Quick viewing(Text Mode)

Cumulative Effects

Cumulative Effects

D O C U MD O E N T 6.1 4

Cumulative Effects

River Gas Pipeline Replacement Project

Under Regulation 5(2)(a) of the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009

Application Reference: EN060004 April 2015

Environmental Statement Volume 6 Environmental Statement Document 6.14

CONTENTS

Tables ...... ii Figures ...... iii DCO Documents Referenced ...... iii Abbreviations ...... iv 14 CUMULATIVE EFFECTS ...... 1 14.1 Introduction ...... 1 14.2 Regulatory and Planning Policy Framework ...... 1 14.3 Methodology ...... 2 14.4 Assessment of Intra-Project Effects ...... 6 14.5 Assessment of Inter-Project Cumulative Effects ...... 15 14.6 Difficulties Encountered in Compiling the ES ...... 41 14.7 Summary ...... 41 14.8 References ...... 42 14.9 Figures ...... 43

The River Humber Gas Pipeline Replacement Project Page i

Environmental Statement Volume 6 Environmental Statement Document 6.14

Tables

Table Title Table 14-1 Cumulative Effects Assessment - Significance Criteria for Determining Cumulative Effects Table 14-2 Cumulative Effects Assessment - Consultation Representations Table 14-3 Cumulative Effects Assessment - Intra-Project Effects of the Scheme Table 14-4 Cumulative Effects Assessment - Cumulative Developments and Plans – Goxhill Table 14-5 Cumulative Effects Assessment - Cumulative Developments and Plans – Table 14-6 Cumulative Effects Assessment - Indicative Timescales for Potential Cumulative Schemes Table 14-7 Cumulative Effects Assessment - Other Developments ‘Screened in’ and ‘Screened out’ of further Assessment Table 14-8 Cumulative Effects Assessment - Able UK Logistics Park – Detailed Cumulative Assessment Table 14-9 Cumulative Effects Assessment - Able Marine Energy Park – Detailed Cumulative Assessment Table 14-10 Cumulative Effects Assessment - OffShore Windfarm (Zone 4) – Project 1 – Detailed Cumulative Assessment Table 14-11 Cumulative Effects Assessment - Hornsea OffShore Windfarm (Zone 4) – Project 2 – Detailed Cumulative Assessment Table 14-12 Cumulative Effects Assessment - A160 - A180 Port of Improvement – Detailed Cumulative Assessment Table 14-13 Cumulative Effects Assessment - Killingholme Energy Centre – Detailed Cumulative Assessment Table 14-14 Cumulative Effects Assessment - Paull LDO – Detailed Cumulative Assessment Table 14-15 Cumulative Effects Assessment - LDO – Detailed Cumulative Assessment Table 14-16 Cumulative Effects Assessment - East Riding Local Plan (Not yet adopted) Haven Employment Site – Detailed Cumulative Assessment

The River Humber Gas Pipeline Replacement Project Page ii

Environmental Statement Volume 6 Environmental Statement Document 6.14

Figures

Figure Number Title Plate 14-1 Cumulative Effects Assessment: Inter-Project Cumulative Effects Assessment Diagram Figure 14.1 Major Planned Developments DCO Documents Referenced

DCO Document Title of Document Reference 5.4 Habitats Regulation Assessment 6.4.1 Appendix 4.1: PINS Scoping Comments 6.4.2 Appendix 4.2: Section 42 Consultation Comments 6.5 Chapter 5: Air Quality 6.6 Chapter 6: Cultural Heritage 6.7 Chapter 7: Ecology and Nature Conservation 6.9 Chapter 9: Landscape and Visual Amenity 6.10 Chapter 10: Noise and Vibration 6.11 Chapter 11: Socio-Economics and Land Use 6.12 Chapter 12: Traffic and Transport 6.13.2 Appendix 13.2 Initial Site Water Management Plan 6.17 Scoping Opinion 7.2.1 Initial Traffic Management Plan 7.3 Initial Construction Environmental Management Plan

The River Humber Gas Pipeline Replacement Project Page iii

Environmental Statement Volume 6 Environmental Statement Document 6.14

Abbreviations

AGI Above Ground Installation CEMP Construction Environmental Management Plan DCO Development Consent Order DMRB Design Manual for Roads and Bridges DPD Development Plan Document EIA Environmental Impact Assessment ES Environmental Statement GW Gigawatt HRA Habitats Regulations Assessment km Kilometres kV kilovolt LDO Local Development Order NPS National Policy Statement NSIP Nationally Significant Infrastructure Project MW Megawatt PINS Planning Inspectorate

The River Humber Gas Pipeline Replacement Project Page iv

Environmental Statement Volume 6 Environmental Statement Document 6.14

14 CUMULATIVE EFFECTS 14.1 Introduction

14.1.1 This chapter presents the findings of the Cumulative Effects Assessment. It describes the requirement for the assessment of cumulative effects, the guidance available for completing the assessment in relation to Nationally Significant Infrastructure Projects (NSIP) and presents the results of the assessment.

14.1.2 Cumulative effects are the result of multiple actions on environmental receptors or resources. There are principally two types of cumulative effect:

. The combined action of a number of different environmental topic specific effects upon a single resource/receptor (Intra-Project Effects); and . The combined action of a number of different projects, in combination with the project being assessed, on a single resource/receptor (Inter-Project Effects).

14.1.3 This chapter should be read in conjunction with Figure 14.1. 14.2 Regulatory and Planning Policy Framework

14.2.1 Schedule 4 of the Infrastructure Planning (Environmental Impact Assessment (EIA)) Regulations 2009 as amended states that an Environmental Statement (ES) should include:

‘A description of the likely significant effects of the development on the environment, which should cover the direct effects and any indirect, secondary, cumulative, short, medium and long-term permanent and temporary, positive and negative effects of the development, resulting from:

a) The existence of the development;

b) The use of natural resources; or

c) The emission of pollutants, the creation of nuisances and the elimination of waste.

And the description by the applicant of the forecasting methods used to assess the effects on the environment.’

14.2.2 The Overarching National Policy Statement for Energy (NPS EN-1) states the following in relation to requirements for the assessment of cumulative effects:

‘When considering cumulative effects, the ES should provide information on how the effects of the applicant’s proposal would combine and interact with the effects of other developments (including projects for which consent has been sought or granted, as well as those already in existence).’

The River Humber Gas Pipeline Replacement Project Page 1

Environmental Statement Volume 6 Environmental Statement Document 6.14

14.3 Methodology

Relevant Guidance

14.3.1 A number of sources provide guidance on how to complete a Cumulative Effects Assessment.

14.3.2 According to the Design Manual for Roads and Bridges (DMRB), Volume 11, Section 2, Part 5 (HA 205/08) ‘Assessment and Management of Environmental Effects’, cumulative effects result from multiple actions on receptors and resources over time and are generally additive or interactive (synergistic) in nature. Cumulative effects can also be considered as impacts resulting from incremental changes caused by other past, present or reasonably foreseeable actions together with the project.’

14.3.3 The European Commission has published the ‘Guidelines for the Assessment of Indirect and Cumulative Impacts as well as Impact Interactions. Prepared for the European Commission, EC DG X1 Environment, Nuclear Safety and Civil Protection’ (Hyder Consulting UK Limited, 1999), which provides information on methods, the assessment process and information needed to assess the impacts.

14.3.4 The Planning Inspectorate (PINS) Advice Note 9 ‘The Rochdale Envelope’ (2011) also provides advice in relation to the assessment of cumulative effects stating:

“The potential cumulative impacts with other major developments will also need to be carefully identified such that the likely significant impacts can be shown to have been identified and assessed against the baseline position (which would include built and operational development). In assessing cumulative impacts, other major development should be identified through consultation with local planning authorities and other relevant authorities on the basis of those that are:

. Under construction; . Permitted application(s), but not yet implemented; . Submitted application(s) not yet determined; . Projects on the Planning Inspectorate’s Programme of Projects; . Identified in the relevant Development Plan (and emerging Development Plans – with appropriate weight being given as they move closer to adoption) recognising that much information on any relevant proposals will be limited; and . Identified in other plans and programmes (as appropriate) which set the framework for future development consents/approvals, where such development is reasonably likely to come forward.

14.3.5 The assessment has drawn on elements of the above guidance and in particular, the EC Guidance (Hyder Consulting UK Limited, 1999) has been used in consideration of the types of impact e.g. spatial, temporal, receptor based approach, the PINS Advice Note 9 has been used to identify the types of The River Humber Gas Pipeline Replacement Project Page 2

Environmental Statement Volume 6 Environmental Statement Document 6.14

developments that should be considered and the DMRB guidance has been used to define significance.

Assessment Approach

14.3.6 The assessment approach for the different types of cumulative effects is outlined below.

Cumulative Effects Resulting from Multiple Environmental Topic Effects on a Receptor – Intra-Project Effects

14.3.7 An example of this type of cumulative effects would be where a local resident is affected by dust, noise and traffic disruption during construction, with the result being a greater nuisance than each individual effect alone.

14.3.8 For cumulative effects assessment, the key is to focus on the receptor and consider its capacity to accommodate the changes that are likely to occur because of the Scheme. Residual effects on specific receptors are presented in Chapters 5 to 13 of this ES (Development Consent Order (DCO) Document Reference 6.5 - 6.13). Using this information, the receptors have been identified that could experience multiple effects and an assessment is made of their likely cumulative significance.

