E1782 v.5

ENVIRONMENT IMPACT ASSESSMENT Public Disclosure Authorized Executive Summary

JIANGXI SHIHUTANG NAVIGATION AND HYDROPOWER COMPLEX PROJECT ON THE

Public Disclosure Authorized Public Disclosure Authorized

Prepared by CCCC SECOND HARBOR CONSULTANTS CO., LTD. PROVINCIAL WATER RESOURCE PLANNING AND DESIGN INSTITUTE

Public Disclosure Authorized

February 2008 Jiangxi Administration of Navigation Affairs (JANA) JIANGXI SHIHUTANG NAVIGATION AND HYDROPOWER COMPLEX PROJECT ON THE GAN RIVER ENVIRONMENT IMPACT ASSESSMENT Executive Summary

Background This document summarizes the environment impact assessment of the WB financed project – Jiangxi Shihutang Navigation and Hydropower Complex Project at the Gan River, highlighting the main issues and conclusions of the environment impact assessment and environment management plan of the project. The Executive Summary is based on the following reports: (i) Environmental Impact Assessment Report (EA); (ii) Environmental Management Plan for Flood Control Areas; and (iii) Environmental Management Plan (EMP) for Navigation/Hydro Complex. These reports were submitted to the Jiangxi Administration of Navigational Affairs (JANA) of the Jiangxi Provincial Communications Department (JPCD) for detailed review and are available to interested parties in their offices and provincial environmental offices. The EA reports and EMPs were submitted to the World Bank for review and they conform fully to Bank policy guidelines regarding environmental and social issues. All above reports have been made available in the Public Information Center (INFOSHOP) of the World Bank. The JANA cleared this summary for submission to the Board of Executive Directors of the World Bank.

Project Objectives When completed, the proposed project would have (i) canalized 38km long waterway, upgrading a stretch of waterway of the Gan River to further extend Grade III navigability to upstream stretches of the river, and to finally reach the planned waterway objective; and (ii) constructed the Shihutang hydropower station that will participate in peak regulation of the Jiangxi power grid together with the upstream Wan’an hydropower station, and thus play an important role in lessening power shortage and improving the energy structure of the Jiangxi Province.

The Jiangxi Gan River Drainage Area Planning Report approved by the Chinese Government recommends two trunk stream cascade development plans I and V through analysis of flood control and protection, hydropower generation, navigation, integrated water resources management, and port construction. Plan V is a ten-step development plan (Xiashan Low Elevation Plan), starting from upstream to downstream with Bai’e, Baikoutang, Xiashan, Maodian, Wan’an (built in 1993, 82 km upstream of Shihutang), Taihe, Shihutang, Xiajiang, Yongtai and Longtoushan. The planned and preliminarily selected projects that will be implemented in the near future are the three project sites of Taihe, Shihutang and Xiajiang.

The Gan River is the main tributary at the middle reaches of the River, and it is one of the key passages for shipping of the Jiangxi Province and has been listed in the state high-rank waterway network. As per the “Approval of Technical Grade of Inland River Waterway” (Document No. [1998]659) issued by the Ministry of Communications, the Ministry of Water Conservancy and the

1 State Trade and Economic Relation Commission in 1998, the 525km long section of the Gan River ( to Wucheng) is denominated as a Grade III inland waterway.

160 Wan’an 150 128 (Built in

117 Shihutang 106 100 100

69 58 50 50

34 26

Environmental Assessment Process and Legal Framework Perhaps the most environmentally and socially sensitive component of the proposed project will be the construction and operation of a dual objective low head dam on the Gan river for both navigation and hydropower generation. A full Environmental Assessment (EA) was carried out following terms of reference agreed with the World Bank. The terms of reference were discussed in public meetings. The project triggered the following World Bank policies: Environmental Assessment (OP/BP/GP4.01; Natural Habitats (OP/BP4.04); Safety of Dams (OP/BP4.37); Involuntary Resettlement (OP4.12); and Physical Cultural Resources (OP4.11).

