Quick viewing(Text Mode)

49107-006: West Bengal Drinking Water

49107-006: West Bengal Drinking Water

Environmental Monitoring Report

Project Number: 49107-006 Semestral Report (May–October 2020) December 2020

India: Drinking Water Sector Improvement Project

Main Report

Prepared by Project Management Unit, Government of West Bengal for Asian Development Bank.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Semi-Annual Environmental Monitoring Report

Project Number: 49107-006 Period: May 2020–October 2020 Submission Date: December 2020

IND: WEST BENGAL DRINKING WATER SECTOR IMPROVEMENT PROJECT (WBDWSIP)

VOL 1: MAIN REPORT

Prepared by Project Management Unit, Government of West Bengal for Asian Development Bank. This document is made publicly available in accordance with ADB’s Access to Information Policy and does not necessarily reflect the views of ADB.

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

WEST BENGAL DRINKING WATER SECTOR IMPROVEMENT PROJECT (WBDWSIP)

PROJECT MANAGEMENT UNIT

4th SEMI ANNUAL ENVIRONMENT MONITORING REPORT ADB Loan 3696-IND (Period May 2020 to October 2020)

December 2020

PUBLIC HEALTH ENGINEERING DEPARTMENT GOVT. OF WEST BENGAL

WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

TABLE OF CONTENTS

I. INTRODUCTION ...... 4 II. COMPLIANCE STATUS WITH NATIONAL/ STATE/ LOCAL SATATUTORY ENVIRONMENTAL REQUITREMENTS ...... 39 III. COMPLIANCE STATUS WITH ENVIRONMENTAL LOAN COVENANTS ...... 62 IV. COMPLIANCE STATUS WITH THE ENVIRONMENTAL MANAGEMENT PLAN ...... 67 V. APPROACH AND METHODOLOGY FOR ENVIRONMENTAL MONITORING OF THE PROJECT ...... 231 VI. MONITORING OF ENVIRONMENTAL IMPACTS ON PROJECT SURROUNDINGS 232 VII. SUMMARY OF KEY ISSUES AND REMEDIAL ACTIONS ...... 300

VOL I: APPENDICES- NORTH 24 PGS

VOL II: APPENDICES- BANKURA

VOL III: APPENDICES- EAST MEDINIPUR

1 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

ABBREVATIONS

AC - Asbestos Cement ADB - Asian Development Bank BOD - Biochemical Oxygen Demand COD - Chemical Oxygen Demand CPCB - Central Pollution Control Board CTE - Consent to Establish CTO - Consent to Operate DBO - Design Build Operate DSC - District Steering Committee DG - Diesel Generator DO - Dissolved Oxygen DSISC - Design, Supervision and Institutional Support Consultants EA - Executing Agency EARF - Environmental Assessment and Review Framework EHS - Environment, Health & Safety EIA - Environmental Impact Assessment EMP - Environmental Management Plan EMR - Environment Monitoring Report ESSR - Environment and Social Safeguard Unit GESI - Gender Equality and Social Inclusion GLSR - Ground Level Storage Reservoir GRC - Grievance Redressal Committee GRM - Grievance Redress Mechanism HDPE High Density Poly ethylene HSGO - Head Safeguards Gender Officer IEE - Initial Environmental Examination LOA - Letter of Acceptance LPG - Liquefied Petroleum Gas Ministry of Environment and Forest & Climate Change, Government MoEFCC - of NGO - Non-Government Organization NTP - Notice to Proceed OHR - Overhead Reservoir O&M - Operation and Maintenance PHED - Public Health Engineering Department PIU - Project Implementation Unit PMC - Project Management Consultant PMU - Project Management Unit PMx - Particulate Matter with size x micron PUC Pollution Under Control RF - Resettlement Framework RP - Resettlement Plan

2 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

SBR - Sundarban Biosphere Reserve SEMP - Site Environment Management Plan SGS - Safeguard and Gender Cell SPS - Safeguard Policy Statement TMP - Traffic Management Plan USD - US Dollar WBDWSIP - West Bengal Drinking Water Sector Improvement Project WBPCB - West Bengal Pollution Control Board WTP - Water Treatment Plant

3 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

I. INTRODUCTION

A. Background – Overall Project Description and Objective

1. Public Health Engineering Department (PHED), Govt of West Bengal (the Executing Agency) through its Project Management Unit and Project Implementing Unit is implementing the “West Bengal Drinking Water Sector Improvement Project” (WBDWSIP). The Loan for WBDWSIP (ADB Loan 3696- IND) was signed on 3rd October 2018 between Government of India and the Asian Development Bank. Government of India has agreed to make the proceeds of the loan available to the Government of West Bengal upon terms and conditions satisfactory to the Asian Development Bank.

2. WBDWSIP will be implemented over years between 2018 and 2024. Implementation of individual package works for 3 years after award of contract and Operation & Maintenance of 2 years after construction. In order to provide safe and sustainable drinking water as per the standards set by the Government of India, the Government of West Bengal through Government of India has requested Asian Development Bank for financing to create infrastructure and strengthen institutions of the PHED and the institutions of the identified districts, blocks, and villages for piped water supply. The selected areas identified are affected with arsenic, fluoride, and salinity in the districts of Bankura, North 24 Parganas and Purba Medinipur of West Bengal where around 1.65 million people are residing.

3. The project adopted a sector approach. All subprojects selected and proposed for funding adhering to the agreed subproject selection criteria for the project. The subprojects proposed under the project stem from a district-wide comprehensive water quality and sustainability planning and completion of the Drinking Water Quality Action Plan for the concerned district. The Drinking Water Quality Action Plan for the project districts supported by the project were prepared by the executing Contractor, the Public Health Engineering Department of the Government of West Bengal, with support of project preparatory consultants from the Asian Development Bank, and has been adopted by Public Health and Engineering Department to guide present and future drinking water improvement in the districts.

4. Total WBDWSIP investment envisaged is USD 349 million and based on 70% ADB financing. ADB’s loan would be USD (240+3) million ADB funding (Ordinary Capital Resources +Trust Fund) and 30% counterpart funding by Government of West Bengal would be around USD 106 million. The implementation period of WBDWSIP is from 2018 to 2024.

5. The impact of the project would ensure drinking water security in West Bengal as envisioned in Vision 2020 and national sub-mission on Arsenic and Fluoride to have an outcome of safe, sustainable, and inclusive drinking water service received in project districts. The outputs of the project are, ✓ Output 1: Climate resilient drinking water infrastructure constructed. ✓ Output 2: Institutions and capacity of stakeholders for drinking water service delivery strengthened

6. The following figures show the area covered under WBDWSIP works and the works proposed under WBDWSIP. .

4 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Figure 1: Arsenic, Fluoride and Salinity affected area

Figure 2: Location of District under the project

5 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Figure 3: Location of different Blocks under South and North 24 pgs

Figure 4A: Location of Two Work (Indpur & Taldangra) Blocks under Bankura District

6 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Figure 4B: Location of Two Work Blocks (Mejhia & Gangajalghati) under Bankura District

Figure 5: Water Supply infrastructure planned in East Medinipur District

7 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

B. Environmental category as per ADB Safeguard Policy Statement, 2009

7. Sub Projects under WBDWSIP has been classified by ADB as environmental assessment Category B (some negative impacts but less significant than category A) and the impacts of subprojects were assessed through Initial Environmental Examination (IEE), prepared according to ADB Safeguard Policy (SPS 2009).

C. Environmental category of each subproject as per national laws and regulations

8. None of the 10 subprojects (civil work contracts) under WBDWSIP are included in the list of projects requiring Environmental Clearance, therefore EIA and Environmental Clearance is not required. Under National rules no categorization is considered for water supply project.

D. Project Safeguards Team

9. Environment safeguard team for the project is given in Table 1.

Table 1: Project Safeguard Team Name Designation/Office Email Address Contact Number 1. PMU

Mr. Tanay Executive Engineer, Mechanical / [email protected] 9433484589 Banerjee Electrical Head Safeguards Gender Officer (HSGO), Safeguard Gender Cell (SGC) 2. PIUs

North 24 Parganas

Mr. Sourav Bose AE-III [email protected] 9434468635 Safeguard Officer (SO), Environmental and Social Safeguard Unit (ESSU) Bankura Mr. Dhiraj A.E. – I Safeguard Officer (SO), [email protected] 9038517645 Mondal Environmental and Social v.in Safeguard Unit (ESSU)

East Medinipur Mr. Tapash Bera AE-I [email protected] 8597245053 Environment Officer (EO), Environmental and Social Safeguard Unit (ESSU) 3. Consultants

PMC Dr. Ardhendu Environment Specialist [email protected] 9830415953 Mitra DSISC

North 24 pgs Mr. Swarnabha Env. Specialist [email protected] 8017668861

8 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Name Designation/Office Email Address Contact Number Bandyopadhyay Mr. Rohan Support Environment Safeguard, - [email protected] 7364804746 Kumar Junior Env. Scientist Mr. Prithwish Support Environmental Safeguard [email protected] 8373003438 Kumar Saha Bankura

Dr. Bidisha Environmental Specialist [email protected] 9830592875 Mukherjee Mr. Chandan Kr. Support Environment Safeguard [email protected] 8918611629 Majee East Medinipur

Mr. Partho Environmental Specialist [email protected] 7003881499 Sarathi Mukherjee Mr. Arpan Support Environmental Safeguard [email protected] 8017925978 Shome 10. Safeguard management system for the project is shown below.

Note: PMU – Project Management Unit; PMC – Project Management Consultant; DSISC – Design, Supervision and Institutional Support Consultant Figure 6: Safeguard Management system E. Overall project and sub-project progress and status

11. There are 10 work sub project packages under WBDWSIP. Summary of work contracts including type of contract (upto 31st October, 2020) is shown below.

Parameters DBO Type Contract Item Rate Contract Total Number of Packages 4 6 Contracts Executed/Completed 0 0 Contracts under Implementation 4 6 Bidding under Progress 0 0 Planning and Design 0 0

12. Other than that, of 10 civil work packages, there are 2 small packages of $3 million as grant from the Japan Fund for Poverty Reduction. Package (JFPR). They are (i) SAN/01: Pilot Faecal Sludge and Septage Management Plant and (ii) STWM/01: Smart Water Management:

9 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Gram Panchayat level smart water management equipment These 2 packages are under Smart Water Management for “Institutions and capacity of stakeholders for drinking water service delivery strengthened”. Till report period package SAN/01 has been awarded. Study location of the said package is under finalization. Preparation of IEE will be done after selection of construction locations and finalization of scope.

13. Table 2 shows the sub projects and the work packages including the status of award of contracts as on 31st October, 2020. The contract agreements for all 10 packages have been signed and project work was continued for 3 packages at North 24 pgs (N-24P/01, N-24P/02A & N-24P/02B), 4 packages at Bankura (BK/02A, BK/02B, BK/03 and BK/04) and 2 packages at East Medinipur (EM/01 and EM/02). Preliminary activities were started for one package at Bankura (BK/01).

Table 2: Summary status of Subprojects under WBDWSIP (on 31st October, 2020) Sr. Package No. Packages Status No. 1 WBDWSIP/DWW/ Design, Construction and Operation of Tendering process completed. N-24P/NCB/01/2017-18 Water Treatment Plant, Reservoirs, Agreement done on 14.12.2018 Transmission Mains and Pumping NTP issued on 11.01.2019 Stations works in Haroa, Rajarhat, and Bhangar II. 2 WBDWSIP/DWW/N-24P/ Design and Construction of Overhead Tendering process completed. NCB/02A/2017-18 Reservoir including design, supply and Agreement done on 11.10.2018 laying of Water Supply Distribution NTP issued on 05.12.2018 Network in Haroa Block. 3 WBDWSIP/DWW/NCB/ Design and Construction of Overhead Tendering process completed. N-24P/02B/2017-18 Reservoir including design, supply and Agreement done on 11.10.2018 laying of Water Supply Distribution NTP issued on 05.12.2018 Network in Bhangar II Block. 4 WBDWSIP/DWW/NCB/ Design, Construction and Operation- Tendering process completed. BK/01/2017-18 Maintenance of Raw Water Intake Agreement done on 22.01.2019 Well, Water Treatment Plant, NTP issued on 24.01.2019 Reservoir, Transmission Main for Indpur and Taldangra block in Bankura. 5 WBDWSIP/DWW/NCB/ Design and Construction of Tendering process completed. BK/02A/2018-19 Intermediate Pumping Station, ground Agreement done on 10.04.2019 storage reservoirs, overhead NTP issued on 27.05.2019 reservoirs, water distribution network and metering works in Indpur block. 6 WBDWSIP/DWW/NCB/ Design and Construction of Tendering process completed. BK/02B/2018-19 Intermediate Pumping Station, Agreement done on 10.04.2019 Secondary transmission mains, NTP issued on 27.05.2019 overhead reservoirs including water distribution network and metering works in Taldangra Block. 7 WBDWSIP/DWW/NCB/ Design, Construction and Operation- Tendering process completed. BK/03/2018-19 Maintenance of Raw Water Intake Agreement done on 10.04.2019 Well, Water Treatment Plant, Raw and NTP issued on 27.05.2019 Clear Water Transmission Main for Mejhia and Gangajalghati Block in Bankura. 8 WBDWSIP/DWW/NCB/ Design and Construction of Overhead Tendering process completed. BK/04/2018-19 Reservoir including Water Supply Agreement done on 10.04.2019

10 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Sr. Package No. Packages Status No. Distribution Network and Metering NTP issued on 27.05.2019 Works in Mejhia and Gangajalghati Blocks including Rehabilitation of Existing Schemes. 9 WBDWSIP/DWW/ICB/ Design, Construction and Operation- Tendering process completed. EM/01/2018-19 Maintenance of Raw Water Intake Agreement done on 03.02.2020 Well, Water Treatment Plant, Raw and NTP issued on 19.02.2020 Clear Water Transmission Main for Nandakumar, Chandpur, Nandigram-I and II blocks in East Medinipur. 10 WBDWSIP/DWW/ICB/ Construction of Intermediate Pumping Tendering process completed. EM/02/2018-19 Station, Secondary transmission Agreement done on 24.10.2019 mains, overhead tanks including water NTP issued on 07.11.2019. distribution network and metering works in Nandigram-I and Nandigram- II block in East Medinipur. 11 SAN/01 Pilot Faecal Sludge and Septage Contract awarded Management Plant under JFPR (small NTP issued on 06.12.2019 package) 12 STWM/01 Smart Water Management)/ Gram Not yet finalized Panchayat level smart water management equipment under JFPR (multiple packages)

14. For all awarded packages, contractors have been mobilized and works are in different stages of implementation. Photo illustration of project activities including training and consultations as well as good work practices are shown in Appendix I (North 24 pgs), II (Bankura) and III (East Medinipur).

F. Description of subprojects (package-wise) and status of implementation

15. Table 3 below shows implementation status of awarded sub project packages upto October 2020. List of submitted zone-wise SEMPs for the packages where final design has been completed are furnished in Table 3A.

16. After suspension of work from 23rd March 2020 for all the packages in the project districts (Ref. West Bengal Govt. order dated 22nd March 2020) due to COVID19 pandemic, the work for all the awarded packages has resumed slowly from 1st June, 2020. Official order from Government of West Bengal for suspension of work and Public Health Engineering Directorate (Govt. of West Bengal) for Resumption of Work of Water Supply Scheme after COVID-19 Pandemic attached below Table 3.

11 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Table 3: Status of Implementation of Sub project (31st October 2020) (After suspension of work due to COVID19 pandemic, the work for packages has resumed slowly from June, 2020) Package Number Components/List of Works Status of Implementation Contract Status If On-going Construction (Preliminary Design/Detailed (specify if under %Physical Expected Design/On-going bidding or contract Progress Completion Date Construction/Completed/O&M)1 awarded) WBDWSIP/DWW/ Design, Construction and Design: Hydraulic design, Soil Contract awarded 4.5 % 10.01.2022 + O & N-24P/NCB/01/2017-18 Operation of Water investigation, design of chemical M period* (Awarded to FFIL -RIL JV) Treatment Plant, house, Pile design for Reservoirs, Transmission Administrative building, Inlet well, Mains and Pumping Parshall flume, flash mixer and Stations works in Haroa, flocculator. Rajarhat, and Bhangar II. • Construction of WTP of Superstructure of flocculator, pile 100 MLD (22 MGD) design of Plate settler, MCC within existing WTP building, GA of CWR, pile caps complex at New Town, for inlet well, Parshall flume, flash Rajarhat mixer and flocculator. • Clear water transmission main of Construction: 4.9 km (1200 mm DI • . Chemical House – Completed pipe) from WTP to clear • Inlet Well - Super-structure – water reservoir at 2nd lift – Completed booster pumping station • Parshall Flume - Super- • Intermediate booster structure completed pumping station cum 1 • Flash Mixer - Super-Structure - GLSR of capacity 4600 2nd lift in Progress cum at Rajarhat, within • Flocculator - Super-structure - existing pumping station F1 & F2 2nd lift - in progress campus • Plate Settlers - Pile under • Boosting station cum progress (201/216) and Pile GLSRs of capacity 5000 Cap in progress cum and 3200 cum at • Filter Bed - Test Pile, Routine Bhangar II and Haroa Vertical Load Test PS-1 (P-16) respectively - Completed • SCADA Smart water • CWR cum PH - Piling (76/169) management work in progress

1 If on-going construction, include %physical progress and expected date of completion

12 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package Number Components/List of Works Status of Implementation Contract Status If On-going Construction (Preliminary Design/Detailed (specify if under %Physical Expected Design/On-going bidding or contract Progress Completion Date Construction/Completed/O&M)1 awarded) • Admin building – Super structure - Plinth beam in progress • Substation – Construction drawing. – released. • MCC Building - Design and Drawing Approved and work not yet started • Sludge Disposal – Handling philosophy - observation given. • CWRM - Final alignment received from WBHIDCO and Survey completed and finalization of Profile Drawing is in progress • Intake – Observation Provided on Mechanical GA and Pump. • BS-I at Newtown – Civil design in Progress. • Bagjola canal crossing – Structural Design Submitted. • Bidyadhari River crossing - Basic Engineering Data Shared WBDWSIP/DWW/N- Design and Construction of Detailed Design zone wise Contract awarded 28.89 % 04.12.2021 + O & 24P/NCB/02A/2017-18 Overhead Reservoir continued and construction M period* (Awarded to NCC Ltd) including design, supply and On-going laying of Water Supply Distribution Network in Design: Design of distribution Haroa Block. network of 19 zones, OHR survey Construction of overhead & layout plan of 14 zones, storage reservoir 21 nos. boundary wall of 14 zones, OHR (capacity 250 to 1000 m3) foundation design of 16 zones • Distribution network 851 km DI and HDPE pipes and superstructure of 9 zones, of dia 63 – 400 Chlorination cum SCADA building • Household service GA & Structural design of 8

13 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package Number Components/List of Works Status of Implementation Contract Status If On-going Construction (Preliminary Design/Detailed (specify if under %Physical Expected Design/On-going bidding or contract Progress Completion Date Construction/Completed/O&M)1 awarded) connection. zones, Super structure design of No.. of household 18 zones approx. -48,000 Construction: Pipe laying work • SCADA Smart water at 18 zones – 1 to 6, 8,10,12 to management 21 - ongoing, Foundation of boundary walls at 5 zones -1,2,12,15 and 17 - ongoing, SCADA cum Chlorination Room’s- 5 zones- 1,3,14, 15, 17 & 18

OHR construction at 13 zones – 1,2,3,6,8,12,13,14,15,16,17,18, 21 - ongoing Distribution pipe laid: 618.7 km out of 851 km Overhead Reservoir (OHR) construction stage: Zone-1: Side wall is in progress Zone-2: Side wall is in progress. Zone-3: Pile load test completed. Zone-6: Pile load test is in progress. Zone-8: PCC of pile cap is in progress. Zone-12: Side wall is in progress. Zone-13: Column above 2nd bracing is in progress. Zone-14: Top dome completed; stair is in progress. Zone-15: Side wall is in progress. Zone-16: Pile cap work is in progress Zone-17: Side wall is in progress.

14 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package Number Components/List of Works Status of Implementation Contract Status If On-going Construction (Preliminary Design/Detailed (specify if under %Physical Expected Design/On-going bidding or contract Progress Completion Date Construction/Completed/O&M)1 awarded) Zone-18: Heal beam and bottom dome completed. Zone-21: Pile cap work is in progress. WBDWSIP/DWW/NCB/ Design and Construction of Detailed Design zone wise Contract awarded 23.10 % 04.12.2021 + O & N-24P/02B/2017-18 Overhead Reservoir continued and construction M period* (Awarded to NCC Ltd) including design, supply and On-going laying of Water Supply Design: Design of distribution Distribution Network in network of 15 zones, OHR survey Bhangar II Block & layout plan of 14 zones, • Construction of boundary wall of 5 zones, OHR overhead storage foundation design of 5 zones and reservoir 18 nos... superstructure of 17 zones, .(capacity 300 to 1000 Chlorination cum SCADA building m3) Structural design of 5 zone • Distribution network 1063 km HDPE Construction: Pipe laying work • Household service at 15 zones - 1,3,4,6 to 17 - connection ongoing, No of household Foundation of boundary walls at 5 approx. -60000 zones -4,10,12,13,15 - ongoing, • SCADA Smart water OHR construction at 5 zones- management 4,10,12, 13 and 15- ongoing.

SCADA cum Chlorination Room’s- 2 zones- 4 and 13

Distribution pipe laid: 633.12 km out of 1063 km Overhead Reservoir (OHR) construction stage: Zone – 4: Top dome completed; Staircase is in progress Zone – 10: Half beam reinforcement and shuttering are

15 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package Number Components/List of Works Status of Implementation Contract Status If On-going Construction (Preliminary Design/Detailed (specify if under %Physical Expected Design/On-going bidding or contract Progress Completion Date Construction/Completed/O&M)1 awarded) in progress. Zone – 12: Columns above 3rd brace beam are complete Zone–13: Top dome completed; Staircase and plastering are in progress. Zone 15: Pilling work completed. Preparation for pipe load test continued WBDWSIP/DWW/NCB/ Design, Construction and Detailed Design and Contract awarded 0.0% 05.02.2022 + O & BK/01/2017-18 Operation-Maintenance of Preliminary activity continued M period* (Awarded to Technofab Raw Water Intake Well, • Finalization of Intake Well Engineering and SN Water Treatment Plant, and WTP locations done. Envirotech JV) Reservoir, Transmission • Layout plan for WTP– Main for Indpur and completed Taldangra block in Bankura. • Hydraulic Design competed • Construction of Intake for WTP. of 44MLD • Bathymetric Survey • Raw water pumping completed for construction of main from intake to intake well. WTP of approx. 3 km • Raw water analysis • Construction of completed. conventional WTP of 44 • Soil investigation work MLD at Khatra block completed for WTP and • Primary clear water GLSR. rising main of 21 km • Resistivity survey completed. • SCADA Smart water • Topographical Survey management completed. • Setting of site office and labour camp at Intake continued. Work started at WTP area, but work suspended due to some local issues. • Purchase of laboratory

16 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package Number Components/List of Works Status of Implementation Contract Status If On-going Construction (Preliminary Design/Detailed (specify if under %Physical Expected Design/On-going bidding or contract Progress Completion Date Construction/Completed/O&M)1 awarded) equipment done, yet to complete the set up.

WBDWSIP/DWW/NCB/ Design and Construction of Detailed Design zone wise Contract awarded 14.78% 26.05.2022+ O & BK/02A/2018-19 Intermediate Pumping continued and construction M period* (Awarded to L & T Ltd) Station, ground storage On-going reservoirs, overhead • Site office and laboratory set reservoirs, water distribution up completed. network and metering works • Topographical survey in Indpur block. completed. • Construction of • Geotechnical survey Intermediate booster completed. pumping station at • Design and drawing of clear Gobindapur in Indpur water transmission main block completed and approved. • Construction of • Design and drawing of Intermediate booster distribution network approved pumping station cum for 18 zones and rest under Ground level storage review. reservoirs (IBPS cum • Layout plan of OHSR has GLSR-II- 1400 KL) at approved for 15 zones. Raghunathpur in Indpur • Clear water transmission block main pipe line laid for 42.574 • Laying of transmission km. Pipe laying work in main of approx. 155.48 progress at following 12 km zones: • Construction of 19 1,2,3,10,11,12,13,14,15,16,1 overhead 8 and 20. reservoirs (OHRs) and • Distribution main pipe line associated works within laid for 267.768 km. Pipe the OHR premises laying work in progress at • Water supply following 18 zones: distribution network of 1,2,3,4,5,6,7,8,9, approx. 757 km 10,11,12,13,15,17,18,19 and • Providing of Household 20. service connection

17 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package Number Components/List of Works Status of Implementation Contract Status If On-going Construction (Preliminary Design/Detailed (specify if under %Physical Expected Design/On-going bidding or contract Progress Completion Date Construction/Completed/O&M)1 awarded) • Construction of overhead reservoir (OHSR) ongoing at following 10 Zones: 1, 2,3,5,6,10,11,13, 18 and 20. WBDWSIP/DWW/NCB/ Design and Construction of Detailed Design zone wise Contract awarded 16.51% 26.05.2022+ O & BK/02B/2018-19 Intermediate Pumping continued and construction M period* (Awarded to L & T Ltd) Station, Secondary On-going transmission mains, • Site office and laboratory set overhead reservoirs up completed. including water distribution • Topography survey network and metering works completed. in Taldangra Block. • Geotechnical survey • Intermediate booster completed pumping station cum • Design and drawing of clear ground level storage water transmission main reservoir (GLSR of completed and approved. capacity 1500 KL) at • Design and drawing of Chenchurya distribution main submitted & • Design of Transmission approved for all zones. mains including laying • Layout plan of OHSR of (rising) mains of approved for 18 zones and approx. 77.28 km. also for 1 IBPS. • Water supply • Transmission main pipe line distribution network of laid for 38.408 km. Pipe approx. 1091 km at 24 laying work in progress at zones following 9 zones: • 24 Overhead reservoirs 2,3,4,5,6,9,12,13 and 15. (OHR) and associated • Distribution main pipe line works within the OHR laid for 348.613 km. Pipe premises in laying work in progress at Taldangra Block following 20 zones: • Providing of Household 1,2,3,4,5,6,7,8, 9, 10, service connection 11,12,13,14,15, 17,20,21,23 and 24. • Construction of overhead

18 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package Number Components/List of Works Status of Implementation Contract Status If On-going Construction (Preliminary Design/Detailed (specify if under %Physical Expected Design/On-going bidding or contract Progress Completion Date Construction/Completed/O&M)1 awarded) reservoir (OHSR) ongoing at following 12 Zones i.e. 1, 3, 4,7, 10,11,13, 15,18,20, 23 and 24. WBDWSIP/DWW/NCB/BK/ Design, Construction and Detailed Design and Contract awarded 24.02% 26.05.2022+ O & 03/2018-19 Operation-Maintenance of Construction work continued M period* (Awarded to L & T Ltd) Raw Water Intake Well, • Site office established at Water Treatment Plant, WTP area. Raw and Clear Water • Bathymetric Survey Transmission Main for completed for construction of Mejhia and Gangajalghati intake well. Block in Bankura. • Topographical Survey • Raw water intake of 36 completed. MLD capacity will be • Geotechnical survey constructed at completed for Intake well & Nutangram mouza of WTP. Barjora Block with • Pipeline route survey arrangement for completed. housing pumping • Well Kerb sinking work in machineries progress at intake well. • Raw water transmission • Inlet system, electrical Main of 16.4 Km will be building, chlorination building, laid from Intake to boundary wall construction in Proposed WTP at progress at WTP. Basudebpur mouza of • Raw (5.046 km) and clear Gangajalghati Block. water transmission main • Water Treatment Plant (74.098 km) pipe line, total (WTP) of 36 Mld 79.144 km laid out of total capacity with booster 162 km. pumping facilities upto design period 2050 would constructed at Basudebpur mouza of Gangajalghati Block. • Clear Water Main of approx. 146 km will be

19 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package Number Components/List of Works Status of Implementation Contract Status If On-going Construction (Preliminary Design/Detailed (specify if under %Physical Expected Design/On-going bidding or contract Progress Completion Date Construction/Completed/O&M)1 awarded) laid from WTP to 34 nos. OHT of Mejhia & Gangajaghati Block WBDWSIP/DWW/NCB/ Design and Construction of Detailed Design zone wise Contract awarded 18.86% 26.05.2022+ O & BK/04/2018-19 Overhead Reservoir continued and construction M period* (Awarded to L & T Ltd) including Water Supply On-going Distribution Network and • Site office established at Metering Works in Mejhia Gangajalghati. and Gangajalghati Blocks • Topographical survey including Rehabilitation of completed Existing Schemes • Geotechnical survey • Construction of 30 completed for all 34 reservoir overhead reservoirs sites. (OHRs) in Mejia and • Household survey completed Gangajaghati Blocks for 30 zones., rest, under • Laying of approx. 1400 progress. km distribution network • Layout plan of OHSR • Provision of domestic completed for 20 No. of water meters for zones. household water • Construction of overhead connections with water reservoir (OHR) ongoing at meters. 16 Zones i.e. 1, 2, 3, 4, 5, 7, 8, 9, 11, 13, 15, 19, 20, 27, 28 and 32. • Distribution main pipe laying started at 26 zones. Total 302.556 km laid (out of 1650 km). WBDWSIP/DWW/ICB/ Design, Construction and Detailed design and Contract awarded 10.0% 05.03.2023 + O & EM/01/2018-19 Operation-Maintenance of Preliminary activity continued. M period* (Awarded to L & T Ltd) Raw Water Intake Well, Intake Jetty & Intake Water Treatment Plant, Substation: Raw and Clear Water • Bathymetric survey Transmission Main for completed by L&T in Nandakumar, Chandpur, Rupnarayan River & Nandigram-I and II blocks in Topographical survey in

20 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package Number Components/List of Works Status of Implementation Contract Status If On-going Construction (Preliminary Design/Detailed (specify if under %Physical Expected Design/On-going bidding or contract Progress Completion Date Construction/Completed/O&M)1 awarded) East Medinipur. substation completed. • Construction of Intake • Construction of Boundary system wall has already been started • Raw water rising main at intake sub-station. approx. 18 km Raw water rising main: • Water treatment plant • Topographical survey capacity 112 MLD completed & Alignment • Clear water rising main drawing and L-section approx. 133 km drawing is approved. • Pipe Supporting RCC • MS Pipe laying has just Bridge started. WTP: • Construction of boundary wall has started. WBDWSIP/DWW/ICB/ Construction of Intermediate Detailed Design and Contract awarded 6.5% 07.11. 2022 + O & EM/02/2018-19 Pumping Station, Preliminary activity continued M period* (Awarded to L & T Ltd) Secondary transmission • Footing of boundary wall has mains, overhead tanks started at Jambari, including water distribution Samsabad, Narasinghapur network and metering works Jalpai, Durgapur, in Nandigram-I and Manoharpur, Haripur and Nandigram-II block in East Manuchak Jalpai Medinipur. • HDPE pipe laying work has • 2 nos. IBPS – GLSR of started at Birulia, Bheturia, capacity 4300 and 2500 Kanakpur, Manoharpur, KL at Nandigram I and narasinghapur Jalpai and II respectively Gopalchak. • 20 new overhead reservoirs (OHRs) in Nandigram-I block and 9 new overhead reservoirs in Nandigram II block • Approx. 1707.7 km of distribution network: 651.7 km in Nandigram

21 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package Number Components/List of Works Status of Implementation Contract Status If On-going Construction (Preliminary Design/Detailed (specify if under %Physical Expected Design/On-going bidding or contract Progress Completion Date Construction/Completed/O&M)1 awarded) II and 1056 km in Nandigram I. • Providing domestic water meters

22 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Official order from Government of West Bengal for Suspension of Work Due to COVID-19

23 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

24 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Official order from Government of West Bengal Public Health Engineering Directorate for Resumption of Work of Water Supply Scheme after COVID-19 Pandemic

25 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

26 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

27 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

28 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

29 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

30 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Table 3A: Zone-wise Submitted SEMP Status for North 24 Parganas, Bankura and East Medinipur Packages North 24 Pgs: Package N24P/01 – Water Treatment Plant Zone Description Location Disclosed at Project website link till October 2020 Water Treatment Plant, Transmission main, Rajarhat, New Town http://wbdwsipmis.wbphed.gov.in/SEMP GLSR _N24PGS01.aspx

North 24 Pgs: Packageg-N24P/02A: HAROA BLOCK- 21 zones Overhead Gram Panchayat Name of Village Reservoir (OHR) Zone -1 Gopalpur-II Amta http://wbdwsipmis.wbphed.gov.in/SEMP _N24pgs02A_Z01_P_O.aspx Zone-2 Gopalpur -I Nebutala Abad http://wbdwsipmis.wbphed.gov.in/SEMP _N24PGS02A_Z02_P_O.aspx Zone – 3 Haroa Adampur http://wbdwsipmis.wbphed.gov.in/SEMP _N24PGS02A_Z03_O.aspx Zone – 6 Kulti Puratan Kamarganti http://wbdwsipmis.wbphed.gov.in/SEMP _N24PGS02A_Z06_O.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone-8 Khasbalanda Bantosa _N24PGS02A_Z08_O.aspx Zone -12 Bokjuri Parchandpur http://wbdwsipmis.wbphed.gov.in/SEMP _N24PGS02A_Z12_P_O.aspx Zone -13 Shalipur Chauhata http://wbdwsipmis.wbphed.gov.in/SEMP _N24PGS02A_Z13_O.aspx Zone-14 Shalipur Khalisadi http://wbdwsipmis.wbphed.gov.in/SEMP _N24PGS02A_Z14_O.aspx Zone -15 Salipur Jinkia http://wbdwsipmis.wbphed.gov.in/SEMP _N24PGS02A_Z15_P_O.aspx Zone – 16 Shalipur Haripur http://wbdwsipmis.wbphed.gov.in/SEMP _N24PGS02A_Z16_O.aspx Zone -17 Salipur-Borjuri Salipur http://wbdwsipmis.wbphed.gov.in/SEMP _N24pgs02A_Z17_P_O.aspx Zone -18 Gopalpur-I, Haroa- Gopalpur http://wbdwsipmis.wbphed.gov.in/SEMP Gopalupur-II _N24pgs02A_Z18_P_O.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone -21 Haroa Haroa _N24PGS02A_Z21_O.aspx Zone – 4 Kulti Laugachi To be submitted Zone – 5 Kulti Tegharia To be submitted Zone – 7 Kulti Kamarganti To be submitted Zone – 9 Sonapukur-Sankarpur Kalinagar To be submitted Zone – 10 Sonarpur-Sankarpur Baganti To be submitted Zone – 11 Borjuri Akandaberia To be submitted Zone -19 Haroa Khardah Chandpur To be submitted Zone -20 Khasbalanda Dakshin Ranigachhi To be submitted Haroa GLSR Sonapukur-Sankarpur Nazarnagar To be submitted

Distribution Gram Panchayat Remarks Network Zone -1 Gopalpur-II http://wbdwsipmis.wbphed.gov.in/SEMP _N24pgs02A_Z01_P_O.aspx

31 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Zone-2 Gopalpur -I http://wbdwsipmis.wbphed.gov.in/SEMP _N24PGS02A_Z02_P_O.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone-3 Haroa _N24PGS02A_Z03_P.aspx Zone -4 Kulti http://wbdwsipmis.wbphed.gov.in/SEMP _N24PGS02A_Z04_P.aspx Zone -5 Kulti http://wbdwsipmis.wbphed.gov.in/SEMP _N24pgs02A_Z05_P.aspx Zone -6 Kulti http://wbdwsipmis.wbphed.gov.in/SEMP _N24PGS02A_Z06_P.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone-8 Khasbalanda _N24PGS02A_Z08_P.aspx Zone-10 Sonarpur & Sankarpur http://wbdwsipmis.wbphed.gov.in/SEMP _N24PGS02A_Z10_P.aspx Zone -12 Bokjuri http://wbdwsipmis.wbphed.gov.in/SEMP _N24PGS02A_Z12_P_O.aspx Zone -13 Salipur http://wbdwsipmis.wbphed.gov.in/SEMP _N24PGS02A_Z13_P.aspx Zone -14 Salipur http://wbdwsipmis.wbphed.gov.in/SEMP _N24pgs02A_Z14_P.aspx Zone -15 Salipur http://wbdwsipmis.wbphed.gov.in/SEMP _N24PGS02A_Z15_P_O.aspx Zone-16 Salipur http://wbdwsipmis.wbphed.gov.in/SEMP _N24PGS02A_Z16_P.aspx Zone -17 Salipur-Borjuri http://wbdwsipmis.wbphed.gov.in/SEMP _N24pgs02A_Z17_P_O.aspx Zone -18 Gopalpur-I, Haroa- http://wbdwsipmis.wbphed.gov.in/SEMP Gopalupur-II _N24pgs02A_Z18_P_O.aspx Zone-19 Haroa http://wbdwsipmis.wbphed.gov.in/SEMP _N24PGS02A_Z19_P.aspx Zone – 20 Khasbalanda http://wbdwsipmis.wbphed.gov.in/SEMP _N24PGS02A_Z20_P.aspx Zone -21 Khasbalanda-Haroa http://wbdwsipmis.wbphed.gov.in/SEMP _N24pgs02A_Z21_P.aspx Zone -7 Kulti To be submitted Zone -9 Sonapukur-Sankarpur To be submitted Zone -11 Borjuri To be submitted

North 24 Pgs: Package-N24P/02B – BHANGAR II BLOCK- 18 Zones Overhead Gram Panchayat Name of Village Reservoir (OHR) http://wbdwsipmis.wbphed.gov.in/SEMP Zone -4 Polerhat-I Sastyangachhi _N24PGS02B_Z04_P_O.aspx Zone -10 Shanpukur Shanpukuria http://wbdwsipmis.wbphed.gov.in/SEMP _N24PGS02B_Z10_P_O.aspx Zone -12 http://wbdwsipmis.wbphed.gov.in/SEMP Bhogali-II Bankochua _N24PGS02B_Z12_P_O.aspx Zone -13 http://wbdwsipmis.wbphed.gov.in/SEMP Bhogali-II Baniara _N24PGS02B_Z13_P_O.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone -15 Chaltaberia Kachua _N24PGS02B_Z15_O.aspx Zone -1 Beonta-II Dharamtala Pancharia To be submitted Zone -2 Beonta-I Chadra Kanthalberia To be submitted

32 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Zone -3 Beonta-II Paikan To be submitted Zone -5 Polerhat-II Tona To be submitted Zone -6 Polerhat-II Shyamnagar To be submitted Zone -7 Polerhat-I Jaynagar To be submitted Zone -8 Uttar Shanpukur To be submitted Kashipur Zone -9 Bhogali-I Nagla Palpur To be submitted Zone -11 Shanpukur Dheyati To be submitted Zone -14 Bhogbanpur Pithapukuria To be submitted Zone -16 Chaltaberia Jawapur To be submitted Zone -17 Bhogali I Bhogali To be submitted Zone -18 Bamanghata Jothbhim To be submitted GLSR- Bhangar II Bhogbanpur Satuli To be submitted Distribution Gram Panchayat Remarks Network http://wbdwsipmis.wbphed.gov.in/SEMP Zone-1 Bamanghata & Benota -II _N24PGS02B_Z01_P.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone-3 Benota II _N24PGS02B_Z03_P.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone -4 Polerhat-I _N24PGS02B_Z04_P_O.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone 6 Polerhat-II – _N24PGS02B_Z06_P.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone-7 Polerhat-I _N24PGS02B_Z07_P.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone-8 Shan Pukur _N24PGS02B_Z08_P.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone -9 Bhogali-I _N24PGS02B_Z09_P.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone -10 Shanpukur _N24PGS02B_Z10_P_O.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone-11 Sanpukur _N24PGS02B_Z11_P.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone -12 Bhogali-II _N24PGS02B_Z12_P_O.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone -13 Bhogali-II _N24PGS02B_Z13_P_O.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone -14 Bhagabanpur _N24PGS02B_Z14_P.aspx Bhagbanpur and http://wbdwsipmis.wbphed.gov.in/SEMP Zone-15 Chaltaberia _N24PGS02B_Z15_P.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone -16 Chaltaberia _N24PGS02B_Z16_P.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone 17 Bhogali – _N24PGS02B_Z17_P.aspx Zone -2 Beonta-I To be submitted Zone -5 Polerhat-II To be submitted Zone -18 Bamanghata To be submitted

http://wbdwsipmis.wbphed.gov.in/update Bankura: Package BK/01 INDPUR TALDANGRA BLOCK d_1_IEE_Bankura_Bk01_Nov2020.aspx for Intake, WTP, Raw and Clear water transmission main (Part of IEE for Bk 01)

33 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Bankura: Package BK/02A- INDPUR BLOCK- 20 Zones Transmission Main Gram Panchayat Name of Village Zone 1 (OHR, Hatagram Uttarkendabona http://wbdwsipmis.wbphed.gov.in/SEMP Distribution) _BK02A_Z01_O_P.aspx Zone 2 (OHR, Hatagram http://wbdwsipmis.wbphed.gov.in/SEMP Hatagram Distribution) _BK02A_Z02_O_P.aspx Zone 3 (OHR, Hatagram Surulia http://wbdwsipmis.wbphed.gov.in/SEMP Distribution) _BK02A_Z03_O_P.aspx Zone 5 (OHR, Gottayara http://wbdwsipmis.wbphed.gov.in/SEMP Brahmandiha Distribution) _BK02A_Z05_O_P.aspx Zone 6 (OHR, Chaukighata http://wbdwsipmis.wbphed.gov.in/SEMP Raghunathpur Distribution) _BK02A_Z06_O_P.aspx Zone 8 (OHR, Chakaltor http://wbdwsipmis.wbphed.gov.in/SEMP Indpur Distribution) _BK02A_Z08_O_P.aspx Zone 9 (OHR, Indpur Kantakuli http://wbdwsipmis.wbphed.gov.in/SEMP Distribution) _BK02A_Z09_O_P.aspx Zone 10 (OHR, Indpur Nayekhir http://wbdwsipmis.wbphed.gov.in/SEMP Distribution) _BK02A_Z10_O_P.aspx Zone 11 (OHR, Indpur Siromanipur http://wbdwsipmis.wbphed.gov.in/SEMP Distribution) _BK02A_Z11_O_P.aspx Zone 12(OHR, Indpur Maukuri http://wbdwsipmis.wbphed.gov.in/SEMP Distribution) _BK02A_Z12_O_P.aspx Zone 13(OHR, Gourbazar Bholarkhap http://wbdwsipmis.wbphed.gov.in/SEMP Distribution) _BK02A_Z13_O_P.aspx Zone 14 (OHR, Gourbazar Dumurtor http://wbdwsipmis.wbphed.gov.in/SEMP Distribution) _BK02A_Z14_O_P.aspx Zone 18 (OHR, Bheduasole Tunamara http://wbdwsipmis.wbphed.gov.in/SEMP Distribution) _BK02A_Z18_O_P.aspx Zone 20 (OHR, Bheduasole Golakpur http://wbdwsipmis.wbphed.gov.in/SEMP Distribution) _BK02A_Z20_O_P.aspx Zone 16 Belasuli-Shyamsundarpur http://wbdwsipmis.wbphed.gov.in/SEMP (Transmission Main) _BK02A_Z16_CWRM_P.aspx

(OHR & Distribution Main under BK 2B) Zone 4 (OHR, Brahmandiha Brahmandiha To be submitted Distribution) Zone 7 (OHR, Raghunathpur Raghunathpur To be submitted Distribution) Zone 15 Brajarajpur Goaldanga To be submitted (Distribution) Zone 16 (OHR, Brajarajpur Gunnath To be submitted Distribution) Zone 17 (OHR, Brajarajpur Jugibad To be submitted Distribution) Zone 19 (OHR, Bheduasole Saluka To be submitted Distribution)

Bankura: Package BK/02B- TALDANGRA BLOCK- 24 Zones Overhead Gram Panchayat Name of Village Reservoir Zones Zone 1(OHR, http://wbdwsipmis.wbphed.gov.in/SEMP Amdangra Amdangra Distribution) _BK02B_Z01_O_P.aspx Zone 3 (OHR, Saltora Koniara http://wbdwsipmis.wbphed.gov.in/SEMP

34 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Distribution) _BK02B_Z03_O_P.aspx Zone 4 (OHR, http://wbdwsipmis.wbphed.gov.in/SEMP Satmouli Chandabila Distribution) _BK02B_Z04_O_P.aspx Zone 7 (OHR, http://wbdwsipmis.wbphed.gov.in/SEMP Saltora Saltora/ Chakmajuriprasadpur Distribution) _BK02B_Z07_O_P.aspx Zone 9 (OHR, http://wbdwsipmis.wbphed.gov.in/SEMP Pachmura Dhobajora Distribution) _BK02B_Z09_O_P.aspx OHR: http://wbdwsipmis.wbphed.gov.in/SEMP Zone 10 (OHR, _BK02B_Z10_O.aspx Saharghati Saharghati Distribution) Pipeline: http://wbdwsipmis.wbphed.gov.in/SEMP _BK02B_Z10_P.aspx Zone 11 (OHR, http://wbdwsipmis.wbphed.gov.in/SEMP Fulmati Manikmara Distribution) _BK02B_Z11_O_P.aspx Zone 13 (OHR, http://wbdwsipmis.wbphed.gov.in/SEMP Fulmati Fulmati Distribution) _BK02B_Z13_O_P.aspx Zone 15 (OHR, http://wbdwsipmis.wbphed.gov.in/SEMP Taldangra Bendalaxmanpur Distribution) _BK02B_Z15_O_P.aspx OHR: http://wbdwsipmis.wbphed.gov.in/SEMP Zone 18 (OHR, _BK02B_Z18_O.aspx Hamasra Hamasra Distribution) Pipeline: http://wbdwsipmis.wbphed.gov.in/SEMP _BK02B_Z18_P.aspx Zone 20 (OHR, http://wbdwsipmis.wbphed.gov.in/SEMP Khalgram Manipur Distribution) _BK02B_Z20_O_P.aspx Zone 23 (OHR, http://wbdwsipmis.wbphed.gov.in/SEMP Bibarda Bhutmaheshpur Distribution) _BK02B_Z23_O_P.aspx Zone 2(OHR, Amdangra Rajpur To be submitted Distribution) Zone 5 (OHR, Satmouli Moulberia To be submitted Distribution) Zone 6 (OHR, Satmouli Dauni To be submitted Distribution) Zone 8 (OHR, Panchmura Panchmura To be submitted Distribution) Zone 12 (OHR, Fulmati Asnasundarpur To be submitted Distribution) Zone 14 (OHR, Taldangra Chenchuriya To be submitted Distribution) Zone 16 (OHR, Taldangra Belasuli Shyamsundarpur To be submitted Distribution) Zone 17 (OHR, Harmasra Khichka To be submitted Distribution) Zone 19 (OHR, Taldangra Sushunia To be submitted Distribution) Zone 21 (OHR, Khalgram Pedda To be submitted Distribution) Zone 22 (OHR, Bibarda Bibarda To be submitted Distribution) Zone 24 (OHR, Bibarda Dhengashimul To be submitted Distribution)

35 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Bankura: Package BK/03 MEJIA GANGAJALGHATI BLOCK http://wbdwsipmis.wbphed.gov.in/SEMP for Intake, WTP, Raw and Clear water transmission main _BK03.aspx

Bankura: Package BK/04 MEJIA-GANGAJALGHATI BLOCK- 34 Zones Overhead Gram Panchayat Name of Village Reservoir Zones Zone 2 (OHR) Sagariya http://wbdwsipmis.wbphed.gov.in/SEMP Lachmanpur _BK04_Z02_O.aspx Zone 3 (OHR, http://wbdwsipmis.wbphed.gov.in/SEMP Bhaktabundh Haribhanga Distribution) _BK04_Z03_O_P.aspx Zone 4(OHR) Ranganathpu http://wbdwsipmis.wbphed.gov.in/SEMP Bhaktabundh _BK04_Z04_O.aspx Zone 5 (OHR, http://wbdwsipmis.wbphed.gov.in/SEMP Bhaktabundh Lakhiyara Distribution) _BK04_Z05_O_P.aspx Zone 6 (OHR, http://wbdwsipmis.wbphed.gov.in/SEMP Gobindadham Arbat Distribution) _BK04_Z06_O_P.aspx Zone 7 (OHR, Pirrabani Pirrabani http://wbdwsipmis.wbphed.gov.in/SEMP Distribution) _BK04_Z07_O_P.aspx Zone 9(OHR) Kapistha Kapistha http://wbdwsipmis.wbphed.gov.in/SEMP _BK04_Z09_O.aspx Zone 11(OHR) Gobindadham Machaparulia http://wbdwsipmis.wbphed.gov.in/SEMP _BK04_Z11_O.aspx Zone 12 (OHR, Nityanandapur Sarangapur http://wbdwsipmis.wbphed.gov.in/SEMP Distribution) _BK04_Z12_O_P.aspx Zone 13 (OHR, Nityanandapur Bankadaha http://wbdwsipmis.wbphed.gov.in/SEMP Distribution) _BK04_Z13_O_P.aspx Zone 15 (OHR, Lachmanpur Lachmanpur http://wbdwsipmis.wbphed.gov.in/SEMP Distribution) _BK04_Z15_O_P.aspx Zone 17 (OHR, Pirrabani Ramkanali http://wbdwsipmis.wbphed.gov.in/SEMP Distribution) _BK04_Z17_O_P.aspx Zone 19 (OHR, Gobindadham Gobindadham OHR: Distribution)) http://wbdwsipmis.wbphed.gov.in/SEMP _BK04_Z19_O.aspx Pipeline: http://wbdwsipmis.wbphed.gov.in/SEMP _BK04_Z19_P.aspx Zone 20 (OHR, Banasuriya ChotoNabagram OHR: Distribution) http://wbdwsipmis.wbphed.gov.in/SEMP _BK04_Z20_O.aspx Pipeline: http://wbdwsipmis.wbphed.gov.in/SEMP _BK04_Z20_P.aspx Zone 22 (OHR, http://wbdwsipmis.wbphed.gov.in/SEMP Barsal Barsal-Srirampur Distribution) _BK04_Z22_O_P.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone 27 (OHR) Ardhadgram Mohona _BK04_Z27_O.aspx http://wbdwsipmis.wbphed.gov.in/SEMP Zone 28 (OHR) Banjora Purbatore _BK04_Z28_O.aspx Zone 31 (OHR, http://wbdwsipmis.wbphed.gov.in/SEMP Kustore Benabad Distribution) _BK04_Z31_O_P.aspx Zone 32 (OHR, http://wbdwsipmis.wbphed.gov.in/SEMP Kustore Pairasol Distribution) _BK04_Z32_O_P.aspx Zone1 (OHR, To be submitted Lachmanpur Rajamela Distribution)

36 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Zone 2 (Pipeline) Lachmanpur Sagariya To be submitted Zone 4(Pipeline) Bhaktabundh Ranganathpu To be submitted Zone 8 (OHR, Kapistha Kallapur To be submitted Distribution) Zone 9(Pipeline) Kapistha Kapistha To be submitted Zone 10 (OHR, Gangajalghati Gangajalghati To be submitted Distribution) Zone 11(Pipeline) Gobindadham Machaparulia To be submitted Zone 14 (OHR, Nityanandapur Subiara To be submitted Distribution) Zone 16 (OHR, Banasurya Banasurya To be submitted Distribution) Zone 18(OHR, Latiabani Deuli To be submitted Distribution) Zone 21 (OHR, Barsal Basudevpur To be submitted Distribution) Zone 23 (OHR, Latiabani Benagari To be submitted Distribution) Zone 24

(Distribution) Zone 25 To be submitted Kesiyara Gamgajalghati (Distribution) Zone 26 (OHR, Mejhia Mejhia To be submitted Distribution) Zone 27 Ardhadgram Mohona To be submitted (Distribution) Zone 28 Banjora Purbatore To be submitted (Distribution) Zone 29 (OHR, Ramchandrapur Mochakend To be submitted Distribution) Zone 30 (OHR, To be submitted Ramchandrapur Ranipur Distribution) Zone 33 To be submitted Bharrah Ramchandrapur (Distribution) Zone 34 To be submitted Jemua Mejhia (Distribution

East Medinipur: Package EM/01 http://wbdwsipmis.wbphed.gov.in/update Raw Water Intake Well, Water Treatment Plant, Raw and Clear Waterd_1_IEE_E_Medinipur_EM01_Nov2020. Transmission Main aspx (Part of IEE for EM 01)

East Medinipur: Package EM/02 – NANDIGRAM I AND NANDIGRAM II BLOCK- 29 zones NANDIGRAM I BLOCK- 20 Zones Overhead Gram Panchayat Name of Village Reservoir Zone 1 Sonachura Gangra http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z01_Nandi1_O.aspx Zone 5 Samsabad Samsabad http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z05_Nandi1_O.aspx Zone 6 Gokulnagar Gokulnagar http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z06_Nandi1_O.aspx

37 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Zone 7 Gokulnagar Jambari http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z07_Nandi1_O.aspx Zone 8 Naynan Daudpur http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z08_Nandi1_O.aspx Zone 9 Dautpur Marisdanga http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z09_Nandi1_O.aspx Zone 10 Vekutia Durgapur http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z10_Nandi1_O.aspx Zone 11 Bhekutia Dinabandhupur http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z11_Nandi1_O.aspx Zone 12 Bhekutia Manuchak Jalpai http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z12_Nandi1_O.aspx Zone 13 Mahammadpur Parbatipur http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z13_Nandi1_O.aspx Zone 18 Nandigram Nandigram CT http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z18_Nandi1_O.aspx Zone 19 Haripur Haripur http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z19_Nandi1_O.aspx Zone 20 Haripur Banashree Gouri http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z20_Nandi1_O.aspx Zone 2 Kalicharanpur Garchakraberia To be submitted Zone 3 Kalicharanpur Kalicharanpur To be submitted Zone 4 Samsabad Chak Chilinga To be submitted Zone 14 Mohammadpur Purushottampur To be submitted Zone 15 Kendamari Jalpai Kendamari Jalpai To be submitted Zone 16 Kendamari Jalpai Bhasurkata To be submitted Zone17 Nandigram Tajpur To be submitted Distribution Gram Panchayat Name of Village Network Zone 7 Gokulnagar Jambari http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z07_Nandi1_P.aspx Zone 10 Bhekutia Durgapur http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z10_Nandi1_P.aspx Zone 13 Mahammadpur Parbatipur http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z13_Nandi1_P.aspx Zone 1 Sonachura Gangra Zone 2 Kalicharnapur Gar Chakraberia To be submitted Zone 3 Kalicharnapur Kalicharanpur To be submitted Zone 4 Samsabad Chak Chilinga To be submitted Zone 5 Samsabad Samsabad To be submitted Zone 6 Gokulnagar Gokulnagar To be submitted Zone 8 Daudpur Naynan To be submitted Zone 9 Daudpur Marisdanga To be submitted Zone 11 Bhekutia Dinabandhupur To be submitted Zone 12 Bhekutia Manuchak Jalpai To be submitted Zone 14 Mahammadpur Purushottampur To be submitted Zone 15 Kendamari Jalpai Kendimarai Jalpai To be submitted Zone 16 Kendamari Jalpai Bhasurkata To be submitted Zone 17 Nandigram Tajpur To be submitted Zone 18 Nandigram Nandigram CT To be submitted Zone 19 Haripur Haripur To be submitted

38 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Zone 20 Haripur Banasri Gauri To be submitted NANDIGRAM II BLOCK- 9 zones Overhead Gram Panchayat Name of Village Reservoir Zone 3 Gholpukuria Birulia http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z03_Nandi2_O.aspx Zone 7 Boyal-I Kanakpur http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z07_Nandi2_O.aspx Zone 8 Boyal II Narasinghapur Jalpai http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z08_Nandi2_O.aspx Zone 1 Amdabad II Kamalpur To be submitted Zone 2 Amdabad I Amdabad To be submitted Zone 4 Birulia Hanu Bhunya To be submitted Zone 5 Bheturia Bheturia To be submitted Zone 6 Reyapara Manoharpur To be submitted Zone 9 Boyal-II Gopalchak To be submitted Distribution Gram Panchayat Name of Village Network Zone 1 Amdabad II Kamalpur http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z01_Nandi2_P.aspx Zone 2 Amdabad I Amdabad http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z02_Nandi2_P.aspx Zone 3 Birulia Birulia http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z03_Nandi2_P.aspx Zone 4 Birulia Hanu Bhunya http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z04_Nandi2_P.aspx Zone 5 Bheturia Bheturia http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z05_Nandi2_P.aspx Zone 6 Reyapara Manoharpur http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z06_Nandi2_P.aspx Zone 7 Boyal-I Kanakpur http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z07_Nandi2_P.aspx Zone 8 Boyal-I Narasinghapur Jalpai http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z08_Nandi2_P.aspx Zone 9 Boyal-II Gopalchak http://wbdwsipmis.wbphed.gov.in/SEMP _EM02_Z09_Nandi2_P.aspx II. COMPLIANCE STATUS WITH NATIONAL/ STATE/ LOCAL SATATUTORY ENVIRONMENTAL REQUITREMENTS

17. For implementation of the project both national and state rules & regulations need to be followed. Table 4 below indicates environment legal compliance status for the awarded projects under WBDWSIP.

18. Before and during implementation of the project, compliance with environmental policy, law and legislation is necessary.

19. Present status of Environment, forest and other clearances are mentioned below.

39 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Table 4: National/State/Local Statutory Environmental Requirements Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 WBDWSIP/DWW/ Design, The EIA notification, 2006 The sub project is not Not Applicable None NA N-24P/NCB/01/2017-18 Construction and (and its subsequent covered in the ambit of (NA) Operation of amendments in 2009) the EIA notification, as Water Treatment provides for categorization of this is not covered under Plant, Reservoirs, projects into category A and either Category A or Transmission B, based on extent of impact Category B of the Mains and notification. As a result, Pumping Stations the categorization, and works in Haroa, the subsequent Rajarhat, and environmental Bhangar II assessment and clearance requirements, either from the state or the central Government is not triggered. Environmental Clearance is not required for the proposed project Water (Prevention and CTE for WTP was Validity upto Should obtain Ambient noise level shall Control of Pollution) Act of obtained from West 30.11.2026 CTO prior to not exceed permissible 1974, Rules of 1975, and Bengal Pollution operation of WTP limit amendments Control Board, attached Monitoring & Compliance During implementation as Appendix I - 6 status – specific and (construction phase) general condition of CTE compliance will be required attached in Appendix I - Consent to Establish (CTE) 6 has to be received from West Bengal Pollution Control Board (WBPCB) for new WTP The Air (Prevention and No establishment of NA CTE & CTO will To be updated in next

2 Specify (environmental clearance? Permit/consent to establish? Forest clearance? Etc.) 3 Specify if obtained, submitted and awaiting approval, application not yet submitted 4 Example: Environmental Clearance requires ambient air quality monitoring, Forest Clearance/Tree-cutting Permit requires 5 trees for every tree, etc.

40 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 Control of Pollution) Act 1981, diesel generator/s, Hot be collected as SEMR when the consent amended 1987 and The Air mix plants, wet mix per requirement is Obtained (if required) (Prevention and Control of plants, stone crushers, and with Pollution) Rules, 1982 advancement of During implementation project (construction phase) Conditions shown in CTE compliance will be required CTE received for Validity upto Compliance of of Batching plant. CTE and CTO for diesel Batching Plant. 17.03.2027 condition. But till Monitoring of emission – generator/s, Hot mix plants, Attached in Appendix I - report period liquid and gaseous is wet mix plants, stone 6 Batching plant required. Compliance crushers, batching plant etc. if not functioning. statement will be installed for construction. Before start prepared and submit in functioning, CTO next SEMR. needs to be obtained.

