<<

FM 5-410

CHAPTER 8

Soil Compaction

Soil compaction is one of the most critical such as embankments, subgrades, and bases components in the construction of , air- for and airfield pavements. No other fields, embankments, and foundations. The construction process that is applied to natural durability and stability of a structure are re- produces so marked a change in their lated to the achievement of proper soil physical properties at so low a cost as compac- compaction. Structural failure of roads and tion (when it is properly controlled to produce airfields and the damage caused by founda- the desired results). Principal soil properties tion settlement can often be traced back to the affected by compaction include— failure to achieve proper soil compaction. Settlement. resistance. Compaction is the process of mechanically Movement of water. densifying a soil. Densification is ac- Volume change. complished by pressing the soil particles together into a close state of contact with air Compaction does not improve the desirable being expelled from the soil mass in the properties of all soils to the same degree. In process. Compaction, as used here, implies certain cases, the engineer must carefully dynamic compaction or densification by the consider the effect of compaction on these application of moving loads to the soil mass. properties. For example, with certain soils This is in contrast to the consolidation process the desire to hold volume change to a mini- for fine-grained soil in which the soil is mum may be more important than just an gradually made more dense as a result of the increase in shearing resistance. application of a static load. With relation to compaction, the density of a soil is normally SETTLEMENT expressed in terms of dry density or dry unit A principal advantage resulting from the weight. The common unit of measurement is compaction of soils used in embankments is pcf. Occasionally, the wet density or wet unit that it reduces settlement that might be weight is used. caused by consolidation of the soil within the body of the . This is true be- Section I. Soil Properties cause compaction and consolidation both Affected by Compaction bring about a closer arrangement of soil par- ticles. ADVANTAGES OF SOIL COMPACTION Densification by compaction prevents later Certain advantages resulting from and settlement of an embank- compaction have made it a standard proce- ment. This does not necessarily mean that dure in the construction of earth structures, the embankment will be free of settlement; its

Soil Compaction 8-1 FM 5-410 weight may cause consolidation of compres- corresponding to a minimum swell and mini- sible soil layers that form the embankment mum shrinkage may not be exactly the same, . soils in which volume change is a factor generally may be compacted so that these ef- SHEARING RESISTANCE fects are minimized. The effect of swelling on Increasing density by compaction usually is important and is increases shearing resistance. This effect is evaluated by the standard method used by highly desirable in that it may allow the use of the US Army Corps of Engineers in preparing a thinner pavement structure over a com- samples for the CBR test. pacted or the use of steeper side slopes for an embankment than would other- Section II. Design wise be possible. For the same density, the Considerations highest strengths are frequently obtained by using greater compactive efforts with water contents somewhat below OMC. Large-scale MOISTURE-DENSITY RELATIONSHIPS experiments have indicated that the uncon- Nearly all soils exhibit a similar relation- fined compressive strength of a clayey ship between moisture content and dry could be doubled by compaction, within the density when subjected to a given compactive range of practical field compaction proce- effort (see Figure 8-1). For each soil, a maxi- dures. mum dry density develops at an OMC for the compactive effort used. The OMC at which maximum density is obtained is the moisture MOVEMENT OF at which the soil becomes sufficiently When soil particles are forced together by workable under a given compactive effort to compaction, both the number of voids con- cause the soil particles to become so closely tained in the soil mass and the size of the packed that most of the air is expelled. For individual void spaces are reduced. This most soils (except cohesionless ), when change in voids has an obvious effect on the the moisture content is less than optimum, movement of water through the soil. One ef- the soil is more difficult to compact. Beyond fect is to reduce the permeability, thus optimum, most soils are not as dense under a reducing the seepage of water. Similarly, if given effort because the water interferes with the compaction is accomplished with proper the close packing of the soil particles. Beyond moisture control, the movement of capillary optimum and for the stated conditions, the air water is minimized. This reduces the ten- content of most soils remains essentially the dency for the soil to take up water and suffer same, even though the moisture content is in- later reductions in shearing resistance. creased. The moisture-density relationship shown VOLUME CHANGE in Figure 8-1 is indicative of the workability of Change in volume (shrinkage and swelling) the soil over a range of water contents for the is an important soil property, which is critical compactive effort used. The relationship is when soils are used as subgrades for roads valid for laboratory and field compaction. and airfield pavements. Volume change is The maximum dry density is frequently generally not a great concern in relation to visualized as corresponding to 100 percent compaction except for soils where com- compaction for the given soil under the given paction does have a marked influence. For compactive effort. these soils, the greater the density, the greater the potential volume change due to The curve on Figure 8-1 is valid only for one swelling, unless the soil is restrained. An ex- compactive effort, as established in the pansive clay soil should be compacted at a laboratory. The standardized laboratory moisture content at which swelling will not compactive effort is the compactive effort exceed 3 percent. Although the conditions (CE) 55 compaction procedure, which has

Soil Compaction 8-2 FM 5-410

been adopted by the US Army Corp of En- air contained in the voids of the soil by com- gineers. Detailed procedures for performing paction alone is not possible. Typically, at the CE 55 compaction test are given in TM moisture contents beyond optimum for any 5-530. The maximum dry density (ydmax) at compactive effort, the actual compaction the 100 percent compaction mark is usually curve closely parallels the zero air-voids termed the CE 55 maximum dry density, and curve. Any values of the dry density curve the corresponding moisture content is the op- that plot to the right of the zero air-voids timum moisture content. Table 8-1, page 8-4, curve are in error. The specific calculation shows the relationship between the US Army necessary to plot the zero air-voids curve are Corps of Engineers compaction tests and in TM 5-530. their civilian counterparts. Many times the names of these tests are used interchange- Compaction Characteristics ably in publications. of Various Soils The nature of a soil itself has a great effect Figure 8-1 shows the zero air-voids curve on its response to a given compactive effort! for the soil involved. This curve is obtained by Soils that are extremely light in weight, such plotting the dry densities corresponding to as diatomaceous earths and some volcanic complete saturation at different moisture soils, may have maximum densities under a contents. The zero air-voids curve represents given compactive effort as low as 60 pcf. theoretical maximum densities for given Under the same compactive effort, the maxi- water contents. These densities are practi- mum density of a clay may be in the range of cally unattainable because removing all the 90 to 100 pcf, while that of a -graded,

