Quick viewing(Text Mode)

Engineers Who Get Their Hands Dirty

Engineers Who Get Their Hands Dirty

Engineers Who Get Their Hands Dirty Mission Statement Our mission here at Dirty Suit Construction is to produce high quality work, no matter how small or how large of a project, while offering competitive pricing, great communication, and a safe work environment for all employees. We at Dirty Suit Construction value our quality reputation and strive to please all parties, whether it be project owner, subcontractors, suppliers, or consultants. All parties are treated with high integrity and respect to help insure lifelong relations and business. Greenfield Bridge Replacement

Bridge Name: Beachwood Blvd. Bridge Originally constructed in 1921 466’ total length: 274’ main span Traffic conditions: Current A.D.T: 12,800 Design Year A.D.T: 16,100 Designer estimated completion: September 5th, 2017 Designer estimated build cost: $15-$20 million Greenfield Bridge Replacement Owner: City Of Department of Transportation BMS No.: 02 7301 0000 3039

Designer: HDR Engineering, INC. 11 Stanwix St, Suite 800 Pittsburgh, Pa 15222 Greenfield Bridge Replacement

General Contractor: Dirty Suit Construction 115 Federal St. Pittsburgh Pa, 15213 Meet Our Construction Management Team: Derrick Lubomski (Project Manager) Ryan Shaffer Adrienne Sciarretti Eric Danko Jack Ozaroff Kevin Link Paige Lumley Limits of Work

GREENFIELD Community Impact

Noise Control Traffic / Detour Air Quality Safety Consideration Access to Schenley Health / Fitness Stimulates local economy Traffic Control Plan East Detour Route

I-376 EAST EXIT 72A -> FORBES AVE BATES STREET -> HALKET ST - > FORBES AVE Traffic Control Plan East Detour Route

FORBES -> S. BELLEFIELD AVE -> FIFTH AVENUE PENN AVENUE -> ENTRANCE I-376 EAST - WILKINSBURG (PA8 NORTH) INTERCHANGE Traffic Control Plan Closure from Squirrel Hill Interchange Ramp To Edgewood / Swissvale Interchange

Murray Ave -> Wilkins Ave -> Penn Ave -> I-376 East Traffic Control Plan West Detour Route

EXIT 78B WILKINSBURG (PA8 NORTH) CLOSURE OF EDGEWOOD / SWISSVALE INTERCHANGE

PENN AVE -> FIFTH AVE -> FORBES AVE ->BATES STREET -> I - 376W Traffic Control Plan Closure from Squirrel Hill Interchange Ramps To Forbes Ave / Oakland Interchange

BEECHWOOD BLVD FOWARD ST-> MURRAY AVE -> FORBES-> BATES STREET -> I - 376W Traffic Control Plan

● Signs : Speed Limit, Road Closed, Work Zone, Detour, End Road Work

● Type B Flashers

● Type III Barricades

● Channelizing Devices (Vertical Panels)

● Road Markers

● Shadow Vehicles

● Concrete Barriers (PennDOT) Quality Management Plan

● Document Change Control ○ version #, date of issue, author(s), description of change ● Quality Policy ● Quality Objectives ● Management Organization ● Quality & Document Control ● Construction Inspection Communication Plan ● Communication is essential for a project to be successful. There are multiple positions involved including subs, architects, engineers and owner(s).

● Meetings (weekly) -project goal priorities will change frequently

● Proper logs, change orders and other documentation such as electronic & hard memorandums / reports determine how smoothly a project can run

● Use methods such as P6, email, & phone calls

● Not only does the internal circle of the project need to be in healthy communication with each other, but also the outsiders involved (stakeholders)

● Different groups of people will be impacted by the project; it is important to keep them updated so that their everyday lives will not be negatively affected ○ Noise & traffic are typically the main issues Communication Plan Public Information ● Information Card handed out at public meetings (Oakland Transportation Management Assoc.)

● Project Description

● Bridge Construction Dates -total duration of ~24 mo.

○ month #1: bridge closes to public & contractor begins physical work

○ month #3: bridge implosion (including part time closure of I-376 Parkway East)

○ month #4 & on: construction of bridge

● Pedestrian traffic restricted from bridge - pedestrian/bicycle detour route implemented

● General traffic detoured around bridge with the aid of a posted detour

* project updates, detailed traffic detours and Q&A can be found on the up-to-date website* Project Partners Foundations Overview: Foundations

Open Cut Excavation ● OSHA Standard 1926 Subpart P ○ Soil Type C: 1.5:1 max allowable slope ● Based on Design Drawings ○ 1.95:1 slope Foundations

• Lengths developed using provided core borings • Micropile Assembly: • #28 All-Thread Reinforcement • Steel Casing • Steel Plate • Hex Nut & Washer • Assumed production rate from Amelie Construction: 3-4 per day

Location Total Average Average Verification Production Length Length Micropiles Quantity (Battered) (Vertical) (ft.) (ft.)

