Attachment 1
Project Narrative
www.essgroup.com
TABLE OF CONTENTS
SECTION PAGE 1.0 INTRODUCTION ...... 1 1.1 Purpose and Need ...... 1 2.0 DETAILED PROJECT DESCRIPTION ...... 2 2.1 Description and Location of Proposed West Point Project ...... 2 2.1.1 Northern Interconnection ...... 3 2.1.2 Northern AC Cable Route ...... 3 2.1.3 Northern Converter Station ...... 4 2.1.4 Northern Land Cable Route ...... 4 2.1.5 In-River Cable Route ...... 4 2.1.6 Southern Land Route ...... 8 2.1.7 Southern Converter Station ...... 8 2.1.8 Southern AC Cable ...... 8 2.1.9 Southern Interconnection ...... 9 2.2 In-River Cable Coexistence with Champlain-Hudson Power Express ...... 9 2.2.1 West Point Project In-River Cable Installed Prior to CHPE Project Cable (Alternative 1A) ... 9 2.2.2 CHPE Project Cable Installed Prior to West Point Project In-River Cable (Alternative 1B) . 10 2.3 Description of Proposed Transmission Line ...... 11 2.3.1 Project Components ...... 12 2.3.2 320 kV DC Circuit ...... 12 2.3.2.1 In-River Cable ...... 12 2.3.2.2 HVDC Land Cable ...... 13 2.3.3 AC Land Cable ...... 13 2.3.4 Fiber Optic Communications Cable ...... 14 2.4 Description of Converter Stations ...... 14 2.4.1 VSC-HVDC Converter Stations ...... 14 2.4.2 Control and Protection ...... 16 2.4.3 Cooling Systems ...... 16 2.4.4 Fire Protection ...... 16 2.5 Installation Methods and Means ...... 16 2.5.1 Anticipated Project Schedule ...... 16 2.5.2 Cable System Installation ...... 17 2.5.2.1 Land Cables ...... 17 2.5.2.2 Landfall Transitions ...... 18 2.5.2.3 Horizontal Directional Drilling ...... 19 2.5.2.4 In-River Cable ...... 22 2.5.3 Cable System Reliability ...... 24 2.5.4 Cable System Maintenance ...... 24 2.5.5 Converter Station Construction ...... 25 2.6 In-River Cable Burial Depth ...... 26 3.0 ALTERNATIVES ANALYSIS ...... 27 3.1 Purpose and Need ...... 27 3.2 No Action Alternative ...... 27 3.3 Selection of Interconnecting Substations ...... 28 3.3.1 Criteria for Selection of Interconnecting Substations ...... 28 3.3.2 Northern Interconnection Substation Alternatives ...... 28 3.3.2.1 National Grid Leeds Substation ...... 28 3.3.2.2 Alternative Northern Interconnection Substations ...... 28 3.3.3 Southern Interconnection Substation Alternatives ...... 29 3.3.3.1 Buchanan Substation ...... 29 3.3.3.2 Alternative Southern Interconnection Substations ...... 29 3.3.4 Comparisons and Selection of Interconnection Substations ...... 29
© 2013 ESS Group, Inc. k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc
TABLE OF CONTENTS (CONTINUED)
SECTION PAGE
3.4 Selection of Project Converter Station Locations ...... 29 3.4.1 Criteria for Selection of Converter Station Locations ...... 29 3.4.2 Northern Converter Station ...... 30 3.4.3 Southern Converter Station ...... 31 3.4.4 Comparisons and Selection of Converter Station Locations ...... 31 3.5 Selection of Transmission Line Routes and Landfalls – Overview ...... 31 3.5.1 Overhead versus Buried ...... 31 3.5.2 Underground versus Underwater ...... 32 3.5.3 Route and Landfall Alternatives ...... 33 3.6 Selection of Transmission Line Routes ...... 33 3.6.1 Criteria for Selection of Routes ...... 33 3.6.2 Summary of Proposed Route (Preferred Alternative – R1) ...... 34 3.6.3 In-River Alternatives Evaluated ...... 34 3.6.3.1 In-River Cable Coexistence with CHPE ...... 35 3.6.3.2 Alternative R2 ...... 35 3.6.3.3 Alternative R3A ...... 36 3.6.3.4 Alternative R3B ...... 36 3.6.3.5 Alternative R4 ...... 37 3.6.3.6 Alternative R5 ...... 38 3.6.3.7 Alternative R6 ...... 39 3.6.3.8 Alternative R7 ...... 39 3.6.4 Land Alternatives Evaluated ...... 40 3.6.4.1 Alternative L1 ...... 40 3.6.4.2 Alternative L2 ...... 41 3.6.4.3 Alternative L3 ...... 41 3.7 Selection of Project Landfall Locations ...... 42 3.7.1 Criteria for Selection of Landfalls ...... 42 3.7.2 Northern Landfall...... 42 3.7.3 Southern Landfall ...... 44 3.7.4 Comparisons and Selection of Preferred Landfalls ...... 44 3.8 Comparison of Alternative Routes ...... 44 3.9 Alternative In-River Installation Techniques ...... 48 3.9.1 Hydraulic Jet Plow (Preferred Alternative) ...... 48 3.9.2 Horizontal Directional Drilling ...... 48 3.9.3 Mechanical Plow ...... 48 3.9.4 Mechanical Dredging ...... 49 3.10 Project Capacity ...... 49 3.11 References ...... 49 4.0 ENVIRONMENTAL CONDITIONS AND IMPACTS ...... 50 4.1 Introduction ...... 50 4.2 Geology, Topography and Soils ...... 52 4.2.1 Existing Conditions ...... 52 4.2.1.1 Geologic Setting ...... 52 4.2.1.2 Topography and Soils ...... 52 4.2.2 Environmental Impacts and Mitigation ...... 54 4.2.2.1 Potential Construction Impacts and Mitigation ...... 54 4.2.2.2 Potential Operational Impacts and Mitigation ...... 55 4.3 Wetlands and Waterbodies ...... 55 4.3.1 Existing Conditions ...... 56 4.3.1.1 Tidal Wetlands ...... 56
© 2013 ESS Group, Inc. k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc
TABLE OF CONTENTS (CONTINUED)
SECTION PAGE
4.3.1.2 Freshwater Wetlands ...... 57 4.3.1.3 Floodplains ...... 59 4.3.1.4 Streams and Rivers ...... 59 4.3.1.5 Groundwater ...... 60 4.3.2 Environmental Impacts and Mitigation ...... 61 4.3.2.1 Potential Construction Impacts and Mitigation ...... 61 4.3.2.2 Potential Operational Impacts and Mitigation ...... 66 4.4 Lower Hudson River Physical Characteristics ...... 66 4.4.1 Existing Conditions ...... 66 4.4.1.1 Tides and Currents ...... 66 4.4.1.2 Federal Channels and Dredging ...... 67 4.4.1.3 Technical Studies Completed ...... 68 4.4.1.4 Geophysical Characteristic Results ...... 70 4.4.1.5 Geotechnical Characteristic Results ...... 74 4.4.2 Environmental Impacts and Mitigation ...... 75 4.4.2.1 Potential Construction Impacts and Mitigation ...... 75 4.4.2.2 Potential Operational Impacts and Mitigation ...... 77 4.5 Lower Hudson River Sediment and Water Quality ...... 77 4.5.1 Existing Conditions ...... 78 4.5.1.1 Sediment Quality ...... 78 4.5.1.2 Sediment Transport ...... 81 4.5.1.3 Water Quality ...... 82 4.5.2 Environmental Impacts and Mitigation ...... 85 4.5.2.1 Potential Construction Impacts and Mitigation ...... 85 4.5.2.2 Potential Operational Impacts and Mitigation ...... 89 4.6 Finfish ...... 89 4.6.1 Existing Conditions ...... 89 4.6.1.1 Description of the Project Area ...... 89 4.6.1.2 Significant Coastal Fish and Wildlife Habitat ...... 90 4.6.1.3 Finfish Species Identified in the Project Area ...... 90 4.6.1.4 Essential Fish Habitat Species ...... 99 4.6.1.5 Commercial and Recreational Fisheries ...... 101 4.6.1.6 Protected Fish Species ...... 102 4.6.2 Environmental Impacts and Mitigation ...... 103 4.6.2.1 Potential Construction Impacts and Mitigation ...... 103 4.6.2.2 Potential Operational Impacts and Mitigation ...... 110 4.6.2.3 Summary of Potential Impacts to Finfish ...... 111 4.7 Benthos and Shellfish ...... 112 4.7.1 Existing Conditions ...... 112 4.7.1.1 Benthos ...... 112 4.7.1.2 Shellfish ...... 114 4.7.1.3 Technical Studies Completed ...... 114 4.7.2 Environmental Impacts and Mitigation ...... 117 4.7.2.1 Potential Construction Impacts and Mitigation ...... 117 4.7.2.2 Potential Operational Impacts and Mitigation ...... 123 4.8 Vegetation and Wildlife ...... 123 4.8.1 Existing Conditions ...... 124 4.8.1.1 Vegetation ...... 124 4.8.1.2 Wildlife ...... 127 4.8.1.3 Non-Indigenous and Invasive Species ...... 129 4.8.2 Environmental Impacts and Mitigation ...... 131
© 2013 ESS Group, Inc. k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc
TABLE OF CONTENTS (CONTINUED)
SECTION PAGE
4.8.2.1 Potential Construction Impacts and Mitigation ...... 131 4.8.2.2 Potential Operational Impacts and Mitigation ...... 133 4.9 Important Habitats and Threatened and Endangered Species ...... 134 4.9.1 Existing Conditions ...... 134 4.9.1.1 Important Habitats ...... 134 4.9.1.2 Threatened and Endangered Species ...... 144 4.9.2 Environmental Impacts and Mitigation ...... 154 4.9.2.1 Important Habitats ...... 154 4.9.2.2 Threatened and Endangered Species ...... 157 4.10 Land Use ...... 162 4.10.1 Existing Conditions ...... 162 4.10.1.1 Zoning ...... 164 4.10.1.2 Parks and Recreational Resources ...... 166 4.10.2 Environmental Impacts and Mitigation ...... 166 4.10.2.1 Potential Construction Impacts and Mitigation ...... 166 4.10.2.2 Potential Operational Impacts and Mitigation ...... 166 4.10.3 Consistency with NYS Coastal Zone Management Policies and LWRP ...... 166 4.10.4 Consistency with NYS and Local Land Use Policies and Plans ...... 168 4.11 Cultural Resources ...... 169 4.11.1 Existing Conditions ...... 169 4.11.1.1 Northern Land Portions of Project Area ...... 169 4.11.1.2 In-River Cable Route ...... 172 4.11.1.3 Southern Land Route ...... 173 4.11.2 Environmental Impacts and Mitigation ...... 175 4.11.2.1 Northern Converter Station Land and Linear Interconnection Route ...... 175 4.11.2.2 In-River Cable Route ...... 176 4.11.2.3 Southern Converter Station and Linear Interconnection Route ...... 176 4.12 Visual and Aesthetic Resources ...... 176 4.12.1 Existing Conditions ...... 177 4.12.1.1 Northern Study Area ...... 177 4.12.1.2 Southern Study Area ...... 178 4.12.1.3 Project Description ...... 178 4.12.1.4 Inventory of Aesthetic Resources ...... 179 4.12.1.5 Visibility Analysis ...... 183 4.12.2 Environmental Impacts and Mitigation ...... 184 4.12.2.1 Potential Visual Effects – Northern Converter Station ...... 184 4.12.2.2 Potential Visual Effects – Southern Converter Station ...... 185 4.12.2.3 Potential Visual Effects During Construction ...... 186 4.12.2.4 Potential Visual Effects During Operation ...... 186 4.13 Noise ...... 186 4.13.1 Existing Conditions ...... 187 4.13.1.1 Sound Level Concepts ...... 187 4.13.1.2 Baseline Sound Level Measurements ...... 189 4.13.1.3 Applicable Noise Regulations ...... 193 4.13.2 Environmental Impacts and Mitigation ...... 195 4.13.2.1 Potential Construction Impacts and Mitigation ...... 195 4.13.2.2 Potential Operational Impacts and Mitigation ...... 197 4.13.2.3 Operational Noise Level Evaluation ...... 198 4.14 Electric and Magnetic Fields ...... 201 4.14.1 Existing Conditions ...... 201 4.14.2 Environmental Impacts and Mitigation ...... 203
