Land Acquisition and Involuntary Resettlement Due Diligence Report

Document stage: Draft for consultation Project Number: 42486-018 June 2020

IND: Urban Services Improvement Project – Additional Financing (Water Supply Scheme in Badoda Town)

Package No: MPUSIP-4H

Prepared by Urban Development and Environment Department, Bhopal, Madhya Pradesh for the Asian Development Bank.

CURRENCY EQUIVALENTS (as of 10 May 2020) Currency unit – Indian rupee (₹) ₹1.00 = $0.0132 $1.00 = ₹75.489

ABBREVIATIONS

ADB - Asian Development Bank BPL - below poverty line CBO - community based organization CMO - Chief Municipal Officer CPHEEO - Central Public Health and Environmental Engineering Organization CWFM - clear water feeder main CWS - clear water sump DBO - Design, build, operate DDR - due diligence report DMS - detailed measurement surveys DPR - detailed project report EMP - environmental management plan GLSR - ground level service reservoir GOI - Government of GOMP - Government of Madhya Pradesh GRM - grievance redress mechanism MPUDC - Madhya Pradesh Urban Development Company Limited MPUSIP - Madhya Pradesh Urban Services Improvement Project NOC - no objection certificate OHT - overhead tank PIU - project implementation unit PMU - project management unit PRO - public relations officer PWD - Public Works Department RFCTLARRA - Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 Act ROW - right-of-way RWRM - raw water rising main UDHD - Urban Development and Housing Department ULB - urban local body WRD - Water Resources Department WSS - water supply scheme WTP - water treatment pant

WEIGHTS AND MEASURES

Ha – hectare kl – kiloliter km – kilometer LPCD – liter per capita day m – meter MLD – million liters per day mm – millimeter

NOTE In this report, "$" refers to United States dollars.

This draft land acquisition and involuntary resettlement due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of the use” section of this website.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

CONTENTS Pages I. INTRODUCTION 1 A. Overview 1 B. Project Description 2 C. Scope of the Report 2 II. POLICY FRAMEWORK AND ENTITLEMENTS 3 III. SUBPROJECT DESCRIPTION 4 A. Description of the Subproject Town 4 B. Existing Water Supply 4 C. Proposed Water Supply 4 IV. FIELD WORK AND PUBLIC CONSULTATION 7 A. Outline of Fieldwork 7 B. Field work Report 7 C. Public Consultation 8 V. LAND AVAILABILITY AND INVOLUNTARY RESETTLEMENT IMPACTS 17 VI. BUDGET 21 VII. CONCLUSIONS 22 A. Summary and Conclusions 22 B. Next Steps 22

APPENDICES:

1. Details of Land Ownership for each Water Works Component to be constructed 2. Photographs of Stakeholder Consultation and List of Participants 3. Involuntary Resettlement Screening Checklists 4. Land Details of Proposed Subproject Components 5. Land Status Certificate of Proposed Components issued by Chief Municipal Officer- Badoda 6. Land Status Certificate of Existing Components issued by Chief Municipal Officer- Badoda 7. Location of proposed components on Google map

GLOSSARY

Assistance refers to the support provided to displaced persons in the form of ex-gratia payments, loans, asset services, training and skills development, etc. in order to improve their standard of living and reduce the negative impacts of the Project.

Below poverty line (BPL) households are households whose monthly income is less than a designated sum as determined by the Government of Madhya Pradesh; INR 10,000/ month as of March 2020.

Cut-off date is the date of notification under Section 11 of the RFCTLARRA 2013 for displaced persons who have legal title to the land/property proposed for acquisition. In the case of squatters, encroachers and unauthorized occupants the date of the census survey conducted by the implementing agency (IA) will be considered as the cut-off date for entitlements under the investment program.

Displaced Persons (Affected Persons) – In the context of involuntary resettlement, displaced persons are those who are physically displaced (relocation, loss of residential land, or loss of shelter) and/or economically displaced (loss of land, assets, access to assets, income sources, or means of livelihoods) as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas.

Encroachers are persons who have extended their building, agricultural lands, business premises or workplaces into government lands.

Titleholders are those who have legal title to land, structure and other assets.

Vulnerable Persons– are those below the poverty line, the elderly–above 60 years of age, female headed households, children (persons below 18 years of age are considered as minors or children in India), physically handicapped, indigenous people, scheduled castes and scheduled tribes, households with disabled persons, landless, transgender and those without legal title.

I. INTRODUCTION A. Overview

1. The Asian Development Bank (ADB) approved a sector loan for the Government of Madhya Pradesh (GOMP) to implement Madhya Pradesh Urban Services Improvement Project (MPUSIP). The sector project loan was approved on 18 May 2017, signed on 19 June and became effective on 21 August 2017. ADB's support was sought to improve water supply services in small and remote ULBs of Madhya Pradesh, which were not supported by any other program. ADB and the GOMP agreed on ADB's investment in phased manner in this priority sector taking up 68 ULBs under the current project and 70 ULBs under additional financing (hereafter referred as “the project”).

2. The additional financing is the next step towards scaling up the coverage of improved urban service delivery in Madhya Pradesh by building on the positive momentum of the outputs 1 and sector reforms initiated to date under the current project. The additional financing will enable additional 64 ULBs to provide 24x7 water supply services; improve and expand the integrated storm water and sewage infrastructure coverage in 6 ULBs following a mix of onsite and offsite sanitation approaches and introduce integrated urban development (IUD) approaches in two ULBs. The integrated storm water and sewage infrastructure approaches include fecal sludge management coupled with stormwater or flood management to address the full range of wastewater generated, cotreated and discharged in the local environment to improve the livability of town. It will also build UDHD, MPUDC, and the participating ULBs’ capacities to improve 2 coverage of urban services in Madhya Pradesh. The project will enhance the outcome of the current project in: (a) expanding access to improved water supply services to additional 1.3 million people, which will increase the project outcome target by 80 percent from 1.6 million to a total of 2.9 million people; (b) increasing coverage area of waste water management from 4 to 11 towns; and (c) expand the capacity development output to include strengthening project ULBs capability in O&M of water supply and integrated storm water and sewage infrastructure. The project is aligned with the following impact(s): economic growth and urban living conditions improved, and 3 infant mortality reduced in the state. The project will have the following outcome: quality, coverage, efficiency, and sustainability of urban service delivery improved in the state. Envisaged outputs of the project include: (i) Output 1: Water supply and integrated storm water and sewage infrastructure improved; and (ii) Output 2: Institutions strengthened, and capacity developed.

3. The executing and implementing agencies will remain unchanged from those in the current project. The State Urban Development and Housing Department (UDHD) will continue to be the executing agency (IA) and Madhya Pradesh Urban Development Company Limited (MPUDC) will continue as the implementing agency (IA) for the project.

4. The Resettlement Framework for MPUSIP (Additional Financing) outlines the objectives, policy principles and procedures for land acquisition, if any, compensation and other assistance measures for Displaced Persons4 /Affected Persons (APs), if any. This framework reflects the

1 Universal coverage, full operation and maintenance cost recovery, 100% metering, adopting volumetric tariff coupled with GOMP led urban property tax reforms and eGovernance, and establishing customer services center in each ULB. 2 The project towns generally have a population of 5,000 to 100,000. 3 As passed by the Lok Sabha on 29 August 2013. 4 In the context of involuntary resettlement, displaced persons are those who are physically displaced (relocation, loss of residential land, or loss of shelter) and/or economically displaced (loss of land, assets, access to assets, income sources, or means of livelihoods) as a result of (i) involuntary acquisition of land, or (ii) involuntary restrictions on land use or on access to legally designated parks and protected areas. It covers them whether such losses and involuntary restrictions are full or partial, permanent or temporary.

