OFFICIAL
GPO Box 2343 Adelaide SA 5001
DPC21/0301 DX 56201 B1037927 Tel 08 8226 3500 Fax 08 8226 3535 www.dpc.sa.gov.au
Hon Kyam Maher MLC Parliament House North Terrace ADELAIDE SA 5000
Sent by email: [email protected]
Dear Mr Maher
Freedom of information (FOI) application
I refer to your request received by the Department of the Premier and Cabinet (DPC) seeking access under section 13 of the Freedom of Information Act 1991 (the Act) to:
All documents and data provided from government agencies to the South Australian Productivity Commission that were used in the preparation of Chapter 4 (Procuring Social and Health Services from the Not-For-Profit Sector) of the Inquiry into Government Procurement Stage 1.
Date range - 20/03/2018 to 16/02/2021
The South Australian Productivity Commission is a separate agency under the Act. DPC processes FOI requests on its behalf.
Under the Act, an agency has 30 days to respond to an FOI request. As DPC did not respond to your request within the time frame required, the department is deemed to have refused you access to all documents relevant to your application. However, I have determined to process the request as if the statutory time frame had been met.
The purpose of this letter is to advise you of my determination.
A total of 56 documents were identified as answering the terms of your application and I have determined as follows:
I grant you access in full to 37 documents, copies of which are enclosed, and I grant you access in part to 19 documents, copies of which are enclosed.
OFFICIAL
Page 1 of 5 OFFICIAL
Please refer to the attached schedule that describes each document and sets out my determination and reasons in summary form.
Documents released in full
Documents 4, 7, 8, 10 – 26, 28, 31 – 33, 35, 39, 41, 42, 45, 47 – 49 and 52 - 56
Please note, document 31 has recently been rescinded by the Department of Health and Wellbeing and is no longer an extant document.
Documents released in part
Documents 1 – 3, 5, 6, 9, 27, 29, 30, 34, 36 – 38, 40, 43, 44, 46, 50 and 51
Documents 1, 2, 5 and 6
These documents contain information which, if released, would disclose details concerning a deliberation or decision of Cabinet. I have therefore determined to exempt this information pursuant to clause 1(1)(e).
Documents 6, 27, 29, 34, 36 – 38, 40, 43, 44, 46 and 51
Sections of these documents contain information relating to the personal affairs of a multiple third parties. Under clause 6(1) of Schedule 1 to the Act, information is exempt if releasing it would involve the ‘unreasonable disclosure of information concerning the personal affairs of any person’. I have considered that the application of clause 6(1) requires two elements, one that the information contains the personal affairs of that person; and secondly that disclosure would be unreasonable and contrary to public interest. I have determined that this information falls within the category of ‘personal affairs’ as listed under section 4(1) of the Act, thereby meeting the first elements of this clause. Further, I have considered whether the disclosure of this information would be unreasonable. In doing so, I have considered the relevance of this information to the public and the likelihood as to whether the person in question would consent to disclosure. I have concluded that this information was likely obtained in confidence and through measures which would otherwise make it unavailable to the public. I have considered the factors in favour of public interest and determined that these factors are outweighed by the need to maintain personal confidentiality in this instance. Therefore, I have determined that this information meets the requirements of clause 6(1) and is thereby exempt pursuant to this clause.
Documents 30
This document contains details of funding provided through significant procurements which involve a ‘commercial in confidence’ requirement. Release of this information would provide the other organisations with detailed knowledge of how the Department of Health and Wellbeing (DHW) distributes funds for contracted services and grants. In applying the public interest test, I have considered the object of the Act, which favour release. I acknowledge there is a strong public interest in the public knowing how much DHW spends on contracted services and grants, however I have determined this is outweighed by the need to ensure the government is able to scrutinise each organisations’ cause and apply funding how it sees fit. Release of this
OFFICIAL Page 2 of 5 OFFICIAL information could prejudice future supply of funds and could cause disharmony between the government and these organisations, especially by those organisations who feel they did not receive a fair apportionment. I have therefore determined to exempt this information pursuant to clause 7(1)(c).
Documents 2, 3, 6, 37 and 50
These documents contain opinions, advice or recommendations provided by the various state government agency employees to the Office of the SA Productivity Commission (OSAPC) in relation to the procurement of Health Services from the Not- For-Profit Sector. These employees deserve a safe space to have free and frank discussion about the strengths and weaknesses of their department’s procurement processes without fear of those opinions being publicly attributed to them. Further, the SAPC uses this information to drive improvement and it is not in the public interest for staff to feel that they cannot freely share information with SAPC without fear of it being made public. On the other hand, I recognise that there is significant public interest in scrutinising how the SAPC drives improvement, and whether agencies have robust procurement practices in place. On balance, I have determined in places to redact the initials of the staff making the comments pursuant to clause 9(1)(a)(i) to the Act.
Documents 2, 6 and 9
These documents contain information relating to the Department for Child Protection (DCP), the disclosure of which could reasonably be expected to have a substantial adverse effect on the effective performance by the agency of its functions. Release of this information would increase service provider leverage and substantially impact DCP’s effective performance of its contract management functions. While it is in the public interest for there to be transparency regarding the operations of government agencies in this sense, it is not in the public interest to release information that would impact on an agency’s ability secure best value for the public. On balance, I consider that the release of this information would be contrary to the public interest, and I have therefore determined it to be exempt pursuant to clause 16(1)(a)(iv) of Schedule 1 to the Act.
Exemptions
Clause 1 – Cabinet documents
(1) A document is an exempt document –
…
(e) if it contains matter the disclosure of which would disclose information concerning any deliberation or decision of Cabinet;
Clause 6 – Documents affecting personal affairs
(1) A document is an exempt document if it contains matter the disclosure of which would involve the unreasonable disclosure of information concerning the personal affairs of any person (living or dead).
OFFICIAL Page 3 of 5 OFFICIAL
Clause 7 – Documents affecting business affairs
(1) A document is an exempt document—
…
(c) if it contains matter—
(i) consisting of information (other than trade secrets or information referred to in paragraph (b)) concerning the business, professional, commercial or financial affairs of any agency or any other person; and
(ii) the disclosure of which—
(A) could reasonably be expected to have an adverse effect on those affairs or to prejudice the future supply of such information to the Government or to an agency; and
(B) would, on balance, be contrary to the public interest.
Clause 9 – Internal working documents
(1) A document is an exempt document if it contains matter—
(a) that relates to—
(i) any opinion, advice or recommendation that has been obtained, prepared or recorded; or
(ii) any consultation or deliberation that has taken place, in the course of, or for the purpose of, the decision-making functions of the Government, a Minister or an agency; and
(b) the disclosure of which would, on balance, be contrary to the public interest.
Clause 16 – Documents concerning operations of agencies
(1) A document is an exempt document if it contains matter the disclosure of which -
(a) could reasonably be expected -
…
(iv) to have substantial adverse effect on the effective performance by an agency of the agency’s functions
OFFICIAL Page 4 of 5 OFFICIAL
FOI Disclosure Log
In compliance with Premier and Cabinet Circular PC045 - Disclosure Logs for Non- Personal Information Released through Freedom of Information (PC045), DPC is required to publish a log of all non-personal information released under the Act.
In accordance with this Circular, any non-personal information determined for release as part of this application will be published on the DPC website.
Right to internal review
If you are aggrieved with this determination, you have a right to apply for internal review under subsection 29(1) of the Act. Pursuant to subsection 29(2), your application must:
be in writing be addressed to the principal officer, and be lodged at an office of DPC, or emailed to [email protected] within 30 days after the day on which you receive this letter or within such further time as the principal officer may allow.
If you have any questions in relation to this matter, please contact Denise Cranwell, Freedom of Information Officer, on telephone (08) 8429 7312 or via email at [email protected].
Yours sincerely
Eamonn Maloney Accredited Freedom of Information Officer Office of the Chief Executive Department of the Premier and Cabinet
01 / 06 / 2021
OFFICIAL Page 5 of 5 1
SA Government Not for Profit Funding Rules and Guidelines Update
20 June 2017
1 Introduction - Rationale
There was no single approach to funding Not for Profit organisations across government.
There was inconsistency in terms of: • contract term length • contract terms and conditions • application of indexation to funding terms greater than one year • data collection • reporting obligations
2 Project Commenced 2013 • DCSI working collaboratively with the NFP sector to identify key elements required for mandated funding rules and guidelines • Discussions re relevant government policy frameworks • DPC, DTF, State Procurement Board became involved • Agreement that two government policy frameworks apply
Procurement Grants State Treasurer’s Procurement Instructions Board
3 Consultation – Key Stakeholders
Not for Profit Sector representatives
Key agencies: • DCSI, SA Health, Department for Child procure from NFP sector Protection
• DCSI, SA Health, Department of Child Key agencies : Protection grants to the NFP sector • DEWNR, DPTI (Office of Rec & Sport), DSD (including Arts South Australia)
• SPB – Procurement Policies Key Across Government • DTF – Treasurer's Instructions Policy Areas • DPC - Premier and Cabinet Circular
4 Government Approvals
1(1)(e) Disclose deliberation of Cabinet
Cabinet Submission June 2016
1(1)(e) Disclose deliberation of Cabinet •
• • Cabinet Submission • June 2017
5 Policy Framework
Procurement or Grant?
From July 1 2017 Automatic Indexation Removal of State Standard NFP Sector Funded Procurement DPC 044 Treasurer’s Board Services Agreement – SA Funding Instruction 15 Exemption for Procurements Policy for Grants Community the Not For & TI 11 Welfare Grants Profit Sector Agreement
State Procurement Board Policies
6 Funding Policy for NFP Sector (DPC Circular 044) supports and strengthens provides a consistent collaborative approach to all aspects partnerships between of funding government and the Key over- NFP sector arching document for reduces the procurements sets clear requirements administrative burden for public authorities and grants on NFPs with NFP sector
maintains independence of NFPs
7 DPC 044 - Key Principles Collaboration and Robust planning and DPC Circular based on partnership design • working collaboratively to • proportional to scale and best practice principles achieve shared outcomes risk of funding activity for government and NFP • longer term contracts • working together when (3+3+3 years) as planning funding strategies funding relationships appropriate
Proportionality An outcomes Achieving value with relevant • Simple robust, accountable orientation money processes. • Clearly defined realistic • working together to achieve value • Balancing complexity & risk for outcomes defined. for the community. all parties. • Outcomes reviewed • standardised, efficient processes • Reporting levels proportional to regularly. that do not impose burdensome risks & policy outcomes sought. requirements on NFP sector.
Governance and Probity and transparency Community development accountability • Funding activities meet principles • Clear governance and legislative & policy • Desired impact e seeking to accountability. obligations. achieve within the community. • Processes minimise red tape and • Funding decisions are • Funding activities advanced duplication and ensure consistency impartial, documented, only where desired outcomes across publicp authorities. publicly defensible & lawful. improved.p
8 Key Principles - Summary Collaboration Agencies and the NFP sector need to work together, collaborate and build strong, ongoing relationships for the benefit of the community and end clients. Simplicity and Red Tape Reduction The volume, detail and frequency of reporting requirements need to be proportional to the risks involved and policy outcomes being sought. Funding processes across government need to be standardised, efficient and effective and not impose burdensome requirements on the NFP sector. Outcomes Focus There needs to be a focus on outcomes with outcomes being realistic and clearly defined about what the funding is intended to achieve, both for beneficiaries and with regard to policy objectives. Community development principles need to be considered including consideration of the desired impact or change they are seeking to achieve within the community.
9 Grant or Procurement?
“Making this determination requires the exercise of judgement based on the public authority’s knowledge of the arrangement and may require additional advice from the Crown Solicitor’s Office for particularly complex cases.”
Simplify Day 2017 Definition of ‘Procurement Operations’ needs to be changed
10 Procurement Framework • State Procurement Board policies have been updated for NFP requirements: and to reflect relevant DPC044 principles. • Additional specific requirements when undertaking procurements with the not-for-profit sector have been added (shaded text boxes) • Six updated policies: – Procurement Policy Framework – Contract Management Policy – Acquisition Planning Policy – Supplier Selection Policy – Simple Procurement Policy – Market Approaches and Contracts Guideline
11 Acquisition Planning Policy definition of not-for-profit from the Australian Taxation Office added Identifying Needs: early stakeholder engagement with NFP sector and need to work together Planning the Procurement Strategy: need to consider community development principles contracting options for NFP sector – including moving to fee for service as far as possible instead of up front ‘block funding’ new section which applies to all procurements on ‘Determining the Contract Period’ determining contract period for NFP sector: 3+3+3 year contracts Contract Renewals: need to provide sufficient notice Reasons for Limiting Number of Suppliers: additional reasons added
12 Supplier Selection Policy
Policy updated to: – better reflects the stages of the supplier selection process – provide additional guidance on distribution and receipt of offers and industry briefings – removes duplication and streamline content. Evaluation Plan: – evaluation team membership for NFP procurements to including consideration for evaluation team member from NFP sector – evaluation criteria for NFP procurements
13 Contract Management Policy
Policy updated to – incorporate more of a partnership/relationship building focus – reorganise content to follow a similar format to other policies – remove duplication and streamline content Relationship Management – NFP sector – need to communicate and work collaboratively Contract Renewals: NFP sector – where there is funding certainty, a minimum of six months’ notice must be provided
14 Simple Procurement Policy Procurement Policy Framework
Simple Procurement Procurement Policy Policy Framework
• Updates similar to process • Updated to include policies references to the NFP policy updates • Includes reference to DPC 044
15 NFP Indexation Policy
1(1)(e) Disclose deliberation of Cabinet
16 Grants: Treasurer’s Instruction 15
• Initial update to reflect new grants agreement – June 30 2017 • Post June 30: more substantial update required
17 Payment of Creditors’ Accounts: Treasurer’s Instruction 11
• To be updated to allow up front payment for NFP organisations undertaking procurements
• Currently: TI11 – Payments in advance for goods that have not been received or for services not yet rendered may only be made as follows: • (d) the payment represents a deposit of 10% or less of the total value of goods to be received
18 Contracting Framework
Bespoke Contract • CSO advice to be obtained for high risk contracts or non- standard contracts Standard NFP Funded Services Agreement • low to medium risk standard procurement contracts with NFP sector >$33,000 Standard Grants Agreement • low to medium risk standard grants with all types of organisations including the NFP sector
19 Contracting Methods • Block Funding • Payment for Inputs • Payment for Outputs • Payment for Performance • Payment for Outcomes Require more commercial, sustainable contracting with NFP
20 Implementation
Implementation begins 1 July 2017 End of transition 1 January 2018
Review – late 2017 • Feedback from •NFP sector • public authorities Training • Procurement • Grants • Contract
21 Office of the SA Productivity Commission 2 Meeting notes
Meeting Department for Child Protection (DCP)
Time & Date 3pm – 4pm, 12 December 2018
Location Level 2 Education Building, 31 Flinders St.
Jennifer Browne (JB), Peter Evans (PE), Deborah Odgers (DO), Kristal Attendees Camedow (KC), Matthew Butlin (MB), Gerard MacDonald (GM), Aaron Witthoeft (AW) Item Items Action No. The discussion was structured around a PowerPoint presentation delivered by PE,
“Contract Management Reform – Project Overview”.
9(1)(a)(i) The following key points were discussed by (unless expressly indicated otherwise): At DCP we had issues with a practice of people in the Dept entering into contractual arrangements without the appropriate authority. We found deficiencies in every aspect of our contract management. Our reforms are about not only reforming practices and procedures but how to contract for new models of care. Our contracts were historically generalised in their expression and non-specific so it wasn’t clear what we’d purchased - we’ve struggled to track inputs and outputs + outcomes. We have triggered an independent review of what a provider is delivering to determine if the intervention successful – this will shape what the future contract looks like. One particular review has come back as good, but the contract in that instance will still need to be a lot more specific going forward. Also, we are looking at our own recording and reporting mechanisms to track whole-of-life care data. We have had to do reconciliations on providers reporting in terms of what was being delivered – this has been a source of complaint from the sector as it has not been past practice. This approach is new for DCP – I’ve managed grants in the past (at SA Health) and always had this type of reporting arrangement in place. 16(1)(a)(iv) Adverse effect on agency functions Moving towards a commissioning model, presently trying to nail what outsourced services are for the next year with treasury. Our contract management was previously paper-based or with excel “work around” approaches across the department. Took a while to firm up what contracts we had in the organisation. The benefit of being in this situation is we can take a generational leap with our CMLS reform – looking at docu-sign For Official Use Only – I1 – A1 1 Office of the SA Productivity Commission Meeting notes
– two-way interaction with the NGOs etc. Aiming for best practice. Our system will be tailored to incorporate our unique requirements.
9(1)(a)(i) – our procurement strategy is identified as a strategic input to our contract management reform program – this is in an attempt to smooth out the procurement program over time and the forward estimates from a budget perspective i.e. 85% of contracts are due for renewal at the end of FY – this creates a large burden for both the sector and the department. Contracts have historically been rolled over – we are trying to better plan – moving to review of specified services so we can consider co-design and more accurately determine what the population needs are etc i.e. undertake a deliberate piece of work in support of a better process and better outcomes, and a more commercial approach. Previously we lacked flexibility from a procurement/contract perspective to provide the care required by particular classes of child clients. Focusing now on contracts we got really wrong in the past.
9(1)(a)(i) – where are you up to in terms of progress on this more deliberate and commercial approach? Have been doing our due diligence, separating underperforming staff, recruiting new staff and are now ready to execute reforms – we are going to market soon on commercial care. Doing a commissioning piece for out of home care – kids have become stuck in commercial care – we needed to grow family-based placements – got 1(1)(e) Disclose deliberation of Cabinet – working with NGOs to deliver more family-based placement and we’ll pay for that. Payment terms/paying on time: I need to convince treasury to pay – we underestimated the poor quality of NGO returns – was a long time before we made growth payments because we found errors in their returns. Not always clear if our records or their records is where the issues are – reconciliation on a quarterly basis so there is some lag to time of payment.
9(1)(a)(i) – we’ve had some feedback on this from the sector who have shared a view about it taking up to 5 months to pay – not sure if DCP or other agency. I’ve indicated if an NGO is in deficit that I’m prepared to pay “mid-point” payments. I’ve done this for one organisation recently.
9(1)(a)(i) – we’ve heard about another complicating factor – NGOs that aren’t incorporated under the Corporations Act 2001 (Cth) and are therefore excluded from the automatic late payment interest provisions of government. They feel a thread of exploitation.
For Official Use Only – I1 – A1 2 Office of the SA Productivity Commission Meeting notes
We are trying to move to a more commercial approach – doing that in the disability space. If NGOs are receiving grant payments, there isn’t a late payment fee. NSW has recently done a good actuarial piece on the impact of care including for example identifying the top 4% of clients absorbing very significant resources. Have a look at our Industry Day references re our intent to grow aboriginal controlled entities. Note also new NFP Service Agreements are better for us than old convoluted contracts that contradicted themselves. The new agreements provide for a more facilitative approach and call up other sources, negating the need for extensive variations and burdensome administrative tasks when amendments are required.
9(1)(a)(i) – to date our engagement strategy has been either industry wide or with individual providers. We are now in a position to be able to go to the next level on specific topics on an industry-wide basis.
For Official Use Only – I1 – A1 3 Office of the SA Productivity Commission 3 Meeting notes
Meeting Department for Child Protection (DCP)
Time & Date 3:15pm – 4pm, 18 December 2018
Location Level 1 Education Building, 31 Flinders St.
Cathy Taylor, (CT), Fiona Ward (FW), Matthew Butlin (MB), Tyson Attendees Miller (TM) Item Items Action No.
1 SAPC’s current inquiry - procurement 9(1)(a)(i) – [ToR and Issues Paper provided by hand]. SAPC is undertaking consultation with agencies on the inquiry and this meeting is the first step in the process. SAPC will release a draft report based on evidence and stakeholders’ experiences by mid-March with a final report by May.
1.1 Procurement inquiry – DCP issues 9(1)(a)(i) – The procurement function of DCP, done previously when the child protection function was part of DECD, is now done by Strategic Procurement in DTF. The observations of the CE in her time in South Australia is that there is a very formal procurement environment here with influences predominantly being about supplier burden, risk and return. There is a lack of maturity amongst the NGO-sector here and there are barriers, such as legislative ones constraining the procurement process.
9(1)(a)(i) – Issues raised by SACOSS around the segmentation of government care services, from a procurement perspective, are valid and seem inefficient.
9(1)(a)(i) – There is an intersection of procurement with contestability, a significant amount of social services are delivered by government, not just on behalf of government and DCP has spent considerable time thinking about its service provision and purchase offerings.
9(1)(a)(i) – SA is only 1 of 2 jurisdictions ( the other being WA) to internally manage residential care services. There are currently 220 funded places for children and 700 staff with some of the buildings owned by government (others leased) for this purpose.
9(1)(a)(i) – The procurement capability of DCP is low but are conscious of trying to lift this (including ‘procurement literacy’) and the design of solutions within the department persists as an issue to address. DCP would support recommendations in our draft report building agency For Official Use Only – I1 – A1 1 Office of the SA Productivity Commission Meeting notes
capability and capacity and the support system for agencies, particularly smaller agencies to improve their procurement functions.