© 2013 ESS Group, Inc. k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc
TABLE OF CONTENTS (CONTINUED)
SECTION PAGE
4.14.2.1 Potential Construction Impacts and Mitigation ...... 203 4.14.2.2 Potential Operational Impacts and Mitigation ...... 203 4.15 Navigation ...... 206 4.15.1 Existing Conditions ...... 206 4.15.1.1 Current Vessel Traffic ...... 207 4.15.1.2 Federal Channels ...... 207 4.15.1.3 Regulated Navigation Area ...... 208 4.15.1.4 Charted Obstructions...... 208 4.15.1.5 Fixed Bridges ...... 208 4.15.1.6 Cable/Pipeline Crossings ...... 208 4.15.1.7 Anchorages ...... 209 4.15.1.8 Restricted Areas ...... 210 4.15.2 Potential Impacts and Mitigation ...... 210 4.15.2.1 Potential Construction Impacts and Mitigation ...... 210 4.15.2.2 Potential Operational Impacts and Mitigation ...... 213 4.16 Summary of Impacts ...... 214 4.17 Cumulative Impacts ...... 218 4.18 References ...... 219 Section 4.2 - Geology, Topography and Soils ...... 219 Section 4.3 - Wetlands and Waterbodiess ...... 219 Section 4.4 - Lower Hudson River Sediment and Water Quality ...... 220 Section 4.5 - Lower Hudson River Sediment and Water Quality ...... 220 Section 4.6 - Finfish ...... 221 Section 4.7 - Benthos and Shellfish ...... 226 Section 4.8 - Vegetation and Wildlife ...... 228 Section 4.9 - Important Habitats and Threatened and Endangered Species ...... 229 Section 4.10 - Land Use...... 232 Section 4.12 - Visual and Aesthetic Resources ...... 232 5.0 COMPLIANCE WITH SECTION 404(B)(1) GUIDELINES ...... 232 5.1 Introduction ...... 232 5.2 Summary of Alternatives Analysis ...... 233 5.2.1 Evaluation of Landfall Locations ...... 233 5.2.2 Evaluation of In-River Transmission Line Routes ...... 234 5.2.3 Evaluation of Cable Installation Methodologies ...... 234 5.3 Compliance with Guidelines ...... 234 5.3.1 Compliance with Guidelines ...... 235 5.3.2 Environmental Effects on Physical and Chemical Characteristics of Aquatic Ecosystem .. 236 5.3.3 Environmental Effects on Biological Characteristics of the Aquatic Ecosystem ...... 238 5.3.4 Environmental Effects on Special Aquatic Sites ...... 239 5.3.5 Potential Impacts on Human Use Characteristics ...... 240 5.3.6 Evaluation and Testing ...... 240 5.3.7 Actions to Minimize Adverse Effects ...... 241 5.4 Conclusion ...... 241 6.0 PUBLIC INTEREST REVIEW ...... 241 6.1 Electric System Benefits ...... 241 6.2 Other Public Benefits ...... 242
© 2013 ESS Group, Inc. k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc
TABLE OF CONTENTS (CONTINUED)
SECTION
TABLES
Table 2.1 Summary of Cable System Component Lengths Table 3-1 Alternatives Summary Table 3-2 In-River Route Alternatives Summary Table 3-3 Land Alternatives Summary Table 4.2-1 Soil Types along Overland Transmission Cable Route Table 4.3-1 Summary of Impacts to Wetlands and Waterbodies in the Project Area Table 4.5-1 Summary of Sediment Chemistry Concentrations Table 4.5-2 Summary of Water Body Classes Crossed by the In-River Cable Route Table 4.6-1 List of common and abundant fish species found within the lower tidal Hudson River (Troy to the Battery) from 1970-2003 (Daniels et al. 2005) Table 4.6-2 Life History Characteristics of Key Fish Species Found in the Hudson River Estuary Table 4.6-3 Summary of EFH Designations for the Project Area1 Table 4.6-4 Summary of Potential Impacts to Finfish Table 4.7-1 Taxa Collected during Site-specific Benthic Sampling Program, August 2012 (see Tables Section) Table 4.7-2 Summary of Key Statistics from Route-specific Survey Table 4.7-3 Summary of Construction Impacts to Benthic Macroinvertebrate Taxa* Table 4.7-4 Summary of Potential Impacts to Benthos and Shellfish Table 4.9-1 Description of Significant Coastal Fish and Wildlife Habitats Crossed by the In-River Cable Table 4.9-2 Summary of Listed Species potentially occurring in or near the Project Area* Table 4.9-3 Seasonality of Listed Sturgeon Species Life Stages that Occur in the Hudson River Estuary Table 4.10-1 List of Completed LWRPs and Harbor Management Plans in Municipalities Located along West Point Transmission Project Table 4.12-1 Three Mile Study Area Scenic Resources Table 4.13-1 Common Sound Levels/Sources and Subjective Human Responses Table 4.13-2 Average Ability to Perceive Changes in Noise Levels Table 4.13-3 Nearest Noise-Sensitive Receivers - Northern Site Table 4.13-4 Short-Term Ambient (LEQ) Community Noise Levels - Northern Site Table 4.13-5 Nearest Noise-Sensitive Receivers - Southern Site Table 4.13-6 Short-Term Ambient (LEQ) Community Noise Levels – Southern Site Table 4.13-7 EPA Noise Levels Identified to Protect Public Health and Welfare Table 4.13-8 Summary of Noise Control Evaluation Standards Considered Table 4.13-9 Projected Northern Site Construction Noise Levels—(LEQ) Table 4.13-10 Projected Southern Site Construction Noise Levels—(LEQ) Table 4.13-11 Projected Northern Site Operation Noise Levels—(LEQ) Table 4.13-12 Projected Southern Site Operation Noise Levels—(LEQ) Table 4.13-13 Day-Night (LDN) Noise Levels Table 4.13-14 Current Ambient Noise Levels versus Future Ambient Noise Levels (dBA) Table 4.13-15 Town of Athens Compliance Evaluation (dBA) Table 4.13-16 Town of Cortlandt Compliance Evaluation (dBA) Table 4.14-1 60-Hz EMF Guidelines Established by Health and Safety Organizations Table 4.14-2 State EMF Standards and Guidelines for Transmission Lines Table 4.14-3 Major axis AC magnetic field levels (mG) 1 meter above ground for the Land Based AC circuits
© 2013 ESS Group, Inc. k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc
TABLE OF CONTENTS (CONTINUED)
SECTION
Table 4.14-4 DC magnetic field levels (mG) for the river-based portion of the DC lines Table 4.14-5 DC magnetic field levels (mG) 1 meter above ground for the Land Based DC lines Table 4.16-1 Summary of Potential Environmental Impacts
FIGURES
Figure 2-1 Project Site Locus Figure 2-2 Northern Land Cable Route Plan Figure 2-3 In-River Cable Route Figure 2-4 Southern Land Cable Route Plan Figure 2-5 In-River Cable Coexisting with CHPE Cable Figure 2-6 HVDC In-River Cable Cross Section Figure 2-7 HVDC Land Cable Cross Section Figure 2-8 AC Land Cable Cross Section Figure 2-9 Trans Bay Cable Project, VSC-HVDC Converter Station Figure 2-10 General Arrangement Diagram Figure 2-11A Typical DC Splice Vault Figure 2-11B Typical 345kV Splice Vault Figure 2-12 Typical Landfall Transition Vault Figure 2-13 Northern Landfall Figure 2-14 Temporary Cofferdam Detail Figure 2-15 Southern Landfall Figure 2-16 Typical Detail Hydroplow Cable Burial Machine Figure 2-17 Cable Lay Barge Atalanti Figure 3-1 Northern Converter Station Alternatives Figure 3-2 Alternative R1 Figure 3-3 Alternative R1A Figure 3-4 Alternative R1B Figure 3-5 Alternative R2 Figure 3-6 Alternative R3A Figure 3-7 Alternative R3B Figure 3-8 Alternative R4 Figure 3-9 Alternative R5 Figure 3-10 Alternative R6 Figure 3-11 Alternative R7 Figure 3-12 Alternative L1 Figure 3-13 Alternative L2 Figure 3-14 Alternative L3 Figure 4.3-1 Tidal Wetlands Along In-River Cable Route Figure 4.3-2 Mapped Hydric Soils within the Project Area Figure 4.3-3 Wetlands and Streams – Southern Land Cable Route and Southern Converter Station Figure 4.3-4 Wetlands and Streams – Northern Land Cable Route and Northern Converter Station Figure 4.4-1 Sediment Type – Vibracore Locations Figure 4.5-1 TSS Sampling Locations Figure 4.7-1 Biological Sampling Locations Figure 4.8-1 Submerged Aquatic Vegetation Figure 4.9-1 Significant Ecological Resources
© 2013 ESS Group, Inc. k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc
TABLE OF CONTENTS (CONTINUED)
SECTION
Figure 4.10-1 Land Use, Parks, and Recreational Resources – Northern Land Cable Route and Northern Converter Station Figure 4.10-2 Land Use, Parks, and Recreational Resources – Southern Land Cable Route and Southern Converter Station Figure 4.10-3 Zoning - Northern Land Cable Route and Northern Converter Station Figure 4.10-4 Zoning - Southern Land Cable Route and Southern Converter Station Figure 4.12-1 Viewshed Analysis and Visually Sensitive Resources Figure 4.12-2 Visual Simulations Figure 4.12-3 Converter Station Layout Figure 4.14-1 Typical Trench Detail – 345kV AC Cable (Dual Circuit) Figure 4.14-2 Typical Trench Detail – HVDC Land Cable Figure 4.14-3 Typical Trench Detail – HVDC In-River Cable
© 2013 ESS Group, Inc. k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc
1.0 INTRODUCTION West Point Partners, LLC (“WPP”) proposes to construct and operate the West Point Transmission Project (“the Project”), an approximately 80-mile-long high voltage electric transmission facility that will connect the existing National Grid Leeds Substation (Leeds Substation) in the Town of Athens, Greene County, NY, and the existing Consolidated Edison Company of New York, Inc. (Con Edison), Buchanan North Substation (Buchanan Substation) located adjacent to the Indian Point Energy Center in the Village of Buchanan, Town of Cortlandt, Westchester County, NY. For approximately 77 miles of its length, the Project will be buried under the bed of the Hudson River (the river). The Project will be capable of providing up to 1,000 megawatts (MW) of firm transmission capacity. At a 100% capacity factor, the Project would deliver 8.76 million MW hours (MWh) of energy per year from New York Independent System Operator’s (NYISO) Zone G to NYISO’s Zone H. In addition to providing firm transmission, because the Project will be a controllable direct current (DC) circuit, it can provide other services, such as voltage support, load following, and energy transfer scheduling to enhance overall system efficiency. The Project will feature a high voltage (320 kilovolt [kV]) DC cable buried for most of its route in the bed of the Hudson River and will use Voltage Source Conversion-High Voltage Direct Current (VSC-HVDC) technology for controllability, voltage stability, and efficiency. In addition to the 320 kV HVDC In-River Cable System, the Project will include land-based HVDC cables connecting the In-River Cable at each terminus to a VSC-HVDC converter station; VSC-HVDC converter stations at each end of the HVDC cable system, close to the points of interconnection at the Leeds and Buchanan Substations; and buried 345 kV AC lines connecting the converter stations to buses in the Leeds and Buchanan Substations. Drawings and detailed descriptions of the Project are provided in Section 2.0 of this Project Narrative. Project plans are provided in Attachment 2 of the Application. Studies of the environmental impact of the Project are presented in Section 4.0 of the Project Narrative and its associated appendices (Attachment 6). In general, these studies show that by embedding the Project cables in the riverbed and underground and by locating the converter stations near existing substations, the Project’s environmental impacts will be minimal and primarily limited to the construction phase. Section 4.0 also describes how the environmental impacts associated with construction of the Project will be minimized by the type of construction methods chosen, by limiting work to time-of-year construction windows, and by building upon the experience that WPP’s personnel and contractors have gained installing similar electric transmission facilities. 1.1 Purpose and Need In 2012, the State of New York launched its “Energy Highway” initiative, stating multiple goals that included strengthening the transmission system between upstate and downstate areas, encouraging the development of renewable energy resources, promoting energy-related economic development and employment, and providing for alternative sources of energy supply in the event of the closure of the Indian Point Energy Center. In response to the Energy Highway goals, the West Point Project will meet, in part or in whole, the following needs: a. Provide a transmission path capable of delivering 1,000 MW of firm capacity from upstate to southeastern New York; b. Provide a means for replacing approximately 50% of the output of Indian Point Units 2 and 3; c. Enhance the alternating current (AC) transmission system by alleviating an existing constraint on the AC system from Leeds Substation south;
© 2013 ESS Group, Inc. k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013 d. Enable generators, including wind, other renewable resources, and repowered plants located north and west of Leeds to deliver an additional 1,000 MW of power to loads in southeastern New York; e. Decrease New York State’s reliance on relatively higher cost power sources in favor of relatively lower cost power sources, thereby reducing, on a net basis, statewide production costs; f. Reduce the use of relatively higher emitting sources of air emissions in favor of relatively lower emitting sources, resulting in a net reduction statewide in air emissions and greenhouse gases; g. Provide the benefits of a controllable HVDC circuit, including voltage support, outage recovery capability, load following capability, and power transfer scheduling capability; and h. Increase the overall reliability and security of the New York State Transmission System in the Hudson Valley by installing a brand new 1,000 MW circuit buried underground and in the bed of the Hudson River in contrast to an overhead circuit in existing utility corridors. A comprehensive study, “An Assessment of the Impacts of the West Point DC Transmission Project on the New York State Electrical System,” was conducted by ESAI Power LLC and is included in Attachment 6, Appendix 11 of the Application. The study cites the Project’s beneficial impacts in terms of relieving system constraints, reducing air emissions, and producing cost savings, noted above Additional information regarding the public needs addressed by the Project is included in Section 6.0, “Public Interest Review.” An Application for a Certificate of Environmental Compatibility and Public Need under Article VII of the New York State Public Service Law was filed with the New York State Public Service Commission (NYSPSC) on June 28, 2013 (Case No. 13-T-0292). As part of the Article VII filing, WPP has requested that the NYSPSC issue a 401 Water Quality Certification. The data and analyses presented in this U.S. Army Corps of Engineers (USACE) permit application represent the culmination of field investigations, laboratory analyses, modeling, and other studies conducted in response to regulatory requirements and numerous consultations with federal, state, and local regulatory officials regarding project design, and review of potential land use and environmental impacts of the Project. The following sections provide details on the Project and the activities that are subject to USACE review. 2.0 DETAILED PROJECT DESCRIPTION 2.1 Description and Location of Proposed West Point Project The Project is an HVDC 1,000 MW electric transmission facility connecting the existing Leeds Substation in the Town of Athens, Greene County, NY, and the existing Con Edison Buchanan Substation in the Village of Buchanan, Westchester County, NY. The Project is comprised of the following elements: a. Approximately 77.3 miles of 320 kV HVDC transmission cable together with associated communications fiber to be buried in the bed of the Hudson River (In-River Cable). b. Two VSC-HVDC Converter Stations, one at each end of the HVDC cable, which are required to link the HVDC Project to the 345 kV AC grid. The Northern and Southern Converter Stations will be located close to the Leeds and Buchanan Substation Interconnection Points respectively. c. Two short lengths of high voltage (345 kV) AC land cable connecting the VSC-HVDC Converter Stations to the Leeds and Buchanan Substation Interconnection Points (AC Land Cables), which will be installed in underground conduits for the Northern Interconnection, and in buried, enclosed duct banks for the southern interconnection.
© 2013 ESS Group, Inc. Page 2 k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013 d. Two short lengths of 320 kV HVDC land transmission cable with associated communications fiber linking the In-River Cable to the Converter Stations (Land Transmission Cables). These Land Transmission Cables will be installed in conduits buried underground. e. Two underground Transition Vaults where the In-River Cable will be spliced to the Land Transmission Cables. Table 2.1 provides a summary of the lengths of each cable component of the Project. Details of the Project Route are provided in the Project Plan Set (Attachment 2). For most of its length, the Project will be buried in the bed of the Hudson River in submerged lands owned by the State of New York. At either end of the In-River Cable Route, the Land Cables will be located primarily in existing public rights-of-way (ROWs) and, to a lesser extent, in ROWs secured from private land owners. The Converter Stations will be located on private property proximate to the existing Leeds and Buchanan Substations. The planned location of the Project is depicted on maps provided in Figures 2-1 through 2-4 as well as in the Project Plan Set provided in Attachment 2. Additional details regarding the location of each Project component, presented from north to south, are provided below. Construction details for underground components of the Project are provided in Section 2.5. Table 2.1: Summary of Cable System Component Lengths Cable System Route Centerline Installation Approximate Length Approximate Length Cable Type Method (LF) (Miles) AC Land Cable (Athens) HDD* 2,545 0.5 DC Land Cable (Athens) Direct Bury 16,370 3.1 HVDC In-River Cable HDD (Northern End) 500 0.1 HVDC In-River Cable Jet Plow Embedment 408,075 77.3 HVDC In-River Cable HDD (Southern End) 850 0.2 DC Land Cable (Cortlandt) Direct Bury 2,560 0.5 AC Land Cable (Cortlandt) Direct Bury 5,555 1.1 Project Total 436,455 82.8 Total Length between Interconnection Points 82.8 In-River Cable Length (77.3 miles of Jet Plow Embedment) 77.6 Land Cable Length (HVDC) 3.6 Land Cable Length (AC) 1.6 *HDD - Horizontal Directional Drilling 2.1.1 Northern Interconnection The Northern Interconnection Point will be the Leeds Substation in the Town of Athens, Greene County, NY. The Project will interconnect via an available bay in the substation. 2.1.2 Northern AC Cable Route The Northern AC Cable will exit from the east side of the Leeds Substation, head east for approximately 600 feet, and then north for 0.4 miles to enter the west side of the Northern Converter Station.