2 borrower’s law on the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act (RFCTLARRA) 2013, state government policies, ADB’s Safeguard Policy Statement (SPS), 2009 and other social safeguard guidelines. A detailed description of compensation measures and assistance is provided in the entitlement matrix.

5. An entitlement matrix, consistent with the existing norms and guidelines of the country and the state government, and ADB’s Safeguard Policy Statement has been prepared to cover losses identified in this Project. The matrix recognizes that the lack of title/customary rights recognized under law will not be a bar to entitlement and has special provisions for non-titled persons. The eligibility for compensation will be determined through a cut-off date. People moving into the sub- project area after the cut-off date will not be entitled to compensation or other assistance.

B. Project Description

6. The objective of the proposed Water Supply Scheme in Badoda is to achieve safe and sustainable water services both in terms of services to customers, cost recovery and conservation of precious water resources. The project proposals envisage providing 100% coverage of population with continuous, pressurized and safe drinking water services and achieving progressively increasing cost recovery by expanding the coverage and increasing operating efficiency. The subproject main objectives are as follows:

(i) To supply potable drinking water; (ii) To promote sustainable measures to increase potable water supply to the population; (iii) To provide water supply through future sustainable source developments; (iv) To provide water supply through improvements of safe yield of existing water sources; (v) To provide water supply through improvements of water treatment works; (vi) To supply drinking water which contributes towards a sustainable regional development; (vii) To improve the current state of the water cycle of subproject through improvements in the separate components of the water supply system in investment program.

Table 1: Subproject Components Main Components Details Source development Intake works (for surface water sources) Treatment works Water Treatment Plant (WTP) Water Transmission Raw water rising main (RWRM), Clear water rising main (CWRM) Water storage Ground level service reservoir (GLSR) and overhead tank (OHT) Water Distribution Distribution mains and network Bulk valves and flow meters Domestic (Household) connection and Commercial Connection

Source: Detailed Project Report, Badoda

C. Scope of the Report

7. This draft land acquisition and involuntary resettlement due diligence report (DDR) is prepared for the proposed water supply augmentation scheme in Badoda, district. The 3 proposed subproject will provide metered water supply for domestic, institutional and commercial users including metered connections to each household in the town. All municipal wards of the town will be covered under the project. The total population of Badoda town as per census 2011 is 18,437. The estimated population for the design year 2048 is 26,125.

8. The proposed subproject in Badoda town is not expected to have any involuntary resettlement impacts. The main objective of due diligence exercise is to confirm that the subproject is free of involuntary resettlement impact such as land acquisition, physical displacement, economic displacement, adverse impact on livelihood, community properties or any other temporary or permanent impacts, based on a review of land records, stakeholder consultations and field visits to proposed project locations. The draft due diligence report (DDR) has been prepared by assimilating the details of the draft detailed project report (DPR), findings from the field visits and discussions with relevant government officials and information gathered during public consultation which is aligned with ADB’s safeguards requirements. This document describes the findings and provides copies of relevant documents, minutes of meetings and photographs.

9. Due diligence involved site visits and discussion with relevant local government offices for land records, ownership details and permissions/approvals required, if any, for use of land. This was followed by a detailed public consultation to inform the public / stakeholders on the project components and to ascertain if there are any potential involuntary resettlement impacts. Site visits and consultations were conducted by the team comprising detailed project report (DPR) consultants, social safeguard consultant and staff from project management unit (PMU) and project management consultants (PMC) and staff from the urban local body (ULB) during planning stage.

10. Involuntary resettlement impacts will be reconfirmed and reassessed after completion of detailed design and detailed measurement surveys (DMS) which will be conducted by Design, Build and Operate (DBO) Contractor, PIU and the project consultants before initiation of civil works during implementation5. The EA will be responsible for submission of the updated social safeguard document to ADB for No Objection prior commencement of civil works. The final involuntary resettlement report will be reviewed and disclosed on website of urban local body (ULB), IA and ADB. No construction work will commence before the updated social safeguard document for the package is reviewed and cleared by ADB and compensation to affected persons, if any, is completed. The IA, MPUDC, is responsible to hand over the project land/site to the contractor, free from all encumbrances.

II. POLICY FRAMEWORK AND ENTITLEMENTS

11. The Resettlement Framework prepared for MPUSIP-Additional Financing sets out the objectives, principles, eligibility criteria and entitlements for the affected persons, based on ADB SPS 2009 and Land Acquisition, Rehabilitation and Resettlement Act (LARR) 2013 as well as national and state laws for protection of street vendors and the Madhya Pradesh Bhumigat Pipeline, Cable Evam Duct (Bhumi Ki Upoyokta ka Adhikaran Ka Arjan) Adhiniyam, 2012. Until recently, all activities related to rehabilitation and resettlement in the State of Madhya Pradesh had been based on the Madhya Pradesh Resettlement and Rehabilitation Policy, 2002 (MPRR)

5 Detailed measurement survey will be jointly conducted by safeguards personnel of PIU, consultants and contractors prior to implementation at each site/stretch of alignment. Report (IR DDR / RP for different sites/stretches will be prepared and submitted to ADB for approval; prior payment of compensation to permanent and/or temporarily impacted persons is mandatory before start of civil work at each site/alignment stretch. Social safeguards document for the package will be updated by PMC in coordination with DBO contractor.

4 and National Rehabilitation and Resettlement Policy, 2007 (NRRP-2007). The Government of Madhya Pradesh (adopted LARR 2013 on 3 October 2014 with some specifications for operationalizing its implementation in the state.6 Details of policies are in the Resettlement Framework for MPUSIP.

III. SUBPROJECT DESCRIPTION

A. Description of the Subproject Town

12. Badoda is a town in District Sheopur of Madhya Pradesh State. The subproject town is located on 25° 29' 26.60"N latitude and 76° 39' 36.46"E longitudes at an altitude of 229 m above mean sea level. Badoda is an urban region spread an extent of about 3.00 sq.km and it has 15 administrative wards. As per 2011 census, the Badoda Nagar Parishad had a total population of 18,437 persons with 3,581 households and having average household size of 5 persons. The sex ratio of Badoda is 907; less than the sex ratio of the state of Madhya Pradesh which is 931. The average literacy rate is 59.04%, lower than the State average of 69.32%. Male literacy is 60.64% and female literacy is 39.36%.

B. Existing Water Supply

13. Badoda has a number of surface water sources like the Aheli River, Parbati River, Awada Dam, etc. Although, groundwater is the preferred source due to its good water quality and availability in abundance at depth of 200 to 300 feet. Presently, Badoda Nagar Parishad is supplying water from 10 tube wells. The water supply is approximately 40 LPCD and about 50% of the localities are covered by municipal water supply. Water is supplied by Badoda Nagar Parishad for a time period of 2 hours each day (1 hour in the morning and 1 hour in the evening). In wards where distribution system is not available (ward no. 05, 11, 12, 14 and 15), water is being supplied through tankers. The town has 7 water tankers; 5 with 5000 liters capacity and 2 with 2500 liters capacities. The town has approximately 2,500 water connections with water charges collected at the rate of Rs.40/- per connection per month for domestic connections.

