The Bronx Zoo Access Improvements
PIN X110.23 THE BRONX ZOO ACCESS IMPROVEMENTS
PROJECT SCOPING REPORT
APRIL 2006
PREPARED BY:
NEW YORK STATE DEPARTMENT OF TRANSPORTATION, REGION 11 IN COLLABORATION WITH TAMS, an Earth Tech company
- a -
TABLE OF CONTENTS
Section Page No.
I. Project Evolution/Introduction/Project Summary...... 1 II. Project Identification, Evolution, Conditions and Needs, and Objectives A. Project Identification 1. Project Type...... 8 2. Project Location...... 8 B. Project Evolution ...... 8 C. Conditions and Needs 1. Transportation Conditions and Engineering Considerations a. Functional Classifications and FA System...... 9 b. Ownership and Maintenance Jurisdiction...... 9 c. Culture, Terrain and Climatic Conditions ...... 9 d. Control and Access...... 10 e. Existing Highway Section...... 10 f. Abutting Highway Segments and Plans for Abutting Highways Segments..... 12 g. Speed and Delay...... 14 h. Traffic Volumes ...... 14 i. Level of Service ...... 18 j. Non Standard features ...... 23 k. Safety Considerations, Accident History and Analysis ...... 26 l. Pavement and Shoulder Conditions...... 33 m. Guide Railing, Median Barriers, Impact Attenuators ...... 33 n. Traffic Control Devices...... 33 o. Structures ...... 34 p. Hydraulics and Bridges and Culverts ...... 34 q. Drainage Systems...... 34 r. Soil and Foundation Conditions ...... 34 s. Utilities...... 34 t. Railroads and Buses ...... 34 u. Landscaping ...... 35 v. Provisions for Pedestrians and Bicyclists...... 35 w. Planned Development for Area ...... 36 x. System Elements and Conditions ...... 36 y. Community Participation ...... 36
- b -
2. Needs
a. Pavement Deficiencies...... 36 b. Safety Deficiencies...... 36 c. Bridges Structural Deficiencies ...... 37 d. Capacity Deficiencies ...... 37 e. Modal Interrelationship...... 38 f. System Deficiencies...... 38 g. Mobility Deficiencies ...... 38 h. Social Demand and Economic Development ...... 39 i. Transportation Plans ...... 39
D. Project Problem Identifications and Project Goals and Objectives ...... 39
III. Alternatives
A. Design Criteria ...... 44
B. Feasible Alternatives
1. Description of Feasible Alternatives...... 50 2. Engineering Conditions and Feasible Alternatives (a) Geometries ...... 82 (b) Traffic Forecasts, Level of Service and Safety Considerations...... 82 (c) Pavement...... 82 (d) Structures ...... 82 (e) Hydraulics...... 82 (f) Drainage...... 82 (g) Maintenance Responsibility...... 83 (h) Maintenance and Protection of Traffic ...... 83 (i) Soil Foundation...... 83 (j) Utilities...... 83 (k) Railroads and Buses...... 83 (l) Right-Of-Way ...... 83 (m) Landscaping Development...... 83 (n) Provisions for Pedestrians, including Persons with Disabilities...... 84 (o) Provisions for Bicycling ...... 84 (p) Lighting...... 84
C. Project Costs and Schedule
1. Costs...... 84 2. Schedule...... 84
- c -
IV. Social Economic and Environmental considerations
A. Environmental Action Plan (EAP/NEPA) Classification ...... 84 B. State Environmental Quality Review (SEQR) Classification...... 85 C. List of Anticipated Cooperating Agencies ...... 85 D. Identification of Potential Social, Economic and Environmental Issues ...... 85 E. Anticipated Permits and Approval Required...... 85 F. List of Sources Reviewed ...... 86 G. Early Coordination Requirements...... 86
V. Evaluation and Comparison of Alternatives
A. Evaluation and Comparison ...(Table N)...... 88
VI. Minutes of Meetings, Correspondence and Comments...... 90
Appendix. (The Bronx Zoo Access Improvement Study report prepared in 24©2 includes an appendix which includes supporting traffic data, accident data, etc. for this PSR. This appendix can be examined in the NYSDOT office)
- d -
Final PSR, April 26, 2006
List of Figures
Figure Description Following Page No. 1. Project Location Map...... 8 2. Project Study Area ...... 8 3. Signalized Intersection at Eastbound Pelham Parkway/Boston Road...... 11 4. Signalized Intersection at Boston Road/Bronx Park East...... 13 5. Unsignalized T-Intersection at Boston Road/NB Bronx River Parkway ...... 13 6. Unsignalized T-Intersection at Boston Road/Bronx Zoo Entrance ...... 17 7. Existing (2042) AM (8-9 am) Hourly Volumes...... 17 8. Existing (2002) Mid-day (12-1 pm) Hourly Volumes and LOS Results...... 17 9. Existing (2002) PM (5-6 p m) Hourly Volumes and LOS Results...... 17 9A. Future No-Build (2026) AM (8-9 am) Hourly Volumes ...... 17 9B. Future No-Build (2026) Mid-day (12-lpm) Hourly Volumes and LOS Results ...... 17 9C. Future No-Build (2026) PM (5-6pm) Hourly Volumes and LOS Results ...... 17 9D. Automatic Traffic Recorder (ATR) Count Locations...... 17 10. Accident Rate/Statewide Average Ratio...... 17 10A. Bus Map for Project Area ...... 