Abutment 1 46 59 55 2

South Thrust 60 66 72 1 Blocks

North Thrust 60 37 47 1 Blocks Foundations

Drill Rig: Comacchio MC-22 High-Tech Line Encountered issues with drilling Bench EL. Bench EL. 1 882.36 1 882.36 2 877.44 2 877.44 3 872.51 3 872.51 4 867.59 4 867.59 5 862.66 5 862.66 6 857.74 6 857.74 Foundations

Control of Heat of Hydration Element with least dimension greater than or equal to 6 ft ◦ South Thrust Block Footers ◦ North Thrust Block Footers ◦ South Thrust Blocks ◦ North Thrust Blocks Reduce cracking due to high temperature and uneven concrete cooling Thrust Block Footer Formwork Foundations

Responsible for stability of all excavated slopes and embankments South end: Greenfield side ◦ Open cut excavation North end: Schenley side ◦ Earth-retaining structure Foundations

● Pittsburgh Redbeds ○ Clay minerals organized randomly ○ Water becomes trapped ■ Causes excessive pore pressure ○ Introducing additional water causes claystones to push themselves apart Foundations Temporary Retaining Wall

Load ● Type of retaining structure: Transfer Soil Nail Wall ○ Quick construction ○ Logical selection ■ Same drill as micropiles

Soil Nail Foundations SNW Wall Location

North Thrust Block Foundation Abutment 2 Foundation

Soil Nail Wall Foundations Preliminary Design ● Wall Length: 70 feet ● Wall Height: 15 feet ● Nail Length: 12 feet ● Nail Inclination: 15 degrees ● Nail Size: No. 10 Bar ● Nail Spacing: 5 feet ○ Horizontal & Vertical Directions ● 6 Inch Shotcrete Facing ● Vertical Wall Foundations Final Design ● Alterations to initial design: ○ Wall Height: 20 feet ○ Nail Length: 20 feet ○ Nail Inclination: 20 degrees ○ 8 Inch Shotcrete Facing ○ Wall Batter: 10 degrees

*Wall modeled in FHWA SNAP-2 Software Foundations SNW Wall Construction

● Construction Sequence ○ Excavate Lift ○ Drill Hole ○ Install Nail ○ Place Facing Substructure Overview: Piers & Abutments Abutments & Piers

Abutments ◦ Total Concrete: 393 CY ◦ 4 Pours ◦ Bush Hammer & Rect. Cut Stone Finish Piers ◦ Total Concrete: 242 CY ◦ 3 Pours ◦ Bush Hammer Architectural Finish Abutment Wingwalls

B C

A D Abutment Wingwalls Mechanically Stabilized Earth Walls

● MSE Wall Components ○ Leveling pad ○ Straps ○ Precast Concrete Panels ○ Backfill ● Construction Sequence ○ Pour leveling pad ○ Erect 1st Row of Panels ○ Place Backfill ○ Place Layer of Geotextile Fabric ○ Install Reinforcement Straps Steel Erection Overview: Preliminary Steel Erection: Alternative 1 Preliminary Steel Erection: Alternative 1

Too Large of Moment Final Erection Sequence: 1) 2)

3) 4) Final Erection Sequence: 5) 6)

7) 8) Final Erection Sequence: 9) 10)

11) 12) Final Erection Sequence: 13) 14)

15) 16) Final Erection Sequence:

17) 18) Falsework Design:

South Tower North Tower Wind Load Elevation Profile: Structure Analysis of Sequence:

Load Cases Examined: 1) 1.4DL 2) 1.25DL + 1WL (T) + .5WL (L) Governing Load Case 3) 1.25DL + .5WL (T) + 1WL (L) 4) 1.25DL + .7WL (T) + .7WL (L) Structure Analysis of Sequence: Structure Analysis of Sequence: Structure Analysis of Sequence: Structure Analysis of Sequence: Structure Analysis of Sequence: Steel Erection- Crane Layout

Show crane layouts/logistics-Derrick/Ry Site Logistics

Material Laydown~ 13,713 SF

Unloading/ Loading~ 4,007 SF

Loose Material Stockpile~ 3,522 SF Deck Overview: Deck

53’ - 9 ¾” Width (Out-To-Out)

10’ width Sidewalk

16” thick Sidewalk Deck 8” thick 1” clearance from bottom for rebar 2.5” clearance from top for rebar

