-t .> 0 Government- of Z - ~ A .PublicWorksDepartment- E498 Volume4 Public Disclosure Authorized

... -eW ; - -2

MIz&tscS 4ib-fto9dsProject

tU~~~ ~- j~ V9

: t - < a^S3 4V~\- i [ 2 . < t~~~~~~~4. , Public Disclosure Authorized

4L~~~~~~~~~~~~~~~~~~~~~~&4 Public Disclosure Authorized

n 4; , i X > .,. gn w~~44~D 44 44b ICT, C LBII)

%~~~~~~~~~~~~~~~~~~~~~~~~~,!,4 ; '.}<2. 4,;4 '4 Lea Associates South~~~~~~~~~~~4 Asi Pv.td

; t - -;--i-2rvv-2 FlE4 COPY~~~~~~~~~~~~~~~/4' *_ ¢'' ' j r !"iif ,,r .,T~~~~~~~~4 4 ~ 4 4

_||l~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~4 h 4 4~' Reiedb

Lea~~4, Asoiae Souh si4Pv. td

' a -~~~~~~~~~~Oia Docmen by IC,CE,LBI Public Disclosure Authorized I PREFACE

The Mizoram State Roads Project includesaugmentation of the capacityand structural upgradationof selectedroad network in the state. A total of 185.71kmroads will be improved/upgraded,and majormaintenance works will be carriedout on 518.615kmroads, in 2 Phases.The projectwas preparedby the ProjectCo-ordinating Consultants (PCC) 1, on behalf of the PWD, Mizoram.As part of the project preparation,environmental/social assessmentswere carried out, as requiredby the WorldBank and the Governmentof .

In accordanceto the requirementsof the World Bank,the environmental/socialassessments (and the outputs)had beensubjected to an IndependentReview. The independentreview 2 evaluatedthe EAprocesses and outputsin the projectto verify that (a) the EA had been carriedout withoutany biasor influencefrom the projectproponent and/or the PCC,(b) the EA/SAhad beenable to influenceplanning and design of the project;and (c) the outputs, especiallythe mitigation/managementmeasures identified in the EA/SAprocesses are | adequatefor the project.

The followingdocuments (dated May 2001) were available for the Review: * SectoralEnvironmental Assessment (SEA) for both phasesof the project(prepared at the feasibilitystage of the projectand the PhaseI of the project) * DetailedEnvironmental Assessments (EA) for the work programmein PhaseI of the | Project, * EnvironmentalManagement Plan (EMP) for the improvement/upgradationworks in PhaseI. m . Resettlement & Indigenous People's Development Plan (R&IPDP) for the improvement/upgradationworks in PhaseI. * Environmentaland Social ManagementPlan (ESMP) for the major maintenance worksin PhaseI.

As part of the IndependentReview, gaps and deficienciesin these basedocuments were identified. This reportis partlyan outcomeof the IndependentReview, closing the gaps,as perthe information/datasupplied by the PCCand supplemented by field investigationscarried during the Independent Review. This report took into consideration, the comments/observationsmade by the WorldBank on the basedocuments.

The recommendationsfrom the IndependentReview are incorporatedin the SEAand the other PhaseI EA/SAreports (as well as in the EngineeringDrawings, and the Contract Documents).All reportsnow are modifiedand structuredas per the commentsfrom the IndependentReview.

Note: The Data providedin the reports,unless specifically mentioned, are from the 3 BaseEA/SA Documents.

I 7 PCCwas a consortiumof consultingfirms, led by IntercontinentalConsultants and Technocrats Pvt. Ltd., India (ICT)and Consulting Engineering Services (India) (CES) in associationwith LouisBerger InternationalInc., USA(LBII). |2 TheIndependent Review was undertaken by MsLea Associates South Asia Pvt. Ltd. l TABLE OF CONTENTS l

|I ENVIRONMENTAL MANAGEMENT PLAN ...... 1

1.1 INTRODUCTION .. 1 1.2 PROJECTCORRIDOR - DESCRIPTION .. 1 1.2.1 PROPOSEDIMPROVEMENTS .2 1.3 MAJOR FINDINGSOF THE ENVIRONMENTALASSESSMENT . . 3 1.3.1 STABILITYOF SLOPES .3 1.3.2 DISPOSALOF CONSTRUCTIONDEBRIS. 3 1.3.3 IMPACT ON BIO-DIVERSITY ...... 3...... 3 1.3.4 IMPACTON SENSITIVESURFACE WATERSOURCES INCLUDING WATERFALLS .3 1.3.5 FAUNA: .4 1.3.6 RESETTLEMENTAND LOSS OF LIVELIHOOD .4 1.4 ENVIRONMENTALMANAGEMENT MEASURES PROPOSED ...... 4 1.4.1 PRE-CONSTRUCTIONSTAGE ...... 4 I 1.4.2 CONSTRUCTIONSTAGE ...... 4 1.4.3 OPERATIONSTAGE ...... 5 1.5 REPORTINGSYSTEM ...... 32 I 1.6 INSTITUTIONALARRANGEMENTS ...... 33 1.7 TRAINING ...... 33 1.7.1 NEEDFOR TRAINING...... 33 I 1.7.2 TARGETSOFPROPOSED TRAINING ...... 34 1.7.3 TRAININGCOMPONENTS ...... 34 1.7.4 LOGISTICALSUPPORTREQUIRED ...... 36 U 1.8 ENVIRONMENTALMONITORING PLAN ...... 36 1.8.1 OBJECTIVES...... 36 1.8.2 METHODOLOGY...... 36 | 1.8.3 AMBIENTAIRQUALITY(AAQ) MONITORING ...... 37 1.8.4 WATERQUALITY MONITORING ...... 37 1.8.5 NOISELEVELS MONITORING ...... 40 1.9 MONITORINGPLAN ...... 40 1.10 ENVIRONMENTALMANAGEMENT - BUDGET ...... 44 1.11 SPECIFICATIONSFOR ENVIRONMENTALMANAGEMENT WORKS ...... 47 1.11.1 CLEARINGAND GRUBBING...... 47 1.11.2 EARTHWORK...... 47 1.11.3 MATERIALS...... 47 1.11.4 BRICKS WORK...... 47 1.11.5 STONEWORK ...... 47 1.11.6 CONCRETEWORK ...... 47 3 1.11.7 CEMENTCONCRETE TILE FLOORING/ PAVING ...... 47 1.11.8 FORMWORK...... 47 1.11.9 CEMENTPLASTERING ...... 48 1.1 1.10 GABION STRUCTURES...... 48 1.11.11 RAILING...... 48 l

ENVIRONMENTALMANAGEMENT PLAN

1.1 INTRODUCTION The Governmentof Mizoramis seekingloan under the World Bankloan assistance program(WB Loan no. 4114IN) availablewith the Governmentof India,for upgradation and maintenanceof the state road network. The project envisagesthe major I augmentationof capacityas well as structuralupgradation of roadnetwork in the state of Mizoram.The projectpreparation activities including the projectplanning and design is beingcarried out by the PWD,Government of Mizoram,through Project Co-ordinating Consultants(PCC). A StrategicOptions Study (SOS),covering 3534 km of the state road network,was conductedin October1998-January 1999 with the objectiveof determininginvestment prioritiesfor the road improvementprogram and identifyingroads for the Feasibility I Studies. FeasibilityStudies, including engineeringanalysis and design, social and environmentalscreening and economicevaluation were carried out (completedin January2000). Based on the findingsof thesestudies and discussions between PWD and WorldBank, corridors have been identified as candidatesfor improvement/upgradation and for major maintenanceworks. The corridors that have been identified for I improvementin the two phasesof the projectare listedin Table1.

Table 1: Work Programme in MSRP Type of PhaseI PhaseII Total Work RoadSection Length(km) RoadSection Length(km) Length(km) Improvement/ PlA: Aizawi -Thenzawl- 98.710 P18: Buangui - Lunglei 71.000 Upgradation Buangpui(via Hmuifang) BP1:Aizawl Bypass 16.000 185.710 Works Sub-Total:Phase I 98.710 Sub-Total:Phase II 87.00 MI: Kawlkulh--Tuivai 96.625 M2: Kanhmun- Zamuang- 90.440 Major M4: Keitum-N.Vanlaiphai 45.780 Tuilutkawn Maintenance M5: Lungsen- Chawngte 47.670 M6: Zobawk - Hualawng 31.000 518.615 Works M7: Damdai - Sialsuk 30.100 M15: Serchhip- Thenhlum 105.000 M9: - E.Lungdar 58.000 M16: Selesih-Thuampui 14.000 ______Sub-Total:Phase I 278.175 Sub-Total:Phase II 240.440

Locationmaps of the aboveproject roads are enclosedas Figure1.1 and1.2 * The PWD,Government of Mizoram,the projectproponent, is responsiblefor the overall preparation,implementation and operationof the project.Contractor selected through InternationalCompetitive bidding shall carry out the implementation.To assistthe PWD in ensuringthe effectiveimplementation of the project,a Supervisionconsultant will be appointed,throughout the constructionperiod of the project(for threeyears). This report details the EnvironmentalManagement Plan worked out for the improvementsproposed along the PriorityRoad (P1-A), between Aizawl and Buangpui via Hmuifang.

Revisedby Lea Associates 1 October2001 (OriginalDocument by ICT, CES, LBII A S S A M

Kanhn7un~~ Rat s

ct I >) Z;Itaci `1cH1

< s ! t Nwe~~ng # A%,Spt}sEpat9 91 t - J; TAmdk-= 397-",-

irn f 1e \s Tam4 <~1se |It oftthae3lT,

;~~~~~~~M . X.raWt m

\To36 ; -

s~~~N 7 twg!,'wwi 2

- \'S !. - awrg-1 . ,1

F;ue1 lpo iormSoicrjc Roas -\PhseIp < ~~~iawl

z [\\) Mel~riot(k.m 10.40) Ke sih (kmr ' 2.3C) rt (K>I0.C

jLr. ( .) lkcwn(km 400) Thinsuthicar V,oliungltnu('Kr td.S3)( Tochhip(kri 2C.40)

A;bawk(krn/ 27-m0) tee(km 28.50)

DOamdiai(krn 34.4a4 lurgy /

eungsi9km 36.00) S h

\ / tT~~~~~hick(km 41.30) ,

9/ XS~~umsuih(km 47 0

\11~X ~ ~ ~ ~~~~~H ift kr 52-00)

\ <

Fg. 1.2 Settl s AChhihtlong

/<;~~~~~~~i1-9.0 Serchhip / * ,

GoEeDc Fig. 1.2 Settlements Along Project Route

- Proposed R_d MIZORAMSTATE ROADS PROJECT - Phase I Other Road 0 Settlement (Aizawl -Hmuifang- Buangpui)

River LEAAssociates South Asia Pvt. Ltd. l MizoramState Roads Project - PhaseI EnvironmentalManagement Plan for P-IA

A 1.2 PROJECTCORRIDOR - DESCRIPTION The projectroute (P1-A)follows the existingalignment of the roadfor Aizawl-Buangpui section,except between Damdiai and Sialsuk,the route is on the existing alternative roadvia Hmuifang.Geographically, the projectroad (about 100kml) can be dividedinto | the followingthree sections. • Aizawl- Damdiai approximately35km . Damdiai- Sialsukvia Hmuifang approximately30km * Sialsuk- Thenzawl- Buangpui approximately35km The characteristicsof theseroad sections are presentedin table2 below.

Table 2: ExistingCharacteristics of the ProjectAlignment (P1-A) Section Length Carriageway width Formation Shoulders Aizawl- Damidiai 35km 3.5m paved 5.0m Absent or bad Damidiai- Sialsuk 30km Unpaved(Jeepable) 4.Om Absent Sialsuk- Buangpui 35km 3.5m paved 5.0m Absent or bad The sectionsbetween Aizawl-Damdiai and Sialsuk-Thenzawl-Buangpuifollow natural contoursof the hills with generallysteep slopes (both on the hill and the valley).These slopes are prone to landslidesduring rainy seasons. The section between Damdiai-Sialsuk(via Hmuifang) passes through five main villages (Lungsai,Thiak, Sumsuih,Hmuifang and Chamring),and is popularly known as the"Five Villages Road". It is an unpavedjeepable road without shoulders and with no proper arrangementsfor drainage. The formation width does not generally exceed4m. With a beautiful scenicview to the west, clean air and a generally salubriousclimate, the route offers potential for developingtourism around the area. There are 18 villages (19 settlements2) falling along the project road.

I 1.2.1 PROPOSEDIMPROVEMENTS The improvementsworks envisagedfor the priority road (P1-A) are: | Wideningof the roadto an intermediatelane carriageway(5.5m wide) with sidedrains and shoulders; * Construction/replacement/reconstruction3of bridges and culverts; . Constructionof retainingwalls, breast walls and other slope protection works; a Improvementof the roadgeometry and junctions wherever necessary; and, * Provisionof road signsand other roadfurniture required for makingtravel on these roads safeand comfortable. The improvementsproposed under the project are almost exclusivelyalong the existing alignment, except for some minor realignmentto avoid acquisition of properties and for | improvementof the road geometry.

1 The tOOkmroute lengthhas been reduced to 98.7kmafter design (this is a resultof minorimprovement of horizontal/verticalcurves at severallocations).

2 VillageMaubong has two settlements,Damidiai and Lungsai. I Whererequired, new culverts will beadded. I Revised by Lea Associates 2 October2001 (OriginalDocument by ICT,CES, LBII l MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA I 1.3 MAJORFINDINGS OF THE ENVIRONMENTALASSESSMENT As part of the project preparationfor the PhaseI of the project, a detailed 3 environmentalassessment of the P1-Aroute was taken up. The major findingsof the EIAare presented in the followingsections:

I 1.3.1 STABILITY OF SLOPES Thewidening of P1corridor is beingcarried out by cuttingthe hillsidefor a majorlength * of the project route. The stabilityof the cut slopesis an issueof concerngiven the immaturegeology of the projectarea. 40 vulnerablelocations with respectto landslides and potentialfor severeerosion identified where adequate protection measures need to be workedout.

I 1.3.2 DISPOSAL OF CONSTRUCTIONDEBRIS The cutting activitiesshall generate an earthworkof 1.09million cu.m. The disposalof whichis an issueof concern.Even after filling alongthe very shortrealignment stretches (proposedat 29 locations)has been accountedfor, massivequantities of debris (0.74 millioncu.m) shall have to be disposedof.

I 1.3.3 IMPACTON BIO-DIVERSrTY: The roadsideslope all alongthe route P1 supportsa varietyof flora speciesincluding ferns, orchids,bryophytes etc. There exist severalstretches with a high degreeof * biodiversity,referred to as EcologicalIdentity Areas.The proposedwidening may affect such EcologicalIdentity Areasidentified by taking up land with in suchareas in some stretchesif adequateprecautionary measures are not takenup. Movementof machinery can also destroy the rare and endangeredplant species(including the endangered Cyathusspecies or tree fern) at the very edge of the road on the valleyside. Also, the lossof medicinalplants is alsoa potentialnegative impact.

I 1.3.4 IMPACTON SENSITIVE SURFACEWATER SOURCES INCLUDING WATERFALLS The corridorpasses close to coupleof swamps/marshylands in additionto severalponds | that would be adverselyimpacted due to the proposedwidening activitiesduring constructionand operationstages. The disposalof debris during constructionand contaminationby roadrun-off during operation onto thesesensitive water resources is a significantnegative impact that nededsto be addressed. In addition, severalstreams from the hillside,form beautifulwaterfalls along the | corridor.Any cutting of the hill face is not only likelyto disturbthe drainageof these streamsbut alsodestroy their visualappeal and denyaccess to the localpeople who tap | thesestreams at present.

Revisedby Lea Associates 3 October 2001 (OriginalDocument by ICT,CES, LBII MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

1.3.5 FAUNA: The stretcharound the villageof Aibawkhas been reportedto be an areawhere the endangeredChinese Pangolin has beensighted. Since the pangolinis killedfor its scales and meat, the widenedroad increasesthe risks to its alreadydwindling population. During construction,the poachingby labourerscan pose a significantthreat to the creature.

I 1.3.6 RESETTLEMENTAND LOSSOF LIVELIHOOD 58 of the 173affected families are beingdisplaced due to the proposedworks. Though the magnitudeof resettlementis not very high in terms of the familiesto be displaced, the projectneeds to addressthe R&Rand lossof livelihoodissues, as the entireaffected populationis tribal.

1.4 ENVIRONMENTALMANAGEMENT MEASURES PROPOSED A descriptionof the variousmanagement measures during the variousstages of the projectis providedin the followingsections.

1.4.1 PRE-CONSTRUCTIONSTAGE | Duringthe pre-constructionstage, the managementmeasures required will include,the clearance of the vegetation,acquisition of the structures/propertieswithin the proposed CoI, measuresfor protecting/replacingcommunity resources such as hand pumpsand other utilities likelyto be impacted.Their enhancementshall alsobe completedbefore constructionactually starts so that the communitycan start using these while the constructionactivity begins.

1.4.2 CONSTRUCTION STAGE This will be the mostcrucial and activestage for the EnvironmentalManagement Plan. This stage would involvehandling huge quantitiesof earthworkfrom the proposed cutting on the hillside for the accommodationof the proposedcross-section. The dumpingof these wastesis an issueof concern.In additionto the monitoringof the constructionactivity to ensurethat the environmentis not impactedbeyond permissible I limits, the enhancementof water fall locations,mitigation measures suggested for conservationof criticalbiodiversity locations and for sensitivewater resourceswill go on simultaneouslyas the constructionprogresses. * To facilitateimplementation of the enhancementand mitigationmeasures suggested, typicaldesigns of the sameare providedin the Appendices.In addition,the needfor a balancedevaluation and planning for risksassociated with constructionactivities related to roads such as accidentalspillages and consequentdamage to the surrounding environmentin terms of lossof flora andfauna, agricultural crops, continues to growin

Revisedby Lea Associates 4 October2001 (OriginalDocument by ICT, CES, LBII MizoramState Roads Project - PhaseI EnvironmentalManagement Plan for P-IA

importance.Other possiblelocations where a risk assessment4 will be useful include the locationsof Hot Mix plants (spillageof fuel, bitumen etc) and labour-campsites.

I 1.4.3 OPERATIONSTAGE The operation stage will essentiallyentail monitoring activity along the corridor, for the I various indicatorsto evaluatethe performanceof the measuressuggested in the project. The monitoring of the indicators specified in the Monitoring Plan will serve the two purposes. I . To checkthe efficacyof the protection/mitigation/enhancementmeasures implemented, and; * To helpverify or refutethe predictionsmade as a part of the impactassessment 5. The MSRP,being the first major project of the PWDwhere the Environmentaland Social Concernshave been taken up as an integral part of the project, shall provide useful guidelinesin establishingnorms and proceduresfor the EnvironmentalManagement of I roads in Mizoram.This, in turn shall feed into the project preparation and addressalof environmental and social issues in future projects. Thus, it will complete a very I important feedback loop for the PWD. The measuresadopted and/or to be adopted during the different stages of the project have been detailed in Table-3.