35 11 Alternative Features (Alternative 1A) ...... 50 12. Alternative Feature (Alternative 1B) ...... 52 13. Alternative Features (Alternative 2) ...... 53 14. Alternative Features (Alternative 3) ...... 54 15. Alternative Features (Alternative 4) ...... 55 16. Alternative Features (Alternative 5) ...... 56 17. Alternative Features (Alternative 6) ...... 57 18. Alternative Features (Alternative 7) ...... 57 19. Alternative Features (Alternative 8) ...... 59 19A. Alternative Features (Alternative 8A) ...... 61 20. Alternative Features (Alternative 9) ...... 61 21. Alternative Features (Alternative 10) ...... 62 22. Alternative Features (Alternative 11) ...... 63 23. Alternative Features (Alternative 12) ...... 65
- e -
Final PSR, April 26, 2006
List of Tables
Table Description On page
A. Existing (2002) Annual Average Daily Traffic (AADT) ...... 16 B. Wildlife Conservation Society/Bronx Zoo Bronxdale Gate Arrival Rate ...... 20 C. LOS Results - Existing and Future (No Build) Weekday Condition...... Following.22 D. LOS Results - Existing and Future (No Build) "Weekend Condition...... Following.22 E. Existing Accident Rates Analyses - Local Street ...... 29 F. Existing Accident Rates Analyses - Bronx River Parkway...... 30 G. Mainline Element Design Criteria ...... 44 H. Ramp Element Design Criteria ...... 47 I. Alternative Features Considered...... 66 J. LOS Results Future (Build) Weekday Condition...... Following 81 K. LOS Results Future (Build) Weekend Condition...... Following.81 L. Weaving Analysis Results - Future (Build) Weekday Condition...... Following.81 M. Weaving Analysis Results - Future (Build) Weekend Condition...... Following.81 N. Summary of Alternatives
- f -
PSR April 24, 2006 Zooreport(04_copy).doc
Project Evolution
The project originated from a request by the Wildlife Conservation Society for improved access from the Bronx River Parkway (BRP) to the Bronxdale Gate of the Bronx Zoo (see Figure 1 & 2). A feasibility study was initiated to develop and evaluate alternative that could enhance accessibility and safe for travelers accessing to the Bronx Zoo from the northbound BRP.
At the beginning of the study, NYSDOT team members met with representatives of the Wildlife Conservation Society (WCS), the NYPD, representatives of elected officials, and community board members. At that time, it was made clear that the problems of accessibility and safety at the BRP/Boston Road/Bronxdale Gate interchange were related to congestion and safety issues at nearby local streets. As a result, the study scope was expanded to include both a primary and a secondary study area (see Fig 2). The primary study area includes the BRP/Boston Road/Bronxdale gate interchange. The secondary study area includes the BRP/Pelham Parkway interchange, Boston Road/Bronx Park East interchange and the Boston Road/Pelham Parkway interchange.
Subsequent to the completion and circulation of the study report, the decision was made to expand the project scope to address both the NB & SB BRP at the Boston Road interchange as well as the related local street network. As a result, an additional alternative was added Also, NYCDOT while progressing the reconstruction of Pelham Parkway (East of Boston Road) has developed an alternative, which reconfigures the ramp between NB BRP and Pelham Pkwy. This PSR includes that alternative.
I. Introduction/Project Summary
This project focuses on the development and evaluation of alternative improvements that will enhance the mobility, safety, and accessibility of the Bronx Zoo in the vicinity of the Bronx River Parkway (BRP)/Pelham Parkway interchange. Due to the proximity and connectivity of the Bronx River Parkway to the surrounding local street network, the proposed access improvements to the Bronx Zoo will most likely affect the local travel patterns within the project study area as well as the east-west corridor along Pelham Parkway. However, because of constraints on consultant resources and time, the study was not able to fully address the problems of safety and congestion for the surrounding local streets and for the southbound BRP/Boston Road interchange. The primary study area remained limited to the area accessible to the zoo only. This Project Scoping Report (PSR) now extends the primary study area to include the interchanges of Boston Road/NB and SB Bronx River Parkway (BRP), Boston Road /EB Pelham Parkway and Boston Road/Bronx Park East. This project identifies a series of alternatives which address various problems in the study area. Alternatives were then assembled into packages for advancement to Preliminary Design Summaries and figures of the strong alternative are included in this Project Summary.
