APPENDIX - I (See paragraph - 6) FORM 1

(I) Basic Information No. Item Details 1. Name of the project/s Integrated Township Project at village Usarghar and Sandap, Dist- . State- 2. S. No. in the schedule 8 (b) 3. Proposed Area as per 7/12 extract: 5, 36,430.00 Sq. mt. capacity/area/length/tonnage to Area as per proposed Subdivision: 4, 96,153.00 Sq. mt. be handled/command Area of plot as per triangulation: 4, 97,543.27 Sq. mt. area/lease area/number of Deduction: 31,732.28 Sq. mt. wells to be drilled Net Plot area: 4, 64,420.72 Sq. mt. Built-up area as per FSI: 8,43,853.94 Sq.mt. (Including Social Housing Component) Total Construction Built-up area: 16, 22,675.46 Sq.mt.

Project Proposal: Phase Building Name & No. of floors Flats/Units No. (Nos.) Phase Residential: Sale Lower Stilt + Upper 1240 Flats

1 12 Buildings Stilt + 2 level podia + 1st to 23rd Floors Residential: Sale Lower Stilt + Upper 2012 Flats 17 Buildings Stilt + 2 level podia + 1st to 26th Floors Educational Stilt + 6 Floors Classrooms: Building (School) 115 Nos. Economically Ground + 7 Floors 448 Flats Weaker Section (EWS) 4 Buildings Mall 2 Basements + -- Ground + 6 Floors Sports Complex Ground + 1 Floor -- Phase Residential: Sale Basement + Lower 4712 Flats 2 37 Buildings Stilt + Upper Stilt + 2 Podia + 1st to 27th Floor EWS Ground + 7 Floors 784 Flats 7 Buildings Shopping 3 Basements + -- Complex (Town Ground + 4 Podia + Hall & 15 Floors Auditorium) Bus Station Stilt + 3 Floors -- Phase Basement + Lower 2828 Flats 3 Residential: Sale Stilt + Upper Stilt + 2 22 Buildings Podia + 1st to 27th Floor EWS: Ground + 7 Floors 448 Flats 4 Buildings Business Office 2 Basements + Offices

Form 1 – Integrated Township Project at Usarghar and Sandap, 1

No. Item Details Ground + 4 Podia + 8 Floors Market Ground + 1 Floor -- Basement + Ground + Beds: 50 Health Care 3 Floors nos. Fire Brigade Stilt + 3 Floors -- Police Station Ground + 2 Floors --

4. New/Expansion/Modernization Expansion and Amendment 5. Existing Capacity/ Area etc. The project has received Environmental Clearance vide No. SEAC- 2013/CR-419/TC-1 dated 13.02.2017. Copy of EC letter is attached as Enclosure. As there is expansion and amendment in the proposal due to increase in FSI as per ITP Approval, hence reapplied for Environment Clearance Total Constructed area on site (FSI + NON FSI): 57499.77 Sq. mt. 6. Category of project i.e.’ A’ or B1 ‘B’ 7. Does it attract the general Not Applicable condition? If yes, please specify. 8. Does it attract the specific Not Applicable condition? If yes, please specify. 9. Location Village Usarghar and Village Sandap, Tal - Kalyan, Dist- Thane, State –Maharashtra. Plot/ Survey/ Khasra No. Village - Usarghar, S. no. 17/1, 17/2, 17/3/A, 17/3/B, 17/4, 17/5, 36/1/A, 36/1/B, 37/1, 37/2, 38/1, 38/2, 38/3, 38/4, 70/9, 70/10, 70/11, 71/1, 71/2, 71/3, 71/4, 71/8, 91/1, 91/2, 91/3, 91/4, 91/5, 92/1, 92/2, 93P, 103/2, 103/6/A, 103/6/B, 103/7, 103/8, 103/9, 103/10, 103/11, 103/12, 103/13, 103/14/B, 103/15, 103/16, 103/17, 103/18, 107/1,107/2/A,107/2/B, 107/3, 107/4, 107/5, 107/6, 107/7, 107/8, 107/9, 107/10, 107/11, 107/12, 107/13, 107/14, 107/15, 107/16, 107/17, 107/18, 107/19, 107/20, 108/1, 108/2, 108/3, 109P, 134/1, 134/2, Village-Sandap, S. No. 2, 21P, Taluka –Kalyan, Dist- Thane in Proposed Growth Center of Kalyan Villages Usarghar and Sandap Tehsil Kalyan District Thane State Maharashtra 10. Nearest railway station Nearest Dativali Railway Station: Within 2.50 km (Road Distance) airport Nilje Railway Station: Within 6.00 km (Road Distance) Chhatrapati Shivaji International Airport: Within 39.00 km (Road Distance) 11. Nearest Town, city, District Kalyan and Dombivali headquarters along with distance in kms. 12. Village Panchayats, Zilla Special Planning Authority: Metropolitan Region Parishad, Municipal Development Authority (MMRDA) Corporation, Local body Municipal Corporation: Kalyan Dombivali Municipal Corporation (complete postal address with (K.D.M.C.) telephone nos. to be given) 13. Name of the applicant M/s. Horizon Projects Pvt. Ltd.