14.3.9 The significance of cumulative effects has been determined using the criteria in Table 14-1 taken from the DMRB.

Table 14-1 Cumulative Effects Assessment - Significance Criteria for Determining Cumulative Effects Significance Effects Severe Effects that the decision-maker must take into account as the receptor/resource is irretrievably compromised. Major Effects that may become a key decision-making issue. Moderate Effects that are unlikely to become issues on whether the project design should be selected, but where future work may be needed to improve on current performance. Minor Effects that are locally significant. Not Significant Effects that are beyond the current forecasting ability or are within the ability of the resource to absorb such change. Cumulative Effects Resulting from Interactions with Other Projects – Inter- Project Effects

14.3.10 Inter-Project Effects occur as a result of a number of developments, which individually might not be significant, but when considered together could create a significant cumulative effect on a shared receptor, and include development separate from and related to the Scheme.

The River Humber Gas Pipeline Replacement Project Page 3

Environmental Statement Volume 6 Environmental Statement Document 6.14

14.3.11 A number of developments have been identified for consideration within the cumulative effects assessment. This list was compiled during the screening and scoping stages of the EIA process and has been updated throughout the preparation of the ES to reflect the latest circumstances. This list of potential cumulative schemes has also been informed by consultation with North Council and East Riding of Council. Refer to Figure 14.1 for the location of the other developments.

14.3.12 The Inter-Project cumulative effects assessment has been split into two distinct stages, initial screening and a more detailed assessment. The initial screening stage provides a high level screening ‘matrix style’ assessment to determine if any of the identified developments could possibly lead to significant cumulative effects with the Scheme. The purpose of this initial stage was to eliminate those developments from the assessment which very clearly would not generate any cumulative effects in order to focus on those developments where there was potential or uncertainty. For example if the development was located at a far enough distance from the Scheme with no overlap in construction periods the development was screened out for further assessment.

14.3.13 Those developments for which cumulative effects were uncertain, based on location, timing, nature and scale of the development were carried forward for more detailed assessment. The detailed assessment comprised assessing each of the identified developments in relation to the potential effects predicted as a result of the development for each environmental topic. The detailed assessment took into consideration distance from the Scheme, construction timetables, nature and scale of the developments and their resultant environmental effects. For each of the developments identified as potentially having a cumulative effect the assessment presents the likely residual cumulative effects using the significance criteria defined in Table 14-1. It should be noted that in certain circumstances the potential for the cumulative developments, in combination with the River Humber Gas Pipeline Replacement Scheme to lead to significant cumulative effects was identified.

14.3.14 Plate 14-1 provides a summary of the two stage assessment process.

The River Humber Gas Pipeline Replacement Project Page 4

Environmental Statement Volume 6 Environmental Statement Document 6.14

Plate 14-1 Cumulative Effects Assessment: Inter-Project Cumulative Effects Assessment Diagram

•All identified developments with the potential to generate cumulative effects initially 'screened'. •Initial 'screening' considered location, timing, nature and scale of Stage 1a ‐ Initial Screening the development and potential effects.

•Developments eliminated i.e. Screened Out from further assessment which clearly would not generate cumulative effects. •Developments where cumulative effects were uncertain were Stage 1b ‐ Initial carried forward for more detailed assessment i.e. Screened In. Screening

• Detailed assessment of each of the identified developments in relation to the potential effects predicted for each environmental topic ‐ considering distance from the River Humber Gas Pipeline Replacement Project, construction timtables, nature and scale. Stage 2 ‐ Detailed • Assessment states whether cumulative effetcs are, severe, Assessment major, moderate, minor or not significant.

Summary of Consultation on the Cumulative Effects Assessment

14.3.15 The Scoping Report submitted to PINS outlined the methodology for the cumulative effects assessment. Further information was also provided in the Preliminary Environmental Information Report (Hyder, 2014).

14.3.16 A summary of all consultation responses relevant to this assessment along with how comments from stakeholders were addressed in this ES Chapter are outlined in Appendices 4.1 and 4.2 (DCO Document Reference 6.4.1 and 6.4.2).

14.3.17 Table 14-2 provides details of additional consultation undertaken following the receipt of the Scoping Opinion (DCO Document Reference 6.17) and the Section 42 Consultation Responses.

Table 14-2 Cumulative Effects Assessment - Consultation Representations Consultee Date of Summary of Results of Consultation Consultation East Riding of 13 November Email correspondence confirmed the cumulative list of Yorkshire 2014 developments complete. Council

The River Humber Gas Pipeline Replacement Project Page 5

Environmental Statement Volume 6 Environmental Statement Document 6.14

Consultee Date of Summary of Results of Consultation Consultation East Riding of 24 November Telephone call with Council regarding Yorkshire 2014 plans for the Paull Local Development Order (LDO), plans for Council the Hull LDO and plans for the Siemens Blade Manufacturing Plant. Call determined that the Council is in talks with developers for the Paull LDO, however, there is nothing in place at this current time. Hull LDO is at a similar stage i.e. there are no applications made as yet (i.e. November 2014) for this site either. Confirmed both sites are economically viable and ear marked for the ‘green energy’ - offshore/onshore wind generation industry. The Council also confirmed that the Paull Blade factory will now go ahead at Green Port Hull rather than Paull. North 24 November Email correspondence confirmed the cumulative list of Lincolnshire 2014 developments complete with the addition of the Lincolnshire Council Lakes Development in .

14.4 Assessment of Intra-Project Effects

14.4.1 Intra-project effects have been presented for receptors which could be affected by more than one ES topic. Where only one effect has been identified for a particular receptor or only one topic has identified effects on that receptor there is no potential for an intra-project effect to occur. Intra-project cumulative effects have therefore only been identified where more than one ES Chapter has identified a residual effect on an individual or group of receptors. Table 14-3 presents the findings of the intra-project cumulative effects assessment.

The River Humber Gas Pipeline Replacement Project Page 6

Environmental Statement Volume 6 Environmental Statement Document 6.14

Table 14-3 Cumulative Effects Assessment - Intra-Project Effects of the Scheme Receptor (Relevant Chapter Effect Reported in Assessment of Cumulative Effects Figure Reference) Chapter Lynton Stud Chapter 5: Air Quality No significant air quality Intra-project effects would be not significant as the only adverse Residential Property (DCO Document effects. effects on Lynton Stud Residential Property would be associated Reference 6.5) with noise and vibration. Chapter 9: Landscape Negligible and Visual Amenity (DCO Document Reference 6.9) Chapter 10: Noise and Daytime: moderate Vibration (DCO adverse Document Reference Night time: slight 6.10) adverse Vibration: negligible Venting (very short duration): moderate adverse Spring Farm Chapter 5: Air Quality No significant air quality Intra-project effects would be moderate as moderate adverse (DCO Document effects. effects were predicted at Spring Farm within both the landscape Reference 6.5) and visual amenity assessment (due to view of the construction works) and the noise and vibration assessment. However, Chapter 9: Landscape Moderate adverse moderate adverse effects are based on a worst case scenario, and Visual Amenity during construction would be temporary during construction and potentially (DCO Document phase. intermittent. Reference 6.9) The Initial Construction Environmental Management Plan Chapter 10: Noise and Daytime: moderate (CEMP) (DCO Document Reference 7.3) provides a number of Vibration (DCO adverse

The River Humber Gas Pipeline Replacement Project Page 7

Environmental Statement Volume 6 Environmental Statement Document 6.14

Receptor (Relevant Chapter Effect Reported in Assessment of Cumulative Effects Figure Reference) Chapter Document Reference Night time: slight commitments the Main Works Contractor would be required to 6.10) adverse adhere to during construction including monitoring of effects. Vibration: negligible Venting (very short duration): moderate adverse Chapter 13: Water Moderate adverse Resources (DCO Document Reference 6.13) Fir Tree Farm Chapter 9: Landscape Moderate adverse Intra-project effects would be moderate as moderate adverse and Visual Amenity during construction effects were predicted at Fir Tree Farm within the landscape and (DCO Document phase. visual amenity assessment (due to views of the construction Reference 6.9) works), the noise and vibration assessment and the groundwater assessment: Chapter 10: Noise and Daytime: moderate Vibration (DCO adverse The Hydrogeological Impact Assessment (DCO Document Reference 6.14.3) indicates there would be a lowering of the Document Reference Night time: slight groundwater level, which may affect water abstraction from the 6.10) adverse borehole (estimated to be 41 days). Vibration: negligible However, moderate adverse effects are based on a worst case Venting (very short scenario, would be temporary during construction and potentially duration): moderate intermittent. adverse The Initial CEMP (DCO Document Reference 7.3) provides a Chapter 13: Water Moderate adverse number of commitments the Main Works Contractor would be Resources required to adhere to during construction including monitoring of effects. Uplands Lodge Chapter 9: Landscape Negligible and Visual Amenity The River Humber Gas Pipeline Replacement Project Page 8

Environmental Statement Volume 6 Environmental Statement Document 6.14

Receptor (Relevant Chapter Effect Reported in Assessment of Cumulative Effects Figure Reference) Chapter (DCO Document Intra-project effects would be not significant as the only adverse Reference 6.9) effects at Uplands Lodge would be associated with noise and Chapter 10: Noise and Daytime: moderate vibration. Vibration (DCO adverse Document Reference Night time: slight 6.10) adverse Vibration: negligible Venting (3 hours): moderate adverse East Marsh Farm Chapter 9: Landscape Negligible Intra-project effects would be not significant as the only adverse and Visual Amenity effects on East Marsh Farm Uplands Lodge would be associated (DCO Document with noise and vibration. Reference 6.9) The Hydrogeological Impact Assessment (DCO Document Chapter 10: Noise and Daytime: moderate Reference 6.13.3) indicates there would be a lowering in the Vibration (DCO adverse groundwater level, which may affect the ponds at East Marsh Farm. Document Reference Night time: slight 6.10) adverse Vibration: negligible Venting (very short duration): moderate adverse Chapter 13: Water Moderate adverse Resources (DCO Document Reference 6.13)