The project is in full compliance with environmental policies and regulations in such as Environmental Protection Law of PRC1989.12 and Environment Impact Assessment Law of PRC 2002.10; Water Pollution Prevention Law of PRC1996.5Wild Animals Protection Law of PRC (1988.11Cultural Relic Protection Law of PRC2002.11and Fishery Law of PRC2000.10 etc. The EA Report was approved by China State Environmental Protection Administration (SEPA) in January 2008.

Project Description The Project is located between the Ji’an City and Taihe County in the middle reaches of the Gan River. The dam will be situated on the Gan River near the Shihutang Village, 26km downstream from the Taihe County Road Bridge. This will be a multipurpose project, with navigation as the main purpose, but providing additional benefits such as power generation and flood control. Main characteristics of the project are presented in the following table.

Normal water level 56.5/57.0 m Normal reservoir storage 281mil. m3 Regulation storage 8.47 mil. m3 Regulation feature Daily regulation Reservoir area 39.36 km2 Backwater length 38 km Hydro capacity 120 MW Nominal water head 5.35 m (max. 9.80m, min. 3.60m)

2 Max. dam height 26.5 m Land acquisition 6.15 km2 Transmission line 18 km Environmental Setting Hydrology. Gan River basin falls within the moist subtropical belt, with abundant rainfall (average annual rainfall of 1300-1800mm), but rainfall is severely uneven in seasons. Rainfall from April to June makes up between 41 and 51% of the precipitation for the whole year. There are frequent rainstorms in the basin. Storms fall mainly between April and September, while from May to June rain falls mainly in frontal rain patterns, which makes cloudbursts more frequent. From July to September rainstorms are caused mainly by typhoons.

Gan River is a flood storm river; therefore the flood season is coincident with the storm season. April is the start of the flood season there is flood in the basin, but without much peak discharges in that month. May to June, but especially in June, is the main flood season, when large-scale floods are caused by heavy storms. Typhoons are common from July to Sept, causing medium-scale floods.

Water Quality. Although there are some raw sewage discharges into the Gan River, the river has good waste assimilation capacity. Therefore, existing records indicate that the water quality of the Gan River section where the project is located meets Chinese Grade II~Grade III water quality standards. Overall water quality is good as a whole.

Ecology. The Shihutang project area is comprised mainly of flat plains and low hilly areas, with secondary and artificial vegetation. There are no national grade protected wild plants and famous trees within the area of influence of the project. There are 11 species of provincial grade protected plants within the broader area of influence of the project. Field investigations identified altogether 215 old trees (under special protection in China) in the project area that conform an Old Trees Community Nature Reserve in Jintan. There are 26 species of birds, classified into 8 families and 17 genera. Passerine are the largest in quantity, 34.62% of all. There is no bird under state protection. There are 7 orders, 7 families and 7 genera of mammals in the Shihutang Project district, none under state protection. Rodents are the largest in numbers and species in this area. No protected animals or fish species have been identified in the area of influence of the project. There are 20 species under province-level protection in Jiangxi Province, widely scattered in quantity throughout the Shihutang Project district. Two fish spawning sites - Taihe Spawning Site and Yanxidu Spawning Site – were reported several decades ago the project area. The main spawning fishes of these two sites are mandarin fish, grass carp, snail carp, silver xenocypris, Elopichthys bambusa, bream fish, Xenocypris argentea, and H.maculatus Bleeker. Although migratory species were identified in the 1980’s they have practically disappeared from this stretch of the river.

Cultural Relics and Historic Sites. No cultural property sites of national importance will be affected by the project. Field research findings carried out during the EA identified one ancient ferry site and an old town site in the inundation area of the reservoir. However, the Huangkeng Ancient Ferry does not belong to any cultural relics protected unit of different grades. These sites show no remaining physical evidence but remain in local memory and records. In addition, two ancient city sites, a Gouzi pagoda and an Ouyang Ancestral Hall were found in the vicinity of the inundation area but at a considerable

3 distance from the inundation area. Further refinement of dike alignment during preliminary designs has avoided flooding to impact any cultural resource sites.

