GENERAL NOTES

OFFSET WHERE REQUIRED TO ALLOW CLEARANCE OF DUCTS, ELECTRICAL CONDUIT, OUTLET BOXES, BEAMS, ETC. TO AVOID INTERFERENCE WITH THE WORK OF OTHER TRADES. TO INCREASE HEAD UNDER PIPING OR TO IMPROVE THE APPEARANCE OF PIPE WORK, THIS CONTRACTOR SHALL OFFSET ANY PIPING AS DIRECTED BY THE ARCHITECT/ENGINEER AND SHALL PROPERLY DRAIN OF VENT SAME WHERE NECESSARY. MAKE ALLOWANCES IN THE

BID THERETO. 02/04/2020

THIS CONTRACTOR SHALL FIELD VERIFY LOCATIONS FOR ALL DUCTWORK AND PIPING FOR DATE THE INSTALLATION PRIOR TO FABRICATION.

THIS CONTRACTOR SHALL COORDINATE HIS WORK WITH THE OTHER CONTRACTORS ON THE PROJECT AND INSTALL MECHANICAL SYSTEMS IN A MANNER WHICH WILL CONFORM TO STRUCTURE, KEEP PASSAGEWAYS AND OPENINGS CLEAR, PRESERVE HEAD ROOM, CLEAR LIGHT FIXTURES AND NOT COVER UP JUNCTION BOXES. THIS CONTRACTOR SHALL MAKE OFFSETS BKB RJA 19590 IN PIPING OR DUCTWORK TO AVOID INTERFERENCE WITH OTHER TRADES, AT NO ADDITIONAL COST TO THE OWNER, WHEN SO DIRECTED BY THE ARCHITECT/ENGINEER.

WHERE PIPING IS CONNECTED TO EQUIPMENT OR FIXTURES THAT ARE BEING REPLACEMENT REMOVED, THE PIPING SHALL BE REMOVED COMPLETELY (UNLESS NOTED OTHERWISE) FROM THE REMODELED SPACE AND CAPPED AT OR NEAR THE MAINS. PLUMBING PIPING THAT IS LOCATED IN A TO BE REMOVED SHALL BE REMOVED (IF NOT ACTIVE) AND CAPPED AT NORTH DAKOTA DEPARTMENT OF TRANSPORTATION THE MAIN LINE OR OUT OF THE REMODELED SPACE.

BISMARCK, NORTH DAKOTA PIPING & STANDARD

ACCESSORY LEGEND ABBREVIATIONS DRAWN BY BY CHECKED JOBNO.

BALL VALVE AD - ACCESS AFF - ABOVE FINISHED BALL VALVE INDICATOR AFG - ABOVE FINISHED GRADE DESIGN TEAM DRAWING SHEETS BUTTERFLY VALVE ATC - AUTOMATIC TEMPERATURE

GATE VALVE CONTROLS BDD - BACKDRAFT PRAIRIE ENGINEERING, P.C. T1.0 - TITLE SHEET VENTURI BFF - BELOW FINISHED FLOOR CHECK VALVE CA - COMBUSTION AIR CO - CLEAN OUT MECHANICAL ENGINEERS 2-WAY CONTROL VALVE EC - ELECTRICAL CONTRACTOR BISMARCK, NORTH DAKOTA M1.0 - MECHANICAL SITE PLAN 3-WAY CONTROL VALVE FA - FRESH AIR FCO - FLOOR CLEAN OUT DRAIN VALVE 701 -258 -3493 M2.0 - MECHANICAL DEMOLITION PLAN FD - FLOOR DRAIN M3.0 - MECHANICAL REMODEL LAN STRAINER FDR - UNION FPH - FREEZE -PROOF HYDRANT PRAIRIE ENGINEERING, P.C. M4.0 - MECHANICAL DETAILS & SCHEDULES GC - GENERAL CONTRACTOR FLANGE GRD - /REGISTER/DIFFUSER ELECTRICAL ENGINEERS MC - MECHANICAL CONTRACTOR BISMARCK, NORTH DAKOTA E1.0 - SCHEDULES & DETAILS MANUAL AIR VENT OB - PLUMBING OUTLET BOX OBD - OPPOSED BLADE DAMPER 701 -258 -3493 E2.0 - EXISTING CONDITIONS AUTO AIR VENT PRV - POWER VENTILATOR RA - RETURN AIR

