MaineDOT Work Plan Calendar Years 2018-2019-2020

January 2018

January 2, 2018

MaineDOT Customers and Partners:

At the beginning of each year, we at the Department of Transportation publish our annual Work Plan, which spells out all of the projects and activities that we plan to construct or undertake over the next three years. In the months before we publish the Work Plan, we adjust the listings for the second and third years of the previous Work Plan to reflect changing conditions—revised project cost estimates, schedule updates, changes in the scope of work, or changes in available funding. We also add new work items for the new third year—in this case, for Calendar Year 2020. As you, our customers and transportation partners, go through this Work Plan for Calendar Years 2018-2019-2020, you may see that the work items listed suggest fresh areas of emphasis, which are driven by the performance of the transportation system. This year, safety is an emphasis area that merits special attention, as shown by the work-item listings that indicate where we will use the resources entrusted to the Department.

Safety is deeply embedded in the Department’s mission and the culture, and has always been at the center of our work. Every project we build and every activity we conduct has safety aspects, and we can confidently say that safety is the #1 priority in every piece of our work. But after a decade of improvement, safety performance on the transportation system across America has been trending in the wrong direction, with vehicle crashes, injuries and fatalities increasing in parallel with the growth in vehicle miles traveled. In Maine, highway deaths have been inching their way back up to previous levels. And, certain segments of the traveling public are experiencing increasing incidence of crashes—for example, motorcycle fatalities have increased markedly in recent years, and the number of pedestrian fatalities per year in Maine has basically doubled in just four years. This year’s Work Plan provides us with tools to attack these trends, including:

 Continued addition of rumble strips to combat lane departure—still the deadliest crash type and still the highest focus of Maine’s Strategic Highway Safety Plan  Sustained funding for bridge improvements and replacements, as recommended in the 2014 report, Keeping Our Bridges Safe  Targeted outreach to communities that have experienced clusters of pedestrian crashes, with the goal to identify problem areas, both physical and behavioral, and develop strategies to tackle them  Funding to address pedestrian infrastructure needs, as identified through that community outreach  Upgrades to guardrail systems across the state to help bring our system to a higher standard  Investments to improve specific intersections and other spot locations identified through collection and analysis of data  Wrong-Way Initiatives: Pavement markings, signage and technological measures to reduce wrong- way driving on Interstate ramps  ‘Went-off-Road’ Curve Mitigations: A package of improvements designed to reduce crashes where there is a high risk of vehicles going off the road  Funding to design and construct improvements on our Interstate Highway System, with specific focus on I-295 north of Portland, where crash incidence is high

Selection of targeted safety projects for the Work Plan involves MaineDOT staff from many disciplines, ensuring a broad-based prioritization that puts the most important safety issues at the top of the list. In 2017, the Department also convened a Task Force on Roadway Safety, comprised of representatives from various partner agencies and other entities. This group developed recommendations that are also incorporated in this Work Plan, such as installing additional Intelligent Transportation System (ITS) equipment, and updating the Department’s Complete Streets Policy.

The Work Plan for Calendar Years 2018-2019-2020 also carries forward from previous Work Plans several other important themes underlying MaineDOT projects, programs and operations:

 A Transportation Asset Management approach—a framework for managing the full range of assets in our transportation system at an optimal cost over extended periods of time. Asset management is informed by both engineering and economic considerations, and is shaped by performance goals set up to meet customer expectations.  The Roads Report: In line with recommendations of this 2016 report, we are shifting distribution of highway funding more toward road preservation, and less toward reconstruction or rehabilitation. The report also led to revised Highway Corridor Priority classifications, a new Cyclical Pavement Resurfacing Program, and corridor management plans for the highest-priority roadways.  Keeping Our Bridges Safe: This 2014 report recommended increasing investment in our bridges, which we are continuing to do.  Partnerships: The 2018-2019-2020 Work Plan continues funding for the Department’s Municipal Partnership Initiative, which provides funding to leverage local funds to make improvements on lower-priority state-jurisdiction roads; and for the Business Partnership Initiative, which provides funding to leverage public- and private-sector investment on state roadways, to support economic opportunity.  Freight: MaineDOT is continuing investment on freight railroads and rail bridges, at ports and harbors, and on highway infrastructure that supports motor transport of goods in our state.  Competitive Grants: MaineDOT will continue aggressively to pursue federal grants such as the TIGER or INFRA grants administered by USDOT and its administrations. Through these opportunities, we have been able to augment our financial resources in recent years, and expand our investments beyond the limitations of federal formula programs.

This Work Plan lays out a $2.3 billion-plus roadmap to maintain and improve Maine’s transportation system over the next three years. During this administration, MaineDOT staff has worked methodically to make our agency more efficient and effective. I am proud of the work MaineDOT has accomplished to date, and confident that we will deliver the work for our transportation customers—on time and within our means. Please use the Work Plan to learn what MaineDOT is doing in your community and your region to enhance safety, individual mobility, economic prosperity and the quality of life for people who live, work and travel in our state. And, as always, I invite you to let me know what we can do to better serve you, our customers.

Sincerely,

David Bernhardt, Commissioner Maine Department of Transportation

Contents

Introduction

The MaineDOT Work Plan - Calendar Years 2018-2019-2020 ...... i

Capital Projects and Programs ...... i . Highway and Bridge Capital Work ...... ii . Multimodal Capital Work ...... iv . Statewide Capital Programs ...... v

Statewide Operations ...... vi . Highway and Bridge Maintenance and Operations ...... vi . Multimodal Operations ...... vi

Resource Assumptions and Resource Allocation ...... vii . Funding Sources ...... vii . Resource Assumptions ...... viii . Resource Allocation ...... ix

Project Prioritization and Selection ...... ix . Highway and Bridge Project Prioritization ...... x . Multimodal Project Prioritization ...... xi

Transportation Needs and Goals ...... xii

Reading the Work Plan ...... xiii . Work Plan Tabs ...... xiii . The Work Plan Online ...... xiv

Counties

• Androscoggin ………………………………………………………………...………………………….. 1 • Aroostook …………………………………………………………………...... 11 • Cumberland ………………………………………………………………...... 27 • Franklin …………………………………………………………………...... 52 • Hancock …………………………………………………………………….. ………………………….. 60 • Kennebec ………………………………………………………………………………………………… 67 • Knox ……………………………………………………………………………………………………... 79 • Lincoln …………………………………………………………………………………………………... 85 • Oxford ………………………………………………………………………………………...... 91 • Penobscot ………………………………………………………………………………………………... 103 • Piscataquis …………………………………………………………………...... 122 • Sagadahoc ……………………………………………………………………………………………….. 126 • Somerset …………………………………………………………………………………………………. 130 • Waldo ……………………………………………………………………………………………………. 139 • Washington …………………………………………………………………………………...... 145 • York ………………………………………………………………………………………………………. 153

Statewide Capital Programs ……………………………………………………………………………… 167

Statewide Operations ……………………………………………………………………………………… 182

Municipal Index …………………………………………………………………………………………..... 235

Work Plan Terms and Definitions ………………………………………………………………………... 242

Introduction

The MaineDOT Work Plan - Calendar Years 2018-2019-2020

This publication of the annual Maine Department of Transportation (MaineDOT) Work Plan describes all of the projects and activities planned by the department for Calendar Years (CYs) 2018, 2019 and 2020. The Work Plan includes capital projects and programs; maintenance and operations projects and activities; and all the administrative functions of the department. The work described in this Work Plan has a value of more than $2.3 billion, including 2,262 individual work items planned over three years. For Calendar Year 2018, the year with the most detailed project/activity scopes, schedules and estimates, there are 1,136 work items among them, with approximate cost estimates: • 604 Capital Projects - Estimated Cost: $511.1 million • 48 Miles of Highway Construction and Rehabilitation - Estimated Cost: $67.6 million • 356 Miles of Preservation Paving - Estimated Cost: $93.8 million • 600 Miles of Light Capital Paving - Estimated Cost: $22 million • 48 Highway Spot and Safety Improvements - Estimated Cost: $28.6 million • 106 Bridge Projects (Highway Bridges) - Estimated Cost: $118.8 million • $149.5 million in Maintenance and Operations Activities . including 336 Maintenance Projects - Estimated Cost: $26.1 million • 28 Transportation Planning and Research Activities - Estimated Cost: $4.55 million • $10.96 million for Administration • 44 Capital Aviation Projects - Estimated Cost: $43.95 million • 9 Port and Marine Projects and Activities - Estimated Cost: $18.7 million • 7 Freight Rail Projects and Activities - Estimated Cost: $15.9 million • 38 Public Transit (Bus, Commuter Ferry) Projects and Activities - Estimated Cost: $63 million • A project to replace a Island Transit District Ferry - Estimated Cost: $10 million • 23 Bicycle and Pedestrian Capital Projects - Estimated Cost: $7.84 million

Capital Projects and Programs

The 2018-2019-2020 Work Plan includes over $1.4 billion in highway, bridge and multimodal capital work—more than $1.1 billion in highway and bridge projects and more than $296 million in multimodal capital projects. Capital projects are major improvement projects with defined begin- and end-dates. They include bridge replacements, highway construction and paving, acquisition of buses and ferries, sidewalk construction, and major improvements to airports, among other investments. Most capital projects in this Work Plan have undergone or are currently undergoing engineering, and will be constructed by private contractors selected through a competitive bidding process. Capital work also includes municipal capital investment through the Local Roads Assistance Program.

i Highway and Bridge Capital Work The largest and most heavily traveled component of Maine’s transportation system is its 8,800- mile state-jurisdiction highway network. Maine’s need to invest in the preservation of the existing highway and bridge system is significant. This Work Plan directs more than $1.1 billion to highway and bridge capital projects over the three-year life of the Work Plan, during which time MaineDOT anticipates delivering to construction: • 229 miles of Highway Construction and Rehabilitation - Estimated Cost: $205 million • 1128 miles of Preservation Paving - Estimated Cost: $286 million • 1,800 miles of Light Capital Paving - Estimated Cost: $71 million • 240 Safety and Spot Improvements - Estimated Cost: $111 million • 260 Bridge Projects - Estimated Cost: $353 million

The bar charts that follow show the total cost of those highway and bridge capital projects in the Work Plan that are funded for construction, including the costs of construction, engineering and right of way (property acquisition). Similar charts of the department’s Construction Advertise Plan (CAP) provide estimates of construction costs only. The CAP is available on the MaineDOT website at www.mainedot.gov.

ii

iii

Multimodal Capital Work Ports and Other Marine Investments - The Work Plan includes over $28 million in state funding for marine-freight investments and other improvements to public marine facilities. Projects include: • $4.5 million for a mobile harbor crane to serve the International Marine Terminal in Portland. • Over $3.6 million for waterfront infrastructure at Mack Point in Searsport, including modifications to the crane, conveyor system, ram revolver, rail and electrical. • $5.5 million for dredging the commercial shipping channel at the port of Searsport. • $11.5 million for Boating Infrastructure Grant (BIG) and Small Harbor Improvement Program (SHIP) projects to make waterfront improvements in coastal communities, including $2.1 million in federal funds, $1.9 million in state funds, and $7.5 million in local and private funds. These programs may leverage additional federal, local or private funding on a competitive basis. Freight Rail –The Work Plan provides over $38 million in freight rail capital funding. The investments will include operational improvements on state-owned rail lines, improvements at railroad crossings, improvements to critical rail bridges and other rail line capital projects. Also included in the Work Plan is $3.75 million in state funding for the Industrial Rail Access Program (IRAP), which will leverage another $3.75 million in private funding.

iv Transit - The Work Plan funds about $39.4 million in transit capital needs, including nearly $31.7 million in federal capital funding, nearly $7 million in local funding and approximately $600 thousand in state funding. These funds provide support to Maine’s 20 regional and local transit providers, which own and operate over 400 transit vehicles with a combined replacement value of more than $50 million. MaineDOT oversees procurement and management of the state transit fleet, and ensures compliance with federal requirements and continued eligibility for federal funding. Aviation - The Work Plan also provides $7.8 million in state funding to match federal grants for safety and infrastructure improvements at publicly owned airports, leveraging approximately $7.4 million in local funding and about $114.4 million in Federal Aviation Administration (FAA) funds. Projects include runway and taxiway reconstruction, safety improvements and devices, and other enhancements to improve airport access and to support economic development. Ferries - The Work Plan provides about $11.1 million for Maine State Ferry Service (MSFS) capital projects, including funding for ferry rehabilitation, and infrastructure improvements at various locations. Bicycle and Pedestrian Capital Projects – This year alone, the Work Plan adds approximately $4.7 million in new funding for bicycle and pedestrian facilities, comprised of about $2.8 million in federal Transportation Alternatives funding, $1.5 million in state funds, and more than $400 thousand in matching funds from towns and cities. Projects and initiatives include sidewalk construction, bicycle/pedestrian shared facilities, crossing improvements, and bicycle and pedestrian safety improvement. Also of special note in this Work Plan is about $3.7 million to complete an important section of the Eastern Trail in Scarborough and South Portland, which will include over $3.1 million from MaineDOT, with the remaining funds coming from local and private contributions.

Statewide Capital Programs Statewide Capital Programs are capital programs and expenditures that are statewide or regional, and that support capital improvements. These programs total more than $295 million in the Statewide Capital Programs tab of the Work Plan. In addition, Maine is receiving $21 million from the Volkswagen Settlement for their use of defeat devices on various diesel vehicles sold or leased in the United States. MaineDOT is the lead agency for fund distribution and is working the Maine Department of Environmental Protection and the Governor’s Energy Office to allocate funds in accordance with the requirements of the settlement. Information regarding the requirements of the settlement can be found at http://maine.gov/mdot/vw/ .

Some of these programs will identify location-specific projects in the future, but project selection may not yet have occurred because the selections are made by local entities (e.g., the Local Road Assistance Program), or because selections cannot be made until need is determined in future years (e.g., Light Capital Paving), or because project selection occurs by means of a rolling, demand-response process (e.g., Municipal Partnership Initiative and Business Partnership Initiative). Descriptions of the expenditure categories included in the Statewide Capital Programs tab are available in Work Plan Terms and Definitions, at the end of this document.

v Statewide Operations

While capital-related work represents about 60% of MaineDOT’s work efforts outlined in this Work Plan, ongoing maintenance, operations and administrative activities that support the department’s work and the transportation system as a whole are also described in the plan. Some of the larger categories of this work include winter snow and ice control, summer road maintenance, maintenance of non-highway/bridge infrastructure, planning and compliance activities, human resources, training, technology and finance and administration. Annually recurring Statewide Operations work items for various MaineDOT work units appear as three annual listings—one each for CYs 2018, 2019 and 2020. These and other activities—which are statewide, regional or non-location-specific in nature and provide support for the department overall, as well as for MaineDOT bureaus and offices—are provided in the Statewide Operations tab. Brief descriptions of the scopes and maintenance work activities listed in the Statewide Operations tab are available in Work Plan Terms and Definitions at the end of this document. Two major subsets of the listings in this tab—Highway and Bridge Maintenance and Operations, and Multimodal Operations and Support—are described in more detail below. (Note: Location- specific activities are shown separately in the County listings.)

Highway and Bridge Maintenance and Operations Maintenance and operation of Maine’s extensive highway and bridge system—a subset of the Statewide Operations listings—accounts for a large portion of MaineDOT’s overall work activities. This work is essential to the movement of people and goods, and to the health of the Maine economy. It is also an essential and cost-effective means of protecting the state highway and bridge system. From year to year, and within CY 2018, actual expenditures for this work will depend on the constantly changing condition of the transportation system, and importantly, on weather. The frequency and duration of weather events, for example, may require the department to change priorities and adjust budgets during the course of the year. For those reasons, overall expenditures for routine maintenance and operation of the highway and bridge system are shown in the Work Plan as approximate, annual budget figures. Multimodal Operations The other major subset of the Statewide Operations tab listings is comprised of funding support for various multimodal operations. Multimodal operations include support for the Downeaster passenger rail service, for the transit (bus) network statewide, for Maine State Ferry Service Operations, and for GOMaine, a statewide ridesharing service. Passenger Rail Operations - The Downeaster passenger rail service runs from Portland to Boston, with three trains per day running from Portland to Brunswick. The Work Plan provides about $36.9 million for passenger rail operations over three years. Transit Operations - Maine’s 20 transit providers, provide coordinated service to commuters, tourists, elderly individuals, and individuals with disabilities. Transit Operations work items include transit planning, administration and operating support for these services. The 2018-2019- 2020 Work Plan provides about $105 million for transit operations, including approximately $61 million in FTA (federal) funds, over $29.4 million in local support from cities and towns, and approximately $14.5 million in state funds.

vi Ferry Service Operations - The Maine State Ferry Service (MSFS) connects Islesboro, North Haven, Swan’s Island, Vinalhaven, Frenchboro, and Matinicus with the mainland. MSFS serves 2,500 year-round residents, plus many summer residents and tourists. The Work Plan provides $32.5 million for MSFS operations—50% from fares and 50% from the Highway Fund. Aviation Operations - In addition to support for capital projects at the public airports in Maine, the Work Plan also provides $1.65 million for operations at one of the two state-owned airports-- the Augusta State Airport.

Resource Assumptions and Resource Allocation Funding Sources Development of the Work Plan requires that the funding that is available to support the work described first be identified and categorized according to eligibility. The major funding sources that combine to provide the financial resources that support the Work Plan include: • Federal Highway Administration (FHWA) Formula Funds • Federal Transit Administration (FTA) Formula Funds • Federal Aviation Administration (FAA) Formula and Entitlement Funds • USDOT TIGER, FASTLANE and Other Federal Competitive Grant Programs • Federal Highway Administration Grant Anticipation Revenue (GARVEE) Bonds • State Highway Fund • State TransCap Revenue Account • State Multimodal Transportation Accounts • State General Obligation Bonding • Funds Transferred from Other State Agencies • Municipal and Private Funds These funding sources must generally be directed to specific uses, with some restrictions: • FHWA dollars must be used on federally eligible highway and bridge projects and programs, allocated by category [e.g., National Highway System roadways and bridges (NHPP), Surface Transportation Program (STP), and Highway Safety Improvement Program (HSIP)]. • FTA dollars can be used on federally eligible buses and bus facilities, certain ferry systems, passenger rail and transit operations. • FAA dollars must be used for federally eligible projects at Maine’s public airports. • State Highway Fund dollars must be used to support the highway and bridge system, and cannot be used to support non-highway-and-bridge needs. • State General Obligation Bond funding must be used on capital projects and is often directed to specific uses. • Legislative requirements exist for certain uses (e.g., Local Road Assistance Program). Below is a percentage breakdown of “Sources and Uses of Funds” for state fiscal years 2018 and 2019.

vii

While these graphics provide an overview of the relative proportion of MaineDOT funding sources and uses over the state budget cycle, the value of work represented this Work Plan— more than $2.3 billion—is different from the graphic representation of the department’s funding sources and uses, due to several factors: • The Work Plan covers three calendar years, while the state budget covers two state fiscal years. • The Work Plan includes funding from sources not considered part of the state budget, including local and private matching finds, and federal funds received directly by non- MaineDOT recipients. • The value of work from all phases of a project is included in the total project costs—in order to give a more accurate view of project cost—even if some amounts have already been expended. (e.g., the cost of design previously performed on projects that are now being funded for construction.) As with any plan that predicts future funding, if the funding does not become available as expected, the Work Plan will be adjusted per actual available resources.

Resource Assumptions In allocating funding for the Work Plan, department staff makes certain assumptions about what resources and revenue streams will be available, knowing that these resources may not turn out exactly as planned. Uncertainty about funding from major federal funding programs has existed for many years and is continuing, in large part because federal and state motor fuel tax revenues have become more unpredictable, due to greater automobile efficiency, fluctuating gasoline prices and changing economic conditions. Federal Funding - Based on estimates of funding authorized by the December 2015 reauthorization of federal surface transportation programs (the “FAST Act”), this Work Plan assumes modest increases in funding from federal highway and transit programs. The Work Plan also assumes support from policy-makers for $25 million in Federal Highway Administration Grant Anticipation Revenue (GARVEE) bonding in each calendar year—2018, 2019 and 2020. The GARVEE instrument enables states to finance debt with future FHWA formula funds. Federal aviation funding is based on assumed funding under the Federal Aviation Authorization Act.

viii State Funding - State revenue forecasts guide the Work Plan’s assumptions about what revenues will be available from the State Highway Fund. Major state resource assumptions in this Work Plan also include both voter-approved bonding and anticipated future state bonding, which continue to be a critical component of state funds. In November 2017, Maine voters approved a $100 million General Obligation (G.O.) bond to fund the state transportation program in 2018. Based on voter approval of transportation bond referenda in recent years, this Work Plan also assumes Governor, Legislative and voter approval for $100 million in G.O. bonding in CY 2019 and $100 million again in CY 2020. The Work Plan also assumes there will be sufficient State Highway Fund dollars to fund 600 miles of paving by the Light Capital Paving Program. While additional resources may arise from federal grant programs, public-private partnerships, and other circumstances, the Work Plan does not make assumptions regarding those possibilities. Some lesser and very conservative assumptions for smaller projected amounts include municipal and private matching funds, year-end balances from federal programs and typical carryover amounts.

Resource Allocation Federal and state eligibilities largely determine the funding available for each expenditure category in the Work Plan. Within the broad categories are other requirements. (For example, a specific amount is allocated by FHWA for the National Highway Performance Program and another amount for the Congestion Mitigation and Air Quality Program.) Allocation of resources to major program areas is thus substantially set by the respective federal and state sources. Few types of funding are flexible for use across multiple programs. Within these limitations, resources are first allocated to ‘must-do’ uses such as debt service, federal compliance, winter plowing and critical bridge needs. MaineDOT managers allocate the remaining available funding to broad categories according to the current needs of the transportation system under an asset management philosophy, and with the context of the dollars and unit-production proportions allocated to those categories in preceding years. Allocation amounts are then provided to department staff for their use in developing the project lists for their respective programs.

Project Prioritization and Selection

Prioritization, selection and recommendation of projects for the Work Plan are conducted by MaineDOT staff committees—the Highway Committee, the Bridge Committee, the Multimodal Committee and the Management Team of the Bureau of Maintenance and Operations (M&O). MaineDOT’s Results and Information Office (RIO), which includes the Highway Management Program and the Bridge Management Program, is instrumental in coordinating the work of the individual program committees with the Program Development Division in the Bureau of Planning. The program committees are comprised of staff from relevant disciplines and specializations. The committees work throughout the year to identify project candidates and prioritize them for potential inclusion in the Work Plan. Late in the year, the committees review the last two years of the current Work Plan (CY 2018 and CY 2019) and make any needed updates in cost, schedule and project scope. Once those adjustments are made, new projects for the Work Plan (mostly CY for 2020) are prioritized and recommended. Selection methodologies for these committees vary according to asset type and transportation mode, but the underlying asset management principles—managing the overall transportation system, using current,

ix reliable data and rational scoring systems, and building in flexibility for unanticipated needs and developments—are common across all areas.

Highway and Bridge Project Prioritization A systems approach is used to prioritize highway corridors and quantify customer-service levels. This Highway Corridor Priority/Customer Service Level framework is based on two questions: • What is the priority of the roadway? • Given its priority, what level of service can highway users reasonably expect? Larger and more heavily traveled highways are considered higher priority than smaller roads that carry less traffic. Interstate corridors have the highest priority, while collector roads and local streets are lower priorities on Maine’s highway system. To determine highway priority, the model also uses other objective criteria such as the roadway’s federal functional classification, truck traffic, relative amount of traffic and the business activity it supports. With this data, the HCP/CSL model classifies all 23,500 miles of public highways as one of five levels, as updated in 2017 per recommendations from the 2016 Roads Report: • HCP l: 1,760 miles - 8% of statewide mileage; 42% of Maine vehicle-miles traveled (VMT); the Maine Turnpike, all Interstate miles, and key principal arterials. • HCP 2: 1,355 miles - 6% of statewide mileage; 17% of VMT; non-Interstate and high-value arterials. • HCP 3: 2,211 miles - 9% of statewide mileage; 16% of VMT; the remaining arterials and the most significant major-collectors. • HCP 4: 3,731 miles - 16% of statewide mileage; 12% of VMT; the remaining major- and urban-collector highways, as well as minor-collector highways and state-aid roads. • HCP 6: 14,362 miles - 61% of statewide mileage; 13% of VMT; local roads and streets that are the year-round responsibility of municipalities. The HCP scale is then compared on a matrix with the department’s Customer Service Level (CSL) metric on an A-through-F scale. The CSL is determined using data on the safety, condition and service of the road. The result is a consistent tool to measure how a road compares to other roads of the same priority level. Additional information on the HCP/CSL system is available online at http://www.maine.gov/mdot/about/assets/hwy/. This data-driven HCP/CSL framework allows MaineDOT to focus resources on the most-needed projects, and to refine long-term capital goals and needs. It also plays a major role in allocating highway maintenance resources. The engineers, planners and technical specialists of the department’s Highway Committee, Bridge Committee and M&O Management Team, use the CSLs of Maine’s highway corridors in developing and prioritizing candidate highway projects to be considered for inclusion in the Work Plan. With the HCP/CSL framework as the foundation for identifying highway and bridge candidates, prioritization and selection of potential projects also involves consideration of further questions: • What is the customer benefit that will arise from the candidate project? • Are there other transportation alternatives if this candidate project does not proceed? • Does the candidate project address a demonstrated safety issue?

x • Does the candidate project involve a public-private or public-public partnership that will leverage additional financial resources? • Does the candidate project enhance economic activity and job growth? • Does the candidate project fill a gap in the highway corridor? • Is the candidate project able to proceed to construction within the next three years, including consideration of environmental documentation and permitting? • Is there public support for the candidate project? • Does the potential project preserve an element of the existing transportation system, such as replacing a failing bridge or protecting an already-existing transportation investment? With the consideration of these questions, project candidates are further refined to generate final project recommendations.

Multimodal Project Prioritization Prioritization and selection of multimodal (non-highway/bridge) projects begins with the lead MaineDOT staff members proposing candidates based on known needs and/or requirements. Allocation of financial resources to these various modal programs is largely determined by available federal funding in specified categories. State bond proceeds and certain other state revenue streams may be more flexible between programs, but may also be limited as to the purposes for which they can be used. Freight Rail Projects - Industrial Rail Access Program (IRAP) projects are ranked on economic and transportation efficiency criteria, and the top-rated projects are then selected within available funding. Rail-crossing safety projects are selected using safety criteria and input from localities, railroad operators and the public. Rail bridge projects are prioritized based on inspection reports and potential economic impacts, and rail maintenance projects are identified based on input from rail operators and staff inspections. Passenger Rail - Infrastructure improvements to maintain or enhance service on the Downeaster passenger rail service are prioritized by staff and Board of Directors of the Northern New England Passenger Rail Authority. MaineDOT is represented on this Board by the Commissioner of Transportation. Capital expenditures require extensive analysis to evaluate system maintenance and need. Transit - Transit project-candidates are grouped by federal urban, small urban and rural program eligibilities. Within each program, formulas that include population, road mileage and level of service are used to distribute operating funds according to local needs. The FTA capital program makes funding available for replacement of buses that have completed their useful life. New or expanded service requires planning to identify service gaps and set measurable objectives. Port and Marine Projects - Prospective investments in Maine ports and other marine facilities are developed by MaineDOT and Maine Port Authority staff using data used to identify market opportunities. Final recommendations are based on the capacities each marine facility to serve those specific markets and are reviewed by the Maine Port Authority Board of Directors. Small Harbor Improvement Program (SHIP) - SHIP projects are selected through an ongoing application process based on the eligibility of the proposed project and an approved local match. Projects must meet the goal of improving access and facilities in coastal communities.

xi Aviation Projects - Aviation projects are selected based on needs identified by municipal and regional airports in their federally approved master plans. Candidate projects are reviewed and prioritized by MaineDOT and proposed to the FAA, which chooses the projects to be funded. Ferry Projects - Capital projects for improvements to public ferries—transfer bridges, piers, and stations of the Maine State Ferry Service and Casco Bay Island Transit District (CBITD)—are prioritized by department and CBITD staff based on remaining service life, repair needs and public benefit. Bicycle and Pedestrian Projects - These projects are funded with dedicated federal funding and selected by an ongoing application process. A selection committee ensures that proposed projects improve safety and promote economic development. A 20% match is required and must be approved by the municipality. Multimodal project selection that is not already determined through funding eligibilities and mode-specific requirements are reviewed and prioritized by the department’s Multimodal Committee. The committee reviews projects eligible for discretionary funding, prioritizes according to economic impacts, project readiness, and cash availability, and makes project and schedule recommendations. The department is also developing Customer Service Levels for multimodal projects, which will be used in an analysis framework similar to the HCP/CSL system for highways and bridges. All Work Plan projects and activities recommended by staff are presented to the department’s senior management team for final review and approval, prior to inclusion in the Work Plan.

Transportation Needs and Goals

The needs of the transportation system in Maine, as in all other states, continue to outpace available federal and state resources. Maine’s large land area, relatively low population and high number of state-jurisdiction highway miles all contribute to the extent of this challenge for Maine. The needs of the system can be measured against capital goals established by the Maine Legislature in 2011 to promote maintaining the state’s highway system at an adequate level. The highway-related goals include: • By 2022, improve all Priority 1 and Priority 2 highways so that their safety, condition and serviceability customer service level is Fair or better. • By 2027, improve all Priority 3 highways so that their safety, condition and serviceability customer service level is Fair or better. • By 2017, implement a pavement program for all Priority 4 corridors that maintains their ride-quality customer service level at Fair or better; • Continue the Light Capital Paving program on a 7-year cycle for Priority 5 highways. These goals were developed to address just the basic needs of the existing highway system. In 2017, per recommendations from the 2016 Roads Report, MaineDOT revised the Highway Corridor Priority classifications to better address the statutory goals and our highway asset management needs. The reclassification allows MaineDOT to prioritize distribution of highway funding to meet preservation needs before rehabilitation or reconstruction of roadways.

xii Reading the Work Plan

The lists in this Work Plan describe all projects and activities of the department. Listings in the Work Plan include projects and activities planned for Calendar Years (CYs) 2018, 2019 and 2020. CY 2018 project listings include specific information about the project construction and delivery schedules. CY 2018 projects are planned definitely to move forward in 2018. The timing of CY 2019 and 2020 projects is more flexible to changing needs, and schedule-years for those projects may possibly change in next year’s Work Plan. CY 2019 and 2020 projects are typically in some stage of pre-construction development, but are expected to move forward so long as the funding assumptions in the Work Plan unfold as anticipated.

Work Plan Tabs • The County Tabs contain location-specific lists—sorted alphabetically by County. Projects and activities are ordered alphabetically by locality. Those located across municipal boundaries are shown in an anchor community only, in order to avoid duplication. • The Statewide Capital Programs tab includes capital work items that are not tied to a specific location. • The Statewide Operations tab describes all other department operations and administrative activities, both internal to MaineDOT and in partnership with other agencies. The Statewide Capital Programs and Statewide Operations lists are displayed similarly to the location-specific County lists. Work item listings appear as in the graphic below:

Unique Project Group or Detailed Work ID Location Asset Project Number Name Description

ID/Year Municipality Scope Name Description Funding

Highway Anticipated Total Available Corridor Delivery Scope Priority Year of Work Funding

xiii The Work Plan Online The content of this Work Plan is published on the MaineDOT website as a printable and searchable PDF document. The Work Plan web page also provides municipality-specific reports that include upcoming, scheduled work on the highway system, a synopsis of the highway maintenance work that was completed in the preceding year, current Local Road Assistance Program (LRAP) payments to that municipality and recently completed capital projects. There is also a link to MaineDOT’s interactive MapViewer, with which the site visitor can find planned projects, highway corridors with their Highway Corridor Priority (HCP) designations, and other features on Maine’s transportation system. Visit http://maine.gov/mdot/workplan/search/ for more information. A printed version of the Work Plan is also available upon request. To request a copy, call 207-624-3300, or e-mail [email protected].

xiv Androscoggin Androscoggin

Androscoggin County Livermore Falls Population 107,702 Land Area (sq mi) 468 Livermore Bridges 149 Highway Corridor Priority Miles HCP 1 117 HCP 2 66 HCP 3 97 HCP 4 127

Total HCP 1-4 407 Leeds

Turner

Greene

Minot Wales

Lewiston Mechanic Falls Sabattus

Poland Auburn Lisbon

Durham Androscoggin ID/Year Municipality Scope Name Description Funding

018651.00 Highway Construction/ Rehabilitation Located at the intersection of Route 136 and Mill 2019/20 Auburn Route 136 $1,000,000 Street. ATRC Sponsored. HCP 2 Intersection Reconstruction

Highway Safety and Spot 018658.00 Fiber optic interconnect, vehicle detection, signal Improvements Various Auburn upgrades, and ADA improvements at selected $372,000 2019/20 Locations intersections. ATRC Sponsored. Intersection Improvements

Aviation Safety and infrastructure improvements that may 018684.01 Auburn - include the relocation of navigational aids for the Auburn Runway/Taxiway Lewiston reconstruction of Runway 4-22 and the Runway $154,500 2019/20 Municipal Airport Safety Areas at the Auburn - Lewiston Municipal Reconstruction Airport (LEW).

Aviation Safety and infrastructure improvements that may 018684.02 Auburn - include the reconstruction of Runway 4-22 and Auburn Runway/Taxiway Lewiston $5,407,500 2019/20 Runway Safety Areas at the Auburn - Lewiston Municipal Airport Reconstruction Municipal Airport (LEW).

Aviation 018684.03 Safety and infrastructure improvements that may Auburn-Lewiston include Design and Permitting for Runway 17-35 and Auburn Runway/Taxiway $257,500 2018 Municipal Airport Runway 4-22 at the Auburn - Lewiston Municipal Reconstruction Airport (LEW).

Aviation 018684.04 Safety and infrastructure improvements that may Auburn-Lewiston Auburn Runway/Taxiway include a fuel farm at the Auburn - Lewiston $618,000 2019/20 Municipal Airport Municipal Airport (LEW). Capital Equipment Purchase

Aviation Safety and infrastructure improvements that may 018684.17 include the design portion necessary for the Auburn-Lewiston Auburn Runway/Taxiway relocation of navigational aids for the reconstruction $154,500 2018 Municipal Airport of Runway 4-22 and Runway Safety Areas at the Reconstruction Auburn - Lewiston Municipal Airport (LEW).

020852.00 Highway Paving Beginning 0.13 of a mile west of Hatch Road and 2018 Auburn Route 11 $2,192,000 extending easterly 2.67 miles. Mill And Fill HCP 2

020894.00 Highway Safety and Spot Located at the intersections of Academy Street and Improvements Main Street; Elm Street and Main Street; Minot 2019/20 Auburn Route 136 $615,000 Avenue and Elm Street; and Minot Avenue and High HCP 2, 1 Intersection Improvements Street. ATRC Sponsored.

021928.03 Maintenance Municipal Partnership Initiative Program. Located on 2018 Auburn Goff Street, Spring Street, Summer Street and Lake $1,001,000 Avenue Highway Rehabilitation Auburn Avenue for a total of 2.18 miles. HCP 4, 6, 3

1

0123456789 ID/Year Municipality Scope Name Description Funding

022090.00 Highway Paving Beginning 0.13 of a mile north of Chicoine Avenue 2018 Auburn Hotel Road $36,816 and extending northerly 1.04 miles. Light Capital Paving HCP 3

022090.00 Highway Paving Beginning at Hotel Road and extending south 0.63 2018 Auburn Lake Street $22,302 of a mile. Light Capital Paving HCP 4

022090.00 Highway Paving Lewiston Beginning at Aviation Avenue and extending 2018 Auburn $36,108 Junction Road northeast 1.02 miles to Hotel Road. Light Capital Paving HCP 4

022224.00 Taylor Brook Bridge (#3225) over Taylor Brook. 2019/20 Auburn Hotel Road $1,000,000 Bridge Culvert Replacement Located 0.03 of a mile north of Chicoine Avenue. HCP 3

Highway Construction/ 022384.00 Rehabilitation Beginning at East Hardscrabble Road and extending 2018 Auburn Hotel Road north 0.50 of a mile to Lewiston Junction Road. $210,000 Highway Improvements - PE ATRC Sponsored. HCP 3 Only

022398.00 Public Transportation Western Maine Western Maine Transportation Systems starting a Auburn Transportation $200,000 2019 new route. CMAQ - FTA Transfer Operating Assistance Services

022398.20 Public Transportation Western Maine Western Maine Transportation Systems starting a Auburn Transportation $250,000 2020 new route-year 2. CMAQ - FTA Transfer Operating Assistance Services

022404.00 Highway Paving Beginning at Washington Street and extending north 2019/20 Auburn Rodman Road $515,000 1.03 miles to Hotel Road. ATRC Sponsored. 1 1/4" Overlay HCP 4

023340.00 Public Transportation Androscoggin Transportation Resource Center Urban Transit (ATRC), Federal Transit Administration § 5303 for Auburn $93,664 2018 Planning metropolitan planning Fiscal Year 2018. Funds are Administrative Assistance transferred to FHWA.

023340.19 Public Transportation Androscoggin Transportation Resource Center Urban Transit (ATRC), Federal Transit Administration § 5303 for Auburn $93,664 2019 Planning metropolitan planning Fiscal Year 2019. Funds are Administrative Assistance transferred to FHWA.

2

0123456789 ID/Year Municipality Scope Name Description Funding

023340.20 Public Transportation Androscoggin Transportation Resource Center Urban Transit (ATRC), Federal Transit Administration § 5303 for Auburn $93,664 2020 Planning metropolitan planning Fiscal Year 2020. Funds are Administrative Assistance transferred to FHWA.

023384.00 Public Transportation Transit Capital Assistance for the Lewiston/Auburn, Urban Transit Auburn Federal Transit Administration § 5339 for small urban $117,500 2018 Capital Capital Equipment Purchase area transit, Fiscal Year 2018.

023384.19 Public Transportation Transit Capital Assistance for the Lewiston/Auburn, Urban Transit Auburn Federal Transit Administration § 5339 for small urban $117,500 2019/20 Capital Capital Equipment Purchase area transit, Fiscal Year 2019.

023384.20 Public Transportation Transit Capital Assistance for the Lewiston/Auburn, Urban Transit Auburn Federal Transit Administration § 5339 for small urban $117,500 2019/20 Capital Capital Equipment Purchase area transit, Fiscal Year 2020.

WR 35079 Bridge and Structural Repairing bridge rail on the Turner Street Bridge 2018 Auburn Maintenance Route 4 (#2875) over the Lake Auburn outlet. Located 0.17 of $59,000 a mile north of Fair Street. HCP 1

020642.18 Public Transportation FTA Section 5307 for urban transit planning - Auburn, Urban Transit Androscoggin Valley Council of Governments $87,500 2018 Lewiston Planning Administrative Assistance (AVCOG).

020642.19 Public Transportation FTA Section 5307 for urban transit planning - Auburn, Urban Transit Androscoggin Valley Council of Governments $87,500 2019 Lewiston Planning Administrative Assistance (AVCOG).

020642.20 Public Transportation FTA Section 5307 for urban transit planning - Auburn, Urban Transit Androscoggin Valley Council of Governments $87,500 2020 Lewiston Planning Administrative Assistance (AVCOG).

020645.18 Public Transportation Auburn, Urban Transit FTA Section 5307 for ADA Operating - Citylink Bus. $124,400 2018 Lewiston ADA Operating Operating Assistance

020645.19 Public Transportation Auburn, Urban Transit FTA Section 5307 for ADA Operating - Citylink Bus. $124,400 2019 Lewiston ADA Operating Operating Assistance

3

0123456789 ID/Year Municipality Scope Name Description Funding

020645.20 Public Transportation Auburn, Urban Transit FTA Section 5307 for ADA Operating - Citylink Bus. $124,400 2020 Lewiston Operating Operating Assistance

022270.00 Vietnam Memorial West Bridge (#6260) over the Auburn, Vietnam Vet 2019/20 west channel of the . Located on $315,000 Lewiston Connector Bridge Joint Replacement the Auburn - Lewiston city line. HCP 1

022599.10 Bernard Lown Peace Bridge (#3330) over the Auburn, 2019/20 Cedar Street Androscoggin River. Located at the Lewiston- $4,765,000 Lewiston Bridge Painting Auburn town line. HCP 2

022721.18 Public Transportation Auburn, Urban Transit FTA Section 5307 for Operating Assistance - Citylink. $912,050 2018 Lewiston Operating Operating Assistance

022721.19 Public Transportation Auburn, Urban Transit FTA Section 5307 for Operating Assistance - Citylink. $912,050 2019 Lewiston Operating Operating Assistance

022721.20 Public Transportation Auburn, Urban Transit FTA Section 5307 for Operating Assistance - Citylink. $912,050 2020 Lewiston Operating Operating Assistance

022759.18 Public Transportation Auburn, Urban Transit FTA Section 5307 for Capital Assistance - Citylink. $589,906 2018 Lewiston Capital Capital-Eligible Maintenance

022759.19 Public Transportation Auburn, Urban Transit FTA Section 5307 for Capital Assistance - Citylink. $589,906 2019/20 Lewiston Capital Capital-Eligible Maintenance

022759.20 Public Transportation Auburn, Urban Transit FTA Section 5307 for Capital Assistance - Citylink. $589,906 2019/20 Lewiston Capital Capital-Eligible Maintenance

022090.00 Highway Paving Jackson Hill Beginning at Lost Valley Road and extending 2018 Auburn, Minot $87,084 Road southwest 2.46 miles to Center Minot Hill Road. Light Capital Paving HCP 4

4

0123456789 ID/Year Municipality Scope Name Description Funding

023304.00 Highway Paving Beginning 0.06 of a mile east of Route 119 and 2018 Auburn, Minot Route 121 $529,799 Ultra Thin Bonded Wearing extending southeasterly 2.08 miles. HCP 2 Surface

020853.00 Beginning 0.03 of a mile north of Fair Street in Highway Paving Auburn extending north 0.73 of a mile to 0.08 of a 2018 Auburn, Turner Route 4 mile south of Hathaway Street in Auburn; beginning $1,273,000 Mill And Fill 0.10 of a mile north of Blanchard Road in Auburn HCP 1 extending north 1.65 miles to Conant Road in Turner.

WR 34948 Drainage Maintenance Cleaning overburden under guard rail to help with 2018 Auburn, Minot Route 11 drainage on Route 11 beginning at the Minot-Poland $22,000 town line and extending east 2.90 miles. HCP 2

023376.00 Bowdoin, Highway Paving Beginning at the intersection of Route 9 and Litchfield, 2019 Route 197 extending east 10.53 miles to the Route 201 $385,246 Richmond, Light Capital Paving intersection. HCP 3 Sabattus, Wales

023352.00 Highway Paving Buckfield, Beginning at Route 119 and extending north 7.73 2019 Route 124 $282,735 Hebron, Minot miles to Route 117. Light Capital Paving HCP 4

021780.00 Highway Safety and Spot Improvements Located at the intersection of Route 125 and 2018 Durham Route 125 $312,398 Meadow Road. HCP 3, 6 Intersection Improvements

023657.00 Tracy Brook Bridge (#2852) over Meadow Brook. 2018 Durham Route 125 $250,000 Bridge Improvements - PE Only Located 0.17 of a mile east of Brickyard Hill Road. HCP 3

WR 33503 Drainage Maintenance Ditching beginning at the Lane Road intersection 2018 Greene Sawyer Road extending north 0.5 of a mile to the Bergeron Road $20,000 intersection. HCP 4

022094.00 Highway Paving Greene, Beginning at Route 126 and extending north 1.03 2018 Greene Street $36,462 Sabattus miles to the Greene town line. Light Capital Paving HCP 4

023352.00 Highway Paving Hebron, Minot, Beginning at Route 124 and extending north 8.86 2019 Route 119 $324,066 Paris miles to Route 26. Light Capital Paving HCP 3

5

0123456789 ID/Year Municipality Scope Name Description Funding

WR 34873 Bridge and Structural Repair of curbing and wing walls on Stinchfield 2018 Leeds Maintenance Route 106 Bridge (#5002) over the Dead River. Located 0.37 of $45,000 a mile south of the Lakeshore Drive intersection. HCP 4

WR 35126 Drainage Maintenance Cleaning under guard rail beginning at the 2018 Leeds Route 219 Livermore-Leeds town line extending east 5.66 miles $12,000 to the Route 133 intersection in Wayne. HCP 3

011599.30 Highway Construction/ Rehabilitation Beginning at Mount Hope Avenue and extending 2019/20 Lewiston River Road $1,220,000 south 0.65 of a mile to Razel Way. ATRC sponsored. HCP 2 Highway Improvements

Highway Safety and Spot 018656.00 Fiber optic interconnect, vehicle detection, signal Improvements Various Lewiston upgrades, and ADA improvements at selected $443,000 2019/20 Locations intersections. ATRC Sponsored. Intersection Improvements

022322.00 Hart Brook Bridge (#6117) over Hart Brook. Located 2019/20 Lewiston Pleasant Street $225,000 Bridge Culvert Rehabilitation 0.02 of a mile south of Alfred A. Plourde Parkway. HCP 2

022324.00 Vietnam Memorial East Bridge (#6331) over Vietnam Vet 2019/20 Lewiston Androscoggin River. Located 0.35 of a mile west of $315,000 Connector Bridge Joint Replacement Route 202. HCP 1

Highway Construction/ 022388.00 Rehabilitation Beginning at Fairlawn Avenue and extending 2018 Lewiston East Avenue southwest 0.45 of a mile to Homefield Street. ATRC $210,000 Highway Improvements - PE Sponsored. HCP 4, 2 Only

Highway Construction/ 022390.00 Rehabilitation Beginning at Alfred A. Plourde Parkway and 2018 Lewiston River Road extending north 0.66 of a mile to Razel Way. ATRC $210,000 Highway Improvements - PE Sponsored. HCP 2 Only

022490.00 Highway Construction/ Rehabilitation Beginning at Main Street and extending southeast 2018 Lewiston Stetson Road $900,000 0.66 of a mile to College Street. ATRC Sponsored. HCP 4 Full Depth Reclaim

023665.00 Highway Paving Beginning at Lisbon Street extending southeast 0.31 Lewiston Cedar Street of a mile to the Bernard Lown Peace Bridge. ATRC $352,000 2019/20 Mill And Fill Sponsored.

6

0123456789 ID/Year Municipality Scope Name Description Funding

023667.00 Highway Paving Beginning 0.01 of a mile east of Route 11 and 2019/20 Lewiston Route 126 $1,251,551 extending easterly 2.08 miles. Mill And Fill HCP 2

023669.00 Highway Paving Beginning at Lincoln Street and extending north 1.38 2019/20 Lewiston Route 202 $2,420,000 miles to Pettingill Street. ATRC Sponsored. Mill And Fill HCP 1

WR 35713 Grind and pave six feet of each approach to establish Surface and Base Maintenance a smooth transition on each side of the James B 2018 Lewiston Route 202 $15,000 Longley Memorial Bridge (#3076) over the HCP 1 Androscoggin River.

022094.00 Highway Paving Lewiston, Beginning at the Bowdoin town line and extending 2018 Crowley Road $200,718 Lisbon, Sabattus north 5.67 miles. Light Capital Paving HCP 4

014862.00 Highway Construction/ Rehabilitation Beginning at Route 196 and extending northeast 2019/20 Lisbon Route 125 $725,000 0.95 of a mile to Huston Street. ATRC Sponsored. HCP 3 Reconstruction

018647.00 Highway Safety and Spot Improvements Located at the intersection of Route 9 and Route 2019/20 Lisbon Route 9 $1,000,000 125. ATRC Sponsored. HCP 3, 1 Auxiliary Turning Lanes

020290.00 Highway Construction/ Rehabilitation Beginning at Huston Street and extending north 0.97 2019/20 Lisbon Route 125 of a mile to 0.19 of a mile southerly of Burrough $1,860,000 Road. ATRC Sponsored. HCP 3 Reconstruction

020868.00 Highway Paving Beginning at Main Street and extending north 1.00 miles to Capital Avenue. Beginning at Frost Hill 2018 Lisbon Route 196 $671,000 Avennue and extending 0.24 of a mile. ATRC Mill And Fill HCP 1 Sponsored.

Highway Construction/ 022643.00 Rehabilitation Beginning at the intersection of Route 133 and 17 2018 Livermore Falls Route 17 $315,000 and extending north 1.10 miles to Route 4. Highway Improvements - PE HCP 3, 2 Only

023133.00 Highway Construction/ Rehabilitation 2019/20 Livermore Falls Route 106 Located 0.12 of a mile north of Strickland Loop Road. $355,000

HCP 3 Large Culvert Replacement

7

0123456789 ID/Year Municipality Scope Name Description Funding

WR 34459 Drainage Maintenance Ditching beginning at Route 133 and extending south 2018 Livermore Falls Route 106 $57,000 2.31 miles to the Leeds town line. HCP 3

021735.00 Androscoggin River Bridge (#2018) over Livermore, 2018 Route 4 Androscoggin River. Located at Livermore - $800,000 Livermore Falls Bridge Painting Livermore Falls town line. HCP 1

020885.00 Highway Paving Beginning 0.08 of a mile south of the Livermore town Livermore, 2018 Route 4 line and extending northerly 1.75 miles to 0.03 of a $676,500 Turner 1 1/4" Overlay mile southerly of Church Street. HCP 1

022432.00 Highway Paving Beginning at the Oxford town line and extending east 2019/20 Mechanic Falls Route 121 $503,863 2.15 miles to Route 124. 1 1/4" Overlay HCP 2

022924.00 Highway Safety and Spot Improvements Beginning 0.08 of a mile southeast of East Chestnut 2019/20 Mechanic Falls Route 121 $315,000 Street and extending southeasterly 0.03 of a mile. HCP 2 Slope Stabilization/Protection

WR 33631 Drainage Maintenance Replacing a culvert (#11540) on Route 11, located 2018 Mechanic Falls Route 11 0.60 of a mile south of the intersection of Route 11 $75,000 and Route 121 in Mechanic Falls. HCP 2

WR 34706 Drainage Maintenance Ditching beginning 0.10 of a mile north of the 2018 Mechanic Falls Route 124 intersection of Oak Street extending northerly 0.60 of $17,000 a mile to the intersection of Bucknam Street. HCP 4

022090.00 Highway Paving Center Minot Hill Beginning at Route 119 and extending south 2.53 2018 Minot $89,562 Road miles. Light Capital Paving HCP 4

020875.00 Highway Paving Beginning at White Oak Hill Road and extending 2018 Poland Route 11 $864,000 north 3.06 miles to the Mechanic Falls town line. 1 1/4" Overlay HCP 3

023370.00 Highway Paving Aggregate Hill Beginning at Route 26 and extending north 4.21 2019 Poland $154,002 Road miles to Empire Road. Light Capital Paving HCP 4

8

0123456789 ID/Year Municipality Scope Name Description Funding

023370.00 Highway Paving Beginning at Route 122 and extending north 4.43 2019 Poland Empire Road $162,049 miles. Light Capital Paving HCP 4

023370.00 Highway Paving Megquire Hill Beginning at Route 26 and extending south 6.38 2019 Poland $233,380 Road, Flint Road miles. Light Capital Paving HCP 4

023707.00 Highway Safety and Spot Improvements Beginning 0.34 of a mile west of Hackett Mills Road 2019/20 Poland Route 11 $400,000 and extending westerly 0.17 of a mile. HCP 2 Slope Stabilization/Protection

WR 34710 Drainage Maintenance Ditching and replacing one culvert (#194487) 2018 Poland Empire Road beginning at the interesection of Route 122 $90,000 extending north 4.25 miles to the Minot town line. HCP 4

WR 34711 Drainage Maintenance Poland Corner Ditching beginning at the intersection of Route 26 2018 Poland Road, Harris Hill extending east 4.00 miles to the intersection of $55,000 Road Empire Road. HCP 4

WR 34945 Custodial Maintenance Brush removal beginning at the New Gloucester- 2018 Poland Route 26 Poland town line extending north 1.80 miles to the $35,000 intersection of Route 122. HCP 1

018649.00 Highway Construction/ Rehabilitation Beginning at Stonewall Road and extending north 2018 Sabattus Route 132 $325,000 0.28 of a mile. ATRC Sponsored. HCP 4 Highway Rehabilitation

022094.00 Highway Paving Pleasant Hill Beginning 0.15 of a mile north of Route 9 and 2018 Sabattus $6,018 Road extending north 0.17 of a mile. Light Capital Paving HCP 3

022094.00 Highway Paving Beginning at Crowley Road and extending northwest 2018 Sabattus Grove Street $14,868 0.42 of a mile. Light Capital Paving HCP 4

022094.00 Highway Paving Beginning at Route 126 and extending north 0.55 of 2018 Sabattus Main Street $19,470 a mile. Light Capital Paving HCP 4

9

0123456789 ID/Year Municipality Scope Name Description Funding

022094.00 Highway Paving 2018 Sabattus Route 132 Beginning at Route 9 and extending north 1.00 mile. $35,400 Light Capital Paving HCP 4

WR 35180 Drainage Maintenance Ditching beginning at the intersection of Route 9 2018 Sabattus Route 132 $32,000 extending north 1.00 mile to the Wales town line. HCP 4

020886.00 Highway Paving Beginning 0.08 of a mile north of Upper Street and 2018 Turner Route 4 $3,813,000 extending northerly 11.18 miles. Mill And Fill HCP 1

022366.00 Martin Stream Bridge (#2518) over Martin Stream. 2019/20 Turner Route 4 $250,000 Bridge Substructure Located 0.43 of a mile south of Harlow Hill Road. Rehabilitation HCP 1

Highway Safety and Spot 022996.05 Improvements Beginning 0.12 of a mile north of Mason Road and 2018 Turner Route 4 $44,000 extending northerly 0.06 of a mile. Rest Area Construction/ HCP 1 Improvements

Highway Safety and Spot 023026.00 Improvements 2018 Turner Route 4 Located 1.03 miles north of Harlow Hill Road. $75,000 Slope Stabilization/Protection - HCP 1 PE Only

WR 32805 Bridge and Structural Repairing drains and joint on the Russell Bridge East Hebron Turner Maintenance (#6234) over the . Located 0.20 of a $105,000 2018 Road mile south of the intersection of Route 117.

10

0123456789 Big Aroostook Twenty Twp

T19 R12 T19 R11 Madawask a WELS WELS

Frenchville Grand T18 T18 R12 T18 R11 Fort Saint R13 Isle WELS WELS Kent Agatha WELS T18 R10 Van Saint WELS New Cross T17 R4 T17 R3 Buren T17 R13 T17 R12 Saint John Plt T17 Wallagrass Canada Lake Twp WELS WELS R14 WELS WELS Francis WELS Cyr Plt Allagash Hamlin T16 R13 T16 R12 T16 R9 T16 R8 Eagle T16 R6 T16 R5 Madawaska Stockholm T16 R14 Lake Twp WELS WELS WELS WELS WELS Lake WELS WELS Connor T15 Caswell Twp R15 T15 R14 T15 R13 T15 R12 T15 R11 T15 R10 T15 R9 T15 R8 Winterville T15 R6 T15 R5 Westmanland New WELS WELS WELS WELS WELS WELS WELS WELS Plt WELS WELS Sweden Limestone T14 Aroostook T14 R15 T14 R14 T14 R13 T14 R12 T14 R11 T14 R10 T14 R9 T14 R8 T14 R6 T14 R5 Woodland R16 T14 R7 Perham WELS WELS WELS WELS WELS WELS WELS WELS WELS WELS Caribou WELS WELS

T13 R16 T13 R15 T13 R14 T13 R13 T13 R12 T13 R11 T13 R10 T13 R9 T13 R8 T13 R5 T13 R7 Portage Wade Washburn Fort WELS WELS WELS WELS WELS WELS WELS WELS WELS WELS Lake WELS Fairfield

T12 R16 T12 R15 T12 R14 T12 R13 T12 R12 T12 R11 T12 R10 T12 R9 T12 R8 T12 R7 Castle T12 R17 Nashville Mapleton WELS WELS WELS WELS WELS WELS WELS WELS WELS Hill Presque WELS WELS Plt Isle Ashland Easton T11 R17 T11 R16 T11 R15 T11 R14 T11 R13 T11 R12 T11 R11 T11 R9 T11 R8 T11 R4 T11 R10 T11 R7 Garfield Chapman WELS WELS WELS WELS WELS WELS WELS WELS WELS WELS WELS WELS Plt Mars Westfield T10 R8 Hill T10 R7 T10 R6 Scopan T10 R3 WELS Masardis WELS WELS Twp WELS E Twp Blaine

T9 R8 Oxbow T9 R5 T9 R4 T9 R7 T9 R3 TD R2 WELS Plt WELS WELS Bridgewater WELS WELS WELS

Saint T8 R5 T8 R3 Croix WELS WELS TC R2 Monticello Twp WELS

T7 R5 Webbertown Dudley WELS Twp Twp Ham mond Littleton

Moro Plt Merrill Smyrna Ludlow Houlton Aroostook County New Limerick Dyer Population 7 1,871 Hersey Oakfield Brook Hodgdon Land Area (sq mi) 6,671 Linneus T4 R3 Crystal Island Bridges 306 Falls WELS TA R2 Cary Plt WELS Highway Corridor Priority Miles Forkstown Amity T3 R4 T3 R3 Sherman Twp HCP 1 195 WELS WELS HCP 2 214 Silver Glenwood Orient Ridge T2 R4 Plt Haynesville HCP 3 220 Twp WELS

HCP 4 462 Upper Weston T1 R5 Molunkus Twp North Yarm outh WELS Academ y Reed Plt Grant Twp Bancroft

Total HCP 1-4 1, 091 Macwahoc Molunkus Plt Twp Aroostook ID/Year Municipality Scope Name Description Funding

022120.00 Highway Paving Frank Mack Beginning 0.83 of a mile west of Carney Road and 2018 Allagash $142,072 Road extending northwesterly 3.09 miles. Light Capital Paving HCP 4

WR 34401 Replacing culverts (#179667, #179668, #179671) Drainage Maintenance and ditching various locations beginning 2.2 miles 2018 Allagash Route 161 $56,000 north of the Saint Francis-Allagash town line and HCP 3 extending 2,000 feet.

Highway Safety and Spot 023737.00 Allagash, Improvements Codyville Plt, Various 2019/20 Cable guard rail upgrades. $152,250 Danforth, Locations Guard Rail Installation And HCP 3, 4, 1 Presque Isle Replacement

022120.00 Allagash, Fort Highway Paving Kent, Saint Beginning 1.94 miles west of Route 1 and extending 2018 Route 161 $1,223,896 Francis, Saint westerly 22.57 miles. Light Capital Paving HCP 3 John Plt

Highway Safety and Spot 022982.00 Allagash, Saint Improvements 2018 Francis, Saint Route 161 Cable guard rail upgrades. $52,000 John Plt Guard Rail Installation And HCP 3 Replacement

020873.00 Highway Paving Beginning 0.73 of a mile north of the Weston town 2018 Amity, Orient Route 1 $3,716,000 line and extending northerly 10.87 miles. 1 1/4" Overlay HCP 3

021659.00 Highway Safety and Spot Improvements Large culvert (#46949) located 0.12 of a mile north of 2018 Ashland Route 227 $436,000 York Ridge Road. HCP 4 Large Culvert Replacement

Rail 022812.00 Sheridan Road Rail Bridge (Rail Milepost 193.50) of the Madawaska Subdivision, Maine Northern Ashland Rail Bridge Sheridan Road $4,800,000 2018 Railway, over the . Located 0.38 of a Rehabilitation mile southwest of Church Street.

WR 35046 Department Building and Lot New cold storage building and repairs to Ashland Ashland Maintenance Route 11 $70,000 2018 garage (#21844) located on Route 11.

023284.00 Highway Paving Beginning 0.18 of a mile east of Walker Street and Ashland, Castle extending easterly 4.03 miles. Continuing 0.85 of a 2018 Route 163 $1,775,913 Hill, Mapleton Ultra Thin Bonded Wearing mile west of Scopan Road and extending easterly HCP 2 Surface 4.82 miles.

11

0123456789 ID/Year Municipality Scope Name Description Funding

WR 34175 Ditching in various loactions from the intersection of Ashland, Castle Drainage Maintenance 2018 Route 227 Route 11 extending east 11.85 miles to the $100,000 Hill intersection of Turner Road in Castle Hill. HCP 4

WR 31242 Drainage Maintenance Ditching various locations along the Kelly Road 2018 Bancroft Twp Kelly Road beginning at the junction of Bancroft Road and $37,000 extending north 3.82 miles. HCP 4

023364.00 Bancroft Twp, Highway Paving Beginning at Reed Plt. town line and extending north 2019 Danforth, Bancroft Road $464,200 12.69 miles to Route 1. Weston Light Capital Paving HCP 4

WR 34067 Ditching and replacing culverts beginning at the Bancroft Twp, Drainage Maintenance 2018 Bancroft Road intersection of Route 171 extending north 9.98 miles $121,000 Reed Plt to the intersection of Kelly Road. HCP 4

018797.00 Benedicta Twp, Herseytown Twp, Highway Paving Beginning 0.08 of a mile north of Interstate 95 off- 2018 Medway, Interstate 95 SB ramp to Route 11 and extending southerly 22.91 $8,018,500 Sherman, T1 R6 Mill And Fill miles to the Medway-T2 R9 town line. HCP 1 WELS

WR 31547 Ditching various locations beginning at the Blaine, Drainage Maintenance 2018 Route 1 Monticello-Bridgewater town line and extending north $56,000 Bridgewater to the Blaine-Mars Hill town line. HCP 1

023364.00 Highway Paving West Bootfoot Beginning at Kinney Road and extending east 3.25 2019 Bridgewater $118,885 Road miles. Light Capital Paving HCP 4

WR 34502 Drainage Maintenance Ditching various locations beginning at the Kinney 2018 Bridgewater Bootfoot Road Road and extending east to the intersection of Route $30,000 1 in Bridgewater. HCP 4

WR 34585 Bridge and Structural Replace wearing surface and repair T-beam on Whitney Bridge (#2942) located on Route 1 between 2018 Bridgewater Maintenance Route 1 $70,000 the intersections of Bootfoot Road and Boundary HCP 1 Line Road.

Aviation 018688.01 Safety and infrastructure improvements that may Caribou Caribou Runway/Taxiway include Fuel Farm installation at the Caribou $515,000 2019/20 Municipal Airport Municipal Airport (CAR). Capital Equipment Purchase

12

0123456789 ID/Year Municipality Scope Name Description Funding

021680.00 Caribou Bridge (#6255) over B&A Railroad. Located 2018 Caribou Route 1 $800,000 Bridge Painting 0.35 of a mile south of Route 161. HCP 1

021681.00 Bypass Bridge (#6203) over Caribou Stream. 2018 Caribou Route 1 $500,000 Bridge Painting Located 0.27 of a mile north of Route 161. HCP 1

021682.00 Highway Safety and Spot Improvements Beginning 0.04 of a mile east of Main Street and 2019/20 Caribou Route 89 $495,000 extending easterly 0.29 of a mile to Bennett Drive. HCP 3 Drainage Improvements

021696.00 Greenlaw Brook No. 2 Bridge (#5625) over Greenlaw 2018 Caribou West Gate Road $115,000 Bridge Improvements - PE Only Brook. Located 0.18 of a mile north of Route 89. HCP 4

022228.00 Route 1 Otter Brook Bridge (#5902) over Otter 2019/20 Caribou Route 1 Brook. Located 0.37 of a mile north of Watson $800,000 Bridge Culvert Replacement Memorial Drive. HCP 1

Highway Safety and Spot 022841.00 Improvements Beginning 0.81 of a mile northwest of the Fort 2018 Caribou Grimes Road Fairfield town line and extending northerly 0.09 of a $75,000 Slope Stabilization/Protection - mile. HCP 4 PE Only

Highway Safety and Spot 022845.00 Improvements Large culvert (#931080) located 1.07 miles north of 2018 Caribou Route 164 $100,000 Route 1. Large Culvert Improvements - HCP 3 PE Only

Highway Safety and Spot 023739.00 Caribou, Improvements Haynesville, Route 2A, Route 2019/20 Cable guard rail upgrade. $88,500 Mapleton, 161, Route 227 Guard Rail Installation And HCP 4, 2 Presque Isle Replacement

023372.00 Highway Paving Caribou, Beginning at Route 89 and extending east 6.44 miles 2019 Route 223 $235,719 Limestone to Route 1A. Light Capital Paving HCP 4

022454.00 Highway Paving Caribou, Beginning 0.69 of a mile north of Washburn Road 2019/20 Route 1 $4,465,433 Presque Isle and extending northerly 9.48 miles. Cold-In-Place Recycle HCP 1

13

0123456789 ID/Year Municipality Scope Name Description Funding

023372.00 Highway Paving Caribou, Presque Isle Beginning at Route 164 and extending north 3.60 2019 $131,769 Presque Isle Road miles. Light Capital Paving HCP 4

WR 32350 Ditching and replacing culverts (#1000519, #138336) Caribou, Connor Drainage Maintenance Madawaska 2018 0.04 of a mile from the Madawaska Dam Road and $25,000 Twp Road extending north 1,000 feet. HCP 4

WR 33967 Ditching beginning 900 feet from the intersection of Caribou, Drainage Maintenance the West Gate Road extending east 0.25 miles. Then 2018 Route 89 $34,000 Limestone beginning at the Albert Road extending east 0.93 HCP 2 miles to the intersection of Route 1A.

WR 35066 Ditching various locations from the intersection of Caribou, Drainage Maintenance 2018 Route 223 Route 89 and extending east to the intersection of $120,000 Limestone Route 1A in Limestone. HCP 4

WR 32622 Replacing culverts beginning 2.85 miles east of the Drainage Maintenance intersection of Route 11 in Ashland and extending 2018 Castle Hill Route 227 $95,000 0.30 of a mile northerly to the Ashland-Castle Hill HCP 4 town line.

022118.00 Castle Hill, Highway Paving Mapleton, Beginning at Route 227 and extending north 3.76 2018 Castle Hill Road $177,472 Wade, miles to Route 164. Light Capital Paving HCP 4 Washburn

021769.00 Highway Safety and Spot Improvements Large culvert (#47246) located 0.89 of a mile south 2018 Caswell Route 1A $376,000 of the Hamlin town line. HCP 3 Large Culvert Replacement

021685.00 Highway Safety and Spot Improvements West Chapman Large culvert (#46947) located 0.29 of a mile south 2018 Chapman $536,000 Road of the Mapleton town line. HCP 4 Large Culvert Replacement

WR 32693 Drainage Maintenance Replacing culvert (#159063) located 2.5 miles north 2018 Cross Lake Twp Route 161 $45,000 of the Ouellette Road HCP 2

023677.00 Cross Lake Twp, Highway Paving Madawaska Beginning 2.04 miles northwest of the Stockholm 2019/20 Route 161 $2,709,150 Lake Twp, T17 town line and extending northwesterly 7.32 miles. 1 1/4" Overlay HCP 2 R4 WELS

14

0123456789 ID/Year Municipality Scope Name Description Funding

022496.00 Highway Construction/ Cross Lake Twp, Rehabilitation Beginning 2.47 miles northwest of the T17 R4 town 2019/20 Saint Agatha, Route 162 line and extending southeasterly 10.50 miles to $2,625,000 T17 R4 WELS Route 161. HCP 3 PMRAP DOT Pugmill

WR 34044 Producing, hauling and providing additional support activities for the placement of plant mix recycled Cross Lake Twp, PMRAP 2019 Route 162 asphalt pavement (PMRAP) beginning 2.47 miles $630,000 Saint Agatha northwest of the T17 R4 town line and extending HCP 3 southeasterly 10.50 miles to Route 161.

WR 35642 Replacing culverts in preparation of plant mix Cross Lake Twp, Drainage Maintenance recycled asphalt pavement (PMRAP) beginning 2.47 2018 Saint Agatha, Route 162 $125,000 miles northwest of the T17 R4 town line and Sinclair Twp HCP 3 extending southeasterly 10.50 miles to Route 161.