2 Further consultation with DE A meeting is 9(1)(a)(i) to occur – Suggested that he and the CE meet again in late January to talk about areas of interest and opportunities for reform. Given the reduced role in procurement of DCP, the most beneficial form of engagement would be for DCP to identify NGO’s (procurement counterparties); these would be very useful stakeholders the Commission to talk to in terms of the findings so far off the inquiry and what improvements can be made to the procurement process. 9(1)(a)(i) – If DCP have thoughts on any future inquiry topics then they are encouraged to advise the Commission.
For Official Use Only – I1 – A1 2 Office of the SA Productivity Commission 4 Meeting notes
Department for Human Services(DHS)
10:30am – 12:00pm, 20 December 2018
Level 4, Ugly Building, 45 Grenfell Street
Caroline Lock (CL), Jody King (JK),Emmanuelle Sloan (ES), Tyson Miller (TM)
Items
1.1: DHS sometimes approach the market before a tender process commences, however this is not done very often and is certainly not part of any formal departmental process. They may speak to a business or an NGO for the purposes of market research or for early engagement in the process but no formal paperwork is required. This has happened recently in DHS with IT, funeral arrangements and pharmaceutical contracts. In addition, there is a requirement in the DPC circular on NGO procurement to undertake co-design in the acquisition planning process with potential suppliers. 1.4 It is a fact of working in an agency with a multitude of demands on those form whom you seek approval (Ministerial and Executive) , however, this aspect of the process is lengthy and generally less timely than other steps in the process. There are conflicting legal views on the use of electronic signatures on contract documents. The roll out of electronic approval systems is a logistical exercise that the department is still trying to come to grips with. 1.5 DHS will generally undertake direct negotiations due to the following factors: corporate requirements , such as for records management, or to meet other requirements government has – particularly in IT or, as is most often, there is little choice in the market you will be approaching. 1.6: Across government contracts are seen as beneficial to the department, they certainly help stream line the process (as contract terms are pre-agreed) and it also reduces the time in the process to undertake procurement. It enables the department to control expenditure. DHS does use secondary suppliers as it had a varied list of mandated products that only a sole supplier could provide. It was the first department to use this arrangement for the across government contract on stationery and in doing so was able to pass on information and lessons learnt from doing so to other departments when they implemented this arrangement. They also use sole supplier arrangements for employee assistance counselling. DHS are thinking of using more panel arrangements so that SMEs can engage in the procurement process but also enabling DHS to meet their needs – this will happen with disability enterprise development contracts, human service centre site cleaning contracts and security guards. DHS is able to do this by leveraging the current department of health contract. The problem with this type of arrangement being used more broadly is that the contracts start to become larger across more than one department which is good from the perspective of gaining efficiencies but this is not always compatible with growing local business. For smaller agencies, as the additional work is in percentage
For Official Use Only – I1 – A1 1 Office of the SA Productivity Commission Meeting notes
terms not that much more than the main department contract, the price for leveraging off a larger agency does not usually provide savings. DHS also had a joint procurement arrangement with DPTI on indigenous employment outcomes. 2.4: Feedback tends to be on an as-required basis, is informal and is usually driven by disgruntled businesses that are not successful in the tender process. Criticisms of the feedback process are generally anecdotal. The DHS Strategic Procurement and Grants Committee (SPGC) takes an active interest in feedback and complaints made to the department. Tender de-briefs are another avenue where feedback comes, however this is usually concerned with trivial details and no substantial ones to do with process fairness or transparency. 3.2: Across government contract data on some contracts is compiled (or was up until the recent changes to strategic procurement removing the data analytics function in DTF) by the analytics group, particularly for use of temporary staff and government travel contracts – this was actual expenditure data. 3.3: DHS make clear in the procurement process that there is a primary (preferred) provider and secondary providers in their panel arrangements. There have not been any instances of businesses securing all the work for similar products; the split in business has been more along the lines of suppliers providing particular goods and services. An example is maintenance panels, which are zoned regionally for particular products. 3.4 Yes, DHS does use examples of these arrangements e.g. housing trust maintenance contracts. A head contractor who subcontracts out for a $100 million contract (40,000 properties). Also the APY lands housing maintenance. Both examples use multi-trade contracts – some regions it works well in, others it doesn’t. Also horticultural maintenance (Independent Review of this contract was paid for by SAHT). Also promotes interesting discussion on the relationship between public authorities and prescribed authorities when procurement is done on an agency’s behalf – application of SPB guidelines and rules. 4.2 Have had some non-compliance issues with not-for-profit (NFP) procurements such as delays in getting the contracts signed through the department/Minister or having services commencing before the contracts are in place. Sometimes the delay is a result of delays in Federal funding. In terms of corrective actions or redress of these instances; DHS procurement provides regular reports to agency executive about upcoming major contracts as well as the SPB process for reporting on future procurement. This helps to guide decision makers about timelines and impacts of contract slippage. DPC Circular 44 also makes agencies more accountable for engaging in contract renewal early – the circular enforces the six-monthly reporting of upcoming contracts. 5.3 The SPGC is very engaged in the procurement processes of the agency, with a focus on contract management and its functions are primarily around approving new procurements. The SPGC meets weekly and its membership comprises 3 executives of the department.
For Official Use Only – I1 – A1 2 Office of the SA Productivity Commission Meeting notes
5.5 Accreditation appears to be a one-size-fits-all approach, when in reality the differing business focus of agencies does not accommodate such an approach. An example of this the analytics of spend and contracting activity for use of category management. This analysis is beneficial for heavy users of category management such as SA Health or DPTI but not for agencies such as DHS. 5.6 The internal audit officer of DHS is the contact for business if they have a complaint and this contact information is made available to every business at the commencement of the tender process. DHS does have a documented internal complaints process and does remove jargon contained in templates (by modifying those issued SPB) to minimise confusion and a potential source of complaint. 6.1 DHS are very mindful of having to be able to demonstrate probity and mollify any perceptions of poor processes, as such there is an element of caution in their approach, particularly for market approaches, perversely selective or direct approaches minimise the probity issues that can arise, in comparison to market approaches. DHS are cautious because of (usually) vexatious complaints and appoint external probity advisors where the perceived probity issues are prevalent, usually for high- value contracts. In a perfect world, the approach would be to engage all businesses at appropriate parts of the tender processes, selecting known suppliers to approach and using a 2-stage process. However, there is a fear around this approach, particularly for decision makers and those who are accountable for decisions. Capability of agencies would need to be increased to attempt or make successful such an approach. 8. Businesses have a valid point on their complaints about allocation of risk – there is a general view that risk is passed on to business from government and government understand that this may result in a risk premium being charged and prices being raised accordingly. There is a tension around the liability cap, there are examples of businesses quoting unrealistic liabilities for small-scale risks. The head-of-liability clause of the contract terms is something that government cannot get out of. In terms of managing risks, there is so much to comply with in terms of DPC Circular’s, TIs, ICAC, AG’s – the natural course for all agencies is to minimise risk to minimise exposure to this level of scrutiny. 9. In DHS’ view, the ECT/IPP doesn’t make a difference in the tender process, mainly because of differences in the respective prices and quality/capabilities of bids and suppliers, when comparing local to interstate/overseas. A lot of the services, as they are provided locally, naturally are provided by local companies. However, in all other cases for procurements of large scale or are specialist in nature, the IPP is of little use because the local companies either do not possess the capability or are too expensive. There is only one example, that DHS can recall, where the ECT/IPP scoring made a difference to the outcome; DHS have also had an example where the IPP had good outcomes. DHS have never had any feedback or analysis from OIA/DIS on all the data that has been submitted or from procurements undertaken. DHS staff don’t see or have a say in the ECT, yet they are required to use the ECT in the procurement process. Where relevant, DHS already have local content criteria that is used for some contracts, particularly for social inclusion, service location and local jobs.
For Official Use Only – I1 – A1 3 Office of the SA Productivity Commission Meeting notes
A representative from OIA used to sit on the SPGC, however it is DHS view that the IPP is not well integrated into SPB policies, SPB have to some extent but it hasn’t gone the other way. IPP not receptive to feedback. 10. Request for quote proposals are impacted by probity concerns (co-design and innovation doesn’t really occur with these processes). In reality, time restrictions and delivery requirements have an impact on planning and innovation. ICT Projects are a good example; these often involve multiple stages and demonstrations. It is costly to a department to employ dedicated resources for this type of role and in any event they are reluctant to change specifications or alter arrangements in the name of innovation. (It is more cost-effective and prudent to contract and independent probity advisor to take up this role as required. Example, debt recovery contract.
For Official Use Only – I1 – A1 4 5
Cranwell, Denise (DPC)
From: Witthoeft, Aaron (OSAPC) Sent: Friday, 1 February 2019 11:04 AM To: Witthoeft, Aaron (OSAPC) Cc: MacDonald, Gerard (OSAPC) Subject: T/A Greg Fenn re DCP human services procurement - 1 Feb 2019 @ 1015
AW called Greg seeking Greg’s views on DCP’s procurement spend on NFPs; Greg indicated as follows:
There isn’t any neat data sets in relation to DCP’s procurement spend but Greg can consider further – consider also Justin Sara and 9(1)(a)(i) Opinion or advice in terms of obtaining access to tender documentation; 1(1)(e) Disclose deliberation of Cabinet DCP are going to market in the next couple of weeks to procure residential care arrangements; 9(1)(a)(i) Opinion or advice That tender is being run by with assistance from Strategic Procurement; To date DCP have not effectively engaged the market, nor have they achieved VFM; Historically DCP has sought bloc services which have not achieved VFM – the market has ben “too cosy”; This tender is expected to put some rigour into the sourcing of these services and test the market nationally; It has also been a challenge to reform the DCP contract management function; This tender is expected to receive bids from NFPs and for profits.
AW thanked Greg for his insights and indicated would speak directly with DHS first before considering anything further from Greg in terms of data and spend for DCP, and will discuss with Gerard whether Commission inclined to comment on DCP specifically.
End call.
Aaron Witthoeft Principal Inquiry Economist | Office of the SA Productivity Commission State Administration Centre, Level 6, 200 Victoria Square ADELAIDE SA 5000 | DX56201 T 08 8226 7107 E [email protected] W www.sapc.sa.gov.au
Information contained in this e-mail message may be confidential and may also be the subject of legal professional privilege or public interest immunity. If you are not the intended recipient, any use, disclosure or copying of this document is unauthorised.
1 6
Cranwell, Denise (DPC)
From: MacDonald, Gerard (OSAPC) Sent: Monday, 4 February 2019 11:43 AM To: Butlin, Matthew (OSAPC); Tembel, Adrian (OSAPC) Cc: Witthoeft, Aaron (OSAPC) Subject: Child Protection Procurement
On Friday afternoon, I had a phone discussion with 9(1)(a)(i) Opinion or advice. 1(1)(e) Disclose deliberation of Cabinet In our meeting with NGO’s I believe this new arrangement, in particular unit pricing, has been a topic that has frustrated some NGOs.
9(1)(a)(i) Opinion or advice indicated 16(1)(a)(iv) Adverse effect on agency functions She also indicated that 9(1)(a)(i) Opinion or advice
For example, one service providers had a contract to deliver 40 foster care places; however, compared to the average price for those services, the total value of the contract suggested that 50 places should be provided. The services providers had only provided 4 places and there was no plan in place to mitigate the issue. This put added pressure on the agency to use commercial care which has much higher costs and much poorer outcomes for the children placed in that type of care.
In an effort to move forward, DCP decided to put incentives in place to grow the number of foster care spaces, which involved developing a unit price for foster care based on interstate benchmarks and only paying for growth in the number of places. They also notified existing contract holders that future contract would be based on the unit price. This frustrated a number of the NGOs that were accustomed to more block funding arrangements that did not require much reporting on actual results.
9(1)(a)(i) Opinion or advice I’ve asked to provide some of the background documents that led to the development of the new arrangement and to meet with us on the subject. She will send some suggested times this week as well as selected papers that explain and support the new arrangements.
Gerard MacDonald Director | Office of the SA Productivity Commission Wakefield House, Level 16, 277 Wakefield Street ADELAIDE SA 5000 | DX56201 6(1) Personal affairs T 08 8226 7069 E [email protected] W www.sapc.sa.gov.au
1 7
Cranwell, Denise (DPC)
From: Witthoeft, Aaron (OSAPC) Sent: Tuesday, 5 February 2019 2:26 PM To: Witthoeft, Aaron (OSAPC) Subject: T/A Mark Carey - Late Payment of Government Debts (Interest) (Automatic Payment of Interest) Amendment Bill - NFPs excluded
Mark advised:
S3(1) of the Late Payment of Government Debts (Interest) Act 2013 i.e. the definition of a “qualifying body” was amended by s5(2) of the Late Payment of Government Debts (Interest) (Automatic Payment of Interest) Amendment Bill 2018, to ensure interest payments were not going to be made to other Crown entities by SA Govt.
The change was from: (a) a corporation incorporated under the Corporations Act 2001 of the Commonwealth; or (b) any other body corporate constituted under the law of the Commonwealth, the State or another State or Territory.
to:
“means a corporation incorporated under the Corporations Act 2001 of the Commonwealth”.
The change was made on the presumption that NFPs are generally incorporated under Corporations Act 2001.
It was an unintended consequence that NFPs were excluded.
Further legislative amendment would be required to capture NFPs, but continue to exclude Crown entities not intended to be eligible for interest payments by SA Govt.
Aaron Witthoeft Principal Inquiry Economist | Office of the SA Productivity Commission State Administration Centre, Level 6, 200 Victoria Square ADELAIDE SA 5000 | DX56201 T 08 8226 7107 E [email protected] W www.sapc.sa.gov.au
Information contained in this e-mail message may be confidential and may also be the subject of legal professional privilege or public interest immunity. If you are not the intended recipient, any use, disclosure or copying of this document is unauthorised.
1 Office of the SA Productivity Commission 8 Discussion Outline
Department of Human Services – NFP Procurement & Grants
12:30pm – 2:00pm, 7 February 2019
DHS Offices, Level 4, 45 Grenfell Street
Caroline Lock (CL), Jody King (JK), Patrick Maher (PM) – Deputy Director
Engagement and Grants, Francis Thomson (FT), Aaron Witthoeft (AW)
Items
1. Has there been a shift in the provision of human/community services from services provided “by” the government to services provided “for” the government.
a. Changes in policy positions by government’s (direct or indirect i.e. as a consequence of a shift to outsourcing services generally; or specific human services policy directions?). b. Data to support this – number of tenders to the NFP sector increasing? Value of those tenders increasing? Any trend in the number or types of services being provided by the NFP sector increasing? PM – yes there has been an increase in human services procurements over the years. CL – procurement framework changes over time have supported NFP procurements i.e. lifting the agency threshold from 4.4m – 15m. Also direct negotiation – we do more of that in the NFP space which is justified by the market research that we do. JK – we don’t want business units to roll over contracts, they need to understand their markets – this challenge is not confined to the NFP sector at DHS, applies also to for profit procurements.
2. Data illustrating the size of the procurement/grants spend on NFP services:
a. Total public sector (DHS) spend on human services contracted through NFPs; b. A breakdown of this by service type (e.g. homelessness, gambling help, financial literacy etc); and c. Any trend data on this spend over the last 5 years [JK had a number of data download documents for discussion and provided AW with one document to take-away indicating value of number of new NFP contracts struck in 2017/18 (need to confirm) – follow up and additional request required]
3. How many contracts with NFPs have been struck since the SANFRAG reforms came into operation (i.e. that are subject to PC044 and new Funding and Grant Agreements etc)?
Only a few. Although PC044 has been out a while the “standard contracts” have only been available since January 2019.
We’ve been putting guides together to assist DHS business units to comply with PC044. A number of our homeless and gambling help programs are already using PC044 – Community (Pat Maher’s group) is also using it now. Community are the most progressive business unit in
For Official Use Only – I1 – A1 1 Office of the SA Productivity Commission Discussion Outline
DHS in terms of using contemporary practices and innovative procurement approaches; particularly in terms of market engagement and continuous improvement.
CL – There are challenges with services funded through Cth in terms of us meeting the 6-month notification requirement under PC44.
4. From the Department’s perspective, what is the more effective way of funding NFP human/community services – grants or procurements?
PM – either can work, our grants framework mirrors the procurement f/work. By having rigor in our grants process it helps us to know what we want. [elaborate]
PM – evidence-based practice across many human services fields is not clear, or there are varying perspectives about what is best practice; nonetheless we should have rigor around what we ask for and what the NFPs will do. In terms of an outcomes-based approach – we do need to specify key components in terms of what we are seeking by way of outcomes and for reporting purposes. Engaging more effectively with the market from this perspective is a developmental area for us – SANFRAG reforms are supporting improvement in this area.
PM – important to note that not all NGOs are high performers, some have less than optimal governance arrangements – the best approach is a partnership approach where we work through things with the sector; this works well [example please]. It is incumbent on DHS to know what we need to acquire to meet government’s expectations – it is public money. Further, government procurers in the human services space have a broader view of the whole community sector, whereas NGOs often have a specific focus or cover a specialised area of service provision so don’t necessarily have an appreciation of government’s total need or requirement.
5. Has the Department received any feedback regarding SANFRAG reforms in terms of the impact on for-profits with an interest in the human services space?
a. E.g. an uneven playing field, or unfairly advantaging the NFPs, particularly in those service areas where NFP and for profits are competing or may compete in future?
CL – we don’t structure procurement processes differently for NFPs as opposed to any other procurement, so procedurally don’t see that PC044 or any other NFO specific requirement has any adverse impact on for profits.
JK – we might have more direct negotiations with NFPs than other non-community sectors – nature of human services provision.
PM – sometimes providers just do what’s more convenient for them, rather than what we have indicated is required (in contract?).
[more comment required, particularly in those areas where for-profits may be competing against NFPs now or into the future]
6. Is there anything that the recent SANFRAG and associated reforms didn’t capture that would be beneficial to procuring with/granting NFPs?
a. Obtain: Social Procurement Action Plan (part of 18/19 Strategic Plan projects).
For Official Use Only – I1 – A1 2 Office of the SA Productivity Commission Discussion Outline
b. SPB accreditation submission (p. 16): Reduction in red tape associated with procurement of services from the NFP sector – PGU and Community Services Division (DHS) have jointly initiated a project to reduce red tape associated with tendering. Key stakeholders (which includes the 9 peak organisations for community services) have been identified; they will provide feedback and input to this project.
PM – “placed based” approaches are advantageous, especially for small geographical areas where multiple services are required and more cultural requirements met e.g. STAY program/aboriginal community programs.(?)
PM – see Cth PC Human Services report 12 months old – should we consider individualised approach like NDIS – PM doesn’t believe this is appropriate at this time.
PM – need more feedback from clients about service design – I’m running focus groups on their experience to capture this. I’m calling on people who have been through the system and can talk to what worked and what didn’t. We also need to check population data and indicators and hear from suppliers and work out what all this means – this is what a “commissioning framework” should look like – we are trying to move to this.
For present process see STAY service to aboriginal youth program – consulted various data sets including youth justice and geographical hot spots – consulted with service providers and cross- checked their feedback to how we procure services [case study – more detail/slideshow from Pat]
CL – we would be happy to rescind current contracts and let new goods and services contract using the new Standard Services Agreement if an NFP requested that.
7. Does procurement/grants with NFPs require wider/more complex/additional considerations compared to other procurements?
a. If yes, what are these considerations and are they supported by the current procurement process and procedures?
b. Is the Forward Procurement Plan published publicly and regularly?
c. Obtain: Contract Management Handbook and Procurement Instructions.
PM – hard to achieve outcomes, politically sensitive, community awareness i.e. I could make a case for a program that is not politically palatable eg food relied – people are on this for average of 7 years, can be counter-productive. We need to increase our evidence-based approach and strategic approach.
PM – our feedback from NFPs is that SPB’s training is not applicable for them and doesn’t address their specific needs [what are these needs?]
PM - don’t want to give unfair advantage to suppliers but we need to discuss with current providers – repeating feedback from service providers to them – concerned this could breach probity if those new suggestions feature in new procurement specs in a subsequent tender process.
For Official Use Only – I1 – A1 3 Office of the SA Productivity Commission Discussion Outline
PM – want to start changing services over the course of the contract as part of our commitment to continuous improvement journey – the contract is the “baseball bat” for me re enforcement but I don’t like to bring that out.
PM – when I do an evaluation I also identify areas for improvement – performance management framework; relational contract management is my preferred approach and it supports service delivery improvement [more on this]
PM – I start early having roundtables with providers and looking for their ideas.
JK – business units are concerned at upsetting non-performing NFPs – can lead to poor outcomes. Poor contract mgt and poor contract reporting. Individual performance issues can also affect this in terms of the agency person managing and reporting on the contract. The contemporary approach being used in the Community Services branch (Pat) is what we are trying to replicate in other areas of DHS.
CL – have not got good contract management tools and guides etc. Historically NFPs weren’t caught in contract reporting arrangement for DHS [more on this]
CL – we can do variation to contract to reflect change in contract specification arising from Pats approach to continuous improvement [any data on how often this happens and process/procedure]
JK – is about drafting sufficiently flexible contract provisions to enable changes to the way services are delivered.
