SITUAȚIA PROIECTELOR DE INFRASTRUCTURĂ - SEPTEMBRIE 2021

1.AUTOSTRĂZI

1.1. AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI - SEPTEMBRIE 2021

PANA LA DETALII NR. CRT. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL STADIUL FINANCIAR ACTUAL DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDERE VALOARE PROIECT OBSERVAȚII (km) PROCEDURĂ

CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 11.08. 2020. 14.09.2020 - EMITERE ORDIN MARTIE 2022 (CONFORM ANUL 2022 6 LUNI - ETAPA DE A FOST TRANSMISA CATRE ANTREPRENOR ADRESA CU ORDINUL DE INCEPERE PENTRU DATA DE 14.09.2020. A FOST ACORDAT DREPTUL DE ACCES IN SANTIER ANTREPRENORULUI. ASOCIEREA TRAMECO SA – VAHOSTAV -SK A.S. – SECTIUNEA 3C, AUTOSTRADA BRASOV - TARGU MURES - SUBSECTIUNEA 3C2: DE INCEPERE PENTRU ETAPA CONTRACT) PROIECTARE; 18 LUNI - ETAPA DE 326.51 MIL. LEI FARA DURATA CONTRACTULUI ESTE DE 144 DE LUNI DIN CARE: 1 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 30+550 59+100 DRUMURI BIHOR SA – DRUM ASFALT SRL – EAST SUBSECTIUNEA 3C2 CHIRIBIS - 28.55 0.50% 0% CLUJ - ORADEA CHIRIBIS - BIHARIA DE PROIECTARE (PROIECT IUNIE 2022 (CONFORM EXECUTIE LUCRARI; 120 LUNI - TVA 6 LUNI - ETAPA DE PROIECTARE; FINALIZARE PUNCT DE REFERINTA NR. 1 IN 09.11.2020. WATER DRILLINGS SRL BIHARIA TEHNIC) PROGRAM) PERIOADA DE GARANTIE 18 LUNI - ETAPA DE EXECUTIE LUCRARI 120 LUNI - PERIOADA DE GARANTIE

SEMNARE CONTRACT PROIECTARE SI EXECUTIE IN DATA DE 28.12.2020. PRETUL PE KM DE AUTOSTRADA ESTE DE CCA. 46,261,293.92 LEI FARA TVA, REPREZENTAND CCA. 9,383,629 EURO FARA TVA. DURATA CONTRACTULUI ESTE DE 96 DE LUNI, DIN CARE: SUBSECTIUNEA 3A2 • 12 LUNI PERIOADA DE PROIECTARE, SECTIUNEA 3A SI SECTIUNEA NADASELU - MIHAIESTI • 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR, AUTOSTRADA BRASOV - TARGU MURES - ASOCIEREA S.C. SPEDITION UMB S.R.L. – S.C. 3B, SUBSECTIUNEA 3A2: KM 8+700 - 25+500+ 1.390,614 MIL. LEI FARA 2 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 8+700 38+760 30.06 0% 0% 25.01.2021 2023 ANUL 2023 • 60 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR. CLUJ - ORADEA TEHNOSTRADE S.R.L. – S.C. ELECTROMONTAJ S.A NADASELU - MIHAIESTI SI 3B1: 3B1, MIHAIESTI – TVA AUTORIZATIE DE CONSTRUIRE EMISA PENTRU SECTORUL 3A2 IN LUNA APRILIE 2021. MIHAESTI ZIMBOR ZIMBOR KM 0+000 - AUTORIZATIE DE CONSTRUIRE EMISA PENTRU SECTORUL 3B1 IN 01.07.2021 13+260 PROIECT TEHNIC DE EXECUTIE PENTRU 3A2 AVIZAT IN CTE - CNAIR IN DATA DE 20.08.2021 PROIECT TEHNIC IN CURS DE ELABORARE PENTRU 3B1 - TERMEN ESTIMAT AVIZARE PROIECT TEHNIC: DEC. 2021

CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN 30.09.2020; SECTIUNEA 3B, 6 LUNI PERIOADA DE PROIECTARE SUBSECTIUNEA 3B5: AUTOSTRADA BRASOV - TARGU MURES - SUBSECTIUNEA 3B5 384.14 MIL. LEI FARA ; 18 LUNI PERIOADA DE EXECUTIE 3 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 66+500 80+054 NUROL INSAAT VE TICARET S.A NUSFALAU - SUPLACU 13.55 0% 15% 01.02.2021 FEBRUARIE 2023 FEBRUARIE 2023 CLUJ - ORADEA NUSFALAU - SUPLACU DE TVA ; 120 LUNI PERIOADA DE GARANTIE DE BARCAU BARCAU LUCRARILE PENTRU REALIZAREA ACESTUI SECTOR DE AUTOSTRADA PREVAD SI CONSTRUCTIA A 12 STRUCTURI (4 PASAJE SI 8 PODURI), RESPECTIV UN NOD RUTIER LA KM 67+500 FINALIZARE ETAPA PROIECTARE (PTE) - PROIECTUL TEHNIC DE EXECUTIE A FOST AVIZAT IN CADRUL CTE IN DATA DE 02.08.2021

CONTRACT PROIECTARE SI EXECUTIE SEMNAT IN DATA DE 01.07.2020; DURATA CONTRACTULUI ESTE DE 156 DE LUNI, DIN CARE: SECTIUNEA 3B, SUBSECTIUNEA 3B2: AUTOSTRADA BRASOV - TARGU MURES - ASOCIEREA SC SA&PE CONSTRUCT SRL - SC 31.05.2021 - ORDIN DE 680.40 MIL. LEI FARA 12 LUNI PERIOADA DE PROIECTARE, 4 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 13+260 25+500 SUBSECTIUNEA 3B2: ZIMBOR - ZIMBOR - POARTA 12.24 0% 0% 2023 ANUL 2023 CLUJ - ORADEA SPEDITION UMB SRL - SC TEHNOSTRADE SRL INCEPERE TVA 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR, POARTA SALAJULUI SALAJULUI 120 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR A FOST CONSTITUITA GARANTIA DE BUNA EXECUTIE A LUCRARILOR, ORDINUL DE INCEPERE A LUCRARILOR EMIS PENTRU DATA DE 31.05.2021

1. CONTRACT DE EXECUTIE SEMNAT IN DATA DE 29.05.2020. 2. AUTORIZATIE DE CONSTRUIRE VALABILA PENTRU ACEST SECTOR. LOT 1 - TARGU MURES - 2022 (CONFORM CONTRACT) 3. DURATA DE REALIZARE A ACESTUI CONTRACT ESTE URMATOAREA: AUTOSTRADA BRASOV - TARGU MURES - SECTOR 1C: TG. MURES - UNGHENI (4.5 KM) + ORDIN DE INCEPERE PENTRU 192.06 MIL. LEI FARA 5 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 0+000 4+500 S.C. STRABAG S.R.L. 9.2 75.00% 42.45% 2021 - CONFORM ESTIMARE ANUL 2022 18 LUNI - PERIOADA DE EXECUTIE A LUCRARILOR; CLUJ - ORADEA OGRA DRUM DE LEGATURA EXECUTIE - 22 IULIE 2020 TVA ANTREPRENOR/ CNAIR SA 108 LUNI (9 ANI) - PERIOADA DE GARANTIE A LUCRARILOR; (4.7 KM) LUCRARILE PENTRU REALIZAREA ACESTUI SECTOR DE AUTOSTRADA PREVAD SI CONSTRUCTIA A 3 PODURI SI PASAJE PE DRUMURI DE LEGATURA, 6 PODURI SI PASAJE PE AUTOSTRADA, PRECUM SI DOUA NODURI RUTIERE PENTRU CONECTAREA AUTOSTRAZII LA RETEAUA DE DRUMURI EXISTENTA.

IN DATA DE 31.08.2020, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL "PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA BUCURESTI KM 0+000-KM 100+900, SECTOR CENTURA NORD KM 0+000-KM 52+770, LOT 4 KM 47+600 - KM 52+070”, CU OFERTANTUL DECLARAT CASTIGTOR, ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L. VALOAREA CONTRACTULUI: 312.633.554,09 LEI FARA TVA. LUNGIME: 4.47 KM AUTOSTRADA DE CENTURA A ASOCIEREA S.C. SA&PE CONSTRUCT S.R.L. - S.C. 312.63 MIL. LEI FARA 6 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 47+600 52+070 SECTOR NORD LOT 4 4.47 0% 0% 2021 2024 ESTIMAT TRIM. IV 2024 SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE. MUNICIPIULUI BUCURESTI (A0) SPEDITION UMB S.R.L. - S.C. TEHNOSTRADE S.R.L. TVA DURATA CONTRACTULUI ESTE DE 150 LUNI, DIN CARE: 12 LUNI PERIOADA DE PROIECTARE, 18 LUNI PERIOADA DE EXECUTIE A LUCRARILOR 120 LUNI PERIOADA DE GARANTIE A LUCRARILOR

IN DATA DE 12.05.2021, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL "PROIECTARE SI EXECUTIE AUTOSTRADA DE CENTURA BUCURESTI KM 0+000-KM 100+900, SECTOR CENTURA NORD KM 0+000-KM 52+770, LOT 2 KM 20+000 - KM 39+000”, CU OFERTANTUL DECLARAT CASTIGTOR, ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE S.R.L. VALOAREA CONTRACTULUI: 831.920.653,34 LEI FARA TVA. LUNGIME: 19 KM ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER AUTOSTRADA DE CENTURA A 831.92 MIL. LEI FARA SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE. 7 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 20+000 39+000 DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE SECTOR NORD LOT 2 19 0% 0% 2021 2024 ESTIMAT TRIM. IV 2024 MUNICIPIULUI BUCURESTI (A0) TVA DURATA CONTRACTULUI ESTE DE 154 LUNI, DIN CARE: S.R.L. 12 LUNI PERIOADA DE PROIECTARE, 22 LUNI PERIOADA DE EXECUȚIE A LUCRĂRILOR 120 LUNI PERIOADA DE GARANȚIE A LUCRĂRILOR A FOST EMIS ORDIN DE INCEPERE IN DATA DE 16.08.2021

10.04.2019 - ORDIN DE ORDIN DE INCEPERE A LUCRARILOR 18.08.2020 ETAPA 1: KM 69+000 - KM 70+700 INCEPERE A ACTIVITATII DE DECIZIA PENTRU EXPROPRIERI AFERENTA HG 675/2020 A FOST EMISA IN DATA DE 15.10.2020 29.11% - PROGRES FINANCIAR AUTOSTRADA DE CENTURA A LOT 2: VIDRA - PROIECTARE 750.85 MIL. LEI FARA A FOST ACORDAT AVANSUL PENTRU EXECUTIE LUCRARI (15% DIN VALOAREA LUCRARILOR) 8 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 69+000 85+300 ALSIM ALARKO SANAYI TESISLERI VE TICARET A.S. SECTOR SUD 16.3 25.00% (INCLUSIV AVANS LUCRARI SI FEBRUARIE 2023 FEBRUARIE 2023 MUNICIPIULUI BUCURESTI (A0) BRAGADIRU 18.08.2020 - ORDIN INCEPERE TVA ORDINUL DE INCEPERE PENTRU ETAPA 2, CONSTAND IN INTREG ALINIAMENTUL LOTULUI 2, A FOST EMIS IN DATA DE 29.10.2020, DATA DE INCEPERE FIIND 05.11.2020 (14,6 KM) ACTUALIZARI PRETURI) LUCRARI KM 69+000 - KM A FOST PUBLICAT IN MONITORIUL OFICIAL HG NR. 1139/30.12.2020 PRIVIND IMOBILELE AFLATE PE CULOARUL SUPLIMENTAR, INCLUSIV DECIZIA DE EXPROPRIERE NR. 378/17.02.2021. 70+700 IN DATA DE 12.03.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE NR. 11 PENTRU ETAPA III, EXPROPRIERI SUPLIMENTARE

SECTOR NORD - KM 52+070 – 03.10.2019 - DATA DE A FOST EMISA AUTORIZATIA DE CONSTRUIRE NR. 66/25.11.2020 AUTOSTRADA DE CENTURA A 19.73% - PROGRES FINANCIAR 830.68 MIL. LEI FARA 9 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 52+070 69+000 ALSIM ALARKO SANAYI TESISLERI VE TICARET A.S. KM 52+770; SECTOR SUD - KM LOT 1: GLINA - VIDRA 16.93 8.60% INCEPERE A ACTIVITATII DE IUNIE 2023 ANUL 2023 A FOST APROBAT PROIECTUL TEHNIC DE EXECUTIE IN DATA DE 11.02.2021. MUNICIPIULUI BUCURESTI (A0) (INCLUSIV AVANS LUCRARI) TVA 52+770 – KM 69+000 PROIECTARE ORDIN DE INCEPERE LUCRARI 01.03.2021

IN PREZENT ANTREPRENORUL A REUSIT SA FINALIZEZE DECLARATIA DE PROIECTARE (INREGISTRAND INTARZIERI MAJORE IN ACTIVITATEA DE PROIECTARE), FIIND PENALIZAT CONFORM CONTRACTULUI PENTRU NEINDEPLINIREA 85+300 - 0+000 - ASOCIEREA AKTOR TECHNICAL SOCIETE SECTOR SUD - KM 85+300 - KM 1,03% (PROGRES FINANCIAR 23.05.2019 - DATA DE AUTOSTRADA DE CENTURA A LOT 3: BRAGADIRU - 853.42 MIL. LEI FARA PUCTULUI DE REFERINTA NR 1 (FINALIZAREA DECLARATIEI DE PROIECTARE). 10 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA 100+765 2+500 ANONYME (AKTOR S.A.) - S.C. EURO CONSTRUCT 100+765; SECTOR NORD - KM 17.965 0.00% INCLUSIV AVANS INCEPERE A ACTIVITATII DE DECEMBRIE 2022 DECEMBRIE 2022 MUNICIPIULUI BUCURESTI (A0) JOITA TVA PAC A FOST ANALIZAT SI APROBAT IN CADRUL CTE CNAIR IN DATA DE 11.06.2021. SUD NORD TRADING 98 S.R.L. 0+000 + KM 2+500 PROIECTARE) PROIECTARE LA DATA PREZENTEI, ANTREPRENORUL IMPLEMENTEAZA LA NIVELUL PTE OBSERVATIILE CONSULTANTULUI.

TERMENUL DE FINALIZARE A LUCRARILOR (ESTIMAT PENTRU 30.10.2021) ESTE COMUNICAT DE CATRE ANTREPRENOR, CARE DORESTE DESCHIDEREA TRAFICULUI, RECEPTIA LA TERMINAREA LUCRARILOR FIIND ESTIMATA PENTRU APRILIE 2022.

CONTRACT PROIECTARE SI EXECUTIE CU INTARZIERI MAJORE INREGISTRATE, DATORATE SLABEI MOBILIZARI A CONSTRUCTORULUI DIN ANII ANTERIORI, DAR SI DIN PREZENT, DATORATA LIPSEI RESURSELOR FINANCIARE PROPRII ASOCIEREA AKTOR TECHNICAL SOCIETE APRILIE 2022 - CONFORM PENTRU SUSTINEREA SANTIERULUI; ESTIMARE DESCHIDERE TRAFIC - 549.33 MIL. LEI FARA 11 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA SEBES - TURDA 17+000 41+250 ANONYME (AKTOR S.A.) - S.C. EURO CONSTRUCT SANTIMBRU - AIUD LOT 2 24.25 88.78% 87.74% 02.12.2014 GRAFIC DE LUCRARI PE ROLUL INSTANTELOR, SE AFLA DOUA DOSARE PRIVIND CONTESTATII ALE UNOR EXECUTARI SILITE PENTRU IMOBILELE NECESARE EXECUTIEI LUCRARILOR. STADIU PROCESUAL: FOND. NOIEMBRIE 2021 TVA TRADING 98 S.R.L. IN DATA DE 18.06.2021, ANTREPRENORUL SI-A ASUMAT SOLUTIA FINALA IN VEDEREA STABILIZARII NECESARE IN ZONA KM 19+300, IN BAZA EXPERTIZEI TEHNICE REALIZATA DE ACESTA. CNAIR SA VA FACE O CONTRAEXPERTIZA, CARE SA VERIFICE CAUZELE ALUNECARII DE TEREN.

APLICARE MECANISM PREVAZUT DE OUG 7/ 2016 PENTRU PLATA CAD NR. 1 - IN DATA DE 28.06.2021, AU FOST APROBATE DE CATRE ORDONATORUL PRINCIPAL DE CREDITE DOCUMENTELE PREVAZUTE PRIN ORDINUL MT 205/ 2021 . IN DATA DE 30.06.2021, A FOST EFECTUATA PLATA SUMEI PREVAZUTA PRIN DECIZIA CAD NR. 1 (ESTE INCLUSA IN PROGRESUL FINANCIAR. DESCHIDERE TRAFIC PT: -15,5 KM AUTOSTRADA, - INTEGRAL NOD RUTIER SEBES, - NOD RUTIER ALBA IULIA SUD TERMENUL DE FINALIZARE A LUCRARILOR IN DATA DE 15.08.2021 A FOST COMUNICAT DE CATRE ANTREPRENOR (CARE DORESTE RECEPTIA LA TERMINAREA LUCRARILOR), DAR NU A FOST RESPECTAT. TERMENUL ESTIMAT DE CNAIR - DESCARCARE PRIN NOD RUTIER SA PENTRU RECEPTIA LA TERMINAREA LUCRARILOR ESTE 15.09.2021. DESCHIDERE TRAFIC - ALBA IULIA NORD ASOCIEREA IMPRESA PIZZAROTTI & C SPA 03.12.2020 541.73 MIL. LEI FARA 12 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA SEBES - TURDA 0+000 17+000 LANCRAM - SANTIMBRU LOT 1 17 98.00% 96.62% 02.12.2014 IN DATA DE 30.07.2021. IN DATA DE 03.12.2020 S-A DESCHIS TRAFICUL PE UN TRONSON DE 15.5 KM. IN DATA DE 30.07.2021, A FOST DESCHIS IN INTEGRALITATE TRAFICUL LA NODUL SEBES, CARE FACE LEGATURA INTRE AUTOSTRADA A10 SI A1. POMPONIO CONSTRUCTII SRL FINALIZARE CONTRACT: TVA AUGUST 2021 IN DATA DE 03.12.2020, A FOST DESCHIDEREA TRAFICULUI PE TOATA LUNGIMEA SECTORULUI DE AUTOSTRADA VA AVEA LOC DOAR DUPA FINALIZAREA LUCRARILOR SI PE LOTUL 2, DEOARECE DESCARCAREA TRAFICULUI ESTE POSIBILA DOAR PRIN NODUL ALBA IULIA DESCHIS TRAFICUL DOAR PRIN 2 NORD DE LA KM 15+500. BRETELE ALE NODULUI SEBES SI SECTORUL PANA LA NODUL ALBA IULIA NORD

2025 IN CF CU PREVEDERILE 22.06.2020 – ORDIN DE INCEPERE FAZA PROIECTARE (12 LUNI) CTR DURATA DE REALIZARE A CONTRACT DE SERVICII NR.92/58937/11.09.2020: „SUPERVIZARE AUTOSTRADA – PITESTI, SECTIUNEA 5 – CURTEA DE ARGES – PITESTI KM 92+600-KM 122+950"" SEMNAT CU ASOCIAREA EGIS INTERNATIONAL S.A.S – SEARCH IUNIE 2020 - EMITERE ORDIN ACESTUI CTR ESTE DE 60 DE CORPORATION S.R.L.- ITALROM INGINERIE INTERNATIONALA S.R.L.- METROUL S.A, A INLOCUIT SUPERVIZORUL DRDP BUCURESTI INCEPAND CU DATA DE 01.10.2020 ETAPA DE PROIECTARE, LUNI, RESPECTIV: 12 LUNI IN DATA DE 30.12.2020 A FOST PUBLICATA HOTARAREA DE GUVERN NR.1134 PENTRU REALIZAREA EXPROPRIERILOR PENTRU SUPRAFETELE DE TEREN AFLATE PE AZA LOCALITATILOR BUDEASA, CURTEA DE ARGES, MALURENI SI AUTORIZATIA DE CONSTRUIRE PERIODA DE PROIECTARE SI 48 MUNICIPIUL PITESTI, DIN JUDETUL ARGES. 13 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA SIBIU - PITESTI 91+761 122+110 ASTALDI SPA (ITALIA) CURTEA DE ARGES - PITESTI SECTIUNEA 5 30.35 0% 3.31% NR.31/17.06.2021 ANUL 2025 1710 MIL. LEI FARA TVA DE LUNI PENTRU EXECUTIA 17.02.2021 - S-A EMIS DECIZIA DE EXPROPRIERE NR. 377/2020 PENTRU IMOBILELE DE PE RAZA LOCALITATILOR BUDEASA, CURTEA DE ARGES, MALURENI SI MUN. PITESTI IN DATA DE 01.09.2021 S-A LUCRARILOR. PERIOADA DE PROCEDURA DE EXPROPRIERE INTERGAL FINALIZATA EMIS ORDINUL DE INCEPERE A GARANTIE A LUCRARILOR IN DATA DE 16.06.2021 S-A OBTINUT AUTORIZATIA DE CONSTRUIRE EXECUTIEI LUCRARILOR OFERTATA DE ASTALDI SPA IN DATA DE 01.09.2021 S-A EMIS ORDINUL DE INCEPERE A LUCRARILOR ESTE DE 120 DE LUNI IN DATA DE 16.09.2021, A FOST AVIZAT IN CTE CNAIR PROIECTUL TEHNIC DE EXECUTIE.

