From: Hamill, Carol L [[email protected]] Sent: Thursday, June 02, 2011 11:37 AM To: Epperson, Dan; Poole, Justin; Raghavan, Rags; Milano, Patrick; Campbell, Stephen Cc: Crouch, William D Subject: Presentation package_Part 1 of 2 Attachments: image001.jpg; Presentation package_Part 1 of 2.pdf - Adobe Acrobat Professional.pdf
Gentlemen, Bill Crouch asked me to divide the presentation package into 2 smaller documents and send them to you separately, so you will have the complete presentation.
Attached is Part 1 of 2, pages 1-14.
Carol L. Hamill
Licensing/Quality Assurance WBN Unit 2 Project, EQB 1B‐ WBN 423‐365‐3177 423‐365‐3833 [email protected]
1 Hearing Identifier: Watts_Bar_2_Operating_LA_Public Email Number: 409
Mail Envelope Properties (25547F570B005144A141ECCA95DA1AB212053950)
Subject: Presentation package_Part 1 of 2 Sent Date: 6/2/2011 11:36:31 AM Received Date: 6/2/2011 11:37:53 AM From: Hamill, Carol L
Created By: [email protected]
Recipients: "Crouch, William D"
Post Office: TVACOCXVS2.main.tva.gov
Files Size Date & Time MESSAGE 384 6/2/2011 11:37:53 AM image001.jpg 1023 Presentation package_Part 1 of 2.pdf - Adobe Acrobat Professional.pdf 4138337
Options Priority: Standard Return Notification: No Reply Requested: Yes Sensitivity: Normal Expiration Date: Recipients Received:
Page 1 of 1
file://c:\EMailCapture\Watts_Bar_2_Operating_LA_Public\409\attch1.jpg 6/16/2011 PART 1 OF 2
ENCLOSURE 1
PRESENTATION PACKAGE “TEMPORARY DAMS’ MODIFICATION PROJECT” Temporary Dams’ Modification Project
PtdtPresentedto The Nuclear Regulatory Commission
Tennessee Valley Authority Riv er Operations
Knoxville, TN May 11, 2011 Temporary Dams’ Modification Project Affected Dams Z Cherokee Z Tellico Z Fort Loudoun Z Watts Bar
Z Modifications of the Dams consisted of: Raising the Embankment Dams by Using HESCO Sand Baskets
2 Temporary Dams’ Modifications (R1) Husein Hasan/TVA Temporary Dams’ Modification Project
Geotextile A heavy-duty, non-woven, permeable, polypropylene fabric Welded Wire Mesh,,, coil, and p ins Alu-Zinc coated Steel, wire diameter of 0.16 inch. With spacing of 3" xx3 3"
Size: 3’X3’X3’ or 3’X3’X4’ Capacity : 1.6 – 2.2 tons
Temporary Dams’ Modifications (R1) 3 Husein Hasan/TVA Temporary Dams’ Modification Project
Temporary Dams’ Modifications (R0) 4 Husein Hasan/TVA Temporary Dams’ Modification Project Cherokee Dam
6783 feet
Temporary Dams’ Modifications (R0) 5 Husein Hasan/TVA Temporary Dams’ Modification Project Cherokee Dam Embankment
Temporary Dams’ Modifications (R0) 6 Husein Hasan/TVA Temporary Dams’ Modification Project
Cherokee Dam Z Dam's length raised by 3'= 6783 feet Z HESCO baskets used = 2261; Size (3’X3’X3’) Z Sand used = 8.2 million pounds
Temporary Dams’ Modifications (R0) 7 Husein Hasan/TVA Temporary Dams’ Modification Project
Tellico Dam
Saddle Dam #2
Saddle Dam #3 6011 feet
Tellico Dam
Temporary Dams’ Modifications (R1) 8 Husein Hasan/TVA Temporary Dams’ Modification Project
Tellico Dam Embankment
Tellico Pedestrian Walkway Temporary Dams’ Modifications (R0) 9 Husein Hasan/TVA Temporary Dams’ Modification Project Tellico Dam – Saddle Dams
Saddle Dam #2 (525 feet)
Saddle Dam #3 (291 feet)
Temporary Dams’ Modifications (R0) 10 Husein Hasan/TVA Temporary Dams’ Modification Project Affected Dams Z Cherokee Z Tellico Z Fort Loudoun Z Watts Bar
Z Modifications of the Dams consisted of: Raising the Embankment Dams by Using HESCO Sand Baskets
2 Temporary Dams’ Modifications (R1) Husein Hasan/TVA Temporary Dams’ Modification Project
Geotextile A heavy-duty, non-woven, permeable, polypropylene fabric Welded Wire Mesh,,, coil, and p ins Alu-Zinc coated Steel, wire diameter of 0.16 inch. With spacing of 3" xx3 3"
Size: 3’X3’X3’ or 3’X3’X4’ Capacity : 1.6 – 2.2 tons
Temporary Dams’ Modifications (R1) 3 Husein Hasan/TVA Temporary Dams’ Modification Project
Temporary Dams’ Modifications (R0) 4 Husein Hasan/TVA Temporary Dams’ Modification Project Cherokee Dam
6783 feet
Temporary Dams’ Modifications (R0) 5 Husein Hasan/TVA Temporary Dams’ Modification Project Cherokee Dam Embankment
Temporary Dams’ Modifications (R0) 6 Husein Hasan/TVA Temporary Dams’ Modification Project
Cherokee Dam Z Dam's length raised by 3'= 6783 feet Z HESCO baskets used = 2261; Size (3’X3’X3’) Z Sand used = 8.2 million pounds
Temporary Dams’ Modifications (R0) 7 Husein Hasan/TVA Temporary Dams’ Modification Project
Tellico Dam
Saddle Dam #2
Saddle Dam #3 6011 feet
Tellico Dam
Temporary Dams’ Modifications (R1) 8 Husein Hasan/TVA Temporary Dams’ Modification Project
Tellico Dam Embankment
Tellico Pedestrian Walkway Temporary Dams’ Modifications (R0) 9 Husein Hasan/TVA Temporary Dams’ Modification Project Tellico Dam – Saddle Dams
Saddle Dam #2 (525 feet)
Saddle Dam #3 (291 feet)
Temporary Dams’ Modifications (R0) 10 Husein Hasan/TVA Temporary Dams’ Modification Project
Tellico Dam Z Dam's length raised by 4' = 6011 feet Z HESCO baskets used = 1993;;( Size (3’X3’X4’ ) Z Sand used = 10.8 million pounds
Temporary Dams’ Modifications (R0) 11 Husein Hasan/TVA Temporary Dams’ Modification Project
Tellico Dam Z Dam's length raised by 4' = 6011 feet Z HESCO baskets used = 1993;;( Size (3’X3’X4’ ) Z Sand used = 10.8 million pounds
Temporary Dams’ Modifications (R0) 11 Husein Hasan/TVA Temporary Dams’ Modification Project Fort Loudoun Dam Embankment
3785 feet
Temporary Dams’ Modifications (R0) 12 Husein Hasan/TVA Temporary Dams’ Modification Project Fort Loudoun Dam Embankment
Temporary Dams’ Modifications (R0) 13 Husein Hasan/TVA Temporary Dams’ Modification Project Fort Loudoun Dam Embankment
Temporary Dams’ Modifications (R0) 14 Husein Hasan/TVA