Pollution under control PUC obtained (sample Validity upto PUC certificate NA certificate (PUC) to be attached in Appendix I - January 2021 will be collected obtained by the contractor for 2) for new vehicle- all vehicles and equipment equipment if any. engaged in the project Also, renewal will be required as per validity Direction of West Bengal Construction activities are NA To be maintained NA Department of Environment being carried out in under the Air Act, 1981 compliance with the Direction No. EN/3170/T-IV-7 requirements /001/2009 dated: 10 December 2009 The Indian Forest Act, 1927; No forest land is involved. NA None NA Forest (Conservation) Act, 1980, amended 1988; Forest (Conservation) Rules, 1981 amended 1992 and 2003

West Bengal Trees No tree felling till date To be updated Till report period (Protection and Conservation if any tree no tree felling is

41 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 in Non- Forest Areas) Act, felling required. Tree 2006- Tree felling permission required felling NOC will be obtained if In case of tree felling NOC required with needs to be obtained from advancement of Forest dept./ concerned dept. work Wild Life (Protection) Act No Wildlife protected area NA None NA 1972, Amendment Act, 1993 within or nearby the and 2002 and Wildlife project area (Protection) Rules, 1995 The Ancient Monument and No protected area within NA Chance find NA Archaeological Sites and or nearby the project protocol to be Remains (Amendment and area. But chance find maintained Validation) Act 2010 protocol will be maintained Labour licence under The Complied Valid upto To comply with NA Contract Labour (Regulation Labour licence obtained 18.05.2021 the requirements & Abolition) Act, 1970. and enclosed as as specified in (Central Act w.e.f. 07-09-70) Appendix I - 3 the issued license. Labour compensation Complied Valid upto To ensure all NA insurance Worker compensation 31.03.2021 potential risks are insurance policy obtained covered. and attached as Appendix I - 4

WBDWSIP/DWW/N-24P/ Design and The EIA notification, 2006 The sub project is not NA None NA NCB/02A/2017-18 Construction of (and its subsequent covered in the ambit of Overhead amendments in 2009) the EIA notification, as Reservoir provides for categorization of this is not covered under including design, projects into category A and either Category A or supply and laying B, based on extent of impact Category B of the of Water Supply notification. As a result, Distribution the categorization, and Network in Haroa the subsequent Block. environmental assessment and

42 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 clearance requirements, either from the state or the central Government is not triggered. Environmental Clearance is not required for the proposed project Water (Prevention and Complied as per NA None NA Control of Pollution) Act of requirement and in line of 1974, Rules of 1975, and rules. amendments Protection of water body continued at project site During implementation (construction phase) compliance will be required The Air (Prevention and CTE & CTO will be NA CTE to be To be updated in next Control of Pollution) Act 1981, collected as per obtained as per SEMR as and when the amended 1987 and The Air requirement and with requirement consent is obtained (as (Prevention and Control of advancement of project - CTO to be per requirement) Pollution) Rules, 1982 Till report period not obtained before required commencement During implementation Diesel Generators used of operations. (construction phase) are of less than 5 kVA, - compliance will be required CTE & CTO not required CTE and CTO for (i) diesel generator/s and (ii) hot mix plants, wet mix plants, stone crushers, batching plant etc. if installed for construction. Pollution under control PUC certificate has been Validity period Timely renewal certificate (PUC) to be collected (sample varied from will be required obtained by the contractor for attached as --- Appendix December all vehicles and equipment I - 2) 2020 to engaged in the project August 2021 Direction of West Bengal Construction activities are NA None NA Department of Environment being carried out in under the Air Act, 1981 compliance with the

43 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 Direction No. EN/3170/T-IV-7 requirements /001/2009 dated: 10 December 2009 The Indian Forest Act, 1927; No forest land is involved. NA Forest (Conservation) Act, 1980, amended 1988; Forest (Conservation) Rules, 1981 amended 1992 and 2003

West Bengal Trees Complied. (Protection and Conservation Tree felling (11 nos.) Tree felling NOC in Non- Forest Areas) Act, NOC obtained for for other sites if 2006- Tree felling permission Gopalpur OHR site (See required as per Appendix I - 5) final design and In case of tree felling NOC advancement of needs to be obtained from Report of Log is work Forest dept./ concerned dept. submitted by Panchayet office to PIU which is reverted to DFO. As a compensation, 55 trees of multiple variety are planted in the site. Compliance status including plantation photos also attached as Appendix I - 5. Wild Life (Protection) Act No Wildlife protected area NA None NA 1972, Amendment Act, 1993 within or nearby the and 2002 and Wildlife project area (Protection) Rules, 1995 Protection of land under NOC received from NA None NA Sundarban Biosphere Director Sundarban Reserve (SBR) Biosphere Reserve on 5th March 2019 indicating non requirement of any clearance from SBR authority since no forest

44 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 area involved under the package (Copy attached as Appendix 7A) The Ancient Monument and No protected area within NA Chance find NA Archaeological Sites and or nearby the project protocol to be Remains (Amendment and area. But chance find maintained Validation) Act 2010 protocol will be maintained Labour licence under The Complied. Valid upto To comply with NA Contract Labour (Regulation Labour licence obtained 04.12.2020 the requirements & Abolition) Act, 1970. and enclosed as as specified in (Central Act w.e.f. 07-09-70) Appendix I - 3 the issued license. Labour compensation Complied. Renewed. To ensure all NA insurance Worker compensation Valid upto potential risks are insurance policy obtained 20.02.2021 covered. and attached as Appendix I - 4

WBDWSIP/DWW/NCB/ Design and The EIA notification, 2006 The sub project is not NA None NA N-24P/02B/2017-18 Construction of (and its subsequent covered in the ambit of Overhead amendments in 2009) the EIA notification, as Reservoir provides for categorization of this is not covered under including design, projects into category A and either Category A or supply and laying B, based on extent of impact Category B of the of Water Supply notification. As a result, Distribution the categorization, and Network in the subsequent Bhangar II Block. environmental assessment and clearance requirements, either from the state or the central Government is not triggered. Environmental Clearance is not required for the proposed project

45 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 The Air (Prevention and CTE & CTO will be NA CTE to be To be updated in next Control of Pollution) Act 1981, collected as per obtained prior to SEMR as and when the amended 1987 and The Air requirement and with start of consent is obtained as (Prevention and Control of advancement of project- construction. per requirement Pollution) Rules, 1982 Till report period not required CTO to be During implementation obtained before (construction phase) Diesel Generators used commencement compliance will be required are of less than 5 kVA, - of operations. CTE and CTO for (i) diesel CTE & CTO not required generator/s and (ii) hot mix plants, wet mix plants, stone crushers, batching plant etc. if installed for construction. PUC certificate has been Validity period Timely renewal Pollution under control collected (sample varied from will be required certificate (PUC) to be attached as ---Appendix I December obtained by the contractor for - 2) 2020 to all vehicles and equipment August 2021 engaged in the project Direction of West Bengal Construction activities are NA None NA Department of Environment being carried out in under the Air Act, 1981 compliance with the Direction No. EN/3170/T-IV-7 requirements /001/2009 dated: 10 December 2009 The Indian Forest Act, 1927; No forest land is involved. NA Tree felling NOC To be updated tree felling Forest (Conservation) Act, if required as per status and NOC in next 1980, amended 1988; Forest No tree felling required till final design and SEMR as per (Conservation) Rules, 1981 date advancement of requirement amended 1992 and 2003 work

West Bengal Trees (Protection and Conservation in Non- Forest Areas) Act, 2006- Tree felling permission

In case of tree felling NOC

46 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 needs to be obtained from Forest dept./ concerned dept. Wild Life (Protection) Act No Wildlife protected area NA None NA 1972, Amendment Act, 1993 within or nearby the and 2002 and Wildlife project area (Protection) Rules, 1995 Protection of land under NOC received from NA No action NA Sundarban Biosphere Director Sundarban required Reserve (SBR) Biosphere Reserve on 5th March 2019 indicating non requirement of any clearance from SBR authority since no forest area involved under the package (Copy attached as Appendix I - 7) East Kolkata Wetland Zone 1, 2, and 18 falls Valid upto OHR sites for 2 Site observation/ (Conservation and within EKW area hence 31.12.2021 and 18 of monitoring to check, Management) Act, 2006 prior permission/ NOC Bhangar-II block • No construction of This legislation regulates all should be obtained from have been permanent structure activities within the notified the East Kolkata relocated outside • No filling of water area of East Kolkata Management Authority the EKWMA body Wetlands. for laying water area. At Zone-1, • No change in distribution pipe Bhangar II characteristics of networks within EKW Distribution will land area. be done using • No discharge of NOC received on control valves effluent, waste in the 08.01.2020 for laying of water body pipes. Appendix I - 8 shows NOC from EKW Management Authority The Ancient Monument and No protected area within NA Chance find NA Archaeological Sites and or nearby the project protocol to be Remains (Amendment and area. But chance find maintained Validation) Act 2010 protocol will be maintained

47 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 Labour licence under The Complied Valid upto To comply with NA Contract Labour (Regulation Labour licence obtained 26.12.2020 the requirements & Abolition) Act, 1970. and enclosed as as specified in (Central Act w.e.f. 07-09-70) Appendix I - 3 the issued license. Labour compensation Complied Valid upto To ensure all NA insurance Worker compensation 20.02.2021 potential risks are insurance policy obtained covered. and attached as Appendix I - 4

WBDWSIP/DWW/NCB/ Design, The EIA notification, 2006 The sub project is not NA None NA BK/01/2017-18 Construction and (and its subsequent covered in the ambit of Operation- amendments in 2009) the EIA notification, as Maintenance of provides for categorization of this is not covered under Raw Water Intake projects into category A and either Category A or Well, Water B, based on extent of impact Category B of the Treatment Plant, notification. As a result, Reservoir, the categorization, and Transmission Main the subsequent for Indpur and environmental Taldangra block in assessment and Bankura clearance requirements, either from the state or & the central Government is & WBDWSIP/DWW/NCB/ not triggered. BK/03/2018-19 Design, Environmental Clearance Construction and is not required for the Operation- proposed project Maintenance of Raw Water Intake Well, Water Treatment Plant, Raw and Clear Water Transmission Main for Mejhia and

48 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 Gangajalghati Block in Bankura. WBDWSIP/DWW/NCB/ Water (Prevention and For both the packages - BK/01/2017-18 - DO – Control of Pollution) Act of Application has been sent 1974, Rules of 1975, and to West Bengal Pollution & amendments Control Board for getting WBDWSIP/DWW/NCB/ CTE for Water Treatment BK/03/2018-19 - DO - During implementation Plant (construction phase) CTE for WTP obtained CTE validity Should obtain Ambient noise level shall compliance will be required from WBPCB on date – CTO prior to not exceed permissible CTE has to be received from 16.03.2020 for BK/01 31.03.2027 operation of WTP limit West Bengal Pollution Control (BK/01) Monitoring & Compliance Board (WBPCB) for new CTE for WTP obtained status – specific and WTP from WBPCB on CTE validity general condition of CTE 02.03.2020 for BK/03 date – attached in Appendix II - (Both the CTE attached 28.02.2027 6 as Appendix II - 6) (BK/03) The Air (Prevention and CTE & CTO will be NA CTE to be To be updated in next Control of Pollution) Act 1981, collected as per obtained (as per SEMR when the consent amended 1987 and The Air requirement and with requirement) is (Prevention and Control of advancement of project- prior to obtained as per Pollution) Rules, 1982 Till report period not start of requirement required construction. During implementation (construction phase) Green – Silent Diesel CTO to be compliance will be required Generator in use. No obtained (if CTE and CTO for (i) diesel requirement of CTE and required) before generator/s and (ii) hot mix CTO commencement plants, wet mix plants, stone of operations. crushers, batching plant etc. if installed for construction.

Pollution under control PUC certificate to be certificate (PUC) to be obtained for package obtained by the contractor for BK/01 all vehicles and equipment engaged in the project PUC certificate has been Validity upto Timely renewal

49 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 collected for package December- will be required BK/01 & Bk/03 (sample 2020 (Validity attached as ---Appendix period II - 2) extended as per Govt. notification on extension of validity date under COVID 19 pandemic situation) Direction of West Bengal Construction activities are NA None NA Department of Environment being carried out in under the Air Act, 1981 compliance with the Direction No. EN/3170/T-IV-7 requirements /001/2009 dated: 10 December 2009 The Indian Forest Act, 1927; No forest land is involved - Tree felling NOC Site observation/ Forest (Conservation) Act, . for other sites if monitoring and recording, 1980, amended 1988; Forest required as per • Information to Forest (Conservation) Rules, 1981 final design and Dept. after amended 1992 and 2003 advancement of completion of work plantation West Bengal Trees For Package BK/03- Letter for Felling of trees • Within a week of (Protection and Conservation Tree felling is required for extension of and plantation of carrying out felling of in Non- Forest Areas) Act, construction of WTP. - permission 1160 nos. tree as trees submission of 2006- Tree felling permission Application send to DFO, needs to be compensatory report to forest dept. Forest dept. Permission obtained. plantation indicating the total In case of tree felling NOC obtained on 05.12.2019 Request to number of logs and needs to be obtained from for felling of 232 no. trees. Forest dept. firewood produced Forest dept./ concerned dept. Tree felling not done due already send. against each species to sudden declaration of • Retention of stamps lock down and then onset Tree felling of the felled trees for of monsoon. Permission will be done at least one month extended. (Copy attached shortly. from date of felling as Appendix II - 5). • Felling & carriage of trees shall not be

50 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 carried out after the sun-set and before sun-set Wild Life (Protection) Act No Wildlife protected area NA None NA 1972, Amendment Act, 1993 within or nearby the and 2002 and Wildlife project area (Protection) Rules, 1995 The Ancient Monument and No protected area within NA Chance find NA Archaeological Sites and or nearby the project protocol to be Remains (Amendment and area. But chance find maintained Validation) Act 2010 protocol will be maintained Labour licence under The WBDWSIP/DWW/NCB/ Valid upto To comply with NA Contract Labour (Regulation BK/01/2017-18 08.06.2021 the requirements & Abolition) Act, 1970. Complied as specified in (Central Act w.e.f. 07-09-70) Labour licence obtained the and enclosed as issued license. Appendix II - 3

WBDWSIP/DWW/NCB/ Valid upto BK/03/2018-19 09.11.2021 Complied Labour licence obtained and enclosed as Appendix II - 3 Labour compensation WBDWSIP/DWW/NCB/ Valid upto To ensure all NA insurance BK/01/2017-18 22.06.2021 potential risks are Complied covered. Worker compensation insurance policy attached as Appendix II - 4

WBDWSIP/DWW/NCB/ BK/03/2018-19 Valid upto Complied 30.3.2021 Group Insurance WC policy. Obtained and

51 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 enclosed (Appendix 4B)

WBDWSIP/DWW/NCB/ Design and The EIA notification, 2006 The sub project is not NA None NA BK/02A/2018-19 Construction of (and its subsequent covered in the ambit of Intermediate amendments in 2009) the EIA notification, as Pumping Station, provides for categorization of this is not covered under ground storage projects into category A and either Category A or reservoirs, B, based on extent of impact Category B of the overhead notification. As a result, reservoirs, water the categorization, and distribution the subsequent network and environmental metering works in assessment and Indpur block. clearance requirements, either from the state or WBDWSIP/DWW/NCB/ Design and the central Government is BK/02B/2018-19 Construction of not triggered. Intermediate Environmental Clearance Pumping Station, is not required for the Secondary proposed projects transmission mains, overhead reservoirs including water distribution network and metering works in Taldangra block

Design and WBDWSIP/DWW/NCB/ Construction of BK/04/2018-19 Overhead Reservoir including Water Supply Distribution Network and Metering Works in

52 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 Mejhia and Gangajalghati Blocks including Rehabilitation of Existing Scheme The Air (Prevention and CTE & CTO will be NA CTE to be To be updated in next WBDWSIP/DWW/NCB/ - DO – Control of Pollution) Act 1981, collected as per obtained prior to SEMR when the consent BK/02A/2018-19 amended 1987 and The Air requirement and with start of is obtained as per & - DO – (Prevention and Control of advancement of project- construction as requirement WBDWSIP/DWW/NCB/ - DO - Pollution) Rules, 1982 Till report period not per requirement BK/02B/2018-19 required & During implementation CTO to be WBDWSIP/DWW/NCB/ (construction phase) For all the packages obtained (as per BK/04/2018-19 compliance will be required Green – Silent Diesel requirement) CTE and CTO for (i) diesel Generator in use. No before generator/s and (ii) hot mix requirement of CTE and commencement plants, wet mix plants, stone CTO of operations. crushers, batching plant etc. if installed for construction.

Pollution under control WBDWSIP/DWW/NCB/ Validity period Timely renewal certificate (PUC) to be BK/02A/2018-19 December will be required obtained by the contractor for Received. Sample 2020 all vehicles and equipment attached as Appendix II - engaged in the project 2 Validity period WBDWSIP/DWW/NCB/ December BK/02B/2018-19 2020 Received. Sample attached as Appendix II - 2 Validity period WBDWSIP/DWW/NCB/ December BK/04/2018-19 2020 Received. Sample attached as Appendix II - (Validity 2 period extended as

53 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 per Govt. notification on extension of validity date under COVID 19 pandemic situation) Direction of West Bengal Construction activities are NA None NA Department of Environment being carried out in under the Air Act, 1981 compliance with the Direction No. EN/3170/T-IV-7 requirements /001/2009 dated: 10 December 2009 The Indian Forest Act, 1927; No forest land is involved. NA Tree felling NOC To be updated tree felling Forest (Conservation) Act, for other sites if status and NOC in next 1980, amended 1988; Forest No tree felling required till required as per SEMR as per (Conservation) Rules, 1981 date for all the 3 final design and amended 1992 and 2003 packages advancement of work West Bengal Trees (Protection and Conservation in Non- Forest Areas) Act, 2006- Tree felling permission

In case of tree felling NOC needs to be obtained from Forest dept./ concerned dept. Wild Life (Protection) Act No Wildlife protected area NA None NA 1972, Amendment Act, 1993 within or nearby the and 2002 and Wildlife project area (Protection) Rules, 1995 The Ancient Monument and No protected area within NA Chance find NA Archaeological Sites and or nearby the project protocol to be Remains (Amendment and area. But chance find maintained Validation) Act 2010 protocol will be maintained Labour licence under The Complied, Obtained for To comply with NA

54 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 Contract Labour (Regulation all the requirements & Abolition) Act, 1970. WBDWSIP/DWW/NCB/ as specified in (Central Act w.e.f. 07-09-70) BK/02A/2017-18 Valid upto the issued Labour licence enclosed 19.08.2021 license. as Appendix II -3

WBDWSIP/DWW/NCB/ Valid upto BK02B/2018-19 19.08.2021 Labour licence enclosed as Appendix II - 3

WBDWSIP/DWW/NCB/ Valid upto BK04/2018-19 11.08.2021 Labour licence enclosed as Appendix II - 3 Labour compensation Group compensation Valid upto To ensure all NA insurance insurance policy in favor 30.03.2021 potential risks are of contractors for all covered. packages obtained (Appendix II -4)

WBDWSIP/DWW/ICB/ EM/01/ Design, The EIA notification, 2006 The sub project is not NA None NA 2018-19 Construction and (and its subsequent covered in the ambit of Operation- amendments in 2009) the EIA notification, as Maintenance of provides for categorization of this is not covered under Raw Water Intake projects into category A and either Category A or Well, Water B, based on extent of impact Category B of the Treatment Plant, notification. As a result, Raw and Clear the categorization, and Water the subsequent Transmission Main environmental for Nandakumar, assessment and Chandpur, clearance requirements, Nandigram-I and II either from the state or blocks in East the central Government is Medinipur. not triggered. Environmental Clearance

55 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 is not required for the proposed project Water (Prevention and NA Follow up for NA- Control of Pollution) Act of getting CTE 1974, Rules of 1975, and amendments

During implementation Application has been (construction phase) done for CTE and fees compliance will be required has been paid. CTE has to be received from CTE under process, will West Bengal Pollution Control be obtained shortly. Board (WBPCB) for new Application attached as WTP Appendix- III -6

The Air (Prevention and CTE & CTO will be CTE to be To be updated in next Control of Pollution) Act 1981, collected as per obtained (as per SEMR when the consent amended 1987 and The Air requirement and with requirement) is obtained as per (Prevention and Control of advancement of project prior to requirement Pollution) Rules, 1982 NA start of construction. During implementation Green- Silent Diesel (construction phase) Generator used, - CTE & CTO to be compliance will be required CTO not required obtained (if CTE and CTO for (i) diesel required) before generator/s and (ii) hot mix commencement plants, wet mix plants, stone of operations. crushers, batching plant etc. if installed for construction.

Pollution under control PUC certificate has been Validity period Timely renewal certificate (PUC) to be collected (sample upto will be required obtained by the contractor for attached as - Appendix December all vehicles and equipment III- 2) 2020 engaged in the project Direction of West Bengal Construction activities are NA None NA

56 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 Department of Environment being carried out in under the Air Act, 1981 compliance with the Direction No. EN/3170/T-IV-7 requirements /001/2009 dated: 10 December 2009 The Indian Forest Act, 1927; No forest land is involved. NA Tree felling NOC Compensatory plantation Forest (Conservation) Act, for other sites if of 490 trees at the ratio of 1980, amended 1988; Forest Tree felling NOC has required as per 1:5. (Conservation) Rules, 1981 been obtained on 16th final design and amended 1992 and 2003 October 2020 for felling of advancement of 98 trees from Intake to work West Bengal Trees Ganjanarayanpur. (Protection and Conservation Transmission pipeline in Non- Forest Areas) Act, alignment (Appendix- III - 2006- Tree felling permission 5)

In case of tree felling NOC needs to be obtained from Forest dept./ concerned dept. Wild Life (Protection) Act No Wildlife protected area NA None NA 1972, Amendment Act, 1993 within or nearby the and 2002 and Wildlife project area (Protection) Rules, 1995 The Ancient Monument and No protected area within NA Chance find NA Archaeological Sites and or nearby the project protocol to be Remains (Amendment and area. But chance find maintained Validation) Act 2010 protocol will be maintained Labour licence under The Complied. Valid upto Timely renewal NA Contract Labour (Regulation Labour licence obtained 03.06.2021 will be required & Abolition) Act, 1970. and enclosed as (Central Act w.e.f. 07-09-70) Appendix III - 3 Labour compensation Obtained Group Valid upto To ensure all NA insurance compensation insurance 30.03,2021 potential risks are policy and attached as covered. Appendix III - 4 WBDWSIP/DWW/ICB/EM02/ 2018- Construction of The EIA notification, 2006 The sub project is not NA None NA

57 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 19 Intermediate (and its subsequent covered in the ambit of Pumping Station, amendments in 2009) the EIA notification, as Secondary provides for categorization of this is not covered under transmission projects into category A and either Category A or mains, overhead B, based on extent of impact Category B of the tanks including notification. As a result, water distribution the categorization, and network and the subsequent metering works in environmental Nandigram-I and assessment and Nandigram-II block clearance requirements, in East Medinipur. either from the state or the central Government is not triggered. Environmental Clearance is not required for the proposed project Water (Prevention and Complied as per NA None NA Control of Pollution) Act of requirement and in line of 1974, Rules of 1975, and rules amendments

During implementation (construction phase) compliance will be required The Air (Prevention and CTE & CTO will be CTE to be To be updated in next Control of Pollution) Act 1981, collected as per obtained (as per SEMR when the consent amended 1987 and The Air requirement and with requirement) is obtained as per (Prevention and Control of advancement of project prior to requirement Pollution) Rules, 1982 start of construction. During implementation Green- Silent Diesel (construction phase) Generator in use, - CTE & CTO to be compliance will be required CTO not required obtained (if CTE and CTO for (i) diesel required) before generator/s and (ii) hot mix commencement plants, wet mix plants, stone of operations.

58 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 crushers, batching plant etc. if installed for construction.

Pollution under control PUC certificate has been Validity period Immediate certificate (PUC) to be collected (sample upto February renewal is obtained by the contractor for attached as - Appendix 2021 required all vehicles and equipment III - 2) engaged in the project Direction of West Bengal Construction activities are NA None NA Department of Environment being carried out in under the Air Act, 1981 compliance with the Direction No. EN/3170/T-IV-7 requirements /001/2009 dated: 10 December 2009 The Indian Forest Act, 1927; No forest land is involved. NA Tree felling NOC To be updated tree felling Forest (Conservation) Act, for other sites if status and NOC in next 1980, amended 1988; Forest No tree felling required till required as per SEMR as per (Conservation) Rules, 1981 date final design and requirement amended 1992 and 2003 advancement of work West Bengal Trees (Protection and Conservation in Non- Forest Areas) Act, 2006- Tree felling permission

In case of tree felling NOC needs to be obtained from Forest dept./ concerned dept. Wild Life (Protection) Act No Wildlife protected area NA None NA 1972, Amendment Act, 1993 within or nearby the and 2002 and Wildlife project area (Protection) Rules, 1995 The Ancient Monument and No protected area within NA Chance find NA Archaeological Sites and or nearby the project protocol to be Remains (Amendment and area. But chance find maintained Validation) Act 2010 protocol will be maintained

59 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Package No. Subproject Name Statutory Environmental Status of Compliance3 Validity if Action Required Specific Conditions that Requirements2 obtained will require environmental monitoring as per Environment Clearance, Consent/Permit to Establish4 Labour licence under The Complied. Valid upto Timely renewal Contract Labour (Regulation Labour licence obtained 03.02.2021 will be required & Abolition) Act, 1970. and enclosed as (Central Act w.e.f. 07-09-70) Appendix III - 3 Labour compensation Applied for Group Valid upto To ensure all NA insurance compensation insurance 30.03.2021 potential risks are policy and attached as covered. Appendix III - 4

60 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

20. Status of land clearances are given below. Details are discussed in Social safeguard monitoring report. Table 5: Land Clearances status (Upto October 2020) District Major Work components Status North 24 pgs Lands for OHRs • Out of 39 nos. land for OHRs 31 are private lands and 8 are government land parcels. • In case of private lands, till the reporting period out of 31 land parcels, 18 numbers have been purchased and rest are under of process of purchase. • In case of 8 vested lands for the OHRs, Record of Right (ROR) or Possession Certificate has already been received for all 8 land parcels. Land for GLSR • Under package N24P/ 01, there are two GLSRs to be constructed and both on private land, out of two, one land at Bhangar II Block is purchased, handed over and other one at Haroa is under process. (Appendix I - 23) Water Treatment plant- • Land for WTP and IBPS, both are Govt Intermediate Booster pumping land have already been transferred to station (IBPS) PHED and handed over to concerned contractor. (Appendix I - 23)

Bankura Lands for OHRs • Out of 76 nos. land for OHRs 58 are private lands and 18 are Government land parcels. • In case of private land, till the reporting period out of 58 land parcels, 53 numbers have already been purchased and rest are under process of purchase. • In case of 18 vested lands for the OHRs, Record of Right (ROR) or Possession Certificate has already been received for all the land parcels Intake – under BK01 & BK03 (Two • Permissive possession obtained from I numbers, one at Khatra Block and & WD for construction of Intake well to the other at Barjora Block) be constructed under Khatra Block (BK 01) (Appendix II - 21) • Relinquishment order obtained from I & WD for the Intake to be constructed under Barjora Block (BK 03) (Appendix II - 21) WTP – under BK01 & BK03 (Two • Possession obtained for WTP under numbers, one at Khatra Block and Package BK 01. (Appendix II - 21) the other at Gangajalghati Block) • Possession obtained for WTP under Package BK 03. (Appendix II - 21) GLSR land at Govindapur (BK01) • Cabinet approval obtained & placed before District Land Purchase Committee.

61 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

District Major Work components Status OHR & IBPS land at Raghunathpur • Cabinet approval obtained & placed (BK02A) before District Land Purchase Committee for construction of OHR and IBPS within same plot of land OHR & IBPS land at Taldangra • Land required for the construction of (Chenchuriya)(BK02B) OHR & IBPS at Taldangra has been purchased by PHED., which is also located within same plot of land District level land purchase committee has completed registration process. Possession letter obtained. (Appendix II - 21)

East Medinipur Water storage reservoir lands – • Out of 29 numbers of land for OHRs all various stages the land parcels are government lands. • All 29 government lands for the OHRs, Record of Right (ROR) or Possession Certificate has already been received. Intake – Electric substation • Land Registry has been completed by land purchase committee on 17. 01.2020 and handed over to the concerned Contractor. And Third Party consultation has already done on 23.06.2020. (Appendix III - 21). WTP land • Possession obtained for the land required to construct the WTP (Appendix III - 21) IBPS cum GLSR (Two numbers, • Possession obtained for the land one each in Nandigram I and required to construct IBPS cum GLSR Nandigram II) at Nandigram I as well as Nandigram II. (Appendix III - 21) Overall status Total Land – 158 nos.

Government Land: Possession obtained - 63 Nos. Pending under EE, I&WD for Hand Over -1 No

Private Land: Land already Purchased -72 Nos. Placed before land purchase committee - 20 Nos. Under Process at PHED - 2 Nos.

III. COMPLIANCE STATUS WITH ENVIRONMENTAL LOAN COVENANTS

21. The loan agreement for WBDWSIP was signed on 3rd October 2018 and details are available in ADB website (http://www.adb.org/projects/documents/ind-49107-006-lna). Table 6 provides a summary of compliance to the loan covenants related to environmental safeguards.

62 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Table 6: Compliance of Loan Covenants – Environment part Serial no. Action required as per loan Program Specific Covenants Status / Issues agreement Environment 6 The Borrower shall ensure or cause Under compliance Updation of IEEs the EA to ensure that the preparation, continued after Document is prepared/ or under design, construction, implementation, completion of design preparation by complying all operation and decommissioning of zone wise and relevant State and National possession of lands. the Project, and all projects’ facilities Laws, Safeguard Policy comply with (a) all applicable laws After completion of Statement (SPS 2009) of ADB, and regulations of the Borrower and design for entire Environment Assessment the State relating to environment, package final IEE will Review Framework (EARF) health, and safety; (b) the be prepared and to be Environmental Safeguards; (c) the Draft Initial Environmental send to ADB for EARF; and (d) all measures and Examination (IEE), Environment approval.. requirements set forth in the Management Plan (EMP), Site IEE will be updated respective IEE and EMP, and any Specific Environment further in case of corrective or preventative actions set Management Plan prepared and change in project scope forth in a Safeguards Monitoring approved by ADB. and location Report. Updation of IEEs zone wise Continuation of done for package N 24P/01(1st application of SEMP as updation), 02A and 02B (2nd per approved IEE and updation North 24 pgs); BK/01, during implementation BK/02A, BK/02B, BK/03, BK/04 of the project (1st updation for all Bankura

packages) and. EM/01 & EM/2 (Both 1st updation for East Medinipur). All reports disclosed to project website after acceptance by ADB

In addition, SOP of COVID 19 and H & S plan for COVID 19 mitigation applied for each package All measures as mentioned in Environment Management Plan (EMP) and Site-Specific Environment Management plan (SEMP) has been followed in the 10 nos. running packages Corrective or preventive action plans reflected in Environment Monitoring Report and project implementation authority take care of such actions as per requirement Observed non-compliances are rectified through agreed

63 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Serial no. Action required as per loan Program Specific Covenants Status / Issues agreement corrective and preventive actions. Human and Financial Resources to Implement Safeguards Requirements 10 The Borrower shall make available, Under Compliance Training continued or cause the EA to make available, all including COVID 19 Budgetary provisions have been necessary budgetary and human awareness for included in EMP resources to fully implement the EMP Environment, health required. Executive Engineer in-charge of and safety officer of Environment and Social contractors for Safeguard is in place in Project application of SEMP Management Unit heading and necessary Safeguard Monitoring Unit corrective action. An Environment Specialist is in place within Project Management Consultancy (PMC) An Environmental Specialist of DSISC, for implementation of EMPs, is in place for regular monitoring to secure complete compliance. (Personnel detail shown in Table 1) Safeguards – Related Provisions in Bidding Documents and Works Contracts In case of any change 11. The Borrower shall ensure, or cause Under compliance of scope, revised IEEs the EA to ensure, that all bidding EMP, BOQ line items, with EMP(s) will be documents and contracts for Works reinstatement to pre-project prepared and corrective contain provisions that require conditions included in the measures will be contractors to: contract agreement. disclosed to the (a) comply with the measures and (a) Approved IEE, EMP is contractor requirements relevant to the attached in Bidding documents. It is pertinent to note contractor set forth in the IEE, the here that in view of In case of any change of scope, EMP, the RP and the IPP (to the COVID-19 pandemic, revised IEEs with EMP(s) will be extent they concern impacts on work almost stopped at prepared and corrective affected people during construction), sites till May 2020 after measures will be disclosed to the and any corrective or preventative June 2020 activity contractor and same will be actions set out in a Safeguards started at sites slowly. Monitoring Report; reflected in the “Environment At all sites including

Monitoring Report”. office COVID 19

Contractors done base line pre protocol maintained as construction monitoring and per SOP and COVID survey of pre- works condition. 19 H & S plan.

Budget has been allocated for EMP application and monitoring. In this context, it may Pre construction documents, be noted that OHR site

environment monitoring report for Zone- 2 and 18 of submitted by contractors for all Bhangar-II block has the packages. During been relocated outside

64 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Serial no. Action required as per loan Program Specific Covenants Status / Issues agreement construction documents the East Kolkata

submitted by contractors except Wetland Management for package BK/01, where Authority (EKWMA) physical work not yet started. area. At Zone-1,

Monitoring will be continued Bhangar II distribution throughout project execution of water will be done period. suing control valves However, NOC for pipe (b) IEE includes budgetary laying work in these (b) make available a budget for all provisions for implementation of locations has been such environmental measures; EMP for all the packages. obtained from EKWMA Contractors submit monitoring (Appendix I - 8) budget in the SEMP Presently, pipeline (c) During implementation of any trenches are filled up (c) provide the EA with a written project if additional impacts/risks and initial road notice of any unanticipated arise due to change in restorations are environmental risks or impacts that scope/area that will be reflected completed on the same arise during construction, in the revised IEEs, EMPs and day. Whenever implementation or operation of the Environment Monitoring Report incomplete restoration Project that were not considered in and accordingly project is observed appropriate the IEE, the EMP, the RP or the IPP; Executing Contractor will inform corrective and the Construction Contractor for preventive actions are taking relevant corrective taken. measures. Till date no as such situation create for packages which under implementation.

(d) Haul roads have marked (d) adequately record the condition of properly (by avoiding residential roads, agricultural land and other and agricultural land) before infrastructure prior to starting to commencement of transportation transport materials and construction; of materials. and (e) Pathways, and land which (e) fully reinstate pathways, other are affected for varying periods local infrastructure, and agricultural during implementation of the sub land to at least their pre-project project restored by concerned condition upon the completion of construction Contractor before construction. acceptance of the work. Restoration status has reflected in post construction monitoring report. Since the pipe laying work continued in villages, no as such underground infrastructure noted Safeguards Monitoring and Reporting 12 The Borrower shall cause the EA to Under compliance Semi Annual do the following: Environment Monitoring (a) Last semi-annual Report will be (a) submit semi-annual environment monitoring report submitted as per Safeguards Monitoring Reports to (SEMR) submitted for the period schedule ADB and disclose relevant November 2019 - April 2020.

65 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Serial no. Action required as per loan Program Specific Covenants Status / Issues agreement information from such reports to Disclosure of SEMR at ADB IEE/ EMP will be affected persons promptly upon and project website done – revised in case of submission; This is 4th SEMR for the period inclusion of additional May 2020 to October 2020 impact and change in location/ scope for the (b) During implementation of any project project, if additional impacts/risks (b) if any unanticipated arise due to change in environmental and/or social risks and scope/area, those will be impacts arise during construction, reflected in revised IEEs with implementation or operation of the EMPs and accordingly Executing Project that were not considered in Contractor (EA) will inform the the IEEs, the EMPs, promptly inform ADB such change along with ADB of the occurrence of such risks corrective action plan which will or impacts, with detailed description be reflected in the subsequent of the event and proposed corrective Monitoring Reports. action plan; and (c) in case of any breach of (c) report any breach of compliance compliance with the measures with the measures and requirements and requirements set forth in the set forth in the EMPs, promptly after EMP, EA will promptly inform becoming aware of the breach. ADB and suitable corrective action program will be planned/initiated. Till date no as such breach of compliance Prohibited List of Investments 13 The Borrower shall ensure or cause Complied the State to ensure that no proceeds There is no violation of of the Loan are used to finance any prohibited investment activities activity included in the list of as per ADB SPS (2009) prohibited investment activities Appendix 5. provided in Appendix 5 of the SPS. Labour Standards 14 The EA shall ensure that civil works Under compliance HIV- AIDS training for contracts under the Project follow all other construction Provision are included (as per applicable labourer laws of the packages which EMP & BID document) to carry Borrower and the State, and that awarded and where out HIV/AIDS awareness these further include provisions to the actual physical work to programs for construction effect that contractors: (a) carry out be started contractor, application of all HIV/AIDS awareness programs for relevant labour laws for health H & S training for labourer and disseminate information and safety including child labour COVID 19 pandemic at worksites on risks of sexually law and engagement of local was carried out on transmitted diseases and HIV/AIDS labours (preferably from regular basis as part of health and safety measures economically backward group) for those employed during Timely renewal of WC covering women labours. construction; and (b) follow and Policy and Labour implement all statutory provisions on No child labour engaged in the license labourer (including not employing or packages using children as labourer, equal pay

66 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Serial no. Action required as per loan Program Specific Covenants Status / Issues agreement for equal work), health, safety, Labour license and health welfare, sanitation, and working related WC policy for workers conditions. Such contracts will also available for all the packages include clauses for termination in (Attached as Appendix I - 3 & I - case of any breach of the stated 4 for North 24 pgs, II - 3 & II - 4 provisions by the contractors. for Bankura and III - 3 & III - 4 for East Medinipur). HIV- AIDS training program conducted for packages for North 24 pgs and Bankura (Appendix I - 14, II - 12). For East Medinipur packages training will be arranged shortly. HIV/ AIDS awareness program to be conducted shortly for other contracts Induction training continued for all the awarded packages In case of any breach of provision, necessary corrective measures as per contract clauses shall be taken. All activities including awareness program reflected in “Monitoring Report”.

IV. COMPLIANCE STATUS WITH THE ENVIRONMENTAL MANAGEMENT PLAN

22. There are 10 environment sensitive packages under implementation. Site Environment plans including site specific EMPs (SEMP) were submitted by the contractors before starting of each construction package. SEMPs were prepared and are being prepared zone wise based on final detailed design. Table 3A shows list of SEMPs finalized before start of construction work (upto 31st October 2020) including disclosed SEMPs website link. SEMPs are available with DSISC and PIU for implementation and monitoring of application of mitigation measures. Compliance status of SEMPs are also available with DSISC and PIU. Table 7 shows package wise EMP implementation status.

67 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Table 7: Package wise EMP Implementation Status Design status Final IEE based on Detailed Design Site specific EMP (Preliminary Not yet due Submitted to (or construction Design Stage/ Disclosed on Package No Components (detailed design ADB (provide Final IEE provided to EMP) approved by Remarks Detailed project website not yet date of Contractors (Yes/No) Project Director Design (provide link) completed) submission) (Yes/ No) Completed WBDWSIP/DWW/ Design, DBO contract: Updated Final IEE Updated IEE 1st Updated IEE Updated disclosed IEE Prepared and Nil N-24P/ Construction design based on upto submitted in disclosed in provided to contractor approved by PIU NCB/01/2017-18 and Operation completed - date design December 2019 project website Further updation of Water partially. Rest prepared along along with Log will be done after Treatment undergoing with SEMP sheet (http://wbdwsip completion of Plant, (specifically mis.wbphed.gov design Reservoirs, transmission .in/updated_1_I Transmission main pipeline) EE_N24pgs_01 Mains and _Jan2020.aspx) Pumping Stations works in Haroa, Rajarhat, and Bhangar II. WBDWSIP/DWW/N- Design and Detailed Updated IEE 2nd Updated IEE Designed Zone Updated disclosed IEE Prepared and Nil 24P/ Construction design prepared upto date submitted in wise 2nd provided to contractor approved by PIU NCB/02A/2017-18 of Overhead continued design and SEMPs August 2020 Updated IEE for Reservoir zone wise. zone wise. along with Log the package The list of SEMPs including Partly 2nd Updation done sheet disclosed in that have been design, supply completed and project website approved from PIU and laying of work ongoing are provided in Water Supply (design status (http://wbdwsip Table 3A. Distribution stated in Table mis.wbphed.gov All SEMPs Network in 3) .in/updated_2_I disclosed in project Haroa Block. EE_N24Pgs_02 website and A_Sept2020.asp website link x) provided in Table 3A

68 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Design status Final IEE based on Detailed Design Site specific EMP (Preliminary Not yet due Submitted to (or construction Design Stage/ Disclosed on Package No Components (detailed design ADB (provide Final IEE provided to EMP) approved by Remarks Detailed project website not yet date of Contractors (Yes/No) Project Director Design (provide link) completed) submission) (Yes/ No) Completed WBDWSIP/DWW/N- Design and Detailed Updated IEE 2nd Updated IEE Designed Zone Updated disclosed IEE Prepared and Nil 24P/ Construction design prepared upto date submitted in wise 2nd provided to contractor approved by PIU NCB/02B/2017-18 of Overhead continued design and SEMPs October 2020 Updated IEE for Reservoir zone wise. zone wise. along with Log the package The list of SEMPs including Partly 2nd Updation done sheet disclosed in that have been design, supply completed and project website approved from PIU and laying of work ongoing are provided in Water Supply (design status (http://wbdwsip Table 3A. Distribution stated in Table mis.wbphed.gov All SEMPs Network in 3) .in/updated_2_I disclosed in project Bhangar II EE_N24Pgs_02 website and Block. B_Oct2020.aspx website link ) provided in Table 3A

WBDWSIP/DWW/N Design, For DBO Updated IEE 1st Updated IEE 1st Updated IEE Updated disclosed IEE Finalized and Nil CB/ Construction contract prepared upto date submitted in for the package provided to contractor included in updated BK/01/2017-18 and detailed design October 2020 disclosed in IEE Operation- design along with Log project website Maintenance completed sheet of Raw Water (http://wbdwsip Intake Well, mis.wbphed.gov Water .in/updated_1_I Treatment EE_Bankura_Bk Plant, 01_Nov2020.as Reservoir, px) Transmission Main for Indpur and Taldangra block in Bankura. WBDWSIP/DWW/N Design and Detailed Updated IEE 1st Updated IEE Designed Zone Updated disclosed IEE Prepared and Nil CB/ Construction design prepared upto date submitted in April wise 1st Updated provided to contractor approved by PIU BK/02A/2018-19 of continued design and SEMPs 2020 along with IEE for the Intermediate zone wise. zone wise. Log sheet package The list of SEMPs

69 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Design status Final IEE based on Detailed Design Site specific EMP (Preliminary Not yet due Submitted to (or construction Design Stage/ Disclosed on Package No Components (detailed design ADB (provide Final IEE provided to EMP) approved by Remarks Detailed project website not yet date of Contractors (Yes/No) Project Director Design (provide link) completed) submission) (Yes/ No) Completed Pumping Partly disclosed in that have been Station, completed and project website approved from PIU ground work ongoing are provided in storage (design status (http://wbdwsip Table 3A. reservoirs, stated in Table mis.wbphed.gov All SEMPs overhead 3) .in/updated_1_I disclosed in project reservoirs, EE_Bankura_Bk website and water 02A_March2020 website link distribution .aspx) provided in Table network and 3A metering works in Indpur block., Bankura WBDWSIP/DWW/N Design and Detailed Updated IEE Updated IEE Designed Zone Draft disclosed IEE only Prepared and Nil CB/ Construction design prepared upto date submitted in June wise 1st Updated provided to contractor approved by PIU BK/02B/2018-19 of continued design and SEMPs 2020 along with IEE for the Intermediate zone wise. zone wise. Log sheet package The list of SEMPs Pumping Partly disclosed in that have been Station, completed and project website approved from PIU Secondary work ongoing are provided in transmission (design status (http://wbdwsip Table 3A. mains, stated in Table mis.wbphed.gov All SEMPs overhead 3) .in/updated_1_I disclosed in project reservoirs EE_Bankura_Bk website and including 02B_June2020. website link water aspx) provided in Table distribution 3A network and metering works in Taldangra Block. WBDWSIP/DWW/N Design, DBO contract: Updated Final IEE Updated IEE 1st Updated IEE Updated disclosed IEE Finalized and Nil CB/ Construction design based on upto submitted on for the package provided to contractor included in updated BK/03/2018-19 and completed date design February 2020 disclosed in IEE Operation- prepared along along with Log project website Maintenance with SEMP sheet (http://wbdwsip

70 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Design status Final IEE based on Detailed Design Site specific EMP (Preliminary Not yet due Submitted to (or construction Design Stage/ Disclosed on Package No Components (detailed design ADB (provide Final IEE provided to EMP) approved by Remarks Detailed project website not yet date of Contractors (Yes/No) Project Director Design (provide link) completed) submission) (Yes/ No) Completed of Raw Water mis.wbphed.gov Intake Well, .in/updated_1_I Water EE_Bankura_B Treatment K_03_Feb2020. Plant, Raw aspx) and Clear Water Transmission Main for Mejhia and Gangajalghati Block in Bankura WBDWSIP/DWW/N Design and Detailed Updated IEE Updated IEE Designed Zone Updated disclosed IEE Prepared and Nil CB/ Construction design prepared upto date submitted in April wise 1st Updated provided to contractor approved by PIU BK/04/2018-19 of Overhead continued design and SEMPs 2020 along with IEE for the Reservoir zone wise. zone wise. Log sheet package The list of SEMPs including Partly disclosed in that have been Water Supply completed and project website approved from PIU Distribution work ongoing are provided in Network and (design status (http://wbdwsip Table 3A. Metering stated in Table mis.wbphed.gov All SEMPs Works in 3) .in/updated_1_I disclosed in project Mejhia and EE_Bankura_Bk website and Gangajalghati 04_March2020. website link Blocks aspx) provided in Table including 3A Rehabilitation of Existing Schemes., Bankura WBDWSIP/DWW/IC Design, DBO contract: Updated Final IEE Updated IEE 1st Updated IEE Updated disclosed IEE Finalized and Nil B/ Construction design based on upto submitted on for the package provided to contractor included in updated EM/01/2018-19 and completed date design October 2020 disclosed in IEE Operation- prepared along along with Log project website Maintenance with SEMP sheet of Raw Water (http://wbdwsip Intake Well, mis.wbphed.gov

71 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Design status Final IEE based on Detailed Design Site specific EMP (Preliminary Not yet due Submitted to (or construction Design Stage/ Disclosed on Package No Components (detailed design ADB (provide Final IEE provided to EMP) approved by Remarks Detailed project website not yet date of Contractors (Yes/No) Project Director Design (provide link) completed) submission) (Yes/ No) Completed Water .in/updated_1_I Treatment EE_E_Medinipu Plant, Raw r_EM01_Nov20 and Clear 20.aspx) Water Transmission Main for Nandakumar, Chandpur, Nandigram-I and II blocks in East Medinipur. WBDWSIP/DWW/IC Construction Detailed Updated IEE Updated IEE Designed Zone Updated disclosed IEE Prepared and Nil B/ of design prepared upto date submitted in June wise 1st Updated provided to contractor approved by PIU EM/02/2018-19 Intermediate continued design and SEMPs 2020 along with IEE for the Pumping zone wise. zone wise. Log sheet package The list of SEMPs Station, Partly disclosed in that have been Secondary completed and project website approved from PIU transmission work ongoing are provided in mains, (design status (http://wbdwsip Table 3A. overhead stated in Table mis.wbphed.gov All SEMPs tanks 3) .in/updated_1_I disclosed in project including EE_E_Medinipu website and water r_EM02_July20 website link distribution 20.aspx) provided in Table network and 3A metering, East Medinipur

72 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

A. Implementation Arrangement

23. Public Health Engineering Department (PHED) of Government of West Bengal is the executing and implementing agency of the WBDWSIP, responsible for management, coordination and execution of all activities funded under the loan. A project management unit (PMU), exclusively established in PHED, assist the PHED in implementation of WBDWSIP. PMU supported by district level Project Implementation Units (PIUs). PMU is headed by a Project Director. Each PIU is headed by a Superintending Engineer, reporting to the Project Director. PMU with the support of PIUs is responsible for planning, implementation, monitoring and supervision, and coordination of all activities under the WBDWSIP. Project Implementation Unit (PIU) for North 24 Parganas, Bankura and East Medinipur district has already been established.

24. PMU is supported by Project Management Consultant (PMC) to supervise, monitor and oversee the implementation. Each PIU is supported by a Design, Supervision and Institutional Support Consultant (DSISC); there are three DSISCs supporting 3 PIUs respectively in North 24 Parganas, Bankura and East Medinipur districts. PIUs appoint construction contractors to build infrastructure.

25. A Steering Committee, headed by Chief Secretary, will provide strategic guidance, and oversee the implementation of the investment project. District Steering Committee, headed by the respective District Magistrate, established for monitoring program implementation at districts level. Steering committee is already established {Appendix I - 17-(North 24 pgs), II-15 (Bankura) & III-15(East Medinipur)}.

B. Safeguard Implementation Arrangement

26. Project Management Unit. A Safeguard and Gender Cell (SGC) established in PMU with the overall responsibility of ensuring compliance with ADB SPS. SGC is headed by a Head Safeguards Gender Officer (HSGO) and report to the Project Director directly. The HSGO have overall responsibility in implementation of the RF, EARF, RPs, EMPs, SEMP, GESI action plan, and appropriate monitoring and reporting responsibilities. Key environmental safeguard tasks and responsibilities at the PMU level are as follows:

o Ensure subprojects confirms to exclusion criteria and project selection guidelines as stipulated in the EARF; o Approve subproject environmental category; o Approve IEEs; ensure that updated IEEs/EMPs reflect final project designs; o Ensure that EMPs are included in bidding documents and civil works contracts; o Ensure proper implementation of EMPs by contractors; o Facilitate and ensure compliance with all government rules and regulations regarding site and environmental clearances, as well as any other environmental requirements (e.g. location clearance certificates, environmental clearance certificates), as relevant; o Oversee public consultation and disclosure; o Approve quarterly EMP implementation reports; o Review and approve semi-annual monitoring reports prepared by PMC; and submit to ADB; o Oversee grievances redress process and ensure timely redress; o Undertake regular review of safeguards related loan c ovenants, and the compliance in program implementation; and

73 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

o Organize periodic capacity building and training programs for WBDWSIP stakeholders, PHED, PMU and PIU staff on safeguards. 27. The SGC supported by environmental, social and gender safeguard specialists in the PMC. Key safeguard tasks and responsibilities of Environmental Specialist of the PMC on environmental safeguards are as follows:

o Review and finalize REA checklist and classify the project; o Review and confirm project selection/ design; ensure compliance with exclusion criteria and project environmental selection guidelines; o Review and finalize IEE reports including EMPs prepared/updated by PIUs/DSISCs; o Oversee public consultation and information disclosure activities; ensure timely disclosure; o Provide advise/support in obtaining government clearance/ approvals; o Review and confirm that IEEs/EMPs are included in bids and contracts; o Review and confirm SEMPs prepared by contractor; o Oversee the implementation of SEMP by contractors and ensure corrective actions, where necessary; o Review and approve quarterly environmental monitoring reports submitted by PIU/DSISCs; o Conduct site visits of project facilities and work sites to oversee implementation; o Prepare semi-annual environmental monitoring reports and submit to PMU SGC HSGO; o Oversee grievance redress process; advise on critical grievance related to environmental issues and concerns; o Review COVID 19 compliance monitoring, and o Organize training and capacity development programs.

28. Project Implementation Unit. At each PIU, an Assistant Engineer is given additional responsibilities of safeguard tasks and designated as Assistant Safeguards Officer. The Safeguards Officer oversee the safeguards implementation at PIU level, coordinate public consultations, information disclosure, regulatory clearances and approvals, RP implementation, EMP implementation and grievance redressal. Key environmental safeguard tasks and responsibilities of Safeguards Officer are as follows:

o Coordinate public consultation and information disclosure; o Liaise with local offices of regulatory agencies in obtaining clearances /approvals; assist PMU for clearances obtained at state level; o Review and approve contractors SEMPs; o Oversee day-to-day implementation of SEMPs by contractors including compliance with all government rules and regulations; o Take necessary action for obtaining rights of way; o Ensure continuous public consultation and awareness; o Coordinate grievance redress process and ensure timely actions by all parties; o Review monthly contractor’s SEMP Monitoring Reports; o Review and forward quarterly monitoring reports to PMU; and o Inform PMU of unanticipated impacts and formulate corrective action plan; and o Recommend issuance of work construction work completion certification to the contractor upon verification of satisfactory post-construction clean-up.

74 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

29. The PIUs assisted by DSISC teams which includes an Environmental Specialist and a Social Safeguards Specialist. Following are the key tasks of Environmental Specialist of DSISC:

o Assist PIU in identifying projects/components in compliance with the project exclusion criteria and selection guidelines stipulated in EARF; o Prepare environmental screening checklists and submit to PMU for categorization; update checklist and category as and when required to reflect project changes, and report to PMU; o Work closely with PIU and design teams to include environmental considerations in project location, design and technical specifications; o Identify statutory clearance / permissions / approvals required for subproject; assist PIU in obtaining them; o Assist in including standards/conditions, if any, stipulated in regulatory clearances, consents in the project design; o Update IEE and EMP to reflect any changes in subproject during detail design / implementation; IEE shall reflect the final project design; o Lead / assist PIU in public consultation in compliance with the EARF; reflect inputs from public consultation in IEEs, EMPs, and project design; o Advise / assist PIU in disclosing relevant information on safeguards to stakeholders, affected people etc.; o Assist / ensure all EMP measures related project design and location and included in the detailed designs; o Integrate EMP into the BID and contract documents (for DBO contracts, include full IEE including EMP in bids); o Advise contractor in preparation of SEMP as per the final design, prior to start of construction; o Ensure that all necessary clearances/permission (including those required by Contractor) are in place prior to start of construction; o Monitor implementation of SEMP; o Ensure Contractors including subcontractor’s, if any, comply with the measures set forth in the EMP; o Assist PIU in establishing GRM for the Project: o Assist PIU in grievance redress, advise the contractor on appropriate actions on grievances, ensure timely resolution and proper documentation; o Identify, if any, non-compliance or unanticipated impacts; initiate corrective actions, report to PMU; o Review and approve monthly monitoring reports submitted by Contractor; consolidate and prepare quarterly Environmental Monitoring Reports (EMR) and submit to PMU; and o Conduct training and capacity building activities (workshops, hands-on trainings, visits etc.,) in EMP implementation.

30. Civil Works Contracts and Contractors. The contractor appoints an Environment, Health and Safety (EHS) Officer to implement EMP. The EHS Officer will update the EMP and submit a SEMP for approval of PIU. Contractors will carry out all environmental mitigation and monitoring measures outlined in EMP, approved SEMP and their contracts. Key responsibilities of the EHS supervisor are:

o Prepare SEMP and submit to PIU for approval prior to start of construction; o Conduct orientation and daily briefing sessions to workers on environment, health and safety;

75 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

o Ensure that appropriate worker facilities are provided at the work place and labour camps as per the contractual provisions; o Records accidents and undertake remedial actions; o Implement SEMP measures and report to PIU/DSISC if any new impacts are surfaced; seek guidance from as required in EMP implementation; o Compliance of H & S issues for COVID 19; o Conduct environmental monitoring (air, noise etc.,) as per the monitoring plan o Ensure conduct of water quality surveillance program; o Prepare monthly EMP monitoring reports and submit to PIU; o Work closely with PIU Safeguards Officer and consultants to ensure communities are aware of project-related impacts, mitigation measures and GRM; and o Address any public compliance and grievances effectively and in timely manner.

31. Environment Specialist and Environment support staff of DSISC visited all construction sites every week and arranged onsite training program for contractors and supervisory staff and instructed contractors for application of corrective action measures to mitigate impacts. Environment Specialist of PMC visited work sites atleast once in a month to audit application of EMP and assess shortfall if any. Due to COVID 19 Lockdown situation and slow progress of work during report period visit to work sites was limited. Table 8 shows detail of safeguard personal from contractor. Table 1 shows project safeguard Team.

Table 8: Details of Contractor’s safeguard officer for WBDWSIP Designation Name and Contact Details

North 24 Parganas Contractor- NCC, North 24 Pgs Name: Mr. Saradindu Gain Package: N-24P/NCB/02A/2017-18, Phone: 9775459487 Safeguard Officer Email: [email protected] Contractor- NCC, North 24 Pgs, Name: Nitin Sartape Package: N-24P/NCB/02B/2017-18, Phone: 8971107720 Safeguard Officer E mail: [email protected]

Contractor- Furnace Fabrica (India) Ltd.- North Name: Subhankar Chattopadhya 24 Pgs, Phone: 6290016411, 9649986813 Package: N-24P/NCB/01/2017-18, Email: Safeguard Officer [email protected] Bankura Contractor- Techno Fab Engineering Ltd. and S Name: Mr. Prasanta Panda N Envirotech Pvt. Ltd. Jv, Bankura, Phone: 7684097086 Package: BK/NCB//01/2017-18, Email: [email protected] Safeguard Officer Contractor- L & T Ltd. Name: Mr. Tirthraj Gupta Package: Phone: 9939691579 BK/NCB/02A/2018-19, Email: [email protected] Safeguard officer Contractor- L & T Ltd. Name: Dhabaleswar Biswal Package: Phone: 8895094563 BK/NCB/02B/2018-19, Email: [email protected] Safeguard officer Contractor- L & T Ltd Name: Mr. Mukesh Kumar Package: BK/NCB/03/2018-19, Phone: 8637860268 Safeguard officer Email: [email protected]

76 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Designation Name and Contact Details

Contractor- L & T Ltd. Name: Mr. Tarak Das Package: BK/NCB/04/2018-19, Phone: 9143696713 Safeguard officer Email: [email protected] East Medinipur Contractor- L & T Ltd Name: Mr. Subrata Kumar Das Package: EM/ICB/01/2018-19 Phone: 8889996575 Safeguard officer Email: [email protected] Contractor- L & T Ltd Name: Mr. Sujan Goswami Package: EM/ICB/02/2018-19 Phone: 7837175749 Safeguard officer Email: [email protected]

32. Figure 7 shows institutional arrangement for safeguard implementations for the project.

Figure 7: Overall Institutional Arrangement – Safeguards

C. EMP implementation - Application of Mitigation measures

33. Environment Specialist from DSISC and PMC carried out periodic monitoring of EMP implementation through desk review of contractor’s records as submitted monthly and site inspections. Sample site inspection report as prepared by DSISC is shown in Appendix I- 9 (North 24 pgs), Appendix II - 7 (Bankura) and Appendix III - 7 (East Medinipur). Further, sample monthly environmental compliance monitoring with photographic evidences is presented in Appendix I - 10 (North 24 pgs), Appendix II - 8 (Bankura) and Appendix III - 8 (East Medinipur). Package wise status of Environment Monitoring for North 24 Parganas are shown in Table 9 (Package: N-24P/01), Table 10 (Package North 24 pgs N-24P/02A and N-24P/02B), Table 11 (Package Bankura BK/01 and BK/03) Table 12 (Package Bankura BK/02A, BK/02B

77 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

and BK/04), Table 13 (Package East Medinipur EM/01) and Table 14 (Package East Medinipur EM/02). Contractors are regularly submitting monthly environment monitoring reports and daily and weekly checklists. Sample monthly EMP monitoring checklist is enclosed as Appendix I - 11 (North 24 pgs), Appendix II - 9 (Bankura) and Appendix III - 9 (East Medinipur).

34. As informed in last SEMR Standard Operating Procedure (SOP) for mitigation of COVID 19 impact to be prepared, accordingly SOP under WBDWSIP has been developed and disclosed in ADB and Project website (weblink at project website: http://wbdwsipmis.wbphed.gov.in/SOP_H_S_COVID19_WBDWSIP.aspx ) on June 2020. Later on the basis of project COVID 19 SOP, supplementary COVID 19 H & S plan has been developed by the construction contractors for all the 10 packages and contractor start compliance of that H & S plan from August 2020 onwards. Appendix I - 12, II - 10 and III -10 shows sample compliance status – filling up of HSE COVID checklist & other relevant format, training & awareness for Nortth 24 pgs, Bankura and East Medinipur districts respectively.

35. Contractors has already complied pre construction requirements like collection of PUC certificate (Appendix I - 2- N 24 pgs, II - 2- Bankura and III - 2- East Medinipur), labour license (Appendix I - 3- N 24 pgs, II - 3- Bankura and III - 3- East Medinipur), Workman Compensation Policy (Appendix I - 4- N 24 pgs, II - 4- Bankura and III - 4 – East Medinipur) and also done during construction monitoring (Appendix I - 13- North 24 pgs, II - 11- Bankura and III - 11- East Medinipur).