8. Are there impediments or influences that impact upon the Department’s ability to collaborate and design services with the NFP sector in a procurement or grant context?
See above.
9. Does procurement process and procedure support or detract from the Department’s ability to fund human and community services in line with government’s policy priorities?
a. Obtain: PGU Business Plan (see DHS SPB accreditation submission)?
JK – I note from their inquiry submission that SACOSS still unhappy about contract reporting. We had examples of fraud and money not going to the right place e.g. service provider using 40% of block funding for administration, contract specifies 18% - a contract enforcement issue.
CL – we are in a position to be able to discuss these issues with you because we have good oversight now [example of recent changes to support this]
For Official Use Only – I1 – A1 4 9
16(1)(a)(iv) Adverse effect on agency functions
10
Cranwell, Denise (DPC)
From: Carey, Mark (DTF) Sent: Thursday, 14 February 2019 7:53 AM To: Witthoeft, Aaron (OSAPC) Subject: RE: NFPs and the Late Payment of Government Debts (Interest) Act 2013
Hi Aaron,
Apologies for the delay – I have been looking through the various late payment interest documents to locate details/recommendations about changing the definition of “qualifying body”.
There isn’t any detailed discussion about this matter in the key documents, however I have extracted the following from a Minute approved by the Treasurer regarding drafting amendments to the Bill.
“In addition to the above, it also recommended that invoices issued from one public authority to another are excluded from the scope of the Act. Section 5(2) of the Bill amends the definition of a “qualifying body” to exclude State, Local and Commonwealth Government authorities from being entitled to receive interest payments.”
As indicated in our discussion, the exclusion of NFPs not incorporated under the Commonwealth Corporations Act was an unintended consequence of adopting the above recommendation.
I have separately been requested to work with the Parliamentary Counsel about what would be required to enable interest to be paid to all applicable NFPs under the Act.
Should any further information be required please let me know.
Regards
Mark Carey A/Executive Director| Government Services Branch
Wakefield House, Level 9, 30 Wakefield Street ADELAIDE SA 5000 t 8226 5102 | e [email protected] | w sharedservices.sa.gov.au
Information contained in this e‐mail message may be confidential and may also be the subject of legal professional privilege or public interest immunity. If you are not the intended recipient, any use, disclosure or copying of this document is unauthorised.
From: Witthoeft, Aaron (OSAPC) Sent: Tuesday, 5 February 2019 2:26 PM To: Carey, Mark (DTF) Subject: NFPs and the Late Payment of Government Debts (Interest) Act 2013
Hi mark,
Thanks for the quick chat this afternoon – very helpful.
1 As discussed, if you have a previous briefing or instructions to Parliamentary Counsel on this that you can share for context, and that sets out the reasons for the change to the definition of “qualifying body” I would be most grateful.
Also, given legislative amendment would be required to address the issues raised by NFPs is there any work proposed in that regard i.e. an amendment?
Many thanks.
Aaron Witthoeft Principal Inquiry Economist | Office of the SA Productivity Commission State Administration Centre, Level 6, 200 Victoria Square ADELAIDE SA 5000 | DX56201 T 08 8226 7107 E [email protected] W www.sapc.sa.gov.au
Information contained in this e-mail message may be confidential and may also be the subject of legal professional privilege or public interest immunity. If you are not the intended recipient, any use, disclosure or copying of this document is unauthorised.
2 11
Cranwell, Denise (DPC)
From: King, Jody (DHS) Sent: Monday, 18 February 2019 10:35 AM To: Witthoeft, Aaron (OSAPC) Cc: Thomson, Frances (OSAPC); Maher, Patrick (DHS) Subject: RE: SA Productivity Commission - Procurement Inquiry - Follow Ups Attachments: 2018 STAY Forum_External Evaluation Summary Report (A20394498).doc; NFP Procurement Processes - STAY Example - PowerPoint Presentation with notes.pptx; Draft SANFRAG Implementation Guide Jan 2019 (A20388630).pdf; SANFRAG Fact Sheet.docx; Contract Management Handbook.docx; Case Studies - Relational Management.docx; Information - Variations due to continuous improvement.docx; Unpacking-Relational-Contracting_v19 IACCM (A20399150).pdf; Procurement Instructions.doc; PGU Annual Business Plan 2018-19.docx; Divisional Plan - Fin- Finance and Business Services.docx; DHS Social Procurement Action Plan - January 2019.docx
Hi Aaron
Please see below (and attached) some of the information as requested.
I know that Pat is still finalising some of his information and I think we might need to discuss question 5 to completely understand what we need to provide.
In the meantime please let me know if we have forgotten something, or would like any further clarification. I will be in the office all day Wednesday if you would like to discuss anything
Regards Jody
Jody King A/Director, Procurement and Grants Finance and Business Services
Department of Human Services Level 4, 45 Grenfell Street, Adelaide SA 5000
T: (08) 8124 4015
This email may contain confidential information, which may be legally privileged. Only the intended recipient(s) may access, use, distribute or copy this email. If this email is received in error, please inform the sender by return email and delete the original. If there are doubts about the validity of this message please contact the sender by telephone. It is the recipient's responsibility to check the email and any attached files for viruses.
From: Witthoeft, Aaron (OSAPC) Sent: Monday, 11 February 2019 2:54 PM To: Lock, Caroline (DHS) ; King, Jody (DHS) ; Maher, Patrick (DHS) Cc: Thomson, Frances (OSAPC) Subject: SA Productivity Commission ‐ Procurement Inquiry ‐ Follow Ups
Hi everyone,
Thank you for taking the time to discuss the procurement inquiry candidly last week – it was a very constructive discussion and we are grateful for the time and information you can share.
As discussed, I have identified some data and documentation following our discussion that would be advantageous to the Commission’s inquiry if you could make it available. I would be happy to discuss the data request further if that would be of assistance. I have listed a couple of examples of potential case studies that arose during our discussion – these are really important from the Commission’s perspective so if you can assist that would be highly valued. I have
1 also listed “issues to elaborate on” that arose during the discussion that would benefit from some additional detail. I have listed them in order of importance from my perspective. Some of them are probably better considered by Pat, others by Caroline and Jody, and some probably with input from both.
I would be happy to meet again and discuss with you if that would be advantageous; otherwise some additional dot points or provision of existing briefings or documents would be great.
Given the timeframes associated with the publication of our draft report I would be most grateful if you could offer any response no later than Friday 15 February 2019. If there is anything you expect to be able to provide but cant meet this timeframe please let me know.
Data Total public sector (DHS) spend on human services contracted through NFPs i.e. total value of contracts under management where NFP is supplier. (Please see attached report) A breakdown of this by service type (e.g. homelessness, gambling help, financial literacy etc). (Please see attached report) Data showing the time to respond to tender for contracts NGOs are competing for We done have any specific data on this. Different tenders (value and risk) have different response timeframes. Recently, the STAY program was open for 5 weeks, the Youth Support and Development 4 weeks (low value under $550k); the Consumer Credit select tender was open for 4.5 weeks. Guidance from procurement instructions business areas should be allowing the 6 weeks instead of minimum 4 weeks.
Data supporting/not supporting the contention that over the last 5 years there has been a shift in the provision of human/community services from services provided “by” the government to services provided “for” the government i.e. an increase in the number of NFP contracts. We do not have any data on this. There has been consistent types of services tendered over the last few years. There have been new funding for certain projects, but we have legislative programs, including gambling help services that have not changed.
Case Studies Challenges with NFPs: Can you please provide information to support a case study regarding where “providers just do what’s more convenient for them”, rather than what is expected by the agency or what they are contracted for. The discussion regarding a supplier continually seeking to acquit 40% of their funding against administrative costs notwithstanding the contract provides for 18% is a good example. It would be even more persuasive if you could provide an example where services are not being met as contracted for, and what issues are at play.
1. Service was tendered for provision of services/advice, total cost just over $400k per year. Tendered budget confirmed no more than 18% of budget to be costed to non-service delivery administrative costs. Acquittal issues of organization acquitting almost 40% as admin. Through contract management, following their performance review and data analysis a performance improvement plan was develop. All PIP actions were addressed, and resubmitted expenditure and budget in line with tendered requirements. Following this KPIs were met.
2. In 2017-18, EFAP funds provided the following assistance to individuals and families experiencing financial crisis: 61% food, 7% transport, 2% utility bills, 30% ‘other’. A further exploration of the data which captures the breakdown of 30% ‘other’ EFAP expenditure was introduced with EFAP providers. This included EFAP providers providing a list of their top ‘other’ categories. As a result, the following additional categories have been added ‘education expenses’ including school fees, uniforms, IT equipment and stationary; clothing/shoes, ‘household items’ including whitegoods, furniture, bedding, appliances, ‘household starter kits and housing stability’ such as contribution to rent, storage/removalists, skip bin hire, and lawn mowing. The EFAP providers welcomed this change, as it allows for additional trends to be identified, and opportunities for service providers to explore arrangements with third parties to negotiate to receive bulk goods (e.g. household whitegoods) at a reduced price.
DHS Innovation: Can you please provide some additional detail/briefing/PowerPoint presentation regarding the “place based” approach (I think this was the STAY program). Our discussion regarding the approach DHS took i.e. data interrogation (including youth justice), geographical hot spots, consulted with service providers and cross-checked their feedback against procurement process makes a good example of innovative and contemporary procurement practice. If there is another example I would be happy for you to provide that instead.
See attached report on External Evaluation STAY forum, PowerPoint process, SANFRAG Fact sheet (still being finalised)
Issues to elaborate on 2
1. In reference to Pat’s comment that not all NGOs are high performers, can you please elaborate on what the “partnership approach” with the NFP market entails? In particular in the context of the discussion around it being incumbent on DHS to “know what we need” to meet expected service and policy outcomes. Still waiting on further information
2. Can Pat share anything further regarding his comments about adopting a “relational management” approach to support identifying areas for service delivery improvement, and how this is integrated into the procurement process? Please see Draft Implementation Guide, Contract Management Handbook, Case Studies Relational Management
Articles that have been used by DHS:
Forbes article - https://www.forbes.com/sites/katevitasek/2016/11/30/relational‐contracting‐on‐the‐rise‐ with‐the‐success‐of‐the‐australian‐navy/#4818ac4a303a IACCM Unpacking Relational Contracts and https://www.iaccm.com/services/relational-contracting/
3. In the context of the comment that DHS applies the same rigour to its grants processes that it does its procurement – can you elaborate on how the DHS grants framework mirrors the procurement framework? -Same planning process: Procurement and Grants Unit works with BU on requirements, outcomes needed -Completion of the same documents: use of AP and tender documents (which are modified to fit within grant information). The AP has to clearly set out what the grants are to achieve, how DHS will receive submissions/proposals, how these will be assessed (evaluation matrix, mandatory criteria, weightings), funding guidelines, how they will be managed (formal contract management, site visits, acquittals/proof of expenditure for project outcomes). If needed, also capture if only certain part of the community can access the grants and justification. Policies still apply, such as late responses, evaluation principles etc A purchase recommendation is also to be completed confirming process undertaken, detail of scores/evaluation summary (signed by delegate with Procurement approval) Contract management reports (or contract closure report only depending on length of agreements)
4. How often are contract variations done to reflect change in contract specification arising from the continuous improvement approach Pat mentioned? What process/policy is followed in these cases? We don’t have any data on how often we vary a contract due to continuous improvement compared to other types of variations, but we have information when we have
Please see attachment: Information on variations due to continuous improvement
5. In relation to the brief discussion regarding NFPs not always having been caught in contract reporting arrangement for DHS, can you indicate why, when and how this has changed? May need some more guidance about this question
6. Can you offer additional feedback regarding NFPs advice to the department that the State Procurement Board’s training offerings are not applicable for them, especially in terms of where they are reporting its missing the mark? Waiting on further information
7. Can you offer any further feedback regarding any unintended impact of the SANFRAG reforms in terms of creating an uneven playing field for for-profits in those service areas where for-profits and NFPs are or will be competing? Generally our procurement processes for community welfare services have been open process, which would allow any organisation (for profit or NFP) to apply. There are certainly tender processes where we have done a select call to certain parts of the NFP Sector. However, these ‘open’ tender processes often require specific requirements that would not appeal to a for profit, for example the organisation must demonstrate their relatable experience, linkage to community, referral services etc, as well as operate in a tight budget. We do have a for profit organisation providing gambling help services, which has previously been provided by and NFP and the rest of the contracts are held by NFPs. In this case the for profit was the best suited organisation and are achieving very good outcomes for vulnerable clients. Similarly, our Linen and Laundry contract is help by Minda and our previous provider was Spotless. After conducting an open and competitive tender process Minda was the overall preferred tenderer taking into account their service delivery model and price.
Documents Social Procurement Action Plan (part of 18/19 Strategic Plan projects) Attached 3
Any documents or briefings regarding the progress of the red tape reduction project between PGU and Community Services Division regarding procurement of services from the NFP sector, including reference to the extent of engagement with the NFP sector. I have included our communication plan. We are just starting talking with our Communication team about developing a video to assist NFPs in applying for tenderers, FAQs and writing in plain English. Also, the Procurement Unit and Community Services is discussing how we approach the Peak bodies about some of the barrier to tendering, and how we can provide guidance to the sector. This is still in early planning.
Contract Management Handbook and Procurement Instructions Attached PGU Business Plan PGU Business Plan, plus our part of the Divisional Business Plan
Many thanks and happy to discuss with you.
Aaron Witthoeft Principal Inquiry Economist | Office of the SA Productivity Commission State Administration Centre, Level 6, 200 Victoria Square ADELAIDE SA 5000 | DX56201 T 08 8226 7107 E [email protected] W www.sapc.sa.gov.au
Information contained in this e-mail message may be confidential and may also be the subject of legal professional privilege or public interest immunity. If you are not the intended recipient, any use, disclosure or copying of this document is unauthorised.
4 12
Service to Aboriginal Youth Community Services - Overview of External Consultation
Background The Department of Human Services (DHS) Service to Aboriginal Youth (STAY) program provides funding to non-government organisations to deliver flexible and ongoing support and programs for young Aboriginal and Torres Strait Islander people living in rural and remote areas. The current STAY program provides support to vulnerable young Aboriginal and Torres Strait Islander people aged between 10 and 25 years and links them to programs and interventions that will have a positive influence on their lives. The existing service agreements with the organisations listed below expire 30 June 2019.
Service Provider Service Name Aboriginal Family Support Services Limited STAY Coober Pedy Anglican Community Care Aboriginal Youth Services - Riverland Anglican Community Care Aboriginal Youth Services - Murray Bridge Ceduna Aboriginal Corporation Ceduna Position Koonibba Aboriginal Community Council Koonibba Aboriginal Youth Service Plaza Youth Centre Plaza Youth Services - Whyalla Port Augusta Youth Centre Port Augusta Youth Services Raukkan Community Council Raukkan/Meningie Aboriginal Youth Services Yalata Community Inc Aboriginal Youth Services - Yalata
Ongoing STAY performance reports and contract management discussions highlighted a disparity between the various STAY programs across the regions relating to areas such as: the types of programs being delivered community and individual successes connectedness between STAY providers governance and organisational capacity quality assurance, compliance and reporting In a bid to understand the reasons behind this disparity in more detail, DHS decided to host a series of Regional STAY Forums. These forums would provide a platform for service providers and young Aboriginal and Torres Strait Islander people to come together as a group to share good practice, capture the participant’s view and suggestions for improvement and showcase successful achievements. In addition, the information gathered during these Forums would be used to inform the next STAY procurement process for new contracts from 1 July 2019 as well as updating the STAY Guidelines. Discussion In preparation for the Regional forums, Regional Coordinators engaged with all STAY service providers to seek their support and suggestions for the most appropriate way to deliver the forums for their respective communities. Using their feedback a proposal was prepared and subsequently approved to host three Regional STAY forums in the locations detailed below. 1. Port Augusta - to include Port Augusta Youth Centre, Plaza Youth Centre, and Aboriginal Family Support Services. 2. Murray Bridge – to include ac care Riverland, ac care Murray Bridge, and Raukkan Community Council. 3. Ceduna – to include Ceduna Aboriginal Corporation, Koonibba Aboriginal Community Council, and Yalata Community Inc. It should be noted that the Ceduna Forum did not proceed due to Traditional Aboriginal Cultural business occurring in the region in the days immediately preceding the event. While Service Providers and DHS staff agreed not to reschedule the Ceduna forum, those affected by this cancelation were provided the opportunity to attend one of the other forums and/or contribute to the feedback process using Youth Surveys and the Request for Information (RFI) questionnaires as well as provide information during the teleconferences that preceded these forums.
Regional Forums Based on the feedback provided by the Service Providers prior to each Forum, a tailored agenda was developed for each event focused on the age groups of those attending and aimed at encouraging optimum group and individual participation. While the agendas differed slightly between each Forum, both events focused their group discussion and activities around three key topics using example prompts below: Community o What do you like most about the community you live in? o Is there anything you would like to see changed or improved? o How could it be changed or improved? Learning o How do you feel about school and your learning (including cultural learning)? o Does anything get in the way of your learning? o What helps you do your best with your learning? Opportunities after school o What opportunities do you know about that are available to you after school? o What are your hopes for yourself after you leave school? o What would support you most to achieve your goals?
Port Augusta Forum - 17 April 2018 This event was held at the Central Oval Community Hub and a total of 29 young Aboriginal and Torres Strait Islander people attended. (This included attendees from Plaza Youth Centre and the Port Augusta Youth Centre). In addition, STAY Coordinators, support staff and a number of family members also attended. While there were a couple of older teenagers, the vast majority of attendees were aged between 10 and 14 years of age.
Murray Bridge Forum – 24 April 2018 This event was held at the Ninkowar Aboriginal Community complex and a total of 24 young Aboriginal and Torres Strait Islander people attended. (This included attendees from Raukkan Community, Murray Bridge and the Riverland). In addition, STAY Coordinators, support staff and a number of family members also attended The vast majority of attendees attending this event were aged between 13 and 22 years of age.
Overview of Youth Feedback During the two STAY forums responses from the 53 attendees were captured using a range of mediums including group work, notes on butcher’s paper, voting tools and one-on-one video interviews. Further, to capture the voice of those who were unable to attend the forums, a survey form (developed in consultation with the STAY Service Coordinators) was sent out to prior to the Forums. 68 survey forms were returned. Below are the key themes based on the feedback received: The importance of family and culture. Impacts of violence and substance abuse, specifically on health, wellbeing, education, employment and housing. A strong desire to be healthy, finish year 12, and gain employment. The need and benefits of leadership training, mentoring and ongoing support. The need and importance of a “safe place” for young people to go to receive culturally appropriate support, meals/snacks and have access to programs and activities. In addition, the need for, and appreciation of, a “quiet place” for homework and other study. The benefits of a holistic approach - wrap around services, partnerships and referrals. Lack of/limited public transport options, including driver training.
The importance of cultural camps and the need for service providers to offer both sport and non sport programs and activities to support young people. The need for more employment and training opportunities in regional areas.
Overview of Service Provider feedback To gather an understanding of the various STAY programs currently being delivered a Request for Information (RFI) questionnaire was sent out to all STAY providers prior to the Forums (see Attachment A). In addition, video interviews were conducted with each STAY Coordinators at the Forums. The RFI questionnaire asked about the respective service models, the priority needs and emerging issues from each community/region. Below is a summary of those responses. While the current program caters for people aged 10 – 25 year, the majority of current attendees are within the 12-18 age brackets. All providers provide a culturally appropriate safe space to deliver programs and support for young Aboriginal and Torres Strait people who are disconnected/disengaged. While programs and activities have similarities, they do vary according to the needs of each community and all have a strong cultural focus. Service providers state that their successes are due to the strong relationships that have been established over time, thus stability in staffing and long term funding is key. All providers employ Aboriginal youth workers/cultural advisors (mostly part time) and actively work with partners to create opportunities for their clients in employment, education, volunteering, training and leadership. Although there are some variances, service providers reported a breath of similar priority and emerging issues amongst the community and young people that included: alcohol and substance misuse, family breakdown, domestic violence, child protection issues, truancy levels, low numeracy and literacy skills, limited education and employment pathways, involvement with juvenile justice and recidivism, inadequate diet, poor hygiene, mental health concerns, loss and grief, disconnection with culture/family, risk of homelessness, and limited transport options. The RFI also sought information about the organisation’s involvement with a quality framework such as the Australian Service Excellence Standards (ASES). While some of the existing service providers have a quality framework such as ASES already in place, those who don’t are either actively working towards one and/or accept the need to commence this process in the near future.
Consultation with other External stakeholders CSD keeps regular communication with the Department of Prime Minister and Cabinet and from information learned considered: the collective allocation of funding to Aboriginal and Torres Strait Islander young people
the wider service system in community opportunities for collaboration between State and Commonwealth funded services in these communities
Next Steps The recent engagement and consultation process has confirmed there continues to be strong need for services that support Aboriginal and Torres Strait Islander young people living in rural and remote communities to achieve their goals, strengthen their cultural and community connection and build long term resilience.
