Social Monitoring Report

Loan Number: 3711 NEP Project Number: 35173-015 Semi-Annual Report January 2021

Nepal: Urban Water Supply and Sanitation (Sector) Project

Prepared by the Government of for the Asian Development Bank.

This Social Monitoring Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Government of Nepal Ministry of Water Supply Department of Water Supply and Sewerage Management Urban Water Supply and Sanitation (Sector) Project Project Management Office Panipokhari,

URBAN WATER SUPPLY AND SANITATION (SECTOR) PROJECT (UWSSP) (ADB loan No.3711-NEP and Project No: 35173-015)

Semi-Annual Social Monitoring Report (July - December, 2020)

Submitted by

Project Management Office Urban Water Supply and Sanitation (Sector) Project Panipokhari, Maharajgunj, Kathmandu,Nepal Tel : 977-1-4006629; Fax: 977-1-4413280 Web: www.uwssp.gov.np Semi-Annual Social Monitoring Report (July to December 2020)

Table of Contents I. EXECUTIVE SUMMARY ...... 1 II. BACKGROUND OF THE REPORT AND PROJECT DESCRIPTION ...... 2 2.1 GOAL AND OBJECTIVES OF THE PROJECT ...... 3 2.2 PROJECT IMPACT AND OUTCOME ...... 3 2.3 MONITORING REQUIREMENTS ...... 3 2.4 KEY SUB PROJECT COMPONENTS WORKS ...... 3 2.5 REPORTING PERIOD ...... 3 2.6 SOCIAL SAFEGUARD POLICY AND IMPLEMENTATION ...... 4 2.7 SOCIAL SAFEGUARD ISSUES AND RISKS ...... 4 III. SCOPE OF THIS REPORT ...... 4 3.1 SCOPE OF SOCIAL SAFEGUARD IMPACTS ...... 4 IV. SOCIAL SAFEGUARDS CATEGORY AND INVOLUNTARY RESETTLEMENT IMPACT ...... 2 4.1 APPROACH AND METHODOLOGY OF SOCIAL SAFEGUARD MONITORING REPORT ...... 4 V. COMPENSATION, REHABILITATION AND MITIGATION MEASURES ...... 5 VI. PUBLIC PARTICIPATION AND CONSULTATION ...... 7 VII. GRIEVANCE REDRESS MECHANISM ...... 27 7.1 RECORD KEEPING AND DISCLOSURE ...... 27 7.2 ENDORSEMENT OF AGREEMENT REACHED WITH MAKAIBARI PEOPLE IN CHARIKOT UWSSP ...... 27 7.3 CHRONOLOGY OF EVENTS ...... 28 VIII. PHYSICAL PROGRESS AND RP/DDR/IPP STATUS ...... 36 IX. PROGRESS STATUS OF SOCIAL SAFEGUARD ACTIVITIES AND INDIGENOUS PEOPLE'S PLAN ...... 37 X. INSTITUTIONAL ARRANGEMENT FOR PROJECT IMPLEMENTATION ...... 42 10.1 NAME OF THE PROJECT MUNIICIPALITIES UNDER UWSSP ...... 43 XI. MONITORING RESULTS AND FINDINGS ...... 45 XII. SAFEGUARDS LOAN COVENANTS ...... 46 XIII. FOLLOW UP ACTIONS, RECOMMENDATION ...... 50

ANNEXES: Annex-1: Training Participation Data Annex-2: Minutes of Meeting Annex-3: Photographs Annex-4: GRC Committee Name List Annex-5: IP Households Selection for Livelihood Training Annex-6: Third Party Verification from Secondary School of Gurbhakot Municipality/Subhaghat subproject

i | P a g e Semi-Annual Social Monitoring Report (July to December 2020)

List of Figures: Figure 1: Physical & Financial Progress made untill December 2020 ...... 37 Figure 2: Institutional Arrangement for Project Implementation ...... 42

List of Tables: Table 1: Summary of project descriptions and identified impacts ...... 1 Table 2: Status of affected assets in 14 subprojects ...... 1 Table 3: Status of subprojects and its implementation till December 2020 in the UWSSP ...... 2 Table 4: Resettlement Plan Implementation Status of sub-projects ...... 6 Table 5: Orientation/consultation meetings/training matrix ...... 11 Table 6: Chronology of Events in Charikot ...... 28 Table 7: Status of Grievances and Resolution ...... 30 Table 8: Submitted Grievances and Resolved Status ...... 31 Table 9: Physical & financial progress made on July-December 2020...... 36 Table 10: Summary of project towns and municipality ...... 43 Table 11: Corrective actions and way forward ...... 50

ii | P a g e Semi-Annual Social Monitoring Report (July to December 2020)

CURRENCY EQUIVALENTS (As of 1st January 2021) Currency unit = Nepalese Rupee (NRs) $ 1.00 = NRs. 116.39 In this report, "$" refers to US dollars.

ABBREVIATIONS ADB – Asian Development Bank CDC – Compensation Declaration Committee DDR – Due Diligence Report DPs – Displaced Persons DSMC – Design and Supervision Consultant DWSSM – Department of Water Supply and Sewerage Management EMP – Environmental Management Plan ERDSMC – Environment Monitoring Personnel Eastern Region Design Supervision Consultant GESI – Gender Equity and Social Inclusion GRC – Grievance Redress Committee GRM – Grievance Redress Mechanism ICG – Implementation Core Group IEE – Initial Environmental Examination IPP – Indigenous Peoples Plan IR – Involuntary Resettlement LAA – Land Acquisition Act OBA – Output Based Aid OHS – Occupational Health and Safety PMO – Project Management Office PMQAC – Project Management & Quality Assurance Consultant PPE – Personal Protective Equipment RDSMC – Regional Design, Supervision and Management Consultant RF – Resettlement Framework RP – Resettlement Plan RPMO – Regional Project Management Office SPS – Safeguard Policy Statement WRDSMC – Western Regional Design, Supervision and Management Consultant WSS – Water Supply and Sanitation WUSC – Water Users and Sanitation Committee

iii | P a g e Semi-Annual Social Monitoring Report (July to December 2020)

NOTES (i) The fiscal year (FY) of the and its agencies ends on 16 July. FY before a calendar year denotes the year in which the fiscal year ends, e.g., FY 2019 ends on 16 July 2020.

(ii) In this report, "$" refers to US dollars.

iv | P a g e Semi-Annual Social Monitoring Report (July to December 2020)

I. EXECUTIVE SUMMARY

1. Urban Water Supply and Sanitation (Sector) Project (UWSSP) is supporting Nepal in expanding access to community-managed water supply and sanitation (WSS) in 20 project municipalities by drawing on experiences and lessons from three earlier projects funded by the Asian Development Bank (ADB). The project is financing climate-resilient and inclusive WSS infrastructure in project municipalities and strengthen institutional and community capacity, sustainable service delivery, and project development. It is being implemented by, Project Management office Kathmandu under the Department of Water Supply and Sewerage Management, who will address any resettlement impacts, permanent or temporary, during project implementation

2. This semi annual report presents the Social Safeguard Documents; Resettlement Plan (RP)/ DDR implementing status till December 2020.The overall project is classified as Social Safegurds category B in accordance with ADB Safeguard Policy Statement (SPS) 2009. ADB's SPS covers both temporary and permanent impacts implementation.

3. 14 projects are under implementation in three geographic regions of Nepal. No land acquisition is required for the proposed projects. Measures to avoid and minimize private land acquisition and involuntary resettlement impacts were adopted. No significant livelihood and income related impacts are anticipated. Adequate vacant government land is available at each project sites. Temporary impact to local residents and pedistrians due to pipe laying work is avoided by good traffic management plan. Efforts are continuing to avoid adverse impact.

4. A total of 54 major consultative/orientation/Trainings/ meeting were held in community to disseminate project information and project entitlements. The meeting covered issues of community participation as well as and other project related activities. The regular meeting with sub projects town community members and stakeholders is continuous. Grievance Redress Committees has been formed in all 12 subprojects.

5. The GRCs have been addressing grievance recorded during implementation of subprojects. During this reporting period 36 cases of grievances have been filed in subprojects. All grievances are resolved by field level GRC. One grievance recorded in Siddhanath- Baijanath subproject is resolved verbally through interaction with complainant, local user and WUSC ; perhaps the minutes of meeting will be included in next QPR.

6. The Project Management Office (PMO) and Regional Project Management Office (RPMO) have set up institutional requirement for the implementation of Resettlement Plan and the Resettlement Plan implementation is continuous.

7. All the 14 subprojects are being monitored regularly in terms of social safeguard and resettlement perspective. Most of the water supply structures are built either on a public land or land already owned by concerned WUSCs. The issues of temporary affected persons during implementation (digging of trench for pipeline) are being dealt as per GRM and EMP.

8. Follow up Actions, Recommendation and Disclosure

9. The implementation of OBA provisions as per the agreement made between PMO and WUSC needs to speed up in applicable remaining subprojects.

10. Due to continuous effects of COVID-19 in different forms, alternative modalities should be adopted to continue monitoring of the sub-project implementation to assess the Involuntary Resettlement impacts and accordingly mitigate the issues. • Emphasize to conduct stakeholder consultations, FGDs, Meetings and site visits by using preventative measures at the subproject locations.

1

Semi-Annual Social Monitoring Report (July to December 2020)

• Assess the need of additional awareness program on grievance redress mechanism and carry out the necessary awareness programs among the community people/stakeholders in subproject implementation locations. • Social Safeguard Specialist and Social Mobiliser of CRDSMC, ERDSMC and WRDSMC shall coordinate and facilitate the social safeguards activities in subproject areas. Mitigation measures, monitoring works as well as awareness raising activities shall be implemented with the involvement of the contractor and WUSC. • Required support shall be provided to safeguard desk in each subproject with the help of WUSC. • The regular follow up and monitoring of safeguard compliance will be continued. The project team will be involved in monitoring and providing instruction to contractors, if, they fail to comply with the safeguard compliance.

II. BACKGROUND OF THE REPORT AND PROJECT DESCRIPTION

11. The Urban Water Supply and Sanitation (Sector) Project (UWSSP) is supporting Nepal in expanding access to community-managed water supply and sanitation (WSS) in 20 project municipalities by drawing on experiences and lessons from three earlier interventions projects funded by the Asian Development Bank. The project will finance climate-resilient and inclusive WSS infrastructure in project municipalities and strengthen institutional and community capacity, sustainable service delivery, and project management. It will also contribute in strengthening sector policy, regulatory capacity and project development.

12. Since the establishment of 276 urban municipalities in 2015, 58% of Nepal’s population out of 29 million is urban. Rapid urbanization resulting from migration, reclassification and natural growth— has widened the urban infrastructure deficit. Unmanaged urban growth and lack of improved WSS has led to environmental degradation, public health risks, increased vulnerability to the impacts of climate change and natural hazards, a rise in urban poverty, and hampered economic growth. Since 2000, Nepal has made strong efforts to improve access to WSS. It increased water supply coverage from 73% to 84% and basic sanitation from 30% to 81% between 2000 and 2015. Yet, in 2016 only 34% of water supply was reported to be safe and only 15% complied with the national water quality standards. More efforts are also needed to achieve improved sanitation; only 34% of urban households have septic tanks and only 15% have sewer connections. Faecal sludge management and sanitation for marginalized groups, especially for women headed households and poor households remain a challenge. Overall, municipalities find it difficult to provide adequate, cost-effective services because they lack funds, skilled personnel and sufficient operation and maintenance budgets (PAM-UWSSP, Feb 2019).

13. The government targets for WSS services focus on inclusive development to improve functionality, enhance service levels, and expand municipal sanitation. The government has defined institutional responsibilities and service delivery mechanisms in the sector. The Ministry of Water Supply (MOWS) is responsible for planning, implementation, regulation, and monitoring of WSS; its Department of Water Supply and Sewerage Management (DWSSM) supports the provision of WSS facilities in municipalities where service level improvement is required, and these are operated by water users and sanitation committees (WUSCs) or municipalities.

14. Extending water supply and sanitation services to areas dealing with hardship is still a priority in Nepal. However, there are other issues; migration from hinterland to road centre is very common in Nepal.This has created many small towns, urban areas especially along the highways in Terai and hills as well. In these urban areas/towns, the improvement of the water supply and sanitation service level is most desirable; moreover, the quality of water has to be assured. Quality of drinking water in Nepal was overlooked in the past due to various reasons.

2

Semi-Annual Social Monitoring Report (July to December 2020)

15. UWSSP ensure both in terms of quantity and quality of drinking water and sanitation as well as the Gender Equity and Social Inclusion (GESI), social and environmental aspects.

16. The scope of services of the project is to improve health and quality of life of the people living in the project areas by facilitating water supply, drainage and sanitation facilities as well as by providing health and hygiene education programmes in the project areas of urban towns/municipalities in the country.

2.1 Goal and Objectives of the Project 17. The objectives of the project are: • To support Nepal in expanding access to community-managed water supply and sanitation (WSS) in 20 project municipalities by drawing on experiences and lessons from three earlier projects funded by the Asian Development Bank (ADB).and • To finance in climate-resilient and inclusive WSS infrastructure project municipalities and strengthen institutional and community capacity, sustainable service delivery, and project development. 2.2 Project Impact and Outcome 18. The project is aligned with the following impact: quality of life for urban population, including the poor and marginalized, improved through the provision of sustainable WSS services. The project will have the following outcome: inclusive and sustainable access to WSS services in project municipalities achieved. It has 2 major outputs as envisaged by the project. The first output is improved water supply and sanitation infrastructure, second is strengthened institutional and community capacities.

2.3 Monitoring Requirements 19. Monitoring is very important for ensuring social safeguard compliance. Three RDSMCs are involved in UWSSP for overall project monitoring. ERDSMC in east, CRDSMC in Central and WRDSMC in West are responsible for overall project management and monitoring in respective region.

20. DSMCs prepare monthly, quarterly and semi-annual progress reports of each town projects. Resettlement activities of the projects are generally incorporated in the reports submitted to each RPMO. RPMO with assistant from DSMC specialist consolidate their reports into semi-annual monitoring report and submit to PMO. PMO with assistant from PMQAC social safegiards specialist consolidate their reports into semi-annual monitoring report and submit to ADB. This report describes the progress of the implementation of resettlement activities, grievance redress mechanism, compliance issues and corrective actions. Any problems or issues identified will be followed-up (including recommendation of mitigation measures and supplementary budget); and learning from such issues will be recorded which will help to deal with issues in future.

2.4 Key Sub Project Components Works 21. The project infrastructures are intakes, deep well borings, overhead reservoir tanks, sump wells, collection wells, ground reservoir tanks, transmission and distribution pipe lines, water treatment plants, office buildings, tube wells, public toilets, electrical and electro-mechanical works (SCADA) including other associated works.

2.5 Reporting Period 22. This semi-annual social safeguard monitoring report includes the status of safeguard implementation activities in three region, 14 projects Municipalities under UWSSP covering the period of July to December 2020.Two Sub projects; Katahariya Storm Drainage Project and Tikapur Storm Drainage and Faecal slued Treatment Plant Project's contract are awarded recently and work has not started yet. Progress of these two projects shall be covered in next reporting period.

3

Semi-Annual Social Monitoring Report (July to December 2020)

2.6 Social Safeguard Policy and Implementation 23. ADB‘s involuntary resettlement policy comprises of compensation of lost assets, livelihood, and income; assistance for relocation with appropriate facilities and services; and assistance for rehabilitation for the same level of well-being of people. The covenants to the loan agreement with ADB requires that Resettlement Framework documents be complied during the implementation of project in accordance with ADB's SPS 2009 and resettlement framework prepared for the project and agreed between the Borrower and ADB. Any projects that involve land acquisition and resettlement impacts to be prepared resettlement plans and other safeguard reports as required under the scope of approved resettlement plan.

2.7 Social Safeguard Issues and Risks 24. Strategy to address social safeguard issues and risks consisted five major areas; involuntary resettlement; indigenous people; labour; affordability; and other risk vulnerabilities. Proper framework and guidelines have been prepared to handle these areas for field work to comply ADB‘s social safeguard policy statement (SPS, 2009). Resettlement framework is a key document in this regard. Resettlement framework has specific objectives, policies, principles, and procedures for land acquisition, compensation, and other assistances to the affected people. The resettlement framework complies with national laws that include the Land Acquisition Act 2034 (1977) and the Land Reform Act 2021 (1964).

III. SCOPE OF THIS REPORT

25. The scope of this social safeguard semi-annual monitoring report is to assess the progress on social safeguard implementation during the period of July to December 2020. The main objective of the report is to implement the social safeguards measures agreed in the due diligence reports, resettlement plans, indigenous peoples plan and any measures identified and recommended during project implementation as reported in previous SSMRs in compliance with the ADB SPS 2009. During the project design phase, agreements, mutual understandings were done in intake site, pipeline alignment and construction site of project related structures. The monitoring report describes the findings of implementing safeguard measures.The report assesses the implementation of following issues. • Compensation payment, • Replacement of affected structures and rehabilitation, • Restoration of public infrastructures, • Review of the consultation and disclosure processes, describe the subproject’s grievance redress mechanism for resolving complaints, • Restoration of livelihood of the affected persons/households, • Based on the Resettlement Framework (RF), all land acquisition and resettlement activities to be completed before commencement of civil works. However, income restoration measures and deed transfer are continued during ongoing civil works. • Assess GESI progress

3.1 Scope of Social Safeguard Impacts 26. The covenants of loan agreement with ADB requires that Resettlement Framework documents shall be complied during the implementation of project in accordance with ADB's SPS 2009 and resettlement framework prepared for the project and agreed between the Borrower and ADB. Any projects that involve land acquisition and resettlement impacts are to be prepared resettlement plan and other safeguard reports as required under the scope of approved resettlement plan.

27. This report covers the information regarding social safeguard and resettlement issues of 14 projects under construction phase. 12 Land Acquisition, Involuntary Resettlement and Indigenous People’s Due Reports (DDRs) were prepared.Two Resettlement Plans were prepared for two subprojects having resettlement impacts. Public land of Shivalaya temple is used for RVT

4

Semi-Annual Social Monitoring Report (July to December 2020)

construction and one community shade with CGI roofing shifted to a new location in Siddhanath- Baijanath subroject. In Shubhaghat subproject, compensation includes compensation for permanent loss of agriculture land, compensation for crop loss, income restoration and permanent loss of agriculture based livelihood.Similarly, one IPP is prepared for Ilam Urban Water Supply and Sanitation Subproject.

28. In 14 subprojects being implemented in eastern, central and western region, there is no displacement of people and adverse impact on indigenous people. However during the construction phase, there were temporary inconveniences such as increased vehicle movements and noise that affect the pedestrians and residents of the immediate vicinity of the site. The minimal impacts were observed along the right of way of roads where new pipes were installed. The remedial measures were taken to have proper movement of traffic and easy access to pedestrians. The Table 1, Table 2 and Table 3 below shows that summary of project activities and identified project impacts.

5

Semi-Annual Social Monitoring Report (July to December 2020)

Table 1: Summary of project descriptions and identified impacts Probable Khalanga Tikapur Katahariya Panchkhal Deurali_ Siddhanath Liwang Chainpur Shubhaghat Pragatinagar Ilam Diktel Bhojpur Charikot Impacts SWD$FSTP SWDP Hupsekot Land Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete Requirement Addressed all No IR No IR •Addressed No IR No IR No IR impact No IR No IR No IR No IR No IR No IR issues of impact impact issues of No IR impact impact impact impact impact impact impact impact Resettlement as Resettlement impact per •As per RP; IR RP(Community (Construction Building of Access Construction is Road) ongoing) No •No additional additional IR IR impact impact IP Impacts N/A N/A N/A N/A N/A N/A N/A Implementation N/A N/A N/A N/A N/A N/A of IPP Implementation Ongoing Ongoing Ongoing Ongoing Ongoing Ongoing Ongoing Ongoing Ongoing Ongoing Ongoing Ongoing Ongoing Ongoing Status RP/DDR/IPP Available Available Available Available Available Available Available Available Available Available Available Available Available Available IP=Indigenous People, IR=Involuntary Resettlement, RP=Resettlement Plan, DDR= Due Diligence Report

Table 2: Status of land availability, affected structures, crops and trees in 14 subprojects Siddhanath Khalanga Tikapur Katahariy Panchkhal Deurali_ Component Chainpur Shubhaghat Liwang Pragatinagar Ilam Diktel Bhojpur Charikot Baijanath SWDFSTP a SWDP Hupsekot Land Land Land available Land Land Land available Land Land available Land Land Land Land Land Land Land available available available available available available available available available available available Structure Construction of N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Community Building ongoing (Relocation/comp ensation) Trees/Crops N/A N/A Complensate N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A d

1

Semi-Annual Social Monitoring Report (July to December 2020) IV. SOCIAL SAFEGUARDS CATEGORY AND INVOLUNTARY RESETTLEMENT IMPACT

29. The category of UWSSP is "B" in terms of Involuntary Resettlement. Resettlement Framework and Indegenous Peoples Framework were prepared to guide the preparation and assessment of subprojects in subsequent phases of the project. Resettlement Plan or Due Diligence Report were prepared for 14 on going subprojects in accordance with ADB, Safeguard Policy Statement (SPS) 2009 and government laws. Additional Indegenous Peoples Plan was prepared for Ilam Subproject.

Table 3: Status of subprojects and its implementation till December 2020 in the UWSSP DEDR Impact on Submission Finalization Name of the Sub Status of Status of Detail Status of DDR / Scope of IR Bid Contract Sn Pkg no. Indigenous Entitlements Presentation of Bid project Feasibility Study Design RP/IPP Impact Invitation Award People with Document Communities 1. Charikot UWSSP, W01 Approved on 23 Submitted to PMO on Disclosed on ADB Site, Not Nil Not 8-Jan-18 15-Jun-18 IFB 29-Mar, Dolakha June 2016 30-11-2016 July 2019 Applicable Applicable published 2019 Disclosed on UWSSP 6-8-018 site July 2020 2. Bhojpur UWSSP, W02 Approved on 24- Submitted to PMO on Disclosed on ADB Site Not Nil Not 26-May-18 8-Jul-18 IFB 31-Mar- Bhojpur 11- 2016 25 -01- 2017 Disclosed on UWSSP Applicable Applicable published 2019 site July 2020 31-8-018 3. Diktel UWSSP, W04 Submitted on 30-6-Design Disclosed on ADB Site Not Nil Not 24-May-18 4-Jun-18 IFB 27- Mar- Khotang 2017 & submitted on Applicable Applicable published 2019 Presentation 23-02-2018 Disclosed on UWSSP 5-10- on 21-1-2018 site July 2020 2018 4. Ilam UWSSP , Ilam W05 Done by Submitted on Disclosed on ADB Site, Not Medium impact at Not 11-Feb-18 8-Jul-18 IFB 31-Mar, PPTA 1-02-2018 July 2019 Applicable Intake site and Applicable published 2019 livelihood 31-8-018 Disclosed on UWSSP enhancement site July 2019 support will be provided. Working IP Action plan was finalized on December 2019. IP Households survey/selection was completed in 2020. 5. Chainpur UWSSP, W07 Approved 0n 26 Submitted to Disclosed on ADB Site Not Nil Not 21-Feb-18 Sept 2018 IFB 7-Apr- Bhajhang June 2016 PMO on 24 August Disclosed on UWSSP Applicable Applicable published 2019 2016 site July 2020 28-11- 2018

6. Liwang UWSSP, Rolpa W06 Approved Submitted to Disclosed on ADB Site Not Nil Not 6-Apr-18 Sept 2018 IFB 10-Jul- PMO Disclosed on UWSSP Applicable Applicable published 2019 site July 2020

2

Semi-Annual Social Monitoring Report (July to December 2020)

DEDR Impact on Submission Finalization Name of the Sub Status of Status of Detail Status of DDR / Scope of IR Bid Contract Sn Pkg no. Indigenous Entitlements Presentation of Bid project Feasibility Study Design RP/IPP Impact Invitation Award People with Document Communities 7. Pragatinagar UWSSP, W10 Completed Submitted to Disclosed on ADB Site Not Nil Not 3-Apr-18 Sept 2018 IFB 8-Sept- Dang PMO on Disclosed on UWSSP Applicable Applicable Published 6-2019 28-12- 2018 site July 2020 08-2019

8. Siddhanath - Baijanath, W02 Completed Submitted to Disclosed on ADB Site Applicable Nil Applicable as 23-Feb-18 Sept 2018 IFB 19-Aug- UWSSP, Kanchanpur PMO on 6-12-2018 Disclosed on UWSSP per RP published 2019 site July 2020 7-03- 2018 9. Shuva ghat UWSSP, W09 Completed Submitted to Disclosed on ADB Site Applicable Nil Applicable as 9-Apr-18 Oct 2018 IFB 15-Jul-2019 Surkhet PMO on 13 Disclosed on UWSSP per RP Published Dec 2018 site July 2020/RP 10-04-2019 10. Khalanga UWSSP, W08 Completed Submitted to Disclosed on ADB Site Not Nil 18-Feb-18 Published October Darchula PMO on 22 Disclosed on UWSSP Applicable 8,2020 Dec 2019 site July 2020 11. Brihat Bhanu UWSSP, W11 Completed 22 Aug, 2018, Under Preparation Nil Not 2 Apr, 2019 Dec, 2019 Tanahu phase Applicable 12. Panchkhal UWSSP, W14 Completed 31 Aug, 2018 Disclosed on ADB Site Not Nil 6 Oct, 2018 Dec, 2019 29 Kavrepalanchok Disclosed on UWSSP Applicable June2020 site July 2020

13. Kanchanrup UWSSP, W12 Completed 9 Sept, 2018 Under Preparation Nil 15 Nov, 2018 Mar, 2020 Saptari phase 14. Rampurtar UWSSP, W13 Completed 27 Sept, 2018 Dropped 3 Jun, 2019 Sept, 2019 Okhaldhunga 15. Deurali -Hupsekot W16 Completed 8 May, 2019 Disclosed on ADB Site Nil 21 Jun, 2019 Dec, 2019 29 UWSSP, Disclosed on UWSSP June2020 Nawalpur site July 2020

16. Charikot DEWATS, W19 Submitted Design on process Cleared by ADB Not Nil Not Dec, 2019 Published Dolakha MP on 22 Disclosed on UWSSP Applicable Applicable Dec 2017 December 2020

17. Bhojpur DEWATS, W21 Sanitation Survey work on Under Preparation Dec, 2019 Bhojpur Master Plan process phase Submitted 18. Dadikot UWSSP , W20 Process Cleared by ADB 26 Nil Published Bhaktapur January 2021 Disclosed on UWSSP January 2021

19. Katahariya Storm WaterW22 Completed Approved Disclosed on ADB Site, Not Nil Not Published 12 Nov Drainage Project, June2020 Applicable Applicable 2020 Rautahat

3

Semi-Annual Social Monitoring Report (July to December 2020)

DEDR Impact on Submission Finalization Name of the Sub Status of Status of Detail Status of DDR / Scope of IR Bid Contract Sn Pkg no. Indigenous Entitlements Presentation of Bid project Feasibility Study Design RP/IPP Impact Invitation Award People with Document Communities Disclosed on UWSSP site July 2020 20. Tikapur Storm Water pW18 Submitted Detailed Survey Disclosed on ADB Site Nil Sept, 2019 Published 30 Dec Drainage and Faecal Master Plan Completed/Approved Disclosed on UWSSP 2020 Sludge Management on 17-12-2017 site July 2020 Project 21. Sharadanagar W15 New Comment Received from Nil UWSSP, Chitawan ADB 22. Madi UWSSP, Palpa W17 New Feasibility study Phase(To be replace by Purnagiri/ Gorushinghe)

4.1 Approach and Methodology of Social Safeguard Monitoring Report 30. This semi-annual monitoring report is prepared based on the available Due Diligence Reports and monthly reports submitted by RDSMCs to the RPMO by the end of December 2020.

31. The project progress report, DDR reports and other relevant documents were also thoroughly reviewed prior to preparing this report. Policies, legislations and guidelines relevant to the project are also referred.

