Public Health Engineering Department Tender Document for Jawai Project Pkg-V and Cluster -III CHIEF ENGINEER, PROJECT, Including 10 Years O&M

CHAPTER-1 PROJECT IN BRIEF 1.1 BACK GROUND The Jawai- Hemawas -Jodhpur Canal conveyance System was in use up to the year 1998 to meet drinking water needs of Jodhpur city, Pali town, five other towns of and 372 villages of Pali and . This system was discontinued for Jodhpur city when RGLC water reached in Kaylana impounding reservoir of Jodhpur City in the month August 1998. The 228 villages & 6 towns of Pali district are covered through Jawai Canal System up to Rohat as source from the year 1999. The total average annual losses in open canal were of the tune of approx. 980 mcft as against net water demand of 1204 mcft in the year 2005-06. On an average, nearly 50% to 60% water quantity drawn from was being lost due to seepage, pilferage and other reasons. Jawai Pipeline Project was framed with the objective to conserve water to enable additional coverage with the water so saved. The villages/towns of Pali district, which are facing acute potable water shortage due to existing ground water source having gone dry or deterioration in quality of water available, are proposed to be covered through this project. Total 333 no. additional villages and 3 no. additional towns of Pali district have been identified for coverage through this project. The A&F sanction of Jawai Pipeline Project was issued by 164th PPC meeting held on dated 25.6.2005 for Rs. 354.73 Crores. Third revised A&F of Rs. 634.79 Crores was issued in 178th PPC meeting held on dated 11.10.2007.The project was divided in five packages to give flexibility to suit cash flow requirements & ease of implementation, as per approval issued in 409th TC meeting dated 5.10.2005. Each package was arranged in such a way that its completion may derive benefits of the investment. Package-wise brief status of Jawai Pipeline project is as follows: Work of Package-1: It is related to work of dead storage pumping from Jawai Dam . It may not be required as dead storage of Jawai Dam has been reduced to about 1/3rd capacity for which present temporary pumping arrangements would be adequate. Work of Package-2: It is related to Transmission Main works from Jawai Dam to Mandli-Pali. Pipeline from Jawai to Pali of size 2000mm to 1100mm MS/GRP in total length of 88Km has been completed and is in use .The pipe line is working as gravity main. Work of Package-3: It is related to Water Supply Distribution Improvement in Pali City and is complete with construction of two OHSR, about 52 Km pipeline and upgradation of three pumphouse in Pali City and is in use. Work of Package-4: It is related to work of pipeline from Pali to & Rohat and Khod to Kherwa.The work related to Pali-Rohat pipeline ± 37.3 Km, 350/300 mm dia GRP/MS completed and is in use. Pipeline from Mandli (Pali) to Sojat, -45 Km , 800/750/350 mm DI K-7 is completed. Remaining work of package i.e. pipe line from Khod to Kherwa is taken up along with cluster project-II whose tender are under process. Work of Package-5: It is related to Pipeline from Sojat to Raipur- Bar--Anandpur Kallu- and is part of this contract.

01- PROJECT IN BRIEF updated Vol-II 1

Public Health Engineering Department Tender Document for Jawai Project Pkg-V and Cluster -III CHIEF ENGINEER, PROJECT, JODHPUR Including 10 Years O&M

1.2. THE PROPOSED PROJECT AREA :

As briefed above the Jawai Pipeline Project is mainly to convey water through close conduit to benefit committed 6 towns and 228 villages as well as additional beneficiaries 4 towns (3 towns of Pali and 1 of ) and 333 villages by way of saving/eliminating canal losses. The additional beneficiaries 333 villages and 3 towns of Pali districts are to be benefited by means of framing cluster packages from various outlets of transmission main. Brief of additional beneficiaries i.e. 333 villages and 3 towns of Pali district is being depicted below.

Cluster Trunk Main No. of Villages/Towns Remarks Project Segment

I Jawai to Sojat 111 Villages & 1 Sanctioned and work is under execution Town since 1st September 2012. II Khod to 82 Villages & 1 Town Sanctioned and work is to be executed for Kherwa and 26 existing which tender already invited. covered villages

III Sojat to Bar 133 Villages & 1 Sanctioned and shall be executed along with Jaitaran-A.Kallu Town execution of Package V in this contract.

Administrative & Financial Sanction for Jawai Pipeline project Package-V is already available as mentioned above. The Technical Sanction of this Package has been accorded in 587th TC dt. 12.08.2013 for estimated cost Rs. 112.86 Cr. The Administrative & Financial Sanction to Jawai Cluster Project-III for benefitting 133 villages and 1 town Jaitaran of Pali district, comprising work with offtake at SOJAT, 30 MLD WTP and pumping station at Sojat, Chandawal, Haripur, Kalab Kallan, Near Bagari, Bar, Sabalpura, Nimaj, Jaitaran, Ap.Kallu, and Balupura along with rising and distribution mains, reservoirs etc. was issued in 190th PPC held on dated 30.05.2013 for Rs. 214.50 Crores. Technical Sanction was accorded to this project by Technical committee of RWSSMB in its 587st meeting held on dated 12.08.2013 for estimated cost Rs.163.07 Cr. As against norms of 70 LPCD laid in the guideline of GoI, the State has decided to supply 55 LPCD water from surface source and rest will be continued through existing ground water based system. So, complete new infrastructure is to be created at Sojat H/W to the benefiting 133 villages and Town Jaitaran. For this purpose 133 villages and one town have been grouped into clusters. Each cluster will have its independent overhead service reservoir (OHSR) from where distribution pipelines are to be laid up to villages of clusters up to the Village Transfer Chamber (VTC) to be developed at each of village to facilitate drawl and metering of water supply. Subsequent management and distribution would rest with the Village Water and Sanitation Committee (VWSC)/Pani Samiti. The scope includes construction of all related works of pumping and transmission system including :DWHU7UHDWPHQW3ODQWV&:5¶V Pumping Stations, Service Reservoirs, Rising and Distribution network up to Village Transfer Chambers, 363¶VZLWK&:7¶VHWFfor the respective water demand of 133 villages & one urban town Jaitaran up to design year 2044. The list of villages now proposed for coverage through Package-V in Cluster Project-III, are tabulated below. The villages/ schemes have been grouped from the point of view of minimum travel of water in pipeline and making optimum use of present facilities available in rural water supply schemes.

