Quarterly Report /Q1 September FY20

• Acquisition of Atlantic Gold completed 1 • Q1 FY20 production of 87,569 ounces at AISC0F of A$1,421 per ounce • Production at Gwalia impacted by ventilation constraints and lower grade • Significant exploration results informing Simberi sulphide project

Executive Summary Operations Health & Safety • Consolidated gold production for the calendar quarter • The Total Recordable Injury Frequency Rate (TRIFR, 12- ended 30 September 2019 (Q1 Sep FY20) was 87,569 month moving average) is stable at 5.0 at the end of Q1 ounces (Q4 June FY19: 86,197 ounces). This includes 4,362 September FY20 (5.0 at end Q4 June FY19). ounces produced by Atlantic Gold prior to St Barbara’s acquisition on 19 July 2019. Gwalia Extension Project • • Consolidated All-In Sustaining Cost1 (AISC) for calendar Q1 The Gwalia Extension Project (GEP) remains on schedule, September FY20 was A$1,421 per ounce (Q4 June FY19: with the overall project budget of $112 million unchanged 2 (details page 6). A$1,219 per ounce)1F . The average realised gold price for Q1 September FY20 was A$1,948 per ounce (Q4 June FY19: • Commissioning activities relating to the Paste Aggregate Fill A$1,848 per ounce). (PAF) project continued during the quarter. Drilling of the • Gwalia () gold production for Q1 September FY20 pilot hole for the final raise bore shaft commenced during was 38,153 ounces (Q4 June FY19: 49,966 ounces) at AISC the quarter. Significant progress was achieved on of A$1,559 per ounce (Q4 June FY19: A$1,230 per ounce). installation of infrastructure associated with the vent fans, Mined grade for Q1 September FY20 was 7.8 g/t Au (Q4 cooling plant and power station expansion. Three of the June FY19 10.0 g/t Au) with 164 kt milled (Q4 June FY19: four 5-metre diameter ventilation shafts underpinning GEP 161 kt). In addition to the impact of lower production on are complete. Completion of the final shaft, along with AISC, capital mine development in Q1 September FY20 was completion and commissioning of surface infrastructure, higher than previous quarters. will enable the shafts and surface ventilation infrastructure to be commissioned from Q2 December FY20 with • Simberi (PNG) gold production for Q1 September FY20 was operation to commence in Q3 March FY20. The investment 27,061 ounces (Q4 June FY19: 36,231 ounces) at AISC of in GEP has been fundamental to extending Gwalia’s mine A$1,603 per ounce (Q4 June FY19: A$1,203 per ounce). life to 2031. Lower production in Q1 September FY20 was due primarily to lower milled grade of 1.19 g/t Au (Q4 June FY19: 1.68 g/t Exploration Au). The Simberi mining lease (ML136) has been extended • Leonora - Gwalia Deeps Extension: The Deeps drilling to December 2028. program progressed with the completion of a new parent • Atlantic Gold (Canada) gold production for Q1 September hole, GWDD25, targeting extensions to the south at an FY20 was 22,355 ounces (Q4 June FY19: 22,948 ounces) at interval between 2,200 and 2,400 metres below surface AISC of A$970 per ounce. Attributable production to St (mbs). Analytical results for this drilling are pending. Barbara post the acquisition on 19 July 2019 was 17,993 • (PNG): The sulphide drilling program ounces at AISC of A$964 per ounce. beneath the Sorowar pit has been completed, with the • Integration is well underway, with the current Atlantic Gold latest drilling results confirming significant additional operating team and key executives retained. Further details sulphide and oxide mineralisation is present. An updated are provided on page 9. Reserves and Resources statement is planned for Q3 March

For personal use only use personal For FY20. Studies on pit design, processing and logistics options are progressing.

1 Non IFRS measure, refer appendix. 2 AISC attributable to the Company from 19 July 2019 for Q1 September FY20 was $1,445/oz Investor Relations Mr David Cotterell Manager Investor Relations +61 3 8660 1959 ASX: SBM Media Relations Mr Tim Duncan GRA Cosway with Hintons +61 408 441 122 ADR: STBMY St Barbara Limited Level 10, 432 St Kilda Road, Melbourne VIC 3004 T +61 3 8660 1900 F +61 3 8660 1999 ACN 009 165 066 Locked Bag 9, Collins Street East, Melbourne VIC 8003 W www.stbarbara.com.au

• Significant results relating to 64 additional holes are • Debt of A$112 million (C$100 million) at 30 September reported in the exploration section and ancillary Table 8, 2019. In addition St Barbara has an undrawn A$200 million including (all intercepts downhole): three year syndicated revolving debt facility.

2 o 11 m @ 8.62 g/t Au from 21 m (110SRDH002) • The Company generated an operational cash contribution3F in Q1 September FY20 of A$43 million (Q4 Jun FY19: A$58 25 m @ 3.09 g/t Au from 136 m (150SRDH045) o million). • Cochrane Hill (Canada): Assay results from Q4 June FY19 infill drilling were received during Q1 September FY20, Outlook confirming the deposit is open at depth and to the east. • As announced on 18 October 2019, on completion of the Significant intercepts are reported in the exploration regular quarterly operational reforecast at Gwalia, the section and ancillary Table 10, including (all intercepts near-term production expectations for Gwalia were downhole): revised. While nearing completion, the remaining Gwalia CH-19-344: Extension Project (GEP) construction and raiseboring program is competing for constrained ventilation with 25 m @ 2.49 g/t Au from 220 m o scheduled production and development activities. CH-19-345: • The constrained ventilation and sequential mining schedule o 22 m @ 3.05 g/t Au from 286 m means any interruption to stoping, including from equipment failure causing a delay in stope development, 2 m @ 9.53 g/t Au from 314 m o cannot be recovered until after GEP is completed and new • Fifteen Mile Stream - Seloam Brook (Canada): Preliminary working faces have been developed. assay results were received from drilling the westward • Guidance for FY20 was revised on 18 October 2019 and is extension of the proposed Hudson and Plenty pits, with summarised as follows: significant intercepts reported in the exploration section and ancillary Table 12, including (all intercepts downhole) o Forecast Gwalia gold production between 175,000 and 190,000 ounces (previously 200,000 to 210,000 ounces) SB-19-031: at an AISC of between A$1,390 and A$1,450 per ounce o 4 m @ 9.73 g/t Au from 81 m (previously A$1,230 to A$1,290 per ounce). o 2 m @ 1.71 g/t Au from 149 m Sustaining capex of between A$60 million to A$65 million (previously A$55 to A$65 million), plus growth 6 m @ 2.22 g/t Au from 174 m o capex of between A$32 million to A$38 million • The exploration section, commencing on page 11, includes (previously A$30 to A$35 million). Gwalia sustaining progress on the following projects: capex includes increased capital towards development activities to establish dual declines and increasing the Pinjin (Australia) o number of mining fronts. This capex is reflected in the o Lake Wells (Australia) AISC guidance. o Back Creek (Australia) Contemporary detailed mine planning has prioritised development over production for FY20. There is Horn Island (Australia) o ongoing work to further optimise operations at Gwalia o Beaver Dam (Canada) in FY20 as the benefits of GEP are realised in the second half of the financial year. o Moose River Corridor Projects (Canada) Forecast Simberi gold production is unchanged at o South-west Nova Scotia (Canada) o between 110,000 and 125,000 ounces at an AISC of Finance (unaudited) between A$1,285 and A$1,450 per ounce, with sustaining capex of between A$4 and A$5 million, plus • Total cash at bank and term deposits at 30 September 2019 growth capex of between A$3 to A$4 million. 1 was A$762F million (30 Jun 2019: A$890 million), after

For personal use only use personal For acquisition of Atlantic Gold of $780 million, dividend o Forecast Atlantic gold production, first announced on payments of $19 million, exploration expense of $13 18 October 2019, is between 95,000 and 105,000 million, growth capex of $14 million, income tax payments ounces at an AISC of between A$900 and A$955 per of $8 million and movement in working capital of $8 million. ounce, with sustaining capex of between A$13 and

1 Financial information unaudited. Balance comprises $66 M cash, 2 Non-IFRS measure, see cash movements table later in this quarterly $10 M term deposits and excludes $2 M restricted cash. report. Corresponds to Operational Cash Flow less sustaining capital, excludes growth capital of A$14 M (Q4 Jun: $20 M).

St Barbara Limited Quarterly Report / Q1 September FY20 Page 2 of 22

A$17 million. Growth capex will be advised in Q2 Consolidated Gold Production December FY20. For comparative purposes, noting that gold production o Forecast exploration expenditure has been revised to from Atlantic Gold is attributable to St Barbara from 19 July between A$31 and A$41 million (previously A$20 to 2019, the below shows full quarter production and AISC A$28 million) and includes Atlantic Gold’s exploration plus historic theoretical combined quarterly production forecast of between A$11 and A$13 million (details on from St Barbara and Atlantic Gold. page 11). Quarterly AISC (A$/oz) 1,421 Bob Vassie 1,053 1,175 Managing Director and CEO 1,073 21 October 2019 868

Quarterly briefing and audio webcast Combined Quarterly Gold Production Bob Vassie, Managing Director & CEO, will brief analysts and (koz) investors on the Q1 September FY20 Quarterly Report at 11:00 126 am Australian Eastern Daylight Time (UTC + 11 hours) on 112 108 109 Monday 21 October 2019. Participation on the conference call 28 is by personal invitation only. 23 20 23 88 A live audio webcast will be available on the website at 36 22 www.stbarbara.com.au/investors/webcast/ or by clicking here. 36 34 36 The audio webcast is ‘listen only’ and does not enable 27 questions. The audio webcast will subsequently be made available on the website. 63 53 54 50 38

FY19 FY19 FY19 FY19 FY20 Q1 Sep Q2 Dec Q3 Mar Q4 Jun Q1 Sep Gwalia Simberi Atlantic Total

Figures displayed to nearest thousand ounces. Reported ounces in associated table.

FY20 Production Indicative Quarterly Guidance Mid-point Profile

28% 25% 25% 22%

FY20 FY20 FY20 FY20 Q1 Sep Q2 Dec Q3 Mar Q4 Jun

Actual Indicative % of annual production (koz) For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Page 3 of 22

St Barbara Gold Production & Guidance Production Summary Q3 Mar Q4 Jun Year Q1 Sep Q1 Sep Guidance 1 Consolidated FY19 FY19 FY 19 FY20 FY20 FY204F St Barbara’s financial Qtr to Qtr to Year to Qtr to Qtr to Year to year is 1 July to 30 June 31 Mar 2019 30 Jun 2019 30 June 2019 30 Sep 2019 30 Sep 2019 30 June 2020 AG full quarter AG SBM Production attributable Gwalia oz 54,261 49,966 220,169 38,153 38,153 175 to 190 koz (prev. 200 to 210 koz) Simberi oz 34,097 36,231 142,177 27,061 27,061 110 to 125 koz Atlantic oz 19,612 22,948 92,639 22,355 17,993 95 to 105 koz (new) Consolidated oz 107,970 109,145 454,985 87,569 83,206 380 to 420 koz (prev. 310-335 koz ex. Atlantic) 2 Mined Grade Reserve grade5F Gwalia g/t 11.7 10.0 11.1 7.8 7.8 6.4 Simberi g/t 1.46 1.48 1.43 1.09 1.09 1.3 Atlantic g/t 0.95 0.91 0.98 0.86 0.86 1.1

Total Cash Op. Costs3

Gwalia A$/oz 713 821 746 1,124 1,124 n/a Simberi A$/oz 1,066 1,021 1,016 1,440 1,440 n/a Atlantic A$/oz 766 744 662 747 746 n/a Consolidated A$/oz 834 871 813 1,125 1,145 n/a

3 All-In Sustaining Cost6F Gwalia A$/oz 1,016 1,230 1,027 1,559 1,559 1,390 to 1,450 (prev. 1,230 to 1,290) 4 Simberi A$/oz 1,229 1,203 1,162 1,603 1,603 1,285 to 1,4507F 5 Atlantic A$/oz 957 1,010 862 970 964 900 to 9558F (new) 1,240 to 1,330 Consolidated A$/oz 1,073 1,175 1,036 1,421 1,445 (prev. 1,250 to 1,350, ex. Atlantic)

Disclaimer This report has been prepared by St Barbara Limited (“Company”). The materially from those expressed in this report. Actual results may vary material contained in this report is for information purposes only. This from the information in this report. The Company does not make, and release is not an offer or invitation for subscription or purchase of, or a this report should not be relied upon as, any representation or warranty recommendation in relation to, securities in the Company and neither as to the accuracy, or reasonableness, of such statements or this release nor anything contained in it shall form the basis of any assumptions. Investors are cautioned not to place undue reliance on contract or commitment. such statements. This report contains forward-looking statements that are subject to risk This report has been prepared by the Company based on information factors associated with exploring for, developing, mining, processing available to it, including information from third parties, and has not and the sale of gold. Forward-looking statements include those been independently verified. No representation or warranty, express or containing such words as anticipate, estimates, forecasts, indicative, implied, is made as to the fairness, accuracy or completeness of the should, will, would, expects, plans or similar expressions. Such forward- information or opinions contained in this report. looking statements are not guarantees of future performance and The Company estimates its reserves and resources in accordance with involve known and unknown risks, uncertainties, assumptions and

For personal use only use personal For the Australasian Code for Reporting of Identified Mineral Resources and other important factors, many of which are beyond the control of the Ore Reserves 2012 Edition (“JORC Code”), which governs such Company, and which could cause actual results or trends to differ disclosures by companies listed on the Australian Securities Exchange.

1 FY20 guidance released 24 July 2019 in Q4 June FY19 Quarterly Report and updated 18 October 2019 in FY20 production and cost guidance update 2 Ore Reserve grade at 30 June 2019, refer Ore Reserve and Mineral Resources Statement (released 21 August 2019) 3 Non-IFRS measure, refer Appendix 4 US$900 to US$1,015 per ounce @ AUD 0.70 5 C$810 to C$860 per ounce @ AUD 0.90 St Barbara Limited Quarterly Report / Q1 September FY20 Page 4 of 22

Gwalia, Leonora, WA Operations

• Gwalia gold production for Q1 September FY20 was 38,153 AISC (A$/oz) ounces (Q4 June FY19: 49,966 ounces). Average mined grade 1,559 1,230 for the quarter was 7.8 g/t Au (Q4 June FY19: 10.0 g/t Au). 1,081 1,016 833 • As previously reported, lower grade stoping areas were mined FY19 average $1,027/oz in Q1 September FY20 as part of Gwalia’s centre-out mining sequence. The mine sequence is also in a generally lower Mined grade grade area at the current depth, and this combined with some (g/t Au) dilution associated with overbreak on a stope on the end of a level, resulted in the lower mined grade for the quarter. 12.4 11.7 10.4 10.0 • Q1 September FY20 mined volume was 152 kt (Q4 June FY19: 7.8 156 kt), with tonnage delivered for the quarter affected by

ongoing management of competing activities (development, Reserve grade FY19 1 Reserve grade FY20 1 7.5 g/t Au 6.4 g/t Au production, projects) in a constrained ventilation Production (koz) environment whilst the GEP project is nearing completion. • The sequential nature of the Gwalia mine plan, under current 62.7 ventilation constraints that limit parallel work activities 53.3 54.3 50.0 underground, also continues to impact mining operations. 38.2 The ventilation constraints will be resolved through the completion of the GEP project in Q3 March FY20, enabling increased development and production. • The figure below shows total tonnes moved, including ore and FY19 FY19 FY19 FY19 FY20 development waste during the quarter, with material Q1 Sep Q2 Dec Q3 Mar Q4 Jun Q1 Sep movement in excess of 1 Mtpa maintained through the quarter. • Ore milled in the quarter was marginally higher at 164 kt Gwalia total material moved (kt) (Q4 June FY19: 161 kt), with recovery maintained at 98% 262 267 (Q4 June FY19: 98%). 252 260 256 19 20 32 • AISC increased to A$1,561 per ounce for Q1 September FY20 69 82 106 115 (Q4 June FY19: A$1,230 per ounce), reflecting the lower 78 mined volume and grade and higher capital mine development expenditure. 164 158 146 156 152 Outlook

FY19 FY19 FY19 FY19 FY20 • As announced on 18 October 2019, on completion of the Q1 Sep Q2 Dec Q3 Mar Q4 Jun Q1 Sep regular quarterly operational reforecast at Gwalia, the near- Ore mined Development waste term production expectations for Gwalia were revised. Raisebore waste Total material moved While nearing completion, the remaining Gwalia Extension Project (GEP) construction and raiseboring program is competing for constrained ventilation with scheduled production and development activities.

For personal use only use personal For • The constrained ventilation and sequential mining schedule means any interruption to stoping, including from equipment failure causing a delay in stope development, cannot be recovered until after GEP is completed and new working faces have been developed. • FY20 guidance was revised as follows:

o Production between 175,000 and 190,000 ounces (previously 200,000 to 210,000 ounces) Reserve grade for FY19 and FY20 can be found respectively in the St BarbaraJune Limited 2018 Quarterly and June Report 2019 /Reserves Q1 September and ResourcesFY20 Statements Page 5 of 22

o AISC between A$1,390 and A$1,450 per ounce Gwalia Extension Project (GEP) (previously A$1,230 to A$1,290 per ounce)

o Capital expenditure comprising: Project Description . Sustaining capex: A$60 to A$65 million • The Gwalia Extension Project was announced on 27 March (previously A$55 to A$65 million), and 2017, has an overall budget of A$112 million (details below), and is expected to be completed in Q3 March FY20. . Growth capex: A$32 to A$38 million (previously A$30 to A$35 million), the increase is primarily • The Project consists of two main components, a ventilation ventilation related. upgrade and paste aggregate fill (PAF). PAF involves mixing paste from surface with waste crushed underground to fill Production Summary Q3 Mar Q4 Jun Q1 Sep stope cavities. Gwalia FY19 FY19 FY20 Gwalia Extension Project Summary Underground ore mined kt 146 156 152 Announced • 27 March 2017 Grade g/t 11.7 10.0 7.8 Status • Under construction Capex • A$112 M 1 Ore milled 9F kt 150 161 164 Construction • Commenced Q3 March FY17 1 Grade g/t 11.5 9.9 7.4 period • Anticipated completion Q3 Mar FY20 Recovery % 98 98 98 • PAF completion Q1 September FY20 Gold production oz 54,261 49,966 38,153 Key components

• 5 metre diameter ventilation shafts, 2 Ventilation All-In Sustaining Cost 10F A$ per ounce upgrade power & cooling Mining 416 527 760 • Supports mining to at least 2,000 mbs Processing 141 143 189 3 in FY 202411F Site services 94 92 125 • Approx. 80% of project budget Stripping and ore inventory 15 11 5 Paste • Underground waste crushing, paste and adjustments Aggregate aggregate fill mixing and pumping 666 773 1,079 Fill • Increase trucking efficiency By-product credits (2) (2) (3) (PAF) • Improve stope cycle times Third party refining & transport 2 2 1 • Reduce impact of vent shaft Royalties 47 48 47 construction on production Total cash operating costs 713 821 1,124 • Approx. 20% of project budget less operating development (86) (74) (199) Adjusted cash operating cost 627 747 925 Project Update

Corporate and administration 58 61 68 • During Q1 September FY20, commissioning of the Corporate royalty 28 29 30 underground crushing and mixing ‘PAF’ infrastructure Rehabilitation 4 4 6 continued. Mechanical and electrical installation of Operating development 78 66 191 equipment on the 1,460 level is now complete, and Capitalised mine development 169 232 313 commissioning activities on the 1420 and 1460 level are well progressed. Sustaining capital expenditure 52 91 26 • Mechanical installation activities for the cooling plant, vent All-In Sustaining Cost (AISC) 1,016 1,230 1,559 fans and power station expansion, and associated critical GEP infrastructure, also progressed through the quarter. • Drilling of the final raise bore pilot hole began during the quarter and is completed. Reaming is now underway.

For personal use only use personal For Ventilation • In parallel to the completion of the GEP project, the Gwalia operations undertook a review of the ventilation strategy to ensure maximised operational benefit from the GEP project

1 Includes Gwalia mineralised waste 3 Ore Reserves at 30 June 2019 extend down to 2,140 mbs, refer to 2 Non-IFRS measure, refer Appendix Ore Reserves and Mineral Resources Statement as at 30 June 2019

St Barbara Limited Quarterly Report / Q1 September FY20 Page 6 of 22

once complete. Based on the review it is proposed to change Simberi, Papua the ventilation strategy through Q2 December FY20 and Q3 March FY20, involving the relocation of underground fans and Operations adjustments to ventilation controls to establish discrete ventilation districts.

AISC Gwalia Extension Project Expenditure 1,603 (A$/oz)

1,229 1,203 • Project expenditure to date (all capitalised): 1,068 1,146

o FY17 $8 million FY19 average A$1,162/oz Production FY18 $32 million o (koz) 36.2 o FY19 $60 million 35.9 36.0 34.1 o FY20 27.1 Q1 $7 million . o Project to date $107 million FY19 FY19 FY19 FY19 FY20 A further $7 million (of $15 million) was spent during the Q1 Sep Q2 Dec Q3 Mar Q4 Jun Q1 Sep quarter on previously announced future-proofing ventilation and cooling works. • Simberi gold production for Q1 September FY20 was 27,061 ounces (Q4 June FY19: 36,231 ounces). • Production was lower than the previous quarter due to lower milled grade (1.19 g/t Au, Q4 June FY19: 1.68 g/t Au), offset by higher processing plant throughput. • Simberi mining activities in the quarter included a focus on stripping campaigns at the new Botlu pit as well as extensions of the Sorowar pit, leading to a drawdown of lower grade stockpiles for processing and reduced mined grade (1.09 g/t Au, Q4 June FY19: 1.48 g/t Au) and milled grade (1.19 g/t Au, Q4 June FY19: 1.68 g/t Au). • The lower grades impacted recovery (83%, Q4 June FY19: 86%). Mill throughput at 857 kt (Q4 June FY19: 780 kt) was the best result since Q1 September FY19. • All-in Sustaining Cost has increased as a result of lower production. • Works to replace the scrubber and install a new pebble crusher are expected to be completed in Q2 December FY20. The impact of this work on production is not anticipated to be material. The pebble crusher will better equip the SAG mill for treatment of harder rock, leading to increased throughput, while replacement of the scrubber will reduce downtime on

the ball mill circuit and reduce maintenance costs. For personal use only use personal For • Maintenance works on the aerial rope conveyor (RopeCon) were successfully undertaken during the quarter, with the RopeCon throughput immediately increasing to its best rate since Q4 June FY18.

