INDIAN BUREAU OF MINES MINERALS DEVELOPMEMT AND REGULATION DIVISION MCDR INSPECTION REPORT Bhubaneshwar regional office

Mine file No : ORI/LST-DOL/SNG/MCDR-2/BBS Mine code : 38ORI13003 (i) Name of the Inspecting : U11( ) DAYANAND UPADHYAY Officer and ID No. (ii) Designation : Sr. Asst. Contrl. Mines (iii) Accompaning mine : Shri A.K. Barik, Mines manager. Official with Designation (iv) Date of Inspection : 15/12/2018 (v) Prev.inspection date : 29/11/2017

PART-I : GENERAL INFORMATION 1. (a) Mine Name : BIRMITRAPUR (b) Registration NO. : IBM/4649/2011 (c) Category : A Other than Fully Mech. (d) Type of Working : Opencast (e) Postal address State : ORISSA District : SUNDARGARH Village : BIRMITRAPUR Taluka : BIRMITRAPUR Post office : BIRMITRAPUR Pin Code : 770033 FAX No. : 0661-2610270 E-mail : [email protected] Phone : 0661-2610270 (f) Police Station : Birmitrapur (g) First opening date : 01/01/1922 (h) Weekly day of rest : SUN 2. Address for : LIMESTONE & DOLOMITE MINE correspondance VILL-RAIPUR,BANUMUNDA PO-BIRAMITRAPUR

3. (a) Lease Number : ORI0011 (b) Lease area : 793.97 (c) Period of lease : (d) Date of Expiry : 31/03/2020

4. Mineral worked : DOLOMITE Associated LIMESTONE Main PAGE : 2

5. Name and Address of the Lessee : BISRA STONE LIME CO. LTD BIRAMITRAPUR DISTRICT ORISSA SUNDARGARH ORISSA Phone: FAX :

Owner : Bisra Stone & lime company ltd Birmitrapur SUNDARGARH ORISSA Phone: 0661-610202. FAX :

Agent : C.S. Tripathy At+ Post-Birmitrapur Dist- Sundargarh SUNDARGARH ORISSA Phone: 0661-2610069 FAX : 0661-261270 Mining Engineer Name : C.R. Nayak,Full Time Qualification : BE(Mining) Appointment/ : 25/03/2002 Termination date Geologist Name : Dr. A.K. Mohapatra,Full Time Qualification : M.sc(Geo.) Appointment/ : 30/12/1992 Termination date Manager Name : A.K.BARIK Qualification : AMIE(MINING) Appointment/ : 14/09/1992 Termination date

6. Date of approval of Mining : Renewal under rule 22 MCR1960 06/07/2005 Plan/Scheme of Mining Mining Scheme rule 12 MCDR1988 12/10/2009 Modif.approved Mining Scheme 14/09/2010 Mining Scheme rule 12 MCDR1988 27/08/2014 FMCP under 23C(1) 05/01/2018 MP modif under 17(3) MCR 2016 05/04/2018 PAGE : 3

PART - II : OBSERVATION/COMMENTS OF INSPECTING OFFICERS Exploration :

Sl.No. Item Proposals Actual work Remarks

1a Backlog of 17 number of Proposed bore holes not Proposed bore previous year bore holes in drilled. holes not drilled. 2017-18. Shortcomings pointed out through violation letter.

1b Exploration over In 2017-18, Proposed bore holes not Proposed bore lease area for total 17 nos. drilled. holes not drilled. geological axis 1 of bore holes Shortcomings or 2 under G1/G2 pointed out Level of through violation exploration. letter.

1c Exploration In 2017-18, Proposed bore holes not Proposed bore Agencies and total 17 nos. drilled. holes not drilled. Expenditure in of bore holes Shortcomings lakh rupees under G1/G2 pointed out during the year Level of through violation exploration. letter.

1d Balance area to In 2017-18, Proposed bore holes not Proposed bore be explored to total 17 nos. drilled. holes not drilled. bring Geological of bore holes Shortcomings axis in 1 or 2 under G1/G2 pointed out Level of through violation exploration. letter.