While DHS remains committed to the continuation of the STAY Program post 30 June 2019, it is important to ensure that the program is consistent with government and community priorities, responsive, targeted and reaches the communities with the greatest need.
Below is a list of “next steps” to assist with this process.
Consult with DHS CSD Aboriginal Policy and Projects as well as DHS Youth Justice Develop new STAY guidelines Consult with senior Aboriginal staff from relevant areas of the Department for Child Protection and the Department for Education, seeking their input to update the STAY program guidelines covering aspects such as the target group, key priorities, program aim, program outcomes and service activities. Review the target group numbers of current, and potential new communities of need, using available ABS and other relevant data sources Complete an analysis of RBA data from existing service providers to assist with the development of a set of standard RBA measures for the STAY program Complete a Risk Assessment of all existing STAY service providers In conjunction with DHS Procurement and Grants Unit, commence the procurement process to award new contracts from 1 July 2019 including the preparation of an Acquisition Plan to assist with any new tender process Determine the most appropriate approach to market (i.e. direct negotiation, public tender or selective tender) Following award of new contracts, work with successful providers to co-design standard RBA measures Establish a regular STAY provider networking forum with successful providers. Attachment A
Request for information We are also keen to gather additional information about your current service model and also how you currently identify the needs of young people in your program as well as the needs of the general community/region.
To assist we ask that you: please consider the following questions and provide responses of about one page in length for each question (no longer than two pages)
Questions:
1. Describe your current service model. In your answer please include the following: a. a description of your Service model b. an overview of your current client group (including age range) c. an overview of how you recruit and maintain culture in your service (e.g. employment of Aboriginal workers, engaging volunteers and/or mentors, involving Elders/Respected Aboriginal people from the community/Region) d. a description of your partnerships with other organisations including, but not limited to, your usual client referral pathways (both how do clients enter your service and who do you refer clients to) e. a description of how your service model reflects a focus on using RBA data and/or other information to improve practice and outcomes
2. In relation to your service: a. What are the priority needs and emerging issues for young Aboriginal people in your community/region? b. What are the potential opportunities for young Aboriginal people in the community/region? c. What are the priority needs for the general community/region? d. How does your service currently contribute to meeting these needs? e. Does your organisation have accreditation, or are you actively involved and progressing, in a whole-of-organisation quality framework such as the Australian Service Excellence Standards (ASES)? If no, is your Organisation involved in DCSI’s STARService program? 13 Services to Aboriginal Youth (STAY) Ceduna, Coober Pedy, Koonibba, Murray Bridge, Port Augusta, Port Lincoln, Port Pirie, The Riverland, Raukkan/Meningie, Whyalla, Yalata
• The STAY program has a focus on early intervention, providing at risk young Aboriginal people aged between 10 – 19 years with access to the services and guidance they need to: – achieve their goals – strengthen their cultural and community connection – build long‐term resilience
• Through a platform that actively encourages partnerships and collaborations with the Aboriginal community (including Elders, Aboriginal leaders, services providers and other stakeholders), the service providers will support young people in the context of their family and community. Services to Aboriginal Youth (STAY)
• Planning and Review – aim for 18 months prior – performance review of existing services
• Needs Analysis – population indicators – other data – YJ, Courts – request for Information from providers – survey of clients
• Budget – redistribution, additional communities – refinement of Target Group Services to Aboriginal Youth (STAY)
• Consultation – Client Voice: youth forums – Internal stakeholders: CS Aboriginal Policy and Programs, Office for Youth, DHS Youth Justice, Dept Child Protection, Dept Education, Department of Prime Minister and Cabinet
• Specification, Outcomes, Targets – Informed by all the above
• External Market Analysis – Aboriginal Community Controlled Organisations Services to Aboriginal Youth (STAY)
• Evaluation Plan – mandatory criteria – evaluation criteria – essential elements of scoring matrix – risk assessment – budget considerations e.g. % administration costs
• Part D (tender document) – format of questions and responses – Presentation stage
• Composition of evaluation panel Services to Aboriginal Youth (STAY)
• Negotiating outcomes, targets, assessment and data collection tools
• Active contract management – Communities of Practice at commencement and ongoing – Performance Reviews – R2D2
• Liaison with stakeholders
• Keeping Minister informed 14
South Australian Not for Profit Rules and Guidelines (SANFRAG) Implementation Guide
Last updated January 2019
Page | 1
SANFRAG Overview
SA PROCUREMENT BOARD TREASURER'S POLICY/GUIDELINE INSTRUCTIONS 11 AND 15 Mandating the use of SANFRAG in Mandating the use of SANFRAG in procurement processes for NFP procurement processes for NFP sector sector
SANFRAG
MANDATED PRINCIPLES FOR FUNDING OF NFPS Robust planning and design – Collaboration and partnership – Proportionality – An outcomes orientation – Achieving value with relevant money – Governance and accountability – Probity and transparency – Community development principles
MANDATED POLICY AND PRACTICE GUIDELINES State Procurement Board policies and guidelines amended to take account the principles for dealing with NFP funding.
PROCUREMENT GRANTS Current master and service Low value/risk contracts agreements replaced with Mandated Grants Agreement simplified agreements as multiple year contracts expire Mandated contracts, rules amd guidelines using the principles the using guidelines amd rules contracts, Mandated
SANFRAG GOVERNANCE Governance and dispute resolution via departments, the State Procurement Board and DTF as set out in DPC044. DTF, DHS, Peak Bodies to monitor, review and update SANFRAG.
Page | 2
SANFRAG Contracting Process Overview
SANFRAG applies to agreements with non-profit providers or public authorities. It applies to ongoing and one-off agreements, including grants that involve a formal contract.
Guiding documents Stage 1: Exploration Links ✓ Draft new or review existing funding
guidelines Funding Policy for the Guiding Questions for ✓ Determine extent of consultation required NFP Sector (DPC044) Program Managers ✓ Consult on draft guidelines and expected outcomes Page 4 State Procurement Act 2004 p 8 State Procurement Practical Stage 2: Planning Regulations 2005 ✓ Implementation Guide Develop Acquisition Plan with PGU ✓ If required, draft tender documents with Procurement Policy Page 5 PGU ✓ Undertake risk assessment Framework ✓ Determine contract length
✓ Consult as determined in Stage 1. Acquisition Planning SANFRAG Definition of Policy Community Development Stage 3: Selection ✓ With PGU, select suitable provider: Supplier Selection Page 15 - evaluate options Policy - negotiate as required - ensure provider meets negotiated and Contract Management non-negotiable requirements Checklist for Engaging Policy ✓ Detail evaluation approach the NFP Sector
Page 16 Simple Procurement Policy
Stage 4: Ongoing Management ✓ Monitor provider’s performance Treasurer’s Instruction Case Study: ✓ Ensure provider takes community 15 - Grant Funding Community Services development approach p 8 Support Program ✓ Provide min 6 months’ notice of cessation and, where funding certainty SPB User Guide: Page 17 exists, of renewal. Procurement Operation or Grants
Guiding Principles Robust planning and design – Collaboration and partnership – Proportionality – An outcomes orientation – Achieving value with relevant money – Governance and accountability – Probity and transparency – Community development principles
Page | 3
Guiding questions for program managers
Stages 1 and 2: Exploration / Planning
Funding Guidelines - Does the program have Funding Guidelines?
Community Impact and Need - What is the desired impact or change you are seeking to achieve in the community? - What is the evidence of community need? - Why and how the funded activity will affect the desired outcomes? - Are the desired outcomes for the funding program defined, including quantitative, qualitative and milestone information that is realistic about what the funding is intended to achieve?
NFP Engagement - To what extent and on what issues do you intend to engage with the NFP sector, based on the scale and risk profile of this funding activity? - Have you determined the non-negotiables of the funding program and developed a rationale for these? - How do you intend to engage the NFP sector, and has your approach have the relevant approvals?
Process - Have you considered (and if necessary consulted) about using a fee-for-service arrangement? - Have you documented a timeline for conducting the planning and selection process? A minimum 6 months’ notice is usually required, and short-term contract extensions to accommodate delays to tendering processes should be avoided. A tendering process should typically commence 12-18 months prior to this (depending on scale and complexity) including 6-9 months consultation.
Term - What is the proposed term of the contract, including any optional extension periods? - Is your proposed term less than 3+3+3 years, and if so, why (i.e. uncertainty of funding, high-risk program or changes in the market)? - If extending the term of an agreement, have you undertaken a review of community need, service specifications, contract performance and requirements?
Community Development - How do you intend to embed a community development approach in the planning and selection process? - How do you intend to promote community and personal empowerment in regard to client outcomes?
Stage 3: Selection
Selection Process - Is your selection process as simple as practicable, while still being robust and accountable? - Have you assessed potential risks associated with your selection process and ways to manage these? - Does your selection process consider both cost and non-cost factors in determining value? - Is there a case for limiting the number of suppliers?
Evaluation - Is there an opportunity to have the NFP sector provide evaluators as part of the program? - Do other experts need to be part of the evaluation process?
Collective Impact - Is this selection process associated with and possibly influenced by a collective impact approach?
Reporting - Are volume, detail and frequency of reporting proportional to risk involved and outcomes sought?
Stage 3: Contract Management
Contract Management Plan - Have you established a plan for ongoing management of the contract that ensures ongoing communication, active management and performance monitoring commensurate with the risk involved and outcomes sought? - Does the contract management plan reflect a continuous improvement approach?
Page | Transition4 Process - Have you considered the transition out process at the end of the contract period, taking into consideration a minimum notice period of six months may apply?
Practical Implementation Guide
Introduction
The South Australian Not for Profit (NFP) Funding Policy (Department for Premier and Cabinet Circular 044 -South Australian Funding Policy for the Not-For Profit Sector) applies from 1 July 2017, and aims to support and strengthen collaborative partnerships between government and the NFP sector. It provides a consistent approach to all aspects of funding, sets clear requirements for public authorities, and reduces the administrative burden on NFPs and maintains their independence.
The approach in the Policy is consistent with the Stronger Together commitment that articulates the principles of collaboration and partnership underpinning the relationship between State Government and the not-for-profit health and community services sector. We know that the best outcomes for people and communities are achieved when we work in partnership with the NFP sector to plan and deliver activities and services.
The Policy applies to ongoing and one-off funding arrangements, including funding for services to the public authority directly, or to a third party, and grants that use a formal contractual agreement, regardless of dollar value. It has been co-designed by government and not-for-profit representatives to reflect the needs and interests of not-for-profits, as well as government, and to acknowledge our shared investment in improving outcomes for communities.
The Policy must be read in conjunction with relevant Treasurer’s Instructions, State Procurement Board policies and guidelines and other relevant legislation.
The NFP Funding Policy has paved the way for the development of the South Australian Not-for-Profit Funding Rules and Guidelines (SANFRAG), a suite of reforms arising from the policy. As part of this reform, the government has endorsed a streamlined approach to applying indexation to funding for NFPs and the use of consistent contract templates for use across government (anticipated to be operational by 1 November 2018).
The State Procurement Board has updated the following policies to incorporate the NFP principles: • Procurement Policy Framework • Acquisition Planning Policy • Supplier Selection Policy • Contract Management Policy and • Simple Procurement Policy.
All funding processes must adhere to the relevant Treasurer’s Instructions, State Procurement Board Policies and Guidelines, and the DHS Procurement Framework. Funding activities, whether funding of services or administering a grant, require a consistent approach, including: • appropriate and robust planning, proportional to the scale and risk profile of the funding activity • clearly defined and transparent selection or application processes in accordance with good probity practices • sound management and reporting frameworks that deliver value.
The Policy outlines a number of best practice principles for government and NFP funding relationships. The intent of this document is to provide guidance to program managers in applying the principles when planning, allocating or managing funding programs.
Page | 5
The Policy outlines an expectation that government will work with the NFP sector in a collaborative partnership approach while maintaining appropriate probity and management in all procurement/grant processes.
The opportunities for engagement of the NFP sector in a collaborative partnership approach include in the: 1. exploration stage of procurement/grant process, especially the development or changes to program Funding Guidelines 2. planning stage of the procurement/grant process 3. selection stage of the procurement/grant process and 4. ongoing contract management stage.
Best Practice Principles for Government and NFP Funding Relationships
Robust planning and design (RPD) 1. Robust planning and design supports efficient, effective, economical and ethical funding administration and is proportional to the scale and risk profile of the funding activity. 2. Public authorities and the NFP sector work together when planning and developing funding strategies to ensure outcomes are based on evidence of community need. 3. Planning is based on a rationale for the funding activity, and defines the expected outcomes and measures of success. 4. Funding activity is designed to achieve value, accountability, probity and transparency.
Collaboration and partnership (CP) 1. Public authorities and the NFP sector work collaboratively and flexibly to achieve shared outcomes. 2. Wherever possible, public authorities need to choose methods that will promote open, transparent and equitable access to funds. 3. Where appropriate, public authorities offer longer term contracts (three years plus three years plus three years) to enable strong, ongoing relationships. 4. Positive working relationships are maintained through effective collaboration that supports the needs and interests of NFP organisations and funding recipient.
Proportionality (P) 1. Processes are as simple as practicable whilst still being robust and accountable. 2. Balance is maintained between managing the complexity of a funding activity and the risk for the NFP sector, recipients and the South Australian Government. 3. The volume, detail and frequency of reporting requirements are proportional to the risks involved and policy outcomes being sought.
An outcomes orientation (OO) 1. Outcomes are clearly defined and include quantitative, qualitative and milestone information that is realistic about what the funding is intended to achieve, both for beneficiaries and with regard to policy objectives. 2. Outcomes should be reviewed regularly and whenever changes are made to the funding activities.
Achieving value with relevant money (AV) 1. Government and the NFP sector work together to achieve value for the South Australian community. 2. Value is achieved by establishing ongoing, joint monitoring arrangements throughout the life of the funding arrangement. 3. Value considers both cost and non-cost factors and promotes proper use and management of public resources. 4. Value demands standardised, efficient and effective funding processes across government that do not impose burdensome requirements on the NFP sector.
Page | 6
Government and accountability (GA) 1. Clear governance and accountability is demonstrated for all aspects of the funding process (planning, selection/allocation and management) for both government and the NFP sector. 2. Staff involved in developing or managing funding activities have the necessary skills, knowledge and experience. 3. Good record keeping informs better decision making and compliance with accountability obligations. 4. Processes minimise red tape and duplication and ensure consistency across all public authorities. 5. Public authorities support contracts through ongoing communication, active contract management and performance monitoring commensurate with the risks involved.
Probity and transparency (PT) 1. Funding activities meet legislative and policy obligations. 2. Probity and transparency are achieved through funding decisions that are impartial, appropriately documented, publicly defensible and lawful. 3. Appropriate mechanisms are in place to identify and manage potential conflicts of interest for funding activities. 4. A transparent and systematic application and selection process enhances government, NFP sector and public confidence in the funding activity outcomes and contract administration processes.
Community development principles (CDP) 1. Public authorities consider the desired impact or change they are seeking to achieve within the community. 2. Funding activities are advanced only where the desired impact or change will improve outcomes for South Australia. 3. Where possible, and particularly in relation to health and community services, funding should reflect a community development approach which builds resilience in the community and the capacity to respond to change and crisis and empowers individuals in the process of development and service delivery.
The following guidance is provided to support program managers in applying the principles when planning, allocating or managing funding programs.
Stage 1: Exploration
Applicable DPC 044 Principles – RPD1, RPD2, RPD3, RPD4, CP1, CP2, OO1, GA1, GA2, CDP1, CDP2, CDP3.
The exploration stage occurs before any formal planning for the market approach commences, for example the Acquisition Plan. This is to ensure ample opportunity is provided to conduct the necessary research and consultation to feed into the program’s Funding Guidelines and market strategy. This stage of the process will focus on identifying and justifying the community need being addressed, and will set the foundation for later stages of the process.
During this stage of the process, Program Managers will begin drafting or reviewing Funding Guidelines, and determining the extent of consultation required, depending on the complexity and scale of the funding program.
Guidance for applying principles
All funding programs are to be considered for NFP sector input, unless there is a compelling reason to do otherwise, for example, all aspects of the funding program have been pre-determined by Ministerial direction. Page | 7
The State Procurement Board’s (SPB) Acquisition Planning Policy, states that public authorities and the NFP sector need to work together, wherever possible, when planning and developing procurement strategies to identify the community outcome, or the desired impact or change being sought, and to ensure outcomes are based on community need.
Ideally, Program Managers will make details available of upcoming funding programs approximately 12 months in advance (where possible) as part of the DHS Forward Procurement Plan, published on the SA Tenders and Contracts website.
Planning for funding programs should be proportional to the scale and risk profile of the funding activity. Robust planning for funding programs should utilise a range of inputs such as: • government policy; • evidence of community need (including relevant population data, government administrative datasets, reports, community and sector consultation); • relevant research evidence; • feedback from the NFP sector to identify opportunities for improvement and potential for innovation; • liaison with other funding organisations including different levels of governments; • departmental learning from managing the specific or similar funding programs; and • other material and inputs relevant to the specific funding program.
These inputs will inform: • rationale for funding activity; • the design of market approach or selection process; • the nature of funding activity; • service model development; • priority funding investments; • priority populations; • priority locations; • risk identification and management; • performance and evaluation measures; and • the design, implementation and monitoring of contracting arrangements.
Funding Guidelines
It is expected that all funding programs, where appropriate, will have Funding Guidelines that outline: • Purpose and rationale of funding; • Expected Outcomes; • Objectives; • Link to Government policy and legislation; • Key priorities; • Performance measures / measures of success; • Reporting requirements; • Any funding administration requirements.
The Funding Guidelines will reflect a community development approach and be aligned to the principles of DPC 044. Government funding programs are expected to act as a steward of the service system they fund and operate using a community development approach that monitors community need, builds community resilience and the sustainable capacity of the system to respond to change, especially changes in community need.
Page | 8
Expected outcomes should be articulated through the Funding Guidelines, contracts and performance measures. An outcome reporting framework such as Results Based Accountability (RBA) should be utilised when setting performance measures that reflect the expected outcomes.
Program Managers are encouraged to consult with the NFP sector on a number of areas, including the planning of future funding programs, the Funding Guidelines, and the process for funding allocation. The method and extent of consultation will be determined by the Program Manager and be proportional to the scale and risk profile of the funding activity.
The SPB’s Acquisition Planning Policy outlines that consultation/participation should occur with NFP sector on: • Evidence of community/client need; • Funding Guidelines for programs; • Developing and/or improving the design of procurement/grant processes including reducing administration and compliance costs of providers and government during planning, selection and management phases of funding programs; • Review of requirements set out in Service Agreements and any significant changes when extending terms; • Performance measures and data collection; • Identifying opportunities for improvement and potential for innovation (SA Better Customer Charter for Business); and • Significant changes in contract management.
Draft Funding Guidelines should be made available to the NFP sector for comment as early as possible. Similarly, consultation on the proposed market approach (including value, timelines and selection criteria) with the NFP sector should occur as early as possible, to allow for meaningful consultation to occur.
Prior to consulting, it is important that Program Managers determine which aspects of the funding activity are open for consultation, and which aspects are non-negotiable. For example, the NFP sector may be invited to provide input into the Funding Guidelines, however, the method for funding allocation may have been pre-determined by Ministerial direction, so input would not be sought on this aspect.
Program Managers are encouraged to refer to the IAP2 Public Participation Spectrum (attached) when determining the appropriate level of participation by the NFP sector. The nature of participation by the NFP sector is dependent on a judgement by Program Managers, aligned to the significance and complexity of the issue(s), and a risk and value assessment.
For all funding programs, informal discussions should occur with the sector on an ongoing basis, to ensure Program Managers are well informed on emerging trends and issues within the community.
The SPB Acquisition Planning Policy and Procurement Policy Framework provides further guidance, if required.
Stage 2: Planning
Applicable DPC 044 Principles – RPD1, RPD2, RPD3, RPD4, P1, P2, P3, OO1,AV1, AV2, AV3, AV4, CDP1, CDP2, CDP3
The planning stage of the process is where the Program Manager will work with stakeholders (including the Procurement and Grants Unit (PGU)) to develop the necessary documentation to enable an appropriate market approach.
Page | 9
During this stage of the process, Program Managers will contribute to the development of the Acquisition Plan (lead by PGU), tender documents (if required) and will finalise the Funding Guidelines for the program. As part of the Acquisition Plan, a risk assessment will be conducted, that will identify procurement specific risks and risks specific to delivering the program.
Guidance for applying principles:
The SPB’s Acquisition Planning Policy states:
When developing procurement strategies, the following community development principles need to be considered: • consideration of the desired impact or change being sought within the community • assessing procurements on their impact on improving social, cultural and/or economic outcomes for South Australia • a community development approach which builds resilience in the community and the capacity to respond to change and crisis and empowers individuals in the process of development and service delivery.
Consultation
Program Managers should seek agreement at an early stage from all Stakeholders (Procurement and Grants Unit, NFP sector etc) on their respective roles and responsibilities before, during and after the selection process. An analysis of stakeholders may be conducted, that will: • identify who needs to be involved and when • identify who will be impacted and when • identify issues associated with the grant/procurement process • provide an opportunity to learn from other people’s experiences and use this information to improve the quality of future outcomes.