022298.00 Crystal Station Road Bridge (#6171) over Interstate 2019/20 Crystal Cow Team Road 95. Located 0.24 of a mile north of the Sherman town $600,000 Bridge Painting line. HCP 6

Highway Construction/ 022659.00 Rehabilitation Crystal, Island Beginning 0.02 of a mile east of Interstate 95 Ramp 2018 Route 159 $265,000 Falls D in Island Falls and extending westerly 1.16 miles. Highway Improvements - PE HCP 3 Only

023364.00 Highway Paving Crystal, Island Beginning at Route 2 and extending northwest 2.32 2019 Belvedere Road $84,866 Falls miles to Route 159. Light Capital Paving HCP 4

023390.00 Highway Paving Beginning 0.26 of a mile north of Belvedere Road 2018 Crystal, Patten Route 159 $1,094,838 Highway Cyclical Pavement and extending westerly 8.11 miles to Route 11. HCP 3 Resurfacing

019231.00 Highway Construction/ Rehabilitation Beginning 2.30 miles north of Pond Road and 2018 Dyer Brook Route 2 $3,074,000 extending northerly 1.54 miles to Keith Brook Road. HCP 4 Reconstruction

WR 34540 Drainage Maintenance Ditching various locations and replacing culverts 2018 Dyer Brook Route 2 beginning 2.2 miles north of the intersection of Pond $30,000 Road and extending north 1.0 mile. HCP 4

023364.00 Highway Paving Dyer Brook, Beginning at Route 2 and extending northeast 2.85 2019 River Road $104,253 Oakfield miles. Light Capital Paving HCP 4, 3

15

0123456789 ID/Year Municipality Scope Name Description Funding

022853.00 Highway Safety and Spot Improvements Cross culvert (#180749) located 1.65 miles south of 2019/20 Eagle Lake Sly Brook Road $243,000 the Wallagrass town line. HCP 4 Large Culvert Replacement

WR 34732 Bridge and Structural Repair retaining walls on Prestile Brook Bridge 2018 Easton Maintenance Route 10 (#2687) located 0.05 of a mile west of the $60,000 intersection of the West Ridge Road in Easton HCP 3

Highway Safety and Spot 022859.00 Improvements Cross culvert (#97545) located 1.43 miles south of 2018 Fort Fairfield Forest Avenue $45,000 Dumond Road. Large Culvert Improvements - HCP 4 PE Only

021882.00 Perley Brook Bridge (#3468) over Perley Brook. 2019/20 Fort Kent Route 161 Located 0.08 of a mile north of South Perley Brook $1,800,000 Bridge Culvert Replacement Road. HCP 2

022861.00 Highway Safety and Spot Improvements 2019/20 Fort Kent Route 1 Located at the intersection of Route 1 and Route 11. $171,500

HCP 2 Traffic Signals

022863.00 Highway Safety and Spot Improvements Replace traffic signal. Located at the intersection of 2019/20 Fort Kent Route 1 Route 1 and Route 161. Includes foundations and $176,500 poles. HCP 2 Traffic Signals

Highway Construction/ 022656.00 Rehabilitation Fort Kent, Beginning 0.40 of a mile west of Church Avenue in 2018 Route 1 $390,000 Frenchville Frenchville and extending westerly 4.66 miles. Highway Improvements - PE HCP 2 Only

022120.00 Highway Paving Fort Kent, Beginning at Route 11 and extending north 5.30 2018 Strip Road $250,160 Wallagrass miles to Route 161. Light Capital Paving HCP 4

Aviation Safety and infrastructure improvements that may 018692.01 Northern include design and permitting for Taxiway Delta Frenchville Runway/Taxiway Aroostook Extension (300') - Phase 2 and partial parallel $309,000 2019/20 Regional Airport Taxiway Construction at the Northern Aroostook New Construction Regional Airport (FVE).

Aviation Safety and infrastructure improvements that may 018692.03 Northern include construction of Taxiway Delta Extension Frenchville Runway/Taxiway Aroostook (300') - Phase 2 and partial parallel Taxiway, crack $1,545,000 2019/20 Regional Airport sealing and pavement markings on airfield pavement New Construction at the Northern Aroostook Regional Airport (FVE).

16

0123456789 ID/Year Municipality Scope Name Description Funding

Rail 021776.00 Gagnon Brook Gagnon Brook Rail Bridge (#7831) over Gagnon Frenchville Rail Bridge $1,540,000 2019/20 Rail Bridge Brook. Located on the Madawaska Branch rail line. Bridge Improvements

022118.00 Highway Paving Beginning at Cleveland Avenue and extending 2018 Frenchville Airport Road $98,176 northeast 2.08 miles. Light Capital Paving HCP 4

Highway Construction/ 022657.00 Rehabilitation Beginning at Madawaska town line and extending 2018 Frenchville Route 1 north 5.74 miles to 0.15 of a mile easterly of St. $450,000 Highway Improvements - PE Agatha Avenue. HCP 2 Only

023565.00 Gagnon Brook Bridge (#2303) over Gagnon Brook. 2019/20 Frenchville Route 1 $1,000,000 Bridge Replacement Located 0.47 of a mile south of Pelletier Avenue. HCP 2

022118.00 Highway Paving Frenchville, Brise-Culotte Beginning at Cleveland Road and extending 2018 $183,608 Saint Agatha Road northwest 3.89 miles to Route 1. Light Capital Paving HCP 4

021884.00 Soucy Bridge (#2781) over Thibodeau Brook. 2019/20 Grand Isle Route 1 $800,000 Bridge Culvert Replacement Located 0.18 of a mile north of Corbin Road. HCP 1

022118.00 Highway Paving Beginning at the Canadian Border and extending 2018 Hamlin Boundary Road $43,424 northwest 0.92 of a mile to Route 1A. Light Capital Paving HCP 4, 6

Highway Safety and Spot 018823.00 Improvements Large culvert (#46921) located 1.33 miles north of 2018 Haynesville Route 2A $50,000 Glenwood Plt. town line. Large Culvert Improvements - HCP 4 PE Only

WR 30781 Removing material under guard rail in various Drainage Maintenance locations beginning at Route 2A and extending 2018 Haynesville Danforth Road $45,000 southeast 4.93 miles to the Haynesville-Bancroft HCP 4 Twp. town line.

022638.00 Hodgdon Mills Bridge (#3103) over South Branch Hodgdon Mills 2018 Hodgdon . Located 0.05 of a mile east of $1,715,000 Road Bridge Replacement South McIntyre Road. HCP 4

17

0123456789 ID/Year Municipality Scope Name Description Funding

023625.00 Maduskeag Bridge (#2492) over Maduskeag Stream. Maduskeag 2019/20 Hodgdon Located 0.93 of a mile north of the Hodgdon Mills $1,000,000 Bridge Bridge Replacement Road. HCP 3

Aviation Safety and infrastructure improvements that may 018695.02 Houlton include the design and permitting of Runway 1-19 Houlton Runway/Taxiway International $247,200 2019/20 and Taxilane at the Houlton International Airport Airport New Construction (HUL).

Aviation 018695.03 Houlton Safety and infrastructure improvements that may Houlton Runway/Taxiway International include airfield pavement markings at the Houlton $103,000 2018 Airport International Airport (HUL). Crack Sealing

Aviation 018695.04 Houlton Safety and infrastructure improvements that may Houlton Planning And Research International include an obstruction analysis at the Houlton $61,800 2018 Airport International Airport (HUL). Planning Studies

Aviation Safety and infrastructure improvements that may 018695.05 Houlton include the construction of Taxilane, Reconstruction Houlton Runway/Taxiway International $4,120,000 2019/20 of Runway 1-19 and Obstruction Removal at the Airport Reconstruction Houlton International Airport (HUL).

021694.00 Pearce Brook No. 6 Bridge (#5019) over Pearce 2019/20 Houlton Green Street $700,000 Bridge Replacement Brook. Located 0.12 of a mile southwest of Route 1. HCP 4

022216.00 Bicycle-Pedestrian Rebuild sidewalks on Market Square, Water Street, 2019/20 Houlton Urban Highways Market Square Broadway and Main Street for a total length of 0.36 $625,000 of a mile. HCP 4 Sidewalk Construction

022240.00 Cooks Brook Bridge (#3401) over Cooks Brook. 2018 Houlton Foxcroft Road $100,000 Bridge Improvements - PE Only Located 1.08 miles north of Pleasant Street. HCP 4

022885.00 Highway Safety and Spot Improvements Located at the intersection of Smyrna Road and 2019/20 Houlton Route 1 $269,500 North Street. HCP 3 Traffic Signals

022426.00 Highway Paving Houlton, Beginning 0.29 of a mile south of Hidden Road and 2019/20 Route 1 $1,314,646 Littleton extending northerly 5.02 miles. Mill And Fill HCP 1

18

0123456789 ID/Year Municipality Scope Name Description Funding

023328.00 Highway Paving Houlton, Ludlow, Beginning 0.66 of a mile west of the New Limerick 2018 New Limerick, Route 2 $1,395,885 town line and extending easterly 10.34 miles. Smyrna Highway Cyclical Pavement HCP 3 Resurfacing

023364.00 Highway Paving Houlton, New Beginning at Route 2A and extending northwest 5.50 2019 Smith Lake Road $201,190 Limerick miles to Route 2. Light Capital Paving HCP 4

021732.00 Randall Bridge (#2703) over the West Branch of the 2018 Island Falls Old Patten Road . Located 0.17 of a mile $300,000 Bridge Deck Replacement northwest of Church Street. HCP 6

022320.00 Randall Bridge (#2703) over the West Branch of the 2019/20 Island Falls Old Patten Road Mattawamkeag River. Located 0.17 of a mile $150,000 Bridge Painting northwest of Church Street. HCP 6

022326.00 Bridge Street Bridge (#2100) over Limestone Stream. 2019/20 Limestone Route 229 $150,000 Bridge Painting Located 0.09 of a mile east of Route 1A. HCP 3

023813.00 Bicycle-Pedestrian Route 1A: Beginning at Route 89 extending north Route 1A, High 0.17 of a mile; High Street: Beginning at Vernon 2019/20 Limestone Trail, On-Road Street, Huggard Street extending north 0.36 of a mile; Huggard $533,900 Avenue Avenue: Beginning at Route 1A extending west 0.12 HCP 6, 3 New Construction of a mile.

WR 32865 Drainage Maintenance Ditching and replacing four culverts from the 2018 Limestone Route 1A intersection of the Noyes Road extending north 1.51 $33,000 miles to the Bog Road. HCP 3

WR 34188 Bridge and Structural Repairing the guard rail and sidewalk, and replacing 2018 Limestone Maintenance Route 229 a wing on Bridge Street Bridge (#2100) located 0.01 $43,000 of a mile east of the intersection of Route 1A. HCP 3

WR 32821 Cleaning culverts and ditching at various locations South Oakfield Linneus, New Drainage Maintenance beginning at the junction of Route 2A and South 2018 Road, New $72,000 Limerick Oakfield Road and extending to junction of Drews Limerick Road HCP 4 Lake Road.

023302.00 Highway Paving Littleton, Beginning 0.38 of a mile north of Little Road and 2018 Route 1 $1,915,578 Monticello Ultra Thin Bonded Wearing extending northerly 10.22 miles. HCP 1 Surface

19

0123456789 ID/Year Municipality Scope Name Description Funding

022250.00 Kingman Road Bridge (#5021) over Macwahoc 2018 Macwahoc Plt Kingman Road $135,000 Bridge Improvements - PE Only Stream. Located 0.38 of a mile southeast of Route 2. HCP 4

WR 34564 Bridge and Structural Repairs drains and T beams on Jordan Bridge 2018 Macwahoc Plt Maintenance Route 2A (#3097) over Macwahoc Stream. Located 0.60 of a $38,000 mile from Silver Ridge Road. HCP 4

Macwahoc Plt, North Yarmouth 023366.00 Academy Grant Highway Paving Twp, Silver Beginning at Route 2A and extending north 9.36 2019 Route 2 $342,389 Ridge Twp, T1 miles. Light Capital Paving HCP 4 R5 WELS, Upper Molunkus Twp

WR 34742 Macwahoc Plt, Replacing culverts beginning at the intersection of North Yarmouth Drainage Maintenance 2018 Route 2 Route 2A and extending west 2.0 miles in Macwahoc $43,000 Academy Grant Plt. HCP 4 Twp

WR 34507 Ditching various locations beginning at the Macwahoc Plt, Drainage Maintenance intersection of Route 2A and extending west 6.9 2018 Route 2 $93,000 T1 R5 WELS miles to the Upper Molunkus Twp.-T1 R5 WELS HCP 4 town line.

021736.00 International Bridge (#2399) over St. John River. 2018 Madawaska Bridge Avenue Located 0.27 of a mile north of Route 1 on the $2,215,000 Bridge Improvements - PE Only Canadian Border. HCP 1

022218.00 Bicycle-Pedestrian Beginning at Fourteenth Avenue and extending west 2019/20 Madawaska Urban Highways Route 1 $178,500 0.16 of a mile to Sixteenth Avenue. HCP 1, 2 Sidewalk Construction

022897.00 Highway Safety and Spot Madawaska Improvements Beginning 2.06 miles north of the Stockholm town 2019/20 Route 161 $200,000 Lake Twp line and extending northerly 1.50 miles. HCP 2 Highway Rehabilitation

022118.00 Highway Paving Madawaska, Cleveland/ Beginning at Route 162 and extending northeast 2018 $418,192 Saint Agatha Beaulieu Road 8.86 miles. Light Capital Paving HCP 4

Rail 023456.00 Presque Isle Rail Bridge 21.06 (#7804) over the Presque Isle Sub Mapleton Rail Bridge North Branch Presque Isle Stream, located on the $200,000 2018 Rail Line Presque Isle Sub rail line. Rehabilitation

20

0123456789 ID/Year Municipality Scope Name Description Funding

WR 34891 Drainage Maintenance Replacing culverts (#110337, #110336) located 0.55 2018 Mapleton Route 227 of a mile from the intersection of the Hale Road in $39,000 Mapleton. HCP 4

023372.00 Highway Paving Mapleton, Beginning 0.11 of a mile south of Route 167 and 2019 Parson Road $161,050 Presque Isle extending northerly 4.40 miles. Light Capital Paving HCP 6, 4

WR 32864 Mapleton, Drainage Maintenance Ditching various locations and cleaning culverts 2018 Presque Isle, Parsons Road beginning at the Hale Road and extending south to $59,000 Washburn the Mapleton-Presque Isle town line. HCP 4

022116.00 Highway Paving Beginning at Route 1A and extending east 1.54 2018 Mars Hill Boynton Road $72,713 miles. Light Capital Paving HCP 4

020870.00 Highway Paving Mars Hill, Beginning 0.11 of a mile east of Clark Road and 2018 Route 1 $628,040 Westfield extending northwesterly 1.20 miles. Mill And Fill HCP 1

021737.00 St. Croix Bridge (#3766) over St. Croix Stream. 2018 Masardis Route 11 Located 0.44 of a mile southwest of Blackwater $200,000 Bridge Painting Road. HCP 2

022899.00 Highway Safety and Spot Improvements Large culvert (#110889) located 0.54 of a mile north 2019/20 Masardis Route 11 $250,000 of Garfield Road. HCP 2 Large Culvert Replacement

022252.00 East Hastings Bridge (#3150) over East Hastings 2019/20 Merrill Route 212 Brook. Located 0.96 of a mile east of the Moro Plt. $800,000 Bridge Replacement town line. HCP 3

022116.00 Highway Paving Beginning at Route 1 and extending east 2.81 miles 2018 Monticello Fletcher Road $132,678 to the Canadian Border. Light Capital Paving HCP 4

WR 32640 Removing material under guard rail in various Drainage Maintenance locations beginning at the Ashland-Nashville Plt. 2018 Nashville Plt Route 11 $19,000 town line and extending north 5.22 miles to the HCP 2 Nashville Plt.-Portage Lake town line.

21

0123456789 ID/Year Municipality Scope Name Description Funding

WR 32742 Drainage Maintenance Ditching from the intersection of the Martin Road and 2018 New Canada Route 161 $18,000 extending north 2,000 feet. HCP 2

WR 31244 Drainage Maintenance Ditching various locations beginning at the 2018 New Limerick Station Road intersection of Route 2 and extending south 1.9 miles $20,000 to Drew Lake Road. HCP 4

WR 34189 Bridge and Structural Repairing guard rail and drains on Tannery Bridge Drews Lake (#5247) over South Branch Meduxnekeag River in 2018 New Limerick Maintenance $23,000 Road New Limerick approximately 0.11 of a mile from the HCP 4 Station Road.

Highway Safety and Spot 018843.00 Improvements Large culvert (#135122) located 0.02 of a mile north 2018 New Sweden Route 161 $85,000 of Stockholm Road. Large Culvert Improvements - HCP 2 PE Only

Highway Safety and Spot 021803.00 Improvements Large culvert (#137321) located 0.96 of a mile north 2018 New Sweden Route 161 $51,000 of Jepson Road. Large Culvert Improvements - HCP 2 PE Only

Highway Construction/ 023697.00 Rehabilitation Cross culvert (#942363) located 0.20 of a mile east 2018 Oakfield Ridge Road of Crandall Lane and extending northerly 0.02 of a $55,000 Large Culvert Replacement - mile. HCP 4 PE Only

WR 34574 Bridge and Structural Repair end post, beam ends and bearing on B&A Railroad Yard Bridge (#6085) located on Interstate 2018 Oakfield Maintenance Interstate 95 $15,000 95 southbound approximately 0.55 of a mile north of HCP 1 the Oakfield Smyrna Road.

WR 35040 Department Building and Lot Building crew quarters and repairing foundation to Oakfield Smyrna Oakfield Maintenance Oakfield garage (#21793) located 0.07 of a mile $131,000 2018 Road north of Interstate 95 on the Oakfield Smyrna Road.

WR 34683 Drainage Maintenance Ditching various locations beginning at the junction of 2018 Orient Boundary Road School House Road and extending east 3.04 miles to $24,600 the Canadian border. HCP 4

Highway Construction/ 006462.92 Rehabilitation Beginning at Westfield town line extending north 5.90 2018 Presque Isle Route 1 $2,350,000 miles to Conant Road. Highway Improvements - PE HCP 1 Only

22

0123456789 ID/Year Municipality Scope Name Description Funding

Aviation 018712.01 Safety and infrastructure improvements that may Northern Maine Presque Isle Runway/Taxiway include acquisition of snow removal equipment (plow $61,800 2018 Regional Airport blades) at the Northern Maine Regional Airport (PQI). Capital Equipment Purchase

Aviation 018712.02 Safety and infrastructure improvements that may Northern Maine Presque Isle Runway/Taxiway include Runway and Taxiway painting and crack $252,350 2019/20 Regional Airport sealing at the Northern Maine Regional Airport (PQI). Crack Sealing

Aviation 018712.04 Safety and infrastructure improvements that may Northern Maine Presque Isle Runway/Taxiway include Runway and Taxiway painting and crack $252,350 2018 Regional Airport sealing at the Northern Maine Regional Airport (PQI). Crack Sealing

Aviation 018712.05 Safety and infrastructure improvements that may Northern Maine include construction of the general aviation ramp - Presque Isle Apron $1,030,000 2019/20 Regional Airport Phase 2 at the Northern Maine Regional Airport Reconstruction (PQI).

Aviation 018712.06 Safety and infrastructure improvements that may Northern Maine include acquisition of snow removal equipment Presque Isle Runway/Taxiway $988,800 2019/20 Regional Airport (sweeper with snow blower and 2 plow trucks) at the Capital Equipment Purchase Northern Maine Regional Airport (PQI).

Aviation 018712.07 Safety and infrastructure improvements that may Northern Maine Presque Isle Runway/Taxiway include Runway and Taxiway painting and crack $252,350 2019/20 Regional Airport sealing at the Northern Maine Regional Airport (PQI). Crack Sealing

020538.00 Highway Safety and Spot Improvements 2019/20 Presque Isle McBurnie Road Located 1.10 miles north of Washburn Road. $55,000

HCP 4 Large Culvert Rehabilitation

022118.00 Highway Paving Beginning 0.14 of a mile south of Mapleton town line 2018 Presque Isle Parson Road $14,632 and extending southerly 0.31 of a mile. Light Capital Paving HCP 4

022350.00 H.N. Flagg Memorial Bridge (#2189) over the 2019/20 Presque Isle Bridge Beam Ends & Bearing Route 1 Aroostook River. Located 0.12 of a mile south of $250,000 Painting Reach Road. HCP 1

022582.00 Highway Safety and Spot Improvements Beginning 1.96 miles south of the Mapleton town line 2018 Presque Isle Parsons Road $1,265,000 and extending southerly 0.15 of a mile. HCP 4 Safety Improvements

23

0123456789 ID/Year Municipality Scope Name Description Funding

022964.00 Highway Safety and Spot Improvements Large culvert (#47000) located 0.16 of a mile south 2019/20 Presque Isle Route 164 $200,000 of the Chandler Road. HCP 3 Large Culvert Replacement

Freight 023264.00 Dead River Propane rail car unloading facility, including towers, Presque Isle Line $551,400 2018 Company pumps, and piping. Rehabilitation

023372.00 Highway Paving Spragueville Beginning at Route 1 and extending southwest 1.91 2019 Presque Isle $69,911 Road miles. Light Capital Paving HCP 4

Rail 023454.00 Presque Isle Rail Bridge 24.91 (#7805) over Presque Presque Isle Sub Presque Isle Rail Bridge Isle Stream. Located on the Presque Isle Sub rail $110,000 2019/20 Rail Line line. Scour Countermeasures

023723.00 Highway Paving Beginning 0.06 of a mile north of the Westfield town 2019/20 Presque Isle Route 1 $2,409,888 line and extending northerly 5.61 miles. 1 1/4" Overlay HCP 1

023725.00 Highway Construction/ Rehabilitation Beginning 0.30 of a mile east of Egypt Road and 2019/20 Presque Isle Route 10 $165,000 extending easterly 0.12 of a mile. HCP 3 Highway Rehabilitation

WR 34489 Drainage Maintenance Spragueville Ditching from the intersection of the State Park Road 2018 Presque Isle $18,000 Road and extending east 0.25 of a mile. HCP 4

WR 35285 Drainage Maintenance Ditching various locations from the intersection of the 2018 Presque Isle Route 1 Jameson Road and extending north 2.25 miles to $85,000 University Street. HCP 1

Highway Safety and Spot 021830.00 Improvements Large culvert (#182487) located 0.48 of a mile west 2018 Saint Agatha Cleveland Road $51,000 of the Madawaska town line. Large Culvert Improvements - HCP 4 PE Only

022118.00 Highway Paving Flat Mountain Beginning at Daigle Cross Road and extending east 2018 Saint Agatha $105,256 Road 2.23 miles. Light Capital Paving HCP 4

24

0123456789 ID/Year Municipality Scope Name Description Funding

Highway Safety and Spot 022970.00 Improvements Located 2.16 miles north of Deboullie Mountain Road 2018 Saint Francis Route 161 $75,000 and extending northerly 0.03 of a mile. Slope Stabilization/Protection - HCP 3 PE Only

Highway Safety and Spot 022972.00 Improvements 2018 Saint John Plt Route 161 Located 0.57 of a mile east of Mill Road. $75,000 Slope Stabilization/Protection - HCP 3 PE Only

023364.00 Highway Paving Beginning at Route 2 and extending south 0.80 of a 2019 Silver Ridge Twp Pond Road $29,264 mile. Light Capital Paving HCP 4

022352.00 I-95 NB/ Route 2 Bridge (#1391) over Route 2. 2019/20 Smyrna Interstate 95 NB Located 0.30 of a mile from Exit 291 on Interstate 95 $550,000 Bridge Painting northbound. HCP 1

022354.00 I-95 SB/ Route 2 Bridge (#6089) over Route 2. 2019/20 Smyrna Interstate 95 SB Located 0.08 of a mile east of the Smyrna Center $550,000 Bridge Painting Road. HCP 1

Highway Safety and Spot 023755.00 Improvements Large culvert (#47102) located 0.39 of a mile 2018 Smyrna Route 2 $45,000 southwest of Timoney Lake Road. Large Culvert Replacement - HCP 3 PE Only

Rail 023458.00 Presque Isle Rail Bridge 10.07 (#7800) over west Presque Isle Sub T11 R4 WELS Rail Bridge inlet of Scopan Lake, located on the Presque Isle $580,000 2019/20 Rail Line Sub rail line. Rehabilitation

Rail 023460.00 Presque Isle Sub Presque Isle Rail Bridge 14.04 (#7801) over Small T11 R4 WELS Rail Bridge $1,100,000 2019/20 Rail Line Brook, located on the Presque Isle Sub rail line. Reconstruction

Highway Safety and Spot 023781.00 Improvements Cross culvert (#181630) located 1.46 miles northeast 2018 T17 R4 WELS Route 162 $30,000 of Shore Road. Large Culvert Replacement - HCP 3 PE Only

020421.00 Highway Construction/ Rehabilitation Beginning 0.02 of a mile south of Monroe Street and 2019/20 Van Buren Route 1 $5,660,000 extending northerly 2.74 miles. HCP 1 Reconstruction

25

0123456789 ID/Year Municipality Scope Name Description Funding

022118.00 Highway Paving Beginning 0.04 of a mile south of Parent Road and 2018 Van Buren Route 1 $94,400 extending northerly 2.00 miles. Light Capital Paving HCP 1

022264.00 Castonguay St. Marys Bridge (#5309) over Violette Brook. 2018 Van Buren $100,000 Enhanced Project Scoping - PE Road Located 0.21 of a mile south of Champlain Street. Only HCP 4

022368.00 International Bridge (#2400) over St. John River. 2019/20 Van Buren Bridge Street $800,000 Bridge Strengthening Located 0.12 of a mile northeast of Dufour Drive. HCP 3

Highway Construction/ 022658.00 Rehabilitation Beginning 0.18 of a mile north of Parent Road in Van 2018 Van Buren Route 1 $246,000 Buren and extending northerly 1.91 miles. Highway Improvements - PE HCP 1 Only

023785.00 Highway Safety and Spot Improvements Soldier Pond Beginning at Route 11 and extending east 0.72 of a 2019/20 Wallagrass $245,000 Road mile. HCP 4 Shoulder Improvements

WR 31359 Drainage Maintenance Replacing culvert (#922540) located 2.2 miles south 2018 Washburn Parsons Road $42,000 of the intersection of Castle Hill Road. HCP 4

Highway Safety and Spot 023036.00 Improvements Large culvert (#135124) located 0.06 of a mile 2018 Woodland Route 161 $65,000 northwest of the Goodwin Road. Large Culvert Improvements - HCP 2 PE Only

26

0123456789 Cumberland

Harrison

Bridgton

Naples New Casco Gloucester

Raymond

Sebago Pownal Brunswick Gray Freeport North Yarmouth

Baldwin Cumberland

Yarmouth Windham Cumberland Standish

Falmouth

Gorham Portland Westbrook

Cumberland County South Population 281,673 Portland Land Area (sq mi) 835 Scarborough Bridges 367 Cape Elizabeth Highway Corridor Priority Miles HCP 1 284 HCP 2 137 HCP 3 232 HCP 4 261

Total HCP 1-4 914 Cumberland ID/Year Municipality Scope Name Description Funding

023354.00 Highway Paving Baldwin, Beginning at Route 11 and extending north 2.23 2019 Long Hill Road $101,959 Sebago miles to Route 107. Light Capital Paving HCP 4

023402.00 Highway Paving Baldwin, Beginning at Ossipee Trail Way west and extending 2018 Route 113 $1,624,050 Standish Highway Cyclical Pavement north 12.03 miles to Depot Road. HCP 3 Resurfacing

022665.00 Highway Safety and Spot Improvements Large culvert (#266518) located 0.50 of a mile north 2019/20 Bridgton Route 117 $457,456 of the Denmark town line. HCP 3 Large Culvert Replacement

023354.00 Highway Paving Beginning at Route 302 and extending north 1.58 2019 Bridgton Knights Hill Road $72,240 miles to the Sweden town line. Light Capital Paving HCP 4

023354.00 Highway Paving South High Beginning at Route 117 and extending north 2.01 2019 Bridgton $91,900 Street miles to Route 302. Light Capital Paving HCP 4

WR 35421 Department Building and Lot Construction of an addition to the maintenance Bridgton Maintenance Route 302 $53,000 2018 garage (#36158) at the Bridgton maintenance lot.

023354.00 Highway Paving Bridgton, Beginning at Route 302 and extending north 6.63 2019 Route 93 $303,132 Sweden miles. Light Capital Paving HCP 4

023354.00 Highway Paving Bridgton, Beginning at Route 117 and extending north 3.69 2019 Route 37 $168,712 Waterford miles. Light Capital Paving HCP 4

WR 34976 Ditching and replacing culverts beginning at the Bridgton, Drainage Maintenance 2018 Route 37 intersection of Route 117 and extending north 3.70 $200,000 Waterford miles to intersection of Route 35 in Bridgton. HCP 4

Aviation 018714.01 Safety and infrastructure improvements that may Brunswick Brunswick Runway/Taxiway include pavement repairs and maintenance at the $171,667 2018 Executive Airport Brunswick Executive Airport (BXM). Crack Sealing

27

0123456789 ID/Year Municipality Scope Name Description Funding

Aviation 018714.02 Safety and infrastructure improvements that may Brunswick include pavement repairs and maintenance (north Brunswick Runway/Taxiway $4,120,000 2019/20 Executive Airport ramp and parking lots) at the Brunswick Executive Crack Sealing Airport (BXM).

Aviation 018714.04 Safety and infrastructure improvements that may Brunswick Brunswick Airport Buildings include an itinerant box hangar at the Brunswick $3,090,000 2018 Executive Airport Executive Airport (BXM). New Construction

Aviation 018714.05 Safety and infrastructure improvements that may Brunswick Brunswick Navigation Aids/Lights include south end obstruction removal and wildlife $1,133,000 2018 Executive Airport fencing at the Brunswick Executive Airport (BXM). Removal Of Obstructions

Aviation 018714.06 Safety and infrastructure improvements that may Brunswick Brunswick Airport Buildings include airport electrical improvements at the $1,287,500 2018 Executive Airport Brunswick Executive Airport (BXM). Rehabilitation

Aviation 018714.07 Safety and infrastructure improvements that may Brunswick Brunswick Airport Buildings include the construction of a 10-unit T-Hangar at the $1,133,000 2019/20 Executive Airport Brunswick Executive Airport (BXM). New Construction

Aviation 018714.08 Safety and infrastructure improvements that may Brunswick Brunswick Planning And Research include a sustainability master plan at the Brunswick $206,000 2019/20 Executive Airport Executive Airport (BXM). Planning Studies

Aviation 018714.10 Safety and infrastructure improvements that may Brunswick Brunswick Runway/Taxiway include drainage repairs - Phase 2 at the Brunswick $412,000 2018 Executive Airport Executive Airport (BXM). Reconstruction

Aviation 018714.11 Safety and infrastructure improvements that may Brunswick Brunswick Runway/Taxiway include the acquisition of snow removal equipment at $257,500 2019/20 Executive Airport the Brunswick Executive Airport (BXM). Capital Equipment Purchase

Aviation 018714.12 Safety and infrastructure improvements that may Brunswick Brunswick Runway/Taxiway include mitigation fees at the Brunswick Executive $515,000 2018 Executive Airport Airport (BXM). New Construction

Aviation 018714.13 Safety and infrastructure improvements that may Brunswick Brunswick Airport Buildings include hangar 5 and 6 solar power installation at the $2,060,000 2019/20 Executive Airport Brunswick Executive Airport (BXM). Rehabilitation

28

0123456789 ID/Year Municipality Scope Name Description Funding

Aviation 018714.17 Safety and infrastructure improvements that may Brunswick Brunswick Runway/Taxiway include pavement repairs and maintenance at the $171,667 2019/20 Executive Airport Brunswick Executive Airport (BXM). Crack Sealing

018811.00 Highway Safety and Spot Improvements Large culvert (#226919) located 0.04 of a mile east 2019/20 Brunswick Old Bath Road $270,000 of Bay Bridge Road. HCP 4 Large Culvert Replacement

018879.00 Bicycle-Pedestrian Install four pedestrian activated flashing crosswalk 2019/20 Brunswick Trail, On-Road Maine Street $246,320 warning systems at various locations. HCP 2 New Construction

020860.00 Highway Paving Interstate 295 Beginning at Route 1 and extending west 0.89 of a 2018 Brunswick $629,682 Ramp mile (includes ramps for a total length of 1.89 miles). Mill And Fill HCP 1

020861.00 Highway Paving Beginning at Pleasant Street and extending north 0.53 of a mile to 0.06 of a mile easterly of Mill Street, 2018 Brunswick Route 1 $819,000 including 0.28 of a mile on the on-ramp from Maine Mill And Fill HCP 1, 2 Street to Route 1S.

021714.00 Maine Street Bridge (#5884) over Route 1. Located 2019/20 Brunswick Route 24B $1,400,000 Bridge Deck Replacement 0.04 of a mile south of Mason Street. HCP 2

021910.00 Highway Safety and Spot Improvements Located at the intersection of Route 1 and Stanwood 2019/20 Brunswick Route 1 $1,350,000 Street. HCP 1 Auxiliary Turning Lanes

022679.00 Highway Safety and Spot Improvements Overlay and stripe to provide parallel acceleration 2018 Brunswick Route 1 $65,000 lanes at Maine Street Ramp. HCP 1 Safety Improvements

WR 33387 Removing trees on Route 1 north and southbound Custodial Maintenance beginning at Cook's Corner overpass, extending 2018 Brunswick Route 1 $250,000 north 2.25 miles to in HCP 1 Brunswick.

WR 35448 Bridge and Structural Mill and fill wearing surface and new joint headers on Brunswick Maintenance Durham Road Durham Road Over US Route 1 Bridge (#6287). $67,000 2018 Located 0.07 of a mile east of Moody Road.

29

0123456789 ID/Year Municipality Scope Name Description Funding

WR 35450 Bridge and Structural Mill and fill wearing surface and replacing joint headers on Durham Road Bridge (#5685) over Brunswick Maintenance Durham Road $55,000 2018 Interstate 295. Located 0.15 of a mile east of Moody Road.

Brunswick, 023663.00 Cumberland, Highway Safety and Spot Implement Transportation System Management Falmouth, Improvements (TSM) actions to improve safety, reliability, and level 2019/20 Interstate 295 $1,000,000 Freeport, of service along the Interstate 295 Corridor between HCP 1 Topsham, Safety Improvements Falmouth and Topsham. Yarmouth

Bicycle-Pedestrian 022212.00 Beginning at the Swinging Bridge, to Mill Street, Bow Brunswick, Trail, On-Road 2018 Cabot Street Street and Cabot Street and extending 0.32 of a mile $80,000 Topsham Bicycle/Pedestrian to the Frank J. Wood Bridge (#2016). HCP 3 Improvements - PE Only

022603.00 Frank J. Wood Bridge (#2016) over Androscoggin Brunswick, 2019/20 Route 201 River. Located at the Brunswick - Topsham town $14,900,000 Topsham Bridge Improvements line. HCP 2

022086.00 Highway Paving Beginning at Spurwink Avenue and extending 2018 Cape Elizabeth Route 77 $10,644 northwest 0.34 of a mile. Light Capital Paving HCP 4

022416.00 Highway Paving Beginning at Brentwood Road and extending east 2019/20 Cape Elizabeth Scott Dyer Road 0.57 of a mile to Ocean House Road . PACTS $227,698 1 1/4" Overlay Sponsored. HCP 4

023583.00 Highway Safety and Spot Improvements Located at the intersection of Route 11 and Route 2019/20 Casco Route 11 $35,000 121. HCP 3 Safety Improvements

WR 32955 Drainage Maintenance Dtiching and culvert replacement (#86252) beginning 2018 Casco State Park Road at the intersection of Route 302 extending west 1.65 $45,000 miles to the Sebago-Naples town line. HCP 4

022476.00 Casco, Naples, Highway Paving Beginning at Whites Bridge Road and extending 2019/20 Raymond, Route 302 $3,944,993 northwest 11.41 miles to Route 11. Windham Hot In Place Recycled HCP 1

023370.00 Highway Paving Casco, Beginning at Route 11 and extending south 4.63 2019 Route 121 $169,365 Raymond miles. Light Capital Paving HCP 4

30

0123456789 ID/Year Municipality Scope Name Description Funding

023370.00 Highway Paving Casco, Beginning 0.09 of a mile north of Egypt Road and 2019 Route 85 $152,904 Raymond extending northerly 4.18 miles. Light Capital Paving HCP 4

WR 34893 Drainage Maintenance Grader ditching and culvert replacement (#86098) 2018 Casco, Naples State Park Road beginning at the intersection of Route 11 extending $110,000 east 2.55 miles to the Naples-Casco town line. HCP 4

021777.00 Highway Safety and Spot Improvements Large culvert (#46804) located 0.04 of a mile north of 2019/20 Cumberland Route 9 $340,000 Turkey Lane. HCP 3 Large Culvert Replacement

021778.00 Highway Construction/ Rehabilitation Beginning 0.03 of a mile east of Crossing Brook 2018 Cumberland Tuttle Road Road and extending easterly 0.16 of a mile. PACTS $500,000 Sponsored MPI. HCP 4 Reconstruction

022088.00 Highway Paving Beginning at Route 88 and extending northwest 3.38 2018 Cumberland Tuttle Road $119,398 miles. Light Capital Paving HCP 4

022088.00 Highway Paving Beginning 0.01 of a mile north of the Falmouth town 2018 Cumberland Winn Road line and extending northerly 0.79 of a mile to Route $27,907 Light Capital Paving 9. HCP 4

022668.00 Highway Safety and Spot Improvements Large culvert (#46210) located 0.04 of a mile 2019/20 Cumberland Tuttle Road $295,000 southeast of Harris Road. HCP 4 Large Culvert Replacement

Marine 023809.00 Cumberland Piers, Floats And Fenders Broad Cove Broad Cove Pier. $530,000 2019/20 Rehabilitation

WR 34766 Custodial Maintenance Brush clearing beginning at the Cumberland- 2018 Cumberland Route 88 $15,000 Falmouth town line extending north 1.00 mile. HCP 4

019357.18 Long Creek Watershed Management District Cumberland Long Creek assessment; to monitor storm water quantity and $186,000 2018 County Watershed Natural Resource Mitigation quality from MaineDOT porous pavement project(s).

31

0123456789 ID/Year Municipality Scope Name Description Funding

019357.19 Long Creek Watershed Management District Cumberland Long Creek assessment; to monitor storm water quantity and $186,000 2019/20 County Watershed Natural Resource Mitigation quality from MaineDOT porous pavement project(s).

019357.20 Long Creek Watershed Management District Cumberland Long Creek assessment; to monitor storm water quantity and $186,000 2019/20 County Watershed Natural Resource Mitigation quality from MaineDOT porous pavement project(s).

022088.00 Highway Paving Cumberland, Beginning 0.31 of a mile north of Mast Road and 2018 Blackstrap Road $120,458 Falmouth extending northerly 3.41 miles to Route 26. Light Capital Paving HCP 4

022088.00 Highway Paving Cumberland, Beginning 1.85 miles south of the Cumberland town 2018 Route 26 $233,852 Falmouth, Gray line and extending northerly 6.62 miles. Light Capital Paving HCP 3

023695.00 Highway Construction/ Durham, North Rehabilitation Beginning at the intersection of Parsonage Road and 2019/20 Yarmouth, Route 9 $2,910,000 extending north 11.89 miles to Route 136. Pownal HCP 3 PMRAP DOT Pugmill

Marine 020843.00 Falmouth Town Replace and expand float system and new gangway Falmouth Piers, Floats And Fenders $112,000 2019/20 Landing at the Town Landing Pier. New Construction

021653.00 Highway Safety and Spot Improvements Located at the intersection of Route 9, Falmouth 2019/20 Falmouth Route 9 $225,000 Road and Bucknam Road. PACTS Sponsored MPI. HCP 4, 3 Intersection Improvements

021720.00 Bucknam Road/ I-295 Bridge (#5830) over Interstate 2019/20 Falmouth Bucknam Road $4,205,000 Bridge Deck Replacement 295. Located 0.30 of a mile northwest of Route 1. HCP 3

021721.00 Johnson Road/ I-295 Bridge (#5792) over Interstate 2019/20 Falmouth Johnson Road $2,775,000 Bridge Rehabilitation 295. Located 0.25 of a mile west of Route 1. HCP 6

021722.00 Libby Bridge (#2457) over the . 2018 Falmouth Route 26 $265,000 Bridge Rehabilitation Located 0.43 of a mile north of the Falmouth Road. HCP 3

32

0123456789 ID/Year Municipality Scope Name Description Funding

021723.00 Lunt Road/ I-295 Bridge (#5829) over Interstate 295. 2018 Falmouth Lunt Road $3,515,000 Bridge Rehabilitation Located 0.10 of a mile south of Route 9. HCP 4

Beginning at Robert's Road and extending north 1.83 021784.00 Highway Construction/ miles to Libby Bridge (#2457) and beginning 1.00 Rehabilitation mile north of Libby Bridge and extending north 1.04 2018 Falmouth Route 26 $11,100,000 miles to Hurricane Road. Also includes sidewalk HCP 2, 3, 4 Reconstruction improvements on Leighton Road and Falmouth Road.

022088.00 Highway Paving Beginning 0.33 of a mile north of Brook Road and 2018 Falmouth Blackstrap Road $36,032 extending northerly 1.02 miles. Light Capital Paving HCP 4

022310.00 Presumpscot Falls Bridge (#5669) over Presumpscot Allen Avenue 2018 Falmouth River. Located 0.21 of a mile northeast of Pleasant $900,000 Extension Bridge Rehabilitation Hill Road. HCP 3

022418.00 Highway Paving Beginning at Staples Point Bridge (#5278), over the 2019/20 Falmouth Route 9 and extending north 0.82 of a $437,203 1 1/4" Overlay mile to Lunt Road. PACTS Sponsored. HCP 4

022422.00 Highway Paving Interstate 495 eastbound and westbound including all 2019/20 Falmouth Interstate 495 $796,000 ramps to Interstate 295 and Route 1. Mill And Fill HCP 1

022672.00 Highway Safety and Spot Improvements Install signal with turn lanes at Interstate 295 2019/20 Falmouth Bucknam Road $640,000 northbound off-ramp. HCP 3 Safety Improvements

WR 32998 Drainage Maintenance Replacing cross culvert (#99390) on Blackstrap Road 2018 Falmouth Falmouth located 0.20 of a mile north of Hemlock Cove Road $25,000 in Falmouth. HCP 4

021652.00 Highway Paving Beginning at the Yarmouth town line and extending 2018 Freeport Route 1 north 2.88 miles to Desert Road. Includes 300 feet $1,357,748 1 1/4" Overlay of Desert Road. PACTS Sponsored. HCP 3

021726.00 Approach Road Interchange Bridge (#5721) over 2018 Freeport Route 125 Interstate 295. Located 0.44 of a mile northwest of $200,000 Bridge Improvements - PE Only Route 1. HCP 3

33

0123456789 ID/Year Municipality Scope Name Description Funding

022186.00 Highway Paving Beginning at Smelt Brook Road and extending north South Freeport 2018 Freeport 1.90 miles to Porter's Landing Road. PACTS $678,000 Road 1 1/2 Overlay Sponsored MPI. HCP 4

022424.00 Highway Paving Beginning at Desert Road and extending north 0.91 2018 Freeport Route 1 $753,815 of a mile to Summer Street. PACTS Sponsored. Mill And Fill HCP 3

022871.00 Highway Safety and Spot Improvements 2018 Freeport Interstate 295 NB Replace lighting at Interstate 295 Exit #22. $625,000

HCP 1 Lighting

Highway Safety and Spot 023589.00 Improvements Beginning at the Interstate 295 northbound off-ramp 2018 Freeport Desert Road extending west 0.24 of a mile (includes 0.04 of a $250,000 Safety Improvements - PE mile of divided highway). HCP 3, 6 Only

023627.00 Merrill Road Bridge (#5720) over Interstate 295. 2018 Freeport Desert Road $200,000 Bridge Improvements - PE Only Located 0.14 of a mile southeast of Hunter Road. HCP 3

WR 33113 Drainage Maintenance Replacing a large culvert (#968402) between Route 2018 Freeport Route 125 $350,000 136 and Woodside Lane. HCP 3

021725.00 Freeport, Route 1/ Bridge (#2183) over Cousins 2019/20 Route 1 $2,250,000 Yarmouth Bridge Replacement River. Located on the Freeport-Yarmouth town line. HCP 3

018821.00 Highway Safety and Spot Improvements Large culvert (#47422) located 0.41 of a mile north of 2019/20 Gorham Route 25 $1,445,000 State Street. HCP 2 Large Culvert Replacement

020277.00 Highway Construction/ Rehabilitation Beginning 0.09 of a mile north of Johnson Road and 2018 Gorham Route 25 $5,188,338 extending westerly 1.48 miles. HCP 1, 2 Highway Rehabilitation

020864.00 Highway Paving Beginning 0.19 of a mile south of the Waterhouse 2018 Gorham Route 114 Road and extending northerly 2.00 miles to Route $1,628,148 1 1/4" Overlay 202. PACTS Sponsored. HCP 3

34

0123456789 ID/Year Municipality Scope Name Description Funding

022238.00 Mitchell Bridge (#0216) over . 2018 Gorham Enhanced Project Scoping - PE Mitchell HIll Road Located 0.04 of a mile northwest of the Scarborough $115,000 Only town line. HCP 6

022873.00 Highway Safety and Spot Improvements Located at the intersection of Route 25 and Libby 2019/20 Gorham Route 25 $380,000 Avenue. HCP 1 Intersection Improvements

023591.00 Highway Safety and Spot Improvements Located at the intersection of Route 202 and Route 2019/20 Gorham Route 202 114; Route 202 and Water Street; and Route 202 $710,600 and New Portland Road. HCP 1 Intersection Improvements

020891.00 Highway Paving Beginning at Main Street/New Gorham Road and Gorham, extending west 3.51 miles to 0.01 of a mile westerly 2019/20 Route 25 $956,000 Westbrook of Johnson Road; including Ramp 25E for 0.08 of a 1 1/4" Overlay HCP 1 mile.

018766.00 Highway Safety and Spot Improvements Located at the intersection of Route 26 and North 2019/20 Gray Route 26 $1,555,000 Raymond Road. HCP 1 Intersection Improvements

023294.00 Highway Paving Beginning on Route 26A at Route 202, extending northwest 1.18 miles to Route 26. Beginning on 2018 Gray Route 26/26A $504,699 Ultra Thin Bonded Wearing Route 26 at Route 202, extending northwest 1.26 HCP 1 Surface miles.

023370.00 Highway Paving Beginning at Route 115 and extending north 2.89 2019 Gray Route 4 $105,716 miles. Light Capital Paving HCP 1, 2

WR 34950 Custodial Maintenance Brush removal beginning at the intersection of Liberty 2018 Gray Route 202 Avenue extending west 2.95 miles to the Windham- $45,000 Gray town line. HCP 2

022088.00 Highway Paving Gray, New Beginning at Route 115 and extending northeast 2018 Depot Road $98,910 Gloucester 2.80 miles to Route 231. Light Capital Paving HCP 4

WR 35341 Department Building and Lot Portland Road, Converting maintenance buildings over to LED Gray, Topsham Maintenance Maintenance $38,000 2018 lighting at the Topsham and Gray maintenance lots. Way

35

0123456789 ID/Year Municipality Scope Name Description Funding

022094.00 Highway Paving Cundys Harbor Beginning 0.10 of a mile south of Route 24 and 2018 Harpswell $162,840 Road extending southerly 4.60 miles. Light Capital Paving HCP 4

Marine 023472.00 George J. Harpswell Piers, Floats And Fenders Navy pier at Mitchell Field. $320,000 2019/20 Mitchell Field Rehabilitation

WR 34762 Custodial Maintenance Removing trees and brush beginning at the 2018 Harpswell Route 24 intersection of Linwood Lane and extending north $15,000 1.00 mile. HCP 4

WR 34655 Bridge and Structural Repair concrete abutments and wings on Edes Falls Naples Maintenance Edes Falls Road Bridge (#3347) over the Crooked River. Located $30,000 2018 0.03 of a mile east of River Road.

WR 34778 Bridge and Structural Songo Lock Drawbridge (#2780) over movable bridge maintenance to ensure the ability for 2018 Naples Maintenance State Park Road $17,000 marine traffic to pass by the bridge. Located 0.01 of HCP 4 a mile northwest of Lock Lane.

018982.00 Morse Road Bridge (#3368) over . 2018 New Gloucester Morse Road $60,000 Bridge Wearing Surface Located 1.01 miles northwest of Route 231. Replacement HCP 6

WR 34947 Custodial Maintenance Brush removal beginning at the Gray-New 2018 New Gloucester Route 26 Gloucester town line and extending north 3.35 miles $55,000 to the New Gloucester-Poland town line. HCP 1

023370.00 Highway Paving New Gloucester, Beginning at Route 231 and extending east 1.83 2019 Allen Road $66,941 Pownal miles. Light Capital Paving HCP 4, 6

WR 34915 Ditching in preparation of Light Capital Paving (LCP) New Gloucester, Drainage Maintenance 2018 Allen Road project, beginning at Route 231 extending east 3.05 $55,000 Pownal miles to Elmwood Road. HCP 4

022338.00 Walnut Hill Bridge (#0188) over MCRR. Located 2019/20 North Yarmouth Route 9 $500,000 Bridge Substructure 0.14 of a mile north of Hazel Lane. Rehabilitation HCP 3

36

0123456789 ID/Year Municipality Scope Name Description Funding

Highway Construction/ 023693.00 Rehabilitation Large culvert (#911957) located 0.05 of a mile south 2018 North Yarmouth Route 115 $100,000 of Mill Road. Large Culvert Replacement - HCP 3 PE Only

WR 34765 Ditching beginning at intersection of Elmwood Road North Yarmouth, Drainage Maintenance 2018 Route 9 and extending west 5.30 miles to the intersection of $150,000 Pownal Parsonage Road. HCP 3

Highway Safety and Spot 014815.00 Improvements Feasibility study and preliminary engineering for intersection improvements beginning at Marginal 2018 Portland Franklin Street $746,500 Way and extending southeast 0.74 of a mile to Enhanced Project Scoping - PE HCP 1, 2 Commercial Street. PACTS Sponsored. Only

017628.00 Highway Construction/ Rehabilitation Beginning at Elm Street and extending 0.26 of a mile 2019/20 Portland Somerset Street to Hanover Street, including part of the Bayside Trail. $433,175 This project is only partially funded for construction. HCP 6 Reconstruction

Highway Construction/ 017628.10 Rehabilitation Feasibility study and alternatives analysis for the extension of Somerset Street from Hanover Street to Portland Somerset Street $200,000 2018 Forest Avenue, combining with the intersection at Highway Improvements - PE High Street and Forest Avenue. Only

018364.01 Bicycle-Pedestrian Trail improvements and widening of the sidewalk 2018 Portland Trail, On-Road Bayside Trail located at the intersection of Franklin Street and $130,000 Marginal Way. HCP 2, 1 Reconstruction

Bicycle-Pedestrian 018469.00 Beginning at Union Branch along Hadlock Field and Trail, On-Road Portland Bayside Trail extending 1.50 miles to the Parkway and $235,805 2018 Bicycle/Pedestrian ending at the Portland Transportation Center. Improvements - PE Only

018624.00 Highway Construction/ Rehabilitation Brighton Avenue, Beginning at Bedford Street and extending west 0.09 2019/20 Portland $2,868,809 Deering Avenue of a mile. PACTS Sponsored. HCP 3 Roundabout Construction

018664.00 Highway Safety and Spot Connection between Congress Street signals via Improvements overhead hardwire to existing signals on Brighton 2018 Portland Congress Street Avenue at Stevens Avenue intersection and the city's $330,000 streetwise Advanced Traffic Management System HCP 2 Traffic Signals (ATMS). PACTS Sponsored.

Aviation Safety and infrastructure improvements that may 018711.01 Portland include environmental assessment mitigation Portland Runway/Taxiway International $1,115,490 2019/20 measures at the Portland International Jetport Jetport New Construction (PWM).

37

0123456789 ID/Year Municipality Scope Name Description Funding

Aviation Safety and infrastructure improvements that may 018711.02 Portland include construction of air cargo taxiway - Phase 1 Portland Runway/Taxiway International $4,326,000 2019/20 (Taxiway "G" to Taxiway "A") at the Portland Jetport New Construction International Jetport (PWM).

Aviation Safety and infrastructure improvements that may 018711.03 Portland include acquisition of snow removal vehicle for Portland Runway/Taxiway International $390,370 2018 airway lights and signs at the Portland International Jetport Capital Equipment Purchase Jetport (PWM).

Aviation Safety and infrastructure improvements that may 018711.04 Portland include long-term hold area, deicing pad expansion Portland Apron International $3,327,525 2019/20 and remaining overnight apron construction - Phase Jetport New Construction 1 at the Portland International Jetport (PWM).

Aviation Safety and infrastructure improvements that may 018711.05 Portland include acquisition of snow melt equipment for Portland Runway/Taxiway International $367,243 2019/20 contaminated snow at the Portland International Jetport Capital Equipment Purchase Jetport (PWM).

Aviation Safety and infrastructure improvements that may 018711.07 Portland include Gate 1 Apron reconstruction for Taxiway "C" Portland Apron International north - Phase 2 and Terminal Apron expansion $4,443,016 2018 Jetport northwest end - Phase 2 at the Portland International Reconstruction Jetport (PWM).

Aviation Safety and infrastructure improvements that may 018711.08 Portland include Runway 11 Taxiway Bypass and Perimeter Portland Runway/Taxiway International $1,133,000 2019/20 service road realignment at the Portland International Jetport New Construction Jetport (PWM).

Aviation 018711.09 Portland Safety and infrastructure improvements that may Portland Runway/Taxiway International include construction of Taxiway "B" Runway 36 to 29 $3,382,520 2019/20 Jetport at the Portland International Jetport (PWM). New Construction

Aviation Safety and infrastructure improvements that may 018711.10 Portland include long-term hold area, deicing pad expansion Portland Apron International $2,884,063 2019/20 and remaining overnight apron construction - Phase Jetport New Construction 2 at the Portland International Jetport (PWM).

Aviation Safety and infrastructure improvements that may 018711.11 Portland include tree removal for Glidepath Qualification Portland Navigation Aids/Lights International $58,710 2019/20 Surface (GQS) on Runway 36 end at the Portland Jetport Removal Of Obstructions International Jetport (PWM).

Bicycle-Pedestrian 018865.00 Multiuse trail. Beginning at Beach Street and Portland Trail, Off-Road Route 1A $353,488 2019/20 extending west 0.57 of a mile. New Construction

38

0123456789 ID/Year Municipality Scope Name Description Funding

018869.18 Public Transportation Urban Transit FTA Section 5307 for ADA Operating - Portland Portland $509,120 2018 ADA Operating Transit Agencies. Operating Assistance

018869.19 Public Transportation Urban Transit FTA Section 5307 for ADA Operating - Portland Portland $337,499 2019 ADA Operating Transit Agencies. Operating Assistance

018869.20 Public Transportation Urban Transit FTA Section 5307 for ADA Operating - Portland Portland $344,249 2020 ADA Operating Transit Agencies. Operating Assistance

018870.18 Public Transportation Urban Transit FTA Section 5307 for urban transit planning - Portland $119,174 2018 Planning Portland. Administrative Assistance

018870.19 Public Transportation Urban Transit FTA Section 5307 for urban transit planning - Portland $343,214 2019 Planning Portland. Administrative Assistance

018870.20 Public Transportation Transit Planning Assistance for Portland Area Transit Urban Transit Portland Agencies, Federal Transit Administration § 5307 for $150,000 2020 Planning Administrative Assistance urbanized area transit.

Bicycle-Pedestrian 018886.00 Portland Trail, Off-Road Bayside Trail Intersection improvements with Eastern Prom Trail. $144,300 2018 Reconstruction

018887.00 Bicycle-Pedestrian Sidewalk improvements located at the intersection of 2018 Portland Trail, On-Road Forest Avenue Forest Avenue and Dartmouth Street for 0.01 of a $103,805 mile. HCP 1 Rehabilitation

Highway Construction/ 020547.00 Rehabilitation Neighborhood Beginning at Deering Center and extending north Portland $375,626 2019/20 Byway 1.30 miles. PACTS Sponsored. New Construction

020625.18 Public Transportation Urban Transit FTA Section 5337 for Capital Assistance - Portland Portland $800,000 2018 Capital UZA Fixed Guideway for Casco Bay Lines. Capital Equipment Purchase

39

0123456789 ID/Year Municipality Scope Name Description Funding

020625.19 Public Transportation Urban Transit FTA Section 5337 for Capital Assistance - Portland Portland $800,000 2019/20 Capital UZA Fixed Guideway for Casco Bay Lines. Capital Equipment Purchase

020625.20 Public Transportation Urban Transit FTA Section 5337 for Capital Assistance - Portland Portland $800,000 2019/20 Capital UZA Fixed Guideway for Casco Bay Lines. Capital Equipment Purchase

020634.18 Public Transportation Urban Transit Portland FTA Section 5339 Capital Assistance Portland UZA. $275,000 2018 Capital Capital Equipment Purchase

020634.19 Public Transportation Urban Transit Portland FTA Section 5339 Capital Assistance Portland UZA. $275,000 2019/20 Capital Capital Equipment Purchase

020634.20 Public Transportation Urban Transit Portland FTA Section 5339 Capital Assistance Portland UZA. $275,000 2019/20 Capital Capital Equipment Purchase

020646.18 Public Transportation Urban Transit FTA Section 5307 for capital projects TBD - Portland Portland $7,692,724 2018 Capital Transit Agencies. Capital-Eligible Maintenance

020646.19 Public Transportation Urban Transit FTA Section 5307 for capital projects TBD - Portland Portland $7,874,541 2019/20 Capital Transit Agencies. Capital-Eligible Maintenance

020646.20 Public Transportation Urban Transit FTA Section 5307 for capital projects TBD - Portland Portland $3,392,271 2019/20 Capital Transit Agencies. Capital-Eligible Maintenance

Marine 020849.00 New float system at East End Park. Located at Cutter Portland Piers, Floats And Fenders Float System $250,000 2019/20 Street. New Construction

021745.00 Veranda Street Bridge (#5933) over Veranda Street. 2019/20 Portland Interstate 295 $12,520,000 Bridge Replacement Located 0.15 of a mile south of Route 1. HCP 1

40

0123456789 ID/Year Municipality Scope Name Description Funding

Marine 021816.00 Fore Street Portland Piers, Floats And Fenders Marina expansion located at Fore Street Marina. $6,852,348 2018 Marina New Construction

021832.00 Public Transportation Transportation Preliminary engineering and partial construction Portland $5,750,000 2019/20 Center funding for Portland Transportation Center. Capital Equipment Purchase

021928.12 Highway Paving Municipal Partnership Initiative Program. Beginning Washington 2018 Portland at Route 9 (Lunt's Corner) and extending north 1.42 $1,000,000 Avenue Mill And Fill miles to Allen Avenue. HCP 2

021928.13 Highway Paving Municipal Partnership Initiative Program: Beginning 2019/20 Portland Stevens Avenue at Forest Avenue and extending north 0.88 of a mile $521,880 Mill And Fill to Clinton Street. HCP 2

Freight 021942.04 Freight Monitoring Systems & Purchase rail packer for International Marine Portland Rail Packer $856,455 2018 Equipment Terminal operations.

Capital Equipment Purchase

Marine 021942.06 Remove existing maintenance building and infill Portland Buildings Wharf $4,282,400 2018 12,000 square feet of terminal marine wharf. Demolition/Removal

Marine 021942.07 Terminal Grading/Paving/Striping: striping for truck Portland Parking Lots Terminal Grading $416,011 2018 access and container placement and drainage. Rehabilitation

Freight 021942.09 Freight Monitoring Systems & Mobile Harbor Purchase of mobile harbor crane for International Portland $4,492,250 2018 Equipment Crane Marine Terminal operations.

Capital Equipment Purchase

022132.00 Highway Safety and Spot Improvements Cumberland Beginning at State Street and extending northeast 2018 Portland $634,260 Avenue 0.62 of a mile to Myrtle Street. PACTS Sponsored. HCP 3 Intersection Improvements

022164.00 Highway Paving Cumberland Beginning at State Street and extending north 0.46 of 2019/20 Portland $397,100 Avenue a mile to Elm Street. PACTS Sponsored. Mill And Fill HCP 3

41

0123456789 ID/Year Municipality Scope Name Description Funding

022170.00 Highway Paving Beginning at High Street and extending south 0.83 of 2019/20 Portland Danforth Street $706,600 a mile to Vaughn Street. PACTS Sponsored. Mill And Fill HCP 4

022188.00 Highway Paving Beginning at Pennell Avenue and extending north 2018 Portland Route 100 0.19 of a mile to Washington Avenue. PACTS $275,000 Mill And Fill Sponsored MPI. HCP 2

Greater Portland Transit District, Metro, core service 022328.00 Public Transportation frequency improvements and system expansion in Portland Metro/Husky Line the communities of Gorham, Westbrook, Portland $813,594 2019 Operating Assistance and South Portland in partnership with the University of Southern Maine. FTA Transfer.

Greater Portland Transit District, Metro, core service 022328.20 Public Transportation frequency improvements and system expansion in Portland Metro/Husky Line the communities of Gorham, Westbrook, Portland $779,778 2020 Operating Assistance and South Portland in partnership with the University of Southern Maine. Year 2-FTA Transfer.

Highway Construction/ 022394.00 Rehabilitation Beginning 0.16 of a mile south of Washington 2018 Portland Interstate 295 Avenue northbound and extending northerly 1.25 $250,000 Highway Improvements - PE miles. HCP 1 Only

022450.00 Highway Paving Beginning at Washington Avenue and extending 2018 Portland Allen Avenue north 0.73 of a mile to Summit Street. PACTS $425,000 Mill And Fill Sponsored. HCP 3

022452.00 Highway Paving Beginning at Greenwood Lane and extending Washington 2019/20 Portland northwest 0.61 of a mile to Riverside Street. PACTS $463,763 Street Mill And Fill Sponsored. HCP 3

022705.18 Marine Casco Bay Island Passenger Ferry Program. Allocation for capital 2018 Portland Piers, Floats And Fenders $635,981 Transit District improvements. HCP 6 Rehabilitation

022705.19 Marine Casco Bay Island Passenger Ferry Program. Allocation for capital 2019/20 Portland Piers, Floats And Fenders $635,981 Transit District improvements. HCP 6 Rehabilitation

022705.20 Marine Casco Bay Island Passenger Ferry Program. Allocation for capital 2019/20 Portland Piers, Floats And Fenders $635,981 District improvements. HCP 6 Rehabilitation

42

0123456789 ID/Year Municipality Scope Name Description Funding

022762.18 Public Transportation Urban Transit FTA Section 5307 for Operating Assistance - Portland $6,389,602 2018 Operating Portland Transit Agencies. Operating Assistance

022762.19 Public Transportation Urban Transit FTA Section 5307 for Operating Assistance - Portland $6,715,226 2019 Operating Portland Transit Agencies. Operating Assistance

022762.20 Public Transportation Urban Transit FTA Section 5307 for Operating Assistance - Portland $6,849,530 2020 Operating Portland Transit Agencies. Operating Assistance

022785.00 Public Transportation Casco Bay Island FTA Section 5307 CBITD Phase II - Terminal Portland $3,200,000 2018 Transit District Project. New Construction

Marine 022998.00 Portland Marine Buildings IMT Port Security Port Security Grant at International Marine Terminal. $385,000 2018 Rehabilitation - PE Only

Marine 023044.00 Freight Monitoring Systems & Acquisition of new reach stacker to support terminal Portland Reach Stacker $700,000 2019/20 Equipment operations at the International Marine Terminal.

Capital Equipment Purchase

023344.00 Public Transportation Portland Area Comprehensive Transportation Urban Transit System(PACTS), Federal Transit Administration § Portland $321,552 2018 Planning 5303 for metropolitan planning Fiscal Year 2018. Administrative Assistance Funds are transferred to FHWA.

023344.19 Public Transportation Portland Area Comprehensive Transportation Urban Transit System (PACTS), Federal Transit Administration § Portland $321,552 2019 Planning 5303 for metropolitan planning Fiscal Year 2019. Administrative Assistance Funds are transferred to FHWA.

023344.20 Public Transportation Portland Area Comprehensive Transportation Urban Transit System (PACTS), Federal Transit Administration § Portland $321,552 2020 Planning 5303 for metropolitan planning Fiscal Year 2020. Administrative Assistance Funds are transferred to FHWA.

023408.00 Highway Paving Beginning at St. John Street and extending west 0.26 2018 Portland Route 22 $112,210 of a mile. Mill And Fill HCP 2

43

0123456789 ID/Year Municipality Scope Name Description Funding

023410.00 Highway Paving Beginning at St. John Street and extending north 2018 Portland Valley Street $166,300 0.75 of a mile to Park Avenue. Mill And Fill HCP 3

023416.00 Highway Paving Beginning at Yale Street extending north 0.38 of a 2018 Portland Allen Avenue $367,500 mile to Pennell Avenue. PACTS Sponsored MPI. 1 1/4" Overlay HCP 2

023468.00 Public Transportation Casco Bay Island Construction of new ferry for Casco Bay Island Portland $10,000,000 2018 Transit District Transit District. New Construction

023545.00 CNRR Crossing Bridge (#5616) under Interstate 295. 2018 Portland Interstate 295 $500,000 Bridge Substructure Located 1.45 miles south of the Falmouth town line. Rehabilitation HCP 1

023661.00 Washington Avenue SB Bridge (#0820) over Washington 2019/20 Portland Interstate 295. Located 0.15 of a mile south of $800,000 Bridge Wearing Surface Avenue Replacement Interstate 295 Exit 8 southbound. HCP 1

023711.00 Highway Paving Beginning 0.11 of a mile north of Warren Avenue and 2019/20 Portland Riverside Street $562,480 extending northerly 0.97 of a mile. Mill And Fill HCP 2

023713.00 Highway Construction/ Rehabilitation Beginning at Fox Street and extending north 0.43 of 2019/20 Portland Franklin Street $5,443,948 a mile. HCP 2, 1 Reconstruction

Highway Safety and Spot 023715.00 Improvements Beginning at Dartmouth Street and extending 2018 Portland Route 25 northwest 1.85 miles to Rowe Avenue. PACTS $195,000 Intersection Improvements - PE Sponsored. HCP 2 Only

023717.00 Highway Construction/ Rehabilitation Beginning at Morrills corner and extending north 0.08 2018 Portland Forest Avenue $210,000 of mile. HCP 1 Reconstruction - PE Only

Marine 023815.00 Portland Marine Buildings IMT Port Security Port Security Grant at International Marine Terminal. $100,000 2019/20 Rehabilitation

44

0123456789 ID/Year Municipality Scope Name Description Funding

Freight 023817.00 Freight Monitoring Systems & Purchase of two yard trucks at the International Portland Yard Trucks $160,000 2019/20 Equipment Marine Terminal.

Capital Equipment Purchase

Freight 023819.00 Freight Monitoring Systems & Purchase of two yard trucks at the International Portland Yard Trucks $160,000 2018 Equipment Marine Terminal.

Capital Equipment Purchase

WR 34777 Bridge and Structural Casco Bay Bridge (#5900) maintenance to ensure 2018 Portland Maintenance Route 77 marine traffic mobility. Located at the Portland - $700,000 South Portland city line. HCP 2

WR 35410 Bridge and Structural Mechanical work on various components to Casco 2018 Portland Maintenance Route 77 Bay Bridge (#5900) over Fore River. Located at the $180,000 Portland - South Portland city line. HCP 2

WR 35460 Bridge and Structural Repair concrete sidewalk in front of north and south towers of Casco Bay Bridge (#5900) over Fore River 2018 Portland Maintenance Route 77 $35,000 with silane, epoxy and sand topcoat. Located at the HCP 2 Portland - South Portland city line.

WR 35469 Bridge and Structural LED lighting upgrade to control room, north tower and kitchen, and adding a MCC overload trip light to 2018 Portland Maintenance Route 77 $25,000 panel on Casco Bay Bridge (#5900) over Fore River. HCP 2 Located at the Portland - South Portland city line.

WR 35578 Bridge and Structural Grout pumping of four approach slabs to two bridges Fore River 2018 Portland Maintenance (#6422 and #6423) located on Fore River Parkway in $30,000 Parkway Portland. HCP 2

022420.00 Portland, Highway Paving Beginning at the Portland city line and extending 9.70 2019/20 Scarborough, Interstate 295 miles, including northbound gaps in previous $3,975,000 South Portland Mill And Fill treatment. HCP 1

021746.00 Portland, South Casco Bay Bridge (#5900) over Fore River. Located 2018 Route 77 $590,000 Portland Bridge Protective Coating at the Portland-South Portland city line. HCP 2

021890.00 Portland, South Casco Bay Bridge (#5900) over Fore River. Located 2019/20 Route 77 $1,000,000 Portland Lighting at the Portland-South Portland city line. HCP 2

45

0123456789 ID/Year Municipality Scope Name Description Funding

023709.00 Beginning 0.08 of a mile east of Pine Tree Industrial Highway Paving Parkway on Route 25 and extending southwest 0.93 Portland, Larrabee Road, 2019/20 of a mile to the intersection of Larrabee Road, then $1,173,284 Westbrook Route 25 Mill And Fill continuing north 0.93 of a mile on Larrabee Road to HCP 2, 1 the intersection of Riverside Street.

023721.00 Highway Paving Portland, Beginning at Riverside Street and extending north 2019/20 Route 302 $707,265 Westbrook 1.17 miles to Chase Hill Drive. Mill And Fill HCP 1

WR 34786 Portland, Removing brush along Interstate 295 beginning at Custodial Maintenance Interstate 295 2018 Scarborough, the Exit 44 toll plaza in Scarborough and extending $75,000 NB/SB South Portland north 8.01 miles to the Portland-Falmouth town line. HCP 1

022962.00 Highway Safety and Spot Improvements Located at the intersection of Elmwood Road and 2019/20 Pownal Route 9 $150,000 Hallowell Road. HCP 3 Flashing Beacon

WR 34917 Replacing two culverts (#99442, #99443) in Drainage Maintenance preparation of Light Capital Paving (LCP) project, 2018 Pownal Allen Road beginning 0.40 of a mile west of the intersection of $9,000 Chadsey Road and extending westerly 0.10 of a HCP 4 mile.