PROIECTUL TEHNIC A FOST FINALIZAT SI APROBAT DE CATRE CNAIR SA IN DATA DE 01.04.2020. 29.05.2019 - EMITERE ORDIN SECTIUNEA 1: SIBIU - DE INCEPERE ETAPA DE 612.65 MIL. LEI FARA AUTORIZATIA DE CONSTRUIRE A FOST EMISA IN DATA DE 09.03.2020. 14 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI AUTOSTRADA AUTOSTRADA SIBIU - PITESTI 0+000 13+170 PORR CONSTRUCT SRL LOT 1: KM 0+000 - KM 13+170 BOITA (KM 0+000 - KM 13.17 48.20% 42.49% PROIECTARE, 30.03.2020 - 28.05.2023 ANUL 2023 TVA 14+150), LOT 1 EMITERE ORDIN DE INCEPERE CONTRACT DE SERVICII NR. 92/61673/22.09.2020: „SUPERVIZARE AUTOSTRADA SIBIU – PITESTI, SECTIUNEA 1 –SIBIU – BOITA KM 0+000-KM 14+150"" ASOCIEREA TPF INGINERIE S.R.L. - SEPTEMBRIE CONSULTING S.R.L. A INLOCUIT ETAPA EXECUTIE LUCRARI SUPERVIZORUL DRDP BUCURESTI INCEPAND CU DATA DE 19.10.2020

DRUM BRAILA- JIJILA - 19,095 KM; DRUM DE SECTIUNEA 2 DECEMBRIE 2021 ASOCIEREA ASTALDI S.P. A - IHI INFRASTRUCTURE POD SUSPENDAT PESTE DECEMBRIE 2021 SECTIUNEA 2 1.996 MLD. LEI FARA 15 AUTOSTRAZI IN EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI DRUM NATIONAL POD BRAILA 1 LEGATURA CU 46.93% 60.60% 21.12.2018 TOTAL CONTRACT: ESTIMAT CONTRACT IN DERULARE. SYSTEM CO. LTD. DUNARE IN ZONA BRAILA PODUL SUSPENDAT TVA DN22 DECEMBRIE 2022 SMARDAN- MACIN - 4,328 KM

1.2. AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI EXECUTIE LUCRARI - SEPTEMBRIE 2021

PANA LA DETALII NR. CRT. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL STADIUL FINANCIAR ACTUAL DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDERE VALOARE PROIECT OBSERVAȚII (km) PROCEDURĂ

http://www.cnadn r.ro/sites/default/f SUBSECTIUNEA 3C1: iles/AUTOSTRADA SE VA STABILI IN URMA FINALIZARII PROCEDURII SECTIUNEA 3C, SUPLACU DE BARCAU - AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI AUTOSTRADA BRASOV - TARGU MURES - 465.14 MIL. LEI FARA _BRA%C8%98OV_T 1 AUTOSTRADA 4+200 30+550 DE LICITATIE ATRIBUIRE CONTRACT PROIECTARE SUBSECTIUNEA 3C1 SUPLACUL CHIRIBIS *KM 4+200 26.35 0% 0% 2021 2023 ANUL 2023 DETALII PRIVIND PROCEDURA DE ATRIBUIRE A CONTRACTULUI IN LINK-UL DE MAI JOS EXECUTIE LUCRARI CLUJ - ORADEA TVA %C3%82RGU%20M SI EXECUTIE DE BARCAU - CHRIBIS COINCIDE CU KM URE%C8%98_CLUJ 80+054.044 DIN 3B5 _ORADEA_CALEND AR.pdf

SUBSECTIUNEA 3B3: http://www.cnadn SECTIUNEA 3B,SUBSECTIUNEA POARTA SALAJULUI - r.ro/sites/default/f 3B3: POARTA SALAJULUI - ZALAU (KM 25+500 - KM 3926.81 MIL. LEI FARA iles/AUTOSTRADA ZALAU (KM 25+500- KM 40+637) + TVA, DIN CARE AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI AUTOSTRADA BRASOV - TARGU MURES - _BRA%C8%98OV_T 2 AUTOSTRADA 25+500 66+500 40+637) + SUBSECTIUNEA 3B4: SUBSECTIUNEA 3B4: 41 2021 2025 ANUL 2025 VALOAREA TUNELULUI DETALII PRIVIND PROCEDURA DE ATRIBUIRE A CONTRACTULUI IN LINK-UL DE MAI JOS EXECUTIE LUCRARI CLUJ - ORADEA %C3%82RGU%20M ZALAU -NUSFALAU (KM ZALAU - NUSFALAU (KM MESES ESTE DE 1075.36 URE%C8%98_CLUJ 40+660- KM 66+500), INCLUSIV 40+660 - KM 66+500), MIL LEI FARA TVA _ORADEA_CALEND TUNEL RUTIER MESES INCLUSIV TUNEL RUTIER AR.pdf MESES

18.09.2020 - NOD CHETANI (1.3 TRONSON OGRA - CAMPIA KM) - DESCHIDEREA TRAFICULUI ASOCIEREA SC STRACO GRUP SRL & SPECIALIST 37.86% - PROGRES 41.97% - PROGRES 383,44 MIL. LEI FARA IN DATA DE 11.03.2021 S-A TRANSMIS ANTREPRENORULUI INSTIINTAREA DE REZILIERE A CONTRACTULUI. AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI AUTOSTRADA BRASOV - TARGU MURES - TURZII 2021 - INTARZIERI MAJORE ALE 3 AUTOSTRADA 21+500 37+191 CONSULTING SRL & SC TOTAL ROAD SRL - LOT 3 15.691 INREGISTRAT LA DATA INREGISTRAT LA DATA 04.05.2016 CTR REZILIAT - RELICITARE LUCRARI TVA (VALOARE PROCEDURA DE REZILIERE A FOST SUSPENDATA IN URMA DECIZIEI TRIBUNALULUI BUCURESTI. EXECUTIE LUCRARI CLUJ - ORADEA (2A3 CHETANI - CAMPIA CONTRACTULUI DE PROIECTARE CONTRACT REZILIAT REZILIERII REZILIERII ESTIMATA CONTRACT) TURZII) SI EXECUTIE - CONTRACT REZILIAT

842.14 MIL. LEI FARA http://www.cnadn TVA (VALOARE r.ro/sites/default/f ESTIMATA PROCEDURA iles/AUTOSTRADA AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI AUTOSTRADA DE CENTURA A DE LICITATIE) 4 AUTOSTRADA 2+500 20+000 SECTOR NORD LOT 1 17.5 0% 0% 2021 2024 ESTIMAT TRIM. IV 2024 RAPORTUL PROCEDURII DE ACHIZITIE PUBLICA A FOST CONTESTAT _DE_CENTURA_A_ EXECUTIE LUCRARI MUNICIPIULUI BUCURESTI (A0) 746.763.568,57 LEI, MUNICIPIULUI_BU FARA TVA (VALOARE CURE%C8%98TI_C OFERTA ALENDAR.pdf CASTIGATOARE)

http://www.cnadn r.ro/sites/default/f iles/AUTOSTRADA AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI AUTOSTRADA DE CENTURA A 466.28 MIL. LEI FARA 5 AUTOSTRADA 39+000 47+600 SECTOR NORD LOT 3 8.5 0% 0% 2021 2024 ESTIMAT TRIM. IV 2024 RAPORTUL PROCEDURII DE ACHIZITIE PUBLICA A FOST CONTESTAT _DE_CENTURA_A_ EXECUTIE LUCRARI MUNICIPIULUI BUCURESTI (A0) TVA MUNICIPIULUI_BU CURE%C8%98TI_C ALENDAR.pdf TERMEN DEPUNERE OFERTE PROCEDURA DE ATRIBUIRE CONTRACT DE PROIECTARE SI EXECUTIE - 27.11.2020 PANA LA TERMENUL LIMITA AU DEPUS OFERTE 15 AGENTI ECONOMICI. VALOAREA ESTIMATA A CONTRACTULUI ESTE DE 5.324.779.469,00 LEI FARA TVA. DURATA CONTRACTULUI ESTE DE: 14 LUNI PERIOADA DE PROIECTARE, 59 LUNI PERIOADA DE EXECUTIE ŞI 60 LUNI PERIOADA DE GARANTIE A LUCRARILOR. TRASEUL ARE O LUNGIME DE 37.4 KM http://www.cnadn SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE. r.ro/sites/default/f AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI 4784.02 MIL. LEI FARA 6 AUTOSTRADA AUTOSTRADA SIBIU - PITESTI 44+500 81+900 CORNETU - TIGVENI SECTIUNEA 3 37.4 0% 0% 2022 2025 ANUL 2025 PRINCIPALELE LUCRARI ALE ACESTEI SECTIUNI SUNT: iles/AUTOSTRADA EXECUTIE LUCRARI TVA • 95 DE PODURI SI PASAJE _SIBIU_PITE%C8%9 • TUNEL CU DOUA GALERII INDEPENDENTE IN LUNGIME DE 1.7 KM/ GALERIE 8TI_CALENDAR.pdf • NOD RUTIER CORNETU SI NOD RUTIER VALENI • ECODUCT IN ZONA LOCALITATII CALINESTI

http://www.cnadn SECTIUNEA 1: SIBIU - r.ro/sites/default/f AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI SECTIUNEA 1, LOT 2 SI BOITA, LOT 2 SI 4081.78 MIL. LEI FARA 7 AUTOSTRADA AUTOSTRADA SIBIU - PITESTI 13+170 44+500 31.33 0% 0% 2022 2025 ANUL 2025 DETALII PRIVIND PROCEDURA DE ATRIBUIRE A CONTRACTULUI IN LINK-UL DE MAI JOS iles/AUTOSTRADA EXECUTIE LUCRARI SECTIUNEA 2 SECTIUNEA 2: BOITA - TVA _SIBIU_PITE%C8%9 CORNETU 8TI_CALENDAR.pdf IN DATA DE 03.09.2021, A FOST COMUNICAT OFERTANTUL DESEMNAT CAȘTIGĂTOR - S.C. PORR CONSTRUCT S.R.L. CU PREŢUL DE 1.678.873.121,77 LEI FĂRĂ TVA. http://www.cnadn DURATA CONTRACTULUI ESTE DE 60 DE LUNI, DIN CARE 16 LUNI PERIOADA DE PROIECTARE ȘI 44 LUNI PERIOADA DE EXECUȚIE A LUCRĂRILOR, ESTIMAT 2025 IN FUNCTIE DE DATA r.ro/sites/default/f AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI 2000.17 MIL. LEI FARA PERIOADA DE GARANȚIE A LUCRĂRILOR ESTE DE 60 DE LUNI. 8 AUTOSTRADA AUTOSTRADA SIBIU - PITESTI 81+900 91+761 TIGVENI - CURTEA DE ARGES SECTIUNEA 4 9.86 0% 0% 2021 2025 LA CARE VA FI FINALIZATA iles/AUTOSTRADA EXECUTIE LUCRARI TVA OBIECTUL CONTRACTULUI ÎL REPREZINTĂ PROIECTAREA ȘI EXECUȚIA LUCRĂRILOR PENTRU CONSTRUCȚIA AUTOSTRĂZII SIBIU - PITESTI, SECTIUNEA 4: TIGVENI - CURTEA DE ARGES ÎN LUNGIME DE 9,86 KM. PROCEDURA DE ATRIBUIRE _SIBIU_PITE%C8%9 SEMNAREA CONTRACTULUI DE ACHIZIȚIE PUBLICĂ VA FI POSIBILĂ DUPĂ EXPIRAREA DIN NOU A PERIOADEI DE DEPUNERE A EVENTUALELOR CONTESTAȚII ȘI RESPECTIV DUPĂ SOLUȚIONAREA TUTUROR CONTESTAȚIILOR/PLÂNGERILOR 8TI_CALENDAR.pdf FORMULATE ÎN CADRUL PROCEDURII DE ATRIBUIRE.

http://www.cnadn r.ro/sites/default/f ORDIN DE INCEPERE AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI 1146.6 MIL. LEI FARA A FOST LANSATA PROCEDURA DE LICITATIE PENTRU ATRIBUIREA CONTRACTULUI DE EXECUTIE LUCRARI 01.06.2021. TERMEN DE DEPUNERE A OFERTELOR 04.08.2021. iles/A7%20PLOIE% 9 AUTOSTRADA AUTOSTRADA PLOIESTI - BUZAU 0+000 63+250 PLOIESTI - BUZAU 63.25 12.11.2018 - ETAPA 2021 EXECUTIE LUCRARI TVA DETALII PROCEDURĂ DE ACHIZIȚIE ÎN LINK-UL DE MAI JOS: C8%98TI%20- PROIECTARE %20BUZ%C4%82U. pdf

AU FOST DEPUSE NOUA CANDIDATURI PENTRU REALIZAREA ACESTEI PORTIUNI, DINTRE CARE SASE APARTIN UNOR ASOCIERI DE FIRME:

AKTOR S.A. (GRECIA) 1560.50 MIL LEI FARA ASOCIEREA SC ALSIM ALARKO SANAYI TESISLERI VE TICARET A.Ș – MAKYOL INSAAT SANAYI TURIZM VE TICARET A.S. (TURCIA) 1. FINALIZAT SECT. A - C (KM TVA - REPREZINTA VAL ASOCIEREA FCC CONSTRUCCION SA – GULERMAK AGIR SANAYI INSAAT VE TAAHHUT A.S. (SPANIA – TURCIA) http://www.cnadn MARGINA - HOLDEA 28.6 (9.13 KM 27+620 - KM 43+060); ESTIMATA TOTALA, ASOCIEREA IMPRESA PIZZAROTTI & CSPA – PIZZAROTTI SA – RETTER PROJECT MANAGEMENT SRL (ITALIA – ) r.ro/sites/default/f AUTOSTRAZI IN LICITATIE FAZA EXECUTIE / PROIECTARE SI SECTIUNEA E (KM 47+090 - KM SECTIUNEA E SI 2. SECTIUNEA E SI REST DE CARE CONTINE ATAT 10 AUTOSTRADA AUTOSTRADA - DEVA 27+620 56+220 LOT 2 27.11.2013 ANUL 2025 ASOCIEREA TERNA SA – INTRACOM CONSTRUCTIONS SOCIETE ANONYME TECHNICAL AND STEEL CONSTRUCTIONS (INTRAKAT) (GRECIA) iles/AUTOSTRADA EXECUTIE LUCRARI 56+220) SI FINALIZARE FINALIZARE EXECUTAT DIN SECTIUNEA D VAL ESTIMATA A KOLIN INSAAT TURIZM SANAYI VE TICARET ANONIM SIRKETI (TURCIA) _LUGOJ_DEVA_CAL SECTIUNEA D SECTIUNE D) (KM 43+060 - KM 56+220) - LUCRARILOR, CAT SI VAL ASOCIEREA MAPA INSAAT VE TICARET A.S. – CENGIZ INSAAT SANAYI VE TICARET A.S. (TURCIA) ENDAR.pdf ESTIMAT DECEMBRIE 2023 POSIBILELOR LUCRARI ASOCIEREA RIZZANI DE ECCHER SPA – OZGUN INSAAT TAAHHUT SANAYI VE TICARET LIMITED STI – CIPA SPA (ITALIA – TURCIA) NOI SIMILARE STRABAG SRL (ROMANIA)

DETALII PRIVIND CALENDARUL PROCEDURII SE VOR VIZUALIZA LA LINK-UL DE MAI JOS:

1.3. AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) - SEPTEMBRIE 2021

PANA LA DETALII NR. CRT. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL STADIUL FINANCIAR ACTUAL DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDERE VALOARE PROIECT OBSERVAȚII (km) PROCEDURĂ

22.05.2020 - DATA SEMNARII DURATA CONTRACTULUI ESTE DE 30 LUNI. SEARCH CORPORATION& PRIMACONS GRUP SRL - CONTRACTULUI DE PRESTARI ORDINUL DE INCEPERE: 10.07.2020 CONTRACT PROIECTARE ELABORARE STUDIU DE SERVICII DE PROIECTARE 2023 - FINALIZARE PROIECTARE ANUL 2023 - FINALIZARE PROIECTARE 8858.21 MIL. LEI FARA PRESTATORUL A ELABORAT ANALIZA MULTICRITERIALA PRIVIND ALEGEREA ALTERNATIVELOR DE TRASEU, ETAPA 1. 1 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA BRASOV - BACAU 0+000 165+000 FEZABILITATE SI PROIECT TEHNIC BRASOV - BACAU LOT 1 165 0% 0% (STUDIU DE FEZABILITATE SI (SF+PT) (SF+PT) TVA A FOST AVIZAT IN CTE CNAIR SA - ANALIZA MULTICRITERIALA ETAPA 1. (VALOARE CONTRACT PROIECTARE: ELABORARE PROIECT TEHNIC) AU FOST FINALIZATE STUDIILE DE TEREN AFERENT PROIECTULUI PRELIMINAR (STUDII TOPOGRAFICE SI GEOTEHNICE). 20.093.359,86 LEI FARA TVA) 10.07.2020 - ORDIN INCEPERE A FOST INAINTATA ANALIZA MULTICRITERIALA NR. 2, IN ANALIZA ETAPA DE PROIECTARE

A1(KM 326+155) - DJ 704(CUGHIR),A1(KM CONTRACT SEMNAT IN DATA DE 17.03.2021 362+813) - DC ELABORARE STUDIU DE ORDINUL DE INCEPERE A ACTIVITATII DE PROIECTARE A FOST EMIS IN DATA DE 22.04.2021 129(SANTUHALM),A1(K FEZABILITATE SI PROIECT DURATA CONTRACTULUI ESTE DE 14 LUNI DE LA DATA DE INCEPERE A CONTRACTULUI, DIN CARE: M 485+030 - DJ TEHNIC DE EXECUTIE PENTRU -6 LUNI PENTRU ELABORAREA STUDIULUI DE FEZABILITATE, 2 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA A1 SI A3 SEARCH CORPORATION SRL 609E(RECAS),A1(KM 0% 0% 22.04.2021 22.06.2022 6 NODURI RUTIERE PE A1 SI - 4 LUNI PENTRU REALIZAREA PROIECTULUI PENTRU AUTORIZAREA LUCRARILOR DE CONSTRUIRE, 450+210) - DJ A3 IN ZONA DE VEST A - 3 LUNI PENTRU ELABORAREA PROIECTULUI TEHNIC DE EXECUTIE SI 609(BETTHAUSEN),A1(K ROMANIEI - 1 LUNI PENTRU ACORDAREA SERVICIILOR DE ASISTENTA TEHNICA BENEFICIARULUI. M 528+509) - DJ A AVUT LOC SEDINTA DE INCEPUT IN DATA DE 22.04.2021. A FOST TRANSMIS RAPORTUL DE INCEPUT. AU FOST FORMULATE OBSERVATII LA RAPORTUL DE INCEPUT. 682G(CRUCENI),A3(KM 39+940) - DN1P(SPINUS)

IN DATA DE 08.04.2021 A FOST SEMNAT CONTRACTUL DE SERVICII „COMPLETARE/ REVIZUIRE/ ACTUALIZARE STUDIU DE FEZABILITATE SI ELABORARE P.A.C., P.A.D. SI P.T.E. PENTRU OBIECTIVUL „AUTOSTRADA TARGU-NEAMT – IASI – UNGHENI” CU SC CONSITRANS S.R.L. 58.83 MIL. LEI FARA TVA PRETUL CONTRACTULUI ESTE DE 58.830.448,35 LEI FARA TVA 2021 -SERVICII DE PROIECTARE (VALOARE CONTRACT IN DATA DE 07.05.2021 A AVUT LOC SEDINTA DE INCEPUT ANUL 2025 - PERIOADA ESTIMATA AUTOSTRADA TARGU NEAMT - IASI - TARGU NEAMT - IASI FAZA S.F. + P.A.C. + P.T.E. 2023 - FINALIZARE PROIECTARE COMPLETARE/REVIZUIR IN PREZENT SE AFLA IN DERULARE ACTIVITATI DE ELABORARE A ANALIZEI MULTICRITERIALE DE TRASEU 3 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA 0+000 100+140 SC CONSITRANS S.R.L. 100.14 DESCHIDERE TRAFIC PENTRU PRIMELE UNGHENI (LETCANI) - UNGHENI SECTIUNE TARGU NEAMT - IASI- E/ACTUALIZARE S.F. SI SECTIUNI UNGHENI ELABORARE P.A.C. + DURATA DE REALIZARE A SERVICIILOR DE PROIECTARE ESTE DUPA CUM URMEAZA: P.A.D. + P.T.E) 12 LUNI PENTRU REALIZAREA STUDIULUI DE FEZABILITATE; 5 LUNI PENTRU REALIZAREA PROIECTULUI PENTRU AUTORIZAREA EXECUTARII LUCRARILOR DE CONSTRUIRE (PAC) SI OBTINEREA AUTORIZATIEI DE CONSTRUIRE; 5 LUNI PENTRU REALIZAREA PROIECTULUI TEHNIC DE EXECUTIE (PTE)

CONSITRANS TRIM III 2021/ FINALIZARE ORDIN DE INCEPERE FINALIZARE PROIECTARE (EMITERE 4 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA SIBIU - BRASOV 0+000 68+050 (VALOARE CONTRACT PROIECTARE: SIBIU - FAGARAS LOT 1 68.05 22.00% PROIECTARE FAZA REVIZUIRE 5170 MIL. LEI FARA TVA CONTRACT REVIZUIRE STUDIU DE FEZABILITATE IN DERULARE - STUDIUL DE FEZABILITATE A FOST AVIZAT IN CADRUL CTE, PROCEDURA DE MEDIU IN DERULARE 11.05.2015 ACORD DE MEDIU) - TRIM. III 2021 16.313.855,49 FARA TVA) STUDIU DE FEZABILITATE

