Science Museum Group - Building ONE

Collection Storage Facility Pre-Application Enquiry - Design & Access Statement

Prepared By: Document QA: Prepared for: GWP Architecture Ref: (390)1716-GWP-A-4A-01 71-75 Shelton Street First Issue: 25.10.17 Borough of Camden Purpose: Comment London Revision: P05 WC2H 9JQ

020 7470 8770 (t)

www.gwp-arch.com [email protected] DESIGN & ACCESS STATEMENT | PAGE 2 SCIENCE MUSEUM GROUP - BUILDING ONE

Disclaimer

This document has been prepared by GWP Architecture in accordance with the instructions of their client detailed above, for the sole use of the client and may contain confidential information.

Any information provided by third parties and referred to herein has not been checked or verified by GWP Architecture, unless otherwise expressly stated in the report.

No third party may rely upon this document without the prior express written agreement of GWP Architecture.

This document is the property of GWP Architecture. Copyright is reserved by them and the drawing is issued on the condition that it is not copied, reproduced, retained, or disclosed to any unauthorised person, either wholly or in part, without the consent in writing of GWP Architecture.

project ref originator volume level type role classification name revision author checked date of issue

(390)1716 gwp 01 zz pp a 4A D&A P06 ta rt 10.11.17

© gwparchitecture 2017 www.gwp-arch.com [email protected] DESIGN & ACCESS STATEMENT | PAGE 3 SCIENCE MUSEUM GROUP - BUILDING ONE CONTENTS

DOCUMENT CONTROL SECTION 5.0 CONTENTS DESIGN PRINCIPLES - BUILDING FORM 5.1 ROOF & FORM SECTION 1.0 5.2 EXTERNAL PLANT BENEFITS INTRODUCTION 5.3 PROPOSED ELEVATIONS 5.4 3D PERSPECTIVE VIEW 1.1 CLIENT & DESIGN TEAM 1.2 INTRODUCTION SECTION 6.0 SECTION 2.0 EXTERNAL SPACES, SERVICING & ACCESS THE SITE 6.1 EXTERNAL SPACES 6.2 SERVICE ACCESS 2.1 SITE LOCATION 6.3 CAR PARKING & HIGHWAYS 2.2 SITE LOCATION PLAN 6.4 HGV LOADING 2.3 SITE PHOTOGRAPHS 6.5 REFUSE STORAGE 2.4 HISTORICAL CONTEXT 6.6 EXTERNAL LIGHTING SECTION 3.0 6.7 ACCESSIBILITY DESIGN PRINCIPLES - BUILDING LOCATION 3.1 BUILDING LOCATION & DEVELOPMENT 3.2 PROPOSED SITE SECTIONS SECTION 4.0 DESIGN PRINCIPLES - BUILDING LAYOUT 4.1 INTERNAL ACCOMMODATION DEVELOPMENT 4.2 FUNCTIONAL ADJACENCIES 4.3 PROPOSED GROUND FLOOR PLAN 4.4 PROPOSED MEZZANINE PLAN 4.5 SUPPORT SPACE LAYOUT

© gwparchitecture 2017 www.gwp-arch.com [email protected] Section 1.0

Introduction

SMG BUILDING ONE | DESIGN & ACCESS STATEMENT DESIGN & ACCESS STATEMENT | PAGE 5 SCIENCE MUSEUM GROUP - BUILDING ONE 1.1 CLIENT & DESIGN TEAM

CLIENT DESIGN TEAM

ARCHITECT PROJECT MANAGER & QUANTITY SURVEYOR

SCIENCE MUSEUM GROUP GWP ARCHITECTURE FEASIBILITY LIMITED Red Barn Gate 71-75 Shelton Street No 5 Hagley Court North Wroughton Borough of Camden The Waterfront London Level Street SN4 9LT WC2H 9JQ Brierley Hill West Midlands DY5 1XF 01793 846 229 (t) 020 7470 8770 (t) 01384 489 023 (t)

STRUCTURAL / CIVIL ENGINEER PLANNING CONSULTANT

ATKINS PEGASUS GROUP Woodcote Grove First Floor, South Wing Ashley Road Equinox North Epsom Great Park Road KT18 5BW Almondsbury Bristol 01454 66 2843 (t) BS32 4QL

01454 625945 (t) BUILDING SERVICES ENGINEER

DESCO 5 Square London W1U 3PD

0207 299 2860 (t)

© gwparchitecture 2017 www.gwp-arch.com [email protected] DESIGN & ACCESS STATEMENT | PAGE 6 SCIENCE MUSEUM GROUP - BUILDING ONE 1.2 INTRODUCTION

This document is submitted in support of a Pre-Application Enquiry for a new collections management facility to house objects for the Science Museum Group (SMG), at their site in Wroughton (SMGW).

SMGW is the large object and library and archives for the SMG. The site is not open for public access, though research visits can be arranged to use the library and archive facilities, or to view the storage collection, by appointment.

The new building will be a fit-for-purpose facility that will house and manage the SMG collection and accommodate managed public visits, support object conservation work and provide staff facilities. The building will utilise the existing vehicular access to the site and its functions will also be supported by the existing SMG operational buildings on the wider site.

The information in this statement includes a description of the proposed facility and development site, an analysis of the design approach and application drawing extracts showing the location of the facility and it’s layout.