01- PROJECT IN BRIEF updated Vol-II 2

Public Health Engineering Department Tender Document for Jawai Project Pkg-V and Cluster -III CHIEF ENGINEER, PROJECT, JODHPUR Including 10 Years O&M

Abstract of Offtake wise Villages/Towns to be covered in water supply network is as follow:

TABLE NO. 1.1

DESIGN POPULATION DESIGN DEMAND NAME OF OFFTAKE NO. OF VILLAGES/ TOWNS S No. (NO. OF SOULS) KLD SECTION TO BE BENEFIITED YR. 2044 1 Juntha(Raipur) 10 Village 31295 2059

2 Bar 32 Village 94585 6222

3 Nimaj 21 Village 74815 4921

4 Jaitaran 34 Village and One town 78699 5177

5 A.P.Kallu 36 Villages 106476 7004

Jaitaran Town 38866 4648

TOTAL 133 Village and 1 Town 424736 30031

01- PROJECT IN BRIEF updated Vol-II 3

Public Health Engineering Department Tender Document for Jawai Project Pkg-V and Cluster -III CHIEF ENGINEER, PROJECT, JODHPUR Including 10 Years O&M

TABLE NO. 1.2

Village-wise Population and Demand

Popu. Off Take Code Popu. Popu. Popu. Demand Demand Demand Demand Name of Village Tehsil 2001 Point No. 2013 2029 2044 KLD(2001) KLD(2013) KLD(2029) KLD(2044) Census

1 2 3 4 5 6 7 8 9 10 11 12

Juntha 1 Kotkirana Raipur 2402200 2629 2962 3473 4031 172.9 194.8 228.4 265.2 (Raipur) 2 Seerma -- do -- 2402100 1449 1633 1914 2222 95.3 107.4 125.9 146.1 3 Kalab Kalan -- do -- 2401900 2318 2612 3062 3554 152.5 171.8 201.4 233.8 4 Kalab Khurd -- do -- 2402600 1538 1733 2032 2358 101.2 114.0 133.6 155.1 5 Kalaliya -- do -- 2402400 3109 3503 4107 4767 204.5 230.4 270.1 313.6 6 Bagri -- do -- 2402300 2627 2960 3470 4028 172.8 194.7 228.3 265.0 7 -- do -- 2401800 1507 1698 1991 2311 99.1 111.7 130.9 152.0 8 Khodiya Sojat 2422000 2046 2305 2703 3137 134.6 151.6 177.8 206.4 9 Raira Kallan & Khurd -- do -- 2419800 2731 3077 3607 4187 179.6 202.4 237.3 275.4 10 Singpura -- do -- 2419700 457 515 604 701 30.1 33.9 39.7 46.1 Bar 11 Bar Raipur 2404100 7239 8156 9562 11099 476.2 536.5 629.0 730.1 12 Kirantiya Kallan -- do -- 2404500 2459 2770 3248 3770 161.8 182.2 213.7 248.0 13 Dholidher -- do -- 2404200 757 853 1000 1161 49.8 56.1 65.8 76.3 14 Birathiya Khurd -- do -- 2406800 3395 3825 4484 5205 223.3 251.6 295.0 342.4 15 Chainpura -- do -- 2406100 523 589 691 802 34.4 38.8 45.4 52.7 16 Bootiwas -- do -- 2405500 2419 2725 3195 3709 159.1 179.3 210.2 244.0 17 Haziwas -- do -- 2404800 1727 1946 2281 2648 113.6 128.0 150.1 174.2 18 Mesiya -- do -- 2405300 1663 1874 2197 2550 109.4 123.2 144.5 167.7 19 Dhoolkot -- do -- 2404900 1206 1359 1593 1849 79.3 89.4 104.8 121.6

01- PROJECT IN BRIEF updated Vol-II 4

Public Health Engineering Department Tender Document for Jawai Project Pkg-V and Cluster -III CHIEF ENGINEER, PROJECT, JODHPUR Including 10 Years O&M

20 Jala ki Chowki Raipur 2407100 860 969 1136 1319 56.6 63.7 74.7 86.7 21 Kaya Bheela -- do -- 2404000 1294 1458 1709 1984 85.1 95.9 112.4 130.5 22 Kanuja -- do -- 2403600 3487 3929 4606 5346 229.4 258.4 303.0 351.7 23 Sendra Raipur 2407200 2328 2623 3075 3569 153.1 172.5 202.3 234.8 24 Amarpura -- do -- 2408100 650 732 859 997 42.8 48.2 56.5 65.6 25 Chittar -- do -- 2406500 3656 4119 4829 5606 240.5 271.0 317.7 368.7 26 Chang -- do -- 2408500 4038 4550 5334 6191 265.6 299.3 350.9 407.3 27 Kanecha Udawatan -- do -- 2406400 299 337 395 458 19.7 22.2 26.0 30.2 28 Relra -- do -- 2406200 1415 1594 1869 2170 93.1 104.9 122.9 142.7 29 Nanana -- do -- 2405900 3088 3479 4079 4735 203.1 228.9 268.3 311.4 30 Sodpura -- do -- 2405800 1545 1741 2041 2369 101.6 114.5 134.2 155.8 31 Pratapgarh -- do -- 2410000 1636 1843 2161 2508 107.6 121.2 142.1 165.0 32 Naharpura -- do -- 2409900 2050 2310 2708 3143 134.8 151.9 178.1 206.8 33 Sumel -- do -- 2410300 2990 3369 3949 4584 196.7 221.6 259.8 301.6 34 Kesarpura Raipur 2406900 980 1104 1294 1503 64.5 72.6 85.1 98.8 35 Sodpura -- do -- 2410100 1165 1313 1539 1786 76.6 86.3 101.2 117.5 36 Ravaniya -- do -- 2410200 2062 2323 2724 3162 135.6 152.8 179.2 208.0 37 Ratariya -- do -- 2409100 2526 2846 3337 3873 166.2 187.2 219.5 254.8 38 Ramgarh Sodotan -- do -- 2407600 1467 1653 1938 2249 96.5 108.7 127.5 148.0 39 Manpura -- do -- 2407900 813 916 1074 1247 53.5 60.3 70.6 82.0 40 Kurantiya -- do -- 2407400 275 310 363 422 18.1 20.4 23.9 27.7 41 Selpura -- do -- 2408900 663 747 876 1017 43.6 49.1 57.6 66.9 42 Badipole -- do -- 2408400 1014 1142 1339 1555 66.7 75.2 88.1 102.3 Jaitaran 43 Ber Kallan Jaitaran 2392900 3029 3413 4001 4644 199.2 224.5 263.2 305.5 (TM) 44 Prathvipura -- do -- 2393000 1160 1307 1532 1779 76.3 86.0 100.8 117.0 45 Rajadand -- do -- 2393400 1316 1483 1738 2018 86.6 97.5 114.3 132.7 46 Lakhasni -- do -- 2393200 155 175 205 238 10.2 11.5 13.5 15.6