St Barbara Limited Quarterly Report / Q1 September FY20 Page 7 of 22

• During the quarter the extension to the Simberi mining lease (ML136) was formally approved by the PNG Mines Minister. Production Summary Q3 Mar Q4 Jun Q1 Sep The lease now extends to December 2028. Simberi FY19 FY19 FY20 Ore & waste mined kt 3,176 2,794 2,956

Outlook Ore mined kt 711 615 578 Grade g/t 1.46 1.48 1.09 • FY20 guidance is unchanged and comprises:

kt 639 780 857 o Production of between 110,000 and 125,000 ounces Ore milled 2 Grade g/t 1.83 1.68 1.19 o AISC of between A$1,285 and A$1,450 per ounce13F Recovery % 90 86 83 o Sustaining capex of A$4 to A$5 million Gold production oz 34,097 36,231 27,061 Growth capex of A$3 to A$4 million. o 1 All-In Sustaining Cost12F A$ per ounce Mining 353 320 535 Sulphide drilling at Sorowar Processing 449 417 568 Site services 222 243 280 • Simberi Island (PNG): The sulphide drilling program beneath the Sorowar pit has been completed, with the latest drilling 1,024 980 1,383 results confirming significant additional sulphide and oxide By-product credits (6) (6) (10) mineralisation. An updated Reserves and Resources Third party refining & 8 8 12 statement is planned for Q3 March FY20. Preliminary studies transport on pit design, processing and logistics options are progressing. Royalties 40 39 55 • Significant results relating to 64 additional holes are reported Total cash operating costs 1,066 1,021 1,440 in the exploration section and ancillary tables. These results include (all intercepts downhole): Corporate and administration 58 61 68 o 11 m @ 8.62 g/t Au from 21 m (110SRDH002) Rehabilitation 21 19 28 o 25 m @ 3.09 g/t Au from 136 m (150SRDH045)

o 12 m @ 12.8 g/t Au from 75 m (125SRDH011) Sustaining capital expenditure 84 102 67 11 m @ 13.2 g/t Au from 45 m (125SRDH015) o All-In Sustaining Cost (AISC) 1,229 1,203 1,603 . Including 1 m @ 70.2 g/t Au from 45 m o 35 m @ 2.2 g/t Au from 62 m (135SRDH005)

For personal use only use personal For

1 Non-IFRS measure, refer Appendix 2 US$900 to US$1,015 per ounce @ AUD 0.70

St Barbara Limited Quarterly Report / Q1 September FY20 Page 8 of 22

Atlantic Gold, Nova Scotia, Canada Production Q3 Mar Q4 Jun Q1 Sep Q1 Sep Summary FY19 FY19 FY20 FY20 Atlantic Gold Attrib. Full Qtr Ore & waste kt Atlantic Gold mined 1,575 1,958 1,743 2,197

AISC Ore mined kt 1,015 1,008 1,131 1,316 (A$/oz) 1,010 970 957 Grade g/t 0.95 0.91 0.86 0.86 840 688 kt 528 611 446 577 Ore milled Grade g/t 1.22 1.24 1.37 1.29 Production Recovery % 95 94 93 94 (koz)

Gold production oz 19,612 22,947 17,993 22,355

27.6 All-In Sustaining 2 22.5 22.9 22.4 Cost15F 19.6 Mining 305 258 302 296

Processing 416 359 405 402 Site services 136 123 127 124 FY19 FY19 FY19 FY19 FY20 Stripping and ore (126) (34) (141) (127) Q1 Sep Q2 Dec Q3 Mar Q4 Jun Q1 Sep inventory Atlantic Gold production is attributable to St Barbara from 19 July adjustments 2019 732 707 693 695 By-product credits - - (1) (1) Operations Third party 2 2 19 18 refining & • Atlantic Gold was acquired on 19 July 2019. Atlantic Gold transport production for the full quarter was 22,355 ounces (includes Royalties 33 35 35 35 4,362 ounces produced prior to acquisition) at an average Total cash 766 744 746 747 milled grade of 1.29 g/t Au. operating costs • As reported previously, September production was affected by power outages related to Hurricane Dorian and Corporate and 83 89 74 76 maintenance of the detox tanks, which interrupted processing administration for approximately one week. Rehabilitation 20 21 7 6

88 157 137 141 Sustaining capital Outlook expenditure All-In Sustaining Cost • FY20 guidance comprises: (AISC) 957 1,010 964 970 Note: Atlantic Gold Corporation Q3 FY19 & Q4 FY19 historical AISC for reference o Production of between 95,000 and 105,000 ounces 1 o AISC of between A$900 and A$955 per ounce14F o Sustaining capex of A$13 to A$17 million (relates to refurbishment of the mining fleet, improvements to increase mill throughput and improve reliability, and Tailings Management Facility extension)

o Growth capex will be advised in Q2 December FY20. For personal use only use personal For

1 C$810 to UC$860 per ounce @ AUD 0.90 2 Non-IFRS measure, refer Appendix

St Barbara Limited Quarterly Report / Q1 September FY20 Page 9 of 22

Atlantic Gold growth projects

• There are three further Atlantic Gold projects scheduled for permitting and development : Beaver Dam, Fifteen Mile Stream and Cochrane Hill. • Beaver Dam: planned to have minimal site infrastructure, with ore trucked approximately 30 kilometres to the Touquoy processing plant. The Federal Environmental Impact Study was submitted in March 2019. • Fifteen Mile Stream: development plan is for a processing plant involving comminution, gravity gold extraction and concentration, with the concentrate trucked approximately 80 kilometres to the Touquoy processing plant. The Federal Environmental Impact Study was submitted in October 2019. • Cochrane Hill: development plan is for a processing plant involving comminution, gravity gold extraction and concentration, with the concentrate trucked approximately 155 kilometres to the Touquoy processing plant. The Federal EIS is planned to be submitted in late 2020. • As these projects are permitted and brought into production, gold production at Atlantic is anticipated to exceed 200,000 ounces per annum whilst maintaining its low cost profile.

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Page 10 of 22

Exploration Exploration – Results Q4 June FY19

Exploration guidance FY20 Gwalia Exploration Program, Leonora WA

• Exploration expenditure is forecast to be between A$31 and • Gwalia Deeps Extension: An extensive interval of mineralised A$41 million, consisting of: alteration and quartz veining encountered in GWDD23C, (previously reported) provided insights on the direction and A$3 to A$4 million at Gwalia Deeps o thickening of the lode system leading to the commencement A$4 to A$5 million in the Leonora region o of a new parent hole (GWDD25) targeting further down- o A$5 to A$7 million elsewhere in Australia mainly at plunge extensions to 2,300 mbs (Figures 1.1 to 1.4). Pinjin and Lake Wells in WA and Back Creek in NSW • Parent hole GWDD25 commenced late Q4 June FY19, to set up o A$3 to A$4 million on Simberi sulphide drilling a suitable platform for targeting southern extensions to the A$5 to A$8 million on the group (inc. o Gwalia lode system between 2,200 and 2,400 mbs. The drill Simberi) in PNG hole achieved a final depth of 2,591 m, entering the mine A$11 to A$13 million in Nova Scotia, Canada o sequence at 2,480 m and intersecting interpreted intervals of Main Lode, South West Branch and South Gwalia Series • The Gwalia Deeps drilling program has historically identified (SGS2), contained within the broader mineralised shear zone. extensions to mineral resources and ore reserves, extending Analytical results are still pending. the life of the underground operation to at least 2031. With • Parent hole GWDD24 and daughter hole GWDD24A, targeting the extension in mine life achieved, exploration at Gwalia and northern extensions to the Gwalia lode system at 1,100 mbs, the Leonora province has shifted its strategic focus, including were completed during Q1 September FY20. Both holes a stronger emphasis on identifying other deposits in the intersecting weakly mineralised intervals equivalent to Main region exploitable in the near term. Lode (Figures 1.1 to 1.3 and Table 1). • Exploration continued on the Pinjin project within the Yilgarn • Rushmore (Leonora, WA): Rushmore is located approximately Province, WA. The Pinjin Project is located 150 km northeast 1.5 km south of Gwalia underground development, centred of Kalgoorlie, comprising a large tenement package of 21 approximately 400 mbs, and consists of two broad seismic exploration licences (1,327 km2) for 474 blocks. targets adjacent to a granite/greenstone contact. Four RC pre- • St Barbara Limited entered into an Earn-In and Joint Venture collars have been completed with diamond tails expected to with Australian Potash Limited covering tenements at the be drilled during early Q2 December FY20. Lake Wells Gold Project in October 2018. The Lake Wells Gold • Jessie Alma (Leonora, WA): Phase 2 drilling, comprising of Project is located approximately 150 km northeast of eight new diamond drill holes with RC pre-collars, and four Laverton, Western Australia. The minimum exploration spend existing hole extensions via diamond tails were completed of $1.75 million was met during the initial 12 month Earn-In during Q1 September FY20 targeting intercepts returned from period. earlier Phase 1 RC drilling (Figure 2.0 and Table 2). • St Barbara Limited entered into an Earn-In and Joint Venture • Significant results from this program thus far include (all with Alice Queen Limited on two tenements (EPM 25520 and intercepts down-hole): EPM 25418) at the Horn Island Gold Project on 5 June 2019. The Horn Island Gold Project is located in the Torres Strait, far- o 1.4 m @ 1.8 g/t Au from 324 m (JARC004) north Queensland. o 1.1 m @ 1.2 g/t Au from 305 m (JARD022) • At Simberi Island in PNG the Company is drilling under the 2.0 m @ 1.5 g/t Au from 59 m (JARD023) current Sorowar pit to improve the potential viability of a o sulphide mining project on the island. o 2.3 m @ 1.1 g/t Au from 64 m (JARD023) • On islands nearby to Simberi in the Tabar Islands group, the • Cricket Pitch (Leonora, WA): A Diamond core drilling program Company is exploring for gold and copper-gold porphyry consisting of nine holes commenced in Q1 September FY20 targets. and at the end of the period, four holes were completed. Three of the four holes intersected a shear zone displaying •only use personal For In Canada’s Nova Scotia province the Group has exploration characteristics associated with the Gwalia Mine Schist (Figure interests at various stages, including advanced prospects 2.0 and Table 3). Significant results to date include (all being permitted for mining operations and less advanced intercepts down-hole): potential satellite pits within the Moose River Corridor, as well as early stage tenements comprising nearly 1,900 km2 in o 0.7 m @ 3.8 g/t Au from 222 m (CPDD001) the south west of the province. • Horse Paddock Well (Leonora, WA): A third phase of drilling comprising eight RC drill holes and two extensional diamond

St Barbara Limited Quarterly Report / Q1 September FY20 Page 11 of 22

tails, with total hole lengths ranging from 150 m to 240 m, • Two RC holes (PJRC0104 to PJRC105) were drilled for 594 commenced during the period (Figure 3.0 and Table 4). The metres testing two IP chargeability anomalies located objective of this program was to target potential extensions of immediately east of the Old Homestead target (Figure 4.4). mineralisation intersected in the previous phase of RC drilling. Assay results are pending. Analytical results received during the quarter include (all • Ground IP geophysics surveys were completed at Graham’s intercepts downhole): Find prospect, south of Lake Rebecca and immediately west of o 1.0 m @ 5.3 g/t Au from 114 m (HWRC0015) the Mulgabbie South Trend target, with the latter highlighting a shallow northwest striking chargeable anomaly (Figures 4.2 1.0 m @ 2.6 g/t Au from 23 m (HWRC0018) o and 4.5). 2.0 m @ 1.8 g/t Au from 27 m (HWRC0018) o • Further aircore and RC drilling is planned for Q2 December • Trevor Bore (Leonora, WA): A program of work consisting of FY20 (Figure 4.6). A three hole, 695 metre RC drill program will 11 RC holes to depths below surface of approximately 200 m, commence in late Q2 December FY20 testing IP targets at over a strike length of 1.4 km, was completed during the northern Graham’s Find and west of the Mulgabbie South quarter (Figure 3.0 and Table 5). The objective of this program Trend. was to test the source of two strong SAM anomalies coincident with mineralisation intersected in previous shallow Lake Wells Gold Project, Yilgarn WA drilling. Significant results from this program included (all intercepts downhole): • A 585 hole (LWAC0001 to LWAC0585) aircore drill program for 29,337 metres testing 8 targets was completed in Q4 June 9.0 m @ 1.6 g/t Au from 134 m (TBRD004) o FY19 with final assay results returned in Q1 September FY20 o 2.0 m @ 2.3 g/t Au from 90 m (TBRD006) (Figures 5.0 to 5.1 and Table 7). A detailed ground gravity survey was completed in July 2019 covering an approximate 10.0 m @ 2.4 g/t Au from 125 m (TBRD006) o 1,273 square kilometre area with 4,040 stations collected on . including 4.0 m @ 5.1 g/t Au from 125 m an 800 metre by 400 metre spacing. • Clay Duck (Leonora, WA): The Clay Duck area is located • A targeting study was completed over the entire tenement approximately 5 km northwest of the Gwalia mine. Four RC package using historical data, a recent detailed airborne pre-collars and three diamond tails were completed (Figure magnetic survey and results of the first aircore drill program. 2.0). These holes targeted potential northern extensions of A second round of aircore drilling, comprising 230 holes for the Gwalia Shear suggested by 3D seismic data. Results will be 13,500 metres testing seven targets is expected to commence evaluated during Q2 December FY20. in October 2019 (Figures 5.0 to 5.1). • Regional Geophysical Program (Leonora, WA): A second Back Creek, NSW phase of SAM over Horse Paddock Well/Trevor Bore, complemented by new Induced Polarisation (IP) surveys over • Horse Paddock Well, Kailis East and Gwalia North prospect A 12 hole, 1,650 metre infill and extension aircore drill areas commenced. Results from these surveys are expected to program commenced at the South West target in EL8214 become available during Q2 December FY20. following up anomalous gold in bedrock returned from three earlier aircore holes spaced 400 metres apart (Figure 6.0). To Pinjin Project, Yilgarn WA date, seven holes (BKAC0042 to BKAC0049) for 904 metres has been completed. Drilling intersected sediments (sandstones, • A 106 hole lake aircore drill program (PJAC2722 to PJAC2827) siltstones and shale) and mafic volcaniclastics containing for 4,728 metres was completed in July 2019, testing localised intervals of quartz veining under approximately 50 Graham’s Find and Far East targets. Final assay results were metres of transported cover. Assay results are pending. received in September 2019 with best assay results including • Subject to access, a MIM Distributed Acquisition System PJAC2783 returning 1 m @ 27.4 g/t Au from 33 metres (Figures (MIMDAS) IP survey is planned to commence in Q2 December 4.0 to 4.2 and Table 6) from Graham’s Find. No further work is FY20 at the North East target in EL8530 covering an planned at Far East. approximate 3 km by 2 km area (Figure 6.0). The survey will cover a magnetic high and surrounds, where a single diamond

•only use personal For A 268 hole land based aircore drill program (PJAC2828 to PJAC3095) for 11,610 metres was completed in September drill hole BKDD0001 returned 45 m @ 0.13% Cu from 113 2019, testing the five best geochemical and geophysical metres and 41 m @ 0.22% Cu from 232 metres. targets in the southeast tenement area known as Green Dam. Horn Island, QLD Preliminary composite assay results were received in October 2019, with best results including PJAC2996 returning 4 m @ • 650 ppb Au from 68 metres and PJAC3004 returning 4 m @ A surface sampling program comprising 407 soils was 587 ppb Au from 68 metres (Figure 4.3 and Table 6). completed on 23 northeast oriented lines spaced 100 metres

St Barbara Limited Quarterly Report / Q1 September FY20 Page 12 of 22

apart with samples collected at 50 metre spacing (Figure 7.0). 125SRDH011: The survey covered an approximate 1.8 kilometre strike of 2 m @ 1.5 g/t Au from 41 m interpreted northwest trending alteration and localised quartz o ± sulphide veining immediately adjacent to the Alice Queen o 6 m @ 1.4 g/t Au from 48 m Limited Horn Island inferred gold resource and historical open 4 m @ 1.3 g/t Au from 56 m cut mine. Quartz veining observed during the soil sampling o were rock chipped with 176 samples collected. To date, 66 o 12 m @ 12.8 g/t Au from 75 m quartz vein rock chip samples results have been received, . Including 2 m @ 58.7 g/t Au from 76 m twenty-four samples returning ≥0.1 g/t Au, five samples ≥ 1.0 g/t Au and a maximum result of 215 g/t Au. The remaining o 3 m @ 1.0 g/t Au from 217 m assay results are pending. 125SRDH015: • A ground dipole-dipole IP survey covering an approximate 3 o 11 m @ 13.2 g/t Au from 45 m km by 2 km area has commenced, with three lines completed to date (Figure 7.0). The geophysical survey will cover a slightly . Including 1 m @ 70.2 g/t Au from 45 m larger area than the surface sampling program and run along o 3 m @ 0.9 g/t Au from 61 m similar northeast orientated lines spaced 200 metres apart with stations at 100 metre spacing. o 1 m @ 4.1 g/t Au from 221 m 2 m @ 0.8 g/t Au from 228 m Simberi, Tatau & Tabar Islands, o 135SRDH005: • Simberi Island (PNG): The sulphide drilling program beneath o 35 m @ 2.2 g/t Au from 62 m the Sorowar pit has been completed, with the latest drilling 135SRDH006: results confirming significant additional sulphide and oxide mineralisation is present (Figures 8.0 to 8.8). An updated o 4 m @ 1.4 g/t Au from 16 m Reserves and Resources statement is planned for Q3 March 4 m @ 21.5 g/t Au from 77 m FY20. Preliminary studies on pit design, processing and o logistics options are progressing. . Including 1 m @ 73.4 g/t Au from 77 m • Significant results relating to 64 additional holes are reported o 3 m @ 0.8 g/t Au from 86 m in Table 8 and include (all intercepts down-hole, hole ID stated 19 m @ 3.0 g/t Au from 102 m first): o . Including 1 m @ 22.4 from 110 m 110SRDH001: • A single 1,000 metre diamond drill hole is planned to further 8 m @ 0.9 g/t Au from 28 m o test the Pigiput copper-gold porphyry target within ML136 o 4 m @ 1.5 g/t Au from 38 m (Figure 8.8). The hole is planned to drill below the previous hole SDH371 that returned 50 m @ 0.37 % Cu, 0.13 % Mo and 4 m @ 5.3 g/t Au from 44 m o 0.24 g/t Au from 506 metres. 3 m @ 2.7 g/t Au from 59 m o • Tatau and Big Tabar Island (PNG): Exploration continued on o 2 m @ 1.1 g/t Au from 106 m EL609 and EL2462 covering Tatau and Big Tabar Islands during Q1 June FY20. Work focussed on the execution of diamond 8 m @ 1.3 g/t Au from 130 m o drilling at Banesa copper-gold target on Big Tabar Island and o 27 m @ 2.6 from 160 m surface sampling (soil and rock chip) on Tatau Island. 110SRDH002: • Results were returned for a 850.3 metre diamond drill hole BND010 completed at Banesa during Q4 June FY19. Best o 11 m @ 8.6 g/t Au from 21m results (all intercepts downhole, details in Figure 8.9 and Table o 15 m @ 5.1 g/t Au from 129 m 9) include:

125SRDH008: BND010: For personal use only use personal For 7 m @ 1.5 g/t Au from 80 m o o 192 m @ 0.25 g/t Au and 0.10 % Cu from 280 m o 11 m @ 4.5 g/t Au from 100 m . including 14 m @ 0.66 g/t Au and 0.20 % Cu from . Including 1 m @ 34.2 g/t Au from 101 m 282 m 26 m @ 0.39 g/t Au and 0.24% Cu from 484 m o 3 m @ 1.1 g/t Au from 169 m o

St Barbara Limited Quarterly Report / Q1 September FY20 Page 13 of 22

. including 8 m @ 0.85 g/t Au and 0.42 % Cu from CH-19-336: 486 m o 9 m @ 1.14 g/t Au from 159 m • Diamond drill hole BND012 was completed to a final depth of 1 m @ 6.00 g/t Au from 174 m 1,144.3 metres during Q1 September FY20. Drilling o intersected potassic alteration (biotite ± magnetite ± CH-19-343: actinolite ± k-feldspar) and low density actinolite – 13 m @ 1.81 g/t Au from 276 m chalcopyrite ± biotite ± magnetite veins overprinting pyroxene o monzodiorite and a later monzonite between 850 and 1,100 o 6 m @ 1.56 g/t Au from 293 m metres depth. Assay results are pending. Two trenches o 7 m @ 1.58 g/t Au from 304 m (TABTR218 and TABTR219) completed at Banesa for 170 metres and 34 samples returned no significant results. CH-19-344:

• Tatau Island (PNG): Results were received for a sixty-nine o 25 m @ 2.49 g/t Au from 220 m hand auger soil sample program completed on Tatau Island CH-19-345: within EL2462 (Figure 8.10). The results highlighted a north- northwest orientated 500 ppm copper anomaly measuring o 22 m @ 3.05 g/t Au from 286 m 1,500 metres by 500 metres. 200 rock chip samples were o 2 m @ 9.53 g/t Au from 314 m collected during mapping at Tatau North prospect. Assay results are pending. o 3 m @ 1.78 g/t Au from 320 m • Subject to access, a single 600 metre diamond drill hole is CH-19-348: planned to test the Mt Tiro gold sulphide target approximately o 19 m @ 1.67 g/t Au from 214 m 200 metres below the levels of previous drilling (Figure 8.10). o 3 m @ 1.24 g/t Au from 251 m Option and Farm-in with Newcrest, Tatau & Tabar o 8 m @ 4.04 g/t Au from 275 m Islands, Papua New Guinea CH-19-352:

• Newcrest PNG Exploration Limited (a wholly owned subsidiary o 7 m @ 2.61 g/t Au from 157 m of Newcrest Mining Limited) withdrew from the Option and o 4 m @ 2.71 g/t Au from 175 m Farm-in Agreement with the St Barbara group (through its wholly owned PNG subsidiary Nord Australex Nominees (PNG) • Cochrane Hill up-dip: A short, five drill hole program was Ltd) in August 2019. During the period from December 2016 completed in Q1 September FY20, with final assays pending. to August 2019, 6 holes were drilled for 4,947 metres testing The drilling was targeting shallow up-dip mineralisation and three copper - gold porphyry targets including Talik North and extended into the footwall for waste rock studies (Figure 9.1). Kupo on Tatau Island and Banesa on Big Tabar Islands. Moose River Corridor, Central Nova Scotia Cochrane Hill Project, Melrose, Nova Scotia • 149 Deposit: Drilling in Q1 September FY20 included 12 • Cochrane Hill down dip and eastern Extension: The Cochrane diamond drill holes focused on resource expansion, including drilling program was completed at the end of Q4 June FY19, delineation of mineralisation to depth along the Fifteen Mile with final assays received in Q1 September FY20 (Figures 9.0 Stream fold axis and the along-strike and up-dip shallow to 9.1 and Table 10). A total of 17 diamond drill holes were expression of the low-grade southern limb mineralisation completed for 4,799 metres, targeting primarily inferred and (Figure 9.5). To date, assays have not been received. However, undefined resources in the central part of the deposit. Seven visual examination and logging of drill core indicates that the holes targeted the down plunge eastern extension of the target zones have been intercepted. higher grade zones below the current deposit, including CH- • Touquoy West: Exploration in Q1 September FY20 included 17 19-336 and CH-19-352 (Figure 9.1). All holes passed through RC drill holes targeting historic advanced exploration mineralised intervals of the shear zone, with significant results prospects and new targets along the Moose River Anticline

below (all intercepts down-hole, hole ID stated first). trend identified based on aeromagnetic data and geological For personal use only use personal For CH-19-335: mapping (Figure 9.6 and 9.7). • Bear Brook: The Bear Brook prospect is a greenfield target o 1 m @ 10.25 g/t Au from 243 m located approximately 1 km west along strike of Seloam o 1 m @ 19.55 g/t Au from 248 m Brook. Three diamond drill holes were completed in Q1 September FY20 targeting a high analytical signal overlapping o 15 m @ 2.17 g/t Au from 253 m with folded and faulted argillite. Assay results are pending. o 7 m @ 1.68 g/t Au from 280 m

St Barbara Limited Quarterly Report / Q1 September FY20 Page 14 of 22

• Cameron Flowage: Drilling comprised a nine hole program intervals up to 1 km west of the existing resource. Significant (CF-19-007 to CF-19-015) following up on CY 2018 drill results intercepts from these holes are shown below (all intercepts designed to locate a displaced extension of the Beaver Dam down-hole, hole ID stated first). Location and full details of deposit to the northeast. Drilling in the Cameron Flowage area these intercepts are provided in Figures 9.2, 9.3 and 9.4 and has defined two main mineralised zones. The upper zone is a Table 12. thickened argillite in an anticlinal hinge while the lower zone SB-19-028: is part of the overturned southern limb. Both zones are characterized by pyrrhotite, strong quartz veining, o 7 m @ 0.79 g/t from 63 m arsenopyrite and trace chalcopyrite. Significant intersections SB-19-030: include (all intercepts downhole, details in Table 11): 4 m @ 0.84 g/t Au from 56 m CF-19-008: o SB-19-031: o 5.0 m @ 0.99 g/t from 136 m 4 m @ 9.73 g/t Au from 81 m CF-19-010: o o 2 m @ 1.71 g/t Au from 149 m o 3.0 m @ 1.35 g/t from 104 m 6 m @ 2.22 g/t Au from 174 m CF-19-011: o SB-19-034: o 3.0 m @ 0.83 g/t from 97 m o 7 m @ 0.64 g/t Au from 57 m o 2.0 m @ 2.07 g/t from 109 m 7 m @ 0.92 m g/t Au from 87 m CF-19-015: o • Fifteen Mile Stream: Exploration drilling (eight diamond drill 1.0 m @ 8.00 g/t from 195 m o holes, Figure 9.3 and Figure 9.4) focused on resource • Mill Shaft: The Mill Shaft Zone (MSZ) is 600 metres west of the expansion between the planned Hudson and Egerton- Beaver Dam deposit. MSZ extends over 1 km in strike length Maclean open pits and delineation drilling along approx. 300 and bounded to the west by the River Lake Pluton. The Q1 m of strike length of the Fifteen Mile Stream Anticline and September FY20 program consisted of a seven diamond drill Seigel Fault. Assays are pending; preliminary drill core logging hole program, testing an anticline along strike of the Beaver supports the potential extension of fold and fault-related gold Dam deposit, coincident with a linear magnetic high. mineralisation along the fold axis and shear zone up to ~200 Highlights of significant intersections from the Q1 September m east of the Hudson pit and ~100 m northwest of the FY20 drilling include (all intercepts downhole, details in Table Egerton-MacLean. 11): South-west Nova Scotia MS-19-006:

o 1.0 m @ 1.03 g/t from 140 m • Airborne Geophysical Survey: The largest independent airborne geophysical survey in Nova Scotia commenced on MS-19-008: August 5th to improve on the limited amount of geophysical o 1.0 m @ 4.07 g/t from 155 m information analogous to the Meguma terrain in the northeast that contain Atlantic Gold’s four main deposits. The • Crusher Lake: The Crusher Lake program is a nine hole data is being collected on 75 m spaced lines and includes: diamond drill program targeting unexplored magnetic anomalies beneath planned mine infrastructure at Beaver o High resolution aero magnetics Dam. The drilling comprised of planar overturned strata on the Horizontal Gradiometer southern limb of the Beaver Dam anticline, striking east-west, o dipping north. Trace pyrrhotite is common without any o Digital Matrix VLF-EM significant mineralisation present. • Field reconnaissance: A first pass field review was carried out Fifteen Mile Stream Project, Trafalgar, Nova Scotia to delineate potential drilling access and to execute a map and sample program with collection of 530 rock samples analysed

For personal use only use personal For for gold and multi-element anomalies. Prospective samples • Seloam Brook: Drilling along strike, approximately 700 metres have returned anomalous values (0.01 g/t to 10.9 g/t) in the west of the Fifteen Mile Stream, has continued into Q1 vicinity of the Pleasant field prospect, along with an arsenic September FY20 with the drilling of 13 diamond drill holes anomaly (100 ppm to 5340 ppm). focused on targets generated from drill programs in FY18 and FY19. Assays are pending for eight holes, with the received assays supporting the presence of gold mineralisation associated with folds and faults along target stratigraphic

St Barbara Limited Quarterly Report / Q1 September FY20 Page 15 of 22

Full regional prospect evaluation Leonora Region

• A full review of current prospects is being undertaken to • Jessie Alma: Evaluation of data from recently completed complete a comprehensive evaluation and program planning drilling campaigns. for the current prospective lease holdings. • Cricket Pitch: Complete diamond drilling program testing the Expenditure Q1 September FY20 (unaudited) northern extensions of the Gwalia Shear Zone and analyse data.

Expenditure on mineral exploration is shown below: • Rushmore: Complete diamond drilling extensions to four RC pre-collars. Q4 Jun Q1 Sep

FY19 FY20 • Horse-Paddock Well: Undertake first pass RC drilling programs on three new target areas located within the Horse Paddock A$ million Well project area. Australia 5.4 4.0 (expensed) • Pacific 1.4 1.6 (expensed) Trevor Bore: Evaluation of data from recently completed drilling campaigns Gwalia Deep Drilling 3.6 2.4 (capitalised) • Canada - 5.4 (capitalised) Evaluate SAM and IP survey data in the Horse Paddock Well/Trevor Bore, Kailis East and Gwalia North prospect areas 10.3 13.4 to identify drill targets.

Pinjin, WA

Planned Exploration – Q2 December FY20 • Reviewing the assay results from the 268 hole, 11,610 metre The map below shows current and planned target areas for Q2 aircore drill program completed at Green Dam. December FY20. • Reviewing the assay results from the two RC holes drilled testing IP chargeability anomalies east of the Old Homestead target. • Completing a three hole, 695 metre RC drill program testing IP targets at Graham’s Find and west of the Mulgabbie South Trend.

Lake Wells, WA

• Completing a second round of aircore drilling, comprising 230 holes for 13,500 metres testing seven targets.

Back Creek, NSW

• Completing the 12 hole, 1,650 metre infill and extension aircore drill program at the South West target in EL8214 and reviewing the assay results. • Subject to access, completing the MIMDAS IP survey at the North East target in EL8530 and review results.

Simberi Island

For personal use only use personal For • Completing a single 1,000 metre diamond drill hole further Exploration in Q2 December FY20 will focus on: testing the Pigiput copper - gold porphyry target on ML136. Gwalia Deeps Tabar Islands, PNG

• Evaluate data returned from GWDD23C and GWDD25 to • Reviewing the assay results from diamond drill hole BND012 determine the trend of high grade extensions to South West at the Banesa copper - gold porphyry prospect on Big Tabar Branch between 2,200 – 2,400 mbs. Island (EL609).

St Barbara Limited Quarterly Report / Q1 September FY20 Page 16 of 22

• Subject to access, completing a single 600 m diamond drill Fifteen Mile Stream Project, Nova Scotia hole at Mt Tiro gold sulphide target on Tatau Island (EL609).

• Subject to access, continuing the soil, rock chip sampling, • Assess assay results from Q1 September FY20 drilling and, reconnaissance mapping and trenching over gold and copper based on results, plan follow up drilling in Hudson-Egerton - gold targets on Tatau and Big Tabar Islands. Gap and Seloam Brook.

Horn Island, QLD • Complete drilling program ongoing in Egerton/149 gap area. Touquoy West, Central Nova Scotia • Reviewing the assay results from the soil and rock chip sampling program. • Complete RC drilling program in Touquoy West and assess • Completing the ground dipole-dipole IP survey on Horn Island assay results from Q1 September FY20 program. and review the results in combination with surface geochemistry to generate and rank targets for further work. Moose River Corridor, Central Nova Scotia

Atlantic Gold • Complete priority target programs in Wire Lake, Jed Lake and The map below shows current and planned target areas for Q2 Union Dam. December FY20. • Assess assays and review geological modelling of priority targets drilled in Q1 September FY20.

Regional Exploration in Q2 December FY20 will focus on:

South-west Nova Scotia – Airborne Geophysics Survey

• The final flights will be completed on the Western and Eastern

blocks in the southwest for a combined total distance of ~41,000Lkm. • The interpretation and targeting program will be completed for South-west Nova Scotia.

Pleasant Field, South-west Nova Scotia

• Commence a six hole, 600 metre RC and diamond drilling program, testing previous shallow anomalous mineralisation. Exploration in Q2 December FY20 will focus on: • Commence 70+ shallow RC drill hole program along strike to the southwest of the main prospect. Cochrane Hill Project, Nova Scotia Indian River, South-west Nova Scotia • Cochrane Hill East: Commence drilling 2,400 m RC and diamond drilling program to sterilize/explore eastern • Subject to access, commence initial drill program to test the extension of geophysical signature. VLF and rock sample anomalies. • Cochrane Hill West: Assess drilling program to North Brookfield, South-west Nova Scotia sterilize/explore western extension of geophysical signature, and to follow up assays from historic shallow RC/interface • Subject to access, commence a diamond drill hole program to program. test the anomalous showing.

For personal use only use personal For 149 Deposit/Extension, Nova Scotia

• Complete remaining diamond drilling, assess assay results, and commence eastern extension/sterilization drilling.

St Barbara Limited Quarterly Report / Q1 September FY20 Page 17 of 22

Exploration Investments Corporate • One component of the Company’s growth strategy is targeted • The Company paid a A$0.04 fully franked final dividend on 25 investments in early to advanced stage exploration through September 2019. Thirty-two percent of shares participated in earn-in arrangements, joint ventures or direct equity the Dividend Reinvestment Plan, resulting in 2,956,112 shares investments. being issued on 25 September 2019. • At the date of this report, St Barbara holds the following Share Capital 1 investments in Australian explorers16F : Issued shares Catalyst Metals Limited (ASX:CYL) 14% Opening balance 30 Jun 2019 695,653,732

Duketon Mining Limited (ASX:DKM) 12% 2 Issued17F 2,956,112 Peel Mining Limited (ASX:PEX) 16% Closing balance 30 Sep 2019 699,161,089 Prodigy Gold (ASX:PRX) 8% Unlisted employee rights • St Barbara also has an Earn-in and Joint Venture with Opening balance 30 Jun 2019 1,940,662 Australian Potash Limited (ASX: APC) on the Lake Wells Gold Project and an Earn-In and Joint Venture with Alice Queen Issued nil Limited on two tenements (EPM 25520 and EPM 25418) at the Exercised as shares nil Horn Island Gold Project in Queensland. Lapsed nil Health & Safety Closing balance 30 Sep 2019 1,940,662 • St Barbara’s 12 month rolling TRIFR is 5.0 as at end of September 2019 with six Recordable Injuries across the Comprises rights expiring: Group, most of low severity. 3 30 June 2020 18F 1,175,059

• All operations continue to focus on Visual Leadership 4 30 June 202119F 765,603 Observations, workplace inspections and START Safe meetings. Atlantic Gold Operations reported no injuries or Closing balance 30 Sep 2019 1,940,662 asset damage from Hurricane Dorian. • This Quarter the HSEC team has conducted a full review and update of the Group’s Critical Risk Control Standards. • Safety reporting for Q1 September FY20 includes results for Australian and PNG operations. Integration of Atlantic Gold

safety systems is underway. For personal use only use personal For

1 Shareholdings as notified by St Barbara in substantial holder notices 3 If these rights do not vest at 2020, they may be retested at 2021 and 2022 2 ASX Appendix 3B 25 September 2019 shares issued in accordance with 4 These rights are not subject to retesting the St Barbara Dividend Reinvestment Plan

St Barbara Limited Quarterly Report / Q1 September FY20 Page 18 of 22

Finance (unaudited) • 80,810 ounces of gold were sold in Q1 September FY20, at an average realised gold price of A$1,948 per ounce (Q4 Jun FY19: 85,006 ounces at A$1,848 per ounce).

1 • Total cash at bank and term deposits at 30 September 2019 was A$76 million20F (30 June 2019: A$890 million) after payment of Atlantic Gold consideration of A$780 million, dividends of $19 million, growth capex of $14 million, exploration of $13 million and income tax payments of $8 million.

2 • The Company generated an operational cash contribution21F in Q1 September FY19 of A$43 million (Q4 Jun FY19: A$58 million). Cash movements are summarised in the following table: Cash movements & balance A$M Q3 Mar Q4 Jun Year Q1 Sep (unaudited) FY19 FY19 FY19 FY20 3 Operating cash flow 22F - Leonora 51 37 186 12 Simberi 20 21 98 22 Atlantic - - - 9 Operational cash contribution 71 58 284 43 Leonora - growth capital (19) (20) (63) (14) Rehabilitation , land management & project costs (2) (2) (8) (2) 4 Corporate costs 23F (5) (5) (22) (8) Corporate royalties (2) (1) (6) (1) 5 Exploration 24F (5) (10) (26) (13) 6 Investments 25F - - (6) - Income tax payments (4) (8) (64) (8) 7 Working capital movement 3 12 11 (8)26F Cash flows before finance costs 37 25 100 (11) Net interest income 2 Other financing 2 3 10 (6) Equity proceeds - 480 480 - Acquisition of Atlantic Gold - - - (780) Dividends paid (14) - (42) (19) Net movement for period 25 508 548 (814) Cash balance at start of quarter (year) 357 382 342 890 Cash balance at end of quarter (year) 382 890 890 76

Cash balance excludes restricted cash 2 2 2 2 For personal use only use personal For

1 Financial information unaudited. Balance comprises A$66 M cash and A$10 M term deposits, excludes A$2 M restricted cash. 2 Non-IFRS measure, see cash movements table this page. Corresponds to Operational Cash Flow less sustaining capital, but excludes growth capital of A$14 million. 3 Net of sustaining capex. 4 Cash corporate costs in Q1 Sep FY20 include payment of short term incentives for employees (inc. key management personnel) accrued at 30 June 2019 and Atlantic Gold corporate costs since acquisition. 5 Includes Gwalia deep drilling. 6 Refer ‘Exploration Investments’ earlier in this report. 7 Movement relates to the payment of accounts payable reported at the 30 June 2019 year end and gold in transit from Simberi and Atlantic Gold.

St Barbara Limited Quarterly Report / Q1 September FY20 Page 19 of 22

• Hedging in place at the date of this report (all in the form of forward gold contracts) comprises: FY20 20,280 ounces to be delivered in monthly instalments between October and December 2019 at A$1,750 per ounce (FY20 component of hedges announced 7 and 19 February 2018 and 7 March 2018). 24,000 ounces to be delivered in monthly instalments between January and June 2020 at A$1,809 per ounce (FY20 component of hedge announced 26 October 2018). 24,000 ounces to be delivered in monthly instalments between January and June 2020 at US$1,300 per ounce (FY20 component of hedge announced 10 December 2018). FY21 26,000 ounces to be delivered in monthly instalments between July and December 2020 at A$1,809 per ounce (FY21 component of hedge announced 26 October 2018). 26,000 ounces to be delivered in monthly instalments between July and December 2020 at US$1,300 per ounce (FY21 component of hedge announced 10 December 2018). Atlantic 100,873, ounces to be delivered in quarterly instalments between November 2019 and February 2021 at

Gold C$1,550 per ounce (announced by Atlantic Gold on TSX 21 September 2018). For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Page 20 of 22

Corporate Directory Shareholder Enquiries St Barbara Limited ABN 36 009 165 066 Computershare Investor Services Pty Ltd GPO Box 2975 Board of Directors Melbourne Victoria 3001 Australia Tim Netscher ...... Non-Executive Chairman Telephone (within Australia) 1300 653 935 Bob Vassie ...... Managing Director & CEO Telephone (international) +61 3 9415 4356 Steven Dean ...... Non-Executive Director Facsimile +61 3 9473 2500 Kerry Gleeson ...... Non-Executive Director www.investorcentre.com/au Stef Loader ...... Non-Executive Director

David Moroney ...... Non-Executive Director American Depositary Receipt enquires:

BNY Mellon Depositary Receipts Executives www.bnymellon.com/shareowner Bob Vassie ...... Managing Director & CEO

Garth Campbell-Cowan ...... Chief Financial Officer Investor Relations Rowan Cole ...... Company Secretary David Cotterell, Manager Investor Relations +61 3 8660 1959 Maryse Bélanger ...... President Americas Rowan Cole, Company Secretary +61 3 8660 1900

Registered Office % of Holdings27F1 Level 10, 432 St Kilda Road Substantial Shareholders Melbourne Victoria 3004 Australia Van Eck Associates Corporation 12.2% Telephone +61 3 8660 1900

Facsimile +61 3 8660 1999 Scheduled Future Reporting Email [email protected] Date Report Website www.stbarbara.com.au 23 October Annual General Meeting

22 January Q2 December FY20 Quarterly Report Australian Securities Exchange (ASX) Listing code “SBM” Dates are tentative and subject to change American Depositary Receipts (ADR OTC code “STBMY”) through BNY Mellon, www.adrbnymellon.com/dr_profile.jsp?cusip=852278100

Financial figures are in Australian dollars (unless otherwise

noted).

Financial year commences 1 July and ends 30 June. Q1 Sep FY20 = quarter to 30 Sep 2019 Q2 Dec FY20 = quarter to 31 Dec 2019

For personal use only use personal For Q3 Mar FY20 = quarter to 31 Mar 2020 Q4 Jun FY20 = quarter to 30 Jun 2020

1 As notified by the substantial shareholders to 18 October 2019

St Barbara Limited Quarterly Report / Q1 September FY20 Page 21 of 22

Appendix

Non-IFRS Measures inclusion in the report of the matters based on his information in the form and context in which it appears. • The Company supplements its financial information reporting • determined under International Financial Reporting Standards (IFRS) The information in this report that relates to Exploration Results for with certain non-IFRS financial measures, including cash operating Nova Scotia is based on information compiled by Dr David Lowe, who costs and All-In Sustaining Cost. We believe that these measures is a professional member of Geoscientists Nova Scotia and the provide additional meaningful information to assist management, Association of Engineers and Geoscientists of Alberta. Dr Lowe is a investors and analysts in understanding the financial results and full-time employee of St Barbara and has sufficient experience assessing our prospects for future performance. relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify • Cash Operating Costs are calculated according to common mining as a Competent Person as defined in the 2012 Edition of the industry practice using The Gold Institute (USA) Production Cost ‘Australasian Code for Reporting of Exploration Results, Mineral Standard (1999 revision). Resources and Ore Reserves’. Dr Lowe consents to the inclusion in • All-In Sustaining Cost (AISC) is based on Cash Operating Costs, and the report of the matters based on his information in the form and adds items relevant to sustaining production. It includes some, but context in which it appears. not all, of the components identified in World Gold Council’s Guidance Mineral Resource and Ore Reserve Estimates Note on Non-GAAP Metrics - All-In Sustaining Costs and All-In Costs (June 2013). • The information in this report that relates to Mineral Resources or Ore o AISC is calculated on gold production in the quarter. Reserves is extracted from the report titled ‘Ore Reserves and Mineral Resources Statements 30 June 2019’ released to the Australian o For underground mines, amortisation of operating development is adjusted from “Total Cash Operating Costs” in order to avoid Securities Exchange (ASX) on 21 August 2019 and available to view at duplication with cash expended on operating development in the www.stbarbara.com.au and for which Competent Persons’ consents period contained within the “Mine & Operating Development” were obtained. Each Competent Person’s consent remain in place for line item. subsequent releases by the Company of the same information in the same form and context, until the consent is withdrawn or replaced by o Rehabilitation is calculated as the amortisation of the a subsequent report and accompanying consent. rehabilitation provision on a straight-line basis over the estimated life of mine. • The Company confirms that it is not aware of any new information or data that materially affects the information included in the original ASX announcement released on 21 August 2019 and, in the case of Competent Persons Statement estimates of Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in Exploration Results the original ASX announcement continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Person's findings are presented have not • The information in this report that relates to Exploration Results for been materially modified from the original ASX announcement. the Tabar Islands Group (including Simberi), Pinjin, Back Creek, Lake Wells and Horn Island is based on information compiled by Dr Roger • Full details are contained in the ASX release dated 21 August 2019 Mustard, who is a Member of The Australasian Institute of Mining and ‘Ore Reserves and Mineral Resources Statements 30 June 2019’ Metallurgy. Dr Mustard is a full-time employee of St Barbara and has available at www.stbarbara.com.au. sufficient experience relevant to the style of mineralisation and type

of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Dr Mustard consents to the inclusion in the report of the matters based on his information in the form and context in which it appears.