Supporting documentation will be included with this pre-application request comprising- • Planning Statement • Heritage Statement • Landscape and Visual Impact Assessment • Ecological Report • Transport Statement

© gwparchitecture 2017 www.gwp-arch.com [email protected] Section 2.0

The Site

SMG BUILDING ONE | DESIGN & ACCESS STATEMENT DESIGN & ACCESS STATEMENT | PAGE 8 SCIENCE MUSEUM GROUP - BUILDING ONE 2.1 SITE LOCATION

Swindon

Wroughton

Overtown

Newbury

Aerial View Extract from Science Museum Group One Collection Facility Client Technical Brief - Dated August 2017

Aerial view of solar farm View of buildings A1, D4, D3 Building A1 Building D4 Motor Vehicle collection in Building D3

© gwparchitecture 2017 www.gwp-arch.com [email protected] 49

Posts

Ponds Tank Pond Path

Elm Rise Spring

4 6

Ailsa C

59

Bethen

0

Dr 7 r ain aig

66

The Ivery y

6

1

a 6 6

1

6 7

2 SNAPPS CLOSE Reservoir 8

137.2m 1

Elcombe Hall

78 ESS

9 6

y 82 9 y-b 6

La 142.6m a

Windshot

3 7 4 361 8

A 4

P

) m u ( h t a 0 161.5m 9 Markham Hill Adit 7

3a

ack r Track Pond T

75

2 9 4

Path (um) 9 Sinks

77 Issues 157.9m Issues Spreads

Issues Issues Elcombe ath (um)

P

9 7

Pond The

7 Lodge 8

163.4m

5 8

P ath (um) O

164.9m VER

T

O Issues W N HIL 159.4m Adit Pa th (um) DESIGN & ACCESS STATEMENT | PAGESluice 9 L SCIENCE MUSEUM GROUP - BUILDING ONE Pond

PRIOR'S HILL

ath (um) P 172.5m

Adit

ath (um) P ain Issues Dr

49

Posts Dr 2.2 SITE LOCATION PLAN Ponds Tank ain LB Pond MS Path

Elm Rise Spring

4 6

Ai

lsa

59

Bethen

Cr Dr 70 ain aig

66

The Ivery y

Coombe Bottom

1

6 key

a 6 6

Path (um)

1

6 7

2 SNAPPS CLOSE Reservoir 8

137.2m 1

181.1m 186.2m ath (um) Elcombe Hall

P 78 ESS 9

6 application site boundary

Shaft 2

y 8

6 a

y-b Pump 9 La 142.6m House

Windshot

4

3 7 Stables 8 A 4361 Reservoir 12a

12 P

) m u ( h t a 0 (covered) 9 Issues 161.5m Markham Hill Adit 73a site ownership boundary Overtown ack r Track Pond T Manor

Path (um) 75

Lay-by

2 9 4

Path (um) 9 Sinks

77 Issues 157.9m PROJECT LOCATION Issues Spreads Springs 187.1m Issues Issues Elcombe ath (um)

P 7 The 9

Pond Engine Shed

7 Lodge 8

Clouts Wood 163.4m

8 5

P ath (um O

164.9m VE

R The facility will be located in the northern section T White House O 201.2m ) WN kham Hill Cottages Issues 159.4m Adit HI Path (um) Langton Park (Stables)

Mar LL 1

2 Sluice T

Pond r

k c a

'S HILL

PRIOR 183.2m ath (um) P of SMGW. A feasibility Spstudyring has determined that 172.5m

ESS Adit

ath (um) P ain Issues Dr

D 203.9m r Stone El Sub Sta ain LB Issues this location takes best advantage of level ground, MS 27 24 Parsloes Barn

206.0m 23 22 Coombe Bottom

Stone Path (um)

kham Bottom Dunnocks 73 28

Mar ESS 21

The Lodge 3 2 2 proximity to services and existing road network. 181.1m rack 186.2m 1 T 67 Path (um) 185.0m LB 35 203.6m

Red Barn Cottages 3 5 Shaft Stone 59 Pump GP House 46 Solar Panels

1

1 66 2 Stables

ack 12a 5 1 Reservoir r 12

T 62

1 4 (covered)

Issues Stone 63 6

7 Dr 2 ESS 28

ain 4 0 1

8 7 22 41 Overtown 17 Manor Path (um)

Sports Facility 3

Lay-by ESS 6

5

12 4

Stone 53 58 TCB

16 188.4m 52 Stone Stone

HoneysCuoctktlaege Thorney

6 1 LOCAL CONTEXT 1 Springs Park 187.1m

48

El Sub Sta 49

3 1 A 4361 1

LB Engine Shed

4 1 Clouts Wood

Highridge Cottage Shelter

1 1 1

The Stables

5 0 1 2 1 1

8 9 201.2m White House ThSMGWe Old Store is located approximately 6.5 kilometres south of kham Hill Cottages