Socio- Economic Situation. Ji’an has a jurisdiction over 2 cities and 11 counties, 218km in length from east to west and about 208km in width from north to south. In 2004 its GDP totaled 24.265 billion Yuan, rising by 14.5%, more than 0.5 % more than last year, the highest rate in the last 9 years. The area of the project is mostly occupied by farmlands. Road infrastructure is quite extensive in the area of the project. No new road access is needed for the construction of the dam.

Sensitive Sites. All sensitive sites in and around the project site (dam and reservoir, canals) were identified, analyzed, and registered in maps such as the one presented below. Sensitive Sites Villages/School Fish spawning site Cultural site

Water intake Sewage discharge Old tree reserve

Analysis of Alternatives The project has been subject to intense analysis of alternative options ranging from the project-no project scenarios, dam sites, to specific alignment of dikes, screens, and drainage canals. All

4 alternatives were compared as to their technical, economic, environmental and social impacts. For instance, project-no project comparison included a comparison with a thermal power plant of the same installed capacity. Although the Shihutang Project will create some negative impacts upon the ecological environment, thermal plant will bring much more pressure to local communities, require more land acquisition, plus the generation of green house gases.

Two dam site options were considered. The selected site represents the option with less land acquisition and resettlement needs, better geology, and less earth/stone works. Several reservoir operating levels were also analyzed The selected layout of the dam (ship lock on the left and powerhouse to the right) provides a smoother connection to the river channel, less spoil disposal, and easier configuration for any future lock.

Special care was taken for the selection of reservoir embankment and screens near the old tree reserve of Jintan. This reserve of old trees, protected by law, is used intensively for recreation and is of high value for the community. The alignment of the embankment and screen will guarantee the preservation of this important site.

Environmental Impacts Construction impacts. The construction of the dam and its ancillary infrastructure will entail potentially significant negative impacts on communities and surrounding aquatic habitats. The proper management of excavation materials, river and drainage crossings, and the reduction of nuisances such as dust, noise, increased traffic, pedestrian safety concerns, and the presence of a large work force in or near small rural communities, will require careful engineering planning, closed supervision, and a continuous and intense community information program. Environmental specifications will be included in all bidding documents and contracts.

5 A phased approach for the construction of the dam will minimize disruption of river flows during construction. Left and then right-hand cofferdams will maintain natural river flows during construction and avoid the need for any river deviation. This is illustrated in the following figure. A Two-phase Coffer Dam Construction Schedule

During the construction period, construction and material carrier vehicles will use existing roads and village roads. Partial congestion may occur with some negative impacts upon local traffic. The presence of communities and some schools along some of these roads pose a significant risk for pedestrian and student safety. Traffic management during construction will require strict controls.

Impacts on River Hydrology. The Shihutang Dam will increase navigation capacity upstream and maintain current navigation capacity downstream. Due to its weak flow regulation capacity (only daily regulation), the average annual, monthly and daily flow after dam construction will be basicly the same as before the construction of the dam. The day-cycle flow will be slightly modified (peak flow will be slightly reduced and low flow increased). Water releases will not impact water use and environmental demand downstream. In coordination and agreement with the Wan’an Dam upstream of Shihutang, a minimum water release sufficient for normal navigation, water use and environmental demand in Shihutang reservoir has been secured.

The flood management and operation mode of the Project is decided by the upstream incoming flow. When the incoming flow is smaller than critical flow for opening gates, it will switch into beneficial flood management and operation mode of navigation and hydropower generation. The design critical flow at the Shihutang dam site is 4700m3/s, and the critical flow at the Guanyuan River discharge section is 70m3/s. In order to meet the shipping requirement of the dam downstream, the release flow of the reservoir shall not be smaller than 187m3/s, accounting for 16.3% of annual average flow. That release flow can also meet the navigational requirement of the downstream channel, and productive, domestic as well as ecological water consumption requirement of the dam downstream.

Sediment in the river will probably create a small delta at the tail of the reservoir. Sediment transport from this point to the dam site is expected to be low.

The water body in the reservoir will present complete mixed patterns, with little or no stratification, thus there will be no significant difference in water temperature in the discharged water and natural water. Therefore, no impacts upon downstream ecosystems are to be expected.