14. At present, there are 3 overhead tanks (OHTs) with storage capacity of 250 KL, 300 KL and 500 KL at premises of Nagar Parishad office, Rupaliya and near Kabristan. The present distribution system was laid 30 years before. The existing pipelines are old and dilapidated which needs to be replaced.

15. In summer season, the water table depletes and tube wells run dry. Hence, tube wells are not dependable source throughout the year. It supplied directly through pipelines without any treatment. Tube wells are the only source for Badoda Nagar Parishad which is unable to meet the minimum norm of water supply at 70 LPCD as per CPHEEO. Considering this, there is a need for augmentation of water supply with reliable surface source in the town.

C. Proposed Water Supply

16. The primary objectives of the proposed water supply subproject include:

6 These GOs issued separately in September 2014 (i) notifies administrative cost of land acquisition; (ii) appoints Divisional Commissioners as Commissioner for Rehabilitation and Resettlement within their respective jurisdictions; (iii) authorizes District Collectors for constituting an Expert Group separately in respect of each project, (iv) notifies the factor which the market value is to be multiplied in case of rural areas, (v) appoints Officer-in charge of Land Acquisition Section in the Office of the Collector as Administrator for Rehabilitation and Resettlement and (vi) limits agricultural land acquisition, as required by the RTFCLARR, 2013. 5

(i) To achieve improved services through provision of safe and sustainable water supply both in terms of services to residents and cost recovery; (ii) To conserve water resources and to provide 100% coverage of the population with continuous, pressurized and safe drinking water services achieving a progressive increase of cost recovery by expanding the coverage and increasing operating efficiency; and (iii) To consider a per capita supply at 135 LPCD.

17. Proposed Water Supply Scheme components: The proposed source for the water supply scheme in Badoda identified the Aheli river as the reliable surface water source. The proposed subproject components will include: construction of intake well with pump house at Aheli river, raw water rising main, clear water feeder main, construction of WTP and providing new distribution system with metering, DMA, supervisory control and data system (SCADA) system and house service connections etc. Details are presented below:

(i) Water Source: Combined source (surface and ground water) in Aheli river near village Undiata / Dhanod and ground water source (existing tube wells). (ii) Anicut: Proposed Anicut with length of 35m, on Aheli river. (iii) Intake Well: 4m diameter with pump room on the top. The height of intake is 10.48m with retention time of 15 minutes is proposed. An approach bridge having width of 3m with 10m length to the intake well has also been proposed for operation and maintenance of the pumps. (iv) Water Treatment Plant: WTP with capacity of 2.35 MLD with 2.15 MLD output at 22 hours is proposed near village Undiata. (v) Raw Water Pumping Main (RWPM): 200 mm dia. DI (K9) pipe having length of 385m is proposed from intake well in Aheli river to the proposed WTP. From the other source (tube wells), combined pumping mains are proposed to WTP having total length of 86,39 varying diameters from 100mm to 300mm. (vi) Clear Water Feeder Main (CWFM): CWFM of 7535 m length and 150 to 200 mm dia of DI K-9 pipes.

Table 2: Proposed Clear Water Feeder Main (CWFM) details From To Flow (2048) Length (m) Pipe Dia Pipe (MLD) (mm) Material WTP (Node A) Node: B (Jn 1) 2.15 4,430 200 DI-K9 Node: B Node: T3 (OHT-3) 0.99 1,420 150 DI-K9 Node: B Node – C (Jn 2) 1.16 300 150 DI-K9 Node: C Node: T1 (OHT-1) 0.45 60 150 DI-K9 Node: C Node: T2 (OHT-2) 0.71 1,325 150 DI-K9 Total 7,535 Source: Detailed Project Report, Badoda

(vii) Number of Water Supply Zones: 03 (considering existing OHTs 250 KL, 300 KL and 500 KL)

6

Table 3: Water Supply Distribution Zones Zone Wards Covered Area Area/Locality Population within the Zone (km2) 2016 2018 2033 2048 Zone- 1(Partly),3 (Partly), 13 0.88 Nagar 3479 3650 4613 5369 1 (Partly), 14 (Partly) Parishad, and 15 (Partly) Govt. Higher Secondary School, Bus Stand, Police Station, LIC Office Zone- 1 (Partly), 2 (Partly), 3 1.30 Mata Mohalla, 6101 6292 7576 8620 2 (Partly), 7 (Partly), 8 Takur (Partly),10 (Partly), 11 Mohalla, Sabji (Partly) 12, 13 (Partly) Mandi, Jila and 14 (Partly) Sahkari Bank, Choti Thodi Mohalla, Sahara India Office, Vidya Valley Convent school Zone- 1 (Partly), 2 (Partly), 3 0.82 Raja Bhawani 10130 10256 11301 12136 3 (Partly), 4,5 (Partly), Singh Colony, 6,7 (Partly), 8 (Partly), Subhasha 9, 10 (Partly), 11 Chandra (Partly) and 15 (Partly) School, Post Office, Sutandi Mohalla, Swami Vivekanand School Total 3.00 19710 20198 23490 26125 Source: Detailed Project Report, Badoda

(viii) Raw and Clear Water Pumps: Vertical Turbine/Submersible pumps are proposed for Raw water pumping and Centrifugal pumps are proposed at clear water sump with 100% standby. (ix) Reservoirs: Clear Water Storage Sump (68 KL) within the campus of proposed WTP (x) Distribution System: HDPE pipes (PE100 PN10) are proposed for distribution system with 10 m head at ferrule. Total 29,871 m length of distribution system is proposed.

Table 4: Summary of Distribution Network S. No Pipe Diameter Pipe Inner Dia. Material Class Unit Quantity (m) 1 90mm 75mm HDPE PE100 PN10 meter 24,786 2 110mm 92mm HDPE PE100 PN10 meter 2,266 3 125mm 105mm HDPE PE100 PN10 meter 865 4 140mm 117mm HDPE PE100 PN10 meter 748 5 160mm 135mm HDPE PE100 PN10 meter 713 6 200 mm 167 mm HDPE PE100 PN10 meter 78 7

S. No Pipe Diameter Pipe Inner Dia. Material Class Unit Quantity (m) 7 225mm 190mm HDPE PE100 PN10 meter 405 8 250mm 210mm HDPE PE100 PN10 meter 10 Total 29,871 Source: Detailed Project Report, Badoda

(xi) Other Provisions: PLC & Local SCADA, Bulk flow meters and 3,923 domestic water meters with house connections.

18. The location of the proposed components is depicted on google map (refer to Appendix 7).

IV. FIELD WORK AND PUBLIC CONSULTATION

19. This involuntary resettlement due diligence document is prepared in consultation with stakeholders including local residents, beneficiaries/consumer, and Urban Local Body (ULB) officials/representatives. Consultations and focus group discussions (FGDs) were conducted to seek feedback from local people and other important stakeholders on the proposed development interventions, perceived impacts and mitigation measures and their participation.