1
PSR April 24, 2006 Zooreport(04_copy).doc
Details of all the alternatives considered in this study are fully discussed in Section III C of this report. Since this project was developed to address safety, operational, and accessibility issues on the study area roadway network, with respect to vehicle volumes generated by the location of the Bronxdale gate of the Bronx Zoo, all traffic analysis for this project correspond with the peak arrival and departure periods for the Zoo. Based on the Bronxdale gate information provided by the zoo, the peak Zoo arrival period is 12:00-1:00 pm and the peak departure period is 5:00-6:00 pm, and are referred to throughout the report as AMid-day@ and APM@ respectively.
In 1982, the Bronx Zoo completed the Traffic Access and Improvement Study for the Bronxdale Gate and Parking Area. The 1982 study identified the existing and potential future operational problems at the immediate access to the Bronxdale Gate and parking area. The current project study area extends from Boston Road to the east, the Bronxdale parking lot to the west, Bronx River Parkway Interchange 7 (Pelham Parkway) to the north, and Bronx River Parkway Interchange 6 to the south.
In August, 2000, NYSDOT completed an Expanded Project Proposal (EPP) under PIN X110.18.101 for the Interchange Improvements at Bronx River Parkway and East 177th Street. Similar to the current project , the primary focus of the EPP was to develop feasible alternatives to improve safety, mobility and access on the various roadways of East 177th Street, including Bronx River Parkway(BRP).The project area of the BRP/East 177th Street EPP was just south of the project area of this Bronx Zoo Access Improvement Study. Although no origin/destination data were collected in this study, based on the existing traffic data collected in 2002, approximately 5% of the weekend Mid-day traffic along the northbound Bronx River Parkway is destined to the Bronx Zoo during the peak Zoo arrival hour. Furthermore, the Bronx River Parkway is the primary source of vehicles entering the zoo and the primary initial destination route of vehicles departing from the zoo. Based on the findings identified in the 1982 study and meetings with the zoo and local law enforcement officials, the following deficiencies within the project area have been identified:
Excessive vehicle delays and roadway congestion along the local street network; High accident rates Non-standard roadway features.
The primary goal of this Project Scoping Report (PSR) is to identify feasible Bronx Zoo access improvements and to improve safety and operations in the vicinity of the BRP/Boston Road Interchange. The following goals have been identified for this project as a result of meetings with the NYPD, community and Bronx Zoo officials:
1. Reduce congestion at accesses to the Bronxdale Gate of the Bronx Zoo
2. Improve traffic safety at accesses to the Bronxdale Gate of the Bronx Zoo 2
PSR April 24, 2006 Zooreport(04_copy).doc
3. Provide a transportation system which supports the Bronx Zoo plan for increased utilization of the Bronxdale Gate and promotes Zoo patronage
4. Reduce congestion and increase mobility on the local street network in the vicinity of the Bronx Zoo including the interchanges of BRP/Boston Road, Boston Road/Bronx Park East and Boston Road/EB Pelham Pkwy.
5. Improve safety and reduce accidents on the local streets in the vicinity of the Bronx Zoo including the interchanges of BRP/Boston Road, Boston Road/Bronx Park East and Boston Road/EB Pelham Pkwy.
6. Reduce congestion and increase mobility within the project limits on the BRP mainline and ramps.
7. Improve safety and reduce accidents with the project limits on the BRP mainline and ramps.
8. Minimize socio-economic and environmental impacts
An iterative process was used in the development of alternative components and composite alternatives which incorporated the results of multiple series of capacity analyses performed using the latest version of Highway Capacity Analyses (Version 4.1b), to determine the levels- of-service for the various signalized and un-signalized intersections, and freeway and weaving segments of the existing conditions (year 2002) and design year of 2026 (ETC year +20) for the no-build condition and the proposed alternative components and composite alternative configurations.
The development of the alternative components and composite alternatives was also guided by the need to address conditions contributing to high accident locations within the study area. The latest available two-years of historic accident data were gathered from NYSDOT and NYPD for the project study area. Accident types and rates were summarized and collision diagrams developed using the Highway Safety Analysis (Version 2.1). The accident rates calculated were compared with the corresponding NYSDOT Statewide Accident Averages for similar highway facility types to determine the high accident locations.
