Chapter-5

Engineering Department PROGRESS OF WORKS FOR GM ANNUAL NARRATIVE REPORT 2010-2011

S. P.B. Name of works Anticip Expend Remarks No. No. ated Iture Cost Upto Crore 31.3.11 Rs Crore Rs 1 2 3 4 5 6 P.H.-16- Traffic facilities works 1 Estimate sanctioned. Tender opened MD -PNU - Through on 19.10.10 & discharged on 15.12.10 50 trap repl. By 1 : 12 18.00 0 for Sr. DEN/W section. Tender turnout with dead end discharged for Sr. DEN/E section on 24.01.11.as work has been deferred. 2 Nal-Gajner : New block Work completed. Final bill of Engg. 42 station. 8.39 5.55 passed in Aug-10. Final bill of S&Tupto 31.03.12 3 44 Kanakpura goods 5.50 2.04 1. Flooring work of off side PF of line shed - development as No. 3 has been completed. and model goods terminal. handed over for loading and unloading goods. 2. Labour room - Completed. 3. Bore well completed. 4. RCC O/H tank bottom dome is in progress. 5. Flooring of PF

no 2 &3 is completed in 500 mtrs lengths out of 700 mtrs lengths. To complete this work during the finaancial year atleast Rs. 3.50 Crores is futher required. 4 47 Malakhera & Digawara 5.90 0 Previously it was decided to do the - Conversion of 2-line work doubling work but as the stations into 3-line with doubling work is not sanctioned it is standard- III decided work will be executed by the interlocking, Division. Estimate sanctioned on simuttaneous 05.08.10 & Track work Tender reception & despatch opened on 30.09.10 and work etc. awarded on 15.02.11 . Civil work tender opened on 10.12.10 and under finalization. S&T - Tender opened on 27.10.10 and work awarded on 27.12.10. 5 -Merta Road - Standard III interl- Work completed. 25 14.89 14.52 ocking with central To be dropped. panel (10 stations) 6 Merta road - Phulera Standard III interl- 26 19.14 13.89 Work completed. ocking with central panel (13 stations) 7 Jodhpur-Phulera - 36 Addl loop lines (4 6.00 0.78 Work completed. Stations) 8 Bhikamkor-Standard-III interlocking with 37 6.65 1.93 Work completed. central panel for new block station. 9 Keduli&Naya 43 Khardia-Addl Loop 4.14 0.54 Work completed. Lines. 10 Mandiya Kalan -New Plan received back with observation 46 7.67 0 Block station. from HQ, being resubmitted.

P.H.-29- Road Safety Works-LCs 11 AII Divn:- LC 50 has been manned. Work of rest N.W.RLY-Manning of LC's have been deffered vide HQ's 59 level 6.34 4.80 letter No. W.350/1/61 dated 03.11.08. crossings(51Nos.) Work completed. JU Divn:- Work completed.

2 12 63 N.W.R. - Manning of 42.00 38.00 AII Divn:- Only 6 LCs will be manned. unmanned level AII-COR -33, 66, 82 crossings (210 Nos.) COR-UDZ- 45, 59 & 61 - Basic requirement like duty bunk, Lifting Barrier at all LC's completed. - Work of quarters in progress. 6 post sanctioned against requirement of 14. - sanction of posts is awaited. Only 6 LCs will be manned. AII-COR -33, 66, 82 COR-UDZ- 45, 59 & 61 - Basic requirement like duty bunk, Lifting Barrier at all LC's completed. - Work of quarters in progress. 6 post sanctioned against requirement of 14. - sanction of posts is awaited. BKN Divn:- Scope reduced to 42 Nos. 6 nos. LCs manned. At remaining 36 LCs, work is in progress. JP Divn:- Details of LCs - JP-SWM & RNW-FL = 10 Nos, SIKAR-LHU & SIKR-CUR= 19 Nos and ADEN/RPC= 10 LCs Total =39 . Engg work :- For 19 Nos LC MG sec work to be dropped due to proposed GC. For 20 LCs lifting barrier (ADEN(RPC)JP , ADEN(Line) JP & FL and 10 LCs ADEN(Line) JP & FL duty bunk and road surface work awarded and in progress. For 10 LCs JP-SWM Sec. -Construction of Qtrs & hand pum work awarded on 03.11.10 and in progress. For 10 LCs RPC Sec. -Construction of Qtrs & hand pum tender dischaged and Re tender to be opened on 11.03.11. For 9 Nos LC in ADEN(RPC)JP Sec duty & improvement to road surface tender opend on 06.01.11 and under finalization . S&T Work :- 21 LC work awarded & material received. JU Divn:- LCs already manned = 17 Nos. Work held for the want of creation of post and manpower