Soil Compaction 8-3 FM 5-410

coarse granular soil may be as high as 135 pcf. moisture, producing sizable changes in dry Moisture-density relationships for seven density. different soils are shown in Figure 8-2. Compacted dry-unit weights of the soil There is no generally accepted and univer- groups of the Unified Sys- sally applicable relationship between the tem are given in Table 5-2, page 5-8. Dry- unit weights given in column 14 are based on OMC under a given compactive effort and the compaction at OMC for the CE 55 compactive Atterberg limit tests described in Chapter 4. effort. OMC varies from about 12 to 25 percent for fine-grained soils and from 7 to 12 percent for The curves of Figure 8-2 indicate that soils well-graded granular soils. For some clay with moisture contents somewhat less than soils, the OMC and the PL will be ap- optimum react differently to compaction. proximately the same. Moisture content is less critical for heavy clays (CH) than for the slightly plastic, clayey Other Factors That Influence Density sands (SM) and silty sands (SC). Heavy clays In addition to those factors previously dis- may be compacted through a relatively wide cussed, several others influence soil density, range of moisture contents below optimum to a smaller degree. For example, tempera- with comparatively small change in dry den- ture is a factor in the compaction of soils that sity. However, if heavy clays are compacted have a high clay content; both density and wetter than the OMC (plus 2 percent), the soil OMC may be altered by a great change in becomes similar in texture to peanut butter temperature. Some clay soils are sensitive to and nearly unworkable. The relatively clean, manipulation; that is, the more they are poorly graded sands also are relatively unaf- worked, the lower the density for a given com- fected by changes in moisture. On the other pactive effort. Manipulation has little effect hand, granular soils that have better on the degree of compaction of silty or clean and higher densities under the same cormpac- sands. Curing, or drying, of a soil following tive effort react sharply to slight changes in compaction may increase the strength of

Soil Compaction 8-4 FM 5-41O

subgrade and base materials, particularly if processing granular materials, the best cohesive soils are involved. results are generally obtained by sprinkling and mixing in place. Any good mixing equip- Addition of Water to Soil ment should be satisfactory. The more friable Often water must be added to soils being in- sandy and silty soils are easily mixed with corporated in embankments, subgrades, and water. They may be handled by sprinkling bases to obtain the desired degree of compac- and mixing, either on the or in the pit. tion and to achieve uniformity. The soil can Mixing can be done with motor graders, be watered in the borrow pit or in place. After rotary mixers, and commercial harrows to a the water is added, it must be thoroughly depth of 8 inches or more without difficulty. and uniformly mixed with the soil. Even if additional water is not needed, mixing may If time is available, water may also be still be desirable to ensure uniformity. In added to these soils by diking or ponding the

Soil Compaction 8-5 FM 5-410 pit and flooding until the desired depth of and maximum density. If the compactive ef- penetration has taken place. This method fort is increased, the maximum density is usually requires several days to accomplish increased and the OMC is decreased. This uniform moisture distribution. Medium fact is illustrated in Figure 8-3. It shows clayey soils can be worked in the pit or in place moisture-density relationships for two dif- as conditions dictate. The best results are ob- ferent soils, each of which was compacted tained by sprinkling and mixing with using two different compactive efforts in the cultivators and rotary mixers. These soils laboratory. When the same soil is compacted can be worked in lifts up to 8 inches or more under several different compactive efforts, a without great difficulty. Heavy clay soils relationship between density and compactive present many difficulties and should never be effort may be developed for that soil. used as fill in an embankment foundation. They should be left alone without disturbance This information is of particular interest to since usually no compactive effort or equip- the engineer who is preparing specifications ment is capable of increasing the in-place for compaction and to the inspector who must condition with reference to consolidation and interpret the density test results made in the . field during compaction. The relationship be- tween compactive effort and density is not The length of the section being rolled may linear. A considerably greater increase in have a great effect on densities in hot weather compactive effort will be required to increase when water evaporates quickly. When this the density of a clay soil from 90 to 95 percent condition occurs, quick handling of the soil of CE 55 maximum density than is required to may mean the difference between obtaining effect the same changes in the density of a adequate density with a few passes and re- sand. The effect of variation in the compac- quiring extra effort to add and mix water. tive effort is as significant in the field rolling process as it is in the laboratory compaction Handling of Wet Soils procedure. In the field, the compactive effort When the moisture content of the soil to be is a function of the weight of the roller and the number of passes for the width and depth of compacted greatly exceeds that necessary for the area of soil that is being rolled. Increas- the desired density, some water must be ing the weight of the roller or the number of removed. In some cases, the use of exces- passes generally increases the compactive ef- sively wet soils is possible without detrimen- fort. Other factors that may be of consequence tal effects. These soils (coarse aggregates) include— are called free-draining soils, and their maxi- mum dry density is unaffected by moisture Lift thickness. content over a broad range of moisture. Most Contact pressure. often, these soils must be dried; this can be a Size and length of the tamping feet slow and costly process. The soil is usually (in the case of sheepsfoot rollers). dried by manipulating and exposing it to Frequency and amplitude (in the case aeration and to the rays of the sun. of vibratory compactors). Manipulation is most often done with cul- tivators, plows, graders, and rotary mixers. To achieve the best results, laboratory and Rotary mixers, with the tail-hood section field compaction must be carefully correlated. raised, permit good aeration and are very ef- fective in drying excessively wet soils. An COMPACTION SPECIFICATIONS excellent method that may be useful when To prevent detrimental settlement under both wet and dry soils are available is simply traffic, a definite degree of compaction of the to mix them together. underlying soil is needed. The degree depends on the wheel load and the depth below the Variation of Compactive Effort surface. For other airfield construction and For each compactive effort used in compact- most road construction in the theater of oper- ing a given soil, there is a corresponding OMC ations, greater settlement can be accepted,

Soil Compaction 8-6 FM 5-410

.