Langton Park (Stables) 6

The Wagon 8

ESS Mar 1

House 2

7 8

8 7

T

r

k c Ash Cottage a

5 8

2

9 7 9

183.2m Spring 197.5m the centre of Swindon and 1.4 kilometres south of the GP

ESS Tank

T

r

ack

203.9m s Stone El Sub Sta A 4361 Issue

27 intervening village of Wroughton. 24 Parsloes Barn

206.0m 23 22 Mast (Telecommunication) 195.7m Stone 192.3m

kham Bottom 73 Dunnocks 8 2 FS Mar ESS 21

The Lodge 3 2 2

rack 1 T 67 185.0m LB 35 203.6m

Red Barn Cottages 3 5 Stone 59 GP

4 6 Solar Panels

1

1 66 2

ack

5 r 1

T 62

4

1 Stone 63 6

72 Dr ESS

28 0

ain 4 1

8 7 22 41 The site falls within the North Wessex Downs Area of 17

Signal Square Sports Facility 6

ESS 3

5

12 4

Stone 53 58 TCB

16 188.4m 52 Stone Stone

Science Museum Honeysuckle Thorney Cottage

6 1 1 Outstanding Natural Beauty. Park

48

196.0m 4

El Sub Sta 9

3 1

A 4361 1

LB

4 1

Highridge Cottage Shelter

1 1 1

The Stables

5 0 1 2 1 1

8 9

Reservoir The Old Store

6 (covered) The Wagon ESS 8

House

7 8

8 7

Ash Cottage

5 8

2 9 7 Wroughton Airfield 9 (dis)

197.5m Def The single access point to the site is from the north- GP

Tank

T

r

ack west via the A4361 (Avebury-Wroughton) road, which, A 4361

Mast (Telecommunication) 195.7m 192.3m

FS C Baulk in turn, is within close proximity and well connected to

bothBS Junction 15 and 16 of the M4 motorway. Signal Square 181.2m Stone

2

A & CP Bdy 1

U Merlin Cottages Co Const, Science Museum

Dr ain 196.0m

Stone Solar Farm

Tk F

Reservoir (covered) SITE CONTEXT Stone

ESS Wroughton Airfield Drain

Stone (dis) The main site is secured with a perimeter fence. The site Def

ESS

Stone Chy 187.1m is manned 24 hours a day, 7 days a week from Red

Dr

ain TCB C Baulk

181.4m

FS

y

Barn Gatehouse, in the north west of the site. y-b

La

Stones

BS

n i a

r D 181.2m Stone

2

A & CP Bdy 1

U Merlin Cottages

Co Const,

Stone

ain

Dr Drain Def The development plot is predominantly flat improved Stone Solar Farm Track

Tk F

Ponds

Tk F Stone

1 Stone grassland, bordered by disused concrete runways. 2 Stone Hackpen ESS Cottages ack r Pond T Drain

Stone Stones

Stone Track 193.5m The tarmac and concrete runways stretch to the edgesStone Issues

Def Path (um) ESS Barbury

Stone Boundary Cottages Stone Chy 187.1m

of the plot and are connected by smaller perimeter Dr

ain

2 1 TCB

Stone Stone 181.4m

ESS FS

y

y-b Tk F

La 1 Dairy 2 roadways. The recent development of 73 hectares of House

Stones

New Cottages 178.0m

Stone

n i

a

r

3 Hackpen D 4 The Ark Farm Midge's Close solar panels now covers the western and southern parts

187.1m Tanks

Mulberry House WB Stone ain

Dr House Def

Downs View ack Stone Tr of the main site. Track

White Cottage Uffcott A F T

Def Pond Ponds

Tk F

1 Stone

2 Stone ESS Hackpen Cottages k ac r Pond T LB

Stones

Stone Track 193.5m

Stone

Issues

Def Path (um) ...... Barbury Down House

Boundary Cottages Stone

This drawing is the property of GWP Architecture. Copyright is reserved by them and the Contractors must verify all dimensions at the job before commencing any work or making

2 1

Stone drawing is issued on the condition that it is not copied, reproduced, retained, or disclosed to shop drawings. Do not scale off drawing. Do not take digital dimensions from this drawing. Stone any unauthorised person, either wholly or in part, without the consent in writing of GWP Written dimensions should be taken. Any discrepancies to be reported to the Architect. The ESS One Collection

Tk F Name (390)1716-GWP-01-01-DR-A-(SK)-0001 Architecture. design is subject to the following: 1 Dairy 0 100m 200 300 400 500 2 House

New Cottages 178.0m All drawings and specifications should be read in conjunction with the project health and - Land Registry Confirmation - Full Structural Review N Scale A3/1:10,000 Revision / StatuStonse 02 / S

safety plan, any possible conflicts should be presented to the Planning Coordinator. - Planning Approval - Topographical Information 3 Hackpen 4 The Ark Farm - Review of Easements and Covenants - Rights of lights Issues Scale Midge's Close Site Location Plan All work to be carried out in accordance with current Building Regulations. - Building Regulations Approval / Fire Engineering - 1:10,000 @A3 187.1m Drawn/Checked TA / RT Tanks Date of Issue 15.09.17 A R C H I T E C T U R E Mulberry House /Volumes/Data/CAD/(390)1716 The Science MuseWuB m/A_Architects_(GWP)/Model/(390)1716-GWP-01-XX-M3- Wiltshire House A-One_Collection.pln

Downs View Stone Track

White Cottage Uffcott

Def Pond

ESS

© gwparchitecture 2017 LB www.gwp-arch.com D R [email protected] ......