78 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Table 9: Summary of Environmental Monitoring Activities for the Package WBDWSIP/DWW/NCB/N24P/01/2017-18: BULK WATER SUPPPLY Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance from IEE) (List from IEE) Monitored (As Monitoring Monitoring Monitoring Person Status/ a minimum Conducted Who Explanation those Conducted identified in the the IEE should Monitoring be monitored) Design Phase Source o Discontinuation of current unsafe and unsustainable • Design Document All project Before Environment Detailed design sustainability groundwater sources and creating a new comprehensive philosophy review and locations Commencement Specialist of under process and efficiency surface water (river) based water supply system • Treatment LOP Survey and during DSISC, particularly water o Recovering wash water from treatment process to optimize scheme final design PIU and transmission the water use • Project PMU/PMC pipeline, o Treatment and reuse of sludge from treatment process QA/QC plan necessary points o Designing the entire system to maintain optimal flow and as mentioned in terminal pressure, and optimizing the overall energy usage IEE are o Reducing the incidence of water borne diseases by considered providing 100% population including urban poor with during potable water supplies finalization of o Preparation and implementation of a water quality design surveillance program including development of a laboratory as part of the project by DBO contractor to ensure that supplied water meets the drinking water standards o Development of laboratory with all necessary environment, health and safety measures and adopting international standard procedures for water quality testing o Using low-noise and energy efficient pumping systems o Installing the noise-producing pumps and motors etc., in enclosed buildings with noise reducing walls, and also maintaining adequate buffer to the nearby inhabited areas. Provision of appropriate personal protection equipment to the workers and staff Chlorine o Provide the following measure at the chlorine application • Project Document WTP and Before Environment Detail design handling and unit: emergency review Booster Commencement Specialist of continued. application risk o Chlorine neutralization pit with a lime slurry feeder management pumping and during DSISC and Existing – health and o Chlorine absorption and neutralization facility plan station site final design PIU authorization safety risk to o Proper ventilation, lighting, entry and exit facilities • Project safety under “The workers and o Visible and audible alarm facilities to alert chlorine gas leak and PPE use manufacture, general public o Facility for isolation in the event of major chlorine leakage plan storage and o Eye wash and shower facility • Training plan import o Personal protection and safety equipment for the operators of hazardous

79 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance from IEE) (List from IEE) Monitored (As Monitoring Monitoring Monitoring Person Status/ a minimum Conducted Who Explanation those Conducted identified in the the IEE should Monitoring be monitored) in the chlorine plant (masks, oxygen cylinders, gloves, etc.,) chemicals rules, o Provide training to the staff in safe handling and application 1989” should be of chlorine; this shall be included in the contract of reviewed and as Chlorinator supplier appropriate o Supplier of Chlorinator equipment shall provide standard authorization for operating manual additional for safe operation and as well as maintenance and repairs; storage should preferably these shall be provided both in English and be sought prior Bengali Languages to operation. Tree cutting o Minimize removal of trees by adopting to site condition and Tree felling • Checking Project Before Environment As of now, tree with appropriate layout design of GLSRs requirement of records locations Commencement Specialist of felling o Obtain prior permission for tree cutting and • Visual and during DSISC and requirement is o Plant and maintain 5 trees for each tree that is removed afforestation inspection final design PIU not envisaged. after final of sites design Disturbance to o Construction GLSR at Haroa away from the flood plain of • Location map • Document GLSR sites Before Environment Under natural Bidyadhari river • Design review Commencement Specialist of compliance- drainage o Integrate measures into GLSR design to avoid risk of philosophy • Visual and during DSISC, PIU during final flooding. inspection final design and designing. of sites PMU/PMC Only one GLSR site at Bhangar - II block has been handed over. Pre-Construction Phase Telephone o Identify and include locations and operators of these utilities List of affected Observation Specific Before Environment Under lines, electric in the detailed design documents to prevent unnecessary utilities if any and project commencement Specialist of Compliance poles and disruption of services during construction phase; and and document location of construction DSISC and Transmission wires, water o Require construction contractor to prepare a contingency operators checking PIU main pipe line lines within plan to include actions to be taken in case of unintentional design under proposed interruption of services. finalization project area o Require contractors to prepare spoils management plan Alignment and traffic Management plan selection almost completed considering minimum social impact. Spoil

80 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance from IEE) (List from IEE) Monitored (As Monitoring Monitoring Monitoring Person Status/ a minimum Conducted Who Explanation those Conducted identified in the the IEE should Monitoring be monitored) management and traffic management plan for pipe line laying locations will be submitted after finalization of design/ alignment Conflicts with o Prioritize areas within or nearest possible vacant space in • List of •Site Specific Before Environment Under local the project location; selected observatio project commencement Specialist of Compliance. community; o If it is deemed necessary to locate elsewhere, consider project n location of final design DSISC and disruption to sites that will not promote instability and result in destruction location and • Review of and PIU WTP traffic flow and of property, vegetation, irrigation, and drinking water supply proposed document commencement construction sensitive systems. pipeline s of construction started within receptors o Not to consider residential areas. alignment • Grievance fixed campus. o Take extreme care in selecting sites to avoid direct disposal plan Register No impact on to water body which will inconvenience the community. • Involvement property. o For excess spoil disposal, ensure (a) site shall be selected of Pipe laying will preferably from barren, infertile lands. In case agricultural traffic dept. be commenced land needs to be selected, written consent from landowners • Road closure after finalization (not lessees) will be obtained; (b) debris disposal site shall planning of design and be at least 200 m away from surface water bodies; (c) no alignment residential areas shall be located within 50 m downwind side of the site; and (d) site is minimum 250 m away from sensitive locations like settlements ponds/lakes or other water bodies Extraction of o Obtain construction materials only from government • List of • Checking Project sites Before DSISC Complied materials can approved quarries with prior approval of PIU; approved of records commencement Construction All materials disrupt natural o PIU to review, and ensure that proposed quarry sources quarry sites • Visual of construction Managemen procured from land contours have all necessary clearances/ permissions in place prior to and inspection t and licensed vendors and vegetation approval sources of of sites Environment after approval of resulting in o Contractor to submit to PIU on a monthly basis materials al Safeguard PIU/ DSISC accelerated documentation on material obtained from each source • Construction Team erosion, (quarry/ borrow pit) Contractor disturbance in o Avoid creation of new borrow areas, quarries etc., for the documentatio natural project; if unavoidable, contractor to obtain all clearances n

81 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance from IEE) (List from IEE) Monitored (As Monitoring Monitoring Monitoring Person Status/ a minimum Conducted Who Explanation those Conducted identified in the the IEE should Monitoring be monitored) drainage and permissions as required under law, including patterns, Environmental Clearance prior to approval by PIU ponding and water logging, and water pollution. Failure to o Obtain all necessary consents, permits, clearance, NOCs, List of Checking All project Before Environment CTE for the WTP obtain etc. prior to award of civil works. applicable of locations commencement Specialist of has been necessary o Ensure that all necessary approvals for construction to be legislation documents of construction DSISC, PIU obtained consents, obtained by contractor are in place before start of and Consent to permits, NOCs, construction PMU/PMC Establish (CTE) etc. can result o Acknowledge in writing and provide report on compliance all for Batching to design obtained consents, permits, clearance, NOCs, etc. plant also revisions o Include in detailed design drawings and documents all obtained and/or conditions and provisions if necessary (Appendix I - 6). stoppage of Batching plant works not start functioning. Compliance statement for WTP CTE included in Appendix I - 6 Other relevant NOC will be obtained as per requirement and with progress of design Health risk due o Obtain details on location of underground asbestos cement asbestos Site Specific Daily visit by DSISC Complied. Till to exposure to materials cement inspection project construction Construction date no rubbish asbestos o Lay the new pipes carefully to avoid encountering asbestos materials location supervisor of Managemen containing materials cement pipes DSISC. t and asbestos cement o If found, leave the asbestos cement pipes undisturbed in the Weekly Environment has been found ground. visit by al Safeguard Construction Team Manager and

82 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance from IEE) (List from IEE) Monitored (As Monitoring Monitoring Monitoring Person Status/ a minimum Conducted Who Explanation those Conducted identified in the the IEE should Monitoring be monitored) Environment Team of DSISC of operational sites. Construction Phase Irreversible Project manager and all key workers will be required to undergo Induction & Review of Project - Environment Complied; impact to the training on EMP implementation including spoils/waste Awareness Training Locations Specialist of Site environment, management, Standard operating procedures (SOP) for Trainings records DSISC, PIU Environmental workers, and construction works; occupational health and safety (OHS), core Toolbox Talks Site and Safety community labor laws, applicable environmental laws, etc. Safeguard Inspections PMU training and Trainings awareness including COVID 19 pandemic mitigation arranged on regular basis (sample attached as Appendix I - 14) Emissions from For all construction works o Location of Site Covering Air – noise DSISC Complied; construction o Comply with the Direction of West Bengal Department of stockpiles inspection different monitoring: Construction During vehicles, Environment under the Air Act, 1981 in controlling air Public locations. Once before Managemen construction data equipment, and pollution from construction activities o Complaints grievance Air – start of t and has been machinery o Comply with the air pollution / dust control measures for from register monitoring: construction Environment collected results used for construction activities stipulated by the “Direction of West sensitive Monitoring is Yearly 3 times al Safeguard attached as installation of Bengal Department of Environment under the Air Act, receptors expected to during Team, PIU Appendix I - 13. pipelines 1981 Direction No. EN/3170/T-IV-7/001/2009 dated: 10 be construction (3- resulting to December 2009” o Monitoring conducted at year period After Emission of dusts and o Damp down the soil and any stockpiled material on site by data- 5 locations. considered) Lockdown equipment and increase in water sprinkling; PM10, Pre limited Site vehicle tested. concentration o Use tarpaulins to cover the loose material (soil, sand, PM2.5 construction Monitoring Visit has PUC certificate of vehicle- aggregate etc.,) when transported by trucks; NO2, SO2, Monitoring conducted been obtained for related o Provide a dust screen around the construction sites at CO remaining at between 15-10- conducted Vehicle pollutants such GLSR and WTP work sites GLSR sites. 2020 to 17-10- since June (Appendix I - 2) as carbon o Clean wheels and undercarriage of haul trucks prior to o Heavy During 2020 2020. monoxide, leaving construction site/quarry equipment construction Relevant sulfur oxides, o Control dust generation while unloading the loose material and monitoring regulation under machinery

83 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance from IEE) (List from IEE) Monitored (As Monitoring Monitoring Monitoring Person Status/ a minimum Conducted Who Explanation those Conducted identified in the the IEE should Monitoring be monitored) particulate (particularly aggregate, soil) at the site by sprinkling water with air was compliance. matter, nitrous and unloading inside the barricaded area pollution conducted at Other activities oxides, and o Stabilize surface soils where loaders, support equipment control WTP and like dust hydrocarbons. and vehicles will operate by using water and maintain Booster suppression, surface soils in a stabilized condition o Water pumping covering of loose o Use tarpaulins to cover the loose material (soil, sand, sprinkling station only. materials, dust aggregate etc.,) when transported by trucks; arrangeme screen will be o Apply water and maintain soils in a visible damp or crusted nt arranged. condition for temporary stabilization For pipe line o Apply water prior to leveling or any other earth moving o Cover work, activity to keep the soil moist throughout the process materials barricading, o Cover the soil stocked at the sites with tarpaulins removal of earth, o Control access to work area, prevent unnecessary backfilling will be movement of vehicle, public trespassing into work areas; done as per limiting soil disturbance will minimize dust generation SEMP o Ensure that all the construction equipment, machinery is fitted with pollution control devises, which are operating correctly, and have a valid pollution under control (PUC) certificate Pipeline works o Barricade the construction area using hard barricades (of 2 m height) on both sides and provide dust/wind screen (such geo textile fabric) up to 3 m height (1m above the hard barricading) o Initiate site clearance and excavation work only after barricading of the site is done o Confine all the material, excavated soil, debris, equipment, machinery (excavators, cranes etc.,), to the barricaded area o Limit the stocking of excavated material at the site; remove the excess soil from the site immediately to the designated disposal area o Undertake the work section wise: 100 – 200 m section should be demarcated and barricaded o Conduct work sequentially - excavation, pipe laying, backfilling; conduct pipe testing section-wise (for a minimum length as possible) so that backfilling, stabilization of soil can be done.

84 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance from IEE) (List from IEE) Monitored (As Monitoring Monitoring Monitoring Person Status/ a minimum Conducted Who Explanation those Conducted identified in the the IEE should Monitoring be monitored) o Remove the excavated soil of first section to the disposal site; as the work progresses, sequentially, by the time second section is excavated, the first section will be ready for back filling, use the freshly excavated soil for back filling, this will avoid stocking of material, and minimize the dust. o Backfilled trench at any completed section after removal of barricading will be the main source of dust pollution. The traffic, pedestrian movement and wind will generate dust from backfilled section. Road restoration shall be undertaken immediately. Mobilization of o All earthworks be conducted during the dry season to • Areas for Site All project Daily visit by DSISC Silt trap settled silt prevent the problem of soil run-off during monsoon stockpiles, inspection locations construction Construction arranged, fuel - materials, and season; storage Public supervisor of Managemen lubricants yet to chemical o Avoid stockpiling of earth fill especially during the of fuels and grievance DSISC. Weekly t and purchase, contamination monsoon season unless covered by tarpaulins or plastic lubricants and register visit by Environment designated site from fuels and sheets; waste materials Construction al Safeguard for waste lubricants o Prioritize re-use of excess spoils and materials in the • Number of silt Manager, Visit by Team disposal under during construction works. If spoils will be disposed, only traps Environment consideration. All construction designated disposal areas shall be used; installed along Safeguard Team. Post safety aspect can o Install temporary silt traps or sedimentation basins along the drainages (in Lockdown, maintained. Contaminate drainage leading to the water bodies; slope) leading Partial Site nearby o Place storage areas for fuels and lubricants away from any to visits are surface water drainage leading to water bodies; water bodies conducted quality. o Store fuel, construction chemicals etc., on an impervious • Entry routes from June Ponding of floor, also avoid spillage by careful handling of pollutant in 2020 water in the o Dispose any wastes generated by construction activities in nearby pits /foundation designated sites; Waterbodies excavations o Conduct surface quality inspection according to the Environmental Management Plan (EMP). o Create a temporary drainage channel around the work area to arrest the entry of runoff from upper areas into the work area o Pump out the water collected in the pits / excavations to a temporary sedimentation pond; dispose of only clarified water into drainage channels/streams after sedimentation in the temporary ponds o Consider safety aspects related to pit collapse due to

85 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance from IEE) (List from IEE) Monitored (As Monitoring Monitoring Monitoring Person Status/ a minimum Conducted Who Explanation those Conducted identified in the the IEE should Monitoring be monitored) accumulation of water Increase in o Plan activities in consultation with PIU so that activities Day time and • Checking Covering Air – noise DSISC Complied; pre- noise level with the greatest potential to generate noise are conducted night time noise of records different monitoring: Construction construction due to earth- during periods of the day which will result in least levels. • Visual locations. Once before Managemen baseline and moving and disturbance; inspection Air – start of t and during excavation o Horns should not be used unless it is necessary to warn of sites monitoring: construction Environment construction data equipment, other road users or animals of the vehicle’s approach; Monitoring is Yearly 3 times al Safeguard has been and the o Minimize noise from construction equipment by using expected to during Team, PIU collected. transportation vehicle silencers, fitting jackhammers with noise-reducing be construction (3- of equipment, mufflers, and use portable street barriers to minimize conducted at year period After There is no as materials, and sound impact to surrounding sensitive receptor; and 5 locations. considered) Lockdown such noise people o Maintain maximum sound levels not exceeding 80 Pre limited Site generated from decibels (dBA) when measured at a distance of 10 m or construction Monitoring Visit has equipment. more from the vehicle/s. Monitoring conducted been Stipulated o Identify any buildings at risk from vibration damage and remaining at between conducted condition as per avoiding any use of pneumatic drills or heavy vehicles in GLSR sites. 15.10.2020- since June SEMP is the vicinity During 18.10.2020 2020. followed o Horns should not be used unless it is necessary to warn construction other road users or animals of the vehicle’s approach; monitoring o Consult local communities in advance of the work to was identify and address key issues, and avoid working at conducted at sensitive times, such as religious and cultural festivals. WTP and Booster pumping station only.

Impacts due o Prepare and implement a Construction Waste Management • Waste • Checking Project Daily visit by Environment Complied to excess Plan Management of records locations construction Specialist of excavated o As far as possible utilize the debris and excess soil in List • Visual supervisor of DSISC, PIU Excess earth earth, excess construction purpose, for example for raising the ground • Stockpile inspection DSISC. Weekly and Mostly used for construction level or construction of access roads etc., Management of sites visit by PMU/PMC Backfilling. materials, and o Stockpiles, lubricants, fuels, and other materials should be • Complaints Construction Domestic solid solid waste located away from steep slopes and water bodies; from Manager, Visit by Post waste collection such as o Avoid stockpiling any excess spoils at the site for long Sensitive Environment Lockdown, bin arranged removed time. Excess excavated soils should be disposed off to receptors Safeguard Team. Limited Site No as such stock concrete, approved designated areas immediately; • PMU/ PIU/ visits are piling allowed for wood, o If disposal is required, the site shall be selected preferably DSISC to conducted spoil

86 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance from IEE) (List from IEE) Monitored (As Monitoring Monitoring Monitoring Person Status/ a minimum Conducted Who Explanation those Conducted identified in the the IEE should Monitoring be monitored) packaging from barren, infertile lands; site should be located away report in from June materials, from residential areas, forests, water bodies and any other writing that 2020 empty sensitive land uses the necessary containers, o Domestic solid wastes should be properly segregated in environmental spoils, oils, biodegradable and non-biodegradable for collection and restoration lubricants, disposal to designated solid waste disposal site; create a work has and other compost pit at workers’ camp sites for disposal of been done similar items. biodegradable waste; non-biodegradable / recyclable material shall be collected separately and sold in the local recycling material market o Residual and hazardous wastes such as oils, fuels, and lubricants shall be disposed of in disposal sites approved by local authorities/WBPCB; o Prohibit burning of construction and/or domestic waste; o Ensure that wastes are not haphazardly dumped thrown within and around the project site and adjacent areas; provide proper collection bins, and create awareness to use the dust bins. o Conduct site clearance and restoration to original condition after the completion of construction work; PIU to ensure that site is properly restored prior to issuing of construction completion certificate Disruption of o Prepare a list of affected utilities and operators if any; • List of Observation Project Daily visit by Environment Complied as service and o Prepare a contingency plan to include actions to be done in affected and locations construction Specialist of Per requirement. Damage to case of unintentional interruption of service utilities if any document supervisor of DSISC, PIU Consultation existing and checking DSISC. Weekly and with utility infrastructure operators visit by PMU/PMC dept.as and at specified • Public Construction when required; project grievance Manager, Visit by pipeline laying location Environment has not yet Safeguard Team. started Loss of o Minimize removal of vegetation and disallow cutting of Tree felling • Checking Project Daily visit by Environment As of now, tree vegetation trees; requirement of records locations construction Specialist of felling and tree cover o If tree-removal will be required, obtain tree-cutting permit and • Visual supervisor of DSISC, PIU requirement is and afforestation inspection DSISC. Weekly and not envisaged. o Plant 5 native trees for every one that is removed. after final of sites visit by PMU/PMC design Construction

87 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance from IEE) (List from IEE) Monitored (As Monitoring Monitoring Monitoring Person Status/ a minimum Conducted Who Explanation those Conducted identified in the the IEE should Monitoring be monitored) Manager, Visit by Environment Safeguard Team. Traffic Hauling (material, waste/debris and equipment) activities • Traffic Site visit Project Daily visit by Environment Complied; problems and o Plan transportation routes so that heavy vehicles do not use Management and locations construction Specialist of WTP location is conflicts near narrow local roads, except in the immediate vicinity of Plan document supervisor of DSISC and within the PHED project delivery sites • Public review DSISC. Weekly PIU campus, no locations and o Schedule transport and hauling activities during non-peak grievance visit by traffic haul road hours; • Number of Construction management is o Locate entry and exit points in areas where there is low signages Manager, Visit by required. potential for traffic congestion; placed at Environment As of now no o Drive vehicles in a considerate manner subproject Safeguard Team. pipeline work o Notify affected public by public information notices, location has started and providing sign boards informing nature and duration of no grievance has construction works and contact numbers for concerns / been registered. complaints. During pipe Pipeline works laying all Traffic o (i) Confine work areas along the roads to the minimum Management possible extent; all the activities, including material and rules will be waste/surplus soil stocking should be confined to this area. followed Proper barricading should be provided; avoid o material/surplus soil stocking in congested areas – immediately removed from site/ or brought to the as and when required. o Leave spaces for access between mounds of soil to maintain access to the houses / properties o Provide pedestrian access in all the locations; provide wooden/metal planks over the open trenches at each house to maintain the access. o Inform the affected local population 1-week in advance about the work schedule o Plan and execute the work in such a way that the period of disturbance/ loss of access is minimum. o Keep the site free from all unnecessary obstructions; o Coordinate with Traffic Police for temporary road diversions, where necessary, and for provision of traffic aids if transportation activities cannot be avoided during peak hours

88 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance from IEE) (List from IEE) Monitored (As Monitoring Monitoring Monitoring Person Status/ a minimum Conducted Who Explanation those Conducted identified in the the IEE should Monitoring be monitored) Generation of o Employ local labor force as far as possible Employment Checking of Project Daily visit by Environment Direct and temporary o Comply with labor laws record records locations construction Specialist of indirect employment supervisor of DSISC, PIU employment for and DSISC. Weekly and local population increase in visit by PMU/PMC local revenue Construction Manager, Visit by Environment Safeguard Team. Occupational o Comply with all national, state and local core labor laws • Site-specific • Checking Project Daily visit by Environment Complied. hazards (see Appendix 7of this IEE) Health and of records locations construction Specialist of which can o Develop and implement site-specific occupational health Safety (H&S) • Visual supervisor of DSISC; PIU Site-specific arise during and safety (OHS) Plan which will include measures such Plan inspection DSISC. Weekly and Health and work as: (a) excluding public from the site; (b) ensuring all • Equipped first- of sites visit by PMU/PMC Safety (H&S) workers are provided with and use personal protective aid Construction Plan under equipment like helmet, gumboot, safety belt, gloves, nose stations; Manager, Visit by Limited Site implementation. musk and ear plugs; (c) OHS Training for all site personnel; • Medical Environment visits are OHS plan (d) documented procedures to be followed for all site insurance Safeguard Team. conducted submitted by activities; and (e) documentation of work-related accidents; coverage for from June contractor and o Ensure that qualified first-aid can be provided at all times. workers 2020 due to approved by Equipped first-aid stations shall be easily accessible • Number of COVID 19 DSISC and PIU. throughout the site; accidents pandemic That document o Provide medical insurance coverage for workers; • Supplies of is available with o Secure all installations from unauthorized intrusion and potable drinking DSISC and PIU accident risks; water; However, the o Provide supplies of potable drinking water; • Record of existing H&S o Provide clean eating areas where workers are not exposed H&S plan is revisited to hazardous or noxious substances; orientation including o Provide health and safety orientation training to all new trainings preventive and workers to ensure that they are apprised of the basic site • Personal mitigative rules of work at the site, personal protective protection, and protective measures with preventing injuring to fellow workers; equipment respect to o Provide visitor orientation if visitors to the site can gain • Sign boards COVID-19 access to areas where hazardous conditions or substances for may be present. Ensure also that visitor/s do not enter hazardous Induction and hazard areas unescorted; areas tool box training o Ensure the visibility of workers through their use of high such as and COVID 19 visibility vests when working in or walking through heavy energized awareness

89 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance from IEE) (List from IEE) Monitored (As Monitoring Monitoring Monitoring Person Status/ a minimum Conducted Who Explanation those Conducted identified in the the IEE should Monitoring be monitored) equipment operating areas; electrical training arranged o Ensure moving equipment is outfitted with audible back-up devices by contractor alarms; and lines, and first aid o Mark and provide sign boards for hazardous areas such as service training arranged energized electrical devices and lines, service rooms rooms by DSISC housing high voltage equipment, and areas for storage and (sample shown disposal. Signage shall be in accordance with international in Appendix I - standards and be well known to, and easily understood by 14) workers, visitors, and the general public as appropriate; and Use of PPEs o Disallow worker exposure to noise level greater than 85 noted mostly. dBA for a duration of more than 8 hours per day without Visibility vest hearing protection. The use of hearing protection shall be also used. enforced actively. . Drinking water and first aid box available at site. . Medical Insurance arranged for the labourer (see Appendix I - 4). Medical tie up with health institute done (Appendix I - 16) but regular health checking of workers pending under COVID 19 situation. But daily health checkup for COVID 19 infection continued for workers.

90 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance from IEE) (List from IEE) Monitored (As Monitoring Monitoring Monitoring Person Status/ a minimum Conducted Who Explanation those Conducted identified in the the IEE should Monitoring be monitored)

No as such noise producing equipment available at site

Accident register is maintained at site. Till date no major accident recorded. Only minor first aid cases recorded. Sample attached as Appendix I - 15. Health risk due o Obtain details on location of underground asbestos cement asbestos Site Specific Daily visit by DSISC Till date no to exposure to materials cement inspection project construction Construction asbestos cement asbestos o Lay the new pipes carefully to avoid encountering asbestos materials location supervisor of Managemen material has materials cement pipes DSISC. t and been found on o If found, leave the asbestos cement pipes undisturbed in Weekly Environment site the ground. visit by al Safeguard Construction Team Manager and Environment Team of DSISC of operational sites. Traffic o Restrict construction vehicle movements to defined access Public Review of Project Daily visit by Environment Work continued accidents and roads and demarcated working areas (unless in the event of grievance documents Locations construction Specialist of within fixed WTP vehicle collision an emergency) supervisor of DSISC and campus. No with o Enforce strict speed limit (20-30 kmph) for playing on DSISC. Weekly PIU pedestrian pedestrians unpaved roads, construction tracks visit by accident has during material o Night-time haulage will be by exception only, as approved Construction been recorded and waste by the PIU to minimize driving risk and disturbance to Manager, Visit by till date transportation communities Environment No traffic control o Adopt standard and safe practices for micro tunneling Safeguard Team. and application

91 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance from IEE) (List from IEE) Monitored (As Monitoring Monitoring Monitoring Person Status/ a minimum Conducted Who Explanation those Conducted identified in the the IEE should Monitoring be monitored) o Temporary traffic control (e.g. flagmen) and signs will be of traffic provided where necessary to improve safety and provide management directions plan is required. o All drivers will undergo safety and training Only during o Public access to all areas where construction works are on- transportation, going will be restricted through the use of barricading and entry of vehicle security personnel at construction o Warning signs, blinkers will be attached to the barricading site controlled by to caution the public about the hazards associated with the concerned works, and presence of deep excavation construction o The period of time when the pipeline trench is left open will supervisor be minimized through careful planning o Control dust pollution – implement dust control measures as suggested under air quality section o Maintain regularly the vehicles and use of manufacturer- approved parts to minimize potentially serious accidents caused by equipment malfunction or premature failure. o Provide road signs and flag persons to warn of on-going trenching activities. Temporary air o Ensure that a proper compound wall is provided, and erect • Public Site Construction Daily visit by Environment Mostly and noise a wind/dust screen around grievance inspection camps construction Specialist of Complied. pollution from o Camp site shall not be located near (100 m) water bodies, • and review supervisor of DSISC and Labour camp, machine flood plains flood prone/low lying areas, or any ecologically, Accommodatio of DSISC. Weekly PIU access to labour operation, socially, archeologically sensitive areas n documents visit by camp, toilet & water pollution o Separate the workers living areas and material storage • Water and Construction kitchen facilities from storage areas clearly with a fencing and separate entry and exit sanitation Manager, Visit by improved after and use of o Provide proper temporary accommodation with proper facilities Environment instruction to fuels, oils, materials, adequate lighting and ventilation, appropriate for employees Safeguard Team. contractor and solvents, and facilities for winters and summers; ensure conditions of • Housekeeping follow up by lubricants livability at work camps are maintained at the highest – DSISC and PMC Unsanitary and standards possible at all times; regular disposal experts. poor living o Consult PIU before locating project offices, sheds, and of Storage and conditions for construction plants; (viii)Minimize removal of vegetation and solid waste disposal of solid workers disallow cutting of trees waste planned o Ensure conditions of livability at work camps are maintained accordingly. at the highest standards possible at all times; living quarters Site photo in and construction camps shall be provided with standard Appendix I - 1. materials (as far as possible to use portable ready to fit-in

92 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance from IEE) (List from IEE) Monitored (As Monitoring Monitoring Monitoring Person Status/ a minimum Conducted Who Explanation those Conducted identified in the the IEE should Monitoring be monitored) reusable cabins with proper ventilation); thatched huts, and facilities constructed with materials like GI sheets, tarpaulins, etc., shall not be allowed as accommodation for workers o Camp shall be provided with proper drainage, there shall not be any water accumulation o Provide drinking water, water for other uses, and sanitation facilities for employees o Prohibit employees from cutting of trees for firewood; contractor should be provided proper facilities including cooking fuel (oil or gas; fire wood not allowed) o Train employees in the storage and handling of materials which can potentially cause soil contamination o Recover used oil and lubricants and reuse or remove from the site o Manage solid waste according to the following preference hierarchy: reuse, recycling and disposal to designated areas; provide a compost pit for biodegradable waste, and non-biodegradable / recyclable waste shall be collected and sold in local market o Remove all wreckage, rubbish, or temporary structures which are no longer required o At the completion of work, camp area shall be cleaned and restored to pre-project conditions, and submit report to PIU; PIU to review and approve camp clearance and closure of work site There are no o Consult Archaeological Survey of India (ASI) or West Site inspection Site Project Daily visit by Environment No chance finds protected Bengal State Archaeology Department to obtain an expert records inspection Locations construction Specialist of to date. properties in assessment of the archaeological potential of the site. and review supervisor of DSISC and the subproject o Include state and local archaeological, cultural and historical of DSISC. Weekly PMU/PMC sites. However, authorities, and interest groups in consultation forums as documents visit by in case of project stakeholders so that their expertise can be made Construction chance finds, available. Manager, Visit by contractors will o In case of chance finds, works must be stopped immediately Environment be required to until such time chance finds are cleared by experts Safeguard Team. follow a protocol as defined in the

93 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance from IEE) (List from IEE) Monitored (As Monitoring Monitoring Monitoring Person Status/ a minimum Conducted Who Explanation those Conducted identified in the the IEE should Monitoring be monitored) mitigation measures. Unsatisfactory o Appointment of (I) Environment, Health and Safety (EHS) Appointment Review of - - Environment Complied compliance to Supervisor to ensure EMP implementation letter records Specialist of Monitoring report EMP o Timely submission of monitoring reports including pictures Monitoring DSISC and submitted timely. records PIU Damage due to o Remove all spoils wreckage, rubbish, or temporary Stockpile Review of Project Daily visit by Environment Complied; Spoil debris, spoils, structures (such as buildings, shelters, and latrines) which Management documents Locations construction Specialist of Management excess are no longer required; and Spoil and site supervisor of DSISC and Plan has been construction o All excavated roads shall be reinstated to original condition. Management inspections DSISC. Weekly PIU submitted for the materials o All disrupted utilities restored Restoration of visit by WTP o All affected structures rehabilitated/compensated sites Construction construction o The area that previously housed the construction camp is to Manager, Visit by No pipe laying be checked for spills of substances such as oil, paint, etc. Environment work started. and these shall be cleaned up. Safeguard Team. Spoil o All hardened surfaces within the construction camp area management shall be ripped, all imported materials removed, and the plan will be area shall be top soiled and re-grassed using the guidelines updated as a set out in the re-vegetation specification that forms part of part of SEMP. this document. o The contractor must arrange the cancellation of all temporary services. quest PIU to report in writing that worksites and camps have been vacated and restored to pre-project conditions before acceptance of work. Operational Phase Public health, o Operate as per the Operational Manual following Standard Health records Review of Project - Environment NA at the safety and Operating Procedures as per the WTP design Facility records facilities specialist of present project environmental o Undertake preventive and periodic maintenance activities inspection DSISC; PIU stage impacts as required records and o Ensure periodic training to staff in WTP operation, Incident reports PMU/PMC especially in chemical handling and dosing, filter backwash, etc., o replace pumps, motors and other parts as per the operating life prescribed by manufacturer o Maintain the mechanical parts as per the maintenance plan to avoid any hazards. o Ensure that all safety apparatus at WTP including personal

94 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance from IEE) (List from IEE) Monitored (As Monitoring Monitoring Monitoring Person Status/ a minimum Conducted Who Explanation those Conducted identified in the the IEE should Monitoring be monitored) protection equipment are in good condition all times; and are at easily accessible and easily identifiable place; periodically check the equipment, and conduct mock drills to deal with emergency situations o Ensure that backwash recirculation system and sludge management system are operated as per the manual Loss of water, Effectiveness of leak detection and water auditing to reduce the DCS system Review of Bulk - Environment NA at the increased water losses. water balance data Distribution specialist of present project demand and network DSISC; PIU stage Inconvenience and to consumers PMU/PMC and general public Health, social o Provide appropriate PPE and training on its proper use and Facility Review of Project - Environment NA at the and economic maintenance. inspection data locations, specialist of present project impacts on the o Use fall protection equipment when working at heights. records especially DSISC; PIU stage workers o Maintain work areas to minimize slipping and tripping Incident register WTP site and Health & Safety hazards. PMU/PMC training will be o Implement a training program for operators who work with continued during chlorine regarding safe handling practices and emergency O & M stage response procedures. o Prepare escape plans from areas where there might be a chlorine emission. o Install safety showers and eye wash stations near the chlorine equipment and other areas where hazardous chemicals are stored or used. o Prohibit eating, smoking, and drinking except in designated areas. Water pollution, Sanitation and sewerage/septage facilities needs to be Health records Review of Project - Environment NA at the and impacts on improved/provided in the project area to suit the increased increase in records influenced specialist of present project public health sewage generation sewage facility area DSISC; PIU stage and and environment PMU/PMC

95 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Table 10: Summary of Environmental Monitoring Activities for the Package WBDWSIP/DWW/NCB/N24P/02A/2017-18: Water Supply Distribution at Haroa Block and Package WBDWSIP/DWW/NCB/N24P/02B/2017-18: Water Supply Distribution at Bhangar II Block Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B Design Phase Source (i) Gravity distribution system: • Design philosophy Document All project Before Environment Complied; Complied; sustainability designing the entire system to • Project QA/QC review and locations commencement Specialist of Distribution Design and efficiency maintain optimal flow and plan LOP Survey of final design DSISC; PIU network completed and terminal pressure, and • Selection and PMC finalized and Pipe laying optimizing the overall energy methodology for pipe laying work work continued usage distribution continued at 18 at 15 zones - (ii)Implementation of a water network zones- 1 to 6, 8, 1,3,4,6 to 17 quality surveillance program 10, 12 to 21 including development of a laboratory as part of the project to ensure that supplied water meets the drinking water standards (iii)Minimizing water losses from pipelines by perfect jointing and alignments using appropriate techniques (iv) Reducing the incidence of water borne diseases by providing 100% population including urban poor with potable water supplies Socio (i) Avoid using low-lying lands List of selected Site survey All OHR sites Before Environment Complied; No Complied; No economic / ponds for construction of location for OHRs commencement Specialist of low-lying lands low-lying lands impact – loss OHRs; alternative private of final design DSISC and or ponds are or ponds are fishery area lands may be explored within PMC being filled for being filled for the vicinity; construction. construction. (ii)Review the applicability of West Bengal Inland Fisheries Act, 1984, whether the site falls under the definition of fisher area; obtained permission from Fisheries Department if required prior to start of construction

96 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B Tree cutting (i) Minimize removal of trees • Tree felling Site survey All project Before Environment Complied; Under by adopting to site condition requirement – site and review of locations commencement Specialist of except Zone 18: compliance, no and with appropriate layout layout plan site layout/ of final design DSISC; PIU Gopalpur no further tree design of OHRs within the • NOC – paper pipeline and other sites felling sites documents from alignment plan PMC requirement for envisaged yet (ii)Avoid cutting of trees by line agency tree felling has In case of tree adopting suitable alignment been envisaged felling action changes as required during till date. NOC will be taken laying of pipelines; obtained and 11 for planation of (iii)In unavoidable cases, no of tree felling trees obtain prior permission for is done for that tree cutting site. (iv)Plant and maintain 5 trees Compensatory for each tree that is removed plantation is done for 55 no. of plants of multiple variety

Pre-Construction Phase Telephone (i) Identify and include List of affected Observation Specific Before Environment Complied; Complied; lines, electric locations and operators of utilities if any and and document project commencement Specialist of About 618 km of About 633 km poles and these utilities in the detailed operators checking location of construction DSISC and pipeline has of pipeline has wires, water design documents to prevent PIU been laid been laid lines within unnecessary disruption of Spoil Spoil proposed services during construction Management Management project area phase; and Plan & Traffic Plan & Traffic (ii) Require construction Management Management contractors to prepare a Plan available Plan available contingency plan to include with SEMP. As with SEMP. As actions to be taken in case of prepared zone prepared zone unintentional interruption of wise wise services. (iii) Require contractors to prepare spoils (waste) management plan and traffic management plan Conflicts with (i) Prioritize areas within or • List of selected • Site Specific Before Environment Complied Complied local nearest possible vacant location for OHRs observatio project commencement Specialist of No disruption No disruption community; space in the project location; • Involvement of n location of final design DSISC; PIU noted. noted.

97 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B disruption to (ii) If it is deemed necessary traffic dept. • Review of and and Area selected Area selected traffic flow and to locate elsewhere, consider • Road closure document commencement PMC nearby vacant nearby vacant sensitive sites that will not promote planning s of construction place place receptors instability and result in • Grievance No excess spoil No excess destruction of property, Register generated. spoil vegetation, irrigation, and Excess earth generated. drinking water supply utilized for back Excess earth systems; filling. utilized for (iii) Do not consider No complete back filling, residential areas; road closure which indicates (iv) Take extreme care in expected. in SEMP. selecting sites to avoid direct Partial closure No complete disposal to water body which noted, which road closure will inconvenience the mentioned in expected. community. traffic Partial closure (v) For excess spoil disposal, management noted, which ensure (a) site shall be plan mentioned in selected preferably from traffic barren, infertile lands. In case management agricultural land needs to be plan selected, written consent from landowners (not lessees) will be obtained; (b) debris disposal site shall be at least 200 m away from surface water bodies; (c) no residential areas shall be located within 50 m downwind side of the site; and (d) site is minimum 250 m away from sensitive locations like settlements, ponds/lakes or other water bodies. Extraction of (i) Obtain construction • List of approved • Checking Quarries Daily visit by DSISC Complied; Complied; materials can materials only from quarry sites and of records and construction Construction Royalty receipt Royalty receipt disrupt natural government approved sources of • Visual material supervisor of Management checked. checked. land contours quarries with prior approval of materials inspection source DSISC. and Approval Approval and vegetation PIU; • Construction of sites areas Weekly Environmental obtained obtained resulting in (ii) PIU to review, and ensure Contractor visit by Safeguard from DSISC, from DSISC,

98 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B accelerated that proposed quarry sources documentation Construction Team PIU before PIU before erosion, have all necessary Manager and procurement. procurement. disturbance in clearances/ permissions in Environment natural place prior to approval Team of DSISC drainage (iii) Contractor to submit to at operational patterns, PIU on a monthly basis sites. ponding and documentation on material water logging, obtained from each source and water (quarry/ borrow pit) pollution. (iv) Avoid creation of new borrow areas, quarries etc., for the project; if unavoidable, contractor to obtain all clearances and permissions as required under law, including Environmental Clearance prior to approval by PIU Failure to (i) Obtain all necessary List of applicable Checking All project Before Environment Complied and to NOC from obtain consents, permits, clearance, legislation of documents locations commencement Specialist of be continued as EKWMA necessary NOCs, etc. prior to award of of construction DSISC and per requirement obtained for consents, civil works. PMC pipelaying permits, (ii) Ensure that all necessary work in EKW NOCs, etc. approvals for construction to area i.e. Zone- can result to be obtained by contractor are 1, 2 and 18. design in place before start of NOC from revisions construction EKWMA is and/or (iii) Acknowledge in writing attached as stoppage of and provide report on Appendix I -8. works compliance all obtained Decided – not consents, permits, clearance, to construct NOCs, etc. OHR within (iv) Include in detailed design EKW zone. drawings and documents all For Zone 1, It conditions and provisions if is decided that necessary the water supply will be done using control valve,

99 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B No OHR will be constructed.

Alternate site has been selected for Zone 2 and 18 outside EKW. Health risk due (i) Obtain details on location Asbestos cement Site inspection Specific Daily visit by DSISC Complied. Till Complied. Till to exposure to of asbestos cement materials materials project construction Construction date no rubbish date no asbestos (ii) Lay the new piper carefully location supervisor of Management containing rubbish materials to avoid encountering AC DSISC. and asbestos containing pipes Weekly Environmental cement has asbestos (ii) Leave the AC pipes visit by Safeguard been found cement has undisturbed in the ground. Construction Team been found Manager and Environment Team of DSISC of operational sites. Construction Phase Irreversible (i) Project manager and all Induction & Awareness Review of Project - Environment Under Under impact to the key workers will be required Trainings Training Locations Specialist of compliance; compliance; environment, to undergo training on EMP Toolbox Talks records DSISC: PIU Site Site workers, and implementation including Safeguard Trainings Site and Environmental Environmental community spoils/waste management, Inspections PMC Safety Safety Standard operating training and training and procedures (SOP) for awareness awareness construction works; (including (including occupational health and COVID 19 COVID 19 safety (OHS), core labor laws, pandemic pandemic applicable environmental mitigation) mitigation) laws, etc. arranged by arranged by contractor on contractor on regular basis regular basis (Sample (Sample attached as attached as Appendix I - Appendix I -

100 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B 14) 14) Awareness Awareness program cum program cum training training arranged by arranged by DSISC which DSISC which shown in shown in Appendix I -14 Appendix I - 14 Emissions For all construction works • Location of Site inspection Project Daily visit by Environment Under Under from (i) Comply with the air stockpiles Public locations construction Specialist of compliance; compliance; construction pollution / dust control • Complaints from grievance Air- monitoring supervisor of DSISC; PIU about 618 km about 633 km vehicles, measures for construction sensitive register as per DSISC. Weekly and pipe line laid. pipe line laid. equipment, activities stipulated by the receptors selected sites visit by PMC and machinery “Direction of West Bengal • Monitoring data- in ref. to Construction Water Water used for Department of Environment PM!0, PM2.5, SEMP Manager, Visit by After Lockdown sprinkling done sprinkling done installation of under the Air Act, 1981 SO2, NO2, CO Environment limited Site as per as per pipelines Direction No. EN/3170/T-IV-7 • Heavy equipment Specialist and Visit has been requirement. requirement. resulting to /001/2009 dated: 10 and machinery Support conducted Pre- Pre- dusts and December 2009” with Environment staff since June construction construction increase in (ii) Damp down the soil and air pollution Air- monitoring 2020. and during and during concentration any stockpiled material on control schedule as per construction air construction air of vehicle- site by water sprinkling; • Water sprinkling SEMP quality quality related (iii)Use tarpaulins to cover the arrangement , monitoring monitoring pollutants such loose material (soil, sand, • Cover materials Monitoring done as per done as per as carbon aggregate etc.,) when conducted IEE (Complete IEE (Complete monoxide, transported by trucks; between result result sulfur oxides, (iv) Provide a dust 12/10/2020 and certificates certificates particulate screen/high compound wall 17/10/2020 for available in available in matter, nitrous around the construction sites package DSISC office as DSISC office oxides, and (OHRs) N24P/02A back up paper as hydrocarbons. (v) Clean wheels and and between and attached as back up paper undercarriage of haul trucks 14/10/2020 and Appendix I -13) and attached prior to leaving construction 16/10/2020 for Most of the as Appendix I site/quarry package 02B PUC certificate - 13) (vi) Control dust generation obtained for Most of the while unloading the loose Vehicle and PUC certificate material (particularly Equipment obtained for aggregate, soil) at the site by (Appendix I - 2 Vehicle and

101 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B sprinkling water and as sample) Equipment unloading inside the Other activities (Appendix I - barricaded area like dust 2 as sample) (vii) Stabilize surface soils suppression, Other activities where loaders, support covering of like dust equipment and vehicles will loose materials, suppression, operate by using water and dust screen covering of maintain surface soils in a arranged. loose stabilized condition materials, dust (viii) Apply water prior to For pipe line screen leveling or any other earth work, arranged. moving activity to keep the barricading, soil moist throughout the removal of For pipe line process earth, backfilling work, (ix) Control access to work done in most of barricading, area, prevent unnecessary the cases removal of movement of vehicle, public earth, trespassing into work areas; backfilling limiting soil disturbance will done in most minimize dust generation of the cases. (x) Ensure that all the construction equipment and machineries are fitted with pollution control devises, which are operating correctly, and have a valid pollution under control (PUC) certificate Pipeline works (i) Barricade the construction area (ii) Initiate site clearance and excavation work only after barricading of the site is done (iii)Confine all the material, excavated soil, debris, equipment, machinery (excavators, cranes etc.,), to the barricaded area

102 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B (iv) Limit the stocking of excavated material at the site; remove the excess soil from the site immediately to the designated disposal area (v) Undertake the work section wise (vi)Conduct work sequentially - excavation, pipe laying, backfilling; conduct pipe testing section-wise (for a minimum length as possible) so that backfilling, stabilization of soil can be done. (vii) Remove the excavated soil of first section to the disposal site; as the work progresses, sequentially, by the time second section is excavated, the first section will be ready for back filling, use the freshly excavated soil for back filling, this will avoid stocking of material, and minimize the dust. (viii) Backfilled trench at any completed section after removal of barricading will be the main source of dust pollution. The traffic, pedestrian movement and wind will generate dust from backfilled section. Road restoration shall be undertaken immediately. Mobilization of (i) All earthworks be • Areas for Site inspection All project Daily visit by Environment Mostly Mostly settled silt conducted during the dry stockpiles, storage Public locations construction Specialist of Complied Complied materials, and season to prevent the of fuels and grievance supervisor of DSISC: PIU Earth work Earth work

103 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B chemical problem of soil run-off during lubricants and register DSISC. Weekly and conducted conducted contamination monsoon season; waste materials visit by PMC during dry during dry from fuels and (ii) Avoid stockpiling of earth • Number of silt Construction season. season. lubricants fill especially during the traps Manager, Visit by After Lockdown No as such No as such during monsoon season unless installed along Environment limited Site requirement of requirement of construction covered by tarpaulins or drainages (in Specialist and Visit has been disposal of disposal of can plastic sheets; slope) leading to Support conducted spoil. Excess spoil. Excess contaminate (iii)Prioritize re-use of excess water bodies Environment staff since June earth utilized for earth utilized nearby surface spoils and materials in the • Entry routes of 2020. backfilling. for backfilling. water quality. construction works. If spoils pollutant in nearby Material never Material never Ponding of will be disposed, only Water bodies disposed in the disposed in the water in the designated disposal areas pond located pond located pits / shall be used; within this site. within this site. foundation (iv) Install temporary silt traps Silt traps / Silt traps / excavations or sedimentation basins along sediment basin sediment basin the drainage leading to the should be should be water bodies; installed prior to installed prior (v) Place storage areas for discharge of to discharge of fuels and lubricants away construction construction from any drainage leading to wastewater wastewater water bodies; from site. from site. (vi) Store fuel, construction Fuel storage not Fuel storage chemicals etc., on an started. not started. impervious floor, also avoid Surface water Surface water spillage by careful handling quality quality (vii) Dispose any wastes monitoring done monitoring generated by construction All safety aspect done activities in designated sites; maintained All safety and aspect (viii) Conduct surface quality maintained inspection according to the Environmental Management Plan (EMP). (ix) Create a temporary drainage channel around the work area to arrest the entry of runoff from upper areas into the work area (x) Pump out the water

104 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B collected in the pits / excavations to a temporary sedimentation pond; dispose of only clarified water into drainage channels/streams after sedimentation in the temporary ponds (xi) Consider safety aspects related to pit collapse due to accumulation of water Increase in (i) Plan activities in • Complaints from o Checking All project Daily visit by Environment Mostly Mostly noise level due consultation with PIU so that sensitive of records locations construction Specialist of Complied. Complied. to earth- activities with the greatest receptors o Visual Noise- supervisor of DSISC; PIU No such noise No such noise moving and potential to generate noise • Use of silencers in inspection monitoring as DSISC. Weekly and generating generating excavation are conducted during periods noise-producing of sites per selected visit by PMC problem near problem near equipment, of the day which will result in equipment and sites in ref. to Construction the project the project and the least disturbance; sound barriers SEMP Manager, Visit by After Lockdown location. location. transportation (ii) Horns should not be used • Monitoring data Environment limited Site Pre-construction Pre- of equipment, unless it is necessary to warn Specialist and Visit has been and during construction materials, and other road users or animals of Support conducted construction and during people the vehicle’s approach; Environment staff since June monitoring construction (iii) Minimize noise from 2020. done. monitoring construction equipment by Noise monitoring Monitoring will done. using vehicle silencers, fitting schedule as per be continued as Monitoring will jackhammers with noise- SEMP. per IEE and be continued reducing mufflers, and use SEMP. as portable street barriers to Monitoring Complete per IEE and minimize sound impact to conducted result SEMP. surrounding sensitive between certificates Complete receptor; and 12/10/2020 and available in result (iv) Identify any buildings at 17/10/2020 for DSISC office as certificates risk from vibration damage package back up paper available in and avoiding any use of N24P/02A and attached as DSISC office pneumatic drills or heavy and between Appendix I - as back up vehicles in the vicinity 14/10/2020 and 13. paper and (v) Horns should not be used 16/10/2020 for However, use of attached as unless it is necessary to warn package 02B ear plugs by Appendix I - other road users or animals of labourer 13 the vehicle’s approach; ensured during However, use

105 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B (vi) Consult local communities noisy activities. of ear plugs by in advance of the work to Honking labourer identify and address key generally ensured during issues, and avoid working at avoided at work noisy activities. sensitive times, such as sites. Honking religious and cultural festivals. generally avoided at work sites. Impacts due to (i) Prepare and implement a • Waste o Checking Project Daily visit by Environment Complied Complied excess Construction Waste Management of records locations construction Specialist of Excess earth Excess earth excavated Management Plan List o Visual supervisor of DSISC: PIU used mostly for used mostly for earth, excess (ii) As far as possible utilize • Stockpile inspection DSISC. Weekly and backfilling backfilling construction the debris and excess soil in Management of sites visit by PMC Excess spoils Excess spoils materials, and construction purpose, for • Complaints from Construction are not are not solid waste example for raising the Sensitive Manager, Visit by After Lockdown generally generally such as ground level or construction receptors Environment limited Site stockpiled stockpiled removed of access roads etc., • PMU/PIU/DSISC Specialist and Visit has been No hazardous No hazardous concrete, (iii) Stockpiles, lubricants, to report in writing Support conducted waste and waste and wood, fuels, and other materials that the necessary Environment staff since June construction construction packaging should be located away from environmental 2020. waste waste materials, steep slopes and water restoration work generated. generated. empty bodies; has been done containers, (iv)Avoid stockpiling any spoils, oils, excess spoils at the site for lubricants, and long time. Excess excavated other similar soils should be disposed of to items. approved designated areas immediately; (v) If disposal is required, the site shall be selected preferably from barren, infertile lands; site should be located away from residential areas, forests, water bodies and any other sensitive land uses (vi) Domestic solid wastes should be properly segregated in biodegradable

106 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B and non-biodegradable for collection and disposal to designated solid waste disposal site; create a compost pit at workers’ camp sites for disposal of biodegradable waste; non- biodegradable / recyclable material shall be collected separately and sold in the local recycling material market (vii) Residual and hazardous wastes such as oils, fuels, and lubricants shall be disposed of in disposal sites approved by local authorities/West Bengal Pollution Control Board (WBPCB); (viii) Prohibit burning of construction and/or domestic waste; (ix) Ensure that wastes are not haphazardly dumped thrown within and around the project site and adjacent areas; provide proper collection bins, and create awareness to use the dust bins. (x) Conduct site clearance and restoration to original condition after the completion of construction work; PIU to ensure that site is properly restored prior to issuing of construction completion certificate

107 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B Disruption of (i) Prepare a list of affected • List of affected Observation Project Daily visit by Environment Complied as Complied as service and utilities and operators if any; utilities if any and And document locations construction Specialist of Per Per damage to (ii) Prepare a contingency operators checking supervisor of DSISC and requirement. requirement. existing plan to include actions to be • Public grievance DSISC. Weekly PIU Consultation Consultation infrastructure done in case of unintentional visit by with utility dept. with utility at specified interruption of service Construction as and when dept. as and project location Manager, Visit by required when required Environment Specialist and Support Environment staff Loss of (i) Minimize removal of Tree felling o Checking Project Daily visit by Environment As of now, tree As of now, tree vegetation and vegetation and disallow requirement of records locations construction Specialist of felling will be felling tree cover cutting of trees, by adopting and afforestation after o Visual supervisor of DSISC and required only at requirement is best site layout and pipeline final design inspection DSISC. Weekly PMC Zone 18: not envisaged. alignments of sites visit by Gopalpur. (ii) If tree-removal will be Construction required, obtain tree-cutting Manager, Visit by NOC obtained permit and Environment for felling of (iii) Plant 5 native trees for Specialist and trees. every one that is removed. Support 11 no of tree Environment staff felling was done for that site. Compensatory plantation is done for 55 no. of plants of multiple variety

Traffic Hauling (material, • Traffic Site visit and Project Daily visit by Environment Complied; Complied; problems and waste/debris and Management Plan document locations construction Specialist of As of now about As of now conflicts near equipment) activities • Public grievance review supervisor of DSISC; PIU 618 km pipeline about 633 km project (i) Plan transportation routes • Number of DSISC. Weekly and has been laid. pipeline has locations and so that heavy vehicles do not signages placed visit by PMC Barricading been laid. haul road use narrow local roads, at subproject Construction done- partially Barricading except in the immediate location Manager, Visit by complied, done- partially vicinity of delivery sites Environment improvement complied. (ii) Schedule transport and Specialist and required. Local people hauling activities during non- Support Local people informed

108 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B peak hours; Environment staff informed before before start of (iii)Locate entry and exit start of work work points in areas where there is No No low potential for traffic transportation of transportation congestion; pipe/ material of pipe/ (iv) Drive vehicles in a done during material done considerate manner pick hours, no during pick (v) Notify affected public by impact on local hours, no public information notices, public impact on local providing sign boards movement. public informing nature and duration Access movement. of construction works and maintained in Access contact numbers for most of the maintained in concerns/complaints. cases at pipe most of the Pipeline works laying areas. In cases at pipe (i) Confine work areas along some cases, laying areas. the roads to the minimum cleaning of soil Work plan possible extent; all the is required from informed to activities, including material pipe laying area local public and waste/surplus soil Work plan atleast 1 week stocking should be confined informed to in advance. to this area. Provide local public barricading; avoid atleast 1 week material/surplus soil stocking in advance. in congested areas – immediately removed from site/ or brought to the as and when required (ii) Leave spaces for access between mounds of soil to maintain access to the houses / properties (iii)Provide pedestrian access in all the locations; provide wooden/metal planks over the open trenches at each house to maintain the access. (iv) Inform the affected local population 1-week in advance

109 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B about the work schedule (v) Plan and execute the work in such a way that the period of disturbance/ loss of access is minimum. (vi) Keep the site free from all unnecessary obstructions; (vii) Coordinate with Police for temporary road diversions, where necessary, and for provision of traffic aids if transportation activities cannot be avoided during peak hours Generation of (i) Employ local labor force as Employment record Checking of Project - Environment Direct and Direct and temporary far as possible records locations Specialist of indirect indirect employment (ii) Comply with labor laws DSISC and employment for employment and increase PMC local population for local in local - noted population - revenue noted Occupational (i) Comply with all national, • Site-specific o Checking Project Daily visit by Environment Site-specific Site-specific hazards which state and local core labor Health and Safety of records locations construction Specialist of Health and Health and can arise laws (H&S) Plan o Visual supervisor of DSISC and Safety (H&S) Safety (H&S) during work (ii) Develop and implement • Equipped first-aid inspection DSISC. Weekly PMC Plan under Plan under site-specific occupational stations; of sites visit by After Lockdown implementation. implementation health and safety (OHS) Plan • Medical insurance Construction limited Site . which will include measures coverage for Manager, Visit by Visit has been Copy of the such as: (a) excluding public workers Environment conducted approved Copy of the from the site; (b) ensuring all • Number of Specialist and since June Health and approved workers are provided with and accidents Support 2020. Safety plan Health and use personal protective • Supplies of Environment staff available with Safety plan equipment like helmet, potable drinking DSISC., PIU available with gumboot, safety belt, gloves, water; H & S training DSISC., PIU nose musk and ear plugs; (c) • Record of H&S including H & S training OHS Training for all site orientation COVID 19 including personnel; (d) documented trainings awareness done COVID 19 procedures to be followed for • Personal on regular basis. awareness all site activities; and (e) protective Sample training done on documentation of work- equipment document is regular basis.

110 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B related accidents; • Sign boards for attached as Sample (iii) Ensure that qualified first- hazardous areas Appendix I -14. training aid can be provided at all such as energized document is times. Equipped first-aid electrical devices Supplementary attached as stations shall be easily and lines, service COVID 19 H & Appendix I -14 accessible throughout the rooms S plan prepared Supplementary site; and compliance COVID 19 H & (iv) Provide medical insurance continued S plan coverage for workers; (Appendix I - prepared and (v) Secure all installations 12) compliance from unauthorized intrusion continued and accident risks; In respect of (Appendix I - (vi) Provide supplies of COVID-19 12) potable drinking water; pandemic, use In respect of (vii) Provide clean eating of Face Mask COVID-19 areas where workers are not and Social pandemic, use exposed to hazardous or Distancing of Face Mask noxious substances; measures were and Social (viii) Provide health and found absent in Distancing safety orientation training to certain measures all new workers to ensure that construction were found they are apprised of the basic sites including absent in site rules of work at the site, OHR in Zone certain personal protective 6,8,12,15,21 construction protection, and preventing and Pipeline in sites including injuring to fellow workers; Zone 5. Zone 17 and 8 (ix) Provide visitor orientation in pipeline and if visitors to the site can gain Drinking water zone 10,13,15 access to areas where and first aid box in OHR. hazardous conditions or available at site. substances may be present. Drinking water Ensure also that visitor/s do Partial use of and first aid not enter hazard areas PPEs- noted. box unescorted; • Missing PPEs available (x) Ensure the visibility of particularly use partially. workers through their use of of safety shoes, high visibility vests when ear plug was • In First aid box working in or walking through noted at few several heavy equipment operating sites (Haroa – medicines

111 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B areas; Zone 6, Zone 8, were found (xi) Ensure moving equipment and Zone 12) missing in is outfitted with audible back- certain sites of up alarms; Tie up letter with Bhangar II – (xii) Mark and provide sign nearby health zone 17, zone boards for hazardous areas center in case of 10. such as energized electrical emergency devices and lines, service obtained rooms housing high voltage (Appendix I - Partial use of equipment, and areas for 16). Health PPEs- noted. storage and disposal. check-up not • Missing PPE, Signage shall be in done during particularly use accordance with international report period of safety standards and be well known due to COVID shoes, ear to, and easily understood by 19 situation plug, goggles workers, visitors, and the are serious general public as appropriate Medical issues at few Insurance sites e.g. arranged for the (Bhangar II – labourer (see Zone 13) Appendix I - 4). Tie up letter Accident/ First with nearby aid register is health center in maintained at case of each site. There emergency are no first aid obtained cases reported (Appendix I - during report 16). Health period check-up done for worker (Appendix I - 16)

Medical Insurance arranged for the labourer (see

112 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B Appendix I - 4). Accident/ First aid register is maintained at each site. There are no first aid cases reported during report period Health risks (i) leave AC pipes in-situ Decommissioned AC Site inspection Project Daily visit by Environment Till date no AC Till date no AC associated untouched Pipes locations construction Specialist of pipes has been pipes has been with AC pipes supervisor of DSISC and found found DSISC. Weekly PMC visit by Construction Manager, Visit by Environment Specialist and Support Environment staff

Impact on (i) Restrict construction Public grievance Review of Project Daily visit by Environment Complied Complied community vehicle movements to defined documents Locations construction Specialist of safety. Traffic access roads and supervisor of DSISC; PIU No pedestrian No pedestrian accidents and demarcated working areas DSISC. Weekly and accident has accident has vehicle (unless in the event of an visit by PMC been recorded been recorded collision with emergency) Construction After Lockdown till date. till date. pedestrians (ii) Enforce strict speed limit Manager, Visit by limited Site Pipe line laying Pipe line laying during material (20-30 kph) for playing on Environment Visit has been work continued. work and waste unpaved roads, construction Specialist and conducted • Barricades and continued. transportation tracks Support since June caution tapes in • Barricades and (iii) Night-time haulage will be Environment staff 2020. work areas, in caution tapes by exception only, as particular along in work areas, approved by the PIU to the pipelines in particular minimize driving risk and has improved along the disturbance to communities for most of the pipelines were (iv) Adopt standard and safe sites in Haroa.. found mostly practices for micro tunneling At Zone 2, satisfactory

113 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B (vi) Temporary traffic control separate lane except at few (e.g. flagmen) and signs will for movement of sites like be provided where necessary school children Bhangar II- to improve safety and provide as well as Zone 15 directions safety . (vii) All drivers will undergo coordinator All safety safety and training should be measures (viii) Public access to all areas provided during arranged. where construction works are school opening No trench will on-going will be restricted and closing be kept open through the use of barricading hours. after pipe and security personnel All safety laying. Caution (ix) Warning signs, blinkers measures tape will be will be attached to the arranged. placed. barricading to caution the No trench will public about the hazards be kept open associated with the works, after pipe and presence of deep laying. Caution excavation tape will be (x) The period of time when placed. the pipeline trench is left open will be minimized through careful planning (xi) Control dust pollution – implement dust control measures as suggested under air quality section (xii) Maintain regularly the vehicles and use of manufacturer-approved parts to minimize potentially serious accidents caused by equipment malfunction or premature failure. (xiii) Provide road signs and flag persons to warn of on- going trenching activities. Impact on (i) As far as possible located • Public grievance Site inspection Construction Daily visit by Environment Partially Partially work camps the camp site within the work • Accommodation and review of camps construction Specialist of Complied Complied

114 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B and work site. sites; if any camp to be • Water and documents supervisor of DSISC and Temporary air established outside these, sanitation facilities DSISC. Weekly PMC However, However, and noise then select a camp site away for employees visit by housekeeping, housekeeping, pollution from from residential areas (at • Housekeeping – Construction toilet facility, toilet facility, machine least 100 m buffer shall be regular disposal of Manager, Visit by testing of testing of operation, maintained) solid waste Environment drinking water, drinking water, water pollution (ii) Avoid tree cutting for Specialist and provision of fuel provision of from storage setting up camp facilities Support (kerosene or fuel (kerosene and use of (iii) Camp site shall not be Environment staff LPG) for or LPG) for fuels, oils, located near (100 m) water cooking, cooking, solvents, and bodies, flood plains flood provision of provision of lubricants prone/low lying areas, or any solid waste and solid waste Unsanitary and ecologically, socially, wastewater and poor living archeologically sensitive disposal are wastewater conditions for areas some of the disposal are workers (iv) Separate the workers aspects some of the living areas and material requiring aspects storage areas clearly with a improvement. requiring fencing and separate entry improvement. and exit • Provision of • (v) Provide proper temporary basic facilities • Provision of accommodation with proper (like bed, basic facilities materials, adequate lighting drinking water (like bed, and ventilation, appropriate fuel for cooking, drinking water facilities for winters and toilets at site) to fuel for summers; ensure conditions labourers in the cooking, toilets of livability at work camps are construction at site) to maintained at the highest camp sites at labourers in standards possible at all Haroa – Zone 6, the times; Zone 8- was construction (vi) Consult PIU before found camp sites at locating project offices, unsatisfactory. Bhangar II – sheds, and construction • Access needs Zone 13 and plants; to be improved 15 – was found (vii) Minimize removal of near the camp. unsatisfactory. vegetation and disallow • Housekeeping Housekeeping cutting of trees near work site near work site (viii) Ensure conditions of and worker’s and worker’s livability at work camps are camp need to camp need to

115 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B maintained at the highest be improved. be improved. standards possible at all • In order to avoid • times; living quarters and contamination • construction camps shall be of groundwater, • Management provided with standard pre-fabricated of toilet waste materials (as far as possible bio-toilets have at camp sites, to use portable ready to fit-in been installed at use of pit reusable cabins with proper certain sites latrines are ventilation); thatched huts, (e.g. Zone-2, 6, serious and facilities constructed with 8, 13, 15 and concern. materials like GI sheets, 17) and (Bhangar II – tarpaulins, etc., shall not be Zone 13, 15) allowed as accommodation In zone 6 – • Instruction has for workers OHR black been given for (ix) Camp shall be provided patch is found in improvement. with proper drainage, there the soil due to • shall not be any water inappropriate • In order to accumulation handling of avoid (x) Provide drinking water, lubricating oil. contamination water for other uses, and of sanitation facilities for groundwater, employees pre-fabricated (xi) Prohibit employees from bio-toilets have cutting of trees for firewood; been installed contractor should be at certain sites providing proper facilities like Zone 4 including cooking fuel (oil or and 13. gas; fire wood not allowed) (xii) Train employees in the storage and handling of materials which can potentially cause soil contamination (xiii) Recover used oil and lubricants and reuse or remove from the site (xiv) Manage solid waste according to the following preference hierarchy: reuse,

116 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B recycling and disposal to designated areas; provide a compost pit for biodegradable waste, and non- biodegradable / recyclable waste shall be collected and sold in local market (xv) Remove all wreckage, rubbish, or temporary structures which are no longer required (xvi) At the completion of work, camp area shall be cleaned and restored to pre- project conditions, and submit report to PIU; PIU to review and approve camp clearance and closure of work site Unsatisfactory (i) Appointment of (I) • Appointment letter Review of - - Environment Safety person Safety person compliance to Environment, Health and • Monitoring records records Specialist of appointed from appointed from EMP Safety (EHS) Supervisor to DSISC and contractor end, contractor end, ensure EMP implementation PMC but environment but (ii) Timely submission of training is environment monitoring reports including required on training is pictures regular basis. required on Monitoring regular basis. report submitted Monitoring on monthly report basis. submitted on monthly basis. Analysis of monitoring Analysis of result indicates monitoring high PM 10 and result indicates PM 2.5 high PM 10 concentration in and PM 2.5 most of the concentration locations. in most of the Furthermore, locations.