.

although the amount of maintenance will range of 90 to 95 percent compaction and a generally increase. In these cases, the mini- moisture range of 12 to 16 percent. mum compaction requirements of Table 8-2, page 8-8, should be met. However. strength CBR Design Procedure can possibly decrease with increased compac- The concept of the CBR analysis was intro- tion. particularly with cohesive materials. duced in Chapter 6. In the following As a result, normally a 5 percent compaction procedures, the CBR analytical process will range is established for density and a 4 per- be applied to develop soil compaction cent range for moisture. Commonly, this specifications. Figure 8-5, page 8-10, outlines “window” of density and moisture ranges is the CBR design process. The first step is to plotted directly on the GE 55 compaction look at the CE 55 compaction curve on a DD curve and is referred to as the specifications Form 2463, page 1. If it is U-shaped, the soil block. Figure 8-4, page 8-8, shows a density is classified as “free draining” for CBR

Soil Compaction 8-7 FM 5-410

Soil Compaction 8-8 FM 5-410

analysis and the left-hand column of the flow- Once you have determined the design den- chart should be used through the design sity range and the moisture content range, process. If it is bell-shaped, use the swell data you have the tools necessary to specify the re- graphically displayed on a DD Form 1211. quirements for and manage the compaction Soils that, when saturated, increase in operations. However, placing a particular volume more than 3 percent at any initial soil in a construction project is determined by moisture content are classified as swelling its gradation. , and design soils. If the percentage of swelling is ‹ 3 per- CBR value. Appendix A contains a discussion cent, the soil is considered nonswelling. of the CBR design process. Regardless of the CBR classification of the A detailed discussion of placing soils soil, the density value from the peak of the CE and aggregates in an aggregate surface or a 55 moisture density curve is ydmax. The flexible pavement design is in FM 5-430 next step is to determine the design moisture (for theater-of-operations construction), content range. For nonswelling soils, the TM 5-822-2 (for permanent airfield design), OMC is used. When the OMC is used, the and TM 5-822-5 (for permanent road design). design moisture content range is + 2 percent. For swelling and free-draining soils, the min- imum moisture content (MMC) is used. The Subgrade Compaction MMC is determined differently for swelling In fill sections, the subgrade is the top layer soils than it is for free-draining soils. The of the embankment, which is compacted to MMC for swelling soils is determined by find- the required density and brought to the ing the point at which the 3 percent swell desired grade and section. For subgrades, occurs. The content that cor- plastic soils should be compacted at moisture responds to the 3 percent swell is the MMC. contents that are close to optimum. Moisture Free-draining soils exhibit an increase in contents cannot always be carefully con- density in response to increased soil moisture trolled during military construction, but up to a certain moisture content, at which certain practical limits must be recognized. point no further increase in density is Generally, plastic soils cannot be compacted achieved by increasing moisture. The mois- satisfactorily at moisture contents more than ture content that corresponds to ydmax is the 10 percent above or below optimum. Much MMC. For both swelling and free-draining better results are obtained if the moisture CBR soil classes, the design moisture-content content is controlled to within 2 percent of op- range is MMC + 4 percent. timum. For cohesionless soils, moisture control is not as important, but some sands For swelling and free-draining soils, the tend to bulk at low moisture content. Com- final step in determining design compaction paction should not be attempted until this requirements is to determine the density situation is corrected. Normally, - range. Free-draining soils are compacted to less soils are compacted at moisture contents 100-105 percent ydmax. Swelling soils are that approach 100 percent saturation. compacted to 90-95 percent dmax. In sections, particularly when flexible Compaction requirement determinations pavements are being built to carry heavy for nonswelling soils require several additional wheel loads, subgrade soils that gain strength steps. Once the OMC and design moisture with compaction should be compacted to the content range have been determined, look at a general requirements given earlier. This DD Form 1207 for the PI of the soil. If PI > 5, may make it necessary to remove the soil, the soil is cohesive and is compacted to 90-95 replace it, and compact it in layers to obtain percent ydmax. If the PI < 5, refer to the CBR the required densities at greater depths. In Family of Curves on page 3 of DD Form 2463. most construction in the theater of opera- If the CBR values are insistently above 20, tions, subgrade soil in cut sections should be compact the soil to 100-105 percent ydmax. If scarified to a depth of about 6 inches and the CBR values are not above 20, compact the recompacted. This is commonly referred to as soil to 95-100 percent dmax. a scarify/compact in-place (SCIP) operation.