3 13 65 MD -PNU Interlocking 2.77 1.69 Scope revised for interlocking of 20 of level crossing gates no.s of LC gates. LOA issued on ( 28 Nos. ) 27.09.10. Part material supplied. All 30 LC gates interlocked. 14 62 Division - 2.90 0.51 Engineering work awarded on Upgradation of level 05.04.10. Work at LC No. 164, 195 & crossings ( 7Nos) (LC 102 in progress. no. 102 RGS- SMPR, S&T- Work awarded on 30.04.10 & 102 NDH-COM "B' work in progress. (ESP & SIP awaited class to "A" ) LC no. for LC 195 & 102 ) TDC 30.06.11( 99 DKBJ-NDH 195 S&T Exp. 2354) (Engg. 2767) GIO-SKAR "C' class to "B-1" ) LC no. 44 NNL -APJ , 98 NDH-COM 164 BOTI-PLSN "C' class to "B-2" ) 15 58 JU Div-Manning of 2.68 1.06 Work completed. unmanned level To be dropped. crossing (21 Nos) 16 60 Jodhpur 2.96 1.00 a)Work completed at 25 LCs. Division-Upgradation b) One LC closed after opening of of manned level ROB. crossings (31nos.) c) Work of ROB/ Limited height sub way sanctioned on 03 LCs. d) Work in progress at 02 LCs.

P.H.-30- Road Over Bridge Works

17 71 Rewari- Jhajjar ROB in 36.75 9.63 Railway portion completed. lieu of LC No. 57-B at km 81/2-3 on Rewari- Delhi section. 18 72 Sirsa -Suchan Kotli 34.82 5.82 Work completed and commissioned in ROB in lieu of LC Dec. 2010 & LC closed. No.143atKm 223 /14-15 on Hissar-Bhatinda Section. 19 73 Abu Road ROB in lieu 15.14 3.72 Railway portion completed. of LC No. 134 - B at Km 601/7-8 on Marwar Jn. - Palanpur section. 20 74 Kishangarh ROB in 15.56 3.53 Rly. Bridge:- Substructure completed. lieu of LC No. 28 at 4 nos. girders out of 8 nos. casted. Km 266/8-9 on Phulera Approaches:- Approaches are almost Jn. - section complete, except end span.

4 21 75 Dausa ROB in lieu of 10.08 1.49 Rly. Bridge:- Substructure completed. LC No. 181 at Km. Super structure work held up for want 179/6-7 on Jaipur- of speed restriction. Dausa section Approaches:- Another party engaged by the State Govt. after first party failed. 22 76 Bhiwani ROB in lieu of 20.36 1.72 Piling and pile cap work is in L-C No. 53-C at Km progress. For 3rd piling work held up 82/13-14 on for want of block and shifting of home Bhiwani-Hissar section signal at Bhiwani yard. Approaches work in progress. 23 77 Mandal- Bhilwara ROB 13.38 3.35 Rly. Portion completed. in lieu of LC No 63-C Approaches work in progress. at Km 120/8-9 on Ajmer - Chittorgarh section. 24 78 Mahendragarh- Zerpur 24.42 7.33 Work completed and commissioned in Pali ROB in lieu of LC Sep. 2010 & LC closed. No 100 at Km133/11-12on Re- wari-Sadulpur sec. 25 79 Charkhi Dadri ROB in 25.52 6.86 ROB commissioned on 01.12.10. lieu of LC No 33 at Km 54/13-14 on Rewari-Hissar sec. 26 80 ROB in lieu 25.10 8.22 Railway portion completed. of LC No. 138 at Km 321/12-13 on Bikaner- Lalgarh section . 27 81 Bhiwani - Bhiwani city 21.65 0.20 GAD under prepration. Estimate of ROB in lieu of LC No Rly. portion prepared but part of 53-B at Km 46/5-6 on estimate from state govt. yet to be Bhiwani-Rohtak received. Work deferred by Govt. of section. Haryana for 2-3 years till completion of ROB in lieu of LC No 53C. 28 82 Daurai- Saradhna 16.06 3.03 Rly. Bridge :- Railway portion ROB in lieu of LC No completed. 5A at Km 306/8-9 on Approaches:- Approaches are almost Ajmer- MarwarJn. complete, except end span. Section. 29 83 Construction of ROB in 22.53 0.01 Test pile work in progress. lieu of LC No. 325 at Barmer 30 84 Kosli ROB in lieu of 25.48 4.19 Substructure work completed. Super LC No.19-C at Km structure work in progress. 28/1-2 on Rewari-Hissar sec.

