other actions? No Not Applicable.

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):

Details thereof (with approximate S. Information/checklist confirmation Yes/No quantities/rates, wherever possible) No. with source of information data 2.1 Land especially undeveloped or No Land has been allotted for the Industrial agricultural land (ha) project as per the CLU memo no. 0-1170- 10DP-98/7867 dated: 02/06/1998. 2.2 Water (expected source & competing Yes During construction phase 60 ML amount users) unit: KLD of water will be required which will be provided by recycled water from Private water Tanker. During operation phase, source of water will be HUDA. About 73 KLD of fresh water will be required during operation phase of the project. 2.3 Minerals (MT) Yes Minerals such as sand and aggregates will

M/ s Honeywell International (India) Pvt. Ltd. 7

Expansion of Industrial building project FORM-I Village- Mohammadpur Jharsa Pace city 2 Sector-36 Gurgaon, Haryana

be required during the construction phase. 2.4 Construction material – stone, aggregates, Yes All materials for construction will be and / soil (expected source – MT) arranged through select suppliers.

2.5 Forests and timber (source – MT) Yes All material from forests and timber will be provided by selected suppliers. However steel frames etc. shall be used to minimize the use of timber. 2.6 Energy including electricity and fuels Yes The power supplied by DHBVN. The (source, competing users) Unit: fuel (MT), maximum load for the complete energy (MW) (Existing (CTO accorded) + Expansion) Industrial project will be approx. 5411 kVA. There are 3 no. of DG sets of total 1250 kVA capacity for 70 % power back up in the project. 2.7 Any other natural resources (use No Not Applicable appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health.

Details thereof (with approximate S. No. Information/Checklist confirmation Yes/No quantities/rates, wherever possible) with source of information data 3.1 Use of substances or materials, which are Yes Diesel for DG sets is being stored in hazardous (as per MSIHC rules) to drums at the earmarked locations. It shall human health or the environment (flora, also be handled as per The Manufacture, fauna, and water supplies) Storage and Import of Hazardous Chemical Rules, 1989 and Material Safety Data Sheet. The E – waste, hazardous as well as the non hazardous waste is handled by government approved vendor. 3.2 Changes in occurrence of disease or No Suitable drainage and waste management affect disease vectors (e.g. insect or measures (with frequent spray of water borne diseases) insecticides etc.) will be adopted in both the construction and operational phase such that there will be no stagnation of water or accumulation of waste. This will effectively restrict the reproduction and growth of disease vectors. 3.3 Affect the welfare of people e.g. by Yes Socio-economic standard of people will

M/ s Honeywell International (India) Pvt. Ltd. 8

Expansion of Industrial building project FORM-I Village- Mohammadpur Jharsa Pace city 2 Sector-36 Gurgaon, Haryana

changing living conditions? improve due to increased employment opportunities provided by this project. This will lead to better quality of life and will also set a standard for future developments in the area. 3.4 Vulnerable groups of people who could No Impacts of this type are not expected. be affected by the project e.g. hospital patients, children, the elderly etc. 3.5 Any other causes No Not Applicable

4. Production of solid wastes during construction or operation or decommissioning (MT/month)

Details thereof (with approximate S. No. Information/Checklist confirmation Yes/No quantities/rates, wherever possible) with source of information data 4.1 Spoil, overburden or mine wastes No No such spoil, overburden or mine wastes will be generated. 4.2 Municipal waste (domestic and or Yes The total municipal (domestic) solid commercial wastes) waste to be generated is approx. 336 kg/day for both existing (CTO accorded) and expansion of the project. 4.3 Hazardous wastes (as per Hazardous Yes The hazardous wastes along with other Waste Management Rules) wastes in the project is using oil from DG sets, which is classified as per The Hazardous Waste Category 5.1 as per The Hazardous Wastes (Management & Handling) Rules, 1989. Used oil from DG sets will be stored in HDPE drums in isolated covered facility. This used oil will be sold to authorized recyclers. Suitable care will be taken so that spills/leaks of used oil from storage are avoided. 4.4 Other industrial process wastes Yes Other Hazardous Waste used will be disposed through Hazardous Waste Management & Handling Rules, 2008. 4.5 Surplus product Yes Computer hardware. 4.6 Sewage sludge or other sludge from Yes Approx. 4.92 Kg/day of sludge generated effluent treatment from the STP plant (CTO accorded) is dried and later used as manure for green belt development & 3.29 kg/day of the sludge would be generated for expansion

