Environmental Monitoring Report

Annual Report July 2017

Sri Lanka: Southern Road Connectivity Project

Prepared by Road Development Authority for the Government of and the Asian Development Bank

This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Contents

1. INTRODUCTION ...... 6 2. PROJECT IMPLEMENTATION PROGRESS ...... 8 3. CONSTRUCTION PROGRESS ...... 11 5. SUMMARY OF ENVIRONMENTAL MITIGATIONS AND COMPENSATION MEASURES .... 20 6. SUMMARY OF ENVIRONMENTAL MONITORING ...... 32 7. PUBLIC COMPLAINTS...... 37 8. STATUS OF COMPLIANCE TO LOAN AGREEMENT ...... 39 9. CONCLUSION ...... 41

2

ABBREVIATIONS ADB Asian Development Bank AIDS Acquired Immune Deficiency Syndrome CEA Central Environmental Authority CP Contract Package EMAP Environmental Management Action Plan EMOP Environmental Monitoring Plan EMP Environmental Management Plan EO Environmental Officer EPL Environmental protection License ES Environmental Specialist GAP Gender Action Plan GRC Graveness Redress Committee GSMB Geological Survey and Mining Bureau HIV Human Immunodeficiency Virus IEE Initial Environmental Examination IML Industrial Mining Licenses LA Local Authority NHSP National Highway Sector Project PIC Project Implement Consultant PD Project Director PMU Project Management Unit RDA Road development Authority RE Resident Engineer ROW Right-of-way SRCP Southern Road Connectivity Project TL Team Leader

3

CP 01- - Mirihana , and Road

CP 02- Kesbewa - Pokunuwita , and Kiriulapana - Godagama Road

CP 03- Matugama - Southern Expressway Road

Figure 1. Location map of selected road sections to be developed under SRCP

4

EXECUTIVE SUMMARY This report is the 2nd annual report on environmental safeguards compliance of the three (3) subprojects under the Southern Road Connectivity Project (SRCP), Loan No: 3027-SRI funded by Asian Development Bank (ADB). The reporting period is from May 2016 to April 2017. The three sub projects under SRCP are; 1. Ratmalana - Mirihana Road B389, and Moratuwa Piliyandala Road B295. CP 01, and total length is 4.69km 2. Kesbewa - Pokunuwita Road B084, and Kiriulapana - Godagama Road A004. CP 02, and total length is 16.45km 3. Mathugama - Southern Expressway B157. CP 03, and total length is 12.06km 4. CINEC Junction to Ambathale Junction Link road. CP04, Total length 1.83 km

CP 01 project is nearing at its’ completion; while the construction works of CP02 and CP03 project’s had already begun recently towards the latter part of 2016 and the project works are currently being progressed. The construction works of CP04 have still not started.

Due to the adverse weather conditions that prevailed, heavy showers and floods were experienced during the initial stage of the reporting period (April-May 2016). However, the weather was mostly dry throughout the latter part of the reporting period and was favourable for construction activities.

The baseline sampling of the selected environment parameters were collected and reports were submitted to the PMU by CP-02 and CP 03 respectively, while only operational period sampling is planned to be collected in CP-01.

Moreover, the contractors have obtained the relevant licences and approvals that were required to execute the construction activities.

No major environmental impacts were observed during the reporting period, because CP 01 road works are almost completed and the works of other projects’ have just started. Nevertheless, we have observed few shortcomings on safety matters which were however rectified then there.

5

1. INTRODUCTION

Sri Lanka is an island, blessed with lush green forest and year around temperate climate. It has hilly terrain in middle and south west part with surrounding flat law terrain. The South-West part of the country experiences more rainfall and defined as Wet Zone, and while other parts mostly North- West and South-West parts received less rainfall defined as Dry Zone of the country. For administrative purposes, the island has been divided into seven administrative divisions. The Central Government is situated in District, where the parliament is situated in. Considering the strength of each province in terms of economic and political, the Southern and the Western Provinces are ranked amongst the first level of administrative divisions of the island. These two provinces have vital economic development compared to the other five . These two provinces contribute over 60% of the country’s GDP while other provinces contribute the rest. The southern Province's capital is Galle, while Colombo is the capital of the western province. Subsistence farming and fishing is the main source of income for the vast majority of the people of the Southern region but recently the economic activities witnessed some degree of diversification viz tourism and related economic activities such as hotels, boutiques, villas, handicrafts, travel guiding, and tour organizing. The majority of people are well educated and enjoy decent healthcare facilities and other common amenities. A vast majority of the people are keen to enter the newly created economic space through the Southern highway network which links all the strategically important townships along the way. These townships are poised to boost new economic development opportunities in the area which are also situated in close proximity to famous tourist destinations. In view thereof, the southern road connectivity project will help improve the connectivity between expressway network and the local transport network in southern region. Accordingly, it is proposed to develop 33.5 km of national highways linking with the three interchanges of the southern expressway.

6

The proposed development will not only improve the expressway connectivity but would also help manage the future traffic volumes. Southern Road connectivity project will improve five priority national highways which provide connectivity to three interchanges of Southern Expressway. The priority roads are selected according to the current road condition and capacity, traffic demands, and readiness for improvement. The road will be widened, upgraded and realigned as necessary to meet the projected traffic demand for the next 20 years. The pavement is designed for life up to 10 years that could be extended to 15-20 years with proper maintenance and excess axle load control. Bridges, drainage structures and culverts will be improved and replaced as required. Road safety audit will be incorporated into the engineering designs and monitored during construction period. The details of the selected roads are furnished below;

Table 1.1 The detail of SRCP road projects

Contract Road Name Route No Length (Km) Package Ratmalana - Mirihana Road B389 2.14 CP1 Moratuwa Piliyandala Road B295 2.55

Kesbewa - Pokunuwita Road B084 14.38 CP2 Kiriulapana - Godagama Road A004 1.79

CP3 Matugama - Southern Expressway B157 10.37

1.1 Report Purpose The monitoring process of the environmental safeguards compliance of the project is entrusted to Project Management Unit and Environmental & Social Development (ESD) Unit of RDA. This Annual report is prepared by Project Management Unit to present the situation of environmental safeguard of the ongoing projects and the monitoring results to the ADB.

7

2. PROJECT IMPLEMENTATION PROGRESS 2.1 Recruitment of Project Implementing Consultant

The MG Consultants (Pvt.) Limited has been selected as the consultancy firm for the SRCP on 12th March 2015. The cabinet approval has also been granted, and the consultant has mobilized on 8th June 2015 and contract is in progress. The PIC office operates in , Sri Lanka and it occupies Team Leader and his technical staff.

2.2 Project Implementing Consultants’ (PIC) role in environmental safeguards compliance

The Team Leader (TL), Residential Engineer (RE) with the Environmental Specialist (ES) of PIC is responsible for assessment of the contractors proposed methods in relation with the stipulated EMP. The TL will advise and assist the RE in co-ordination and meetings with external agencies and bodies with direct concerns in the project.

Further, the RE gives direction and instructions to the contractor to mitigate the possible adverse effects on the environment caused by construction activities.

In the event that some sections of sub project’s roads run through the environmentally sensitive areas, the contractors should strictly follow all the rules and regulations laid down by various authorities governing these areas while the construction activities are going on. The ES of PIC shall pay particular attention to these areas and advice the RE and contractor accordingly as regards the proper procedure to be followed and the necessary permits which need to be obtained before commencement of work/completion of the works.

The environmental monitoring procedure/task is being carried out by the PMU and the PIC on a monthly basis with the participation of the contractor’s representatives. The meeting summarizes the activities done by the contractor in each month and suggestions are made to mitigate possible adverse impacts on the environment. The issues that cannot be resolved at the above meeting will be

8 tabled at the Monthly Progress Meeting conducted by the PD of the PMU and would be further escalated to the GRC if necessary.

2.3 The project implementing progress

Of the ongoing three road projects, CP 01 has almost been completed its major works and other two projects ‘works are being progressed. CP-02 and CP 03 projects works have been handed over to the contractors with sectional basis due to the land acquisition matters. The time targets are given to solve the land acquisition matters in said two road projects and those sections will be handed over to the contractor. 2.3.1. Rehabilitation/Improvements to sections of Moratuwa – Piliyandala Road The project has been awarded to KD Ebert & Sons Holdings (PVT) on 23rd of October 2014. The all major construction activities have almost been completed during the reporting period, while considering about progress up to 31st March, 2017, the Physical progress was 96.44%. 2.3.2.. Rehabilitation/Improvements to sections of Kesbewa – Pokunuwita and – Godagama Road. The project has been awarded to MAGA Engineering (Pvt.) Ltd, on 9th of September 2016 and the contract should be completed within two years from the commencement date. The Order to Commence was issued on 17th November 2016 for the Section 1 – B084 Km 13+800 to 16+520 (2.72km),Section 3 – B084 Km 18+600 to 21+800 (3.20km), and Section 5 (amended) – A004 Km 17+260 to 18+200 (0.94km). The rest of area (9.33km in Sections 2, 4 and 6) will be handed over to the contractor immediate after the land acquisition completed, that are expected to be finished on August 2017.

2.3.3. Rehabilitation/Improvements to sections of Southern Expressway – Matugama Road The project has been awarded to MAGA Engineering (PVT) Ltd, on 27th June 2016.

9

Road works have started at the sections 1, and 2. The construction works of section 01 are well progressing. The major culverts and bridges works have been started while 39/5 bridge works almost has started. Considering about progress up to 31st March, 2017, the Physical progress is 16.67%.

2.3.4. Rehabilitation/Improvements to CINEC Junction to Ambathale Junction Link Road The Letter of Acceptance (LOA) was issued to Olimpus Construction (Pvt)Ltd, and the work planned to be started from June 2017. The project road hasn’t land acquisition matters.

10

3. CONSTRUCTION PROGRESS

The all project roads have started their construction works during the reporting period except the CP04, while the CP 01 project is nearing completion. The CP-02 and CP03 project have just begun their works.

4.1 Rathmalana-Mirihana (B389) and Moratuwa-Piliyandala (B295) roads. The Contractor has finished his material sources from his crusher, quarry and asphalt plant at Naboda which is located approx. 50 km away from the road sites. The monthly plant visits by Client and Consultant have completed in the month of September 2016. The all major construction activities have been completed. Related images pertaining to some of the project activities are given below; 1. Moratuwa-Piliyandala (B295) Road

2. Rathmalana-Mirihana (B389) Road

Figure3:1 completed pedestrian crossing at Km 2+930 road marking at Km 3+860 of B 295 and completed sections at Km 0+200 and Km 0+480 of B389

During the material sourcing period up to December 2016, the contractor has obtained all the relevant permissions and licenses for quarry, crusher and asphalt 11 plant operations. The validity periods of given licences are not necessary to extend due to completion of road works. Table 3.1. The summary of obtained licences and permits

Type of Approving Date of Date of Type of Location Approval/ Licensing obtaining validity Quarry/plant license Authority Approval end

1.Metal EPL CEA 24 .06.2015 23.06. 2017 quarry 00376(R8)

Industrial GSMB 21.05.2017 Thudugala, Mining IML/A/HO/219 22.05.2015

Neboda License 5/R/5 District Explosive Explosive controller 30.06.2015 30.12.2016 License (A 275109) 2.Crusher CEA EPL Plant 01587(R7)04481(R 16.07.2015 15.07.2017

Thudugala, 4) Neboda Trade Dodangoda LA 18.02.2015 31.12.2017 License 3. Asphalt EPL CEA Thudugala, 16.03.2015 31.03.2017 Plant Neboda 05067 (R2) 4.Concrete Batching Rukmalgama, EPL CEA 01/10/2015 31 01 2017 Athurugiriya Plant

3.2. CP-02 Rehabilitation/Improvements to sections of Kesbewa – Pokunuwita and Kirulapana – Godagama Road The Order to Commence was issued on 17th November 2016 for the sections 1, 3 and 5. Other sections such as sections 2, 4 and 6 are to be granted on August 2017. The construction works of culverts and bridges of section 01 and 03 have been started while only clearing and grubbing works are started at section 05. The contractor has found 06 disposal lands to dispose the waste. The approval process is being progressed during the reporting period while; the Western

12

Provincial Waste Authority is willing to accept the unsuitable at their waste dumping premises situated close to the project road. The material sourcing sites of the contractor, such as quarry, crusher and concrete batching plants are operated with relevant updated licenses (See Table 3.3). The environmental and social issues are negligible in these sites and regular inspections have been carried out. The contractor’s own plant sites such as Quarry, Crusher and Asphalt plants are situated nearby areas such as follows;

Table.3.2. The materials sourcing locations and distance Plant type Capacity Location Distance from Project Road(KM) Asphalt 80 ton/hour 20 Quarry - Kumbuka 5 Crusher 500m3/day Millaniya 35 Concrete Batching 350m3/day Kumbuka 5 Plant

The contractor is not operating his own burrow areas and sourcing his sub-base material requirements from outside commercial base burrow areas.

Table 3:3 The summary of obtained licenses and permits Type of Approving Date of Date of Type of Location Approval/li Licensing obtaining validity Remarks Quarry/plant cense Authority Approval end 1.Metal Informed to EPL CEA quarry 10 .06.2016 09.06. 2017 renew the 00976(R8) licenses Apply to Industrial GSMB 26.05.2017 renewal on Millaniya, Mining IML/A/HO 27.05.2016 15th April License /7037/R/03 2017 District - Explosive Explosive 10.08.2016 14.08.2017 License controller (A 280360)

2.Crusher Kumbuka, EPL CEA 28.03.2016 27.03.2018 -

13

Plant Horana 08019(R2) Trade - Horana LA 10.0`.2017 31.12.2017 License 3. Asphalt Informed to EPL CEA Plant Hoamagama 07.06.2016 06.06.2017 renew the 01576 (R8) licenses 4.Concrete CEA - EPL 24.04.2017 23.04.2018 Batching 13911(Ro) Kumbuka, Plant Horana Trade - Horana LA 25.01.2017 31.01.2017 License

Culvert & Bridges Bridges and Culverts construction activities are progressing in all three sections while 63% progress is recorded in section 1. The relevant warning signs such as “Men at works, Road marrows and other signs have properly been fixed.

Figure 3.2 the ongoing construction activities of Culvert (16/1) deck concreting at Km 15+298 and Bridge (17/3) base concreting at 16+321

Other Constructions Clearing and Grubbing, Roadway Excavation, Rock Filling, and Lined drains works are progressing in all sections while section 01 almost finished the Clearing and Grubbing activity. Restoration of Government properties adjoining to the road is progressing. Under this activity, mainly boundary walls and utility facilities are considered to be reconstructed.

14

3.3. CP-03 Rehabilitation/Improvements to sections of Southern Expressway – Matugama Road.

The Order to Commence was issued on 09th September 2016 for Section 1 – from Km 42+372 to 37+000 (5.372km). While remain section (5.0km in Section 2) was given to the contractor on March 2017. Meanwhile the construction works of section 01 are progressing while the major culverts and bridges works have also been started. The bridge works of 39/5 works has just started and bypass road including temporary bridge is constructed to carrying the traffic until new bridge will be finished. The necessary safety precautions including night time visibility are taken at the site.

Table 3:4 The summary of obtained licenses and permits. Type of Date of Type of Approving Licensing Date of Location Approval/lice obtaining Remarks Quarry/plant Authority validity end nse Approval

1.Metal quarry CEA - EPL 21 .11.2016 20.11. 2017 04762(R5)

The Mr. Industrial GSMB contractor Wanniarchchi, Mining IML/B/HO/1332/LR 21.03.2016 30.06.2017 has applied Wallatha, License /08 to renewal Naboda District Explosive Do Explosive controller 28.12.2016 27.06.2017 License (A 280327) 2.Crusher The Plant contractor CEA has applied EPL 25.05.2016 24.05.2017 W.K.K, 02547(R7)) to renewal Neboda on 21st March 2017 Trade License Dodangoda LA 08.03.2017 31.12.2017 - 3. Asphalt CEA Danister EPL 04.01.2017 03.01.2018 - Plant Estate, 12060 (R1) Welipenna Trade License Mathugama LA 07.03.2017 31.12.2017 -

15

4.Concrete - Gabada CEA Batching Plant Junction, EPL 28.10.2016 27.10.2019 WE-B 03552(R0) Welipenna

16

4. Completion of the Environmental Compliance

The SRCP projects have been categorized under “B” category of the ADB environmental and safeguard policy statements in 2009. Therefore the PMU have submitted only IEEs reports to ADB regarding the five road sections. The Basic Information Questionnaire, which is a report that included all the significant and anticipated impacts of the proposed project, was submitted to the CEA for each projects, the B084 and A004 roads fall under the EIA category while other projects (B157, B 389 and B 295) only required basic questionnaire. The status of the government compliance details are as follows;

4.1. CP01: Rathmalana-Mirihana (B389) and Moratuwa-Piliyandala (B295)

The Initial Environmental Examination reports (IEE) had been submitted for the Rathmalana-Mirihana and Moratuwa-Piliyandala road respectively. Those reports were approved by the ADB.

The environmental approvals are granted by the Central Environmental Authority (CEA) based on the Basic Information Questionaries to implement the road works for the above two projects. The validity period of above project roads will expire in the year 2017 and renewal is not required because the construction works of the road have almost been completed (See Annex 01).

Validity Period Road Code Name of the Road From To

B389 Ratmalana-Mirihana Road 13. 02. 2013 20. 09. 2017

B295 Moratuwa-Piliyandala Road 11. 03. 2013 12. 05. 2017

The contractor’s Environmental Management Action plan (EMAP) and Traffic Management Plan have been approved on August 2015 and September 2015 respectively by the Client and Consultant.

Environmental parameter observation activity for the pre construction stage (Base line) and construction stage were completed. The results have been submitted to the client.

17

Monthly environmental meetings have been completed on December 2016 due to end of the major construction works.

The restoring activities such as debris cleaning at yards and office locations, stock piling and disposal yard (Suwarapola) have been initiated. The contractor has prepared a rehabilitation report, which is included all his restoring activities is being reviewed.

4.2. CP02: Kirulapana-Godagama (A004) and -Pokunuwita (B084)

The Initial Environmental Examination reports (IEE) of both road projects had been approved by the ADB.

The environmental approvals are also granted by the Central Environmental Authority (CEA) based on the submitted EIA to implement the road works for the above two projects (See Annex 01).

Validity Period Road Code Name of the Road From To Aoo4 Kirulapona-Godagama Road 24.03. 2014 23.03.2020

B084 Kesbewa-Pokunuwita Road 25.03. 2013 24.03.2020

The contractor’s Environmental Management Action plan (EMAP) and Traffic Management Plan have been approved on November 2016 by the Client and the Consultant.

When the meetings are held, joint site inspections are carried out together with client, consultant and contractor to observe the environmental and safety lapses. During the site visits, any recorded public complains are also being followed up.