117 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B marginal Furthermore, exceedance of marginal noise level was exceedance of also observed in noise level was most of the also observed locations. in most of the However, this locations. exceedance is However, this largely exceedance is attributable to largely high attributable to background high concentrations background concentrations Damage due (i) Remove all spoils • Stockpile Review of Project Daily visit by Environment Complied; Complied; to debris, wreckage, rubbish, or Management documents Locations construction Specialist of About 618 km About 633 km spoils, excess temporary structures (such as • Spoil and site supervisor of DSISC and pipe laying has pipe laying has construction buildings, shelters, and Management inspections DSISC. Weekly PMC been laid. been laid. materials latrines) which are no longer • Restoration of visit by Spoil Spoil required; and sites Construction Management Management (ii) All excavated roads shall Manager, Visit by Plan has been Plan has been be reinstated to original Environment submitted for submitted for condition. Specialist and the pipe laying the pipe laying (iii) All disrupted utilities Support work. work. restored Environment staff No utilities No utilities (iv) All affected structures affected during affected during rehabilitated/compensated pipe laying at pipe laying at (v) The area that previously village roads. village roads. housed the construction camp All excavated All excavated is to be checked for spills of road reinstated road reinstated substances such as oil, paint, to original to original etc. and these shall be condition condition cleaned up. (vi) All hardened surfaces within the construction camp area shall be ripped, all imported materials removed, and the area shall be top soiled and re-grassed using

118 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation identified in the IEE the Pack- Pack- should be monitored) Monitoring N24P/02A N24P/02B the guidelines set out in the re-vegetation specification that forms part of this document. (vii) The contractor must arrange the cancellation of all temporary services. (viii) Request PIU to report in writing that worksites and camps have been vacated and restored to pre-project conditions before acceptance of work.

119 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Table 11: Summary of Environmental Monitoring Activities for the Package WBDWSIP/DWW/NCB/BK/01/2017-18 and WBDWSIP/DWW/NCB/BK/03/2018-19: Bulk Water Supply for Bankura Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) Design Phase Source o Discontinuation of current unsafe o Design Document All project Before Environment Detailed Detailed design sustainability and unsustainable groundwater philosophy review and locations Commencement Specialist of design done completed as and efficiency sources and creating a new o Treatment LOP Survey and during DSISC, as per per guideline of comprehensive surface scheme final design PIU and guideline of IEE. water(river)based water supply o Project QA/QC PMU/PMC IEE. The water system plan The water treatment o Recovering wash water from treatment process work will treatment process to optimize the process work be continuing water use will be without o Treatment and reuse of sludge continuing disturbing the from treatment process without ground water o Designing the entire system to disturbing the source & maintain optimal flow and terminal ground water optimizing the pressure, and optimizing the source & overall energy. overall energy usage optimizing the Before supplying o Reducing the incidence of water overall of treated borne diseases by providing 100% energy. drinking water, it population including urban poor Before will ensure the with potable water supplies supplying of water test as per o Preparation and implementation of treated IS standard by a water quality surveillance drinking testing of water program including development of water, it will parameter at a laboratory as part of the project ensure the Laboratory by DBO contractor to ensure that water test as supplied water meets the drinking per IS water standards standard by o Development of laboratory with all testing of necessary environment, health and water safety measures and adopting parameter at international standard procedures Laboratory for water quality testing o Using low-noise and energy efficient pumping systems o Installing the noise-producing pumps and motors etc.in enclosed

120 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) buildings with noise reducing walls, and also maintaining adequate buffer to the nearby inhabited areas. Provision of appropriate personal protection equipment to the workers and staff Chlorine o Provide the following measure at o Project Document WTP and Before Environment Considered in Considered in handling and the chlorine application unit: emergency review Booster Commencement Specialist of design- at the design- at the application o Chlorine neutralization pit with a management pumping site and during final DSISC and chlorination chlorination risk– health lime slurry feeder plan design PIU room chlorine room chlorine and safety risk o Chlorine absorption and o Project safety neutralization neutralization pit to workers and neutralization facility and PPE plan pit & leakage & leakage general o Proper ventilation, lighting, entry o Training plan detector detector public and exit facilities provided for provided for o Visible and audible alarm facilities identification identification to alert chlorine gas leak purpose. purpose. o Facility for isolation in the event of The adequate The adequate major chlorine leakage lighting, lighting, o Eye wash and shower facility ventilation, ventilation, o Personal protection and safety proper access proper access & equipment for the operators in the & egress egress provide chlorine plant (masks, oxygen provide at at chlorination cylinders, gloves, etc.,) chlorination room. o Provide training to the staff in safe room. The Eye wash, handling and application of The Eye Shower, PPEs, chlorine; this shall be included in wash, SCADA & the contract of Chlorinator supplier Shower, handling manual o Supplier of Chlorinator equipment PPEs, in local language shall provide standard operating SCADA & is provide in manual handling design. for safe operation and as well as manual in maintenance and repairs; local preferably these shall be provided language is both in English and Bengali provide in Languages design. Tree cutting o Minimize removal of trees by o Tree felling o Checking Project Before Environment As of now, Total 232 adopting to site condition and with requirement of records locations Commencement Specialist of tree felling number of tree appropriate layout design of WTP and o Visual and during final DSISC and requirement is felling required

121 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) o Obtain prior permission for tree o afforestation inspection design PIU not envisaged at WTP site. cutting after final of sites at any project Necessary o Plant and maintain 5 trees for each design locations. permission tree that is removed obtained from Forest Department (Appendix II - 5) Tree felling will be done shortly Disturbance to o Diversion of drainage system o Location map o Checking Project Before Environment Will be Under natural o Minimization of impact on drainage o Design of records locations Commencement Specialist of complied compliance- drainage basin philosophy o Visual and during final DSISC, PIU during during inspection design and PMU/PMC implementatio implementation of sites n. Pre-Construction Phase Telephone o Identify and include locations and List of affected o Observatio Specific Before Environment The overhead The overhead LT lines, electric operators of these utilities in the utilities if any and n project commencement Specialist of LT power power supply poles and detailed design documents to operators and location of construction DSISC and supply line line pass over wires, water prevent unnecessary disruption of o Document PIU pass over WTP area. lines within services during construction checking WTP area. Communication proposed phase; and Communicati made for shifting project area o Require construction contractor to on made for of LT line. prepare a contingency plan to shifting of LT Permission include actions to be taken in case line. received, shifting of unintentional interruption of Permission of utility yet to be services. received, done o Require contractors to prepare shifting of Permission spoils management plan and traffic utility yet to received. Management plan be done Spoil and Traffic Procedure management has been plan submitted. initiated. Spoil and Traffic management plan submitted. Conflicts with o Prioritize areas within or nearest o List of selected o Site Specific Before Environment The area The area

122 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) local possible vacant space in the project location observatio project commencement Specialist of selected for selected for community; project location; and proposed n location of final design DSISC and construction construction disruption to o If it is deemed necessary to locate pipeline o Review of and PIU work camp is work camp is traffic flow and elsewhere, consider sites that will alignment plan document commencement vacant vacant sensitive not promote instability and result in o Involvement of s of construction government government land receptors destruction of property, vegetation, traffic dept. o Grievance land and free and free from irrigation, and drinking water o Road closure Register from any any conflict. supply systems. planning conflict. o Not to consider residential areas. o Take extreme care in selecting sites to avoid direct disposal to water body which will inconvenience the community. o For excess spoil disposal, ensure (a) site shall be selected preferably from barren, infertile lands. In case agricultural land needs to be selected, written consent from landowners (not lessees) will be obtained; (b) debris disposal site shall be at least 200 m away from surface water bodies; (c) no residential areas shall be located within 50 m downwind side of the site; and (d) site is minimum 250 m away from sensitive locations like settlements ponds/lakes or other water bodies Extraction of o Obtain construction materials only • List of approved o Checking Project sites Before DSISC All materials All materials materials can from government approved quarry sites and of records commencement Construction procured from procured from disrupt natural quarries with prior approval of PIU; sources of o Visual of construction Management licensed licensed vendors land contours o PIU to review, and ensure that materials Inspection and vendors after after approval of and vegetation proposed quarry sources have all • Construction of sites Environmental approval of PIU resulting in necessary clearances/ permissions Contractor Safeguard PIU accelerated in place prior to approval documentation Team erosion, o Contractor to submit to PIU on a disturbance in monthly basis documentation on natural material obtained from each drainage source (quarry/ borrow pit)

123 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) patterns, o Avoid creation of new borrow ponding and areas, quarries etc., for the project; water logging, if unavoidable, contractor to obtain and water all clearances and permissions as pollution. required under law, including Environmental Clearance prior to approval by PIU

Failure to o Obtain all necessary consents, List of applicable Checking of All project Before Environment CTE for WTP CTE for WTP obtain permits, clearance, NOCs, etc. legislation documents locations commencement Specialist of (Appendix II - (Appendix II- 6), necessary prior to award of civil works. of construction DSISC, PIU 6), land land possession consents, o Ensure that all necessary and PMU/PMC possession certificate permits, approvals for construction to be certificate (Appendix II - NOCs, etc. obtained by contractor are in place (Appendix II- 21) received. can result to before start of construction 21) received. Others design o Acknowledge in writing and Others necessary revisions provide report on compliance all necessary approval, NOC, and/or obtained consents, permits, approval, clearance & stoppage of clearance, NOCs, etc. NOC, permits has works o Include in detailed design clearance & been initiated for drawings and documents all permits has safely execution conditions and provisions if been initiated of work at site. necessary for safely execution of work at site. Health risk o Obtain details on location of Asbestos cement Site Specific Daily visit by DSISC Till date no Till date no due to underground asbestos cement materials inspection project Construction Construction asbestos asbestos cement exposure to materials location supervisor of Management cement material has asbestos o Lay the new pipes carefully to DSISC. Weekly and material has been found on materials avoid encountering asbestos visit by Environmental been found on site cement pipes Construction Safeguard site o If found, leave the asbestos Manager and Team cement pipes undisturbed in the Environment ground. Team of DSISC of operational sites. Construction Phase Irreversible o Project manager and all key Induction & Review of Project - Environment Only few Site Complied; site

124 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) impact to the workers will be required to undergo Awareness Training Locations Specialist of Environmenta Environmental environment training on EMP implementation Trainings Toolbox records DSISC and l Safety Safety workers, and including spoils/waste Talks Site PMU training and training and community management, Standard operating Safeguard Inspections awareness awareness procedures (SOP) for construction Trainings (including (including works; occupational health and COVID 19) COVID 19) safety (OHS), core labor laws, has been arranged on applicable environmental laws, etc. arranged for regular basis commenceme (sample nt of work. attached as (sample Appendix II - attached as 12) Appendix II - 12) Emissions For all construction works o Location of o Site Covering Air – noise DSISC Complied; Complied; pre- from o Comply with the Direction of West stockpiles inspectio different monitoring: Construction pre- construction construction Bengal Department of n locations of Once before Management construction baseline data vehicles, Environment under the Air Act, o Complaints WTP, Intake, start of and baseline data and during equipment, 1981 in controlling air pollution from sensitive o Public pumping construction Environmental has been construction and machinery from construction activities receptors grievanc stations as Yearly 3 times Safeguard collected. monitoring data used for o Comply with the air pollution / e per during Team, PIU Results has been installation of dust control measures for o Monitoring register monitoring construction (3- attached as collected results pipelines construction activities stipulated data- PM10, plan. year period After Appendix II - attached as resulting to by the “Direction of West Bengal PM2.5 NO2, considered) Lockdown 11. Appendix II - dusts and Department of Environment under SO2, CO limited Site Collection of 11. increase in the Air Act, 1981 Direction No. Visit has been PUC Concentration of concentration EN/3170/T-IV-7/001/2009 dated: o Heavy conducted certificate PM10 and 2.5 of vehicle- 10 December 2009” equipment since June under have increased related o Damp down the soil and any and 2020. process. in compared to pollutants stockpiled material on site by machinery baseline such as water sprinkling; with air Relevant condition both at carbon o Use tarpaulins to cover the loose pollution regulation WTP and intake monoxide, material (soil, sand, aggregate control under sites, may sulfur oxides, etc.,) when transported by trucks; compliance. attributed both particulate o Provide a dust screen around the o Water Other by construction matter, nitrous construction sites at GLSR and sprinkling activities like activities and oxides, and WTP work sites arrangement dust regular vehicular hydrocarbons. o Clean wheels and undercarriage suppression, movement of haul trucks prior to leaving o Cover covering of through nearby

125 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) construction site/quarry materials loose road. Emission o Control dust generation while materials, of equipment unloading the loose material dust screen and vehicle (particularly aggregate, soil) at will be tested. PUC the site by sprinkling water and arranged. certificate unloading inside the barricaded For pipe line obtained for area work, Vehicle o Stabilize surface soils where barricading, (Appendix II -2) loaders, support equipment and removal of Relevant vehicles will operate by using earth, regulation under water and maintain surface soils backfilling will compliance. in a stabilized condition be done as Other activities o Use tarpaulins to cover the loose per SEMP like dust material (soil, sand, aggregate suppression, etc.,) when transported by trucks; covering of loose o Apply water and maintain soils in materials, dust a visible damp or crusted screen have condition for temporary arranged. stabilization For pipe line o Apply water prior to leveling or work, any other earth moving activity to barricading, keep the soil moist throughout the removal of earth, process backfilling has o Cover the soil stocked at the sites done as per with tarpaulins SEMP. o Control access to work area, prevent unnecessary movement of vehicle, public trespassing into work areas; limiting soil disturbance will minimize dust generation o Ensure that all the construction equipment, machinery is fitted with pollution control devises, which are operating correctly, and have a valid pollution under control (PUC) certificate Pipeline works o Barricade the construction area

126 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) using hard barricades (of 2 m height) on both sides and provide dust/wind screen (such geo textile fabric) up to 3 m height (1m above the hard barricading) o Initiate site clearance and excavation work only after barricading of the site is done o Confine all the material, excavated soil, debris, equipment, machinery (excavators, cranes etc.,), to the barricaded area o Limit the stocking of excavated material at the site; remove the excess soil from the site immediately to the designated disposal area o Undertake the work section wise: 100 – 200 m section should be demarcated and barricaded o Conduct work sequentially - excavation, pipe laying, backfilling; conduct pipe testing section-wise (for a minimum length as possible) so that backfilling, stabilization of soil can be done. o Remove the excavated soil of first section to the disposal site; as the work progresses, sequentially, by the time second section is excavated, the first section will be ready for back filling, use the freshly excavated soil for back filling, this will avoid stocking of material, and minimize the dust. o Backfilled trench at any completed section after removal of

127 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) barricading will be the main source of dust pollution. The traffic, pedestrian movement and wind will generate dust from backfilled section. Road restoration shall be undertaken immediately. Mobilization o All earthworks be conducted • Areas for Site All project Daily visit by DSISC Work not yet Work started. of settled silt during the dry season to prevent stockpiles, storage inspection locations construction Construction started. Silt Earthen materials, the problem of soil run-off during of fuels and Public supervisor of Management trap will be embankment and chemical monsoon season; lubricants and grievance DSISC. Weekly and arranged if has provided contaminatio o Avoid stockpiling of earth fill waste materials register visit by Environmental required, instead of Silt n from fuels especially during the monsoon • Number of silt Construction Safeguard designated trap, designated and season unless covered by traps Manager, Visit Team site for waste site for waste lubricants tarpaulins or plastic sheets; installed along by Environment After disposal disposal during o Prioritize re-use of excess spoils drainages (in Safeguard Lockdown under selected and construction and materials in the construction slope) leading to Team. limited Site consideration. approved. All can works. If spoils will be disposed, water bodies Visit has been All safety safety aspects Contaminate only designated disposal areas • Entry routes of conducted aspect will be are maintained. nearby shall be used; pollutant in nearby since June maintained. surface water o Install temporary silt traps or waterbodies 2020. quality. sedimentation basins along the Ponding of drainage leading to the water in the waterbodies; pits o Place storage areas for fuels and /foundation lubricants away from any excavations drainage leading to water bodies; o Store fuel, construction chemicals etc., on an impervious floor, also avoid spillage by careful handling o Dispose any wastes generated by construction activities in designated sites; o Conduct surface quality inspection according to the Environmental Management Plan (EMP). o Create a temporary drainage channel around the work area to

128 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) arrest the entry of runoff from upper areas into the work area o Pump out the water collected in the pits / excavations to a temporary sedimentation pond; dispose of only clarified water into drainage channels/streams after sedimentation in the temporary ponds o Consider safety aspects related to pit collapse due to accumulation of water Increase in o Plan activities in consultation with Day time and o Checki Covering Noise DSISC Complied; Complied; pre- noise level PIU so that activities with the night time noise ng of different monitoring: Construction pre- construction due to earth- greatest potential to generate levels. records locations of Once before Management construction baseline and moving and noise are conducted during WTP, Intake, start of and baseline data during excavation periods of the day which will o Visual pumping construction Environmental has been construction data equipment, result in least disturbance; inspecti stations as Yearly 3 times Safeguard collected. has been and the o Horns should not be used unless on of per during Team There is no as collected. transportation it is necessary to warn other road sites monitoring construction (3- After such noise of equipment, users or animals of the vehicle’s plan. year period Lockdown generated There is no as materials, approach; considered) limited Site from such noise and people o Minimize noise from construction Visit has been equipment. generated from equipment by using vehicle conducted Stipulated equipment. silencers, fitting jackhammers since June condition as Stipulated with noise-reducing mufflers, and 2020. per SEMP will condition as per use portable street barriers to be followed SEMP is minimize sound impact to followed surrounding sensitive receptor; and o Maintain maximum sound levels not exceeding 80 decibels (dBA) when measured at a distance of 10 m or more from the vehicle/s. o Identify any buildings at risk from vibration damage and avoiding any use of pneumatic drills or heavy vehicles in the vicinity o Horns should not be used unless it

129 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) is necessary to warn other road users or animals of the vehicle’s approach; o Consult local communities in advance of the work to identify and address key issues, and avoid working at sensitive times, such as religious and cultural festivals. Impacts due o Prepare and implement a • Waste • Checking Project Daily visit by Environment Excess earth Complied to excess Construction Waste Management Management of records locations construction Specialist of will be used Excess earth is excavated Plan List • Visual supervisor of DSISC, PIU mostly for being used for earth, excess o As far as possible utilize the • Stockpile inspection DSISC. Weekly and PMU/PMC backfilling backfilling construction debris and excess soil in Management of sites visit by Domestic Domestic solid materials, construction purpose, for example • Complaints from Construction solid waste waste collection and solid for raising the ground level or Sensitive Manager, Visit collection bin bin arranged. waste such construction of access roads etc., receptors by Environment will be Burning of waste as removed o Stockpiles, lubricants, fuels, and • PMU/ PIU/ Safeguard arranged has been strictly concrete, other materials should be located DSISC to report Team. Burning of prohibited in site. wood, away from steep slopes and inwriting that the waste has packaging water bodies; necessary been strictly materials, o Avoid stockpiling any excess environmental prohibited in empty spoils at the site for long time. restoration work site. containers, Excess excavated soils should be has been done spoils, oils, disposed off to approved lubricants, designated areas immediately; and other o If disposal is required, the site similar items. shall be selected preferably from barren, infertile lands; site should be located away from residential areas, forests, water bodies and any other sensitive land uses o Domestic solid wastes should be properly segregated in biodegradable and non- biodegradable for collection and disposal to designated solid waste disposal site; create a compost pit at workers’ camp sites for disposal of biodegradable waste; non-

130 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) biodegradable / recyclable material shall be collected separately and sold in the local recycling material market o Residual and hazardous wastes such as oils, fuels, and lubricants shall be disposed of in disposal sites approved by local authorities/WBPCB; o Prohibit burning of construction and/or domestic waste; o Ensure that wastes are not haphazardly dumped thrown within and around the project site and adjacent areas; provide proper collection bins, and create awareness to use the dust bins. o Conduct site clearance and restoration to original condition after the completion of construction work; PIU to ensure that site is properly restored prior to issuing of construction completion certificate Disruption of o Prepare a list of affected utilities • List of affected Observation Project Daily visit by Environment Will be done Complied as Per service and and operators if any; utilities if any and and locations construction Specialist of as per requirement. Damage to o Prepare a contingency plan to operators document supervisor of DSISC, PIU requirement. At present, there existing include actions to be done in case • Public grievance checking DSISC. Weekly and PMU/PMC At present, is no any infrastructure of unintentional interruption of visit by there is no disruption of at specified service Construction any disruption service and project Manager, Visit of service and damage the location by Environment damage the existing Safeguard existing infrastructure. Team. infrastructure Loss of o Minimize removal of vegetation Tree felling • Checking of Project Daily visit by Environment As of now, Measures taken vegetation and disallow cutting of trees; requirement records locations construction Specialist of tree felling for minimize and tree o If tree-removal will be required, and afforestation • Visual supervisor of DSISC, PIU requirement is number of tree cover obtain tree-cutting permit and after final design inspection of DSISC. Weekly and PMU/PMC not felling.

131 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) o Plant 5 native trees for every one sites visit by envisaged. Tree felling that is removed. Construction anticipated in Manager, Visit WTP site only. by Environment Necessary Safeguard permission Team. obtained from Forest Department (Appendix II - 5) Tree felling will be done shortly Traffic Hauling (material, waste/debris and • Traffic Site visit and Project Daily visit by Environment No work Haul road problems and equipment) activities Management Plan document locations construction Specialist of started. prepared for conflicts near o Plan transportation routes so that • Public grievance review supervisor of DSISC and transportation of project heavy vehicles do not use narrow • Number of DSISC. Weekly PIU material to WTP locations and local roads, except in the signages placed visit by site. For intake haul road immediate vicinity of delivery sites at subproject Construction point, there is o Schedule transport and hauling location Manager, Visit only one road activities during non-peak hours; by Environment which is used for o Locate entry and exit points in Safeguard transportation of areas where there is low potential Team. material and for for traffic congestion; communication o Drive vehicles in a considerate of villagers and manner traffic. Adequate o Notify affected public by public signage, safety information notices, providing sign steward is boards informing nature and implemented duration of construction works and during contact numbers for concerns / construction. complaints. Local villagers Pipeline works are informed in o Confine work areas along the advance to avoid roads to the minimum possible the extent; all the activities, including inconvenience. material and waste/surplus soil Traffic plan has stocking should be confined to this been submitted area. Proper barricading should be for pipe laying provided; avoid work. o material/surplus soil stocking in Local people are

132 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) congested areas – immediately informed in removed from site/ or brought to advance in every the as and when required. case. o Leave spaces for access between Construction mounds of soil to maintain access work is limited by to the houses / properties considering the o Provide pedestrian access in all convenience of the locations; provide local people. wooden/metal planks over the open trenches at each house to maintain the access. o Inform the affected local population 1-week in advance about the work schedule o Plan and execute the work in such a way that the period of disturbance/ loss of access is minimum. o Keep the site free from all unnecessary obstructions; o Coordinate with Traffic Police for temporary road diversions, where necessary, and for provision of traffic aids if transportation activities cannot be avoided during peak hours Generation o Employ local labor force as far as Employment Checking of Project Daily visit by Environment Direct and Maximum of temporary possible record records locations construction Specialist of indirect number of local employment o Comply with labor laws supervisor of DSISC, PIU employment people are and DSISC. Weekly and PMU / for local engaged in site. increase in visit by PMC population will local Construction be ensured. revenue Manager, Visit by Environment Safeguard Team. Occupational Comply with all national, state and o Site-specific • Checking of Project Daily visit by Environment Work not Complied. hazards local core labor laws (see Health and records locations construction Specialist of started. Site-specific

133 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) which can Appendix 7of this IEE) Safety (H&S) • Visual supervisor of DSISC; PIU Site-specific Health and arise during o Develop and implement site- Plan inspection of DSISC. Weekly and PMU/PMC Health and Safety (H&S) work specific occupational health and o Equipped sites visit by Safety (H&S) Plan under safety (OHS) Plan which will first-aid Construction After submitted and implementation. include measures such as: (a) stations; Manager, Visit Lockdown approved by OHS plan excluding public from the site; (b) o Medical by Environment limited Site DSISC and submitted by ensuring all workers are provided insurance Safeguard Visit has been PIU. contractor and with and use personal protective coverage for Team. conducted OHS plan approved by equipment like helmet, gumboot, workers since June submitted by DSISC and PIU. safety belt, gloves, nose musk and o Number of 2020. contractor That document ear plugs; (c) OHS Training for all accidents and approved is available with site personnel; (d) documented o Supplies of by DSISC and DSISC and PIU. procedures to be followed for all potable PIU. That site activities; and (e) drinking document is Supplementary documentation of work-related water; available with COVID 19 H & S accidents; o Record of DSISC and plan prepared o Ensure that qualified first-aid can H&S PIU. and compliance be provided at all times. Equipped orientation continued first-aid stations shall be easily trainings Supplementar (Appendix II - accessible throughout the site; o Personal y COVID 19 H 10) o Provide medical insurance protective & S plan coverage for workers; equipment prepared and Induction and o Secure all installations from o Sign boards compliance tool box training unauthorized intrusion and for continued (including accident risks; hazardous (Appendix II - COVID 19 o Provide supplies of potable areas 10) awareness drinking water; such as training) o Provide clean eating areas where energized Induction and arranged by workers are not exposed to electrical tool box contractor hazardous or noxious substances; devices training (sample shown o Provide health and safety and lines, (including in Appendix II - orientation training to all new service COVID 19 12) workers to ensure that they are rooms awareness Use of PPEs apprised of the basic site rules of training) will noted mostly. work at the site, personal be arranged Visibility vest protective protection, and by contractor. also used. preventing injuring to fellow Drinking water, workers; Use of PPEs first aid box, o Provide visitor orientation if visitors will be hand sanitizer,

134 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) to the site can gain access to ensured at face masks etc. areas where hazardous conditions site. are available at or substances may be present. Drinking site. Ensure also that visitor/s do not water, first aid enter hazard areas unescorted; box will be Medical o Ensure the visibility of workers available at Insurance through their use of high visibility site. arranged for the vests when working in or walking WC Policy laborers (see through heavy equipment renewal done Appendix II - 4). operating areas; (validity upto o Ensure moving equipment is 22.06.2021, Medical tie up outfitted with audible back-up Appendix II - and health alarms; 4). checking of o Mark and provide sign boards for Medical tie up workers done hazardous areas such as done with (Appendix II - energized electrical devices and local hospital. 4) lines, service rooms housing high No as such voltage equipment, and areas for noise No as such storage and disposal. Signage producing noise producing shall be in accordance with equipment equipment international standards and be well available at available at site. known to, and easily understood site. Accident register by workers, visitors, and the Accident is maintained at general public as appropriate; and register will site. Till date no o Disallow worker exposure to noise be maintained major accident level greater than 85 dBA for a at site. First aid case duration of more than 8 hours per was recorded. day without hearing protection. (sample The use of hearing protection shall Appendix II - be enforced actively. 13) Health risk o Obtain details on location of asbestos cement Site Specific Daily visit by DSISC Till date no Till date no due to underground asbestos cement materials inspection project construction Construction asbestos asbestos cement exposure to materials location supervisor of Management cement material has asbestos o Lay the new pipes carefully to DSISC. and material has been found on materials avoid encountering asbestos Weekly Environmental been found site cement pipes visit by Safeguard on site o If found, leave the asbestos Construction Team cement pipes undisturbed in the Manager and ground. Environment

135 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) Team of DSISC of operational sites. Traffic o Restrict construction vehicle Public grievance Review of Project Daily visit by Environment No work Haul road accidents and movements to defined access documents Locations construction Specialist of started. prepared for vehicle roads and demarcated working supervisor of DSISC and transportation of collision with areas (unless in the event of an DSISC. Weekly PIU material to WTP pedestrians emergency) visit by site. For intake during material o Enforce strict speed limit (20-30 Construction point, there is and waste kmph) for playing on unpaved Manager, Visit only one road transportation roads, construction tracks by Environment which is used for o Night-time haulage will be by Safeguard transportation of exception only, as approved by the Team. material and for PIU to minimize driving risk and communication disturbance to communities of villagers and o Adopt standard and safe practices traffic. Adequate for micro tunneling signage, safety o Temporary traffic control (e.g. steward is flagmen) and signs will be implemented provided where necessary to during improve safety and provide construction. directions Local villagers o All drivers will undergo safety and are informed in training advance to avoid o Public access to all areas where the construction works are on-going inconvenience. will be restricted through the use of Traffic plan has barricading and security personnel been submitted o Warning signs, blinkers will be for pipe laying attached to the barricading to work. caution the public about the Local people are hazards associated with the works, informed in and presence of deep excavation advance in every o The period of time when the case. pipeline trench are left open will be Construction minimized through careful planning work is limited by o Control dust pollution – implement considering the dust control measures as convenience of suggested under air quality section local people.

136 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) o Maintain regularly the vehicles and use of manufacturer-approved parts to minimize potentially serious accidents caused by equipment malfunction or premature failure. o Provide road signs and flag persons to warn of on-going trenching activities. Temporary air o Ensure that a proper compound • Public grievance Site Construction Daily visit by Environment Site office, Complied. and noise wall is provided, and erect a • Accommodation inspection camps construction Specialist of labour camp Housekeeping, pollution from wind/dust screen around • Water and and review of supervisor of DSISC and at intake and toilet facility, machine o Camp site shall not be located sanitation facilities documents DSISC. Weekly PIU WTP sites are testing of operation, near (100 m) water bodies, flood for employees visit by After under drinking water, water pollution plains flood prone/low lying areas, • Housekeeping – Construction Lockdown construction. provision of fuel from storage or any ecologically, socially, regular disposal of Manager, Visit limited Site (kerosene or and use of archeologically sensitive areas solid waste by Environment Visit has been LPG) for fuels, oils, o Separate the workers living areas Safeguard conducted cooking, solvents, and and material storage areas clearly Team. since June provision of solid lubricants with a fencing and separate entry 2020. waste and Unsanitary and exit wastewater and poor living o Provide proper temporary disposal are conditions for accommodation with proper properly workers materials, adequate lighting and maintained. ventilation, appropriate facilities for Safe distance is winters and summers; ensure maintained at conditions of livability at work camp for camps are maintained at the protection highest standards possible at all against COVID- times; 19. infection o Consult PIU before locating project offices, sheds, and construction plants; (viii)Minimize removal of vegetation and disallow cutting of trees o Ensure conditions of livability at work camps are maintained at the highest standards possible at all times; living quarters and

137 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) construction camps shall be provided with standard materials (as far as possible to use portable ready to fit-in reusable cabins with proper ventilation); thatched huts, and facilities constructed with materials like GI sheets, tarpaulins, etc., shall not be allowed as accommodation for workers o Camp shall be provided with proper drainage, there shall not be any water accumulation o Provide drinking water, water for other uses, and sanitation facilities for employees o Prohibit employees from cutting of trees for firewood; contractor should be provided proper facilities including cooking fuel (oil or gas; fire wood not allowed) o Train employees in the storage and handling of materials which can potentially cause soil contamination o Recover used oil and lubricants and reuse or remove from the site o Manage solid waste according to the following preference hierarchy: reuse, recycling and disposal to designated areas; provide a compost pit for biodegradable waste, and non-biodegradable / recyclable waste shall be collected and sold in local market o Remove all wreckage, rubbish, or temporary structures which are no longer required o At the completion of work, camp area shall be cleaned and restored

138 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) to pre-project conditions, and submit report to PIU; PIU to review and approve camp clearance and closure of work site There are no o Consult Archaeological Survey of Site inspection Site Project Daily visit by Environment No chance No chance finds protected India (ASI) or West Bengal State records inspection Locations construction Specialist of finds to date. to date. properties in Archaeology Department to obtain and review of supervisor of DSISC and the subproject an expert assessment of the documents DSISC. Weekly PMU/PMC sites. archaeological potential of the site. visit by However, in o Include state and local Construction case of archaeological, cultural and Manager, Visit chance finds, historical authorities, and interest by Environment contractors will groups in consultation forums as Safeguard be required to project stakeholders so that their Team. follow a expertise can be made available. protocol as o In case of chance finds, works must defined in the be stopped immediately until such mitigation time chance finds are cleared by measures. experts Unsatisfactory o Appointment of (I) Environment, Appointment letter Review of - - Environment Partially Overall compliance to Health and Safety (EHS) Monitoring records records Specialist of complied. complied. Safety EMP Supervisor to ensure EMP DSISC and Monthly person implementation PIU reporting not appointed from o Timely submission of monitoring started as contractor end. reports including pictures actual EHS training physical work conducted on yet to start. regular basis. Monitoring report submitted on monthly basis. Damage due o Remove all spoils wreckage, Stockpile Review of Project Daily visit by Environment Complied; Complied; Spoil to debris, rubbish, or temporary structures Management documents Locations construction Specialist of Spoil Management spoils, excess (such as buildings, shelters, and Spoil and site supervisor of DSISC and Management Plan has been construction latrines) which are no longer Management inspections DSISC. Weekly PIU Plan has submitted as materials required; and Restoration of visit by been part of SEMP o All excavated roads shall be sites Construction submitted. No reinstated to original condition. Manager, Visit pipe laying o All disrupted utilities restored by Environment work started.

139 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance from IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ minimum those Conducted Conducted Explanation Explanation for identified in the the for BK 01 BK03 IEE should be Monitoring monitored) o All affected structures Safeguard rehabilitated/compensated Team. o The area that previously housed the construction camp is to be checked for spills of substances such as oil, paint, etc. and these shall be cleaned up. o All hardened surfaces within the construction camp area shall be ripped, all imported materials removed, and the area shall be top soiled and re-grassed using the guidelines set out in the revegetation specification that forms part of this document. o The contractor must arrange the cancellation of all temporary services. quest PIU to report in writing that worksites and camps have been vacated and restored to pre-project conditions before acceptance of work.

140 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Table 12: Summary of Environmental Monitoring Activities for the Package WBDWSIP/DWW/NCB/ BK/02A/2018-19, WBDWSIP/DWW/NCB/BK/02B/2018-19, and WBDWSIP/DWW/NCB/BK/04/2018-19- Water Supply Distribution Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) Design Phase Source (i) Gravity distribution • Design Document All project Before Environment Complied; Complied; Complied; sustainability system: designing the philosophy review and locations commencem Specialist of Transmission Transmission Distribution and efficiency entire system to maintain • Project QA/QC LOP Survey ent DSISC; PIU main network and network optimal flow and terminal plan of final and design Distribution design pressure, and optimizing • Selection design PMC completed for network design finalized for the overall energy usage methodology all zones and completed for 29 zones out (ii)Implementation of a for distribution Distribution all zones. of 34 and water quality surveillance network network design validated with program including finalized for 18 consumer development of a zones out of 20. survey data. laboratory as part of the project to ensure that supplied water meets the drinking water standards (iii)Minimizing water losses from pipelines by perfect jointing and alignments using appropriate techniques (iv) Reducing the incidence of water borne diseases by providing 100% population including urban poor with potable water supplies Socio (i) Avoid using low-lying List of selected Site survey All OHR Before Environment Complied; Complied; Complied; economic lands / ponds for location for OHRs sites commencem Specialist of No low-lying No low-lying No low-lying impact – loss construction of OHRs; ent DSISC and lands or ponds lands or ponds lands or fishery area alternative private lands of final PMC are being filled are being filled ponds are may be explored within design for construction. for being filled for the vicinity; construction. construction. (ii)Review the applicability of West Bengal Inland Fisheries Act, 1984, whether the

141 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) site falls under the definition of fisher area; obtained permission from Fisheries Department if required prior to start of construction Tree cutting (i) Minimize removal of • Tree felling Site survey All project Before Environment Complied; no Complied; no Complied; no trees by adopting to site requirement – and review locations commencem Specialist of tree felling has tree felling has tree felling condition and with site of site ent DSISC; PIU been envisaged been has been appropriate layout design layout plan layout/ of final and till date. envisaged till envisaged till of OHRs within the sites • NOC – paper pipeline design PMC date. date. (ii) Avoid cutting of trees documents alignment by adopting suitable from line plan alignment changes as agency required during laying of pipelines; (iii)I In unavoidable cases, obtain prior permission for tree cutting (iv) Plant and maintain 5 trees for each tree that is removed Pre-Construction Phase Telephone (i) Identify and include List of affected Observation Specific Before Environment Complied; about Complied; Complied; lines, electric locations and operators utilities if any and and project commencem Specialist of 42.574 km of about 38.408 about 302.556 poles and of these utilities in the operators document location ent of DSISC and transmission km of km of wires, water detailed design checking construction PIU main and transmission distribution lines within documents to prevent 267.768 km main and main pipeline proposed unnecessary disruption distribution 348.613 km of has been laid project area of services during network pipeline distribution (Spoil construction phase; has been laid main pipeline Management (ii) Require construction (Spoil has been laid Plan & Traffic contractors to prepare a Management (Spoil Management contingency plan to Plan & Traffic Management Plan attached include actions to be Management Plan & Traffic with SEMP) taken in case of Plan submitted Management unintentional interruption along with Plan submitted

142 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) of services. SEMP) with SEMP) (iii) Require contractors to prepare spoils (waste) management plan and traffic management plan Conflicts with (i) Prioritize areas within • List of selected • Site Specific Before Environment Complied, Complied, Complied, local or nearest possible location for observat project commencem Specialist of No disruption No disruption No disruption community; vacant space in the OHRs ion location ent DSISC; PIU noted. noted. noted. disruption to project location; • Involvement of • Review of final and PMC Area selected Area selected Area selected traffic flow and (ii) If it is deemed traffic dept. of design and nearby vacant nearby vacant nearby vacant sensitive necessary to locate • Road closure docume commencem place. place. place. receptors elsewhere, consider sites planning nts ent of No excess spoil No excess No excess that will not promote • Grievan construction generated. spoil spoil instability and result in ce Excess earth generated. generated. destruction of property, Register utilized for back Excess earth Excess earth vegetation, irrigation, and filling. utilized for utilized for drinking water supply No complete back filling. back filling. systems; road closure No complete No complete (iii) Do not consider expected. road closure road closure residential areas; Partial closure expected. expected. (iv) Take extreme care in noted, which Partial closure Partial closure selecting sites to avoid mentioned in noted, which noted, which direct disposal to water traffic mentioned in mentioned in body which will management traffic traffic inconvenience the plan management management community. plan plan (v) For excess spoil disposal, ensure (a) site shall be selected preferably from barren, infertile lands. In case agricultural land needs to be selected, written consent from landowners (not lessees) will be obtained; (b) debris disposal site shall be at least 200 m away from surface water bodies; (c)

143 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) no residential areas shall be located within 50 m downwind side of the site; and (d) site is minimum 250 m away from sensitive locations like settlements, ponds/lakes or other water bodies. Extraction of (i) Obtain construction • List of • Checkin Quarries Daily visit by DSISC Complied. Complied. Complied. materials can materials only from approved g of and construction Construction Approval Approval Approval disrupt natural government approved quarry sites records material supervisor of Management obtained from obtained from obtained from land contours quarries with prior and sources of • Visual source DSISC. and DSISC, PIU DSISC, PIU DSISC, PIU and vegetation approval of PIU; materials inspecti areas Weekly Environmenta before before before resulting in (ii) PIU to review, and • Construction on of visit by l Safeguard procurement. procurement. procurement. accelerated ensure that proposed Contractor sites Construction Team erosion, quarry sources have all documentation Manager disturbance in necessary clearances/ and natural permissions in place Environment drainage prior to approval Team of patterns, (iii) Contractor to submit DSISC at ponding and to PIU on a monthly operational water logging, basis documentation on sites. and water material obtained from pollution. each source (quarry/ borrow pit) (iv) Avoid creation of new borrow areas, quarries etc., for the project; if unavoidable, contractor to obtain all clearances and permissions as required under law, including Environmental Clearance prior to approval by PIU Failure to (i) Obtain all necessary List of applicable Checking All project Before Environment Complied and to Complied and Complied and obtain consents, permits, legislation of locations commencem Specialist of be continued as to be to be

144 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) necessary clearance, NOCs, etc. documents ent of DSISC and per requirement continued as continued as consents, prior to award of civil construction PMC per per permits, works. requirement requirement NOCs, etc. (ii) Ensure that all can result to necessary approvals for design construction to be revisions obtained by contractor and/or are in place before start stoppage of of construction works (iii) Acknowledge in writing and provide report on compliance all obtained consents, permits, clearance, NOCs, etc. (iv) Include in detailed design drawings and documents all conditions and provisions if necessary Health risk due (i) Obtain details on Asbestos cement Site Specific Daily visit by DSISC Complied. Till Complied. Till Complied. Till to exposure to location of asbestos materials inspection project construction Construction date no rubbish date no date no asbestos cement materials location supervisor of Management containing rubbish rubbish materials (ii) Lay the new piper DSISC. and asbestos containing containing carefully to avoid Weekly Environmenta cement has asbestos asbestos encountering AC pipes visit by l Safeguard been found cement has cement has (ii) Leave the AC pipes Construction Team been found been found undisturbed in the Manager ground. and Environment Team of DSISC at operational sites. Construction phase Irreversible (i) Project manager and Induction & Review of Project - Environment Under Under Under impact to the all key workers will be Awareness Training Locations Specialist of compliance; compliance; compliance; environment, required to undergo Trainings records DSISC: PIU Site Site Site

145 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) workers, and training on EMP Toolbox Talks Site and Environmental Environmental Environmental community implementation including Safeguard Trainings Inspections PMC Safety training Safety training Safety training spoils/waste and awareness and and management, Standard including awareness awareness operating procedures COVID 19 arranged by arranged by (SOP) for construction arranged by contractor on contractor on works; occupational contractor on regular basis regular basis health and safety (OHS), regular basis (Sample (Sample core labor laws, (Sample attached as attached as applicable environmental attached as Appendix II - Appendix II – laws, etc. Appendix II- 12) 12) 12) Safeguard Safeguard Safeguard orientation/ orientation/ orientation / Audit program Audit program Audit program arranged by arranged by arranged by DSISC and DSISC and DSISC and PMC PMC PMC (Appendix II - (Appendix II - (Appendix II- 19) 19) 19)

Emissions For all construction • Location of Site Project Daily visit by Environment Under Under Under from works stockpiles inspection locations construction Specialist of compliance; compliance; compliance; construction (i) Comply with the air • Complaints Public Air- supervisor of DSISC; PIU About 42.574 About 38.408 About vehicles, pollution / dust control from grievance monitoring DSISC. and km of km of 302.556 km equipment, measures for sensitive register as per Weekly PMC transmission transmission pipe line laid. and machinery construction activities receptors selected visit by main and main and Water used for stipulated by the • Monitoring sites in ref. Construction After 267.768 km 348.613 km of sprinkling installation of “Direction of West data- PM!0, to SEMP Manager, Lockdown distribution distribution done as per pipelines Bengal Department of PM2.5, SO2, Visit by limited Site network pipe main pipe line requirement. resulting to Environment under the NO2, CO Environment Visit has been line laid. laid. During dusts and Air Act, 1981 Direction • Heavy Specialist conducted Water sprinkling Water construction increase in No. EN/3170/T-IV-7 equipment and Support since June arrangement sprinkling done air quality concentration /001/2009 dated: 10 and machinery Environment 2020. available as per as per monitoring of vehicle- December 2009” with staff requirement. requirement. done as per related (ii) Damp down the soil air pollution Air- During During IEE pollutants such and any stockpiled control monitoring construction air construction (Complete as carbon material on site by water • Water schedule as quality air quality result monoxide, sprinkling; per SEMP monitoring done monitoring certificates

146 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) sulfur oxides, (iii)Use tarpaulins to sprinkling as per IEE done as per available in particulate cover the loose material Arrangement Monitoring (Complete IEE (Complete DSISC office matter, nitrous (soil, sand, aggregate Cover materials carried out result result as back up oxides, and etc.,) when transported between certificates certificates paper and hydrocarbons. by trucks; 09.10.2020 – available in available in attached as (iv) Provide a dust 23.10.2020 DSISC office as DSISC office Appendix II - screen/high compound back up paper as back up 11) wall around the and attached as paper and Most of the construction sites Appendix II - attached as PUC (OHRs) 11) Appendix II - certificate (v) Clean wheels and PUC certificate 11) obtained for undercarriage of haul obtained for Most of the Vehicle and trucks prior to leaving Vehicle and PUC certificate Equipment construction site/quarry Equipment obtained for (Appendix II - (vi) Control dust (Appendix II - Vehicle and 2) generation while 2) Equipment Other unloading the loose Other activities (Appendix II - activities like material (particularly like dust 2) dust aggregate, soil) at the suppression, Other activities suppression, site by sprinkling water covering of like dust covering of and unloading inside the loose materials, suppression, loose barricaded area dust screen covering of materials, (vii) Stabilize surface arranged. loose dust screen soils where loaders, For pipe line materials, dust arranged. support equipment and work, screen For pipe line vehicles will operate by barricading, arranged. work, using water and maintain removal of For pipe line barricading, surface soils in a earth, backfilling work, removal of stabilized condition done as per barricading, earth, (viii) Apply water prior to SEMP. removal of backfilling leveling or any other earth, done as per earth moving activity to backfilling SEMP keep the soil moist done as per throughout the process SEMP. (ix) Control access to work area, prevent unnecessary movement of vehicle, public trespassing into work

147 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) areas; limiting soil disturbance will minimize dust generation (x) Ensure that all the construction equipment and machineries are fitted with pollution control devises, which are operating correctly, and have a valid pollution under control (PUC) certificate Pipeline works (i) Barricade the construction area (ii) Initiate site clearance and excavation work only after barricading of the site is done (iii)Confine all the material, excavated soil, debris, equipment, machinery (excavators, cranes etc.,), to the barricaded area (iv) Limit the stocking of excavated material at the site; remove the excess soil from the site immediately to the designated disposal area (v) Undertake the work section wise (vi)Conduct work sequentially - excavation, pipe laying, backfilling; conduct pipe testing section-wise (for a minimum length as

148 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) possible) so that backfilling, stabilization of soil can be done. (vii) Remove the excavated soil of first section to the disposal site; as the work progresses, sequentially, by the time second section is excavated, the first section will be ready for back filling, use the freshly excavated soil for back filling, this will avoid stocking of material, and minimize the dust. (viii) Backfilled trench at any completed section after removal of barricading will be the main source of dust pollution. The traffic, pedestrian movement and wind will generate dust from backfilled section. Road restoration shall be undertaken immediately. Mobilization of (i) All earthworks be • Areas for Site All project Daily visit by Environment Complied Complied Complied settled silt conducted during the dry stockpiles, inspection locations construction Specialist of Earth work Earth work Earth work materials, and season to prevent the storage and supervisor of DSISC: PIU conducted conducted conducted chemical problem of soil run-off of fuels and Public DSISC. and during dry during dry during dry contamination during monsoon season; lubricants and grievance Weekly PMC season. season. season. from fuels and (ii) Avoid stockpiling of waste materials register visit by No as such No as such No as such lubricants earth fill especially during • Number of silt Construction After requirement of requirement of requirement during the monsoon season traps Manager, Lockdown disposal of disposal of of disposal of construction unless covered by installed along Visit by limited Site spoil. Excess spoil. Excess spoil. Excess can tarpaulins or plastic drainages (in Environment Visit has been earth utilized for earth utilized earth utilized contaminate sheets; Specialist conducted backfilling. for backfilling. for backfilling.

149 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) nearby surface (iii)Prioritize re-use of slope) leading and Support since June Material never Material never Material never water quality. excess spoils and to Environment 2020. disposed in the disposed in disposed in Ponding of materials in the water bodies staff pond located the pond the pond water in the construction works. If • Entry routes of within this site. located within located within pits / spoils will be disposed, pollutant in Silt traps / this site. Silt this site. Silt foundation only designated disposal nearby Water sediment basin traps / traps / excavations areas shall be used; bodies should be sediment sediment (iv) Install temporary silt installed prior to basin should basin should traps or sedimentation discharge of be installed be installed basins along the construction prior to prior to drainage leading to the wastewater discharge of discharge of water bodies; from site. construction construction (v) Place storage areas Fuel storage not wastewater wastewater for fuels and lubricants started. from site. from site. away from any drainage Surface water Fuel storage Fuel storage leading to water bodies; quality not started. not started. (vi) Store fuel, monitoring done Surface water Surface water construction chemicals All safety aspect quality quality etc., on an impervious maintained monitoring monitoring floor, also avoid spillage done done by careful handling All safety All safety (vii) Dispose any wastes aspect aspect generated by maintained maintained construction activities in designated sites; and (viii) Conduct surface quality inspection according to the Environmental Management Plan (EMP). (ix) Create a temporary drainage channel around the work area to arrest the entry of runoff from upper areas into the work area (x) Pump out the water collected in the pits /

150 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) excavations to a temporary sedimentation pond; dispose of only clarified water into drainage channels/streams after sedimentation in the temporary ponds (xi) Consider safety aspects related to pit collapse due to accumulation of water Increase in (i) Plan activities in • Complaints o Checkin All project Daily visit by Environment Complied. Complied. Complied. noise level due consultation with PIU so from g of locations construction Specialist of No such noise No such noise No such noise to earth- that activities with the sensitive records Noise- supervisor of DSISC; PIU generating generating generating moving and greatest potential to receptors o Visual monitoring DSISC. and problem near problem near problem near excavation generate noise are • Use of inspecti as per Weekly PMC the project the project the project equipment, conducted during periods silencers in on of selected visit by location. location. location. and the of the day which will noise- sites sites in ref. Construction After Pre-construction Pre- However, transportation result in least producing to SEMP Manager, Lockdown monitoring construction daytime noise of equipment, disturbance; equipment and Visit by limited Site done. and during level increase materials, and (ii) Horns should not be sound barriers Environment Visit has been During construction at few people used unless it is Monitoring data Specialist conducted construction monitoring locations in necessary to warn other and Support since June monitoring be done. compared to road users or animals of Environment 2020. continued as Monitoring be baseline the vehicle’s approach; staff per IEE. continued as condition, (iii) Minimize noise from Complete result per IEE. which may be construction equipment Noise certificates Complete attributed due by using vehicle monitoring available in result to silencers, fitting schedule as DSISC office as certificates construction jackhammers with noise- per SEMP. back up paper available in activities. reducing mufflers, and and attached as DSISC office Pre- use portable street Monitoring Appendix II - as back up construction barriers to minimize carried out 11. paper and and during sound impact to between Honking attached as construction surrounding sensitive 09.10.2020 – generally Appendix II- monitoring receptor; and 23.10.2020 avoided at work 11. done. (iv) Identify any buildings sites. Honking Monitoring be at risk from vibration generally continued as

151 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) damage and avoiding avoided at per IEE. any use of pneumatic work sites. Complete drills or heavy vehicles in result the vicinity certificates (v) Horns should not be available in used unless it is DSISC office necessary to warn other as back up road users or animals of paper and the vehicle’s approach; attached as (vi) Consult local Appendix II - communities in advance 11. of the work to identify Honking and address key issues, generally and avoid working at avoided at sensitive times, such as work sites. religious and cultural festivals. Impacts due to (i) Prepare and • Waste o Checkin Project Daily visit by Environment Complied Complied Complied excess implement a Management g of locations construction Specialist of Excess earth Excess earth Excess earth excavated Construction Waste List records supervisor of DSISC: PIU used mostly for used mostly used mostly earth, excess Management Plan • Stockpile o Visual DSISC. and backfilling. for backfilling. for backfilling. construction (ii) As far as possible Management inspecti Weekly PMC Excess spoils Excess spoils Excess spoils materials, and utilize the debris and • Complaints on of visit by are not are not are not solid waste excess soil in from sites Construction After generally generally generally such as construction purpose, for Sensitive Manager, Lockdown stockpiled. stockpiled. stockpiled. removed example for raising the receptors Visit by limited Site No hazardous No hazardous No hazardous concrete, ground level or • PMU/PIU/ Environment Visit has been waste and waste and waste and wood, construction of access DSISC to Specialist conducted construction construction construction packaging roads etc., report in writing and Support since June waste waste waste materials, (iii) Stockpiles, lubricants, that the Environment 2020. generated. generated. generated. empty fuels, and other materials necessary staff containers, should be located away environmental spoils, oils, from steep slopes and restoration lubricants, and water bodies; work has been other similar (iv)Avoid stockpiling any done items. excess spoils at the site for long time. Excess excavated soils should be disposed of to

152 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) approved designated areas immediately; (v) If disposal is required, the site shall be selected preferably from barren, infertile lands; site should be located away from residential areas, forests, water bodies and any other sensitive land uses (vi) Domestic solid wastes should be properly segregated in biodegradable and non- biodegradable for collection and disposal to designated solid waste disposal site; create a compost pit at workers’ camp sites for disposal of biodegradable waste; non-biodegradable / recyclable material shall be collected separately and sold in the local recycling material market (vii) Residual and hazardous wastes such as oils, fuels, and lubricants shall be disposed of in disposal sites approved by local authorities/West Bengal Pollution Control Board (WBPCB); (viii) Prohibit burning of construction and/or domestic waste; (ix) Ensure that wastes

153 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) are not haphazardly dumped thrown within and around the project site and adjacent areas; provide proper collection bins, and create awareness to use the dust bins. (x) Conduct site clearance and restoration to original condition after the completion of construction work; PIU to ensure that site is properly restored prior to issuing of construction completion certificate Disruption of (i) Prepare a list of • List of affected Observation Project Daily visit by Environment Complied as Complied as Complied as service and affected utilities and utilities if any And locations construction Specialist of Per Per Per damage to operators if any; and operator’s document supervisor of DSISC and requirement. requirement. requirement. existing (ii) Prepare a Public checking DSISC. PIU Consultation Consultation Consultation infrastructure contingency plan to grievance Weekly done with utility done with done with at specified include actions to be visit by dept. as and utility dept. as utility dept. as project location done in case of Construction when required and when and when unintentional interruption Manager, required required of service Visit by Environment Specialist and Support Environment staff Loss of (i) Minimize removal of Tree felling o Checkin Project Daily visit by Environment As of now, no As of now, no As of now, no vegetation and vegetation and disallow requirement g of locations construction Specialist of tree felling is tree felling is tree felling is tree cover cutting of trees, by and afforestation records supervisor of DSISC and anticipated at anticipated at anticipated at adopting best site layout after final design o Visual DSISC. PMC work sites work sites work sites and pipeline alignments inspecti Weekly (ii) If tree-removal will be on of visit by required, obtain tree- sites Construction

154 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) cutting permit and Manager, (iii) Plant 5 native trees Visit by for every one that is Environment removed. Specialist and Support Environment staff Traffic Hauling (material, • Traffic Site visit and Project Daily visit by Environment Complied; Complied; Complied; problems and waste/debris and Management document locations construction Specialist of conflicts near equipment) activities Plan review supervisor of DSISC; PIU Barricading Barricading Barricading project (i) Plan transportation • Public DSISC. and done in pipe done in pipe done in pipe locations and routes so that heavy grievance Weekly PMC laying areas. laying areas. laying areas. haul road vehicles do not use • Number of visit by Local people Local people Local people narrow local roads, signages Construction informed before informed informed except in the immediate placed at Manager, start of work before start of before start of vicinity of delivery sites subproject Visit by No work work (ii) Schedule transport location Environment transportation of No No and hauling activities Specialist pipe/ material transportation transportation during non-peak hours; and Support done during of pipe/ of pipe/ (iii)Locate entry and exit Environment pick hours, no material done material done points in areas where staff impact on local during pick during pick there is low potential for public hours, no hours, no traffic congestion; movement. impact on impact on (iv) Drive vehicles in a Access local public local public considerate manner maintained in movement. movement. (v) Notify affected public most of the Access Access by public information cases at pipe maintained in maintained in notices, providing sign laying areas. most of the most of the boards informing nature Work plan cases at pipe cases at pipe and duration of informed to laying areas. laying areas. construction works and local public Work plan Work plan contact numbers for atleast 1 week informed to informed to concerns/complaints. in advance. local public local public Pipeline works atleast 1 week atleast 1 week (i) Confine work areas in advance. in advance. along the roads to the minimum possible extent; all the activities, including material and

155 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) waste/surplus soil stocking should be confined to this area. Provide barricading; avoid material/surplus soil stocking in congested areas – immediately removed from site/ or brought to the as and when required (ii) Leave spaces for access between mounds of soil to maintain access to the houses / properties (iii)Provide pedestrian access in all the locations; provide wooden/metal planks over the open trenches at each house to maintain the access. (iv) Inform the affected local population 1-week in advance about the work schedule (v) Plan and execute the work in such a way that the period of disturbance/ loss of access is minimum. (vi) Keep the site free from all unnecessary obstructions; (vii) Coordinate with Police for temporary road diversions, where necessary, and for provision of traffic aids if transportation activities

156 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) cannot be avoided during peak hours Generation of (i) Employ local labor Employment record Checking of Project - Environment Maximum Maximum Maximum temporary force as far as possible records locations Specialist of number of local number of number of employment (ii) Comply with labor DSISC and people are local people local people and increase laws PMC engaged in are engaged in are engaged in local work. Only at work. Only at in work. Only revenue few locations few locations at few outside/ migrant outside/ locations labours are migrant outside/ engaged. labours are migrant engaged. labours are engaged. Occupational (i) Comply with all • Site-specific • Checkin Project Daily visit by Environment Site-specific Site-specific Site-specific hazards which national, state and local Health and g of locations construction Specialist of Health and Health and Health and can arise core labor laws Safety (H&S) records supervisor of DSISC and Safety (H&S) Safety (H&S) Safety (H&S) during work (ii) Develop and Plan • Visual DSISC. PMC Plan under Plan under Plan under implement site-specific • Equipped first- inspecti Weekly implementation implementatio implementatio occupational health and aid stations; on of visit by After n n safety (OHS) Plan which • Medical site Construction Lockdown Copy of the will include measures insurance Manager, limited Site approved Copy of the Copy of the such as: (a) excluding coverage for Visit by Visit has been Health and approved approved public from the site; (b) workers Environment conducted Safety plan Health and Health and ensuring all workers are • Number of Specialist since June available with Safety plan Safety plan provided with and use accidents and Support 2020. DSISC., PIU available with available with personal protective • Supplies of Environment Supplementary DSISC., PIU DSISC., PIU equipment like helmet, potable staff COVID 19 H & Supplementary Supplementar gumboot, safety belt, drinking water; S plan prepared COVID 19 H & y COVID 19 H gloves, nose musk and • Record of H&S and compliance S plan & S plan ear plugs; (c) OHS orientation continued prepared and prepared and Training for all site trainings (Appendix II - compliance compliance personnel; (d) • Personal 10) continued continued documented procedures protective (Appendix II - (Appendix II - to be followed for all site equipment H & S training 10) 10) activities; and (e) including H & S training H & S training • Sign boards for documentation of work- COVID 19 done including including hazardous related accidents; on regular COVID 19 COVID 19 areas such as (iii) Ensure that qualified basis. Sample done on done on energized

157 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) first-aid can be provided electrical training regular basis. regular basis. at all times. Equipped devices and document is Sample Sample first-aid stations shall be lines, service attached as training training easily accessible rooms Appendix II- document is document is throughout the site; 12. attached as attached as (iv) Provide medical Drinking water Appendix II - Appendix II - insurance coverage for and first aid box 12. 12. workers; available at site. Drinking water Drinking water (v) Secure all Proper use of and first aid and first aid installations from PPEs- noted. box available box available unauthorized intrusion Tie up letter with at site. at site. and accident risks; nearby health Proper use of Proper use of (vi) Provide supplies of center in case PPEs- noted. PPEs- noted. potable drinking water; of emergency Tie up letter Tie up letter (vii) Provide clean eating obtained with nearby with nearby areas where workers are (Appendix II - health center health center not exposed to 14) Health in case of in case of hazardous or noxious checkup done emergency emergency substances; for worker obtained obtained (viii) Provide health and (Appendix II - (Appendix II - (Appendix II - safety orientation training 14) 14). Health 14). Health to all new workers to Medical checkup done checkup done ensure that they are Insurance for worker for worker apprised of the basic site arranged for the (Appendix II - (Appendix II - rules of work at the site, labourer (see 14) 14) personal protective Appendix II -4). Medical Medical protection, and Accident/ First Insurance Insurance preventing injuring to aid register is arranged for arranged for fellow workers; maintained at the labourer the labourer (ix) Provide visitor each site (see (see orientation if visitors to No case Appendix II- Appendix II - the site can gain access recorded during 4). 4). to areas where report period Accident/ First Accident/ First hazardous conditions or aid register is aid register is substances may be maintained at maintained at present. Ensure also that each site each site visitor/s do not enter No case No case hazard areas recorded recorded unescorted; during report during report

158 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) (x) Ensure the visibility of period period workers through their use of high visibility vests when working in or walking through heavy equipment operating areas; (xi) Ensure moving equipment is outfitted with audible back-up alarms; (xii) Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate Health risks (i) leave AC pipes in-situ Decommissioned Site Project Daily visit by Environment Till date no AC Till date no AC Till date no associated untouched AC Pipes inspection locations construction Specialist of pipes has been pipes has AC pipes has with AC pipes supervisor of DSISC and found been found been found DSISC. PMC Weekly visit by Construction Manager, Visit by Environment Specialist and Support

159 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) Environment staff Impact on (i) Restrict construction Public grievance Review of Project Daily visit by Environment No pedestrian No pedestrian No pedestrian community vehicle movements to documents Locations construction Specialist of accident has accident has accident has safety. Traffic defined access roads supervisor of DSISC; PIU been recorded been recorded been accidents and and demarcated working DSISC. and PMC till date. till date. recorded till vehicle areas (unless in the Weekly date. collision with event of an emergency) visit by After Pipe line laying Pipe line laying pedestrians (ii) Enforce strict speed Construction Lockdown work continued. work Pipe line during material limit (20-30 kph) for Manager, limited Site All safety continued. All laying work and waste playing on unpaved Visit by Visit has been measures safety continued. All transportation roads, construction Environment conducted arranged. measures safety tracks Specialist since June Improvement of arranged. measures (iii) Night-time haulage and Support 2020. access at few Improvement arranged. will be by exception only, Environment locations of access at Improvement as approved by the PIU staff required. few locations of access at to minimize driving risk No trench will required. few locations and disturbance to be kept open No trench will required. communities after pipe be kept open No trench will (iv) Adopt standard and laying. Caution after pipe be kept open safe practices for micro tape / barricade laying. Caution after pipe tunneling placed. tape/ barricade laying. (vi) Temporary traffic placed Caution tape / control (e.g. flagmen) barricade and signs will be placed. provided where necessary to improve safety and provide directions (vii) All drivers will undergo safety and training (viii) Public access to all areas where construction works are on-going will be restricted through the use of barricading and security personnel (ix) Warning signs,

160 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) blinkers will be attached to the barricading to caution the public about the hazards associated with the works, and presence of deep excavation (x) The period of time when the pipeline trench is left open will be minimized through careful planning (xi) Control dust pollution – implement dust control measures as suggested under air quality section (xii) Maintain regularly the vehicles and use of manufacturer-approved parts to minimize potentially serious accidents caused by equipment malfunction or premature failure. (xiii) Provide road signs and flag persons to warn of on-going trenching activities. Impact on (i) As far as possible • Public Site Construction Daily visit by Environment Mostly Mostly Mostly work camps located the camp site grievance inspection camps construction Specialist of Complied Complied Complied and work site. within the work sites; if • Accommodatio and review supervisor of DSISC and Few issues Few issues Few issues Temporary air any camp to be n Water and of DSISC. PMC such as such as such as and noise established outside sanitation documents Weekly establishment of establishment establishment pollution from these, then select a facilities for visit by After site office and of site office of site office machine camp site away from employees Construction Lockdown installation of and installation and operation, residential areas (at least • Housekeeping Manager, limited Site bio-toilet not yet of bio-toilet not installation of water pollution 100 m buffer shall be – regular Visit by Visit has been done at some yet done at bio-toilet not from storage maintained) disposal of Environment conducted newly started some newly yet done at and use of (ii) Avoid tree cutting for Specialist since June sites at zone started sites at some newly

161 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) fuels, oils, setting up camp facilities solid waste and Support 2020. 1,2,3,10,11,18,2 zone started sites solvents, and (iii) Camp site shall not Environment 0. 7,11,13,23,24. at zone lubricants be located near (100 m) staff In most of the In most of the 3,8,12,32. Unsanitary and water bodies, flood plains places local places local In most of the poor living flood prone/low lying labours are labours are places local conditions for areas, or any employed. employed. labours are workers ecologically, socially, Rented house Rented house employed. archeologically sensitive have been have been Rented house areas arranged at arranged at has been (iv) Separate the workers zone 2,6,10 and zone arranged at living areas and material 20 for few 3,4,10,15,18 zone 19 for storage areas clearly outside/ migrant and 20 for few few with a fencing and labours. outside/ outside/migra separate entry and exit Maintenance of migrant nt labours. (v) Provide proper housekeeping, labours. Maintenance temporary social Maintenance of accommodation with distancing, toilet of housekeeping proper materials, facility, drinking housekeeping, , ,social adequate lighting and water social distancing, ventilation, appropriate availability, distancing, toilet facility, facilities for winters and provision of fuel toilet facility, drinking water summers; ensure (kerosene or drinking water availability, conditions of livability at LPG) for availability, provision of work camps are cooking etc. are provision of fuel (kerosene maintained at the highest satisfactory at fuel (kerosene or LPG) for standards possible at all those locations. or LPG) for cooking etc. times; cooking etc. are available (vi) Consult PIU before are available at those locating project offices, at those locations. sheds, and construction locations. plants; (vii) Minimize removal of vegetation and disallow cutting of trees (viii) Ensure conditions of livability at work camps are maintained at the highest standards possible at all times;

162 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) living quarters and construction camps shall be provided with standard materials (as far as possible to use portable ready to fit-in reusable cabins with proper ventilation); thatched huts, and facilities constructed with materials like GI sheets, tarpaulins, etc., shall not be allowed as accommodation for workers (ix) Camp shall be provided with proper drainage, there shall not be any water accumulation (x) Provide drinking water, water for other uses, and sanitation facilities for employees (xi) Prohibit employees from cutting of trees for firewood; contractor should be providing proper facilities including cooking fuel (oil or gas; fire wood not allowed) (xii) Train employees in the storage and handling of materials which can potentially cause soil contamination (xiii) Recover used oil and lubricants and reuse or remove from the site

163 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) (xiv) Manage solid waste according to the following preference hierarchy: reuse, recycling and disposal to designated areas; provide a compost pit for biodegradable waste, and non- biodegradable / recyclable waste shall be collected and sold in local market (xv) Remove all wreckage, rubbish, or temporary structures which are no longer required (xvi) At the completion of work, camp area shall be cleaned and restored to pre-project conditions, and submit report to PIU; PIU to review and approve camp clearance and closure of work site Unsatisfactory (i) Appointment of (I) • Appointment Review of - - Environment Safety person Safety person Safety person compliance to Environment, Health and letter records Specialist of appointed from appointed appointed EMP Safety (EHS) Supervisor Monitoring records DSISC and contractor’s from from to ensure EMP PMC end; contractor’s contractor implementation environmental end; end; safeguard environmental environmental (ii) Timely submission of training safeguard safeguard monitoring reports including training training including pictures COVID 19 including including awareness COVID 19 COVID 19 done. awareness awareness Monitoring done. done. report submitted Monitoring Monitoring on monthly report report

164 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) basis. submitted on submitted on monthly basis. monthly basis. Damage due (i) Remove all spoils • Stockpile Review of Project Daily visit by Environment Complied; Complied; Complied; to debris, wreckage, rubbish, or Management documents Locations construction Specialist of Spoil Spoil Spoil spoils, excess temporary structures • Spoil and site supervisor of DSISC and Management Management Management construction (such as buildings, Management inspections DSISC. PMC Plan has been Plan has been Plan has materials shelters, and latrines) • Restoration of Weekly submitted for submitted for been which are no longer sites visit by the pipe laying the pipe laying submitted for required; and Construction work. work. the pipe Manager, No utilities No utilities laying work. (ii) All excavated roads Visit by affected during affected during No utilities shall be reinstated to Environment pipe laying at pipe laying at affected original condition. Specialist village roads. village roads. during pipe (iii) All disrupted utilities and Support All excavated All excavated laying at restored Environment road reinstated road reinstated village roads. (iv) All affected structures staff to original to original All excavated rehabilitated/compensate condition condition road d reinstated to original (v) The area that condition previously housed the construction camp is to be checked for spills of substances such as oil, paint, etc. and these shall be cleaned up. (vi) All hardened surfaces within the construction camp area shall be ripped, all imported materials removed, and the area shall be top soiled and re-grassed using the guidelines set out in the re-vegetation specification that forms part of this document. (vii) The contractor must

165 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Method of Location of Date of Name of Compliance Compliance Compliance Monitored (As a Monitoring Monitoring Monitoring Person Who Status/ Status/ Status/ minimum those Conducted Conducted Explanation for Explanation Explanation identified in the the BK 02A for BK 02B for BK 04 IEE should be Monitoring monitored) arrange the cancellation of all temporary services. (viii) Request PIU to report in writing that worksites and camps have been vacated and restored to pre-project conditions before acceptance of work.