I

1 4 Whilerisk managementhere deals exclusively with the physicalenvironment, the ResettlementAction Plan addresses equallyreal risks on the socio-economicaspects. Contingency Planning may be adopted to set asideresources for the eventsfor whichthere is no way of predictingseverity and probabilityof occurrencewith any great degreeof confidence.Normally fixed proportion of the emergencyresponse resource allocabon is kept alwayson stand-byto countersuch a situation. 5 The inputsfrom this and other projectsof similar naturewill help improvethe quality of the environmental managementplans in subsequentprojects or modify any future activitiesalong this highwaytoo. Risk Managementduring the operationphase of the projectalmost exclusively deals with the accidentsof vehides carryingfuel or other hazardousmaterials. At this stagetoo, a dispassionateweighing up of the severityand probabilityis a must to ensurethat neithertoo manynor too few resourcessuch as personnel,vehicles or communicationfacilities are available to tacklethe situationwhenever it arises.

| Revisedby LeaAssociates 5 October2001 (OriginalDocument by ICT,CES, LBII - - m m ------

MizoramState RoadsProject - PhaseI EnvironmentalManagement Planfor P-IA

Table-3: Environmental Management Plan

6 Referenceto Responsibility Environmental Mitigation Measures Contract Location8 Time Frame9 _ _ _ _ Impact/Issue Documents7 Implementation Supervision

P-1: Pre-constructionStaqe ______P.1.1 Vegetationwill be removedfrom the Corridor of Impact Project Before Engineer Removalof Corridor of Impact. Construction Contractor EIneer Vegetation before the commencementof Construction. requirement star PIU, MPWD The acquisitionof structures shall be carried out in NGOs,Collaborating accordanceto the RAPand entitlement Frameworkfor Agencies,SLAO P.1.2 the project. It shall be ensured that all R&Ractivities be RAP P.1. reasonablycompleted before the constructionactivity APadBfrPU,and Before PIU MW,GreacMPWD Grievance Acquisitionof starts, on any sub-sectionof project roads. Project Corridor of impact construction RedressalCells (GRC), Structures requirement. starts Village LevelCommittee All grievancesof the EPswill be reasonablyredressed, (DLC) District Revenue in accordanceto the RAPimplementation mechanism authorities suggestedfor the project. _ _ P.1.3 All utilities will be relocatedwith prior approvalof the Before Relevantstate utility concernedagencies. Relocation will be reasonably Project Referutility relocation core Relevant PIU, MPWD Relocation completebefore constructionstarts, on any sub-section requirement. drawings. starts. Departments of the project road. All community utilities such as community sourcesof water will be replacedat appropriatelocations. Listof community Removalof Therelocation of handpumps at new locationsshall be ufiisa adpms Bfr Common carried out in consultationwith the local village council RAP utilities as hand pumps Before PCC,NGO, PIU, MPWD Property of the nearestsettlement and the roadsidehand pumps requirement. provided in Appendix starts. PIU, MPWD Resources will be shifted to the settlement area, or as desired by 1 the community The replacementwill be reasonablycomplete before ______

6 Someof the mitigation measures are preventive in nature while some others includeadditional measuresin terms of environmental conservationand Involvephysical and constructionwork. The ContractDocuments refer to the following: Ministryof SurfaceTransport, RoadsWing (MoST),Government of India. Speciflcationsfor Road and Bridge Works (Third Revision, 1995. Reprinted, 1998).Speclflcand general conditions of the contract. Unlessotherwise stated, the Project Site covers area beyond the Corridor of Impact and/or the RoW,such as borrow areas, accessroads, service roads and equlpmentstorage sites (MoST: 306.3). Time frame refers to the duration or instant of time when the mitigation measureswill be taken. $ Refer EIA Reportof the project for required detailson the various mitigatlon/managementmeasures proposed. Revised by Lea Associates 7 October 2001 (Original Documentby ICT, CES, LBII ------

MizoramnState RoadsProject - PhaseI EnvironmentalManagement Plan-final for P-IA

Envirorimental .T Referenceto Responsibility ImpactrIssuen Mitigation Measures6 Contract Location' Time Frame9 Documents' Implementation Supervision construction starts.

All accessroads on the hillside (includingvillage access Immediately roads,access to private properties)affected due to the List of accessroads to before project shall be restored prior to the beginningof be restoredprovided construction of P.1.5 construction alongthat particularsection. in Apped 2rovied tructin Constructionof Any land acquisitioninvolved in the constructionof Project in Appendix2. Needs the main Contractor, PIU, MPWD PIU Accessroads these accessroads shall be taken up in accordanceto duricouctin inhay the R&R Policyfor the project, and the entitlements dunng constructon in any shall be in accordanceto the frameworkworked upon period. segmentedof in the R&IPDPplan for the project. Project Highway. All cultural /religious propertiesas gravestones,and P.1.6 buildings,if any, within the CoI shall be relocatedat Referlist of cultural Rel,cation of suitablelocations, as desiredby the community. (Local RAPand propertiesto be Before NGOs(Village level), Cultural Communitymeetings, facilitated by local NGOs,will be Project relocatedin Appendix construction VC, Churchauthorities, PIe MPWD Cutroperv held to discussrelocation aspects, siting of structures requirement. 3. starts. PCC,PIU,MPWD Property etc.) Relocationwill be completebefore construction starts. Advancenotice, as per R&IDPshall be given to the Notice to be P.1.7 proprietor, whosewater drums & pigsty are affected. servedat least Shiftingof water For squatters needingrelocation, all R&R activities will RAP Within RoW. four months PIU, MPWD PIU, MPWD drums, pig sty be undertaken.The assistancefor shifting these requirement. before disbursedbefore construction starts, on any sub-section scheduledstart of project road. of construction.

C-1 ConstructionStage __ _ _ _ *______No hill side shall be cut at slope higher than those SlidesI suggestedin Annexure Li Maximum cut slope for During cutting, Land.Slides All areas of cutting shall be coveredwith vegetation each geomorphological blasting pre- Contractor Engineer LandSldszone givenIn spitting Bioengineeringtechniques as appropriate shall be Annexure_ operations undertakenat all vulnerablelocations. Revised by Lea Associates 8 October2001 (Original Documentby ICT, CES, LBII m ------

MizoramState Roads Project - PhaseI EnvironmentalManagement Plan for P-IA

Environmental Referenceto Responsibility Impact/Issue Mitigation Measures' Contract Location8 Time Framem Impact/Issue Documen~~~~~~~~~~~ts7 Implementation ..... Su~pervisio~n A combinationof bio-engineeringtechniques and hard engineeringsolutions shall be as rockbolting, provision of banddrains at locationsvulnerable to landslides provided,based on the suitabilityat site,as decidedby the geotechnicalexpert of the engineer. Debrisgenerated due to the dismantlingof the existing MoST:112.6 pavementstructure and the cuttingof the hillsidefor the wideningshall be suitably reused in the proposed construction,as follows: As fill materials,for embankments,if C.1.2 any, suchas for Generationof bridgeon the riverVanva, for othershort realignments MoST:112.2 ThroughoutProject During Contracor2MIUD Debris that arebeing proposed. Ductio Contractor EMPWD, e PU.Corridor. Thesub grade of the existingpavement shall be used as embankmentfill material. BentoniteSlurry or similardebris generated from pile l drivingor other constructionactivities shall be disposed suchthat it doesnot flow intothe surfacewater bodies or form mudpuddles in the area. Thedisposal of debrisshall be carriedout onlyat sites Project identifiedfor the purpose.Each site identified shall be requirement approvedby the Engineerbefore dumping is allowedon the site.At eachof the debrisdisposal sites, the Thesites identified are contractorshall carry out the disposalas describedin listedin Appendix5. C.1.3 Appendix-SA. If newdumping sites are openedduring Disposa of the constructionperiod, the Engineershall certify that During Cotatr nier Engineer,PIU, Debrisposlo (a) Theseare not locatedwithin designated forest Environmentallylo s a Constg MPrD areas.(b) Thedumping does not impactnatural ienstife lionsApen drainagecourses (c) Noendangered/rare flora is 6. impactedby suchdumping. . All arrangementfor transportationduring construction includingprovision, maintenance, dismantling and clearing debris, where necessarywill be considered _ __

Revisedby LeaAssociates 9 October2001 (OriginalDocument by lCT,CES, LBII ------m - - mm m -

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan-final for P-IA

Environmental 6 Referenceto Responsibility Environmental Mitigation Measures Contract Location8 Time Frame9 Impact/Issue Documents7 Implementation Supervision

incidentalto the work and should be plannedand implementedby the contractor as approvedand directedby the Engineer. If the dumping locations identified(in appendix-5) are not sufficient for all the cut materialgenerated, the new locationsshall be selectedand approvedby the Engineer.Under no circumstancesshall be contractor dump any material in environmentallysensitive areas identified in appendix 6. Constructionvehicle, machineryand equipment shall C.1.4 moveor be stationed in the designatedarea (RoW or Compactionof CoI, as applicable)only. While operating on temporarily MoST: 112.6 Throughout Project During Engineer, Soil acquired land for traffic detours, storage, material Corridor and all areas Construction. Contractor. PIU,MPWD. handling or any other construction related or incidental temporarily acquired. activities,topsoil from agriculturalland will be preservedas mentionedabove. C.1.5 On road embankmentslopes, slopesof all cut, fill etc., Soil Erosion shrubsand grasswill be planted. On sectionswith high Design Throughout Project filling and deep cutting the side slopeswill be graded requirement Corridor, and coveredwith bushesand grass, etc., adopting serviceroads and suitablebioengineering techniques. The suitabilityto be equipmentstorage decidedby the Engineerat site. sites, etc. Along sectionsabutting water bodies stone pitching MoST: needsto be carried out for slopesbetween 1 vertical: 4 305.2.2.2 During Engineer horizontalto 1 vertical to 2 horizontal. Construction Contractor. PIU,MPWD. At the outfall of each culvert, erosion prevention measure,such as the following, will be undertaken,as provided in the design: MoST: 306.2 1. Grassscales 2. Rockriprap 3. Rock mattresses 4. Cut off wall

Revised by Lea Associates 10 October 2001 (Original Documentby ICT, CES, LBII ------m - m

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

Environmental 66 Referenceto Responsibility Envimpac/Iena Mitigation Measures Contract Location8 Time Frame9 Impact/Issue Documents7 Implementation - Supervision

5. Downstreamsilt screens/walls The work shall consistof measuresas per design,or as directed by the Engineerto control soil erosion, sedimentationand water pollution, through use of berms, dikes, sedimentbasins, fiber mats, mulches, grasses,slope drains and other devices.All temporary sedimentation,pollution control works and maintenance thereof will be deemedas incidentalto the earth work or other items of work and as such no separate payment will be made for them. C.1.6 Vehicle/machineryand equipmentoperation, Contamination maintenanceand refueling shall be carried out in such Contract of Soilby Fuel a fashionthat spillageof fuels and lubricantsdoes not Requirement and Lubricants contaminatethe ground. An 'oil interceptor" will be Throughout Project provided for washdown and refueling areas. Corridor, During Engineer, Fuel storageshall be in proper bundedareas. All spills all accessroads, Construction. Contractor. PIU,MPWD. and collectedpetroleum products shall be disposedoff temporarily acquired in accordancewith MoEFand MPCBguidelines. site. Fuel storageand refilling areasshall be located at least 300m from all cross drainagestructures and important water bodiesor as directed by the Engineer. C.1.7 All spoilsshall be disposedoff in the manneras Contamination specifiedin C.1.2. No new disposalsite shall be created of Soil by as part of the project, except with prior written and MoST:201.2 Construction expressapproval of the Engineer. Throughout Project Wastes& their All waste materialshall be completelydisposed as Corridor, DuringEngineer, disposal desiredand the site shall be fully cleanedbefore all accessroads, Construction Contractor PIU,MPWD. handingover. The Engineerwill certify in this regard. MoST: temporarily acquired All temporary acquiredland shall be dealt in the 301.3.11 sites. manner as laid out in the EMPif dumping of waste is .3. envisaged.The contractor at his cost shall resolveany claim, arising out of waste disposal.

Revised by Lea Associates 11 October 2001 (Original Documentby ICT, CES, LBII ------m -

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

Environmental 6Reference to Responsibility IEmpact/Issue Mitigation Measures6 Contract Location8 Time Frame9 Documents7 Implementation Supervision C.1.8 The Contractorshall obtain materialsfrom quarriesonly Quarry after consentof the DoFor other concemedauthorities Operations and only after developmentof a comprehensivequarry' redevelopmentplan, as per the MizoramMining Rules. All quarries During licensing Alternativelythe Contractorshall acquire the required recommendedto be operationof the Contractor Engineer, materialfrom quarries licensedby the SPCB.The used in the project are quarriesfor the PIU,MPWD. quarry operationsshall be undertakenwithin the rules listed in Appendix7. project and regulationsin force. Whereverhill are used and operated for the purpose of quarrying in the bedsor banksof rivers/rivuletswill not be usedfor quarrying. C.1.9 Sandwould have to be hauledfrom the valleysfor use Useof Crusher in construction.However, sincesand is a scarce Dust resource,the project recommendsthe use of crusher Project Throughout the During Contractor Engineer, PIU, dust as fine aggregate.The contractor shall obtain the requirement project corridor construction MPWD requisitepermission from the Engineer,prior to hauling sand for construction,indicating the source. C.1.10 The constructionof a seriesof pipe culverts shall be Ch. 86.7 to 86.8 km During Lossof Water undertakento enable unhinderedcross-flow and Project construction Bodies maintainthe level of water in the swampyarea. The requirement. constructionshall be carried out during summer only. The constructionshall be worked out to encroach minimum area of the pond. A clear strip 3 to 4 m width only shall be used for construction activity around the All water body Whenever corridor within the swamp.The workersshall be MoST: locationsalong the encountered instructed not to venture into or poachfor wildlife 305.4.1 corridor. during Contractor Engineer, PIU, within the swamp. The volumeof water storage lost construction MPWD. shall be compensatedfor by excavationof an equal volume of similar depth in the directionof flow as approved by the Engineer. Whereverdigging is undertaken,the banksshall be protected by means as designedor as approved by the SeeAppendix 8. Engineer.The excavationshall be carried out in a manner so that the side slopesare no steeperthan 1 Revised by Lea Associates 12 October 2001 (Original Documentby lCT, CES, LBII -- - - m - m ------m -

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

Environmental Referenceto Responsibility Impact/Issue Mitigation Measures6 Contract Location8 Time Frame9 Documents? Implementation Supervision vertical to 4 horizontal, otherwise slope protection work shall be provided,as approvedby the Engineerand specified by EMPclause C.1.5. As far as practicable,and as approved by the Engineer, excavationfor replacementof water bodies shall be at the closestpossible place/location, with respectto the original water body or part thereof consumedby filling. C.1.11 Any sourceof water (potable or otherwise) for the Lossof Other community such as water tanks along the water RAP Water Sources streamsfor community usesetc., incidentallylost shall requirement. be replacedimmediately. The locationand siting of the MoST: 110.3 replacedsource of water shall be in consultationwith Throughout Project Whenever the local user population.Generally, the sourceof Corridor encountered Contractor Engineer, water supply will be movedaway from the road and during PIU,MPWD. within the settlement area. construction The replacementshall be ready prior to demolition/ MoST301.5 dismantling of the existing source. This sub-clause covers the identified sourcesof water in the pre- constructionstage. C.1.12 The contractor shall construct adequatelysized culvert Flooding to allow unimpededflow of all the streamscrossing the highway. In addition to the widening of existing culvertsthe construction of new adequatelysized cross- Appendix-8 drainageworks shall be carried out. Project During In addition to the design requirements,the contractor requirement Throughout proje ConstructionD Engineer, shall take all desired measuresas directed by the MoST corridoruall access and the Defects . PIU,MPWD. Engineersuch measuresto preventtemporary or 305.3M2 cordo, allpaccess LiabilityPeriod. permanentflooding of the siteor anyadjacent area. 3acq3u2roads,itemprrlsLaiiy.eid The scopefor prevention of flooding includes prevention of lossof use, lossof accessof any land or property thereon resulting from flowing or stagnant water as direct/ indirect impactof construction.

Revised by Lea Associates 13 October 2001 (Original Document by ICT, CES, LBII ------m ------

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

6 Referenceto Responsibility Environmental Mitigation Measures Contract Location3 Time Frame9 ___ Impact/Issue Documents7 Implementation Supervision

C.1.13 Silt fencingwill beprovided at the baseof the Siltationinto embankmentfor the perimeterof waterbodies abutting MoST:306 WaterBodies the road. ThroughoutProject Siltationof soilinto the waterbodies will beprevented hrogout Pes During as far as possible.The contractor will take all Cordor, all access Construction. Contractor. PIU,MPWD. reasonablemeasures as per EMPClause C.1.5 acquiredsites. Constructionmaterials containing fine particles shall be MoST:306 storedin anenclosure such that sediment-ladenwater doesnot draininto nearby watercourses. C.1.14 Notree or vegetationother than those designated for TorrentRun-off fellingwill cleared. MoST:201.2. ThroughoutProject Thecontractor shall take all necessaryprecautions and Corridor,all access During Cotrct Engineer, constructtemporary/permanent devices to prevent MoST: roads,temporarily Construction. ontracor. PIU,MPWD. waterpollution (due to silitationand increaseof 306.2& 4 acquiredsites. turbidity). C.1.15 In sectionsalong water courses, and close to cross- Alterationof drainagechannels, earth, stone or anyother Drainage constructionmaterials or appendageshall be properly MoST: ThroughoutProject disposedoff so as not to blockthe flow of water. 305.3.7 Corridor,all accesscngineer, During PIU, Allnecessary measures shall be takento prevent roads,temporarily Construuion. Contractor. MPWD. earthwork,stonework, materials and appendage as well acquiredsites. as the methodof operationfrom impeding cross- MoST:306 drainageat rivers,streams, water canals and existing irrigationand drainage systems.