Form 1 – Integrated Township Project at Usarghar and Sandap, Kalyan 2

No. Item Details 14. Registered Address Runwal & Omkar Esquare, 5th floor, Off Eastern Express Highway, Opp. Sion Chunabhatti Signal, Sion (E), Mumbai – 400 055 15. Address for correspondence Runwal & Omkar Esquare, 5th floor, Off Eastern Express Highway, Opp. Sion Chunabhatti Signal, Sion (E), Mumbai – 400 055 Name Ms. Pallavi Matkari Designation Chief Architect (Owner/Partner/CEO) Address Runwal & Omkar Esquare, 5th floor, Off Eastern Express Highway, Opp. Sion Chunabhatti Signal, Sion (E), Mumbai – 400 055 Pin Code 400 055 E-mail [email protected] Telephone No. 9769620211 Fax No. 022-61179003 16. Details of Alternative Sites Not Applicable examined, if any. Location of these sites should be shown on a topo-sheet. 17. Interlinked Projects No 18. Whether separate application Not Applicable of interlinked project has been submitted? 19. If yes, date of submission Not applicable 20. If no, reason Not applicable 21. Whether the proposal involves approval/clearance under: if yes, details of the same and their status to be given. a) The Forest (Conservation) Not applicable Act, 1980? b) The Wildlife (Protection) Not applicable Act, 1972? c) The C.R.Z Notification, Not applicable 1991? 22. Whether there is any  Received Locational Clearance (LC) from Urban Development Government Order / Policy Department, Govt. of Maharashtra on date 21.08.2017 relevant/ relating to the site?  Received Letter of Intent (LOI) from MMRDA on date 23.04.2018  Received Layout approval dated 23.04.2018 LOI, LC and Layout approval are attached as Enclosure 23. Forest land involved (hectares) Not applicable 24. Whether there is any litigation No pending against the project and/or land in which the project is propose to be set up? (a) Name of the Court (b) Case No. (c) Order /directions of the Court, if any and its relevance with the proposed project.