A. Outline of Fieldwork

20. During the visit, field inspection of the proposed subproject facility locations and pipeline alignments that had been identified was undertaken. These include field visit to the identified sites and alignments and stakeholder consultations. The entire land requirement for the proposed subproject component will be fulfilled by government lands. The details of selected lands for subproject components are given in the Appendix 1 and Appendix 4.

B. Field work Report

21. Meetings were held with the concerned ULB Officials, public representatives, and local residents of Badoda to collect data and gather information for proposed subproject during various discussions/meetings (refer to Table 5 and Appendix 2).

(i) During the meeting and discussion, information on the present situation of water supply in the town and the requirement of the stakeholders was gathered. Based on present water supply arrangements, gaps were identified and were well documented; (ii) With the ULB authorities, all the possible water supply sources were visited and locations for all other the components of water supply scheme were identified; (iii) All the options of possible water supply sources, its dependability, quality assurance, source availability and the distance from the town were studied; (iv) Water from the selected source was collected and tested from the Laboratory of Bhopal Municipal Corporation Laboratory, Bhopal. Test report is obtained for designing purpose; (v) Ascertained the water security from the concerned department like WRD etc. such that best-chosen water source is made available to ULB for the purpose of water supply scheme; (vi) Consulted Revenue Department authorities to collect land ownership details of the proposed subproject components;

8

(vii) After getting all the required data for the preparation of DPR, the survey team was mobilized for the survey work, focusing on road survey for water supply distribution system, elevation differences in individual command areas and the required pressure conditions.

C. Public Consultation

22. Extensive consultations were undertaken with key stakeholders in line with ADB's requirements pertaining to environment and social considerations. Focus group discussion (FGD) was conducted at nearby proposed locations of intake well, WTP and OHT etc. with the community residents and line departments (persons involved in Infrastructure like water, waste water and allied services - engineers and workers of Local Body, Water Resource Department (WRD), Public Works Department (PWD), District Administrator and others. The major stakeholders targeted during consultations are:

(i) The municipalities, its elected members and staff who will be required to oversee the construction of the distribution networks and WTP as well as be directly responsible for the maintenance of the installations. (ii) Local residents who will take initiative to connect their houses with the water distribution line. (iii) Local business people and traders. (iv) The opinion makers are well-acquainted with and well-regarded by the community. They need to be enlisted in spreading environmental awareness within the community as well as in conveying the benefits of the project.

23. FGDs and consultations focused on various issues and mitigation measures during pre and post execution of work were undertaken. On the spot discussions with residents were also conducted during town visits. The following were the outcomes of consultations. Details of each consultation is provided in Table 5. The following were the outcomes of consultations:

(i) Consultations helped to identify the felt needs /concerns and apprehensions of the communities related to the project and priorities of concerned stakeholders; (ii) Consultations revealed that people are aware of the problems of the existing water supply system in the town and are willing to cooperate in the proposed project; (iii) Consultations with the key stakeholders revealed that existing water supply system is in a poor condition, so improvement is required and local inhabitant will definitely and fully accept the project. (iv) The ULB Officials had apprehensions regarding the project whether it will be a financial burden to the Nagar Parishad. Nagar Parishad does not have capacity or resource to be party in sharing the loan repayment.

9

Table 5: Summary of Consultation with Stakeholders Date Location No. of Participants Topics Discussed Issues Participants 8 June Nagar Parishad Total: 18 Elected • Briefing on project • The Chairman of the urban local body (ULB) 2016 Meeting Hall Male: 10 representatives, objectives on the of Badoda expressed the need for the Female: 8 Chairperson of probable subproject and willingness to take it up ULB, Chief implementation • The prime concern and apprehension of the Municipal Officer, procedures ULB Chairman regarding the project was Engineers, • Present drinking whether it will be a financial burden on the officials of water supply Nagar Parishad revenue source and its • Operation and maintenance of the facilities department condition developed under the project was explained; • Need of community participation was encouraged improvement of • Possibility of exempting the poor and the present vulnerable from user charge payment situation • There is an immediate need of improving • Potential positive the present water works infrastructure in the and negative town. impacts due to • Chairman explained the problematic areas project (low pressure zones, electricity supply implementation duration) related to the water supply • Land use and area • There are three zones of distribution to get to be covered water supply under the project • Timely road restoration • Drinking water user charge 8 June Ward No.5 Total: 10 Local residents/ • Existing water • The area has insufficient and inadequate 2016 Female: 4 Community (Low supply status drinking water supply. Water from two tube Male: 6 income group; • Proposed wells is presently supplied to the the men work as subproject area/community. The area faces severe daily laborers components water crisis during the summer season and the women • Impact of when the ground water level depletes. are housewives) subproject on • The community welcomed the project and community expressed need for it. However, they were particularly apprehensive that their economic condition scheduled tribes’ would prevent them from paying water user population charges. • Impact during construction work

10

Date Location No. of Participants Topics Discussed Issues Participants • Impact on health • The community expressed that they are by proposed happy that the entire community would be subproject benefited from the regular water supply. • Willingness to take • Slum dwellers showed willingness to take new water water connections but demanded relaxation connection in user charges. • People were briefed about the complaint redress mechanism.

8 June Ward No.14 M:11 Local • Briefing on project • Most of the people does not know about the 2016 FL3 households/ objectives proposed project. On learning about the Total:14 Slum dwellers probable project, they expressed that they were implementation happy that the entire community would be procedures benefited from the upgraded water supply. • Potential positive • Slum dwellers showed willingness to take and negative water connections but demanded relaxation impacts due to in user charges. project • People were briefed about the complaint implementation redress mechanism. • Experiences • Few women had heard about the proposed sharing on project and welcomed it as women are Resettlement and facing many problems in fetching water for Rehabilitation, hours. women • Some participants did not have water empowerment, connections. The women were happy to health, education, learn about the proposed project. convergence with • Possibility of exempting the poor and existing vulnerable from user charge payment, if government social possible as some of the residents are very security schemes poor. etc. • Slum area must be given relaxation for • Grievance connection and water use Redress procedures

03 Ward No.14 Male: 8 Local • Existing status of • Willingness to connect to piped drinking December Female: 4 households/ drinking water water supply; 2018 General public 11

Date Location No. of Participants Topics Discussed Issues Participants supply, need for • Subsidy to the poor; whether community project and taps would be provided; demand from the • Community participation in project community; implementation; • Area covered by • Implementing agency; and better /improved the project; service. • Status of existing • People were briefed about the complaint drinking water redress mechanism. supply system; • Women were happy to know about the • Need for proposed project. improvements to present system; • Potential positive and negative impacts project implementation; • Local community’s response to the project. 03 Market area Badoda Male: 8 Shopkeeper • Existing status of • Shopkeepers promise support for the December drinking water upcoming water supply project as it will be 2018 supply, need for beneficial to the community in all aspects. project and • All the participants agreed to pay proposed demand from the water tariff. community; • Timely road restoration. • Area covered by • Prior information is to be conveyed about the project; civil works in market area • Status of existing • Raised queries whether public post or drinking water community taps would be provided; supply system; • Community participation at each stage in • Need for project implementation; improvements to • Implementing agency; and better /improved present system; service. • Potential positive • People were briefed about the complaint and negative redress mechanism

12

Date Location No. of Participants Topics Discussed Issues Participants impacts project implementation; • Local community’s response to the project. 24 Office of Nagar Male: 3 CMO-Badoda, • Status of existing • The area has insufficient and inadequate January Parishad Badoda Sub engineer drinking water drinking water supply. Water from tube 2020 Nagar Parishad- supply system; wells is presently supplied to the Badoda and • Need for area/community. The area faces water Ward Councilor improvements to crisis during the summer season. of ward number 4 present system; • Briefed about proposed WSS Badoda and • Relevant its components. information of the • Project has already been delayed. upcoming project • Operation and maintenance of the facilities and benefits of developed under the project and the project. community participation. • They welcomed the project and expressed need for it. • They have apprehension that economic condition of few households may prevent them from paying water user charges. • Briefed about Project Grievance Redressal Mechanism and resettlement framework. • Under proposed WSS, all the households will get 24 x 7 supply with potable water, so households will come forward to take the ensured water supply with good pressure.

