WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP SOUTHEAST STUDY GROUP Subarea 4 Master Plan Update Kick-Off!

July 19

@ 6:30pm

@atlantabeltline

@atlantabeltline

@atlantabeltline WELCOME > BACKGROUNDINTENTION, > PLANNING PROCESS > EXISTING CONDITIONS GOAL > OPEN DISCUSSION & > MEETING WRAP UP PURPOSE Subarea 4 GOAL: Master Plan To implement the Redevelopment Plan goals in the context of each unique Update geographic area.

PURPOSE & OUTCOMES: To guide growth for vibrant, livable mixed-use communities by applying best management practices for transit-oriented development, mobility, affordable housing, green space, and alternative modes of transportation. The outcome is a Master Planning document updated through the voice of community and adopted by the City of for information in the Comprehensive Development Plan. WELCOME > BACKGROUNDTONIGHT’S > PLANNING PROCESS > EXISTING ON CONDITIONS + > OPEN OFF DISCUSSION >CAMERA MEETING WRAP UP TEAM WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP VIRTUAL MEETING FORMAT

• Your line is muted, and you won’t be able to share your video or screen during the meeting.

• To submit questions and provide answers , you may do so in the Q&A box anytime during the meeting . • During discussions you may use the “Raise Hand” feature . • A recording of this meeting, the presentation, a copy of tonight’s Q&A and all other supporting materials will be made available online at www..org/meetings • If you are having technical difficulties during the meeting, please email [email protected] WELCOME > BACKGROUNDVIRTUAL > PLANNING PROCESS > MEETINGEXISTING CONDITIONS > OPEN DISCUSSION FORMAT > MEETING WRAP UP (CONTD.) Phone Attendees • Press *9 on telephone keypad to “raise your hand” during the Q&A to indicate you want to speak. Facilitator will unmute your mic.

Online Attendees: • Submit a question or comment any time in Q&A box. • The “raise your hand” feature is available to all Zoom participants however we are prioritizing phone attendees.

Facebook Live Attendees: • Please feel free to participate in the “Comments Section.” Someone on our staff will make sure I see your questions. WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP POLL QUESTIONS Poll Question #1 What neighborhood do you live in? • Reynoldstown • Cabbagetown • Edgewood • Grant Park • • Ormewood Park • A BeltLine neighborhood in the City of Atlanta not on this list • A neighborhood in the City of Atlanta not on this list • A neighborhood not in the City of Atlanta WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP POLL QUESTIONS Poll Question #2 How do you feel about the Beltline Master Plan Updates? • Thrilled • Happy • No opinion • Apprehensive • Upset WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP POLL QUESTIONS Poll Question #3 How many BeltLine meetings have you been to? • None • 1-4 meetings • 5 or more meetings WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP POLL QUESTIONS Poll Question #4 How would you rate your knowledge of the BeltLine's full portfolio of projects? • I'm an expert. • I know more than most people. • I don't know a lot, but I want to learn more. • I don't know anything about the BeltLine. WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP ATLANTA BELTLINE VISION WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP Original Subarea Master Plan

• Original 10 Subarea Master Plans 7 created over 10 years ago • A lot has happened, it’s time to update 8 them to reflect these changes and the 6 potential for the future 9 • Updates are adopted into the 5 Comprehensive Development Plan 10 (CDP) 4 • We are NOT starting from scratch 1 3 2 WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP MEET THE CONSULTING TEAM

Sizemore Group Modern Mobility Partners Transportation Award-winning Planning And Architecture Kirsten Mote

Bill de St. Aubin, AIA, LEED AP, CEO Principal Noell Consulting Group Market Analysis David Laube Deanna Murphy, AICP, M. ARCH Chirag Date Jordan Rowe Project Manager Sr. Project Planner

Nick Miller Ashlyn Oakes Duncan Associates Zoning & Land Use Co-Project Manager Project Planner Intern Kirk Bishop

Lakota Group Landscape Architecture Sycamore Community Engagement Kevin Clark Ed Caddell Scott Freres WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP PLANNING PROCESS