As outlined above, the development of Funding Guidelines should include participation by the NFP sector, to the extent deemed appropriate by responsible Director (aided by consideration of the IAP2’s Public Participation Spectrum).
Additional time allowance will be required to undertake meaningful consultation with the NFP sector, therefore planning for Funding Programs should commence ideally approximately 18-24 months prior to the end of the current funding period.
Risk Identification and Management
As part of the Planning stage, a risk assessment should be undertaken by the Program Manager, in accordance with the SPB Risk Management Guideline, to identify the level of risk associated with the funding program. Care should be taken not to over-engineer processes in the pursuit of risk mitigation. Program Managers should continuously identify and manage emerging risks throughout the funding lifecycle.
When designing funding and reporting requirements Program Managers should consider proportionality of the risks involved and policy outcomes being sought. Risk assessment should consider: • Nature of funding (e.g. scope, complexity, quantum of funds, any co-funding arrangements); • Design of funding allocation process (e.g. new approach, timeframes); • Departmental capacity to administer funding (e.g. staff capabilities, resourcing, infrastructure requirements); • Implementation issues including communication with stakeholders, ongoing grant administration; Page | 10
• Nature of industry e.g. industry capabilities, experience and past history of providers; • Relationship between parties to the funding agreement; and • The nature of activities being funded e.g. number and range of activities, locations, nature of clients, relevant service standards.
The State Procurement Board’s Risk Management Guideline states that the level of analysis and detail required in the management of risk will vary depending on the value, complexity and scope of the procurement. The risk management process identifies, and plans for, the potential risks that impact on a project’s procurement objectives. Planning for risk needs to occur at the earliest stages of planning for a procurement project.
Potential risks that may impact on the achievement of the procurement objectives need to be identified, including specific funding program risks. In undertaking analysis of the risks, and in determining necessary treatments, Program Managers need to refer to the DHS Risk Management Policy & Framework. The Framework includes a list of potential sources of risk, and a Risk Assessment Matrix for determining the likelihood and consequence of risks.
When undertaking risk assessments, assistance can be sought from the DHS Risk Management Unit.
Funding programs should continuously identify and manage emerging risks throughout the funding lifecycle.
Contract Length
The SPB’s Acquisition Planning Policy provides the following guidance regarding determining the contract length for NFPs:
In order to provide greater certainty and improve sustainable service delivery, public authorities must establish contractual agreements of three years plus three years plus three years (3 + 3 + 3) for all NFP procurements longer than two years where appropriate (i.e. where risk is low and there are no linked funding arrangements with the Commonwealth Government).
The Policy further states:
The appropriateness of long-term contracts needs to be assessed on a case-by-case basis and needs to represent value for money, and be balanced against the potential for new suppliers, whilst also considering the potential to encourage innovation in service delivery and new service models.
The Policy outlines the following factors to consider in determining the duration of any possible contract extension period: • the likelihood of market change in the meantime; • the need to secure and demonstrate value for money; • the switching costs to change from the incumbent to another supplier; and • the costs of approaching the market.
Staff Training
All staff involved in process of planning, selection/allocation and management of funding programs should undertake relevant training through the State Procurement Board and through their Department.
Page | 11
Stage 3: Selection
Applicable DPC 044 Principles – P1, AV3, AV4, CDP1, CDP2, CDP3, GA1, GA2, GA3, GA4, PT1, PT2, PT3, PT4.
The selection stage of the process is where the Program Manager will work with PGU to select a suitable service provider to deliver a funding program. External assessors may also be involved in the selection process, and this will ideally be decided during the planning stage.
During this stage of the process, Program Managers may contribute to the evaluation of responses received to an open or selective market approach, or be involved in negotiating with one or more service providers on the delivery of a funding program.
Guidance for applying principles
Limiting the Number of Suppliers
The SPB’s Acquisition Planning Policy outlines that where a collective impact approach is operational in any given area (geographic or issue based) which addresses the purpose for which the funding has been made available, a contract can be negotiated with appropriate not-for-profit organisations if such negotiation is beneficial to the community.
The Policy provides further guidance regarding instances where it may be appropriate to limit the number of suppliers, and requires that Program Managers ensure that the relevant justification is documented and approved by the appropriate delegate.
Evaluation
Consideration should be given to having an evaluation team member from the NFP sector with relevant expertise to the funding program. The evaluation team member may be nominated by a relevant peak body, but should not have substantial ties to any of the potential respondents.
Standardised Approach
Funding programs will ensure they utilise the required across government standardised contracts and indexation processes.
Stage 4: Ongoing Management
Applicable DPC 044 Principles – CP1, CP4, GA1, GA2, GA3, GA4, GA5, P3, OO2, CDP3
The ongoing management stage of the process commences once the funding agreement is in place and concludes only once transition to a new service provider has occurred, or the funding agreement expires, whichever occurs last.
During this stage of the process, Program Managers will work with the NFP service provider to ensure the intended outcomes of the funding program are met. The Program Manager needs to be aware of the reporting requirements under the funding agreement, and the process for exercising any extension options including as part of the agreement.
Page | 12
Guidance for applying principles
Service providers are expected to deliver services using a community development approach that builds clients skills, resilience and capacity to respond to change. This will include consulting or co-designing with clients about emerging community need, service design, service delivery and evaluation.
Contract Management
The SPB Contract Management Policy defines contract management as the process of pro-actively managing a contractual relationship between a supplier and public authority, including addressing risks and disputes that arise, to achieve the agreed contractual outcomes.
Effective contract management: • supports the achievement of value for money outcomes by ensuring that all parties to the contract meet or exceed their obligations in line with the contract performance measures, timeframes and expected deliverables; • minimises the risks to the public authority, government and clients; • holds the supplier to account; • prevents misunderstandings about the contract scope; • promotes innovation and improvement in supplier performance; • assists in developing the capability of both the supplier and the public authority; and • assists with achieving the contract outcomes in a timely manner.
The Policy further outlines that positive working relationships need to be maintained through effective collaboration that supports the needs and interests of NFP organisations and funding recipients. Public authorities need to openly communicate with contracted NFP organisations and work collaboratively, respectfully and flexibly to achieve agreed outcomes.
The ongoing management of funding programs should feed back into the explorative stage, with a continuous open dialogue occurring between Program Managers and the NFP sector.
Renewing Contractual Arrangements
The SPB’s Acquisition Planning Policy states that when extending terms reviews need to be undertaken prior to each extension term to ensure: • there is a continuing need; • the service specifications, quality standards and contractual requirements are being met; • the contract is operating efficiently and effectively; and • there is active engagement to continuously improve and provide the best possible service to the community.
The Policy also requires that where there is funding certainty, a minimum of six months’ notice must be provided to not-for-profit organisations regarding whether long term contracts are to be renewed. Funding uncertainty exists where the public authority is dependent on state or Commonwealth government funding and the funding outcomes are not advised with sufficient lead time to enable six months’ notice to be provided to the not-for-profit sector.
Page | 13
Page | 14
Definition of Community Development
DPC044 requires that: • public authorities consider the desired impact or change they are seeking to achieve within the community. • funding activities are advanced only where the desired impact or change will improve outcomes for South Australia. • where possible, and particularly in relation to health and community services, funding should reflect a community development approach which builds resilience in the community and the capacity to respond to change and crisis and empowers individuals in the process of development and service delivery
What is Community Development?
The United Nations define Community Development as a process where community (1) members come together to take collective action and generate solutions to common problems, typically aiming to make their community more cohesive, resilient and/or prosperous.
How does this relate to DPC044?
When developing procurement strategies, the following should be considered: • aligning procurements with the desired impact or change being sought within the community • assessing procurements on their impact on social, cultural and/or economic outcomes for South Australia • prioritising procurements that o build the community’s resilience and capacity to respond to change and crisis o empowers individuals in the process of service development and delivery.
For funding programs this may involve, for example: • actively pursuing partnerships and collaborations with others, including through place-based initiatives such as Collective Impact • enabling service design and delivery to be shaped by the priorities and aspirations of clients, their families and communities. • aligning decision-making with an intent of building social capital (2), community capacity (3), resilience and adaptability. • using operational processes (service design, delivery and evaluation) that include co-design with clients/communities around their needs and priorities • monitoring community need and building the capacity of the system to respond to changes (including crises) within in the community • sharing data and other information to assist community-based and place-based action.
Definitions
(1) Community: Community can denote those who live in a specific region (communities of place), those who share certain characteristics e.g. cultural history, religious belief (communities of identity) and those who come together through shared interests or concerns (communities of interest) (Maguire & Cartwright, 2008) (2) Social Capital: Social Capital refers to the interpersonal relationships (including a shared sense of identity, a shared understanding, shared norms, shared values, trust, cooperation, and reciprocity) that enable communities to function well. There are different types of Social Capital. (3) Community Capacity: Community Capacity refers to the skills, abilities, resources and networks that enable communities to create new and take up existing opportunities. There are different approaches to Community Capacity Building.
Page | 15
Checklist for engaging the NFP sector
This checklist should be read in conjunction with the Department of the Premier and Cabinet’s (DPC's) guide titled Better Together: Principles of Engagement and the values and practices outlined by the International Association of Public Participation (IAP2), and the Reforming Democracy: Deciding, Designing and Delivery Together Policy.
Planning
✓ Have you conducted a risk assessment for your program to identify any critical factors that may be addressed as part of the consultation process? ✓ Have you determined who you will consult with? The most effective consultations are undertaken with a cross-section of providers & stakeholders, not just a few ‘dominant’ providers. ✓ Have you determined how you will consult? Will you consult with providers individually, conduct a survey or hold workshops? ✓ Have you determined what it is you will be consulting the sector on? Do you know why you are engaging? Have you determined the non-negotiables? It is important to be clear with those being consulted with on what you have the power to change. ✓ Have you determined what you already know? Ideally, you will build upon previous engagement activities, and be aware of current sentiment in the sector regarding the funding initiative. ✓ Who will run the engagement? Will you lead the discussion? How will outcomes be recorded and used?
Engaging
✓ For consultation to be meaningful, you need to engage with the sector early to secure buy-in. ✓ Care needs to be exercised to ensure that no provider has, or is perceived to have, information that provides them with an unfair advantage in a subsequent procurement process. ✓ Keep thorough records of your consultations to leave an audit trail. ✓ During your consultation, ask providers & stakeholders specific questions and provide guidance and context where possible – make your consultation relevant and engaging. ✓ Ensure your method of consulting is accessible for all providers or stakeholders who seek to contribute – i.e. consider allowing phone-ins for group discussions to ensure those in regional locations can participate, allow sufficient time for contributions to be made.
Next Steps
✓ Review the information you obtained as part of your consultation. How does this shape the funding guidelines, market approach or any other aspect of the process or agreement? ✓ Provide a report on the consultation to relevant managers, outlining any recommendations and seeking endorsement for actions required. ✓ Close the feedback loop. Let the sector know the outcome of your consultation process, i.e. what decisions were made? This will build trust with the sector and add legitimacy to future consultations. ✓ Include a summary of the consultation process you have conducted in the acquisition plan, including how it shaped funding guidelines, market approach or other aspects of the resulting agreement.
Page | 16
Case Study: Community Services Support Program
Exercising of available three-year extension option for the Community Services Support Program (first term 1 July 2015 - 30 June 2018)
• $10.5 million per annum • 40 service providers, 73 services, 12 State Government Regions
Six streams:
• Community Neighbourhood and Development • Facilitating and Supporting Community Hubs • Family Support and Early Intervention • Life Skills Development • Low Income Support Program • Youth Support and Development
Stage 1: Exploration
• External evaluators (Charles Darwin University) appointed to evaluate the program over a period of up to four years • Jan 2017 - planning commenced (18 months prior to contract expiry) • Feb 2017 – notice to service providers to set expectation for them to achieve Quality Framework accreditation within 12 months time • March 2017 - briefing to Minister outlining planned approach • April 2017 - letter to service providers from Executive Director advising of intention to extend the contract and the planned approach.
Stage 2: Planning
• May 2017 consultation with sector commenced including 8 Regional information sessions held across South Australia and an information session or 1:1 meeting with Peak Bodies • Service Provider risk assessment and service-level performance review undertaken for each service provider and service • Request for Information sent to all 73 services. Each service was asked to provide information on: o Their assessment of identified community needs o Their linkages to community assets/strengths o How they plan to align service provision to local collective impact initiative goals and/or how they plan to improve service provision to address identified areas of persistent disadvantage o and, any Intended improvements/refinements to the service model • Following this, 73 individual 1:1 meetings held with each service manager / service provider. As a result of these meetings, a number of future contract improvements were negotiated across the CSSP including: o Merging of Streams with similar service models and outcomes allowing for efficiencies o Clarity of Purpose Statements and Refinement of service models o Separation of services where two distinct services had been operating as one service, allowing for better transparency of funding and reporting Page | 17
o Better alignment to collective impact initiatives o Introduction of a data sharing requirement o Introduction of definition for budgeted administration costs o Introduction of administration limits for metropolitan services (up to 18%) and regional services (up to 22%) o Improved clarity on staff FTE, award and classification o Introduction of risk-based approach to contract management o Red tape reduction by way of reducing frequency of expenditure reporting based on risk o Introduction of a benchmark for # of clients per year o Greater focus on clients from areas of persistent disadvantage as per the ABS population health area data o Introduction of Targets for % of Aboriginal clients and % of Culturally and Linguistically Diverse/New Emerging Communities clients
In addition, there was amicable negotiation to discontinue three services for various reasons as follows: • Discontinuing of 1 service which will be superseded by another service provider through a different funding program from July 1 2018 • Discontinuing of 1 service which did not align well to the region nature of the program and reallocation of these funds to another service delivered by the same provider • Discontinuing of 1 service in line with new strategic direction of the service provider
Stage 3: Selection
• October 2017 - SPGC approval to extend agreements • Early November 2017 - new Service Agreements drafted and issued to Service Provider for feedback • Late November 2017 - new Service Agreements issued to Service Provider for signing • December 2017 - New Service Agreements executed by DHS delegate (6 months prior to contract expiry)
Stage 4: Ongoing Management
• Development of CSD Contract Management Guidelines for multi-year funding to guide in line with Stronger Together and SANFRAG principles • RBA Training and Mentoring provided free to Service Providers and delivered by Community Centres SA • Financial support toward ASES accreditation for Service Providers with total income less than $500k • Creation of an online reporting portal for RBA outcomes reporting Next steps will include: • Continue with evaluation of the program (external evaluators – Charles Darwin University) • Review of Funding Guidelines • Planning for next procurement process will commence • Tender likely to be released Jan-June 2020 (12-18 months out from contract expiry)
Page | 18
15
South Australian Not for Profit Rules and Guidelines SANFRAG Fact Sheet
The Department for the Premier and Cabinet Circular 044 -South Australian Funding Policy for the Not-For Profit Sector sets out the requirements under the Policy.
The South Australian Funding Policy (Policy) aims to support and strengthen collaborative partnerships between government and the NFP sector.
It provides a consistent approach to all aspects of funding, sets clear requirements for public authorities, and reduces the administrative burden on NFPs and maintains their independence.
It also ensures that we capture learning and evidence that can be used to continually improve outcomes for South Australian communities.
The Policy applies to: ongoing and one-off funding arrangements funding for services to the public authority directly or to a third party grants (that use a formal contractual agreement) regardless of dollar value.
It does not apply to funding arrangements with schools, universities and churches
What has changed….
Definition of a procurement: The purchase of services from NFP are generally considered a ‘procurement’ and not a grant. Therefore, the State Procurement Board procurement, acquisition, supplier selection and contract management policies apply.
The DHS Procurement Framework already requires the purchase of services and provision of grant funding to follow the State Procurement Board policies and guidelines. Therefore, there is no change to the procurement process, i.e. acquisition strategy and tender process.
The definitions of a procurement and grant are included in attachment 1. For assistance contact the Procurement and Grants Unit. PGU will make an assessment based on guidance from DTF.
Notice to the sector: A minimum 6-months’ notice should be provided to the supplier if the contract is to cease or be extended.
For instance, if you tender the services the selection of the supplier should be completed (and tenderers advised) at least 6-months prior to the current contract end date. Likewise, if an extension option is being exercised 6-months should be provided.
Indexation: DTF has agreed to set indexation to be paid each financial year for contracts longer than two years.
Exceptions:
services transitioning to the National Disability Insurance Scheme (NDIS)
services transitioning to the Commonwealth Government under aged care reform arrangements indexation arrangements negotiated as part of a competitive tender arrangement.
Further information can be found here.
Agreements: Standard agreements have been drafted by the Crown Solicitors Office, in consultation from DTF.
Current agreements will continue to be valid as will the Master Agreement. However, all new agreements will be drafted using the new agreements.
The new clauses in the agreement can’t be amended (including adding clauses) without approval from DTF. Please contact the Procurement and Grants Unit to discuss
If business units want current agreements transitioned early to the new standard agreements, please contact the Procurement and Grants Unit to discuss.
Contract terms (3+3+3): Long term contracts provide certainty to the sector; however, the appropriateness of long-term contracts needs to be assessed on a case-by-case basis.
Contracts need to: represent value for money be balanced against the potential for new suppliers consider the potential to encourage innovation in service delivery and new service models
3+3+3-year agreements still require robust review and scrutiny. Extension options are not guaranteed and should only be exercised if the contract still meets the need of the community/clients.
During the term of the contract the service model should be responsive to the needs of the clients and should be actively managed to ensure they deliver the right outcomes.
Payments in advance: 25% pre-payment is allowed unless other arrangements are approved by the Chief Executive. Business Units can continue to pay NFPs quarterly.
Industry Participation Policy The Industry Participation Policy must be adhered to for the purchases of goods/services from NFP. Generally, this will be the completion of an Economic Contribution Test.
Sector consultation and co-design: Business Units will need to increase their engagement with the NFP sector. Engagement could be: emerging community need future of funding programs funding guidelines market approach and funding allocation (procurement process) contract management innovation opportunities
The engagement should depend on the scale and risk profile of the funding activity. Not all aspects of the program or delivery model need to be co-designed with the sector. Program managers should decide what are non-negotiables before consultation begins.
Refer to the “SANFRAG Implementation Guideline” for further details on engagement and consultation processes with the sector.
Attachment xx provides an overview of a case study on implementing SNAFRAG principles.
For further assistance on engagement with the sector contact the DHS Community Services Division.
Attachment 1: Definitions of Procurement and Grant
Procurement: State Procurement Act a) the procurement of goods or services required by the authority for its operations, including (without limitation) the procurement of— (i) a supply of electricity, gas or any other form of energy; or (ii) intellectual property; or b) the management of goods of the authority, including (without limitation) the care, custody, storage, inspection, stocktaking or distribution of goods of the authority; or c) the management of the authority's contracts for services; or d) the disposal of goods surplus to the authority's requirements, but does not include operations excluded from this definition by the regulations Grants: Treasurers Instruction 15 (a) it constitutes expenditure by a public authority to assist or support a third party in the conduct of its undertaking; and (b) the benefits on account of that expenditure do not flow, or do not predominantly flow, to the public authority.
Grants as defined in Treasurer’s Instruction 15 are excluded from the definition of procurement operations via the State Procurement Act Contact DHS Procurement and Grants for more information
Attachment 2: Case Study Implementing the SANFRAG Principles
NFP Procurement Processes: Generally, the roles and responsibilities of the business unit and the Procurement and Grants Unit are as follows. The level of work for each part can depend on:
the nature of the program or service the business unit’s relationships with the sector risk level market analysis
Role of the Business Unit Role of the Procurement and Grants Unit • Planning new funding program • Review previous issues/contract • Review the requirements and previous • Risk analysis issues/contract • Advice on market analysis • Needs analysis • Acquisition Plan • Budget • Evaluation Strategy • Consultation • Advice on Market Approach • Market analysis • Market Documents • Risk analysis • Advice on evaluation criteria • Specification, outcomes, targets • Consideration of Industry Participation
• Essential elements for evaluation criteria Policy • Composition of evaluation panel • Managing the tender via SA Tenders and • Contract negotiations Contracts • Advice on contract details • Chairing the evaluation panel • Keeping Minister informed • Contract negotiations • Contract management • Purchase Recommendation • Contract development
Services to Aboriginal Youth (STAY) Service The STAY program has a focus on early intervention, providing at risk young Aboriginal people aged between 10 – 19 years with access to the services and guidance they need to:
achieve their goals strengthen their cultural and community connection build long-term resilience Through a platform that actively encourages partnerships and collaborations with the Aboriginal community (including Elders, Aboriginal leaders, services providers and other stakeholders), the service providers will support young people in the context of their family and community.
Planning Planning commenced in February 2018 (17 months prior to the expiry of contract contracts) Conducted a Needs Analysis:
Population indicators:
# of Aboriginal young people # young people leaving school early # young people not engaged in further education, training # young people unemployed at age 25 # single parent families
Youth Justice and Court data Requested information from suppliers Surveyed clients
Service Model Changes: Using information gathered areas were ranked by need, identifying:
two additional areas to service redistribution of funding refined target group
Roles: Business Unit responsible for each of the planning tasks Procurement and Grants Unit to be notified of planning stage. An Adviser will be allocated and provide a point of contact for the program manager.