M/ s Honeywell International (India) Pvt. Ltd. 9

Expansion of Industrial building project FORM-I Village- Mohammadpur Jharsa Pace city 2 Sector-36 Gurgaon, Haryana

part of the project, which will be handled in the same manner. Sewage is treated in 100 KLD STP plant & effluent is treated in ETP of 5 KLD, for odor control plantation is proposed. 4.7 Construction or demolition wastes Yes The construction waste of the expansion part of the industrial project will consist of excess earth and construction debris along with cement bags, steel in bits and pieces, insulating and packaging materials etc. Recyclable waste construction materials will be sold to recyclers. Unusable and excess construction debris will be disposed at designated places in tune with the local norms. Demolition waste will be reused within the project site during the construction phase. 4.8 Redundant machinery or equipment No Redundant machinery will not be generated. 4.9 Contaminated soils or other materials No Contaminated soils or other materials will not be generated. 4.10 Agricultural wastes Yes Landscape wastes of 0.59 kg/day are being generated. 4.11 Other solid wastes Yes E waste is generated and is handled from the government approved vendor.

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr).

Details thereof (with approximate S. No. Information/Checklist confirmation Yes/No quantities/rates, wherever possible) with source of information data 5.1 Emissions from combustion of fossil Yes The project does not envisage any major fuels from stationary or mobile sources air pollution sources except operation of DG sets during power failure and vehicular traffic. 5.2 Emissions from production processes No Production processes does not produce such emissions. 5.3 Emissions from materials handling Yes Small quantities of fugitive emissions are including storage or transport envisaged during transport and handling of construction materials. Such emissions will be temporary and controlled by the

M/ s Honeywell International (India) Pvt. Ltd. 10

Expansion of Industrial building project FORM-I Village- Mohammadpur Jharsa Pace city 2 Sector-36 Gurgaon, Haryana

use of sprinkling and other viable techniques like covering of loose material. 5.4 Emissions from construction activities Yes This will be restricted to the construction including plant and equipment phase and the construction site only. 5.5 Dust or odours from handling of Yes Dust is anticipated during loading and materials including construction unloading of construction material and materials, sewage and waste excavation of upper earth surface. These will however be temporary in nature, which will be controlled by providing water sprinklers. Tarpaulin cover will be provided on stored loose materials to reduce the dust emission. 5.6 Emissions from incineration of waste No No incineration of wastes is proposed. 5.7 Emissions from burning of waste in open No Open burning of biomass/other material air (e.g. slash materials, construction will be prohibited on site. debris) 5.8 Emissions from any other sources No Not Applicable 6. Generation of Noise and Vibration, and Emissions of Light and Heat: Details thereof (with approximate S. No. Information/Checklist confirmation Yes/No quantities/ rates, wherever possible) with source of information data 6.1 From operation of equipment e.g. Yes Source of noise in the operational phase of engines, ventilation plant, crushers the expansion part will be from backup DG sets, pumps & motors and other machinery used in the Industry (which are already in operation for the existing plant (CTO accorded), the DG sets are provided with acoustic enclosure to have minimum 75 dB (A) insertion loss or for meeting the ambient noise standard whichever is on higher side as per E (P) Act, GSR 371 (E) and its amendments). All the machinery to be employed in the expansion part of the exiting Industrial project will be of highest standard and of reputed company compiling with standard. Therefore, no significant impact due to operation of machinery is anticipated. 6.2 From industrial or similar processes Yes Industrial processes is carried out in the project for which CTO for collection, reception, treatment , storage, transportation and disposal of hazardous