1e Balance reserve Balance Balance reserve as on Balance reserve as as on 01/04/20 reserve as 01/04/2018 on 01/04/2018 per Scheme of Limestone Proved Limestone Proved mining Reserve-154.93 Million T Reserve-154.93 approved on & resources-106.04 Million T & 27/08/2014, Million T resources-106.04 Limestone Dolomite Proved Million T Proved Reserve-116.0 Million T Dolomite Proved Reserve- & resources-48.79 Reserve-116.0 154.93 Million T Million T & Million T & resources-48.79 resources- Million T 106.04 Million T Dolomite Proved Reserve-117.4 Million T & resources- 48.79 Million T PAGE : 4

1f General remarks In 2017-18, Proposed bore holes not About 451.24 ha of inspecting total 17 nos. drilled. area has been officers on of bore holes explored under geology, under G1/G2 G1/G2 level by exploration etc Level of putting 134 nos. exploration. of bore holes. Proposed bore holes not drilled. Shortcomings pointed out through violation letter.

Development :

Sl.No. Item Propasals Actual work Remarks

2a Location of Patpahar Development and Proposed limestone development dolomite production is only quarries & other w.r.t.lease area quarry concentrated in Patpahar dolomite quarries (1300W/600W & dolomite quarry not developed. 200N/600N), (1300W/600W & Shortcomings Main dolomite 200N/600N), pointed out quarry through violation (400N/800N& letter. 6200W/5600W), Gurupahar limestone quarry (2800W/2200W & 200N/600N) & Durasani/New hoist limestone quarry (4600W/4200W & 800N/1000N). 2b Separate benches Separate Separate benches in OB Separate benches in topsoil, benches in OB and ore have been in OB and ore have overburden and and ore, top maintained. been maintained. minerals (Rule soil bench- 15) nil. 2c Stripping ratio 1:0.12 T/cu.m 1:0.25T/cu.m for Stripping ratio is or ore to OB for limestone dolomite. more or less same. ratio & 1:0.21 T/cu.m for dolomite. 2d Quantity of Not proposed. Nil. There is no top topsoil soil generation. generation in m3 PAGE : 5

2e Quantity of 258380cu.m 144362cu.m Less quantity of overburden OB generated due generation in m3 to less production of ROM & limestone quarry not developed as proposed. 2f General remarks The Development and Proposed limestone of inspecting development is production is only quarries & other officers on proposed in 04 concentrated in Patpahar dolomite quarries development of quarries. dolomite quarry. not developed. pit w.r.t. type Shortcomings of deposit etc pointed out through violation letter.

Exploitation:

Sl.No. Item Propasals Actual work Remarks

3a Number of pit 04 pits Development and Proposed limestone proposed for production is only quarries & other production concentrated in single dolomite quarries pit i.e Patpahar not developed. dolomite quarry. Shortcomings pointed out through violation letter. 3b Quantity of ROM Limestone- ROM production reported ROM Production is mineral 3481884T & in 2017-18 for dolomite less due to low production Dolomite - is 567121.679T market demand. No proposed 2991104T production of limestone is carried out. Shortcomings pointed out through violation letter. 3c Recovery of 80% Recovery of dolomite is No production of sailable/usable reported 80%. limestone is mineral from ROM carried out. production Shortcomings pointed out through violation letter. PAGE : 6

3d Quantity of Limestone- Limestone-Nil, Dolomite- Mineral reject mineral reject 325542T, 910T generation is low generation Dolomite- due to less ROM 280416T production of dolomite and not worked out limestone quarries as proposed. 3e Grade of mineral 35% to 42% Cao Dolomite-910T , -18% Mgo No production rejects for limestone for the year 2017-18. reported from generation and and 15 to19% limestone. threshold value Mgo for Shortcomings declared. dolomite. pointed out through violation letter. 3f Quantity of sub Limestone- Limestone-Nil, Dolomite- Mineral reject grade mineral 325542T, 910T generation is low generation. Dolomite- due to less ROM 280416T production of dolomite and not worked out limestone quarries as proposed. 3g Grade of sub 35% to 42% Cao Dolomite-910T , -18% Mgo Mineral reject grade mineral for limestone for the year 2017-18. generation is low generation and 15 to19% due to less ROM Mgo for production of dolomite. dolomite and not worked out limestone quarries as proposed. 3h Manual / Mechanised. Mechanised. Mechanised. Mechanised method adopted for segregating from ROM 3i Any analysis or Not proposed. Nil. Only crushing and beneficiation screening is study proposed practiced. and carried out for sub grade mineral and rejects. PAGE : 7