Soil Compaction 8-9 FM 5-410

Soil Compaction 8-10 FM 5-410

This procedure is generally desirable in the compact them. Instead, they should be left in interest of uniformity. their natural state and additional cover material used to prevent the subgrade from Expansive Clays. As indicated previously, being overstressed. soils that have a high clay content (partic- ularly (CH), (MH), and (OH)) may expand in When these soils are encountered, their detrimental amounts if compacted to a high sensitivity may be detected by performing un- density at a low moisture content and then ex- confined compression tests on the un- posed to water. Such soils are not desirable as disturbed soil and on the remolded soil com- subgrades and are difficult to compact. If they pacted to the design density at the design have to be used, they must be compacted to moisture content. If the undisturbed value is the maximum density obtainable using the higher, do not attempt to compact the soil; MMC that will result in a minimum amount manage construction operations to produce of swelling. Swelling soils, if placed at mois- the least possible disturbance of the soil. ture contents less than the MMC, can be Base the pavement design on the bearing expected to swell more than 3 percent. of the undisturbed soil. volume increases of up to 3 percent generally do not adversely affect theater-of-operations structures. This method requires detailed Base Compaction testing and careful control of compaction. In Selected soils that are used in base con- some cases, a base of sufficient thickness struction must be compacted to the general should be constructed to ensure against the requirements given earlier. The thickness of harmful effects of expansion. layers must be within limits that will ensure proper compaction. This limit is generally Clays and Organic Soils. Certain clay soils from 4 to 8 inches, depending on the material and organic soils lose strength when and the method of construction. remolded. This is particularly true of some (CH) and (OH) soils. They have high Smooth-wheeled or vibratory rollers are strengths in their undisturbed condition, but recommended for compacting hard, angular scarifying, reworking, and compacting them materials with a limited amount of fines or in cut areas may reduce their shearing stone screenings. Pneumatic-tired rollers are strengths, even though they are compacted to recommended for softer materials that may design densities. Because of these qualities, break down (degrade) under a steel roller. they should be removed from the construction site. Maintenance of Soil Density Soil densities obtained by compaction . When some silts and very fine sands during construction may be changed during (predominantly (ML) and (SC) soils) are com- the life of the structure. Such considerations pacted in the presence of a high water table, are of great concern to the engineer engaged they will pump water to the surface and be- in the construction of semipermanent instal- come “quick”, resulting in a loss of shearing lations, although they should be kept in mind strength. These soils cannot be properly com- during the construction of any facility to en- pacted unless they are dried. If they can be sure satisfactory performance. The two compacted at the proper moisture content. principal factors that tend to change the soil their shearing resistance is reasonably high. density are— Every effort should be made to lower the Climate. water table to reduce the potential of having Traffic. too much water present. If trouble occurs with these soils in localized areas, the soils As far as embankments are concerned, nor- can be removed and replaced with more mal embankments retain their degree of suitable ones. If removal, or drainage and compaction unless subjected to unusual con- later drying, cannot be accomplished, these ditions and except in their outer portions, soils should not be disturbed by attempting to which are subjected to seasonal wetting and

Soil Compaction 8-11 FM 5-410 drying and frost action. Subgrades and bases For military construction, this is generally a are subject to more severe climatic changes specified minimum percentage of CE 55 max- and traffic than are embankments. Climatic imum density for the soil concerned. The changes may bring about seasonal or per- moisture content of the soil is maintained at manent changes in soil moisture and or near optimum, within the practical limits accompanying changes in density, which may of field construction operations (normally + 2 distort the pavement surface. High-volume- percent of the OMC). Principal types of change soils are particularly susceptible and equipment used in field compaction are should be compacted to meet conditions of sheepsfoot, smooth steel-wheeled, vibratory, minimum swelling and shrinkage. Granular and pneumatic-tired rollers. soils retain much of their compaction under exposure to climatic conditions. Other soils may be somewhat affected, particularly in SELECTION OF MATERIALS areas of severe seasonal changes, such as— Soils used in fills generally come from cut Semiarid regions (where long, hot, sections of the road or airfield concerned, dry periods may occur). provided that this material is suitable. If the Humid regions (where deep freezing material excavated from cut sections is not occurs). suitable, or if there is not enough of it, then some material is obtained from other sources. Frost action may change the density of a Except for highly organic soils, nearly any soil compacted soil, particularly if it is fine- can be used in fills. However, some soils are grained. Heavy traffic, particularly for more difficult to compact than others and subgrades and bases of airfields, may bring some require flatter side slopes for stability. about an increase in density over that ob- Certain soils require elaborate protective tained during construction. This increase in devices to maintain the fill in its original con- density may cause the rutting of a flexible dition. When time is available, these pavement or the subsidence of a rigid pave- considerations and others may make it ad- ment. The protection that a subgrade soil vantageous to thoroughly investigate receives after construction is complete has an construction efforts, compaction charac- important effect on the permanence of com- teristics, and shear strengths of soils to be paction. The use of good shoulders, the used in major fills. Under expedient condi- maintenance of tight joints in a concrete tions, the military engineer must simply pavement, and adequate drainage all con- make the best possible use of the soils at tribute toward maintaining the degree of hand. compaction achieved during construction. In general terms, the coarse-grained soils of Section III. Construction the USCS are desirable for fill construction, Procedures ranging from excellent to fair. The fine- grained soils are less desirable, being more difficult to compact and requiring more care- GENERAL CONSIDERATIONS ful control of the construction process. Table The general construction process of a 5-2, page 5-8, and Table 5-3, respectively con- rolled-earth embankment requires that the tain more specific information concerning the fill be built in relatively thin layers or “lifts,” suitability of these soils. each of which is rolled until a satisfactory de- gree of compaction is obtained. The subgrade DUMPING AND SPREADING in a fill section is usually the top lift in the Since most fills are built up of thin lifts to compacted fill, while the subgrade in a cut the desired height, the soil for each lift must section is usually compacted in in-place soil. be spread in a uniform layer of the desired Soil bases are normally compacted to a high thickness. In typical operations, the soil is degree of density. Compaction requirements fre brought in, dumped, and spread by scraper quently stipulate a certain minimum density. units. The scrapers must be adjusted carefully