Alternative components considered in this PSR range from minor operational changes such as signal re-timing, pavement re-striping, and addition of signs to low-cost capital improvements such as fence relocation and zoo entrance booth relocation, to capital-intensive construction improvements such as roadway widening, interchange ramp relocation, and intersection reconfiguration. The estimated costs of the construction for the various alternative components
3
PSR April 24, 2006 Zooreport(04_copy).doc
and composite alternatives, not including right-of-way costs, range approximately from $15,000 to $6.2 million in 2002 dollars. This project will be funded by City, State and/or Federal funds.
Alternative Description Figure Components
1A Reconfigure Boston Road/Pelham Parkway 11 Intersection, widen NB exit to Pelham Pkwy. 1B Reconfigure NB BRP Exit to Pelham Pkwy. to Include 12 Additional Branch and Underpass Beneath EB Pelham Parkway 2 Close Portion of Boston Road Between NB BRP and 13 Bronx Park East to Vehicular Traffic; widen NB Exit to Pelham Pkwy. 2 Close Portion of Boston Road Between NB BRP and 14 Bronx Park East to Vehicular Traffic; widen NB Exit to Pelham Pkwy. 3 Reconfigure NB BRP Ramps at the BRP/Boston Road 15 Interchange (Interchange 6) 4 Reconfigure Zoo Entrance 16 5 Reconfigure Zoo Exit and Zoo Parking Lot Fence 17 6 Re-Time Traffic Signal and Provide Warning Signage at 18 Boston Road/Bronx Park East 7 Widen Boston Road between Bronx Park East and Bronx Zoo Entrance 8 Reconfigure Intersection of Boston Road and Bronx 19 Park East and Eliminate NB BRP Exit to Pelham Pkwy (Ramp 7E). 8A Reconfigure Intersection of Boston Road and Bronx 19A Park East and Eliminate NB BRP Exit to Pelham Pkwy. (Ramp 7E,) Improve SB BRP/Boston Road Interchange
9 Direct Access Ramps from NB BRP to Bronx Zoo 20 10 Composite Alternative with Alternative Components 21 1A,2,3,4,and 5 11 Composite Alternative with Alternative Components 3,8, 22 and 9 12 Reconfigure NB BRP Exit to Pelham Pkwy to create 23 weaving section Pelham Pkwy
These project alternatives will most likely be classified as NEPA Class II and SEQRA Type II actions. Future stages of this project will be prepared in compliance with the level of documentation required for the State Environmental Quality Review Act (SEQRA) and the New York State Environmental Action Plan (EAP). An Environmental Assessment (EA) or Environmental Impact Statement (EIS) is not anticipated as part of the preliminary design for any alternatives of this project.
4
PSR April 24, 2006 Zooreport(04_copy).doc
After a series of evaluations and analyses of the initial alternative components considered (Alternatives 1 to 9 See Figure 1-20), composite alternatives 10 and 11 (Figures 21 and 22) were developed which combine various alternative components. Table N of this report illustrates the comparison of the various alternative components and composite alternatives considered based on their ability to meet the goals developed for this study.
A brief summary of three of the strongest alternatives follows: (For a complete detailed description of these alternatives, see Section III.B.1)
Alternative 10 (See Figure 21 after Section I-Introduction/Project Summary) In this composite alternative, the segment of Boston Road between Bronx Park East and the terminus of the northbound Interchange 6 ramp is closed to vehicular traffic. The Northbound exit to EB PelhambPkwy/Boston Road (7E) is widened to two lanes to accommodate additional volume reassigned from Interchange 6, which is destined to northbound Boston Road. The intersection of Boston Road and eastbound Pelham Parkway is operationally reconfigured as a five-legged intersection with a separate signal phase for ramp 7E. The northbound exit and entrance ramp at Interchange 6 are reconfigured to extend the weaving length on northbound Bronx River Parkway. On the Zoo property, a portion of the parking lot fence is relocated to improve sight distance and the entrance toll plaza is relocated to the west to increase vehicle queue storage.
The estimated construction cost of Alternative 10 is approximately $3,568,000.
A disbenefit of the proposed configuration of Alternative 10 is that local vehicle access to and from the Zoo via Boston Road is eliminated. Vehicles originating from Bronx Park East or eastbound Pelham Parkway must utilize one existing loop ramp of Interchange 7 (BRP/Pelham Parkway) and one existing ramp from southbound BRP at Interchange 6 (Boston Road)in order gain access to Bronxdale gate of the Bronx Zoo, and the reconfigured entrance ramp to northbound BRP at Interchange 6 and all three remaining loop ramps of Interchange 7 (BRP/Pelham Parkway) for egress back to Bronx Park East thus increasing the travel time and the vehicle miles traveled of this group of travelers. In addition, the reconfigured northbound entrance and exit ramp of Interchange 6 encroach on two baseball fields and a soccer field in the recreational park area east of the Bronx River Parkway.