Consultation Youth Forum held in Murray Bridge and Port Augusta (over 100 young people attended) Stakeholders engaged:
Department of the Prime Minister and Cabinet – consultation on outcomes and funding distribution Senior Aboriginal Advisers (DCP and DECD), Office of the Youth and Aboriginal Programs and Policy – Draft guidelines Program Specification: Informed by the consultation the program guidelines, outcomes and targets were developed
Roles: Business Unit responsible for each of the consultation tasks
Market Approach and Documentation
Market analysis – consideration of organizations in identified regions and Aboriginal Communities Develop evaluation criteria and scoring matrix using key elements of the specification:
Service model (program theory, evidence) Knowledge and experience Workforce Capability and capacity Connection to community Cultural responsiveness Risk assessment of the procurement process and service Consideration of the tender documents and response:
Use of plain English Construction of easy to understand questions Allowing presentations from organisations (if necessary) Composition of the evaluation team – subject matter experts (including representation by Aboriginal people)
Roles: Business Unit responsible for identifying key elements of the specification for the evaluation, service risk assessment, input into tender documents and approval documents and composition of the evaluation panel. Procurement and Grants Unit responsible for advice and finalization of the evaluation, tender and approval documents and tender process.
Contract Negotiate service delivery, outcomes, targets, assessment and data collection Develop contracts based on agreed service model and negotiated items
Roles: Business Unit responsible for negotiation positions, contract detail and active contract management. Procurement and Grants Unit responsible contract negotiations, contract development and contract management oversight.
16
Procurement and Grants Unit
Contract Management Handbook
Version: 1.2 January 2019
Table of Contents
CONTEXT ...... 4
PURPOSE AND APPLICATION ...... 4
DEFINITIONS ...... 5
1 BENEFITS OF EFFECTIVE CONTRACT MANAGEMENT ...... 7 2 REQUIREMENT TO APPOINT A CONTRACT MANAGER ...... 7 3 PGU HANDOVER TO BUSINESS UNIT CONTRACT MANAGER ...... 8 4 CONTRACT MANAGEMENT TOOLS AND ASSISTANCE ...... 10 5 KEY CONTRACT MANAGEMENT ROLES AND RESPONSIBILITIES ...... 10 5.1 Role of SPGC ...... 10 5.2 Contract Management Roles and Responsibilities matrix ...... 11 6 CONTRACT MANAGER GOVERNANCE RESPONSIBILITIES ...... 13 7 CONTRACT MANAGER TRANSACTIONAL RESPONSIBILITIES ...... 14 8 CONTRACT MANAGEMENT PLAN ...... 15 9 GOVERNANCE AND OVERSIGHT ...... 16 9.1 Schedule meetings of governance group ...... 16 10 IMPLEMENT THE CONTRACT ...... 16 10.1 Start‐Up tasks ...... 16 10.1.1 Transition to new contract with incumbent Supplier ...... 17 10.1.2 Service Continuity and Transition to new Supplier ...... 17 10.1.3 Transition out – incumbent supplier ...... 18 11 PAYMENTS ...... 18 12 RECORD KEEPING AND DOCUMENTATION ...... 20 13 MEASURE, MONITOR, ASSESS AND MANAGE SUPPLIER PERFORMANCE ...... 20 13.1 Performance Measures and Data Collection ...... 20 13.2 Results‐Based Accountability ...... 21 13.3 Contract Management Meetings ...... 21 13.4 Performance Monitoring ...... 22 13.5 Risk Management ...... 22 13.6 Stakeholder and User Feedback ...... 23 13.7 Performance Assessment and Management ...... 23 13.8 Abatements ...... 24 13.9 Management of performance issues ...... 24 14 CONTRACT MANAGEMENT REPORTS ...... 24 14.1 Timing of CMRs ...... 25 15 MANAGING FUNDING ACQUITTALS/BUDGET EXPENDITURE REPORTS ...... 25 16 MANAGING CONTRACTORS AND CONSULTANTS ...... 26 16.1 Active Management ...... 26 16.2 Setting Expectations ...... 26 16.3 Regular Meetings and Review ...... 26 16.4 Transfer and Training ...... 27 16.5 Handover ...... 27
Contract Management Handbook | Version 1.2 January 2019 2 17 DISPUTE RESOLUTION AND TERMINATIONS ...... 27 18 CONTRACT RENEWALS: NOT‐FOR‐PROFIT SECTOR ...... 28 19 CONTRACT EXTENSIONS ...... 28 19.1 Exercising a contract extension option ...... 28 19.2 Extension beyond extension options ...... 29 20 CONTRACT VARIATIONS ...... 29 20.1 Principles ...... 29 20.2 Nature of Contract Variations ...... 29 20.3 Approvals ...... 31 20.3.1 Procurement Approval ...... 31 20.3.2 Financial Approval ...... 33 20.4 Contract Documentation ‐ Legal Authorisation ...... 33 20.5 Novation ...... 33 20.6 Records Management ...... 34 20.7 Administrative notices ...... 34 20.8 Roles and Responsibilities ...... 34 21 PRICE VARIATIONS ...... 35 21.1 Information to support a price variation ...... 35 22 CONTRACT CLOSURE REPORT ...... 36 23 IS THERE A CONTRACT IN PLACE TO MEET MY NEEDS? ...... 36
APPENDIX 1 OVERVIEW OF KEY CONTRACT MANAGEMENT ACTIVITIES ...... 37
APPENDIX 2 CONTRACT MANAGEMENT CHECKLIST FOR CONTRACT MANAGERS – CONTRACTS BELOW $4,400,000 ...... 38
APPENDIX 3 CONTRACT MANAGEMENT REPORTING REQUIREMENTS ...... 41
APPENDIX 4 CONTRACT MANAGEMENT REPORT DEVELOPMENT AND ESCALATION PROCESS ...... 42
APPENDIX 5 CONTRACT MANAGEMENT POLICY, GUIDELINE, TEMPLATE AND INFORMATION SHEET LIST ..... 44
APPENDIX 6 EXAMPLES OF CONTRACT VARIATION IMPACT ASSESSMENT ...... 46
Contract Management Handbook | Version 1.2 January 2019 3 Context The State Procurement Board (SPB), established pursuant to the State Procurement Act 2004, is responsible for establishing policies and procedures relating to procurement and contract management across the SA public sector. The State Procurement Board has provided the DHS CE with procurement authority of $15 million (GST inclusive). The CE has further delegated this authority to the DHS Strategic Procurement and Grants Committee (SPGC). As part of its responsibilities, SPGC oversights all contract management activities across DHS. This Contract Management Handbook has been developed to assist Contract Managers across DHS meet their contract management responsibilities consistent with the requirements and expectations of the SPGC.
Under DHS Policy YCO/41, the Procurement and Grants Unit (PGU) within DHS is responsible for managing the procurement of goods and services over $110,000 (GST inclusive) and the provision of all grants, regardless of value, must be referred to PGU.
The SPB’s procurement policies and guidelines are based around a number of themes – Procurement Governance; Procurement Reporting; Government Requirements; Procurement Process; Supplier Complaints; and Not-for-Profit Sector Procurement. For each theme there are a number of SPB, DHS and other agency policies, Guidelines, Processes, Better Practice Handbooks, and templates.
This document “Contract Management Handbook” is focussed on the Contract Management component of the Procurement Process theme, taking into account relevant aspects of other framework themes where appropriate.
This Handbook should be read in conjunction with the SPB Contract Management Policy. Managing contracts with reference to this Handbook will facilitate compliance with these policy requirements.
Purpose and Application This Contract Management Handbook is intended to serve as a tool for Contract Managers. Contract Managers are encouraged to establish contract management procedures and tailored approaches which are consistent with relevant policies, using additional reference material in this Handbook.
Business Units (BUs) should establish their own operational/day-to-day processes and procedures and ensure that roles and responsibilities for managing the contract have been identified and understood by the relevant parties1.
The Handbook applies to grants and contracts for goods and services, including with the Not-for-Profit sector, of all values within DHS business units, LSA and SAHT contracts managed by SA Housing Authority.
1 Reference: SPB Contract Management Policy
Contract Management Handbook | Version 1.2 January 2019 4 Arrangements with the not-for-profit (NFP) sector can involve a procurement of goods or services or grants (provision of funds in the nature of giving/gifting or investing). Procurements with NFP entities are covered by State Procurement Act. Grant funding is not covered by the State Procurement Act. DHS follows standard procurement processes for the provision of funding to NFPs. Historically a number of funding arrangements to NFP entities have been referred to as grants whereas in fact the arrangement is more in the nature of a fee for service, or purchasing arrangement, that is intended to be captured by the requirements of the State Procurement Act. The CE has delegated the SPGC the authority to consider all grants above $500,000 (GST exclusive). Business should contact PGU at the earliest opportunity to identify the appropriate process to be followed in relation to arrangements with NFP entities.
While this Handbook covers contract management for all contracts, the effort allocated to contract management is dependent on the value, risk and complexity of the contract. The Contract Manager should use the DHS Risk Assessment template to assess the service and service provider risks. A tool is available to assist business units assess risks. This tool can be adapted to meet specific criteria relevant to a particular contract or business unit. Consider all of the risk items included in the risk assessment templates for inclusion in the tool.
Contracts that have minimal purchases, tasks or activities may not require or benefit from a formal contract management approach.
The owner of this Handbook is the Director Procurement and Grants. Any feedback or queries on the content should be directed to the Manager Procurement and Grants or the Manager Contract Operations using the PGU email [email protected]
Definitions Contract Management is the process of pro-actively managing a contractual relationship between a supplier (including NFP organisations) and the DHS contracting entity, including addressing risks and disputes that arise, to achieve the agreed contractual outcomes.
The SPB Contract Management Framework outlines the key processes and activities to be undertaken by public authorities to achieve effective contract management outcomes. The framework comprises both organisational requirements that apply more generally, and transactional requirements that apply to specific contracts.
The Contract Management Plan (CMP) is an internal document outlining key strategies, activities and tasks required for managing a contract including but not limited to roles and responsibilities, timelines, performance management and financial matters.
The Contract Manager is the person nominated to be responsible for the management of the day-to-day matters of a contract.
CMR contract management report
CCR contract closure report
Contract Management Handbook | Version 1.2 January 2019 5 FGMS Funding and Grants Management System IPP Industry Participation Policy issued by the SA Department of State Development
LSA Lifetime Support Agency
NFP - A Not-for-Profit is an organisation that does not operate for the profit, personal gain or other benefit of particular people. Not-for-Profit organisations consist of two broad categories; charities, and other organisations such as community service organisations, professional and business associations, sporting and recreational clubs and cultural and social societies.
PCMS Procurement and contract management system, the system used by DHS to (amongst other things) act as the contract register.
PGU is the Procurement and Grants Unit within DHS
RBA Results-based Accountability is a flexible planning, evaluation and continuous improvement tool that can be adapted to fit the unique needs and circumstances of different individuals, communities, programs and organisations.
SAHT South Australian Housing Trust
SAHA South Australian Housing Authority, includes previous Housing SA staff and Renewal SA staff undertaking contract management activities for SAHT
Significant Contract A contract above $4.4M, or above $550k which is assessed as medium- high risk in the acquisition plan or purchase recommendation, or as determined by SPGC
SPB State Procurement Board
SPGC is the DHS Strategic Procurement and Grants Committee
Supplier refers to the contracting party and may be a For-Profit or Not-for-Profit entity
Contract Management Handbook | Version 1.2 January 2019 6
1 Benefits of Effective Contract Management Contract management focuses on the activities to be undertaken after the contract has been awarded and executed, but it is strongly influenced by what has occurred in the previous stages of the procurement process: acquisition planning and supplier selection.
Effective contract management:
supports the achievement of value-for-money outcomes by ensuring that all parties to the contract meet or exceed their obligations in line with the contract performance measures, timeframes and expected deliverables minimises the risks to the DHS, government and clients holds the supplier to account prevents misunderstandings about the contract scope promotes innovation and improvement in supplier performance assists in developing the capability of both the supplier and the DHS assists with achieving the contract outcomes in a timely manner.
Contract Managers are encouraged to use their knowledge of the contract and DHS needs to continually influence change to yield improved outcomes for DHS and its clients. For example, identification of industry wide price reductions, or innovations/new products, or competitors providing items at lower cost, should be raised with suppliers to identify if there are opportunities to improve the contract terms for DHS. Contract Managers should engage with PGU for advice and guidance in the event of these potential improvement opportunities being identified.
PGU and many business units use PCMS to record and manage certain Contract Management activities. Business units not currently using PCMS (for example some business units using FGMS do not utilise PCMS) for contract management purposes are encouraged to utilise its functionality.
An overview of key contract management activities is provided as Appendix 1.
2 Requirement to appoint a Contract Manager For contracts valued at or above $4.4m and for Significant Contracts (refer Definition) an adequately resourced and skilled Contract Manager must be appointed2. Contract Managers appointed for contracts at or above $4.4m and significant contracts must have completed the SPB’s contract management training program (or similar) and undergo refresher training every three years3.
2 Reference: SPB Contract Management Policy 3 Reference: SPB Contract Management Policy
Contract Management Handbook | Version 1.2 January 2019 7 For all contracts, regardless of value, business units are to ensure roles and responsibilities for managing the contract have been identified and understood by the relevant party4.
PGU will generally seek to have the business unit identify the Contract Manager early in the procurement process to allow them to influence the final contract and develop the contract management plan prior to the contract being awarded. Complex or high risk contracts may require the appointment of a contract management team.
For across-DHS contracts the Contract Manager may be a PGU Officer, or an officer from an identified Business Unit e.g. Corporate Services. For contracts that are not across-DHS but have more than one business unit receiving services under the contract, the Contract Manager within the business unit accessing the majority of the services by value shall be deemed to be the “lead contract manager”, and this business unit shall be responsible for ensuring the appropriate coordination of contract management activities across the business units.
3 PGU Handover to Business Unit Contract Manager At the conclusion of a procurement process, PGU will confirm the business unit Contract Manager has been provided with access to all of the information and documents required to effectively perform the Contract management function. Refer to the contract handover to business unit checklist.
In many cases the Contract Manager will have been an important member of the procurement project team, or procurement process, and will have access to most if not all of the material required to undertake the CM role. PGU will meet with the CM to provide: details of any relevant aspect of the procurement process details of any matters that were negotiated and that may require special attention by the Contract Manager a copy of the final contract – this will generally be through providing the Contract Manager with access to the relevant objective folders a contract management report template (together with the schedule for provision of the reports) and advice as to any delegations approved by SPGC (eg for contract variations, extensions, price increases), which will also be recorded in PCMS a copy of the risk assessment (or risk management plan if completed) access to the Better Customer Charter for Business which outlines the South Australian Government’s commitment to being the best public service customer to suppliers. If not already provided, access to the successful supplier response/proposal together with notes of any outcomes from clarifications, presentations and negotiations that occurred with the supplier. While the executed agreement contains the final position agreed between the parties, the response and other information can be useful to the Contract Manager/business unit both during transition/implementation and ongoing management of the relationship and deliverables a range of other information as detailed in the handover checklist.
4 Reference: SPB Simple Procurement Policy and SPB Contract Management Policy
Contract Management Handbook | Version 1.2 January 2019 8 PGU will record the name of the Contract Manager in PCMS, the DHS contract register.
Contract Management Handbook | Version 1.2 January 2019 9
4 Contract Management tools and assistance PGU provides assistance to Business Unit Contract Managers by
Issuing this Handbook Maintaining relevant policies, procedures and templates Providing advice on contract management Resolving escalated contract issues Facilitating approvals required for contract extensions, price changes, novations and variations Managing the documentation process to formalise changes to the contract terms, conditions and schedules.
Appendix 5 provides a listing of relevant policies, guidelines and templates.
5 Key Contract Management Roles and Responsibilities 5.1 Role of SPGC The SPGC5, with assistance from the PGU, oversee procurement and grant funding operations, including contract management activities, across DHS, to: • ensure the use of best practice processes • ensure probity, accountability and transparency • provide for ethical and fair treatment of participants • manage agency interests in contractual arrangements • ensure a strategic approach • oversee the collection, analysis and distribution of information that will help develop strategy • implement effective risk management • develop policies and oversee their implementation.
5 Reference: Strategic Procurement and Grants Committee Terms of Reference
Contract Management Handbook | Version 1.2 January 2019 10
5.2 Contract Management Roles and Responsibilities matrix The key contract management activities, which are described in this Handbook, are:
Activity CM Handbook Responsibility* section number Appoint a Contract Manager 2 BU Contract Manager name placed in PCMS 3 PGU Contract Manager undertakes contract 2 CM management training Lead Contract Manager nominated for multi- 2 BU with guidance business unit contracts from PGU Develop a contract management plan 8 BU with guidance CMP to address responsibility for the review of from PGU contracts, business risk assessments, business continuity planning, correspondence and enquiries relating to the contract, operational requirements of the contract Approve a contract management plan 8 BU following endorsement from PGU Schedule initial and regular Governance 9 CM Committee and Contract Management Team meetings Contract start up and implementation activities 10 CM Establish records in FGMS/PCMS 10 CM/PGU in accordance with the FGMS Guideline Prepare contract management meeting agenda 13.3 CM Attend contract management meetings 13.3 CM Undertake specific tasks for managing 16 CM consultants and contractors Obtain and review performance data and monitor 13 CM performance measures Lead Contract Manager to obtain input from 2 CM other business unit users Certify invoices for payments (non FGMS 11 BU contracts) Process payments through FGMS (where 11 CM/PGU/Finance applicable) in accordance with the FGMS Guideline Review risk management plan 13.5 CM Manage disputes and non-performance 17, 13.8 CM with guidance For NFP contracts, manage acquittals and from PGU retrieve underspends 15 CM with guidance from Finance Document outcomes of meetings 12 CM Communicate with stakeholders 13.6 CM
Contract Management Handbook | Version 1.2 January 2019 11 Activity CM Handbook Responsibility* section number Report on contract performance 13 CM Prepare contract management reports 14 CM (with guidance from PGU for >$550k) Manage process of submission of CMRs to 14 PGU SPGC IPP reporting – 6 Monitor supplier obligations as per the CM contract. Report IPP outcomes to PGU CM Report to Department of State Development PGU on IPP outcomes Social Outcomes Reporting to PGU – CM ABE/ADE outcomes SME engagement Aboriginal employment Northern exemplar Seek approval for novations, variations, price 19,20,21 CM (with guidance adjustments and extensions to contract from PGU for Negotiate with supplier re price adjustments, >$550k) extensions, variations CM (with guidance from PGU for >$550k Prepare contract variation PGU documentation/exchange of letters for execution by supplier and Business Unit Approve price adjustments, contract extensions, 20.3 In accordance with and contract variations financial and procurement delegations and impact assessment Manage contract closure processes 22 CM Prepare contract closure reports 22 CM *BU = Business Unit PGU = Procurement and Grants Unit CM = Contract Manager
A spreadsheet (one for period and one for one-off contracts) is available for CMs to record various actions/tasks taken against contract management activities.
Contract Management Handbook | Version 1.2 January 2019 12
6 Contract Manager Governance Responsibilities Contract Managers must ensure6:
privacy and confidentiality - all commercial information provided to the CM is to be treated as confidential. Confidential government, user, client and supplier information is to be handled appropriately throughout the contract management process in accordance with confidentiality and privacy clauses contained in the contract. probity, ethical behaviour, accountability and transparency – The SA Government’s Better Customer Charter requires that public authorities are honest and fair in commercial dealings, and behave in accordance with the highest ethical standards stakeholder management - manage the needs and expectations of internal and external stakeholders (end-users, customers or clients, managers, sponsors, suppliers, technical or functional experts or advisers) and determine the type and frequency of interaction and communication with stakeholders which will vary according to the nature of the goods and services, value, risk and complexity of the contract. Communicate with users, stakeholders and clients on the key aspects of the contract and the supplier, as relevant management of Industry Participation Policy requirements - o monitor IPP Plan commitments o review regular reports from suppliers o report on IPP outcomes to PGU annually. (PGU prepares reports to the Department of State Development.)
Further guidance and detail are available in the South Australian Industry Participation Policy published by the Office of the Industry Advocate (OIA).
Contract Managers should:
provide reports to PGU on social outcomes or targets (if applicable) - o Engagement with Aboriginal Business Enterprises or Disability Business Enterprises o Engagement of small to medium enterprises under the contract o Aboriginal employment o Northern Exemplar maintain a written record of all decisions, contract management meeting outcomes, key discussions with suppliers and significant contract management issues including approvals and the rationale for decisions made undertake supplier audits and access supplier information where necessary undertaking site visits to verify contract undertakings and outcomes
6 Reference: SPB Contract Management Policy and SA Industry Participation Policy
Contract Management Handbook | Version 1.2 January 2019 13 establish processes for identifying, declaring and managing conflicts of interest to avoid the potential for and the perception of unethical behaviour and conflict of interest use the DHS gift register adhere to the Government’s Code of Ethics for the South Australian Public Sector achieve the contract outcomes maintain a professional and respectful working relationship with the supplier Further information is available in the SPB’s Probity and Ethical Procurement Guideline
7 Contract Manager Transactional Responsibilities The Contract Manager should: o understand the contract requirements and obligation o be involved in the procurement processes (where possible) o identify opportunities for realising additional value o manage and address contract risks7 o maintain effective relationships with the supplier and schedule regular contract management meetings.