01- PROJECT IN BRIEF updated Vol-II 5

Public Health Engineering Department Tender Document for Jawai Project Pkg-V and Cluster -III CHIEF ENGINEER, PROJECT, JODHPUR Including 10 Years O&M

47 Jhajhanwas Jaitaran 2393300 1352 1523 1786 2073 88.9 100.2 117.5 136.4 48 Khati Khera -- do -- 2392400 89 100 118 136 5.9 6.6 7.7 9.0 49 Raniwal -- do -- 2392600 1471 1657 1943 2255 96.8 109.0 127.8 148.4 50 Garniya -- do -- 2392500 3013 3395 3980 4620 198.2 223.3 261.8 303.9 TM 51 Hunawas Kallan -- do -- 2394100 744 838 983 1141 48.9 55.1 64.6 75.0 52 Hunawas Khurd -- do -- 2394200 539 607 712 826 35.5 39.9 46.8 54.4 53 Jodhawas -- do -- 2394000 279 314 369 428 18.4 20.7 24.2 28.1 54 Lototi -- do -- 2390800 3562 4013 4705 5461 234.3 264.0 309.5 359.3 55 Kishan Nagar -- do -- 2392800 804 906 1062 1233 52.9 59.6 69.9 81.1 56 Bhakarasni -- do -- 2393100 41 46 54 63 2.7 3.0 3.6 4.1 57 Ramawas Kallan -- do -- 2390900 1080 1217 1427 1656 71.0 80.0 93.8 108.9 58 Ramawas Khurd -- do -- 2391000 1120 1262 1479 1717 73.7 83.0 97.3 113.0 59 Karoliya -- do -- 2392200 643 724 849 986 42.3 47.7 55.9 64.9 60 Patus -- do -- 2392000 420 473 555 644 27.6 31.1 36.5 42.4 61 Talkiya -- do -- 2391900 1184 1334 1564 1815 77.9 87.7 102.9 119.4 62 Ghorawar -- do -- 2391400 1807 2036 2387 2771 118.9 133.9 157.0 182.2 63 Pepliya Khurd -- do -- 2391800 1783 2009 2355 2734 117.3 132.1 154.9 179.8 64 Phoolmal -- do -- 2395100 1549 1745 2046 2375 101.9 114.8 134.6 156.2 65 Khera Maharajpura -- do -- 2398900 804 906 1062 1233 52.9 59.6 69.9 81.1 66 Beekarlai -- do -- 2391100 1349 1520 1782 2068 88.7 100.0 117.2 136.1 67 Kanecha Ranawatan -- do -- 2390400 1602 1805 2116 2456 105.4 118.7 139.2 161.6 68 Leelariya -- do -- 2390000 1729 1948 2284 2651 113.7 128.1 150.2 174.4 69 Malpuriya -- do -- 2391200 781 880 1032 1197 51.4 57.9 67.9 78.8 70 Balunda -- do -- 2390200 7761 8744 10251 11900 510.5 575.2 674.3 782.8 71 Kanawas -- do -- 2390300 632 712 835 969 41.6 46.8 54.9 63.7 TM 72 Banjakuri -- do -- 2391300 2692 3033 3556 4128 177.1 199.5 233.9 271.5 73 Nimbol -- do -- 2390600 4654 5244 6147 7136 306.1 344.9 404.4 469.4

01- PROJECT IN BRIEF updated Vol-II 6

Public Health Engineering Department Tender Document for Jawai Project Pkg-V and Cluster -III CHIEF ENGINEER, PROJECT, JODHPUR Including 10 Years O&M

74 Sinla Jaitaran 2388700 1469 1655 1940 2252 96.6 108.9 127.6 148.2 75 Bogasni -- do -- 2390700 323 364 427 495 21.2 23.9 28.1 32.6 76 Doongar Nagar -- do -- 2388800 392 442 518 601 25.8 29.1 34.1 39.5 Nimaj 77 Samokhi -- do -- 2399000 947 1067 1251 1452 62.3 70.2 82.3 95.5 78 Mahrai -- do -- 3992000 1973 2223 2606 3025 129.8 146.2 171.4 199.0 79 Birampuri -- do -- 2399100 568 640 750 871 37.4 42.1 49.4 57.3 80 Asarlai -- do -- 2398800 3631 4091 4796 5567 238.8 269.1 315.5 366.2 81 Lasni -- do -- 2395200 991 1117 1309 1519 65.2 73.4 86.1 99.9 82 Mundawa -- do -- 2391700 1016 1145 1342 1558 66.8 75.3 88.3 102.5 83 Khinwari -- do -- 2395000 1728 1947 2282 2649 113.7 128.1 150.1 174.3 84 Dagla -- do -- 2399300 750 845 991 1150 49.3 55.6 65.2 75.6 TM 85 Agewa -- do -- 2393800 3354 3779 4430 5143 220.6 248.6 291.4 338.3 TM 86 Chawadiya -- do -- 2393700 2654 2990 3506 4069 174.6 196.7 230.6 267.7 TM 87 Sangawas -- do -- 2394800 1910 2152 2523 2929 125.6 141.6 166.0 192.6 TM 88 Deoriya -- do -- 2393900 3585 4039 4735 5497 235.8 265.7 311.5 361.6 89 Janasni -- do -- 2394400 255 287 337 391 16.8 18.9 22.2 25.7 90 Khera Ramgarh -- do -- 2394600 694 782 917 1064 45.7 51.4 60.3 70.0 91 Nimbara Khurd -- do -- 2398700 665 749 878 1020 43.7 49.3 57.8 67.1 92 Toonkra -- do -- 2398500 1458 1643 1926 2235 95.9 108.1 126.7 147.0 93 Vijaigarh -- do -- 2398600 558 629 737 856 36.7 41.4 48.5 56.3 94 Jhyhenda -- do -- 2394300 1786 2012 2359 2738 117.5 132.4 155.2 180.1 95 Bhakarwas -- do -- 2392100 1134 1278 1498 1739 74.6 84.0 98.5 114.4 96 Patwa -- do -- 2393500 3806 4288 5027 5836 250.4 282.1 330.7 383.9 TM 97 Nimaj -- do -- 15309 17248 20221 23473 1007.0 1134.6 1330.2 1544.0 Anandpur 98 A.P.Kallu -- do -- 2390100 8334 9390 11008 12778 548.2 617.7 724.1 840.5 Kallu 99 Kanwaliya Kallan -- do -- 2389800 593 668 783 909 39.0 43.9 51.5 59.8 100 Kanwaliya Khurd Jaitaran 2389900 1574 1773 2079 2413 103.5 116.7 136.8 158.7