Alternative 11 (See Figure 22 after Section I-Introduction/Project Summary) In this composite alternative, direct access is provided to the Bronx Zoo from the northbound Bronx River Parkway via a new loop ramp connection to westbound Boston Road which segregates the zoo-bound traffic from the local street traffic that in the current configuration share the northbound BRP exit ramp at Interchange 6. The northbound BRP exit ramp at Interchange 6 is realigned and terminates at the signalized intersection at Bronx Park East/Boston Road. The reconfigured signalized intersection is aligned with the existing north-
5
Alternative 10 – Figure 21
Alternative 11 – Figure 22
Alternative 8A – Figure 23
PSR April 24, 2006 Zooreport(04_copy).doc
south geometry along Boston Road with a 15 ft. wide pedestrian sidewalk along the west side of Boston Road.
The estimated construction cost of Alternative 11 is approximately $5,415,000.
Disbenefits of the proposed configuration of Alternative 11 are that the proposed loop ramp from northbound BRP to westbound Boston Road crosses the only pedestrian route to the Bronxdale gate. In addition, the reconfigured northbound entrance and exit ramp of Interchange 6 encroach on two baseball fields and a soccer field in the recreational park area east of the Bronx River Parkway, and approximately 24 existing on street parking spaces are eliminated. For this alternative to be advanced the sport field would need to be re-configured. Also the radius of the proposed on-ramp from EB Boston Road is only 100 ft.
Alternative 8A (New Alternative, Figure Attached)
After completion of the study an additional alternative; Alternative 8A has been developed which includes the addition of several ramps located on the west side (SB side) of BRP to satisfy all goals and NEPA and SEQRA. The description and cost etc. of this new alternative are attached. Alternative 8A is a variation of Alternative 8 (already described) with the addition of improvements to the SB BRP. Alternative 8 and 8A reconfigure the intersection of Boston Road/Bronx Park East to improve the geometry and vehicular capacity. Alternative 8 and 8A both eliminate the existing Bronx River Parkway NB Exit to EB Pelham Pkwy. (Ramp 7E) allowing signal phase time for a leading pedestrian interval in the signal phasing and improving level of service of Pelham Parkway and Boston Road. A difference is that Alternative 8A has a signalized intersection at the end of the ramps intersection with Boston Road, instead of a slip ramp into Boston Road. This offers one more at grade crossing option for people walking and cycling to the Bronx Zoo, calms traffic on Boston Road coming from the Parkway, and offers a much safer distance for lane changes between the intersections.
Alternative 8A adds lane channelization and a pedestrian refuge island on eastbound Pelham Parkway at Boston Road. The channelization is possible due to the elimination of Ramp 7E and creates shorter crossing distances in addition to a much more intuitive geometry leading into eastbound Pelham Parkway service road right turn on to Boston Road.
This alternative also adds a roundabout on Boston Road, west of the parkway to more safely handle traffic to and from the Bronx Zoo parking area as well as traffic using the southbound Bronx River Parkway entrance and exit ramps. A roundabout has several advantages over other traffic control devices at this location including its safety statistics over signalized or signed intersection when properly utilized; the lack of pedestrian conflict leading to into the Zoo causes crossings not to be an issue , there is not enough space under the Bronx River Parkway Bridge over Boston Road for adequate lanes or sight distance, it should have an improved level of service over a signalized intersection in this context , it offers traffic calming into the 6
PSR April 24, 2006 Zooreport(04_copy).doc
neighborhood and Zoo parking for the existing traffic from southbound Bronx River Parkway, and can potentially be designed as a beautiful gateway leading into the Bronx Zoo.
The estimated construction cost of Alternative 8A in 2004 dollars is approximately $15M.
Using data collected for the study, NYSDOT performed a preliminary modeling effort to determine the effectiveness of Alternatives 10 and 11. A CORSIM simulation model, suitable for freeways and surface streets was used. Though the model has not been calibrated yet, both alternatives have been found to be feasible from the perspective of traffic operations. Additional data can be collected and the modeling task can be further progressed during Design stages.