© 2013 ESS Group, Inc. Page 3 k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013
2.1.3 Northern Converter Station The Northern Converter Station will be situated on a 3.8-acre portion of a 44-acre private parcel located approximately 950 feet west of Flats Road Extension and approximately 3,100 feet north of Leeds Athens Road in the Town of Athens. 2.1.4 Northern Land Cable Route The Northern Land Cable system will exit the east side of the Northern Converter Station as a direct buried cable system and cross the private parcel to exit at Flats Road Extension. The Land Cable will then proceed south within the Flats Road Extension ROW for approximately 0.55 miles to the Leeds Athens Road. At the Leeds Athens Road the Land Cable will turn east for approximately 1.13 miles until it reaches 2nd Street in the Village of Athens. The Land Cable will then turn south briefly onto 2nd Street, and then will proceed north onto North Vernon Street for approximately 0.67 miles. The Land Cable then will continue southeast on Union Street for 0.20 miles where it meets Washington Street and will continue north for 0.20 miles before turning east onto private property, entering an underground Transition Vault where it will be spliced with the In-River Cable. 2.1.5 In-River Cable Route The In-River Cable Route runs from the Transition Vault located in the vicinity of the Northern Landfall near River Mile (RM) 118 on the west side of the Hudson River to the Transition Vault located in the vicinity of the Southern Landfall near RM 42 on the east side of the Hudson River. The total length of the In-River Cable between these two locations will be approximately 77.6 miles. Of this total, approximately 77.3 miles of the In-River Cable will be embedded into the river bottom by hydraulic jetting. As it proceeds south, the In-River Cable Route passes through or adjacent to a variety of natural and manmade riverbed conditions and resource areas. These include: shallows, deep channels, rocky outcrops, and islands; bridges, outfalls/intakes, and cable/pipeline crossings; navigation features including Federal Channels; and New York State Department of State (NYSDOS)-designated Significant Coastal Fish and Wildlife Habitats (SCFWHs). In developing the In-River Cable Route, WPP has avoided or limited placement of the In-River Cable Route within the limits of these resources to the extent practicable while also avoiding conditions unsuitable for jet plow embedment of the cable, such as extreme slopes, rocky and/or stiff sediment, and physical obstructions. As a result, the In-River Cable Route crosses the river multiple times over its 76+ mile length to locate the cable in conditions suitable for jet plow embedment and/or to avoid or limit placement within various River resource areas. The In-River Cable Route is described below. Northern Landfall The Project’s Northern Landfall will be located at a Peckham Industries liquid calcium chloride storage terminal facility, which is located off of North Washington Street (Route 385) in the Village of Athens. The facility is bordered to the east by the Hudson River. The facility includes an existing bulkhead along the river, a gravel parking area, and liquid calcium chloride storage tanks. From the Transition Vault within the Peckham Industries facility, the In-River Cable will enter a series of conduit-lined Horizontal Directional Drilling (HDD) boreholes for a distance of approximately 500 feet to a Temporary Cofferdam in the Hudson River at approximately RM 118. From the Temporary Cofferdam, the In-River Cable will be installed within the riverbed of the Hudson River via jet plow embedment.
© 2013 ESS Group, Inc. Page 4 k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013
RM 118 to RM 106 The Hudson River Federal Channel is the dominant deepwater feature in the stretch of the river between RM 118 and RM 106. Shallow water conditions on alternating sides of the Federal Channel prevent routing of the cable entirely along one side or the other and in some areas, shallow water conditions on both sides preclude any routing outside of the Federal Channel. However, by crossing the river several times in this section, the In-River Cable Route maximizes the use of conditions outside of the Federal Channel that are suitable for in-river installation and reduces the length of the In-River Cable that is routed within the limits of the Federal Channel. The result is that only approximately 2.7 miles of the approximately 9.1 miles of In-River Cable Route in this section is located within the Federal Channel, and the portions routed in the Federal Channel are only in areas where there is no other area outside of the Federal Channel with water depths, slope conditions, or bottom conditions, conducive to installation of the In-River Cable. Additional details are provided below. The In-River Cable Route exits the Temporary Cofferdam on the west side of the river at RM 118. It enters the Federal Channel in the vicinity of RM 116 and crosses diagonally to emerge on the east side, where it runs along, but outside of, the Federal Channel until just south of RM 115. At that point, the In-River Cable Route crosses diagonally back across the Federal Channel to run along, but outside of, the west side of the Federal Channel for approximately 0.7 miles. Shallow water, bottom slope conditions, and the presence of mapped submerged aquatic vegetation beds prevent the installation of the cable entirely on either side of the Federal Channel in this stretch of the river, but by crossing the Federal Channel in this manner instead of routing the cable entirely within the Federal Channel, approximately 1.8 miles of route was removed from the Federal Channel limits. Approximately 1,000 feet north of the Rip Van Winkle Bridge (about RM 113.5), the In-River Cable Route re-enters the Federal Channel and follows the centerline, avoiding shallows and aquatic vegetation on both sides, to RM 112, where it exits the Federal Channel on the west side. In the 1.9- mile stretch of the In-River Cable Route that is located within the middle of the Federal Channel, river bottom elevations range between -45 feet NAVD88 and -60 feet NAVD88, which are approximately 11 to 26 feet below the Federal Channel’s authorized depth of -32 feet MLW (-33.58 feet NAVD88). From RM 112, the In-River Cable Route runs parallel to and west of the Federal Channel until a point just north of RM 110. At that point, it crosses the Federal Channel at a nearly perpendicular angle and then turns to the south to run parallel to and east of the Federal Channel limits until RM 108 where the distance between the cable route and the Federal Channel increases to as much as approximately 1,500 feet. The In-River Cable Route crosses the Catskill Deepwater SCFWH, which spans the entire deepwater water area of the Hudson River between RM 114 and RM 110. RM 106 to RM 92 From RM 106 to RM 102, the In-River Cable Route continues south within a shallow channel that runs along the east side of the river. By routing the In-River Cable within this shallow channel and to the east, WPP is able to avoid placement of the cable within the Malden-on-Hudson Reach of the Hudson River Federal Channel and main navigational fairway, both of which are located along the west side of the river. WPP elected this route to eliminate potential conflict with commercial navigation interests and strike a balance between competing interests for river resources. Routing the In-River Cable through the shallow channel also avoids slope conditions on the west side of the river that are unfavorable for cable installation and reduces the length of cable by approximately 0.4 miles between RM 106 and RM 102.
© 2013 ESS Group, Inc. Page 5 k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013
From RM 107 to 103, the In-River Cable Route passes through the Germantown-Clermont Flats SCFWH area and two submerged land grants, one at about RM 104 (Edward L. Clarkson, May 19, 1899) and one at about RM 103 (John Henry Livingston, August 16, 1898). South of RM 102 and the mouth of Esopus Creek, the In-River Cable Route shifts to the west side of the river for about one mile. WPP initially investigated continuing along the east side of the river in this area, but marine surveys conducted for the Project identified bottom conditions that appeared to be rocky or comprised of harder substrate. Marine surveys to the west of this area indicated more favorable bottom conditions for jet plow embedment. Between RM 102 and RM 101, the route crosses through the Esopus Estuary SCFWH, which extends across the entire width of the Hudson River. Just north of RM 101, the In-River Cable Route turns slightly southeast and then proceeds south near the center of the river. South of RM 101, the In-River Cable Route continues south near the center of the river to avoid the Tivoli Reach of the Hudson River Federal Channel to the east. At RM 100, the In-River Cable Route follows the main navigational fairway along the east side of the river to avoid the one-mile-long shallow shoal known as Saddle Bags to the west. At RM 99, the In-River Cable Route shifts further east out of the main navigational fairway, to the east of Hogs Back shoal, and continues along the east side of the river until RM 92. This easterly shift avoids potential conflicts with the Barrytown Reach and the Kingston Point Reach of the Hudson River Federal Channel, and the Kingston Point water intake, all of which are located on the west side of the river south of RM 99. The In-River Cable Route runs parallel to, but does not enter, the North and South Trivoli Bays SCFWH between approximately RM 100.5 and RM 97.5. Just north of RM 95, the route crosses under the Kingston-Rhinecliff Bridge. RM 92 to RM 81 At RM 92, the In-River Cable Route crosses a charted cable area occupied by several cables or pipelines, then continues south along the east side of the river. Off of Port Ewen and Big Rock Point (on the west side of the river between RM 89 and RM 90), there are two uncharted anchorage grounds used by the River Pilots as they bring vessels up and down the river. During WPP’s discussions with the Pilots about the Project, they indicated that vessels anchor approximately 0.25 miles off the shore of Big Rock Point and between buoys 71 and 73. To avoid potential conflicts with ship anchors, the In-River Cable Route is located on the east side of the river along the edge of the navigational fairway, which is also the easterly limit of the uncharted anchorage areas. South of the uncharted anchorages, the In-River Cable Route continues along the eastern edge of the navigational fairway until about RM 86.5, east of Esopus Meadows Point, where it turns west to cross the navigational fairway at a nearly perpendicular angle, then turns south to run along the west side of the river to RM 85. At RM 85, the In-River Cable Route turns east and crosses perpendicular to the navigational fairway, then runs south along the east side of the river. In this stretch, WPP initially investigated an In-River Cable Route along the west side of the river to avoid charted Anchorage 19-A at RM 82. However, WPP's marine survey identified rocky bottom material with rock outcrops along the west side of the river in this stretch, while on the east side of the river more favorable bottom conditions were found. At RM 84, the In-River Cable Route passes to the east of Esopus Island and then runs along and outside of the easterly boundary of Anchorage 19-A. Once past the southern end of Anchorage 19-A and Buoy 62D, the In-River Cable Route crosses back to the west side of the river. Between RM 91 and RM 81, the route travels along the edges of and crosses the Kingston-Poughkeepsie Deepwater SCFWH, which extends across the entire width of the Hudson River.