25 Ward No. 5 Male: 6 local residents • Proposed WSS • Community was glad to hear about the January Female: 7 residing of ward project objectives proposed water supply scheme 2020 number 5 probable • Community assured full support during implementation implementation procedures • People were concerned about the hiked of • Project monthly water tariff effectiveness and • Some people also show their grievance participation of about the delay in project. 13

Date Location No. of Participants Topics Discussed Issues Participants community • People are ready to take new water people connection in replacement of the old one • Community • People agreed to pay proposed water participation in tariff. project • Residents requested to select good implementation contractor to speed up the construction • Operation and process maintenance by • Briefed about GRC DBO Contractor • Grievance Redressal Mechanism under MPUSIP 25 Market Area Badoda Male: 8 Shopkeepers and • Briefing on project • Assured full support during January vendors objectives implementation. 2020 probable • Local shopkeepers and vendors. Were implementation assured that during excavation, dust and procedures traffic management would be properly • Present drinking mitigated with the help from local police. water supply • Consultation will be continually conducted source and its before the start of civil works in market condition area. • Potential positive • Road restoration must be in timely and negative manner. impacts due to • Shop keepers assured their full support to project the Project and assured full cooperation implementation during the construction phase • Potential positive • Street vendors and small shop owners and negative agreed on temporary shifting of Haats (to impacts due to other road side were alignment is not project proposed) during excavation and that it implementation should be ensured that their business will • Land use and area not be closed for the civil works; ensuring to be covered no income loss under the project • The shop owners said that they are willing • Relevant to accept the project which is ultimately for information of the the benefit of the community people;

14

Date Location No. of Participants Topics Discussed Issues Participants upcoming project • GRC will be formed at town level to and benefits of the address the local complaints and briefed project. about other levels under GRM • Ensuring no income loss • Grievance Redressal Mechanism (GRM) 25 Ward No.14 Male: 8 Local residents • Briefing on project • The area has insufficient and inadequate January Female: 4 objectives drinking water resource. Water is supplied 2020 probable to the area through tube wells implementation • The area faces severe water crisis during procedures the summer season when the ground water • Present drinking level drops. water supply • During discussion, people complained source and its about poor water supply in town. Some condition people even don’t have water supply • Potential positive connection in their home. and negative • All the households are ready to take new impacts due to water connection. project • Residents agreed to pay proposed water implementation tariff and demanded to subsidized rate also • Potential positive • People were briefed about the grievance and negative redress mechanism impacts due to project implementation • Land use and area to be covered under the project • Relevant information of the upcoming project and benefits of the project. 15

Date Location No. of Participants Topics Discussed Issues Participants • Ensuring no income loss • Proposed subproject components 25 Ward No.4 Male: 7 Local residents • Proposed WSS • Community was glad to hear about the January residing of ward project objectives scheme and assured their full support 2020 number 4 probable during implementation implementation • People were concerned about the hiked of procedures monthly water tariff • Project • Some people also show their grievance effectiveness and about the delay in project. participation of • People are ready to take new water community connection people • People agreed to pay the proposed water • Community tariff. participation in • All people requested to select good project contractor to speed up the construction. implementation • Operation and maintenance by DBO Contractor 25 Ward No.7 Male: 8 Local residents • Present drinking • Badoda Nagar Parishad is operating the January residing near water supply water supply system for the town 2020 existing OHT source and its • Participants expressed need for the (250 KL) under condition project and showed willingness to take it ward number 7 • Need of up improvement of • Operation and maintenance of the facilities the present developed under the project was situation discussed • Briefing on • Community participation is highly project objectives encouraged probable • People were briefed about the complaint implementation redress mechanism procedures • All the wards will be covered under this • Potential positive proposed subproject water supply for town and negative Badoda.

16

Date Location No. of Participants Topics Discussed Issues Participants impacts due to project implementation

17

V. LAND AVAILABILITY AND INVOLUNTARY RESETTLEMENT IMPACTS

24. No acquisition of private lands or involuntary resettlement impacts are anticipated for any of the proposed civil works for Badoda town water supply subproject. Sites identified for subproject components are government lands, refer to Appendix 1 and 4, which are reported vacant, unused, without any settlement / squatter / cultivation or other use. In this regard, a land status certificate has been obtained from the Chief Municipal Officer- Nagar Parishad in Badoda (refer to Appendix 5). Any temporary loss of income to roadside users identified during construction will be mitigated in accordance with the Resettlement Framework of MPUSIP.

25. The water will be sourced out from the Aheli river and utilization of the existing 10 tube wells. Raw water abstraction will be done then treated and supplied to the town. An anicut with 35m long is proposed on Aheli river. A small storage will be required as compared to the total volume of water available in Aheli river. No impact is envisaged on downstream. There is no commercial fishing taking place in this stretch of the river and on downstream up to the meeting point of Parbati River. There are seven streams which are the natural drains that carry the runoff generated by the rainfall in this area meets in the river. The proposed impoundment will likely benefit the environment through groundwater recharge and propagating aquatic life too. The proposed Anicut will store the water requirement for the low-flow period of four months and height of Anicut (proposed) which is lower than the riverbanks. Submergence/storage will be confined to river course itself. So, this type of structure allows heavy monsoon flow freely without any obstruction and also avoids dam silting. This structure impounds water during low or no flow period, and during heavy river flow, gates will be removed. Therefore, the change in flow regime due to this proposed Anicut will be negligible. Details of the land ownership is presented in Table 6.

26. An intake well cum pump house with approach bridge is also proposed on Aheli river. The intake well will be constructed within the river course and the land belongs to Water Resource Department (WRD). The approach bridge from intake well will partly fall within river course (WRD land) while remaining part of the approach bridge will come under revenue department land adjacent to river course. Land is vacant, unused, without any settlement/ squatter /cultivation/other use. Locals informed that the natural pooling of water is always and this river flows all year round except in the month of April to June. No fishing activities were reported and no adverse impact is anticipated for downstream users.

27. The identified land for WTP (2.35 MLD) has been in the possession of Revenue Department from many years and was not acquired in anticipation of ADB funded MPUSIP, as revealed through discussions with the officials of revenue department during visit. It is a vacant land free from any encroachment/any type of cultivation or not used for other purposes. The process of land transfer to ULB is under process.

