OUR BUILDINGS Long-term Strategies for Deep Energy Retro tting

Etropole Strategy and pilot projects for renovation of the municipal Project “Accelerating climate action building stock buildings – Strengthening civil society and policy makers in and

BPIE Goals of Municipality

STRATEGIC GOAL The implementation of comprehensive and ambitious energy efficiency projects in all inhabited public buildings with actual potential for energy savings and increased use of “The benefits of local renewable energy sources to provide an optimal environment for the energy efficiency are provision of high quality public services undeniable.” and to attract private investment to support the transformation of Etropole into a preferred place for living and professional development of young

Dimitar Dimitrov, Mayor of Etropole Municipality

SPECIFIC TARGETS BY TARGETS SUMMARY Increasing RES 2030 Reduction of final Reduction of final Reduction of share in the final Period/Targets energy demand energy demand carbon emissions energy demand people. (MWh/а) (%) (%) (%) 1. Improving the energy efficiency (EE) of buildings and reducing CO Short-term 2 programme »»397 »»18 »»15 »»32 emissions: 2020 – 2022 »»Reduction of the required final Long-term energy demand compared to the programme »»682 »»27 »»34 »»50 2020 – 2030 OUR BUILDINGS “normalised” baseline scenario for the selected priority buildings 15% to 50%. Achieving this goal energy measures, as well as their Long-term Strategies for by 27% by 2030, or approximately Deep Energy Retro tting is also expected to contribute to relationship with air quality; 682 MWh / a, and reduction of CO 2 improving air quality. » Maintenance of the Municipal emissions by 34% by 2030 or a » 3. Raising citizens’ awareness of Energy Information System (MEIS) total of 452 tСО . 2 the benefits of energy efficiency, for monitoring the condition and »»Achieving optimal thermal and renewable energy sources and improvement of the energy and hygienic comfort in accordance stimulating investments for ecological characteristics of the with the regulations; renovation of public and private municipal buildings. 2. Increasing the share of renewable buildings: BPIE energy sources (RES): »»Preparation of a schedule for »»Increasing the RES share of energy conducting annual information consumed for heating in the campaigns and training seminars selected priority buildings from on the benefits of implementing energy efficiency and renewable 2 | | 3 HORT-TERM AND LONG-TERM PROGRAMME OF THE IMPLEMENTATION OF THE INVESTMENT PROJECTS AND THE NON-INVESTMENT ACTIVITIES Проект за Проект за AND THE