ENGINEERING WING STATUS OF WORKS Sl. Details of the project Estimate Agreement No & Date Date of Remarks No amount Amount of completio agreement n as per & Agency Agreement (Rs.lakhs) DIVISION-I

IN PROGRESS WORKS

1 Providing and widening 710 529.12 Sri 01.02.2020 work proposal of existing BT Road P.V.Subba was sent to from single lane to two Raju government for lane from clearance Junction (via Rythu bazar) to Boni (V), SUB TOTAL 710

WORKS YET TO BE GROUNDED 1 Construction of 930 717.6 M/s. - Work proposal Commercial Complex at Sandeep was sent to Ramnagar Site-1, Ravindra government for Visakhapatnam Engineers & clearance Contractors

2 Construction of 420 313.14 M/s. - Work proposal Commercial Complex at Sandeep was sent to Ramnagar Site-2, Ravindra government for Visakhapatnam. Engineers & clearance Contractors

36 3 Construction of toilet 3.95 3.38 M/s. S.S. - work to be block in premises of Enterprises commenced police repeater / wireless station at top. SUB TOTAL 1353.95

TENDERS UNDER FINALIZATION 1 Construction of Hakers 200 - - - Tender to be Zone in VMRDA Vacant invited land in Sector-7 of MVP Colony

SUB TOTAL 200 TOTAL 2263.95 DIVISION-II

IN PROGRESS WORKS 1 Formation of embankment 372 242.94 M/s. Sundeep - Pending with Quarry Rubbish and Ravindra polocy Construction of Minor Engineers & decision by Bridges& Construction of Contractors the Govt., C.D Works for 100'-0", on Land 60'-0" & 40'-0" wide pooling Roads toTrijunctionLay- schemes , out in S.Nos 1, 2, 4, 5 of process E- (V) & 363, may be kept 365, 385, 395, 406,408 of in abeyance Pedamusidivada for the time (V),Visakhapatnam. being. 2 Jungle clearing, trench 9.69 5.78 Sri. Pothina - Pending cutting and levelling of polocy earthen road portion for Naidu decision by Try juction layout at e- the Govt., marripalem. on Land pooling schemes , process may be kept in abeyance for the time being. 4 Construction of Pedastal 14 10.14 M/s. Vengala - Work is in and Walkway Platform for Projects progress installation of Y. S. Rajasekhara Reddy Statue at City Central park SUB TOTAL 395.69

37

WORKS YET TO BE GROUNDED

1 Development of Multi 380 - - - Tender

theme park at Cancelled

Mudasarlova park at

Visakhapatnam, Package-

I under Phase-I Gate complex, Toilet Block and Signature Pavilion 2 Clearing of jungle in the 8.69 5.78 Sri.K.Ramba - Pending proposed integrated bu polocy layout under Land pooling decision by scheme at Dabbanda (V), the Govt., Anandapuram (M), on Land Visakhapatnam pooling schemes , process may be kept in abeyance for the time being. SUB TOTAL 388.69

TENDERS UNDER FINALIZATION

SUB TOTAL 0 TOTAL 784.38

DIVISION-III

IN PROGRESS WORKS 1 Providing Road widening, 386 311 Sri. Sagi siva 12 Months Work Construction of side drains, seetarama 10.07.2018 completed. footpath and central divider raju Final bill to to the existing road from be paid Surya Mahal junction to PSN mill junction at 2 Widening of 100' Ring 1200 792.51 3/2016- 16-05- Work Road Phase-II 17/CE/EE- 2016 completed. Dasannapeta Jn., to IV/VUDA Final bill to Neela Tank Junction. Dt:16-05- be paid 2016 Sri P.V. 15-05- Prabhuji 2018 24 months

38 3 Widening and 210 153.07 Sri 17-02- Encroachm Strengthening of the road G.Chinnam 2018 ents not and Construction of CC Naidu removed by drains for the existing the ULB. approach road from R&B 16-08- Processed guest house jn., to State 2018 for Bank at Cantonment in 6 Months cancellation. 4 Widening and 273 195.63 Sri 17-02- 50% Work Strengthening of the road G.Chinnam 2018 is held up and Construction of CC Naidu due to drains for the existing shifting of approach road of K.A. electrical peta VUDA layout to poles and Duppada -Y jn. in removal of Vizianagaram 16-08- encroachme 2018 nts along 6 Months the road 5 Widening of existing road 255 197 Sri N. Pulla 30.05.2018 4 properties from Gumchi Jn., to Rao are yet to be Dasannapeta Rythubazar removed by Jn., to 66'-0" along with the side Drains, CD works, Municipality. Retaining wall, Footpaths, Road work Central Divider at for balance Vizianagaram stretch yet 28.02.2019 to be 9 months started. 6 Construction of 90 77.81 Sri P. 20.11.18 Work DECORATIVE Srinivsa Rao completed. BOUNDARY WALL for Final bill to Pedda Cheruvu be paid Beautification - Phase-II at Vizianagaram. 19.05.19 6 months