TYPICAL SECTION Deck Pour Specs

CONCRETE WATER CURING SPECS

AAAP: Deck Slab, Concrete End Diaphragms AAAP: 14 days

AA: Sidewalk, Abutment / Back walls, Abutment AA: 7 days Integral drain through, Approach Slabs, Moment Slabs, Sleeper Slabs

High Early Strength: Fillers (Dowel Bars) High Early Strength: 3 days Immediately after water curing is done & A reduction in shrinkage potential that would help reduce cracking after surface film of water has Improvement in workability and easier to finish allowing contractors disappeared, apply curing compound to to provide a finish that would be more durable and long lasting bridge approach slabs. Deck Setup

Total Duration: 25 days Deck MAIN DECK POUR SEQUENCE 1 & 2 Pour End Diaphragms at Abutments below construction joints

3 & 4 Pour Approaches

5 Pour main portion over arch, placement must remain plastic

6 & 7 Pour Block Outs over Abutments Concrete: PennDOT AAAP Quantity: 785 CY Greenfield Side Schenley Side SUBCONTRACTORS / PLANTS Essroc Ready Mix – for concrete / trucks 2220 2nd Avenue Pittsburgh, PA 15219-3107 412.431.6001 MAIN DECK POUR CREW Howard Pumping – used for pumps and equipment ● 1. Bidwell Operator 701 Millers Run Road Cuddy, PA 15031 ● 1. Pump operator 412.257.1800 ● 1 laborer with hose

DOT Diamond Core Drilling - Bridge Deck Grooving ● 1. Supervisor / Foreman 780 Sugar Lane ● 2 laborers with vibrators Elyria, Ohio 44035 ● 4 Laborers with lutes Peter J. Caruso & Sons, Inc. – paving ● 2 Laborers with coverups 352 Baldwin Rd. ● 2 Carpenters Pittsburgh, PA 15207 412-462-4500 ● 2 Finishers behind Bidwell ● 1 Other Finishers JB Sciarretti Trucking Inc - trucking ● 2 Gutter Finishers 1800 Whitaker Way, ● Homestead, PA 15120 TOTAL CREW SIZE OF 19 Deck

SEQUENCE

Form & Pour Sidewalks (West Side) Greenfield Side to Schenley Side

Form & Pour Parapets East Side then West Side Architectural Finish on both sides. 42” High Conduit running through them

West Side East Side

Erosion & Sediment Pollution Control Plan

● Topsoil shall be stockpiled at designated locations; height shall not exceed 35 feet

● Building materials / wastes shall be removed from site & recycled; none shall be burned or buried on site

● Until site is stabilized, all erosion & sediment BMP’s shall be maintained; log dates from inspections required

● Strict policy on concrete wash water… in no case shall it be allowed to enter surface or groundwater systems

● All embankment/rock/topsoil stockpiles shall be protected by compost filter socks at downstream side

● It is is the contractor’s responsibility for all waste material storage and disposal Best Management Practices (BMPS) Staging of Earthwork/Installation of Control Measures

Phase I (bridge demolition) Phase 2 (bridge & approach construction) Clean Fill & Environmental Due Diligence • Fill deposited on site or exported to an off site location must meet PADEP’s definition of “clean fill” • “Uncontaminated non-water soluble non- decomposable inert soil material” (includes rock, stone, dredged material, used asphalt, brick, block or concrete) Recycle Plan:

PennDot Specifications [PUB 408/2011] Recycled Concrete: Salvaged and crushed concrete pavements and concrete highway structures from Department, county, or municipal projects for use as aggregate in subbase only.

Acceptable aggregate produced from recycled concrete need not conform to soundness requirements

*Recycling requirements must follow community regulations* Schedule

● Developed using Oracle Primavera P6 ● Total Calendars: 8 ● Total Activities: 340 ○ General PENNDOT ● NTP: Sept. 1 - 2015 ○ Steel Erection (4) ● Project Duration: 736 Days ○ Concrete Deck Placement ● Project Completion: Sept. 5 - 2017 ○ Paving ○ 7-Day Week - Round Clock Schedule Estimate Developed using HCSS HeavyBid

Total Number of Bid Items: 162 (From PennDOT) 4 (Add-ons)

Estimate Priced 3 Different Ways ◦ Subcontractors’ Prices ◦ Historical Prices ◦ Average Prices from PennDOT’s ECMS site ◦ In House Estimate ◦ The items below under Bridge Structure Lump Sum item Estimate: Concrete Work

