Social Monitoring Report

#2 Semiannual Report November 2020

PRC: Modern Technical and Vocational Education and Training Development Program

Prepared by the Guangxi Education Department for the People's Republic of and the Asian Development Bank.

CURRENCY EQUIVALENTS (as of 18 November 2020)

Currency unit – (CNY) CNY1.00 = $0.1525 $1.00 = CNY6.5568

ABBREVIATIONS ADB – Asian Development Bank AP – affected person CAP – corrective action plan GPMO – Guangxi project management office GRM – grievance redress mechanism GZAR – Guangxi Zhuang Autonomous Region HD – house demolition IR – involuntary resettlement LA – land acquisition LAR – land acquisition and resettlement M&E – monitoring and evaluation PRC – People's Republic of China RBL – results-based lending RF – resettlement framework TVET – technical and vocational education and training

WEIGHTS AND MEASURES m – meter m2 – square meter mu – Chinese unit of measurement (1 mu = 666.667 square meters)

NOTE In this report, "$" refers to United States dollars.

This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Results-based Guangxi Modern Development Program

Resettlement Monitoring Report

(No.2)

March 2020

CONTENTS 1. Background ...... 1 1.1 Project Overview ...... 2 1.2 Overview of Subprojects and Involuntary Resettlement Impacts ...... 3 1.3 Scope of External Resettlement Monitoring and Evaluation ...... 44 2. Land Acquisition and Resettlement Impacts ...... 47 3. Public Participation and Grievance Redress Mechanism ...... 68 4. Institutional Arrangements ...... 81 4.1 Responsibilities of the Institutions ...... 82 4.2 Personnel and Facility ...... 84 4.3 Office Facility ...... 84 4.4 Assessment on Organization Capacity ...... 84 4.5 Institution Capacity Building and Training ...... 86 5 Resettlement Monitoring ...... 89 5.1 University of Aerospace Technology ...... 89 5.2 Guilin College ...... 90 5.3 ...... 91 5.4 Guangxi Transport Vocational and Technical College ...... 92 5.5 Guangxi Vocational College of Industrial ...... 93 5.6 Guangxi Vocational College of Construction ...... 95 5.7 Guangxi College for Preschool Education ...... 96 5.8 University ...... 98 5.9 University ...... 100 5.10 Guangxi Eco-engineering Vocational and Technical College ...... 102 5.11 Guangxi Financial Vocational College ...... 103 5.12 Guangxi Business School ...... 105 5.13 Guangxi Yulin Agriculture ...... 106 5.14 City Luzhai Vocational Education Center ...... 108 5.15 Yulin Shi Di Yi Zhi Zhong Deng Zhuan Ye Xue ...... 109 5.16 Rong County Secondary Specialized School ...... 110 5.17 Hechi City Health School...... 110

5.18 Hechi Yizhou Vocational Education Center ...... 111

5.19 Guangxi Industrial Technician College (The original name is Guangxi petrochemical advanced technical school) ...... 112 5.20 The Second Light Industry Technical School of Guangxi ...... 113

5.21 Guangxi yulin technician college(Guangxi yulin senior technical school) 114

5.22 Liuzhou No.2 Vocational School ...... 115 5.23 QuanZhou Vocational & Technical Schools ...... 116 5.24 city NO.1 secondary vocational and technical school ...... 116 5.25 Guilin Tourism Vocational Secondary Professional School ...... 117 5.26 Liuzhou No.1 Vocational and Technical School ...... 118 5.27 Guangxi Agriculture School ...... 119 5.28 Guangxi Wuzhou Business School ...... 119 5.29 Guangxi Urban Construction School ...... 120 5.30 Guangxi Senior Technical School ...... 120 6 Conclusions and Suggestions ...... 122 6.1 Conclusions ...... 122

LIST OF TABLES

Table 1-1 Guangxi Modern TVET Development Demonstration Program (college) Resettlement Impact and Category—Screening Table ...... 5

Table 1-2: Resettlement M&E Schedule...... 45

Table 2-1: 30 Resettlement Impact and Category of Schools of Subproject under Construction—Screening Table (Draft) ...... 48

Table 3-1 Project Public Participation and Information Disclosure ...... 68

Table 3-2 Project Appeal Table ...... 73

Table 3-3 The Feedback Form of Grievance Redress Mechanism ...... 74

Table 3-4 The Data of Grievance Redress ...... 77

2

1. Background

This report presents the second semiannual monitoring report on implementation of resettlement provisions consistent with the Program Action Plan agreed for the

Results-based Lending (RBL) Guangxi Modern Technical and Vocational Education and Training (TVET) Development Program. The status of progress on each of the actions related to involuntary resettlement safeguards in the Program Action Plan for the monitoring period July 2019 to December 2019 is summarized in Table below:

No Action Status Reference Remarks 1 Carry out the necessary screening, Completed for 74 Table 1-1 In the event of any preparation of resettlement planning schools proposed Guangxi Modern changes to documents, and implementation and in the RBL TVET locations monitoring of resettlement activities in program Development identified, the accordance with the agreed Program (college) screening will be resettlement framework Resettlement revised and Impact and recategorized, in Category— line with the Screening Table potential impacts.

2 Assign a staff at the PMO to act as Completed Section 4.2 - resettlement coordinator on resettlement activities, prepare resettlement monitoring reports, and maintain a resettlement database 3 Engage an external resettlement Monitoring to be Table 1,2 It has been monitor, acceptable to ADB and the carried out during Resettlement agreed between PMO, to carry out resettlement the RBL M&E Schedule. ADB and the PMO monitoring on a semiannual basis; implementation Chapter 5 that the semiannual external monitoring period summarizes the semiannual reports prepared by the external findings of the monitoring report resettlement monitor to be submitted monitoring carried will be prepared simultaneously to ADB and the PMO out for 30 of the by the TRTA 74 schools being consultant with taken up under support from the RBL program. PMO. As a result, the external resettlement monitor has not

No Action Status Reference Remarks been engaged. 4 Establish clear roles and Completed Section 4.1 - responsibilities on resettlement as part details the of the program’s institutional responsibilities of arrangements the various institutions responsible for land acquisition and involuntary resettlement 5 Ensure timely submission of internal Completed - monitoring reports to ADB, and The resettlement disclose resettlement monitoring To be carried out monitoring reports reports to the village committee and to be disclosed TVET institutions in local language upon finalization of reports. ADB = Asian Development Bank, M&E = monitoring and evaluation, PMO = program management office, RBL = results-based lending, TRTA = transaction technical assistance, TVET = technical and vocational education and training. 1.1 Project Overview

The results-based Guangxi Modern TVET Development Program will strengthen the capacity of education departments of regional, municipal and county in the Guangxi

Zhuang Autonomous Region (GZAR) to provide guidance and supervision for vocational education institutions and manage projects.

The program will support various building, procurement of advanced practice and training equipment, and training of teaching staff of vocational education institutions

(schools) in Guangxi province. It will also support government capacity-building efforts to achieve effective management of TVET system; improve the standards and quality of vocational and technical education, strengthen cooperation between schools and enterprises, and establish partnerships with ASEAN region institutions to promote regional cooperation. The project will have the following four outputs:

Output 1: Industry relevance of the technical and vocational education and training enhanced. Explore a new mode of school–enterprise cooperation in which enterprise participate in lesson, training materials and method developing, evaluation process, promote the upgrading of professional construction and support the 2

construction demonstration characteristic specialty and training base by school-

enterprise cooperation.

Output 2: Quality of technical and vocational education and training improved. Strengthen the internal quality assurance in vocational college, teaching diagnosis and improving work system, improve vocational college, especially the teaching environment in secondary vocational schools, and strive to meet the national construction standards. Further improve the capacity of the faculty, establish a

“double-qualified” teacher certification and incentive system, increase the proportion of “double-qualified” teacher with teacher certification and vocational qualification certification.

Output 3: Inclusiveness of technical and vocational education and training increased. Expand access for poor students to capacity-building subsidy such as

counseling, career guidance and employment service, so that they can successfully

find jobs or start their own businesses after completing their studies. support the

building of national cultural heritage and innovation bases and promote the inheritance

and innovation of national culture.

Output 4: Role of technical and vocational education and training in regional economic development expanded. Strengthen the transfer of technology and knowledge between Guangxi and ASEAN countries, promote long-term cooperation

between vocational schools in Guangxi and ASEAN countries, increase the number of

two-way exchanges, and expand the number of ASEAN students who have obtained vocational education certificates in Guangxi.

1.2 Overview of Subprojects and Involuntary Resettlement

Impacts

According to the involuntary resettlement impact screening list and subproject content list provided by each subproject school, there are a total of 74 subproject schools, including 22 colleges and 52 secondary vocational schools. The 74 schools are mainly used to build and improve teaching buildings, training buildings and administration buildings in the campus, and improve infrastructure equipment and 3

information construction as well as teachers.

According to preliminary investigation, the proposed 74 subproject schools are screened and categorized as follows, which might be recategorized when more information available during the implementation.

 60 subproject schools are built on the reserved land of the original campus

without land acquisition (LA) and house demolition (HD) impact, which are

categorized as C;

 10 subproject schools have completed the LA and HD from 2010 to 2019, and

the land acquisition of 3,265.88 mu has been completed, which are

categorized as B;

 4 subproject schools have not yet determined the construction content of

specific projects, and the category is not decided yet.

For the 10 subproject schools that have completed land acquisition and house demolition, only the project content and the amount of land expropriated are provided, specific data of the affected persons (APs) and consultations with the APs are currently being undertaken by the Guangxi program management office (GPMO). The next monitoring report will conduct a site visit to the 10 subproject schools and the schools about to start construction, collect relevant information such as the compensation contract of land acquisition and house demolition, payment vouchers, and check whether the APs have any unresolved grievances, and whether there are legal disputes over the land or inheritance.

The detailed resettlement situation of 74 subproject schools is shown in Table 1-

1.

By the end of November 2019, 30 out of 74 subproject schools are under construction, and the others have not started yet. According to the investigation, 30 subproject schools that have started construction are categorized as C in terms of land acquisition and resettlement (LAR). The resettlement information of these 30 subproject schools was detailed in this report.

4

Table 1-1 Guangxi Modern TVET Development Program (college) Resettlement Impact and Category—Screening Table As of November 2019 Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) 1. Civil project is a construction content The new campus has completed of the new campus extension project. LA and HD in 2017. As Guilin Including NO.1 to NO.4 Training University of Aerospace Center, Center of Students Innovation Technology participates the and Entrepreneurship as well as the Guangxi reginal cooperation and Comprehensive Gymnasium. The total integration promotion project construction area is 44,376.93 m2 and (project no: 50050-004), and covers an area of 14,890 m2. DDR has been prepared for the 205 million yuan 2. Maintenance and renovation project. newly campus in 2017. Guilin University (130 million yuan The estimated cost of the maintenance According to the conclusion of 1 of Aerospace Guilin City from ADB and 75 Category C and renovation project is 30 million DDR, land acquisition Technology million yuan yuan and 20 million yuan from ADB compensation and resettlement supporting funds) Being loan will be planned to put into use in of house demolition have been constructed 2019. completed, the land certificate 3. Balance Payment of the has been obtained in 2018, there Construction. Balance payment of is no remaining problems. apartment buildings No.2, 5 and 6 in The old campus obtained the the south campus is expected to be land certificate in 2004. After paid with 15 million yuan, and it is investigation, there are no planned to use loans all from ADB. remaining problems. 1. The main content of the project is a The school obtained the land teaching facility construction project certificate in 2004 and the Guilin Tourism 2 Guilin City named "college students physical 133.88 million yuan Category C construction contents are in the College education teaching center", in addition original campus, the acquired to the construction installation project, land is reserved for the school,

5

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) equipment purchases and supporting and there is no LA and HD municipal facilities. The main body impact. adopts frame structure, and the building has two floors. The construction area is about 18,000 m2. 2. The main content of construction including a teaching facility construction named "Bagui cuisine culture experience center" and renovation of the original training center (Hotel Training Center). 3. The content of the Talent Project Plan including introduction of high-level talents, teacher training and promotion. 4. The contents of the International Cooperation Projects including consulting fee and certification fee, OLF training fee, teaching fee and construction of ASEAN tourism vocational service platform. 1 Comprehensive teaching building The school completed the LA in No.7 and sports facilities construction 2009 and the land project. The construction area of No.7 compensation, and obtained the Investment Yulin Normal comprehensive teaching building is land certificate in 2014, there is 3 Yulin city amount: 147.98 Category C University 25,000 m2; a standard 400-meter no remaining problems. million yuan ground track field with 3,000 m2 According to the investigation, platform and audience area; road, the construction contents are power, water supply, sewage and in the original campus, the

6

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) greening will be also equipped as well acquired land is reserved for the as the pavement of Yulan Lake, school, and there is no LA and Qingshui Platform and Square of Yulan HD impact. Lake. 2. Basic laboratory renovation and upgrading project (including experimental instruments, equipment and software systems). 3. Construction of Information Center (including cloud center, servers, switches and other basic equipment). 4. Supporting facilities of dormitory No.7 and No.8 (including bed, multifunction desk, chair and air condition and so on). The school obtained the land The total construction area is Guangxi certificate in 2003. According to 66,354.36 m2 and covering an area of Transport 227.54 million yuan the investigation, the 17,834.95 m2. including newly built Vocational and Nanning (70.99 million yuan construction contents are in the 4 cars and track training buildings for Category C Technical city /156.55 million original campus, the acquired 27,215.36 m2, road and bridge training College of yuan) land is reserved for the school, buildings for 39,139 m2. Equipped with Communications and there is no LA and HD parking lot, road and greening. impact. The total building covering an area of According to the investigation, Guangxi 114.79 million yuan 14,100 m2 and construction area is the land of original campus was Vocational Nanning (ADB and KfW 5 51,025 m2 (including 2,9584 m2 Category C state-owned unused land and College of City Loan for 20 million construction area of the intelligent allocated to the government of Industrial yuan/supporting manufacturing training base of Wuming county, GZAR on 8

7

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) Guangxi Vocational College of funds for 94.79 January 2003. Since the Industrial) million yuan) government has not yet developed and utilized the land, the surrounding farmers have reclaimed and cultivated during this period. In 2012, the government of Wuming county has made green crop compensation to the farmers who cultivated the land. After completing the green crop compensation, the land has been allocated to Guangxi Vocational College of Industrial. There are no remaining problems. Total construction is 34,780 m2 (including office building for 10,837.1 According to the investigation, m2, basement for 3,667.9 m2, the construction is in the original information center for 2,127.9 m2, campus, the acquired land is Guangxi library for 18,147.1 m2), covering an reserved for the school, and Vocational Nanning 6 area of 5,218.8 m2. The building is 147.06 million yuan Category C there is no LA and HD impact. College of City frame-shear wall structure. The The school obtained the land Construction construction content includes building, certificate in 2016. According to structure, water supply, electric, the investigation, there is no heating, air condition, fire control and remaining problems. environment protection.

8

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) The construction for Phase I covers an area of 477,102.39 m2 (about 715.65 mu). 427,028.8 m2 (about 640.54 mu) for net area. The construction content includes According to the investigation, teaching and training building (public Total investment is the land occupied by the new teaching room, teaching and training 1,733.21 million campus of Guangxi College for room and office room), library, indoor Guangxi College Nanning yuan (ADB loan Preschool Education is state gym, office room, assembly hall and 7 for Preschool Educational 144 million Category C owned land, and the allocation students activity room, student Education Zone yuan/supporting procedures of state-owned land dormitory, dormitory for single staff, funds for 1,589.21 have been completed, the land canteen, office supporting room and million yuan) certificate is being applied now. attachment room and so on. As well as There is no LA and HD impact. the supporting infrastructure such as intelligent system, playground, water supply, electric supply, front gate, wall, road, greening and viewing, water and square. 1. Building a 15-floor vocational The school obtained the land training building. Covering an area of certificate in 2016. there are no 2,520 m2 and the construction is remaining problems. According 30,000 m2. to the investigation, the 8 Hechi University Yizhou City 2. Demolished the old dangerous 82.39 million yuan Category C construction is conducted on the building and rebuilt a 7-floor student site where two old dangerous dormitory. The building covers an area training buildings in the original of 3,926.30 m2 and the construction campus are demolished. There area is 10,409.75 m2. is no impact of LA and HD.

