The World Bank Report No: ISR16833

Implementation Status & Results Siddhirganj Power Project (P095965)

Operation Name: Siddhirganj Power Project (P095965) Project Stage: Implementation Seq.No: 13 Status: ARCHIVED Archive Date: 20-Dec-2014 Country: Bangladesh Approval FY: 2009

Public Disclosure Authorized Product Line:IBRD/IDA Region: SOUTH ASIA Lending Instrument: Specific Investment Loan Implementing Agency(ies): EGCB, GTCL, Power Grid Company of Bangladesh (PGCB) Key Dates Board Approval Date 30-Oct-2008 Original Closing Date 31-Mar-2016 Planned Mid Term Review Date 18-Dec-2013 Last Archived ISR Date 21-May-2014 Public Disclosure Copy Effectiveness Date 31-Mar-2009 Revised Closing Date 31-Mar-2016 Actual Mid Term Review Date 21-Jan-2014

Project Development Objectives Project Development Objective (from Project Appraisal Document) Increase supply of electricity to Bangladesh grid network.

Has the Project Development Objective been changed since Board Approval of the Project?

● Yes No Public Disclosure Authorized Component(s)

Component Name Component Cost 335 MW Combined Cycle Power Plant (CCPP) 460.17 230 kV Power Evacuation System 39.53 60 km, 30-inch gas transmission line 101.10 Technical Assistance and MIS 50.52 Price/Physical Contingency of GTCL and TA, and Exchange Rate Loss 11.57

Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Moderately Unsatisfactory Moderately Unsatisfactory Public Disclosure Authorized Overall Implementation Progress (IP) Moderately Unsatisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial

Implementation Status Overview

Public Disclosure Copy Implementation of the project implementation has been accelerated since May 2014. There is steady progress of physical infrastructure, overall 63% completed. Construction of combined cycle power plant (CCPP) has advanced to 50%; installation of power evacuation system is complete and it is on partial load-test; and installation of gas transmission line is 85% complete and scheduled to flow upstream gas from November. Implementation of Technical Assistance (TA) is going on steadily with three large contracts, at advanced stage

Page 1 of 5 Public Disclosure Authorized The World Bank Report No: ISR16833

of procurement. The implementing agencies are acquiring a wide range of utility capability with the help of the TA. The current rate of implementation trend of the project is expected to continue.

Based on the above, the implementation performance rating of the project has been upgraded to Moderately Satisfactory (MS). However, the PDO rating of the project remains Moderately Unsatisfactory (MU) as the PDO Indicator (supply 2.49 billion kWh of energy per annum) cannot be monitored in life time of the project (project closing on March 31, 2016) since the CCPP is scheduled to be commissioned in February 2016. Hence, an extension of the closing date is required to review the PDO rating for an upgrade. An additional reason for not upgrading the PDO rating is the lack of signed gas supply agreement (GSA) since this is key to ensuring that the PDO can be achieved. The Simple Cycle commissioning scheduled for May 2015 is achievable with continued concerted efforts of the implementing agencies, Isolux and Fichtner.

The next supervision mission planned for December 2014 will review the implementation performance for an upgrade of the IP rating, and also the PDO rating in case an extension of the project closing date is processed in Bank system.

Public Disclosure Copy Locations Country First Administrative Division Location Planned Actual Bangladesh Division Siddhirganj

Bangladesh Not Entered Maniknagar

Bangladesh Not Entered Bakhrabad

Bangladesh Dhaka District

Bangladesh Dhaka Division District

Bangladesh Dhaka Division Munshiganj District

Bangladesh District

Results

Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Additional annual electricity delivered to grid (in Text Value 0 0.00 At least 2.49 billion billion kWh): peak and off-peak: 2.49 kWh delivered to grid. Peak:0.624 bilion kwh Off-peak :1.87 billion kWh Date 01-Apr-2009 04-Nov-2014 31-Mar-2016 Comments No kWh generated as CCPP is under construction.

Intermediate Results Indicators Public Disclosure Copy

Page 2 of 5 The World Bank Report No: ISR16833

Indicator Name Core Unit of Measure Baseline Current End Target Generation Capacity of Conventional Megawatt Value 0.00 0.00 335.00 Generation constructed under the project Date 01-Apr-2009 04-Nov-2014 31-Mar-2016 Comments Construction of 335 MW 335 MW CCPP built and Siddhirganj CCPP advanced, operational. 50% completed. GT and GTG being assembled, other key foundation and erection works ongoing Transmission lines constructed or rehabilitated Kilometers Value 0.00 11.00 11.00 under the project Date 01-Apr-2009 04-Nov-2014 31-Mar-2016 Public Disclosure Copy Comments Transmission lines constructed under the Kilometers Value 0.00 11.00 11.00 project Sub Type Date 01-Apr-2009 04-Nov-2014 31-Mar-2016 Breakdown Comments Installation of Siddhirganj- 11 km 230 kV power Maniknagar Power evacuation system built, evacuation system is transfers at least 2.49 billion complete on it is partial load- kWh to grid. test. The system is awaiting commissioning of the CCPP so that it can be tested on full load from the power plant. 60 km gas transmission line constructed Kilometers Value 0.00 60.00 60.00 Date 01-Apr-2009 04-Nov-2014 31-Mar-2016 Comments Pipeline installation complete, 60 km gas supply line pre-commissiong doneand supplies gas to 335 MW other associated works CCPP and the other 1,300 ongoing. MW power plants at Siddhirganj. Projected lifetime fuel savings Mega Joules (MJ) Value 0.00 0.00 218.60 Date 01-Apr-2009 04-Nov-2014 31-Mar-2016 Comments 0.00 The CCPP is not yet 218.6 billion MJ projected life ready to burn any fuel. time fuel saving achieved. O&M Contracts budgeted and implemented Text Value Limited O&M capacity of O&M for Siddhirganj 2x120 EGCB runs the 335 MW EGCB MW peaking units is CCPP on global O&M operational. It is providing protocols. O&M service but is constrained to deliver annual

Public Disclosure Copy energytarget due to acute

Page 3 of 5 The World Bank Report No: ISR16833

shortage of gas supply to these plants. Date 01-Apr-2009 04-Nov-2014 31-Mar-2016 Comments ERP functional and generating reports Text Value Information based on past Information based on past ERP go live and is generating data and records data and records. Both EGCB reports. and GTCL earned some knowledge on ERP design. Date 01-Apr-2009 04-Nov-2014 31-Mar-2016 Comments EGCB is evaluating the bids on ERP. GTCL is finalizing its

Public Disclosure Copy ERP bid document, will submit to Bank this week for RPM review.

Data on Financial Performance (as of 18-Nov-2014)

Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P095965 IDA-45080 Effective 30-Oct-2008 13-Nov-2008 31-Mar-2009 31-Mar-2016 31-Mar-2016

Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P095965 IDA-45080 Effective XDR 222.60 222.60 0.00 122.03 100.57 55.00

Disbursement Graph Public Disclosure Copy

Page 4 of 5 The World Bank Report No: ISR16833 Public Disclosure Copy

Key Decisions Regarding Implementation Nothing to disclose.

Restructuring History Level 1 Board/AOB Decision on 15-Apr-2014

Related Projects There are no related projects. Public Disclosure Copy

Page 5 of 5