TEMPERATURE GAUGE RD - ROOF DRAIN SA - SUPPLY AIR Engineering P.C. Engineers Consulting Professional

SAN - SANITARY Prairie PRESSURE GAUGE SFD - SMOKE/FIRE DAMPER VD - VOLUME DAMPER SENSOR VT - VENT VTR - VENT THROUGH ROOF W - WASTE WCO - WALL CLEAN OUT WH - WALL HYDRANT PIPING LEGEND

VENT HWS HOT WATER HTG SUPPLY HWR HOT WATER HTG RETURN FOS FUEL OIL SUPPLY HVAC LEGEND FOR FUEL OIL RETURN COND CONDENSATE DRAIN POSITIVE PRESSURE CWS SUPPLY NEGATIVE PRESSURE DUCT CWR CHILLED WATER RETURN G NATURAL GAS MANUAL DAMPER

MOTORIZED DAMPER

BACK DRAFT DAMPER NORTH DAKOTA DEPARTMENT OF TRANSPORTATION ACCESS DOOR

BOILER REPLACEMENT PROJECT ELBOW WITH 608 EAST BOULEVARD AVENUE TURNING VANES HI -EFFICENCY TAKEOFF BISMARCK, NORTH DAKOTA 58505 (W/ VOLUME DAMPER) Bismarck,Dakota North State of North North Dakota of State Department of Transportation Boiler Replacement ofDepartment Transportation

THIS DOCUMENT WAS

ORIGINALLY ISSUED AND Sheet Title Project SEALED BY RANDY J. AXVIG REGISTRATION NUMBER 3606, ON FEBRUARY 4, 2020, SHEET AND IS STORED AT THE OFFICE OF PRAIRIE ENGINEERING, P.C. T1.0 EXISTING UNDERGROUND ELECTRICAL CONDUIT CONCRETE SIDEWALK

WITH CURB 02/04/2020 DATE

EXISTING CONCRETE LIGHT STANDARD. FIELD VERIFY ACTUAL LOCATION WITH EXCAVATION AREA. ADJUST EXCAVATION AREA ASPHALT PARKING LOT SO LIGHT STANDARD IS NOT DISTURBED. BKB RJA 19590

35' - 0"

D3 TANK REMOVAL CONSTRUCTION BOUNDARY ASPHALT, CONCRETE, AND CURB REMOVAL BY M.C. VT

20' - 0" DRAWN BY BY CHECKED JOBNO. TANK ORIENTATION IS SHOWN BASED ON ORIGINAL D1 CONSTRUCTION DRAWINGS. FIELD VERIFY TANK ORIENTATION PRIOR TO EXCAVATION.

D2 FIELD VERIFY LOCATION OF CONDUIT AND DISCONNECT/RECONNECT ELECTRICAL FOR EXCAVATION EXCAVATION, TANK REMOVAL, & BACKFILL BY M.C.

EXISTING UNDERGROUND ELECTRICAL CONDUIT Engineering P.C. Engineers Consulting Professional Prairie

D2

DN

KEYNOTE LEGEND Bismarck,Dakota North

D1 REMOVE UNDERGROUND FUEL OIL TANK COMPLETELY. State of North North Dakota of State FUEL OIL WILL BE EMPTIED BY OWNER. D2 FLUSH UNDERGROUND FUEL OIL SUPPLY AND RETURN PIPES AND PERMANENTLY CAP PIPES AT BOTH ENDS.