This drawing is the property of GWP Architecture. Copyright is reserved by them Contractors must verify all dimensions at the job before commencing any work or and the drawing is issued on the condition that it is not copied, reproduced, making shop drawings. Do not scale off drawing. Do not take digital dimensions retained, or disclosed to any unauthorised person, either wholly or in part, from this drawing. Written dimensions should be taken. Any discrepancies to be SMG Building ONE without the consent in writing of GWP Architecture. reported to the Architect. The design is subject to the following: Name (390)1716-GWP-01-XX-DR-A-(PA)-0001

All drawings and specifications should be read in conjunction with the project - Land Registry Confirmation - Full Structural Review 0 100m 200 300 400 500 health and safety plan, any possible conflicts should be presented to the Planning - Planning Approval - N Scale A3/1:10000 Rev / Status P05 / S Coordinator. Topographical Information Site Location Plan - Review of Easements and Covenants - Rights of lights Issues Dr/Checked TA / RT Date of Issue 15.09.17 All work to be carried out in accordance with current Building Regulations. - Building Regulations Approval / Fire Engineering Scale - 1:10,000 @A3 BIM Server: BIMServer-HP - BIM Server 20/One Collection (390)1716-GWP-01-XX-M3-A DESIGN & ACCESS STATEMENT | PAGE 10 SCIENCE MUSEUM GROUP - BUILDING ONE 2.3 SITE PHOTOGRAPHS

1.

3

2 2. 5

Barbury Castle VP01

4 3.

Go Kart Parking PRoW

4.

Ridgeway Red Gate B October 2017 P16-1396_02 Viewpoint Panoramas

October 2017 P16-1396_02 Viewpoint Panoramas 5.

1

Go Kart Entrance SE Offices www.gwp-arch.com © gwparchitecture 2017 October 2017 P16-1396_02 Viewpoint Panoramas [email protected] October 2017 P16-1396_02 Viewpoint Panoramas

Entrance Road

Exit Road

October 2017 P16-1396_02 Viewpoint Panoramas DESIGN & ACCESS STATEMENT | PAGE 11 SCIENCE MUSEUM GROUP - BUILDING ONE 2.4 HISTORICAL CONTEXT

WROUGHTON AIRFIELD The site was established in 1940 as an RAF airfield and consists of a number of runways and aircraft hangars. The hangars vary in construction: there are four of the ‘L’ type ‘Blister’ hangars (a steel framework with a concrete skin), four of the ‘D’ type hangars (steel reinforced concrete with an arching roof), and two ‘C’ type hangar (steel framework with an external cladding), within the land owned by SMG.

The Ministry of Defence commenced disposal of this site in 1979.

SMG AT WROUGHTON The Science Museum Group took ownership of the 545-acre site in 1979, and Aerial photograph taken by the US Army Air Force in 1944 No 15 Maintenance Unit RAF Wroughton - 1968/69 has used it since this time as the storage facility for the largest objects of the Science Museum Group collections.

Over 35,000 3D and 500,000 2D objects from the national collection are currently stored on site, within nine former aircraft hangars and a purpose- built store. The collection ranges from the first hovercraft to MRI scanners, and science publications to (de-activated) nuclear missiles. The collections here are particularly notable for the extensive collection of very large aircraft, road transport vehicles, agricultural machinery and industrial collections.

In 1994 the Museum opened a new purpose-built facility at Wroughton, providing an environmentally controlled building for the storage of objects. Boeing B17 at Wroughton Air Show - 1993 Wroughton Air Show - 1992 Since 2000 the freehold of the majority of the site has been owned by Board of Trustees of the Science Museum.

Latterly SMG has undertaken a number of projects on site to refurbish hangars, construct award-winning innovative storage, work with universities and industry in research and development, and develop a large scale solar farm for electricity supply into the national grid. These projects along with extensive biodiversity enhancements have helped define the vision for SMGs long term use of the site.

The site is currently not open to the public due to the increased risks presented by the failing 1940s infrastructure and the lack of circulation space due to compression of the stores to enable additional collections to be accommodated. SMG large object storage within Aircraft Hangars Environmentally controlled purpose built storage facility

© gwparchitecture 2017 www.gwp-arch.com [email protected] Section 3.0

Design Principles - Building Location

SMG BUILDING ONE | DESIGN & ACCESS STATEMENT DESIGN & ACCESS STATEMENT | PAGE 13 SCIENCE MUSEUM GROUP - BUILDING ONE 3.1 BUILDING LOCATION & DEVELOPMENT

The location for the new collections management facility has been identified through assessment of access requirements for the building - both from the main D4 entrance to site (utilising existing D4 roadways and former runways) and in the context of the SMG Runway 22 operational facilities on the wider site. Consideration has also been Runway 22 given to the orientation of the building, its proximity to existing services and the topography of

Runway 22

the site. This evaluation has led / Runway Access Road to the development site running Runway / Runway Runway / Runway Access Road perpendicular to the former Access Road External Plant Towers runway as shown. ExternalExternal Plant Towers Towers Grasscrete Plant Access / Service Route A1 GrasscreteGrasscrete Plant Access / Ser vicePlant Route Access / Service Route A1 289 Meters Car park Future Expansion CarCar parkpark Space 6,000Future m2 Expansion Future Expansion Space 91.5 Meters 6,000 mSpace2 6,000 m2 Service Yard

Servicevice Yard Yard Waste Store Building ONE Waste Store

Waste Store

Site Layout Proposal

© gwparchitecture 2017 www.gwp-arch.com [email protected] DESIGN & ACCESS STATEMENT | PAGE 14 SCIENCE MUSEUM GROUP - BUILDING ONE 3.2 PROPOSED SITE SECTIONS Key Plan

Key Plan D3

D4 A

A1 A

B

B

A1 Store D4 Hangar D3 Hangar

Approx. 13m Approx. 16m Approx. 12m Approx. 4.15m Approx. 13m Extent of mezzanine structure Approx. 12m

access grass car parking building A1 A1 access road margin Proposed Building ONE facility (approx. 289m overall building length) & entrance runway grass / open area

access grass car parking building A1 A1 access road margin Proposed Building ONE facility (approx. 289m overall building length) & entrance runway grass / open area

