VILANGALPATTU GRAVEL & PEBBLES QUARRY

S.F.NO:51/16B,51/17,93/3B, Vilangalpattu Village, Taluk,

Cuddalore District, Tamilnadu.

LEASE PERIOD: ONE YEAR ONLY.

Quarry lease area – 1.36.5 Ha

Proposed Gravel & Pebbles Production – 24,742m3 (23,507 m3 of Gravel & 1237 m3 of Pebbles) for a Period of One Year Only.

FORM -1, PREFEASIBILITY REPORT & APPROVED MINING PLAN.

Thiru.K.SARANGAPANI,

S/O.KALIYAPERUMAL,

KULANTHAI KUPPAM,

VANMADEVI(P.O)

CUDDALORE DISTRICT-607105.

CONTENTS

S.NO PARTICULARS PAGE NO

1. Covering Letter I 2. CHECK LIST II 3. FORM 1 1 4. PRE FEASIBILTY REPORT 35 5. Approved Mining Plan Letter with seal by the 75 & 79 Department of Geology and Mining. 6. Precise Area Communication Letter from 71 District Collector. 7. Certificate from the VAO stating the details of 179,181 Habitation & RI Letter For Inter State Boundary. 8. Letter from the Department of Geology and 183 Mining of other quarries within 500m Radius from the proposed quarry site. 9. Affidavit from the Applicant regarding general 187 Conditions,Habitation,other quarry, Permanent structure ,Child Labour ,etc 10. Documents of Village records, FMB and 1Km & 161,131,135 10Km Radius Map.

Form 1 as per EIA Notification 2006 for Vilangalpattu Gravel & Pebbles Quarry of Thiru.K.Sarangapani, Vilangalpattu Village, and District, Tamilnadu.

Application Form for Obtaining Environmental Clearance from State Level Environment Impact Assessment Authority (SEIAA), .

S. No Item Details 1 Name of the project/s Vilangalpattu Gravel & Pebbles Quarry project 2 S. No. in the schedule 1 (a) Proposed capacity = 24,742m3 (23507m3 Of Gravel & 1237m3 of Pebbles) for a period of One Year only. Area =1.36.5Ha. Proposed capacity/area/length/ Dimensions of the area tonnage to be handled / length in Width in Depth 3 command area/lease (m) (M) in (m) area/number of wells to be drilled Avg 99 72 2 69 76 It is open cast shallow quarrying the Gravel & Pebblesis clearly visible right from the surface hence No wells are proposed not drilled. New/ Expansion/ Modernization It’s a new Project ( Vilangalpattu Gravel & 4 Pebblesquarry) Existing capacity / Area etc. The proposed capacity is only 24,742m3 (23507m3 Of Gravel & 1237m3 of Pebbles) for 5 2m. The total Geological reserve is about 83,420m3. Area = 1.36.5Ha. 6 Category of project i.e. `A’ or ‘B’ Category - B (B2) Does it attract the general 7.5m safety distance from the adjacent patta 7 condition? If yes, please specify. lands. Does it attract the specific The project does not attract any specific 8 condition? If yes, please specify. condition. Location Vilangalpattu Village, Cuddalore Taluk and District. Plot/ Survey/ Khasra No. 51/16B,51/17,93/3B Village Vilangalpattu 7 Taluk Cuddalore District Cuddalore State Tamilnadu Nearest railway station/ airport Railway station -5 km - N 10 along with distance in km. Chennai Airport - 132km - NE Nearest Town, city, District Nearest Town: Cuddalore - 4.0km - NE 11 Headquarters along with distance Nearest City : Cuddalore - 4.0km - NE in kms. District : Cuddalore - 4.0km - NE

Village Panchayats, Zila Parishad, Village Panchayat - Vilangalpattu Municipal Corporation, Local Panchyat Union - Cuddalore 12 body (Complete postal addresses Taluk - Cuddalore with telephone nos. to be given) District - Cuddalore 13 Name of the applicant Thiru.K.Sarangapani,

S/o. Kaliyaperumal,

Kulanthaikupppam,

Vanamadevi(Post),

14 Cuddalore District. Registered Address Pincode – 607105.

Address for correspondence Thiru. K.Sarangapani, Designation Proprietor/Owner (Owner/Partner/CEO)

S/o. Kaliyaperumal,

Kulanthaikupppam,

Vanamadevi(Post),

15 Cuddalore District. Address Pincode – 607105.

Pin code 607105.