RESPECTIVE EXPENSES, INCLUDED IN THE ENERGY EFFICIENCY PLAN OF ETROPOLE MUNICIPALITY Short-term programmeShort-term programme Long-term programme Long-term programme PROJECTS ANDPROJECTS ACTIVITIES AND ACTIVITIES 2020 20212020 20222021 20222023 2024 2023 2025 20242026 20252027 20262028 20292027 2030 TOTAL2028 AMOUNTS2029 BY 2030TOTAL AMOUNTSTOTAL BYAMOUNTS BY TOTAL AMOUNTS BY INVESTMENT PROJECTS:INVESTMENTТип: PROJECTS: Тип: PROJECTS PROJECTS UNTIL NOWPROJECTS PROJECTS UNTIL NOW Etropole MunicipalEtropole Adm Ministrationunicipal Administration EE+RES BGN 300.000,00EE+RES BGN 300.000,00BGN 0,00 BGN BGN0,00 0,00 BGNBGN 0,00 0,00 BGN 150.000,00BGN 0,00BGN BGN0,00 150.000,00BGN 0,00 BGNBGN 0,00 0,00 BGNBGN 0,00 0,00 BGN BGN0,00 0,00BGN 0,00 BGN 0,00 BGNBGN 0,00450.000,00BGN 0,00 BGN 300.000,00BGN 450.000,00 BGN 300.000,00 Primary SchoolPrimary "Hristo Sc Bhoolotev" "" EE+RES BGNEE+RES 0,00 BGN 145.793,00BGN 0,00 BGNBGN 145.793,00 0,00 BGNBGN 0,00 0,00 BGN 0,00BGN 0,00BGN 0,00 BGN 0,00BGN 0,00 BGNBGN 0,00 0,00 BGNBGN 0,00 0,00 BGN BGN0,00 0,00BGN 0,00 BGN 0,00 BGNBGN 0,00145.793,00BGN 0,00 BGN 145.793,00BGN 145.793,00 BGN 145.793,00 Vocational schoolVocational school EE+RES BGNEE+RES 0,00 BGN 571.209,00BGN 0,00 BGNBGN 571.209,00 0,00 BGNBGN 0,00 0,00 BGN 0,00BGN 0,00BGN 0,00 BGN 0,00BGN 0,00 BGNBGN 0,00 0,00 BGNBGN 0,00 0,00 BGN BGN0,00 0,00BGN 0,00 BGN 0,00 BGNBGN 0,00571.209,00BGN 0,00 BGN 571.209,00BGN 571.209,00 BGN 571.209,00 Additional buildingAdditional - Primary building School - Primary "Hristo Botev"School "Hristo Botev" EE+RES BGNEE+RES 0,00 BGNBGN 0,00 0,00 BGN 54.160,00BGN 0,00 BGN 54.160,00BGN 0,00 BGN 0,00BGN 0,00BGN 0,00 BGN 0,00BGN 0,00 BGNBGN 0,00 0,00 BGNBGN 0,00 0,00 BGN BGN0,00 0,00BGN 0,00 BGN 0,00 BGNBGN 0,00 54.160,00BGN 0,00 BGN 54.160,00BGN 54.160,00 BGN 54.160,00 High School "HristoHigh School Yasenov" "Hristo Yasenov" RES BGNRES 0,00 BGNBGN 0,00 0,00 BGN BGN0,00 0,00 BGN BGN250.000,00 0,00 BGNBGN 0,00 250.000,00BGN 0,00 BGN 0,00 BGNBGN 0,00 0,00 BGN 0,00 BGN BGN0,00 0,00BGN 0,00 BGN 0,00 BGNBGN 0,00250.000,00BGN 0,00 BGN 0,00BGN 250.000,00 BGN 0,00 Home for theHome elderly f orand the a c eentrelderly for a ndsocial a c entrerehabilitatio for socialn and rehabilitatio n and RES BGNRES 0,00 BGNBGN 0,00 0,00 BGN BGN0,00 0,00 BGNBGN 0,00 0,00 BGN 40.000,00BGN 0,00BGN 0,00BGN 40.000,00BGN 0,00 BGNBGN 0,00 0,00 BGNBGN 0,00 0,00 BGN BGN0,00 0,00BGN 0,00 BGN 0,00 BGNBGN 0,00 40.000,00BGN 0,00 BGN 0,00BGN 40.000,00 BGN 0,00 integration integration Nursery "Patilantsi"Nursery "Patilantsi" RES BGNRES 0,00 BGNBGN 0,00 0,00 BGN BGN0,00 0,00 BGNBGN 0,00 0,00 BGN 0,00BGNBGN 