Southam Joint Parish Council

May 2019

1MC07-CEK-SE-PRE-C003-000005 Nisha Mejer

Community Engagement Manager Area Central High Level Programme of Works

EWC ECOLOGY AND ARCHAEOLOGY MITIGATIONS Key

AWARD AND DESIGN EWC CIVILS CONSTRUCTION START OF CONSTRUCTION

MWCC SURFACE ROUTE (EARTHWORKS)

EARLY CONTRACTOR INVOLVEMENT MWCC SURFACE ROUTE (VIADUCTS & BRIDGES)

UTILITY WORKS

RAIL INFRASTRUCTURE INSTALLATION & TESTING

2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 Ongoing works – archaeology surveys

Archaeological surveys along the route.

Trial trenching, followed by full investigations, where necessary. Ongoing works – other surveys

Ground investigation Ground penetrating radar Topographical

Invasive plant species Hydraulic Environmental surveys Ongoing sites Southern Environmental mitigation works around Creation of new haul roads from A429 to , & Burton Green Burton Green

Compound preparation

Diversion of oil fuel pipe Wills Pasture – creating access road for MWCC

Utility provision for Tunnel boring machine Heave trial Ongoing sites Ecological works around Curdworth, Water Archaelogical investigations at Middleton Orton and Coleshill and Curdworth

National Grid overhead line diversion

Ongoing ecological mitigation

Cadent site Demolition of IAC compound for gas building and vegetation diversion clearance Local engagement activity

Jeremy Wright MP construction forum – expecting another in June/July

Stratford DC meeting

HS2/EK – and Wormleighton Parish Councils

AGMs – including Boddington

HS2 Growing Spaces project – Kenilworth and Cubbington

Fusion engaging with Wills Pasture residents

Southam school drop in, Southam/Feldon Community Forum

Harbury businesses

Drop ins – Stoneleigh, Weston under Wetherley, Kenilworth, etc https://hs2inwarwicks.commonplace.is/ CEF/BLEF funding

Ladbroke Village Hall - £65,000

Southam Bowling Club - £18,775

Long Itchington Parish Council - £74,500 – play aera

Kenilworth Parish Council - £74,500 – BLEF Enabling Works Update

Carley Richards Area Central - Fusion Wills Pasture Update Scheme Design • Currently seeking Council approval

Initial area works – Clearance of vegetation • Set up temporary welfare units off Wills Pasture junction • Fencing

Start construction works junction widening improvements – • Construction works scheduled. • Traffic Lights set up Wills Pasture (Banbury road A423)

Wills Pasture Road - potential closure • Currently being reviewed and considered Enabling Works Update

Ashley Jackson Area North - LM Fosse Way A46 compound compound and temporary diversion of A46

Welsh Road compound

Utility provision for Tunnel boring machine Wood – Stage 2

x Welsh Road Contains Contains Ordnance Survey data ©Crown copyrightand database right 2017 y Road

w B4452 Ufton Road B4452B4552 v B4552 Deppers Bridge Road

B4451 Station Road Part of utility installation work with u David Wilson Homes 1 metre Twin ducts for power cables

Depth of trench 2 spare ducts for future utilities

1.50 metres Water pipe (Welsh Road only) Archaeological site

Environmental Environmental mitigation site mitigation site Main Works Update

Simon Matthews Interface Manager Heave Trial

• Monitoring boreholes in place • Earthworks preparation about to start • Bulk earthworks start late June • Site visits being organised over the summer • Target completion mid October Earthworks Main Works Update

1. Local Traffic Plans being developed

2. Land Possessions from Q3/2019 for enabling works – archaeology, ecology

and site clearance towards the end of the year

3. Design development ongoing

4. Planning applications due from Q1/2020

5. August 2020 access to start main works Main Works Update

Andy de Bell Balfour Beatty Vinci Contents

1. Long Itchington Tunnelling Compound 2. Tunnel Boring Machine

Balfour Beatty Vinci charity bike ride from Windsor Castle to the Palace of Versailles - 14th June https://uk.virginmoneygiving.com/Team/BalfourBeattyVinciWheelers Raising money for St. Basils + Autism + Birmingham Solihull Women’s Aid Long Itchington Tunnel - Compound a) Compound layout being finalised b) Phased work to create the Compound c) Tunnel Boring Machine delivered through Ufton via Ridgway Lane d) Assembled and commissioned at site

• Communications to date? • What would you like from us? Tunnel Boring Machine

• Order to finalise as part of Notice to Proceed process • Delivery route finalisation • TBM will travel through Ufton • HS2 looking at church survey • Results dictate next steps • TBM engagements?