Haparanda Line

2007-SE-92402-P

Member States involved:

Implementation schedule Start date: February 2008 End date: October 2010

Implementing body: Banverket (Swedish Rail Administration)

Budget: National budget: €42,300,000

Total project cost covered by this Decision: €47,000,000

EU contribution: €4,700,000

Percentage of EU support: Works: 10%

Additional information: This project concerns the rail line, the only fixed rail link between Sweden and . It consists of the TEN link Boden-Morjärv-Haparanda- European Commission, DG MOVE Tornäa and branch Morjärv-. It connects northern Finland and with http://ec.europa.eu/dgs/transport/ Norway, and Western Europe via Sweden/Denmark. index_en.html

Part of the NEW Corridor (Northern East-West Railway Freight Corridor), an UIC Trans-European Transport Network (International Union of Railways) initiative for a new multimodal transport corridor Executive Agency (TEN-T EA) for freight and container service, the is also near the ongoing http://ec.europa.eu/tentea construction of Bothnia line (190 km of a new doubletrack Nyland-Umäa) and the

planned Norrbothnia Line between Luläa and Umäa. Beneficiary & Implementing body: This project includes electrification, installation of ERTMS (European Rail Traffic Banverket (Swedish Rail Management System) Level 2, upgrading for higher axle-loads Boden-Morjärv- Administration) Kalix (115 km), and construction of the new, electrified and ERTMS Level 2- www.banverket.se equipped line Kalix-Haparanda (42 km). By removal of the section Morjärv-

Haparanda, the total line-length will be reduced by +/- 50 km. The upgraded lines

will allow trains with the axle load of 25 tonnes, and the new lines up to 30

tonnes.

This project has been completed.

Updated: September 2011