IN DATA DE 23.08.2021, CNAIR A SEMNAT CONTRACTUL PENTRU „COMPLETARE STUDIU DE FEZABILITATE ȘI PROIECT TEHNIC PENTRU "AUTOSTRADA BRAȘOV - FĂGĂRAȘ”, CU OFERTANTUL DECLARAT CÂȘTIGĂTOR ASOCIEREA SEARCH CORPORATION S.R.L. - PROTELCO S.A. - LIKE CONSULTING S.R.L. – MEGA MUHENDISLIK MUSAVIRLIK A.S. (MEGA ENGINEERING CONSULTING INC.). VALOAREA CONTRACTULUI ESTE DE 18.174.952,71 LEI FĂRĂ TVA. SURSA DE FINANȚARE: FONDURI EUROPENE NERAMBURSABILE. CONTRACTUL DE SERVICII ESTE STRUCTURAT ASTFEL: http://www.cnadn • ETAPA I: 25 LUNI r.ro/sites/default/f ASOCIEREA SEARCH CORPORATION S.R.L. - STUDIU DE FEZABILITATE: 22 LUNI iles/STUDII_DE_FE PROTELCO S.A. - LIKE CONSULTING S.R.L. – MEGA 5 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA SIBIU - BRASOV 0+000 48+410 FAGARAS - BRASOV LOT 2 48.41 0% 0% 2021 2023 18.17 MIL LEI FARA TVA PROIECT PENTRU AUTORIZAREA EXECUTĂRII LUCRĂRILOR DE CONSTRUIRE (P.A.C.) ȘI ZABILITATE_%C8% MUHENDISLIK MUSAVIRLIK A.S. (MEGA ASISTENȚĂ TEHNICĂ ACORDATĂ BENEFICIARULUI PENTRU SUSŢINEREA APLICAŢIEI DE FINANŢARE: 3 LUNI 98I_PROIECTE_TEH ENGINEERING CONSULTING INC.) • ETAPA II: 6 LUNI NICE_CALENDAR.p PROIECT TEHNIC (P.T.): 3 LUNI df ASISTENȚĂ TEHNICĂ ACORDATĂ BENEFICIARULUI PENTRU PROCEDURA DE ATRIBUIRE A EXECUŢIEI LUCRĂRILOR: 2 LUNI RAPORT FINANCIAR FINAL: 1 LUNĂ. • ETAPA III: 36 LUNI ASISTENȚĂ TEHNICĂ ACORDATĂ BENEFICIARULUI PE DURATA EXECUŢIEI LUCRĂRILOR, CU CONDIŢIA DEMARĂRII LUCRĂRILOR NU MAI TÂRZIU DE 3 ANI DE LA APROBAREA PROIECTULUI TEHNIC. IN DATA DE 28.05.2019 A FOST SEMNAT CONTRACTUL DE SERVICII 92/36788 AFERENT „COMPLETARE STUDIU DE FEZABILITATE PENTRU AUTOSTRADA TARGU MURES – TARGU NEAMT”. TERMEN INITIAL DE FINALIZARE A REVIZUIRII STUDIULUI DE FEZABILITATE - 25.01.2021. CONTRACT DE REVIZUIRE SF IN DERULARE IN DATA DE 31.07.2020 A FOST SEMNAT ADITIONALUL NR. 1, PRIN CARE SE PRELUNGESTE TERMENUL DE FINALIZARE AL SERVICIILOR DE PROIECTARE CU 6 LUNI. TERMEN DE FINALIZARE CONFORM ACT ADITIONAL - 25.07.2021 EMITEREA DECIZIEI ETAPEI DE INCADRARE INITIALE ANPM IN DATA DE 18.09.2020. IN DATA DE 31.09.2020 A AVUT LOC SEDINTA PENTRU AVIZAREA IN CTE / CNAIR A TRASEULUI CORECTAT CONFORM CONSTRANGERILOR IDENTIFICATE. PENTRU FINALIZAREA AVIZARII CTE A FOST SOLICITATA COMPLETAREA 25.07.2021 (CONFORM ACT ANUL 2021 - FINALIZARE PROIECTARE DOCUMENTATIEI. AUTOSTRADA TARGU MURES - TARGU PROIECTANT: INGENIERIA ESPECIALIZADA OBRA TARGU MURES - TARGU 6 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA 0+000 211+000 LOT 1 211 52% 11% 28.05.2019 ADITIONAL LA CTR DE PRESTARI 2025 - PERIOADA ESTIMATA PENTRU 17.58 MIL. LEI FARA TVA IN DATA DE 05.11.2020 A FOST AVIZAT TRASEUL FINAL IN COMISIA CTE CNAIR. NEAMT CIVIL E INDUSTRIAL SA NEAMT SERVICII) DESCHIDEREA PRIMELOR SECTIUNI IN DATA DE 27.01.2021 A FOST APROBAT STUDIU TOPOGRAFIC. MASURATORI TOPOGRAFICE CU TEHNOLOGIA LIDAR IN DATA DE 25.03.2021 A FOST APROBAT STUDIUL GEOTEHNIC AFERENT TRONSON: DITRAU - TARGU NEAMT, SECTOR 4 KM 95+600 – KM 118+800. AU FOST FINALIZATE INVESTIGATIILE IN SITU PE JUD. MURES SI JUD. HARGHITA SI AU FOST AVIZATE STUDIILE ARHEOLOGICE ETAPA 2 JUD. HARGHITA SI JUD. MURES - IN DATA DE 16.04.2021 A FOST INAINTATA O VARIANTA PRELIMINARA A STUDIULUI DE FEZABILITATE AU FOST FINALIZATE INVESTIGATIILE IN SITU PE JUD. NEAMT SI JUD. IASI SI AU FOST AVIZATE STUDIILE ARHEOLOGICE ETAPA 2 JUD. NEAMT SI JUD. IASI A FOST EMISA DECIZIA ETAPEI DE INCADRARE CU NR. 90 DIN 22.06.2021 AU FOST FINALIZATE INVESTIGATIILE GEOTEHNICE IN TEREN. IN DATA DE 09.08.2021 A FOST INAINTAT STUDIUL DE FEZABILITATE PENTRU AUTOSTRADA TARGU MURES-TARGU NEAMT_REV1. IN PREZENT ACESTA FIIND IN ANANLIZA IN CADRUL CNAIR SA SEARCH CORPORATION & EGIS ROMANIA- MAI 2022 - TERMEN FINALIZARE ETAPA DE PROIECTARE (ELABORARE STUDIU DE FEZABILITATE) IN DERULARE. CONTRACT PROIECTARE ELABORARE SF SEMNAT PROIECTARE; PERIOADA MAI 2022 - TERMEN FINALIZARE S-A AVIZAT IN CTE-CNAIR ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU, ETAPA 1 7 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA TIMISOARA - MORAVITA 0+000 60+000 IN DATA DE 4 MARTIE 2020 TIMISOARA – MORAVITA LOT 1 60 04.03.2020 - ELABORARE SF 141.6 MIL. LEI FARA TVA CONTRACTUALA DE PRESTARE PROIECTARE A FOST TRANSMISA DOCUMENTATIA AMC ETAPA 2. (VALOARE CONTRACT PROIECTARE: 8.727.474,68 A SERVICIILOR - 24 LUNI DOCUMENTATIA AMC 2 A FOST REVIZUITA CONFORM OBSERVATIILOR JASPERS SI SE ASTEAPTA PREDAREA AMC 2 DE CATRE PRESTATOR. FARA TVA)

INGINERIA ESPECIALIZADA OBRA CIVIL E ACTIVITATE DE PROIECTARE IN DERULARE/ FINALIZARE ANALIZA MULTICRITERIALA, AVIZARE IN CTE/ STABILIRE PROFIL DE AUTOSTRADA INDUSTRIAL SA - CONTRACT ELABORARE SF SI PT ORDIN DE INCEPERE ANUL 2021 - FINALIZARE ETAPA 1750.27 MIL. LEI FARA AU FOST INAINTATE OBSERVATII PENTRU STUDIU DE FEZABILITATE, 8 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA BACAU - PASCANI 0+000 77+394 IN DERULARE BACAU - PASCANI LOT 1 77.283 0% 23% 01.03.2019 - ETAPA 2021 PROIECTARE TVA A FOST EFECTUATA EVALUAREA DE IMPACT ASUPRA SIGURANTEI RUTIERE. (VALOARE CONTRACT PROIECTARE: PROIECTARE IN DATA DE 16.07.2021 A FOST INAINTAT STUDIUL DE FEZABILITATE REVIZUIT. 16.950.944,23 FARA TVA)

CONTRACT PROIECTARE IN DERULARE - ETAPA ELABORARE STUDIU DE FEZABILITATE ANALIZA MULTICRITERIALA ETAPA 1 SI ETAPA 2. CONSITRANS - CONTRACT ELABORARE SF SI PT ORDIN DE INCEPERE A FOST AVIZAT IN CADRUL CTE CNAIR STUDIUL SI RAPORTUL ALTERNATIVELOR DE TRASEU (AMC 1 SI AMC 2) 1270.62 MIL. LEI FARA 9 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA BUZAU - FOCSANI 0+000 82+440 (VALOARE CONTRACT PROIECTARE: BUZAU - FOCSANI 82.44 10.35% 12.11.2018 - ETAPA 2021 FINALIZARE 2021 INVESTIGATIILE GEOTEHNICE AU FOST REALIZATE IN PROPORTIE DE 100%. IN CURS DE ELABORARE TESTELE DE LABORATOR. TVA 13.933.291,10 LEI, FARA TVA) PROIECTARE A FOST AVIZAT IN CADRUL COMISIEI TEHNICE PENTRU SIGURANTA CIRCULATIEI NODURILE RUTIERE SI DOTARILE AUTOSTRAZII. A FOST INAINTAT STUDIUL DE FEZABILITATE - IN CURS DE ANALIZA

ETAPA DE PROIECTARE (ELABORARE STUDIU DE FEZABILITATE) IN DERULARE. S-A AVIZAT IN CADRUL CTE CNAIR SA - STUDIUL SI RAPORTUL ALTERNATIVELOR DE TRASEU (ANALIZA MULTICRITERIALA ETAPA 1 SI ANALIZA MULTICRITERIALA ETAPA 2). CONSITRANS - CONTRACT ELABORARE SF SI PT ORDIN DE INCEPERE AU INCEPUT INVESTIGATIILE ARHEOLOGICE. ANUL 2021 - FINALIZARE ETAPA 1927.35 MIL. LEI FARA 10 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA FOCSANI - BACAU 0+000 96+052 (VALOARE CONTRACT PROIECTARE: FOCSANI - BACAU 96.052 0% 0.37% 10.01.2019 - ETAPA 2021 STUDIILE GEOTEHNICE IN CURS DE REALIZARE-PROCENTUL DE REALIZARE ESTE DE 61%. PROIECTARE TVA 20.123.408,52 LEI, FARA TVA) PROIECTARE STUDIUL ARHEOLOGIC ETAPA NR. 2 A FOST TRANSMIS LA MINISTERELE DE CULTURA DE PE RAZA JUDETELOR VRANCEA SI BACAU IN VEDEREA OBTINERII AVIZELOR. IN DATA DE 09.03.2021 AU FOST ANALIZATE IN CADRUL COMISIEI TEHNICE PENTRU SIGURANTA CIRCULATIEI NODURILE RUTIERE SI DOTARILE AUTOSTRAZII IN DATA DE 05.05.2021 A FOST INAINTAT STUDIUL DE FEZABILITATE SUB FORMA DRAFT- AU FOST EMISE OBSERVATII

Valori estimate: 2.099 http://www.cnadn SECTIUNEA 6, CONEXIUNE DN MIL. LEI FARA TVA - r.ro/sites/default/f 73C CU AUTOSTRADA SIBIU - TIGVENI - CURTEA DE iles/STUDII_DE_FE 11 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA SIBIU - PITESTI 44+800 68+000 PITESTI (NOD TIGVENI) SI SECTIUNEA 6 23.2 0% 0% 2022 2023 ANUL 2023 - FINALIZARE PROIECTARE ARGES DETALII PRIVIND PROCEDURA DE ATRIBUIRE A CONTRACTULUI IN LINK-UL DE MAI JOS ZABILITATE_%C8% MODERNIZARE DN 73C (KM 3.926 MIL. LEI FARA TVA 98I_PROIECTE_TEH 44+800 – KM 68+000) - AUTOSTRADA SIBIU - NICE_CALENDAR.p PITESTI df

2021 - DEMARARE SERVICII DE 2023 - FINALIZARE SERVICII DE CONTRACT IN DERULARE. PLOIESTI - BRASOV (FARA 1000.8 MIL. LEI FARA https://ploiesti- 12 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA AUTOSTRADA PLOIESTI - BRASOV SC CONSITRANS S.R.L. 97.3 0% 0% PROIECTARE FAZA S.F. + P.A.C. PROIECTARE FAZA S.F. + P.A.C. + S-AU EFECTUAT VIZITE IN TEREN CU REPREZENTANTI DIN PARTEA BENEFICIARULUI SI DIN PARTEA PRESTATORULUI PENTRU IDENTIFICAREA EVENTUALELOR CONSTRANGERI. SECTOR RASNOV - CRISTIAN) TVA brasov.ro/ + P.T.E. P.T.E. A FOST APROBAT DE CATRE BENEFICIAR RAPORTUL DE INCEPUT SI RAPORTUL DE PROGRES NR. 1.

2.POD UNGHENI - STUDIU DE FEZABILITATE FINALIZAT CU EXCEPTIA ACORDULUI DE MEDIU ; PROCEDURA DE MEDIU IN DERULARE OBTINERE DEROGARE DE LA ART ART. 23 ALIN. (2) SI ALE ART. 27 ALIN. (1) DIN ORDONANTA DE URGENTA A GUVERNULUI 2016 - DEMARARE PROIECTARE 2021 - FINALIZARE PROIECTARE NR. 57/2007 PRIVIND REGIMUL ARIILOR NATURALE PROTEJATE, PRIN OUG NR. 105/2020, SEMNARE MEMORANDUM IN VEDERE PROMOVARII ACORDULUI BILATERAL ROMANIA-MOLDOVA NECESAR OBTINERII ACORDULUI DE MEDIU. POD UNGHENI; 2020 - FAZA SF, DEMARARE SERVICII ANUL 2024 - DESCHIDERE TRAFIC POD 13 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA S.C. EXPERT PROIECT 2002 S.R.L. POD PESTE PRUT LA UNGHENI 1 80% 45% 0.8 MIL. LEI FARA TVA ESTE IN PREGATIRE LA MTIC ACORDUL BILATEARAL ROMANIA-MOLDOVA. POD PESTE PRUT LA UNGHENI DEMARARE PROIECTARE DE PROIECTARE SI EXECUTIE PESTE PRUT LA UNGHENI IN DATA DE 24.08.2020 A FOST EMISA DECIZIA ETAPEI DE EVALUARE INITIALA DE CATRE A.N.P.M. IASI. SECTIUNEA IASI - UNGHENI POD UNGHENI IN DATA DE 24.08.2020 A FOST EMISA DECIZIA ETAPEI DE INCADRARE INITIALA NR. 133/2020 ANMP . PENTRU CONTINUAREA PROCEDURII DE OBTINERE A ACORDULUI DE MEDIU S-A TRANSMIS MEMORIUL DE PREZENTARE CATRE APM IASI. IN DATA DE 22.02.2021 A FOST EMISA DECIZIA ETAPEI DE INCADRARE NR. 15 DE CATRE APM IASI.

CONTRACT SEMNAT IN DATA DE 23.09.2020. ORDINUL DE INCEPERE A ACTIVITATII DE PROIECTARE A FOST EMIS IN DATA DE 26.10.2020 DURATA CONTRACTULUI ESTE DE 8 LUNI DE LA DATA DE INCEPERE A CONTRACTULUI, DIN CARE: -3 LUNI PENTRU ELABORAREA STUDIULUI DE FEZABILITATE, ELABORARE STUDIU DE - 2 LUNI PENTRU REALIZAREA PROIECTULUI PENTRU AUTORIZAREA LUCRARILOR DE CONSTRUIRE, FEZABILITATE SI PROIECT NOIEMBRIE 2021 - FINALIZAR E 674,39 MIL LEI FARA - 1 LUNI PENTRU ELABORAREA PROIECTULUI TEHNIC DE EXECUTIE SI 14 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA A4 16+700 16+700 SEARCH CORPORATION SRL TEHNIC DE EXECUTIE PENTRU 0% 0% 26.10.2020 NOIEMBRIE 2021 PROIECT TEHNIC TVA - 1 LUNI PENTRU ACORDAREA SERVICIILOR DE ASISTENTA TEHNICA BENEFICIARULUI. NOD RUTIER CUMPANA A4 A AVUT LOC SEDINTA DE INCEPUT IN DATA DE 26.10.2020. (KM 16+700)-DN 39E S-A EMIS ORDINUL ADMINISTRATIV NR. 1 - APROBARE EXPERTI NON CHEIE. CTR SUSPENDAT, ACTIVITATEA FIIND RELUATA INCEPAND CU DATA DE 16.04.2021 A FOST AVIZATA IN CADRUL CTE CNAIR IN DATA DE 20.05.2021 ANALIZA MULTICRITERIALA ETAPA 1. AU FOST FINALIZATE STUDIILE GEOTEHNICE, TERMENUL ESTIMAT DE PREDARE A STUDIULUI DE FEZABILITATE ESTE 31 AUGUST 2021 SI ELABORARE PROIECT TEHNIC - NOIEMBRIE 2021

IN DATA DE 10.03.2021, A FOST SEMNAT CONTRACTUL NR. 92/19393 – ELABORARE S.F DRUM DE MARE VITEZA BISTRITA-: LOT 2 BISTRITA – VATRA DORNEI. DURATA CONTRACTULUI ESTE DE 18 LUNI. ORDINUL DE INCEPERE AL CONTRACTULUI ESTE 22.04.2021. IN DATA DE 04.06.2021 A AVUT LOC SEDINTA CU REPREZENTANTII PRIMARIILOR UNITATILOR ADMINISTRATIV TERITORIALE INTERSECTATE DE VARIANTELE DE TRASEU, IN VEDEREA IDENTIFICARII CONSTRANGERILOR. - 14 LUNI AUTOSTRADA BAIA MARE - DEJ - BISTRITA - 15,79 MIL LEI FARA TVA 15 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA SC EXPLAN SRL BISTRITA - VATRA DORNEI LOT 2 83 2021 2022 ANUL 2022 ELABORARE STUDIU DE FEZABILITATE; VATRA DORNEI - SUCEAVA (VALOARE PROIECT SF) - 3 LUNI PREGATIRE DOCUMENTATIE DE ATRIBUIRE A CONTRACTULUI DE PROIECTARE SI EXECUTIE LUCRARI SI ACORDAREA SERVICIILOR DE ASISTENTA TEHNICA BENEFIICIARULUI IN PERIOADA DERULARII PROCEDURII DE LICITATIE SI IN VEDEREA DEPUNERII SI APROBARII APLICATIEI DE FINANTARE DIN FONDURI STRUCTURALE; - 1 LUNA INTOCMIREA RAPORTULUI DE FINALIZARE A SERVICILOR. IN PREZENT SE AFLA IN DERULARE ACTIVITATI DE ELABORARE A ANALIZEI MULTICRITERIALE DE TRASEU IN DATA DE 15.03.2021, A FOST SEMNAT CONTRACTUL NR. 92/20422 ELABORARE S.F DRUM DE MARE VITEZA BISTRITA-SUCEAVA: LOT 3 VATRA DORNEI-SUCEAVA. DURATA CONTRACTULUI ESTE DE 18 LUNI. ORDINUL DE INCEPERE AL CONTRACTULUI ESTE 28.04.2021. IN DATA DE 10.03.2021, A FOST SEMNAT CONTRACTUL NR. 92/19393 – ELABORARE S.F DRUM DE MARE VITEZA BISTRITA-SUCEAVA: LOT 2 BISTRITA – VATRA DORNEI. DURATA CONTRACTULUI ESTE DE 18 LUNI. ASOCIEREA BEST CONSULTING & DESIGN S.R.L. – AUTOSTRADA BAIA MARE - DEJ - BISTRITA - 14,47 MIL LEI FARA TVA ORDINUL DE INCEPERE AL CONTRACTULUI ESTE 22.04.2021. 16 AUTOSTRAZI IN PREGATIRE FAZA PROIECTARE (SF, PT) AUTOSTRADA INGENIERIA ESPECIALIZADA OBRA CIVIL E VATRA DORNEI-SUCEAVA LOT 3 107 2021 2022 VATRA DORNEI - SUCEAVA (VALOARE PROIECT SF) IN DATA DE 04.06.2021 A AVUT LOC SEDINTA CU REPREZENTANTII PRIMARIILOR UNITATILOR ADMINISTRATIV TERITORIALE INTERSECTATE DE VARIANTELE DE TRASEU, IN VEDEREA IDENTIFICARII CONSTRANGERILOR. INDUSTRIAL S.A. - 14 LUNI ELABORARE STUDIU DE FEZABILITATE; - 3 LUNI PREGATIRE DOCUMENTATIE DE ATRIBUIRE A CONTRACTULUI DE PROIECTARE SI EXECUTIE LUCRARI SI ACORDAREA SERVICIILOR DE ASISTENTA TEHNICA BENEFIICIARULUI IN PERIOADA DERULARII PROCEDURII DE LICITATIE SI IN VEDEREA DEPUNERII SI APROBARII APLICATIEI DE FINANTARE DIN FONDURI STRUCTURALE; - 1 LUNA INTOCMIREA RAPORTULUI DE FINALIZARE A SERVICILOR. IN PREZENT SE AFLA IN DERULARE ACTIVITATI DE ELABORARE A ANALIZEI MULTICRITERIALE DE TRASEU

2. DRUMURI EXPRES

2.1 DRUMURI EXPRES PROIECTE IN EXECUTIE - SEPTEMBRIE 2021

PANA LA DETALII NR. CRT. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL STADIUL FINANCIAR ACTUAL DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDERE VALOARE PROIECT OBSERVAȚII (km) PROCEDURĂ

IN DATA DE 15.04.2021, CNAIR A SEMNAT CONTRACTUL PENTRU ""PROIECTAREA SI EXECUTIA DRUMULUI EXPRES BRAILA - GALATI” CU ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE ASOCIEREA SC SA & PE CONSTRUCT SRL (LIDER ORDIN DE INCEPERE S.R.L. 371.42 MIL. LEI FARA 1 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES DRUM EXPRES BRAILA - GALATI 0+000 11+088 DE ASOCIERE) - SPEDITION UMB - TEHNOSTRADE BRAILA - GALATI LOT 1 11.08 0% 0% 01.07.2021 - ETAPA MAI 2024 ANUL 2024 VALOAREA CONTRACTULUI ESTE DE 371.416.131,09 LEI FARA TVA. TVA S.R.L. PROIECTARE SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE. DURATA CONTRACTULUI ESTE DE 34 LUNI, DIN CARE 10 LUNI PERIOADA DE PROIECTARE SI 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR. PERIOADA DE GARANTIE ESTE DE 120 DE LUNI.

