Green Initiatives

1. Towards energy saving at Mahabubnagar station 5 kWp solar power panels were installed with the cost `2.4 lakh and 30 kWp Solar Panels are installed at Station 2. All stations in Parliamentary Constituency have been completely provided with LED lighting.

Passenger Train Services Mahbubnagar parliamentary constituency Details of New Trains/ Special Trains/ Provision of Stoppages/ Extension/ Increase in the frequency of Trains in Mahbubnagar Parliamentary Constituency Jurisdiction. Shri Narendra Modi Hon’ble Prime Minister New Trains introduction 1. Tr.No.77622/77623 Mahabubnagar–Jaklair–Mahabubnagar Bi-Weekly DEMU passenger has been introduced. Running of Special trains RAIL DEVELOPMENTAL WORKS 1. Krishna to Guntakal 12 special trains. Mahbubnagar Parliamentary Constituency Jurisdiction 2. Krishna to Tirupati 11 special trains. 3. Krishna to 12 special trains. 4. Mahabubnagar to Bolarum 1 special train S. (Total 36 special Trains) South Central Railway Provision of Stoppage serving the entire state of 1. Tr.No.16353/16354 Kacheguda–Nagercoil–Kacheguda Weekly Express stoppage is given at , major portion Mahabubnagar of and 2. Tr.No.17021/17022 –Vasco-da-Gama–Hyderabad Weekly Express stoppage is given at considerable portion of , Mahabubnagar & SOUTH CENTRAL Karnataka, Maharastra 3. Tr.No.77622/77623 Mahabubnagar–Jaklair–Mahabubnagar bi-Weekly DEMU passenger states and small parts stoppage is given at Manyamkondda, , Marikel RAILWAY 4. Tr.No.17615/17616 Kacheguda – Madurai at Shadnagar of Tamilnadu and 5. Tr. No. 17652/17651 Kacheguda – Chengalpattu at Shadnagar Madhya Pradesh. 6. Tr. No. 12769/12770 Tirupati – Secunderabad at Shadnagar Mahabubnagar Extension of Trains Parliamentary 1. Tr. No. 11303/11304 Kolhapur – Hyderabad Express upto Constituency falls under 2. Tr. No. 12785/12786 Kacheguda – Bengaluru Telangana State. Express upto Mysuru Entire Railway Network of this constituency is being served by South Central Railway. ASSEMBLY SEGMENTS Road Over / Under Bridges With a view to strengthen safety at Level Crossing gates and to avoid untoward incidents and also to provide seamless journey to Kodangal road traffic, the following Road under /over Bridges (RuB/RoB) are constructed / proposed for construction under Mahabubnagar Parliamentary constituency. Mahbubnagar Road over Bridges (RoB) Jadcherla 1. Construction of RoB in lieu of LC No.73 between Devarakadra and Kaukuntla at sanctioned cost of `27.66 Devarkadra crore is in progress. 2. Proposed for construction of RoB in lieu of LC No. 60 between Mahabubnagar and Manyamkonda with Makthal an estimated cost of `66.37 crore Shadnagar Road under Bridge (RuB) 1. Construction of RuB in lieu of Manned LC No. 56 between Mahabubnagar and Divitipalli stations in Secunderabad – Dhone Section with an estimated cost of `2.41 crore is completed 2. Construction of RUB in lieu of Manned LC No. 101 E between Gadwal and Poodoor stations in RAIL DEVELOPMENTAL WORKS Secunderabad – Dhone Section by open cut method with an estimated cost of `2.40 crore is completed Mahbubnagar Parliamentary Constituency Jurisdiction 3. Construction of RUB in lieu of Manned LC No. 115 between Itikyala–Manopad in Secunderabad – Dhone Section by open cut method with an estimated cost of `2.47 crore is completed 4. All Unmanned Level Crossings in Mahabubnagar Parliamentary jurisdiction are eliminated through Infrastructural Development construction of RuBs/LHS/Direct closure

New Railway Lines Doubling of Railway Lines Passenger Amenities Station Amenity Amount Status 1. Devarkadra–Jaklair section for a distance It is proposed for Doubling of Secunderabad – Mahabubnagar 3Water Vending --- Installed of 28.5 kms is Completed as a part of Mahbubnagar section for the distance of 85 Kms with Machines Munirabad–Mahbubnagar New line at a cost of an estimated cost of `728.10 crore Mahabubnagar TIB/CIB `14.14 Lakh Installed `279.30 crore (SCR Portion Devarakadra-Krishna ) Provision of Passenger Amenities Mahabubnagar 20 CCTVs `46 Lakh Proposed 2. Construction of Jaklair–Krishna new Railway line Electrification of Railway Lines and facilities, and its improvements Shadnagar TIB/CIB `1.693 crore In Progress for the distance of 36.2 kms as a part of It is proposed for electrification of Manmad – Dhone at Railway Stations is one of the & Jadcherla Munirabad– Mahabubnagar New line with an section for the distance of 868 Kms with an estimated most important aspect Railway Gadwal 2 Lifts `1 crore Proposed estimated cost of `354.76 crore (SCR Portion cost of `1031 crore Mahabubnagar 2 ATVMs `6 Lakh Installed Devarakadra–Krishna) is in progress Services. Jadcherla 1 ATVM `1.5 Lakh Installed Shadnagar 1 ATVM `1.5 Lakh Installed Mahabubnagar Concrete Apron `1.78 crore Provided New Station `90 Lakh Proposed Building Divitipalli Toilets `0.10 crore In Progress Safety – The First Priority ` Proposed FOBs Mahabubnagar Toilets 0.05 crore In Progress ` Safety is the priority on SCR, to Manyamkonda Platform work 0.50 crore Proposed ` ensure safety of the Rail users, Foot Station Cost in ` Crore Mahabubnagar Platform work 0.80 crore Proposed Chegunta 1.18 Town over Bridges (FoBs) are constructed / Mahabubnagar Circulating area `1.42 crore Proposed proposed for construction at various Balanagar 1.24 Mahabubnagar Platform Shelter `0.14 core In Progress stations/ locations in Mahabubnagar Divitipalli 0.98 Krishna Station Building `1.99 crore In Progress Parliamentary Constituency Mahabubnagar 0.85 ` Jurisdiction. Krishna Station Building 6.20 crore Proposed 6 Stations Wi-Fi `9 lakh Provided