Form 1 – Integrated Township Project at Usarghar and Sandap, Kalyan 3

(II) Activity 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) Details thereof (with approximate quantities / Sr. Information/Checklist Yes / rates, wherever possible) with source of No. confirmation No information data 1.1 Permanent or temporary change in Yes Site was an open land and is being developed as land use, land cover or topography Integrated Township Project. including increase in intensity of The project site is partly in Residential zone and land use (with respect to local land partly in commercial zone along with reservations use plan) for Playground, Garden, Public Office and staff quarters as per DP remarks of MMRDA 1.2 Clearance of existing land, No -- vegetation and building? 1.3 Creation of new land uses? Yes Site was an open land and is being developed as Integrated Township Project. The project site is partly in Residential zone and partly in commercial zone along with reservations for Playground, Garden, Public Office and staff quarters as per DP remarks of MMRDA 1.4 Pre-construction investigation e.g. Yes Geotechnical Investigation has been carried out. bore houses, soil testing? Copy of report is attached as Enclosure. 1.5 Construction works? Yes Integrated Township Project 1.6 Demolition works? No -- 1.7 Temporary sites used for No Provision of temporary hutments with facilities like construction works or housing of drinking water, toilets etc. construction workers? 1.8 Above ground building, structures Yes Details shall be submitted or earthworks including linear structures, cut and fill or excavations 1.9 Underground works including No -- mining or Tunneling? 1.10 Reclamation works? No -- 1.11 Dredging? No -- 1.12 Offshore structures? No -- 1.13 Production and manufacturing No -- processes? 1.14 Facilities for storage of goods or Yes Temporary storage facilities on site to store the materials? construction raw material 1.15 Facilities for treatment or disposal Yes  STP for Treatment of sewage of solid waste or liquid effluents?  Solid waste will be segregated into non- biodegradable and biodegradable garbage  Biodegradable waste will be treated on site and the non-biodegradable waste will be segregated into recyclable & non-recyclable. Recyclable waste shall be handed over to recyclers and non- recyclable waste will be handed over to local authority.  Dried sludge from STP will be used as manure for gardening  E – Waste: Will be stored separately and disposed through authorized recyclers.  Bio-medical waste will be handled and disposed

Form 1 – Integrated Township Project at Usarghar and Sandap, Kalyan 4

Details thereof (with approximate quantities / Sr. Information/Checklist Yes / rates, wherever possible) with source of No. confirmation No information data as per Bio-Medical Waste Management Rules, 2016 1.16 Facilities for long term housing of No -- operational workers? 1.17 New road, rail, or sea traffic during Yes Railway freight corridor shall be passing abutting construction or operation? the plot and also multi modal corridor shall be passing through the site in future which shall help to enhance accessibility to project site. 1.18 New road, rail, air waterborne or Yes Railway freight corridor shall be passing abutting other transport infrastructure the plot and also multi modal corridor shall be including new or altered routes and passing through the site in future which shall help to stations, ports, airports etc.? enhance accessibility to project site. 1.19 Closure or diversion of existing Yes Multi Modal Corridor is passing through the site. transport routes or infrastructure In future this shall help to enhance accessibility to leading to changes in traffic project site Movements? 1.20 New or diverted transmission lines No or pipelines? 1.21 Impoundment, damming, culver No -- ting, realignment or other change to the hydrology of watercourses or aquifers? 1.22 Stream crossings? No -- 1.23 Abstraction or transfers of water No -- from ground or surface waters? 1.24 Changes in water bodies or the land Yes By considering the runoff before development and surface affecting drainage or run- runoff after development there is some increment in off? runoff of storm water. 1.25 Transport of personnel or materials Yes Transport of construction materials. Precautions will for construction, operation or be taken to reduce the impact of the vehicular decommissioning? movement by trying to avoid the vehicular trips during peak hours. 1.26 Long-term dismantling or No -- decommissioning or restoration works? 1.27 Ongoing activity during No -- decommissioning which could have an impact on the environment? 1.28 Influx of people to an area in either Yes There will be influx of ~ 174045 nos. (Including temporarily or permanently? floating population) 1.29 Introduction of alien species? No -- 1.30 Loss of native species or genetic No -- diversity? 1.31 Any other actions? No --

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or ion short supply): Sr. Information/Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data 2.1 Land especially undeveloped or Yes Project site was open land and being developed as agricultural land (ha) Integrated Township.