E-mail [email protected] Telephone No. Cell No. 9443268726 Fax No. - Details of Alternative Sites examined, if any. Location of There is no alternative site examined. The 16 these sites should be shown on a project is site specific. Topo sheet 17 Interlinked Projects There is no interlinked projects Whether separate application of As there is no interlinked project, no 18 interlinked project has been application has been submitted submitted? If yes, date of submission As there is no interlinked project hence no 19 application has been submitted. If no, reason The project involves Gravel & Pebbles Quarry 20 only. Whether the proposal involves approval/ clearance under: if yes, (a) The project does not attract the Forest details of the same and their (Conservation) Act 1780. There is no status to be given. Forestland involved within the quarry lease- (a) The Forest (Conservation) Act, applied area. 21 1780? (b) There is no wild life within the 10km (b) The Wildlife (Protection) Act, radius from applied area and does not fall 1772? under the Wildlife (protection) Act 1772. (c) The C. R. Z. Notification, 1771? (C) The project doesn’t attract the C.R.Z. Notification, 1771. The applicant has obtained precise area communication from the District Collector, Cuddalore vide (R.C.No.420/Mines/2014

dated 31.05.2016.) Whether there is any Government 22 The Mining Plan was got approval by the Order/ Policy relevant/ relating to the site? Assistant Director, Department of Geology and Mining, Cuddalore vide (R.C.No.420/Mines/2014 dated 16.06.2016.)

There is no forest land involved in this lease 23 Forest land involved (hectares) area. Whether there is any litigation pending against the project and/ or land in which the project is propose to be set up? There is no court case pending, litigations (a) Name of the Court 24 relating to the project directly and indirectly. (b) Case No. (c) Orders/ directions of the Court, if any and its relevance with the proposed project.

I. Basic information II. Activity 1. Construction operation or decommissioning of the project involving actions, which will cause physical changes in the locality (Topography, land use changes in water bodies, etc.)

Details thereof (with approximate Information/Checklist Yes/ S. No quantities/rates, wherever possible) with confirmation No sources of information data Permanent or temporary change in land use, land The topography will be slightly changed cover or topography after the quarrying of Gravel & Pebbles as 1.1 including increase in Yes per the Mining Plan, Gravel & Pebbles intensity of land use (with formation is seen right from the surface respect to local land use to a depth of 2m Above ground level. plan)

Clearance of existing land, The quarry lease applied area is devoid of 1.2 vegetation and building? No vegetation’s, Human settlement and buildings hence clearance is redundant.

The quarrying activity is proposed to carry out within the quarry lease applied area. Temporary approach road within Creation of new land uses? No 1.3 the area will be form for the easy access of men and machinery which will be well maintained. The Gravel & Pebbles deposits are clearly Pre-construction visible right from the surface hence pre- 1.4 investigations e.g. bore No construction investigation and soil houses, soil testing? testing is not proposed before quarrying operation. There will be no major civil work in this project involved. The infrastructure Construction works? Yes 1.5 facilities are proposed in the quarry site on semi-permanent structures. There is no existing building within the 1.6 Demolition works? No quarry lease applied area, hence no demolition work is involved. Temporary sites used for Sites service on semi-permanent construction works or Yes structure will be constructed only after 1.7 housing of construction grant of quarry lease. workers? There are no tall buildings or linear Above ground buildings, structure found in and around the structures or Gravel & quarry site. There is no requirement of 1.8 Pebblesworks including No cutting and filling in the site. The linear structures, cut and proposed quarry is to exploit Gravel & fill or excavations. Pebbles from consolidated sediments for 2m Above ground level.

Open cast semi mechanized method of Underground works quarrying will be adopted. No 1.9 including mining or No underground mining or tunneling is tunneling? proposed. The quarry operation is restricted up to a depth of 2m Above ground level. after Reclamation works? removing the Gravel & Pebbles there is No 1.10 no proposal for backfilling or reclamation. The quarried out land will be leveled and used for agricultural There is no such type of activities 1.11 Dredging? No involved in this opencast quarrying operation. There is no such type of activities 1.12 Offshore structures? No involved; It is an inland quarrying project.