The Wildlife Conservation Society (Bronx Zoo) attended several coordination meetings and provided input, including possible additional project alternatives, while the project was progressing. In a site meeting elected officials and NYPD highlighted the access problems to the zoo and also identified accident prone areas surrounding the Bronx Zoo. The final draft report was circulated to NYCDOT Traffic Planning and NYC Department of Parks and Recreation. Parks representatives were briefed on the project alternatives. NYC Department of Parks and Recreation and NYCDOT Traffic Planning offered their comments which are included in Chapter VI, Minutes of Meetings, Correspondence, and Comments.
The comments and concerns of the NYC Department of Parks and Recreation and NYSDOT Traffic Engineering and Safety unit were not addressed in this report primarily because of funding constraints. However, they will be addressed along with revisiting all alternatives in the subsequent design phase of the project. An electronic copy of this report is available through the NYSDOT, Region11, Planning Department.
Additional information regarding the project can be obtained from:
Larry T. Malsam NYSDOT - Region 11 Planning & Development Hunters Point Plaza Long Island City, NY 11101 (718) 482-4559 Attn: Fred Libove, P.E.
7
PSR April 24, 2006 Zooreport.doc
II. Project Identification, Evolution, Conditions and Needs, and Objectives
A. Project Identification
1. Project Type
This project involves traffic safety, operations and access improvements intended to maximize utilization of existing facilities and enhance the connectivity of the various roadways as needed in the vicinity of Bronx River Parkway, Boston Road and Pelham Parkway.
2. Project Location
This project location is in the Borough of Bronx, as shown in Figure 1. The project study areas, as shown in Figure 2, extend from Boston Road to the east, Bronx River Parkway (and its service road) to the west, Bronx River Parkway Interchange 7 (Pelham Parkway) to the north and Bronx River Parkway Interchange 6 to the south.
The overall project area for this study is separated into two study areas - Primary and Secondary study areas (See Figure 2). The primary study area is comprised of the transportation roadway link and nodes immediate to the Bronxdale Gate parking lot.
B. Project Evolution
The Bronx Zoo completed the Traffic Access and Improvement Study for The Bronxdale Gate and Parking Area in December 1982. The 1982 study addressed accessibility and mobility issues in dealing with the vehicular access to the Bronxdale Gate entrance to the Bronx Zoo. A few minor improvements were implemented by the Zoo as a result of the 1982 study, including increasing the number of Zoo entrance gates from two to four. In this study, many of the problems and recommendations identified in the 1982 study have been revisited in conjunction with the evaluation of roadway system connectivity needs and impacts to Bronx River Parkway and local roadway network (Boston Road, Pelham Parkway, and Bronx Park East). Representatives of the zoo have identified the need to increase usage for the Bronxdale Gate by enhancing the accessibility of the Zoo via the nearby highway and local street network. It is anticipated that the zoo=s needs can be met.
- - 8
't Figure 1 Project Location Map TWS F!GVPF 2 NEN/YORK4ATEDEPARLNEN7CFTRAPSPOR7AT10N 3RONXRIVERPAkKI'/AY AREA MAP PIN_ X110.1' PRC7EQ AREA_ ThMS, en EevN Teeh C mpeny PSR April 24, 2006 Zooreport.doc The Wildlife Conservation Society-Bronx Zoo and NYSDOT R11-Planning and Development Unit identified the need for this access improvement study. Since NYSDOT maintains jurisdiction over Bronx River Parkway and NYCDOT over Boston Road, Pelham Parkway, Bronx Park East, and the surrounding local streets, any capital improvement in the vicinity of the Bronx Zoo must be coordinated with the corresponding agencies. A project kick-off scoping meeting was held in January, 2002. Subsequent meeting with NYSDOT further defined the scope of this study. In April 2002 a field visit and meeting was conducted and attended by the State, NYPD, community and Bronx Zoo officials. C. Conditions and Needs The primary historic data source for the project is the 1982 Bronx Zoo Study. The latest available traffic and accident data, along with existing field condition data, were collected for this study. 