4.3: CP03: B157 Mathugama-Southern Highway

The Initial Environmental Examination report (IEE) had been submitted on May 2013 and it was approved by the ADB.

18

The environmental approval has been granted by the Central Environmental Authority (CEA) based on the Basic Questionnaire to implement the road works (See Annex 01).

Validity Period Road Code Name of the Road From To B157 Mathugama-Southern Highway 24.11.2014 06.01.2018

The contractor’s Environmental Management Action plan (EMAP) and Traffic Management Plan have been approved on November 2016 by the Client and the Consultant.

4.4. Changes in project scope The proposed scope of the project of Southern Highway to Mathugama has been amended as follows. Mathugama-Southern Highway (B157), the initial approvals were granted to carry out about the 12 km length to 32 km post from 40 km post. The two kms length has been excluded from 30km to 32km, as 2Km length has already been developed through an another project. Hence, there has been a reduction in the road length from 12.37 km to 10.37km.

19

5. SUMMARY OF ENVIRONMENTAL MITIGATIONS AND

COMPENSATION MEASURES

Based on the approved EMAP, the sub-project contractor has to periodically carry out the monitoring of selected environmental parameters such as ambient air quality, noise levels, water quality and vibration levels. The contractor should monitor the above parameters during the pre-construction (Baseline), construction and post- construction or operation period of each project road. In order to prevent lowering of green cover along the road due removal of existing tree/bushes, the contractor is obligated to implement suitable tree planting programs along the road or within the project road area. In additionally the contractor should rehabilitate their all material sourcing locations, yard and disposal sites, immediate after the completion of the project activity.

5.1. Moratuwa - Piliyandala (B295) and Ratmalana - Mirihana (B389) 4.64 km. Collection of baseline and the construction stage data have been completed. Data was collected by the approved sub-contractor of Industrial Technology Institute (ITI) during 2015-2016. The results have been submitted to the PMU of the RDA. The operation stage data will be collected as immediate after the road section completed and handed over to the client. During the construction period of B295 road, all the readings of water samples found to be similar to baseline values but TSS was less and E Coli had increased not due to construction activities. B 389 when compared with baseline values, pH was at neutral range, TSS decreases and E coli level has increased, not due to construction activities. It was identified that the domestic waste water discharged into surface water body was coursed to increase E-coli in the area. According to the noise measurement test results of B 295, allowable noise level is 75dB(A). Except at B389 in front of Mahamaya School (80dB(A) and at B295 near Indra Traders, Piliyandala (76dB(A), noise level all the other locations were within allowable levels.

20

Except for location, Kospalana Junction, all the parameters of other locations were well below the ambient air quality standards. TSPM level is high at Kospalana Junction, this may due to vehicular movement of the road. As per the given vibration data, all the measured levels (baseline data) are within the standard level. The vibration levels have not exceeded with normal vehicle movement of these two road sections. A detail of observed data during the pre-construction period is given in Appendix 02.

Considering about the awareness programs, there were nine (09) programs which are related to HIV/AIDS, Human Trafficking, and Environmental awareness held by the project staff during the reporting period as follows.

Table 5:1 A summary of the held HIV/AIDS programs Total Date & Venue Resource Persons Participated personals participants Male Female 11/06/2017 at RE’s National HIV/AIDS control Labours, site supervisors office in unit of Sri Lanka(Dr. Janaki and staff members Pandithrathne, Dr. 53 03 N.Dissanayake and Dr. P.Premadasa 13/09/2016 at DS Do Government officers of office in Maharagama surrounding areas of 25 67 project road 22/10/2016 at Rural Dr.Duminda Senevirathne and Workers and contractor’s Hospital in Neboda, Dr.H.S.S Ruwan of Plant sites and 17 25 Kaluthara surround communities 20/11/2016 at Rural Do Do Hospital in Neboda, 43 19 Kaluthara

There were four (04) programs on HIV/AIDS conducted by the National HIV/AIDS Control Unit. The programs had been organized to improve the awareness among the construction workers as well as community members of

21 project area. These programs were keenly conducted by close supervision of Dr. (Ms.) Janaki Panditharathne, who represents the National HIV/AIDS Control Unit of Sri Lanka.

With regards to the environmental awareness programs, there were two programs held under the topic of Solid Waste Management and Recycling. These programs have been organized to improve the knowledge of project areas communities.

Meanwhile, the contractor had organized the two human trafficking programs, two child protection programs and one income generation program as follows;

Table 5:2 The summary of conducted other programs participation Program Date & Venue Resource persons Female Male Solid Waste 26th May 2016 at Mr. S. Jayatissa, CEA, Sri Lanka management and RE’s office 06 42 Human Mr. M.Dissanayake, Attorny at Law, Trafficking Colombo Solid Waste 21st July 2016 at Mrs. Shantha Dayaseeli, CEA, Sri management & Rukmalagama lanka 15 15 Recycling Road Safety and 14th July 2016 at Ms.Kusum Punchihewa, Sri Lanka Child protecting Pre-school, Police. 32 8 Suwarapola 25th August 2016 at Do Agrarian Service 18 18 centre, Udahamulla Human 30th September 2016 Mr.Lasantha Alwis Trafficking and at School in Income Piliyandala 82 23 Generation Activity

The all lectures were conducted by specialized personnel on the relevant field.

22

HIV/AIDS program held on 11/06/2016 and 13/09/2016

Solid Waste Management program held on 26/05/2016 and 30/09/2016

Figure 5:1 The held Safety and Environmental awareness meetings

The scheduled Gender Action Plan (GAP) and the environmental awareness programs have been conducted successfully by CP 01 project and the detail of environmental mitigation activities performed by the contractor are summarized as below in Table 5.2.

Table 5.2 A summary of the major environmental mitigation activities of CP 01

Comment on Issues for Reasons for Compliance Further Action EMP Requirement Partial or Attained and Target Non- Dates Compliance Baseline Yes Completed - sampling Construction Environmental Yes Completed - 1 stage Parameter Observation The activity Operational To be No will be Stage conducted conducted Immediate after 23

the road section handed over to the RDA 2 Fauna flora survey Yes Completed - Environmental 3 Yes Completed - awareness Health & Safety 4 Yes Completed - Awareness Yes 5 HIV/AIDS programs Completed -

According to the contractor’s completed compensative tree planting program, 260 saplings were planted. A tree enrichment program also carried out to replacement of wilted trees of previously replanted areas. The following table shows the summary of completed works. Table: 5:3 A summary of completed tree planting program

Survival Number Programme Venue/Date Plant Varieties rates and of Plant action taken Replanting Mirihana Police Mangifera indica (Mango), 20 plants Programme 01 Ground & Nephelium lappaceum (Rambutan), were Subadrarama Temple Aegle marmelos (Beli), Terminalia replanted by 50 premises on arjuna (Kumbuk) Artocarpus plant 05/05/2012 heterophyllus (Jack), Cassia fistula enrichment (Ehela) etc, program Replanting Waste Management Terminalia arjuna (Kumbuk), Cassia 4 plants Programme 02 Authority premises at fistula (Ehela), Aegle marmelos (Beli) were 20 For World Envi: Day Karadiyana on replanted 07/06/2016 Replanting Along the Bolgoda lake Mangrove Plants such as 90% plants Programme 03 at Waste Management Rhizophora mucronata, and R. survived Mangrove Planting Authority premises at Apiculata (Maha Kadole, Rathu and wilted Karadiyana on Kadole.). plants were 16/08/2016 not replaced because the 100 WM Authority promised to complete the task by themself

24

Replanting Sri Siddartha Homegarden species such as 3 plants Programme 04 Collage premises and Mangifera indica (Amba), Punica were play ground area on granatum (Delum) Psidium guajava replanted 26/10/2016 (Pera), Annona muricata(Katu anoda) ,Persea Americana (Aligeta pera), Cinnamomum verum(Kurudu), 50 Citrus spp.(Dehi) and Piper nigrum(Gammiris). Forest trees such as Swietenia macrophylla (Mahogani),Tactonia grandis (Thekka), Berrya cordifolia (Halmilla) , Pongamia pinnata (Karanda)etc. Replanting Stenly Thilakarathna Home-garden species such as All the Programme 05 School premises on Flacourtia Indica(Uguressa), plants were 23/11/2016 Syzygium aqueum (Jumboo), Punica at good granatum (Delum), Psidium guajava condition. It (Pera), Annona muricata(Katu was anoda), Persea Americana (Aligeta observed 40 pera),Citrus spp. and Piper 100% nigrum(Gammiris) survival rate

Shade and forest trees such as Pongamia pinnata(Karanda) Messua ferrea (Na) etc.)

Figure 5:2 A mango sapling is planted by Project Director at Police Ground premises while Resident Engineer is plating a mangrove plant at Bolgoda lake area

5.2. Kesbewa - Pokunuwita Road (B084) and Kirulapana - Godagama Road (A004 Collection of baseline data has been completed and this activity was done under the approved sub-contractor. The Industrial Technology Institute (ITI) was selected for the above purpose and it was conducted in December 2016. The results have been submitted to the PMU of the RDA. The construction stage data will be

25 collected within six month intervals and next sampling will be conducted on June 2017. According to the test results of water quality, pH is within standard levels, while ground water sample did not fall within the stipulated levels. pH is acidic (6.2), standard in 6.5-8.5 range. pH acidic due to soil nature. This type of soil contains the Humic acid. All six samples of “BoD5” levels are within standard level. However all the locations’ day time background noise level was higher than the permissible level of the area and total suspended particulate matter (TSPM) of air quality monitoring was lower than the permissible level of 450µg/m3 of the all sampled locations. During the reporting period, there was one (01) program on HIV/AIDS conducted by MOH office staff with coordinating of the National HIV/AIDS Control Unit of Colombo. The program was useful to improve the knowledge of the construction workers as well as community members of project area.

Similarly, the contractor has conducted two road safety awareness programs with participation of Police traffic control units within the area. The details of conducted programs are as follows,

Table 5:4 A summary of the held HIV/AIDS programs

participation Program Date & Venue Resource persons Female Male HIV/AIDS 11/01/2017 at Dr.Samanthi Wijesundara, and prevention Boralesgamuwa Dr.Dilshan Wijerathne, MOH office, 20 20 programm Boralesgamuwa Road safety 7th March 2017 at Mr. Madugoda, Piliyandala Police. Awarenss Guidance 28 16 programm international School, Kesbewa Mr.M.K Jagath and Mr.Indika Prasad 70 00 of Moragahahena Police, Kesbewa

Similarly, the scheduled Gender Action Plan (GAP) and the environmental awareness programs are being progressed by CP 02 project and the detail of

26

environmental mitigation activities performed by the contractor are summarized as below in Table 5.5.

Table: 5:5 A summary of the major environmental mitigation activities of CP 02 Comment on Reasons for Issues for Further Compliance EMP Requirement Partial or Action and Target Attained Non- Dates Compliance Baseline Yes Completed - sampling The quotations were called to 1st sampling and it has Construction Yes been approved by stage PIC. Sampling will Environmental 1 be taken place in Parameter Observation June 2017. The activity will be conducted Operational To be Immediate after the No Stage conducted road section handed over to the RDA 2 Fauna flora survey Yes Completed - More The contractor is Environmental 3 NO programs to advised to conduct awareness be conducted the programs More Health & Safety 4 Yes programs to - Awareness be conducted The contractor is Being 5 HIV/AIDS programm Yes advised to expedite progressed the activity

27

Figure 5: 3 The conducted HIV/AIDS programs in Boralesgamuwa on 21/01/21 and Gonapola Temple main hall on 3/4/2017.

Having discussed about the tree planting program, a plant nursery is established to maintain the selected saplings inside the contractor’s yard which is intended to be used for future tree planting programs along the road. In comparison to the CP 01 project road, this road has adequate spaces within the ROW which can be used to tree planting activity.

Figure 5:4 A nursery which is managed to replant along the ROW of the road

In addition to the above mentioned program, the contractor was requested to carry out the plant enrichment program along the Piliyandala bypass road which was constructed by previous project of NHSP funded by ADB. A greenery program

28 was previously conducted and now it is likely to be abandoned. Therefore the client has requested to carry out the plant enrichment program.

Figure 5:5 The weeds spread over the road side trees and the Green Islands are abandoned. 5.3. Southern Expressway - Matugama Road (B157)- 10.37km Initially, the collection of baseline data has been completed and the task was carried out by Industrial Technology Institute (ITI) which is a government own institute. The activity was conducted on December 2016. The results have been submitted to the PMU of the RDA. The construction stage data will be collected by six month intervals and next sampling will be conducted on June 2017. With regards to the submitted test results of water quality, the pH, BOD and oil/greece content were at its standard level in all locations. According to the measured vibration levels, the maximum permissible levels of interim vibration standards have not been exceeded with the vehicle movements of this road section. As compared to the measured results of air quality, TSPM (03hr) average was lower than the permissible level of 450µg/m3 at all locations.

During the reporting period, there was one (01) program on HIV/AIDS conducted by MOH office staff with coordinating of National HIV/AIDS Control Unit of Colombo. The program has been organized for the community in the neighbourhood of project area and as well as for the construction workers.

29

Similarly, the contractor had conducted a one road safety awareness programs with participation of Police traffic control units within the area. The details of conducted programs are as follows,

Table 5:6 A summary of the held HIV/AIDS programs participation Program Date & Venue Resource persons Female Male HIV/AIDS 21/01/2017 at Dr. Geethani Samaraweera and Dr. prevention School Auditorium, S.A.P Nishanthi, MOH office, 35 19 program Walipenna Nagoda, Kaluthara 15/03/2017 at Road safety School Auditorium, Mr. Rajarathne Jayasundara, Police Awareness 42 11 Owitigala, station, Welopenna. program Mathugama

In the same way, the scheduled Gender Action Plan (GAP) and the environmental awareness programs are being progressed by CP 03 project. However an implementation delay was observed which was due to various reasons and the contractor was informed to expedite the work without any further delay. The details of environmental mitigation activities done by the contractor are summarized as below in Table 5.7.

Table 5:7 A summary of the major environmental mitigation activities of CP03 Comment on Issues for Further Compliance Reasons for EMP Requirement Action and Target Attained Partial or Non- Dates Compliance Baseline Yes Completed - sampling The quotations were called to 1st Construction Yes sampling and it has stage been approved by Environmental 1 PIC Parameter Observation The activity will be conducted Operational immediate after the No To be conducted Stage road section handed over to the RDA

30

2 Fauna flora survey Yes Completed - Environmental More programs 3 Yes - awareness to be conducted Health & Safety More programs 4 Yes - Awareness to be conducted

5 HIV/AIDS program Yes Being Completed -

Figure 5:6 Conducted awareness programs of CP 03 project, Above: Road safety awareness meeting at Owitigala School hall conducted on 15th March 2017. Below: HIV/AIDS awareness program conducted at Welipenna School hall on 21st January 2017

The contractor has planned to implement a tree planting program along the road in the space available in ROW immediate after road completion. The root bowling trees will be used for this activity and community tree planting programs are also planned to be implementation.

31

6. SUMMARY OF ENVIRONMENTAL MONITORING

Based on the approved EMAP, the sub-project contractor has to periodically carry out the monitoring of selected environmental parameters such as ambient air quality, noise levels, water quality and vibration levels. The contractor should monitor the above parameters during the pre-construction (Baseline), construction and post- construction or operation period of each project road.

6.1 Moratuwa - Piliyandala (B295) and Ratmalana - Mirihana (B389) 4.64 km Collecting of environmental parameters such as Air quality, water quality, Noise and Vibration levels for Pre-construction (baseline data) and the construction stage had been observed. The task was assigned by the approved sub-contractor of government of Sri Lanka. The project road and the material sourcing locations were also subjected to monitoring and the following table shows the data collecting activity of the CP 01 project. Table 6:1 The dates of environmental parameters monitoring Parameter Baseline Construction stage I Construction stage II Water 06/10/2015 30/06/2016 21/09/2016 Air 06/10/2015 30/06/2016 12/09/2016 Noise 13/10/2015 28/04/2016 02/08/2016 Vibration 13/10/2015 14/06/2016 04/08/2016

The detail of the observed data that was during the pre-construction period is given in Appendix 2. According to the observed water quality data of B295 road, it was similar to baseline values, but TSS was low and E-coli had increased during the construction stage I and II data. In B 389 road, when compared with baseline values, pH in neutralize range, TSS decreased and E-coli had increased during construction stage II data. Considering about the air quality results, baseline measurements were carried out with 8hr average but during the construction stage I and II data measurements were carried out with 1hr average. All locations in both roads of B295 and B 389, the TSPM (1hr) was higher than the allowable level (500μg/m3) during the construction stage II. The noise level of B295 road, the measured levels of two locations (Kospalana and Suwarapola) were higher than the

32 baseline values during the construction stage I and II, but lower than the allowable level(75dB(A). At Piliyandala town, measured levels were lower than baseline values and lower than allowable level. B 389 road locations, all three locations during construction stage I and II measured locations are lower than baseline values and lower than the allowable level (75dB) 6.2 Kesbewa - Pokunuwita Road (B084) and Kirulapana - Godagama Road (A004). Baseline data collection for the pre-construction stage of the project roads, i.e. the Ambient Air, Water, Noise and Vibration levels, were collected before commencement of the main construction activities. The data was collected in December 2016, and the construction stage data will be collected in June 2017.

The detail of the observed data that was during the pre-construction period is given in Appendix 2. Considering about the water quality results, the pH values were within the standard for all surface water samples, but ground water samples’ pH was 6.2, which was not within standard. All eight locations of air quality samples of B084 , A004 and all plant sites baseline values of TSPM (3hr average) was lower than the permissible level of 450/μg/m3. According to noise levels, most of the locations background level is higher than the permissible level of the area and all existing measured noise levels are higher than the permissible levels at day times. These may due to existing traffic nature. The results of the vibration levels of the project area, maximum permissible levels (1.0, 2.0, or 4.0) of interim vibration standards have not become exceeded with the vehicle movements of these road sections.

6.3 Southern Expressway - Matugama Road (B157) Similarly, the baseline data collection of the project road was collected before commencement of the main construction activities. The observer of the event was Industrial Technological Institute (ITI). During the sampling, water, air, noise and vibrations were sampled along the project road as well as selected material sourcing location of the contractor.

33

The detail of the observed data that was during the pre-construction period is given in Appendix 2. According to the measured water quality of all three locations pH, BOD and grease content are within standard. All three locations of air quality samples, TSPM 3hr average is lower than the permissible level of 450/ug/m3. The all existing measured noise levels are higher than the permissible level of day time, this may due to traffic noise. Considering about the vibration levels, permissible level of interim standards have not been exceeded with vehicular movement of this road section. 6.4 Compliance Inspections

During the reporting period, road construction works were progressing in all sub- projects while CP-01 works were nearing completion. Monthly field inspections were carried out by Environmental Specialists of the Employer, PIC and Contractor. Appendix 03, summarizes the activities carried out in CP-01, CP-02 and CP-03 Sub-projects, their impacts to the environment (as observed during each field visit mainly by the ES of PIC), suggestions given by ES to mitigate, avoid or minimize the adverse impacts, effectiveness of the migration measures adopted, and any further action needed.