Increased Retentionwork will be takenup on the roadside MoST:111.15 . S During Contractor Engineer,PIU, Run-offse drainagechannels as per the roadsidedrainage design. Entire Run-off__.__ Project ite. Construction. . MPWD. C.1.17 All measureswill betaken to preventthe wastewater ThroughoutProject Contamination producedin constructionfrom entering directly into MoST:306 Corridor, During Contractor Engineer,PIU, of Waterfrom streams,water bodiesetc. asdirected by Engineer. Construction MPWD Construction Constructionwork close to the streamsor waterbodies

Revisedby LeaAssociates 14 October2001 (OriginalDocument by ICT,CES, LBII ------

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

Referenceto Responsibility Impact/Issue Mitigation Measures6 Contract Location8 Time Frame9 IpmntnSeVl Impact/Issue ~~~~~~~~~~~~~~Documents7 Implementation Supervision

Wastes shall be avoidedduring monsoonand measuresas per MoST: 111.13 EMPclause C. 1. 13 will be taken. The dischargestandards promulgated under the EnvironmentalProtection Act, 1986shall be strictly adheredto. All waste arisingfrom the project is to be MoST: 111.1 disposedoff in a manner that is acceptableto MPCB and the Engineer. C.1.18 The work shall be carried out in sucha manner that MoST: 111.4 Contamination pollution of natural watercoursesand, ponds is avoided. from Fuel and Vehicle,machinery & equipment maintenanceand Lubricants refueling shall be done in a manneras specified in EMP MoST: 113.13 Throughout Project clauseto prevent pollution of water. Corridor, all access At construction vehicleparking locationsand at roads, sites During Engineer fuel/lubricant storagesites, oil and greasetraps shall be temporarily acquired, Construction Contractor PIU,MPWD. providedto preventthe contaminationof the soil and MoST: 111.1 all borrow areas and nearby watercourses. truck lay-byes. Waste products must be collected,stored and taken to approveddisposal sites in complianceof MPCB guidelinesor any other relevantlaws, and to the entire satisfactionof the Engineer. C.1.19 Constructionlabourers' camps shall be located at least Sanitationand 500m away from the nearesthabitation. MoST:111.14 waste disposal The sewagesystem (including septic tones & soak-pits) in construction for a construction labourer'scamp shall be designed, All areas in immediate During camps built and operated so that no pollution to ground or vicinity of construction Establishment, adjacentwater bodies/ watercoursestakes place. campsitechosen by Operationand Contractor. Engineer, Compliancewith the relevantlegislation shall be strictly the contractor from Dismantlingof PIU,MPWD. adheredto. Garbagebins shall be provided in the recommendedlocation Such Camps. campsand regularly emptiedand the garbagedisposed of camps given in off in a hygienic manner,to the satisfactionof the Appendix 9. relevant norms and the Engineer. In connectionwith undergroundwater resources, Revised by Lea Associates 15 October 2001 (Original Documentby ICT, CES, LBII ------m ------

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

6 EnIronment/ls Mitigation Measures Referenceto Location Time Frame9 Responsibility Documents mlmnation Supervision including percolatingwater, the contractor shall take all necessaryprecaution to prevent interferencewith such water resources. MoST: 111.1 All relevantprovisions of the FactoriesAct, 1948 and the Buildingand other ConstructionWorkers (regulation of Employmentand Conditionsof Service)Act, 1996 shall be adheredto. Unlessotherwise arranged by the local sanitation authority, arrangementsfor proper disposalof excreta by Compostingat the workplace suitably approvedby the local medicalhealth or municipalauthorities or as per directed by Engineer,shall be made. C.1.20 The contractor will minimisewastage of water in the Wastageof construction process/operations. Project Water The Contractorshall arrange for supplyand storageof requirement Throughout Proje* During Engineer, water and no such supply and storagewill be provided Corridor Construction. Contractor. PIU,MPWD. by the PIU, MPWD.The Contractorshall not open a new bore well or extract groundwaterwithout permissionfrom the GroundWater Board. C.1.21 Water harvestingstructures will be constructedas per As per Appendix 10. During Engineer PIU, MPWD Harvestingof the typical designsprovided in the EMP.The selection Project Construction. Water for of the typology applicablewill be decided by the requirement Construction Engineerwith inputs from the PIU. Such storageof water will be deemed incidentalto the work. The contractorwill be responsiblefor the maintenanceof water quality in such storage. As these streams(on which the storage will be built) are used by the community now, the contractor shall not disrupt the traditional use of water from this storage. C.1.22 The Contractorshall be responsiblefor arranging RAP Throughout Project During Engineer, Disruptionto adequatesupply of water for the whole construction requirement. Corridor, all access Construction Contractor PIU,MPWD. other Usersof period. _ roads, sites

Revised by Lea Associates 16 October 2001 (Original Documentby ICT, CES, LBII -- m ------

MizoramState RoadsProject - PhaseI Environmental ManagementPlan for P-IA

6 Environmental Mitigation Measures Referenceto Enimpat/ssena Mitigation Measures' Contract LocationO Time Frame9' Responsibilitymlmnaio uevso 7 Impact/Issue ~~~~~~~~~~~~~~Documents Implementation Supervision Water While working acrossor closeto the Vanva River,the temporarily acquired Contractorshall not preventthe flow of water. If for and all borrow areas any bridgework, etc., closureof flow is required,the as well as the Contractor shall seekapproval of the Engineer.The immediate Engineerwill havethe right to ask the Contractorto surroundingsof these serve notice on the downstreamusers of water areas. sufficientlyin advance. Constructionover and closeto the non-perennial streamsshall be undertakenin the dry session. Constructionwork expectedto disrupt usersand impacting community water bodieswill be taken up after serving noticeon the localcommunity. The Contractormay use the natural sourcesof water subject to the provisionthat any claim arising out of conflicts with other usersof the said natural sourcesof water shall be dealt with entirely by the contractor. C.1.23 All vehiclesdelivering materials to the site shall be MoST: 111.9 Generationof coveredto avoid spillageof materials. Dust The Contractorshall take every precautionto reduce the level of dust emissionfrom the hot mix plants and MoST: 111.5 the batchingplants up to the satisfactionof the Engineer. All existing highwaysand roadsused by vehiclesof the MoST: 111.9 Throughout Project contractor, or any of his sub-contractoror suppliersof Corridor,all access During Engineer, materialsor plant and similarly roads which are part of roads,temporarily Construction Contractor PIUMPWD. the works shall be kept clean and clear of all dust/mud acquiredsites. or other extraneous materialsdropped by such vehicles or their tyres. Clearanceshall be effected immediatelyby manual sweepingand removalof debris, or, if so directed by MoST: 111.10 the Engineer,by mechanicalsweeping and clearing equipment, and all dust, mud and other debris shall be _ __ removedcompletely. Additionally if so directed by the MoST:118.1 ______Revised by Lea Associates 17 October 2001 (Original Documentby ICT, CES, LBII ------

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

Environmental . . . 6 Referenceto Responsibility Impact/Issue Mitigation Measures6 Contract Location8 Time Frame9 Impact/Issue ~~~~~~~~~~~~~~~DocumentS7 Imnplementation Supervision removedcompletely. Additionally, if so directed by the Engineer,the road surfacesshall be hosed or watered Contract using necessaryequipment. requirement Plants, machineryand equipmentshall be so handled (including dismantling)as to minimisegeneration of dust. C.1.24 Hot mix plants and batching plantsshall be located Emissionfrom sufficiently awayfrom habitation, agricultural Hot-Mix Plants operationsor industrial establishments.Where possible and Batching such plants will be located at least 1000m away from MoST: 111.5 During Erection, Plants the nearesthabitation. All Hot-mix and Testng, Contractor. Engineer,PIU, The exhaust gasesshall comply with the requirements MoST: 111.5 Batching Plants. Dismantlingof MPWD. of the relevantcurrent emissioncontrol legislation.All Such Plants. operationsat plantsshall be undertakenin accordance with all current rules and regulationsprotecting the environment. C.1.25 Constructionlabourers' camps shall be located at least Odour from 500m away from the nearesthabitation to avoid Construction conflicts and stressover the infrastructure facilities, labourer's with the local community. All Construction During camps The waste disposaland sewagesystem for the camp Contract Labourers'Campsand Establishment, Engineer, PIU, shall be properly designed,built and operatedso that requirement immediate surrounding Operation and Contractor. MPWD. no odour is generated. Relevantprovisions as the Dismantlingof FactoriesAct, the Buildingand other Construction Such Camps. Workers (regulation of Employmentand Conditionsof Service)Act, 1996 and all other relevantlegislations shall be strictly adheredto. C.1.26 The dischargestandards promulgated under the Contract Throughout Project Emissionfrom EnvironmentProtection Act, 1986shall be strictly requirement Corridor, all access During Engineer, PIU, Construction adheredto. All vehicles,equipment and machineryused roads, sites Dunng Contractor. MPWD. Vehicles, for construction shall conform to the relevant Bureauof temporarily acquired . Equipmentand Indian Standard(BIS) norms. and all borrow areas.

Revisedby Lea Associates 18 October 2001 (OriginalDocument by ICT, CES, LBII ------

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

Environmental . . 6 6 Referenceto Responsibility Impact/Issue Mitigation Measures Contract Location8 Time Frame9 Documents' Implementation Supervision Machinery All vehicles,equipment and machineryused for Contract construction shall be regularly maintainedto ensure requirement that pollution emissionlevels comply with the relevant requirementsof MPCBand the Engineer. C.1.27 All crushersused in constructionshall conform to Pollutionfrom relevant dust emissioncontrol legislations. Clearance Contract Crusher for siting shall be obtained from the MPCB. requirement Alternatively, only crushersalready licensedby the During Erection, MPCBshall be used. Waterwill be sprayedduring the Testing, non-monsoonmonths, regularlyto minimisedust, in All AggregateCrushing Operationand Contractor. Engineer,PIU, the wholecrusher plant area. Design Plants. Dismantlingof MPWD. The suspendedparticulate matter contribution value at requirement. Such plants. a distanceof 40m from a controlled isolatedas well as . from a unit locatedin a cluster should be lessthan MoST: 111.1 500jig/m3 . The monitoring is to be conductedis envisagedin the monitoringplan. C.1.28 The plantsand equipmentused in construction MoST: 111.13 Noisefrom (including the aggregatecrushing plant) shall strictly Vehicles,Plants conform to the Gol noise standards. and Equipment. All vehiclesand equipment used in constructionshall be MoST: 111.13 fitted with exhaust silencers.During routine servicing operations, the effectivenessof exhaust silencersshall MoST: 111.1 be checkedand if found to be defectiveshall be Throughout Project replaced.Notwithstanding any other conditions of Corridor, all access During Engineer, PIU contract, noise level from any item of plant(s) must roads,sites Con*ruction. Contractor. MPWD. comply with the relevant legislationfor levelsof sound temporarily acquired emission. Non-compliantplant shall be removedfrom and all borrow areas. site. Noiselimits for construction equipmentused in this project (measuredat one metre from the edge of the MoST: 111.13 equipment in free fleld) such as compactors,rollers, front loaders,concrete mixers, cranes(moveable), vibrators and saws shall not exceed75 dB(A), as ______Revised by Lea Associates 19 October 2001 (Original Documentby ICT, CES, LBII m ------

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

Environmental Mitigation Measures6 6Reference to Responsibility Environmen MitigationMeasures Contract Location' Time Frame9 _'l Impact/Issue Documents7 Implementation Supervision

specifiedin the Environment(Protection) Rules, 1986, Maintenanceof vehicles,equipment and machinery shall be regular and to the satisfactionof the Engineer, to keep noisefrom these at a minimum. Workers in vicinity of loud noise,and workers working MoST: 111.6 with or in crushing, compaction,concrete mixing operationsshall wear earplugs. C.1.29 Blastingshall be carried out only with permissionof the Noisefrom Engineer.All the statutory laws, regulations,rules etc., MoST:302.1 Blastingor Pre- pertainingto acquisition,transport, storage, handling splitting and use of explosivesshall be strictly followed. During Operations Blastingshall be carried out during fixed hours (preferablyduring mid-day), as permitted by the All Blastingand Pre- Operationand Contractor. Engineer, PIU, Engineer.The timing should be made known to all splitting Sites. Closureof Such MPWD. peoplewithin 500m (200m for pre-splitting) from the Sites. blastingsite in all directions. People,except those who actually light the fuse shall be excludedfrom the area MoST-302.4 of 200m (50m for pre-splitting) from the blasting site in all directions at least 10 minutes before the blasting. ______C.1.30 All works shall be carried out in sucha fashionthat the During Lossor Damage damage or disruption to the flora is minimum. Treesor Entire Project Site. Construction Contractor Engineer,PIU, of Vegetation shrubswill only be felled or removedthat impinge Contract As encountered During MPWD. directly on the permanentworks or necessary requirement Construction temporary works with prior approval from the Engineer. During Engineer, PIU, MPWD The Engineershall approve suchfelling on the adviceof As decided by the Construction DoF. the PIU and only when the PIU receivesa "clearance" DoF. for such felling from the DoF,as applicable. Design Treesfelled shall be replacedas per the compensatory requirement. As per DoF afforestation criteria in accordancewith the Forest Existing PIU, MPWD. (Conservation)Act, 1980. Programmes.

Revised by Lea Associates 20 October 2001 (Original Document by ICT, CES, LBII m m - - - - - m ------m - - - -

MizoramState RoadsProject - PhaseI Environmental ManagementPlan for P-IA

Environmental Mitigaton Measures Referenceto Responsibility ImpactitiatinsMasues 6 Contract Location8 Time Frame9 Impact/Issue ~~~~~~~~~~~~~~~~Documents' Implementation - Supervision C.1.31 Bamboofencing shall be erectedto delineatethe area Design At the locations During Contractor Engineer, PIU, Conservationof rich in biodiversityas identifiedfrom field visits. Drains requirement mentionedin Appendix Construction MPWD. Biodiversityat will be provided in the area to prevent exposureto 13. But protection specific contaminatedrun-off during the constructionphase. works to be locations The sketchesare attached at the end of the EMPfor completed protection works. before Introduction of exotic specieswill be preventedin the earthworksstart roadsideplantation for suchstretches. Instead of in stretch blasting, pre-splitting will be used for stretches extending 500 m extendingzoom beyondthe chainagesidentified in on either side of Appendix-4. chainages Water shall be sprayedto preventdust accumulationon specified. flora by the measuresdescribed above. A dated photographwhen sprayingis carried out, each Saturday afternoon shall be maintained.Otherwise, the contractor shall be responsiblefor lossof any flora within these areas. C. 1. 32 Accessto the road shall be restrictedusing barbedwire Project Km15.816to During Contractor Engineer,PIU, Protectionof fencing alongthe entire realignmentsection. requirement kml6.011 construction MPWD Biodiversity-rich No constructioncamp shall be sited within 500 m of period area in Falkwan both the ends of the realignment. No constructionactivity, except if and when concreting is required, shall be allowed before sunrise or after sunsetwithin this extended area. C.1.33 Blastingwill be prohibited in the stretch extending During At locationsidentified Contractor Engineer,PIU, Conservationof 200m on either side of the designatedEcological construction as E.Id.A'sin MPWD Ecological Identity Areas (E.Id.A). Introduction of exotic species Appendix-4. Identity Areas will be prohibited in the E.Id.A'S.No construction (EIdA) workers campsshall be allowed in the stretch extending 200m on either side of E.Id.A's.Water sprayingshall be carried out every day during the duration of earthwork within the E.Id.A's.

Revised by Lea Associates 21 October 2001 (OriginalDocument by ICT, CES, LBII ------

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

Environmental MitigationEnvironmentalMeasures 6 ~~ReferenceContract to Location8 Time Frame9 RsnbiResponsibility Impact/Issue Documents7 Implementation Supervision

During construction,at any point of time, if a rare/ C.1.34 threatened/endangeredflora speciesis found, it shall Damageor Loss be conservedin a suitable manner.The Engineer,on Contract Throughout Project During Contractor, Engineer, PIU MPWD. of Chance-found specificadvice from the PIU, MPWDshall approve requirement Area. Construction Important Flora detailedconservation processes, plans and designsas well as associatedmodification in the project design. C.1.35 All works are to be carried out in such a fashionthat Contract During Contractor. Engineer,PIU, Loss,Damage the damageand disruption to fauna is minimum. requirement Construction. MPWD. or Disruptionto Constructionworkers shall be instructedto protect Fauna. natural resourcesand fauna, including wild animalsand All along the Project aquatic life. Hunting and unauthorisedfishing are corridor,all access prohibited. roads,sites Adequatelysized culverts will be provided for the easy temporarilyacquired. Engineer, passageof the ChinesePangolin in the vicinity where Forests sighting has beenreported. The months of all these Department, culverts shall be kept clean during construction phase. DepartmPWD The PWD will co-ordinateefforts with the local NGOs, specifiedin Appendix PIU, MPWD YMAand the Churchat Falkawnand Aibawkto spread awareness,and to save the endangeredFauna-Chinese 11. Pangolin.Adequate number of signboards(at every km.) will be placed in the stretchesspecified in Appendix 11. C.1.36 Duringconstruction, at any point of time, if a rare/ Damageor Loss endangered/ threatenedfauna speciesis spotted,the Contract During Contractor, of Chance-found contractor shall makeall arrangementsto intimate the r tD Entre Project Site. Cunr PIU,MPWD. Important Forests(wildlife) authoritiesand measureswill be taken Construction. Engineer Fauna. for its conservationduring the operation period also. C.1.37 The Contractorshall provide safeand convenient MoST: 112.7 Lossof Access passagefor vehicles,pedestrians and livestockto and All alongthe Project During Engineer, from side roads and propertyaccesses connecting the corridor. Construction Contractor PIU,MPWD. project road. Work that affects the use of side roads and existing accessesshall not be undertakenwithout

Revised by Lea Associates 22 October 2001 (OriginalDocument by ICT, CES, LBII ------

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

Environmental . . . 6 Referenceto Responsibility Impact/rssue Mitigation Measures Contract Locations Time Frame9 Documents' Implementation Supervision providing adequate provisionsto the prior satisfaction of the Engineer. The works shall not interfere with or cause inconvenienceto public or restrict the accessto use and occupation of public or private roads,and any other accessfootpaths to or of propertieswhether public or private. Accessacross the work-zonewill be provided for two slots every day during construction(2 hours in the morning;. and 2 hours in the afternoon). For this purposethe contractor shall maintaina strip of pavement acrossthe work zone of such quality that light motor vehicles (LMV) can passwithout difficulty or dangerof breakingdown. C.A38 DetailedTraffic Control Plansshall be preparedand Traffic Delays submittedto the Engineerfor approval, 5 daysprior to MoST:112.1 and Congestion commencementof works on any section of road. The traffic control plans shall contain detailsof arrangementsfor construction under traffic and details of traffic arrangementafter cessationof work each day. All along the Project Du ing Contractor Engineer, PIU, The Contractorshall ensurethat the running surface is always maintainedin running condition, particularly during the monsoonso that no disruption to the traffic flow occurs. MoST: 112.2

C.1.39 The Contractorshall take all necessarymeasures for Traffic Control the safety of traffic during constructionand provide, and Safety erect and maintain such barricades,including signs, MoST:112.4 markings,flags, lights and flagmen as may be required During Engineer, PIU, by the Engineerfor the information and protection of Entire Projectsite. During n Contractor MPWD traffic approachingor passingthrough the section of the highway under improvement. MoST: 112.1 All signs, barricades,pavement markings shall be as per the MoSTspecification. Before taking up construction Revised by Lea Associates 23 October 2001 (Original Documentby ICT, CES, LBII ------

MizoramState Roads Project - PhaseI Environmental ManagementPlan for P-IA

Environmental M M 6 Referenceto Responsibility Impact/Issue Mitigation Measu res6 Contract Location8 Time Frame9 Documents7 Implementation Supervision on any sectionof the highway, a traffic control plan shall be devisedto the satisfactionof the Engineer. C.1.40 The Contractor is requiredto comply with all the Risk from precautionsas required for the safety of the workmen Operations as per the International LabourOrganisation (ILO) ConventionNo. 62 as far as those are applicableto this contract. The contractor shall supplyall necessary C Engineer, PIU, safety appliancessuch as safety goggles,helmets, Contract Entire Projectsite. During Contractor MPW I masks, etc., to the workers and staff. The contractor has to comply with all regulation regardingsafe scaffolding, ladders,working platforms, gangway, stairwells,excavations, trenches and safe meansof entry and egress. C.1 41 Adequateprecautions will be taken to preventdanger Risk from from electrical equipment. No materialor any of the Electrical sites will be so stackedor placed as to causedanger or Equipment inconvenienceto any person or the public. All necessaryfencing and lights will be providedto protect Engineer,PIU, the public. All machinesto be used in the construction MoST: 106 Entire Project site. During Contractor MPW I will conform to the relevantIndian Standards(IS) Construction MPWD codes, will be free from defect, will be kept in good working order, will be regularly inspectedand properly maintainedas per IS provisionsand to the satisfaction of the Engineer. _____ C.1.42 All workersemployed on mixingasphaltic material, Riskat cement, lime mortars, concrete etc., will be provided Hazardous with protectivefootwear and protective goggles. MoST: 111.1 Activity Workers,who are engagedin welding works, would be Engineer, provided with welder's protectiveeye-shields. Entire Project site. During Contractor PIU,MPWD. Stonebreakerswill be providedwith protectivegoggles Construction and clothing and will be seatedat sufficiently safe intervals. The use of any herbicideor other toxic chemicalshall _ Revised by Lea Associates 24 October 2001 (Original Documentby ICT, CES, LBII m ------