© 2013 ESS Group, Inc. Page 6 k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013
RM 81 to RM 66 At RM 81, the In-River Cable Route turns south and runs along the west side of the river for approximately one mile. The route then crosses to the east side in a gradual transition between RM 80 and RM 79. The cable will be routed in the center of the river as it makes this transition through a deep depression in the river bottom so as to avoid the very steep slopes on the sides of this depression where installation using a towed cable plow would not be possible. Near the mouth of Maritje Kill (about RM 78.7), the In-River Cable Route turns south and runs along the east side of the river until RM 77. At this point, the In-River Cable Route moves back towards the center of the river to avoid two City of Poughkeepsie water intakes to the east. Once in the center, the In-River Cable Route crosses several cable/pipelines that cross the river at Poughkeepsie and travels under the Walkway Over the Hudson and the Mid-Hudson Suspension Bridge. At RM 75 (about 0.25 miles south of the Mid-Hudson Suspension Bridge), the In-River Cable Route moves back to the east side of the riverand continues along the east side to RM 68. At RM 68, the In-River Cable Route shifts to the west to avoid a rocky bottom area identified on navigation charts and by WPP marine surveys on the east side of the river between New Hamburg and Diamond Reef (about RM 67). Once around Diamond Reef, the route shifts back to the east side of the river in the vicinity of Wappinger Creek to avoid the main navigational fairway in this area. Between RM 81 and RM 66, the In-River Route runs through the Kingston-Poughkeepsie Deepwater Habitat SCFWH, which extends across almost the entire width of the river in this stretch. The route passes to the west of the Wappinger Creek SCFWH between RM 67 and RM 66. RM 66 to RM 42 From RM 66, the In-River Cable Route continues along the east side of the river to avoid the center of the main navigational fairway. The route crosses a charted cable and pipeline area containing several cable and pipeline crossings, some of which are located to the south of the charted cable and pipeline area, between RM 66 and RM 65. One of these crossings, the Delaware Aqueduct Roundout-West Branch Tunnel, is over 1,000 feet below the river’s surface. Between RM 64 and RM 63, the In-River Cable Route shifts towards the center of the river to avoid a possible rock outcrop identified during WPP marine surveys that is located between Red Buoy 52 and the east shore of the river. The route deviation around this outcrop is approximately 3,000 feet long. Once back on the east side, the In-River Cable Route continues south. At RM 57.5 the route shifts towards the center of the river for a short distance to avoid a fixed aid to navigation marking Pollepel Island, then continues south along the east side of the river again until Constitution Island (RM 53.5). The river bottom between Constitution Island and West Point contains a deep depression with rock outcrops and sheer walls. WPP marine surveys identified a more appropriate substrate (silty clay with some rock outcrops).in the center of the river in this area. The In-River Cable Route follows the bottom slope of the river down into this hole, runs through the center of relatively flat bottom of the hole, and emerges on the south side of the hole to the east of Duck Island (RM 53). Near RM 56, the In-River Cable Route crosses the Catskill Aqueduct Hudson River Siphon, which is over 1,000 feet below the river’s surface. From Duck Island, the In-River Cable Route proceeds south along the east side of the river to RM 49 where it crosses almost perpendicularly to the west, then runs southerly along the west side of the river to the Bear Mountain Bridge. After passing under the Bear Mountain Bridge (RM 47), the In-River Cable Route moves towards the center of the river to avoid a charted shallow area to the southwest of Green Buoy 31 that is likely a rock outcrop (based
© 2013 ESS Group, Inc. Page 7 k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013
on the dramatic change in bottom depth). The In-River Cable Route then proceeds southeast along the west side of the river to Jones Point. At Jones Point (about RM 43.7), the In-River Cable Route turns to the southwest, continuing along the west side of the river to about RM 42.5. At this point, the In-River Cable Route turns south across the river towards the Southern Landfall at Indian Point. After making this turn, the In-River Cable Route crosses a series of pipelines, and then makes an angled approach to east to Southern Landfall. Between RM 60 and RM 42, the In-River Cable Route runs through the Hudson Highlands SCFWH, which extends across the almost the entire width of the river in this stretch. The routes passes, but does not enter, the Moodna Creek (RM 57), Constitution Marsh (RM 54), and Iona Island Marsh (RM 46) SCFWHs. Southern Landfall The In-River Cable Route will exit the Hudson River at the Southern Landfall in the Town of Cortlandt, NY onto property now owned by Con Edison. The Town of Cortlandt and Village of Buchanan occupy a peninsula-like landform that is bordered by the Hudson River to the west and south, Lents Cove to the north and Lake Meahagh to the east. The southern portion of this peninsula, the location of the Project Landfall, is a hamlet community known as Verplanck, which supports residences, retail commercial and institutional uses. The northern portion of the peninsula, the Village of Buchanan, has a heavy industrial component with residential pockets to the east and south. In the vicinity of the Southern Landfall, a Transition Vault will be located underground within an existing unused paved area on the Con Edison property near the western terminus of 9th Street. The In-River Cable will be spliced to the Southern Land Cable in the Transition Vault. 2.1.6 Southern Land Route The Southern Land Cable will run southwest within the Con Edison property for approximately 240 feet before reaching 9th Street, from which the cable will proceed southeast for approximately 950 feet, then turn north on Highland Avenue for 400 feet to re-enter the Con Edison property. The cable will then proceed northerly along an existing, unused access road for approximately 650 feet before turning east to enter the Southern Converter Station. 2.1.7 Southern Converter Station The Southern Converter Station will occupy approximately 3.8 acres of a 105-acre underutilized parcel owned by Con Edison in the Town of Cortlandt, NY. The property is bisected by two high voltage overhead transmission lines that enter the site from the west side of the Hudson River and then turn northeast toward the Buchanan Substation. The proposed Converter Station site property is bordered on the north by the Lafarge Gypsum Manufacturing Facility and Entergy’s Indian Point Nuclear Power Station, which are both in the Village of Buchanan. The Southern Converter Station will be entirely within the Town of Cortlandt, outside of the Village of Buchanan. 2.1.8 Southern AC Cable The Southern AC Cable will exit from the east side of the Southern Converter Station and proceed south for approximately 890 feet to 11th Street. The cable will then follow 11th Street for approximately 460 feet to Broadway, then follow Broadway for approximately 0.79 miles before turning east into the Buchanan Substation. The Southern AC Cable will be located in both the Town of Cortlandt and the Village of Buchanan, NY.
© 2013 ESS Group, Inc. Page 8 k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013
2.1.9 Southern Interconnection The Southern Interconnection for the Project will be the Buchanan Substation in the Village of Buchanan, Westchester County, NY. The Project will interconnect via an available bay in the substation. 2.2 In-River Cable Coexistence with Champlain-Hudson Power Express The proposed In-River Cable Route described above is located in the same stretch of the Hudson River as the Champlain-Hudson Power Express (CHPE) Project, which received its Article VII Certificate from the NYSPSC on April 18, 2013. It is WPP’s understanding that, as of July 26, 2013, the CHPE Project is still undergoing review at the federal level (USACE New York District and U.S. Department of Energy). Since the CHPE Project has not received its federal approvals or its work permit from the New York State Office of General Services, there is uncertainty as to when, or if, the CHPE Project cable would get installed. As a result, WPP is presenting two In-River Cable Route alternatives that would coexist with the CHPE Project cable route (based on the 2012 route certified under Article VII on April 18, 2013) in the event that the CHPE Project receives its remaining permits and is installed in accordance with the Article VII Certificate, with the difference in the two being based on installation sequence. To coexist within the Hudson River, the routes of both the West Point Project In-River Cable and the CHPE Project cable would need to be adjusted slightly to allow installation and operation of both cables. Figure 2-5 shows two different route alternates for the In-River Cable based on this scenario. The magenta color route (solid line) is based on the West Point Project In-River Cable being installed prior to the CHPE Project cable (designated Alternative 1A). The red color route (dashed line) is based on the CHPE Project cable being installed prior to the West Point Project In-River Cable (designated Alternative 1B). The Northern and Southern Landfalls would not change from those described in Section 2.1. In each scenario, WPP would commit to working with CHPE to develop mutually acceptable crossing agreements to allow the two cables to be installed with cable crossing techniques that allow the two cables to coexist. Such crossing agreements are typically required by the USACE New York District as a condition of its permits. These crossings may require the use of additional concrete mattresses or other cable protection means over the second cable that is installed at a crossing location (be it WPP’s or CHPE’s cable). The details of the selected crossing methods would be described in each Project’s detailed construction plans that will be included in the Environmental Management and Construction Plan (EM&CP) submitted to the NYPSC for its approval. 2.2.1 West Point Project In-River Cable Installed Prior to CHPE Project Cable (Alternative 1A) Installation of the West Point Project In-River Cable before the CHPE Project cable is installed would require adjustments to the In-River Cable Route described in Section 2.1. These adjustments are required to allow the In-River Cable to be installed at minimum distance of 250 feet from the CHPE Project Route included in the April 2013 Article VII Certificate to reduce the potential for encountering the cable during installation and to allow for cable maintenance should that ever become necessary. These adjustments result in the route designated as Alternative 1A. RM 118 to RM 106 Alternative 1A matches the In-River Cable Route described in Section 2.1 since the CHPE Cable enters the Hudson River at RM 107 (Cementon on the river's western shore) and the In-River Cable Route is located in the eastern side of the river in this segment. RM 106 to RM 92 Alternative 1A matches the In-River Cable Route until RM 102.5. At this point, Alternative 1A angles to the east to allow the CHPE Cable Route to make two crossings of Alternative 1A in the vicinity of
© 2013 ESS Group, Inc. Page 9 k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013