9

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) 3. 15,000 m2 of the surface of the teaching building and 3,000 m2 environmental maintenance; 19.500 m2 of artificial grassland and runway renovation project; 4,500 m2 of roof renovation on gym; 800 m2 for the well lid of the ditch in school as well 850 m2 of the road widening; 500 m2 single floor -framed training room for art and design; 400 m2 renovation of the art and design exhibition hall; circuit expansion 1250KVA box transformer and laying 10KV cable. 1. Civil of the comprehensive experimental building (technical building). The school obtained the land 2. Reeducation and training center certificate in 2003. According to 3. Comprehensive practical training the investigation, the platform for economic and Wuzhou Wuzhou construction contents are in the 9 management vocational education. 105.5 million yuan Category C University City original campus, the acquired 4. Intelligent control and manufacturing land is reserved for the school, integrated training platform and there is no LA and HD 5. Comprehensive training room for impact. teacher’s educational ability 6. Intelligent renovation of library. 7. Construction of teaching staff

10

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) The school obtained the land certificate in 2003. According to Guangxi the investigation, the Eco-engineering Construction of No.3 and No.4 student Liuzhou Total investment is construction contents are in the 10 Vocational and dormitory, a cooking practice building, Category C city 176.63 million yuan original campus, the acquired Technical and a library, a total of 45,313.14 m2. land is reserved for the school, College and there is no LA and HD impact. The school obtained the land Total estimated certificate in 2013, there is no investment of the Guangxi remaining problems. According project is 97.61 Finance 28,116.91 m2 of the construction of to the investigation, the Nanning million. The loan is 11 Vocational and library, including 24,500.72 m2 above Category C construction contents are in the City 60 million yuan, Technical ground and 3,616.2 m2 underground. original campus, the acquired with supporting School land is reserved for the school, facilities of 37.61 and there is no LA and HD million yuan. impact. Two comprehensive buildings with the function of practical training and teaching and student accommodation The school obtained the land will be built, covering an area of 937.04 certificate in 2005. According to m2, with a total construction area of the investigation, the Guangxi Liuzhou 12 6,680.2 m2 (1,874.08 m2 for practical 25 million yuan Category C construction is in the original Business School city training and teaching and 4,806.12 m2 campus, the acquired land is for student accommodation). A reserved for the school, and dormitory building, covering an area of there is no LA and HD impact. 383.81 m2, building area of 2,363.06 m2 at the same time supporting

11

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) automobile marketing training equipment and corresponding facilities of student apartments. 1. An investment of 18.2026 million yuan is invested in the construction of a seven-story high building (including empty space), 2# teaching building in the campus with an area of 1,223.62 m2 and a total construction area of 9,000 m2. 2. An investment of 3.5 million yuan was used to purchase teaching A total estimated equipment and facilities, including: investment of The school obtained the land (1)An investment of 1.674 million 21.7026 million certificate in 2011. According to Guangxi Yulin yuan was used to purchase 54 sets of yuan , including : the investigation, the 13 Agricultural Yulin city multimedia equipment for classroom of proposed KFW Category C construction is in the original School 2# teaching building. loan of 20 million- campus, the acquired land is (2)An investment of 0.48 million yuan yuan, self-raised reserved for the school, and was used to purchase 2000 sets of funds of 1.70 there is no LA and HD impact. desks and chairs for 2# teaching million yuan. building classroom. (3)An investment of 1.346 million yuan was used to purchase a batch of new energy vehicle equipment, and build three training rooms, including the training room for basic technology of new energy vehicles, the training room for integration of electricians and

12

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) electronics of new energy vehicles, and the training room for new energy vehicles. The project covers an area of 2,133.40 m2, with a total construction area of 15,128.01 m2, including an above- ground construction area of 11,148.09 m2. There are six floors above the ground, one floor underground. The basement is 4.5 meters high and the A total investment The school obtained the land first floor is 4.2 meters high, the height of 37.89 million certificate in 2010. According to Liuzhou city of the two to six layers is 3.9 m, and the yuan (20 million the investigation, the Luzhai Luzhai total height is 23.85 m. The basement 14 yuan from Category C construction is in the original vocational county is mainly equipped with motor vehicle ADB/supporting campus, the acquired land is education center parking space, fire pool, water pump funds of 14.89 reserved for the school, and room, generator room and power million yuan) there is no LA and HD impact. distribution room; The first to fifth floors are mainly equipped with training rooms, preparation rooms, toilets, guard rooms, boiling water rooms, lecture halls and reading rooms. There are offices, toilets, guard rooms and boiling water rooms on the sixth floor. 1. Two (1#, 4#) student dormitory A total investment The school obtained the land Yulin No.1 building construction, the total of 21.5 million certificate in 2015. According to Secondary 15 Yulin city construction area of 3,817.82 m2, yuan(ADB Category C the investigation, the Vocational including: 1# student dormitory, the investment of 20 construction is in the original School floor area of 316.34 m2, a total of five million yuan/self- campus, the acquired land is

13

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) floors, the construction area of raised funds of 1.5 reserved for the school, and 1,637.98 m2; 4# student dormitory, the million yuan) there is no LA and HD impact. building covers an area of 326.62 m2, the design of the empty space, a total of six floors, the construction area of 2,179.84 m2; 2. Construction of intelligence campus 3. Purchase of professional training equipment for and western cuisine 4. Logistics service and management professional training base construction 5. Book purchase According to the investigation, Student dormitory project of campus Rong county the subproject construction is expansion project covers an area of secondary Rong ADB investment of in the original campus, the 16 1,221.26 m2; e-commerce training Category C Vocational county 29.79 million yuan acquired land is reserved for the building project of campus expansion school school, and there is no LA and project, covers an area of 1,275 m2 HD impact. Total investment: According to the investigation, The new construction for training 29.24 million yuan the new training building of building of Hechi City Health School /25 million yuan Hechi City Health School will Hechi City covers an area of 1,186 m2. the (ADB) / 4.24 17 Hechi city Category C demolish the school’s old Health School demolished old auditorium in this million yuan auditorium and rebuild it on the school is used for construction, which (Local site. There is no LA and HD does not involve land acquisition. government impact. supporting funds)

14

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) 1. The area of occupied land of vocational education center fusion education complex building in Hechi The school obtained the land city is 810 m2, with a total Hechi certificate in 2014. According to construction area of 7290 m2 20 million yuan Yizhou the investigation, the 2. The project of production-education (ADB: 20 million 18 Vocational Hechi city Category C construction is in the original integration information equipment yuan/ Local Education campus, the acquired land is procurement and installation for Yizhou supporting funds) Center reserved for the school, and vocational education center in there is no LA and HD impact. Hechi city, is mainly information equipment procurement and installation. The student apartment for high-skilled talents is located in the east of the middle of the campus, with a total The total construction area of 19,304.25 m2. The investment of the area of occupied land for building is The school obtained the land project is 48.81 11,44.67 m2,it is high-rise buildings certificate in 2014. According to Guangxi million yuan with 17 floors. The building is used for the investigation, the Industrial Nanning (Germany KFW 19 the student dormitory and supporting Category C construction is in the original Technician city bank is 20 million rooms. The main contents of campus, the acquired land is College yuan, and the construction include construction reserved for the school, and school raised engineering, decoration engineering, there is no LA and HD impact. 28.81 million yuan water supply and drainage by itself). engineering, electrical engineering, heating engineering and general level related supporting engineering

15

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) It had completed the land A student dorm building with a six-layer acquisition in 2014 and gotten frame structure will be constructed in land certificate in 2015. 139.98 this project. The height of building is mu land has been acquired The Second 25.8 m, the total area of building is which concludes cultivated land Light Industry 10,322.2 m2, the occupied land of Nanning A total investment: of 19.89 mu, garden plot of 20 Technical building is 3,247.86 m2. There will be Category C city 28.11 million yuan 87.88 mu and forestland of School of 227 standard apartment dormitories (8 32.21 mu. After investigation, LA Guangxi persons/room), 2 accessible work had been completed, and dormitories (2 persons/room), 5 public its compensation had been laundry rooms and 1 management completed in 2014. There are no room in this new building. remaining issues, The project will build a training Total investment: Guangxi yulin According to investigation, the comprehensive building with 8 floors 29.03 million yuan technician practical training building is and public auxiliary facilities, the area (KFW: 25 million college(Guangxi built in the original campus of the 21 Yulin City of construction planning land is 3,991 yuan, the Category C yulin senior school, and the land was m2, the area of planning occupied land supporting funds: technical reserved for the school. There is is 1,056.69 m2, total area of building is 4.03 million school) no impact of LA and HD. 8,904.00 m2. yuan) 1. Build a new integrated teaching building, and at the same time, build The school obtained the land supporting power supply and certificate in 2010. The Liuzhou NO.2 distribution, water supply and Liuzhou Total investment: construction is in the original 22 Vocational drainage, and other ancillary facilities. Category C city 61.73 million yuan. campus, the acquired land is School 2. The project will cover an area of reserved for the school, and 2,713 m2, the building covers an area there is no impact of LA and HD. of 13,738 m2. The main content of construction is to build a 4# training

16

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) school and water supply and drainage and other ancillary facilities. 1. A new student dormitory building, 5- floor frame structure building, covering an area of 881.29 m2, a total The school obtained the land construction area of 4,524.55 m2. certificate in 2008. According to Quanzhou 2. Construct a one-floor steel frame the investigation, the Vocational & Quanzhou structures mechanics training 23 22 million yuan Category C construction is in the original Technical county workshop, the building covers an area campus, the acquired land is Schools of 1,600 m2, with a total construction reserved for the school, and area of 1,600 m2 there is no LA and HD impact. 3. Information teaching equipment 4. Upgrade and replace training equipment A newly training comprehensive building will be built, covering an area of 800 m2, the ground floor will be 13 The total Guiping city According to the investigation, floors, a total construction area of investment of the NO.1 Secondary the construction is in the original 9,812 m2, supporting with related project is 20 24 Vocational and Guiping city Category C campus, the acquired land is ancillary projects. The main million yuan (KFW Technical reserved for the school, and construction content is civil loans of 20 million School there is no LA and HD impact. engineering, water supply and yuan.) drainage, fire control, electrical, lightning protection and other projects. 1. Teaching comprehensive building: The school obtained the land Guilin tourism land area: 1,130 m2, the total area of certificate in 2005. According to 25 vocational Guilin city 25.68 million yuan Category C building:5,400 m2,the height: 18 m(5 the investigation, the secondary ground floors) subprojects are rebuilt on the

17

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) professional 2. Counseling center building covers site where the training building in school an area of 362 m2, including group the original campus is activity area, sand table game area, demolished, and there is no LA music relaxation area. and HD impact. 3. Computer application professional training base: 3 training room, including:(a) 1 computer professional animation graphics processing room (55 desk computers) covers an area of 102 m2; (b) 1 Network comprehensive wiring competition to upgrade the training room, located in training building 4# 4-1 room, covering an area of 102 m2 ; 3. PDS engineering technology certification training room (Network integrated wiring engineering certification training room), covering an area of 102 m2. In addition, Including training equipment procurement and training room decoration. 4. Stadium stage construction project: which covers an area of 200 m2. 5. The renovation project of the lecture theatre (multifunction hall): located in 2 floors of 7# in school,which covers an area of 404 m2, including sound amplification system, LED and other supporting facilities and equipment.

18

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) 6. Renovation for track and field plastic ring runway: Refurbishment for a plastic ring track at the standard of 8 tracks, 400 m, including a mixed plastic track: 8,148 m2; 30 mm reinforced non- filling artificial turf: 7,775.6 m2. 7. Rebuilding the dining room: covering an area of 1,125 m2, the repast area is 1,406 m2. Including the demolition and reconstruction of the old operation room, internal washing and elimination facilities and equipment in the operation room, water supply and drainage lines, the ground will be changed to anti-skid environmentally friendly glue ground, decorative partition, new add dining table cover, healthy diet culture canteen management materials. 1. Power electrical renovation The school obtained the land 2. School teaching, work area of smart certificate in 2010. According to Liuzhou No.1 water and electricity meters and the investigation, the Vocational and supporting facilities 26 liuzhou city 25 million yuan Category C construction is in the original Technical 3. Energy-saving hot water supply campus, the acquired land is School system for student dormitory reserved for the school, and 4. Indoor and outdoor lighting lamps there is no LA and HD impact. and lanterns transformation

19

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) 5. Construction for Integrated business information system 6. Construction for financial management internal control system 7. Introduction of western food courses and vocational qualification certificates 8. Constructing new student dormitory buildings 1. The project will construct a teaching building with 5 ground floors, and the building covers an area of 2,822.7 m2 2. The project will construct a training The school obtained the land student dormitory building with 5 certificate in 2002. According to Guangxi ground floors, and the building covers the investigation, the Qinzhou Qinzhou an area of 3,500 m2. 27 25 million yuan Category C construction is in the original Agricultural city 3. Purchasing 10,000 books. campus, the acquired land is School 4. Purchasing information campus reserved for the school, and system, professional teaching there is no LA and HD impact. resources, library digital management system and another digital platform. 5. Teacher training 6. Purchasing 100 computers Guangxi Wuzhou Business School The total The school obtained the land proposes to build one Training investment amount Guangxi certificate in 2011. According to Wuzhou Building, with 7 floors above ground of 26.73 million 28 Wuzhou Category C investigation, the dilapidated old city and 1 underground floor (for yuan, the ADB Business School administrative office building in underground civil anti-parking loan will be 25 the original campus will be facilities). The building covers an area million yuan, and

20

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) of 672.74 m2 and the total construction the school self- demolished, and there is no LA area is 6,696.26 m2. The main raised funds is and HD impact. construction contents include civil 1.73 million yuan. engineering, decoration works, equipment and tools purchase, water supply and drainage engineering, electrical engineering, outdoor site hardening and greening, etc. 1. Sewage treatment center. 2. Sports center 3. No. 17 Teaching Building; newly build 1 teaching building, with 6 floors, and total construction area for 4,650 m2, including civil work and installation. 4. National Craft Inheritance and The school obtained the land Innovation Training Building, with total certificated in 2012. According to of 2 floors, with total construction area Guangxi Urban the investigation, the for 3,000 m2, including civil work and 29 Construction Guilin City 30 million yuan Category C construction is in the original installation. School campus, the acquired land is 5. UAV application technology reserved for the school, and production and education integration there is no LA and HD impact. training base: (1) The indoor training room covers an area of about 300 m2, and the outdoor training field covers an area of about 5,000 m2. Including two major modules, the UAV production and teaching integration of basic skills training module and UAV production

21

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) and education integration surveying and mapping industry application training module. (2) Basic training and cultural construction of the training room; (3) Related equipment and facilities. 6. National Crafts Inheritance and Innovation Training Room: Baogui concrete training ground, Fine woodworking training room, Carved porcelain training room 7. Student Comprehensive Literacy Center: including Mind Oxygen Bar, Music House, Glamour Body Shape Dance Room, Dance Club, Tea Art Club, Originality Club. 8. School–enterprise cooperation dual- sector construction (teacher training, corporate training), teaching ability improvement (information training, professional training, etc.), school executive training, school and enterprise teacher training (including foreign training), totaling of 70 person/times or more. Guangxi Integrated teaching building 55.32 million yuan The school obtained the land Nanning 30 Nanning Senior construction project of Guangxi (25 million yuan Category C certificate in 2014. According to city Technical School Nanning senior technical school, main from ADB/ 30.32 the investigation, all subprojects

22

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) construction contents: foundation pit million yuan of are in the original campus, the support engineering, civil engineering, local supporting acquired land is reserved for the installation engineering, water supply funds) school, and there is no LA and and drainage engineering, electrical HD impact. engineering, heating engineering, elevator engineering, firefighting engineering, outdoor greening engineering, outdoor road engineering, sponge city, green building, etc. Construction scale: this project will build an integrated teaching building, with a total land area of 9,227.51 m2 (13.84 mu in total) and a building area of 19,054.06 m2, including an above- ground building area of 14,894.06 m2, including a building area of 14,591.70 m2 for practical training and a building area of 302.36 m2 for ancillary buildings. The underground building area is 4,160.00 m2. And supporting roads, greening, outdoor hydropower and other ancillary projects. Guangxi 1. Intelligent manufacturing innovation The school obtained the land Vocational center: it is planned to construct the A total investment certificate in 1999. The College of Nanning first floor of the first practical training of 47.56 million construction is in the original 31 Category C Have not started Mechanical and City building to be put into use in the yuan (40 million campus, the acquired land is Electronical college, including the training room of yuan of ADB) reserved for the school, and Technology the comprehensive practical training there is no LA and HD impact.