Table 13: Summary of Environmental Monitoring Activities for the Package WBDWSIP/DWW/ICB/EM/01/2018-19: BULK WATER SUPPPLY Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) Design Phase Source sustainability • Discontinuation of current unsafe & • Design Document All project Before Environment Detailed design and efficiency unsustainable groundwater sources philosophy review and locations Commencem Specialist of continued section and creating a new comprehensive • Treatment LOP Survey ent and DSISC, wise. surface water (river) based water scheme during PIU and supply system • Project QA/QC final design PMU/PMC • Recovering wash water from plan treatment process to optimize the water use • Treatment and reuse of sludge from treatment process • Designing the entire system to maintain optimal flow and terminal pressure, and optimizing the overall energy usage • Reducing the incidence of water borne diseases by providing 100%

166 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) population including urban poor with potable water supplies • Preparation and implementation of a water quality surveillance program including development of a laboratory as part of the project by DBO contractor to ensure that supplied water meets the drinking water standards • Development of laboratory with all necessary environment, health and safety measures and adopting international standard procedures for water quality testing • Using low-noise and energy efficient pumping systems • Installing the noise-producing pumps and motors etc., in enclosed buildings with noise reducing walls, and also maintaining adequate buffer to the nearby inhabited areas • Provision of appropriate personal protection equipment to the workers and staff Chlorine handling and • Provide the following measure at the • Project Document WTP and Before Environment Detail design application risk – chlorine application unit: emergency review Booster Commencem Specialist of continued. health and safety risk ➢ Chlorine neutralization pit with a lime management pumping site ent and DSISC and Authorization under to workers and slurry feeder plan during PIU “The manufacture, general public ➢ Chlorine absorption and neutralization • Project safety final design storage and import facility and PPE use of hazardous ➢ Proper ventilation, lighting, entry and plan chemicals rules, exit facilities • Training plan 1989” will be done ➢ Visible and audible alarm facilities to as per requirement alert chlorine gas leak ➢ Facility for isolation in the event of major chlorine leakage ➢ Eye wash & shower facility ➢ Personal protection and safety

167 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) equipment for the operators in the chlorine plant (masks, oxygen cylinders, gloves, etc.,) • Provide training to the staff in safe handling and application of chlorine; this shall be included in the contract of Chlorinator supplier Supplier of Chlorinator equipment shall provide standard operating manual for safe operation and as well as maintenance and repairs; preferably these shall be provided both in English and Bengali Languages Tree cutting • Minimize removal of trees by adopting Tree felling • Checking of Project Before Environment Till now no tree to site condition and with appropriate requirement records locations Commencem Specialist of felling is required. If layout design of GLSRs and afforestation • Visual ent and DSISC and required proper • Obtain prior permission for tree cutting after final design inspection of during PIU measure will be • Plant and maintain 5 trees for each tree sites final design taken. that is removed Tree felling is required for pipe laying activities. Permission obtained from concerned department (Appendix III- 5) Pre-Construction Phase Telephone lines, • Identify and include locations and • List of affected Observation Specific Before Environment Under compliance. electric poles and operators of these utilities in the utilities and and project commencem Specialist of Contingency plan wires, water lines detailed design documents to prevent operators; document location ent of DSISC and preparation is under within proposed unnecessary disruption of services • Bid document checking construction PIU process. project area during construction phase; to include • Require construction contractor to Requirement Transmission main prepare a contingency plan to include for a pipeline alignment actions to be taken in case of contingency and L section unintentional interruption of services; plan for service drawing approved. and interruptions, And Clear water • Contractor prepared spoils (waste) waste main alignment management plan and traffic management design is under

168 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) management plan plan and traffic process management plan Spoil management plan and traffic management plan attached with SEMP. Conflicts with local • Prioritize areas within or nearest • List of •Site Specific Before Environment Under compliance. community; disruption possible vacant space in the project selected sites observation project commencem Specialist of WTP and Intake to traffic flow and location; for • Review of location ent DSISC and pump house sensitive receptors • If it is deemed necessary to locate construction documents of final design PIU boundary wall elsewhere, consider sites that will not work camps, • Field and construction has promote instability and result in stockpile level commencem started and it is in destruction of property, vegetation, areas, public ent of closed proximity. irrigation, and drinking water supply storage consultat construction And raw water pipe systems; areas, and ion line work is going on • Do not consider residential areas; disposal and field level public • Take extreme care in selecting sites areas. consultation is going to avoid direct disposal to water body • Written on regular basis to which will inconvenience the consent of know the problem of community. landowner/s local people during • For excess spoil disposal, ensure (a) (not lessee/s) pipe line laying work. site shall be selected preferably from barren, infertile lands. In case agricultural land needs to be selected, written Consent from landowners (not lessees) will be obtained; (b) debris disposal site shall be at least 200 m away from surface water bodies; (c) no residential areas shall be located within 50 m downwind side of the site; and (d) site is minimum 250 m away from sensitive locations like settlements, ponds/lakes or other water bodies Extraction of materials • Obtain construction materials only • List of • Checking Project sites Before DSISC Complied. can disrupt natural from government approved quarries approved of records commencem Construction All materials land contours and with prior approval of PIU; quarry sites • Visual ent of Management procured from vegetation resulting in • PIU to review, and ensure that and inspection construction and licensed vendors.

169 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) accelerated erosion, proposed quarry sources have all sources of of sites Environment disturbance in natural necessary clearances/permissions in materials al Safeguard drainage patterns, place prior to approval Team ponding and water • Contractor to submit to PIU on a logging, and water monthly basis documentation on pollution. material obtained from each source (quarry/ borrow pit) • Avoid creation of new borrow areas, quarries etc., for the project; if unavoidable, contractor to obtain all clearances and permissions as required under law, including Environmental Clearance (EC) prior to approval by PIU Failure to obtain • Obtain all necessary consents, List of applicable Checking All project Before Environment Under compliance. necessary consents, permits, clearance, NOCs, etc. prior legislation of locations commencem Specialist of CTE for WTP has permits, NOCs, etc. to award of civil works. documents ent of DSISC, PIU been applied, can result to design • Ensure that all necessary approvals construction and expected to receive revisions and/or for construction to be obtained by PMU/PMC shortly. (Application stoppage of works contractor are in place before start of – Appendix III- 6) construction provisions if any. NOC for tree felling • Acknowledge in writing and provide from Intake to report on compliance all obtained Ganjanarayanpur consents, permits, clearance, NOCs, raw water etc. transmission route • Include in detailed design drawings has been obtained and documents all conditions and (NOC – Appendix III provisions if necessary. -5).

NOC from I & W Department from Raw water transmission has been obtained.

NOC from I & W department for Clear water main will be

170 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) obtained and will be incorporated in next SEMR Health risk due to • Obtain details on location of asbestos cement Site Specific DSISC Complied. Till date exposure to asbestos underground AC pipes materials inspection project Construction no rubbish materials • Locate the new piper carefully to location Management containing asbestos avoid encountering AC pipes and cement has been • Leave the AC pipes undisturbed in the Environment found ground. al Safeguard Team Construction Phase Irreversible impact to Project manager and all key workers have Induction and Review of Project - Environment Safety training, PEP the environment, undergone training on EMP implementation tool box training Training Locations Specialist of talk, awareness workers, and including spoils/waste management, records DSISC, PIU training on COVID19 community Standard Operating Procedures (SOP) for Awareness Site and arranged on regular construction works; Occupational Health and training on Inspections PMU basis (Sample Safety (OHS) including COVID 19 H & S COVID19 Attached in awareness, core labour laws, applicable Appendix III -12). environmental laws, etc. Emissions from For all construction works • Location of Site Covering Air – noise DSISC Baseline and during construction vehicles, • Comply with the Direction of West stockpiles inspection different monitoring: Construction construction equipment, and Bengal Department of Environment • Monitoring Public locations. Once before Management monitoring have machinery used for under the Air Act, 1981 in controlling data- PM10, grievance Air – noise start of and been completed as installation of air pollution from construction PM2.5 NO2, register monitoring: construction Environment per IEE. (Complete pipelines resulting to activities SO2, CO Monitoring is Yearly 3 al Safeguard result certificates dusts and increase in • Comply with the air pollution / dust • Heavy expected to times during Team, PIU available in DSISC concentration of control measures for construction equipment be construction office as back up vehicle-related activities stipulated by the “Direction and conducted at (3-year period paper and attached pollutants such as of West Bengal Department of machinery 5 locations. considered) as Appendix III - 11) carbon monoxide, Environment under the Air Act, 1981 with air sulfur oxides, Direction No. EN/3170/T-IV-7 pollution During PUC certificate has particulate matter, /001/2009 dated: 10 December 2009” control construction been obtained for nitrous oxides, and • Damp down the soil and any • Water Monitoring vehicle as well as hydrocarbons. stockpiled material on site by water sprinkling conducted on equipment sprinkling; arrangement 28-10-2020 to (Appendix III - 2). • Use tarpaulins to cover the loose • Regular site 31-10-2020 material (soil, sand, aggregate etc.,) visit Water sprinkling is when transported by trucks; being doing as per

171 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) • Provide a dust screen around the requirement. construction sites at Intake and WTP work sites Along the pipe line, • Clean wheels and undercarriage of hard barricade haul trucks prior to leaving observed. construction site/quarry Soil is not covered • Control dust generation while by tarpaulins. unloading the loose material (particularly aggregate, soil) at the site Excavated soil is by sprinkling water and unloading being used for inside the barricaded area backfilling as well as • Stabilize surface soils where loaders, for filling up low support equipment and vehicles will laying land. operate by using water and maintain surface soils in a stabilized condition Excavation work • Apply water and maintain soils in a conducted as visible damp or crusted condition for section wise. temporary stabilization • Apply water prior to levelling or any other earth moving activity to keep the soil moist throughout the process • Cover the soil stocked at the sites with tarpaulins • Control access to work area, prevent unnecessary movement of vehicle, public trespassing into work areas; limiting soil disturbance will minimize dust generation • Ensure that all the construction equipment, machinery is fitted with pollution control devises, which are operating correctly, and have a valid pollution under control (PUC) certificate Pipeline works • Barricade the construction area using hard barricades (of 2 m height) on both sides and provide dust/wind

172 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) screen (such geo textile fabric) up to 3 m height (1m above the hard barricading) • Initiate site clearance and excavation work only after barricading of the site is done • Confine all the material, excavated soil, debris, equipment, machinery (excavators, cranes etc.,), to the barricaded area • Limit the stocking of excavated material at the site; remove the excess soil from the site immediately to the designated disposal area • Undertake the work section wise: 100 – 200 m section should be demarcated and barricaded • Conduct work sequentially - excavation, pipe laying, backfilling; conduct pipe testing section-wise (for a minimum length as possible) so that backfilling, stabilization of soil can be done. • Remove the excavated soil of first section to the disposal site; as the work progresses sequentially, by the time second section is excavated, the first section will be ready for back filling, use the freshly excavated soil for back filling, this will avoid stocking of material, and minimize the dust. • Backfilled trench at any completed section after removal of barricading will be the main source of dust pollution. • The traffic, pedestrian movement and wind will generate dust from backfilled section. Road restoration shall be

173 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) undertaken immediately. Mobilization of • All earthworks be conducted during • Areas for Site All project Daily visit by DSISC Under compliance. settled silt materials, the dry season to prevent the problem stockpiles, inspection locations construction Construction All safety aspect and chemical of soil run-off during monsoon storage Public supervisor of Management maintained. contamination from season; of fuels and grievance DSISC. and Excess spoil is being fuels and lubricants • Avoid stockpiling of earth fill lubricants and register Weekly Environment used for backfilling during construction especially during the monsoon waste materials visit by al Safeguard and filling up low can Contaminate season unless covered by tarpaulins • Number of silt Construction Team laying land. nearby surface water or plastic sheets; traps Manager, Storage of fuels not quality. • Prioritize re-use of excess spoils and installed along Visit by yet started. Ponding of water in materials in the construction works. If drainages (in Environment the pits /foundation spoils will be disposed, only slope) leading to Safeguard Fuel storage not excavations designated disposal areas shall be water bodies Team. found at any site. used; • Install temporary silt traps or Surface water quality sedimentation basins along the monitoring for pre- drainage leading to the water bodies; construction as well • Place storage areas for fuels and as construction lubricants away from any drainage period is completed. leading to water bodies; • Store fuel, construction chemicals etc., on an impervious floor, also avoid spillage by careful handling • Dispose any wastes generated by construction activities in designated sites; and • Conduct surface quality inspection according to the Environmental Management Plan (EMP). • Create a temporary drainage channel around the work area to arrest the entry of runoff from upper areas into the work area • Pump out the water collected in the pits / excavations to a temporary sedimentation pond; dispose off only clarified water into drainage channels/streams after sedimentation

174 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) in the temporary ponds • Consider safety aspects related to pit collapse due to accumulation of water Increase in noise • Plan activities in consultation with PIU Day time and • Checking of Covering Noise DSISC Complied; level due to earth- so that activities with the greatest night time noise records different monitoring: Construction Pre-construction moving and potential to generate noise are levels. • Visual locations. Once before Management baseline and during excavation conducted during periods of the day inspection of Air – noise start of and construction equipment, and the which will result in least disturbance; sites monitoring: construction Environment monitoring has been transportation of • Horns should not be used unless it is Monitoring is Yearly 3 al Safeguard completed. equipment, necessary to warn other road users or expected to times during Team materials, and animals of the vehicle’s approach; be construction Complete result people • Minimize noise from construction conducted at (3-year period certificates available equipment by using vehicle silencers, 5 locations. considered) in DSISC office as fitting jackhammers with noise- back up paper and reducing mufflers, and use portable During attached as street barriers to minimise sound construction Appendix III -11. impact to surrounding sensitive Monitoring receptor; and conducted on There is no as such • Maintain maximum sound levels not 28-10-2020 to noise generated exceeding 80 decibels (dBA) when 31-10-2020 from equipment. measured at a distance of 10 m or Daily visit by Stipulated condition more from the vehicle/s. construction as per SEMP is • Identify any buildings at risk from supervisor of followed vibration damage and avoiding any DSISC. use of pneumatic drills or heavy Weekly vehicles in the vicinity visit by • Consult local communities in advance Construction of the work to identify and address Manager, key issues, and avoid working at Visit by sensitive times, such as religious and Environment cultural festivals. Safeguard Team at operational site Impacts due to • Prepare and implement a • Waste • Checking Project Daily visit by Environment Complied excess excavated Construction Waste Management Management of records locations construction Specialist of earth, excess Plan List • Visual supervisor of DSISC, PIU Excess earth construction • As far as possible utilize the debris • Stockpile inspection DSISC. and Mostly used for

175 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) materials, and solid and excess soil in construction Management of sites Weekly PMU/PMC Backfilling and filling waste such as purpose, for example for raising the • Complaints visit by of low laying land. removed concrete, ground level or construction of access from Construction wood, packaging roads etc., Sensitive Manager, Waste dustbin has materials, empty • Stockpiles, lubricants, fuels, and other receptors Visit by placed at Intake and containers, spoils, materials should be located away • PMU/ PIU/ Environment WTP for proper oils, lubricants, and from steep slopes and water bodies; DSISC to Safeguard disposal of waste. other similar items. • Avoid stockpiling any excess spoils at report in writing Team. the site for long time. Excess that the No as such stock excavated soils should be disposed necessary piling allowed for off to approved designated areas environmental spoil immediately; restoration • If disposal is required, the site shall be work has been selected preferably from barren, done infertile lands; site should locate away from residential areas, forests, water bodies and any other sensitive land uses • Domestic solid wastes should be properly segregated in biodegradable and non-biodegradable for collection and disposal to designated solid waste disposal site; create a compost pit at workers camp sites for disposal of biodegradable waste; non- biodegradable / recyclable material shall be collected separately and sold in the local recycling material market • Residual and hazardous wastes such as oils, fuels, and lubricants shall be disposed off in disposal sites approved by local authorities/WBPCB; • Prohibit burning of construction and/or domestic waste; • Ensure that wastes are not haphazardly dumped thrown within and around the project site and adjacent areas; provide proper

176 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) collection bins, and create awareness to use the dust bins. • Conduct site clearance and restoration to original condition after the completion of construction work; PIU to ensure that site is properly restored • prior to issuing of construction completion certificate Disruption of service • Prepare a list of affected utilities and • List of affected Observation Project Daily visit by Environment Under compliance. and Damage to operators if any; utilities if any and locations construction Specialist of existing • Prepare a contingency plan to include and document supervisor of DSISC, PIU Contingency plan will infrastructure at actions to be done in case of operators checking DSISC. and be developed. specified project unintentional interruption of service Weekly PMU/PMC location visit by Consultation will be Construction done Manager, with utility dept.as Visit by and when required. Environment Safeguard Team. Loss of vegetation • Minimize removal of vegetation and Tree felling • Checking of Project Daily visit by Environment Permission of tree and tree cover disallow cutting of trees; requirement records locations construction Specialist of felling has been • If tree-removal will be required, obtain and afforestation • Visual supervisor of DSISC, PIU obtained as per final tree-cutting permit and after final design inspection of DSISC. and design for raw water • Plant 5 native trees for every one that sites Weekly PMU/PMC main (Intake to is removed. visit by Ganjanarayanpur). Construction For further Manager, processing of work, if Visit by tree felling is Environment required, permission Safeguard will be obtained from Team. concerned department. Traffic problems and Hauling (material, waste/debris and • Traffic Site visit and Project Daily visit by Environment Complied; conflicts near project equipment) activities Management document locations construction Specialist of Intake pump house locations and haul • Plan transportation routes so that Plan review supervisor of DSISC and and WTP is within road heavy vehicles do not use narrow • Public DSISC. PIU the isolated area. No

177 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) local roads, except in the immediate grievance Weekly need of traffic vicinity of delivery sites • Number of visit by management plan. • Schedule transport and hauling signages placed Construction Traffic management activities during non-peak hours; at Manager, plan has been • Locate entry and exit points in areas subproject Visit by prepared and where there is low potential for traffic location Environment submitted with congestion; Safeguard SEMP for pipeline • Drive vehicles in a considerate Team. work. manner During road block for • Notify affected public by public pipe line laying work, information notices, providing sign flagman has boards informing nature and duration observed. of construction works and contact numbers for concerns/complaints. Spaces for access Pipeline works between mounds of • Confine work areas along the roads to soil to maintained the minimum possible extent; all the access to the activities, including material & houses / properties waste/surplus soil stocking should be confined to this area. Proper Local people have barricading should be provided; avoid been informed in material/surplus soil stocking in advance but no congested areas – immediately miking or removed from site/ or brought to the announcement has as and when required been done. • Leave spaces for access between mounds of soil to maintain access to the houses / properties • Provide pedestrian access in all the locations; provide wooden/metal planks • over the open trenches at each house to maintain the access. • Inform the affected local population 1- week in advance about the work schedule • Plan and execute the work in such a way that the period of disturbance/

178 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) loss of access is minimum. • Keep the site free from all unnecessary obstructions; Coordinate with Traffic Police for temporary road diversions, where necessary, and for provision of traffic aids if transportation activities cannot be avoided during peak hours Generation of • Employ local labor force as far as Employment Checking of Project Daily visit by Environment Local people are temporary possible record records locations construction Specialist of engaged as far as employment and • Comply with labor laws supervisor of DSISC, PIU possible. increase in local DSISC. and revenue Weekly PMU/PMC visit by Construction Manager, Visit by Environment Safeguard Team. Occupational • Comply with all national, state and • Site-specific • Checking of Project Daily visit by Environment Under compliance. hazards which can local core labor laws Labour License, Health and records locations construction Specialist of arise during work All Risk policy, and WC Policy. Safety (H&S) • Visual supervisor of DSISC; PIU Site-specific Health • Develop and implement site-specific Plan inspection of DSISC. and and occupational health and Site-specific • Equipped first- sites Weekly PMU/PMC Safety (H&S) occupational health and safety (OHS) aid visit by Plan include Plan and Supplementary H & S plan stations; Construction COVID19 mitigation for COVID 19 have been developed • Medical Manager, plan submitted by and implemented which included insurance Visit by contractor and measures such as: (a) excluding coverage for Environment approved by DSISC public from the site; (b) maintaining workers Safeguard and PIU. social distancing for protection from • Number of Team. COVID 19 infection; (c) ensuring all accidents Induction and tool workers are provided with and use • Supplies of box training personal protective equipment like potable drinking including COVID 19 helmet, gumboot, safety belt, gloves, water; awareness arranged nose mask, face mask and ear plugs; • Record of H&S by contractor and (d) OHS Training and COVID 19 orientation first aid training

179 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) awareness H & S training for all site trainings arranged by DSISC personnel; (e) documented • Personal (sample shown in procedures to be followed for all site protective Appendix III -12) activities including follow of SOP for equipment PPE and visibility COVID 19 as developed for the • Sign boards for vest are observed. project and H & S plan; and (f) hazardous areas But in WTP and in documentation of work-related such as pipe line laying work accidents; energized some workers not • Ensure that qualified first-aid can be electrical devices using safety shoes. provided at all times. Equipped first- and lines, aid stations shall be easily accessible service Drinking water throughout the site; rooms and first aid box • Provide medical insurance coverage available at site and for workers; ambulance available • Secure all installations from at sites. unauthorized intrusion and accident . risks; Medical Insurance • Provide supplies of potable drinking arranged for the water; labourer (see • Provide clean eating areas where Appendix III- 14). workers are not exposed to Medical tie up with hazardous or noxious substances; health institute done • Provide health and safety orientation and also health training including COVID 19 risk and check- up done mitigation to all new workers to (Appendix III -14). ensure that they are apprised of the basic site rules of work at the site, Proper precaution personal protective protection, and has been taken at preventing injuring to fellow workers; site and labour are • Provide visitor orientation if visitors to filling annexure 1 & 2 the site can gain access to areas format as per project where hazardous conditions or SOP/ H & S plan of substances may be present. Ensure COVID19. also that visitor/s do not enter hazard areas unescorted; Accident register is maintained at site. • Ensure the visibility of workers One near miss through their use of high visibility accident happened vests when working in or walking at site and

180 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) through heavy equipment operating documents attached areas; as Appendix III - 13. • Ensure moving equipment is outfitted with audible back-up alarms; Face Mask has been • Mark and provide sign boards for provided to labour. hazardous areas such as energized But it is observed electrical devices and lines, service that labours are not rooms housing high voltage using mask while equipment, and areas for storage and working. disposal. • Disallow worker exposure to noise Paddle sanitizer is level greater than 85 dBA for a available at Intake duration of more than 8 hours per day and WTP. without hearing protection. The use of hearing protection shall be enforced actively. • Standard Operating Procedure (SOP) for the project and Supplementary H & S plan for COVID 19 prepared which cover, o General instruction to follow to prevent the spread of COVID- 19 in construction workplace o Detail (step-by-step) work procedure to getting the workplace ready under COVID- 19 situation o Worksite prevention practice at work site, office, during meeting, travelling, etc. o Precaution taken at workmen habitat/ camp o Control measures taken for deploying new workmen at site o Use of PPEs: face mask – hand gloves, maintaining social distancing, disinfection, requirement of awareness

181 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) covered under the H & S plan. (Separate H & S plan for COVID 19 as supplementary document developed and keep as standalone document to mitigate COVID 19 health risk) Health risks • Leave AC pipes in-situ untouched asbestos cement Site Specific Daily visit by DSISC Till date no asbestos associated with AC materials inspection project construction Construction cement material has pipes location supervisor of Management been found on site DSISC. and Weekly Environment visit by al Safeguard Construction Team Manager and Environment Team of DSISC of operational sites. Traffic accidents and • Restrict construction vehicle Public grievance Review of Project Daily visit by Environment Work continued vehicle collision with movements to defined access roads documents Locations construction Specialist of within fixed WTP pedestrians during and demarcated working areas supervisor of DSISC and campus. No material and waste (unless in the event of an emergency) DSISC. PIU pedestrian accident transportation • Enforce strict speed limit (20-30 Weekly has been recorded kmph) for playing on unpaved roads, visit by till date construction tracks Construction No traffic control and • Night-time haulage will be by Manager, application of traffic exception only, as approved by the Visit by management plan is PIU to minimise driving risk and Environment required. disturbance to communities Safeguard Only during • Adopt standard and safe practices for Team. transportation, and micro tunnelling movement of hydra • Temporary traffic control (e.g. and entry of vehicle flagmen) and signs will be provided at construction site where necessary to improve safety controlled by and provide directions concerned • All drivers will undergo safety and construction training supervisor • Public access to all areas where Partial barricading

182 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) construction works are on-going will noted be restricted through the use of Safety training barricading and security personnel provided • Warning signs, blinkers will be attached to the barricading to caution the public about the hazards associated with the works, and presence of deep excavation • The period of time when the pipeline trench is left open will be minimized through careful planning • Control dust pollution – implement dust control measures as suggested under air quality section • Maintain regularly the vehicles and use of manufacturer-approved parts to minimize potentially serious accidents caused by equipment malfunction or premature failure. • Provide road signs and flag persons to warn of on-going trenching activities Temporary air and • As far as possible located the camp • Water and Site Construction Daily visit by Environment To be noise pollution from site within the work sites; if any camp sanitation inspection camps construction Specialist of Complied. machine operation, to be established outside these, then facilities and review of supervisor of DSISC and Labour camp not yet water pollution from select a camp site away from for employees documents DSISC. PIU constructed. Local storage and use of residential areas (at least 100 m • Housekeeping Weekly labours engaged. fuels, oils, solvents, buffer shall be maintained) regular disposal visit by and lubricants • Avoid tree cutting for setting up camp of Construction facilities solid waste Manager, Unsanitary and poor • Camp site shall not be located near Visit by living conditions for (100 m) water bodies, flood plains Environment workers flood prone/low lying areas, or any Safeguard ecologically, socially, archeologically Team. sensitive areas • Separate the workers living areas and material storage areas clearly with a fencing and separate entry and exit

183 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) • Provide proper temporary accommodation with proper materials, adequate lighting and ventilation, appropriate facilities for winters and summers; ensure conditions of livability at work camps are maintained at the highest standards possible at all times; • Consult PIU before locating project offices, sheds, and construction plants; • Minimize removal of vegetation and disallow cutting of trees • Ensure conditions of liability at work camps are maintained at the highest standards possible at all times; living quarters and construction camps shall be provided with standard materials (as far as possible to use portable ready to fit-in reusable cabins with proper ventilation); thatched huts, and facilities constructed with materials like GI sheets, tarpaulins, etc., shall not be allowed as accommodation for workers • Camp should be protected from COVID 19 health risk. All Health and safety procedure to follow for operation of camp (H & S plan for COVID 19 will be used as ref. document) during stay, cooking, eating, use of toilet- common space etc. • Self- hygiene, regular disinfection of entire camp and toilet, maintaining of social distancing to be continued for protection from COVID 19 infection • Unknown person not allowed within

184 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) the camp • Camp shall be provided with proper drainage, there shall not be any water accumulation • Maintenance of hygienic environment at staying area, cooking area and toilet • Provide drinking water, water for other uses, and sanitation facilities for employees • Prohibit employees from cutting of trees for firewood; contractor should be providing proper facilities including cooking fuel (oil or gas; fire wood not allowed) • Train employees in the storage and handling of materials which can potentially cause soil contamination • Recover used oil and lubricants and reuse or remove from the site • Manage solid waste according to the following preference hierarchy: reuse, recycling and disposal to designated areas; provide a compost pit for biodegradable waste, and non- biodegradable / recyclable waste shall be collected and sold in local market • Remove all wreckage, rubbish, or temporary structures which are no longer required • At the completion of work, camp area shall be cleaned and restored to pre- project conditions, and submit report to PIU; PIU to review and approve camp clearance and closure of work site There are no • Consult Archaeological Survey of Site inspection Site Project Daily visit by Environment Not found any protected properties in India (ASI) or West Bengal State records inspection Locations construction Specialist of Archaeological site

185 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) the subproject sites. Archaeology Department to obtain an and review of supervisor of DSISC and within the vicinity. However, in case of expert assessment of the documents DSISC. PMU/PMC chance finds, archaeological potential of the site Weekly contractors will be • Include state and local archaeological, visit by required to follow a cultural and historical authorities, and Construction protocol as defined in interest groups in consultation forums Manager, the mitigation as project stakeholders so that their Visit by measures. expertise can be made available. Environment • In case of chance finds, works must Safeguard be stopped immediately until such Team. time chance finds are cleared by experts Unsatisfactory • Appointment of EHS Supervisor to Appointment Review of - - Environment Complied compliance to EMP ensure EMP implementation letter records Specialist of EHS officer already • Timely submission of monitoring Monitoring DSISC and appointed for the reports including pictures records PIU package Monitoring report preparation just started. Damage due to • Remove all spoils wreckage, rubbish, Stockpile Review of Project Daily visit by Environment Complied; Spoil debris, spoils, excess or temporary structures (such as Management documents Locations construction Specialist of Management Plan construction materials buildings, shelters, and latrines) which Spoil and site supervisor of DSISC and has been submitted are no longer required; and Management inspections DSISC. PIU as a part of SEMP. • All excavated roads shall be Restoration of Weekly reinstated to original condition. sites visit by • All disrupted utilities restored Construction • All affected structures Manager, rehabilitated/compensated Visit by • The area that previously housed the Environment construction camp is to be checked Safeguard for spills of substances such as oil, Team. paint, etc. and these shall be cleaned up. • All hardened surfaces within the construction camp area shall be ripped, all imported materials removed, and the area shall be top soiled and re-grassed using the

186 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts (List from Mitigation Measures Parameters Method of Location of Date of Name of Compliance Status/ IEE) (List from IEE) Monitored (As a Monitoring Monitoring Monitoring Person Who Explanation minimum those Conducted Conducted identified in the the IEE should be Monitoring monitored) guidelines set out in the revegetation specification that forms part of this document. • The contractor must arrange the cancellation of all temporary services. • Request PIU to report in writing that worksites and camps have been vacated and restored to pre-project conditions before acceptance of work.

Table 14: Summary of Environmental Monitoring Activities for the East Medinipur Package WBDWSIP/DWW/ICB/EM/02/2018-19 : Water Supply Distribution at Nandigram I and II Block

Impacts Mitigation Measures Parameters Monitored Method of Location of Date of Name of Compliance (As a minimum those Monitoring Monitoring Monitoring Person Who Status/ identified in the IEE Conducted Conducted Explanation should be monitored) the Monitoring Design Phase Source (i) Gravity distribution system: designing the • Design philosophy Document review All project Before Environment Compiled: sustainability entire system to maintain optimal flow and • Project QA/QC plan and LOP Survey locations commenceme Specialist of Zone wise design and efficiency terminal pressure, and optimizing the overall • Selection nt of final DSISC; PIU continued. Pipeline energy usage methodology for design and work continue at 6 (ii)Implementation of a water quality distribution network PMC Zones- 3, 5, 6,7,8,9 surveillance program including development of a laboratory as part of the project to ensure that supplied water meets the drinking water standards (iii)Minimizing water losses from pipelines by perfect jointing and alignments using appropriate techniques (iv) Reducing the incidence of water borne diseases by providing 100% population including urban poor with potable water supplies

187 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Monitored Method of Location of Date of Name of Compliance (As a minimum those Monitoring Monitoring Monitoring Person Who Status/ identified in the IEE Conducted Conducted Explanation should be monitored) the Monitoring Socio (i) Avoid using low-lying lands / ponds for List of selected location Site survey All OHR sites Before Environment No ponds have economic construction of OHRs; alternative private for OHRs Commenceme Specialist of been filled for impact – loss lands may be explored within the vicinity; nt of final DSISC and construction work. fishery area (ii)Review the applicability of West Bengal design PMC Inland Fisheries Act, 1984, whether the site falls under the definition of fisher area; obtained permission from Fisheries Department if required prior to start of construction Tree cutting (i) Minimize removal of trees by adopting to • Tree felling Site survey and All project Before Environment Under compliance, site condition and with appropriate layout requirement review of site locations commenceme Specialist of no tree felling has design of OHRs within the sites • Site layout plan layout/ pipeline nt of final DSISC; PIU been envisaged for (ii)Avoid cutting of trees by adopting suitable • NOC – paper alignment plan design and PMC these 6 zones alignment changes as required during laying documents from In case of tree of pipelines; line agency felling in further (iii)In unavoidable cases, obtain prior work progress, permission for tree cutting NOC will be taken (iv)Plant and maintain 5 trees for each tree from concern that is removed authority. Replantation will be adopted after construction as per Govt. norms. Pre-Construction Phase Telephone (i) Identify and include locations and • List of affected • Observation Specific Before Environment Complied lines, electric operators of these utilities in the detailed utilities if any and And project commenceme Specialist of A contingency plan poles and design documents to prevent unnecessary operators • document location nt of DSISC; PIU has been prepaid wires, water disruption of services during construction • Bid document to checking construction and for avoiding lines within phase; and include requirement PMC unnecessary proposed (ii) Require construction contractors to for a contingency disruption of project area prepare a contingency plan to include plan for service services during actions to be taken in case of unintentional interruptions construction. interruption of services. (example provision Spoil and Traffic (iii) Require contractors to prepare spoils of water if Management plan (waste) management plan and traffic disruption is more prepared. management plan than 24 hours), And enclosed in waste management SEMP plan and traffic management plan

188 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Monitored Method of Location of Date of Name of Compliance (As a minimum those Monitoring Monitoring Monitoring Person Who Status/ identified in the IEE Conducted Conducted Explanation should be monitored) the Monitoring Conflicts with (i) Prioritize areas within or nearest possible • List of selected • Site Specific Before Environment Complied local vacant space in the project location; sites for observation project commenceme Specialist of No disruption community; (ii) If it is deemed necessary to locate construction work • Review of location nt DSISC; PIU noted. disruption to elsewhere, consider sites that will not camps, hot mix documents of final design and Area selected traffic flow and promote instability and result in destruction plants, stockpile • Grievance and PMC nearby vacant sensitive of property, vegetation, irrigation, and areas, storage Register commenceme place receptors drinking water supply systems; areas, and disposal nt of No complete road (iii) Do not consider residential areas; areas construction closure expected. (iv) Take extreme care in selecting sites to avoid direct disposal to water body which • Written consent of will inconvenience the community. landowner/s (not (v) For excess spoil disposal, ensure (a) site lessee/s) shall be selected preferably from barren, infertile lands. In case agricultural land needs to be selected, written consent from landowners (not lessees) will be obtained; (b) debris disposal site shall be at least 200 m away from surface water bodies; (c) no residential areas shall be located within 50 m downwind side of the site; and (d) site is minimum 250 m away from sensitive locations like settlements, ponds/lakes or other water bodies. Extraction of (i) Obtain construction materials only from• List of approved • Checking Quarries Daily visit by DSISC Complied; materials can government approved quarries with prior quarry sites and of records and construction Construction disrupt natural approval of PIU; sources of • Visual material supervisor of Management Approval obtained land contours (ii) PIU to review, and ensure that proposed materials inspection source DSISC. and from DSISC, PIU and vegetation quarry sources have all necessary of sites areas Weekly Environmenta before resulting in clearances/ permissions in place prior to visit by l Safeguard procurement. accelerated approval Construction Team erosion, (iii) Contractor to submit to PIU on a Manager and Presently new disturbance in monthly basis documentation on material Environment borrow area. not natural obtained from each source (quarry/ borrow Team of required drainage pit) DSISC of patterns, (iv) Avoid creation of new borrow areas, operational ponding and quarries etc., for the project; if unavoidable, sites. water logging, contractor to obtain all clearances and and water permissions as required under law, pollution. including Environmental Clearance prior to approval by PIU

189 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Monitored Method of Location of Date of Name of Compliance (As a minimum those Monitoring Monitoring Monitoring Person Who Status/ identified in the IEE Conducted Conducted Explanation should be monitored) the Monitoring Failure to (i) Obtain all necessary consents, permits, List of applicable Checking All project Before Mostly Complied obtain clearance, NOCs, etc. prior to award of civil legislation of documents locations commenceme Tree cutting NOC necessary works. nt of will be obtained as consents, (ii) Ensure that all necessary approvals for construction per requirement permits, construction to be obtained by contractor NOCs, etc. are in place before start of construction can result to (iii) Acknowledge in writing and provide design report on compliance all obtained consents, revisions permits, clearance, NOCs, etc. and/or (iv) Include in detailed design drawings and stoppage of documents all conditions and provisions if works necessary Health risk due (i) Obtain details on location of asbestos Detailed construction Site inspection Specific Daily visit by DSISC Till date no rubbish to exposure to cement materials drawings showing project construction Construction containing asbestos asbestos (ii) Lay the new pipes carefully to avoid alignment of AC pipes location supervisor of Management cement has been materials encountering AC pipes DSISC. and found (ii) Leave the AC pipes undisturbed in the Weekly Environmenta AC pipe is not using ground. visit by l Safeguard in this project. Construction Team Manager and Environment Team of DSISC of operational sites. Construction Phase Irreversible Project manager and all key workers have Induction and Tool box Review of training Project Environment Under Compliance; impact to the undergone training on EMP implementation training on daily basis. records and site locations Specialist of Induction Training, environment, including spoils/waste management, Awareness training on inspection DSISC: PIU Pep talk, workers, and Standard Operating Procedures (SOP) for OCVID19 pandemic. and awareness training community construction works; Occupational Health PMC of COVID is and Safety (OHS) including COVID 19 H & arranged by S awareness, core labour laws, applicable contractor on environmental laws, etc. regular basis. (sample attached as Appendix III - 12) Emissions For all construction works • Location of Site inspection Project Daily visit by Environment • Under from • Comply with the air pollution / dust control stockpiles locations Air construction Specialist of compliance.

190 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Monitored Method of Location of Date of Name of Compliance (As a minimum those Monitoring Monitoring Monitoring Person Who Status/ identified in the IEE Conducted Conducted Explanation should be monitored) the Monitoring construction measures for construction activities • Monitoring data- monitoring as supervisor of DSISC; PIU • Water sprinkling vehicles, stipulated by the “Direction of West PM10, PM2.5, SO2, per selected DSISC. and has been done at equipment, Bengal Department of Environment under NO2, CO sites in Weekly PMC working sites as and machinery the Air Act, 1981 Direction No. • Heavy equipment reference to visit by per requirement. used for EN/3170/T-IV-7 /001/2009 dated: 10 and machinery with SEMP. Construction • Use tarpaulins installation of December 2009” air pollution control Manager, Visit and plastic for pipelines • Damp down the soil and any stockpiled • Water sprinkling by covering resulting to material on site by water sprinkling; arrangement Environment construction dusts and • Use tarpaulins to cover the loose material • Cover materials Specialist and material. increase in (soil, sand, aggregate etc.,) when Support • Pre construction concentration transported by trucks; Environment and during of vehicle- • Provide a dust screen/high compound wall staff construction related around the construction sites (OHRs) Air- monitoring ambient air pollutants such • Clean wheels and undercarriage of haul schedule as monitoring has as carbon trucks prior to leaving construction per SEMP been completed monoxide, site/quarry as per IEE. and sulfur oxides, • Control dust generation while unloading Monitoring Scanned test particulate the loose material (particularly aggregate, conducted certificates matter, nitrous soil) at the site by sprinkling water and between attached as oxides, and unloading inside the barricaded area 22/10/2020 Appendix III -11 hydrocarbons. • Stabilize surface soils where loaders, and • PUC certificate of support equipment and vehicles will 29/10/2020. vehicle obtained operate by using water and maintain and copy of PUC surface soils in a stabilized condition is available at • Apply water prior to levelling or any other DSISC office. earth moving activity to keep the soil moist • For pipe line throughout the process work, barricading, • Control access to work area, prevent removal of earth, unnecessary movement of vehicle, public backfilling done trespassing into work areas; limiting soil but improvement disturbance will minimize dust generation required at few locations • Ensure that all the construction equipment • A plan have been and machineries are fitted with pollution adopted for pipe control devises, which are operating laying work correctly, and have a valid pollution under progresses as control (PUC) certificate sequentially i.e Pipeline works first remove the • Barricade the construction area excavated soil of

191 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Monitored Method of Location of Date of Name of Compliance (As a minimum those Monitoring Monitoring Monitoring Person Who Status/ identified in the IEE Conducted Conducted Explanation should be monitored) the Monitoring • Initiate site clearance and excavation work first section will only after barricading of the site is done be disposed in a • Confine all the material, excavated soil, disposal site; by the time second debris, equipment, machinery section is (excavators, cranes etc.,), to the excavated, the barricaded area first section will • Limit the stocking of excavated material at be ready for back the site; remove the excess soil from the filling, use the site immediately to the designated freshly excavated soil for back disposal area filling, this will • Undertake the work section wise avoid stocking of • Conduct work sequentially - excavation, material, and pipe laying, backfilling; conduct pipe minimize the testing section-wise (for a minimum length dust. as possible) so that backfilling, stabilization of soil can be done. • Remove the excavated soil of first section to the disposal site; as the work progresses, sequentially, by the time second section is excavated, the first section will be ready for back filling, use the freshly excavated soil for back filling, this will avoid stocking of material, and minimize the dust. • Backfilled trench at any completed section after removal of barricading will be the main source of dust pollution. The traffic, pedestrian movement and wind will generate dust from backfilled section. Road restoration shall be undertaken immediately. Mobilization of • All earthworks be conducted during the• Areas for stock piles, Site inspection All project Daily visit by Environment Mostly complied settled silt dry season to prevent the problem of soil storage of fuels and locations construction Specialist of • All excess spoil, materials, and run-off during monsoon season; lubricants and waste supervisor of DSISC: PIU is utilized for

192 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Monitored Method of Location of Date of Name of Compliance (As a minimum those Monitoring Monitoring Monitoring Person Who Status/ identified in the IEE Conducted Conducted Explanation should be monitored) the Monitoring chemical • Avoid stockpiling of earth fill especially materials. DSISC. and backfilling and for contamination during the monsoon season unless• Entry routes of Weekly PMC filling up low from fuels and covered by tarpaulins or plastic sheets; pollutant in nearby visit by laying sites. lubricants • Prioritize re-use of excess spoils and water bodies. Construction • Material never during materials in the construction works. If Manager, Visit disposed in the construction spoils will be disposed, only designated by pond located can disposal areas shall be used; Environment within this site. contaminate • Install temporary silt traps or Specialist and • Fuel storage not nearby surface sedimentation basins along the drainage Support started. water quality. leading to the water bodies; Environment • Pre construction Ponding of • Place storage areas for fuels and staff and during water in the lubricants away from any drainage leading construction pits / to water bodies; surface water foundation • Store fuel, construction chemicals etc., on quality monitoring excavations an impervious floor, also avoid spillage by has been done careful handling • All safety aspect • Dispose any wastes generated by maintained construction activities in designated sites; partially. Need to and be improved. • Create a temporary drainage channel • Generation of around the work area to arrest the entry of construction runoff from upper areas into the work area waste is very less • Pump out the water collected in the pits / however it will be excavations to a temporary sedimentation disposed at pond; dispose of only clarified water into designated drainage channels/streams after disposal sites. sedimentation in the temporary ponds • Consider safety aspects related to pit collapse due to accumulation of water • Surface and ground water quality have been monitored according to the Environmental Management Plan (EMP) and after collection of representative samples from different work sites Increase in • Plan activities in consultation with PIU so • Complaints from • Checking of All project Noise Environment Mostly Complied. noise level due that activities with the greatest potential to sensitive receptors records locations monitoring Specialist of No such noise to earth- generate noise are conducted during • Use of silencers in • Visual Noise- schedule as DSISC; PIU generating moving and periods of the day which will result in least noise-producing inspection of sites monitoring as per SEMP. and problem near excavation disturbance; equipment per selected Monitoring PMC the project

193 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Monitored Method of Location of Date of Name of Compliance (As a minimum those Monitoring Monitoring Monitoring Person Who Status/ identified in the IEE Conducted Conducted Explanation should be monitored) the Monitoring equipment, • Horns should not be used unless it is • Monitoring data sites in ref. to conducted location. and the necessary to warn other road users or SEMP between Pre-construction transportation animals of the vehicle’s approach; 22/10/2020 and during of equipment, • Minimize noise from construction and construction materials, and equipment by using vehicle silencers, 30/10/2020. monitoring people fitting jackhammers with noise-reducing done. mufflers, and use portable street barriers Monitoring will be to minimize sound impact to surrounding continued as sensitive receptor; and per IEE. • Identify any buildings at risk from vibration Pre construction damage and avoiding any use of and during pneumatic drills or heavy vehicles in the construction results vicinity are available at • Consult local communities in advance of DSISC office and the work to identify and address key scanned certificates issues, and avoid working at sensitive attached as times, such as religious and cultural Appendix III -11. festivals. There is no building • Noise level have been monitored at nearby working different work locations area which is under risk by earth moving activities. Impacts due to • Prepare and implement a Construction • Waste Management • Checking of Project Daily visit by Environment Under compliance. excess Waste Management Plan List and Spoil records locations construction Specialist of Excess soil is used excavated • As far as possible utilize the debris and Management Plan • Visual supervisor of DSISC: PIU for backfilling and earth, excess excess soil in construction purpose, for • Stockpile • inspection of DSISC. and filling up low laying construction example for raising the ground level or Management sites Weekly PMC areas. materials, and construction of access roads etc., • Complaints from visit by No hazardous solid waste • Stockpiles, lubricants, fuels, and other Sensitive receptors Construction waste is generated. such as materials should be located away from • PMU/PIU/DSISC to Manager, Visit Till now no labour removed steep slopes and water bodies; report in writing that by camp has been concrete, • Avoid stockpiling any excess spoils at the the necessary Environment constructed, so wood, site for long time. Excess excavated soils environmental Specialist and there is no chance packaging should be disposed of to approved restoration work Support of generation of materials, designated areas immediately; has been done Environment domestic solid empty • If disposal is required, the site shall be staff waste. containers, selected preferably from barren, infertile Road restoration is spoils, oils, lands; site should be located away from taking place after lubricants, and residential areas, forests, water bodies pipe laying other similar activities. Road

194 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Monitored Method of Location of Date of Name of Compliance (As a minimum those Monitoring Monitoring Monitoring Person Who Status/ identified in the IEE Conducted Conducted Explanation should be monitored) the Monitoring items. and any other sensitive land uses restoration partially • Domestic solid wastes should be properly complied. segregated in biodegradable and non- biodegradable for collection and disposal to designated solid waste disposal site; create a compost pit at workers’ camp sites for disposal of biodegradable waste; non-biodegradable / recyclable material shall be collected separately and sold in the local recycling material market • Residual and hazardous wastes such as oils, fuels, and lubricants shall be disposed of in disposal sites approved by local authorities/West Bengal Pollution Control Board (WBPCB); • Prohibit burning of construction and/or domestic waste; • Ensure that wastes are not haphazardly dumped thrown within and around the project site and adjacent areas; provide proper collection bins, and create awareness to use the dust bins. • Conduct site clearance and restoration to original condition after the completion of construction work; PIU to ensure that site is properly restored prior to issuing of construction completion certificate Disruption of • Prepare a list of affected utilities and List of affected utilities if Observation and Project Daily visit by Environment Complied. service and operators if any; any and operators. document locations construction Specialist of Contingency plan damage to • Prepare a contingency plan to include checking supervisor of DSISC and has been existing actions to be done in case of unintentional DSISC. PIU developed. infrastructure interruption of service Weekly As at specified visit by per requirement. project Construction consultation location Manager, Visit with utility dept. as by and when required. Environment Specialist and Support

195 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Monitored Method of Location of Date of Name of Compliance (As a minimum those Monitoring Monitoring Monitoring Person Who Status/ identified in the IEE Conducted Conducted Explanation should be monitored) the Monitoring Environment staff Loss of • Minimize removal of vegetation and Tree felling requirement • Checking of Project Daily visit by Environment Till now no vegetation and disallow cutting of trees, by adopting best and afforestation after records locations construction Specialist of requirement of tree tree cover site layout and pipeline alignments final design • Visual supervisor of DSISC and felling. • If tree-removal will be required, obtain • inspection of DSISC. PMC If required, NOC tree-cutting permit and sites Weekly will be obtained • Plant 5 native trees for every one that is visit by from concerned removed. Construction authority. Manager, Visit by Environment Specialist and Support Environment staff Traffic Hauling (material, waste/debris and Traffic Management Site visit and Project Daily visit by Environment Traffic management problems and equipment) activities Plan document review locations construction Specialist of plan has been conflicts near • Plan transportation routes so that heavy Project information supervisor of DSISC; PIU already prepared project vehicles do not use narrow local roads, board. DSISC. and and maintained. locations and except in the immediate vicinity of delivery Safety signages placed Weekly PMC Some of the places haul road sites at subproject locations. visit by barricade observed • Schedule transport and hauling activities Construction during pipe laying during non-peak hours; Manager, Visit work and its • Locate entry and exit points in areas by partially complied. where there is low potential for traffic Environment All pipe transport congestion; Specialist and during non- peak • Drive vehicles in a considerate manner Support hours. • Notify affected public by public information Environment Project information notices, providing sign boards informing staff board has been nature and duration of construction works displayed at OHSR and contact numbers for sites. concerns/complaints. Safety signage not Pipeline works displayed at all pipe • Confine work areas along the roads to the laying sites. minimum possible extent; all the activities, Access available including material and waste/surplus soil between excavated stocking should be confined to this area. soil and to the Provide barricading; avoid house or properties.