Production and No production and manufacturing is No 1.13 manufacturing processes? involved in the Gravel & PebblesQuarrying. There is no proposal for storage of material within the quarry lease applied area. The Gravel & Pebbles will be loaded directly to the trucks / Lorries for Facilities for storage of transportation to the needy customers No 1.14 goods or materials? site for construction industries for Government & Public sector projects besides catering domestic housing and infrastructure projects in and around the district. There is no wastage encountered during the quarrying operation, the entire excavation will be used for construction industries for Government & Public Facilities for treatment or 1.15 disposal of solid waste or No sector projects besides catering domestic liquid effluents? housing and infrastructure projects in and around the district. The Gravel & Pebbles will not produce toxic effluence in the form of solid, liquid or gas. The proposed project is 1.36.5Ha for a period of One Year only. The required Facilities for long term employees (7Nos.) are available in the 1.16 housing of operational No nearby villages, hence long term housing workers? of operational workers are not proposed.

No new roads, rail or sea traffic is New road, rail or sea traffic proposed during operation, the existing during construction or road will be utilized for transportation of operation? No the Gravel. 1.17 However, internal roads within the quarry

lease applied area will be developed and

maintained.

New road, rail, air There is no such type of activities waterborne or other involved in this project. transport infrastructure No Existing road will be utilized for the 1.18 including new or altered transportation of Gravel & Pebbles to the routes and stations, ports, needy customers site. airports etc.?

Closure or diversion of existing transport routes or The project will not cause any changes 1.19 infrastructure leading to No and hindrance in the existing traffic changes in traffic movements. movements? New or diverted The project does not involve divers ion of 1.20 transmission lines or No transmission/pipe lines. pipelines? The quarrying operation is restricted up Impoundment, damming, to a depth of 2m Above ground level; 1.21 culverting, realignment or No Ground water occurrence in this area is other changes to the at 35m depth from ground profile. Hence hydrology of watercourses there is no damage for ground water or aquifers? hydrology or aquifers.

There is no stream crossing within the 1.22 Stream crossings? No quarry lease applied area.

Abstraction or transfers of The proposed quarrying does not require 1.23 water form ground or No any abstraction or transfer of water from surface waters? the ground or surface water bodies. The quarry operation is restricted up to a Changes in water bodies or depth of 2m. Quarry operation will not 1.24 the land surface affecting No affect the drainage pattern of the area. drainage or run-off? There is no change in water bodies or the land surface affected during run off. During operation phase, after grant of lease quarrying personnel will be brought from surrounding villages by jeep or van. Transport of personnel or materials for construction, The materials and tools shall be 1.25 No operational or transported by trucks and tippers, the decommissioning? existing road and infrastructure facilities are sufficient. No construction operation or decommissioning envisaged.

Long-term dismantling or There is no Dismantling or 1.26 decommissioning or No decommissioning is proposed in this restoration works? project. Ongoing activity during decommissioning which There is no such type of activities involved No 1.27 could have an impact on in this project. the environment? During operational phase, the manpower requirement will be around 7. Local people are envisaged in this quarry Influx of people to an area operation. No child labor will be deployed 1.28 in either temporarily or Yes for any type of quarrying operation. All the permanently? labors engaged for quarrying operations will be trained, equipped with protective devices and insured till the end of life of quarry. . Introduction of alien There are no causes to develop the alien No 1.29 species? species. There will no loss of native species or genetic diversity taken during the Loss of native species or No quarrying operation as the lease applied 1.30 genetic diversity? area is devoid of vegetation and agriculture.

1.31 Any other actions? No There is no any other actions

2. Use of Natural resources for construction or operation of the project (such as land, water, materials or energy, especially any resources which are non - renewable or in short supply): Details thereof (with approximate Information/Checklist Yes S. No quantities/rates, wherever possible) with confirmation /No sources of information data It’s a Patta land Registered in the name of Thiru.K.Sarangapani Vide Patta Nos-, 952,842. The applicant has obtained surface rights to lease applied area. Please refer the Annexure No – III. The lease applied area is exhibits slightly elevated topography covered with Gravel & Pebbles which does not Land especially undeveloped sustain any type of vegetation due to the No 2.1 or agricultural land (ha) topography of the land. The altitude of the area is 28m (Maximum) from MSL, the slope of the area is gentle towards southeastern side. Please refer the Topography, Geological plan and sections (Plate No –III & III A).

