QWEST CORPORATION ACCESS SERVICE TARIFF F.C.C. NO. 2 DESCRIPTION AND JUSTIFICATION SPECIAL CONSTRUCTION

Page 1

INTRODUCTION AND DESCRIPTION

This filing is being made by Corporation (Qwest) in its Tariff F.C.C. No. 2, Special Construction to add eight new cases in Section 6 of the tariff.

CASE DETAIL Worldcom-WTL Case No. 57 (Reference No. C16692816)

Description: This special construction case is for the conditioning of copper facilities and the installation of electronics to provide a suitable circuit path for the provisioning of DS1 level service from the customer’s location at 601 East Front St., Davenport, IA, to the Qwest Central Office located at 528 N. Main St., Davenport, IA. A total charge of $7,610.87 is due and payable in a one-time up-front payment.

Page 2

CASE DETAIL Telecommunications, Inc. Case No. 58 (Reference No. C16996013)

Description: This special construction case is for the conditioning of copper facilities and the installation of electronics to provide a suitable circuit path for the provisioning of DS1 level service from the customer’s location at 1516 Old Portland Rd., Van Meter, IA to the Qwest central office located at 909 High St., Des Moines, IA. A total charge of $2,073.11 is due and payable in a one-time up-front payment.

CASE DETAIL Nextel Partners Case No. 59 (Reference No. C17376562)

Description:

This special construction case is for the conditioning of copper facilities and the installation of electronics to provide a suitable circuit path for the provisioning of DS1 level service from the customer’s location at 17270 R. Ave., Dike, IA to the Qwest central office located at 1504 St., Cedar Falls, IA. A total charge of $18,186.53 is due and payable in a one-time up-front payment.

Page 3

CASE DETAIL Worldcom-WTL Case No. 60 (Reference No. C21627558)

Description: This special construction case is for the conditioning of copper facilities and the installation of electronics to provide a suitable circuit path for the provisioning of DS1 level service from the customer’s location at 3854 Buffalo Ridge Rd., Anamosa, IA to the Qwest central office located at 103 N. Davis St., Anamosa, IA. A total charge of $2,437.02 is due and payable in a one-time up-front payment.

CASE DETAIL MWR Telcom, Inc. Case No. 61 (Reference No. C22476668)

Description: This special construction case is for the conditioning of copper facilities and the installation of electronics to provide a suitable circuit path for the provisioning of DS1 level service from the customer’s location at 3882 Main St., Keokuk, IA to the Qwest central office located at 421 N. 4th St., Keokuk, IA. A total charge of $2,343.29 is due and payable in a one-time up-front payment.

Page 4

CASE DETAIL Nextel Partners Case No. 62 (Reference No. C34779377)

Description: This special construction case is for the conditioning of copper facilities and the installation of electronics to provide a suitable circuit path for the provisioning of DS1 level service from the customer’s location at 812 W. 6th St., Monticello, IA to the Qwest central office located at 1800 Blairs Ferry Rd., NE, Cedar Rapids, IA. A total charge of $4,643.60 is due and payable in a one-time up-front payment.

CASE DETAIL AT&T Communications Case No. 63 (Reference No. C35367816)

Description: This special construction case is for the conditioning of copper facilities and the installation of electronics to provide a suitable circuit path for the provisioning of DS1 level service from the customer’s location at 18671 Applewood Rd, Council Bluffs, IA to the Qwest central office located at 118 S. 19th St., Omaha, NE. A total charge of $11,797.87 is due and payable in a one-time up-front payment.

Page 5

CASE DETAIL Worldcom-WTL Case No. 64 (Reference No. C42694868)

Description: This special construction case is for the conditioning of copper facilities and the installation of electronics to provide a suitable circuit path for the provisioning of DS1 level service from the customer’s location at 3707 W. River Dr. Davenport, IA to the Qwest central office located at 528 N. Main St., Davenport, IA. A total charge of $3,453.94 is due and payable in a one-time up-front payment.

Page 6

COST SUPPORT AND WORKPAPERS

Construction Costs

These cases meet the conditions for Special Construction as specified in Qwest’s Special Construction Tariff. The costs are for the engineering and placement of facilities and loadings to recover overhead costs.

The Direct Costs consist of the non-reusable investment associated with these Special Construction Cases. These are costs directly associated with the project such as engineering the job, the equipment, the labor to install the equipment, placement of the fiber or cable, and shipping of the material.

Once these Direct Costs have been identified, an “Overhead Loading for Special Construction” is than calculated. The overhead loading includes the following type of expenses: administrative expenses, product management expenses, sales expenses, common overhead expenses, and business fees.