Bicycle-Pedestrian 018888.00 Trail, On-Road Beginning at Route 302 and extending east 0.57 of a 2019/20 Raymond Main Street $405,000 mile to Route 121. Bicycle/Pedestrian HCP 6 Improvements

WR 34708 Drainage Maintenance Ditching beginning at the intersection of Eygpt Road 2018 Raymond Route 85 extending north 1.20 miles to the intersection of $30,000 Dryad Woods Road. HCP 4

WR 34756 Custodial Maintenance Removing trees on Route 121 beginning at the 2018 Raymond Route 121 Casco-Raymond town line and extending south 3.85 $50,000 miles to the intersection of Route 302 in Raymond. HCP 4

Bicycle-Pedestrian 018889.00 Trail, On-Road Beginning at Adams Way and extending north 0.21 2018 Scarborough Route 114 $48,000 of a mile to Hannaford Drive. Bicycle/Pedestrian HCP 2 Improvements - PE Only

021928.02 Highway Construction/ Rehabilitation Municipal Partnership Initiative Program. Beginning 2018 Scarborough Route 114 at Hannaford Drive and extending north 0.80 of a $1,640,000 mile to Maple Avenue. HCP 2 Highway Rehabilitation

46

0123456789 ID/Year Municipality Scope Name Description Funding

022086.00 Highway Paving Beginning 0.09 of a mile south of Glendale Drive and 2018 Scarborough Broadturn Road $35,689 extending southerly 1.14 miles. Light Capital Paving HCP 3

022086.00 Highway Paving Beginning 0.16 of a mile north of Milliken Road and 2018 Scarborough Payne Road $24,732 extending northerly 0.79 of a mile. Light Capital Paving HCP 3

022086.00 Highway Paving Beginning 0.26 of a mile east of Two Rod Road and 2018 Scarborough Holmes Road $26,610 extending easterly 0.85 of a mile to Payne Road. Light Capital Paving HCP 4

WR 33274 Drainage Maintenance Replacing a stone culvert (#973812) located 0.55 of Scarborough Route 22 $50,000 2018 a mile east of Saco Street.

WR 35678 Bridge and Structural Repairing the bridge rail and paved approaches on Pleasant Hill Pleasant Avenue Crossing Bridge (#3911), over the 2018 Scarborough Maintenance $43,000 Road Boston and Maine Railroad. Located 0.10 of a mile HCP 4 north of Rigby Road.

Bicycle-Pedestrian 019426.00 Beginning at Wainright Field in South Portland and Scarborough, Trail, On-Road Eastern Trail extending south 0.80 of a mile to Pleasant Hill Road $565,275 2019/20 South Portland in Scarborough . PACTS Sponsored. New Construction

Bicycle-Pedestrian 019426.10 Eastern Trail bicycle and pedestrian connection. Scarborough, Trail, Off-Road Eastern Trail Beginning at Nonesuch River and extending 0.60 of $3,100,000 2019/20 South Portland a mile to Pleasant Hill Road. Includes two bridges. New Construction

022086.00 Highway Paving Scarborough, Beginning 0.02 of a mile east of Honan Road and 2018 Mussey Road $19,723 South Portland extending northeasterly 0.63 of a mile. Light Capital Paving HCP 3

022462.00 Highway Paving Beginning at off-ramp to Scarborough Connector and Scarborough, Scarborough 2019/20 extending south 1.57 miles to Route 1. PACTS $658,164 South Portland Connector Mill And Fill Sponsored HCP 1

022466.00 Highway Paving Scarborough, 2019/20 Route 701 Beginning at Route 1 and extending north 1.71 miles. $732,982 South Portland Mill And Fill HCP 1

47

0123456789 ID/Year Municipality Scope Name Description Funding

Highway Safety and Spot 022976.00 Improvements Scarborough, Beginning 0.30 of a mile north of Route 1 and 2019/20 Route 701 $480,000 South Portland extending northerly 1.35 miles. Guard Rail Installation And HCP 1 Replacement

WR 34461 Custodial Maintenance Brush removal beginning at the intersecion of Long 2018 Sebago Route 11 Hill Road and extending north 4.25 miles to the $65,000 intersection of Hawkes Road. HCP 3

WR 35015 Drainage Maintenance Ditching Long Hill Road beginning at the intersection 2018 Sebago Long Hill Road of Route 107 extending south 2.00 miles to the $80,000 intersection of Fitch Road. HCP 4

Highway Construction/ 012783.00 Rehabilitation Beginning at the southerly intersection of the Wards Sebago, 2018 Route 114 Cove Road in Standish and extending north 2.13 $408,634 Standish Highway Rehabilitation - PE miles to the West Shore Road. HCP 3 Only

018638.00 Highway Construction/ Beginning at Pleasant Avenue and extending north Lincoln Street, Rehabilitation 1.11 miles. Billy Vachon Drive beginning at Lincoln 2019/20 South Portland Billy Vachon $1,366,200 Street and extending west 0.24 of a mile. PACTS Drive HCP 6, 3, 2 Highway Rehabilitation Sponsored.

018665.00 Highway Safety and Spot Multifaceted approach to corridor improvements to 2019/20 Improvements South Portland Route 77 address traffic, safety, and bicycle/pedestrian needs $402,050 HCP 2, 6, 4, and deficiencies on/off Route 77. PACTS Sponsored. Traffic Signals 3

022136.00 Highway Safety and Spot Improvements Located at the intersection of Broadway and Evans 2019/20 South Portland Broadway Street, and the intersection of Broadway and Lincoln $378,238 Street. PACTS Sponsored. HCP 2 Intersection Improvements

Bicycle-Pedestrian 022138.00 Multiuse path extension beginning 350 feet north of the Broadway intersection, including a 200-foot path Trail, On-Road 2019/20 South Portland Route 1 connection to Cash Street. Signal upgrades on $728,322 Bicycle/Pedestrian Route 1 at Broadway and Rumery Street to facilitate HCP 1 Improvements pedestrian movements. PACTS Sponsored.

022258.00 Ramp SP4 Bridge (#1376) over northbound ramp of 2018 South Portland Route 1 SB Interstate 295 to 1/PTR. Located off Exit 4 on $250,000 Bridge Improvements - PE Only Interstate 295 southbound. HCP 1

023599.00 I-295/ Westbrook Street Bridge (#6249) over Route 2019/20 South Portland Interstate 295 $350,000 Bridge Painting 9. Located 0.47 of a mile north of Route 701. HCP 1

48

0123456789 ID/Year Municipality Scope Name Description Funding

023601.00 I-295 NB/ Red Brook Bridge (#6285) over Red Brook. 2019/20 South Portland Interstate 295 $250,000 Bridge Culvert Rehabilitation Located 0.93 of a mile north of the Portland city line. HCP 1

023605.00 I-295 SB/ Westbrook Street Bridge (#6532) over 2019/20 South Portland Interstate 295 Route 9. Located 0.11 of a mile northeast of $350,000 Bridge Painting Interstate 295 Exit #3. HCP 1

023757.00 Highway Paving Beginning 0.04 of a mile east of the Scarborough town line and extending easterly 0.85 of a mile. 2019/20 South Portland Broadway $330,238 Broadway West: Beginning 0.09 of a mile west of Mill And Fill HCP 3, 2 Sokokis Street and extending westerly 0.22 of a mile.

020210.00 Highway Construction/ Rehabilitation Located at the intersection of Route 25, Manchester 2018 Standish Route 25 $2,170,000 Road and Saco Road. HCP 2 Roundabout Construction

021703.00 Watchic Bridge (#2914) over Page Brook. Located 2019/20 Standish Route 113 $800,000 Bridge Replacement 0.08 of a mile north of Connor Road. HCP 3

018637.00 Highway Safety and Spot "Rotary" area intersections of Harnois Street/Main Improvements Street/Cumberland Street; Main Street/Warren 2019/20 Westbrook Route 25B $1,771,000 Avenue; and Main Street/Forest Avenue. PACTS HCP 2 Intersection Improvements Sponsored.

022168.00 Highway Paving Beginning at Pierce Street and extending northwest Cumberland 2019/20 Westbrook 0.47 of a mile to Willoughby Farm Road. PACTS $163,000 Street 1 1/4" Overlay Sponsored. HCP 3

022474.00 Highway Paving Cumberland Beginning at Harnois Avenue and extending west 2019/20 Westbrook $232,642 Street 0.41 of a mile to Cottage Place. PACTS Sponsored. Mill And Fill HCP 2, 3

023797.00 Highway Safety and Spot Improvements Beginning at Mechanic Street and extending 0.28 of 2018 Westbrook Route 25 $2,311,054 a mile west. PACTS Sponsored HCP 1 Intersection Improvements

011219.20 Highway Construction/ Rehabilitation Beginning at the Westbrook town line and extending 2019/20 Windham River Road $6,550,000 north 3.07 miles. HCP 3 Highway Rehabilitation

49

0123456789 ID/Year Municipality Scope Name Description Funding

021924.00 Doles Bridge (#5061) over Colley Wright Brook. 2019/20 Windham River Road $1,700,000 Bridge Replacement Located 0.11 of a mile south of Willow Drive. HCP 3

021928.09 Highway Construction/ Rehabilitation Municipal Partnership Initiative Program. Beginning 2018 Windham Falmouth Road 0.04 of a mile north of Nash Road and extending $973,000 northerly 1.16 miles. HCP 4 Highway Rehabilitation

021928.11 Highway Construction/ Rehabilitation Municipal Partnership Initiative Program. Beginning 2018 Windham River Road at Route 302 and extending south 0.32 of a mile to $600,000 Pottersville Road. HCP 3 Reconstruction

022166.00 Bicycle-Pedestrian Beginning at Basin Road and extending east 0.36 of 2019/20 Windham Trail, On-Road Route 35 $300,000 a mile to Route 302. PACTS Sponsored. HCP 2 New Construction

023801.00 Highway Safety and Spot Improvements Installation of traffic signal at the intersection of 2019/20 Windham Route 202 $320,000 Route 202 and Falmouth Road. HCP 2 Safety Improvements

WR 34951 Custodial Maintenance Brush removal beginning at the intersection of 2018 Windham Route 302 Mineral Spring Road and extending north 1.15 miles $4,000 to the Windham-Raymond town line. HCP 1

Rail 018626.00 FTA - NNEPRA Passenger Rail Royal Junction Yarmouth Line Passenger Rail Siding. PACTS Sponsored. Intended FHWA $575,000 2019/20 Transfer. Rehabilitation

022088.00 Highway Paving Beginning at the Cumberland town line and 2018 Yarmouth Route 88 $30,380 extending north 0.86 of a mile to Pleasant Street. Light Capital Paving HCP 4

022380.00 Bayview Street/ I-295 Bridge (#5835) over Interstate 2019/20 Yarmouth Bayview Street $1,405,000 Bridge Deck Replacement 295. Located 0.09 of a mile east of Spring Street. HCP 6

022382.00 Route 1/ I-295 Bridge (#5804) over Interstate 295. 2019/20 Yarmouth Interstate 295 Located 0.04 of a mile north of Exit #15 of Interstate $3,000,000 Bridge Rehabilitation 295 northbound. HCP 3

50

0123456789 ID/Year Municipality Scope Name Description Funding

022478.00 Highway Paving Beginning at Route 88 and extending south 0.23 of a mile to Gilman Road. Beginning at Princes Point 2019/20 Yarmouth Gilman Road $1,161,840 Road and extending east 1.76 miles to Cousins 1 1/4" Overlay HCP 4 Island Road. PACTS Sponsored.

023412.00 Highway Construction/ Rehabilitation Beginning at the intersection of Route 115 and 2018 Yarmouth Route 115 Bowdoin Street and extending east 0.42 of mile to $569,000 Elm Street. PACTS Sponsored MPI. HCP 3 Highway Rehabilitation

Bicycle-Pedestrian 023825.00 Beginning 0.06 of a mile southwest of Spring Street Beth Condon and extending northerly 0.50 of a mile to the State of Yarmouth Trail, Off-Road $80,000 2018 Shared Use Path Maine Visitor Information Center building. PACTS New Construction - PE Only Sponsored.

51

0123456789 Franklin Gorham Gore

Lowelltown Twp Beattie Twp

Franklin County Merrill Strip Twp Skinner Population 30,768 Twp Land Area (sq mi) 1,697

Coburn Bridges 194 Gore Highway Corridor Priority Miles Kibby HCP 1 37 Chain of Twp Ponds Twp HCP 2 88 HCP 3 91

Jim Pond HCP 4 175 Alder Twp Seven Stream Ponds Twp Twp Total HCP 1-4 391

Tim Eustis Pond Stetsontown Twp Twp Wyman Twp Coplin Plt Lang Twp Davis Carrabassett Twp Valley

Redington Dallas Twp Rangeley Plt Mount Abram Kingfield Twp

Sandy Madrid Twp Salem Twp Plt Plt Freeman Twp Franklin

Phillips Township E

Strong Township D Township New Vineyard 6 North Avon of Weld Industry

Weld Temple Farmington

New Sharon Carthage Wilton

Chesterville

Jay Franklin ID/Year Municipality Scope Name Description Funding

023394.00 Alder Stream Highway Paving Twp, Chain of Beginning at the Eustis town line and extending north 2018 Route 27 $1,429,634 Ponds Twp, Jim Highway Cyclical Pavement 10.59 miles. HCP 3 Pond Twp Resurfacing

Aviation Safety and infrastructure improvements that may 018689.03 include permit, design and construction of an 8 unit Carrabassett Sugarloaf Airport Buildings T-Hangar and Taxilane; crack sealing/crack repair $918,760 2019/20 Valley Regional Airport and pavement markings at the Sugarloaf Regional New Construction Airport (B21).

WR 34843 Operational and Safety Replacing guard rail beginning at the junction of Carrabassett 2018 Maintenance Route 27 Carriage Road extending north 2.73 miles to $168,000 Valley Redington Pond Road. HCP 2

WR 35293 Bridge and Structural Replacing stub post, and riprap the wing wall on Carrabassett Redington Stream Bridge (#3731) over Redington 2018 Maintenance Route 27 $10,000 Valley Stream. Located 0.05 of a mile south of Redington HCP 2 Pond Road.

WR 35717 Operational and Safety Repairing guard rail on Redington Stream Bridge Carrabassett 2018 Maintenance Route 27 (#3731) over Redington Stream. Located 0.05 of a $17,000 Valley mile south of Redington Pond Road. HCP 2

WR 34147 Drainage Maintenance Repairing pipe between catch basins on Route 142 2018 Carthage Route 142 in Carthage beginning at Skidgell Drive extending $41,000 north 0.40 of a mile to Judkins Road. HCP 4

022102.00 Highway Paving Beginning at Route 142 and extending north 3.49 2018 Carthage, Weld West Side Road $121,720 miles to the Webb Beach Road. Light Capital Paving HCP 4

021715.00 Dead River Bridge (#3135) over North Branch Dead Chain of Ponds 2018 Route 27 River. Located 0.03 of a mile north of Alder Stream $650,000 Twp Bridge Rehabilitation Twp. HCP 3

021688.00 Dutch Gap Bridge (#3951) over Little Norridgewock 2018 Chesterville Dutch Gap Road $1,700,000 Bridge Culvert Replacement Stream. Located 1.19 miles north of Zions Hill Road. HCP 4

022296.00 Farmington Falls Bridge (#2273) over the Sandy Chesterville, 2018 Route 41 River. Located on the Chesterville-Farmington Falls $300,000 Farmington Bridge Improvements - PE Only town line. HCP 3

52

0123456789 ID/Year Municipality Scope Name Description Funding

021773.00 Highway Safety and Spot Improvements Large culvert (#92135) located 0.76 of a mile east of 2018 Coplin Plt Route 16 $135,940 Lang Twp. town line. HCP 3 Crew Operations

WR 33918 Drainage Maintenance Placing concrete extensions to a concrete box culvert 2018 Coplin Plt Route 16 $20,000 on Route 16 in Coplin Plt. HCP 3

022102.00 Coplin Plt, Highway Paving Beginning 0.97 mile southwest of Coplin Plt. and 2018 Eustis, Lang Route 16 $257,043 extending northeasterly 7.37 miles. Twp Light Capital Paving HCP 3

Highway Construction/ 023563.00 Coplin Plt, Rehabilitation Beginning at Route 27 and extending south 7.37 2018 Eustis, Lang Route 16 $1,000,000 miles. Twp Highway Rehabilitation - PE HCP 3 Only

WR 35423 Operational and Safety Repairing guard rail 0.10 of a mile east of Redington 2018 Dallas Plt Maintenance Route 16 Road in Dallas Plt. $9,000

HCP 3

022488.00 Highway Construction/ Dallas Plt, Lang Rehabilitation Beginning at Redington Road and extending 2019/20 Route 16 $1,870,000 Twp northeast 6.58 miles. HCP 3 PMRAP DOT Pugmill

021936.02 Highway Paving Dallas Plt, Beginning at Route 4 and extending northerly 4.63 2018 Route 16 $1,150,000 Rangeley miles. 1 1/4" Overlay HCP 3

022102.00 Highway Paving Dallas Plt, Beginning at Route 4 and extending east 2.46 miles 2018 Dallas Hill Road $85,797 Rangeley to Saddleback Mountain Road. Light Capital Paving HCP 4

021690.00 Williams #1 Bridge (#2980) over Branch of Williams 2019/20 Farmington Route 156 Brook. Located 0.19 of a mile southeast of Wilton $800,000 Bridge Culvert Replacement town line. HCP 3

021880.00 Gower Farm Bridge (#2324) over Beales Brook. 2018 Farmington Route 2 $820,000 Bridge Culvert Replacement Located 0.14 of a mile west of Dump Road. HCP 1

53

0123456789 ID/Year Municipality Scope Name Description Funding

022236.00 Hamlin Bridge (#3286) over Wilson Stream. Located 2019/20 Farmington Route 133 $1,750,000 Bridge Replacement 0.16 of a mile south of Wilton Road. HCP 3

WR 34327 Drainage Maintenance Ditching on Route 43 in Farmington 0.11 of a mile 2018 Farmington Route 43 south of Woodfield Drive and extending east 3.26 $36,000 miles to the Farmington-Industry town line. HCP 4

WR 32876 Department Building and Lot Farmington, 2018 Maintenance Route 137 Paving the maintenance lot. $22,000 Mercer HCP 4

WR 34321 Ditching along Route 142 in Freeman Twp. beginning Freeman Twp, Drainage Maintenance 2018 Route 142 at the junction of Route 145 and extending east 3.32 $83,000 Kingfield miles to the junction of Curve Street in Kingfield. HCP 4

WR 34322 Freeman Twp, Drainage Maintenance Ditching beginning at the junction of West Freeman 2018 Kingfield, Route 145 Road and extending south 0.93 of a mile to the $82,000 Phillips, Strong junction of Route 142. HCP 4

Repairing bridge rail on Lisherness Bridge (#5189) WR 35426 Bridge and Structural and West Freeman Bridge (#3353) over Bean Brook. Freeman Twp, Lisherness Bridge (#5189) located 0.13 of a mile Maintenance Freeman Road $10,000 2018 Strong south of the Freeman Twp. town line. West Freeman Bridge (#3353) located 0.01 of a mile south of Huff Road.

021695.00 Sawyer Bridge (#5047) over Falls Brook. Located 2018 Industry Shaw Hill Road $800,000 Bridge Replacement 0.04 of a mile south of Route 148. HCP 6

WR 34061 Drainage Maintenance Replacing culverts on Route 43 in Farmington 2018 Industry Route 43 beginning at the Savage Road extending 3.4 miles $33,000 east to the Tracy Road. HCP 4

WR 34060 Drainage Maintenance Ditching on Route 43 beginning at the Farmington- 2018 Industry, Starks Route 43 Industry town line and extending to the junction of $74,000 Route 134 in Starks. HCP 4

021733.00 Seven Mile Bridge (#3801) over Seven Mile Stream. 2019/20 Jay Route 140 Located 0.22 of a mile northeast of the Davenport Hill $1,500,000 Bridge Replacement Road. HCP 3

54

0123456789 ID/Year Municipality Scope Name Description Funding

022428.00 Highway Paving Beginning 0.24 of a mile north of Hyde Road and 2019/20 Jay Route 4 $807,921 extending northwesterly 1.89 miles. Mill And Fill HCP 1

022430.00 Highway Paving Beginning 0.56 of a mile north of Old Jay Hill Road 2019/20 Jay Route 4 $1,055,982 and extending northerly 3.81 miles. Mill And Fill HCP 1

022887.00 Highway Safety and Spot Improvements Located at the intersection of Route 133 and Route 2019/20 Jay Route 133 $215,000 156. HCP 3 Intersection Improvements

023320.00 Highway Paving Beginning 0.09 of a mile north of Osgood Road and 2018 Jay Route 133 $677,694 Highway Cyclical Pavement extending northerly 5.02 miles. HCP 3 Resurfacing

WR 33988 Route 156, Route 2018 Jay, Livermore Drainage Maintenance Repairing drainage structures in Livermore Falls, 4, Route 17, $40,000 Falls, Wilton Wilton and Jay. HCP 1, 2, Main Street 4

WR 33986 Drainage Maintenance Ditching on Route 133 from the intersection of Route 2018 Jay, Wilton Route 133 $9,000 156 extending north 1.63 miles to the Melcher Road. HCP 3

WR 34470 Cleaning under guard rails beginning on Route 133 Drainage Maintenance Route 2, Route 2018 Jay, Wilton in Jay and extending north to Farmington. Continuing $22,000 133 on Route 2 in Wilton. HCP 1, 3

Highway Construction/ 018245.00 Rehabilitation Beginning at the southerly intersection of High Street 2018 Kingfield Route 27 $400,000 and extending northerly 2.33 miles. Highway Improvements - PE HCP 2 Only

Bicycle-Pedestrian 018882.00 Beginning at the existing sidewalk on Depot Street Trail, On-Road 2019/20 Kingfield Route 142 and extending 0.65 of a mile to the Kingfield $553,000 Bicycle/Pedestrian Elementary School. HCP 4 Improvements

023048.00 Centennial Bridge (#5852) over the Carrabassett 2019/20 Kingfield Route 16 $400,000 Bridge Wearing Surface River. Located 0.05 of a mile north of Main Street. Replacement HCP 3

55

0123456789 ID/Year Municipality Scope Name Description Funding

022615.00 Weymouth Bridge (#2934) over Sandy River. 2019/20 Madrid Twp Route 4 $2,600,000 Bridge Replacement Located 1.75 miles east of the Township E town line. HCP 2

018247.00 Highway Construction/ Madrid Twp, Rehabilitation Beginning at Toothaker Pond Road in Phillips and 2019/20 Route 4 $10,564,500 Phillips extending northwest 4.58 miles. HCP 2 Reconstruction

019178.10

2018 New Sharon Route 2 Located 1.57 miles west of Route 134. $800,000 Bridge Culvert Replacement HCP 1

022934.00 Highway Safety and Spot Improvements Large culvert (#47113) located 0.55 of a mile 2019/20 New Sharon Route 27 $146,000 northwest of the York Hill Road. HCP 2 Large Culvert Rehabilitation

023633.00 New Muddy Brook Bridge (#5723) over Muddy 2019/20 New Sharon Bridge Wearing Surface Route 27 Brook. Located 0.20 of a mile northeast of Weeks $200,000 Replacement Mills Road. HCP 1

Bicycle-Pedestrian 018885.00 Beginning at River Road and extending west 0.52 of Trail, On-Road 2019/20 Phillips Route 149 a mile. Continuing on Route 142 and extending 0.36 $477,500 Bicycle/Pedestrian of a mile. HCP 4, 2 Improvements

022348.00 Dill Bridge (#2228) over South Branch Sandy River. 2019/20 Phillips Route 4 $250,000 Bridge Substructure Located 0.10 of a mile northwest of Number 6 Road. Rehabilitation HCP 2

022616.00 Wing Bridge (#2955) over Sandy River. Located 0.52 2019/20 Phillips Route 4 $2,900,000 Bridge Replacement of a mile east of the Madrid Twp. town line. HCP 2

023623.00 Lower Village Bridge (#5063) over Sandy River. 2018 Phillips Route 149 $250,000 Bridge Improvements - PE Only Located 0.02 of a mile south of Amble Street. HCP 4

023641.00 Ross Bridge (#5064) over Sandy River . Located 2018 Phillips Route 142 $250,000 Bridge Improvements - PE Only 0.21 of a mile south of Bridge Street. HCP 4

56

0123456789 ID/Year Municipality Scope Name Description Funding

Aviation 018705.02 Safety and infrastructure improvements that may Steven A. Bean Rangeley Runway/Taxiway include environmental mitigation at the Steven A. $360,500 2019/20 Municipal Airport Bean Municipal Airport (8B0). New Construction

Aviation 018705.03 Safety and infrastructure improvements that may Steven A. Bean Rangeley Planning And Research include an environmental assessment at the Steven $154,500 2018 Municipal Airport A. Bean Municipal Airport (8B0). Planning Studies

Aviation 018705.04 Safety and infrastructure improvements that may Steven A. Bean include design and permitting for Runway 14-32 Rangeley Runway/Taxiway $515,000 2018 Municipal Airport extension at the Steven A. Bean Municipal Airport New Construction (8B0).

Aviation 018705.05 Safety and infrastructure improvements that may Steven A. Bean Rangeley Runway/Taxiway include construction of Runway 14-32 extension at $9,929,200 2019/20 Municipal Airport the Steven A. Bean Municipal Airport (8B0). New Construction

Aviation 018705.06 Safety and infrastructure improvements that may Steven A. Bean Rangeley Runway/Taxiway include the design and reconstruction of Runway 14- $3,605,000 2019/20 Municipal Airport 32 at the Steven A. Bean Municipal Airport (8B0). Reconstruction

022102.00 Highway Paving Beginning at Route 4 and extending north 1.49 miles 2018 Rangeley Loon Lake Road $51,967 to Frenchies Way. Light Capital Paving HCP 4

Bicycle-Pedestrian 022220.00 Beginning on the west side of Main Street at the Trail, On-Road Scenic Overlook, and extending northerly 0.30 of a 2019/20 Rangeley Route 4 $525,785 mile to the existing sidewalk that ends just north of Bicycle/Pedestrian HCP 2 Grandview Avenue. Improvements

WR 35034 Operational and Safety Installing guard rail on Route 16 in Rangeley 2018 Rangeley Maintenance Route 16 between Indian Rock Road and Oquossoc Angling $12,000 Road. HCP 4

WR 36270 Drainage Maintenance 2018 Rangeley Loon Lake Road Repairing basins in Rangeley on Loon Lake Road $30,000

HCP 4

WR 36272 Drainage Maintenance Ditching and installing underdrain on Loon Lake 2018 Rangeley Loon Lake Road $10,000 Road. HCP 4

57

0123456789 ID/Year Municipality Scope Name Description Funding

WR 34314 Bridge and Structural Maintaining channel, and placing riprap on the wing South Shore wall on South Bog Bridge (#5772) over South Bog 2018 Rangeley Plt Maintenance $15,000 Drive Stream. Located 0.52 of a mile southwest of State HCP 4 Park Road.

022102.00 Highway Paving Rangeley Plt, South Shore Beginning at Route 17 and extending east 7.56 miles 2018 $263,669 Sandy River Plt Drive to Route 4. Light Capital Paving HCP 4

022102.00 Rangeley, Highway Paving Beginning 0.71 of a mile south of Rangeley Plt. town 2018 Rangeley Plt, Route 17 $372,834 line and extending northerly 10.69 miles. Township D Light Capital Paving HCP 3

020537.00 Highway Safety and Spot Improvements Restore Aquatic Organism Passage to a recently 2019/20 Sandy River Plt Route 4 installed culvert (#46859) located 1.25 miles $123,000 northwest of Township E town line. HCP 2 Large Culvert Rehabilitation

022358.00 Sandy River Bridge (#5161) over Sandy River. 2019/20 Strong Route 145 $500,000 Bridge Painting Located 0.05 of a mile north of Route 4. HCP 4

018953.00 Day Mountain Blodgett Bridge (#3974) over Temple Stream. 2018 Temple $400,000 Bridge Rehabilitation Road Located 0.06 of a mile north of Intervale Road. HCP 6

022102.00 Highway Paving Beginning at Web Beach Road and extending north 2018 Weld West Side Road $138,112 3.96 miles to Route 142. Light Capital Paving HCP 4

021898.00 Wilson Stream Bridge (#5936) over Wilson Stream. 2018 Wilton Route 2 $900,000 Bridge Deck Replacement Located 0.25 of a mile east of Cemetery Road. HCP 1

022378.00 Wilson Stream Bridge (#5936) over Wilson Stream. 2019/20 Wilton Route 2 $250,000 Bridge Painting Located 0.25 of a mile east of Cemetery Road. HCP 1

Highway Construction/ 023799.00 Rehabilitation Large culvert (#46542) located 0.13 of a mile east of 2018 Wilton Route 2 $55,000 Gammon Hill Road. Large Culvert Replacement - HCP 1 PE Only

58

0123456789 ID/Year Municipality Scope Name Description Funding

WR 35565 Drainage Maintenance Repairing large culvert (#46562) located 0.27 of a 2018 Wilton Main Street $6,000 mile north of McLaughlin Road. HCP 4

WR 35733 Operational and Safety 2018 Wilton Maintenance Depot Street Repairing guard rail in Wilton on Depot Street. $25,000

HCP 4

59

0123456789 Hancock

Hancock County Oqiton Twp Population 54,420 T3 ND Land Area (sq mi) 1,587 Bridges 122 Highway Corridor Priority Miles T41 MD HCP 1 83 T40 MD T39 MD HCP 2 45 HCP 3 161 T35 MD HCP 4 243 T34 MD Great Pond T32 MD Total HCP 1-4 532

T28 MD Aurora Amherst

T22 MD Osborn Mariaville

Otis T16 MD Dedham Eastbrook Waltham

Bucksport T9 T10 SD Fletchers Franklin Landing Twp SD Ellsworth Orland Hancock T7 SD

Verona Sullivan Island

Surry Hancock Lamoine Penobscot Trenton Blue Hill Gouldsboro

Castine Winter Bar Harbor Harbor Brooksville Blue Hill Sedgwick Mount Southw est Desert Harbor Tremont Deer Brooklin Isle Hancock

Stoningto n Swans Island Hancock ID/Year Municipality Scope Name Description Funding

021870.00 Half Mile Brook Bridge (#6246) over Half Mile Pond. 2019/20 Amherst Route 9 $800,000 Bridge Culvert Replacement Located 0.05 of a mile east of Haynes Brook Road. HCP 1

WR 34575 Ditching and culvert replacement beginning at the Amherst, Drainage Maintenance 2018 Route 181 intersection of Route 180 in Otis extending north $687,000 Mariaville, Otis 12.48 miles to the intersection of Route 9 in Amherst. HCP 4

018776.00 Highway Safety and Spot Improvements Beginning at Eden Street and extending east 0.48 of 2019/20 Bar Harbor Route 3 $130,000 a mile. HCP 1, 3 Drainage Improvements

022652.00 Highway Safety and Spot Closed system drainage improvements beginning Improvements 0.04 of a mile north of Cromwell Harbor Road and 2019/20 Bar Harbor Route 3 $250,000 extending northerly 0.51 of a mile to Mount Desert HCP 3 Drainage Improvements Street.

WR 34379 Ditching and replacing culverts beginning at the Bar Harbor, Drainage Maintenance Route 102, Seal intersection of Route 3 extending to the Seal Cove 2018 Southwest $129,000 Cove Road Road in Southwest Harbor and continuing on the Harbor HCP 3, 4 Seal Cove Road to the Long Pond Road.

017712.00 Blue Hill Falls Bridge (#5038) over the tidal basin. 2019/20 Blue Hill Route 175 $7,100,000 Bridge Improvements Located 0.66 of a mile south of Route 172. HCP 4

018728.00 Village Bridge (#2893) over Mill Stream. Located 2019/20 Blue Hill Route 15 $1,000,000 Bridge Superstructure 0.04 of a mile northeast of Water Street. Replacement HCP 3

018777.00 Highway Construction/ Rehabilitation Beginning at the Sedgwick town line and extending 2019/20 Blue Hill Route 15 $1,550,000 north 2.09 miles. HCP 3 Reconstruction

021845.00 Highway Safety and Spot Improvements Beginning 0.06 of a mile south of Mill Street and 2019/20 Blue Hill Route 15 $185,000 extending northerly 0.06 of a mile. HCP 3 Drainage Improvements

WR 34611 Drainage Maintenance Removing excess shoulder material on Route 172 in 2018 Blue Hill South Street Blue Hill from the intersection of Route 15 to the Blue $41,000 Hill - Sedgwick town line. HCP 4

60

0123456789 ID/Year Municipality Scope Name Description Funding

WR 35326 Bridge and Structural Concrete rehab on wing wall and re-point granite abutments on Peters Brook Bridge (#3846) over 2018 Blue Hill Maintenance Route 176 $74,000 Peters Brook. Located 0.68 of a mile east of HCP 4 Ellsworth Road.

022112.00 Highway Paving Blue Hill, Beginning at Route 3 and extending south 19.47 2018 Route 176 $689,238 Orland, Surry miles to Ellsworth Road. Light Capital Paving HCP 4, 3

Highway Construction/ 023531.00 Rehabilitation Large culvert (#46688) located 0.05 of a mile south 2018 Brooklin Route 175 $70,000 of Flye Point Road. Large Culvert Improvements - HCP 4 PE Only

021677.00 Brooklin, Bridge (#3216) over Benjamin River. 2018 Route 175 $1,500,000 Sedgwick Bridge Replacement Located at the Brooklin-Sedgwick town line. HCP 4

WR 32468 Brooksville, Drainage Maintenance Drainage maintenance beginning at the Mines Road 2018 Penobscot, Route 176 $209,000 and extending to the intersection of Route 175. Sedgwick HCP 4

018812.00 Highway Safety and Spot Improvements Large culvert (#264890) located 0.37 of a mile 2018 Bucksport Route 46 $425,000 northeast of Heritage Park Road. HCP 3 Large Culvert Replacement

022414.00 Highway Paving Beginning 0.04 of a mile northwest of First Street and 2019/20 Bucksport Route 15 $759,620 extending northwesterly 0.81 of a mile. Mill And Fill HCP 2

022412.00 Highway Paving Bucksport, Beginning 0.01 of a mile north of the Verona Island 2019/20 Route 1 $2,437,843 Orland town line and extending easterly 4.15 miles. Mill And Fill HCP 1

023288.00 Highway Paving Bucksport, Beginning 0.51 of a mile north of Franklin Street and 2018 Route 15 $1,965,103 Orrington Ultra Thin Bonded Wearing extending northerly 9.36 miles. HCP 2 Surface

023356.00 Highway Paving Beginning at Route 166 and extending north 4.14 2019 Castine Route 166A $151,441 miles. Light Capital Paving HCP 4

61

0123456789 ID/Year Municipality Scope Name Description Funding

023356.00 Highway Paving Castine, Beginning at 166A and extending north 10.44 miles 2019 Route 199 $381,895 Penobscot to Route 15. Light Capital Paving HCP 4

022356.00 Deer Isle, Mill Hill Bridge (#3063) over Mill Pond Outlet. 2019/20 Route 15 $2,250,000 Stonington Bridge Replacement Located on the Stonington- Deer Isle town line. HCP 3

021718.00 Branch Pond Bridge (#3139) over Branch Pond Christian Ridge 2018 Ellsworth Stream. Located 0.34 of a mile north of Red Bridge $100,000 Road Bridge Culvert Rehabilitation Road. HCP 4

Marine 023470.00 Ellsworth Harbor Ellsworth Marine Buildings Replace fuel system at town dock. Facility upgrades. $150,000 2019/20 Park Rehabilitation

Highway Safety and Spot 021785.00 Improvements Cross culvert (#110136) located 0.19 of a mile north 2018 Franklin Route 182 $120,000 of Alder Brook Hill Road. Large Culvert Improvements - HCP 3 PE Only

022112.00 Highway Paving Franklin, Beginning at Route 1 and extending north 5.93 miles 2018 Route 200 $209,922 Sullivan to route 182. Light Capital Paving HCP 4

Marine 022202.00 Frenchboro Piers, Floats And Fenders Lunt Harbor Construction of new Frenchboro dolphin. $425,000 2019/20 Reconstruction

022112.00 Highway Paving Hancock, Beginning at Route 204 and extending north 2.91 2018 Mud Creek Road $103,014 Lamoine miles to Route 1. Light Capital Paving HCP 4

023595.00 Highway Paving Beginning 0.18 of a mile east of Cemetery Road and Hancock, 2019/20 Route 1 extending easterly 1.31 miles, including the Hancock- $581,560 Sullivan Mill And Fill Sullivan Bridge (#2973). HCP 2

Highway Safety and Spot 018359.00 Improvements To determine solution to erosion near Stanley Brook 2018 Mount Desert Route 3 $251,601 from underdrain outfall from Route 3. Highway Improvements - PE HCP 3 Only

62

0123456789 ID/Year Municipality Scope Name Description Funding

021928.10 Highway Construction/ Rehabilitation Municipal Partnership Initiative Program. Beginning 2018 Mount Desert Route 3 1.10 miles south of Route 233 and extending $1,000,000 southerly 1.10 miles. HCP 3 Full Depth Reclaim

023515.00 Babsons Bridge (#5244) over Meadow Brook. 2019/20 Mount Desert Route 3 $1,500,000 Bridge Replacement Located 0.09 of a mile east of Route 102. HCP 3

WR 32896 Bridge and Structural Replacing the concrete wearing surface on the Harbor Brook Bridge (#5377) over Little Harbor 2018 Mount Desert Maintenance Route 3 $42,000 Brook. Located 0.56 of a mile east of Wheelwright HCP 3 Way.

WR 34729 Remove shoulder material and perform drainage Penobscot, Drainage Maintenance 2018 Route 175 maintenance on Route 175 from the intersection of $205,000 Sedgwick Route 176 to the intersection of Route 166. HCP 4

Highway Safety and Spot 021825.00 Improvements Large culvert (#47198) located 0.33 of a mile south 2018 Sedgwick Route 172 $60,000 of Hales Hill Road. Large Culvert Improvements - HCP 4 PE Only

022112.00 Highway Paving Beginning at Sedgwick Road and extending 2018 Sedgwick Ridge Road $145,140 northwest 4.10 miles to Mines Road. Light Capital Paving HCP 4

022112.00 Highway Paving Beginning at Route 175 and extending north 3.45 2018 Sedgwick Route 172 $122,130 miles. Light Capital Paving HCP 4

Highway Safety and Spot 023753.00 Improvements Large culvert (#986663) located 0.01 of a mile 2018 Sedgwick Route 176 $50,000 southeast of Rocks Lane. Large Culvert Improvements - HCP 4 PE Only

WR 35104 Drainage Maintenance Ledge removal in the clear zone in various locations 2018 Sedgwick Route 176 $35,000 along Route 176 in Sedgwick HCP 4

022204.00 Bicycle-Pedestrian Located on the west side of Main Street from Apple Southwest 2019/20 Urban Highways Main Street Lane and extending 0.20 of a mile to the entrance to $842,000 Harbor "The Village at Ocean's End." HCP 3 Sidewalk Construction

63

0123456789 ID/Year Municipality Scope Name Description Funding

WR 32576 Southwest Drainage Maintenance Ditching and replacing pipes on Route 102A between 2018 Route 102A $26,000 Harbor Haddock Road and Cable Crossing Road. HCP 4

021702.00 Southwest Marsh Bridge (#2511) over Marsh Brook. Located on 2018 Route 102 $1,500,000 Harbor, Tremont Bridge Replacement the Southwest Harbor-Tremont town line. HCP 3

WR 34377 Ditching and replacing culverts beginning at the Southwest Drainage Maintenance intersection of Main Street and Seawall Road in 2018 Route 102A $246,000 Harbor, Tremont Southwest Harbor and extending to the intesection of HCP 3, 4 the Tremont Road and Bass Harbor Road.

WR 34745 Ditching and replacing culverts beginning at Apple Southwest Drainage Maintenance Route 102, Lane intersection in Southwest Harbor and 2018 $51,000 Harbor, Tremont Tremont Road continuing 0.33 miles past the intersection of Route HCP 3 102A in Tremont.

022630.00 Oceanville Bridge (#3696) over Oceanville 2018 Stonington Oceanville Road Thoroughfare. Located 0.38 of a mile west of Hatchs $1,000,000 Bridge Replacement Cove Road. HCP 6

MaineDOT Multimodal System 023478.00 Operations Swans Island Crew Quarters, 1-2 bedroom Swans Island Crew Quarters $250,000 2019 expansion. New Construction

Marine 023480.00 Swans Island Piers, Floats And Fenders Swans Island Build two dolphins, walkways and wave fence. $1,000,000 2019/20 New Construction

019305.00 Clark Bridge (#3663) over Marshall Brook. Located 2018 Tremont Trenton Road $1,655,000 Bridge Replacement 0.14 of a mile northwest of Flat Iron Road. HCP 4

019305.10 Bicycle-Pedestrian New sidewalk: beginning at Flat Iron Road and 2018 Tremont Trail, On-Road Tremont Road extending west 0.20 of a mile to the south entrance $152,713 to Tremont Consolidated School. HCP 4 New Construction

Marine 023018.00 Dock Replace stingers, pilings, decking, install bracing and Tremont Boat Ramps $300,000 2019/20 Rehabilitation shore up municipal pier. New Construction

64

0123456789 ID/Year Municipality Scope Name Description Funding

Highway Safety and Spot 023020.00 Improvements 2018 Tremont Shore Road Located 0.12 of a mile south of McMullen Avenue. $75,000 Slope Stabilization/Protection - HCP 3 PE Only

Marine 023476.00 Tremont Piers, Floats And Fenders Bass Harbor Install south side dolphin, walkway and wave fence. $500,000 2019/20 New Construction

WR 35216 Bridge and Structural Replacing asphalt wearing surface with concrete on 2018 Tremont Maintenance Tremont Road Cousins Creek Bridge (#3664) over Cousins Creek. $75,000 Located 0.20 of a mile east of Bernard Road. HCP 4

Aviation 018710.02 Hancock County Safety and infrastructure improvements that may Trenton Runway/Taxiway - Bar Harbor include airfield pavement markings at the Hancock $257,500 2019/20 Airport County - Bar Harbor Airport (BHB). Crack Sealing

Aviation Safety and infrastructure improvements that may 018710.05 Hancock County Airport Buildings include easement/land acquisition for Runways 4, 22 Trenton - Bar Harbor $360,500 2019/20 and 17 at the Hancock County - Bar Harbor Airport Airport Sale Or Purchase Of Lot Or (BHB). Building

Aviation Safety and infrastructure improvements that may 018710.07 Hancock County include an environmental assessment for easement Trenton Planning And Research - Bar Harbor acquisition and obstruction removal (Runways 4, 22 $309,000 2019/20 Airport and 17) at the Hancock County - Bar Harbor Airport Planning Studies (BHB).

Aviation Safety and infrastructure improvements that may 018710.08 Hancock County include replacement of the high intensity runway Trenton Navigation Aids/Lights - Bar Harbor lights and medium intensity runway lights to include $1,545,000 2018 Airport conduit, light bases and new cable/counterpoise at Lighting the Hancock County - Bar Harbor Airport (BHB).

022364.00 Mount Desert Bridge (#2591) over Mount Desert 2019/20 Trenton Route 3 Narrows. Located 0.21 of a mile south of Haynes $400,000 Bridge Painting Point Road. HCP 1

023022.00 Highway Safety and Spot Improvements Large culvert (#46200) located 0.36 of a mile south 2019/20 Trenton Route 230 $720,000 of the Ellsworth town line. HCP 4 Large Culvert Replacement

Highway Safety and Spot 023024.00 Improvements Located 0.49 of a mile north of the Bar Harbor town 2018 Trenton Route 3 $75,000 line. Slope Stabilization/Protection - HCP 1 PE Only

65

0123456789 ID/Year Municipality Scope Name Description Funding

023316.00 Highway Paving Beginning 0.20 of a mile west of West Side Drive 2018 Verona Island Route 1 $356,504 Ultra Thin Bonded Wearing and extending northeasterly 0.95 of a mile. HCP 1 Surface

023356.00 Highway Paving East/West Side Beginning at the south intersection of Route 3 and 2019 Verona Island $316,051 Drive extending southerly 8.64 miles. Light Capital Paving HCP 4

66

0123456789 Kennebec Kennebec

Clinton

Unity Twp

Benton Rome Waterville Oakland Vienna

Winslow Albion Belgrade

Mount Vernon Fayette Sidney Vassalboro

China

Readfield

Wayne

Augusta

Manchester Winthrop Windsor Hallowell

Farmingdale Chelsea

Monmouth Randolph West Kennebec County Gardiner Population 122,151 Land Area (sq mi) 868 Gardiner Pittston Bridges 253 Litchfield Highway Corridor Priority Miles HCP 1 167 HCP 2 120 HCP 3 200 HCP 4 231

Total HCP 1-4 718 Kennebec ID/Year Municipality Scope Name Description Funding

022092.00 Highway Paving South Freedom Beginning at the Freedom town line and extending 2018 Albion $145,907 Road northwest 4.15 miles to Route 9. Light Capital Paving HCP 4

022092.00 Highway Paving Albion Road, Beginning at Garland Road and extending southeast 2018 Albion, Benton $247,865 Benton Road 7.05 miles to Route 9. Light Capital Paving HCP 4

022092.00 Highway Paving Albion Road, Beginning at Garland Road and extending east 7.53 2018 Albion, Winslow $264,741 Winslow Road miles to Route 9. Light Capital Paving HCP 4

Aviation 018716.01 Augusta State Augusta Airport Buildings Perimeter Fence at the Augusta State Airport (AUG). $200,000 2018 Airport New Construction

Aviation 018716.19 Infrastructure Improvements to include cold storage Augusta State Augusta Airport Buildings building, terminal walkway, and terminal windows at $200,000 2019/20 Airport the Augusta State Airport (AUG). New Construction

019402.00 Bicycle-Pedestrian Beginning at Townsend Road and extending north 2019/20 Augusta Trail, On-Road Route 27 0.62 of a mile. $767,273

HCP 2 New Construction

Bicycle-Pedestrian 019403.00 Bicycle and Pedestrian Safety Improvements: Located between neighborhoods connecting the Trail, Off-Road School 2018 Augusta Farrington Elementary School to Cony Middle and $9,000 Trail/Sidewalk Bicycle/Pedestrian High School Complex, including a sidewalk on Pierce HCP 2, 6 Improvements - PE Only Drive. Approximately 0.50 of a mile.

Aviation 020655.01 Safety and infrastructure improvements that may Augusta State Augusta Planning And Research include a Master Plan Update at the State owned $154,500 2019/20 Airport Augusta State Airport (AUG). Planning Studies

Aviation 020655.02 Safety and infrastructure improvements that may Augusta State Augusta Runway/Taxiway include snow removal equipment acquisition at the $284,165 2019/20 Airport State owned Augusta State Airport (AUG). Capital Equipment Purchase

021672.00 Western Avenue/ I-95 Bridge (#5808) over Interstate 2018 Augusta Route 202 95. Located 0.27 of a mile south of Old Winthrop $250,000 Bridge Improvements - PE Only Road. HCP 1

67

0123456789 ID/Year Municipality Scope Name Description Funding

021872.00 Rines Hill Bridge (#3528) over the Old Maine Central 2018 Augusta Rines Hill Bridge Rail Road. Located 0.01 of a mile north of Gage $250,000 Bridge Improvements - PE Only Street. HCP 4

021980.00 Highway Paving Beginning 0.15 of a mile east of Church Hill Road 2018 Augusta Route 3 $779,096 Ultra Thin Bonded Wearing and extending westerly 3.29 miles. HCP 1 Surface

022272.00 Augusta Interchange Bridge (#5809) over Route 11. 2019/20 Augusta Interstate 95 Located 0.33 of a mile north of Exit 109 on Interstate $350,000 Bridge Painting 95 northbound. HCP 1

Aviation 022717.18 Transportation Administration Augusta State Funding for Operations at the State-owned Augusta Augusta $550,000 2018 Airport State Airport (AUG). General Program Administration

Aviation 022717.19 Transportation Administration Augusta State Funding for Operations at the State-owned Augusta Augusta $550,000 2019/20 Airport State Airport (AUG). General Program Administration

Aviation 022717.20 Transportation Administration Augusta State Operating costs for 2020 at the State owned Augusta Augusta $550,000 2019/20 Airport State Airport (AUG). General Program Administration

022938.00 Highway Safety and Spot Improvements Located at the intersection of Route 201 and Route 2019/20 Augusta Route 3 $300,000 3. HCP 2 Intersection Improvements

MaineDOT Multimodal System 023062.00 Operations Augusta Loader New loader for the airport. $450,000 2018 Capital Equipment Purchase

Augusta, Benton, 021763.00 Bowdoinham, Clinton, 2018 Interstate 95/295 Fairfield, Interstate 95 bridges from Richmond to Waterville. $1,300,000 Bridge Protective Coating Bridges HCP 4, 6, 1, Gardiner, 3, 2 Richmond, Waterville, West Gardiner

Highway Construction/ 022392.00 Rehabilitation Augusta, Beginning 0.16 of a mile east of the intersection of 2018 Route 202 $255,000 Manchester Granite Hill Road and extending easterly 1.67 miles. Highway Improvements - PE HCP 1 Only

68

0123456789 ID/Year Municipality Scope Name Description Funding

023571.00 Augusta Memorial Bridge (#5196) over the Kennebec Augusta, River on Route 201. Augusta Cushnoc Crossing Various 2019/20 Waterville, Bridge (#6400) over the on Route 3. $850,000 Locations Winslow Bridge Protective Coating Waterville Donald V Carter Bridge (#1141) over the HCP 2, 1 Kennebec River on Route 137.

WR 35446 Contracted tree removal on Interstate 95 Waterville- Augusta, Sidney, Custodial Maintenance 2018 Interstate 95 Augusta southbound, and Sidney-Augusta $250,000 Waterville northbound including the median. HCP 1

018253.00 Highway Construction/ Rehabilitation Beginning at West Road and extending north 0.36 of 2018 Belgrade Route 27 $3,125,000 a mile. HCP 2 Reconstruction

WR 32623 Ditching and replacing a culvert on Route 8 in Drainage Maintenance Belgrade beginning at the Pauls Acres Lane 2018 Belgrade Route 8 $29,000 intersection extending north 3.56 miles to the HCP 2, 3 Howland Hill Road intersection.

WR 32722 Ditching and replacing a culvert on the Castle Island Belgrade, Mount Drainage Maintenance Castle Island 2018 Road in Mount Vernon extending east 2.99 miles to $28,000 Vernon Road the Belgrade-Mount Vernon town line. HCP 4

023290.00 Belmont, China, Highway Paving Liberty, Beginning 0.27 of a mile west of Hanson Road and 2018 Montville, Route 3 $3,854,588 extending easterly 21.71 miles. Morrill, Palermo, Ultra Thin Bonded Wearing HCP 1 Searsmont Surface

022482.00 Highway Construction/ Rehabilitation Beginning at Falls Road and extending northeast 2018 Benton Route 139 $488,000 4.40 miles. HCP 3 PMRAP DOT Pugmill

022482.10 Highway Construction/ Rehabilitation Beginning at Falls Road and extending easterly 4.40 2018 Benton Route 139 $737,000 miles. HCP 3 PMRAP Laydown/Surface HMA

022829.00 Highway Safety and Spot Improvements Located at the intersection of Benton Avenue and the 2019/20 Benton Neck Road $211,500 Neck Road. HCP 3 Traffic Signals

023611.00 I-95 SB/ River Road Bridge (#1455) over River Road. 2019/20 Benton Interstate 95 $200,000 Bridge Strengthening Located 0.53 of a mile east of the Fairfield town line. HCP 1

69

0123456789 ID/Year Municipality Scope Name Description Funding

WR 34042 Producing, hauling and providing additional support PMRAP activities for the placement of plant mix recycled 2018 Benton Route 139 asphalt pavement (PMRAP) beginning at the $500,000 Sebasticook Bridge Road and extending northeast HCP 3 4.47 miles to the Fifteen Mile Stream Bridge.

WR 35471 Drainage Maintenance Replacing four instream pipes (#93635, #103934, 2018 Benton Route 139 $125,000 #93636, #93631) on Route 139 in Benton. HCP 3

022484.00 Highway Construction/ Rehabilitation Beginning at the north junction of Route 139 and 2018 Benton, Clinton Route 11 $348,150 extending northerly 4.23 miles. HCP 3 PMRAP DOT Pugmill

022484.10 Highway Construction/ Rehabilitation Beginning at the north junction of Route 139 and 2018 Benton, Clinton Route 11/100 $706,850 extending northerly 4.23 miles. HCP 3 PMRAP Laydown/Surface HMA

023360.00 Highway Paving Beginning at the Winslow town line and extending 2019 Benton, Clinton River Road $323,367 north 8.84 miles to Route 23. Light Capital Paving HCP 3, 4

023360.00 Highway Paving Gogan Road, Beginning at Route 139 and extending north 3.00 2019 Benton, Clinton $109,740 Pleasant Street miles to Route 11. Light Capital Paving HCP 4

023360.00 Highway Paving Beginning at Route 137B and extending north 5.44 2019 Benton, Winslow Garland Road $198,995 miles to Sebasticook Bridge Road. Light Capital Paving HCP 4

WR 34041 Producing, hauling, and providing additional support PMRAP activities for the placement of plant mix recycled 2018 Benton, Clinton Route 11 asphalt pavement (PMRAP) beginning 200 feet south $336,000 of Sebasticook Bridge Road and extending north HCP 3 4.23 miles to the Clinton-Burnham town line.

WR 34805 Ditching and replacing a culvert (#1001146) Drainage Maintenance beginning 0.05 of a mile north of Route 11 and 2018 Benton, Clinton River Road $43,000 extending north 7.83 miles, ending at the Canaan HCP 4 Road intersection in Clinton.

WR 34795 Ditching and installing multiple culverts in Winslow on Drainage Maintenance Route 100A beginning at the Route 201 intersection 2018 Benton, Winslow Route 100A $143,000 extending north 5.16 miles to the Route 11 HCP 3 intersection in Benton.

70

0123456789 ID/Year Municipality Scope Name Description Funding

WR 34803 Drainage Maintenance Ditching on the Garland Road in Winslow beginning 2018 Benton, Winslow Garland Road at the Route 137 intersection extending east for 5.67 $29,100 miles to the Route 139 intersection in Benton. HCP 4

022456.00 Highway Paving Beginning 0.02 of a mile north of Route 27 and Chelsea, 2019/20 Route 9 extending northerly 4.52 miles to the Augusta city $1,642,069 Randolph 1 1/4" Overlay line. HCP 2

023398.00 Highway Paving Chelsea, Beginning at Water Street and extending northeast 2018 Route 226 $742,491 Randolph Highway Cyclical Pavement 5.50 miles to Eastern Avenue. HCP 3 Resurfacing

021770.00 Highway Safety and Spot Improvements Large culvert (#269621) located 0.22 of a mile 2018 China Route 202 $480,000 northeast of Rockwood Drive. HCP 1 Large Culvert Replacement

023360.00 Highway Paving Weeks Mills Beginning at Dirigo Road and extending north 2.30 2019 China $84,134 Road miles to Route 32. Light Capital Paving HCP 4

WR 35110 Grader ditching and replacing four culverts beginning Drainage Maintenance Weeks Mills 2018 China at the Route 32 intersection extending south 2.3 $28,000 Road miles to the Dirigo Road intersection. HCP 4

021842.00 Highway Construction/ Beginning 1.39 miles north of Village Street and China, Rehabilitation extending northerly 5.65 miles to 1.14 miles north of 2019/20 Vassalboro, Route 32 the Gray Road. Beginning 0.21 of a mile north of $4,000,000 Winslow Preble Hill and extending northerly 2.40 miles to HCP 3 Highway Rehabilitation Timber Oaks Drive.

023543.00 Highway Paving Beginning at Route 202 and extending west 6.14 2019/20 China, Winslow Route 137 miles to Route 137B. Then extending north 1.04 $2,089,995 1 1/4" Overlay miles to Route 201. HCP 2

022232.00 Manley Holt Bridge (#2508) over Carrabassett 2018 Clinton River Road Stream. Located 0.22 of a mile north of Pishon Ferry $165,000 Bridge Improvements - PE Only Road. HCP 6

023360.00 Highway Paving Beginning at River Road and extending northeast 2019 Clinton Route 23 $99,498 2.72 miles. Light Capital Paving HCP 3

71

0123456789 ID/Year Municipality Scope Name Description Funding

023360.00 Highway Paving Beginning at Route 11 and extending north 6.93 2019 Clinton Hinckley Road $253,499 miles to Route 23. Light Capital Paving HCP 3, 4

WR 34098 Bridge and Structural Replacing the joint armor on the George W. Hinckley Bridge (#3389) over the Lower Kennebec River. 2018 Clinton Maintenance Route 23 $10,000 Located 0.16 of a mile east of the Route 201 HCP 3 intersection.

WR 34798 Drainage Maintenance Cleaning under guard rail beginning at the Route 11 Clinton Hinckley Road intersection and extending northwest 6.96 miles to $12,620 2018 the Route 23 intersection.

WR 35371 Bridge and Structural Removing the concrete slope under I-95 NB/ 2018 Clinton Maintenance Hinckley Road Hinckley Road Bridge (#5995) over Hinckley Road. $100,000 Located 0.30 of a mile east of True Road. HCP 1

WR 35373 Bridge and Structural Replacing aluminum rail and posts with Thrie-Beam guard rail on Mutton Lane Bridge (#5997) over Clinton Maintenance Mutton Lane $100,000 2018 Interstate 95 north and southbound. Located 0.33 of a mile south of Club House Road.

023376.00 Farmingdale, Highway Paving Beginning at the intersection of Route 197 and Hallowell, Hallowell 2019 extending north 15.34 miles to the end of Middle $561,222 Litchfield, West Litchfield Road Light Capital Paving Street. HCP 4, 6 Gardiner

WR 32312 Bridge and Structural Repairing pier and wing walls on the Fayette Mills 2018 Fayette Maintenance Route 17 Bridge (#3053) over the outlet. Located $115,000 0.10 of a mile south of Lovejoy Pond Road. HCP 3

Bicycle-Pedestrian 013344.10 Bicycle-pedestrian trail along the rail line from Water Cobbossee Gardiner Trail, Off-Road Street to Winter Street. Also, included improvements $590,047 2018 Stream Trail to rail bridge over stream along Summer Street. New Construction

018735.00 Bridge Street Bridge (#2101) over Cobbossee 2018 Gardiner Route 201 Stream. Located 0.04 of a mile north of Water $7,775,000 Bridge Replacement Street. HCP 2

018736.00 Main Avenue Bridge (#3098) over Cobbossee 2018 Gardiner Route 24 $3,055,000 Bridge Replacement Stream. Located 0.20 of a mile south of Route 27. HCP 3

72

0123456789 ID/Year Municipality Scope Name Description Funding

018736.10 Bicycle-Pedestrian Beginning at the Kennebec River Rail Trail and extending south 0.12 of a mile to Arcade Street, then 2018 Gardiner Bicycle/Pedestrian Bridge Main Avenue $1,031,979 beginning at Arcade Street and extending west 0.16 HCP 4 New Construction of a mile to the Bridge Street Bridge on Route 201.

022312.00 Route 201 Bridge (#1533) over Interstate 295 2019/20 Gardiner Route 201 southbound. Located 0.05 of a mile northeast of Exit $350,000 Bridge Painting 49 off Interstate 295. HCP 2

022314.00 Route 201 Bridge (#6318) over Interstate 295 2019/20 Gardiner Route 201 northbound. Located 0.18 of a mile southwest of $350,000 Bridge Painting Enterprise Avenue. HCP 2

022684.00 Highway Safety and Spot Improvements 2019/20 Gardiner Route 201 Replace traffic signals at Route 126 and at Route 27. $630,000

HCP 3, 2 Intersection Improvements

023376.00 Gardiner, Highway Paving Plains Road and Beginning at Hallowell Road and extending northeast 2019 Litchfield, West $349,026 Pond Road 9.54 miles to the intersection of Route 9. Gardiner Light Capital Paving HCP 4

WR 34962 Grader ditching and cleaning under guard rail Gardiner, West Drainage Maintenance beginning at the Litchfield-West Gardiner town line 2018 Pond Road $70,000 Gardiner and extending north 3.76 miles to the Route 126 HCP 4 intersection at the West Gardiner-Gardiner town line.

018622.00 Highway Construction/ Rehabilitation Beginning 0.10 of a mile north of Winthrop Street and 2018 Hallowell Route 201 $5,140,000 extending southerly 0.54 of a mile. HCP 1 Reconstruction

023376.00 Highway Paving Beginning at Winthrop Street and extending north 2019 Hallowell Whitten Road 0.38 of a mile to 0.03 of a mile from the Augusta city $13,902 Light Capital Paving line. HCP 4

WR 34972 Ditching on the Hallowell Litchfield Road beginning at Hallowell, West Drainage Maintenance Hallowell 2018 the West Gardiner-Farmingdale town line extending $75,000 Gardiner Litchfield Road north 4.47 miles to Winthrop Street in Hallowell. HCP 4

022246.00 Palmer Bridge (#5141) over Maxwell Brook. Located 2019/20 Litchfield Richmond Road $800,000 Bridge Culvert Replacement 0.39 of a mile north of the Bowdoin town line. HCP 3

73

0123456789 ID/Year Municipality Scope Name Description Funding

023376.00 Litchfield, Highway Paving Pond Road and Beginning at the Hallowell Road intersection and 2019 Manchester, $307,684 Neck Road extending north 8.41 miles to Route 202. West Gardiner Light Capital Paving HCP 4

023655.00 Litchfield, Thoroughfare Thoroughfare Bridge (#3925) over Pleasant Pond. 2019/20 $400,000 Richmond Bridge Deck Replacement Road Located on the Litchfield- Richmond town line. HCP 4

022376.00 Litchfield, West Hallowell Tappan Bridge (#2834) over Cobbossee Stream. 2019/20 $250,000 Gardiner Bridge Substructure Litchfield Road Located on the West Gardiner- Litchfield town line. Rehabilitation HCP 4

023324.00 Highway Paving Litchfield, West Beginning 0.14 of a mile west of the Huntington Hill 2018 Route 9 $539,994 Gardiner Highway Cyclical Pavement Road and extending northwesterly 3.99 miles. HCP 3 Resurfacing

WR 34968 Ditching and grader ditching on Route 197 in Litchfield, Drainage Maintenance Litchfield beginning at the Wales-Litchfield town line 2018 Route 197 $154,000 Richmond extending east 8.16 miles to the Bowdoin-Richmond HCP 3 town line.

WR 32889 Ditching and replacing two culverts on Route 135 Manchester, Drainage Maintenance beginning at the Scribner Hill Road intersection in 2018 Route 135 $32,000 Readfield Readfield extending north 3.25 miles to the Knowles HCP 4 Road intersection in Belgrade.

019404.00 Bicycle-Pedestrian Beginning at Route 132 and extending northwest 2018 Monmouth Trail, On-Road Academy Road $696,600 0.60 of a mile. HCP 6 New Construction

023376.00 Monmouth, Highway Paving Beginning at the intersection of Route 132 and 2019 Readfield, Route 135 $510,368 extending north 13.95 miles. Winthrop Light Capital Paving HCP 4, 1, 3

021698.00 West Mount Vernon Bridge (#2930) over Echo Lake. 2018 Mount Vernon Route 41 $1,600,000 Bridge Replacement Located 0.04 of a mile east of Sandy River Road. HCP 4

022096.00 Highway Paving Beginning at the Vienna town line and extending 2018 Mount Vernon Route 41 $204,258 south 5.77 miles. Light Capital Paving HCP 4

74

0123456789 ID/Year Municipality Scope Name Description Funding

022092.00 Highway Paving Beginning at Middle Road and extending north 1.36 2018 Oakland Route 23 $47,815 miles to Route 137. Light Capital Paving HCP 3

022092.00 Highway Paving Beginning 0.01 of a mile south of Trafton Road and 2018 Oakland Middle Road $35,158 extending northerly 1.00 mile to Route 23. Light Capital Paving HCP 4

022178.00 Bicycle-Pedestrian Located at the intersections of Oak Street, Pleasant 2019/20 Oakland Urban Highways Route 137 $120,000 Street, and Heath Street for 0.03 of a mile. HCP 3 Intersection Improvements

022092.00 Highway Paving Oakland, Beginning at Route 3 and extending north 1.72 miles 2018 Alder Park Road $60,472 Waterville to Route 202. Light Capital Paving HCP 3

022092.00 Highway Paving Oakland, Beginning at Mitchell Road and extending west 1.97 2018 Webb Road $69,262 Waterville miles to Libby Hill Road. Light Capital Paving HCP 4

023699.00 Highway Construction/ Oakland, Rehabilitation Beginning at Middle Road and extending east 1.44 2019/20 Trafton Road $360,000 Waterville miles. HCP 3 PMRAP DOT Pugmill

WR 32888 Ditching and cleaning under guard rail on Route 11 in Oakland, Drainage Maintenance Oakland beginning at the Route 23 intersection 2018 Route 11 $23,000 Waterville extending east 1.61 miles to the First Park Drive HCP 2 intersection.

022297.00 Maintenance 2019 Pittston Route 27 Located 0.07 of a mile south of Whitefield Road. $150,000 Drainage Improvements HCP 2

021744.00 Pittston, Togus Bridge (#2862) over Togus Stream. Located 2018 Route 27 $150,000 Randolph Bridge Substructure at the Pittston town line. Rehabilitation HCP 2

WR 33363 Cutting trees and removing brush beginning at Route Pittston, Custodial Maintenance Route 126 220 in Washington and extending 21.34 miles east to $100,000 2018 Washington the Route 27 intersection in Randolph.

75

0123456789 ID/Year Municipality Scope Name Description Funding

021819.00 Highway Construction/ Rome, Rehabilitation Beginning at Route 27 and extending east 5.62 miles 2018 Route 225 $475,000 Smithfield to Route 8. HCP 4 PMRAP DOT Pugmill

021819.10 Highway Construction/ Rome, Rehabilitation Beginning at Route 27 and extending east 5.62 miles 2018 Route 225 $925,000 Smithfield to Route 8. HCP 4 PMRAP Laydown/Surface HMA

Producing, hauling and providing additional support WR 32224 activities for the placement of plant mix recycled PMRAP asphalt pavement (PMRAP) beginning at Route 225 2018 Rome, Smithfield Route 225 $320,000 and extending east 5.63 miles to 0.68 of a mile HCP 4 easterly of the Jamaica Point Road intersection in Rome.

WR 32890 Drainage Maintenance Ditching in Sidney on Route 104 beginning at the 2018 Sidney Route 104 Augusta-Sidney town line extending north 5.64 miles $33,500 to the Lyons Road. HCP 3

023400.00 Highway Paving Sidney, Beginning 0.04 of a mile south of the Lyons Road 2018 Route 104 $720,892 Waterville Highway Cyclical Pavement and extending northerly 5.34 miles to Webb Road. HCP 3 Resurfacing

018803.00 Highway Construction/ Rehabilitation Beginning 1.14 miles north of Gray Road and 2019/20 Vassalboro Route 32 $805,000 extending northerly 0.73 of a mile. HCP 3 Highway Rehabilitation

021452.00 Maintenance Large culvert (#47040) located 0.22 of a mile north of 2019 Vassalboro Route 32 $150,000 Oak Grove Road. Large Culvert Replacement HCP 3

Aviation 018707.01 Safety and infrastructure improvements that may Robert LaFleur Waterville Planning And Research include a Wildlife Hazard Assessment at the $103,000 2018 Airport Waterville, Robert LaFleur Airport (WVL). Planning Studies

Aviation 018707.03 Safety and infrastructure improvements that may Robert LaFleur include snow removal equipment acquisition (snow Waterville Runway/Taxiway $288,400 2019/20 Airport blower) at the Waterville, Robert LaFleur Airport Capital Equipment Purchase (WVL).

Aviation 018707.04 Safety and infrastructure improvements that may Robert LaFleur Waterville Runway/Taxiway include design and permitting for Taxiway "A" at the $360,500 2019/20 Airport Waterville, Robert LaFleur Airport (WVL). Reconstruction

76

0123456789 ID/Year Municipality Scope Name Description Funding

Aviation 018707.17 Safety and infrastructure improvements that may Robert LaFleur include obstruction removal, grubbing and grinding to Waterville Navigation Aids/Lights $154,500 2018 Airport include design and permitting at the Waterville, Removal Of Obstructions Robert LaFleur Airport (WVL).

021894.00 I-95 SB/ Webb Road Bridge (#1461) over Webb 2018 Waterville Interstate 95 SB Road. Located 1.41 miles north of the Sidney town $250,000 Bridge Improvements - PE Only line. HCP 1

021900.00 I-95 NB/ Webb Road Bridge (#5813) over Webb 2018 Waterville Interstate 95 NB Road. Located 1.41 miles north of the Sidney town $250,000 Bridge Improvements - PE Only line. HCP 1

Highway Construction/ Business Partnership Initiative: Intersection 021936.01 Rehabilitation improvements, parking reconfiguration and traffic Waterville Downtown pattern changes associated with the implementation $600,000 2018 Highway Improvements - PE of Waterville's Downtown Improvement Feasibility Only Study.

