82. SH. LAKSHMAN NAPA, M.L.A.: Will the Deputy Chief Minister be pleased to state:-

a) whether it is a fact that the traffic is a big problem in city due to which traffic remain Jammed in the city all the time; and b) whether there is any proposal under consideration of the Government to construct a bye pass in Ratia city if so, the details thereof ? ______

DUSHYANT CHAUTALA, DEPUTY CHIEF MINISTER, ______(a) & (b) No, sir.

UNSTARRED ASSEMBLY QUESTION NO. 82 RAISED BY

LAKSHMAN NAPA, M.L.A, RATIA CONSTITUENCY

NOTE FOR PAD

Regarding traffic congestion in the city portion Ratia, it is brought out that there is already 4-lanned existing road i.e Budhada- Ratia- Fatehabad Road (SH-21) and 4- lanned - Ratia Road (MDR-101). It is also brought out that in the remaining portion of ROW on both side, interlocking paver blocks have been provided. The total land width of these roads is 82’-6”. However, a bye-pass for Ratia city was proposed in the detailed project report (DPR) for Fatehabad-Ratia-Budhlada Mandi road. It is brought out that Fatehabad-Ratia-Budhlada Mandi was declared as “In Principle” National Highway vide Ministry of Road, Transport & Highways (MoRT&H) letter No. NH-14012/30/2015-P&M dt. 08/02/2016 and MoRT&H directed to prepare DPR of this road stretch. Subsequently, work of preparation of DPR was awarded to M/s ARKITECHNO Consultants () Pvt. Ltd. The consultant submitted alignment report for the Fatehabad-Ratia-Budhlada Mandi road which included Ratia Bypass. This alignment was submitted to MoRT&H for approval vide office of EIC PWD B&R letter No. 188418/NH dated 11.11.2017 after approval from Government of Haryana. The alignment was subsequently, discussed in the meeting held under chairmanship of Secretary, Road, Transport & Highway, Government of India on 20.08.2018 and during the meeting, it was opined that declaration of Fatehabad-Ratia-Budhlada Mandi road as National Highway will only create a parallel artery to the already existing NH-703 and NH-148B and would not be beneficial for NH traffic. Accordingly, it was decided in the meeting that the proposal for declaration of “Fatehabad-Ratia-Budhlada Mandi road” as National Highway is not recommended. Since, Fatehabad-Ratia-Budhlada Mandi road could not be declared as National Highway, the proposed Ratia bypass could not be taken up with MoRT&H for execution. In view of above, it is intimated that there is no proposal under consideration of the Government to construct bye pass in Ratia City.

(A) Total road Length in Ratia Constituency is as under:-

Road Length

i) State Highway (SH) -- 33.45 km ii) Major District roads (MDR) -- 33.98 km iii) Other District roads (ODR) -- 438.83 km iv) Recently transferred from HSAMB -- 98.81 Km Total:- -- 605.07 km

(B) Condition of road in Ratia Constituency

i) Road length in very good condition -- 382.02 Km. ii) Road Length in good condition -- 25.76 Km. iii) Road length which require treatment -- 208.81 Km. iv) Road Length in which work is in progress -- 040.00 Km. Total -- 605.07 Km.

(C) Patch work/pot holes repair/surface dressing done from 1st September, 2019 to 30th November, 2019.

(i) Pot hole repairs carried out = 0.00 Km. (ii) Surface dressing done = 0.00 Km

(D) Target of patch work Pothole repair/Surface dressing from 1st February, 2020 to 30th April, 2020.

(i) Pot hole repair = 0.00 Km. (ii) Surface dressing = 0.00 Km.

(E) Length of roads constructed / repaired in Ratia Constituency from 01.04.2015 to 31.01.2020:

Sr. Item 2015-16 2016-17 2017-18 2018-19 2019-2020 Total No. (01/2020)

1 Construction 7.10 - 10.75 18.538 7.872 44.26 of new roads 2 Widening/ 97.07 73.44 34.53 120.29 - 325.33 Strengthening/ Raising etc. 3 Improvement 35.30 33.09 20.00 80.32 10.20 178.91 of Road Total 139.47 106.53 65.28 219.148 18.072 548.50

(Length in km)

(F) In Ratia Constituency year wise expenditure incurred on various road activities is as under:- i) 01.04.2015 to 31.01.2020 –Ratia Constituency Expenditure-Roads

Sr. Item 2015-16 2016-17 2017-18 2018-19 2019-2020 Total No. (01/2020)