M/ s Honeywell International (India) Pvt. Ltd. 11

Expansion of Industrial building project FORM-I Village- Mohammadpur Jharsa Pace city 2 Sector-36 Gurgaon, Haryana

waste has been authorized from Haryana Pollution Control Board 01/04/2014 to 31/03/2016 vide letter no. HSPCB/Consent/:277841GUSOCTOHW M494485 dated: 16/03/2014. 6.3 From construction or demolition Yes Due to various construction activities, there will be short-term noise impacts in the immediate vicinity of the project site. The construction & Demolition activities will include the following noise generating activities:  Concreting, mixing & operation of DG sets.  Construction plant and heavy vehicle movement.  Demolition creates noise but it will be of temporary and hence would not be adverse in nature. 6.4 From blasting or piling No No blasting or mechanized piling will be done. 6.5 From construction or operational Yes Noise is generated from the vehicular traffic movement during the operational phase of the existing part of the industrial project (CTO accorded) which is mitigated by green belt. Some noise will be generated from vehicular movement in the construction and operational phase of the expansion part but that will be mitigated in the same manner as above. 6.6 From lighting or cooling systems No No significant noise impact will result from lighting or cooling systems. 6.7 From any other sources No Not Applicable

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:

Details thereof (with approximate S. No. Information/Checklist confirmation Yes/No quantities/rates, wherever possible) with source of information data 7.1 From handling, storage, use or spillage of No The used oil from DG sets will be hazardous materials carefully stored in HDPE drums at isolated storage, and periodically sold to authorized recyclers. All precautions will be taken to avoid spillage from

M/ s Honeywell International (India) Pvt. Ltd. 12

Expansion of Industrial building project FORM-I Village- Mohammadpur Jharsa Pace city 2 Sector-36 Gurgaon, Haryana

storage as per The Hazardous Wastes (Management & Handling) Rules, 1989. 7.2 From discharge of sewage or other No There will be no discharge of untreated effluents to water or the land (expected sewage on land or into water bodies mode and place of Discharge) from the existing (CTO accorded) as well as expansion part of the industrial project. Adequate treatment of sewage is being carried out in a STP of capacity 100 KLD & ETP of capacity 5 KLD, present within the project premises. Treated sewage will be re-used for flushing and landscaping. External facility will be provided to discharge the excess treated water as per The Water (Prevention and Control of Pollution) Act, 1974. 7.3 By deposition of pollutants emitted to air No The DG sets are provided in the existing into the land or into water Industrial project with stacks of adequate height and these will be employed for the expansion part as well. Hence dispersion is achieved and deposition of pollutants in significant concentrations at any single location is avoided. 7.4 From any other sources No Not Applicable 7.5 Is there a risk of long term build up of No Not Applicable pollutants in the environment from these sources?

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment

Details thereof (with approximate S. No. Information/Checklist confirmation Yes/No quantities/rates, wherever possible) with source of information data

8.1 From explosions, spillages, fires, etc. Yes To deal with any fire related accident, from storage, handling, use or production fire fighting facility of single handed of hazardous substances hydrant valve, long hose reel, and portable fire extinguisher will be provided at strategic location for the expansion part similar to existing part of the Industrial project (CTO accorded). 8.2 From any other causes No Not Applicable

M/ s Honeywell International (India) Pvt. Ltd. 13

Expansion of Industrial building project FORM-I Village- Mohammadpur Jharsa Pace city 2 Sector-36 Gurgaon, Haryana

8.3 Could the project be affected by natural Yes The project falls under seismic active disasters causing environmental damage Zone IV indicating high damage risk (e.g. floods, earthquakes, landslides, zone. The expansion of the industrial cloudburst etc.) buildings will be designed as earthquake resistant and comply with the required IS specifications.