Table 6.2 The status of the contractor’s EMP implementation EMP part of EMP being Status of EMP Contract Sub Project Implemented Implementation Action Proposed Document (Yes/No) (*) (Yes/No) Advised to fully Implement the EMAP CP-01 Yes Yes Good submitted by Contractor Advised to fully Implement the EMAP CP-02 Yes Yes Good submitted by Contractor Advised to fully Implement the EMAP CP 03 Yes Yes Good submitted by Contractor

(*) 1 – Very good (All required Mitigation Implemented), 2 – Good (The majority of required Mitigation Implemented), 3- Fair (Some Mitigation Implemented), 4– Poor (Few Mitigation Implemented) ,5 – Very Poor (Very few or No Mitigation Implemented)

34

Although the contractors have been placed in good category based on the EMP implemented, their traffic and safety measures should be upgraded further due to high traffic congestion in the project area, especially in the morning and evening time at CP01 and CP02. The detailed compliance to EMP is provided in Appendix 04 and their activities are separately discussed as follows.

Considering the total number of 19 mitigation actions to be complied in CP 01 project, 13 actions have been fully complied; while six (6) mitigation actions are partly complied. The main reasons for the partly complied actions were; the activities will be implemented after handed over the road sections. Other than these, set of all other mitigation actions were completed by the contractor.

Because of newly started projects, all the mitigation actions that are described in EMP should be implemented or complied by the contractors of CP02 and CP 03.

The monthly payment item for EMP requirements is provided in the contract. The payment is released after receiving of the recommendations based on the monthly inspections and observations by employer and the PIC Environmental Specialists (ES) with participation of the contractor’s Environmental Officer (EO).

According to approved payment percentage of the EMP payments (Table 6.2), the contactor has obtained 75% of average payment values base on the EMP implementation activities done during each month.

The following table shows the monthly payment percentages that had been made to the contractor based on the EMP implementation in the project.

Table 6.3. The approved monthly percentages for EMP implementation during the reporting period

EMP implementation Months Approved percentage (%) CP01 CP 02 CP 03 May 2016 78 - - 35

June 2016 83 - - July 2016 66 - - August 55 - - September 2016 65 - - October 2016 35 - - November 2016 80 - - December 2016 87 - 69 January 2017 - 79 69 February 2017 - 89 70 March 2017 - 88 83 April 2017 91 81

36

7. PUBLIC COMPLAINTS

The Grievance Redress Committees (GRCs) have been established to look into the public complaints regarding the social and environmental impacts during the period of construction works for every sub project. The GRC considers the problems that could not be solved directly by the Employer, Consultant and Contractor. The GRC committee holds meetings with all responsible parties to yield the best solutions for the problems.

Table 7:1 The established GRC dates and Divisional Secretariat Offices Package Road Name Divisional Secretariat GRC established date Rathmalana - Mirihana Road (B389) Maharagama 05. 05 .2015 CP 01 Moratuwa - Piliyandala Road Sri Jayawardenpura 01.11 .2014 (B295)

Kirulapana - Godagama Road Homagama 05. 05 .2015 (A004) CP 02 Kesbewa - Pokunuwita Road (B084) Kesbewa 05. 05 .2015 Southern Expressway - Matugama CP 03 Mathugama 05. 05 .2015 Road (B157

The PMU and Divisional Secretary arrange the GRC meetings upon receiving of public complaints to solve the problems. Considering the number of complaints received so far, there were two GRC meetings conducted at Divisional Secretariat Office in Kesbewa to discuss the received 04 complaints regarding to CP01 project and these problems have been solved.

The above mentioned GRC meetings were conducted at Divisional Secretariats office in Kesbewa respectively on 23rd December 2016 and January 2017.

37

Figure: 2.1 The GRC Committee members including chief incumbent of Buddhist temple, Project Engineer of CP01, Divisional Secretariat (Kesbewa) and Resettlement Assistant were chaired and discussing about the public complains.

Further, the employer, the consultant and the Contractor attend the public complains which are received in written form and through the electronic media (E- mail, Fax and Telephone). Moreover, all complains received have been listed out and discuss in the monthly progress meetings. The summary of the received complaints up to 31st March 2016 are given in Appendix 05. There were 99 complains have received from both B295 and B389 roads so far, most of them are requesting of cover slabs and proper access to their hoses and business premises. Among them 70 complains were already solved and others are being completed by involving the related line agenesis. Some of the complaints await to insurance claims and those cases will be completed immediately after the claim area received.

Likewise, there were 31 complaints received so far from CP 02 project, among these complaints 15 have been solved, while 13 are pending and, 3 are progressing. In the same way there were 44 complaints received up to 31st march 2016 from CP 03 project, while 15 complaints are already solved, 18 complaints are being progressed and 11 complaints are pending.

In the monthly environmental meetings progress, they draw their attention and discuss about the public complaints.

In addition, small scale Community Committee Meeting had been conducted by CP 01 project (mainly by appointed Environmental Officer of the project) aiming to address the public disturbances while construction activities are progressing.

It was suggested to conduct the Community Committee Based Organizations if necessary in the project affected areas in CP02 and CP 03 (public and private authorities and personnel) which will address the problems regarding the constructions.

38

8. STATUS OF COMPLIANCE TO LOAN AGREEMENT

Based on the information provided in the above sections the compliance of the project to the environment safeguards related clauses in the “Loan Agreement” are generally satisfactory. Detail of the compliance of environmental clauses is provided in the table below. Clause Status of Compliance 1. Schedule 4, Conditions for Award of Complied. Contract Para 6: RDA shall not award any Works contract which involves All contracts have been awarded after CEA environmental impacts until: (a) CEA or the approval of the respective project. All project approving agency designated by bidding documents included the EMP CEA has granted the final approval of the before issuance to the contractor. IEE; and (b) RDA has incorporated the relevant provisions from the EMP into the Works contract. 2. Schedule 5, Environment, Para 4: Complied. The Borrower shall ensure or cause RDA to ensure that the preparation, design, All measures in the IEE and EMP are being construction, implementation, operation implemented. and decommissioning of the Project and all Project facilities comply with (a) all applicable laws and regulations of the Borrower relating to environment, health and safety; (b) the Environmental Safeguards; and (c) all measures and requirements set forth in the relevant IEE, the relevant EMP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report. 3. Schedule 5, Safeguards – Related Complied. Provisions in Bidding Documents and Works Contracts Para 9: All bidding documents included relevant The Borrower shall ensure or cause RDA to provisions from the IEE and EMP. ensure that all bidding documents and contracts for Works contain provisions that The contractor is providing budget for require contractors to: implementing the EMP (a) comply with the measures relevant to the contractor set forth in the IEEs, the There have been no unanticipated EMPs and the RPs (to the extent they environmental risks so far concern impacts on affected people during construction), and any corrective or preventative actions set forth in a Safeguards Monitoring Report; (b) make available a budget for all such environmental and social measures; (c) provide RDA with a written notice of any unanticipated environmental,

39 resettlement or indigenous peoples risks or impacts that arise during construction, implementation or operation of the Project that were not considered in the IEE, the EMP and the RP; 4. Schedule 5, Safeguards Monitoring and Being complied. Reporting Para 10: The Borrower shall do the following or Since the project is environment category B, cause RDA to do the following: the annual environmental monitoring (a) submit semi-annual Safeguards report is being submitted. Monitoring Reports to ADB and disclose relevant information from such reports to There have been no unanticipated affected persons promptly upon environmental risks so far. submission; (b) if any unanticipated environmental There has been no breach of compliance to and/or social risks and impacts arise the EMP so far. during construction, implementation or operation of the Project that were not considered in the relevant IEE, EMP and/or RP, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan; and (c) report any actual or potential breach of compliance with the measures and requirements set forth in an EMP or a RP promptly after becoming aware of the breach.

40

9. CONCLUSION

The guidelines for Environmental protection and pollution control for construction activities are clearly defined in the EMP for all sub-projects. In addition, the Contractor’s EMAP provides further specific time lines & schedules to protect project impacted areas by observing the selected environmental parameters (i.e. Water, Air, Noise & Vibration) to ensure that the surround environment is protected. Firstly, the completed project road of CP 01 was successfully implemented their proposed mitigation measures that were proposed by employer and the consultant during their site observations. The issues at the contractor’s Asphalt plant were satisfactorily solved, but he had taken a long period of time to rectify these issues. Therefore, the all contractors must be taken the proposed remedial actions as soon as possible because these impacts are irreversible. It was revealed that the contractor’s quick response/actions are very important when addressing the construction related environmental problems. Secondly, the weekly site inspections are carried by the Contractor, while Monthly Inspections are continued by the Environmental Specialists of the Employer and PIC. The monthly environmental meetings conduct regularly and the contractor’s participation was satisfied. Site inspection will be regularly carried out to ensure that Environmental impacts are being adequately mitigated and to ensure continuation of compliance with stationary regulations as required by laws and accepted in the EMP. The Contractor is being regularly guided and instructed to pay attention to environmental issues and adhere to the provisions of EMP and his own EMAP. The ongoing projects (CP02 and CP 03) environmental monitoring activities are being progressed as proposed scheduled while final stage monitoring activity will be completed by CP 01. Finally, the overall status of implementation of environment safeguards under the project is satisfactory.

41

Appendix: 01 1.1 CEA approval for B295 road.

42

1.2 CEA Approval for B389 road

43

1.3 CEA approval for B084

44

1.4. CEA approval for A004 road

45

1.5 CE Approval for B157 road

46

Appendix 02 The Summary of tested parameters of CP 01

Table 2.1. Water Quality results

Date of Oil and Road EC DO TSS BOD Chloride Sulphate Sample location Sampling grease E.Coli Section μs/cm mg/l mg/l mg/l mg/l mg/L pH mg/l Baseline(6th October 2015) Bolgoda Ela B 295 7.30 309 3.42 40 03 ND ND 34 19 upstream Irrigation canal B 389 7.47 366 5.07 75 04 ND ND 31 20 upstream Construction Stage-I (12th July 2016) Bolgoda Ela B 295 7.42 1109 5 14 3 ND 20 254 40 upstream Irrigation canal B 389 5.33 380 3 25 2 ND 110 32 17 upstream Construction Stage-II(21st September 2016 Bolgoda Ela B 295 6.93 366 5.8 55 2 ND 2.2*104 31 13 upstream Irrigation canal B 389 6.88 17680 6.9 15 3 ND 170 5706 750 upstream Surface water quality 6-9 - - - 05 0.1 Negative 1200 - standards

EC=Electrical conductivity, DO=Dissolved Oxygen, TSS=Total Suspended Solid, BOD3=Biological Oxygen Demand, ND=Not Detected

47

Table 2. 2 Baseline Noise levels

Base Line Construction Stage-I Construction Stage-II Road Measured locations RBL RBL Section ENL.dB(A) RBL dB(A) ENL.dB(A) ENL.dB(A) dB(A) dB(A) Day Night Day Night Day Night Day Night Kattiya Junction 74 73 64 63 71 NS 70 NS B 389 Gansabha Junction 75 73 69 68 74 NS 72 NS Front of Mahamaya School 74 73 64 63 80 NS 71 NS Kospalana Junction 61 60 56 53 72 NS 73 NS B 295 Suwarapola Junction 67 67 60 59 71 NS 72 NS Indra Treaders, Piliyandala 78 72 69 63 76 NS 72 NS

ENL=Existing Noise levels(L Aeq)-dB-(A), RBL-Rating Back Ground Noise level(L A90-15min) NS=Not Sampled

Standard Maximum Permissible Noise Levels at Boundaries in LAeq'T. LAeq', T Areas Day time Night time 55 Low Noise 45

Medium Noise 63* 50

High Noise 70 60

Silent Zone 50 45

* Provided that the noise level should not exceed 60 dB (A) inside existing houses, during day time. LAeq', T=the equivalent continuous, A- weighted sound pressure determined over a time interval T(in dB) The project area falls into the medium noise level zone

48

Table 2.3 Baseline vibration levels

Road section Measured locations A(ROW) B(ROW=10m) C(ROW+20m) Near Sri Wijerama Temple 0.572 0.199 0.371 Suwarapola Bodhi 0.265 0.092 0.142 B 295 Near Church 0.209 0.145 0.135 Near Bauddaloka Mawatha 0.157 0.140 0.134 Near School lane 0.207 0.101 0.096 Near Mirihana Junction 0.32 0.14 0.095 Subadrarama Temple 0.26 0.09 0.075 Court complex, B 389 0.16 0.085 0.085 Gangodawila Mahamaya Girls College 0.365 0.105 0.08 Walauwatta Junction 0.09 0.072 0.072 Maximum Peak Value in Velocity mode (mm/sec) day time-one hour measurement average, Standreds-02mm/sec(type 03)

49

Table 2.4 Baseline air quality results

Wind Road Mesured So2(8hr) NO2(8hr) CO(1hr) O3 (1hr) TSPM TSPM 8hr Wind Speed Section Locations (ug/m3) (ug/m3) (ppm) (ppb) (ug/m3) 8hr (night) Direction (ms-1) Indra traders, 52.0 21.0 1.8 0.01 319 48 1-2 NE Piliyandala B 295 Suwarapola 30.4 12.6 1.4 0.02 236 38 1-3 NE Kospalana 30.3 8.4 1.0 0.01 455 57 2 N Junction Gansaba 38.8 21.4 4.5 0.01 278 151 2 E Junction Kattiya B 389 41.0 11.8 0.8 0.01 165 91.4 2 NE Junction Mirihana 44.7 6.8 0.9 0.01 158 111 2 NE Junction Maximum Permissible 120 150 26 100 350 Level

50

Appendix 2(A) The Summary of tested parameters of CP 02

Table 2.5 Water Quality results

BoD5 Oil and Road Temperature TSS Sample location Date of Sampling pH (mg/l) grease E.Coli Section (0C) mg/l 100ml mg/l Pinwala Ela, Pokunuwita at 28th December 03 7.20 30 44 ND ND 28+000Km RHS 2016 Maha Oya upstream at 02 28th December Gonapala Junction at 23+280 7.76 29 08 ND ND 2016 km RHS Maha Oya upstream at 02 B 084 28th December Gonapala Junction at 22+760 6.80 28 10 ND 140 2016 km LHS Kimbulkatuwa Ela upstream 28th December 05 6.60 30 20 ND 92 at18+720 km LHS 2016 Maha Oya upstream at 16+320 28th December 04 6.60 29 07 ND 220 Km LHS 2016 Well at Mr. Jayakody(near 28th December 02 A004 6.20 27 - ND 550 Army Camp in Homagama) 2016 Surface Water Quality Standard 6-9 - - 05 Negative Negative

ND=Not detected

Note: For all samples, pH is within standard, while ground water sample does not fall within standard. All six samples ‘ BoD5 levels are within standard

51

Table 2. 6 Baseline Noise levels (measured on 08th December 2016)

Base Line Road Section Measured locations ENL.dB(A) RBL dB(A) Day Day Polgasowita at 17+100 RHS 72 60 B084 Kahathuduwa interchange at 18+540 RHS 73 67 Gonapola Junction at 23+160 km RHS 69 59 Pokunuwita Junction at 28+140km LHS 68 59 in front of Anula School LHS 74 67 A004 Homagama in front of Army Camp 68 63 Homagama in front of Army Camp’s Temple 74 64 Concrete/crusher plant at Kumbuka at 26+320 RHS 67 54 Plant Sites Asphalt /crusher Plant at Olaboduwa 21+850km 58 56

ENL=Existing Noise levels(L Aeq)-dB-(A), RBL-Rating Back Ground Noise level(L A90-15min)

Standard Maximum Permissible Noise Levels at Boundaries in LAeq'T. LAeq', T Areas Day time Night time Low Noise 55 45 Medium Noise 63* 50 High Noise 70 60 Silent Zone 50 45 * Provided that the noise level should not exceed 60 dB (A) inside existing houses, during day time. LAeq', T=the equivalent continuous, A- weighted sound pressure determined over a time interval T(in dB) The project area falls into the medium noise level zone

Note: Most of the locations’ day time background noise level is higher than the permissible level of the area.

52

Table 2.7 Baseline vibration levels measured on 08th December 2016

Road Category of Vibration Level Frequency Predominant Measured locations section structure PPV(mm/Sec. range(Hz) frequency) Dharamasena Artigala Girl’s school at Type 3 0.12-0.22 10-50 10.5-11.0 14+130 RHS, Kesbewa District Hospital at 17+920 Km RHS, Type 3 0.09-0.16 10-50 13.0 Polgasowita Primary School at 18+940 Km LHS Type 3 0.14-0.30 10-50 10.0-12.5 B084 Police Station at 19+080Km RHS, Type 3 0.22-0.30 10 8.5-11.75 Polgasowita Primary School at 26+180 km LHS, Type 3 0.23-0.41 10 60.5-61.5 Kumbuka Prashanthi Reception hall at 26+320Km Type 3 0.09-0.15 10 25.5-30.0 LHS, Kumbuka Kumara Udayam Tamil School at 0+160 Type 3 0.10-0.16 10 10.75-13.0 LHS, Kirulapona Public Library at 0+800km RHS, Type 3 0.07-0.11 10 13.0-14.5 A004 Kirulapona Army Camp Entrance at 16+280 RHS, Type 3 0.20-0.43 10 18.5-20.0 Homagama Army Camp’s temple , Homagama Type 3 0.09-031 10 12.0-15.5

**Maximum Peak Value in Velocity mode (mm/sec) day time-one hour measurement average, Standreds-02mm/sec(type 03)

**According to the measured vibration levels, maximum permissible levels (2.0 or 4.0mm/sec) of interim vibration standards have not been exceeded with the vehicle movements of this two road section

53

Table 2.8 Baseline air quality results

Road TSPM(µg/m3) 3hour Mesured Locations Sampling Date Section average) Polgasowita at 17+100 RHS 16/12/2016 309 Kahathuduwa interchange at 16/12/2016 217 B 084 18+540 RHS Gonapola Junction at 23+160 km 16/12/2016 302 RHS Pokunuwita Junction at 16/12/2016 259 28+140km LHS Nugegoda in front of Anula 16/12/2016 254 School LHS A004 Homagama in front of Army 16/12/2016 260 Camp Concrete/crusher plant at 15/12/2016 251 Plant Kumbuka at 26+320 RHS Sites Asphalt /crusher Plant at 15/12/2016 234 Olaboduwa 21+850km

Note: As per the results, all eight locations of B084, A004 and plant sites, baseline level of total suspended particulate matter(TSPM) for three hour average is lower than the permissible level of 450µg/m3.