ABANDON PIPES IN PLACE. Boiler Replacement ofDepartment Transportation D3 REMOVE UNDERGROUND FUEL OIL TANK VENT PIPE COMPLETELY. THE ABOVE GROUND PORTION OF PIPE IS INSIDE AN OLD LIGHT POLE. REMOVE VENT PIPE AND UP LIGHT POLE.

THIS DOCUMENT WAS ORIGINALLY ISSUED AND SEALED BY RANDY J. AXVIG REGISTRATION NUMBER

3606, ON FEBRUARY 4, 2020, Plan Site Mechanical AND IS STORED AT THE 1 OFFICE OF PRAIRIE Mechanical Site Demolition Plan ENGINEERING, P.C.

3/32" = 1'-0" N SHEET M1.0 0' 5'-4" 10'-8" 16' 21'-4" M1.0 SCALE: 3/32'' = 1'-0'' 02/04/2020 DATE BKB RJA 19590

REMOVE FUEL OIL GAUGE

EXISTING MCC 1 1/4" FOR HWS EXISTING ATC PANEL 1" FOS HWR D2 D2 DN D13 DRAWN BY BY CHECKED JOBNO. G

D12

G D6 EXISTING BOILER HWR CAP AT TEE D5 D4 STACK TO REMAIN HWS D12 HWS REMOVE REGULATOR D7 HWR REMOVE VALVE AND CAP AT TEE G

G G G D10 D12

EXISTING G HWS D7 D9 D8 D6 D6 BOILER #1 D15 D8 2" EXISTING SUMP DISCHARGE TO REMAIN HWR D5 HWR HWS 6" HWR HWR BOILER #2 HWS D8 5" D8 D14 D9

HWR HWR D11 D8 1/2" GAS VENT PIPES TO REMAIN

HWR HWR HWR

D13 Engineering P.C. Engineers Consulting Professional D11 Prairie D10 D8 HWR EXISTING CONCRETE EXISTING CONCRETE PAD TO REMAIN PAD TO REMAIN D8 D8 EXISTING CONCRETE G PAD TO REMAIN

EXISTING HWS AHU -6 HWS HWS HWR M.C. SHALL DRAIN THE HOT SYSTEM HWS CW IN THE OR BACK TO LOCATED OUTSIDE HW THE BOILER ROOM. M.C. SHALL REFILL SYSTEM BASED ON THE REMOVE HWS PIPING TO VALVES

AMOUNT OF WATER REMOVED AND SHALL REMOVE ALL AIR CW FROM THE SYSTEM AND ENSURE PIPING SYSTEMS ARE NOT CW HWR AIR LOCKED. M.C. SHALL PROVIDE THE NECESSARY LEVEL OF CORROSION INHIBITOR IN THE SYSTEM. EXISTING PUMP TO REMAIN

EXISTING PUMP TO REMAIN HWS HWS CW

1 Mechanical Demolition Plan

M2.0 1/4" = 1'-0" N Bismarck,Dakota North State of North North Dakota of State

KEYNOTE LEGEND Department of Transportation Boiler Replacement ofDepartment Transportation D2 FLUSH UNDERGROUND FUEL OIL SUPPLY AND RETURN PIPES AND PERMANENTLY CAP PIPES AT BOTH ENDS. ABANDON PIPES IN PLACE. D4 REMOVE ALL FUEL OIL PIPING ABOVE FLOOR. PERMANENTLY CAP FUEL OIL PIPING BELOW FLOOR UNDER ACCESS DOOR. D5 REMOVE FUEL OIL DAY TANK, PUMPS, AND PIPING. FUEL OIL WILL BE EMPTIED BY OWNER. COORDINATE WITH OWNER TO SCHEDULE REMOVAL OF TANK AND PUMPS. D6 REMOVE BOILER COMPLETELY. D7 REMOVE BOILER VENTING TO LOCATION SHOWN AND TEMPORARILY CAP. D8 REMOVE HWS/HWR PIPING TO LOCATION SHOWN. D9 REMOVE HWR VALVES AND TEMPORARILY CAP PIPE. D10 REMOVE BOILER RELIEF PIPE AND RELIEF VALVE. D11 REMOVE GAS VENT PIPING TO LOCATION SHOWN AND TEMPORARILY CAP. D12 REMOVE GAS PIPE TO LOCATION SHOWN. D13 REMOVE EMERGENCY BOILER SHUT DOWN SWITCHES. D14 REMOVE THREE-WAY VALVE. D15 REMOVE AIR SEPARATOR.

