Public Disclosure Copy The World Bank Implementation Status & Results Report Qiantang River Basin Small Town Environment Project (P116656)

Zhejiang Qiantang River Basin Small Town Environment Project (P116656)

EAST ASIA AND PACIFIC | | Social, Urban, Rural and Resilience Global Practice Global Practice | IBRD/IDA | Specific Investment Loan | FY 2011 | Seq No: 11 | ARCHIVED on 05-Nov-2016 | ISR25563 | Public Disclosure Authorized

Implementing Agencies: Zhejiang Provincial Constrcution Commission Project Management Office

Key Dates

Key Project Dates

Bank Approval Date:20-Jan-2011 Effectiveness Date:06-May-2011 Planned Mid Term Review Date:07-Apr-2014 Actual Mid-Term Review Date:14-Apr-2014 Original Closing Date:31-Dec-2016 Revised Closing Date:31-Dec-2016 Public Disclosure Authorized Project Development Objectives

Project Development Objective (from Project Appraisal Document) To improve access to sustainable urban environmental infrastructure in selected cities, districts and towns in the Qiantang RiverBasin

Has the Project Development Objective been changed since Board Approval of the Project Objective? No

PHRPDODEL

Components Public Disclosure Authorized

Name Water Supply and Distribution:(Cost $46.64 M) Wastewater Collection and Treatment:(Cost $163.68 M) Solid Waste Management:(Cost $20.32 M) Institutional Strengthening and Training:(Cost $2.00 M)

Overall Ratings

Name Previous Rating Current Rating

Progress towards achievement of PDO  Satisfactory  Satisfactory

Public Disclosure Authorized Overall Implementation Progress (IP)  Satisfactory  Satisfactory Overall Risk Rating  Low  Low

11/5/2016 Page 1 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Zhejiang Qiantang River Basin Small Town Environment Project (P116656)

Implementation Status and Key Decisions

Overall progress towards achieving the project development objectives continues to be satisfactory. The two water treatment plants in City and Wucheng have been operating satisfactorily, serving 397,000 beneficiaries which exceeded the end of project targets. Four completed wastewater treatment plants and associated collection networks in Jiangde City, Qujiang District, Jianshan Town and Youbu Town are operating satisfactorily, with all the related PDO-level indicators exceeding the end of project targets. Three dumps have been closed and the sanitary landfill in Meicheng has been built and is operating satisfactorily. To date, 219,800 residents are being served with sanitary solid waste collection and disposal under this project, which exceeds the end of project target of 202,500 beneficiaries. All the agreed O&M plans have been operationalized. All project counties/cities have introduced tariffs which have improved the financial sustainability of the built assets, except Youbu Town which has collected the industrial tariffs but will start collecting residential tariffs in 2017. The Institutional Strengthening and Training component has improved the local capacity through consulting services and training activities. The capacity of the project implementation units on technical, operational and institutional aspects for sustainable infrastructure service provision have been strengthened through various training and study tours The project has also contributed to the ongoing provincial “Integrated Water EnvironmentManagement" program which aims to strategically improve the environmental quality and sustainable development in Zhejiang Province.

Risks

Systematic Operations Risk-rating Tool

Risk Category Rating at Approval Previous Rating Current Rating

Political and Governance  --  Low  Low Macroeconomic  --  Low  Low Sector Strategies and Policies  --  Low  Low Technical Design of Project or Program  --  Low  Low Institutional Capacity for Implementation and -- Low Low Sustainability    Fiduciary  --  Low  Low Environment and Social  --  Low  Low

11/5/2016 Page 2 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Zhejiang Qiantang River Basin Small Town Environment Project (P116656)

Stakeholders  --  Low  Low Other  --  --  -- Overall  --  Low  Low

Results

Project Development Objective Indicators

PHINDPDOTBL

 Number of people in urban areas provided with access to Improved Water Sources under the project (Number, Core)

Baseline Actual (Previous) Actual (Current) End Target

Value 60000.00 397000.00 397000.00 360418.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDPDOTBL

 Voume(mass) of COD pollution load reduction achieved under the project (Tones/year, Core)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 3723.00 4642.00 3907.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDPDOTBL

 Nutrient load reduction (Nitrogen(N)) achieved under the project (Tones/year, Core)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 152.00 152.00 141.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDPDOTBL

 Wastewater: Volume of Phosphorus pollution load reduction achived under the project (Tons/year) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 35.00 35.00 30.00

11/5/2016 Page 3 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Zhejiang Qiantang River Basin Small Town Environment Project (P116656)

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDPDOTBL

 Solid Waste: # of people served with sanitary solid waste collection and disposal under the project (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 219800.00 219800.00 202500.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDPDOTBL

 Institutional: Number of agreed O&M plans operationalized (cumulative) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 6.00 6.00 6.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDPDOTBL

 Financial: Number of project areas with tariffs/user fees introduced (cumulative) (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 7.00 10.00 10.00 10.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDPDOTBL

 Number of water utilities that the project is supporting (Number, Core)

11/5/2016 Page 4 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Zhejiang Qiantang River Basin Small Town Environment Project (P116656)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 2.00 2.00 2.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDPDOTBL

 Industrial and municipal waste disposal capacity created under the project (Metric ton, Core)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 210000.00 210000.00 210000.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

Overall Comments

Intermediate Results Indicators

PHINDIRITBL

 Water Supply: % of potable water connections to households: Zhuji City (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 30.00 95.00 95.00 95.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDIRITBL

 Water Supply: % of potable water connections to households: Wucheng District (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 100.00 100.00 95.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

11/5/2016 Page 5 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Zhejiang Qiantang River Basin Small Town Environment Project (P116656)

PHINDIRITBL

 Water Supply: % of full costs covered by water supply tariffs: Zhuji City (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 80.00 102.00 102.00 100.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDIRITBL

 Water Supply: % of full costs covered by water supply tariffs: Wucheng District (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 101.00 101.00 100.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDIRITBL

 Wastewater: % of wastewater collected and treated: City (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 97.00 97.00 85.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDIRITBL

 Wastewater: % of wastewater collected and treated: Qujiang District (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 93.00 93.00 80.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

11/5/2016 Page 6 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Zhejiang Qiantang River Basin Small Town Environment Project (P116656)

PHINDIRITBL

 Wastewater: % of wastewater collected and treated: Lanxi City, Youbu Town (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 75.00 75.00 70.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDIRITBL

 Wastewater: % of wastewater collected and treated: Pan'an County Jianshan Town (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 93.00 93.00 65.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDIRITBL

 Wastewater: % wastewater collected and treated: Pan'an County Shenze District (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 0.00 0.00 30.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

Comments Upon compleiton of the last 100 main sewers scheduled for end of November, the WW i

PHINDIRITBL

 Wastewater: % wastewater collected and treated: Jiangnan Town (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 75.00 75.00 75.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

11/5/2016 Page 7 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Zhejiang Qiantang River Basin Small Town Environment Project (P116656)

PHINDIRITBL

 Wastewater: % wastewater collected and treated: (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 91.00 91.00 85.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDIRITBL

 % of O&M treatment cost covered by wastewater tariffs: Jiande City (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 156.00 156.00 100.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDIRITBL

 % of O&M treatment cost covered by wastewater tariffs: Qujiang District (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 100.00 100.00 90.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDIRITBL

 % of O&M treatment cost covered by wastewater tariffs: Lanxi County Youbu Town (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 20.00 60.00 70.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

11/5/2016 Page 8 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Zhejiang Qiantang River Basin Small Town Environment Project (P116656)

PHINDIRITBL

 % of O&M treatment cost covered by wastewater tariffs: Pan'an County Jianshan Town (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 64.00 64.00 70.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDIRITBL

 Cumulative number of open solid waste dumps closed in Jiande City (Number, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 3.00 3.00 3.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDIRITBL

 % of solid waste collected and disposed at a sanitary landfill in Jiande City (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 100.00 100.00 90.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

PHINDIRITBL

 % of O&M cost covered by solid waste user fees in Jiande City (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 25.00 25.00 20.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

11/5/2016 Page 9 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Zhejiang Qiantang River Basin Small Town Environment Project (P116656)

PHINDIRITBL

 Wastewater: % of wastewater collected and treated: Pan’an County Yunshan District (Percentage, Custom)

Baseline Actual (Previous) Actual (Current) End Target

Value 0.00 95.00 95.00 75.00

Date 31-Dec-2009 31-Mar-2016 26-Oct-2016 31-Dec-2016

Overall Comments Almost all intermediate outcome indicators have achieved or exceeded the set targets. In Shenze, by completing of the last 100-meter main sewer in November 2016, 90% of the wastewater generated in the service area will be collected and conveyed to the WWTP. Youbu Town has started collecting the industrial wastewater treatment tariffs, but will begin collecting the residential wastewater treatment tariffs in early 2017. According to the financial projection, the O&M treatment cost covered by wastewater tariffs will meet the target in 2018. The O&M treatment cost covered by wastewater tariffs in Jianshan Town is the measured value for year 2015. The updated result for 2016 will be reported after December 2016.

Data on Financial Performance

Disbursements (by loan)

Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed

P116656 IBRD-80010 Effective USD 100.00 100.00 0.00 81.82 18.18 82%

Key Dates (by loan)

Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date

P116656 IBRD-80010 Effective 20-Jan-2011 03-Mar-2011 06-May-2011 31-Dec-2016 31-Dec-2016

Cumulative Disbursements

11/5/2016 Page 10 of 11 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Zhejiang Qiantang River Basin Small Town Environment Project (P116656)

Restructuring History

Level 2 Approved on 10-Mar-2015

Related Project(s)

There are no related projects.

11/5/2016 Page 11 of 11 Public Disclosure Copy