5 31 85 ROB in lieu of 16.76 3.01 Railway portion completed. LC No. 63-C at Km Approaches work in progress. 578/1-2 on Bikaner-Merta Road section 32 86 Jn. ROB in 12.76 1.74 Substructure completed. CRS lieu of LC No. 36-C at approval for staging is awaited. Km 64/1-2 on Phulera - Approaches work in progress. Merta Road section . 33 87 Alwar ROB in lieu of 16.4 0.95 46 nos. piles and 4 nos. pile caps and LC No 111 at km 4 pier casted LC diversion is required 71/3-4 on Rewari- which is held up due to land acquisition Alwar section and court case. PHED pipe line to be diverted. 34 88 Construction of ROB in 18.92 0.04 GADapproved.Detailed esti-mate lieu of LC no 139 at sanctioned. Work will be started after Bikaner commission-ing of ROB at LC 138.

P.H.-31- Track Renewal Works

35 91 Mavli - Barisadri sec. 3.21 2.21 Work in Progress CTR(S) - 82.01 Km 36 92 Rai ka Bagh - 45.61 41.72 Work Completed Jaisalmer - CTR (P) - 44.92 km 37 93 Jaipur - Ajmer 4.77 0.68 Not required & deleted from Pink TRR(S) & TSR(P) - Book 11-12 14.00 Km 38 94 Hisar - Bhatinda - 84.56 84.55 Work Completed CTR - 41 km, TRR - 32.4 km & TSR - 10.7 km (P) 39 95 Phulera - Jodhpur - 3.06 1.52 Work Completed TSR - 10 km (P) 40 96 Merta Road - Jodhpur 2.78 1.17 Work Completed - TTR (25 Nos) 41 97 Phulera - Merta Road 4.13 1.70 Work Completed - TTR (40 Nos) 42 98 Madar - Palanpur - 2.66 1.66 Work in Progress TTR (43 Nos) & traps (40 Nos) 43 99 Madar - Palanpur - 2.84 2.81 Work Completed TBR - 40 km 44 100 Jaisalmer - Rai ka 10.21 10.18 Work Completed Bagh Palace - CTR - 10 km (P) (Osiyan - Dhelana)

6 45 101 Jaisalmer - Rai ka 181.63 179.84 Work Completed Bagh Palace - CTR - 186 km (P) (Marwar Mathanian - Jaisalmer) 46 102 Jaisalmer - Rai ka 26.68 20.11 Work Completed Bagh Palace - CTR (P) - 30 km (Rai ka Bagh Palace - Marwar Mathanian) 47 103 Jaisalmer - Rai ka 8.74 8.33 Work Completed Bagh Palace - CTR (P) -10 km (Jetha Chanda - Thaiyat Hamira) 48 104 Jaisalmer - Rai ka 11.28 11.05 Work Completed Bagh Palace - CTR (P) -10 km (Marwar Bithri - Ashapur Gomat) 49 105 Suratgarh - Anupgarh 7.30 7.30 Work in Progress - TSR - 17.4 km 50 106 Hissar - Bhatinda - 35.43 35.15 Work Completed CTR - 26.37 km, TRR - 0.23 km & TSR - 0.545 km 51 107 Bikaner - Bhatinda 6.94 6.93 Work Completed (Loop / Yard) - TSR - 25 km 52 108 Phulera - Jodhpur 3.92 1.99 Work Completed (Loop / Yard) - TSR - 12 km 53 109 Loharu - Sikar - CTR - 13.30 13.30 Work not required and deleted from 30 km Pink Book 11-12 54 110 Hanumangarh - 23.90 7.28 Work Completed Sadulpur - CTR - 37.32 km 55 111 Churu - Bikaner - 23.42 2.79 Work not required and deleted from CTR - 36.89 km Pink Book 11-12 56 112 Ratangarh - Bikaner - 16.02 4.85 Work completed and deleted from TRR - 48.33 km Pink Book 11-12 57 113 Marwar - Mavli Jn - 6.28 0.37 Work Completed TSR - 32.38 km