The River Humber Gas Pipeline Replacement Project Page 9

Environmental Statement Volume 6 Environmental Statement Document 6.14

Receptor (Relevant Chapter Effect Reported in Assessment of Cumulative Effects Figure Reference) Chapter Lakes Farm Chapter 5: Air Quality No significant air quality Intra-project effects would be moderate as moderate adverse (DCO Document effects. effects were predicted at Lakes Farm within both the landscape Reference 6.5) and visual amenity assessment (due to views of the construction works) and the noise and vibration assessment. However, Chapter 9: Landscape Moderate adverse moderate adverse effects are based on a worst case scenario, and Visual Amenity during construction would be temporary during construction and potentially (DCO Document phase. intermittent. Reference 6.9) The Initial CEMP (DCO Document Reference 7.3) provides a Chapter 10: Noise and Daytime: moderate number of commitments the Main Works Contractor would be Vibration (DCO adverse required to adhere to during construction including monitoring of Document Reference Night time: slight effects. 6.10) adverse Vibration: negligible Venting (very short duration): moderate adverse Chapel Farm Chapter 9: Landscape No impact. Intra-project effects would be not significant as the only adverse and Visual Amenity effects at Chapel Farm would be associated with noise and (DCO Document vibration. Reference 6.9) Chapter 10: Noise and Daytime: moderate Vibration (DCO adverse Document Reference Night time: slight 6.10) adverse Vibration: negligible

The River Humber Gas Pipeline Replacement Project Page 10

Environmental Statement Volume 6 Environmental Statement Document 6.14

Receptor (Relevant Chapter Effect Reported in Assessment of Cumulative Effects Figure Reference) Chapter Venting (very short duration): moderate adverse Chapter 13: Water Moderate adverse The Hydrogeological Impact Assessment (DCO Document Resources (DCO Reference 6.13.3) indicates there would be a lowering in the Document Reference groundwater level, which may affect water abstraction from the 6.13) borehole at Chapel Farm. The Hall and Chapter 6: Cultural Potential effects on Intra-project effects would be not significant as the only adverse associated Stables Heritage (DCO setting. Slight adverse effects at The Hall would potentially be associated with cultural and adjoining Coach Document Reference predicted during heritage. House 6.6) construction phase only. Chapter 9: Landscape Negligible and Visual Amenity (DCO Document Reference 6.9) South Pasture Chapter 9: Landscape Negligible Intra-project effects would be not significant as the only adverse and Visual Amenity effects at South Pasture would be associated with noise and (DCO Document vibration. Reference 6.9) Chapter 10: Noise and Daytime: moderate Vibration (DCO adverse Document Reference Night time: slight 6.9) adverse Vibration: negligible

The River Humber Gas Pipeline Replacement Project Page 11

Environmental Statement Volume 6 Environmental Statement Document 6.14

Receptor (Relevant Chapter Effect Reported in Assessment of Cumulative Effects Figure Reference) Chapter Venting (very short duration): moderate adverse Rose Hill (please note Chapter 9: Landscape Slight adverse during Intra-project effects would be minor / moderate. However, that this property and Visual Amenity construction. moderate adverse effects are based on a worst case scenario, would be rented by (DCO Document would be temporary during construction and potentially National Grid Gas staff Reference 6.9) intermittent. for the duration of the Chapter 10: Noise and Daytime: moderate The Initial CEMP (DCO Document Reference 7.3) provides a works and would Vibration (DCO adverse number of commitments the Main Works Contractor would be comprise the affected required to adhere to during construction including monitoring of Document Reference Night time: slight receptors) effects. 6.19) adverse

Vibration: negligible Venting (very short duration): moderate adverse Boreas Hall Farm Chapter 9: Landscape Negligible Intra-project effects would be not significant as the only adverse and Visual Amenity effects at Boreas Hall Farm would be associated with noise and (DCO Document vibration. Reference 6.9) Chapter 10: Noise and Daytime: moderate Vibration (DCO adverse Document Reference Night time: slight 6.19) adverse Vibration: negligible Venting (very short duration): moderate adverse

The River Humber Gas Pipeline Replacement Project Page 12

Environmental Statement Volume 6 Environmental Statement Document 6.14

Receptor (Relevant Chapter Effect Reported in Assessment of Cumulative Effects Figure Reference) Chapter Chapter 13: Water Negligible Resources (DCO Document Reference 6.13) Footpaths 50, 70, 72, Chapter 5: Air Quality No significant air quality Intra-project effects would be minor as minor / slight adverse / 73, 1, 2 and 6 (DCO Document effects. negative effects were predicted at Footpaths 50, 70, 73 and 6 Reference 6.5) within both the landscape and visual amenity assessment and the socio-economic and land use assessment. However, minor Chapter 9: Landscape Footpath 50 – slight adverse effects would be relatively short-lived and transient for and Visual Amenity adverse during the user of the footpaths as they travel along the paths. In (DCO Document construction addition, effects would only last for the duration of the Reference 6.9) Footpath 72: negligible construction phase and would, therefore, be temporary in nature. Footpath 70: slight The Initial CEMP (DCO Document Reference 7.3) provides a adverse during the number of commitments the Main Works Contractor would be construction period. required to adhere to during construction including monitoring of Footpath 73: slight effects. adverse during the construction period. Footpaths 1: negligible Footpath 6: slight adverse during construction. Footpath 2: negligible. Chapter 11: Socio- Footpath 50: negligible. Economics and Land Footpath 70: negligible. Use (DCO Document Footpaths 72 and 73: Reference 6.11) negligible.

The River Humber Gas Pipeline Replacement Project Page 13

Environmental Statement Volume 6 Environmental Statement Document 6.14

Receptor (Relevant Chapter Effect Reported in Assessment of Cumulative Effects Figure Reference) Chapter Footpaths 1 and 6: Minor negative. During the maximum three day closure. Footpath 2: negligible. With a minor negative on amenity for all users during construction. Humber Chapter 5: Air Quality No significant air quality Intra-project effects would be not significant as no significant European Site and (DCO Document effects. adverse effects were anticipated on the Humber Estuary associated bird Reference 6.5) European Site and associated bird species / assembledges. species / Chapter 7: Ecology Potential displacement, assembledges. and Nature visual disturbance, Conservation (DCO noise disturbance, Document Reference vehicle movements and 6.7) loss of habitat. All assessed as not significant following the implementation of environmental design and enhancement measures. Chapter 13: Water Negligible Resources (DCO Document Reference 6.13)

The River Humber Gas Pipeline Replacement Project Page 14

Environmental Statement Volume 6 Environmental Statement Document 6.14

14.5 Assessment of Inter-Project Cumulative Effects

Identification of Other Developments

14.5.1 Details of the other developments that could potentially generate cumulative effects with the Scheme are provided in Table 14-4 and presented on Figure 14.1.

14.5.2 The information presented is based on the information available at the time of submission of this ES about the developments and their delivery timescales. The greatest level of uncertainty is related to delivery timescales as these can be subject to change following publication of an ES and supporting environmental information.

14.5.3 It should be noted where timescales could not be confirmed for other developments we adopted a worst case assumption that construction would run parallel to the Scheme.

The River Humber Gas Pipeline Replacement Project Page 15

Environmental Statement Volume 6 Environmental Statement Document 6.14

Table 14-4 Cumulative Effects Assessment - Cumulative Developments and Plans – Goxhill Type of Development Details Development Status Timescales Approx. Distance Development from the Scheme Under Construction No developments identified. Permitted Applications but not yet Implemented Able UK Logistics The construction of around 1,500m of Full planning permission Construction programmed for Located Park new quays, facilities for off-shore wind granted. summer 2015. approximately (Drawing Ref: 4 on turbine manufacture, assembly and 540m to the south Figure 14.1) installation, and associated supply chain east operations. Lincolnshire Lakes, The development will comprise new Lincolnshire Lakes Expected to start in 2015 and Located in excess Scunthorpe villages (up to 3,500 new units in two concept as adopted in complete in 2026. of 25km to the This development is villages), a commercial park, new local the south west not shown on amenities, a new primary school, flood Council’s Core Strategy Figure 14.1 owing defences, a new terminating junction for (June 2011). to the distance from the M181, a new access to Scotter Road the Scheme. and wider highways improvements. Nationally Significant Infrastructure Projects Able Marine Energy Development of a quay of solid DCO granted The ES stated that a minimum Located Park (Drawing Ref: construction on the south bank of the 18/12/2013. two year construction approximately 1 on Figure 14.1) Humber Estuary, with an ecological programme is anticipated for 4,160m to the compensation scheme comprising both the marine works. Preparatory south east temporary and permanent habitat work on site has commenced. creation on the opposite bank, dredging (August 2014, Able and land reclamation, onshore facilities UK).Construction of buildings for the manufacture, assembly and will commence in 2016 with quays becoming available early

The River Humber Gas Pipeline Replacement Project Page 16

Environmental Statement Volume 6 Environmental Statement Document 6.14

Type of Development Details Development Status Timescales Approx. Distance Development from the Scheme storage of marine energy installation 2018 (source: Able UK components. website).