28. The proposed raw water pumping main is of 385m long 200 mm dia. DI K9 from proposed intake well to proposed WTP. From the other source (tube wells) point of view, combined pumping mains are proposed to WTP having total length of 8639 varying diameters from 100mm to 300mm will be laid within the road right of way (RoW) of Madhya Pradesh Road Development Corporation (MPRDC) road namely Sheopur – Kuhajapur road and road under revenue department which is dirt road. The clear water feeder main of total length is 7535m of dia. 150 – 200mm pipe proposed and to be laid from WTP to OHT along with ROW of MPRDC road namely Sheopur – Kuhajapur road and Bagar to Nahar road and PWD road namely, Thana to company Darwaja to Bagar Tiraha. The pipelines will not cross any private land along the alignments.

18

29. No new tube well will be constructed under the WSS in Badoda. At present, water is drawn from 10 municipal tube wells located across the town. Water is directly drawn from ground water sources and supplied to the households. The water drawn from the 10 tube wells are located across the town with an average depth of 80-100m and yield 16-24 KL/hour. The locations of the existing tube/bore wells of existing water supply scheme of Badoda are as follows:

(i) Existing pumphouse/tube well at Bagar Tiraha under ward number 15 (ii) Existing pumphouse/tube well at opposite Batta Maharaj under ward number 14 (iii) Existing pumphouse/tube well at Rupaliyya under ward number 11 (iv) Existing pumphouse/tube well at near Kabristan under ward number 15 (v) Existing pumphouse/tube well at Jagdish Dharamshala under ward number 10 (vi) Existing pumphouse/tube well at near Sabzi Mandi under ward number 8 (vii) Existing pumphouse/tube well at Rapat ke Balaji under ward number 9 (viii) Existing pumphouse/tube well at Holi Chowk under ward number 4 (ix) Existing pumphouse/tube well at near Adarsh Vidya Mandir under ward number 13 (x) Existing pumphouse/tube well at Bachhawat ke Balaji under ward number 6

30. There is no need of new OHT as all the existing OHTs, 250 KL, 300 KL and 500 KL located at in the premises of Nagar Parishad office, Rupaliya and near Kabristan, are adequate to accommodate improved water supply. These OHTs and existing tube wells are located on government land under the possession of Nagar Parishad-Badoda. In this regard, a certificate has also been issued by chief municipality officer-Badoda, refer to Appendix 6.

31. New distribution network includes laying of 29,871m pipeline. These pipelines are proposed to be laid underground within ROW of the existing public roads belonging to Badoda- Nagar Parishad. Proposed pipe diameters to be laid range between 90 mm to 280 mm depending on the width of the roads. Distribution lines are proposed on one sides/ centre of the road depending up on availability of space where road widths are small. Subsequent to completion of works, road reinstatement will be undertaken by the contractor as part of the civil works.

32. The proposed distribution pipe-laying on roads will not have any permanent or temporary involuntary resettlement impacts. Laying of transmission mains and distribution network pipelines in the project area has been carefully planned to minimize disturbance to pedestrians and traffic and avoid income loss to businesses. Pipe laying activity on roads in the most congested market areas and densely built-up areas has been carefully planned to avoid involuntary resettlement impacts including temporary economic impacts to hawkers, shops and businesses. Measures will be taken to minimize excavation, disturbance to pedestrians and traffic and avoid income loss to businesses, while minimizing road reconstruction costs. Temporary impacts to traffic/access to shops and residences due to digging of pits for pipe laying are possible during construction; however, these will be mitigated by ensuring access to properties through provision of pedestrian planks, provision of adequate signage, and careful traffic management. Mobile hawkers will be assisted to move to places vacant nearby or to other side of the road, to ensure their earnings are not affected. No income loss is anticipated.

33. House Service connections: House service connection tapping from a distribution main/sub-main from tapping point to the chamber near property boundary or inside the property boundary will be provided. The work shall include excavation, road restoration, etc. Although, water supply connections are given to number of households but under this proposed subproject about 3923 connections with water meter are proposed.

19

Table 6: Land Ownership and Involuntary Resettlement Impacts No. Components Capacity Unit Length Land ownership Involuntary Resettlement Impact (No.) 1 Anicut on Aheli river 35m 1 Water Resource Anicut is proposed on Aheli river. NOC is Department (WRD), required from WRD. Negligible change in GOMP flow regime anticipated. Based on assessment, no downstream impact is expected and no commercial fishing activities are reported. No involuntary resettlement impact is anticipated. For more details, please refer to para 25. For land details, refer Appendix 1 and 4.

2 Intake well and Intake Well: 1 Water Resource Intake well is proposed at Aheli river. Approach bridge at Dia.: 4 m, Department (WRD), Land is available. The proposed site for Aheli river Height: 10.48 m and Revenue the intake well is within the river course incl. pump room Department, GOMP belongs to WRD. A part of approach and Approach bridge falls within the Revenue Bridge: width of Department land adjacent to WRD land 3.0m with 10 m near river course. Proposed sites are length to the vacant, unused and without any intake well settlement/ squatter /cultivation or other use. No involuntary resettlement impact is anticipated. For land details, refer Appendices 1 and 4. 3 Water Treatment Plant 2.35 MLD 1 Revenue Land belongs to Revenue Department. (WTP) including clear Department, GOMP Land is reported without any settlement/ water cultivation squatter /cultivation or Other. Proposed storage sump of 68 KL site is vacant, unused and without any with in premises of settlement/ squatter / or other use. No WTP involuntary resettlement impact anticipated. refer Appendices 1 and 4. 4 Guard cum operator 3 Revenue The proposed site is under the legal house at Intake well, Department, GOMP ownership of the government. No WTP and Boundary involuntary resettlement impact is wall with gate at anticipated. respective components.

20

No. Components Capacity Unit Length Land ownership Involuntary Resettlement Impact (No.) 5 RWPM 385 m + 8639 RWPM (i) Existing MPRDC RWPM will be laid from the intake to WTP m, Total: 9324 200mm dia Road ROW and road and other source like tube wells to WTP m length 385m, under Revenue along road right of way. Sufficient (ii) other Department. shoulder width is available for laying pipe source tube line. It will not cross any private land along well to WTP the alignment. No involuntary 100-300mm resettlement impact is anticipated. dia length 8639m

6 CWFM 7535 m CWFM 150- Existing MPRDC CWFM will be laid from WTP to OHTs 200 mm dia Road ROW and along existing road right of way. Sufficient length PWD road. shoulder width available for laying pipe 7535m) Nagar Parishad road line. It will not cross any private land along ROW the alignment. No involuntary resettlement impact is anticipated.

