Pre-Feasibility Report
Total Page:16
File Type:pdf, Size:1020Kb
Project Name: “Basalt Stone Mining” (2.06 ha.) Form -1M Village – Choparit, Tah -Bhadravati, Dist Chandarpur (Maharashtra) Applicant: Shri Chandrakanth Namdeorao wasade Capacity- 51938 MTPA PRE-FEASIBILITY REPORT Project Name: “Basalt Stone Mining” (2.06 ha.) Form -1M Village – Choparit, Tah -Bhadravati, Dist Chandarpur (Maharashtra) Applicant: Shri Chandrakanth Namdeorao wasade Capacity- 51938 MTPA 3.23 EXECUTIVE SUMMARY Proposal of obtaining Environmental Clearance for Basalt Stone with production Capacity 51938 MTPA Near Village: –Chopanrit, Tah-Bhadrawati, Dist-Chandarpur (Maharashtra) The total lease area is 2.06 ha. The said Mining Lease has been sanctioned in favor of project proponent Shri Chandrakanth Namdeorao Wasade as per provision of GoI and Govt. of Maharashtra notification under rule 23 of MMME(D & R). The Applicant has applied for new mining lease for five years. The mining plan is submitted. The mining plan has been approved vide letter no. MA/MP/170III/2017 on dated 4/04/2018 for a production capacity of 51938 MTPA which is valid at present. TABLE-1.1 SALIENT FEATURES OF THE PROJECT S.No. Particulars Details A. Mining Lease Details 1. Name of the Project Basalt Stone Mining Project 2. Mineral Explored Basalt Stone 3. Mining Lease sanction The said Mining Lease has been sanctioned in favor project proponent Shri Chandrakanth Namdeorao Wasade R/O Chandrapur, Maharashtra as per provision of GoI and Govt. of Maharashtra notification under rule 23 of MMME(D & R). The Applicant has applied for applied for new mining lease new mining lease for further five years, 2016 to 2021, The mining plan is submitted. 4. Mining Lease Area 2.06 ha 5. Lease Period 5.0 years B Location 6. Village Chopanrit 7. Tehsil Bhadrawati Project Name: “Basalt Stone Mining” (2.06 ha.) Form -1M Village – Choparit, Tah -Bhadravati, Dist Chandarpur (Maharashtra) Applicant: Shri Chandrakanth Namdeorao wasade Capacity- 51938 MTPA 9. District Chandarpur 10. State Maharashtra 11. Latitude & Longitude Points Latitude Longitude A. 200 12’ 37.0.”N 780 03’ 09.6 ”E B. 200 12’ 37.3.”N 780 03’ 13.5 ”E C. 200 12’ 34.4.”N 780 03’ 13.5 ”E D. 200 12’ 33.8.”N 780 03’ 13.5 ”E E. 200 12’ 33.8.”N 780 03’ 14.3 ”E F. 200 12’ 32.5.”N 780 03’ 13.6 ”E G. 200 12’ 29.7.”N 780 03’ 10.4 ”E H. 200 12’ 29.7.”N 780 03’ 10.2 ”E I. 200 12’ 34.2.”N 780 03’ 09.8 ”E C. Environmental settings 13. Nearest Village Chopanrit Approx 1.10 Km towards SE. 14. Nearest City Bhadrawati Approx. 13.7 in SE direction 15. Nearest Railway Station Warora Railway Station (Approx 5.9 in NW direction) 16. Nearest Airport Nagpur International Airport (Approx. 97.7 km. in N direction) 17. Archaeological Important None, within 10 km distance from the periphery of lease Place area. 18. Ecological Sensitive Park, None, within 10 km distance from the periphery of lease Wildlife Sanctuary, area. Reserve etc.) 19. Reserved/Protected Forest None, within 10 km distance from the periphery of lease within 10km radius area. 20. Nearest River / water body River approx 0.6 km towards N River approx 9.7 km towards W Project Name: “Basalt Stone Mining” (2.06 ha.) Form -1M Village – Choparit, Tah -Bhadravati, Dist Chandarpur (Maharashtra) Applicant: Shri Chandrakanth Namdeorao wasade Capacity- 51938 MTPA 3.23 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION 2.1 Identification of Project and Project Proponent The Proposal of obtaining Environmental Clearance for Basalt Stone Mining Project with production Capacity 51938 MTPA at Village: – Chopanrit, Tah -Bhadrawati, Dist Chandarpur (Maharashtra) The total lease area is 2.06 ha. The details of the project proponent and project are given below: Name of the applicant Shri Chandrakanth Namdeorao Wasade Name & Address of Applicant R/o Chandrapur (MH) Name of Mine Basalt Stone Mining Project Mineral Basalt Stone Area (ha) 2.06 Hect. Status of Project New Mining lease 2.2 Brief description of nature of the project Proposal of obtaining Environmental Clearance for Basalt Stone mining with production Capacity 51938 MTPA, Village: – Chopanrit, Tah -Bhadrawati, Dist Chandarpur (Maharashtra). The total lease area is 2.06 ha. 2.3 Need for the Project and Its Importance to the Country or Region The said project plays a significant role in the construction achieving a huge infrastructure as being envisaged by Government of India particularly in road basic building materials. The mining activities as proposed are the backbone of all construction and infrastructure projects as the raw material for construction is available only from such mining. 