54

Appendix 2(b) The Summary of tested parameters of CP 03

Table 2.9 Water Quality results

Oil and Road Date of EC Temperature TSS BOD Sample location pH grease E.Coli Section Sampling μs/cm (0C) mg/l mg/l mg/l Baseline sampling Kadiththamankada Ela upstream(34/2 05/12/2016 7.30 45 28.6 11 02 ND 2400 Culvert-33+610 km) Badugandola Ela B 157 upstream, 05/12/2016 7.39 42 28.1 02 ND ND 1700 (34+998Km LHS Welipenna Ela Upstream(40/1 05/12/2016 6.59 60 28.1 08 02 ND 790 culvert, 39+172kmLHS Surface Water Quality 6-9 - - - 05 0.1 1 Standard

Note: The pH ,BOD & oil/greese content at its standard level in all locations

55

Table 2.10 Baseline Noise levels(measured on 21st November 2016)

Road Base Line Section Measured locations ENL.dB(A) RBL dB(A) Day Night Night Day Mathugama Town at 31+500 66 66 59 56 B 157 Horawala Junction at 36+500km 70 68 59 58 Welipenna Interchange at 68 69 50 51 42+300km

ENL=Existing Noise levels(L Aeq)-dB-(A), RBL-Rating Back Ground Noise level(L A90-15min)

Standard Maximum Permissible Noise Levels at Boundaries in LAeq'T. LAeq', T Areas Day time Night time Low Noise 55 45 Medium Noise 63* 50 High Noise 70 60 Silent Zone 50 45 * Provided that the noise level should not exceed 60 dB (A) inside existing houses, during day time. LAeq', T=the equivalent continuous, A- weighted sound pressure determined over a time interval T(in dB) The project area falls into the medium noise level zone

56

Table 2.11 Baseline vibration levels

Road Category of Vibration Level Frequency Predominant Mesured locations section structure PPV(mm/Sec. range(Hz) frequency) Divisional Secretariate, Type 3 0.190-0.232 10-50 10.63-12.13 Mathugama at 32+120km Primary school-Ovitigala at Type 3 0.082-0.156 10 12.13-18.38 34+040 km Child Friendly School in B 197 Type 3 0.129-0.362 10 11.5-13.25 Badugama at 35+985km Rahumania School in Type 3 0.407-0.863 10 17.0-19.5 Welipenna at 39+320km Primary School in Type 3 0.299-0322 10 49.25-51.75 Lewwanduwa at 40+840km

**Maximum Peak Value in Velocity mode (mm/sec) day time-one hour measurement average, Standreds-02mm/sec(type 03)

**According to the measured vibration levels, maximum permissible levels (2.0 or 4.0mm/sec) of interim vibration standards have not been exceeded with the vehicle movements of this road section

57

Table 2.12 Baseline air quality results

Road TSPM(µg/m3) 3hour Mesured Locations Sampling Date Section average) Mathugama Town at 32+100 In 05/12/2016 269 Front of DS office Horawala Junction B 157 05/12/2016 105 At 36+763 km RHS Welipenna Interchange at 05/12/2016 41 42+372km

Note: Maximum permissible level of total suspended particulate matter(TSPM) for three hour average is 450µg/m3. As per the measured results, all three locations of B157(East) road section, TSPM (03hr)average is lower than the permissible level of 450µg/m3.

58

Appendix: 03 Table 3.1 Observed Environmental Issues of the Contract Package of CP01

Timing Description of Cause Issue Required Action Responsibility (Target Resolution and

Dates) Timing (Actual) Quarry- The quarry is a commercial base one owned by out-side party Neboda Crusher Supplying of materials have been stopped November 2016 Plant Asphalt 1.Tar barrels at 1. Advised to construct a Plant Manager Within 1Construting of Plant open area roof for the tar storage & Head Office one roof is being area. management month progressed but it During was a sluggish Supplying of Septemb progress. However materials have er 2016 the roof has been been stopped completed within December 2016 the last quarter of 2016.

Concrete Supplying of materials have been stopped December 2016 Batch Mixing Plant Borrow Not operated sites 1.Advised to regular Yard Manager, Within 1.regullar maintains SO & EO one maintaining 2. Advise to handing over week observed the collected solid waste from 5th 2.Solid waste Contractor to UC, Kesbewa to 11th of management 's Yard 3. Advise to handed over Septemb activities are ok to owner after proper er 2016 3. The contractor is cleaning of the land still operating the yard 1.Labour 1. the camp is 1. Dust bins, hygiene Plant Manager 1. The said facilities Camps at maintained facilities, mosquito nets & EO are provided Plant site, well were provided satisfactorily Naboda 2.Labour 1.Sanitary 1.Advised to improve all Project Within 3 1. The existing bad Camps at problems the conditions Manager, SO & weeks condition was B389/B28 2.Poor labour EO From uplifted. 5 facilities 29th (two August labour to 18th camps are Septemb under er 2016 operation for both roads) Stock piles Not operated

59

Disposal Condition is Advised to implement of Project Once a Regular Yards good regular maintaining such Manager , EO week maintenance as keep the ground & SO observed. levelling and avoid water stagnation Structure 1. PPEs usage 1. Advised to ensure of Project Daily 1PPEs usage by Constructi by workers is the PPEs usage by all Manager , EO rooting workers should be on poor. workers while working & SO further improved and upgrade the site on or before 30th 2. Traffic safety and traffic Site engineers, September 2016, management controlling activities supervisors of while traffic and site safety especially at Kattiya each section management at the should be Junction of B389. and working Kattiya Junction of improved sites B389 was improved.

EO=Environmental officer, SO Safety Officer

Table 3.2 Observed Environmental Issues of the Contract Package of CP02 Kesbewa-Pokunuwita(B084) and Hoamagama-Godagama(A004)

Timing Description of Cause Issue Required Action Responsibility (Target Resolution and

Dates) Timing (Actual) Quarry- Millaniya Provide relevant PPE for No proper PPE Within all workers who engage Plant Manager usage week with quarry activities. Crusher Plant-Millaniya 1.Dust emission Install the water sprinkles Plant Manager Within The water sprinkles 2.Water and their regular one had been installed stagnation maintenance. week and dust emission Regular levelling of the 20th also controlled well crusher area April Regular levelling is 2017 being progressed Crusher Plant-Pokunuwita 1.Water Advised to regular Plant Manager Within Area has been stagnation levelling of the crusher one levelled and avoid area week water stagnation Before 5th April 2017 Asphalt Plant-Homagama 1.Plant area The plan site is well managed well managed

Concrete Batch Mixing Plant-Pokunuwita 1.Water Advised to avoid water Plant manager Within Area has been stagnation is stagnation within the area one levelled and avoid observed week water stagnation

60

Before 5th April 2017 Borrow Not operated sites 1.Water 1.Advised to regular Yard Manager, Within 1.regullar stagnation was maintains SO & EO one maintaining Contractor observed in the week observed 's Yard abandoned 5th April materials and 2017 vehicle parts Stock piles No proper 1.Advised to erect Project Within Barricades and barricades and barricades and Manager, SO two demarcation demarcations demarcating items days applied applied 5th April 2017 Disposal Yards-Temporary disposal sites Condition is Advised to implement of Project Once a Regular good regular maintaining such Manager , EO week maintenance as keep the ground & SO 5th April observed. levelling and avoid water 2017 stagnation Structure 1.PPEs usage by 1. Advised to ensure of Project Daily 1. PPEs usage by Constructi sub-contract the PPEs usage by all Manager , EO rooting workers should be on workers are workers while working. & SO further improved poor. (The designated PPEs on or before 30th 2. Inadequate of should be provided to Site engineers, April 2017. the sign boards workers such as ear plugs, supervisors of 2.The sign board along the road. mask and gum boots each section installation, 3. Demarcation while activities concreting, and working maintenance and of the machine operating and sites site demarcating construction compaction going on). are regularly sites specially 2 & 3.. Advised to install observed culvert adequate sign boards 3. the Site Engineers locations along the construction are advised to should be sites and culvert locations install sign bords improved according to approved along the danger further. Safety Manual. locations 4. Danger 4. Advised to erect the locations of the danger warning sites road should be along the road where identified and necessary. install the warning signs(bent locations, road narrows etc.)

61

Table 3.3 Observed Environmental Issues of the Contract Package of CP03 Mathugama-Southern Expressway (B157)

Timing Description of Cause Issue Required Action Responsibility (Target Resolution and

Dates) Timing (Actual)

Quarry Quarries are managed by commercial base Crusher Plant-Daniston estate, Commercial base 1.Oil leakage at 1.Advised to avoid oil Plant Manager Within 1. Attended to backyard of the leakage along the pump two rectify said issue office premises area and put a collecting weeks with cleaning the 2.Dust emission span to collect 26th area. was observed overflowing oil April 2.The water 2.Install the water 2017 sprinkles had been sprinkles and regular installed and dust maintenance emission also controlled well Asphalt 1.used 1. Advised to dispose Plant Manager Within 1. Properly Plant polythine properly. & Head Office one disposed covers dumped 2.Advised to ovoid oil management month 2. & 3.Taken steps at the open area overflowing when oil 29th to avoid oil & tar 2.Oil spill-out at pumping, and construct March spilling out. pump area the concreted trays under 2017 3.Bitumen the pump area leakage at the 3. Advised to use trays bitumen while bitumen pumping pumping area and ground should be concreted to avoid tar mix(infiltration) with soil. Concrete 1.Wash water Advised to reuse the Batching Plant Immedi A tank is Batch of truck dispose water and not to Manager ate constructed to re- Mixing mixture should dump into open use the waste water Plant(Dry) be disposed in of truck mixtures proper way 1.Updating of 1.The contractor is Project Immedi 1.The contractor licences advised to submit timely Manager ate has promised to Borrow approvals and updated licenses and submit these detail sites material approvals as well as without quantity obtained quantities delay 1. Maintaining 1.Advised to regular Yard Manager, Within 1.Regular of yard is at maintains SO & EO one maintaining Contractor good level 2. Advise to handing over week observed 's Yard the collected solid waste 22nd 2.Solid waste to UC, Mathugama March management 2017 activities are ok 1.labour camp 1. Advised to maintaining Plant Manager Within 1. Regular 1.Labour and kitchen 2.Advise to obtain the & EO two maintaining Camps at maintainace Labour department weeks observed main yard area at good approval 22nd 2.Labur dept. level March approval pending

62

2.No Labour 2017 department’s approval Stock piles 1.Three lands 1.advised to obtain Project Daily 1. Regular are operated for consent letters from manager and rooting maintenance store ABC, and owaners EO observed. soil. 2.Avoid soil erosion and dust formation from stock piles Disposal 1.More than 20 1.Advised to implement of Project Once a 1. Regular Yards lands have been regular maintaining such Manager , EO week maintenance selected as as keep the ground & SO observed. disposal lands levelling and avoid water stagnation in the lands Structure 1. PPEs usage 1. Advised to ensure of Project Daily 1PPEs usage by Constructi by workers is at the PPEs usage by all Manager , EO rooting workers should be on poor level, workers including sub & SO further improved especially sub- contractors. on or before 30th contractors. 2. Advised to increase the Site engineers, April 2017. 2. Traffic awareness activities (tool supervisors of 2. Traffic management box meeting etc) on safety each section controlling should improve and traffic team. and working activities should be further. Traffic 3. The sites should be free sites further improved. controllers with disposed soil and 3.Constrution sites haven’t good scattered construction neatness should be awareness materials improved further about their work. 3. Neatness around the working sites, especially at culverts area.

63

Appendix: 04(a) Status of EMP* Compliance (Road B 295 & B 389) (*this EMP is included in the bidding document) Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied 1. (a) Selection Selection of lands in accordance with local Site visits and complied The contractor has Disposal lands have of lands for laws, regulations and in close consultation observations obtained the approvals for been returned to temporally use with Weekly checklists all temporary used lands owners with proper LAs Public complains and has returned the lands levelling with proper levelling. All temporary facilities should be established No complain received. away from the environmental and public sensitive areas

All relevant legal compliances should be Do Complied Debris disposal activities Completed obtained prior to the establishment of have been managed successfully temporary facilities without problems. 1.(b) Solid waste Minimize health hazards and environmental Excavated materials were disposal and pollution based on CEA guidelines. removed into temporary sanitation Keep the all site free with environmental disposal lands along the hazards road and finally disposed Selection of disposal site away from public into permanent disposal and environment sensitive areas lands (mainly at Re-use of debris and residual spoil materials Suwarapola disposal wherever possible under instruction of land). Engineers & CSC. Provision of proper solid waste disposal, PHI has periodically sanitation and sewerage facilities to all sites visited to observe the Dumping of garbage in a hygienic manner waste generated areas under the inspection of PHI in the area (labour camps and yards) Minimize/avoid stagnation of water around of the contractor. worker based camps

64

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied Selection of local un-skilled and skilled The all skilled and workers for the proposed construction unskilled workers have activities been selected to sites within the area as well as out sides. While female labour has paid same wages for their works. 2. Removal of Advance notice to the public about the time Number of complain by Complied Water line, CEB & Shifting of utilities public utilities and the duration of the utility disruption public & the contractor Telecom Poles removing has been completed. Recruitment of well trained and experienced Monthly field visits activities are fully machinery operators, technical officers & Number of remaining completed at both road labours Poles of CEB and Telecom sections of B 389 and B Proper coordination and consent from service Total remaining length of 295. providers for the removal of utilities and re- water pipe laying Considering about the establishment received complains, 3 complaints were from B 295 and 15) complains were received from B 389 Road. The most of complaints about underground telecom cable damaged and these are forwarded to insurance company to process compensation. 3. Extraction, Consideration of environmental requirements Site visits and Complied Bitumen Barrels were The raised problems transportation and guide lines issued by the CEA, GSMB and observations stored at open areas since were solved and storage of LAs Weekly checklists the project starting time satisfactorily. construction If new material extraction sites need to be Public complains (Instructions were issued materials located, they should exclude places which are to contractor on 28th close to the public and environment sensitive October 2015). After

65

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied areas advising to management Planning of construction activity to ensure of plant, a new roof was that haulage of materials does not take place constructed and the during night barrels have been kept Storage of sand, rubble, mettle bitumen under the roof. cement in covered areas to ensure protection A drainage path has been from dust, emissions constructed and avoid Storage of cement, bitumen, oil and other water stagnation inside chemicals on an impervious surface above the plant area ground level and should be enclosed ensuring that no storm water flows in to the structure. Provision of adequate ventilation should be kept to avoid accumulation of fumes and offensive odour to storage yards. All legal compliances for extraction, Do Do All legal documents have Completed transportation and storage of construction been obtained by the materials should be obtained prior to the contractor for material operation extraction as well as All drivers should follow the speed limits on transportations roads and specific condition given by LAs or relevant authorities in given time and should have license for the category of vehicles they drive Construction materials should not exceed the carrying capacity of the trucks as well as roads when transporting provision should be made for repair and restoration, If public roads get damaged Transport loading and unloading of materials should not cause nuisance to the public Restoration of the material extraction sites

66

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied once after borrowing. 4. Effect on local provision made for repair and restoration, If Public complains Complied The contractor has Completed road network project roads(B295 & B 389) get damaged Site visits and repaired the project road observations when it damaged. Weekly checklists No complain was received. A provision is available to do this maintenance Obtain approvals from LAs to use local road Do Do Approvals (Trade licences) completed network prior construction have been obtained from Construction materials should not exceed the the respective Local carrying capacity of the local road network. Authorities to transport provision should be made for repair and materials. restoration, If public roads get damaged 5.(a) Restoration of water bodies to its original Site visits and Complied The contractor has Completed. Under Effect on status once after construction observations attended to provide the project, the existing canals, Prevent storage of construction materials and Weekly checklists temporary/permanent existing poor quality water disposal of debris around cross drainages. Water quality test drainage facilities, drainages and side restoration areas Provision of temporally drainage facilities Public complains cleaning of existing drainages in entire and drainage until requires line or earth drains are drainages length of the road paths provided are improved. Replacement of structurally damaged So far, 10 complain for B drainage structures 285 and 03 complain for B389 were received regarding the drainage problem. 04 complain of B285 road will be rectified by Kesbewa MC while others are solved. Obtaining of proper approvals from relevant Do Complied The contractor had been Completed.

67

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied authorities prior to diversion, close or instructed to obtain 5.(b) blocking of water sources as well as material relevant permission. Effect on water storage resources Storage of toxic and hazardous construction Do Complied The contractor had been Do materials away from water bodies advised to store toxic or Avoid excavation of beds of any irrigation hazardous away from systems or other water bodies water sources, avoid Implement additional safety precautions to excavations close to reduce the water pollution and degradation of vulnerable water sources, water resources due to work and avoid water pollution when his work progressing. Cleaning of upstream and lead-away channels Do Do The facilities for smooth Do of cross drainages to maintain a smooth water water flow and preventing flow. siltation were provided Introduction of catch pits wherever possible during the construction to prevent silting of water bodies activities were done Awareness of employees on water Do Do Awareness of water Do conservation, pollution and minimization of conservation, prevention water usage of pollution etc were Prevent entering waste- water directly in to included under the worker water bodies. awareness programs Maintaining vehicles and equipment in good condition, to prevent leakage of oil or fuel Prevention of disrupting community water sources Restore the water resources due to any pollution or negligence done by contractor 6. Soil erosion Placement of erosion control measures to Do Do The contractor was Completed.

68

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied sedimentation erodible areas. advised to implement his and siltation Covering of temporary soil dumps with construction work during thick tarpaulin sheets until remove from the dry period along the water site ways. Eg: B295 near the Undertake construction activities in erodible Kospalana Bridge area. sections during dry season. Limitation of steep cuts and the reduction of slop of cuts Treatment of clearing and filling areas against flow acceleration Re use of top soil generated from construction Do Complied sites for turfing and tree planting activities. 7. Effect on flora, Compensative tree planting activity with Field visits and Complied Compensative tree Three tree planting fauna and their participation of project effected people and observations planting programs were programs have been habitats adjoining communities. Do not promote or Weekly checklists conducted. Due to absence implemented. introduction of any alien invasive plants to re- of space along the ROW, 1.Police ground and planting activity and use only native and vicinity areas were temple premises in endemic species in the area selected to replanting. B389 2.Ananda Samarakoon School premises 3.Karadiyana waste dumping land(mangrove species) Awareness of workforce regarding important Do Complied Awareness meeting were The contractor has of fauna, flora and their habitats conducted. The resource conducted the Display the relevant warning signs along the persons, who represented awareness programs environmentally sensitive areas from CEA have as periodical Do not use any resources that adjoining into participated those intervals the wildlife (specially demarcated to wildlife) activities.

69

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied such as water, feeding grounds, breeding areas and habitats. Providing facilities to wild-life in the area during the environmental hazardous situation Removal of road side trees adhering to the Do Compiled Removal of road side trees Completed CEA guidelines and recommendation. are completed Decision on tree removal based on Detailed Engineering Design Marking road side trees subjected to removal and preparation of inventory prior to start clearing. Valuable timber should be properly stacked and handed over to the DoF or rightful owners.