7 Chemical Storage and 1 Revenue No involuntary resettlement impact is dosing pump house at Department, GGOMP anticipated. WTP 8 Distribution Pipeline 29871 m Existing road ROW of Pipelines will pass through the existing HDPE pipe - 29871 m Nagar Parishad- ROWs of government roads. Temporary Badoda (Public land) impacts on traffic/access to shops and residences anticipated in some places. However, Contractor will provide signages indicating available alternate access route to minimize traffic disruptions. Contractor will ensure access to shops and residences as per EMP provisions. 9 Household 3923 - During construction period, access to connections with residents and shops may be temporarily metres affected. Contractor will have to ensure access as per EMP provisions to avoid any economic impact. 21

34. Mitigation measures: The sites or locations for the subproject components have been selected carefully to avoid and minimize involuntary resettlement impacts. The following mitigation measures are proposed to avoid and/or reduce the impacts during linear pipe works:

(i) Provide prior advanced notice (minimum one week) to community along the construction stretch. Distribute information on project and grievance redress mechanism, (ii) Maintain access to avoid disturbance to residents and businesses by providing planks and leaving spaces for businesses and residents to maintain access, (iii) Manage traffic flows as per traffic management plan prepared by the contractor in coordination with local authorities and communities, (iv) Limit the amount of time of open trenches, and complete works quickly where business activities are located, (v) Avoid full street closure to extent possible, (vi) Contractors shall provide employment opportunity to the local residents and particularly woman where possible; and, (vii) Contractors shall assist vendors and hawkers in shifting to alternative locations, if required.

35. No involuntary resettlement impact is expected as there will no acquisition of private lands, nor physical or economic displacement envisaged. The subproject components are proposed in government-owned lands (revenue land) and does not belong to tribal community. Transmission and distribution pipeline carry raw and clear water will traverse only through right-of-way (ROW) of the government road. An involuntary resettlement screening checklist is prepared and attached as Appendix 3. Accordingly, the subproject is classified under ‘Category C’ for involuntary resettlement under ADB SPS, 2009.

VI. BUDGET

36. A budgetary provision is made for costs likely to be incurred during implementation of subproject.

Table 7: Budget Sl. No Description Target group Estimated cost Source of fund 1 Consultation and information disclosure Persons/households INR 200,000; Included in and awareness drive through IEC tools of project area subproject cost

2 Communication (Plan), awareness Persons/households INR 100,000 Included in generation and grievance redress of project area subproject cost

3 Tanker supply for areas where existing Affected areas INR 100,000 Included in water supply disrupted during subproject cost construction

4 15% contingencies INR 60,000 Included in subproject cost Total INR 460,000

22

VII. CONCLUSIONS

A. Summary and Conclusions

37. No private land acquisition or involuntary resettlement impacts are anticipated at identified sites for subproject components, as adequate vacant land is available for the proposed facilities, within the compounds of government lands. The proposed site for WTP belongs to Revenue Department, GOMP. The Office of Nagar Parishad-Badoda is in process to get no objection certificate (NOC) for water abstraction from the proposed source-Aheli river. Land records are collected from Revenue Department, refer to Appendix 4 and 5. While other details if any, shall be appended accordingly to the updated DDR. For linear components (pipe laying) or those proposed along government road ROWs, temporary disruption to road users, pedestrians and community members will be avoided in the most congested zones of both the town. Safety measures shall be ensured, and temporary disruptions mitigated during construction by the contractor through simple measures such as provision of planks for pedestrian access to shops and traffic management. Accordingly, the subproject comes under category C for involuntary resettlement under ADB SPS 2009. Any temporary loss of income to roadside users identified during construction will be mitigated in accordance with the Resettlement Framework of MPUSIP- Additional Financing.

38. The Social Safeguards and Gender Officer (SSGO) at PMU, MPUSIP will be responsible to undertake a review of due diligence report during project implementation and if there is any imperative change in the alignment, concerned safeguard officials will carry out a due diligence investigation to document and study the social impact assessment of new alignment.

B. Next Steps

39. This draft involuntary resettlement DDR needs to be updated during detailed design with the following information, and ADB’s clearance obtained prior to start of construction. Any temporary loss of income to roadside users identified during construction will be mitigated in accordance with the Resettlement Framework of MPUSIP- Additional Financing.

(i) No objection certificate (NOC) is required from WRD for abstraction of water; (ii) Transfer of proposed land for the intake well, approach bridge and WTP in the name of Nagar Parishad Badoda; (iii) NOC is required from MPRDC and PWD to lay the transmission line; (iv) Reflection of design or site changes proposed, if any; (v) Site-specific consultations and town level consultations; (vi) If no impacts are identified based on DMS, site layout plans clearly depicting avoided impacts (particularly for proposed WTP) will be included in the updated DDR. On the other hand, if impacts are identified based on DMS, detailed inventory of losses, surveys will be conducted, and appropriate safeguard document will be prepared to address the impacts before the start of civil works.

Appendix 1 23

Appendix 1: Details of Land Ownership for each Water Works Component to be constructed Component Location Ownership of Land Plot No. Status of NOC Photograph of the Proposed Proposed (Khasra No) Location Intake Well & Aheli river Intake well cum pump A part of Proposal to be Approach Bridge house on Water approach will be sent to District Lat: Resource Department within Khasra No. Collector, Sheopur 25.48337N, (WRD) and part of 80 belonging to and WRD. Lng: 76.611995 E approach bridge within Revenue WRD and Revenue Department Department land (area available is (Adjacent to WRD land) 1.473 ha. and area required is 400 sq.m)

Anicut (35 M in Aheli river Water Resource River course Proposal to be length) Department (WRD) sent to WRD to Lat: 25.483373 N, obtain NOC. Lng: 76.619954E

WTP including Near Village Revenue Department, Khasra No. 66 Proposal to be clear water Undiata Government of Madhya (area available sent to District storage sump of Pradesh 0.637 ha. and Collector, 68 KL within Lat: area required is Sheopur. premises of WTP 25.483859999N, 0.50 ha.) Lng: 76.6215566666E

24 Appendix 1

Component Location Ownership of Land Plot No. Status of NOC Photograph of the Proposed Proposed (Khasra No) Location RWPM Within the ROW of - NOC to be Length: 9324 M existing road of MPRDC obtained from and Nagar Parishad MPRDC before road laying of RWPM

CWFM Dirt road under Revenue - NOC to be Length 7535 M Department and obtained from MPRDC Road MPRDC and revenue department before laying of CWFM

View of Dirt road

CWFM (contd.) - - Same as CWFM component.

View of MPRDC road

Appendix 2 25

Appendix 2: Photographs of Stakeholder Consultation and List of Participants a. Photograph of Consultation with Nagar Parishad Officials and Ward Councillor of town Badoda

26 Appendix 2

Appendix 2 27

List of Participants of Consultation with President and Ward Councillor of town Badoda

English Translation S.N. Participants Designation 01 Bharti/ RiteshTomar Vice President 02 Mahaveer Ji Nagar Councilor 03 Kishangopal Nagar Councilor 04 Murarilal Prajapati Councilor 05 Deepakraj Valmiki Councilor 06 Vishnu Suman Councilor 07 Mamta/Laxman Sharma Councilor 08 Seema/Vishnu Pandit Councilor 09 Dama Bai/Sitaram Mama Councilor 10 Sushila/Dhannalal Prajapati Councilor 11 Ramprashad Meena Councilor 12 BharatbhushanBairwa Councilor 13 Bharosi Bai/Shambhudayal Suman Councilor 14 Ghanshyam Adiwasi Councilor 15 Sunita Dhanraj Mahor Councilor 16 Vivek Agrawal Engineer 17 Rajeshwar Goad Darasha Consultancy

28 Appendix 2

b. Photograph of Consultation with Residents of Ward No.5

Appendix 2 29

List of Participants

English Translation S.N. Participants Mob. No. 01 Ranjeet 9993249273 02 Kamlesh 7415836459 03 Ramcharan 99930702975 04 Lakhan 7429876731 05 Jitendra 06 Chanda Bai 07 Kamla 08 Mukesh 09 Prem Bai 10 Shikandar 11 Sundar Bai