23

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) system of intelligent processing unit, the training room of the comprehensive practical training system of industrial robot technology application and the training room of Siemens advanced automation technology. The total construction area is about 1,000 m2. Self-owned capital construction. 2. Mass entrepreneurship space: it is planned to build a student innovation and entrepreneurship base including seed incubation room, start-up incubation room, open Shared work platform, entrepreneurship training center, road show hall and other places on the second floor and part of the second teaching building on the second floor of the college, with a total construction area of about 3,000 m2. 3. The college students' cultural quality education base: plan the second would be built in the college classroom teaching building on the fourth floor of the whole layer and the second and third floor construction includes parts of college students creative studio, youth culture media center, the second classroom transcripts experience show

24

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) center, student community cultural exchange area, the second classroom performance database, dance studio, music studio, such as moral lecture hall, the amphitheater, a students' cultural quality education center, a total construction area of about 1,700 m2. A student apartment building with 6 floors above ground and 1 floor Total investment is The school obtained the land Guangxi underground will be built, covering an 40 million yuan certificate in 1998. The Vocational and Nanning area of 2,258.07 m2, the total (including 34 construction is in the original 32 Category C Technical city construction area is 14,963.55 m2 million yuan from campus, the acquired land is College (including 13,098.75 m2 above ground ADB and 6 million reserved for the school, and and 1,864.80 m2 underground), the yuan from school) there is no LA and HD impact. building height is 21.85 m. Newly built 3 student dormitories and a The school obtained the land Guangxi canteen building, with a total area of Total investment is certificate in 2004. The Vocational Nanning 4,493 m2 and a total construction area 78 million yuan. construction is in the original 33 College of Category C City of 32,727.45 m2. The estimated total ADB loan for 65 campus, the acquired land is International investment of the project is 102.76 million yuan reserved for the school, and Business million yuan. there is no LA and HD impact. The total construction is 62,483.14 m2, Total investment is The school obtained the land building area is 2,938.44 m2. 170 million yuan. certificate in 2010. The Construction area for 15# student ADB loan for 57 Guangxi Medical Nanning construction is in the original 34 dormitory is 1,498.12 m2; construction million Category C College City campus, the acquired land is area for student dormitory is 31,858.48 yuan/supporting reserved for the school, and m2. 22 floors above ground, 1 floor funds for 113 there is no LA and HD impact. underground and the building height million yuan.

25

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) 79.64 m. Construction area for 16# student dormitory and canteen is 1,440.32 m2. The functions are student dormitory, kitchen and canteen, the building area is 30,624.66 m2 (including underground area for 2,818.28 m2, capacity area for 2,156 m2 and 662.28 m2 out of calculate). 20 floors above ground, 2 floors underground and the building height 74.25 m. 1. Project of student dormitory: two 8- floor frame structure buildings. The Nanning The construction is in the original construction area is 20,000 m2 Prefecture campus, the acquired land is 35 including furniture and other 61 million yuan Category C Education City reserved for the school, and equipment. College there is no LA and HD impact. 2. 100,000 books, library digital resources and equipment 1. Construction of practical training The school obtained the land Guangxi platform for general skills of teachers' certificate in 2012. The Science and specialty in demonstration teacher construction is in the original 36 Technology City education base. 80.78 million yuan Category C campus, the acquired land is Normal 2. Library resources and equipment reserved for the school, and University construction. there is no LA and HD impact. 3. Construction of intelligence campus. 105 million yuan The school obtained the land Hezhou 1. The industry-education integration 37 (75 million yuan Category C certificate in 2012. The University City training center covers an area of 6,650 from ADB construction is in the original

26

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) m2, and the construction area is 20,000 loan/supporting campus, the acquired land is m2. Total 6 floors, frame structure. funds for 30 million reserved for the school, and 2. The local ethnic studies center yuan) there is no LA and HD impact. covers an area of 5,305 m2, and the construction area is 14,442.25 m2. Total 4 floors, frame structure. 3. The modern vocational education experimental training center planning purchase 4 laboratories' modern vocational education training equipment The proposed "Guangxi Ji Dian Gong Cheng Xue Xiao Shuangchuang building" is located in the west of Guangxi Ji Dian Gong Cheng Xue Xiao, on Anji avenue. A teaching building covers an area of 1,650 m2 A total investment The school obtained the land and a construction area of 10,140 m2 of 40 million yuan, certificate in 2012, after Guangxi Ji Dian (including the basement of the negative including 25 million investigation, the construction is Nanning 38 Gong Cheng first floor covering an area of 2,800 m2). yuan of ADB, 15 Category C in the original campus, the city Xue Xiao 2. Floor function design: the first floor: million yuan of acquired land is reserved for the reception center and car beauty and local supporting school, and there is no LA and sales center; The second and third funds. HD impact. floors: school–enterprise cooperative hotel management and training base; Fourth and fifth floors: entrepreneurship and innovation training, skills training, policy

27

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) consulting and information service room; Floor 6 to 9: "introducing enterprises to school" workshop room; Level 10: training and large conferences. The project contents include civil engineering, electrical engineering, water supply and drainage engineering, firefighting engineering, A total investment solar energy hot water engineering, of 92 million yuan. After investigation, the Guangxi elevator and split air conditioning, etc. The proposed construction is in the original Institute Science Nanning The total construction area of the KFW loan is 25 39 Category C campus, the acquired land is and Technology city project is 36,167.39 m2, including the million yuan, and reserved for the school, and School construction of an art training building the supporting there is no LA and HD impact. of 12,557.23 m2, a teaching and funds is 67 million training building of 9,905.47 m2, a yuan. student dormitory building of 5,844.48 square meters, a library of 8,244.96 square meters. A total investment The school obtained the land of 46.5217 million Construct a teaching building with 15 certificate in 1996, after yuan. The ADB layers on the ground, one underground investigation, the construction is Guangxi Textile Nanning loans of 2.5 million 40 layer, a total construction area of Category C in the original campus, the Industry School city yuan, and the 15,872.37 m2, covers an area of acquired land is reserved for the school raised 996.40 m2. school, and there is no LA and 21.52 million yuan HD impact. by itself.

28

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) 1. A new 12-story student apartment building with a floor area of 14,754.29 m2 is concave, 50.30 m long, 39.20 m wide and 43.50 m high. There are 12 floors above ground, each of which is 3.60 m high. Underground parking is provided in the building. 2. To build an information management platform based on big data and Internet The school obtained the land of Things. The construction contents 37.5 million yuan certificate in 2013, after Guangxi include intelligent campus (ADB of 25 million investigation, the construction is Nanning 41 Overseas informatization unified management yuan/ supporting Category C in the original campus, the city Chinese School platform, campus one-card system, funds of 12.5 acquired land is reserved for the teaching diagnosis and improvement million yuan) school, and there is no LA and quality monitoring and analysis HD impact. platform, teacher professional development platform, professional development and evaluation platform, teaching resources and network teaching platform, as well as hardware infrastructure equipment needed to support the operation of each platform and system. Guangxi The project is a new practical building, The school obtained the land nationality the building area: 1,243 m2, building certificate in 1993, after Nanning 30 million yuan/ 42 secondary with 10 layers, building height of 36.3 Category C investigation, the construction is city (KFW) professional meters, a total construction area of in the original campus, the school 9,614.95 m2. acquired land is reserved for the

29

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) school, and there is no LA and HD impact. The school obtained the land certificate in 1981, after investigation, the school Guangxi construction content is to Youjiang A teaching administrative complex demolish the small dangerous 43 Commercial city building is to be built covers an area of 9 million yuan Category C and old teaching administration College for about 600 m2. complex building, the acquired Nationalities land is reserved for the school, and there is no LA and HD impact. This project is divided into three aspects: practical training condition construction, information construction and teacher training. The construction A total estimated of practical training conditions includes investment of The school obtained the land the construction of a new VR wisdom 25.28 million yuan certificate in 2010, after Gvangjsih practical training center; Improve the (including investigation, the construction is Liujcouh Liuzhou existing car beauty repair integration 44 proposed KFW Category C in the original campus, the Cuzmuz Couyih city training room function; Improve loan of 25 million acquired land is reserved for the Yozyau agricultural mechanization operation yuan , supporting school, and there is no LA and and maintenance training base of level funds of school of HD impact. 2 maintenance module, vehicle 282,600 yuan) electrical vehicle maintenance module, automotive engine troubleshooting module, car parts detection module, car engine disassemble module,

30

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) automobile chassis and transmission disassembling modules, and on the base of new energy between the training room, car marketing training room 1;1 newly built 3D tour guide training room specializing in tourism service and management; 1 newly built financial affairs training room for financial affairs major;1 newly built practical training room for network construction and application of computer network technology; New social culture and art (preschool education direction) professional kindergarten simulation classroom, multi-functional vocal music training room each 1.Information construction mainly improves the information security of campus network and creates a smart campus environment by improving software and hardware configuration. Teacher training is to improve the overall quality of the teaching staff by means of practical training in enterprises and training in developed areas.

31

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) The comprehensive building project including three supplies and one The school obtained the land leveling and the main construction, certificate in 2014, after covering an area of 1,074 m2, with a A total investment investigation, the construction is secondary Wuzhou 45 total construction area of 7,678 m2. It of 20 million yuan, Category C in the original campus, the specialized city has seven floors, with a height of 4.5 m from KFW loan. acquired land is reserved for the school for each floor and 3.6 m high from the school, and there is no LA and second to seventh floors. The functions HD impact. are set as office and training. 1. The new construction of a new culture and sports and skill training center, a total construction area of 9,556 m2, 2 layer. The main contents of The school obtained the land construction include civil engineering, certificate in 2009, after Beibuwan decoration engineering, equipment A total investment investigation, the construction is vocational Qinzhou procurement, water supply and 46 of 28.95 million Category C in the original campus, the technical city drainage engineering, electrical yuan; acquired land is reserved for the institute engineering and outdoor water supply school, and there is no LA and and drainage and other infrastructure HD impact. engineering within the scope, procurement of equipment, etc. 2. culture and sports and skills training center supporting equipment 1. It is planned to build a teaching A total investment The school obtained the land Lingshan county building, covering an area of 701 m2, of 26 million yuan certificate in 2003, after vocational Lingshan 47 with a total construction area of 3,505.5 (The financial loan Category C investigation, the construction is technical county m2, with five floors on the ground, amount is 20 in the original campus, the institute frame structure. million yuan and acquired land is reserved for the

32

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) 2. It is planned to build a student the self-raised school, and there is no LA and dormitory building, covering an area of supporting fund is HD impact. 2 576 m with a total construction area of 6 million yuan) 2,880 m2, with five floors on the ground, frame structure. 3. It is planned to build a publicity hall for enterprises recruitment, covering an area of 2,400 m2, with a total construction area of 2,400 m2, a floor height of 18 m, and a frame + steel structure. The school obtained the land certificate in 2009, after city investigation, the construction is Guigang Civil engineering projects of 8,000 m2, A total investment 48 vocational Category C in the original campus, the city covers an area of 1,140 m2 of 22 million yuan education center acquired land is reserved for the school, and there is no LA and HD impact. 1. Plan to build a virtual and real integrated training base for nursing major (equipment procurement); Equipment procurement, no civil Baise ethnic 49 Baise city 2. Smart campus construction 25 million yuan Category C engineering, and there is no LA health school (equipment procurement); and HD impact. 3. Faculty quality improvement project (training) Comprehensive building project The school obtained the land LaiBin 27.5 million yuan, 50 Laibin city construction, frame structure, the Category C certificate in 2013, after Vocational including the self- occupied land area of construction is investigation, the construction is

33

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) Education about 1,200 m2, the building is 10 raised funds is 2.5 in the original campus, the Center School floors, its area is 10,000 m2. million yuan. acquired land is reserved for the school, and there is no LA and HD impact. A total area of the planning land is 235,542.27 m2 (Total: 353.313 mu), The school obtained the land construction area of planning is The investment is Guangxi certificate in 1993, after 216,732.13 m2, according to the unified 35 million yuan (25 Technician investigation, the construction is Liuzhou planning, phased implementation, the million yuan for 51 College of Category C in the original campus, the city construction area of project (phase I) KFW / 10 million Machinery & acquired land is reserved for the is 153,965 m2, the construction area of yuan for the Electricity school, and there is no LA and numerical control technology center college) HD impact. building in the first phase of the project is 13,838.29 m2. The school obtained the land certificate in 2010, after Nanning Guangxi Traffic A student apartment building with a 30 million yuan(20 investigation, the construction is city of 52 Technician total area of 12,000 m2 will be million yuan/10 Category C in the original campus, the Guangxi College constructed. and will add 1,700 beds. million yuan) acquired land is reserved for the province school, and there is no LA and HD impact. The project will build a new teaching and common building with a six-layer After investigation, the GuangXi frame structure, the total area of 50 million yuan(25 construction is in the original Shangmao Nanning 53 building is 20,550 m2, the area of million yuan/25 Category C campus, the acquired land is Senior Technical city occupied land is 3,500 m2. Planning million yuan) reserved for the school, and School 100 integrated classroom, 4 ladder there is no LA and HD impact. teaching buildings, 10 teacher's

34

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) lounges with supporting elevator room and toilet. 1. A newly training comprehensive building will be built in the Hechi city vocational education center school, covering an area of 24,918.45 m2, the ground area is 23,851.95 m2, the underground area is 1,066.5 m2, the land area is 1,862.76 m2. The main content of construction includes civil engineering and supporting construction electrical engineering, The school obtained the land 110.7314 million water supply and drainage certificate in 2014, after Hechi city yuan (ADB: 25 engineering, fire production investigation, the construction is vocational million yuan/ local 54 Hechi city engineering, ventilation engineering, Category C in the original campus, the education center supporting funds: weak current engineering, acquired land is reserved for the school 85.7314 million communication engineering, etc. school, and there is no LA and yuan) 2. A newly training comprehensive HD impact. building will be built, the a total construction area of 29,214.02 m2,and a training building covers an area of 19,250.02 m2;2 nursing buildings, and each nursing building covers an area of 9,964 m2. According to the actual situation, the original two nursing buildings were combined into one building, with a construction area of

35

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) 10,401.85 m2, which covers total land area of 1,654.75 m2. 1. Improving the basic ability of running a school 2. Construction of campus culture 3. Special promotion of educational The school obtained the land research and reform certificate in 1979, after 4. Research and construction of investigation, the construction is GuangxI Wuzi Nanning 55 linkage between middle and higher 30 million yuan. Category C in the original campus, the School city vocational education acquired land is reserved for the 5. Teaching resource construction school, and there is no LA and 6. Construction for professional HD impact. training room 7. Campus intelligent informatization 8. Educational propaganda The project will Cover an area of 683.6 m2, the original building (old hall) will be The investment of demolished with an area of 711.65 m2, this project is and a new multipurpose building of estimated to be The school obtained the land 6,874.29 m2 will be built. The ground 32.71 million yuan, certificate in 2003, after Guangxi floor will be ten floors, the basement including ADB loan investigation, the construction is Mechanical and Nanning 56 will be one floor, and the first ground for 30 million yuan, Category C in the original campus, the Electrical City floor is a multipurpose hall, conference and 2.71million acquired land is reserved for the Industry School room, school history hall, and the yuan will be raised school, and there is no LA and second floor for the Youth League and by local HD impact. community activities center, the third construction floor is the conference room and the department. teacher's office, the fourth floor is the

36

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) conference room and the administrative office; the fifth floor is the classroom, and the sixth to tenth floors are the training room and the integrated classroom. 1. A newly teaching and training comprehensive building will be built, covering an area of 1,500 m2, and a The investment of After investigation, the Guangxi Aquatic total construction area of 10,000 m2, this project is construction is in the original Animal Nanning 57 supporting with outdoor greening, estimated to be 30 Category C campus, the acquired land is Husbandry City landscape, road hardening and million yuan, from reserved for the school, and School hydropower facilities. ADB loan. there is no LA and HD impact. 2.Construction of campus informatization. The school obtained the land Which covers with total land area of certificate in 2001, after Guidong Health 2,500 m2,of which the Building will Special central investigation, the construction is 58 Secondary Hezhou city cover an area of 1,500 m2. Total funds and self- Category C in the original campus, the School construction area for 12,100 m2,with 6 raised funds. acquired land is reserved for the floors. school, and there is no LA and HD impact. The school obtained the land certificate in 1985, after Jingxi Jingxi city vocational and technical The total investigation, the construction is Vocational and school, comprehensive training 59 Baise city investment is about Category C in the original campus, the Technical building project building area 6,868 m2, 21.11 million yuan. acquired land is reserved for the School 7 floors above ground school, and there is no LA and HD impact.