SECTOR 1: 0+000 - 1+850 27.12.2018 - PROIECTARE; SECTOR 1: 0+000 - IN DATA DE 03.07.2020 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE. 16.09.2019 - EXECUTIE SECTOR 1+800 INCEPAND CU DATA DE 13.07.2020 A FOST EMIS ORDINUL DE INCEPERE EXECUTIE LUCRARI TRONSON 1 - - 3 ; DRUM EXPRES CRAIOVA - PITESTI SECTOR 2: 1+800 - 358.18 MIL. LEI FARA 2 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES 0+000 17+700 TIRRENA SCAVI S.P.A. (ITALIA) ROBANESTI 17.7 33.05% 25.82% 13.07.2020 - EXECUTIE SECTOR TRIM IV 2022 ANUL 2022 10+000 TVA SECTOR 2: 1+850 - 10+000 (KM 0+000 - KM 17+700) 1; SECTOR 3: 10+000 - A FOST EMISA HG EXPROPRIERE NR. 843/2020 (aporx. de la km 5+190 -km 10+000). IN DATA DE 22.02.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE. 01.03.2021 - EXECUTIE SECTOR 17+700 PENTRU RESTUL ZONELE RAMASE NEEXPROPRIATE URMEAZA A FI INTOCMITA DOC. PENTRU HG DE EXPROPRIERE 2 - km 5+245 - km 10+000 SECTOR 3: 10+000 - 17+700 – IN EXECUTIE

21.12.2018 - ACTIVITATEA DE TRONSON 2 - ROBANESTI - ASOCIEREA SA & PE CONSTRUCT SRL - SC PROIECTARE, 24.09.2019 - DRUM EXPRES CRAIOVA - PITESTI BALS - VALEA MARE (KM LOT 1: KM 17+700 - KM 661.45 MIL. LEI FARA 3 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES 17+700 36+200 SPEDITION UMB SRL - SC TEHNOSTRADE SRL - SC 18.5 88.86% 58.46% EXECUTIE (ETAPELE I, II SI III), TRIM IV 2021 ANUL 2022 17+700 - KM 57+550) 36+200 TVA CONSITRANS SRL 21.11.2019 - EXECUTIE (ETAPA Lot 1 km 17+700 - km 36+200 IV)

TRONSON 2 - ROBANESTI - 21.12.2018 - ACTIVITATEA DE BALS - VALEA MARE (KM ASOCIEREA SA & PE CONSTRUCT SRL - SC PROIECTARE, 24.09.2019 - DRUM EXPRES CRAIOVA - PITESTI 17+700 - 57+550) LOT 2: KM 36+200 - KM 792.18 MIL. LEI FARA 4 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES 36+000 57+500 SPEDITION UMB SRL - SC TEHNOSTRADE SRL - SC 21.35 86.29% 63.33% EXECUTIE (ETAPELE I, II SI III), TRIM IV 2021 ANUL 2022 Lot 2 - km 36+200 - km 57+550 TVA CONSITRANS SRL 21.11.2019 - EXECUTIE (ETAPA 57+550 IV)

CONTRACTUL DE PROIECTARE SI EXECUTIE A FOST SEMNAT IN DATA DE 19.08.2021. DURATA CONTRACTULUI ESTE DE 156 DE LUNI, DIN CARE: ASOCIEREA SA & PE CONSTRUCT SRL - SC TRONSON 4 617.08 MIL. LEI FARA 5 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES DRUM EXPRES CRAIOVA - PITESTI 89+300 121+115 TRONSON 4 31.82 0% 0% 2021 2024 ANUL 2024 • 12 LUNI PERIOADA DE PROIECTARE, SPEDITION UMB SRL - SC TEHNOSTRADE SRL COLONESTI - OARJA - PITESTI TVA • 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR, • 120 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR.

ANTREPRENORUL A CONSTITUIT GARANTIA DE BUNA EXECUTIE, IN CONFORMITATE CU PREVEDRILE CONTRACTUALE, ACEASTA FIIND APROBATA DE CATRE C.N.A.I.R. S.A. IN DATA DE 10.11.2020.

DURATA CONTRACTULUI ESTE DE 156 DE LUNI, DIN CARE: ASOCIEREA SA & PE CONSTRUCT SRL - SC TRONSON 3, VALEA MARE - 670.71 MIL. LEI FARA • 12 LUNI PERIOADA DE PROIECTARE, 6 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES DRUM EXPRES CRAIOVA - PITESTI 57+550 89+300 TRONSON 3 31.75 0% 0% 18.01.2021 2024 ANUL 2024 SPEDITION UMB SRL - SC TEHNOSTRADE SRL COLONESTI TVA • 24 LUNI PERIOADA DE EXECUTIE A LUCRARILOR, • 120 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR. INCEPAND CU DATA DE 18.01.2021 A FOST EMIS ORDIN DE INCEPERE. PAC AVIZAT IN CADRUL CTE IN LUNA MARTIE 2021

IN DATA DE 21.07.2021 A FOST SEMNAT CONTRACTUL DE PROIECTARE SI EXECUTIE CU STRABAG S.R.L. LEGATURA CENTURA ORADEA DURATA CONTRACTULUI ESTE DE 30 DE LUNI, DIN CARE: 7 DRUMURI EXPRES PROIECTE IN EXECUTIE DRUM EXPRES DRUM DE LEGATURA A3 0+000 18+960 SC STRABAG SRL (GIRATIA SANTANDREI) - 18.96 0% 0% 27.09.2021 2024 2024 545.9 MIL. LEI FARA TVA 6 DE LUNI PERIOADA DE PROIECTARE, AUTOSTRADA A3 (BIHARIA) 24 DE LUNI PERIOADA DEEXECUTIE A LUCRARILOR.

2.2 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) - SEPTEMBRIE 2021

PANA LA DETALII NR. CRT. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL STADIUL FINANCIAR ACTUAL DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDERE VALOARE PROIECT OBSERVAȚII (km) PROCEDURĂ

SEPTEMBRIE 2021 - TERMEN CONTRACT ELABORARE SF IN DERULARE. SEARCH CORPORATION & EGIS ROMANIA FINALIZARE PROIECTARE; IANUARIE 2022 - TERMEN FINALIZARE AU FOST TRANSMISE CATRE CNAIR SA VARIANTELE DE TRASEU ANALIZATE IN BAZA STUDIILOR PRELIMINARE - AMC ETAPA 1 REVIZIA 4. MARTIE 2020 - ETAPA 1123.86 MIL. LEI FARA 1 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES BACAU - PIATRA NEAMT 0+000 61+000 (VALOARE CONTRACT PROIECTARE: 8,923,930.03 BACAU - PIATRA NEAMT LOT 1 61 0% 0% PERIOADA CONTRACTUALA DE PROIECTARE (CONFORM AA NR. 1 AMC ETAPA 1 REVIZIA 4 A FOST TRANSMIS CATRE CONSULTANTUL JASPERS PENTRU PUNCT DE VEDERE IN DATA DE 02.04.2021. IN DATA DE 18.05.2021 A FOST ORGANIZATA O NOUA SEDINTA CU CONSULTANTII JASPERS. IN DATA DE PROIECTARE TVA LEI, FARA TVA) PRESTARE A SERVICIILOR - 18 DIN 01.07.2021) 07.06.2021 A FOST TRANSMISA CONSULTANTILOR JASPERS DOCUMENTATIA REVIZUITA DE CATRE PRESTATOR CA URMARE A SEDINTEI DIN DATA DE 18.05.2021. LUNI IN DATA DE 14.07.2021 A FOAT AVIZATA AMC 1 IN CADRUL CTE CNAIR S.A.

INGINERIA ESPECIALIZADA OBRA CIVIL E CONTRACT ELBORARE S.F. IN DERULARE. INDUSTRIAL SA - CONTRACT PROIECTARE DOCUMENTATIA AMC ETAPA 1 REVIZIA 2 A FOST TRANSMISA CONSULTANTILOR JASPERS PENTRU OBSERVATII. DRUM EXPRES BRAILA - TULCEA (JIJILA - (ELABORARE STUDIU DE FEZABILITATE SI PROIECT IUNIE 2020 - ETAPA 1674.75 MIL. LEI FARA DOCUMENTATIA AMC ETAPA 1 REVIUITA A FOST RETRANSMISA CONSULTANTILOR JASPERS PENTRU OBSERVATII IN DATA DE 10.05.2021. 2 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES 0+000 59+700 BRAILA - TULCEA LOT 1 59.7 0% 0% IUNIE 2022 CATALOI) TEHNIC) SEMNAT IN LUNA MAI 2020. PROIECTARE TVA IN DATA DE 09.06.2021 FOST ORGANIZATA O NOUA SEDINTA CU EXPERTII JASPERS. (VALOARE CONTRACT PROIECTARE: IN PREZENT PRESTATORUL IMPLEMENTEAZA OBSERVATIILE EMISE DE CATRE EXPERTII JASPERS IN CADRUL DOCUMENTATIEI AMC ETAPA 1. 14.159.206,13 LEI, FARA TVA) PRESTATORUL ANALIZEAZA NOILE PROPUNERII DE AMENAJARE A DRUMULUI DE LEGATURA LA PUNCTUL DE TRECERE A FRONTIERE ISACCEA IN CONFORMITATE CU SOLICITARILE PRIMARIEI ISACCEA.

INGINERIA ESPECIALIZADA OBRA CIVIL E CONTRACT ELABORARE SF IN DERULARE. INDUSTRIAL SA - CONTRACT ELABORARE SF SI PT AMC - ETAPA 1 SE AFLA IN ANALIZA CONSULTANTILOR JASPERS. 03.04.2020 - ETAPA APRILIE 2022 - TERMEN FINALIZARE 1805.55 MIL. LEI FARA 3 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES BUZAU - BRAILA 0+000 98+000 IN DERULARE BUZAU - BRAILA LOT 1 98 0% 0% APRILIE 2022 DOCUMENTATIA AMC 1 SE AFLA IN CURS DE REVIZUIRE CONFORM OBSERVATIILOR JASPERS. PROIECTARE PROIECTARE TVA (VALOARE CONTRACT PROIECTARE: DOCUMENTATIA AMC 1 REVIZUIT A FOST TRANSMISA CATRE CNAIR, CARE A EMIS NOI OBSERVATII CATRE PRESTATOR. 16.591.031,97 LEI, FARA TVA) IN DATA DE 26.05.2021 A FOST ORGANIZATA O NOUA SEDINTA CU CONSULTANTII JASPERS.IN PREZENT PRESTATORUL IMPLEMENTEAZA OBSERVATIILE DE CATRE EXPERTII JASPERS IN CADRUL DOCUMENTATIEI AMC ETAPA 1. IN DATA DE 17.03.2021 CNAIR A SEMNAT CU OFERTANTUL DECLARAT CASTIGATOR - ASOCIEREA EGIS ROMANIA S.A. – SEARCH CORPORATION S.R.L. ORDIN DE INCEPERE ASOCIEREA EGIS ROMANIA S.A. – SEARCH VALOAREA CONTRACTULUI ESTE DE 20.247.133,77 LEI FARA TVA, SURSA DE FINANTARE FIIND DIN FONDURI EUROPENE NERAMBURSABILE. 4 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES CRAIOVA - TARGU JIU CRAIOVA - TARGU JIU 108 0% 0% 16.04.2021 - ETAPA APRILIE 2023 20.25 MIL LEI FARA TVA CORPORATION S.R.L IN DATA DE 16.04.2021 A FOST SEDINTA DE INCEPUT (ORDINUL DE INCEPERE) PROIECTARE TERMENUL DE PREDARE AMC 1 (16.07.2021) A FOST DEPASIT DIN CAUZA UNOR OBIECTIVE SEVESO DEPISTATE IN ZONA DE INTERES A DRUMULUI EXPRES.

CONTRACT SEMNAT IN DATA DE 19.06.2020. INGENIERIA ESPECIALIZADA OBRA CIVIL E ORDINUL DE INCEPERE 27.07.2020 INDUSTRIAL S.A. ORDIN DE INCEPERE ANUL 2022 - FINALIZARE ETAPA 1400.22 MIL. LEI FARA DURATA CONTRACTULUI ESTE DE 24 LUNI DE LA DATA DE INCEPERE A CONTRACTULUI 5 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES FOCSANI - BRAILA 0+000 76+000 SEMNAT IN DATA DE 19.06.2020 FOCSANI - BRAILA 76 0% 15% 27.07.2020 - ETAPA IULIE 2022 PROIECTARE TVA ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU, ETAPA 1 (AMC1) FOST AVIZATA IN CTE CNAIR SA. (VALOARE CONTRACT PROIECTARE: PROIECTARE A FOST APROBATA TEMA PENTRU STUDII ARHEOLOGICE ETAPA1 SI STUDIUL ARHEOLOGIC ETAPA 1. 15.001.446,99 LEI, FARA TVA) IN CURS DE ELABORARE ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU ETAPA 2 (AMC 2).

SEARCH CORPORATION & EGIS ROMANIA- CONTRACT PROIECTARE ELABORARE SF SI ORDIN DE INCEPERE CONTRACT IN DERULARE. DRUM EXPRES OVIDIU (CONSTANTA) - PROIECT TEHNIC SEMNAT IN DATA DE 13.07. AUGUST 2022 - TERMEN FINALIZARE 2664.38 MIL. LEI FARA 6 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES 0+000 112+000 CONSTANTA - TULCEA 112.5 0% 0% 10.08.2020 - ETAPA Aug-22 AMC ETAPA 1 ESTE IN CURS DE REVIZURIRE CONFORM OBSERVATIILOR JASPERS. PRESTATORUL ANALIZEAZA REALIZAREA UNOR DRUMURI DE LEGATURA CU MUN. TULCEA. TULCEA 2020 PROIECTARE TVA PROIECTARE PRESTATORUL IMPREUNA CU CESTRIN ANALIZEAZA REALIZAREA DRUMURILOR EXPRES/DRUMURI DE LEGATURA LA DX8 IN CONFORMITATE CU DATELE/INFORMATIILE ACTUALIZATE TRANSMISE DE CATRE PRIMARIA TULCEA. (VALOARE CONTRACT PROIECTARE: 17.845.626,28 LEI, FARA TVA)

SEARCH CORPORATION SRL - EGIS ROMANIA S.A - EGIS INTERNATIONAL SAS. CONTRACT IN DERULARE. CONTRACT PROIECTARE ELABORARE SF SI OCTOMBRIE 2022 - FINALIZARE 1304.96 MIL. LEI FARA IN DATA DE 14.04.2021 A FOST AVIZATA IN CADRUL CTE-CNAIR SA DOCUMENTATIA AMC ETAPA 1. IN CURS DE ELABORARE DOCUMENTATIA AMC ETAPA 2. IN DATA DE 16.06.2021 PRESTATORUL A INTAINTAT DOCUMENTATIA AMC 7 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES PASCANI - SUCEAVA 0+000 61+000 PASCANI - SUCEAVA 61 0% 0% OCTOMBRIE 2020 PROIECT TEHNIC SEMNAT IN DATA DE 07.09.2020 ETAPA DE PROIECTARE TVA ETAPA 2. DOCUMENTATIA AMC ETAPA 2 ESTE IN ANALIZA LA BENEFICIAR. (VALOARE CONTRACT DE PROIECTARE: DOCUMENTATIA AMC 2 A FOST AVIZATA IN CTE - CNAIR S.A. IN DATA DE 23.07.2021. 11,721,430.96 LEI FARA TVA)

SEARCH CORPORATION & – MEGA MUHENDISLIK MUSAVIRLIK A.S. (MEGA ENGINEERING CONTRACT IN DERULARE. CONSULTING INC.) - CONTRACT PROIECTARE PRESTATORUL A TRANSMIS DOCUMENTATIA ANALIZA MULTICRITERIALA DE TRASEU. AUGUST 2020 – DEMARARE OCTOMBRIE 2022 - FINALIZARE OCTOMBRIE 2022 - TERMEN 1671.37 MIL. LEI FARA 8 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES PLOIESTI - GAESTI 0+000 76+000 ELABORARE STUDIU DE FEZABILITATE SI PROIECT PLOIESTI - GAESTI 76 0% 0% AU FOST EMISE OBSERVATII DIN PARTEA BENEFICIARULUI SI PRESTATORUL A TRANSMIS DOCUMENTATIA REVIZUITA. ETAPA DE PROIECTARE ETAPA DE PROIECTARE FINALIZARE PROIECTARE TVA TEHNIC DE EXECUTIE SEMNAT IN DATA DE IN DATA DE 09.04.2021 ANALIZA MULTICRITERIALA ETAPA 1 A FOST AVIZATA IN CADRUL C.T.E. CNAIR. 25.08.2020 (VAL CTR PROIECTARE: 15.86 MIL LEI A FOST SUSPENDAT CONTRACTUL PENTRU O PERIOADA DE 3 LUNI INCEPAND CU DATA DE 18.05.2021. FARA TVA)

SEARCH CORPORATION SRL - EGIS ROMANIA S.A - CONTRACT IN DERULARE. EGIS INTERNATIONAL SAS. DOCUMENTATIA ANALIZA MULTICRITERIALA DE TRASEU ESTE REVIZUITA CONFORM OBSERVATIILOR BENEFICIARULUI. CONTRACT PROIECTARE ELABORARE SF SI 9 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES SUCEAVA - SIRET 0+000 40+000 SUCEAVA- SIRET 40 0% 0% OCTOMBRIE 2020 OCTOMBRIE 2022 882.9 MIL. LEI FARA TVA IN DATA DE 14.04.2021 A FOST AVIZATA IN CADRUL CTE-CNAIR SA DOCUMENTATIA AMC ETAPA 1. IN CURS DE ELABORARE DOCUMENTATIA AMC ETAPA 2. IN DATA DE 16.06.2021 PRESTATORUL A INTAINTAT DOCUMENTATIA AMC PROIECT TEHNIC SEMNAT IN DATA DE 07.09.2020 ETAPA 2. DOCUMENTATIA AMC ETAPA 2 ESTE IN ANALIZA LA BENEFICIAR. (VALOARE CONTRACT DE PROIECTARE: DOCUMENTATIA AMC 2 A FOST AVIZATA IN CTE - CNAIR S.A. IN DATA DE 23.07.2021. 10,092,839.13 LEI FARA TVA)

SEARCH CORPORATION & EGIS ROMANIA- CONTRACTUL IN DERULARE CONTRACT PROIECTARE ELABORARE STUDIU DE A FOST TRANSMIS AMC ETAPA 1 SE AFLA IN CURS DE REVIZUIRE CONFORM OBSEVATIILOR BENEFICIARULUI. AUGUST 2020 DEMARARE OCTOMBRIE 2022 - FINALIZARE OCTOMBRIE 2022 - TERMEN 3563.3 MIL. LEI FARA 10 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES TISITA - ALBITA 0+000 160+000 FEZABILITATE SEMNAT IN DATA DE 09.07. 2020 TISITA - ALBITA 160 0% 0% PRESTATORUL ANALIZEAZA ETAPIZAREA SI FAZAREA OBIECTIVULUI DE INVESTITII CONFORM CERINTELOR CNAIR SI MTI. IN DATA DE 09.06.2021 PRESTATORUL A INTAINTAT DOCUMENTATIA AMC ETAPA 1. DOCUMENTATIA AMC ETAPA DE PROIECTARE ETAPA DE PROIECTARE FINALIZARE ETAPA DE PROIECTARE TVA (VALOARE CONTRACT PROIECTARE: ETAPA 1 ESTE IN ANALIZA LA BENEFICIAR. 11.057.073,07 LEI FARA TVA) DOCUMENTATIA AMC 1 REV 2 ETAPIZARE/FAZARE ESTE IN CURS DE REVIZUIRE IN CONFORMITATE CU OBSERVATIILE BENEFICIARULUI.