RM 102. Once south of these crossings, Alternative 1A runs parallel to the CHPE Cable Route at a distance of approximately 250 feet, and along the path of the proposed In-River Cable Route, from RM 101 to RM 99. Just south of RM 99, Alternative 1A is located slightly east of the In-River Cable Route, to maintain separation of at least 250 feet from the CHPE Cable Route. Alternative 1A then follows the path of the In-River Cable Route to RM 92. RM 92 to RM 81 Between RM 92 and RM 91, Alternative 1A maintains a nearly straight alignment to allow the CHPE Cable Route to make two crossings of Alternative 1A. From RM 91, Alternative 1A follows the In- River Cable Route to RM 87. At this point, Alternative 1A stays on the east side of the river to maintain separation from the CHPE Cable Route. Alternative 1A rejoins the In-River Cable Route just south of RM 85 and follows it to about RM 81.5. At this point, Alternative 1A runs south along the east side of the river to maintain separation from the CHPE Cable Route. RM 81 to RM 66 Alternative 1A rejoins the In-River Cable Route at RM 80, and follows it to about RM 78.5. At this point, Alternative 1A shifts to the west to maintain at least 250 feet separation from the CHPE Cable Route. Alternative 1A rejoins the In-River Cable Route at RM 77, and generally follows it until RM 72, where it again shifts west to maintain separation from the CHPE Cable Route. The CHPE Cable Route would cross Alternative 1A at RM 74 and again just south of RM 73. Near RM 71, Alternative 1A would shift to the middle of the river to go around a rocky area marked by red-green buoy "A". Between RM 70 and RM 66, Alternative 1A generally follows the In-River Cable Route except for slight deviations between RM 69 and RM 68 to maintain separation from the CHPE Cable Route. The CHPE Cable Route would cross Alternative 1A just south of RM 67. RM 66 to RM 42 Alternative 1A follows the In-River Cable Route to RM 64, where it shifts farther towards the center of the river to maintain separation from the CHPE Cable Route. The CHPE Cable Route would cross Alternative 1A twice between RM 64 and RM 63. Alternative 1A would then follow the In-River Cable Route to RM 53. The CHPE Cable Route would cross Alternative 1A six times (near RM 57.5, RM 56, RM 54.5, RM 53.5, RM 53 and RM 52.5) in the stretch of the river between Pollepel Island and West Point. From RM 52, Alternative 1A follows the In-River Cable Route all the way to the Southern Landfall. 2.2.2 CHPE Project Cable Installed Prior to West Point Project In-River Cable (Alternative 1B) Installation of the West Point Project In-River Cable after the CHPE Project Cable has already been installed in the Hudson River would require adjusting the In-River Cable Route to allow the crossings to be performed. WPP’s installer has indicated that crossings of the CHPE Cable should be made at an angle as close to perpendicular as possible. WPP has developed a route that meets the installer’s requirement for the crossings of the CHPE Project except at one location near West Point where a more angled crossing is required due to river hydrography and the presence of steep rocky slopes on the river bottom. These adjustments are required to allow the In-River Cable to be installed at minimum distance of 250 feet from the CHPE Project Route included in the April 2013 Article VII Certificate to reduce the potential for encountering the cable during installation and to allow for cable maintenance should that ever become necessary. These adjustments result in the route designated as Alternative 1B.
© 2013 ESS Group, Inc. Page 10 k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013
RM 118 to RM 106 Alternative 1B matches the In-River Cable Route described in Section 2.1 since the CHPE Cable enters the Hudson River at RM 107 (Cementon on the river's western shore) and the In-River Cable Route is located in the eastern side of the river in this segment. RM 106 to RM 92 Alternative 1B matches the In-River Cable Route until RM 102.5. At this point, Alternative 1B angles to the west towards Esopus Creek to make two crossings of the CHPE Cable in the vicinity of RM 102. Once south of these crossings, Alternative 1B runs parallel to the CHPE Cable Route at a distance of approximately 250 feet, and along the path of the In-River Cable Route, from RM 101 to RM 99. Just south of RM 99, Alternative 1B is located slightly east of the In-River Cable Route, to maintain separation of at least 250 feet from the CHPE Cable Route. Alternative 1A then follows the path of the In-River Cable Route to RM 92. RM 92 to RM 81 Between RM 92 and RM 91, Alternative 1B angles to make two perpendicular crossings of the CHPE Cable Route. From RM 91, Alternative 1B follows the In-River Cable Route to RM 87. At this point, Alternative 1B stays on the east side of the river to maintain separation from the CHPE Cable Route. Alternative 1B rejoins the In-River Cable Route just south of RM 85 and follows it to about RM 81.5. At this point, Alternative 1B runs south along the east side of the river to maintain separation from the CHPE Cable Route. RM 81 to RM 66 Alternative 1B rejoins the In-River Cable Route at RM 80, and follows it to about RM 78.5. At this point, Alternative 1B shifts to the west to maintain separation from the CHPE Cable Route. Alternative 1B rejoins the In-River Cable Route at RM 77, and generally follows it until RM 72, where it again shifts west to maintain separation from the CHPE Cable Route. The CHPE Cable Route would cross Alternative 1B at RM 74 and again just south of RM 73. Near RM 71, Alternative 1B would shift to the middle of the river to go around rocky area marked by red-green buoy "A". Between RM 70 and RM 66, Alternative 1B generally follows the In-River Cable Route except for slight deviations between RM 69 and RM 68 to maintain separation from the CHPE Cable Route and at RM 67 to make a perpendicular crossing of the CHPE Cable Route. RM 66 to RM 42 Alternative 1B follows the In-River Cable Route to RM 64, where it shifts farther towards the center of the river to maintain at least 250 feet separation from the CHPE Cable Route. Alternative 1B would make two perpendicular crossings of the CHPE Cable Route between RM 64 and RM 63. Alternative 1B would then follow the In-River Cable Route to RM 58 where it would make a perpendicular crossing of the CHPE Cable Route and then rejoin the In-River Cable Route just north of Pollepel Island (RM 57). Between RM 57 and 52, Alternative 1B would generally follow the In-River Cable Route, except for where it makes five crossings of the CHPE Cable Route (near RM 55.5, RM 54.5, RM 53.5, RM 53, and RM 52.5). From RM 52, Alternative 1B follows the In-River Cable Route all the way to the Southern Landfall. 2.3 Description of Proposed Transmission Line While the West Point Transmission Cable is referred to as a “line” or “cable” for convenience, the HVDC portion will consist of two transmission cables in a bipolar system, plus a fiber optic communications cable. The 345 kV AC portion will consist of two three-phase circuits in parallel duct banks, each with a fiber optic communications cable.
© 2013 ESS Group, Inc. Page 11 k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013
2.3.1 Project Components The Project will be constructed entirely within the State of New York as part of the NYISO system, and will include the following components: Northern Interconnection: The Northern Interconnection for the Project will be at the existing National Grid Leeds Substation in the Town of Athens, NY, a major 345 kV substation. The interconnection will be by means of a new 345 kV AC circuit leading from the substation to a nearby Converter Station. Northern Converter Station: A VSC-HVDC Converter Station will be constructed on a parcel of land of approximately 5 acres in close proximity to the Leeds Substation in the Town of Athens. Northern HVDC Land Cable and Landfall: A 320 kV underground cable system will extend from the Northern Converter Station for approximately 3.1 miles into the Village of Athens to a landfall site on the western bank of the Hudson River (the Northern Landfall). The land cables will transition to in-river cables in an underground vault at the landfall site. The in-river cables will enter the river via conduits installed through HDD. In-River Cable: From the Northern Landfall, the 320 kV cable will enter the Hudson River and proceed southward for approximately 77.6 miles to the Southern Landfall in Cortlandt, NY, as described in Section 2.1.5. The In-River Cable will be installed a minimum of 15 feet below authorized depth in the Federal Navigational Channel, and a minimum of 8 feet below present bottom in areas outside of the channel. Southern Landfall and HVDC Land Cable: The Southern Landfall in Cortlandt, which will be substantially identical to the Northern Landfall, will include a second cable Transition Vault, with the landfall itself accomplished via HDD. The 320 kV southern HVDC land cable will extend approximately 0.5 miles to the Southern Converter Station situated on the same property in Cortlandt. Southern Converter Station: A VSC-HVDC Converter Station, substantially identical to the Northern Converter Station, will be constructed on a parcel of approximately 5 acres in Cortlandt and will convert DC power back into AC power. Southern Interconnection: The Southern Interconnection point will be the existing 345 kV Buchanan Substation owned by Con Edison, in the Village of Buchanan, NY. A 345 kV AC land cable will extend underground approximately 1.1 miles from the Southern Converter Station to the Buchanan Substation. 2.3.2 320 kV DC Circuit The Project’s 320 kV HVDC cable system will include two Land Cable components (Athens and Cortlandt) and one In-River Cable component. Each will feature cross linked polyethylene (XLPE) dielectric insulation cable design. 2.3.2.1 In-River Cable For the In-River Cable, the conductor is of a compacted circular design, constructed from annealed copper wires and filled with a water blocking material to limit water propagation in case of cable severance. The conductor has a nominal cross sectional area of 2,000 mm². The conductor design meets the requirements laid down by Class 2 stranding as per IEC 60228. The insulation system is manufactured in a dry curing CV line and consists of an inner semi-conducting screen layer, the insulation compound and an outer semi-conducting extruded insulation screen, which are extruded in a triple tandem process in order to avoid inter-layer
© 2013 ESS Group, Inc. Page 12 k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013
contamination. The insulation is composed of a cross-linked compound for HVDC applications. The insulation shield is securely bonded to the insulation and requires the application of heat for removal, thus assuring the consistent bond required at this important stress interface. A semi-conducting water swelling tape is applied between the insulation screen and the metallic sheath in order to limit water propagation along the cable core in case of cable damage. The insulated core has a lead alloy (type E) sheath applied over the longitudinal water barrier. An extruded layer of polyethylene compound is provided over the metallic sheath. To avoid any electrical breakdown by induced transient over-voltages, the metallic sheath is short-circuited with the armor wires at intermediate distances. The “armoring” includes the bedding, the armor wires, and the serving application in one common process as follows: Two layers of polyester tape are applied over the inner jacket as bedding for the armor wires. One layer of galvanized steel armor wires is applied over this bedding. Application of bitumen is provided over the armor layer as further anti-corrosion protection and to aid the adhesion of the cable serving. A double layer of polypropylene strings is applied over the armor as cable serving, to provide a degree of abrasion protection and to reduce cable/skid friction during installation. The polypropylene serving is applied with a black and yellow pattern in order to give high visibility to the cable and enable monitoring of cable horizontal movement by ROV cameras. A cross section of the In-River Cable is shown as Figure 2-6. 2.3.2.2 HVDC Land Cable For the HVDC Land Cable, the conductor is a compacted circular design, constructed from annealed copper wires. The conductor has a nominal cross sectional area of 5,000 kcmil (2535 mm²). The conductor design meets the requirements laid down by Class 2 stranding as per IEC 60228. The insulation system consists of an inner semi-conducting conductor screen layer, the insulation compound, and an outer semi-conducting extruded insulation screen, which are extruded in a triple tandem process in order to avoid inter-layer contamination. The insulation is composed of XLPE compound for HVDC applications, and is securely bonded to the insulation and requires the application of heat for removal, thus assuring the consistent bond required at this important stress interface. A semi-conducting water swelling tapes is helically applied between the insulation screen and the metallic sheath in order to limit water propagation along the cable core in case of cable damage. The insulated core has a lead alloy (type E) sheath applied over the longitudinal water barrier, and an extruded layer of polyethylene compound is provided over the metallic sheath. A cross section of the HVDC Land Cable is shown as Figure 2-7 and in the Project Plan Set provided in Attachment 2. 2.3.3 AC Land Cable The segments of 345 kV AC Land Cable for the Project will be single core XLPE cable consisting of segmental strips of copper conductor, semi-conductive polymer conductor screen, XLPE insulation, semi-conductive polymer insulation screen, water barrier, metallic sheath, and extruded polyethylene sheath with graphite coating. The Project’s 345 kV AC Land Cable is substantially identical to the 345 kV AC land cables presently in service for the Neptune and Hudson Transmission projects.