37

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) The school obtained the land certificate in 2010, after Chongzuo City The total land area of the building is 3 investigation, the construction is Vocational and Chongzuo mu, and the building area is 7,950 m2, 20 million yuan of 60 Category C in the original campus, the Technical city which is four-floor frame structure KFW loan acquired land is reserved for the School above the land. school, and there is no LA and HD impact.

The school obtained the land Proposed construction of a six-story Guangxi certificate in 2013, in Nanning comprehensive training building, the Industrial and Nanning 25 million yuan Wuming district to build a new 61 total construction area of about 7,200 Undetermined Commercial city (ADB) campus, need to acquire land, m2, covers an area of about 600 m2; It School land planning procedures are has 60 multifunctional classrooms being handled. integrating theory and reality. Guangxi Quality The construction content has not been Technology Nanning 62 determined and relevant materials Undetermined For screening Engineering city have not been submitted School Undetermined The construction content has not been Nanning Sports Nanning 63 determined and relevant materials Undetermined For screening School city have not been submitted Pingnan County Secondary Vocational and Technical school integrated Pingnan County building project, the main construction Secondary Pingnan 64 of teaching and training rooms 9,095 20 million yuan Undetermined For screening Vocational and County m2, construction content including civil Technical school engineering, decoration, water supply and drainage, electrical engineering.

38

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) The planning construction net area for the new campus is 731,857 m2 (about 1,098 mu), campus net area is 55,4813 m2 (about 832 mu). Conduct site Land area for the Construction of visits, collect Phase I will be 406,008 m2 (about 609 relevant data mu), the construction net area is such as 358,895 m2 (about 538 mu); reserved compensation development land is 325,864 m2 (about contracts for LA 489 mu); total building area is 286 960 Land acquisition of 832 mu has and HD, m2. The construction includes: public been completed in 2019. No payment teaching building for 2,967 m2, Guangxi specific data of the affected vouchers, etc., teaching building for 14,454 m2, Vocational population, as well as payment and check Nanning comprehensive training building for Total 1,535 million 65 College of Category B vouchers for land acquisition, whether the city 3,398 m2, library for 6,067 m2, gym for yuan International have been obtained. affected persons 5,615 m2, students and staff activity Business The project acquired farmland in have any center for 1,696 m2, assembly hall for Zhentang Village of Ningwu. unresolved 2,720 m2, student dormitory for 21,735 More screening is needed. grievances, and m2, canteen for 2,281 m2, dormitory for whether there single staff for 1,053 m2, are legal comprehensive office support building disputes over for 3,054 m2, teaching management the land or building (administration building) for inheritance 1,909 m2, basement for 12,000 m2, acquired. green building incremental investment for 286,960 m2, seismic stabilizer bracket for 286,960 m2, electric transformer and distribution for

39

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) 286,960 m2, 12 elevator, outdoor supporting facilities for 288,481 m2. Construction area for graphic design information center is 25,561.91 m2, Total investment is covering an area of 3,028.5 m2; 130.85 million The acquisition of agricultural Guangxi construction area for accounting and yuan. land has been completed, Vocational finance department is 16,032.71 m2, Nanning ADB loan for 65 covering an area of 429.62 mu. 66 College of covering an area of 2,973.12 m2; Category B City million The specific data of the APs and Economy and construction area for trading and yuan/supporting the payment voucher for LA Trade management, tourism and foreign funds for 65.85 have not been obtained yet. language is 14,392.97 m2, covering an million yuan. area of 2600.72m2. Total 55,987.59 m2 of construction area. 1. Building of 2# opening teaching and training center covers an area of According to the investigation, 1,006.51 m2, the construction area is the school has completed the LA 5,266.37 m2, cost 14.16 million yuan; in 2017, acquired 178 mu of 2. Building of the information center unused land from the village and 2# distance education center Guangxi Radio collective, and has completed Nanning covers an area of 2,775 m2, the 67 and TV 58.10 million yuan Category B the compensation of LA and City construction area is 11,524.5 m2, cost University resettlement. And has obtained 33.43 million yuan. the land certificate in 2017. 3. Training for teachers (training for There are no remaining team management, professional problems regarding teacher training, including outdoor resettlement. training, indoors training and graduate trainee).

40

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) 4. Construction of professional (talent training program, curriculum system, curriculum construction). Construction of training room (purchase and installation of equipment and decoration of the training room) Primary canteen in new campus Planned land area of the new campus From 2015 to 2016, land and is 391,721 m2 (about 587.58 m2). acquisition was completed with comprehensive Including the construction area for 587.58 mu, and compensation teaching Nanning 18,800 m2 of primary canteen and Total invest 118.34 68 Category B has been completed. Specific building project City covers an area of 4,320 m2. The million yuan. data on the APs and payment of Guangxi comprehensive teaching building vouchers for land compensation Electrical covers an area of 2,293 m2, and the were not immediately available. Polytechnic construction area is 2,0645 m2. Institute The school completed the acquisition of 64.15 mu of collective agricultural land in A new training building, covering an 20 million yuan 2018. Compensation and Heng area of 1,510 m2, the total construction 69 vocational ( KFW 20 million Category B resettlement had been county area of 7,640 m2, five floors above education center yuan completed. Specific data on the ground, frame structure. APs and payment vouchers for land compensation were not immediately available. 1.“KFW Building” project and “KFW” The school has completed LA of city A total investment 70 Cenxi city cultural square construction project Category B 188 mu, all belonging to the secondary of 20,395,800 yuan cover a total area of 4,088.00 m2 mountain land, has completed

41

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) specialized 2. The campus culture square covers the compensation and the school an area of 1,500 m2 resettlement, and the land certificate was obtained in 2010. The acquisition of collective agricultural land and state-

owned agricultural land of It covers an area of 229,770 m2 and a 344.66 mu had been completed. Bobai county Bobai construction area of 152,915 m2. It completed the compensation secondary county mainly builds teaching buildings, book 71 398.67 million yuan Category B and resettlement. Specific data specialized education reading rooms, training buildings, on the APs and payment school park student dormitories, canteens, office vouchers for land compensation rooms, sports fields, sport ground with were not immediately available. roof, etc. The school received a land ownership certificate in 2019. Land acquisition of 4.12 mu has been completed. The It is proposed to build a comprehensive compensation and the teaching building with 6 floors above resettlement had been Zhaoping Bank loan ground and 1 floor underground, with a completed. Specific data on the 72 vocational Hezhou city investment of 20 Category B planned land area of 4,442.42 m2, floor APs and payment vouchers for education center million yuan space of 1,540.85 m2, and a total land compensation were not construction area of 11,658.66 m2. immediately available. The school received the land ownership certificate in 2019. Guangxi The project plans Proposed to build a new Constructing 2 student dormitory University of Nanning to invest 41.98 campus, it has completed the 73 buildings, which covers an area of Category B Chinese city million yuan, apply acquisition of agricultural land, 3,664.14 m2. Medicine for a cofinancing land acquisition area of 616 mu,

42

Investment amount ten Project Name of thousand/CNY Implementation No. Location Proposed Project Content Impact LA and HD Situation School (ADB/local Status Category supporting funds) loan of 30 million and has completed land yuan from KFW acquisition compensation. And bank, and the there is no HD impact. remaining 11.98 million yuan will be raised by the school through other ways. The school obtained the land certificate in 2014. 21.75 mu of land has been completed. The secondary The stadium covers an area of 6,350 74 Beihai City 90.57 million yuan Category B specific data of the APs and the vocational and m2 with a building area of 12,960 m2. payment voucher of land technical school compensation have not been obtained yet. ADB = Asian Development Bank, DDR = due diligence report, GZAR = Guangxi Zhuang Autonomous Region, HD = house demolition, LA = land acquisition, m = meter, m2 = square meter, mu = Chinese unit of measurement (1 mu = 666.667 square meters) .

43

1.3 Scope of External Resettlement Monitoring and Evaluation

The objectives of M&E are to assess whether the LAR is implemented on schedule and within budget and whether the goals and principles of the resettlement framework

(RF) are achieved. Specifically, M&E will focus on the following aspects of the APs’ situation and the resettlement process.

• Social and economic situation prior to and after LA and/or resettlement;

• Timely disbursement of funds and compensation payments to APs;

• Measures taken to restore APs’ income/livelihoods;

• Functioning of the grievance redress mechanism (GRM);

• Social adaptability after resettlement, where required;

• Restoration of APs’ incomes/livelihood, including vulnerable groups;

• Special items related to the vulnerable groups;

• Condition and quality of land temporarily acquired when it is returned to the

original land users; and

• Living conditions and economic status of APs following resettlement in

comparison to the “without project” scenario.

M&E will include (i) the verification or establishment of a socioeconomic baseline of the APs prior to actual land acquisition, physical displacement/relocation, loss of assets or disruption of businesses (as relevant); (ii) verification of internal monitoring data and reports; (iii) the regular monitoring of their house demolition and displacement/relocation to new housing (as relevant) and adjustment during subproject implementation; and (iv) evaluation of their situation for a period of 2 years after land acquisition or house displacement (as relevant). In addition, qualitative and quantitative evaluation will be made on the sustainability of living conditions of APs.

Investigation will include consultations and observations with APs, implementing agencies, local officials, village leaders, as well as a quantitative sample survey of at least 20% of affected households. Focus group discussions will be conducted with male and female APs, vulnerable groups and others.

If the findings of the M&E indicate significant compliance gaps, the external

44

monitor will work with the GPMO to prepare a corrective action plan (CAP) in cooperation with the relevant stakeholders, to address pending issues. The external monitor will also monitor and report on the implementation of the CAP.

Table 1-2: Resettlement Monitoring and Evaluation Schedule

No. Resettlement report Time of survey Submission date 1 Semiannual monitoring 1 May 2019 July 2019 2 Semiannual monitoring 2 December 2019 January 2020 3 Semiannual monitoring 3 June 2020 July 2020 4 Semiannual monitoring 4 December 2020 January 2021 5 Semiannual monitoring 5 June 2021 July 2021 6 Semiannual monitoring 6 December 2021 January 2022 7 Resettlement Completion report December 2022 January 2023

This second M&E report for the period from June 2019 to December 2019, is based on field visits to the sub-project schools, consultations with the GPMO and communities in the vicinity of the sub-projects.

According to the field survey and consultations, by the end of October 2019, 30 of the

74 subproject schools had started construction. Independent resettlement consulting experts visited the site in mid-November 2019 and monitored the resettlement impacts of the 30 subprojects schools. According to the investigation, the 30 subproject schools under construction are classified as Category C, all of which are being built on the reserved land of the original campus without LA and HD impact. See Part 5 for detailed information on the land availability and requirements for the individual subprojects. This report only monitors the 30 subproject schools that have already started construction. Other schools are preparing for the preliminary work, so they are not monitored and will be covered as part of the subsequent monitoring visits.

45

Figure 1-1 Construction Site of Subproject School Being Constructed

46

2. Land Acquisition and Resettlement Impacts

This monitoring found that, based on the results of monitoring, consultations and land availability reviews of 30 subproject schools, these sub-projects do not involve the impact of LA or HD and are category C involuntary resettlement.

By the end of November 2019, construction of all 30 subproject schools has started.

The 30 subproject schools that have started the construction are all classified as category

C in terms of resettlement. They are all being built in the original campus of the school, which is reserved for school, and there is no LA and HD impact. See Table 2-1 for detailed classification and impact.

47

Table 2-1: 30 Resettlement Impact and Category of Schools of Subproject under Construction—Screening Table (Draft) Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) 1. Civil project is a construction content of the new campus The new campus has completed extension project. Including NO.1 LA and HD in 2017. As Guilin to NO.4 Training Center, Center University of Aerospace of Students Innovation and Technology participates the Entrepreneurship as well as the Guangxi reginal cooperation and Comprehensive Gymnasium. The integration promotion project total construction area is (project no: 50050-004), and 44,376.93 m2 and covers an area DDR has been prepared for the of 14,890 m2. Guilin 205 million yuan (130 newly campus in 2017. 2. Maintenance and renovation University of million yuan from ADB According to the conclusion of 1 Guilin City project. The estimated cost of the Category C Not applicable Aerospace and 75 million yuan DDR, land acquisition maintenance and renovation Technology supporting funds) compensation and resettlement project is 30 million yuan and 20 of demolition have been million yuan from ADB loan will be completed, the land certificate planned to put into use in 2019. has been obtained in 2018, there 3. Balance Payment of the is no remaining problems. Construction. Balance payment of The old campus obtained the apartment buildings No.2, 5 and 6 land certificate in 2004, in the south campus is expected According to the investigation, to be paid with 15 million yuan, there is no remaining problems. and it is planned to use loans all from ADB. 1. The main content of the project The school obtained the land Guilin is a teaching facility construction certificated in 2004 and the 2 Tourism Guilin City project named "college students 133.88 million yuan Category C construction contents are Not applicable College physical education teaching building in the original campus, center", in addition to the the acquired land is reserved for

48

Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) construction installation project, the school, and there is no LA equipment purchases and and HD impact. supporting municipal facilities. The main body adopts frame structure, and the building has two floors. The construction area is about 18,000 m2. 2. The main content of construction including a teaching facility construction named "Bagui cuisine culture experience center" and renovation of the original training center (Hotel Training Center). 3. The content of the Talent Project Plan including introduction of high-level talents, teacher training and promotion. 4. The contents of the International Cooperation Projects including consulting fee and certification fee, OLF training fee, teaching fee and construction of ASEAN tourism vocational service platform. 1 Comprehensive teaching The school completed the land building No.7 and sports facilities Yulin Normal Investment amount: acquisition in 2009 and the land 3 Yulin city construction project. The Category C Not applicable University 147.98 million yuan resettlement compensation, and construction area of No.7 obtained the land certificate in comprehensive teaching building

49

Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) is 25,000 m2; a standard 400-m 2014, there is no remaining ground track field with 3,000 m2 problems. platform and audience area; road, According to the investigation, power, water supply, sewage and the construction is in the original greening will be also equipped as campus, the acquired land is well as the pavement of Yulan reserved for the school, and Lake, Qingshui Platform and there is no LA and HD impact. Square of Yulan Lake. 2. Basic laboratory renovation and upgrading project (including experimental instruments, equipment and software systems). 3. Construction of Information Center (including cloud center, servers, switches and other basic equipment). 4. Supporting facilities of dormitory No.7 and No.8 (including bed, multifunction desk, chair and air condition and so on). The total construction area is Guangxi The school obtained the land 66,354.36 m2 and covering an Transport certificate in 2003. According to area of 17,834.95 m2. including Vocational 227.54 million yuan the investigation, the Nanning newly built cars and track training 4 and Technical (70.99 million yuan Category C construction is in the original Not applicable city buildings for 27,215.36 m2, road College of /156.55 million yuan) campus, the acquired land is and bridge training buildings for Communicati reserved for the school, and 39,139 m2. Equipped with parking ons there is no LA and HD impact. lot, road and greening.