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

En v i r o n m e n t al . . 6 Referenceto Responsibility Impact/Issue Mitigation Measures Contract Location8 Time Frame9 Documents7 Implementation Supervision be strictly in accordancewith the manufacturer's instructions.The Engineershall be given at least6 MoST: 111.6 working days notice of the proposeduse of any herbicideor toxic chemical.A registerof all herbicides and other toxic chemicalsdelivered to the site shall be kept and maintainedup to date by the Contractor.The register shall include the trade name, physical propertiesand characteristics,chemical ingredients, health and safety hazard information, safe handlingand storageprocedures, and emergencyand first aid proceduresfor the product. C.1.43 No man below the age of 18 yearsand no woman shall Riskof Lead be employedon the work of painting with products Pollution containinglead in any form. No paint containinglead or lead products will be used except in the form of paste Entire Project site During Contractor Engineer, or readymadepaint. Facemasks will be suppliedfor MoST: 111.1 Construction PIU,MPWD. use by the workers when paint is appliedin the form of spray or a surface having lead paint dry rubbed and scrapped. C.1.44 All reasonableprecaution will be taken to prevent Riskcaused by danger of the workers and the public from fire, flood, Contract During Engineer, Force'Majure drowning, etc. All necessarysteps will be taken for Entire Projectsite CronstitDucion Contractor PIU,MPWD. prompt first aid treatment of all injuries likely to be requirement Entire Proectsit sustainedduring the courseof work. Exceptas may be provided in the contract or ordered or authorisedby the Engineer,the Contractorshall not use explosives.Where the use of explosivesis so C.1.45 provided or orderedor authorised,the Contractorshall Riskfrom comply with the requirementsof the following Sub- MoST: 302.4 All blastingand Pre- During Contractor Engineer Explosives Clausesof this Clausebesides the law of the land as splitting Sites. Construction applicable: The Contractor shall at all times take every possible

______precaution and shall comply with appropriate laws and ______Revised by Lea Associates 25 October 2001 (Original Documentby ICT, CES, LBII ------

MizoramState RoadsProject- PhaseI EnvironmentalManagement Plan for P-IA

6 Referenceto 8 9 Responsibility Environmental MMitigationMeasures Contract Location Time Frame - - - 7 Impact/Issue Documents Implementation Supervision

regulationsrelating to the importation,handling, transportation, storageand use of explosivesand shall, at all times when engagedin blastingoperations, post sufficient warning flagmen, to the full satisfactionof the Engineer. The Contractorshall at all times makefull liaison with and inform well in advanceand obtain such permission as is requiredfrom all GovernmentAuthorities, public bodiesand private partieswhomsoever concerned or affectedor likely to be concernedor affected by blastingoperations. The Contractorshall, at his own expense,conform to all C.1.46 anti-malarialinstructions given to him by the Engineer, Contract Entire Projectsite. During Contractor. Engineer, Malarialrisk including filling up any borrow pits which may have requirement Construction PIU,MPWD. beendug by him. At every workplace,a readily availablefirst aid unit including an adequatesupply of steriliseddressing material and applianceswill be provided as perthe FactoryRules of Mizoram. C.1.47 Workplaces,remote and far awayfrom regular Entire Projectsite. During Contractor Engineer, First Aid hospitalswill have indoor heath units with one bedfor MoST: 1207.6 Construction PIU,MPWD. every 250 workers. Suitabletransport will be provided to facilitate take injured or ill person(s)to the nearest applicablehospital. At everyworkplace and construction camp, equipment and nursing staff shall be provided. In every workplaceat suitableand easilyaccessible placesa sufficient supply of cold potable water (as per C.1.48 IS) will be providedand maintained.If the drinking Contract Entire Projectst During Contractor Engineer, PotableWater water is obtained from an intermittent public water requirement Construction PIU,MPWD. supplythen, storagetanks will be provided.

C.1.49 The Contractorduring the progressof work will Contract All Construction During Contractor Engineer, Revised by Lea Associates 26 October 2001 (Original Documentby ICT, CES, LBII ------m - -

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

Environmental Referenceto Responsibility Impact/Issue Mitigation Measures0 Contract Location8 Time Frame9 Implementation Supervision

Hygiene provide,erect and maintainnecessary (temporary) requirement Labourers'Camps Construction PIU,MPWD. living accommodationand ancillaryfacilities for labour to standardsand scalesapproved by the resident Engineer. There shall be providedwithin the precinctsof every workplace,latrines and urinals in an accessibleplace, and the accommodation,separately for each for these, as per standardsset by the Buildingand other ConstructionWorkers (regulation of Employmentand Conditionsof Service)Act, 1996. Exceptin workplaces providedwith water-flushedlatrines connected with a water borne sewagesystem, all latrinesshall be providedwith dry-earth system (receptacles)which shall be cleaned at least four times daily and at least twice during working hours and kept in a strict sanitary condition. Receptaclesshall be tarred insideand outsideat least once a year. If women are employed, separatelatrines and urinals, screenedfrom those for men (and marked in the vernacular) shall provided. There shall be adequatesupply of water, closeto latrinesand urinals. All temporary accommodationmust be constructed and maintainedin such a fashion that uncontaminated water is availablefor drinking, cookingand washing. The sewagesystem for the camp must be designed, built and operated so that no health hazardoccurs and no pollutionto the air, ground or adjacentwatercourses takes place.Compliance with the relevantlegislation must be strictly adheredto. Garbagebins must be provided in the camp and regularly emptiedand the garbagedisposed off in a hygienicmanner. Constructioncamps are to be sited at least 200m away from the nearesthabitation and adequate health care is

Revised by Lea Associates 27 October 2001 (Original Documentby ICT, CES, LBII - m - m m m - m - - m - - m m - -m -

MizoramState Roads Project - PhaseI EnvironmentalManagement Plan for P-IA

Referenceto Responsibility Environmental MitigationMeasures6 DContract Location Implementation Supervision

to be providedfor the workforce. Unlessotherwise arranged for by the localsanitary authority,arrangement for disposalof excretaby incinerationat the workplaceshall be madeby means of a suitableincinerator approved by the localmedical healthor municipalauthorities. Alternatively, excreta maybe disposedoff by puttinga layerof nightsoils at the bottomof a permanenttank preparedfor the purposeand covering it with 15cm layerof wasteor refuseand then covering it with a layerof earthfor a fortnight(by then it will turn into manure). Oncompletion of the works,all suchtemporary structuresshall be clearedaway, all rubbishburnt, excretaor otherdisposal pits or trenchesfilled in and effectivelysealed off andthe outlinesite left cleanand tidy, at the Contractor'sexpense, to the entire satisfactionof the Engineer. _ All necessaryand adequate care shall be taken to 1.50l minimizeimpact on culturalproperties (which includes Protection/Mitig culturalsites and remains,places of worshipincluding MoST3015 aroection/Mitig churchesand shrines, etc., graveyards, monuments and MoSn:301.5 ation of anyother importantstructures as identifiedduring EntireProject site. During Contractor Engineer, Religious design. Design Construction PIU,MPWD. Structuresand design.en Shrines All conservationand protectionmeasures will be taken requirement up as perdesign. Access to suchproperties from the roadshall be maintainedclear and clean. Allfossils, coins, articles of valueof antiquityand C.1.51 structuresand other remainsor thingsof geologicalor Chancefound archaeologicalinterest discovered on the site shallbe Contract . . During Engineer, Archaeological the propertyof the Government,and shallbe dealt with requirement Construction PIU,MPWD. property as per provisionsof the relevantlegislation. Thecontractor shall take reasonableprecaution to

Revisedby LeaAssociates 28 October2001 (OriginalDocument by ICT,CES, LBII m ------m - m ------

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

Environmental 6 to 8 Environmental Mitigation Measures ~~ReferenceContract Location Time Frame9 RsnbiResponsibility 7 Impact/Issue Documents Implementation Supervision

prevent his workmen or any other personsfrom removing and damagingany sucharticle or thing and shall, immediatelyupon discoverythereof and before removalacquaint the Engineerof such discoveryand carry out the Engineer'sinstructions for dealing with the same, awaiting which all work shall be stopped 100m all directionsfrom the site of discovery. The Engineershall seekdirection from the ArchaeologicalSociety of India (ASI) before instructing the Contractorto recommencework on the site. Provision,replacement, restoration of bus shelters Design inclusiveof bus bays completewith seating requirement Entre ProjectCorndor, C.1.52 arrangement,infrastructure, etc., if any, as per designs DPR Typical designs During Engineer, Roadside shall be taken up. of roadsideamenities ConDruction Contractor PIU,MPWD. Amenities The design layout drawingsand specificationsof the are provided in the various roadsideamenities shall be as per the DPRo engineeringdesign. C.1.53 Road furniture including footpaths, railings,storm water Design RoadFurniture drains, crash barrier, traffic signs,speed zone signs, requirement pavementmarkers and any other such items will be At locationsas per the providedas per design given in the Bid Documents. detailed design. During Contractor Engineer, PIU, Intersections, rotaries, traffic islands,roadside Construction protection and other structures or furniture shall be Design constructed,complete with the landscapeelements as requirement ______per landscapestrategy.. C.1.54 For preservationof the waterfalls, no cutting shall be Design During Water-falls carried out along stretchesidentified during project requirement Construction Contractor Engineer, PIU preparation. MPWD. The detailed designsof measuresenvisaged at the At the locations water-falls identified for enhancementhave been mentionedin Appendix prepared and shall be implementedfully. Eachlocation 12. has been specifiedand the recommendedtreatment

Revised by Lea Associates 29 October 2001 (Original Documentby lCT, CES, LBII ------m -

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

Environmental 6 Referenceto Responsibility Mitigation Measures Contract Location8 Time Frame9 I m p Supervision Impact/Issue Documents7 Implementation Supervision

elaborated in the sketchesattached at the end of this document.

C.1.55 In additionto the compensatoryafforestation being Project All along the corridor During NGOs,VCs T Roadside carried out by the State Forest Department,tree Requirement construction > Engineer,PIU landscape plantation alongthe valley side slopesshall be carried MPWD,State out all alongthe corridor. As per the landscape Forest A total of 1,00,000 saplingsshall need to be planted. strategy Department The plantationto be carried out on a grid not larger than 6 x 6m, along free lands and lands belongingto NGOs,village councilsand unclassifiedforest lands, after due consultationwith the relevant stakeholders. 0 1.: OperationStage~

0.1.1 Silt fencing, Oil & Greasetraps, etc. shall be provided at At sensitivewater sensitivewater bodiesto ensure that the water quality bodiesidentified in Waterquality is not impaired due to contaminantsfrom road run-off. Project 6. Asndix tper PIU, MPWDand/or P MPWD to road run-off Monitoringshall be carried out as specifiedin the As specified in the Monitoringplan monitoring plan 0.1.2 _ at Contamination Contingencyplans to be in place for cleaningup of State and Sector FlyingSquad of the of Soiland spills of oil, fuel and toxic chemicals. Project Entire Project corridor. Levelis Motor Vehicles Motor Vehicles Water Spill of oil, fuel and automobileservicing units without requirement expectedv to be Department. Inspector. Resourcesfrom adequate disposalsystems in place to be discouraged. developed. SpillsAccidents devloed 01.3 Dependingon the level of congestionand traffic Traffic and hazards,traffic managementplans will be prepared. All along the Project PIU,MPWD,Local AccidentSafety Traffic control measuresincluding speed limits to be Project 'd d Through Government Bodies, PIU,MPWD, enforced strictly. requirement corrnior and Operation Stage. Development PIU,MPWD. Roadcontrol width to be enforced. Localgovernment Authorities. bodies and developmentauthorities will be encouraged

Revised by Lea Associates 30 October 2001 (OriginalDocument by ICT, CES, LBII mm- m - - mm - - -m- - m mm

MizoramState RoadsProject- PhaseI Environmental ManagementPlan for P-IA

Referenceto Responsibility 8 EnvIronmental MitigationMeasures6 Contract Location TirmeFrame 9' mieto Supervisio Impact/ssue Documents7 Implementation Supervision to control buildingdevelopment along the highway. Furtherencroachment and squatting on the public RoW will be discouraged. 01.4 Compliancewith the HazardousWastes (Management Accidents and Handling)Rules, 1989 including: involving For deliveryof hazardoussubstances, permit license, Hazardous driving licenseand guidancelicense will be required. Hazardous Fr k Materials Publicsecurity, transportation and fire fighting wastes All along the Project raew or PIU, MPWD, departmentswill designatea specialroute for vehicles (Management corridor and During Early VehiclesDepartment. Motor Vehicles delivering hazardousmaterial. Thesevehicles will only and Handling) surrounding areas OperationStage. Department. be harbouredat designatedparking lots. Rules,1989. In caseof spill of hazardousmaterials, the relevant departmentswill be intimated at once to dealwith it with the spill contingencyplan. 0.1.5 Conservationmeasures in the biodiversityrich areas Project At locations identified As perthe Institution/NGO PIU, MPWD Biodiversity include the contributed restriction of accessto these. requirement in Appendix 13 monitoring plan selectedby PIU, MPWD Monitoring by way of transectsat locationsidentified will provide important feedbackfor this and other such projects. PIU, MPWD No developmentshall be allowed along the short Between chainage During the VillageCouncils realignmenton the valley side in a stretch extending km15.816 and lifetime of the 200m on both sidesof the short realignmentstretch km16.011 project near Falkawnvillage.

0.1.6 The openingsof culvertsaround Aibawk, where Project At locations identified Everymonsoon PIU, MPWD PIU, MPWD Fauna Pangolinhas been sighted, shall be kept clean. requirement in Appendix-11. during operation stage. __ 0.1.7 Monitoringof land slide locations in collaborationwith Project At locations identified All year round PIU, MPWD& Aizawl PIU, MPWD Landslideson AizawlUniversity to determine locationsand extent of requirement in conjunction with university cut faces of the occurrenceof landslides Aizawl University hills.

Revised by Lea Associates 31 October 2001 (Original Do6umentby ICT, CES, LBII MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

1.5 REPORTINGSYSTEM Reportingsystem provides the necessaryfeedback for projectmanagement to ensurequality of the works and that the programis on schedule.The rationalefor a reportingsystem is I based on accountabilityto ensure that the measuresproposed as part of the Environmental ManagementPlan get implementedin the project. | The reporting system will operate linearly with the contractor reporting to the Supervision Consultant,who in turn shall report to the PIU.All reporting by the contractor and Supervision Consultantshall be on a quarterly basis.The PIU shall be responsiblefor preparingtargets for each of the identified EMP activities. All subsequent reporting by the contractor shall be monitored as per these targets set by the PIU before the contractorsmove on to the site. The I reporting by the Contractor will be a monthly report like report of progresson construction and will form the basis for monitoring by the PIU, either by its own EnvironmentalEngineer/s or the EnvironmentalSpecialist hired by the SupervisionConsultant. The monitoring and the subsequentreporting would include: : Monitoringof facilitiesat constructioncamps I . Monitoringof air, noise,soil and water parameters including silt load * Monitoringof survivalrate of treesplanted on valleyslopes * Monitoringof cleaningof drainsand water bodies * Monitoringfor biodiversity- protectionmeasures during construction phase Mmonitoring of bio-engineeringmeasures suggested I Table 4: Desired Monitoring and Reporting Processand Responsibilities Contractor SupervisionConsultant ProjectImplementation World Bank ______(SC) Unit (PIU) (WB) Fomat Item Implementati Oversee/Field H ~~~~~~~No.~ onand SprionReporting to Copiac Reportto Deid { Reportington to Suvistn Monitonng Ws Supervision ____~~~~~SC ___nit_ _ _ _ CONSTRUCTIONPHASE Monitorng of C1 constructon site and Beforetart of Quarterly Quarterly Halfyearly |zconstruction camp -Q Targetsheet for Asrequired AfterMonitofng Ater Halfyeary PollutionMonitoring Monitoring

l C3 aragetsheet for Monthly uarterly Quarterly Halfyearly Yearly

Targetsheet for C4 monitoringof cleaning Monthly Monthly Quarterly Halfyearly Yearly waterbodies * ~~~~~~~~Targetsheet for C monitornga bio- Beforestart of Quarterly Quarterly As required HalfyeaHy Yearly work * _ ,diversity *l OPERATIONPHASE - Targetsheet for Ae Onceafter 3 01 survivalreporting of Quarterly After earsof endof roadsideplantation monitonngconstruction Targetsheet for A 02 monitoringof cleaning Quarterly monitorngoperaion phase water bodies/culverts monitonng operaton phase

Revised by Lea Associates 32 October 2001 I (Original Document by ICT, CES, LBII MizoramState Roads Project - PhaseI EnvironmentalManagement Plan for P-IA

The reporting formats are annexedto this plan as Appendix 13.

I 1.6 INSTITUTIONAL ARRANGEMENTS The MSRPhas been initiated and is being carried out by the Public Works Department. The PWDthrough the Engineer- in - chief, is responsiblefor the effective implementationof the project activities. To carry out the project prioritisation, and to design for the various improvementsthat are proposed, the PWD has appointed international consultants as the Project Co-ordinatingConsultants (PCC) for the project. To effectively oversee the project preparationand to ensurethe timely implementationof the project, a ProjectImplementation Unit (PIU) has been established.The Project Director heads the Project ImplementationUnit (PIU), which at present includes 3 Executive Engineers, looking into the Procurement, Environment and Social Aspects. Each of these executive engineers are assisted by an Assistantengineer for carrying out their responsibilities.The PIUis expectedto play a key role in implementationof the project including the overall control of constructionactivities and implementationof contracts. During the implementationof MSRP,the PIU will be assisted by a SupervisionConsultant I procured through International Competitive Bidding. The SC will assume the role of the Engineer and ensure construction in an environmentally sound manner through their EnvironmentalSpecialist. The monitoring of ConstructionActivities by the PIU will be carried out in conjunction with the Mizoram Pollution Control Board Officials for the pollution component (Air, Water, Noise). For the implementationof R&Ractivities, & local NGOwill be procured. The roles and responsibilities of the various individuals/agencies responsible for the I implementationof the EnvironmentalProvisions have been worked out and detailed terms of referenceworked out for: * EnvironmentalEngineer of the PIU * AssistantEnvironmental Engineer of the PIU * EnvironmentalSpecialist - SupervisionConsultant I . Non-GovernmentalOrganisations - responsible for maintenanceof the plantationon the valleyside * Environmentalspecialist of the QualityAssurance Consultant | EnvironmentalEngineer of the Contractor.

I 1.7 TRAINING

1.7.1 NEED FOR TRAINING The EnvironmentalCell of the PIU is alreadyin place. However,the lack of environmentaland social expertiseand sensitivity of the PWD,though has been mitigated to a certainextent due to the exposure to the preparation of the EnvironmentalAssessments for the MSRP,is a matter of concern.This deficiencyshould be mitigated as soon as possibleto enablethe PWD in integrating the social and environmental issues in its day-to-day operation and in I internalising the environmentaland socialissues in the future road developmentprojects. To Revised by Lea Associates 33 October2001 | (OriginalDocument by ICT,CES, LBII MizoramState Roads Project - PhaseI EnvironmentalManagement Plan for P-IA

achievethis goal,the EnvironmentalCell at the PIU,need to be trainedon roaddevelopment andenvironment management and the effectiveimplementation of the environmentalissues.