4

Semi-Annual Social Monitoring Report (July to December 2020)

V. COMPENSATION, REHABILITATION AND MITIGATION MEASURES

32. Land acquisition activity is not associated under the Loan 3711-NP for Urban Water Supply Sanitation (Sector) Project.The Land Acquisition Act (LAA) 2034 (1977A.D) sets out compensation standards and benefits such as compensation for lost assets at market value, provision for alternative land and compensation for standing crops and trees. To cover resettlement related requirements of the Project Affected Persons (PAP's), under Loan 3711-NP, a Resettlement policy Framework is in place. The policy ensures benefits to non-titled persons such as encroachers, squatters, shared croppers and informal tenant with appropriate displacement allowances for relocation and income restoration assistance. The Compensation Determination Committee (CDC) headed by Chief District Officer is responsible for evaluation of property and its compensation.The resettlement framework emphasizes that compensation should enable project affected people to maintain the existing to better standard of living.

33. As per the monthly reports and resettlement due diligence reports prepared by DSMC of each subproject no affected person or households are found.

34. Most of the subprojects under UWSSP are/will be implemented either on government lands (owned by government roads) or within the RoW of Public Road owed and maintained by respective municipalities. WUSCs or Local governments have assured that required land will be provided to use to the project.

35. Temporary impacts to traffic/access to shops and residences due to digging and excavation of trenches for laying of water supply pipe line are mitigated by ensuring access to properties, through provisions of pedestrian wooden walkways, provision of adequate signage, and careful traffic management. In some areas, traffic diversions with prior planning and proper traffic management plan by the contractors in consultation with the traffic police authorities and the community were required. The community people were duly informed about the subprojects and consulted before start of civil work. The mitigation measures were implemented at the sites. The photographs are attached in Appendix 3.

36. Compensation and mitigation measures include the following: 37. During the reporting period updating of RP/DDR of all sub projects under construction phase and contract awarded were completed and approved by ADB. During previous reporting period compensation worth NRs.49, 789 to one of the informal land user was processed for payment but it was delayed due to pandemic and countrywide lockdown.

38. Mr. Bhim Raj Gharti Magar, 65 years old, resident of Gurbhakot Municipality, ward no 6 was possessing public land/Gurbhakot Municipality a total area of 7-0-0-0 (Seven Ropanis, that is, 3561.0 square meter) land within the Municipality. Out of this possessed area, Bhim Raj Gharti, had provided Subhaghat Water Users and Sanitation Committee 440 sq m. land for construction of physical structures including road tracks, tanks and generator house under Shubhaghat Urban Water Supply and Sanitation Sector Project. Although he was entitled to receive NPR 49,789.00 (In words forty-nine thousand seven hundred eighty-nine rupees only) from Subaghat UWSSP as compensation to permanent loss of agriculture land, compensation for crop loss, income restoration and permanent loss of agriculture based livelihood. He and his family didn’t want to receive the amount as compensation and they decided to voluntarly donate the compensation amount to the subproject. Furthermore, they assure not to claim compensation in future too. They have provided a consent letter for voluntary donation of compensation amount for the subproject. The detail third party verification/recommendation is attached in Annex-6.

5

Semi-Annual Social Monitoring Report (July to December 2020)

Table 4: Resettlement Plan Implementation Status of sub-projects

Income Compensation Deed Public infrastructure restoration Remarks payment transfer reinstated/New Structure Name of training S. No. subproject Ac Achi Target Achieve % Target % Target hie % Target Achieve % eve ve Chainpur, Not 1 Bajhang Applicable

Siddhanath Community 2 NA NA NA 1 0.90% 0.90% Baijanath Building Voluntary donation of compensatio n amount. Shubhaghat, The third 3 49,789 _ _ NA NA 100% 100% Surkhet party verification letter is attached in Annex 6. Not 4 NA NA NA Liwang,Rolpa Applicable Pragatinagar Not 5 NA NA NA ,Dang Applicable Khalanga, NA NA NA NA NA Not 6 Darchula Applicable Tikapur NA NA NA NA NA Not 7 SWD&FSTP, Applicable Kailali Not 8 NA NA NA Ilam, Ilam Applicable Not 9 NA NA NA Bhojpur Applicable Not 10 NA NA NA Diktel Applicable Katahariya 11 SDP Not 11 NA NA NA Charikot Applicable 1

2 1

3 Total 49,789 23.61%

6

Semi-Annual Social Monitoring Report (July to December 2020)

VI. PUBLIC PARTICIPATION AND CONSULTATION

39. Consultations: Consultations were carried out with local people, organizations and other stakeholders during the implementation phase. The field team of the project have made various consultations and meetings at local level in ongoing subprojects. COVID 19 is affected to continue such consultations in the last 6 months. However following basic safety measures; interactions and communication with community people, local organizations and other stakeholders were carried out at the implementation sites. During project preparation, feasibility study, detail design and implementation phase; team leader of DSMC, Social Safeguard Specialist and GESI Specialist of DSMC visited the project municipalities several times and consulted with the community people, local organizations and other stakeholders. Local representatives of political parties, school teachers, business persons, women, representative from Indigenous people and vulnerable groups were contacted in different project locations for consultation and disclosures about the project, its impacts and measures to be adopted for mitigating the negative impacts. Queries raised by the communities including indigenous people in regard to the project, its activities and impacts were well addressed. In implementing all subprojects, interaction and meeting was continued by the PMO representatives, project consultant team, WUSCs and contractors in the project sites. Another part of the disclosure was to answer questions raised by the communities including affected persons with regard to the project, its activities and impacts. The consulted people were informed about different aspects of the projects and likely resettlement impacts and mitigation measures. They were also informed about the (i) process of assessing resettlement impacts during feasibility and detail design, (ii) process of compensation determination in accordance to the Land Acquisition Act 1977 and provisions of compensation. (Photographs in annex - 3).

40. Western Region: Regular field visit to construction sites and interaction with community people were carried out to assess and monitor the social issues. Such site visits and community interactions were carried out for OBA data collection and eligible household selection.

41. Eastern Region: September to November 2020, Training Need and Assessment (TNA) household survey conducted by district consultant team for implementation of IPP. After the completion of TNA household survey, ERDSMC team conducted Training Need and Assessment (TNA) workshop in 26 December 2020 in Sandakpur Ward No-2 under the chairmanship of Sandakpur Rural Municipality chairperson. Workshop was conducted with presence of PMQAC, ERDSMC, WUSC and contractor representatives. The purpose of workshop was to finalize selection of IPs fro livelihood enhancement training. Discussion was held on provision of IPP in UWSSSP and categorization livelihood enhancement training of IP. The minutes of consultation and training participants' attendance sheet attached in Annex-2.

42. Central Region: In implementing Charikot subproject, interaction and meeting was continued by the PMO representatives, project consultant team, WUSC and Contractor in the project sites. Especially at the locality of Bhimeshwor Municipality, Ward No. 7, Makaibari, joint team of the project visited and interacted with the people and continuous efforts made to address their issues and concerns to make conducive environment in the construction sites. The consulted people were informed about different aspects of the project and possible measures to be addressed their demands under the project’s provisions. The consultations and training participants' attendance sheet attached in Annex-2.

43. Training and Orientation on UWSSP: A two days orientation programs on project introduction, working modalities, different components including social safeguard were organized on 24 and 25 December 2020 at Panchkhal UWSSP and on 29 and 30 December 2020 at Deurali Hupsekot UWSSP. Participants of the training were Mayor/Chairperson of the Municipality/Rural Municipality and Ward Chairpersons, Ward Members, WUSC Members, Contractors representatives, representatives from local community organizations, ICG Engineer and Staff and

7

Semi-Annual Social Monitoring Report (July to December 2020)

field level Consultants team. Total 46 persons (Male 31 and Female 15) in Panchkhal and 54 persons (Male 43 and Female 11) in Hupsekot participated in the training. (Attendance of Participants in Appendix- 1). Overview of the training are as follows:

Major Objectives: 44. The main objective of the orientation program was to disseminate the procedural steps of the project, importance of UWSSSP, GESI, Social safeguard and WASH etc. The orientation was helpful in understanding about UWSSSP, GESI and social safeguard and their arrangements in UWSSSP including WASH related activities.

Major contents: • Introduction of UWSSSP, its policy and approach • Contract management and its management in UWSSSP • Role and responsibility of stakeholders • Arrangement of GESI in UWSSSP • Provision of social safeguards in UWSSSP • Output Based Aid (OBA) activities in sub project • Environment impact and EMP implementation

Methodology: 45. The following approaches and methodologies applied to achieve the objective. • Methods such as short lecture, discussion, question and answer etc. • Participatory approach in interaction and discussion to encourage participants for active participation. • Power point presentation of each topic presented. • Materials supports will be provided to all participants.

Inauguration and closing ceremony: 46. Inauguration and closing ceremonies were conducted informally. In orientation of Panchkhal UWSSP, inauguration and closing program was held on the Chairmanship of Mr. Kumar Prasad Lamichhane (Chairperson of WUSC). Mr. Mahesh Kharel (Mayor of Panchkhal Municipality) was the Chief Guest of the program and Mrs. Laxmi Danuwar (Deputy Mayor of Panchkhal Municipality) was a Special Guest at the program.

47. Similarly, in Deurali Hupsekot WSSP, inauguration and closing program was held on the Chairmanship of Mr. Mekh Bahadur Pulami (Chairperson of WUSC). Ms. Laxmi Pande (Chairperson of Hupsekot Rural Municipality) was the Chief Guest of the program.

Output of the Orientation: 48. After completion of orientation program of subprojects, the program found to be fruitful and successful in achieving its objectives as envisaged. The participants of the orientation programs improved their knowledge about the project and they are able to say as follows; i) general introduction about UWSSSP, its process and approach; ii) role and responsibility of stakeholders; iii) GRM and role of GRC in mitigation of social issues; iv) provision of social safeguard in UWSSSP; v) environment impact and EMP implementation; vi) arrangement of GESI in UWSSP; vii) OBA activities and implementation process.

49. Resource persons of respective subject specialist presented the topics as follows: • Introduction, working modalities and scope of UWSSP, • Roles and responsibilities of stakeholders, • Technical features/components of subProject, • Basic concept of GESI, Project provision of inclusive WUSC, GESI action plan, • Basic concept of social safeguards 8

Semi-Annual Social Monitoring Report (July to December 2020)

• Project requirements • Covid-19 safety and protocols • Contract management and procurement process • Basic concept of environmental issues and requirement of project, prevailing rules and regulations • GRC formation (Importance and procedure) • Introduction of OBA & its implementation • Tariff setting and subsidies for poor

50. Out of 100 participants in the two events of orientation program, 26 percent female participated. Similarly 14% Dalit and 30 % Janajati were also involved in the orientations. Participants were found satisfied as per response and they are fully aware and gained knowledge about project implementation procedures.

51. Orientation on CLS and OHS to Contractor/Labors: The orientations were conducted for the Contractors and Labors on 26 December 2020 and 31 December 2020 in Panchkhal and Deurali Hupsekot projects respectively. Representative of Construction Company and Labors participated in the orientation programs. Out of 71 participants, 25 Labors participated in Panchkhal WSS and 46 Labors participated in Hupsekot WSS.

52. The main objective of the orientation on Core Labor Standard (CLS) and Occupational Health and Safety to Contractor/Labors was to disseminate the procedural steps of the project, importance of UWSSSP, GESI, Social safeguard and WASH etc. The orientation focused on National CLS, gender equality in wages, gender based violence (including sexual exploitation and human trafficking) and occupational health and safety sanders. Contents of the Orientation:

• Introduction of UWSSSP, its policy and approach • Contract management and its management in UWSSSP • National CLS, gender equality in wages, gender based violence • Arrangement of social safeguard in UWSSSP • Environment impact and EMP implementation

Methodology:

53. The following approaches and methodologies applied to achieve the objective. • Methods such as short lecture, discussion, question and answer etc. were used. • Participatory approach for interaction and discussion to encourage participants for active participation. • Power point presentation of each topic was presented. • Sanitation materials support provided to all participants.

Outcome of the Orientation: 54. After completion of the orientation programs the programs found to be fruitful and successful in achieving its objectives as envisaged. The participants of the orientation programs increased their knowledge and able to say about the project and other related subjects as follows: understanding of Core Labor Standards (CLS), its importance and implication, environment impact and health and safety measures, gender equality in wages and gender based violence and social safeguard in UWSSSP.

55. Resource persons of respective subject specialist presented the topics as follows: ➢ Introduction, working modalities and scope of UWSSP ➢ Roles and responsibilities of stakeholders

9

Semi-Annual Social Monitoring Report (July to December 2020)

➢ Basic concept and importance of core labor standards ➢ Mandates of CLS in construction works in UWSSSP supported by ADB ➢ Gender equality in wages gender-based violence ➢ Mandates and requirements in construction works in UWSSSP supported by ADB ➢ Occupational health and safety standards, Covid-19 safety and protocols

56. Out of 71 participants, all participants were male due to absence of female labors in the construction sites at present. Similarly 21.13% Dalit and 53.52 % Janajati were participated in the orientation programs.

57. Orientation Program on COVID 19: Awareness program was held at Panchkhal UWSSP on 26 December 2020 and on 31 December 2020 in Deurali-Hupsekot UWSSP in presence of consultant team, WUSC representative, contractor representative and workers. The contractors have prepared COVID-19 response plan. Discussion was concentrated about the present pandemic situation, precaution in this situation while working at site (Following the COVID 19 response plan) and about PPE safety measures. According to the COVID-19 Response Plan, the following COVID 19 safety protocols were included in awareness program.

58. Social distancing: Space (at least 2 meters) between people waiting to enter or leaving site and minimising contact during working.

59. Personal Hygiene Practices: • COVID-19 symptoms, go home and rest • Washing hands with clean water and soap at least for 20 seconds frequently or use sanitizer after contact. • Use of clean cloth, handkerchief or elbow for sneezing or coughing. Clean hands after coughing or sneezing thoroughly by using soap and water (minimum for 20 seconds) or with sanitizer was instructed. • Avoiding touching nose, mouth, eyes and face • Avoid close contact with people • Avoid unnecessary contact with surfaces used by others. • Use of clean mask appropriately and do not share. • Avoid unsafe contact with wild animals or other animals • Consume properly cooked meats items. • All will be encouraged to carry their own water bottle for drinking and will not be shared • Use of Personal Protective Equipment (PPE) appropriately and properly.

60. The summary of orientation/consultation meetings/trainings conducted so far during this semi- annual period (July - December 2020) is summarized in Table-5.

10

Semi-Annual Social Monitoring Report (July to December 2020)

Table 5: Consultation, Orientation and Training matrix Nos. of Type of Discussed S.N. Date Location Decisions/ Conclusions Participants Participants Issues Western Region Chainpur Sub- Project 10th July 2020 M-14 WUSC member RPMO team, Bill disbursement (IPC 4). WUSC Office Meeting among consultant team, RPMO team, F-3 Contractor representative 1. Contractor representative and WUSC team about bill

disbursement (IPC 4) 10th July 2020 WUSC Office M-14 WUSC member RPMO team, Bill disbursement (IPC 4). F-3 Contractor representative Meeting among consultant team, RPMO team, 2. Contractor representative and WUSC team about bill disbursement (IPC 4)

20th July 2020 Ward No. 9 Office, Dewal M-20 RPMO, RDSMC, Aware about OBA Implementation steps Meeting about selection process of eligible 3. Bajhang F-12 WUSC, Contractor households for OBA & Selection committee formation 28th July 2020 Rithapata; Dewal M-15 RPMO, RDSMC, Aware about WASH and COVID. Awareness program about WASH, Hand washing, 4. F-12 WUSC, community members COVID-19. Ward No. 9 Office, Dewal M-5 Consultant Staff/WSUC/ICG Meeting for OBA Eligible selection committee about Aware about OBA HH selection criteria 5. 30 th July 2020 Bajhang F-3 the Selective household Under OBA. 6th August 20 Ward No. 9 Office, Dewal M-9 RPMO, RDSMC, Evaluation & selection of eligible household. Aware about OBA HH selection procedure 6. Bajhang F-3 WUSC, community members 18th August Ward No. 10 Office, M-17 RPMO, RDSMC, Aware about OBA HH selection procedure 7. 20 20 Chainpur F-10 WUSC, community members Evaluation & selection of eligible household.

6th September WUSC Office Chainpur M-10 RPMO, RDSMC, Decided to request permission from WUSC meeting on pipeline expansion in market area 8. 2020 F-4 WUSC, community members Jayapriyhivi Municipal office. and permission from the municipality 18th September Consultant Office (Ward M-17 RPMO, RDSMC, Meeting for selection of eligible HHs under OBA Decided to identify the eligible household 9. 2020 No. 10) F-4 WUSC, community members among consultant team, WUSC members, RPMO under OBA by the monitoring committee Team, Ward level representative and water users. as per the criteria. 23rd September, WUSC Office , Chainpur M-15 RPMO, RDSMC, Meeting about the selection of needy & poor eligible Decided that the applications received 2020 Bajhang F-3 WUSC, community members household under OBA from selection committee from the poor and needy households under OBA Program from Jayapriyhivi Municipality ward 10/11 would be 10. identified/selected by the monitoring team (coordinator of OBA program/ committee/ Chainpur Water Supply and User’s Committee/RPMO/ ITECO Nepal).

11

Semi-Annual Social Monitoring Report (July to December 2020)

Nos. of Type of Discussed S.N. Date Location Decisions/ Conclusions Participants Participants Issues 27th WUSC Office ,Chainpur M-12 RPMO, RDSMC, Agenda: 1-Regarding to extend the time of the It was decided to recommend extension of September-20 Bajhang F-3 WUSC, community members project 180 days as it seemed appropriate to 11. Agenda:2– Regarding variation order No.1 extend the time of the project by 180 days out of the 268 days. 14th October- WUSC Office M-13 RPMO, RDSMC, Regarding the approval of final list of HH under OBA It was decided to endorse the final list of 2020 F-3 WUSC, from different ward applications for OBA grant for HH tap connections and toilet construction which 12. consists of 43 HHs from Ward No # 9, 107 HHs from Ward No # 10 and 3 HHs from Ward No # 11 by publishing the notice in this regard. 15th October- WUSC Office M-11 RPMO, RDSMC, Agenda:1–Regarding IPC-05 2020 F- WUSC, contractor Agenda:2–According toIPC-05, Requesting for loan It was decided, according to IPC-05, Rs from City Development Fund 8088014.81 is collected from contractor Ashish-C.A.B. J.V. of the Chainpur Water Supply and Sanitation Users Project, 13. Bajhang in which 25% of amount under city Development Fund will be Rs. 1963574.66 with VAT 13% (Rs.255364.72) the total amount will be Rs. 2012385.94 which is the amount to be asked for loan from CDF.

nd 2 December, WUSC Office M-11 WUSC members /ICG Regarding the construction of the OBA grant toilet. It was decided to take responsibility by 14. 2020 F- Engineer /Consultant team WUSC themselves to construct the OBA grant toilet.

12

Semi-Annual Social Monitoring Report (July to December 2020)

Nos. of Type of Discussed S.N. Date Location Decisions/ Conclusions Participants Participants Issues 3rd December, Hotel Holiday Inn M-12 PMO,RPMO, PMQAC, ITECO- About OHS, Revised work schedule, Action plan of 2020 F- UNEC Team, WUSC Members, OBA, Site specific work plan, the complete proposal Contractor team of WTP, Agreement between RPMO and WUSC under OBA grant Toilet/Tap. It was decided that the OHS should be maintain at the site of Under construction Phase of different structure. COVID response plan should be follow while working at site. Revised work schedule should be maintain. Action Plan of Out Based Aid (OBA) Should be implemented and complete the OBA 15. action plan in time. Site Specific Work Plan should be made and to review it to complete the project work in time. The contractor should approve the WTP proposal by the consultant. The agreement between WUSC and the RPMO Office Nepalgunj for the OBA program.

Hotel Holiday Inn M-9 WUSC/Contractor/Consultant/I Regarding the 16. Bill disbursement of IPC06. 7th December, F-1 CG IPC 06 112020th December, WUSC Office M-9 WUSC/Contractor/Consultant/I Regarding the OBA grant toilet model. Toilet model under OBA grant has been 17. 2020 F-3 CG selected from the WUSC. 21st December, WUSC Office M-11 RPMO Chief/ RPMO Engineer Regarding the agreement between WUSC and Decided to finish the agreement process 2020 F- and the team /WRDSMC/ EMP beneficiaries for the OBA grant Toilet and Tap. between Beneficiaries (ward 9,10 & 11) 18. /SM/ WUSC Chairperson and WUSC Chainpur, Bajhang within the month 30th December, WUSC Office M-11 WUSC/Consultant team /ICG Regarding the selection of candidate for plumbing Decided to send the male and female 19. 2020 F- Engineer training candidate for the plumbing training.

Siddhanath Baijanath Sub-Project

13

Semi-Annual Social Monitoring Report (July to December 2020)

Nos. of Type of Discussed S.N. Date Location Decisions/ Conclusions Participants Participants Issues 1st July 2020 Awareness program in M-17 Consultant, and community OBA and Wash Aware about OBA and Wash presence of tole sanyojak F-5 members and other beneficiaries about OBA and WASH 1.

3rd July 2020 WUSC M-8 Consultant, Contractor and IPC#3 Recommendation for payment of IPC#3 2. F-6 WUSC from CSE and WUS

24th July 20 Tilachaur M-8 WUSC,.RPMO, Consultant Community meeting Sub project related F-3 17th August WUSC M-6 WUSC, ICG, Consultant OBA A task force committee was formed to 3. 2020 F-4 finalize the list of eligible HHs for OBA.

18th August Ward 6, 8, 10 M-9 Consultant, and community OBA, COVID-19 community people aware about OBA, 4. 2020 F-3 members, local authorities water conservation and hand washing for prevention of COVID-19 23rd August Construction Site Tilachor M-17 Consultant, and community Hand washing and health and safety protocols Awareness creation to workers involved 5. 2020 F-0 members, local authorities for OHT construction on hand washing and health and safety protocols

Construction Site Tilachor M-13 Consultant, and community Hand washing and health and safety protocols Awareness creation to workers involved 6. 24th August 2020 F-0 members, local authorities for OHT construction on hand washing and health and safety protocols Pasupati tole M-2 Consultant, and community Community Meeting Aware about Water conservation, 4th September- 7. 2020 F-23 members, local authorities, Sustainable hygiene behavior and WASH WUSC Janahit tole M-7 Consultant, and community Community Meeting Aware about Water conservation, 8. 6th September- F-3 members, local authorities, Sustainable hygiene behavior and WASH 2020 WUSC 10th September-Thapa chock M-5 Consultant, and community WUSC Meeting Aware about Water conservation, 9. 2020 F-4 members, local authorities, Sustainable hygiene behavior and WASH wusc Ward no 8,6,10 M-180 Consultant, and community Information sharing on Water conservation, Aware about Water conservation, 20th September- F-249 members, local authorities, Sustainable hygiene behaviour and WASH Sustainable hygiene behavior and WASH 10. 2020 WUSC

Ward no.6 M-5 Consultant, and community OBA application selection OBA application selection 21st September- 11. F-3 members, local authorities, 2020 WUSC

14

Semi-Annual Social Monitoring Report (July to December 2020)

Nos. of Type of Discussed S.N. Date Location Decisions/ Conclusions Participants Participants Issues 22nd September-Pasupati tole M-4 Consultant, and community OBA application selection OBA application selection 12. 2020 F-2 members, local authorities, WUSC WUSC Office M-12 WRPMO, WUSC, ICG, Rate negotiation of VO-01 Rate negotiation of new items which were 9th October- F- 6 Consultant and Contractor not included in BoQ was done and 13. 2020 decision was made.

10th October-ward no.10 school building M-24 WUSC and Water users WASH and OBA activities Aware about OBA implementation step 14. 2020 F-3 and WASH

12th October-WUSC Office M-9 WUSC, ICG, Consultant and Regarding VO-01 Different issues of VO-01 have been 15. 2020 F-2 Contractor discussed and forwarded.

16th October-Tilachaur M-27 WUSC and Water users WASH and OBA activities Aware about OBA implementation step 16. 2020 F-4 and WASH WUSC M-3 WRPMO, WUSC, ICG, Regarding Public Toilet The required land area of 14m*12m for the F-2 Consultant and Contractor construction of public toilet in Siddhanath Baijanath WSSSP has been chosen at 2nd November- 17. Ward 6 near the office of Ward 6, Health 2020 post and . It is decided to request to the Committee of Ward 6 for the allotment of required land. WUSC M-4 WRPMO, WUSC, ICG, Recommendation of OBA selected households The selected households for OBA program F-5 Consultant from Ward 6, 8 and 10 were verified and 24th November- recommended by WUSC and for further 18. 2020 recommendation, the WUSC shall inform the Ward offices and concerned authority via letter. Construction Site Tilachor M-15 RPMO, RDSMC, Information sharing to Office Building and Boundary Aware about health and safety issues 27th November- 19. F-1 WUSC, Contractor wall workers on health and safety. 2020 and community members 28th November- Ward no. 10 M-20 RPMO, RDSMC, Information sharing to Distribution line workers Aware about GESI and safety 20. 2020 F- WUSC ,Contractor regarding GESI and safety at site. 30th November- WUSC M-8 RPMO, RDSMC, Regarding OBA Aware about OBA 21. 2020 F-5 WUSC, Contractor 7th December, M-9 WUSC/Contractor/Consultant/I Regarding the 22. Hotel Holiday Inn Bill disbursement of IPC06. 2020 F-1 CG IPC 06 M-7 WUSC, ICG and Consultant OBA toilet construction The decision made in the meeting 20th December, F-3 23. conducted on 11 December 2020 to be 202020 applicable.

15

Semi-Annual Social Monitoring Report (July to December 2020)

Nos. of Type of Discussed S.N. Date Location Decisions/ Conclusions Participants Participants Issues WUSC M-6 WUSC, ICG and Consultant Selection of name list for the training of plumbing. Following people have been working in F-3 pipeline works of Siddhanath Baijanath WSSSP since the beginning of the work as the representative of WUSC. So the below mentioned name list are selected for the 29th December, plumbing training and after the training they 24. 2020 are allowed to continue the work in the project. Name list: 1.Narayan Singh Rawal 2. Laxmi Khidali 3.Bhan Dev Dhanuk Liwang Sub-roject 8th September, WUSC Office M-9 WUSC members, Ward Progress review and final HH selection for OBA It was decided to approve the final list of 2020 F-4 chairpersons and applications/HHs for OBA grant for HH tap 1. representatives, RPMO, connections and toilet construction. WRDSMC and contractor 8th September, WUSC Office M-9 WUSC members, Ward Progress review and final HH selection for OBA It was decided to approve the final list of 2020 F-4 chairpersons and applications/HHs for OBA grant for HH tap 2. representatives, RPMO, connections and toilet construction. WRDSMC and contractor 4th October, WUSC Office M-8 WUSC members, Ward Progress review and final HH selection for OBA. It was decided to approve the final list of 2020 F-4 chairpersons and applications/HHs for OBA grant for HH tap 3. representatives, RPMO, connections and toilet construction. WRDSMC and contractor 17th December, WUSC Office M-11 WUSC members, Ward Discuss about the selection of plumber and how to Discuss about the selection of plumber 4. 2020 F-5 chairpersons, RPMO, provide fund under OBA and how to provide fund under OBA WRDSMC and contractor. Subhaghat Sub-Project WUSC Office M-12 WUSC, Consultants, ICG and Planning of Construction work progress for coming Contractor accepted that they will continue F-3 Contractors month and manage Indian experience skill workers building work/RVT work during rainy during this time. season and manage Indian skill WUSC, J. Engineer absent from site without any experience mason for this work during this information. pandemic time. Contractors vehicle busy her own works and not Warning letter to J.Engineer why he 1. 22nd July-2020 fully site supervision work due to project vehicles, absent from site and may be another So all minute people request to Regional Manager technician will be manage WUSC group. to provide Project Vehicle during this Pandemic Request to RPMO and PMO to provide Situation as soon as possible. Project Vehicle during this Pandemic Situation as soon as possible.