7 58 114 Bikaner - Bhatinda & 7.99 3.56 Work Completed Suratgarh - Anupgarh - TTR (52 & 48 Nos) 59 115 Phulera - Jodhpur & 5.78 3.06 Work in Progress Merta - Bikaner - TTR (1:12 - 31 Nos, 1:8.5 - 36 Nos) & trap switches (33 Nos) 60 116 Hissar - Bhatinda - 3.01 0.97 Work Completed TTR (1:12 - 13 Nos & 1:8.5 - 17 Nos) 61 117 Rewari-Madar-TTR 2.40 2.30 Work in Progress (1:16 -1 No, 1:12 - 2 Nos & 1:8.5 - 30 Nos), traps (15 Nos) & diamond crossings (2 Nos) 62 118 Jodhpur - Merta & 4.73 2.52 Work in Progress Bikaner - Merta - TBR - 57 km 63 119 Madar - Palanpur - 3.76 3.12 Work in Progress TBR - 73.79 km 64 120 Madar - Palanpur - 3.28 0.05 Work in Progress TFR - 80 km 65 121 Suratgarh - Bhatinda - 4.71 1.44 Work Completed CTR (P) - 3.27 km & TRR - 1.33 km 66 122 Bathinda (Bypass 9.54 7.04 Work Completed Line) & Hissar - Bathinda - CTR - 8.27 km (P) 67 123 Suratgarh - Kalyan Kot 22.23 16.85 Work Completed - TRR (S) - 28.83 km, Suratgarh By-pass - TRR - 0.7 km & Suratgarh (Yard / By-pass) - TSR (P) - 2.3 km 68 124 Sri Ganganagar Yard - 4.80 2.60 Work Completed CTR (P) - 1.56 km, TRR (S) & TSR (P) - 1.972 km 69 125 Rohtak - Bhiwani - 15.97 8.91 Work Completed TRR (P) - 24.3 km

8 70 126 Udaipur - 4.14 3.62 Work Completed Himmatnagar - CTR - 2.46 km & TSR - 10.57 km (S) 71 127 Udaipur - 8.33 7.57 Work Completed Himmatnagar - TRR - 24.82 km (S) 72 128 Sri Ganganagar - 14.08 5.42 Work Completed Hanumangarh - CTR - 20.97 km (S) 73 129 Ratangarh West - 10.34 10.34 Work completed and deleted from Sardar Shahar - CTR - Pink Book 11-12 15 km (S) 74 130 Bikaner - Bhatinda - 7.52 4.08 Work Completed TSR - 19 km (P) (13 stations) (24 loops) 75 131 Madar - Palanpur - 13.34 12.58 Work in Progress Through switches & CMS crossing renewal (212 Nos) 76 132 Merta Road - Merta 15.89 7.12 Work Completed City - CTR - 14.66 km (P) 77 133 Rai ka Bagh - 10.69 4.53 Work Completed Jaisalmer - TSR - 15.47 km (P) 78 134 Madar - Palanpur - 3.78 0.55 Work in Progress TFR - 80 km 79 135 Rewari-Jaipur-Ma-dar- 3.42 3.38 Work in Progress TFR - 74.2 km 80 136 Madar - Durai & 2.59 0.59 Work Completed Marwar - Jodhpur - TBR - 49.63 km 81 137 Merta - Phulera - TBR 1.79 0.80 Work in Progress - 29 km 82 138 Renewal of ordinary 88.09 5.80 Work not started curved switches and crossing with new 52 Kg (1:12 & 1:8.5) TWS and WCMSC on existing PSC layout - 416 SETS

9 83 139 CTR(TRR/S & TSR/P) 4.01 3.85 Work Completed 5.60 Km at BNSR, KYNT, SRPR, SBNR and RMSR & APH Loop lineson SOG-APH section 84 140 TRR(P) 33.65 Km 22.89 20.50 Work Completed (from Km 195 to 228.650 SOG - BKN section. 85 141 TRR(S) 34 Loop Lines 9.68 1.28 Work in Progress (25.30 Km) on Phulera – Jodh-pur BG section of Jodhpur Div. 86 142 TRR(S) of 49 Loop 16.72 5.65 Work in Progress Lines (35.581 Km) and Sleeper Renewal (P) of Loop Lines to increase the sleeper density from M+4 to M+7 on Madar - Palanpur section 87 143 Laying of 60 Kg (90 13.78 2.00 Work not started UTS) 1 in 12 TWS and WCMS crossings on 58 Nos. existing 1 in 12 fan shaped turn out sleepers on Rewari - Jaipur section 88 144 Rewari - Phulera - 10.59 0.01 Not required and deleted from Pink CTR - 20.045 km, Book 11-12 TRR - 24.09 km & TSR - 13.25 km (S) 89 145 Jaipur - Phulera - CTR 6.07 0.04 Not required and deleted from Pink - 28.45 km (S) Book 11-12 90 146 Marwar - Mavali - 2.80 1.60 Work completed CTR-113.55 km (S) 91 147 Udaipur - 7.06 3.33 Work completed Himmatnagar - CTR - 22.32 km (S) 92 148 Hissar - CTR - 9.78 29.86 29.67 Work completed km bye pass line & Rewari - Hissar - TRR - 3 km & TSR - 41.4 km (P)

