WHAT WORK IS TAKING PLACE? Structural work to accommodate construction of the Hurontario LRT will begin soon in the north and south parking lots of Port Credit GO Station. Crews are currently mobilizing in the area and construction will begin in March.

At the north parking lot, crews will be working on construction of a new channel and flood walls for Mary Fix Creek. Crews will be using telehandlers, cranes and excavators to replace the existing bridges and widen the current profile of the channel to allow for more flow.

At the south parking lot, crews will begin works for the future Port Credit Stop. Using auger machines, crews will drill holes into the ground and fill them with concrete and steel piles to create columns that will support excavation works as well as surrounding utilities and structures.

TIMING WHAT TO EXPECT • Work on the north parking lot and Mary Fix Creek is • Residents and businesses near the work site can expect to scheduled to start in March 2021 and expected to be hear noise caused by trucks, excavators, and other completed by the end of 2022. construction equipment related to this work. • Work in the south parking lot at Port Credit GO Station is • Every effort will be made to minimize disruption. scheduled to start in March 2021. This work involves construction of the LRT station stop and is anticipated to PEDESTRIAN DETAILS be completed in summer 2024. • Please take care when walking or cycling near construction • Work will generally occur between 7 a.m. and 7 p.m., areas and watch for additional signs directing the public Monday to Friday. However, night and weekend works such as detours and dismounting. may be scheduled as required. • Work could be rescheduled and delayed due to weather GO CUSTOMER DETAILS conditions or unforeseen circumstances. • A portion of the south lot will be closed along Hurontario Street on the east side of the parking lot, and into the TRAFFIC DETAILS northern half of the south parking lot. • Watch for construction vehicles entering and exiting work • During construction, the stairs from Hurontario Street into areas. the south parking lot will be closed. • Please reduce driving speed within the GO Station parking • Some of the reserved parking spaces in the south parking lot to ensure the safety of yourself and those around you. lot will be relocated.