16

Semi-Annual Social Monitoring Report (July to December 2020)

Nos. of Type of Discussed S.N. Date Location Decisions/ Conclusions Participants Participants Issues WUSC Office M-12 WUSC, Consultants, ICG and Planning of Construction work progress for coming Contractor accepted that they will continue F-3 Contractors month and manage Indian experience skill workers building work/RVT work during rainy during this time. season and manage Indian skill 2. 22nd July-2020 experience mason for this work during this WUSC J.Engineer absent from site without any pandemic time. information. Warning letter to J.Engineer why he absent from site and may be another WUSC Office M-9 WUSC/DSMC/ICG/Contractor Contractors- WUSC Junior vehicle engineer busy extensionher own works time. and not technicianOne-month will extension be manage time WUSCextend group.and F-04 fullyOBA site Verification supervision work work due to project vehicles, Requestwatch her to performance RPMO and PMOduring to site provide work. SoWUSC all minute copy of people our project request document to Regiona needl Manager Project ProjectOBA verification Vehicle during work startsthis Pandemic from 5th toDrawing, provide Contract Project Vehicleagreement during and this Specification Pandemic SituationAugust for as 6 soonno’s wards.as possible. 3. 1st August 2020 Situationbook also. as soon as possible. Co-ordinate from RPMO for this project WUSC project vehicle hand over documents drawing, Contracts documents and Specification book. Project Vehicle handover by PMO to WUSC. WUSC Office M-8 WUSC and Consultant Due to COVID-19 Be safe and during construction Be safe and careful from safety and Covid- F-5 time take care self from covid-19 with social 19 also and maintain social distance distance maintain during construction time and take care of body with self-responsible 4. 5th August 2020 Safety education each day aware to workers before start of work every day by EMP and aware from Covid -19 education to workers also. WUSC Office M-14 WUSC/Consultant/ICG and Safety and Covid-19 education aware to worker Be safe and careful from safety and Covid- F-4 contractor before start work 19 also and maintain social distance during construction time and take care of body with self-responsible Health and Safety committee organize Safety education each day aware to Extension time not extended to WUSC, Junior workers before start of work every day by th 5. 14 August 2020 engineer for coming month EMP and aware from Covid -19 education to workers also. Health and safety committee organise by EMP Decision of extension time not extended to WUSC Junior engineer for coming month. WUSC Office M-9 WUSC/DSMC/ICG/Contractor WUSC Junior engineer New candidate Appointment Minute decision new candidate JE quickly 23rd September- 6. F-5 appointment for this vacant post. 2020

WUSC Office M-8 WUSC/DSMC/ICG/Contractor Problem/issues during Transmission pipe line Problem solved after discussion and 27th September- 7. F-2 excavation work continued the pipe line excavation and 2020 laying work

17

Semi-Annual Social Monitoring Report (July to December 2020)

Nos. of Type of Discussed S.N. Date Location Decisions/ Conclusions Participants Participants Issues WUSC Office M-11 WUSC, Consultants, ICG and Discussion about Variation order to Negotiation of Decision of rate negotiation of fitting rate 11th October- 8. F-3 Contractors Fitting rate for DI & GI, New items and Place for GI/DI fittings and new items and new 2020 selection for Public toilet place selection for Public toilet. 13th October-WUSC Office M-9 WUSC, Consultants, ICG and Forwarded of IPC-4 Recommendation and forwarded for IPC-4 9. 2020 F-3 Contractors 11th November WUSC Office M-8 WUSC, Consultants, ICG and VO-1 submitted for new items and remaining items Recommendation and forwarded to VO-1 10. 2020 F-5 Contractors for new items and remaining items. 6th WUSC Office M-19 WUSC/ICG/Consultant/Contrac IPC-05Recommended and Forwarded for payment. Recommendation and forwarded to IPC- 11. December.2020 F-4 tor 05 for Payment. WUSC Office M-11 WUSC/ICG/Consultant/Contrac Facilitated for Poor water users people who Decision for Selection of poor water users 22nd December- F-5 tor benefited from OBA Selection for house Water which focalized of OBA for water 12. 2020 Connection and Toilet connection and Toilet

Pragatinagar Sub- Project WUSC Office M-11 WUSC /Consultant/ICG Payment of IPC-01 (TDF part) TDF is requested to send the amount for 1. 13th July 20 F-6 Engineer the payment of IPC-01 (TDF parts). WUSC Office M-11 WUSC /Consultant/ICG Payment of IPC-01 (TDF part) TDF is requested to send the amount for 2. 13th July 20 F-6 Engineer the payment of IPC-01 (TDF parts).

WUSC Office M-10 WUSC / Consultant Application for OBA program and sub-engineer Decided to increase the date of F-6 applications from related people for public toilet and house connection assistance. 3. 23rd July 2020 Decided to publish the notice for the application for the appointment of sub- engineer. WUSC Office M-6 WUSC /Consultant To bring vehicle from Kathmandu It is decided to bring vehicle from To deposit TDS money in the tax office Kathmandu F-5 It is decided to deposit TDS money in the th 4. 29 July 2020 Fee for Water Supply Service Tax office, Tulsipur, Dang It is decided to increase 1.5% water supply service fee from Bhadra 01, 2077. WUSC Office M-8 WUSC / Consultant Time extension of application for Sub-Engineer It is decided to extend 15 days for the OBA program application of sub-engineer

F-5 Bank account of WUSC for retention money It is decided to form verification committee th 5. 10 August 2020 to verify the OBA application It is decided to open new Bank Account of WUSC for the retention money

18

Semi-Annual Social Monitoring Report (July to December 2020)

Nos. of Type of Discussed S.N. Date Location Decisions/ Conclusions Participants Participants Issues WUSC Office M-16 WUSC / Consultant/ Water Extension of pipe line It is decided to extend the pipe lines in the users To solve the grievance required places 6. 22ndAugust 2020 F-3 The grievance is solved by deciding the Grievance Committee extension of pipe line in the demanded members area. WUSC Office M-8 WUSC / Consultant To publish the name of sub- engineer to participate It is decided to publish the name of sub –

th F-5 in the examination and formation of sub-engineer engineer for examinations and form 7. 26 August 2020 selection committee selection committee for sub-engineer selection. WUSC Office Office M-9 WUSC /Consultant/ Regarding correction of name in registration Requested ward no-05, 07 and 08 ward 21st September- F-3 certificate of the project offices to provide notice for Site clearance 8. 2020 along the pipe lines to water user.

WUSC Office M-4 WUSC/Consultant/ICG Compulsory use of PPE in working site. It was decided that labor should use the F- Regarding speedup the progress PPE such as Helmet, Gloves, Boot, Arrangement of Safe and adequate scaffolding Jacket, Mask etc compulsorily in the Regarding to visit the site working site. As the progress of the work is less than the target, speed up the work by arranging the necessary manpower, construction 27th September- 9. materials and equipment should be 2020 increased. It was decided to arrange the safe and adequate scaffolding. It was decided to visit the site every Friday in a week at 15:00 clock by contractor, Consultant, WUSC Committee and ICG Engineer Jointly. WUSC Office M-5 WUSC / Consultant /ICG Regarding preparation of question paper It is decided to entrust the exam’s question 29th September- 10. F- paper of candidate to Mr. Chandrakant 2020 Jha, CSE Consultancy WUSC Office M-4 WUSC /Consultant/RPMO ICG Regarding the publication of written results It was decided to publish the final results 2nd October- 11. F-1 of written exam conducted on October 2 in 2020 order to qualification of candidates. WUSC Office M-4 WUSC /Consultant/RPMO ICG Regarding the publication of written results It was decided to publish the final result as 2nd October- F-1 per the qualification order on the basis of 12. 2020 written exam and interview taken for sub- engineer.

19

Semi-Annual Social Monitoring Report (July to December 2020)

Nos. of Type of Discussed S.N. Date Location Decisions/ Conclusions Participants Participants Issues WUSC Office M-12 WUSC /Consultant/RPMO ICG Regarding Expenditure Details Regarding Final Name List of OBA It was decided to approve the details of the F-6 expenditure of Asoj 2 to Asoj, 9 2077, which was spent in order to receive the vehicle from Department of Water Supply and 9th-October- Sewerage Management Kathmandu as per 13. 2020 the agreement between the Government of Nepal and the Asian Development Bank It was decided to endorse the final list of applications for OBA grant for HH tap connections and toilet construction. WUSC Office M-7 WUSC/Consultant/ICG Final list of OBA applications It was decided to endorse the final list of F-5 applications for OBA grant for HH tap connections and toilet construction which 14. 9th October-2020 consists of 61 HHs from Ward No # 5, 17 HHs from Ward No # 7 and 129 HHs from Ward No # 8 by publishing the notice in this regard and 28 HHs were rejected. WUSC Office M-9 WUSC /Consultant/ RPMO Regarding progress review A detailed review of the progress was done and encountered the problems faced 24th November- 15. F-2 during working period of the project were 2020 discussed and necessary instructions were given. WUSC Office WUSC /Consultant Regarding OBA Discussed on the model of the toilet 28th November- M-6 16. construction and decided to sing the 2020 F-5 agreement with RPMO. WUSC Office M-7 WUSC /Consultant/RPMO Regarding the IPC 01 The total Bill amount of the IPC 02 is Rs, 3,79,11,505.49 (In words: Three Crore F-6 seventy nine lakhs eleven thousand five hundred five rupees Forty nine paisa only) 7th December- was collected from the contractor Raman- 17. 2020 Sagarmatha JV of Pragatinagar UWSSP Dang. Which has been submitted on 3rd December 2020 and was checked by the consultant & ICG engineer has been recommended and decided on the meeting.

20

Semi-Annual Social Monitoring Report (July to December 2020)

Nos. of Type of Discussed S.N. Date Location Decisions/ Conclusions Participants Participants Issues WUSC Office M-9 WUSC /Consultant Regarding the construction of toilet under OBA Decided to construct the toilet under OBA program. grant by beneficiaries themselves from the F-6 Regarding to attend the meeting which is going to skilled and unskilled labor. The raw held at RPMO Office Nepalgunj for the agreement materials should be provided from the between RPMO and WUSC under OBA Program. suppliers which will be recommended by Regarding correction in name. the WUSC. It was decided the Chairperson Mr. Shanta Raj Sharma will go to RPMO Office Regarding the household tap connection Nepalgunj for the Agreement under OBA program 9th December- Due to there was very difficulties in 18. 2020 documentation work, it was decided to recommend the RPMO Office Nepalgunj for the name correction of WUSC Dang, as “Pragatinagar Urban Water Supply and user’s Committee”. It was decided to recommend that the quantity of pipe for household tap connection is needed only 38000m according to the site condition of Pragtinagar UWSSP whereas the quantity of pipe is mentioned is 48120m in BOQ. WUSC Office M-12 WUSC /Consultant/RPMO Agreement between RPMO Nepalgunj and WUSC According to the UWSSP the agreement of different sub-project of UWSSP under OBA between the RPMO Nepalgunj and the F-2 program. WUSC different of Sub- Project under the Out Based Aid (OBA ) program has been 13th December- 19. decided the model of Toilet should be 2020 selected by the respective WUSC of sub- project and should be written information has to be given to the RPMO Office within 24th December 2020.

21

Semi-Annual Social Monitoring Report (July to December 2020)

Nos. of Type of Discussed S.N. Date Location Decisions/ Conclusions Participants Participants Issues WUSC Office M-8 WUSC /Consultant/RPMO Regarding the office vehicle renewal It was decided that vehicle renewal process F-7 Regarding the selection of Plumber should be done from the Rapti Traffic Office which is located in Bhalubang. It was decided to announce the vacancy for Regarding the agreement between WUSC and the post of plumber and to select the male beneficiaries. and female candidate from poor family for 3 months plumbing training as the application 15th December- 20. fee will be Rs.150. 2020 Regarding the expenditure It was decided to publish the notice about the agreement between WUSC and selected household under OBA program. It was decided to pay the bill amount i.e. Rs 2,200 for the charge of making the notice about to collect connection fee from the water users’. WUSC Office M-8 WUSC /Consultant/RPMO Regarding the bill disbursement of IPC 02. The total bill amount of the IPC 02 is Rs. F-4 37911505.49 is collected from contractor Raman-Sagarmatha J.V of Pragatinagar UWSSP Dang, according to the decision of 7th Dec.2020 in which 5% will be Regarding the Bill payment Rs.20,01,539.36 and the amount to be asked for loan disbursement from the Town Development Fund from 25% will be Rs.92,12,966.15. 17th December- 21. It is decided to pay the charge Rs. 2000 of 2020 Selection of male and female candidate from the marginalized/poor family for the 3 months plumbing notice published from the Today training. Newspaper about to deposit the fee of tap connection of the household. According to the Pragatinagar Urban water supply and sanitation users’ committee, It was decided that the committee has selected the 1 Male and female candidate from the marginalized and poor family for the three months plumbing training.

WUSC M-7 WUSC /Consultant/RPMO Selection of male and female candidate from the According to the Pragatinagar Urban water marginalized/poor family for the 3 months plumbing F-4 supply and sanitation users’ committee, It 31st December- training. was decided that the committee has 22. 2020 selected the 1 Male and female candidate from the marginalized and poor family for the three months plumbing training. Khalanga Sub- Project

22

Semi-Annual Social Monitoring Report (July to December 2020)

Nos. of Type of Discussed S.N. Date Location Decisions/ Conclusions Participants Participants Issues 2nd December- WUSC M-24 WUSC /Consultant/RPMO formation of Grievance committee Two level GRC has been formed 1 2020 F-3 23rd December- WUSC M-4 WUSC /Consultant/RPMO Advance loan from TDF Advance loan from TDF 2 2020 F-1 Central Region Charikot Sub-Project 1 26 July 2020 Site M-16 EMP and SM and local people, Community level awareness program on WASH F-9 labor integrating COVID 19

2 24 July, 2020 Site M-7 Labor force, EMP, SM, OHS session incorporating corona virus message to F-0 labor force

3 22 September, Site M-11 Labor force, EMP, SM, EHS/OHS and Corona Virus protection Environment/Occupational Health and 2020 F-0 Safety (EHS/OHS) orientation integrating Corona virus message and its preventive measures 4 December WUSC office M-15 Muncipality ,WUSC, Regarding the implementation status of the Agreement between local of Makaibari 10,2020 F-4 Consultant and ICG engineer agreement reached with the residents of Bhimeshwor ward no 7and WUSC. Minutes of meetin Municipality-7 attached in Annex-2 center 2&1.

5 December Makaibari-ward no.7 M-49 Local , WUSC and Municipality Interaction and endorsement of 9 point agreement An extensive interaction / discussion was 12,2020 F-9 held with the local users about the implementation status of the 9 point agreement. Minutes of meetin attached in Annex-2 center 2&1. Deurali Hupsekot Sub-Project Site M-43 WUSC, Contractor and Project Information Project details, social safeguards, F-11 beneficiaries environmental safeguards, and GESI 29 & 30 1 aspects December-2020 Minute of meeting annex-2 Orientation to Stakeholders of Deurali -Hupeskot Site M-43 WUSC, Contractor and project Project Information Project details, social safeguards, 31 December- 2 F-11 team environmental safeguards, and GESI 2020 aspects Panchkhal Sub-Project 1 12 November-. Campsite M-7 Labourers, project staff , Awareness event on the occasion of “Global

2020 F-1 contractor team Handwashing Day 2 12 November-. Tindhare 150 cum RVT M-11 Labourers, project staff , Information on OHS corona virus Protection

2020 site F-0 contractor 23

Semi-Annual Social Monitoring Report (July to December 2020)

Nos. of Type of Discussed S.N. Date Location Decisions/ Conclusions Participants Participants Issues 3 Site M-31 WUSC, Contractor and EHS/OHS and Corona Virus protection F-15 beneficiaries Environment/Occupational Health and Safety (EHS/OHS) orientation integrating Corona virus message and its preventive measures. 24 & 25 December-2020 (along with project management, social safeguards and GESI aspects Minutes of meeting attached in Annex2: Orientation to labourers of Panchkhal UWSS Project (25th December 2020)

Eastern Region Ilam Sub Project 1 1 July 2020 Intake area Total- 18 SM and IP people Sandukpur Discussion/Information about poor Household and Information provided about poor Sandukpur2 ( Male- 14 ward no 2 chairman benefit by project Household and benefit by UWSSP project, Female-4 name list collected, Health awareness UWSSP

2 13 July 2020 Intake area Total- 19 EMP and SM and local Public awareness about Project health and Awareness about UWSSP project and Sandukpur2 ( Male- 9 people/IPs sanitation and OBA health Orientation /Discuss about Female-10) safety, health.

3 3 August Site office Total- 8 CSE. SM. ICG site staff Meeting about Public toilet construction and Decision made to write request letter to 2020 ( Male- 5 coordinate local body local body through WUSC 4 24 August Sing fring area Ilam ward Total Female 12 -3 SM and local community Sanitation and Health awareness UWSSP Information dissemination Sanitation and 2020 no 6 Male-4 people Health awareness UWSSP 5 22 September- Sandakpur 2 Todke area TotalFemale 19- 8 SM and local IP community UWSSP and IP provision and TNA survey Information dissemination UWSSP IP plan 2020 Male -9 people and Training Need Assessment (TNA) Female-10 survey

6 24 September- Sandakpur 2 Todke area Total 22 SM and local IP community UWSSP and IP provision and TNA survey Information dissemination UWSSP IP plan 2020 Male -6 people and Training Need Assessment (TNA) Female-16 survey

7 14 October- Ilam ward no 6 area Total-17 CSE, SM , ICG and TNA survey, OBA and Covid-19 awareness Information dissemination about Public 2020 Jordhara Male -3 community people hand wash and no entry in mass movement OBA awareness Covid-19 awareness, hand Female-14 awareness wash and hand wash and OBA awareness

24

Semi-Annual Social Monitoring Report (July to December 2020)

Nos. of Type of Discussed S.N. Date Location Decisions/ Conclusions Participants Participants Issues 8 26 December, Sandakpur 2 Total-38 Sandukpur Rural Municipality Provision of IP plan and Finalization Training Information dissemination Training Need 2020 Maimajhuwa Male -20 chairman, ward chairman, Need Assessment (TNA) survey result Assessment (TNA) survey result and Female-18 CAO PMQAC, ERDSMC, categorized Livelihood enhancement WUSC CSE SM ICG, Local Training for Indigenous people people Name list and minutes of meeting attached in Annex 2 Eastern region Meeting no 8.and Annex -5. Bhojpur Sub-Project 1 19 July 2020 Bhojpur- 12 Total- 6 SM , and community people Information OBA and awareness Covid-19 Information dissemination Sanitation OHS Male- 4 .Health awareness UWSSP and Female-2 awareness regarding Covid -19, hand community people wash and movement

2 6 August, 2020 Site office Total- 11 WUSC ICG CSE Contractor Progress review and Health and safety on Progress Contractor agreed to apply Male- 10 construction work health and safety work for the all ongoing Female-1 construction site 3 23 September, Bhojpur Ward no 12 Total- 10 SM , and community people Information about project Implementation Sanitation Information dissemination about project 2020 Male- 1 and .Health awareness Implementation Sanitation and Health Female-9 4 8 October Bhojpur Ward no 12 Total- 10 SM and community people Information about project Implementation Sanitation Information dissemination about project 2020 Male- 1 and .Health awareness covid -19 awareness Implementation Sanitation and Health Female-9 awareness covid -19 awareness 5 18December,20 Bhojpur Ward no 12 Total- 9 SM , and community project Implementation Sanitation and .Health Information dissemination project 20 Male- 1 people awareness Implementation Sanitation and .Health Female-8 5% amount collection awareness 5% amount collection status Diktel Sub-Project 1 10 July 2020 Diktel ward no 1 Danda Total- 20 EMP, SM , and Information about project Implementation and Information dissemination about project tole Male- 5 community people Sanitation Health awareness Implementation Sanitation and Health Female-15 awareness 2 24 July 2020 Diktel ward no 1 Danda Total- 15 EMP, SM , and community Information about project Implementation and Information dissemination about project tole Male- 1 people Sanitation Health awareness Implementation Sanitation and Health Female-14 awareness 3 3 August- 2020 Diktel ward no 1 Basnet Total- 16 EMP, SM , and community Information about project Implementation and Information dissemination about project tole Male- 9 people Sanitation Health awareness Implementation Sanitation and Health Female-7 awareness 4 4 September- Diktel ward no 2 Cherpa Total- 15 EMP, SM , and community Information about project Implementation and Information dissemination about project 2020 tole Male- 5 people Sanitation awareness Implementation Sanitation and Health Female-10 awareness

25

Semi-Annual Social Monitoring Report (July to December 2020)

Nos. of Type of Discussed S.N. Date Location Decisions/ Conclusions Participants Participants Issues 5 15 October- Diktel ward no 1 santi Total- 8 EMP, SM , and Information about project Implementation & Information dissemination about project 2020 salleri Male- 2 community people Sanitation awareness Implementation Sanitation and Health Female-6 awareness 6 29 November- PMO meeting hall M-13 Project Director, DPD, Detailed Engineering Design Report will be Detailed Engineering Design Report will be 2020. f-0 TDF, Municipality Mayor, prepared for one house one connection in ward prepared for one house one connection in ward chairperson, PMQAC, no 2 & 6 within December 2020. ward no 2 & 6 within December 2020. WUSC secretary, Minutes of meeting attached in Annex-2 Complainer Rabin Rai and Eastern region meeting no 20 affected family representative. 7 10 December- Diktel ward no 2 Tal Total- 19 SM and community people Information about project Implementation & Information dissemination about project 2020 kharkaa tole Male- 7 Sanitation awareness Implementation Sanitation and Health Female12 awareness 8 27 December- WUSC office Total- 32 WUSC CSE ICG SM OBA finalization and Monitoring It is decided OBA list finalize and WUSC 2020 Male- 18 Monitor quality of material of OBA Female14 beneficiaries

26

Semi-Annual Social Monitoring Report (July to December 2020)

VII. GRIEVANCE REDRESS MECHANISM

61. In line with the ADB Project Administration Manual of UWSSP, a first level Grievance Redress Committees was formed in each subproject. The third level (project level) GRC was formed under the Project Director of UWSSP on 6th Feb 2020. The concern DPD, Social and Environment Safeguard officers from PMO and PMQAC environment & social safeguard experts and NEFIN representative as members. Accordingly, all 12 under construction urban subprojects have formed first and second level of Grievances Redress Committees in Ilam, Bhojpur, Diktel, Liwang, Siddhnath Baijanath, Pargatinagar, Chainpur, Shubhaghat, Charikot, Panchkhal and Deurali - Hupsekot WSSP. Two newly contracted SWDP and FSTP subprojects are yet to form the GRC. The list of the GRC Committee has attached in Annex-4. The GRM aims to provide a time-bound and transparent mechanism to voice and resolve social and environmental concerns linked to the project. A common GRM is to be in place for social, environmental, or any other grievances related to the project. The GRM is to provide an accessible forum for receiving and facilitating resolution of affected person‘s grievances related to the project. Every grievance related to project have registered and careful documentation of process with regard to each grievance undertaken and handling. The social safeguards specialist of RDSMC at each project municipality level will have the overall responsibility for timely grievance redress on social safeguards issues. The Social Development Officer at the Regional Project Management Office (RPMO) is the focal person for facilitating the grievance redress at Municipality/Rural Municipality level. A second Grievance Redress Committee (GRC) has been formed at Municipality level, comprising the Mayor as Chairperson of GRC and Regional Project Manager RPMO as Secretary. The GRC members to be comprise of (1) WUSC secretary (2) RPMO Engineer social (3) RPMO social/ environmental (as relevant) officer, (4) representative of affected persons, (5) regional DSMC‘s safeguards specialist (social/environment as relevant), (6) a representative of reputable and relevant CBO/SHG/organization working in the project area as invitee1 and (vi) contractor‘s representative. The secretary of the GRC will be responsible for convening timely meetings and maintaining minutes of meetings. The concerned social safeguards expert of regional DSMC will support the RPMO safeguard‘s officer and Project Manager of RPMO to ensure that grievances, including those of the poor and vulnerable are addressed.

7.1 Record Keeping and Disclosure 62. Records at subprojects are kept by the concerned WUSC Member Secretary of all grievances received including contact details of complainant, date the complaint received, nature of grievance, agreed corrective actions and the date of the incident and final outcome. The number of grievances recorded, resolved and the outcomes are being displayed/disclosed in the PMO and WUSC/municipal/rural municipal office. In addition, it is also reported in the safeguards monitoring reports to be submitted in ADB on a semi-annual basis.

63. The grievances recording system has been in initiated in the entire project sites. The PMQAC Safeguard specialist has instructed all safeguard Specialist of Regional DSMCs to provide a short orientation to all concerned social mobilizes of each project sites about the documentation of grievances at field level. A standard and uniform template for registration and processing was forwarded to all project sites addressing to the safeguard focal person. The summary with matrix of grievances/incidents, including the dates nature of complaints/problems, and how these were resolved (either resolved on-site or through the GRC) are included in this SSMR. During the monitoring period 36 complaints were recorded for the month of July to December 2020 as illustrated in the Table 8.

7.2 Endorsement of agreement reached with Makaibari people in Charikot UWSSP 64. As the Makaibari issue is already resolved and the construction works are smoothly ongoing at the sites, endorsement process of agreement made with struggle group is performed by community level meeting at the Makaibari, Ward No.7 of Bhimeshwor Municipality. A mass meeting was held on 12 December 2020 (BS 2077/08/27) in the presence of local people's

27

Semi-Annual Social Monitoring Report (July to December 2020)

representatives, WUSC members, PMO representative, CRDSMC team, Contractor’s representatives, officials of local organizations and local people including members of struggle groups. All together 58 participants (male 45 and female13) attended at the meeting. During the meeting it was explicitly discussed on progress status of each point of the nine point agreement and finally, the meeting unanimously endorsed the development of the agreement. As the implementation of the nine point agreement was found to be satisfactory on the basis of the detailed discussion held at that meeting, the meeting approved the achievements mentioned in the agreement. It was decided to provide necessary support from the local users to complete the remaining works of the project in a timely manner.

65. In regards, the joint review meeting held on 27th February 2020 had decided to provide authority to the WUSC Chairperson for taking initiation to coordinate the joint meeting of PMO, Municipality, WUSC and other concern stakeholders for endorsement/finalization of previously nine point agreement made with the struggle group. Further discussion on the endorsement process has made in progress review meeting held at Project Management Office on 16 September 2020. The meeting genuinely discussed on the constraints and difficulties at that moment and decided to take initiation with possible alternatives. Further, the meeting had reached on consensus for request to the Chairperson of WUSC to coordinate the endorsement meeting after the WUSC meeting decided on the implementation of agreement.

66. As per the decision, the WUSC discussed on their internal meeting on the progress status of nine point agreement reached with the Makaibari people on 10 December 2020 (BS 2077/08/25). The meeting also decided to make commitment to implement the agreed points of the nine point agreement. The meeting minutes of the community level meeting and WUSC meeting are attached in Appendix-2 Central Region meeting minutes no 1 & 2.

7.3 Chronology of Events 67. The major events developed till date regarding this difference of opinion among Makaibari struggle group and project stakeholders (WUSC, Municipality and project actors) can be listed as follows. Table 6: Chronology of Events in Charikot S.N. Event Date 1 Complaints lodged in ADB NRM by Makalbari Struggle Group led by Mr. 28 November 2019 Deepak Tamang 2 ADB forwarded the complaints to PMO Officials 05 December 2019 3 PMO instructed WUSC to resolve the issues in consultation with 9 December 2019 Municipality, District Administration Office, Bhimeshor Ward No 7 elected representatives, and other concerned stakeholders at local level 4 Same instruction letter dispatched to Municipality and CRDSMC 9 December 2019 5 WUSC held series of discussions at local level with Makaibari Struggle Various Dates group in close consultation with CRDSMC and PMO 6 WUSC Meeting decided to reach a written agreement with the 14 December 2019 complainants within a week 7 In the targeted week for agreement the Leader of struggle group was Since third week of accused of violating some social norms in his community and was in December 2019 police custody after his arrest 8 A joint team of PMO, PMQAC, CRDSMC led by DPD Mr. Ram Kumar 25 December 2019 Shrestha visited the project site to discuss with WUSC, Municipality, District Administration Office, Complainants group and other concerned stakeholders and resolve the issues 9 The joint team of PMO, Bhimeshwor Municipality, WUSC, PMQAC, 26 December 2019 CRDSMC and Contractor had visited the Ward No. 7, Makaibari area for consultation with local people. To identify local residents’ concerns and grievances, a consultation meeting with the community was held on the coordination of Mr. Bharat KC, Mayor of Bhimeshwor Municipality. 10 CRDSMC SSS Mr Samir Dhakal visited Charikot to explore the issues and First week of January their possible solutions 2020

28

Semi-Annual Social Monitoring Report (July to December 2020)

11 A nine point agreement has been reached with the struggle group of 26 January 2020 Bhimeshwor Municipality, Ward No.7, Makaibari. 12 A joint review meeting held for the discussion on 9 point agreement made 27 February 2020 with the struggle group 13 WUSC discussed on their internal meeting on the progress status of nine 10 December 2020 point agreement reached with the Makaibari people.