THIS DOCUMENT WAS ORIGINALLY ISSUED AND SEALED BY RANDY J. AXVIG REGISTRATION NUMBER

3606, ON FEBRUARY 4, 2020, Plan Demolition Mechanical AND IS STORED AT THE OFFICE OF PRAIRIE ENGINEERING, P.C. SHEET 0'2' 4' 6' 8' M2.0 SCALE: 1/4'' = 1'-0'' 02/04/2020

SEE DETAIL 3/M3.0 DATE

Penthouse Roof 88' - 0" BKB RJA 19590

EXISTING MCC HWS EXISTING ATC PANEL Roof

HWR 74' - 0" ALTERNATE 1 BOILER AND PUMP, IF ACCEPTED, DN B-4A SHALL BE INSTALLED WHERE B-4 & P-4 ARE SHOWN EMERGENCY BOILER SHUT -DOWN SWITCH INSULATE SINGLE WALL M5

EXPOSED IN BOILER ROOM DRAWN BY BY CHECKED JOBNO. G

1 1/4" NEW BOILER VENTS UP THROUGH HWS EXISTING BOILER STACK. P-4A HWR Fourth Floor HX -1 EXISTING BOILER M1 M2 60' - 0" G STACK TO REMAIN P-5 G 2" 2" M3 HWS 8"ø G NEW ACCESS OPENING HWS G ET -2 HWS EXISTING REGULATOR B-4 TO REMAIN 1 1/4" B-1 SEE DETAIL 2/M4.0 HWR COVER WITH 1/2" SCREEN HWR G G 2 P-1 M3.0 1" HWS/HWR 1 1/4" EXISTING 3" HWR EXISTING 1 1/2" G 8"ø CHILLER G 8"ø CONNECT TO EXISTING 26"x12" 3" M5 1 1/2" Third Floor HWR 2" EXISTING ELEVATOR SUMP DISCHARGE TO REMAIN HWR 46' - 0" HWS HWR HWS B-2 6" HWR HWR 4" HWS 3" EXISTING 3" HWS P-2 3/4" NEW VALVE 5" CONNECT TO EXISTING P-4 G G G G G BC -1 1 1/4"

HWR 3/4" GAS VENT PIPES TO REMAIN B-3

EMERGENCY BOILER HWR HWR HWS M4

5" HWR SHUT -DOWN SWITCH G P-3 Second Floor

HWS Engineering P.C. Engineers Consulting Professional G

32' - 0" Prairie HWR CARBON MONOXIDE DETECTOR 3/4" 4" 6" HWR 5" HWR

4" G HWR HWS

ET -1 CW 3" 1" CW DN 1" EXISTING 6" SEE DETAIL 1/M4.0 HWR 26"x12" AHU -6 AIR SEPARATOR WITH AUTO AIR VENT HWR Ground Floor

M6 HWS HWS CW 18' - 0" HW CONNECT TO EXISTING G

HWS 1 1/4" SEE DETAIL 4/M3.0 26"x12" AS A PART OF THIS PROJECT, ALL EXISTING HOT WATER 6" 3/4" CW HEATING PIPING IN THE BOILER ROOM SHALL BE RE -LABLED. PIPES LABELED " SUPPLY" SHALL BE RE -LABELED "HWS" AND PIPES LABELED "HEAT PUMP RETURN" SHALL BE RE -LABELED "HWR" CONNECT TO EXISTING ACCORDING TO SPECIFICATION SECTION 230510. DUCTWORK FLOOR