8. Biodiversity Rehabilitation of degraded eco-systems (such Field visits and Complied It was proposed to Not completed conservation as wet land, forest ect.) adjoining into the observations conduct some and sustainable project area or project effected area with Weekly checklists rehabilitation activities natural resource approval of Engineer along the Bolgoda lake in management the B 285 road. But contractor couldn’t conduct these activities due to various reasons

70

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied Awareness of all stakeholders regarding Do Complied Some of the activities were Do environmental conservation implemented parallel with Displaying signs and warning boards about the tree planting the importance of the existing fauna and flora campaign. Eg: During the of the area tree planting program was Avoid clearing of natural habitats and conduting at the school, replacement of natural vegetation for any the awareness program construction purpose except the proposed was also conducting to road construction. children. Use of natural resources in sustainable manner Rehabilitation of degraded eco-systems (such as wet land, forest ect.) adjoining into the project area or project effected area Rehabilitation (with approved and proper rehabilitation plan) of all resources extract areas and temporary used lands

9. Disruption of Provide an advance notice to local Public complains Complied Inadequate traffic Monthly payments traffic and communities about the schedule of Weekly checklists controlling and were reduced due to public construction activities Site visits and inconvenience to public poor performance of inconvenience Installation of traffic warning signs, observations had been observed along traffic safety temporary traffic lights or flagman at the the roads during the site controls. construction sites observations. Implementation of traffic management plans in close coordination with local police and Public complains on house public access and business access Schedule movement of large trucks and plant had been solved. in off-peak traffic times.

Provision of safe passage/ alternative routes Do Do Provision was provided to Completed.

71

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied to the vehicles and passengers make alternative passage or bypass making where necessary 10. Personal Proper and regular awareness on Site observation Complied Three programs on Scheduled all health and health(sexually transmitted, Non-transmitted Weekly checklists HIV/AIDS prevention had programs were safety and vector born diseases ) and hygiene Public been conducted. completed matters during the working period complain/worker’s complains

Provision of personal protective equipments Do Complied PPE usage was observed Reductions of (PPEs) and clothes to workers, based on their as weak among the monthly payments duty workers. were carried out according to the monthly observations made by RDA and the consultant.

Establishment of road engineering aspects Do Do Temporary signs have Completed and sign boards to reduce accidents been fixed during the construction period while permanent signs were erected/fixed after the road work finished Proper briefing and training of workers on Do Do Tool box meetings and Completed safety precautions, and their responsibilities awareness meetings were Use of licensed and well trained operators for conducted. handling of machinery, equipment and labour accommodations material processing plants were provided Provision of first aid facilities and emergency Explosive materials were

72

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied transport to the nearest hospital handled under Arranging regular safety checks of workers, supervision of nearest vehicles and plants Police of the plant site Provide proper labour facilities in labour (quarry) camps, yards and accommodations for full fill their health and safety requirements. Storage of explosive materials in a secure location in a protective way 11. Safety of Enforcement of speed limits, traffic rules and Site observation Complied The signs boards had been Completed road users regulations Weekly checklists installed throughout the Installation of the warning signs, road Public complain road during the markings and relevant road furniture construction period and Provision of bus bays, pedestrian crossings at those were maintained the appropriate locations regular manner.

12. Impact from Placement of crushers and hot mixed plants Site observation Complied - - dust, noise and away from public and environmental Weekly checklists vibration sensitive areas Air, Noise and Vibration Placement of exhaust silencers and noise test reduction devices to the road side crushers, Public complain construction vehicles and hot mixed plants Periodically checking of air, water, noise and Do Being Baseline /construction Monitoring vibration of the project area complied stage monitoring activities activities for were carried out operation stage to be implemented immediate after the handing over the road. Storage and transport of construction Do Complied The contractor has Actions have been materials with proper covering, provision of followed the guidelines followed

73

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied dust barriers, spraying of water and control of that given to control the throughout the vehicular speed to minimize dust emission storage and transportation project period of materials. Implementation of National Emission Do Complied CEA approvals have been completed Standards and Noise Control Regulations of obtained. CEA for project activities Implementing an effective work plan to reduce dust, noise and vibration due to construction work Regular maintenance of machinery, equipment and vehicles in a good condition Prevent bad odour and offensive smell emanating from chemicals, material processing or other construction activities Arrangement of construction activities closer to public sensitive locations coordination with the relevant authorities Operation stage 13. Air quality It is expected to reduce existing dust after Site observation Being The contractor has taken Immediate after the surfacing of the roads. Proper alignment and Weekly checklists Complied to step to monitor the air road handing over surfacing of the road will help to reduce the Public complain quality. The quotation are to the Employer vehicular emissions. Air quality test invited and finalized Checking of differentiation of environmental parameters 14. Drainage Regular maintenance of drainage system as Site observation Being Performance based After the road Congestions and well as road surface Weekly checklists complied to maintainace work will be handing over to the maintainace of Regular maintenance of road furniture that Public complain implemented. Employer road already installed and providing an adequate Air quality test requirements Avoid dumping garbage and other spoil

74

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied material

GSMB=Geological Survey & Mining Bureau, CEB=Ceylon Electricity Board, LAs=Local Authorities, CSC=Construction supervision consultant, CEA=Central environmental Authority,

75

Appendix: 04(b) Status of EMP* Compliance (Kesbewa-Pokunuwita (B084) Road) (*this EMP is included in the bidding document)

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied A. Pre construction and Construction stage

1. Removal As part of the pre-construction Site observation Being Water lines, CEB & Utility shifting of public activities, initially consultation and consent Weekly checklists complied to Telecom Poles shifting activities are utilities should be taken from relevant service Public complains activities are being monitored by providers (CEB / NWSDB / SLT) if sections progressed. monthly progress of utility lines needs to be shifted due meetings. to design requirements or shift in alignment During the reporting period 1% of CEB poles The relocating Obtain permission from DoI for any and 17% Telecom poles activities should be proposed construction works on irrigation have been shifted. expedite canals Considering about the Use of well trained and experienced received 31 complaints, 15 machinery operators to reduce accidental complaints are solved, 3 damage to the public utilities are progressing while 13 complaints are pending Advance notice to be served to the affected about decisions. public about the time and the duration of the utility disruption

Substitute sources of water and other utilities during the disruption period, and restoration of the public utilities as soon as possible. 2. Removal Mark all road side trees subjected to Site observation Being Clearing activities are at of road side potential felling and preparation of inventory Weekly checklists complied to near completion along the prior to start clearing.

76

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied trees handed over section Decision on tree removal should be based on (Sec.1). detailed engineering design.

Maximum effort towards avoiding removal of religious, cultural and aesthetic important trees through joint field verifications and decision taking.

Obtain permission in writing from DoF regarding removal of trees and seek compensatory modalities and plan for afforestation programmes.

Compensatory plantation program at twice the number to be felled and its cost estimation in consultation with DoF.

To avoid further tree losses, the contractor should ensure that the temporary use of land for construction related activities will be established without any additional tree cutting. 3. Temporary Construction facilities should be Site observation Being The contractor is using Monthly site visits use of lands established at least 500 m away from Weekly checklists complied to temporary stock pile yard water bodies, natural flow paths, important ecological habitats and residential at 16+500km and disposal areas. land at 17+500km. The contractor’s machinery Selection of site for these facilities by yard is also situated at adhering to stipulated local laws and 21+700km as a temporary regulations and in close consultation with

77

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied LAs. basis. The contractor has obtained the consent Pay compensation / rent for using the letters from owners and site and get an official permit from the has taken necessary agencies if any public utilities will be used actions regarding the for its facilities. environmental protection.

In establishing these facilities, the contractor should minimize removal of trees and other green cover vegetation to the extent possible. 4.Land Compensation prior to acquisition of Work done records To be Land acquisition activities acquisition property as per the RAP policy and Site observations complied have almost been finished and restoration of livelihood. Public complain in section 01, 03 and 04, Resettlement while some activities are being progressed in other sections. 5. Solid waste Designing and Provision of solid waste Site observation To be Waste collecting facilities disposal and collection, storage, disposal, sanitation and Weekly checklists complied have been sanitation sewage facilities at all sites for the Public complains provided(garbage bins) onstruction/labor camps, and other construction sites. The contractor has built linkage between Handling and management of waste Municipal councils in the generated from the construction/labor area to give collected solid camps without contaminating the waste from their office, surrounding environment and not posing yard and the labour camps any threat to the public/communities living in regular basis. in and around the sites.

Provide adequate facilities to manage its wastes in consultation with CEA and PHI

78

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied of the area.

Proper drainage facilities should be designed and developed in the workers base camp sites to minimize stagnation of wastewater.

Solid waste should not be burnt but emphasis to be laid for their recycling, composting and sanitary land filling. Adequate supply of hygienic water should be provided to the urinals, toilets and wash rooms of the worker camps.

Garbage bins should be provided to all workers’ camps and construction sites, and needs regular clearing and appropriate disposal and if needed to be treated with disinfectants. 6. Top soil The fertile top soil to a depth of 20 - Site visits & observations Being Approved disposal sites Sites visit/checklist Conservation 30 cm should scoop out and preserved in Weekly checklist complied have been operated. updating is being and Disposal a manner so that the stack is not washed Public complains conducted regular of debris away during rainy days. The top soil The temporary disposal basis. can be utilized in the future for turfing lands also being operated. purpose, enhancing soil quality of degraded land patches, plantation purposes etc. Road side excavated materials are stock piled All debris and residual spoil materials by contractor for future including any left out earthen material usage (at 16+500km RHS). should be disposed off only at locations approved by the relevant LAs.

Spoil materials (soil, sand, rock etc,)

79

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied generated during the construction activities should be utilised wherever found suitable for activities like site levelling, back- filling etc with prior approval of CSC.

Suitable dumping grounds/ land fill sites should be identified for the disposal of surplus excavated/surplus/discarded/demolished materials of existing structures.

The debris and spoil should be disposed in such a manner that; • Does not block the waterways and drainage paths • The disposed materials should not be washed away by runoff • Debris should not be disposed into any agriculture lands, marshlands, down slopes or any environmental sensitive areas • Avoid/ Minimize annoyance to general public and road users. 7. Extraction of Suitable quarry sites and borrow areas Site visits & observations Being The contractor has Sites visit/checklist construction s h o u l d be identified at the initial stage Weekly checklist complied obtained the materials updating is being materials of the project. Public complains from approved sources conducted regular and submitted their basis. Utilizing the existing mines and quarry approvals to the client. sites available in the project influential areas, which are approved by GSMB or LAs, The periodic site visits operating with EPL and IML conduct to observe the site

80

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied hygiene matters as well as If new quarries and sand mines are to be house-keeping activities. opened, prior approval should be obtained from GSMB, CEA and LAs.

Project’s quarries should not be located in any environmentally sensitive areas, in vicinity to archeological and cultural sites, religious places, schools and settlements.

Quarries and borrow areas should meet aesthetic demands and have rehabilitation plans designed and implemented.

Use of alternative source for the river sand such as screened crusher fines or sea sand.

Restoration of the borrow pits by contractor or relevant authorities once after borrowing.

Use of insecticides/disinfectants in the camp sites/plant sites and waste collection areas to discourage Vector breeding. 8. Trucks carrying construction materials Site visits & observations Being Contractor use tar-poling Sites visits and Transportation should not be overloaded and covered with Weekly checklist complied covers to close the material checklist updating and storage tarpaulins to reduce fines getting airborne. Public complains when transporting while are being conducted of construction the vehicle conditions and regular basis. materials Avoid storage of construction materials loads are being observed beside the road, around water bodies, by client and consultant in residential or public sensitive locations. regular basis.

81

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied Materials loading and unloading should not cause nuisance to the people by way of noise, vibration and dust emission.

Sand, rubble, metal, bitumen, cement etc should be stored in designated areas to ensure optimum utilization preferably on a solid platform. Such materials should be handled in environment friendly and nuisance free manner. 9.Effect on Permit from LAs to use local roads prior to Site visits & observations Being The contractor is advised Consider about the local road using the roads for transportation of Weekly checklist complied to get permission from complains from the network construction materials, machinery and Public complains relevant authorities when public and line equipment etc. he using the other roads authorities/agenesis except the project road The contractor should- ensure that transportation of construction materials by The contractor has suppliers should not exceed the carrying obligated to repair the capacity of the local roads. roads while using them for their activities. Regular Maintenance of local roads and their restoration which are used for hauling activities for the construction related activities. 10. Soil Implement erosion control measures such as Site visits & observations Being The contractor is advised Regular site visits erosion and fiber mats, gabions walls, rip raps and deep- Weekly checklist complied to take relevant actions and checklist are surface runoff rooted grasses etc to erodible areas against the soil erosion being implemented and surface runoff their Seeding with a fast growing native species construction sites as well and seed mix immediately after fill as filling areas/materials placement to develop green cover to protect excavation areas.

82

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied the earth works.

Construction in erosion and flood- prone areas should be restricted to the dry season (excluding December – February)

Stabilization of embankment slopes and road cuts by re-vegetation and take up a turfing work as soon as possible before rains.

Treat clearing and filling areas against flow acceleration and construction work should be carefully designed to minimize obstruction or destruction to natural drainage. 11. Effect Contractor should avoid storage of Site visits & observations Being The contractor has taken Regular site visits on existing construction materials and disposal of Weekly checklist complied steps to avoid unnecessary and checklist drainage debris around irrigation canals, cross impact to existing pattern drainage and natural flow paths. drainage system, further he has found the approved Culverts and all other drainage paths have to stock piles away from be appropriately designed by allowing water paths as well as sheath flow and without any blockages. agrarian activities.

Provide temporary diverting drainage facilities to construction sites while repairing and replacement of obstructed drains and structurally damaged culverts/ bridges. 12. Protection of Avoid tapping water from sources in Site visits & observations Being The contractor has been Regular site visits

83

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied water resources residential areas being used by the local Weekly checklist complied advised to minimize any and checklist community. Public complains impact will course due to his activities. Contractor should not obstruct or prevent flowing of water when working closer to Stock piles are situated water bodies. away from water sources.

Construction works affecting the streams and The contractor obtain irrigation canals have to be undertaken water for his purposes during the dry season with prior permission mainly from main water from the concerned Department. supply(WSDB) and own dug wells in their Minimize excavation of beds of any streams, premises(at Main Yard). irrigation systems, and other water resources so that water flow in the beds is unaltered.

Use of silt traps and erosion control measures where the construction is carried out in close proximity to the water bodies to avoid entering of cement, sand and other particulate matters which cause turbidity and increase sedimentations.

Storage of construction materials which are toxic, hazardous and containing other fine particles would be sited at least 500 from water bodies to avoid its contamination to water resources. Trenches around the storage area to confine the flow outs . 13. Affect Approval from DoF should be Site visits & observations Being The all trees to be cut Site visits and on flora and obtained prior to start of project activities Weekly checklist complied within the ROW are progress meeting fauna clearly marked by Survey

84

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied towards felling of trees and planning prior to construction towards carrying out compensatory started. afforestation. The all possible trees will be protected within ROW

Contractor will prevent his work force and re-planting program from gathering fire wood from surrounding will be carried out. habitats, disturbing to the flora, fauna including hunting of animal and fishing in The contractor is maintaining a plant water bodies nursery in order to carry All construction materials extraction sites, out the tree planting material processing plants, storage yards period. and construction vehicle service stations will be located away from the water bodies, Provisions are provided to environmental sensitive locations conduct the Environmental awareness. Proper awareness programs to be conducted regarding conservation of flora, fauna including ground vegetation to all drivers, operators and other workers 14. Provide and publicize advance Site visits & observations Being The contractor has Monthly progress Disruption of notices to local communities about the Weekly checklist complied submitted traffic safety meetings and traffic schedule of construction activities. plan for the project. checklists

Installation of traffic waning signs, signaling Accordingly the contractor system, flagman at the construction sites. obligated to install relevant signs along the Provide safe and convenient passage to road vehicles, passengers and livestock from the

approaching roads. Smooth traffic flow is

compulsory to maintained

85

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied Traffic and safety management plan should by the contractor be implemented in close coordination with throughout the project local communities/authorities and police period department during the entire construction period.

Contractors to plan and implement diversion roads for sensitive locations with prior approval of the Supervision Consultant. 15. Air quality Contractors should place crushers Site visits & observations Being The periodical checking of Monthly progress and hot mix plants at least 500 m away Weekly checklist complied air quality has been meetings and from residential areas or other social carried out (under the checklists infrastructures (school, hospital/religious project’s EMP) and the places etc) contractor obligated with national emission Such establishments should strictly comply standard that stipulated to National Emission Standards for all when EPL issuance for construction vehicles, equipment and their plant operations material processing plants Dust controlling activities Dust extraction/suppression systems should such as sprinklers, dust be fitted to crusher units, construction barriers are installed in the vehicles and hot mix plants crusher units/hot mix plants (at Kumbuka 26+320RHS)

16. Noise Strictly implement noise control regulations Site visits & observations Being The periodical checking of Monthly progress and vibration for all construction vehicles and equipments. Weekly checklist complied noise and vibration levels meetings and have been carried out checklists Contractors should equip their heavy (under the project’s EMP) construction equipment with acoustic and the contractor

86

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied enclosures/ silencers to limit the obligated with national construction equipment not to generate emission standard that noise exceeding 75 db (compacters, loaders, stipulated when EPL vibrators, cranes, diesel generator sets) issuance for their plant operations/yard Limit working time for activities that operations and create noise only between 6.00 am to 6.00 machineries a pm except for construction site near schools, offices, religious places.

Contractors should schedule their activities at sensitive locations in consultation with the relevant authorities (school’s principals, high-priest etc.)

Regularly maintain all construction vehicles and machinery to meet the National Emission Standards. 17. Personal Organize awareness programs Site visits & observations Being The contractor is being Monthly progress safety and regarding personal safety of workers and Weekly checklist complied implemented tool box meetings and health general public during construction period. meeting/awareness checklists campaigns periodically. Attending to Establishment of safety provisions to awareness and tool reduce the likelihood of accidents by Safety provisions are box meetings placing warning signs, speed limit provided to caring out the markings, speed breakers and signals to PPEs and the Traffic safety particular locations. activities. The contractor has Providing appropriate PPEs such as submitted a schedule protective footwear, helmets, goggles, eye- about the HIV/AIDS shields and clothes to the workers awareness program that to

87

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied depending on their activities (Mixing asphalt, be conducted by him. blasting, handling equipments etc) and motivating the workforce for their usage.

Establishing first aid facilities and Ambulance facilities at active working sites to meet emergency situations.

Use experienced and well trained workers for the handling of machinery, equipment and material processing plants.