1.7.2 TARGETSOF PROPOSEDTRAINING | The trainingprogramme should equip the membersof the Environmentalcell to implement and supervisethe EMPand exposesenior members of the PWDto environmentaland social issuesassociated with the highwayprojects. Such a groupof seniorstaff canthen be given the responsibilityof activedissemination of the cultureof environmental/socialconsciousness andethics within the restof the organisation. Oncethe staff of the EnvironmentalCell havereceived training and havegained experience throughthe implementationof the EMP,they should be readyto resumeleadership role within the PWD in providingtraining and in implementingfuture projects. In order to disseminateenvironmental experience gained by the PWD,each staff wouldbe requiredto maintaingood recordsand preparedissemination notes on specificissues and problems encounteredand resolved,and howthe experiencegained could be integratedin future road projects.Competent members of the PWDshould be offeredadditional environmental training andshould be encouragedto train otherstaff. a 1.7.3 TRAININGCOMPONENTS The environmentaltraining aspects of the Environmentalstaff of the PIUshould encompass * the following: * Understandingof the relevant environmental regulations and their application to theproject. * Environmentalmanagement practices in hillroads upgradation and maintenance | Mainimpacts of theproject on the environment. * Mitigationmeasures as givenin the EMPand their implementationthrough incorporation in the design,construction supervision and monitoring. I . Dutiesand responsibilities of the Contractors,Supervisor Engineers, Supervision Consultants and the PIU. : Public/communityconsultation and its roleduring the implementation of the project. I . Liaisonwith other departments and relevant agencies (such as Forestry). * Supervisionof the implementationof the EMPand social issues during construction and operation. Resolutionof environmental and social issues and their reporting. * . Monitoringduring construction and operation. * Weekly,monthly and quarterly report preparations and submission. 3 . Preparationof dissemination notes, holding of workshops, and training of otherstaff in PWD. The trainingmodules to be workedout for the projectneed to be of relevanceto the specific contextof the roadsin Mizoram,focussing on the followingissues: * * Conservationof biodiversity * Slopestability and vulnerability to landslides Sitingcriteria for identificationof dumping sites * Harnessingwater resources, including rain water harvesting * Conceptsof bio-engineering. * The trainingmodules suggested are given in the Table-5. Revisedby Lea Associates 34 October2001 | (OriginalDocument by ICT,CES, LBII I~~~~~~~~~~~~~~MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

Table 5: TrainingModules for EnvironmentalManagement Training ~~~~~~~~~~EnvironmentalAspects TrainingConducting lRecipients Training Mode of Training to be coveredtraining Agency No. ~~~~~~~~~~~~module I Environmentalstaff of LectureSystem Environmentaloverview EnvironmentalSpecialist, "Environmentaland Social Workshops EnvironmentalRegulations Supervisionconsultant * ManagementCell". GroupDiscussion and Acts AssociatedNGOs in Shortterm trainingcourse Environmentalissues implementationand PIU associatedwith hill road staff associatedwith projects constructionsupervision Environmental managementPlan Environmentallysound constructionmanagement Planningfor environmental sustainableoperation of hill roads Longterm environmental issuesin roadmanagement 2 All PIUstaff construction Seminar Environmentaloverview EnvironmentalSpecialist, super-visionconsultant and Workshop EnvironmentalImpact Supervisionconsultant contractors Lectures Assessment Environmental ManagementPlan Implementation EnvironmentalRegulations and Acts Environmentalpollution _ associatedwith road projects Environmentallysound constructionmanagement RoadProjects and EnvironmentalIssues

3 All PIUstaff and Executve Shortterm trainingcourses Environmentaloverview EnvironmentalSpecialist, Engineersand PWD Visit to casestudies EnvironmentalRegulations Supervisionconsultant, officialsassociated with the Seminar and Acts EnvironmentalCell, PIU projectroutes EnvironmentalPollution Roadprojects and environmentalissues I _ EMPfor roadprojects 4 CollaboratingGovernment AudioVisual EnvironmentalOverview EnvironmentalCell of PIU Agenciessuch as Pollution Communication EnvironmentalRegulabons and PCCConsultant ControlBoard, Traffic and InformatonTraining and Acts TransportDepartments, EnvironmentalPollubon State ForestDepartment etc. andall staff of PWD

5S All staffof PIUentrusted Shortterm trainingcourse Theoreticalcourse to Extemalagency. with environmentalrelated environmentalimpact matters assessmentand procedures. EnvironmentalRegulabons, Actsand Clearance procedures. Environmentaldata acquisitionand monitoring analysis. Handson trainingon compliancemonitoring and operationstaqe monitoring. 7 PIU Stafffor EnvironmentalVisits to casestudy areas Bio-EngineeringMethods EnvironmentalSpecialist, relatedmatters and expertlectures Water Harvesting Supervisionconsultant Techniques BiodiversityPreservation Disposalof Construction *______Waste

Revised by Lea Associates 35 October 2001 (Original Document by ICT, CES, LBII MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

1 1.7.4 LOGISTICAL SUPPORT REQUIRED The various items that need to be procuredfor the EnvironmentalCell are listed below: Ownequipments for monitoringnoise levels viz. portablesound level meter, water sampling kit etc. * One4-wheel drive vehicle exclusively for the EnvironmentalCell | Equipmentsas a DigitalCamera and adequatecomputing facilities to allowthe documentationunit to be self-sufficientincluding the latestversion of GIS softwaresuch as ARCInfo, Mapinfoand Idrisi etc. In additionthey shouldhave access to one licensedcopy of the latestversion of the softwareuseful for environmentalwing. These could include Caline (for air pollutionmodeling from traffic pollution),Sound 32 (for traffic noise) and a fugacity-basedmodel (for predictingthe behaviourof volatile/hazardousmaterial that mightspill on the road). * A well-stockedlibrary with booksand manuals related to environmentalimpacts of infrastructurein generaland roads in particular,would be an advantage.

I 1.8 ENVIRONMENTALMONITORING PLAN The purpose of the monitoring programme is to ensure that the envisagedpurpose of the I project are achieved and result in desired benefits to the target population. To ensure the effective implementationof the EMP,it is essentialthat an effective monitoringprogramme be designed and carried out. The environmental monitoring programme provides such information on which managementdecision may be taken during constructionand operational phases. It provides basis for evaluating the efficiency of mitigation and enhancement measuresand suggest further actionsthat need to be taken to achievethe desiredeffect. The monitoring includes: | . Visualobservations; * Selectionof environmentalparameters at specificlocations; | Samplingand regular testing of theseparameters.

1.8.1 OBJECTIVES The objectives of the environmentalmonitoring programmeare: * Evaluationof the efficiencyof mitigationand enhancementmeasures; * Updatingof the actionsand impactsof baselinedata; * Adoptionof additionalmitigation measures if the presentmeasures are insufficient; * Generatingthe data, which may be incorporatedin environmentalmanagement plan in future projects.

I 1.8.2 METHODOLOGY Monitoringmethodology covers the following key aspects: I * Componentsto be monitored; Parametersfor monitoringof the abovecomponents; * Monitoringfrequency; Monitoringstandards; * Responsibilitiesfor monitoring; * Directresponsibility, I * Overallresponsibility; Revised by Lea Associates 36 October2001 | (OriginalDocument by ICT, CES, LBII MizoramState Roads Project - PhaseI EnvironmentalManagement Plan for P-IA

I * Monitoring costs. Environmentalmonitoring of the parameters involved and the threshold limits specified are discussedbelow.

| 1.8.3 AMBIENTAIR QUALITY(AAQ) MONrTORING Ambient air quality parameters recommendedfor road transportation developments are 3 RespirableParticulate Matter (RPM), SuspendedParticulate Matter (SPM), Carbon Monoxide (CO), Oxides of Nitrogen (NOx), Hydro-Carbons(HC), Sulphur Dioxide (SO2) and Lead (Pb). These are to be monitored at designated locations starting from the commencementof I constructionactivity. Data should be generated over three days at all identified locations in accordanceto the National Ambient Air Quality Standards (Table-6). The location, duration and the pollution parametersto be monitored and the responsibleinstitutional arrangements are detailed out in the EnvironmentalMonitoring Plan. Table 6: National Ambient Air Quality Standards Pollutants Time Sensitiv Industrial Residential Method of measurement Weighted e Area Rural &other Method_of_measurement 3 3 SulphurDioxide (SO2) Annual* 15Pg/m 80 pg/mr 60 gg/M ImprovedWest and Gaeke ______~method 24 hours"* 30pg/r 3 120pg/r 3 pg/rg/rn3 Ultravioletfluorescence Oxidesof Nitrogen Annual& 15pg/r 3 80 ,'m 65 3 Jg/rJacoband Hochheiser 3 (NOx) modified(Na-Arsenite 3 3 3 24 hours** 30Fig/m 120 jg/M 91 lig/M Gas phase Chemiluminescence 3 CarbonMonoxide (CO) 8 hours** 1000 5000pgfm 2000pg/M 3 Nondispersive infrared g9/rn3 spectroscopy 1 hour 2000 1000gMi;3 4000pg/m 3 pg/rn3 d75gm AAMehd2horafr Lead(Pb) Annual* 0.50 1.0i7l 0.75pg/rn 3 MS Method24 hours after 3 Cg/M _ sampling using EPM 20000 3 24hours** 0.75 1.5pg/mr 1.00gg/m 3 or equivalentfilter paper RespirableParticulate Annual* 50 Pg/rM3 120[g/m 60plg/m 3

(RPM)-Size less than 24 hours** 75 pg/M3 10g/m3 100 pg/M 3

10pi.m ____flow_____rate Average______not____ less__ SuspendedParticulate Annual* 70pg/rm 3 60pg/m 140pLg/M 3 Averageflow rate not less Matter(SPM) 24hours** 100 500IL/rn 200pg/r 3 than 1.1cu.m / minute

Source Anon 1996-97, National Ambient Air Quality Monitoring Series NAQMS/a/1996-97, Central Pollution Control Board, Delhi.

*AverageArithmetic meanof minimum 104 measurementin a year taken for a week 24 hourly at uniform interval. I **24 hourly/8 hourly valuesshould meet 98 percentof the timein a year

I 1.8.4 WATERQUALITY MONITORING The physicaland chemical parametersrecommended for analysisof water quality relevant to road development projects are pH, total solids, total dissolvedsolids, total suspendedsolids, oil and grease, COD, chloride, lead, zinc and cadmium. The location, duration and the pollution parameters to be monitored and the responsible institutional arrangements are detailed in the EnvironmentalMonitoring Plan. The monitoring of the water quality is to be Revisedby LeaAssociates 37 October2001 | (Original Documentby ICT,CES, LBII MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

I carried out at all identified locations in accordance to the Indian Standard Drinking Water Specification - IS 10500: 1991 (stated in Table-7)

Table-7:Indian StandardDrinking Water Specification-IS10500:1991 lRequiremeI Undesirable Effect Permissible Limit Methods of I ~ No.~~Si. SubstanteoristicSubstance or ntesirbnt Outside the in the Absence of Test (Ref. To Remarks No. ChaLracteristic (Desiramble Desirable Limit Alternate Source IS) I Essential Characteristics 1 Colour,Hazen 5 Above 5, consumer 25 3025 (Part 4) Extendedto 25 only units, Max. acceptancedecreases 1983 if toxic substances are not suspected, in absenceof alternatesources 2 Odour Unobjection - 3025(Parts a) Test cold and able 5):1984 when heated ______b) Test at several dilutions 3 Taste Agreeable - 3025 (Part 7 Test to be I and8) conductedonly after 1984 safetyhas been established 4 TurbidityNTU, 5 Above5, consumer 10 3025(Part 10) Max. acceptancedecreases 1984 5 PhValue 6.5 to 8.5 Beyondthis range, the No relaxation 3025(Part 11) waterwill affectthe 1984 mucousmembrane and/orwater supply system 6 Totalhardness 300 Encrustationin water 600 3025(Part 21) (as CaCO3) MG/I, supplystructure and 1983 Max adverseeffects on domesticuse 7 Iron (as Fe) 0.3 Beyondthis limit 1 32of 3025: mg/i, Max taste/appearanceare 1964 affected,has adverse effecton domesticuses andwater supply structures,and promotesiron bacteria 8 Chlorides(as Ca) 250 Beyondthis limit,taste, 1000 3025(Part 32) mg/i, Max corrosionand 1988 palatabilityare affected 9 Residual,free 0.2 - 3025 (Part 26) To be applicable chlorine,mg/i, 1986 onlywhen water is MMin chlorinated.Tested at consumerend. Whenprotection againstviral infectionis required, it shouldbe Min 0.5 *______mg/l DesirableCharacteristics 1 Dissolvedsolids 500 Beyondthis palatability2000 3025(Part 16) mg/I, Max decreasesand may 1984 U i causegastro intestinal * l ~~~~~~~~~~~~~~irritation 2 Calcium(as Ca) 75 Encrustationin water 200 3025(Part 40) mg/i, Max supplystructure and 1991 adverseeffects on domesticuse Revisedby LeaAssociates 38 October2001 (OriginalDocument by ICT,CES, LBII MizoramState Roads Project - PhaseI EnvironmentalManagement Plan for P-IA

Requireme Undesirable Effect Permissible Limit Methods of SN. Substance or nt Outside the in the Absence of Test (Ref. To Remarks No. Characteristic (Desirable Desirable Limit Alternate Source IS)

3 Magnesium(as 30 Encrustationto water 100 16, 33, 34 of Mg), mgl/, Max supplystructure and IS 3025: 1964 adverseeffects on ______domesticuse 4 Copper(as Cu) 0.05 Astringenttaste, 1.5 36 of 3025: mg/i, Max discolorationand 1964 1 corrosionof pipes, fitting and utensilswill be causedbeyond this 5 Manganese(as 0.1 Beyondthis limit 0.3 35 of 3025: * Mn) mg/i, Max taste/appearanceare 1964 affected, has adverse effects on domestic usesand water supply ______structures 6 Sulphate(as 200 200 Beyondthis causes 400 3025 (Part 24) Maybe extendedup S04) mg/I, Max gastrointestinal 1986 to 400 provided (as I irritation when Mg) does not exceed magnesiumor sodium 30 are present 7 Nitrate (as NO2) 45 Beyondthis, may cause 100 3025 (Part 34) - mg/1, Max methaemoglobinemia 1988 8 Fluoride(as F) 1 Fluoridemay be kept as 1.5 23 of 3025: - mg/i, Max low as possible.High 1964 I fluoride maycause fluorosis 9 Phenolic 0.001 Beyondthis, it may 0.002 54 of 3025: - compounds(As causeobjectionable 1964 I C6H50H)mg/I, taste and odour Max 10 Mercury (as Hg) 0.001 Beyondthis, the water No relaxation (see Note) To be tested when mg/I, Max becomestoxic Mercury ion pollution is analyser suspected 11 Cadmium(as Cd), 0.01 Beyondthis, the water No relaxation (Seenote) To be tested when mg/1, Max becomestoxic pollution is suspected 12 Selenium(as Se), 0.01 Beyondthis, the water No relaxation 28 of 3025: To be tested when mg/I, Max becomestoxic 1964 pollution is suspected * 13 Arsenic(As As) 0.05 Beyondthis, the water No relaxation 3025 (Part 37) To be tested when mg/I, max becomestoxic 1988 pollution is ~suspected l 14 Cyanide(As CN), 0.05 Beyondthis limit, the No relaxation 3025 (Part 27) To be tested when mg/i, Max water becomestoxic 1986 pollution is ~suspected 15 Lead(as Pb), 0.05 Beyondthis limit, the No relaxation (see note) To be tested when C mg/i, Max water becomestoxic pollution is ______suspected 16 Zinc (As Zn). 5 Beyondthis limit it can 15 39 of 3025: To be tested when Mg/l, Max causeastringent taste 1964) pollution is and an opalescencein suspected water 17 Anionic 0.2 Beyondthis limit it can I Methylene- To be tested when

__detergents (As causea light froth in blue extraction pollution is _ MBAS)m /1, Max water method suspected 18 Chromium(As 0.05 May be carcinogenic No relaxation 38 of 3025: To be tested when Cr5+) mg/i, Max abovethis limit 1964 pollution is

_~ ~ ~~ =______~_____ suspected Revisedby Lea Associates 39 October2001 (OriginalDocument by ICT, CES, LBII MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA l Requireme Undesirable Effect Permissible Limit Methods of No. Characteristic (Desirable Outside the in the Absence of Test (Ref. To Remarks Limit) Desirable Limit Alternate Source IS) 19 Poly nuclear May be carcinogenic aromatic abovethis limit hydrocarbons(as PAH) 9/1, Max . 20 Mineraloil mg/l, t0.01 Beyondthis limit 0.03 Gas - Max undesirabletaste and Chromatograp odour after chlorination hic method take place 21 Pesticidesmg/i, lAbsent Toxic 0.001 - Max j 22 Radioactivematerials: 58 of _~~~~~ 3025:01964 23 a) Alpha emitters 0.1 - Bq/1, Max I 24 Beta emiters 1 - pci/l, Max 25 Aluminium(as 200 Beyondthis limit taste 600 13 of I ___ Al), mg/I, Max becomesunpleasant 3025:1964 26 Aluminium(as 0.03 Cumulativeeffect is 0.2 31 of 3025: Al), mg/I, Max reportedto cause 1964 dementia 27 Boron, mgil, 1 5 29 of 3025: Max 1964 I Source:Indian Standard Drinking Water Speciflcatlon-1510500:1991

1.8.5 NOISELEVELS MONrTORING I The measurementsfor monitoring noiselevels would be carried out at all designatedlocations in accordanceto the Ambient NoiseStandards formulated by Central Pollution Control Board (CPCB)in 1989 (refer Table-8) Sound pressure levels would be monitored on twenty-four hour basis. Noise should be recorded at an "A" weighted frequency using a " slow time responsemode" of the measuringinstrument. The location, duration and the noise pollution I parametersto be monitored and the responsibleinstitutional arrangementsare detailed in the EnvironmentalMonitoring Plan (Table-8). Table 8: NoiseLevel Standards (CPCB) I Km. Noise level for Noise level for Day Night Time Industrial area 75 70 Commercial 65 55 Residentialarea 55 45 Silencezone 50 40 Daytime - 6.00 am - 9.00 pm (15 hours) Night bme - 9.00 pm - 6.00 am (9 hours) The monitoring plan along with the environmental parameters and the time frame is I presentedin the Table 1.6, environmentalmonitoring plan.