022374.00 Gilman Street Bridge (#3121) over Messalonskee 2019/20 Waterville Gilman Street Stream. Located 0.03 of a mile east of Messalonskee $300,000 Bridge Painting Avenue. HCP 4

023246.00 Highway Construction/ Rehabilitation Beginning at Eight Rod Road and extending east 2019/20 Waterville Trafton Road $2,225,000 0.95 of a mile to Route 104. HCP 3 Highway Rehabilitation

023505.00 Armstrong Road/ I-95 Bridge (#5815) over Interstate 2019/20 Waterville Armstrong Road $5,800,000 Bridge Replacement 95. Located 0.05 of a mile east of Marston Road. HCP 6

023541.00 Chaplin Street Bridge (#6039) over Route 11. 2019/20 Waterville Colby Street $350,000 Bridge Painting Located 0.13 of a mile north of Chaplin Street. HCP 2

023635.00 North Street Overpass Bridge (#5235) over M C 2019/20 Waterville North Street $150,000 Bridge Wearing Surface Railroad. Located 0.02 of a mile north of West Street. Replacement HCP 4

023789.00 Highway Paving Beginning at Old Winthrop Road and extending 2019/20 Wayne Route 133 $845,295 north 3.18 miles to Livermore Falls town line. 1 1/4" Overlay HCP 2

77

0123456789 ID/Year Municipality Scope Name Description Funding

022370.00 Pond Road/ I-295 Bridge (#6320) over Interstate 295. 2019/20 West Gardiner Pond Road $400,000 Bridge Painting Located 0.91 of a mile south of Old Lewiston Road. HCP 4

023376.00 Highway Paving Beginning at the Hallowell Litchfield Road and 2019 West Gardiner High Street $172,318 extending east 4.71 miles to the Gardiner town line. Light Capital Paving HCP 4

WR 34097 Bridge and Structural Replacing the joint armor and repairing the curb on the Route 126/ I-295 Bridge (#6321) in West 2018 West Gardiner Maintenance Route 126 $20,000 Gardiner over Interstate 295 north and southbound. HCP 2 Located 0.44 of a mile west of Old Lewiston Road.

WR 34899 Bridge and Structural Replacing the wearing surface on the Collins Bridge Collins Mills West Gardiner Maintenance (#3331) over Cobbossee Stream in West Gardiner. $125,000 2018 Road Located 0.05 of a mile north of Emery Lane.

WR 35236 Ditching and replacing culverts on High Street in Drainage Maintenance West Gardiner beginning at Browns Corner 2018 West Gardiner High Street $75,000 extending east 4.68 miles to the West Gardiner- HCP 4 Gardiner town line.

Highway Safety and Spot 021841.00 Improvements Located at the intersection of Route 17 and Route 2018 Windsor Route 17 $120,000 32. Highway Improvements - PE HCP 2 Only

022268.00 Fish Bridge (#0509) over Winslow Stream. Located 2018 Winslow Garland Road $115,000 Bridge Improvements - PE Only 0.10 of a mile southwest of the Benton town line. HCP 4

Highway Safety and Spot 023803.00 Improvements Large culvert (#93710) located 0.55 of a mile south 2018 Winslow Route 100A $40,000 of Heywood Road. Large Culvert Replacement - HCP 3 PE Only

022222.00 Bicycle-Pedestrian Beginning 0.17 of a mile west of the southbound exit of Route 202 and extending westerly 0.10 of a mile to 2019/20 Winthrop Urban Highways Main Street $354,025 Metcalf Road. Continuing at Depot Street and HCP 3 Sidewalk Construction extending westerly 0.03 of a mile to Route 41.

023034.00 Highway Safety and Spot Improvements Located at the intersection of Route 202 and 2019/20 Winthrop Route 202 $50,000 Highland Avenue. HCP 1 Flashing Beacon

78

0123456789 Knox

Knox County Population 39,736 Land Area (sq mi) 365 Bridges 90 Highway Corridor Priority Miles

HCP 1 24 Knox HCP 2 36 Appleton HCP 3 35

Washington HCP 4 131

Hope

Camden Total HCP 1-4 226 Union

Rockport

Warren North Haven Rockland

Thomaston

Owls Head Vinalhaven South Thomaston Isle au Haut Cushing Friendship

Saint George Muscle Ridge Twp

Knox County Island

Matinicus Isle Plt

Criehaven Twp Knox ID/Year Municipality Scope Name Description Funding

WR 35070 Ditching and replacing nine culverts on Route 105 in Drainage Maintenance Appleton beginning 0.25 of a mile east of the Liberty- 2018 Appleton Route 105 $97,000 Appleton town line extending easterly to the Route HCP 4 131 intersection.

WR 33386 Appleton, Drainage Maintenance Replacing three cross culverts (#280370, #280400, 2018 Route 105 $150,000 Camden, Hope #280422) on Route 105 in Hope and Appleton. HCP 4

023539.00 Bicycle-Pedestrian Pedestrian facility improvements along Route 1, 2019/20 Belfast, Camden Trail, On-Road Route 1 Route 52, Chestnut Street, Bayview Street, and $614,143 HCP 1, 4, 6, Mechanic Street. New Construction 3

018283.00 Highway Construction/ Rehabilitation Beginning 0.56 of a mile north of Sagamore Farm 2019/20 Camden Route 1 $5,530,000 Road and extending northerly 1.54 miles. HCP 1 Reconstruction

019400.00 Bicycle-Pedestrian Beginning at Matthew John Avenue and extending north 0.30 of a mile. 2019/20 Camden Trail, On-Road Route 105 $382,500

HCP 4 New Construction

021771.00 Highway Safety and Spot Improvements Beginning at Wood Street and extending north 0.31 2019/20 Camden Route 1 $321,000 of a mile to 0.03 of a mile northerly of High Street. HCP 1 Drainage Improvements

022608.00 Spring Brook Bridge (#2794) over Spring Brook. 2019/20 Camden Route 1 Located 0.94 of a mile southwest of the Lincolnville $2,500,000 Bridge Replacement town line. HCP 1

022610.00 Great Brook Bridge (#2326) over Great Brook. 2019/20 Camden Route 1 $700,000 Bridge Replacement Located 0.05 of a mile south of Dyer Drive. HCP 1

Highway Safety and Spot 022839.00 Improvements 2018 Camden Route 1 Located 0.03 of a mile northeast of Harden Avenue. $75,000 Slope Stabilization/Protection - HCP 1 PE Only

023380.00 Camden, Highway Paving Beginning 0.30 of a mile south of Lincolnville town 2019 Lincolnville, Route 1 $198,992 line and extending northerly 5.44 miles. Northport Light Capital Paving HCP 1

79

0123456789 ID/Year Municipality Scope Name Description Funding

018880.00 Bicycle-Pedestrian Camden, Beginning at Quarry Hill Road in Camden and 2019/20 Trail, On-Road Route 1 $606,000 Rockport extending south 0.36 of a mile. HCP 1 New Construction

023380.00 Highway Paving Beginning at Pleasant Point Road and extending 2019 Cushing Cross Road $57,064 west 1.56 miles to Route 97. Light Capital Paving HCP 4

WR 35156 Ditching and replacing culverts beginning 0.02 of a Drainage Maintenance mile south of Old Settlers Lane in Cushing extending 2018 Cushing River Road $50,264 northerly 2.5 miles to the Cushing-Thomaston town HCP 4 line.

023380.00 Highway Paving Cushing, Pleasant Point Beginning at Route 1 and extending south 10.94 2019 $400,179 Thomaston Road miles. Light Capital Paving HCP 4

023380.00 Highway Paving Friendship, Beginning at Route 97 and extending north 10.09 2019 Route 220 $369,087 Waldoboro miles to Route 1. Light Capital Paving HCP 4

WR 35299 Grader ditching on Route 220 beginning in Friendship at the Route 97 intersection extending Friendship, Drainage Maintenance 2018 Route 220 north 9 miles to 0.28 of a mile southerly of Pleasant $15,000 Waldoboro Street in Waldoboro. HCP 4

022098.00 Highway Paving Beginning at Iron Point Road and extending north 2019 North Haven Main Street $286,586 1.92 miles to Crab Tree Point Road. Light Capital Paving HCP 4

021808.00 Highway Safety and Spot Improvements Large culvert (#46010) located 0.05 of a mile north of 2018 Owls Head Route 73 $195,000 North Shore Drive. HCP 3 Large Culvert Rehabilitation

018793.00 Highway Paving Owls Head, Beginning at Route 1 in Rockland and extending 2019/20 Route 73 $574,000 Rockland south 0.90 of a mile. Mill And Fill HCP 3

018793.10 Maintenance Owls Head, Beginning at Route 1 in Rockland and extending 2019 Route 73 $23,000 Rockland south 0.90 of a mile. Drainage Improvements HCP 3

80

0123456789 ID/Year Municipality Scope Name Description Funding

Marine 018376.20 Margaret Chase Design effort to rehabilitate the Margaret Chase Rockland Intermodal Passenger Facility $85,000 2019/20 Smith Smith Ferry. Rehabilitation

Aviation 018713.01 Safety and infrastructure improvements that may Knox County include reconstruction of the apron - Phase 1 and Rockland Apron $1,318,629 2019/20 Regional Airport drainage exploration at the Knox County Regional Reconstruction Airport (RKD).

Aviation 018713.02 Safety and infrastructure improvements that may Knox County Rockland Apron include reconstruction of the apron - Phase 2 at the $783,945 2019/20 Regional Airport Knox County Regional Airport (RKD). Reconstruction

Aviation 018713.03 Safety and infrastructure improvements that may Knox County include an FAA reimbursable agreement for the Rockland Runway/Taxiway $164,800 2018 Regional Airport reconstruction of Runway 13-31 at the Knox County Reconstruction Regional Airport (RKD).

Aviation 018713.04 Safety and infrastructure improvements that may Knox County Rockland Runway/Taxiway include Runway 13-31 extension - Phase 2 at the $805,460 2018 Regional Airport Knox County Regional Airport (RKD). New Construction

Aviation 018713.05 Safety and infrastructure improvements that may Knox County Rockland Runway/Taxiway include a security system at the Knox County $360,500 2019/20 Regional Airport Regional Airport (RKD). Capital Equipment Purchase

018794.10 Highway Construction/ Rehabilitation Culvert replacement with large culvert and removal of 2019/20 Rockland Route 1 existing failing gabion wall. Located 0.10 of a mile $270,000 north of Waldo Avenue. HCP 1 Large Culvert Replacement

MaineDOT Multimodal System 022194.00 Operations Margaret Chase Rockland Margaret Chase Smith Ferry. $4,000,000 2019 Smith Ferry Rehabilitation

022458.00 Highway Paving Beginning 0.10 of a mile northeast of Glenwood 2019/20 Rockland Route 1 $618,944 Avenue and extending northeasterly 1.22 miles. 1 1/4" Overlay HCP 1

MaineDOT Multimodal System 022946.00 Operations Maine State Parking lot reconfiguration including expansion and Rockland $250,000 2018 Ferry Service overlay at the Maine State Ferry Service. Rehabilitation

81

0123456789 ID/Year Municipality Scope Name Description Funding

Marine 023000.00 Multi-purpose project to include dredging, new pier Rockland Piers, Floats And Fenders Fish Pier $500,000 2019/20 surface, pier extension and berthing. New Construction

023268.00 Bicycle-Pedestrian Move existing crosswalk signal to appropriate 2018 Rockland Trail, On-Road Main Street $86,000 location on Main Street. HCP 1 Rehabilitation

MaineDOT Multimodal System 023577.00 Operations Captain Rockland Captain Philbrook Ferry design and rehabilitation. $200,000 2020 Philbrook Ferry Rehabilitation

MaineDOT Multimodal System 023811.00 Operations Henry Lee Ferry mid-life rebuild, design and Rockland Henry Lee Ferry $2,200,000 2020 construction. Reconstruction

018794.00 Highway Paving Rockland, Beginning at Maverick Street and extending north 2019/20 Route 1 $671,484 Rockport 0.86 of a mile. Mill And Fill HCP 1

021822.00 Highway Safety and Spot Improvements Large culvert (#46916) located 0.62 of a mile west of 2018 Saint George Route 131 $215,000 Glenmere Road. HCP 3 Large Culvert Replacement

023380.00 Saint George, Highway Paving Beginning at Route 131 and extending east 3.41 2019 South Route 73 $124,736 miles. Thomaston Light Capital Paving HCP 3

023759.00 Highway Construction/ Saint George, Rehabilitation Beginning 0.03 of a mile south of Island Road and 2019/20 South Route 73 $855,000 extending westerly 3.42 miles. Thomaston HCP 3 PMRAP DOT Pugmill

WR 35100 Replacing thirteen culverts and incidental ditching Saint George, Drainage Maintenance beginning at the River Road intersection in Saint 2018 South Route 73 $56,000 George extending east then northerly for 3.06 miles Thomaston HCP 3 to the Island Road intersection in South Thomaston.

023619.00 James Andrew Griffith Bridge (#2786) over St. Thomaston, 2019/20 Route 1 George River. Located on the Warren - Thomaston $200,000 Warren Bridge Substructure Rehabilitation town line. HCP 1

82

0123456789 ID/Year Municipality Scope Name Description Funding

WR 35112 Ditching on Route 131 beginning at the Route 1 Thomaston, Drainage Maintenance 2018 Route 131 intersection in Thomaston extending north 8.09 miles $28,000 Union to the Warren-Union town line. HCP 4

021707.00 Lanes Island Lane Island Bridge (#5270) over Tidal Flow. Located 2019/20 Vinalhaven $1,500,000 Bridge Replacement Road 0.06 of a mile south of Round the Mountain Road. HCP 6

022098.00 Highway Paving North Haven Beginning at Calderwood Neck Road and extending 2019 Vinalhaven $782,142 Road southeast 5.24 miles. Light Capital Paving HCP 4

022098.00 Highway Paving Beginning at Sands Road and extending northeast 2019 Vinalhaven West Main Street $46,272 0.31 of a mile to High Street. Light Capital Paving HCP 4

MaineDOT Multimodal System 023821.00 Operations Vinalhaven Crew Quarters Vinalhaven Crew Quarter expansion. $250,000 2019 New Construction

Marine 023823.00 Vinalhaven Ferry Add dolphin on south side, fender rehabilitation, Vinalhaven Piers, Floats And Fenders $1,200,000 2019/20 Slip walkway and wave fence. New Construction

020888.00 Highway Paving 2018 Warren Route 90 Beginning at Route 1 and extending east 3.62 miles. $1,386,000 Mill And Fill HCP 2

Highway Safety and Spot 021835.00 Improvements Large culvert (#46645) located 0.06 of a mile north of 2018 Warren Route 235 $50,000 the Waldoboro town line. Large Culvert Improvements - HCP 4 PE Only

022472.00 Highway Paving Beginning 0.06 of a mile east of Camden Road and 2018 Warren Route 1 $835,660 extending southeasterly 1.79 miles. 1 1/4" Overlay HCP 1

Highway Safety and Spot 022996.06 Improvements Beginning 0.10 of a mile north of Cooper Road and 2018 Warren Route 90 $44,000 extending northerly 0.1 of a mile. Rest Area Construction/ HCP 2 Improvements

83

0123456789 ID/Year Municipality Scope Name Description Funding

023649.00 St. George River Bridge (#5654) over St. George 2019/20 Warren Bridge Substructure Route 90 River. Located 0.04 of a mile southwest of Company $300,000 Rehabilitation Lane. HCP 2

WR 34872 Bridge and Structural Replacing the curb, posts and bridge rails and repairing the wing walls on the Kalloch Bridge Warren Maintenance Western Road $45,000 2018 (#3785) over the Back River. Located 0.15 of a mile south of the North Pond Road intersection.

WR 34664 Department Building and Lot Installing new shingles on the Washington Washington Maintenance Route 17 maintenance camp salt dome (#B36165). Located $62,500 2018 0.15 of a mile south of Bump Hill Road.

WR 35071 Drainage Maintenance Ditching on Route 126 in Washington beginning 0.04 2018 Washington Route 126 of a mile east of the Fitch Road extending easterly $16,730 2.09 miles to the Route 220 intersection. HCP 4

84

0123456789 Lincoln

Lincoln County Population 34,457 Land Area (sq mi) 456 Somerville Bridges 101 Highway Corridor Priority Miles HCP 1 27 HCP 2 33 HCP 3 41 HCP 4 226 Whitefield

Jefferson Total HCP 1-4 327

Dresden Waldoboro

Nobleboro

Alna Lincoln

Dresden Newcastle

Damariscotta Wiscasset

Bremen

Edgecomb

South Bristol Bristol

Westport Boothbay Island

Boothbay Harbor

Southport Lincoln ID/Year Municipality Scope Name Description Funding

WR 34960 Grader ditching on the West Alna Road beginning at Drainage Maintenance the intersection of Route 218 in Wiscasset extending 2018 Alna, Wiscasset West Alna Road $37,000 north 6.89 miles to the Route 218 intersection in HCP 4 Alna.

Public Transportation 022176.00 Boothbay Fire Pave, stripe, and sign a new Park and Ride facility Boothbay Parking Lots $75,000 2019/20 Station located at the Boothbay Fire Station. New Construction

022607.00 Barters Island Barters Island Bridge (#2039) over Back River. 2018 Boothbay $8,080,000 Bridge Replacement Road Located 0.06 of a mile east of Spofford Lane. HCP 4

Marine 023807.00 The Footbridge Boothbay Piers, Floats And Fenders and Town Pedestrian footbridge. $563,164 2019/20 Landing Rehabilitation

022831.00 Highway Safety and Spot Improvements Beginning 0.12 of a mile south of Bay Street and 2019/20 Boothbay Harbor Atlantic Avenue $300,000 extending southerly 0.40 of a mile. HCP 4 Drainage Improvements

WR 34094 Bridge and Structural Repairing the joint armor on the Southport Bridge 2018 Boothbay Harbor Maintenance Route 27 (#2789) over Townsend Gut. Located on the $10,000 Boothbay Harbor-Southport town line. HCP 4

021751.00 Boothbay Southport Bridge (#2789) over Townsend Gut. 2018 Harbor, Route 27 $300,000 Located at Boothbay Harbor - Southport town line. Southport Bridge Improvements - PE Only HCP 4

WR 34140 Installing new guard rail and stabilizing the existing Boothbay Operational and Safety slope beginning at the Plummer Road intersection in 2018 Harbor, Maintenance Route 27 $22,062 Southport extending north 0.88 of a mile to the West Southport HCP 4 Harbor Dam Bridge in Boothbay Harbor.

019397.00 Bicycle-Pedestrian Boothbay, Beginning at Back River Road and extending south 2019/20 Trail, On-Road Route 27 $667,269 Boothbay Harbor 0.87 of a mile. HCP 2 New Construction

022094.00 Highway Paving Beginning at Huddle Road and extending south 2.96 2018 Bristol Route 130 $104,784 miles to Pemaquid Loop Road. Light Capital Paving HCP 3, 4

85

0123456789 ID/Year Municipality Scope Name Description Funding

022094.00 Highway Paving Snow Ball Hill Beginning at the north intersection of Route 130 and 2018 Bristol $77,880 Road extending south 2.20 miles. Light Capital Paving HCP 4

022094.00 Highway Paving Bristol, South Beginning at Route 129 and extending south 2.80 2018 Harrington Road $99,120 Bristol miles to Route 130. Light Capital Paving HCP 4

019406.00 Bicycle-Pedestrian Beginning 0.03 of a mile south of Route 1B and extending southerly 0.40 of a mile. 2018 Damariscotta Trail, On-Road Route 129 $489,620

HCP 3 New Construction

022094.00 Highway Paving Beginning at Main Street and extending south 1.91 2018 Damariscotta Route 129 $67,614 miles to the Bristol town line. Light Capital Paving HCP 3

WR 35443 Drainage Maintenance Replacing instream culvert (#131518) located 0.02 of 2018 Damariscotta Route 129 $120,000 mile south of Days Cove Lane. HCP 3

022094.00 Highway Paving Beginning at Route 128 and extending east 0.54 of a 2018 Dresden Indian Road $19,116 mile to Route 127. Light Capital Paving HCP 4

022421.00 Highway Safety and Spot Improvements Large culvert (#131773) located 0.55 of a mile north 2019/20 Dresden Route 127 $725,000 of James Eddy Road. HCP 4 Large Culvert Replacement

WR 35440 Drainage Maintenance Replacing a culvert (#131750) located 0.06 of a mile 2018 Dresden Route 127 $175,000 north of the Day Lane intersection. HCP 4

WR 35441 Drainage Maintenance Replacing culvert (#131599) located 0.13 of a mile 2018 Dresden Route 128 $150,000 north of Courthouse Road. HCP 4

WR 35442 Drainage Maintenance Replacing instream culvert (#780152) located 0.13 of 2018 Dresden Route 128 $125,000 a mile north of Popp Road. HCP 4

86

0123456789 ID/Year Municipality Scope Name Description Funding

022094.00 Highway Paving Dresden, Beginning at Route 1 and extending northerly 14.69 2018 Route 127 $520,026 Woolwich miles to Route 27. Light Capital Paving HCP 3, 4, 1

022094.00 Highway Paving Dresden, Beginning at Route 27 and extending south 15.20 2018 Route 128 $538,080 Woolwich miles to Route 127. Light Capital Paving HCP 4

WR 35385 Milling pavement in preparation for Light Capital Dresden, Surface and Base Maintenance Route 127 Paving (LCP) extending south 14.7 miles to the $65,000 2018 Woolwich Route 1 intersection in Woolwich.

021783.00 Highway Safety and Spot Improvements Preliminary Engineering: Located at the intersection 2019/20 Edgecomb Route 1 $1,650,000 of Route 1 and Route 27. HCP 1 Intersection Improvements

023585.00 Highway Safety and Spot Improvements Located 0.01 of a mile west of Clifford Road and 2019/20 Edgecomb Eddy Road $60,000 extending northerly 0.55 of a mile. HCP 4 Slope Stabilization/Protection

Highway Safety and Spot 023587.00 Improvements Located 0.01 of a mile west of Clifford Road and 2019/20 Edgecomb Eddy Road $150,000 extending northerly 0.55 of a mile. Guard Rail Installation And HCP 4 Replacement

WR 35383 Department Building and Lot Paving the Edgecomb Maintenance Lot (#55158). 2018 Edgecomb Maintenance Route 1 $85,000 Located across from Davis Island Drive. HCP 1

022094.00 Highway Paving Beginning at the Newcastle town line and extending 2018 Jefferson Route 215 $358,248 north 10.12 miles to Route 32. Light Capital Paving HCP 4, 3

WR 35384 Surface and Base Maintenance Milling pavement in preparation for Light Capital Jefferson Route 215 Paving (LCP) beginning at the Jefferson town line $47,500 2018 and extending north 10.12 miles to Route 32.

WR 33389 Drainage Maintenance Replacing a cross culvert (#130352) located 0.10 of 2018 Newcastle Route 213 $35,000 a mile south of the Jefferson-Newcastle town line. HCP 4

87

0123456789 ID/Year Municipality Scope Name Description Funding

WR 35393 Bridge and Structural Replacing aluminum rail with galvanized tube steel 2018 Newcastle Maintenance Route 1 rail on Ramp A (#5887) over Route 1B. Located 0.28 $60,000 of a mile north of the Hopkins Hill Road intersection. HCP 1

016750.20 The Gut Bridge (#2339) over The Gut. Located 0.17 2018 South Bristol Route 129 $280,000 Bridge Improvements of a mile north of West Side Road. HCP 4

022094.00 Highway Paving Beginning 0.14 of a mile south of Half Moon Cove 2018 South Bristol Route 129 Road and extending south 4.48 miles to Middle $158,592 Light Capital Paving Road. HCP 4

WR 34943 Drainage Maintenance Ditching and replacing four culverts beginning at the 2018 South Bristol Route 129 Tidewater Way intersection extending south 4.03 $36,000 miles to the Thompson Inn Road intersection. HCP 4

018748.00 Thompsons Bridge (#2848) over Decker Cove. 2018 Southport Route 238 $2,700,000 Bridge Replacement Located 0.03 of a mile south of Route 27. HCP 4

018230.00 Wagner Number Two Bridge (#2905) over Hoak 2019/20 Waldoboro Route 32 $800,000 Bridge Replacement Brook. Located 0.30 of a mile south of Depot Street. HCP 3

Marine 018868.00 Replace bulkhead, replace and expand boat ramp, Pine Street Waldoboro Piers, Floats And Fenders including curbing and drainage improvements for $252,000 2018 Landing parking area and new facility. New Construction

020887.00 Highway Paving Beginning at Winslows Mills Road and extending 2018 Waldoboro Route 1 northeast 3.90 miles to 0.16 of a mile southerly of the $1,728,000 1 1/4" Overlay Waldoboro-Warren town line. HCP 1

023380.00 Highway Paving Beginning at Route 1 and extending east 1.75 miles 2019 Waldoboro Main Street $64,014 to Friendship Road. Light Capital Paving HCP 4, 6

Rail 023462.00 Rockland Branch Rockland Rail Bridge 65.91 (#7659) over Medomak Waldoboro Rail Bridge $10,000 2019/20 Rail Line River. Located on the Rockland Branch rail line. Rehabilitation

88

0123456789 ID/Year Municipality Scope Name Description Funding

WR 34892 Drainage Maintenance Ditching and replacing eight culverts beginning at the 2018 Waldoboro West Main Street Route 1 intersection extending east 1.8 miles to the $107,000 Route 220 intersection. HCP 4

Highway Safety and Spot 023032.00 Improvements Large culvert (#46459) located 0.73 of a mile south 2018 Whitefield Route 194 $55,000 of Jewett Lane. Large Culvert Improvements - HCP 4 PE Only

WR 34095 Bridge and Structural Repairing two wings on the south side of the Whitefield Maintenance Main Street Coopers Mills Bridge (#2175) over the Sheepscot $150,000 2018 River. Located 0.07 of mile east of Windsor Road.

Aviation 018708.01 Safety and infrastructure improvements that may Wiscasset Wiscasset Apron include apron crack sealing at the Wiscasset $169,950 2019/20 Municipal Airport Municipal Airport (IWI). Crack Sealing

Aviation 018708.02 Safety and infrastructure improvements that may Wiscasset Wiscasset Runway/Taxiway include acquisition of snow removal equipment at the $118,450 2018 Municipal Airport Wiscasset Municipal Airport (IWI). Capital Equipment Purchase

Aviation 018708.03 Safety and infrastructure improvements that may Wiscasset Wiscasset Navigation Aids/Lights include obstruction removal - Phase 2 at the $360,500 2018 Municipal Airport Wiscasset Municipal Airport (IWI). Removal Of Obstructions

Aviation Safety and infrastructure improvements that may 018708.04 include design and permitting for the reconstruction Wiscasset Wiscasset Runway/Taxiway of Runway 7-25 to include fencing and obstruction $309,000 2019/20 Municipal Airport removal - Phase 3 at the Wiscasset Municipal Airport Reconstruction (IWI).

Aviation 018708.05 Safety and infrastructure improvements that may Wiscasset Wiscasset Planning And Research include a Wildlife Hazard Assessment at the $103,000 2019/20 Municipal Airport Wiscasset Municipal Airport (IWI). Planning Studies

Aviation 018708.16 Safety and infrastructure improvements that may Airport Buildings Wiscasset Wiscasset include easement acquisition - Phase 2 at the $230,720 2018 Municipal Airport Sale Or Purchase Of Lot Or Wiscasset Municipal Airport (IWI). Building

Aviation 018708.17 Safety and infrastructure improvements that may Wiscasset include reconstruction of Runway 7-25 to include Wiscasset Runway/Taxiway $3,090,000 2019/20 Municipal Airport fencing and obstruction removal - Phase 3 at the Reconstruction Wiscasset Municipal Airport (IWI).

89

0123456789 ID/Year Municipality Scope Name Description Funding

018892.00 Highway Safety and Spot Improvements Construct northbound left turn lane at Old Bath Road 2019/20 Wiscasset Route 1 $475,000 intersection. HCP 1 Intersection Improvements

021843.00 Highway Construction/ Rehabilitation Wiscasset downtown improvements at various 2018 Wiscasset Route 1 $5,000,000 locations. HCP 1, 6 Reconstruction

022508.00 Highway Safety and Spot Improvements Construct left turn lane on southbound lane at Birch 2019/20 Wiscasset Route 1 $554,000 Point Road. HCP 1 Intersection Improvements

022509.00 Highway Safety and Spot Improvements Construct left turn lane and right turn lane at Route 2019/20 Wiscasset Route 1 $540,000 144. HCP 1 Intersection Improvements

WR 34063 Drainage Maintenance Repairing two large culverts (#900545, #900622) 2018 Wiscasset Route 1 located 0.61 of mile north and 0.45 of a mile south of $35,000 the intersection of Birchpoint Road. HCP 1

90

0123456789 Oxford Bowmantown Twp

Parmachenee Oxbow Twp Twp

Upper Lynchtown Cupsuptic Twp Twp

Lower Parkertown Cupsuptic Oxford County Twp Twp Population 57,831 Land Area (sq mi) Adamstown 2,077 Lincoln Tw p 7 Plt Bridges 37 Highway Corridor Priority Miles HCP 1 58 Richardsontown Twp HCP 2 70 Magalloway Plt HCP 3 144

Township C HCP 4 278

Upton C Byron Surplus An dover Total HCP 1-4 550 North Surplus

Roxbury Andover West Andover Grafton Surplus Twp Twp Mexico

Newry Rum ford Dixfield

Riley Hanover Twp Peru Canton Milton Twp Bethel Gilead Woodstock Batchelders Sumner Hartford Grant Twp

Mason Twp West Albany G re e n wo o d Paris Twp Oxford Stoneham Buckfield

Norway Paris

Waterford Hebron Stow Lovell

Oxford Sweden

Otisfield Fryeburg

Denmark

Brownfield

Hiram Porter Oxford ID/Year Municipality Scope Name Description Funding

Adamstown Twp, 022102.00 Lincoln Plt, Highway Paving Lower Cupsuptic Beginning at the New Hampshire state line and 2018 Route 16 $934,352 Twp, extending northeast 26.79 miles to Route 4. Light Capital Paving HCP 4 Magalloway Plt, Rangeley

WR 34912 Operational and Safety Adamstown Twp, Repairing guard rail on Route 16 In Adamstown Twp. 2018 Maintenance Route 16 $80,000 Lincoln Plt and Lincoln Plt. HCP 4

Adamstown Twp, WR 35261 Lincoln Plt, Lower Cupsuptic Bridge and Structural Milling of various bridge wearing surfaces prior to the 2018 Twp, Rangeley, Maintenance Various $30,000 2018 Rangeley area Light Capital Paving Project. Rangeley Plt, HCP 4 Sandy River Plt, Weld

WR 35518 Drainage Maintenance Ditching on Route 5 in Albany Twp. beginning at the 2018 Albany Twp Route 5 junction of Route 35 extending north to Woodsman $66,000 Loop Road. HCP 4

023352.00 Highway Paving Albany Twp, Beginning at Route 35 and extending north 12.70 2019 Route 5 $464,519 Bethel miles to Route 2. Light Capital Paving HCP 3, 4, 1

022090.00 Albany Twp, Highway Paving Beginning at W. Stoneham Road and extending 2018 Lovell, Route 5 $148,680 north 4.20 miles. Stoneham Light Capital Paving HCP 3

WR 34388 Albany Twp, Ditching on Route 120 beginning in Rumford at the Andover, Drainage Maintenance Route 5, Route 2018 junction of Isthmus Road extending to Andover Falls $87,000 Roxbury, 120 Bridge. HCP 4 Rumford

021658.00 Merrill Bridge (#3215) over the West Branch Ellis 2019/20 Andover Route 120 $1,800,000 Bridge Replacement River. Located 0.02 of a mile west of Blakie Road. HCP 4

WR 35435 Bridge and Structural Repairing bridge rail on Stoney Brook Bridge (#3971) Andover Maintenance Upton Road over Stoney Brook. Located 0.45 of a mile west of $10,000 2018 Cross Road.

023352.00 Andover, Highway Paving Mexico, Beginning 1.02 miles north of Route 2 and extending 2019 Route 120 $514,995 Roxbury, northerly 14.08 miles to Route 5. Light Capital Paving HCP 4 Rumford

91

0123456789 ID/Year Municipality Scope Name Description Funding

023352.00 Highway Paving Andover, Beginning at Route 2 and extending north 10.66 2019 Route 5 $389,904 Rumford miles to Route 120. Light Capital Paving HCP 4

018724.00 Batchelders Evans Brook Bridge (#5506) over Evans Brook. 2019/20 Route 113 $680,000 Grant Twp Bridge Deck Replacement Located 1.44 miles south of the Gilead town line. HCP 4

023352.00 Batchelders Highway Paving Beginning at the New Hampshire state line and 2019 Grant Twp, Route 113 $394,293 extending north 10.78 miles to Route 2. Gilead, Stow Light Capital Paving HCP 4

WR 34420 Batchelders Drainage Maintenance Route 113, Route Cleaning under guard rail on Route 113 in 2018 Grant Twp, $12,000 26 Batchelders Grant Twp. and Route 26 in Newry. Gilead, Newry HCP 4

Aviation 018686.01 Safety and infrastructure improvements that may Airport Buildings Bethel Regional Bethel include land and easement acquisition at the Bethel $154,500 2018 Airport Sale Or Purchase Of Lot Or Regional Airport (0B1). Building

Aviation 018686.02 Safety and infrastructure improvements that may Bethel Regional include design and construction for obstruction Bethel Navigation Aids/Lights $206,000 2019/20 Airport removal and fence relocation at the Bethel Regional Removal Of Obstructions Airport (0B1).

Bicycle-Pedestrian 021667.00 Sidewalk on west side of street, beginning at existing Trail, On-Road 2019/20 Bethel Route 26 sidewalk (0.02 of a mile north of railroad crossing) $310,000 Bicycle/Pedestrian and extending south 0.09 of a mile to Railroad Street. HCP 2 Improvements

023352.00 Highway Paving Beginning at Church Street and extending east 0.30 2019 Bethel Route 26 $11,339 of a mile Light Capital Paving HCP 2

023352.00 Highway Paving Beginning 0.03 of a mile north of Broad Street and 2019 Bethel Church Street $14,996 extending northerly 0.41 of a mile to Route 26. Light Capital Paving HCP 3

023352.00 Highway Paving Beginning at Broad Street and extending north 0.46 2019 Bethel Main Street $16,825 of a mile to Route 26. Light Capital Paving HCP 3

92

0123456789 ID/Year Municipality Scope Name Description Funding

023352.00 Highway Paving Beginning at Route 5 and extending northeast 0.33 2019 Bethel Mill Hill Road $12,070 of a mile. Light Capital Paving HCP 3

023651.00 Sunday River Bridge (#2822) over Sunday River. 2019/20 Bethel Route 2 $250,000 Bridge Wearing Surface Located 0.18 of a mile north of Martin Lane. Replacement HCP 1

023292.00 Highway Paving Beginning at the New Hampshire state line and 2018 Bethel, Gilead Route 2 $2,253,874 Ultra Thin Bonded Wearing extending east 11.96 miles. HCP 1 Surface

022104.00 Highway Paving Bethel, Beginning at Route 26 and extending north 5.08 2018 East Bethel Road $179,893 Greenwood miles. Light Capital Paving HCP 4

021876.00 Hall Bridge (#3287) over Nezinscot River. Located 2019/20 Buckfield Route 117 $2,250,000 Bridge Replacement 0.05 of a mile west of East Buckfield Road. HCP 3

022286.00 River Bridge (#5450) over the West Branch 2019/20 Buckfield Paris Hill Road Nezinscot River. Located 0.10 of a mile southwest of $300,000 Bridge Painting North Buckfield Road. HCP 6

023533.00 River Bridge (#5450) over Nezinscot River. Located 2019/20 Buckfield Paris Hill Road $200,000 Bridge Substructure 0.10 of a mile south of North Buckfield Road. Rehabilitation HCP 6

023352.00 Buckfield, Highway Paving Beginning at Route 117 and extending north 5.16 2019 Hartford, Route 140 $188,734 miles to Main Street. Sumner Light Capital Paving HCP 4

WR 34675 Ditching and replacing culverts beginning at the Buckfield, Drainage Maintenance 2018 Route 124 junction of Route 119 extending north 7.73 miles to $278,000 Hebron, Minot the junction of Route 117. HCP 4

021668.00 Byron Village Coos Bridge (#2176) over . Located 0.06 2018 Byron $1,000,000 Bridge Superstructure Road of a mile northeast of Route 17. Replacement HCP 6

93

0123456789 ID/Year Municipality Scope Name Description Funding

023537.00 Highway Construction/ Rehabilitation Beginning 0.04 of a mile north of Byron Village Road 2019/20 Byron Route 17 $250,000 and extending westerly 0.12 of a mile. HCP 3 Reconstruction

023559.00 Dugway Bridge (#2236) over Baldwin Brook. Located 2019/20 Byron Route 17 $800,000 Bridge Culvert Replacement 0.62 of a mile north of Garland Pond Road. HCP 3

022102.00 Highway Paving Byron, Township Beginning 1.91 miles south of the Rangeley Plt. town 2018 Route 17 $370,741 D, Township E line and extending southerly 10.63 miles. Light Capital Paving HCP 3

WR 34222 Bridge and Structural Replacing bridge joint seals on Frye Bridge (#2300) Frye Crossing which carries the Frye Crossing Road over the Swift 2018 Byron, Roxbury Maintenance $50,000 Road, Route 17 River in Roxbury, and Mort Bridge (#2587) which HCP 3, 4 carries Route 17 over the Swift River in Byron.

022292.00 Childs Brook #4 Bridge (#5242) over Childs Brook. 2019/20 Canton Pleasant Street $200,000 Bridge Culvert Rehabilitation Located 0.75 of a mile north of Route 140. HCP 2

022234.00 Durrells Mill Bridge (#0658) over Norton Road. 2019/20 Dixfield Common Road $700,000 Bridge Culvert Replacement Located 0.04 of a mile northwest of Main Street. HCP 6

WR 35427 Bridge and Structural Repairing bridge rail on Aunt Hannah Bridge (#5181) 2018 Dixfield, Weld Maintenance Route 142 over Aunt Hannah Brook, and on the Bowley Bridge $6,000 (#5362) over Bowley Brook. HCP 4

017280.00 Highway Construction/ Beginning at the New Hampshire state line extending Rehabilitation east 1.27 miles to 0.09 of a mile easterly of Elm 2018 Fryeburg Route 302 Street. Beginning 0.01 of a mile east of Recreational $13,710,000 Complex Road extending east 3.18 miles to Osgood HCP 1 Reconstruction Bridge (#2635) over Dead Lake Stream.

Highway Construction/ 017280.10 Rehabilitation Beginning 0.09 of a mile east of Elm Street and 2018 Fryeburg Route 302 extending easterly 1.24 miles to 0.01 of a mile $375,000 Highway Improvements - PE easterly of the Recreational Complex Road. HCP 1 Only

017912.00 Eddy Flats Bridge (#2261) over Overflow. 2018 Fryeburg Route 302 $1,680,000 Bridge Replacement Located 0.20 of a mile west of Stanley Hill Road. HCP 1

94

0123456789 ID/Year Municipality Scope Name Description Funding

Aviation 018693.01 Safety and infrastructure improvements that may Eastern Slope Fryeburg Planning And Research include a wildlife hazard assessment at the Eastern $103,000 2019/20 Regional Airport Slope Regional Airport (IZG). Planning Studies

Aviation 018693.17 Safety and infrastructure improvements that may Eastern Slope Fryeburg Airport Buildings include design and construction of a hangar at the $1,500,000 2018 Regional Airport Eastern Slope Regional Airport (IZG). New Construction

021691.00 Kimball Brook Bridge (#5573) over Kimball Brook. 2018 Fryeburg Route 113 $1,015,000 Bridge Culvert Replacement Located 0.04 of a mile north of Harbor Road. HCP 4

WR 35094 Drainage Maintenance Ditching on Fish Street beginning at the intersection 2018 Fryeburg Fish Street of Route 5 extending north 3.00 miles to the $140,000 intersection of Route 113. HCP 4

022316.00 Cambridge Bridge (#3524) over the Swift Cambridge 2019/20 Grafton Twp Route 26 River. Located 0.12 of a mile north of the northerly $400,000 Bridge Deck Replacement intersection of the Cambridge River Road. HCP 4

022104.00 Highway Paving Grafton Twp, Beginning at Route 2 and extending north 22.02 2018 Route 26 $779,771 Newry, Upton miles. Light Capital Paving HCP 1, 4

023352.00 Highway Paving Greenwood, Beginning at Route 26 and extending north 5.59 2019 Route 219 $204,462 West Paris miles. Light Capital Paving HCP 4

WR 34051 Drainage Maintenance Ditching beginning 1100 feet west of Bonney Road 2018 Hartford Route 140 $95,000 extending southerly 5.34 miles to Route 219. HCP 3

022248.00 Creek Bridge (#3582) over Creek Brook. Located 2019/20 Lovell Harbor Road $805,000 Bridge Culvert Replacement 0.14 of a mile northeast of the Fryeburg town line. HCP 4

022090.00 Highway Paving Lovell, West Stoneham Beginning at Main Street and extending northwest 2018 $65,844 Stoneham Road 1.86 miles to Adams Road. Light Capital Paving HCP 4

95

0123456789 ID/Year Municipality Scope Name Description Funding

023354.00 Highway Paving Beginning 0.07 of a mile west of Waterford Road and 2019 Lovell, Sweden Route 93 $197,059 extending westerly 4.31 miles to Route 5. Light Capital Paving HCP 4

WR 34867 Drainage Maintenance Adams Road, Ditching and culvert replacement beginning at the 2018 Lovell, Stoneham West Stoneham intersection of Slide Inn Road extending east 1.85 $70,000 Road miles to the intersection of Route 5. HCP 4

WR 35095 Drainage Maintenance Ditching and culvert replacement beginning at the 2018 Lovell, Stoneham Route 5 intersection of West Stoneham Road extending east $240,000 4.41 miles to the Albany Twp. town line. HCP 3

WR 35093 Drainage Maintenance Ditching and culvert replacement beginning at the 2018 Lovell, Sweden Knights Hill Road Sweden town line extending north 4.20 miles to the $125,000 intersection of Route 93 in Lovell. HCP 4

023547.00 Cupsuptic Bridge (#3542) over . Lower Cupsuptic 2019/20 Route 16 Located 0.59 of a mile northeast of the Adamstown $200,000 Twp Bridge Substructure Rehabilitation Twp. town line. HCP 4

023549.00 Cupsuptic Bridge (#3542) over Cupsuptic River. Lower Cupsuptic 2019/20 Route 16 Located 0.59 of a mile northeast of the Adamstown $300,000 Twp Bridge Painting Twp. town line. HCP 4

WR 35159 Bridge and Structural Repairing wearing surface, mill and fill on Brown 2018 Magalloway Plt Maintenance Route 16 Farm Bridge (#3513) over the . $40,000 Located 0.02 of a mile south of Pond Brook Road. HCP 4

018790.00 Highway Paving Beginning at the Rumford town line and extending 2019/20 Mexico Route 2 $350,000 east 0.99 of a mile. Mill And Fill HCP 1

022434.00 Highway Paving Beginning 0.08 of a mile south of Water Street and 2019/20 Mexico Route 2 $1,111,015 extending southeasterly 3.76 miles. Mill And Fill HCP 1

Highway Safety and Spot 022928.00 Improvements Beginning 0.38 of a mile south of Richards Avenue 2018 Mexico Route 2 $75,000 and extending southerly 0.08 of a mile. Slope Stabilization/Protection - HCP 1 PE Only

96

0123456789 ID/Year Municipality Scope Name Description Funding

023352.00 Highway Paving Beginning at Route 17 and extending north 2.21 2019 Mexico Highland Terrace $80,834 miles to Roxbury Road. Light Capital Paving HCP 4

023683.00 Highway Safety and Spot Improvements Closed drainage improvements beginning at the 2019/20 Mexico Highland Terrace intersection of Route 2 and Highland Terrace and $150,000 extending north 2.20 miles to Route 17. HCP 4 Drainage Improvements

WR 34089 Drainage Maintenance Repairing catch basins beginning at Richards 2018 Mexico Highland Terrace $11,000 Avenue extending north 0.74 of a mile to Pine Street. HCP 4

021700.00 Mexico, Red Bridge (#2707) over Swift River. Located at 2019/20 Route 2 $3,600,000 Rumford Bridge Replacement Rumford-Mexico town line. HCP 1

Highway Safety and Spot 022936.00 Improvements Large culvert (#900175) located 0.57 of a mile south 2018 Newry Route 26 $50,000 of Branch Road. Large Culvert Improvements - HCP 4 PE Only

023525.00 Bear Bridge (#2055) over . Located 0.07 2019/20 Newry Route 2 $200,000 Bridge Wearing Surface of a mile south of Bear River Road. Replacement HCP 1

Bicycle-Pedestrian 022691.00 Trail, On-Road Beginning at Main Street and extending north 0.32 of 2019/20 Norway Alpine Street $178,000 a mile to Skillin Avenue. Bicycle/Pedestrian HCP 6 Improvements

023352.00 Highway Paving Beginning at Watson Road and extending east 2.83 2019 Norway Route118 $103,511 miles. Light Capital Paving HCP 3, 2

023352.00 Highway Paving Beginning at Route 118 and extending north 3.27 2019 Norway Greenwood Road $119,605 miles to Morse Road. Light Capital Paving HCP 4

023639.00 Pleasant Street Bridge (#2677) over 2019/20 Norway Route 117 Pennesseewassee Stream. Located 0.06 of a mile $500,000 Bridge Deck Replacement southwest of Pleasant Street. HCP 2

97

0123456789 ID/Year Municipality Scope Name Description Funding

022438.00 Highway Paving Beginning 0.05 of a mile north of Main Street and 2019/20 Norway, Paris Route 26 $896,130 extending northeasterly 1.90 miles to Porter Street. Mill And Fill HCP 2

WR 34460 Ditching and replacing six culverts on Route 121 Drainage Maintenance beginning at the intersection of Bolster's Mills Road 2018 Otisfield Route 121 $75,000 extending north 5.00 miles to the Otisfield-Oxford HCP 4 town line in Otisfield.

022090.00 Highway Paving Beginning at Bolsters Mills Road and extending north 2018 Otisfield, Oxford Route 121 $176,292 4.98 miles. Light Capital Paving HCP 4

WR 34705 Ditching beginning at the intersection of Tower Road Otisfield, Drainage Maintenance 2018 Route 121 in Raymond and extending 7.00 miles to the $85,000 Raymond Otisfield-Casco town line. HCP 4

Aviation 018702.01 Safety and infrastructure improvements that may Oxford County Oxford Runway/Taxiway include Phase 3 Boundary Fencing at the Oxford $206,000 2018 Regional Airport County Regional Airport (81B). New Construction

020874.00 Highway Paving Beginning 0.60 of a mile north of the Mechanic Falls 2018 Oxford Route 26 $984,000 town line and extending northerly 2.26 miles. 1 1/4" Overlay HCP 2

022090.00 Highway Paving West Poland Beginning at Route 121 and extending south 1.05 2018 Oxford $37,170 Road miles. Light Capital Paving HCP 4

022506.00 Highway Safety and Spot Improvements Located at the southerly intersection of Route 26 and 2019/20 Oxford Route 26 $725,000 Route 121. HCP 2 Intersection Improvements

022952.00 Highway Safety and Spot Improvements Located at the intersection of Route 26 and 2019/20 Oxford Route 26 $460,000 Skeetfield Road. HCP 2 Intersection Improvements

WR 35214 Mill and fill wearing surface and approaches, Bridge and Structural repairing all headers along joints, and repairing joints 2018 Oxford Maintenance Route 26 on Little Androscoggin Bridge (#2461) over the Little $125,000 Androscoggin River. Located 0.07 of a mile north of HCP 2 Oxford Street.

98

0123456789 ID/Year Municipality Scope Name Description Funding

022956.00 Highway Safety and Spot Beginning 0.01 of a mile north of Maple Street Improvements extending north 0.34 of a mile. Beginning 0.03 of a 2019/20 Paris Route 26 mile north of Oxford Street extending north 0.14 of a $500,000 mile. Beginning at Penley Street extending north HCP 3, 2, 4 Drainage Improvements 0.34 of a mile.

WR 35725 Drainage Maintenance Replacing eleven catch basins including connecting 2018 Paris High Street pipes in various locations on High Street in South $53,000 Paris. HCP 4

022448.00 Highway Paving Paris, West Beginning 0.02 of a mile south of Porter Street and 2019/20 Route 26 $2,379,331 Paris extending northerly 8.79 miles. Hot In Place Recycled HCP 2

023352.00 Highway Paving Paris, West Beginning at Route 26 and extending north 7.62 2019 High Street $278,712 Paris miles to Route 26. Light Capital Paving HCP 4

021740.00 Mary Turner Road Bridge (#0781) over Spears Mary Turner 2018 Peru Stream. Located 0.07 of a mile northeast of Dickvale $100,000 Road Bridge Deck Replacement Road. HCP 6

WR 35432 Bridge and Structural Dickvale Road, Bridge rail repairs on Dickvale Bridge (#5603) and Peru Maintenance $20,000 2018 Ridge Road Gowell Bridge (#5432) over Spears Stream.

023310.00 Highway Paving Beginning at the New Hampshire state line extending 2018 Porter Route 25 $1,198,600 Ultra Thin Bonded Wearing east 5.68 miles. HCP 2 Surface

023352.00 Highway Paving Frye Crossover Beginning at Route 120 and extending northeast 2019 Roxbury $12,070 Road 0.33 of a mile to Route 17. Light Capital Paving HCP 4

Highway Construction/ 023743.00 Rehabilitation Large culvert (#202713) located 0.03 of a mile north 2018 Roxbury Route 120 $60,000 of Frye Crossover Road. Large Culvert Replacement - HCP 4 PE Only

023745.00 Highway Safety and Spot Beginning 0.29 of a mile south of Main Street and Improvements extending southerly 0.49 of a mile. Continuing 0.43 of 2019/20 Roxbury Route 120 a mile south of Mine Notch Road and extending $100,000 southerly 0.54 of a mile. Continuing at Horseshoe HCP 4 Shoulder Improvements Valley Road and extending east 1.80 miles.

99

0123456789 ID/Year Municipality Scope Name Description Funding

WR 34000 Drainage Maintenance Installing large culvert (#122600) located 0.56 of a 2018 Roxbury Route 120 $65,000 mile west of Horseshoe Valley Road. HCP 4

WR 36168 Operational and Safety Frye Crossover Replace cable guard rail on approaches to Frye 2018 Roxbury Maintenance $9,000 Road Bridge. HCP 4

022460.00 Highway Paving Beginning 0.02 of a mile south of Free Street and 2019/20 Rumford Route 2 $232,631 extending northerly 0.56 of a mile. Mill And Fill HCP 1

022621.00 South Rumford High Bridge (#5188) over Androscoggin River. 2019/20 Rumford $4,215,000 Bridge Replacement Road Located 0.11 of a mile east of Route 2. HCP 4

023352.00 Highway Paving Beginning at Route 2 and extending north 4.91 miles 2019 Rumford Andover Road $179,590 to Route 5. Light Capital Paving HCP 4

023352.00 Highway Paving Beginning 0.19 of a mile west of Mountain View 2019 Rumford Wyman Hill Road Road and extending northerly 1.19 miles to Route $43,526 Light Capital Paving 108. HCP 4

WR 35089 Bridge and Structural Replacing sidewalk lighting fixtures and wiring on the Chisholm Park Bridge (#2990) over the Rumford Maintenance Portland Street $278,000 2018 Androscoggin River. Located 0.06 of a mile west of River Street.

017517.06 Maintenance

2018 Sumner Route 140 Guard rail upgrades on Route 140. $35,000 Guard Rail Installation And HCP 4 Replacement

021704.00 Heald Bridge (#0673) over West Branch of Nezinscot 2018 Sumner Redding Road River. Located 0.45 of a mile west of Black Mountain $1,100,000 Bridge Replacement Road. HCP 6

021705.00 Fields Bridge (#0690) over the East Branch 2018 Sumner Gammon Road Nezinscot River. Located at the Sumner - Hartford $1,200,000 Bridge Replacement town line. HCP 6

100

0123456789 ID/Year Municipality Scope Name Description Funding

022360.00 West Sumner Meadow Bridge (#5843) over the West 2019/20 Sumner Bridge Substructure Main Street Branch Nezinscot River. Located 0.25 of a mile $200,000 Rehabilitation northeast of Front Street. HCP 3

WR 35348 Operational and Safety Replace damaged guard rail beginning at the 2018 Sumner Maintenance Route 140 intersection of Route 219 extending west $10,000 approximately 175 feet. HCP 4

021838.00 Highway Safety and Spot Improvements Large culvert (#940780) located 0.25 of a mile west 2019/20 Waterford Route 118 $330,000 of Hunts Corner Road. HCP 3 Large Culvert Replacement

022090.00 Highway Paving Beginning at Route 35 and extending north 2.98 2018 Waterford Route 37 $105,492 miles to Route 118. Light Capital Paving HCP 4

022372.00 Horrs Bridge (#5192) over Crooked River. Located 2019/20 Waterford Route 35 0.34 of a mile southeast of the Albany Twp. town $600,000 Bridge Deck Replacement line. HCP 3

WR 34411 Drainage Maintenance Replacing cross culvert (#103226) on Route 35 2018 Waterford Route 35 located 0.10 of a mile north of the Bridgton-Waterford $45,000 town line. HCP 4

WR 34866 Drainage Maintenance Ditching and culvert replacement beginning at the 2018 Waterford Route 37 Waterford town line extending east 6.40 miles to the $90,000 intersection of Route 118. HCP 4

WR 35163 Bridge and Structural Concrete wearing surface replacement on Maxfield 2018 Waterford Maintenance Route 37 Bridge (#0771) over Kedar Brook. Located 0.02 of a $65,000 mile north of Valley Road. HCP 4

WR 35192 Operational and Safety Replace approach rail and update bridge 2018 Waterford Maintenance Route 37 attachments on Maxfield Bridge (#0771) over Kedar $16,000 Brook. Located 0.02 of a mile north of Valley Road. HCP 4

021758.00 Penley Avenue Bridge (#3460) over the Little 2019/20 West Paris Bridge Wearing Surface Route 219 Androscoggin River. Located 1.03 miles south of the $75,000 Replacement Lower River Road. HCP 4

101

0123456789 ID/Year Municipality Scope Name Description Funding

WR 31235 Bridge and Structural Repairing bridge curb, sidewalk and retaining walls 2018 West Paris Maintenance Route 219 on the Trap Corner Bridge (#3575) over Andrews $140,000 Brook. Located 0.06 of a mile west of Route 26. HCP 4

Highway Construction/ 018767.00 Rehabilitation Beginning 0.06 of a mile east of Rumford Avenue 2018 Woodstock Route 26 $365,000 and extending westerly 2.51 miles. Highway Improvements - PE HCP 2 Only

022104.00 Highway Paving Beginning 0.74 of a mile west of Route 232 and 2018 Woodstock Route 26 $90,300 extending west 2.55 miles. Light Capital Paving HCP 2

102

0123456789 T8 R8 T8 R7 T8 R6 Penobscot WELS WELS WELS

T7 R8 T7 R7 T7 R6 WELS WELS WELS

T6 R8 T6 R7 T6 R6 WELS WELS WELS

Penobscot County T5 R8 T5 R7 Mount Population 153,920 WELS WELS Chase Land Area (sq mi) 3,397 T4 R7 Bridges 432 T4 R8 Patten WELS WELS Highway Corridor Priority Miles

HCP 1 275 T3 R7 Stacyville T3 R8 WELS HCP 2 143 WELS

HCP 3 307 Soldiertown T2 R8 Herseytown Twp T2 HCP 4 444 WELS Twp R7 WELS

T1 R8 Grindstone T1 R6 Total HCP 1-4 1,1 69 WELS Twp WELS

T3 Indian Millinocket Purchase T4 Indian Twp Purchase Medway Twp TA R7 Hopkins Academy WELS Drew Plt Grant Twp Kin gman Mattawamkeag Long A Twp Twp T2 R9 Woodville Prentiss T3 R9 Twp T7 NWP Webster NWP R3 NBPP Plt Winn Chester T2 R8 Carroll Springfield Plt Seboeis NWP Plt Lee Lincoln Mattamiscontis Twp Maxfield Lakeville Pu ka kon T3 R1 Twp Enfield NBPP

Howland Lowell Burlington Edinburg Lagrange Grand Summit Falls Twp Argyle Twp Bradford Twp Charleston Greenbush Garland Greenfield Dexter Alton Twp Hudson Corinth Milford Exeter Corinna Old Town

Kenduskeag

Glenburn Orono Bradley Penobscot Stetson Levant Newport Bangor Eddington Hermon Carmel Clifton Etna Bre wer

Plymouth Holden Ham pden Newburgh Dixmont Orrington Penobscot ID/Year Municipality Scope Name Description Funding

Alton, Argyle Twp, Edinburg, 023681.00 Howland, Highway Paving Mattamiscontis Beginning at the Medway town line extending south 2019/20 Twp, Medway, Interstate 95 SB $7,928,000 49.55 miles. Old Town, Ultra Thin Bonded Wearing HCP 1 Orono, T2 R8 Surface NWP, T2 R9 NWP

020855.00 Highway Paving Alton, Bangor, Beginning 5.78 miles north of the Hampden town line 2018 Old Town, Interstate 95 NB and extending northerly 13.80 miles to the Argyle $2,208,000 Orono, Veazie Ultra Thin Bonded Wearing town line. HCP 1 Surface

023300.00 Highway Paving Beginning 0.11 of a mile southeast of Route 6 and 2018 Alton, Lagrange Route 16 $1,235,420 extending southeasterly 6.37 miles. 3/4" Overlay HCP 2

021687.00 Hemlock Stream Bridge (#3735) over Hemlock 2018 Argyle Twp Route 116 $115,000 Bridge Improvements - PE Only Stream. Located 2.22 miles north of Argyle Road. HCP 4

022402.00 Argyle Twp, Highway Paving Beginning at the Alton town line and extending north 2019/20 Edinburg, Interstate 95 NB $6,072,000 15.18 miles. Howland Mill And Fill HCP 1

WR 34870 Argyle Twp, Drainage Maintenance Clean guard rails and wing walls. Ditch problem area 2018 Route 116 $39,000 Howland on Route 116. HCP 4

Highway Safety and Spot 018595.10 Improvements Design for diverging diamond interchange on Hogan Road/ Interstate 95 Exit #187 and Hogan Road/ I-95 2018 Bangor Hogan Road $775,000 Bridge (#5823) over Interstate 95. Located 0.26 of a Intersection Improvements - PE HCP 2 mile north of Haskell Road. Only

Aviation Safety and infrastructure improvements that may 018709.01 Bangor include design and reconstruction of Taxiway "A" Bangor Runway/Taxiway International south (Taxiway "K" to Runway 33) and light bar $10,557,500 2018 Airport rehabilitation at the Bangor International Airport Reconstruction (BGR).

Aviation Safety and infrastructure improvements that may 018709.02 Bangor include design and reconstruction of Taxiway "A" Bangor Runway/Taxiway International north, light bar rehabilitation and new regulators and $2,472,000 2019/20 Airport Airport Light Control and Monitoring System Reconstruction (ALCMS) at the Bangor International Airport (BGR).

Aviation Safety and infrastructure improvements that may 018709.03 Bangor include design and reconstruction of Taxiway "A" Bangor Runway/Taxiway International $3,090,000 2019/20 from Taxiway "M" to north hold apron at the Bangor Airport Reconstruction International Airport (BGR).

103

0123456789 ID/Year Municipality Scope Name Description Funding

018722.00 Ohio Street/ I-95 Bridge (#5790) over Interstate 95. 2019/20 Bangor Ohio Street $6,207,213 Bridge Replacement Located 0.02 of a mile southeast of Sixteenth Street. HCP 3

020720.18 Public Transportation Urban Transit FTA Section 5307 for ADA Operating - Community Bangor $125,000 2018 Operating Connector. Operating Assistance

020720.19 Public Transportation Urban Transit FTA Section 5307 for ADA Operating - Community Bangor $125,000 2019 Operating Connector. Operating Assistance

020720.20 Public Transportation Transit American with Disabilities Act (ADA) Urban Transit Operating Assistance for Bangor, Community Bangor $125,000 2020 Operating Connector, Federal Transit Administration § 5307 for Operating Assistance urbanized area transit.

020811.00 Highway Safety and Spot Improvements Extend Interstate 95 southbound Exit #185 on-ramp 2018 Bangor Interstate 95 SB $450,000 acceleration lane. HCP 1 Ramp Improvements

020856.00 Highway Paving Beginning at Johnson Street and extending south 2018 Bangor Maine Avenue $657,828 0.57 of a mile to Venture Way. BACTS Sponsored. Mill And Fill HCP 3

020857.00 Highway Paving Beginning at Venture Way and extending south 0.40 2018 Bangor Maine Avenue $577,410 of a mile to Hammond Street. BACTS Sponsored. Mill And Fill HCP 3

020895.00 Highway Safety and Spot Improvements Located at the intersection of Ohio Street and 2018 Bangor Ohio Street $210,938 Fourteenth Street. BACTS Sponsored. HCP 4 Traffic Signals

020896.00 Highway Safety and Spot Improvements Located at the intersection of Route 222 and 2018 Bangor Route 222 $240,865 Fourteenth Street. BACTS Sponsored. HCP 2 Traffic Signals

021661.00 Bicycle-Pedestrian Beginning at Davis Road and extending south 0.38 of 2018 Bangor Trail, On-Road Finson Road $151,000 a mile. HCP 6 New Construction

104

0123456789 ID/Year Municipality Scope Name Description Funding

Highway Safety and Spot 021663.00 Roadway and intersection safety improvements on Improvements Broadway. Beginning at Center Street and extending 2018 Bangor Broadway 0.14 of a mile to Alden Street. Including intersection $100,000 Highway Improvements - PE improvments at north and southbound Interstate 95 HCP 2 Only ramps.

021674.00 Six Mile Falls Bridge (#2771) over Kenduskeag 2018 Bangor Bridge Wearing Surface Route 15 Stream. Located 0.10 of a mile northwest of Route $200,000 Replacement 221. HCP 2

Bicycle-Pedestrian 022208.00 Bicycle - Beginning at the end of Sylvan Road and extending Bangor Trail, Off-Road $550,000 2019/20 Pedestrian Trail west 0.39 of a mile to Stillwater Avenue. New Construction

022210.00 Bicycle-Pedestrian Beginning at Vermont Avenue and extending 2019/20 Bangor Urban Highways Union Street $399,300 northwest 0.79 of a mile to Griffin Road. HCP 3, 2 Sidewalk Construction

022276.00 I-95/ Broadway Bridge (#5789) over Route 15. 2018 Bangor Interstate 95 Located 0.06 of a mile west off Exit #187 Interstate $300,000 Bridge Improvements - PE Only 95 northbound. HCP 1

022694.00 Highway Safety and Spot Improvements Construct parallel acceleration lane at Broadway 2018 Bangor Interstate 95 $690,000 northbound on-ramp. HCP 1 Safety Improvements

022757.18 Public Transportation Urban Transit FTA Section 5307 for Capital / Preventive Bangor $387,500 2018 Capital Maintenance - Community Connector. Capital-Eligible Maintenance

022757.19 Public Transportation Urban Transit FTA Section 5307 for Capital / Preventive Bangor $387,500 2019/20 Capital Maintenance - Community Connector. Capital-Eligible Maintenance

022757.20 Public Transportation Transit Capital Assistance for Bangor, Community Urban Transit Bangor Connector, Federal Transit Administration § 5307 for $387,500 2019/20 Capital Capital-Eligible Maintenance urbanized area transit, Fiscal Year 2019.

022761.18 Public Transportation Urban Transit FTA Section 5307 for Operating Assistance - Bangor $1,544,000 2018 Operating Community Connector. Operating Assistance

105

0123456789 ID/Year Municipality Scope Name Description Funding

022761.19 Public Transportation Urban Transit FTA Section 5307 for Operating Assistance - Bangor $1,544,000 2019 Operating Community Connector. Operating Assistance

022761.20 Public Transportation Urban Transit FTA Section 5307 for Operating Assistance - Bangor $1,544,000 2020 Operating Community Connector. Operating Assistance

022769.18 Public Transportation Urban Transit FTA Section 5339 Capital Assistance SMALL Bangor $117,500 2018 Capital URBAN. Capital Equipment Purchase

022769.19 Public Transportation Transit Capital Assistance for the Bangor, Small Urban Transit UrbanTransit Agencies , Federal Transit Bangor $117,500 2019/20 Capital Administration § 5339 for urbanized area transit, Capital Equipment Purchase Fiscal Year 2019.

022769.20 Public Transportation Transit Capital Assistance for the Bangor, Small Urban Transit UrbanTransit Agencies , Federal Transit Bangor $117,500 2019/20 Capital Administration § 5339 for urbanized area transit, Capital Equipment Purchase Fiscal Year 2020.

022827.00 Highway Safety and Spot Improvements Located at the intersection of Union Street and Main 2019/20 Bangor Main Street $257,330 Street. BACTS Sponsored. HCP 2 Intersection Improvements

023342.00 Public Transportation Bangor Area Comprehensive Transportation System Urban Transit (BACTS), Federal Transit Administration § 5303 for Bangor $96,522 2018 Planning metropolitan planning Fiscal Year 2018. Funds are Administrative Assistance transferred to FHWA.

023342.19 Public Transportation Bangor Area Comprehensive Transportation System Urban Transit (BACTS), Federal Transit Administration § 5303 for Bangor $96,522 2019 Planning metropolitan planning Fiscal Year 2019. Funds are Administrative Assistance transferred to FHWA.

023342.20 Public Transportation Bangor Area Comprehensive Transportation System Urban Transit (BACTS), Federal Transit Administration § 5303 for Bangor $96,522 2020 Planning metropolitan planning Fiscal Year 2020. Funds are Administrative Assistance transferred to FHWA.

023420.00 Public Transportation Urban Transit City of Bangor, Community Connector, carryover Bangor $769,200 2018 Capital balance FTA funds for capital procurement. Capital Equipment Purchase

106

0123456789 ID/Year Municipality Scope Name Description Funding

023517.00 Highway Paving Beginning at Haskell Road and extending south 0.43 2019/20 Bangor Hogan Road $582,705 of a mile to Mt. Hope Avenue. BACTS Sponsored. Mill And Fill HCP 2

023519.00 Highway Paving Beginning at the Hampden town line and extending 2019/20 Bangor Main Street north 0.66 of a mile to Dutton Street. BACTS $831,588 Mill And Fill Sponsored. HCP 2

Highway Construction/ 023521.00 Rehabilitation Beginning at Hancock Street and extending 2018 Bangor State Street northeasterly 0.97 of a mile to Hogan Road. BACTS $69,117 Enhanced Project Scoping - PE Sponsored. HCP 2, 3 Only

023573.00 Highway Safety and Spot Improvements Located at the intersection of State Street and Forest 2019/20 Bangor State Street $205,593 Avenue. BACTS Sponsored. HCP 2 Intersection Improvements

WR 34234 Bridge and Structural Breast wall seat repair to US 202/ Perry Road Bridge 2018 Bangor Maintenance Route 202 (#6081) over Perry Road. Located 0.36 of a mile $38,000 northeast of Mecaw Road. HCP 2

021713.00 Bangor, Brewer Interstate 395 Interstate 395 Bridge Study. $250,000 2018 Bridge Improvements - PE Only

022278.00 Veterans Remembrance Bridge (#1558) over the 2019/20 Bangor, Brewer Interstate 395 . Located at the Bangor-Brewer city $1,500,000 Bridge Rehabilitation line. HCP 1

Bangor, Carmel, Etna, Hampden, 021791.00 Hermon, Maintenance Newburgh, Beginning in Newport and extending north 39.98 2018 Interstate 95 NB $100,000 Newport, Old miles to the Old Town city line. Signing HCP 1 Town, Orono, Plymouth, Veazie

023388.00 Highway Paving Bangor, Beginning 0.37 of a mile southeast of Wagner Road 2018 Glenburn, Route 222 $1,036,789 and extending southeasterly 7.68 miles. Hermon, Levant Highway Cyclical Pavement HCP 3 Resurfacing

WR 32533 Bangor, Ditching, repairing and/or replacing culverts Drainage Maintenance Union Street, 2018 Glenburn, beginning at the Davis Road in Bangor to the $65,000 Route 222 Hermon, Levant intersection of Avenue Road in Levant. HCP 3

107

0123456789 ID/Year Municipality Scope Name Description Funding

WR 34182 Bridge and Structural Upgrading bridge rail on three bridges: US 202/ Perry Bangor, 2018 Maintenance Route 202 Road Bridge (#6081), Route 202/ MCRR Bridge $200,000 Hampden (#6080) and US 202/ I-395 Bridge (#6082). HCP 2

Benedicta Twp, Crystal, Dyer Brook, 022470.00 Herseytown Twp, Highway Paving Houlton, Island Beginning at the T1 R6 WELS- Herseytown Twp. 2019/20 Interstate 95 NB $7,833,600 Falls, Ludlow, Ultra Thin Bonded Wearing town line and extending north 48.89 miles. HCP 1 New Limerick, Surface Oakfield, Sherman, Smyrna

022110.00 Highway Paving Bradford, Milo, Beginning at Route 221 in Bradford extending to 2018 Route 11 $434,712 Orneville Twp Route 6 in Milo. Light Capital Paving HCP 4

Bicycle-Pedestrian 018858.00 Beginning at Wilson Street and extending northeast Riverwalk Trail Brewer Trail, Off-Road 0.40 of a mile to the Penobscot Bridge, including $1,461,000 2018 Phase 2 pedestrian spot improvements in the downtown area. New Construction

020859.00 Highway Paving Beginning at Thompson Street and extending 2018 Brewer Route 1A southeast 0.66 of a mile to Arista Drive. BACTS $468,320 Mill And Fill Sponsored. HCP 2

021928.04 Highway Safety and Spot Improvements Municipal Partnership Initiative Program. Beginning 2018 Brewer Mill Street at the Orrington town line and extending north 0.47 of $210,000 a mile. HCP 4 Highway Rehabilitation

022408.00 Highway Paving Beginning 0.13 of a mile south of Spark Road and extending southeasterly 0.09 of a mile. Continuing 2018 Brewer Route 1A $377,903 from 0.02 of a mile south of Arista Drive and Mill And Fill HCP 2, 1 extending southeasterly 0.57 of a mile.