The project does not require huge water for quarrying operation, about 1 KLD of water will be used for the project. 1. Drinking Water – 0.3 KLD & Domestic purpose 2. Dust Suppression – 0.3 KLD 3. Green belt – 0.4 KLD Total – 1 KLD 0.3 KLD of Packaged Drinking water and Domestic purpose will be brought from Water (expected source & 2.2 Yes the approved water vendors in competing users) unit: KLD Vanamadevi which is about 0.5km on the Northeastern side of the area. 0.3 KLD of water for dust suppression and 0.4KLD of water for Green developments will be brought from approved water venders or existing borehole on nearby quarry. Total requirement for the project is around 1KLD. There is no Minerals used for 2.3 Minerals (MT) No construction purposes

Construction material - two, There is no Construction material aggregates, and/Soil No 2.4 proposed. (expected source-MT)

Forests and timber There are no forests and timber material 2.5 No (source-MT) is proposed.

The limited scale of activities adopted in Gravel & Pebbles Quarrying does not Energy including electricity require high-tension electric power and fuels (source, competing 2.6 Yes supply. Fuels are used for operating users) unit: fuel (MT),Energy (MW) vehicles during quarrying process. Fuels required for excavator for the entire project life 10200 liters of HSD. 2.7 Any other natural resources There is no other natural resource will (use appropriate standard No be required. units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health. Details thereof (with approximate Information/Checklist Yes S. No quantities/rates, wherever possible) with confirmation /No sources of information data Use of substances or There is no proposal for storage, materials, which are handling or transportation of any hazardous (as per MSIHC No hazardous materials or substances as 3.1 rules) to human health or the per MSIHC rules in this Gravel & environment (flora, fauna, Pebbles Quarry project. and water supplies) The Gravel & Pebblesdoes not produce Changes in occurrence of any toxic effluent in the form of solid, disease or affect disease 3.2 No liquid and gas, hence the diseases vectors ( e.g. insect or water related to insect or water borne diseases borne diseases) is not envisaged. Welfare of people will get positive change due to the project, where a number of Welfare activities are being undertaken. Due to increase of the employment earning of local people and Affect the welfare of people lifestyle of the people will enhance, 3.3 e.g. by changing living No around 7 peoples will be directly benefit conditions? to this project. No child labor will be engaged for any type of quarrying operation. All the labor will be insured and the salary and benefits will be paid as per the Labor enforcement officers (Ministry of labor

Vulnerable groups of people There is no effect envisaged for the who could be affected by the No vulnerable groups of people who could 3.4 project e.g. hospital patients, be affected by the project. children’s, the elderly etc., 3.5 Any other causes No There is no other cause are envisaged

4.0 Production of solid wastes during construction or operation or decommissioning (MT/mounts) Details thereof (with approximate Information/Checklist Yes S. No quantities/rates, wherever possible) with confirmation /No sources of information data The Gravel & Pebbles Quarrying does not produce any waste. The entire Gravel & Spoil, overburden or mine No Pebbles will be excavated. There are no 4.1 wastes wastages encountered during the quarrying period (One Year).

Small quantity of Municipal waste will be Municipal waste (domestic Yes generated which shall be disposed as per 4.2 and or commercial wastes) guidelines. In this quarrying activities waste oil will be generated during the operation period it will be sent to authorize Re- Circulars Hazardous wastes (as per as per SPCB/ CPCB norms. Care and Hazardous Waste No 4.3 maintenance of vehicles by experience Management Rules) qualified mechanics will be undertaken to prevent breakdown and spillage of oils and lubes.

Other industrial process Industrial wastages are not generated 4.4 No wastes during the quarrying operation. There is no such type of activities in this Surplus product No 4.5 quarry. Sanitary facilities will be constructed as Sewage sludge or other semi-permanent structure and the 4.6 sludge form effluent Yes sewage waste will be disposed as per the treatment norms. Construction or demolition There are no Construction or demolition No 4.7 wastes wastes involved in this quarry.

No redundant machineries involved in Redundant machinery or No this project, only Excavator and tipper 4.8 equipment are involved in this quarry operation.

Contaminated soils or other There is no contaminated material or soil No 4.9 materials observed in the quarry area. There is no agricultural waste Agricultural wastes No 4.10 anticipated. 4.11 Other solid wastes No There is no other solid waste anticipated.