HWS Boiler Room Floor

HWS 0' - 0"

1 Mechanical Remodel Plan 2 Section 1

M3.0 1/4" = 1'-0" N M3.0 1/8" = 1'-0" Bismarck,Dakota North

NEW BOILER FLUES State of North Dakota of State

KEYNOTE LEGEND Department of Transportation Boiler Replacement ofDepartment Transportation EXISTING BOILER STACK M1 DOUBLE WALL BOILER VENT PER MANUFACTURER INSTRUCTIONS. 21" I.D. WITH 2" CONCRETE WALL M2 SINGLE WALL BOILER VENT PER MANUFACTURER INSTRUCTIONS. WITH STAINLESS STEEL WRAP EXIT CONES M3 CONNECT TO EXISTING GAS PIPE. MAXIMUM HEIGHT OF NEW ACCESS OPENING TO M4 CONNECT TO EXISTING GAS VENT PIPES. 8"Ø M5 PROVIDE AND INSTALL 300 KW BOILER UNDER BASE BID. PROVIDE AND INSTALL 480 KW BOILER UNDER ALTERNATE 1. SEAL PENETRATIONS M6 PROVIDE AND INSTALL . REMOVE EXISTING EXPANSION TANK IN PENTHOUSE MECHANICAL ROOM WEATHERTIGHT 8"Ø PITCH DOWN 6" REMOVE RAIN CAP AND INSTALL NEW EXPANSION TANK IN SAME LOCATION AND CONNECT TO EXISTING PIPING AS REQUIRED. 1" PER FOOT EXISTING ACCESS DOOR EXPANSION TANK SHOWN IN THIS LOCATION FOR CLARITY. M.C. SHALL CUT NEW 30"x18" ACCESS OPENING OFFSET 8"Ø NEW FLASHING 45 DEGREES FROM EXISTING ACCESS DOOR. 0" - PROVIDE AND INSTALL 4"x4"x3/8" ANGLE STEEL FRAME 6' 0"

- INSIDE OPENING. COVER WITH 3/16" FLAT PLATE STEEL 5' 0"

- COVER BOLTED TO FRAME WITH GASKET SEALED WEATHERTIGHT. REMOVE FLASHING 4' BOILER ROOM WALL CONCRETE BASE

SUPPORTS* EXISTING ROOF CURB BASEMENT FLOOR ROOF ROOF

EXISTING BOILER STACK EXISTING BOILER STACK

* SUPPORT NEW BOILER FLUES FROM EXISTING USING STAINLESS BOILER ROOM FLOOR STEEL CABLE AND CLAMPING COLLARS OR OTHER APPROVED METHODS SUGGESTED BY M.C. OR VENTING MANUFACTURER. THIS DOCUMENT WAS ORIGINALLY ISSUED AND EXISTING CONDITIONS NEW INSTALLATION SEALED BY RANDY J. AXVIG REGISTRATION NUMBER

3606, ON FEBRUARY 4, 2020, Plan Remodel Mechanical 3 Boiler Vent Roof Detail 4 Boiler Stack/Vent Detail AND IS STORED AT THE M3.0 NTS M3.0 NTS OFFICE OF PRAIRIE ENGINEERING, P.C. SHEET 0'2' 4' 6' 8' M3.0 SCALE: 1/4'' = 1'-0'' 02/04/2020 DATE

6" HWR 12" MIN. 4" 5" BKB RJA HWR HWR 19590

4" 5" 5" HWS HWS HWS CONNECTIONS FOR SYSTEM 4" FLUSHING BY OWNER 6" B & G R -6F AIR SEPARATOR WITH AUTO AIR VENT

HWR HWS

2" HWS 2" HWS TO SYSTEM PUMPS 3" 3" 3" PRESSURE/TEMP. GAUGE CW 6"