022410.00 Highway Paving Beginning 0.06 of a mile north of Elm Street and 2019/20 Brewer Route 15 extending northerly 1.08 miles to Abbott Street. $650,000 Mill And Fill BACTS Sponsored. HCP 2

Highway Safety and Spot 022833.00 Improvements 2018 Brewer Route 15 Located 0.13 of a mile north of Abbott Street. $75,000 Slope Stabilization/Protection - HCP 1 PE Only

023575.00 Highway Safety and Spot Improvements Located at the intersection of Wilson Street and 2019/20 Brewer Wilson Street $91,147 Dirigo Drive. BACTS Sponsored. HCP 2 Intersection Improvements

108

0123456789 ID/Year Municipality Scope Name Description Funding

Highway Construction/ Beginning 0.25 of a mile west of Interstate 395 with 018915.00 Brewer, Rehabilitation Interstate 395, Route 1A, roughly paralleling the Brewer-Holden Eddington, Route 9 $8,750,000 2018 town line, extending 6.00 miles to Route 9 west of Holden Connector Highway Improvements - PE Chemo Pond Road (in the vicinity of Lois Lane). Only

023368.00 Highway Paving Burlington, Beginning at the Grand Falls Twp. town line and 2019 Route 188 $687,793 Enfield, Lowell extending north 12.99 miles to Route 155. Light Capital Paving HCP 4

WR 31958 Burlington, Drainage Maintenance Ditching in various locations along Route 188 in 2018 Route 188 $146,000 Enfield Enfield, Lowell, and Burlington. HCP 4

WR 34862 Drainage Maintenance Ditching and replacing cross culverts along Route 69 2018 Carmel, Etna Route 69 $141,000 between Route 143 and the I-95 overpass. HCP 4

WR 34576 Carmel, Etna, Drainage Maintenance Ditching and replacing cross culverts along Route 69 2018 Route 69 $89,000 Plymouth between Route 7 in Plymouth to Route 143 in Etna. HCP 4

Highway Safety and Spot 023581.00 Improvements Large culvert (#979262) located 1.38 miles north of 2018 Carroll Plt Route 6 $55,000 the Kossuth Twp. town line. Large Culvert Replacement - HCP 3 PE Only

WR 34861 Drainage Maintenance Repairing cross culvert (#1000460) located at the 2018 Carroll Plt Route 6 $27,000 intersection of the Brown Road. HCP 3

WR 33090 Bridge and Structural Repair Medunkeunk Bridge (#5907) over 2018 Chester Maintenance Route 116 Medunkeunk Stream. Located 0.05 of a mile $70,000 northeast of Downs Road. HCP 3

022110.00 Highway Paving Beginning at Williams Road and extending northeast 2018 Corinna Nokomis Road $92,394 2.61 miles to St. Albans Road. Light Capital Paving HCP 4

022110.00 Highway Paving Corinna, Beginning at Route 7 in Newport extending to the 2018 Williams Road $96,642 Newport Nokomis Road. Light Capital Paving HCP 4

109

0123456789 ID/Year Municipality Scope Name Description Funding

023306.00 Highway Paving Corinna, Beginning 0.02 of a mile northeast of Route 2 and 2018 Route 7 $1,474,208 Newport Ultra Thin Bonded Wearing extending northerly 6.66 miles. HCP 2 Surface

022110.00 Corinna, Highway Paving Beginning at Route 7 in Corinna extending to Route 2018 Newport, Route 222 $254,172 143 in Stetson. Stetson Light Capital Paving HCP 3

022110.00 Corinth, Exeter, Highway Paving Beginning at Exeter Road and extending 12.56 miles 2018 Kenduskeag, Avenue Road $444,624 to Route 15. Levant Light Capital Paving HCP 4

Crystal, Houlton, 021765.00 Island Falls, Ludlow, 2018 Interstate 95 Medway, Interstate 95 bridges from Medway to Houlton. $1,400,000 Bridge Protective Coating Bridges HCP 1, 6, 4, Oakfield, 3 Sherman, Smyrna

022116.00 Danforth, Prentiss Twp T7 Highway Paving Beginning 0.13 of a mile south of T8 R3 NBPP and 2018 R3 NBPP, T8 Route 169 $586,428 extending north 12.42 miles to Route 1. R3 NBPP, T8 Light Capital Paving HCP 4 R4 NBPP

Aviation 018690.01 Safety and infrastructure improvements that may Dexter Regional Dexter Planning And Research include an obstruction analysis at the Dexter $154,500 2018 Airport Regional Airport (1B0). Planning Studies

Aviation 018690.02 Safety and infrastructure improvements that may Dexter Regional Dexter Planning And Research include an environmental assessment for obstruction $128,750 2018 Airport removal at the Dexter Regional Airport (1B0). Planning Studies

Aviation 018690.03 Safety and infrastructure improvements that may Airport Buildings Dexter Regional Dexter include easement acquisition at the Dexter Regional $77,250 2019/20 Airport Sale Or Purchase Of Lot Or Airport (1B0). Building

Aviation 018690.04 Safety and infrastructure improvements that may Dexter Regional Dexter Navigation Aids/Lights include obstruction removal at the Dexter Regional $154,500 2019/20 Airport Airport (1B0). Removal Of Obstructions

023553.00 Highway Paving Dexter, Beginning 0.46 of a mile north of Crockett Road and 2019/20 Route 23 $2,220,983 Sangerville extending northerly 4.74 miles. Cold-In-Place Recycle HCP 2

110

0123456789 ID/Year Municipality Scope Name Description Funding

022110.00 Dixmont, Highway Paving Beginning at Route 9 in Dixmont and extending to 2018 Hampden, Kennebec Road $540,204 Route 1A in Hampden. Newburgh Light Capital Paving HCP 4

022304.00 Mattawamkeag River Bridge (#5105) over 2018 Drew Plt Route 171 Mattawamkeag River. Located 0.14 of a mile north of $215,000 Bridge Improvements - PE Only Eight Road. HCP 4

WR 34821 Replacing culverts beginning 0.16 of a mile south of Drew Plt, Drainage Maintenance the Prentiss Twp.-Drew Plt. town line and extending 2018 Prentiss Twp T7 Route 171 $78,000 northerly 6.35 miles to the intersection of the Eight R3 NBPP HCP 4 Road.

018818.00 Highway Safety and Spot Improvements Large culvert (#46678) located 0.53 of a mile north of 2018 Eddington Route 46 $605,000 Sweets Hill Road. HCP 2 Large Culvert Replacement

021782.00 Highway Safety and Spot Improvements Large culvert (#46776) located 0.22 of a mile north of 2019/20 Eddington Route 46 $720,000 Hatcase Pond Road. HCP 2 Large Culvert Replacement

023368.00 Highway Paving Beginning at Route 2 and extending north 12.45 2019 Enfield, Lincoln Route 155 $659,201 miles to Route 6. Light Capital Paving HCP 4

WR 32833 Enfield, Drainage Maintenance Removal of excess shoulder material on the Caribou 2018 Caribou Road $73,000 Passadumkeag Road. HCP 4

022110.00 Highway Paving Beginning at Route 2 in Etna extending to Route 222 2018 Etna, Stetson Route 143 $197,886 in Stetson. Light Capital Paving HCP 4

022110.00 Highway Paving Beginning at Exeter Road and extending north 3.74 2018 Exeter, Garland Garland Road $132,396 miles to Cornith Road. Light Capital Paving HCP 4

022110.00 Highway Paving Beginning at Village Road and extending 5.62 miles 2018 Exeter, Stetson Stetson Road $198,948 to Exeter Road. Light Capital Paving HCP 4

111

0123456789 ID/Year Municipality Scope Name Description Funding

021727.00 Boom Bridge (#3587) over Beach Bridge Brook. 2019/20 Greenbush Route 2 $2,600,000 Bridge Replacement Located 2.43 miles north of Milford town line. HCP 3

011577.00 Highway Construction/ Rehabilitation Beginning at Western Avenue and extending north 2019/20 Hampden Route 1A $4,868,879 1.73 miles. BACTS Sponsored HCP 2 Reconstruction

018959.00 Twin Bridge (#5315) over the West Branch 2019/20 Hampden Route 69 Souadabscook Stream. Located 0.04 of a mile north $1,000,000 Bridge Culvert Replacement of Meadow Road. HCP 3

019401.00 Bicycle-Pedestrian Beginning at Mayo Road and extending southeast 2018 Hampden Trail, On-Road Route 202 $191,680 0.15 of a mile. HCP 3 New Construction

021673.00 I-95 SB/ Emerson Mills Road Bridge (#1430) over 2019/20 Hampden Interstate 95 SB B&A Railroad and Emerson Mills Road. Located $5,800,000 Bridge Replacement 0.12 of a mile south of Old Emerson Mill Road. HCP 1

021673.10 I-95 NB/Emerson Mills Road Bridge (#5969) over 2019/20 Hampden Interstate 95 NB Emerson Mills Road. Located 0.29 of a mile west of $5,800,000 Bridge Replacement Exit 180. HCP 1

021692.00 Grist Mill Bridge (#2334) over Souadabscook 2018 Hampden Route 1A Stream. Located 0.21 of a mile northeast of Elm $2,640,000 Bridge Replacement Street. HCP 2

021728.00 Souadabscook Center NB Bridge (#5950) over the 2019/20 Hampden Interstate 95 NB Souadabscook Stream. Located 2.05 miles west of $3,350,000 Bridge Replacement Emerson Mill Road. HCP 1

021728.10 Souadabscook Center SB Bridge (#1432) over 2019/20 Hampden Interstate 95 SB Souadabscook Stream. Located 1.88 miles east of $3,900,000 Bridge Replacement the Hermon town line. HCP 1

021729.00 Souadabscook East NB Bridge (#5949) over the 2019/20 Hampden Interstate 95 NB Souadabscook Stream. Located 1.29 miles west of $3,350,000 Bridge Replacement Emerson Mill Road. HCP 1

112

0123456789 ID/Year Municipality Scope Name Description Funding

021729.10 Souadabscook East SB Bridge (#1431) over 2019/20 Hampden Interstate 95 SB Souadabscook Stream. Located 2.63 miles east of $3,900,000 Bridge Replacement the Hermon town line. HCP 1

021730.00 Souadabscook West NB Bridge (#5951) over the 2019/20 Hampden Interstate 95 NB Souadabscook Stream. Located 1.62 miles east of $3,100,000 Bridge Replacement Shaw Hill Road. HCP 1

021730.10 Souadabscook West SB Bridge (#1433) over 2019/20 Hampden Interstate 95 SB Souadabscook Stream. Located 1.38 of a mile east $3,900,000 Bridge Replacement of the Hermon town line. HCP 1

023569.00 Highway Paving Beginning 0.05 of a mile east of Stoney Brook Road 2019/20 Hampden Route 202 and extending northeasterly 2.39 miles to Mecaw $709,786 Mill And Fill Road. HCP 2

023593.00 Highway Paving Beginning 0.02 of a mile west of Route 1A and 2019/20 Hampden Route 9 $214,290 extending westerly 0.47 of a mile. Mill And Fill HCP 2, 3

WR 34712 Drainage Maintenance 2018 Hampden Route 1A Repair catch basins along Route 1A in Hampden. $29,000

HCP 2

WR 35388 Drainage Maintenance Replacing five cross culverts, ditching and cutting 2018 Hampden Kennebec Road brush on the Kennebec Road in Hampden between $90,000 the Mayo Road and the Carmel Road north. HCP 4

023318.00 Highway Paving Beginning 0.04 of a mile southeast of Autocar Lane Hampden, 2018 Coldbrook Road and extending southeasterly 2.53 miles ending at $341,546 Hermon Highway Cyclical Pavement Route 202. HCP 3 Resurfacing

022581.00 Highway Construction/ Hampden, Rehabilitation Beginning at Western Avenue in Newburgh and 2019/20 Route 69 $507,500 Newburgh extending south 3.87 miles. HCP 3 PMRAP DOT Pugmill

022581.10 Highway Construction/ Hampden, Rehabilitation Beginning at Western Avenue in Newburgh and 2019/20 Route 69 $585,000 Newburgh extending south 3.87 miles. HCP 3 PMRAP Laydown/Surface HMA

113

0123456789 ID/Year Municipality Scope Name Description Funding

023326.00 Highway Paving Hampden, Beginning 0.18 of a mile west of Chapman Road and 2018 Route 9 $1,012,489 Newburgh Highway Cyclical Pavement extending easterly 7.50 miles. HCP 3 Resurfacing

022877.00 Highway Safety and Spot Improvements Located at the intersection of Coldbrook Road, Odlin 2018 Hermon Coldbrook Road $202,082 Road and Emerson Mill Road. BACTS Sponsored. HCP 3 Intersection Improvements

022879.00 Highway Safety and Spot Improvements Located at the intersection of Route 2 and Annis 2019/20 Hermon Route 2 $500,000 Road. HCP 3 Intersection Improvements

WR 34695 Bridge and Structural Replacing wearing surface and patching breast wall wings around footing on Black Stream Bridge Hermon Maintenance Fuller Road $79,000 2018 (#3786) over Black Stream. Located 0.30 of a mile east of Brad Way.

018824.00 Highway Safety and Spot Improvements Large culvert (#776300) located 0.15 of a mile south 2018 Herseytown Twp Interstate 95 SB $120,000 of Interstate 95 southbound on-ramp. HCP 1 Large Culvert Rehabilitation

023679.00 Herseytown Twp, Highway Paving Beginning 1.56 miles north of the T2 R9 NWP- 2019/20 Medway, T1 R6 Interstate 95 NB Medway town line and extending northerly 12.70 $5,080,000 WELS Mill And Fill miles. HCP 1

023366.00 Herseytown Twp, Sherman, Highway Paving Beginning 1.07 miles north of Grindstone Twp.- 2019 Soldiertown Twp Route 11 Soldiertown twp. town line extending northerly 12.13 $443,715 T2 R7 WELS, Light Capital Paving miles. HCP 4 Stacyville

022881.00 Highway Safety and Spot Improvements Beginning 0.16 of a mile east of Charles Street and 2019/20 Holden Route 1A $905,000 extending easterly 0.95 of a mile. HCP 1 Highway Improvements

022883.00 Highway Safety and Spot Improvements Beginning 0.49 of a mile southeast of Debeck Road 2019/20 Holden Route 1A $585,000 and extending southeast 0.61 of a mile. HCP 1 Highway Improvements

018826.00 Highway Safety and Spot Improvements Large culvert (#46276) located 0.31 of a mile north of 2019/20 Howland Route 116 $300,000 Edinburg town line. HCP 4 Large Culvert Replacement

114

0123456789 ID/Year Municipality Scope Name Description Funding

018827.00 Highway Safety and Spot Improvements Large culvert (#46277) located 5.73 miles north of 2019/20 Howland Seboeis Road $500,000 North Howland Road. HCP 4 Large Culvert Rehabilitation

WR 34230 Bridge and Structural Replacing joint on I-95 NB/ Bridge 2018 Howland Maintenance Interstate 95 NB (#1419) which carries Interstate 95 over the $63,000 Piscataquis River in Howland. HCP 1

WR 35340 Bridge and Structural Upgrading bridge rail and repairing concrete parapet 2018 Howland Maintenance Route 6/155 on Route 155/ I-95 Bridge (#6068) over Interstate 95. $40,000 Located 0.26 of a mile east of Maxfield Road. HCP 3

023597.00 Howland, Highway Paving Mattamiscontis Beginning 0.24 of a mile north of the Edinburg town 2019/20 Twp, Medway, Interstate 95 NB $4,233,600 line and extending northerly 26.47 miles. T2 R8 NWP, T2 Ultra Thin Bonded Wearing HCP 1 R9 NWP Surface

WR 32666 Bridge and Structural Repairing bridge rail and curb on Higginsville Bridge Kenduskeag Maintenance Higginsville Road (#3753) over . Located 0.05 of a $138,000 2018 mile south of Grant Road.

022110.00 Highway Paving Levant/ Beginning at Hermon-Levant town line extending Kenduskeag, 2018 Kenduskeag north 4.87 mi les to Stetson Road/Town House Road $172,398 Levant Light Capital Paving Road in Kenduskeag. HCP 4

Kingman Twp, 023366.00 Macwahoc Plt, Highway Paving Prentiss Twp T7 Beginning 0.19 of a mile north of Webster Plt. town 2019 Route 170 $609,789 R3 NBPP, line and extending northerly 16.67 miles to Route 2. Light Capital Paving HCP 4 Springfield, Webster Plt

WR 32874 Ditching various locations beginning at the Webster Kingman Twp, Drainage Maintenance 2018 Route 170 Plt.- Kingman Twp. town line and extending west to $68,000 Macwahoc Plt the intersection of Route 2 in Macwahoc Plt. HCP 4

018786.00 Highway Construction/ Rehabilitation Beginning 0.11 of a mile west of Medford Road and 2019/20 Lagrange Route 6 $600,000 extending southerly 0.93 of a mile. HCP 2 Highway Rehabilitation

WR 35053 Drainage Maintenance Replacing road base 0.69 of a mile east of the 2018 Lee Route 6 intersection of the Maxwell Road and repairs $21,000 extending 500 feet. HCP 3

115

0123456789 ID/Year Municipality Scope Name Description Funding

Aviation 018697.01 Safety and infrastructure improvements that may Lincoln Regional include the reconstruction of Runway 17-35 with Lincoln Runway/Taxiway $3,605,000 2019/20 Airport safety areas and construction of Taxiway on the 17 Reconstruction end at the Lincoln Regional Airport (LRG).

Aviation 018697.02 Safety and infrastructure improvements that may Airport Buildings Lincoln Regional include easement acquisition for the Runway 35 Lincoln $103,000 2018 Airport Approach - Phase 2 at the Lincoln Regional Airport Sale Or Purchase Of Lot Or (LRG). Building

Aviation 018697.03 Safety and infrastructure improvements that may Lincoln Regional Lincoln Planning And Research include a wildlife hazard assessment at the Lincoln $103,000 2018 Airport Regional Airport (LRG). Planning Studies

Aviation 018697.04 Safety and infrastructure improvements that may Lincoln Regional include design and permitting for the reconstruction Lincoln Runway/Taxiway $309,000 2019/20 Airport of Runway 17-35 at the Lincoln Regional Airport Reconstruction (LRG).

Aviation 018697.16 Safety and infrastructure improvements that may Airport Buildings Lincoln Regional Lincoln include land acquisition at the Lincoln Regional $188,490 2018 Airport Sale Or Purchase Of Lot Or Airport (LRG). Building

Aviation 018697.17 Safety and infrastructure improvements that may Lincoln Regional include design, permitting and obstruction removal - Lincoln Navigation Aids/Lights $154,500 2019/20 Airport Phase 2 (Runway 35 Approach) at the Lincoln Removal Of Obstructions Regional Airport (LRG).

021847.00 Highway Safety and Spot Improvements Beginning at Goding Avenue and extending north 2019/20 Lincoln Route 2 $265,000 0.80 of a mile to Lee Road. HCP 3 Drainage Improvements

022653.00 Highway Construction/ Rehabilitation Beginning at Hale Street and extending south 0.57 of 2019/20 Lincoln Route 155 $50,000 a mile to Transalpine Road. HCP 4 Drainage Improvements

WR 32559 Drainage Maintenance Resetting inlet side of large culvert (#46275) 0.22 2018 Lincoln Route 116 $52,000 miles west of Route 2. HCP 3

WR 34177 Replacing cross culverts (#102457, #890727) located Long A Twp, Drainage Maintenance 0.52 of a mile north of West Seboeis Road in Long A 2018 Route 11 $35,000 Medway Twp. and 0.60 of a mile south of the Medway-East HCP 3, 4 Millinocket town line in Medway.

116

0123456789 ID/Year Municipality Scope Name Description Funding

Highway Safety and Spot 022922.00 Improvements Large culvert (#46619) located 0.37 of a mile north of 2018 Mattawamkeag Route 157 $60,000 Jordan Mills Road. Large Culvert Improvements - HCP 3 PE Only

023234.00 Mattawamkeag Bridge (#2522) over Mattawamkeag 2019/20 Mattawamkeag Route 2 River. Located 125 feet north of Boyd Street. This $3,362,578 Bridge Improvements project is only partially funded for construction. HCP 3

Freight 023256.00 Perma Treat Mattawamkeag Line Construct new turnout and 450' of additional track. $152,960 2018 Corporation Rehabilitation

WR 34032 Drainage Maintenance Replacing culvert (#184299) located 0.4 of a mile 2018 Mattawamkeag Route 2 $21,000 south of the Mattawamkeag-Winn town line. HCP 3

WR 34159 Bridge and Structural Repair erosion under the south end of both Vaughn Interstate 95 Daggett Bridges (#6078, #1410) located on Interstate 2018 Medway Maintenance $58,000 NB/SB 95 over the Penobscot River approximately 0.43 of a HCP 1 mile south of Route 157 in Medway.

023647.00 Second Otter Bridge (#2754) over Otter Stream. 2018 Milford County Road $400,000 Slope Stabilization/Protection Located 0.07 of a mile west of Overlook Drive. HCP 6

WR 33686 Drainage Maintenance Drainage work beginning 1.00 mile east of Route 2 2018 Milford Greenfield Road $44,000 and extending easterly 0.2 miles. HCP 4

Aviation 018699.01 Safety and infrastructure improvements that may Millinocket Millinocket Runway/Taxiway include the acquisition of snow removal equipment at $342,990 2019/20 Municipal Airport the Millinocket Municipal Airport (MLT). Capital Equipment Purchase

Aviation 018699.02 Safety and infrastructure improvements that may Millinocket include an Airport Master Plan Update to include a Millinocket Planning And Research $154,500 2019/20 Municipal Airport Wildlife Hazard Site Visit at the Millinocket Municipal Planning Studies Airport (MLT).

WR 34559 Bridge and Structural Repair abutment and bridge rail on State Street Millinocket Maintenance State Street Bridge (#0909) over Millinocket Stream located $170,000 2018 between the intersection of State and Spring Street.

117

0123456789 ID/Year Municipality Scope Name Description Funding

WR 34562 Bridge and Structural Repair southwest approach and wearing surface on Granite Street Bridge (#0902) located over Millinocket Maintenance Granite Street $40,000 2018 Millinocket Stream between Congress Street and York Street.

WR 34738 Drainage Maintenance Ditching from the Beebe Road extending north to the 2018 Mount Chase Route 159 $19,000 Shin Pond Bridge in Mount Chase. HCP 4

022960.00 Highway Safety and Spot Mount Chase, Improvements Beginning 0.02 of a mile south of the Patten town line 2019/20 Route 11 $40,000 Patten and extending northerly 0.20 of a mile. HCP 2 Drainage Improvements

WR 32921 Ditching various locations beginning at the Mount Chase, Drainage Maintenance 2018 Route 159 intersection of Route 11 and extending north to the $90,000 Patten Patten-Mount Chase town line. HCP 4

WR 35287 Bridge and Structural Mill and fill asphalt wearing surface on Durham Durham Bridge Newport Maintenance Bridge (#3170) over Stetson Stream. Located 0.29 of $25,000 2018 Road a mile south of Rutland Road.

023368.00 Highway Paving Newport, East Newport Beginning at Route 2 and extending north 5.80 miles 2019 $307,098 Stetson Road to Route 143. Light Capital Paving HCP 4

WR 32697 Stetson Road, Drainage Maintenance Ditching and replacing cross culverts on the East 2018 Newport, Stetson East Newport $110,000 Newport Road between Route 2 and Route 143. Road HCP 4

Aviation 018701.01 Dewitt Field, Old Safety and infrastructure improvements that may Old Town Airport Buildings Town Municipal include construction of a 6 unit T-Hangar at the $592,250 2019/20 Airport Dewitt Field, Old Town Municipal Airport (OLD). New Construction

022340.00 Route 43/ I-95 Bridge (#6061) over Interstate 95. West Old Town 2019/20 Old Town Located 0.09 of a mile northwest of Exit #197 $3,000,000 Road Bridge Deck Replacement Interstate 95 northbound. HCP 3

022445.00 Highway Paving Beginning at Abbott Street and extending northeast 2019/20 Old Town Route 2A $310,295 0.28 of a mile to Center Street. BACTS Sponsored. Mill And Fill HCP 2

118

0123456789 ID/Year Municipality Scope Name Description Funding

022511.00 Stillwater #2 Bridge (#2806) over the North Channel 2019/20 Old Town Stillwater Avenue . Located 0.13 of a mile north of Free $5,600,000 Bridge Replacement Street. HCP 2

022512.00 Stillwater #1 Bridge (#1472) over the South Channel 2019/20 Old Town Stillwater Avenue Stillwater River. Located 0.06 of a mile north of Free $2,000,000 Bridge Replacement Street. HCP 2

022950.00 Highway Safety and Spot Improvements Located at the intersection of Route 2A and College 2019/20 Old Town Stillwater Avenue $5,000,000 Avenue (includes all approaches). HCP 2 Intersection Improvements

023396.00 Highway Paving Beginning 0.44 of a mile south of West Coiley Road 2018 Old Town Route 43 $307,797 Highway Cyclical Pavement and extending southerly 2.28 miles. HCP 3 Resurfacing

020898.00 Highway Safety and Spot Improvements Large culvert (#942495) located 0.66 of a mile north 2019/20 Orono Route 2 $512,367 of the Veazie town line. BACTS Sponsored. HCP 3 Large Culvert Replacement

022344.00 Kelly Road/ I-95 Bridge (#5905) over Kelly Road. 2019/20 Orono Kelly Road Located 0.61 of a mile southeast of Stillwater $2,530,000 Bridge Rehabilitation Avenue. HCP 2

WR 34699 Drainage Maintenance Ditching and stone ditch protection beginning 0.50 of 2018 Orono Stillwater Avenue a mile north of Forest Avenue and extending $42,000 northerly 0.25 of a mile. HCP 3

Bicycle-Pedestrian 018884.00 Trail, On-Road Beginning at Pebble Creek Drive and extending north 2018 Orrington Route 15 $735,000 0.82 of a mile to Harrison Avenue. Bicycle/Pedestrian HCP 2 Improvements

022110.00 Highway Paving Brewer Lake Beginning at Fields Pond Road extending to Brewer- 2018 Orrington $65,490 Road Orrington town line. Light Capital Paving HCP 4

022110.00 Highway Paving Dow/ Snows Beginning at intersection of Dow Road and Center 2018 Orrington $90,270 Corner Road Drive extending north to Route 15. Light Capital Paving HCP 4

119

0123456789 ID/Year Municipality Scope Name Description Funding

022446.00 Highway Paving Beginning at Snows Corner Road and extending 2018 Orrington Route 15 north 0.76 of a mile to Harrison Avenue. BACTS $475,000 Mill And Fill Sponsored. HCP 2

023308.00 Highway Paving Beginning 0.22 of a mile northeast of Industrial Way 2018 Orrington Route 15 $393,423 Ultra Thin Bonded Wearing and extending northeasterly 1.65 miles. HCP 2 Surface

Highway Safety and Spot 021810.00 Improvements Large culvert (#282919) located 0.01 of a mile south 2018 Patten Route 11 $100,000 of Church Street. Large Culvert Improvements - HCP 2 PE Only

Highway Safety and Spot 023703.00 Improvements Large culvert (#923891) located 0.03 of a mile 2018 Plymouth Route 69 $50,000 southwest of Twitchell Road. Large Culvert Improvements - HCP 4 PE Only

023014.00 Highway Safety and Spot Improvements 2018 T2 R8 NWP Interstate 95 Replace lighting at Interstate 95 Exit #227. $625,000

HCP 3 Lighting

WR 32395 Bridge and Structural Replacing two joints on I-95 SB/CPRR Bridge 2018 T2 R8 NWP Maintenance Interstate 95 SB $64,000 (#6075) over the Eastern Maine Railway. HCP 1

023236.00 West Branch Bridge (#3666) over West Branch T3 Indian Penobscot River. Located 400 feet north of North 2019/20 Route 11 $5,230,937 Purchase Twp Bridge Improvements Twin Dam Road. This project is only partially funded HCP 3 for construction.

WR 34741 Ditching beginning 1.1 miles east of Scraggly Lake Drainage Maintenance Grand Lake 2018 T6 R7 WELS Road extending westerly to the Seboeis Stream $21,000 Road Bridge. HCP 4

WR 34725 Replacing three cross culverts (#995738, #995896, T6 R7 WELS, T6 Drainage Maintenance Grand Lake 2018 #995921) beginning at the intersection of Bowlin $95,000 R8 WELS Road Pond Road extending to the Huber Road. HCP 4

WR 34740 Ditching various locations beginning at the T6 R7 Drainage Maintenance Grand Lake 2018 T6 R8 WELS Wells - T6 R8 Wells town line and extending west $23,000 Road 1.00 mile. HCP 4

120

0123456789 ID/Year Municipality Scope Name Description Funding

Highway Safety and Spot 023028.00 Improvements 2018 Veazie Route 2 Located 0.07 of a mile north of Main Street. $75,000 Slope Stabilization/Protection - HCP 3 PE Only

022266.00 Mattagodus Bridge (#5116) over Mattagodus Stream. 2019/20 Webster Plt Route 170 Located 0.43 of a mile southeast of the Kingman $1,200,000 Bridge Replacement Twp. town line. HCP 4

WR 32879 Drainage Maintenance Repairing culvert (#184295) located 0.08 of a mile 2018 Winn Route 2 $152,000 south of the intersection of Main Street. HCP 3

121

0123456789 Piscataquis

T10 R15 T10 R14 T10 R13 T10 R12 T10 R11 T10 R10 T10 R9 Piscataquis WELS WELS WELS WELS WELS WELS WELS

T9 R15 T9 R14 T9 R13 T9 R12 T9 R11 T9 R10 T9 R9 WELS WELS WELS WELS WELS WELS WELS

Soper T8 R15 T8 R14 Eagle T8 R11 T8 R10 T8 R9 Mountain WELS WELS Lake Twp WELS WELS WELS Twp

T7 R15 T7 R14 T7 R13 T7 R12 T7 R11 T7 R10 T7 R9 WELS WELS WELS WELS WELS WELS WELS

Trout T6 R11 T6 R10 T6 R15 T6 R14 T6 R13 T6 R12 Brook WELS WELS WELS WELS WELS WELS Twp

T5 R15 T5 R14 Chesuncook T5 R12 T5 R11 Nesourdnahunk T5 R9 WELS WELS Twp WELS WELS Twp WELS

T4 R15 WELS T4 R14 T4 R13 T4 R12 T4 R11 T4 R10 T4 R9 WELS WELS WELS WELS WELS WELS

Northeast Mount T3 R13 T3 R12 T3 R11 T3 R10 Katahdin Carry Lobster WELS WELS WELS WELS Twp Twp Twp

TX R14 WELS T2 R13 T2 R12 Rainbow T2 R10 T2 R9 East Middlesex WELS WELS Twp WELS Piscataquis County Canal WELS Days Grant Tw p Population 17,535 Academy Grant Twp Spencer T1 R13 T1 R12 T1 R11 T1 R10 T1 R9 Land Area (sq mi) 3,961 Bay Twp WELS WELS WELS WELS WELS Bridges 124 Lily Highway Corridor Priority Miles Bay Twp Frenchtown Shawtown TA R11 TA R10 Twp Twp WELS WELS HCP 2 70 HCP 3 58 Beaver Cove TB R11 TB R10 Big HCP 4 145 Bow doin WELS WELS Moose Bowdoin College Grant Twp College Grant Eas t Twp West Twp T4 R9 Total HCP 1-4 2 73 Greenville Ebeemee NWP Moosehead Katahdin Twp Junction T7 R9 Iron Works Twp Elliottsville NWP Twp Twp Lake Williamsburg View Twp Brownville Shirley Plt Bowerbank Willimantic Barnard Twp Monson Medford Milo Blanchard Sebec Twp Guilford Abbot Dover-Foxcroft Orneville Kingsbury Atkinson Twp Plt Sangerville Parkman

Wellington Piscataquis ID/Year Municipality Scope Name Description Funding

022646.00 Highway Construction/ Rehabilitation Beginning 0.39 of a mile north of West Road and 2019/20 Abbot Route 6 $5,885,000 extending southerly 2.69 miles. HCP 2 Reconstruction

023368.00 Highway Paving Beginning at the Kingsbury Plt. town line and 2019 Abbot Route 16 $225,558 extending east 4.26 miles to Route 6. Light Capital Paving HCP 4

023368.00 Highway Paving Abbot, Guilford, Beginning at Route 6 and extending north 13.60 2019 Route 150 $720,091 Willimantic miles. Light Capital Paving HCP 2, 4

WR 32494 Abbot, Kingsbury Drainage Maintenance Ditching and replacing culverts on Route 16 from 2018 Kingsbury Road $201,000 Plt Kingsbury to Abbot. HCP 4

WR 32661 Bridge and Structural Repairing rail, fixing curb and facia, and installing approach guard rail on Marden Bridge (#5920) over Atkinson Maintenance Maple Road $66,000 2018 Alder Stream. Located 0.38 of a mile north of Power Line Road.

WR 34107 Drainage Maintenance Replacing culverts on Lily Bay Road between Prong 2018 Beaver Cove Lily Bay Road $8,000 Pond Road and State Park Road. HCP 4

WR 34108 Beaver Cove, Drainage Maintenance Cleaning under the guard rail and removing 2018 Frenchtown Twp, Lily Bay Road overburden on wing walls from Beaver Cove to $20,000 Lily Bay Twp Frenchtown Twp. HCP 4

WR 34500 Big Moose Twp, Sandwich Drainage Maintenance Replacing culverts on Route 6 from the Demo Road 2018 Route 6 $30,000 Academy Grant to Mountain View Pond Road. HCP 3 Twp

WR 34703 Blanchard Twp, Surface and Base Maintenance Repairing culvert crossings on the Blanchard Road in 2018 Blanchard Road $11,000 Monson Monson and Blanchard Twp. HCP 4

020415.00 Highway Safety and Spot Improvements 2019/20 Brownville Route 11 Located 0.75 of a mile south of Airport Road. $412,500

HCP 3 Slope Stabilization/Protection

122

0123456789 ID/Year Municipality Scope Name Description Funding

WR 34769 Sebec Village Ditching and replacing drainage structures on various Brownville, Drainage Maintenance 2018 Road, High sections of the Sebec Village Road in Sebec and $37,000 Sebec Street Brownville. HCP 4

WR 34444 Removing excess shoulder material from the railroad Brownville, T4 Drainage Maintenance 2018 Route 11 tracks in Brownville Jct. to the T4 R9 - Long A Twp. $196,000 R9 NWP town line. HCP 3

021779.00 Highway Construction/ Rehabilitation Beginning at Shaw Road and extending north 4.13 2018 Dover-Foxcroft Route 7 $372,500 miles. HCP 3 PMRAP DOT Pugmill

021779.10 Highway Construction/ Rehabilitation Beginning at Shaw Road and extending north 4.13 2018 Dover-Foxcroft Route 7 $690,000 miles. HCP 3 PMRAP Laydown/Surface HMA

022851.00 Highway Safety and Spot Improvements Large culvert (#967780) located 0.48 of a mile north 2019/20 Dover-Foxcroft Route 15 $630,000 of Norton Hill Road. HCP 2 Large Culvert Replacement

023555.00 Highway Paving Beginning at Lincoln Street and extending northeast 2019/20 Dover-Foxcroft Route 6 $578,619 0.96 of a mile. Mill And Fill HCP 2

WR 32360 Producing, hauling and providing additional support PMRAP activities for the placement of plant mix recycled 2018 Dover-Foxcroft Route 7 asphalt pavement (PMRAP) beginning at the $500,000 intersection of Shaw Road and extending north 4.13 HCP 3 miles.

WR 32444 Drainage Maintenance Replacing a culvert (#148271) located 0.08 of a mile 2018 Dover-Foxcroft Route 7 $176,000 south of Kinney Corner Road on Route 7. HCP 3

021752.00 Station 350 Bridge (#3781) over the East Branch 2018 Ebeemee Twp Route 11 Pleasant River. Located 0.19 of a mile southwest of $1,300,000 Bridge Deck Replacement the T4 R9 NWP town line. HCP 3

WR 34057 Frenchtown Twp, Drainage Maintenance Ditching beginning at the intersection of Route 6 2018 Lily Bay Road $40,000 Greenville extending north 18.86 miles to Frenchtown Twp. HCP 4

123

0123456789 ID/Year Municipality Scope Name Description Funding

Aviation 018694.01 Safety and infrastructure improvements that may Greenville Greenville Runway/Taxiway include an aeronautical survey for Runway 32 at the $103,000 2019/20 Municipal Airport Greenville Municipal Airport (3B1). New Construction

Aviation 018694.17 Safety and infrastructure improvements that may Greenville Greenville Runway/Taxiway include the installation of a fuel farm at the Greenville $342,990 2018 Municipal Airport Municipal Airport (3B1). Capital Equipment Purchase

WR 34570 Drainage Maintenance Route 6, Lily Bay Repairing catch basins on Route 6 and Lily Bay 2018 Greenville $8,000 Road Road in Greenville. HCP 2, 4

023296.00 Highway Paving Beginning 0.01 of a mile southeast of North Main 2018 Guilford Route 6 $1,104,153 Ultra Thin Bonded Wearing Street and extending easterly 4.93 miles. HCP 2 Surface

WR 33946 Bridge and Structural Replace wearing surface, install new joint headers Guilford, and seals on Sangerville Station Bridge (#2801) over 2018 Maintenance Route 23 $200,000 Sangerville Piscataquis River. Located 0.13 of a mile south of HCP 2 Route 6.

023671.00 Highway Construction/ Long A Twp, T4 Rehabilitation Beginning 0.01 of a mile south of the T4 R9 NWP 2018 Route 11 $120,000 R9 NWP town line and extending northerly 5.59 miles. HCP 3 PMRAP DOT Pugmill - PE Only

WR 33225 Drainage Maintenance Ditch and replace entrance and cross culverts as 2018 Medford Medford Road needed between the Medford Center Road and the $37,000 Schoodic Point Road. HCP 4

020502.00 Old Toll Bridge (#2867) over Piscataquis River. 2018 Milo Route 6 $150,000 Bridge Improvements - PE Only Located 0.35 of a mile northwest of Route 11. HCP 2

022627.00 Pleasant River Bridge (#3244) over Pleasant River. 2019/20 Milo Pleasant Street Located 0.09 of a mile west of Pleasant River Road. $2,870,265 Bridge Improvements This project is only partially funded for construction. HCP 4

Highway Safety and Spot 022930.00 Improvements Large culvert (#267649) located 0.40 of a mile south 2018 Monson Route 6 $50,000 of Shirley town line. Large Culvert Improvements - HCP 2 PE Only

124

0123456789 ID/Year Municipality Scope Name Description Funding

023523.00 Barrows Falls Barrow Falls Bridge (#3413) over Piscataquis River. 2019/20 Monson $100,000 Bridge Painting Road Located 0.05 of a mile south of Pine Lane. HCP 6

Highway Safety and Spot 022958.00 Improvements Large culvert (#46300) located 0.26 of a mile north of 2018 Parkman Route 150 $95,000 Wellington Road. Large Culvert Improvements - HCP 3 PE Only

WR 34599 Surface and Base Maintenance Roadway base gravel cuts or fills on the Parkman 2018 Wellington Parkman Road $83,000 Road in Wellington. HCP 4

WR 34601 Surface and Base Maintenance 2018 Wellington Parkman Road Grading the Parkman Road in Wellington. $10,000

HCP 4

022624.00 Goodell Bridge (#2317) over Davis Brook. Located 2018 Willimantic Elliotsville Road $1,600,000 Bridge Replacement 0.02 of a mile north of Route 150. HCP 6

125

0123456789 Sagadahoc

Richmond

Bowdoin Sagadahoc

Bowdoinham

Woolwich Topsham

Bath

Sagadahoc County West Bath Arrowsic Population 35,293 Land Area (sq mi) 254 Bridges 103 Highway Corridor Priority Miles HCP 1 6 4 HCP 2 2 HCP 3 69 HCP 4 85

Phippsburg Total HCP 1-4 22 0 Sagadahoc ID/Year Municipality Scope Name Description Funding

022094.00 Arrowsic, Highway Paving Beginning at the Woolwich town line and extending 2018 Georgetown, Route 127 $359,664 south 10.16 miles. Woolwich Light Capital Paving HCP 4

023507.00 Max L. Wilder Memorial Bridge (#2026) over Arrowsic, 2019/20 Route 127 Sasonoa River. Located 0.21 of a mile south of $1,200,000 Woolwich Bridge Wearing Surface Replacement Route 1. HCP 4

019390.00 Bicycle-Pedestrian Beginning at the train station and extending north Commercial 2018 Bath Trail, On-Road 0.13 of a mile. $260,609 Street HCP 4 New Construction

021664.00 Highway Construction/ Rehabilitation Located at the intersection of Route 1 and State 2019/20 Bath Route 1 $1,320,000 Road. HCP 1 Intersection Reconstruction

021665.00 Bicycle-Pedestrian Beginning at Crawford Drive and extending south 0.41 of a mile, plus 0.02 of a mile for divided Oak Grove 2018 Bath Trail, On-Road highway. Then beginning at Oak Grove Avenue and $152,710 Avenue extending west 0.15 of a mile to Old Brunswick HCP 6, 4 New Construction - PE Only Road.

022280.00 Paul Davis Memorial Bridge (#3837) over Route 1. 2019/20 Bath High Street $250,000 Bridge Wearing Surface Located 0.10 of a mile north of Union Street. Replacement HCP 3

022094.00 Highway Paving Beginning at the Bath town line and extending west 2018 Bath, West Bath State Road $70,800 2.00 miles to the Brunswick town line. Light Capital Paving HCP 3

WR 35420 Vegetation management along Route 196 beginning at the intersection of Route 201 extending south to Bath, Brunswick, Custodial Maintenance Route 1, Route 2018 the intersection of Route 1, and Route 1 beginning at $7,000 Topsham 196, Route 24 the intersection of Mill Street extending north 8.00 HCP 1 miles to High Street in West Bath.

022094.00 Highway Paving Beginning at Route 125 and extending north 0.80 of 2018 Bowdoin Store Road $28,320 a mile. Light Capital Paving HCP 4

023376.00 Highway Paving Store House Beginning at Main Street and extending northwest 2019 Bowdoin $29,634 Road 0.81 of a mile to the Lisbon town line. Light Capital Paving HCP 4

126

0123456789 ID/Year Municipality Scope Name Description Funding

WR 35290 Drainage Maintenance Ditching beginning at the Route 125 intersection 2018 Bowdoin Litchfield Road $17,000 extending north 3.00 miles. HCP 4

022094.00 Bowdoin, Highway Paving Beginning at Route 201 and extending north 9.48 2018 Bowdoinham, Route 138 $335,592 miles. Richmond Light Capital Paving HCP 3, 4

022094.00 Highway Paving Bowdoin, Beginning at Route 201 and extending north 3.41 2018 Meadow Road $120,714 Topsham miles. Light Capital Paving HCP 4

WR 34091 Repairing the curb and installing bridge rail and Bridge and Structural guard rail on Two Bridges West (#0972) and Two 2018 Bowdoinham Maintenance Route 24 Bridges East (#2974) over the and $130,000 West Branch Denham Stream. Located 0.14 of a HCP 3 mile east of Ridge Road.

WR 35374 Bridge and Structural Replacing the southern joint and reinforcing the backwall on Brooklyn Bridge (#5190) over the 2018 Bowdoinham Maintenance Route 24 $250,000 Cathance River. Located 0.04 of a mile south of HCP 3 River Road.

023376.00 Highway Paving Beginning 0.05 of a mile from Route 24 and Dresden, 2019 Route 197 extending east 2.51 miles to 0.03 of a mile from $91,830 Richmond Light Capital Paving Route 127. HCP 3

022094.00 Highway Paving Beginning 0.14 of a mile north of Griffiths Head Road 2018 Georgetown Seguinland Road $74,694 and extending northerly 2.11 miles. Light Capital Paving HCP 4

WR 34978 Drainage Maintenance Ditching and replacing ten culverts on Route 127 2018 Georgetown Route 127 beginning 0.13 of a mile north of Bay Point Road $106,700 extending northerly 1.98 miles to Seguinland Road. HCP 4

Marine 020848.00 Popham Road Phippsburg Piers, Floats And Fenders Pier rehabilitation, located on Fort Popham Pier. $140,000 2018 Pier Rehabilitation

WR 35082 Drainage Maintenance Cleaning under guard rails beginning at the Phippsburg Route 209 Phippsburg town line extending south 13.25 miles to $78,000 2018 Sea Street.

127

0123456789 ID/Year Municipality Scope Name Description Funding

020877.00 Highway Paving Beginning 0.06 of a mile east of Williams Street and 2018 Richmond Route 197 $348,000 extending easterly 0.48 of a mile to Route 24. Mill And Fill HCP 3

020878.00 Highway Paving Beginning 0.77 of a mile east of Route 138 and 2018 Richmond Route 197 $221,000 extending easterly 0.64 of a mile. Mill And Fill HCP 3

023741.00 Highway Safety and Spot Improvements Located 0.02 of a mile south of Baker Street and 2019/20 Richmond Route 24 $125,000 extending northerly 0.02 of a mile to Baker Street. HCP 3 Slope Stabilization/Protection

WR 33369 Drainage Maintenance Replacing an instream culvert (#899171) located 2018 Richmond Route 201 0.15 of a mile southwest of the Route 197 $160,000 intersection. HCP 3

WR 34973 Ditching beginning at the Route 201 intersection Drainage Maintenance Alexander Reed 2018 Richmond extending 5.68 miles east to the Route 197 $14,000 Road intersection. HCP 4

WR 35222 Department Building and Lot Installing new shingles on the Richmond Maine DOT Richmond Maintenance Route 138 maintenance lots salt dome (#B36020). Located $62,500 2018 0.10 of a mile south of the Route 201 intersection.

023783.00 Highway Safety and Spot Improvements Located at the intersection of Route 201 and Route 2019/20 Topsham Route 201 $211,500 24. HCP 2 Intersection Improvements

WR 34662 Bridge and Structural Install approach guard rail and michigan shoe rail to bridge attachment plates to the four corners of the Topsham Maintenance Foreside Road $18,000 2018 Muddy River Bridge (#3825) over the Muddy River. Located 0.28 of a mile south of Middlesex Road.

023030.00 Highway Safety and Spot Improvements Located at the intersection of State Road and New 2019/20 West Bath State Road $550,000 Meadows Road/ Fosters Point Road. HCP 6, 3 Intersection Improvements

Highway Construction/ 023795.00 Rehabilitation Large culvert (#46177) located 0.31 of a mile south 2018 West Bath Berry's Mill Road $38,000 of Austin Road. Large Culvert Replacement - HCP 4 PE Only

128

0123456789 ID/Year Municipality Scope Name Description Funding

023805.00 Highway Paving Wiscasset, Beginning 0.25 of a mile north of Montsweag Road 2019/20 Route 1 $2,279,477 Woolwich and extending northerly 3.90 miles. 1 1/4" Overlay HCP 1

021759.00 Nequasset Bridge (#5695) over Nequasset Lake 2018 Woolwich Route 1 Outlet. Located 0.14 of a mile northeast of $450,000 Bridge Painting Nequasset Road. HCP 1

129

0123456789 Big Te n T10 R 16 Tw p WELS Somerset

T9 R1 7 T9 R1 6 T9 R 18 WELS WELS WELS

T8 R1 8 T8 R1 7 T8 R1 6 T 8 R 1 9 WELS WELS WELS WELS

T7 R1 9 T7 R1 8 T7 R1 7 T7 R1 6 WELS WELS WELS WELS

Sa int T6 R1 8 Big Six T6 R1 7 Jo hn WELS WELS Tw p Tw p Russell T5 R1 8 T5 R1 7 T5 R 19 Po nd T5 R 20 WELS WELS WELS WELS Tw p Elm Dole T4 R1 7 Stream T 4 R 5 C o m s to ck NBKP WELS Broo k Tw p Twp Tw p Se b oo m oo k Plymouth Pittston Tw p H a m m o n d Acad emy Twp P ren tis s Tw p Twp T 4 Gra nt R4 N B K P Bi g W Ald er West Soldiertown Mid dlesex Tw p B a l d Broo k Sa nd y Tw p T2 Canal Grant M o u n ta in Tw p Ba y R3 N BKP Tw p T4 R 3 Tom h egan Somerset County Tw p Tw p Moose Th o rn d ik e Brassua Population 52,228 River Tw p Tw p D e nn isto w n Land Area (sq mi) 3,924 Forsyth Pl t Taunton & Lon g S andw ic h Raynham Academy Tw p Bridges 77 Somerset A ca dem y Grant 2 Po nd Gr ant T wp Attea n Jackman Tw p Highway Corridor Priority Miles Hole b Tw p Sapling Tw p Parlin Mise ry Twp HCP 1 78 B r a d s tre e t Pond Twp Tw p T5 R 7 Tw p Appleton BK P W K R Johnson Chase In dia n HCP 2 141 Stream St re a m Twp Mountain Twp U p p e r Twp HCP 3 140 T5 R6 H ob bstow n E n c h a n te d Twp BKP Tw p Tw p Sq ua re to w n HCP 4 247 Tw p WKR West M o xie Lower Forks Plt T3 R5 Enchanted Go r e Kin g & Ea st BKP Twp Total HCP 1-4 6 06 Ba rtlett WKR Bow to wn The Moxie Tw p Pie rce Tw p Forks Tw p T3 R4 Po nd Plt Flagstaff BKP Tw p B a l d Twp WKR M o u n ta in Ca rryin g Caratun k Tw p T2 R 3 Bige low Dea d Pla ce Tw p River Tow n Tw p Tw p P lea s ant Mayfie ld Ridge P lt Mosco w Tw p High lan d Plt Bin gh a m Brigh to n Plt Cambridge Lexington Con cord Twp Tw p Riple y Harmon y Athe ns So lon Sa int New Emb de n Alb an s Po rtlan d Hartland Cornville Pa lmyra An so n Madison

Detroit Skowhegan Pittsfield Starks C a n a a n Norridgewock

Me rce r Smithfield Fairfield Somerset ID/Year Municipality Scope Name Description Funding

021657.00 Ice House Bridge (#3726) over Gilbert Brook. 2019/20 Anson Route 201A $900,000 Bridge Replacement Located 0.05 of a mile south of Campground Road. HCP 2

WR 34889 Drainage Maintenance Ditching beginning at the intersection of Route 43 2018 Anson Route 148 $43,000 extending 4.61 miles west to the Industry town line. HCP 4

016864.00 Bicentennial Memorial Bridge (#2491) over 2018 Anson, Madison Route 8 Kennebec River. Located on the Madison-Anson $1,000,000 Bridge Painting town line. HCP 2

WR 34667 Ditching beginning at the intersection of Route 16 in Drainage Maintenance Embden Pond 2018 Anson, Embden Anson extending north 5.45 miles to the East Shore $55,000 Road Road in Embden. HCP 4

WR 34671 Ditching beginning at the intersection of East Shore Anson, Embden, Drainage Maintenance 2018 Crosstown Road Road extending 2.66 miles east to the intersection of $127,000 Smithfield Route 201A in Embden. HCP 4

018952.00 Gilman Bridge (#2313) over the East Branch 2018 Athens Route 150 Wesserunsett Stream. Located 0.03 of a mile $2,185,000 Bridge Replacement northeast of Stickney Hill Road. HCP 3

022825.00 Wesserunsett Bridge (#2925) over Wesserunsett 2019/20 Athens Bridge Substructure Route 43 Stream. Located 0.02 of a mile northeast of South $300,000 Rehabilitation Main Street. HCP 3

023513.00 Highway Safety and Spot Improvements Cross culvert (#159147) located 0.37 of a mile north 2019/20 Athens Route 151 $400,000 of Leavitt Road. HCP 4 Large Culvert Replacement

WR 35736 Department Building and Lot 2018 Athens Maintenance Route 150 Paving the Athens Maintenance Lot (#55271). $75,000

HCP 3

WR 32903 Ditching beginning 1.20 miles south of Stagecoach Athens, Brighton Drainage Maintenance Road extending south 0.66 of a mile toward Hill 2018 Route 151 $25,000 Plt Road. Ditching beginning at Leavitt Road extending HCP 4 north 0.66 of a mile toward Bunker Hill Road.

130

0123456789 ID/Year Municipality Scope Name Description Funding

Bangor, Carmel, Etna, Hampden, 021764.00 Howland, Newburgh, 2018 Newport, Old Interstate 95 Interstate 95 Bridges from Pittsfield to T2 R8. $1,674,063 Town, Orono, Bridge Protective Coating Bridges HCP 6, 1, 4, Palmyra, 3, 2 Pittsfield, Plymouth, T2 R8 NWP

022288.00 Austin Stream Bridge (#2027) over Austin Stream. 2019/20 Bingham Route 201 $550,000 Bridge Painting Located 0.04 of a mile north of Mayfield Road. HCP 2

WR 34746 Drainage Maintenance Ditching beginning at Savage Road extending north 2018 Bingham Route 201 $30,000 2.14 miles to Mahoney Hill Road. HCP 2

WR 34755 Cleaning under guard rail beginning at the junction of Bingham, Drainage Maintenance 2018 Route 16 Route 201 extending north 0.51 of a mile to the $17,000 Moscow junction of Stream Road. HCP 4

Highway Safety and Spot 022835.00 Improvements Large culvert (#46672) located 0.67 of a mile west of 2018 Brighton Plt Route 154 $50,000 the Wellington town line. Large Culvert Improvements - HCP 4 PE Only

022290.00 Burnham, Eel Weir Bridge (#6209) over . 2018 Mount Road $350,000 Pittsfield Scour Countermeasures Located on the Pittsfield-Burnham town line. HCP 6

021878.00 Canaan Bridge (#2120) over Carrabassett Stream. 2018 Canaan Route 2 $1,500,000 Bridge Replacement Located 0.05 of a mile east of Easy Street. HCP 1

022226.00 Hall Bridge (#3159) over Black Stream. Located 0.47 2019/20 Canaan Route 23 $2,000,000 Bridge Replacement of a mile north of Browns Corner Road. HCP 4

WR 32902 Drainage Maintenance Replacing culvert (#167013) and ditching beginning 2018 Canaan Route 23 at Pine Valley Road extending north 1.21 miles to $11,000 Browns Corner Road. HCP 4

WR 35241 Bridge and Structural Replacing joints on Nickerson Bridge (#5551) over 2018 Canaan Maintenance Route 23 Carrabassett Stream. Located 0.77 of a mile from $91,000 the intersection of Route 2. HCP 4

131

0123456789 ID/Year Municipality Scope Name Description Funding

021775.00 Highway Safety and Spot Improvements Beginning 0.05 of a mile east of the Athens town line 2018 Cornville Route 43 $100,000 and extending easterly 0.30 of a mile. HCP 4 Highway Rehabilitation

WR 34592 Ditching in Cornville on the West Ridge Road from West Ridge Cornville, Drainage Maintenance the junction of Route 150 to the Skowhegan town 2018 Road, Malbon $35,000 Skowhegan line. Ditching on the Malbon Mills Road from the Mills Road HCP 4 Cornville town line to the junction of Prescott Lane.

023685.00 Dennistown Plt, Highway Paving Jackman, Beginning 0.24 of a mile south of the 2019/20 Route 201 $6,790,354 Moose River, town line and extending northerly 14.30 miles. Cold-In-Place Recycle HCP 2 Sandy Bay Twp

023659.00 Village Bridge (#3309) over East Branch Sebasticook 2018 Detroit Route 69 River. Located 0.26 of a mile northwest of Troy $200,000 Bridge Improvements - PE Only Road. HCP 4

WR 32758 Drainage work, ditiching and replacing cross culverts Detroit, Pittsfield, Drainage Maintenance 2018 Route 69 between the intersection of Route 100 in Pittsfield $94,000 Plymouth and Route 7 in Plymouth Village. HCP 4

021689.00 Embden Pond Hancock Bridge (#3372) over . 2018 Embden $840,000 Bridge Replacement Road Located 1.89 miles north of Cross Town Road. HCP 6

021719.00 Embden-Solon Bridge (#2267) over the Kennebec 2018 Embden, Solon Route 201A $750,000 Bridge Painting River. Located at the Embden-Solon town line. HCP 3

021743.00 Snakeroot Road/ I-95 Bridge (#5983) over Interstate 95. Located 1.12 miles south of Taylor Road. West 2018 Etna, Pittsfield Snakeroot Road $850,000 Bridge Wearing Surface Etna Road/ I-95 Bridge (#5961) over Interstate 95. Replacement HCP 6 Located 0.61 of a mile north of Route 69.

022306.00 I-95 Over 201 Bridge (#5820) over Route 201. 2019/20 Fairfield Interstate 95 $800,000 Bridge Painting Located on Exit #133 Interstate 95 northbound. HCP 1

022308.00 Western Avenue/ I-95 Bridge (#5819) over Interstate 2019/20 Fairfield Western Avenue $500,000 Bridge Painting 95. Located 0.34 of a mile west of Industrial Road. HCP 2

132

0123456789 ID/Year Municipality Scope Name Description Funding

Highway Safety and Spot 022855.00 Improvements Beginning 0.56 of a mile north of Route 139 and 2018 Fairfield Interstate 95 NB $130,000 extending northerly 0.36 of a mile. Guard Rail Installation And HCP 1 Replacement

023360.00 Highway Paving Beginning at Route 104 and extending north 3.95 2019 Fairfield Route 23 $144,491 miles to Route 201. Light Capital Paving HCP 4

WR 34809 Department Building and Lot 2018 Fairfield Maintenance Route 201 Paving the Fairfield Maintenance Lot (#55131). $35,000

HCP 2

020382.10 Highway Construction/ Beginning at the south bridge abutment of the C.A. Fairfield, Rehabilitation Clauson SB Bridge and extending southerly 3.38 2018 Interstate 95 SB $3,063,852 Waterville miles to the southern end of the I-95 SB/ Main Street HCP 1 Cold-In-Place Recycle Bridge.

Aviation 018696.01 Safety and infrastructure improvements that may Newton Field Jackman Planning And Research include an Airport Master Plan Update with a Wildlife $154,500 2018 Airport Hazard Site Visit at the Newton Field Airport (59B). Planning Studies

Aviation 018696.02 Safety and infrastructure improvements that may Airport Buildings Newton Field Jackman include an easement acquisition at the Newton Field $154,500 2018 Airport Sale Or Purchase Of Lot Or Airport (59B). Building

Aviation 018696.03 Safety and infrastructure improvements that may Newton Field include an environmental assessment and permitting Jackman Planning And Research $154,500 2019/20 Airport for master plan projects at the Newton Field Airport Planning Studies (59B).

Aviation 018696.04 Safety and infrastructure improvements that may Airport Buildings Newton Field Jackman include land acquisition at the Newton Field Airport $154,500 2019/20 Airport Sale Or Purchase Of Lot Or (59B). Building

Aviation 018696.05 Safety and infrastructure improvements that may Newton Field Jackman Navigation Aids/Lights include obstruction removal at the Newton Field $154,500 2019/20 Airport Airport (59B). Removal Of Obstructions

022330.00 Parlin Stream No. 2 Bridge (#6025) over Parlin Pond 2019/20 Long Pond Twp Route 6 Stream. Located 3.14 miles west of the Sandwich $250,000 Bridge Painting Academy Grant Twp. town line. HCP 3

133

0123456789 ID/Year Municipality Scope Name Description Funding

023637.00 Parlin Stream No. 2 Bridge (#6025) over Parlin 2019/20 Long Pond Twp Bridge Substructure Route 6 Stream. Located 3.14 miles west of the Sandwich $200,000 Rehabilitation Academy Grant Twp. town line. HCP 3

023312.00 Highway Paving Beginning 0.08 of a mile northwest of the Skowhegan 2018 Madison, Solon Route 201 $2,433,262 Ultra Thin Bonded Wearing town line and extending northwesterly 13.12 miles. HCP 2 Surface

020536.10 Construct rock weirs for fish passage downstream of 2019/20 Mayfield Twp Route 16 Mayfield Bridge (#2525) over Bigelow Brook. $41,300 Drainage Improvements Located 0.03 of a mile east of Athens Road. HCP 4

022926.00 Highway Safety and Spot Improvements Located at the intersection of Route 2 and Beech Hill 2019/20 Mercer Route 2 $55,000 Road. HCP 1 Flashing Beacon

021828.00 Highway Construction/ Mercer, Rehabilitation Beginning at Route 8 and extending northwest 4.62 2018 Route 137 $395,000 Smithfield miles to Route 2. HCP 4 PMRAP DOT Pugmill

021828.10 Highway Construction/ Mercer, Rehabilitation Beginning at Route 8 and extending northwest 4.62 2018 Route 137 $780,000 Smithfield miles to Route 2. HCP 4 PMRAP Laydown/Surface HMA

WR 31075 Producing, hauling and providing additional support Mercer, PMRAP activities for the placement of plant mix recycled 2018 Route 137 $400,000 Smithfield asphalt pavement (PMRAP) beginning at Route 8 HCP 4 and extending northwest 4.62 miles to Route 2.

WR 32150 Bridge and Structural Replacing the concrete wearing surface on the Chase Stream Bridge (#3992) over Chase Stream. Moscow Maintenance Stream Road $75,000 2018 Located 0.45 of a mile north of intersection of Beaudoin Road.

021888.00 Proctor Brook Bridge (#5943) over Proctor Brook. 2018 New Portland Route 16 $200,000 Bridge Culvert Rehabilitation Located 0.27 of a mile northwest of Tower Road. HCP 3

022254.00 Carrabassett Bridge (#5131) over the Carrabassett 2019/20 New Portland Route 146 River. Located 0.02 of a mile north of New Portland $1,250,000 Bridge Deck Replacement Road. HCP 4

134

0123456789 ID/Year Municipality Scope Name Description Funding

023631.00 New Great Works Bridge (#5718) over Lemon 2019/20 New Portland Bridge Wearing Surface Route 27 Stream. Located 0.06 of a mile south of Colegrove $75,000 Replacement Road. HCP 2

WR 35258 Bridge and Structural Replacing wearing surface on the Wire Bridge Wire Bridge New Portland Maintenance (#3383) over the . Located 0.15 of $55,000 2018 Road a mile north of Stone Wall Drive.

Highway Safety and Spot 023689.00 Improvements Newport, Beginning at the Palmyra town line and extending 2018 Route 2 $250,000 Palmyra east 0.22 of a mile. Safety Improvements - PE HCP 1 Only

Aviation 018700.02 Safety and infrastructure improvements that may Central Maine Norridgewock Navigation Aids/Lights include obstruction removal for Runway 3-21 at the $154,500 2019/20 Regional Airport Central Maine Regional Airport (OWK). Removal Of Obstructions

Aviation 018700.03 Safety and infrastructure improvements that may Central Maine include design, permitting and construction of Norridgewock Runway/Taxiway $536,630 2019/20 Regional Airport taxilanes at the Central Maine Regional Airport New Construction (OWK).

Aviation 018700.16 Safety and infrastructure improvements that may Central Maine include an environmental assessment for master Norridgewock Planning And Research $154,500 2019/20 Regional Airport plan projects at the Central Maine Regional Airport Planning Studies (OWK).

023691.00 Highway Safety and Spot Improvements Located at the intersection of Route 2 and Bridge 2019/20 Norridgewock Route 2 $211,500 Street. HCP 1 Traffic Signals

022256.00 Hanson Bridge (#1035) over Smith Brook. Located 2018 Palmyra Palmyra Road $115,000 Bridge Improvements - PE Only 0.34 of a mile south of Spring Hill Road. HCP 4

022954.00 Highway Safety and Spot Improvements Located at the intersection of Route 2 and Route 2018 Palmyra Route 2 $50,000 152. HCP 1 Planning Studies - PE Only

023653.00 Thomas Jay Merry Memorial Bridge (#2404) over 2019/20 Palmyra Bridge Wearing Surface Repair Route 2 Sebasticook River. Located 0.19 of a mile southwest $150,000 /Mill & Fill of Raymond Road. HCP 1

135

0123456789 ID/Year Municipality Scope Name Description Funding

022110.00 Highway Paving Palmyra, Madawaska Beginning at North Main Street and extending north 2018 $138,768 Pittsfield Road 3.92 miles to Route 2. Light Capital Paving HCP 4

WR 33698 Surface and Base Maintenance Repairing surface on the southern approach slab on 2018 Parlin Pond Twp Route 201 Piel Bridge (#2993) over Piel Brook. Located 0.35 of $45,000 a mile north of the Johnson Mountain Twp. town line. HCP 2

Aviation 018703.00 Safety and infrastructure improvements that may Pittsfield include design, permitting and construction of an 8 Pittsfield Airport Buildings $797,220 2019/20 Municipal Airport bay nested T-Hangar at the Pittsfield Municipal New Construction Airport (2B7).

021741.00 I- 95 NB/ North Main Street Bridge (#5989) over 2018 Pittsfield Interstate 95 NB North Main Street. Located 0.26 of a mile south of $550,000 Bridge Rehabilitation the Palmyra town line. HCP 1

021742.00 Waverley Bridge (#5279) over Sebasticook River. 2018 Pittsfield Waverly Street $200,000 Bridge Substructure Located 0.18 of a mile east of Route 152. Rehabilitation HCP 6

021812.00 Highway Construction/ Rehabilitation Beginning 0.02 of a mile south of Nichols Street and 2019/20 Pittsfield Route 11 $617,500 extending northerly 1.81 miles. HCP 3 Highway Rehabilitation

022110.00 Highway Paving Beginning at Main Street and extending east 0.38 of 2018 Pittsfield Peltoma Avenue $13,452 a mile to Harrison Street. Light Capital Paving HCP 4

022110.00 Highway Paving Phillips Corner Beginning at I-95 southbound off-ramp extending 2018 Pittsfield $113,280 Road north to Route 2. Light Capital Paving HCP 4

Public Transportation 022172.00 Pittsfield Design, pave, stripe, and sign a new Park and Ride Pittsfield Parking Lots $99,403 2019/20 Shopping Plaza facility located in the Pittsfield Shopping Plaza. New Construction

023603.00 I-95 SB/ Route 152 & MCRR Bridge (#5986) over 2019/20 Pittsfield Interstate 95 SB Route 152. Located 1.24 miles west of the Palmyra $2,500,000 Bridge Deck Replacement town line. HCP 1

136

0123456789 ID/Year Municipality Scope Name Description Funding

023607.00 I-95 NB/ North Main Street Bridge (#5989) over 2019/20 Pittsfield Interstate 95 NB Madawaska Road. Located 0.38 of a mile west of the $1,000,000 Bridge Deck Replacement Palmyra town line. HCP 1

023609.00 I-95 SB/ North Main Street Bridge (#1445) over 2019/20 Pittsfield Interstate 95 SB Madawaska Avenue. Located 0.36 of a mile west of $2,200,000 Bridge Rehabilitation the Palmyra town line. HCP 1

023613.00 I-95 SB/ Sebasticook River Bridge (#1446) over 2019/20 Pittsfield Interstate 95 SB Interstate 95 southbound. Located 1.06 of a mile of $3,600,000 Bridge Rehabilitation the Palmyra town line. HCP 1

WR 34612 Drainage Maintenance Repair inlet on large culvert (#46591) located 0.05 of 2018 Ripley Route 154 $5,000 a mile west of Controversy Drive. HCP 4

WR 34588 Drainage Maintenance Ditching from the junction of Route 23 to the Palmyra 2018 Saint Albans Palmyra Road $24,000 town line. HCP 4

016869.00 West Ridge Bridge (#3773) over West Branch Malbons Mills 2018 Skowhegan Wesserunsett Stream. Located 0.14 of a mile north $150,000 Road Bridge Painting of Notch Road. HCP 4

021749.00 Margaret Chase Smith South Bridge (#2785) over 2018 Skowhegan Bridge Wearing Surface Route 201 the Kennebec River. Located 0.05 of a mile $400,000 Replacement northeast of Mill Street. HCP 1

021750.00 Margaret Chase Smith North Bridge (#2617) over the 2018 Skowhegan Bridge Wearing Surface Route 2 Kennebec River. Located 0.04 of a mile south of $400,000 Replacement Madison Avenue. HCP 1

Highway Safety and Spot 022978.00 Improvements Large culvert (#47168) located 0.09 of a mile north of 2018 Skowhegan Route 104 $95,000 Heritage Drive. Large Culvert Improvements - HCP 3 PE Only

Freight 023260.00 Springfield Replacement of Bridge (#91.15) located on the Skowhegan Line $467,275 2018 Terminal Railway Hinckley Branch. Rehabilitation

137

0123456789 ID/Year Municipality Scope Name Description Funding

WR 32291 Bridge and Structural Repairing west pier on the Wesserunsett Bridge 2018 Skowhegan Maintenance Route 2 (#2924) over Wesserunsett Stream. Located 0.10 of $50,000 a mile west of Dudley Corner Road. HCP 1

WR 32887 Drainage Maintenance Repair cross culvert (#970379) located 0.03 miles 2018 Skowhegan Route 2 $34,000 east of the junction of Route 2 and Lambert Road. HCP 1

WR 32901 Ditching beginning 0.5 miles east of the intersection Drainage Maintenance of Route 2 and River Road extending to the Eaton 2018 Skowhegan Route 2 $50,000 Mountain Road. Continuing 0.5 miles east of Lambert HCP 1 Road to the Skowhegan-Canaan town line.