Each type of concrete was broken down by location & quantity needed

For each location, 4 activities were priced out ◦ Furnish material ◦ Formwork ◦ Crew ◦ Production Rates: vary by type of structure ◦ Equipment ◦ Place/Pour and Finish/Cure ◦ Crew Size: 8 workers each for the Structures (ex. Piers) but 19 workers each for the Superstructure (Deck) ◦ Production Rates: vary by quantity ◦ Equipment ◦ Strip Formwork ◦ Same Crew & Equipment as Formwork ◦ Production Rate: varies by amount formwork Estimate: Steel Work

Furnishing the steel and temporary towers were priced first

Then each erection sequence was priced separately ◦ Temp. Towers including striping them, 3 Arch Segments, Arch Columns, Floorbeams, and Stringers/Diaphragms

For each Piece Erection, 3 activities were priced out ◦ Unload & Prep ◦ Production Rate: 3 to 4 hrs per piece ◦ Crew ◦ Equipment ◦ Erecting Pieces ◦ Same Crew and Equipment as Unload & Prep ◦ Price by the schedule time to erect piece ◦ Bolt Up Piece ◦ Production Rate: 1 Ironworker can do 10 bolts/man-hour ◦ Crew ◦ Equipment Estimate: Breakdown & Total

Direct Costs (Bid Items): $14,374,265.31 Bridge Structure: $6,730,567.25 Subcontractors: $5,854,932.06 Historical Prices: $1,788,766.00 Indirect Costs (General Conditions): $1,724,911.84 12% of Direct Cost Bond & Insurance: $1,149,941.22 8% of Direct Cost Risk (Refer to Risk Breakdown): $743,750.00 Mark Up Profit: $718,713.27 5% of Direct Cost

Project Total: $18,711,581.64 Risk Identification Risk Contingency Risk Contingency TOP 5 RISKS

1. ADDITIONAL PARKWAY CLOSURES (Construction Risk)

2. WEATHER (Environmental Risk)

3. SCHEDULE DELAYS (Construction & Project Management Risk)

4. DEFECTIVE WORK/ QUALITY ISSUES (Construction Risk)

5. ACCURACY OF ESTIMATE (Projection Management Risk) Risk Breakdown

TOTAL DIRECT COSTS: $14,374,265.31

TOTAL CONTINGENCY BUDGET: $743,750.00

CONTINGENCY PERCENTAGE: 5.17% Safety

SAFETY

Our employees are valuable team members who continue to lead Dirty Suit Construction toward a successful pathway. Safety is an integral part of all operations. The health and safety of our employees and every worker on our jobsite is a top priority, so that they may go home to their families.

WHY US?

Dirty Suit Construction would be honored to lead in the construction of the Greenfield Bridge. We want to promote a team attitude throughout the construction of this project that commits the sincere and honest commitment to quality and safety. Emergency Response

● First aid kits are provided in the field office Required: First Aid Kit, Fire ● If Indication for need of care, outside local emergency Extinguisher, Telephone, Mobile responders will be called to the site. ● Employees with less severe injuries may be transported Telephone, Twoway Radio, Offsite by a fellow employee to the nearest medical care Telephone facility. ● All injuries /illnesses must immediately be reported to the site owner and supervisor POLICE Pittsburgh Police Department Zone 4 Station 5858 Northumberland Street Pittsburgh, PA 15217 FIRE DEPT Pittsburgh Fire Bureau Station 12, 4156 Winterburn Avenue Pittsburgh, PA 15207 AMBULANCE Pittsburgh Ambulance Service Medic 5 Allequippa Street, Pittsburgh, PA 15213 HOSPITALS •UPMC Mercy Hospital, Locust Street, Pittsburgh, PA •Emergency Department at Magee-Womens Hospital of UPMC, Craft Avenue, Pittsburgh, PA 15213 Historical Preservation

Architectural significance: Monuments removed, preserved and reinstalled Stored right there on site in pieces Originally 5 urns, 4 will be replaced back onto bridge Monuments go on the 4 corners of bridge Extra obelisks have been transferred to various locations: Market Square, Jefferson Memorial, and the island on Pocusset Street Acknowledgments

Allegheny County Department of Public Works: Joseph B. Fay Company Bryan Urbanec Jason Esser Jeanna Fisher Lee Ednie Mosites Construction: Michael Burdelsky Derrick Jeannerette John Gyure Amelie Construction: Jared Fasick PennDot: Scott Stonecheck Cory Shugats American Bridge Company: University of Pittsburgh Staff: Nick Greco John Oyler Jason Hoover John Sebastian Essroc Ready Mix: Brandon O‘Neil

HDR Engineering Inc. John Kennelly Questions? Appendix: