Quick viewing(Text Mode)

North Eastern Region Capital Cities Development Investment Program

North Eastern Region Capital Cities Development Investment Program

Social Monitoring Report

2nd Semestral Report April 2016

Period: July 2015 - December 2015

IND: North Eastern Region Capital Cities Development Investment Program

Prepared by State Investment Program Management and Implementation Unit (SIPMIUs) , , , , for Asian Development Bank and is made publicly available in accordance with ADB’s public communications policy (2011). It does not necessarily reflect the views of ADB.

This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

SEMI ANNUAL SOCIAL SAFEGUARD MONITORING REPORT (Consolidated)

Reporting Period: (July - December 2015)

INDIA: North Eastern Region Capital Cities Development Investment Program (NERUDP)

CONSOLIDATE BY

PMMC

APRIL 2016

Prepared by: State Investment Program Management and Implementation Unit (SIPMIUs) Agartala, Aizawl, Gangtok, Kohima, Shillong

TABLE OF CONTENTS

 Agartala ...... 3

 Aizawl ...... 28

 Gangtok ...... 72

 Kohima ...... 136

 Shillong ...... 163

GOVERNMENT OF URBAN DEVELOPMENT DEPARTMENT

State Investment Programme Management & Implementation Unit (SIPMIU) North East Region Development Investment Programme (NERCCDIP)

SEMI ANNUAL REPORT ON SOCIAL SAFEGUARD & GENDER ACTION PLAN

July to December - 2015 January – 2016

Design, Supervision & Management Consultancy (DSMC)

STUP Consultants P. Ltd.

3 Semi-Annual Social Safeguard Monitoring Report, July to December , 2015

As per ADB Safeguard Policy Statement (2009) and the Operations Manual section on safeguard policy (OM F1), borrowers/clients are required to establish and maintain procedures to monitor the status of implementation of safeguard plans and ensure progress is made toward the desired outcomes. For projects categorized as A or B in Involuntary Resettlement and/or Indigenous People, the Borrowers/clients are required to submit semiannual monitoring reports for ADB review. The present awarded sub projects under Tranche I and II are categorized as Category C in respect to Involuntary Resettlement and/or Indigenous People and accordingly as per ADB policy no monitoring report is required, only filling up of checklists have been done.

4

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

Table of Contents

1. Introduction and Project Background ...... 2 2. Project Background...... 2 4. Social Safeguard Activities during the Period ...... 4 5. Status of RP Implementation ...... 5 6. Implementation of Resettlement Activities in the Tranches ...... 10 7. Project Impact ...... 10 10. Validation and Verifications of APs ...... 12 11. Issues and Action Plan ...... 12 13. Due Diligence Findings ...... 13 14. Conclusions...... 14

Tables

Table 1: Institutional Roles and Responsibilities...... 3 Table 2: Subproject components ...... 3 Table 3: Status of Construction and Social Impact in Tranche-I Subprojects ...... 6 Table 4: Status of Construction and Social Impact in Tranche-II Subprojects ...... 6 Table 5: Status of Construction and Social Impact in Tranche-III Subprojects ...... 10 Table 6: Summary of Resettlement Impacts and Socioeconomic Details ...... 11

Annexure

1. Details of Public Consultations, Disclosure, Awareness campaigns………………………………16 2. Gender Action Plan………………………………………………………………………………………17 3. Social Safeguard Monitoring Checklist…………………………………………………….……..……19 4. Summary of IR and IP Check List……………………………………………………………………..21 5. Summary of Policy and Legal Framework (Only relevant portions…………………..…………….23 6. Land Record- To Be Acquired……………………………………………………………………….…24 7. List of Affected Persons…………………………………………………………………………………25 8. Resettlement Budget and Financial Plan (WS Subprojects)………………………………………..26 9. Documentary Proofs……………………………………………………………………………………..27

5

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

Abbreviations

ADB - Asian Development Bank AP - Affected Person DSMC - Design Supervision and Management Consultant FGDs - Focus Group Discussion GoT - GRC - Grievance Redressal Committee IPCC - Investment Program Coordination Cell RO - Resettlement Officer RP - Resettlement Plan SIA - Social Impact Assessment SIPMIU - State-level Investment Program Management and Implementation Unit SS - Social Safeguard Specialist

61 STUP Consultants P. Ltd SIPMIU, Agartala (Design Supervision and Management Consultant)

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

Semi Annual Social Safeguard Monitoring Report

1. Introduction and Project Background The Government of (GoI) reaffirmed its obligation to sectoral reforms by launching National Urban Renewal Mission (JNNURM), that aims at improving existing poor infrastructure and quality of life in urban areas in India. The North Eastern Region Capital Cities Development Investment Program (NERCCDIP) carries the Mission statement further through a planned, organized, yet flexible approach to meet the growth needs in consonance with specific needs of the capital cities namely, Agartala, Aizawl, Gangtok, Kohima and Shillong in the North Eastern Region (NER) to bring those at par with the rest of the country. The components under the Investment Program in Agartala include

Development of urban infrastructure facilities in the sector for Water Supply Solid Waste Management systems The Investment Program is being implemented in three tranches of funding; began in 2009.

2. Project Background NERCCDIP is being implemented in Agartala Municipal Corporation (AMC) area for improvement of existing infrastructure, environmental quality and enhancing vital urban services for the residents of the city. It is beibg implemented over a six year period beginning in 2010, and is funded by a loan via Multi-tranche Financing Facility (MFF) of the Asian Development Bank (ADB). . ADB is committed to assist the integrated urban development initiatives of the GoI. 70% of the loan component will be borne by ADB and the GoI will share the balance 30 %. The objectives of the subproject are to: Provide potable water through effective treatment Increase supply hours through effective storage Generate adequate water through installation of new deep tube wells Manage water in a better manner and control on NRW through installation of water meters The entire project area has been broadly divided into three main water zones: 1.Central Zone- The area between Haora and 2. South Zone- a. Bardowali Division b. Jogendranagar Division.

3. The institutional role and responsibilities is described in the table below

      

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

Table 1: Institutional Roles and Responsibilities

Activities Agency Responsible Subproject Initiation Stage Finalization of sites/alignments for subprojects SIPMIU/DSMC Disclosure of proposed land acquisition and subproject details by issuing public SIPMIU/GoT notice Meetings at community/household level with APs of land/property Formation of SIPMIU Valuation Committees RP Preparation Stage Conducting Census of all APs SIPMIU/External agency Conducting FGDs/meetings/workshops during SIA surveys SIPMIU/DSMC Computation of Replacement Values of land/properties proposed for acquisition SIPMIU/GoT and for associated assets Categorization of APs for finalizing entitlements SIPMIU Formulating compensation and rehabilitation measures conducting SIPMIU discussions/meetings/workshops with all APs and other stakeholders Fixing compensation for land/property with titleholders SIPMIU/GoT Finalizing entitlements and rehabilitation packages SIPMIU Disclosure of final entitlements and rehabilitation packages SIPMIU Approval of RP IPCC/ADB Sale Deed Execution and Payment SIPMIU Taking possession of land RP Implementation Stage Implementation of proposed rehabilitation measures SS/RO Consultations with APs during rehabilitation activities SS/RO Grievances Redress SIPMIU/RO/GRC Internal Monitoring SIPMIU

The work is ongoing and in mid way phase of Tranche-II is being implemented in Agartala and these focus on water supply improvements. The DPR for Tranche-III is already approved by the Ministry oo Urban Development. The current report is the Annual report on implementation of social safeguard activities for Tranche-II (January-December 2015), and is prepared in compliance with the Policies of ADB. The subproject components are as follows:

Table 2: Subproject components Component Tranche Works Water Supply I  Replacement of existing 22nos. of Tubewells. (WS-01) Water Supply II  Supporting NRW Reduction Program through Procurement and Installation of Bulk (WS-03)  Installation of 7 ground water treatment units (WS-02, 07, 08)  Construction of 14 Reservoirs (WS-09)  Laying of primary pipelines (60 Kms) and secondary pipelines (410 Kms) ( WS10/1, 10/3) Water Supply III  Rehabilitation of WTP a. College Tilla b. Bardwali  Intake Well a. Aralia b. Balurchar  Distribution Network- Central- 176 km  New Deep Tube Wells- 12

83 STUP Consultants P. Ltd SIPMIU, Agartala (Design Supervision and Management Consultant)

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

Component Tranche Works Solid Waste  Procurement of equipments for primary and secondary collection of Management solid waste  Procurement of vehicles for transportation of waste Septage  Procurement of Equiptment for collection & transportation. Management  Procuremeent and installation of Septage Treatment Plant

4. Social Safeguard Activities during the Period

4.1 Social Issues In order to identify any social impact, due to the Project implementations, the SIPMIU and the DSM Consultant have carried out several site visits and consultative assessments in the project areas during the preparation of this document. Based on this and discussions held with the local residents in the Project locations, it has been confirmed that the implementation of the concerned Project does not have any negative social impact till date (Ref 5 public consultations in different sites). Hence the subprojects under all the Tranches with respect to issues related to involuntary resettlement as well as IP are Category C. However, public consultations shall be continued throughout the project implementation period to confirm that no social/resettlement issues remain addressed.

4.2 Scope of Work and Resettlement Impact It has been assessed that no resettlement issue is involved for the works in these Tranches. The following situation was found at/around places.  Impacts as assessed No land acquisition is envisaged for water supply subproject. The sites for all the components of the water supply subprojects of all the Tranches are either located on vacant government lands or along the existing Right of Way (RoW) of Government land. No encroachment or any squatter has been found on the selected sites till date, therefore it does not involve any land acquisition and resettlement. The improvement work is being carried out within the RoW in road shoulders particularly in the side through which the present water supply lines passes through. Existing bituminous roads which are being dug for laying of pipelines are being restored with bituminous courses confirming with the existing pavement

conditions. Wherever shoulder space is available, the pipeline will be laid along that width

      

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

The transect walk does not find presence of any IPs. In brief the extent of negative impact is negligible in this subproject.

4.3 Benefits as assessed- It is expected that this subproject will benefit a population of 5,97,808 by 2026 and 8,22,267 by 2041. An estimated 40,000 house connections will be provided- majority of those will be domestic with some commercial connections. Construction of a few stand posts is proposed to cater to the slum areas and the areas with economically weaker section. Local people are being deployed at the sites for Project works.

4.3. The design principles incorporated other mitigation measures, including but not limited to the following:

Selection of alternative alignments to minimize impacts Implementation of works in a phased manner to minimize the period of disruption Provision of advance notice to the local people Provision of temporary access to people during the digging for laying pipelines.

It has been proposed that suitable mitigation measures will be considered if any evolving situation arises, so that during construction business establishments/residences can be left undisturbed. Access to the business setups/residences will be ensured during construction.

5. Status of RP Implementation The resettlement monitoring review has been done periodically and it has found that there is no impact which required mitigation measures as the construction activities are being done either within the available RoW of city roads or along the open area

5.1 Scope of Construction and Social Impacts This is a rehabilitation work of the existing water supply system. An attempt was made to observe the situation in the city along the supply systems and also probe into the resettlement issues in various locations by a reconnaissance visit and consecutive visits. The following situation was found at/around subproject sites:

      

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

Table 3: Status of Construction and Social Impact in Tranche-I Subprojects SN Works Achieved Status of Works Status of RP (% of Implementation completion) 1 Replacement of existing 22nos. 100% There is no requirement of of Tubewells. (WS-01) 100% land acquisition  Lot – 1(6 TW with PH) 100% 100% No temporary impact like  Lot – 2 (8TW) 100% 100% access restriction, impact  Lot – 3 (8TW) 100% on livelihood etc.  Construction of pump 98% house for 16 TWs)

Table 4: Status of Construction and Social Impact in Tranche-II Subprojects SN Works Status of Works SIA 1 Construction of 7 Groundwater Treatment Plants (GWTPs) GWTP-1: Public Health No impact on any Engineering (PHE) Complex, structure, land or opposite Pragati School livelihood Under construction

GWTP-2: Area near Battala No impact on any burial ground structure, land or Land development livelihood

GWTP-3: Camper Bazar, No impact on any Dindayal Ashram structure, land or Almost complete livelihood

GWTP-4: Public Health No impact on any Engineering (PHE) Stores, structure, land or Dukli livelihood Almost complete

GWTP-5: Pratapgarh, Sadhu No impact on any

116 STUP Consultants P. Ltd SIPMIU, Agartala (Design Supervision and Management Consultant)

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

SN Works Status of Works SIA Tilla structure, land or Almost complete livelihood

GWTP-6: Area near AMC Zonal No impact on any Office (Ward 35) structure, land or Almost complete livelihood

GWTP-7: Near Aralia-II DTW No impact on any Almost complete structure, land or livelihood

2 Construction of 14 New OHSRs Lot 1: 7- 45% Lot 2: 19% OHSR 01: Near/backside of No impact on any Sadhu Tilla School- 1130 KL structure, land or Under construction livelihood

OHSR 02: Near AMC Zonal No impact on any office (Ward 35)- 680 KL structure, land or Under construction livelihood

OHSR 03: Salbagan Road- No impact on any 450 KL structure, land or Under construction livelihood

127 STUP Consultants P. Ltd SIPMIU, Agartala (Design Supervision and Management Consultant)

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

SN Works Status of Works SIA Work not yet started. It OHSR 04: Backside of Public has been assessed that Health Engineering (PHE) sub- there will be no impact on div office Jogendranagar- 450 any structure, land or KL livelihood Under construction

OHSR 05: Near Bankumari No impact on any Bazaar/Nath Para- 450 KL structure, land or Under construction livelihood

OHSR 06: Near Aralia II DTW- No impact on any 450 KL structure, land or Under construction livelihood

OHSR 07: Opposite No impact on any Champamura Horticulture structure, land or Office- 450 KL livelihood Under construction

OHSR 08: Cold storage, No impact on any Sripally near Badharghat- structure, land or 1130 KL livelihood Under construction

138 STUP Consultants P. Ltd SIPMIU, Agartala (Design Supervision and Management Consultant)

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

SN Works Status of Works SIA OHSR 09: Near Sarbadharma Mission- 900 KL Land development

OHSR 10: Near No impact on any Pranabananda School- 680 KL structure, land or Almost complete livelihood

OHSR 11: Near DTW at Retendering under progress There is no such Rampur- 1130 KL,GWTP is negative impact under progress OHSR 12: Near Pragati School Retendering under progress complex- 900 KL OHSR 13: Near Harijan Retendering under progress Colony- 680 KL OHSR 14: Area near Battala Retendering under progress burial ground- 1130 KL 3 Providing and Laying of Water Supply Distribution pipelines- Supply and laying of water No impact on any supply distribution pipelines and structure, land or allied works (South) livelihood (Jogendranagar) 72.82%

4 Providing and Laying of water supply Distribution pipelines Supply and laying of water No impact on any supply distribution pipelines and structure, land or allied works (South) (Bardowali) livelihood

5. Laying of New Primary Mains in No impact on any different parts of Agartala city structure, land or 62% livelihood

6 Installation of bulk water meters- 67% completed.

149 STUP Consultants P. Ltd SIPMIU, Agartala (Design Supervision and Management Consultant)

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

SN Works Status of Works SIA 7. Procurement of Ground Water Treatment Plants Design, Construction, Supply, Installation, Commissioning Including Mechanical & Electrical Equipments with trial run for One Year in Agartala 58%

The Subprojects will involve no physical displacement as the constructions are being done within the RoW or vacant Government land. The citizens are identified as the beneficiaries of the project. They are happy in welcoming the Project as currently the supplied water is not very satisfactory and adequate to them.

Table 5: Status of Construction and Social Impact in Tranche-III Subprojects SN Works Status of Works (% of SIA completion)* 1 Rehabilitation of WTP No impact on any structure/ land/livelihood (a) College Tilla DPR has been approved & (b) Bardwali Tendering is 2 Distribution Network- Central complete.Awaiting. ADB’s No impact on any structure/ approval land/livelihood 3 New Deep Tube Well No impact on any structure/ land/livelihood 4 Solid Waste Management:- DPR has been approved & Bid Document under (a) Procurement of preparation. equipments for primary and secondary collection of solid waste (b) Procurement of vehicles for transportation of waste 5 Septage Management:- DPR submitted for approval. (a) Procurement of Equiptment for collection & transportation. (b) Procuremeent and installation of Septage Treatment Plant

6. Implementation of Resettlement Activities in the Tranches

Since there is no issue of land acquisition and/or resettlement the sub project does not entail any resettlement planning. Construction of 7 GWTUs and 14 OHSRs are designed to be built on vacant government/municipal land. Laying of primary pipelines (60 kms) and secondary pipelines (410 kms) also do not have any impact on land acquisition and resettlement impacts because it will be undertaken within sufficient and vacant road RoW.

7. Project Impact The Investment Program is intended to optimize the socioeconomic development in Agartala Municipal area with an objective to improve the urban environment cum living conditions of

1510 STUP Consultants P. Ltd SIPMIU, Agartala (Design Supervision and Management Consultant)

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

citizens. The subprojects implementations will not create any major negative impact on community. The implementation of RPs integrating with various developmental schemes of governmental and non-governmental agencies will enhance the living standard of PAPs. Summary of negative social impacts in tranche sub projects is summarised below:

Table 6: Summary of Resettlement Impacts and Socioeconomic Details Type of Impact Number of APs 1.Permanent Loss Title Holder/Land Owner Nil Total Loss of land(sq.mts) Nil Loss of trees Nil Total land Holding in that Particular Plot (sq.mts) Nil Occupation NA Vulnerability NA Annual Income (INR) NA 2.Temporary Loss A)Temporary Loss/ Disruption of Business(Nos) Nil B)Temporary Loss/ Disruption of Business Employees of the business Nil enterprises(Nos) 3. Encroacher in ROW A) Encroacher in ROW(Nos) Nil Affected CPRs Nil

7.1.Land Acquisition, and Rehabilitation in Solid Waste Management Subproject Since the responsibility of this subproject has been transferred to the AMC, the DSMC is not required to design any safeguards measures.

7.2.Status of Contractor Social Safeguards Compliance Contractors are maintaining compliance by following the social safeguards norms set by the Project. The only problem they are facing that the labourers, especially the women, are not comfortable with the use of safety gadgets. With the women labors the contractors notified that apart from casting they are not usually employed as it becomes insecure for them. The workers are being counseled by the team members for using those. It is a slow process as behaviour change takes long time Tranche 1-The following contractors were awarded M/S Subhas Poddar,M/S Priyatosh Saha, Uttam Dey,Kabir Saha (tubewell) M/S Utkarsh Tubes & Pipes Ltd (MSERW pipe) Tranche II ITD-ITD Cem JV-(GWTP) Ramky Infrastructure- (OHT)

1611 STUP Consultants P. Ltd SIPMIU, Agartala (Design Supervision and Management Consultant)

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

M/S Jaihind Projects Ltd (Bulk Meter) Electro Steel (D I Pipe)

8. Validation and Verifications of APs Validation and verification are done and it is being confirmed that there is no negative impact of the subproject till date. Since there is no impact there is no requirement for compensation and assistance.

9. Issues and Action Plan Since the action plan has been revised in the year of December 2011 on the basis of the proposal for the work of Tranche-I and Tranche-II, there is no change from the proposed plan after sanction. If situation needs RP will be prepared and its implementations will be attended by social safeguard specialist of SIPMIU and DSMC.

10. Public Consultations i) Champamura, Gurudaspara Venue- Roadside discussion Participants –Ms Aparna Pal,Ms Rupa pal, Ms Khona Lobo Opinion This is a very good project .As all the females have to do the household chores they have to face all the problems relating water so naturally it will be much better for them.

ii) Jogendra Nagar Venue-House houseof Mr. Uttam Choudhury, Participants - Mr. Uttam Choudhury Ms Laxmi Choudhury,Ms Chinu Sinha, Ms Pinki Saha, Ms Anjali Roy Opinion They asked about the installation of water meter. They opined that project is very much necessitated as water flow will be regular and iron free.

iii) Bankumari, Nathpara Venue- House of Subhadra Debnath Participants Ms.Subhadra Debnath, Ms Jhuma Debnath Opinion They are facing water related problems in many ways.They think this project will bring iron free fresh water , a blessing for all.

1712 STUP Consultants P. Ltd SIPMIU, Agartala (Design Supervision and Management Consultant)

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

iv) Adarsha Colony Venue Roadside discussion Participants Ms Milanbala Das, Ms Chandana Das,Ms Munna das,Ms Bhanu Debnath Opinion This is a very good project. People will be benefitted.

v) Shalbagan Venue House of Mr raju Ghosh

Participants Mr raju Ghosh, Ms Purnima Ghosh

Opinion

It is a good project. The water will be iron free and clean. So far water is damaging for skin, hair, full of iron.

vi) Camper Bazar, Hospital Road Venue House of Mr Ganesh Chandra Dhar

Participants Mr Ganesh Chandra Dhar, Ms Mitra Dhar

Opinion The water had been irregular, it come twice a day. It will be very advantageous for people. vii) ONGC Venue Roaside discussion

Participants Mr Dipak Kumar debnath, Mr Prahlad saha, Mr Swapan Karmakar

Opinion Within ONGC campus there had been a pumphouse but that is not functional anymore so naturally it will be truely very helpful.

viii) Badharghat, Sripally Venue Roaside discussion

Participants Ms Sima Debnath, Ms Eka Das, Ms Khela Shil

Opinion The water is full of iron. It is very irregular, hampers household work . So naturally when clean water will come they will be very happy. 11. Due Diligence Findings The proposed work is a rehabilitation work of the existing water supply systems. The new structures are being constructed within the existing RoW. It has been found that no additional

1813 STUP Consultants P. Ltd SIPMIU, Agartala (Design Supervision and Management Consultant)

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

land will be required for this subproject and there is no structure affected; hence there is neither any land acquisition issue nor any resettlement issue involved in it. Therefore it has been confirmed that there is no resettlement planning required for this.

12. Conclusions The report confirms that the NERCCDIP water supply subproject under the Tranches does not have adverse social impacts associated with land acquisition and resettlement and it is expected that the project will benefit entire population of the city of Agartala after the completion of the Project. According to this information the Subproject comes under Category C of Resettlement Categorization. So no resettlement planning is required for this.

Annexure 1: Details of Public Consultations, Disclosure, Awareness campaigns

Please attach list of meetings etc held only during the last 6 months (January to December, 2015 only) in the table provided below: Issues SN Date Place Participants Opinion & Consensus Discussed

Informal consultations held in this

period (Ref Section 10)

1914 STUP Consultants P. Ltd SIPMIU, Agartala (Design Supervision and Management Consultant)

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

Annex 2: Gender Action Plan

Water Supply Project of NERUDP (Based On ADB Approved GAP and Agreed in Gender Workshop) Output Activities Planned Activities conducted Remarks during the period under report Sustainable and increased Conduct gender A seminar had been It was highly successful access to better urban sensitization seminar in organized on 17th&18th and well appreciated. services for Water supply, the city to highlight gender February, 2012 where 40% Sewerage, & Solid waste issues in water supply, were women participants. management. sanitation, solid waste and drainage, and the need for women’s involvement in the implementation, O&M of these services. Understanding needs of Conduct FGDs in all The following number of It was seen that majority of women for provision of income groups (Upper, meetings was conducted. the participants were not water supply point/stand middle and lower class) to 10 with middle income aware of the project. With posts, timings of water understand their needs & groups, 15 in slum areas & these FGDs they came to supply, need to conserve concerns vis a vis, 10 with SHGs of Agartala in know about the ongoing water, need to be proactive household connections 3 zones, South, East and project. In most of the regarding reporting/repairs Central. Total participants cases councilors or their of leaks, wastages etc. were 673, out of which 182 representatives were were males (27%) and 491 present. It had been were females (73%). The beneficial for all. meetings were evenly distributed all over the city. Creating awareness Prepare IEC material and It will be done in later stage. regarding conservation of develop mass media water from women's campaigns about the perspective through use of project, conservation of media water, repair of leaks etc. with special emphasis on, how women can contribute towards reduction of water wastage and help in conservation Creating awareness Conduct activities in 13 sit & draw and 13 slogan The participants were regarding conservation of Schools such as slogan competitions were enthusiastic and opined water and good sanitation competition, painting organized. Total sit & draw they have become much habits through school competition, skits to participants were 572, out of more aware due to these children (with active increase awareness and which 55% were girls, 45% programs. participation of girl students) spread of the message to were boys. For slogan the parents. ( minimum competition, 205 guardians 50% participation of girls) participated out of which 73% were females. To reinforce the messages To undertake outdoor It is done. By these activities more of water use and its activities as a reminder people became aware. conservation through medium by way of cycle various activities rallies (10), thematic street theatres (10) workshops (5) seminars (1) etc. (minimum 50% participation of girls and women). Provision of water services Survey of FHHs and SIPMIU to approve to FHH (Female Headed preparation of list for Household) on priority. giving priority to FHH in Prepare a disaggregated the NERUDP project data base MIS on provision of water 1. Provision of water It has been initiated. 100% FHH will have water connections to FHH connections and meters to connection and water female headed meter

2015 STUP Consultants P. Ltd SIPMIU, Agartala (Design Supervision and Management Consultant)

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

Output Activities Planned Activities conducted Remarks during the period under report households with priority to poor FHHs in the city 2. uploading data on website Improving repairs and Conduct five public It had been discussed during maintenance and improving consultation meetings the FGDs, the participants compliance with payment of with women groups , and agreed to pay. user charges through five with mix groups of people's participation. women and men (target: 50% women) on timing and duration of water supply, water tariff and method of collection, responsibility of repair and maintenance Equal employment Tender conditions have It is seen during The muster roll has been opportunities been incorporated in the construction. checked. contract agreement of the contractor for emphasis on employment for women with equal pay. MIS regarding employment Employment of women in Not within the scope of of women in the sewerage the construction of work project pipelines, plants, etc., with implementation of ‘same pay for same work – notices to be displayed up at-least 6 locations publicizing equal pay for equal work policy. (e.g. work site, at the notice board of ULB/UDD, SIPMIU office and local employment exchange) Any other (please mention) One project proposal on Awaits approval Of SIPMIU solid waste will be initiated soon

2116 STUP Consultants P. Ltd SIPMIU, Agartala (Design Supervision and Management Consultant)

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

Annex 3: SOCIAL SAFEGUARD MONITORING CHECKLIST

1: Social Safeguards Monitoring Checklist Project Data Name of Project & Subproject: Replacement of 6 Tube Wells including Pump House in Lot-I Project Disbursement Status (%): Type of contract:  Regular √  Design-Build  Combined Safeguards Categorization C C C IR C C C IP C C C

A. Design and Engineering Status Item Status Follow up Type of Required Action (Y/N) required (Y/N) Final detailed engineering design of the Yes Yes  Updated draft IR/IP subproject completed  New RP/IPP preparation Changes in project design/ scope No No  Project re-categorization (IR/IP) (occurred or envisaged)  IR/IP Impact assessment  New RP/IPP preparation

B. Institutional Status Readiness No Item Status(Ready/ Follow up Completion Deadline Not ready/NA) required(Y/N) 1 Mobilization of civil works Yes , the contractors Yes Work completed contractor had been awarded work 2 Mobilization of Project Yes Yes Supervision Consultant 3 EA’s Safeguards Unit with Yes Yes designated staff 4 Recruitment of External NA No Monitoring Agency

C. Safeguards Requirements No Item Status(Ready/ Follow up Completion Deadline Not ready/NA) required(Y/N) 1 Safeguards monitoring included in the Included Y project progress report 2 Final/ updated RP/IPP1 prepared and NA N submitted 3 Project’s Grievance Redress Established, but Y Mechanism established there is no grievance as such 4 Recruitment of third independent party NA N for negotiated land acquisition 5 Project’s ESMS (for FI) established Ready Y

2217 STUP Consultants P. Ltd SIPMIU, Agartala (Design Supervision and Management Consultant)

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

2. RP/IPP MONITORING CHECKLIST

Item Safeguards Related Requirements Status Completion Progress No. (Ready/Not Deadline to Date/ ready/ NA) Remarks 1.0 MANAGEMENT Institutional and Financing Arrangements 1.1 Financing and budget : (i) safeguard office and staff; (ii) RP/IPP cost Ready/NA 1.2 Establish Safeguard Unit: (i) resettlement offices (ii) Ready/NA resettlement staff as in RP (iii) safeguards’ database (iv) facilities (v) safeguards training Updating of DD/RP/IPP based on Detailed Design 1.3 Update DD/RP/IPP: (i) revise based on DMS (ii) revise implementation Ready schedule (iii) revise budget 1.4 Compensation rates: (i) approved by Government ; (ii) NA Adequate as per RP/RF; (iii) APs informed. Disclosure and Grievance Redress Arrangements 1.5 Disclose final/updated RP/IPP: (i) to the APs in local ; (ii) in Ready ADB website; (iii) in EA’s website 1.6 Disclose project activities to affected communities: (i) put up a project Ready sign boards; (ii) distribution of project leaflets and GRM to affected communities 1.7 Grievance redress committees: (i) clear terms of reference; (ii) Ready appointment decree; (iii) publicly disclosed among APs. 1.8 Grievance redress records: (i) list and numbers of grievances received; NA (ii) numbers of resolved issues; (iii) numbers of cases under GRC review; (iv) outstanding cases (filed to court) Monitoring and Reporting Arrangements 1.9 Set up internal monitoring system : (i) assessment on Ready capacity and staff requirements; (ii) criteria of safeguards assessment ; (iii) reporting mechanism 1.10 Appoint external monitoring agency (as relevant): (i) recruitment NA schedule; (ii) TOR; (iv) baseline survey (v) reporting mechanism (vi) action taken by management on reports. 1.11 Reporting: (i) frequency; (ii) timeliness; (iii) identified issues; (iv) action Ready taken and/recommendation. 2.0 PR/IPP IMPLEMENTATION Consultation 2.1 Consultation: (i) responsibility; (ii)stakeholders Ready Identified; (iii) consultation and process; (iv) documentation Mapping and Assets Inventory 2.2 AP Identity cards & affected assets records: (i) issuance and NA distribution of AP ID cards, (ii) detail measurements survey of affected assets and documentation 2.3 Land acquisition activities: (i) maps of affected and relocation sites; (ii) NA acquisition & relocation schedule; (iii) coordination with the asset’s acquiring, transfer and registration bodies 2.4 Common property/ public assets: (i) final inventory; NA (ii) restoration plan and schedule; (iii) funding sources Compensation, Relocation and Rehabilitation 2.5 Payment of compensation and entitlements (as stated in the RP): (i) NA schedule of payment; (ii) records/ receipts of payment 2.6 Relocation of process ( relocation site readiness): (i) housing NA & associated facilities established; (ii) transfer of new land/plot/ house ownerships completed 2.7 Provision of (a) income restoration, (b) additional assistance for NA vulnerable APs, (c) training, etc. (as stated in the RP): (i) per type of activities; (ii) schedule of implementation Monitoring and Reporting 2.8 Submission of the reports: (i) semiannual monitoring reports; (ii) Ready external monitoring and evaluation reports (as required); (iii) completion report 2.9 Transfer of acquired assets to the acquiring agency NA

2318 STUP Consultants P. Ltd SIPMIU, Agartala (Design Supervision and Management Consultant)

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

A. SAFEGUARDS LOAN COVENANTS

Not applicable for IR impacts and RP implementation

Overall Status of Compliance    Not complied – Redressed action & Complied with further monitoring Fully complied – no further action monitoring required

Annex 4: Summary of IR and IP Check List Has Has involuntary Indigenous resettlement People (IP) Has No IR Has No IP (IR) impact, impact, an impact, no impact, no a Issues indigenous Issues Name of the Work resettlement IPP/specific resettlement if any people plan if any plan is action plan plan (or (IPP) (or required is required. corrective specific IP action plan) action plan) is required is required Replacement of 22 Deep Tube Wells Lot 1, 2 and 3 (AGT/WS01(R) – X NA X NA /NCB/11/1/Lot1, Lot 2 & Lot 3) 22 √ √ locations in Agartala city Procurement of Ground Water Treatment Plants Design, Construction, Supply, Installation, Commissioning Including X NA X NA Mechanical & Electrical Equipments √ √ and Operation for One Year in Agartala. (AGT/WS 02,07,08/ICB/11/8). Design Supply and Construction of 14 Nos. of Over Head Service X NA X NA Reservoir (OHSR), √ √ (AGT/WS09/ICB/11/7, Lot -1 & 2) Providing, Installation, Testing and Commissioning of Bulk Flow Water Meter in Agartala water Supply X √ NA X √ NA Project, Agartala city (AGT/WS03/M/NCB/11/6) Supply and Laying of Water Supply Distribution Pipelines and allied works in Agartala city (South) {[Jogendranagar] (AGT/WS10- X NA X NA 3/ICB/11/9, Lot-1}, {Bardowali] √ √ (AGT/WS10-3/ICB/11/9, Lot-2}: South part of Agartala city –105.3 km & 126.2 km=Total231.5 km Procurement of DI Pipes for Laying of Rising Mains in X √ NA X √ NA AgartalaCity(AGT/WS03/M/NCB/11/6) Laying of new Primary Mains in various parts of Agartala X NA X NA (AGT/WS10-2(R)/NCB/12/2). 58.7 km √ √ rising mains Rehabilitation of WTP X √ NA X √ NA Intake well X √ NA X √ NA Distribution Network – Central X √ NA X √ NA New Deep Tube Well- 14 (8 ’R’ and 6 X √ NA X √ NA ’N’)

      

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

Annex 5: SUMMARY OF POLICY AND LEGAL FRAMEWORK

Policy and Legal Framework The policy framework and entitlements for the program as well as for this subproject are based on following national laws: The Land Acquisition Act, 1894 (amended in 1984), and the National Resettlement and Rehabilitation Policy (NRRP), 2007, State laws and regulations: The Tripura State Land Acquisition (LA) Act 1894, ADB’s Safeguard Policy Statement, 2009; and the agreed Resettlement Framework (RF).

Based on these, the core involuntary resettlement principles applicable are: Land acquisition, and other involuntary resettlement impacts will be avoided or minimized exploring all viable alternative subproject designs Where unavoidable, time-bound Resettlement Plans will be prepared and APs will be assisted in improving or at least regaining their pre-program standard of living Consultation with APs on compensation, disclosure of resettlement information to APs, and participation of affected persons in planning and implementing subprojects will be ensured Vulnerable groups will be provided special assistance Payment of compensation to APs including non-titled persons (e.g., informal dwellers/squatters, and encroachers) for acquired assets at replacement rates Payment of compensation and resettlement assistance prior to the contractor taking physical acquisition of the land and prior to the commencement of any construction activities Provision of income restoration and rehabilitation and Establishment of appropriate grievance redress mechanisms

The RP outlines the objectives, policy principles and procedures for land acquisition, compensation and other assistance measures for Affected Persons (APs). The Executing Agency (EA) and the Implementing Agency (IA) will have to endorse the Resettlement Plan prior to Project Appraisal. The RPs shall be disclosed to the affected persons (APs) and submitted to ADB for review and approval prior to commencement of any civil works. Compensation and other assistances will have to be paid to APs prior to any physical or economic displacement of affected households. Remarks: Not applicable as no land acquisitionisrequired.

Annex 6: Land Record- To Be Acquired Not applicable as no land acquisition is involved . Annex 7: Resettlement Budget and Financial Plan

There is no resettlement issue in any of the Tranchesso no budget provision is required

      

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

Photos of Public Consultation

Fig:-1, Back side of Jogendranagar Fig:-2, Nathpara

Fig:-3, AMC Zonal office, word - 35 Fig:-4, Salbagan

Fig:-5, AD Nagar Fig:-6, ONGC

Fig :- 7, Badharghat (Sripally) Fig :- 8, Champamura

2621 STUP Consultants P. Ltd SIPMIU, Agartala (Design Supervision and Management Consultant)

Semi Annual Social Safeguard Monitoring Report, July to December, 2015

2722 STUP Consultants P. Ltd SIPMIU, Agartala (Design Supervision and Management Consultant)

SEMI ANNUAL SOCIAL MONITORING REPORT

Loan Number: 2834 IND Reporting Period: (July-December 2015)

INDIA: North Eastern Region Capital Cities Development Investment Program (NERCCDIP)

Project City: Aizawl, State

Implementing Agency: State Investment Program Management and Implementation Unit (SIPMIU)

Executing Agency: Urban Development & Poverty Alleviation Department,

28 CONTENTS 1. INTRODUCTION: ...... 2 1.1 Implementation status of sub projects Tranche 2 in general ...... 2 1.2 Background and context of the report: ...... 3 2. Status of Implementation of sub projects under TRANCHE II with regards to Social safeguards: . 3 2.1 Social Safeguard Monitoring Checklist – TRANCHE II ...... 8 2.2 Monitoring indicators and status report ...... 14 2.3 Monitoring and reporting arrangements...... 15 2.4 Summary of Resettlement impacts and socio-economic details under water supply and sewerage sub project: ...... 16 2.5 Status of the affected people: Land requirement, Compensation and Rehabilitation in Water Supply and Sewerage Sub Projects in TRANCHE II: ...... 16 2.6 Land requirement, Compensation and Rehabilitation in SWM Sub Project (Tranche 3) ...... 20 2.7 Permanent land acquisition and ownership details under Solid Waste Management sub project Tr-3: ...... 20 2.8 Status of land acquisition for Tranche-3: ...... 21 2.9 Rag Pickers (Tr-3):...... 22 2.10 Status of Contractors Social Safeguards Compliance...... 22 2.11 COMPLIANCE TO NATIONAL LAWS AND POLICIES (POLICY AND LEGAL FRAME WORK):...... 23 2.12 GREIVANCE REDRESSAL SYSTEMS AND MECHANISMS...... 23 3. ACTIVITIES CARRIED OUT WITH RESPECT TO PUBLIC PARTICIPATION OF GENDER ACTION PLAN (GAP): ...... 24 3.1 Gender Action Plan:...... 24 3.2 Activities with respect to Gender Action Plan: ...... 24 4. Public Consultations and Disclosure ...... 296 5. ANNEXURES...... 29 Annexure 1: IR and IP check list: ...... 29 Annexure 2: Photographs ...... 33 Annexure 3: Compensation Process...... 27 Annexure 4: Compliance to National laws and Policies: ...... 37 Annexure 5: Govt. Payment Reciept for STP Approach Road Land ...... 40 Annexure 6: Sale Letter for STP approach road...... 41 Annexure 7: Grievance Redressal Systems and process...... Error! Bookmark not defined.42 6. ABREVIATIONS ...... 43

1 | P a g e 29 Semi Annual Social Safeguards Monitoring Report - AIZAWL (July, 2015 – December 2015)

1. INTRODUCTION: The North Eastern Region Capital Cities Development Investment Program (NERCCDIP) envisages achieving sustainable urban development in the Project Cities of Agartala, Aizawl, Kohima, Gangtok and Shillong through investments in urban infrastructure sectors. NERCCDIP is funded by a loan via the Multi-tranche Financing Facility (MFF) of the Asian Development Bank (ADB). The primary objective of NERCCDIP is to promote economic development in 5-North Eastern Region States as stated through expansion of basic services such as water supply, sewerage, sanitation, solid waste management of the Capital Cities. The NERCCDIP will also strengthen the service delivery capacity of each State urban agencies and urban local bodies through management reform, capacity building and training. Safeguard Policy are the policies that require to “avoid, minimize or mitigate adverse environmental and social impacts” that may result from development projects. The Safeguard Policies adopt a so called, “do no harm” approach. Development projects that change patterns of use of land, water and other natural resources can cause a range of resettlement effects.

1.1 Implementation status of sub projects Tranche 2 in general

The work of water supply and sewerage is ongoing. The contractors so far have not encountered any complications/ issues. Work where social concern monitoring requirement required were as follows:

i) 3 RCC Reservoirs (Tanhril, Mualpui and South Hlimen): All works in the three locations have been completed. Reservoirs in three locations are completed.

ii) Water supply network: Pipe laying work for distribution and feeder main work is in progress. Distribution pipe laying work so far is been carried out at residential area where traffic volume is low. Accesses to house wherever disrupted are being provided with temporary backfill with soil or with wooden plank/sheet etc. Public consultations prior to start of work in particular area conducted with the Community, members of local council and NGOs Coordination with traffic police department is also been taken up. Wherever road block is required prior intimation to the Local Council of the area and all other offices, institutions etc. are given written information before start of work, followed by joint site inspection and discussion with all concern ensuring road diversions and other inconveniences likely to encounter during construction work. Restoration work wherever required are also being taken up once the pipe laying work of the area is completed.

iii) Dedicated Power Supply (I32Kv Sub-station at Dihmunzawl): The work of substation is being carried out at PHE Land hence, no private land is required. Site development work and Quarter construction at the verge of completion. Valuation Committee has finalised rates for tower locations and stringing area falling under private land. Consultations with all landowner had been carried out. Several joint site inspections with landowners were taken up for re-confirming of all tower locations.

iv) Community Toilet Blocks (10 Nos.): All toilet completed and open.

v) Sewerage Network: Work of pipe laying work for sewerage network were stop to avoid slippery road during the period in between August and September, restoration work were taken up instead. Several joint inspection and consultations were carried out before work resume. There has been no

2 | P a g e 30 complications nor issues encountered so far. Public and other line department are informed well in advance before start of work.

vi) Site Development work of STP and STP Approach road: Site development work is completed. Work of STP approach road is in progress.

1.1.1 Status of sub projects Tranche 3:

i) Solid Waste Management (SWM): Awareness regarding segregation of waste at household end is been taken up. Tendering of work is in progress. ii) Water supply: Feeder main & distribution network and GSR Contract ready for award. Work of WTP and approach road tendering is in progress. All required land has been finalised details mentioned in Water supply RP T-3. iii) Septage Management Pilot Project: Tendering of work is in progress.

1.2 Background and context of the report: This is the consolidated report on implementation of Social Safeguard Activities between July 2015 and December 2015, and is prepared in compliance with the ADB Policies. The report comprises activities performed under TRANCHE II only as TRANCHE I stand completed and TRANCHE III yet to commence. This report consists of the following content:

 The scope of activities and progress – An overview of project information  Implementation and institutional arrangements  Social safeguard Monitoring checklist  Monitoring and reporting arrangements for safeguards monitoring  Social safeguard activities - Update on RP and IP plans and implementation status  Summary of land acquisition (temporary / permanent) – Details of ownership of land  Status of Affected People: Land Requirement, Compensation and Rehabilitation ( systems, Plans, Details of affected persons , Validation and Verification of Affected persons (APs) , compensation decided / planned and progress on provision of compensation)  Compliance status – loan covenants, policy frameworks  Contractors compliance to safeguard norms and monitoring  Gender Action Plan (Activities during the period)  Annexure

2. Status of Implementation of sub projects under TRANCHE II with regards to Social safeguards:

A. The scope and progress of activities under Tranche 2 subprojects– An overview of project information and implementation arrangements:

Details of Subproject components are provided in Table 1:

Table 1: Scope and status of RP impact

Activity Site Scope of IR/RP Status of Status of Completi Implementation work in % on date and issues if any A. Component: Water Supply

3 | P a g e 31 Activity Site Scope of IR/RP Status of Status of Completi Implementation work in % on date and issues if any Construction of 3 1.Mualpui, No land All Works 100 Oct ground level RCC 2. acquisition successfully 2013 zonal tanks Tanhril required. All the completed 3. S Hlimen, 3 zonal tanks without any are proposed in issues and government complaints. lands which are vacant and free from any use. No IR Impact.