WR 35259 Bridge and Structural Painting bearings and beam ends on Smith Pond Bridge (#6152) over the west branch of Cold Brook. 2018 Skowhegan Maintenance Route 150 $20,000 Located 0.37 of a mile south of the Cornville town HCP 3 line.

022260.00 Main Street Bridge (#2504) over Fall Brook. Located 2019/20 Solon Route 201 $2,000,000 Bridge Replacement 0.01 of a mile west of Brook Street. HCP 2

022362.00 The Forks Bridge (#2841) over the Upper Kennebec The Forks Plt, 2019/20 Route 201 River. Located 0.03 of a mile north of Lake Moxie $800,000 West Forks Plt Bridge Rehabilitation Road. HCP 2

138

0123456789 Waldo

Burnham Troy Winterport

Jackson Monroe Frankfort Unity Thorndike

Prospect

Brooks Knox Swanville Stockton Freedom Springs

Searsport Waldo

Montville Morrill

Palermo Belfast

Belmont Liberty Searsmont Northport Waldo

Lincolnville

Waldo County Population 38,786

Islesboro Land Area (sq mi) 730 Islesboro Bridges 173 Highway Corridor Priority Miles HCP 1 6 4 HCP 2 20 HCP 3 99 HCP 4 1 90

Total HCP 1-4 3 73 Waldo ID/Year Municipality Scope Name Description Funding

Aviation 018685.01 Safety and infrastructure improvements that may Belfast Municipal Belfast Navigation Aids/Lights include obstruction removal - Phase 2, Runway 33 at $221,450 2019/20 Airport the Belfast Municipal Airport (BST). Removal Of Obstructions

Aviation 018685.17 Safety and infrastructure improvements that may Belfast Municipal include final design, permitting, geotech and Belfast Runway/Taxiway $6,695,000 2018 Airport construction for Runway 15 partial Parallel Taxiway New Construction at the Belfast Municipal Airport (BST).

021666.00 Sheldon Bridge (#5557) over Warren Brook. Located 2019/20 Belfast Poors Mill Road $700,000 Bridge Culvert Replacement 0.89 of a mile east of Shepard Road. HCP 4

021874.00 Goose River Bridge (#2319) over Goose River. 2019/20 Belfast Route 1 $1,100,000 Bridge Replacement Located 0.15 of a mile east of Mitchell Street. HCP 1

022683.00 Highway Safety and Spot Improvements Located at the intersection of Route 1 and the Route 2018 Belfast Route 1 $764,000 7 southbound off-ramp. HCP 1 Safety Improvements

WR 34871 Bridge and Structural Replacing the bridge joint on the northern end of the Route 1/ Route 3 Bridge (#1378) over Route 3. 2018 Belfast Maintenance Route 1 $65,000 Located 0.4 of a mile south of the Route 52 HCP 1 intersection.

WR 35149 Ditching and repairing two culverts (#133442, Drainage Maintenance #209842) beginning at the Northport Avenue 2018 Belfast Route 1 intersection extending northeast 6.86 miles to 0.09 of $14,800 a mile northerly of the Searsport Road intersection in HCP 1 Searsport.

WR 35136 Ditching and culvert (#132496) replacement and Drainage Maintenance catch basin (#140457) repair on Route 1 beginning at 2018 Belfast, Camden Route 52 $18,000 the Rockport-Camden town line extending 22.12 HCP 1, 3 miles to the Porter Road in Belfast.

WR 35140 Ditching, cleaning under guard rail and replacing one Belfast, Monroe, Drainage Maintenance culvert (#212688) on Route 141 beginning in Belfast 2018 Route 141 $24,060 Swanville at the intersection of Route 1 extending north 13.17 HCP 4 miles to the Route 139 intersection in Monroe.

022092.00 Highway Paving Beginning at Route 137 and extending east 4.02 2018 Brooks, Knox Webb Road $141,336 miles to Route 139. Light Capital Paving HCP 4

139

0123456789 ID/Year Municipality Scope Name Description Funding

WR 35146 Ditching and cleaning under guard rail on Route 139 Brooks, Drainage Maintenance Winterport, beginning in Brooks at the Route 7 intersection 2018 $20,000 Winterport Monroe, Brooks extending northeast 15.3 miles to the Route 69 HCP 4 intersection in Winterport.

022092.00 Highway Paving South Horseback Beginning at the Unity town line and extending north 2018 Burnham $140,281 Road 3.99 miles to Troy Road. Light Capital Paving HCP 4

022092.00 Highway Paving Beginning at Route 11 and extending east 6.08 miles 2018 Burnham Troy Road $213,762 to the Troy town line. Light Capital Paving HCP 4

WR 34903 Bridge and Structural Repairing curb, paving approaches and installing new guard rail and painting bridge rail on the Village 2018 Burnham Maintenance Troy Road $50,000 Bridge (#5257) over the Sebasticook River. Located HCP 4 0.06 miles east of the Route 11 intersection.

022334.00 Lord Bridge (#3348) over Marsh Stream. Located 2019/20 Frankfort Stream Road $300,000 Bridge Deck Replacement 0.03 of a mile west of Marsh Stream Road. HCP 6

022865.00 Highway Safety and Spot Improvements Large culvert (#46841) located 0.14 of a mile west of 2019/20 Frankfort Loggin Road $400,000 Old Stage Road. HCP 4 Large Culvert Replacement

022867.00 Highway Safety and Spot Improvements Large culvert (#46840) located 0.21 of a mile west of 2019/20 Frankfort Loggin Road $415,000 the West Hill Road. HCP 4 Large Culvert Improvements

WR 35142 Ditching and replacing two entrance culverts Frankfort, Drainage Maintenance North Searsport 2018 beginning at the Route 1 intersection extending north $22,000 Searsport Road 11.58 miles to the Loggin Road in Frankfort. HCP 4

022092.00 Highway Paving Beginning at the Albion town line and extending 2018 Freedom Albion Road $21,095 southeast 0.60 of a mile to North Palermo Road. Light Capital Paving HCP 4

Highway Safety and Spot 022869.00 Improvements Large culvert (#94422) located 0.22 of a mile 2018 Freedom Palermo Road $40,000 northeast of Sibley Road. Large Culvert Improvements - HCP 4 PE Only

140

0123456789 ID/Year Municipality Scope Name Description Funding

022092.00 Highway Paving Freedom, Freedom Pond Beginning at Route 220 and extending northwest 2018 $68,910 Montville Road 1.96 miles to Route 137. Light Capital Paving HCP 4

022092.00 Highway Paving Freedom, North Palermo Beginning at the China town line and extending north 2018 $390,959 Palermo Road 11.12 miles to Route 137. Light Capital Paving HCP 4

Marine 023484.00 Islesboro Ferry Islesboro Piers, Floats And Fenders Wave fence and crib improvements. $750,000 2019/20 Slip Rehabilitation

WR 35147 Custodial Maintenance Brush and tree removal beginning at Gilkey's Harbor 2018 Islesboro Ferry Road Boat Launch extending north 1.15 miles to the West $15,370 Bay Road-Mill Creek Road intersection. HCP 4

023567.00 Great Farm Bridge (#3128) over Great Farm Brook. 2019/20 Jackson Route 7 $250,000 Bridge Rehabilitation Located 0.12 of a mile south of Great Farm Road. HCP 3

WR 35439 Drainage Maintenance Replacing two instream culverts (#153908, #131738) 2018 Knox Webb Road located 0.10 of a mile east of Old Country Road and $200,000 0.36 of a mile easterly of Route 137. HCP 4

WR 35237 Drainage Maintenance Ditching and replacing culverts beginning at Beans 2018 Knox, Montville Route 220 Corner extending north 5.58 miles to the Route 137 $125,000 intersection in Knox. HCP 4

023380.00 Highway Paving Liberty, Beginning at Route 173 and extending northeast 2019 Trues Pond Road $65,477 Montville 1.79 miles to Route 3. Light Capital Paving HCP 4

022092.00 Highway Paving Beginning at Route 3 and extending northeast 2.36 2018 Morrill Higgins Hill Road $82,973 miles to Route 131. Light Capital Paving HCP 4

022436.00 Highway Paving Beginning 0.46 of a mile east of Spruce Head Lane 2019/20 Northport Route 1 $1,298,056 and extending northeasterly 4.59 miles. Mill And Fill HCP 1

141

0123456789 ID/Year Municipality Scope Name Description Funding

021739.00 Sheepscot Bridge (#2758) over the . 2018 Palermo Route 3 $250,000 Bridge Wearing Surface Located 0.15 of a mile east of Level Hill Road. Replacement HCP 1

022092.00 Highway Paving Branch Mills Beginning at Route 3 and extending north 0.91 of a 2018 Palermo $31,994 Road mile. Light Capital Paving HCP 4

Highway Safety and Spot 022966.00 Improvements 2018 Prospect Route 1 Located 0.20 of a mile north of Switzer Spring Road. $75,000 Slope Stabilization/Protection - HCP 1 PE Only

WR 34092 Operational and Safety Intalling new guard rail and attachments on Hawes 2018 Prospect Maintenance Hawes Road Bridge (#2358) over Hawes Stream. Located 0.50 of $15,000 a mile west of Route 1A. HCP 4

WR 35141 Drainage Maintenance Ditching and replacing two entrance culverts 2018 Prospect Route 174 beginning at the Route 1A intersection extending $24,680 northeast 3.82 miles to the Route 1 intersection. HCP 3

023314.00 Highway Paving Prospect, Beginning 0.08 of a mile north of Devereux Cove 2018 Route 1 $998,283 Stockton Springs Ultra Thin Bonded Wearing Road and extending northeasterly 4.83 miles. HCP 1 Surface

018523.18 MaineDOT Multimodal System Prospect, Operations Operating costs at the Penobscot Narrows 2018 Observatory $150,000 Verona Island Observatory. HCP 1 Operating Assistance

018523.19 MaineDOT Multimodal System Prospect, Operations Operating costs at the Penobscot Narrows 2019 Observatory $150,000 Verona Island Observatory. HCP 1 Operating Assistance

018523.20 MaineDOT Multimodal System Prospect, Operations Operating costs at the Penobscot Narrows 2020 Observatory $150,000 Verona Island Observatory. HCP 1 Operating Assistance

021748.00 Bickford Bridge (#5574) over Maple Meadow Stream. 2018 Searsmont Route 173 $200,000 Bridge Culvert Rehabilitation Located 0.08 of a mile north of Lawry Road. HCP 4

142

0123456789 ID/Year Municipality Scope Name Description Funding

017281.00 Highway Construction/ Rehabilitation Beginning at Savage Road and extending northeast 2019/20 Searsport Route 1 $5,000,000 1.85 miles. HCP 1 Reconstruction

Marine 020804.00 Material handling equipment at Mack Point, including Searsport Marine Buildings Mack Point modifications to the crane, conveyor system, ram $3,666,437 2019/20 revolver, rail and electrical. New Construction

Marine 020805.00 Searsport The commercial channel of Searsport, which serves Searsport Channels, Pier Berths $5,500,000 2018 Channel Mack Point. Dredging

Freight 023254.00 GAC Chemical Construct new turnout and 550' of new track and Searsport Line $172,200 2018 Corporation crossing. Rehabilitation

Highway Safety and Spot 023751.00 Improvements Mount Ephram Large culvert (#46842) located 0.15 of a mile north of 2018 Searsport $50,000 Road Route 1. Large Culvert Replacement - HCP 4 PE Only

022468.00 Highway Paving Searsport, Beginning 0.13 of a mile northeast of Trundy Road 2019/20 Route 1 $1,787,285 Stockton Springs and extending northeasterly 4.43 miles. 1 1/4" Overlay HCP 1

021831.00 Highway Safety and Spot Improvements Large culvert (#94441) located 0.09 of a mile north of 2019/20 Stockton Springs Route 1 $1,399,000 Muskrat Farm Road. HCP 1 Large Culvert Replacement

Highway Safety and Spot 023779.00 Improvements Large culvert (#46702) located 0.03 of a mile north of 2018 Stockton Springs Route 1 $50,000 the Searsport town line. Large Culvert Replacement - HCP 1 PE Only

Highway Safety and Spot 023012.00 Improvements 2018 Swanville Route 141 Located 1.10 miles north of Town House Road. $75,000 Slope Stabilization/Protection - HCP 4 PE Only

022092.00 Highway Paving Beginning at the Burnham town line and extending 2018 Troy Burnham Road $37,619 southeast 1.07 miles to Route 220. Light Capital Paving HCP 4

143

0123456789 ID/Year Municipality Scope Name Description Funding

023360.00 Highway Paving Beginning at Route 9 and extending north 1.62 miles 2019 Troy Rodgers Road $59,260 to Route 220. Light Capital Paving HCP 4

WR 35026 Drainage Maintenance Ditching beginning at the Burnham-Troy town line 2018 Troy Troy Road and extending east 1.07 miles to the Route 220 $10,100 intersection. HCP 4

WR 35029 Drainage Maintenance Ditching and replacing six culverts beginning at the 2018 Troy Rogers Road Troy Center Road intersection extending 1.64 south $101,000 miles to the Route 202 intersection. HCP 4

022092.00 Highway Paving Beginning at Route 139 and extending north 1.67 2018 Unity Prairie Road $58,714 miles to the Burnham town line. Light Capital Paving HCP 4

023270.00

2018 Waldo Route 137 Located 0.24 of a mile southeast of Birches Road. $100,000 Drainage Improvements HCP 3

WR 33375 Drainage Maintenance Replacing a large culvert (#46030) located 0.62 of a 2018 Winterport Route 139 $135,000 mile northwest of the Goshen Road intersection. HCP 4

WR 35144 Drainage Maintenance Cleaning under guard rail beginning at the 2018 Winterport Route 69 intersection of Route 1A extending north 5.75 miles $20,200 to the Winterport-Hampden town line. HCP 3

144

0123456789 Washington

Forest City Twp T8 R4 Danforth NBPP T11 R3 Washington County Forest NBPP Twp Vanceboro Population 32,856 Brookton T8 R3 Twp Lambert Land Area (sq mi) 2,563 NBPP Lake Twp Bridges 174

Codyville Highway Corridor Priority Miles Topsfield Plt HCP 1 5 2 Kossuth Twp Dyer Twp HCP 2 103 HCP 3 1 48 Waite HCP 4 25 1 Talmadge Fowler T6 R1 Twp NBPP Total HCP 1-4 5 54 Indian Twp Res T6 ND Grand Lake BPP Stream Plt Sakom Twp Princeton

Big Greenlaw Calais T43 MD Lake Baileyville Chopping BPP Twp T42 MD Twp Baring BPP Alexander Plt Robbinston Meddybem ps Crawford T37 MD T26 ED T36 MD BPP BPP Charlotte BPP Cooper Perry Pembroke T19 ED Day Block BPP Dennysville Twp Cathance T30 MD Wesley Twp Devereaux BPP Twp Berry Edmunds Twp T25 MD Twp BPP Marion T24 MD Northfield Twp Beddington BPP Lubec East Trescott T19 MD Machias Twp BPP Whiting T18 MD Centerville BPP Marshfield Deblois Twp C olum bia M ac hias Cutler Falls Columbia Jonesboro

Cherryfield Roque Bluffs

Harrington Jonesport

Milbridge Addison Washington

Steuben Washington ID/Year Municipality Scope Name Description Funding

016849.00 Dyke Bridge (#3718) over West Branch Pleasant 2019/20 Addison Ridge Road River. Located 0.06 of a mile southwest of Water $2,015,000 Bridge Replacement Street. HCP 6

023358.00 Highway Paving Addison, Beginning at Water Street and extending north 2.67 2019 Point Street $58,427 Columbia Falls miles to Route 1. Light Capital Paving HCP 4

022106.00 Addison, Highway Paving Columbia Falls, Beginning at Route 1 in Columbia Falls, extending to 2018 Route 187 $809,598 Jonesboro, Route 1 in Jonesboro. Light Capital Paving HCP 4 Jonesport

WR 34204 Grading shoulders, replacing culverts, and ditching Addison, Drainage Maintenance beginning at the south side of Pleasant River Bridge 2018 Water Street $104,000 Columbia extending 2.79 miles to the intersection of Route 1 in HCP 4 Columbia.

WR 34211 Ditching, replacing and lowering culverts, and Addison, Drainage Maintenance Point Street, grading shoulders beginning at the intersection of 2018 $107,000 Columbia Falls Main Street Water Street extending north 2.67 miles to the HCP 4 intersection of Route 1 in Columbia Falls.

022400.00 Alexander, Highway Paving Baileyville, Beginning 0.28 of a mile north of Sucker Brook Road 2019/20 Route 9 $4,425,041 Baring Plt, and extending northerly 13.81 miles. 1 1/4" Overlay HCP 1 Crawford

WR 35311 Drainage Maintenance Grader ditching and changing drainage structures on 2018 Baileyville Access Road $27,000 the Access Road in the town of Baileyville. HCP 4

Main Street WR 34355 Raising catch basin covers flush with pavement on Baileyville, South Baileyville, Drainage Maintenance Main Street in Baileyville, South Street in Calais, and 2018 Street and North $77,000 Calais North Street Extension in Calais. Ditching lower half Street Extension of Main Street in Baileyville. HCP 3, 4 Calais

WR 32705 Bridge and Structural Mill and fill wearing surface, paint beam ends and seal concrete on Blacks Tannery Bridge (#5648) over 2018 Beddington Maintenance Route 9 $91,000 . Located 0.02 of a mile west of HCP 1 E. Beddington Lake Road.

023358.00 Beddington, Highway Paving Beginning at Route 1 and extending north 19.08 2019 Cherryfield, Route 193 $417,523 miles to Route 9. Deblois, T22 MD Light Capital Paving HCP 3

145

0123456789 ID/Year Municipality Scope Name Description Funding

023527.00 Beddington, Highway Paving Beginning 0.23 of a mile south of the Devereaux Devereaux Twp, 2019/20 Route 9 Twp.-Beddington town line and extending northerly $3,365,360 T24 MD BPP, 1 1/4" Overlay 8.50 miles. HCP 1 T30 MD BPP

WR 34931 Grading, excavator ditching and culvert replacement Beddington, Drainage Maintenance beginning at the intersection of Route 1 in Cherryfield 2018 Cherryfield, Route 193 $451,000 extending north to the Deblois - Beddington town Deblois HCP 3 line.

WR 34604 Ditching and culvert replacement beginning at the Beddington, T22 Drainage Maintenance 2018 Route 193 Beddington - Deblois town line extending north to the $236,000 MD Route 9 intersection. HCP 3

023358.00 Highway Paving Big Lake Twp, Beginning at Big Lake Road and extending northeast 2019 West Street $90,595 Princeton 4.14 miles to Route 1. Light Capital Paving HCP 4

018853.00 Highway Safety and Spot Brookton Twp, Improvements Spot improvements along Route 1 beginning at 2018 Danforth, Route 1 $100,000 Route 6 and extending north 13.04 miles. Topsfield HCP 3 Highway Rehabilitation

022116.00 Brookton Twp, Highway Paving Beginning at Route 1 and extending northeast 11.94 2018 Forest City Twp, Forest City Road $563,764 miles. Forest Twp Light Capital Paving HCP 4

Marine 020841.00 North Street New floats including moorings, pump out station, Calais Piers, Floats And Fenders $139,375 2019/20 Floats power pedestals, and water to floats. New Construction

021846.00 Highway Safety and Spot Improvements Beginning at Main Street and extending south 0.41 of 2019/20 Calais Route 1 $200,000 a mile. HCP 2 Drainage Improvements

022649.00 Highway Safety and Spot Improvements 2019/20 Calais South Street Beginning 0.07 of a mile east of Washington Street. $100,000

HCP 4 Drainage Improvements

021686.00 Moosehorn Bridge (#3332) over Cranberry Creek. 2018 Charlotte Station Road $100,000 Enhanced Project Scoping - PE Located 0.17 of a mile west of Goodell Road. Only HCP 6

146

0123456789 ID/Year Municipality Scope Name Description Funding

022230.00 Schoodic Bridge (#3649) over Schoodic Brook. 2019/20 Cherryfield North Main Street $1,200,000 Bridge Replacement Located 0.32 of a mile south of the Deblois town line. HCP 3

022294.00 Covered Bridge (#2192) over the Narraguagus River. 2019/20 Cherryfield Route 1 $400,000 Bridge Wearing Surface Located 0.03 of a mile west of Main Street. Replacement HCP 3

Highway Construction/ 020405.00 Rehabilitation Cherryfield, Beginning 0.07 of a mile north of Spruce Street in 2018 Route 1 $400,000 Milbridge Milbridge and extending northerly 4.81 miles. Highway Improvements - PE HCP 3 Only

023358.00 Highway Paving Cherryfield, Beginning 0.15 of a mile north of Route 1A and 2019 Route 1 $105,256 Milbridge extending northerly 4.81 miles to Route 182. Light Capital Paving HCP 3

023362.00 Codyville Plt, Highway Paving Beginning 3.32 miles south of the Lambert Lake 2019 Lambert Lake Route 6 $549,066 Twp. town line and extending northerly 15.01 miles. Twp, Vanceboro Light Capital Paving HCP 3

023482.00 Highway Construction/ Codyville Plt, Rehabilitation Beginning at the intersection of Route 6 and Route 1 2019/20 Route 6 $1,602,500 Topsfield and extending northeast 6.41 miles. HCP 3 PMRAP DOT Pugmill

WR 35645 Producing, hauling and providing additional support activities for the placement of plant mix recycled Codyville Plt, PMRAP 2020 Route 6 asphalt pavement (PMRAP) beginning at the $650,000 Topsfield intersection of Route 6 and Route 1 and extending HCP 3 northeast 6.41 miles.

021772.00 Highway Safety and Spot Improvements Large culvert (#269581) located 0.35 of a mile 2019/20 Columbia Route 1 $580,000 southwest of the Columbia Falls town line. HCP 2 Large Culvert Replacement

WR 34208 Ditching, replacing culverts and grading shoulders Drainage Maintenance beginning at the intersection of Route 1 extending 2018 Columbia Station Road $113,000 west 2.84 miles to the intersection of Pea Ridge HCP 4 Road.

023358.00 Highway Paving Tibbetstown Beginning at Route 1 and extending north 4.81 2019 Columbia Falls $105,256 Road miles. Light Capital Paving HCP 4

147

0123456789 ID/Year Municipality Scope Name Description Funding

WR 34344 Ditching, replacing and repairing culverts, and Drainage Maintenance Tibbetstown 2018 Columbia Falls grading shoulders beginning at the intersection of $206,000 Road Route 1 extending west 4.81 miles. HCP 4

018949.00 Rocky Stream Bridge (#3620) over Rocky Brook. 2018 Crawford Route 9 $820,000 Bridge Culvert Replacement Located 1.72 miles west of the Love Lake Road. HCP 1

022106.00 Highway Paving 2018 Cutler Ridge Road Beginning at Route 191 extending west 1.12 miles. $39,648 Light Capital Paving HCP 4

022106.00 Cutler, East Highway Paving Machias, Beginning at Number Nine Road and extending 2018 Route 191 $468,342 Machiasport, northwest 13.23 miles to Route 1. Light Capital Paving HCP 4 Whiting

023358.00 Highway Paving Cutler, Lubec, Beginning 6.63 miles south of Whiting town line and 2019 Route 191 $301,764 Trescott Twp extending northerly 13.79 miles to Route 189. Light Capital Paving HCP 4

WR 33677 Dixie Road, Ditching and replacing drainage structures on Route Cutler, Lubec, Drainage Maintenance 2018 Number Nine 191 from the intersection of Route 189 to the $111,000 Trescott Twp Road intersection of the Cove Road. HCP 4

021716.00 Town Bridge (#5461) over Baskahegan Stream. 2018 Danforth Route 169 $400,000 Bridge Deck Replacement Located 0.07 of a mile east of Maple Street. HCP 4

022300.00 Town Bridge (#5461) over Baskahegan Stream. 2019/20 Danforth Route 169 $200,000 Bridge Painting Located 0.07 of a mile east of Maple Street. HCP 4

022849.00 Highway Safety and Spot Improvements Large culvert (#46692) located 0.12 of a mile north of 2019/20 Danforth Route 1 $430,000 the Brookton Twp. town line. HCP 3 Large Culvert Improvements

023362.00 Highway Paving Beginning at the Weston town line and extending 2019 Danforth Bancroft Road $29,264 south 0.80 of a mile to Route 169. Light Capital Paving HCP 4

148

0123456789 ID/Year Municipality Scope Name Description Funding

Day Block Twp, 020884.00 Beginning 1.93 miles south of the eastern most T24 T24 MD BPP, Highway Paving MD BPP - T30 MD BPP town line and extending 2018 T26 ED BPP, Route 9 $7,655,553 northerly 17.90 miles to 0.26 of a mile east of the T30 MD BPP, Hot In Place Recycled Wesley-T26 ED BPP town line. HCP 1 Wesley

WR 32546 Bridge and Structural Removing and installing slab overs on abuments and replacing two joints over the piers on 2018 Dennysville Maintenance Route 1 $170,000 Bridge (#5626) over Dennys River. Located 0.20 of HCP 2 a mile north of Belyea Road.

018968.00 Dennysville, Dennys River Bridge (#5626) over Dennys River. 2018 Route 1 $500,000 Edmunds Twp Bridge Substructure Located at the Edmunds Twp.- Dennysville town line. Rehabilitation HCP 2

019198.00 Highway Construction/ Rehabilitation Beginning at Pope Memorial Bridge (#2682) over the 2019/20 East Machias Route 1 $3,652,300 East and extending north 1.80 miles. HCP 2 Reconstruction

019416.00 Bicycle-Pedestrian Beginning at Hadley Lake Road and extending north 2019/20 East Machias Trail, On-Road Route 191 $136,500 0.10 of a mile to Elm Street School. HCP 4 New Construction

Aviation 018691.00 Safety and infrastructure improvements that may Eastport include construction of a snow removal equipment Eastport Airport Buildings $824,000 2019/20 Municipal Airport building with a Wildlife Hazard Site Visit at the New Construction Eastport Municipal Airport (EPM).

023038.00 Highway Safety and Spot Improvements Beginning at Deep Cove Road and extending east 2019/20 Eastport Route 190 $200,000 0.62 of a mile to Water Street. HCP 2 Drainage Improvements

018969.00 New Hobart Bridge (#5612) over New Hobart 2018 Edmunds Twp Bridge Substructure Route 1 Stream. Located 0.29 of a mile south of Belyea $500,000 Rehabilitation Road. HCP 2

023358.00 Grand Lake Highway Paving Grand Lake Beginning at Route 1 and extending southwest 10.16 2019 Stream Plt, $222,329 Stream Road miles. Indian Twp Res Light Capital Paving HCP 4

WR 35360 Grand Lake Drainage Maintenance Grand Lake Ditching and replacing drainage structures on the 2018 Stream Plt, $71,000 Stream Road Grand Lake Stream Road. Indian Twp Res HCP 4

149

0123456789 ID/Year Municipality Scope Name Description Funding

021693.00 Johnson Bridge (#3275) over Flat Bay River. 2019/20 Harrington Route 1A $900,000 Bridge Culvert Replacement Located 0.95 of a mile northeast of Oak Point Road. HCP 2

Highway Construction/ 022651.00 Rehabilitation Beginning at Route 1 in Milbridge and extending Harrington, north 0.16 of a mile. Beginning 0.25 of a mile north of 2018 Route 1A $290,000 Milbridge Cross Road in Milbridge and extending northerly 3.39 Highway Improvements - PE HCP 2 miles. Only

023392.00 Highway Paving Beginning 0.26 of a mile north of the southern Indian Twp Res, intersection of the U Road extending north 2.03 miles 2018 Route 1 $282,147 Waite Highway Cyclical Pavement to 0.70 of a mile north of the Indian Twp. Res. town HCP 3 Resurfacing line in Waite.

WR 34312 Indian Twp Res, Drainage Maintenance Ditching and replacing drainage structures on Route 2018 Houlton Road $96,000 Princeton 1 in Princeton and Indian Twp. Res. HCP 3

020845.00 Marine Development of a carry-in boat launch on the Chandler River with picnic area, interpretative signs, 2019/20 Jonesboro Piers, Floats And Fenders $124,000 Bridge and parking on the southeast side of the Chandler HCP 2 Rehabilitation River Bridge.

023557.00 Drisco Bridge (#3956) over Chandler River. Located 2019/20 Jonesboro Station Road $200,000 Bridge Substructure 0.13 of a mile northeast of Geel Lane. Rehabilitation HCP 6

WR 24524 Bridge and Structural Replacing wearing surface on Chandler River Bridge 2018 Jonesboro Maintenance Route 1 (#2149) over the Chandler River. Located 0.06 of a $110,000 mile north of Looks Point Road. HCP 2

023843.00 Highway Construction/ Beginning 0.82 of a mile west of the Topsfield and Kossuth Twp, Rehabilitation 2019/20 Route 6 Kosuth Twp town line and extending easterly 0.92 of $675,000 Topsfield a mile. HCP 3 Highway Rehabilitation

Bicycle-Pedestrian 018883.00 Trail, On-Road Beginning at Main Street extending east 0.36 of a 2019/20 Lubec Route 189 $320,000 mile to Water Street. Bicycle/Pedestrian HCP 3 Improvements

020497.00 FDR Memorial Bridge (#5978) over Lubec Narrows. 2018 Lubec Route 189 $450,000 Bridge Improvements - PE Only Located 0.11 of a mile northeast of Water Street. HCP 3

150

0123456789 ID/Year Municipality Scope Name Description Funding

021697.00 Mays Bridge (#2527) over Mays Stream. Located 2019/20 Lubec Route 189 $750,000 Bridge Culvert Replacement 0.10 of a mile west of Crows Neck Road. HCP 3

016714.00 Dyke Bridge (#2246) over . Located 2019/20 Machias Route 1 $2,400,000 Bridge Replacement 0.17 of a mile north of Route 1A. HCP 2

Aviation 018698.02 Safety and infrastructure improvements that may Machias Valley include the design and reconstruction of Runway 18- Machias Runway/Taxiway $4,326,000 2018 Regional Airport 36, lighting and taxiway at the Machias Valley Reconstruction Regional Airport (MVM).

Aviation 018698.04 Safety and infrastructure improvements that may Machias Valley Machias Runway/Taxiway include the construction of a fuel farm at the Machias $309,000 2019/20 Regional Airport Valley Regional Airport (MVM). Capital Equipment Purchase

022332.00 Covered Center Bridge (#1469), Covered West Bridge (#1470) and Covered East Bridge (#2191) 2018 Machias Route 1 $200,000 Bridge Wearing Surface Repair over the Machias River. Located 0.09 of a mile north /Mill & Fill HCP 2 of Route 92.

022655.00 Highway Safety and Spot Improvements Beginning at Center Street and extending north 0.30 2019/20 Machias Route 1A $300,000 of a mile. HCP 4 Drainage Improvements

Highway Safety and Spot 023673.00 Improvements Beginning 0.28 of a mile north of Court Street and 2018 Machias Route 1 $60,000 extending northerly 0.38 of a mile. Safety Improvements - PE HCP 2 Only

018834.00 Highway Safety and Spot Improvements Large culvert (#146244) located 0.42 of a mile north 2019/20 Machiasport Port Road $315,000 of Base Road. HCP 4 Large Culvert Replacement

021699.00 Bog Stream Bridge (#3719) over Bog Stream. 2018 Northfield Route 192 Located 1.78 miles northwest of Eastern Ridge $1,300,000 Bridge Replacement Road. HCP 4

022346.00 Pennamaquan Bridge (#5326) over Pennamaquan 2019/20 Pembroke Route 1 River. Located 0.08 of a mile northeast of Little Falls $1,200,000 Bridge Deck Replacement Road. HCP 2

151

0123456789 ID/Year Municipality Scope Name Description Funding

Aviation 018704.01 Safety and infrastructure improvements that may Princeton Princeton Airport Buildings include construction of a terminal building at the $309,000 2019/20 Municipal Airport Princeton Municipal Airport (PNN). New Construction

WR 32646 Bridge and Structural Replacing wearing surface on Whitten Stream Bridge Steuben Maintenance Village Road (#2944) over Whitten Stream. Located on the $80,000 2018 Steuben/T7 SD BPP town line.

Highway Safety and Spot 023016.00 Improvements Located 1.1 miles north of the T24 MD BPP - T30 2018 T30 MD BPP Route 9 $75,000 MD BPP town line. Slope Stabilization/Protection - HCP 1 PE Only

WR 32345 Bridge and Structural Replacing membrane and wearing surface on Mopang Stream Bridge (#5438) over Mopang 2018 T30 MD BPP Maintenance Route 9 $91,000 Stream. Located 1.00 mile east of the Devereaux HCP 1 Twp. town line.

Highway Safety and Spot 022996.02 Improvements Located 0.32 of a mile south of the Topsfield town 2018 Talmadge Route 1 $25,000 line and extending northerly 0.06 of a mile. Rest Area Construction/ HCP 3 Improvements

018798.00 Highway Paving Talmadge, Beginning 0.65 of a mile north of Indian Twp. Res.- 2018 Route 1 $3,540,000 Topsfield, Waite Waite town line and extending northerly 11.45 miles. Mill And Fill HCP 3

021706.00 Farrow Lake Stream Bridge (#5378) over Farrow 2018 Topsfield Route 6 Lake Stream. Located 0.44 of a mile west of $700,000 Bridge Replacement Snigdom Road. HCP 3

021753.00 Flood Brook Bridge (#2288) over Flood Brook. 2018 Topsfield Route 6 $200,000 Bridge Culvert Rehabilitation Located 1.41 miles east of Kossuth Twp. HCP 3

WR 35151 Bridge and Structural Resetting granite stone retaining wall and grouting stone on Holmes Stream Bridge (#3810) over 2018 Whiting Maintenance Route 191 $33,000 Holmes Stream. Located 0.02 of a mile north of the HCP 4 Cutler town line.

152

0123456789 York York Cornish Limington

Parsonsfield

Limerick

Newfield Buxton Hollis

Waterboro

Shapleigh

Dayton Saco Old Orchard Beach Acton Lyman Alfred

Biddeford Sanford Arundel

Kennebunkport Lebanon Kennebunk

North Berwick Wells

Berwick York County Population 197,134

Ogunquit Land Area (sq mi) 991 South Bridges 316 Berwick Highway Corridor Priority Miles HCP 1 23 5 York HCP 2 6 7 HCP 3 1 69 Eliot Kittery HCP 4 235

Total HCP 1-4 70 6

Kittery York ID/Year Municipality Scope Name Description Funding

020267.00 Highway Construction/ Rehabilitation Beginning 0.60 of a mile south of Garvin Road and 2019/20 Acton Route 109 $4,259,000 extending northerly 2.16 miles. HCP 2 Highway Rehabilitation

022084.00 Highway Paving Beginning 0.22 of a mile west of Youngs Ridge Road 2018 Acton Route 109 $79,515 and extending southeasterly 2.15 miles. Light Capital Paving HCP 2

022084.00 Highway Paving Beginning at Foxes Ridge Road and extending east 2018 Acton Milton Mills Road $213,395 5.77 miles to Route 109. Light Capital Paving HCP 4

WR 35478 Bridge and Structural Mill and fill the wearing surface and approaches on Acton Maintenance Route 109 Horns Mill Bridge (#3959) over the Salmon Falls $40,000 2018 River. Located on the Acton town line.

022084.00 Highway Paving Foxes Ridge Beginning at Route 11 and extending north 8.07 2018 Acton, Lebanon $298,457 Road miles to French Street. Light Capital Paving HCP 4

022084.00 Highway Paving Beginning at Route 4A and extending north 0.60 of a 2018 Alfred Route 4 $22,190 mile. Light Capital Paving HCP 1

023511.00 Highway Paving Alfred, Arundel, Beginning at the Biddeford city line and extending 2019/20 Route 111 $3,198,649 Lyman west 10.04 miles. 1 1/4" Overlay HCP 1

023286.00 Alfred, Berwick, Highway Paving Beginning 0.13 of a mile south of Driscoll Lane and North Berwick, extending northeasterly 6.23 miles. Continuing 0.07 2018 Route 4 $1,837,888 Sanford, South Ultra Thin Bonded Wearing of a mile north of Route 109 and extending HCP 1 Berwick Surface northeasterly 4.27 miles.

Highway Safety and Spot 022821.00 Improvements Beginning 0.08 of a mile from Clark Road and 2018 Alfred, Lyman Route 111 $210,000 extending east 0.96 of a mile. Highway Improvements - PE HCP 1 Only

021823.00 Highway Safety and Spot Improvements Large culvert (#910881) located on the Alfred- 2019/20 Alfred, Sanford Route 202 $330,000 Sanford town line. HCP 1 Large Culvert Replacement

153

0123456789 ID/Year Municipality Scope Name Description Funding

023749.00 Highway Paving Beginning at Route 11 and extending north 3.37 2019/20 Alfred, Sanford Route 202 $1,568,398 miles. Cold-In-Place Recycle HCP 1

WR 35130 Surface and Base Maintenance Shimming eastbound side of Route 111. Beginning at 2018 Alfred, Lyman Route 111 Walker Road and extending west 1.00 mile to $40,000 Blueberry Hill Road. HCP 1

019002.00 Highway Safety and Spot Improvements Located at the intersection with New Road and Old 2018 Arundel Route 111 $1,800,000 Alfred Road. HCP 1 Intersection Improvements

019107.00 Highway Safety and Spot Improvements Beginning at Old Alfred Road and extending west 2018 Arundel Route 111 $2,375,000 0.58 of a mile. HCP 1 Safety Improvements

022823.00 Highway Safety and Spot Improvements Located at the intersection of Route 1 and Log Cabin 2019/20 Arundel Route 1 $211,500 Road. HCP 1 Traffic Signals

023509.00 Highway Safety and Spot Improvements Beginning at River Road and extending north 0.03 of 2019/20 Arundel Route 1 $211,500 a mile to Limerick Road. HCP 1 Traffic Signals

WR 35415 Bridge and Structural Mill and fill wearing surface, repair concrete headers Durrells Bridge and repair damaged bridge rail on Durrells Bridge Arundel Maintenance $100,000 2018 Road (#6049) over the . Located on the Kennebunk-Arundel town line.

WR 35418 Operational and Safety Replacement of 25 feet of approach guard rail at Durrells Bridge each end of Durrells Bridge (#6049) over the Arundel Maintenance $16,000 2018 Road Kennebunk River. Located on the Kennebunk- Arundel town line.

023298.00 Highway Paving Arundel, Beginning 0.04 of a mile south of Barnard Lane and 2018 Biddeford, Route1 $1,042,395 extending northeasterly 5.50 miles. Kennebunk Ultra Thin Bonded Wearing HCP 1 Surface

023322.00 Highway Paving Arundel, Dayton, Beginning at the Kennebunk-Arundel town line and 2018 Route 35 $566,994 Lyman Highway Cyclical Pavement extending north 4.06 miles. HCP 3 Resurfacing

154

0123456789 ID/Year Municipality Scope Name Description Funding

022084.00 Highway Paving Arundel, Beginning at Route 9 and extending north 5.05 miles 2018 Log Cabin Road $186,397 Kennebunkport to Route 1. Light Capital Paving HCP 4

Highway Construction/ 020249.00 Rehabilitation Beginning at Route 35 and extending east 1.00 mile 2018 Arundel, Lyman Route 111 $450,000 to Thompson Road. Highway Improvements - PE HCP 1 Only

022282.00 Hubbard Bridge (#6221) over . Located 2019/20 Berwick Hubbard Road $650,000 Bridge Deck Replacement 0.02 of a mile north of Horns Mill Road. HCP 4

022284.00 New Dam Bridge (#6053) over . 2019/20 Berwick New Dam Road Located on the Berwick, Maine- Somersworth, New $350,000 Bridge Rehabilitation Hampshire town line. HCP 6

022606.00 Eddy Bridge (#6048) over Salmon Falls River. 2018 Berwick Rochester Street Located on the Berwick, Maine - Somersworth, New $550,000 Bridge Rehabilitation Hampshire state line. HCP 4

Highway Construction/ 023529.00 Rehabilitation Large culvert (#189339) located 0.02 of a mile west 2018 Berwick Route 9 $160,000 of Old Sanford Road. Large Culvert Replacement - HCP 2 PE Only

022084.00 Highway Paving Berwick, South Beginning 0.03 of a mile south of the Berwick town 2018 Route 236 $77,665 Berwick line and extending northerly 2.10 miles. Light Capital Paving HCP 2

Aviation 018687.01 Safety and infrastructure improvements that may Biddeford include obstruction removal, reconstruction of Biddeford Runway/Taxiway $4,532,000 2019/20 Municipal Airport Runway 6-24 to include lighting and Runway 6 Reconstruction Safety Area at the Biddeford Municipal Airport (B19).

Aviation 018687.02 Safety and infrastructure improvements that may Airport Buildings Biddeford Biddeford include easement acquisitions on the Runway 24 end $515,000 2018 Municipal Airport Sale Or Purchase Of Lot Or at the Biddeford Municipal Airport (B19). Building

Aviation 018687.03 Safety and infrastructure improvements that may Biddeford include FAA reimbursable agreement for the design Biddeford Runway/Taxiway $154,500 2019/20 Municipal Airport of Runway 6-24 at the Biddeford Municipal Airport Reconstruction (B19).

155

0123456789 ID/Year Municipality Scope Name Description Funding

Aviation 018687.04 Safety and infrastructure improvements that may Biddeford include FAA reimbursable agreement for the Biddeford Runway/Taxiway $154,500 2019/20 Municipal Airport construction of Runway 6-24 at the Biddeford Reconstruction Municipal Airport (B19).

Aviation 018687.17 Safety and infrastructure improvements that may Biddeford include design and permitting for Runway 24, runway Biddeford Runway/Taxiway $412,000 2019/20 Municipal Airport safety area, obstruction removal and drainage at the Reconstruction Biddeford Municipal Airport (B19).

022084.00 Highway Paving Beginning 0.03 of a mile north of Sky Oaks Drive and 2018 Biddeford West Street $32,545 extending northerly 0.88 of a mile. Light Capital Paving HCP 4

022084.00 Highway Paving Beginning at Route 9 and extending north 0.51 of a 2018 Biddeford West Street $18,862 mile. Light Capital Paving HCP 4

022182.00 Highway Safety and Spot Improvements Located at the intersection of Main Street, Adams 2019/20 Biddeford Main Street $229,600 Street, and Lincoln Street. PACTS Sponsored MPI. HCP 4 Intersection Improvements

022406.00 Highway Paving Beginning at South View Drive and extending west 2018 Biddeford South Street 0.39 of a mile to Mt. Pleasant Street. PACTS $297,847 Mill And Fill Sponsored. HCP 4

023418.00 Highway Construction/ Rehabilitation Beginning at the intersection of Main Street and 2018 Biddeford Main Street Lincoln Street and extending west 0.19 of a mile to $472,500 Route 1. PACTS Sponsored MPI. HCP 4 Highway Rehabilitation

WR 34789 Removal of overgrown brush within the right-of-way Custodial Maintenance beginning at the intersection of Pool Street and New 2018 Biddeford Route 9 $30,000 Town Road extending south 3.67 miles to the HCP 3 Biddeford-Kennbunk town line.

018574.00 Highway Safety and Spot Located at the intersections of Main Street, Water Biddeford, Improvements Street, Hill Road and Pepperell Mill Campus 2019/20 Portland, Route 9 entrance. Mill and fill beginning at Hill Street and $1,547,500 Scarborough extending east 0.13 of a mile to Hill Street. PACTS HCP 2, 3 Intersection Improvements Sponsored.

WR 34790

2018 Biddeford, Custodial Maintenance Route 112, Route Sealing bridges in Scarborough Crew area to help $2,000 Buxton, Saco 9, Route 5 preserve the longevity of the structures. HCP 2, 3, 4

156

0123456789 ID/Year Municipality Scope Name Description Funding

Highway Safety and Spot 022837.00 Improvements Located at the intersection of Broadturn Road and 2018 Buxton Route 22 $210,000 Route 22. Highway Improvements - PE HCP 3 Only

022641.00 Highway Construction/ Beginning 0.13 of a mile north of Route 5 extending Buxton, Rehabilitation northerly 2.16 miles. Beginning 0.16 of a mile north 2019/20 Gorham, Hollis, Route 202 of Main Street extending northerly 0.20 of a mile. $7,040,000 Lyman Beginning 0.62 of a mile north of Osborne Road HCP 1 Reconstruction extending north 0.56 of a mile.

023643.00 Salmon Falls Bridge (#3708) over Saco River. 2019/20 Buxton, Hollis Route 202 $1,100,000 Bridge Deck Replacement Located on the Hollis- Buxton town line. HCP 1

022086.00 Highway Paving Beginning 0.02 of a mile east of the Buxton town line 2018 Buxton, Saco Route 117 $67,308 and extending northwesterly 2.15 miles to Route 202. Light Capital Paving HCP 3

022086.00 Highway Paving Buxton, Beginning at Route 22 and extending south 2.40 2018 Broadturn Road $75,134 Scarborough miles. Light Capital Paving HCP 3

WR 34200 Custodial Maintenance Canopy clearing beginning at the junction of Route 2018 Buxton, Gorham Route 112 112 and Route 4A and extending northeasterly 9.81 $55,000 miles to Buxton-Gorham town line. HCP 4

Highway Safety and Spot 022847.00 Improvements Beginning 0.01 of a mile east of Thompson Street 2018 Cornish Route 25 $75,000 and extending westerly 0.02 of a mile. Slope Stabilization/Protection - HCP 2 PE Only

023350.00 Cornish, Highway Paving Limerick, Beginning at Route 11 and extending north 12.51 2019 Route 160 $497,787 Parsonsfield, miles to Route 25. Light Capital Paving HCP 4, 2 Porter

Highway Construction/ 023551.00 Rehabilitation Large culvert (#46526) located at the intersection of 2018 Dayton Route 5 $200,000 Route 5 and River Road. Large Culvert Replacement - HCP 3 PE Only

WR 35131 Custodial Maintenance Tree and brush removal beginning at the intersection 2018 Dayton Route 35 of Gould Road extending north 1.10 miles to the $50,000 intersection of Route 5 in Dayton. HCP 3

157

0123456789 ID/Year Municipality Scope Name Description Funding

Highway Safety and Spot 019429.00 Improvements Located at the intersection of Route 236 and Depot 2018 Eliot Route 236 $235,000 Road. Intersection Improvements - PE HCP 1 Only

Highway Construction/ 022500.00 Rehabilitation Eliot, South Beginning at Scotland Bridge Road in York and 2018 Route 91 $290,000 Berwick, York extending northwest 3.75 miles. Highway Improvements - PE HCP 3 Only

022086.00 Highway Paving Beginning at Shy Beaver Road and extending east 2018 Hollis Plains Road $36,315 1.16 miles. Light Capital Paving HCP 4, 3

023350.00 Highway Paving Beginning at Shy Beaver Road and extending east 2019 Hollis Plains Road $46,158 1.16 miles. Light Capital Paving HCP 4, 3

Bicycle-Pedestrian 019392.00 Engineering for future drainage and pedestrian safety improvements on Factory Pasture Lane and Depot Trail, On-Road 2018 Kennebunk Depot Street Street as part of a larger highway improvement $20,750 Bicycle/Pedestrian project by the town. Approximate length of 0.67 of a HCP 6 Improvements - PE Only mile.

021793.00 Highway Safety and Spot Improvements Beginning 0.15 of a mile north of Glenwood Terrace 2018 Kennebunk Ross Road $120,000 and extending westerly 0.11 of a mile. HCP 4 Structural Overlay

021928.05 Highway Construction/ Rehabilitation Municipal Partnership Initiative Program. Beginning 2018 Kennebunk Route 9A at Heath Road and extending north 1.08 miles to Sea $1,094,000 Road. HCP 3 Highway Rehabilitation

022084.00 Highway Paving Beginning at the Sanford town line and extending 2018 Kennebunk Route 99 $159,029 east 4.30 miles. Light Capital Paving HCP 3

022242.00 Pasture Bridge (#0569) over Ward Brook. Located 2018 Kennebunk Emmons Road $400,000 Bridge Replacement 0.18 of a mile southeast of Serendipity Way. HCP 6

023629.00 Nash Mill Bridge (#5756) over . 2019/20 Kennebunk Mill Street $500,000 Bridge Rehabilitation Located 0.14 of a mile north of Hammond Road. HCP 4

158

0123456789 ID/Year Municipality Scope Name Description Funding

WR 35213 Bridge and Structural Mill and pave 120 sqare feet of wearing surface on 2018 Kennebunk Maintenance Mill Street Nash Mill Bridge (#5756) over Mousam River. $17,000 Located 0.14 of a mile north of Hammond Road. HCP 4

022084.00 Highway Paving Kennebunk, Beginning 0.55 of a mile north of Lindsey Road and 2018 Route 9A $143,496 Wells extending northerly 3.88 miles. Light Capital Paving HCP 4

022704.00 Highway Safety and Spot Located at the intersections of Route 1 and Kennebunk, Improvements Laudholm Farm Road, of Route 1 and Drakes Island 2018 Route 1 $80,000 Wells Road in Kennebunkport, and of Route 35 and HCP 3, 1 Flashing Beacon Durrells Bridge Road in Wells.

WR 35127 Kennebunk, Custodial Maintenance Tree and brush removal beginning at the intersection 2018 Route 9A $40,000 Wells of Route 9 and extending north 5.91 miles. HCP 4

021928.01 Highway Construction/ Municipal Partnership Initiative Program. Route 9: Rehabilitation Beginning at Main Street and extending north 1.65 2018 Kennebunkport Route 9 miles to 0.05 of a mile southerly of Beachwood $877,100 Avenue. North Street: Beginning at Mill Lane and HCP 3, 4 Highway Rehabilitation extending north 0.68 of a mile.

WR 35402 Bridge and Structural Install and attach approach guard rail, replace bridge rail, fluid film beam ends and bearings, and mill and 2018 Kennebunkport Maintenance Route 9 $130,000 fill wearing surface on Mill Pond Bridge (#3852). HCP 3 Located 0.05 miles south of Beachwood Avenue.

018653.00 Beginning 0.09 of a mile northwest of Main Street Highway Paving and extending easterly 0.31 of a mile; Wentworth 2019/20 Kittery Route 103 Street extending north 0.19 of a mile to Whipple $913,054 1 1/4" Overlay Road. Includes signal at Walker and Wentworth HCP 2 Streets. KACTS Sponsored.

019270.00 I-95/ Piscataqua River Bridge (#6330) over the 2018 Kittery Bridge Wearing Surface Interstate 95 Piscataqua River and Route 103. Located on the $27,948,755 Replacement Maine - New Hampshire state line. HCP 1

019394.00 Bicycle-Pedestrian Beginning at Old Ferry Lane and extending west 0.53 2019/20 Kittery Trail, On-Road Route 103 $902,000 of a mile. HCP 4 New Construction

020867.00 Highway Paving Beginning at Chauncey Creek Road and extending 2018 Kittery Route 103 $460,000 north 1.17 miles. KACTS Sponsored 1 1/4" Overlay HCP 4

159

0123456789 ID/Year Municipality Scope Name Description Funding

022889.00 Highway Safety and Spot Improvements Located at the intersection of Route 101 and Picott 2019/20 Kittery Route 101 $50,000 Road. HCP 4 Flashing Beacon

023621.00 Kittery Point Bridge (#3013) over Kittery Point. 2018 Kittery Route 103 $500,000 Bridge Wearing Surface Located 0.08 of a mile east of Bowen Road. Replacement HCP 4

WR 35690 Operational and Safety Install new fence along property line under Piscataqua River Maine Approach Bridge (#1477) 2018 Kittery Maintenance Route 103 $40,000 over the Piscataqua River. Located at the Maine - HCP 1 New Hampshire state line.

022244.00 New Bridge (#3717) over Salmons Falls. Located 2019/20 Lebanon New Bridge Road $520,000 Bridge Replacement 0.08 of a mile north of Hillside Drive. HCP 6

WR 35445 Bridge and Structural Replace wearing surface, replace up to 25% of deck as needed and approach rail on three corners of Lebanon Maintenance Little River Road $90,000 2018 Gristmill Bridge (#5258) over Little River. Located 0.30 of a mile north of Chick Road.

022492.00 Highway Construction/ Rehabilitation Beginning at Route 11 and extending north 4.78 2019/20 Limington Route 117 $1,195,000 miles to Route 25. HCP 4 PMRAP DOT Pugmill

022893.00 Highway Safety and Spot Improvements Large culvert (#86554) located 0.05 of a mile east of 2019/20 Limington Route 117 $305,000 Deer Ridge Road. HCP 4 Large Culvert Replacement

WR 34047 Producing, hauling and providing additional support PMRAP activities for the placement of plant mix recycled 2019 Limington Route 117 asphalt pavement (PMRAP) beginning at Route 11 $286,800 and extending north 4.78 miles to Route 25 in HCP 4 Limington.

WR 35399 Repairs to large culvert (#992807) that will consist of Drainage Maintenance curb and fascia repairs of the existing structure 2018 Limington Route 25 $45,000 including updating guard rail. Located 0.20 of a mile HCP 2 west of Christian Hill Road.

Highway Construction/ 020248.00 Rehabilitation Beginning at Route 35 and extending west 0.86 of a 2018 Lyman Route 111 $210,000 mile. Highway Improvements - PE HCP 1 Only

160

0123456789 ID/Year Municipality Scope Name Description Funding

022501.00 Highway Safety and Spot Improvements Located at the intersection of Route 111 and 2019/20 Lyman Route 111 $155,000 Kennebunk Pond Road. HCP 1 Flashing Beacon

022895.00 Highway Safety and Spot Improvements Located at the intersection of Route 35 and South 2019/20 Lyman Route 35 $150,000 Street. HCP 3 Flashing Beacon

WR 35128 Custodial Maintenance Clearing trees on Route 111 beginning at the Lyman 2018 Lyman Route 111 town line and extending west 5.00 miles to the Alfred $197,000 town line. HCP 1

Highway Construction/ 023687.00 Rehabilitation Beginning at Bridge Street and extending east 0.14 2018 Newfield Route 11 $80,000 of a mile. Highway Improvements - PE HCP 3 Only

022084.00 Highway Paving Beginning at Route 4 and extending northwest 1.89 2018 North Berwick Lebanon Road $69,899 miles to Valley Road. Light Capital Paving HCP 4

022336.00 Staples Bridge (#1238) over the . 2019/20 North Berwick Card Mill Road $600,000 Bridge Superstructure Located 0.15 of a mile east of Lebanon Road. Replacement HCP 6

WR 35457 Bridge and Structural Mill and fill wearing surface and update approach rail and attachment to Madison Street Bridge (#5172) North Berwick Maintenance Madison Street $50,000 2018 over the Great Works River. Located 0.08 of a mile west of Partridge Lane.

023350.00 Highway Paving Beginning 0.07 of a mile north of York town line and 2019 Ogunquit Shore Road $50,933 extending northerly 1.28 miles to Route 1. Light Capital Paving HCP 4

022440.00 Highway Paving Old Orchard Beginning at Union Avenue and extending north 1.33 2019/20 Route 5 $1,087,734 Beach miles to the Saco city line. PACTS Sponsored. 1 1/4" Overlay HCP 2

022948.00 Highway Safety and Spot Old Orchard Improvements Located at the intersection of Route 98 and Ross 2018 Route 98 $50,000 Beach Road. HCP 3 Planning Studies - PE Only

161

0123456789 ID/Year Municipality Scope Name Description Funding

023350.00 Highway Paving Province Lake Beginning at the New Hampshire state line and 2019 Parsonsfield $78,786 Road extending north 1.98 miles to Stagecoach Road. Light Capital Paving HCP 4

023354.00 Highway Paving Beginning at Route 160 and extending north 4.44 2019 Parsonsfield Elm Street $203,003 miles to Route 25. Light Capital Paving HCP 4

WR 34921 Drainage Maintenance Ditching on Elm Street in preparation of the Standish 2018 Parsonsfield Elm Street area LCP. Beginning at Route 160 and extending $80,000 north 4.45 miles. HCP 4

WR 34922 Drainage Maintenance Replacing culverts on Elm Street in preparation of 2018 Parsonsfield Elm Street the Standish area LCP. Beginning at Route 160 $17,000 extending north 4.45 miles. HCP 4

WR 35125 Excavator ditching to improve drainage beginning at Drainage Maintenance Province Lake the Maine-New Hampshire state line and extending 2018 Parsonsfield $85,000 Road north 2.00 miles to the intersection of Stagecoach HCP 4 Road in Parsonsfield.

Marine 020850.00 Expand float system, power pedestals, hoist, and Saco Piers, Floats And Fenders Camp Ellis Pier $63,680 2019/20 seasonal water at Camp Ellis Pier. New Construction

Marine 020851.00 Camp Ellis Boat Ramp rehabilitation and new float system, located Saco Piers, Floats And Fenders $215,000 2019/20 Ramp near Camp Ellis Pier. New Construction

020879.00 Highway Paving Industrial Park Beginning at Route 112 and extending northeast 2018 Saco $1,521,938 Road 1.79 miles. PACTS Sponsored. Mill And Fill HCP 2, 3

020880.00 Highway Paving Beginning at the Biddeford town line and extending 2018 Saco Route 9 north 0.63 of a mile to Elm Street. PACTS $886,688 Mill And Fill Sponsored. HCP 2, 4

021747.00 Saco I-195 Bridge (#0810) over Industrial Park Road eastbound. Saco I-195 Bridge (#0811) over Industrial Interstate 195 2018 Saco Park Road westbound. Saco I-195 Bridge (#0812) $1,200,000 Bridge Wearing Surface Bridges Replacement over Route 1 eastbound. Saco I-195 Bridge (#0813) HCP 1 over Route 1 westbound.

162

0123456789 ID/Year Municipality Scope Name Description Funding

022086.00 Highway Paving Beginning at Route 5 and extending northeast 0.57 2018 Saco Louden Road $17,844 of a mile. Light Capital Paving HCP 4

022464.00 Highway Paving Beginning at Route 1 and extending east 0.94 of a 2019/20 Saco Route 5 mile to the Old Orchard Beach town line. PACTS $648,591 1 1/4" Overlay Sponsored. HCP 4

023414.00 Highway Construction/ Rehabilitation Beginning at the Somesville Bridge (#3412) and 2018 Saco Market Street extending northwest 0.17 of a mile to Lincoln Street. $362,799 PACTS Sponsored MPI. HCP 4 Highway Rehabilitation

Aviation Safety and infrastructure improvements that may 018706.17 Sanford include construction of a snow removal equipment Sanford Airport Buildings Seacoast $916,700 2018 building and fencing at the Sanford Seacoast Regional Airport New Construction Regional Airport (SFM).

019001.00 Highway Safety and Spot Improvements Located at the intersection of Route 4 and School 2019/20 Sanford Route 4 $21,000 Street. HCP 1 Intersection Improvements

022084.00 Highway Paving Beginning at Route 11 and extending north 2.43 2018 Sanford Route 11A $89,870 miles. Light Capital Paving HCP 3

022084.00 Highway Paving Beginning 0.10 of a mile east of Beaconsfield Road 2018 Sanford Route 99 $21,450 and extending easterly 0.58 of a mile Light Capital Paving HCP 3

Highway Construction/ 022642.00 Rehabilitation Beginning at River Street and extending north 0.72 2018 Sanford Route 202 $215,000 miles. Highway Improvements - PE HCP 1 Only

Highway Safety and Spot 022678.00 Intersection of Route 109/ Emery Street, Washington Improvements Street, Lebanon/Winter Street, Route 11A /224, Various 2018 Sanford Route 4 and Cottage Street, Route 109 at Walmart, $175,000 Locations Intersection Improvements - PE Jagger Mill at Shaw's, Westview at Mardens, Route HCP 1, 3 Only 4A and Route 224, Route 224 and River Street.

022974.00 Highway Safety and Spot Improvements 2019/20 Sanford Route 109 Located at the intersection of Route 109 and 4A. $255,000

HCP 1 Signing

163

0123456789 ID/Year Municipality Scope Name Description Funding

023346.00 Highway Safety and Spot Improvements Located at the intersection of Old Mill Road and 2019/20 Sanford Route 4A Route 4A. Continuing 0.06 of a mile south of Old Mill $285,500 Road. HCP 1 Intersection Improvements

023348.00 Public Transportation Kittery Area Comprehensive Transportation System Urban Transit (KACTS), Federal Transit Administration § 5303 for Sanford $37,240 2018 Planning metropolitan planning Fiscal Year 2018. Funds are Administrative Assistance transferred to FHWA.

023348.19 Public Transportation Kittery Area Comprehensive Transportation System Urban Transit (KACTS), Federal Transit Administration § 5303 for Sanford $37,240 2019 Planning metropolitan planning Fiscal Year 2019. Funds are Administrative Assistance transferred to FHWA.

023348.20 Public Transportation Kittery Area Comprehensive Transportation System Urban Transit (KACTS), Federal Transit Administration § 5303 for Sanford $37,240 2020 Planning metropolitan planning Fiscal Year 2020. Funds are Administrative Assistance transferred to FHWA.

Highway Construction/ 023747.00 Rehabilitation Large culvert (#46484) located 0.19 of a mile 2018 Sanford Route 202 $80,000 northeast of Jellerson Road. Large Culvert Replacement - HCP 1 PE Only

022498.00 Highway Construction/ Rehabilitation Beginning 0.15 of a mile south of the Wire Road and 2019/20 Sanford, Wells Route 109 $2,179,795 extending northwesterly 4.72 miles. HCP 1 Cold-In-Place Recycle

021829.00 Highway Safety and Spot Improvements Located at the intersection of Route 236 and Route 2019/20 South Berwick Route 91 $421,000 91. KACTS Sponsored. HCP 3 Highway Improvements

023645.00 Salmon Falls Bridge (#5700) over Salmon Falls 2018 South Berwick Main Street River. Located on the South Berwick, Maine- $200,000 Bridge Improvements - PE Only Rollinsford, New Hampshire state line. HCP 4

Install approach rail and bridge attachment points at WR 34657 Bridge and Structural the four corners, as well as fluid film beam ends and Emery's Bridge South Berwick Maintenance bearings on Junction Bridge (#5944) over Great $25,000 2018 Road Works River. Located 0.02 of a mile west of Old Emery's Bridge Road.

WR 35406 Bridge and Structural Repair wearing surface and also grout under the Hooper Sands abutments and wing walls on Emery's Bridge (#1243) South Berwick Maintenance $40,000 2018 Road over Great Works River. Located 0.04 of a mile north of Emery's Bridge Road.

164

0123456789 ID/Year Municipality Scope Name Description Funding

WR 35458 Bridge and Structural Paint beam ends, bearings, and all metal bridge rail on Great Works Bridge (#5343) over the Great South Berwick Maintenance Brattle Street $200,000 2018 Works River. Located 0.03 of a mile east of Pine Street.

021837.00 Highway Safety and Spot Improvements Large culvert (#910880) located 0.03 of a mile east 2019/20 Waterboro West Road $330,000 of Federal Street. HCP 4 Large Culvert Replacement

023350.00 Highway Paving Beginning at Route 202 and extending north 4.60 2019 Waterboro Route 5 $183,039 miles. Light Capital Paving HCP 3

022084.00 Highway Paving Beginning at Route 9 and extending northeast 0.88 2018 Wells Route 9A $32,545 of a mile to Route 109. Light Capital Paving HCP 4

022084.00 Highway Paving Beginning 0.02 of a mile west of Loop Road and 2018 Wells Route 9B $42,901 extending easterly 1.16 miles. Light Capital Paving HCP 4

Marine 023474.00 Re-decking public landing and structural Wells Boat Ramps Town Pier $170,000 2019/20 improvements. Rehabilitation

023535.00 Buffam Bridge (#2107) over . 2019/20 Wells Post Road $1,500,000 Bridge Replacement Located 0.02 of a mile south of Falls Park. HCP 1

Highway Safety and Spot 023791.00 Improvements Located at the intersection of Route 109 and Garden 2018 Wells Route 109 $45,000 Street. Safety Improvements - PE HCP 2, 1 Only

023793.00 Highway Safety and Spot Improvements Located at the intersection of Route 109 and Route 2019/20 Wells Route 109 $275,000 9A. HCP 4 Safety Improvements

WR 35133 Custodial Maintenance Clearing trees beginning at the intersection of Route 2018 Wells Route 9 9A and extending north 4.00 miles to the intersection $20,000 of Bragdon Road in Wells. HCP 2

165

0123456789 ID/Year Municipality Scope Name Description Funding

020899.00 Highway Safety and Spot Improvements Located at the intersection of Route 1 and New 2019/20 York Route 1 $689,000 Connector Road. KACTS Sponsored. HCP 1 Traffic Signals

021651.00 Highway Safety and Spot Improvements Located at the intersection of Route 1A and Long 2019/20 York Route 1A $1,340,134 Sands Road. KACTS Sponsored. HCP 3 Intersection Improvements

021709.00 Cape Neddick Bridge (#2127) over Cape Neddick 2018 York Route 1 $1,940,000 Bridge Replacement River. Located 0.12 of a mile north of Route 1A. HCP 1

Highway Safety and Spot 021904.00 Improvements Located at the intersection of Route 1A and Long 2018 York Route 1A $38,000 Sands Road. Intersection Improvements - PE HCP 3 Only

020644.18 Public Transportation FTA Section 5307 for Operating Assistance - Kittery Urban Transit York County Area Comprehensive Transportation System $345,828 2018 Operating Operating Assistance (KACTS) urban area (Portsmouth).

020644.19 Public Transportation FTA Section 5307 for Operating Assistance - Kittery Urban Transit York County Area Comprehensive Transportation System $345,828 2019 Operating Operating Assistance (KACTS) urban area (Portsmouth).

020644.20 Public Transportation FTA Section 5307 for Operating Assistance - Kittery Urban Transit York County Area Comprehensive Transportation System $345,828 2020 Operating Operating Assistance (KACTS) urban area (Portsmouth).

022709.18 Public Transportation FTA Section 5307 for Operating Assistance - Kittery Urban Transit York County Area Comprehensive Transportation System $200,000 2018 Operating Operating Assistance (KACTS) urban area (Dover-Rochester).

022709.19 Public Transportation FTA Section 5307 for Operating Assistance - Kittery Urban Transit York County Area Comprehensive Transportation System $200,000 2019 Operating Operating Assistance (KACTS) urban area (Dover-Rochester).

022709.20 Public Transportation FTA Section 5307 for Operating Assistance - Kittery Urban Transit York County Area Comprehensive Transportation System $200,000 2020 Operating Operating Assistance (KACTS) urban area (Dover-Rochester).

166

0123456789 Ë Statewide Capital Projects

Statewide Capital ID/Year Municipality Scope Name Description Funding

018896.12 Highway Preservation Paving Various Region 1 Light Pavement Treatment. $6,600,000 2019 Locations

018896.13 Highway Preservation Paving Various Region 1 Light Pavement Treatment. $7,000,000 2020 Locations

018995.11 Highway Preservation Paving Various Region 1 Crack Seal, Chip Seal, and Fog Seal. $108,113 2018 Locations

018995.12 Highway Preservation Paving Various Region 1 Crack Seal, Chip Seal, and Fog Seal. $100,000 2019 Locations

018995.13 Highway Preservation Paving Various Region 1 Crack Seal, Chip Seal, and Fog Seal. $100,000 2020 Locations

022196.11 Highway Preservation Paving Various Region 1 Cyclical Pavement Resurfacing. $1,644,489 2019 Locations

022196.12 Highway Preservation Paving Various Region 1 Cyclical Pavement Resurfacing. $3,067,782 2020 Locations

018896.22 Highway Preservation Paving Various Region 2 Light Pavement Treatment. $4,700,000 2019 Locations

018896.23 Highway Preservation Paving Various Region 2 Light Pavement Treatment. $5,200,000 2020 Locations

018995.21 Highway Preservation Paving Various Region 2 Crack Seal, Chip Seal, and Fog Seal. $100,000 2018 Locations

167

0123456789 ID/Year Municipality Scope Name Description Funding

018995.22 Highway Preservation Paving Various Region 2 Crack Seal, Chip Seal, and Fog Seal. $100,000 2019 Locations

018995.23 Highway Preservation Paving Various Region 2 Crack Seal, Chip Seal, and Fog Seal. $100,000 2020 Locations

021818.00 Highway Safety and Spot Various Region 2 Improvements Replace guard rail. $60,500 2018 Locations

022196.21 Highway Preservation Paving Various Region 2 Cyclical Pavement Resurfacing. $616,779 2019 Locations

022196.22 Highway Preservation Paving Various Region 2 Cyclical Pavement Resurfacing. $2,543,368 2020 Locations

023727.00 Highway Safety and Spot Various Region 2 Improvements Replace guard rail. $165,000 2020 Locations

023729.00 Highway Safety and Spot Various Region 2 Improvements Guard rail upgrades. $75,000 2020 Locations

023731.00 Highway Safety and Spot Various Region 2 Improvements Guard rail upgrades. $200,000 2020 Locations

018896.32 Highway Preservation Paving Various Region 3 Light Pavement Treatment. $4,400,000 2019 Locations

018896.33 Highway Preservation Paving Various Region 3 Light Pavement Treatment. $4,800,000 2020 Locations

168

0123456789 ID/Year Municipality Scope Name Description Funding

018995.31 Highway Preservation Paving Various Region 3 Crack Seal, Chip Seal, and Fog Seal. $100,000 2018 Locations

018995.32 Highway Preservation Paving Various Region 3 Crack Seal, Chip Seal, and Fog Seal. $100,000 2019 Locations

018995.33 Highway Preservation Paving Various Region 3 Crack Seal, Chip Seal, and Fog Seal. $100,000 2020 Locations

022196.31 Highway Preservation Paving Various Region 3 Cyclical Pavement Resurfacing. $24,041 2019 Locations

022196.32 Highway Preservation Paving Various Region 3 Cyclical Pavement Resurfacing. $2,235,757 2020 Locations

023733.00 Highway Safety and Spot Various Region 3 Improvements Cable guard rail upgrade. $350,000 2020 Locations

018896.42 Highway Preservation Paving Various Region 4 Light Pavement Treatment. $5,600,000 2019 Locations

018896.43 Highway Preservation Paving Various Region 4 Light Pavement Treatment. $5,200,000 2020 Locations

018995.41 Highway Preservation Paving Various Region 4 Crack Seal, Chip Seal, and Fog Seal. $100,000 2018 Locations

018995.42 Highway Preservation Paving Various Region 4 Crack Seal, Chip Seal, and Fog Seal. $100,000 2019 Locations

169

0123456789 ID/Year Municipality Scope Name Description Funding

018995.43 Highway Preservation Paving Various Region 4 Crack Seal, Chip Seal, and Fog Seal. $100,000 2020 Locations

022196.41 Highway Preservation Paving Various Region 4 Cyclical Pavement Resurfacing. $1,204,937 2019 Locations

022196.42 Highway Preservation Paving Various Region 4 Cyclical Pavement Resurfacing. $3,112,023 2020 Locations

023735.00 Highway Safety and Spot Various Region 4 Improvements Guard rail upgrades. $300,000 2020 Locations

018896.52 Highway Preservation Paving Various Region 5 Light Pavement Treatment. $4,100,000 2019 Locations

018896.53 Highway Preservation Paving Various Region 5 Light Pavement Treatment. $3,100,000 2020 Locations

018995.51 Highway Preservation Paving Various Region 5 Crack Seal, Chip Seal, and Fog Seal. $100,000 2018 Locations

018995.52 Highway Preservation Paving Various Region 5 Crack Seal, Chip Seal, and Fog Seal. $100,000 2019 Locations

018995.53 Highway Preservation Paving Various Region 5 Crack Seal, Chip Seal, and Fog Seal. $100,000 2020 Locations

022196.51 Highway Preservation Paving Various Region 5 Cyclical Pavement Resurfacing. $1,338,165 2019 Locations

170

0123456789 ID/Year Municipality Scope Name Description Funding

022196.52 Highway Preservation Paving Various Region 5 Cyclical Pavement Resurfacing. $2,041,070 2020 Locations

022494.00 Highway Preservation Paving Various Municipal Partnership Initiative (MPI) Program. Regional $1,280,402 2019 Locations PACTS Sponsored.