FURNISHED WITH BOILER, 1" DRAWN BY BY CHECKED JOBNO. THERMOMETER 3/4" INSTALLED BY M.C. BY -PASS BALANCING VALVE (TYP) (NORMALLY CLOSED) LWCO WITH MANUAL RESET INTEGRAL TO BOILER 235000 - ELECTRIC BOILER SCHEDULE 65 PSI RELIEF VALVE FURNISHED PRESSURE WITH BOILER, INSTALLED BY M.C. SCHEDULE NOTES FLOW INDICATOR SEE PLAN FOR HIGH LIMIT WITH GAUGE 2" CONTINUATION AUTOMATIC RESET BY MC 2" 2" 2" 1. PROVIDE LWCO, FLOW SWITCH, PRESSURE/TEMP GAUGE, ELECTRICAL DISCONNECT G G G 2. PROVIDE 65 PSIG ASME RELIEF VALVE HIGH LIMIT WITH 1 1/4" 1 1/4" 1 1/4" 1/4" P-1 P-2 P-3 MANUAL RESET BY MC 3. INCLUDE CONTROLS TO OPERATE BOILER PUMP AND FOR BAS CONNECTION

GAS SHUTOFF VALVE CW TO FLOOR 4. BOILER ELECTRIC PANEL SHALL BE REMOVED FOR ENTRY INTO BUILDING FLOW SWITCH FURNISHED

G G G CW DRAIN WITH BOILER, INSTALLED BY M.C. 6" DIRT LEG 1" ELECTRICAL 65 PSI RELIEF VALVE FURNISHED B-2 B-3 1/4" GAS PILOT TUBE 1" 12 PSI PRESSURE MARK MANUFACTURER MODEL KW STEPS NOTES WITH BOILER, INSTALLED BY M.C. 3/4" GAS Volt Ph Hz B-1 REDUCING VALVE P-4 VENT BACKFLOW B-4 LATTNER 270-LW-480-8 270 8 480 3 60 1, 2, 3, 4 8" COMBUSTION AIR. TERMINATE WITH PIPE TO FLOOR 8" PREVENTER ELBOW AND SCREEN 12" ABOVE BOILER. B-4A LATTNER 480-LW-480-10 480 10 480 3 60 1, 2, 3, 4, ALTERNATE 1 SAFE -T-VENT WITH BOOT TEE B-4 CONDENSATE DRAINS 5/8" TUBING. UNDER ALTERNATE 1, BOILER PIPING SEE MANUFACTURER'S IS THE SAME UNISTRUT 232100 - EXPANSION TANK SCHEDULE 1" BOILER DRAIN INSTALLATION INSTRUCTIONS. TO FLOOR STAND BY M.C. DRAIN 1" TO FLOOR 1" TO FLOOR 1" TO FLOOR MARK MANUFACTURER MODEL FILL PRES. FINAL PRES. ACCEPT. VOL. TANK VOL. TRENCH TRENCH TRENCH ET-1 AMTROL AX-260V 8.00 psi 15.00 psi 56 gal 158.5 gal COND COND COND ET-2 AMTROL AX-15 12.00 psi 20.00 psi 2.4 gal 8 gal Engineering P.C. Engineers Consulting Professional

CONDENSATE NEUTRALIZER CONDENSATE NEUTRALIZER CONDENSATE NEUTRALIZER FILTER/FEEDER Prairie EXISTING CONCRETE PAD COMBO UNIT EXISTING CONCRETE PAD 238000 - BLOWER COIL SCHEDULE ELECTRICAL MARK MANUFACTURER MODEL CFM ESP MOTOR MCA VOLT Ph Hz BC-1 DAIKIN BCHD0201 1,800 0.25 in-wg 0.75 hp 19.80 120 1 60 1 Boiler Piping Schematic M4.0 NTS 232200 - PUMP SCHEDULE