Booster Pump PHED land No IR Impact All Works 100 Jan successfully 2014 completed without any complications. Feeder Mains (WS) Existing No land  Prior to start of 37.88 Feb 2017 Water distribution- RoWs acquisition work 107.55 Km. required. Pipe consultations laying work is are carried along the out. existing road. No IR impact  No issue encountered so far Installation of Dihmunzawl Sub stations  Valuation 27.50 Nov 2016 dedicated power work carried out Committee supply system within PHE has finalized Land. rates for In case of land towers falling for towers and under private stringing land, land compensation to amicably. all private  No issue landowners for payment. No IR impacts. B. Component : Improvement of sewerage systems C. D. Sewerage network Along No land  Work is in 13.8 May consisting of 43.5Km existing road acquisition progress. 2017 including manholes side required. Pipe  No issue and ventilation shafts laying work is and all associated along the earthworks; and utility existing road. shifting No IR impact

Construction of 10 10 different No Private land  All 10 toilets 100 Oct 2015 community toilets in localities is involved in all completed few lots the locations. and open No IR Impact  No issue

4 | P a g e 32 Activity Site Scope of IR/RP Status of Status of Completi Implementation work in % on date and issues if any Construct1ion of Bethlehem Private land 66.09 May  All required STP (10 MLD) Vengthlang purchased from 2016 machineries (about 2 km one landowner. transported from the No IR Impact.  Work is in city) progress.

 No issue

Construction of Bethlehem Land purchased  Work of 74.43 Jan 2016 approach road to STP Vengthlang for approach approach and various non (about 2 km road. road started. physical items such from the Landowner has  No issue. as procurement of main city) been paid with goods. all necessary procedures. No IR Impact.

B. Implementation and institutional arrangements: The Ministry of Urban Development (MoUD) is the national level executing agency (EA) of the program. SIPMIU is responsible for overall program implementation, monitoring and supervision. SIPMIU has deputed a Social Development Officer exclusively for monitoring the programme. The DSMC team is working closely with SIPMIU Social Development Officer and resettlement officer for all the planning and implementation activities including internal monitoring and reporting. Roles and responsibilities are identified in the table no.2 below:-

Table 2: Institutional Roles and Responsibilities Activities Responsible Agency Sub-project Initiation Stage Finalization of sites/alignments for sub project SIPMIU/DSMC RP Preparation Stage Conducting Census of all APs SIPMIU / DSMC Conducting FGDs/meeting/workshops during SIA surveys SIPMIU / DSMC Categorization of APs for finalizing entitlements SIPMIU Conducting discussions/meetings/workshops with all APs & SIPMIU / DSMC other stakeholders for finalizing entitlements and rehabilitation packages Disclosure of final entitlements and rehabilitation packages SIPMIU / DSMC Approval of RP ADB Payment of compensation and assistance SIPMIU RP Implementation Stage Implementation of proposed rehabilitation measures SIPMIU/ RO Consultations with APs during rehabilitation activities SIPMIU/ RO Grievance Redressal Committee (Both at State level and City SIPMIU/ RO/GRC level) Internal Monitoring SIPMIU/DSMC External Monitoring External Agency AP=Affected person, VC=Valuation Committee, NGO = nongovernment organization, SIPMIU = state-level investment program management and implementation unit, IPCC = investment program coordination cell, RO = resettlement officer, RP=resettlement plan, SIA=social impact assessment.

5 | P a g e 33 C. Status of Institutional Strengthening of SIPMIU: Training workshop on Safeguards implementations on Social, Environment and Gender Sensitization (GAP) specially organized by ADB were successfully attended by the concern Engineers and Consultants. SIPMIU Deputy Program Director & Social Development Officer & DSMC Community Development Expert attended training program on GAP held at in between 11th &12th May 2015 organized by ADB. Safeguard Team of SIPMIU and DSMC also attended One day national conference on “Recent Advances Regarding Environment And Forest Laws” on 22nd May 2015 at Shilong organized by Ministry of Environment, Forest & Climate Change, North Eastern Region. The period from July 2015 to December 2015 several training program had been attended on different aspects, as of safeguards proceedings there had been one training during the period which is as follows: 1. Social Development Officer, SIPMIU, and Community Development Expert DSMC attended workshop on Safeguard Procedures organized by ADB in the month of July 2015 at Delhi.

Table 3: Monitoring Team:

Sl.No Name Position Contact Email Number

1 Valbuanga Program Director, SIPMIU 0389-2390532 [email protected]

2 Lalthanzuali Dy. Program Director, 9436155383 [email protected] SIPMIU

3 Dorothy Laldinpuii Social Development 9862538566 laldinpuiidorothy@gm

Officer, SIPMIU ail.com

4 Lalchhuantluangi Community Development 9862363797 [email protected] Officer, DSMC m

5 Lalhmuaka Asst. Engineer 9612195925 [email protected] (Environment &SWM), m SIPMIU

6 Rahul Kumar Environment Specialist, 07607440857 Rahulkumar_env@red DSMC iffmail.com

7 C.Dorema Evaluation & Monitoring, 9436144127 NA

6 | P a g e 34 DSMC

8 Ignatius Zomuankima Resettlement & 9436141236 [email protected] Rehabilitation Expert, m

DSMC

11 Jacob Lalfakzuala Asst. Engineer, cltconstruction2011@ Fanai Contractor, C.L.T gmail.com Construction

12 Martin Vanhmingmawia Asst. Engineer, Contractor, 8974728512 [email protected] Gangwal Engineering &

Construction Corporation Pvt. Ltd

13 Nipen Gogoi Asst. Engineer, 9612135358 [email protected]

Contractor, Tantia om Constructions Ltd

14 Shudhanshu Das Asst. Engineer, 9612850627 dasshudhangshu@gm Contractor, EMC Pvt. Ltd. ail.com

15 Maria Edward Jude Dy. Project Manager, 8575049131 ecoprotectionengineer Contractor Eco Protection [email protected]

Pvt Ltd.

7 | P a g e 35 2.1 Social Safeguard Monitoring Checklist – TRANCHE II Project Data Name of Project & NERCCDIP funded by ADB. Subproject comprises of water supply Subproject : and sewerage as part of NERCCDIP 1 Water supply 2. Sewerage 3. Solid Waste management Project Di sbursement Status Tranc he –II Rs.25, 00,000/- (Rupees Twenty Five Lakhs Only) for (%) : STP and Rs.80, 00,000/- (Rupees Eighty Lakhs Only) for approach road land and Rs. 50,000/- (Rupees Fifty Thousand Only) for UPC temporary structure. Type of contract :  Design-Build  Combined Safeguards Categorization A B C IR Entitlement matrix IP NA

A. Design and Engineering Status Item Status Follow up Type of Required Action (Y/ N) required (Y/N) Final detailed engineering design Y Y Updated draft IR/IP of the sub project completed  New RP/IPP preparation Changes in project design/ scope N N  Project re-categorization (IR/IP) (occurred or envisaged)  IR/IP Impact assessment  New RP/IPP preparation NA

B. Institutional Status Readiness No Item Status Follow up Completion (Ready/Not required Deadline ready/NA) (Y/ N) 1 Mobilization of civil works Ready Y May 2012 contractor 2 Mobilization of Project Ready N April 2010 Supervision Consultant 3 EA’s Safeguards Unit with Ready N February 2011 designated staff 4 Recruitment of External NA - Monitoring Agency

C. Safeguards Requirements No Item Status Follow up Completion Deadline (Ready/Not required ready/NA) (Y/ N) 1 Safeguards monitoring included in Ready Y Up to full completion of work the project progress report 2 Final/ updated RP/IPP 1 prepared Not Ready Y March 2015 and submitted 3 Project’s Grievance Redress Ready N Up to full completion of work Mechanism established 4 Recruitment of third independent Ready N November 2015 party for negotiated land acquisition 5 Project’s ESMS (for FI) Ready Y Up to full completion of work established D. RP/ IPP Monitoring Checklist 2

 1 Detail checklist for RP/IPP supervision provided in section D. 2 For project with multiple RPs/IPPs provide the status of each RP/IPP progress separately.