Contractor should implement STD/ HIV/AIDS awareness programs for general public in and around project implementation area and workers to reduce the risk of spreading STD among them. 18. Bridge Design of bridges should comply Site visits & observations Being The contractor has taken Monthly progress construction with the requirements of “Bridge Weekly checklist complied step to implement bridge meetings and Design Manual” of RDA. construction activities checklists according to the approved Contractor should provide safe and methodology with convenient passage or alternative access to minimum environmental road users for the entire construction period damage to the nearby or seeking approval from the Supervision vicinity areas. consultant. Smooth traffic flow to be ensured The consultant and the during the entire construction period with client will keenly observed the provision of appropriate safety their activities and guiding measures. when he needs to dispose the slurry into open. During piling activities, the Bentonite slurry generated will be collected and air dried.

88

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied Then it should be disposed in disposal yards. In no case the slurry will be discharged to the water bodies and agricultural land etc. 19. Access to Access to new public utilities should be Site visits & observations Being The contractor has Monthly progress Public utilities clearly marked within the road reservation in Weekly checklist complied completed the access meetings and consultation with the concerned survey to ensure the checklists departments. neediness of the new access along the ROW. The provisions provided to make better accesses to public parallel to road development. B. Operation stage 20. Routine checking to discourage Site visits & observations To Be During the performance Monthly progress Encroachment encroachments and removal of unauthorized complied based management, the meetings of the RoW st r u c t u r e s from RoW in consultation contractor, the Executive with Police Department. Engineer and the PMU staff will conducting Popularizing and Implementation of rules routing visits to see any and regulations with respect to RoW and encroachments along the to avoid encroachment from the RoW. road 21. Clearing of Periodical clearing of Cross drains and Site visits & observations To Be Do Monthly progress Cross side drains (specially before commencing of complied meetings Drainage rainy season) to facilitate easy Structures discharge of 22. Road safety Enforcement of the speed limits, Site visits & observations To Be Do Monthly progress traffic rules and regulations to the sensitive complied meetings locations, Installation of the warning signs, marking of center line, pedestrian crossings,

89

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied bus halts and other utilities. 23. Road Developing and Implementation of Site visits & observations To Be Do Monthly progress maintenance Periodical maintenance program. complied meetings

90

Appendix: 04(c) Status of EMP* Compliance (Mathugama-Southern Expressway (B157) Road) (*this EMP is included in the bidding document)

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied A. Pre construction and Construction stage

1. Removal As part of the pre-construction Site observations Being Water lines, Telecom and of public activities, initially consultation and consent Monthly Progress complied to Electricity poles are being utilities should be taken from relevant service meetings removed. providers (CEB / NWSDB / SLT) if sections Public complaints of utility lines needs to be shifted due During the reporting to design requirements or shift in alignment period, 28% of Electricity Poles, 42% of Telecom Obtain permission from DoI for any poles were shifted. proposed construction works on irrigation canals No any complaints received so far. Use of well trained and experienced machinery operators to reduce accidental damage to the public utilities

Advance notice to be served to the affected public about the time and the duration of the utility disruption

Substitute sources of water and other utilities during the disruption period, and restoration of the public utilities as soon as possible. 2. Removal Mark all road side trees subjected to Site observations Being Removal of road side trees of road side potential felling and preparation of inventory Weekly checklists complied to is completed in section 01 trees prior to start clearing. and the activity has

91

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied Decision on tree removal should be based on already begun in sections detailed engineering design. 02.

Maximum effort towards avoiding removal of religious, cultural and aesthetic important trees through joint field verifications and decision taking.

Obtain permission in writing from DoF regarding removal of trees and seek compensatory modalities and plan for afforestation programmes. Compensatory plantation program at twice the number to be felled and its cost estimation in consultation with DoF.

To avoid further tree losses, the contractor should ensure that the temporary use of land for construction related activities will be established without any additional tree cutting. 3. Temporary Construction facilities should be Site observations Being The contractor uses Monthly site visits use of lands established at least 500 m away from Weekly checklists complied to temporary lands for his water bodies, natural flow paths, Public complaints main yard at 40+010 km, important ecological habitats and residential stock pile at 41+280(ABC), areas. 37+920(soil), and 36+840(soil). Selection of site for these facilities by The permission has been adhering to stipulated local laws and obtained and rental is regulations and in close consultation with paid. LAs. The existing trees have

92

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied been saved within the Pay compensation / rent for using the yard during its site and get an official permit from the construction. agencies if any public utilities will be used for its facilities.

In establishing these facilities, the contractor should minimize removal of trees and other green cover vegetation to the extent possible. 4.Land Compensation prior to acquisition of Site observations Being Land acquisition activities acquisition property as per the R& R policy and Public complaints complied to have been completed in and restoration of livelihood. section 01 and it is being Resettlement progressed in section 02. 5. Solid waste Designing and Provision of solid waste Site observations Being Waste collecting facilities disposal and collection, storage, disposal, sanitation and Weekly checklist complied to have been provided to sanitation sewage facilities at all sites for the Public complaints labour camps, yards and construction/labour camps, and other office. construction sites. Solid Waste materials are Handling and management of waste weekly handed over to generated from the construction/labor waste collecting vehicles camps without contaminating the of MC in Mathugama. surrounding environment and not posing any threat to the public/communities living Adequate toilets and wash in and around the sites. room facilities are at the labour camps. Provide adequate facilities to manage its wastes in consultation with CEA and Waste water discharging PHI of the area. facilities have been established. Proper drainage facilities should be designed

93

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied and developed in the workers base camp sites to minimize stagnation of wastewater.

Solid waste should not be burnt but emphasis to be laid for their recycling, composting and sanitary land filling. Adequate supply of hygienic water should be provided to the urinals, toilets and wash rooms of the worker camps.

Garbage bins should be provided to all workers’ camps and construction sites, and needs regular clearing and appropriate disposal and if needed to be treated with disinfectants. 6. Top soil The fertile top soil to a depth of 20 - Site observations Being Approved ....disposal Conservation 30 cm should scoop out and preserved in Check lists complied to sites are being operated and Disposal a manner so that the stack is not washed Public complaints and those of debris away during rainy days. The top soil can be utilized in the future for turfing Levelling activities are also purpose, enhancing soil quality of degraded being progressed. land patches, plantation purposes etc.

All debris and residual spoil materials including any left out earthen material should be disposed off only at locations approved by the relevant LAs.

Spoil materials (soil, sand, rock etc,) generated during the construction activities should be utilised wherever found

94

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied suitable for activities like site leveling, back- filling etc with prior approval of CSC.

Suitable dumping grounds/ land fill sites should be identified for the disposal of surplus excavated/surplus/discarded/demolis hed materials of existing structures.

The debris and spoil should be disposed in such a manner that; • Does not block the waterways and drainage paths • The disposed materials should not be washed away by runoff • Debris should not be disposed into any agriculture lands, marshlands, down slopes or any environmental sensitive areas • Avoid/ Minimize annoyance to general public and road users 7. Extraction of Suitable quarry sites and borrow areas Site observations Being The contractor is allowed construction should be identified at the initial stage of Check lists complied to only to sourcing materials materials the project. Public complaints from approved sites

Utilizing the existing mines and quarry The contractor has sites available in the project influential areas, submitted their permits which are approved by GSMB or LAs, and licenses about operating with EPL and IML material extortion sites

If new quarries and sand mines are to be The monthly visits

95

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied opened, prior approval should be obtained conduct to observe the from GSMB, CEA and LAs. sites. During the visits, Project’s quarries should not be located in environmental protection any environmentally sensitive areas, in activities, hygiene matters, vicinity to archeological and cultural sites, waste disposal and related religious places, schools and settlements. activities are observed.

Quarries and borrow areas should meet aesthetic demands and have rehabilitation plans designed and implemented.

Use of alternative source for the river sand such as screened crusher fines or sea sand.

Restoration of the borrow pits by contractor or relevant authorities once after borrowing.

Use of insecticides/disinfectants in the camp sites/plant sites and waste collection areas to discourage Vector breeding. 8. Trucks carrying construction materials Site observations Being The contractor is advised Transportation should not be overloaded and covered with Check lists complied to to cover the materials and storage tarpaulins to reduce fines getting airborne. Public complaints when it transport to the of construction sites, handling and its materials Avoid storage of construction materials storage. beside the road, around water bodies, residential or public sensitive locations. When monthly site visits conducting, these activities Materials loading and unloading should not are observed. cause nuisance to the people by way of

96

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied noise, vibration and dust emission.

Sand, rubble, metal, bitumen, cement etc should be stored in designated areas to ensure optimum utilization preferably on a solid platform. Such materials should be handled in environment friendly and nuisance free manner. 9.Effect on Permit from LAs to use local roads prior to Site observations Being The contractor has been local road using the roads for transportation of Check lists complied to advised to get permissions network construction materials, machinery and Public complaints from relevant authorities equipment etc. prior to use local roads for his activities mainly for The contractor should- ensure that material transports. transportation of construction materials by suppliers should not exceed the carrying If the roads get damaged capacity of the local roads. due to contractor’s activities, he is obligated Regular Maintenance of local roads and their to repair it immediately. restoration which are used for hauling activities for the construction related activities. 10. Soil Implement erosion control measures such as Site observations Being According to the EMP, the erosion and fiber mats, gabions walls, rip raps and deep- Check lists complied to contractor is advised to surface runoff rooted grasses etc to erodible areas Public complaints take all possible remedial actions against the soil Seeding with a fast growing native species erosion takes places such and seed mix immediately after fill as structure construction placement to develop green cover to protect areas, material sourcing the earth works. areas, and road excavation areas.

97

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied Construction in erosion and flood- prone areas should be restricted to the dry season (excluding December – February)

Stabilization of embankment slopes and road cuts by re-vegetation and take up a turfing work as soon as possible before rains.

Treat clearing and filling areas against flow acceleration and construction work should be carefully designed to minimize obstruction or destruction to natural drainage. 11. Effect Contractor should avoid storage of Site observations Being The contractor has taken Regular site visits on existing construction materials and disposal of Check lists complied to steps to avoid blockage, and checklist drainage debris around irrigation canals, cross Public complaints make temporary diverts, pattern drainage and natural flow paths. and cleaning existing drainage periodically. Culverts and all other drainage paths have to be appropriately designed by allowing sheath flow and without any blockages.

Provide temporary diverting drainage facilities to construction sites while repairing and replacement of obstructed drains and structurally damaged culverts/ bridges. 12. Protection of Avoid tapping water from sources in Site observations Being The contractor is advised water resources residential areas being used by the local Check lists complied to to avoid unnecessary community. Public complaints obstructs due to his works

98

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied to nearby water sources. Contractor should not obstruct or prevent flowing of water when working closer to The contractor has taken water bodies. steps to minimize the effects from their bridge Construction works affecting the streams and construction sites. irrigation canals have to be undertaken during the dry season with prior permission Silt traps are located at from the concerned Department. yard, and crusher plant

Minimize excavation of beds of any streams, Stock piles are situated irrigation systems, and other water away from the water resources so that water flow in the beds is sources. unaltered.

Use of silt traps and erosion control measures where the construction is carried out in close proximity to the water bodies to avoid entering of cement, sand and other particulate matters which cause turbidity and increase sedimentations.

Storage of construction materials which are toxic, hazardous and containing other fine particles would be sited at least 500 from water bodies to avoid its contamination to water resources. Trenches around the storage area to confine the flow outs. 13. Affect Approval from DoF should be Site observations Being All the trees that to be on flora and obtained prior to start of project activities Check lists complied to removed within the ROW fauna towards felling of trees and planning Public complaints are clearly marked by towards carrying out compensatory Survey prior to construction started.

99

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied afforestation. The trees that possible to save within ROW will be Contractor will prevent his work force protected. from gathering fire wood from surrounding A re-planting program habitats, disturbing tothe flora, fauna will be carried out as a including hunting of animal and fishing in compensation to cut trees. water bodies More than 500 plants will be planted along the road All construction materials extraction sites, Provisions are provided to material processing plants, storage yards conduct the and construction vehicle service stations Environmental awareness will be located away from the water bodies, and the contractor has environmental sensitive locations advised to carry out the programm Proper awareness programs to be conducted regarding conservation of flora, fauna including ground vegetation to all drivers, operators and other workers 14. Provide and publicize advance Site observations Being The contractor has Monthly Disruption of notices to local communities about the Check lists complied to submitted the traffic observations traffic schedule of construction activities. Public complaints control plan and it is parallel to monthly approved. meeting Installation of traffic waning signs, signaling system, flagman at the construction sites. The traffic safety plan is implemented and site Provide safe and convenient passage to safety /traffic safety vehicles, passengers and livestock from the activities are smoothly approaching roads. functioning.

Traffic and safety management plan should be implemented in close coordination with local communities/authorities and police

100

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied department during the entire construction period.

Contractors to plan and implement diversion roads for sensitive locations with prior approval of the Supervision Consultant. 15. Air quality Contractors should place crushers Site observations Being The periodical cheeking of Monthly site and hot mix plants at least 500 m away Check lists complied to air quality is being observations from residential areas or other social Public complaints progressed along the road parallel to monthly infrastructures (school, hospital/religious as well as selected plant meeting places etc) sites to see possible pollutions Such establishments should strictly comply to National Emission Standards for all Dust controlling activities construction vehicles, equipment and such as water sprying for material processing plants road construction areas, dust barriers for plant Dust extraction/suppression systems should operation are be fitted to crusher units, construction implemented vehicles and hot mix plants

Sprinkling of water to the construction sites and haul roads which are being used for the transportation of construction materials in regular intervals towards dust suppression.

Placing of dust barriers nearby schools, religious places, market etc.

Use construction equipment, machinery and

101

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied vehicles which are in good condition and those to be regularly maintained.

16. Noise Strictly implement noise control regulations Site observations Being The periodical cheeking of Monthly site and vibration for all construction vehicles and equipments. Check lists complied to noise and vibration are observations Public complaints being progressed along parallel to monthly Contractors should equip their heavy the road as well as selected meeting construction equipment with acoustic plant sites to see possible enclosures/ silencers to limit the impacts construction equipment not to generate noise exceeding 75 db (compacters, loaders, The contractor is obligated vibrators, cranes, diesel generator sets) to maintain the national standards of noise and Limit working time for activities that vibrations during his create noise only between 6.00 am to 6.00 construction activities. pm except for construction site near schools, offices, religious places.

Contractors should schedule their activities at sensitive locations in consultation with the relevant authorities (school’s principals, high-priest etc.)

Regularly maintain all construction vehicles and machinery to meet the National Emission Standards. 17. Personal Organize awareness programs Site observations Being The contractor is being Monthly safety and regarding personal safety of workers and Check lists complied to implemented tool box observations, and health general public during construction period. Public complaints meeting/awareness weekly checklist campaigns periodically. observations Establishment of safety provisions to

102

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied reduce the likelihood of accidents by Safety provisions are placing warning signs, speed limit provided to caring out the markings, speed breakers and signals to PPEs and the Traffic safety particular locations. activities. First aid facilities, and Providing appropriate PPEs such as worker rest room are protective footwear, helmets, goggles, eye- provided. shields and clothes to the workers Standstill emergency depending on their activities (Mixing asphalt, vehicle is available. blasting, handling equipments etc) and The contractor has motivating the workforce for their usage. submitted a schedule about the HIV/AIDS Establishing first aid facilities and awareness program that to Ambulance facilities at active working sites be conducted and these to meet emergency situations. activities are being implemented. Use experienced and well trained workers for the handling of machinery, equipment and material processing plants.

Contractor should implement STD/ HIV/AIDS awareness programs for general public in and around project implementation area and workers to reduce the risk of spreading STD among them. 18. Bridge Design of bridges should comply with Site visits & observations Being The contractor has taken Monthly progress construction the requirements of “Bridge Design Weekly checklist complied step to implement bridge meetings and Manual” of RDA. construction activities checklists Contractor should provide safe and according to the approved convenient passage or alternative access to methodology with road users for the entire construction period minimum environmental

103

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied seeking approval from the Supervision damage to the nearby or consultant. Smooth traffic flow to be ensured vicinity areas. during the entire construction period with The consultant and the the provision of appropriate safety client will keenly observe measures. their activities and guiding when he needs to dispose During piling activities, the Bentonite the slurry into open. slurry generated will be collected and air dried. Then it should be disposed in disposal yards. In no case the slurry will be discharged to the water bodies and agricultural land etc. 19. Access to Access to new public utilities should be Site visits & observations Being The contractor has Monthly progress Public utilities clearly marked within the road reservation in Weekly checklist complied completed the access meetings and consultation with the concerned survey in section 01 and is checklists Departments. to be completed in section 02. This is for identifying the neediness of the new access along the ROW. The provisions provided to make better accesses to public parallel to road development. B. Operation stage 20. Routine checking to discourage Site visits & observations To Be During the performance Monthly progress Encroachment encroachments and removal of unauthorized complied based management, the meetings of the RoW structures from RoW in consultation with contractor, the Executive Police Department. Engineer and the PMU staff will conducting Popularizing and Implementation of rules routing visits to see any and regulations with respect to RoW and encroachments along the

104

Complied? Potential Yes/Not Explanation if compliance Indicator or Means of Further Environmental Mitigation Action Complied/ status is partly complied verifications actions/Timeline Impact Partly or not complied Complied to avoid encroachment from the RoW. road 21. Clearing of Periodical clearing of Cross drains and Site visits & observations To Be Do Monthly progress Cross side drains (specially before commencing of complied meetings Drainage rainy season) to facilitate easy Structures discharge of 22. Road safety Enforcement of the speed limits, Site visits & observations To Be Do Monthly progress traffic rules and regulations to the sensitive complied meetings locations, Installation of the warning signs, marking of center line, pedestrian crossings, bus halts and other utilities. 23. Road Developing and Implementation of Site visits & observations To Be Do Monthly progress maintenance periodical maintenance program. complied meetings

105

Appendix: 05 Public Complains Table 3.1 (a)The list of complains up to 31st March 2017 for B295 ‘Moratuwa-Piliyandala’ Road