3j Provision of DTH drilling Drilling and blasting is Drilling and drilling and of 115 mm dia. carried out with DTH blasting is blasting in Blast hole drilling of 115 mm dia. carried out with mineral benches with crtridge Blast hole with crtridge DTH drilling of explosive explosive alongwith 115 mm dia. Blast alongwith delay detonator. hole with crtridge delay explosive detonator. alongwith delay detonator. 3k Provision of BACK HOE 1.8 BACK HOE 1.8 CU.M-10, Excavator, Loader mining CU.M-10, SHOVEL (HYDRAULIC) and Dumper are machineries in SHOVEL 0.9/1.8 cu.m- 6, FRONT equipped to mineral benches (HYDRAULIC) END LOADER 2.0 cu.m-2, winning out the 0.9/1.8 cu.m- DUMPER 20.0T-32, CRUSHER mineral. 6, FRONT END 150.000 T/H-1, WATER LOADER 2.0 TANKER 8000L-2 cu.m-2, DUMPER 20.0T-32, CRUSHER 150.000 T/H-1, WATER TANKER 8000L-2 3l Whether height Bench height- Bench height is suitably Bench height is of benches in 8m matched with the loading suitably matched overburden and excavator. with the loading mineral suitable excavator. for method of mining proposed in MP/SOM 3m Total area 179.12 ha About 159.61 ha. has About 159.61 ha. covered under proposed been covered under has been covered excavation/pits during excavation pits. under excavation approved plan pits. period. 3n Ore to OB ratio 1:0.12 T/cu.m 1:0.25T/cu.m for Stripping ratio is for the pit/mine for limestone dolomite. more or less same. during the year. & 1:0.21 T/cu.m for dolomite. PAGE : 8

3o Total area put Total area Total area proposed Total area in use under proposed under under different heads proposed under different heads different are Pit-159.61 ha, different heads at the end of heads are waste dump-39.52 ha, are Pit-159.61 year Pit-179.12 ha, Infrastructure, roads & ha, waste dump- waste dump- Mineral storage, 39.52 ha, 41.112 ha, plantation & others - Infrastructure, Infrastructure 54.940 ha. roads & Mineral -14.12ha, storage, roads-10.08 ha plantation & & Mineral others -54.940 ha. storage, plantation & others -64.845 ha. 3p Production of 2013-14: 2013-14: Limestone- ROM Production is ROM mineral Limestone- 17684T & Dolomite - less due to low during the last 3220632T & 378225T market demand. five year period Dolomite - 2014-15: Limestone-2229T as applicable 1587508T & Dolomite -102498T 2014-15: 2015-16: Limestone-5636T Limestone- & Dolomite -476391T 3319032T & 2016-17: Limestone-243T Dolomite - & Dolomite -476241T 2963303T 2017-18: Limestone-Nil & 2015-16: Dolomite -567121.67T Limestone- 3339696T & Dolomite - 2975744T 2016-17: Limestone- 3374628T & Dolomite - 2985472T 2017-18: Limestone- 3481884T & Dolomite - 2991104T PAGE : 9

3q General remarks Excavation of The ROM production for The ROM production of inspecting ROM has been dolomite ore has been for dolomite ore officers on proposed in carried out only from has been carried method of mining Patpahar Patpahar dolomite out only from etc. dolomite quarry. Patpahar dolomite quarry, Main quarry. dolomite Shortcomings quarry, pointed out Gurupahar through violation limestone letter. quarry & Durasani/New hoist limestone quarry.

Solid Waste Management - Dumping:

Sl.No. Item Propasals Actual work Remarks

4a Separate dumping Separate Separate dumping for Mineral reject of topsoil, OB dumping for overburden/waste is generated during and mineral overburden/was maintained. mining proposed rejects (Rule te and no for blending 32,33) mineral reject however proposed dump proposed. limestone quarries not worked out. There is no top soil generation. 4b Location of Dump-4, OB/Waste generated OB/Waste dumped as topsoil, OB and 5000W/46100W during mining operation per proposal. mineral reject & 400N/1200N. has been dumped on dumps No proposal of active Dump-4, top soil & MR 5000W/46100W & dump 400N/1200N . 4c Number of dumps Dump-4, There is one active There is one within lease 5000W/46100W dumps i.e dump-4 within active dumps i.e area and outside & 400N/1200N. the lease area. dump-4 within the of lease area lease area. There is also 16 nos. of dumps present in the lease area which are inactive. PAGE : 10