196 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Monitored Method of Location of Date of Name of Compliance (As a minimum those Monitoring Monitoring Monitoring Person Who Status/ identified in the IEE Conducted Conducted Explanation should be monitored) the Monitoring material/surplus soil stocking in congested Spoil not stored areas – immediately removed from site/ or within the access brought to the as and when required areas. • Leave spaces for access between mounds of soil to maintain access to the houses / properties • Provide pedestrian access in all the locations; provide wooden/metal planks over the open trenches at each house to maintain the access. • Inform the affected local population 1- week in advance about the work schedule • Plan and execute the work in such a way that the period of disturbance/ loss of access is minimum. • Keep the site free from all unnecessary obstructions; • Coordinate with Police for temporary road diversions, where necessary, and for provision of traffic aids if transportation activities cannot be avoided during peak hours Generation of • Employ local labor force as far as possible Employment record Checking of Project Environment Complied. temporary • Comply with labor laws records locations Specialist of Engagement of employment DSISC and local labour as far and increase PMC as possible. in local revenue Occupational • Comply with all national, state and local • Site-specific Health • Checking of Project Daily visit by Environment Complied hazards which core labor law. and Safety (H&S) records locations construction Specialist of can arise • Develop and implement site-specific Plan • Visual supervisor of DSISC and Workman during work occupational health and Site-specific • Equipped first-aid inspection DSISC. PMC compensation for occupational health and safety (OHS) • stations; Weekly workers have been Plan and Supplementary H & S plan for • Medical insurance visit by obtained COVID 19 have been developed and coverage for workers Construction (Appendix III -4) implemented which included measures • Supplies of potable Manager, Visit First aid box such as: (a) excluding public from the site; drinking water; by available at all (b) maintaining social distancing for • Record of H&S Environment sites. protection from COVID 19 infection; (c) Orientation trainings Specialist and Potable drinking

197 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Monitored Method of Location of Date of Name of Compliance (As a minimum those Monitoring Monitoring Monitoring Person Who Status/ identified in the IEE Conducted Conducted Explanation should be monitored) the Monitoring ensuring all workers are provided with and • Personal protective Support water was not use personal protective equipment like Equipment Environment available at all helmet, gumboot, safety belt, gloves, nose • Daily worker health staff working sites. mask, face mask and ear plugs; (d) OHS check-up before Daily thermal Training and COVID 19 awareness H & S commencement of scanning for training for all site personnel; (e) work due to COVID19 labours before documented procedures to be followed for starting of works. all site activities including follow of SOP Toilet facilities not for COVID 19 as developed for the project available at working and H & S plan; and (f) documentation of sites. work-related accidents; Medical tie-up letter • Qualified first-aiders have been provided is available and at all times. Equipped first-aid stations medical check- up (with sufficient disinfectant) are easily done (Appendix III accessible throughout the site; -14) • Availability of Ambulance at work site; Partial use of PPE • WC policy has been received by the observed at contractor of the package (Appendix 15); Samsabad (Z-5), • Secure all installations from unauthorized Jambari (Z-7) and intrusion and accident risks; Haripur (Z-19) • Provide supplies of potable drinking water; Use of PPEs for • Provide clean eating areas where workers COVID 19 are not exposed to hazardous or noxious protection - noted substances; • Provide health and safety orientation training including COVID 19 risk and mitigation to all new workers to ensure that they are apprised of the basic site rules of work at the site, personal protective protection, and preventing injuring to fellow workers; • Provide visitor orientation if visitors to the site can gain access to areas where hazardous conditions or substances may be present. Ensure also that visitor/s do not enter hazard areas unescorted; • Ensured the visibility of workers through their use of high visibility vests when working in or walking through heavy

198 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Monitored Method of Location of Date of Name of Compliance (As a minimum those Monitoring Monitoring Monitoring Person Who Status/ identified in the IEE Conducted Conducted Explanation should be monitored) the Monitoring equipment operating areas; • Ensured moving equipment is outfitted with audible back-up alarms; • Mark and provide sign boards for hazardous areas such as energized electrical devices and lines, service rooms housing high voltage equipment, and areas for storage and disposal. Signage shall be in accordance with international standards and be well known to, and easily understood by workers, visitors, and the general public as appropriate; • Standard Operating Procedure (SOP) for the project and Supplementary H & S plan for COVID 19 prepared which cover, o General instruction to follow to prevent the spread of COVID-19 in construction workplace o Detail (step-by-step) work procedure to getting the workplace ready under COVID-19 situation o Worksite prevention practice at work site, office, during meeting, travelling, etc. o Precaution taken at workmen habitat/ camp o Control measures taken for deploying new workmen at site o Use of PPEs: face mask – hand gloves, maintaining social distancing, disinfection, requirement of awareness covered under the H & S plan. • (Separate H & S plan for COVID 19 as supplementary document developed and keep as standalone document to mitigate COVID 19 health risk) Health risks • Leave AC pipes in-situ untouched Decommissioned AC Site inspection Project Daily visit by Environment Complied. associated Pipes locations construction Specialist of No AC pipe is being

199 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Monitored Method of Location of Date of Name of Compliance (As a minimum those Monitoring Monitoring Monitoring Person Who Status/ identified in the IEE Conducted Conducted Explanation should be monitored) the Monitoring with AC pipes supervisor of DSISC and used. DSISC. PMC Weekly visit by Construction Manager, Visit by Environment Specialist and Support Environment staff Traffic • Restrict construction vehicle movements Accident register Review of Project Daily visit by Environment No pedestrian accidents and to defined access roads and demarcated documents locations construction Specialist of accident has been vehicle working areas (unless in the event of an supervisor of DSISC and recorded till date. collision with emergency) DSISC. PMC pedestrians • Enforce strict speed limit (20-30 kph) for Weekly Pipe line laying during material playing on unpaved roads, construction visit by work continued. and waste tracks Construction • Barricades and transportation • Night-time haulage will be by exception Manager, Visit caution tapes in only, as approved by the PIU to minimize by work areas, in driving risk and disturbance to Environment particular along the communities Specialist and pipelines were • Adopt standard and safe practices for Support found except some micro tunnelling Environment locations like • Temporary traffic control (e.g. flagmen) staff Kadambari pipe and signs will be provided where laying work. necessary to improve safety and provide TMP needs to be directions followed. • All drivers will undergo safety and training Trench have not • Public access to all areas where kept open after pipe construction works are on-going will be laying. Caution tape restricted through the use of barricading will be placed. and security personnel • Warning signs, blinkers will be attached to At Haripur OHSR the barricading to caution the public about site, trench was the hazards associated with the works, kept open without and presence of deep excavation caution tape. Complete • The period of time when the pipeline

200 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Monitored Method of Location of Date of Name of Compliance (As a minimum those Monitoring Monitoring Monitoring Person Who Status/ identified in the IEE Conducted Conducted Explanation should be monitored) the Monitoring trench is left open will be minimized barricading is through careful planning required • Control dust pollution – implement dust control measures as suggested under air Flagman observed quality section at Narasinghapur • Maintain regularly the vehicles and use of Jalpai Pipe line manufacturer-approved parts to minimize work. potentially serious accidents caused by equipment malfunction or premature failure. • Provide road signs and flag persons to warn of on-going trenching activities. Impact on • As far as possible located the camp site • Water and sanitation Site inspection Construction Daily visit by Environment Under compliance. work campus within the work sites; if any camp to be facilities for and review of camp construction Specialist of Work camp under and working established outside these, then select a employees. documents supervisor of DSISC and construction as per sites. camp site away from residential areas (at • Regular disposal of DSISC. PMC requirement and Temporary air least 100 m buffer shall be maintained) solid waste Weekly site condition and noise • Avoid tree cutting for setting up camp • Proper sanitization of visit by pollution from facilities work place Construction machine • Camp site shall not be located near (100 • Regular disinfection of Manager, Visit operation, m) water bodies, flood plains flood toilet by water pollution prone/low lying areas, or any ecologically, Environment from storage socially, archeologically sensitive areas Specialist and and use of • Separate the workers living areas and Support fuels, oils, material storage areas clearly with a Environment solvents, and fencing and separate entry and exit staff lubricants • Provide proper temporary accommodation with proper materials, adequate lighting Unsanitary and ventilation, appropriate facilities for and poor living winters and summers; ensure conditions conditions for of liveability at work camps are maintained workers at the highest standards possible at all times; • Consult PIU before locating project offices, sheds, and construction plants; • Minimize removal of vegetation and disallow cutting of trees • Ensure conditions of liveability at work camps are maintained at the highest

201 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Monitored Method of Location of Date of Name of Compliance (As a minimum those Monitoring Monitoring Monitoring Person Who Status/ identified in the IEE Conducted Conducted Explanation should be monitored) the Monitoring standards possible at all times; living quarters and construction camps shall be provided with standard materials (as far as possible to use portable ready to fit-in reusable cabins with proper ventilation); thatched huts, and facilities constructed with materials like GI sheets, tarpaulins, etc., shall not be allowed as accommodation for workers • Camp should be protected from COVID 19 health risk. All Health and safety procedure to follow for operation of camp (H & S plan for COVID 19 will be used as ref. document) during stay, cooking, eating, use of toilet- common space etc. • Self- hygiene, regular disinfection of entire camp and toilet, maintaining of social distancing to be continued for protection from COVID 19 infection • Unknown person not allowed within the camp • Camp shall be provided with proper drainage, there shall not be any water accumulation • Maintenance of hygienic environment at staying area, cooking area and toilet • Provide drinking water, water for other uses, and sanitation facilities for employees • Prohibit employees from cutting of trees for firewood; contractor should be providing proper facilities including cooking fuel (oil or gas; fire wood not allowed) • Train employees in the storage and handling of materials which can potentially cause soil contamination • Recover used oil and lubricants and reuse or remove from the site

202 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Monitored Method of Location of Date of Name of Compliance (As a minimum those Monitoring Monitoring Monitoring Person Who Status/ identified in the IEE Conducted Conducted Explanation should be monitored) the Monitoring • Manage solid waste according to the following preference hierarchy: reuse, recycling and disposal to designated areas; provide a compost pit for biodegradable waste, and non- biodegradable / recyclable waste shall be collected and sold in local market • Remove all wreckage, rubbish, or temporary structures which are no longer required • At the completion of work, camp area shall be cleaned and restored to pre- project conditions, and submit report to PIU; PIU to review and approve camp clearance and closure of work site There are no • Consult Archaeological Survey of India • Utility survey Review of Project Environment Complied protected (ASI) or West Bengal State Archaeology • Topographical survey documents locations Specialist of No archeological properties in Department to obtain an expert DSISC and structure observed the subproject assessment of the archaeological PMC within the working sites. potential of the site sites. However, in • Include state and local archaeological, case of cultural and historical authorities, and chance finds, interest groups in consultation forums as contractors will project stakeholders so that their expertise be required to can be made available. follow a • In case of chance finds, works must be protocol as stopped immediately until such time defined in the chance finds are cleared by experts mitigation measures. Unsatisfactory • Appointment of Environment, Health and • Appointment letter Review of records Safety person compliance to Safety (EHS) Supervisor to ensure EMP • Monitoring records appointed from EMP implementation contractor end, but • Timely submission of monitoring reports environment including pictures training is required on regular basis. Monitoring report submitted on monthly basis.

203 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Impacts Mitigation Measures Parameters Monitored Method of Location of Date of Name of Compliance (As a minimum those Monitoring Monitoring Monitoring Person Who Status/ identified in the IEE Conducted Conducted Explanation should be monitored) the Monitoring Damage due • Remove all spoils wreckage, rubbish, or • Stockpile Review of Project Daily visit by Environment Spoil Management to debris, temporary structures (such as buildings, Management documents and location construction Specialist of Plan has been spoils, excess shelters, and latrines) which are no longer • Spoil Management site inspection supervisor of DSISC and submitted for the construction required; and • Restoration of sites DSISC. PMC pipe laying work. materials • All excavated roads shall be reinstated to Weekly original condition. visit by No utilities affected • All disrupted utilities restored Construction during pipe laying • All affected structures Manager, Visit at village roads rehabilitated/compensated by • The area that previously housed the Environment Road restoration construction camp is to be checked for Specialist and after pipe laying spills of substances such as oil, paint, etc. Support work. and these shall be cleaned up. Environment • All hardened surfaces within the staff construction camp area shall be ripped, all imported materials removed, and the area shall be top soiled and re-grassed using the guidelines set out in the revegetation specification that forms part of this document. • The contractor must arrange the cancellation of all temporary services. • Request PIU to report in writing that worksites and camps have been vacated and restored to pre-project conditions before acceptance of work.

204 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

D. Site Specific Issues and Present Compliance Status

North 24 pgs

o Provision of office and toilet facility at Site.

36. It is mandatory requirement to provide an office and toilet facility at site for workers. Although in zone 6, zone 12 and zone 15 (OHR) of Haroa block have temporary site offices whereas zone 18, zone 14 and zone 17 of Haroa block has site offices in Chlorination building. In Zone 4 (OHR) and zone 13 of Bhangar II block and in WTP site have the site office facility available however, the site offices in Haroa and Bhangar were heavily damaged due to cyclone “Amphan” which are in need to be restored. In other sites of Haroa and Bhangar II Block site offices are not yet established. Toilet facility has been provided at all the sites but condition at zone 10 & 13 (OHR) of Bhangar II block and Zone 8 & 6 (OHR) of Haroa block were found unhygienic. Further, in order to avoid ingress of faecal sludge into groundwater, presently installed single pit latrines are being replaced with pre-fabricated bio-toilets in OHR sites in both Haroa as well as Bhangar II blocks.

Fig: Single pit latrine replaced with pre-fabricated bio-toilet at Zone -2: Nebutala Abad in Haroa o Provision of basic facilities at construction camps

37. The project requires proper hygienic living facility for the workers. While at most sites adequate arrangements have been made but in some sites like Zone 6 and 8 (OHR) of Haroa and Zone 13 & 15 (OHR) of Bhangar II block the condition was found unsatisfactory. Instruction has been given to contractors for improvement.

205 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Fig: Damp unhygienic living condition at Bhangar II block - Zone 15 (OHR) Site

o Use of PPEs e.g. safety harness, shoes, gloves and goggle while at work.

38. Although the usage of PPEs at work has improved but still in some sites, especially during pipeline activities, violations were observed. Violations such as non-use of safety shoes, gloves, etc. while digging of trenches may lead to major accidents.

Fig: Satisfactory living condition at Zone 14 (OHR) Site of Haroa Block

Fig: Bhangar II Zone 15 pipeline site – Working Fig: Haroa Zone 12 – Working with PPEs without PPEs o Barricading and caution tapes along pipelines.

39. While barricading and installation of caution tapes is a mandatory requirement during laying of pipelines, in many instances such practices were not seen earlier at sites. However, upon constant supervision and awareness campaigning by DSISC, good practices are being seen at most sites. The photographs below depict the positive change.

206 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Fig: Pipelaying at Bhangar II Block (Zone 17) Fig: Pipelaying at Haroa Block (Zone 8) o Management of wastewater and pit latrines at Sites

40. The pit latrines installed at Zone 15 of Bhangar – II and, Zone 6 and 8 of Haroa Block may cause faecal coliform contamination to groundwater. These pit latrines should at least be replaced with systems promoted under Swachh Bharat or be removed from site.

41. As noted above, in order to avoid ingress of faecal sludge into groundwater, presently installed single pit latrines are being replaced with pre-fabricated bio-toilets in OHR sites in both Haroa as well as Bhangar II blocks

o Camp located within school in Zone 8 of Haroa Block and Zone 15 of Bhangar II Block.

42. Labour camps located inside schools pose risk to the children in terms of social distancing, high noise and accidents. However, upon DSISC’s intervention and strict instructions from PIU, these camps have been shifted from schools.

Fig: Camp inside Raikha school in zone 8, Haroa Fig: Camp inside school at Zone 15 in Bhangar II

207 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Bankura 43. Few non complied site- specific issues and compliance status as recorded during report period are given below. • Provision of site office, labour rest area, drinking water and toilet facilities at site

44. Provision of site office, labour rest area, drinking water availability and toilet facility are mandatory requirement as per EMP which often not present during initial phases of site establishment; however, after regular monitoring by DSISC team these are improved a lot. Before After

Proper site office not yet established Site office with basic facilities established (BK/02A)

Good Practice:

Drinking water, shaded area provided at pipe laying site (BK/02A)

208 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Bio-toilet installed at different OHSR sites

• Provision of basic facilities at labor camp

45. Provision of basic facilities like bed, cooking gas, electricity, clean eating area etc. are mandatory requirement in labour hutment as per EMP. These are often missing at OHSR sites. Only few locations have all such facilities. Portable cabins are arranged for labour hutment at some fixed location like Chenchuriya (BK/02B), Danga (BK/02A) etc. after maintaining the recommended physical distancing.

Bed has provided in labour hutment Cooking gas has provided in labour hutment (BK/03) (BK/03)

Portable cabin with light, fan, locker facility Kitchen facility under construction (BK/02B) (BK/02B)

209 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

• Housekeeping at construction site, labour camp area

46. Maintenance of clean working area and labour camp are important requirements to avoid many types of accidents. Before After

Spoil dumped beside the road (BK/04) Proper housekeeping done

No proper housekeeping at temporary labour Propoer housekeeping done camp at Fulmati (BK/02B)

• Barricading and caution tape at pipe laying and other construction sites

47. Barricading and installation of caution tapes is a mandatory requirement during pipe laying work and around deep excavated area which were sometimes absent at sites. Compliance done after supervision by DSISC team. Before After

Pipelaying work ongoing without proper Proper barricading given with GR number barricading (BK/02A) displayed at pipe laying site

210 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Site boundary and caution board absent at Site boundary and caution signage like “deep intake site (BK/03) water” etc. are provided

Proper barricading absent around OHSR site Barricading done properly (BK/04)

• Road restoration after pipe laying work

48. Back filling after pipe laying work usually done at the same day, while road restoration work done few days after natural compaction. Before After

Uncovered Pipe laying site (BK/04) Dated- Road restoration done properly, dated 15.07.20 14.07.20

211 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

• Electrical and Fire safety at construction site

49. “Electrical and fire safety”, important safety aspects which are often undermined at construction site. Before After

Rubbur mat absent beneath electrical connection Rubber mat given beneath the elcetrical Intake site(BK/03) connection

• General safety measures

50. Various other safety issues are noted at site for which the necessary compliance picture is illustrated. Before After

Water sample collection from Mukutmanipur Water sample collection at same location with reservoir without taking any safety measures taking proper safety measures (BK/01)

Assembly point located at road side, no emergency Assembly ponit shifted with site boundary. contact detail at Intake point (BK/03) Emergency contact details are displayed.

212 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

East Medinipur

Package: EM/01

• Barricading or caution tape along the pipe laying trench

51. Some good practices like use of PPEs and hard barricade along the trench have seen for Package EM/01. Although hard barricading was not observed along the trench at all work locations, but after necessary instruction to contractor by DSISC, they arranged hard barricading on very next day.

Date of observation: 14-10-2020 Date of compliance: 15-10-2020

• Use of PPEs by workers

52. Use of PPEs by workers is necessary to avoid the risks. But due to lack of awareness some workers not using the PPE during the work. Intensive training is required explaining importance of use of PPEs for personal safety

• No proper material stacking

53. No proper material stacking was observed at intake substation site. But after necessary instruction construction contractor complied this issue.

213 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Date of observation:21-10-2020 Date of compliance: 23-10-2020

Package: EM/02

• Provision of toilet facility at site

54. It is mandatory requirement to provide toilet facility at site for workers. But till report period no toilet facilities has been provided at sites where construction work has started.

• Insufficient Fire safety measure

55. At Birulia site fire extinguisher was not in working condition and extinguisher pressure was dropped and hose pipe was not attached.

Date of observation : 07.10.2020 Date of compliance : 08.10.2020

• Use of PPEs and barricading or caution tape along the pipe laying trench

56. Although use of PPEs and barricading is mandatory during pipe laying work, but at some places this practice not followed. Instruction was given to contractors for improvement in use of PPEs and placement of barricades.

214 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Excavation without barricade and PPEs Use of caution tape along with trench

57. Based on the foregoing observations, findings and environmental monitoring carried out from May 2020 to October 2020, it may be concluded that the subprojects have been implemented in partial compliance of the required environmental safeguards. Overall compliance level is shown in Table 15 below.

Table 15: Overall Compliance with Environmental Management Plan No. Sub-project Name EMP Part of EMP Being Status of Action Proposed and Contract Implemented Implementation Additional Measures Documents (Y/N) (Excellent/Satisfactory Required (Y/N) / Partially Satisfactory, Below Satisfactory) North 24 Pgs 1 Package - • PPE usage and WBDWSIP/DWW/N discharge of waste water CB/N24P/01/2017- in local drain is an issue 18: Bulk water in this sub project. supply • Soil debris are needed to Y Y Satisfactory be transported in separate location. • Drainage should be upgraded before next monsoon 2 Package - • Improvement of facilities WBDWSIP/DWW/N in Construction Camps, CB/N24P/02A/2017 especially sleeping -18: Haroa Block arrangements, toilet facilities, provision of drinking water and fuel for cooking, access, solid Y Y Partially Satisfactory waste and wastewater management • Present labour accommodation at Zone 8 is very poor and should be improved immediately.

215 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

No. Sub-project Name EMP Part of EMP Being Status of Action Proposed and Contract Implemented Implementation Additional Measures Documents (Y/N) (Excellent/Satisfactory Required (Y/N) / Partially Satisfactory, Below Satisfactory) • Missing PPE, particularly use of working shoes, ear plug, goggles (Haroa – Zone 6 and Zone 8). Complete use of PPEs is required • In Haroa zone 6 during site visit black patch was found in the soil, formed by spilling used/spent oil in the ground. Need to educate labours about environmental concerns due to spills. • Barricade need to be placed at all working sites • Electrical safety needs to be improved 3 Package - • Provision should be WBDWSIP/DWW/N made for site office and CB/N24P/02B/2017 bio-toilets at all work -18: Bhangar - II sites Block • Improvement of facilities in Construction Camps, especially sleeping arrangements, toilet facilities, housekeeping, provision of drinking water and fuel for cooking, solid waste and wastewater management • Management of toilet waste at camp sites, use Y Y Partially Satisfactory of pit latrines are serious concern (Bhangar II – Zone 13 and 15). The pit latrines installed may cause faecal coliform contamination to groundwater and should be replaced with better, approved systems. It may be noted, bio-toilet has already been installed at Zone 13. Such arrangement should also be made at all other sites. • Use of PPEs e.g. safety

216 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

No. Sub-project Name EMP Part of EMP Being Status of Action Proposed and Contract Implemented Implementation Additional Measures Documents (Y/N) (Excellent/Satisfactory Required (Y/N) / Partially Satisfactory, Below Satisfactory) shoes and goggles should be ensured at all sites especially for activities like concrete braking, trenching, etc. • Electrical safety needs to be improved Bankura 4 Package - • Only the preliminary WBDWSIP/DWW/N activities started in the CB/BK/01/2017-18- package. Bulk water supply Y Y Satisfactory • Site office and labour Indpur and camp establishment Taldangra continued. Laboratory set up not yet done. 5 Package - • Project office and WBDWSIP/DWW/N laboratory set up at CB/ BK/02A/2018- Indpur - completed. 19- Water supply • Site office established at distribution all OHSR locations Indpur block where construction work has initiated. But, Installation of bio- toilet not yet done at 7 OHSR zone (1,2,3, 10, 11, 18 and 20). Immediate installation of bio-toilet is required • Facilities in the construction camps, especially sleeping Y Y Satisfactory arrangements, toilet facilities, provision of drinking water and fuel for cooking, waste and wastewater management needs to be arranged at IBPS/GLSR site at Raghunathpur • Project information display board, emergency contact details and grievance redressal board available at site. Needs to be maintained for all working sites.

217 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

No. Sub-project Name EMP Part of EMP Being Status of Action Proposed and Contract Implemented Implementation Additional Measures Documents (Y/N) (Excellent/Satisfactory Required (Y/N) / Partially Satisfactory, Below Satisfactory) 6 Package - • Project office and WBDWSIP/DWW/N laboratory set up at CB/BK/02B/2018- Taldangra - completed. 19- Water supply • Site office under distribution construction at zone 7, Taldangra block 11, 13, 23 and 24. • Installation of bio- toilet not yet done at zone 7, 11, 13, 23 and 24. • Facilities in the construction camps, especially sleeping arrangements, toilet Y Y Satisfactory facilities, provision of drinking water and fuel for cooking, waste and wastewater management needs to be arranged at IBPS/GLSR site at Chenchuriya. • Project information display board, emergency contact details and grievance redressal board available at site. Needs to be maintained for all working sites. 7 Package - • Activities are ongoing at WBDWSIP/DWW/N intake and pipe laying CB/BK/03/2018-19- sites with proper safety Bulk water supply arrangement. Mejhia and • Construction camp, Gangajalghati labour hutment with all Y Y Satisfactory Blocks facilities established at WTP and Intake locations. Maintenance of all safety requirements at all work sites as per EMP 8 Package - • Project office and WBDWSIP/DWW/N laboratory set up at CB/BK/04/2018-19 Rangamati - completed. Water supply • Site office and distribution installation of bio- toilet Y Y Satisfactory Mejhia and under construction at Gangajalghati zone 3, 8, 12 and 32. Blocks Complete installation is required • Project information

218 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

No. Sub-project Name EMP Part of EMP Being Status of Action Proposed and Contract Implemented Implementation Additional Measures Documents (Y/N) (Excellent/Satisfactory Required (Y/N) / Partially Satisfactory, Below Satisfactory) display board, emergency contact details and grievance redressal board available at site. Needs to be maintained for all working sites.

East Medinipur 9 Package - • Hard barricading was WBDWSIP/DWW/I observed at raw water CB/EM/01/2018-19 rising main i.e. Intake to – Bulk water Ganjanarayanpur. supply Sometime barricade was missing • Labor camp need to be Y Y Satisfactory constructed as soon as possible. • Some places like at WTP labours not using safety shoes. Complete use of PPEs needs to be ensured. 10 Package - • Provision should be WBDWSIP/DWW/I made for site office and CB/EM/02/2018- toilets at all work sites. 19- Water supply • Gender specific toilet distribution facilities need to Nandigram I and II arranged at all working blocks sites. • Barricading was seen at some of the pipe laying work areas. It needs to be placed at all excavated areas. • GRM Board and Y Y Partially Satisfactory Emergency Contact board need to be displayed at sites. • Labour camp need to be constructed as soon as possible. • Missing of PPE, particularly safety shoes, (Nandigram I – Zone 05).. Complete use of PPEs e.g. safety shoes and goggles should be ensured at all sites. • Missing caution tape at

219 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

No. Sub-project Name EMP Part of EMP Being Status of Action Proposed and Contract Implemented Implementation Additional Measures Documents (Y/N) (Excellent/Satisfactory Required (Y/N) / Partially Satisfactory, Below Satisfactory) Kodambari Pipe laying work. Instruction was given to arrange caution tape.as per requirement • Electrical safety arrangement needs to be improved

E. Grievance Redressal Mechanism

58. A common Grievance redressal mechanism (GRM) is placed to address social, environmental, or any other project and/or subproject related grievances. The GRM has been developed in consultation with stakeholders. A public awareness campaign conducted to ensure that awareness of the project and its grievance redress procedures is generated. The campaign ensured that the poor, vulnerable, and others are made aware of grievance redress procedures and entitlements according to the project entitlement matrix, and PMU and concerned PIUs responsible for addressing their grievances.

59. GRM consists of the following three tiers, one tier at project level and two beyond project level, as shown in Figure 8. Each tier identifies the persons responsible for addressing grievances and provides a time limit for this.

o For the project level GRM, a Grievance Redress Cell established at PIU; the safeguards officers (Assistant Engineer and Junior Engineer of PIU) of the ESSU PIU, supported by the social safeguards specialist of DSICS is responsible for conducting periodic community meetings with affected communities to understand their concerns and help them through the process of grievance redressal including translating the complaints into Bengali or English, recording and registering grievances of non-literate affected persons and explaining the process of grievance redress mechanism.

o All expedient and minor grievances is resolved at field level; should the PIU fail to resolve any grievance within the stipulated time period, the PMU will be consulted and suggested actions by PMU taken by PIU with DSISC support, within specified time. PIU is also be responsible for follow-through for each grievance, periodic information dissemination to complainants on the status of their grievance and recording their feedback (satisfaction/dissatisfaction and suggestions). In the event that certain grievances cannot be resolved at project level, they will be referred to the District Steering Committee (DSC), which will also act as grievance redress committee (GRC), particularly in matters related to land purchase/acquisition, payment of compensation, environmental pollution etc. Any higher than district level inter-departmental coordination or grievance redress required will be referred to the state level Steering Committee.

60. The GRM aims to provide a time-bound and transparent mechanism to voice and resolve social and environmental concerns linked to the project. All grievances – major or minor,

220 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

is registered. In case of grievances that are immediate and urgent in the perception of the complainant, the contractor, and supervision personnel from the PIU supported by DSISC will try to successfully resolve them in consultation with the Member, Panchayat and the Gram Panchayat Pradhan. In case of larger issues, they will seek the advice and assistance of the Superintending Engineer PIU. Grievances not redressed through this process within/at the project level within stipulated time period will be referred to the DSC/GRC.

61. The DSC set up to monitor project implementation in each district. In its role as a GRC, the DSC will meet every month (if there are pending, registered grievances), determine the merit of each grievance, and resolve grievances within specified time upon receiving the complaint-failing which the grievance will be addressed by the state-level steering committee. The steering committee will resolve escalated/unresolved grievances received. Grievances remaining unresolved by steering committee may be referred by affected persons to appropriate courts of law. The GRC continue to function throughout the project duration.

62. An aggrieved person shall have access to the country's legal system at any stage, and accessing the country's legal system can run parallel to accessing the GRM and is not dependent on the negative outcome of the GRM.

Figure 8: Grievance Redress Mechanism

221 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Composition of the Grievance Redress Committee

63. The DSC, acting as GRC have District Magistrate (Chairperson), Superintending Engineer, PIU as Member Secretary, Additional Executive Officer, Zilla Parishad, Assistant (Social and Environmental) Safeguard Officers of the Environment and Social Safeguard Units (ESSU) of the PIU, Institutional Support and Capacity Building Officer, PIU, Block Development Officers from respective blocks, and representatives from the affected village panchayat and / or community, if any, eminent citizens, CBOs and NGOs.

64. The DSC/GRC must have a minimum of two women members. In case of any indigenous people impacts in future subprojects, the DSC/GRC must have representation of the affected indigenous people community, including at least one female indigenous person, the chief of the tribe or a member of the tribal council as traditional arbitrator (to ensure that traditional grievance redress systems are integrated) and an NGO working with indigenous people groups.

65. The State level Steering Committee include Chief Secretary, as chair, Principal Secretary/Additional Chief Secretary, PHED, Principal Secretary, Panchayat and Rural Development, Principal Secretary, Finance, Principal Secretary, Irrigation and Waterways Development Department, Principal Secretary, Public Works Department, Engineering in Chief, PHED, Member Secretary, and Others as invitees.

Areas of Jurisdiction

66. The areas of jurisdiction of the district level GRC, headed by the District Magistrate, will be (i) all locations or sites within the district where subproject facilities are proposed or being implemented, or (ii) their areas of influence within the district. The state-level steering committee will have jurisdictional authority across the state (i.e., areas of influence of subproject facilities beyond district boundaries, if any).

Consultation Arrangements

67. Consultations include regular group meetings and discussions by the social safeguard personnel of DSISC and PIUs with affected persons, at least twice during resettlement plan preparation. During the first year of project implementation, such meetings take place on a quarterly basis, while in subsequent years they will be held at least twice a year. The consultation arrangements thus envisaged are intended to address both general and/or specific individual grievances through a participatory approach. The consultative process is meant to be flexible to provide timely mitigation of grievances of the affected persons.

Recordkeeping

68. Records of all grievances received, including contact details of complainant, date the complaint was received, nature of grievance, agreed corrective actions and the date these were affected and final outcome will be kept by PIU (with the support of DSISC) and submitted to PMU

Information Dissemination Methods of the Grievance Redress Mechanism

69. The PIU, assisted by DSISC responsible for information dissemination to affected persons on grievance redressal procedure. Gram Panchayat/coverage area/affected area-wide public awareness campaigns ensure that awareness on grievance redress procedures is

222 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

generated through the consultation and participation plan. Public awareness campaign will be conducted to ensure that awareness on the project and its grievance redress procedures is generated. The PIU safeguard officers (environment and social) assisted by DSISC safeguards specialists with information/collateral/awareness material etc. and in conducting project awareness campaigns. The campaign ensures that the poor, vulnerable and others are made aware of grievance redress procedures and entitlements per agreed entitlement matrix including whom to contact and when, where/ how to register grievance, various stages of grievance redress process, time likely to be taken for redressal of minor and major grievances, etc. Grievances received and responses provided be documented and reported back to the affected persons. The number of grievances recorded and resolved and the outcomes will be displayed/disclosed in the PMU and PIU offices, Gram Panchayat/concerned local panchayat notice boards and on the web, as well as reported in the semi-annual environmental and social monitoring reports to be submitted to ADB.

70. Periodic review and documentation of lessons learned. The PMU safeguards and gender cell periodically review the functioning of the GRM and record information on the effectiveness of the mechanism, especially on the PIU’s ability to prevent and address grievances.

71. Costs. All costs involved in resolving the complaints (meetings, consultations, communication and reporting/information dissemination) be borne by the PMU. Cost estimates for grievance redress are included in resettlement cost estimates.

72. Till report period State level and district level steering committee have been established. Also, PMU, PIU and Gram panchyat level GRC notification done for North 24 pgs, Bankura and East Medinipur. All Notifications related to Grievance Redressal Committee are given in Appendix I - 17 (North 24 pgs), Appendix II - 15 (Bankura) and Appendix III - 15 (East Medinipur).

73. During the reporting period District Co-ordination and DSC meeting for East Medinipur was conducted on 22nd September 2020 and 13th July, 2020 regarding components and major constrains of this project like permission of land, NH 116B, irrigation, state highway etc. The minutes of the meeting has been appended as Appendix III -15.

74. Grievance Registration Form in local language as proposed for the project is also presented in Appendix I - 18, II - 16 and III - 16. Sample filled format is also shown in Appendix I - 18.

75. Grievance Redressal Register is maintained at each of the package working sites.

76. Complaints Received during the Reporting Period from North 24 pgs packages are summarized below

Table 16A: Summary of Grievance Received during May 2020 to October 2020- North 24 pgs Package name Total No of Nature of the Issue Minimum Time Maximum Complaints/ Complaint Resolved/ Taken to Time Taken enquiry Not Resolved Resolve the to resolve Recorded Issue the Issue 02A: Haroa 1 Contractor’s Yes Within Same Maximum 1 safety issues Day Day was

223 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

taken 02B: Bhangar II 8 Road restoration Yes Within 2-3 Maximum 7 problem, Pipe not Days days were laid, local issues, taken to problems, utility resolve issue. affected, regarding Pond Some issues restoration are not resolved but under the process of screening and reviewing.

Table 16B: Summary of Grievance Received during May 2020 to October 2020 - Bankura Package name Total No of Nature of the Issue Minimum Time Maximum Complaints/ Complaint Resolved/ Taken to Time Taken enquiry Not Resolved Resolve the to resolve Recorded Issue the Issue 02A: Indpur 1 Construction Yes Around 90% 2 days distribution material stacking issues are on road solved Within Same Day 02B: Taldangra Nil - - - - distribution 03: WTP & Nil - - - - Intake 04: Mejhia- 2 Access issue Yes Around 90% 2 days Gangajalghati (HDPE pipe issues are distribution placed in front of solved Within house) Same Day Soil dumping (Excavated earth dumped beside the road) 77. There are no grievances recorded for East Medinipur packages.

78. Details of complaints received during report period and resolved status attached as Appendix I - 19 (North 24 pgs) and Appendix II - 17 (Bankura). Complaints are mostly related to,

✓ Non laying of pipes at few locations. Non coverage of water supply scheme at few locations ✓ Improper material storage ✓ Dumping of soil beside the road- access problem ✓ Problem related to public access ✓ Affecting existing utility during pipe laying ✓ Non-use of PPEs by workers ✓ Road restoration at earliest

79. Issues are resolved mostly by site supervisor engineer and safety officer of contractor within same day of complaints received.

224 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

F. Training, Workshop, Public consultation and Focus group discussion

80. As per approved IEEs, consultations and disclosure will be a continuous process throughout project implementation involving public consultations and focus group discussions. Informal consultations were carried out with local people, pedestrian, etc. Field level public consultation as conducted by contractor is attached as Appendix I - 20 (North 24 pgs), Appendix II - 18 (Bankura) and III - 18 (East Medinipur).

81. The indicative schedule for consultations and disclosure is presented in Table 17. Table 17: Indicative Schedule for Consultations Type of Consultation/ Target Date Location Target Responsible Disclosure Participants Person and Source of Funds Local level Weekly – to be At all General public, Construction consultation continued construction shop keepers, supervisor, locations pedestrian Environment & safety population officer of contractor Project budget – continuous process Consultation – safety During At WBDWSIP Supervisor Construction issues, implementation November office and Engineer, PIU Manager, of EMP 2020 to April project site Engineer, all Environment 2021 and office safety and specialist of DSISC continued environment and PMC staff of contractors 82. Field level training , awareness program on safety and environment has been arranged for contractors, supervisors by DSISC’s Environment Specialist on regular basis.

83. There are series of informal discussions by the DSISC engineering Consultants with PIU mainly on understanding current situation and optimum design to be adopted in order to attain the safeguard objectives.

84. During report period limited consultation, FGD has been carried out due to COVID 19 situation. Summary of trainings, workshops, public consultation and FGD arranged in all the project districts are shown below.

85. Summary of consultation for North 24 pgs package shown below and attached sample copy in Appendix I - 22. Due to COVID 19 pandemic situation limited FGD has been carried out at project site.

Table 18A: Summary of Details of Consultations during May 2020 – October 2020- North 24 pgs Package Date of Type of Total No of No. of Details of the Meeting Name and Training Consultation Participant Female meeting Conductor Site /Consultati Participant Location on/FGD Package No. WBDWSIP/ DWW/ NCB/ N-24P/ 02A; Haroa Z-18 14/08/2020 Public 10 - Project Beneficiation DSISC Gopalpur Consultation and Awareness Z-12 23/09/2020 Training and 13 - Dengue, Malaria and Contractor

225 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Package Date of Type of Total No of No. of Details of the Meeting Name and Training Consultation Participant Female meeting Conductor Site /Consultati Participant Location on/FGD Parchandpur Group COVID-19 awareness and DSISC Discussion Z-14 23/09/2020 Training and 23 - Dengue, Malaria and DSISC and Khalisadi induction COVID-19 awareness Contractor Z-15 09/09/2020 Training and 16 - Dengue, Malaria and DSISC and Jhinkia Group COVID-19 awareness Contractor Discussion Z-17 09/09/2020 Training 17 - HIV/AIDS Awareness DSISC Shalipur Programme including COVID-19 Z-5 29/09/2020 Public 20 13 Project Beneficiation DSISC Tegharia Consultation and Awareness Z-8 14/10/2020 Focused 11 - Environmental DSISC and Bantosha Group Safeguard: EMP contractor Discussion Implementation, Health and Safety Training including COVID-19 Z-06 24/10/2020 Public 10 - Benefit and Impact of DSISC Radhanagar Meeting the Project, GRM information Z-6 OHR 01/10/2020 Public 29 26 Project Beneficiation DSISC Puratan Consultation and Awareness Kamarganti Package No. WBDWSIP/ DWW/ NCB/ N-24P/ 02B; Bhangar II Z-01 Pipeline 15/10/2020 Training and 8 - Pipe Trench Contractor Dharamtala Induction Excavation, Pipeline Pachuria joining Z-06 Pipeline 01/10/2020 Training and 13 Trench Cutting and Contractor Syamnagar Induction Excavation Z-13 OHR 17/10/2020 Training and 7 Chlorination Tank Contractor Baniara Induction and COVID 19 Z-4 OHR 17/10/2020 Training and 14 Work at height, Contractor Swastayan Induction COVID-19 Gachi Z-12 OHR 10/10/2020 Toolbox 8 Work at Height and Contractor Bankachua Training and COVID-19 Induction Awareness Z-8 Pipeline 14/10/2020 Training and 8 COVID-19, Dengue, DSISC Uttar Awareness Malaria, AIDS Kashipur awareness Z-06 Pipeline 09/10/2020 Training and 12 Project Beneficiation DSISC Shyamnagar Awareness and COVID 19 awareness Z-10 OHR 14/10/2020 Training and 12 - Dengue, Malaria and DSISC Shanpukuria Awareness COVID 19 awareness Z-10 OHR 15/10/2020 Public 41 25 Project Beneficiation DSISC Shanpukuria Consultation and Awareness Z- 4 OHR 09/10/2020 Training and 10 - Dengue, Malaria, DSISC Swastayan Awareness COVID-19 awareness Gachi

226 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Package Date of Type of Total No of No. of Details of the Meeting Name and Training Consultation Participant Female meeting Conductor Site /Consultati Participant Location on/FGD Z-15 OHR 24/09/2020 Training and 12 - Dengue, Malaria and DSISC Kachua Awareness COVID-19 awareness Z-17 Pipeline 24/09/2020 Training and 18 - Dengue, Malaria and DSISC Bhogali Awareness COVID- 19 awareness Z-7 Pipeline 15/10/2020 Public 41 25 Project Beneficiation DSISC Jaynagar Consultation and Awareness Package No. WBDWSIP/ DWW/ NCB/ N-24P/ 01; WTP, Rajarhat WTP 04/08/2020 Tool box 10 - COVID 19 Contractor Rajarhat Training and awareness, Work at and DSISC Induction height WTP 25/09/2020 Public 7 2 Project Beneficiation, DSISC and Rajarhat Consultation COVID 19 awareness Contractor WTP 01/10/2020 Tool box 8 - Work at height, Contractor Rajarhat training and COVID 19 awareness Induction WTP 4/10/2020 Training about 7 - COVID 19 training, Contractor Rajarhat COVID 19 Piling work and tool box procedure, work at training height WTP 7/10/2020 Tool box 10 - Work at height, PPE Contractor Rajarhat training and usefulness, COVID Induction 19 WTP 11/10/2020 Induction and 9 - COVID 19 safety Contractor Rajarhat COVID 19 procedure, Work in training height WTP 14/10/2020 Induction and 11 - COVID 19 Contractor Rajarhat COVID 19 awareness, Work at awareness height WTP 17/10/2020 Tool box 7 - Malaria, Dengue, Contractor Rajarhat training and Cleanliness, Work at Induction height WTP 23/10/2020 Training about 10 - Work at height, PPE Contractor Rajarhat COVID 19 usefulness, COVID and tool box 19 training WTP 29/10/2020 Induction and 8 - COVID 19 Contractor Rajarhat COVID 19 awareness, work at awareness height

227 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Table 18B: Summary of Consultation, meeting for Bankura Packages during May 2020 – October 2020 Package Name Date of Type of Total No of No. of Female Details of the meeting Meeting Conductor and Site Location Training Consultation Participant Participant /Consultation Training cum Workshop organized by DSISC, PMC

All Packages 09.07.20 Workshop 07 01 Environmental Safeguard: DSISC EMP Implementation, Health and Safety Training All Packages 25.08.20 Workshop 07 01 Awareness program and DSISC documentation requirement for COVID-19 compliance All packages 26.08.20 Meeting - - Implementation of COVID-19 PMU, PMC and DSISC Protocol All packages 15.09.20 Workshop - - HSE Workshop PMC All Packages 25.09.20 Workshop 09 01 Environmental safeguard DSISC documentation requirement BK 02A and BK 19.10.20 Meeting 09 01 To resolve field related DSISC 02B safeguard issues Public Consultation organized by Contractor

BK 02A Continuous Public - - Benefit and Impact of the Contractor (Siromanipur, consultation Project, GRM information, to Chaukighata, register suggestion and Bholarkhap, complain (if any). Raghunathpur, Golakpur, Brahmandiha) BK 03 Continuous Public - - Contractor (Kalgora pipe consultation laying site, Maliyapara Intake site) BK 04 Continuous Public - - Contractor (Kallapur, consultation Haribhanga, Arbat, Purbator, Machaparulia, Gobindadham)

228 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

86. At East Medinipur project site during this report period, FGD has been conducted at following 4 places (Appendix III - 20). It is recorded that 38% female participants attended those discussion. Summary shows in the Table below. Due to COVID 19 pandemic situation limited meeting has been conducted during report period. Table 18C: Focus Group discussion at East Medinipur Sl no Location Date of Total no of No of Female Issue Discussed Consultation Participants Participants 1. Purbo 03.08.2020 60 15 • Objectives of the WBDWSIP (EM) and its implementation Byabottarhat plan. • Pipe laying rout of CWRM and Intake point. Community • Land Issues at WTP and OHR location. hall of • Stakeholder’s participation at different stages of the project. Nandakumar • Scope of local employment. BDO Office • Tree felling from Intake to Ganjanarayanpur. • Environmental issue like water scarcity problem, salinity problem in drinking water. 2. Purbo 18.08.2020 23 5 • MS Pipe laying route of CWRM from Mirpur to Byabottarhat 24.08.2020 14 4 Ganjanarayanpur. 08.09.2020 14 2 • People’s participation at pipe laying stages. • Affected Structure and trees. • Adequate Safeguard measures. • Effect on environment for tree cutting. • Effect on water due to construction activities. • Quality of drinking water. • Local people also agreed 3. Madhya 15.10.2020 40 5 • Public consultation before laying of DI pipe Mangalchak • Brief discussion on total project ICDS Centre • Local people problem regarding this activity 4. Nandigram II 10.09.2020 13 7 • Consultation regarding some big trees and Monosha Along the Mandir Clear water • The primary source of drinking water if from tube wells and main submersible pumps (ground water). • The participants reckon that the proposed water supply project will solve their problem permanently. Treated surface water will not only be good for their health but at the same time they will be able to save money indirectly. Health related expenses due to water will be reduced which will indirectly increase their savings. Cost for cooking will also reduce due to lesser consumption of fuel.

229 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Table 18D: Orientation Training Programme- East Medinipur during May 2020- October 2020 Sl no Location No of Date Discussion Participants 1. Mirpur 10 7th October, 2020 • Mainly discussed importance of First aid at working sites. • Handholding Training on the basics of First Aid • The participants were imparted handholding training and orientation on how to provide safety 2. Virtual 11 14th October,2020 • Virtual orientation and Audit program have been arranged by PMC orientation with DSISC and Contractor for both the packages. and audit • Discussion about labor camp and contractor assured that they will program complete the labour camp within December,2020 • Dr. Ardhendu Mitra, Environment Spl of PMC also guide us regarding COVID19 measures and its checklist. • GRM board need to be displayed at site. 3. Virtual 15th September, • Discussed why Occupational health and safety is important in meeting on 2020 working places Occupational • Requirement of work permit Health and • Life jacket for intake required. Safety • COVID19 awareness program. Training with PMC 4. First Aid 12 7th October, 2020 • Mainly discussed importance of First aid at working sites. training • Handholding Training on the basics of First Aid program • The participants were imparted handholding training and orientation on how to provide 5. First Aid 10 29th September, • Mainly discussed importance of First aid at working sites. training 2020 • Handholding Training on the basics of First Aid program • The participants were imparted handholding training and orientation on how to provide

230 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

87. Appendix I - 14 indicates training components on environment, Health and safety issues, including awareness programme for HIV/ AIDS as conducted by North 24 pgs DSISC at project sites. Sample internal training documents as submitted by contractors are included in this appendix. Till report period official training is pending for Bankura DSISC, only field level instruction and awareness cum review meeting has been provided for contractors (Appendix II - 19). First aid training has been conducted by DSISC, East Medinipur for both the packages and sample copy has appended as Appendix III - 12 and HIV/AIDS awareness training pending due to COVID19 pandemic. It will be done shortly and incorporated in next SEMR.

88. During the report period Environment and Social safeguard related Audit has been conducted by PMC at North 24 pgs PMU/ PMC office, through virtual system for East Medinipur PIU & DSISC and Bankura PIU & DSISC. PIU staffs, contractor’s project manager, safety officers, DSISC staff attended that Audit Program. Review meeting cum orientation program on environment safeguard for DSISC, PIU and contractors are also conducted on regular basis. Appendix I - 21, II - 19 and III - 19 shows note on Technical Audit for North 24 pgs, Bankura and East Medinipur districts, respectively.

V. APPROACH AND METHODOLOGY FOR ENVIRONMENTAL MONITORING OF THE PROJECT

89. For effective monitoring, selected environmental parameters have been identified as indicators which will be qualitatively and quantitatively measured and compared over a period of time in order to assess/ensure the compliance of Environment Management Plan (EMP). The environmental performance indicators are physical, biological and social characteristics identified as most important in affecting the environment at critical locations all along the subproject locations. The parameters identified as performance indicators are: o Air, noise and water quality o Compliance to EMP o Compliance to local/state/national environmental regulations

90. Field level monitoring comprises monitoring of environmental parameters like air quality, noise level and water quality. These are monitored for understanding base line conditions at project locations and during construction monitoring for understanding level of impact on environment (in respect to those parameters) from project activity during implementation of the project. Monitoring is conducted as per monitoring plan of approved IEE.

91. Field level monitoring also carried out during pre-construction, construction and operation phases for understanding degree of impacts and mitigation measures. Corrective action plan and target date for effective implementation of mitigation measures planned accordingly. Site Environment Management Plan is the base document for implementation of EMP and application of corrective measures. This field level monitoring is continuous process and reported through weekly, monthly checklist.

92. Monitoring of applicability of local/state/national environmental regulations in respect to project activity and locations is also required for smooth progress of the project. For that site verification and desk review is essential. Starting from pre-construction to construction – operation phases screening of work areas, work components under the national, state and local statutory rules and regulations is necessary.

231 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

VI. MONITORING OF ENVIRONMENTAL IMPACTS ON PROJECT SURROUNDINGS

A. Brief discussion on the basis for monitoring

93. In addition to desk reviews and site inspections, monitoring of selected environmental parameters have been conducted during the reporting period. The frequencies of the environmental monitoring activities are commensurate to the type and significance of the impacts. Monitoring of ambient air quality, noise level, soil quality and water quality has been conducted to establish baseline of environmental qualities in the project area and during construction impact on environment.

I. North 24 pgs District

94. In accordance with the IEE & SEMP, the contractors are required to undertake environmental monitoring as per below table. Table 19A: Environmental Monitoring Requirement (Package N 24 pgs/ 01) Monitoring Field Monitoring Location Monitoring Frequency Parameters Ambient air quality 5 locations (WTP, PM10, PM2.5 NO2, SO2, (i) Once before start of Booster pumping CO construction. station, 2 GLSRs, 1 (ii) Yearly 3 times (for pipe line) seasons: pre-monsoon, post-monsoon and winter) during construction (3-years period considered) Ambient noise 5 locations (WTP, Day time and night (i) Once before start of Booster pumping time noise levels construction. station, 2 GLSRs, 1 (ii) Yearly 3 times (for pipe line) seasons: pre-monsoon, post-monsoon and winter) during construction (3-years period considered) Surface water quality 2 locations (Bidyadhari pH, Oil and grease, Cl, Once before start of River and Kestopur F, NO3, TC, FC, construction half yearly Canal) Hardness, Turbidity during construction (3- BOD, COD, DO, Total year construction Alkalinity period considered)

Table 19B: Environmental Monitoring Requirement (Package N 24 pgs/02A – Haroa and 02B- Bhangar II) Monitoring Field Monitoring Location Monitoring Frequency Parameters Ambient air quality 5 locations PM10, PM2.5 NO2, SO2, (i) Once before start of (Selection during CO construction. implementation to (ii) Yearly 3 times (for represent the overall seasons: pre-monsoon, project area) post-monsoon and winter) during construction (3-years period considered) Ambient noise 5 locations Day time and night (i) Once before start of

232 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Monitoring Field Monitoring Location Monitoring Frequency Parameters (same as air quality time noise levels (24 construction. monitoring) hours) (ii) Yearly 3 times (for seasons: pre-monsoon, post-monsoon and winter) during construction (3-years period considered) Surface water quality 2 locations (to be pH, Oil and grease, Cl, Once before start of selected during F, NO3, TC, FC, construction implementation and as Hardness, Turbidity Half yearly during per site condition) BOD, COD, DO, Total construction (3 - year Alkalinity construction period considered)

II. Bankura District

95. Environmental Monitoring Plan of IEE/SEMP is the basis for environmental monitoring before start of the work and during implementation of the project.

Table 20A: Environmental Monitoring Requirement (Package BK/01) Monitoring Field Monitoring Location Monitoring Frequency Parameters Ambient air quality 2 locations (WTP and PM10, PM2.5 NO2, SO2, (i) Once before start of GLSR- IBPS sites) CO construction. (ii) Yearly 3 times (for seasons: pre-monsoon, post-monsoon and winter) during construction (3-years period considered) Ambient noise 4 locations (Intake, Day time and night (i) Once before start of WTP and GLSR-IBPS time noise levels construction. sites) (ii) Yearly 3 times (for seasons: pre-monsoon, post-monsoon and winter) during construction (3-years period considered) Reservoir water quality One location pH, TDS, Oil and (i) Once before start of (Reservoir intake grease, Cl, F, NO3, construction point) TC, FC, Hardness, (ii) Monthly (yearly 12 Turbidity BOD, COD, times) (3-year DO, Total Alkalinity construction period considered) Table 20B: Environmental Monitoring Requirement (Package BK/02A and BK/02B) Monitoring Field Monitoring Location Monitoring Frequency Parameters Ambient air quality 5 locations (Selection PM10, PM2.5 NO2, SO2, (i) Once before start of during implementation CO construction. to represent the (ii) Yearly 3 times (for overall project area) seasons: pre-monsoon, post-monsoon and

233 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Monitoring Field Monitoring Location Monitoring Frequency Parameters winter) during construction (3-years period considered)

Ambient noise 10 locations (same as Day time and night (i) Once before start of air quality monitoring) time noise levels (24 construction. hours) (ii) Yearly 3 times (for seasons: pre-monsoon, post-monsoon and winter) during construction (3-years period considered) Surface water quality 5 locations (Selection pH, Oil and grease, Cl, (i) Once before start of during implementation F, NO3, TC, FC, construction. to represent the Hardness, Turbidity (ii) Yearly 3 times (for overall project area) BOD, COD, DO, Total seasons: pre-monsoon, Alkalinity post-monsoon and winter) during construction (3-years period considered) Soil quality 5 locations (including, pH, Elect. Conductivity (i) Once before start of construction camps, (at 250C), Moisture (at construction. workers camps) 1050C), Texture (silt, (ii) Yearly 3 times (for clay, sand), Calcium seasons: pre-monsoon, (as CaO), Magnesium post-monsoon and (as Mg), Permeability, winter) during Nitrogen (as N), construction (3-years Sodium (as Na), period considered) Phosphate (as PO4), Potassium (as K), Organic Matter, oil and grease Ground Water Quality 5 locations (including As per IS10,500: 2012 (i) Once before start of workers camp site & construction. Construction camp/ (ii) Yearly 3 times (for storage yards) seasons: pre-monsoon, post-monsoon and winter) during construction (3-years period considered) Table 20C: Environmental Monitoring Requirement (Package BK/03) Monitoring Field Monitoring Location Monitoring Frequency Parameters Ambient air quality 2 location (WTP PM10, PM2.5 NO2, SO2, (i) Once before start of &Intake sites) CO construction. (ii) Yearly 3 times (for seasons: pre-monsoon, post-monsoon and winter) during construction (3-years period considered) Ambient noise 4 locations Day time and night (i) Once before start of

234 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Monitoring Field Monitoring Location Monitoring Frequency Parameters (Intake, WTP & 2 time noise levels construction. sensitive sites like (ii) Yearly 3 times (for hospital /school) seasons: pre-monsoon, post-monsoon and winter) during construction (3-years period considered) Barrage water quality One location pH, TDS, Oil & grease, (i) Once before start of (Reservoir intake Cl, F, NO3, TC, FC, construction point) Hardness, Turbidity (ii)Monthly (yearly 12 times) BOD, COD, DO, Total (3 years construction period Alkalinity considered) Table 20D: Environmental Monitoring Requirement (Package BK/04) Monitoring Field Monitoring Location Monitoring Frequency Parameters Ambient air quality 10 locations (Selection PM10, PM2.5 NO2, SO2, (i) Once before start of during implementation CO construction. to represent the (ii) Yearly 3 times (for overall project area) seasons: pre-monsoon, post-monsoon and winter) during construction (3-years period considered) Ambient noise 20 locations (same as Day time and night (i) Once before start of air quality monitoring) time noise levels (24 construction. hours) (ii) Yearly 3 times (for seasons: pre-monsoon, post-monsoon and winter) during construction (3-years period considered) Surface water quality 10 locations (to be pH, Oil and grease, Cl, (i) Once before start of selected during F, NO3, TC, FC, construction. implementation) Hardness, Turbidity (ii) Yearly 3 times (for BOD, COD, DO, Total seasons: pre-monsoon, Alkalinity post-monsoon and winter) during construction (3-years period considered) Soil quality 10 locations (including, pH, Elect. Conductivity (i) Once before start of construction camps, (at 250C), Moisture (at construction. workers camps) 1050C), Texture (silt, (ii) Yearly 3 times (for clay, sand), Calcium seasons: pre-monsoon, (as CaO), Magnesium post-monsoon and winter) (as Mg), Permeability, during construction (3-years Nitrogen (as N), period considered) Sodium (as Na), Phosphate (as PO4), Potassium (as K), Organic Matter, oil and grease Ground Water Quality 10 locations (including As per IS10,500: 2012 (i) Once before start of workers camp site & construction. Construction camp/ (ii) Yearly 3 times (for storage yards) seasons: pre-monsoon, post-monsoon and winter)

235 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Monitoring Field Monitoring Location Monitoring Frequency Parameters during construction (3-years period considered) III. East Medinipur District

96. Environmental Monitoring Plan of IEE/SEMP is the basis for environmental monitoring before start of the work and during implementation of the project. Table 21 A: Environmental Monitoring Requirement (Package EM/01) Monitoring field Monitoring Monitoring parameters Frequency location Ambient air quality 5 locations (Intake, • PM10, PM2.5 NO2, SO2, (i) Once before start of WTP, CO construction. Transmission (ii) Yearly 3 times (for mains route) seasons: pre-monsoon, post- monsoon and winter) during construction (3-years period considered) Ambient noise 5 locations (Intake, • Day time and night time (i) Once before start of WTP, noise levels construction Transmission (ii) Yearly 3 times (for mains route) seasons: pre-monsoon, post- monsoon and winter) during construction (3-years period considered) Surface water One location • pH, TDS, Oil & grease, Cl, (i) Once before start of quality (River intake) F, NO3, TC, FC, construction Hardness, Turbidity BOD, (ii) Monthly (yearly 12 COD, DO, Total Alkalinity times) (2-year construction and Salinity period considered) (iii) Salinity of river water should be checked at 2-3 points downstream of intake, may at an interval of 1 km, 2 km Table 21 B: Environmental Monitoring Requirement (Package EM/02) Monitoring Field Monitoring Location Monitoring Frequency Parameters Ambient air quality 10 locations PM10, PM2.5 NO2, SO2, (i) Once before start of (Reservoirs, IBPS and CO construction. pipe line) (ii)Yearly3 times (for seasons: pre-monsoon, post-monsoon and winter) during construction (3-years period considered) Ambient noise 20 locations Day time and night (i) Once before start of (Reservoirs, IBPS and time noise levels (24 construction. pipe line) hours) (ii)Yearly 3 times (for seasons: pre-monsoon, post-monsoon and winter) during construction (3-years period considered) Surface water quality 10 locations pH, Oil and grease, Cl, (i) Once before start of (Reservoirs, IBPS and F, NO3, TC, FC, construction. pipe line) Hardness, Turbidity (ii)Yearly 3 times (for seasons: BOD, COD, DO, Total pre-monsoon, post-monsoon

236 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Monitoring Field Monitoring Location Monitoring Frequency Parameters Alkalinity and winter) during construction (3-years period considered) Soil quality 10 locations pH, Elect. Conductivity (i) Once before start of (Reservoirs, IBPS and (at 250C), Moisture (at construction. pipe line) 1050C), Texture (silt, (ii)Yearly 3 times (for seasons: clay, sand), Calcium pre-monsoon, post-monsoon (as CaO), Magnesium and winter) during construction (as Mg), Permeability, (3-years period considered) Nitrogen (as N), Sodium (as Na), Phosphate (as PO4), Potassium (as K), Organic Matter, oil and grease Ground Water Quality 10 locations As per IS10,500: 2012 (i) Once before start of (Reservoirs, IBPS and construction. pipe line) (ii)Yearly 3 times (for seasons: pre-monsoon, post-monsoon and winter) during construction (3-years period considered) B. Type and location of Environmental Parameters Monitored

97. As detailed in above tables, for all the districts, air and noise monitoring should be conducted for yearly 3 times except monsoon while surface water quality should be conducted at every half-yearly (North 24 pgs), yearly 3 times (Bankura and East Medinipur packages) and monthly (Barrage and reservoir of Bankura Packages and river water at intake site of East Medinipur). The monitoring parameters are also stated in Table above.

98. In order to determine new monitoring locations, following matrices were developed for each package.

99. Based on outcome of above exercise air quality, noise level and surface and ground water quality monitoring locations were selected for packages.

100. Monitoring Locations of North 24 pgs Packages. Monitoring locations are shown with Co-ordinate in Table below and in Figures followed.

237 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Table 22A: Ambient Air Monitoring Locations – During construction monitoring - North 24 pgs during May 2020 to October 2020 Sl. No Monitoring Location Co-ordinates Construction phase - Time period Package N 24 Pgs//02A: Haroa Distribution 1. Khalisadi (Zone -14) 22°35'44.30"N, During construction- October 88°45'3.80"E 2020 2. Khardah (Zone-19) 22°35'10.50"N, During construction- October 88°38'46.60"E 2020 3. Bantosha (Zone-8) 22°33'55.00"N, During construction -October 88°42'20.00"E 2020 4. Ranigachi (Zone-20) 22°34'9.00"N, During construction- October 88°40'35.00"E 2020 5. Puratan Kamar ghanti (Zone 22°31'28.60"N During construction- October 6) 88°41'11.90"E 2020 Package N 24 Pgs/02B: Bhangar II Distribution 1. Joynagar (Zone -7) 22°32'26.39"N During construction- October 88°38'1.41"E 2020 2. Bhogali pipe line(Zone-17) 22°33'3.19"N During construction -October 88°33'16.81"E 2020 3. Pipeline Paikan(Zone-3) 22°32'31.25"N, During construction -October 88°31'35.91"E 2020 4. Uttar Kashipur(Zone-8) 22°33'18.41"N, During construction- October 88°35'50.13"E 2020 5. Kochua (Zone-15) 22°31'19.46"N, During construction -October 88°34'25.76"E 2020 Package N 24 Pgs/01: Bulk Water Supply * 1. WTP 22°35'13.00"N, During construction -October 88°26'49.00"E 2020 2. CWR 22°35'22.00"N, During construction- October 88°26'50.00"E 2020 (* Note: Baseline monitoring remaining for 2 GLSRs location of pack N 24pgs/01. Monitoring to be conducted before start of physical construction) Table 22B: Surface Water Sampling Locations – During construction monitoring -North 24 Pgs during May 2020 to October 2020* Sl. Monitoring Location Co-ordinates Construction phase- No Time period Package N 24 pgs/02A : Haroa Distribution 1. Pond water in zone 20 22°34'7.00"N, During-construction- 88°40'33.00" October 2020 2. Pond water in zone 8 22°33'55.00"N, During-construction 88°42'20.00"E October 2020 Package N 24 pgs/02B : Bhangar II Distribution

1. Pond water in Zone 15 22°31'22.00"N, During construction - 88°34'27.00"E October 2020 2. Pond water in zone 10 22°32'15.00"N During construction- 88°34'56.00"E October 2020 Package N 24 pgs/01 : WTP and Bulk Distribution 1. WTP, New Town, Rajarhat 22°35'12.62"N During construction - 88°26'52.74"E October 2020

238 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

*Note: Water quality data is monitored once in 6 months. However, due to COVID-19 situation monitoring could not be conducted in May 2020 (For package 01, 02A and 02B – Monitoring done during October 2020) Table 22C: Ambient Noise Monitoring Station Details- During construction monitoring - North 24 pgs during May 2020 to October 2020

Sl. Monitoring Location / Landuse Co-ordinates Construction No phase- Time period Package N 24 Pgs/02A: Haroa Distribution 1. Khalisadi (Zone -14)/ Residential 22°35'44.30"N, During construction 88°45'3.80"E -October 2020 2. Khardah (Zone-19)/ Commercial 22°35'10.50"N, During construction 88°38'46.60"E -October 2020 3. Bantosha (Zone-8)/ Commercial 22°33'55.00"N, During construction- 88°42'20.00"E October 2020 4 Ranigachi (Zone-20)/ Residential 22°34'9.00"N, During construction- 88°40'35.00"E October 2020 5 Puratan Kamar ghanti (Zone 6) / 22°31'28.60"N During construction- Residential 88°41'11.90"E October 2020 Package N 24 Pgs/02B: Bhangar II Distribution 1. Joynagar (Zone -7) / Silent 22°32'26.39"N During construction- 88°38'1.41"E October 2020 2. Bhogali pipe line(Zone-17) / Silent 22°33'3.19"N During construction- 88°33'16.81"E October 2020 3. Pipeline Paikan(Zone-3) / Residential 22°32'31.25"N, During construction- 88°31'35.91"E October 2020 4. Uttar Kashipur(Zone-8) / Residential 22°33'18.41"N, During construction- 88°35'50.13"E October 2020 5. Kochua (Zone-15) / Residential 22°31'19.46"N, During construction- 88°34'25.76"E October 2020 Package N 24 Pgs/01: Bulk Water Supply 1. Near WTP/ Industrial 22°35'13.00"N, During construction- 88°26'49.00"E October 2020 2. Near CWR / Industrial 22°35'22.00"N, During construction- 88°26'50.00"E October 2020 101. The monitoring locations for the projects are marked on google earth and presented below.