FT of MOTOR INFORMATION MARK MANUFACTURER MODEL TYPE GPM NPSH HD BHP HP VOLTS Ph Hz NOTES P-1 B & G e-80 INLINE 125 20 4.63 0.91 1.50 480 3 60 P-2 B & G e-80 INLINE 125 20 4.63 0.91 1.50 480 3 60 P-3 B & G e-80 INLINE 125 20 4.63 0.91 1.50 480 3 60 P-4 B & G e-80 INLINE 93 20 4.62 0.74 1.00 480 3 60 P-4A B & G e-80 INLINE 165 20 5.70 1.17 1.50 480 3 60 ALTERNATE 1 P-5 B & G PL-36 CIRCULATOR 6 20 0.10 0.17 120 1 60

BLOWER COIL 238000 - BLOWER COIL HW COIL SECTION SCHEDULE BC -1 HEATING COIL AIR SIDE WATER SIDE EQUIP CAPACITY ROWS FINS/INCH CFM EAT LAT FLUID FLOW WPD EWT LWT BC-1 177,287 Btu/h 2 16 1,800 -30 °F 60 °F 50% E.G. 6 GPM 4.47 ftH2O 170 °F 102 °F HWR

235700 - HYDRONIC FLUID SCHEDULE HWS

SURFACE LOAD SIDE HYDRONIC CHARACTERISTICS SOURCE SIDE HYDRONIC CHARACTERISTICS 30 PSI RELIEF MARK MANUFACTURER MODEL TYPE PIPED TO FLOOR AREA FLUID FLOW EWT LWT PD FLUID FLOW EWT LWT PD HWS SENSOR BY ATC HX-1 B & G BP405-50 BRAZED PLATE 13.87 SF 50% E.G. 6 GPM 102 °F 170 °F 2.33 ftH2O WATER 10.4 GPM 180 °F 145 °F 4.66 ftH2O 1 1/4" Bismarck,Dakota North

HWS HWS North Dakota of State 235000 - GAS BOILER SCHEDULE 1" HX -1 SCHEDULE NOTES: Department of Transportation Boiler Replacement ofDepartment Transportation HWR HWR 1. PROVIDE TESTABLE LWCO, FLOW SWITCH, COMBINATION PRESSURE/TEMP GAUGE, 65# ASME RELIEF VALVE P-5 1 " 1 1/4" 2. BOILER CONTROLLER SHALL HAVE CAPACITY TO OPERATE BOILER PUMP AND PROVIDE FOR CONNECTION TO BAS BVI 6.0 GPM 3/4" FILL BVI 10.4 GPM GAS ELECTRICAL CONTROL VALVE EXPANSION MARK MANUFACTURER MODEL TYPE FUEL INPUT OUTPUT DESIGN FLOW PRESSURE VOLT Ph Hz BY ATC TANK ET -2 THREADED HOSE CONNECTION. B-1 THERMAL SOLUTIONS EVS 1500 HIGH EFFICIENCY NON-CONDENSING NATURAL GAS 5 PSI Max. 1,500,000 Btu/h 1,251,000 Btu/h 125 GPM 120 1 60 M.C. SHALL FILL WITH 50% GLYCOL B-2 THERMAL SOLUTIONS EVS 1500 HIGH EFFICIENCY NON-CONDENSING NATURAL GAS 5 PSI Max. 1,500,000 Btu/h 1,251,000 Btu/h 125 GPM 120 1 60 SOLUTION AS SPECIFIED. B-3 THERMAL SOLUTIONS EVS 1500 HIGH EFFICIENCY NON-CONDENSING NATURAL GAS 5 PSI Max. 1,500,000 Btu/h 1,251,000 Btu/h 125 GPM 120 1 60

2 Heat Exchanger Piping Detail M4.0 NTS

THIS DOCUMENT WAS

ORIGINALLY ISSUED AND Schedules and Details Mechanical SEALED BY RANDY J. AXVIG REGISTRATION NUMBER 3606, ON FEBRUARY 4, 2020, SHEET AND IS STORED AT THE OFFICE OF PRAIRIE ENGINEERING, P.C. M4.0