SiteS itSectione Secti oAn A 1:12501:12 5@0 @A3 A3

A1 Store D4 Hangar

Approx. 13m Approx. 16m Approx. 12m

Approx. 12m Extent of mezzanine structure

Proposed Building ONE facility service runway grass / open area (approx. 91.5m overall building width) zone grass / open area

Proposed Building ONE facility service runway grass / open area (approx. 91.5m overall building width) zone grass / open area

SiteS itSectione Secti oBn B 1:12501:12 5@0 @A3 A3

www.gwp-arch.com ©. .gwpa...... rchitecture...... 2017...... [email protected] This drawing is the property of GWP Architecture. Copyright is reserved by them Contractors must verify all dimensions at the job before commencing any work or and the drawing is issued on the condition that it is not copied, reproduced, making shop drawings. Do not scale off drawing. Do not take digital dimensions ...... retained, or disclosed to any unauthorised person, either wholly or in part, from this drawing. Written dimensions should be take...... n. Any discrepancies to be ...... SMG Building ON...... E without the consent in writing of GWP Architecture. reported to the Architect. The design is subject to the following: Name (390)1716-GWP-01-XX-DR-A-(PA)-0008 This drawing is the property of GWP Architecture. Copyright is reserved by them Contractors must verify all dimensions at the job before commencing any work or and theAl l drawingdrawing sis aissuednd sp eoncifi thecat ioconditionns should that be rite aisd not in ccopied,onjunct ioreproduced,n with the projemakingct - shopLand drawings. Registry C oDonfi notrma scaletion off drawing. Do not- Fu ltakel Stru digitalctural Rdimensionseview 0 10m 20 30 40 50 retained,he aorlth disclosedand safet yto p laanyn, aunauthorisedny possible c on flperson,icts sho ueitherld be pwhollyresen teord tino tpart,he Plannifromng this- P drawing.lanning A pWrittenproval dimensions should be taken. Any discrepancies to be - N Scale A3/1:1250 Rev / Status P06 / S SMG Building ONE withoutC theoor consentdinator. in writing of GWP Architecture. reportedTo ptoo gthera pArchitect.hical Info Trhema designtion is subject to the following: Name (390)1716-GWP-01-XX-DR-A-(PA)-0008 Proposed Site Sections - Review of Easements and Covenants - Rights of lights Issues 0 10m 20 30 40 50 Dr/Checked TA / RT Date of Issue 24.10.17 All drawingsAll wo rkand to bspecie carfircationsied out shouldin acco rbeda nreadce w iinth cconjunctionurrent Build iwithng R ethegu laprojecttions. - Land -Registry Buildin gCon Refigrmationulations Approval / F i r e E n -g iFullnee Structuralring Review Scale - 1:1250 @A3 health and safety plan, any possible conflicts should be presented to the Planning - Planning Approval - N Scale BIM Server: BIMSA3/1:1250erver-HP - BIM Server 20/RevOne C o/ll eStatusction (390)1716-P02GWP-01 -/XX -MS3-A Coordinator. Topographical Information Proposed Site Sections - Review of Easements and Covenants - Rights of lights Issues Dr/Checked TA / RT Date of Issue 24.10.17 All work to be carried out in accordance with current Building Regulations. - Building Regulations Approval / Fire Engineering Scale - 1:1250 @A3 BIM Server: BIMServer-HP - BIM Server 20/One Collection (390)1716-GWP-01-XX-M3-A Section 4.0

Design Principles - Building Layout

SMG BUILDING ONE | DESIGN & ACCESS STATEMENT DESIGN & ACCESS STATEMENT | PAGE 16 SCIENCE MUSEUM GROUP - BUILDING ONE 4.1 INTERNAL ACCOMMODATION LAYOUT

MEZZANINE LEVEL 2 The layout of the internal space has been defined by the building 9,000 m orientation and the operational adjacencies for the functional spaces 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 within the superstructure. These rooms have been optimised to provide External Plant Gantry External Plant Gantry External Plant Gantry External Plant Gantry External Plant Gantry (Mezz AHUs) (Mezz AHUs) (Mezz AHUs) (Mezz AHUs) (Mezz AHUs) high quality collections management services, maximise the storage A A

Conditioned Store capability of the building and minimise operational costs. 850 m2

Stairs

Mezzanine Store (Low Bay) 2 45,000 8,200 m

B B

7,200 7,200 7,200 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41

202.5 metres

GROUND FLOOR 26,000 m2

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41

Cold Proposed Proposed AHU AHU water Electrical substation/ Boiler Sprinklers Sprinklers Chillers Chillers pump HV/LV Switch Plant A A

Collections Study 200 m2

Entrance Lobby Store (Low Bay) 2

45,000 8,370 m Toilets Welfare 30 m2 70 m2

Conservation Laboratory 200 m2 Photography Studio 160 m2 B B Conservation Workshop 91.5 metres 500m2