7.4 Agreement reached with ward no 2 Solma's local user, PMO, Diktel Municipality and PMO: 68. The Issue in Solma ward no 2, regarding the use of water source for Rambakhola, Majkhola and Kaulekhola. The local issues are already resolved and the construction works are smoothly ongoing at the sites. The agreement and summary of meeting are as follows:

• Meeting conducted with complainant (complainer Rabin Rai and affected family representative Kumar Puri), WUSC and PMO on 7 Mansir 2077 (22 Nov 2020) at PMO for settlement of the issue, both the parties have agreed on 13 points out of 14 points (All point resolved except one point remaining (To provide private connection to approximately 368 household of ward no 2&6). • Follow up Meeting conducted at PMO in presence of Project Director, DPD, TDF, Municipality Mayor, ward chairperson, PMQAC, WUSC secretary, Complainer Rabin Rai and affected family representative Kumar Puri and Pramod Rai on 29 Nov 2020.

Agenda of meeting: One household one tap concept in ward no 2 Solma and ward no 6 nearby area of source (approximately 368 Households).

Decision: • Detailed Engineering Design Report will be prepared for one house one connection in ward no 2 & 6 within December 2020 (design estimate is undergoing). • Prepare the implementation modality (framework) between the Municipality and the Project Management Office for the providing safe water to 368 households. (It will be done after receiving the DEDR.) • Decision has been made to resume all the stalled work of the project along with the work of Detailed Engineering Design Report of 368 HHs.

Table 6a: Chronology of Diktel complaint

S.N. Event Date 1 Complaints lodged in ADB NRM by ward no 2 and 6 of Solma 1st and 4th Oct Struggle Group led by Mr. Rabin Rai. 2020 2 ADB forwarded the complaints to PMO Officials 7th Oct 2020 3 PMO responded to ADB on complain; and instructed WUSC to 13 Oct 2020 resolve the issues in consultation with Municipality, District Administration Office, Diktel Majuwagadi Municipality Ward No 2 and 6 elected representatives, and other concerned stakeholders at local level. 4 WUSC held series of discussions at local level with Solma's Struggle Various Dates group in close consultation with ERDSMC and PMO. 5 Meeting conducted with complainants (complainer Rabin Rai and 22 Nov 2020 affected family representative Kumar Puri), WUSC and PMO at PMO 6 Follow up Meeting conducted at PMO in presence of Project Director, 29 Nov 2020 DPD, TDF, Municipality Mayor, ward chairperson, PMQAC, WUSC

29

Semi-Annual Social Monitoring Report (July to December 2020)

secretary, Complainer Rabin Rai and affected family representative Kumar Puri and Pramod Rai. A decision was reached.

69. The cost estimate of the agreed area has been prepared, submitted by ERDSMC which was reviewed and commented by PMQAC.

70. The resolution of complaint under Diktel subproject has also been resolved in principally with the complainer, but the mechanism or modality to implement the agreed solution is being finalized by PMO in coordination with DWSSM/MOWS to prepare the separate project financing under Province Financing Modality. Hence, PMO discussed the matter with the DWSSM/MOWS and confirmation of fund availability in budget of Facial year 2078/79, to provide water connection services to 368 households of wards 2 and 6 of Diktel. PMO committed to provide full information on resolutions of this matter in the next SEMR.

Table 7: Status of Grievances and Resolution in this reporting period Ilam, Bhojpur, Diktel, Charikot, Chainpur, Liwang, Subhagh, Pragatinagar, Siddhanat, SN Description Total Ilam Bhojpur Khotang Dolakha Bajhang Rolpa Surket Dang Kanchanpur 1 No. of Submitted 4 5 14 8 2 0 0 1 2 36 Grievances 2 No. of Resolved 4 5 14 8 2 0 0 1 2 36 Grievances 3 No. of Remaining 0 0 0 0 0 0 0 0 0 0 Grievances

30

Semi-Annual Social Monitoring Report (July to December 2020)

Table 8: Submitted Grievances and Resolved Status Record Complain By and Affected Site/ Current Resolved Status SN Grievance Issues Action Taken to Solution Remarks Status Date Location Solve In ProcessPending Discard Western Region 1. Chainpur Complaints about very less Problem solved by sharing financial help for the information of OBA Ward No. 6,8 1 construction of toilets under V October 2020 guidelines and norms of toilet S and 10 OBA. construction with the community. 2 To build the retaining wall Kamala Joshi, Bhopur Site Consultation with Contractor as soon as possible to Bhopur; 8th August (Sliding and WUSC to build the Protect from landslide 2020 occurred due V retaining wall, she agreed for S to excavation construction after the rainy work for season. masonry wall) 2. Liwan No grievances received 3. Shubaghat No grievances received 4. Siddhanath -Baijanath 1 Chakkiphata Water Supply Chakkiphata Water Ward-10/ Letter sent by Siddhanath The grievances has been and Sanitation Committee Supply and Sanitation Jimuwa- Baijanath WUSC to the solved in field level consent stopped the trench Project, Kanchanpur Tilkeni, Chakkiphata WSSP and letter received by the ward excavation and pipe laying Kanchanpur Ward 10 Office regarding the office ward no 10 of works of Siddhanath R December 2020 solution. Answer received S Bhimdatta municipality Baijanath WSSSP claiming from ward office with the giving the consessus to carry the area to be under their solution. on the pipeline work on control. their area. Its has been attached in Annex-7. 2 Dust emission at October 2020 OHT/Office Water sprinkling done at time construction site. Building site to time basis for the control V S of possible dust emission at site. 5. Pragatinagar 1 Extension of pipe line Tara Ghimire 20th Sanmsad It is decided to extend the R Aug,2020 Road pipe lines in the required S Nayabasti Tole places. 6. Kalanga No grievances received

31

Semi-Annual Social Monitoring Report (July to December 2020)

Record Complain By and Affected Site/ Current Resolved Status SN Grievance Issues Action Taken to Solution Remarks Status Date Location Solve In ProcessPending Discard 7. Tikapur No grievances received Central Region 1. Charikot 1 During the excavation of the pipeline, there were Ms. PramilaTamang, complaints that the ditch Bhimeshwor had been widened by Ms. NirmalaTamang, Reinstated the wall as In first level of GRC. V Municipality-6, S digging a hole in the previous position. BS 2077/09/10 Lekhtole pipeline and causing 19 October 2020 damage to the boundry wall. 2 The old pipeline was cut Mr. Jagat The disconnected pipeline Bhimeshwor while digging the pipeline BahadurTamang, was reconnected and the V Municipality-3, S and there was no water in 25 December 2020 pipeline was restored to its Dhadkharka the house. original condition 3 It has been complained that In firs level of GRC. Resolved by estimating the digging the pipeline will BS 2077/09/02 Bhimeshwor gabion wall for landslide affect the landslide as the Mr. Kumar Shrestha, V Municipality-7, prevention and assuring that S landslide filled up the 27 December 2020 Newargaun it will be constructed pipeline about five years accordingly. ago.digging works 4 Rain water flooded in Basu Karki, Bhimeshwor residents due to filled out Closed the head of flooded V Municipality- 7, Municipality- 7, S the water in trenched side water September 13, 2020 Makaibari of pipeline 5 Complain about pipeline Mr. Basu trenching on inside the road Thapa, Bhimeshwor Local Assured to the local people V Municipality,6, people of Ward S On pipeline digging works Chothang, August 27, no.6, Chothang 2020 6 Complain about mud- Speedilycompleted the Local people of Ward covered on the road during Local people of pipeline digging works and V No.2, August 13, S the pipeline digging works Ward No.2 filled out the trenching parts 2020 properly 7 Complain about mud- Local people of Ward Speedily completed the Local people of covered on the road during V No.2, August 13, pipeline digging works and S Ward No.2 the pipeline 2020 filled out the

32

Semi-Annual Social Monitoring Report (July to December 2020)

Record Complain By and Affected Site/ Current Resolved Status SN Grievance Issues Action Taken to Solution Remarks Status Date Location Solve In ProcessPending Discard 8 Possible to encroach of Mr. Syam Transfer the pipeline in upper private land during the V Basnet, July Mati S site from existing line pipeline digging work 21, 2020 2. Deurali Hupsekot No grievances received 3. Panchkhal No grievances received Eastern Region 1. Illam 1 Traffic obstruction at Bazaar Saru Shrestha Chowk Bazaar Traffic diversion managed area during pipe distribution Vl S 17 Dec, 2020 Ward no 7 during pipe laying. laying 2 During pipe laying Chowk Bazaar During pipe laying work Arjun Pathak 17 Dec, disposal/dust made problem V Ward no 7 water sprinkling work has S 2020 in Bazaar area been done at Bazaar area. 3 Laid pipe line disturbed by Both pipe line and road Padam Kattel Golbasti Ward Municipality during V expansion work has been S 19 Nov, 2020 no. 9 expansion of Road. done simultaneously 4 Pakhari School Damaged existing pipe line Existing pipe line damaged Prabin Adhikari 24 V Area Ward no repair immediately by S During the pipe laying work Nov, 2020 09 contractor 2. Bhojpur 1 Damage of existing Bhojpur Coordination with WUSC, pipeline by heavy rainfall Ambika Rai 24 Nov Municipality consultant representative V S 2020 (2077/08/09) ward no. 4 and Contractor and resolved Dakha complaint grievance. 2 Damage of existing Informed to contractor and V Local bazar area Ward-12 S pipeline by heavy rainfall quickly repair of pipeline 3 Pipe line filling soil had Krishna Pd. Soil have been filled and washed away by rain water BK, July 13, 2020 compacted in damaged area V Ward-12 S (2077/03/ 29) Bhojpur by contractor Municipality-12, 4 Truck had been trapped in Ram Br. herpa July Bhojpur V Same day truck pulled by pipeline trench during rain 22, 2020 Municipalit y-9 S backhoe. (2077/04/07) Panitanki 5 Mr. Indra Kumar Bhojpur New pipe line excavated in hrestha Sep.24, 2020 Municipalit12 Site observation and Airport road by road V S (2077/06/08) Airport Road, carefully backfilling done contractor, during Taxar

33

Semi-Annual Social Monitoring Report (July to December 2020)

Record Complain By and Affected Site/ Current Resolved Status SN Grievance Issues Action Taken to Solution Remarks Status Date Location Solve In ProcessPending Discard construction of road side gabion works. 3. Diktel 1 Existing pipe affected during Netra Khadka, Gharelu The damaged pipe has been the laying of new pipeline. V Menuka Khadka, Chowk, Ward fixed by the contractor S no.1 immediately. Pipeline trench made Contractor immediately 2 Sakela Tole, unconvenence to the bike Harka Raj Rai, refilled the exavated trench in V Solma, Ward S rider 6 December, 2020 coordination with complainer no.2 and solved The excavated soil did not Lila Bajimaya, Contractor immediately 3 Bank Chowk, remove from pipeline trench V October 9 2020 removed the soil from S Ward no. 1. area. (2077-6-23) excavated area by tractor. Staircase was affected Manoj Bajimaya, Contractor fixed or reinstated 4 Bank Chowk, during the excavation of V October 11 2020 the staircase into its original S Ward no. 1 pipeline trench. (2077-6-25) position and solved. Existing pipeline was Contractor 5 Yuvraj Basnet, July damaged during the Trivenichowk, coordination with WUSC V 2 2020 (2077-3- S excavation of new pipeline Ward no. 1 fixed the damaged 18) trench. Pipe. Existing transmission Ambagac hhitole, 6 Amba Gachhi pipeline was damaged July 4 WUSC fixed the damaged V tole, Ward no. S during the excavation of 2020 (2077-03- Transmission pipeline. 1 new pipeline trench. 20) Backfilling wasn’t done in Contractor immediately 7 Devi Maya Bista, July proper manner and the Hatdanda, mobilized labors and V 12 2020 (2077-03- S trench wasn’t backfilled Ward no. 1 backfilled the trench as per 28) completely specification. Drainage pipe was Tej Bahadur Khattrai, Alchedhun 8 Contractor fixed the damaged during the e/w of V August 4 2020 (2077- ga tole, Ward S damaged drainage pipe. pipeline trench. 4-20) no. 2 The excavated soil Alchedhungat 9 Alchedhun Contractor immediately was piled infront of the ole, August V gatole, Ward removed the soil by S users house during the 72020(2077- no. 2 tractor. pipeline trench excavation 04-23) Staircase was destroyed HiraUdash, 10 Contractor rebuilt the during the excavation of August 14 Shanti Salleri, V staircase into its original S pipeline trench. 2020 (2077-04- Ward no. 1 state. 30)

34

Semi-Annual Social Monitoring Report (July to December 2020)

Record Complain By and Affected Site/ Current Resolved Status SN Grievance Issues Action Taken to Solution Remarks Status Date Location Solve In ProcessPending Discard 11 The trench made Planks were kept as a during the e/w for pipeline Shivhari Dhakal, Sep Shanti Salleri bridge to make people’s V S made difficult for people’s 3,2020 (2077/5/18) Ward no. 1 movement safe and movement easier. Old pipeline was damaged Gyanendra Shanti 12 Contractor and WUSC jointly during the excavation of V Joshi, Sep 6 Salleri S fixed the damaged pipe. new pipeline. (2077/5/21) Ward no. 1 13 Pipeline was crossing Contractor moved the through the private land so ShantikaRai & pipeline 5m away from the Hatdanda, the owner grieved about not V Suresh Rai, Sep 10 private property and passed S Ward no. 1 installing pipeline through his (2077/5/25) along the road land coordination with WUSC Pipeline excavation HiraKatwal , Hatdanda, Contractor fixed (solved) the 14 V S destroyed the staircase Sep 18 (207/6/2) Ward no. 1 damaged staircase 4. Katahariya No grievances received Note:-Recorded Status: Registered (R), Verbal (V); Resolved Status: Solved (S),In Process (IP),Pending (P)Discard (NA)

35

Semi-Annual Social Monitoring Report (July to December 2020)

VIII. PHYSICAL PROGRESS AND RP/DDR/IPP STATUS

71. Till this reporting period total 14 projects have been awarded the contract on different dates. 12 subprojects now in construction phase and two subprojects (Katahariya and Tikapur) contracts were awarded on November and December 2020. Thus significant physical as well as financial progresses have been achieved till date. The mitigation measures recommendation will be implemented during the different stages of construction work.

Table 9: Physical and financial progress made on July -December 2020 Physical Achieved Achieved Targeted Achieved Actual Project Pkg Targeted Physical Financial Progress Progress Financial Time SN Name No. Progress Progress Progress Jul-Dec Jul-Dec Progress Jul- Elapsed % Till Now % till Now % till Now % 2020 % 2020 % Dec 2020% 1 Chariko 38.43% 87.84 W01 68.44% 46.34% 45.70% 16.33% 9.96% t 2 Bhojpur W02 70.10% 66.21% 50.16% 24.37% 20.48% 5.81% 87.57 3 Siddha 32.00% W03 91.45% 39.45% 36.99% 15.80% 12.19% 90.91 nath 4 Diktel W04 82.25% 70.55% 44.74% 32.76% 21.06% 8.75% 92.14 5 Ilam W05 62.71% 59.18% 48.60% 29.36% 23.11% 5.64% 87.57 6 Liwang W06 99.98% 44.5% 44.39% 33.39% 8.64% 10.88% 98.18 7 Chainp 30.85% W07 75.45% 68.2% 41.09% 23.60% 9.91% 86.85 ur 8 Khalan W08 2.44% 0.32% 8.52% 2.44% 0.32% 8.52% 15.27 ga 9 Subhag 32.8% W09 73.92% 46.27% 44.50% 13.60% 12.87% 73.29 hat 10 Pragati 22.65% W10 89.9% 52.31% 35.20% 24.37% 11.07% 87.27 nagar 11 Panchk W14 5.87% 16.25% 12.89% 5.87% 16.25% 12.89% 20.29 hal 12 Deurali Hupsek W16 17.68% 12.18% 22.36% 17.68% 12.18% 22.36% 25.38 ot 13 Katahar W22 0% 0% 8.49% 0% 0% 8.49% 8.91 iya 14 Tikapur W18 0% 0% 0% 0% 0% 0% 0%

36

Semi-Annual Social Monitoring Report (July to December 2020)

% of Physical & Financial progress Vs Contracted Elapsed time (till Dec 2020) 100.00 90.00 80.00 70.00 60.00 50.00 40.00 30.00 20.00 10.00

0.00 % of progress & time & %progress of

Time elapsed % Physical % Financial %

Figure 1: Physical & Financial Progress Made on till December 2020

IX. PROGRESS STATUS OF SOCIAL SAFEGUARD ACTIVITIES AND INDIGENOUS PEOPLE'S PLAN

72. All the social safeguard activities and Indigenous People Plan (IPP) as per the mentioned in the PAM/UWSSP is the major part of the project and shall be implemented according to the activities and project cycle in each project municipalities. It is obvious that different projects are in different stages of the project cycle. Hence, activities, as mentioned in the project PAM, shall be implemented in the different phases of the project cycle.

73. According to the implementation modality of UWSSP, a consultant team, Regional Design, Supervision and Management Consultant (RDSMC), comprised of the different thematic experts including the Social safeguard Specialist has been engaged in Central, Eastern and Western region to provide support to the Regional Project Management Office of the respective region in the course of implementing the project in a full-fledged manner.

74. The Sami Annual Progress Reports has been prepared based on the progress reports received from the Social Safeguard Specialist of the Regional Design Supervision and Management Consultant (RDSMC) of central Region, Eastern Region and Western Region. Some of the major activities have been carried out during the reporting period:

75. Formation of WUSC: As per the provision of GESI AP, there should be 9 members in Water Users and Sanitation Committee (WUSC). There should be at least 33% female members and of them, at least 1 female member must be in key post. WUSCs have been already formed in all 20 projects municipalities.

76. Due Diligence Report (DDR) preparation: Due Diligence Report of on-going construction subprojects and awarded two subprojects are approved by ADB. Due Diligence Report for remaining subprojects are being prepared and updated for ADB clearance before contract award. Any safeguards issues identified during sub project implementation will be incorporated in QPR, SSMR and updated in DDR or Resettlement Plan if required. The status of DDR is described in detail in Table 3.

9.1 Status of implementation of Indigenous People Plan (IPP) in Ilam subproject

37

Semi-Annual Social Monitoring Report (July to December 2020)

77. Action plan for Indigenous People's Plan implementation of Ilam subproject is prepared and shared with ERDSMC for implementation. The Indigenous People's Action plan is prepared based on ADB disclosure of IPP report. The IPP will focus on meaningful participation of the indigenous people so as to enhance their livelihoods through:- • Priority to indigenous people living in the service area in the construction activities and in O & M phase activities. • Capacity development activities for livelihood promotion • Watershed conservation and development activities will be prioritized in the government planning and budgeted accordingly. • A total NRs 2.53 Million is provisioned in the IPP for the implementation of the said activities.

78. Indigenous Peoples Plan (IPP) of Ilam is being implemented to address the concerns of Indigenous People (IP) in source area. The IPP implementation status during this reporting period (July - December 2020) is summarized as following.

79. Two Social Mobilizers have been inducted from 15 December 2019 to accelerate the IPP activities. One social mobilizer has been fielded to the source area to carry out the IPP related activities and another social mobilizer has been engaged to carry out social activities in the project service area. The social mobilizers are actively involving in field survey for identification and selection of eligible household for OBA, grievance handling, awareness generation, TNA/IPP related activities as illustrated by the photographs below.

38

Semi-Annual Social Monitoring Report (July to December 2020)

80. Several site visits to source area were made and interaction is being continued by ERDSMC project team with Local people in Sandukpur 2. The propose of the site visit to Sandakpur (source area) was to interact/discuss with Sandakpur Rural Municipality Chairperson, Ward Chairperson and local people. Discussion was held on demand of source area people and provision of IPP. TNA workshop conducted at ward no 2 office on dated in 26 Dec 2020 with Chairmanship of Sandukpur Rural Municipality. Chief administrative officer of Sandukpur Rural Municipality, Ward no 2 Chairman, WUSC and PMQAC, ERDSMC and District team also represented workshop. Minutes of meeting/interaction is attached in Annex-2 meeting no. 7, photographs in Annex-3 and name list of selected households in Annex -5. • Orientation/Consultation conducted by social mobilizer on project objectives, IPP and public awareness meeting minute on 1 July 2020. Ward no 2 Maimajhuwa area. • Orientation/Consultation conducted by Social mobiliser on project objectives Indigenous People Plan and public awareness meeting minute on 20 July 2020. Ward no 2 Maimajhuwa, Khursane Tar area. • Orientation/Consultation conducted by social mobilizer on project objectives IPP and public awareness meeting minute on 22 September 2020. Ward no 2 Maimajhuwa, Gitang area • Orientation/Consultation conducted by social mobilzer on project objectives IPP and public awareness meeting minute on 24 September 2020. Ward no 2 Maimajhuwa Budhabare area • Orientation/Consultation conducted by social mobilzer on project objectives IPP and public awareness meeting minute on 12 November 2020. Ward no 2 Maimajhuwa, Khursane Tar area. • Orientation/Consultation conducted on project objectives IPP and public awareness meeting minute on 22 November 2020. Ward no 2 Maimajhuwa, Budhabare area. • Orientation/Consultation conducted by social mobilzer on project objectives IPP and public awareness meeting minute on 25 November 2020 Ward no 2 Maimajhuwa, Tesre Gaun area. • Final Consultation meeting conducted by social mobilzer on project objectives/IPP and public awareness meeting minute finalization of TNA Survey on 28 Dec, 2020. Ward no 2 Khursane tar. • Final Consultation meeting conducted on project objectives/IPP and public awareness meeting minute during TNA Survey on 30 December 2020. Ward no 2 Gitang. • TNA household survey conducted for 100 household in pipe line area Mewa, Rate, Gitang and Todke area near intake site Sandukpur-2 • The workshop concluded/decided for 5 types of Livelihood Enhancement Training for INdegenous People. They are: Cow farming, Swing-netting, Goat farming, Pig farming and Kiwi farming. Details in Annex-5. • Public toilet in Budhaware Hat (market) area: It was discussed with the officials of Sandakpur Rural Municipality to construct a public toilet in Budhaware Hat (market) area. Construction work of public toilet is ongoing. • Inclusive employment opportunities with preference to IPs living in source area were given. Equal opportunity provided to women depending on skills. Local labors (IPs) including women have been deployed in pipe line works at intake site. Total 6450 person days of local people (Indigenous people) in source area were employed till the reporting period. Local indigenous people (IP) have got financial benefit due to employment opportunity of 6450 person day x700 = NRs. 45,15000. The short story of one of them is given below.

39

Semi-Annual Social Monitoring Report (July to December 2020)

• Rabindra Rai: Mr. Rabindra Rai (28 Age) is permanent residence of Sandukukpur Rural municipality ward no 2 Sankhe Golai with 4 family members (3 female and 1 male). He earned some amount by the agriculture and dairy production of every year. He had no sufficient money for fulfilling demand of family members. He has no opportunity to other work except daily wage labor. During the lockdown, there was no labor work in his village. After the relaxation of lockdown, he got opportunity to work as labor near Sankhe Golai and Todke intake area (Rs, 700 per day) in Ilam Urban water supply sanitation subproject. He earned Rs. 18,200 in one month period. He is grateful to Ilam urban water supply sanitation project. He is interested to continue working with Ilam Urban water supply sanitation sector project.

9.2 OBA and Subsidized Piped Water Connection Facilities 81. OBA is one of key tools for providing service to poor, vulnerable and excluded groups by providing household toilet and free tap connection service. For the service delivery of OBA and free tap connection purpose, baseline data of poor, backward, single women headed households and vulnerable households etc. have been collected in three regions. Unfortunately, lockdown and travel restrictions due to COVID-19, field activities were delayed. 82. As per the prepared plan, all the 9 urban projects have completed verification works, final list preparation and entered in agreement process for both house hold latrine and tap connection. All the activities have been resumed by maintaining social distancing and adopting covid-19 response plan/survey protoccal. 83. In 9 urban projects; Ilam, Bhojpur, Diktel, Liwang, Pragatinagar, Siddhanath, Shubhaghat and Chainpur have prepared final list after field verification. Few of the urban projects has completed agreement with WUSC and PMO/RPMO. However, process is going on in eastern region. Simialrly, selection process is started in Panchakhal, Deuralii Hupsekot and Khalanga urban projects. Progress status up to the December 2020 is given in the following table:

Progress Status of OBA: S.N. Urban Region Selected Selected Remarks Project Households for Households for Household Toilet Free Tap Connection

1 Ilam Eastern 143 143 Agreement process ongoing 2 Bhojpur Eastern 128 128 Agreement process ongoing 3 Diktel Eastern 22 22 Agreement process ongoing 4 Charikot Central 560 874 Agreement completed 5 Panchakhal Central - - Selection process ongoing 6 Hupsekot Central - - Selection process ongoing 7 Liwang Western 58 96 Agreement Completed 8 Pragatinagar, Western 146 207 Agreement process ongoing 9 Siddhanath Western 90 104 Agreement process Baijanath, ongoing

40

Semi-Annual Social Monitoring Report (July to December 2020)

10 Shubhaghat Western 550 429 Agreement process ongoing 11 Chainpur Western 110 141 Agreement process ongoing 12 Khalanga Western 110 141 Selection process ongoing

41

Semi-Annual Social Monitoring Report (July to December 2020)

X. INSTITUTIONAL ARRANGEMENT FOR PROJECT IMPLEMENTATION

84. The project cycle of UWSSP has been divided into three phases: Study and Planning phase, Construction phase, and Operation and Maintenance phase. The study and planning phase includes information dissemination, an application submitted by community, review of the application, public awareness activity, a detailed feasibility study and if feasible, a detailed engineering design, cost estimate and finally concluding a subproject agreement between the WUSC and the project.

85. The second phase involves the construction of water, sanitation, and drainage facilities and the institutional development, training and public awareness activities. The post construction or operation and maintenance phase starts after sub-project completion and when project site office is closed. The post construction activities particularly service delivery there after (administrative, technical and financial management) become the responsibility of WUSC.

86. Different stakeholders have coordinative role in the implementation of the UWSSP and their involvement in the UWSSP is illustrated in following Figure 2. .

Figure 2: Institutional Arrangement for Project Implementation

ISSAU = Institutional Support and Service Advisory Unit, PCC = Project Coordination Committee, PMO= project management office, PMQAC = project management and quality assurance consultant, RDSMC = regional design, supervision, and management consultant, WASH = water, sanitation and hygiene. *PMO will act as regional project management office for the central region. Source: Asian Development Bank.

1. The Regional Project Management Office (RPMO) has the responsibility to implement resettlement activities in each region. The RPMO in this regard, work together with the DSMC's Social Safeguard Specialist during detailed design work. The RPMO continue further consultation with APs during project implementation and solicits views regarding

42

Semi-Annual Social Monitoring Report (July to December 2020) compensation and relocation options. UWSSP/RPMO entrusted with the responsibilities for planning, design, and implementation of the project. The Regional Project Management Office is also responsible to ensure compliance with safeguard requirements of the Government and ADB and for day-to-day monitoring of project progress, including the implementation of resettlement provisions in the project and to produce progress report on all aspects concerning planning, implementation and monitoring of the land acquisition and resettlement issues. Regional Design, Supervision and Management Consultant (RDSMC) have been engaged to carry out the detail design, supervision and management of the projects. The RDSMC Social Safeguard Specialist is responsible to carry out the social impact assessment issues and to closely work with UWSSP/RPMO for safeguard implementation. The UWSSP/RPMO staff, ICG Engineer, Social Mobilizer and DRSMC – Construction Supervision Engineer, Sub- Engineer, Environment Management Plan Monitor and Social Mobilizer have also engaged to carry out the community mobilization activities and responsible for the implementation safeguard related activities and resettlement plan implementation in field level.

10.1 Name of the project Muniicipalities under UWSSP

87. Total 22 (18 water supply, 2 DEWATS and 2 Storm Drainage) projects municipalities are selected under the Urban Water Supply and Sanitation (Sector) Project. The list of the projects municipalities is given Table -10.