Form 1 – Integrated Township Project at Usarghar and Sandap, Kalyan 5

Sr. Information/Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data 2.2 Water (expected source & Yes During Construction Phase – competing users) unit : KLD  For Workers: From MIDC (Maharashtra Industrial Development Corporation): 16 KLD

 For Construction Activity: From Water Tankers: 50 - 100 KLD (Depending upon the activity) (*Note: For fulfilling the construction water requirement of initial phase (Phase -1) proponents are planning to use water sourced from tankers. After commissioning STPs of Phase -1, the excess treated sewage from Phase-1 shall be used for the construction activity of the subsequent phases. This will help to reduce the fresh water demand for construction activity)

During Operational Phase –  Fresh water: From MIDC: 5996 KLD (For Domestic purpose)  Tanker water of potable quality: 21 KLD (For Swimming pool make up) 2.3 Minerals (MT) No -- 2.4 Construction material – stone, Yes Quantity : As per requirement aggregates, and / soil (expected Sources: The material required for construction source – MT) activities procured from company’s authorized / approved vendors only. 2.5 Forests and timber (source – Yes Timber required for doors sourced from local MT) suppliers. 2.6 Energy including electricity and Yes During Constructional Phase- fuels (source, competing users) Source : Maharashtra State Electricity Distribution Unit: fuel (MT), energy (MW) Company Limited (MSEDCL) D.G. Sets: As per requirement

During Operational Phase Source : MSEDCL Details shall be submitted. 2.7 Any other natural resources(use No -- appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which would be harmful to human health or the environment or raise concern about actual or perceived risks to human health. Details thereof (with approximate quantities / Sr. Information/Checklist Yes / rates, wherever possible) with source of No. confirmation No information data 3.1 Use of substances or materials, No -- which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies) 3.2 Changes in occurrence of disease or No -- affect disease vectors (e.g. insect or water borne diseases)

Form 1 – Integrated Township Project at Usarghar and Sandap, Kalyan 6

Details thereof (with approximate quantities / Sr. Information/Checklist Yes / rates, wherever possible) with source of No. confirmation No information data 3.3 Affect the welfare of people e.g. by No -- changing living conditions? 3.4 Vulnerable groups of people who No -- could be affected by the project e.g. hospital patients, children, the elderly etc., 3.5 Any other causes No --

4. Production of solid wastes during construction or operation or decommissioning (MT/month) Sr. Information/Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data 4.1 Spoil, overburden or mine No -- wastes 4.2 Municipal waste (domestic and Yes During Construction Phase: or commercial wastes) Total quantity of solid waste = 25 kg/day (Biodegradable and Non-biodegradable)

During Operation Phase:  The total quantity of solid waste: 38305 Kg/day. (Biodegradable and Non-biodegradable)  Biomedical waste: 19 kg/day  E – waste: 463 kg/month 4.3 Hazardous wastes (as per Yes Waste oil generated from D.G. shall be stored at separate Hazardous waste Management location duly marked and will be sold to the authorized Rules) recyclers. 4.4 Other industrial process wastes No -- 4.5 Surplus product No -- 4.6 Sewage sludge or other sludge Yes Dried sludge from STP will be used as manure for the from effluent treatment. plants within the premises 4.7 Construction or demolition Yes No demolition activity is involved wastes. Excavation and Construction waste management details shall be submitted 4.8 Redundant machinery or No -- equipment. 4.9 Contaminated soils or other No -- materials. 4.10 Agriculture wastes. No -- 4.11 Other solid wastes. Yes  Bio-medical waste will be handled and disposed as per Bio-Medical Waste Management Rules, 2016  E-Waste will be stored separately and disposed through authorized recyclers

5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) Sr. Information/Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data 5.1 Emissions from combustion of Yes D.G. Sets will be used during power failure. fossil fuels from stationary or mobile sources 5.2 Emissions from production No -- processes 5.3 Emissions from materials handling Yes Frequent water sprinkling to minimize the fugitive dust