• The information in this report that relates to Exploration Results for

Gwalia and the Leonora region is based on information compiled by For personal use only use personal For Mr Robert Love, who is a Fellow of The Australasian Institute of Mining and Metallurgy. Mr Love is a full-time employee of St Barbara and has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves’. Mr Love consents to the

St Barbara Limited Quarterly Report / Q1 September FY20 Page 22 of 22

Exploration Figures and Tables

Figure 1.0: Leonora: Gwalia Deeps Drilling Program Q1 FY20 Plan View

Figure 1.1: Gwalia Deeps Drilling Program Q1 FY20, Cross Section (looking north)

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables i

Figure 1.2: Gwalia Deeps Drilling Program Q1 FY20 Results, Long Section (looking west)

Figure 1.3: Gwalia Deeps Drilling Program Q1 FY20 Results, Long Section (looking west)

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables ii

Figure 2.0: Jessie Alma, Cricket Pitch and Clay Duck Drilling Results Q1 FY20

Figure 3.0: Horse Paddock Well and Trevor Bore Project Areas - Drilling Program Q1 FY20

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables iii

Figure 4.0: Pinjin Project Aircore and Reverse Figure 4.1: Pinjin Project Drilling Results Map Circulation Drilling Location Map (Enlargement) – maximum gold in bedrock

Figure 4.2: Graham’s Find Drilling Results Map (Enlargement) – maximum gold in bedrock

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables iv

Figure 4.3: Green Dam Drilling Results Map (Enlargement) – maximum gold in bedrock

Figure 4.4: Homestead and Mulgabbie Trend North Geophysics and RC Drilling Location Map

(Enlargement) For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables v

Figure 4.5: Mulgabbie Trend South Geophysics Figure 4.6: Pinjin Planned Drilling Location Map and Drilling Location Map (Enlargement)

Figure 5.0: Lake Wells Gold Project Aircore Figure 5.1: Lake Wells Drilling Results Map Drilling Location Map (Enlargement) – maximum gold in bedrock

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables vi

Figure 6.0: Back Creek Aircore Drilling and Geophysics Location Map

Figure 7.0: Horn Island Surface Sampling and Geophysics Location Map

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables vii

Figure 8.0: Tabar Islands Location Map, Papua New Guinea

Figure 8.1: Location of Sorowar Sulphide Drill Cross Sections, Simberi Island, Papua New Guinea

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables viii

Figure 8.2: Sorowar Sulphide Drill Cross Section (66,307), Simberi Island, Papua New Guinea

Figure 8.3: Sorowar Sulphide Drill Cross Section (66,337), Simberi Island, Papua New Guinea

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables ix

Figure 8.4: Sorowar Sulphide Drill Cross Section (66,357), Simberi Island, Papua New Guinea

Figure 8.5: Sorowar Sulphide Drill Cross Section (66,557), Simberi Island, Papua New Guinea

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables x

Figure 8.6: Sorowar Sulphide Drill Cross Section (66,627), Simberi Island, Papua New Guinea

Figure 8.7: Sorowar Sulphide Drill Cross Section (66,897), Simberi Island, Papua New Guinea

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xi

Figure 8.8: Simberi ML136 Drill Location Map, Figure 8.9: Banesa Drill Location Map, Big Tabar Simberi Island, Papua New Guinea Island, Papua New Guinea

Figure 8.10: Soil Copper Results Map, Tatau Island, Papua New Guinea For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xii

Figure 9.0: Project Locations – Cochrane Hill

Figure 9.1: Plan View Map, highlighting location of Q4 FY19 Resource Drilling Programs. Note location of highlights from resource drilling, assay results released in Q1 FY20

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xiii

Figure 9.2: Project Locations – Fifteen Mile Stream and 149 Deposit

Figure 9.3: Plan View highlighting location of Seloam Brook Section 12,100E and location of Q1 FY20 drilling in Seloam Brook, Hudson-Egerton Gap, and Egerton-MacLean (Fifteen Mile Stream Project). Two DDH can be seen in the far east from Egerton-149 gap drill program

(ongoing). For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xiv

Figure 9.4 Section 12,100E in Seloam Brook, showing location of SB-19-031. Note shallow higher grade mineralization (4m @ 9.73g/t from 81m).

Figure 9.5: Plan View map 149 Deposit, highlighting location of current drill program. All drilling shown in deposit area was completed by the time of this report (late Q1 FY20), assay

results are still pending. For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xv

Figure 9.6: Project Locations – Touquoy Mine and Touquoy West Area

Figure 9.7: Plan View map of Touquoy West RC program, with relative position to Touquoy mine. For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xvi

Table 1: Gwalia Deeps Significant Intercepts – Leonora, WA

Metres Below Down-hole North East RL Dip/ Azimuth Surface Mineralised Intersection Hole Id From To Interval Gold grade m m m degrees m m m m Au g/t GWDD24 6608 8687 4274 -60/251 1106 1186 1188 2.0 1.7 NOTES: Dip and Azimuth angles estimated at intercept depth. Coordinates and Azimuth referenced to Gwalia Local Mine Grid. Reported intercepts are all down hole lengths. Numbers have been rounded to one significant figure.

Table 2: Jessie Alma Significant Intercepts – Leonora, WA

Metres Below Down-hole North East RL Dip/ Azimuth Surface Hole Id Mineralised Intersection From To Interval Gold grade m m m degrees m m m m Au g/t JARC004 6611 6504 5076 -66/256 304 324 325 1.4 1.8 JARD022 6617 6553 5090 -65/276 290 306 307 1.1 1.2 JARD023 6760 6388 5306 -75/248 74 59 61 2.0 1.5 JARD023 6759 6387 5301 -75/248 79 64 66 2.3 1.1 NOTES: Dip and Azimuth angles estimated at intercept depth. Coordinates and Azimuth referenced to Gwalia Local Mine Grid. Reported intercepts are all down hole lengths. Numbers have been rounded to one significant figure.

Table 3: Cricket Pitch Significant Intercepts – Leonora, WA

Metres Below Down-hole North East RL Dip/ Azimuth Surface Mineralised Intersection Hole Id From To Interval Gold grade m m m degrees m m m m Au g/t CPDD001 7033 7620 5189 -57/255 191 222 223 0.7 3.8 NOTES: Dip and Azimuth angles estimated at intercept depth. Coordinates and Azimuth referenced to Gwalia Local Mine Grid. Reported intercepts are all down hole lengths. Numbers have been rounded to one significant figure.

Table 4: Horse Paddock Well Significant Intercepts – Leonora, WA Metres Below Down-hole North East RL Dip/ Azimuth Surface Mineralised Intersection Hole Id From To Interval Gold grade m m m degrees m m m m Au g/t HWRC0015 6820887 325648 403 -61/238 102 114 115 1 5.3 HWRC0018 6819478 325542 399 -62/234 21 23 24 1 2.6

For personal use only use personal For HWRC0018 6819478 325542 399 -62/234 25 27 29 2 1.8 NOTES: Coordinates and Azimuth referenced to MGA94 zone 51 Grid. Reported intercepts are all down hole lengths. Dip and azimuth represent drill hole at collar. Numbers have been rounded to one significant figure.

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xvii

Table 5: Trevor Bore Significant Intercepts – Leonora, WA Metres Dip/ Down-hole North East RL Below Azimuth Mineralised Intersection Hole Id Surface From To Interval Gold grade m m m degrees m m m m Au g/t TBRC004 6818259 327213 394 -60/198 117 134 143 9 1.6 TBRC006 6818031 327433 395 -60/200 78 90 92 2 2.3 TBRC006 6818031 327433 395 -60/200 112 125 135 10 2.4 Incl. 109 125 129 4 5.1 NOTES: Coordinates and Azimuth referenced to MGA94 zone 51 Grid. Reported intercepts are all down hole lengths. Dip and azimuth represent drill hole at collar. Numbers have been rounded to one significant figure.

Table 6: Pinjin Aircore Significant Intercepts – Yilgarn, WA

Dip/ Total Down-hole North East RL Azimuth Depth Mineralised Intersection Hole Id From To Interval Gold grade m m m degrees m Comments m m m Au ppb PJAC2773 6,654,497 446,720 328.4 -65 / 271 49 34 35 1 881 Transported PJAC2775 6,654,694 446,821 328.6 -65 / 271 48 38 40 2 630 OX PJAC2783 6,655,001 446,747 328.7 -65 / 271 50 33 35 2 14,139 OX including 33 34 1 27,400 OX 43 44 1 1070 OX PJAC2787 6,655,099 446,722 328.7 -65 / 271 46 44 45 1 617 OX PJAC2792 6,655,199 446,671 325.1 -65 / 271 34 19 20 1 723 OX PJAC2996 6,628,250 471,302 399.9 -60 / 271 81 68 72 4 650 OX PJAC3004 6,628,044 470,951 398.1 -60 / 270 101 68 72 4 587 OX NOTES: Coordinates and Azimuth referenced to MGA94 zone 51 Grid. Reported intercepts are all down hole lengths. OX: oxide, FR: fresh, TR: transitional material.

Table 7: Lake Wells Aircore Significant Intercepts – Yilgarn, WA

Down-hole North East RL Dip/ Azimuth Total Depth Mineralised Intersection Hole Id From To Interval Gold grade m m m degrees m Comments m m m Au ppb LWAC0254 6,958,000 543,795 512.0 -60 / 272 50 34 35 1 523 OX NOTES: Coordinates and Azimuth referenced to MGA94 zone 51 Grid. Reported intercepts are all down hole lengths. OX: oxide, FR: fresh, TR: transitional material. only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xviii

Table 8: Sorowar Significant Intercepts – Simberi Island, Papua New Guinea Dip/ Total Down-hole North East RL Azimuth Depth Mineralised Intersection Hole Id Gold From To Interval m m M degrees m grade Comments m m m g/t Au -60 / SORDGC001 210,219 44,329 165 208 114 142 28 1.37 TR,SU (165SORDGC001) 030 167 171 4 1.85 SU -60 / SORDGC002 210,164 44,290 165 184 82 101 19 4.96 OX,TR,SU (165SORDGC002) 030 Including 89 90 1 67.2 TR 154 156 2 6.51 SU 176 181 5 2.86 SU -60 / SORDGC003 210,120 44,272 165 200 65 69 4 1.48 TR (165SORDGC003) 030 174 182 8 1.86 SU 187 198 11 1.05 SU -60 / SORDGC004 210,151 44,221 165 220 35 44 9 1.60 OX (165SORDGC004) 030 -60 / SORDGC005 210,186 44,177 165 78 10 14 4 4.62 OX (165SORDGC005) 030 -60 / SORDGC006 210,200 44,249 165 200 136 138 2 3.12 SU (165SORDGC006) 030 151 168 17 1.62 SU -60 / SORDGC007 210,278 44,432 165 200 38 43 5 3.67 SU (165SORDGC007) 030 60 80 20 8.42 TR,SU 89 104 15 7.08 SU 113 138 25 1.20 SU -60 / SORDGC008 210,221 44,400 159 200 136 145 9 1.76 SU (165SORDGC008) 030 150 166 16 1.54 SU 182 200 18 1.49 SU -60 / SORDGC009 210,256 44,281 165 200 41 46 5 1.21 SU (165SORDGC009) 030 82 87 5 3.87 OX,TR,SU 144 148 4 1.99 SU -60 / SORDGC010 210,281 44,230 165 204 36 41 5 2.25 OX (165SORDGC010) 030 53 55 2 2.85 TR 58 68 10 2.46 OX,TR,SU 73 75 2 2.83 SU 137 144 7 0.98 SU -60 / SORDGC011 210,163 44,367 165 239 171 176 5 6.65 SU (165SORDGC011) 030

196 215 19 2.65 SU For personal use only use personal For 221 229 8 0.96 SU -60 / SORDGC012 209,938 44,237 165 216 25 34 9 2.56 SU (165SORDGC012) 030 110SRDH001 209,954 44,652 110 -60/030 250 28 36 8 0.91 OX 38 42 4 1.54 OX 44 48 4 5.24 OX

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xix

Dip/ Total Down-hole North East RL Azimuth Depth Mineralised Intersection Hole Id Gold From To Interval m m M degrees m grade Comments m m m g/t Au 59 62 3 2.68 SU 106 109 2 1.08 SU 130 138 8 1.28 SU 160 187 27 2.60 SU 110SRDH002 209,973 44,628 110 -60/030 144 21 32 11 8.62 SU 129 144 15 5.08 SU,EOH 120SRDH006 209,918 44,434 120 -60/030 186 No significant results 125SRDH007 210,061 44,343 125 -60/030 250 73 80 7 1.54 OX 144 150 6 1.94 OX,TR,SU

125SRDH008 210,035 44,468 125 -60/030 250 80 87 7 1.47 TR,SU 100 111 11 4.47 OX,TR,SU Including 101 102 1 34.2 OX 169 172 3 1.07 SU 125SRDH011 210,080 44,461 125 -60/030 250 41 43 2 1.51 OX 48 54 6 1.42 OX,TR,SU 56 60 4 1.25 TR,SU 75 87 12 12.8 SU Including 76 78 2 58.7 SU 217 220 3 0.95 SU 125SRDH012 210,060 44,482 125 -60/030 250 184 194 10 1.44 SU 125SRDH013 210,067 44,326 125 -60/030 250 71 80 9 1.09 OX,SU 115 117 2 0.98 OX,SU 146 149 3 0.82 SU 152 156 4 0.81 SU 242 244 2 1.37 SU 125SRDH014 210,088 44,430 125 -60/030 250 52 63 11 4.26 SU 82 84 2 2.37 SU 206 210 4 0.85 SU 217 222 5 0.86 SU 125SRDH015 210,063 44,415 125 -60/030 250 45 56 11 13.2 SU Including 45 46 1 70.2 SU 61 64 3 0.87 SU

For personal use only use personal For 221 222 1 4.11 SU 228 230 2 0.75 SU 125SRDH016 210,100 44,373 125 -60/030 250 120 123 3 0.83 SU 160 163 3 7.08 TR,SU Including 161 162 1 18.5 SU 163 169 6 0.64 SU

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xx

Dip/ Total Down-hole North East RL Azimuth Depth Mineralised Intersection Hole Id Gold From To Interval m m M degrees m grade Comments m m m g/t Au 125SRDH017 210,264 44,184 125 -60/030 250 36 41 5 1.28 SU 104 108 4 0.93 SU 125SRDH018 210,178 44,308 125 -60/030 250 27 30 3 0.91 SU 117 121 4 3.50 SU 220 223 3 1.01 SU 135SRDH005 209,866 44,474 135 -60/030 138 62 97 35 2.21 SU 135SRDH006 209,865 44,508 135 -60/030 144 16 20 4 1.41 SU 77 81 4 21.5 SU Including 77 78 1 73.4 SU 86 89 3 0.83 SU 102 121 19 2.99 SU Including 110 111 1 22.4 SU 135SRDH007 209,868 44,544 136 -60/030 150 82 85 3 1.86 SU 88 92 4 1.23 SU 102 111 9 3.31 SU 114 125 11 2.31 SU 135SRDH008 209,889 44,614 135 -60/030 176 16 28 12 1.51 TR,SU 41 43 2 2.59 SU 49 51 2 2.07 SU 134 140 6 1.10 SU 145SRDH021 210,193 44,697 140 -60/054 250 126 132 6 0.83 SU 235 239 4 1.22 SU 242 247 5 1.31 SU 145SRDH022 210,173 44,686 141 -60/030 250 172 174 2 1.06 SU 145SRDH023 210,136 44,664 141 -90 250 24 40 16 1.72 OX,TR,SU 101 108 7 8.63 SU Including 101 104 3 17.4 SU 145SRDH024 210,142 44,668 140 -60/030 174 44 52 8 1.99 SU 56 71 15 2.23 SU 119 125 6 3.27 SU 138 142 4 1.42 SU 145SRDH025 210,118 44,688 137 -60/030 250 114 118 4 4.73 SU 207 217 10 2.78 SU 145SRDH026 210,144 44,704 138 -60/030 250 97 103 6 1.58 SU 107 119 12 2.48 SU

For personal use only use personal For 210 214 4 0.86 SU 145SRDH027 210,148 44,764 132 -60/030 250 56 60 4 1.18 SU 219 223 4 1.09 SU 145SRDH028 210,168 44,483 141 -60/030 250 114 120 6 3.35 SU 124 127 3 0.92 SU 161 175 14 2.38 SU

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xxi

Dip/ Total Down-hole North East RL Azimuth Depth Mineralised Intersection Hole Id Gold From To Interval m m M degrees m grade Comments m m m g/t Au 145SRDH029 210,108 44,736 134 -60/030 250 64 77 13 0.85 SU 88 93 5 1.37 SU 100 102 2 1.56 SU 112 114 2 1.34 SU 222 230 8 1.60 SU 233 237 4 1.53 SU 245 250 5 1.11 SU,EOH 150SRDH024 210,182 44,634 143 -60/030 250 108 111 3 0.78 SU 198 203 5 1.21 SU 208 218 10 1.95 SU 150SRDH036 210,300 44,540 150 -90 84 48 61 13 1.64 SU 78 81 3 1.92 SU 83 84 1 2.78 SU,EOH 150SRDH039 210,220 44,367 150 -90 250 152 154 2 4.43 SU 150SRDH040 210,283 44,333 150 -90 250 60 63 3 1.10 SU 65 69 4 0.84 SU 89 94 5 0.63 SU 131 133 2 3.75 SU 137 143 6 1.73 SU

150SRDH041 210,121 44,552 150 -60/030 250 59 63 4 0.88 SU 84 87 3 0.76 SU 150SRDH043 210,286 44,301 149 -90 250 65 84 19 1.83 OX,TR,SU 93 97 4 1.26 SU 105 114 9 1.53 SU 150SRDH044 210,253 44,558 150 -90 250 118 121 3 2.48 SU 138 143 5 0.69 SU 149 157 8 1.40 SU 158 162 4 0.81 SU 203 205 2 1.96 SU 150SRDH045 210,315 44,491 154 -90 248 60 69 9 1.04 SU 77 80 3 1.64 SU 105 127 22 0.99 OX,TR,SU 136 161 25 3.09 SU 163 181 18 2.10 SU

For personal use only use personal For Including 168 169 1 18.6 SU 192 194 2 1.30 SU 230 236 6 0.73 SU 150SRDH046 210,325 44,497 155 -60/030 250 111 119 8 4.69 SU 174 176 2 1.24 SU 204 210 6 1.66 SU

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xxii

Dip/ Total Down-hole North East RL Azimuth Depth Mineralised Intersection Hole Id Gold From To Interval m m M degrees m grade Comments m m m g/t Au 210 222 12 0.66 SU 231 233 2 2.52 SU 236 240 4 0.98 SU 243 245 2 10.8 SU 150SRDH047 210,303 44,541 149 -60/030 250 36 38 2 0.89 SU 49 69 20 0.81 OX,TR,SU 74 86 12 0.80 SU 115 130 15 0.75 SU 150 156 6 1.23 SU 164 182 18 3.62 SU 200 202 2 1.66 SU 231 234 3 2.44 SU 150SRDH048 210,199 44,562 150 -90 250 191 198 7 1.48 SU 150SRDH049 210,203 44,565 150 -60/030 250 186 188 2 1.39 SU 191 200 9 0.88 SU 200 207 7 1.35 SU 247 250 3 1.21 SU,EOH 175SRDH026 210,511 44,396 175 -60/030 250 No significant intersections 175SRDH027 210,497 44,387 175 -60/030 246 No significant intersections 175SRDH028 210,466 44,328 175 -60/030 250 No significant intersections 175SRDH029 210,431 44,246 175 -60/030 250 35 38 3 1.06 SU 47 55 8 0.80 SU 207 210 3 2.39 SU 175SRDH030 210,432 44,200 175 -60/030 250 No significant assays 175SRDH031 210,415 44,121 175 -60/030 250 100 104 4 2.27 SU 175SRDH032 210,403 44,180 175 -60/030 250 44 47 2 0.75 SU 83 85 2 1.71 SU 135 137 2 1.16 SU 180SRDH004 210,315 43,925 180 -60/030 200 39 54 15 2.31 OX 57 60 3 2.53 OX,SU 152 164 12 1.27 SU 174 190 16 2.07 SU 198 200 2 1.07 SU,EOH 185SRDH017 210,451 44,073 185 -90 200 40 43 3 1.14 SU 61 65 4 0.96 SU