4d Location of Dump-4, There is one active There is one dumps w.r.t. 5000W/46100W dumps i.e dump-4 active dumps i.e ultimate pit & 400N/1200N. 5000W/46100W & dump-4 limit (Rule 16) 400N/1200N within the 5000W/46100W & lease area. 400N/1200N within the lease area. There is also 16 nos. of dumps present in the lease area which are inactive. 4e Number of active One active There is one active There is one and alive dumps. dump dumps i.e Dump-4. active dumps i.e Dump-4. 4f Number of dead Not proposed. There is 16 nos. of There is 16 nos. dumps. dumps present in the of dumps present lease area which are in the lease area inactive. which are inactive. 4g Number of dumps Not proposed. There is 16 nos. of There is 16 nos. established. dumps present in the of dumps present lease area which are in the lease area inactive which are which are inactive mostly stabilised by which are mostly plantation. stabilised by plantation. 4h Whether Not proposed. Retaining wall and Retaining wall and Retaining wall garland drain maintained garland drain or garland drain around dump. maintained around all along dumps dump. are there. 4i Length of Not proposed. Retaining wall and Retaining wall and Retaining wall garland drain maintained garland drain or garland drain around dump. maintained around all along dumps dump. 4k Specific One active OB has been dumped on There is 16 nos. comments of dumps i.e Dump-4, 5000W/46100W & of dumps present inspecting Dump-4, 400N/1200N. in the lease area officer on waste 5000W/46100W which are inactive dump management & 400N/1200N. and mostly stabilized by plantation.

Solid Waste Management - Backfilling:

Sl.No. Item Propasals Actual work Remarks PAGE : 11

5a Status of part Not proposed Pits are not fully Pits are not fully or full as pits are exhausted for exhausted for extraction of not fully reclamation and reclamation and mineral from exhausted. rehabilitation. rehabilitation. mined out area before starting backfilling. 5b Area under Not proposed. Pits are not fully Pits are not fully backfilling of exhausted for exhausted for mined out area reclamation and reclamation and rehabilitation. rehabilitation. 5c Concurrent use Not proposed. Pits are not fully Pits are not fully of topsoil for exhausted for exhausted for restoration or reclamation and reclamation and rehabilitation rehabilitation. rehabilitation. of mineral out area (Rule 32) 5d Total area Not proposed. Pits are not fully Pits are not fully fully reclaimed exhausted for exhausted for and reclamation and reclamation and rehabilitated rehabilitation. rehabilitation. 5e General remarks Not proposed Pits are not fully Pits are not fully of inspecting as pits are exhausted for exhausted for officers on not exhausted. reclamation and reclamation and backfilling and rehabilitation. rehabilitation. reclamation etc.

Progressive Mine Clousre Plan:

Sl.No. Item Propasals Actual work Remarks

6a Whether Annual Not specified. Annual return on PMCP Annual return on report on PMCP has been submitted. PMCP has been submitted on submitted. time and correctly. Rule 23 E(2). 6b Area available Not proposed Pits are not fully Pits are not fully for as pits are exhausted for exhausted for rehabilitation not exhausted. reclamation and reclamation and (ha) . rehabilitation. rehabilitation. 6c afforestation 0.5 ha. In 2017-18, total area In 2017-18, total done (ha). cover under area cover under afforestation is about afforestation is 1.0 ha. about 1.0 ha. 6d No. of saplings 800 saplings In 2017-18, total 2500 In 2017-18, total planted during nos. of saplings have 2500 nos. of the year been planted by lessee. saplings have been planted by lessee. PAGE : 12