1. Community Engagement through the Update Process

2. Drafting the Final Document

3. Introduce Plan to City Council for Adoption

4. Neighborhood Planning Unit Engagement

5. Amend Draft Document

6. Final Plan Adoption WELCOME > BACKGROUNDCOMMUNITY> PLANNING PROCESS > EXISTING ENGAGEMENTCONDITIONS > OPEN DISCUSSION > MEETING WRAP UP STRATEGY

Take a look Web-Based & at our Social Pin Point Interactive Stakeholder Festivals & Working Groups Community/Pop-Up Website Events

Social Pinpoint Project Survey https://bit.ly/BeltLineSA4

Virtual Public Design Meetings Technical & Small Workshops Group Discussions WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP DEMOGRAPHICS - INCOME

Subarea 4 Median Income, 2019 BeltLine Subarea 4 Subarea 4 Household Income Distribution, 2011 Household incomes City of Atlanta $100,000 2011 vs 2019 have seen large Atlanta Metro 2019 $90,000 $95,012 increases since 2011 $80,000 United States 27.8% with the local area $70,000 < $30,000 $60,000 $68,316 10.9% $62,843 outpacing city and $50,000 $59,948 $58,700 regional growth $40,000 16.4% $30,000 $30k - $50k 15.6% rates. $20,000 $10,000 17.6% $0 $50k - $75k 11.6% Subarea 4 Median Income % Change, 2011-2019

80.0% 11.4% 67.5% $75k - $100k 70.0% 14.2% 60.0% 13.2% 50.0% $100k - $150k 20.3% 40.0% 30.5% 30.0% 18.2% 18.0% 19.1% 13.6% 20.0% $150k < 27.5% 10.0%

0.0% 0.0% 5.0% 10.0% 15.0% 20.0% 25.0% 30.0% WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP DEMOGRAPHICS - AGE

The local area has Age Distribution Change, 2011 vs 2019 Age Distribution Comparison, 2019 seen the strongest 40.0% 35.0% growth in young 35.0% professional 30.0% households aged 30.0% 25.0% 25-34. 25.0% 20.0% 20.0%

15.0% 15.0%

10.0% 10.0%

5.0% 5.0%

0.0% 0.0% < 17 18 - 24 25 - 34 35 - 54 55 < < 17 18 - 24 25 - 34 35 - 54 55 <

2011 2019 BeltLine Subarea 4 City of Atlanta WELCOME > BACKGROUNDDEMOGRAPHICS > PLANNING PROCESS > EXISTING CONDITIONS > OPEN - DISCUSSION > MEETING WRAP UP EDUCATION

Change in Education, 2011 vs 2019 Educational Attainment Comparison, 2019 60.0% 50.0%

45.0% 43.4% 50.0% 48.2% 40.0% 36.2% 35.7% 35.0% 32.6% 31.8% 40.0% 35.7% 30.0% 31.8% 32.6% 28.9% 25.0% 30.0% 20.3% 20.0% 22.9%

15.0% 20.0%

10.0% 10.0% 5.0%

0.0% Less than Bachelor's Bachelor's Degree Master's Degree or More 0.0% Degree Less than Bachelor's Degree Bachelor's Degree Master's Degree or More

2011 2019 BeltLine City of Atlanta WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP DEVELOPMENT ACTIVITY

Development has been primarily residential and retail.

Atlanta Dairies, Retail & Office Glencastle, Office Modera Reynoldstown, Multifamily Rental Development Totals 3,039 multifamily rental units added 369 for-sale units added 75% attached product (condos, duplexes, townhomes) ~107,000 SF of office space ~452,000 SF of retail space WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP EXISTING STUDIES

1. ABI Affordable Housing 7. City of Atlanta 13.One Atlanta Economic Working Group Report Comprehensive Mobility, Recovery and Development Plan Resiliency Plan 2. Atlanta BeltLine 2030 Strategic 8. DCP Inclusionary 14.One Atlanta Housing Implementation Plan Zoning Report Affordability Plan 3. Atlanta BeltLine 9. Hulsey Yard 15.One Atlanta Strategic Redevelopment Plan Neighborhood Master Transportation Plan Plan 4. Atlanta City Design – 16.Reynoldstown 2000 Aspiring to the Beloved 10.Imagine Memorial and Beyond: A Community Neighborhood Master 11.Memorial Dr.–Martin Plan 5. Atlanta Streetcar Luther King, Jr. Drive System Plan Area Revitalization Study 6. CAP/ADID Master Plan 12.Moreland Corridor LCI Update WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP WHAT WOULD YOU LIKE TO…

Preserve? Change?