# Date Complainant Nature of Complaint Action Taken Resolution Contractor B.D.P. Kularathne (4+230 RHS) Not to upgrade culvert Employer agreed to omit culvert instructed 1 26-May-15 241, Moratuwa Road, Suwarapola, discharging to lead-away drain improvement accordingly on Piliyandala through their property 09/03/2016 Haklis Bathlo, Remove signboard near their Contractor directed to remove Sign removed on 2 10-Aug-15 Piliyandala gate sign 10/12/2015 (LHS) Contractor cleared culvert inlet, Existing culvert at Km 3+027 Completed on 3 27-Sep-15 outlet and lead-away channel to unable to cope with heavy flow 12/10/2015 improve flow Action by Objects to improving existing Lead-away drain improvement N.C. Dulwala (4+560 RHS) Municipal 4 28-Sep-15 lead-away drain through her has been referred to Municipal 175/5, Moratuwa Road, Piliyandala Authority and it is property Authority being processed i. Contractor directed to provide i. Request for house access, access, B.D.M.U. Kularathne (4+280 LHS) ii. Retaining wall to front ii. PE to refer wall to GRC, and Work completed 5 16-Oct-15 196, Moratuwa Road, Piliyandala boundary, and iii. Contractor directed to on 08/06/2016 iii. Protection of water well construct drain to protect water well Request for additional M. Kulawathi De Costa (4+840 LHS) Completed on 6 16-Oct-15 compensation for land Referred to Employer 88/2, Moratuwa Road, Piliyandala 15/03/2016 acquisition and payment delay H.M. Upasena (3+940 RHS) Request to construct their two 263, Ransara Reception Hall, Contractor directed to construct Work completed 7 16-Oct-15 accesses one-by-one to avoid Moratuwa Road, Suwarapola, accesses one-by-one on 15/11/2015 disturbing business Piliyandala Y.A. Dayarathne Request to construct by-road Contractor directed to provide Work completed 8 16-Oct-15 142/6, Moratuwa Road, Piliyandala access suitable for large vehicle sufficient cover slabs on 20/10/2015 P.A.D. Rohana (3+770 RHS) Request to protect front door Structure encroaches into ROW Completed on 9 16-Oct-15 285/A, Moratuwa Road, Suwarapola, frame during construction and required demolition 12/12/2015

106

# Date Complainant Nature of Complaint Action Taken Resolution Piliyandala i. Request to protect boundary Contractor directed to protect W.A.A.P. Gunathilaka (4+640 RHS) wall during construction, and Work completed 10 16-Oct-15 boundary wall and ensure 126, Moratuwa Road, Piliyandala ii. Provide temporary vehicle on 05/11/2015 uninterrupted access access i. Double access request referred i. Request two access to I.D. Siripala Perera (3+990 LHS) to Employer, and Work completed 11 16-Oct-15 property, and 248, Moratuwa Road, Piliyandala ii. Contractor directed to attend on 03/03/2016 ii. Shift CEB pole at boundary to utility relocation i. Request 2 months to demolish shop front for construction, (i) Contractor directed to (i) Work plus coordinate construction with completed on B.D.D.N. Kularathne (4+280 RHS) 12 16-Oct-15 ii. Additional resettlement shop demolition, and 05/01/2016, 223, Moratuwa Road, Piliyandala compensation, plus (ii) Compensation issues and iii. Additional compensation for referred to Employer (ii) Pending disturbance to business P.G.R. Anula Gamlath Request for alternative property Contractor directed to provide an Work completed 13 13-Nov-15 320/1, Basil Niwasa, Suwarapola, access location at Km 3+250 LHS access suitable for the property on 08/05/2016 Piliyandala M.P. Chandana Perera Request for additional access at Work completed 14 23-Dec-15 Referred to Employer 237, Moratuwa Road, Piliyandala KM 4+180 RHS on 10/03/2016 B.D.P. Kularathne Instruction issued to alternatively Request not to construct new Work done on 15 15-May-15 241, Moratuwa Road, Suwarapola, open and extend existing culvert culvert at Km 4+238 09/03/2016 Piliyandala at Km 4+210 Muditha Chaminda Sudasinghe Site inspection determined there Request to slope cover slabs at Resolved on 16 06-Jan-16 320, Moratuwa Road, Suwarapola, is no need to install sloping cover Km 3+235 LHS 12/02/2016 Piliyandala slabs Work completed Referred to Employer for K. Indika Thilakarathne Request not to open existing by Municipal 17 Jan-16 discussion with local government 226/2, Moratuwa Road, Suwarapola culvert at Km 4+210 Authority on authority 25/02/2016 Work completed Concern about potential flooding Referred to Employer for T.A. Priyarathna by Municipal 18 12-Jan-16 of access road during rainy discussion with local government Suwarapola, Deniya, Piliyandala Authority on season at Km 3+263 RHS authority 25/02/2016 G.T.S. Thilakarathne Referred to Employer for Action by Request for lead-away drain at 19 13-Jan-16 37B, Hadigama, Piliyandala discussion with local government Municipal Km 3+446 RHS 317, Moratuwa Road, Suwarapola, authority Authority to be

107

# Date Complainant Nature of Complaint Action Taken Resolution Piliyandala completed C.D. Palathirathne Request to slope cover slabs and Work completed 20 14-Jan-16 320/A, Moratuwa Road, Deniya, provide 2m paving at Km 3+172 Instruction issued to Contractor on 28/04/2016 Piliyandala LHS Sandya Jayawardhna Request for additional access at Employer determined that Resolved on 21 15-Jan-16 321/5, Basil House, Moratuwa Road, Km 3+153 LHS existing access is sufficient 28/01/2016 Suwarapola, Piliyandala K.D. Laksiri ROW confirmed and instruction Work completed 22 20-Jan-16 317/B, Moratuwa Road, Suwarapola, ROW at Km 3+668 RHS issued to Contractor to proceed on 20/02/2016 Piliyandala Ravina Mortes Instruction issued to Contractor Request for cover slabs at Km Work completed 23 23-Jan-16 331/1/A, Moratuwa Road, Deniya to provide cover slabs for culvert 3+268 LHS on 07/06/2016 Junction catch pit Sanio Lanka Apparels Request to cover culvert opening Necessary instruction issued to 24 25-Jan-16 226/2, Moratuwa Road, Suwarapola, Work in progress at Km 4+210 Contractor on culvert design Piliyandala Contractor has advised Insurance S.D.J. Jayasinghe Boundary wall at 3+140 LHS Work completed 25 25-Jan-16 Company and commenced 320/1, Suwarapola, Piliyandala collapsed on 28-Jan-16 on 14/05/2016 reconstruction Damage to existing water line at Advised Contractor to take action Water line repaired 26 01-Mar-16 DGM NWS&DB Km 3+137 RHS with NWS&DB on 03/03/2016 Rasanga Gamage Request for more substantial Contractor instructed to provide 27 14-Mar-16 213/4, Gangarama Road, Werahara, Work in progress cover slabs at Km 2+220 LHS medium duty cover slabs Boralegamuwa S.D. Siriyawathi Instruction issued to Contractor Request for suitable access Work completed 28 18-Mar-16 No.128C, Moratuwa Road, to accommodate access for arrangement at Km 4+730 LHS on 06/06/2016 Piliyandala finished road level L.A.S. Suwarna Ajantha Drainage concern at Km 4+230 Instruction issued to Contractor Work completed 29 05-Apr-16 No.64/2, Moratuwa Road, RHS to close drain opening on 05/05/2016 Suwarapola, Piliyandala N. Jayasundara Request for suitable access at Km Completed on 30 05-Apr-16 Asala Steel Centre, No.279A Instruction issued to Contractor 3+830 RHS 05/08/2016 Motatuwa Road, Suwarapola Request for extension of P.L.A. Perera, No.307 Completed on 31 26-Apr-16 provided access at Km 3+670 Sent to the PE for further advise Moratuwa Road, Suwarapola 10/07/2016 RHS N. Jayasundara Request for cover slabs at Km Instruction issued to Contractor Completed on 32 04-May-16 No.108/A, Horana Road, Piliyandala 3+830 RHS for cover slabs 05/08/2016

108

# Date Complainant Nature of Complaint Action Taken Resolution Cable repaired on Underground cable at Km 0+970 29/05/2016 and SLT and Insurance Company 33 28-May-16 SLT RHS damaged during settlement of notified construction activity insurance claim pending Insurance claim Fire damaged operators paid and repairs 34 31-May-16 Vishwakala Labour Camp Insurance Company notified accommodation carried out on 15/01/2017 P.A.R.P. Perera Request for suitable access at Km Completed on 35 10-Jun-16 No. 302A, Moratuwa Road, Instruction issued to Contractor 3+360 LHS 16/08/2016 Suwarapola, Piliyandala Boundary Bodhi Bharakara Mandalaya, Purana RDA Boundary problem at Km Survey Department has marked confirmed and 36 10-Jun-16 Bodhi Rajaya, Suwarapola, 3+558-3+603 LHS RDA boundary work resumed on Piliyandala 15/09/2016 K. Sanath Nihal, No 259, Maratuwa Request for suitable access at Km Instruction issued Contractor to Completed on 37 10-Jun-16 Road, Suwarapola, Piliyandala 3+980 - 4+000 RHS provide vehicle access 28/02/2017 Boundary K. Chaya Pranandu, No. 14, Johon De RDA Boundary problem at Km Survey Department has marked confirmed and 38 17-Jun-16 Silva Mawatha, Molpe, Moratuwa 3+558-3+603 LHS RDA boundary work resumed on 15/09/2016 W.S. Wimala Fernando, 349/1, Request to provide steps for Contractor instructed to provide Completed on 39 30-Jun-16 Moratuwa Road, Kospelana, access suitable steps for access 14/01/2016 Piliyandala Vibration Contractor directed to investigate measured and S.D. Srimal, 242, Moratuwa Road, Complaint over vibration during 40 09-Jul-16 and carry out vibration found to be within Suwarapola, Piliyandala construction activity measurement allowable limit on 18/08/2016 Contractor directed to operate Contractor took V.S. Weerakkodi, 1B, Gangule Complaint about dust and 41 11-Jul-16 disposal yard within approved action on Mawatha, Suwarapola, Piliyandala disposal truck speed constraints 15/07/2016 Boundary I.A.D.U.R. Perera, 1, Gangule confirmed and 42 11-Jul-16 RDA boundary at Km 3+560 LHS Referred to PE Mawatha, Suwarapola, Piliyandala work resumed on 15/09/2016 43 08-Aug-16 Ransara Reception Hall Request cattle trap cover on Referred to PE who has further Resolved

109

# Date Complainant Nature of Complaint Action Taken Resolution 263, Moratuwa Road, Suwarapola, concrete drain at Km 3+900 RHS referred to EE 05/03/2017 Piliyandala K.I. Thilakaratne Request to omit culvert parapet Completed on 44 29-Aug-16 226/2, Moratuwa Road, wall to avoid blocking access at Instruction issued to Contractor 10/03/2016 Piliyandala Km 4+207 Cable damaged during Contractor notified Dialog and Insurance claim 45 07-Sep-16 Dialog construction work at Km 3+369 Insurer and lodged insurance pending LHS claim Work done on Wepataira Hemaloka Thero Request to construct temple road Contractor requested to submit a 15/11/2016, but 46 13-Sep-16 Siri Wijayaramaya Udayogi Pura, at Km 2+980 proposal Contractor Wewala, Piliyandala proposal awaited PE advised to remove parapet U.D. Pilyasena Request to remove new parapet 47 22-Sep-16 wall; Contractor instructed Pending 148, Moratuwa Road, Piliyandala wall at Km 4+538 accordingly Nihal Pagoda Arachchi Request for line marking and Bodhi Bharakara Mandalaya, Purana Incorporated in line marking Completed on 48 17-Oct-16 pedestrian crossing at Km 3+560 Bodhi Rajaya, Suwarapola, design 12/01/2017 LHS Piliyandala Hemantha U. Arachchi Km 4+070 LHS access road Contractor instructed to match 49 19-Oct-16 238, Moratuwa Road, Suwarapola, Work in progress connection issue access road level with B295 Piliyandala T.A. Piyarathna Urban Council Water stagnation at Km 3+268 Lead-away drain action by 50 19-Oct-16 Suwarapola, Deniya Road, work completed RHS Kesbewa Urban Council Piliyandala 15/03/2017 G.H.D. Wijeesena, Request for cover slabs over Cover slabs instructed for 51 31-Oct-16 Work in progress Piliyandala drains electrical post area Nuwani Construction, 128, Details submitted to PE for 52 29-Dec-16 Request for cover slabs Pending Moratuwa Road, Piliyandala approval

110

Table 3.1 (b)The list of complains up to 31st March 2017 for B389 ‘Ratmalana-Mirihana’ Road

# Date Complainant Nature of Complaint Action Taken Resolution C.L. Jayawardhana (0+210 RHS) Request for temporary Contractor directed to Temporary access provided 1 2-Sep-15 62A, Mirihana Road, Nugegoda access during construction provide continuous access on 20/09/2015 H.M.D.D. Dammika (1+230LHS) RDA have inspected and Claim that compensation 2 7-Sep-15 337, Amarasa Hotel, Gamsabha Referred to Employer replied to the Complainant was not paid Junction, Nugegoda on 17/10/2015 Wimaladharma Ekanayaka Water flowing to their Contractor instructed to 3 17-Sep-15 (0+065 RHS) Completed on 15/03/2017 property construct lined side drain 73/1, Mirihana Road Palitha Wijayawardhana (1+150 Contractor directed to allow LHS) Request to open drain 4 21-Sep-15 storm-water to flow from by- Completed on 16/02/2016 111/7, Subodarama Road, from by-road road to main road drainage Nugegoda Boundary wall collapsed Contractor directed to Ishara Wijesinghe (0+620 LHS) Reconstruction completed 5 23-Sep-15 during lined drain reconstruct boundary wall as 30/1, Mirihana Road, Nugegoda on 10/06/2016 construction soon as possible Request to avoid property Contractor directed to liaise D. Kadahawala (0+520 RHS) Work completed on 6 26-Oct-15 damage during with resident and avoid 23, Mirihana Road, Nugegoda 14/03/2016 construction damage Contractor directed to check D.H.H.M. Sathischandra Request to maintain level at location and ensure Work completed on 7 11-Dec-15 126D, Subadrarama Road, drainage at Km 0+820 RHS drainage to new roadside 14/02/2016 Nugegoda drain S.D. Devasunara Request to relocate Contractor directed to liaise Work completed on 8 Dec-15 107, Subadrarama Road, telephone post at Km with Telecom and property 09/03/2016 Nugegoda 1+113 LHS owner over post relocation D.R.K.V. Wijegunawardhana Disputing ROW land Boundary checked and work Work completed on 9 Jan-16 51, Papiliyana Road, boundary at Km 1+550 cleared to proceed 09/03/2016 Gangodavila, Nugegoda LHS Boundary wall at Km Contractor has submitted B.S.A.S.N. Sudasighe Contractor directed to 1+340 RHS collapsed claim to Insurer and 10 9-Jan-16 22/A, Papiliyana Road, promptly reconstruct during lined drain completed reconstruction Gangodavila, Nugegoda damaged wall and access construction on 20/01/2017 Contractor damaged Contractor advised SLT and SLT repair completed but 11 9-Jan-16 Telecom buried STL wire at Km Insurers insurance claim pending 1+820 LHS

111

# Date Complainant Nature of Complaint Action Taken Resolution B.S.A.S.N. Sudasighe Request for cover slabs at Contractor directed to Work completed on 12 Jan-16 22/A, Papiliyana Road, Km 1+340 RHS provide cover slabs 05/03/2016 Gangodavila, Nugegoda Request for specific house M.D.N. Daminda Contractor directed to Work completed on 13 20-Jan-16 access arrangement at Km 10, Papiliyana Road, Nugegoda provide access as requested 28/02/2016 1+315 RHS V.A.D. Kularathne Request for specific house Contractor directed to adjust Work completed on 14 25-Jan-16 162, Subadrarama Road, access arrangement at Km drain height to suit access 18/01/2017 Nugegoda 1+135 RHS SLT post at Km 1+430 RHS New pole erected on Contractor notified Insurer 15 29-Feb-16 SLT collapsed onto three- 02/03/2016 but insurance and lodged claim wheeler during heavy rain claim pending Underground cable Km LECO repair completed on 0+880 to 0+920 RHS Contractor notified LECO 16 29-Feb-16 LECO 02/03/2016 but insurance damaged during and Insurer and lodged claim claim pending construction activity Underground cable at Km Cable repaired and 0+078 LHS damaged Contractor notified LECO Contractor paid 17 04-Mar-16 during construction and Insurer and lodged claim compensation to SLT on activity 05/04/2016 Request that by-road Ananda Perera Maddumage Referred to Employer as drainage be blocked from 18 26-Mar-16 111/9, Subadhraramaya Road, contradicts requests of other Resolved on 05/04/2016 entering lined side drain at Gangodavila, Nugegoda residents Km 1+124 LHS Bandula de Silva, Request for house access at Contractor directed to Work completed on 19 31-Mar-16 No 81, Pepiliyana Road, Km 1+810 LHS provide access as requested 03/05/2016 Gangodawila, Nugegoda. Underground cable at Km Cable has been repaired on 0+750 LHS damaged Contractor notified LECO 20 25-Apr-16 LECO 26/04/2016 but insurance during construction and insurer and lodged claim claim pending activity Electricity pole collapsed New pole erected on Contractor notified LECO 21 29-Apr-16 LECO during construction at Km 29/04/2016 but insurance and insurer and lodged claim 0+240 RHS claim pending Underground cable at Km Cable has been repaired on 0+970 LHS damaged Contractor notified SLT and 22 06-May-16 SLT 08/05/2016 but insurance during construction insurer and lodged claim claim pending activity

112

# Date Complainant Nature of Complaint Action Taken Resolution Underground cable at Km Cable has been repaired 0+920 RHS damaged Contractor notified LECO 23 07-May-16 LECO 08/05/2016 but insurance during construction and insurer and lodged claim claim pending activity Boundary wall at Km Contractor has submitted Contractor directed to 0+640 LHS collapsed claim to Insurer and is 24 11-May-16 promptly reconstruct during construction proceeding with damaged wall and access activity reconstruction Damage to house roof Contractor directed to A.I. Walikada Work completed on 25 17-May-16 canopy during promptly repair damaged No 128, Subadhrarama Road 08/08/2016 construction activity canopy Underground cable at Km Cable has been repaired on 0+360 LHS damaged Contractor notified SLT and 26 28-May-16 SLT 30/05/2016 but insurance during construction insurer and lodged claim claim pending activity Underground cable at Km Cable has been repaired on 0+680 LHS damaged Contractor notified SLT and 27 06-Jul-16 SLT 07/07/2016 but insurance during construction insurer and lodged claim claim pending activity Electrical post has been Electrical pole collapse Contractor notified LECO repaired on 08/07/2016 28 08-Jul-16 LECO while backhoe working at and insurer and lodged claim but insurance claim Km 0+250 RHS pending Vibration level measured D.U.R. Wijesinghe, 17B, Mirihana Contractor directed to and contractor directed to 29 09-Jul-16 Complaint about vibration Road, Nugegoda investigate and adjust rolling procedure on 12/07/2016 Underground cable at Km Cable has been repaired on 0+735 LHS damaged Contractor notified SLT and 30 30-Jul-16 SLT 01/08/2017, but insurance during construction lodged Insurance claim claim pending activity Underground cable at Km Cable has been repaired on 1+883 RHS damaged Contractor notified SLT and 31 30-Jul-16 SLT 01/08/2017, but insurance during construction lodged Insurance claim claim pending activity Karunasena Moramudali Request for cover slabs at Instruction issued to Work completed on 32 10-Aug-16 13, Kattiya Junction, Mirihana Km 0+647 to 0+660 RHS Contractor 18/01/2017 Road, Nugegoda

