TECHNICAL PAPER OPTUS STADIUM and STADIUM PARK Abstract
Total Page:16
File Type:pdf, Size:1020Kb
AUSTRALIAN CONSTRUCTION ACHIEVEMENT AWARD TECHNICAL PAPER OPTUS STADIUM AND STADIUM PARK Abstract In the construction of Optus Stadium and appointed in 2014 to design, build, partially the surrounding Stadium Park, Multiplex has finance and facilities manage the Stadium. delivered a truly world-class venue for Western Australia. A ‘one team’ approach was taken from the outset, with the Multiplex and Client teams co- Located on the Burswood Peninsula, the 60,000 located on site to foster a collaborative working seat multi-purpose Stadium can host a variety relationship. All team members were energised of sports and entertainment events including to work toward the project’s shared vision of Australian Football League, cricket, soccer, rugby delivering a world-class stadium in an activated and concerts. sports and entertainment precinct. The surrounding Stadium Park provides year- The result is an innovative design which ensures round access for visitors of all ages, with facilities an exceptional event atmosphere and home including nature playgrounds in the Chevron Parkland, the BHP Boardwalk and Amphitheatre, ground advantage. picnic and barbeque areas, public art, recreational facilities and bars and restaurants. Construction of Optus Stadium and Stadium Park was delivered over three weeks ahead of Multiplex was responsible for the design and schedule. It is owned by the Western Australian construction of the Stadium and surrounding State Government and opened to the public on precinct as part of the Westadium Consortium, January 21, 2018. EXECUTIVE SUMMARY Optus Stadium and Stadium Park | Technical Paper 2 1. Scope of Work The consortium comprises John Laing (equity investor and asset manager), Multiplex (lead Multiplex was responsible for managing a design design and construction contractor), BGIS team consisting of three architects and 20 (facilities manager leading the maintenance consultants, as well as engaging more than 130 and services delivery), and Brookfield Financial subcontractors and suppliers to deliver the full (financial adviser). range of trades and services. The State of Western Australia funded 60 per The Stadium itself is a six-level steel and concrete cent of the design and construction (paid during structure with a colosseum seating bowl of the three year design and construction phase) 60,000 seats, designed with the potential to and Westadium is responsible for financing the increase to 70,000 seats within the existing remaining 40 per cent of the infrastructure. structure. A lightweight fabric roof covers 85% of seats and creates a suspended ‘halo’ effect. 3. Rehabilitation of the Burswood Peninsula The structure is clad with a striking anodised aluminium façade reflecting WA’s unique geology Previous land use of the Burswood Peninsula and incorporating LED lighting displaying team meant that at project commencement, the site colours. Over 50 food and beverage options was registered as ‘possibly contaminated – are provided including restaurants, cafes and investigation required’ under the Contaminated other outlets. The Stadium also hosts 17 distinct Sites Act 2003 (WA). premium product areas, the largest variety of any stadium in Australia. Additionally, the site is located adjacent to the protected Swan River and interconnected with With a vision of a ‘Stadium within a park’, the the river via an onsite river fed tidal lake. scope of work also consisted of hard and soft landscaping over an area of 41 hectares, As a result, the ground conditions for the project including the design and construction of nature were particularly challenging. Site investigations play areas, a boardwalk and amphitheatre, a found that the upper eight metres of ground community arbour and a number of cycle and consisted of fill including concrete, fly ash, car pedestrian pathways connecting the precinct. bodies and household appliances. Multiplex managed and coordinated the design Beneath this fill, the estuarine sediment known as consultant team to interpret the brief and develop the Swan River Alluvium was found to depths of a compliant and coordinated design solution with 25 metres, overlying stiffer clays and sandstone. buildability input. Environmental challenges included management Key challenges included overcoming poor ground of potential impacts to ground and surface water, conditions and implementing a delayed design contaminated soils, and ground gases. Site and procurement process without impacting on- specific management plans and procedures were time delivery of the project. developed and implemented to manage these risks and included: 2. Type of Contract • Developing a soil capping strategy involving Optus Stadium and Stadium Park was procured