88. Out of 22 Projects, 14 projects namely Ilam of , Bhojpur of Bhojpur District, Diktel of , Charikot of , Panchkahl of Kavre District, Deurali-Hupsekot of Nawalpur Distrct, Katahariya of , Subhaghat of Surkhet, Siddhanath Baijanath of , Pargatinagar Dang District, Liwang , Chainpur and Tikapur of are under construction phase. Similarly, all other projects are progressing for the implementation phase.

Table 10: Summary of project towns and municipality Project Status Package District SN Sub Project Municipality DDR/RP/IPP Nos. Type Status 1 W01 Charikot Dolakha Bhimeshwor DDR Disclosed 2 W02 Bhojpur Bhojpur Bhojpur DDR Disclosed 3 W03 Siddhanath Kanchanpur Bhimdutta RP Cleared 4 W04 Diktel Khotang Rupakotmajuwagadi DDR Disclosed 5 W05 Ilam Ilam Ilam IPP Disclosed 6 W06 Liwang Rolpa Rolpa DDR Disclosed 7 W07 Chainpur Bajhang Jaya Prithivi DDR Disclosed 8 W08 Khalanga Darchula Mahakali DDR Cleared 9 W09 Subaghat Surkhet Ghurvakot RP Disclosed 10 W10 Pragatinagar Dang Rapti DDR Disclosed Tanahun Bhanu Design 11 W11 Brihat Bhanu DDR stage Saptari Kanchanrup Design 12 W12 Kanchanrup DDR stage 13 W13 Rampurtar Okhadhunga Molung Rural Dropped 14 W14 Panchkhal Kavre Panchkhal DDR Disclosed Chitwan Bharatpur Draft to 15 W15 Sharadanagar DDR ADB

43

Semi-Annual Social Monitoring Report (July to December 2020)

Deurali Nawalpur Hupsekot Rural 16 W16 DDR Disclosed Hupsekot Municipality Palpa Rampur Feasibility 17 W17 Madi Town DDR survey Tikapur Kailali Tilapur 18 W18 Drainage & DDR Cleared FSM Charikot Dolakha Bhimeshowar Design 19 W19 DDR DEWATS stage Bhaktapur Suryabinayak Design 20 W20 Dadhikot DDR stage Bhojpur Bhojpur Bhojpur Design 21 W21 DDR DEWATS stage Kathariya Rautahat Katahariya 22 W22 DDR Cleared Drainage

44

Semi-Annual Social Monitoring Report (July to December 2020)

XI. MONITORING RESULTS AND FINDINGS

89. The regular monitoring of safeguards measures depicted in resettlement plans, DDRs and Indegenous Peoples Plan, during project implementation period is continued in this monitoring period. All ongoing construction subproject were monitored by the safeguard team and valuable suggestion and needful advices were shared to WUSC and project stakeholders. The safeguard team is closely working with the construction team to avoid adverse impacts. Water Users and Sanitation Committees (WUSCs) are actively facilitating to coordinate the construction team and local people during civil work. The monitoring works were undertaken by using specific format and documents for assessment and evaluation. Prior the commencement of the construction work the safeguard team actively participates in field work for site possession. Information is provided to all local level users and villagers on construction being started and facilitated contractor for clearing the site.

90. Monitoring system is important to measure the actual safeguard issues and affected people, what kind of mitigation/resolving measures to be adopted, what compensation is delivered to them and what impacts are achieved. In order to strengthen the monitoring system, there is a need to do the following: • Mobilize monitoring team to strengthen supervision, find associated risks, and identify the emerging needs of local effected people. • Develop an effective observation system for the prompt monitoring of complains with technical support from expert groups. • Mobilize local leaders and community organizations to monitor local issues and concerns related to the project construction works and provide feedback to the Project team for immediate correction, if needed.

91. One social mobilizer has been engaged in Ilam from December 15, 2019 from IP group. A full-fledged Grievance Redress Committees (GRC) are established in the project sites of ongoing construction. Complaint register is available in WUSC office for receiving aggrieved party’s grievances.

92. Two days training on WUSC and Stakeholders Orientation on CRDSMC-UWSSP were conducted in Panchkhal, Kavre and Deurali –Hupsekot, Nawalpur subprojects

93. A two days orientation programs on project introduction, working modalities, different components including social safeguard were organized on 24 and 25 December 2020 at Panchkhal UWSSP and on 29 and 30 December 2020 at Deurali Hupsekot UWSSP.

94. After finalised the Indigenous household's finalised survey, Training Need Assessment (TNA) workshop conducted at ward no 2 office on dated in 26 Dec 2020 with Chairmanship of Sandukpur Rural Municipality. Chief administrative officer of Sandukpur Rural Municipality, Ward no 2 Chairman, WUSC and PMQAC, ERDSMC and District team also represented workshop.

95. CRDSMC-UWSSP conducted two days training/orientation on “Core Labor Standards”. Working labor and contractor representative and stakeholders participated in the orientation. The particular training was conducted in two subproject municipalities (Panchkhal and Deurali-Hupsekot). The CRDSMC team expert (GESI Specialist, Environment and Social Safeguard Specialist) were involved in the training program.

45

Semi-Annual Social Monitoring Report (July to December 2020)

XII. SAFEGUARDS LOAN COVENANTS

Status of Compliance Loan Covenants S.N. Date: Up to December 2020 A. Procurement Loan Agreement (LA) The Borrower shall ensure that construction works under the Project do not involve Complied and being followed in IEE, SCHEDULE 5, Para 5 significant adverse environmental, involuntary resettlement and indigenous peoples EMP, EARF, RP, IPP. All incorporated in impacts which may be classified as category A under the SPS or its related rules/manuals DPR B. Land Acquisition and Involuntary Resettlement Loan Agreement (LA) The Borrower shall ensure that all land and all rights-of-way required for the Being fully Compiled. SCHEDULE 4, Para 7 Project, each Subproject and all Project facilities are made available to the Works contractor in accordance with the schedule agreed under the related Works contract and all land acquisition and resettlement activities are implemented in compliance with a) all applicable laws and regulations of the Borrower relating to land acquisition and in, voluntary resettlement; b) the Involuntary Resettlement Safeguards; c) the RF; and d) all measures and requirements set forth in the respective RP, and any corrective or preventative actions set forth in the Safeguards Monitoring Report. C. Monitoring Report Loan Agreement (LA) The Borrower shall ensure that the Involuntary Resettlement Safeguards and the RF Being complied. No involuntary or SCHEDULE4, Para 8 are followed in any involuntary or voluntary land acquisitions or government land voluntary land acquisitions and clearing activities in preparation for the future subproject or any component of displacements. such future subproject. Loan Agreement (LA) Without limiting the application of the Involuntary Resettlement Safeguards, the RF Being complied. No land acquisition and SCHEDULE4, Para 9 or the RP, the Borrower shall ensure that no physical or economic displacement displacement. takes place in connection with a Subproject until: a) compensation and other entitlements have been provided to affected people in accordance with the RP; and, b) a comprehensive income and livelihood restoration program has been established in accordance with the RP. D. Indigenous Peoples Loan Agreement The Borrower shall ensure that the preparation, design, construction, Complied in ongoing 14 sub project that (LA) SCHEDULE4, implementation and operation of the Project, each Subproject and all Project is under implementation at the moment. Para facilities comply with No major indigenous people's impacts 10 a) all applicable laws and regulations of the Borrower relating to indigenous peoples; are involved in the activities. IPP action

46

Semi-Annual Social Monitoring Report (July to December 2020)

Status of Compliance Loan Covenants S.N. Date: Up to December 2020 b) the Indigenous Peoples Safeguards; plan is being implemented in Ilam c) the IPPF; and subproject. d) all measures and requirements set forth in the respective IPP, and any corrective or preventative actions set forth In a Safeguards Monitoring Report. E. Human and Financial Resources to Implement Safeguards Requirements Loan Agreement The Borrower shall make available necessary budgetary and human resources to Being complied (LA) SCHEDULE4, fully implement the EMPs, the RPs and the IPPs. Para 11 F. Safeguards - Related Provisions in Bidding Documents and Works Contracts Loan Agreement The Borrower shall ensure that all bidding documents and contracts for Works Being complied; (LA) SCHEDULE4, contain provisions that require contractors to: All bidding documents are prepared as Para a) comply with the measures relevant to the contractor set forth in the IEE, the EMP, per ADB Standard Bidding Document 12 IPP, and the RP (to the extent they concern impacts on affected people during (SBD).Prepared safeguard related construction), and any corrective or preventative actions set forth in a Safeguards (IEE, EMP, RP, IPP & GESI-AP) Monitoring Report; compliance with the implementation b) make available a budget for all such environmental and social measures; and monitoring during project c) provide the Borrower with a written notice of any unanticipated environmental, construction stage. resettlement or indigenous peoples risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP, the RP or the IPP; d) adequately record the condition of roads, agricultural land and other Infrastructure prior to starting to transport materials and construction; and e) fully reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction. G Safeguards Monitoring and Reporting Loan Agreement The Borrower shall do the following: Safeguard issues being Incorporated (LA) SCHEDULE4, a) submit semi-annual Safeguards Monitoring Reports to ADB and and considered as in reports and Para disclose relevant information from such reports to affected persons promptly followed in implementation stage and 13 upon submission; submitted along with quarterly, Semi b) if any unanticipated environmental and/or social risks and impacts arise Annual and Annual report. during construction, implementation or operation of the Project that were not considered in the IEE, the EMP, the IPP or the RP, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan; and

47

Semi-Annual Social Monitoring Report (July to December 2020)

Status of Compliance Loan Covenants S.N. Date: Up to December 2020 c) report any actual or potential breach of compliance with the measures and requirements set forth in the EMP, IPP, or the RP promptly after becoming aware of the breach. H Labour Standards. Health and Safety Loan Agreement The Borrower shall ensure that the core labour standards and the Borrower's Being complied; PMO through its (LA) SCHEDULE4, applicable laws and regulations are complied with during the Project implementation. Design, Supervision and Management Para The Borrower shall include specific provisions in the bidding documents and Consultant (DSMC) is supervising and 15 contracts financed by ADB monitoring the compliance of labour, under the project requiring that the contractors, among other things: health and safety law regulations. The (a) comply with the Borrower's applicable labour law and regulations and incorporate project work is in compliance with applicable workplace occupational safety norms; ADBs requirements and national laws a) do not use child labour; & regulations. b) do not discriminate workers in respect of employment and occupation; c) do not use forced labour; d) allow freedom of association and effectively recognize the right to collective bargaining; and e) disseminate, or engage appropriate service providers to disseminate, information on the risks of sexually transmitted diseases, including HIV/AIDS, to the employees of contractors engaged under the Project and to members of the local communities surrounding the Project area, particularly women. I Gender and Development Loan Agreement The Borrower shall ensure that Complied with development of GESI (LA) SCHEDULE4, Action Plan and is being implemented Para a) the GESI Action Plan is implemented in accordance with its terms; in the sub- project under 16 b) the bidding documents and contracts include relevant provisions for contractors to implementation. comply with the measures set forth in the GESI Action Plan; PMO has deputed a Social c) adequate resources are allocated for implementation of the GESI Action Plan; development (GESI) Specialist in and PMQAC; One GESI specialist has d) progress on implementation of the GESI Action Plan, including progress toward been engaged in each three RDSMC. achieving key gender outcome and output targets, is regularly monitored and reported to ADB. J Framework for Inclusion of Poor and Vulnerable Households Loan Agreement The Borrower shall ensure that the Framework for Inclusion of Poor and Vulnerable Being implement, covering by GESI (LA) SCHEDULE4, Households are implemented in accordance with its terms. Action Para Plan Output 1.2.

48

Semi-Annual Social Monitoring Report (July to December 2020)

Status of Compliance Loan Covenants S.N. Date: Up to December 2020 17 K OBA Loan Agreement The OBA has been developed by (LA) SCHEDULE4, The Borrower shall develop and implement OBA in accordance with the guidelines for Social development (GESI) Specialist Para OBA to be set out in the PAM to ensure delivery of sanitation services primarily to the of PMQAC and being complied. 20 poor and vulnerable groups in Project Municipalities.

49

Semi-Annual Social Monitoring Report (July to December 2020)

XIII. FOLLOW UP ACTIONS, RECOMMENDATION

96. The implementation of OBA provisions as per the agreement made between PMO and WUSC needs to speed up in applicable remaining subprojects.

97. Due to continuous effects of COVID-19 in different forms, alternative modalities should be adopted to continue monitoring of the subproject implementation to assess the Involuntary Resettlement impacts and accordingly mitigate the issues. • Emphasize to conduct stakeholder consultation by using preventative measures at the subproject locations. • Assess the need of additional awareness program on grievance redress mechanism and carry out the necessary awareness programs among the community people/stakeholders in subproject implementation locations. • Social Safeguard Specialist and Social Mobiliser of CRDSMC, ERDSMC and WRDSMC will be coordinated and facilitated the social safeguards activities in sub- project areas. Mitigation measure, monitoring works as well as awareness raising activities shall be implemented with the involvement of the contractor and WUSC. • Required support shall be provided to safeguard desk in each subproject level with the help of WUSC. • The regular follow up and monitoring of safeguard compliance will be continued. The project team will be involved in monitoring and providing instruction to contractors, if, they fail to compile the safeguard compliance.

Table 11: Corrective actions and way forward SN Issues Corrective Actions/ Way Forward Status Remarks 1 Proactive • Dedicate the required EHS personal in Appointment of Appoint EHS safeguard all level (from Client and Contractor Environmental personal by newly desk and site) to establish effective safeguard specialist by contracted regular unit respective DSMC contractor team of monitoring and • Regular monthly meeting, field level and EHS Khalanga, reporting. monitoring and reporting by safeguard personal by all Katahariya and desk coordinator. contractors is Tikapur soon before • Establish mechanism and organize completed work progress safeguard orientation training by Consultant to concerned personal working at site. 2 Erection of Continuously place clear and Ongoing Signboards informative safety, caution signboards as per the scope of work at site & on camps 3 Maintain work • Barricade the project site from easy Ongoing Simple site Protection access of local pubic ribbon/caution for labor and • Apply proper fencing of the work area tapes are not for other public from the excess of the local public. sufficient for the • Provide hard barricading at the trench fencing the area and earth excavation area more than instead hard 1m depth area. barricade should be • Continuously flow information of place in deep and project activates and work to the wide nearby public regarding the concerns trenches/excavation of their safety and mobility factor. 4 Occupational It is covered by EMP and monitoring by On-going, OHS health and EMP Monitor training and

50

Semi-Annual Social Monitoring Report (July to December 2020)

SN Issues Corrective Actions/ Way Forward Status Remarks safety in awareness including program has awareness in been done in nine COVID-19. projects. 5 Place hard Replace rope lining with bamboo and Complied. Hard barricade in metal fencing at trench area more then barricade fencing hazard prone one meter depth. of site. area

51

Semi-Annual Social Monitoring Report (July to December 2020)

ANNEXES

52

Semi-Annual Social Monitoring Report (July to December 2020)

Annex-1: Training Participation Data

53

Semi-Annual Social Monitoring Report (July to December 2020)

Orientation to all Contractors/ Laborers on CLS (Core Labor standards), Gender Equality in Wages, Gender Based Violence, Occupational Health and Safety Standards Urban Water Supply and Sanitation Sector Project (UWSSSP) (July to December 2020) Participants by Sex Participants by Sex and Ethnicity Name of Urban SN District Brhamin/Chhetry Jana Jati Dalit Others Muslim Project M F Total M F Total M F Total M F Total M F Total M F Total 1 Ilam Ilam 28 2 30 10 2 12 8 0 8 0 0 0 10 0 10 0 0 0 2 Bhojpur Bhojpur 19 1 20 3 0 3 10 1 11 0 0 0 6 0 6 0 0 0 3 Diktel Khotang 16 4 20 1 1 2 7 1 8 3 2 5 5 0 5 0 0 0 4 Katahariya Rautahat 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5 Charikot Dolakha 25 0 25 1 0 1 11 0 11 0 0 0 13 0 13 0 0 0 6 Panchakhal Kavre 25 0 25 8 0 8 10 0 10 5 0 5 2 0 2 0 0 0 7 Hupsekot Nawalpur 46 0 46 6 0 6 28 0 28 10 0 10 2 0 2 0 0 0 8 Liwang Rolpa 34 3 37 13 1 14 19 2 21 0 0 0 2 0 2 0 0 0 9 Pragatinagar Dang 69 5 74 20 3 23 26 2 28 0 0 0 23 0 23 0 0 0 10 Siddhanath Kanchanpur 65 3 68 15 3 18 13 0 13 0 0 0 37 0 37 0 0 0 11 Subhaghat Surkhet 30 1 31 8 1 9 6 0 6 0 0 0 16 0 16 0 0 0 12 Chainpur Bajhang 57 5 62 43 2 45 10 0 10 4 3 7 0 0 0 0 0 0 13 Khalanga Darchula 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 14 Tikapur D Kailali 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Total 414 24 438 128 13 141 148 6 154 22 5 27 116 0 116 0 0 0 Percentage 94.52 5.48 100 32.19 35.16 6.16 26.48 0.00

54

Semi-Annual Social Monitoring Report (July to December 2020)

Consultation/Meetings/ Orientation/Sharing Information etc. Conducted Urban Water Supply and Sanitation Sector Project (UWSSSP) (July to December 2020) Participants by Vulnerable Groups (Dalit, Participants by Sex and Ethnicity Name of Urban Sex Poor, Excluded etc.) SN District Project Brhamin/Chhetry Jana Jati Dalit Others Muslim M F Total M M Total M F Total M F Total M F Total M F Total M F Total 1 Ilam Ilam 93 90 183 36 36 72 41 32 73 14 22 36 2 0 2 0 0 0 0 0 0 2 Bhojpur Bhojpur 49 55 104 7 10 17 31 41 72 7 4 11 4 0 4 0 0 0 0 0 0 3 Diktel Khotang 53 82 135 36 40 76 13 34 47 2 8 10 2 0 2 0 0 0 0 0 0 4 Katahariya Rautahat 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5 Charikot Dolakha 142 95 237 63 42 105 56 34 90 22 19 41 1 0 1 0 0 0 8 1 9 6 Panchakhal Kavre 22 10 32 14 6 20 6 4 10 2 0 2 0 0 0 0 0 0 0 0 0 7 Hupsekot Nawalpur 39 13 52 26 9 35 9 4 13 3 0 3 0 0 0 1 0 1 0 0 0 8 Liwang Rolpa 36 17 53 27 7 34 6 8 14 2 1 3 0 1 1 1 0 1 9 10 19 9 Pragatinagar Dang 180 97 277 140 76 216 23 21 44 10 0 10 0 0 0 7 0 7 39 21 60 10 Siddhanath Kanchanpur 222 90 312 149 46 195 56 18 74 15 26 41 2 0 2 0 0 0 73 44 117 11 Subhaghat Surkhet 119 41 160 112 29 141 0 1 1 7 11 18 0 0 0 0 0 0 7 12 19 12 Chainpur Bajhang 197 57 254 147 33 180 22 12 34 28 12 40 0 0 0 0 0 0 50 24 74 13 Khalanga Darchula 33 8 41 31 3 34 2 2 4 0 3 3 0 0 0 0 0 0 2 5 7 14 Tikapur Kailali 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Grand Total 1185 655 1840 788 337 1125 265 211 476 112 106 218 11 1 12 9 0 9 188 117 305 Percentage 64.4 35.6 100 61.14 25.87 11.8 0.65 0.49 16.58

55

Semi-Annual Social Monitoring Report (July to December 2020)

Participants of WUSC and Stakeholders Training on UWSSP Approach, Modality, GESI, Safeguards (Env./Social) Urban Water Supply and Sanitation Sector Project (UWSSSP) (July to December 2020) Participants by Sex Participants by Sex and Ethnicity Vulnerable Groups ( Name of Urban Dalit, Poor, Socially SN District Brhamin/Chhetry Jana Jati Dalit Others Muslim Excluded etc.) Project M F Total M F Total M F Total M F Total M F Total M F Total M F Total 1 Ilam Ilam 37 4 41 24 2 26 10 2 12 0 0 0 3 0 3 0 0 0 8 1 9 2 Bhojpur Bhojpur 50 7 57 17 1 18 32 6 38 0 0 0 1 0 1 0 0 0 12 2 14 3 Diktel Khotang 40 4 44 18 4 22 16 0 16 1 0 1 5 0 5 0 0 0 9 1 10 4 Katahariya Rautahat 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5 Charikot Dolakha 46 18 64 30 7 37 11 11 22 2 0 2 2 0 2 1 0 2 3 1 4 6 Panchakhal Kavre 31 15 46 19 5 24 10 6 16 2 4 6 0 0 0 0 0 0 2 4 6 7 Hupsekot Nawalpur 43 11 54 23 5 28 11 3 14 6 2 8 2 1 3 1 0 1 6 2 8 8 Liwang Rolpa 50 14 64 34 8 42 12 6 18 4 0 4 0 0 0 0 0 0 8 5 13 9 Pragatinagar Dang 50 20 70 28 10 38 20 8 28 2 2 4 0 0 0 0 0 0 6 7 13 10 Siddhanath Kanchanpur 62 24 86 48 22 70 12 0 12 0 2 2 2 0 2 0 0 0 8 2 10 11 Subhaghat Surkhet 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 12 Chainpur Bajhang 89 22 111 76 19 95 10 2 12 2 1 3 1 0 1 0 0 0 8 3 11 13 Khalanga Darchula 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 14 Tikapur Kailali 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Grand Total 498 139 637 317 83 400 144 44 188 19 11 30 16 1 17 2 0 3 70 28 98 Percentage 78.18 21.82 100 62.8 29.5 4.7 2.7 0.47 15.38

56

Semi-Annual Social Monitoring Report (July to December 2020)

Annex-2: Minutes of Meeting

57

Semi-Annual Social Monitoring Report (July to December 2020)

Minutes of Meetings, Orientation Consultation and Training/Awareness; 1. Eastern Region, Meeting no 1

English Translation of Meeting minute Date of Meeting: 1 July 2020 (BS 2077/03/08 Meeting Chaired by: Ward chairperson- Giriraj Khanal Meeting Agenda/discussion on: Project implementation and health and sanitation and provision of facilities for project for poor Household Presenters from Consultant: Sub Engineer and Social Mobilizer of the Subproject Attendance: Total-18 (Male- 14 and Female-4) Output of the Meeting: Information provided about the benefits to be provided to the poor Households, beneficiary names were collected, provide awareness on Health and sanitation.

Meeting no 2

58

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation of Meeting minute Date of Meeting: 13 July 2020 (BS 2077/03/29) Meeting Chaired by: User mass meeting Meeting Agenda/discussion on: Public awareness on Project health and Sanitation, and OBA Presenters from Consultant: EMP monitor and social mobilizer of the sbproject Attendance: Total- 19 (Male- 9 and Female-10) Output of the Meeting: Discussed on project activities and its impact, and provide awareness on Health and Sanitation

59

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting no 3.

English Translation of Meeting minute Date of Meeting: 3 August 2020 (BS 2077/05/08) Meeting Chaired by: WSSUC Chairperson, Kedar Thapa Meeting Agenda/discussion on: Meeting about Public toilet construction &OBA and to coordinate with local body for tis effective implementation Presenters from Consultant: CSE. EMP MOnitor and Socail Mobilizer Attendance: Total- 8 (Male-5 and Female-3) Output of the Meeting: Discussed on Provision of OBA, agreed to write request letter to local body through WUSC for constructing public toilets

60

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting no 4

English Translation of Meeting minute Date of Meeting: 24 August 2020 (BS 2077/05/08) Meeting Chaired by: General user meeting (settlement) Meeting Agenda/discussion on: Meeting about Public toilet construction &OBA, Sanitation and Health awareness Presenters from Consultant: EMP monitor and Social Mobilizer Attendance: Total- 12 (Male-4 and Female-8) Output of the Meeting: Provision and requirements for OBA is discussed and awareness on Health and Sanitation carried out.

61

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting no 5

English Translation of Meeting minute Date of Meeting: 22 September 2020 (BS 2077/06/06) Meeting Chaired by: General user meeting (settlement) Meeting Agenda/discussion on: Meeting about TNA Survey and Sanitation and Health awareness Presenters from Consultant: EMP monitor and Social Mobilizer Attendance: Total- 19 (Male-9 and Female-10) Output of the Meeting: TNA survey and Information dissemination regarding IP plan was carried out

62

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting no 6

English Translation of Meeting minute Date of Meeting: 24 September 2020 (BS 2077/06/08) Meeting Chaired by: General user meeting (settlement) Meeting Agenda/discussion on: Meeting on TNA Survey and Sanitation and Health awareness Presenters from Consultant: EMP Monitor and Social Mobilizer Attendance: Total- 22 (Male-6 and Female-16) Output of the Meeting: TNA survey including Pubic awareness in Sanitation and Health awareness

63

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting no 7

English Translation of Meeting minute Date of Meeting: 24 September 2020 (BS 2077/06/28) Meeting Chaired by: General user meeting (settlement) Meeting Agenda/discussion on: Meeting about TNA survey, OBA and Covid-19 awareness hand wash and no entry in mass movement OBA awareness Presenters from Consultant: Social Mobilizer, CSE, EMP Monitor Attendance: Total- 17 (Male-3 and Female-14) Output of the Meeting: TNA survey and OBA information collection including Pubic awareness Covid-19 awareness, hand wash and OBA awareness

64

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting no. 8

65

Semi-Annual Social Monitoring Report (July to December 2020)

66

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation of Meeting minute Date of Meeting: 26 December 2020 (BS 2077/09/1) Meeting Chaired by: Udaya Rai Chair Person of Sandakpur Rural Municipality Meeting Agenda/discussion on: Meeting about discussing TNA survey report, IP Plan and Finalization of IPP Households Presenters from Consultant/stakeholders: Chairperson of Sandakpur Rural Municipality Ward-2, experts from PMQAC, ERDSMC, WUSC, ICG, EMP Monitor and Social mobilizer Attendance: Total- 38 (Male-20 and Female-18) Output of the Meeting: TNA survey discussed and finalized five different category of skill development programs for indigenous people under IPP.

67

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting no 9

English Translation of Meeting minute Date of Meeting: 19 July 2020 (BS 2077/04/04) Meeting Chaired by: User awareness campaign Meeting Agenda/discussion on: Meeting about dissemination of information on UWSSP and awareness on health and sanitation; hand washing practices Presenters from Consultant/stakeholders: EMP Monitor and Social Mobilizer Attendance: Total- 6 (Male-4 and Female-2) Output of the Meeting: Discussed about the project activities, its impact and benefit to the community and provided awareness especially about importance of hand washing.

68

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting no 10

69

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation of Meeting minute Date of Meeting: 19 July 2020 (BS 2077/04/04) Meeting Chaired by: Prabin Suwal, Chairperson of WSSUC Meeting Agenda/discussion on: Meeting about Progress review and labor issues and Health and safety of the Labour Presenters from Consultant/stakeholders: CSE, ICG engineer and EMP Attendance: Total- 11 (Male-10 and Female-1) Output of the Meeting: Discussed about the progress and quality, agreed to accelerate the delay activities with proper labor management and provide awareness & instruction on OSH and covid-19 related preventive measures

70

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting no 11

English Translation of Meeting minute Date of Meeting: 23 September 2020 (BS 2077/06/07) Meeting Chaired by: Meeting with Women Group Meeting Agenda/discussion on: Meeting about UWSSP working modalities, its impact and benefit and community health and sanitation Presenters from Consultant/stakeholders: EMP Monitor and Social Mobilizer Attendance: Total- 10 (Male-1 and Female-9) Output of the Meeting: Information disseminated about the UWSSP working modalities, its impact and benefit and provided orientation on community health and sanitation

71

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting no 12

English Translation of Meeting minute Date of Meeting: 23 September 2020 (BS 2077/06/07) Meeting Chaired by: Meeting with Women Group Meeting Agenda/discussion on: Meeting about implementation progress of UWSSP, community health and sanitation and covid -19 response activities Presenters from Consultant/stakeholders: EMP Monitor and Social Mobilizer Attendance: Total- 10 (Male-1 and Female-9) Output of the Meeting: Information received on progress status of UWSSP, provide orientation on community health and sanitation and covid -19 response activities.