01- PROJECT IN BRIEF updated Vol-II 7

Public Health Engineering Department Tender Document for Jawai Project Pkg-V and Cluster -III CHIEF ENGINEER, PROJECT, JODHPUR Including 10 Years O&M

101 Leelariya -- do -- 2390000 1729 1948 2284 2651 113.7 128.1 150.2 174.4 102 Bassi -- do -- 2395600 1635 1842 2160 2507 107.6 121.2 142.1 164.9 103 Kharchiya -- do -- 2389600 1080 1217 1427 1656 71.0 80.0 93.8 108.9 104 Bankas -- do -- 2389500 473 533 625 725 31.1 35.1 41.1 47.7 105 Lambiya -- do -- 2395800 6823 7687 9012 10461 448.8 505.7 592.8 688.1 106 Gangliya -- do -- 2395900 100 113 132 153 6.6 7.4 8.7 10.1 107 Digarna -- do -- 2388600 2865 3228 3784 4393 188.5 212.3 248.9 289.0 108 Akodiya -- do -- 2389300 400 451 528 613 26.3 29.6 34.8 40.3 109 Falka -- do -- 2389000 3137 3534 4144 4810 206.4 232.5 272.6 316.4 110 Peepra -- do -- 2399100 649 731 857 995 42.7 48.1 56.4 65.5 111 Teebri -- do -- 2389200 476 536 629 730 31.3 35.3 41.4 48.0 112 Teegra -- do -- 2389400 182 205 240 279 12.0 13.5 15.8 18.4 113 Bhoombliya -- do -- 2396200 2458 2769 3247 3769 161.7 182.2 213.6 247.9 114 Odawas -- do -- 2396400 544 613 719 834 35.8 40.3 47.3 54.9 115 Likhmaniya -- do -- 2396000 353 398 466 541 23.2 26.2 30.7 35.6 116 Dhaneriya -- do -- 2396900 2394 2697 3162 3671 157.5 177.4 208.0 241.5 117 Kekindra -- do -- 2396100 2203 2482 2910 3378 144.9 163.3 191.4 222.2 118 Balupura -- do -- 2396600 794 895 1049 1217 52.2 58.8 69.0 80.1 119 Amarpura -- do -- 2396500 2031 2288 2683 3114 133.6 150.5 176.5 204.8 120 Rabariyawas -- do -- 2395400 4369 4922 5771 6699 287.4 323.8 379.6 440.6 121 Kathmore -- do -- 2396800 852 960 1125 1306 56.0 63.1 74.0 85.9 122 Bhildeva -- do -- 2398000 567 639 749 869 37.3 42.0 49.3 57.2 123 Rampura -- do -- 2396300 660 744 872 1012 43.4 48.9 57.3 66.6 124 Balara -- do -- 2395300 5133 5783 6780 7870 337.6 380.4 446.0 517.7 125 Pratappura -- do -- 2395700 726 818 959 1113 47.8 53.8 63.1 73.2 126 Gyas -- do -- 2395500 1101 1240 1454 1688 72.4 81.6 95.7 111.0 127 Dayalpura -- do -- 2396700 797 898 1053 1222 52.4 59.1 69.2 80.4 Manpura 128 -- 2397000 1037 1168 1370 1590 68.2 76.9 90.1 104.6 Baktawarpura

01- PROJECT IN BRIEF updated Vol-II 8

Public Health Engineering Department Tender Document for Jawai Project Pkg-V and Cluster -III CHIEF ENGINEER, PROJECT, JODHPUR Including 10 Years O&M

129 Ras Jaitaran 2398200 8419 9485 11121 12908 553.8 624.0 731.5 849.1 130 Beemgarh -- do -- 2398400 2607 2937 3444 3997 171.5 193.2 226.5 262.9 131 Khera Nanipura -- do -- 2398000 23 26 30 35 1.5 1.7 2.0 2.3 132 Paliyawas -- do -- 2398100 1263 1423 1668 1936 83.1 93.6 109.7 127.4 133 Roopnagar -- do -- 2397800 1087 1225 1436 1667 71.5 80.6 94.4 109.6 TOTAL Rural 251668 283548 332424 385870 16554.7 18651.8 21866.8 25382.5 TM 1 Jaitaran -- do -- 19328 23488 30461 38866 2311.6 2809.2 3643.1 4648.4 TOTAL Urban 19328 23488.4 30460.8 38866 2311.6 2809.2 3643.1 4648.4 Grand Total 270996 307037.55 362884.5 424736 18866 21461 25510 30031