warning layers and importing over 40,000 through a Public Private Partnership using cubic metres of high quality top soil a Design-Build-Finance-Maintain (DBFM) • Implementing a comprehensive ground and procurement model. surface water monitoring system • Requirement for a ground gas membrane to The Westadium consortium was awarded the the satisfaction of an impartial Contaminated DBFM contract in August 2014, which includes a Site Auditor 25 year maintenance period. Optus Stadium and Stadium Park | Technical Paper 3 Multiplex’s target was the reclassification of the of the precinct including the Chevron Parkland and site’s contamination status to enable it to be utilised BHP Amphitheatre and Boardwalk, while meeting for its intended purpose as a Stadium and precinct. stringent environmental requirements for the site. This was successfully achieved with the Over 2,700m2 of sheet piling was also installed to Independent Auditor and Government further prevent any contaminants migrating into Environmental agencies endorsing the targeted the Swan River. reclassification for the site. It was also achieved ahead of the targeted date, being the first public The Stadium structure itself is supported by over event being held at the Stadium. 2,600 piles to depths of 36 metres. In total over 30,000m3 of concrete was used for the ground 4. Ground Improvement improvement works, representing nearly a third of the concrete used on the Stadium structure in total. A number of different ground improvement techniques were used to counter the conditions. A 5. Ground Gas Mitigation 20,000m2 area within the Stadium Park underwent dynamic compaction and surcharge loading to A further common environmental impact from collapse large voids, like those created by car landfill sites is the presence of ground gases bodies or similar items located within the fill. such as methane and carbon dioxide in the soil. Additionally the Swan River Alluvium is known Over 8,000m2 of vertical drains were installed to produce ground gases due to the organic to the Bus Hub area. Due to objects in the fill content within the soil. blocking the installation of the drains, over 50% of the area was required to be pre-punched to Initial testing of the site identified the presence of clear obstructions. gases including methane and carbon dioxide. In a ‘worse case’ scenario, gases could enter the Over 10,000 Controlled Modulus Columns building once constructed and pose a hazard to (CMCs) were used to improve ground conditions human health or create a potentially explosive across a 60,000m2 area of the Stadium Park atmosphere. adjacent to the Swan River and river-fed lake. As such, gas mitigation was identified as a CMCs are a relatively new technology to Western requirement to remediate the site for its intended Australia and the Stadium was one of the first use. projects to utilise CMCs to this extent. As opposed to pre-loading this area, which may have pushed There is no set standard for gas mitigation in contaminants into the Swan River and river-fed Western Australia. A compound known as lake, CMCs work by improving the characteristics ‘Golden Boot’ is commonly used in Melbourne, of compressible ground by use of rigid inclusions. however this was identified as being sensitive to heat and therefore not suitable for use in Perth’s This successfully improved the ground for key areas warm climate. Optus Stadium and Stadium Park | Technical Paper 4 Multiplex instead employed the innovative use of The project had several external interfaces with an existing product - utilising the Enviro HP1600 independent contractors adjacent or within the water proofing membrane as a gas membrane. project site including the Stadium Operator, This had recently been used by Multiplex on the Swan River Pedestrian Bridge, Public Transport adjacent Crown Towers development on a much Authority train station development and Victoria smaller scale (the first time it had been used for Park Drive road realignment. this purpose in Western Australia). Other interfaces included State utilities upgrading The Stadium is the first time Enviro HP1600 has water, communications and power provisions to been successfully implemented on such a large site. footprint and has proven meet the stringent specifications for a ground gas mitigation solution. All interfaces were successfully managed by Multiplex as the lead contractor for the precinct, 6. Logistics, Interfaces and with regular interface meetings held to maintain dialogue and transparency. Constraints With the site classified as ‘potentially On-site logistics required careful consideration contaminated’ the site team also carefully due to the large volume of traffic movement in managed all civil works and tracked all civil and around site, with multiple work fronts under earthwork movements,