HURONTARIO LIGHT RAIL TRANSIT

Information as of April 2020

Median Removals on Hurontario between and Matheson Boulevard Beginning Early May 2020

What is the Hurontario Light Rail Transit Project? The Hurontario LRT will be an 18-kilometre, 19-stop light rail service connecting people from the GO station to the Gateway Terminal. The Hurontario LRT will connect with the Port Credit and GO stations, Transitway, MiWay and Züm transit lines.

What work is taking place? To prepare for future construction of the Hurontario LRT, crews will remove existing medians along , between Dundas Street and Matheson Boulevard.

Once medians have been removed, the area will be converted to roadway, reducing the amount of lane reductions required during major construction.

Timing • Work is scheduled to begin in early May 2020 and will be completed approximately in three months’ time. • Work will occur between the hours of 7 a.m. and 7 p.m., Monday to Friday. • Work could be rescheduled and delayed due to weather conditions or any unforeseen circumstances.

What to Expect • Every effort will be made to minimize disruptions. • Access to properties will always be maintained through at least one driveway. • Residents and businesses near the work site can expect to hear noise caused by trucks, excavators and mini loaders.

…2

For information regarding the Hurontario LRT project and construction updates, follow us on Twitter @HurontarioLRT, or contact us at the Metrolinx Community Relations office at 416-202-7500 or email: [email protected].

-2-

Traffic Details • During construction hours, short-term lane reductions will be required on Hurontario Street between Dundas Street and Matheson Boulevard. • A minimum of four lanes will be maintained on Hurontario Street, ensuring both northbound and southbound traffic flows at all times. • Traffic delays are expected.

Transit Details • Due to lane reductions along Hurontario Street, some delays can be expected on MiWay routes 2,17, MiWay express route 103 and Züm route 502.

Pedestrian Details • Please take care when travelling near construction areas. • Watch for additional signs directing pedestrians as detours may be required. • Clear and defined walking paths will be maintained during construction to ensure pedestrian safety.

Metrolinx is building new transit in your communities! Want to stay in the loop? Please sign up to our new regional newsletter at metrolinx.com/peel.

For more information please contact the Community Relations staff for Metrolinx Peel region by email [email protected] or phone 416.202.7500.

Thank you for your patience as we work to build this new project. Please support your local businesses during construction.

Cet avis de travaux de construction est disponible en français sur demande. Si vous êtes intéressé, veuillez envoyer un courriel à [email protected].