Abstract of Offtake-wise Population and Demand Popu. Code Popu. Popu. Popu. Demand Demand Demand Demand S.N. Offtake Point Tehsil 2001 No. 2013 2029 2044 KLD(2001) KLD(2013) KLD(2029) KLD(2044) Census 1 Juntha(Raipur) Offtake Raipur - 20411 22997 26961 31295 1343 1513 1773 2059 2 Bar Offtake Raipur - 61689 69503 81484 94585 4058 4572 5360 6222 3 Jaitaran Offtake Jaitaran - 51328 57830 67798 78699 3376 3804 4460 5177 4 Nimaj Offtake Jaitaran - 48795 54976 64452 74815 3210 3616 4240 4921 5 A.P.Kallu Offtake Jaitaran - 69445 78242 91729 106476 4568 5147 6034 7004 Total 251668 283548 332424 385870 16555 18652 21867 25383 Jaitaran Town Jaitaran - 19328 23488 30461 38866 2312 2809 3643 4648 G.Total 270996 307037 362885 424736 18866 21461 25510 30031

01- PROJECT IN BRIEF updated Vol-II 9

Public Health Engineering Department Tender Document for Jawai Project Pkg-V and Cluster -III CHIEF ENGINEER, PROJECT, JODHPUR Including 10 Years O&M

1.3 SALIENT FEATURES OF PROPOSED CONTRACT The boundary limits under this contract starts from RGFP at Sojat H/W from which filter water will be pumped to Chandawal IPS and from Chandawal IPS to five offtake viz Jhuta (Raipur), Bar, Nimaj, Jaitaran, and A.P.Kallu. From these offtake water will be further pumped to cluster of 133 villages through ten IPS viz at Haripur, Kalab Kallan, Near Bagari, Bar, Sabalpura, Nimaj, Jaitaran, A.P.Kallu, Lambiya, Balupura. The scope includes construction of all related works of transmission main & pumping (including WTP, CWR etc.) up to Cluster ESRs/GSRs construction of Cluster ESRs/GSRs, distribution pipe network up to villages and development of village transfer chamber as described in subsequent para with 10 years O&M of executed works (scheme) after completion of one year of defect liability period, sufficient to carry designed water flow of year 2044 through five offtakes to 133 villages and one town during its operation, and other works or any other works necessary to achieve objective of flow of referred quantity of water in safe, effective and reliable manner and to complete the system as per good and sound acceptable engineering practices. Details section wise Clusters and benefiting 133 villages/ one town along with their design demands are produced in Table 1.2, above besides giving brief of salient features in foregoing para. The schematic diagram of network is also attached to supplement understanding the proposed system including tentative lengths and sizes of transmission and distribution mains. The salient features of Jawai Pipeline Project Package-V and Jawai Cluster Project III are as under: TABLE NO. 1.3 S. Particulars Salient features of proposed system N. 1. Survey, Geo- 1. Survey, investigation and designs etc. as per tender provisions Technical investigations & Designs 2. Sojat H/W 1. Inlet arrangement for taking raw water from 750mm dia, DI-K7 Jawai-Pali- Sojat Trunk Main in proposed RGFP at Sojat H/W. 2. Construction of RGFP of capacity 1500 KLH. 3. Construction of Circular RCC CWR of capacity 3000KL including sump. 4. Construction of pump house for clear water HSC pumping sets (2 working + 2 stand bye) with allied electrical; mechanical and instrumentation and data / voice communication system. 5. P&L and jointing of 700mm dia DI K7 about 23500 meter lengthTrunk main up to CWR at IPS Chandawal. 6. Construction of J-2 type quarter 3. Chandawal 1. Inlet arrangement for taking clear water from 700mm dia,DI-K7 Sojat Trunk H/W Main in proposed CWR at Chandawal . 2. Construction of Circular RCC CWR of capacity 3000KL including provision of sump. 3. Construction of pump house for clear water HSC pumping sets (2 working + 2 stand bye) with allied electrical; mechanical and instrumentation and data / voice communication system for both A.P.Kallu and Bar Section . 4. P&L and jointing of 400mm dia DI K9/K7 about 24000 meter and 450mm dia 5. DI k7 about 4800mm length rising main(For Chandawal-Jutha-Bar section) 6. P&L and jointing of 700mm dia DI K7 about 14250 meter,600mm dia DI K7 about 12500 meter,400mm dia BWSC about 21500mm and 300mm dia BWSC about 8700 meter length rising main(For Chandawal-Jaitaran-Nimaj- A.P.Kallu section) 7. Construction of J-2 type quarter

01- PROJECT IN BRIEF updated Vol-II 10

Public Health Engineering Department Tender Document for Jawai Project Pkg-V and Cluster -III CHIEF ENGINEER, PROJECT, JODHPUR Including 10 Years O&M

S. Particulars Salient features of proposed system N. Rising Pipe Sl. No. Size & class of Pipes Length in Mtr. line work (Package-V) 1 300 mm BWSC 8650 2 400 mm BWSC 34200 3 400 mm K-9 9670 4 450 mm K-7 4750 5 600mm K-7 12500 6 700 mm K-7 36620 Total Length 59680

Pipe Sluice valves /BFV with dismantling joints (telescopic type). Appurtenances Scour valve with dismantling joints (telescopic type) Air Valves , and ancillary Valve Chamber for Sluice, Scour and Flow control Valves works (Package-V) High Rise Air Valve Placement arrangements with Air valve pillars/ chambers. Bends, tees etc. with thrust blocks and fixidity blocks etc

4. JUNTHA(RAIPUR) OFFTAKE (i) Haripur 1. Offtake arrangement at Juntha village for taking filter water from 400mm DI IPS,Kalab K-9 Chandawal-Bar Trunk Main through 200mm DI K7 in proposed RCC Kallan IPS and CWR at Haripur H/W. Near Bagari 2. Construction of RCC clear water reservoir 210 KL at Haripur H/W including Nagar IPS sump. 3. Construction of RCC clear water reservoir 125 KL at Kalab Kallan H/W including sump. 4. Construction of RCC clear water reservoir 100 KL at Near Bagari including sump. 5. Construction of pump houses at Haripur,Kalab Kallan and Near Bagari Nagar for housing 6 nos clear water HSC pumping sets (1 working + 1 stand bye) with allied electrical; mechanical and instrumentation and data / voice communication system. 6. Providing pumping manifold with control valves and flow metering etc. 7. Campus development, guard hut, cow catcher and allied works including rejuvition of boundary wall. 8. Construction of J-2 type quarter 9. Repairing of GSR at Kot and Kirana . 10. P&L and jointing of rising main and distribution main from Haripur, Kalab Kalan and Near Bagari Nagar pump house as depicted below.