10 93 149 Ratangarh - Bikaner & 15.18 0.61 Not required and deleted from Pink Ratangarh - Degana - Book 11-12 CTR - 0.75 km & 22.77 km (S) respectively 94 150 Suratgarh - Bhatinda - 15.23 14.80 Work completed Hissar - TRR - 25.73 km (S) (23 stations) (37 loop lines) 95 151 Rewari - Hissar - TRR 45.90 45.34 Work completed - 65 km (P) 96 152 Rewari - Hissar - 10.91 10.39 Work in Progress TRR(S) & TSR(P) - 15 km (12 stations) 97 153 Hissar - Bhatinda - 9.31 9.29 Work completed TSR - 16.4 km (P) 98 154 Hissar - Bhatinda - 12.53 12.52 Work completed TSR - 19.5 km 99 155 Rewari - Ringus - TSR 7.60 4.00 Not required and deleted from Pink - 33.57 km Book 11-12 100 156 Udaipur City - 5.59 5.56 Work completed Himmatnagar - TSR - 24.82 km 101 157 Sawai Madhopur - 3.04 2.84 Work completed Jaipur - TSR - 10.3 km (P) 102 158 Hissar - Bhatinda - 7.29 5.57 Work completed TSR - 19 km (P) (11 stations) (23 loop lines) 103 159 Merta Road – 11.33 4.20 Work in Progress Bika-ner - TSR - 18.2 km (P) (12stations) (24 loop lines) 104 160 Merta Road –Jodh-pur 8.26 3.88 Work in Progress - TSR - 13.2 km(P) (10 stations) (17 loop lines) 105 161 Rai ka Bag - Phalodi - 4.78 3.01 Work completed TSR - 7.6 km (P) (7 stations) (10 loop lines) 106 162 Rewari - Hisar - TSR - 40.81 39.58 Work completed 100 km (P) 107 163 Madar - Palanpur - 4.18 1.35 Work in Progress TBR - 80 km

11 108 164 Merta Road - Bik- 2.36 1.81 Work completed aner - TBR & deep screening - 40 km 109 165 Bikaner Division - 3.89 3.88 Work in Progress Turnouts (45 sets) & traps (32 sets) 110 166 Rewari - Bandikui - 3.55 3.51 Work completed Jaipur - TTR (37 Nos) (P) 111 167 Madar - Palanpur - 3.30 1.53 Work completed TTR (43 Nos) & traps (41 Nos) 112 168 Lalgarh - Suratgarh - 3.20 3.19 Work completed TTR (40 Nos) 113 169 Rewari - Hissar - TTR 4.15 4.04 Work in Progress (53 Nos) 114 170 Merta Road - 2.87 1.45 Work in Progress Bika-ner - TTR (34 Nos) 115 171 Rewari - Phulera - 3.55 3.05 Work in Progress TTR (39 Nos) 116 172 Rewari-Hissar-TTR 7.89 5.43 Work in Progress (P)(70Nos)(12 yards) 117 173 Hissar - Bhatinda - 3.64 0.82 Work in Progress Bikaner - TTR (P) (24 Nos & 18 Nos) (22 yards) 118 174 TTR(P) 58 nos of 3.88 3.08 Work in Progress existing 1in12(14 Nos.), 1 in 8.5 (31 Nos.) & D/S(13 Nos.) on PSC sleepers in Jaipur yard, Rewari-Phulera section in Jaipur division 119 175 Rai ka Bagh Palace - 4.38 4.15 Work completed and deleted from Jaisalmer - Welding - Pink Book 11-12 145 km & Bikaner - Merta Road - Welding (13 stations) (858 joints) 120 176 Madar - Palanpur - 3.28 2.01 Work in Progress TFR - 80 km (P) 121 177 Degana - Jodhpur - 2.97 1.40 Work in Progress TFR - 73 km