72

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting no 13

English Translation of Meeting minute Date of Meeting: 18 December 2020 (BS 2077/09/03) Meeting Chaired by: Meeting with Women saving Group Meeting Agenda/discussion on: Meeting about community health and sanitation and covid -19 response activities Presenters from Consultant/stakeholders: EMP Monitor and Social Mobilizer Attendance: Total- 9 (Male-1 and Female-8) Output of the Meeting: Provide orientation on community health and sanitation and covid - 19 response plan and activities.

73

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting no 14

English Translation of Meeting minute Date of Meeting: 10 July 2020 (BS 2077/03/26) Meeting Chaired by: User Awareness campaign Meeting Meeting Agenda/discussion on: campaign on UWSSP implementation activities, public health, community hygiene and sanitation Presenters from Consultant/stakeholders: EMP Monitor and Social Mobilizer Attendance: Total- 20 (Male-5 and Female-15) Output of the Meeting: Provide orientation on UWSSP activities, public health, community health/Hygiene and sanitation, and importance of drinking pure water.

74

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting no 15

English Translation of Meeting minute Date of Meeting: 24 July 2020 (BS 2077/04/09) Meeting Chaired by: User Awareness campaign Meeting Meeting Agenda/discussion on: campaign on UWSSP implementation activities, public health, community hygiene and sanitation Presenters from Consultant/stakeholders: EMP Monitor and Social Mobilizer Attendance: Total- 15 (Male-1 and Female-14) Output of the Meeting: Provide orientation on UWSSP activities, public health, community health/Hygiene and sanitation, and importance of drinking pure water.

75

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting no 16

English Translation of Meeting minute Date of Meeting: 3 August 2020 (BS 2077/04/19) Meeting Chaired by: User Awareness campaign Meeting Meeting Agenda/discussion on: campaign on UWSSP implementation activities, public health, community hygiene and sanitation Presenters from Consultant/stakeholders: EMP Monitor and Social Mobilizer Attendance: Total- 16 (Male-9and Female-7) Output of the Meeting: Provide orientation on UWSSP activities, public health, community health/Hygiene and sanitation, and importance of drinking pure water.

76

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting no 17

English Translation of Meeting minute Date of Meeting: 4 September 2020 (BS 2077/05/19) Meeting Chaired by: User Awareness campaign Meeting Meeting Agenda/discussion on: campaign on UWSSP implementation activities, public health, community hygiene and sanitation Presenters from Consultant/stakeholders: EMP Monitor and Social Mobilizer Attendance: Total- 15 (Male-5 and Female-10) Output of the Meeting: Provide orientation on UWSSP activities, public health, community health/Hygiene and sanitation, and importance of drinking pure water.

77

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation of Meeting minute Date of Meeting: 15 October 2020 (BS 2077/06/29) Meeting Chaired by: User Awareness campaign Meeting Meeting Agenda/discussion on: campaign on UWSSP implementation activities, public health, community hygiene and sanitation Presenters from Consultant/stakeholders: EMP Monitor and Social Mobilizer Attendance: Total- 8 (Male-2 and Female-6) Output of the Meeting: Provide orientation on UWSSP activities, public health, community health/Hygiene and sanitation, and importance of drinking pure water.

78

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting no 18

English Translation of Meeting minute Date of Meeting: 10 December 2020 (BS 2077/08/25) Meeting Chaired by: User Awareness campaign Meeting Meeting Agenda/discussion on: campaign on UWSSP implementation activities, public health, community hygiene and sanitation Presenters from Consultant/stakeholders: EMP Monitor and Social Mobilizer Attendance: Total- 19 (Male-7 and Female-12) Output of the Meeting: Provide orientation on UWSSP activities, public health, community health/Hygiene and sanitation and importance of drinking pure water.

79

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting no 19

80

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation of Meeting minute Date of Meeting: 27 December 2020 (BS 2077/09/12) Meeting Chaired by: Dhan Kumar Joshi, Chair person of WSSUC Meeting Agenda/discussion on: Provision of OBA, Selection of OBA and Construction of toilets, community hygiene and sanitation Presenters from Consultant/stakeholders: EMP Monitor and Social Mobilizer Attendance: Total- 32 (Male-18 and Female-14) Output of the Meeting: Discussed the Provision of OBA, Finalized the list of OBA beneficiary and Provided orientation on community health/Hygiene and sanitation

81

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting 20 Meeting Minutes of Diktel settlement (29 Nov 2020) at PMO

82

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation

• Meeting conducted with complainant (complainant Rabin Rai and affected family representative Kumar Puri), WUSC and PMO on 7 Mansir 2077 (22 November 2020) at PMO for settlement of the issue, both the parties have agreed on 13 points out of 14 points (All point resolved except one point remaining (To provide private connection to approximately 368 household of ward no 2&6). • Follow up Meeting conducted at PMO in presence of Project Director, DPD, TDF, Municipality Mayor, ward chairperson, PMQAC, WUSC secretary, Complainant Rabin Rai and affected family representative Kumar Puri and Pramod Rai on 29 November 2020.

Agenda of meeting: To arrange one tap in each household in ward no 2 Solma and ward no 6 nearby area of source (approximately 368 Households).

Decision: • Detailed Engineering Design Report will be prepared for one house one connection in ward no 2 & 6 within December 2020. • Prepare the implementation modality (framework) between the Municipality and the Project Management Office for the providing safe water to 368 households. • Decision was made to resume all the stalled work of the project along with the work of Detailed Engineering Design Report of 368 HHs.

1. Central Region

83

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting no.1 Endorsement of 9 point agreement

84

Semi-Annual Social Monitoring Report (July to December 2020)

85

Semi-Annual Social Monitoring Report (July to December 2020)

86

Semi-Annual Social Monitoring Report (July to December 2020)

87

Semi-Annual Social Monitoring Report (July to December 2020)

88

Semi-Annual Social Monitoring Report (July to December 2020)

89

Semi-Annual Social Monitoring Report (July to December 2020)

Meeting no.2 internal meeting of WUSC for Endorsement of 9 point agreement

90

Semi-Annual Social Monitoring Report (July to December 2020)

91

Semi-Annual Social Monitoring Report (July to December 2020)

92

Semi-Annual Social Monitoring Report (July to December 2020)

93

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation Meeting at Bhimeshwor Municipality, Ward No. 7, Makaibari: On Saturday, December 12, 2020 (BS 2077/08/27), an extensive interaction / discussion was held with the local users about the implementation status of the 9 point agreement reached with the local users of Makaibari, Ward 7 of Bhimeshwor Municipality on January 26, 2020 regarding the Urban Water Supply and Sanitation Project under construction under Charikot Water Supply and Sanitation Users Committee. The following decisions have been taken in the following resolutions in the meeting.

94

Semi-Annual Social Monitoring Report (July to December 2020)

Attendance: S.N. Name Sex Position/ Address Sign 1 Hari Sharan Shivakoti Male Chairperson, Bhimeshowr Municipality-3 2 Krishna BahadurGautam Male Patron Member 3 Krishna Karki Male Bhimeshowr Municipality-5 4 Ramkrishna KC Male Chairperson, Charikot WUSC 5 Birajman Shrestha Male Chairperson, Bhimeshowr Municipality-2 6 Anita Shrestha Female Treasurer, Charikot WUSC 7 RupaShahi Female Municipal Executive Member, Bhimeshowr Municipality-5 8 Bishwaniti Pakhrin Male Chief Patron, Charikot WUSC 9 Sita KC Female Accountant, Charikot WUSC 10 Kamala Maharjan Female Member, Charikot WUSC 11 Krishna BahadurKhadka Male Vice Chairperson, Charikot WUSC 12 Dhruba Basnet Male Secretary, Charikot WUSC 13 Moti Prasad Chaulagain Male Member, Charikot WUSC 14 Samjhana Basnet Female Social Mobilizer, Bhimeshowr Municipality-7 15 Birendra Maharjan Male CSE, CRDSMC, UWSSP 16 Dipak Acharya Male Project Manager, Contractor, UWSSP 17 PushkalSubedi Male ICG Engineer, PMO, UWSSP 18 Prakash Khatri Male Bhimeshowr Municipality-7, Makaibari 19 Ramkrishna Raut Male Bhimeshowr Municipality-7, Makaibari 20 Arjun Kumar Lama Male Bhimeshowr Municipality-7, Makaibari 21 RekhaTamang Female Bhimeshowr Municipality-7, Makaibari 22 Arjun Raut Male Bhimeshowr Municipality-7, Makaibari 23 Bir Bahadur Moktan Male Bhimeshowr Municipality-7, Makaibari 24 Anisha Shrestha Female Bhimeshowr Municipality-7, Makaibari 25 SunitaTamang Female Bhimeshowr Municipality-7, Makaibari 26 Sunil Tamang Male Bhimeshowr Municipality-7, Makaibari 27 Ram BahadurBhujel Male Bhimeshowr Municipality-7, Makaibari 28 Kumar Karki Male Bhimeshowr Municipality-7, Makaibari 29 KiranShahi Male Bhimeshowr Municipality-7, Makaibari 30 PremTamang Male Bhimeshowr Municipality-7, Makaibari 31 Prakash Chandra Lama Male Bhimeshowr Municipality-7, Makaibari 32 Dan BahadurTamang Male Bhimeshowr Municipality-7, Makaibari 33 BikashTamang Male Bhimeshowr Municipality-7, Makaibari 34 Krishna BahadurTamang Male Bhimeshowr Municipality-7, Makaibari 35 Shanti Shaha Female Bhimeshowr Municipality-7, Makaibari 36 UrmilaTamang Female Bhimeshowr Municipality-7, Makaibari 37 Purnima Gurung Tamang Female Bhimeshowr Municipality-7, Makaibari 38 Dinesh Bi Ka Male Bhimeshowr Municipality-7, Makaibari 39 Mekh Bahadur Khati Male Bhimeshowr Municipality-7, Makaibari 40 Lal Bahadur Bi Ka Male Bhimeshowr Municipality-7, Makaibari 41 Nimpasang Lama Male Bhimeshowr Municipality-7, Makaibari 42 Lanam Lama Male Bhimeshowr Municipality-7, Makaibari 43 Kedar Bahadur Tamang Male Bhimeshowr Municipality-7, Makaibari 44 Dal Bahadur Lama Male Bhimeshowr Municipality-7, Makaibari 45 Hem Prasad Dahal Male Bhimeshowr Municipality-7, Makaibari 46 Nanda Bahadur Tamang Male Bhimeshowr Municipality-7, Makaibari 47 Aita Maya Tamang Female Bhimeshowr Municipality-7, Makaibari 48 AratiUpreti Female Bhimeshowr Municipality-7, Makaibari 49 Indra Prasad Upreti Male Bhimeshowr Municipality-7, Makaibari 50 Anjan Prasad Upreti Male Bhimeshowr Municipality-7, Makaibari 51 Surya Raj Upreti Male Bhimeshowr Municipality-7, Makaibari 52 Tanka NathUpreti Male Bhimeshowr Municipality-7, Makaibari 53 Gopal Bahadur Khatri Male Bhimeshowr Municipality-7, Makaibari 54 Balram Khatri Male Bhimeshowr Municipality-7, Makaibari 55 Krishna Khatri Male Bhimeshowr Municipality-7, Makaibari 56 Ramesh Khatri Male Bhimeshowr Municipality-7, Makaibari 57 BijayTamang Male Bhimeshowr Municipality-7, Makaibari 58 Krishna Bahadur Khadka Male Bhimeshowr Municipality-7, Makaibari

95

Semi-Annual Social Monitoring Report (July to December 2020)

Agenda 1. Regarding the implementation status of the agreements under the previous nine point agreement. 2. Regarding the implementation of the nine point agreement based on its implementation status and the remaining work to be done in the project. Decisions 1. While discussing in agenda no. 1, today's discussion has decided that the implementation status of the above agreement is as follows in accordance with the nine point agreement reached with the Struggle Committee of Local Users in Bhimeshor Municipality, Ward 7, Makaibari of Charikot Water Supply and Sanitation Project under construction under Urban Water Supply and Sanitation Project on 26 January 2020 (BS 2076/10/12).

A. Regarding the advance of Rs. 1500/- per household from the users of Ward No.7 mentioned in point no. 1 of the agreement; it has been decided to collect the advance amount of Rs. 1500/- from 258 households of the area. The rest are being collected from the remaining households. B. As the users of Ward No. 7 are already using water supply from various sources and the Charikot Water Supply and Sanitation Users Committee has decided to impose a minimum tariff of up to 12,000 liters after the Charikot Water Supply and Sanitation Project comes into operation, the Committee seems to be committed to this as per the agreement. C. As per the agreement mentioned in point 3 of the agreement, the households added as users of Charikot Water Supply Project in Ward No. 7, Makaibari area have become members.The Committee has decided to charge 50 percent less connection fee for the additional houses than the users of other Wards. D. The issue of keeping 5 percent of the minimum tariff in the Water Resource Management Fund as per point no. 4 of the agreement was discussed at a meeting held on November 1, 2020 (BS 2076/07/16) at the Project Management Office, Panipokhari, Kathmandu. In the meeting, it was agreed in the presence of the representative of the Town Development Fund to deposit 5 percent amount in the Water Resource Management Fund and to collect additional 5 percent amount from the users after the completion of the project. The Charikot Water Supply Users Committee seems to be committed in this regard as it has already decided to collect additional 5 percent from the users and set aside the amount for the Water Resource Management Fund after the completion of the project. E. As per the suggestion of the concerned technicians of Charikot Water Supply Project regarding the agreement mentioned in point no. 5 of the agreement, it is not necessary to use other existing water sources of ward no.7. And it seems that a decision has been made by that committee. F. In point 6 of the agreement, it was decided to involve the local youth in the work of the project and accordingly, the local people are getting employment in the pipeline, structure construction and other works of the Committee. And two persons of this Ward, Ms. Samjhana Basnet and Mr. Kumar Basnet have been found working as employees of the project. G. It has been found that the Charikot Water Supply Committee has decided to provide necessary assistance to the local users of Ward No. 7 in the various types of disasters mentioned in point No. 7 of the agreement. H. According to point no. 8 of the agreement reached with the users of the area on the above date, it has been decided to provide adequate amount of water in Ranipokhari area from the pipeline where the Charikot Water Users Committee will

96

Semi-Annual Social Monitoring Report (July to December 2020)

bring water from Hattichhahara. It is seen that the Charikot Water Users Committee has decided not to provide water from the pipeline designed by the project. I. As mentioned in point no. 9 of the agreement, project related works are being carried out in this area by continuous liaison and coordination with the local people's representatives and users of Ward no. 7. It has been found that the Committee has decided to form a sub-committee in this area in the coming days to carry out the functions of the Users Committee effectively.

2. As the implementation situation of the above 9 point agreement was found to be satisfactory on the basis of the detailed discussion held in today's meeting regarding agenda no. 2, today's meeting has approved the achievements mentioned in the above points. As the construction work of the project is progressing satisfactorily despite various disruptions including COVID 19, it was decided to provide necessary support from the local users to complete the remaining works of the project in a timely manner. It was decided to provide information in this regard to the concerned users from the Committee.

Signature of the participants

WUSC Meeting:

Today, on December 10, 2020 (BS 2077/08/25), under the chairmanship of Mr. Ram Krishna KC, the chairperson of this Charikot Water Supply and Sanitation Users Association, we had a meeting with the following office bearers, members and consultants and decided on the following agendas.

Attendance: S.N. Name Sex Position/ Address 1 Bishwaniti Prakash Man Singh Male Chief Patron, Charikot WUSC Lama 2 Krishna Bahadur Gautam Male Patron 3 Narayan BahadurThapa Male Patron 4 Ramkrishna KC Male Chairperson, Charikot WUSC 5 Krishna Bahadur Khadka Male Vice Chairperson, Charikot WUSC 6 Dhruba Basnet Male Secretary, Charikot WUSC 7 Anita Shrestha Female Treasure , Charikot WUSC 8 Krishna Bahadur Karki Male Member, Charikot WUSC 9 Rajesh Thapa Male Member, Charikot WUSC 10 Moti Prasad Chaulagain Male Member, Charikot WUSC 11 Kamala Maharjan Female Member , Charikot WUSC 12 Parvati Shrestha Female Member , Charikot WUSC 13 Sita KC Female Accountant, Charikot WUSC 14 Arjun Lama Male Member , Charikot WUSC 15 Dawa Lama Male Chairperson, ToleSudharSamiti 16 Lungur Lama Male Member , ToleSudharSamiti 17 RupaShahi Female Executive Member, Bhimeshwor Municipality 18 Birendr aMaharjan Male CSE, CRDSMC 19 Pushkal Subedi Male ICG Engineer, PMO

Agenda:

97

Semi-Annual Social Monitoring Report (July to December 2020)

1. Regarding the implementation status of the agreement reached with the residents of Bhimeshwor Municipality-7.

Decisions: 1. During the discussion on Agenda No. 1, the implementation status of the 9 point agreement reached between this Users Committee and the Local Users' Struggle Committee of Bhimeshwor Municipality, Ward No. 7 on 26 January 2020 has been reviewed as follows:

1.1 As mentioned in point no.1 of the agreement, residents of other wards paid cash at the rates of Rs. 6,500/- and Rs. 8,500/- as upfront cash participation, but an agreement was reached to collect advance from the users of Ward No. 7 at the rate of Rs. 1,500/- per tap stand. Accordingly, the amount has been collected from 258 households so far. Although there is still work to be done to collect from the remaining households, it was reviewed that the agreement has been implemented by collecting the amount from more than 95 percent of the households as per the agreement reached on this point.

1.2 The users of Ward No. 7 are currently using water supply from various sources. It is informed that the committee is committed to implement the point of the agreement that the amount of water supply will be fixed at the rate of minimum 12000 liters per month while determining the fee for the users living in Ward no.7.

1.3 As mentioned in point 3 of the agreement, after the completion of the project, the tap stand connection fee will be charged 50 percent less from the users already living in Ward No.7 than those living in other wards.

1.4 As per point 4 of the agreement, it was discussed that 5 percent of the minimum tariff will be deposited for the water supply resource management fund. After the completion of the project, additional 5 percent amount will be collected from the users and kept in the water supply resource management fund. The fund will be made available to resource managers. This amount will be collected in addition to the water tariff rate determined as per the business plan prepared by the Town Development Fund. In this regard, the committee is committed to collect additional 5 percent amount and establish the fund as per the decision made in the meeting attended by the representatives of the Town Development Fund.

1.5 Apart from the water sources registered by the Charikot Water Supply Users Association mentioned in point 5 of the agreement, it is not necessary to use any of the water sources currently being used by the residents of Ward No. 7.In this regard, it has been re-committed not to use the mentioned resources and not to make any claim.

1.6 As mentioned in point no. 6 of the agreement, it was decided to give priority to the residents of ward no. 7 in the employment opportunities required in this organization. Accordingly, two persons (Ms. Samjhana Basnet and Mr. Kumar Basnet) have been given employment as employees. It was reviewed that more than 90 percent of the people in the area are employed as skilled and

98

Semi-Annual Social Monitoring Report (July to December 2020)

unskilled laborers in digging and burying pipelines and constructing structures at the local level.

1.7 The committee is committed to provide all possible assistance to the residents of Ward No. 7 in case of various natural calamities and disasters as per point no. 7 of the agreement.

1.8 As per point no. 8 of the agreement, it was agreed to provide some amount of water from Hattichhahara to Ranipokhari area. In this regard, it has been committed to bring additional water from the pipeline currently in use in addition to the pipeline designed by the project and to provide adequate amount of water from the pipeline in the places as per the agreement.

1.9 It was decided that close relationship, coordination and cooperation would be maintained with the people's representatives and users of Ward No. 7 while operating the project as per point no. 9 of the agreement. Accordingly, work is being carried out in coordination.A commitment has been made to make the work of water supply project effective by forming and mobilizing subcommittee as per coordination, cooperation and need.

1.10 In accordance with the above, it was decided to continue implementing the points of the agreement in the presence of local people's representatives, users and other stakeholders after extensive discussion and review.

99

Semi-Annual Social Monitoring Report (July to December 2020)

Event of July 2020 - Charikot UWSS Project

100

Semi-Annual Social Monitoring Report (July to December 2020)

Minutes of interaction event conducted on September 2020 Charikot Project

101

Semi-Annual Social Monitoring Report (July to December 2020)

Orientation to Stakeholders of Deurali Hupeskot

102

Semi-Annual Social Monitoring Report (July to December 2020)

Hupsekot UWSSP (24th to 25th December 2020)

103

Semi-Annual Social Monitoring Report (July to December 2020)

Orientation to labourers of Panchkhal UWSS Project (25th December 2020)

104

Semi-Annual Social Monitoring Report (July to December 2020)

Orientation to Stakeholders of Deurali Hupsekot Project (29th to 31st December 2020)

105

Semi-Annual Social Monitoring Report (July to December 2020)

106

Semi-Annual Social Monitoring Report (July to December 2020)

Orientation to labourers of Deurali Hupsekot Project (31st December

107

Semi-Annual Social Monitoring Report (July to December 2020)

108

Semi-Annual Social Monitoring Report (July to December 2020)

1. Name list of training participants of Orientation to WUSC and Stakeholders at Panchkhal WSS SN Name Address Institution Position Remarks 1 Mahesh Kharel Panchkhal Panchkhal Municipality Mayor

2 Laxmi Danuwar Panchkhal-12 Panchkhal Municipality Deputy mayor 3 Kumar Prasad Panchkhal-3 WUSC Chairperson Lamichhane 4 Chet Prasad Gautam Panchkhal-10 WUSC Secretary 5 Kiran Shrestha Panchkhal-9 9 no. ward Chairperson 6 Sundar Adhikari Panchkhal-3 3 no. ward Chairperson 7 Birman Pahari Panchkhal Community Representative 8 Shyam Bahadur BK Panchkhal-9 WUSC Member 9 Shiva Hari Parajuli Panchkhal-6 6 no ward Member 10 Jhalak Kumari Dulal Panchkhal-6 WUSC Member 11 Rajesh Mainali Panchkhal-12 12 no.ward Member 12 Rabindra raj Shipkhan Panchkhgal-3 WUSC Vice chairperson 13 Goma Mijar Panchkhal-6 Community Representative 14 RenukaChaulagain Panchkhal-10 Community Representative 15 Samjhana Pariyar Panchkhal-6 Community Representative 16 Maili Danuwar Panchkhal-4 Community Representative 17 Hariram Khatiwoda Panchkhal-2 2 no.ward Chairperson 18 Durga Mijar Panchkhal-12 Community Representative 19 Sita Rokka Panchkhal-12 Community Representative 20 Chandika Mijar Panchkhal-2 Community Representative 21 Narayan Prasad Panchkhal-10 Ward no.10 Chairperson Sapkota 22 Puskar Dhakal Panchkhal-7 Existing WUSC Member 23 Suresh Mahaju CRDSMC CSE 24 Indra Mansing Basnet Contractor PM 25 Rakesh Chaudhari Contractor Site engineer 26 Aaditya Aryal CRDSMC EMP 27 Smith Devekota CRDSMC Engineer 28 Suman Bajgain CRDSMC Engineer 29 Taradevi Shrestha ICG SM 30 Apsara Ghorsaine Panchkhal-3 CRDSMC SM 31 Keshav Dhungana CRDSMC GESI S 32 Yogesh Shakya CRDSMC ES 33 Samir Dhakal CRDSMC SSS 34 Suraj Sigdel CRDSMC CMS 35 Shambhabi Khanal PMO ICG engineer 36 Ramchandra Devekota CRDSMC TL 37 Elina Pudasaini CRDSMC Manager 38 Sundar Tamang Panchkhal-4 4 no ward Chairperson 39 Shiba Saran lama Panchkhal-11 11 no. ward Chairperson 40 Kapil Koirala Panchkhal Municipality Press adviser 41 Sukbir Tamang Panchkhal-13 13 no, ward Chairperson 42 Sanjaya Tamang Panchkhal-8 8 no. ward Chairperson 43 Sanjita Danuwar Panchkhal-4 Community Representative 44 Singha Bahadur Panchkhal-11 Community Representative Tamang 45 Gopal Bahadur Panchkhal-12 12 no. ward Chairperson Danuwar 46 Shanti Danuwar Panchkhal-12 12 no. ward Member

109

Semi-Annual Social Monitoring Report (July to December 2020)

2. Name list of training participants on Orientation to WUSC and other Stakeholders at Deurali Hupsekot WSS SN Name Address Institution Position Remarks 1 Laxmi Pande Hupsekot-3 Hupsekot Rural Chairperson municipality 2 Mek Bahadur Pulami Hupsekot-3 WUSC Chairperson 3 Faganath Pande Hupsekot-3 WUSC Vice chairperson 4 Saran hari Gyawali Hupsekot Sharma-Diwa bhimeswor Manager 5 Urmila Mahato Hupsekot-1 Hupsekot Rural Member municipality 6 Rebati Saru Hupsekot-3 Community Representative 7 Guru Prasad Subedi Hupsekot-3 WUSC Coordinator 8 Krishna Prasad Hupsekot-3 Community Representative Pande 9 Lalchandra Hupsekot-3 WUSC (Safeguard member Lamichhane committee) 10 Prem Bahadur Karkee Hupsekot-3 Forest consumer Chairperson committee 11 Mani Pande Hupsekot-4 WUSC Treasurer 12 Cham Kumari Pariyar Hupsekot-2 WUSC Member 13 Rana Bahadur Nepali Hupsekot-1 Community Representative 14 Lal Bahadur Sherpuja Hupsekot-1 WUSC Co-Secretary 15 Krishna Raj Kandel Hupsekot-3 WUSC Member 16 Bhim Narayan Regmi Hupsekot-3 WUSC Secretary 17 Dol Raj Pande Hupsekot-3 WUSC (Safeguard member committee) 18 Nawal Sing Damai Hupsekot-3 WUSC Member 19 Mohamad Nurtuja CRDSMC Engineer Husen 20 Roshan Gupta CRDSMC EMP 21 Tara Bahadur Karkee Hupsekot-3 3 no. ward Member 22 Chiranjibi Thapa Hupsekot-4 4 no. ward Member 23 Man kumari Tamang Hupsekot-1 Community Representative 24 Buddhiman Tamang Hupsekot-1 Satybati community forest Chairperson 25 Madan Thapa Hupsekot-3 Mayur pokhari community Chairperson forest 26 Dal Bahadur Hupsekot-1 Trikathi Community forest Chairperson Serimagar 27 Brihaspati Darai Deurali -3 WUSC Member 28 Durga Devi Khanal Deurali-3 WUSC Member 29 Bhanu Narayan CRDSMC CSE Shrestha 30 Yogesh Shakya CRDSMC ES 31 Samir Dhakal CRDSMC SSS 32 Keshav Dhungana CRDSMC GESI S 33 Shrijana Pande Hupsekot-3 WUSC Manager 34 Yubaraj Pande Hupsekot-2 Thunidevi Community Chairperson Forest 35 Ramchandra CRDSMC TL Devekota 36 Alina Pudasaini CRDSMC manager 37 Sita KC CRDSMC SM 38 Sabin Yadav ICG OA 39 Tek Bahadur Bam Hupsekot-1 Satyawati Community Chairperson Forest 40 Oman Sing Rajali Hupsekot-3 WUSC Adviser 41 Bhagawati Pande Hupsekot-3 WUSC Member 42 Iswori Prasad Pande Hupsekot-3 Community Representative

110

Semi-Annual Social Monitoring Report (July to December 2020)

43 Yam Bahadur BK Hupsekot Dalit Organization Representative 44 Bishal KC PMO ICG engineer 45 Sharmila Ghale Hupsekot 1 no. ward Member 46 Tej maya Pande Hupsekot-3 3 no. ward Member 47 Roshan Subedi PMQAC SDS 48 Sajan KC Bhimeswor construction Site-engineer 49 Nabin Magar Hupsekot-3 WUSC Sub-engineer 50 Yam Bahadur Somai Hupsekot-4 4 no. ward Member 51 Ganesh Thakuri Hupsekot-4 Hupsekot rural WSST Municipality 52 Narayan Mukhiya Hupsekot Community forest OA 53 Dev Bahadur Pulami Hupsekot CRDSMC Driver 54 Indra Dhakal Hupsekot Sharma-Bhimeswor Driver

111

Semi-Annual Social Monitoring Report (July to December 2020)

2. Western Reagion 1. Pragatinagar (November)

On November 24, 2020 (2077/08/09), the consultation meeting of Pragatinagar Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mr. Shanta Raj Sharma, WUSC Chairperson and made the following decisions: Attendees: Total: 11; Male: 9; Female: 2 Agendas and decisions: Agenda: 1 – Regarding Progress Review Decisions: 1. A detailed review of the progress was done and problems faced during working period of the project were discussed and necessary instruction were given.