Effective contract management includes:
o working collaboratively, respectfully and flexibly with the supplier to achieve agreed outcomes. An effective professional supplier relationship underpins achieving contract outcomes, with the Contract Manager being the key link between DHS and the supplier. An ineffective or difficult relationship may result in the supplier taking a more adversarial approach or being less willing to provide quality services. o maintaining positive working relationships with Not-for-Profit suppliers through effective collaboration that supports the needs and interests of NFP organisations and funding recipients. Communicate openly with NFP organisations and work collaboratively, respectfully and flexibly to achieve agreed outcomes. o developing and maintain a professional relationship through appropriate communications. . set up regular meetings with the supplier to review progress and discuss opportunities for improvement . establish a system to monitor milestones and key deliverables . ensure the flow of relevant information at critical stages of the contract . ensure all formal communication in relation to the contract is channelled through the Contract Manager. o scheduling contract management meetings with the supplier to monitor contract activities and to discuss improvement opportunities. The frequency of contract management meetings varies. For example, the majority of medium to longer
7 SPB Risk Management Guideline
Contract Management Handbook | Version 1.2 January 2019 14 term contracts may require contract management meetings on a quarterly basis, with short term contracts (less than six months) or higher risk contracts requiring meetings on a more regular basis. Prepare a formal agenda to guide the discussion towards improving contract outcomes. Document key contract management meeting outcomes. o providing timely assessment of the supplier’s performance, particularly if they are failing to met their KPIs or performance does not meet expectations. o ensuring that performance indicators are met and provide contract management and contract closure reports as required by the DHS Contract Management Guideline o for NFP contracts managing expenditure acquittals and recovering surplus funds o ensuring the supplier is charging in accordance with the contract schedule of rates o ensuring suppliers do not apply a price increase without approval o certifying payments to the supplier for goods/services delivered (where applicable) o ensuring payments are made in accordance with Treasurer’s Instruction 11 – Payment of Creditors’ Accounts o processing invoices for payment within 30 days of the suppliers invoice being received by DHS unless stipulated otherwise in a contract. o processing payments through FGMS (where applicable) in accordance with the FGMS Guideline o addressing problems and conflicts that may arise o assessing and (where required) seek approval for any variations/extensions/novations to the contract o advising PGU of any change in personnel acting as Contract Manager; PGU will update PCMS.
8 Contract Management Plan The DHS Contract Management Guideline requires that all contracts at or above $550,000 (GST incl) (except for contracts that are of a one-off nature and have minimal management tasks), and for other contracts determined by SPGC to be significant, require a contract management plan (CMP). The CMP:
o is an internal (DHS) document for documenting the key strategies, activities and tasks o summarises meeting procedures, timelines and KPIs is required to manage the contract provides a systematic and accountable method to ensure that both parties fulfil their contractual obligations is used to review the performance of the contract and monitor the achievement of the contract outcomes is valuable for new staff assuming the Contract Manager role, as it provides critical information required to enable a smooth transition from one Contract Manager to another.
Contract Management Handbook | Version 1.2 January 2019 15 PGU will provide the Contract Manager with a CMP template for the Contract Manager who is able to tailor it for specific business unit requirements. Refer to the information sheet Complete the CMP template.
Where a procurement process has been undertaken using a single acquisition plan and purchase recommendation covering a “program” or “service” that may involve multiple contracts with multiple providers, a single Contract Management Plan may be used, providing that all high risks that relate to a specific/single service and/or provider are addressed.
Once the CMP has been endorsed by PGU and approved by the BU Executive, the Contract Manager should provide the final CMP to PGU, for storage in Objective.
The simple contract management plan template may be used for contracts valued up to $4.4m incl GST. A contract management checklist is provided as Appendix 2 to this Handbook as a useful tool for managing contracts as a companion tool to the Simple CMP.
9 Governance and Oversight An oversight or governance committee can be established to oversee contracts of high value, risk or complexity. Membership may comprise senior staff, users and business unit representatives, as well as the Contract Manager. DHS’s SPGC monitors contract management for contracts valued above $550,000, or high risk contracts of any value, through receiving reports as outlined in the DHS Contract Management Guideline.
9.1 Schedule meetings of governance group The Contract Manager should ensure that meetings for the relevant contract management oversight group are scheduled as required by the Contract Management Plan.
10 Implement the Contract Works or services, or purchases of goods, should not commence until the contract has been fully executed. There may otherwise be a lack of clarity as to the respective rights and obligations of the parties, which could lead to disputes and /or risks being assumed that may not have occurred under the final approved and executed version of the contract.
10.1 Start-Up tasks To implement the contract, the Contract Manager should:
At all times follow the contract management plan where applicable. Identify and undertake contract start-up tasks including: o Convening the initial contract management meeting with suppliers, DHS representatives and other relevant stakeholders to detail all parties’ obligations. o Confirm contract risks and strategies to manage risks. o Assist supplier by arranging site inductions. o Finalise record keeping protocols for the contract.
Contract Management Handbook | Version 1.2 January 2019 16 o Obtain confirmation from supplier that screening requirements have been met. Communicate the existence of the contract to users and stakeholders and the requirements they must fulfil. It is important that all key customer groups are informed of the contract. For whole-of-DHS contracts for consumable items such as stationery or printing services an implementation strategy may need to be developed by the Contract Manager with an implementation plan on how to maximise usage of the contract. Ensure that the ordering processes are appropriately set up. Provide new supplier/vendor details to Shared Services SA (non FGMS contracts). This enables payments to be processed via Basware. Ensure a system for timely payments is in place and users are aware of the process for certifying and approving invoices for payment (non FGMS contracts) With PGU and Finance, ensure FGMS payment arrangements and processes are established and implemented in accordance with the FGMS Guideline. Ensure record keeping protocols for contract management are developed, implemented and understood by all participants. This includes electronic record keeping in PCMS and/or FGMS and Objective.
The implementation period commences at the execution of the contract and in some cases, can last up to three to six months before ongoing contract management and monitoring activities take precedence. The Contract Manager should ensure that the new contract is quickly established and operational to deliver the required goods or services to clients and end-users, communicate the existence of the contract to users and stakeholders, and describe what goods and services the contract will provide, who is responsible for the key contract tasks and how to utilise the contract.
10.1.1 Transition to new contract with incumbent Supplier It is important to ensure that all provisions of a new contract with an incumbent supplier/provider are honoured and implemented. A re-engagement of an incumbent provider should not be assumed to mean “business as usual”. Contract Managers should be aware of all changes to terms, conditions, schedules, deliverables, reporting, payment arrangements and ensure these are enforced both with the supplier and with DHS staff through operational procedures associated with the contract. It is appropriate to undertake the “start-up” tasks outlined in section 10.1 even where the contract is with an incumbent supplier.
10.1.2 Service Continuity and Transition to new Supplier The Contract Manager must plan for and implement the transition from one supplier to another or from one contract to another to ensure a smooth handover and the continuity of service provision. The transition period can entail high risks and stress on both parties.
A transition plan and/or the establishment of a transition team may be warranted to manage the transition and is useful where there are:
complex or essential service contracts in place
Contract Management Handbook | Version 1.2 January 2019 17 significant assets or intellectual property that will become the property of the public authority or new supplier security or safety issues.
A transition plan identifies and addresses risks allowing the transition to occur with minimal disruption to existing services and for improving systems and procedures.
The new supplier may also have several issues to consider including:
outstanding warranty matters obtaining previous contractual records and information obtaining access to premises and assets understanding any areas in which the previous supplier did not perform adequately.
Refer to the Contract Transition meeting and minute template with guidance.
10.1.3 Transition out – incumbent supplier The Contract Manager must8 ensure various matters are considered at the end of the contract including whether: all outstanding contract actions have been completed, including deliveries required documents, equipment or other goods have been returned, and documents stored in accordance with DHS Records Management protocols all payments and financial obligations have been completed and reconciled there are any outstanding reports or disputes any warranty issues are still outstanding there are any legal rights and obligations on the parties that may survive after the contract has closed access arrangements have been terminated or revoked, including security passes.
A contract closure report may also be required – refer section 22.
11 Payments The Contract Manager is responsible for: Setting up processes to allow orders off the contract. Providing new supplier/vendor details to Shared Services SA. This enables payments to be processed via Basware if applicable (i.e. for non FGMS agreements). Scheduling payments in FGMS where relevant. Establishing a process to confirm that the supplier is charging the correct contracted rates. Establishing a system for timely payments and making users aware of the process for certifying and approving invoices for payment (non FGMS agreements). Establish o Who will review and code the invoice, who will approve the invoice? o What data will the reviewer and approver require to enable them to check the invoice and how will it be available to them?
8 Reference: Note that this is a mandatory requirement under the SPB Contract Management Policy for contracts >$4.4million and significant contracts and a recommended action for all other contracts.
Contract Management Handbook | Version 1.2 January 2019 18 o Who will monitor that invoices have been received in line with contract requirements, and have been paid on time to meet Treasurer’s Instruction 11 Payment of Creditors’ Accounts requirements? o Do reviewers and approvers require Basware training? o Does the supplier know who to forward invoices to, and who to provide any supporting information to? o What is the process in the event there is a dispute in relation to an invoice or supporting data? Reviewing and monitoring payments made to the supplier o Are payments being processed in accordance with appropriate timeframes? o Are payments/expenditure in line with the estimated expenditure approved as part of the purchase recommendation and financial authorisation? If payments are in excess of the expected amount on a monitoring period basis (eg monthly, quarterly, annually), and this may lead to the approved value of the contract being exceeded, taking appropriate remedial action. This can range from restricting purchases under the contract (i.e. demand management) to seeking an approval of a variation by the procurement delegate and the financial delegate to ensure compliance with delegations. o PGU will assist Contract Managers to obtain the required procurement approval (e.g. to vary the terms of the procurement delegate’s approval and/or a contract variation if required). Contract Managers must9 obtain the relevant Financial Delegate’s approval for the expenditure increase.
9 Reference: Treasurer’s Instruction 8 Financial Authorisations
Contract Management Handbook | Version 1.2 January 2019 19
12 Record Keeping and Documentation The Contract Manager must10 ensure that records are maintained within PCMS (and/or FGMS and/or Riskman) and documents are stored in Objective in relation to:
risk monitoring and assessments issues register the original contract and contract management plan minutes of contract management meetings significant communications with the supplier where applicable, records of payments performance reports, assessments, feedback or non-compliance issues variations or extensions to the contract legal or technical advice received.
13 Measure, Monitor, Assess and Manage Supplier Performance Contract performance management must be undertaken throughout the life of the contract. It includes performance measurement, monitoring, assessment and management. For areas using Results-based accountability (RBA), performance assessment will be undertaken within that context and framework.
13.1 Performance Measures and Data Collection Performance measures, such as Key Performance Indicators (KPIs) specified in the contract, are the key criteria against which contract performance is to be assessed. These should link to the original procurement objectives and are generally documented in the contract.
Performance measures are outcome focussed, able to be measured objectively, agreed and understood by all parties and reflect key aspects of the contract.
Premier and Cabinet Circular 44 Funding Policy for the Not-for-Profit Sector advises that public authorities and the NFP sector work together when planning and developing funding strategies to ensure outcomes are based on evidence of community need, and that planning is based on a rationale for the funding activity, and defines the expected outcomes and measures of success. Therefore, Business Units must work with the NFP entity/ies to develop the performance measures11.
The Contract Manager should be aware of all of the performance measures that are detailed in the contract, and the processes that have been agreed to in the event that requirements are not met (including for example any abatements that have been provided for).
10 Reference: State Records Act 1997 11 Reference: SPB Contract Management Policy and DPC044 South Australian Funding Policy for the Not for Profit Sector
Contract Management Handbook | Version 1.2 January 2019 20 Even where performance measures are not specifically included in a contract, performance against the general contract requirements should be monitored.
Systems for collecting relevant data are best established from the commencement of the contract, with the data discussed with all parties at the regular contract management meetings. Qualitative data may also be collected, for example, through client and user surveys. Examples of performance measures include:
targets to be met outcomes to be met key steps or milestones achieving invoicing deadlines client feedback or customer service metrics technical considerations quality, safety, environmental or social outcomes.
In some cases, (for example, in contracts relating to complex or highly technical matters), an independent assessment or periodic audit can determine whether the performance measures have been met.
KPIs should be relevant and meaningful and link to the original procurement or grant objectives as documented in the contract. If a supplier is meeting the KPIs yet is not delivering services to the satisfaction of the relevant stakeholders, this may indicate the KPIs are not appropriate. Refer to the DHS Specification Writing Guideline for further information.
13.2 Results-Based Accountability Where the RBA framework has been implemented in relation to a service or program, performance measurement will be an integral part of the program evaluation process. RBA is a flexible planning, evaluation and continuous improvement tool that can be adapted to fit the unique needs and circumstances of different individuals, communities, programs and organisations. As a framework, RBA also has the capacity to enhance organisational outcomes through:
Creating measurable improvements for clients and communities Assisting organisations to gather evidence during practice Enabling organisations to demonstrate the outcomes they have achieved to DHS, other funding bodies (where applicable) and the community. Community Sector Development, a team within Policy and Community Development, has lead responsibility for implementing RBA within the department.
13.3 Contract Management Meetings The Contract Manager should
schedule the regular contract managements meetings with the supplier, in accordance with the contract management plan requirements. Prepare the contract management meeting agenda
Contract Management Handbook | Version 1.2 January 2019 21 Attend the contract management meetings Document the outcomes of the meeting. Refer to the Contract Management meeting minute template Store the records of the meeting in the relevant Objective folder.
Regularly scheduled contract management and review meetings with the supplier to monitor contract activities are important to monitor contract performance. The frequency of these meetings will be detailed in the contract and should occur no less than quarterly for high value/high complex long term contracts and may occur less frequently for other contracts, or more frequently for shorter term contracts (e.g. for a 6 month contract it may be appropriate to have contract management meetings monthly).
13.4 Performance Monitoring Performance monitoring focuses on the collecting and analysis of information to provide assurance that the supplier will achieve contract milestones and outcomes in line with agreed timelines and includes the following:
capturing and recording of contract performance monitoring data. provision of progress reports by the supplier, progress review meetings, contract reviews, supplier visits, independent technical reviews, contract audits and financial examinations. looking for the warning signs of potential supplier problems or slippage. Any formal or informal meeting or conversation with a supplier should be used to question progress and raise issues early. recording all contract performance monitoring activities including copies of supplier reports and records of discussions as these may form the basis of any future action involving the supplier. monitoring compliance with Industry Participation Plan commitments (where applicable) including regular reporting.
Contract performance monitoring should not be excessive and be should be related to the value and complexity of the contract to identify essential information required to measure and assess supplier performance.
13.5 Risk Management Managing risk is central to effective contract management and involves developing and monitoring relevant risk minimisation strategies, including those related to contract risks previously identified in the acquisition planning and supplier selection phases as well as risks relating to the supplier identified in the contract management plan. Further information on managing contract risks and examples are provided in the SPB’s Risk Management Guideline.
The Contract Manager should complete risk assessments for the service and for the supplier and regularly review the risk assessment and risk management plan, and ensure all risks are
Contract Management Handbook | Version 1.2 January 2019 22 assigned to an appropriate risk owner12. Have any additional risks emerged? Are insurance and indemnity provisions within the contract still appropriate? Are there additional risk mitigation strategies required?
A risk assessment tool containing a structured approach to calculating risk is available to assist in this assessment.
13.6 Stakeholder and User Feedback For contracts relating to goods and/or services provided directly to DHS staff, the Contract Manager should obtain feedback from key stakeholders throughout the life of the contract on whether the quality and level of services they are receiving is in line with the contract requirements. Feedback can be collected via surveys, incident log books, questionnaires, telephone or face-to-face enquiries.
Feedback is best considered with other performance data to provide a more comprehensive view. By itself, feedback from one stakeholder may not represent the total or majority stakeholder experience as can skew towards the negative as more unsatisfied stakeholders are likely to log an issue.
Stakeholder and end-user feedback is particularly important on large complex service contracts.
For programs and services using the RBA framework, feedback from end-user/clients will be provided under the RBA reporting mechanisms, likely from the service provider.
For contracts providing services to end-users/clients, in the absence of RBA mechanisms, the CM should ensure feedback is obtained to enable a validation of service delivery.
The Contract Manager should inform stakeholders of any relevant outcomes from the contract monitoring and /or contract management meetings. Appropriate communication strategies to advise end-users/clients should be implemented in the event there are changes agreed that are relevant for the client base.
13.7 Performance Assessment and Management Performance assessment is the evaluation of supplier performance measures on individual contracts using performance monitoring information and other available data. Individual supplier performance is compared against performance benchmarks for the contract.
Areas to be performance assessed should be in-line with performance measures defined in the contract. This assessment can include:
Delivery Quality Management
12 Reference DHS Risk Management Framework
Contract Management Handbook | Version 1.2 January 2019 23 Relationship management Stakeholder (DHS staff) satisfaction Client/end-user satisfaction.
Performance standards should be set for each metric and performance recorded.
The results of contract performance assessment form the basis for follow-up with the supplier which can result in an agreed recovery plan, contract amendment, remedial action and/or legal recourse.
Where the supplier’s performance is found to be inadequate, the Contract Manager should discuss the issue with the supplier and agree the remedial actions. These discussions are to be documented and the outcomes monitored at contract management meetings.
13.8 Abatements Generally speaking, an abatement is a reduction, a decrease, or a diminution. Contract Managers need to be aware of a right of abatement that exists in a contract. This right would exist in the form of a contract clause in the contract which gives DHS the right to reduce, decrease, suspend or cease payments due under a contract in specific circumstances. Where such a clause exists in the contract, Contract Managers should apply abatements promptly in accordance with the relevant contract where abatable contract performance failures occur. Contract Managers must not delay the application of abatement or enter into extra contractual arrangements in lieu of abatement.
13.9 Management of performance issues PGU is available to advise and assist with any contract performance issue. Business Units and Contract Managers are encouraged to engage with PGU at [email protected] at the earliest opportunity in the event an emerging issue is identified. PGU will be able to advise on strategies and/or procedural requirements in relation to the management of any issues.
14 Contract Management Reports DHS’s Contract Management Guideline outlines the requirement for contract management reports (CMR). PGU staff will work with the business unit to develop a tailored CMR report or Simple CMR from the standard template. Refer to the information sheet How to complete the CMR for guidance. Where CMRs are required to be forwarded to SPGC, PGU will manage the process.
Three CMR templates are available:
Simple CMR for contracts valued up to $4.4m including GST CMR for contracts and panel arrangements valued at and above $4.4m incl GST Program CMRs for programs/services involving multiple suppliers which were approved as part of a single procurement process (acquisition plan) valued at or above $550k incl GST.
Contract Management Handbook | Version 1.2 January 2019 24 PGU will advise the business unit of the most relevant CMR template at the end of a procurement process.
CMRs are also the mechanism for obtaining delegate approval of price adjustments, term extensions, and other contract variations (refer sections 19-21).
Business Units/Contract Managers are able to tailor the CMR template to meet the particular needs of the contract/issue. Attachments can be used rather than the table format in the sections to provide relevant information in the format that is appropriate for the specific arrangements and circumstances where this will provide information in a more useful format for the delegate.
Where a contract valued above $550k is utilised by more than one business unit, PGU will liaise with the individual business units to advise the CMR content required from each unit. PGU will consolidate information into a single report for SPGC.
A Business Unit representative is encouraged to be available to attend SPGC meetings when their CMRs are being considered, to assist with addressing SPGC queries.
PGU endeavours to advise BUs of SPGC decisions in a timely manner. Decisions are also recorded in PCMS. BUs are encouraged to pro-actively contact PGU for advice of outcomes the day after the SPGC meeting.
14.1 Timing of CMRs CMRs are required based on 6-monthly or annual reporting periods as outlined in Appendix 3, and are generally based on the commencement date of the contract. PGU will confirm with the Contract Manager at handover the reporting cycle and due dates for the CMRs.
Appendix 4 details the CMR development and escalation process. Where CMRs are overdue relevant officers will receive an email advice of the escalation reports being prepared by PGU.
CMs should consider any issues that are likely to arise in the period following the CMR and plan to seek the delegate’s approval of variations, price adjustments and extensions in a timely manner to coincide with scheduled CMRs wherever possible.
In the event there is a need to seek the delegate’s approval of a matter outside of the scheduled CMR reporting timeline, CMs should liaise with PGU to determine whether a CMR report can be brought forward, deferred or whether the most recent CMR report can be used as an attachment to a memo with only the specific item being requested forming the basis of the new submission.