Soil Compaction 8-12

FM 5-410

Soil Compaction 8-14 FM 5-410 to accomplish this objective. Materials may For adequate compaction, sands and also be brought in by trucks or wagons and that have and clay fines require dumped at properly spaced locations so that a effective control of moisture. Certain soils of uniform layer may be easily spread by blade the (GM) and (SM) groups have especially graders or bulldozers. Working alone, great need for close control. Pneumatic-tired bulldozers may form very short and shallow rollers are best for compacting these soils, al- fills. End dumping of soil material to form a though vibratory rollers may be used fill without compaction is rarely permitted in effectively. modern embankment construction except when a fill is being built over very weak soils, Large rock is sometimes used in fills, par- as in a swamp. The bottom layers may then ticularly in the lower portion. In some cases, be end dumped until sufficient material has the entire fill may be composed of rock layers been placed to allow hauling and compacting with the voids filled with smaller rocks or soil equipment to operate satisfactorily. The best and only a cushion layer of soil for the sub- thickness of the layer to be used with a given grade. The thickness of such rock layers soil and a given equipment cannot be deter- should not be more than 24 inches with the mined exactly in advance. It is best deter- diameter of the largest rock fragment being mined by trial during the early stages of roll- not greater than 90 percent of the lift thick- ing on a project. No lift, however, will have a ness. Compaction of this type of fill is difficult thickness less than twice the diameter of the but may generally be done by vibration from largest size particle in the lift. As stated pre- the passage of tack-type equipment over the viously, compacted lifts will normally range fill area or possibly 50-ton pneumatic-tired from 4 to 8 inches in depth (see Table 8-3, page rollers. 8-13). Finishing in embankment construction in- COMPACTION OF EMBANKMENTS cludes all the operations necessary to If the fill consists of cohesive or plastic soils, complete the earthwork. Included among the embankment generally must be built up these operations are the trimming of the side of uniform layers (usually 4 to 6 inches in and ditch slopes, where necessary, and the compacted thickness), with the moisture con- fine grading needed to bring the embankment tent carefully controlled. Rolling should be section to final grade and cross section. Most done with the sheepsfoot or tamping-foot of these are not separate operations per- rollers. Bonding of a layer to the one placed formed after the completion of other on top of it is aided by the thin layer of loose operations but are carried along as the work material left on the surface of the rolled layer progresses. The tool used most often in by the roller feet. Rubber-tired or smooth- finishing operations is the motor grader, wheeled rollers may be used to provide a while scraper and dozer units may be used if smooth, dense, final surface. Rubber-tired the finish tolerances are not too strict. The construction equipment may provide sup- provision of adequate drainage facilities is an plemental compaction if it is properly routed essential part of the work at all stages of con- over the area. struction, temporary and final.

If the fill material is clean sand or sandy DENSITY DETERMINATIONS , the moisture range at which compac- tion is possible is generally greater. Because Density determinations are made in the of their rapid draining characteristics, these field by measuring the wet weight of a known soils may be compacted effectively at or above volume of compacted soil. The sample to be OMC. Vibratory equipment may be used. weighed is taken from a roughly cylindrical Soils may be effectively compacted by com- hole that is dug in the compacted layer. The bined saturation and the vibratory effects of volume of the hole may be determined by one crawler tractors, particularly when tractors of several methods. including the use of— are operated at fairly high speeds so that Heavy oil of known specific gravity. vibration is increased. Rubber balloon density apparatus.

Soil Compaction 8-15 FM 5-410

Calibrated sand. required density can be achieved in the field Nuclear densimeter. with the equipment available. When the wet weight and the volume are Determination of Moisture Content known, the unit wet weight may then be cal- It may be necessary to check the moisture culated, as described in FM 5-430. content of the soil during field rolling for two reasons. First, since the specified density is In very arid regions, or when working with in terms of dry unit weight and the density soils that lose strength when remolded, the measured directly in the field is generally the adequacy of compaction should be judged by wet unit weight, the moisture content must performing the in-place CBR test on the com- be known so that the dry unit weight can be pacted soil of a subgrade or base. The CBR calculated. Second, the moisture content of thus obtained can then be compared with the some soils must be maintained close to op- design CBR, provided that the design was timum if satisfactory densities are to be based on CBR tests on unsoaked samples. If obtained. Adjustment of the field moisture the design was based on soaked samples, the content can only be done if the moisture con- results of field in-place CBR tests must be cor- tent is known. The determination of density related with the results of laboratory tests and moisture content is often done in one performed on undisturbed mold samples of overall test procedure; these determinations the in-place soil subjected to soaking. are described here separately for con- Methods of determining the in-place CBR of a venience. soil are described in TM 5-530. Field Examination. Experienced engineers who have become familiar with the soils en- FIELD CONTROL OF COMPACTION countered on a particular project can As stated in previous paragraphs, specifica- frequently judge moisture content accurately tions for adequate compaction of soiI used in by visual and manual examination. Friable military construction generally require the or slightly plastic soils usually contain attainment of a certain minimum density in enough moisture at optimum to permit the field rolling. This requirement is most often forming of a strong cast by compressing it in stated in terms of a specified percentage the hand. As noted, some clay soils have range of CE 55 maximum density. With OMCs that are close to their PLs; thus, a PL many soils, the close control of moisture con- or “thread” test conducted in the field may be tent is necessary to achieve the stated density highly informative. with the available equipment. Careful con- trol of the entire compaction process is Field Drying. The moisture content of a soil necessary if the required density is to be is best and most accurately determined by achieved with ease and economy. Control drying the soil in an oven at a controlled generally takes the form of field checks of temperature. Methods of determining the moisture and density to— moisture content in this fashion are described Determine if the specified density is in TM 5-530. being achieved. Control the rolling process. The moisture content of the soil may also be Permit adjustments in the field, as re- determined by air drying the soil in the sun. quired. Frequent turning of the soil speeds up the drying process. From a practical standpoint, The following discussion assumes that the this method is generally too slow to be of laboratory compaction curve is available for much value in the control of field rolling. the soil being compacted so that the maxi- mum density and OMC are known. It is also Several quick methods may be used to assumed that laboratory-compacted soil and determine approximate moisture contents field-compacted soil are similar and that the under expedient conditions. For example,