6 As mentioned before, discharges of raw sewage and wastewater treatment plant effluents do not exert water quality problems on the river. With the formation of the reservoir, this situation still will be maintained and no major quality degradation issues are expected. Annual mean phosphorus element in Shihutang reservoir is predicted to be less than 0.016mg/l, which is at the lower limit of the mesotrophic level. This means that the likelihood of reservoir eutrophication is very low.

Groundwater Impacts. After the reservoir is impoundedwater levels of different river sections will be raised to different extents. Water from the reservoir will feed underground water tables at the front edge of the first terrace and second terrace until new dynamic balance more beneficial to underground water resources is established. Lowering of the underground water level will be under effective control. The underground water reserve will remain stable and steady providing sufficient water sources for domestic and industrial water consumption in the Taihe County.

Ecological Environment. The project will not threaten the survival or reproduction on the 11 species of plants under province-level protection, including podocarpus macrophyllus, Osmanthus fragrans, camellia, mastic tree, Chinese holly, Ilex rotunda, Bischofia tyifliata, Gentiana scabra Bunge, Planchonella spp., Sapindus mukorossi Gaerth and Asnaragus cochinchinensic. These species are mainly distributed in the shrubbery and underbrush of the broad-leaved forest close to villages. None of the mentioned species exist in the project site or reservoir area.. The Old Tree Reserve will be preserved.

Although practically depleted, the Gan River is one of the major habitats of the four major Chinese carps, whose spawning ground is of certain special topographical and hydrographic characters. Every year from April to July when water temperature reaches over 18 C, the four carp species will go to their spawning grounds for breeding. The scale of this migration is related to high flows and flood duration. In unprecedented floods there will be more oviferous laying, while a small-scale flood will bring about limited egg laying or no reproduction at all. In the project section of the Gan River, the spawning in May-June will make up 7080% of the whole spawning season. During the flood season all the scouring sluices of Shihutang Project will be opened for flood discharge in order to avoid raising upstream flood level of the dam and to keep the upstream stretch of the river at natural conditions. Therefore impacts on spawning patterns will be minimal.

Although downstream movements of fish and spawning will not be severely interrupted by the dam, the dam will block the upstream migration of migratory fishes. Some migratory and semi-migratory fish species can not swim back to the upstream for spawning. Therefore, it will be necessary to build fish passing device to lessen impacts of water conservancy projects on fish resources in the Gan River. Although the severity of this impact is quite insignificant given the almost disappearance of migratory fish in the river, Chinese environmental authorities are requiring fish passages and laboratories in all dams along the Gan river in order to facilitate future fisheries development programs. Fish passages and laboratories are included in project costs.

Resettlement. The Project will permanently acquire 194 ha of farmland in 53 villages, which will result in an approximate 6% decrease of land holdings in the affected villages. Measures such as land redistribution, cash compensation, and land improvement were explored following consultation with

7 the affected villagers. About 78 ha of farmland will be used temporarily and returned to the villagers after restoration by the civil works contractors under close supervision from local authorities. 169 affected households comprising 597 persons will be relocated. 95 of these households will build their new houses in their current villages and 74 households will be moved into newly constructed villages, after receiving compensation including the replacement cost for their original houses, movement subsidies and resettlement allowance. During the house restoration process, the local government will provide assistance in addition to specific investment for the planned infrastructure within these villages

Four small enterprises, which do not need to be relocated, will be affected by the project. They will be able to reopen for business in their current locations. The Project will provide compensation for loss of assets and cost of restoration as well as a transitional subsidy for loss of wages or profits during restoration. The employment of the workers will not be affected.

The Project will inundate or demolish some local infrastructures and public facilities in the vicinity of the reservoir and at the dam site. The reconstruction costs of the affected infrastructures and facilities will be fully compensated to the respective owners, who will be responsible for the reconstruction or restoration of the affected infrastructures. The compensation costs for the restoration have been estimated and included in the project budget.

Cultural Resources. Optimization of reservoir embankment alignments has eliminated the need to flood the three unclassified heritage sites (old ferry, old towns). Prior to the construction of the project, the Jiangxi Provincial Cultural Relics and Archaeology Institute will carry out additional field research of all sites, register relevant historical information, and propose additional measures if needed.