Inward Store (High Bay) Transit 15,150 m2 45,000

Transit Outward Storage Transit

Radioactive/High Freezer Explosives Store C C

7,200 7,200 7,200

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41

289 metres

© gwparchitecture 2017 www.gwp-arch.com [email protected] DESIGN & ACCESS STATEMENT | PAGE 17 SCIENCE MUSEUM GROUP - BUILDING ONE 4.2 FUNCTIONAL ADJACENCIES

conditioned KEY: store object staff mezzanine store (low bay) stais / lift public external glazing pedestrian entrance vehicle entrance rooflights Mezzanine level

collections study

entrance store (low bay)

wc welfare

conservation laboratory photography studio

store (high bay) conservation workshop

freezer inward loading area transit

transit storage outward transit

Ground Floor

© gwparchitecture 2017 www.gwp-arch.com [email protected] DESIGN & ACCESS STATEMENT | PAGE 18 SCIENCE MUSEUM GROUP - BUILDING ONE 4.3 GROUND FLOOR PLAN

0007 NE

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41

Z1 Z1 A B B C D E Z Z A A

A1 14 A1

A2 A2 2

A3 A3 3 4

A4 A4

5 A5 A5 GROUND FLOOR 26,000 m2 6 B B S E N W 0 7 0 7 1 7 B1 B1

B2 B2 9 10

a p r o x . 9 1 5 m O v e l B u i d n g W t h B3 B3

B4 B4 11 12

B5 B5 8 13 C C

1j 1h 1g 1f 1e 1d 1c 1b 1a 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32

SW 0007

approx. 289m Overall Building Length

Ground Floor GA Plan 1:1000 @ A3

NOTES

Room Types: External Plant Allocation: Transit storage Extents 1. Object Store (23,534m2) 8. Freezer (116m2) A. Proposed Sprinkler

2. Entrance Lobby (75m2) 9. Inward transit (250m2) B. Chiller compound

3. Unisex & DDA toilets (30m2) 10. Loading bay (320m2) C. Chilled Water Pump

4. Staff Welfare Suite (70m2) 11. Transit storage (260m2) D. Electrical Sub Station/HV/LV Switch rooms

5. Conservation Laboratory (200m2) 12. Outward transit (200m2) E. Boiler house

6. Photography Studio (160m2) 13. Special Collections Store (160m2) ALL PLANT LOCATIONS TO BE COORDINATED WITH BUILDING SERVICES ENGINEER 7. Conservation Workshop (500m2) 14. Collections Study (200m2)

......

This drawing is the property of GWP Architecture. Copyright is reserved by them Contractors must verify all dimensions at the job before commencing any work or and the drawing is issued on the condition that it is not copied, reproduced, making shop drawings. Do not scale off drawing. Do not take digital dimensions retained, or disclosed to any unauthorised person, either wholly or in part, from this drawing. Written dimensions should be taken. Any discrepancies to be SMG Bwww.uildigwp-archng ONE .com © gwparchitecture 2017without the consent in writing of GWP Architecture. reported to the Architect. The design is subject to the following: Name (390)1716-GWP-01-GF-DR-A-(PA)-0004

All drawings and specifications should be read in conjunction with the project - Land Registry Confirmation - Full Structural Review 0 10m 20 30 40 50 [email protected] health and safety plan, any possible conflicts should be presented to the Planning - Planning Approval - N Scale A3/1:1000 Rev / Status P04 / S Coordinator. Topographical Information Proposed Ground Floor Plan - Review of Easements and Covenants - Rights of lights Issues Dr/Checked TA / RT Date of Issue 24.10.17 All work to be carried out in accordance with current Building Regulations. - Building Regulations Approval / Fire Engineering Scale - 1:1000 @A3 BIM Server: BIMServer-HP - BIM Server 20/One Collection (390)1716-GWP-01-XX-M3-A DESIGN & ACCESS STATEMENT | PAGE 19 SCIENCE MUSEUM GROUP - BUILDING ONE 4.4 MEZZANINE PLAN

0006 NE

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41

Z1 Z1 F F F F F F Z Z A A

16 A1 A1

A2 A2 15 MEZZANINE FLOOR A3 9,000 m2 A3 17 A4 A4

A5 A5

B B S E N W 0 6 0 6

B1 B1

B2 B2

B3 B3

B4 B4

B5 B5

C C

SW 0006

1j 1h 1g 1f 1e 1d 1c 1b 1a 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32

Mezzanine Floor GA Plan 1:1000 @ A3

NOTES

Room Types: External Plant Allocation: Void space 15. Mezzanine lobby (65m2) F. Air Handling Units

16. Conditioned Store (904m2) ALL PLANT LOCATIONS TO BE COORDINATED WITH 17. Mezzanine Store (Low Bay) (8,200m2) BUILDING SERVICES ENGINEER

......

This drawing is the property of GWP Architecture. Copyright is reserved by them Contractors must verify all dimensions at the job before commencing any work or and the drawing is issued on the condition that it is not copied, reproduced, making shop drawings. Do not scale off drawing. Do not take digital dimensions retained, or disclosed to any unauthorised person, either wholly or in part, from this drawing. Written dimensions should be taken. Any discrepancies to be SMG Building ONE © gwparchitecture 2017without the consent in writing of GWP Architecture. reported to the Architect. The design is subject to the following: Name (390)1716-GWP-01-M1-DR-A-(PA)-0005 www.gwp-arch.com 0 10m 20 30 40 50 All drawings and specifications should be read in conjunction with the project - Land Registry Confirmation - Full Structural Review [email protected] health and safety plan, any possible conflicts should be presented to the Planning - Planning Approval - N Scale A3/1:1000 Rev / Status P04 / S Coordinator. Topographical Information Proposed Mezzanine Plan - Review of Easements and Covenants - Rights of lights Issues Dr/Checked TA / RT Date of Issue 24.10.17 All work to be carried out in accordance with current Building Regulations. - Building Regulations Approval / Fire Engineering Scale - 1:1000 @A3 BIM Server: BIMServer-HP - BIM Server 20/One Collection (390)1716-GWP-01-XX-M3-A DESIGN & ACCESS STATEMENT | PAGE 20 SCIENCE MUSEUM GROUP - BUILDING ONE 4.5 SUPPORT SPACE LAYOUT