50

Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) According to the investigation, the land of original campus was stated-owned unused land and allocated to the government of Wuming county, GZAR on January 8, 2003. Since the The total building covering an government has not yet area of 14,100 m2 and developed and utilized the land, 114.79 million yuan (ADB Guangxi construction area is 51,025 m2 the surrounding farmers have and KfW Loan for 20 Vocational Nanning (including 29,584 m2 construction reclaimed and cultivated during 5 million yuan/supporting Category C Not applicable College of City area of the intelligent this period. In 2012, the funds for 94.79 million Industrial manufacturing training base of government of Wuming county yuan) Guangxi Vocational College of has made green crop Industrial) compensation to the farmers who cultivated the land. After completing the green crop compensation, the land has been allocated to Guangxi Vocational College of Industrial. There are no remaining issues. Total construction is 34,780 m2 According to the investigation, (including office building for the construction contents are in 10,837.1 m2, basement for the original campus, the acquired Guangxi 3,667.9 m2, information center for land is reserved for the school, Vocational Nanning 2,127.9 m2, library for 18,147 m2), 6 147 million yuan Category C and there is no LA and HD Not applicable College of City covering an area of 5,218.8 m2. impact. The school obtained the Construction The building is frame-shear wall land certificate in 2016. structure. The construction According to the investigation, content includes building, there is no remaining problems. structure, water supply, electric,

51

Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) heating, air condition, fire control and environment protection. The construction for Phase I covers an area of 477,102.39 m2 (about 715.65 mu). 427,028.8 m2 (about 640.54 mu) for net area. The construction content includes teaching and training building According to the investigation, (public teaching room, teaching the land occupied by the new and training room and office Total investment is campus of Guangxi College for Guangxi room), library, indoor gym, office Nanning 1,733.21 million yuan Preschool Education is state- College for room, assembly hall and students 7 Educationa (ADB loan 144 million Category C owned land, and the allocation Not applicable Preschool activity room, student dormitory, l Zone yuan/supporting funds for procedures of state-owned land Education dormitory for single staff, canteen, 1,589.21 million yuan) have been completed, the land office supporting room and certificate is being applied now. attachment room and so on. As There is no impact of LA and HD. well as the supporting infrastructure such as intelligent system, playground, water supply, electric supply, front gate, wall, road, greening and viewing, water and square. 1. Building a 15-floor vocational The school obtained the land training building. Covering an certificate in 2016. there are no area of 2,520 m2 and the remaining problems. According Hechi construction is 30,000 m2. 8 Yizhou City 82.39 million yuan Category C to the investigation, the Not applicable University 2. Demolished the old dangerous construction is carried out on the building and rebuilt a 7-floor site where 2 old dangerous student dormitory. The building training buildings in the original covers an area of 3,926.30 m2

52

Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) and the construction area is campus are demolished. There is 10,409.75 m2. no impact of LA and HD. 3. 15,000 m2 of the surface of the teaching building and 3,000 m2 environmental maintenance; 19,500 m2 of artificial grassland and runway renovation project; 4,500 m2 of roof renovation on gym; 800 m2 for the well lid of the ditch in school as well 850 m2 of the road widening; 500 m2 single floor steel-framed training room for art and design; 400 m2 renovation of the art and design exhibition hall; circuit expansion 1250KVA box transformer and laying 10KV cable. 1. Civil of the comprehensive experimental building (technical building). The school obtained the land 2. Reeducation and training certificate in 2003. According to center the investigation, the Wuzhou Wuzhou 3. Comprehensive practical 9 105.5 million yuan Category C construction are in the original Not applicable University City training platform for economic and campus, the acquired land is management vocational reserved for the school, and education. there is no LA and HD impact. 4. Intelligent control and manufacturing integrated training platform

53

Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) 5. Comprehensive training room for teacher’s educational ability 6. Intelligent renovation of library. 7. Construction of teaching staff The school obtained the land Guangxi certificate in 2003. According to Eco- Construction of No.3 and No.4 the investigation, the engineering Liuzhou student dormitory, a cooking Total investment is 10 Category C construction is in the original Not applicable Vocational city practice building, and a library, a 176.63million yuan campus, the acquired land is and Technical total of 45,313.54 m2. reserved for the school, and College there is no LA and HD impact. The school obtained the land Total estimated certificate in 2003, there is no Guangxi 28116.91 m2of the construction of investment of the project remaining problems. According Finance Nanning library, including 24,500.72 m2 is 97.61 million. The loan to the investigation, the 11 Vocational Category C Not applicable City above ground and 3,616.2 m2 is 60 million yuan, with construction is in the original and Technical underground. supporting facilities of campus, the acquired land is School 37.61 million yuan. reserved for the school, and there is no LA and HD impact. Two comprehensive buildings with the function of practical training and teaching and student The school obtained the land accommodation will be built, certificate in 2005. According to Guangxi covering an area of 937.04 m2, the investigation, the Liuzhou 12 Business with a total construction area of 25 million yuan Category C construction is in the original Not applicable city School 6,680.2 m2 (1,874.08 m2 for campus, the acquired land is practical training and teaching reserved for the school, and and 4,806.12 m2 for student there is no LA and HD impact. accommodation). A dormitory building, covering an area of

54

Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) 383.81 m2, building area of 2,363.06 m2,, at the same time supporting automobile marketing training equipment and corresponding facilities of student apartments. 1. An investment of 18.2026 million yuan is invested in the construction of a seven-story high building (including empty space), 2# teaching building in the campus with an area of 1,223.62 m2 and a total construction area of 9,000 m2. 2. An investment of 3.5 million The school obtained the land yuan was used to purchase A total estimated certificate in 2011. According to teaching equipment and facilities, investment of 21.7026 Guangxi Yulin the investigation, the including: million yuan,including: 13 Agricultural Yulin city Category C construction is in the original Not applicable ( 1 ) An investment of 1.674 proposed KFW loan of 20 School campus, the acquired land is million yuan was used to million-yuan, self-raised reserved for the school, and purchase 54 sets of multimedia funds of 1.70 million yuan. there is no LA and HD impact. equipment for classroom of 2# teaching building. (2)An investment of 0.48 million yuan was used to purchase 2,000 sets of desks and chairs for 2# teaching building classroom. ( 3 ) An investment of 1.346 million yuan was used to purchase a batch of new energy

55

Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) vehicle equipment, and build three training rooms, including the training room for basic technology of new energy vehicles, the training room for integration of electricians and electronics of new energy vehicles, and the training room for new energy vehicles. The project covers an area of 2,133.40 m2, with a total construction area of 15,128.01 m2, including an above-ground construction area of 11,148.09 m2. There are six floors above the ground, one floor underground. The basement is 4.5 m high and The school obtained the land Liuzhou city the first floor is 4.2 m high. The A total investment of certificate in 2010. According to Luzhai basement is mainly equipped with 37.89 million yuan (20 the investigation, the Luzhai 14 vocational motor vehicle parking space, fire million yuan from Category C construction is in the original Not applicable county education pool, water pump room, generator ADB/supporting funds of campus, the acquired land is center room and power distribution 14.89 million yuan) reserved for the school, and room; The first to fifth floors are there is no LA and HD impact. mainly equipped with training rooms, preparation rooms, toilets, guard rooms, boiling water rooms, lecture halls and reading rooms. There are offices, toilets, guard rooms and boiling water rooms on the sixth floor.

56

Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) 1. Two (1#, 4#) student dormitory building construction, the total construction area of 3,817.82 m2, including: 1# student dormitory, the floor area of 316.34 m2, a total of five floors, the construction area of 1,637.98 m2; 4# student The school obtained the land dormitory, the building covers an certificate in 2015. According to area of 326.62 m2, the design of A total investment of 21.5 Yulin No.1 the investigation, the the empty space, a total of six million yuan ( ADB Secondary construction contents are in the 15 Yulin city floors, the construction area of investment of 20 million Category C Not applicable Vocational original campus, the acquired 2,179.84 m2; yuan/self-raised funds of School land is reserved for the school, 2. Construction of intelligence 1.5 million yuan) and there is no LA and HD campus impact. 3. Purchase of professional training equipment for Chinese cuisine and western cuisine 4. Logistics service and management professional training base construction 5. Book purchase student dormitory project of According to the investigation, campus expansion project covers Rong county the subproject construction is in an area of 1,221.26 m2; e- secondary Rong ADB investment of 29.79 the original campus, the acquired 16 commerce training building Category C Not applicable Vocational county million yuan land is reserved for the school, project of campus expansion school and there is no LA and HD project, covers an area of 1,275 impact. m2 Hechi City The new construction for training Total investment: 29.24 According to the investigation, 17 Hechi city Category C Not applicable Health School building of Hechi City Health million yuan/25 million the new training building of Hechi

57

Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) School covers an area of 1,186 yuan (ADB) / 4.24 million City Health School will demolish m2. the demolished old auditorium yuan(Local government the school’s old auditorium and in this school is used for supporting funds) build it on the site. There is no LA construction, which does not and HD impact. involve land acquisition. 1. the area of occupied land of vocational education center fusion education complex building in Hechi city is 810 m2, with a The school obtained the land total construction area of 7,290 Hechi certificate in 2014. According to m2 Yizhou 20 million yuan(ADB: 20 the investigation, the 2. the project of production- 18 Vocational Hechi city million yuan/ Local Category C construction is in the original Not applicable education integration information Education supporting funds) campus, the acquired land is equipment procurement and Center reserved for the school, and installation for Yizhou district there is no LA and HD impact. vocational education center in Hechi city, is mainly information equipment procurement and installation. The student apartment for high- skilled talents is located in the east of the middle of the campus, The total investment of The school obtained the land with a total construction area of the project is 48.81 million certificate in 2014. According to Guangxi 19,304.25 m2. The area of yuan (Germany KFW the investigation, the Industrial Nanning 19 occupied land for building is bank is 20 million yuan, Category C construction is in the original Not applicable Technician city 1,144.67 m2, it is high-rise and the school raised campus, the acquired land is College buildings with 17 floors. The 28.81 million yuan by reserved for the school, and building is used for the student itself). there is no LA and HD impact. dormitory and supporting rooms. The main contents of construction

58

Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) include construction engineering, decoration engineering, water supply and drainage engineering, electrical engineering, heating engineering and general level related supporting engineering A student dorm building with a six- It had completed the land layer frame structure will be acquisition in 2014 and obtained constructed in this project. The land certificate in 2015. 139.98 height of building is 25.8 m, the mu land has been acquired The Second total area of building is 10,322.2 which concludes cultivated land Light Industry m2, the occupied land of building Nanning A total investment: 28.11 of 19.89 mu, garden plot of 87.88 20 Technical is 3,247.86 m2. There will be 227 Category C Not applicable city million yuan mu and forestland of 32.21 mu. School of standard apartment dormitories After investigation, LA work had Guangxi (8 persons/room), 2 accessible been completed, and its dormitories (2 persons/room), 5 compensation had been public laundry rooms and 1 completed in 2014. There are no management room in this new remaining issues. building. The project will build a training Guangxi yulin comprehensive building with 8 technician Total investment: 29.03 According to investigation, the floors and public auxiliary college million yuan (KFW): 25 construction is in the original facilities, the area of construction 21 ( Guangxi Yulin City million yuan, the Category C campus of the school, and the Not applicable planning land is 3,991 m2, the yulin senior supporting funds: 4.03 land was reserved for the school. area of planning occupied land is technical million yuan) There is no impact of LA and HD. 1,056.69 m2, total area of building school) is 8,904.00 m2. Liuzhou NO.2 1. Build a new integrated teaching The school obtained the land Liuzhou Total investment: 61.73 22 Vocational building, and at the same time, Category C certificate in 2010. The Not applicable city million yuan School build supporting power supply construction is in the original

59

Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) and distribution, water supply and campus, the acquired land is drainage, and other ancillary reserved for the school, and facilities. there is no LA and HD impact. 2. The project will cover an area of 2,713 m2, the building covers an area of 13,738 m2. The main content of construction is to build a 4# training school and water supply and drainage and other ancillary facilities. 1. A new student dormitory building, 5-floor frame structure building, covering an area of 881.29 m2, a total construction area of 4,524.55 m2 The school obtained the land 2. Construct a one-floor steel certificate in 2008. According to QuanZhou frame structures mechanics the investigation, the vocational & Quanzhou 23 training workshop, the building 22 million yuan Category C construction is in the original Not applicable technical county covers an area of 1,600 m2, with a campus, the acquired land is schools total construction area of 1,600 reserved for the school, and m2 there is no LA and HD impact. 3. Information teaching equipment 4. Upgrade and replace training equipment A newly training comprehensive The total investment of According to the investigation, Guiping city building will be built, covering an the project is 20 million the construction is in the original NO.1 Guiping 24 area of 800 m2, the ground floor yuan, and KFW loan of 20 Category C campus, the acquired land is Not applicable secondary city will be 13 floors, a total million yuan (about €2.75 reserved for the school, and vocational construction area of 9,812 m2, million) there is no LA and HD impact.

60

Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) and technical supporting with related ancillary school projects. The main construction content is civil engineering, water supply and drainage, fire control, electrical, lightning protection and other projects. 1. Teaching comprehensive building: land area: 1,130 m2,the total area of building: 5,400m2, the height: 18 m(5 ground floors) 2. Counseling center building covers an area of 362 m2, including group activity area, sand table game area, music relaxation area. The school obtained the land 3. Computer application certificate in 2005. According to Guilin tourism professional training base:3 the investigation, the vocational training room, including:(a) 1 construction is conducted on the 25 secondary Guilin city 25.68 million yuan Category C Not applicable computer professional animation site where the training building in professional graphics processing room (55 the original campus is school desk computers) covers an area demolished, and there is no LA of 102 m2; (b) 1 Network and HD impact. comprehensive wiring competition to upgrade the training room, located in training building 4# 4-1 room, covering an area of 102 m2; (c) PDS engineering technology certification training room (Network integrated wiring

61

Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) engineering certification training room), covering an area of 102 m2. In addition, Including training equipment procurement and training room decoration. 4. Stadium stage construction project: which covers an area of 200 m2. 5. The renovation project of the lecture theatre (multifunction hall): located in 2 floors of 7# in school,which covers an area of 404 m2, including sound amplification system, LED and other supporting facilities and equipment. 6. Renovation for track and field plastic ring runway: Refurbishment for a plastic ring track at the standard of 8 tracks,400m, including a mixed plastic track: 8,148 m2; 30mm reinforced non-filling artificial turf: 7,775.6 m2. 7. Rebuilding the dining room: covering an area of 1125 m2, the repast area is 1,406 m2. Including the demolition and reconstruction of the old operation room, internal washing and elimination facilities

62

Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) and equipment in the operation room, water supply and drainage lines, the ground will be changed to anti-skid environmentally friendly glue ground, decorative partition, new add dining table cover, healthy diet culture canteen management materials. 1. Power electrical renovation 2. School teaching, work area of smart water and electricity meters and supporting facilities 3. Energy-saving hot water supply system for student dormitory The school obtained the land 4. Indoor and outdoor lighting certificate in 2010. According to lamps and lanterns Liuzhou No.1 the investigation, the transformation Vocational construction contents are in the 26 liuzhou city 5. Construction for Integrated 25 million yuan Category C Not applicable and Technical original campus, the acquired business information system School land is reserved for the school, 6. Construction for financial and there is no LA and HD management internal control impact. system 7. Introduction of western food courses and vocational qualification certificates 8. Constructing new student dormitory buildings The school obtained the land Guangxi Qinzhou 1. The project will construct a 27 25 million yuan Category C certificate in 2002. According to Not applicable QinZhou city teaching building with 5 ground the investigation, the

63

Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) Agricultural floors, and the building covers an construction contents are in the School area of 2,822.7 m2 original campus, the acquired 2. The project will construct a land is reserved for the school, training student dormitory building and there is no LA and HD with 5 ground floors, and the impact. building covers an area of 3,500 m2. 3. Purchasing 10,000 books. 4. Purchasing information campus system, professional teaching resources, library digital management system and another digital platform. 5. Teacher training 6. Purchasing 100 computers Guangxi Wuzhou Business School proposes to build one Training Building, with 7 floors above ground and 1 underground The school obtained the land floor (for underground civil anti- The total investment certificate in 2011. According to Guangxi parking facilities). The building amount of 26.73 million investigation, the dilapidated old Wuzhou Wuzhou covers an area of 672.74 m2 and yuan, the ADB loan will be administrative office building in 28 Category C Not applicable Business city the total construction area is 25 million yuan, and the the original campus will be School 6,696.26 m2. The main school self-raised funds is demolished to build a training construction contents include civil 1.73 million yuan. building, and there is no LA and engineering, decoration works, HD impact. equipment and tools purchase, water supply and drainage engineering, electrical

64

Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) engineering, outdoor site hardening and greening, etc. 1. Sewage treatment center. 2. Sports center 3. No. 17 Teaching Building; newly build 1 teaching building, with 6 floors, and total construction area for 4,650 m2, including civil work and installation. 4. National Craft Inheritance and Innovation Training Building, with total of 2 floors, with total The school obtained the land construction area for 3,000 m2, certificate in 2012. According to Guangxi including civil work and the investigation, the Urban installation. construction contents are in the 29 Guilin City 30 million yuan Category C Not applicable Construction 5. UAV application technology original campus, the acquired School production and education land is reserved for the school, integration training base: (1) The and there is no LA and HD indoor training room covers an impact. area of about 300 m2, and the outdoor training field covers an area of about 5,000 m2. Including two major modules, the UAV production and teaching integration of basic skills training module and UAV production and education integration surveying and mapping industry application training module. (2) Basic training

65

Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) and cultural construction of the training room; (3) Related equipment and facilities. 6. National Crafts Inheritance and Innovation Training Room: Baogui concrete training ground, Fine woodworking training room, Carved porcelain training room 7. Student Comprehensive Literacy Center: including Mind Oxygen Bar, Music House, Glamour Body Shape Dance Room, Dance Club, Tea Art Club, Originality Club. 8. School–enterprise cooperation dual-sector construction (teacher training, corporate training), teaching ability improvement (information training, professional training, etc.), school executive training, school and enterprise teacher training (including foreign training), totaling of 70 person/times or more. Integrated teaching building Guangxi The school obtained the land construction project of Guangxi 55.32 million yuan (25 Nanning certificate in 2014. According to Nanning Nanning senior technical school, million yuan from ADB/ 30 Senior Category C the investigation, all subprojects Not applicable city main construction contents: 30.32 million yuan of local Technical are building in the original foundation pit support supporting funds) School campus, the acquired land is engineering, civil engineering,

66

Investment amount ten Name of thousand/CNY Project Impact Take Action No. Location Proposed Project Content LA and HD Situation School (ADB/local supporting Category and Measure funds) installation engineering, water reserved for the school, and supply and drainage engineering, there is no LA and electrical engineering, heating HD impact. engineering, elevator engineering, firefighting engineering, outdoor greening engineering, outdoor road engineering, sponge city, green building, etc. Construction scale: this project will build an integrated teaching building, with a total land area of 9,227.51 m2 (13.84 mu in total) and a building area of 19,054.06 m2, including an above-ground building area of 14,894.06 m2, including a building area of 14,591.70 m2 for practical training and a building area of 302.36 m2 for ancillary buildings. The underground building area is 4,160.00 m2. And supporting roads, greening, outdoor hydropower and other ancillary projects. ADB = Asian Development Bank, DDR = due diligence report, GZAR = Guangxi Zhuang Autonomous Region, HD = house demolition, LA = land acquisition, m = meter, m2 = square meter, mu = Chinese unit of measurement (1 mu = 666.667 square meters).