Soil Compaction 8-16 FM 5-410

the sample may be placed in a frying pan and ensure that the operator does not receive a dried over a hot plate or a field stove. The medically significant dose of radiation during temperature is difficult to control in this pro- the operation of this device. There are strin- cedure, and organic materials may be burned, gent safety and monitoring procedures that thus causing a slight to moderate error in the must be followed. The method of determining results. On large-scale projects where many the moisture content of a soil in this fashion is samples are involved, this quick method may described in the operator’s manual. be used to speed up determinations by com- paring the results obtained from this method Determination of Water to Be Added with comparable results obtained by oven- If the moisture content of the soil is less drying. than optimum, the amount of water to be added for efficient compaction is generally Another quick method that may be useful is computed in gallons per square yards. The to mix the damp soil with enough denatured computation is based on the dry weight of soil grain alcohol to form a slurry in a perforated contained in a compacted layer. For example, metal cup, ignite the alcohol, and permit it to assume that the soil is to be placed in 6-inch, burn off. The alcohol method, if carefully compacted layers at a dry weight of 120 pcf. done, produces results roughly equivalent to The moisture content of the soil is determined those obtained by careful laboratory drying. to be 5 percent while the OMC is 12 percent. For best results, the process of saturating the Assume that the strip to be compacted is 40 soil with alcohol and burning it off completely feet wide. Compute the amount of water that should be repeated three times. This method must be added per 100-foot station to bring is not reliable with clay soils. Safety the soi1 to optimum moisture. The following measures must be observed when using this formula applies: method. The burning must be done outside or in a well-ventilated room and at a safe dis- tance from the alcohol supply and other flammable materials. The metal cup gets ex- tremely hot, arid it should be allowed to cool before handling. Substituting in the above formula from the “Speedy” Moisture-Content Test. The conditions given: “speedy” moisture test kit provided with the set provides a very rapid moisture- content determination and can be highly ac- curate if the test is performed properly. Care must be exercised to ensure that the reagent used has not lost its strength. The reagent must be very finely powdered (like portland If either drying conditions or conditions cement) and must not have been exposed to exist at the time work is in progress, it may be water or high humidity before it is used. The advisable to either add to or reduce this quan- specific test procedures are contained in the tity by up to 10 percent. test set. Nuclear Denimeter. This device provides real-time in-place moisture content and den- COMPACTION EQUIPMENT sity of a soil. Accuracy is high if the test is Equipment normally available to the performed properly and if the device has been military engineer for the compaction of soils calibrated with the specific material being includes the following types of rollers: tested. Operators must be certified, and Pneumatic-tired. proper safety precautions must be taken to Sheepsfoot.

Soil Compaction 8-17 FM 5-410

Tamping-foot. roller, usually a “wobble wheel. ” The Smooth steel-wheeled. pneumatic roller is suitable for granular Vibratory. materials; however, it is not recommended for fine-grained clay soils except as necessary for Pneumatic-Tired Roller sealing the surface after a sheepsfoot roller These heavy pneumatic-tired rollers are has “walked out. ” It compacts from the top designed so that the weight can be varied to down and is used for finishing all types of apply the desired compactive effort. Rollers materials, following immediately behind the with capacities up to 50 tons usually have two blade and water truck. rows of wheels, each with four wheels and tires designed for 90 psi inflation. They can Self-Propelled, Pneumatic-Tired Roller be obtained with tires designed for inflation The self-propelled, pneumatic-tired roller pressures up to 150 psi. As a rule, the higher has nine wheels (see Figure 8-6). It is very the tire pressure the greater the contact pres- maneuverable, making it excellent for use in sures and, consequently, the greater the confined spaces. It corn pacts from the top compactive effort obtained. Information down. Like the towed models, the self- available from projects indicates that large propelled, pneumatic-tired roller can be used rubber-tired compactors are capable of com- for compaction of most soil materials. It is pacting clay layers effectively up to about 6 also suitable for the initial compaction of inches compacted depth and coarse granular bituminous pavement. or sand layers slightly deeper. Often it is used especially for final compaction (proof rolling) of the upper 6 inches of subgrade, for subbases, and for base courses. These rollers are very good for obtaining a high degree of compaction. When a large rubber-tired roller is to be used, care should be exercised to en- sure that the moisture content of cohesive materials is low enough so that excessive pore pressures do not occur. Weaving or springing of the soil under the roller indicates that pore pressures are developing.

Since this roller does not aerate the soil as much as the sheepsfoot, the moisture content at the start of compaction should be ap- proximately the optimum. In a soil that has the proper moisture content and lift thick- For a given number of passes of a rubber- ness, tire contact pressure and the number of tired roller, higher densities are obtained passes are the important variables affecting with the higher tire pressures. However, cau- the degree of compaction obtained by rubber- tion and good judgment must be used and the tired rollers. Generally, the tire contact tire pressure adjusted in the field depending pressure can be assumed to be approximately on the nature of the soil being compacted. For equal to the inflation pressure. compaction to occur under a rubber-tired roller, permanent deformation has to occur. Variants of the pneumatic-tired roller in- If more than slight pumping or spring occurs clue the pneumatic roller and the self- under the tires, the roller weight and tire propelled pneumatic-tired roller. pressure are too high and should be lowered immediately. Continued rolling under these Pneumatic Roller conditions causes a decrease in strength even As used in this manual, the term “pneu- though a slight increase in density may occur, matic roller” applies to a small rubber-tired For any given tire pressure, the degree of