5.0. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) Details thereof (with approximate Information/Checklist Yes/ S. No quantities/rates, wherever possible) confirmation No with sources of information data The emissions of SO2 (Sulfur dioxide) &

NO2 (Nitrogen dioxide) may be due to Emissions form combustion of use of diesel operated quarry 5.1 fossil fuels from stationary or Yes machinery and vehicles. Better mobile sources maintenance of equipment in good condition will help to reduce such emissions. Dust is the main pollutant produced in the proposed activity. Emission from loading and plying of tippers can take place but they will be maintained Emissions from production Yes 5.2 processes within limits by proper maintenance and sprinkling of water on haul roads, Tarpaulin covers during Transportation.

Fugitive dust will be generated from material handling activities. Dust suppression by water Emissions from materials sprinkling will be provided to prevent handing including storage or Yes 5.3 the fugitive dust emissions during transport loading. Tarpaulin covers will be covered in vehicles during transportation. Emissions form construction There is no major construction 5.4 activities including plant and No activities are envisaged. equipment Minor Dust will be generated during loading of material, transportation of Dust or odors form handling Gravel & Pebble sand it will be of materials including No controlled. However, there is no 5.5 construction materials, possibility of any odor generation as sewage and waste there are no organic solvents/processes involved. Emissions from incineration The Gravel & Pebbles Quarrying does No 5.6 of waste not produce any toxic effluents. Emissions from burning of waste in open air (e.g. slash There is no such type of activities 5.7 No materials, construction involved in this project. debris) 5.8 Emissions from any other Emissions from other sources are not No sources envisaged.

6.0. Generation of Noise and Vibration, and Emissions of Light and Heat: Details thereof (with approximate Information/Checklist Yes/ S. No quantities/rates, wherever possible) confirmation No with sources of information data Due to operation of machinery there is likely hood of some increase in noise level. The noise level at site will be maintained Above permissible limit. Measures like lubrication and From operation of equipment preventive maintenance shall be 6.1 e.g. engines, ventilation plant, Yes taken to control noise from the crushers machinery. The vibration during the movement of machinery will be minimal for a short span which will be well within the prescribed limits. From industrial or similar There is no proposal of processing No 6.2 processes plant

From construction or No construction or demolition work No 6.3 demolition takes place. No drilling or blasting is proposed for this Gravel & PebblesQuarrying 6.4 From blasting or piling No operation.

The transport of Gravel & Pebbles through tippers can produce noise but are maintained within permissible From construction or 6.5 Yes limits, by keeping machinery in operational traffic proper condition as per RTO &TNPCB norms and maintenance under experience and qualified mechanics.

The quarry operation will be carried From lighting or cooling out at the daytime only between 7Am 6.6 No systems to 6Pm hence; the lighting and cooling systems are not required. 6.7 From any other sources No Not envisaged

7.0. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface water, ground water, coastal water or the sea: Details thereof (with approximate Information/Checklist Yes/ S. No quantities/rates, wherever possible) confirmation No with sources of information data No hazardous materials will be used in the process. From handling, Storage, use Oiling and lubrication of hauling 7.1 or spillage of hazardous No vehicles will be done by using oil tray materials to prevent spillage of oil. Vehicles and machinery will be well maintained to prevent leakage of oil.

The discharge of sewage will The Discharge of sewage will be be collected on soak pits will collected on soak pits and will be 7.2 be discharge to a place No discharge to a place authorized by authorized by municipal Municipal Authorities as per guide authorizes as per guidelines lines. There is likely hood of increase of By deposition of pollutants particulate matter due to quarrying 7.3 emitted to air into the land or No operations. Regular sprinkling of into water water will suppress dust at points/places of generation.

An efficient and effective management plan is proposed for the project; 7.4 From any other sources No hence it may not have any significant impact on the surrounding environment. Is there a risk of long term There is no such type of activities buildup of pollutants in the involved in this quarry. No 7.5 environment from these sources?

8.0. Risk of accidents during construction or operation of the project, which could affect human health or the environment

Details thereof (with approximate Information/Checklist Yes/ S. No quantities/rates, wherever possible) confirmation No with sources of information data No explosions and spillages are From explosions, spillages, proposed for quarry operation. The fires etc., form storage, Gravel & Pebbles will be directly No 8.1 handling, use or production of excavated with the help of excavator. hazardous substances The quarry operation does not produced hazardous material. Limited vehicles are only used for quarrying operation up to a depth of 2m Above ground level. Hence the accident is anticipated minimal. However, all safety measures 8.2 From any other causes Yes shall be taken to prevent any accidents. The quarrying activities will be monitored under the supervision of experienced and qualified competent mines foreman. There is no Earth quake, floods, Landslides, cloud burst Could the project be affected recorded in the area. Its opencast by natural disasters causing 8.3 environmental damage (e.g. No quarrying proposed only for 2m depth floods, Earth quakes, Above ground level. which will not landslides, cloudburst etc.)? cause any adverse environmental damage due to natural disasters.