The ancient city site is located 40m from the south bank of the Gan River. It is over 60.80m in elevation, higher than the design flood level (58.65m), and therefore will suffer no impacts from water level rise in the Gan River. But the north wall of the ancient city, due to channel re-routing of the Zhulin River, has an Elevation of only 56.7m, about 0.20m higher than the normal storage level (56.5m), but lower than the design flood level (58.65m). Special protection measures (excavation, salvage, grouting, underground screens, humidity protection) will be implemented by the Jiangxi Provincial Cultural Relics and Archaeology Institute before the construction of the Shihutang Project.

Safety of Dams. The Project includes the construction of a 26.5m high dam consisting of a powerhouse, ship lock, sluice gates and an earthen dam about 869 meters in length. The dam forms a run-off type reservoir with normal pool storage of 281 million cubic meters. The project is located about 82km downstream from the existing Wan’an Dam, which is a 46m high dam with normal pool storage of 2.22 billion cubic meters. Therefore, the safety status of the Wan’an dam will substantially affect the normal operation of the Shihutang dam. Therefore, a dam safety assessment of the existing dam is required according to OP4.37.

An independent dam safety panel (DSP), consisting of three experts, has been established to assist the JPMO in ensuring that the Project complies with Bank and Chinese dam safety requirements. For the Shihutang Dam, the DSP will (a) review and comment on the investigation, design, and construction of the dam and the start of operations; (b) review and comment on the safety-related plans prepared by the

8 JPMO. For the upstream Wan’an Dam, the DSP has already conducted an inspection and review on the safety status of the dam. The review concluded that the Wan’an Dam operates under safe conditions

Cumulative Impacts. Shihutang is the second of a cascade of dams that will be built on the Gan River to improve and promote navigation in this important inland waterway. A main reservoir has already been built. A Strategic Environmental Assessment was developed in 2005 for Jiangxi Inland Waterway Navigation Development Plan, which addressed cumulative environmental impact issues. The negative impacts are mainly on aquatic life, especially on migratory fishes, semi-migratory fishes and spawning sites. Multiple-phase construction will cause floating and semi-floating spawn to flow into static waters too early during drifting and hatching process, thus affecting their growth. Since the cascade dam development is mainly for upgrading of existing navigation channel, concerns about an adequate environmental flow will not be an issue. SEPA requests that all dams and locks on the Gan River include fish passage infrastructure, fish laboratories, and implement fish stocking in the river. The positive impacts of the cascade dams are to promote the economic development of the Gan River basin, especially poor counties along the River. The Project will bolster the capacity to manage cumulative impacts at watershed level through a specific training under the TA component of the project.

Linked Projects. There are two projects directly linked to the Shihutang Project: the existing upstream Wan’an Dam; and the 18km transmission line from the powerhouse to the grid which will be constructed by local power authority separately at the later stage of Shihutang Project. For the existing Wan’an Dam, the DSP experts have already reviewed the dam safety status and concluded that the Wan’an Dam operates under safe conditions. For the 18 km transmission line, as the Chinese requirements are broadly comparable to the Bank Policy requirements, the Bank task team will carry out a due diligence exercise on the EIA of the transmission line and their compliance with the Chinese regulations. The JPMO will make available a copy of EIA for the Bank review. Given the low sensitivity of the project area, the transmission line is not expected to raise any significant environmental or social issues.

Environmental Management Plan The EA report recommends the implementation of an Environmental Management Plan (EMP). The EMP proposes a number of measures to mitigate environmental impacts during the construction and operation of the proposed project and establishes an organizational structure, set of procedures and a budget to implement activities under the EMP. The EMP has also identified a set of environmental monitoring activities and capacity building programs to ensure achievement of the project’s environmental objectives. The EMP addresses all issues identified in the EIA, and includes a detailed description of all activities, the institutional responsibilities for implementation, and defines a budget and source of financing for each one of the activities included in the EMP. Most mitigation measures have already been included in project design and included in project costs. Main components of the EMP are presented in the following table.