Soil Compaction 8-18 FM 5-410

compaction increases with additional passes, obtained by sheepsfoot rollers. The minimum although the increase may be negligible after foot contact pressure for proper compaction is six to eight passes. 250 psi. Most available sheepsfoot rollers are equipped with feet having a contact area of 5 Sheepsfoot Roller to 8 square inches. The foot pressure can be This roller compacts all fine-grained changed by varying the weight of the roller materials, including materials that will break (varying the amount of ballast in the drum), down or degrade under the roller feet, but it or in special cases, by welding larger plates will not compact cohesion less granular onto the faces of the feet. For the most effi- materials. The number of passes necessary cient operation of the roller, the contact for this type of roller to obtain the required pressure should be close to the maximum at densities must be determined for each type of which the roller will “walk out” satisfactorily, soil encountered. The roller compacts from as indicated in Figure 8-7. the bottom up and is used especially for plas- tic materials. The lift thickness for sheepsfoot rollers is limited to 6 inches in compacted depth. Penetration of’ the roller feet must be obtained at the start of rolling operations This roller “walks out” as it com- pletes its compactive effort, leaving the top 1 to 2 inches uncompacted. The roller may tend to “walk out” before proper compaction is obtained. To prevent this, the soil may be scarified lightly behind the roller during the first two or three passes, and additional weight may be added to the roller. A uniform density can usually be obtained throughout the full depth of the lift if the material is loose and workable enough to allow the roller feet to penetrate the layer on the initial passes. This produces compaction from the bottom up; therefore, material that becomes compacted by the wheels of equip- ment during pulverizing, wetting, blending, and mixing should be thoroughly loosened before compaction operations are begun. This also ensures uniformity of the mixture. The same amount of rolling generally The desirable foot contact pressure varies produces increased densities as the depth of for different soils, depending on the bearing the lift is decreased. If the required densities capacity of the soil; therefore, the proper ad- are not being obtained, it is often necessary to justments have to be made in the field based change to a thinner lift to ensure that the on observations of the roller. If the feet of the specified density is obtained. roller tend to “walk out,” too quickly (for ex- ample, after two passes), then bridging may In a soil that has the proper moisture con- occur and the bottom of the lift does not get tent and lift thickness, foot contact pressure sufficient compaction. This indicates that the and the number of passes are the important roller is too light or the feet too large, and the variables affecting the degree of compaction weight should be increased. However, if the

Soil Compaction 8-19 FM 5-410

roller shows no tendency to “walk out” within the required number of passes, then the in- dications are that the roller is to (heavy and the pressure on the roller feet is exceeding the bearing capacity of the soil. After making the proper adjustments in foot pressure (by changingroller size), the only other variable is the repetition of passes. Tests have shown that density increases progressively withan increase in the number of passes.

Tamping-Foot Roller A tamping-foot roller is a modification of the sheepsfoot roller. The tamping feet are trapezoidal pads attached to a drum. Tamp- ing-foot rollers are normally self-propelled, and the drum may be capable of vibrating. The tamping-foot roller is suitable for use with a wide range of soil types.

Steel-Wheeled Roller The steel-wheeled roller is much less ver- satile than the pneumatic roller. Although extensively used, it is normally operated in conjunction with one of the other three types of compaction rollers. It is used for compact- ing granular materials in thin lifts. Probably its most effective use in subgrade work is in the final finish of a surface. following immedi- ately behind the blade, forming a dense and watertight surface. Figure 8-8 shows a two- axle tandem (5- to 8-ton) roller. Self-Propelled, Smooth-Drum Vibratory Roller crawler-type tractor units and loaded hauling The self-propelled, smooth-drum vibratory units, including rubber-tired scrapers. roller compacts with a vibratory action that Crawler tractors are practical compacting rearranges the soil particles into a denser units, especially for rock and cohesionless mass (see Figure 8-9). The best results are ob- gravels and sands. The material should be tained on cohesionless sands arid gravels. spread in thin layers (about 3 or 4 inches Vibratory rollers are relatively light but thick) and is usually compacted by vibration. develop high dynamic force through an ec- centric weight arrangement. Compaction COMPACTOR SELECTION efficiency is impacted by the ground speed of Table 8-3, page 8-13, gives information con- the roller and the frequency and amplitude of cerning compaction equipment and compactive the vibrating drum. efforts recommended for use with each of the groups of the USCS. Other Equipment Other construction equipment may be Normally, there is more than one type of useful in certain instances, particularly compactor suitable for use on a project’s

Soil Compaction 8-20 FM 5-410 type(s) of soil. When selecting a compactor, use the following criteria: Availability. Efficiency.

Availability Ascertain the types of compactors that are available and operationally ready. On major construction projects or when deployed, it may be necessary to lease compaction equip- ment. The rationale for leasing compaction equipment is based on the role it plays in determining overall project duration and con- struction quality. Uncompacted lifts cannot be built on until they are compacted. Sub- stituting less efficient types of compaction equipment decreases productivity and may reduce project quality if desired dry densities are not achieved.

Efficiency Decide how many passes of each type of compactor are required to achieve the specified desired dry density. Determining the most efficient compactor is best done on a test strip. A test strip is an area that is located adjacent to the project and used to evaluate compactors and construction procedures. The Once the type(s) of compactor is selected, optimum lift thicknesses can be determined. compactive effort of each type of compactor Table 8-3, page 8-13, provides information on can be determined on the test strip and average optimum lift thicknesses, but this in- plotted graphically. Figure 8-10 compares the formation must be verified. Again, the test following types of compactors: strip is a way to determine optimum lift thick- Vibratory (vibrating drum) roller. ness without interfering with other Tamping-foot roller. operations occurring on the actual project. Pneumatic-tired roller. In actual operation, it is likely that more than In this example, a dry density of 129 to 137 one type of compactor will be operating on the pcf is desired. The vibrating roller was the project to maintain peak productivity and to most efficient, achieving densities within the continue operations when the primary com- specified density range in three passes. The pactors require maintenance or repair. Test- tamping foot compactor also compacted the strip data helps to maintain control of project soil to the desired density in three passes. quality while providing the flexibility to allow However, the density achieved (130 pcf) is so construction at maximum productivity. close to the lower limit of the desired density range that any variation in the soil may cause Section IV. Quality Control the achieved density to drop below 129 pcf. The pneumatic-tired roller was the least efficient and did not densify the soil PURPOSE material to densities within the specified Poor construction procedures can in- density range. validate a good pavement or embankment