1. Transportation Conditions and Engineering Considerations a. Functional Classifications and Federal Aid System Pelham Parkway and Boston Road (US-1) are most closely classified and function as Urban Arterials under the State=s functional classification system. They provide local access and traffic circulation within the project study area while serving as connectors for freeway-to-freeway traffic between the Major Deegan Expressway (I-87), Bronx River Parkway, Hutchinson River Parkway (I-678) and New England Thruway (I-95). Boston Road (US-1) is also a federal designated local truck route by the NYCDOT providing truck access and goods transportation movement to the local communities. The Bronx River Parkway is a designated State highway with commercial vehicle restriction. It meets the Bruckner Expressway (I-278) to the south and the Sprain Brook Parkway and Taconic State Parkway to the north. b. Ownership and Maintenance Jurisdiction Roadway Ownership / Maintenance Jurisdiction Boston Road/Bronx Park East NYCDOT / NYCDOT Bronx River Parkway and Ramps NYSDOT / NYCDOT Pelham Parkway NYCDOT / NYCDOT c. Culture, Terrain and Climatic Conditions Land use in the primary study area is entirely NYC Department of Parks and Recreation. The adjacent land use primarily consists of urban residential, commercial, automobile repair facilities, and gas station. Areas west of Bronx Park East are designated as park - - 9 PSR April 24, 2006 Zoorepor.doc areas (Ben Abrams Park) by the NYC Department of Parks and Recreation. The Bronx River Parkway and Pelham Parkway run through areas designated as park property. Based on field observations, the terrain along the existing roadway of Boston Road, Pelham Parkway and Bronx Park East is generally level, with the exception of the various grade separated interchange approaches to/from the Bronx River Parkway. No unusual climatic conditions are expected within this project study area. d. Control of Access The Bronx River Parkway is a fully controlled access facility in the project area. The local street network, namely Boston Road, Bronx Park East and Pelham Parkway, provides uncontrolled access from secondary streets and commercial driveways such as auto service and gas stations, and other traffic generators and destinations. e. Existing Highway Section 1- Eastbound Pelham Parkway This segment of Pelham Parkway is also known as Fordham Road (west of Boston Road). Pelham Parkway is a divided roadway with wide grassy median segregating the eastbound and westbound roadway. The secondary focus of this study, however, deals only with the eastbound Pelham Parkway intersection with Boston Road. The intersection of the westbound Pelham Parkway with Boston Road is beyond the scope of this current study. The Bronx River Parkway is a six-lane north-south non-commercial controlled access principal urban arterial providing direct connection between the Bruckner Expressway (I-278) and Cross Bronx Expressway (I-95) to the south and Sprain Brook Parkway and Cross County Parkway to the north. Pelham Parkway (also known as Fordham Road west of Boston Road) serves as a major east-west arterial roadway connecting the Major Deegan Expressway (I-87) to the west and Hutchinson River Parkway and I-95 to the east. Pelham Parkway also serves as a critical transportation link across the Bronx serving various facilities such as the Bronx Zoo, Fordham University, Jacobi Medical Center, and Pelham Bay Park. There are three approaches to this signalized intersection serving both the north and southbound traffic on Boston Road and the eastbound traffic from Fordham Road and the northbound Bronx River Parkway exit (See Figure 3). The eastbound 10 PSR April 24, 2006 Zoorepor.doc approach consists of four lanes. Three lanes (11-12ft. each) approach from eastbound Fordham Road and one merging lane (12 ft.) from the exit ramp from northbound Bronx River Parkway at Interchange 7. The existing eastbound approach creates movement conflicts between vehicles coming off the exit ramp and those from Fordham Road. 2- Boston Road (US-1) from Bronx Park East to Pelham Parkway This segment of Boston Road is an undivided roadway carrying two lanes of traffic in each direction. The width of each travel lane is approximately 11 ft. with 8 ft. parking lanes on both side of the roadway. This segment of Boston Road serves as the connector between the Bronx River Parkway and Pelham Parkway and Bronx Park East. Curbside parking is permitted in both directions of Boston Road south of Pelham Parkway, with the exception of the bus stops and driveway access to the gas station at the southeast corner of Boston Road/Eastbound Pelham Parkway (See Figure 4). 3- Boston Road (US-1) from Bronx Zoo to Bronx Park East This segment of Boston Road is an undivided roadway carrying a single lane of traffic in each direction. The width of each travel lane is approximately 12 ft. Boston Road traverses underneath the Bronx River Parkway east of the Bronxdale Gate parking lot to the Zoo. Boston Road not only serves as the connector between the Bronx River Parkway and Pelham Parkway and Bronx Park East to the east, it also serves as the entrance and exit to the Bronxdale Gate of the Bronx Zoo. Curbside parking is prohibited in both directions of Boston Road between Bronx Park East and the Zoo gate (See Figure 5). 