9 Main Components of the EMP „ Protection of “old tree” forest „ Renegotiation of embankments, canals and river embankments with bamboo „ Fish canal and fish laboratory „ Excavation, “information” salvage, and/or protection of cultural sites „ Management of construction impacts „ Environmental monitoring and supervision „ Resettlement Action Plan „ Institutional strengthening program

Clear environment management responsibilities have been defined for both construction and operation of the Shihutang project. Environmental management must be available throughout the construction and operational periods whereby there will emerge many factors that will have impacts on the environment. Therefore, the project will establish professional administrative institutions that have good professional basis and administrative competence. They will be equipped with necessary environmental protection personnel, being merged into the established integrative and professional environmental protection system to be responsible for carrying out and supervising the work of environmental protection of the project. Environment management procedure during construction

Environment Protection Section of Project Office EA bureau

Fishery bureau EA consultant institution Envi. Monitor. Organ Envi. Supervisor

Forestry bureau

Water bureau &RQWUDFWRUÃÃ

Environment management procedure during operation

(QYLURQPHQWÃ3URWHFWLRQÃ6HFWLRQÃRIÃ3URMHFWÃ0DQDJHPHQWÃ'HSW EA bureau

Fishery bureau EA consultant institution

Forestry bureau

Water bureau Environment )LVKÃSDVVÃ 3UROLIHUDWLRQÃ '\NHÃ ÉÃUHOHDVHÃ 'DPÃ6DIHW\Ã Monitoring 2SHUDWLRQÃ 0DLQWHQDQFHÃ VWDWLRQÃ Organ 6HFWLRQÃ 6HFWLRQÃ 6HFWLRQÃ

10 Comprehensive environmental monitoring programs have been designed for both construction and operation phases of the project. Monitoring includes water quality, fish, hydrology, construction dust and noise, as well as erosion downstream of the reservoir. A qualified environment monitoring company will assist to well do environment monitoring work during construction. During operation, environmental monitoring will be carried out by provincial and prefecture (municipal) environmental protection bureaus, forestry bureaus, water conservancy bureaus and fishery bureaus, being responsible for submitting the annual report on environmental management and for compiling the reports of environmental monitoring during operation.

All personnel of the Project Office Environment Protection Section and construction workers will receive environmental protection training before commencement of construction. Key environmental administrative and monitoring personnel will also receive the technical training. The main issues addressed in the EMP are presented in the following table.

Impact Mitigation Responsibility Construction A detailed set of environmental specifications will be included Contractor, enforced by Impacts in all bidding documents and contracts including traffic control. engineering supervision Environmental training of all workers Workers camp rules Fish impacts Fish passage is already designed and included in project costs. Construction is part of A fish proliferation and fry releasing station will be set to project. Operation will be implement fish proliferation and fry releasing with fry release under the Provincial Fishery quantity of 2.2 million for a long period and the effect of fish administration proliferation and fry releasing will be surveyed; Cultural Although realignment of embankments avoided flooding of Jiangxi Provincial Cultural Resources these sites, archaeological excavation on the Huangkeng Relics and Archaeology Ancient Ferry (work area 600m2) and site of ancient city (work Institute. area 5000m2) to obtain related historic information. The cultural relics and relative historical information of 2 cultural relic points will be transferred to the site protected for historical and cultural value or museum. After the archaeological excavation work is completed, the two cultural relics points can be submerged. The cost of archaeological excavation work has been listed in the project budget. Chance finding procedures. Old trees Construction contractor during construction period will Contractor designate special person to be responsible for the patrol, Enforced by project monitoring on old trees, big trees and provincial level protected supervision. plants in the vicinity of the construction point, so as to prevent harm to old trees, big trees and protected plants due to construction activities or stealthily cut down tree Relocation of Resettlement Action Plan Jiangxi Provincial Population Resettlement Office

Resettlement Plan As a leading resettlement management authority, the Jiangxi Provincial Resettlement Office has reviewed and approved the TOR for the project resettlement planning. The RAP is subject to the approval by the provincial government after the NDRC’s approval of the FSR, and before the commencement of the resettlement actions.