6e Cumulative no Not specified. Cumulative nos. of Cumulative nos. of .of plants saplings planted in the saplings planted lease area is about in the lease area 26800. is about 26800. 6f Any other method Not proposed Pits are not fully Pits are not fully of as pits are exhausted for exhausted for rehabilitation not exhausted. reclamation and reclamation and rehabilitation. rehabilitation. 6g Cost incurred on Not specfied. Around Rs 2.5 lakh cost Around Rs 2.5 lakh watch and care incurred on watch and cost incurred on during the year care. watch and care. 6h Compliance on Not proposed Pits are not fully Pits are not fully reclamation and as pits are exhausted for exhausted for rehabilitation not exhausted. reclamation and reclamation and by backfilling rehabilitation. rehabilitation. (i) Voids available for backfilling ( Lx B x D 6i Compliance on Not proposed Pits are not fully Pits are not fully reclamation and as pits are exhausted for exhausted for rehabilitation not exhausted. reclamation and reclamation and by backfilling rehabilitation. rehabilitation. (ii) Voids filled by waste / tailings 6j Compliance on Not proposed Pits are not fully Pits are not fully reclamation and as pits are exhausted for exhausted for rehabilitation not exhausted. reclamation and reclamation and by backfilling rehabilitation. rehabilitation. (iii)Afforestati on on backfilled area 6k Compliance on Not proposed Pits are not fully Pits are not fully reclamation and as pits are exhausted for exhausted for rehabilitation not exhausted. reclamation and reclamation and by backfilling rehabilitation. rehabilitation. (iv) Rehabilitation by making water reservoir 6l Compliance on Not proposed Pits are not fully Pits are not fully reclamation and as pits are exhausted for exhausted for rehabilitation not exhausted. reclamation and reclamation and by backfilling rehabilitation. rehabilitation. (v)any other specific means. PAGE : 13

6m Compliance of Not proposed Nil. Waste land not rehabilitation proposed for of waste land rehabilitation. within lease (i)afforestation 6n Compliance of Not proposed. Nil. Waste land not rehabilitation proposed for of waste land rehabilitation. within lease (ii)Area rehabilitation (ha) 6o Compliance of Not proposed. Nil. Waste land not rehabilitation proposed for of waste land rehabilitation. within lease (iii)Method of rehabilitation 6p Compliance of Quarterly Quarterly monitoring of Quarterly environmental monitoring air, water and noise monitoring of air, monitoring (core level are being carried water and noise zone and buffer out. level are being zone) carried out. 6q General remarks No proposal of Pits are not fully Pits are not fully of inspecting recamation and exhausted for exhausted for officers on PMCP rehabilitation reclamation and reclamation and compliance and as pits are rehabilitation. rehabilitation. progressive not exhausted. closure operations etc.

Mineral Conservation:

Sl.No. Item Propasals Actual work Remarks

7a ROM Mineral Gradewise Gradewise sorting is Gradewise sorting dispatch or sorting. being practiced. is being grade-wise practiced. sorting within lease area 7b Method of grade- Mechanised Mechanised Mechanised wise mineral sorting i.e. manual or mechanical. PAGE : 14

7c Different grade 35% to 42% &+ 15 to19% & +19% Mgo for 15 to19% & +19% of mineral 40% Cao for dolomite. Mgo for dolomite. sorted out at limestone and No ROM production mines. 15 to19% & from limestone is +19% Mgo for reported. dolomite 7d Any Not proposed. Only crushing and Only crushing and beneficiation screening is being screening is being process at mines practiced. practiced. . 7e General remarks Sorting of 15 to19% & +19% Mgo 15 to19% & +19% of inspecting different sorted out for dolomite Mgo for dolomite. officer on grade, 35% to at mine head. No ROM production Mineral 42% &+ 40% Cao from limestone is conservation and for limestone reported. beneficiation and 15 to19% & issues +19% Mgo for dolomite

Environment:

Sl.No. Item Propasals Actual work Remarks

8a Separate removal Not proposed. Nil. No top top soil and utilization generation is of topsoil (Rule proposed. 32) 8b Concurrent use Not proposed. Nil. No top top soil or storage of generation is topsoil proposed. 8c Separate dumps Separate dump OB/Waste generated OB/Waste dumped as for overburden, for OB. No during mining operation per proposal. waste rock, proposal of has been dumped on rejects and top soil & MR active Dump-4, fines (Rule 33) dump 5000W/46100W & 400N/1200N . 8d Use of Not proposed Pits are not fully Pits are not fully overburden, as pits are exhausted for exhausted for waste rock, not exhausted. reclamation and reclamation and rejects and rehabilitation. rehabilitation. fines dumps for restoring the land to its original use PAGE : 15

8e Phased Not proposed Pits are not fully Pits are not fully restoration, as pits are exhausted for exhausted for reclamation and not exhausted. reclamation and reclamation and rehabilitation rehabilitation. rehabilitation. of lands affected by mining operations (Pits, dumps etc) 8f Baseline 800 nos. of Total 2500 nos. saplings Total 2500 nos. information on plantation have been planted in saplings have been existence of 2017-18. Cumulative planted in 2017- plantation and 26800 nos. have been 18. Cumulative additional planted by lessee . 26800 nos. have plantation done been planted by (Rule 41) lessee . 8g Survival rate Not specified. As reported survival As reported rate is 80%. survival rate is 80%.