2.4 Demands-Supply Gap There is large demand of Basalt to the nearby markets and stone crusher units. The crushed material of stone crusher units is used in infrastructure projects. This mineral is also used as infrastructure. Presently, maximum infrastructure projects are in operation hence this project will be viable. Project Name: “Basalt Stone Mining” (2.06 ha.) Form -1M Village – Choparit, Tah -Bhadravati, Dist Chandarpur (Maharashtra) Applicant: Shri Chandrakanth Namdeorao wasade Capacity- 51938 MTPA 2.5 Imports vs. Indigenous Production Indigenous Production: The demand for Basalt is ever growing. The mineral is used in infrastructure sector. Therefore there is always a good demand of the mineral in the domestic market. Export Market: There is no possibility of export of the mineral. 2.6 Export Possibility There is no proposal to export the mineral. 2.7 Domestic/ Export Markets A) Domestic Market The mineral excavated will be directly sold to nearby market and may further transport to Stone Crusher Zone. B) Export Market There is no possibility of export of the mineral except the Domestic Market. 2.8 Employment Generation (Direct and indirect) due to the project Project will create direct & indirect employment within the surrounding region. Unit will use good faith efforts to employ local people from nearby villages depending upon the availability of skilled and unskilled man-power surrounding the project site. In operational phase, the proposed expansion required 40 persons. In addition to that functions like supply of explosive preparation and amendment of plans etc. will also require professionals. This project operation will provide livelihood to the poorest section of the society. 3.0 PROJECT DESCRIPTION 3.1 Type of Project Including Interlinked and Interdependent Projects, If Any. Mining of Basalt Stone is site specific project. 3.2 Location Points Latitude Longitude A. 200 12’ 37.0.”N 780 03’ 09.6 ”E Project Name: “Basalt Stone Mining” (2.06 ha.) Form -1M Village – Choparit, Tah -Bhadravati, Dist Chandarpur (Maharashtra) Applicant: Shri Chandrakanth Namdeorao wasade Capacity- 51938 MTPA B. 200 12’ 37.3.”N 780 03’ 13.5 ”E C. 200 12’ 34.4.”N 780 03’ 13.5 ”E D. 200 12’ 33.8.”N 780 03’ 13.5 ”E E. 200 12’ 33.8.”N 780 03’ 14.3 ”E F. 200 12’ 32.5.”N 780 03’ 13.6 ”E G. 200 12’ 29.7.”N 780 03’ 10.4 ”E H. 200 12’ 29.7.”N 780 03’ 10.2 ”E I. 200 12’ 34.2.”N 780 03’ 09.8 ”E State: Maharashtra District: Chandrapur Tehsil: Bhadrawati Village: Chopanrit The entire project area is 2.06 Hectare 3.3 Details of Alternate Sites Mining of Basalt Stone is site specific project and it cannot be shifted to one place to another due to specific availability of mineral resources. Hence, no alternate site is considered. 3.4 Size or Magnitude of Operation It is proposed to produce annual production of 51938 MTPA Basalt Stone over a 2.06 ha area. 3.5 Project Description with Process Details Method of Mining It is a mining project of Basalt over an area 2.06 ha situated Near Vill. Chopanrit, Tehsil Bhadrawati, District- Chandrapur, Maharashtra with annual production capacity of 51938 MTPA The method of mining is Opencast manual. The mining operation will be done in single shift only and excavation will be done by simple hand tools. Drilling& Blasting: Drilling will be done by shot holes by compressor operated jack hammer drill machine 30mm Project Name: “Basalt Stone Mining” (2.06 ha.) Form -1M Village – Choparit, Tah -Bhadravati, Dist Chandarpur (Maharashtra) Applicant: Shri Chandrakanth Namdeorao wasade Capacity- 51938 MTPA diameter and Blasting is needed in hard strata Blasting is done with skilled personnel with the use of ANFO and emulsion as explosives or slurry explosives, concentional blasting methods along with delay detonator will be used Loading: The material excavated from mine by drilling and blasting will be loaded into Trucks and Tractor Trolly by steel ghamelas then transported to the market. Transport: The market for this Basalt is in nearby areas. Maximum stone is transported in trucks and tractor trollies. 3.6 Raw Material Required Along With Estimated Quantity, Likely Source, Marketing Area of Final Product/s, mode of Transport of Raw Material and FinisHed Product No raw material will be required in the proposed project. The operation involves the excavation of Basalt Stone along with associated minerals from the mining lease area and sold to the crusher. A. The Mineral production (in TONNES) for the next 5years is given below: TABLE-3.1 YEAR WISE PRODUCTION S. No. Production in M3 OB Volume M3 First Year 14620 1462 Second Year 32481 3248 Third Year 51938 5194 Forth Year 49480 4948 Fifth Year 35664 3566 Total 184183 18418 Source: Approved Progressive mine closure Plan Project Name: “Basalt Stone Mining” (2.06 ha.) Form -1M Village – Choparit, Tah -Bhadravati, Dist Chandarpur (Maharashtra) Applicant: Shri Chandrakanth Namdeorao wasade Capacity- 51938 MTPA B. LAND REQUIREMENT The proposed Basalt Stone along with minor minerals mining project has lease area is 2.06 ha and same will be used for the mining activities.