GOVERNMENT OF COMMUNICATION &WORKS DEPARTMENT No. SOR/V-39/C&W/2019 Dated Peshawar, the ' /05/2021 To The Chief Engineer (North), Communication & Works, Saidu Sharif, .

SUBJECT: REVISED ADMINISTRATIVE APPROVAL FOR THE SCHEME "AOM&R OF ALL GOVT. ROADS INCLUDING CLEARANCE OF ROAD WAY / REMOVAL OF LANDSLIDE SLIPS ETC DISTRICT SHANGLA."

In exercise of the powers delegated vide Part-I Serial No.5 Second Schedule of the Delegation of Powers under the Financial Rules and Powers of Re-appropriation Rules, 2018, the Khyber Pakhtunkhwa Provincial Government is pleased to accord the Revised Administrative Approval for the implementation of the scheme under AOM&R during (2020-21) "AOM&R of all Govt. Roads including Clearance of Road Way / Removal of Landslide Slips etc District Shangla" for current financial year (2020-21) at a total cost of Rs. 50.00 million (Rupees Fifty million only) as per detail given below:-

S.No. Name of Work Amount (Rs. In Million) A Already Approved Roads 1. Bord Yekhtangi Road 2.01 2. Karora Ajmir Road 2.69 3. Karora Chakiser Road 2.08 4. Chakiser Dandai Road 0.64 5. Biagli Road 0.31 6. Loder Road 1.49 7. Kormang Road 1.63 8. Alpure Lilioni Road 1.88 9. Road 1.48 10. Martung Road 0.40 D/d 7.50 % income tax -1.10 D/d 47.72 % below -6.45 Total (A) 7.06 B Emergency nature work 5.650 D/d 51.63 % below -2.92 Total (B) 2.73 C Proposed road (Additional Work) 1. Puran Martung Road 3.91 2. Karora Shalpur Road asphalt work (Km-1.9) 10.05 3. Uchlas Road 0.62 4. Chakiser Dandai Road (asphalt work KM-8, 9, 11, 12, 13, & 16) 3.40 5. Butyal to Khatakser Road 0.45 6. Chakiser Said Abad Road 1.99 7. Almi Banda Road 1.26 8. Banr Road 0.74 9. Gajee Karshat Road 1.87 10. Zara Dehrai Road 2.58 11. Alpure Lilioni Road (asphalt work Km-14,15,16) 2.69 12. Link Road Sari Khawre 2.00 13. Repair of Kabalgram Bridge 6.33 14. Shangla Top Maroofkhel Road 0.43 15. Tetwalan Bechar Road 0.38 16. Ranyal Opel Road 0.51 17. Dera Serai Dunkacha 0.58 18. Manai Maira Road 0.97 19. Karora Chakiser Road (asphalt work Km-1, 2, 3) 2.49 20. D/d 7.50 % income tax -3.24 Total (C) 40.01 Total (A + B +C) 49.80 Advertisement charges 0.20 G.Total 50.00

1. The scheme was revised approved by the DDWP/DSC in its meeting held on 06.04.2021. Minutes circulated by C&W Department vide No. SOR/3-4/G-MTG-W&S/2010 dated 28.04.2021.