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality

Details thereof (with approximate S. No. Information/Checklist confirmation Yes/No quantities/rates, wherever possible) with source of information data 9.1 Lead to development of supporting. utilities, ancillary development or Yes Appropriate infrastructure like roads, development power supply, waste management and stimulated by the project which could waste water treatment will be have impact on the environment e.g.: developed for the expansion part of the • Supporting infrastructure (roads, power project within the project site. supply, waste or waste water treatment, Development of the area will be as per etc.) the CLU memo no. 0-1170-10DP- 98/7867 dated: 02/06/1998.

• Housing development No Not Applicable • Extractive industries No Not Applicable • Supply industries No Not Applicable • Other Yes Industrial Building 9.2 Lead to after-use of the site, which could No Not Anticipated have an impact on the environment 9.3 Set a precedent for later developments Yes The project is already a world class process providing employment opportunities and molding the modern lifestyle and same will be ensured for the expansion part of the project. 9.4 Have cumulative effects due to proximity No Not Applicable to other existing or planned projects with similar effects

(III) Environmental Sensitivity

M/ s Honeywell International (India) Pvt. Ltd. 14

Expansion of Industrial building project FORM-I Village- Mohammadpur Jharsa Pace city 2 Sector-36 Gurgaon, Haryana

Name/ Aerial distance (within 15 km) Areas Identity project location boundary S. No. 1 Areas protected under international Sultanpur national Approx. 10.02 Km in WNW conventions, national or local Park direction of the project site. legislation for their ecological, landscape, cultural or other related value 2 Areas which are important or Jheel Approx. 8.58 Km in NNW sensitive for ecological reasons - direction of the project site. Wetlands, watercourses or other water bodies, coastal zone, Sultanpur national Approx. 10.02 Km in WNW biospheres, mountains, forests. Park direction of the project site.

3 Areas used by protected, important Najafgarh Jheel Approx. 8.58 Km in NNW or sensitive species of flora or direction of the project site. fauna for breeding, nesting, Sultanpur national Approx. 10.02 Km in WNW foraging, resting, over wintering, Park direction of the project site. migration 4 Inland, coastal, marine or Ground water The depth of groundwater is 20- underground waters 23 meter below the ground level. (Source: CGWA) 5 State, National boundaries Delhi – Haryana 9.36 Km, NNW of the project state border site.

6 Routes or facilities used by the Gurgaon Railway 7.17 Km, NNE from the project station public for access to recreation or site

other tourist, pilgrim areas NH-8 (Delhi Jaipur 920 mt. ESE from the project

M/ s Honeywell International (India) Pvt. Ltd. 15

Expansion of Industrial building project FORM-I Village- Mohammadpur Jharsa Pace city 2 Sector-36 Gurgaon, Haryana

Road)

Khandsa Road 360 mt, SE from the project site. 7 Defense installations Air force station 7.55 km in the NE direction from the project site. 8 Densely populated or built-up area village 3.73 Km, N of the project site.

9 Areas occupied by sensitive man- Sharda 1.81 Km, WSW of the project made land uses (hospitals, International School site. schools, places of worship, community facilities) Krishna Mandir, 2.17 Km, NNE of the project site. Vidya medical 3.69 Km, N of the project site. centre

HUDA community 6.89 km, ENW from the project centre site 10 Areas containing important, high Ground Water The ground water level is 20-23 quality or scarce resources. meters bgl. (ground water resources, surface (Source: CGWA) resources, forestry, agriculture, fisheries, tourism, minerals) 11 Areas already subjected to pollution Ground Water - or environmental damage. (those where existing legal environmental standards are exceeded) 12 Areas susceptible to natural hazard Earthquakes The site falls under the zone IV which could cause the project to as per the Seismic Zone Map of present environmental problems India. Adequate measures will (earthquakes, subsidence, be taken during the construction

M/ s Honeywell International (India) Pvt. Ltd. 16

Expansion of Industrial building project FORM-I Village- Mohammadpur Jharsa Pace city 2 Sector-36 Gurgaon, Haryana

landslides, erosion, flooding or of the project. extreme or adverse climatic conditions)

(IV) Terms of Reference for EIA studies Not Applicable

M/ s Honeywell International (India) Pvt. Ltd. 17