30 Appendix 2

c. Photograph of Consultation with Shopkeepers and Vendors

Appendix 2 31

Photograph of Consultation with Shopkeepers of town Badoda

List of Participants attended Consultation with Shopkeepers of town Badoda

English Translation S.N. Participants Mobile No. 01 Mukesh Verma 6260949469 02 Sakhir Khan 8439469559 03 Kanhaiya Lal Suman 9993264716 04 Nidesh Suman 8817168231 05 Vikesh Meena 8085794015 06 Dinu Gupta 8871272719 07 Vivek Sengar 9630682308 08 Ravi Arya 8993283183

32 Appendix 2

d. Photograph of Consultation with Local Residents of Ward No.14

Appendix 2 33

List of Participants attended Consultation with Local Residents of Ward No.14

English Translation S.N. Participants Mob. No. 01 Mahaveer Suman 8120079055 02 Raju Prajapati 8085801056 03 Gyaniram Suman 04 Monu 05 Sonu Sharma 06 Rakesh 07 Mohan 08 Dai 7447094379 09 Sher Singh 9893939356 10 Vahid Khan 9826712065 11 Rajesh Tripathi 7697547588 12 Ramnivas Rathor 9893453451

34 Appendix 2

e. Photograph of Consultation with CMO and Sub Engineer of Nagar Parishad Badoda and Ward Councillor

Discussion with Mr. Vivek Aggrawal, Sub Engineer

Discussion with Mr. Manohar Lal Prajapati, ward councillor Appendix 2 35

f. Photograph of Consultation with local residents of Ward No. 4 under Nagar Parishad

S.N. List of Participants S.N. List of Participants S.N. List of Participants 1 Murarilal prajapati ward 4 Budhdhi 7 Govind mahor Councilor 2 Rajendra panchal 5 Malkhan suman 8 Ajay mishra 3 Makhyajj nagar 6 Ramsingh 9

36 Appendix 2

g. Photograph of Consultation with local residents residing near existing OHT (250 KL) under Ward No. 7 Nagar Parishad

S.N. List of Participants S.N. List of Participants S.N. List of Participants 1 Dinesh kumar Sharma 4 Charan singh tomar 7 Satendra singh jadon 2 Suresh singh 5 Sultan 8 Rajendra panchal 3 Radhesyam varma 6 Pappu panchal 9 Ajay mishra

Appendix 3 37

Appendix 3: Involuntary Resettlement Screening Checklists

A. Introduction

Each project/subproject/component needs to be screen for any involuntary resettlement impacts which will occur or already occurred. This screening determines the necessary action to be done by the project team.

B. Information on project/subproject/component:

a. District/ Administrative Name: Sheopur b. Location: Badoda (24 Kms away from Sheopur) c. Civil work dates (proposed): Not yet proposed

Technical Description: Planning and design of Water Supply Scheme for Badoda. The scheme involves construction of anicut and intake well on Aheli river, construction of WTP, laying of transmission main and further distribution to end users by various distribution networks through gravitation.

C. Screening Questions for Involuntary Resettlement Impact

Below is the initial screening for involuntary resettlement impacts and due diligence exercise. Both permanent and temporary impacts must be considered and reported in the screening process.

Involuntary Resettlement Impacts Yes No Not Reason known Will the project include any physical ✓ Construction of intake well, WTP, construction work? transmission main and distribution network pipelines proposed

Does the proposed activity include ✓ No upgradation or rehabilitation of upgrading or rehabilitation of existing existing structures is proposed. physical facilities? Monitoring system (SCADA) will be installed within existing structures which will not involve any civil work Will there be permanent land ✓ Only revenue land under government of acquisition? MP is identified for construction of subproject components. Will it require temporary land ✓ acquisition? Is the ownership status and current ✓ All identified sites belong to government usage of the land known? / revenue department and it is vacant, free of any structures and encumbrances. All sites are vacant and belong to government.

Are there any non-titled people who ✓ All sites are free of non- live or earn their livelihood at the site titleholders/encroachers or within the corridor of impact (COI) / Right of Way (ROW)? Will there be loss of housing? ✓ Will there be loss of agricultural ✓ plots?

38 Appendix 3

Involuntary Resettlement Impacts Yes No Not Reason known Will there be losses of crops, trees, ✓ As distribution line will be proposed and fixed assets (i.e. fences, pumps, along the road in town, no losses to crop, etc.)? tree and fixed assets are assessed.

Will there be loss of businesses or ✓ During laying of distribution lines in enterprises? congested lanes, temporary arrangements will be made, pipeline will be located in unused government lands alongside the existing roads (within ROW) and can be constructed without causing disturbance to houses and commercial establishments.

Will there be loss of incomes and ✓ Temporary loss of incomes will be livelihoods? avoided through provisions of access planks by the contractor.

Will people lose access to facilities, ✓ Any disruption of public facilities or services, or natural resources? services will be taken care of during excavation. Grievance redress cell will be formed ward wise to settle the grievances soon.

Will any social or economic activities ✓ be affected by land use-related changes? Will people lose access to natural ✓ resources, or common property resources, or communal facilities and/or services? If land use is changed will it have an ✓ adverse impact on social and economic activities? Will access to land and resources ✓ owned communally or by the state be restricted? Are any of the affected persons (AP) ✓ from indigenous or ethnic minority groups?

D. Involuntary Resettlement Impact

After reviewing the answers above, Executing Agency / Safeguard Team confirms that the proposed subsection/ section/ subproject/component (tick as appropriate):

[ N ] Has involuntary resettlement impact, a resettlement plan (or corrective action plan) is required [ Y ] Has No involuntary resettlement impact, no resettlement plan is required.

Appendix 3 39

Prepared By: DARASHAW & CO.PVT. LTD, Verified by: PMU Safeguard Team under HYDERABAD MPUSIP Signature: Name: Signature: Position: Name: Position: Date: Date:

40 Appendix 4

Appendix 4: Land Details of Proposed Subproject Components Image of Proposed Khasra for WTP and Sump at Undiata village

English Translation: Village: Undiata, under Tehsil Badoda, District: Sheopur. Identified Khasra for Intake well cum approach bridge and WTP are 80 and 66 respectively. Note: Khasra map is sketch of pocket or location of land on map, land record maintained by the state government, which depicts for each land parcel, the parcel number. Appendix 4 41

Proposed Land for Intake well (Khasra No. 80) at Undiata village

The above records depict that the proposed site of Intake well is owned by government and has an area of 1.473 ha under Khasra Number 80.

42 Appendix 4

Proposed Land for WTP (Khasra No. 66) at Undiata village respectively

The above records depict that the proposed site of WTP is owned by government and has an area of 0.637 ha under Khasra Number 66.

Appendix 5 43

Appendix 5: Land Status Certificate of Proposed Components issued by Chief Municipal Officer-Badoda

44 Appendix 6

Appendix 6: Land Status Certificate of Existing Components issued by Chief Municipal Officer-Badoda

Appendix 7 45

Appendix 7: Location of proposed components on Google map

Showing Locations of Intake Well and Anicut

Showing Location of Proposed WTP