For personal use only use personal For 65 71 6 2.22 SU 102 106 4 2.24 SU 108 113 5 1.10 SU 153 156 3 0.97 SU 164 166 2 1.21 SU 185SRDH021 210,413 43,912 186 -90 200 81 83 2 1.37 TR

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xxiii

Dip/ Total Down-hole North East RL Azimuth Depth Mineralised Intersection Hole Id Gold From To Interval m m M degrees m grade Comments m m m g/t Au 92 94 2 2.52 SU 113 117 4 1.56 SU 123 145 22 1.03 SU 147 158 11 0.84 SU 163 167 4 1.25 SU 174 176 2 2.18 SU 178 181 3 1.26 SU 183 190 7 1.56 SU 215SRDH002 210,024 44,013 217 -60/030 252 115 147 32 1.56 SU 215SRDH003 209,971 44,052 214 -60/030 252 37 39 2 1.76 TR,SU 81 86 5 0.90 SU 89 96 7 1.23 SU 129 132 3 1.31 SU 136 143 7 1.07 SU 145 153 8 0.85 SU 215SRDH005 209,974 43,980 219 -90 252 29 42 13 1.38 SU 47 74 27 1.60 SU 174 180 6 0.79 SU 215SRDH006 210,019 44,080 218 -60/030 252 31 39 8 1.84 SU 65 101 36 0.82 SU 114 133 19 0.61 SU 215SRDH007 209,956 44,109 214 -90 252 42 45 3 1.15 SU 56 61 6 0.68 SU 67 82 15 0.83 SU 215SRDH008 209,986 44,129 214 -60/030 252 No significant results

215SRDH009 210,001 43,975 220 -60/030 250 17 27 10 0.80 OX 35 41 6 1.42 SU 53 56 3 0.87 SU 63 72 9 0.60 SU 158 165 7 1.12 SU 215SRDH010 210,028 43,990 218 -60/030 250 0 7 7 1.13 OX 10 19 9 0.62 OX 53 56 3 1.01 SU 104 108 4 0.85 SU

For personal use only use personal For 229 233 4 0.89 SU 215SRDH011 210,054 44,005 214 -60/030 250 7 27 20 0.89 OX 50 53 3 0.73 SU 88 103 15 1.66 SU 164 166 2 1.20 SU 215SRDH012 209,974 43,964 221 -60/030 250 0 8 8 0.91 OX

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xxiv

Dip/ Total Down-hole North East RL Azimuth Depth Mineralised Intersection Hole Id Gold From To Interval m m M degrees m grade Comments m m m g/t Au 34 37 3 0.95 OX 42 49 7 0.87 OX,TR 54 56 2 1.09 TR 61 64 3 0.96 SU 72 79 7 0.67 SU 99 103 4 0.78 SU 168 169 3 0.96 SU 177 182 5 0.90 SU 183 188 5 1.30 SU 200 204 4 1.01 SU 215SRDH013 209,991 44,061 215 -60/030 250 31 42 11 1.30 OX,TR,SU 54 57 3 1.64 SU 70 73 3 0.97 SU 119 121 2 1.63 SU 128 130 2 1.39 SU 215SRDH014 210,004 44,103 218 -60/030 250 166 170 4 0.88 SU 215SRDH015 209,977 44,088 214 -60/030 250 70 72 2 0.92 SU 215SRDH016 209,962 44,114 214 -60/030 250 134 136 2 0.96 SU 215SRDH017 209,950 44,072 214 -60/030 250 6 8 2 1.00 TR 23 25 2 1.00 TR 30 33 3 0.78 OX,TR 57 60 3 0.93 SU 148 151 3 0.98 SU 215SRDH018 209,941 44,067 213 -90 250 53 65 12 1.01 SU 82 91 9 1.01 SU 109 112 3 1.20 SU 184 193 9 0.84 SU NOTES: Azimuth referenced to Tabar Island Grid (TIG). Reported intercepts are all down hole lengths.

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xxv

Table 9: Simberi Significant Intercepts – Big Tabar Island, Papua New Guinea

Dip/ Total Down-hole North East RL Azimuth Depth Mineralised Intersection Hole Id Lode Gold Copper From To Interval m m m degrees m grade grade m m m g/t Au % Cu BND010 174,038 47,925 215 -60 / 53 850.3 SU 280 472 192 0.25 0.10 including SU 282 296 14 0.66 0.20 SU 484 510 26 0.39 0.24 including SU 486 494 8 0.85 0.42 SU 528 552 24 0.15 0.04 BND011 173,926 47,668 242 -60 / 71 51.1 No Significant Results NOTES: Coordinates and Azimuth referenced to Tabar Island Grid (TIG). Reported intercepts are all down hole lengths. OX: oxide, SU: sulphide, TR: transitional material.

Table 10: Cochrane Hill Significant Intercepts – Sherbrooke, Nova Scotia

Dip/ Total Down-hole East North RL Azimuth Depth Mineralized Intersection Hole Id From To Interval Gold grade m m m degrees m m m m Au g/t CH-19-335 3050 3220 117 -68 180 302 243 244 1 10.25 248 249 1 19.55 253 268 15 2.17 280 287 7 1.68 CH-19-336 3475 3171 133 -52 180 181 159 168 9 1.14 174 175 1 6.00 CH-19-337 3477 3200 133 -54 180 212 193 198 5 1.74 CH-19-338 3226 3269 123 -65 180 341 271 272 1 3.70 289 295 6 0.74 299 312 13 0.65 328 330 2 3.31 CH-19-339 3450 3160 134 -52 180 190 173 177 4 6.76 176 177 1 23.00 CH-19-340 3175 3270 120 -61 180 341 248 249 1 7.65 290 300 10 1.01 305 306 1 93.70 CH-19-341 3450 3180 133 -54 180 200 152 156 4 2.25 188 189 1 6.82 CH-19-342 3400 3210 130 -63 180 272 No Significant Results

CHonly use personal For -19-343 3150 3265 119 -60 180 341 276 289 13 1.81 293 299 6 1.56 304 311 7 1.58 CH-19-344 3375 3220 130 -64 180 302 220 245 25 2.49 Including 234 235 1 21.20 273 274 1 6.58

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xxvi

Dip/ Total Down-hole East North RL Azimuth Depth Mineralized Intersection Hole Id From To Interval Gold grade m m m degrees m m m m Au g/t CH-19-345 3125 3270 117 -62 180 341 286 308 22 3.05 Including 291 292 1 31.10 314 316 2 9.53 320 323 3 1.78 CH-19-346 3325 3240 127 -64 180 295 51 52 1 14.20 229 234 5 3.83 246 249 3 1.63 CH-19-347 3075 3250 120 -69 180 326 289 326 37 0.76! CH-19-348 3275 3210 124 -68 180 290 214 233 19 1.67 251 254 3 1.24 275 283 8 4.04 CH-19-349 3382 3057 131 -50 180 152 6.6 17 10.4 0.59 24 37 13 3.25 Including 35 36 1 31.40 46 47 1 5.32 54 55 1 4.32 CH-19-350 2950 3240 112 -59 180 275 153 154 1 7.14 214 216 2 3.03 249 255 6 0.86 CH-19-351 3525 3170 132 -49 171 250 162 163 1 4.34 CH-19-352 3500 3170 133 -54 171 188 157 164 7 2.61 175 179 4 2.71 NOTES: Coordinates and azimuth referenced to CH Mine Grid. Reported intercepts are all down hole lengths.

Assay results are Fire Assays of 50g charge from 1kg pulverized sub-sample split from 2mm crushed parent of sawn half 1m NQ core. ! Mineralization to the end of hole. Table includes all assay results which are deemed significant (≥0.5g/t), with [Sample Length (m) * Gold Assay (g/t Au) ≥ 3.0g/t Au*m], with up to 3m internal dilution.

Table 11: Beaver Dam Significant Intercepts – Beaver Dam, Nova Scotia

Dip/ Total Down-hole East North RL Azimuth Depth Mineralized Intersection Hole Id From To Interval Gold grade m m m degrees m m m m Au g/t CAMERON FLOWAGE

CF-19-007 522321 4991046 130 -45 155 200 138 139 1 6.15 For personal use only use personal For 182 183 1 1.23 CF-19-008 522297 4990980 130 -45 155 170 81 82 1 1.97 136 141 5 0.99 CF-19-009 522231 4990941 130 -45 155 170 58 59 1 0.65 CF-19-010 522215 4990994 130 -45 155 200 90 91 1 1.44 104 107 3 1.35

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xxvii

Dip/ Total Down-hole East North RL Azimuth Depth Mineralized Intersection Hole Id From To Interval Gold grade m m m degrees m m m m Au g/t CF-19-011 522512 4991022 130 -45 155 152 97 100 3 0.83 106 107 1 0.55 109 111 2 2.07 CF-19-012 522457 4991108 130 -45 155 230 179 180 1 2.30 CF-19-013 522164 4991028 130 -45 155 245 183 184 1 2.78 CF-19-014 522608 4991129 130 -45 155 209 175 176 1 0.53 CF-19-015 522097 4991052 130 -45 155 219.3 195 196 1 8.00 CRUSHER LAKE CR-19-001 523259 4989755 130 -45 190 155 No Significant Results CR-19-002 522652 4989694 130 -45 190 161 No Significant Results CR-19-003 521433 4989690 130 -45 190 152 No Significant Results CR-19-004 520654 4989881 130 -45 190 120 No Significant Results CR-19-005 520704 4989622 130 -45 190 17 No Significant Results CR-19-006 521842 4989361 130 -45 190 104 No Significant Results CR-19-007 523000 4989813 130 -45 190 98 No Significant Results CR-19-008 522953 4989601 130 -45 190 101 No Significant Results CR-19-009 522914 4989378 130 -45 190 101 No Significant Results MILL SHAFT MS-19-005 521281 4990466 130 -45 190 110 No Significant Results MS-19-006 521224 4990595 130 -45 190 212 140 141 1 1.03 MS-19-007 521208 4990481 130 -45 190 152 No Significant Results MS-19-008 521155 4990610 130 -45 190 218 155 156 1 4.07 MS-19-009 521052 4990509 130 -45 190 152 No Significant Results MS-19-010 521455 4990560 130 -45 190 200 No Significant Results MS-19-011 521437 4990460 130 -45 190 140 No Significant Results NOTES: Coordinates and azimuth referenced to NAD83 zone 20. Reported intercepts are all down hole lengths.

Assay results are Fire Assays of 50g charge from 1kg pulverized sub-sample split from 2mm crushed parent of sawn half 1m NQ core. ! Mineralization to the end of hole. Table includes all assay results which are deemed significant (≥0.5g/t), with [Sample Length (m) * Gold Assay (g/t Au) ≥ 0.5g/t Au*m], with up to 1m internal dilution.

Table 12: Fifteen Mile Stream Significant Intercepts – Halifax, Nova Scotia

Dip/ Total Down-hole East North RL Azimuth Depth Mineralized Intersection Hole Id From To Interval Gold grade m m m degrees m For personal use only use personal For m m m Au g/t SELOAM BROOK SB-19-028 12300 9985 122 45 175 152 63 70 7 0.79 SB-19-029 12100 10085 131 -45 175 164 No Significant Results SB-19-030 12100 9845 115 -45 175 197 56 60 4 0.84 SB-19-031 12100 10240 127 -45 175 188 81 85 4 9.73

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xxviii

Dip/ Total Down-hole East North RL Azimuth Depth Mineralized Intersection Hole Id From To Interval Gold grade m m m degrees m m m m Au g/t Including 81 82 1 38.00 91 92 1 4.63 149 151 2 1.71 174 180 6 2.22 SB-19-032 12100 9965 125 -45 175 191 59 64 5 0.87 123 129 6 0.53 170 190 20 0.57 SB-19-033 11900 10095 123 -45 175 212 SB-19-034 11950 9960 117 -45 175 176 57 64 7 0.64 87 94 7 0.92 SB-19-035 11650 10015 105 -45 175 194 SB-19-036 11850 9920 105 -45 175 191 SB-19-037 11700 9965 104 -45 175 191 SB-19-038 11750 9965 105 45 175 236 SB-19-039 11600 9860 103 45 175 209 SB-19-040 11900 9850 105 45 175 197 NOTES: Coordinates and azimuth referenced to FMS Mine Grid. Reported intercepts are all down hole lengths.

Assay results are Fire Assays of 50g charge from 1kg pulverized sub-sample split from 2mm crushed parent of sawn half 1m NQ core. ! Mineralization to the end of hole. Table includes all assay results which are deemed significant (≥0.5g/t), with [Sample Length (m) * Gold Assay (g/t Au) ≥ 3.0g/t Au*m], with up to 3m internal dilution.

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xxix

LEONORA – JORC Code, 2012 Edition – Table 1

Contents

Gwalia Deeps Drilling: Section 1 Sampling Techniques and Data

Section 2 Reporting of Exploration Results

Jesse Alma and Cricket Pitch Drilling: Section 1 Sampling Techniques and Data

Section 2 Reporting of Exploration Results

Horse Paddock Well and Trevor Bore Drilling: Section 1 Sampling Techniques and Data

Section 2 Reporting of Exploration Results

Gwalia Deeps Drilling - Section 1 Sampling Techniques and Data (Criteria in this section apply to all succeeding sections.)

Criteria Commentary Sampling techniques • Half-core sampling of NQ2 diamond drilling with boundaries defined geologically. Samples are mostly one metre in length unless a significant geological feature warrants a change from this standard unit. The upper or right-hand side of the core is submitted for sample analysis, with each one metre of half core providing between 2.5 – 3 kg of material as an assay sample. Drilling techniques • Diamond drilling using NQ2 (50.6mm) sized core (standard tubes). Holes have been surveyed using a north seeking multishot electronic camera. All core is orientated using a Reflex ACT III RD orientation tool. Drill sample recovery • Core is metre marked and orientated and checked against drillers blocks to ensure that any core loss is accounted for. • Sample recovery is rarely less than 100%. Where minor core loss does occur it is due to drilling conditions and not ground conditions. Logging • All SBM holes are logged primarily for lithology, alteration and vein type/intensity which are key to modelling gold grade distributions. Validation of geological data is controlled via the use of library codes and reliability and consistency of data is monitored through regular peer review. • All logging is qualitative. Sub-sampling • SBM half core is cut using a core saw before being sent to SGS laboratory in Kalgoorlie where the entire sample is crushed techniques and to achieve particle size <4mm followed by complete pulverisation (90% passing 75 µm). sample preparation Quality of assay data • SBM samples were analysed for gold using fire assay with a 50g charge and analysis by flame Atomic Absorption(FAA505) and laboratory tests Spectrometry (AAS). QC includes insertion of 3 commercial standards (1 per 20 samples), barren material used for blank control samples, use of barren flush material between designated high grade samples during the pulverising stage, re- numbered sample pulp residues re-submitted to original laboratory, and sample pulp residues submitted to accredited umpire laboratory, submission of residual (duplicate) half core from ore intervals. The analysis of gold was sound and re- analysis of pulps showed acceptable repeatability with no significant bias. Verification of • Sampling data is recorded electronically in spread sheets which ensure only valid non-overlapping data can be recorded. sampling and Assay and down hole survey data are subsequently merged electronically. All drill data is stored in a SQL database on assaying secure company server. Location of data • Collars for surface holes are recorded by DGPS. Upon completion of surface drill holes an authorised surveyor or trained points delegate will pick up the collar. • All coordinates and Azimuth are specified in using the Gwalia Local Mine Grid (LE_SGMG). The two-point transformation of MGA_51 to LE_SGMG is detailed below:

Grid Azimuth MGAE 1 MGAN 1 MGAE 2 MGAN 2 GridE 1 GridN 1 GridE 2 GridN 2 Rotation Scale

LE_SGMG Sons of 15.13 337371.157 6800342.586 340246.451 6799408.751 7200.281 6987.844 10219.711 6836. 814 344.522 1 Gwalia Mine Grid

Data spacing and • Surface drilling is spaced on an approximate 60m x 80m below 1,850 metres below surface. Drilling data is sufficient to distribution establish down plunge continuity for all lodes.

For personal use only use personal For Orientation of data • Sampling is perpendicular to lode orientations and is sound-based on past production and underground mapping. in relation to geological structure Sample security • Company personnel or approved contractors only allowed on drill sites; drill samples are only removed from drill site by approved contractors to the company’s secure core logging/processing facility; cut core is consigned to accredited laboratories for sample preparation and analysis.

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xxx

Criteria Commentary Audits or reviews Regular reviews of core logging and sampling are completed through SBM mentoring and auditing. Additionally, regular laboratory inspections are conducted by SBM personnel. Inspections are documented electronically and stored on secure company server. No significant issues were identified.

Gwalia Deeps Drilling - Section 2 Reporting of Exploration Results (Criteria listed in the preceding section also apply to this section.)

Criteria Commentary Mineral tenement • SBM has 100% ownership of the three tenements M37/25, M37/849 and M37/333 over the Gwalia deposit. and land tenure status Exploration done by • Western Mining Corporation (WMC) and Sons of Gwalia (SGW), have previously completed deep diamond drilling below other parties 1,100 metres below surface. Geology • Gold mineralisation occurs as a number of stepped, moderately east dipping, foliation parallel lodes within strongly potassic altered mafic rocks which extend over a strike length of approximately 500 metres and to a vertical depth of at least 2,200 metres below surface. The deposit exhibits significant down-plunge continuity but is interrupted at approximately 1,200 metres below surface (mbs) by a cross cutting post-mineralisation doleritic dyke, with a horizontal width of approximately 30 metres. Drill hole Information • Drill hole information is included in intercept table outlining mid-point co-ordinates including vertical hole depth and composited mineralized intercepts lengths and depth. Data aggregation • Down hole intercepts are reported as length weighted averages. No high grade cut is applied. methods Relationship between • Down hole length is reported for all holes; true width is not immediately known until further drilling is completed and mineralisation widths the orebody modelled. and intercept lengths Diagrams • Appropriate diagrams are included within the body of the report. Balanced reporting • Details of all holes material to Exploration Results have been reported in the intercept table. Other substantive • These holes test the deepest limits and extents of mineralisation and no other data is available. exploration data Further Work • Further exploration drill holes are planned.

Jessie Alma and Cricket Pitch Drilling - Section 1 Sampling Techniques and Data (Criteria in this section apply to all succeeding sections.)

Criteria Commentary Sampling techniques • Half-core sampling of NQ2 diamond drilling with boundaries defined geologically. Samples are mostly one metre in length unless a significant geological feature warrants a change from this standard unit. The upper or right-hand side of the core is submitted for sample analysis, with each one metre of half core providing between 2.5 – 3 kg of material as an assay sample. Drilling techniques • Jessie Alma, drilling comprised a combination of reverse circulation (RC) drilling pre-collars and diamond drilling tails. A multipurpose exploration drill rig, Sandivik DE840, was utilised by DDH1 during the drilling program. • At Cricket Pitch only diamond drilling was conducted where an underground coring electric drill rig, Boart Longyear LM75, was used by DDH1. • Diamond drilling has used NQ2 (50.6mm) sized core (standard tubes). Holes have been surveyed using a north seeking multishot electronic camera. All core is orientated using a Reflex ACT III RD orientation tool. Drill sample recovery • Core is metre marked and orientated and checked against drillers blocks to ensure that any core loss is accounted for. • Sample recovery is rarely less than 100%. Where minor core loss does occur it is due to drilling conditions and not ground conditions. Logging • All SBM holes are logged primarily for lithology, alteration and vein type/intensity which are key to modelling gold grade distributions. Validation of geological data is controlled via the use of library codes and reliability and consistency of data is monitored through regular peer review. • All logging is qualitative.

Sub-sampling • SBM half core is cut using a core saw before being sent to SGS laboratory in Kalgoorlie where the entire sample is crushed For personal use only use personal For techniques and to achieve particle size <4mm followed by complete pulverisation (90% passing 75 µm). sample preparation Quality of assay data • SBM samples were analysed for gold using fire assay with a 50g charge and analysis by flame Atomic Absorption(FAA505) and laboratory tests Spectrometry (AAS). QC includes insertion of 3 commercial standards (1 per 20 samples), barren material used for blank control samples, use of barren flush material between designated high grade samples during the pulverising stage, re- numbered sample pulp residues re-submitted to original laboratory, and sample pulp residues submitted to accredited umpire laboratory, submission of residual (duplicate) half core from ore intervals. The analysis of gold was sound and re- analysis of pulps showed acceptable repeatability with no significant bias.

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xxxi

Criteria Commentary Verification of • Primary geological and sampling data were recorded into made for purpose excel spreadsheets, peer reviewed and sampling and validated by SBM Geologists. assaying • Data was then transferred into the St Barbara corporate database (Datashed) where it was further validated by an experienced database geologist. • No adjustments to assay data were made. Location of data • Prior to drilling, all holes were marked out using a handheld GPS with ±3 m accuracy for easting, northings and ±10 m points elevation. • Upon completion of the program, all holes were surveyed by the Gwalia mine surveyors using a Leica GS16 base and rover system to determine the final collar positions in MGA94 Zone 51 grid. • Downhole surveys were taken by the drilling contractor at 30 m intervals utilising a Reflex multishot north seeking solid state gyro system. Data spacing and • Drilling targeted individual geophysical targets and was not designed on a pattern spacing grid. distribution • No historic drilling had been completed in the immediate vicinity of the holes drilled in this program. Orientation of data • The regional stratigraphy trend N-S and dips approximately 30 degrees to the E. in relation to • Drill hole dips were typically -60 degrees, with an azimuth of 270 degrees (National Grid). geological structure • Drill hole orientation was consistent with historic drilling completed over the prospect, drilled towards the west (270 degrees azimuth) on the MGA94 Zone 51 grid. Sample security • Company personnel or approved contractors only allowed on drill sites; drill samples are only removed from drill site by company employees and transported to the company’s secure processing facility. Processed samples are consigned to accredited laboratories for sample preparation and analysis. Audits or reviews • Logging and sampling data was peer reviewed in-house by SBM Geologists.