0,00 30.000,00 BGN 0,00BGN 0,00BGN 30.000,00BGN 0,00 BGNBGN 0,00 0,00 BGN BGN0,00 0,00BGN 0,00 BGN 0,00 BGNBGN 0,00 30.000,00BGN 0,00 BGN 0,00BGN 30.000,00 BGN 0,00 KindergartenKindergarte "Edelweiss"n "Edelweiss" RES BGNRES 0,00 BGNBGN 0,00 0,00 BGN BGN0,00 0,00 BGNBGN 0,00 0,00 BGN 0,00BGN 0,00BGN 0,00 BGN 40.000,000,00 BGNBGN 0,00 0,00BGN 40.000,00BGN 0,00 BGN BGN0,00 0,00BGN 0,00 BGN 0,00 BGNBGN 0,00 40.000,00BGN 0,00 BGN 0,00BGN 40.000,00 BGN 0,00 KindergartenKindergarte "Bell" n "Bell" RES BGNRES 0,00 BGNBGN 0,00 0,00 BGN BGN0,00 0,00 BGNBGN 0,00 0,00 BGN 0,00BGN 0,00BGN 0,00 BGN 0,00BGN 0,00 BGNBGN 40.000,00 0,00 BGNBGN 0,00 0,00 BGNBGN 40.000,00 0,00 BGN 0,00 BGN 0,00 BGNBGN 0,00 40.000,00BGN 0,00 BGN 0,00BGN 40.000,00 BGN 0,00 Nursery "Sun"Nursery "Sun" RES BGNRES 0,00 BGNBGN 0,00 0,00 BGN BGN0,00 0,00 BGNBGN 0,00 0,00 BGN 0,00BGN 0,00BGN 0,00 BGN 0,00BGN 0,00 BGNBGN 0,00 0,00 BGNBGN 30.000,00 0,00 BGN BGN0,00 0,00BGN 0,00BGN 30.000,00 BGNBGN 0,00 30.000,00BGN 0,00 BGN 0,00BGN 30.000,00 BGN 0,00 Project for renovatioProject nf orof rSUOenovation of SUO EE+RES EE+RES BGN 452.000,00 BGN 452.000,00 BGN 452.000,00 BGN 452.000,00 TOTAL FOR INVESTMENTTOTAL PROJECTS: FOR INVESTMENT PROJECTS:BGN 300.000,00 BGNBGN 717.002,00 300.000,00 BGNBGN 506.160,00 717.002,00 BGNBGN 506.160,00 250.000,00 BGN 190.000,00BGN 250.000,00BGN 30.000,00BGN 190.000,00BGN 40.000,00BGNBGN 30.000,00 40.000,00BGN 40.000,00 BGN 40.000,00 BGN 1.651.162,00 BGN 1.523.162,00BGN 1.651.162,00 BGN 1.523.162,00 NON-INVESTMENT ACTIVITIES:NON-INVESTMENT ACTIVITIES: AdministrativeAdministrative Nomination ofNomination energy manager of energy manager BGN 0,00 BGN 0,00 BGN 0,00 BGN 0,00 DevelopmentDevelopment of a proposal forof aattracting proposal investments for attracting investments BGN 0,00 BGN 0,00 BGN 0,00 BGN 0,00 DevelopmentDevelopment of public procurement of public for procurement the purchase for of energythe purchase from a of energy from a BGN 0,00 BGN 0,00 BGN 0,00 BGN 0,00 liberalised marketliberalised market DevelopmentDevelopment of "green" public of "green" procurement public procurement Training and Trainingqualification and qualification DevelopmentDevelopment of a training plan of a for training employees plan and for specialistsemployees and specialists BGN 500,00 BGNBGN 500,00 500,00 BGN BGN500,00 500,00 BGN 500,00 BGN 1.500,00 BGN 1.000,00 BGN 1.500,00 BGN 1.000,00 BGN 0,00 BGN 0,00 BGN 0,00 BGN 0,00 Information andInformation communication and communication DevelopmentDevelopment of a long-term of communication a long-term communication platform platform BGN 0,00 BGN 0,00 BGN 0,00 BGN 0,00