Create? Connect? WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP

Existing Community Facilities, Public Space, Parks , Schools & Landmarks

Schools Community Facilities

Schools

Parks WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP

Subarea 4 Historic & Cultural Resources WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP WHAT WOULD YOU LIKE TO…

Preserve? Change?

Create? Connect? WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP WHAT WOULD YOU LIKE TO…

Preserve? Change?

Create? Connect? WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP

3

Major Multifamily Housing Projects 2 1. Lumen Grant Park 2. Reynoldstown Senior Residences 3. Station R 4 4. Modera Reynoldstown 7 5. RT Dairies (Formerly 1 5 Alta Dairies) 6 8 6. Alta East 7. 841 Memorial 8. Elan Madison Yards 9 11 9. Link Grant Park 10. Glenwood at Grant 10 Park 12 11. ENSO 12. 915 Glenwood WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP

Major Commercial Projects

1. The Larkin 2. Atlanta Dairies 3. Madison Yards 1 4. Glencastle 2 3 5. Glenwood Kroger

5 4 WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP WHAT WOULD YOU LIKE TO…

Preserve? Change?

Create? Connect? WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP WHAT WOULD YOU LIKE TO…

Preserve? Change?

Create? Connect? WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP

Existing Mobility WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP

Traffic Volume WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP

Planned Projects WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP WHAT WOULD YOU LIKE TO…

Preserve? Change?

Create? Connect? WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP OPEN DISCUSSION Phone Attendees • Press *9 on telephone keypad to “raise your hand” during the Q&A to indicate you want to speak. Facilitator will unmute your mic.

Online Attendees: • Submit a question or comment any time in Q&A box. • The “raise your hand” feature is available to all Zoom participants however we are prioritizing phone attendees.

Facebook Live Attendees: • Please feel free to participate in the “Comments Section.” Someone on our staff will make sure I see your questions. WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP UPCOMING MEETINGS

TENTATIVE965 SCHEDULE 1,029 Subarea 4 Master Plan Update – Kick-Off • Monday, July 19th at 6:00 p.m. Subarea 4 Master Plan Update – Data Presentation • Thursday,593 September 30th at 6:30 p.m. 1,3 Subarea 4 Master Plan Update – Design Workshops 79 • October – Dates & times to be announced Subarea 4 Master Plan Update – Draft Presentation • Thursday, November 4th at 6:30 p.m. Subarea 4 Master Plan Update – Final Draft Presentation • Thursday, January 20th at 6:30 p.m. WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP CONTACT INFORMATION

Community965 Engagement Managers: 1,029 Whitney Fuller: [email protected] Nathan Soldat: [email protected] 593 1,3 Director of Planning: 79 Lynnette Reid: 404-477-3550, [email protected]

For more information on the project: beltline.org/

Share your feedback: [email protected] WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP THANK YOU! WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP HOME EMPOWERMENT! TAX APPEAL WORKSHOP

Tax Appeal • The Atlanta BeltLine Partnership, Atlanta Legal Aid, and Grove Park Foundation are partnering to guide property owners in BeltLine neighborhoods through the property tax assessment appeal process.

The Fix That! • Home Repair Series, a 4-part series of free online workshops focused on helping you make simple repairs in your home, save money on repairs, and making you safer and more secure in your home. Join us for the final workshops in our series:

Plumbing Basics with Heads Plumbing: Wednesday, July 28th at 6:00 p.m.

Visit beltline.org/empower or call 404-446-4404 WELCOME > BACKGROUND >JOB PLANNING PROCESS OPPS: > EXISTING CONDITIONS GROW > OPEN DISCUSSION ON> MEETING THE WRAP UP BELTLINE

Construction Education Foundation of Georgia: • CEFGA, is one of our newest workforce partners. They offer a four-week construction readiness training and certification program providing skills to kickstart your career in the industry.

Juvo Jobs: • Juvo360 helps residents find hyper-local work inside their communities. Download the Juvo Jobs app and apply for jobs on your mobile device.