12 122 178 Bikaner - Merta Road 2.97 1.42 Work in Progress -TFR - 73 km 123 179 Hissar - Bhatinda - 28.79 24.26 Work completed CTR - 21 km & TSR - 10 km (P) 124 180 Merta Road- Bikaner 6.50 2.46 May be deleted from Pink Book 11-12 & Jodhpur - Through weld repair - 104 km 125 181 Rewari - Madar - TFR 7.09 5.81 Work completed - 138 km 126 182 Works in progress - - Details in LAW Book items below costing Rs. 2.50 Cr each 127 183 TRR(P)of4.023 Km bet 2.70 0 Work in Progress Km 508.5-589.6&614.7-92 7.9 atImp& Maj bridges in MD-PNU sec 128 184 TRR(P) of 15 Km from 11.82 3.00 Work Completed Km 18.8-20.8, 35-39, 51.1-53.1, 69-72, 75-76 & 76-79 in RE-HSR sec 129 185 Glued Joints Renewal 5.20 0 Work in Progress of 975 Nos.MD-PNU sec. 130 186 TRR(S) of 12.58 Km & 10.24 0 Work in Progress ISD of 47.618 Km of Loop Lines from M+4 to M+7 in MD-PNU sec 131 187 Laying of 60 Kg 1in12 11.41 0.01 Work not started TWS & WCMSC-50 nos in FL-JU-MJ sec 132 188 Laying of 60 Kg 1in12 13.24 0.01 Work not started TWS & WCMS in RE-BKI sec (18 nos) & JP–SWM sec (40 nos) 133 189 TBR of 51 Km in MTD 3.28 0.01 Work in Progress –JU sec (33 Km bet Km 670-714) & JU–MJ sec(18 Km from Km 593-611) 134 190 CTR of 5.166 Km 7.25 0.50 Work Completed (From Km 187-192.166) in AQG-POK sec

13 135 191 TRR(P) of 5 Km 5.17 3.16 Work Completed (FromKm 160-165) & CTR(P) of 1 Km (FromKm 181-182) in SOG-BKN sec 136 192 TRR(P) of 4.9 Km 3.38 0.50 Work Completed (From Km 510.1-515) in BKN-MTD sec 137 193 TTR(P)of1in8.5 T/out 4.62 0 Work in Progress -43 nos & Trap–19 nos in MD-PNU sec 138 194 New Works below - - Details in LAW Book items costing Rs. 2.50 Cr each

P.H.-32- Bridge Works

139 199 Madar- Palanpur- 6.83 2.37 Total 08 bridges. 07 bridges have Regirdering & been completed upto March 2011. Br. strengthening of NO. 831 was completed during April sub structure 2010. Br. No. 823 is in progress. (Bridge Nos. 736, 789, 792, 793, 823, 831, 843, 848 ) (Total 8 Bridges) 140 200 Jethi - Chitrasani - 5.59 0 i) GAD approved. CRS sanction Regirdering & received. Design of pile and pile cap Strengthening of approved. sub structure ii) Tender awarded (bridge No. 845) iii) Work order to be placed on (6x30.50m) with workshop for girders. Drawing for underslung girder awaited from RDSO. super-structure 141 201 Hisar - Bhatinda - 9.06 1.22 Work on Br. No. 170, 175 & 68 suratgarh completed upto March 11. Bridge No. strengthening of 28 & 142 is under planning. major bridge for 30 tones axle load for upgrading of feeder route to dedicated freight corridor. Total bridge no. 5

14 142 202 Phulera - Degana - 4.62 1.79 Works on 6 Bridges i.e. Br. 17, 21, 36, Repl. of steel 39, 40, 44 completed during the year. girders by Revised Estimate sent to Railway pre-stressed Board on 28.02.11. Sanction is concrete slabs awaited to take up further works. (bridge Nos 17, 21, 32, 34, 36, 39, 40, 44 & 47): 9 Bridges. 143 203 Jodhpur - Marwar 4.08 3.82 Work completed in July 2010. Jn. - Repl. of steel girders by pre-stressed concrete slabs (bridge No 85) 17X12.20m) 144 204 Jodhpur - Marwar 4.08 3.21 Work completed in August 2010. Jn. - Repl. of steel girders by pre-stressed concrete slabs (bridge No 92) (17X12.20m) 145 205 Phulera Degana - 5.15 4.17 All 10 No. girders received at site. Regirdering (bridge Tender for regirdering awarded. No 22) (10X24.40m) 146 207 Hisar - Bathinda - 4.10 0.04 Bridge no. 95, 98, 99, 100, 103, 105, Suratgarh - 110, 111, 112 & 126 (Total 10 Strengthening of Bridges) completed upto March 2011. substructure of 81 30 drawings were approved. bridges, (Eastern Corridor). 147 208 Rewari - Hisar - 2.80 0 Bridge no. 15, 34, 44, 52, 53, 55 & 71 Strengthening of of RE - HSR section (Total 7 Bridges) substructure of 64 were completed in Feb. 2011. 27 bridges. (Western drawings were approved. Corridor) 148 AII-Regirdering of bridge no.509 incl. Strengthening 195 6.00 5.51 Work completed. (jacketting) of sub-structure & foundation etc.