1 Construction 308.19 71.81 564.97 397.70 906.89 2249.56 of new roads 2 Widening/ 206.09 814.66 755.31 87.86 417.39 2281.31 Strengthening/ Raising etc. 3 Cement 0.00 43.00 43.37 0.00 - 86.37 Concrete/ Block pavement 4 Annual 100 0 0.00 0.00 - 100.00 surfacing/pre mix carpet of roads. 5 Annual 134.59 34.37 0.00 27.59 30.39 226.94 maintenance of roads 6 Special Repair 288.37 318.75 142.31 973.15 205.65 1928.23

7 PMGSY 0 0 0.00 0.00 - 0

Total 1037.24 1282.59 1505.96 1486.30 1560.32 6872.41

(G) Details of year wise expenditure incurred on the building works falling under Ratia constituency for the period from 01.04.2015 to 31.01.2020

2015-16 2016-17 2017-18 2018-19 2019-2020 Total (01/2020) 485.44 372.62 0.00 264.05 170.81 1292.92

(Rs. in lacs) (H) Details of year wise expenditure incurred on the bridge works falling under Ratia constituency for the period from 31.10.2014 to up to date (i.e. 31.01.2019)

2015-16 2016-17 2017-18 2018-19 2019-2020 Total (01/2020) 0.00 0.00 83.49 146.70 - 230.19

(Rs. in lacs) (H) Since 01.04.2015 to till date, following works have been completed. (a) Road Work

(i) Work Programme for the year 2013-14 under SCSP Components in Provincial Sub Division No. 1, PWD B&R Br., Fatehabad. (14 Nos. Road) (5516, 5478, 5506, 5521, 5625, 5499, 5518, 5533, 5536, 5537, 5627, 5496, 5514, 5509) in (C. M. Announcement Code No. 9763 on dated 30.12.2014) with an estimated cost of Rs. 4.11 crore Under SCSP Scheme. Date of completion 31.03.2016.

(ii) Constructing a Road from Village Bahamanwala to Reyond Up to Punjab Border in Fatehabad District (C. M. Announcement Code No. 9763 on dated 30.12.2014) with an estimated cost of Rs. 1.51 crore under head 5054-R&B (P). Date of completion 31.03.2016.

(iii) Special Repair of Tohana Dharsul Ratia to State Border Km 25.00 to 34.15 (Road ID 5468) (G-6) in Fatehabad District with an estimated cost of Rs. 2.19 crore under head 3054 R&B (NP). Date of completion 31.03.2016.

(iv) Special Repair of various Road :- (i) Bhuna Ratia Road to Digoh (ID 5595), (ii) Aherwan to Dhani Ruriwali (ID 5538), (iii) Fatehabad Hanspur road to Rattatibba (ID 5539), (iv) DHS road to Khairati Khera (ID 5633) and; (v) Alipur Barota road (5529) with an estimate cost on Rs. 1.88 Crore under Head 3054 R&B (NP) in Fatehabad District Date of completion of this work is 04-08-2016.

(v) Constructing a Road from Village Nagpur to Nakta in Fatehabad District (C. M. Announcement Code No. 9763 on dated 30.12.2014) with an estimated cost of Rs. 1.59 Crore under Head 5054 R&B (P). Date of completion 30.09.2016.

(vi) Tohana Dharsul Ratia to State Border road (Ratia to State Border) (MDR-101) (ID No. 5468) Km 34.15 to 36.00, 39.00 to 50.00 & 52.00 to 57.98 in Fatehabad District (C. M. Announcement Code No. 9763 on dated 30.12.2014) with an estimated cost of Rs. 12.39 crore under head 5054-R&B (P) Date of completion 31.01.2017.

(vii) Special Repair of Ratia Fatehabad Road to Dhani Dadi Jakhan (Road ID 5543) in Fatehabad District with an estimate cost on Rs. 0.50 Crore under Head 5054 R&B (P). Date of Completion of this work is 09/2016.

(viii) Providing & Laying Premix Carpet with seal coat on Ratia Fatehabad road to Sheikhpur Sottar Km. 5.70 to 6.81 (Road ID 5551) under Head 5054 ODR (Group-3) with an estimate cost on Rs. 0.86 Crore in Fatehabad District Date of Completion of this work is 09/2016.

(ix) Improvement of Ratia Rori road to Rattakhera Km. 0 to 0.55 Work Programme 2016-2017 in Ratia Constituency (Road ID 5488) with an estimate cost on Rs. 19.08 Lacs.under Head 3054 R&B (NP) in Fatehabad District Date of Completion of this work is 01/2017.

(x) Improvement of various roads under head 5054 ODR SCSP scheme Work Programme 2016-2017 in Ratia Constituency (Road ID 5500, 5504, 5516 & 5483). (Group-21) (Tender No. 18621) with an estimate cost on Rs. 350.00 Lacs in Fatehabad District Date of Completion of this work is 12/2016.