11.9 MONITORING PLAN The monitoring plan for the various performanceindicators of the project in the construction I and operation stages is summarisedin the Table 9. Revised by Lea Associates 40 October2001 | (OriginalDocument by ICT, CES, LBII - - m - - - - - m - m ------

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

Table 9: Environmental Monitoring Plan Env. Project Special MONITORING Institutionalresponsibility component Stage Parameters Guidance Standards Location Frequency Duration Implementation Supervision Highvolume samplerto be located50 m Al fromthe plantAi in the ~~~(Prevention Onea Continuous ContractorEnier Construction SPM,RSPM, SOC tVei andC2ntro of Hot t pantthing Once a 4 hours/or throughapproved Pngieer stage NOx,CO HC downwind anPonltrol)of lHotmi ln/acigmonth for for 1 full monitoring PIU PWD miecthod method Ue Rules,1994CPCB, t,o years workingday agency specifiedby CPCBfor Air analysis HighVolume Samplerto be located40 m Air fromthe Cotnouiotrco Construction SPM,RSPM earthworkssite andControi of Stretchof the roadwhere Onceevery Construction SPM,RSPM downwind Pnotolluton) constructonis in progress monthfor 2 2 f4ourshoursfullronitappoving or throughapprved P113,Engineer,PWD stage direction.Use Rules,CPCB, site years workingday agency method 19 specifiedby 1994 CPCBfor analysis Grabsample 1.RiverVanva collectedfrom 2. RiverChar Endof sourceand 3. 5 waterfallsidentfied summer Construction pH,BOD, COD, analyseas per Waterquality for beforethe Contractor WaterQuality stageo TDS,TSS, DO, Oil Standard standardsby conservation/enhancemen onsetof throughapproved Engineer, stage ~~&Grease and Pb Methodsfor CPCB t.monsoon mnonitoring PIU,PWD Examinationof 4. Swampsat ch. Km59.6 everyyear agency Waterand and86.7 for 3 years Wastewater Grabsample 1. RiverVanva collectedfrom 2. RiverChar Endof sourceand 3. 5 waterfallsidentified summer Operation BOD,COD,TDS,TS analys as per Waterquality for beforethe stage S, DO,Pb, Oiland Standard standardsby conservation/enhancemen onsettof PIU PWD stage , DO,b, Oiland. Methodsfor CPCB t. monsoonin Grease. Examinationof 4. Swampsat ch. Km59.6 2004,2006 Waterand and86.7 and2010 Wastewater

Revised by Lea Associates 41 October 2001 (Original Documentby ICT, CES, LBII ------

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

Env. Project Special MONITORING Institutional responsibility component Stage Parameters Guidance Standards Location Frequency Duration Implementation Supervision Flooding locationsto be identifiedand Waterquality chokeddrains, standardsof Thricein Flooingand waterbodies CPBadmonsoon Cleaningof siltatoiognd cleaningshall Allalong the corridor + mleaonso drains/waterFloodingad slainndbeudebrlsdsgoin CPbheegneto the and landslidesielqb locationmosnPIPW andpost- I t P bodies subjectto satisfactionof seasonsof debrisdisposal tenier2004, 2006 should te andg2010. monitored (PWD)an200 undercleaning operations Freefield at I Free field at 1 ~~~~~~~~Oncene everyvr Readingsbetaken atto m fromthe month 1betaken at Noiselevels on dB equipment Noise (max) for t15seconds t onuhaptov Engineer, (A) scale woeq noismen standardsby At equipmentyards twoyears, inutesvlo mhonitapporing PIU,MPWD whosenoiseCPCB as ~~~~~~~~~required1 iue nntrn levelsare being everyhour agency determined. enginee andthen SoilConstruction Erosion waternengineeriPWDn29eerter_ In mnoo_osltn_I____ averaged. Noiselevels Construct Equivalent rives t RevisedbyLeaAsstciagesnoise levels Reag t usingan Thricea betaken at Noiseevelson dB integrated Noise Asdirected by the yearfor 2 15 seconds ContractorEnier Noislevls o dB noiselevel standardsby Engineer(At maximum5 yearsduring intervalfor throughapproved EnIneer,D (A) scale meterkept at a CPCB locations) the 15 minutes monitoring PU W distanceof 15 construction everyhour agency from edgeof period, andthen pavement averaged. s~wampsat-chainage km Turbidityin Storm Asspecified 59.6to 59.65and km 86.7 Pre- by the t868monsoon SoilErosion Construction water engineerPWD 29 waterfallsIdentified in andpost- SupervisionPL stage Silt loadin ponds, / Water Apni10monsoon ConsultantPI watercourses quality 2 rves km 8.71an seasonsfor standards 297vrs(k0 8.11 n 2 years

Revised by Lea Associates 42 October 20-01 (Original Documentby lCT, CES, LBII ------m m------

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

Env. Project MONITORING Institutionalre ponsibility component Stage Parameters Special Standards Guidance Location Frequency Duration Implementation Supervision The parameters Monitoringof: mentionedare To the Construction 1. StorageArea further satisfactionof Quarterlyin Sitesand Construction 2. Drainage elaboratedin the PIUand At Storagearea and the Egne I,MW Construction Stage rangent the reporting the standards constructioncamps construction Engineer PIU,MPWD Camps 3.Sanitation in formatCl. givenin the ag Construction Theseare to be reporting Camps checkedfor form. adequacy. Comparison 1tm Bio-diersity Construction Quadrate withpre- At locationsselected by Qurely eautionamnieeeI,MW Bio-diversity Constage Speciesdiversity method project engineer Quarterly evaluhtionat Engineer PIU,MPWD situation Selectionof locationsas 1 t Bioengineering Operation Vegetationcover advisedby Geotechnical Q tine measures Stage (sq.m) personnelof Engineer Quarterly evaluationat Engineer PIU,MP\D eachsite Thestudy locationto be Monitoringof soil identifiedin Construction movementusing consultation At vulnerableland slide Fntsme Pachunga pegs/boltson cut with location Fotih esrmnUniversity EngineerGeo slopes Geotechnical Expertof Landslides Engineer Thestudy locationto be Monitoringof soil identifiedin Operation movementusing consultation At vulnerableland slide pegs/boltson cut with locationFotih Fortnight mesrenUvriyPWm time Pachunga PWD slopes Geotechnical Expertof Engineer _

Revised by Lea Associates 43 October 2001 (Original Documentby ICT, CES, LBII MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

| 1.10 ENVIRONMENTALMANAGEMENT- BUDGET The environmentalbudget for the variousenvironmental management measures proposed in the EMPis detailedin Table 10.There are severalother environmental issues that havebeen addressedas part of goodengineering practices, the costsfor whichhas been accounted for in the EngineeringCosts.

Ii 3 I l l I l

| Revisedby LeaAssociates 44 October2001 (OriginalDocument by ICT, CES, LBII 11------mm- -

Mizoram State RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

Table 10: Environmental Budget for Priority road IA COMPONENT STAGE ITEM Unit Unit Cost (INR)) QUANTITY TR) Mitigation/ Enhancement

AIR Construction Dust Management with sprinkling of water, covers for vehicles Km 0,000 Ctransportingconstruction material Covered in Engineering Costs Pre-construction Hand pumnp No. 25,000 26 ~ 50,000 ATER Ctt Water harvesting structures (suitable design to be finalized by Construction engineerbased on site conditions) No, As per design Covered in Contractor's Costs SOIL Construction urfing/Pitching sq. m. Covered in Engineering costs Operation Redevelopmentof Borrowareas sq.m. CULTURAL Pre-Construction Relocationof graves,church buildings No. Covered in R&IPDP Budget

FLORA Construction Compensatory afforestation, in accordance with Fores Lumpsum ConservationAct (1980) Additionaltree plantation along valley slopes No 15 1,00,00 15,00,00 MaintenanceGrant to local NGOs for ensuring survival No 20 1,00,000 20,00,000 CONSERVATION OF Construction Provisionof barbedwire fencing along Falkawn realignment m 54 400 21,600 BIODIVERSITY Mitigationdesigns for endangered plant species m 1000 5r 50,00 Constructionof a seriesof pipe culverts to avoid breedingground fo No 1 Covered in Engineering Costs kragon flies Provisionof additionalculverts for passageof ChinesePangolin No 5 Coveredin EngineeringCosts STABILITYOF SLOPES Construction Bioengineeringmneasures for protectionof slopes No. Lumpsum 20,00,00C ROADSIDEAMENITIES Pre-construction Constructionof bus shelters No As perdesign Coveredin EngineeringCosts Constructionof urinals No Asper design Coveredin EngineeringCosts ENVIRONMENTAL Construction Enhancementof water falls as per enhancementdesigns No. 2,00,000 5 10,00,00C ENHANCEMENTS ______I

(A) Mitigation I Enhancement Costs 7921600 Monitoring

Monitoringnear all hotmix plantlocations approved by the EngineerNo. of Samples 5000 for 3-sample36 1,80,00C AIR Construction t_ Monitoringat construction sites in tandem with construction No. of Samples 5000 for 3-sample3 6 1,80,00C

Construction At locations specified in the monitoringplan No. of Samples .5,000 27 1,35,00C WATER QUALITY . _. Operation At four locations specified in the MonitoringPlan No. of Samples 5,000 27 1,35,00C NOISEConstruction At equipmentyards as directedby the Engineer No.of Samples4,000 36 1,44,000

Revised by Lea Associates 45 October 2001 (Original Documentby ICT,CES, LBII m ------m m - - -

MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

COMPONENT STAGE ITEM Unit Unit Cost (INR)) QUANTITY Total Cost (INR) Operation At locationsof compensatoryplantation L.S 25,000 per year All along the corridor 75,00 Bio Engineering Construction Monitoringsurvival L.S. [ _ 3,00,00 Measures Operation Monitoringeffectiveness L.S. 2,00,00 Bio Diversity Construction Species Diversity L.S. 3,00,000 Monitoring Cost 16,49,00 Training & Mobilisation Constructionand 2,00 Training Operation As per modulesdeveloped for MSRP L.S 20,00,00 Erection of hoardings indicating the biological diversity, and sceni No. 4000 20 80,00 viewsalong the project route Monitoring of Landslide vulnerability along Project road, to b LS 300,00 Advocacy and polic O arriedout by Aizawl University LS.3_00_000 making Holding meetings for policy planning and subsequent revie meetingswith the Revenue Department,local representatives,town Year 1,00,000 3 3,00,00 planning authorities, NGOs, etc. regarding development control especiallyw.r.t biodiversitypreservation. _ _-

Administrative chargesConstruction Maintenance of vehicle with the Environmental Cell, Dat Month 50,000 36 18,00,00 includingLogistics orocessing, administrativesupport, stationery etc.

Vehicle Costs ne 4-wheeldrive vehicle (Gypsy)for the EnvironmentalCell No 5,00,000 1 5,00,00

Miscellaneousitems Digital Camerafor the EnvironmentalCell No 50,000 1 50,00

Portable sound level meter No 5,000 2 50,00

Training & Mobilisation Costs 50,80,00 Total Costs 1,46,50,600 Contingency@ 5% 7,32,530 TOTAL BUDGETED COSTS 1,53,83,000

Revised by Lea Associates 46 October 2001 (Original Documentby ICT, CES, LBII l MizoramState Roads Project - PhaseI EnvironmentalManagement Plan for P-IA l

| 1.11 SPECIFICATIONS FOR ENVIRONMENTAL MANAGEMENT WORKS

I 1.11A1CLEARINGAND GRUBBING All site clearanceworks shall be done as per section 200 of MoSTspecifications for Roadand Bridge Works.

1.11.2 EARTHWORK | All excavation, disposal, filling and related works shall be as per section 300 of MoST specificationsfor Roadand Bridge works.

1.11.3 MATERIALS | All materials used in environmentalenhancement works shall be as per section 1000 of MoST specificationsfor Roadand Bridge works.

I 1.11.4BRIcKSWORK All Brickwork including Laying, jointing finishing of joints, curing, scaffolding etc shall be as per shall be as per section 1300 of MOSTspecifications for Roadand Bridgeworks.

I Brick paving / Flooring The preparation of base concretefor laying bricks shall be as per section 409.3.3 and bricks paving shall be done as per clause409.3.4 in all respectsexcept that bricks shall be used.

1.11.5STONE WORK I All stone masonry work shall be as per section 1400 of MOSTspecifications for Road and Bridge works

1.11.6CONCRETEWORK All concretework includingsize and grading of material, admixtures, stackingof materialsetc shall be as per section 1700 of MOSTspecifications.

I 1.11.7CEMENT CONCRETETILE FLOORING/PAVING The base for laying the concreteflooring/paving, size of cementconcrete tiles/stone slab shall be shall be as per section 409 of MOSTspecification for Roadand Bridgeworks.

1.11.8FORMWORK All formwork shall be as per section 1500 of MOSTspecifications for Roadand Bridge works.

| Revisedby LeaAssociates 47 October2001 (OriginalDocument by ICT,CES, LBII MizoramState RoadsProject - PhaseI EnvironmentalManagement Plan for P-IA

1.11.9 CEMENTPLASTERING All cement plastering works and finishing of surfaces shall be done as per section 1312 of MOSTspecifications for Roadand Bridge works.

I 1.11.10 GABIONSTRUCTURES All Gabionworks shall be done as per section 705 of MOSTspecifications for Roadand Bridge | works. a) Footpaths | Materialand Constructionof Footpathsshall be as per section 409 of MOSTspecifications for Road and BridgeWorks.

* Cement Concrete Kerb And Channels Material and Constructionof all cement concrete Kerb and channel stones shall be as per section 408 of road MOSTspecifications for Road and Bridgeworks. i 1.11.11 RAIUNG Sectionfor the railing shall be square pipe section as per detailed drawings.The railing shall be as per section 808 of MOSTspecifications except that the railing section shall be square and as per the detailed drawing for the same. 3 Silt Fencing Materials The wire mesh and geotextile miraf shall be of approved standard and brand. The iron sectionsto be used as struts shall be of IS standard and free from rust, cracks etc. 3 Assemble The angles are to be assembledas per drawing and directions of supervisionengineer. The 3 mesh has to fixed with the frame after the geotextile miraf is fixed with the mesh. Fixing 3 The fencing shall be fixed at site in such a mannerthat the geotextilemiraf is placed next to the silt. l

| Revisedby LeaAssociates 48 October2001 (OriginalDocument by lCT. CES, LBII I I I I I I I I I I I ANNEXURES I I I I I I I I I I Mizoram State Roads Project - Phase I Annexures for P-IA

APPENDIX1 LIST OF COMMUNITY PROPERTIESTO BE RELOCATED

Hand Pumps Public Urinals Public Taps Bus Stops 3 Distance Distance Distance Distance * Chainage Direction from Chainage Direction from hdainagein hainag Dromrection from Proposed Proosed hanar eirdto Proposed CL CL CL- CL - 10.340 R 4.00 26.260 R 4.41 23.920 R 3.8E 23.913 L 4.89 *15.240 L 4.00 27.320 L 3.71 26.01C R 3.00 27.075 R 3.44 15.620 L 4.00 36.025 R 2.90 16.120 L 3.14 36.03G0 R 5.32 I 28.275 L 2.76 41.870 L 3.24 28.340 L 2.00 89.515 L 2.90 89.895 L 3.89 90.225 R 3.49 90.55 L 4.75 I

I

I I I

I Revised by Lea Associates 1October 2001 (Original Document by ICT, CES, LBII1 l Mizoram State Roads Project - Phase I Annexures for P-IA

APPENDIX: 2 APPROACHROADS TO BE RESTORED/PROVIDED

S.No Settlement Chainage Type of road

l ~~~~~1Melriat 10.450 Approach to) church 2 10.700 Melriat Village link road 3 11.450 pproachto Melriat High School 4 Kelsih 12.200 Kelsihvillage road l 5 Mullungthu 16.050 Approachroad to pastor quarters

6 Approach road to water point 7 before paramountgarden illageapproach road

8 _eepable track 9 Tachip 23.950 Footpathto village 10 Aibawk 25.140 Approachto communitycentre 11 26.300 Approachto animal husbandrydept ______U 12 26.400 Approachto forest department 13 27.000 Approachto rural development 14 Sateek 29.480 Villageapproach road 15 Damidai 33.150 Approachto Damidaifarm l 16 34.350 Approachroad to Damidaivillage 17 Lungsei 36.000 Approachto LungseiVillage 18 Thiak 41.150 Approachto Thiak 19 44.400 Approachroad to Thiak 20 Hmuifang 51.600 Approachroad 21 Chamring 54.500 Villageapproach road l I l

Revised by Lea Associates 2 October 2001 I (Original Document by ICT, CES, LBII l l Mizoram State Roads Project- Phase I Annexures for P-IA

APPENDIX-3 LIST OF RELIGIOUS PROPERTIESALONG PRIORITY CORRIDOR

I ChainageDirection Distance From ProposedCl 0.250 R 4.30 2.165 L 5.95 I 2.834 L 3.08 51.595 R 4.50 54.690 R 5.73 2.150 L 5.55 2.785 L 3.50 l I

Revised by Lea Associates 3 October 2001 (Original Document by ICT, CES, LBII l Mizoram State Roads Project - Phase 1 Annexures for P-IA l

APPENDIX 4 3 CHAINAGEAND CHARACTERISTICSOF BIO-RICH AREASTO BE PROTECTED:

SI.No Location Importance 1. Km 17.2-22.1 Chinesepangolin (Manis pentadactyla)-becoming a rare I km 14.00 (Falkawnvillage) speciesin the entire north east region km27-34 2. 36- 41.80 km (Lungsaito Densesemi-evergreen forest with characteristicspecies.

______Thiak) 3. 47.46-48.51km (before Higher degreeof canopyclosure and with rare plant species. Samsuito before Hmuifang) 4. 59.6-59.65 km. (near -Densegrowth of aquatic macrophytesand typical swamp Sialsuk) vegetation. -High invertebrateand amphibiandiversity I 5. 78.750-79.00km High aestheticand ecologicalidentity. (Waterfall near Sentezel stone quarry) I 6. 86.7 - 86.8 km (before Denseswamp forest with marsh area. Thenzawl 7. 97.00-97.100 km (Vanva Riparianvegetation and aquatic life. 9 River) 8. 82-98.4 km Pondsand swampsnear the road

l

I

Revisedby LeaAssociates 4 October2001 (OriginalDocument by [CT,CES, LBfl Annexure: L-1:

I ProposedCut Slopesalong Priority Road (PlA) The cut slopes have been recommendedbased on a GeomorphologicalAssessment of I the projectroute, wherein a Geologicalzoning was worked out. GeologicalZoning Criteria

Zone A: Vertical Rock cuts in relativelyunweathered bedrocks. If exposedsometimes has a potentialfor rock falls. They are of two broad modes: (i) MassiveBlock falls along joints/beddingplane; and, (ii) Laminated,interlaminated thinly bedded, highly weatheredfaces. They cause heaps of small sized weatheredrock elements. This may not pose any serious | blockage.

Zone B: Vertical Exposuresat specificJhoras/ Waterfalls at structurallydisturbed points particularlyon the shaded face of the mountain.They typicallyoccur at concave road * bends in between spurs on the sinusoidalroute of a hilly road. These would demand critical examinationof proper protection.In some cases, one may shift the road curve * outwardto provideadditional space for any occasionalrock fall withoutroad blockage.

Zone C: Cuts may be on partly weatheredrock and partly on scree materials.The top scree materialsare often cohesivein characterpermitting near vertical cute.

* Zone D: At some location cliff formationsare evident. Historicallythese are associated with structuraldisturbances and / or weatheringeffects on the unfavorablysteep planes | of weakness.

Zone E: Sloping Hill faces (steep to moderate)exhibits unconsolidated,non-cohesive scree materialshaving the potentialof sliding.

Zone F: Cuts in highly laterisedto partiallylaterised hummocky hill top materials.

Zone G: Locations specificallyidentified as structurally disturbed,with faulted weak zonesetc.

| Notes:

Slopeof cut above 5m (or 1Om in caseof no-problemhard rock) is to be smallerthan the slopes suggestedabove, by a degreeadequate for lesseningthe potentialoverburdens; or provideadequate benching.

