Bond Update: January 26, 2021 How it started

Citizens Bond Advisory Committee (CBAC) Thank you, Humble ISD Community!

Steps Factors that impact construction timelines:

● how imminently critical the need ● the volume and complexity of projects that can be effectively managed simultaneously ● economies of scale that can be achieved by bundling similar projects when doing so maximizes resources and is practical ● the amount of bonds that can be issued at one time without increasing Humble ISD’s tax rate ● minimization of interruption to the campus environment How it’s going

North Transportation Center

North Agricultural Center

Kingwood MS

Lakeland ES

Autumn Creek ES

Middle School #10

Humble HS

Quest HS Groundbreakings No Tax Increase COVID Economy = Maximized Opportunities Completed - 2019

Built secured visitors’ HVAC entries for all schools that did not have them KHS Visitors Entry Updated alarm systems, HVAC and more

Added field turf at AHS, KHS, KPHS, SCHS (HHS uses Turner Stadium)

Field Turf Completed - 2019 Security & Technology

Increased quality and quantity of security cameras

Improved technology connectivity, reliability, and security by improving bandwidth, wifi access, and the firewall

Completed - 2019 Security & Technology Coming Soon - 2022 Police Department & Emergency Operations Center Expansion Completed - 2018 West Lake Middle School-Bond 2008 Completed - 2020 Centennial Elementary-Bond 2008 Completed - 2020 Centennial Elementary-Bond 2008 Completed - 2020 Centennial Elementary-Bond 2008 Completed - 2020 Centennial Elementary-Bond 2008 Completed - 2020 Centennial Elementary-Bond 2008 Coming Soon - 2021 Autumn Creek Elementary Coming Soon - 2021 Autumn Creek Elementary Coming Soon - 2021 Autumn Creek Elementary Coming Soon - 2021 Autumn Creek Elementary Coming Soon - 2021 North Transportation Center Coming Soon - 2021 North Transportation Center Coming Soon - 2021 North Transportation Center Coming Soon - 2021 Additions

AHS Classroom Addition, Third Gym, Weight Room Coming Soon - 2021 Atascocita High School Additions Coming Soon - 2022 Middle School #10 Coming Soon - 2022 Middle School #10 Completed - 2020 Middle School Gym Floors

Wood gym floors instead of sport court (AMS, CMS, HMS, RMS, TMS, WMS) Renewal: Coming Soon - 2021 Renewal: Coming Soon - 2021 Coming Soon - 2021 Renewal: Coming Soon - 2021 Lakeland Elementary Renewal: Coming Soon - 2021 Renewal: Coming Soon - 2021 Renewal: Coming Soon - 2021 Renewal: Coming Soon - 2021 Renewal: Coming Soon - 2021 Renewal: Coming Soon - 2021 Renewal: Coming Soon - 2021 Renewal: Coming Soon - 2021 Renewal: Coming Soon - 2021 Renewal: Coming Soon - 2021 Renewal: Coming Soon - 2021 Coming Soon - 2022 Renovations Coming Soon - 2022 Humble High School Renovations Coming Soon - 2022 Humble High School Renovations Coming Soon - 2022 Humble High School Renovations Coming Soon - 2022 Humble High School Renovations Coming Soon - 2022 Renovations Coming Soon - 2022 Kingwood High School Renovations Coming Soon - 2022 Kingwood High School Renovations Coming Soon - 2022 Kingwood High School Renovations Coming Soon - 2022 Kingwood Park High School Renovations Coming Soon - 2022 Kingwood Park High School Renovations KHS Flood Mitigation Strategies Coming Soon - 2022 Multipurpose Rooms/Gyms - Group 3 Renewal: Coming Soon - 2021 Coming Soon - 2022 Kingwood Middle School Rebuild Coming Soon - 2022 Kingwood Middle School Rebuild Coming Soon - 2022 Kingwood Middle School Rebuild Coming Soon - 2022 Kingwood Middle School Rebuild Coming Soon - 2022 Kingwood Middle School Rebuild Coming Soon - 2022 North Belt Elementary Rebuild Coming Soon - 2022 North Belt Elementary Rebuild Coming Soon - 2022 North Belt Elementary Rebuild Savings = new North Belt Elementary CTE Campus Renovations Atascocita High School

Opening - 2021

Cisco Lab Pharmacy Lab Robotics Lab CTE Campus Renovations Atascocita High School CTE Campus Renovations Humble High School

Completed - 2020

Nursing Lab Computer Tech Lab

Coming Soon - 2021

Cosmetology Renovation CTE Campus Renovations Kingwood High School

Coming Soon - 2022

Nursing Lab CTE Campus Renovations Kingwood Park High School

Coming Soon - 2022 Criminal Justice Court Culinary Lab Tiny Homes Workshop

Tiny Homes Workshop

Criminal Justice Courtroom Culinary Lab CTE Campus Renovations

Completed - 2020

Criminal Justice Courtroom Robotics Lab

Tiny Homes Canopy

Coming Soon - 2021

Tiny Homes Outdoor Lab Tiny Homes Outdoor Lab Coming Soon - 2021 Charles Street Stadium Coming Soon - 2021 Charles Street Stadium Opening Dates

2018 Bond Referendum Financial Goals • All bonds authorized in the 2018 bond referendum will be repaid without increasing the debt service tax rate above 35 cents which is the rate Humble ISD has assessed since 2008.

• Debt will be retired at a pace sufficient to enable Humble ISD to address future facility needs without raising the debt service tax rate above 35 cents.

• No bonds will be sold with a term of more than 30 years. Current Financial Projections How Will These Interest Savings Benefit The District? Facility Assessment Before 2018 Bond Bond Sale Dates Facilities Assessment Study Update Invitation to Join Citizens Bond Advisory Committee Fall 2021 Brainstorming Next Bond

Foster Elementary School

Second Gyms at Middle Schools

Early Childhood Center

Virtual Learning Studios and Pods

Daylighting

Ross Sterling Middle School

Elementary Updates $ Doing everything we said we were going to do, and more Major Projects Bond Matrix Checklist High Schools Atascocita High School - Third Gym Nearly Complete Atascocita HS 10 20 Classroom Addition Nearly Complete Humble High School - Third Gym In Progress Humble HS Library Renovation, Cafeteria Addition In Progress Kingwood High School - Third Gym In Progress Kingwood Park High School - Third Gym In Progress Summer Creek High School - Third Gym Completed Field Turf at District Baseball/Softball Complex (Turner) Completed Field Turf at all HS Football Competition Fields (Excluding Humble HS at Turner) Completed Community Learning Center Multi-Purpose Gym In Progress CTE Classroom Renovations In Progress Doing everything we said we were going to do, and more Major Projects Bond Matrix Checklist Middle Schools Kingwood Middle School (Replacement Campus) In Progress Middle School Gyms Convert to Wood Floors Completed New Middle School #10 In Progress

Bond Matrix Checklist Elementary Schools Lakeland Elementary School (Replacement Campus) In Progress Multi-Purpose Rooms at Elementary Campuses In Progress New Elementary School #30 (Autumn Creek Elementary) In Progress Doing everything we said we were going to do, and more Major Projects

Bond Matrix Checklist Support Facilites

Northern Ag Barn (Replacement) In Progress New Transportation Center In Progress Emergency Operations Center Expansion In Progress Charles Street Stadium Major Renovations In Progress Doing everything we said we were going to do, and more

Atascocita High School Guy M. Sconzo North Belt Elementary Early College High School Added 20 classrooms (not 10) Replacing 53-year-old campus Fund Balance funded