© 2013 ESS Group, Inc. Page 13 k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013
Figure 2-8 and the Project Plan Set provided in Attachment 2 show a typical cross section of a 345 kV AC land cable. 2.3.4 Fiber Optic Communications Cable In order to provide the required remote monitoring telemetry, control and voice communications, a fiber optic cable will be installed alongside the power cable for both the Land and In-River portions. For the In-River Cable installation, the fiber optic cable will be simultaneously installed via jet plow embedment in the same trench as the two conductor cable bundle and will be provided with appropriate mechanical protection. The fiber optic cable is made up of 48 single-mode fiber members, and the In-River portion will be designed to meet the underwater physical conditions. For the AC and HVDC Land Cable systems, dual and redundant fiber optic cables will be installed with adequate separation to avoid a common mode failure. 2.4 Description of Converter Stations The two Converter Stations will use VSC-HVDC technology, one near the northern terminus and one near the southern terminus of the West Point cable system. Control and protection, cooling, fire protection, and other types of equipment are integral to the Converter Stations. 2.4.1 VSC-HVDC Converter Stations Siemens VSC-HVDC technology, known as “HVDC Plus,” represents an evolution in conversion technology that features a high degree of controllability of both active and reactive power; a high degree of modularity and scalability; and a relatively small footprint due to the elimination of certain components that characterize the “classic” HVDC converter station (such as those used for the Neptune and Hudson transmission projects). The Trans Bay Cable project in California between the cities of Pittsburg and San Francisco, completed in 2010, uses HVDC Plus technology and is comparable both in technology and in overall appearance to the West Point Converter Stations. Figure 2-9 is an aerial photograph of one of the Trans-Bay HVDC Plus Converter Stations. Because of its modularity and scalability, an HVDC Plus converter station can be adapted to fit the conditions of its site. The West Point Northern and Southern Converter Stations will require less than 5 acres each, and their final configurations will be determined based on detailed site investigations. For illustrative purposes, a General Arrangement diagram for the West Point Converter Station is shown as Figure 2-10. The figure below shows a typical configuration for point-to-point interconnectors with HVDC cables. The final configuration will account for project-specific requirements. A tertiary transformer winding will be included to supply station auxiliary power.
© 2013 ESS Group, Inc. Page 14 k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013
no DC reactors
2nd star point reactor star point reactor (optional) conventional AC transformers converter reactors on DC side
tertiary winding secondary breaker secondary breaker (optional) (optional) (optional)
Different operational modes are feasible for HVDC Plus interconnectors. In contrast to HVDC “classic”, there is no “minimum power” limitation that requires power flow above 0 MW to be at or above a certain minimum (60 MW for the Neptune and Hudson projects). The Project will be designed for 1,000 MW of bidirectional power flow between the Leeds and Buchanan Substations. In addition, both Converter Stations will have reactive power capability of 400 MVAr at zero power transfer, and 300 MVAr at full load. The reactive power capability can be highly beneficial in assuring system stability. The reactive power can be controlled independently from the active power within specified limits. Furthermore, both stations may exchange reactive power with their connected AC grids independently of each other. The DC link between them is not necessary for exchange of reactive power. The reactive power control is implemented separately for each Converter Station. If desired as another beneficial feature of the Project, black start capability can be provided. This is the ability of HVDC Plus converters to start up a passive AC system. The Project can be designed for black start capability at both stations. The AC bus bar of the VSC Converter Station can be energized after a blackout if the other, sending station is still connected to a live AC network and the auxiliary energy supply is available, for example by a diesel generator set. AC to DC conversion will be accomplished via converter power modules in the Converter Halls. The modules will be designed and rated to meet the performance requirements of the HVDC transmission system. The converters will be indoor, air-insulated, and water-cooled, and have a modular or sectional design and removable components for ease of maintenance. They also will be designed and protected so as to withstand overcurrent and overvoltage stresses due to faults occurring in various parts of the station. Further, they will be designed to be fault-tolerant and capable of operating satisfactorily in service between scheduled maintenance outage periods. Additional detailed information regarding Siemens HVDC Plus technology is included as Appendix 1.
© 2013 ESS Group, Inc. Page 15 k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013
2.4.2 Control and Protection The control and protection system is designed to electrically isolate the West Point Transmission Cable immediately from the interconnecting transmission system upon recognizing a system electrical fault. By automatically powering down the transmission line components in the case of a fault, major failures of the system will be avoided. Electrical power for continuously operating the control and protection system will be provided from a dedicated source (redundant on-site dc batteries) and will be unaffected by the status of the West Point Converter Station it is monitoring. In order to insure that there will be no conflicts between Project and the existing transmission system, National Grid and Con Edison will be consulted on the design and operation of the control and protection system. 2.4.3 Cooling Systems There are no cooling systems associated with the Project other than internal cooling system for Converter Station components. 2.4.4 Fire Protection Each Converter Station will have a suitable fire protection system that meets state and local fire codes as well as industry standards such as the National Fire Protection Association Standards. The Project’s Land and In-River Cables are solid state and will not contain fluid or other flammable materials. 2.5 Installation Methods and Means The Project involves the installation of a new 320/345 kV HVDC Cable System routed from Athens, NY to Buchanan, NY. Installation of the approximately 82.6-mile long Cable System will include the following components: A 320 kV HVDC In-River Transmission Cable (approximately 77.3 miles). Two HVDC Converter Stations, one at each end of the HVDC Cable System. Two short lengths of 320 kV HVDC Land Cable to connect the In-River Cable to the Converter Stations. Two short lengths of 345 kV AC Land Cable to connect the Converter Stations with existing land based system interconnections at the Leeds Substation at the northern end of the Project and at the Buchanan Substation at the southern end. Two series of HDD Conduits at the landfalls at each end of the In-River Transmission Cable. Two underground Transition Vaults, one at each end of the In-River Cable to house the connection between the In-River Cable and Land Cable systems. All Project components, with the exception of the Converter Stations, will be installed underground in ducts and/or conduits. 2.5.1 Anticipated Project Schedule WPP can implement an Accelerated Schedule to achieve a Commercial Operation Date for the Project of June 1, 2016 to meet the needs of the New York State electrical system in the event of the closure of the Indian Point Energy Center. This date is achievable assuming timely receipt of approvals from regulatory agencies. The anticipated schedule for construction, which would include installation of the entire In-River Cable in one construction season, is summarized below.
© 2013 ESS Group, Inc. Page 16 k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013
Task Anticipated Start Anticipated Completion Land Cables Ductbank Installation June 2014 November 2014 Cable Pulling and Splicing November 2014 April 2015 Landfall Transitions Temporary Cofferdam and HDD Installation August 2014 October 2014 In-River Cables Cofferdam Preparation August 2015 August 2015 Route Clearance August 2015 August 2015 Jet Plow Embedment – 1ST Campaign August 2015 September 2015 Jet Plow Embedment – 2ND Campaign September 2015 October 2015 Jet Plow Embedment – 3RD Campaign October 2015 November 2015 Converter Station Construction March 2014 March 2016 Commissioning and Testing March 2016 May 2016
The Alternative Schedule would achieve a Commercial Operation Date for the Project of December 31, 2017. This schedule would include cable installation work beginning in 2015, rather than 2014, and installation of the In-River Cable over the course of two construction seasons in 2015 and 2016. 2.5.2 Cable System Installation The underground components of the Project will include both Land and In-River cable systems, as well as transition facilities for landfalls and In-River/Land HVDC cable connections, as described above. Preliminary installation details for each of these components are presented below. 2.5.2.1 Land Cables The Land Transmission Cable sections and AC interconnect cables will be installed using a combination of HDD and standard utility trenching and installation techniques, depending on location. Excavation will be performed with standard earthmoving machinery, including excavators and backhoes, and will be performed in accordance with applicable standards. HDD methods for installing the Northern AC Transmission Cables will be performed with standard HDD equipment as described below in Section 2.5.2.3. The Land Transmission Cables (Northern and Southern HVDC cables) and Southern AC Transmission Cables will be located in duct bank systems with compacted stabilized backfill or encased in concrete as shown in Figure 4.14-1. Underground splice vaults will be installed to facilitate splicing of sections of Land Cable together at locations to be determined during final design (see Figure 2-11 for details of the splice vaults) Once the cables are installed, trenches will be backfilled using excavated soil and/or clean fill. Excess soil or soil unsuitable for use as backfill will be removed off-site as needed and in accordance with applicable regulations. Site specific details concerning the Land Cables installation techniques will be provided in the EM&CP.