239 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Figure 9A: Ambient Air Quality, Noise Level and Surface Water Monitoring Stations in Haroa Block (Package N 24 Pgs/02A)

Figure 9B: Ambient Air Quality, Noise Level and Surface Water Monitoring Stations in Bhangar-II Block (Package N 24 Pgs/02B)

240 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Figure 9C: Ambient Air Quality and Noise Level Monitoring Stations in Bulk water distribution (Package N 24 Pgs/01) 102. Monitoring Locations of Bankura Packages.

103. For Bankura during construction monitoring have been conducted for all packages except BK 01. Below tables show detail of monitoring stations, where monitoring conducted during report period.

Table 23 A: Ambient Air Monitoring Station Locations –During Construction Monitoring – Bankura-May to October 2020

Sl. Construction phase - Time Monitoring Location Co-ordinates No period Package BK/01 Monitoring not done during this period- No work at that site Package BK/02A 1. Chaukighata OHSR Lat :23°9’ 33.01751’’ During Construction (13/10/20) Lon: 86°50’20.77876’’ 2 Hatgram OHSR 23°14’ 21.7432’’ During Construction (12/10/20) 86°48’ 10.05512’’ 3 Nayekhir OHSR 23°9’24.57677’’ During Construction (14/10/20) 86°54’ 47.09059’’ 4 Siromanipur OHSR 23°9’ 48.8988’’ During Construction (12/10/20) 86°56’ 43.53724’’ 5 Golakhpur OHSR :23°6’ 12.61296’’ During Construction (15/10/20) 86°54’ 49.46026’’ Package BK/02B 1. Chandabila OHSR 22°59’ 12.31’’ N During Construction (09/10/20) 87°16’ 02.33’’ E

241 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

2 Fulmati OHSR 22°58’ 49.47’ N’ During Construction (10/10/20) 87°06’ 42.24’’ E 3 Dhengashimul OHSR 23°01’ 02.72’ N’ During Construction (10/10/20) 87°02’ 02.45’’ E 4 Manipur OHSR 23°04’ 48.20’ N’ During Construction (10/10/20) 87°00’ 53.11’’ E 5 Chakmanjuriprasadpur 22°57’ 02.78’ N’ During Construction (10/10/20) OHSR 87°14’ 31.14’’ E Package BK/03 1 WTP Area 23°28’ 29.8’ N’ During Construction (15/07/20) 87°09’ 07.5’’ E 2 Intake Site 23°28’ 14.9’ N’ During Construction (15/07/20) 87°17’ 31.11’’ E Package BK/04 1 Haribhanga OHSR N 23°23'33, E 87°2'39 During Construction (19/10/20) 2 Lakhariya OHSR N 23°21'56, E 87°4'27 During Construction (19/10/20) 3 Bankdaha OHSR N 23°25'43, E 87°9'24 During Construction (21/10/20) 4 Purbator OHSR N 23°31'52, E 87°11'9 During Construction (20/10/20) 5 Kallapur OHSR N 23°24'23, E 87°11'3 During Construction (20/10/20) 6 Sarangapur OHSR N 23°25'59, E 87°11'23 During Construction (21/10/20) 7 Pairasol OHSR N 23°31'3, E 87°3'36 During Construction (20/10/20) 8 Ramkanali OHSR N 23°23'33, E 87°9'6 During Construction (22/10/20) 9 Rajamela OHSR N 23°26'31, E 87°3'20 During Construction (21/10/20) 10 Lachhmanpur OHSR N 23°26'33, E 87°1'56 During Construction (19/10/20)

Table 23B: Ambient Noise Sampling Locations - During Construction Monitoring – Bankura-May to October 2020

Sl. Construction phase - Time Monitoring Location Co-ordinates No period Package BK/01 Monitoring not done during this period- No work at that site Package BK/02A 1. Chaukighata OHSR Lat :23°9’ 33.01751’’ During Construction Lon: 86°50’20.77876’’ (13/10/20) 2 Hatgram OHSR Lat :23°14’ 21.7432’’ During Construction Lon: 86°48’ 10.05512’’ (12/10/20) 3 Nayekhir OHSR Lat :23°9’24.57677’’ During Construction Lon: 86°54’ 47.09059’’ (14/10/20) 4 Siromanipur OHSR Lat :23°9’ 48.8988’’ During Construction Lon: 86°56’ 43.53724’’ (12/10/20) 5 Golakhpur OHSR Lat :23°6’ 12.61296’’ During Construction Lon: 86°54’ 49.46026’’ (15/10/20) 6 Chakaltor Pipeline Lat :23°9’ 51.92716’’ During Construction Lon: 86°48’ 26.56098’’ (13/10/20) 7 Golakpur Pipeline Lat :23°5’ 36.72254’’ During Construction Lon: 86°56’ 18.91925’’ (15/10/20) 8 Bholarkhap Pipeline Lat :23°9’ 51.96769’’ During Construction Lon: 86°48’ 26.43041’’ (14/10/20) 9 Surulia Pipeline Lat :23°11’ 42.22669’’ During Construction Lon: 86°47’ 49.52551’’ (13/10/20)

242 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

10 Saluka (Saldiha) Pipeline Lat :23°9’ 52.0’’ During Construction Lon: 86°48’ 26.4’’ (12/10/20) Package BK/02B 1. Chandabila OHSR 22°59’ 12.31’’ N During Construction 87°16’ 02.33’’ E (09/10/20) 2 Fulmati OHSR 22°58’ 49.47’ N’ During Construction 87°06’ 42.24’’ E (10/10/20) 3 Dhengashimul OHSR 23°01’ 02.72’ N’ During Construction 87°02’ 02.45’’ E (10/10/20) 4 Manipur OHSR 23°04’ 48.20’ N’ During Construction 87°00’ 53.11’’ E (10/10/20) 5 Chakmanjuriprasadpur OHSR 22°57’ 02.78’ N During Construction 87°14’ 31.14’’ E (10/10/20) 6 23°00’ 34.19’ N During Construction Bhutamahespur pipeline 87°03’ 10.71’’ E (10/10/20) 7 Bendalaxmanpur Pipeline 23°03’ 20.08’ N During Construction 87°05’ 51.89’’ E (10/10/20) 8 Saharghati Pipeline 23°01’ 11.35’ N During Construction 87°07’ 14.22’’ E (10/10/20) 9 Panchamura Pipeline 22°58’ 08.93’ N During Construction 87°10’ 37.44’’ E (10/10/20) 10 Pedda Pipeline 23°02’ 38.59’ N During Construction 86°58’ 50.94’’ E (10/10/20) Package BK/03 1 Intake Area 23°28’ 15.0’ N During Construction 87°17’ 30.4’’ E (15/07/20) 2 WTP site 23°28’ 29.8’ N During Construction 87°09’ 07.3’’ E (15/07/20) 3 School area 23°28’ 20.5’ N During Construction 86°58’ 50.94’’ E (15/07/20) 4 Hospital area 23°18’ 15.1’ N During Construction 87°11’ 30.0’’ E (15/07/20) Package BK/04 1 Haribhanga OHSR N 23°23'33, E 87°2'39 During Construction (20.10.20) 2 Lakhariya OHSR N 23°21'56, E 87°4'27 During Construction (20.10.20) 3 Bankdaha OHSR N 23°25'43, E 87°9'24 During Construction (21.10.20) 4 Purbator OHSR N 23°31'52, E 87°11'9 During Construction (21.10.20) 5 Kallapur OHSR N 23°24'23, E 87°11'3 During Construction (22.10.20) 6 Sarangapur OHSR N 23°25'59, E 87°11'23 During Construction (22.10.20) 7 Pairasol OHSR N 23°31'3, E 87°3'36 During Construction (21.10.20) 8 Ramkanali OHSR N 23°23'33, E 87°9'6 During Construction (23.10.20) 9 Rajamela OHSR N 23°26'31, E 87°3'20 During Construction (23.10.20)

243 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

10 Lachhmanpur OHSR N 23°26'33, E 87°1'56 During Construction (21.10.20) 11 Lakhariya Pipe line N 23°21'56, E 87°4'27 During Construction (17.10.20) 12 Amarkanan Pipe line N 23°23'24, E 87°6'25 During Construction (18.10.20) 13 Haribhanga pipe line N 23°23'7, E 87°1'55 During Construction (18.10.20) 14 Kapistha Pipe line N 23°23'53, E 87°8'9 During Construction (18.10.20) 15 Ranganathpur pipe line N 23°19'3, E 87°4'34 During Construction (17.10.20) 16 Piraboni Pipe line N 23°19'45, E 87°9'36 During Construction (19.10.20) 17 Purbator pipe line N 23°31'52, E 87°11'55 During Construction (17.10.20) 18 Piraboni OHSR N 23°19'15, E 87°9'39 During Construction (19.10.20) 19 Gobindadham OHSR N 23°21'32, E 87°6'36 During Construction (20.10.20) 20 Benagari Pipe line N 23°31'52, E 87°11'5 During Construction (10.10.20)

Table 23C: Ground water Sampling Locations – During Construction Monitoring – Bankura- May to October 2020

Sl. Construction phase - Time Monitoring Location Co-ordinates No. period Package BK/02A 1. Chaukighata OHSR Lat :23°9’ 33.01751’’ During Construction (13/10/20) Lon: 86°50’20.77876’’ 2 Hatgram OHSR Lat :23°14’ 21.7432’’ During Construction (12/10/20) Lon: 86°48’ 10.05512’’ 3 Nayekhir OHSR Lat :23°9’24.57677’’ During Construction (14/10/20) Lon: 86°54’ 47.09059’’ 4 Siromanipur OHSR Lat :23°9’ 48.8988’’ During Construction (12/10/20) Lon: 86°56’ 43.53724’’ 5 Golakhpur OHSR Lat :23°6’ 12.61296’’ During Construction (15/10/20) Lon: 86°54’ 49.46026’’ Package 02B

1. Chandabila OHSR 22°59’ 12.31’’ N During Construction (09/10/20) 87°16’ 02.33’’ E 2 Fulmati OHSR 22°58’ 49.47’ N’ During Construction (10/10/20) 87°06’ 42.24’’ E 3 Dhengashimul OHSR 23°01’ 02.72’ N’ During Construction (10/10/20) 87°02’ 02.45’’ E 4 Manipur OHSR 23°04’ 48.20’ N’ During Construction (10/10/20) 87°00’ 53.11’’ E 5 Chakmanjuriprasadpur 22°57’ 02.78’ N’ During Construction (10/10/20) OHSR 87°14’ 31.14’’ E Package BK/04 1 Haribhanga OHSR N 23°23'33, E 87°2'39 During Construction (19.10.20)

244 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

2 Lakhariya OHSR N 23°21'56, E 87°4'27 During Construction (19.10.20) 3 Bankdaha OHSR N 23°25'43, E 87°9'24 During Construction (21.10.20) 4 Purbator OHSR N 23°31'52, E 87°11'9 During Construction (20.10.20) 5 Kallapur OHSR N 23°24'23, E 87°11'3 During Construction (20.10.20) 6 Sarangapur OHSR N 23°25'59, E 87°11'23 During Construction (21.10.20) 7 Pairasol OHSR N 23°31'3, E 87°3'36 During Construction (20.10.20) 8 Ramkanali OHSR N 23°23'33, E 87°9'6 During Construction (22.10.20) 9 Rajamela OHSR N 23°26'31, E 87°3'20 During Construction (21.10.20) 10 Lachhmanpur OHSR N 23°26'33, E 87°1'56 During Construction (19.10.20)

Table 23D: Surface water Sampling Locations –Baseline and During Construction Monitoring – Bankura- May to October 2020 Sl. Construction phase - Time Monitoring Location Co-ordinates No. period Package BK/01 1. Intake point ------Baseline (August, 20) Package BK/02A 1 Chaukighata OHSR Lat :23°9’ 33.01751’’ During Construction Lon: 86°50’20.77876’’ (13/10/20) 2 Hatgram OHSR Lat :23°14’ 21.7432’’ During Construction Lon: 86°48’ 10.05512’’ (12/10/20) 3 Nayekhir OHSR Lat :23°9’24.57677’’ During Construction Lon: 86°54’ 47.09059’’ (14/10/20) 4 Siromanipur OHSR Lat :23°9’ 48.8988’’ During Construction Lon: 86°56’ 43.53724’’ (12/10/20) 5 Golakhpur OHSR Lat :23°6’ 12.61296’’ During Construction Lon: 86°54’ 49.46026’’ (15/10/20) Package BK/02B

1 Chandabila OHSR 22°59’ 12.31’’ N During Construction 87°16’ 02.33’’ E (09/10/20) 2 Fulmati OHSR 22°58’ 49.47’ N’ During Construction 87°06’ 42.24’’ E (10/10/20) 3 Dhengashimul OHSR 23°01’ 02.72’ N’ During Construction 87°02’ 02.45’’ E (10/10/20) 4 Manipur OHSR 23°04’ 48.20’ N’ During Construction 87°00’ 53.11’’ E (10/10/20) 5 Chakmanjuriprasadpur 22°57’ 02.78’ N’ During Construction OHSR 87°14’ 31.14’’ E (10/10/20) Package BK/03 1 Intake Point N 23°28'15.6, E 87°17'13.1 During Construction July, August, September and October 2020 Package BK/04 1 Haribhanga OHSR N 23°23'33, E 87°2'39 During Construction (19.10.20)

245 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Sl. Construction phase - Time Monitoring Location Co-ordinates No. period 2 Lakhariya OHSR N 23°21'56, E 87°4'27 During Construction (19.10.20) 3 Bankdaha OHSR N 23°25'43, E 87°9'24 During Construction (21.10.20) 4 Purbator OHSR N 23°31'52, E 87°11'9 During Construction (20.10.20) 5 Kallapur OHSR N 23°24'23, E 87°11'3 During Construction (20.10.20) 6 Sarangapur OHSR N 23°25'59, E 87°11'23 During Construction (21.10.20) 7 Pairasol OHSR N 23°31'3, E 87°3'36 During Construction (20.10.20) 8 Ramkanali OHSR N 23°23'33, E 87°9'6 During Construction (22.10.20) 9 Rajamela OHSR N 23°26'31, E 87°3'20 During Construction (21.10.20) 10 Lachhmanpur OHSR N 23°26'33, E 87°1'56 During Construction (19.10.20)

Table 23E: Soil Sampling Locations – During Construction Monitoring – Bankura- May to October 2020

Sl. Construction phase - Monitoring Location Co-ordinates No. Time period Package BK/02A 1 Chaukighata OHSR Lat :23°9’ 33.01751’’ During Construction Lon: 86°50’20.77876’’ (13/10/20) 2 Hatgram OHSR Lat :23°14’ 21.7432’’ During Construction Lon: 86°48’ 10.05512’’ (12/10/20) 3 Nayekhir OHSR Lat :23°9’24.57677’’ During Construction Lon: 86°54’ 47.09059’’ (14/10/20) 4 Siromanipur OHSR Lat :23°9’ 48.8988’’ During Construction Lon: 86°56’ 43.53724’’ (12/10/20) 5 Golakhpur OHSR Lat :23°6’ 12.61296’’ During Construction Lon: 86°54’ 49.46026’’ (15/10/20) Package BK/02B

1 Chandabila OHSR 22°59’ 12.31’’ N, 87°16’ During Construction 02.33’’ E (09/10/20) 2 Fulmati OHSR 22°58’ 49.47’ N’, 87°06’ During Construction 42.24’’ E (10/10/20) 3 Dhengashimul OHSR 23°01’ 02.72’ N’, 87°02’ During Construction 02.45’’ E (10/10/20) 4 Manipur OHSR 23°04’ 48.20’ N’, 87°00’ During Construction 53.11’’ E (10/10/20) 5 Chakmanjuriprasadpur OHSR 22°57’ 02.78’ N’, 87°14’ During Construction 31.14’’ E (10/10/20) Package BK/04 1 Haribhanga OHSR N 23°23'33, E 87°2'39 During Construction (20/10/20)

246 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

2 Lakhariya OHSR N 23°21'56, E 87°4'27 During Construction (20/10/20) 3 Bankdaha OHSR N 23°25'43, E 87°9'24 During Construction (22/10/20) 4 Purbator OHSR N 23°31'52, E 87°11'9 During Construction (21/10/20) 5 Kallapur OHSR N 23°24'23, E 87°11'3 During Construction (21/10/20) 6 Sarangapur OHSR N 23°25'59, E 87°11'23 During Construction (22/10/20) 7 Pairasol OHSR N 23°31'3, E 87°3'36 During Construction (21/10/20) 8 Ramkanali OHSR N 23°23'33, E 87°9'6 During Construction (23/10/20) 9 Rajamela OHSR N 23°26'31, E 87°3'20 During Construction (22/10/20) 10 Lachhmanpur OHSR N 23°26'33, E 87°1'56 During Construction (20/10/20)

104. The monitoring locations for the projects were marked on Google earth and presented below.

Figure 10A: Surface Water Monitoring stations for Package BK/01- Bankura

247 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Figure 10B: Monitoring stations for Package BK/02A- Bankura

Figure 10C: Monitoring stations for Package BK/02B- Bankura

248 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Figure 10D: Monitoring stations for Package BK/03- Bankura

Figure 10 E: Monitoring stations for Package BK/04- Bankura

105. Monitoring locations of East Medinipur: For two packages of East Medinipur, i.e. EM/01 and EM/02, the baseline monitoring work and also during construction monitoring work has been completed.

249 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Package: EM/01

Table 24A: Ambient Air Monitoring Station Locations- Baseline & During construction monitoring- East Medinipur – May to October 2020

Baseline Location During Construction Location Monitoring Co-ordinates Monitoring Co-ordinates Monitoring Sl. Location period period No Package EM/01 1 WTP 592960.639,, 06.07.2020 592960.639 , October,2020 2450290.207 2450290.207 2 Intake 598593.344, 06.07.2020 598593.344 , October,2020 2460317.309 2460317.309 3 Totabaria 596531.065,2462082.976 07.07.2020 596531.065,2462082.976 October,2020 4 Near Haldi 592024.135, 07.07.2020 592024.135, October,2020 River 2448255.045 2448255.045 5 Magrajpur 59040.283, 2446049.088 08.07.2020 59040.283, 2446049.088 October,2020

Table 24B: Surface Water Sampling location- Baseline & During construction monitoring - East Medinipur– May to October 2020

Baseline Location During Construction Location Monitoring Co-ordinates Monitoring Co-ordinates Monitoring Sl. Location period period No Package EM/01 1 Intake 598593.344 , 10.07.2020 598593.344 , October,2020 2460317.309 2460317.309 2 Totabaria 596531.065,2462082.976 10.07.2020 596531.065,2462082.976 October,2020

Table 24C: Noise Sampling Locations- Baseline & During construction monitoring- East Medinipur- May to October 2020

Baseline Location During Construction Location Monitoring Co-ordinates Monitoring Co-ordinates Monitoring Sl. Location period period No Package EM/01 1 WTP 592960.639 , 06.07.2020 592960.639 , October,2020 2450290.207 2450290.207 2 Intake 598593.344 , 06.07.2020 598593.344 , October,2020 2460317.309 2460317.309 3 Totabaria 07.07.2020 596531.065,2462082.976 October,2020 596531.065,2462082.976 4 Near Haldi 592024.135, 07.07.2020 592024.135, October,2020 River 2448255.045 2448255.045 5 Magrajpur 59040.283, 08.07.2020 59040.283, 2446049.088 October,2020 2446049.088

106. The monitoring locations for the package were marked on google earth and presented below.

250 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Figure 11A: Air, Noise, Surface Water quality Monitoring sites for Package East Medinipur, Package- EM/01 Package: EM/02

Table 25A: Ambient Air Monitoring Station Locations- During construction– East Medinipur- May to October 2020 During Construction Location Sl. Monitoring Co-ordinates Monitoring period No Location Package EM/02 1 Garchakraberia 21⁰59’0.9”, 87⁰59’42.6” October,2020 Near Primary School 2 Jambari Near OHR 22⁰57’31.1” , 87⁰56’13.1” October,2020 3 Manuchak Jalpai 22⁰3’36.9” , 87⁰59’22.2” October,2020 4 Parbatipur,Near 22⁰0’54.6” , 88⁰1’21.4” October,2020 OHR 5 Nandigram CT 22⁰1’21.1” , 87⁰58’23.2” October,2020 6 Haripur, Near OHR 22⁰1’17.7” , 87⁰57’7.1” October,2020 7 Kamalpur, Near 21⁰59’6.9” , 87⁰54’48.3” October,2020 OHR 8 Birulia 21⁰59’4.8” , 87⁰51’32.4” October,2020 9 Monoharpur, Near 22⁰3’2.3” , 87⁰54’49.8” October,2020 Primary School 10 Kanakpur, Near 22⁰4’28.9” , 87⁰56’28.5” October,2020 OHR

251 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Table 25B: Ground Water Sampling locations- During construction– East Medinipur- May to October 2020 During Construction Location Sl. Monitoring Co-ordinates Monitoring period No Location Package EM/02 1 Manoharpur 22⁰3’2.3” , 87⁰54’49.8” October,2020 2 Haripur 22⁰1’17.7” , 87⁰57’7.1” October,2020 3 Nandigram CT 22⁰1’21.1” , 87⁰58’23.2” October,2020 4 Parbatipur 22⁰0’54.6” , 88⁰1’21.4” October,2020 5 Manuchak Jalpai 22⁰3’36.9” , 87⁰59’22.2” October,2020 6 Jambari 22⁰57’31.1” , 87⁰56’13.1” October,2020 7 Garchakraberia 21⁰59’0.9”, 87⁰59’42.6” October,2020 8 Kamalpur 21⁰59’6.9” , 87⁰54’48.3” October,2020 9 Kanakpur 22⁰4’28.9” , 87⁰56’28.5” October,2020 10 Birulia 21⁰59’4.8” , 87⁰51’32.4” October,2020

Table 25C: Surface Water Sampling location- During construction–East Medinipur- May to October 2020 During Construction Location Sl. Monitoring Co-ordinates Monitoring period No Location Package EM/02 1 Manoharpur 22⁰3’2.3” , 87⁰54’49.8” October,2020 2 Haripur 22⁰1’17.7” , 87⁰57’7.1” October,2020 3 Nandigram CT 22⁰1’21.1” , 87⁰58’23.2” October,2020 4 Parbatipur 22⁰0’54.6” , 88⁰1’21.4” October,2020 5 Manuchak Jalpai 22⁰3’36.9” , 87⁰59’22.2” October,2020 6 Jambari 22⁰57’31.1” , 87⁰56’13.1” October,2020 7 Garchakraberia 21⁰59’0.9”, 87⁰59’42.6” October,2020 8 Kamalpur 21⁰59’6.9” , 87⁰54’48.3” October,2020 9 Kanakpur 22⁰4’28.9” , 87⁰56’28.5” October,2020 10 Birulia 21⁰59’4.8” , 87⁰51’32.4” October,2020

Table 25D: Soil Sampling location- During construction– East Medinipur-May to October 2020 During Construction Location Sl. Monitoring Co-ordinates Monitoring period No Location Package EM/02 1 Manoharpur 22⁰3’2.3” , 87⁰54’49.8” October,2020 2 Haripur 22⁰1’17.7” , 87⁰57’7.1” October,2020 3 Nandigram CT 22⁰1’21.1” , 87⁰58’23.2” October,2020 4 Parbatipur 22⁰0’54.6” , 88⁰1’21.4” October,2020 5 Manuchak Jalpai 22⁰3’36.9” , 87⁰59’22.2” October,2020 6 Jambari 22⁰57’31.1” , 87⁰56’13.1” October,2020 7 Garchakraberia 21⁰59’0.9”, 87⁰59’42.6” October,2020 8 Kamalpur 21⁰59’6.9” , 87⁰54’48.3” October,2020 9 Kanakpur 22⁰4’28.9” , 87⁰56’28.5” October,2020 10 Birulia 21⁰59’4.8” , 87⁰51’32.4” October,2020

252 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Table 25E: Noise Sampling location- During construction– East Medinipur- May to October 2020 During Construction Location Sl. Monitoring Location Co-ordinates Time period No Package EM/02 1 Garchakraberia Near 21.97036N, 88.00255E October,2020 Primary School 2 Jambari, Near OHR 21.96176N, 87.93721E October,2020 3 Manuchak Jalpai 22.02545N, 87.95165E October,2020 4 Parbatipur, Near OHR 22.01462N, 88.02223E October,2020 5 Nandigram CT 22.02251N, 87.97307E October,2020 6 Haripur, Near OHR 22.02545N, 87.94174E October,2020 7 Kamalpur, Near OHR 21.97626N, 87.91178E October,2020 8 Birulia 21.98457N, 87.95907E October,2020 9 Monoharpur, Near Primary 22.05032N, 87.91311E October,2020 School 10 Kanakpur, Near OHR 22.08565N, 87.94714E October,2020 11 Gangra, Near OHR 21.91829N, 87.98309E October,2020 12 Chakchilinga, Near OHR 21.58184N, 87.58548E October,2020 13 Gokulnagar,near OHR 21.94799N, 87.95879E October,2020 14 Naynan 21.98991N, 87.93808E October,2020 15 Dinabandhupur 22.04204N, 88.00729E October,2020 16 Purushottompur 22.00700N, 87.98996E October,2020 17 Banasri Garui 22.00577N, 87.91885E October,2020 18 Gholpukuria 22.01559N, 87.88141E October,2020 19 Narasinghapur Jalpia 22.06273N, 87.95632E October,2020 20 Gopalchak 22.08573N, 87.97943E October,2020

Figure 11B: Monitoring location of EM/02

253 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

C Method of monitoring and Equipment used

107. Ambient Air Quality Monitoring Equipment and Methodology. Respirable Dust Samplers and Fine Dust Samplers (Model no.-APM-860/APM-154) have been used to collect samples for PM (10) and PM (2.5) in ambient air at a flow rate of 1.2 m3/min. The ambient air was sucked through the cyclone and filter paper by a blower. Samples of gases were drawn at a flow rate of 0.5 liters per minute and were analysed in the laboratory. Ambient air quality monitoring methodology is given in table below. Table 26: Methodology for the ambient air monitoring Sl. Parameters Measurement Method As per No 1. PM10 Gravimetric IS:5182 Part-23, RA-2017 2. PM2.5 Gravimetric USEPA CFR-40, Part-50 3. SO2 Colorimetric (EPA modified West & Gaeke Method) IS:5182 Part-2, 2001, RA-2017 4. NOX Colorimetric (Arsenite modified Jacobs & IS:5182 Part-6, 2006, RA-2017 Hochheiser Method) 5. CO Non-Dispersive Infra-Red (NDIR) Spectroscopy IS:5182 Part-10, 1999, RA- Technique 2014

108. Methodology of Surface and Ground Water Monitoring. In order to establish baseline/ during construction conditions, grab samples were collected from water source and were analysed for various parameters as per the procedures laid down in the BIS. Samples were collected as per IS- 2488 (Part I-V). Surface water samples were analysed as per surface water quality criteria by Central Pollution Control Board (CPCB) for class B. Ground water samples were also analysed as per method provided by CPCB. Wet chemical, Atomic Absorption Spectrophotometer and UV/VIS Spectrophotometer were used for analysis of water samples according to the necessity.

109. Methodology of Noise Monitoring. Pulsar Data logger Noise Meter (Model 30) was used to monitor the noise levels. Noise level was monitored continuously for 24 hours with one- hour interval. Noise level was measured in the form of Leq dB(A), - Day and Night

D. Monitoring results and analysis of results

110. Monitoring results and analysis of results are presented below for sub projects at North 24 Pgs, Bankura and East Medinipur.

I. Environmental Monitoring Results of North 24 Pgs and observations

Table 27A: Ambient Air Quality Monitoring Results- North 24 pgs- During Construction Site no. Date of Site Construction Parameters Testing Location phase PM10 PM2.5 CO SO2 NO2 (μg/m3) (μg/m3) (μg/m3) (μg/m3) (μg/m3) Contract Package WBDWSIP/DWW/NCB/N24P/02A/2017-18 Zone -14 12-13.10.2020 Khalisadi During construction 144 80 748 11.6 38.8 Zone-19 12-13.10.2020 Khardah During construction 116 73 757 11.8 38.8 Zone-8 12-13.10.2020 Bantosha During construction 138 77 645 11.2 38.4 Zone-20 13-14.10.2020 Ranigachi During construction 124 75 803 10.8 36.4 Zone- 6 16-17.10.2020 Puratan During construction 97 54 582 10.6 36.6 Kamar ghanti Contract Package WBDWSIP/DWW/NCB/N24P/02B/2017-18

254 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Site no. Date of Site Construction Parameters Testing Location phase PM10 PM2.5 CO SO2 NO2 (μg/m3) (μg/m3) (μg/m3) (μg/m3) (μg/m3) Zone -7 14-15.10.2020 Joynagar During construction 118 71 544 9.9 38.5 Zone-17 14-15.10.2020 Bhogali During construction 125 71 541 10.7 36.4 pipe line Zone-3 15-16.10.2020 Pipeline During construction 108 62 515 11.8 38.4 Paikan Zone-8 15-16.10.2020 Uttar During construction 98 57 672 10.7 36.2 Kashipur Zone-15 15-16.10.2020 Kachua During construction 112 64 657 11.4 38.8 Contract Package: WBDWSIP/DWW/NCB/N24P/01/2017-18 15-16.10.2020 Near During construction 88 42 418 9.7 36.2

WTP 17-18.10.2020 Near During construction 82 36 422 9.2 36.6 CWR National Ambient Air Quality Standard 100 60 2000 80 80 (NAAQS) WHO standard 100 50 - 50* 40* *Interim target 2 Note: National level Central Pollution Control Board’s (Govt. of India) guideline/ protocol used for sampling, For analysis. INDIAN STANDARD IS 5182 and USEPA CFR 40 (International protocol) used for analysis Table 27B: Noise Level Monitoring data- North 24 Pgs- During Construction Site No Date of Testing Site Location/ Construction phase Leq dB(A) Landuse Day Time Night Time Contract Package WBDWSIP/DWW/NCB/N24P/02A/2017-18 Zone -14 12-13.10.2020 Khalisadi / Residential During construction 56.4 47.9 Zone-19 12-13.10.2020 Khardah / Commercial During construction 59.3 50.2 Zone-8 13-14.10.2020 Bantosha / Commercial During construction 60.1 54.8 Zone-20 13-14.10.2020 Ranigachi / Residential During construction 59.7 51.7 Zone- 6 16-17.10.2020 Puratan Kamar ghanta / During construction 58.8 50.9 Residential Contract Package WBDWSIP/DWW/NCB/N24P/02B/2017-18 Zone -7 14-15.10.2020 Joynagar During construction 49.6 47.2 Zone-17 14-15.10.2020 Bhogali pipe line During construction 57.8 49.0 Zone-3 15-16.10.2020 Pipeline Paikan / During construction 56.2 49.7 Residential Zone-8 15-16.10.2020 Uttar Kashipur / During construction 51.5 47.2 Residential Zone-15 15-16.10.2020 Kochua / Residential During construction 49.6 45.0 Contract Package: WBDWSIP/DWW/NCB/N24P/01/2017-18 15-16.10.2020 Near WTP / Industrial During construction 58.7 48.0 15-16.10.2020 Near CWR / Industrial During construction 59.4 46.8 Code/Category Leq Day Time dB(A) - Standard Leq Night Time dB(A) - Standard A/Industrial 75 70 B/Commercial 65 55 C/Residential 55 45 D/Ecological- 50 40 Sensitive Note: National level Central Pollution Control Board’s, CPCB’s (Govt. of India) guideline/ protocol used for sampling

255 WBDWSIP: ADB Loan 3696-IND – Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Table 27C: Surface Water quality monitoring Result – North 24 Pgs- During construction Site no. Date of Site Location Parameters sampling pH Turbidity Cl- F No3- COD BOD DO Total Hard Oil & Total Faecal (NTU) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) (mg/l) alkalin ness Grease coliform coliform ity (mg/l) (mg/l) (MPN/ (MPN/10 (mg/l) 100 ml) 0ml) Contract Package WBDWSIP/DWW/NCB/N24P/02A/2017-18 Zone-20 12.10.2020* Pond water in 8.05 60.9 538.1 <0.1 0.68 20.0 5.6 5.4 192 275 1.6 12.0 <2 Zone 20 Zone-8 12.10.2020* Pond water in 8.06 25.5 978.0 0.21 0.74 80.0 22.0 5.1 228 495.0 2.8 9.0 <2 Zone 8 Contract Package WBDWSIP/DWW/NCB/N24P/02B/2017-18 Zone-15 13.10.2020* Pond water in 7.17 58.0 66.53 0.19 0.62 62.4 18.0 5.2 144 429 2.2 16 <2 Zone 15 Zone-10 13.10.2020* Pond water in 7.66 15.3 49.96 0.50 0.88 83.2 22.2 5 124 176 1.8 9.0 <2 Zone 10 Surface water quality criteria By CPCB 6.5-8.5 ------1.5 ------3 5 ------500 --- (class B outdoor bathing) *Note: Water quality data is monitored once in 6 months.

256 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Table 27D: Raw Water quality monitoring Result – North 24 Pgs- Package N 24pgs/01

Sampling Location: WTP (Canteen), New Town Sampling Date: 17.10.2020 Sample Description: Raw Water A) Biological Analysis Results

Norms as per IS Sl. No. Characteristic Test Method Results 10500:2012 Total Coliform 1 Not detectable IS15185-2016 Not detectable Bacteria/100ml 2 E Coli/100ml Not detectable IS15185-2016 Not detectable B) Chemical Analysis Results As per Drinking water standard : Sl. No. Test Parameter Test Method IS:10500, 2012 Results Desirable Limit Permissible Limit Colour in Hazen 1 IS 3025 (Part 4) 1983 (RA 2012) 5 15 <1.0 Units 2 Odour IS 3025 (Part 4) 1983 (RA 2012) Agreeable Agreeable Agreeable IS 3025 (Part 7&8) 1984 (RA 3 Taste Agreeable Agreeable Agreeable 2002) IS 3025 (Part 11)-1984; Rffm: 4 pH Value at 250C 6.5-8.5 No Relaxation 7.18 2006 IS 3025 (Part 14)-1984; Rffm: 5 Turbidity in NTU 1 5 <1.0 2006 Total Dissolved 6 Solids (as TDS) IS 3025 (Part 16)-1984; RA 2012 500 2000 264.0 in mg/l Calcium (as Ca) IS 3025 (Part 40)-1991; Rffm 7 75 200 18.10 in mg/l 2009 Chloride (as Cl) IS 3025 (Part 32)-1988; Rffm 8 250 1000 22.60 in mg/l 2009 Iron (as Fe) in IS 3025 (Part 53)-1988; Rffm 9 1.0 No Relaxation <0.05 mg/l 2009 Magnesium (as IS 3025 (Part 46)-1994; Rffm 10 30 100 2.58 Mg) in mg/l 2009 Sulphate (as IS 3025 (Part 24)-1986; Rffm 11 200 400 8.64 SO4) in mg/l 2009 Total Hardness IS 3025 (Part 21)-1983; Rffm 12 (as CaCO3) in 200 600 56.0 2003 mg/l Alkalinity (as 13 IS 3025 (Part 23)-1986, RA 2014 200 600 78.0 CaCO3) in mg/l Comparative Analysis of Monitoring Results 111. The monitoring results obtained from same locations over time have been compared in the charts presented below.

Air Quality

112. Out of the 5 locations where ambient air quality has been monitored, only one location (Zone 19) in Haroa block is common with previous monitoring campaigns. However, no monitoring location was common with previous monitoring locations during this period for Bhangar II block. Thus, comparison is primarily done for all the zones in this current 6-monthly period. Ambient air quality has been consistently monitored at WTP, New Town under Bulk water supply subproject. Hence, trend analysis over time is presented below for these locations only.

257 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Comparison of Air Quality Parameters for Haroa Block

PM10 Monitoring of Haroa block from May 2020 to PM2.5 Monitoring of Haroa block from May 2020 to October 2020 October 2020 200 100 80 150 60 100

40 μg/m3 50 μg/m3 20 0 0 Zone 14 Zone 19 Zone 8 Zone 20 Zone 6 Zone 14 Zone 19 Zone 8 Zone 20 Zone 6

PM 10 NAAQS for PM10 WHO Standard PM 2.5 NAAQS for PM2.5 WHO Standard

Comparison of Air Quality Parameters for Bhangar II Block

PM10 Monitoring of Bhangar II block form May 2020 to PM2.5 monitoring of Bhangar II block from May 2020 October 2020 to October 2020 150 80

60 100

40 μg/m3 μg/m3 50 20

0 0 Zone 7 Zone 17 Zone 3 Zone 8 Zone 15 Zone 7 Zone 17 Zone 3 Zone 8 Zone 15

PM 10 NAAQS for PM10 WHO standard PM 2.5 NAAQS for PM2.5 WHO standard

258 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Comparison of Air Quality Parameters for WTP

Comparison of Air Quality data from current 6- PM 2.5 and PM 10 monitoring for the current monthly vs last 6-monthly near WTP location 6-monthly period in WTP site 120

150 100

80 100

60 μg/m3 μg/m3 50 40

20 0 May 20 to Oct 20 Nov 19 to April 20 0 Near WTP Near CWR PM10 PM 2.5 PM 2.5 PM 10 NAAQS for PM2.5 NAAQS for PM10 NAAQS for PM2.5 NAAQS for PM10

Comparison of Drinking Water Quality Parameters for WTP

Comparing drinking water quality for current and last 6- monthly period for sample collected from Canteen 60 50 40

30 units 20 10 0 Total Cauliform PH TDS(*10^2)

Nov 19 to April 20 May 20 to Oct 20

259 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Comparison of Air and Noise Quality in Haroa block Zone 19

Comparison of Air Quality for Zone 19

150

100

μg/m3 50 0 May 20 to Oct 20 Nov 19 to April 20

PM2.5 PM10 NAAQS for PM2.5 NAAQS for PM10

Comparison of Noise Quality in Haroa zone 19 Commercial Area 70 60 50 40 30 20 Leq in dB(A) 10 0 May 20 to Oct 20 Nov 19 to April 20 Leq Day Leq Night

Permissible Day Permissible Night

*Note: Since the locations for water quality monitoring during the present 6-monthly period are not common with previous 6-monthly period therefore, the comparison for surface water quality could not be done. As of now only zone-19 of Haroa block is common with previous 6-monthly period, so comparison for Air and Noise is shown for this location only.

260 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Comparison of Noise Quality parameter for Commercial and Residential areas of Haroa block

Comparison of Noise quality in Residential Comparison of Noise quality in area Commercial Area 80 80 60 ) 60 40 40 20 dB(A) in Leq 20 dB(A in Leq 0 0 Zone 19 Zone 8 Zone 20 Zone 6 Zone 14

Leq Day Time Leq Night Time Leq Day Time Leq Night Time Permissible Day Permissible Night Permissible Day Permissible Night

Comparison of Noise Quality parameter for Residential and Silent areas of Bhangar II block

Comparison of Noise quality in Silent Comparison of noise quality in areas Residential areas 60 80 50 60 40 30 40 20

20 Leq Leq in dB(A) 10 dB(A) inLeq 0 0 Zone 8 Zone 15 Zone 3 Zone 7 Zone 17 Leq Day Time Leq Night Time Leq Day Time Leq Night Time

Permissible Day Permissible Night Permissible Day Permissible Night

261 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Comparison of Noise quality parameter for WTP site

Comparison of Noise quality at WTP Site during Comparison of Noise quality in current 6-monthly current 6-monthly period vs previous monitoring at Rajarhat 80 80 70 70 60 60 50 50 40 40 30

30 Leq Leq in dB(A) Leq Leq in dB(A) 20 20 10 10 0 May 20 to Oct 20 Nov 19 to April 20 0 WTP Site CWR Site Leq day Leq night Leq Day Leq Night Permissible Day Permissible night Permissible Day Permissible Night

262 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

113. For all the subprojects except Zone 6 of Haroa, Zone 8 of Bhangar II, and both WTP and CWR sites, PM10 and PM2.5 results “during constructions” are found to be exceeding the limits prescribed in National Ambient Air Quality Standard as well as WHO. Although, CO, SO2 and NO2 concentration levels –typically emitted due to combustion of fossil fuels – were all found within the prescribed National standard. Concentration of NO2 is just below the WHO standard. Therefore, it can be inferred that the increased levels of PM10 and PM2.5 are due to high background concentration and construction activities.

114. Except, zone 19 of Haroa block, there is no common zone where monitoring has taken place previously. Therefore, the trend could not be analysed for any of the other zones of Haroa and Bhangar II block. But at zone 8 and 14 of Haora, and zone 17 and 7 of Bhangar II block, significant high amount of PM10 and PM2.5 was observed. These high amounts of pollution load might be due to the construction activity. All mitigation measures need to be applied to control air pollutants.

115. Further, trend analysis of monitoring data from Haroa zone 19 shows that the parameters like PM2.5 and PM10 have declining pattern. This might be due to the sprinkling of water done for dust suppression. Similarly, pattern for noise has also been analysed and it is seen that the Leq for day and night has reduced compared to the previous monitoring period in zone 19 in Haroa block. This declining pattern might be due to proper implementation of work scheduling.

116. Contractors have been advised regularly to take necessary action on dust suppression by sprinkling of water whenever required.

117. Water quality for the surface water bodies could not be compared due to change in monitoring locations over time. However, comparison has been done for WTP site in Rajarhat for drinking water. By comparing these trends, it is understood that total cauliform has reduced in this current 6-monthly period, PH has also been decreased and finally total dissolved solids are also reduced than previous monitoring period.

118. In case of noise level, for package 02A, zone 19 and 8 is situated within commercial area (shops and Cooperative Society) and rest are in residential area. For the locations in commercial land use, the noise levels are within the permissible limit whereas for those in residential zones, noise level is within stipulated limit in Zone 14 but slightly exceeded in zone 6 and 20 from standard.

119. However, for package 02B, monitoring in pipe laying work of zone 7 and 17 was done in front of school, so it accounts for silent zone, rest were in Residential zone. For this case, it is found that for all the locations, the day time noise is within the stipulated limit except for zone 17 but night time noise levels are exceeded at all locations.

120. Except for Zone 19 of Haroa block, trend analysis for noise level could not be done in Haroa and Bhangar II areas as the monitoring zones are different than in the previous 6-monthly period. The noise level has reduced over time at Zone 19 of Haroa block. In WTP site Rajarhat it is seen that the trend is improving which accounts for lower noise level. Moreover, the present noise level is well below the industrial limit.

121. Noise producing activities should be limited near schools and healthcare facilities during working hours. Accordingly, instruction has been given to contractors.

263 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

122. During Construction, air quality, noise level and water quality monitoring will be continued as per Environment Management and Monitoring Plan. All monitoring expenses will be borne by contractors from their project Health safety monitoring budget

123. All original test certificates are available in DSISC/PIU office as back-up and result scanned copy attached as Appendix I - 13.

II. Environmental Monitoring Results of Bankura Packages and observations

124. Environmental monitoring results and observations of different packages under Bankura District are given below.

Table 28A: Ambient Air Quality Monitoring Results- Bankura- During Construction Parameters Site Date of Site Location PM10 PM2.5 CO SO2 NO2 no. Testing (μg/m3) (μg/m3) (mg/m3) (μg/m3) (μg/m3) Contract Package: WBDWSIP/DWW/NCB/BK/01/2017-18 No during construction monitoring conducted as work not yet started Contract Package: WBDWSIP/DWW/NCB/BK/02A/2018-19 1 October, Hatagram OHSR 60.76 30.33 0.319 7.64 37.66 2 2020 During Shiromanipur OHSR 65.4 32.01 0.446 7.89 37.96 3 Construction Chaukighata OHSR 58.4 28.64 0.354 7.56 37.35 4 (2nd time) Nayekhir OHSR 71.57 36.22 0.516 8.06 38.27 5 Golakpur OHSR 66.33 31.17 0.482 7.98 37.66 Contract Package: WBDWSIP/DWW/NCB/BK/02B/2018-19 1 October, Chandabila OHSR 77.88 39.59 0.612 8.31 38.57 2 2020 During Dhengasimul OHSR 81.39 40.44 0.596 8.73 38.88 3 Construction Fulmati OHSR 71.9 36.65 0.533 8.06 38.27 4 (2nd time) Manipur OHSR 69.44 35.38 0.478 8.06 37.96 5 Chakmajuri OHSR 64.82 31.59 0.415 7.98 37.66 Contract Package: WBDWSIP/DWW/NCB/BK/03/2018-19 1 July, 2020 WTP area, 82.41 39.6 0.642 8.82 40.41 During Radhamadhabpur 2 Construction Intake point, Natungram 73.81 36.22 0.498 8.48 39.49 (2nd time) Contract Package: WBDWSIP/DWW/NCB/BK/04/2018-19 1 October, Haribhanga OHSR 68.34 32.86 0.354 7.81 37.96 2 2020 During Lakhayara OHSR 62.46 31.17 0.302 7.47 37.35 3 Construction Lachmanpur OHSR 70.43 36.22 0.442 8.14 38.27 4 (2nd time) Pairasol OHSR 58.47 28.64 0.288 7.22 37.04 5 Purbatore OHSR 65.15 33.7 0.375 7.64 37.35 6 Kallapur OHSR 72.6 37.91 0.416 7.89 37.66 7 Bankadaha OHSR 56.46 27.8 0.245 7.3 36.64 8 Sarangapur OHSR 74.24 38.33 0.479 8.14 38.27 9 Rajamela OHSR 53.17 25.7 0.258 7.14 36.43 10 Ramkanali OHSR 62.13 30.75 0.325 7.56 37.04 National Ambient Air Quality Standard 100 60 2 80 80 WHO standard 100 50 - 50* 40* *Interim target 2 Note: National level Central Pollution Control Board’s (Govt. of India) guideline/ protocol used for sampling, For analysis. INDIAN STANDARD IS 5182 and USEPA CFR 40 (International protocol) used for analysis

Table 28B: Noise Level Monitoring Data- Bankura- During Construction Site No Date of Testing Site Location Leq dB(A) Day Time Night Time Contract Package: WBDWSIP/DWW/NCB/BK/01/2017-18 Monitoring not conducted during this report period

264 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Site No Date of Testing Site Location Leq dB(A) Day Time Night Time Contract Package: WBDWSIP/DWW/NCB/BK/02A/2018-19 1 October, 2200, During Saluka (Saldiha) Pipeline 54.6 37.5 2 Construction (2nd time) Surulia Pipeline 48.9 37.2 3 Chakoltor Pipeline 53.5 40.4 4 Golakpur Pipeline 52.5 33.3 5 Bholarkhap Pipeline 53.3 39.4 6 Hatagram OHSR Site 51.9 40.0 7 Siromonipur OHSR Site 57.3 44.7 8 Choukighata OHSR Site 50.8 55.0 9 Nayekhir OHSR Site 59.9 54.6 10 Golakpur OHSR Site 55.8 53.5 Contract Package: WBDWSIP/DWW/NCB/BK/02B/2018-19 1 October, 2020, During Bhutamaheshpur pipeline 49.0 37.0 2 Construction (2nd time) Bindalaxmanpur pipeline 46.5 35.8 3 Saharghati pipeline 56.4 41.6 4 Panchmura pipeline 50.2 38.3 5 Pedda pipeline 49.2 35.4 6 Chandabila OHSR site 52.3 40.4 7 Dhangashimul OHSR site 48.7 37.9 8 Fulmati OHSR site 53.5 42.2 9 Manipur OHSR site 52.9 45.1 10 Chakmajuri OHSR site 51.7 42.6 Contract Package: WBDWSIP/DWW/NCB/BK/03/2018-19 1 July, 2020 WTP Site, Basudevpur 48.0 37.4 2 During Construction (2nd Intake point, Natungram 50.2 39.1 3 time) School, near intake point 49.6 39.0 4 Hospital, near WTP area 51.6 39.4 Contract Package: WBDWSIP/DWW/NCB/BK/04/2018-19 1 October, 2020, During Lakhiyara Pipeline Site 56.4 41.6 2 Construction (2nd time) Purbator Pipeline Site 53.9 42.6 3 Amarkanon Pipeline Site 55.7 45.1 4 Kapista Pipeline Site 50.1 38.7 5 Benagari Pipeline site 46.5 35.8 6 Pirraboni Pipeline Site 49.0 37.0 7 Pirraboni OHRS Site 56.4 41.6 8 Gobindadham OHSR Site 49.2 35.4 9 Haribhanga OHSR Site 52.3 40.4 10 Lakhiyara OHSR Site 50.2 38.3 11 Lachmanpur OHSR Site 52.9 45.1 12 Pairasol OHSR Site 48.7 37.9 13 Purbator OHSR Site 53.5 42.2 14 Kallapur OHSR Site 51.7 40.2 15 Sarangapur OHSR site 52.5 34.3 16 Rajamela OHSR site 53.5 40.4 17 Ramkanali OHSR Site 53.3 39.7 18 Ranganathpur Pipeline Site 51.1 36.0 19 Bankadaha OHSR Site 52.4 37.2 20 Haribhanga Pipeline Site 42.3 38.4 Code/Category Leq Day Time dB(A) - Standard Leq Night Time dB(A) - Standard A/Industrial 75 70 B/Commercial 65 55 C/Residential 55 45 D/Ecological- 50 40 Sensitive Note: National level Central Pollution Control Board’s, CPCB’s (Govt. of India) guideline/ protocol used for sampling

265 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Table 28C: Ground Water Quality Monitoring Data for BK/02A- Bankura- During Construction Sl. No. Parameters Unit Contract Package: WBDWSIP/DWW/NCB/BK/02A/2018-19 National Standards for Drinking Water- Results (During Construction) BIS 10500-2012 Location: Location: Location: Location: Location: Acceptable limit Hatagram Nayekhir Chaukighata Golakpur Siromanipur (Maximum

permissible limit) Date of Date of Date of Date of Date of sampling sampling sampling sampling sampling 12.10.20 14.10.20 13.10.20 15.10.20 12.10.20 1 pH - 7.18 7.47 7.48 7.46 7.42 6.5-8.5 2 Colour Hazan 1.0 1.0 1.0 1.0 1.0 5 (15) Unit 3 Taste and Odor - Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable 4 Turbidity NTU 5.98 1.22 0.68 11.68 1.84 1 (5) 5 Conductivity µS/cm 386.49 548.65 1886.49 1598.65 1193.24 6 TDS Mg/l 286 406 1396 1183 883 500 (2000) 7 Total Mg/l 126.72 233.64 704 431.64 376.2 200 (600) Hardness 8 Chloride Mg/l 27.96 8.68 242.99 231.42 160.06 250 (1000) 9 Alkalinity Mg/l 86.0 324 292 232 146 200 (600) 10 Sulphate Mg/l 35.07 4.72 111.23 45.69 65.13 200 (400) 11 Nitrate Mg/l 4.6 4.0 8.4 7.5 7.8 45 12 Fluoride Mg/l BDL BDL BDL BDL BDL 1 (1.5) 13 Calcium Mg/l 35.71 57.14 144.43 144.43 119.04 75(200) 14 Magnesium Mg/l 9.14 22.13 83.5 17.32 19.25 30(100) 15 Iron Mg/l 0.17 BDL BDL BDL BDL 0.3 16 Residual Mg/l Nil Nil Nil Nil Nil 0.2(1.0) Free Cl 17 Ammonia Mg/l BDL BDL BDL BDL BDL 0.5 18 Chromium Mg/l BDL BDL BDL BDL BDL 0.05 19 Copper Mg/l BDL BDL BDL BDL BDL 0.05 (1.5) 20 Lead Mg/l BDL BDL BDL BDL BDL 0.01 21 Arsenic Mg/l BDL BDL BDL BDL BDL 0.01 (0.05) 22 Zinc Mg/l BDL BDL BDL BDL BDL 5 (15) 23 Mercury Mg/l BDL BDL BDL BDL BDL 0.001 24 Manganese Mg/l BDL BDL BDL BDL BDL 0.1 (0.3) 25 Cadmium Mg/l BDL BDL BDL BDL BDL 0.03(0.2) 26 Nickel Mg/l BDL BDL BDL BDL BDL 0.02 27 Aluminium Mg/l BDL BDL BDL BDL BDL 0.03 (0.2) 28 Barium Mg/l BDL BDL BDL BDL BDL 0.7 29 Boron Mg/l BDL BDL BDL BDL BDL 0.5(1.0) 30 Phenolic Comp. Mg/l BDL BDL BDL BDL BDL 0.001(0.002)

266 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Sl. No. Parameters Unit Contract Package: WBDWSIP/DWW/NCB/BK/02A/2018-19 National Standards for Drinking Water- Results (During Construction) BIS 10500-2012 Location: Location: Location: Location: Location: Acceptable limit Hatagram Nayekhir Chaukighata Golakpur Siromanipur (Maximum permissible limit) Date of Date of Date of Date of Date of sampling sampling sampling sampling sampling 12.10.20 14.10.20 13.10.20 15.10.20 12.10.20 31 Biphenyl Mg/l BDL BDL BDL BDL BDL 0.005 32 Aromatic Mg/l BDL BDL BDL BDL BDL 0.001 Hydrocarbon 33 DDT µg/l BDL BDL BDL BDL BDL 1.0 34 E-Coli MPN/100 ND ND ND ND ND Must not be detectable ml in 100 ml sample 35 Total MPN/ 100 ND ND ND ND ND Must not be detectable Coliform ml in 100 ml sample

Table 28D: Ground Water Quality Monitoring Data for BK/02B- Bankura- During Construction Sl. No. Parameters Unit Contract Package: WBDWSIP/DWW/NCB/BK/02B/2018-19 National Standards for Drinking Results (During Construction) Water-BIS Location: Location: Location: Location: Location: 10500-2012 Fulmati Manipur Dhengasimul Chakmajuri Chandabila Acceptable limit (Maximum Date of sampling Date of sampling Date of sampling Date of sampling Date of sampling permissible 10.10.20 11.10.20 10.10.20 11.10.20 09.10.20 limit) 1 pH - 7.15 7.13 7.4 7.33 6.98 6.5-8.5 2 Colour Hazan 1.0 1.0 1.0 1.0 1.0 5 (15) Unit 3 Taste and - Agreeable Agreeable Agreeable Agreeable Agreeable Agreeable Odor 4 Turbidity NTU 4.11 35.6 13.31 2.81 6.07 1 (5) 5 Conductivity µS/cm 201.35 272.97 471.62 182.43 131.08 6 TDS Mg/l 149 202 349 135 130 500 (2000) 7 Total Mg/l 69.3 91.08 47.52 97 200 (600) Hardness 67.32 8 Chloride Mg/l 4.8 36.64 6.75 8.68 7.71 250 (1000) 9 Alkalinity Mg/l 60.0 56 90.0 46 32 200 (600) 10 Sulphate Mg/l 13.56 12.09 3.67 1.52 2.04 200 (400) 11 Nitrate Mg/l 2.6 2.6 3.2 2.2 2.0 45 12 Fluoride Mg/l BDL BDL BDL BDL BDL 1 (1.5) 13 Calcium Mg/l 20.63 22.22 26.98 15.87 10.32 75(200) 14 Magnesium Mg/l 3.85 3.37 5.77 1.92 1.92 30(100)

267 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Sl. No. Parameters Unit Contract Package: WBDWSIP/DWW/NCB/BK/02B/2018-19 National Standards for Drinking Results (During Construction) Water-BIS Location: Location: Location: Location: Location: 10500-2012 Fulmati Manipur Dhengasimul Chakmajuri Chandabila Acceptable limit (Maximum Date of sampling Date of sampling Date of sampling Date of sampling Date of sampling permissible 10.10.20 11.10.20 10.10.20 11.10.20 09.10.20 limit) 15 Iron Mg/l 0.17 0.22 0.15 BDL BDL 0.3 16 Residual Mg/l Nil Nil Nil Nil Nil 0.2(1.0) Free Cl 17 Ammonia Mg/l BDL BDL BDL BDL BDL 0.5 18 Chromium Mg/l BDL BDL BDL BDL BDL 0.05 19 Copper Mg/l BDL BDL BDL BDL BDL 0.05 (1.5) 20 Lead Mg/l BDL BDL BDL BDL BDL 0.01 21 Arsenic Mg/l BDL BDL BDL BDL BDL 0.01 (0.05) 22 Zinc Mg/l BDL BDL BDL BDL BDL 5 (15) 23 Mercury Mg/l BDL BDL BDL BDL BDL 0.001 24 Manganese Mg/l BDL BDL BDL BDL BDL 0.1 (0.3) 25 Cadmium Mg/l BDL BDL BDL BDL BDL 0.03(0.2) 26 Nickel Mg/l BDL BDL BDL BDL BDL 0.02 27 Aluminium Mg/l BDL BDL BDL BDL BDL 0.03 (0.2) 28 Barium Mg/l BDL BDL BDL BDL BDL 0.7 29 Boron Mg/l BDL BDL BDL BDL BDL 0.5(1.0) 30 Phenolic Mg/l BDL BDL BDL BDL BDL 0.001(0.002) Comp. 31 Biphenyl Mg/l BDL BDL BDL BDL BDL 0.005 32 Aromatic Mg/l BDL BDL BDL BDL BDL 0.001 Hydrocarbon 33 DDT µg/l BDL BDL BDL BDL BDL 1.0 34 E-Coli MPN/100 ND ND ND ND ND Must not be ml detectable in 100 ml sample 35 Total MPN/ ND ND ND ND ND Must not be Coliform 100 detectable in ml 100 ml sample

268 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Table 28E: Ground Water Quality Monitoring Data for BK/04- Bankura- During Construction Sl.N Parameters Unit Contract Package: WBDWSIP/DWW/NCB/BK/04/2018-19 o Results (During Construction)

.

(Maximum permissible limit)

Acceptable limit

Bankadaha site OHSR (Oct, 2020) Kallapur site OHSR (Oct, 2020) Lachmanpur site OHSR (Oct, 2020) Lakhiyara site OHSR (Oct, 2020) Pairasol site OHSR (Oct, 2020) Purbator site OHSR (Oct, 2020) Rajamela site OHSR (Oct, 2020) Ramkanali site OHSR (Oct, 2020) Sarangapur site OHSR (Oct, 2020) Haribhanga site OHSR (Oct, 2020) National Standards Drinking for Water- 10500-2012 BIS 1. Turbidity NTU 0.6 0.89 9.31 1.54 0.55 0.42 3.4 2.27 4.37 0.37 1 (5) 2. pH - 7.25 7.16 7.41 7.48 7.45 7.47 7.5 7.19 7.32 7.49 6.5-8.5 3. Colour Hazen 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 5 (15) Unit 4. Taste and - Agreeab Agreeable Agreeable Agreeabl Agreeable Agreeable Agreeabl Agreeabl Agreeabl Agreeab Agreeable Odor le e e e e le 5. TDS Mg/l 424 449.0 458.0 728.0 1171.0 607.0 663.0 481.0 468.0 678.0 500 (2000) 6. Iron Mg/l BDL BDL BDL BDL 0.22 BDL BDL BDL BDL BDL 0.3 7. Manganese Mg/l BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL 0.1 (0.3) 8. Arsenic Mg/l BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL 0.01 (0.05) 9. Cadmium Mg/l BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL 0.003 10. Chromium Mg/l BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL 0.05 12. Fluoride Mg/l BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL 1 (1.5) 13. Lead Mg/l BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL 0.01 14. Ammonia Mg/l BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL 0.5 15. Chloride Mg/l 6.17 17.48 8.22 51.4 200.47 10.8 39.07 49.35 8.22 47.29 250 (1000) 16. Sulphate Mg/l 13.55 6.64 18.14 53.46 66.12 21.19 31.99 14.14 8.4 20.9 200 (400) 17. Nitrate Mg/l 2.6 3.8 3.4 7.2 9.0 5.6 5.2 4.7 3.0 5.8 45 18. Copper Mg/l BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL 0.05 (1.5) 19. Total Mg/l 79.2 39.6 106.92 209.88 564.3 237.6 269.28 114.84 73.26 285.12 200 (600) Hardness 20. Calcium Mg/l 23.81 11.11 31.74 65.07 182.52 68.25 68.25 38.09 22.22 77.77 75 (200) 21. Magnesium Mg/l 4.81 2.84 6.74 11.55 26.46 16.35 24.06 4.81 4.33 22.13 100 22. Zinc Mg/l BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL 5 (15) 23. Mercury Mg/l BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL 0.001 24. Aluminium Mg/l BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL 0.1 (0.3)

25. Residual Mg/l Nil Nil Nil Nil Nil Nil Nil Nil Nil Nil 0.2 Chlorine

269 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Sl.N Parameters Unit Contract Package: WBDWSIP/DWW/NCB/BK/04/2018-19 o Results (During Construction)

.