(ii) Rising Pipe Sl. No. Size & class of Pipes Length in Mtr. line work 1 80 mm K-7 14470 2 100 mm K-7 760 3 125 mm K-7 16760 4 200 mm K-7 10960 5 150 mm K-9 4550 6 200 mm K-9 12180 Total Length 59680

01- PROJECT IN BRIEF updated Vol-II 11

Public Health Engineering Department Tender Document for Jawai Project Pkg-V and Cluster -III CHIEF ENGINEER, PROJECT, JODHPUR Including 10 Years O&M

S. Particulars Salient features of proposed system N. (iii) Distribution Sl. No. Size & class of Pipes Length in Mtr. Pipe line work 1 80 mm DI K-7 26970 2 90 mm uPVC Cl-3 10000 Total 36970

(iv) Intze type S.N. Name of village Capacity and Staging of Over Head Reservoir Reservoirs 1 Kalab Khurd 100 KL Hillock including boundary 2 Kheenwal 100 KL ESR stg.18 mtr. walls as 3 Rayra Khurd 170 KL Hillock required (Live 4 Kalaliya 100 KL stg 18 m capacity with minimum 5 Bagri 150 KL Hillock staging as 6 Seerma 150 KL GLR mentioned) (v) Pipe Sluice valves /BFV with dismantling joints (telescopic type). Appurtenances Scour valve with dismantling joints (telescopic type) Air Valves , and ancillary Valve Chamber for Sluice, Scour and Flow control Valves works High Rise Air Valve Placement arrangements with Air valve pillars/ chambers. Bends, tees etc. with thrust blocks and fixidity blocks, VTC, PSP, CWT etc 5. BAR OFFTAKE i Bar IPS and 1. Construction of Clear Water reservoir at Bar and Sabalpura head works of Sabalpura IPS capacity 630 KL, and 200KL respectively. 2. Construction of pump house at Bar for housing 2 nos clear water HSC pumping sets (1 working + 1 stand bye for sectionBar-Birathiya Kallan); 2 nos clear water HSC pumping sets (1 working + 1 stand bye for section Bar- Butiwas) and QR¶Vclear water HSC pumping sets (2 working + 2 stand bye) for pumping to Sendra section and Sabalpura IPS and at Sabalpura IPS 2 no¶s clear water HSC pumping sets (1 working + 1 stand bye) for pumping to Chang-Rawaniya section with allied electrical; mechanical and instrumentation and data / voice communication system. 3. Providing pumping manifold with control valves and flow metering. 4. Construction of J-2 type quarters at Bar H/W. 5. 'LVPDQWOLQJ RI H[LVWLQJ DEDQGRQHG &:5 SXPS KRXVH QR¶V --2type quarter ,switch room etc. 6. Repairing of Jen office at Bar H/W and GSR at Nanana, Chitar and Chang. 7. Campus development, guard hut, cow catcher and allied works including boundary wall. 8. P&L and jointing of rising main and distribution main from Bar and Sabalpura pump house as depicted below.

01- PROJECT IN BRIEF updated Vol-II 12

Public Health Engineering Department Tender Document for Jawai Project Pkg-V and Cluster -III CHIEF ENGINEER, PROJECT, JODHPUR Including 10 Years O&M

S. Particulars Salient features of proposed system N. ii Rising Sl. No. Size & class of Pipes Length in Mtr. Pipeline work 1 80 mm K-7 6890

100 mm K-7 16810 2 3 150 mm K-7 35450

4 200 mm K-7 35260 5 200 mm K-9 4570 6 300 mm K-9 11680 Total 110660

iii Distribution Sl. No. Size & class of Pipes Length in Mtr. Pipeline work 1 90 mm CL-3 27000 2 110 mm CL-3 3600 3 125 mm CL-3 500 4 80 mm K-7 61610 Total 92710

iv Intze type Over Head S.N. Name of village Capacity and Staging of Reservoir Reservoirs 1 Bar 200 KL stg 18 m including 2 Bar 100 KL(GSR) boundary 3 Birathiya Kallan 170 KL stg 18 m walls as Hajiwas 150KL stg 18 m required (Live 4 capacity with 5 Mesiya 100 KL stg 18 m minimum 6 Bootiwas 130 KL stg 18 m staging as 7 Birathiya Khurd 100 KL(GSR) mentioned) 8 Chainpura 60 KL(GLR) 9 Kaya 65 KL(GLR) 10 Bheela 65 KL(GLR) 11 Sendra 120 KL stg 18 m 12 Kesarpura 100 KL(GSR) 13 Chitar 100 KL(GSR) 14 Amarpura 70 KL(GSR) 15 Chang 110 KL(GSR) 16 Ratadiya 180 KL stg 18m 17 Naharpura 200 KL(GSR) 18 Sumel 160 KL (GSR) 19 Sodpura(Pratapgarh) 60KL(GLR)

v Pipe Sluice valves /BFV with dismantling joints (telescopic type). Appurtenances Scour valve with dismantling joints (telescopic type) Air Valves , and ancillary Valve Chamber for Sluice, Scour and Flow control Valves works High Rise Air Valve Placement arrangements with Air valve pillars/ chambers. Bends, tees etc. with thrust blocks and fixidity blocks, VTC, PSP, CWT etc.

01- PROJECT IN BRIEF updated Vol-II 13

Public Health Engineering Department Tender Document for Jawai Project Pkg-V and Cluster -III CHIEF ENGINEER, PROJECT, JODHPUR Including 10 Years O&M

S. Particulars Salient features of proposed system N. 6. Nimaj Offtake (i) Nimaj IPS 1. Construction of Clear Water reservoir at Nimaj HW of capacity 150 KL. 2. Construction of pump house at Nimaj for housing 2 nos. clear water HSC pumping sets for Morai Tookara section (1 working + 1 stand bye)and 2 nos. clear water HSC pumping sets for Khiwal Aasarlai Section (1 working + 1 stand bye) with allied electrical; mechanical and instrumentation and data / voice communication system. 3. Providing pumping manifold with control valves and flow metering. 4. Construction of J-2 type quarters at Nimaj H/W. 5. Campus development, guard hut, cow catcher and allied works including boundary wall. 6. P/L&J of rising main and distribution main from Nimaj pump house and trunk main as depicted below. (ii) Rising Pipeline work Sl. No. Size & class of Pipes Length in Mtr.