Hornsea Offshore Project 1 will constitute up to three DCO granted Construction is proposed in Located Wind Farm (Zone 4) offshore wind generating stations with a 10/12/2014. 2016 with onshore features approximately - Project 1 (Drawing total capacity of up to 1,200 MW, constructed in the first three 3,830m to the Ref: 10 on Figure including all offshore and onshore years. south. 14.1) infrastructure. Hornsea Offshore Project 2 will connect to Killingholme Submitted to PINS. Construction timescales Located Wind Farm (Zone 4) North 400 kilovolt (kV) substation. The unknown but the onshore approximately – Project 2 majority of the route will follow that of elements are assumed to be 3,830m to the (Drawing Ref: 10 on Project One. constructed as part of Project south. Figure 14.1) One. A160 - A180 Port of Highways Agency. 06/11/2014 Project being brought forward Located Immingham The development aims to improve road Recommendation issued under the accelerated roads approximately Improvement access to the in order by The Planning programme. 6,560m to the (Drawing Ref: 2 on to meets the needs of the current traffic Inspectorate. Target is for construction to south Figure 14.1) flows and predicted growth in traffic 04/02/2015 Secretary of commence in 2015 and be resulting from planned and approved State has granted completed in Autumn 2016. development at the port. development consent Proposed thermal generating station that DCO granted Construction is expected in Located Power Project will operate either as a combined cycle 11/09/2014. 2015 and C.GEN Killingholme approximately (Drawing Ref: 3 on gas turbine plant or as an integrated Ltd states commercial operation 2,080m to the Figure 14.1) gasification combined cycle plant, with a is expected 2016-2017. south total electrical output of up to 470 megawatts (MW).

The River Humber Gas Pipeline Replacement Project Page 17

Environmental Statement Volume 6 Environmental Statement Document 6.14

Type of Development Details Development Status Timescales Approx. Distance Development from the Scheme Killingholme Energy Combined cycle gas turbine with a Pre Application. Construction timescales Located Centre (Drawing nominal generating capacity of up to unknown. Earliest construction approximately Ref: 11 on Figure 1,200MW and associated overhead start is 2017. 3,800m to the 14.1) power lines, gas pipeline and highway south access. Dogger Bank Dogger Bank A & B (previously Examination. 2015 onwards pre-construction, Located in excess Teesside A & B part of Dogger Bank Teesside) is the construction and operation. of 125km to the This development is second stage of Forewind’s offshore wind east not shown on energy development of the Dogger Bank Figure 14.1 owing Zone (Zone 3, Round 3). Dogger Bank to the distance from Teesside A & B will comprise up to two the Scheme. wind farms, each with an installed capacity of up to 1.2 gigawatts (GW), which are expected to connect to the national grid at the existing national grid substation at Lackenby, near Eston. Dogger Bank Teesside A & B is located within The Dogger Bank Zone which comprises an area of 8660 square kilometres (km2) located in the between 125 kilometres (km) and 290km off the UK North East coast. The onshore elements of the development will be located in the Borough of Redcar and Cleveland. Dogger Bank Dogger Bank Teesside C & D (previously Pre Application. Construction timescales Located in excess Teesside C & D part of Dogger Bank Teesside) is the uncertain. of 125km to the This development is third stage of Forewind’s offshore wind east not shown on energy development of the Dogger Bank The River Humber Gas Pipeline Replacement Project Page 18

Environmental Statement Volume 6 Environmental Statement Document 6.14

Type of Development Details Development Status Timescales Approx. Distance Development from the Scheme Figure 14.1 owing Zone (Zone 3, Round 3). Dogger Bank to the distance from Teesside C & D will comprise up to two the Scheme. wind farms, each with an installed capacity of up to 1.2GW, which are expected to connect to the national grid in Teesside, just south of the Tees Estuary. Therefore, Dogger Bank Teesside C & D could have a total installed capacity of up to 2.4GW. Projects identified in the Relevant Development Plan or other plans No developments identified.

The River Humber Gas Pipeline Replacement Project Page 19

Environmental Statement Volume 6 Environmental Statement Document 6.14

Table 14-5 Cumulative Effects Assessment - Cumulative Developments and Plans – Paull Type of Development Details Development Status Timescales Approx. Distance Development from the Scheme Under Construction EON Humber Underground electricity cable routed Planning consent Offshore construction Appears to cross Gateway Onshore within proximity to Paull Above Ground granted – construction commencement: August 2013, the application site Installation, Hull Installation (AGI). commenced. targeted completion: 2015. at the Rose Hill (Drawing Ref: 5 on access track. Figure 14.1) Green Port Hull, Development will include a facility for Planning consent Completion of construction work Located Alexander Dock, wind turbine equipment assembly, with granted in May 2012. is anticipated in 2017. approximately Hull component storage areas, offices and car 5,050m to the (Drawing Ref: 6 on parking, plus a new 600m riverside berth north west Figure 14.1) for the export of wind turbine components. Development will also include a rotor blade manufacturing facility to be constructed alongside the assembly Permitted Applications but not yet Implemented Paull LDO Site The Humber Renewable Energy Super Reserved matters Construction and operational Located (Drawing Ref: 7 on Cluster Enterprise Zone and the Humber applications still need to timescales uncertain. approximately Figure 14.1) Green Port Corridor Enterprise Zone are be submitted. 307m to the west relevant to the proposed Paull LDO. The aim of the Humber Enterprise Zones is to attract large top-tier manufacturing companies and associated supply chains to sites around the Humber, to create a renewable energy super cluster.

The River Humber Gas Pipeline Replacement Project Page 20

Environmental Statement Volume 6 Environmental Statement Document 6.14

Type of Development Details Development Status Timescales Approx. Distance Development from the Scheme Port of Hull LDO The Port of Hull LDO grants outline Reserved matter Construction and operational Located (Drawing Ref: 8 on planning permission for development that applications still need to timescales uncertain. approximately Figure 14.1) is associated with renewable and low be submitted. 2,330m to the carbon industries. north west Nationally Significant Infrastructure Projects Dogger Bank Offshore site will comprise of two 17/02/2015 – Secretary Construction timescale not Located in excess Creyke Beck. windfarms expected to connect to the of State has granted confirmed but expected 2016- of 15km to the This development is national grid in the East Riding of development consent 2018 with the first phase to be north west not shown on Yorkshire. for this application. online for 2019. Figure 14.1 owing to the distance from the Scheme. A63 Castle Street Improvement of a one mile stretch of A63 Pre Application. Construction expected Located Improvements at Castle Street. 2016/2017 to complete in 2020. approximately (Drawing Ref: 9 on 7,780m to the Figure 14.1) north west Projects Identified in the Relevant Development Plan East Riding Local Area between Paull and Saltend Adoption expected early Unknown. Located directly Plan (adoption Chemicals site allocated as key 2015. north of the expected 2015) employment area. application site at This site is allocated due to the potential the Rose Hill Employment Site. it offers to support the economy of the access track (Drawing Ref 12 on East Riding, the Humber and general Figure 14.1) sub-region. Restricting the development of this site will ensure that the most effective use is made of this limited resource, and ensure that the East

The River Humber Gas Pipeline Replacement Project Page 21

Environmental Statement Volume 6 Environmental Statement Document 6.14

Type of Development Details Development Status Timescales Approx. Distance Development from the Scheme Riding is in a prime position to benefit from its growth potential. Sand and Gravel The sand and gravel safeguarding areas Submission of DPD – Unknown. The areas partially Safeguarding Areas do not imply a presumption in favour of Expected Winter covers the - East Riding of mineral working. The minerals 2014/15 application site Yorkshire and Hull safeguarding policy is a means of Examination of DPD – City Council Joint balancing the relative importance of any Expected Spring 2015 Minerals underlying mineral against any proposals Adoption of DPD - Development Plan for non mineral development. Expected Summer Document (DPD) NB Sand and gravel safeguarded areas 2015. (Drawing Ref: 13 on cover a significant area of the East Figure 14.1) Riding of Yorkshire.

The River Humber Gas Pipeline Replacement Project Page 22

Environmental Statement Volume 6 Environmental Statement Document 6.14

14.5.4 Table 14-6 outlines the current timescales for construction of the other developments based on publicly available information.

Table 14-6 Cumulative Effects Assessment - Indicative Timescales for Potential Cumulative Schemes Under construction Operational Unknown so assumed timescales

Development Name 2014 2015 2016 2017 2018 2019 2020 Goxhill

River Humber Gas Pipeline Replacement Project Able UK Logistics Park (Drawing Ref: 4 on Figure 14.1) Lincolnshire Lakes, Scunthorpe

Able Marine Energy Park (Drawing Ref: 1 on Figure 14.1) Hornsea Offshore Wind Farm (Zone 4) - Project 1 Hornsea Offshore Wind Farm (Zone 4) - Project 2 A160 - A180 Port of Immingham Improvement (Drawing Ref: 2 on Figure 14.1) North Killingholme Power Project (Drawing Ref: 3 on Figure 14.1) Killingholme Energy Centre (Drawing Ref: 11 on Figure 14.1) Dogger Bank Teesside A & B

Dogger Bank Teesside C & D Paull

EON Humber Onshore Installation (Drawing Ref: 5 on Figure 14.1) Green Port Hull, Alexander Dock, Hull (Drawing Ref 6: on Figure 14.1)

The River Humber Gas Pipeline Replacement Project Page 23

Environmental Statement Volume 6 Environmental Statement Document 6.14

Development Name 2014 2015 2016 2017 2018 2019 2020 Paull LDO (Drawing Ref: 7 on Figure 14.1) Port of Hull LDO (Drawing Ref: 8 on Figure 14.1) Dogger Bank Creyke Beck

A63 Castle Street Improvements (Drawing Ref: 9 on Figure 14.1) East Riding Local Plan Hedon Haven Employment Site (Drawing Ref 12 on Figure 14.1) Minerals Safeguarded Areas - East Riding of Yorkshire Council and Joint Minerals DPD (Drawing Ref: 13 on Figure 14.1) Screening of the Other Developments

14.5.5 The information presented in Tables 14-4 and 14-5 has been used to make a decision about whether developments need to be considered within the cumulative effects assessment. Table 14-7 therefore presents the initial screening of developments listed in Tables 14-4 and 14-5 and determines whether each development has been ‘screened in’ or ‘screened out’ for further assessment. For each of the developments all available environmental information has been used to inform these judgements. Please note that references to the Scheme in the table refer to the River Humber Gas Pipeline Replacement Project and that distances quoted are approximate from the main working areas of the Scheme i.e. the drive pit or the reception pit.