SUB TOTAL 2414

WORKS YET TO BE GROUNDED

SUB TOTAL 0 TENDERS UNDER FINALIZATION

SUB TOTAL 0 TOTAL 2414

39 DIVISION-IV

IN PROGRESS WORKS

1 Renovation of 38 25.63 M/s.K.Prasad 29.07.2019 Work is in Metropolitan & Co progress Commissioner’s Chamber and Meeting hall 9th floor at UB Complex, Siripuram, Visakhapatnam

2 Providing Annual 26.5 16.89 29.04.2020 Work is maintenance of VMRDA under Childrens Arena, progress Siripuram Jn, Visakhapatnam M/s K. Prasad & Co,

SUB TOTAL 64.5 WORKS YET TO BE GROUNDED

SUB TOTAL 0

TENDER UNDER FINALIZATION 1 Annual maintenance (Civil) 64.47 - - - Tender of VMRDA office located UB under Complex A, B, & C Blocks finalization including power room building, Gurajada kalakshetram, Mini Zoo and MC Camp office at Pandurangapuram fro the period from 01.02.2019 to 31.01.2020 2 Renovation of 6th and 7th 47 - - - Tender floor U.B Complex suitated under at Siripuram, Visakhapatnam finalization

3 Providing Maintenance of 12.6 - - - Tender VMRDA shopping under complexes at finalization & MVP Colony, Sector-VII, suitated in Visakhapatnam

SUB TOTAL 124.07 TOTAL 188.57

40 DIVISION-V

IN PROGRESS WORKS

2 Improvements, Widening 560 392.45 M/s. AR 17.05.2019 Work and Strengthening from Constructions stopped due km 290/0 to 292/100 of to High - Court Stay Visakhapatnam road (Old NH-5 of Town Limits) in Visakhapatnam. 3 Construction of 513.75 335.91 M/s 17.07.2019 work is in Kalyanamandapam at Chaitanya progress Chinamushidiwada, VUDA Constructions layout, Pendurthy Constituency, Visakhapatnam.

SUB TOTAL 1073.75

WORKS YET TO BE GROUNDED

1 Construction of Modern 350 215.64 M/s. Giri 31-05-2020 Work to be fish market opposite Santhosh started after VUDA City central Engineering receiving park,Visakhapatnam. Works the Govt. Orders

SUB TOTAL 350 TENDER UNDER FINALIZATION

SUB TOTAL 0 TOTAL 1423.75

DIVISION-VI IN PROGRESS WORKS 1 Construction of OE:760.0 501.45 M/s.Maruthi 01-04- Finishing Commercial Shopping 0 Engineering 2017 to work is in Complex Pitapuram Company 31-03- progress Colony, Visakhapatnam WE-1: 2018 680.00 WE-2: 654.00

41 2 Widening of 100'-0'' O.E: 616.45 Sri.K.Sekhar 31.07.2019 Shifting of Master Plan Road from 910.00 babu electrical Arch to poles, water Railway Station supply lines, (Flyover Bridge), properties Visakhapatnam W.E: and TDR 910.00 issues to be cleared by GVMC 3 Construction of Ground O.E: 78.49 M/s. Giri 10-11- Finishings floor and 1st floor building 90.00 Santhosh 2016 to work is for Fire Station at Engineering 09-11- under Suryabaugh, Works 2017 progress Visakhapatnam R.E.-1- 110.00 R.E.-2- 120.80

4 Proposed construction of 156 104.87 M/s.Giri 03.03.2019 65% of work Community Hall / Santhosh is Kalyanamandapam / Engineering completed. Meeting Hall at Works Remaining Thadichetlapalem, work is in Dharma Nagar, Ward progress. No.35 Visakhapatnam 5 Formation of 60'-0" master 593 280.98 M/s. - Work paln road from NH-16 A.R.Construc proposal junction to Beach Road tions was sent to via , government Visakhapatnam for clearance 6 Proposed construction of 52.48 35.49 Sri.P.Trinadh 03-05- Work is in Auditorium in the Hon’ble a rao Rao 2019 to progress District Court Complex at Visakhapatnam 02-02- 2020 SUB TOTAL 801.48 WORKS TO BE GROUNDED