15 149 AII-Regirdering of bridge no.676 incl. Strengthening 196 3.45 3.09 Work completed. (jacketting) of sub-structure & foundation 150 Strengtheningof major bridges for 30 ton axle load for upgradation of Work completed at Br. No. 68, 170 & 201 9.07 0 feeder rout to 175 dedicated freight on HSR-BTI-SOG sec. 151 Contract awarded on 28.09.10. RCC HSR-BTI-SOG-BD box casting is in progress. Plan for 25 WL : Strengthening 207 4.11 0.05 Bridges approved & 11 nos. are of substructure (81 under approval in HQ.Work at 9 bridges) bridge completed. P.H.-33- S & T Works 152 JAL-BMN-PNU-Blo ck providing by Physically completed. Supply of Tool 213 8.19 5.86 Axle Counter (25 Kit left. Block sec.) 153 Detailed Estimate sanctioned on 25.01.2010. Financial Expenditure MJ-MVJ - 6 quad 223 6.00 0 kept pending as per Railway board cable 152 km. order.Work de-freezed in March 2010. MS for cables submitted to HQ 154 LGH-BTI : Streng-thening of telecom circuits by Estimate sanctioned. However, Board 221 OFC and 5.64 0 has instructed not to incur any liability STM-1/STM-4 till further instructions. equipment & D/I MUX. (112 km) 155 Jodhpur-Phalodi Jn. - Provision of optic fibre cables 217 3.41 3.36 Work completed. STM-1/ STM-4 equipment & D/1 MUX.

16 156 Mandore-Pokran-J aisalmer 6 MDB-PLC: Commissioned. 218 composite cable 9.41 2.47 PLC-JSM : 150 km 6 (E-route) quad cable and OFC duct laid. (290 km) 157 JU-MTD-DNA-Opti c fibre 219 4.87 2.09 Work in progress. 150 km OFC laid. cable,STM-1/4 Equp & D/1 MUX 158 MTD, DNA & RKB- 220 Track circuiting in 4.87 0.50 Work in progress. complete yard. 159 Degana-Phulera optic fibre cable, Work transferred to M/s Railtel as per 222 STM-1/STM-4 3.25 0 instruction of HQ Rly Board. equipment and D/I MUX (112 km) 160 Rai Ka Bagh - 225 Route relay 3.00 0 Contract awarded on 22.09.10. interlocking. P.H.-36-Other Electrical Works 161 228 Jaisalmer - Wind 66.50 0 Being dealt by HQ. power plant (10.5 MW capacity) P.H.-42-Workshop and Prod.unit 162 235 Madar- Routine 17.40 0 Detailed estimate sanctioned overhauling facilities. 163 232 BME-Integrated 3.33 0 Work dropped in ref. to CME/NWR coach care letter no.NWR/M/ 324/Intra/coach/vol-I complex. dated 7.2.2008. Case reviewed and revived. Detailed Estimate sanctioned.Tender for building work opened on 03.12.10 & under TC. ESP under approval of HQ for track work & building work. P.H.- 51 – Staff Quarters 164 242 UDZ-HMT- Shifting 4.23 0 Estimate resubmitted for A/C vetting of gang from for construction of Type II quarters in section to stations place of Type I quarters. Scope - 37 (16 Gangs) Type II quarters. Decision of new (128 Type I quarter pend till finalisation of BG & 32 Type II) alignment.