© 2013 ESS Group, Inc. Page 17 k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013
2.5.2.2 Landfall Transitions The transition of the Transmission Cable from land to water at the Northern Landfall, then water to land at the Southern Landfall, will be accomplished through the use of low impact HDD to avoid interference with shoreline structures or direct disturbance of coastal resource areas. Use of HDD also minimizes or avoids direct impacts to nearshore aquatic habitat and shorelines at both ends of the In-River Cable Route. The transition splices and interconnection of the In-River Cable and Land Transmission Cables will be housed within underground Transition Vaults to be constructed in the vicinity of each landfall. Details regarding underground construction at each landfall are provided below. For details of the Transition Vaults, refer to Figure -2-12. Northern Landfall, Athens, NY (RM 118) The Project’s Northern Landfall will be located off North Washington Street, in the Village of Athens in Greene County, NY. This site area is approximately 0.2 miles north of the Union Street intersection, and is on the river’s western shore at approximately RM 118. Refer to Figure 2-13. Just onshore at the Northern Landfall, an underground Transition Vault will be installed at the northwest corner of the site or adjacent to the site within North Washington Street. To the extent practicable, the Transition Vault will be constructed within the drilling pit area for HDD operations to avoid increased areas of direct land disturbance. The final location of the splicing vault will be dependent on the location of other local underground utilities and subsurface geotechnical conditions encountered in the area. Details of this standard utility practice will be provided in the EM&CP. From the Transition Vault, three conduit-lined HDD boreholes will be advanced approximately 500 feet into subsurface sediment in the bottom of the Hudson River. A Temporary Cofferdam structure will be installed in approximately 20 feet of water and its enclosed area mechanically dredged to provide sufficient depth to accept the land-side HDD borehole and conduit. The In- River Cable will be pulled through the underground conduit system from the river to the drill pit. For details of the Temporary Cofferdam, refer to Figure 2-14 and the Project Plan set. WPP has conducted a preliminary geological conditions assessment at the Northern Landfall site and anticipates that the material within and overlying the intended HDD drill path may likely consist of uncontrolled fill over silty sand-sized ancient lacustrine and riverine natural sedimentary deposits. Shale rock does express itself in the subsurface of this area, but is anticipated to be located well below the typical depth of bore for this HDD profile. Further investigations into the as- built conditions of the existing waterfront sheet pile bulkhead, which lines the riverfront in the vicinity of the Northern Landfall, will be needed prior to commencement of HDD operations. Relevant findings will be described in the EM&CP. The diameter of the bore and conduit installed by the HDD process will also depend upon the type and location of known underground utilities and other subsurface structures/foundations in the vicinity of the Northern Landfall transition. Initial evaluations indicate that three boreholes approximately 18 to 24 inches in diameter will be required for the cable’s landfall transition to the underground Transition Vault onshore. After completing the three HDD bores, a high-density polyethylene (HDPE) (or similar material) conduit will be placed in each borehole. These will ultimately house the In-River Transmission Cable. The final design diameter of the boreholes will be determined during engineering design and will be presented in the EM&CP. Additional information on HDD construction methods are provided in Section 2.5.2.3.
© 2013 ESS Group, Inc. Page 18 k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013
Southern Landfall, Cortlandt, NY (RM 42) The Project’s Southern Landfall will be located at a property on the eastern shore of the river that is owned by Con Edison. The Landfall location is approximately at RM 42 in the Town of Cortlandt, NY. Refer to Figure 2-15 and the Project Plan Set provided in Attachment 2. Another underground Transition Vault will be installed in an existing unused paved area on the Con Edison property and near the western terminus of 9th Street. To the extent practicable, the Transition Vault will be constructed within pits excavated for HDD operations. The final location will be dependent on the location of underground utilities and the subsurface geotechnical conditions encountered in the area. Details will be provided in the EM&CP. Similar to the Northern Landfall, the In-River Cable will exit the Hudson River at the Southern Landfall via an approximately 850-foot-long HDD. A Temporary Cofferdam structure will be installed in approximately 20 feet of water and its enclosed area mechanically dredged to provide sufficient depth to accept the land-side HDD borehole and conduit. WPP anticipates that the subsurface material at the Southern Landfall within and overlying the HDD drill path may be silty sand-sized ancient lacustrine and riverine natural sedimentary deposits. Further investigations into the as-built conditions of the existing waterfront sheet pile bulkhead, which lines the riverfront in the vicinity of the Southern Landfall, will be needed prior to commencement of HDD operations. Relevant findings will be described in the EM&CP. The diameter of the bore and conduit installed by the HDD process will also depend upon the type and location of known underground utilities and other subsurface structures/foundations in the vicinity of the Northern Landfall transition. Initial evaluations indicate that, that three boreholes approximately 18 to 24 inches in diameter will be required for the cable’s landfall transition to the underground Transition Vault onshore. After completing the three HDD bores, an HDPE (or similar material) conduit will be placed in each borehole. These will ultimately house the In-River Transmission Cable. The final design diameter of the boreholes will be determined during engineering design and will be presented in the EM&CP. 2.5.2.3 Horizontal Directional Drilling The horizontal drilling proposed for the Project is as follows: Two HDD bores between the Leeds Substation and the Northern Converter Station will total approximately 2,500 feet in length. The HDD at the Northern Landfall will be approximately 500 feet long. The HDD at the Southern Landfall will be approximately 850 feet long. The horizontal alignment, length, and vertical profile of the HDD bores will be determined during final design and will be provided in the EM&CP. The HDD operation at each location will include a land-based HDD drilling rig system, drilling fluid recirculation systems, residuals management systems, and associated support equipment. At the landfalls, the ends of the HDD in the river will terminate within the Temporary Cofferdams, where jet plow embedment of the In-River Cable into the riverbed will start (at the north) and end (at the south). HDD Borehole and Cable Pulling Operations The land-based HDD operations areas will each be approximately 175 feet long by 100 feet wide. It is probable that three boreholes will be required at each of the HDD boring operations: two, boreholes 18 to 24 inches in diameter for the HVDC power cables, and one borehole 6 to 12 inches in diameter for the fiber optic cable. A drill rig staging area approximately 65 feet long by
© 2013 ESS Group, Inc. Page 19 k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013
8.5 feet wide, which includes the HDD/bentonite pit (approximately 8 feet wide by 12 feet long), will be constructed within the HDD operations area for operating the mud system and drill. After HDD operations are complete, the HDD/bentonite pits may also be utilized for the construction of the underground Transition Vaults in the vicinity of the landfalls and the underground Splice Vaults for the Northern AC Transmission Cable. Excess soils and water from these bore pits will be contained during drilling operations and ultimately disposed of off-site in accordance with acceptable disposal area methods. Once completed, the HDD pits will be backfilled with excavated soils and/or clean fill as appropriate. Erosion and sedimentation controls will be installed in accordance with good practice standards of care and methods prior to, during, and after borehole and cable pulling activities. A specially designed HDD drill rig will be set up behind the excavation pit where drill pipe will be set in place to begin the HDD. A bentonite and freshwater slurry will be injected into the borehole to hold the bore open for insertion of the plastic conduit casing as the bore proceeds. When the drill bit advances to exit points for the Northern AC Transmission Cable HDD bores or through the Temporary Cofferdam for the In-River Cable, the bit will be replaced with a series of reamers to widen the borehole. Once the desired borehole diameter is achieved, a pulling head will be placed on the end of the drill pipe and the pipe will be used to pull a section of HDPE conduit into the bored hole from the offshore end. Once the internal cable conduit(s) have been inserted into the HDPE conduit, a clay/bentonite medium will be inserted to fill the void between the cable and the HDPE conduit, and the HDPE conduit ends will be sealed. When construction is complete, all equipment and construction materials will be removed from the site and the area will be returned to its original condition. The land-based HDD operation will be a self-contained operational area system combined with a drilling fluid re-circulation system. This re-circulation system will recycle drilling fluids (water and clay) and contain and process drilling returns of the earth from the boreholes. The earth residuals will then be transferred to trucks for offsite disposal at approved locations. The HDD construction process will involve the use of bentonite drilling fluids in a water-based slurry to transport drill cuttings to the surface for recycling, aid in stabilization of the in situ overburden and sediment drilling formations, and to provide lubrication for the HDD drill string and down-hole assemblies. This drilling fluid is composed of a carrier fluid and solids. The carrier fluid for this HDD operation will likely consist of water (approximately 95%) and inorganic bentonite clay (approximately 5%). Fresh water will be utilized to the maximum extent practicable as the drilling and reaming progresses near the Temporary Cofferdams at the Landfall locations to reduce the potential for bentonite release. No residual earth materials from the boring operation will be directly discharged or released to freshwater wetlands or tidal waters in the Hudson River. Drilling Fluid Monitoring The HDD operation will include monitoring of potential fracture or overburden breakout of the downhole water/bentonite slurry to minimize the potential of drilling fluid breakout adjacent overland areas or the Hudson River. Preliminary review on estimates of overburden thickness and porosity indicate that the HDD conduit systems will predominantly be drilled through sediment overburden at each of the HDD locations. Drilling depths in the overburden should be sufficiently deep to avoid any pressure-induced breakout of drilling fluids through the overburden or riverbed. For extra precaution, a monitoring program will be implemented during the HDD operation to observe and monitor for fluid breakout conditions. This monitoring program will be described in the EM&CP, and is likely to include the following:
© 2013 ESS Group, Inc. Page 20 k:\w296-000 west point partners route concept\regulatory\usace\attachment 1_project narrative\attachment 1_proj. narrative.doc Attachment 1: Project Narrative July 31, 2013