MaintenanceMaintenance and update of andthe Municipalupdate of Energy the Municipal System Energy System BGN 300,00 BGNBGN 300,00 300,00 BGN BGN300,00 300,00 BGN 300,00 BGN 900,00 BGN 600,00 BGN 900,00 BGN 600,00

Conducting anConducting information an campaign information among campaign the residents among the residents BGN 800,00 BGNBGN 800,00 800,00 BGN BGN800,00 800,00 BGN 800,00 BGN 2.400,00 BGN 1.600,00 BGN 2.400,00 BGN 1.600,00 Information daysInformation and events days for and the residentsevents for the residents BGN 0,00 BGN 0,00 BGN 0,00 BGN 0,00 Pre-investmentPre-investment activities activities Conducting energyConducting audits energy audits BGN 10.000,00 BGNBGN 10.000,00 10.000,00 BGNBGN 3.000,00 10.000,00 BGN 3.000,00 BGN 23.000,00 BGN 23.000,00BGN 23.000,00 BGN 23.000,00 Plan for preparationPlan for of preparation energy audits of and energy projects audits and projects BGN 4.000,00 BGN 4.000,00 BGN 4.000,00 BGN 4.000,00 BGN 2.000,00 BGNBGN 2.000,00 2.000,00 BGN 2.000,00 DevelopmentDevelopment of design assignments of design and assignments / or energy andaudits / or energy audits BGN 0,00 BGN 0,00 BGN 0,00 BGN 0,00 Monitoring Monitoring Monitoring planMonitoring for all buildings plan for all buildings BGN 0,00 BGN 0,00 BGN 0,00 BGN 0,00 TOTAL FOR NON-INVESTMENTTOTAL FOR ACTIVITIES: NON-INVESTMENT ACTIVITIES:BGN 11.600,00 BGNBGN 13.600,00 11.600,00 BGNBGN 6.600,00 13.600,00 BGN 6.600,00BGN 0,00 BGN 0,00BGN 0,00BGN 0,00 BGN 0,00BGN 0,00 BGNBGN 0,00 0,00 BGN 0,00 BGN 0,00 BGN 31.800,00 BGN 30.200,00BGN 31.800,00 BGN 30.200,00 TOTAL FOR THE PLAN:TOTAL FOR THE PLAN: BGN 1.682.962,00 BGN 1.553.362,00BGN 1.682.962,00 BGN 1.553.362,00 4 | | 5 FORECAST FOR THE DEVELOPMENT OF PRIMARY ENERGY CONSUMPTION (BY ENERGY SOURCES) AFTER THE IMPLEMENTATION OF THE SCENARIO “ENERGY COSTS AFTER THE IMMPLEMENTATION OF THE PROJECTS WITH NORMALIZED COMFORT DURING THE WHOLE PLANNING PROJECTS PERIOD” Energy costs (BGN)

Real baseline scenario (reduced comfort)

Industrial gas oil Wood Pellets Electric energy Heat energy from heat pump with SCOP>3,5 Normalised baseline scenario (normalised comfort) Scenario “Final energy consumption after the completion of the projects with normalised comfort during the whole planning Primary energy consumption (by energy sources) (MWh) energy sources) consumption (by Primary energy period”

SCENARIO “CO2 EMISSIONS AFTER THE IMPLEMENTATION OF THE PROJECTS WITH NORMALIZED COMFORT DURING THE WHOLE PLANNING PERIOD” FORECAST FOR THE SHARE OF ENERGY FROM RES AFTER THE IMPLEMENATATION OF PROJECTS ) 2 Carbon emissions (tCO

Real baseline scenario (reduced comfort) Share of energy from RES (%) of energy from Share Normalised baseline scenario (normalised comfort)

Scenario “Final energy consumption after the completion of the projects with normalised comfort during the whole Conventional fuels and energy RES planning period”

Note: The energy produced from burning wood is only considered to be RES if the wood is harvested and utilized in a sustainable way, ie. if harvested under the required conditions for forest sanitation and if the wood material does not exceed the appropriate humidity content.

6 | | 7 Etropole Municipal Administration DESCTIPTION CONCLUSIONS OF THE FROM THE BUILDING: ENERGY AUDIT:

The administrative building has The average temperature in the external conditions. There is great hollow brick walls with reinforced building is low, the heating system potential for energy savings if the concrete structure. The hip roof is old, in some places even clogged boiler is replaced with air-to-water is wooden with an attic space. and inefficient, and fails to heat heat pumps or VRV/VRF systems. The roof structure was repaired in the building sufficiently. This The roof of the building can also be 2011. The majority of the windows leads to reduced comfort in the used for energy production, with in the building are wooden, building. To compensate for the the potential to deploy photovoltaic installed during the construction lack of heat, some employees use capacities up to 23.5 kWp. of the building. They are in poor air conditioners in the rooms, as Despite the poor characteristics condition, crooked and with poor well as electric heaters to raise of the building envelope and the aesthetic appearance. In addition the temperature in the rooms. boiler, due to the good shape factor to the wooden windows, the During the summer months, the and the low energy consumption building also has metal windows installed individual split systems of appliances and lighting, the and aluminum doors with thermal are used for cooling. Most of building falls into a class of bridges. There are no effective them are inverter and with energy consumption higher than thermal insulation materials very high seasonal efficiency. the average values ​​for buildings used on the building envelope. The heat transfer coefficients of the without energy saving measures. Etropole Municipal Administration The building is inhabited by 54 walls, roof and floor are much higher The building has an energy employees and has about 7 visitors than the normative ones, which consumption class C and has the BASIC DATA ABOUT on weekdays. It is occupied for shows significant potential for potential for savings up to class A+. 9 hours a day, 5 days a week. The energy savings when implementing THE SITE: heating is managed with local measures on the building envelope. heating installation with a gas The windows and doors are old NAME: Administrative building with 3 above-ground floors and 1 unheated semi- oil boiler without the necessary and crooked and some of them Etropole Municipal Administration basement floor. The building was built in 1967. The structure is monolithic automation to regulate the have single glazing and very with reinforced concrete beams and slabs and brick walls. Figure 1 shows operating mode of the installation high heat transfer coefficients. ADDRESS: a diagram of the building. and the output power, except The air infiltration through Etropole town, 1 “Deveti ” for the possibility to adjust the windows and doors is very high, Str. supply temperature to the building which leads to increased energy TYPE OF BUILDING: installation. There is no possibility costs and severe discomfort. Administrative to regulate the heat transfer from Domestic hot water is heated by the radiators at the local level electric boilers located near the CLIMATE: (thermostatic valves). consumers, thus realising lower heat Moderate continental climate losses in the plumbing system. Due to the low consumption of hot water, GEOMETRIC CHARACTERISTICS: the installation of solar collectors 2 BUA: 518 м2; GFA: 1560 м ; Heated on the roof of the building is not 3 volume: 4428 м recommended, but it is possible to NUMBER OF INHABITANTS: Scheme of the Etropole Municipal Administration install heat pump boilers for DHW. 61 – administrative staff The heat supply is managed with an oil boiler. The heating is used WORKING HOURS: Form factor between 6 and 12 hours a day 9 – 18 on workdays A outside surface / V heated = on weekdays, depending on the Etropole

8 | | 9 BUILDING LOG (IBROAD LOGBOOK) - TECHNICAL CHARACTERISTICS::

ENERGY SAVING MEASURES: ЕSМ В1. Additional thermal insulation of the walls FIRST STEP: ЕSМ В2. To be able to apply for a subsidy programme that is limited in the amount Replacement of windows and doors of the investment, a first step with an investment of up to BGN 250,000 has been developed. ЕSМ В3. Additional thermal insulation of the Energy savings Cash savings roof

ЕSМ В4. Additional thermal insulation of the Step1 Description floor Investment Economic life Electric energy Diesel fuel for heating Electric energy ЕSМ С1. Industrial gas oil and Operation maintenance Total Heat pumps BGN a kWh/a kWh/a kWh/a BGN/a BGN/a BGN/a »»ЕСМ В1 Additional 111 200 25 -134 46 468 -31 10 536 0 »»10 505 ЕSМ С2 . thermal Heat pump boilers for DHW insulation walls »»ЕСМ В2 Replacement 92 500 30 -119 43 995 -28 9 976 0 »»9 948 ЕSМ С3. of windows and Local room ventilation with heat doors recovery »»ЕСМ В3 Additional 35 000 25 -27 19 221 -6 4 358 0 »»4 352 thermal ЕSМ С4. PV plant insulation roof 10 | | 11 Roadmap for building renovation SECOND STEP: (iBroad Roadmap): To provide good working conditions, and especially to ensure thermal comfort, it is necessary to redesign the main heating system in the building. This should be done as a second step, after reducing the energy consumption in the building and should be done as soon as the Municipality can invest BGN 200,000.