Form 1 – Integrated Township Project at Usarghar and Sandap, Kalyan 7

Sr. Information/Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data including storage or transport emissions due to handling and loading-unloading activities 5.4 Emissions from construction Yes / Rise in dust levels during construction phase. activities including plant and Marginal Precautions taken to reduce dust generation during equipment construction phase:  Use of covering sheets for trucks carrying construction material to prevent air borne dust  Separate storage for construction material  Water sprinkling to suppress dust or aligning the waste disposal in such a way to minimizes dust dispersal (wind breakers)  Use of CPCB approved DG sets with proper maintenance  Adequate parking provision and proper traffic management  Open burning of solid waste is prohibited  Regular health checkup of the workers  Use of the standard personal protective equipments like masks, goggles  Dust suppression measures during construction shall be followed as per Notification dt. 25.01.2018 5.5 Dust or odour from handling of Yes Dust generation will be controlled as described above. materials including construction For odour control: Proper ventilation shall be provided materials, sewage and waste around STP & solid waste management location 5.6 Emissions from incineration of No -- waste 5.7 Emissions from burning of waste No -- in open air (e.g. slash materials, construction debris) 5.8 Emissions from any other sources No --

6. Generation of Noise and Vibration, and Emissions of Light and Heat: Sr. Information/Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data 6.1 From operation of equipment Yes but Noise levels may increase due to operation of machinery e.g. engines, ventilation plant, negligible as well as transportation vehicles. This causes nuisance to crushers. the nearby area. Following precautions taken to control noise pollution:  Regular noise monitoring to ascertain the noise levels are within limit  Contractors use well maintained & relatively newer equipments to mitigate noise generation in initial stages when excavation & earth removal is carried out  Provision of ear plugs for construction labour and staff during high noise construction activity  No noise polluting work in night shifts  Provision of barricades along the periphery of the site  Acoustic enclosure for DG sets 6.2 From industrial or similar No -- processes 6.3 From construction or Yes Noise Pollution Control: demolition  Regular noise monitoring to ascertain the noise levels

Form 1 – Integrated Township Project at Usarghar and Sandap, Kalyan 8

Sr. Information/Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data are within limit  Contractors use well maintained & relatively newer equipments to mitigate noise generation in initial stages when excavation & earth removal is carried out  Provision of ear plugs for construction labour and staff during high noise construction activity  No noise polluting work in night shifts  Provision of barricades along the periphery of the site  Acoustic enclosure for DG sets  Tree plantation 6.4 From blasting or piling. No -- 6.5 From construction or Yes During Construction phase: operational traffic.  Proper traffic management for the construction vehicles  Regular maintenance of vehicles with suitable enclosures and intake silencers  Planning and ensuring effective implementation of the waste movement plan for loading and offsite movement in non-traffic hours

Operation Phase :  Provision of proper parking arrangement, traffic management plan for smooth flow of a vehicle helps to abate noise pollution due to vehicular traffic  Plantation of trees of various varieties on ground that shall act as natural noise buffer and also will enhance air quality 6.6 From lighting or cooling No -- systems. 6.7 From any other sources. Yes D.G. sets will be enclosed in acoustic enclosures to mitigate the noise of D.G. sets while in operation Noise due to freight corridor or multimodal corridor

7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: Sr. Information/Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data 7.1 From handling, storage, use or No -- spillage of hazardous materials. 7.2 From discharge of sewage or other No  During Construction phase: effluents to water or the land Disposal of sewage to septic tank and soak pits (expected mode and place of discharge).  During Operation phase:  Treated sewage shall be reused for gardening, flushing and cooling tower make up  For fulfilling the construction water requirement of initial phase (Phase -1) proponents are planning to use water tankers  After commissioning STPs of Phase 1, the excess treated sewage from Phase-1 shall be used for the construction activity of the subsequent phases. This will help to reduce the fresh water demand for construction activity and further reduce the quantity of