IN DATA DE 10.07.2020 A FOST SEMNAT CONTRACTUL PROIECTARE SF+PAC/DTAC+PT SEARCH CORPORATION SRL DURATA DE REALIZARE A CONTRACTULUI DE SERVICII ESTE DE 18 LUNI AUGUST 2020 - DEMARARE 2022 - FINALIZARE SERVICII DE SEMNAT IN DATA DE 10.07. 2020 SATU MARE - OAR (GRANITA ANUL 2022 - TERMEN FINALIZARE 311.79 MIL. LEI FARA IN DATA DE 10.08.2020 S-A DAT ORDINUL DE INCEPERE. 11 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES DRUM EXPRES OAR - SATU MARE 0+000 10+900 10.9 0% 3% SERVICII DE PROIECTARE FAZA PROIECTARE FAZA S.F. + P.A.C. + (VALOARE CONTRACT PROIECTARE: 3.646.308,36 RO/HU) FAZA DE PROIECTARE TVA IN DATA DE 05.03.2021 A FOST AVIZATA IN CADRUL CTE CNAIR ANALIZA MULTICRITERIALA A VARIANTELOR DE TRASEU AMC1 + AMC2 (VARIANTA 1) S.F. + P.A.C. + P.T.E. P.T.E. LEI FARA TVA) INVESTIGATIILE GEOITEHNICE SUNT REALIZATE IN PROCENT DE 70%. IN DATA DE 17.05.2021 A FOST EMIS CERTIFICATUL DE URBANISM.

CONTRACT IN DERULARE. DOCUMENTATIA AMC ETAPA 1 A FOST ANALIZATA SI S-AU EMIS OBSERVATII. DOCUMENTATIA REVIZUITA AMC 1 A PRIMIT AVIZUL C.T.E. IN DATA DE 01.04.2021. ORDIN DE INCEPERE IULIE 2022 - TERMEN 222.71 MIL. LEI FARA IN DATA DE 08.04.2021 A FOST TRANSMISA DOCUMENTATIA AMC ETAPA 2 SI SE AFLA IN ANALIZA IN CADRUL CNAIR. 12 DRUMURI EXPRES IN PREGATIRE FAZA PROIECTARE (SF, PT) DRUM EXPRES A1 (PITESTI) - MIOVENI 0+000 10+000 SEARCH CORPORATION S.R.L. A1 (PITESTI) - MIOVENI 10 0% 0% 09.12.2020 - FINALIZARE ETAPA DE TVA IN DATA DE 21.04.2021 AU FOST TRANSMISE OBSERVATII ASUPRA DOCUMENTATIEI AMC 2 CATRE PRESTATOR. DOCUMENTATIA AMC ETAPA 2 REVIZUITA CONFORM OBSERVATIILOR FORMULATE DE CATRE BENEFICIAR (SOLICITARE ETAPA DE PROIECTARE PROIECTARE PRIM. PITESTI RECONFIGURARE NOD A1-DEX) A FOST TRANSMISA BENEFICIARULUI. DOCUMENTATIA ESTE IN CURS DE ANALIZA LA BENEFICIAR. DOCUMENTATIA AMC ETAPA 2 A FOST AVIZATA IN CADRUL CTE-CNAIR S.A. IN DATA DE 24.06.2021. PRESTATORUL A INAINTAT DOCUMENTATIA IN VEDEREA OBTINERII CERTIFICATULUI DE URBANISM.

3. DRUMURI DE MARE VITEZĂ

3.1. DRUMURI DE MARE VITEZĂ ÎN FAZA PROIECTARE SF/PT - SEPTEMBRIE 2021

PANA LA DETALII NR. CRT. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL STADIUL FINANCIAR ACTUAL DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDERE VALOARE PROIECT OBSERVAȚII (km) PROCEDURĂ

http://www.cnadn r.ro/sites/default/f iles/STUDII_DE_FE DRUM DE MARE VITEZA BAIA MARE - DEJ - 6681.19 MIL. LEI FARA PROCEDURA DE ACHIZIȚE PENTRU LOTUL 1 A FOST ANULATA 1 DRUMURI DE MARE VITEZĂ ÎN FAZA PROIECTARE SF/PT DRUM DE MARE VITEZĂ 0+000 145+000 BAIA MARE - DEJ - BISTRITA LOT 1 145 ESTIMAT 2022 2024 ZABILITATE_%C8% BISTRITA - VATRA DORNEI - SUCEAVA TVA DETALII STADIU PROCEDURA DE ATRIBUIRE IN LINK-UL DE MAI JOS. 98I_PROIECTE_TEH NICE_CALENDAR.p df

15.8 MIL LEI FARA TVA IN DATA DE 10.03.2021, CNAIR A SEMNAT CONTRACTUL PENTRU ELABORARE STUDIU DE FEZABILITATE DRUM DE MARE VITEZA VITEZA BAIA MARE - SUCEAVA, LOT 2 BISTRITA - VATRA DORNEI CU OFERTANTUL SC EXPLAN SRL., CU DRUM DE MARE VITEZA BAIA MARE - DEJ - 2 DRUMURI DE MARE VITEZA IN FAZA PROIECTARE SF/PT DRUM DE MARE VITEZĂ 145+000 228+000 SC EXPLAN SRL BISTRITA - VATRA DORNEI LOTUL 2 83 2021 2023 ANUL 2023 (VALOARE CONTRACT O VALOARE DE 15.793.026,12 LEI FARA TVA. BISTRITA - VATRA DORNEI - SUCEAVA ELABORARE S.F.)

ASOCIEREA BEST CONSULTING & DESIGN SRL – 14.48 MIL LEI FARA TVA DRUM DE MARE VITEZA BAIA MARE - DEJ - IN DATA DE 10.03.2021, CNAIR A SEMNAT CONTRACTUL PENTRU ELABORARE STUDIU DE FEZABILITATE DRUM DE MARE VITEZA BAIA MARE - SUCEAVA, LOT 3 VATRA DORNEI – SUCEAVA CU ASOCIEREA BEST CONSULTING & DESIGN 3 DRUMURI DE MARE VITEZA IN FAZA PROIECTARE SF/PT DRUM DE MARE VITEZĂ 228+000 335+000 INGENIERIA ESPECIALIZADA OBRA CIVIL E VATRA DORNEI - SUCEAVA LOTUL 3 107 2021 2023 ANUL 2023 (VALOARE CONTRACT BISTRITA - VATRA DORNEI - SUCEAVA SRL – INGENIERIA ESPECIALIZADA OBRA CIVIL E INDUSTRIAL, CU PRETUL DE 14.475.000,00 LEI FARA TVA. INDUSTRIAL ELABORARE S.F.) 4. DRUMURI NAȚIONALE

4.1. DRUMURI NATIONALE IN REABILITARE / MODERNIZARE - SEPTEMBRIE 2021

PANA LA DETALII NR. CRT. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL STADIUL FINANCIAR ACTUAL DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDERE VALOARE PROIECT OBSERVAȚII (km) PROCEDURĂ

PROBLEME: DN79 ARAD - ORADEA, KM 4+150 – 266.31 MIL. LEI FARA CONTRACTUL A FOST REZILIAT DE CATRE BENEFICIAR IN DATA DE 02.10.2020 DATORITA INTARZIERILOR SI NEEXECUTARII LUCRARILOR RAMASE DE EXECUTAT DE CATRE ANTREPRENOR. 1 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL 4+150 107+745 ASTALDI S.P.A. 103.55 98% 98% 03.02.2009 REZILIAT IN FOLOSINTA KM 107+745 TVA 1. NEEXECUTAREA LUCRARILOR PENTRU PODUL DE LA KM 41+635 2. INTARZIEREA FINALIZARII EXECUTIEI LUCRARILOR

126.323 MII LEI FARA ASOCIEREA S.C. ALEXCOR TRADING S.R.L. - TVA - VALOARE ALEXANDRIA - TURNU DATA INCEPERII ACTIVITATII DE 2 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN 52 1+350 44+600 IMPRESA DI COSTRUZIONI ING. E. MANTOVANI 43.25 PROIECTARE ȘI ORDINUL DE INCEPERE A EXECUTIEI LUCRARILOR SE VA DA DUPA OBTINEREA AUTORIZATIEI DE CONSTRUCTIEI MAGURELE PROIECTARE: 09.06.2020 S.P.A. – S.C. PEGASUS ENGINEERING S.R.L. EXECUȚIE PENTRU AMBELE SECTOARE

126.323 MII LEI FARA ASOCIEREA S.C. ALEXCOR TRADING S.R.L. - TVA - VALOARE TURNU MAGURELE - PORT DATA INCEPERII ACTIVITATII DE 3 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN 52 49+194 52+649 IMPRESA DI COSTRUZIONI ING. E. MANTOVANI 3.455 PROIECTARE ȘI ORDINUL DE INCEPERE A EXECUTIEI LUCRARILOR SE VA DA DUPA OBTINEREA AUTORIZATIEI DE CONSTRUCTIEI TURNU MAGURELE PROIECTARE: 09.06.2020 S.P.A. – S.C. PEGASUS ENGINEERING S.R.L. EXECUȚIE PENTRU AMBELE SECTOARE

REALIZARE LARGIRE VALEA S.C GEIGER TRANSILVANIA SRL – SERVICII DE OLTULUI LA 4 BENZI DE 22.141 MIL. LEI FARA 4 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN7 251+475 254+315 PROIECTARE SC CONSIS PROIECT SRL IN CALITATE 2.84 40% 25% 01.11.2019 SEPTEMBRIE 2021 A FOST OBTINUTA AC NR. 50 DIN DATA DE 04 SEPTEMBRIE 2020. ORDINUL ADMINITRATIV DE RELUARE A FOST DAT CU 21.09.2020. CIRCULATIE INTRE KM TVA DE SUBCONTRACTANT 251+475 – KM 254+315

MODERNIZARE DN 5, ASOCIEREA EUROCOGEN - FILIALA ANINOASA SRL DRUM MODERNIZAT - BUCURESTI – ADUNATII 5 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN5 7+573 19+220 & ALEANDRI SPA & BEOZZO COSTRUZIONI SRL & LUCRARI FINALIZATE IN 11.647 99.50% 93.80% 23.04.2015 ESTIMAT SEPTEMBRIE 2021 76.13 MIL. LEI FARA TVA EXECUTIE LUCRARI COPACENI KM 7+573 - KM SMART BUILDING PROJET SRL ANUL 2020 19+220

MODERNIZARE: PITESTI - A FOST RECEPTIONAT UN SECTOR DE 28,85 KM. ASOCIEREA AZVI SA - STRACO GRUP SRL - CAMPULUNG - BRASOV 275.86 MIL. LEI FARA 6 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN73 13+800 128+250 103.25 49.82% 51.00% 19.05.2014 DECEMBRIE 2023 PENTRU RESTUL SECTORULUI CONTRACTUL ESTE IN CURS DE REZILIERE SI SE VA LANSA O PROCEDURA DE LICITATIE AVAND CA OBIECT ACTUALIZAREA PROIECTULUI PENTRU REST DE EXECUTAT. TRACTEBEL KM 13+800 - KM 42+850; KM TVA DOCUMENTATIA DE ATRIBUIRE PENTRU SERVICII DE ACTUALIAZARE PROIECT FINALIZATA, PROCEDURA DE LICITATIE SUSPENDATA CA URMARE A UNOR CONTESTATII . 54+050 - KM 128+250

RECEPTIE LA TERMINAREA ASOCIEREA SC SYLC CON TRANS 7 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN76 55+425 69+350 IONESTI - VARFURILE LOT 3 13.93 96.92% 97.00% 15.03.2019 LUCRARILOR - PREVIZIUNE 55.95 MIL. LEI FARA TVA RECEPTIE LA TERMINAREA LUCRARILOR - PREVIZIUNE OCTOMBRIE 2021, INCLUSIV CONSOLIDAREA ZONELOR CU ALUNECARI KM 65+288 - KM 65+448 DREAPTA SI KM 65+843 - KM 65+996 STANGA SRL/HIDROSTROY AD NOIEMBRIE 2021

8 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN56 47+000 84+020 MOCHLOS S.A. GALICEA MARE - CALAFAT LOT 2 33.83 100% 91.43% 03.09.2012 16.06.2021 81.94 MIL. LEI FARA TVA PROCESUL VERBAL DE RECEPTIE LA TERMINAREA LUCRARILOR A FOST APROBAT DE DIRECTORUL GENERAL AL CNAIR IN DATA DE 16.06.2021.

DECEMBRIE 2021 - RECEPTIE LA ASOCIEREA SC DRUM ASFALT SRL – VAHOSTAV SK CONTRACTUL PENTRU FINALIZAREA LUCRARILOR A FOST SEMNAT IN DATA DE 08.05.2020; TERMINAREA LUCRARILOR 9 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN76 69+350 102+660 A.S. – TRAMECO SA – ILE VIOREL CONSTRUCT VARFURILE - STEI LOT 4 33.31 70.18% 30.65% 29.06.2020 ANUL 2021 74.78 MIL LEI FARA TVA ORDINUL DE INCEPERE A LUCRARILOR A FOST EMIS IN DATA DE 29.06.2020; DECEMBRIE 2026 - RECEPTIE SRL. PREDARE AMPLASAMENT - 02.07.2020. FINALA

LOT 1 (SECTOR 1): LOT 1 - ASOCIEREA SC AQUA BALDANA - TARGOVISTE http://www.cnadn PARC SRL - SC MAVGO KM. 0+000 - KM 44+130 r.ro/sites/default/f HOLDING SRL - HYDROSTROY LARGIRE LA 4 BENZI DE LOTUL 1 - IN DATA DE 14.01.2021 A FOST INAINTATA NOTIFICAREA DE REZILIERE. iles/DRUMURI_NA AD - VDH AD (VODSTROI 98 CIRCULATIE; LOT 2 1567.03 MIL. LEI FARA 10 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN71 0+000 109+905 102.99 0% 0% LOTUL 2 - PROCEDURA RELUATA %C8%9AIONALE_% AD) - SC BDU MAXI (SECTOR 2): TVA PROCEDURA DE ACHIZITIE PUBLICA IN DERULARE C8%98I_VARIANTE CONSTRUCT SRL TARGOVISTE - SINAIA _DE_OCOLIRE_CAL CONSTRUCTORUL A FOST KM. 51+041 - KM ENDAR.pdf NOTIFICAT PENTRU REZILIERE 109+905 - DRUM LA 2 BENZI)

ASOCIEREA SC AQUA PARC SRL - SC MAVGO MODERNIZARE DN28B, TARGU 15.07.2020 - ORDIN INCEPERE 267.31 MIL LEI FARA CONTRACT PROIECTARE SI EXECUTIE IN DERULARE - SEMNAT IN DATA DE 20.05.2020. 11 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN28B 0+000 76+758 HOLDING SRL - VAHOSTAV - SK A.S. - TRAMECO FRUMOS – BOTOSANI, KM 71.512 3% 10.1% AUGUST 2023 PENTRU ETAPA PROIECTARE TVA AVIZAT PT CTE CNAIR 21.07.2021 AVIZAT PT CTE DRDP IASI - 09.06.2021 - AVIZAT DTAC DRDP IASI - 10.03.2021; AVIZAT DTAC CNAIR SA - 16.03.2021. AUTORIZATIE DE CONSTRUIRE NR. 21/12.05.2021 EMISA DE MTIC. SA 0+000 – KM 76+758

IN DATA DE 29.06.2020 A FOST DEPUSA APLICATIA DE FINANTARE PENTRU ANGAJAREA CHELTUIELILOR AFERENTE ACESTUI PROIECT, DIN FONDURI NERAMBURSABILE, ALOCALTE IN CADRUL POIM 2014 - 2020 MODERNIZARE DN29D ASOCIEREA SC AUTOTEHNOROM SRL - SC OPR 22.06.2020 - EMITERE ORDIN CONTRACT PROIECTARE SI EXECUTIE IN DERULARE BOTOSANI - STEFANESTI KM 208.44 MIL LEI FARA 12 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN29D 2+800 48+146 ASFALT SRL - OBRAS PUBLICAS-Y REGADIOS SA - 45.046 12% 2% DE INCEPERE PENTRU ETAPA MARTIE 2023 IN DATA DE 08.01.2021 A FOST OBTINUTA AUTORIZATIA DE CONSTRUCTIE 2+800 – KM 18+500 SI KM TVA SC EVALCONS TECH SRL PROIECTARE TERMEN DE PREDARE A PROIECTULUI TEHNIC DE EXECUTIE: 28.02.2021 18+800 – KM 48+146 PT - AVIZAT CNAIR SA NR. 5035/26.03.2021

04.11.2020 A AVUT LOC DEPUNEREA OFERTELOR PENTRU PROCEDURA DE ATRIBUIRE A CONTRACTULUI "PROIECTARE TI EXECUTIE LARGIRE LA 4 BENZI A DN 7, BALDANA-TITU, KM 30+950 – KM 52+350”. PANA LA TERMENUL LIMITA AU DEPUS OFERTE URMATORII AGENTI ECONOMICI: 1. ASOCIEREA CLAY WORK - DIMAKS TURIZM INSAAT ENERJI AKARYAKIT NAK. VE TAS. GIDA TEM. OTOM. OTO. KIR.ITH. IHR. SAN.VE.TIC.LTD.STI. ISTANBUL; 2. ASOCIEREA COSEDIL SPA – SC BIT INVEST SRL - CHIRULLI ANDREA IMPRESA INDIVIDUALE – SC TOTAL ROAD SRL; 3. ASOCIEREA SC G&M ROAD BUILDING ENGINEERING SRL – SC KIRLIC GROUP SRL – SC BUILDING DESIGN 2000 TOP SRL – SC IRIMAT CONS S.R.L. - D'AGOSTINO ANGELO ANTONIO COSTRUZIONI GENERALI S.R.L. – SC CONCORDIA CON. STRADE S.R.L – SC SERCONSTRUCT ROADS S.R.L.; LARGIRE LA 4 BENZI A DN7, ESTIMAT SEMNARE CONTRACT 4. ASOCIEREA SC MAVGO HOLDING S.R.L. – SC BDU MAXI CONSTRUCT S.R.L.; 210.63 MIL. LEI FARA 13 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN7 30+950 52+350 BALDANA-TITU, KM 30+950- 21.4 IN IPOTEZA FARA DECEMBRIE 2023 DECEMBRIE 2023 5. OZALTIN INSAAT TICARET VE SANAYI A.S. TVA KM 52+350 CONTESTATIE: MARTIE 2021 VALOAREA ESTIMATA A CONTRACTULUI ESTE CUPRINSA IN INTERVALUL 243.801.103,00 - 289.093.324,00 LEI FARA TVA. DURATA CONTRACTULUI ESTE DE 6 LUNI PERIOADA DE PROIECTARE TI 20 DE LUNI PENTRU EXECUTIA LUCRARILOR. COMISIA DE EVALUARE VA ANALIZA OFERTELE IN CONFORMITATE CU PREVEDERILE DOCUMENTATIILOR DE ATRIBUIRE TI CU LEGISLATIA IN VIGOARE IN DOMENIUL ACHIZITIILOR PUBLICE. ANALIZA SI EVALUAREA OFERTELOR CU STABILIREA OFERTANTULUI CASTIGATOR: 29.04.2021; COMUNICAREA REZULTATULUI PROCEDURII: 29.04.2021; TERMEN DEPUNERE CONTESTATII: 10.05.2021; ESTIMAT SEMNARE CONTRACT, IN IPOTEZA FARA CONTESTATII: 25.05.2021 CONTRACT REALIZARE EXPERTIZA TEHNICA SEMNAT IN DATA DE 06.06.2020 ORDINUL DE INCEPERE A FOST EMIS IN DATA DE 10.07.2020, CU O DURATA CONTRACTUALA DE 90 DE ZILE, TERMEN DE FINALIZARE 08.10.2020 REABILITARE DN 6, CALENDAR PROCEDURA DE LICITATIE LOTUL 2, KM 132+435 - 185+230 - RELICITARE ALEXANDRIA - CRAIOVA, KM 267.15 MIL. LEI FARA DEPUNERE OFERTE: 24.05.2021; 14 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN6 132+435 185+230 90+190 - KM 222+182 48.009 2021 2024 ANUL 2024 TVA ANALIZA SI EVALUAREA OFERTELOR CU STABILIREA OFERTANTULUI CASTIGATOR: 26.07.2021; LOT 2: KM 132+435 - KM COMUNICAREA REZULTATULUI PROCEDURII DE ACHIZITIE PUBLICA: 26.07.2021; 185+230 (RELICITARE) CONTESTATII: 05.08.2021 ESTIMARE SEMNARE CONTRACT: 20.08.2021

REABILITARE DN66 PRIN CONTRACT EXECUTIE LUCRARI SEMNAT IN DATA DE 02.11.2020 REAMENAJAREA SECTORULUI DURATA DE REALIZARE A INVESTITIEI: 12 LUNI (EXCLUSIV PERIOADA DE TIMP FRIGUROS, DE REGULA, CUPRINSA IN PERIOADA 15.11- 15.03 ), CU O PERIOADA DE GARANTIE A LUCRARILOR ACORDATA DE EXECUTANT DE 96 LUNI (8 CUPRINS INTRE KM 105+000 – ANI). KM 105+580 IN VEDEREA ASOCIEREA S.C. FREYROM S.A. - PROCONS APROBATA SITUATIA DE LUCRARI NR. 1 IN VALOARE DE 673.083,63 LEI FARA TVA. APROBATA SITUATIA DE LUCRARI NR. 2 IN VALOARE DE 991.685,77 LEI FARA TVA. 15 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN66 106+220 106+965 CONSTRUIRII UNUI POD NOU 1.325 33.25% 10.75% 12.11.2020 12.07.2022 ANUL 2022 19.85 MIL. LEI FARA TVA GROUP S.R.L DOCUMENTATIA TEHNICA REPREZENTAND MODIFICARILE PREVAZUTE IN DISPOZITIILE DE SANTIER 1-7 A FOST AVIZATA IN CTE DRDP CRAIOVA CU AVIZ NR.545/01.07.2021 SI IN CTE CNAIR SA IN DATA DE 21.07.2021. DISPOZITIILE DE PESTE JIU DE LA MERI LA KM SANTIER 1-6 CONSUMA REZERVELE DE IMPLEMENTARE, IN VALOARE DE 1.893.728,52 LEI FARA TVA. MODIFICARILE DIN DISPOZITIA DE SANTIER NR. 7 CONDUC LA O DEPASIRE CU 4.122.679,12 LEI FARA TVA A VALORII CONTRACTULUI 105+250, REAMENAJARE , CEEA CE REPREZINTA 20.77 % DIN VALOAREA CONTRACTULUI. S-A TRANSMIS CĂTRE CNAIR O ADRESĂ PENTRU COMUNICAREA SURSEI DE FINANȚARE AFERENTĂ LUCRĂRILOR SUPLIMENTARE AVIZATE AFERENTE PODULUI PESTE JIU SECTOR KM 106+220 – KM DE LA MERI. 106+965

CONTRACT DE PROIECTARE SI EXECUTIE LUCRARI SEMNAT IN DATA DE 24.07.2020. VALOARE CONTRACT PROIECTARE + EXECUTIE LUCRARI: 126.778.219,70 LEI CU TVA, DIN CARE: PROIECTARE: 3.655.098,42 LEI CU TVA EXECUTIE LUCRARI: 123.123.121,28 LEI CU TVA MODERNIZARE DN 2L, SOVEJA - ORDINUL DE INCEPERE PENTRU PROIECTARE IN 106.54 MIL. LEI FARA AVIZAT DTAC CTE DRDP IASI 16918/ 10.05.2021; AVIZAT DTAC CTE CNAIR SA - 08.06.2021 16 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN2L 60+165 76+277 LEPSA, KM 60+165 - KM 16.112 PROIECTARE A FOST EMIS IN DECEMBRIE 2023 DECEMBRIE 2023 DERULARE TVA DURATA CONTRACTULUI ESTE: 30 LUNI PERIOADA DE PROIECTARE SI EXECUTIE A LUCRARILOR: 76+277 DATA DE 22.09.2020 - 6 LUNI PROIECTARE; - 24 LUNI EXECUTIE LUCRARI; - 84 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR. PTE IN CURS DE REVIZUIRE.

