Central and Western District Council (2012-2015) 6th Meeting of Food, Environment, Hygiene & Works Committee Drainage improvement in Central and Western District Progress Report

Commencement Anticipated Date Any Temporary Traffic Intake Location Works Progress Remarks Date of Completion Arrangement (Yes/ No)

Kennedy Road opposite to The Construction of intake structure substantially completed. W3 04.2010 Mid 2012 No Hongkong Electric Center Reinstatement works in progress.

Bowen Road near Borrett B2 09.2010 Mid 2012 Works completed. No Mansions

MA14 Magazine Gap Road 05.2010 Mid 2012 Works completed. No

MA15 Magazine Gap Road 03.2010 Mid 2012 Works completed. No

Magazine Gap Road near its Construction of intake structure substantially completed. MA17 04.2010 Mid 2012 Yes Junction with May Road Reinstatement works in progress.

Construction of intake structure substantially completed. M3 May Road 02.2010 Mid 2012 Yes Reinstatement works in progress.

TP789 Tregunter Path near Tavistock 11.2009 Mid 2012 Works completed. No

TP5 Tregunter Path near Aigburth 01.2010 Mid 2012 Works completed. No

TP4 Tregunter Path 10.2009 Mid 2012 Works completed. No

Construction of intake structure substantially completed. W5 Glenealy near Raimondi College 12.2009 Mid 2012 Yes Reinstatement works to commence. Additional time spent for the unforeseeable difficult Conduit Road beside Mid-levels CR1 06.2010 End 2012 Construction of dropshaft and intake structure in progress. Yes underground condition encountered during construction of Escalator intake Additional time spent for the unforeseeable difficult Robinson Road Junction with RR1 10.2009 End 2012 Construction of intake structure in progress. Yes underground condition encountered during construction of Castle Road intake Construction of intake structure substantially completed. W8 Breezy Path 03.2010 Mid 2012 Yes Reinstatement works in progress.

At the Junction of Robinson Additional time spent for the unforeseeable difficult P5 Road, Kotewall Road and 12.2009 End 2012 Construction of dropshaft in progress. Yes underground condition encountered during construction of Oaklands Avenue intake At the Junction of Kotewall Road Construction of intake structure substantially completed. W10 10.2009 Mid 2012 Yes and Conduit Road Reinstatement works in progress. University Drive next to Graduate HKU1 09.2009 Early 2012 Works completed. No House

SM1 Smithfield 01.2009 Mid 2011 Works completed. No

Construction of intake structure substantially completed. PFLR1 Pokfulam Road Playground 07.2009 Mid 2012 No Reinstatement works in progress.

Remark: Please refer to the attached drawing for the intake locations.

Central and Western District Council (2012‐2015) 6th Meeting of Food, Environment, Hygiene & Works Committee (18‐Oct‐2012) Drainage improvement in Central and Western District Lower Catchment Works Progress Report (From 04‐Jul‐2012 to 29‐Sep‐2012)

I. Works completed since the last report: Comm. Expect Actual Drain no. Location Remarks Date Comp. Comp. Investigation works were completed and the road pavement was reinstated. near Tim Wa S11(2) 09.2011 03.2013 07.2012 Revised design is required due to congested underground facilities, and is pending negotiation with relevant Avenue authorities. Jubilee Street (Between Drainage works on Jubilee Street except construction of a manhole at j/w Connaught Rd. Cental (AD‐5(2)) were AD‐5(1)* Connaught Rd. Central & Des 12.2009 07.2012 07.2012 completed. Pavement was reinstated and opened to traffic. Voeux Rd. Central) Works are divided into 3 stages. The first stage was completed. Works under Stage 2 were obstructed by congested CD‐5A* Ko Shing Street 09.2011 12.2012 08.2012 underground utilities and the original design will be revised to cope with the site condition. The pavement was temporarily reinstated. The works will be commenced when the revised design is finalized.

II. Works in progress, location shown as drawing DC0719/2: Comm. Expect Construction Drain no. Location Duration TTM Remarks Date Comp. Method 09.2009‐ Trenchless and Theatre Lane near Des Voeux C10‐3B(2)* 02.2010 32 11.2012 Open Trench Valid Works in progress as scheduled. Rd. Central 08.2010 (Night Works) Queen’s Rd. Central j/w Trenchless Works obstructed by utilities. Liaison with Utility Undertakings for diversion in C10‐2* 08.2011 18 02.2013 Valid Theatre Lane (Night Works) progress. Expected completion date postponed to Feb 2013. Trenchless and Jubilee St. j/w Connaught Rd. Open Trench AD‐5(2)* 07.2011 15 10.2012 Valid Works in progress as scheduled. Central (Non‐peak hour and Night Works) 05.2010‐ Excavation of inspection pits in progress and will be completed in November Des Voeux Rd. West near Hill C3‐1A* 07.2011 28 11.2012 Trenchless Valid 2012. Final design of drainage works will be carried out based on information Rd. 09.2010 from inspection pit. The programme of the detailed works will be submitted later. Lining Works Connaught Rd. West near The remaining works will be carried out by night works, detailed arrangement of AS2* 03.2011 21 01.2013 (Trenchless) Required Eastern St. which being discussed with traffic authorities and EPD. (Night Works) Bonham Strand West near Des Water mains obstructing the designed works have been diverted. Further BSW* 09.2011 19 04.2013 Trenchless Valid Voeux Rd. West excavation is in progress for diversion of electricity cables.