67

3. Public Participation and Grievance Redress Mechanism

In order to engage with the community and enhance public understanding on the

project and address the issues pertaining to resettlement, various types of APs and

other stakeholders will be consulted with LRB/HDO. According to the RF, the views

and attitudes of the stakeholders are collected during the negotiation, which will be

recorded in writing and explain how the concerns of the APs are addressed and dealt

with.

This monitoring found that there was no LA and HD impact on the 30 subproject

schools that had started construction, so no public participation and information

disclosure was carried out in each subproject school.

In the follow-up monitoring, the subproject schools with LA and HD impact will

carry out public participation activities with the APs through forum and interview and track the resettlement and income recovery situation of the APs. External M&E personnel go deep into the affected households, conduct face-to-face interview with them, understand the situation of the implementation of the APs. Household interviews are mainly to learn the social and economic condition and resettlement policy implementation of the affected individuals and households, all kinds of compensation standard and the situation and resettlement situation of production and living, information release and transfer, public participation, vulnerable groups protection measures, grievance and appeal and its condition and opinions and suggestions of the

APs on the implementation of resettlement. See table 3-1 for details.

Table 3-1 Project Public Participation and Information Disclosure Number of Public Participation No. Subproject Location Remarks during the Monitoring Period * Guilin University of 1 Guilin City Not Applicable Aerospace Technology 2 Guilin Tourism College Guilin City Not Applicable

3 Yulin Normal University Yulin city Not Applicable

68

Number of Public Participation No. Subproject Location Remarks during the Monitoring Period * Guangxi Vocational College 4 of Mechanical and Nanning City Electronical Technology Guangxi Vocational and 5 Nanning city Technical College Guangxi Transport Vocational 6 and Technical College of Nanning city Not Applicable Communications Guangxi Vocational College 7 Nanning City Not Applicable of Industrial Guangxi Vocational College 8 Nanning city of International Business Guangxi Vocational College 9 Nanning City of International Business Guangxi Vocational College 10 Nanning City Not Applicable of Construction Guangxi Vocational College 11 Nanning City of Economy and Trade

12 Guangxi Medical College Nanning City

Nanning Guangxi College for 13 Educational Not Applicable Preschool Education Zone Guangxi Radio and TV 14 Nanning City University Nanning Prefecture Education Chongzuo 15 College City Guangxi Science and 16 Laibin City Technology Normal University 17 Hechi University Yizhou City Not Applicable 18 Wuzhou University Wuzhou City Not Applicable 19 Hezhou University Hezhou City Guangxi Electrical 20 Nanning City Polytechnic Institute Guangxi 21 Eco-engineering Vocational Liuzhou city Not Applicable and Technical College Guangxi Finance Vocational 22 Nanning City Not Applicable and Technical School Guangxi Ji Dian Gong Cheng 23 Nanning city Xue Xiao Guangxi Institute Science and 24 Technology Nanning city School Guangxi Textile Industry 25 Nanning city School Guangxi Overseas Chinese 26 Nanning city School Guangxi nationality 27 secondary professional Nanning city school 69

Number of Public Participation No. Subproject Location Remarks during the Monitoring Period * 28 Guangxi Business School Liuzhou city Not Applicable Guangxiyoujiang Commercial 29 Baise city College for Nationalities Gvangjsih Liujcouh Cuzmuz 30 Liuzhou city Couyih Yozyau Guangxi Yulin Agricultural 31 Yulin city Not Applicable School Guangxi Industrial and 32 Nanning city Commercial School Heng county vocational 33 Heng county education center Liuzhou city Luzhai vocational Luzhai 34 Not Applicable education center county Cenxi city secondary 35 Cenxi city specialized school Cangwu county secondary 36 Wuzhou city specialized school Beibuwan vocational 37 Qinzhou city technical institute Lingshan county vocational Lingshan 38 technical institute county Guigang city vocational 39 Guigang city education center Yulin No.1 Secondary 40 Yulin city Not Applicable Vocational School Rong county secondary 41 Rong county Not Applicable Vocational school Bobai county Bobai county secondary 42 education specialized school park

43 Baise ethnic health school Baise city

Zhaoping vocational 44 Hezhou city education center 45 Hechi City Health School Hechi city Not Applicable Hechi Yizhou Vocational 46 Hechi city Not Applicable Education Center LaiBin Vocational Education 47 Laibin city Center School

Guangxi Industrial Technician 48 Nanning city Not Applicable College

Guangxi Technician College 49 Liuzhou city of Machinery & Electricity

Guangxi Traffic Technician 50 Nanning city College Guangxi Shangmao Senior 51 Nanning city Technical School

70

Number of Public Participation No. Subproject Location Remarks during the Monitoring Period * The Second Light Industry 52 Nanning city Not Applicable Technical School of Guangxi Guangxi yulin technician Not Applicable 53 college(Guangxi yulin senior Yulin City technical school) Liuzhou NO.2 Vocational Not Applicable 54 Liuzhou city School QuanZhou vocational & Quanzhou Not Applicable 55 technical schools county Guiping city NO.1 secondary Not Applicable 56 vocational and technical Guiping city school Hechi city vocational 57 Hechi city education center school Guilin tourism vocational Not Applicable 58 secondary professional Guilin city school Liuzhou No.1 Vocational and Not Applicable 59 liuzhou city Technical School GuangxI Wuzi 60 Nanning city School

Guangxi University of 61 Nanning city Chinese Medicine

Guangxi QinZhou Agricultural Not Applicable 62 Qinzhou city School Guangxi Wuzhou Business Not Applicable 63 Wuzhou city School Guangxi Urban Construction Not Applicable 64 Guilin City School Guangxi Mechanical and 65 Nanning City Electrical Industry School Guangxi Aquatic Animal 66 Nanning City Husbandry School Guidong Health Secondary 67 Hezhou city School Beihai secondary vocational 68 Beihai City and technical school Jingxi Vocational and 69 Baise city Technical School Guangxi Nanning Senior 70 Nanning city Not Applicable Technical School Guangxi Quality Technology Nanning city 71 Engineering School Nanning city 72 Nanning Sports School Pingnan County Secondary Pingnan 73 Vocational and Technical County school Chongzuo City Vocational Chongzuo 74 and Technical School city

71

There is an existing GRM as per government laws and regulations. However, it is

not part of the 1B4P and CARP documents. To improve the documents, grievances

will be properly documented during the process.

Existing Grievance Redress Mechanism. An existing GRM will receive, manage

and address any social issues which may arise due to the program. The purpose of

this procedure is to provide a mutually satisfactory means for rapid response to any

AP’s complaint, to avoid any likelihood of a complicated legal procedure. The detailed

procedures are as follows:

a. If any AP has grievance, he/she can voice his/her complaint to the village or

residential committee. The village or residential committee should keep records

and provide a reply to the AP within 10 working days.

b. If the AP is not satisfied with the reply, he/she can appeal to the township or

subdistrict government, which will take records, and provide a resolution to the

AP within 10 working days.

c. If the AP still does not accept the proposed resolution, then he/she can appeal

directly to the LRB/HDO, which should make a record of any appeal and

provide a resolution within 10 working days.

d. If the dispute still cannot be resolved, then the AP can appeal to the GPMO.

GPMO will facilitate and coordinate with local government. The GPMO is

responsible for keeping records of all appeals, and the resultant resolutions.

APs also have the right to use alternative channels at any time: (i) go through an administrative appeal according to the Administrative Procedure Law of People's

Republic of China (PRC), or (ii) go directly to the People’s Court.

GRM Documentation. The GRM tracking system by the GPMO will include the following elements: (i) tracking forms and procedures for gathering information from project personnel and complainant(s); (ii) regular updating of the GRM database by the Resettlement Coordinator in the GPMO; and (iii) a simple but effective filing system, so that data can be retrieved for reporting purposes.

GRM Processing Form (Table 3-2) and GRM Reporting Form (Table 3-3) will be

72

provided to the TVET School which will then be distributed to the concerned villages,

LRB and HDO during preparation of the 1B4P/CARP. The forms will be filled in by the

village committees/HRB/LDO to document and track the

grievances/complaints/requests received and resolutions made by their respective

offices. The TVET school will regularly obtain the information and input them in the

GRM tracking system of the GPMO.

Table 3-2 Project Appeal Table

Name Department

Time Place

Content:

Grievance Suggestion:

Claimant’s opinion on the handling Agree Disagree

Signature of Signature of claimant responsible personnel

Time Time

Claimant’s telephone number: Responsible personnel’s telephone number:

Alternatively, the aggrieved person(s) may submit a complaint to the ADB’s project

team to try to resolve the problem. If good faith efforts are still unsuccessful, they may

submit their complaint to ADB's Accountability Mechanism (2012). 1 The first step requires good faith efforts to resolve the problem with the ADB project team.

The resettlement external monitor will record any grievances and concerns raised by the affected households during monitoring. The concerns and issues raised, external monitor’s assessment of each case, and recommendations proposed by the external monitor will be reflected in the external monitoring report. See the feedback of the GRM of this monitoring in the table.

1 Accountability Mechanism. https://www.adb.org/site/accountability-mechanism/main 73

Table 3-3 The Feedback Form of Grievance Redress Mechanism Problem of No. Subproject Location Remarks identification Guilin University of 1 Guilin City Not Applicable Aerospace Technology 2 Guilin Tourism College Guilin City Not Applicable 3 Yulin Normal University Yulin city Not Applicable Guangxi Vocational College 4 of Mechanical and Nanning City Electronical Technology Guangxi Vocational and 5 Nanning city Technical College Guangxi Transport Vocational 6 and Technical College of Nanning city Not Applicable Communications Guangxi Vocational College 7 Nanning City Not Applicable of Industrial Guangxi Vocational College 8 Nanning city of International Business Guangxi Vocational College 9 Nanning City of International Business Guangxi Vocational College 10 Nanning City Not Applicable of Construction Guangxi Vocational College 11 Nanning City of Economy and Trade 12 Guangxi Medical College Nanning City Nanning Guangxi College for 13 Educational Not Applicable Preschool Education Zone Guangxi Radio and TV 14 Nanning City University Nanning Prefecture Education Chongzuo 15 College City Guangxi Science and 16 Laibin City Technology Normal University 17 Hechi University Yizhou City Not Applicable 18 Wuzhou University Wuzhou City Not Applicable 19 Hezhou University Hezhou City Guangxi Electrical 20 Nanning City Polytechnic Institute Guangxi 21 Eco-engineering Vocational Liuzhou city Not Applicable and Technical College Guangxi Finance Vocational 22 Nanning City Not Applicable and Technical School Guangxi Ji Dian Gong Cheng 23 Nanning city Xue Xiao Guangxi Institute Science and 24 Technology Nanning city School Guangxi Textile Industry 25 Nanning city School Guangxi Overseas Chinese 26 Nanning city School

74

Problem of No. Subproject Location Remarks identification Guangxi nationality 27 secondary professional Nanning city school 28 Guangxi Business School Liuzhou city Not Applicable Guangxiyoujiang Commercial 29 Baise city College for Nationalities Gvangjsih Liujcouh Cuzmuz 30 Liuzhou city Couyih Yozyau Guangxi Yulin Agricultural 31 Yulin city Not Applicable School Guangxi Industrial and 32 Nanning city Commercial School Heng county vocational 33 Heng county education center Liuzhou city Luzhai vocational Luzhai 34 Not Applicable education center county Cenxi city secondary 35 Cenxi city specialized school Cangwu county secondary 36 Wuzhou city specialized school Beibuwan vocational 37 Qinzhou city technical institute Lingshan county vocational Lingshan 38 technical institute county Guigang city vocational 39 Guigang city education center Yulin No.1 Secondary 40 Yulin city Not Applicable Vocational School Rong county secondary 41 Rong county Not Applicable Vocational school Bobai county Bobai county secondary 42 education specialized school park 43 Baise ethnic health school Baise city Zhaoping vocational 44 Hezhou city education center 45 Hechi City Health School Hechi city Not Applicable Hechi Yizhou Vocational 46 Hechi city Not Applicable Education Center LaiBin Vocational Education 47 Laibin city Center School Guangxi Industrial Technician 48 Nanning city 不适用 College Guangxi Technician College 49 Liuzhou city of Machinery & Electricity Guangxi Traffic Technician 50 Nanning city College GuangXi Shangmao Senior 51 Nanning city Technical School The Second Light Industry 52 Nanning city Not Applicable Technical School of Guangxi Guangxi yulin technician 53 college(Guangxi yulin senior Yulin City Not Applicable technical school)

75

Problem of No. Subproject Location Remarks identification Liuzhou NO.2 Vocational 54 Liuzhou city Not Applicable School QuanZhou vocational & Quanzhou 55 Not Applicable technical schools county Guiping city NO.1 secondary 56 vocational and technical Guiping city Not Applicable school Hechi city vocational 57 Hechi city Not Applicable education center school Guilin tourism vocational 58 secondary professional Guilin city Not Applicable school Liuzhou No.1 Vocational and 59 liuzhou city Not Applicable Technical School Guangxi Wuzi 60 Nanning city School of 61 Nanning city Chinese Medicine Guangxi QinZhou Agricultural 62 Qinzhou city Not Applicable School Guangxi Wuzhou Business 63 Wuzhou city Not Applicable School Guangxi Urban Construction 64 Guilin City Not Applicable School Guangxi Mechanical and 65 Nanning City Electrical Industry School Guangxi Aquatic Animal 66 Nanning City Husbandry School Guidong Health Secondary 67 Hezhou city School Beihai secondary vocational 68 Beihai City and technical school Jingxi Vocational and 69 Baise city Technical School Guangxi Nanning Senior 70 Nanning city Not Applicable Technical School Guangxi Quality Technology 71 Nanning city Engineering School 72 Nanning Sports School Nanning city Pingnan County Secondary Pingnan 73 Vocational and Technical County school Chongzuo City Vocational Chongzuo 74 and Technical School city

This monitoring found that 30 subproject schools that have started construction have set up a GRM in accordance with the above requirements. GPMO has also established GRM tracking system and GRM database. Schools of each subproject shall regularly collect information and feedback the information to the GPMO.