023701.00 Highway Preservation Paving Various Regional PACTS Collector Road Paving. $2,198,192 2020 Locations

023705.00 Highway Preservation Paving Various Municipal Partnership Initiative (MPI) Program. Regional $3,280,402 2020 Locations PACTS Sponsored.

005412.18 External Capital Statewide Management Local Road Assistance Program (LRAP). $55,000 2018 Highways

005412.19 External Capital Statewide Management Local Road Assistance Program (LRAP). $55,000 2019 Highways

005412.20 External Capital Statewide Management Local Road Assistance Program (LRAP). $55,000 2020 Highways

018516.18 Bicycle-Pedestrian Management fee to Maine Department of Agriculture, Down East Statewide Conservation, and Forestry for oversight of the Down $50,000 2018 Trail, Off-Road Sunrise Trail East Sunrise Trail.

018516.19 Bicycle-Pedestrian Management fee to Maine Department of Agriculture, Down East Statewide Conservation, and Forestry for oversight of the Down $50,000 2019 Trail, Off-Road Sunrise Trail East Sunrise Trail.

018516.20 Bicycle-Pedestrian Management fee to Maine Department of Agriculture, Down East Statewide Conservation, and Forestry for oversight of the Down $50,000 2020 Trail, Off-Road Sunrise Trail East Sunrise Trail.

171

0123456789 ID/Year Municipality Scope Name Description Funding

018517.18 Public Transportation Various Statewide Capital improvements to Park and Ride Lots. $60,000 2018 Parking Lots Locations

018517.19 Public Transportation Various Statewide Capital improvements to Park and Ride Lots. $60,000 2019 Parking Lots Locations

018517.20 Public Transportation Various Statewide Capital improvements to Park and Ride Lots. $60,000 2020 Parking Lots Locations

018521.18 Rail Support economic opportunity by improving freight Industrial Rail Statewide rail related infrastructure for Maine businesses and $2,500,000 2018 Line Access Program shippers.

018521.19 Rail Support economic opportunity by improving freight Industrial Rail Statewide rail related infrastructure for Maine businesses and $2,500,000 2019 Line Access Program shippers.

018521.20 Rail Support economic opportunity by improving freight Industrial Rail Statewide rail related infrastructure for Maine businesses and $2,500,000 2020 Line Access Program shippers.

Transfer of dedicated Transportation Alternatives 018524.18 Bicycle-Pedestrian funding to Maine Department of Agriculture, Recreational Statewide Conservation and Forestry for administration and $938,000 2018 Trail, Off-Road Trails Program capital improvements to improve recreational trails statewide.

Transfer of dedicated Transportation Alternatives 018524.19 Bicycle-Pedestrian funding to Maine Department of Agriculture, Recreational Statewide Conservation and Forestry for administration and $938,000 2019 Trail, Off-Road Trails Program capital improvements to improve recreational trails statewide.

Transfer of dedicated Transportation Alternatives 018524.20 Bicycle-Pedestrian funding to Maine Department of Agriculture, Recreational Statewide Conservation and Forestry for administration and $938,000 2020 Trail, Off-Road Trails Program capital improvements to improve recreational trails statewide.

Project management, resource allocation and 018535.18 Aviation development of the Department's Aviation Work Plan Statewide Aviation Program using asset management systems and principles, $208,877 2018 Planning And Research production of the federally required Airport Capital Improvement Plan (ACIP) and other submittals.

172

0123456789 ID/Year Municipality Scope Name Description Funding

Project management, resource allocation and 018535.19 Aviation development of the Department's Aviation Work Plan Statewide Aviation Program using asset management systems and principles, $211,135 2019 Planning And Research production of the federally required Airport Capital Improvement Plan (ACIP) and other submittals.

Project management, resource allocation and 018535.20 Aviation development of the Department's Aviation Work Plan Statewide Aviation Program using asset management systems and principles, $211,135 2020 Planning And Research production of the federally required Airport Capital Improvement Plan (ACIP) and other submittals.

018599.18 Rail State-Owned Statewide Operational improvements to state-owned rail lines. $1,407,000 2018 Line Lines

018599.19 Rail State-Owned Statewide Operational improvements to state-owned rail lines. $1,407,000 2019 Line Lines

018599.20 Rail State-Owned Statewide Operational improvements to state-owned rail lines. $1,407,000 2020 Line Lines

018717.01 Aviation Aviation Systems Update to the Statewide Aviation Systems Plan that Statewide $309,000 2018 Planning And Research Plan may result in safety and infrastructure improvements.

018717.02 Aviation Statewide Crack Safety and infrastructure improvements that may Statewide $309,000 2019 Runway/Taxiway Sealing include statewide crack sealing at multiple airports.

018717.03 Aviation Aviation Systems Update to the Statewide Aviation System Plan that Statewide $309,000 2020 Planning And Research Plan may result in safety and infrastructure improvements.

019253.00 Highway Safety and Spot To improve safety, and for mitigation of potential Statewide Improvements Slopes $230,000 2020 slope failures.

020222.18 External Capital Local Road This program disburses a portion of the State Statewide Assistance Highway Fund directly to municipalities primarily for $21,079,597 2018 Highways Program capital improvement of local roads.

173

0123456789 ID/Year Municipality Scope Name Description Funding

020222.19 External Capital Local Road This program disburses a portion of the State Statewide Assistance Highway Fund directly to municipalities primarily for $21,079,597 2019 Highways Program capital improvement of local roads.

020222.20 External Capital Local Road This program disburses a portion of the State Statewide Assistance Highway Fund directly to municipalities primarily for $20,923,498 2020 Highways Program capital improvement of local roads.

U.S. Fish and Wildlife Service's Boating 020229.18 Marine Infrastructure Grant (BIG) Program Tier I allocation to Statewide BIG Program fund construction, renovation or maintenance of tie- $266,000 2018 Piers, Floats And Fenders up facilities for transient boaters in vessels 26 feet or more in length.

U.S. Fish and Wildlife Service's Boating 020229.19 Marine Infrastructure Grant (BIG) Program Tier I allocation to Statewide BIG Program fund construction, renovation or maintenance of tie- $266,000 2019 Piers, Floats And Fenders up facilities for transient boaters in vessels 26 feet or more in length.

U.S. Fish and Wildlife Service: Boating Infrastructure 020229.20 Marine Grant Program (BIG); Tier I allocation to fund Statewide BIG Program construction, renovation or maintenance of tie-up $266,000 2020 Piers, Floats And Fenders facilities for transient boaters in vessels 26 feet or more in length.

020581.18 Highway Safety and Spot Various Statewide Improvements Statewide striping to increase safety on Maine roads. $6,000,000 2018 Locations

020581.19 Highway Safety and Spot Various Statewide Improvements Statewide striping to increase safety on Maine roads. $6,000,000 2019 Locations

020581.20 Highway Safety and Spot Various Statewide Improvements Statewide striping to increase safety on Maine roads. $6,000,000 2020 Locations

020587.00 Highway Safety and Spot Installation of dynamic wrong way signs on Interstate Statewide Improvements Signs $250,000 2018 ramps.

020773.18 External Capital Rural Transit FTA Section 5311 for Capital Assistance - statewide Statewide $531,330 2018 Public Transportation Capital transit agencies RURAL.

174

0123456789 ID/Year Municipality Scope Name Description Funding

020773.19 External Capital Rural Transit FTA Section 5311 for Capital Assistance - statewide Statewide $531,330 2019 Public Transportation Capital transit agencies RURAL.

020773.20 External Capital Rural Transit FTA Section 5311 for Capital Assistance - statewide Statewide $531,330 2020 Public Transportation Capital transit agencies RURAL.

020777.18 External Capital Rural Transit FTA Section 5310 for Operating / Capital Assistance Statewide $875,000 2018 Public Transportation Capital - transit agencies statewide RURAL.

020777.19 External Capital Rural Transit FTA Section 5310 for Operating / Capital Assistance Statewide $875,000 2019 Public Transportation Capital - transit agencies statewide RURAL.

020777.20 External Capital Rural Transit FTA Section 5310 for Operating / Capital Assistance Statewide $875,000 2020 Public Transportation Capital - transit agencies statewide RURAL.

020791.18 External Capital Urban Transit FTA Section 5310 for Operating / Capital Assistance Statewide $625,000 2018 Public Transportation Capital - transit agencies URBAN.

020791.19 External Capital Urban Transit FTA Section 5310 for Operating / Capital Assistance Statewide $625,000 2019 Public Transportation Capital - transit agencies URBAN.

020791.20 External Capital Urban Transit FTA Section 5310 for Operating / Capital Assistance Statewide $625,000 2020 Public Transportation Capital - transit agencies URBAN.

020809.18 External Capital Public Safety Capital equipment acquisition for the Maine State Statewide $250,000 2018 Freight Equipment Police Commercial Vehicle Enforcement Unit.

020809.19 External Capital Public Safety Capital equipment acquisition for the Maine State Statewide $250,000 2019 Freight Equipment Police Commercial Vehicle Enforcement Unit.

175

0123456789 ID/Year Municipality Scope Name Description Funding

020809.20 External Capital Public Safety Capital equipment acquisition for the Maine State Statewide $250,000 2020 Freight Equipment Police Commercial Vehicle Enforcement Unit.

020828.18 Rail Various Statewide Rail Line Improvements. $1,500,000 2018 Line Locations

020828.19 Rail Various Statewide Rail Line Improvements. $1,500,000 2019 Line Locations

020828.20 Rail Statewide Rail Line Rail Line Improvements $1,500,000 2020 Line

021849.00 Highway Safety and Spot Various Install centerline rumble strips on high volume Statewide Improvements $787,629 2018 Locations Highway Corridor Priority 1 and 2 roads.

021930.00 Highway Rehabilitation Statewide MPI Program Municipal Partnership Initiative Program $8,000,000 2019

021932.00 Highway Rehabilitation Statewide MPI Program Municipal Partnership Initiative Program $8,000,000 2020

021936.00 Highway Safety and Spot Statewide Improvements BPI Program Business Partnership Initiative Program. $3,000,000 2018

021938.00 Highway Safety and Spot Statewide Improvements BPI Program Business Partnership Initiative Program. $3,000,000 2019

021940.00 Highway Safety and Spot Statewide Improvements BPI Program Business Partnership Initiative Program. $3,000,000 2020

176

0123456789 ID/Year Municipality Scope Name Description Funding

022152.18 Highway Safety and Spot ADA Funding to upgrade critical ADA deficiencies in Statewide Improvements $500,000 2018 Improvements priority areas.

022152.19 Highway Safety and Spot ADA Funding to upgrade critical ADA deficiencies in Statewide Improvements $500,000 2019 Improvements priority areas.

022152.20 Highway Safety and Spot ADA Funding to upgrade critical ADA deficiencies in Statewide Improvements $500,000 2020 Improvements priority areas.

022318.00 Bridge Preservation Various Statewide Interstate Bridge Joints - Pavement Synergies. $1,000,000 2018 Locations

022527.19 Highway Light Capital Paving Reserved for Funding for Light Capital Paving projects. Locations Statewide $4,689,178 2019 LCP to be determined.

022777.20 Marine Maine State Maine State Ferry Service Infrastructure Statewide $575,498 2020 Piers, Floats And Fenders Ferry Service Improvements.

022779.18 External Capital Rural Transit FTA Section 5339 Capital Assistance Statewide - Statewide $2,187,500 2018 Public Transportation Capital Statewide National Distribution.

022779.19 External Capital Rural Transit FTA Section 5339 Capital Assistance Statewide - Statewide $2,187,500 2019 Public Transportation Capital Statewide National Distribution.

022779.20 External Capital Rural Transit FTA Section 5339 Capital Assistance Statewide - Statewide $2,187,500 2020 Public Transportation Capital Statewide National Distribution.

022783.19 External Capital Transit FTA Voter approved state bond for Transit Buses - Statewide $1,130,000 2019 Public Transportation Passenger Rail capital projects only.

177

0123456789 ID/Year Municipality Scope Name Description Funding

022783.20 External Capital Transit FTA Voter approved state bond for Transit Buses - Statewide $1,000,000 2020 Public Transportation Passenger Rail capital projects only.

022814.18 Rail Rail/Highway Crossing Improvement Program (23 Rail/Highway USC 130). These funds provide for the elimination of Statewide $1,200,000 2018 Rail/Highway Crossings Crossings hazards and the installation of protective devices at public rail/highway crossings.

022814.19 Rail Rail/Highway Crossing Improvement Program (23 Rail/Highway USC 130). These funds provide for the elimination of Statewide $1,200,000 2019 Rail/Highway Crossings Crossings hazards and the installation of protective devices at public rail/highway crossings.

022814.20 Rail Rail/Highway Crossing Improvement Program (23 Rail/Highway USC 130). These funds provide for the elimination of Statewide $1,200,000 2020 Rail/Highway Crossings Crossing hazards and the installation of protective devices at public rail/highway crossings.

022980.00 Highway Safety and Spot Slope Statewide Improvements Statewide slope stabilization. $1,045,000 2020 Stabilization

022990.00 Highway Safety and Spot Various Statewide Improvements Guard rail end treatment upgrades. $250,000 2019 Locations

022992.00 Highway Safety and Spot Statewide Improvements Sign Upgrades Local roads sign upgrades. $50,000 2019

022996.00 Highway Safety and Spot Safety Commercial vehicle enforcement/ text/ cellphone pull Statewide Improvements $12,000 2019 Improvements off areas at 10-12 locations.

023006.00 Highway Safety and Spot Speed Feedback 2018 Statewide Improvements Speed feedback signs. $200,000 Signs HCP 3

023010.00 Highway Safety and Spot Statewide Improvements Interstate 95 Interstate on-ramp wrong way mitigation. $300,000 2019

178

0123456789 ID/Year Municipality Scope Name Description Funding

023486.00 Rail Various Statewide Rail bridge superstructure improvements. $4,340,000 2018 Rail Bridge Locations

023488.00 Rail Various Statewide Rail bridge superstructure improvements. $4,990,000 2019 Rail Bridge Locations

023490.00 Rail Various Statewide Development of rail bridge improvement projects. $110,000 2020 Rail Bridge Locations

023494.18 Environmental Improvements Proposed funding reserved for light duty electric Statewide VW Settlement vehicle supply equipment. $1,020,000 2018 http://www.maine.gov/mdot/vw/

023494.19 Environmental Improvements Proposed funding reserved for light duty electric Statewide VW Settlement vehicle supply equipment. $2,040,000 2019 http://www.maine.gov/mdot/vw/

023496.18 Environmental Improvements Proposed funding reserved for Diesel Emission Statewide VW Settlement Reduction Act (DERA). Administered by Maine DEP. $1,400,000 2018 http://www.maine.gov/mdot/vw/

023496.19 Environmental Improvements Proposed funding reserved for Diesel Emission Statewide VW Settlement Reduction Act (DERA). Administered by Maine DEP. $2,800,000 2019 http://www.maine.gov/mdot/vw/

023498.18 Environmental Improvements Proposed funding reserved for municipal and private Statewide VW Settlement applicants. $1,750,000 2018 http://www.maine.gov/mdot/vw/

023498.19 Environmental Improvements Proposed funding reserved for municipal and private Statewide VW Settlement applicants. $3,500,000 2019 http://www.maine.gov/mdot/vw/

023503.18 Environmental Improvements Proposed funding reserved for state multimodal Statewide VW Settlement $2,800,000 2018 priorities.

179

0123456789 ID/Year Municipality Scope Name Description Funding

023503.19 Environmental Improvements Proposed funding reserved for state multimodal Statewide VW Settlement $5,600,000 2019 priorities.

023615.00 Bridge Preservation Various Statewide Interstate Bridge Joints - Pavement Synergies. $1,900,000 2019 Locations

023617.00 Bridge Preservation Various Statewide Interstate Bridge Joints - Pavement Synergies. $1,000,000 2020 Locations

023761.00 Highway Safety and Spot Various Statewide Improvements Rumble Strips. $500,000 2020 Locations

023763.00 Highway Safety and Spot High Visibilty Statewide Improvements High Visibilty Cross Walks (5 demonstration projects) $150,000 2019 Cross Walks

023765.00 Highway Safety and Spot Dynamic Speed Statewide Improvements Dynamic Speed signs. $200,000 2020 Signs

023767.00 Highway Safety and Spot Design of variable speed limit devices, Real Time message boards, Road Weather Information System, Statewide Improvements ITS Architecture $720,000 2019 wrong way driver detection and review of ITS architecture.

023769.00 Projects will be selected annually based on Highway Light Capital Paving Light Capital Statewide pavement conditions in order to keep roads $22,500,000 2020 Paving serviceable.

023771.00 Highway Safety and Spot Off Road Went Off Road safety mitigation on 5-8 selected high Statewide Improvements $200,000 2020 Mitigations risk curves on HCP 1 or 2 roads.

023773.00 Highway Safety and Spot Address pedestrian safety infrastructure needs within Pedestrian some of the focus communities that were identified Statewide Improvements $356,180 2020 Needs through Pedestrian Safety Forums/Site Safety Reviews.

180

0123456789 ID/Year Municipality Scope Name Description Funding

023775.00 Highway Safety and Spot Various Statewide Improvements Large truck weigh stations. $250,000 2020 Locations

023777.00 Highway Safety and Spot Various Interstate Wrong Way remediation for Interstate on-ramps and Statewide Improvements $150,000 2020 Ramps off-ramps.

181

0123456789 Ë Statewide Operations

Statewide Operations ID/Year Municipality Scope Name Description Funding

018411.81 Maintenance Excavator Leasing excavators to maintain and upgrade the Region 1 $100,000 2018 Leasing drainage systems prior to paving.

018411.91 Maintenance Excavator Leasing excavators to maintain and upgrade the Region 1 $100,000 2019 Leasing drainage systems prior to paving.

023434.20 Maintenance Excavator Leasing excavators to maintain and upgrade the Region 1 $100,000 2020 Leasing drainage systems prior to paving.

018411.82 Maintenance Excavator Leasing excavators to maintain and upgrade the Region 2 $100,000 2018 Leasing drainage systems prior to paving.

018411.92 Maintenance Excavator Leasing excavators to maintain and upgrade the Region 2 $100,000 2019 Leasing drainage systems prior to paving.

023436.20 Maintenance Excavator Leasing excavators to maintain and upgrade the Region 2 $100,000 2020 Leasing drainage systems prior to paving.

018411.83 Maintenance Excavator Leasing excavators to maintain and upgrade the Region 3 $100,000 2018 Leasing drainage systems prior to paving.

018411.93 Maintenance Excavator Leasing excavators to maintain and upgrade the Region 3 $100,000 2019 Leasing drainage systems prior to paving.

023438.20 Maintenance Excavator Leasing excavators to maintain and upgrade the Region 3 $100,000 2020 Leasing drainage systems prior to paving.

018411.84 Maintenance Excavator Leasing excavators to maintain and upgrade the Region 4 $100,000 2018 Leasing drainage systems prior to paving.

182

0123456789 ID/Year Municipality Scope Name Description Funding

018411.94 Maintenance Excavator Leasing excavators to maintain and upgrade the Region 4 $100,000 2019 Leasing drainage systems prior to paving.

023440.20 Maintenance Excavator Leasing excavators to maintain and upgrade the Region 4 $100,000 2020 Leasing drainage systems prior to paving.

018411.85 Maintenance Excavator Leasing excavators to maintain and upgrade the Region 5 $100,000 2018 Leasing drainage systems prior to paving.

018411.95 Maintenance Excavator Leasing excavators to maintain and upgrade the Region 5 $100,000 2019 Leasing drainage systems prior to paving.

023442.20 Maintenance Excavator Leasing excavators to maintain and upgrade the Region 5 $100,000 2020 Leasing drainage systems prior to paving.

Portland Area Comprehensive Transportation 002142.18 Work Program Management System (PACTS) Unified Planning Work Program: Federally mandated program associated with Regional PACTS Planning $1,038,326 2018 Planning and Research Maine's U.S. Census-defined metropolitan planning area in the Greater Portland region. PACTS Sponsored.

Portland Area Comprehensive Transportation 002142.19 Work Program Management System (PACTS) Unified Planning Work Program: Federally mandated program associated with Regional PACTS Planning $1,038,326 2019 Planning and Research Maine's U.S. Census-defined metropolitan planning area in the Greater Portland region. PACTS Sponsored.

Portland Area Comprehensive Transportation 002142.20 Work Program Management System (PACTS) Unified Planning Work Program: Federally mandated program associated with Regional PACTS Planning $1,038,326 2020 Planning and Research Maine's U.S. Census-defined metropolitan planning area in the Greater Portland region. PACTS Sponsored.

Androscoggin Transportation Resource Center 002153.18 Work Program Management (ATRC) Unified Planning Work Program: Federally Regional ATRC Planning mandated program associated with Maine's U.S. $385,434 2018 Planning and Research Census-defined metropolitan planning area in the Greater Lewiston-Auburn region. ATRC Sponsored.

Androscoggin Transportation Resource Center 002153.19 Work Program Management (ATRC) Unified Planning Work Program: Federally Regional ATRC Planning mandated program associated with Maine's U.S. $385,434 2019 Planning and Research Census-defined metropolitan planning area in the Greater Lewiston-Auburn region. ATRC Sponsored.

183

0123456789 ID/Year Municipality Scope Name Description Funding

Androscoggin Transportation Resource Center 002153.20 Work Program Management (ATRC) Unified Planning Work Program: Federally Regional ATRC Planning mandated program associated with Maine's U.S. $385,434 2020 Transit Support Census-defined metropolitan planning area in the Greater Lewiston-Auburn region. ATRC Sponsored.

Bangor Area Comprehensive Transportation System 002163.18 Work Program Management (BACTS) Unified Planning Work Program: Federally Regional BACTS Planning mandated program associated with Maine's U.S. $390,434 2018 Planning and Research Census-defined metropolitan planning area in the Greater Bangor region. BACTS Sponsored.

Bangor Area Comprehensive Transportation System 002163.19 Work Program Management (BACTS) Unified Planning Work Program: Federally Regional BACTS Planning mandated program associated with Maine's U.S. $390,434 2019 Planning and Research Census-defined metropolitan planning area in the Greater Bangor region. BACTS Sponsored.

Bangor Area Comprehensive Transportation System 002163.20 Work Program Management (BACTS) Unified Planning Work Program: Federally Regional BACTS Planning mandated program associated with Maine's U.S. $390,434 2020 Planning and Research Census-defined metropolitan planning area in the Greater Bangor region. BACTS Sponsored.

Kittery Area Comprehensive Transportation System 002173.18 Work Program Management (KACTS) Unified Planning Work Program: Federally Regional KACTS Planning mandated program associated with Maine's U.S. $169,093 2018 Planning and Research Census-defined metropolitan planning area in the Greater Kittery region. KACTS Sponsored.

Kittery Area Comprehensive Transportation System 002173.19 Work Program Management (KACTS) Unified Planning Work Program: Federally Regional KACTS Planning mandated program associated with Maine's U.S. $169,093 2019 Planning and Research Census-defined metropolitan planning area in the Greater Kittery region. KACTS Sponsored.

Kittery Area Comprehensive Transportation System 002173.20 Work Program Management (KACTS) Unified Planning Work Program: Federally Regional KACTS Planning mandated program associated with Maine's U.S. $169,093 2020 Planning and Research Census-defined metropolitan planning area in the Greater Kittery region. KACTS Sponsored.

014845.18 Policy Planning and Research AVCOG RPO Androscoggin Valley Council of Governments Regional $12,500 2018 Support (AVCOG) Regional Planning Organization support.

014845.19 Policy Planning and Research AVCOG RPO Androscoggin Valley Council of Governments Regional $12,500 2019 Support (AVCOG) Regional Planning Organization support.

014845.20 Policy Planning and Research AVCOG RPO Androscoggin Valley Council of Governments Regional $12,500 2020 Support (AVCOG) Regional Planning Organization support.

184

0123456789 ID/Year Municipality Scope Name Description Funding

014846.18 Policy Planning and Research GPCOG RPO Greater Portland Council of Governments (GPCOG) Regional $12,500 2018 Support Regional Planning Organization support.

014846.19 Policy Planning and Research GPCOG RPO Greater Portland Council of Governments (GPCOG) Regional $12,500 2019 Support Regional Planning Organization support.

014846.20 Policy Planning and Research GPCOG RPO Greater Portland Council of Governments (GPCOG) Regional $12,500 2020 Support Regional Planning Organization support.

014847.18 Policy Planning and Research HCPC RPO Hancock County Planning Commission (HCPC) Regional $10,000 2018 Support Regional Planning Organization support.

014847.19 Policy Planning and Research HCPC RPO Hancock County Planning Commission (HCPC) Regional $10,000 2019 Support Regional Planning Organization support.

014847.20 Policy Planning and Research HCPC RPO Hancock County Planning Commission (HCPC) Regional $10,000 2020 Support Regional Planning Organization support.

014848.18 Policy Planning and Research KVCOG RPO Kennebec Valley Council of Governments (KVCOG) Regional $12,500 2018 Support Regional Planning Organization support.

014848.19 Policy Planning and Research KVCOG RPO Kennebec Valley Council of Governments (KVCOG) Regional $12,500 2019 Support Regional Planning Organization support.

014848.20 Policy Planning and Research KVCOG RPO Kennebec Valley Council of Governments (KVCOG) Regional $12,500 2020 Support Regional Planning Organization support.

014849.18 Policy Planning and Research LCRPC RPO Lincoln County Regional Planning Commission Regional $7,500 2018 Support (LCRPC) Regional Planning Organization support.

185

0123456789 ID/Year Municipality Scope Name Description Funding

014849.19 Policy Planning and Research LCRPC RPO Lincoln County Regional Planning Commission Regional $7,500 2019 Support (LCRPC) Regional Planning Organization support.

014849.20 Policy Planning and Research LCPC RPO Lincoln County Regional Planning Commission Regional $7,500 2020 Support (LCRPC) Regional Planning Organization support.

014850.18 Policy Planning and Research Regional Planning Support Mid-Coast Regional Planning Organization support. $7,500 2018

014850.19 Policy Planning and Research Regional Planning Support Mid-Coast Regional Planning Organization support. $7,500 2019

014850.20 Policy Planning and Research Regional Planning Support Mid-Coast Regional Planning Organization support. $7,500 2020

014851.18 Policy Planning and Research MCRPC RPO Mid-Coast Regional Planning Commission (MCRPC) Regional $10,000 2018 Support Regional Planning Organization support.

014851.19 Policy Planning and Research MCRPC RPO Mid-Coast Regional Planning Commission (MCRPC) Regional $10,000 2019 Support Regional Planning Organization support.

014851.20 Policy Planning and Research MCRPC RPO Mid-Coast Regional Planning Commission (MCRPC) Regional $10,000 2020 Support Regional Planning Organization support.

014852.18 Policy Planning and Research NMDC RPO Northern Maine Development Commission (NMDC) Regional $10,000 2018 Support Regional Planning Organization support.

014852.19 Policy Planning and Research NMDC RPO Northern Maine Development Commission (NMDC) Regional $10,000 2019 Support Regional Planning Organization support.

186

0123456789 ID/Year Municipality Scope Name Description Funding

014852.20 Policy Planning and Research NMDC RPO Northern Maine Development Commission (NMDC) Regional $10,000 2020 Support Regional Planning Organization support.

014853.18 Policy Planning and Research Penobscot/Piscataquis Regional Planning Regional Planning Support $10,000 2018 Organization support.

014853.19 Policy Planning and Research Penobscot/Piscataquis Regional Planning Regional Planning Support $10,000 2019 Organization support.

014853.20 Policy Planning and Research Penobscot/Piscataquis Regional Planning Regional Planning Support $10,000 2020 Organization support.

014854.18 Southern Maine Planning and Development Policy Planning and Research SMPDC RPO Regional Commission (SMPDC) Regional Planning $12,500 2018 Support Organization support.

014854.19 Southern Maine Planning and Development Policy Planning and Research SMPDC RPO Regional Commission (SMPDC) Regional Planning $12,500 2019 Support Organization support.

014854.20 Southern Maine Planning and Development Policy Planning and Research SMPDC RPO Regional Commission (SMPDC) Regional Planning $12,500 2020 Support Organization support.

014855.18 Policy Planning and Research WCCOG RPO Washington County Council of Governments Regional $7,500 2018 Support (WCCOG) Regional Planning Organization support.

014855.19 Policy Planning and Research WCCOG RPO Washington County Council of Governments Regional $7,500 2019 Support (WCCOG) Regional Planning Organization support.

014855.20 Policy Planning and Research WCCOG RPO Washington County Council of Governments Regional $7,500 2020 Support (WCCOG) Regional Planning Organization support.

187

0123456789 ID/Year Municipality Scope Name Description Funding

018619.00 MaineDOT Building and Lot Visitor Replacements of windows and air conditioner in the Regional Maintenance Information $140,000 2019 Kittery visitors information center. Center

022130.00 Inventory and Performance High Crash Locations Review and High Accident Regional Management Recommendations throughout the PACTS region. $100,000 2018 Locations PACTS Sponsored.

023446.00 MaineDOT Building and Lot Visitor Northbound and southbound HVAC (Ventiliation 2018 Regional Maintenance Information $80,000 System) upgrade. Center HCP 1

023448.00 MaineDOT Building and Lot Visitor Northbound and southbound Visitor Information Regional Maintenance Information $40,000 2018 Center vestibule heating system. Center

023450.00 MaineDOT Building and Lot Visitor Regional Maintenance Information Visitor information center interior LED lighting. $20,000 2020 Center

002102.18 Inventory and Performance Highway Statewide Management State transportation network. $60,000 2018 Classification

002102.19 Inventory and Performance Highway Statewide Management State transportation network. $60,000 2019 Classification

002102.20 Inventory and Performance Highway Statewide Management State transportation network. $60,000 2020 Classification

Develops purpose and need, project definition, and 002116.18 Policy Planning and Research assignment of cost shares through project Statewide Scoping Division agreements. Also oversees MPO scoping and $910,000 2018 performs major studies, traffic analysis, safety project selection, and ITS planning.

Develops purpose and need, project definition, and 002116.19 Policy Planning and Research assignment of cost shares through project Statewide Scoping Division agreements. Also oversees MPO scoping and $920,000 2019 performs major studies, traffic analysis, safety project selection, and ITS planning.

188

0123456789 ID/Year Municipality Scope Name Description Funding

Develops purpose and need, project definition, and 002116.20 Policy Planning and Research assignment of cost shares through project Statewide Scoping Division agreements. Also oversees MPO scoping and $920,000 2020 performs major studies, traffic analysis, safety project selection, and ITS planning.

Management of MaineDOT Highway Asset 002118.18 Work Program Management Management System, including inventory, highway Highway Statewide data collection, asset priorities, customer service $400,000 2018 Administration Management levels, performance reporting, and prioritization/ scoping of pavement preservation candidates.

Management of MaineDOT Highway Asset 002118.19 Work Program Management Management System, including inventory, highway Highway Statewide data collection, asset priorities, customer service $400,000 2019 Administration Management levels, performance reporting, and prioritization/ scoping of pavement preservation candidates.

Management of MaineDOT Highway Asset 002118.20 Work Program Management Management System, including inventory, highway Highway Statewide data collection, asset priorities, customer service $400,000 2020 Administration Management levels, performance reporting, and prioritization/ scoping of pavement preservation candidates.

002134.18 Policy Planning and Research Research Administration and management of the federally Statewide $120,000 2018 Administration mandated research program.

002134.19 Policy Planning and Research Research Administration and management of the federally Statewide $120,000 2019 Administration mandated research program.

002134.20 Policy Planning and Research Research Administration and management of the federally Statewide $120,000 2020 Administration mandated research program.

Work includes resource allocation and development 004777.18 Program Policy Planning and Research of the Department's Work Plan using asset Statewide Development $495,000 2018 management systems and principles, production of Division the federally required STIP and other submittals.

Work includes resource allocation and development 004777.19 Program Policy Planning and Research of the Department's Work Plan using asset Statewide Development $510,000 2019 management systems and principles, production of Division the federally required STIP and other submittals.

Work includes resource allocation and development 004777.20 Program Policy Planning and Research of the Department's Work Plan using asset Statewide Development $510,000 2020 management systems and principles, production of Division the federally required STIP and other submittals.

189

0123456789 ID/Year Municipality Scope Name Description Funding

005692.18 Policy Planning and Research Statewide Work includes federally mandated Statewide Statewide $350,000 2018 Planning Planning. Customer outreach.

005692.19 Policy Planning and Research Statewide Work includes federally mandated Statewide Statewide $380,000 2019 Planning Planning. Customer outreach.

005692.20 Policy Planning and Research Statewide Work includes federally mandated Statewide Statewide $380,000 2020 Planning Planning. Customer outreach.

006309.18 Work Program Management Application development and user support of the Statewide GIS Management $770,000 2018 Administration Department's Geographical Information Systems.

006309.19 Work Program Management Application development and user support of the Statewide GIS Management $770,000 2019 Administration Department's Geographical Information Systems.

006309.20 Work Program Management Application development and user support of the Statewide GIS Management $770,000 2020 Administration Department's Geographical Information Systems.

007115.18 Inventory and Performance Post - Work includes evaluation of projects to identify Statewide Management Construction efficiencies and increase the cost effectiveness of $40,000 2018 Evaluation future projects.

007115.19 Inventory and Performance Post - Work includes evaluation of projects to identify Statewide Management Construction efficiencies and increase the cost effectiveness of $40,000 2019 Evaluation future projects.

007115.20 Inventory and Performance Post - Work includes evaluation of projects to identify Statewide Management Construction efficiencies and increase the cost effectiveness of $40,000 2020 Evaluation future projects.

007519.18 Policy Planning and Research New Product Evaluate new products to identify efficiencies and Statewide $80,000 2018 Evaluation increase cost effectiveness.

190

0123456789 ID/Year Municipality Scope Name Description Funding

007519.19 Policy Planning and Research New Product Evaluate new products to identify efficiencies and Statewide $80,000 2019 Evaluation increase cost effectiveness.

007519.20 Policy Planning and Research New Product Evaluate new products to identify efficiencies and Statewide $80,000 2020 Evaluation increase cost effectiveness.

008246.18 External System Operations Municipal Salt Coordination of the Municipal Salt and Sand Statewide $14,000 2018 Highways and Sand Program.

008958.18 Projects established to address research needs, Policy Planning and Research such as: conducting synthesis of the state of the Statewide Problem Solving $60,000 2018 practice, collecting and analyzing field data and longer-term performance evaluation.

008958.19 Projects established to address research needs, Policy Planning and Research such as: conducting synthesis of the state of the Statewide Problem Solving $60,000 2019 practice, collecting and analyzing field data and longer-term performance evaluation.

008958.20 Projects established to address research needs, Policy Planning and Research such as: conducting synthesis of the state of the Statewide Problem Solving $60,000 2020 practice, collecting and analyzing field data and longer-term performance evaluation.

008993.18 Inventory and Performance Statewide traffic volume counts for monitoring traffic Traffic Volume growth, meeting FHWA reporting requirements, and Statewide Management $775,000 2018 Counts providing detailed information for Legislative and Department analysis.

008993.19 Inventory and Performance Statewide traffic volume counts for monitoring traffic Traffic Volume growth, meeting FHWA reporting requirements, and Statewide Management $800,000 2019 Counts providing detailed information for Legislative and Department analysis.

008993.20 Inventory and Performance Statewide traffic volume counts for monitoring traffic Traffic Volume growth, meeting FHWA reporting requirements, and Statewide Management $800,000 2020 Counts providing detailed information for Legislative and Department analysis.

008995.18 Inventory and Performance Vehicle Manual collection of vehicle size and weight Statewide Management $100,000 2018 Classification classification data for highway and bridge design.

191

0123456789 ID/Year Municipality Scope Name Description Funding

008995.19 Inventory and Performance Vehicle Manual collection of vehicle size and weight Statewide Management $100,000 2019 Classification classification data for highway and bridge design.

008995.20 Inventory and Performance Vehicle Manual collection of vehicle size and weight Statewide Management $100,000 2020 Classification classification data for highway and bridge design.

008998.18 Inventory and Performance Vehicle Size and Operation and analysis of vehicle weigh in motion Statewide Management Weight $175,000 2018 devices used in highway and bridge design. Characteristics

008998.19 Inventory and Performance Vehicle Size and Operation and analysis of vehicle weigh in motion Statewide Management Weight $175,000 2019 devices used in highway and bridge design. Characteristics

008998.20 Inventory and Performance Vehicle Size and Operation and analysis of vehicle weigh in motion Statewide Management Weight $175,000 2020 devices used in highway and bridge design. Characteristics

008999.18 Inventory and Performance Collection of data from origin and destination, and Statewide Management Traffic Studies other traffic studies for use in improving highway $90,000 2018 system efficiency.

008999.19 Inventory and Performance Collection of data from origin and destination, and Statewide Management Traffic Studies other traffic studies for use in improving highway $90,000 2019 system efficiency.

008999.20 Inventory and Performance Collection of data from origin and destination, and Statewide Management Traffic Studies other traffic studies for use in improving highway $100,000 2020 system efficiency.

009001.18 Inventory and Performance Collecting and categorizing crash records for Statewide Management Crash Records $390,000 2018 analysis in targeting safety improvements.

009001.19 Inventory and Performance Collecting and categorizing crash records for Statewide Management Crash Records $390,000 2019 analysis in targeting safety improvements.

192

0123456789 ID/Year Municipality Scope Name Description Funding

009001.20 Inventory and Performance Collecting and categorizing crash records for Statewide Management Crash Records $390,000 2020 analysis in targeting safety improvements.

Operation of the Maine Local Roads Center, the 009676.18 Local Road Assistance Program (LRAP), highway Communication and Outreach Community Statewide classifications, Urban Compact boundaries, State/US $48,000 2018 Services Division Route Numbering, Municipal Sand/Salt Facility Program, and the Adopt-A-Highway.

Operation of the Maine Local Roads Center, the 009676.19 Local Road Assistance Program (LRAP), highway Communication and Outreach Community Statewide classifications, Urban Compact boundaries, State/US $49,000 2019 Services Division Route Numbering, Municipal Sand/Salt Facility Program, and the Adopt-A-Highway.

Operation of the Maine Local Roads Center, the 009676.20 Local Road Assistance Program (LRAP), highway Communication and Outreach Community Statewide classifications, Urban Compact boundaries, State/US $49,000 2020 Services Division Route Numbering, Municipal Sand/Salt Facility Program, and the Adopt-A-Highway.

Bureau of Planning management and support, 009730.18 including development of required federal Administration documents, direction of planning activities statewide, Statewide Capital Planning $420,000 2018 Work Plan development, management and performance management of 30 FTEs in three divisions.

Bureau of Planning management and support, 009730.19 including development of required federal Administration documents, direction of planning activities statewide, Statewide Capital Planning $430,000 2019 Work Plan development, management and performance management of 30 FTEs in three divisions.

Bureau of Planning management and support, 009730.20 including development of required federal Administration documents, direction of planning activities statewide, Statewide Capital Planning $430,000 2020 Work Plan development, management and performance management of 30 FTEs in three divisions.

009860.18 Interagency transfer of funds to the Maine DEP's Air Policy Planning and Research Mobile Source Statewide Bureau for federally required conformity and related $250,000 2018 Impact analysis and reporting.

009860.19 Interagency transfer of funds to the Maine DEP's Air Policy Planning and Research Mobile Source Statewide Bureau for federally required conformity and related $250,000 2019 Impact analysis and reporting.

009860.20 Interagency transfer of funds to the Maine DEP's Air Policy Planning and Research Mobile Source Statewide Bureau for federally required conformity and related $250,000 2020 Impact analysis and reporting.

193

0123456789 ID/Year Municipality Scope Name Description Funding

012818.18 Work Program Management Funding for USFWS liaison to review projects subject to the federal Clean Water Act and Endangered Statewide USFWS Reviews $260,000 2018 Compliance Activities Species Act to ensure on-time and in-compliance project delivery.

012818.19 Work Program Management Funding for USFWS liaison to review projects subject to the federal Clean Water Act and Endangered Statewide USFWS Reviews $260,000 2019 Compliance Activities Species Act to ensure on-time and in-compliance project delivery.

012818.20 Work Program Management Funding for USFWS liaison to review projects subject to the federal Clean Water Act and Endangered Statewide USFWS Reviews $260,000 2020 Compliance Activities Species Act to ensure on time and in compliance project delivery.

014856.18 Regional multimodal transportation planning services Policy Planning and Research Regional consistent with current state and federal Statewide $337,500 2018 Planning transportation laws with emphasis on municipal outreach.

014856.19 Regional multimodal transportation planning services Policy Planning and Research Regional consistent with current state and federal Statewide $337,500 2019 Planning transportation laws with emphasis on municipal outreach.

014856.20 Regional multimodal transportation planning services Policy Planning and Research Regional consistent with current state and federal Statewide $337,500 2020 Planning transportation laws with emphasis on municipal outreach.

016336.18 Information Technology Enhance the MLRC Road System Management RSMS Sign Statewide Support Software to include sign management with low-end $25,000 2018 Software GIS component.

016336.19 Information Technology Enhance the MLRC Road System Management RSMS Sign Statewide Support Software to include sign management with low-end $25,000 2019 Software GIS component.

016336.20 Information Technology Enhance the MLRC Road System Management RSMS Sign Statewide Support Software to include sign management with low-end $25,000 2020 Software GIS component.

Implement requirements of the Clean Water Act, 017266.18 Work Program Management including retrofits of drainage systems on MaineDOT MEPDES Statewide assets within Urban Impaired Stream watersheds. $150,000 2018 Compliance Activities General Permits Maine Pollutant Discharge Elimination System (MEPDES).

194

0123456789 ID/Year Municipality Scope Name Description Funding

Implement requirements of the Clean Water Act, 017266.19 Work Program Management including retrofits of drainage systems on MaineDOT MEPDES Statewide assets within Urban Impaired Stream watersheds. $150,000 2019 Planning and Research General Permits Maine Pollutant Discharge Elimination System (MEPDES).

Implement requirements of the Clean Water Act. 017266.20 Work Program Management Including retrofits of drainage systems on MaineDOT MEPDES Statewide assests within Urban Impaired Stream watersheds. $150,000 2020 Planning and Research General Permits Maine Pollutant Discharge Elimination System (MEPDES).

017269.18 Work Program Management Manage existing mitigation properties to maintain Statewide Mitigation $10,000 2018 Compliance Activities regulatory compliance.

017269.19 Work Program Management Manage existing mitigation properties to maintain Statewide Mitigation $10,000 2019 Compliance Activities regulatory compliance.

017269.20 Work Program Management Manage existing mitigation properties to maintain Statewide Mitigation $10,000 2020 Compliance Activities regulatory compliance.

017275.18 Work Program Management Historic Ensure efficient delivery of work subject to federal Statewide Resource $60,000 2018 Compliance Activities historic resource review under Sections 106 and 4(f). Reviews

017275.19 Work Program Management Historic Ensure efficient delivery of work subject to federal Statewide Resource $60,000 2019 Compliance Activities historic resource review under Sections 106 and 4(f). Reviews

017275.20 Work Program Management Historic Ensure efficient delivery of work subject to federal Statewide Resource $60,000 2020 Compliance Activities historic resource review under Sections 106 and 4(f). Reviews

Develop bank site proposals and pursue their 017279.18 Work Program Management addition to MaineDOT's Umbrella Mitigation Banking Statewide Mitigation Bank instrument to reduce costs associated with project- $15,000 2018 Compliance Activities specific mitigation and improve efficiency of mitigation delivery.

Develop bank site proposals and pursue their 017279.19 Work Program Management addition to MaineDOT's Umbrella Mitigation Banking Statewide Mitigation Bank instrument to reduce costs associated with project- $10,000 2019 Compliance Activities specific mitigation and improve efficiency of mitigation delivery.

195

0123456789 ID/Year Municipality Scope Name Description Funding

Develop bank site proposals and pursue their 017279.20 Work Program Management addition to MaineDOT's Umbrella Mitigation Banking Statewide Mitigation Bank instrument to reduce costs associated with project- $10,000 2020 Compliance Activities specific mitigation and improve efficiency of mitigation delivery.

017582.18 Funding for the continued analysis of potential Policy Planning and Research transportation solutions that promote economic Statewide Planning Studies $100,000 2018 development, leverage additional investment, and improve safety and mobility.

017582.19 Funding for the continued analysis of potential Policy Planning and Research transportation solutions that promote economic Statewide Planning Studies $100,000 2019 development, leverage additional investment, and improve safety and mobility.

017582.20 Funding for the continued analysis of potential Policy Planning and Research transportation solutions that promote economic Statewide Planning Studies $100,000 2020 development, leverage additional investment, and improve safety and mobility.

017690.18 External System Operations Regulatory requirements dictate that MaineDOT Statewide Fish Passage complete post-construction monitoring on stream $25,000 2018 System-Wide crossing structures of particular importance.

017690.19 External System Operations Regulatory requirements dictate that MaineDOT Statewide Fish Passage complete post-construction monitoring on stream $25,000 2019 System-Wide crossing structures of particular importance.

017690.20 External System Operations Regulatory requirements dictate that MaineDOT Statewide Fish Passage complete post-construction monitoring on stream $25,000 2020 System-Wide crossing structures of particular importance.

018099.18 Work Program Management Statewide Data Collection Existing condition data collection and processing. $100,000 2018 Capital Project Support

018099.19 Work Program Management Statewide Data Collection Existing condition data collection and processing. $100,000 2019 Capital Project Support

018099.20 Work Program Management Statewide Data Collection Existing condition data collection and processing. $100,000 2020 Capital Project Support

196

0123456789 ID/Year Municipality Scope Name Description Funding

018452.18 MaineDOT Multimodal System Ferry Service Statewide Operations Maine State Ferry Service operations. $10,672,938 2018 Operations

018452.19 MaineDOT Multimodal System Ferry Service Statewide Operations Maine State Ferry Service operations. $10,791,422 2019 Operations

018452.20 MaineDOT Multimodal System Ferry Service Statewide Operations Maine State Ferry Service operations. $11,007,250 2020 Operations

018501.18 Maintenance Vegetation Statewide Roadside vegetation management. $100,000 2018 Management

018501.19 Maintenance Vegetation Statewide Roadside vegetation management. $100,000 2019 Management

018501.20 Maintenance Vegetation Statewide Roadside vegetation management. $100,000 2020 Management

018505.18 Planning Policy Planning and Research This competitive program supports regional planning Statewide Partnership $200,000 2018 efforts through grants awarded on a best-value basis. Initiative

018505.19 Planning Policy Planning and Research This competitive program supports regional planning Statewide Partnership $200,000 2019 efforts through grants awarded on a best-value basis. Initiative

018505.20 Planning Policy Planning and Research This competitive program supports regional planning Statewide Partnership $200,000 2020 efforts through grants awarded on a best-value basis. Initiative

018507.18 Employee Education and Occupational safety training, education and wellness Statewide Training Training programs to reduce costs and increase staff $64,000 2018 productivity.

197

0123456789 ID/Year Municipality Scope Name Description Funding

018507.19 Employee Education and Occupational safety training, education and wellness Statewide Training Training programs to reduce costs and increase staff $64,000 2019 productivity.

018507.20 Employee Education and Occupational safety training, education and wellness Statewide Training Training programs to reduce costs and increase staff $64,000 2020 productivity.

018509.18 Work Program Management Develop and implement initiatives to ensure Health, Safety MaineDOT operations and personnel work in Statewide $425,000 2018 Employee Safety and Training and Compliance accordance with applicable and relevant environmental, health and safety regulations.

018509.19 Work Program Management Develop and implement initiatives to ensure Health, Safety MaineDOT operations and personnel work in Statewide $435,000 2019 Employee Safety and Training and Compliance accordance with applicable and relevant environmental, health and safety regulations.

018509.20 Work Program Management Develop and implement initiatives to ensure Health, Safety MaineDOT operations and personnel work in Statewide $445,000 2020 Employee Safety and Training and Compliance accordance with applicable and relevant environmental, health and safety regulations.

018520.18 Work Program Management Increase traveler safety, decrease wildlife mortality, Animal Crash Statewide and comply with relevant regulations by reducing $25,000 2018 Compliance Activities Reduction incidents.

018520.19 Work Program Management Increase traveler safety, decrease wildlife mortality, Animal Crash Statewide and comply with relevant regulations by reducing $15,000 2019 Compliance Activities Reduction incidents.

018520.20 Work Program Management Increase traveler safety, decrease wildlife mortality, Animal Crash Statewide and comply with relevant regulations by reducing $35,000 2020 Compliance Activities Reduction incidents.

018522.18 Bicycle and Pedestrian Safety Education Program in Communication and Outreach Bike/Ped Safety schools and communities statewide, focuses on Statewide $156,000 2018 Program safety presentations and activities to improve safety behaviors to reduce injuries and crashes.

018522.19 Bicycle and Pedestrian Safety Education Program in Communication and Outreach Bike/Ped Safety schools and communities statewide, focuses on Statewide $156,000 2019 Program safety presentations and activities to improve safety behaviors to reduce injuries and crashes.

198

0123456789 ID/Year Municipality Scope Name Description Funding

018522.20 Bicycle and Pedestrian Safety Education Program in Communication and Outreach Bike/Ped Safety schools and communities statewide, focuses on Statewide $156,000 2020 Program safety presentations and activities to improve safety behaviors to reduce injuries and crashes.

018526.18 Administration Funding to support the operations of the Executive Statewide Executive Office $1,350,000 2018 Office.

018526.19 Administration Funding to support the operations of the Executive Statewide Executive Office $1,350,000 2019 Office.

018526.20 Administration Funding to support the operations of the Executive Statewide Executive Office $1,350,000 2020 Office.

Work includes labor relations, workers compensation 018528.18 administration, recruitment and retention as well as Administration Human Statewide supporting managers in policy compliance, state and $1,400,000 2018 Resources federal regulations, and collective bargaining administration.

Work includes labor relations, workers compensation 018528.19 administration, recruitment and retention as well as Administration Human Statewide supporting managers in policy compliance, state and $1,400,000 2019 Resources federal regulations, and collective bargaining administration.

Work includes labor relations, workers compensation 018528.20 administration, recruitment and retention as well as Administration Human Statewide supporting managers in policy compliance, state and $1,400,000 2020 Resources federal regulations, and collective bargaining administration.

018533.18 Work Program Management Assists employees with printing large print jobs and supply needs. Prepares bid documents and Statewide Support Services $1,000,000 2018 Capital Project Support publications for sale to the public. Organizes all incoming and outgoing mail/packages.

018533.19 Work Program Management Assists employees with printing large print jobs and supply needs. Prepares bid documents and Statewide Support Services $1,000,000 2019 Capital Project Support publications for sale to the public. Organizes all incoming and outgoing mail/packages.

018533.20 Work Program Management Assists employees with printing large print jobs and supply needs. Prepares bid documents and Statewide Support Services $1,000,000 2020 Capital Project Support publications for sale to the public. Organizes all incoming and outgoing mail/packages.

199

0123456789 ID/Year Municipality Scope Name Description Funding

018549.18 Inventory and Performance Ancillary Inspection of mast arms, sign trusses, signals, and Statewide Management $500,000 2018 Structures highway lighting.

018549.19 Inventory and Performance Ancillary Inspection of mast arms, sign trusses, signals, and Statewide Management $500,000 2019 Structures highway lighting.

018549.20 Inventory and Performance Ancillary Inspection of mast arms, sign trusses, signals, and Statewide Management $500,000 2020 Structures highway lighting.

To support Maine Suicide Prevention Program's 018586.18 Communication and Outreach research, media education, and training efforts, Statewide NAMI especially those involving transportation $10,000 2018 infrastructure. This funding provided to the National Alliance on Mental Illness - Maine Affiliate.

018877.00 Communication and Outreach Maine Transportation Safety Coalition public safety Statewide Safety Coalition $6,000 2018 outreach and training.

018893.18 Communication and Outreach Sign Upgrade sign packages for municipalities Statewide $50,000 2018 Upgrade/Training administered through Maine Local Roads Center.

018893.19 Communication and Outreach Sign Upgrade sign packages for municipalities Statewide $50,000 2019 Upgrade/Training administered through Maine Local Roads Center.

018893.20 Communication and Outreach Sign Upgrade sign packages for municipalities Statewide $50,000 2020 Upgrade/Training administered through Maine Local Roads Center.

018905.18 Work Program Management Reimbursement funding for multimodal freight rail Statewide Freight Rail $603,599 2018 Freight and Business Services grade crossings.

018905.19 Work Program Management Reimbursement funding for multimodal freight rail Statewide Freight Rail $603,599 2019 Freight and Business Services grade crossings.

200

0123456789 ID/Year Municipality Scope Name Description Funding

018905.20 Work Program Management Reimbursement funding for multimodal freight rail Statewide Freight Rail $603,599 2020 Freight and Business Services grade crossings.

019066.00 Work Program Management PROJEX To further develop the Department's project Statewide $1,085,000 2018 Administration Upgrade management information system.

019358.18 Work Program Management Assess regulatory compliance of crossing structure Aquatic Statewide projects. Identify measures to avoid and mitigate for $30,000 2018 Compliance Activities Resources environmental impacts.

019358.19 Work Program Management Assess regulatory compliance of crossing structure Aquatic Statewide projects. Identify measures to avoid and mitigate for $30,000 2019 Compliance Activities Resources environmental impacts.

019358.20 Work Program Management Assess regulatory compliance of crossing structure Aquatic Statewide projects. Identify measures to avoid and mitigate for $30,000 2020 Compliance Activities Resources environmental impacts.

019364.18 Work Program Management Natural Areas Data collection and project screening to ensure Statewide $15,000 2018 Compliance Activities Program regulatory compliance.

019364.19 Work Program Management Natural Areas Data collection and project screening to ensure Statewide $15,000 2019 Compliance Activities Program regulatory compliance.

019364.20 Work Program Management Natural Areas Data collection and project screening to ensure Statewide $15,000 2020 Compliance Activities Program regulatory compliance.

Operation of 10 gauges in USGS-managed statewide 019369.18 Work Program Management stream gage network. Data is critical for maintaining Streamflow Statewide up-to-date hydrologic design methods as well as $80,000 2018 Compliance Activities Gauging tracking climate change impacts on river flows. Cost share is MaineDOT 60% / USGS 40%.

Operation of 10 gauges in USGS-managed statewide 019369.19 Work Program Management stream gage network. Data is critical for maintaining Streamflow Statewide up-to-date hydrologic design methods as well as $80,000 2019 Compliance Activities Gauging tracking climate change impacts on river flows. Cost share is MaineDOT 60% / USGS 40%.

201

0123456789 ID/Year Municipality Scope Name Description Funding

Operation of 10 gauges in USGS-managed statewide 019369.20 Work Program Management stream gage network. Data is critical for maintaining Streamflow Statewide up-to-date hydrologic design methods as well as $80,000 2020 Compliance Activities Guaging tracking climate change impacts on river flows. Cost share is MaineDOT 60% / USGS 40%.

019371.18 Work Program Management Data collection and project screening to identify Endangered nexus with state and federal endangered species to Statewide $70,000 2018 Compliance Activities Species ensure efficient, compliant design, construction, and performance.

019371.19 Work Program Management Data collection and project screening to identify Endangered nexus with state and federal endangered species to Statewide $70,000 2019 Compliance Activities Species ensure efficient, compliant design, construction, and performance.

019371.20 Work Program Management Data collection and project screening to identify Endangered nexus with state and federal endangered species to Statewide $70,000 2020 Compliance Activities Species ensure efficient, compliant design, construction, and performance.

019518.18 MaineDOT Highway System Park and Ride Statewide Operations Statewide maintenance of Park and Ride Lots. $40,000 2018 Lots

019518.19 MaineDOT Highway System Park and Ride Statewide Operations Statewide maintenance of Park and Ride Lots. $40,000 2019 Lots

019518.20 MaineDOT Highway System Park and Ride Statewide Operations Statewide maintenance of Park and Ride lots. $40,000 2020 Lots

019786.18 Employee Education and Fairfield Training Funding for the operation and maintenance of the Statewide Training $90,000 2018 Center MaineDOT Fairfield Training Center.

019786.19 Employee Education and Fairfield Training Funding for the operation and maintenance of the Statewide Training $90,000 2019 Center MaineDOT Fairfield Training Center.

019786.20 Employee Education and Fairfield Training Funding for the operation and maintenance of the Statewide Training $90,000 2020 Center MaineDOT Fairfield Training Center.

202

0123456789 ID/Year Municipality Scope Name Description Funding

019928.18 Inventory and Performance Bridge Inspection and bridge load rating on all Statewide Management Rail $450,000 2018 MaineDOT-owned rail bridges on active rail lines.

019928.19 Inventory and Performance Bridge Inspection and bridge load rating on all Statewide Management Rail $650,000 2019 MaineDOT-owned rail bridges on active rail lines.

019928.20 Inventory and Performance Bridge Inspection and bridge load rating on all Statewide Management Rail $450,000 2020 MaineDOT-owned rail bridges on active rail lines.

020221.18 Communication and Outreach Work includes equipment, training and management Statewide Creative Services to realize efficiencies and enhance communication $460,000 2018 with MaineDOT's customers.

020221.19 Communication and Outreach Work includes equipment, training and management Statewide Creative Services to realize efficiencies and enhance communication $470,000 2019 with MaineDOT's customers.

020221.20 Communication and Outreach Work includes equipment, training and management Statewide Creative Services to realize efficiencies and enhance communication $470,000 2020 with MaineDOT's customers.

Includes National Cooperative Highway Research 020223.18 Program (NCHRP), Transportation Research Board Policy Planning and Research Pooled Fund Statewide (TRB), New England Consortium, Clean Roads $304,000 2018 Projects Initiative and American Association of State Highway Transportation Officials (AASHTO).

Includes National Cooperative Highway Research 020223.19 Program (NCHRP), Transportation Research Board Policy Planning and Research Pooled Fund Statewide (TRB), New England Consortium, Clean Roads $304,000 2019 Projects Initiative and American Association of State Highway Transportation Officials (AASHTO).

National Cooperative Highway Research Program 020223.20 (NCHRP), Transportation Research Board (TRB), Policy Planning and Research Pooled Fund Statewide New England Consortium, Clean Roads Initiative and $304,000 2020 Projects American Association of State Highway Transportation Officials (AASHTO).

The Maine Local Roads Center provides training and 020224.18 Communication and Outreach Local Technical assistance to local road/bridge managers in 502 Statewide Assistance municipalities. The Center is one of 50+ Local $350,000 2018 Program Technical Assistance Programs (LTAP) established by the FHWA.

203

0123456789 ID/Year Municipality Scope Name Description Funding

The Maine Local Roads Center provides training and 020224.19 Communication and Outreach Local Technical assistance to local road/bridge managers in 502 Statewide Assistance municipalities. The Center is one of 50+ Local $350,000 2019 Program Technical Assistance Programs (LTAP) established by the FHWA.

The Maine Local Roads Center provides training and 020224.20 Communication and Outreach Local Technical assistance to local road/bridge managers in 502 Statewide Assistance municipalities. The Center is one of 50+ Local $350,000 2020 Program Technical Assistance Programs (LTAP) established by the FHWA.

020237.20 MaineDOT Multimodal System Various Improvements at MaineDOT Visitor Information Statewide Operations $105,000 2020 Locations Centers.

020523.18 Provides legal advice and representation, contracts Administration for specialized legal consultants, prepares title Statewide Legal Services $1,130,000 2018 abstracts and provides other real estate support to MaineDOT and other state agencies.

020523.19 Provides legal advice and representation, contracts Administration for specialized legal consultants, prepares title Statewide Legal Services $1,130,000 2019 abstracts and provides other real estate support to MaineDOT and other state agencies.

020523.20 Provides legal advice and representation, contracts Administration for specialized legal consultants, prepares title Statewide Legal Services $1,130,000 2020 abstracts and provides other real estate support to MaineDOT and other state agencies.

020524.18 Support to enhance the accuracy of financial Administration Finance and Statewide forecasting and promoting integrity in the $4,100,000 2018 Administration administration of transportation programs and funds.

020524.19 Support to enhance the accuracy of financial Administration Finance and Statewide forecasting and promoting integrity in the $4,300,000 2019 Administration administration of transportation programs and funds.

020524.20 Support to enhance the accuracy of financial Administration Finance and Statewide forecasting and promoting integrity in the $4,300,000 2020 Administration administration of transportation programs and funds.

020541.18 Communication and Outreach Efforts to educate the public about the importance of Statewide Media Outreach $40,000 2018 Work Zone Safety.

204

0123456789 ID/Year Municipality Scope Name Description Funding

020541.19 Communication and Outreach Efforts to educate the public about the importance of Statewide Media Outreach $40,000 2019 Work Zone Safety.

020541.20 Communication and Outreach Efforts to educate the public about the importance of Statewide Media Outreach $40,000 2020 Work Zone Safety.

020580.18 MaineDOT Highway System Statewide Operations River Gauges River Gauge operation fees. $80,000 2018

020580.19 MaineDOT Highway System Statewide Operations River Gauges River Gauge operation fees. $80,000 2019

020580.20 MaineDOT Highway System Statewide Operations River Gauges River Gauge operation fees. $80,000 2020

020767.18 External System Operations Rural Transit FTA Section 5311 - Intercity Capital / Operating - Statewide $2,133,800 2018 Public Transportation Intercity statewide transit agencies RURAL.

020767.19 External System Operations Rural Transit FTA Section 5311 - Intercity Capital / Operating - Statewide $2,133,800 2019 Public Transportation Intercity statewide transit agencies RURAL.

020767.20 External System Operations Rural Transit FTA Section 5311 - Intercity Capital / Operating - Statewide $2,133,800 2020 Public Transportation Intercity statewide transit agencies RURAL.

020787.18 External System Operations Rural Transit FTA Section 5311 for Administrative Assistance - Statewide $2,720,766 2018 Public Transportation Administration statewide transit agencies RURAL.

020787.19 External System Operations Rural Transit FTA Section 5311 for Administrative Assistance - Statewide $2,720,766 2019 Public Transportation Administration statewide transit agencies RURAL

205

0123456789 ID/Year Municipality Scope Name Description Funding

020787.20 External System Operations Rural Transit FTA Section 5311 for Administrative Assistance - Statewide $2,720,766 2020 Public Transportation Administration statewide transit agencies RURAL

020789.18 External System Operations Rural Transit FTA Section 5311 for Operating Assistance - Statewide $5,629,816 2018 Public Transportation Operating statewide transit agencies RURAL.

020789.19 External System Operations Rural Transit FTA Section 5311 for Operating Assistance - Statewide $5,629,816 2019 Public Transportation Operating statewide transit agencies RURAL.

020789.20 External System Operations Rural Transit FTA Section 5311 for Operating Assistance - Statewide $5,629,816 2020 Public Transportation Operating statewide transit agencies RURAL.

020793.18 External System Operations GO Maine Activities. A partnership with the Maine Statewide GO Maine Turnpike Authority to provide statewide commuting $45,000 2018 Public Transportation options.

020793.19 External System Operations GO Maine Activities. A partnership with the Maine Statewide GO Maine Turnpike Authority to provide statewide commuting $45,000 2019 Public Transportation options.

020793.20 External System Operations GO Maine Activities. A partnership with the Maine Statewide GO Maine Turnpike Authority to provide statewide commuting $45,000 2020 Public Transportation options.

020819.18 Work Program Management Materials Materials research in coordination with highway Statewide $300,000 2018 Capital Project Support Research construction projects.

020819.19 Work Program Management Materials Materials research in coordination with highway Statewide $300,000 2019 Capital Project Support Research construction projects.

020819.20 Work Program Management Materials Materials research in coordination with highway Statewide $300,000 2020 Capital Project Support Research construction projects.

206

0123456789 ID/Year Municipality Scope Name Description Funding

020821.18 MaineDOT Highway System Landscaping support associated with high-profile Statewide Operations Landscaping $52,000 2018 projects.

020821.19 MaineDOT Highway System Landscaping support associated with high-profile Statewide Operations Landscaping $52,000 2019 projects.

020821.20 MaineDOT Highway System Landscaping support associated with high-profile Statewide Operations Landscaping $52,000 2020 projects.

Annual contributions to the AASHTO Technical 020822.18 Work Program Management AASHTO Services Program for initiatives such as pavement Statewide Technical and bridge preservation technical transfer, new $101,000 2018 Planning and Research Services product evaluation, material standards development and sustainable transportation technical assistance.

Annual contributions to the AASHTO Technical 020822.19 Work Program Management AASHTO Services Program for initiatives such as pavement Statewide Technical and bridge preservation technical transfer, new $101,000 2019 Planning and Research Services product evaluation, material standards development and sustainable transportation technical assistance.

Annual contributions to the AASHTO Technical 020822.20 Work Program Management AASHTO Services Program for initiatives such as pavement Statewide Technical and bridge preservation technical transfer, new $101,000 2020 Planning and Research Services product evaluation, material standards development and sustainable transportation technical assistance.

020823.00 Work Program Management Bond The repayment of GARVEE bonds for Calendar Statewide $73,378,396 2020 Financial Administration Principal/Interest Years 2018, 2019 and 2020.

The Business and Community Relations Office 020825.18 Business and Communication and Outreach provides a communication interface with community Statewide Community $215,000 2018 leaders, business, law enforcement, chambers of Relations commerce and other stakeholder organizations.

The Business and Community Relations Office 020825.19 Business and Communication and Outreach provides a communication interface with community Statewide Community $220,000 2019 leaders, business, law enforcement, chambers of Relations commerce and other stakeholder organizations.

The Business and Community Relations Office 020825.20 Business and Communication and Outreach provides a communication interface with community Statewide Community $220,000 2020 leaders, business, law enforcement, chambers of Relations commerce and other stake holder organizations.

207

0123456789 ID/Year Municipality Scope Name Description Funding

020826.18 Information Technology Annual cost-share for Commercial Vehicle Statewide Support CVISN Information Systems and Networks (CVISN) hosting $90,000 2018 and system maintenance.

020826.19 Information Technology Annual cost-share for Commercial Vehicle Statewide Support CVISN Information Systems and Networks (CVISN) hosting $90,000 2019 and system maintenance.

020826.20 Information Technology Annual cost-share for Commercial Vehicle Statewide Support CVISN Information Systems and Networks (CVISN) hosting $90,000 2020 and system maintenance.

020829.18 Policy Planning and Research Multimodal Multimodal planning, administration, and support for Statewide $134,000 2018 Planning Division bicycle, pedestrian, and other multimodal projects.

020829.19 Policy Planning and Research Multimodal Multimodal planning, administration, and support for Statewide $134,000 2019 Planning Division bicycle, pedestrian, and other multimodal projects.

020829.20 Policy Planning and Research Multimodal Multimodal planning, administration, and support for Statewide $134,000 2020 Planning Division bicycle, pedestrian, and other multimodal projects.

020830.18 Multimodal Planning, Administration, and Support for Policy Planning and Research Municipal Statewide Aviation, Bicycle/Pedestrian, Ferry Service and $50,000 2018 Coordination Transit.

020830.19 Multimodal Planning, Administration, and Support for Policy Planning and Research Municipal Statewide Aviation, Bicycle/Pedestrian, Ferry Service and $50,000 2019 Coordination Transit.