SUB TOTAL

42 TENDERS UNDER FINALIZATION

1 Construction of 144 - - - Tender Compensatory class under rooms and toilets to finalization Visakha valley School, Visakhapatnam 2 construction of Toilet 39 - - - Tender Block Adjacent to SRK under Block at Visakha valley finalization School, Visakhapatnam 3 Construction of Rooms for 58.5 - - - Tender Food Craft Institute & under Junival Home for Girls at finalization Visakhavalley School, Visakhapatnam

SUB TOTAL 241.5 TOTAL 1042.98 DIVISION-VII IN PROGRESS WORKS 1 Construction of Open 225 156.6 28.09.2018 Work is in Auditorium at progress Sri. R.S Santharam 2 Construction of RDO 320 200.62 02.06.2018 Expected Office at Anakapalli date of completion M/s. 31-10-2019 Raghuram Hume Pipes PVT Ltd.,

SUB TOTAL 545 WORKS TO BE GROUNDED

1 Construction of Function 25 18.43 Sri. Y. 02.06.2018 Site to be Hall at Karunakar finalized Satyanarayanapuram, Reddy Anakapalli

2 BT Road from Anakapalli - 35 28.14 M/s. Sai 28.08.2019 Work to be road to Krishna commenced Vadrapalli (Munagapaka Enterprises By pass Road)

43 3 Construction of Bus 9 7.27 M/s. 07.06.2019 Work to be Shelter at Venkateswar commenced Municipality a Builders & Developers

4 Construction of Bus 9 6.48 M/s. Sri Sai 07.06.2019 Work to be Shelter at Nagulapalli (V) Constrictions commenced Munagapaka(M)

5 Construction of Bus 9 7.11 M/s. 07.06.2019 Work to be Shelter at Pulaparthu (V) Venkateswar commenced of Elamanchili (M) a Builders & Developers

6 Construction of Bus 9 6.51 M/s. Sri Sai 07.06.2019 Work to be Shelter at Venkatapuram Constrictions commenced of (M)

SUB TOTAL 96 TENDERS UNDER FINALIZATION

1 Widening of road to 60' 245 - Sri. Murugan 18.09.2018 RDP from arch at NH to RTC Constructions approved by complex road via . VUDA and Nukalamma temple at requested Anakapalli, Bit- I from 0/0 the Km to 1/200 KM Commission er, GVMC to remove the encroachme nts. 2 Widening of road to 60' 240 - K. Shekar 12.09.2018 RDP from arch at NH to RTC Babu approved by complex road via VUDA and Nukalamma temple at requested Anakapalli, Bit- II from the 1/200 Km to 2/400 KM Commission er, GVMC to remove the encroachme nts.

44

3 Providing side drains from 235 196.7 M/s Giri 23.06.2018 RDP N.H. Arch to R.T.C Santhosh approved by complex road Nukalamma Engineering VUDA and Temple at Anakapalli works requested the Commission er, GVMC to remove the encroachme nts. Work order issued 4 Construction of Function 25 20.98 Sr. Site to be Hall at M.Sanjeeva finalized Kasimkota,Anakapalli Rao 5 Construction of Auditorium 189 Site to be in (V & M) handed over by Elamanchili Municipality SUB TOTAL 934 TOTAL 1575 DIVISION-VIII IN PROGRESS WORKS 1 Construction of Sump and 70 55.67 M/s Sampath _ Work pump house with hydro Hydro nearing pneumatic pumping Techniques completion. system along with pipe lines to improve water supply facilities to Thotla Konda hill. SUB TOTAL 70 WORKS YET TO BE GROUNDED

SUB TOTAL 0 TENDERS UNDER FINALIZATION

SUB TOTAL 0 TOTAL 70

45 DIVISION-IX IN PROGRESS WORKS 1 Providing under Duct 83 75.64 M/s. Maruthi 08.04.2019 Work is in istallation to the ceiling Engineering progress with 100 mm Resin Company bonded glass wool for thernal and rain sound insulation and false ceiling with 20 mm glass fiber ceiling tiles and cement board fiber sheets for acoustics to the sound produced by the Audio System at Gurajafda Kalakshetram, Visakhapatnam SUB TOTAL 83 WORKS TO BE GROUNDED

SUB TOTAL 0

TENDERS UNDER FINALIZATION 1 Supply and installation of 25 Tender VRV/VRF air conditioners under to the proposed finalization modification of south side halls of 9th floor, U.B Complex , Visakhapatnam 2 Providing Electrification & 6.7 Tender Lighting to the proposed under modification of south side finalization halls of 9th floor, U.B Complex, Visakhapatnam 3 Supply, delivery & 5.4 Tender Installation of 2Nos. 20'-0" under HVLS Fans to Gurajada finalization Kalakshetram auditorium, Visakhapatnam

SUB TOTAL 37.1

TOTAL 120.1 GRAND TOTAL 9882.73