Energy savings Cash savings

Step 2 Description Investment Economic life Electric energy Industrial gas oil Electric energy Diesel fuel for heating and Operation maintenance Total

BGN a kWh/a kWh/a BGN/a BGN/a BGN/a BGN/a »»ЕSМ В4 Additional thermal insulation of the floor 25 500 25 -41 12 828 -9 2 909 0 »»2 899

»»ЕSМ C1 Heat pump type VRV/VRF 178 838 10 -9 164 158 839 -2 133 36 016 -1000 »»32 884

THIRD STEP: This step is to improve the indoor air quality - it was set at a later date because the local community has not yet fully realised the importance of installing ventilation in workplaces and homes. However, since the initiation of the first step, the installation of ventilation is planned and therefore the necessary openings are provided. In addition to ventilation, two measures which only lead to a reduction in energy consumption from conventional sources are envisaged.

Energy savings Cash savings

Step 3 Description Investment Economic life Electric energy Industrial gas oil Electric energy Diesel fuel for Diesel fuel for heating and Operation maintenance Total

BGN a kWh/a kWh/a лв./год. BGN/a BGN/a. BGN/a »»ЕSМ C2 Heat pump boilers for DHW 7 500 15 5 951 0 1 385 0 0 »»1 385

»»ЕSМ C3 Local room ventilation with heat recovery 17 640 15 5 441 0 1 266 0 -100 »»1 166

»»ЕSМ C4 PV plant 43 000 23 25 861 0 5 398 0 0 »»5 398

12 | | 13 Comfort and benefits

Besides the financial benefits of implementing the measures - long- term savings and environmental benefits from reducing greenhouse gas emissions, there are also social and health benefits for residents and society. Such health benefits are present in each of the steps, improving sound comfort (step 1), thermal comfort (step 1 and step 2) and indoor air quality (step 3). The social benefit comes from improving the aestetics of the building located in the city center (step 1). Since it is the Municipal Admini- stration building, the focus on improving the air quality in the city is also integral and this is achieved by reducing emissions from the building’s heating process (steps 1 and 2) and the use of green energy (step 3), produced locally. The enhancement of the building’s aestetics and thus the city centre after the reconstruction of the facade of the building is achieved (step 1).

14 | | 15 Additional financial analysis of Interview with Dimitar Dimitrov, the implemented measures Mayor of Etropole Municipality