020830.20 Multimodal Planning, Administration, and Support for Policy Planning and Research Municipal Statewide Aviation, Bicycle/Pedestrian, Ferry Service and $50,000 2020 Coordination Transit.

020831.18 MaineDOT Highway System Data Collection Operating costs for the Department's Data Collection Statewide Operations $200,000 2018 Vehicle Vehicle (ARAN).

208

0123456789 ID/Year Municipality Scope Name Description Funding

020831.19 MaineDOT Highway System Data Collection Operating costs for the Department's Data Collection Statewide Operations $200,000 2019 Vehicle Vehicle (ARAN).

020831.20 MaineDOT Highway System Data Collection Operating costs for the Department's Data Collection Statewide Operations $200,000 2020 Vehicle Vehicle (ARAN).

021800.18 Communication and Outreach Defensive Driving Defensive driving training for municipal and public Statewide $15,000 2018 Training works employees.

021912.18 MaineDOT Highway System Weigh in Motion Statewide Operations Weigh in Motion (WIM) data processing. $25,000 2018 (WIM)

021912.19 MaineDOT Highway System Weigh in Motion Statewide Operations Weigh in Motion (WIM) data processing. $25,000 2019 (WIM)

021912.20 MaineDOT Highway System Weigh in Motion Statewide Operations Weigh in Motion (WIM) data processing. $25,000 2020 (WIM)

022001.18 Administration Project Statewide Capital project development and production. $450,000 2018 Development

022001.19 Administration Project Statewide Capital project development and production. $450,000 2019 Development

022001.20 Administration Project Statewide Capital project development and production. $450,000 2020 Development

022002.18 Work Program Management Construction Construction contracts development, procurement Statewide $625,000 2018 Capital Project Support Contracts and payment.

209

0123456789 ID/Year Municipality Scope Name Description Funding

022002.19 Work Program Management Construction Construction contracts development, procurement Statewide $625,000 2019 Capital Project Support Contracts and payment.

022002.20 Work Program Management Construction Construction contracts development, procurement, Statewide $625,000 2020 Capital Project Support Contracts and payment.

022005.18 Work Program Management Property Statewide Property management and acquisition. $800,000 2018 Capital Project Support Acquisition

022005.19 Work Program Management Property Statewide Property management and acquisition. $800,000 2019 Capital Project Support Acquisition

022005.20 Work Program Management Property Statewide Property management and acquisition. $800,000 2020 Capital Project Support Acquisition

022006.18 Work Program Management Statewide Survey Survey project support and equipment. $1,100,000 2018 Capital Project Support

022006.19 Work Program Management Statewide Survey Survey project support and equipment. $1,100,000 2019 Capital Project Support

022006.20 Work Program Management Statewide Survey Survey project support and equipment. $1,100,000 2020 Capital Project Support

022007.18 Work Program Management Multimodal Statewide Multimodal project engineering and development. $425,000 2018 Capital Project Support Engineering

022007.19 Work Program Management Multimodal Statewide Multimodal project engineering and development. $425,000 2019 Capital Project Support Engineering

210

0123456789 ID/Year Municipality Scope Name Description Funding

022007.20 Work Program Management Multimodal Statewide Multimodal project engineering and development. $425,000 2020 Capital Project Support Engineering

022008.18 Work Program Management Multimodal Multimodal design and construction program Statewide $530,000 2018 Capital Project Support Production management and support.

022008.19 Work Program Management Multimodal Multimodal design and construction program Statewide $530,000 2019 Capital Project Support Production management and support.

022008.20 Work Program Management Multimodal Multimodal design and construction program Statewide $530,000 2020 Capital Project Support Production management and support.

022009.18 Work Program Management Design and Bridge design and construction program Statewide Construction $975,000 2018 Capital Project Support management and project support. Support

022009.19 Work Program Management Design and Bridge design and construction program Statewide Construction $975,000 2019 Capital Project Support management and project support. Support

022009.20 Work Program Management Design and Bridge design and construction program Statewide Construction $975,000 2020 Maintenance and Operations management and project support. Support

022010.18 Work Program Management Design and Highway design and construction program Statewide Construction $2,250,000 2018 Capital Project Support management and project support. Support

022010.19 Work Program Management Design and Highway design and construction program Statewide Construction $2,250,000 2019 Capital Project Support management and project support. Support

022010.20 Work Program Management Design and Highway design and construction program Statewide Construction $2,250,000 2020 Capital Project Support management and project support. Support

211

0123456789 ID/Year Municipality Scope Name Description Funding

022011.18 Work Program Management Materials exploration and testing services and Statewide Materials Testing $450,000 2018 Capital Project Support equipment.

022011.19 Work Program Management Materials exploration and testing services and Statewide Materials Testing $450,000 2019 Capital Project Support equipment.

022011.20 Work Program Management Materials exploration and testing services and Statewide Materials Testing $450,000 2020 Capital Project Support equipment.

022012.18 Work Program Management Quality Materials Quality Assurance Program and project Statewide $1,100,000 2018 Capital Project Support Assurance support.

022012.19 Work Program Management Quality Materials Quality Assurance Program and project Statewide $1,100,000 2019 Capital Project Support Assurance support.

022012.20 Work Program Management Quality Materials Quality Assurance Program and project Statewide $1,100,000 2020 Capital Project Support Assurance support.

022015.18 Work Program Management Engineering Engineering oversight, evaluation and enhancements Statewide $250,000 2018 Administration Oversight to Maine's transportation system.

022015.19 Work Program Management Engineering Engineering oversight, evaluation and enhancements Statewide $250,000 2019 Administration Oversight to Maine's transportation system.

022015.20 Work Program Management Engineering Engineering oversight, evaluation and enhancements Statewide $250,000 2020 Administration Oversight to Maine's transportation system.

022017.18 Direct labor and operating costs for administration, Administration Engineering Statewide user support, and development of the Department's $300,000 2018 Software CADD system.

212

0123456789 ID/Year Municipality Scope Name Description Funding

022017.19 Direct labor and operating costs for administration, Administration Engineering Statewide user support, and development of the Department's $300,000 2019 Software CADD system.

022017.20 Direct Labor and operating costs for administration, Administration Engineering Statewide user support, and development of the Department's $300,000 2020 Software CADD system.

022020.18 Work Program Management Environmental Statewide Environmental coordination (inter- and intra- agency). $950,000 2018 Compliance Activities Coordination

022020.19 Work Program Management Environmental Statewide Environmental coordination (inter- and intra- agency). $950,000 2019 Compliance Activities Coordination

022020.20 Work Program Management Environmental Statewide Environmental coordination (inter- and intra- agency). $950,000 2020 Compliance Activities Coordination

022025.18 Work Program Management Oversight, evaluation and enhancement of Statewide Safety Office transportation safety operations and improvements $220,000 2018 Safety Management statewide.

022025.19 Work Program Management Oversight, evaluation and enhancement of Statewide Safety Office transportation safety operations and improvements $230,000 2019 Safety Management statewide.

022025.20 Work Program Management Oversight, evaluation and enhancement of Statewide Safety Office transportation safety operations and improvements $230,000 2020 Safety Management statewide.

The Office of Freight and Business Services (OFBS) 022026.18 Office of Freight Administration forms policy, programs, and projects that improve Statewide and Business $809,824 2018 Maine's freight transportation network as a cohesive Services system to provide more choices to shippers.

The Office of Freight and Business Services (OFBS) 022026.19 Office of Freight Administration forms policy, programs, and projects that improve Statewide and Business $813,684 2019 Maine's freight transportation network as a cohesive Services system to provide more choices to shippers.

213

0123456789 ID/Year Municipality Scope Name Description Funding

The Office of Freight and Business Services (OFBS) 022026.20 Office of Freight Administration forms policy, programs, and projects that improve Statewide and Business $813,684 2020 Maine's freight transportation network as a cohesive Services system to provide more choices to shippers.

022028.18 Surface Transportation Research: Anticipated Policy Planning and Research Research Statewide funding for future federally mandated research $175,000 2018 Initiative initiatives.

022028.19 Surface Transportation Research: Anticipated Policy Planning and Research Research Statewide funding for future federally mandated research $90,000 2019 Initiative initiatives.

022028.20 Surface Transportation Research: Anticipated Policy Planning and Research Research Statewide funding for future federally mandated research $175,000 2020 Initiative initiatives.

022029.18 Employee Education and Employee Occupational safety, training, education and wellness Statewide Training $380,000 2018 Development to reduce costs and increase staff productivity.

022029.19 Employee Education and Employee Occupational safety, training, education and wellness Statewide Training $390,000 2019 Development to reduce costs and increase staff productivity.

022029.20 Employee Education and Employee Occupational safety, training, education and wellness Statewide Training $441,000 2020 Development to reduce costs and increase staff productivity.

State Cost Allocation Plan (STACAP) enables 022031.18 Administration Maine's Controller's Office and central government to Statewide STACAP recover the cost of providing un-billed central $1,000,000 2018 services to state programs that operate with federal and/or special revenue funds.

State Cost Allocation Plan (STACAP) enables 022031.19 Administration Maine's Controller's Office and central government to Statewide STACAP recover the cost of providing un-billed central $1,000,000 2019 services to state programs that operate with federal and/or special revenue funds.

State Cost Allocation Plan (STACAP) enables 022031.20 Administration Maine's Controller's Office and central government to Statewide STACAP recover the cost of providing un-billed central $1,000,000 2020 services to state programs that operate with federal and/or special revenue funds.

214

0123456789 ID/Year Municipality Scope Name Description Funding

022032.18 Information Technology Information Technology charges incurred in the support, Statewide Support Technology development and maintenance of MaineDOT's $13,800,633 2018 Expenditures information technology systems.

022032.19 Information Technology Information Technology charges incurred in the support, Statewide Support Technology development and maintenance of MaineDOT's $13,710,521 2019 Expenditures information technology systems.

022032.20 Information Technology Information Technology charges incurred in the support, Statewide Support Technology development and maintenance of MaineDOT's $13,710,521 2020 Expenditures information technology systems.

022033.18 Inventory and Performance To provide ongoing process review and appropriate Information Statewide Management management tools to increase Department efficiency, $610,000 2018 Development effectiveness and transparency to the public.

022033.19 Inventory and Performance To provide ongoing process review and appropriate Information Statewide Management management tools to increase Department efficiency, $610,000 2019 Development effectiveness and transparency to the public.

022033.20 Inventory and Performance To provide on going process review and appropriate Information Statewide Management management tools to increase Department efficiency, $610,000 2020 Development effectiveness and transparency to the public.

022034.18 MaineDOT Highway System Operation of Intelligent Transportation Systems (ITS) Statewide Operations ITS Field Devices field devices. These systems will help drivers avoid $265,000 2018 hazards and manage congestion.

022034.19 MaineDOT Highway System Operation of Intelligent Transportation Systems (ITS) Statewide Operations ITS Field Devices field devices. These systems will help drivers avoid $265,000 2019 hazards and manage congestion.

022034.20 MaineDOT Highway System Operation of Intelligent Transportation Systems (ITS) Statewide Operations ITS Field Devices field devices. These systems will help drivers avoid $265,000 2020 hazards and manage congestion.

022035.18 Inventory and Performance Bridge Bridge inspections to include scour evaluation and Statewide Management $4,500,000 2018 Inspections testing of bridges.

215

0123456789 ID/Year Municipality Scope Name Description Funding

022035.19 Inventory and Performance Bridge Bridge inspections to include scour evaluation and Statewide Management $4,500,000 2019 Inspections testing of bridges.

022035.20 Inventory and Performance Bridge Bridge inspections statewide to include scour and Statewide Management $4,500,000 2020 Inspections testing of bridges.

022037.18 MaineDOT Highway System Operations for Advanced Traffic Management ATMS/TIS Statewide Operations System (ATMS) and Traveler Information System $200,000 2018 Operations (TIS).

022037.19 MaineDOT Highway System Operations for Advanced Traffic Management ATMS/TIS Statewide Operations System (ATMS) and Traveler Information System $200,000 2019 Operations (TIS).

022037.20 MaineDOT Highway System Operations for Advanced Traffic Management ATMS/TIS Statewide Operations System (ATMS) and Traveler Information System $200,000 2020 Operations (TIS).

022038.18 Work Program Management Responsible for general civil rights issues and Statewide Civil Rights specific legal requirements related to civil rights $315,000 2018 Compliance Activities under state and federal law.

022038.19 Work Program Management Responsible for general civil rights issues and Statewide Civil Rights specific legal requirements related to civil rights $315,000 2019 Compliance Activities under state and federal law.

022038.20 Work Program Management Responsible for general civil rights issues and Statewide Civil Rights specific legal requirements related to civil rights $315,000 2020 Compliance Activities under state and federal law.

022039.18 Work Program Management Combination of federal grant and formula funds for DBE Support Statewide the Disadvantaged Business Enterprise Program for $100,000 2018 Compliance Activities Services federally funded highway projects and contracts.

022039.19 Work Program Management Combination of federal grant and formula funds for DBE Support Statewide the Disadvantaged Business Enterprise Program for $100,000 2019 Compliance Activities Services federally funded highway projects and contracts.

216

0123456789 ID/Year Municipality Scope Name Description Funding

022039.20 Work Program Management Combination of federal grant and formula funds for DBE Support Statewide the Disadvantaged Business Enterprise Program for $100,000 2020 Compliance Activities Services federally funded highway projects and contracts.

022040.18 Work Program Management Combination of federal grant and formula funds for services to promote and increase diversity in Statewide OJT Support $35,000 2018 Compliance Activities employment in highway construction trades and on federally funded projects.

022040.19 Work Program Management Combination of federal grant and formula funds for services to promote and increase diversity in Statewide OJT Support $35,000 2019 Compliance Activities employment in highway construction trades and on federally funded projects.

022040.20 Work Program Management Combination of federal grant and formula funds for services to promote and increase diversity in Statewide OJT Support $35,000 2020 Compliance Activities employment in highway construction trades and on federally funded projects.

022042.18 Communication and Outreach Diversity Funding to promote education and employment in Statewide $30,000 2018 Education the trades to support economic opportunity.

022042.19 Communication and Outreach Diversity Funding to promote education and employment in Statewide $30,000 2019 Education the trades to support economic opportunity.

022042.20 Communication and Outreach Diversity Funding to promote education and employment in Statewide $30,000 2020 Education the trades to support economic opportunity.

022043.18 Communication and Outreach Annual FHWA National Summer Transportation Statewide NSTI Institute (NSTI) grant funding to support youth $35,000 2018 education in transportation related professions.

022043.19 Communication and Outreach Annual FHWA National Summer Transportation Statewide NSTI Institute (NSTI) grant funding to support youth $35,000 2019 education in transportation related professions.

022043.20 Communication and Outreach Annual FHWA National Summer Transportation Statewide NSTI Institute (NSTI) grant funding to support youth $35,000 2020 education in transportation related professions.

217

0123456789 ID/Year Municipality Scope Name Description Funding

022046.18 External System Operations NNEPRA Northern New England Passenger Rail Authority Statewide $12,293,419 2018 Public Transportation Operating operating assistance, SGR/CMAQ-FTA Transfer.

022046.19 External System Operations NNEPRA Northern New England Passenger Rail Authority Statewide $12,293,419 2019 Public Transportation Operating operating assistance, SGR/CMAQ-FTA Transfer.

022046.20 External System Operations NNEPRA Northern New England Passenger Rail Authority Statewide $12,293,419 2020 Public Transportation Operating operating assistance, SGR/CMAQ-FTA Transfer.

022150.00 Policy Planning and Research Planning- Establishing Planning and Environment linkages by Statewide Environmental incorporating environmental and NEPA-related risk $48,000 2018 Linkages assessments into project screening.

022154.18 Work Program Management Health-Wellness Statewide Healthy Workforce Initiative. $400,000 2018 Planning and Research Efforts

022154.19 Work Program Management Health-Wellness Statewide Healthy Workforce Initiative. $400,000 2019 Planning and Research Efforts

022154.20 Work Program Management Health-Wellness Statewide Healthy Workforce Initiative. $400,000 2020 Planning and Research Efforts

022160.18 Information Technology Statewide Support LIDAR Aquisition Light detection and ranging (LIDAR) data acquisition. $125,000 2018

022160.19 Information Technology Statewide Support LIDAR Aquisition Light detection and ranging (LIDAR) data acquisition. $125,000 2019

022160.20 Information Technology Statewide Support LIDAR Aquisition Light detection and ranging (LIDAR) data acquisition. $125,000 2020

218

0123456789 ID/Year Municipality Scope Name Description Funding

022198.18 Work Program Management Survey Software upgrades and purchase of survey Statewide $300,000 2018 Capital Project Support Equipment equipment.

022198.19 Work Program Management Survey Software upgrades and purchase of survey Statewide $300,000 2019 Capital Project Support Equipment equipment.

022198.20 Work Program Management Survey Software upgrades and purchase of survey Statewide $300,000 2020 Capital Project Support Equipment equipment.

022200.18 Communication and Outreach Pedestrian Statewide Pedestrian safety outreach to targeted populations. $25,000 2018 Safety Outreach

022200.19 Communication and Outreach Pedestrian Statewide Pedestrian safety outreach to targeted populations. $25,000 2019 Safety Outreach

022200.20 Communication and Outreach Pedestrian Statewide Pedestrian safety outreach to targeted populations. $25,000 2020 Safety Outreach

022767.18 External System Operations Statewide Transit Statewide FTA Section 5310 Statewide Administration. $70,000 2018 Public Transportation Administration

022767.19 External System Operations Statewide Transit Statewide FTA Section 5310 Statewide Administration. $70,000 2019 Public Transportation Administration

022767.20 External System Operations Statewide Transit Statewide FTA Section 5310 Statewide Administration. $70,000 2020 Public Transportation Administration

022768.18 External System Operations Rural Transit Statewide FTA Section 5311 Statewide Administration. $487,559 2018 Public Transportation Administration

219

0123456789 ID/Year Municipality Scope Name Description Funding

022768.19 External System Operations Rural Transit Statewide FTA Section 5311 Statewide Administration. $487,559 2019 Public Transportation Administration

022768.20 External System Operations Rural Transit Statewide FTA Section 5311 Statewide Administration. $487,559 2020 Public Transportation Administration

022771.18 MaineDOT Multimodal System Statewide Urban FTA Section 5304 for statewide Urban Transit Statewide Operations $143,350 2018 Transit Planning Planning.

022771.19 MaineDOT Multimodal System Statewide Urban FTA Section 5304 for statewide Urban Transit Statewide Operations $143,350 2019 Transit Planning Planning.

022771.20 MaineDOT Multimodal System Statewide Urban FTA Section 5304 for statewide Urban Transit Statewide Operations $143,350 2020 Transit Planning Planning.

022780.18 External System Operations FTA Section 5311 for Rural Transit Assistance Rural Transit Statewide Program (RTAP) - statewide transit agencies $146,349 2018 Public Transportation RTAP RURAL.

022780.19 External System Operations FTA Section 5311 for Rural Transit Assistance Rural Transit Statewide Program (RTAP) - statewide transit agencies $146,349 2019 Public Transportation RTAP RURAL.

022780.20 External System Operations FTA Section 5311 for Rural Transit Assistance Rural Transit Statewide Program (RTAP) - statewide transit agencies $146,349 2020 Public Transportation RTAP RURAL.

022994.00 Communication and Outreach Transportation Statewide Maine Transportation Safety Coalition. $4,000 2019 Safety Coalition

Feasibility analysis to identify and prioritize specific 023002.00 Policy Planning and Research alternatives to improve the efficiency and safety of Statewide Interstate Study MaineDOT's share of the Interstate with emphasis on $225,000 2018 Interstate 295 between Scarborough and Topsham over the next 20 years.

220

0123456789 ID/Year Municipality Scope Name Description Funding

023008.00 Communication and Outreach Work Zone Statewide Work zone safety- media outreach. $40,000 2018 Safety

023382.00 External System Operations Transit JARC Operating Assistance for Federal Rural Transit Statewide Transit Administration §5311 for statewide non- $283,252 2018 Public Transportation Operating urbanized transit, Fiscal Year 2018 (50/50).

023382.19 External System Operations Transit JARC Operating Assistance for Federal Rural Transit Statewide Transit Administration §5311 for statewide non- $283,252 2019 Public Transportation Operating urbanized transit, Fiscal Year 2019 (50/50).

023382.20 External System Operations Transit JARC Operating Assistance for Federal Rural Transit Statewide Transit Administration §5311 for statewide non- $283,252 2020 Public Transportation Operating urbanized transit, Fiscal Year 2020 (50/50).

023426.00 Work Program Management Bond and Statewide Interest Bond payments to principal and interest. $41,426,418 2020 Financial Administration Payments

The New England Transportation Consortium (NETC) is a research cooperative between New 023430.18 New England Policy Planning and Research England States. The NETC is a valuable regional Statewide Transportation $600,000 2018 partnership for the identification, prosecution and Consortium dissemination of shared transportation research initiatives.

The New England Transportation Consortium (NETC) is a research cooperative between New 023430.19 New England Policy Planning and Research England States. The NETC is a valuable regional Statewide Transportation $600,000 2019 partnership for the identification, prosecution and Consortium dissemination of shared transportation research initiatives.

The New England Transportation Consortium (NETC) is a research cooperative between New 023430.20 New England Policy Planning and Research England States. The NETC is a valuable regional Statewide Transportation $600,000 2020 partnership for the identification, prosecution and Consortium dissemination of shared transportation research initiatives.

023452.18 Administration Insurance for Augusta State Airport and Deblois Statewide Aviation Program $4,000 2018 Airstrip.

023452.19 Administration Insurance for Augusta State Airport and Deblois Statewide Aviation Program $4,000 2019 Airstrip.

221

0123456789 ID/Year Municipality Scope Name Description Funding

023452.20 Administration Insurance for Augusta State Airport and Deblois Statewide Aviation Program $4,000 2020 Airstrip.

Management of MaineDOT Bridge Asset 024000.18 Work Program Management Management System, including inventory, bridge Bridge Statewide data collection, asset priorities, customer service $400,000 2018 Administration Management levels, performance reporting, and prioritization / scoping.

Management of MaineDOT Bridge Asset 024000.19 Work Program Management Management System, including inventory, bridge Bridge Statewide data collection, asset priorities, customer service $400,000 2019 Administration Management levels, performance reporting, and prioritization / scoping.

Management of MaineDOT Bridge Asset 024000.20 Work Program Management Management System, including inventory, bridge Bridge Statewide data collection, asset priorities, customer service $400,000 2020 Administration Management levels, performance reporting, and prioritization / scoping.

BR 22811 System Operations Various Statewide 24-Hour Operations Center. $550,000 2018 Locations

BR 22873 System Operations Various Statewide 24-Hour Operations Center. $575,000 2019 Locations

BR 22924 System Operations Various Statewide 24-Hour Operations Center. $600,000 2020 Locations

BR 22849 Crew Operations Statewide Dept. Operations Augusta Sign Shop operations. $630,000 2018

BR 22909 Crew Operations Statewide Dept. Operations Augusta Sign Shop operations. $650,000 2019

BR 22959 Crew Operations Statewide Dept. Operations Augusta Sign Shop operations. $650,000 2020

222

0123456789 ID/Year Municipality Scope Name Description Funding

BR 22822 Department, Bureau and Office Bureau of Maintenance and Operations Statewide Administration Dept. Operations $1,900,000 2018 Administration, Headquarters.

BR 22903 Department, Bureau and Office Bureau of Maintenance and Operations Statewide Administration Dept. Operations $1,930,000 2019 Administration, Headquarters.

BR 22954 Department, Bureau and Office Bureau of Maintenance and Operations Statewide Administration Dept. Operations $1,930,000 2020 Administration, Headquarters.

BR 22817 Department, Bureau and Office Bureau of Maintenance and Operations Statewide Administration Dept. Operations $920,000 2018 Administration, Region 1.

BR 22898 Department, Bureau and Office Bureau of Maintenance and Operations Statewide Administration Dept. Operations $935,000 2019 Administration, Region 1.

BR 22949 Department, Bureau and Office Bureau of Maintenance and Operations Statewide Administration Dept. Operations $935,000 2020 Administration, Region 1.

BR 22818 Department, Bureau and Office Bureau of Maintenance and Operations Statewide Administration Dept. Operations $1,250,000 2018 Administration, Region 2.

BR 22899 Department, Bureau and Office Bureau of Maintenance and Operations Statewide Administration Dept. Operations $1,250,000 2019 Administration, Region 2.

BR 22950 Engineering and Professional Various Bureau of Maintenance and Operations Statewide Services $1,250,000 2020 Locations Administration, Region 2.

BR 22819 Department, Bureau and Office Bureau of Maintenance and Operations Statewide Administration Dept. Operations $1,165,000 2018 Administration, Region 3.

223

0123456789 ID/Year Municipality Scope Name Description Funding

BR 22900 Department, Bureau and Office Bureau of Maintenance and Operations Statewide Administration Dept. Operations $1,165,000 2019 Administration, Region 3.

BR 22951 Department, Bureau and Office Bureau of Maintenance and Operations Statewide Administration Dept. Operations $1,165,000 2020 Administration, Region 3.

BR 22820 Department, Bureau and Office Bureau of Maintenance and Operations Statewide Administration Dept. Operations $1,350,000 2018 Administration, Region 4.

BR 22901 Department, Bureau and Office Bureau of Maintenance and Operations Statewide Administration Dept. Operations $1,350,000 2019 Administration, Region 4.

BR 22952 Department, Bureau and Office Bureau of Maintenance and Operations Statewide Administration Dept. Operations $1,350,000 2020 Administration, Region 4.

BR 22821 Department, Bureau and Office Bureau of Maintenance and Operations Statewide Administration Dept. Operations $990,000 2018 Administration, Region 5.

BR 22902 Department, Bureau and Office Bureau of Maintenance and Operations Statewide Administration Dept. Operations $1,000,000 2019 Administration, Region 5.

BR 22953 Department, Bureau and Office Bureau of Maintenance and Operations Statewide Administration Dept. Operations $1,000,000 2020 Administration, Region 5.

BR 22813 Communication and Outreach Communication and Outreach - Bureau of Statewide Dept. Operations $155,000 2018 Maintenance and Operations.

BR 22878 Communication and Outreach Communication and Outreach - Bureau of Statewide Dept. Operations $160,000 2019 Maintenance and Operations.

224

0123456789 ID/Year Municipality Scope Name Description Funding

BR 22929 Communication and Outreach Communication and Outreach - Bureau of Statewide Dept. Operations $160,000 2020 Maintenance and Operations.

BR 22824 Contract Administration Contract Administration - Bureau of Maintenance and Statewide Dept. Operations $1,350,000 2018 Operations.

BR 22879 Contract Administration Contract Administration - Bureau of Maintenance and Statewide Dept. Operations $1,450,000 2019 Operations.

BR 22930 Contract Administration Contract Administration - Bureau of Maintenance and Statewide Dept. Operations $1,500,000 2020 Operations.

BR 22823 Asset Location Management Data management, collection, processing and Statewide Dept. Operations $250,000 2018 reporting - Bureau of Maintenance and Operations.

BR 22881 Asset Location Management Data management, collection, processing and Statewide Dept. Operations $250,000 2019 reporting - Bureau of Maintenance and Operations.

BR 22932 Asset Location Management Data management, collection, processing and Statewide Dept. Operations $250,000 2020 reporting - Bureau of Maintenance and Operations.

BR 22814 Employee Education and Employee Education and Training - Bureau of Statewide Training Dept. Operations $4,980,000 2018 Maintenance and Operations.

BR 22883 Employee Education and Employee Education and Training - Bureau of Statewide Training Dept. Operations $5,150,000 2019 Maintenance and Operations.

BR 22934 Employee Education and Employee Education and Training - Bureau of Statewide Training Dept. Operations $5,150,000 2020 Maintenance and Operations.

225

0123456789 ID/Year Municipality Scope Name Description Funding

BR 22842 Engineering and Professional Various Engineering and Professional Services - Bureau of Statewide Services $1,200,000 2018 Locations Maintenance and Operations.

BR 22896 Engineering and Professional Various Engineering and Professional Services - Bureau of Statewide Services $1,225,000 2019 Locations Maintenance and Operations.

BR 22947 Engineering and Professional Various Engineering and Professional Services - Bureau of Statewide Services $1,225,000 2020 Locations Maintenance and Operations.

BR 22816 Environmental Stewardship Various Environmental Stewardship - Bureau of Maintenance Statewide $980,000 2018 Locations and Operations.

BR 22884 Environmental Stewardship Various Environmental Stewardship - Bureau of Maintenance Statewide $1,100,000 2019 Locations and Operations.

BR 22935 Environmental Stewardship Various Environmental Stewardship - Bureau of Maintenance Statewide $1,100,000 2020 Locations and Operations.

BR 22833 Custodial Maintenance Various Statewide Statewide Integrated Vegetation Control. $4,000,000 2018 Locations

BR 22914 Custodial Maintenance Various Statewide Statewide Integrated Vegetation Control. $6,150,000 2019 Locations

BR 22965 Custodial Maintenance Various Statewide Statewide Integrated Vegetation Control. $6,150,000 2020 Locations

BR 22812 System Operations Various Statewide Intelligent Transportation System (ITS) Statewide $176,000 2018 Locations Device Maintenance.

226

0123456789 ID/Year Municipality Scope Name Description Funding

BR 22887 System Operations Various Statewide Intelligent Transportation System (ITS) Statewide $180,000 2019 Locations Device Maintenance.

BR 22938 System Operations Various Statewide Intelligent Transportation System (ITS) Statewide $180,000 2020 Locations Device Maintenance.

BR 22825 Custodial Maintenance Various Statewide Statewide bridge cleaning, washing and sealing. $1,975,000 2018 Locations

BR 22874 Custodial Maintenance Various Statewide Statewide bridge cleaning, washing and sealing. $1,995,000 2019 Locations

BR 22925 Custodial Maintenance Various Statewide Statewide bridge cleaning, washing and sealing. $2,000,000 2020 Locations

BR 22836 Bridge and Structural Various Statewide Maintenance Statewide bridge work and improvements. $3,800,000 2018 Locations

BR 22875 Bridge and Structural Various Statewide Maintenance Statewide bridge work and improvements. $10,950,000 2019 Locations

BR 22926 Bridge and Structural Various Statewide Maintenance Statewide bridge work and improvements. $11,300,000 2020 Locations

BR 22827 Department Building and Lot Statewide Maintenance Dept. Operations Statewide building and lot maintenance. $9,500,000 2018

BR 22876 Department Building and Lot Statewide Maintenance Dept. Operations Statewide building and lot maintenance. $9,975,000 2019

227

0123456789 ID/Year Municipality Scope Name Description Funding

BR 22927 Department Building and Lot Statewide Maintenance Dept. Operations Statewide building and lot maintenance. $9,975,000 2020

BR 22828 Drainage Maintenance Various Statewide Statewide catch basin and culvert cleaning. $1,450,000 2018 Locations

BR 22877 Drainage Maintenance Various Statewide Statewide catch basin and culvert cleaning. $1,500,000 2019 Locations

BR 22928 Drainage Maintenance Various Statewide Statewide catch basin and culvert cleaning. $1,550,000 2020 Locations

BR 22829 Crew Operations Statewide Dept. Operations Statewide crew supervision and management. $5,600,000 2018

BR 22880 Crew Operations Statewide Dept. Operations Statewide crew supervision and management. $6,100,000 2019

BR 22931 Crew Operations Statewide Dept. Operations Statewide crew supervision and management. $6,300,000 2020

BR 22837 Drainage Maintenance Various Statewide Statewide drainage maintenance and improvements. $5,500,000 2018 Locations

BR 22882 Drainage Maintenance Various Statewide Statewide drainage maintenance and improvements. $21,500,000 2019 Locations

BR 22933 Drainage Maintenance Various Statewide Statewide drainage maintenance and improvements. $22,000,000 2020 Locations

228

0123456789 ID/Year Municipality Scope Name Description Funding

BR 22830 Crew Operations Statewide equipment service, repair and associated Statewide Dept. Operations $9,125,000 2018 fleet costs.

BR 22885 Crew Operations Statewide equipment service, repair and associated Statewide Dept. Operations $9,260,000 2019 fleet costs.

BR 22936 Crew Operations Statewide equipment service, repair and associated Statewide Dept. Operations $9,260,000 2020 fleet costs.

BR 22831 Operational and Safety Various Statewide Maintenance Statewide guard rail installation and maintenance. $2,500,000 2018 Locations

BR 22886 Operational and Safety Various Statewide Maintenance Statewide guard rail installation and maintenance. $3,000,000 2019 Locations

BR 22937 Operational and Safety Various Statewide Maintenance Statewide guard rail installation and maintenance. $3,200,000 2020 Locations

BR 22839 Custodial Maintenance Various Statewide Statewide highway patrolling and inspecting. $2,300,000 2018 Locations

BR 22893 Custodial Maintenance Various Statewide Statewide highway patrolling and inspecting. $2,300,000 2019 Locations

BR 22944 Custodial Maintenance Various Statewide Statewide highway patrolling and inspecting. $2,300,000 2020 Locations

BR 22815 Infrastructure Inspection and Statewide Inventory Dept. Operations Statewide infrastructure inspections and inventory. $1,300,000 2018

229

0123456789 ID/Year Municipality Scope Name Description Funding

BR 22888 Infrastructure Inspection and Statewide Inventory Dept. Operations Statewide infrastructure inspections and inventory. $1,320,000 2019

BR 22939 Infrastructure Inspection and Statewide Inventory Dept. Operations Statewide infrastructure inspections and inventory. $1,320,000 2020

BR 22834 Custodial Maintenance Various Statewide Statewide litter and debris removal. $490,000 2018 Locations

BR 22889 Custodial Maintenance Various Statewide Statewide litter and debris removal. $500,000 2019 Locations

BR 22940 Custodial Maintenance Various Statewide Statewide litter and debris removal. $550,000 2020 Locations

BR 22835 Crew Operations Statewide Dept. Operations Statewide material processing and transport. $1,650,000 2018

BR 22890 Crew Operations Statewide Dept. Operations Statewide material processing and transport. $1,675,000 2019

BR 22941 Crew Operations Statewide Dept. Operations Statewide material processing and transport. $1,675,000 2020

BR 22838 System Operations Various Statewide Statewide movable bridge operations. $1,190,000 2018 Locations

BR 22891 System Operations Various Statewide Statewide movable bridge operations. $1,205,000 2019 Locations

230

0123456789 ID/Year Municipality Scope Name Description Funding

BR 22942 System Operations Various Statewide Statewide movable bridge operations. $1,205,000 2020 Locations

BR 22845 Custodial Maintenance Various Statewide Statewide mowing. $955,000 2018 Locations

BR 22892 Custodial Maintenance Various Statewide Statewide mowing. $965,000 2019 Locations

BR 22943 Custodial Maintenance Various Statewide Statewide mowing. $965,000 2020 Locations

BR 22840 Surface and Base Maintenance Various Statewide Statewide pavement maintenance and repair. $4,850,000 2018 Locations

BR 22894 Surface and Base Maintenance Various Statewide Statewide pavement maintenance and repair. $4,950,000 2019 Locations

BR 22945 Surface and Base Maintenance Various Statewide Statewide pavement maintenance and repair. $4,950,000 2020 Locations

BR 22841 System Operations Various Statewide Statewide permitting. $1,925,000 2018 Locations

BR 22895 System Operations Various Statewide Statewide permitting. $1,950,000 2019 Locations

BR 22946 System Operations Various Statewide Statewide permitting. $1,950,000 2020 Locations

231

0123456789 ID/Year Municipality Scope Name Description Funding

BR 22843 Custodial Maintenance Various Statewide Statewide railroad maintenance. $360,000 2018 Locations

BR 22897 Custodial Maintenance Various Statewide Statewide railroad maintenance. $365,000 2019 Locations

BR 22948 Custodial Maintenance Various Statewide Statewide railroad maintenance. $365,000 2020 Locations

BR 22844 Custodial Maintenance Various Statewide Statewide rest area maintenance. $1,180,000 2018 Locations

BR 22905 Custodial Maintenance Various Statewide Statewide rest area maintenance. $1,200,000 2019 Locations

BR 22956 Custodial Maintenance Various Statewide Statewide rest area maintenance. $1,450,000 2020 Locations

BR 22847 Surface and Base Maintenance Various Statewide Statewide roadway shoulder and base maintenance. $1,840,000 2018 Locations

BR 22907 Surface and Base Maintenance Various Statewide Statewide roadway shoulder and base maintenance. $1,860,000 2019 Locations

BR 22961 Surface and Base Maintenance Various Statewide Statewide roadway shoulder and base maintenance. $1,880,000 2020 Locations

BR 22846 Surface and Base Maintenance Various Statewide Statewide shoulder grading. $975,000 2018 Locations

232

0123456789 ID/Year Municipality Scope Name Description Funding

BR 22906 Surface and Base Maintenance Various Statewide Statewide shoulder grading. $990,000 2019 Locations

BR 22957 Surface and Base Maintenance Various Statewide Statewide shoulder grading. $990,000 2020 Locations

BR 22848 Operational and Safety Various Statewide Maintenance Statewide sign maintenance. $1,900,000 2018 Locations

BR 22908 Operational and Safety Various Statewide Maintenance Statewide sign maintenance. $1,950,000 2019 Locations

BR 22958 Operational and Safety Various Statewide Maintenance Statewide sign maintenance. $1,950,000 2020 Locations

BR 22850 Winter Maintenance Various Statewide Statewide snow and ice control. $36,000,000 2018 Locations

BR 22910 Winter Maintenance Various Statewide Statewide snow and ice control. $36,000,000 2019 Locations

BR 22960 Winter Maintenance Various Statewide Statewide snow and ice control. $36,000,000 2020 Locations

BR 22851 Custodial Maintenance Various Statewide Statewide sweeping. $1,550,000 2018 Locations

BR 22911 Custodial Maintenance Various Statewide Statewide sweeping. $1,575,000 2019 Locations

233

0123456789 ID/Year Municipality Scope Name Description Funding

BR 22962 Custodial Maintenance Various Statewide Statewide sweeping. $1,575,000 2020 Locations

BR 22852 System Operations Various Statewide Statewide traffic engineering and support. $1,620,000 2018 Locations

BR 22912 System Operations Various Statewide Statewide traffic engineering and support. $1,650,000 2019 Locations

BR 22963 System Operations Various Statewide Statewide traffic engineering and support. $1,650,000 2020 Locations

BR 22853 Operational and Safety Various Statewide traffic signal and highway lighting Statewide Maintenance $1,160,000 2018 Locations maintenance.

BR 22913 Operational and Safety Various Statewide traffic signal and highway lighting Statewide Maintenance $1,175,000 2019 Locations maintenance.

BR 22964 Operational and Safety Various Statewide traffic signal and highway lighting Statewide Maintenance $1,175,000 2020 Locations maintenance.

BR 22832 System Operations Various Statewide transportation system emergency Statewide $925,000 2018 Locations response.

BR 22904 System Operations Various Statewide transportation system emergency Statewide $1,050,000 2019 Locations response.

BR 22955 System Operations Various Statewide transportation system emergency Statewide $1,050,000 2020 Locations response.

234

0123456789 Ë Municipal Index Municipal Index

Municipality County Tab Municipality County Tab Abbot Piscataquis Berwick York Acton York Bethel Oxford Addison Washington Biddeford York Albany Twp Oxford Blaine Aroostook Alfred York Blue Hill Hancock Allagash Aroostook Boothbay Lincoln Alna Lincoln Boothbay Harbor Lincoln Alton Penobscot Bowdoin Sagadahoc Amherst Hancock Bowdoinham Sagadahoc Amity Aroostook Bremen Lincoln Andover Oxford Brewer Penobscot Anson Somerset Bridgton Cumberland Appleton Knox Bristol Lincoln Argyle Penobscot Brooklin Hancock Arrowsic Sagadahoc Brooks Waldo Arundel York Brooksville Hancock Ashland Aroostook Brookton Twp Washington Athens Somerset Brownfield Oxford Attean Township Somerset Brownville Piscataquis Auburn Androscoggin Brunswick Cumberland Augusta Kennebec Buckfield Oxford Aurora Hancock Bucksport Hancock Avon Franklin Burlington Penobscot Baileyville Washington Burnham Waldo Baldwin Cumberland Buxton York Bancroft Aroostook Byron Oxford Bangor Penobscot Calais Washington Bar Harbor Hancock Camden Knox Baring Plt Washington Canaan Somerset Batchelders Grant Oxford Cape Elizabeth Cumberland Bath Sagadahoc Caratunk Somerset Beals Washington Caribou Aroostook Belfast Waldo Carmel Penobscot Belgrade Kennebec Carrabassett Valley Franklin Belmont Waldo Carthage Franklin Benedicta Aroostook Cary Plt Aroostook Benton Kennebec Caswell Aroostook

235

0123456789 Municipality County Tab Municipality County Tab Cathance Twp Washington Dixfield Oxford Chain Of Ponds Twp Franklin Dixmont Penobscot Chapman Aroostook Dover-Foxcroft Piscataquis Charleston Penobscot Dresden Lincoln Charlotte Washington Durham Androscoggin Chebeague Island Cumberland Dyer Brook Aroostook Cherryfield Washington E Plt Aroostook Chester Penobscot Eagle Lake Aroostook Chesterville Franklin East Machias Washington China Kennebec East Millinocket Penobscot Clifton Penobscot Eastbrook Hancock Clinton Kennebec Easton Aroostook Coburn Gore Twp Franklin Eastport Washington Codyville Plt Washington Ebeemee Twp Piscataquis Columbia Washington Eddington Penobscot Columbia Falls Washington Edgecomb Lincoln Connor Twp Aroostook Edmunds Twp Washington Cooper Washington Eliot York Coplin Plt Franklin Ellsworth Hancock Corinna Penobscot Embden Somerset Corinth Penobscot Enfield Penobscot Cornish York Etna Penobscot Cornville Somerset Fairfield Somerset Crawford Washington Falmouth Cumberland Cross Lake Twp Aroostook Farmington Franklin Crystal Aroostook Forest City Twp Washington Cumberland Cumberland Forktown Twp Aroostook Cutler Washington Fort Fairfield Aroostook Dallas Plt Franklin Fort Kent Aroostook Damariscotta Lincoln Franklin Hancock Danforth Washington Freedom Waldo Day Block Twp Washington Freeport Cumberland Dayton York Frenchville Aroostook Dedham Hancock Friendship Knox Deer Isle Hancock Fryeburg Oxford Denmark Oxford Gardiner Kennebec Dennysville Washington Garfield Plt Aroostook Detroit Somerset Garland Penobscot Dexter Penobscot Gilead Oxford

236

0123456789 Municipality County Tab Municipality County Tab Glenwood Plt Aroostook Kennebunk York Gorham Cumberland Kennebunkport York Gouldsboro Hancock Kingfield Franklin Grafton Twp Oxford Kingsbury Plt Piscataquis Grand Isle Aroostook Kittery York Gray Cumberland Knox Waldo Greenbush Penobscot Lagrange Penobscot Greene Androscoggin Lakeville Penobscot Greenville Piscataquis Leeds Androscoggin Guilford Piscataquis Letter D Twp Franklin Hallowell Kennebec Lewiston Androscoggin Hamlin Aroostook Liberty Waldo Hampden Penobscot Lily Bay Twp. Piscataquis Hancock Hancock Limerick York Harpswell Cumberland Limestone Aroostook Harrington Washington Limington York Harrison Cumberland Lincoln Penobscot Hartford Oxford Lincoln Plt Oxford Hartland Somerset Linneus Aroostook Haynesville Aroostook Lisbon Androscoggin Hermon Penobscot Litchfield Kennebec Herseytown Twp Penobscot Littleton Aroostook Hiram Oxford Livermore Androscoggin Hodgdon Aroostook Livermore Falls Androscoggin Holden Penobscot Long A Twp Penobscot Hollis York Long Pond Twp Somerset Hope Knox Lovell Oxford Houlton Aroostook Lowell Penobscot Howland Penobscot Lower Cupsuptic Oxford Hudson Penobscot Lubec Washington Industry Franklin Ludlow Aroostook Island Falls Aroostook Lyman York Islesboro Waldo Machias Washington Jackman Somerset Machiasport Washington Jay Franklin Macwohoc Plt Aroostook Jefferson Lincoln Madawaska Aroostook Johnson Mt Twp Somerset Madison Somerset Jonesboro Washington Madrid Franklin Jonesport Washington Magalloway Plt Oxford

237

0123456789 Municipality County Tab Municipality County Tab Manchester Kennebec Newport Penobscot Mapleton Aroostook Nobleboro Lincoln Mariaville Hancock Norridgewock Somerset Marion Twp Washington North Haven Knox Mars Hill Aroostook North Yarmouth Cumberland North Yarmouth Marshfield Washington Aroostook Masardis Aroostook Academy Northfield Washington Maxfield Penobscot Northport Waldo Mayfield Twp Somerset Norway Oxford Mechanic Falls Androscoggin Oakfield Aroostook Meddybemps Washington Oakland Kennebec Medway Penobscot Ogunquit York Mercer Somerset Old Orchard Beach York Mexico Oxford Old Town Penobscot Milbridge Washington Orient Aroostook Milford Penobscot Orland Hancock Millinocket Penobscot Orneville Twp Piscataquis Milo Piscataquis Orono Penobscot Molunkus Twp Aroostook Orrington Penobscot Monmouth Kennebec Osborn Hancock Monroe Waldo Otisfield Oxford Monticello Aroostook Owls Head Knox Montville Waldo Oxbow Plt Aroostook Morrill Waldo Oxford Oxford Moscow Somerset Palermo Waldo Mount Chase Penobscot Palmyra Somerset Mt Desert Hancock Paris Oxford Mt Vernon Kennebec Parkman Piscataquis Naples Cumberland Parlin Pond Twp Somerset Nashville Plt Aroostook Parsonsfield York New Gloucester Cumberland Patten Penobscot New Limerick Aroostook Penobscot Hancock New Portland Somerset Perham Aroostook New Sharon Franklin Perry Washington New Sweden Aroostook Peru Oxford New Vineyard Franklin Phillips Franklin Newburgh Penobscot Phippsburg Sagadahoc Newcastle Lincoln Pittsfield Somerset Newfield York

238

0123456789 Municipality County Tab Municipality County Tab Pittston Kennebec Sebago Cumberland Plymouth Penobscot Sebec Piscataquis Poland Androscoggin Sedgwick Hancock Porter Oxford Shapleigh York Portland Cumberland Sherman Aroostook Pownal Cumberland Shirley Piscataquis Presque Isle Aroostook Sidney Kennebec Princeton Washington Silver Ridge Twp Aroostook Prospect Waldo Skowhegan Somerset Randolph Kennebec Smithfield Somerset Rangeley Franklin Smyrna Aroostook Rangeley Plt Franklin Soldiertown Twp Penobscot Raymond Cumberland Solon Somerset Readfield Kennebec Somerville Lincoln Reed Plt Aroostook South Berwick York Region 1 Statewide South Portland Cumberland Region 2 Statewide South Thomaston Knox Region 3 Statewide Southport Lincoln Region 4 Statewide Southwest Harbor Hancock Region 5 Statewide Springfield Penobscot Richmond Sagadahoc St Agatha Aroostook Ripley Somerset St Albans Somerset Rockland Knox St Francis Aroostook Rockport Knox St George Knox Rockwood Strip Somerset St John Plt Aroostook Rome Kennebec Stacyville Penobscot Roque Bluffs Washington Standish Cumberland Roxbury Oxford Starks Somerset Rumford Oxford Statewide Statewide Sabattus Androscoggin Stockholm Aroostook Saco York Stockton Springs Waldo Sandy Bay Twp Somerset Stoneham Oxford Sandy River Plt Franklin Stonington Hancock Sanford York Strong Franklin Sangerville Piscataquis Sullivan Hancock Sapling Twp Somerset Sumner Oxford Scarborough Cumberland Surry Hancock Searsmont Waldo Swans Island Hancock Searsport Waldo Swanville Waldo

239

0123456789 Municipality County Tab Municipality County Tab T01 R01 NBKP Somerset Veazie Penobscot T3 Indian Purchase Penobscot Verona Hancock T4 Indian Purchase Penobscot Vienna Kennebec Talmadge Washington Vinalhaven Knox Taunton And Somerset Waite Washington Raynham Waldo Waldo Temple Franklin Waldoboro Lincoln Temple Somerset Wales Androscoggin The Forks Plt Somerset Wallagrass Plt Aroostook Thomaston Knox Waltham Hancock Thorndike Waldo Warren Knox Topsfield Washington Washburn Aroostook Topsham Sagadahoc Washington Knox Tremont Hancock Waterboro York Trenton Hancock Waterford Oxford Turner Androscoggin Waterville Kennebec Twp 01 R09 Wels Piscataquis Weld Franklin Twp 02 R09 Wels Piscataquis Wellington Piscataquis Twp 05 R09 Piscataquis Wells York Twp 22 Md Hancock Wesley Washington Twp 28 Md Hancock West Bath Sagadahoc Twp01 R06 Wels Penobscot West Forks Plt Somerset Twp02 R08 Nwp Penobscot West Gardiner Kennebec Twp06 R08 Wels Penobscot West Paris Oxford Twp07 R05 Wels Aroostook Westbrook Cumberland Twp08 R05 Wels Aroostook Westfield Aroostook Twp14 R06 Wels Aroostook Westport Island Lincoln Twp15 R06 Wels Aroostook Whitefield Lincoln Twp17 R05 Wels Aroostook Whiting Washington Twp24 MD Washington Whitneyville Washington Twp26 ED Washington Willimantic Piscataquis Twp30 MD Washington Wilton Franklin TwpR07 Wels Penobscot Windham Cumberland Union Knox Windsor Kennebec Unity Waldo Winn Penobscot Upton Oxford Winslow Kennebec Van Buren Aroostook Winter Harbor Hancock Vanceboro Washington Winterport Waldo Vassalboro Kennebec Winterville Plt Aroostook

240

0123456789 Municipality County Tab Winthrop Kennebec Wiscasset Lincoln Woodland Aroostook Woodstock Oxford Woolwich Sagadahoc Yarmouth Cumberland York York

241

0123456789 Ë Terms & Definitions Work Plan WORK PLAN TERMS AND DEFINITIONS

ACIP: Airport Capital Improvement Plan.

ADA or Americans with Disabilities Act: The Americans with Disabilities Act prohibits discrimination and ensures equal opportunity for persons with disabilities in employment, government services, public accommodations, commercial facilities and transportation.

Administration: The ongoing functions that support MaineDOT programs and projects, including department-wide financial and administrative services, financial administration for federal programs, human resources, legal services, operation of the Executive Office, geographic information systems, performance measurement and accountability, the Freight and Business Services Office, the Business and Community Relations Office and engineering oversight.

Airport Master Plan: An Airport Master Plan is a comprehensive study of an airport that describes short-, medium- and long- term development plans to meet future aviation demand.

Apron: The area of an airport intended to accommodate the loading and unloading of passengers and cargo, and the refueling, servicing and parking of aircraft.

Asset Location Management: Managing transportation asset data, coordinating data between systems, analyzing data and work-reporting, and producing reports, maps and data files.

Asset Name: Names the publicly owned or publicly used facility or program on which work is to occur.

Aviation: Includes crack-sealing to preserve airport runway pavement.

AVL or Automatic Vehicle Location: Automatic Vehicle Location is a means of determining the location of a vehicle and transmitting that information to a receiver, allowing transit agencies to determine location of buses, wait times and other information.

BIG or Boating Infrastructure Grant: BIG is a program of the U.S. Fish and Wildlife Service that provides funding for recreational boating infrastructure.

BPI or Business Partnership Initiative: The BPI program provides state funding to match private and municipal investment in highway improvements intended to facilitate economic development.

BR: Bureau Request for Maintenance and Operations.

Items in Italics indicate Statewide Operations or Statewide Capital Programs

242

0123456789 Bridge: A span length of at least 20 feet, as defined by FHWA.

Bridge and Structural Maintenance: Work performed to prevent or repair routine problems, and to extend the useful life of bridges until capital funding becomes available.

Bridge Deck: The portion of the bridge that provides direct support for vehicular and non- motorized traffic.

Bridge Preservation: Bridge strengthening and other bridge improvements on state-owned bridges.

Bridge Scour Countermeasures: Techniques used to mitigate the effects of sediment scour and other hydraulic stress on bridge structures.

Bridge Substructure: The parts of a bridge that are below the bottom of the girders. Pilings, shafts, spread footings and columns may be part of the substructure.

Bridge Superstructure: The parts of a bridge that are above the bottom of the girders. Girders, bridge deck and bridge railing are parts of the superstructure.

Building and Lot Maintenance: This work involves maintenance of over 600 buildings and more than 100 building lots, as well as maintenance of ancillary lot structures.

CADD: Computer Aided Design and Drafting.

Catch Basin: A reservoir for collecting surface drainage or runoff.

CBITD: Casco Bay Island Transit District. The ferry system that serves Portland and nearby islands in Casco Bay.

CE or Construction Engineering: The supervision and inspection of construction activities.

Chip Sealing: Chip sealing consists of a layer of asphalt binder that is overlaid by a layer of embedded aggregate that furnishes, among other things, protection to the asphalt layer from tire damage and macrotexture that creates a skid-resistant surface.

CIPR or Cold in Place Recycling: The process of removing a portion of roadway pavement surface, processing it to a uniform particle size, and mixing with emulsion and Portland cement in a continuous portable operation to create a recycled pavement layer.

CMAQ or Congestion Mitigation for Air Quality: A Federal Highway Administration Program that funds transportation improvements designed to improve air quality and mitigate congestion.

Items in Italics indicate Statewide Operations or Statewide Capital Programs

243

0123456789 CMQ or CMQR: The Central Maine and Quebec Railway.

Cold Storage Building: A building used to store salt and sand materials for use in maintaining roadways throughout the winter.

Communications and Outreach: This program includes the Local Transportation Assistance Program, work zone-safety and bicycle-pedestrian safety education, and audio-visual and other creative services.

CON: Construction phase of project work.

Contract Administration: Costs related to developing and administering contracts.

CPR or Cyclical Pavement Resurfacing: The application of a 3/4” overlay used to preserve lower priority roads that are considered “built”.

Crack Sealing: Roadway or runway surface crack sealing treatments performed to prevent surface damage from freeze thaw cycles.

Crew Operations: Crew management and planning, and overall work preparation activities. Equipment transport and certain repairs also fall into this category.

CSL or Customer Service Level: A measure of how a road compares to other roads of the same priority across the state, based on safety, condition and service.

Culvert: Any pipe or other structure under a roadway that has a diameter of less than 5 feet, or multiple pipes or other structures with a combined opening of less than 20 square feet in area.

Custodial Maintenance: Activities aimed at keeping the assets clean and functioning, such as patrolling and inspecting highways, sweeping, cleaning bridges, and vegetation management.

Debt Service: Debt service is the cash required over a given time period for the repayment of interest and principal on a debt instrument.

Dolphin: Man-made marine structure that extends above the water level and is not connected to shore.

Drainage Maintenance: Removing water from the highway structure, which increases roadway longevity—ditching, catch basin and culvert cleaning, and installation or replacement of drainage structure.

DSRX: Downeast Scenic Railroad.

Easement: A right to use the real property of another without possessing it. Items in Italics indicate Statewide Operations or Statewide Capital Programs

244

0123456789 EMR: Eastern Maine Railway.

Enhanced Project Scoping: A planning process intended to manage future risk by detailing the basic need, possible impacts, roadway design matters, potential cost and stakeholder issues of proposed projects.

Environmental Stewardship: The collection, documenting, permitting and administration of environmental issues associated with maintenance activities or projects.

FAA or Federal Aviation Administration: The national aviation authority of the United States with powers to regulate all aspects of civil aviation, including inspecting and rating civilian aircraft and pilots, enforcing the rules of air safety, and installing and maintaining air-navigation and traffic-control facilities..

Feasibility Study: An analysis and evaluation of a proposed action that is based on extensive investigation and research to determine order-of-magnitude costs and benefits for the proposed action.

Federal Functional Classification: The process by which both rural and urban streets and highways are grouped into classes.

FFY or Federal Fiscal Year: Federal Fiscal Year, which begins October 1st.

Finger Floats: Floating parallel docks that are used as a boat slip.

Fog Seal: A method of adding asphalt to an existing pavement surface to improve sealing or waterproofing, prevent further stone loss by holding aggregate in place, or simply improve the surface appearance.

FTA or Federal Transit Administration: The FTA provides financial and technical assistance to local public transit systems, including buses, subways, light rail, commuter rail, trolleys and ferries. FTA also oversees safety measures and helps develop next-generation technology research.

FTA 5303: Funding provided by FTA for Metropolitan Transportation Planning.

FTA 5304: Funding provided by FTA for Statewide and Non-metropolitan Transportation Planning.

FTA 5307: Funding provided by FTA for transit investments, operating assistance and transportation planning in urbanized areas.

Items in Italics indicate Statewide Operations or Statewide Capital Programs

245

0123456789 FTA 5310: Funding provided by FTA to improve transportation for seniors and individuals with disabilities.

FTA 5311: Funding provided by FTA to support public transportation in rural areas.

FTA 5337: Funding provided by FTA to finance capital projects to maintain public transportation systems in a state of good repair.

FTA 5339: Funding provided by FTA to replace, rehabilitate and purchase buses and related equipment and to construct bus-related facilities.

Full-Depth Reclamation with Foamed Asphalt: The foamed asphalt stabilization process involves full-depth reclamation of the existing hot mix asphalt and approximately 2 inches of the underlying sub-base gravel, shaping this material to the desired grade and cross-slope, and compacting the material to specifications.

GARVEE: A Grant Anticipation Revenue Vehicle is any bond or other form of debt repayable, either exclusively or primarily, with future Federal-aid highway funds under Section 122 of Title 23 of the United States Code.

General Obligation Bonds: General obligation (G.O.) bonds are debt instruments issued to raise funds for public works. G.O. bonds are backed by the full faith and credit of the issuing entity.

Grader Work: Reshaping the shoulder of the highway to facilitate runoff to ditches.

Guardrail Crash Cushion: Energy-absorbing cushioning device that offers protection from collisions with fixed guardrail installations.

HCP (Highway Corridor Priority): A classification system based on common-sense factors including the economic importance of the road. All 23,500 miles of Maine public highway are divided into six priority levels:

Priority 1 Roads: These roads include the Maine Turnpike, the Interstate System and key principal arterials like Route 1 in Aroostook County, the Airline (Route 9), Route 2 west of Newport, and Route 302.

Priority 2 Roads: Priority 2 roads are non-Interstate, high-value arterials.

Priority 3 Roads: These roads generally are the remaining arterials and most significant major collector highways.

Priority 4 Roads: These roads generally are the remainder of the major collector highways. Items in Italics indicate Statewide Operations or Statewide Capital Programs

246

0123456789 Priority 5 Roads: These roads are approximately 2,400 miles of minor collector highways.

Priority 6 Roads: These roads are local roads and streets, and are the year-round responsibility of our municipal partners.

Heavy Pavement Treatment: A paving treatment applied to roadways in fair to good condition that have deteriorated too far for light treatments to be effective, but are still able to be preserved with a more substantial treatment.

Highway Preservation Paving: A program to preserve the investments in existing highways with activities such as repaving, crack sealing, drainage repair, etc., in each region and the Interstate.

Highway Preservation Paving 1 1/4" overlay: Projects scoped for this treatment will receive a 1 ¼ inch Hot Mix Asphalt surface covering the travel way and any adjacent paved shoulders.

Highway Preservation Paving 3/4" overlay: Projects scoped for this treatment will receive a travel way leveling course followed by a ¾ inch Hot Mix Asphalt surface course covering the mainline travel way and shoulders.

Highway Reconstruction: The rebuilding of an existing highway to modern design standards to ensure adequate levels of service for travelers.

Highway Rehabilitation: Structural enhancements that extend the service life of an existing pavement and/or improve its load-carrying capacity.

Highway Safety and Spot Improvements: An activity grouping that includes striping, guardrail, rumble strips, crack-sealing, signage, measures to reduce vehicle/large animal collisions, improvements to visitor information centers, and installation of pedestrian crossing signals.

Highway System Operations: A grouping of project-level expenses across multiple types of projects and operational activities including fees for river gauges, landscaping, operating costs for the ARAN data collection vehicle, operation of intelligent transportation system field devices and advanced transportation management system operations.

HMA or Hot Mix Asphalt: Hot mix asphalt is a combination of approximately 95% stone, sand, or gravel bound together by asphalt cement- a product of crude oil. Asphalt cement is heated aggregate, combined, and mixed with the aggregate at an HMA facility.

HTF or Highway Trust Fund: An account established by law to hold federal highway user taxes that are dedicated for highway and transit-related purposes. The HTF has two accounts: the Highway Account and the Mass Transit Account.

Items in Italics indicate Statewide Operations or Statewide Capital Programs

247

0123456789 IMT: The International Marine Terminal, located on the Portland waterfront

Information Technology Support: A cost center for development, operation and maintenance of the department’s technology systems through the state Office of Information Technology.

Infrastructure Inspection and Inventory: Collection, monitoring and review of the department’s assets, which include highways, rail, ferries, bridges and other transportation assets.

Intermodal Facility: A transportation facility designed to facilitate the transition in mode for passenger or freight movement.

Interpretive Signs: Signs used to inform and make visitors aware of notable features of an area.

Inventory and Performance Management: A grouping of work that includes vehicle size/weight classification, traffic counts, highway classification, traffic studies, bridge inspections, the Safety Office, and operation of the Results and Information Office (RIO).

Large Culvert: (Formerly referred to as a “strut”.) A large culvert is a pipe or other structure that has a diameter of between 5 and 10 feet, or multiple pipes or structures with a combined opening between 19 and 80 square feet in area.

LCP or Light Capital Paving: Light Capital Paving is typically the application of a 5/8 of an inch nominal overlay, used as a holding action on unbuilt roads, in an effort to improve safety and durability and to extend the life of lower-priority roadways.

LED or Light-Emitting Diode: Semiconductor light sources that are highly efficient, used in highway lighting and signage installation.

Light Pavement Treatment: Pavement intended to provide a new wearing surface for traffic and to protect the underlying pavement on the roadway.

LRAP or Local Road Assistance: A MaineDOT program that works with municipal and tribal jurisdictions to provide training, technical assistance and information regarding the construction, maintenance and management of local roads and bridges in Maine.

MCRR: Maine Central Railroad.

Microsurfacing: A mixture of asphalt emulsion, graded aggregates (1/4 of an inch to 3/8 of an inch), mineral filler, water and other additives. The mixture is made and placed on a continuous basis using a travel paver (Slurry Surfacing Machine).

Items in Italics indicate Statewide Operations or Statewide Capital Programs

248

0123456789 Mill and Fill: A pavement management treatment that extends the life of existing roadways by removing a portion of the roadway surface then replacing it with a suitable depth of new hot mix asphalt.

Mitigation: Actions that avoid, minimize, or compensate for potential adverse impacts.

MNR: Maine Northern Railway.

MPI or Municipal Partnership Initiative: A MaineDOT program to develop, fund and build projects of municipal interest on the state infrastructure system with MaineDOT as a funding partner.

MPO or Metropolitan Planning Organization: A federally chartered planning entity responsible for transportation planning and approval of federal transportation funding in federally defined metropolitan areas. Maine has four: Androscoggin Transportation Resource Center (ATRC), Bangor Area Comprehensive Transportation System (BACTS), Kittery Area Comprehensive Transportation System (KACTS) and Portland Area Comprehensive Transportation System (PACTS).

MTA or Maine Turnpike Authority: The Maine Turnpike Authority is a public entity that was established for the purpose of constructing, maintaining, reconstructing and operating a toll highway from Kittery to Augusta.

Multimodal: A term that describes transportation of goods or passengers performed by multiple modes of transport. This can include rail, bus, ferry, bicycling, walking and aviation.

Multimodal Capital: Capital outlays for non-highway transportation system.

Multimodal Operations: Operating outlays for non-highway transportation investments.

Multimodal System Operations: An activity grouping that includes operating support for aviation facilities, bicycle/pedestrian facilities, Visitor Information Centers, buses, and operation of the Maine State Ferry Service.

Multi-use Path: A path or sidewalk designed for use by cyclists and pedestrians, and sometimes by motorized vehicles.

NHPP or National Highway Performance Program: A Federal-aid Highway program that funds capital improvement projects located on the National Highway System.

NHS or National Highway System: A federally defined highway system, consisting primarily of existing Interstate routes and some federally designated principal arterial highways.

Items in Italics indicate Statewide Operations or Statewide Capital Programs

249

0123456789 NPDES II MS4: As authorized by the Clean Water Act, the National Pollutant Discharge Elimination System (NPDES) permit program controls water pollution by regulating point sources that discharge pollutants into waters of the United States.

Operational and Safety Maintenance: A work grouping that includes traffic control and roadway delineation and protection, including signage, traffic signal maintenance, lighting, striping, and guardrail installation and maintenance.

PACTS Municipal Partnership Initiative: A program that funds state/ local financial partnerships with municipalities to make highway improvements of local interest in the Portland metropolitan area.

Park and Ride Lots: Designated parking areas for drivers who ride in another vehicle for a portion of their trip.

PE or Preliminary Engineering: Engineering work done prior to advertising a project.

Pedestrian Refuge: A small section of pavement or sidewalk completely surrounded by asphalt or other road materials, where pedestrians can stop before finishing crossing the road.

PMRAP or Plant Mix Recycled Asphalt Pavement: A cold pavement mix consisting of reclaimed asphalt materials used as a base to add structure and correct deficient cross-slopes.

Policy, Planning and Research: An activity group that includes management of MaineDOT planning activities and studies; public outreach; project scoping and analysis; Work Plan development; Metropolitan and non-metropolitan planning; and research programs and projects.

PPP or Public-Private Partnership: A Public-Private Partnership is a mutually beneficial collaboration between a public agency and a private-sector entity.

Preservation Paving: Paving treatment performed on a highway to facilitate preservation of the investment.

Public Transportation Capital: Capital funding for buses and bus facilities under Federal Transit Administration (FTA) intercity, urban, small urban, and rural programs that serve the general public, and elderly and disabled persons. Some FTA funding may be used for either capital or operating expenses.

Rail: Operational improvements to state-owned rail lines, rail-crossing improvements and the Industrial Rail Access Program, (IRAP) which partners with private-sector entities to fund rail improvements that support economic development.

Items in Italics indicate Statewide Operations or Statewide Capital Programs

250

0123456789 Recreational Trails Program: A Federal Highway Administration (FHWA) funding set-aside that MaineDOT transfers to the Maine Department of Agriculture, Conservation and Forestry for improvements to multi-use trails.

Region: A MaineDOT maintenance region. MaineDOT's field operations and facilities are grouped as five large geographic areas of the state (Northern, Southern, Eastern, Western and Mid-Coast).

Roundabout: A type of circular intersection or junction in which road traffic is slowed and flows almost continuously in one direction around a central island with several exits onto the various intersecting roads.

ROW or Right of Way: A right of way is a type of ownership or easement granted over the land for transportation purposes. This can be for a highway, public footpath, rail transport, canal, etc. Also, the property acquisition phase of a project.

RTAP or Rural Transit Assistance Program: A Federal Transit Administration program that provides a source of funding to assist in the design and implementation of training and technical assistance projects and other support services tailored to meet the needs of transit operators in non-urbanized areas.

Safety and Spot Improvements: Roadway treatments that address single issues or a series of issues along a roadway.

Scope: The type and extent of the planned treatment, activity, or operation that will take place.

SHIP or Small Harbors Improvement Program: A state program that promotes economic development, public access and improved commercial fishing opportunities, and works to preserve and create infrastructure at facilities in tidewater and coastal municipalities.

SLA, SLR: Saint Lawrence and Atlantic Railroad.

State Highway Fund: The State Highway Fund is an account that receives its revenue mainly through fuel taxes and is used to fund projects that are related to the State's highway system.

STP or Surface Transportation Program: A Federal-aid Highway program that provides flexible funding that can be used by states and localities for projects on any Federal-aid highway including the National Highway System and bridge projects on any public road.

Surface and Base Maintenance: Localized pavement repairs, shimming, and paving of certain corridors. This activity also includes the preparation of base gravels or shoulder work.

Items in Italics indicate Statewide Operations or Statewide Capital Programs

251

0123456789 TIGER: The Transportation Investment Generation Economic Recovery discretionary grant program that provides funding for investment in road, rail, transit and port projects that promises to achieve national objectives.

Traffic Calming: Changes in street alignment, installation of barriers and other physical measures that are intended to reduce traffic speed and/or cut-through volumes, in the interest of street safety, livability and other public purposes.

Transfer Bridge: A structure that facilitates car movement from a dock to a ferry.

Urbanized Area: A continuous urban area with a population of 50,000 or more as determined by the U.S. Bureau of the Census.

Ultra-Thin Bonded Wearing Course: The placement of a thin (3/4 of an inch) HMA surface course over a polymer modified tack coat membrane placed by a spray paver.

Wearing Surface: The surface portion of a roadway or bridge deck which is in the direct contact with the vehicles.

Wetland Mitigation: Actions that avoid, minimize, or compensate for potential adverse impacts to wetlands.

Wing Walls: The extension of an abutment to the side slope material of an approach, causeway or embankment.

Winter Maintenance: Activities associated with snow and ice control, and monitoring the highways for hazardous winter conditions.

Work Program Management: A grouping of work activities that support the development of projects, including overall project management, software, property acquisition and compliance oversight.

WR or Work Request: A Work Request for the Bureau of Maintenance and Operations.

Items in Italics indicate Statewide Operations or Statewide Capital Programs

252

0123456789