Soil Compaction 8-21 FM 5-410

design. Therefore, quality control of construc- have plant and equipment breakdowns and tion procedures is as important to the final other problems that would require that product as is proper design. The purpose of production be stopped for certain periods of quality control is to ensure that the soil time. This halt in production could cause dif- is being placed at the proper density and ficulties in recording production time. On the moisture content to provide adequate bearing other hand, there are always records that strength (CBR) in the fill. This is ac- would show the amount of materials that complished by taking samples or testing at each stage of construction. The test results have been produced. Therefore, the better are compared to limiting values or specifica- way to describe a lot is to specify that a lot will tions, and the compaction should be accepted be expressed in units of quantity of produc- or reworked based on the results of the den- tion By using this method, each lot will sity and moisture content tests. A quality- contain the same amount of materials, estab- control plan should be developed for each lishing each one with the same relative project to ensure that high standards are importance. Factors such as the size of the achieved. For permanent construction, statisti- job and the operational capacity usually cal quality-control plans provide the most govern the size of a production lot. Typical lot reliable check on the quality of compaction. sizes are 2,000 square yards for subbase con- struction and 1,200 square yards for QUALITY-CONTROL PLAN stabilized subgrade construction. To statisti- Generally, a quality-control plan consists of cally evaluate a lot, at least four samples breaking the total job down into lots with each should be obtained and tested properly. lot consisting of “X” units of work. Each lot is considered a separate job, and each job will be Random Sampling accepted or rejected depending on the test For a statistical analysis to be acceptable, results representing this lot. By handling the the data used for this analysis must be ob- control procedure in this way, the project en- tained from random sampling. Random gineer is able to determine the quality of the sampling means that every sample within the job on a lot-by-lot basis. This benefits the en- lot has an equal chance of being selected. gineering construction unit and project There are two common types of random sam- engineer by identifying the lots that will be pling. One type consists of dividing the lot accepted and the lots that will be rejected. As into a number of equal size sublets; one ran- this type of information is accumulated from dom sample is then taken from each of the lot to lot, a better picture of the quality of the sublets. The second method consists of taking entire project is obtained. the random samples from the entire lot. The sublet method has one big advantage, espe- The following essential items should be cially when testing during production, in that considered in a quality-control plan: the time between testing is spaced somewhat; Lot size. when taking random samples from the lot, Random sampling. all tests might occur within a short time. Test tolerance. The sublet method is recommended when Penalty system. taking random samples. It is also recom- mended that all tests be conducted on Lot Size samples obtained from in-place material. By There are two methods of defining a lot size conducting tests in this manner, obtaining (unit of work). A lot size may be defined as an additional samples for testing would not be operational time period or as a quantity of a problem. production. One advantage that the quantity- of-production method has over the Test Tolerance operational-time-period method is that the A specification tolerance for test results engineering construction unit will probably should be developed for various tests with

Soil Compaction 8-22 FM 5-410

consideration given to a tolerance that could Test every 50 linear feet. be met in the field and a tolerance narrow Remove all oversized materials. enough so that the quality of the finished Remove any pockets of organic or product is satisfactory. For instance, the unsuitable soil material. specifications for a base course would usually Increase the distance between tests state that the material must be compacted to as construction progresses, if initial at least 100 percent CE 55 maximum density. checks are satisfactory. However, because of natural variation in material, the 100 percent requirement cannot CORRECTIVE ACTIONS always be met. Field data indicates that the When the density and/or moisture of a soil average density is 95 percent and the stand- does not meet specifications, corrective action ard deviation is 3.5. Therefore, it appears that must be taken. The appropriate corrective the specification should require 95 percent action depends on the specific problem situa- density and a standard deviation of 3.5, al- tion. There are four fundamental problem though there is a good possibility that the situations: material will further densify under traffic. Overcompaction. Undercompaction. Penalty System Too wet. After the project is completed, the job Too dry. should be rated based on the results of the statistical quality-control plan for that It is possible to have a situation where one project. A satisfactory job, meeting all of the or more of these problems occur at the same specification tolerances, should be considered time, such as when the soil is too dry and also 100 percent satisfactory. On the other hand, under compacted. The specification block that those jobs that are not 100 percent satisfac- was plotted on the moisture density curve tory should be rated as such. Any job that is (CE 55) is an excellent tool for determining if completely unsatisfactory should be removed a problem exists and what the problem is. and reconstructed satisfactorily. Overcompaction THEATER-OF-OPERATIONS Overcompaction occurs when the material QUALITY CONTROL is densified in excess of the specified density In the theater of operations, quality control range. An overcompacted material may be is usually simplified to a set pattern. This is stronger than required, which indicates— not as reliable as statistical testing but is ade- quate for the temporary nature of Wasted construction effort (but not theater-of-operations construction. There is requiring corrective action to the mate- no way to ensure that all areas of a project are rial). checked; however, guidelines for planning Sheared material (which no longer quality control are as follows: meets the design CBR criteria). Use a “test strip” to determine the ap- In the latter case, scarify the overcompacted proximate number of passes needed lift and recompact to the specified density. to attain proper densities. Laboratory analysis of overcompacted soils Test every lift as soon as compaction (to include CBR analysis) is required before a is completed. corrective action decision can be made. Test every roller lane. Test obvious weak spots. Test roads and airfields every 250 Undercompaction linear feet, staggering tests about the Undercompaction may indicate— centerline. A missed roller pass. Test parking lots and storage areas A change in . every 250 square yards. Insufficient roller weight.

Soil Compaction 8-23 FM 5-410

A change in operating frequency or Aerate. amplitude (if vibratory rollers are in use). Retest the moisture content. A defective roller drum. Recompact, if moisture content is The use of an improper type of com- within the specified range. paction equipment. Retest for both moisture and density.

Corrective action is based on a sequential ap- Too Dry proach. Initially, apply additional compactive effort to the problem area. If undercompact- Soils that are too dry when compacted do not ing is a frequent problem or develops a achieve the specified degree of densification as frequent pattern, look beyond a missed roller do properly moistened soils. Corrective action pass as the cause of the problem. for a soil compacted too dry is to- Scarify. Too Wet Add water. Soils that are too wet when compacted are Mix thoroughly. susceptible to shearing and strength loss, Retest the moisture content. Corrective action for a soil compacted too wet Recompact, if moisture content is is to— within the specified range. Scarify. Retest for both moisture and density.

Soil Compaction 8-24