Jessie Alma and Cricket Pitch Drilling - Section 2 Reporting of Exploration Results (Criteria listed in the preceding section also apply to this section.)

Criteria Commentary Mineral tenement • SBM has 100% ownership of the tenements M37/0025 and M37/0903 in which the drilling was completed. and land tenure status Exploration done by • Numerous shallow workings exist in the project area. other parties • Exploration activities including RAB and RC drilling by Sons of Gwalia and more recently, evaluation of previous geological data and re-processed magnetics and gravity dataset by Southern Geoscience. • Small scale underground mining was conducted to around 30m below surface which is reported to be about the same level as the water table. Geology Jessie Alma: • Project area is located in the Leonora area of the Norsema-Wiluna Archean greenstone. • The project is situated on the eastern flank of the intusive Raeside granite batholith which is overlain by steeply east dipping ultramafics, in places displaying strong alteration to talc chlorite schist, and mafics (basalts) the latter of which form the footwall sequence to the Gwalia deposit. • Project area hosts a sequence of basalts, talc-chlorite ultramafics, gabbroic/doleritic sills and interflow sediments. Cricket Pitch: • Project area is located in the Leonora area of the Norsema-Wiluna Archean greenstone. • The project is situated on the eastern flank of the intusive Raeside granite batholith which is overlain by steeply east dipping ultramafics, in places displaying strong alteration to talc chlorite schist, and mafics (basalts) the latter of which form the footwall sequence to the Gwalia deposit. • Project area hosts a sequence of basalts, talc-chlorite ultramafics, gabbroic/doleritic sills and interflow sediments. Drill hole Information • Drill hole information for holes returning significant results have been reported in the intercept talble outlining the collar co-ordinates and includes drilled depth, hole dip and azimuth and composited mineralised intercept lengths and depth. Data aggregation • Down hole intercepts are reported as length weighted averages. methods • No high grade cut is applied. Relationship between • Down hole length is reported for all holes; true width is not known as the orientation of mineralisation is not fully mineralisation widths understood. and intercept lengths Diagrams • Appropriate diagrams are included within the body of the report. For personal use only use personal For Balanced reporting • Details of all holes material to Exploration Results have been reported in the intercept table. Other substantive • Data is included in the body of the report. exploration data • The Cricket Pitch zone is located north of Gwalia mine and west of well-known landmark, Mt Leonora, which represents a significant cultural element in the region Further Work • Further exploration drill holes are planned. Balanced reporting • Details of all holes material to Exploration Results have been reported in the intercept table.

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xxxii

Criteria Commentary Other substantive • Data is included in the body of the report. exploration data

Horse Paddock Well and Trevor Bore Drilling - Section 1 Sampling Techniques and Data (Criteria in this section apply to all succeeding sections.)

Criteria Commentary Sampling techniques RC Drilling • Sampling was conducted via Reverse Circulation(RC) drilling. • One metre samples were generated by a rig-mounted cyclone splitter. One half of the split sample collected in calico bags and the other, collected by a bucket and placed on the ground in neat rows of thirty. • Samples were transported to the secure onsite processing facility for storage in bulka bags. • Bulka bags were picked up by an SGS laboratory representative and transported to SGS laboratory in Kalgoorlie for fire assay with a 50 g charge and analysis by Flame Atomic Absorption Spectrometry (FAA505 method). • Representative specimens from every metre were sieved, cleaned and stored in plastic chip trays for future reference.

Diamond Drilling • Half-core sampling of NQ2 diamond drilling with boundaries defined geologically. Samples are mostly one metre in length unless a significant geological feature warrants a change from this standard unit. The upper or right-hand side of the core is submitted for sample analysis, with each one metre of half core providing between 2.5 – 3 kg of material as an assay sample. Drilling techniques • RC drilling was carried out using a 132 mm hammer bit. Drilling was completed by TOPDrill who utilised a truck mounted Schramm T685 rig with 1350 cfm/500 psi compressor coupled with an 8x8 carrier mounted auxillary compressor and booster package. • Diamod drilling tail was completed by DDH1 utilising a multipurpose exploration drill rig, Sandivik DE840. • Diamond drilling has used NQ2 (50.6mm) sized core (standard tubes). Holes have been surveyed using a north seeking multishot electronic camera. All core is orientated using a Reflex ACT III RD orientation tool.

Drill sample recovery RC Drilling • RC sample recovery and condition (wet/dry) were routinely recorded. • The drill cyclone and sample buckets were cleaned regularly, in particular after wet ground was encountered. The cyclone was also cleaned several times during the course of each hole and after the completion of each hole. Diamond Drilling • Core is metre marked and orientated and checked against drillers blocks to ensure that any core loss is accounted for. • Sample recovery is rarely less than 100%. Where minor core loss does occur it is due to drilling conditions and not ground conditions. Logging • All drill holes were logged in full for lithology, alteration, veining, weathering/regolith and colour. • All logging is qualitative. Sub-sampling • Samples received by SGS laboratories in Kalgoorlie were sorted, dried, followed by complete pulverisation (90% passing techniques and -75 µm). sample preparation Quality of assay data • Sample charge sizes of 50 g for each one metre sample analysed by fire assay is considered appropriate for the sample and laboratory tests medium (predominantly fresh rock). • Certified reference material was inserted into the sample stream at a ratio of 1:25. • SGS Labraotries inserted certified standards, blanks and replicates and lab repeats. Verification of • Primary geological and sampling data were recorded into made for purpose excel spreadsheets, peer reviewed and sampling and validated by SBM Geologists. assaying • Data was then transferred into the St Barbara corporate DataShed database where it was further validated by an experienced database geologist. • No adjustments to assay data were made. Location of data • Prior to drilling, all holes were marked out using a handheld GPS with ±3 m accuracy for easting, northings and ±10 m points elevation. • Upon completion of the program, all holes were surveyed by the Gwalia mine surveyors using a Leica GS16 base and rover system to determine the final collar positions in MGA94 Zone 51 grid. • Downhole surveys were taken by the drilling contractor at 10 m intervals utilising a multishot north seeking solid state gyro system.

Data spacing and • Drilling targeted individual geophysical targets and was not designed on a pattern spacing grid. For personal use only use personal For distribution • No historic drilling had been completed in the immediate vicinity of the holes drilled in this program. Orientation of data in • The regional stratigraphy strikes NNW and dips approximately 30 degrees to the NE. relation to geological • Drill hole dip was typically -60 degrees. structure • Drill hole orientation was consistent with historic drilling completed over the prospect, drilled towards the west (270 degrees azimuth) on the Horse Paddock Well local grid (Local Grid: Magnetic Grid + 34.37).

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xxxiii

Criteria Commentary Sample security • Company personnel or approved contractors only allowed on drill sites; drill samples are only removed from drill site by company employees and transported to the company’s secure processing facility. Processed samples are consigned to accredited laboratories for sample preparation and analysis. Audits or reviews • Logging and sampling data was peer reviewed in-house by SBM Geologists.

Horse Paddock Well and Trevor Bore Drilling - Section 2 Reporting of Exploration Results (Criteria listed in the preceding section also apply to this section.)

Criteria Commentary Mineral tenement • SBM has 100% ownership of the tenement M37/587 in which the drilling was completed. and land tenure status Exploration done by • Numerous shallow workings exist in the project area. other parties • Exploration activities including RAB drilling, soil sampling and geophysics by groups such as Esso, City Resources and Sons of Gwalia. • Sons of Gwalia undertook shallow (10 m deep) open pit mining of the oxide/lateritic material at the Harlech deposit within the project area. Geology • Project area is located in the Leonora area of the Norseman-Wiluna Archean greenstone. • The project lies between the Mt George Shear Zone to the east, and the Raeside Batholith/greenstone contact to the west. • Project area hosts a sequence of basalts, talc-carbonate schists, gabbroic/doleritic sills and interflow sediments. The sequence is intruded by granitoids and E-W oriented dolerite dykes. Drill hole Information • Drill hole information for holes returning significant results have been reported in the intercept table outlining the collar co-ordinates and includes drilled depth, hole dip and azimuth and composited mineralised intercept lengths and depth. Data aggregation • Down hole intercepts are reported as length weighted averages. methods • No high grade cut is applied. Relationship between • Down hole length is reported for all holes; true width is not known as the orientation of mineralisation is not fully mineralisation widths understood. and intercept lengths Diagrams • Appropriate diagrams are included within the body of the report. Balanced reporting • Details of all holes material to Exploration Results have been reported in the intercept table. Other substantive • Data is included in the body of the report. exploration data Further Work • Further exploration drill holes are planned. Balanced reporting • Details of all holes material to Exploration Results have been reported in the intercept table. Other substantive • Data is included in the body of the report. exploration data

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xxxiv

PINJIN & LAKE WELLS – JORC Code, 2012 Edition – Table 1

Contents

Drilling: Section 1 Sampling Techniques and Data

Section 2 Reporting of Exploration Results

Drilling - Section 1 Sampling Techniques and Data (Criteria in this section apply to the succeeding section.)

Criteria Commentary Sampling techniques • Sampling was conducted via Aircore and RC drilling. Aircore drill holes were on 50 m or 100 m spacing with line spacing ranging between 200 m and 1,600 m or as individual scout lines. RC holes were not designed on any regular spacing. • Samples were collected from a rig-mounted cyclone by bucket and were then placed directly on the ground in neat rows of between ten and fifty (depending on hole depth). • Drill spoil was sampled with a scoop to 4 m composite samples of approximately 2.5 kg. • During RC drilling one metre samples were also generated by the rigs cone splitter system and collected in calico bags, these were left on the ground on top of the corresponding metre of drill spoil. One metre samples are submitted for assaying based on the results of the initial 4m composite sampling. • The Aircore composites were submitted to Bureau Veritas Minerals Pty Ltd - Perth where they were sorted and dried, crushed to 10 mm and pulverised to -75 µm. A 40 g charge of pulverised sample was then digested with aqua regia with a gold analysis by ICP-MS to a detection limit of 1 ppb. The same digested sample was also tested for arsenic by ICP-AES to 1ppm detection limit. • Anomalous Aircore composite samples (>100ppb Au) were subsampled on a metre by metre basis using an aluminium scoop. These samples were submitted to Bureau Veritas Minerals Pty Ltd- Perth where they were sorted and dried, crushed to 10mm and pulverised to -75 μm. A 40 g charge of pulverised sample was then analysed for Au, Pd & Pt by Fire Assay with an ICP-AES finish to a detection limit of 1ppb. • Anomalous RC composite samples (>100 ppb) were subsampled using the previously collected one metre samples from the rigs cone splitter system. These were submitted to Bureau Veritas Minerals Pty Ltd - Perth where they were sorted, dried, crushed to 10 mm and pulverised to -75 µm. A 40 g charge of pulverised sample was then analysed for Au by Fire Assay with an ICP-AES finish to a detection limit of 1 ppb. • Representative specimens from end of hole Aircore rock chips were stored in plastic chip trays for future reference. For RC drilling a representative specimen of every metre was stored in plastic chip trays for future reference. • The EOH Aircore samples, as well as a selection of RC samples, were submitted to Genalysis and were prepared in the same manner as those samples submitted to Bureau Veritas. A 10g charge of pulverised sample was then digested by four acid digestion with analysis by the Scott Halley technique (ICP-OES & ICP-MS to ultra-trace levels) via 4A/OM20 method for 60 elements (Ag, Al, As, Ba, Be, Bi, Ca, Cd, Ce, Co, Cr, Cs, Cu, Dy, Er, Eu, Fe, Ga, Gd, Ge, Hf, Ho, Ln, K, La, Li, Lu, Mg, Mn, Mo, Na, Nb, Nd, Ni, P, Pb, Pr, Rb, Re, S, Sb, Sc, Se, Sm, Sn, Sr, Ta, Tb, Te, Th, Ti, Tl, Tm, U, V, W, Y, Yb, Zn & Zr). Drilling techniques • Aircore drilling was carried out by an 85 mm bit. All holes were drilled to refusal, which was generally at the fresh rock interface. Drilling was carried out by Raglan Drilling who utilised two separate Aircore rigs; a truck mounted R/A 180 Rig with 750 cfm and 350 psi and a track mounted lake rig with 750 cfm and 350 psi. • RC drilling was carried out using 140 to 145 mm hammer bits. Drilling was completed by Raglan Drilling who utilised a truck mounted SCHRAMM T685W rig with Sullair 1150/350 on board air. Drill sample recovery • Sample recoveries and condition (wet/dry) were routinely recorded. • The drill cyclone and sample buckets were cleaned regularly, in particular after wet ground was encountered. The cyclone was also cleaned several times during the course of each hole and after the completion of each hole. Logging • All drill holes were logged in full for lithology, alteration, weathering/regolith and colour. • Aircore and RC logging is both qualitative and quantitative. Sub-sampling techniques • Aircore and RC samples were collected as both dry and wet samples using a sample scoop. and sample preparation • All composite samples were sorted, dried, crushed and pulverised to produce a 40g charge prior to fire assay. • Samples were collected at 1 m intervals and composited in 4 m samples using a scoop to sample individual metre samples. • QC procedures for composite sampling involved the insertion of certified reference material, field duplicates and blanks at ratios of 1:50. • Bureau Veritas inserted certified standards, replicates and lab repeats. Quality of assay data and • The Aircore composite samples used a 40 g charge with an aqua regia digest, which is considered appropriate for

laboratory tests analysis of the regolith dominated sample medium. For personal use only use personal For • The RC composite samples used a 40 g charge for fire assay, which is considered appropriate for gold mineralisation in fresh rock material. • Certified reference material was inserted into the sample stream at a ratio of 1:50. • Field duplicates and blanks were inserted at a ratio of 1:50. • Bureau Veritas inserted certified standards, replicates and lab repeats.

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xxxv

Criteria Commentary Verification of sampling • Primary geological and sampling data were recorded into made for purpose excel spreadsheets. Data was then and assaying transferred into the St Barbara corporate DataShed database where it was validated by an experienced database geologist. • No adjustments to assay data were made. Location of data points • Prior to drilling, all holes were marked out using a handheld GPS with ±3 m accuracy for easting, northings and ±10m elevation. Upon completion of the program, all holes were resurveyed using a DGPS with decimetre accuracy to determine the final collar positions. • No downhole surveys were conducted on Aircore holes. • All RC holes were surveyed downhole by Raglan drilling who captured dip/azimuth readings at five metre intervals using a Reflex gyro tool. The gyro tool provides True North Azimuth. • All locations were captured in MGA94 zone 51 grid. Data spacing and • Aircore drill holes were on 50 m or 100 m spacing with line spacings ranging between 200 m and 600 m or as distribution individual scout lines. • RC holes were not designed on any regular spacing. • Reported Aircore and RC results are based on the 1 m Fire Assay re-splits of original 4 m composite samples or the original composite sampling. Orientation of data in • The majority of land based Aircore drill holes had a dip and azimuth of -60/270. Lake aircore holes had a dip and relation to geological azimuth of either -65/225 or -65/270. AC holes were drilled vertically in areas were transported cover made structure drilling difficult. AC drill traverses were designed perpendicular to the regional structures known to control mineralisation. This was either east – west or northeast – southwest. • All RC holes had a planned dip and azimuth of -60/270. Sample security • Only trained and experienced contractors and company personnel were allowed to collect the samples; all samples were held within a secure company location before dispatch to Bureau Veritas in Perth for Au analysis. Audits or reviews • No audits or reviews of sampling protocols have been completed.

Drilling - Section 2 Reporting of Exploration Results (Criteria listed in the preceding section also apply to this section.)

Criteria Commentary Mineral tenement and • SBM has 100% ownership of the 19 tenements comprising the Pinjin Project. These include: E28/2234, E28/2283, land tenure status E28/2284, E31/0999, E31/1000, E31/1005, E31/1007, E28/2218, E28/2245, E28/2250, E28/2264, E28/2357, E28/2375, E28/2445, E31/1056, E31/1082, E28/2246, E28/2247 and E28/2494. Exploration done by • There have been numerous historical holders of the project area which covers over ~1,131 square kilometres. other parties • Exploration has been conducted by numerous companies including but not limited to: Newmont Pty Ltd, Endeavour Minerals, WMC, Goldfields Exploration Pty Ltd, Anglo American, Gutnick Resources, Carpentaria Exploration Company, BHP, Uranez, Placer Exploration Ltd, Jacksons Minerals Limited, Anglo Australian Resources, Troy Resources NL, Saracen, Hawthorn Resources and Renaissance Minerals Limited. Geology • SBM is targeting Archean orogenic gold mineralisation near major regional faults. • The tenement package covers Archaean greenstones within the highly prospective Eastern Goldfields Province of the Yilgarn Craton. The Pinjin project covers portions of the prospective Laverton and Keith-Kilkenny Tectonic Zones which pass through the eastern and western portions respectively. Drill hole Information • Drill hole information for holes returning significant results have been reported in the intercept table. Included in the intercept table are collar position obtained by DGPS pickup, hole dip and azimuth acquired from hand held compass and clinometre, composited mineralised intercepts lengths and depth as well as hole depth. Metres below surface (mbs) for intercepts were calculated for the start of the intercept. Data aggregation • Broad down hole intercepts are reported as length weighted averages using a cut-off of 500 ppb Au. Such methods intercepts may include material below cut-off but no more than 1 sequential metre of such material and except where the average drops below the cut-off. Supplementary grades of > 1000 ppb Au are used to highlight higher grades zones within the broader zone. • No high grade cut is applied. • No metal equivalent values are used for reporting exploration results. Relationship between • Down hole length is reported for all holes; true width is not known as the orientation of mineralisation is not fully mineralisation widths understood. and intercept lengths Other substantive • Included in the body of the report. exploration data Diagrams • Diagrams show all drill holes material and immaterial to Exploration Results.

Balanced reporting • Details of all holes material to Exploration Results have been reported in the intercept table, and all other drill holes For personal use only use personal For drilled during the reporting period are highlighted on diagrams included in the report. Other substantive • Data is included in the body of the report. exploration data Further Work • Further exploration Aircore and RC drill holes are planned and are discussed in the body of the report.

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xxxvi

LAKE WELLS – JORC Code, 2012 Edition – Table 1

Contents

Drilling: Section 1 Sampling Techniques and Data

Section 2 Reporting of Exploration Results

Drilling - Section 1 Sampling Techniques and Data (Criteria in this section apply to the succeeding section.)

Criteria Commentary Sampling techniques • Sampling was conducted via Aircore drilling. Aircore drill holes were on 40 m or 80 m spacing with line spacing ranging between 200 m and 1,000 m or as individual scout lines. • Samples were collected from a rig-mounted cyclone by bucket and were then placed directly on the ground in neat rows of between ten and fifty (depending on hole depth). • Drill spoil was sampled with a scoop to 4 m composite samples of approximately 2.5 kg. • During RC drilling one metre samples were also generated by the rigs cone splitter system and collected in calico bags, these were left on the ground on top of the corresponding metre of drill spoil. One metre samples are submitted for assaying based on the results of the initial 4m composite sampling. • The Aircore composites were submitted to Bureau Veritas Minerals Pty Ltd - Perth where they were sorted and dried, crushed to 10 mm and pulverised to -75 µm. A 40 g charge of pulverised sample was then digested with aqua regia with a gold analysis by ICP-MS to a detection limit of 1 ppb. The same digested sample was also tested for arsenic by ICP-AES to 1ppm detection limit. • Anomalous Aircore composite samples (>100ppb Au) were subsampled on a metre by metre basis using an aluminium scoop. These samples were submitted to Bureau Veritas Minerals Pty Ltd- Perth where they were sorted and dried, crushed to 10mm and pulverised to -75 μm. A 40 g charge of pulverised sample was then analysed for Au, Pd & Pt by Fire Assay with an ICP-AES finish to a detection limit of 1ppb. • Anomalous RC composite samples (>100 ppb) were subsampled using the previously collected one metre samples from the rigs cone splitter system. These were submitted to Bureau Veritas Minerals Pty Ltd - Perth where they were sorted and dried, crushed to 10 mm and pulverised to -75 µm. A 40 g charge of pulverised sample was then analysed for Au by Fire Assay with an ICP-AES finish to a detection limit of 1 ppb. • Representative specimens from end of hole Aircore rock chips were stored in plastic chip trays for future reference. For RC drilling a representative specimen of every metre was stored in plastic chip trays for future reference. • The EOH Aircore samples, as well as a selection of RC samples, were submitted to Genalysis and were prepared in the same manner as those samples submitted to Bureau Veritas. A 10g charge of pulverised sample was then digested by four acid digestion with analysis by the Scott Halley technique (ICP-OES & ICP-MS to ultra-trace levels) via 4A/OM20 method for 60 elements (Ag, Al, As, Ba, Be, Bi, Ca, Cd, Ce, Co, Cr, Cs, Cu, Dy, Er, Eu, Fe, Ga, Gd, Ge, Hf, Ho, Ln, K, La, Li, Lu, Mg, Mn, Mo, Na, Nb, Nd, Ni, P, Pb, Pr, Rb, Re, S, Sb, Sc, Se, Sm, Sn, Sr, Ta, Tb, Te, Th, Ti, Tl, Tm, U, V, W, Y, Yb, Zn & Zr). Drilling techniques • Aircore drilling was carried out by an 85 mm bit. All holes were drilled to refusal, which was generally at the fresh rock interface. Drilling was carried out by Raglan Drilling who utilised two separate Aircore rigs; a truck mounted R/A 180 Rig with 750 cfm and 350 psi and a track mounted lake rig with 750 cfm and 350 psi. • RC drilling was carried out using 140 to 145 mm hammer bits. Drilling was completed by Raglan Drilling who utilised a truck mounted SCHRAMM T685W rig with Sullair 1150/350 on board air. Drill sample recovery • Sample recoveries and condition (wet/dry) were routinely recorded. • The drill cyclone and sample buckets were cleaned regularly, in particular after wet ground was encountered. The cyclone was also cleaned several times during the course of each hole and after the completion of each hole. Logging • All drill holes were logged in full for lithology, alteration, weathering/regolith and colour. • Aircore and RC logging is both qualitative and quantitative. Sub-sampling techniques • Aircore and RC samples were collected as both dry and wet samples using a sample scoop. and sample preparation • All composite samples were sorted, dried, crushed and pulverised to produce a 40g charge prior to fire assay. • Samples were collected at 1 m intervals and composited in 4 m samples using a scoop to sample individual metre samples. • QC procedures for composite sampling involved the insertion of certified reference material, field duplicates and blanks at ratios of 1:50. • Bureau Veritas inserted certified standards, replicates and lab repeats. Quality of assay data and • The Aircore composite samples used a 40 g charge with an aqua regia digest, which is considered appropriate for laboratory tests analysis of the regolith dominated sample medium.