11 Resettlement Policies. Policies and entitlements included in the RAP are based on national, provincial and municipal regulations, as well as requirements in the World Bank’s OP 4.12. The following key considerations and activities were conducted in project planning and design and in RAP preparation: • Optimizing the normal pool level to minimize losses due to inundation. • Minimizing the extent of land acquisition and resettlement by optimizing project design and providing flood protection works. • Surveying socio-economic baseline conditions, and identifying all displaced persons (DP) in households, enterprises and others. • Entitling all displaced persons, including those who have no households’ registration, business licenses or other legal documentation, to compensation or other forms of resettlement assistance so that their incomes and living standards can be improved or at least restored. • Determining compensation for land, structures, and other fixed assets at replacement cost, and submitting the option of compensation either in cash or in kind. • Consulting with displaced persons on arrangements for compensation and assistance. • Establishing mechanism to address complaints and grievances for the displaced persons including discussions, negotiations, arbitration, and legal proceedings. • Arranging supervision and monitoring to ensure the RAP compliance and to address other issues that may arise during RAP implementation

Organizational Management: The JPMO and Taihe County will set up resettlement offices as outlined in the RAP. The staff of the offices will be trained to develop management capacity. The RAP sets out training and resource requirements for these offices. The JPMO will coordinate implementation of the RAP by the county government via its resettlement office. The PMPO will facilitate the coordination with the local government regarding the resettlement when needed.

Resettlement Monitoring: Internal and external monitoring mechanisms for RAP implementation will be set up prior to project implementation. Internal monitoring is to be conducted by the JPMO resettlement office and county resettlement office, which will focus primarily on physical progress. An external monitoring agency will be engaged to report resettlement progress every six months. Apart from physical progress, external monitoring reports will assess household relocation and livelihood restoration as well as transitional measures for affected enterprises, schools and others. The RAP describes monitoring purposes, responsibilities, indicators, methodology, procedures and reporting requirements.

Public Consultation A combination of opinion surveys and public symposia held in the township government, village committee and affected villagers’ homes have been implemented during preparation of the EIA and Resettlement Action Plan studies.

Public notices of the EIA of the Jiangxi Shihutang Navigation and Hydropower Pivotal Project at the Gan River were posted on bulletins and made available in the governments and villager committees. After the public has understood the general situation of the Project and possible impacts, the public participated in the symposia. At the symposia, the Owner and the EIA contractor first introduced the general situation and possible environment impacts of the project, then, the public asked questions, the

12 Owner and the EIA contractor answered those questions. Finally, the public put forward their comments and suggestions about construction of the project; the EIA contractor was responsible for recording and sorting these inputs. In total 17 symposia were held with 132 people in the first round, including the affected households, affected people, affected village committees, township governments, and related functional departments of the environment protection, water conservancy, forestry and communications of Taihe County. This was carried out in the early stages of the EIA as well as the final draft (first and second round consultations).

A wide range of suggestions and concerns were received during both rounds of consultations. These range from employment of local labors as much as possible during construction; to building a new bridge and fending groin at Xinzhou. Other concerns had to do with minimization of required farmland and woodland. A non-inclusive list of recommendations and concerns include: build the project simultaneously with ecological work; assure relocation and resettlement fund paid to the affected people; to commence the project construction as soon as possible and to benefit local people; simultaneously well build water conservancy and flood control facilities; completely solve the water logging problem; earnestly protect the ecological environment at the surrounding of the reservoir area and to resettle people in a fair manner; to protect farmland from being occupied, and improve farming condition at the surrounding of the reservoir area; recommend to the dam open to traffic; and protect the ancestral temple of the village during relocation of Pingshang Village.

Most of the concerns have been incorporated either in project design or in the environmental management plan or resettlement plan.

Disclosure The complete EIA report is available in the Taihe County Government Building for public reference. A summary of the EIA has been placed at the governments of Wanhe Township, Tangzhou Township, Yanxi Township, Chengjiang Township and Mashi Township, and Wushan Reclamation Farm Office for public reference. In October 2007, official notice was posted on the Jinggangshan Newspaper (No.1 newspaper at the location of the Project) for public reference.

13

14