9. Factors which should be considered (such as consequential development) which could lead to environmental effects to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality

Details thereof (with approximate Information/Checklist Yes/ S. No quantities/rates, wherever possible) confirmation No with sources of information data

Lead to development of Living standard will be improved supporting. cities, ancillary development or development of the nearby villagers. stimulated by the project This short span of project does which could have impact on not require any supporting

the environment e.g.: infrastructures like roads, power

9.1  Supporting infrastructure supply, waste treatment, etc., (roads, power supply, waste The workers are available from or waste treatment, etc.) No the nearby villages, hence the project  housing development will not attract housing Development,  extractive industries  supply industries Extractive industries, supply  other industries or any other activities.

The quarry operation is restricted up to a depth of 2m Above ground level, Lead to after- use of the site, after removing the Gravel & Pebbles 9.2 which could heaven impact on No there is no proposal for backfilling or environment reclamation. The quarried out land will be leveled and used for agricultural purpose.

Set a precedent for later No There is no later developments 9.3 developments Have cumulative effects due to proximity to other existing There is no cumulative impacts are No 9.4 or planned projects with envisaged. similar effects

(I) Environmental Sensitivity

S. Name/ Aerial distance (within 15 km.) Areas No Identity Proposed project location boundary

Areas protected under international conventions, national or local No protected areas to be identified with in 15 km 1 No legislation for their distance. ecological, landscape, cultural or other related value

Areas which are important or There is no wild life, bird sanctuary, Reserve or sensitive for Social forest 15km near the quarrying lease ecological reasons applied area. - Wetlands, No 2 watercourses or There is no coastal, Forest, Eco sensitive Zone other water bodies, within the radius of 15Km, the area does not fall coastal zone, in HACA region. biospheres, mountains, forests

Areas used by protected, important or sensitive species of There is no protected sensitive species identified flora or fauna for No 3 within the 15km radius. breeding, nesting, foraging, resting, over wintering, migration

Inland, coastal, marine or There is no Inland, coastal, marine or No 4 underground underground water around the site. waters

State, National There is no State or National boundaries within a 5 No boundaries radius of 15Km. Routes or facilities used by the public for access to There is no Tourist, pilgrim areas within 15Km Yes 6 recreation or other radius tourist, pilgrim areas Defense 7 No No defense installation found 15km near the site installations Vanmadevi is a densely populated village which is about at a distance 0.5km Northeastern side. Approximate distance & Approximate S.No Name of the Village Direction population from lease Densely populated applied area 8 or built-up area Yes 1. Vanamadevi 0.5km – NE 350 2. Ampothkarnagar 1.7km - NW 400

3. KNplayam 2.3Km – SE 420

4. Kulanthaikuppam 1km –SW 300

Areas occupied by sensitive man- Cuddalore is having all the facilities, which are at a made land uses distance of 11km on the Northeastern side from the 9 (hospitals, schools, Yes lease-applied area. places of worship, community facilities) Areas containing important, high quality or scarce resources The quarry operation is restricted to only 2m (ground water Above ground level. Hence the ground water will No 10 resources, surface not be affected beside the area is devoid of resources, forestry, agriculture, Forestry, Tourist place etc., agriculture, fisheries, tourism, minerals) This is a fresh quarry lease applied area. Areas already subjected to pollution or environmental 11 damage. (those No where existing legal environmental standards are exceeded)

Areas susceptible to natural hazard which could cause the project to present environmental The area is not susceptible to natural hazards like problems No 12 landslides, Earth quake; it is a high stable land. (Earth quakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)

“I hereby given undertaking that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted is found to be false or misleading at any stage, the project will be rejected and clearance give, if any to the project will be revoked at our risk and cost.

Signature of the applicant with Name and Full Address

Thiru.S.Sarangapani, S/o. Kaliyaperumal, Kulanthaikupppam, Vanamadevi (Post), Cuddalore District.

Signature of the Recognized qualified person

R.Rajasekar.M.Sc., RQP/CNN/264/2015/A

Place: Cuddalore. Date