Southam Joint Parish Council
May 2019
1MC07-CEK-SE-PRE-C003-000005 Nisha Mejer
Community Engagement Manager Area Central High Level Programme of Works
EWC ECOLOGY AND ARCHAEOLOGY MITIGATIONS Key
AWARD AND DESIGN EWC CIVILS CONSTRUCTION START OF CONSTRUCTION
MWCC SURFACE ROUTE (EARTHWORKS)
EARLY CONTRACTOR INVOLVEMENT MWCC SURFACE ROUTE (VIADUCTS & BRIDGES)
UTILITY WORKS
RAIL INFRASTRUCTURE INSTALLATION & TESTING
2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 Ongoing works – archaeology surveys
Archaeological surveys along the route.
Trial trenching, followed by full investigations, where necessary. Ongoing works – other surveys
Ground investigation Ground penetrating radar Topographical
Invasive plant species Hydraulic Environmental surveys Ongoing sites Southern Warwickshire Environmental mitigation works around Creation of new haul roads from A429 to Cubbington, Kenilworth & Burton Green Burton Green
Compound preparation
Diversion of oil fuel pipe Wills Pasture – creating access road for MWCC
Utility provision for Tunnel boring machine Heave trial Ongoing sites North Warwickshire Ecological works around Curdworth, Water Archaelogical investigations at Middleton Orton and Coleshill and Curdworth
National Grid overhead line diversion
Ongoing ecological mitigation
Cadent site Demolition of IAC compound for gas building and vegetation diversion clearance Local engagement activity
Jeremy Wright MP construction forum – expecting another in June/July
Stratford DC meeting
HS2/EK – Priors Hardwick and Wormleighton Parish Councils
AGMs – including Boddington
HS2 Growing Spaces project – Kenilworth and Cubbington
Fusion engaging with Wills Pasture residents
Southam school drop in, Southam/Feldon Community Forum
Harbury businesses
Drop ins – Stoneleigh, Weston under Wetherley, Kenilworth, Ufton etc https://hs2inwarwicks.commonplace.is/ CEF/BLEF funding
Ladbroke Village Hall - £65,000
Southam Bowling Club - £18,775
Long Itchington Parish Council - £74,500 – play aera
Kenilworth Parish Council - £74,500 – BLEF Enabling Works Update
Carley Richards Area Central - Fusion Wills Pasture Update Scheme Design • Currently seeking Council approval
Initial area works – Clearance of vegetation • Set up temporary welfare units off Wills Pasture junction • Fencing
Start construction works junction widening improvements – • Construction works scheduled. • Traffic Lights set up Wills Pasture (Banbury road A423)
Wills Pasture Road - potential closure • Currently being reviewed and considered Enabling Works Update
Ashley Jackson Area North - LM Fosse Way A46 compound compound and temporary diversion of A46
Welsh Road compound
Utility provision for Tunnel boring machine Long Itchington Wood – Stage 2
x Welsh Road Contains Contains Ordnance Survey data ©Crown copyrightand database right 2017 y Bascote Road
w B4452 Ufton Road B4452B4552 v B4552 Deppers Bridge Road
B4451 Station Road Part of utility installation work with u David Wilson Homes 1 metre Twin ducts for power cables
Depth of trench 2 spare ducts for future utilities
1.50 metres Water pipe (Welsh Road only) Archaeological site
Environmental Environmental mitigation site mitigation site Main Works Update
Simon Matthews Interface Manager Heave Trial
• Monitoring boreholes in place • Earthworks preparation about to start • Bulk earthworks start late June • Site visits being organised over the summer • Target completion mid October Earthworks Main Works Update
1. Local Traffic Plans being developed
2. Land Possessions from Q3/2019 for enabling works – archaeology, ecology
and site clearance towards the end of the year
3. Design development ongoing
4. Planning applications due from Q1/2020
5. August 2020 access to start main works Main Works Update
Andy de Bell Balfour Beatty Vinci Contents
1. Long Itchington Tunnelling Compound 2. Tunnel Boring Machine
Balfour Beatty Vinci charity bike ride from Windsor Castle to the Palace of Versailles - 14th June https://uk.virginmoneygiving.com/Team/BalfourBeattyVinciWheelers Raising money for St. Basils + Autism West Midlands + Birmingham Solihull Women’s Aid Long Itchington Tunnel - Compound a) Compound layout being finalised b) Phased work to create the Compound c) Tunnel Boring Machine delivered through Ufton via Ridgway Lane d) Assembled and commissioned at site
• Communications to date? • What would you like from us? Tunnel Boring Machine
• Order to finalise as part of Notice to Proceed process • Delivery route finalisation • TBM will travel through Ufton • HS2 looking at church survey • Results dictate next steps • TBM engagements?