PROIECTARE SI EXECUTIE "REALIZARE BANDA A TREIA 17 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN7 256+675 258+950 2.274 8.46 MIL. LEI FARA TVA DN 7 VALEA OLTULUI INTRE KM 256+675 – KM 258+950”

DRUM DE LEGATURA INTRE CTR SEMNAT IN DATA 189.95 MIL. LEI FARA CONTRACT SEMNAT IN DATA DE 29.01.2021, CU O PERIOADA CONTRACTUALA DE 2 ANI (6 LUNI PROIECTAREA) ȘI ARE O GARANȚIE DE 84 DE LUNI. 18 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN69 0+000 10+000 TODINI COSTRUZIONI GENERALI S.P.A. 10 2021 2023 ANUL 2023 DN69 SI AUTOSTRADA A1 DE 29.01.2021 TVA AVIZ CTE CNAIR NR. 5075 DIN 30.06.2021 - FAZA PAC. AC NR. 35/02.07.2021

STUDIUL DE FEZABILITATE IN VARIANTA DRAFT PREDAT DE CATRE PRESTATOR IN CURS DE ANALIZA. DRUM DE LEGATURA A1 - DN7 S-AU EMIS OBSERVATII ASUPRA VARIANTEI DRAFT A STUDIUL DE FEZABILITATE SI SE ASTEAPTA VARIANTA FINALA. 19 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN7 0+000 14+300 (TITU) (DJ 711A) - LARGIRE LA 14.3 OCTOMBRIE 2019 Aug-21 73.33 MIL. LEI FARA TVA IN DATA DE 29.04.2021 PRESTATORUL A TRANSMIS STUDIUL DE FEZABILITATE. STUDIUL DE FEZABILITATE SE AFLA IN ANALIZA LA BENEFICIAR. IN DATA DE 25.05.2021 AU FOST TRANSMISE OBSERVATIILE BENEFICIARULUI LA 4 BENZI DE CIRCULATIE DOCUMENTATIA INAINTATA IN DATA DE 29.04.2021. PRESTATORUL IMPLEMENTEAZA OBSERVATIILE FORMULATE PENTRU SF.

CONTRACT SERVICII DE PROIECTARE DERULAT IN STUDIU DE FEZABILITATE IN ELABORARE 20 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DRUM TRANSREGIO GILAU - APAHIDA 0+000 38+800 GILAU - APAHIDA 38.8 BAZA UNUI PROTOCOL 2345.52 MIL. FARA TVA FINALIZARE SF - TRIM. IV 2021 DE CATRE UAT CLUJ NAPOCA

S.C. SEARCH CORPORATION S.R.L. - ELABORARE 109.69 MIL. LEI FARA SF REVIZUIT IN ANUL 2016 / HG NR. 460/28.06.2018 PENTRU APROBAREA INDICATORILOR TEHNICO-ECONOMICI 21 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN24C 106+650 142+250 SF / S.C. BEST CONSULTING & DESIGN S.R.L. MANOLEASA - RADAUTI PRUT 35.6 33.63% 0% TVA LIPSA FINANTARE LUCRARI BUCURESTI - REVIZUIRE S.F.

POD PE DN13C PESTE RAUL TARNAVA POD PE DN 13C PESTE RAUL 22 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL 1+200 1+252 0.0521 5.45 MIL. LEI FARA TVA CONTRACT SEMNAT IN LUNA OCTOMBRIE 2020. MARE LA VANATORI TARNAVA MARE LA VANATORI

REMEDIERE DEFECTIUNI PE 12.761 MIL. LEI FARA 23 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN1H 6+000 12+000 SC MECANO BAU TRADING SRL 6 91.58% 47.88% 15.10.2020 15.11.2021 ANUL 2021 ORDINUL DE INCEPERE A FOST EMIS INCEPAND CU DATA DE 15.10.2020 DN1H KM 6+000 - KM 12+000 TVA

0.1953 MIL. LEI FARA 24 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN51 2+600 43+783 ZIMNICEA - ALEXANDRIA 41.183 DOCUMENTATIE INTOCMITA IN VEDEREA PROMOVARII SPRE LICITATIE. T.V.A.

PASAJ SUPERIOR PE DN2, 841.094 MIL. LEI FARA 25 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN2 PESTE CF LA ROMAN, KM 2 TVA 332+961

152+990 - 200+745 (ORAVITA - 26 DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL DN57 152+990 200+745 47.755 1.638 MII LEI FARA TVA DOCUMENTATIE PREDATA LA DIRECTIA ACHIZITI MORAVITA)

S-A EMIS ORDINUL DE INCEPERE IN DATA DE 15.03.2021. PROIECTARE SI EXECUTIE DURATA DE EXECUTIE CONTRACT : DRUMURI NATIONALE IN REABILITARE/ MODERNIZARE DRUM NATIONAL 98.120 MIL LEI FARA 27 DN21 104+160 106+900 PASAJ SUPERIOR PE DN 21, 2.74 0% 0% 15.03.2021 01.09.2023 ANUL 2023 - 360 ZILE PERIOADA DE PROIECTARE TVA KM105+500 - 540 ZILE PERIOADA DE EXECUTIE. STADIU: S-A EMIS AVIZUL PENTRU DECLARATIA DE PROIECTARE. 5. VARIANTE OCOLITOARE

5.1. VARIANTE OCOLITOARE IN FOLOSINTA - SEPTEMBRIE 2021

PANA LA DETALII NR. CRT. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL STADIUL FINANCIAR ACTUAL DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDERE VALOARE PROIECT OBSERVAȚII (km) PROCEDURĂ

LUCRARI FINALIZATE - 20.11.2020 PENTRU ACEST PROIECT A FOST FINALIZAT PROCESUL DE ACCESARE A FINANTARII NERAMBURSABILE ALOCATE IN CADRUL POIM 2014-2020, FIIND EMISA NOTA DE APROBARE A FINANTARII ACESTUIA DIN FONDURI NERAMBURSABILE 1 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOARE VARIANTA OCOLITOARE RADAUTI 0+000 16+580 SPEDITION UMB - SC TEHNOSTRADE SRL RADAUTI 1 16.58 08.10.2018 20.11.2020 ANUL 2020 97.44 MIL. LEI FARA TVA IN LUNA DEC. 2020. CONTRACT DE FINANTARE A LUCRARILOR EXECUTATE IN CADRUL POIM 2014-2020 SEMNAT IN LUNA IANUARIE 2021

LUCRARILE AU FOST FINALIZATE SI VARIANTA DE OCOLIRE SACUENI ESTE IN DATA IN CIRCULATIE INCEPAND CU 09.12.2020. SC ANTREPRIZA DE REPARATII SI LUCRARI ARL MOMENTAN SE AFLA IN PROCEDURA DE RECEPTIE LA TERMINAREA LUCRARILOR, FIIND REALIZATA INSPECTIA PRELIMINARA (10.06.2021) IN URMA CAREIA ANTREPRENORUL TREBUIE SA EXECUTE LUCRARI DE REMEDIERI ALE 2 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOARE VARIANTA OCOLITOARE SACUENI 0+000 7+620 SACUENI 7.62 10.09.2019 12.08.2020 DECEMBRIE 2020 42.83 MIL. LEI FARA TVA CLUJ SA DEFICIENTELOR CONSTATATE. LA DATA DE 29.07.2021 ANTREPRENORUL COMUNICA FINALIZAREA LUCRARILOR DE REMEDIERE, IAR DUPA CONFIRMAREA SUPERVIZORULUI DIN 09.08.2021, BENEFICIARUL A PROCEDAT LA CONTINUAREA DEMERSURILOR CUPRINSE IN PROCEDURA DE RECEPTIE LA TERMINAREA LUCRARILOR. SE ESTIMEAZA EFECTUAREA R.T.L. IN PRIMA DECADA A LUNII SEPTEMBRIE 2021.

ASOCIEREA S.C. AUTOTEHNOROM S.R.L. (LIDER) – OCTOMBRIE 2021 - RECEPTIE LA S.C. OPERATIONAL AUTOLEASING S.R.L. – S.C. DESCHISA TRAFICULUI - TERMINAREA LUCRARILOR OCTOMBRIE 2021 - FINALIZARE 3 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOARE VARIANTA OCOLITOARE SUCEAVA 0+000 7+285 OPR ASFALT S.R.L. – OBRAS PUBLICAS Y SUCEAVA 1 7.285 IN DATA DE 27 SEPT. 77% 01.10.2018 63.85 MIL. LEI FARA TVA OCTOMBRIE 2028 - RECEPTIE LUCRARI AUXILIARE REGADIOS S.A. – S.C. FLORCONSTRUCT S.R.L. – 2019 FINALA S.C. CALCARUL S.A.

VARIANTA OCOLITOARE CARACAL - 24.05.2018 - A FOST REALIZATA RTL 4 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOARE 0+000 10+345 ASOCIEREA SECOL S.A. - S.E.C.O.L S.P.A. CARACAL 10.345 100% 97.05% 16.10.2014 RTL: 24.05.2018 41.69 MIL. LEI FARA TVA RELICITARE IN DATA DE 10.11.2020 A FOST REALIZATA RECEPTIA FINALA

ASOCIEREA CHIRULLI ANDREA IMPRESA RTL: 28.11.2016; IN DATA DE 29.11.2016 A AVUT LOC RECEPTIA LA TERMINAREA LUCRARILOR. LA DATA PREZENTEI CONTRACTUL SE AFLA IN PERIOADA DE NOTIFICARE A DEFECTIUNILOR. 5 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOARE VARIANTA OCOLITOARE BRASOV 0+000 7+292 INDIVIDUALE - ALEANDRI SPA - SMART BUILDING TRONSON I, DN1 - DN 11 LOT 1 - RELICITARE 100% 98.56% 16.12.2014 59.56 MIL. LEI FARA TVA RF:19.12.2019 IN DATA DE 19.12.2019 A FOST APROBAT PROCESUL VERBAL DE RECEPTIE FINALA. PROJECT- PASQUALE ALO' SRL

ASOCIEREA SC VIAROM CONSTRUCT SA - SC BETA RECEPTIE LA TERMINAREA 6 VARIANTE OCOLITOARE IN FOLOSINTA VARIANTA OCOLITOARE VARIANTA OCOLITOARE BRASOV 0+000 4+924 TRONSON II, DN11 - DN13 LOT 3 4.924 100% 98.77% 07.08.2014 64.42 MIL. LEI FARA TVA PROCESUL VERBAL DE RECEPTIE LA TERMINAREA LUCRARILOR A FOST APROBAT DE DIRECTORUL GENERAL AL CNAIR IN DATA DE 29.11.2019. COPS SRL - SC MAXIDESIGN SRL LUCRARILOR: 29.11.2019

5.2. VARIANTE OCOLITOARE PROIECTE IN EXECUTIE - SEPTEMBRIE 2021

PANA LA DETALII NR. CRT. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL STADIUL FINANCIAR ACTUAL DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDERE VALOARE PROIECT OBSERVAȚII (km) PROCEDURĂ

15.01.2019 - PENTRU CONTRACTUL DE PROIECTARE SI EXECUTIE PASAJ DOMNESTI A FOST SEMNAT IN DATA DE 10.05.2017 LUCRARILE AUTORIZATE PRIN AUTORIZATIA DE CONSTRUIRE NR. 140/ 20.12.2018, NR. 69/ 28.08.2019 SI NR. 54/ 23.09.2020 AC 140/ 20.12.2018 LUCRARI CE SE EXECUTA: SCENTURA BUCURESTI , KM. 0+250 - KM. 0+500 , BANDA 1: STRAT FUNDATIE DIN BALAST STABILIZAT, HIDROIZOLATIE PE BALAST STABILIZAT; STRAT DE MIXTURA DENSA AB31,5, HIDROIZOLATIE PE STRAT DE PASAJ SUPRATERAN PE DJ 602 16.09.2019 PENTRU LUCRARILE 24 LUNI DE LA EMITEREA STRACO GRUP SRL - SC COMNORD SRL - BAZA AB 31,5; STRAT DE LEGATURA, BINDER BAD 22,4; PANOURI PREFABRICATE TERRE ARMEE RAMPA PAMANT ARMAT COBORARE C3 ( TRONSON 1,2,3,4 ): UMPLUTURA GRANULARA CENTURA BUCURESTI - DEVIERE: COMPLETARE 1 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE CENTURA BUCURESTI CENTURA BUCURESTI DOMNESTI - DJ 602 0.536 40.09% 32.27% AUTORIZATE PRIN AC AUTORIZATIEI DE CONSTRUIRE ANUL 2022 91.55 MIL. LEI FARA TVA SPECIALIST CONSULTING SRL SI INSTALARE INDICATOARE RUTIERE; CENTURA BUCURESTI - KM 0+370 - KM. 0+500 STG.: BETON DE EGALIZARE - FUNDATII PARAPET; COFRARE FUNDATIE DE PARAPET; ARMARE FUNDATIE DE PARAPET; BETONARE FUNDATIE DE DOMNESTI 69/28.08.2019 (ESTIMAT LUNA 09.2022) PARAPET; HIDROIZOLATIE BETON FUNDATIE DE PARAPET CENTURA BUCURESTI RAMPA PAMANT ARMAT C8: PANOURI PREFABRICATE TERRE ARMEE; UMPLUTURA GRANULARA PILA P3: COFRARE RADIER; ARMARE RADIER; 23.09.2020 - PENTRU BETONARE RADIER; BETON DE RADIER ST 2 - TRONSON GIRATIE - BUCURESTI: CUZINETI GIRATIE : TABLIER METALIC APROVIZIONAT ST1; TABLIER METALIC MONTAT ST1; PILA P9: SPARGERE BETON NECORESPUNZATOR CAPETE PILOTI; LUCRARILE AUTORIZATE PRIN ARMARE RADIER; BETON DE EGALIZARE CULEE C1: SPARGERE BETON NECORESPUNZATOR CAPETE PILOTI; COFRARE RADIER ST3 - C8 - GIRATIE - MONTARE PREDALE PREFABRICATE AC 54/23.09.2020

23.01.2019 - DATA DE INCEPERE PERIOADA DE PROIECTARE OBIECT 1: 0+000 - 08.03.2019 - DATA DE DESCHIDERE TRAFIC 20+299, INCEPERE A LUCRARILOR IN 668.33 MIL. LEI FARA 2 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE BACAU 0+000 30+842 SPEDITION UMB SRL – TEHNOSTRADE SRL BACAU 30.842 100.00% 99.78% IANUARIE 2022 ANUL 2020 03.09.2020 - OBIECT 3; OBIECT 2: 0+000 - 3+177 BAZA AC TVA 02.12.2020 - OBIECT 1 OBIECT 3: 0+000 -7+366 040/15.07.201503.07.2019 - DATA DE INCEPERE A LUCRARILOR IN BAZA AC 051/28.06.2019

05.12.2018 CONTRACTUL A FOST SEMNAT IN DATA DE 24.10.2018. ORDINUL DE INCEPERE PENTRU PROIECTAREA LUCRARILOR A FOST EMIS. (DATA DE INCEPERE A A FOST AVIZAT PROIECTUL TEHNIC IN SEDINTA CTE DIN DATA DE 19.06.2020 ASOCIEREA SC TEHNIC ASIST SRL – SC TASS INFRA 132.051 MIL. LEI FARA 3 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE BARLAD 0+000 11+281 BARLAD 1 11.281 27.00% 18.98% ACTIVITATII DE PROIECTARE) ESTIMAT IUNIE 2022 AUTORIZATIE DE CONSTRUIRE A FOST EMISA. LOGISTIC SRL TVA 06.08.2020 - DATA DE ORDINUL DE INCEPERE A LUCRARILOR A FOST EMIS IN DATA DE 06.08.2020 INCEPERE A LUCARILOR) AMPLASAMENTUL LUCRARILOR A FOST PREDAT CATRE ANTREPRENOR IN DATA DE 06.08.2020.

PRETUL PE KM ESTE DE CCA. 20.990.555 LEI FĂRĂ TVA, REPREZENTAND CCA. 4,327,949 EURO FARA TVA. DURATA CONTRACTULUI ESTE DE 174 DE LUNI, DIN CARE: ASOCIEREA S.C. SA&PE CONSTRUCT S.R.L. – S.C. 705.28 MIL. LEI FARA 4 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE GALATI 0+000 33+600 GALATI 1 33.6 0% 0% IUNIE 2021 DECEMBRIE 2025 ANUL 2025 • 12 LUNI PERIOADA DE PROIECTARE, SPEDITION UMB S.R.L. – S.C. TEHNOSTRADE S.R.L. TVA • 42 LUNI PERIOADA DE EXECUTIE A LUCRĂRILOR, • 64 DE LUNI PERIOADĂ DE GARANȚIE A LUCRĂRILOR.