1 The slopes are recommendedfor a cut height upto 5m in case of laterisedsoil. For hard rockswith tight joint planes,slope of 900 is recommendedfor a height of 1Om.

I l I

I MitigationMeasures Suggested Dependingon the practical classification,the type of solution is to be chosen.

* In the zoneswhere scree materialsare of incoherent character, non - cohesive, with vulnerable geometrical profile, special treatments in the None of known I solutionsand/ or improvisedlocal solutionsare to be adopted.Timber guards to hold or delaythe slides. * Use of Revetment on specific stretches; sometimes turtfier strengthenedwith I Retaining Walls (open pattern), Breast Walls being of Gravity type are often necessary. But In general, only Revetmentappears to be cost effectiveto arrest I delay/ avoid nearsurface long-term degeneration of the exposedmaterials. 0 All specificvulnerable points on scree / overburdenmaterials, are to be shieldedwith propertydesigned Cut-Off drains to avoid surface / near subsurface erosionfrom run-off & or nearsurface water-flows during high precipitation. i I

I I I Annexure: L-1 Identification of Geological Zones from the Field Data

ChairrageLandslides ~~~Geomorphologic-alCut Slope Proposed Recommended Chainage LandslIides Ge Zone by Consultants Cut Slope' AdditionalMeasures Suggested

9.700-10.160 Evicencesof scil fai ure afe noticed A(i) VerticalCut .750

10.160-10.200 C Vertical Cut <750 10.200-10.400 A(ii) Vertical Cut 83° 10.400-11.020 C Vertical Cut 76°-793 1 .320-11.050 A(ii) Vertical Cut 83° M.D50-11.1 - C VerticalCut 76°-793 _11150-11900 Alij Vertic41Cul 11.900-12.200 VerticalCut 763-790 12.200-13.400 Vu nerableto landslides B VerticalCut <750 *13400-14.900 - A(ii) VerticalCut 83f Joint planesare u.nfavourableand Rock stratahsa to be stabifised by one of *4.900-17.300 failure took placeat 16.3 A;ii) VerticalCut 750 the optionsprovided in the text 7.000-t7 S00 C VerticalCut 763-793 17.800-t7.550 A slidehas occured recently Ali) VerticalCut 83 Bancddramrs are to be provided 17.850-18120 Aii) VerticalCut <75 18.120-18.400 Ai Vertical t-1o 0750 Rock stratahas to be stabiiisedby one of _18.120-18.400 A(i) VerticalCut <75° theoptions providedirnthe text 18.400-18.700 C VerticalCut 78°-790 18.700-t9.250 . Aiil) VerticalCut 830 19.25C-20.800 C VerticalCut 76°-790 I 20.80C-21.000 A(ii) VericalCut 830 210OOG022.DOOflow Rocks and soil Alit) VerticalCut go0 Rock stratahas to be stabiised by one of 21.000-22.000 Rocksand soil fov A(ii) VerticalCut 90° the optionsprovided in the text

22.000-24.000 Rapid fbwge of soil debnsare A(ii) VerticalCut 830

Debrisflow (10-15mtrs) at places A(ii) VerticalCut 3 te cipbhnsp tovidedmithie lea I 24.000-26.500 are observedthopospoeinheex 26.500-27500 C Verical Cut 830

27.500-28.000 Alii) VerticalCut 900 29.400 A(i) 2_003100 A(i etclCtao Rock stratanas to be stabilisedby one of 28.000-31| .000 Alii ) VerticalCud 83° 'theoptions providedin the text 0 1.000-31.400 D Vertical Cut e75 Rock strata has to be stabilisedby one of 31.400-31.200 A(i) Vertical Cot 83° theoptions providedin the text 31.400-33.200 A(j) Vertical Cut 8~~ ~ ~~~~~~~~~~30Rock strt has to be stabilised by ore of 31 400-33.200- Afil VerticalCut '~~~~~~~~~~~~~~~~~heoptiona prvdMedin tire tent 33.200-34.000 Vertical Cut 76°0790

34.OO.35.025 0 A(i,) Verlical Cut 0750 Rock straLahas to be stabilised by one of 34000-35.025- Aiil VerticalCat ~~~~~~~~~~~~~~~~~~~~theopions providledin the text 35.025-35.075 A(ii) VerticalCut 76° 79° 35.075-3.000 A(i) VerticalCut 630 30 000-36.600 C Verlical Cut 76°-790 Lan(islide/rocklalalong the Major road protectionwol,s at krn.36.650. 36.600-38650 interfaceof rockof rock soil Verical Cut 76-79 to preventerson of roadsub-structure by juncture.The rocksare 00eassiveepre C ~~~~~~~~~compactdark shale. seepage

38.720-38.815 A slidehas occurredrecently for a C VerticalCut v750 Soilhas to be stabilisecd wdth of SOn 3 1400AVclCt750 Rock stratahas to be stabdilsedby oneof |30.815-41.400 A(i) Venical Cut <75° the oplionsprovided in thetext 41.400-41.500 Ain) VerticalCut 76°-79° 41 500-42.050 C VerticalCut 76o-79° 42.050-42.255 C VerticalCul 76°-79° 42 255-42.350 A( i) VerticalCua lo. 42.350-42600 C VerticalCut 760-790

42.600-42.825 - VerticaiCat 830 Rock strata',as lo be stabilisedby one of *_|_2.800-42.825_8_Vertical_Cut_83° the options providedin the text 42.825-430O0 C Vertical Cut 7S°-790 3 o Rock stratahas to 00 stabilisedby odneof 43r0043.125 A(ii) VerticalCut 83 the optionsprovided in the text

43.125,43.300 C VerticalCut 770-790 43.300-43.625 A(i) VerticalCut 830 43.625-44.025 D Vertical Cut 900 444025-45.200 C Vefticai Cot 76°0790

4520045.650 45 20(1-45~~~~~~~~~~650 ~~~~VerticalD VenicalCt83° Cat 50 theRock options strataprovidedhas to bein stabilised the text by one of 45665045.800 C Ventcal Cut 760.790 45.800-47.000 Slideat krr.45.950. due to loose soil A(ii) Ver cal Cut °- ° over the rock got dislodged 76 79 47.000-47.052 C VerticalCut 76°-790 47.052-47900 A(l) VerticalCut go. 47 500-48.650 C VerticalCut 760.790 48.650t48.830 A(r) VerticalCut 83° 84830-48880 C VerticalCut 76 -790 48.98049.100 Ali) Verical Cut 900 49.100-51 650 C Verical Cut 760.790 51.650-52000 A(ii) VerticalA_ Cut 830°______V 52.0052 2290 C 76°-79° Chainage Landslides Geomorphological Cut Slope Proposed Recommended Additional Measures Suggested ChainageLandslides ~~~~~~Zoneby Consultants Cut Slope' ______Rocks at km. 52.330are massiveand highly Rock fai ure, debnsfall along ith weatheredwith Jant planesinclining towards 0 52.250-52.500 rock. Rockfall is largeiyalong the jt D VerticalCut <75 the road andare verywide- Rock surface stab,hsatanhos to be taken up accordingto one of the optionsgiven in the text

52.500-52.700 C Vertical Cut 76°-79° *52.700-52.300 D Verlical Cut 830 Rock stratahas to be staoilisedby oneof 52.700-53.400 A Venical Cut the optionsprovided in the text 52.800-53.410 A0i1) VerticalCut 83° 53.410-54270 C VerticalCut 76°790 54.270-54.370 Atiil Vertical Cut 83° 54.370-55.420 C VerticalCut 770f79 * 55.420-55 550 C Vertical Cut 76°-79°

55.500-56.000 A(ui) VerticalCut 830

56.000-56.400 Rock & soil detns failure observed C VerticalCut 76°-79° at (564) _ _ _ _

Rock stratahas to be stabilisedby oneof 56.400-56.500 D VerbcalCut 830 the optionsprovided in the text

56.500-56.700 C VerncalCut 760-790

56700-57.020 C VerticalCut 760-79e

57.020-57.055 A(i) VerticalCut go0

57.055-57.175 C VerticalCut 76°-790

57.175-57.200 A(i) VerticalCut 90°

57.200-57.240 C VerticalCut 76-790

57.240-57.270 A(i) VerticalCut 90o

57.270-57.300 C VerticalCut 760-79°

57.300-57.350 A(i) VerticalCut 900

57.350-57.920 C Vertcal Cut 76P-79

57920-56000 Rock/sodfall noticedB VerticalCot ~~~~~~~~~~~RockstrataItas to be stabdisedby one of *57.92G-58.000 Rock/soilfall notied B VerticalCut .75° the optionsprovided in the text

59.000-58.070 C VerticalCut 760-790

507-840DCt750Rock stratahas to be stabilsed by one of 56 07D-58460 0 VerticalCat 170 the optionsprovided in the text

58.460-58.540 C verticalCut 76°-790

58.540-58.620 A(ii) VerticalCut <750

58.620-58.770 C Vertical 76-790

58.770-58.925 B Vertical 83' Rockstabilisation after cutting

58.925-59.290 C Verbcal 76°.790 59290-59365 B Verticatl 83 59 365-60.133 C Vertical 76°079°

60.1t3-50.925 C Vertical 760.79°

60.925-61.590 C Vertical 760-79°

361.5900-51.720 B Verncal 63° I ~~~~~~~~~~GeomorphologkcalCut SlopeProposed Recommended Chainage Landslides ZoneZorpholonsrtat by ConsultantsCutSlopeP Cut Slope, Additional Measures Suggested 61 720-62.280 C Vertical 76o 79'

Bypass Slalsuk

65.071-65.210 C Vertical 750.79°

65.210-655350 A(i) Vertical 83 OCuting fill stable slope is attainecl as there 65.350-65.505 D Vertical 83l are greater chances ouffailure along joint

65.50-655865 Ms s Afic) Vertical 830 Stabilisation of the rock after cutting 5 5.535-655.525 D Vertical 83° Stabilisation of the rock afler cutting _65.625-55.760 C Vertical 76°-79'

655750-65.a60 Mass wasting of rock O Verical 83Stabilisattior of the rock aRler cutting

65.860-65960C Vertical 7S0.790 65 960-665090 Vertical 83' Rrck stabilisaton after cutting 56.050-66.61QO Vertical 76 ° 7 9 ° 66100-66.230 Ajli) Vertical i0 66.230-66 820 C Verical 750o790 66 820-67 200 C Verical 750.790 * 67.200-67 250 C Vertical 750o790 67-250-67 300 Aiil) Vertical S3T 67.300-67 415 A(ii) Vertical 83° 67.415-67.475 C Vertical 750.790 BOanddrains are to be oonstructed 67.475-67.580 Dfii) Vertical 83° .56750-67.950 C Vertical 750°79° 67 .950-68.215 Alii) Vertical 83' 68215568.525 A(ii) Vertical 83° 68.525568.940 A(ii) Vertical 76°0790

68.940-69.370 Debes flow of 25 m high 3 m width A(ii) Vertical 83°

59.370-69.435 All) Vertical 83' |69435-69.825 C Vertical 790790 69 825-69.870 A(i) Vertical 69.870-70.000 C Vertical 760°790 70.000-70.100 A(ii) Vertical 90' 7 10A-70.200 Mud flow along pnt planes chances B Vertical 8Rock stabilisation 7of rockfall 70 250-70.220 A(l) Vertical o90 70.22D70.350_c___w Mud o A(ii) Vertical 76-79° Conistruction of band drains upto Bm on 70.220-70.3.50Mud & icofifow Alii) Vertical 160.790 either side of nud flow

70.350-71.500 Chances of slide if cuL ht >50m B Vertical No cutting is to be done Diversion of alignent on valley side

71 500-71.600 C Vertical 750-790 7_,600-71.9W Chances of tailure along fractures. A(ii) Vertical 63° .0- 1 rock fall at - 71.980______

71.980-72.515 jLandslides debris forw at kn 72.019 B Vertical 83° Rock stablisation after cutting

72.51 5-72.700 Afil) Vertical 83° i72.7DO-73.580 C Vertical 760°790 Recoerrnrended. 73.580-73.9 Vulnerable location at km.73.900- Vetical aignment valley elitebh knn.73.250 breast w-elttram bottorn

73.950-75.950 Debns fow km.74.790 C Vertical 7650790 75 950-76.050 Dehns flow at 76.050 A(ii) Vertical 83' Band drains at saUnrockinterface 76 00-76.325 C Vertical 769-790

76 325-76.450 Mass failure of kaolinised shale al A(ii) Vertical 769-790 Bard drans at soiUrock inlerface km 70.450 76.450-76.500 C Vertical 76°0790

76.500-75.540 A(ui) Vertical 900 76.540-7S.520 C Vertical 760.790 76.580-76 970 __ A(ii) Vertical 0750 7 6970-77.225 A ii) Vertical Vertical * 77 025-77.076 C Vertical 76°.79° 77_025T7.076_ Failure shall be along defound joint V 77 076-77.400 plane for to bedding I dipping D Vertical 83' Rock stablisation after construction towards road 77.400-77.491 C Vertical 760-790

77.491-77.600 Dock falidue to Kaolionisation at A(ii) Vertical 830 775600-77.625 C Vertical 760-790 5T25-77.610 C Vertical 760.790'______77.6510-776900 A(ii) - C Vertical 831

77.900-78 070 Debns flow at km 78.06 0 Vertical 83 Rock stabilisatici after cuttin 78.070-7B.450 C Vertical 760-7909 78 450-79.010 B Vertical 830 Rock stabilisaticn ater cuding 79.010-798040 C Vertical 830 79-040-79.840 C Vertical 769-790 79-80-79.970 A(it) Vertical 830 79-970-60.180 C Vertical 76°0790 80.180-80.470 A(ii)}C Vertical 830 80 470-80 270 A(ii) Verical 760.79° 80 270-80 300 C Vertical 76°0790 Band drains to prevent further erosion 80.300-81500 ANi) Vertical 833 8 s0-82. 170 C Vecal 76 °790 Chainage Landslides GeomorphologicalCut Slope Proposed Recommended Chainage Landslides Zone by Consultants Cut Slopel 82.170-83500 A(ii) Vertcal 83' 83.500-83560 C Vertical 78079° 83.500-83140 A(l) Vertical 830 83.940-83.980 Charces of ock fai ure alongjoint Vertcal 83° Rock stabilisation Iplanes 83 960-844C0 C Vertical 7S°.79° 84.400-84.560 A(ii Vertical S3- 84.500-85.873 Debnsflo at 85 150 C Vertcal 76° 79° 8*-870-88.900 Debnsfo o Vertical Sr3 Rock stablisation 85.900-86.180 C Vertical 760O79° 86.180-88.240 A(ii) Vertical 53 RQcestabilisation aflter cult ng 86 240-8791.0 C Vetical 76o 790 87.910-88015 A(l) Vertical S3° 88.015-89.400 C Vertical 76°-790 I 89.400-89500 A(li) Vertical B3r 89.500-89640 C Vertical 76°-79° 89 540-93 400 No cutting is required 93.400-96.080 C Vertical 760-790 96 080-36.250 Ali) VertOcal 900 96.250-96.824 C Vertcal 76°-79° 96.824-96.900 A(i) Vertcai 83° 96 0Go-97.000 C Ver cal 76°.790 97.000-97.190 Ali) Vertical 830 97.190-97.238 C Vert:cal 76°-79- 97 238-980330 Debnsflow at 98.120 A(i) Vertbcal 83° 98.330-98.470 C Vertical 76-790 98 470-98.540 Alll Vertical 830 98.540-98.620 A(,) Vertcal 83'_. __ . 98 620-98.720 F Vertical 83° 98.720-100.00 . F Vertical 76-79° -_-_-_-_.

I 3

I I I I. Mizoram State Roads Project - Phase I Annexures for P-IA l

APPENDIX 5 LOCATIONSFOR DUMPING CONSTRUCTIONWASTE

S. No Location Approximate Lead (km) 1 20.2 6 l 2 20.85 6 3 34.4-35.0 5 4 50.500 4 5 59.150 6 6 59.600 6 7 65.600 6 8 67.300 6 9 81.100 4 10 82.400 4 11 86.81 7 12 86.975 7 13 87.320 7 14 87.410 7 15 88.600 7 16 88.800 7 17 95.930 7 16 98.985 1 l 1 l l l

I Revisedby LeaAssociates 5 October2001 (OriginalDocument by ICT,CES, LBII l MizoramState RoadsProject - Phase I Annexures for P-IA

I APPENDIX5-A GUIDELINESFOR DISPOSALOF DEBRIS

1. The debrisgenerated shall be disposedof withindesignated areas only. 2. The filled uparea shall be usedfor designatedpurposes such as: I a) Playing fields

. Thesewill be createdby levelingof the filled up areaand compactingthe fill with severalpasses of a roller. . This compactedarea will be coveredwith topsoilfrom excavationfor a depth of 15- I 30 m. * The soil will be wateredand grassedto developa greencover over an areaof the playingfield.

3 b) Short realignments (see Appendix_ for chainages * The shortrealignments provide ideal disposal sites for substantialquantities of debris of cutting. * Thevalley between the sharpcurve shall be filledto the levelof the sub-grade.

| * A retainingwall of dimensionsas per engineeringdesign shall be constructedand the roadsection shall be constructedon the filled area. | Debriswill be continuedto filled till the levelof the top of the pavementis reached betweenthe newand old roads. I l I

Revised by Lea Associates 6 October2001 (OriginalDocument by ICT, CES, LBII Mizoram State Roads Project - Phase I Annexures for P-IA

| APPENDIX: 6 STRETCHES TO BE AVOIDED FOR DUMPING SITES: l Sl.No Starting Ch. Ending Ch. Reasons for avoiding Bio-diversity 1. 33.550 33.750 2. 40.340 40.450 3. 41.750 41.825 4. 47.400 47.700 Swamps and Marshes 5. 86.700 86.800 6. 86.750 87.00 7. 88.750 88.925 8. 90.300 90.500 9. 93.350 93.680 Ponds 10 88.100 88.175 11. 88.500 88.560 3

I l l

I

Revised by Lei Associales 7 October 2001 |(Original Document by ICT. CES, LBII Mizoram State RoadsProject - Phase I Annexuresfor P-IA I

APPENDIX-7 IDENTIFIED BORROWAREAS FOR PRIORITY ROAD Chainage( IN Km) Borrow Area Direction

3.600 BA-I R * 14.100 BA-2 L 19.700 BA-3 R l 28.500 BA-4 L 32.300 BA-5 L 75.100 BA-9 L 86.000 BA-10 L 93.900 BA-1l L 101.10 BA12 R

Identified Quarries Locationsfor Priority Road PI-A Phase-I:

S. Quarry Name & Location Tentative Yield lNo. (Tons) 1 ZAWNGEKHAM-6.0km from Damdiaion M7 MaintenanceRoad 25000

* ~ ~~~2SENTEZEL-KM 78+ 115-ATL-LEFT 100000 3 FANGFAR-KM78+860-ATL-LEFT 150000 4 Ch. 70.6 km On ati left 375000 5 Km 47.60 near village SAMSUIHon HmuifangSection "Not Estimated 6 DILKAWNLUI-KM74+020-ATL-LEFT 12500 7 SAILAM-KM66+760-ATL-LEFT 875 8 QUARRYOF MR. C. LALDUHAWMA(HAULAWNG) KM 131.9LEFT 17500 9 Km. 57.5, 4.5 Km fromHmuifangTowards Sialsuk 12,500 10 RAMRIKAWR,6.0 km from KEIFANGTOWARDS MUALPHEANG 100000 11 Km 31-000 ON ATL-LEFT 31250 12 Km 47.0 near village SAMSUIHon HmuifangSection 12500 13 Km 43.0, 2.00 KM aheadof village THIAK 10000 l l

Revisedby LeaAssociates 8 October2001 (Original Document by ICT, CES, LBII MizoramState RoadsProject - Phase / Annexuresfor P-IA

APPENDIX-8 SURFACEWATER BODIES I LOCATIONOF PONDS: Distancefrom Remarks Ponds Direction ProposedCL 88.120 L 39.10 No impact 88.705 R 6.98 At the outlet of the pond a small portion is impacted 90.360 R 20.74 No impact 90.385 R 7.95 At the outlet of the pond a small portion is impacted Due to the improvementof geometric 1/7 of the 92.390 L -8.4 pond area ( 156sq.m)to be acquired.