Form 1 – Integrated Township Project at Usarghar and Sandap, Kalyan 9

Sr. Information/Checklist Yes / Details thereof (with approximate quantities / rates, No. confirmation No wherever possible) with source of information data excess treated sewage. 7.3 By deposition of pollutants No Dust generation during construction phase from emitted to air into the land or into earthworks and movement of vehicles. Appropriate water. fugitive dust control measures at exposed areas and dust covers for trucks provided to minimize any impacts. Stack height of DG sets as per CPCB guidelines. 7.4 From any other sources. No -- 7.5 Is there a risk of long term build No -- up of pollutants in the environment from these sources?

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment Details thereof (with approximate quantities Sr. Yes / Information/Checklist confirmation / rates, wherever possible) with source of No. No information data 8.1 From explosions, spillages, fires etc from No -- storage, handling, use or production of hazardous substances 8.2 From any other causes. No -- 8.3 Could the project be affected by natural -- Detailed Disaster Management plan shall be disasters causing environmental damage submitted in EIA report (e.g. floods, earthquakes, landslides, cloudburst)?

9. Factors which should be considered (such as consequential development) which could lead to environmental effected or the potential for cumulative impacts with other existing or planned activities in the locality Details thereof (with approximate quantities / Sr. Yes / Information/Checklist confirmation rates, wherever possible) with source of No. No information data 9.1 Lead to development of supporting facilities, ancillary development or development stimulated by the project which could have impact on the environment e.g.: • Supporting infrastructure (roads, power Yes There would be upgradation of existing local supply, waste or waste water treatment, infrastructure, where there would be improvement etc.) of transport services in the surrounding villages of the project.

• housing development Yes The Project is Integrated Township Project • extractive industries • supply industries • other 9.2 Lead to after-use of the site, which could No -- have an impact on the environment 9.3 Set a precedent for later developments Yes  The development will provide housing structures with appropriate amenities, adequate sanitation facilities as well as fire fighting and safety measures to people.  There would be 1680 houses for Economically

Form 1 – Integrated Township Project at Usarghar and Sandap, Kalyan 10

Details thereof (with approximate quantities / Sr. Yes / Information/Checklist confirmation rates, wherever possible) with source of No. No information data Weaker Section (EWS) with all the appropriate amenities.  In amenities, the project would provide School, Mall, sports complex, Shopping Complex (Town Hall & Auditorium), Bus station, Market, Health care center, Fire brigade and police station which will not only benefit he residents but also to the peripheral population.  The project would provide employment as construction workers to about 500 persons in every phase. Besides the project would also provide business opportunities to the local people such as contractors, transporters and raw material suppliers etc.  During the operational phase, due to commercial development there would be additional employment for the poor strata of society by way of security guard, driver, maid/servant, sweeper, gardener etc.  There would be tremendous improvement in infrastructure viz. roads, transport, electricity and water supply in and around villages as the existing infrastructure is poor also inclusion of villages in KDMC  The proposed projects of Railways freight corridor and Alibag-Virar multimodal corridor will boost infrastructure and employment in the peripheral area of villages. 9.4 Have cumulative effects due to proximity Yes Impacts on water availability, storm water to other existing or planned projects with drainage, availability of electricity, traffic similar effects congestion etc.