Table 14-7 Cumulative Effects Assessment - Other Developments ‘Screened in’ and ‘Screened out’ of further Assessment Development Screened Relevant Justification In / Out Topics Where there Could be an Interface (If Screened In) Goxhill Able UK IN Traffic and There is the potential for interactive / Logistics Park Transport cumulative effects due to the proximity (Drawing Ref: 4 assessment (i.e. 540m to the south east) and the scale on Figure 14.1) (DCO of this development. In addition, Document timescales for construction are anticipated Reference to start in summer 2015 and potentially 6.12), Ecology overlap with the Scheme. For the reasons

The River Humber Gas Pipeline Replacement Project Page 24

Environmental Statement Volume 6 Environmental Statement Document 6.14

Development Screened Relevant Justification In / Out Topics Where there Could be an Interface (If Screened In) and Nature outlined above this development has been Conservation ‘screened in’ for further assessment. assessment (DCO Document Reference 6.7) Landscape and Visual Amenity assessment (DCO Document Reference 6.9) Lincolnshire OUT Not applicable This development is located in excess of Lakes, 25km to the south west of the Scheme. Scunthorpe This together with the unlikely shared This construction transport routes and unlikely development is significant ecological links between the not shown on Scheme and this development, it has Figure 14.1 been screened out. owing to its distance from the Scheme. Able Marine IN Traffic and This development would be constructed at Energy Park Transport the same time the Scheme is planned to (Drawing Ref: 1 assessment be constructed. Due to the proximity of on Figure 14.1) (DCO this development to the Scheme i.e. Document approximately 4,160m to the south east Reference and the scale of this development the 6.12), Ecology potential for interactive / cumulative and Nature effects cannot be ruled out. Therefore this Conservation development has been ‘screened in’ and assessment assessed further. (DCO Document Reference 6.7) Hornsea IN Traffic and Construction is anticipated to run in Offshore Wind Transport parallel with the Scheme. Therefore, Farm (Zone 4) - assessment owing to the distance (i.e. 3,830m to the Project 1 (DCO south) and the anticipated construction (Drawing Ref: Document programme there is the potential for 10 on Figure Reference 6.12) interactive and cumulative effects. 14.1) Ecology and Therefore this development has been Nature ‘screened in’ for further assessment. Conservation The River Humber Gas Pipeline Replacement Project Page 25

Environmental Statement Volume 6 Environmental Statement Document 6.14

Development Screened Relevant Justification In / Out Topics Where there Could be an Interface (If Screened In) assessment (DCO Document Reference 6.7) Hornsea IN Traffic and There is the potential for interactive and Offshore Wind Transport cumulative effects as this development is Farm (Zone 4) - assessment located approximately 3,830m to the Project 2 (DCO south and the assumed construction (Drawing Ref: Document timetable runs in parallel with the 10 on Figure Reference 6.12) Scheme. Therefore this development has 14.1) Ecology and been ‘screened in’ for further assessment. Nature Conservation assessment (DCO Document Reference 6.7) A160 - A180 IN Traffic and This development is located Port of Transport approximately 6,560m to the south of the Immingham assessment Scheme and there is overlap between the Improvement (DCO construction periods. Therefore interactive (Drawing Ref: 2 Document / cumulative effects cannot be ruled out at on Figure 14.1) Reference 6.12) this stage. For these reasons this development has been ‘screened in’ for further assessment. North OUT Not applicable This development would be operational in Killingholme 2016, therefore there would be no Power Project cumulative / interactive effects and owing (Drawing Ref: 3 to distance and the location of this on Figure 14.1) development cumulative effects are considered unlikely. Killingholme IN Traffic and The assumed construction period Energy Centre Transport overlaps with the Scheme and works (Drawing Ref: assessment would be undertaken approximately 11 on Figure (DCO 3,800m to the south of the Scheme. For 14.1) Document these reasons interactive / cumulative Reference 6.12) effects cannot be ruled out. Therefore this Ecology and development has been ‘screened in’ for Nature further assessment. Conservation assessment (DCO

The River Humber Gas Pipeline Replacement Project Page 26

Environmental Statement Volume 6 Environmental Statement Document 6.14

Development Screened Relevant Justification In / Out Topics Where there Could be an Interface (If Screened In) Document Reference 6.7) Dogger Bank OUT Not applicable Owing to the distance of the Dogger Bank Teesside A & B development i.e. in excess of 125km to This the east and that the works would be development is undertaken offshore there are not not shown on considered to be the potential for any Figure 14.1 interactive / cumulative effects. owing to its distance from the Scheme. Dogger Bank OUT Not applicable Owing to the distance of the Dogger Bank Teesside C & D development i.e. in excess of 125km to This the east and that the works would be development is undertaken offshore there are not not shown on considered to be the potential for any Figure 14.1 interactive / cumulative effects. owing to its distance from the Scheme. Paull EON Humber OUT Not applicable This development would be operational in Gateway 2016 and as this is a cable development Onshore (i.e. the infrastructure would be buried) Installation there are not considered to be any (Drawing Ref: potential for interactive / cumulative 5 on Figure effects. 14.1) Green Port Hull, OUT Not applicable It is considered there would be no Alexander cumulative effects with the Green Port Dock, Hull development as it is likely to be (Drawing Ref 6: operational by the time of the Scheme’s on Figure 14.1) construction. Also owing to the low traffic flows of the Scheme and this development being largely focussed on the riverside export of turbine components there would be no cumulative effects. Paull LDO IN Traffic and Although there are no confirmed (Drawing Ref: 7 Transport developments or construction dates within on Figure 14.1) assessment the LDO there remains a risk that (DCO development / construction may come forward / start over the construction period

The River Humber Gas Pipeline Replacement Project Page 27

Environmental Statement Volume 6 Environmental Statement Document 6.14

Development Screened Relevant Justification In / Out Topics Where there Could be an Interface (If Screened In) Document of the Scheme. In addition the LDO is Reference 6.12) located approximately 307m to the west, Ecology and therefore, interactive / cumulative effects Nature cannot be ruled out. Therefore this Conservation development has been ‘screened in’ for assessment further assessment. (DCO Document Reference 6.7) Port of Hull IN Traffic and Although there are no confirmed LDO (Drawing Transport developments or construction dates within Ref: 8 on Figure assessment the LDO there remains a risk that 14.1) (DCO development / construction may come Document forward / start over the construction period Reference 6.12) of the Scheme. In addition the LDO is Ecology and located approximately 2,330m to the north Nature west, therefore, interactive / cumulative Conservation effects cannot be ruled out. Therefore this assessment development has been ‘screened in’ for (DCO further assessment. Document Reference 6.7) Dogger Bank OUT Not applicable Works for the Dogger Bank Creyke Beck Creyke Beck development are likely to overlap with the This construction works at the Scheme. development is However, the works for Dogger Bank not shown on Creyke Beck comprise a cable scheme in Figure 14.1 excess of 15km to the north west of Paull owing to its therefore there are not considered to be distance from the potential for any interactive / the Scheme. cumulative effects. A63 Castle OUT Not applicable Work for the A63 improvements are Improvements planned to start in 2016 / 2017 and to (Drawing Ref: 9 complete in 2020. However, owing to the on Figure 14.1) distance of the works from the Scheme (i.e. 7,780m to the north west), the implementation of Traffic Management Plan (an Initial Traffic Management Plan has been prepared for the Scheme, DCO Document Reference 7.2.1) and the limited number of vehicle movements to be generated by the Scheme, it is

The River Humber Gas Pipeline Replacement Project Page 28

Environmental Statement Volume 6 Environmental Statement Document 6.14

Development Screened Relevant Justification In / Out Topics Where there Could be an Interface (If Screened In) considered that there would be no cumulative / interactive effects. East Riding IN Traffic and The Hedon Haven employment allocation Local Plan Transport (located directly adjacent to the Scheme) Hedon Haven assessment is included within the emerging Local Plan Employment (DCO which is due to be adopted in 2015. Site (Drawing Document Although there are currently no Ref 12 on Reference 6.12) applications for Hedon Haven, there Figure 14.1) Ecology and remains the possibility of planning Nature applications coming forward and Conservation construction timescales overlapping with assessment the Scheme. Together with the proximity (DCO of the allocation to the Scheme the Document allocation cannot be screened out at this Reference 6.7) stage. Sand and OUT Not applicable There are areas within the red line Gravel boundary identified as ‘sand and gravel Safeguarding safeguarding areas’. However, there are Areas - East no immediate plans to extract these Riding of resources over the construction period of Yorkshire and the Scheme. For this reason it is Hull City considered that there would be no Council Joint cumulative / interactive effects. Minerals DPD (Drawing Ref: 13 on Figure 14.1) Assessment

14.5.6 As a result of the ‘initial screening stage’, the geographical location and timescales for construction it is considered that there is potential for cumulative / interactive effects with the Scheme associated with the following developments:

. Able UK Logistics Park; . Able Marine Energy Park; . Hornsea Offshore Wind Farm (Zone 4) - Project One; . Hornsea Offshore Wind Farm (Zone 4) - Project Two; . A160 - A180 Port of Immingham Improvement; . Killingholme Energy Centre; . Paull LDO;

The River Humber Gas Pipeline Replacement Project Page 29

Environmental Statement Volume 6 Environmental Statement Document 6.14

. Port of Hull LDO; and . East Riding Local Plan Hedon Haven Employment Site.

14.5.7 Tables 14-8 to Table 14-16 present the detailed cumulative assessment for other developments. Please note that references to the Scheme throughout these tables refers to the River Humber Gas Pipeline Replacement Project.