STREAMS/WATERFALLS (LOCATION WITH FLOW MAGNITUDE) Location Status of the Location Flow Magnitude streams/riversas on (Km.) ~~~~~~sep,2001 16.170 Dry I 18.985 Flow ht. Is 10 mt. Medium 20.855 21.040 Very high flow Medium 21.323 21.746 22.278 Good flow Medium 24.190 No flow Dry 25.939 No flow Dry 28.100 Good flow Medium 28.340 No flow Dry 28.742 Dry Dry 29.458 Good flow Dry 29.676 No flow Dry 29.883 _Dry 29.921 No flow Dry 30.190 No flow Dry 30.900 Small flow Minor 31.900 Dry 32.135 Dry 33.875 No flow Dry I 36.780 No flow Dry 37.088 Small flow Minor 37.265 Small flow Minor 37.473 Mediumflow Medium 37.560 Mediumflow Medium 40.800 Small flow Minor 42.335 Small flow Minor * 42.650 Dry 42.812 Dry 43.013 Dry I 44.330 Dry 44,685 Dry 45,009 Small flow Minor 45.191 Small flow Minor 46.210 & Tricklingsmall Minor 46.215 flow 47.278 (Sum Small flow Minor Suih ______Revisedby LeaAssociates 9 October2001 I (OriginalDocument by ICT,CES, LBII MizoramState RoadsProject - Phase I Annexuresfor P-IA

Location Status of the Location Flow Magnitude streams/riversas on (Km.) ~~~~~~sep,2001 47.575 Smallflow Minor 47.890 Small flow Minor 47.980 No flow Dry 48.36 Mediumflow Medium 48.725 No flow Dry 48.937 No flow Dry 49.076 Smallflow Minor 65.350 No flow Dry 65.863 No flow Dry 66.117 No flow Dry 66.192 No flow Dry 66.308 Small flow Dry 69.993 No flow Dry I 70.685 Small flow Minor 70.779 Small flow Minor *71.475 (Two Highflow (50 m Medium waterfalls) high need to be & 71.517& 71.517 preserved)High flow 71.803 Small flow Minor 72.155 Small flow Minor 72.260 Flow Minor l73.556 High flow exists, Medium 73.556 ~50m high 73.810, High flow Medium 73.834, High flow 73.860 High flow High flow, fall 5 Medium m 74.329 Anotherfall on I ______valley side 10 m below. " 74.433 High flow, 15 m Medium high 75.400 Smallflow Minor 75.934 Low flow Minor 76.093 No flow Dry 78.267 Flow exists Minor 78.735 Fall exists Minor 79.532 Large flow Medium I 81.009 Smallflow Minor 80.040 Smallflow Minor 80.311 Smallflow Minor 3 81.441 Small flow Minor 81.813 Villageflow Minor 83.683 No flow Dry 83.920 Small flow Minor 85.612 Largeflow Major

(existing) No flow Dry 87.400 No flow Dry {existin 87.620 No flow Dry 88.524 No flow Dry 88.800 No flow Dry I Revised by Lea Associates 10 October2001 (OriginalDocument by ICT,CES, LBII Mizoram State Roads Project - Phase I Annexures for P-IA

I- Status of the Lc(Kati) Flow Magnitude streams/riversas on

(existing) 89.040 No flow Dry 94.215, No flow Dry 94.332 96.175 No flow Dry 96.725 Dry 97.040- Vanva River Major 97.064 97.330 No flow Minor 97.543 No flow Dry 97.500 No flow Dry 97.754 Dry 97.798 No flow Dry * 98.102 No flow Dry & 98.142 No flow 95.935 No flow Dry l I I I l I l

I Revisedby LeaAssociates 11 October2001 (Original Documentby ICT, CES, LBII l Mizoram State Roads Project - Phase I Annexures for P-IA l

| APPENDIX- 9 LOCATIONS PROPOSED FOR LABOURCAMPS

Chainage Nearest Settlement 1 20.200 Tachhip 33.600 Damdiai 45.300 Sumsuih 54.000 Chamring 59.150 Sialsuk 59.600 Sialsuk 65.600 Sialsuk 81.100 Tenzwal(km 90.000) l l l l l 3

Revisedby Lea Associates 12 October2001 (Original Documentby ICT, CES, LBII Mizoram State RoadsProject - Phase I Annexuresfor P-IA

APPENDIX:11 CULVERTLOCAITONS ALONG THE PROJECT ROAD (including of proposedadditional culverts)

Chainage Type of culvert 1 Chainage Type of culvert 17.264 S.C 30.706 P.C 17.346 S.C 30.765 P.C 17.569 S.C 31.097 P.C 18.114 P.C 31.29 P.C 18.256 S.C 31.404 P.C 18.406 P.C 31.657 P.C 18.556 S.C 31.89 S.C 18.679 S.C 31.985 S.C 18.819 P.C 32.134 S.C 18.987 S.C 32.324 S.C 19.136 S.C 32.595 S.C 19.152 S.C 32.619 S.C 19.306 S.C 32.725 S.C 19.364 S.C 32.825 S.C 19.58 P.C 33.114 S.C 19.77 P.C AdditionalCulvert 20.02 P.C to be provided AdditionalCulvert 33.504 S.C to be provided 33.583 S.C 20.325 Out let 33.692 S.C 20.595 S.C 33.775 S.C 21.046 S.C 33.986 S.C 21.327 S.C AdditionalCulvert 21.55 P.C to be provided 21.741 S.C 34.321 S.C 21.92 P.C 34.367 S.C 22.092 S.C 34.526 P.C 27.37 S.C 34.900 P.C 27.579 S.C 27.721 S.C SC-SLAB CULVERT 27.871 S.C PC-PIPE CULVERT 28.103 S.C 28.337 S.C 3 28.426 S.C 28.622 P.C 28.743 S.C 3 28.924 S.C 29.062 S.C Additional Culvert 3 . to be provided 29.456 S.C 29.674 S.C 29.856 S.C 29.926 P.C 30.194 P.C

_ 30.264 P.C _ 30.537 P.C Revisedby LeaAssociates 13 October2001 (Original Documentby [CT, CES,LBII Mizoram StateRoads Project - Phase I Annexures for P-IA l APPENDIX:12 WATERFALLS THAT NEED TO BE PRESERVED FROM IMPACTS OF THE HILL CUTTING

S.No Chainage Mitigation Measure I 3 minor streams to be preserved.No hill cutiting for at least 30 m on either sides o 1 71.48-71.512 the location. Roadto be realigned.

Minor realignment of the road to shift the road section away from the hillside. No I 2 73.8-73.87 cutting of hill side for distanceof 30m on either side of th location No cutting of Hillside for a distance of 30 m on either side of the hillside. Waterfall to 3 74.3 be preservedas it is.

4 74.46 No cutting of the Hillsidefor a distanceof 30 m on either side of the location.

Road to be realigned.Also Sentezel Quarry adjacent to the waterfall to be closed. No * 5 78.759 cutting of the hill sidefor a distanceof 30 m on either side of the waterfall location l l l l l l

Revised by Lea Associates 14 October 2001 |(Original Document by ICT, CES, LBII m - -- m - m - - - - m - - - - -

Mizoram State RoadsProject - Phase I Anrnextiresfor P-IA

APPENDIX 10 FEASIBILITY OF HARVESTING WATER ON PRIORITY ROAD PlA FEASIBILITYOF HARVESTINGWATER ON PRIORITY ROAD PIA S. CHIAELCTO IEOTALAT HILL & AT ROAD OTHER REMARKS NO CHAINAGE LOCATIONSIDECATEGORY HILL SIDE VALLEY SIDE ROAD REALIGNMENT RIVER BED INTERFACE RELGMN RIRBD Missed the Around 1 Km Meiriat RHS Checkdamon 12x 18m space Small covered tank existing,usedfor 2 16.2 Mulluangthu RHS Medium NA valley side available NA NA bathing,washing etc After link to Medium I Ht - Storageof about 10x15x1.5m 3 18.9 Rantla RHS lOim available NA NA NA NA Existing water tank at 1Omaprrox. 700mafter 4 21 link to Tachip LHS Medium Water Tank at 6m ht feasible Check Dam NA NA NA 2 Existing Tanks/ 4-5 small tarnksof 3x4x2mon Underground 5 21.4 LHS Medium cascades Tank NA NA Underground 6 22.28 Link to Tachip LHS Medium NA NA Tank NA NA Storage at 3 7 28.1 LHS Small levels(4rnx5mx3m) - NA NA NA NA Garbage dumping on valey Small rectangular tank partly sunk in Storageat levels along stream side.Tank not Underground ground existing plus water harvesting 8 29.47 LHS Medium cascade feasible Tank NA NA tank of tin.HP existing. Underground 9 29.965 LHS Medium NA NA Tank NA NA 3 Tanks feasible at levels along stream cascades Space of 10 31.9 LHS Large about 12m x 15m available NA NA NA NA Space available 4 x 20m at 3m 11 42.35 LHS Minor height. NA NA NA NA 12 42.66 __ Minor Tank of 1Omx 6m NA NA NA NA Baskets of mystery Crabs? 13 47.3 Medium Tanks at 2 levels 3-4m wide NA NA NA NA After 14 48.2 Hmuifang LHS Major 2 levels Check Dam NA NA NA 2 streams at about 50m distance/Ht 50m /To be enhance.Roadto be realigned to 71.48 preserve rockface from being cut/To be 15 /71.512 RHSI Major NA NA NA NA NA enhanced Underground 16 73.5 RHS Major Storage feasible at 6 levels NA Tank NA NA Check dam at 2/3 Space available at > 9m levels along To be enhanced.Spaceto be generated 17 73.8-73.87 RHS Major ht.steep vertical fall. stream cascade. NA NA NA through minor realignment./3 streams_ Revised by Lea Associates 15 October 2001 (Original Document by ICT, CES, LBII ------m - -

Mizoram StateRoads Project- Phase I Annexures for P-IA

FEASIBILITYOF HARVESTINGWATER ON PRIORITY ROAD PIA NO CHASNME LOCATION SIDE ALF HIDE AT ROAD OTHER REMARKS CATEGORY HILL SIDE VALLEY SIDE ROADRIEBD ______~~~~~~~INTERFACERELGMN RIRBD Tanks at levels Waterfall to be preservedtenhanced No 18 74.3 Major NA along cascade NA NA NA cutting on hill side Check dam on valley side To be preserved.Nocutting of hillface/6- 19 74.46_ _ Major Steep vertical face,not feasible feasible NA NA NA 8m space available for enhancement 20 75.44 RHS Major Tanks in levels along cascades NA NA NA NA Check Dam at 2 21 75.9 Small Sorage feasible at 3 levels levels NA NA NA Check dam 22 77868 RHS Major Storagefeasible in 3 levels feasible NA NA NA Water fall to be enhanced/Highestand 23 78.759 NA NA NA NA NA biggest waterfall on Priority Road PIA 24 79.5 RHS Major Storage on hill side NA NA NA NA 25 81.55 RHS Major NA Checkdam NA NA NA 26 83.93 Medium Tank feasible at 6m ht NA NA NA NA Steep vertical fall. Space for Underground 27 _ 85.3 RHS Medium Storageat 3 levels NA Tank NA NA 28 92.58 RHS Exsiting pond can be used Location ideal for rest area Area under /around Bridge to be 29 97.06 NA NA NA NA dredged/deepened River Vanwa

Revised by Lea Associates 16 October 2001 (Original Document by ICT, CES, LBII I I I I I I I I I I I Mitigations/EnhancementDrawings I I I I I I I I I I I

High Ncy |-mbrl0 Mesh of 6mrm openings (typ.) o o / to be fixed w th barbed w re in all l n o i ~~~ponels

. , ISA,_ 55x55x8n (typ.) I~~~~~~~~

Minimum 700 Bomboo poles of 125-1500 Minimum; _ 700 _ @O300 c/c

oooo0oooo0 ooo0000ooooooooooooooooooooo 00 0 To be provided in case of volley

0 * 0o -B o~~~~~~~~~mbooafencing (As per detail) osbengwest or south of the rood I 0 c I,

0 e ° 1000 4 rs >5 0 E

30 Carbed wire fencing V ~~~~~~~~~~~30 (As per detail) .f E To be provided in case of volley

w o o .' D ~~~~~~~~~~~~~~~~~~~beingwest or south ot the rooc

l~~~~~~~~~~~ -300wide s 300deep drain

-~~~~~~~~~~~ -2 U

IrScheme forProtecting Trees During Construction

| ~~~~~~~~~~~~~MIZORAMSTATEROADS PROJECT - Phase I (Aizawl- Hmuifang - Buangpui) 3 ______jLEAAssociatesSouthAsia Pvt. Ltd. j tEambooMesh of 6mm openings (typ.) ,o o to be fixed with borbed wire in all

p $F 55x55x8

Min 300x 0 @0 c/c

r ~~~~SECTION 1-1

Bamboo poles of 125-1500 _Minimum 700 _ , 300 c/c

o000000000000 o00000000000c00000000000 a o To be provided in case of volley 0o f being west or south of the rood oa -8 ornboc fencirg (As per detail) a

o | 0 To be provided only if the volley c0 0 is locted west of the rood Q,0

0

.0 0

0 0 _ di °° fi 3recwr fnig 1 0jE a' 0 _ 4 1u oiAre toOprtc 03 a

To beprciet ic perdetail) 000 00 IDIac c

Barbedfeasrofvale wireT beprvied

3003 widedeep x drainbein westidor sout cofste rofadle

PLAN

Scheme11 for Protecting Trees During Construction

MIZORAMSTATE ROADS PROJECT - Phase I (Aizawl- Hmuifang - Buangpui) LEAAssociates South Asia Pvt. Ltd. 300 g Bamboo poles ot 125-1500 L t ~ ~~~~~. / 'O 0 c/c.

ELEVATION (Outer Most Row)

2010 (Typf) 750 - 1000 Bcmboo strits (6-8 nos.) r750 - 1000 BOrnoDo brcicng (diosonol)

750 - 1000 Baboo brocirg (diagonal) BBornboo poles of 75-1000 0 2000 c/c PLAN

0~~C

ELEVATION (Intermedicte Row)

Borbed Wire (G.l) Bomboo Mesh of 6mrnmopenings (typ.) to be fixed with bcrbed wire in oll 1000 panels

/* A. SA 55x55x: (typ.)

Detail of Barriers for Protecting Trees

MIZORAM STATE ROADS PROJECTPROJECT- - Phase I (Aizawl- Hmuifang- Buangpui)

LEA Associates South Asia Pvt. Ltd. I~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

| rain 0.6m wide

4\Corrio3ewoy r r | Stone masonry parapet 8< A~~~~~~~~~~~PoCulvert

Hill \ Valley Valley~~~~ale

6 tS ~~~~~Stonernosorry il%*^he~~Chekdcm

* W r HrSpillover drsineg through

SECTION M S P P

T-1 VValley T~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~-

: / / t l | ___-_--- ~ ~-_-_-a=-~-~-_-_-=\ \

(Aizawi- Hmuifa- - -B-angp--u-) HlEAAsoiteSothAiacl.Ld

/~~~~~~~~~ae==_ =Side Haresin\\ Vale

*~~~~~~~~~~~~~~~~~~~Azw-'Hmifn - Bungui

|~~~~~~~~~~~~~~~E MIOAsscaeSoThT RADSi PvOET. Phase. 500 Holes for spillover

'la_~atr Tank _

Woter Ton Stone masonry

Hill

IF Spillover drained to -,neorest culvert

tt tDrounOC6m wide Snt ne mosonry wol prurpet

X- ieIv at _, 1-X _ ,V,lley

WaterHarvesting on Hill Side

MIZORAMSTATE ROADS PROJECT - PhaseI (Aizawl- Hmuifang- Buangpui)

LEA AssociatesSouth Asia Pvt. Ltd. Existinq Exetn IProposed - =i = \ , ~~~~~~~~~~~Corriageway

\ _ _ _ _ _ 0 ~~~~~~~~~~~~~~~~Re tauining WallI -v------_- \------Lw j = Valley

I, - 1 Om d. Concrete p pe | /'2-' C ~~~~~~~~~~~~~~~~~~~~~~~to be laid in 51ope

l ~~~~~~SECTION AXX t sPipe Cu vertv ~~~~~~~PipeCulvert I. : Ir

I PLANWate HarvestingatRealignmentLocatExistini

------

p\\---==----=------Valley Side)

------MIORM TAT RAD-POJCT- hae-

------(A-i-a-l- -unpi - - Hm ifn ------LE-Asocite Soth si-Pv. Ld. I~ ~ ~ ~~~~~------. ------ioe uvr 1~~~~~~~~~~~~~------

-A-a w- HmuiangBuanigpment ti)

LEA-Associae- SouTh -ROADS PRCT.- I c I1 tlI

~~~~~Pilot Tonk _

I /v/ -/ Ptone masonr ot

L ! y / / r ~~~~~~~~~~p'ortlyunderground/// //~ I~~~~~~~~~~~~~~~~~~~~VIe

Sp,iaover to be corried by drair to nearest culvert

I PLAN

WaterHarvesting at Hilland Road Interface

MIZORAMSTATE ROADS PROJECT - Phase I (Aizawl- Hmuifang- Buangpui) LEAAssociates South Asia Pvt. Ltd. X -tfe';\\~~~~~~~~~~~~~~~~~~~~q%.F!

. ~~EnhancementDesign for Waterfall at Km.73.44

MIZORAMSTATE ROADS PROJECT - PhaseI

(Aizawi- Hmuifang- Buangpui)

: L | ~~~~~~~~~~~~~~~~~~~~~LEAAssociatesSouth Asia Pvt Ltd 1 WATERFALL WATERFALL

rn$'\ t BrDdge n eall for 2

k'tt>.t\..LL L ttttt..t-ttt LLLLtt

- -~~~~~~~~~1 -h I -LL ~ M SA ROADSP J

I -alngp\) a - LLLLLA

L AsoiaeViewsn Sout A P L 0 ' // ~~~~~~~~~~~~~~~~Proposed Culvert\

EnhancementDesign for Waterfall at Krn.71.24

MIZORAMSTATE ROADS PROJECT - Phase I (Aizawl- Hmuifang- Buangpui) LEAAssociates South Asia Pvt. Ltd. 5 1-25q ,Bt / V A L L E Y

EnhancementDesign for Waterfall at Km.78.100

MIZORAMSTATE ROADS PROJECT - PhaseI (Aizawl- Hmuifang- Buangpui) LEAAssociates South Asia Pvt. Ltd.