8h Water sprinkling One Water Water tanker is used to Water tanker is on roads to tanker control air borne dust. used to control control airborne air borne dust. dust 8i General remarks 800 nos. of In 2017-18, total 2500 Aesthic beauty is of inspecting plantation in nos of saplings have maintained by officer on 2017-18. been planted by lessee. plantation. aesthetic beauty As reported cumulative in and around no. of trees planted by mines area lessee is about 26800 nos.

Compliance of Rule 45:

Sl.No. Item Propasals Actual work Remarks

9a Status of Monthly & Monthly & Annual returns Monthly & Annual submission of Annual returns are being regularly returns are being Monthly and are being submitted by lessee. regularly Annual returns regularly submitted by submitted by lessee. lessee. 9b Scrutiny of Graduate Graduate Mining Graduate Mining Annual return Mining Engineer-3, Diploma Engineer-3, for information Engineer-3, mining Engineer-2, Diploma mining on Mining Diploma mining Geologist-1, Surveyor-1 Engineer-2, Engineer, Engineer-2, Geologist-1, Geologist and Geologist-1, Surveyor-1 Manager Surveyor-1 PAGE : 16

9c Scrutiny of Area covered Area covered under Area covered under Annual return on under different heads are different heads land use pattern different Pit-149.930 ha, waste are Pit-149.930 for area under heads are dump-39.520 ha, Plant, ha, waste dump- pits, reclaimed Pit-149.930 building, roads-53.940 39.520 ha, Plant, area, dumps etc. ha, waste ha & others -1.0 ha. building, roads- dump-39.520 53.940 ha & ha, Plant, others -1.0 ha. building, roads-53.940 ha & others - 1.0 ha. 9d Scrutiny of Total 2500 Total 2500 nos. saplings Total 2500 nos. Annual return on nos. saplings have been planted in saplings have been afforestation have been 2017-18. planted in 2017- planted in 18. 2017-18. 9e Scrutiny of Dolomite 910T, Dolomite 910T, Less than No production of Annual return on Less than 18 % 18 % Mgo% limestone reported mineral reject Mgo% as proposed. generation (Grade and quantity) 9f Scrutiny of Limestone: Limestone: Closing stock Limestone: Closing Annual return on Closing stock (BF Grade)- 410913.40 stock (BF Grade)- ROM stock and/or (BF Grade)- Dolomite: Production- 410913.40 graded ore 410913.40 567121.67T, Closing Dolomite: Dolomite: stock-265238.68 Production- Production- 567121.67T, 567121.67T, Closing stock- Closing stock- 265238.68 265238.68

9g Scrutiny of Ex mine price Ex mine price of No production of Annual return on of dolomite Rs dolomite Rs 671.00. limestone reported sale value, Ex. 671.00. as proposed. Mine price and production cost 9h Scrutiny of Fixed asset as Fixed asset as furnished Fixed asset as Annual return on furnished in in AR is Rs 6058000/- furnished in AR is fixed assets AR is Rs Rs 6058000/- 6058000/- 9k Scrutiny of BLAST HOLE BLAST HOLE DRILL 100mm- BLAST HOLE DRILL Annual return on DRILL 100mm-5, 5, SHOVEL 0.9 cu.m- 6, 100mm-5, SHOVEL mining SHOVEL 0.9 FRONT END LOADER 0.9 cu.m- 6, FRONT machineries cu.m- 6, FRONT 1.7cu.m-6, TIPPER 11 END LOADER END LOADER cu.m-20, CRUSHER-6, 1.7cu.m-6, TIPPER 1.7cu.m-6, 11 cu.m-20, TIPPER 11 CRUSHER-6, cu.m-20, CRUSHER-6, PAGE : 17 PAGE : 18

Details of violations observed during current inspection and compliance position of violation pointed out Violation observed Show couse position Rule NO. Issued on Compliance on Rule NO. Issued on Compliance on

MCDR17 Rule 11(1) 28/12/2018

Date : (DAYANAND UPADHYAY)

Indian Bureau of Mines