Form 1 – Integrated Township Project at Usarghar and Sandap, Kalyan 11

(III) Environmental Sensitivity Sr. Areas Name/ Identity Aerial distance (within 15 No. km.) from Proposed project location boundary 1 Areas protected under international Sanjay Gandhi National Park Approx. 12.00 Km conventions, national or local legislation Mumbra/ Parsik Hill Approx. 6.00 Km for their ecological, landscape, cultural Thane Creek Flamingo Approx. 10.25 Km or other related value Sanctuary 2 Areas which are important or sensitive Betawade Lake Approx. 0.60 km for ecological reasons - Wetlands, Usarghar Ganesh Visarjan Ghat Approx. 0.50 km watercourses or other water bodies, Betawade Ganesh Visarjan Ghat Approx. 0.55 km coastal zone, biospheres, mountains, Nilaje Lake Approx. 1.00 km forests Khidkali Lake Approx. 3.00 km Kausa Lake Approx. 5.00 km Kala Talao Approx. 8.00 km Jail Lake Approx. 9.00 km Kolshet Lake Approx. 10.00 km Rewale Lake Approx. 10.00 km Hariyali Lake Approx. 10.00 km Masunda Lake Approx. 10.00 km Ambe Ghosale Lake Approx. 10.00 km Makhmali Lake Approx. 11.00 km Kachrali Lake Approx. 11.00 km Siddheshwar Lake Approx. 11.00 km Brahmala Lake Approx. 11.00 km Raila Devi Lake Approx. 12.00 km Yeoor Lake Approx. 14.00 km Upvan Lake Approx. 13.00 km Thane Creek Approx. 9.00 km Ulhas River Approx. 2.50 km 3 Areas used by protected, important or Sanjay Gandhi National Park Approx. 12.00 Km sensitive species of flora or fauna for Mumbra/ Parsik Hill Approx. 6.00 Km breeding, nesting, foraging, resting, over Thane Creek Flamingo Approx. 10.25 Km wintering, migration Sanctuary 4 Inland, coastal, marine or underground Betawade Lake Approx. 0.60 km waters Usarghar Ganesh Visarjan Ghat Approx. 0.50 km Betawade Ganesh Visarjan Ghat Approx. 0.55 km Nilaje Lake Approx. 1.00 km Khidkali Lake Approx. 3.00 km Kausa Lake Approx. 5.00 km Kala Talao Approx. 8.00 km Jail Lake Approx. 9.00 km Kolshet Lake Approx. 10.00 km Yeoor Lake Approx. 14.00 km Rewale Lake Approx. 10.00 km Hariyali Lake Approx. 10.00 km Masunda Lake Approx. 10.00 km Ambe Ghosale Lake Approx. 10.00 km Makhmali Lake Approx. 11.00 km Kachrali Lake Approx. 11.00 km Siddheshwar Lake Approx. 11.00 km Brahmala Lake Approx. 11.00 km Raila Devi Lake Approx. 12.10 km Upvan Lake Approx. 13.00 km

Form 1 – Integrated Township Project at Usarghar and Sandap, Kalyan 12

Sr. Areas Name/ Identity Aerial distance (within 15 No. km.) from Proposed project location boundary Thane Creek Approx. 9.00 km Ulhas River Approx. 2.50 km 5 State, National boundaries None -- 6 Routes or facilities used by the public for National Highway 4 Approx. 5.00 km access to recreation or other tourist, pilgrim areas 7 Defence installations No -- 8 Densely populated or built-up area Dombivali Approx 2.00 Km 9 Areas occupied by sensitive man-made Dombivali Approx 2.00 Km land uses (hospitals, schools, places of worship, community facilities) 10 Areas containing important, high quality Khidkali Temple Approx. 4.00 km or scarce resources Durgadi Fort Approx. 8.00 km (Ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals) 11 Areas already subjected to pollution or No -- environmental damage. (those where existing legal environmental standards are exceeded) 12 Areas susceptible to natural hazard No -- which could cause the project to present environmental problems (Earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)

(IV) Proposed Terms of Reference for EIA studies:

The EIA Report shall be prepared based on the standard TOR notified by MoEF & CC on dt. 10.04.2015 and as per the guidelines given in Environmental Impact Assessment Guidance Manual for Township/area development projects by MoEF & CC

Proposed draft Terms of References (ToR) for the EIA Studies is attached as Enclosure.

Form 1 – Integrated Township Project at Usarghar and Sandap, Kalyan 13