Workpapers A-1 through A-8 display the direct costs and the overhead loading.

Case Preparation Cost

The case preparation charge, as displayed on Workpapers A-1 through A-8 covers the one-time preparation costs and filing fees associated with these special construction cases. The charge consists of labor to prepare cost documentation; to write the tariff; and to prepare the Description and Justification (D&J), the Transmittal Page 7

Letter and coordinate the filing. These fees are based on average 2002 case preparation times.

After the work functions were identified, the time required for case preparation was calculated (an average of 2 hours per case). The task time identified was then multiplied by the appropriate labor rate (2 X $38.11= $76.22).

The prorated cost of the filing fees was calculated by taking the number of special construction cases filed in 2002 divided by the number of special construction tariff filings to produce and average number of special access cases per filing (4.29). The FCC’s $720 filing fee was then divided by this factor to come up with a prorated filing fee of $168 per special construction case.

The sum of the labor calculations plus the prorated cost of the filing fee produces the case preparation charge.

Workpaper A-1

COST SUPPORT

Customer: Worldcom-WTL Case Number: 57 Reference Number: C16692816

CONSTRUCTION COSTS

Direct Costs $ 5,837.22 Overhead $ 1,529.43

Total $ 7,366.65

CASE PREPARATION CHARGE

Case Preparation $ 76.22 Prorated FCC Filing Fee $ 168.00

Total Case Preparation Charge $ 244.22

Total Charge $ 7,610.87

Workpaper A-2

COST SUPPORT

Customer: Global Crossing Telecommunications, Inc. Case Number: 58 Reference Number: C16996013

CONSTRUCTION COSTS

Direct Costs $ 1,392.23 Overhead $ 436.66

Total $ 1,828.89

CASE PREPARATION CHARGE

Case Preparation $ 76.22 Prorated FCC Filing Fee $ 168.00

Total Case Preparation Charge $ 244.22

Total Charge $ 2,073.11

Workpaper A-3

COST SUPPORT

Customer: Nextel Partners Case Number: 59 Reference Number: C17376562

CONSTRUCTION COSTS

Direct Costs $ 14,896.10 Overhead $ 3,046.21

Total $ 17,942.31

CASE PREPARATION CHARGE

Case Preparation $ 76.22 Prorated FCC Filing Fee $ 168.00

Total Case Preparation Charge $ 244.22

Total Charge $ 18,186.53

Workpaper A-4

COST SUPPORT

Customer: Worldcom-WTL Case Number: 60 Reference Number: C21627558

CONSTRUCTION COSTS

Direct Costs $ 1,696.51 Overhead $ 496.29

Total $ 2,192.80

CASE PREPARATION CHARGE

Case Preparation $ 76.22 Prorated FCC Filing Fee $ 168.00

Total Case Preparation Charge $ 244.22

Total Charge $ 2,437.02

Workpaper A-5

COST SUPPORT

Customer: MWR Telcom, Inc. Case Number: 61 Reference Number: C22476668

CONSTRUCTION COSTS

Direct Costs $ 1,652.09 Overhead $ 446.98

Total $ 2,099.07

CASE PREPARATION CHARGE

Case Preparation $ 76.22 Prorated FCC Filing Fee $ 168.00

Total Case Preparation Charge $ 244.22

Total Charge $ 2,343.29

Workpaper A-6

COST SUPPORT

Customer: Nextel Partners Case Number: 62 Reference Number: C34779377

CONSTRUCTION COSTS

Direct Costs $ 3,243.15 Overhead $ 1,156.23

Total $ 4,399.38

CASE PREPARATION CHARGE

Case Preparation $ 76.22 Prorated FCC Filing Fee $ 168.00

Total Case Preparation Charge $ 244.22

Total Charge $ 4,643.60

Workpaper A-7

COST SUPPORT

Customer: AT&T Communications Case Number: 63 Reference Number: C35367816

CONSTRUCTION COSTS

Direct Costs $ 9,808.20 Overhead $ 1,745.45

Total $ 11,553.65

CASE PREPARATION CHARGE

Case Preparation $ 76.22 Prorated FCC Filing Fee $ 168.00

Total Case Preparation Charge $ 244.22

Total Charge $ 11,797.87

Workpaper A-8

COST SUPPORT

Customer: Worldcom-WTL Case Number: 64 Reference Number: C42694868

CONSTRUCTION COSTS

Direct Costs $ 2,341.20 Overhead $ 868.52

Total $ 3,209.72

CASE PREPARATION CHARGE

Case Preparation $ 76.22 Prorated FCC Filing Fee $ 168.00

Total Case Preparation Charge $ 244.22

Total Charge $ 3,453.94