(Maximum permissible limit)

Acceptable limit

Bankadaha site OHSR (Oct, 2020) Kallapur site OHSR (Oct, 2020) Lachmanpur site OHSR (Oct, 2020) Lakhiyara site OHSR (Oct, 2020) Pairasol site OHSR (Oct, 2020) Purbator site OHSR (Oct, 2020) Rajamela site OHSR (Oct, 2020) Ramkanali site OHSR (Oct, 2020) Sarangapur site OHSR (Oct, 2020) Haribhanga site OHSR (Oct, 2020) National Standards Drinking for Water- 10500-2012 BIS 26. E-Coli MPN/ Nil Nil Nil Nil Nil Nil Nil Nil Nil Nil Must not be 100 ml detectable in 100 ml sample 27. Total Coliform MPN/ Nil Nil Nil Nil Nil Nil Nil Nil Nil Nil Must not be 100 ml detectable in 100 ml sample

Table 28F: Surface Water Quality Monitoring data–PKG BK/01, Bankura- Baseline Sl. No. Parameters Unit Location: Intake Point (Mukutmanipur Category- A Category-B Category- C Category-D Category-E Reservoir) Date of sampling- 18.08.20 1. pH (max) (min-6.5) 7.4 8.5 8.5 8.5 8.5 8.5 2. DO Mg/l 5.85 6 5 4 4 -- (minimum) 3. BOD Mg/l 2.6 2 3 3 -- -- 0 (3D, 27 C) 4. O & G Mg/l 1.5 -- -- 0.1 0.1 -- 5. Total Mg/l 72 300 ------Hardness as CaCO3 6. Chloride as Cl Mg/l 10.76 250 -- 600 -- 600

7. Nitrate as NO3 Mg/l <1.0 20 -- 50 -- -- 8. Fluorides as F Mg/l <0.05 1.5 1.5 1.5 -- --

9. Turbidity NTU 0.45 ------10. COD Mg/l 12.34 ------11. Total Alkalinity Mg/l 76 ------

12 Total Coliform MPN/100 ml Not Detected

13 Faecal coliform MPN/100 ml Not Detected

270 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Table 28G: Surface Water Quality Monitoring data –PKG BK/02A, Bankura- During Construction Sl. No. Parameters Unit Contract Package: WBDWSIP/DWW/NCB/BK/02A/2018-19 Surface Water Quality Standards (as per IS: Results (During Construction) 2296) Location: Location: Location: Location: Location:

Siromanipur Golakpur Chaukighata Nayekhir Hatagram

E E D D Date of Date of Date of Date of Date of B

sampling: sampling: sampling: sampling: sampling:

Category- Category- 12.10.20 15.10.20 13.10.20 14.10.20 12.10.20 Category- 1. pH (max) (min-6.5) 7.34 7.52 7.46 7.5 7.49 8.5 8.5 8.5 2. DO (minimum) Mg/l 4.36 4.86 5.77 5.57 5.16 5 4 -- 3. BOD (3D, 270 C) Mg/l 8.0 7.0 <5.0 <5.0 5.0 3 -- -- 4. O & G Mg/l <3.0 <3.0 <3.0 <3.0 <3.0 -- 0.1 -- 5. Total Hardness as Mg/l 39.6 89.1 39.6 49.5 110.88 ------CaCO3 6. Chloride as Mg/l 7.71 33.75 10.61 8.68 17.36 -- -- 600 Cl 7. Nitrate as Mg/l 6.5 7.2 6.0 5.4 6.2 ------NO3 8. Fluorides as Mg/l BDL BDL BDL BDL BDL 1.5 -- -- F 9. Total Coliforms MPN/100 ml ND ND ND ND ND 500 -- -- 10. Fecal Coliforms MPN/100 ml ND ND ND ND ND ------11. Turbidity NTU 33.9 10.88 7.25 13.25 19.79 ------12. COD Mg/l 70.56 60.48 40.32 50.4 59.52 ------13. Total Alkalinity Mg/l 50.0 94.0 48.0 54.0 98.0 ------

Table 28H: Surface Water Quality Monitoring data –PKG BK/02B, Bankura- During Construction Sl. No. Parameters Unit Contract Package: WBDWSIP/DWW/NCB/BK/02B/2018-19 Surface Water Quality Results (During Construction) Standards (as per IS: 2296) Location: Location: Location Location Location Manipur Fulmati :Chakmajuri :Dhengasimul :Chandabila Date of Date of Date of Date of Date of sampling: sampling: sampling: Sampling: sampling:

11.10.20 10.10.20 11.10.20 10.10.20 10.10.20

Category-E Category-D Category-B 1. pH (max) (min-6.5) 7.17 6.94 6.96 6.96 6.99 8.5 8.5 8.5 2. DO Mg/l 4.25 4.56 4.05 4.66 5.07 5 4 -- (minimum) 3. BOD Mg/l 6.0 <5.0 7.0 <5.0 <5.0 3 -- -- (3D, 270 C) 4. O & G Mg/l <3.0 <3.0 <3.0 <3.0 <3.0 -- 0.1 --

271 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Sl. No. Parameters Unit Contract Package: WBDWSIP/DWW/NCB/BK/02B/2018-19 Surface Water Quality Results (During Construction) Standards (as per IS: 2296) Location: Location: Location Location Location Manipur Fulmati :Chakmajuri :Dhengasimul :Chandabila Date of Date of Date of Date of Date of sampling: sampling: sampling: Sampling: sampling:

11.10.20 10.10.20 11.10.20 10.10.20 10.10.20

Category-E Category-E Category-D Category-D Category-B 5. Total Hardness Mg/l 71.28 29.7 55.44 33.66 29.7 ------as CaCO3 6. Chloride as Mg/l 3.86 4.82 4.8 22.18 10.61 -- -- 600 Cl 7. Nitrate as Mg/l 4.6 3.8 5.4 6.0 5.4 ------NO3 8. Fluorides as Mg/l BDL BDL BDL BDL BDL 1.5 -- -- F 9. Total Coliforms MPN/100 ND ND ND ND ND 500 -- -- ml 10. Fecal MPN/100 ND ND ND ND ND ------Coliforms ml 11. Turbidity NTU 5.31 19.6 65.8 20.1 31.6 ------12. COD Mg/l 60.48 40.32 60.0 50.4 40.0 ------13. Total Mg/l 82.0 34.0 58.0 42.0 40.0 ------Alkalinity

Table 28J: Monthly Surface Water Quality Monitoring data PKG BK/03, Bankura- During Construction Sl. Parameters Unit Contract Package: WBDWSIP/DWW/NCB/BK/03/2018-19 Surface Water Quality No. Location: Intake point (Damodar River) Standards (as per IS: 2296)

Results (During Construction) Date of Date of Date of Date of

Sampling: Sampling: Sampling: Sampling:

E E

B B C D 16.07.20 19.08.20 12.09.20 10.10.20 A

(JULY) (AUGUST) (SEPTEMBER) (OCTOBER)

Category- Category- Category-

Category- Category-

1. pH (max) (min-6.5) 7.08 7.03 7.33 7.03 8.5 8.5 8.5 8.5 8.5 2. DO Mg/l 4.0 4.66 4.25 4.2 6 5 4 4 -- 3. BOD Mg/l <5.0 7.0 8.0 <5.0 2 3 3 -- -- (3D, 270 C) 4. O & G Mg/l <3.0 3.2 3.4 <3.0 -- -- 0.1 0.1 -- 5. Total Mg/l 93.1 87.4 91.2 102.96 300 ------Hardness as

272 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Sl. Parameters Unit Contract Package: WBDWSIP/DWW/NCB/BK/03/2018-19 Surface Water Quality No. Location: Intake point (Damodar River) Standards (as per IS: 2296)

Results (During Construction) Date of Date of Date of Date of

Sampling: Sampling: Sampling: Sampling:

E E

B B C D 16.07.20 19.08.20 12.09.20 10.10.20 A

(JULY) (AUGUST) (SEPTEMBER) (OCTOBER)

Category- Category- Category-

Category- Category-

CaCO3 6. Chloride as Mg/l 7.71 7.71 9.64 7.71 250 -- 600 -- 600 Cl 7. Nitrate as Mg/l 3.8 3.4 2.6 3.2 20 -- 50 -- -- NO3 8. Fluorides as Mg/l BDL BDL BDL BDL 1.5 1.5 1.5 -- -- F 9. Total Coliforms MPN/100 ND ND ND ND 50 500 5000 -- -- ml 10. Fecal MPN/100 ND ND ND ND ------Coliforms ml 11. Turbidity NTU 5.6 18.82 3.34 3.93 ------12. COD Mg/l 38.64 40.48 50.0 40.48 ------13. Total Mg/l 78.0 86.0 98.0 104.0 ------Alkalinity (Due to COVID 19 pandemic Lockdown – monitoring not done during April to June 2020)

Table 28K: Surface Water Quality Monitoring data –PKG BK/ 04, Bankura- During Construction Parameter Unit Contract Package: WBDWSIP/DWW/NCB/BK/04/2018-19 Standard Results (During Construction ) as per IS Location: Location: Location: Location: Location: Location: Location: Location: Location: Location: 2296:1982 Bankadaha Haribhanga Kallapur Lachmanpur Lakhayara Pairasol Purbatore Rajamela Ramkanali Sarangapur Category- Date of Date of Date of Date of Date of Date of Date of Date of Date of Date of B sampling: sampling: sampling: sampling: sampling: sampling: sampling: sampling: sampling: sampling: 21.10.20 19.10.20 20.10.20 19.10.20 19.10.20 20.10.20 20.10.20 21.10.20 22.10.20 21.10.20 pH 6.89 7.04 7.24 7.08 7.34 7.21 7.03 7.01 7.32 7.18 8.5 Turbidity NTU 36.48 10.57 9.5 12.85 4.62 2.16 1.48 5.12 13.67 0.96 - DO mg/l 5.06 4.76 5.06 4.2 4.76 4.36 4.66 4.96 4.56 5.17 5 BOD mg/l <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 <5.0 3 COD mg/l 50.4 39.68 40.32 49.6 49.6 39.68 40.32 50.0 40.0 30.24 - Hardness mg/l 33.66 49.5 47.52 47.52 104.94 108.9 67.32 41.58 59.4 71.28

273 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Parameter Unit Contract Package: WBDWSIP/DWW/NCB/BK/04/2018-19 Standard Results (During Construction ) as per IS Location: Location: Location: Location: Location: Location: Location: Location: Location: Location: 2296:1982 Bankadaha Haribhanga Kallapur Lachmanpur Lakhayara Pairasol Purbatore Rajamela Ramkanali Sarangapur Category- Date of Date of Date of Date of Date of Date of Date of Date of Date of Date of B sampling: sampling: sampling: sampling: sampling: sampling: sampling: sampling: sampling: sampling: 21.10.20 19.10.20 20.10.20 19.10.20 19.10.20 20.10.20 20.10.20 21.10.20 22.10.20 21.10.20 Alkalinity mg/l 36.0 52.0 50.0 50.0 108.0 112.0 68.0 44.0 60.0 72.0 - Chloride mg/l 21.59 15.42 11.31 14.39 22.62 11.31 5.14 8.22 26.73 9.25 - Fluoride mg/l BDL BDL BDL BDL BDL BDL BDL BDL BDL BDL 1.5

NO3 mg/l 9.4 7.9 7.0 7.4 8.6 7.3 6.4 6.4 8.0 6.7 50 O&G mg/l <3.0 <3.0 <3.0 <3.0 <3.0 <3.0 <3.0 <3.0 <3.0 <3.0 - Total Coliform ND ND ND ND ND ND ND ND ND ND 500 (MPN/ 100 ml) Faecal Coliform ND ND ND ND ND ND ND ND ND ND ND (MPN/100 ml) NOTE: ➢ Category A-Drinking water without conventional treatment but after disinfection. ➢ Category B- Water for outdoor bathing ➢ Category C-Drinking water with conventional treatment followed by disinfection ➢ Category D- Water for fish culture and wild life propagation ➢ Category E- Water for irrigation, industrial cooling and controlled waste disposal

Table 28L: Soil Quality Monitoring data –PKG BK/02A, Bankura- During Construction Sl. No. Parameters Unit Contract Package: WBDWSIP/DWW/NCB/BK/02A/2018-19 Results (During Construction) Location: Location: Location: Location: Location: Hatagram Nayekhir Chaukighata Golakpur Siromonipur Date of sampling: Date of Date of sampling: Date of Date of sampling: 12.10.20 sampling: 13.10.20 Sampling: 12.10.20 14.10.20 14.10.20 1. pH -- 6.94 7.06 7.12 7.02 6,65 2. Elec. Conductivity µS/cm 428 402 429 456 412 3. Moisture % 11 9.8 10.2 12 9.2 4. Permeability cm/S 10-5 to 10-3 10-9 to 10-6 10-9 to 10-6 10-5 to 10-3 10-3 to 10 5. Texture -- Clay loam Clay loam Clay loam Clay loam Clay loam 6. Calcium as Ca mg/kg 72,24 88.68 96.18 88.56 74.16 7. Magnesium as Mg mg/kg 32.28 34.04 35.46 31.24 28 8. Nitrogen as N Kg/hectare 480.5 446.52 472.1 435.14 450.22 9. Potassium as K mg/kg 74.52 68.32 74.8 80.36 71.18

274 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Sl. No. Parameters Unit Contract Package: WBDWSIP/DWW/NCB/BK/02A/2018-19 Results (During Construction) Location: Location: Location: Location: Location: Hatagram Nayekhir Chaukighata Golakpur Siromonipur Date of sampling: Date of Date of sampling: Date of Date of sampling: 12.10.20 sampling: 13.10.20 Sampling: 12.10.20 14.10.20 14.10.20 10. Sodium as Na mg/kg 41.98 38.15 41.39 45.62 40.26 11. Phosphorous as P mg/kg 0.78 0.66 0.81 1.08 0.77 12. Organic Matter % 4.8 4.2 4.8 5.2 4.4 13. Oil & Grease mg/kg 1.16 0.94 0.87 1.02 0.65

Table 28M: Soil Quality Monitoring data –PKG BK/02B, Bankura- During Construction Sl. No. Parameters Unit Contract Package: WBDWSIP/DWW/NCB/BK/02B/2018-19 Results (During Construction) Location: Location: Location: Location: Location: Fulmoti Monipur Dhengasimul Chandabila Chakmajuriprasadpur Date of Date of Date of sampling: Date of Date of sampling: sampling: sampling: 10.10.20 Sampling: 09.10.20 11.10.20 10.10.20 11.10.20 1. pH -- 6.9 7.02 7.22 7.15 6.97 2. Elec. Conductivity µS/cm 430.0 455.0 469.0 445.0 418.0 3. Moisture % 8.8 8.3 9.8 10.6 9.0 4. Permeability cm/S 10-5 to 10-3 10-5 to 10-3 10-9 to 10-6 10-9 to 10-6 10-9 to 10-6 5. Texture % Sandy Clay Loam Clay Loam Sandy Loam Sandy Loam Sandy Loam 6. Calcium as Ca mg/kg 74.16 68.39 88.92 91.63 77.84 7. Magnesium as Mg mg/kg 28.0 26.22 32.26 34.0 27.61 8. Nitrogen as N Kg/Hectare 464.22 438.14 470.18 485.16 437.82 9. Potassium as K mg/kg 74.96 70.35 80.49 88.44 79.16 10. Sodium as Na mg/kg 42.29 38.92 47.65 50.02 44.26 11. Phosphate as PO4 mg/kg 0.89 0.82 1.11 1.26 0.9 12. Organic Matter % 4.6 4.2 5.0 5.2 4.6 13. Oil & Grease mg/kg 0.6 0.4 0.92 0.8 0.64

275 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to October 2020)

Table 28N: Soil Quality Monitoring data –PKG BK/04, Bankura- During Construction Sl. Parameters Unit Contract Package: WBDWSIP/DWW/NCB/BK/04/2018-19 N Results (During Construction) o

.

Location:Haribhanga Dateof sampling: 20.10.20 Location:Lakhayara Dateof sampling: Location:Lachmanpur Dateof sampling: 20.10.20 Location: Pairasol Dateof Sampling: 21.10.20 Location:Purbator Date of 21.10.20 sampling: Location:Kallapur Dateof Sampling: 21.10.20 Location:Bankadaha Dateof Sampling: 22.10.20 Location: Sarangapur Dateof Sampling: 22.10.20 Location:Rajamela Dateof Sampling: 22.10.20 Location:Ramkanali Dateof Sampling: 23.10.20

20.10.20

1. pH -- 6.77 6.52 6.9 7.06 6.53 6.6 7.24 7.03 6.77 6.58 2. Conductivity µS/cm 439 410 436 452 390 378 410 419 382 364 3. Moisture % 8.0 7.8 7.5 7.9 7.2 7.6 8.2 7.6 7.0 6.6 4. Permeability cm/S 10-3 to 10- 10-3 to 10-6 10-3 to 10-3 to 10-3 to 10-3 to 10-3 to 10-3 to 10-3 to 10-3 to 9 10-6 10-9 10-9 10-9 10-6 10-6 10-6 10-6 5. Texture -- Clay loam Clay loam Clay Clay Clay Clay Clay Clay Loam Clay Clay Loam Loam Loam Loam Loam Loam Loam 6. Calcium as mg/kg 68.32 62.44 71.23 74.12 62.52 60.32 71.56 74 63.54 59.08 Ca 7. Magnesium mg/kg 24.56 22.82 27.14 28.56 21.36 20.45 25.74 28.94 22.45 20.85 as Mg 8. Nitrogen as N Kg/hectare 428.16 407.15 415.2 388 372 366 428 435 398 386 9. Potassium as mg/kg 66.74 62 66.72 70.24 63.96 60.78 67.28 69.24 63.14 61.44 K 10. Sodium as mg/kg 38.12 36.65 40.52 38.44 35.28 32.41 39.16 42.35 37.02 35.83 Na 11. Phosphorous mg/kg 0.68 0.71 0.82 0.78 0.63 0.57 0.64 0.68 0.67 0.62 as P 12. Organic % 5.0 4.6 5.2 4.8 4.2 4.4 5.2 4.8 4.2 4.6 Matter 13. Oil & Grease mg/kg 0.53 0.5 0.46 0.53 0.44 0.48 0.56 0.5 0.48 0.46

276 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Dec 2020)

Comparative Analysis of Monitoring Results

125. The monitoring results obtained from same locations over time have been compared in the charts are presented below.

Air Quality

Value of PM10 and PM2.5 for BK/02A 120

100

80

60

40

20

0 Golakpur March 2020 Golakpur October 2020

PM10 (µg/m3) PM2.5 (µg/m3) NAAQS for PM10 NAAQS for PM2.5

Value of PM10 and PM2.5 for BK/02B 120

100

80

60

40

20

0 Chandabila Nov 2019 Chandabila Oct 2020

PM10 (µg/m3) PM2.5 (µg/m3) NAAQS for PM10 NAAQS for PM2.5

277 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Dec 2020)

Value of PM10 and PM2.5 for BK/03 120

100

80

60

40

20

0 WTP_Baseline WTP_During Intake_Baseline Intake_During Construction (2nd) Construction(2nd)

PM10 (µg/m3) PM2.5 (µg/m3) NAAQS for PM10 NAAQS for PM2.5

Noise Quality

Noise Level Monitoring BK/02A 70 60 50 40 30 20 10 0 Choukighata Nayekhir Zone Bholarkhap Zone Golakpur Zone Chakoltor Zone Siromonipur Zone Zone

1st DC_Leq Day 1st DC_Leq Night 2nd DC_Leq Day 2nd DC_Leq Night STD (Leq Day) STD (Leq Night)

1st DC: First time during construction, 2nd DC: Second time during construction

278 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Dec 2020)

Noise Level Monitoring BK/02B 70 60 50 40 30 20 10 0 Bindalaxmanpur Zone Saharghati Zone Chandabila Zone

1st DC_Leq Day 1st DC_Leq Night 2nd DC_Leq Day 2nd DC_Leq Night STD (Leq Day) STD (Leq Night)

1st DC: First time during construction, 2nd DC: Second time during construction

Noise Level Monitoring BK/03 70 60 50 40 30 20 10 0 WTP Site Intake Site

Baseline_Leq Day Baseline_Leq Night 1st DC_Leq Day 1st DC_Leq Night 2nd DC_Leq Day 2nd DC_Leq Night STD (Leq Day) STD (Leq Night)

1st DC: First time during construction, 2nd DC: Second time during construction

279 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Dec 2020)

Noise Level Monitoring BK/04 60 50 40 30 20 10 0 Lakhiyara Zone Purbator Zone Ranganathpur Kapista Zone Lachchmanpur Sarangapur Zone Zone Zone

Baseline (Leq Day) Baseline (Leq Night) During Construction (Leq Day) During Construction (Leq Night) STD (Leq Day) STD (Leq Night)

Surface Water Quality

BOD value for BK/02A 8 7 6 5 4 3 2 1 0 Golakpur Golakpur Chaukighata Chaukighata Nayekhir Nayekhir (March 2020) (Oct 2020) (Nov 2019) (Oct 2020) (Nov 2019) (Oct 2020)

BOD (mg/L) CPCB Class B Std.

280 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Dec 2020)

BOD value for BK/02B 6

5

4

3

2

1

0 Chandabila (Nov 2019) Chandabila (Oct 2020)

BOD (mg/L) CPCB Class B Std.

BOD value for BK/03 9 8 7 6 5 4 3 2 1 0 Intake Intake (During Intake (During Intake (During Intake (During (Baseline) Dec Construction) Construction) Construction) Construction) 2019 July 2020 Aug 2020 Sep 2020 Oct 2020

BOD (mg/L) CPCB Class B Std.

BOD value for BK/04 7 6 5 4 3 2 1 0 Bankadaha (March 2020) Bankadaha (Oct 2020)

BOD (mg/L) CPCB Class B Std.

281 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Dec 2020)

126. By analysing the trends for PM10 and PM2.5 at the common monitoring locations reveals slightly higher concentration both at WTP and Intake point compared to baseline condition at BK/03, may be partially attributable to project activities along with regular vehicular movement. Mitigation measures like water sprinkling has recommended at those sites. However, the trends remain almost unchanged at common monitoring locations under BK/02A and BK/02B. There are no common monitoring locations under BK/04 during this report period. In overall PM10 and PM2.5 at all the locations are within the standard.

127. By analysing the trend in noise levels no such variations are observed at most of the common locations and results are within the limit considering the standard set for mixed zone (commercial zone). However, it shows a consistent increase in all BK/04 packages in day time where construction works are in progress at full pace. The results are slightly higher during day time considering standard set for residential areas. In all those cases, the project sites are located near vehicular road, which might be an additional cause of increasing noise level during day time. Mitigation measures are applied during construction time, as per site condition.

128. In all cases, surface water quality results were within prescribed limit except BOD level and can be classified as Category B, i.e. suitable for outdoor bathing.

129. From trend analysis, BOD concentrations are found higher in all cases while comparing to baseline/ previous conditions which may be due to post-monsoon influx on surface water quality and has no relation to project activities. However, necessary preventive measures are recommended as per EMP for protection surface water resources nearby to OHSR sites.

130. Ground water parameters were within the prescribed limit, except samples as collected from some locations under package BK/02A. At those locations’ concentrations of Turbidity, TDS, Hardness, Chloride and Calcium were high and sometime above the standard.

131. In all cases, soil quality results were within prescribed limit. In most places Sandy Loamy to Clay Loamy soils were found.

132. During Construction, air quality, noise level, soil and water quality monitoring will be continued as per Environment Management and Monitoring Plan. All monitoring expenses will be borne by contractors from their project Health safety monitoring budget

133. All original test certificates are available in DSISC office as back-up and result scanned copy (except soil) attached as Appendix II - 11.

III. Environmental Monitoring Results of East Medinipur Package and observation

134. Baseline as well as during construction environmental monitoring has been completed as per IEE. Monitoring results are submitted by contractor. All original test certificates are available in DSISC office as back-up and result scanned copy (except soil) attached as Appendix III - 11.

282 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Dec 2020)

Package no: East Medinipur- EM/01

Table29A: Ambient Air Monitoring Data (Package- EM/01)- Base line Sl. Station Village Name Study Area Date Parameters (Government Standards) No. Code PM10 PM2.5 CO SO2 NO2 (μg/m3) (μg/m3) (mg/m3) (μg/m3) (μg/m3) 1. AQ1 Intake well- Rural 06.07.2020 65.49 32.43 0.325 7.98 37.96 Mirpur Residential 2. AQ2 Totaberia Rural 08.07.2020 70.44 34.12 0.346 8.06 37.35 Residential 3. AQ3 WTP-Banbhera Rural 06.07.2020 73.73 34.96 0.377 8.23 38.27 Residential 4. AQ4 Haldi river side Rural 07.07.2020 58.85 27.8 0.218 7.3 36.74 Residential 5. AQ5 Magrajpur Rural 07.07.2020 62.26 30.33 0.282 7.64 37.05 Residential National Ambient Air Quality Standard 100 60 2 80 80 WHO Standard 100 50 - 50 -

Table 29B: Noise Monitoring Data (Package- EM/01)- Base line Sl. Station Village Name Study Area Date Leq dB (A) Day Leq dB (A) No. Code Time Night Time 1 N1 Intake well-Mirpur Residential 06.07.2020 53.96 52.26 2 N2 Totaberia Residential 23.07.2020 50.00 37.33 3 N3 WTP-Banbhera Residential 06.07.2020 52.46 45.25 4 N4 Haldi river side Residential 07.07.2020 46.31 53.57 5 N5 Magrajpur Residential 07.07.2020 49.86 51.13 Code/Category Leq Day Time dB(A) - Standard Leq Night Time dB(A) - Standard A/Industrial 75 70 B/Commercial 65 55 C/Residential 55 45 D/Ecological- 50 40 Sensitive Note: National level Central Pollution Control Board’s, CPCB’s (Govt. of India) guideline/ protocol used for sampling

283 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (Nov 2019 to April 2020)

Table 29C: Surface water monitoring result- Base line

Location Name Date Parameter pH Turbi Conduct TDS Total Chloride Dissolved BOD COD Oil & (25 dity ivity µs/ in Hardness as Cl in Oxygen mg/L mg/L Grease ºC) (NTU) cm mg/l as CaCO3 mg/l mg/L Mg/L in mg/l Rupnarayan river 09.07.2020 7.35 203 323.88 217 95 34.71 5.28 5.2 42.5 <3 (Intake-Mirpur) Rupnarayan river 09.07.2020 7.42 224 426.87 286 114 78.1 5.7 5.3 38 <3 (Totaberia) Acceptable Limit 6.5 1 -- 500 200 250 4.0 30.0 250.0 10.0 to N.T.U 8.5

284 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (Nov 2019 to April 2020)

Graphical presentation of results shown below.

PM10 concentration (EM/01) 120

100

80

60

40

20

0 AQ1 AQ2 AQ3 AQ4 AQ5

NAAQS PM10 (μg/m3)

PM2.5 concentration (EM/01) 70

60

50

40

30

20

10

0 AQ1 AQ2 AQ3 AQ4 AQ5

NAAQS PM2.5 (μg/m3)

285 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (Nov 2019 to April 2020)

Noise Monitoring Data (Package- EM/01) 60

50

40

30

20

10

0 Intake well-Mirpur Totaberia WTP-Banbhera Haldi river side Magrajpur

Leq dB (A) Day Time Leq dB (A) Night Time Leq Day Time dB(A) - Standard Leq Night Time dB(A) - Standard

Analyses of Results • Baseline monitoring as per IEE has been conducted in 5 locations. Among these five locations, the concentration of PM10 and 2.5 relatively higher at WTP and lower at Haldi rive side its due to the location of WTP and Haldi river. The WTP site is adjacent to the National highway and due to constant movement of vehicle the particle concentration is higher at this site. The Haldi river location is away from the busy traffic road and adjacent to the river and this is the main reason for low concentration of particle matter. • In this baseline report, it was observed that the night noise is higher than permissible limit except Totaberia. One of the reasons is the movement of heavy vehicle like trucks at nigh time. Day time noise was within the standard. • The result of surface water shows all the parameters are within the permissible limit

Table 29D: During construction ambient air monitoring data (package- EM/01) Sl. Station Village Name Study Area Date Parameters (Government Standards) No. Code PM10 PM2.5 CO SO2 NO2 (μg/m3) (μg/m3) (mg/m3) (μg/m3) (μg/m3) 1. AQ1 Intake well- Rural 31.10.2020 126 64 0.549 9.2 31.3 Mirpur Residential 2. AQ2 Totaberia Rural 31.10.2020 68 31 0.755 6.8 27.4 Residential 3. AQ3 WTP-Banbhera Rural 31.10.2020 130 79 0.606 6.5 28.6 Residential 4. AQ4 Haldi river side Rural 30.10.2020 76 40 0.526 8.8 32.7 Residential 5. AQ5 Magrajpur Rural 30.10.2020 89 42 0.480 7.6 29.2 Residential National Ambient Air Quality Standard 100 60 2 80 80 WHO Standard 100 50 - 50 -

286 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (Nov 2019 to April 2020)

135. From the report, it was observed that drastic difference between baseline and during construction particulate matter concentration. During construction concentration of PM10 and PM2.5 at WTP and Intake are way above the National Ambient Air Quality Standard. It is mainly due dry weather condition during sampling and we all know that concentration of particulate matter generally high in dry season. Also, the WTP location plays a major role for this high concentration of particulate matter. WTP located beside the national highway and earthen muddy road adjacent to the project location can cause the high concentration of PM10 and PM2.5. The lowest concentration of particulate matter found at Haldi river side and it because of the location that is adjacent to the river side and no pollution source nearby and another reason for the high particulate matter due to the use of fire cracker during the festive time and the samplings were being done during Durga puja festival.

287 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (Nov 2019 to April 2020)

Table 29E: During construction ambient noise monitoring data (package- EM/01)

Sl. Station Village Name Study Area Date Leq dB (A) Day Leq dB (A) No. Code Time Night Time 1 N1 Intake well-Mirpur Residential 31.10.2020 59.1 49.7 2 N2 Totaberia Residential 31.10.2020 56.8 48.2 3 N3 WTP-Banbhera Residential 30.10.2020 57.2 47.8 4 N4 Haldi river side Residential 30.10.2020 56.2 50.1 5 N5 Magrajpur Residential 30.10.2020 55.3 48.6 Code/Category Leq Day Time dB(A) - Standard Leq Night Time dB(A) - Standard A/Industrial 75 70 B/Commercial 65 55 C/Residential 55 45 D/Ecological- 50 40 Sensitive Note: National level Central Pollution Control Board’s, CPCB’s (Govt. of India) guideline/ protocol used for sampling

136. From the report, we can see that the average night time noise is higher during post monsoon monitoring because use of cracker during the festive season and sampling was being caried out during that time. Also, the movement of heavy vehicle at night plays a role for high noise level. Construction activities at Intake and WTP may result the high noise level data at day time.

137. As shown in below Table surface water quality parameters are within the standard.

288 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (Nov 2019 to April 2020)

Table 29F: During construction surface water monitoring data (package- EM/01)

Location Date Parameters Name pH Turbidity Chloride Fluoride Nitrate COD BOD DO Total Hardness Oil & Total Faecal (25 (NTU) as Cl in as F in as in in in alkalinity as CaCO3 Grease Coliform Coliform ºC) mg/l mg/l NO3 in mg/l mg/l mg/l as in mg/l in mg/l MPN/100ml MPN/100ml mg/l CaCO3 in mg/l Totaberia 31.10.2020 7.8 8.8 19.56 <0.1 0.51 <4 <2 6.4 140 143 1.6 90 40 Intake 31.10.2020 7.94 7.9 39.12 <0.1 0.65 <4 <2 6.6 170 165 1.8 120 30 substation Desirable 6.5 -- -- 2 -- 250 30 4 2100 300 10 500 -- Limit as per to IS:2296:1982 8.5

.

289 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (Nov 2019 to April 2020)

Package no: East Medinipur - EM/02

Table 29G: During construction Ambient Air Monitoring data (package- EM/02) Sl. Station Village Name Study Area Date Parameters (Government Standards) No. Code PM10 PM2.5 CO SO2 NO2 (μg/m3) (μg/m3) (mg/m3) (μg/m3) (μg/m3) 1.AQ1 Garchakraberia Sensitive 29.10.2020 51 22 0.572 4.4 25.2 Near Primary School 2. AQ2 Jambari Near Rural 21.10.2020 78 35 0.480 4.3 21.3 OHR Residential 3. AQ3 Manuchak Jalpai Rural 28.10.2020 114 64 0.549 6.9 29.5 Residential 4. AQ4 Parbatipur,Near Rural 29.10.2020 109 45 0.789 7.7 31.2 OHR Residential 5. AQ5 Nandigram CT Rural 28.10.2020 85 53 0.755 7.5 31.4 Residential 6. AQ6 Haripur, Near Rural 27.10.2020 70 31 0.606 7.3 30.3 OHR Residential 7. AQ7 Kamalpur, Near Rural 28.10.2020 80 39 0.675 6.6 28 OHR Residential 8. AQ8 Birulia Rural 28.10.2020 74 41 0.709 7.1 30.4 Residential 9. AQ9 Monoharpur, Sensitive 21.10.2020 81 49 0.526 5 26.3 Near Primary School 10. AQ10 Kanakpur, Near Rural 29.10.2020 59 28 0.469 4.2 26.9 OHR Residential National Ambient Air Quality Standard 100 60 2 80 80 WHO Standard 100 50 - 50 -

290 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (Nov 2019 to April 2020)

Average PM10 Data Comparison 120 100 80 60 40 20 0 Baseline During Construction

PM 10 NAAQS

Average PM2.5 Data Comparison 80

60

40

20

0 Baseline During Construction

PM 2.5 NAAQS

138. At individual site PM10 above the standard at 2 locations and PM2.5 above the standard at one location. From the above comparison graph, it is clearly visible the difference between baseline and during construction particulate matter concentration. The average baseline PM10 3 3 and PM2.5 concentration was 65 μg/m and 33 μg/m respectively. The increase in concentration due to construction activities around the monitoring locations and also due to dry weather during sampling. Because of less moisture content in atmosphere, particulate matter will be high in atmosphere.

Table 29H: During construction Ambient Noise Monitoring data (package- EM/02) Sl. No. Station Village Name Study Area Date Leq dB (A) Leq dB (A) Code Day Time Night Time 1 N1 Garchakraberia Silence Zone 24.10.2020 59.5 47.8 Near Primary School 2 N2 Jambari, Near Residential 21.10.2020 63.5 50.4 OHR 3 N3 Manuchak Residential 23.10.2020 58.8 50.1 Jalpai 4 N4 Parbatipur, Near Residential 24.10.2020 60.6 49.2

291 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (Nov 2019 to April 2020)

Sl. No. Station Village Name Study Area Date Leq dB (A) Leq dB (A) Code Day Time Night Time OHR 5 N5 Nandigram CT Residential 23.10.2020 59.9 49.9 6 N6 Haripur, Near Residential 22.10.2020 62.4 51.4 OHR 7 N7 Kamalpur, Near Residential 23.10.2020 62.4 48.8 OHR 8 N8 Birulia Residential 24.10.2020 62.5 49.0 9 N9 Monoharpur, Silence Zone 21.10.2020 61.8 51.1 Near Primary School 10 N10 Kanakpur, Near Residential 22.10.2020 59.3 48.8 OHR 11 N11 Gangra, Near Residential 22.10.2020 60.0 49.7 OHR 12 N12 Chakchilinga, Residential 21.10.2020 54.9 49.8 Near OHR 13 N13 Gokulnagar,near Residential 25.10.2020 58.9 50.1 OHR 14 N14 Naynan Residential 25.10.2020 57.2 48.6 15 N15 Dinabandhupur Residential 25.10.2020 60.2 49.7 16 N16 Purushottompur Residential 26.10.2020 59.0 50.4 17 N17 Banasri Garui Residential 26.10.2020 58.4 48.3 18 N18 Gholpukuria Residential 26.10.2020 60.8 49.0 19 N19 Narasinghapur Residential 27.10.2020 59.1 46.7 Jalpia 20 N20 Gopalchak Residential 27.10.2020 61.3 51.2 Code/Category Leq Day Time dB(A) - Standard Leq Night Time dB(A) - Standard A/Industrial 75 70 B/Commercial 65 55 C/Residential 55 45 D/Ecological- Sensitive 50 40 Note: National level Central Pollution Control Board’s, CPCB’s (Govt. of India) guideline/ protocol used for sampling

292 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (Nov 2019 to April 2020)

139. From the above graph, it is noticeable that due construction activities in and around the sampling locations noise (day as well as night) is above CPCB permissible limit. Where day time noise standard is 55 dB(A), the graph is showing during construction noise is way above the 55 dB(A), i.e. 60 dB(A). It is also higher than the baseline monitoring data. Some other factors like relative humidity and temperature also play a major role on these noise data.

293 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (Nov 2019 to April 2020)

Table 29J: During construction Surface Water Monitoring data (package- EM/02)

Location Date Parameters Name pH Turbidity Chloride Fluoride Nitrate COD BOD DO Total Hardness Oil & Total Faecal (25 (NTU) as Cl in as F in as in in in alkalinity as CaCO3 Grease Coliform Coliform ºC) mg/l mg/l NO3 in mg/l mg/l mg/l as in mg/l in mg/l MPN/100ml MPN/100ml mg/l CaCO3 in mg/l Manoharpur 21.10.2020 7.37 3.2 102.7 0.13 <0.5 62.4 12 6.1 190 451 2.2 10 2 Haripur 27.10.2020 8.10 6.6 146.8 0.98 <0.5 20.8 4.6 6.2 320 165 1.6 20 7 Nandigram CT 28.10.2020 7.0 8.5 127.2 0.13 0.52 41.6 8.0 6.2 200 176.0 1.8 15 4 Parbatipur 29.10.2020 7.15 8.1 318 0.53 <0.5 20 2.8 5.5 130 308 1.6 20 6 Manuchak 28.10.2020 7.68 7.8 259.3 0.59 0.60 83.2 15 6.4 350 363.0 2.8 <2 <2 Jalpai Jambari 21.10.2020 7.50 6.4 48.92 0.24 0.71 41.6 9.5 6.3 150 154 1.8 <2 <2 Garchakraberia 29.10.2020 7.19 7.7 88.05 0.22 <0.5 62.4 9.8 6.3 80 132 2.4 10 2 Kamalpur 28.10.2020 7.82 7.2 156.5 0.28 0.15 20.8 4.4 6.4 250 198 <1.4 <2 <2 Kanakpur 29.10.2020 7.64 8.9 137 0.27 <0.5 20.8 3.8 6 170 231 <1.4 90 33 Birulia 28.10.2020 7.24 8.4 151.6 0.46 <0.5 41.6 6.6 5.3 200 231 1.8 <2 <2 Desirable 6.5 -- -- 2 -- 250 30 4 2100 300 10 500 -- Limit as per to IS:2296:1982 8.5

294 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

140. From the above results we can see the high concentration of DO in all the water sample. There may be several reasons for this. One reason can be the time of the sampling, as we know the relationship between the temperature and DO is inversely proportional. If during the sampling the temperature was low, there is a chance of getting high DO concentration. Another reason for this might be the eutrophication condition of pond. Eutrophic condition is caused by excessive plant and algal growth due to increased availability of sunlight and nutrient fertilizers needed for photosynthesis. More photosynthesis causes release of oxygen in water.

141. Due to stagnant water bacterial growth is less and less oxygen is being consumed by bacteria for breaking the organic matter, this is the reason of less BOD concentration in water. At three locations i.e. Manoharpur, parbatipur and Manuchak Jalpai showing high concentration of hardness due to domestic use of pond like use of soap, detergent etc. Concentration of BOD and COD was within the standard.

295 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Table 29K: During construction Ground Water Monitoring data (package- EM/02)

Location Name Date Parameter pH Turbi Conduct TDS Total Chloride Sulfate Nitrate Iron Copper Lead Arsenic Mercury (25 dity ivity µs/ in Hardness as Cl in as SO4 as NO3 as As as as as Hg in ºC) (NTU) cm mg/l as CaCO3 mg/l in mg/l in mg/l Fe in Cu in Pb in As in mg/l in mg/l mg/l mg/l mg/l mg/l

Manoharpur 21.10.2020 7.43 <1 983 580 363 132.1 3.40 6.82 0.17 <0.02 <0.01 <0.01 <0.001 Haripur 27.10.2020 7.81 <1 966.1 570 296 132.1 11.40 2.98 0.14 <0.02 <0.01 <0.01 <0.001 Nandigram CT 28.10.2020 7.59 <1 1051.7 610 385 137 24.75 <0.5 0.29 <0.02 <0.01 <0.01 <0.001 Parbatipur 29.10.2020 7.60 <1 1455.2 844 429 166.3 7.71 2.76 0.38 <0.02 <0.01 <0.01 <0.001 Manuchak Jalpai 28.10.2020 7.46 <1 1431 830 352 308.2 2.76 4.25 0.05 <0.02 <0.01 <0.01 <0.001

Jambari 21.10.2020 7.39 <1 1258.6 730 495 53.81 6.06 4.71 <0.05 <0.02 <0.01 <0.01 <0.001 Garchakraberia 29.10.2020 7.50 <1 1142.4 674 385 151.6 19.53 7.62 <0.05 <0.02 <0.01 <0.01 <0.001 Kamalpur 28.10.2020 7.31 <1 1179.3 684 418 53.81 3.30 2.52 0.05 <0.02 <0.01 <0.01 <0.001 Kanakpur 29.10.2020 7.22 <1 1430.5 844 330 244.6 <1 4.76 0.20 <0.02 <0.01 <0.01 <0.001 Birulia 28.10.2020 7.12 <1 1200 696 440 181 7.77 8.32 0.18 <0.02 <0.01 <0.01 <0.001 Acceptable Limit 6.5 1 -- 500 200 250 200 45 0.3 0.05 0.01 0.01 0.001 to NTU 8.5 Permissible limit in No 5 -- 2000 600 1000 400 No 1.0 1.5 No 0.05 No the absence of Relax relaxatio relaxatio relaxatio alternate source ation n n n

296 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

142. The TDS concentration in ground water is showing higher than acceptable limit. High concentration of TDS in the ground water sample is due to leaching of salts from soils and also domestic sewage may percolate into the ground water which may lead to increase in TDS value. The chloride concentration is high at Manuchak Jalpai and the reason might be the fertilizers use in agricultural land. This fertilizer percolate through ground water and increase the chloride concentration and also chloride naturally occur in ground water. The hardness level is always higher than acceptable level, due to domestic use of water like use of soap and detergent for washing cloth.

Table 29L: During construction Soil Quality monitoring data (Package- EM/02)

No. Parameters Result Unit Nandigram II- Manoharpur (Zone- 6) Date: 21.10.2020 1 pH (at 18 ºC) Value (1:2) 8.78 -- 2 Elect. Conductivity (1:5) 2.82 ms/ cm 3 Moisture 1.2 % 4 Texture Clay Loam 5 Calcium as Ca 1.26 % 6 Magnesium as Mg 0.45 % 7 Permeability 0.88 cm/hr 8 Organic Matter 0.65 % 9 Oil & Grease 0.10 mg/kg 10 Phosphorous as P 16.61 mg/kg 11 Sodium as Na 79 mg/kg 12 Potassium as K 184 mg/kg 13 Nitrogen as N 20.18 mg/kg Nandigram I – Haripur (Zone- 19) Date: 27.10.2020

297 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

No. Parameters Result Unit 1 pH(at 18 ºC) Value (1:2) 9.01 -- 2 Elect. Conductivity (1:5) 1.97 ms/ cm 3 Moisture 1.4 % 4 Texture Silty clay 5 Calcium as Ca 0.77 % 6 Magnesium as Mg 0.12 % 7 Permeability 0.30 cm/hr 8 Organic Matter 1.15 % 9 Oil & Grease 0.07 mg/kg 10 Phosphorous as P 23.45 mg/kg 11 Sodium as Na 92 mg/kg 12 Potassium as K 126.1 mg/kg 13 Nitrogen as N 33.10 mg/kg Nanigram I- Nandigram CT (Zone- 18) Date: 28.10.2020 1 pH(at 18 ºC) Value (1:2) 8.49 -- 2 Elect. Conductivity (1:5) 2.35 ms/ cm 3 Moisture 1.4 % 4 Texture Silty clay 5 Calcium as Ca 1.19 % 6 Magnesium as Mg 0.03 % 7 Permeability 0.25 cm/hr 8 Organic Matter 0.86 % 9 Oil & Grease 0.12 mg/kg 10 Phosphorous as P 278.4 mg/kg 11 Sodium as Na 74.2 mg/kg 12 Potassium as K 216 mg/kg 13 Nitrogen as N 24.90 mg/kg Nandigram I -Parbatipur (Zone-13) Date: 29.10.2020 1 pH(at 18 ºC) Value (1:2) 8.61 -- 2 Elect. Conductivity (1:5) 1.34 ms/ cm 3 Moisture 1.2 % 4 Texture Silty clay 5 Calcium as Ca 1.12 % 6 Magnesium as Mg 0.03 % 7 Permeability 0.25 cm/hr 8 Organic Matter 0.40 % 9 Oil & Grease 0.18 mg/kg 10 Phosphorous as P 134.1 mg/kg 11 Sodium as Na 75.90 mg/kg 12 Potassium as K 206.1 mg/kg 13 Nitrogen as N 31.86 mg/kg Nandigram I - Manuchak Jalpai (Zone- 12) Date: 28.10.2020 1 pH(at 18 ºC) Value (1:2) 9.04 -- 2 Elect. Conductivity (1:5) 2.56 3 Moisture 1.2 % 4 Texture Clay Loam 5 Calcium as Ca 1.75 % 6 Magnesium as Mg 0.06 % 7 Permeability 0.84 cm/hr 8 Organic Matter 0.31 % 9 Oil & Grease 0.47 mg/kg 10 Phosphorous as P 237.4 mg/kg 11 Sodium as Na 88.50 mg/kg 12 Potassium as K 192.4 mg/kg 13 Nitrogen as N 28.64 mg/kg Nandigram I – Jambari (Zone- 7) Date: 21.10.2020 1 pH(at 18 ºC) Value (1:2) 8.92 -- 2 Elect. Conductivity (1:5) 1.87 ms/ cm 3 Moisture 1.1 % 4 Texture Silty clay

298 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

No. Parameters Result Unit 5 Calcium as Ca 0.77 % 6 Magnesium as Mg 0.09 % 7 Permeability 0.28 cm/hr 8 Organic Matter 0.55 % 9 Oil & Grease 0.08 mg/kg 10 Phosphorous as P 10.26 mg/kg 11 Sodium as Na 106 mg/kg 12 Potassium as K 68 mg/kg 13 Nitrogen as N 22 mg/kg Nandigram I – Garchakraberia (Zone- 2) Date: 29.10.2020 1 pH(at 18 ºC) Value (1:2) 8.49 -- 2 Elect. Conductivity (1:5) 1.22 ms/ cm 3 Moisture 1.2 % 4 Texture Silty clay 5 Calcium as Ca 0.84 % 6 Magnesium as Mg 0.09 % 7 Permeability 0.28 cm/hr 8 Organic Matter 0.27 % 9 Oil & Grease 0.20 mg/kg 10 Phosphorous as P 115.8 mg/kg 11 Sodium as Na 98.40 mg/kg 12 Potassium as K 210.5 mg/kg 13 Nitrogen as N 28.14 mg/kg Nandigram II – Kamalpur (Zone – 1) Date: 28.10.2020 1 pH(at 18 ºC) Value (1:2) 9.41 -- 2 Elect. Conductivity (1:5) 2.37 ms/ cm 3 Moisture 7.6 % 4 Texture Silty clay 5 Calcium as Ca 0.35 % 6 Magnesium as Mg 0.15 % 7 Permeability 0.26 cm/hr 8 Organic Matter 0.52 % 9 Oil & Grease 0.08 mg/kg 10 Phosphorous as P 335.6 mg/kg 11 Sodium as Na 56.80 mg/kg 12 Potassium as K 164.1 mg/kg 13 Nitrogen as N 26.70 mg/kg Nandigram II - Kanakpur (Zone- 7) Date: 29.10.2020 1 pH(at 18 ºC) Value (1:2) 8.68 -- 2 Elect. Conductivity (1:5) 2.15 ms/ cm 3 Moisture 1.2 % 4 Texture Clay Loam 5 Calcium as Ca 1.05 % 6 Magnesium as Mg 0.03 % 7 Permeability 0.82 cm/hr 8 Organic Matter 1.22 % 9 Oil & Grease 0.14 mg/kg 10 Phosphorous as P 61.80 mg/kg 11 Sodium as Na 82.08 mg/kg 12 Potassium as K 194.6 mg/kg 13 Nitrogen as N 36.70 mg/kg Nandigram II – Birulia (Zone- 3) Date: 28.10.2020 1 pH(at 18 ºC) Value (1:2) 8.02 -- 2 Elect. Conductivity (1:5) 1.14 ms/ cm 3 Moisture 1.1 % 4 Texture Clay Loam 5 Calcium as Ca 1.05 % 6 Magnesium as Mg 0.21 % 7 Permeability 0.80 cm/hr 8 Organic Matter 1.93 %

299 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

No. Parameters Result Unit 9 Oil & Grease 0.16 mg/kg 10 Phosphorous as P 21 mg/kg 11 Sodium as Na 68.40 mg/kg 12 Potassium as K 178.4 mg/kg 13 Nitrogen as N 30.22 mg/kg

143. The results of ten locations showing that all the soil parameters are within the normal range including pH and electrical conductivity.

VII SUMMARY OF KEY ISSUES AND REMEDIAL ACTIONS

144. Status of EMP application discussed in earlier section. Some partial compliance issues have been noted during report period.

145. Table 30 lists the implementation status of corrective action observed during May 2020 to October 2020 in work sites of North 24 pgs, Bankura packages that were active during Nov 2019 – April 2020. Since activity of East Medinipur district packages started during the report period, implementation of corrective action will be reflected in next SEMR. The implementation plan for partially completed corrective actions are presented in Table 30.

Table 30: Implementation of Corrective Action Plan (North 24 pgs & Bankura) Sr Pending issues Status Further Responsible- Budget no. (November 2019 to April Action Implementation 2020 report period) Required North 24 pgs 1 Facilities in the worksite Partially improved. Further Contractor Contractor should include an office and Newly constructed improvement work cost toilet for workers (For chlorination tank rooms is required. and EMP package N 24 pgs/02A and are currently used as budget 02B) site office. Pre- Pre- fabricated bio-toilets fabricated have been installed at bio-toilets certain sites. should be installed at all working sites. 2 Facilities in the construction Partially improved. Immediate Contractor Contractor camps, especially sleeping improvement work cost arrangements, toilet facilities, of and EMP provision of drinking water and housekeeping budget fuel for cooking, waste and and basic wastewater management facilities for needs to be improved (For workers, package N 24 pgs 02A and especially at 02B) Zone 6 and 8 of Haroa Use of PPEs e.g. safety Improvement noted. Complete Contractor Contractor shoes, gloves and goggles Use of helmet – noted. supply and work cost should be improved at all sites Face mask and Hand use of PPEs and EMP 3 especially for activities like sanitizer is provided as particularly budget concrete braking while use of essential part of PPE. safety safety harness is mandatory harness for during working at heigh. (For working at

300 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Sr Pending issues Status Further Responsible- Budget no. (November 2019 to April Action Implementation 2020 report period) Required package N 24 pgs/02A and height, shoes, 02B) hand gloves as well as COVID related PPEs e.g. face mask, sanitizers, etc. – Immediately Barricading and caution tapes Partially Improved Need to Contractor Contractor should be put along pipeline provide work cost trenches at all pipeline laying barricading and EMP 4 sites. (For package N 24 along the budget pgs/02A and 02B) entire trenches Labour camp located inside Issue Solved None ICDS in Zone 16 pose risk to the children in terms of social Labour Camp is shifted 5 distancing, high noise and from ICDS centre. accidents (package N 24 pgs/02A) The pit latrines installed at These latrines are Considering Contractor Contractor Zone 10 and 13 of Bhangar – mostly abandoned. onset of work cost II Block as well as in WTP site Bio toilet are provided monsoon, all and EMP of Subproject may cause in certain zones. these latrines budget faecal coliform contamination New sites are also should either to groundwater (For package having Single pit be replaced 6 N 24 pgs/01 and 02B) Latrine which should be with systems replaced quickly. promoted under Swachh Bharat or removed. Improvement of housekeeping, Improvement Noted. None access to working area (Haroa 7 – Zone1 of package Regular spraying of N24P/02A, Bhangar II – Zone disinfectant is seen. 10, 13 package N24P/02B) Management of wastewater at Partially Improved. Further Contractor Contractor camp sites (Haroa – Zone1 Soak pit is seen Improvement work cost package N24P/02A, Bhangar sometimes. Required and EMP II Zone 10, 13 of package In zone 13, 90% work budget 8 – N24P/02B) is completed, In zone 10 Labour camp is shifted from OHR location. Discharge of wastewater from Not Improved Drainage Contractor Contractor WTP (package N 24 pgs/01) system inside work cost 9 site is a concern as there is no WTP is not and EMP drainage in the site and may properly budget cause severe water logging constructed.

301 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Sr Pending issues Status Further Responsible- Budget no. (November 2019 to April Action Implementation 2020 report period) Required during monsoon. There is a problem with discharge point. Health checkup of workers Due to surge of COVID Health Contractor Contractor under package N 24pgs/01 -19 Doctor’s checkup is work cost pending during report period appointment is not required but and EMP available. Health doctor’s budget check- up pending appointment 10 is not received by the contractors during COVID -19 Non availability of First aid box Improvement Noted. Complete Contractor Contractor at few pipe laying locations First -Aid box includes supply of First work cost Face mask and Hand aid box in all and EMP 11 sanitizer under the zones. budget COVID-19 pandemic situation Bankura 1 Facilities in the worksite Partially complied Further Contractor Contractor’ should include site office, labor (under construction) improvement s own cost hutment with toilet, drinking is required water, electricity, fuel for cooking, solid waste and waste water management etc. at WTP and Intake site for package BK/01 2 Renewal of Workman Complied No action - - Compensation, and All Risk required Policy for package BK/01 3 Baseline surface water quality Complied No action - - results pending for package required BK/01 4 Non availability of proper work Partially complied Further Contractor Contractor display board and grievance (under construction) improvement work cost registration contact number is required and EMP board at all work sites for budget package BK/03, BK/02A, BK/02B and BK/04

146. Table 31 provides the recommended corrective action plan that has been devised and target dates that have been set so as to remove these non-compliances. The concerned Contractors have been suitably advised. Contractors have also been advised to provide written commitment for implementation of corrective action plan.

302 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Table 31: Implementation Plan for Pending/ New Corrective Actions (North 24 pgs, Bankura and East Medinipur) Sr New/ Pending Action Responsible- Target Date Responsible Responsible Indicator of no issues Required Implementati – Monitoring – Reporting Compliance . on/ Budget North 24 pgs 1 Facilities in the Immediate Contractor/ Within 31st DSISC, PIU PIU, PMU- Site worksite should improveme Contractor December PMC observation include an office nt in the work cost and 2020. and checking and toilet for site to EMP budget workers (For provide package N 24 basic pgs/02A and 02B) facilities 2 Facilities in the Immediate Contractor/ Within 31st DSISC, PIU PIU, PMU- Site construction improveme Contractor December PMC observation camps, especially nt of work cost and 2020. and checking sleeping housekeepi EMP budget arrangements, ng and toilet facilities, basic provision of facilities for drinking water and workers, fuel for cooking, especially waste and at Zone 6,8 wastewater of Haroa management and Zone needs to be 15, 13 of improved (For Bhangar II package N 24 pgs block 02A and 02B) Use of PPEs e.g. Although Contractor- Immediate DSISC, PIU PIU, PMU- Site safety shoes, Contractor PIU/ PMC observation gloves and goggles has Contractor and checking should be provided work cost and improved at all adequate EMP budget sites especially for numbers of activities like PPEs but concrete braking, use of trenching, etc. these PPEs while use of safety during harness is hazardous mandatory during activities working at height. . are 3 (For package N 24 inadequate. pgs/01, pgs/02A Hence, and 02B) manageme nt with respect to use of PPEs should be improved. Further, face mask and hand sanitizer

303 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Sr New/ Pending Action Responsible- Target Date Responsible Responsible Indicator of no issues Required Implementati – Monitoring – Reporting Compliance . on/ Budget must be provided to all. The pit latrines These pit Contractor- Within 15th DSISC, PIU PIU, PMU- Site installed at Zone latrines PIU/ January 2021 PMC observation 15 of Bhangar – II should at Contractor and checking Block and Zone 6 least be work cost and and 8 of Haroa replaced EMP budget block as well as in with WTP site of systems 4 Subproject may promoted cause faecal under coliform Swachh contamination to Bharat or groundwater (For be removed package N 24 from site pgs/01 and 02B) Discharge of Discussion Contractor/ Within 15th DSISC, PIU PIU, PMU- Site wastewater from should be PIU January 2021 PMC observation WTP (package N held with Contractor and checking 24 pgs/01) site is a HIDCO to work cost and concern as there is establish EMP budget no drainage in the appropriatel site and may cause y sized 5 severe water discharge logging during line to monsoon. evacuate water/ wastewater from the site Soil debris are Discussion Contractor/ Within 15th DSISC, PIU PIU, PMU- Site need to be should be PIU January 2021 PMC observation transported in held with Contractor and checking separate location HIDCO to work cost and 6 from WTP identify and EMP budget (package N 24 dispose the pgs/01) site soil debris kept on site In Haroa zone 6 Immediate Contractor/ Within 31st DSISC, PIU PIU, PMU- Site during site visit remediation Contractor December PMC observation black patch was of the area work cost and 2020 for and checking found in the soil, and EMP budget awareness formed by spilling enhanceme training used/spent oil in nt of the ground. Need awareness 7 to educate labours about spill about response environmental amongst concerns due to labours spills (For package N 24 pgs/01)

304 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Sr New/ Pending Action Responsible- Target Date Responsible Responsible Indicator of no issues Required Implementati – Monitoring – Reporting Compliance . on/ Budget Health checkup of Health Contractor/ Within 15th DSISC, PIU PIU, PMU- Site workers under checkup for Contractor January 2021 PMC observation package N all workers work cost and and checking 24pgs/01 and N must be EMP budget 8 24 pgs/02A done pending during amidst report period COVID- 19 pandemic. Barricading and Immediate Contractor/ Immediate DSISC, PIU PIU, PMU- Site caution tapes improveme Contractor PMC observation should be put nt is work cost and and checking along pipeline required EMP budget 9 trenches at all pipeline laying sites. (For package N 24 pgs/02A and 02B) Electrical safety at Immediate Contractor/ Immediate DSISC, PIU PIU, PMU- Site work sites and improveme Contractor PMC observation 10 camp (For nt is work cost and and checking package N 24 required EMP budget pgs/02A and 02B) Bankura 1. Facilities in the Immediate Contractor/ Within 15th DSISC, PIU PIU, PMU- Site worksite should improveme Contractor January 2021 PMC observation include site office, nt in the work cost and and checking labor hutment with site to EMP budget toilet, drinking provide water, electricity, basic fuel for cooking, facilities solid waste and waste water management etc. at WTP and Intake site for package BK/01 2 Facilities in the Immediate Contractor/ Within 15th DSISC, PIU PIU, PMU- Site worksite should improveme Contractor January 2021 PMC observation include an office nt in the work cost and and checking and toilet for site to EMP budget workers (For provide package BK/02A, basic BK/02B and BK/ facilities 04) 3. Facilities in the Immediate Contractor/ Within 15th DSISC, PIU PIU, PMU- Site construction improveme Contractor January 2021 PMC observation camps, especially nt in the work cost and and checking sleeping site to EMP budget arrangements, provide toilet facilities, basic provision of facilities drinking water and

305 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Sr New/ Pending Action Responsible- Target Date Responsible Responsible Indicator of no issues Required Implementati – Monitoring – Reporting Compliance . on/ Budget fuel for cooking, waste and wastewater management needs to be arranged at IBPS/GLSR site (For package BK02A and BK 02B) 4 Non availability of Partially Contractor/ Within 15th DSISC, PIU PIU, PMU- Site proper work Pending. Contractor January 2021 PMC observation display board and Immediate work cost and grievance EMP budget registration contact number board at few work sites for package BK/02A, BK/02B and BK/04 East Medinipur 1 Facilities in the Immediate Contractor/ 31st DSISC, PIU PIU, PMU- Site worksite should arrangeme Contractor December, PMC observation include an office nt of work cost and 2020 and toilet for facilities EMP budget workers (For package EM/02) 2 Construction of Immediate Contractor/ For EM/01- DSISC, PIU PIU, PMU- Site labor camp (For arrangeme Contractor 31st January, PMC observation package EM/01 nt of camp work cost and 2021 and EM/02) EMP budget For EM/02 31st December, 2020 3 Barricading and Use of Contractor- Immediate DSISC, PIU PIU, PMU- Site caution tapes barricading PIU/ PMC observation should be put and caution Contractor along pipeline tapes work cost and trenches at all should be EMP budget pipeline laying ensured sites (For Package EM/02) 4 Non availability of Immediate Contractor/ 31st DSISC, PIU PIU, PMU- Site grievance register arrangeme Contractor December, PMC observation board (For nt of work cost and 2020 package EM/01 grievance EMP budget and EM/02) register 5 Use of PPEs e.g. Although Contractor/ Immediate DSISC, PIU PIU, PMU- Site safety shoes, contractor Contractor PMC observation gloves, mask has work cost and should be provided EMP budget improved at all PPE to

306 WBDWSIP: ADB Loan – 3696-IND Semi Annual Environment Monitoring Report for WBDWSIP (May 2020 to Oct 2020)

Sr New/ Pending Action Responsible- Target Date Responsible Responsible Indicator of no issues Required Implementati – Monitoring – Reporting Compliance . on/ Budget sites (For package worker and EM/01 and EM/02) contractor has to ensure that workers are using these PPE while working. 6 Availability of Fire Immediate Contractor/ Immediate DSISC, PIU PIU, PMU- Site Extinguisher at all Contractor PMC observation working sites (For work cost and package EM/02) EMP budget 7 Electrical safety Improveme Contractor/ Immediate DSISC, PIU PIU, PMU- Site arrangement nt required Contractor PMC observation needs to be work cost and improved (For EMP budget package EM/02)

307