Quick viewing(Text Mode)

Llangadog • Flooding from Afon Sawdde, Afon Bran and Afon Tywi Around Llangadog

Llangadog • Flooding from Afon Sawdde, Afon Bran and Afon Tywi Around Llangadog

CCC Flood Risk Management Plan

9.3.34 Llangadog • Flooding from Afon Sawdde, Afon Bran and Afon Tywi around Llangadog. Council(s): Llangadog Llanddeusant Policy Units in Ward There are no Policy Units identified in this Ward. Councillor: Andrew James Population: 1,912 people Area: 192.50 km2 Count Table (see Maps 1 & 2 below) Population Density: 10 people/km2 Criteria Total at-risk Dwellings Community Area Description Property affected Services Llangadog Ward is a vast rural area on ’s western Count border between the and the foothills of the High Risk 67 11 0 Beacons National Park. It contains the town of Llangadog with smaller settlements including Bethlehem, Capel , Felindre, Medium Risk 111 25 1 Llanddeusant, Myddfai, Pont Meredith & Twynllanan. The general geography of the area consists of the steep mountains Low Risk 248 56 2 and moorlands of the National Park leading to the Breakdown by Policy Unit refer to Appendix E. pastoral farmland and several woodland areas. Includes the two tallest peaks in Carmarthenshire, Picws Du and Fan Foil. The area contains numerous small tributaries of the main River Tywi. Other risk management authorities The Main Rivers are the Afon Tywi, Afon Bran and Afon Sawdde. DCWW has identified flood risks at the following locations: • Llangadog Flood History • Myddfai • Glanrhyd Railway Bridge collapse at Afon Tywi in 1987 leading to loss of life. NRW will continue to take the lead and manage the flood risk from • Flooding at Nant Dyrfal east of Llangadog. the Rivers Afon Tywi, Bran and Sawdde. • Repeated flooding to property and council asset at Afon Llechach.

• Flooding to Cilgwyn Manor from Afon Ydw.

P4.0 For Consultation November 2019 Page 164 CCC Flood Risk Management Plan

P4.0 For Consultation November 2019 Page 165 CCC Flood Risk Management Plan

P4.0 For Consultation November 2019 Page 166 CCC Flood Risk Management Plan

Llangadog - Delivery Plan Measure Description Priority Timescale Cost M22 Investigate options to reduce Med Med Med The following summarises actions we propose to manage flood risk to properties within local flood risk to an acceptable level within the community. the overall community M31 Investigate opportunities to Med Med Med reduce runoff from adjacent moorland / hillsides M34 Work with DCWW to better Med Ongoing Low Prevention Protection understand and manage flood risk from surface water 1 2 and sewers in highlighted locations M42 Raise awareness of flood risk Med Med Low and support preparation of Recovery and Community Flood Plans if Preparedness Review applicable 2 1 M43 Working with NRW to raise Med Med Low awareness of flood risk from the Main Rivers M51 Countywide recovery plans Med Ongoing Low are in place. These will be triggered when appropriate

P4.0 For Consultation November 2019 Page 167