CONTRACT REZILIAT IN DATA DE 04.04.2019 DE CATRE CNAIR SA PENTRU NEINDEPLINIREA DE CATRE ANTREPRENOR A MAI MULTOR INSTIINTARI DE REMEDIERE. EXPERTIZA TEHNICA REALIZATA - 2019 IN DATA DE 23.12.2020 CNAIR A SEMNAT CONTRACTUL AVAND CA OBIECT “CONSTRUCTIA VARIANTEI DE OCOLIRE MIHAILESTI - FINALIZARE LUCRARI”, CU OFERTANTUL DECLARAT CASTIGATOR S.C. VIAROM CONSTRUCT S.R.L. 30.7% - PROGRES IN 31.94% - PROGRES IN CADRUL VALOAREA CONTRACTULUI ESTE DE 36.862.651,20 LEI FARA TVA. CADRUL CONTRACTULUI FEBRUARIE 2021 - DEMARARE CONTRACTULUI REZILIAT; SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE. 5 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE MIHAILESTI 0+000 3+180 S.C. VIAROM CONSTRUCT S.R.L. MIHAILESTI RELICITARE 3.18 REZILIAT; LUCRARI RAMASE DE FEBRUARIE 2022 36.9 MIL. LEI FARA TVA 27.82 % IN CADRUL NOULUI TRASEUL ARE O LUNGIME DE 3,18 KM. 54% IN CADRUL NOULUI EXECUTAT CONTRACT DURATA CONTRACTULUI ESTE DE 72 DE LUNI, DIN CARE: CONTRACT 12 LUNI PERIOADA DE EXECUTIE A LUCRARILOR, 60 DE LUNI PERIOADA DE GARANTIE A LUCRARILOR. A FOST EMIS ORDINUL DE INCEPERE LUCRARI PENTRU DATA DE 15.02.2021. 30.06.2017 (SERVICII DE CONTRACTUL DE PROIECTARE SI EXECUTIA VARIANTEI DE OCOLIRE SATU MARE A FOST SEMNAT IN DATA DE16.11.2015 ASOCIEREA ITINERA SPA COLLINI LAVORI SPA - PROIECTARE) 304.791 MIL. LEI FARA DATA DE INCEPERE A PERIOADEI DE PROIECTARE ESTE 30.06.2017. 6 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE SATU MARE 0+000 19+540 SATU MARE 1 19.54 75.14% 60.75% ESTIMAT DECEMBRIE 2021 VIA DESIGN SRL 28.06.2018 TVA DATA DE INCEPERE EXECUTIE LUCRARi ESTE 28.06.2019-ETAPA I. (EXECUTIE LUCRARI) DATA DE INCEPERE EXECUTIE LUCRARI ETAPA II ESTE 02.12.2020

40% PROGRES 37.5% PROGRES INREGISTRAT CONTRACT REZILIAT DE CATRE INREGISTRAT IN CADRUL COLLINI LAVORI SPA - CONTRACT REZILIAT IN CADRUL CONTRACTULUI 14.10.2014 - CTR REZILIAT ANTREPRENOR IN LUNA IN DATA DE 24.11.2020 A FOST SEMNAT CONTRACTUL NR 92/79265. CONTRACTULUI DE 7 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE TARGU JIU 0+000 19+987 CONTRACT RELICITAT - ASOCIEREA SECOL TARGU JIU RELICITARE 19.987 DE LUCRARI REZILIAT; NOV. 2020 - CONTRACT 05.2018. 207 MIL. LEI FARA TVA A FOST EMIS ORDINUL DE INCEPERE LUCRARI PENTRU DATA DE 15.02.2021. LUCRARI REZILIAT; SOCIETA EDILE COSTRUZIONI E LAVORI S.A. 1.15%IN CADRUL NOULUI RELICITAT SEMNAT CONFORM CONTRACT IN DATA DE 18.02.2021 A FOST PREDAT AMPLASAMENTUL. 9.7% IN CADRUL NOULUI CONTRACT RELICITAT - AUGUST 2022 CONTRACT

VINERI, 16.04.2021, C.N.A.I.R. S.A. A SEMNAT CONTRACTUL PENTRU "CONSTRUCTIA VARIANTEI DE OCOLIRE TECUCI - REST DE EXECUTAT”, CU ASOCIEREA S.C. MAVGO HOLDING S.R.L. – S.C. ANTREPRIZA DE CONSTRUCTII DRUMURI SI CONTRACT REZILIAT IN DATA CONTRACTUL PENTRU AUTOSTRAZI S.R.L. (FOSTA S.C. AQUA PARC S.R.L.) – S.C. BDU MAXI CONSTRUCT S.R.L. – HYDROSTROY AD. DE 20.05.2019.CONTRACTUL "CONSTRUCTIA VARIANTEI DE 29.63% - PROGRES PENTRU "CONSTRUCTIA ASOCIEREA S.C. MAVGO HOLDING S.R.L. – S.C. 58% - PROGRES FIZIC OCOLIRE TECUCI - REST DE VALOAREA CONTRACTULUI ESTE DE 41.735.534,38 LEI FARA TVA. INREGISTRAT IN CADRUL VARIANTEI DE OCOLIRE TECUCI - ANTREPRIZA DE CONSTRUCȚII DRUMURI ȘI INREGISTRAT LA DATA EXECUTAT” A FOST SEMNAT IN SURSA DE FINANTARE: FONDURI EUROPENE NERAMBURSABILE. CONTRACTULUI DE LUCRARI REST DE EXECUTAT” A FOST 8 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE TECUCI 0+000 6+945 AUTOSTRĂZI S.R.L. (FOSTA S.C. AQUA PARC S.R.L.) TECUCI (RELICITARE) RELICITARE 6.945 REZILIERII 16.04.2021. A FOST EMIS 41.74 MIL. LEI FARA TVA VARIANTA DE OCOLIRE TECUCI ARE O LUNGIME DE 6,945 KM. REZILIAT SEMNAT IN 16.04.2021. A FOST – S.C. BDU MAXI CONSTRUCT S.R.L. – 10% IN CADRUL NOULUI ORDINUL DE INCEPE LUCRARI 0% IN CADRUL NOULUI EMIS ORDINUL DE INCEPE HYDROSTROY AD CONTRACT IN 20.05.2021.IN 21.05.2021 A VARIANTA SE DESPRINDE DIN DN24, TRAVERSEAZĂ CU UN PASAJ SUPERIOR DN24 ȘI LINA CF MARASESTI - TECUCI LA KM 0+385,95, CONTINUA IN ALINIAMENT PANA LA INTERSECTIA LA NIVEL CU DJ252H LA KM 2+490, TRAVERSEAZA CONTRACT LUCRARI IN 20.05.2021.IN AVUT LOC PREDAREA CU PASAJ SUPERIOR LINIA CF FAUREI - TECUCI LA KM 6+416,29 SI SE FINALIZEAZA LA KM 6+945 (ECHIVALENT CU KM 6+801,29), LA INTERSECȚIA CU DN25. 21.05.2021 A AVUT LOC AMPLASAMENTULUI PREDAREA AMPLASAMENTULUI PERIOADA CONTRACTUALA DE EXECUTIE A LUCRARILOR ESTE DE 12 DE LUNI, IAR PERIOADA DE GARANTIE ESTE DE 60 DE LUNI.

29.01.2019 - DATA DE INCEPERE PERIOADA DE PROIECT TEHNIC FINALIZAT 272.43 MIL. LEI FARA 9 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE TIMISOARA SUD 0+000 25+690 TIRRENA SCAVI S.P.A TIMISOARA - SECTOR SUD 25.69 34.57% 32.34% PROIECTARE ESTIMAT 2022 ANUL 2022 AUTORIZATIE DE CONSTRUIRE EMISA IN LUNA MARTIE 2020. TVA 25.03.2020 - ORDIN - EXECUTIE LUCRARI IN DERULARE. INCEPERE EXECUTIE LUCRARI

ORDINUL DE INCEPERE A CONTRACTULUI A FOST COMUNICAT CA FIIND 25.09.2020 (PROIECTARE+EXECUTIE). PERIOADA DE PROIECTARE ESTE DE 6 LUNI (FINALIZARE 24.03.2021) SI 24 LUNI EXECUTIE LUCRARI (FINALIZARE 5.535 KM (5 23.03.2023). VIADUCTE, 2 ASOCIEREA SINOHYDRO CORPORATION LIMITED ETAPA 2 - 7 KM INTRE DN 1F 185.54 MIL. LEI FARA DECIZIA DE EXPROPRIERE NR. 1848 DIN 10.11.2020. 10 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE VARIANTA OCOLITOARE ZALAU 0+000 5+535 1 PODURI, 2 1% 15% 2020 2023 – SC GOOD PROOD S.R.L. KM 79+625 - DJ 191C TVA A FOST ACORDATA ANTREPRENORULUI POSESIA SANTIERULUI. INTERSECTII TIP A FOST OBTINUTA AUTORIZATIA DE CONSTRUIRE NR. 17/26.03.2021. GIRATIE) A FOST EMISA HOTARAREA DE GUVERN NR.622 DIN 03.06.2021 PRIVIND SCOATEREA DEFINITIVA DIN FONDUL FORESTIER NATIONAL.

IN DATA DE 19.11.2019 A FOST SEMNAT CONTRACTUL DE PROIECTARE SI EXECUTIE AFERENT ACESTUI OBIECTIV. DRUM DE LEGATURA DN5 - DRUM DE LEGATURA DN5 - SOSEAUA DE 106.638 MIL. LEI FARA IN DATA DE 05.03.2020 A FOST SEMNAT CONTRACTUL DE SUPERVIZARE AFERENT LUCRARILOR. 11 VARIANTE OCOLITOARE PROIECTE IN EXECUTIE VARIANTA OCOLITOARE 0+000 5+720 PORR CONSTRUCT S.R.L. SOSEAUA DE CENTURA - POD 5.72 46.82% 36.45% APRILIE 2020 ESTIMAT 2022 ESTIMAT 2022 CENTURA - POD PRIETENIEI TVA IN DATA DE 15.04.2020 A FOST EMIS ORDINUL DE INCEPERE PENTRU PROIECTARE PRIETENIEI IN DATA DE 21.10.2020 A FOST EMIS ORDINUL DE INCEPRE PENTRU EXECUTIA LUCRARILOR

5.3. VARIANTE OCOLITOARE IN REABILITARE / MODERNIZARE - SEPTEMBRIE 2021

PANA LA DETALII NR. CRT. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL STADIUL FINANCIAR ACTUAL DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDERE VALOARE PROIECT OBSERVAȚII (km) PROCEDURĂ

CONTRACTUL DE EXECUTIE LUCRARI A FOST SEMNAT IN DATA DE 20.06.2019/ AUTORIZATIE DE CONSTRUIRE VALABILA. LUCRARI IN EXECUTIE: DRUM - LUCRARI DE EXCAVATIE DN4 SI CB, LUCRARI DE UMPLUTURI, EXECUTIE STRAT DE FORMA, EXECUTIE FUNDATIE DIN BALAST,ASTERNERE STRAT DE BALSAT STABILIZAT. PASAJ - TURNARE BETON EGALIZARE: 31 DE FUNDATII; TURNARE RADIERE: 31 BUC; EXECUTIE ELEVATII PILE: 27 BUC; EXECUTIE ELEVATII CULEE: 4 BUC; EXECUTIE RIGLE: 9 BUC, ARMARE SI COFRARE 2 BUC, CUZINETI SI ORPITORI LARGIRE LA 4 BENZI A SEISMICI SP1A, SP1B SI P2B, P4B, P1B, COFRARE SI ARMARE RIGLE: P2B1, P3, P5B1, APROVIZIONARE APARATE DE REAZEM. CENTURII RUTIERE A AMENAJARE NOD 31.07.2019 - DATA DE CONSOLIDARI - RAMPA A1: BETON DE EGALIZARE RAMPA A1; RADIERE BETONATE ZID TIP L – 7 BUC; ELEVATII BETONATE ZID TIP L – 6 BUC, EXCAVATIE SEGMENT 2 ZID TIP U, RADIER BETONAT SEGMENT 1 TIP U, ELEVATII BETONATE 1 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI 29+500 33+190 ITINERA SPA MUNICIPIULUI BUCURESTI RUTIER LOT 1: OLTENITA 3.69 24.50% 32.00% INCEPERE PERIOADA DE ESTIMAT 2022 SEPTEMBRIE 2022 169.5 MIL. LEI FARA TVA SEGMENT 1 TIP U; RAMPA A: EXCAVATIE PRIMUL ZID TIP L, BETON DE EGALIZARE ZID TIP L – 7 BUC, RADIERE ZID TIP L, 7 SEGMENTE; ELEVATII ZID TIP L – 4 BUC. SUD INTRE A2 KM 23+600 SI - DN 4 PROIECTARE RAMPA B: EXECUTATA IN PROPORTIE DE 90 %; MONTARE GEODREN, BETON DE PANTA PE ZIDUL TIP L; RAMPA B1: EXECUTATA IN PROPORTIE DE 75 %; RAMPA BUCURESTI: EXCAVATIE ZID DE SPRIJIN TIP L; BETON DE EGALIZARE; A1 KM 55+520 RADIERE BETONATE; ELEVATII BETONATE; RAMPA OLTENITA: RADIERE BETONATE ZID DE SPRIJIN TIP L; BETON DE EGALIZARE; RADIERE BETONATE; ELEVATII BETONATE RETELE DE UTILITATI - RETEA DE DISTRIBUTIE GAZE NATURALE – INTREGIRE CONDUCTA NOUA DN CB SI BRANSAMENTE NOI, S-A DEVIAT RETEAUA PE NOUL TRASEU PE DN4, KM 1+140 LA KM 1+580, SE PREGATESTE O NOUA CUPLARE PE DN4; RETEA DE TELECOMUNICATII – FINALIZATA, TREBUIE INTOCMIT PV LA TERMINAREA LUCRARILOR; RETEA E-DISTRIBUTIE – S-AU DEVIAT TRASEELE JT ANTENA VODAFONE SI REMAT SI TRASEU MT 20 kV – PORCINE 1, SE MONTEAZA CABLURILE PE DN 4, PE TRASEELE DE MEDIE TENSIUNE. RETEA DE CANALIZARE PLUVIALA - RETEA DN 4, REALIZAT APROXIMATIV 2600 M, 83,00%; RETEA CB, REALIZAT APROXIMATIV 1260 M, 32,12 %.

MODERNIZAREA CENTURII 1. CONTRACTUL DE EXECUTIE LUCRARI A FOST SEMNAT IN DATA DE 02.03.2020/ AUTORIZATIE DE CONSTRUIRE VALABILA. RUTIERE A MUNICIPIULUI 235.75 MIL. LEI FARA 2 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI 12+300 23+750 TIRRENA SCAVI S.P.A SECTIUNEA DN 2 - A2 11.524 11.05% 17.61% 04.05.2020 ESTIMAT AUGUST 2021 ANUL 2022 LUCRARI IN EXECUTIE: 3000 MP CURATARE AMPLASAMENT; 2250 MC DECAPARE PAMANT VEGETAL; - 2400 MC SAPATURA CORP DRUM; - 800 MC UMPLUTURI TERASAMENTE; - 500 M RIGOLA DREPTUNGHIULARA; - 600 MC STRAT DE BUCURESTI INTRE A1 - DN7 SI TVA FORMA DIN BALAST; - 650 MC STRAT DE FUNDATIE DIN BALAST; - 25 MP COFRARE PILE; - 3 TONE ARMATURA ELEVATII PASAJE; - 10 MC BETONARE ELEVATII PASAJE; - 500 M PILOTI DE INDESARE; - ACTIVITATI GENERALE. DN2 - A2

LARGIRE LA 4 BENZI A CONTRACTUL DE PROIECTARE SI EXECUTIE PASAJ BERCENI A FOST SEMNAT IN DATA DE 19.03.2019. ASOCIEREA S.C. TRAMECO S.A. - VAHOSTAV -SK, CENTURII RUTIERE A AMENAJARE NOD LUCRARI CE SE EXECUTA: EXECUTIE STRAT DE BALAST INTRE KM 35+220 - KM 35+280; '- EXECUTIE SAPATURA SI STRAT DE FORMA DIN BALASTE INTRE KM 35+240 - KM 35+280; '- EXECUTIE STRUCTURA DE SPRIJIN DIN PAMANT 3 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI 33+190 35+600 A.S. - CONSTRUCTII ERBASU S.A. - GRAFIC TENDS MUNICIPIULUI BUCURESTI RUTIER LOT 2: BERCENI - 2.41 29.96% 16.80% 06.05.2019 ESTIMAT 2022 IUNIE 2022 146 MIL. LEI FARA TVA ARMAT TIP MACRES PE RAMPA BERCENI; '- EXECUTIE RADIER LA CULEEA C3; '- DEMOLARE CAPETE PILOTI SI EXECUTIE SAPATURA LA PILA P20; '- EXECUTIE PILOTI FORATI LA PILA LA CULEEA C4 SI PILA P21; ' - EXECUTIE STRAT DE S.R.L. S.C. (LIDER DE ASOCIERE TRAMECO S.A.) SUD INTRE A2 KM 23+600 SI DJ 401 BALAST STABILIZAT PE DJ INTRE KM 0+820 KM 1+140, PARTEA DREAPTA; A1 KM 55+520

http://www.cnadn MODERNIZAREA CENTURII r.ro/sites/default/f ASOCIEREA S.C. DELTA A.C.M. 93 SRL & AZVIRT RUTIERE A MUNICIPIULUI SECTIUNEA A1 KM A FOST DEMARATA PROCEDURA DE ACHIZITIE PUBLICA PENTRU LUCRARI DE REMEDIERE SI FINALIZARE LUCRARI - REST DE EXECUTAT. iles/DRUMURI_NA 86.5% - PROGRES FIZIC LA 77.73% - PROGRES FINANCIAR 4 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI 55+465 64+160 LLC & S.C. MAXIDESIGN S.R.L. - CONTRACT BUCURESTI INTRE A1 - DN 7 SI 55+465 - DN7 KM 8.695 2021 TRIM IV 2022 106.6 MIL. LEI FARA TVA A FOST PUBLICAT ANUNTUL DE PARTICIPARE. %C8%9AIONALE_% DATA REZILIERII LA DATA REZILIERII REZILIAT DN 2-A2:SECTIUNEA A1 (KM 64+160 DETALII IN LINK-UL DE MAI JOS: C8%98I_VARIANTE 55+465) - DN 7 (KM 64+160) _DE_OCOLIRE_CAL ENDAR.pdf

CONTRACT SEMNAT IN DATA DE 23.10.2018. PROIECTARE SI EXECUTIE AUTORIZATIA DE CONSTRUIRE NR. 13 DIN DATA DE 16.03.2020. PASAJ MOGOSOAIA PE 04.12.2018 - PROIECTARE; 2021- CONFORM ASUMARI ANUL 2022 CONFORM GRAFIC ORDINUL DE INCEPERE PENTRU PROIECTARE A FOST DAT IN DATA DE 04.12.2018. 5 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI SC STRABAG SRL MOGOSOAIA/ DN 1A 0.8 65.00% 37.29% 32.26 MIL. LEI FARA TVA CENTURA BUCURESTI PESTE 02.04.2020 - EXECUTIE ANTREPRENOR CONTRACT ORDINUL DE INCEPERE PENTRU LUCRARI A FOST EMIS IN DATA DE 02.04.2020 DN 1A LUCRARI CE SE EXECUTA: RAMPA CHITILA - GRINDA DE CORONAMENT, PLACI DE RACORDARE, MONTARE LISE LA GRINDA DE CORONAMENT, PE PASAJ: SE ARMREAZA SI SE MONTEAZA LISE PREFABRICATE CONSOLE, RAMPA OTOPENI SE ASTERNE STRATA MIXTURA ASFALTIACA AB 31.5 (STRATA DE BAZAA) UTILITATI: CANALIZARE APE PLUVIALE, CAMERA DE CADERE 1 , CAMIN VIZITARE 8, 9 SI 10, SUBTRAVERSARE CAMINE APA NOVA.

PENETRATIE PRELUNGIREA GHENCEA – DOMNESTI SI CAIET DE SARCINI, APROBAT SUPRALARGIRE BULEVARDUL REFERAT DE NECESITATE, GHENCEA INTRE STRADA 139.255 MII lei FARA PAAP APROBAT 02.02.2021 6 VARIANTE OCOLITOARE IN REABILITARE/MODERNIZARE VARIANTA OCOLITOARE CENTURA BUCURESTI BRASOV SI TERMINAL 1.1 TVA - VALOARE PUBLICAT IN SEAP 05.03.2021 TRAMVAI 41” CU PROIECTUL PROIECTARE DESCHIDEREA OFERTELOR 08.04.2021 “PASAJ SUPRATERAN PE DJ 602, CENTURA BUCURESTI - DOMNESTI 5.4. VARIANTE OCOLITOARE IN PREGATIRE FAZA EXECUTIE LUCRARI - SEPTEMBRIE 2021

PANA LA DETALII NR. CRT. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL STADIUL FINANCIAR ACTUAL DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDERE VALOARE PROIECT OBSERVAȚII (km) PROCEDURĂ

VARIANTE OCOLITOARE IN PREGATIRE FAZA EXECUTIE PROCEDURA DE LICITATIE ATRIBUIRE CONTRACT 293.084 MIL LEI FARA 1 VARIANTA OCOLITOARE VARIANTA OCOLITOARE SIGHISOARA 0+000 13+057 SIGHISOARA 13.057 0.00% 0.00% 14.06.2021 ESTIMAT 23.11.2021 ESTIMAT 2021 14.06.2021 - DATA PUBLICARII ANUNTULUI, 31.08.2021 - DATA DE DEPUNERE A OFERTELOR, 23.11.2021 - DATA FINALIZARE PROCEDURA DE EVALUARE LUCRARI PROIECTARE SI EXECUTIE IN DERULARE TVA

VARIANTE OCOLITOARE IN PREGATIRE FAZA EXECUTIE VARIANTA OCOLITOARE SFANTU 2020 - FINALIZARE PROIECTARE, 2 VARIANTA OCOLITOARE 0+000 8+000 CONTRACT ELABORARE SF FINALIZAT SFANTU GHEORGHE 1 8 07.05.2018 41.47 MIL. LEI FARA TVA PROCEDURA DE ATRIBUIRE CONTRACT PROIECTARE SI EXECUTIE - IN DERULARE, ETAPA EVALUARE OFERTE. LUCRARI GHEORGHE ETAPA STUDIU DE FEZABILITATE

http://www.cnadn LARGIRE LA 4 BENZI A r.ro/sites/default/f CENTURII RUTIERE A 31,508lei fara TVA - LOT iles/DRUMURI_NA VARIANTE OCOLITOARE IN PREGATIRE FAZA EXECUTIE MUNICIPIULUI BUCURESTI 1 3 VARIANTA OCOLITOARE CENTURA BUCURESTI 35+600 55+465 18,68 DETALII PRIVIND PROCEDURA DE ATRIBUIRE A CONTRACTULUI IN LINK-UL DE MAI JOS %C8%9AIONALE_% LUCRARI SUD INTRE A1 (KM 55+520) SI 638,945 lei fara TVA - C8%98I_VARIANTE DN 5 (KM 40+000) - LOT 1 SI LOT 2 _DE_OCOLIRE_CAL LOT 2 ENDAR.pdf

5.5. VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC - SEPTEMBRIE 2021

PANA LA DETALII NR. CRT. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL STADIUL FINANCIAR ACTUAL DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDERE VALOARE PROIECT OBSERVAȚII (km) PROCEDURĂ