(xi) Improvement of road from Rattangarh to Pilchiyan Km. 0 to 16.00 under Head 5054 ODR Work Programme 2016-2017 in Ratia Constituency (Road ID 5476) (Group-19) with an estimate cost on Rs. 527.65 Lacs under Head 5054 R&B (P) in Fatehabad District Date of Completion of this work is 05/2017.

(xii) Providing & Laying Premix Carpet with Seal Coat on various roads under Head 3054 R&B (NP) ODR for the year 2017-18 (Road ID 5441, 5389, 5648, 5649, 5492, 5420, 5624, 5552, 5554, 5568, 5497, 5512, 5350, 5544, 5503, 10179, 5519, 9111, 5576, 5614, 9072, 5556, 5379, 5579, 5603, 5610 & 5365) with an estimate cost on Rs. 729.75 Lacs in Fatehabad District Date of Completion of this work is 10.05.2018

(xiii) Special Repair on various roads under Head 3054 R&B (NP) ODR For the year 2017-18 in Ratia Constituency (Road ID 5475, 5501, 5478 & 5555) (Group-2) with an estimate cost on Rs. 465.15 Lacs in Fatehabad District Date of Completion of this work is 03.07.2018

(xiv) Special Repair on various State Highways under Head 3054 R&B (NP) For the year 2017-18 in Ratia Constituency (Road ID 5546 & 5567) (Group-3) with an estimate cost on Rs. 315.00 Lacs in Fatehabad District Date of Completion of this work is 29.06.2018

(xv) Special Repair on various roads under Head 3054 R&B (NP) ODR For the year 2017-18 in Ratia & Fatehabad Constituency (Group-10) (Road ID 10170, 9102, 5632, 5638, 5517, 5515, 5530, 5521, 5482 & 9104) with an estimate cost on Rs. 654.15 Lacs in Fatehabad District Date of Completion of this work is 16.11.2018.

(xvi) Special Repair of various roads under Head 5054 R&B (P) ODR For the year 2017-18 in Tohana & Ratia Constituency (Group-8) (Road ID 5407, 9030, 5600, 9071, 9029 & 5598) with an estimate cost on Rs. 566.35 Lacs in Fatehabad District Date of Completion of this work is 24.07.2018.

(xvii) Special Repair on various roads under Head 5054 R&B (P) ODR for the year 2017-18 in Ratia Constituency (Group-12) (Road ID 5531, 5480, 9060, 10182 & 5562) with an estimate cost on Rs. 283.50 Lacs in Fatehabad District Date of Completion of this work is 22.10.2018.

(xviii) Special Repair on various roads under Head 5054 R&B (P) ODR For the year 2017-18 in Ratia Constituency (Group-13) (Road ID 5481, 5498, 5564 & 10178) with an estimate cost on Rs. 563.85 Lacs in Fatehabad District Date of Completion of this work is 22.10.2018. (xix) Improvement of road from Ratia to Babanpur road Km. 0 to 14.80 under Head 5054 ODR Work Programme 2016-2017 in Ratia Constituency (Road ID 5477) (Group-20) with an estimate cost on Rs. 410.00 Lacs in Fatehabad District Date of Completion of this work is 05/2017.

(xx) Constructing a road from village Nakta to Khumber in Fatehabad District (CM announcement code No. 9763 dated 30.12.2014) with an estimated cost of Rs. 2.07 crore under head 5054 R&B (P). Date of Completion of this work is 13.11.2017.

(xxi) Constructing a road from village Malhar to Chuganwali road in Fatehabad District (CM announcement code No. 9763 dated 30.12.2014) with an estimated cost of Rs. 0.36 crore under head 5054 R&B (P). Date of Completion of this work is 14.12.2017.

(xxii) Constructing a road from village Chankoti to Malhar road in Fatehabad District (CM announcement code No. 15091 dated 28.08.2016) with an estimated cost of Rs. 202.12 Lacs under head 5054 R&B (P). Date of Completion of this work is 13.06.2018.

(xxiii) Constructing a road from village Noorki Ahli to Jandwala Sottar road in Fatehabad District (CM announcement code No. 15093 dated 28.08.2016) with an estimated cost of Rs. 201.58 Lacs under head 5054 R&B (P). Date of Completion of this work is 13.06.2018.

(xxiv) Constructing a road from village Bara to Bhani Khera road in Fatehabad District (CM announcement code No. 15101 dated 28.08.2016) with an estimated cost of Rs. 115.28 Lacs under head 5054 R&B (P). Date of Completion of this work is 31.05.2018.