Collections Entance Welfare Conservation Conservation Conditioned Stair Mezzanine Store 2 Study Lobby 70 m Laboratory Workshop Store Lobby (Low Bay) 2 2 2 200 m 200 m 500 m 850 m2 8,200 m2

15,250 5,900 7,900 16,000 11,400 9,000 12665 12,665 Unisex 14,500 WCs 1,800

Lift DDA WC 6,000 43,300 28,700 Store (Low Bay) 8,370 m2 Photo Studio 160 m2 58,000

15,250

Ground Floor

Mezzanine Level

© gwparchitecture 2017 www.gwp-arch.com [email protected] Section 5.0

Design Principles - Building Form

SMG BUILDING ONE | DESIGN & ACCESS STATEMENT DESIGN & ACCESS STATEMENT | PAGE 22 SCIENCE MUSEUM GROUP - BUILDING ONE 5.1 ROOF & FORM

ROOF & CLADDING

- Industry standard approaches to design of this building are essential to produce a cost effective structure for SMG.

- Constructed around a portal frame, a shallow sloping roof will fall from a ridge height of approximately 12m to an external eaves of approximately 8m.

- Longitudinal walls will be clad in the same fabric as the roof and wrap over the south-west and north- east elevations, Gable walls will be similar in colour and nature.

- The roof and external walls will likely be sinusoidal cladding in muted colours. Designed to blend in with the ground from the elevated viewpoints surrounding the site and minimise its visual impact.

- Highly focused proprietary warehouse materials are being used to create construction efficiencies, drive sustainability and maximise storage capacity.

© gwparchitecture 2017 www.gwp-arch.com [email protected] DESIGN & ACCESS STATEMENT | PAGE 23 SCIENCE MUSEUM GROUP - BUILDING ONE 5.2 EXTERNAL PLANT STRATEGY

REQUIREMENTS

This building is being designed for the storage of collections protected under the National Heritage Act (1983). SMG has specific requirements to meet the needs of the collection. These include (amongst other elements): humidity control and an air-tight structure to provide an internal condition meeting the brief specifications; good levels of security; fire detection and minimised risk of leaks/water ingress. By installing the plant externally to the main structure of the building the following benefits are derived:

ACCESS TO PLANT

- Externally mounted plant and services can be easily installed, accessed, maintained and replaced from the perimeter of the building. - This reduces the need for maintenance staff to enter the main building to maintain & service plant. - Improves security of the collection by reducing the number of personnel who access the building for maintenance.

EQUIPMENT, PERFORMANCE & SAFETY

- Air handling units mounted externally have a ready supply of fresh air for intake, reducing the quantity of ducting and improving their performance. - Minimises the number of penetrations to the building envelope, which improves the performance of the building envelope. - Maximises the internal space for the storage of the collections. - Reduces risk of damage to the collection caused by potential leaks & faults of the equipment, minimises fluctuations in humidity and helps to manage vermin and pest control. - External plant is naturally ventilated – protecting against unwanted heat gain within the building and reducing the need for additional ventilation. - Limits the risk of a fire inside the main store should a problem with the plant arise, improving safety for the objects and people. Removes the requirement for fire rated internal plant spaces / compartmentation of plant spaces. - Fire escape from the internal collection stores and plant areas are kept separate. Direct fire escape for maintenance personnel from external plant areas.

© gwparchitecture 2017 www.gwp-arch.com [email protected] DESIGN & ACCESS STATEMENT | PAGE 24 SCIENCE MUSEUM GROUP - BUILDING ONE 5.3 ELEVATIONS

1 2

South-West Elevation 1:750 @ A3

1 2 7

North-East Elevation 1:750 @ A3

KEY

1 Roof Covering 1 2 3 4 8 5 6 7 7 1 2 2 Facade Cladding 3 Loading Door 4 Personnel Door 5 Windows 6 Pedestrian Entrance 7 Plant Gantry South-East Elevation North-West Elevation 8 Look-a-like panel band 1:750 @ A3 1:750 @ A3

......

This drawing is the property of GWP Architecture. Copyright is reserved by them Contractors must verify all dimensions at the job before commencing any work or and the drawing is issued on the condition that it is not copied, reproduced, making shop drawings. Do not scale off drawing. Do not take digital dimensions retained, or disclosed to any unauthorised person, either wholly or in part, from this drawing. Written dimensions should be taken. Any discrepancies to be SMG Building ONE without the consent in writing of GWP Architecture. reported to the Architect. The design is subject to the following: Name (390)1716-GWP-01-XX-DR-A-(PA)-0007