CONTRACT PRESTARI SERVICII DE PROIECTARE FAZELE SF+PT+DE+DATC+AT SEMNAT IN DATA DE 14.03.2018. ORDIN DE INCEPERE NR.3B/4773/26.03.2018 EMIS IN DATA DE 26.03.2018 PENTRU SERVICII DE PROIECTARE IN FAZA SF. SF FINALIZAT SI APROBAT PRIN HG INDICATORI TEHNICO-ECONOMICI NR. 58/24.02.2021. ORDIN DE INCEPERE PENTRU PT+DTAC SI AVIZE - NR. 3B/4773/26.03.2018 - INCEPAND CU 01.10.2020. PROIECTUL TEHNIC A FOST PREDAT IN 29.01.2021. DOCUMENTATIA PENTRU PROMOVAREA HG DE EXPROPRIERI SI DOCUMENTATIA PT + DTAC AU FOST CONDIȚIONATE DE SUPRAPUNEREA OBIECTIVULUI CU UN OBIECTIV PRIVAT FINANTAT DIN FONDURI EUROPENE AFIR, FIIND NECESAR URMATOARELE: * SEDINTE DE LUCRU LA SEDIUL MINISTERULUI TRANSPORTURILOR SI LA SEDIU AFIR; * UN PUNCT DE VEDERE AFIR OBTINUT IN DATA DE 02.06.2021 - PRIN CARE AFIR ESTE DE ACORD CA BENEFICIARUL PRIVAT S-A MODIFICE AMPLASAMENTUL AFECTAT DE EXPROPRIERE NECESARA REALIZARII VO CU CONDITIA MENTINERII CONDITIILOR DE ELIGIBILITATE SI SELECTIE INSCRISE IN CEREREA DE FINANTARE; 2021 - FINALIZARE ETAPA DE VALOARE PROIECT 1.6 * AVIZAREA IN CTE DRDP BUCURESTI A DOCUMENTATIEI PT+DTAC IN VARIANTA NOUA PROPUSA PENTRU CORELAREA OBIECTIVELOR, AVIZ OBTINUT IN DATA 04.06.2021; PROIECTARE. 12.068 70% - SF FINALIZAT SI MIL LEI FARA TVA; * AVIZAREA IN CTE CNAIR A DOCUMENTATIEI PT+DTAC A DOCUMENTATIEI CU SOLUTIA MODIFICATA FATA DE CEA DIN SF; DURATA DE EXECUTIE A CONFORM APROBAT PRIN HG VALOARE LUCRARI CF. * AVIZARE IN CTE CNAIR SIGURANTA CIRCULATIEI PENTRU PROIECT VO GIURGIU IMPREUNA CU PROIECTUL DE SEMNALIZARE SI MARCAJE SI CU PROIECTUL DE PARAPETE; CONTRACT ELABORARE FAZE DE PROIECTARE LUCRARILOR : 36 DE LUNI DE LA 1 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE GIURGIU 0+000 12+068 GIURGIU 1 VARIANTEI DE INDICATORI TEHNICO - 57% 14.03.2018 SF - VARIANTA 4 MAI SUNT DE ELABORAT : SF+PT+DE+DTAC+AT IN DERULARE ORDINUL DE INCEPERE, DUPA TRASEU ECONOMICI NR. AVIZATA: TOTAL * DETALII DE EXECUTIE 1 LUNA; FINALIZAREA SERVICIILOR DE APROBATA 58/24.02.2021 GENERAL - 343.36 MIL *PREGATIRE DOCUMENTATIE DE ATRIBUIRE PENTRU ACHIZITIA LUCRARI DE EXECUTIE: 2 LUNI; PROIECTARE SI OBTINEREA LEI FARA TVA * DOCUMENTATIA CADASTRALA PENTRU HG DE EXPROPRIERI DE UTILITATE PUBLICA; AUTORIZATIEI DE CONSTRUCTIE MAI SUNT DE OBTINUT: * AVIZ CTE CNAIR PENTRU FAZA PT+DTAC; * AUTORIZATIA DE CONSTRUIRE SI HG DE EXPROPRIERI DE UTILITATE PUBLICA; * AVIZ CTE DRDP BUCURESTI PENTRU FAZA DE; IN DATA DE 25.06.2021 CA URMARE A SOLICITARII CNAIR - DEPARTAMENT OBTINERE FINANTARI PRIN ADRESA NR. 3B/ 2737/25.06.2021, DRDP BUCURESTI A INAINTAT DOCUMENTATIILE TEHNICE IN FAZELE SF - FINAL AVIZAT, PT + DTAC IN VARIANTA INAINTATA LA CTE CNAIR, PENTRU A FI PUSE LA DISPOZITIA CONSILIULUI JUDETEAN GIURGIU PENTRU INCHEIEREA UNUI PARTENERIAT PENTRU IMPLEMENTAREA OBIECTIVULUI IN TEMEIUL OUG NR. 101/2020. IN DATA DE 10.08.2021 A AVUT LOC SEDINTA CTE CNAIR IN CARE A FOST ANALIZATA DOCUMENTATIA INTOCMITA PENTRU FAZA PT+DTAC, IN URMA CAREIA MEMBRII CTE AU DECIS AMANAREA AVIZARII SI NECESITATEA UNOR COMPLETARI/JUSTIFICARI ADUSE DOCUMENTATIEI. IN DATA DE 19.08.2021 S-AU TRANSMIS LA CNAIR JUSTIFICARILE SI CLARIFICARILE SOLICITATE DE MEMBRI CTE CNAIR SI SE PROPUNE REANALIZAREA SI AVIZAREA DOCUMENTATIEI PAC.

CONTRACT DE SERVICII DE PROIECTARE ACTUALIZARE A STUDIULUI INITIAL INCLUSIV DOCUMENTATII PENTRU AVIZE,OBTINERE AVIZE SI ACORDURI, ELABORARE PROIECT TEHNIC INCLUSIV DTAC, DETALII DE EXECUTIE SI ASISTENTA TEHNICA PENTRU OBIECTIVUL VARIANTA DE OCOLIRE RM. VALCEA NR. 148 /04.10.2019, CU ORDIN DE INCEPERE ACTIVITATI EMIS IN DATA DE 16.12.2019, IN DERULARE. PRESTATOR SC SEARCH CORPORATION SRL. VALOAREA CONTRACT PROIECTARE: 3,832,075.75 LEI FARA TVA. DOCUMENT DE AVIZARE CTE-CNAIR NR. 4915/09.04.2020 - ACTUALIZARE SF - ALTERNATIVE DE TRASEU. CERTIFICATUL DE URBANISM NR. 12/10054/06.08.2020 EMIS DE C.J. VALCEA ""NU POATE FI UTILIZAT IN SCOPUL DECLARAT"" URMARE A AVIZULUI NEFAVORABIL AL PRIMARIEI ORASULUI CALIMANESTI. 276.36 MIL. LEI FARA 2 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE RAMNICU VALCEA 0+000 21+837 SC SEARCH CORPORATION SRL RAMNICU VALCEA PROIECTARE 21.84 30% 0% 16.12.2019 2022 DOCUMENT DE AVIZARE CTE-CNAIR NR. 4992/19.10.2020 - ACTUALIZARE SF - ALTERNATIVE DE TRASEU (AMC ETAPA 4) - VARIANTE PENTRU RACORDAREA LA CENTURA CALIMANESTI. TVA C.J. VALCEA A EMIS UN NOU CERTIFICAT DE URBANISM, NR. 70/16141/23.11.2020, CARE SPECIFICA FAPTUL CA ""NU POATE FI UTILIZAT IN SCOPUL DECLARAT"" URMARE A AVIZULUI NEFAVORABIL AL PRIMARULUI COMUNEI DAESTI. DOCUMENT DE AVIZARE CTE-DRDP CRAIOVA NR. 3/20.01.2021 - STUDIUL ALTERNATIVELOR DE TRASEU IN ZONA LOCALITATII FEDELESOIU, COMUNA DAESTI - ETAPA 5. DOCUMENTATIA TEHNICA A FOST INAINTATA LA CJ VALCEA CARE A EMIS CERTIFICATUL DE URBANISM NR. 05/19899/26.01.2021 CARE ""NU POATE FI UTILIZAT IN SCOPUL DECLARAT"" URMARE A AVIZULUI NEFAVORABIL AL PRIMARULUI COMUNEI DAESTI. S-A EMIS ORDIN DE SISTARE DIN DATA DE 29.01.2021. AU FOST INITIATE DEMERSURI IN VEDEREA ADRESARII INSTANTELOR JUDECATORESTI COMPETENTE PENTRU CHEMARE IN JUDECATA A C.J. VALCEA SI A REPREZENTANTULUI UAT DAESTI.

108.11 MIL. LEI FARA CONTRACT PRESTARI SERVICII COMPLETARE STUDIU DE FEZABILITATE SEMNAT LA DATA DE 05.12.2019, IN DERULARE. 3 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE REGHIN 0+000 10+440 SC TPF INGINERIE SRL REGHIN 1 10.44 05.12.2019 2021 TVA CONTRACT COMPLETARE SF IN DERULARE - FINALIZARE 2021

RELICITAREA LUCRARILOR RAMASE DE EXECUTAT SE VA 09.10.2014 (ORDIN DE REALIZA IN 2 ETAPE: INCEPERE PENTRU COPISA CONSTRUCTORA PIRENAICA SA - CONTRACT REZILIAT ETAPA 1: REVIZUIRE 34.26% -PROGRES CONTRACTUL REZILIAT) LICITATIE ATRIBUIRE CONTRACT REST LUCRARI RAMASE DE EXECUTAT, CU TERMEN DEPUNERE OFERTE: 26.08.2020 37.55% - PROGRES FINANCIAR CONTRACT 1 INCETAT PE CALE PROIECT TEHNIC INREGISTRAT IN CADRUL ORDIN DE INCEPERE A 134.80 MIL. LEI FARA PROCEDURA ANULATA ADMINISTRATIV PENTRU NEDEPUNERE DE OFERTE 4 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE TARGU MURES 0+000 11+643 TARGU MURES 11.643 INREGISTRAT LA DATA AMIABILA IN 29.12.2017 ANUL 2023 ETAPA 2: LICITATIE CONTRACTULUI DE LUCRARILOR -PENTRU TVA DEMERSURILE IN VEDEREA ACTUALIZARII PROIECTULUI TEHNIC SUNT DEMARATE DE CATRE DRDP BRASOV. REZILIERII LUCRARI RAMASE DE LUCRARI REZILIAT CONTRACTUL RELICITAT - VA FI IN DATA DE 23.02.2021, A FOST PUBLICAT IN SEAP ANUNTUL NR. CN1029446 CU PRIVIRE LA ACHIZITIA PUBLICA CARE VA AVEA CA SCOP ACTUALIZAREA DOCUMENTATIEI TEHNICE PT+DDE VARIANTA DE OCOLIRE TARGU MURES. EXECUTAT, CORELATE SPECIFICAT ULTERIOR PROCEDURA DE LICITATIE IN DERULARE LA NIVELUL DRDP BRASOV CU PROIECTUL TEHNIC SEMNARII ACESTUIA REVIZUIT

"CONTRACTUL PENTRU ELABORARE SF, PT SI DTAC A FOST SEMNAT IN DATA DE 26.07.2019 . ORDINUL DE INCEPERE A FOST EMIS IN LUNA FEBRUARIE 2020. SC CONSITRANS SRL - CONTRACT PROIECTARE STUDIU DE FEZABILITATE FINALIZAT, URMEAZA PARCURGEREA PROCEDURII PRIVIND APROBAREA INDICATORILOR TEHNICO-ECONOMICI (AVIZ CTE CNAIR, AVIZ MT, AVIZ CI SI HG). DUPA EMITEREA HG, TERMENUL CONTRACTUAL 5 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE ALTERNATIVA TECHIRGHIOL 0+000 28+833 TECHIRGHIOL 1 28.833 30% 0% FEBRUARIE 2020 DECEMBRIE 2021 DECEMBRIE 2021 5.372 MIL. LEI FARA TVA ELABORARE SF, PT SI DTAC PENTRU EMITERE PT ESTE 3 LUNI. AMC 1+2 A FOST AVIZAT IN CADRUL CTE CNAIR SA. IN CURS DE FINALIZARE INVESTIGATIILE GEOTEHNICE DE TEREN."

SF - 2006 (AVIZ MT 36/27/19.03.2007). CONTRACT REVIZUIRE SF SI ELABORARE PT + DTAC SEMNAT IN LUNA MAI 2019 - IN DERULARE, CU TERMEN DECALAT FINALIZARE SEPTEMBRIE 2021 6 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE VASLUI 0+000 14+940 CONTRACT REVIZUIRE SF IN DERULARE VASLUI 1 14.94 2019 2021 142.8 MIL. LEI FARA TVA DURATA REVIZUIRE SF – 8 LUNI AVIZ CTE DRDP IASI NR. 16891/19.04.2021 IN AVIZARE LA CTE CNAIR SA DURATA ELABORARE PT – 6 LUNI VALOARE CONTRACT PROIECTARE: 1.478.500 LEI

CONTRACT IN DERULARE. A AVUT LOC SEDINTA NR. 1 DE PROGRES IN DATA DE 25.03.2021. VALOARE SPF + SF 2.732 IN DATA DE 26.04.2021 PRESTATORUL A TRANSMIS STUDIUL DE PREFEZABILITATE CONFORM GRAFICULUI ACTIVITATILOR. AU FOST FORMULATE OBSERVATII ASUPRA DOCUMENTATIE STUDIUL DE PREFEZABILITATE. PRESTATORUL A 7 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE PITESTI VEST 0+000 20+000 TPF INGINERIE SRL PITESTI VEST 20 0% 0% MIL LEI FARA TVA TRANSMIS SPF-UL REVIZUIT. A FOST PREDAT STUDIUL DE TRAFIC REVIZUIT. IN CURS DE ANALIZA LA BENEFICIAR (TRANSMIS LA CESTRIN). SE ASTEAPTA NOTA DE PREZENTARE PENTRU SUSTINEREA SPF IN CADRUL CTE-CNAIR S.A. 8 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE DOROHOI 0+000 13+900 SC NV CONSTRUCT SRL DOROHOI 13.9 0% 0% 429.22 MII LEI IN CURS DE FINALIZARE STUDIUL DE FEZABILITATE, DUPA APROBARE PUZ DOROHOI

CONTRACT IN DERULARE. 9 VARIANTE OCOLITOARE IN PREGATIRE FAZA SF/PT/DTAC VARIANTA OCOLITOARE VARIANTA OCOLITOARE TIMISOARA VEST 0+000 22+000 SEARCH CORPORATION SRL TIMISOARA 22 18.01.2021 18.04.2022 3.66 MIL. LEI FARA TVA IN DATA DE 20.05.2021 FOST AVIZAT IN CTE CNAIR SA - ANALIZA MULTICRITERIALA ETAPA 1. IN CURS DE ELABORARE DOCUMENTATIA AMC ETAPA 2

5.6. VARIANTE OCOLITOARE IN PREGATIRE FAZA PROIECTARE - SEPTEMBRIE 2021

PANA LA DETALII NR. CRT. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL STADIUL FINANCIAR ACTUAL DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDERE VALOARE PROIECT OBSERVAȚII (km) PROCEDURĂ

2.33 MIL LEI FARA TVA PROCEDURA DE ACHIZITIE PUBLICA PENTRU CONTRACTUL DE SERVICII DE „ELABORARE STUDIU DE FEZABILITATE PENTRU VARIANTA DE OCOLIRE BISTRITA”, A FOST ANULATA. 1 VARIANTE OCOLITOARE IN PREGATIRE FAZA PROIECTARE VARIANTA OCOLITOARE VARIANTA OCOLITOARE BISTRITA 0+000 15+000 BISTRITA 1 15 (VALOARE ESTIMATA OBIECTIVUL FACE PARTE DIN ,,AUTOSTRADA NORDULUI” – FIIND SPECIFICAT IN STUDIUL DE FEZABILITATE CA DRUMUL DE MARE VITEZA BAIA MARE-SUCEAVA: LOT 1 BAIA MARE-BISTRITA SI LOT 2 BISTRITA-VATRA DORNEI, VA CONTRACT S.F.) INDEPLINI SI FUNCTIA DE VARIANTA DE OCOLIRE PENTRU LOCALITATILE INTERSECTATE DE ACESTA.

CNAIR SA A TRANSMIS CATRE MINISTERUL TRANSPORTURILOR SI INFRASTRUCTURII CEREREA DE FINANTARE PENTRU PROIECTUL: ""ELABORARE STUDIU DE FEZABILITATE, PROIECT TEHNIC DE EXECUTIE INCLUSIV PAC, DETALII DE EXECUTIE, ASIGURAREA ASISTENTEI TEHNICE PE PARCURSUL EXECUTIEI DE LUCRARI SI IN PERIOADA DE GARANTIE A LUCRARILOR EXECUTATE PENTRU OBIECTIVUL DE INVESTITIE: DRUM DE LEGATURA PENTRU SPORIREA CAPACITATII DE TRAFIC INTRE DN6 (ZONA UZINEI FORD) SI DRUMUL EXPRES CRAIOVA – PITESTI (TRONSONUL 1)"". DRUM DE LEGATURA DN6 - DRUM EXPRES INITIERE PROCEDURA DE ACHIZITIE ATRIBUIRE 2 VARIANTE OCOLITOARE IN PREGATIRE FAZA PROIECTARE VARIANTA OCOLITOARE 10 CRAIOVA-PITESTI (TRONSONUL 1) CONTRACT DE PRESTARI SERVICII DE PROIECTARE PROCEDURA DE ACHIZITIE IN DERULARE CU O VALOARE ESTIMATA A CONTRACTULUI DE 1.500.000 LEI INCLUSIV TVA. TERMEN LIMITA DE DEPUNERE A OFERTELOR: 08.09.2021. DURATA ESTIMATA A PRESTARII SERVICIILOR ESTE DE 89 LUNI (3 LUNI – ELABORARE SF INCLUSIV DOCUMENTATII PENTRU OBTINERE AVIZE/ACORDURI; 2 LUNI – ELABORARE PT INCLUSIV DTAC SI DE; 24 LUNI – ASISTENTA TEHNICA PE PARCURSUL EXECUTIEI LUCRARILOR; 60 LUNI – ASISTENTA TEHNICA IN PERIOADA DE GARANTIE A LUCRARILOR).

5.7. VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU AUTORITATILE LOCALE - SEPTEMBRIE 2021

PANA LA DETALII NR. CRT. CATEGORIE DRUM RANG DRUM INDICATIV DRUM DE LA (km) ANTREPRENOR SECTORUL LOTUL LUNGIME (km) STADIUL FIZIC ACTUAL STADIUL FINANCIAR ACTUAL DATA ÎNCEPERII DATA FINALIZĂRII AN DESCHIDERE VALOARE PROIECT OBSERVAȚII (km) PROCEDURĂ

OBIECTIVUL A FOST TRANSFERAT CATRE CJ BIHOR IN VEDEREA REVIZUIRII DOCUMENTATIEI TEHNICE SI IMPLEMENTARII ACESTUIA IN BAZA OUG 101/2020. DECEMBRIE 2020 - A FOST SEMNAT UN PARTENERIAT INTRE CNAIR SI CJ BIHOR IN ACEST SENS VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU 1 VARIANTA OCOLITOARE VARIANTA OCOLITOARE ALESD 0+000 16+840 ALESD 16.84 IN DATA DE 20.05.2021 A FOST AVIZAT IN CADRUL CTE CNAIR SA STUDIUL DE FEZABILITATE. AUTORITATILE LOCALE IN DATA DE 21.05.2021 A FOST AVIZAT IN CADRUL CTE MTI STUDIUL DE FEZABILITATE IUNIE 2021- URMEAZA AVIZAREA IN CADRUL CTE IM SI PROMOVAREA HG DE APROBARE A INDICATORILOR TEHNICO ECONOMICI

ETAPA I – VARIANTA SUD 126.88 MIL. LEI FARA PENTRU IMPLEMENTAREA ACESTUI OBIECTIV PRIMARIA MUNICIPIULUI IASI A INAINTAT O PROPUNERE DE SCHIMBARE A TRASEULUI, CA URMARE A IMPOSIBILITATII PASTRARII TRASEULUI PE BULEVARDUL POITIERS SI STRADA TREI VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU 19+690 26+460 2 VARIANTA OCOLITOARE VARIANTA OCOLITOARE IASI OBIECT 3 – VARIANTA TRAFIC 6.77 TVA (VALOARE FANTANI (KM 19+690 - KM 26+460). AUTORITATILE LOCALE (SELGROS) (DN28) GREU ESTIMATA) PROPUNEREA A FOST ACCEPTATA DE CNAIR, URMAND A SE IDENTIFICA SURSA DE FINANTARE.

PENTRU IMPLEMENTAREA ACESTUI OBIECTIV A FOST SEMNAT UN PARTENERIAT DE IMPLEMENTARE INTRE CNAIR SA SI PRIMARIA MEDIAS IN BAZA PREVEDERILOR OUG 101/2020. VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU OBIECTIVUL SE IMPLEMENTEAZA DE CATRE UAT MEDIAS. 3 VARIANTA OCOLITOARE VARIANTA OCOLITOARE MEDIAS 0+000 8+500 MEDIAS 1 8.5 2022 2024 AUTORITATILE LOCALE A FOST SEMNAT CONTRACTUL DE REVIZUIRE A STUDIULUI DE FEZABILITATE DE CATRE PRIMARIA MEDIAS IN LUNA IUNIE 2021. A FOST EMIS ORDINUL DE INCEPERE IN DATA DE 10.06.2021 - TERMEN PENTRU EMITEREA RAPORTULUI DE INCEPUT- 31.07.2021

COPISA CONSTRUCTORA PIRENAICA SA - CONTRACT REZILIAT LICITATIE ATRIBUIRE OBIECTIVUL A FOST TRANSFERAT CATRE CJ BIHOR IN VEDEREA REVIZUIRII DOCUMENTATIEI TEHNICE SI IMPLEMENTARII ACESTUIA IN BAZA OUG 101/2020. VARIANTE OCOLITOARE - PROIECTE IN COLABORARE CU CONTRACT REZILIAT DE CATRE CONTRACT REZILIAT DE CATRE CONTRACT REZILIAT DE CATRE 257.413 MIL. LEI FARA 4 VARIANTA OCOLITOARE VARIANTA OCOLITOARE STEI 0+000 27+230 CONTRACT REST LUCRARI RAMASE DE STEI 1 27.23 0% 0% A FOST SEMNAT IN LUNA DECEMBRIE 2020, PARTENERIATUL INTRE CNAIR SI CJ BIHOR IN ACEST SENS. AUTORITATILE LOCALE ANTREPRENOR ANTREPRENOR ANTREPRENOR TVA EXECUTAT, CU TERMEN DEPUNERE OFERTE : CONTRACT REVIZUIRE STUDIU DE FEZABILITATE IN DERULARE - ESTIMAT FINALIZARE TRIM. III 2021 22.06.2020