1 100 mm K-7 17824

100 mm K-9 575 2 3 150 mm K-7 21995 4 150 mm K-9 4749

5 200 mm K-9 7294 Total 52437

(iii) Distribution Sl. No. Size & class of Pipes Length in Mtr. Pipeline work 1 90 mm CL-3 36216 2 110 mm CL-3 6323 3 125 mm CL-3 9407 4 140 mm CL-3 3639 5 160 mm CL-3 5301 6 180 mm CL-3 3360 7 200 mm CL-3 1673 Total 65919

(iv) Intze type Over Head S.N. Name of village Capacity and Staging of Reservoir Reservoirs including 1 Nimaj 300 KL stg 18 m boundary 2 Morai 200 KL stg 18 m walls as 3 Tookara 135 KL stg 15 m required (Live Asarlai 300 KL stg 15 m capacity with 4 minimum 5 Khinwari 120 KL stg 18m staging as 6 Sangawas 300 KL stg 20m

mentioned) (v) Pipe Sluice valves /BFV with dismantling joints (telescopic type). Appurtenances Scour valve with dismantling joints (telescopic type) Air Valves , and ancillary Valve Chamber for Sluice, Scour and Flow control Valves works High Rise Air Valve Placement arrangements with Air valve pillars/ chambers. Bends, tees etc. with thrust blocks and fixidity blocks, VTC, PSP, CWT etc.

01- PROJECT IN BRIEF updated Vol-II 14

Public Health Engineering Department Tender Document for Jawai Project Pkg-V and Cluster -III CHIEF ENGINEER, PROJECT, JODHPUR Including 10 Years O&M

S. Particulars Salient features of proposed system N. 7. Jaitaran Offtake (i) Jaitaran IPS 1. Construction of Clear Water reservoir at Jaitaran head works of capacity 400 KL. 2. Construction of pump house at Jaitaran for housing 4 nos clear water HSC pumping sets (2 working + 2 stand bye) with allied electrical; mechanical and instrumentation and data / voice communication system. 3. Providing pumping manifold with control valves and flow metering. 4. Construction of J-2 type quarters at Jaitaran H/W. 5. Dismanteling of old,Store room,Boundry wall etc at Jaitaran H/W 6. Campus development, guard hut, cow catcher and allied works including boundary wall. 7. P/L&J of rising main and distribution main from Jaitaran pump house and trunk main are as depicted below.

(ii) Rising Sl. No. Size & class of Pipes Length in Mtr. Pipeline work 1 100 mm K-7 26530 2 150 mm K-7 33180 3 200 mm K-7 19730

4 250 mm K-7 5070 Total 84510

(iii) Distribution Sl. No. Size & class of Pipes Length in Mtr. Pipeline work 1 90 mm CL-3 66724 2 110 mm CL-3 7428 3 125 mm CL-3 22484 4 140 mm CL-3 12505 5 160 mm CL-3 3326 6 180 mm CL-3 7125 7 200 mm CL-3 988 8 250 mm CL-3 4831 9 300 mm CL-3 788 Total 126199

(iv) Intze type S.N. Name of village Capacity and Staging of Reservoir Over Head Jaitaran 600 KL(2 No's) Reservoirs 1 including 2 Garnia 100 KL stg 20 m boundary 3 Rajdand 150 KL stg 20 m walls as 4 Hunawas Kallan 100 KL stg 20 m required (Live capacity with 5 Ramawas Khurd 110 KL stg 20 m minimum 6 Latoti 100 KL stg 20m staging as 7 Nimbol 400 KL stg 22 m mentioned) 8 Ber Kallan 100 KL stg 18 m 9 Litariya 200 KL stg 22 m 10 Banjakudi 200 KL stg 20 m 11 Phoolmal 180 KL stg 20 m 12 Karoliya 100 KL stg 20 m

01- PROJECT IN BRIEF updated Vol-II 15

Public Health Engineering Department Tender Document for Jawai Project Pkg-V and Cluster -III CHIEF ENGINEER, PROJECT, JODHPUR Including 10 Years O&M

S. Particulars Salient features of proposed system N. (v) Pipe Sluice valves /BFV with dismantling joints (telescopic type). Appurtenances Scour valve with dismantling joints (telescopic type) Air Valves , and ancillary Valve Chamber for Sluice, Scour and Flow control Valves works High Rise Air Valve Placement arrangements with Air valve pillars/ chambers. Bends, tees etc. with thrust blocks and fixidity blocks, VTC, PSP, CWT etc. 8. A.P.Kallu Offtake i A.P.Kallu IPS; 1. Construction of Clear Water reservoir at A.P.Kallu, Lambiya and Balupura Lambiya IPS head works of capacity 700 KL, 175KLand 150KL respectively. & Balupura 2. Construction of pump house at A.P.Kallu for housing 2 nos clear water HSC IPS pumping sets (1 working + 1 stand bye for section A.P.Kallu- Akodiya,Digrana); 2 nos clear water HSC pumping sets (1 working + 1 stand bye for section A.P.Kallu-Rabadiyawas,Balupura IPS) and 2 QR¶V clear water HSC pumping sets (1 working + 1 stand bye) for pumping to Kanwaliya Khurd and Lambiya IPS section and at Lambiya IPS 2 no¶s clear water HSC pumping sets (1 working + 1 stand bye) and at Balupura IPS 2 no¶s clear water HSC pumping sets (1 working + 1 stand bye) with allied electrical; mechanical and instrumentation and data / voice communication system. 3. Providing pumping manifold with control valves and flow metering. 4. Construction of J-2 type quarters at A.P.Kallu H/W. 5. Dismanteling of old pump house and CWR at A.P.Kallu H/W 6. Campus development, guard hut, cow catcher and allied works including boundary wall. 7. P/L &J of rising main and distribution main from A.P. Kallu, Lambiya and Balupura pump house as depicted below. ii Rising Sl. No. Size & class of Pipes Length in Mtr. Pipeline work 1 100 mm K-7 42877 2 150 mm K-7 23232