112

Semi-Annual Social Monitoring Report (July to December 2020)

On November 28, 2020 (277/08/13), the consultation meeting of Pragatinagar Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mr. Shanta Raj Sharma, WUSC Chairperson and made the following decisions:

Attendees: Total: 11; Male: 6; Female: 5

Agendas and decisions: Agenda: 1 – Regarding OBA

Decisions: 1. Discussed on the model of the toilet construction and decided to sign the agreement with RPMO.

113

Semi-Annual Social Monitoring Report (July to December 2020)

October

On October 02, 2020 (2077/06/13), the consultation meeting of Pragatinagar Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mr. Arjun Kumar Adhikari, Coordinator of the staff selection committee and made the following decisions: Attendees: Total: 5; Male: 4; Female: 1 Agendas and decisions: Agenda: 1 – Regarding the publication of the final result Decisions: 1. It was decided to publish the final result as per the qualification order on the basis of written exam and interview taken for sub-engineer. S.N Name Address Result 1 Nirajan Chaudhary Rapti-6 Passed 2 Ram Bahadur Roka Magar Rapti-2 Waiting

114

Semi-Annual Social Monitoring Report (July to December 2020)

115

Semi-Annual Social Monitoring Report (July to December 2020)

116

Semi-Annual Social Monitoring Report (July to December 2020)

On October 09, 2020 (2077/06/23), the consultation meeting of Pragatinagar Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mr. Shanta Raj Sharma, WUSC Chairperson and made the following decisions: Attendees: Total: 17; Male: 11; Female: 6 Agendas and decisions: Agenda: 1 – Regarding Expenditure Details Agenda: 2 – Regarding Final Name List of OBA Agenda: 3 – Regarding raising the amount of drinking water Decisions: 2. It was decided to approve the details of the expenditure of 2 Asoj to 2 Asoj 2077, which was spent in order to receive the vehicle from Department of Water Supply and Sewerage Management Kathmandu as per the agreement between the Government of Nepal and the Asian Development Bank. 3. It was decided to endorse the final list of applications for OBA grant for HH tap connections and toilet construction. 4. As the work is hampered due to delay in collection of money from the consumers so it was decided to write a notice to ward office 5, 7 and 8 and also decided to do information dissemination in the working site.

117

Semi-Annual Social Monitoring Report (July to December 2020)

118

Semi-Annual Social Monitoring Report (July to December 2020)

119

Semi-Annual Social Monitoring Report (July to December 2020)

On October 09, 2020 (2077/06/28), the consultation meeting of Pragatinagar Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mr. Shantaraj Sharma, WUSC Chairperson and made the following decisions: Attendees: Total: 12 Male: 7 Female: 5 Agendas and decisions: Agenda: 1 – Final list of OBA applications

Decisions: It was decided to endorse the final list of applications for OBA grant for HH tap connections and toilet construction which consists of 61 HHs from Ward No # 5, 17 HHs from Ward No # 7 and 129 HHs from Ward No # 8 by publishing the notice in this regard and 28 HHs were rejected.

120

Semi-Annual Social Monitoring Report (July to December 2020)

Pragatinagar (August)

On Aug 22, 2020 (2077/05/10), the consultation meeting of Pragatinagar Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mr. Shanta Raj Sharma, WUSC Chairperson and made the following decisions: Attendees: Total: 6; Male: 3; Female: 3 Agendas and decisions: Agenda: 1 – Resolution of grievance Decisions: Since the people of southern side of Sansad road Tedhi galli, ward number 8, Rapti Gaupalika have registered a grievance that this locality is missing for survey work, although it is under the territory of Pragatinagar Water Supply and Sanitation Project, the grievance was resolved to include the same locality in project coverage area by carrying out the re-survey and extension of pipeline.

121

Semi-Annual Social Monitoring Report (July to December 2020)

2. Siddhanath (November)

122

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation On November 30, 2020 (2077/08/15), the consultation meeting of Siddhanath Baijanath Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mr. Karbir Singh Airee, WUSC Chairperson and made the following decisions: Attendees: Total: 12; Male: 7; Female: 5 Agendas and decisions: Agenda: 1 – Regarding OBA. Decisions: 1. The total selected households under OBA program of Siddhanath Baijanath WSSSP on Ward No. 6, 8 and 10 for the construction of toilets and tap connection have been verified on the basis of field verification and the given indicators. Also the selected households have been recommended by the concerned Ward offices and Office of the Bhimdutta Municipality. So the decision has been made that the WUSC shall verify the following households and forward the final documents to the concerned authorities for agreement purpose. S.N Ward No. Selected Household No. Tap Connection Toilet Construction 1 6 22 22 17 2 8 12 12 12 3 10 70 70 61 Total 104 104 90

123

Semi-Annual Social Monitoring Report (July to December 2020)

124

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation On November 24, 2020 (2077/08/09), the consultation meeting of Siddhanath Baijanath Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mr. Karbir Singh Airee, WUSC Chairperson and made the following decisions: Attendees: Total: 9; Male: 4; Female: 5 Agendas and decisions: Agenda: 1 – Recommendation of OBA selected households. Decisions: 1. The door to door field verification campaign conducted by the representatives of WUSC, WRPMO, Consultant, respective Ward and Tole Development Coordinator for the selection of households for the construction of toilets and tap connection under OBA program have been completed. It is found that the selected households fulfilled the criteria of OBA program. Hence the decision has been made that WUSC shall recommend the list of the households to the concerned authority and also inform the respective Ward offices for the recommendation via letter.

S.N Ward No. Selected Household Tap Connection Toilet Construction No. 1 6 22 22 17 2 8 12 12 12 3 10 70 70 61 Total 104 104 90

125

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation On November 2, 2020 (2077/07/17), the consultation meeting of Siddhanath Baijanath Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mr. Karbir Singh Airee, WUSC Chairperson and made the following decisions: Attendees: Total: 5; Male: 2; Female: 3 Agendas and decisions: Agenda: 1 – Regarding Public Toilet. Decisions: 1. The required land area of 14m*12m for the construction of public toilet in Siddhanath Baijanath WSSSP has been selected at Ward 6 near the office of Ward 6, Health post and Mahendra Highway. It is decided by the WUSC to request to the Committee of Ward 6 for the acquisition of required land for the construction of Public Toilet.

126

Semi-Annual Social Monitoring Report (July to December 2020)

Siddhanath (October)

127

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation On October 12, 2020 (2077/06/26), the consultation meeting of Siddhanath Baijanath Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mr. Karbir Aire, WUSC Chairperson and made the following decisions: Attendees: Total: 11 Male: 7 Female: 4 Agendas and decisions: Agenda: 1 – Additional items to be included in VO. Decisions: 1. E/W work excavation quantity increased due to additional pipe line to be included in VO 2. Additional concrete work, form work and steel work shall be done in DTW2 compound wall included in VO 3. Additional Random Rubble (RR) masonry work shall be done in DTW2 compound wall due to increment in wall height 4. Additional finishing work in OHT compound wall to be included in VO. 5. Additional Gabion work in DTW2 shall to be included in VO. 6. Some pipe line omitted in design will be included in VO 7. Due to COVID-19 pandemic, composite pipe for house hold connection mentioned in BoQ could not be made available, therefore PE pipes and fittings will be made available for HH connection and need to be included in VO 8. Electromechanical work including pump, transformer, voltage stabilizer and generator are missing in DTW2, therefore these items shall be included in VO. Also riser pipes for 3 deep tube wells will be included in VO

128

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation On October 9, 2020 (2077/06/23), the consultation meeting of Siddhanath Baijanath Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mr. Karbir Aire, WUSC Chairperson and made the following decisions: Attendees: Total: 17; Male: 11; Female: 6 Agendas and decisions: Agenda: 1 – New rate negotiation for purposed VO Decisions: 1 It is found that cost prices of materials included in purposed VO prevail the market rates, hence on behalf of WUSC, ICG Consultant and contractor, it has been endorsed new rates for negotiation for purposed VO.

129

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation On October 20, 2020 (2077/06/20), the consultation meeting of Siddhanath Baijanath Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mr. Karbir Aire, WUSC Chairperson and made the following decisions: Attendees: Total: 16; Male: 11; Female: 5 Agendas and decisions: Agenda: 1 - Supervision Work Agenda: 2- Tap faucets Decisions: 1. Attendees have decided to discuss items to be included in VO, followed by construction supervision work in project area. 2. WUSC has decided to demand tap faucets.

130

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation On October 12, 2020 (2077/06/26), the consultation meeting of Siddhanath Baijanath Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mr. Karbir Aire, WUSC Chairperson and made the following decisions: Attendees: Total: 11; Male: 9; Female: 2 Agendas and decisions: Agenda: 1 – Recommendation of OBA at wards 6 and 8 Decisions: 1 Those water users in ward 6 and 8, who are still omitted and not applied for OBA, could take time and reapply and finally list of applicants, will be recommended for OBA within two days after submission of applications.

131

Semi-Annual Social Monitoring Report (July to December 2020)

132

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation On October 10, 2020 (2077/06/24), the consultation meeting of Siddhanath Baijanath Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mr. Karbir Aire, WUSC Chairperson and made the following decisions: Attendees: Total: 27 Male: 23 Female: 4 Agendas and decisions: Agenda: 1 - General briefing OBA in ward 10 Agenda: 2 – Final selections of HHs and recommendation Decisions: 1 All concerned stakeholders like Ward 10, WUSC, Consultants, ICG and street co-coordinators under Siddhanath Baijanath Water Supply Project decided to commit OBA implementation in project area 2 It is unanimously decided that still those HHs who are eligible to OBA and not included in list, there will be final visit from task force door to door and final recommendation list will be prepared through next meeting.

133

Semi-Annual Social Monitoring Report (July to December 2020)

Siddhanath (August)

134

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation On August 17, 2020 (2077/05/01), the consultation meeting of Siddhanath Baijanath Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mr. Karbir Aire, WUSC Chairperson and made the following decisions: Attendees: Total: 10 Male: 6 Female: 4 Agendas and decisions: Agenda: 1 – Formation of Task force for field verification of applications for OBA

Decisions: 1. It was decided to form a Task force for field verification of applications received for OBA grant in Siddhanath Baijanath Water Supply and Sanitation Project comprising of 7 members under the leadership of WUSC chairperson including the representatives of concerned wards and Tole Coordinators: i. Chairperson - Mr. Karbir Singh Aire ii. Member - Mrs. Janaki Bista iii. Member - Mr. Tul Bahadur Khadka iv. Member - Mrs. Laxmi Khadayat v. Member - Mr. Ananta Gautam vi. Member - Mr. Tirtha Raj Joshi vii. Member - Mrs. Prema Subba

135

Semi-Annual Social Monitoring Report (July to December 2020)

3. Shubaghat (October)

English Translation On October 11, 2020 (2077/06/25), the consultation meeting of Shubhaghat Urban Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mr. Sanjiv Kumar Shah, RPMO Chief and made the following decisions: Attendees: Total: 13; Male: 10; Female: 03 Agendas and decisions: Agenda: 1 – Site for public toilet Agenda: 2 - Rate and cost estimation of new items Decisions: 3. The Chairman of WUSC committed to provide site for public toilet within one month 4. The contractor will submit the rates of new items due to variation and the consultant will prepare their rates and cost estimation for the new items. Additional finishing work in OHT compound wall to be included in VO.

136

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation On October 13, 2020 (2077/06/27), the consultation meeting of Shubhaghat Urban Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mrs. Maina BK, WUSC Chairperson and made the following decisions: Attendees: Total: 14; Male: 11; Female: 3 Agendas and decisions: Agenda: 1 – Recommendation of IPC 4.

Decisions: 1. It was decided to recommend the IPC 4 as submitted by the contractor and recommended by the consultant.

137

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation On October 05, 2020 (2077/06/19), representatives from the contractor, consultant and the complainer had a meeting to discuss and resolve the complaint made by an affected person during pipe laying action. The meeting made the following decisions: Attendees: Total: 10 Male: 10 Female: 01

Agendas and decisions: Agenda: 1 – Listen and Resolve the problem faced by an affected person during pipe laying.

Decisions: The affected person had a complaint that he has plan to construct a house in the area of proposed pipe laying. Therefore he obstructed the pipe laying work. The meeting decided that the pipe laying be shifted slightly towards downstream area so that it will not affect the house construction.

138

Semi-Annual Social Monitoring Report (July to December 2020)

Shubaghat (August)

139

Semi-Annual Social Monitoring Report (July to December 2020)

140

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation On August 01, 2020 (2077/04/17), the consultation meeting of Subhaghat Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mrs. Maina B.K., WUSC Chairperson and made the following decisions: Attendees: Total: 13 Male: 9 Female: 4 Agendas and decisions: Agenda: 1 – Cash collection from beneficiaries Agenda: 2 – Time extension of Sub-Engineer Agenda: 3 – Formation of Task force for OBA program Agenda: 4 – Drawing, specification and BOQ Agenda: 5 – Hand over of vehicle Decisions: 1. As per requirement of UWSSP and agreement with PMO, upfront cash contribution @ 5% from the beneficiaries of coverage ward number 6, 7, 8 and 9 is mandatory to deposit and the responsibility was assigned to concerned ward-wise sub-committees. Till date, it has been updated and cleared from ward # 8 and 9 and still remaining from ward # 6 and 7. So, it was decided to discuss at the office with Mr. Hari Pariyar, Mr. Biraute B.K. and Mr. Sahabir Thapa from Ward # 6 being most huge cash to be collected. 2. The performance of Sub-Engineer is not satisfactory and the written as well as verbal clarification were also acceptable. So, it was decided not to extend his contract if his performance evaluation for next one month is not satisfactory. It was also decided to make contract agreement with Mr. Sher Bahadur Poudel, Account Officer of this organization because of expiry of his contract. 3. It was decided to commence the field verification of applications received under OBA program for toilet construction and HH Tap connection from 2077/04/21 at ward # 6 with the presence of concerned ward chairperson, one representative from main WUSC and all members of sub- committee. 4. Due to lack of necessary drawings, specification and BOQ with the WUSC, the team has been facing difficulties. So, it was decided to request RPMO, Nepalgunj to provide the same. 5. It was decided to make the chairperson of the WUSC responsible for coordination with ICG Engineer and CSE for use of vehicle allotted to this Users’ Committee and received from the Project Management Office, Department of Water Supply and Sewerage Management, Kathmandu.

141

Semi-Annual Social Monitoring Report (July to December 2020)

142

Semi-Annual Social Monitoring Report (July to December 2020)

On August 05, 2020 (2077/04/21), the consultation meeting of Subhaghat Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mrs. Maina B.K., WUSC Chairperson and made the following decisions: Attendees: Total: 13 Male: 8 Female: 5 Agendas and decisions: Agenda: 1 – Location change of office room and toilet on office building Agenda: 2 – Maintaining of social distance during working hour Decisions: 1. It was decided to change unanimously the location of office room and toilet in previous drawing by discussing among WUSC, representatives of the contractor, WRDSMC (ITECO) and RPMO because the location of office room and toilet is not appropriate in the previously approved drawing. 2. It was decided to appeal all project staff, WUSC and workers to follow strictly the health and safety protocols prepared by the government during the working period in Subhaghat Water Supply and Sanitation Project and it was also decided if anybody violates the protocols, s/he would be responsible for punishment as well as penalty for medical expenses.

143

Semi-Annual Social Monitoring Report (July to December 2020)

On August 14, 2020 (2077/04/30), the consultation meeting of Subhaghat Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mrs. Maina B.K., WUSC Chairperson and made the following decisions: Attendees: Total: 18

144

Semi-Annual Social Monitoring Report (July to December 2020)

Male: 14 Female: 4 Agendas and decisions: Agenda: 1 – Prevention from COVID-19 Agenda: 2 – Formation of Health and Safety Committee Agenda: 3 – Contract Extension Decisions: 1. It was decided to make continuity of the construction works by providing all materials related to the health and safety protocols such as masks, sanitizers as well as placing banners at working sites and conduction of awareness campaign for all construction workers and project team. 2. It was decided to form Health and Safety Committee to make all workers safe and prevention from the pandemic of COVID-19 with following members: i. Anandita Dhakal - Coordinator (EMP Monitor) ii. Basanta Rayamajhi - Members (Engineer, Contractor) iii. Govinda Oli - Members (WUSC) iv. Dambar Bahadur Bista - Member (Worker) v. Prem B.K. - Member (Worker) vi. Dipak B.K. - Member (Worker) vii. Man Singh Thagunna - Member (Worker) viii. Om Prakash B.K. - Member (Worker) ix. Parash Mani Bhatta - ICG Engineer 3. It was decided not to extend the contract of Sub-Engineer of Subhaghat Water Supply and Sanitation Users’ Committee Mr. Mahendra Bahadur Karki because of his unwillingness to work and no improvement of his performance although he was given one month timeframe to be improved. It was also decided to extend the contract of Mr. Sher Bahadur Poudel, Account Officer of this organization.

145

Semi-Annual Social Monitoring Report (July to December 2020)

4. Chainpur (October)

146

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation On September 27, 2020 (2077/06/11), the consultation meeting was held under the chairmanship of Mr. Lokendra Bahadur Bista, WUSC Chairperson of Chainpur Water Supply and Sanitation Project, Bajhang and made the following decisions: Attendees: Total: 15 Male: 12 Female: 3 Agendas and decisions: Agenda: 1 – Regarding to extend the time of the project Agenda: 2 – Regarding variation order N.1 Decisions: 1. According to Chainpur Water Supply and Sanitation Project, Bajhang, the interim probable completion date of the project is 22nd of Asoj, 2077 but due to various reasons such as lockdown due to corona pandemic, snowfall, various changes in design, etc the project could not be completed at that time, so the contractor has requested to extend the time of the project by 268 days. It was decided to recommend extension of 180 days as it seemed appropriate to extend the time of the project by 180 days out of the 268 days. 2. There are some essential items for the project but not included in the BOQ and some items are added so various items to be included in variation order –I were discussed and recommended on the following topics: a. Soil work: Pankot–Golai area is included in this project, therefore extra quantity of pipeline is included & some location of structure is changed to Bhopur station. Therefore quantity of earthwork is increased, thus the extra quantity is included in VO-01 b. In reinstatement of concrete roads: Concrete road length in Chainpur bazaar has to be dismantle for laying the water supply pipeline work as well as for re concreting by M15 grade of concrete, In actual BoQ quantity was less. Therefore total quantity is increased & included in VO-01. c. Miscellaneous: In order to provide protection for two sump well in Seti river Gabion quantity was calculated less in actual BoQ, therefore extra required quantity is included in VO-01 d. Regarding the pipeline: During the design of the project, the pipeline required in different was not taken accurately in the BOQ and inclusion of Pankot- Golai area was added to the variation order –I. e. Stone Wall: Since different structure of the Chainpur Water Supply and Sanitation Project are located on a sloping slope, almost all the structures have to be protected with stone masonry retaining wall in order to reduce the probability of landslide, so extra quantity is included as per site condition in VO –I. f. Regarding Tractor: The tractor to be provided is 45 HP in BOQ but project site is in a hilly area, tractor of that capacity will not be able to meet the demand. So at least 65 HP tractor to be added to variation order –I, but in final discussion with RPMO team this consideration is omitted therefore in revised final VO-01 original contract value & specification of tractor is taken.

.

147

Semi-Annual Social Monitoring Report (July to December 2020)

148

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation On October 13th, 2020 (2077/06/27), under the Chainpur Water Supply and Sanitation Project, Bajhang, the health workers of Kamana Health Clinic and Diagnostic Center conducted a general health check-up of the workers and provided information about health and sanitation and Covid-19 at Bhopur site: Attendees: Total: 48 M=46 F=2

Agendas and decisions: Agenda: 1 – General Health check-up of the workers Decisions: 1. The health workers of Kamana Health Clinic and Diagnostic Center conducted a general health check-up of the workers and provided information about health and sanitation and Covid-19 at Bhopur site.

149

Semi-Annual Social Monitoring Report (July to December 2020)

150

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation On October 14, 2020 (2077/06/28), the consultation meeting of Chainpur Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mr. Lokendra Bahadur Bista,, WUSC Chairperson and made the following decisions: Attendees: Total: 16 Male: 13 Female: 3 Agendas and decisions: Agenda: 1 – Final list of OBA applications

Decisions: 1. It was decided to endorse the final list of applications for OBA grant for HH tap connections and toilet construction which consists of 43 HHs from Ward No # 9, 107 HHs from Ward No # 10 and 3 HHs from Ward No # 11 by publishing the notice in this regard.

151

Semi-Annual Social Monitoring Report (July to December 2020)

152

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation On October 15, 2020 (2077/06/29), the consultation meeting was held under the chairmanship of Mr. Lokendra Bahadur Bista, WUSC Chairperson of Chainpur Water Supply and Sanitation Project, Bajhang and made the following decisions: Attendees: Total: 11 Male: 11 Female: 0 Agendas and decisions: Agenda: 1 – Regarding IPC-05 Agenda: 2 – According to IPC-05, Requesting for loan from City Development Fund

Decisions: 1. According to IPC-05, Rs 80,88,014.81 is collected from contractor Ashish-C.A.B. J.V. of the Chainpur Water Supply and Sanitation Users Project, Bajhang in which 5% is under drinking water structure and 15% under sanitation (Amount-427772.31) will be Rs. 427772.31 in which mortgage 5% will be Rs. 21388.62 and contract tax 1.5% will be Rs 6416.58, Contractor Fund 0.1% will be 427.77 and VAT 6.5% will be Rs. 27805.17 to the total amount Rs 56038.17. The remaining amount will be Rs. 351424.24 with VAT 13% amount will be Rs 407034.64 which is the amount to be paid by committee to the contractor. 2. It was decided, according to IPC-05, Rs 8088014.81 is collected from contractor Ashish-C.A.B. J.V. of the Chainpur Water Supply and Sanitation Users Project, Bajhang in which 25% of amount under city Development Fund will be Rs. 1963574.66 with VAT 13% (Rs.255364.72) the total amount will be Rs. 2012385.94 which is the amount to be asked for loan from City Development Fund for contractor.

153

Semi-Annual Social Monitoring Report (July to December 2020)

5. Liwang (October)

On October 04, 2020 (2077/06/18), the consultation meeting of Liwang Water Supply and Sanitation Users’ Committee was held under the chairmanship of Mr. Liladhar Acharya, WUSC Chairperson and made the following decisions: Attendees: Total: 13 Male: 9 Female: 4 Agendas and decisions: Agenda: 1 – Fourth Running Bill Agenda: 2 – Dhungebisauna RVT and WUSC building Agenda: 3 – Miscellaneous Decisions: 1. It was decided to endorse the fourth IPC-04(Amount Nrs: 28956675.18).Also endorse to pay contractor 5%(pay also 25% from TDF loan)money of this IPC-04. 2. Request to construct 40m3 new RVT at Dhungebisauna and also request to add meeting hall room at second floor of WUSC building. 3. It was decided to hold next meeting as per necessity

154

Semi-Annual Social Monitoring Report (July to December 2020)

Liwang (August)

155

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation On Aug 06, 2020 (2077/04/22), the consultation meeting was held under the chairmanship of Mrs. Nisha Tiruwa, Coordinator of OBA program for ward # 9 for Chainpur Water Supply and Sanitation Project, Bajhang and made the following decisions: Attendees: Total: 12 Male: 9 Female: 3 Agendas and decisions: Agenda: 1 – Selection of poor household for OBA grant Decisions: 1. The field verification for applications of OBA grant received from Ward number 9 was executed by the joint team of representatives of WUSC, Ward, RPMO and WRDSMC (ITECO) and it was decided to recommend the following 43 households for final approval for OBA grant: i. Dalit – 23 HHs ii. Brahmin/ – 20 HHs

156

Semi-Annual Social Monitoring Report (July to December 2020)

157

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation On Aug 18, 2020 (2077/05/02), the consultation meeting was held under the chairmanship of Mrs. Kumari Hira Bhatta, Acting Ward Chairperson, Ward 10 for Chainpur Water Supply and Sanitation Project, Bajhang and made the following decisions: Attendees: Total: 27 Male: 17 Female: 10 Agendas and decisions: Agenda: 1 – Formation of Task force (Monitoring) for field verification Agenda: 2 – Field verification of applications for OBA grant Decisions: 1. It was decided to form a Task force (Monitoring) for field verification of applications received under OBA grant for construction of toilets and HH tap connections with following members: i. Coordinator – Phakir Roaya ii. Member - Kandhe Khadka iii. Member - Bijendra Nepali iv. Member - Dharma Raj Rasaili v. Member - Shankar Rasaili vi. Member - Urmila Chitrakar vii. Member - Prem Prakash Chhtyal viii. Member - Raj Kumari Badayak ix. Member - Bhawana Khadka It was decided to submit the list of applications for OBA grant to the office of Chainpur Water Supply and Sanitation Users’ Committee for construction of toilet and HH tap connections after field verification by the Task force within one week.

158

Semi-Annual Social Monitoring Report (July to December 2020)

Annex-3: Photographs

159

Semi-Annual Social Monitoring Report (July to December 2020)

I. Photo No. 1 Rebar works for the concreting of slab of Photo No. 2: : Column concreting work of OHT Generator House under Siddhanath-Baijanath Siddhanath-Baijanath subproject subproject

Photo No. 3: Progress of Social Center Building. Photo No. 4: Progress of Boundary wall construction Siddhanath-Baijanath subproject work Siddhanath-Baijanath subproject

Photo No. 6: Progress of Generator House Photo No. 5: Consultation meeting on OBA activities. construction

160

Semi-Annual Social Monitoring Report (July to December 2020)

Khalanga

Photo No.1: Sedimentation site excavation, Khalanga Photo No. 2: Site visit at the office building location Khalanga.