(xxv) Constructing a road from Alipur Barota to Binja Lamba road in Fatehabad District (CM announcement code No. 15105 dated 28.08.2016) with an estimated cost of Rs. 117.30 Lacs under head 5054 R&B (P). Date of Completion of this work is 08.07.2018.

(xxvi) Constructing a Road from Village Rojanwali to Bhunderwas Km 0 to 2.60 (C. M. Announcement Code No. 15099) in Fatehabad District with an estimated cost of Rs. 147.05 Lacs under head 5054 R&B (P). Date of Completion of this work is 08.07.2018.

(xxvii) Constructing a Road from Village to Nakhatia Road (C. M. Announcement Code No. 15090 dated 28.08.2016) in Fatehabad District with an estimated cost of Rs. 88.19 Lacs under head 5054 R&B (P). Date of Completion of this work is 29.12.2018.

(xxviii)Construction of Road from to Jandwala Sottar (C. M. Announcement Code No. 15095 dated 28.08.2016) in Fatehabad District with an estimated cost of Rs. 154.96 Lacs under head 5054 R&B (P). Date of Completion of this work is 29.12.2018. (xxix) Improvement of various road under head 5054 ODR Work Programme 2016-2017 in Fatehabad Constituency in Fatehabad District (Road ID 5339 & 5593) (Group- 11) with an estimated cost of Rs. 3.20 lacs. Date of completion 29.06.2017.

(xxx) Improvement of various roads work programme 2016-17 (Road ID 9066, 5505, 5511 & 5540) in Fatehabad District with an estimated cost of Rs. 3.64 crore. Date completion 24.08.2017.

(xxxi) Improvement of Tohana Dharsul Ratia road (MDR-101) Km. 17.60 to 20.00 & 22.50 to 25.00 under Head 5054 MDR Work Programme 2016-2017 in Ratia Constituency under Provincial Division, PWD B&R Fatehabad (Road ID 5370). (Group-9) with an estimated cost of Rs. 2.44 crore. Date of completion 18.05.2017. (xxxii) Improvement of Road from Section Tohana Kullan Ratia upto Punjab State Border (Road ID 5370 & 5468) Km 17.60 to 34.15 (MDR-101) in Fatehabad District Estimated cost of Rs. 2.80 crore under NABARD Scheme. Date of completion 30.11.2019.

(xxxiii)Construction of Road from Khumber to Haroli (CM announcement code No. 15092 dated 28.08.2016) in Fatehabad District with an estimated cost of Rs. 224.56 Lacs under head 5054 R&B (P). Date of completion 11.12.2019.

(xxxiv) Construction of Road from Village Mirana to Main Road (CM announcement code No. 15100 dated 28.08.2016) in Fatehabad District with an estimated cost of Rs. 87.42 Lacs under head 5054 R&B (P). Date of completion 21.12.2019.

(xxxv) Construction of Road from Hanspur to Dhingana upto Punjab Border (CM announcement code No. 15104 dated 28.08.2016) in Fatehabad District with an estimated cost of Rs. 201.71 Lacs under head 5054 R&B (P). Date of completion 12.12.2019.

(b) Building Work

(i) Construction of Primary Health Centre and Residential Building at Village Khairati Khera in Fatehabad District with an estimated cost of Rs. 2.07 crore. Date of completion on 15.03.2015.

(ii) Construction of Primary Health Centre at Village Aherwan in Fatehabad District with an estimated cost of Rs. 1.38 crore. Date of completion on 16.09.2014.

(iii) Construction of Construction of Primary Health Centre with 1220 Sft. 1 No. Residence & 4 No. 440 Residence at Village Hasinga in Fatehabad District with an estimate cost of Rs. 2.00 crore. Date of completion on 24.10.2014.

(iv) Construction of Primary Health Centre at Village Mehmra in Fatehabad District with an estimated cost of Rs. 1.33 crore. Date of completion on 22.10.2014.

(v) Construction of the Building of Govt. College for Women at Ratia in Fatehabad District with an estimate cost of Rs. 10.51 crore work completed 30.04.2016.

(vi) Up-gradation from 30 Bedded to 50 Bedded Community Health Centre at Ratia in Fatehabad District Including Civil + PH + EI Works with an estimate cost on Rs. 64.12 Lacs. Date of completion on 06/2017.

(vii) Construction of Govt. Veterinary Hospital at Ratia in Fatehabad District (I/c Civil, P.H., E.I. Internal Services, Road Parking & Boundary Wall) with an estimate cost of Rs. 72.28 Lacs work completed 09.04.2018.