Table 14-8 Cumulative Effects Assessment - Able UK Logistics Park – Detailed Cumulative Assessment Environmental Potential Cumulative Effect Topic Able UK Logistics Park (Drawing Ref: 4 on Figure 14.1) Ecology and Able UK Logistics Park would lead to the loss of a Nature relatively large area of arable habitat along the southern Conservation banks of the Humber. Given that the impacts predicted as a result of the Scheme are temporary during construction, and that the habitats would be reinstated following completion of the pipeline installation, the cumulative / interactive effects arising as a result of the Scheme in conjunction with other developments would only relate to bird disturbance impacts as a result of the construction phase. The potential for cumulative / interactive impacts from the Able Logistics Park would depend largely upon the construction timetables and the amount of overlap between the construction periods – for the purposes of this assessment we have assumed the construction of the Logistics Park would overlap with the construction of the Scheme. However, the Logistics Park planning application includes mitigation areas to off-set the impacts associated with the loss of habitats; as such, in the long term any temporary cumulative impacts that may arise during the construction period are considered to be not significant. Furthermore, the Habitats Regulations Assessment (HRA) (DCO Document Reference 5.4) for the Scheme has concluded that there would be no cumulative/interactive effects. Landscape and In terms of the landscape there is the potential for the Visual Amenity overlap in construction of the development and the Scheme to result in a change and loss in the rural character of the local landscape. The combination of construction noise and the visual intrusion of construction activities would result in loss of tranquillity and sense of remoteness. There is also the possibility of highly localised lighting effects on the night time landscape. It is anticipated the Scheme’s construction in addition to this development would result in a temporary minor cumulative change on the local landscape character. The River Humber Gas Pipeline Replacement Project Page 30

Environmental Statement Volume 6 Environmental Statement Document 6.14

Environmental Potential Cumulative Effect Topic Able UK Logistics Park (Drawing Ref: 4 on Figure 14.1) In terms of visual amenity it is anticipated the parallel construction of the development and the Scheme would be visible in some southerly successive views as well as sequential views from Footpath 50 along the sea defence. It is also possible that tall construction elements such as cranes / masts associated with the development could be visible skyline features in a number of southerly views in the vicinity of Chapel Field Road where elements of the scheme would form a foreground element. Therefore cumulative impacts that may arise during the construction period are considered to be minor adverse. However, this would only be during the construction phase of the Scheme, following construction there would be no potential for any interactive / cumulative effects. Therefore it is considered to be not significant. Traffic and Construction for the Able UK Logistics Park is likely to start Transport in summer 2015 therefore as a worst case scenario an overlap in construction has been assumed. However, construction traffic would not use the same route as the Scheme. Construction vehicles accessing the Able UK Logistics Park would use the A160 and A180 and Eastfield Road to the south of the Scheme. Therefore, it is considered that there would be no cumulative / interactive effects on the Scheme. Therefore it is considered to be not significant. Other The effects of the Scheme for all other topics would be Environmental highly localised and limited to the area immediately within Statement the Scheme redline or within approximately 500m of the Chapter Topics Scheme boundary, for example, construction dust effects. All of these potential localised effects would be controlled through the implementation of the Initial CEMP (DCO Document Reference 7.3) and Site Waste Management Plan. Therefore there would be no potential for significant cumulative effects. Construction of the Able UK Logistics Park is anticipated to be overlap with Scheme, therefore, there would be the potential for this to generate positive cumulative effects on the local economy during the construction period, through an increase in spending and job creation. This is considered to be of a minor significance. However, following construction there would be no potential for cumulative / interactive effects.

The River Humber Gas Pipeline Replacement Project Page 31

Environmental Statement Volume 6 Environmental Statement Document 6.14

Table 14-9 Cumulative Effects Assessment - Able Marine Energy Park – Detailed Cumulative Assessment Environmental Potential Cumulative Effect Topic Able Marine Energy Park (Drawing Ref: 1 on Figure 14.1) Ecology and As above the Able Marine Energy Park would lead to the Nature loss of a relatively large area of arable habitat along the Conservation southern banks of the Humber. Again as the impacts predicted as a result of the Scheme are temporary during construction, and habitats would be reinstated following completion, the cumulative / interactive effects arising as a result of the Scheme in conjunction with other developments would only relate to bird disturbance impacts as a result of the construction phase. The potential for cumulative / interactive impacts from the Able Energy Park again depend largely upon the construction timetables. However, research has suggested construction would be 2016 – 2017 - therefore running in parallel with the Scheme. Although it should be noted the DCO for the Energy Park provides mitigation areas to off- set the impacts associated with the loss of habitats; as such, in the long term any temporary cumulative impacts that may arise during the construction period are considered to be not significant. Traffic and The inbound and outbound routes for deliveries of plant Transport and materials to the Cherry Cobb Sands site (on the Paull side) would be via the A1033 through . The Scheme would use a private track to access the Paull construction site and, therefore, there would be limited interface with this development. Furthermore, with the implementation of a Traffic Management Plan (an Initial Traffic Management Plan has been prepared for the Scheme, DCO Document Reference 7.2.1) for both the Scheme and this development, the limited number of vehicle movements to be generated by the Scheme and the fact that the A1033 is designed to take significant traffic flows, it is considered that cumulative / interactive effects would be not significant. For the Goxhill side, construction traffic would use the A160, the A180, Rosper Road and Humber Road which are located in excess of 6km south of the Scheme. This together with a Traffic Management Plan for the Scheme and this development (an Initial Traffic Management Plan has been prepared for the Scheme, DCO Document Reference 7.2.1) and the limited number of vehicle movements to be generated by the Scheme, it is considered that there would be no cumulative / interactive effects. Therefore it is considered to be not significant.

The River Humber Gas Pipeline Replacement Project Page 32

Environmental Statement Volume 6 Environmental Statement Document 6.14

Environmental Potential Cumulative Effect Topic Able Marine Energy Park (Drawing Ref: 1 on Figure 14.1) Other The effects of the Scheme for all other topics would be Environmental highly localised and limited to the area immediately within Statement the Scheme redline or within approximately 500m of the Chapter Topics Scheme boundary, for example, construction dust effects. All of these potential localised effects would be controlled through the implementation of the Initial CEMP (DCO Document Reference 7.3) and Site Waste Management Plan, therefore there would be no potential for significant cumulative effects. The Able Marine Energy Park is anticipated to be constructed at the same time as the Scheme, therefore, there would be the potential for this to generate positive cumulative effects on the local economy during the construction period, through an increase in spending and job creation. This is considered to be of a minor significance. However, following construction there would be no potential for cumulative / interactive effects. Table 14-10 Cumulative Effects Assessment - Hornsea OffShore Windfarm (Zone 4) – Project 1 – Detailed Cumulative Assessment Environmental Potential Cumulative Effect Topic Hornsea Offshore Wind Farm (Zone 4) - Project 1 (Drawing Ref: 10 on Figure 14.1) Ecology and This development would be located within a zone that is Nature already subject to existing levels of background Conservation disturbance from the adjacent industrial areas. No significant impacts associated with Humber Estuary SPA (alone or in combination) have been identified within the Hornsea Offshore windfarm HRA. In addition, the land- take associated with the Scheme and this development is relatively minor; as such the potential for cumulative / interactive effects in conjunction with the Scheme is considered to be not significant. Traffic and Construction for this development would overlap with the Transport construction of the Scheme. However, HGVs and construction traffic would use the A180, A160, Rosper Road, Chase Hill Road and Eastfield Road which are located in excess of 6km south of the Scheme. Traffic Management Plans would be implemented for the Scheme and this development (an Initial Traffic Management Plan has been prepared for the Scheme, DCO Document Reference 7.2.1) and there would be a limited number of vehicle movements generated by the Scheme. Therefore it is considered that there would be no cumulative /

The River Humber Gas Pipeline Replacement Project Page 33

Environmental Statement Volume 6 Environmental Statement Document 6.14

Environmental Potential Cumulative Effect Topic interactive effects. Therefore it is considered to be not significant. Other The effects of the Scheme for all other topics would be Environmental highly localised and limited to the area immediately within Statement the Scheme redline or within approximately 500m of the Chapter Topics Scheme boundary, for example, construction dust effects. All of these potential localised effects would be controlled through the implementation of the Initial CEMP (DCO Document Reference 7.3) and Site Waste Management Plan, therefore there would be no potential for significant cumulative effects. The Hornsea Off Shore Windfarm (Zone 4) – Project 1 is anticipated to be constructed at the same time as the Scheme, therefore, there would be the potential for this to generate positive cumulative effects on the local economy during the construction period, through an increase in spending and job creation. This is considered to be of a minor significance. However, following construction there would be no potential for cumulative / interactive effects. Table 14-11 Cumulative Effects Assessment - Hornsea OffShore Windfarm (Zone 4) – Project 2 – Detailed Cumulative Assessment Environmental Potential Cumulative Effect Topic Hornsea Offshore Wind Farm (Zone 4) – Project 2 (Drawing Ref: 10 on Figure 14.1) Ecology and The development would be located within a zone that is Nature already subject to existing levels of background Conservation disturbance from the adjacent industrial areas. As per Project 1, it considered unlikely the development would have significant impacts associated with Humber Estuary SPA (alone or in combination). In addition, the land-take associated with the Scheme and this development is relatively minor; as such the potential for cumulative / interactive effects in conjunction with the Scheme is considered to be not significant. Traffic and This development has been submitted to PINS and it is Transport assumed that construction would run parallel to Project 1. HGVs and construction traffic would use the A180, A160, Rosper Road, Chase Hill Road and Eastfield Road located in excess of 6km south of the Scheme. This together with assumed Traffic Management Plans being implemented for both the Scheme (an Initial Traffic Management Plan has been prepared for the Scheme, DCO Document Reference 7.2.1) and the limited number of vehicle movements generated by the Scheme. It is considered The River Humber Gas Pipeline Replacement Project Page 34