15 Managing Funding Acquittals/Budget Expenditure Reports The Acquittals Process must be managed in accordance with the Unexpended Grant Money Policy (FIN201) and associated procedures.
Contract Management Handbook | Version 1.2 January 2019 25 16 Managing Contractors and Consultants In addition to the contract management requirements outlined in this document, there are some specific considerations required in the management of contractors and consultants.
Contractors may be appointed as part of a contract for the supply of goods and services, supply of services or under a consultancy services agreement. A contractor may be retained to perform defined tasks or to provide more general services and advice to the Department. During the engagement the contractor may develop procedures, systems and processes, or may collect, create or collate information important for the Department to retain and use.
A person managing (the manager) a contractor should take appropriate steps to ensure the contractor effectively documents and communicates processes, procedures, and other information. This is to ensure valuable institutional knowledge gained is transferred to, and retained by, DHS.
If the contract is subject to a Contract Management Plan, protection of information procedures should be incorporated into that planning process.
16.1 Active Management Transfer of institutional knowledge should not just occur at the end of the contract term and handover. If an early contractual relationship termination occurs, it should be possible for the manager, other personnel or another contractor to seamlessly continue with the work that had been undertaken by the contractor prior to termination.
Consequently, the manager should actively manage this. This is particularly important in circumstances where the specific deliverables are not well defined in the contract documentation.
16.2 Setting Expectations At the beginning of the contractual relationship the manager should clearly explain what information, documents and other deliverables are to be produced and how. It is critical the contractor documents any systems, processes and procedures that he/she is developing and has developed.
The manager shall ensure the contractor understands information storage systems, both electronic and paper-based. Further, the manager should regularly check that the processes, procedures, and other information are stored in the appropriate place, in the agreed manner, and are readily accessible.
16.3 Regular Meetings and Review It is important that the manager and the contractor meet regularly to review progress, check that documentation is clear, comprehensive and accessible, and that the expectations of both parties are being met.
Meeting frequency will vary according to the nature of the assignments and if applicable the requirements of the contract management plan. However, meetings need to be sufficiently
Contract Management Handbook | Version 1.2 January 2019 26 frequent to ensure that there is no risk of institutional knowledge not being captured or retained by DHS.
16.4 Transfer and Training In many cases the contractor will work closely with, and in some circumstances, train DHS personnel other than the Contract Manager.
The Contract Manager will ensure relevant personnel receive all necessary training to enable them to access, use and further develop systems, processes, procedures and documents produced by the contractor during the contract.
The Contract Manager will regularly check with the contractor and relevant personnel to ensure that institutional knowledge has been transferred.
16.5 Handover At the end of the contract term the Contract Manager and the contractor should meet to review the contract, expectations and deliverables and ensure all handover activities have been completed. Use the contract closure checklist.
It should be assumed that the contractor cannot be recalled to further explain or locate any systems, processes, procedures and/or documents.
17 Dispute Resolution and Terminations Dispute resolution processes are usually outlined in the contract including mechanisms for resolving formal disputes such as negotiation, arbitration, mediation and litigation.
Disputes often relate to definitions of deliverables or performance measures, disagreements over requirements, delivery schedules, price changes, additional tasks, contract scope, payment schedules and complaints by third parties. The Contract Manager must13 inform the supplier of any problems in writing and provide the supplier with an opportunity to respond. Good contract management can prevent issues from reaching the formal dispute stage.
Formal disputes are to be avoided where possible as they can affect the goods or services provided and undermine the relationship. The Contract Manager should obtain advice from Manager Contract Operations [email protected] should concerns emerge, remedial action is not available or effective, agreed actions are not being implemented, or any other issue arises whereby the Contract Manager needs advice on management strategies and options. Where appropriate, PGU will engage the DHS Legal Services unit or the Crown Solicitor’s Office before formal action is taken in such disputes.
Termination and legal action are only to be considered as a last resort after all reasonable attempts to resolve the issue have been made.
13 Reference: SPB Contract Management Policy
Contract Management Handbook | Version 1.2 January 2019 27 18 Contract Renewals: Not-for-Profit sector The SPB Contract Management Policy requires that where there is funding certainty, the Contract Manager must14 provide a minimum of six months’ notice to NFP organisations regarding whether long term contracts are to be renewed. This notice will assist to prevent unnecessary loss of staff and reduce the impact on individuals who rely on these services.
Funding uncertainty exists where the public authority is dependent on state or Commonwealth government funding and the funding outcomes are not advised with sufficient lead time to enable six months’ notice to be provided to the NFP sector.
Other than if exercising an extension option, a renewal will require either a contract variation process or a new procurement process. The timelines for these processes should be provided for in planning, and the Contract Manager should engage with the PGU (using the Procurement Request form extension or variation) at least 12 months (longer for high value high complexity engagements) prior to contract completion to determine the appropriate approach.
DPC Circular 44 provides additional information on the Government’s funding policy for the NFP sector.
19 Contract Extensions 19.1 Exercising a contract extension option Contract extension options are outlined in the contract and the relevant provisions detail how the contract extension options are to be exercised. Prior to exercising a contract extension consideration should be given as to whether the contract extension would provide value-for- money based on the contract outcomes to date and any new or emerging trends and issues relevant to the contract deliverables. Contract extensions as contemplated within the original contract which are exercised do not require formal procurement or financial approval as this would have been obtained when the original procurement and contract was approved and executed, however for all contracts above $550,000 (and in some other cases as determined by SPGC) SPGC will review contract performance prior to approving a contract extension. This is obtained through submission of a CMR. PGU will assist the Contract Manager to complete the CMR. For contracts valued below $4.4m the simple CMR can be used to obtain the SPGC’s or the delegate’s approval. Once approved, extensions are generally exercised by an exchange of letters. The tailored DHS extension letter template should be used and PGU will prepare the necessary contract variation/exchange of letters for execution by the supplier and BU.
Consideration to exercise an extension option generally commences well before the expiry date in case the extension is not taken up and a new procurement process is required.
For extensions beyond all contract extension options, refer to Section 19.2
14 Reference: SPB Contract Management Policy
Contract Management Handbook | Version 1.2 January 2019 28 19.2 Extension beyond extension options Where a contract has not yet expired and does not contain any (or any further) extension options, it can be extended before expiration by enacting a mutually agreed variation to the contract (subject to the approvals processes outlined below).
In these cases, there are two pathways for approval.
Where the proposed extension is for up to 12 months and involves more of the same goods/service while a new procurement process is completed or where the services are not required beyond extension period, the CMR process or a Memo may be used to seek approval. The extension should be progressed as a contract variation as outlined in section 20.3. Where the proposed extension is beyond 12 months, or involves a moderate or major change in the nature of the goods/services being procured and/or contract terms, then SPGC and PGU require an acquisition plan to be prepared. PGU Advisers need to consider risk and value-for-money and assess any negative impact of the proposed extended arrangements on the contract deliverables, price, timeframes, supplier market and objects of the State Procurement Act 2004 (Act) (including probity, transparency and accountability).
20 Contract Variations 20.1 Principles The key principles for the management of contract variations include:
Contract variations require financial and procurement approvals Procurement approval requires an assessment of the impact of the variation (Insignificant, Minor, Moderate or Major). o For all contracts with an initial value of greater than $550,000, SPGC may need to approve each variation, unless specifically delegated by SPGC. This is obtained by the BU completing a CMR, with assistance from PGU. o For a moderate or major variation to contracts valued below $15m, approval may be sought using the simple CMR, submitted by the business unit and endorsed by the Director Procurement and approved by SPGC. o State Procurement Board approval is required where the variation takes the total value of the contract from below to above DHS’s $15 million procurement authority irrespective of the assessed impact. Financial approval must15 take into account the value of the variation in addition to the original value of the procurement process The contract variation should be in writing using a letter (for minor variations only) or variation agreement or as otherwise detailed in the contract. For variations to extend the contract beyond all extension options contemplated in the contract, refer to section 19.
20.2 Nature of Contract Variations A contract variation is defined as an addition or alteration to the original contract.
15 Reference: SPB Contract Management Policy and Treasurer’s Instruction 8 Financial Authorisations
Contract Management Handbook | Version 1.2 January 2019 29 Variations may be proposed by either party and may refer to adding, removing or changing an existing contract provision.
Contract variations do not include exercising extension options provided for within the existing contract terms. These are not variations but are a contract management activity, refer section 19 above.
Identifying the approvals and processes required for a contract variation can be complex. Contract Managers should engage with PGU via [email protected] as soon as the potential need for a contract variation is identified. PGU will provide assistance and guidance to the Contract Manager throughout the process.
Although contract variations can be a normal part of contract management, PGU Advisers and DHS Contract Managers are to avoid unnecessary and unplanned variations by:
o undertaking careful planning and preparation of market and contract documentation to minimise the potential requirement for contract variations; and o identifying and including a process for managing variations at the acquisition planning stage and within draft contract documentation.
It is important that variations not be used to address, or compensate for the absence of, poor procurement management planning processes within the Business Unit or by the Contract Manager.
Any contract variation that relates to an unusually high complexity procurement or one that has a potential across-government impact should be referred to PGU for advice in relation to approval requirements.
There may be international free trade implications dependent on the nature and value of the variation proposed.
Contract Management Handbook | Version 1.2 January 2019 30
20.3 Approvals As outlined above, there are two approvals relevant to contract variations.
20.3.1 Procurement Approval An assessment of the impact of a variation is required to determine its level of significance and consequent need for procurement approval or not. As part of the assessment, Contract Managers, with assistance from PGU Advisers, will need to decide whether the requirements supporting the need for a contract variation are best managed under a contract variation or under a new procurement and contract arrangement. Approving delegates are to be satisfied that a contract variation is best suited and that the measure of impact has been appropriately assessed. Refer to the Appendix 6 for examples of variations and impact assessment.
A variation may impact:
• The scope of the contract – eg expanding the service • The term of the contract - with or without an increase in the value of the contract • The value of the contract • The contract options to be exercised • Prices (where outside of price variation provision outlined/contemplated within the contract) • Quantity • Specifications
For variations which are essentially “more of the same” (for example the addition of a new site, or a change in the site, for a cleaning service, or waste disposal arrangement) or a minor change to the contract terms (for example recognising a qualification or accreditation as acceptable under the contract), following the contract variation process is appropriate.
For variations which envisage a significant change such as the expansion of a service, then a procurement process is generally appropriate. If, after the procurement process has concluded, the result is the approval of using an existing supplier, then a contract variation may be the appropriate mechanism/instrument to use, rather than entering into a new contract. If the value of the varied contract exceeds the delegation level of the approving delegates of the new procurement, then additional approvals will also be required (potentially both procurement and financial).
The level of impact is determined by an assessment of the proposed variation in terms of its impact on the contract deliverables, price, timeframes and objects of the Act (including value for money outcomes, probity, transparency and accountability). The levels of impact for variations and the corresponding criteria for assessing a level of impact are categorised in the following table.
Contract Management Handbook | Version 1.2 January 2019 31 Impact of contract variations
Measure of Criteria for Assessing Procurement Approval Required (All Impact Impact (Examples are procurements, including simple provided in Appendix procurements) 6) Assessment by Aggregate Value Impact increases from below to above $15million Insignificant No potential to negatively Where a variation Irrespective of the impact the contract is assessed as assessed impact, deliverables, price Insignificant or approval is sought timeframes and objects Minor, a file note from the State of the Act (including detailing the Procurement Board value for money variation should be where the variation outcomes, probity, uploaded to the takes the total value transparency and objective folder, of the contract from accountability). unless variations below to above Minor Limited potential to are outside of DHS’s $15 million negatively impact the specific/limited procurement contract deliverables, variations for the authority. (Refer price, timeframes and contract set by note below) objects of the Act SPGC. (including value for For contracts money outcomes, valued above probity, transparency $550,000, SPGC and accountability). approval is required. Moderate Moderate potential to Where a variation negatively impact the is assessed as contract deliverables, Moderate or Major, price timeframes and procurement objects of the Act approval is to be (including value for sought from the money outcomes, approver of the probity, transparency acquisition plan. and accountability). (Refer note below) Major Major potential to negatively impact the contract deliverables, price timeframes and objects of the Act (including value for money outcomes, probity, transparency and accountability).
Note that in the case of a contract/s which resulted from an original procurement approval of the State Procurement Board, or a contract/s where the Board has approved a previous variation due to the aggregate value of the contract/s, PGU will assess the variation’s measure of impact to determine whether or not further procurement approval is required from the Board.
Contract Management Handbook | Version 1.2 January 2019 32 20.3.2 Financial Approval Any variation that will result in an increase in the total contract value must be approved by an officer with the appropriate financial authorisation to enter into a contract16. To determine the appropriate financial delegate, refer to the relevant agency’s (DHS, SAHA, LSA) delegations.
20.4 Contract Documentation - Legal Authorisation For a contract variation to be legally binding, all variations must also be dealt with in line with the variation procedures set out in the contract. Procurement approval by itself will not suffice. A contract will usually provide that a contract variation must be in writing and authorised by all of the contract signatories.
Note that changes to terms and conditions of contracts may only be authorised by all of the contract signatories. Advice from the Crown Solicitor’s Office may be necessary before such authorisation is given.
A list of authorised delegates can be found in in relevant agency delegations.
Contract Managers must17 not agree to informal contract variations by way of oral agreement or other conduct. Contact PGU using the Procurement Request Form – Extension or Variation and an officer will assist with the preparation of the CMR and will prepare the necessary contract variation/exchange of letters documentation.
20.5 Novation Novation refers to the act of replacing one party in a contract with another, or of replacing one debt or obligation with another. It extinguishes (cancels) the original contract and replaces it with another, requiring the consent of all parties involved.
When a novation is required due to an existing supplier simply changing its name eg a change in ABN, with no other associated changes (eg to company structure or ownership) then a deed can be created using the template drafted by the Crown Solicitor’s Office. The Deed will be forwarded to the original Supplier (party to the contract) which will then arrange for execution by the original supplier and the new supplier. The deed will then be executed by the relevant Minister, CE or ED, with an accompanying memo describing the background.
For a novation that involves changes other than a simple change of name, then the Business Unit Manager/Director should first endorse the change. Careful analysis and consideration of any such change is required. Where company restructures are occurring, the financial strength, viability and/or corporate ownership/guarantees can be significantly altered. In these cases, a novation could be a significant variation to the original contract. In such cases the contract variation process should be followed. PGU will manage this process, in accordance with the Contract Variation Section of this Handbook. It may be that a new procurement process is required and a new contract issued with a new supplier. The DHS Legal Services Unit should be engaged to advise in the event it is considered that a new procurement is required and the existing contract should be concluded.
16 Reference: Treasurer’s Instruction 8 Financial Authorisations 17 Reference: Contract Management Policy
Contract Management Handbook | Version 1.2 January 2019 33 20.6 Records Management All records must18 be saved into the relevant objective file, and variations should be recorded in PCMS and/or FGMS.
20.7 Administrative notices Standard contract terms provide that Contract Managers are the first point of contact between the Parties and are responsible for overseeing the effective administration of the Agreement including variations and extensions. Minor administrative amendments, such as the change from one DHS Contract Manager to another, may be advised to the supplier through a notice from the Contract Manager, with a copy of the notification filed with contract records.
20.8 Roles and Responsibilities The Contract Manager must19:
ensure all contract variations are undertaken in accordance with required policies and guidelines ensure appropriate financial approval is obtained for all contract variations that increase total contract value ensure appropriate procurement approvals are obtained based on the outcome of the impact assessment ensure contract variation documentation is executed by the authorised delegates from each party ensure records are kept ie documents are stored in Objective and notes are recorded in PCMS and/or FGMS.
Contact PGU (using the Procurement Request form extension or variation) and an officer will assist by preparing the necessary approvals documentation and contract variation agreement.
18 Reference: SPB Contract Management Policy and State Records Act 1997 19 Reference: SPB Contract Management Policy
Contract Management Handbook | Version 1.2 January 2019 34
21 Price Variations Where the contract provides a mechanism for price variations, processing of the variation in accordance with the provisions is part of the contract management process. For example, if the contract provides for prices/fees to be increased according to a formula/index, then the new price is generally formalised between the parties by exchange of letter.
A price variation which is not in accordance with the original contract provisions is a contract variation and must be managed in accordance with the standard contract variation process. An assessment of the proposed variation is to be made in terms of its impact on the contract deliverables, price, timeframes, value for money outcomes, probity, transparency and accountability. The level of variation is to be determined in terms of whether it is insignificant, minor, moderate or major.
Business Units are responsible for negotiating with the supplier to minimise price increases to achieve best value-for-money outcomes. PGU are able to provide advice on negotiation strategies. DHS practice is that SPGC approves all price variations for contracts above $550,000 (GST inclusive), where the contract does not provide for such an increase, unless specifically delegated to a Director/Executive Director. SPGC’s approval will be sought via a Contract Management Report, prepared by the Business Unit with assistance from PGU.
Once the delegate has approved the price adjustment, PGU will prepare the necessary documentation/exchange of letters for execution by the Business Unit.
21.1 Information to support a price variation The formal contract/agreement should specify the procedure for price adjustments. This should include information on what information is required when an adjustment is sought, and the frequency/timing of any price adjustment request.
Generally at a minimum the supplier should provide:
a schedule in the same format/with the same level of detail (ie itemised deliverables and prices) as the price/fee schedule in the contract/agreement the existing price for each item the increase requested/proposed for each item (eg % increase) the new price for each item data supporting the % increase eg relevant benchmark or index
The Contract Manager should check the information provided, validate any % increase (eg to the independent index/benchmark) and where appropriate negotiate for any reductions in proposed prices.
Contract Management Handbook | Version 1.2 January 2019 35 22 Contract Closure report The requirements for the completion of a contract closure report are detailed in the DHS Contract Management Guideline.
The Contract Closure Checklist should be completed by the Contract Manager on contract closure. A contract closure report (CCR) should also be conducted at the end of a contract (contract period) for all contracts, as outlined in the DHS Contract Management Guideline. PGU will tailor a CCR for the contract. The SPB Contract Management Policy provides further information. File the contract report in Objective.
Refer to the PCMS instructions to record the completion of the contract within PCMS.
Information provided through CCRs is important to document lessons learned, capture corporate knowledge and assist in achieving improved outcomes in future procurements.
23 Is there a contract in place to meet my needs? The PGU intranet site contains a Purchasing Portal which is designed to assist DHS staff get the best value-for-money when acquiring goods and services.
This site contains information for all DHS staff about where and who to buy goods and services from. It contains a listing of the most recent news relating to purchasing including any new contracts that have been finalised. The portal can be used to check whether there are any Across-Government or Across-DHS Mandated contracts which provide the goods or services you require.
The quickest way to navigate the site is by clicking on the relevant A-Z Index to the left of the page. If you can't find what you are looking for on this site, please email the Contract Operations Team [email protected] to discuss your needs.
Contract Management Handbook | Version 1.2 January 2019 36 Appendix 1 Overview of Key Contract Management Activities Reference numbers to the section in the Handbook are included in parenthesis.
Appoint a Contract Manager (over $550,000) Place name in contract register (2) (3) Undertake contract management training (where required) (2) Develop contract management plan (over $4,400,000) (8)
Schedule initial and regular Governance Committee and Contract Management Team meetings (where appropriate) (9)
Schedule initial and regular contract management meetings (monthly, quarterly, biannual) (9)
Contract Start up and Implementation activities (10)
Prepare contract management meeting agenda (13.3)
Attend contract management meetings (13.3) Undertake specific tasks for managing consultants and contractors (16)
Review performance data and monitor performance measures (13)
Review risk management plan (13.5)
Manage disputes and non‐performance (when For NFP contracts, manage required) (17,13.8) acquittals and retrieve surplus funds (15)
Document outcomes of meeting (12) Certify payments (where relevant) ensuring in line with contract pricing (11) Communicate with stakeholders/users (as required) (13.6)
Undertake review of contract performance Prepare contract management (e.g. quarterly/biannual) (13) reports (14)
Seek approval for novations, variations and extensions to contract (where required) (18,19,20,21) Prepare contract closure report (22)
Contract Management Handbook | Version 1.2 January 2019 37 Appendix 2 Contract Management Checklist for Contract Managers – contracts below $4,400,000 This contract management checklist is available as a stand-alone template
Pre-contract execution stage
̀ Involvement in the contract planning and development phase. Identify key factors to be included in the request document that will increase the success of the contract management phase. These include appropriate performance measures and reporting mechanisms and incorporating the lessons learnt from previous contracts.
̀ Read and understand the proposed Contract/Agreement, including the Standard Terms and Conditions and specific details in Attachments; the Request For Quote/Invitation to Supply document; the Supplier’s Response; and the Contract Award Letter; other documents such as any correspondence between the parties from close of tender to award.
̀ Ensure that the required information from the suppliers’ tender response has been incorporated correctly into the contract.
̀ Develop a Contract Management Plan or Simple CMP (and Workbook as appropriate) and update it regularly so it is a useful source of information.
̀ Understand legislative, compliance, governance and audit requirements. This includes DHS, State Procurement Board, and Industry Participation Policy requirements as well as other legislative requirements.
̀ Attend the State Procurement Board’s Contract Management Training session (optional).
Ongoing