4- Bronx River Parkway The Bronx River Parkway is a six-lane divided roadway carrying three lanes of non- commercial traffic in each direction. Lane widths are approximately 3.6 m (11 ft). This segment of the Bronx River Parkway consists of a full cloverleaf interchange at Pelham Parkway (Interchange 7), and a special all direction grade separated interchange at Boston Road (Interchange 6). The Bronx River Parkway is a six-lane north-south non-commercial controlled access principal urban arterial providing direct connection between the Bruckner Expressway (I-278) and Cross Bronx Expressway (I-95) to the south and Sprain Brook Parkway and Cross County Parkway to the north. Pelham Parkway (also known as Fordham Road west of Boston Road) serves as a major east-west arterial 11 GREEN 3 SEO 3 SEC S SEC -, YELLOW 3 SEC SEC FCD- 4O SEC 50 A11-PEO 2 SEC 2 SEC MOVEMENS CYCLE LENGTH ' 90 SEC IGNAllZED INTERSECTION AT EH PET.RAM PARKWAY/BOSTON ROAD FIGURE 3 . NEW YORK STATE DEPARTMENT OFTRANSPORTACON RONX 200 ACCES S PiN %110 .23 ISIPROV2MFST5 YSR 1M9. nn Tea'CM TecL Cempevy PSR April 24, 2006 Zoorepor.doc roadway connecting the Major Deegan Expressway (I-87) to the west and Hutchinson River Parkway and I-95 to the east. Pelham Parkway also serves as a critical transportation link across the Bronx serving various facilities such as the Bronx Zoo, Fordham University, Jacobi Medical Center, and Pelham Bay Park. f. Abutting Highway Segments and plans for Abutting Highway Segments 1- Interchange Improvements at Bronx River Parkway and East 177th Street (PIN X110.18.101) The Expanded Project Proposal for the Interchange Improvements at Bronx River Parkway and East 177th Street study was completed in August, 2000. Due to the relative close proximity and roadway connectivity of this current study, the recommended interchange improvement at BRP/East 177th Street will greatly benefit mobility and accessibility to all visitors to the Bronx Zoo who originated from the south or the west. The interchange improvement at BRP/East 177th Street will provide direct freeway-to-freeway movements between Arthur Sheridan Expressway and Bronx River Parkway. However, the improvements recommended under PIN X110.18 has not been advanced. 2-Bruckner/Sheridan Expressway Interchange Improvement (PIN X730.39) Due to the close proximity of the Bruckner/Sheridan Expressway Interchange to the East 177th Street/Bronx River Parkway Interchange, both projects must be coordinated with each other in terms of project development as well as the maintenance and protection of traffic (MPT) scheme and environmental processing. The EPP for the Bruckner/Sheridan Expressway Interchange Improvement study was approved by NYSDOT in October of 1997. This project is currently in the preliminary design phase. 3-Interim and Full Rehabilitation Programs for the CBE (PIN X726.81 & X726.80) As part of the overall rehabilitation program for the CBE, interim and full rehabilitation (PIN X726.81 and X726.80) fis programmed or the interchanges between the northbound and southbound ASE and the CBE. The existing northbound ASE ramp to the westbound CBE is geometrically non-standard. Interim rehabilitation work was performed in the summer of 1998 at these locations. 4- Bronx River Greenway Project (PIN X027.05) 12 PSR April 24, 2006 Zoorepor.doc NYSDOT is currently developing the Bronx River Greenway Project along the Arthur Sheridan Expressway. The proposed Greenway will enhance recreational facilities along the Bronx River by providing a bicycle and pedestrian path through the current project area. 5- Bronx River Parkway Bridge Rehabilitation Project (PIN X110.19.121) The project includes the replacement of three bridges carrying the Bronx River Parkway over Amtrak/CSX, east Tremont Ave., and East 180th St. /Morris Park Ave. /NYCTA Unionport Yard. These bridges are located between the subject project and the BRP/E. 177th Street project referred to in the EPP. Letting is currently scheduled for March 2007. 6- Pelham Parkway Reconstruction, BRP to Stillwell Ave., NYCDOT Phase I of this Project is for the portion of Pelham Pkwy East of Boston Road. Phase I is schedule to start construction in Fiscal Year 2008. Phase II, west of Boston Road is scheduled to start construction in Fiscal Year 2010. As the Pelham Pkwy reconstruction project directly interfaces with PIN X110.23, an ongoing coordination effort will be needed. 7- Potential Parking Garage at the Bronx Zoo Bronxdale Gate (pending funding approval) The wildlife Conservation Society (WCS) in partnership with the NYC Department of Cultural Affairs has proposed an intermodal parking structure at the Boston Road entrance to the zoo. It is roughly estimated that the facility (pending funding approval from FTA) will have 1000 parking spaces. 8- Bronx Arterial Needs Major Investment Study (BANMIS) The BAN-MIS was completed in March 2004. The study recommended various mobility and operational improvements to the Major Deegan Expressway (MDE) and Cross Bronx Expressway (CBE). The short list of improvements recommended for advancement to the preliminary Design phase includes: - MDE Auxiliary lanes at selected locations. - CBE Connector road for Bus and HOV use The CBE Connector Roads are currently being considered for inclusion in the CBE structural rehabilitation projects. 13