3 150 mm K-9 13424

4 200 mm K-7 12335 5 200 mm K-9 833 6 250 mm K-7 4129 7 250 mm K-9 11199 Total 108029

iii Distribution Sl. No. Size & class of Pipes Length in Mtr. Pipeline work 1 90 mm CL-3 60307 2 110 mm CL-3 4378 3 125 mm CL-3 14762 4 140 mm CL-3 4023 5 160 mm CL-3 11140 6 180 mm CL-3 1916 7 200 mm CL-3 7196 8 80 mm K-7 18000 9 125 mm K-7 2739 Total 124461

01- PROJECT IN BRIEF updated Vol-II 16

Public Health Engineering Department Tender Document for Jawai Project Pkg-V and Cluster -III CHIEF ENGINEER, PROJECT, JODHPUR Including 10 Years O&M

S. Particulars Salient features of proposed system N. iv Intze type S.N. Name of village Capacity and Staging of Reservoir Over Head Anandpur Kallu 300 KL stg 18 m Reservoirs 1 including 2 Rabariyawas 400 KL stg 22 m boundary 3 Balara 120 KL stg 15 m walls as 4 Akodiya 110 KL stg 22 m required (Live capacity with 5 Digrana 150 KL stg 20 m minimum 6 Kanwaliya Khurd 250 KL stg 20 m staging as 7 Lambiya 100 KL stg 18 m mentioned) 8 Kekindra 120 KL stg 20 m 9 Bhumaliya 100 KL stg 15 m 10 Dhaneriya 220 KL stg 22 m 11 Ras 500 KL stg 22 m 12 Bhimgarh 135 KL stg 15 m 13 Paliyawas 125kL(GLR) 14 Bhildeva 60kL(GLR)

v Pipe Sluice valves /BFV with dismantling joints (telescopic type). Appurtenances Scour valve with dismantling joints (telescopic type) Air Valves , and ancillary Valve Chamber for Sluice, Scour and Flow control Valves works High Rise Air Valve Placement arrangements with Air valve pillars/ chambers. Bends, tees etc. with thrust blocks and fixidity blocks, VTC, PSP, CWT etc. 9 Flow control Size Pk-V Juntha Bar Jaitaran Nimaj A.P.Kallu Total Valves 100mm 1 1 9 1 5 3 20 WHQWDWLYHQR¶V 125 mm 2 2 (Section Wise) 150 mm 2 3 1 3 9 200 mm 2 1 3 2 8 300 mm 2 2

10 Electro Size magnetic Flow meters with Bar ESR VTC Total Total Nimaj Nimaj Juntha Juntha

remote reading Jaitaran A.P.Kallu A.P.Kallu devices GSM V Package supported. 25 mm 22 22 on Rising and 40 mm 45 45 Distribution 50 mm 48 20 68 mains 80 mm 1 1 1 2 17 7 29 100 mm 2 3 1 6 200 mm 2 2 250 mm 2 2

---do---at Head Size Works V Bar Total Total Nimaj Nimaj Juntha Juntha Jaitaran Jaitaran Package Package A.P.Kallu A.P.Kallu 80 mm 1 1 2 100 mm 2 1 3 6 150 mm 2 2 2 1 1 8

01- PROJECT IN BRIEF updated Vol-II 17

Public Health Engineering Department Tender Document for Jawai Project Pkg-V and Cluster -III CHIEF ENGINEER, PROJECT, JODHPUR Including 10 Years O&M

S. Particulars Salient features of proposed system N. 200 mm 1 1 250 mm 3 3 300 mm 1 1 500 mm 3 3

11 Pumping Name of I.P.S./Pumping to Discharge Head(m) Kw No. machinery Oftake Section (Cum/Hr.) (Tentative Sojat Sojat 74 640 190 4 duty Chandawal 80 460 160 4 conditions) (A.P.Kallu section) Chandawal Chandawal 120 180 94 4 (Bar Section) Haripur I.P.S. 82 89 35 2 Juntha (Raipur) Kalab Kallan I.P.S. 110 53 28 2 Chainage 6100 IPS Nr Offtake 104 43 22 2 Bagari IPS Bar 124 74 40 4 (Bar-Sabalpura) IPS Bar 72 75 25 2 Bar (Bar-Birathiya Kallan) Offtake IPS Bar 64 45 15 2 (Bar-Butiwas) IPS Sabalpura 84 83 32 2 Jaitaran Jaitaran 65 80 25 4 Offtake Nimaj IPS (Morai- 95 30 12.5 2 Nimaj Toonkara section) Offtake Nimaj IPS (Kheewal- 78 30 12.5 2 Asarlai Section) A.P. Kallu IPS (Digrana-Akodiya 75 40 12.5 2 Section) A.P. Kallu IPS A.P.Kallu 85 130 50 2 (Balupura Section) Offtake A.P. Kallu IPS 67 100 30 2 (Lambiya Section) IPS Lambiya 85 80 30 2 IPS Balupura 90 60 26.5 2

12 Railway Size of Pipe Line Rly. Remark Section Location crossing (Tentative) Ref. Juntha (Raipur) Nr Haripur 200 mm DI /MS pipe, Sanction Offtake required Bar Offtake Near Jhala Ki 150mm DI /MS pipe Chowki Near Manpura 100mm DI /MS pipe Near Lalpura 200mm DI /MS pipe Near Amarpura 200mm DI /MS pipe

01- PROJECT IN BRIEF updated Vol-II 18

Public Health Engineering Department Tender Document for Jawai Project Pkg-V and Cluster -III CHIEF ENGINEER, PROJECT, JODHPUR Including 10 Years O&M

S. Particulars Salient features of proposed system N.

NOTE: Length and Diameter of encasing pipe is to be decided as per approvals issued by Railways & as per latest guidelines & circular issued by RESEARCH DESIGNS AND STANDARDS ORGANISATION, Ministry of Railways.

13 New electrical Related system for new pumps at all pumping stations. installation 14 Automation Complete automation system with PLC SCADA to monitor and control flow in the system, as defined in scope of work and Chapter 15 IRU³6SHFLILFDWLRQV´ 15 O & M O & M for 10 years after completion of one year defect liability period of constructed system after physical completion; No payment admissible in the year designated for defect liability period.

01- PROJECT IN BRIEF updated Vol-II 19