76

The GRM tracking system established by GPMO will include the following elements: (i) tracking forms and procedures to collect information from project personnel and complainants (see project complaint processing form and GRM feedback form); (ii) the resettlement coordinator of the GPMO regularly updates the complaint database; and (iii) a simple and efficient filing system for retrieving data for reporting purposes.

Resettlement experts have set up a monitoring GRM database by EXCEL for

GPMO, and the GPMO staff were trained. The GRM database would be updated once in 2 weeks and twice in 1 month. After the update, the updated summary results would be timely fed back to the consulting experts or external monitoring staff.

Table 3-4 The Data of Grievance Redress

Legacy Grievance Grievance Handing No. School Results Feedback Remarks Content Time Time Problems

1

2

Since 74 subproject schools involved in the project, each subproject school is required to establish a GRM for the APs in accordance with the above requirements.

The GPMO will urge and supervise all subproject schools to establish a GRM as soon as possible and assign a full-time staff responsible for the resettlement. The GPMO has assigned a full-time staff member to handle resettlement. According to the survey,

30 subproject schools that have started construction have established GRM and designated full-time staff responsible for resettlement. See table 3-5 for the full-time resettlement staff designated by the subproject school that has started construction.

77

Table 3-5 Contact Information of School Resettlement Staff of the Project

under Construction

Project Contact No. School Duty Work E-mail Leader Information Guilin University of Propaganda 0773- 1 Wu Shixian [email protected] Aerospace Minister 6796509 Lin Yejiang Deputy party 0773- Zhang secretary 3690016 Guilin Tourism 2 Xianchun Dean of 0773- [email protected] College international 3690150 Yongqiang college 0773-

Vice president Yulin Normal Tang of School of 3 13457604598 [email protected] University Zhangxin Education Science Director of 0778- logistics and 4 Hechi University Qin Yong 3146683 [email protected] Infrastructure 13907787116 Division Director of 5 Wuzhou University Liang Li Finance 13977493338 [email protected] Department Guangxi Transport Head of Vocational and 6 Infrastructure 18977182033 [email protected] Technical College of Renhong Department Communications Director of logistics Fan Hongri Director of Jia Mingzu development 18178632088 Guangxi Vocational Deng planning 18178632688 7 [email protected] College of Industrial Kaihao Director of 18178633200 Huang New Campus 18178632211 Wensheng Construction Headquarters Office Guangxi Eco- engineering 8 [email protected] Vocational and Technical College

Guangxi Vocational 0771- 9 College of Xie Dong Vice-president 3389889 [email protected] Construction 18677155661

Director of Guangxi College for Deng 10 logistics 18078145188 [email protected] Preschool Education Bochang management

78

Project Contact No. School Duty Work E-mail Leader Information

Guangxi Finance 11 Vocational and Shen Lijun Dean [email protected] Technical School

Guangxi Business Qin 12 President 18907722582 [email protected] School Bingxin

Guangxi QinZhou Chen 13 Vice-president 13877729919 [email protected] Agricultural School Mingqiang

Guangxi Yulin Luo 14 13877590186 [email protected] Agricultural School Guoqiu

Dean of Guangxi Urban Cui 15 Academic 15877027979 [email protected] Construction School Yongjuan Affairs Guangxi Wuzhou Liang Assistant to 16 18934842568 [email protected] Business School Zhaohui the president

Liuzhou No.1

17 Vocational and Qin Haibo 18077216151 [email protected] President Technical School

Liuzhou NO.2 Long 18 18977268808 [email protected] Vocational School Linying President

Liuzhou city Luzhai 19 vocational education [email protected] center

Guilin tourism 20 vocational secondary President 18907739122 [email protected] professional school

QuanZhou vocational Yan 21 Secretary 18078308276 [email protected] & technical schools Qiuming

Deputy Guiping city NO.1 Yang director of 22 secondary vocational 18934902693 [email protected] Zhiwen general affairs and technical school department

Yulin No.1 Secondary 23 [email protected] Vocational School

Rong county Director of 24 secondary Vocational Liang Yuan 18977518598 [email protected] general affairs school Chief of Hechi City Health 0778-2297004 25 Jiang Bin General Affairs [email protected] School 18007786012 Section Hechi Yizhou Wei 26 Vocational Education President 13788081119 [email protected] Jiuxian Center

79

Project Contact No. School Duty Work E-mail Leader Information

Guangxi Industrial Guan 27 Vice-president 13877168610 [email protected] Technician College Guoai

The Second Light 28 Industry Technical Vice-president 13878111956 [email protected] Yangchong School of Guangxi

Guangxi Nanning Head of Huang 29 Senior Technical scientific 18178118050 [email protected] Xingyi School research

Guangxi yulin technician college Xin 0775-2630025 30 (Guangxi yulin Vice-president [email protected] Xiangning 18907755959 senior technical school)

APs also have the right to use alternative channels at any time: (i) go through an

administrative appeal according to the Administrative Procedure Law of the PRC, or (ii)

go directly to the People’s Court.

If the APs remains dissatisfied and believes that he/she has been harmed by

his/her non-compliance with ADB policies and has worked in good faith to resolve the problem by working with the ADB project team, they may lodge a complaint under the

ADB's accountability mechanism. Information about how to complain, can browse the web https://www.adb.org/site/accountability-mechanism/main.

According to the survey, there have been no complaints so far from the 30

subproject schools under construction. Resettlement external monitoring staff will

record any complaints and concerns raised by affected households during the

monitoring process. The concerns and questions raised, the assessment of events by

external monitors and the recommendations made by external monitors will be

reflected in the external monitoring report.

80

4. Institutional Arrangements

The GPMO will be responsible for management of the overall investment program implementation including resettlement. The GPMO has assigned a full-time staff to handle any resettlement matters, including collecting and summarizing resettlement materials, maintaining resettlement databases and GRM, and assisting resettlement experts and external monitoring staff in conducting investigations. Since GPMO has limited experience on resettlement, especially ADB Safeguard Policy Statement (2009) policies and requirements, a resettlement consultant will be engaged to provide support and capacity building to the GPMO.2

Other key institutions involved in resettlement planning and implementation are

the (i) TVET School for each subproject; (ii) Country/District LRB/HDO; and (iii)

Village/Community Committees. Figure 4-1 presents the institutional arrangements.

TVET school/design Site identification institute

Category C: No

TVET action. To screening school/GPMO/LRB/HDO document in the monitoring report External Category A: Monitoring excluded. Category B Prepare (External Prior LAR: due TVET school/ LRB/HDO/village improved 1-book-4- Monitor) plan/Compensation committee and Relocation Plan

TVET school/ LRB/HDO/village Implementation

Committee/other government Monitoring and agencies Reporting

Figure 4-2 Institutional Framework

2 There is a separate capacity development technical assistance for the program to provide support. This includes engagement of resettlement consultant to provide guidance and support during screening, planning, and implementation. The resettlement consultant will also be tasked to provide training to GPMO. 81

4.1 Responsibilities of the Institutions

GPMO. The roles and responsibilities include:

 organize related training on ADB’s involuntary resettlement (IR) policies, screen the IR impacts.

 conduct due diligence for prior LAR and coordinate with the local government in developing CAP.

 coordinate with the LRB/HDO at all levels to provide all the necessary LAR information.

 set-up resettlement database.

 set-up GRM tracking system.

 engage the external monitoring agency.

 prepare the semiannual internal M&E reports based on the information provided by local TVET school, LRB, HDO and other concerned organizations (civil affairs, labor and social security bureau, all women’s federation, village leaders, etc.).

TVET school for each subproject.

 Its main duties are to coordinate with the related agencies (LRB, HDO, etc.), and report regularly to the GPMO. A resettlement staff will be assigned.

 coordinate with the LRB/HDO to get the information and assist the GPMO to screen and the IR impacts and conduct the due diligence.

 Establish GRM, assist external monitoring units in their investigations and collect information.

 fill in the tables of appendix 2 of this RF and submit the improved 1-Book-4-Plan/

Compensation and Relocation Plan to GPMO.

 During LAR, closely monitor the implementation and coordinate with the

LRB/HDO to collect information for the internal monitoring report.

 file all approval documents related to LAR.

County/District LRB and HDO are the key agencies for implementation of LAR.

 conduct detailed measurement survey, consultation, information disclosure.

82

 prepare the 1-Book-4-Plan/ Compensation and Relocation Plan before LAR and share with TVET school.

 documentation of the information disclosure, participation and GRM and share with TVET school.

 provide the information for the M&E reports to TVET school.

 Village/Community Committee play a key role in LA/HD since they are aware of the history and socio-economic situation of the affected residents.

 participate in the detailed measurement survey.

 assist the LRB/HDO to conduct consultation, information disclosure, negotiation and GRM.

 reallocate housing sites and contracted land after land acquisition and house demolition.

 provide information on the affected vulnerable groups or those who may become vulnerable.

 organize village meetings to discuss the compensation rates, restoration and relocation plan.

 documentation of the information disclosure, participation and GRM and share with TVET school.

Other Agencies. Apart from the key players above, other agencies will also be requested to support the program based on their specific roles and responsibilities: a) Civil Affairs responsible for identification Five-Guarantee and those eligible for the

Minimum Living Guarantee System. b) Women’s Federation for cash or in-kind assistance to the women headed households. c) Health Bureau responsible for urgent assistance if the households have serious illness. d) Construction and Housing Bureau responsible for affordable housing and low-rent housing to vulnerable groups; approval of the house relocation plan.

83

e) Labor and Social Security responsible for endowment insurance system for the landless farmers, provide relevant training and access to job opportunities in the area including project-related employment opportunities.

4.2 Personnel and Facility

In order to make the resettlement work smoothly, the resettlement agencies at all levels of the project are equipped with special staff, forming up and down smooth information transmission channels. Currently, there are five employees in GPMO, including one person in charge of resettlement. He is responsible for resettlement matters, including the collection and statistics of LA and HD, the collection and feedback of grievance and appeal, and other resettlement matters. According to the survey, 30 schools already under construction have assigned one full-time resettlement staff. The GPMO will urge schools that have not yet started construction to assign a full-time staff member in charge of resettlement work.

4.3 Office Facility

Each subproject school have made use of available resources and 30 schools already under construction have been equipped with basic office equipment, transportation equipment and communication equipment, including office tables and chairs, computers, printers, telephones, fax machines, vehicles and other equipment resources. The GPMO requires schools that have not yet started construction to be equipped with basic office facilities and equipment as soon as possible before starting work.

4.4 Assessment on Organization Capacity

This monitoring found that during the implementation of the project, the GPMO has assigned a full-time staff member to be responsible for the resettlement of the APs, including the summary and statistics of land acquisition and house demolition, the summary and feedback of grievance and appeals, as well as the coordination and monitoring assistance of the resettlement work. According to the survey, 30 schools already under construction have assigned on full-time resettlement staff. The GPMO

84

will urge schools that have not yet started construction to assign a full-time staff member in charge of resettlement work. In order to better implement the resettlement activities, the GPMO and each subproject schools should establish the organization, coordination, data and information feedback, and take the following measures:

(1) Each subproject school shall assign a full-time staff responsible for

resettlement matters, including the implementation of resettlement activities, the

collection and data statistics of land acquisition and house demolition materials,

the collection and feedback of grievances and appeals, as well as the coordination

and monitoring assistance of resettlement work.

(2) Resettlement consultants will be organize the training on resettlement,

monitoring and report preparation for each subproject school full-time staff in the

later stage, let the full-time staff of GPMO and subproject schools understand and

master the relevant requirements of the PRC's resettlement policy and ADB, and

improve their professional quality and policy processing capacity.

(3) The schools of each subproject should provide timely feedback on resettlement.

The schools of each subproject will provide feedback on any resettlement-related

information to the GPMO, and the GPMO will collect the feedback to the consulting

experts and ADB. Make its information from top to bottom and from bottom to top

smooth.

(4) Schools under construction have established GRM and designated a full-time

staff member responsible for resettlement work; but the subproject school that has

not started the construction has not yet established GRM and assigned a full-time

staff. The GPMO should urge the subproject schools that have not yet established

the GRM to establish the GRM as soon as possible, and let each subproject school

that has not yet started to assign a full-time staff responsible for resettlement

matters, so as to find problems and solve them in time, and establish a timely

information communication and feedback mechanism.

85

4.5 Institution Capacity Building and Training

In November 2018, independent experts on resettlement provided training to the staff of the GPMO, and each subproject schools in charge of resettlement, mainly include: Safeguard Policy Statement, RF, involuntary resettlement impact categorization checklist, the 1-Book-4 Plan and acquisition and compensation scheme table, information disclosure and public participation, training in the documentation of grievance mechanism and outline of internal monitoring, and answer the feedback of each subproject school to the training content. According to the implementation progress of the program, resettlement consulting experts in the later period will conduct detailed training on resettlement policy, the 1-Book-4 Plan, compensation plan form, information disclosure and public participation, and GRM for schools that have not started construction.

Figure 4-3 Training

86

87

Figure 4-4 Conference Attendance List

88

5 Resettlement Monitoring

According to the survey, 30 of the 74 subproject schools have started construction.

In mid-November 2019, independent resettlement consulting experts visited the site

and monitored the resettlement of the 30 subprojects already under construction.

According to the survey, the resettlement impact of the 30 subproject schools under

construction is classified as class C, all of which are constructed in the reserved land

of original campus, without LA and HD impact. The detailed monitoring situation is as

follows:

5.1 Guilin University of Aerospace Technology

Guilin university of aerospace technology is mainly to expand the training center,

entrepreneurship center, comprehensive gymnasium, maintenance and renovation the

corresponding facilities and equipment in the original campus.

According to the survey, all the newly built contents are in the original campus,

which is reserved for the school, without any LA and HD impact. Construction units have obtained the construction project planning permit and construction permit from the planning department and construction department before starting construction. As

shown in figures 5-1–5-3.

Figure 5-5 Land Use Certificate of Guilin University of Aerospace Technology 89

Figure 5-6 Construction Project Planning Permit of Guilin University of Aerospace Technology

Figure 5-7 Construction Permit of Guilin University of Aerospace Technology 5.2 Guilin Tourism College

The civil engineering of Guilin tourism college is mainly to renovate and

decorate the original buildings, improve the teaching staff, and improve the basic

supporting facilities.

90

According to the survey, the project is built in the original campus of the school,

and the land is reserved for the school, there will be no LA and HD impact. Land

use certificate had been obtained in 2004, without any remaining problems, Land

Certificate is shown in Figure 5-4.

Figure 5-8 Land Use Certificate of Guilin Tourism College 5.3 Yulin Normal University

Yulin normal university mainly transforms the original infrastructure. According to the survey, all the construction contents are built in the original campus, reserved land for the school, there is no LA and HD impact and the land use certificate has been obtained, as shown in Figure 5-5.

91

Figure 5-9 Land Use Certificate of Yulin Normal University 5.4 Guangxi Transport Vocational and Technical College

Guangxi transport vocational and technical college is mainly for the construction

of practical training buildings and supporting infrastructure equipment.

After investigation, all the construction contents are built in the original campus,

the acquired land is reserved for the school, there is no LA and HD impact. Land use certificate had been obtained in 2003, as shown in Figure 5-6.

92

Figure 5-10 Land Use Certificate of Guangxi Transport Vocational and Technical College 5.5 Guangxi Vocational College of Industrial

Guangxi vocational college of Industrial is to newly build the manufacture

training base.

After investigation, the land of the original campus is unused state-owned land,

which was allocated to Wuming county government in Guangxi on 8 January 2003.

Because the land has been left undeveloped by government, surrounding farmers

exploited and farmed it since 2003. The government of Wuming county has

completed young crop compensation with farmers in 2012 and allocated it to

Guangxi Vocational College of Industrial. There are no remaining problems.

Compensation certificates and land use certificates are shown in Figure 5-7 and

Figure 5-8.

93

Figure 5-11 Land Use Certificate of Guangxi Vocational College of Industrial

Figure 5-12 Description of Young Crop of Guangxi Vocational College of Industrial

94

5.6 Guangxi Vocational College of Construction

Guangxi vocational college of construction mainly builds office buildings and libraries, including supporting infrastructure.