Cumulative cash flows Mr. Dimitrov, which is the biggest of Etropole worth BGN 6,681,783. the public about the fact that in success of Etropole in the field of The benefits of energy efficiency addition to living comfort and energy efficiency? Are municipal are undeniable. The introduction of reducing energy costs of households, specialists convinced of the this set of measures has a positive energy efficiency has an impact on benefits of energy efficiency -not impact on both energy savings and the environment, air quality and only in terms of financial savings, indoor air quality and living comfort, climate, drastically reducing harmful but also in terms of improving which affects employees’ health and emissions from domestic heating, comfort and living conditions? workability. which we know is one of the biggest In recent years, the municipality Together we have developed a factors for air pollution both in the of Etropole has introduced project for the renovation of the municipality and in the whole country. energy efficiency measures in municipal administration building, Observing the buildings around us, eight buildings of the municipal which is expected to reach energy it is impressive how many people infrastructure (educational, class A. We believe that its have renovated their homes with new sports and cultural) under various implementation will significantly windows, installed thermal insulation European and national programmes. improve the working conditions of and changed their heating systems. Under the Operational Programme This means that these owners have an ГодинаOne year след after първоначална the initial investment инвестиция municipal specialists; however, do “Regional Development” we imple- you think that this project will also opinion on the subject and are aware of Step 1 Step 2 Step 3 mented a project, which was worth affect citizens’ awareness of the the benefits of these basic measures. BGN 822,960, for the renovation of benefits of energy efficiency? The jointly developed plan for Secondary School “Hristo Yassenov” Through the implementation of the renovation of the public building Assuming that the owner’s funds are invested in the building and the individual steps in Etropole, in order to improve its municipal plan for introduction of stock focuses mainly on buildings are implemented over a three-year period, then the cash flows from investments energy efficiency. energy efficiency measures of the of the educational infrastructure. and energy savings, while maintaining the same price of fuel and electricity, would Under the National Green Investment public building stock in the municipality In this regard, do you think that look like this. Scheme from the NTEF, we introduced of Etropole the ecological indicators in such projects affect the quality of energy saving measures worth a total the municipality will be improved and public services in general and the of BGN 1,781,172 in seven more the living standard and the quality of satisfaction of citizens with them? buildings. These are: life of the citizens will be increased. In the municipality of Etropole, caring »»Kindergarten “Sun” It is very important to inform for the younger generation is a top »»Kindergarten “Edelweiss” »»Kindergarten “Bell” »»Kindergarten “Patilantsi” »»Community centre “Todor Peev 1871” »»Sports hall “Stoyan Nikolov” »»Dormitory of the Vocational High School, Etropole. Under the National Program for Energy Efficiency of Multifamily Residential Buildings, we introduced energy saving measures in 8 blocks in the town Etropole 16 | | 17 Etropole priority. That is why it is important infrastructure - not only in the field »»“Maksim Gorki” Str. to provide a good environment for of energy efficiency, but also in the »»“Opylchenska” Str. the development of the potential wider context? of the children and young people In connection with increasing the energy »»“Deveti Septemvri” Str. and their growth as educated and efficiency of the municipal building »»“” Str.. confident citizens who will stay to stock, we have submitted projects for Correction in certain sections of live and grow in our municipality. the implementation of energy saving »» the bed of the River, In my opinion, good working conditions measures in four municipal buildings. Etropole. and a pleasant working environment These are the buildings of Hristo affect employee productivity. They Botev Primary School in Etropole, an put more effort into their work and additional building of Hristo Botev are more efficient and motivated, Primary School in Etropole, Todor Peev which respectively affects the overall Vocational High School in Etropole, satisfaction of the services provided. and a two-storey administrative What support is needed for the building in the city centre. Funding OUR BUILDINGS municipality to implement more is expected for these projects. ambitious projects, apart from In 2021 we will implement key Long-term Strategies for the financial one? Is there a need infrastructure projects for the Deep Energy Retro tting for expert technical assistance municipality of Etropole. These are: or support to develop investment »»Reconstruction and modernization plans? of the Municipal Market - Etropole I have the pleasure to work with a good and motivated team of experts »»Complete rehabilitation of 8 and specialists. Thanks to their streets in the town of Etropole: professionalism, I think the results are »»“Todor Peev” Str. present. We will continue to work with »»“” Str. BPIE the same energy. Could you tell us more about the »»“Moskovska” Str. new projects and ambitions of the »»“Grigor Mihaylov” Str. municipality to improve public

18 | | 19 Deep Ener L OUR BUILDINGS ong-term Strategiesf Etropole gy Retro tting

WWW.ENEFFECT.COM Strategy and pilot projects for renovation of the municipal building stock BPIE WWW.EUKI.DE WWW.BPIE.EU WWW.OER.RO or

Conservation and NuclearSafety(BMU). Nature Environment, the for Ministry Federal the of views the reflect necessarily not do put forwardopinions The this publication in areresponsibilitythe sole oftheauthor(s)and in order tomitigate greenhouse gasemissions. climateoverarchingto foster cooperationthe EUKI goalof Europeanthe (EU) within Union the IIt is GmbH. (GIZ) für Internationalethe DeutscheGesellschaft Zusammenarbeit byimplemented projectfor is competition EUKI ideas The (BMU). Safety Nuclear and byinstrument Federal theGerman fortheEnvironment, Ministry NatureConservation financing project a is EUKI (EUKI). Initiative Climate European the of part is project This containedinthispublication. EASME isresponsible theuseofalloranypartinformation for nor EU the Neither Union. European the of opinion the reflect necessarily not does It authors. the with lies publication the roadthe developmentof building renovation.used for wasfor maps this responsibilitythe contentof sole for The EU, the of program 2020 Horizon the by funded project, iBROAD the under developed English, in software Specialised Energy© Centerfor EfficiencyEnEffect,,2021 Graphic RalitsaYordanova design:arch. Genchev Simeonov, eng. Borislav Ivanov, TeodoraPavel Stanisheva, Manchev,arch. Zdravko Dr. DragomirAuthors: Dr. Tzanev, Stankov, eng.Aleksander Kamen Manolova, eng. Maria Dr.