Photo No. 3: Galphai RVT location site clearance, Photo No. 4: Galphai RVT location site clearance, Khalanga Khalanga

Photo no.5 Dhauligad intake site visited at Galphai, Photo no.6 Intake at Bangabagar source, Khalanga Khalanga

161

Semi-Annual Social Monitoring Report (July to December 2020)

Center and Eastern

1. Photo no.1: Fever checking of the participants – Photo no.2: Facilitating by Team Leader (RDSMC) on Orientation to WUSC and stakeholders, Panchkal orientation to WUSC and stakeholders at Deurali - Hupsekkot

2. 3. Photo no.3: TNA workshop in Ilam, Sandakpur Photo no.4:TNA workshop in Ilam , Sandakpur December

4. Photo no.5: TNA workshop in Ilam, Sandakpur Photo no.6 TNA workshop in Ilam, Sandakpur

162

Semi-Annual Social Monitoring Report (July to December 2020)

Annex-4: GRC Committee Name List

163

Semi-Annual Social Monitoring Report (July to December 2020)

A) Project, Municipality and WUSC level Grievance Redress Committees Project level GRC Designation/Status S.N. Name Designation on GRC 1 Mr. Ramkumar Shrestha Project Director, UWSSP, PMO Coordinator of GRC 2 Concerned Deputiy Directors Deputy Project Director-PMO Member-Secretary 3 Ms. Ajita Regmi Social Safeguard Officer, PMO Member Environmental Safeguard Officer, 4 Mr. Manish Raj Member PMO Social Safeguard Specialist, 5 Mr. Shiva Adhikari Member PMQAC Environmental Safeguard 6 Mr. Arun Acharya Member Specialist, PMQAC 7 Representative from NEFIN Representative Member 1. Bhojpur: WUSC level GRC Designation/Status S.N. Name Designation on GRC 1 Mr.Parbin Kumar Suwal Chairperson WUSC Chairperson GRC Social Safeguard Specialist 2 Mr. Dipendra Pokheral Member secretary ERDSMC Construction Super vision 3 Laxmi Prasad Chaudhary Member Engineer/ ERDSMC 4 Mr. Nabin Kumar Kalyan Engineer Contractor Member 5 Mrs. Renuka Poudel Social Mobilizer ERPMO Member Bhojpur: Municipality level GRC Designation/Status S.No. Name Designation on GRC 1 Mr.Kailash Kumar Ale Mayor, Chairperson GRC 2 Mr. Padam Kunwar Regional Project Manager-RPMO Member secretary Social Safeguard Specialist- 3 Mr. Dipendra Pokheral Member ERDSMC Construction Supervision Engineer 4 Mr. Laxmi Prasad Chaudhary Member - ERDSMC 5 Mr. Nabin Kumar Kalyan Local user Member 6 Mrs. Renuka Poudel ICG Engineer - RPMO Member Env focal person/Social Safeguard 7 Mr. Ankit Man Shrestha Member Officer-RPMO(Engineer ERPMO) 2. Ilam: WUSC level GRC Designation/Status S.No. Name Designation on GRC 1 Mr. Kedar Thapa Chairperson WUSC Chairperson GRC 2 Mr. Tilak Bahadur Thakuri secretary WUSCC Member secretary Social Safeguard Specialist 3 Mr. Dipendra Pokheral Member ERDSMC Construction Super vision 4 Mr. Dhirendra Yadav Member Engineer/ ERDSMC 5 Mr.Rupdhan Rai local user Member 6 Mr. Bibek Jha Engineer ERPMO Member 7 Mr. Megraj Dhimal Engineer Contractor Member 8 Mr. Gopal Poudel Member WUSC Member 9 Mrs. Mokchhe Dahal Social Mobilizer ERPMO Member Ilam: Municipality level GRC Designation/Status S.No Name Designation on GRC 1 Mahesh Basnet Mayor, Chairperson 2 Mr. Padam Kunwar Regional Project Manager-RPMO Member secretary 3 Bibek Jha,ICG,Er Member secretary Member 4 Ram Pachhera,CSE Member Member Meghraj Dhimal,Site 5 Member Member engineer/contractor 6 Tara Gurung SM Member Member 7 Dhana maya Subedi,SM Member Member

164

Semi-Annual Social Monitoring Report (July to December 2020)

3. Diktel: WUSC level GRC Designation/Status S.No. Name Designation on GRC 1 Mr. Dhan Kumar Joshi Chairperson WUSC Chairperson GRC Social Safeguard Specialist 2 Mr. Dipendra Pokheral Member ERDSMC Construction Super vision 3 Mr. Bhola Prasad Chaudhary Member Engineer/ ERDSMC 4 Mr. Santosh Basnet Engineer Contractor Member 5 Mrs. Bhawana Karki Social Mobilizer ERPMO Member

Diktel: Municipality level GRC Designation/Status S.No Name Designation on GRC Mayor, Rupakot Majuwagadhi 1 Mr. Deep Narayan Rijal Chairperson GRC Municipality 2 Mr. Padam Kunwar Regional Project Manager-RPMO Member secretary 2 ,ICG,Engineer Member secretary Member secretary 3 Mr. Bhola Prasad Chaudhary ,CSE Member Member

4 Santosh Basnet,CM,contractor Member Member

5 Bhawana Karki SM Member Member

4. Subhaghat: WUSC level GRC Designation/Status S.No. Name Designation on GRC 1 Mrs. Maina B.K Chairperson WUSC Chairperson GRC Social Safeguard Specialist 2 Mr. Gauri prasad Sharma Member WRDSMC Construction Super vision 3 Mr.Santosh Bhujel Member Engineer/ WRDSMC 4 Basanta Rayamajhi Engineer Contractor Member 5 Ms. Janaki Gautam Social Mobilizer WRPMO Member Subhaghat: Municipality level GRC Designation/ S.No. Name Designation Status on GRC 1 Mr. Hasta Pun Mayor-Gurvakot Municipality Chairperson GRC 2 Mr. Purna Prasad Upadhyaya Regional Project Manager-RPMO Member-Secretary Social Safeguard Specialist- 3 Mr. Gauri Prasad Sharma Member WRDSMC Construction Supervision Construction Supervision 4 Member Engineer- WRDSMC Engineer- WRDSMC 5 Social Safeguard Officer Social Safeguard Officer-RPMO Member 6 ICG Engineer-RPMO ICG Engineer-RPMO Member Sub project Affected Family 7 Affected Family Representative Member Representative 8 Mr. Harihar Regmi Chairman WUSC Member

4. Subhaghat: WUSC level GRC Designation/Status S.No. Name Designation on GRC 1 Mrs. Maina B.K Chairperson WUSC Chairperson GRC

165

Semi-Annual Social Monitoring Report (July to December 2020)

Social Safeguard Specialist 2 Mr. Gauri prasad Sharma Member WRDSMC Construction Super vision 3 Mr.Santosh Bhujel Member Engineer/ WRDSMC 4 Basanta Rayamajhi Engineer Contractor Member 5 Ms. Janaki Gautam Social Mobilizer WRPMO Member

Subhaghat: Municipality level GRC Designation/ S.No. Name Designation Status on GRC 1 Mr. Hasta Pun Mayor-Gurvakot Municipality Chairperson GRC 2 Mr. Purna Prasad Upadhyaya Regional Project Manager-RPMO Member-Secretary Social Safeguard Specialist- 3 Mr. Gauri Prasad Sharma Member WRDSMC Construction Supervision Construction Supervision 4 Member Engineer- WRDSMC Engineer- WRDSMC 5 Social Safeguard Officer Social Safeguard Officer-RPMO Member 6 ICG Engineer-RPMO ICG Engineer-RPMO Member Sub project Affected Family 7 Affected Family Representative Member Representative 8 Mr. Harihar Regmi Chairman WUSC Member

5. Siddhanath Baijnath: WUSC level GRC Designation/Status S.No. Name Designation on GRC 1 Mr. Karbeer Singh Airee Chairperson WUSC Chairperson GRC Social Safeguard Specialist - 2 Mr. Gauri Prasad Sharma Member WDRSMC Construction Supervision Engineer- 3 Mr. Ananta Prasad Gautam Member WRDSMC 4 Social Mobilizer Social Mobilizer - WRDSMC Member 5 Contractor Representative Contractor Representative Member

Siddhanath Baijnath: Municipality level GRC Designation/Status S.No. Name Designation on GRC 1 Mr. Surendra Bista Mayor, Bhimdutta Municipality Chairperson GRC 2 Mr. Purna Prasad Upadhyaya Regional Project Manager-RPMO Member, Secretary Social Safeguard Specialist- 3 Mr. Gauri Prasad Sharma Member DRSMC Construction Supervision Engineer - 4 Mr. Ananta Prasad Gautam Member DRSMC 5 Social Safeguard Officer Social Safeguard Officer-RPMO Member 6 Mr. Balram Yadav ICG Engineer - RPMO Member Sub project Affected Family 7 Affected Family Representative Member Representative 8 Mr. Tul Bahadur Khadaka Secretary-WUSC Member 9 Mr. Keshav Bhatta Engineer-Contractor Member

6. Chainpur: WUSC level GRC Designation/Status S.No. Name Designation on GRC 1 Mr.Lokendra Bahadur Bista Chairperson WUSC Chairperson GRC

166

Semi-Annual Social Monitoring Report (July to December 2020)

Social Safeguard Specialist- 2 Mr.Gauri Prasad Sharma Member WRDSMC Construction Supervision 3 Construction Supervision Engineer Member Engineer- WRDSMC 4 Social Mobilizer Social Mobilizer- WRDSMC Member 5 Contractor Representative Contractor Representative Member

Chainpur: Municipality level GRC Designation/Status S.N Name Designation on GRC 1 Mr. Birendra Bahadur Khadka Mayor-Jay Prithvi Municipality Chairperson GRC 2 Mr. Purna Prasad Upadhyaya Regional Project Manager-RPMO Member-Secretary Social Safeguard Specialist- 3 Mr.Gauri Prasad Sharma Member WRDSMC Construction Supervision Construction Supervision 4 Member Engineer- WRDSMC Engineer- WRDSMC 5 Social Safeguard Officer Social Safeguard Officer-RPMO Member 6 ICG Engineer-RPMO ICG Engineer-RPMO Member Sub project Affected Family 7 Affected Family Representative Member Representative 8 Mr.Prem Prakash Chhatyal Secretary-WUSC Member 9 Mr Engineer-Contractor Engineer-Contractor Member

7. Liwang: WUSC level GRC Designation/Status S.N. Name Designation on GRC 1 Mr.Liladhar Acharya Chairperson WUSC Chairperson GRC Social Safeguard Specialist- 2 Mr.Gauri Prasad Sharma Member WRDSMC Construction Supervision 3 Construction Supervision Engineer Member Engineer- WRDSMC 4 Social Mobilizer Social Mobilizer- WRDSMC Member 5 Mr. Sobik Shrestha Contractor Representative Member

Liwang: Municipality level GRC Designation/Status S.N. Name Designation on GRC 1 Mr. Purna K.C. Mayor-Rolpa Municipality Chairperson GRC 2 Mr. Purna Prasad Upadhyaya Regional Project Manager-RPMO Member-Secretary Social Safeguard Specialist- 3 Mr.Gauri Prasad Sharma Member WRDSMC Construction Supervision Construction Supervision 4 Member Engineer- WRDSMC Engineer- WRDSMC 5 Social Safeguard Officer Social Safeguard Officer-RPMO Member 6 ICG Engineer-RPMO ICG Engineer-RPMO Member Sub project Affected Family 7 Affected Family Representative Member Representative 8 Mr.Hari Prasad Acharya Secretary-WUSC Member 9 Mr -Sobik Shrestha Project Engineer-Contractor Member

8. Pragatinagar: WUSC level GRC Designation/Status S.N. Name Designation on GRC 1 Mr.Shanta Raj Sharma Chairperson WUSC Chairperson GRC Social Safeguard Specialist- 2 Mr.Gauri Prasad Sharma Member WRDSMC Construction Supervision 3 Mr. Chandra Kant Jha Member Engineer- WRDSMC 4 Miss Sushma Bhujel Social Mobilizer- WRDSMC Member 5 Mr. Bechulal Shrestha Contractor Representative Member

167

Semi-Annual Social Monitoring Report (July to December 2020)

Pragatinagar: Rural Municipality level GRC Designation/Status S.N. Name Designation on GRC 1 Mr. Numananda Subedi Chairman Rapti Rural Municipality Chairperson GRC 2 Mr. Purna Prasad Upadhyaya Regional Project Manager-RPMO Member-Secretary Social Safeguard Specialist- 3 Mr.Gauri Prasad Sharma Member WRDSMC Construction Supervision 4 Mr. Chandra Kant Jha Member Engineer- WRDSMC 5 Social Safeguard Officer Social Safeguard Officer-RPMO Member 6 ICG Engineer-RPMO ICG Engineer-RPMO Member Sub project affected family 7 Affected Family Representative Member representative 8 Mr.Omnath Banjade Secretary-WUSC Member 9 Mr Bechulal Shrestha Engineer-Contractor Member

9. Charikot: WUSC level GRC

Designation/Status S.N. Name Designation on GRC 1 Mr. Ram Krishna KC, Chairperson WUSC Chairperson GRC 2 Mr. Biraj Man Shrestha, Ward Chairperson, Ward No.2 Member 3 Mr. Hari Sharan Sapkota, Ward Chairperson, Ward No.3 Member 4 Haribansha Chaulagain, Ward Chairperson, Ward No.4 Member 5 Mr. Ram Chandra Basnet, Ward Chairperson, Ward No.5 Member 6 Mr. Navin Lama, Ward Chairperson, Ward No.6 Member 7 Mr. Kailash Kumar Shrestha, Ward Chairperson, Ward No.7 Member 8 Mr. Pushkal Subedi, ICG Engineer Member 9 Mr. Birendra Maharjan, CSE, CRDSMC Member 10 Mr. Sanjay Shrestha Site Engineer, Contractor Member 11 Ms. Samjhana Basnet, Social Mobilizer, CRDSMC Member

Charikot: Municipality level GRC Designation/Status S.N. Name Designation on GRC 1 Mr. Bharat KC Mayor, Bimeshowar Muicipality Chairperson GRC 2 Mr. Ram Kumar Shrestha Deputy Project Director-PMO Member-Secretary Social Safeguard Specialist- 3 Mr.Samir Dhakal Member CRDSMC Construction Supervision 4 Mr. Birendra Maharjan Member Engineer- CRDSMC 5 Social Safeguard Officer Social Safeguard Officer-RPMO Member 6 Mr. Pushkal Subedi, ICG Engineer-RPMO Member Sub project affected family 7 Affected Family Representative Member representative 8 Mr.Dhurba Basnet Secretary-WUSC Member 9 Mr. Sanjay Shrestha Engineer-Contractor Member

10. Panchkahl: WUSC level GRC Designation/Statu S.N. Name Designation s on GRC 1 Mr. Kumar Prasad Lamichhane Chairperson WUSC Chairperson GRC 2 Mr. Suresh Mahaju CSE (CRDSMC) Member 3 Mr. Samir Dhakal Social Safeguard Specialist Member (CRDSMC) 4 Ms. Apsara Dahal, CM Members (Ward Member (CRDSMC) Representatives) 5 Mr. Indra Man Singh Basnet ( Representative, Contractor Member

168

Semi-Annual Social Monitoring Report (July to December 2020)

Panchkhal: Muniicpality Level GRC Designation/Status S.N. Name Designation on GRC 1 Mr. Mahesh Kharel Mayor, Panchkhal Municipality Chairperson GRC 2 Mr. Tika Bahadur Deputy Director, PMO Secretary Chaudhari, 3 Ms. Sambhavi Khanal ICG Engineer, PMO Member 4 Narman Pahari Representative of Effected People Member

5 Mr. Samir Dhakal Social Safeguard Specialist, Member CRDSMC 6 Mr. Saroj Dhital Representative of Social Organization 7 Mr. Indra Man Singh Representative of Contractor Basnet 8 Mr. Chet Prasad Gautam Secretary, WUSC 10 Mr. Suresh Mahaju CSE, CRDSMC

11 Deurali-Hupsekot: WUSC level GRC S.N Name Designation Designation/Status on GRC 1 Mr.Mek Bahadur Pulami Chairperson WUSC Chairperson GRC 2 Mr.Bhanu Narayan Shrestha CSE (CRDSMC) Member 3 Mr. Samir Dhakal Social Safeguard Specialist Member (CRDSMC) 4 Mr.Bishal KC ICG, Engineer PMO Member 5 Mr.Bhim Narayan Regmi Secretary, WUSC Member

6 Mr. Dal BahadurSoti Trikon Community Trikon Member Community Forest Users Group, Hupsekot-1 7 Ms.Ekata KC SM (ICG, PMO) Member

8 Ms.Sita KC SM, CRDSMC Member Mr.SharanHariGyawali Project Manage, Contractor Member

Deurali-Hupsekot: Rural Municipality level GRC Designation/Status on S.N Name Designation GRC 1 Ms.Laxmi Pandey Hupsekot Rural Municipality Chairperson GRC

2 Mr.Bhanu Narayan CSE (CRDSMC) Member Shrestha 3 Mr. Samir Dhakal Social Safeguard Specialist (CRDSMC) Member 4 Mr.Bishal KC ICG, Engineer PMO Member 5 Mr.Bhim Narayan Secretary, WUSC Member Regmi 6 Mr. Dal BahadurSoti Trikon Community Trikon Community Member Forest Users Group, Hupsekot-1 7 Ms.Ekata KC SM (ICG, PMO) Member

8 Ms.Sita KC SM, CRDSMC Member 9 Mr.SharanHariGyawali Project Manage, Contractor Member

169

Semi-Annual Social Monitoring Report (July to December 2020)

Khalanga: WUSC Level GRC Designation/Status on S.N Name Designation GRC 1 Jaya Dev Joshi WUSC Chairperson Chairperson Social Safeguard Specialist- 2 Gauri Prasad Sharma Member DRSMC Construction Supervision 3 Kuber Singh Member Engineer-DRSMC 4 Social Mobilizer-DRSMC Member 5 Santosh Chand Contractor Representative Member 6 Other Invitee Member

Khalanga: Municipality level Designation/Status on S.N Name Designation GRC 1 Hansa Raj Bhatta Mayor-Mahakali Municipality Chairperson Regional Project Manager- 2 Sanjeev Kumar Saha Member-Secretary RPMO Social Safeguard Specialist- 3 Gauri Prasad Sharma Member DRSMC 4 Khadga Singh Khatri WUSC Secretary Member 5 Santosh Chand Contractor Representative Member 6 Project Affected Person Member 7 Other Invitee Member

170

Semi-Annual Social Monitoring Report (July to December 2020)

Annex-5: Indegenous People's Household selection for Livelihood Training

171

Semi-Annual Social Monitoring Report (July to December 2020)

Summary of TNA Workshop Result

S.N Name of Training Interested Household Number 1 Cow farming 39 2 Swing Netting 20 3 Goat Farming 19 4 Pig Farming 14 5 Kiwi Farming 8 Total 100

Indegenous People selected for Cow farming Ward S.N. Name Address No. Location/Tole Contact No 1 Bishnu rai Sandukpur 2 Malenge Mewa 9825984779 Khom Bahadur Sandukpur 2 Gurung 2 Sangratar rate 9807911406 3 Kamala Gurung Sandukpur 2 Budhbare 9863719996 4 Amrita Rai Gurung Sandukpur 2 Budhbare 9842768560 5 Lalit Gurung Sandukpur 2 Budhbare 9814950419 6 Umesh Gurung Sandukpur 2 Budhbare 9865542487 7 Neha Gurung Sandukpur 2 Budhbare 9864537071 8 Dinesh Gurung Sandukpur 2 Budhbare 9862684057 9 Dhak Maya Gurung Sandukpur 2 Budhbare 9825916330 10 Urmila Rai Sandukpur 2 Gitang 9814987088 11 Lokimaya Gurung Sandukpur 2 Dhadbari 9818815245 12 Mina Kumari Rai Sandukpur 2 Gitang 9817945374 Sandukpur Lama Gau 13 Kumari Gurung 2 Budhbare 9842766955 Sandukpur Lama Gau 14 Yub Bahadur Gurung 2 Budhbare 9864181494 15 Dhan Kumar Rai Sandukpur 2 Gitang 9815970686 16 Bimal Rai Sandukpur 2 Khorsanetar Mewa 9815073519 17 Nubir Rai Sandukpur 2 Khorsanetar Mewa 9817096671 18 Shuk Raj Rai Sandukpur 2 Khorsanetar Mewa 9814055006 19 Kiran Rai Sandukpur 2 Khorsanetar Mewa 20 Aakriti Rai Sandukpur 2 Khorsanetar Mewa 9816026644 21 Ram Kumar Rai Sandukpur 2 Khorsanetar Mewa 9803214709 22 Nar Kumar Rai Sandukpur 2 Mewa Bistare 9815917986 23 Puran Rai Sandukpur 2 Mewa Bistare 9803736985 24 Shridhan Rai Sandukpur 2 Niwa Basti 9813565305 25 Khem Maya Gurung Sandukpur 2 Budhabare 9814072709 26 Sukbir Rai Sandukpur 2 Mewa Pidale 9742655086 Kamal Prasad Sandukpur 2 Budhabare 9814011196 27 Gurung 28 Deu prakash Rai Sandukpur 2 Mewa lumchowk 9817935491 29 Dilliram Gurung Sandukpur 2 Budhabare 9863668591 30 Kumar Gurung Sandukpur 2 Budhabare 9828883993 31 Ratnamaya Gurung Sandukpur 2 Budhabare 32 Chandra Maya Rai Sandukpur 2 Khorsanetar 9815989728 33 Shyam Kumar Rai Sandukpur 2 Pidale Mewa 9804983608 34 Sangita Magar Sandukpur 2 Malenge Mewa

172

Semi-Annual Social Monitoring Report (July to December 2020)

35 Saraswata Rai Sandukpur 2 Malenge Mewa 9844626557 36 Pradip Rai Sandukpur 2 Pidale Mewa 9815916509 37 Tek Bdr Rai Sandukpur 2 Pidale Mewa 9808541007 Chandra Maya Sandukpur 2 Budhabare 38 Gurung 39 Patma Maya Gurung Sandukpur 2 Budhabare 9814381309 Total- 39

Male -23 Female- 16

Indegenous People selected for sewing-netting

S.N. Name Address Ward No. Location/Tole Contact No 1 Nismati Rai Sandukpur 2 Gitang shankhegolai 9804946073 2 Binita Rai Sandukpur 2 Todke 9817080145 3 Nandni Rai Sandukpur 2 Todke 9804966326 4 Khadga Gurung Sandukpur 2 Dhadbari rate 9805982332 5 Rita Gurung Sandukpur 2 Lama Gau Budhbare 9815985911 6 Puja Gurung Sandukpur 2 Lama Gau Budhbare 9864658280 7 Saru Rai Gurung Sandukpur 2 Budhbare 9849404060 8 Bhawana Rai Sandukpur 2 Gitang 9815956682 9 Dipa Rai Sandukpur 2 Khorsanetar Mewa 9814038085 10 Sangita Gurung Sandukpur 2 Dhadbari 9823058906 11 Deukumari Rai Sandukpur 2 Dhadbari(Rate Intek) 9815963528 12 Sanjila Gurung Sandukpur 2 Rate Sharpe 9807913311 Sushma Rai Sandukpur 13 2 Mewa Bistare 9813086314 14 Prajila Rai Sandukpur 2 Khorsanetar 9817072038 15 Samikshya rai Sandukpur 2 Pidale Mewa 9815986741 16 Milan Kala Rai Sandukpur 2 Khursanetar Mewa 9815094616 17 Chitra kala Rai Sandukpur 2 Khursanetar Mewa 18 Ranjana Rai Sandukpur 2 Khursanetar Mewa 9825910256 19 Bidhya Rai Sandukpur 2 Bistare Mewa 20 Amrita Rai Sandukpur 2 Bistare Mewa 9825995080 Total- 20 Male -0 Female- 20

Indegenous People selected for Goat farming S.N. Name Address Ward Location/Tole Contact No No. 1 Tubir Rai Sandukpur 2 Todke 9862440960 Sandukpur Gitang 2 Rabindra Rai 2 shankhegolai 9815944507 3 Dipesh Rai Sandukpur 2 Gitang 9824002957 4 Ram Kumar Rai Sandukpur 2 Gitang 9828056570 5 Bipen Rai Sandukpur 2 Gitang 9814941890 Sandukpur Gitang 6 Hai Bahadur Rai 2 shankhegolai 9806051453 7 Diwas Rai Sandukpur 2 Gitang 9814034585 8 Dhan Bdr Rai Sandukpur 2 Todke 9814989229 9 Bunu Gurung Sandukpur 2 Budhbare 9842675664 10 Gita Gurung Sandukpur 2 Budhbare 9817005009

173

Semi-Annual Social Monitoring Report (July to December 2020)

11 Khin Maya Gurung Sandukpur 2 Budhbare 12 Alisha Gurung Sandukpur 2 Budhabare 9824911179 13 Dil Kumar Rai Sandukpur 2 Mewa lumchowk 9824086644 14 Kailash Rai Sandukpur 2 Mewa lumchowk 15 Manmaya Rai Sandukpur 2 Budhabare 9869836529 16 Dhan Raj Magar Sandukpur 2 Mewa Malenge 9842739827 17 Dil Kumari Gurung Sandukpur 2 Budhabare 18 Himal Rai Sandukpur 2 Bistare Mewa 9810375734 19 Khimendra Gurung Sandukpur 2 Budhabare 9862766897 Total- 19 Male -14 Female- 5

Indegenous People selected for Pig farming S.N. Name Address Ward Location/Tole Contact No No. Sandukpur Gitang 1 Purn Maya Rai 2 shankhegolai 9817919953 Men Bahadur Sandukpur 2 Gurung 2 Todke 9828056570 3 Nar Bahadur Rai Sandukpur 2 Todke 9804917206 4 Kamala rai Sandukpur 2 Gitang 9842014776 5 Birat Kumar Rai Sandukpur 2 Gitang 9815988004 6 Ramila Rai Sandukpur 2 Khorsanetar Mewa 9824004311 7 Hark Bahadur Rai Sandukpur 2 Niwa Basti 8 Sumni Maya Rai Sandukpur 2 Niwa Basti 9824036908 9 Nirmala Rai Sandukpur 2 Budhabare 10 Bishnu Kumari Rai Sandukpur 2 Khorsanetar 9824980588 11 Sujata Rai Sandukpur 2 Khursanetar Mewa 9816094798 12 Fulmaya Rai Sandukpur 2 Khursanetar Mewa 9816918624 13 Bhim Rai Sandukpur 2 Niwa Basti 9823428688 14 Sashi Rai Sandukpur 2 Bistare 9810107001 Total- 14

Male -6

Female- 8

Indegenous People selected for Kiwi farming S.N. Name ADDRESS Ward Location/Tole Contact No No. 1 Sharmila Gurung Sandukpur 2 Sangratar rate 9818815245 2 Nar Maya Gurung Sandukpur 2 Budhbare 9815991985 Sandukpur Khorsanetar 3 Mani Raj Rai 2 Mewa 4 Kumari Gurung Sandukpur 2 Budhabare 9862770207 Amar Bahadur Sandukpur 2 Budhabare 9862622514 5 Gurung 6 Sommaya Rai Sandukpur 2 Budhabare 7 Sapana Rai Sandukpur 2 Budhabare 8 Chet Bdr Magar Sandukpur 2 Mewa Malenge 9869383787 Total- 8

Male -3

Female- 5

174

Semi-Annual Social Monitoring Report (July to December 2020)

Grand Total -100 Male - 44 Female - 56

175

Semi-Annual Social Monitoring Report (July to December 2020)

Annex-6: Third Party Verification from Secondary School of Gurbhakot Municipality

176

Semi-Annual Social Monitoring Report (July to December 2020)

Third Party Verification from Secondary School of Gurbhakot Municipality

177

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation of Third Party Verification

Shree Nepal Rastriya Madhyamik Bidyalaya, Badakholi Gurbhakot Municipality -6, Surkhet Estd.2030 Date 2077-07-05

To, Department of Water Supply and Sewerage, Urban Water Supply and Sanitation Sector Project, Project Management Office, Pani Pokhari, Kathmandu

Subject: Regarding the Recommendation

As per the above mentioned subject, Mr. Bhim Raj Gharti Magar, 65 years old, son of Rup Singh Gharti, grandson of Mampati Gharti resident of Gurbhakot Municipality, Ward no 6 was using public land/Gurbhakot Municipality a total area of 7-0-0-0 (Seven Ropanis, that is, 3561.0 square meter) land within the Municipality. Out of this total land area, Bhim Raj Gharti had provided consent to use 440 sq m. for Subhaghat Water Users and Sanitation Committee for construction of physical structures including road tracks, tanks and generator house under Shubhaghat Urban Water Supply and Sanitation Sector Project. Although he was entitled to receive NPR 49,789.00 (In words forty nine thousand seven hundred eighty nine rupees only) from Subaghat UWSSSP as compensation to loss of agriculture products, loss of permanent income and livelihood from the land. In consultation with his family members, he is not willing to receive the compensation amount at the present and not claim such amount in future too.Therefore it was recommended that it is his pure intension, in consultation with his family, to voluntarly contribute land that was being used by him to Subhaghat UWSSSP as consented earlier.This is in line with whatever the consents and decisions were made earlier and will not subject to claim compensation in future.

Dhal Bahadur (Stamped) Principal

178

Semi-Annual Social Monitoring Report (July to December 2020)

Annex-7: Grievance resolution of Siddhanath – Baijanath consent letter from ward no 10 of Bhimdatta municipality. Grievances resolved and letter from Ward office

179

Semi-Annual Social Monitoring Report (July to December 2020)

English Translation

Bhimdatta Municipality 10 no. ward office Jimuwa Sudoorpachhim Province Contact no: 9848812345 Letter no.2077/78 Outgoing letter no.1879 Date: 2077.11.07 (23 Feb 2021)

Subject: Permission to perform work Regarding the above subject matter, the dispute on pipeline work between Shree Siddhanath– Baijanath Drinking Water supply and sanitation Project which is under construction in ward no 6,8 and 10 of Bhimdatta Municipality and Tilkeni- Mataina Drinking Water Supply project, operation in the same ward has been mutually resolved through discussion among both project and beneficiaries, therefore permission is given to perform the pipeline work in their respective surveyed area under jurisdiction of the project.

Ward Chairman

180