(viii) Construction of Facilitation Centre in Stadium at Village Bhodia Khera in Fatehabad District (I/c Civil, P.H., E.I. Internal Services, Road Parking & Boundary Wall) with an estimate cost of Rs. 3.25 crore work completed 23.05.2018.

(ix) Construction of Govt. Veterinary Dispensary at village Allalwas in Fatehabad DIstt estimated cost of Rs. 0.33 crore under head 8443. Date of completion on 10.03.2019.

(c) Bridge Work:- -Nil-

(I) Following works are in progress.

(a) Road Work (i) Construction of Road from Khundan to Khumber (CM announcement code No. 15094 dated 28.08.2016) in Fatehabad District with an estimated cost of Rs. 288.81 Lacs under head 5054 R&B (P). Likely date of completion 11.12.2019.. (ii) Construction of Road from Rattakhera to Tamaspura (CM announcement code No. 15097 dated 28.08.2016) in Fatehabad District with an estimated cost of Rs. 216.83 Lacs under head 5054 R&B (P). Likely date of completion 12.12.2019. (iii) Construction of Road from Daulatpur to Karian via Dhani Ishar (CM announcement code No. 15102 dated 28.08.2016) in Fatehabad District with an estimated cost of Rs. 344.54 Lacs under head 5054 R&B (P). Likely date of completion 15.09.2020. (iv) Construction of Road from Sardarewala to Bhimra upto Punjab Border (CM announcement code No. 15103 dated 28.08.2016) in Fatehabad District with an estimated cost of Rs. 123.51 Lacs under head 5054 R&B (P). Likely date of completion 12.12.2019. (v) Construction of road from Hijrawan Kalan to Akkawali Road in Fatehabad District (CM announcement code No. 24366 dated 06.11.2018) with an estimated cost of Rs. 2.11 crore under head 5054 R&B (P). Likely date of completion 16.01.2020. (vi) Construction of road up to Khaira (Punjab Border) in Village Bhattu Sottar in Fatehabad District (CM announcement code No. 24367 dated 06.11.2018) with an estimated cost of Rs. 1.69 crore under head 5054 R&B (P). Likely date of completion 16.01.2020. (vii) Construction of road Village Akkawali to Bhoria Khera in Fatehabad District (CM announcement code No. 24369 dated 06.11.2018) with an estimated cost of Rs. 2.27 crore under head 5054 R&B (P). Likely date of completion 11.01.2020. (viii) Construction of road Village Mussali to Khumber in Fatehabad District (CM announcement code No. 24373 dated 06.11.2018) estimated cost of Rs. 1.85 crore under head 5054 R&B (P). Likely date of completion 21.02.2020. (ix) Improvement by Providing and Laying 20 mm thick Premix Carpet on Various ODRs in PSD No. 1 Fatehabad in the Jurisdiction of Provincial Division PWD BandR Fatehabad (Road ID 5475, 9102, 9101, 9052, 5639, 5508, 5510, 5534, 5621, 5628, 10180, 10182, 10181 and 5601) (Group-2) 2018-19 with an estimated cost of Rs. 4.45 crore under head 3054 R&B (NP). Likely date of completion 17.05.2020. (x) Improvement and Providing 20 mm thick Premix Carpet of Various Roads in PSD No. 1 Fatehabad in the Jurisdiction of Provincial Division, Fatehabad in Fatehabad District (Road ID 5572, 10177, 5651, 10172, 5360, 9046 and 5338) with an estimated cost of Rs. 3.32 crore under head 3054 R&B (NP). Likely date of completion 04.08.2020. (xi) Improvement of Ratia Fatehabad Road to Sheikhupur Sottar Km 0 to 5.70 & 6.81 to 8.25 (Road ID 5551) in Fatehabad District (NABARD RIDF-XXIV) (Part-B) under NABARD Scheme. Likely date of completion 18.03.2020. (xii) Construction of road Village Chuganwali to Jandwala in Fatehabad District (CM announcement code No. 24375 dated 06.11.2018) estimated cost of Rs. 2.23 crore under head 5054 R&B (P). Likely date of completion 19.03.2020. (b) Building

i) Construction of SDO Civil Complex (Administrative Block) at Ratia in Fatehabad District (i/c Civil, P.H., E.I. Internal Services, Road Parking & Boundary Wall) (C. M. Announcement Code No. 10278 dated 31.05.2015) with an estimate cost on Rs. 914.80 Lacs. Last date of Completion of this work is 28.02.2020.

(c) Bridge: Nil

(J) Following works are in pipe line: (a) Road Work:- Nil

(b) Building Work:- Nil

(c) Bridge Work:- Nil