113

# Date Complainant Nature of Complaint Action Taken Resolution M.D.S.F. Arthakularathne Work completed on 33 08-Sep-16 Request to cover slab Provided 87, Papiliyana Road, Nugegoda 25/09/2016 Boundary wall at Km Contractor has submitted Contractor directed to 1+330 RHS collapsed claim to Insurer and 34 11-Sep-16 promptly reconstruct during construction reconstructed the wall on damaged wall activity 22/01/2017 Underground cable at Km Cable has been repaired on 1+350 LHS damaged Contractor notified SLT and 35 11-Sep-16 SLT 12/09/2017, but insurance during construction lodged Insurance claim claim is pending activity Underground cable at Km Cable has been repaired 0+890 RHS damaged Contractor notified LECO 36 23-Sep-16 LECO 24/09/2017,but insurance during construction and lodged Insurance claim claim is pending activity Malika Disanayaka 37 28-Sep-16 House access problem Instruction issued for steps Work in progress 75, Mirihana Road, Nugegoda Site inspected and Contractor 38 20-Oct-16 35, Privet Lane, Mirihana Access problem instructed to take mitigation Completed on 21/12/2017 action S.M.A. Senavirathna Site inspected and Contractor 39 27-Oct-16 17, Subadrarama Road, Access problem instructed to take mitigation Completed on 28/12/2016 Gangodavilla, Nugegoda action Damage to property W. Ekanayake Contractor instructed to 40 01-Nov-16 entrance by water line Completed on 23/11/2016 73/1, Mirihana Road, Nugegoda rectify access damage construction Thabbowa Ananda Revatha Thero, Subadrarame, Athula Awaiting Employer 41 03-Nov-16 Request for stone wall Referred to PE Rajamaha Viharaya, response Gangodavila, Nugegoda Request to construct by- Work completed on 42 15-Nov-16 Police Inspector, Mirihana By-road scope confirmed road 20/11/2016 Director, Agricultural & Agrarian Insurance Board, 117, Contractor instructed to Work completed on 43 01-Dec-16 Access problem Subadrarama Road, improve property access 18/12/2016 Gangodavila, Nugegoda Amith Batugedara, 106, Old Contractor instructed to Work completed on 44 29-Dec-16 Water ponding Kesbewa Road, Nugegoda remove pipe culvert 06/01/2017 45 11-Jan-17 M.A. Perera Request to construct by- By-road construction Solved on 22/01/2017

114

# Date Complainant Nature of Complaint Action Taken Resolution 115, Subadrarama Road, road and damaged completed and no boundary Nugegoda boundary wall wall damage identified Location inspected & M.A.R.K. Perera Request for new water Work completed on 46 06-Feb-17 approval given to excavate 77A, Mirihana Road, Nugegoda connection 03/03/2017 road W. Ekanayaka Request to add pedestrian Awaiting Employer 47 20-Feb-17 Referred to RDA 73/1, Mirihana Road, Nugegoda crossing decision

115

Table 3.2 The list of complains up to 31st March 2017 for B084

# Date Complainant Description Action Taken Resolution Mr. A.A.D. Jagath Kumara Vertical alignment Steep access slope due Survey carried out to 1 21-Dec-16 252, Kahathuduwa, Polgasowita adjusted to improve to road realignment amend alignment B084 Km 19+680 RHS access on 26/01/2017 Mr. M.D. Jayarathne Acquired boundary Verification of Currently subject to court 2 13-Jan-17 72/3, Kondurawawa, Polgasowita demarcated on boundary case B084 Km 15+220 RHS 18/01/2017 Referred to Local Mr. P.D. Diyasiri Pannarathne Request to change lead- Authority as lead-away Awaits action by Local 3 16-Jan-17 52A, Kondurawawa, Polgasowita away due to erosion outside ROW on Authority B084 Km 15+295 RHS from Culvert 16/1 17/01/2017 Referred to Local Residents near “Samagi Praja Lead-away drain near Authority as lead-away Awaits action by Local 4 01-Feb-17 Shalawa” “Samagi Praja outside ROW on Authority B084 Km 14+993 RHS Shalawa” 03/02/2017 Referred to RDA Land Mr. G. Gunasoma Verification of Acquired boundary Division for check with 5 02-Feb-17 22, Undurugoda, Polgasowita boundary demarcated Section 2 hand-over on B084 Km 18+020 RHS 02/02/2017 Survey being carried out To be considered under Mr. F.P. Wickramasinghe Concern about erosion 6 02-Feb-17 to determine protection Section 4 design on B084 Km 25+200 RHS after road excavation requirements 09/02/2017 Request to realign road Mr. Amarakoon Piyasena Road design checked on 7 02-Feb-17 to give space for his Survey being carried out B084 Km 21+950 RHS 09/02/2017 shop Residents near Rilawala Junction Request for a bus Information being Bus halt location to be 8 02-Feb-17 B084 Km 18+200 RHS shelter assembled on 09/02/2017 considered Request for parking Necessary setting out Mrs. D.L.S. Kumari 9 02-Feb-17 space and steps to determined on Work in progress B084 Km 15+710 RHS residence 24/03/2017 Mr. D.K. Abesinghe Request to move Relocated to 19+945 to 10 06-Feb-17 Work in progress B084 Km 19+930 Culvert 20/6 culvert align with lead-away B.A. Perera, 311/13, Request to remark land To be done for Section 2 11 13-Feb-17 Kahathuduwa, Polgaswita Survey to be carried out acquisition boundary hand-over B084 Km 17+380 to 18+380

116

# Date Complainant Description Action Taken Resolution Mr. S.J. Nawagamuwa Request for house To be surveyed once 12 13-Feb-17 Lot No. 4334 Access to be provided access Section 4 handed-over B084 Km 26+100 RHS Mr. B. Ariyawansha Request to verify land Directed to RDA Land 13 13-Feb-17 PP No.9265/Lot No.35 Survey to be carried out acquisition boundary Division on 03/02/2017 B084 Km 18+890 LHS Mr. K.B. Chandrapala Request to move Inspected by PE & EE on Lead-away to be moved 14 15-Feb-17 B084 Km 18+735 LHS Culvert 19/6 lead-away 20/02/2017 by 5m Request to close Further inspection Mr. D.G.L. Ramyasiri Inspected by PE & EE on 15 15-Feb-17 Culvert 18/2 and lead- scheduled with SDE for B084 Km 18+890 LHS 20/02/2017 away 09-Mar-17 Mr. Ranjith Fernando Request to move Inspected by PE & EE on Lead-away to be moved 16 15-Feb-17 B084 Km 18+730 LHS Culvert 19/6 lead-away 20/02/2017 by 5m (Adjacent to as 15 above) Mr. A.D. Leelarathna Request to mark land Remarked correct 17 16-Feb-17 Boundary agreed B084 Km 14+300 RHS acquisition boundary boundary on 16/02/2017 A004 Km 17+300 to 17+800 RHS, Request for retaining Part of government Work in progress from 18 16-Feb-17 Panagoda, Homagama walls property relocation work 20/02/2017

Requests to connect Residents near Kesbewa RDA requirements 19 20-Feb-17 rain water outlets to Accepted on 20/02/2017 B084 Km 13+800 to 14+200 explained to shop owners road drainage Resident near Kesbewa Request for time to Section 2 not yet handed- 20 21-Feb-17 Accepted by PE B084 Km 17+540 LHS demolish house over on 21/02/2017 Mr. R. Geekiyanage, 252/1, Request for soil to Referred to DS on 21 22-Feb-17 Kahatuduwa, Polgasowita RDA considering private property 22/02/2017 B084 Km 19+700 RHS Mr. S.A.I. Mahendradasa, 60A, “Udula”, Honnanthara Road, Improper utility Inspected & discussed 22 28-Feb-17 Resolved on 01/03/2017 Piliyandala shifting with PE B084 Km 14+360 LHS Mr. W.U.R. Rodrigo Contractor agreed to Request to remark 23 03-Mar-17 29, ‘Ratnasiri’ Market Lane, Remarking scheduled remark ROW on acquisition boundary Bandaragama 07/03/2017 Mr. W. Atigala Request for time to Accepted by PE on 24 03-Mar-17 14/C, Horathumbuwa, Demolition completed on demolish house 07/03/2017 Polgasowita (Lot No.217) 25 09-Mar-17 Mr. M.D. Premadasa Request to widen Culvert widening agreed Wider culvert instructed

117

# Date Complainant Description Action Taken Resolution 136, Old Police Road, culvert at Kesbewa on 10/03/2017 Kahathuduwa Junction Mr. W.A. Ariyasena Request for house Accepted by PE on 26 09-Mar-17 778, High Level Road, Panagoda, Access scheduled access 09/03/2017 Homagama (Lot Nos. 205 & 206) Mr. D.U. Wickramage Request for unsuitable Scheduled for inspection 27 15-Mar-17 6F-1 Wickrama Pedesa, Horana soil on 17/03/2017 Road, Kesbewa, Piliyandala D.A. Kumawathi Inspected with PE & New water connection 28 22-Mar-17 277/C, Horana Road, Loss of well NWS&DB on 22/03/2017 scheduled Kahathuduwa, Polgasowita B.A. Angohami New water connection Inspected with PE & 29 22-Mar-17 277/A, Horana Road, Loss of well scheduled NWS&DB on 22/03/2017 Kahathuduwa, Polgasowita Upashama Kottage Agreed to provide steps 30 24-Mar-17 26/3, Sarwodaya Road, Request for shop steps Access scheduled on 24/03/2014 Honnaththara, Kesbewa Mr. A.K. Perera Concern about land Inspected and provisions Lined drain completed on 31 28-Mar-17 59-B, Horana Road, Honnaththara, inundation made 28/03/2017 Piliyandala

118

Table 3.3 The list of complains up to 31st March 2017 for B157

Nature of Complaint / # Date Complainant Action Taken Resolution Issue Mr. O.T.M.S.E. Premarathna Cracks observed in Post 1 19-Oct-16 Referred to Contractor Monitoring in progress Km 38+940 RHS Office Building walls Principal of Lewwanduwa Contractor removed Requested removal of 2 01-Nov-16 Junior School Referred to Contractor tree Kottamba tree Km 41+810 LHS On 07/11/2017 Mrs S. Weerakoon Contractor requested to Cover slabs installed 3 01-Nov-16 Weera Niwasa, Lewwanduwa Request for access place cover slabs over On 02/12/2016 Km 41+950 RHS lined drain Mr. U.K.D. Asela Contractor requested to Cover slabs installed 4 01-Nov-16 Pallegodawatte, Lewwanduwa Request for access place cover slabs over On 02/12/2016 Km 41+980 LHS lined drain Mr. S. Kuruneru, Contractor instructed to Construction Request for retaining 5 03-Nov-16 Lewwanduwa incorporate wall in lined completed on wall Km 42+100 RHS drain 20/12/2016 Mr. J.K.P.S. Jayaneththi Contractor requested to Cover slabs installed 6 04-Nov-16 Pallegodawatte, Lewwanduwa Request for access place cover slabs over On 02/12/2016 Km 41+810 RHS lined drain Mr. H. Perera Existing access affected Contractor providing To be finally resolved 7 22-Nov-16 632, Siyathko, Lewwanduwa by raised road profile temporary access by the permanent work Km 41+750 RHS Mr. D.U. Jayaneththi Contractor requested to Cover slabs installed 8 24-Nov-16 Heel House, Lewwanduwa Request for access place cover slabs over On 02/12/2016 Km 41+250 RHS lined drain Mr. M.V. Wimaladasa Contractor requested to Awaits construction of 9 24-Nov-16 Lewwanduwa Request for access place cover slabs over lined drain Km 41+160 RHS lined drain Mr. K.A.D.K. Kodithuwakku Existing drain New lined drain under 10 25-Nov-16 Lewwanduwa temporarily blocked by Work is in progress construction Km 39+560 RHS construction Mrs. D.S.T. Samarakoon Contractor requested to Cover slabs installed 11 28-Nov-16 Shamin, Kopiwatte Request for access place cover slabs over On 21/12/2016 Km 40+530 RHS lined drain Mr. K.A.D. Sanjeewa Request for retaining Contractor instructed to Construction 12 28-Nov-16 Lewwanduwa wall incorporate wall in lined completed

119

Nature of Complaint / # Date Complainant Action Taken Resolution Issue Km 41+800 RHS drain On 25/02/2017 Mr. K.M.G. Ananda Pallegodawatte, 13 24-Dec-16 House cracks Referred to Contractor Monitoring in progress Lewwanduwa Km 41+870 RHS Mr. K.A.D.K. Kodithuwakku 14 26-Dec-16 Lewwanduwa House cracks Referred to Contractor Monitoring in progress Km 39+560 RHS Mr. K.A.D.K. Kodithuwakku Requests RFL to be RFL raised to avoid 15 03-Jan-17 Lewwanduwa Work in progress raised to flood level frequent flooding Km 39+560 RHS Mr. W. Kodithuwakku, Referred to PE as this is PE to advise whether 16 03-Jan-17 Dippita, Welipenna Request for cover slabs undeveloped land additional slabs needed Km 39+850 LHS Mr. D.P. Peiris Near Telephone Exchange, Access reinstated 17 03-Jan-17 Request for access Referred to Contractor Lewwanduwa On 20/02/2017 Km 40+635 RHS Mr. D.M. Kodithuwakku Requests RFL to be RFL raised to avoid 18 03-Jan-17 68, Main Street, Welipenna Work in progress raised to flood level frequent flooding Km 39+560 RHS Mrs. P.D. Arachchigoda Referred to PE as this is PE to advise whether 19 03-Jan-17 Pannila Request for cover slabs undeveloped land additional slabs needed Km 40+000 RHS Mrs. G.W. Raniani 20 05-Jan-17 Lewwanduwa House cracks Referred to Contractor Monitoring in progress Km 41+060 RHS Mrs. S. Jinadari Pallegodawaththa, 21 26-Jan-17 House cracks Referred to Contractor Monitoring in progress Lewwanduwa Km 41+910 LHS Mr. K.M.G. Ananda Pallegodawaththa, 22 26-Jan-17 House cracks Referred to Contractor Monitoring in progress Lewwanduwa Km 41+970 LHS Mr. D.M. Kodithuwakku Requests RFL to be RFL raised to avoid 23 26-Jan-17 Work in progress 68, Main Street, Welipenna raised to flood level frequent flooding

120

Nature of Complaint / # Date Complainant Action Taken Resolution Issue Km 38+750 RHS Mrs. S. Jinadari Pallegodawaththa, Referred to PE as this is PE to advise whether 24 26-Jan-17 Request for cover slabs Lewwanduwa undeveloped land additional slabs needed Km 41+910 LHS Mr. S.S. Manjuka Contractor instructed to Near Telephone Exchange, Request for protection 25 26-Jan-17 raise outer wall of lined Work in progress Lewwanduwa wall at well drain Km 40+635 RHS Mr. P.K. Piyadasa Request for heavy duty Scheduled requirement 26 26-Jan-17 Kopiwatta, Welipenna Work in progress cover slabs confirmed to Contractor Km 40+290 RHS Request protection Mr. J.K.D.S.C. Jayawardena Request forwarded to PE measure to avoid 27 07-Feb-17 Kopiwaththa, Welipenna for approval Pending approval inconvenience from Km 40+297 LHS culvert discharge Mr. W.A De Silva Dickhena, Access steps to be 28 08-Feb-17 Polwatta, Welipenna Request for access steps Work in progress provided Km 38+110 LHS Mr. H.M.D. Mahindapala Water tanker allocated Aluthgama Road, Horawala Dust emission Contractor took action to 29 08-Feb-17 to spray water to Junction, Welipenna minimize dust emission minimize dust emission Km 36+840 RHS Mr. T.D.S.K. Tudugala Request has been "Sithumina" near the Request to raise the forwarded to PE for 30 09-Feb-17 Telephone Exchange, lined drain wall up to Pending approval approval Lewwanduwa, Welipenna road level

Km 41+ 890 RHS Mr. D.G. ThewarapperumaNo.12, Request to place cover Agreed to place cover Completed 31 09-Feb-17 Dikhena, Welipenna slabs slabs On 20/03/2017 Km 38+115 LHS Mrs. T. Jayaneththi Request to raise the Request has been Pallegadawatte, 32 09-Feb-17 lined drain wall up to forwarded to PE for Pending Approval Lewwanduwa, Welipenna road level approval Km 41+895 RHS 33 09-Feb-17 Mr. R.D. Galabadaarachchi Request to reinstate Contractor agreed to Work in progress

121

Nature of Complaint / # Date Complainant Action Taken Resolution Issue No.170B, School Junction, damaged gate posts and reinstate the damaged Welipenna fence gate posts and fence Km 39+950 RHS Mr. I.G. Thewarapperuma, Request has been Request for vehicular No.12/1, Dikhena, Welipenna forwarded to PE for 34 20-Feb-17 access with cover slabs Pending Approval Km 38+240 LHS & Near 39/1 approval

Culvert LHS The Principal, Cracks developed in WP/MT/Lewwand-uwa building walls due to Contractor to monitor Monitoring of cracks is 35 20-Feb-17 Junior School, Lewwanduwa road construction cracks in progress Km 41+810 LHS activity Pathmendra, Gaianayaka & Request for lined drain Malkanthi Requires inspection with 36 07-Mar-17 from Culvert 37/5 to Welipenna RDA 38/1 Km 37+130 LHS A.A.M. Nazeer Request for retaining To be constructed after 37 15-Mar-17 180/2, Main Street, Welipenna wall to Bridge 39/4 lead- completing bridge work Km 38+880 RHS away drain D.S.S. Thevarapperuma Kopiwatta Junction, Request for access to Precast slabs being 38 15-Mar-17 Welipenna new building prepared at Maga yard Km 41+270 RHS U.I. Sendanayaka Request access and lined Contractor to reinstate 29, Mahawatta Junction, 39 15-Mar-17 lead-away drain beyond access but lead-away Welipenna ROW requires RDA decision Km 38+127 RHS Pradeshiya Sabawa, Request to asphalt Requires RDA 40 16-Mar-17 Mathugama nursery access consideration Km 40+380 RHS D.C. Jayaneththi Mahawatta Junction, Instruction issued to Work completed 41 16-Mar-17 Request for access steps Welipenna Contractor 0n 21/02/2017 Km 38+200 LHS M.B.M. Hazen Contractor instructed to 42 17-Mar-17 5, Nallagoda Road, Welipenna Issues with stormwater provide temporary Km 39+290 LHS protection 43 17-Mar-17 K.D.A.S. Gamini Request for access steps Instruction issued to Work in progress

122

Nature of Complaint / # Date Complainant Action Taken Resolution Issue Lewwanduwa, Welipenna Contractor Km 40+630 RHS P.V.S.S. Abagahawatta Request for separate Requires RDA 44 17-Mar-17 Lewwanduwa, Welipenna vehicle access consideration Km 41+680 RHS

123