Environmental Statement Volume 6 Environmental Statement Document 6.14

Environmental Potential Cumulative Effect Topic Hornsea Offshore Wind Farm (Zone 4) – Project 2 (Drawing Ref: 10 on Figure 14.1) that there would be no cumulative / interactive effects. Therefore it is considered to be not significant. Other The effects of the Scheme for all other topics would be Environmental highly localised and limited to the area immediately within Statement the Scheme redline or within approximately 500m of the Chapter Topics Scheme boundary, for example, construction dust effects. All of these potential localised effects would be controlled through the implementation of the Initial CEMP (DCO Document Reference 7.3) and Site Waste Management Plan, therefore there would be no potential for significant cumulative effects. The Hornsea Offshore Wind Farm (Zone 4) – Project 2 is assumed to be constructed at the same time as the Scheme, therefore, there would be the potential for this to generate positive cumulative effects on the local economy during the construction period, through an increase in spending and job creation. This is considered to be of a minor significance. However, following construction there would be no potential for cumulative / interactive effects. Table 14-12 Cumulative Effects Assessment - A160 - A180 Port of Immingham Improvement – Detailed Cumulative Assessment Environmental Potential Cumulative Effect Topic A160 - A180 Port of Immingham Improvement (Drawing Ref: 2 on Figure 14.1) Traffic and Although there is a year overlap between the construction Transport periods in 2016. Owing to the distance of this development from the Scheme on the Goxhill side (i.e. approximately 6,560m to the south), the low construction traffic the Scheme is likely to generate, and that construction traffic would use A180, A160, Rosper Road and Humber Road over 6km south, no interactive / cumulative effects are anticipated. Therefore it is considered to be not significant. Other The effects of the Scheme for all other topics would be Environmental highly localised and limited to the area immediately within Statement the Scheme redline or within approximately 500m of the Chapter Topics Scheme boundary, for example, construction dust effects. All of these potential localised effects would be controlled through the implementation of the Initial CEMP (DCO Document Reference 7.3) and Site Waste Management Plan, therefore there would be no potential for significant

The River Humber Gas Pipeline Replacement Project Page 35

Environmental Statement Volume 6 Environmental Statement Document 6.14

Environmental Potential Cumulative Effect Topic A160 - A180 Port of Immingham Improvement (Drawing Ref: 2 on Figure 14.1) cumulative effects. The A160 - A180 Port of Immingham Improvement is anticipated to be constructed at the same time as the Scheme, therefore, there would be the potential for this to generate positive cumulative effects on the local economy during the construction period, through an increase in spending and job creation. This is considered to be of a minor significance. However, following construction there would be no potential for cumulative / interactive effects. Table 14-13 Cumulative Effects Assessment - Killingholme Energy Centre – Detailed Cumulative Assessment Environmental Potential Cumulative Effect Topic Killingholme Energy Centre (Drawing Ref: 11 on Figure 14.1) Ecology and The development would be located within a zone that is Nature already subject to existing levels of background Conservation disturbance from the adjacent industrial areas. The area of land-take associated with the scheme is relatively minor; as such the potential for cumulative / interactive effects in conjunction with the Scheme is considered to be not significant. Traffic and This development is at the ‘Pre-application’ stage therefore Transport little is known about the construction traffic routes / likely movements it would generate. However, as a worst case it has been assumed that the construction periods would overlap. It is likely the construction traffic would use the A160 and A180 for the construction works as per other developments in the area. Traffic Management Plans would be implemented for both the Scheme (an Initial Traffic Management Plan has been prepared for the Scheme, DCO Document Reference 7.2.1) and this development and there would be a limited number of vehicle movements generated by the Scheme. Therefore it is considered that there would be no cumulative / interactive effects. Therefore it is considered to be not significant. Other The effects of the Scheme for all other topics would be Environmental highly localised and limited to the area immediately within Statement the Scheme redline or within approximately 500m of the Chapter Topics Scheme boundary, for example, construction dust effects. All of these potential localised effects would be controlled through the implementation of the Initial CEMP (DCO

The River Humber Gas Pipeline Replacement Project Page 36

Environmental Statement Volume 6 Environmental Statement Document 6.14

Environmental Potential Cumulative Effect Topic Killingholme Energy Centre (Drawing Ref: 11 on Figure 14.1) Document Reference 7.3) and Site Waste Management Plan, therefore there would be no potential for significant cumulative effects. The Killingholme Energy Centre is anticipated to be constructed at the same time as the Scheme, therefore, there would be the potential for this to generate positive cumulative effects on the local economy during the construction period, through an increase in spending and job creation. This is considered to be of a minor significance. However, following construction there would be no potential for cumulative / interactive effects. Table 14-14 Cumulative Effects Assessment - Paull LDO – Detailed Cumulative Assessment Environmental Potential Cumulative Effect Topic Paull LDO (Drawing Ref: 7 on Figure 14.1) Ecology and The Paull LDO Enterprise Zone lies within close proximity Nature of existing areas of development (including ) on Conservation the Paull side therefore the site is already subject to existing levels of background disturbance. Furthermore, the Paull LDO site includes an area of compensation land to off-set potential impacts. In addition, the Scheme would not result in any significant impacts on the other Key Ecological Receptors identified including, water voles and barn owls (refer to Chapter 7: Ecology and Nature Conservation (DCO Document Reference 6.7). Therefore, it is not considered likely that the Paull LDO would lead to significant cumulative effects associated with the Scheme. Furthermore, the same conclusion can be drawn when considering other potential impact pathways such as disturbance and displacement during construction, which would be temporary in nature and would not lead to significant cumulative effects on other ecological receptors. As such, the potential for this development to lead to cumulative / interactive effects in conjunction with the current proposals is considered to be not significant. Traffic and The Paull LDO Enterprise Zone lies to the west of Paull Transport Road. It is assumed that construction vehicles may enter the site from both Paull Road and Salt End Lane, via the A1033. Although there are no confirmed developments or construction dates within the LDO there remains a risk that development / construction may come forward / start over the construction period of the Scheme. As construction vehicles for the Scheme would use Paull Road and the

The River Humber Gas Pipeline Replacement Project Page 37

Environmental Statement Volume 6 Environmental Statement Document 6.14

Environmental Potential Cumulative Effect Topic Paull LDO (Drawing Ref: 7 on Figure 14.1) A1033, there is the potential for cumulative / interactive effects. However, with the implementation of a Traffic Management Plan for the Scheme (an Initial Traffic Management Plan has been prepared for the Scheme, DCO Document Reference 7.2.1) and this development and the limited number of vehicle movements to be generated by the Scheme, it is considered that cumulative / interactive effects would be of a minor significance. Other The effects of the Scheme for all other topics would be Environmental highly localised and limited to the area immediately within Statement the Scheme redline or within approximately 500m of the Chapter Topics Scheme boundary, for example, construction dust effects. All of these potential localised effects would be controlled through the implementation of the Initial CEMP (DCO Document Reference 7.3) and Site Waste Management Plan, therefore there would be no potential for significant cumulative effects. Construction at the Paull LDO is assumed at the same time as the Scheme, therefore, there would be the potential for this to generate positive cumulative effects on the local economy during the construction period, through an increase in spending and job creation. This is considered to be of a minor significance. However, following construction there would be no potential for cumulative / interactive effects. Table 14-15 Cumulative Effects Assessment - Port of Hull LDO – Detailed Cumulative Assessment Environmental Potential Cumulative Effect Topic Port of Hull LDO (Drawing Ref: 8 on Figure 14.1) Ecology and The Hull LDO Enterprise Zone lies within close proximity to Nature existing areas of development (including Salt End) on the Conservation Paull side therefore the site is already subject to existing levels of background disturbance. In addition, the Scheme would not result in any significant impacts on the other Key Ecological Receptors identified including, water voles and barn owls (refer to Chapter 7: Ecology and Nature Conservation (DCO Document Reference 6.7). Therefore, it is not considered likely that the Hull LDO would lead to significant cumulative effects associated with the Scheme. Furthermore, the same conclusion can be drawn when considering other potential impact pathways such as disturbance and displacement during construction, which

The River Humber Gas Pipeline Replacement Project Page 38

Environmental Statement Volume 6 Environmental Statement Document 6.14

Environmental Potential Cumulative Effect Topic Port of Hull LDO (Drawing Ref: 8 on Figure 14.1) would be temporary in nature and would not lead to significant cumulative effects on other ecological receptors. Therefore, cumulative / interactive effects in conjunction with the current proposals are considered to be not significant. Traffic and The Hull LDO Enterprise Zone lies south of the A63 Hedon Transport Road. It is expected that construction vehicles would access the site from the A63. There are no confirmed developments or construction dates within the LDO. Therefore, there is potential for an overlap between this development and the construction period of the Scheme. However, the A63 is a dual carriageway which is designed for high volumes of traffic, particularly HGVs. Therefore, the increase from construction traffic would not have a significant effect on traffic flow. It is considered that there would be no cumulative / interactive effects on the Scheme. Therefore it is considered to be not significant. Other The effects of the Scheme for all other topics would be Environmental highly localised and limited to the area immediately within Statement the Scheme redline or within approximately 500m of the Chapter Topics Scheme boundary, for example, construction dust effects. All of these potential localised effects would be controlled through the implementation of the Initial CEMP (DCO Document Reference 7.3) and Site Waste Management Plan, therefore there would be no potential for significant cumulative effects. Construction at the Port of Hull LDO is assumed at the same time as the Scheme, therefore, there would be the potential for this to generate positive cumulative effects on the local economy during the construction period, through an increase in spending and job creation. This is considered to be of a minor significance. However, following construction there would be no potential for cumulative / interactive effects. Table 14-16 Cumulative Effects Assessment - East Riding Local Plan (Not yet adopted) Hedon Haven Employment Site – Detailed Cumulative Assessment Environmental Potential Cumulative Effect Topic East Riding Local Plan (Not yet adopted) Hedon Haven Employment Site (Drawing Ref 12 on Figure 14.1) Ecology and The Hedon Haven Key Employment Site lies Nature approximately 307m to the west of the Scheme on the Conservation Paull side and includes an area of approximately 200ha of