• The RC composite samples used a 40 g charge for fire assay, which is considered appropriate for gold For personal use only use personal For mineralisation in fresh rock material. • Certified reference material was inserted into the sample stream at a ratio of 1:50. • Field duplicates and blanks were inserted at a ratio of 1:50. • Bureau Veritas inserted certified standards, replicates and lab repeats. Verification of sampling • Primary geological and sampling data were recorded into made for purpose excel spreadsheets. Data was then and assaying transferred into the St Barbara corporate DataShed database where it was validated by an experienced database geologist. • No adjustments to assay data were made.

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xxxvii

Criteria Commentary Location of data points • Prior to drilling, all holes were marked out using a handheld GPS with ±3 m accuracy for easting, northings and ±10m elevation. Upon completion of the program all holes were resurveyed using a DGPS with decimetre accuracy to determine the final collar positions. • No downhole surveys were conducted on Aircore holes. • All RC holes were surveyed downhole by Raglan drilling who captured dip/azimuth readings at five metre intervals using a Reflex gyro tool. The gyro tool provides True North Azimuth. • All locations were captured in MGA94 zone 51 grid. Data spacing and • Aircore drill holes were on 40 m or 80 m spacing with line spacings ranging between 200 m and 2,000 m or as distribution individual scout lines. • RC holes were not designed on any regular spacing. • Reported Aircore and RC results are based on the 1 m Fire Assay re-splits of original 4 m composite samples or the original composite sampling. Orientation of data in • The majority of Aircore drill holes had a dip and azimuth of -60/270 or -60/180. AC holes were drilled vertically in relation to geological areas were transported cover made drilling difficult. AC drill traverses were designed perpendicular to the regional structure structures known to control mineralisation. This was either east – west or north – south. Sample security • Only trained and experienced contractors and company personnel were allowed to collect the samples; all samples were held within a secure company location before dispatch to Bureau Veritas in Perth for Au analysis. Audits or reviews • No audits or reviews of sampling protocols have been completed.

Drilling - Section 2 Reporting of Exploration Results (Criteria listed in the preceding section also apply to this section.)

Criteria Commentary Mineral tenement and • The Lake Wells Gold Project comprises 16 tenements and are wholly owned by Australian Potash Limited. These land tenure status include: E38/3018, E38/2114, E38/1903, E38/2988, M38/1275, E38/3021, E38/3028, E38/2113, E38/3224, E38/3225, E38/3226, E38/2505, E38/3270, E38/3109, E38/2901 and E38/3039. • St Barbara Limited entered into an Earn-In and Joint Venture with Australian Potash Limited on the Lake Wells Gold Project on 8 October 2018. Exploration done by • There have been numerous historical holders of the project area which covers over ~1,273 square kilometres. other parties • Exploration has been conducted by numerous companies including but not limited to: Goldphyre Resources Ltd, Anglogold Ashanti Australia Ltd, Australian Potash, Utah Development Corporation, Gold Partners NL, Kilkenny Gold NL, Johnsons Well Mining, Croesus Mining NL, Oroya Mining Limited, Western Mining Corporation Ltd, RGC Exploration Pty Ltd. Geology • SBM is targeting Archean orogenic gold mineralisation near major regional faults. • The tenement package covers Archaean greenstones within the highly prospective Yamarna Terrane of the Yilgarn Craton. The Lake Wells JV project covers portions of the prospective Yamarna Shear Zone, which passes through the southeastern portion of the project. Drill hole Information • Drill hole information for holes returning significant results have been reported in the intercept table. Included in the intercept table are collar position obtained by DGPS pickup, hole dip and azimuth acquired from hand held compass and clinometre, composited mineralised intercepts lengths and depth as well as hole depth. Metres below surface (mbs) for intercepts were calculated for the start of the intercept. Data aggregation • Broad down hole intercepts are reported as length weighted averages using a cut-off of 500 ppb Au. Such methods intercepts may include material below cut-off but no more than 1 sequential metre of such material and except where the average drops below the cut-off. Supplementary grades of > 1000 ppb Au are used to highlight higher grades zones within the broader zone. • No high grade cut is applied. • No metal equivalent values are used for reporting exploration results. Relationship between • Down hole length is reported for all holes; true width is not known as the orientation of mineralisation is not fully mineralisation widths understood. and intercept lengths Other substantive • Included in the body of the report. exploration data Diagrams • Diagrams show all drill holes material and immaterial to Exploration Results. Balanced reporting • Details of all holes material to Exploration Results have been reported in the intercept table, and all other drill holes drilled during the reporting period are highlighted on diagrams included in the report. Other substantive • Data is included in the body of the report. exploration data

For personal use only use personal For Further Work • Further exploration Aircore and RC drill holes are planned and are discussed in the body of the report.

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xxxviii

BACK CREEK – JORC Code, 2012 Edition – Table 1

Contents

Drilling: Section 1 Sampling Techniques and Data

Section 2 Reporting of Exploration Results

Drilling - Section 1 Sampling Techniques and Data (Criteria in this section apply to the succeeding section.)

Criteria Commentary Sampling techniques • Aircore drill holes were spaced at 400 m intervals on lines. Only two Aircore drill lines were completed and these were not on any regular spacing. Diamond hole BKDD0001 was designed as a single drill hole. • Aircore samples were collected from a rig-mounted cyclone via a green plastic bags and were then placed directly on the ground in neat rows of between ten and fifty (depending on hole depth). • Drill spoil was sampled with a spear to 4 m composite samples of approximately 1.5 kg. • The Aircore composites were submitted to ALS Orange where they were sorted and dried, crushed to 10 mm and pulverised to -75 µm. A 25 g charge of pulverised sample was then digested with aqua regia with a gold analysis by ICP-MS to a detection limit of 1 ppb. The same digested sample was also tested for Ag, Al, As, B, Ba, Be, Bi. Ca. Cd. Ce. Co. Cr. Cs. Cu. Fe, Ga, Ge, Hf, Hg, ln, K, La, Li, Mg, Mn, Mo, Na, Nb, Ni, P, Pb, Rb, Re, S, Sb, Sc, Se, Sn, Sr, Ta, Te, Th, Ti, Tl, U, V, W, Y, Zn, Zr by ICPAES. • The EOH Aircore samples, were submitted to ALS Orange and were prepared in the same manner the composites. A 25 g charge of pulverised sample was then digested with aqua regia with a gold analysis by ICP-MS to a detection limit of 1 ppb. A second charge was digested via multi acid digestion with HF and analysed for Ag, Al, As, Ba, Be, Bi, Ca, Cd, Ce, Co, Cr, Cs, Cu, Fe, Ga, Ge, Hf, Ln, K, La, Li, Mg, Mn, Mo, Na, Nb, Ni, P, Pb, Rb, Re, S, Sb, Sc, Se, Sn, Sr, Ta, Te, Th, Ti, Tl, U, V, W, Y, Zn & Zr by ICAES & ICPMS. ALS also analysed the EOH Aircore samples with a hyperspectral device using technique HYP-PKG. Drilling techniques • Aircore drilling was carried out by an 85 mm bit. All holes were drilled to refusal which was generally at the fresh rock interface. Drilling was carried out by Chief Drilling, who utilised a Ute mounted Aircore rig. Drill sample recovery • Sample recoveries and condition (wet/dry) were routinely recorded. • The drill cyclone and sample buckets were cleaned regularly, in particular after wet ground was encountered. The cyclone was also cleaned several times during the course of each hole and after the completion of each hole. Logging • All drill holes were logged in full for lithology, alteration, weathering/regolith and colour. • Aircore and diamond logging is both qualitative and quantitative. Sub-sampling techniques • Aircore samples were collected as both dry and wet samples using a spear tool. and sample preparation • All composite samples were sorted, dried, crushed and pulverised to produce a 25g charge prior to digestion. • Aircore samples were collected at 1 m intervals and composited in 4 m samples using a scoop to sample individual metre samples. • QC procedures for composite sampling involved the insertion of certified reference material, field duplicates and blanks at ratios of 1:50. • ALS inserted certified standards, replicates and lab repeats. Quality of assay data and • The Aircore composite samples used a 25 g charge with an aqua regia digest which is considered appropriate for laboratory tests analysis of the regolith dominated sample medium. • Certified reference material was inserted into the sample stream at a ratio of 1:50. • Field duplicates and blanks were inserted at a ratio of 1:50. • ALS inserted certified standards, replicates and lab repeats. Verification of sampling • Primary geological and sampling data were recorded into made for purpose excel spreadsheets. Data was then and assaying transferred into the St Barbara corporate DataShed database where it was validated by an experienced database geologist. • No adjustments to assay data were made. Location of data points • Prior to drilling, all holes were marked out using a handheld GPS with ±3 m accuracy for easting, northings and ±10m elevation. Upon completion of the program all holes were resurveyed using the same handheld GPS to determine the final collar positions. • No downhole surveys were conducted on Aircore or DDH holes. • All locations were captured in MGA94 zone 55 grid. Data spacing and • Aircore drill holes were spaced at 400 m intervals on lines. Only two drill lines were completed and these were not distribution on any regular spacing. Orientation of data in • Aircore drill holes were drilled vertically due to expected difficult conditions in transported cover. AC drill traverses relation to geological were designed to follow roadways or boundary fences to minimise the impact on agricultural land. For personal use only use personal For structure Sample security • Only trained and experienced contractors and company personnel were allowed to collect the samples; all samples were held within a secure company location before dispatch to ALS in Orange for analysis. Audits or reviews • No audits or reviews of sampling protocols have been completed.

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xxxix

Drilling - Section 2 Reporting of Exploration Results (Criteria listed in the preceding section also apply to this section.)

Criteria Commentary Mineral tenement and • SBM has 100% ownership of the two tenements comprising the Back Creek Project. These comprise EL8214 and land tenure status EL8530. Exploration done by • There have been numerous historical holders of the project area which covers over ~245 square kilometres. other parties • Exploration has been conducted by numerous companies including but not limited to: Newcrest Mining Pty Ltd, Brynes FC, Base Mines Ltd, Seltrust Mining Corporation Pty Ltd, Nationwide Resources Pty Ltd, Vanwild Pty Ltd, CRA Exploration Pty Ltd, Gold Mines of Australia Ltd, Astco Resources NL, Golden Hills Mining NL, Resolute Ltd, Teck Cominco Australia Pty Ltd and Goodrich Resources Ltd. Geology • SBM is targeting epithermal and porphyry-style copper-gold mineralisation with Ordovician aged rocks along strike from known occurrences of Macquarie Arc rocks and mineralisation. • The tenement package covers Ordovician aged rocks within the highly prospective Macquarie Arc in the Lachlan Orogen. Drill hole Information • Drill hole information for holes returning significant results have been reported in the intercept table. Included in the intercept table are collar position obtained by GPS pickup, hole dip and azimuth acquired from hand held compass and clinometre, composited mineralised intercepts lengths and depth as well as hole depth. Metres below surface (mbs) for intercepts were calculated for the start of the intercept. Data aggregation • Broad down hole intercepts in aircore holes are reported as length weighted averages using a cut-off of 500 ppb methods Au. Such intercepts may include material below cut-off but no more than 1 sequential metre of such material and except where the average drops below the cut-off. Supplementary grades of > 1000 ppb Au are used to highlight higher grades zones within the broader zone. • No high grade cut is applied and no metal equivalent values are used for reporting exploration results. Relationship between • Down hole length is reported for all holes. mineralisation widths • True width is not known as the orientation of mineralisation is not fully understood. and intercept lengths Other substantive • Included in the body of the report. exploration data Diagrams • Diagrams show all drill holes material and immaterial to Exploration Results. Balanced reporting • Details of all holes material to Exploration Results have been reported in the intercept table, and all other drill holes drilled during the reporting period are highlighted on diagrams included in the report. Other substantive • Data is included in the body of the report. exploration data Further Work • Further exploration Aircore and Diamond drill holes are currently being planned.

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xl

HORN ISLAND – JORC Code, 2012 Edition – Table 1

Contents

Surface Sampling: Section 1 Sampling Techniques and Data

Section 2 Reporting of Exploration Results

Surface Sampling - Section 1 Sampling Techniques and Data (Criteria in this section apply to all succeeding sections.)

Criteria Commentary Sampling techniques • Soil samples are collected by first removing organic litter from the surface. A palaeo-pick and aluminum scoop is used to collect a lower B to C-horizon sample from typically between 15cm to 30cm depth. Sampling teams are supervised by a geologist who determined the depth of the sample collected. A minus 0.5 mm sample of ≥0.5 kg is then sieved and collected in a green plastic bag. A sample of soil is placed in a plastic chip tray for reference. • Rock chip samples (1 to 5kg) are collected from vein occurrences, including outcrop, subcrop and float material, and recorded. These samples are cleaned of any organic material and placed in a green plastic bag Drilling techniques • N/A Drill sample recovery • N/A Logging • All rock chips are qualitatively logged for lithology, alteration, mineralisation and structure. • Soil sample sites are recorded for general landform and surrounding outcrop general geological descriptions. For soil samples, the depth (from) collected was recorded in centimetres. Soil samples are logged for regolith (weathering) type and soil type by a geologist. A digital photograph is taken showing the soil sample location and it’s profile within the excavated sample pit. Sub-sampling techniques • Rock chip and soil samples collected are taken to a restricted area at the company’s exploration sample logging and sample preparation and processing site on Horn Island and prepared for transport. • Prior to dispatch all samples are inspected by AQIS and Department of Agriculture & Water Resources permits issued for transport from protected/biosecurity zone in the Torres Strait. • The surface samples are sent via secure/registered sea and road freight to ALS (Townsville) for sample preparation. All sample freight is managed by Sea Swift Pty Ltd. • Upon receiving samples ALS issue formal notification of sample quantities. • Rock chip sample preparation involves drying, jaw crush to 70% passing -6mm (CRU-21 method), pulverise in LM5 to a 85% passing -75um (PUL-23 method). • Soil sample preparation involves drying and pulverising in LM2 to a minimum 95% passing -106um (PUL-35a method). A sub-sample (DSPLT) was taken prior to pulverising for hyperspectral analysis Quality of assay data and • The rock chip and soil samples are prepared at ALS, Townsville. Rockchip samples are analysed for Au via 50g Fire laboratory tests Assay and AAS finish (Au-AA26 method) at ALS, Townsville. Soil samples are analysed for Au via 30g Fire Assay and AAS finish (Au-AA21 method) at ALS, Townsville. Rock chip and soil samples are analysed for multi-elements (Ag, Al, As, Ba, Be, Bi, Ca, Cd, Ce, Co, Cr, Cs, Cu, Fe, Ga, Ge, Hf, In, K, La, Li, Mg, Mn, Mo, Na, Nb, Ni, P, Pb, Rb, Re, S, Sb, Sc, Se, Sn, Sr, Ta, Te, Th, Ti, Tl, U, V, W, Y, Zn and Zr) via 4 acid digest with HF and Inductively Coupled Plasma Mass Spectroscopy (ICP-MS) via (ME-MS61L method) at ALS, Perth. • All surface samples are hyperspectrally analysed via Spectral Scan VNIR and SWIR (method TRSPEC-20) followed by Spectral Interpretation (INTERP-11 method) by ALS, Perth. This forms a combned analysis and interpretation package (HYP-PKG). • Soil sample field duplicates are collected in the field while collecting the original sample. Field duplicates are collected from a new hole dug less than 1m from the primary sample site at the same depth as the primary sample. Field duplicates are collected so that 5% of samples (1 in 20) are a duplicate. Standards (OREAS45h, OREAS45f) are inserted into the sample sequence so that 5% of samples (1 in 20) are a standard. Verification of sampling • N/A and assaying Location of data points • All soil and rock chip sampling sites are surveyed by a hand held GPS for Easting, Northing and RL using GDA94. Data spacing and • Regional soil sample sites are located on a 100m x 50m northwest-southeast orientated grid. distribution • Rock chip sample locations are dictated by the presence of vein occurences (outcrop, subcrop or float) which is recorded. Orientation of data in • N/A relation to geological

structure For personal use only use personal For Sample security • Only trained personnel under geologist supervision are permitted to collect the samples. All samples are held within a secure company building before dispatch. The samples are prepared at ALS Townsville and then analysed at ALS Townsville, Brisbane and Perth. Audits or reviews • No audits or reviews of sampling protocols have been completed.

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xli

Surface Sampling - Section 2 Reporting of Exploration Results (Criteria listed in the preceding section also apply to this section.)

Criteria Commentary Mineral tenement and • EPM25520 Horn Island and EPM 25418 Kaiwalagal, form part of the The Horn Island Gold Project that is located in land tenure status the Torres Strait, far-north Queensland. EPM25520 and EPM 25418 are wholly owned by Alice Queen Limited under subsidiary company Kauraru Gold Pty Ltd. St Barbara Limited entered into an Earn-In and Joint Venture with Alice Queen Limited on the two tenements on 5 June 2019. Exploration done by • Previous explorers include Seltrust Mining Corporation Pty Ltd, BP Minerals, Torres Strait Gold Pty Ltd, Augold NL, other parties Carpenteria Exploration Company Pty Ltd. A modern operation was established by Augold Pty Ltd in 1987 and operated until 1989. Between 2013 and current day, Alice Queen Limited through Kauraru Gold Pty Ltd has completed mapping, soil sampling, rock chip sampling, diamond drilling and geological studies. A Maiden Inferred Mineral Resource Estimate was reported by Alice Queen Limited in August 2017. Geology • Geology of the Horn Island Gold Project comprises comagmatic extrusive volcanic rocks and I-type intrusive rocks (with a range of recognisable textural and mineralogical phases) of Late Carboniferous to Early Permian age. • St Barbara Limited is targeting Intrusive Related Gold System (IRGS) type deposits. Drill hole Information • N/A Data aggregation • N/A methods Relationship between • N/A mineralisation widths and intercept lengths Diagrams • Figures show all sample sites material and immaterial to Exploration Results. Balanced reporting • All rock chip, float and soils sample locations with any significant results are shown in Figures. Other substantive • Included in the body of the report. exploration data Further work • Included in the body of the report.

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xlii

SIMBERI – JORC Code, 2012 Edition – Table 1

Contents

Drilling: Section 1 Sampling Techniques and Data

Section 2 Reporting of Exploration Results

Surface Sampling: Section 1 Sampling Techniques and Data

Section 2 Reporting of Exploration Results

Drilling - Section 1 Sampling Techniques and Data (Criteria in this section apply to the succeeding section.)

Criteria Commentary Sampling techniques • Diamond Drilling - Sampled using PQ3 (85mm), HQ3 (61.1mm) and NQ3 (45mm) sized core using standard triple tubes. Half or quarter core was sampled on nominal 1 or 2-metre intervals with the upper or left - hand side of the core collected for sample preparation. For PQ diameter core a further cut was completed, whereby quarter core is submitted to provide a practical sample size. • Half core or quarter core was dispatched to the ITS PNG Ltd (Lae) sample preparation facility with 250g pulps sent to Intertek Laboratory in Perth. Pulps residuals are stored in (Lae) for six months following assay. • RC Drilling at Sorowar - One metre samples were generated by the rigs cyclone splitter system by collection in calico bags. When samples are wet, samples are collected in a 20 litre bucket, the water decanted and the sample transferred to the calico bag. One metre calico bag samples are then submitted for assay. Samples were fully prepared at the company's on-site sample preparation facility on Simberi Island with 200g pulps sent to SGS Laboratory in Townsville. Pulp residues are stored in Townsville for future re-assay if required. Drilling techniques • Diamond drilling comprised PQ3 (85mm), HQ3 (61.1mm) and NQ3 (45mm) core recovered using 1.5m to 3m barrels. Drilling was completed by Quest Exploration Drilling (QED). When ground conditions permit, an ACT Digital Core Orientation Instrument was used by the contractor to orientate the core. • RC drilling at Sorowar was carried out using 140mm hammer bits. Drilling was completed by Quest Exploration Drilling (QED) who utilised a track mounted SCHRAMM 685 rig coupled to an auxiliary compressor/booster unit. A limited number of holes were drilled using a DML 45 drill, also coupled to the auxiliary compressor/booster unit. Drill sample recovery • Diamond drilling recovery percentages were measured by comparing actual metres recovered per drill run versus metres measured on the core blocks. Recoveries averaged over >90% with increased core loss present in fault zones and zones of strong alteration. • RC drilling conditions (wet/dry) were routinely recorded. The drill cyclone and sample buckets were cleaned regularly, in particular after wet ground was encountered, nominally after each six metre rod, depending on ground conditions. The cyclone was also cleaned several times during the course of each hole and after the completion of each hole. Logging • Diamond holes are qualitatively geologically logged for lithology, structure and alteration and qualitatively and quantitatively logged for veining and sulphides. Diamond holes are geotechnically logged with the following attributes qualitatively recorded - strength, infill material, weathering and shape. Whole core together with half core, were photographed when dry and wet. • RC drilling chips were sieved, cleaned, logged and photographed. Reference material was not stored in plastic chip trays for future reference. • All holes are fully logged. Sub-sampling techniques • All diamond drill core associated with St Barbara work program was half cut with the upper or left-hand side and sample preparation submitted for assay. For PQ diameter core a further cut was completed, whereby quarter core is submitted to provide a practical sample size. All samples were sent to ITS PNG Ltd (Lae) sample preparation facility, where preparation involves drying, jaw crush to 95% passing -4.75mm, pulverise in LM5 or LM2 to a minimum 95% passing -106um, with 250g pulps sent to Intertek Laboratory in Perth. Pulps residuals are stored in Lae for six months following assay. Quality control of sub-sampling consisted of insertion of blank control samples and coarse reject duplicates, both at a ratio of 1:20 samples. • All Sorowar reverse circulation rock chip and diamond core samples were fully prepared at the company's on-site sample preparation facility on Simberi Island. Preparation involved drying, jaw crush to 70% passing -6mm, pulverise in LM5 or LM2 to a minimum 85% passing -75um, with 200g pulps sent to SGS Laboratory in Townsville.