Visit beltline.org/workforce-partnerships or call 404-446-4404 WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP POLL QUESTIONS Poll Question #5 How did you hear about this meeting? • Email from Atlanta BeltLine, Inc. • Social Media • Next Door • Newsletter • Communication from a family member, friend or neighbor • Other WELCOME > BACKGROUND > PLANNING PROCESS > EXISTING CONDITIONS > OPEN DISCUSSION > MEETING WRAP UP POLL QUESTIONS Poll Question #6 Was this meeting helpful? • Yes • No • No opinion APPENDIX APPENDIX

Resources Where We Are Today Timeline for Trail Completion • Year-over-year maps through 2023 • Projected timeline for completion • Budget and expenditures Additional Financial Impact Examples APPENDIX Resources

• Legacy Resident Retention Fund: www.beltline.org/retentionfund and 678-718-5469 • Home Empowerment Workshops: www.beltline.org/empower • STRIVE (job training and career support): www.beltline.org/workforce-partnerships or call 404-446-4404 • Juvo Jobs (app that connects you to nearby jobs): www.beltline.org/workforce-partnerships or call 404-446-4404 Subarea 4 Natural Features Subarea 4 Existing Land Use Subarea 4 COA Future Land Use Subarea 4 2011 Master Plan BeltLine Proposed Land Use Subarea 4 Existing Zoning Subarea 4 Plan Review & Items for Coordination APPENDIX Where we are today: trails

Affordable housing has been spurred on in areas near completed trails.

Completing the 22-mile loop with increase affordable housing in all geographies. Atlanta BeltLine - Affordable Housing Approach

AS OF 8/31/2020

STRATEGIES FOR CREATION AND PRESERVATION Policy Programs Support existing affordable Partner with agencies to design housing policy (Inclusionary and implement Anti-Displacement Zoning/Development Authority strategies, Rental Assistance, and Ordinance) and work toward new other innovative programs to help policy initiatives create/preserve affordable Preservation housing units Engage partners to identify Acquisition/ existing affordable housing units Direct Development at-risk of expiration to preserve Acquire vacant land and/or affordability distressed real estate for future housing development Developer Incentives Developer Incentives (BAHTF) (TAD Increment) Utilizing the Housing Trust Fund to Utilizing the TAD Increment to provide gap financing and other provide gap financing and other developer incentives for affordable developer incentives for affordable housing production 28,000 5,600 housing production Housing Units Affordable Units APPENDIX Housing Affordability 101

What is does 965 1,029 AMI mean?

Area Median Income (AMI): a measure of an area’s median income calculated annually by HUD 593 1,3 (Department of Housing and Urban Development) 79 For more details, please visit: beltline.org/housing or hud.gov

CHART LEGEND >>

ABI Atlanta BeltLine AH Atlanta Housing DAFC Development Authority of Fulton County DCA Department of Community Affairs IA Invest Atlanta APPENDIX Affordable Housing created & Preserved APPENDIX

Affordable Housing created & Preserved

965 1,029

593 1,3 3,966 79 1,558 2,408 APPENDIX Affordable Housing pipeline

Affordable 965 1,029 Units Created/Preser ved 593 1,3 79 APPENDIX Where we are today: Econ. Dev.

REDEVELOPMENT PLAN GOAL • $10 billion in economic development STATUS • $7 billion generated in private development • Nearly $670 million invested in the project at the end of 2020 including more than $50 million in private contributions • Return on investment of over 10-to-1 • ~2 million visitors to the Atlanta BeltLine annually APPENDIX Where we are today: Jobs APPENDIX Where we are today: transit

STATUS • Acquired right of way for future transit where running adjacent to BeltLine trail • With MARTA, ABI obtained FTA Tier I EIS, Record of Decision to advance transit around 22-mile loop • Working with City and MARTA to advance Streetcar East Extension and Streetcar West Extension APPENDIX Timeline for Completion

Estimated trail status with SSD by end of year: 2021

Hispanic Heritage Month Feature on Buena Vida Tapas & Sol EXPANSION: STREETCAR EAST EXTENSION

✓ Working with City of Atlanta, Atlanta Beltline Inc.

✓ Design 2022-2024

✓ Construction 2024-2026

✓ In Service 2027

59