The River Humber Gas Pipeline Replacement Project Page 39

Environmental Statement Volume 6 Environmental Statement Document 6.14

Environmental Potential Cumulative Effect Topic East Riding Local Plan (Not yet adopted) Hedon Haven Employment Site (Drawing Ref 12 on Figure 14.1) land. Given that this site is currently just a site allocation (within the currently unadopted Local Plan for East Riding of Yorkshire), it is considered unlikely that any large-scale development would take place at the site within the same timeframe as the construction phase of the Scheme. However, smaller scale development could potentially come forward. In addition, the HRA for the allocation includes the need for areas of mitigation and compensation land to off-set the potential impacts of any development which may take place at the site in the future. In addition, the Scheme would not result in any significant impacts on the other Key Ecological Receptors identified including, water voles and barn owls (refer to Chapter 7: Ecology and Nature Conservation (DCO Document Reference 6.7). Therefore, it is not considered likely that the Hedon Haven Employment Site would lead to significant cumulative effects associated with the Scheme. Furthermore, the same conclusion can be drawn when considering other potential impact pathways such as disturbance and displacement during construction, which would be temporary in nature and would not lead to significant cumulative effects on other ecological receptors. Therefore, the potential for the Hedon Haven Key Employment Site to lead to cumulative / interactive effects, during the construction phase of the Scheme, in conjunction with the current proposals is considered to be low. Therefore it is considered to be not significant. Traffic and The Hedon Haven Key Employment Site is located Transport between the A1033 Main Road, Paull Road and Farbridge Lane. It is assumed that access to the site could be from any of these roads, which are also identified as part of the construction routes for the Scheme. Although there are currently no applications for Hedon Haven, there remains the possibility of planning applications coming forward and construction timescales overlapping with the Scheme. Therefore, there is the potential for cumulative / interactive effects. However, with the implementation of a Traffic Management Plan for the Scheme (an Initial Traffic Management Plan has been prepared for the Scheme, DCO Document Reference 7.2.1) and this development and the limited number of vehicle movements to be generated by the Scheme. It is considered that cumulative / interactive effects would be minor adverse. However,

The River Humber Gas Pipeline Replacement Project Page 40

Environmental Statement Volume 6 Environmental Statement Document 6.14

Environmental Potential Cumulative Effect Topic East Riding Local Plan (Not yet adopted) Hedon Haven Employment Site (Drawing Ref 12 on Figure 14.1) this would only be during the construction phase of the Scheme, following construction there would be no potential for any interactive / cumulative effects. Therefore it is considered to be not significant. Other The effects of the Scheme for all other topics would be Environmental highly localised and limited to the area immediately within Statement the Scheme redline or within approximately 500m of the Chapter Topics Scheme boundary, for example, construction dust effects. All of these potential localised effects would be controlled through the implementation of the Initial CEMP (DCO Document Reference 7.3) and Site Waste Management Plan, therefore there would be no potential for significant cumulative effects. Construction at the Hedon Haven Employment Site is assumed at the same time as the Scheme, therefore, there would be the potential for this to generate positive cumulative effects on the local economy during the construction period, through an increase in spending and job creation. This is considered to be of a minor significance. However, following construction there would be no potential for cumulative / interactive effects.

14.6 Difficulties Encountered in Compiling the ES

14.6.1 Difficulties were encountered in assessing the residual cumulative effects of construction traffic for those developments that were at the ‘Pre-application stage’, that were allocations or LDOs as limited information was available to undertake an informed assessment. Therefore, worst case assumptions had to be made. 14.7 Summary

14.7.1 Cumulative effects have been considered in two categories:

. Intra Scheme – effects which occur due to the different aspects of a scheme affecting a single receptor e.g. a residential property; and . Inter Scheme – effects which occur as a result of the scheme combining with another development resulting in an increased effect e.g. noise effects from two schemes combining and increasing overall noise levels. Intra-Scheme

14.7.2 Residential receptors and footpaths users have the potential to experience multiple effects as a result of the construction of the Scheme, e.g. dust, noise and vibration and visual intrusion. All such effects would be temporary and for the duration of the construction phase only and this may only be experienced by The River Humber Gas Pipeline Replacement Project Page 41

Environmental Statement Volume 6 Environmental Statement Document 6.14

certain receptors and a very limited number of them. Furthermore, it is considered unlikely that the combined effect on these receptors would lead to an increase in the overall temporary adverse effect with mitigation.

Inter-Scheme

14.7.3 A number of other developments were identified as having the potential to interact with the Scheme. These were identified through internet searches and consultation.

14.7.4 For most of the identified developments the main potential for cumulative effects relates to construction traffic and also loss of habitat that may be used by birds of the Humber Estuary. However, it is considered that there would be no significant traffic impacts as there is limited potential for the construction routes of the Scheme to overlap with the other developments and all would implement Traffic Management Plans.

14.7.5 While there would be permanent habitat loss for many of the above developments they have all been subject to detailed assessments and where necessary mitigation measures including replacement habitat have been provided. In addition, the EIA findings indicate that there would be no cumulative effects in combination with other developments. This is also re- confirmed in the associated HRA (DCO Document Reference 5.4). 14.8 References

Department of Energy and Climate Change (2011) Overarching National Policy Statement for Energy (NPS EN-1)

East Riding of Yorkshire (adoption expected 2015) Local Plan

East Riding of Yorkshire and Hull City Council (adoption expected 2015) Joint Minerals Development Plan Document

European Commission / Hyder Consulting (1999) ‘Guidelines for the Assessment of Indirect and Cumulative Impacts as well as Impact Interactions. Prepared for the European Commission, EC DG X1 Environment, Nuclear Safety and Civil Protection’

Highways Agency (2008) Design Manual for Roads and Bridges, Volume 11, Section 2, Part 5 (HA 205/08)

Hyder Consulting (UK) Limited (2014) EIA Scoping Report

Hyder Consulting (UK) Limited (2014) PEIR Report

Infrastructure Planning (Environmental Impact Assessment) Regulations 2009 Available at: http://infrastructure.independent.gov.uk/wp- content/uploads/2009/08/uksi_20092263_en.pdf (online)

North Lincolnshire Council (adopted 2011) Core Strategy

The River Humber Gas Pipeline Replacement Project Page 42

Environmental Statement Volume 6 Environmental Statement Document 6.14

Planning Inspectorate (2011) Rochdale Envelope, Advice Note 9 14.9 Figures

The River Humber Gas Pipeline Replacement Project Page 43

RED LINE BOUNDARY 1. ABLE MARINE ENERGY PARK (NATIONALLY SIGNIFICANT INFRASTRUCTURE PROJECT) - DEVELOPMENT CONSENT ORDER 5 km GRANTED 2. A160 -180 PORT OF IMMINGHAM IMPROVEMENT (NATIONALLY SIGNIFICANT INFRASTRUCTURE 10 km 6 8 PROJECT) - DEVELOPMENT CONSENT ORDER GRANTED 9 COMPENSATION AREA FOR PAULL KINGSTON 12 LOCAL DEVELOPMENT ORDER 3. NORTH KILLINGHOLME POWER UPON HULL PROJECT (NATIONALLY SIGNIFICANT INFRASTRUCTURE PROJECT) - DEVELOPMENT CONSENT ORDER 7 GRANTED

4. ABLE UK LOGISTICS PARK - FULL PAULL 13 PLANNING PERMISSION GRANTED

5. EON - HUMBER GATEWAY ONSHORE INSTALLATION - CURRENTLY UNDER CONSTRUCTION

6. GREEN PORT HULL - CURRENTLY UNDER CONSTRUCTION

7. PAULL LOCAL DEVELOPMENT ORDER 5 - OUTLINE PLANNING PERMISSION GRANTED

8. PORT OF HULL LOCAL DEVELOPMENT ORDER - OUTLINE PLANNING CHERRY COBB SANDS PERMISSION GRANTED COMPENSATION SITE 9. A63 CASTLE STREET IMPROVEMENTS GOXHILL - CURRENTLY AT PRE-APPLICATION 5 km STAGE 4 1 10. HORNSEA OFFSHORE WIND FARM 3 (NATIONALLY SIGNIFICANT INFRASTRUCTURE PROJECT) ZONE 4 PROJECT 1 - DEVELOPMENT 10 CONSENT ORDER GRANTED HORNSEA OFFSHORE WIND FARM (NATIONALLY SIGNIFICANT 1 INFRASTRUCTURE PROJECT) - ZONE 4 - PROJECT 2 - APPLICATION SUBMITTED TO THE PLANNING INSPECTORATE

10 km 11. KILLINGHOLME ENERGY CENTRE 11 (NATIONALLY SIGNIFICANT 10 km INFRASTRUCTURE PROJECT) - CURRENTLY AT PRE APPLICATION STAGE 2 12. PROPOSED ALLOCATION FOR A KEY EMPLOYMENT SITE AT HEDON HAVEN - EAST RIDING OF YORKSHIRE ALLOCATION DEVELOPMENT PLAN DOCUMENT

13. SAND AND GRAVEL SAFEGUARDING AREAS - HULL AND EAST RIDING JOINT MINERALS PLAN

OTHER PROJECT BOUNDARIES ARE APPROXIMATE BASED ON CURRENT KNOWLEDGE