Pulp residues are stored in Townsville for future re-assay if required. For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xliii

Criteria Commentary Quality of assay data and • All diamond drill samples associated with the St Barbara work program (excluding the Sorowar RC and Diamond laboratory tests drill samples) were sent to Intertek for analysis. Half or quarter core samples were analysed for Au via 50g Fire Assay ICP and AAS finish (FA50/ICP OE04 method) for low detection sample or 50g Fire Assay and AAS finish (FA50/AA method) and then multi-elements (Ag, Al, As, Ba, Be, Bi, Ca, Cd, Ce, Co, Cr, Cs, Cu, Fe, Ga, Ge, Hf, In, K, La, Li, Mg, Mn, Mo, Na, Nb, Ni, P, Pb, Rb, Re, S, Sb, Sc, Se, Sn, Sr, Ta, Te, Th, Ti, Tl, U, V, W, Y, Zn and Zr) via 4 acid digest with HF (4A method) and Inductively Coupled Plasma Optical Emission Spectroscopy (ICP-OES) or Inductively Coupled Plasma Mass Spectroscopy (ICP-MS) via (OM10 method). QC included insertion of certified reference material (1 in 20); insertion of in-house blank control material (1 in 20); and the insertion of reject residues (1 in 20). QAQC results were assessed as each laboratory batch was received and again on a quarterly basis. Results indicate that pulveriser bowls were adequately cleaned between samples. • All Sorowar Reverse Circulation rock chips and diamond core were analysed for gold using fire assay with a 50g charge and analysis by flame atomic absorption spectrometry (FAA505 method) at SGS, Townsville; and then multi-elements (Ag, As, Ca, Cu, Mo, Pb, S, Sb, Zn) via 4 acid digest (DIG41Q method) and Inductively Coupled Plasma Atomic Emission Spectroscopy ICP-AES via (ICP41Q method). • Diamond drilling QC included insertion of certified reference material (1 in 20); insertion of in-house blank control material (1 in 20); and the insertion of reject residues (1 in 20). QAQC results were assessed as each laboratory batch was received and again on a quarterly basis. Results indicate that pulveriser bowls were adequately cleaned between samples. Sorowar Reverse Circulation drilling QC included insertion of certified reference material (1 in 20); insertion of in-house blank control material (between 1 in 15 and 1 in 20). • Intertek Perth and SGS Townsville inserted certified standards and replicates and lab repeats. Verification of sampling • Sampling data is recorded electronically which ensures only valid non-overlapping data can be recorded. Assay and and assaying downhole survey data are subsequently merged electronically. All drill data is stored in a SQL database on secure company server. No twin holes have been completed. Location of data points • All Simberi Island collars were surveyed by in-house surveyors using DGPS using Tabar Island Grid (TIG) which is based on WGS84 ellipsoid and is GPS compatible. Tatau and Tabar Island collars were surveyed initially by hand held GPS and by DGPS after hole completion. All holes were downhole surveyed using either a Reflex or Ranger single shot camera with the first reading at about 18m and then approximately every 30m increments to the bottom-of-the hole. • For Sorowar Reverse Circulation drilling, one survey reading was collected at the bottom of the hole and a second at approximately half the hole’s maximum depth. Data spacing and • Diamond drilling data is not yet sufficient to establish continuity of the lodes and therefore the drill spacing is distribution irregular and broad spaced. • At Sorowar pit, the RC drilling data is sufficient to establish continuity of the lodes in some areas of the Sorowar pit, with infill holes on a nominal 30m x 30m having been drilled. Elsewhere, in the Sorowar area, the drilling density is nominally at a 60m x 60m spacing, and still insufficient to be able to predict orebody continuity. Orientation of data in • Where surface mapping and sampling has contributed to understanding of outcropping geological structures, relation to geological drilling and sampling has been undertaken orthogonal to the mapped structure. structure • At Sorowar pit, the RC drilling targeting sulphide gold mineralisation is optimised with holes drilled at 60° dip towards the northeast where possible to test the interpreted main northwest striking orientation to mineralisation. Limited RC holes are drilled in a vertical or 60° dip towards the southwest orientations when access is restricted. Sample security • Only company personnel or approved contractors are allowed on drill sites; drill core is only removed from drill site to secure core logging/processing facility within the gated exploration core yard; core is promptly logged, cut and prepped on site. The samples sent to Intertek are stored in locked and guarded storage facilities until receipted at the Laboratory. Audits or reviews • No audits or reviews of sampling protocols have been completed.

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xliv

Drilling - Section 2 Reporting of Exploration Results (Criteria listed in the preceding section also apply to this section.)

Criteria Commentary Mineral tenement and • SBM has 100% ownership of the three tenements over the Simberi Islands; ML136 on Simberi Island, EL609 which land tenure status covers the remaining area of Simberi Island, as well as Tatau Island and Big Tabar Island and 4 sub-block EL2462 which covers part of Tatau and Mapua Island. Exploration done by • CRA, BHP, Tabar JV (Kennecott, Nord Australex and Niugini Mining), Nord Pacific, Barrick and have all other parties previously worked in this area. Nord Pacific followed by Allied Gold was instrumental in the discovery and delineation of the 5 main oxide and sulphide deposits at Simberi. Geology • The Simberi gold deposits are low sulphidation, intrusion related adularia-sericite epithermal gold deposits. The dominant host rocks for mineralisation are andesites, volcaniclastics and lesser porphyries. Gold mineralisation is generally associated with sulphides or iron oxides occurring within a variety of fractures, such as simple fracture in- fills, single vein coatings and crackle brecciation in the more competent andesite units, along andesite/polymict breccia contact margins as well as sulphide disseminations. • On Tatau and Big Tabar Islands, located immediately south of Simberi, porphyry Cu-Au, epithermal quartz Au-Ag and carbonate-base metal Au mineralisation is present. • On Simberi Island, Diamond and RC drilling is being conducted on the Simberi ML136 testing for epithermal sulphide gold potential. • Diamond drilling is being conducted at Simberi Island on the Simberi ML136 at depth below Pigiput pit and on Big Tabar Island at Banesa Prospect testing for porphyry Cu-Au mineralisation. Drill hole Information • Drill hole information is included in intercept table outlining collar position obtained by DGPS pickup, hole dip and azimuth acquired from a downhole surveying camera as discussed in section 1, composited mineralised intercepts lengths and depth as well as hole depth. Data aggregation • For gold only epithermal mineralisation, broad down hole intercepts are reported as length weighted averages using methods a cut-off of 0.5 g/t Au and a minimum grade*length of 5gmpt. Such intercepts may include material below cut-off but no more than 5 sequential metres of such material and except where the average drops below the cut-off. Supplementary cut-offs, of 2.5g/t Au, 5.0g/t Au and 10g/t Au, may be used to highlight higher grade zones and spikes within the broader aggregated interval. Single assays intervals are reported only where ≥5.0g/t Au and ≥1m down hole. • For porphyry copper-gold mineralisation at Banesa, broad downhole intercepts are reported as length weighted averages using a cut-off of 0.1 g/t Au and a minimum length of 20m with up to 10m of sequential internal dilution. Supplementary cut-offs of > 0.5 g/t Au may be reported. Au and Cu grades are reported. • For both mineralised styles, core loss is assigned the same grade as the sample grade; no high grade cut is applied; grades are reported to two significant figures and no metal equivalent values are used for reporting exploration results. Relationship between • Down hole length is reported for all holes; true width is not known as the orientation of the orebody is not fully mineralisation widths understood. and intercept lengths Diagrams • Diagrams show all drill holes material and immaterial to Exploration Results. Balanced reporting • Details of all holes material to Exploration Results will be reported in intercept tables, and all other drill holes drilled during the reporting period are highlighted on diagrams included in the report. Other substantive • Included in the body of the report. Core holes are routinely measured for bulk density determinations to be used for exploration data potential future resource modelling. Further work • Included in the body of the report.

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xlv

Surface Sampling - Section 1 Sampling Techniques and Data (Criteria in this section apply to all succeeding sections.)

Criteria Commentary Sampling techniques • The soil samples were collected by first removing organic litter from the surface. A hand auger was then used to collect a C-horizon sample from typically between 140cm to 190cm depth. Sampling teams were supervised by a geologist who determined the depth of the sample collected. A bulk sample of ≥2kg was then collected in a calico bag. A reference sample of soil and any weathered rock fragments is placed in a plastic chip tray for ASD analysis. • Rock chip samples (2 to 5kg) are cleaned of any organic material and placed in a calico bag. A small reference rock chip sample is placed in a plastic chip tray for ASD analysis. Drilling techniques • N/A Drill sample recovery • N/A Logging • All rock chip and float were qualitatively logged for lithology, alteration, weathering and colour. • Regional soil sample sites were recorded for land use, vegetation type, slope (degrees) and slope direction. For regional soil samples, the depth (from, to) collected was recorded in centimetres. Regional soil samples were logged for regolith (weathering) type, colour, tone and moisture content by a geologist. A digital photograph is taken showing the soil profile laid out and the location of the sample material highlighted. Sub-sampling techniques • Rock chip, float and soil samples collected were taken to a restricted area at the company’s on-site sample and sample preparation preparation facility on Simberi Island and dried in a dedicated oven at low Temperature (60°C) for 24 hours to reduce weight for transport. • Surface samples used for alteration studies are sent to Intertek in Lae (PNG) for sample preparation. • Surface samples for drill targeting were fully prepared at the company’s on-site preparation facility with 200g pulps sent to ALS Townsville for assay. • At Intertek, sample preparation involves drying, jaw crush to 95% passing -4.75mm, pulverise in LM5 or LM2 to a minimum 95% passing -106um. • At the company's on-site sample preparation facility on Simberi Island. Preparation involved drying, jaw crush to 70% passing -6mm, pulverise in LM5 or LM2 to a minimum 85% passing -75um. Quality of assay data and • Surface samples used for alteration studies were prepared and analysed by Intertek Lae and Intertek Perth. Samples laboratory tests were analysed for Au via 50g Fire Assay and AAS finish (FA50/AA method) and then multi-elements (Ag, Al, As, Ba, Be, Bi, Ca, Cd, Ce, Co, Cr, Cs, Cu, Fe, Ga, Ge, Hf, In, K, La, Li, Mg, Mn, Mo, Na, Nb, Ni, P, Pb, Rb, Re, S, Sb, Sc, Se, Sn, Sr, Ta, Te, Th, Ti, Tl, U, V, W, Y, Zn and Zr) via 4 acid digest with HF (4A method) and Inductively Coupled Plasma Optical Emission Spectroscopy (ICP-OES) or Inductively Coupled Plasma Mass Spectroscopy (ICP-MS) via (OM10 method). • Surface samples sent to ALS Townsville were analysed via 30g Fire Assay and AAS finish (Au-AA21 method) and then multi-elements (Ag, As, Cu, Fe, Mo, Pb, S, Sb, and Zn) via aqua regia and Inductively Coupled Plasma Atomic Emission Spectroscopy (ICP-AES) via (ME-ICP41 method). • Regional soil sample field duplicates are collected in the field while collecting the original sample. Field duplicates are collected from a new hole dug less than 1m from the primary sample site at the same depth as the primary sample. Field duplicates are collected so that 5% of samples (1 in 20) are a duplicate. Standards (OREAS45d, OREAS45e) are inserted into the sample sequence so that 5% of samples (1 in 20) are a standard. • For rock chip sample QC, Standards (OREAS45d, OREAS45e) are inserted into the sample sequence so that 5% of samples (1 in 20) are a standard. Verification of sampling • N/A and assaying Location of data points • All regional soil and rock chip sampling sites were surveyed by a hand held GPS for Easting, Northing and RL using WGS84, or using Tabar Island Grid (TIG). Data spacing and • Regional soil sample sites are located on a 200m x 200m off-set grid. Subject to results, follow-up soil samples may distribution be collected on 100m x 100m spacing in selected areas. In some areas samples cannot be collected due to the presence of sacred sites or swamps. • Rock chip sample locations are dictated by the presence of outcrop and are usually restricted to creeks, cliffs and breaks in slope. Orientation of data in • N/A relation to geological structure Sample security • Only trained company personnel were allowed to collect the samples. All samples were held within a secure company building before dispatch. The samples were prepared at Intertek Lae and then analysed at Intertek Townsville. Audits or reviews • No audits or reviews of sampling protocols have been completed. only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xlvi

Surface Sampling - Section 2 Reporting of Exploration Results (Criteria listed in the preceding section also apply to this section.)

Criteria Commentary Mineral tenement and • SBM has 100% ownership of the three tenements over the Simberi Islands; ML136 on Simberi Island, EL609 which land tenure status covers the remaining area of Simberi Island, as well as Tatau Island and Big Tabar Island and 4 sub-block EL2462 which covers part of Tatau and Mapua Island. Exploration done by • CRA, BHP, Tabar JV (Kennecott, Nord Australex and Niugini Mining), Nord Pacific, Barrick and Allied Gold have all other parties previously worked in this area. Nord Pacific followed by Allied Gold was instrumental in the discovery and delineation of the 5 main oxide and sulphide deposits at Simberi. Geology • The Simberi gold deposits are low sulphidation, intrusion related adularia-sericite epithermal gold deposits. The dominant host rocks for mineralisation are andesites, volcaniclastics and lesser porphyries. Gold mineralisation is generally associated with sulphides or iron oxides occurring within a variety of fractures, such as simple fracture in- fills, single vein coatings and crackle brecciation in the more competent andesite units, along andesite/polymict breccia contact margins as well as sulphide disseminations. • On Tatau and Big Tabar Islands, located immediately south of Simberi, porphyry Cu-Au, epithermal quartz Au-Ag and carbonate-base metal Au mineralisation is present. The current surface sampling is targeting porphyry Cu-Au mineralisation. Drill hole Information • N/A Data aggregation • N/A methods Relationship between • N/A mineralisation widths and intercept lengths Diagrams • Figures show all sample sites material and immaterial to Exploration Results. Balanced reporting • All rock chip, float and soils sample locations with any significant results are shown in Figures. Other substantive • Included in the body of the report. exploration data Further work • Included in the body of the report.

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xlvii

Atlantic Gold - Cochrane HIll, Fifteen Mile Stream and Beaver Dam – JORC Code, 2012 Edition – Table 1

Contents

Drilling: Section 1 Sampling Techniques and Data

Section 2 Reporting of Exploration Results

Drilling - Section 1 Sampling Techniques and Data (Criteria in this section apply to the succeeding section.)

Criteria Commentary Sampling techniques • Drill holes were sampled in their entirety, in nominal meter intervals. • Core samples have been processed as sawn to half core using a diamond-tipped core saw with nominal 1m half-core sample intervals. Samples were dispatched from Atlantic’s core facility in Moose River, directly to ALS in Sudbury, ON or in some cases ALS in Moncton, NB. Drilling techniques • Diamond drilling comprised NQ core recovered using 3m barrels. Drilling was completed by Maritime Diamond Drilling (MDD) and Major Drilling. Drill sample recovery • Diamond drilling recovery percentages were measured by comparing actual meters recovered per drill run versus meters measured on the core blocks. Recoveries averaged over >90% with increased core loss present in fault zones and zones of strong alteration. Logging • Diamond holes are qualitatively geologically logged for lithology, structure and alteration and qualitatively and quantitatively logged for veining and sulphides. Whole core was photographed when dry and wet. Core recovery and rock quality designation (RQD) were measured for each hole at the same metre-by-metre intervals. • All holes are fully logged. Sub-sampling techniques • Sawn half-core samples were submitted to ALS Chemex facility where each sample was dried, finely crushed to and sample preparation better than 70% passing a 2mm screen. A split up to 1,000g was taken using a Boyd rotary splitter and pulverized to better than 85% passing a 75µm screen. Quality of assay data and • A subsample of 50g was analysed by ALS Vancouver via 50g Fire Assay with AAS finish (ALS method Au-AA26). laboratory tests • Diamond drilling QC included randomized insertion of four OREAS certified reference materials (1 in 28) and insertion of in-house blank control material (1 in 28). QAQC results were assessed monthly. Results indicate good quality in laboratory sample preparation and analysis procedures. • Pulverized duplicates were prepared and analysed on every tenth original sample. • ALS inserted certified standards, blanks and lab repeats. Verification of sampling • Sampling data is recorded electronically which ensures only valid non-overlapping data can be recorded. Assay and and assaying downhole survey data are subsequently merged electronically. All drill data is stored in an SQL database on secure company server. Location of data points • All drill collars were surveyed by both third party (WSP) and in-house surveyors using DGPS. Drill collars were surveyed initially by handheld GPS and by DGPS after hole completion. All holes were downhole surveyed using either a Reflex EZ-Trac or Reflex EZ-Gyro at least 6m below casing and 30m increments to the bottom-of-the hole. Data spacing and • For Beaver Dam area (Mill Shaft, Cameron Flowage and Crusher Lake), Seloam’s Brook and Bear Brook diamond distribution drilling data is not yet sufficient to establish continuity of the mineralization and therefore the drill spacing is irregular and broad spaced. • In Cochrane Hill and Fifteen Mile Stream, diamond drilling data is generally spaced on a 25m X 20m grid. Orientation of data in • Where surface mapping and sampling has contributed to understanding of outcropping geological structures, relation to geological drilling and sampling has been undertaken perpendicular (orthogonal where possible as near vertical/steeply structure dipping ore bodies makes this difficult) to the mapped structure. Sample security • Only company personnel or approved contractors are allowed on drill sites; drill core is only removed from drill site to secure work site trailer; core is promptly logged and shipped to Moose River core Facility, where it is cut and prepped. The samples sent to ALS are stored in locked and guarded storage facilities until receipted at the Laboratory. Audits or reviews • No audits or reviews of sampling protocols have been completed.

only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xlviii

Drilling - Section 2 Reporting of Exploration Results (Criteria listed in the preceding section also apply to this section.)

Criteria Commentary Mineral tenement and • AGB has 100% ownership of the tenements over the Cochrane Hill deposit (EL51477); Seloam’s Brook Prospect land tenure status (EL05889, EL51573 and EL 52901) and Beaver Dam Area (EL50421). Exploration done by • Massval Mine, Northumberland Mines, Scominex, NovaGold, Acadian, Pan East, Seabright, MRRI, Aurogin, other parties Scorpio have all previously worked in the areas reported in this section. Geology • The Atlantic Gold gold deposits are mesothermal gold deposits hosted in folded turbidite sequences of the Meguma supergroup. The dominant host rocks for mineralisation are the argillites, with lesser greywackes (associated with shear zones). Gold mineralisation is generally associated with shearing, quartz veining and minor sulphides, but exists as free gold, and is found disseminated throughout the host rock as well as higher grade quartz veins. Drill hole Information • Drill hole information is included in intercept table outlining collar position obtained by DGPS pickup,(or in some cases listed as original handheld GPS layout if they haven’t been picked up by DGPS survey at time of report), hole dip and azimuth, composited mineralised intercepts lengths and depth as well as hole depth. Data aggregation • For Cochrane Hill and Fifteen Mile Stream Deposits (including Seloam’s Brook Prospect), broad down hole intercepts methods are reported as length weighted averages using a cut-off of 0.5 g/t Au and a minimum grade*length of 3gmpt. Such intercepts may include material below cut-off but no more than 3 sequential meters of such material and except where the average drops below the cut-off. Single assay intervals are reported only where ≥3.0g/t Au. • For Beaver Dam area (Cameron Flowage, Mill Shaft, and Crusher Lake), broad down hole intercepts are reported as length weighted averages using a cut-off of 0.5g/t Au and a minimum grade*length of 0.5gmpt. Such intercepts may include material below cut-off but no more than 1 sequential meters of such material and except where the average drops below the cut-off. Single assays intervals are reported only where ≥3.0g/t Au. Relationship between • For Cochrane Hill, down hole length is reported for all holes. Holes drilled were inclined to the south (azimuth 171°) mineralisation widths at angles between 69° and 49° from horizontal. Mineralisation is confined to a tabular zone or envelope that dips to and intercept lengths the north at approximately 70° such that drill holes intersect the mineralization at angles of between 41° and 61° respectively and down-hole mineralized intercepts are exaggerated over true widths by between 1.1 and two times. • For Fifteen Mile Stream, down hole length is reported for all holes. Holes drilled were inclined to the south (azimuth 175°) at 45° from horizontal, true width is not known as the orientation of the orebody is not fully understood. • For Beaver Dam area, down hole length is reported for all holes. Holes drilled were inclined to the south (azimuth 155°) at 45° from horizontal, true width is not known as the orientation of the orebody is not fully understood. Diagrams • Diagrams show all drill holes material and immaterial to Exploration Results. Balanced reporting • Details of all holes material to Exploration Results will be reported in intercept tables, and all other drill holes drilled during the reporting period are highlighted on diagrams included in the report. Other substantive • Included in the body of the report. Core holes are routinely measured for bulk density determinations to be used for exploration data potential future resource modelling. Further work • Included in the body of the report.

End of report

For personal use only use personal For

St Barbara Limited Quarterly Report / Q1 September FY20 Exploration Figures and Tables xlix