After investigation, the new office building and library are built in the original campus, the acquired land is reserved for the school, there is no LA and HD impact, and before the commencement of civil construction, planning permit of construction engineering and building construction permit of planning department and construction department has been obtained according to domestic procedure, see figures 5-9–5-11.

Figure 5-13 Land Use Certificate of Guangxi Vocational College of Construction

95

Figure 5-14 Planning Permit of Construction Engineering of Guangxi Vocational College of Construction

Figure 5-15 Building Construction Permit of Guangxi Vocational College of Construction 5.7 Guangxi College for Preschool Education

Guangxi College for Preschool Education is mainly used for teaching and training

in the new campus (public teaching room, teaching and training room and office room),

library, indoor gym, school-level office room, halls and accommodation for college

96

students, student dormitory (apartment), single staff dormitory (apartment), canteen,

logistics and accessory occupancy, and intellectualized system, playground, water

supply and drainage, power supply and distribution, gates, walls, roads, greening and

landscape, water, square and other supporting infrastructure construction.

After investigation, the occupied land by the new campus of Guangxi College for

Preschool Education is state-owned land, the allocation procedure of state-owned land has been completed, the land use certificate is being handled now, there is no impact of LA and HD. The supporting materials are shown in the Figure 5-12; before the commencement of civil construction, the construction project planning license of the planning department and construction department has been obtained, as shown in

Figure 5-13.

Figure 5-16 the Certificate of State-owned Land Use for the New Campus of Guangxi College for Preschool Education

97

Figure 5-17 Construction Project Planning Permit for Construction land of Guangxi College for Preschool Education 5.8 Hechi University

The project of Hechi university is to demolish two dangerous buildings in the original campus and rebuild the education training building on the original site. After survey, there is no LA and HD impact. Construction occurs on reserved land for the school. Land certificate, planning permit of construction engineering and building construction permit have been provided before commencement of construction, which are shown in figures 5-14–5-16.

98

Figure 5-18 Land Use Certificate of Hechi University

Figure 5-19 Planning Permit of Construction Engineering of Hechi

University

99

Figure 5-20 Building Construction Permit of Hechi University

5.9 Wuzhou University

Wuzhou university mainly builds the comprehensive experimental building and the improvement of the faculty, and so on.

After investigation, comprehensive experimental building is in the original campus, the acquired land is reserved for the school, and there is no LA and HD impact; Wuzhou university obtained the land use certificate in 2003, see Figure 5-17; before project civil work, project planning and construction work permits, construction permits of planning department and construction department has been obtained according to domestic procedure. See figures 5-18 and 5-19.

100

Figure 5-21 Land Use Certificate of Wuzhou University

Figure 5-22 Planning Permit of Construction Engineering of Wuzhou University

101

Figure 5-23 Construction Work Permits of Wuzhou University

5.10 Guangxi Eco-engineering Vocational and Technical

College

Guangxi Eco-engineering Vocational and Technical College mainly builds the

student apartment, training building, comprehensive library. After investigation, all

subprojects are in the original campus, the acquired land is reserved for the school,

and there is no LA and HD impact.; Guangxi Vocational Ecological Technology College

obtained the land use certificate in 2004, see Figure 5-20; before project civil work,

project planning and construction work permits, construction permits of planning

department and construction department has been obtained according to domestic

procedure.

102

Figure 5-24 Land Use Certificate of Guangxi Eco-engineering Vocational and

Technical College

Figure 5-25 Planning Permit of Construction Engineering of Guangxi Eco-engineering

Vocational and Technical College

5.11 Guangxi Financial Vocational College

Guangxi Financial Vocational College builds one library.

After investigation, all the subprojects are built in the original campus, the acquired

land is reserved for the school, and there is no LA and HD impact; before project civil

103

work, project planning and construction work permits, construction permits of planning department and construction department has been obtained according to domestic procedure. See figures 5-22–5-24.

Figure 5-26 Land Use Certificate of Guangxi Financial Vocational College

Figure 5-27 planning permit of construction engineering of Guangxi Financial

Vocational College

104

Figure 5-28 building construction permit of Guangxi Financial Vocational

College

5.12 Guangxi Business School

Guangxi Business School mainly builds student apartment and training building.

After investigation, all subprojects are in the original campus, the acquired land is

reserved for the school, and there is no LA and HD impact. And the land use certificate

was obtained in 2005. Guangxi Business School obtained the land use certificate in

2005. See Figure 5-25.

105

Figure 5-29 Land Use Certificate of Guangxi Business School

5.13 Guangxi Yulin Agriculture

Guangxi Yulin Agriculture mainly builds teaching building and purchase teaching facilities in the original campus and so on.

After investigation, the teaching building is in the original campus, the acquired land is reserved for the school, and there is no LA and HD impact. The documentary evidence is shown in Figure 5-26. Before project civil work, project planning and construction work permits, construction permits of planning department and construction department have been obtained according to domestic procedure. See figures 5-27–5-28.

106

Figure 5-30 Land Explanation of Guangxi Yulin Agriculture

Figure 5-31 Planning Permit of Construction Engineering of Guangxi Yulin

Agriculture

107

Figure 5-32 Building Construction Permit of Guangxi Yulin Agriculture

5.14 Liuzhou City Luzhai Vocational Education Center

Liuzhou City Luzhai Vocational Education Center mainly builds training room, office and relevant supporting facilities.

After investigation, all subprojects are in the original campus, the acquired land is reserved for the school, and there is no LA and HD impact. Liuzhou City Luzhai

Vocational Education Center obtained the land use certificate in 2010. See Figure 5-

29. Before project civil work, project planning and construction work permits, construction permits of planning department and construction department have been obtained according to domestic procedure. See figures 5-30–5-31.

Figure 5-33 Land Use Certificate of Liuzhou Luzhai City Vocational

Education Center 108

Figure 5-34 planning permit of construction engineering of Liuzhou City

Luzhai Vocational Education Center Figure

Figure 5-35 Building Construction Permit of Liuzhou City Luzhai Vocational Education Center 5.15 Yulin Shi Di Yi Zhi Ye Zhong Deng Zhuan Ye Xue Xiao

Yulin Shi Di Yi Zhi Ye Zhong Deng Zhuan Ye Xue Xiao mainly builds two student apartments, Smart Campus and improvement and purchase of facilities, etc.

After investigation, two student apartments are built in the original campus, where the acquired land is reserved for the school, and there is no LA and HD impact. The land use certificate was obtained; see Figure 5-32 for land use certificate.

109

Figure 5-36 Land Use Certificate of Yulin Shi Di Yi Zhi Ye Zhong Deng Zhuan Ye

Xue Xiao

5.16 Rong County Secondary Specialized School

Rong County Secondary Specialized School mainly builds student apartment and training building, and improvement and purchase of facilities.

After investigation, the acquired land is reserved for the school, and there is no LA and HD impact; see Figure 5-33 for land use certificate.

Figure 5-37 Land Use Certificate of Rong County Secondary Specialized

School

5.17 Hechi City Health School

Hechi City Health School constructs training building with the land of demolished old auditorium and improve supporting facilities and equipment.

After survey, the demolished old auditorium is reconstructed in the original site,

110

without LA and HD impact. Construction units have obtained the construction project planning permit from the planning department and construction department before starting construction. See figures 5-34–5-35.

Figure 5-38 Land Use Certificate of Hechi City Health School

Figure 5-39 Construction Project Planning Permit of Hechi City Health School 5.18 Hechi Yizhou Vocational Education Center

Hechi Yizhou vocational education center mainly constructs student dormitory

rooms and supporting rooms, decoration engineering, water supply and drainage

engineering, electrical engineering, heating engineering and related supporting

engineering.

According to the survey, all subprojects are built in the original campus, which are

reserved land for the school, and there is no LA and HD impact. Land certificate is

shown in Figure 5-36.

111

Figure 5-40 Land Use Certificate of Hechi Yizhou Vocational Education Center 5.19 Guangxi Industrial Technician College (The original name is Guangxi petrochemical advanced technical school)

Guangxi industrial technician college mainly constructs student dormitory rooms and supporting rooms, decoration engineering, water supply and drainage engineering, electrical engineering, heating engineering and related supporting engineering.

According to the survey, all subprojects are built in the original campus, which are reserved land for the school, and there is no LA and HD impact. Construction units have obtained the construction project planning permit from the planning department and construction department before starting construction. See figures 5-37 and 5-38.

Figure 5-41 Land Use Certificate 0f Guangxi Industrial Technician College

112

Figure 5-42 Construction Project Planning Permit of Guangxi Industrial Technician College 5.20 The Second Light Industry Technical School of Guangxi

The Second Light Industry Technical School of Guangxi builds student dorm

building, improvement of supporting facilities.

The land for Second Light Industry Technical School of Guangxi has been

acquired in 2014, and the land certificate have been obtained in 2015. A total of 139.98

mu of land was acquired, including 19.89 mu of arable land, 87.88 mu of garden land and 32.21 mu of woodland.

After investigation, the compensation and resettlement have been completed, there is no leftover problem. The detailed documents are shown in the figures 5-39–5-

41.

Figure 5-43 Completion of LA Compensation Situation Notes of The Second Light Industry Technical School of Guangxi

113

Figure 5-44 Land Use Certificate of The Second Light Industry Technical School of Guangxi

Figure 5-45 Construction Land Use Permit of The Second Light Industry Technical School of Guangxi 5.21 Guangxi yulin technician college(Guangxi yulin senior technical school)

Guangxi yulin technician college(Guangxi yulin senior technical school)builds a

training comprehensive building and public auxiliary facilities, etc.

After investigation, training building is in the original campus, the acquired land is

reserved for the school, and there is no LA and HD impact; See Figure 5-42 for land use certificate.

114

Figure 5-46 Land Use Certificate of Guangxi Yulin Technician College(Guangxi yulin

senior technical school)

5.22 Liuzhou No.2 Vocational School

Liuzhou No.2 Vocational School newly builds one teaching building and training building, including a new integrated teaching building, water supply and drainage and other ancillary facilities.

After investigation, all subprojects are in the original campus, the acquired land is

reserved for the school, and there is no LA and HD impact; See Figure 5-43 for land use certificate.

Figure 5-47 Land Use Certificate of Liuzhou No.2 Vocational School

115

5.23 QuanZhou Vocational & Technical Schools

QuanZhou vocational & technical schools mainly builds student dormitory building and automobile repair workshop, including supporting facilities.

After investigation, all the subprojects are in the original campus, where the acquired land is reserved for the school, and there is no LA and HD impact. QuanZhou vocational & technical schools obtained land use certificate in 2008, see figures 5-44–

5-45.

Figure 5-48 Land Use Certificate of QuanZhou Vocational & Technical Schools

Figure 5-49 Planning Permit of Construction Engineering of QuanZhou

Vocational & Technical Schools

5.24 Guiping city NO.1 secondary vocational and technical

school

Guiping city NO.1 secondary vocational and technical school builds new

comprehensive training building, supporting facilities related ancillary projects. 116

After investigation, comprehensive training building in the original campus, where the acquired land is reserved for the school, and there is no LA and HD impact. See

Figure 5-46 for land use certificate.

Figure 5-50 Land Use Certificate of Guiping city NO.1 Secondary Vocational

and Technical School

5.25 Guilin Tourism Vocational Secondary Professional School

Guilin tourism vocational secondary professional school builds new comprehensive teaching building, training room and renovating the existing amphitheater, and improvement of supporting facilities.

After investigation, new comprehensive teaching building and training room are

built on the land which is reserved for the school, and there is no LA and HD impact.

Guilin tourism vocational secondary professional school obtained land use certificate

in 2005. See Figure 5-47.

117

Figure 5-51 Land Use Certificate of Guilin Tourism Vocational Secondary

Professional School

5.26 Liuzhou No.1 Vocational and Technical School

Liuzhou No.1 Vocational and Technical School built new student apartment,

renovation of power facilities and improvement of supporting facilities.

After investigation, new student apartment building in the original campus, where the acquired land is reserved for the school, and there is no LA and HD impact. Liuzhou

No.1 Vocational and Technical School obtained land use certificate in 2010. See Figure

5-48.

Figure 5-52 Land Use Certificate of Guangxi Qinzhou Agriculture School

118

5.27 Guangxi Qinzhou Agriculture School

Guangxi Qinzhou Agriculture School built new training teaching building and

student apartment, and improvement of equipment, etc.

After investigation, new training teaching building and student apartment building is in the original campus, where the acquired land is reserved for the school, and there is no LA and HD impact. Guangxi Qinzhou Agriculture School obtained land use certificate in 2002. See Figure 5-49.

Figure 5-53 Land Use Certificate of Guangxi Qinzhou Agriculture School

5.28 Guangxi Wuzhou Business School

Guangxi Wuzhou Business School builds one training building and decoration engineering, and purchase equipment and tool, water supply and drainage, electric engineering, outdoor hardening, greening engineering, etc.

After investigation, the construction is conducted on the site where the dangerous old administrative office building is demolished in the original campus. Therefore, there is no LA and HD impact. See Figure 5-50 for land use certificate.

119

Figure 5-54 Land Use Certificate of Guangxi Wuzhou Trade School

5.29 Guangxi Urban Construction School

Guangxi Urban Construction School mainly builds teaching building, training base

and gym center.

After investigation, new teaching building, training base and gym center are built

in the original campus, where the acquired land is reserved for the school, and there

is no LA and HD impact. See Figure 5-51 for land use certificate.

Figure 5-55 Land Use Certificate of Guangxi Urban Construction School

5.30 Guangxi Nanning Senior Technical School

Guangxi Nanning Senior Technical School mainly builds one integrated teaching

building, and complementary road, greening, outdoor water and electricity and other

ancillary work.

After investigation, all the subprojects are built in the original campus, where the

acquired land is reserved for the school, and there is no LA and HD impact. See figures

120

5-52–5-53 for land use certificate and project planning and construction permits.

Figure 5-56 Land Use Certificate of Guangxi Nanning Senior Technical School

Figure 5-53 Planning Permit of Construction Engineering of Guangxi Nanning

Senior Technical School

121

6 Conclusions and Suggestions

6.1 Conclusions

Based on the findings of the monitoring visits, consultations and review of the land

availability of the 30 subprojects that have been initiated till date, there are no LA or

HD impacts and the subprojects were categorized C for involuntary resettlement. The

monitoring visits confirmed that the proposed subprojects are being developed within

the existing campuses of the 30 schools, the lands for them are already reserved for school development, and the required land use certificates from the government have

been obtained.

To make the resettlement work smoothly, GPMO and each of the subproject schools already under construction have assigned a full-time staff member responsible for resettlement matters and established a GRM. With the help of consulting experts, a GRM processing table and tracking table were prepared, and the GRM database was recommended to be updated regularly. The GRM database would be updated once in 2 weeks and twice in 1 month. After the update, the updated summary results

would be timely fed back to the consulting experts or external monitoring staff. To date,

GPMO has not receive any complaints regarding resettlement.

The subproject school that has not started the construction has not yet established

a GRM and assign full-time staff, GPMO shall urge and supervise the subprojects that has not established GRM to established GRM as soon as possible. In addition, each subproject school that has not yet started the construction should assign a full-time staff responsible for resettlement issues three months before the project starts, so as to find problems and solve them in time and establish a timely information communication and feedback mechanism. Because more subprojects school involved in the project, after each sub-project school determines the full-time staff of the resettlement, it is recommended the staff should be kept stable. If it is necessary to change the staff, the GPMO will be informed in time, and the resettlement work and data transfer will be done well, and the training on the resettlement work procedures will be conducted for the new staff. 122

.Resettlement consultants will organize the training on resettlement, monitoring

and report preparation for each subproject school full-time staff in the later stage, let

the full-time staff of GPMO and subproject schools understand and master the PRC’s

LA and HD policy and ADB policies, and improve their professional quality and policy processing capacity.

Schools of sub-projects that have not yet started the construction should work closely with relevant departments in a timely manner to speed up the relevant land procedures and submit the 1-Book-4-Plan in a timely manner.

So far, there have been no complaints from the communities where the 30 subproject schools have been started the construction, according to the survey.

GPMO suggested to establish the internal data organization system, strengthen the internal monitoring responsibility system, speed up the collection and statistics of data, submit materials timely, do a good job of sorting out project files, and find problems to solve. Each subproject school shall provide timely feedback on resettlement. Any information related to resettlement of each subproject school will be fed back to the GPMO, which will collect and feed back to the consulting experts and

ADB.

123