Approval has been obtained from HYD and LCSD to commence excavation of Footpath near inspection pits in October 2012 and will be completed in December 2012. Final E3* 10.2011 15 12.2012 Open Trench Valid Bus Terminal design of drainage works will be carried out based on information from inspection pit. The programme of the detailed works will be submitted later. The works are divided into phases. Temporary traffic arrangement for the Queen’s Rd. West (Bet. forthcoming stage has been approved by traffic authorities and agreed by the S4* 02.2012 12 02.2013 Open Trench Valid Belcher's St. and Hill Rd) affected hotel. The works will be commenced in October 2012, and anticipated to be completed by Feb 2013.

III. Works to be commence in forthcoming 6 months, location shown as drawing DC0719/2: Comm. Expect Construction Drain no. Location Duration TTM Remarks Date Comp. Method The temporary traffic arrangement has been approved by traffic authorities and C38‐1* Ka Wai Man Road 10.2012 6 06.2013 Open Trench Valid reported to the District Councilor. Consultation with the affected locals will be carried out prior to commencement of site works in October 2012. Bonham Strand (Bet. Wing Lok Site works are being reviewed based on result of public consultation. We will seek E1(2)* 10.2012 7 05.2013 Open Trench Required St. & Cleverly St.) approval by traffic authorities for temporary traffic arrangement in due course. Connaught Rd. Central (near Open Trench Investigation works have been completed, based on which the design is revised S7* 10.2012 7 05.2013 Valid Man Wa Lane & Rumsey St.) (Night Works) and being negotiated with the relevant authorities. Des Voeux Rd. Central j/w Open Trench Night works only. Detailed arrangement is being negotiated with EPD and E2* 10.2012 7 05.2013 Valid Hillier St. (Night Works) relevant traffic authorities including buses and tram. Belcher’s St (bet. Cadogan St. & The remaining works will be carried out by night works, detailed arrangement of AS1(1)* 11.2012 7 06.2013 Lining Works Valid Sands St.) which being discussed with EPD. SW3* & Wing Lok St. (Morrison St & Open Trench Night works only. Detailed arrangement is being negotiated with EPD and 11.2012 6 05.2013 Required CD6(3)* Cleverly St.) (Night Works) relevant traffic authorities. CD4* & Des Voeux Rd. West (bet. Site investigation works are scheduled for commencement in November 2012 and 11.2012 6 05.2013 Trenchless Valid C4‐2* Water St. & Chiu Kwong St) anticipated to last for a month. Temporary traffic arrangement is being negotiated with District Councilor and CD1* Cadogan St. j/w Victoria Rd. 12.2012 6 06.2013 Open Trench Required traffic authorities. Site works will commence after water works nearby are completed. Queen’s Rd. West (Bet. Centre AD‐1* 11.2012 6 05.2013 Open Trench Valid To negotiate with WSD project for works in common trench. St. & Eastern St.) Des Voeux Rd. West (bet. Sung Pending further negotiation with Hong Kong and China Gas Company Ltd. for D2(2)* 12.2012 4 04.2013 Open Trench Required Hing Lane & Mui Fong St.) diversion of gas main. Pedder St. j/w Connaught Rd. Traffic impact assessment is being implemented. Detailed arrangement is to be D9* 12.2012 11 11.2013 Open Trench Required Central further negotiated with traffic authorities.

CD‐5B Ko Shing Street 11.2012 6 05.2012 Open Trench Required Temporary traffic arrangement is pending approval by traffic authorities.

Queen’s Rd. Central near Revised design is required due to congested underground facilities, and is pending AD‐5A* 01.2013 10 11.2013 Open Trench Valid Jubilee St negotiation with relevant authorities. Des Voeux Rd. Central (bet. Open Trench Revised design is required due to congested underground facilities, and is S8* 01.2013 11 12.2013 Required Wing Kut St and Queen Victoria (Night Works) pending negotiation with relevant authorities. St) Des Voeux Rd West (bet. Sai Revised design is required due to congested underground facilities found in S5(2)* 03.2013 8 11.2013 Open Trench Valid Woo Lane & Wilmer St.) inspection pits, and is pending negotiation with relevant authorities. AD‐2A* & Excavation of Inspection pits completed. Drainage works to be carried in Centre Street 12.2012 9 09.2013 Trenchless Valid AD‐2B* trenchless method.

* Already reported in last meeting。 DSD Project Management Division 29‐Sep‐2012