17 165 245 ABR- Repl. Of 2.83 0 Plan under preparation for gang quarters, 10 construction of 47 Nos. Type II qtrs gangs (100 units due to reduction in scope of work as type I quarters) with per joint note.Estimate under A/C type II. vetting since 25.11.10. Estimate not being vetted by A/C due to shortage of fund. 166 Reconstruction of 2.52 0.24 Work de-freezed. For BKN HQ, tender quarters Type-I-66, opened on 07.09.10 & under TC. Type-II-17, For section of DEN/S, tender opened Type-III-2 & on 03.09.10 but discharged. Tender Type-IV-1 unit over re-opened on 08.12.10 & under TC. BKN Divn. (Type-I = For section of Sr.DEN/E, tender BNW-2, HSR-33, opened on 13.10.10 & under TC. BKN-10, SGNR-6 & SDLP-15 243 Total-66 Qtrs.) (Type-II = BNW-2, HSR-9, BKN-1, SGNR-1, SDLP-2 LHU-1 & RTGH-1 Total-17 Qtrs.) (Type-III = BNW-1 & SDLP-1 Total - 2 Qtrs.) (Type-IV = BNW-1) 167 Replacement of 3.29 0 Contract awarded on 13.12.2010 but quarters, type-I-88 terminated to be reopened on & type-II-1 with 04.04.11. 246 type-II total 89 units on Bikaner Division. 168 Replacement of 3.27 0.25 Work is in progress. gang quarters with 248 type-II 63 units over RTGH sub-divn. 169 240 Nizampur & Ateli :- 4.11 0 Tender opened on 24.10.08 & tender Replacement of cancelled. Material modification (Type gang quarters, I to type II) sent to HQ for sanctioned type I 118 & type second week of Nov. 09. Tender II -22 units. opened on 30.09.10 for 64 units type II Quarter and dis charged. Re tender opened on 06.01.11 & under finalization.

18 170 RKB-JSM- 4.03 0 Repla-cement of 241 jack arch roof type Work in progress. quarters, type-I-136 units 171 Jodhpur division- 3.88 0 Work in progress. Replacement of 244 arch type I- 84 type -II - 33 units with standard type-II. P.H.- 52 – Staff Amenities 172 250 Community Halls at 6.40 4.80 ABR - Work in progress. Sikar, FL, JU, Aii, UDZ- Work started but stopped due HMH, UDZ and to stay order. (Land dispute between ABR. Army and state govt.) started again in Mar.2010 but stopped in April 10. AII- Work dropped & sanctioned separate-ly in LB 2010-11 for renovation of existing community hall. HMH- Completed. SIKAR & FL : Completed. JU : Completed. 173 251 Rewari- Jaipur - The progress in water supply work is Improvement to out of 5750 RM 4500 RM have been water supply, roads laid . The progress of RCC OH tank is & drainage. out 5 RCC over head tank 3 RCC 3.20 1.04 over head tank completed & one is progress. The road work is completed out of 27000 Sqm 27500 Sqm is constructed. The bill of RS. One crore is pending. 174 252 Jodhpur – 1.00 0 Under review. Upgrad-ation of Divisional Hospital (PB No. 526/09-10/SR) P.H.- 64 – Other Specified Works 175 258 Udaipur- 3.00 0 Work monitered by Principle Upgradation of ZRTI/UDZ. Work in progress. training facilities at 28 works - 24 zonal railway completed. Balance 1- Moulded training institute. chairs for Audi -400 Nos.2 - 15 Nos. Book shelves. 3 - Two work to be executed by IRITM, LKO, software for training of Drivers.

19 176 259 AII-PNU-Infrastructu 2.51 0 Siding is to be provided on 6 stations re facilities for i.e. MJ, RN, ABR, JWB, SOH, IQG mechanization of while rest room is to be provided on 5 track(7 stations). stations i. e. DOZ, JWB, SOH, IQG & SOD.work awarded on 06.09.10 for stabling sidings & started . For resting facility retender opened on 08.09.10 & discharged. Tender again reinvited on 06.01.11 & under TC. (T. No. 265/10) 177 260 Infrastructure 3.27 1.47 Civil work completed at JMS, HMH, facilities for RMN, PGK & SBNR (5 stations) and mechanisation of work dropped at KNL & APH (2 track (7 stations) stations) Track work will be executed by CAO/C alongwith Std III work 178 Building work awarded on 21.09.10 Jaipur :- and Stractural & design work 261 Upgradation of 21.12 2.65 awarded on 25.08.10. The Railway hospital dismentaling started. (T & P booking 83 Lac) 179 North Western Rly - Pertains to HQ. 262 Integrated security 8.27 0 system (04 stns)

********