All drawings and specifications should be read in conjunction with the project - Land Registry Confirmation - Full Structural Review 0 10m 20m Scale A3/1:750 Rev / Status P06 / S health and safety plan, any possible conflicts should be presented to the Planning - Planning Approval - www.gwp-arch.com © gwparchitecture 2017 Coordinator. Topographical Information Proposed Elevations - Review of Easements and Covenants - Rights of lights Issues Dr/Checked TA / RT Date of Issue 24.10.17 All work to be carried out in accordance with current Building Regulations. - Building Regulations Approval / Fire Engineering Scale - 1:750 @A3 [email protected] BIM Server: BIMServer-HP - BIM Server 20/One Collection (390)1716-GWP-01-XX-M3-A DESIGN & ACCESS STATEMENT | PAGE 25 SCIENCE MUSEUM GROUP - BUILDING ONE 5.4 3D PERSPECTIVE VIEW

© gwparchitecture 2017 www.gwp-arch.com [email protected] Section 6.0

External Spaces, Servicing & Access

SMG BUILDING ONE | DESIGN & ACCESS STATEMENT DESIGN & ACCESS STATEMENT | PAGE 27 SCIENCE MUSEUM GROUP - BUILDING ONE

6.1 EXTERNAL SPACES HGVs will access the facility via the service yard. A large insulated sectional roller loading door is proposed on the south-east elevation, allowing delivery vehicle to drive into an air lock area The external spaces surrounding the facility will mainly be located in front of the South-East located within the building. Within this airlock, the delivery vehicles will be loaded / unloaded via entrance elevation and consist of the following spaces: forklift, pallet truck or by hand (dependant on object size). Level access will provided to allow the vehicles to drive into the airlock. Whilst deliveries are expected to be infrequent, the service yard • car parking facilities for staff and visitors allows sufficient space for HGV parking in the case that HGVs are queued / waiting for the air lock • service yard for object delivery vehicles and service vehicles to be cleared to allow for vehicle access. • pedestrian access routes • limited external grassed areas The existing access routes and proposed service yard are sufficiently sized for two 18-tonne Vs.HG The proposed loading door and airlock space are also sufficiently sized for access for an 18-tonne It is proposed that these spaces will be developed within the footprint of the existing runway to the HGV, with space for loading / unloading. South-East of the building. 6.5 REFUSE STORAGE 6.2 SERVICE ACCESS A covered refuse storage area is proposed, adjacent to the grasscrete service route and the Service (including vehicles) access to the building will be via the existing site entrance at Red Barn existing runway access, for waste storage and collection. The storage area consists of space for Gate. People will be required to sign in at the main gate, before accessing the site through a four Euro bins, as well as space for loading and un-loading two 18 cubic yard skips secure barrier, in line with current site operations. 6.6 EXTERNAL LIGHTING Service vehicle will be able to access the service yard at the front of the facility, with sufficient space for HGV turning and parking. A Grasscrete (or similar) service route will be provided Generally the service illuminance for the external lighting installation will be in accordance with parallel to the north-east facade of the building, providing access for service vehicles to plant the society of light and lighting (SLL) codes for lighting and with particular reference to the CIBSE gantries. lighting guide LG6: the outdoor environment.

6.3 CAR PARKING & HIGHWAYS Careful consideration will be given to the dark skies nature of the site, reducing light spill and the duration that lighting operates. Vehicle access to the site will be in line with current operations - signing in via the Red Barn Gate All luminaires will be of external quality, suitable for the installed environment and be of robust and along the existing vehicular routes. Car parking is proposed adjacent to the pedestrian design and vandal resistant. Final selection of these luminaires will be in accordance with the entrance on the south-east side of the building. Car parking is provided predominantly for architect’s requirements. building staff. Visitors accessing the facility by appointment will park at the existing visitor area on site, before being escorted to the proposed building. Each escape door will be provided with emergency lighting externally above or adjacent to the door. A total of 12no parking spaces are proposed, including 2no DDA spaces. External lighting will be controlled via photoelectric cell and central time clock, where applicable 6.4 HGV LOADING motion sensing external systems will be used.

HGV access for the delivery and collection of objects to be stored in the facility will be in line with current site operations and as noted in the Service Access section (6.2).

© gwparchitecture 2017 www.gwp-arch.com [email protected] DESIGN & ACCESS STATEMENT | PAGE 28 SCIENCE MUSEUM GROUP - BUILDING ONE

6.7 ACCESSIBILITY

The proposals will provide an inclusive environment for the widest range of users possible within the constraints of the project. The design includes the following key features which will facilitate and enhance disabled users experience of the building:

• Provision of accessible parking bay

• Level pedestrian access walkways to the building allow two way wheelchair use

• Pedestrian entrance with level thresholds to allow access for wheelchair users into the building.

• Fire escape exits with ramped access to current standards

• Provision of an accessible WC, in line with Approved Document M standards

• Provision of fixed induction loops to relevant spaces

• All access and egress routes will be step free, limiting the need for assisted evacuation

• Provision of a personnel lift, with sufficient space for wheelchair access (including assistance)

• Provision of disabled refuge and call point within the main stair lobby.

© gwparchitecture 2017 www.gwp-arch.com [email protected] LEEDS LONDON

bracken house 71-75 shelton street 1 lidgett lane borough of camden leeds london ls8 1pq wc2h 9jq

0113 266 6044 (t) 020 7470 8770 (t)

www.gwp-arch.com www.gwp-arch.com [email protected] [email protected]

CARDIFF MANCHESTER

15TH floor 46 barton arcade brunel house deansgate 2 fitzalan road manchester cardiff, cf24 0eb m3 2bh

02921 303 322 (t) 0161 962 4882 (t)

www.gwp-arch.com www.gwp-arch.com [email protected] [email protected]