   Item Safeguards Related Requirements Status Completion Progress to Date/ No. (Ready/Not Deadline Remarks ready/ NA) 1.0 MANAGEMENT Institutional and Financing Arrangements 1.1 Financing and budget : (i) safeguard office and Ready Completed staff; (ii) RP/IPP cost

1.2 Establish Safeguard Unit: (i) resettlement Ready Completed SIPMIU has offices (ii)resettlement staff as in RP (iii) established safeguard safeguards’ database (iv) facilities (v) team safeguards training

Updating of DD/RP/IPP based on Detailed Design 1.3 Update DD/RP/IPP: (i) revise based on DMS (ii) Ready Submitted Completed revise implementation schedule (iii) revise budget

1.4 Compensation rates: (i) approved by Ready completed Rates fixed as Government; (ii) Adequate as per RP/RF; (iii) per current APs informed. market price in consultation with APs Disclosure and Grievance Redressal 1.5 Disclose final/updated RP/IPP: (i) to the APs in Ready Uploaded in Translated Copy of RP local language; (ii) in ADB website; (iii) in EA’s websites and IEE submitted in website state library and uploaded in SIPMIU Aizawl websites.

1.6 Disclose project activities to affected Ready On going Public communities: (i) put up a project sign boards; (ii) Consultation, distribution of project leaflets and GRM to awareness to affected communities all APs. Signboards put up.

1.7 Grievance redress committees: (i) clear terms Ready Completed Mechanism informed to of reference; (ii) appointment decree; (iii) APs publicly disclosed among APs. 1.8 Grievance redress records: (i) list and numbers NA No complaints received of grievances received; (ii) numbers of resolved so far issues; (iii) numbers of cases under GRC review; (iv) outstanding cases (filed to court)

Monitoring and Reporting Arrangements 1.9 Set up internal monitoring system : (i) Ready Completed SIPMIU/DSMC assessment on capacity and staff requirements; (ii) criteria of safeguards assessment ; (iii) reporting mechanism

1.10 Appoint external monitoring agency (as Not required NA NA relevant): (i) recruitment schedule; (ii) TOR; (iv) baseline survey (v) reporting mechanism (vi) action taken by management on reports.

9 | P a g e 37 1.11 Reporting: (i) frequency; (ii) timeliness; (iii) Same as NA Na identified issues; (iv) action taken above and/recommendation.

2.0 PR/IPP IMPLEMENTATION Consultation 2.1 Consultation: (i) responsibility; (ii)stakeholders Ready On going Consultations are Identified; (iii) consultation and process; (iv) ongoing with other documentation required action.

Mapping and Assets Inventory 2.2 AP Identity cards & affected assets records: (i) Ready Completed Since there is only one issuance and distribution of AP ID cards, (ii) AP so far in Tranche 2 detail measurements survey of affected assets no identity card had and documentation been issued. Measurement of land acquired completed.

2.3 Land acquisition activities: (i) maps of affected Ready Ongoing Completed for and relocation sites; (ii) acquisition & relocation sewerage and ongoing schedule; (iii) coordination with the asset’s for water supply acquiring, transfer and registration bodies

2.4 Common property/ public assets: (i) final Ready Completed No issue inventory; (i) restoration plan and schedule; (iii) funding sources

Compensation, Relocation and Rehabilitation 2.5 Payment of compensation and entitlements (as Ready Completed STP approach road stated in the RP): (i) schedule of payment; (ii) land purchased. records/ receipts of payment Ongoing for water supply 2.6 Relocation of process ( relocation site Ready Completed Completed readiness): (i) housing & associated facilities established; (ii) transfer of new land/plot/ house ownerships completed

2.7 Provision of (a) income restoration, (b) NA No APs are vulnerable. additional assistance for vulnerable APs, (c) training, etc. (as stated in the RP): (i) per type of activities; (ii) schedule of implementation Monitoring and Reporting 2.8 Submission of the reports: (i) semiannual Ready Completed Submission is monitoring reports; (ii) external monitoring and being carried evaluation reports (as required); (iii) completion out in time report

2.9 Transfer of acquired assets to the acquiring Ready STP land Is in progress agency completed. Approach road outstanding and tower land

10 | P a g e 38 A. Safeguards Loan Covenants Sl POLICY PRINCIPLES COMPLIANCE STATUS

I 1.Land Acquisition and Involuntary Resettlement: (Sch. 5 Para 19 &20) 1 The Borrower and the State shall ensure that all land and This is addressed in the RF. The all rights-of-way required for the project, and all Project locations for project components have facilities are made available to the Works contractor in been identified in such a manner that accordance with the schedule agreed under the related IR is avoided to the extent possible. Works contract and all land acquisition and resettlement These IR impacts shall be further activities are implemented in compliance with Involuntary minimized during construction resettlement should be avoided where feasible.

2 Where population displacement is unavoidable, it should This is addressed in the RF. The be minimized by exploring viable project options. locations for project components have been identified in such a manner that IR is avoided to the extent possible. These IR impacts shall be further minimized during construction

3 If individuals or a community must lose their land, means The RF addresses the IR impacts. The of livelihood, social support systems, or way of life in entitlements to the APs are outlined in order that a project might proceed, they should be the Entitlement Matrix. compensated and assisted so that their economic and social future will generally be at least as favorable with the project as without it. Appropriate land, housing, infrastructure, and other compensation, comparable to the without project situation, should be provided to the adversely affected population, including indigenous groups, ethnic minorities, and pastoralists who may have usufruct or customary rights to the land or other resources taken for the project.

4 Any involuntary resettlement should, as far as possible, The RF addresses the IR impacts. The be conceived and executed as a part of a development entitlements to the APs are outlined in project or program and resettlement plans should be the Entitlement Matrix. prepared with appropriate time-bound actions and budgets. Re-settlers should be provided sufficient resources and opportunities to reestablish their homes and livelihoods as soon as possible.

5 The affected people should be fully informed and closely Consultations have been carried out Consulted on resettlement and compensation options. with APs. This will be further Where adversely affected people are particularly consolidated by the RP implementing vulnerable, resettlement and compensation decisions NGO. The plan for should be preceded by a social preparation phase to information disclosure in the project, build up the capacity of the vulnerable people to deal with including the RF. the issues.

6 Appropriate patterns of social organization should be This is addressed in the Entitlement promoted, and existing social and cultural institutions of Matrix. re-settlers and their hosts should be supported and used to the greatest extent possible. Re-settlers should be integrated economically and socially into host communities so that adverse impacts on host communities are minimized. One of the effective ways of achieving this integration may be by extending development benefits to host communities.

7 The absence of formal legal title to land some affecte d The process of verification of impacts groups should not be a bar to compensation. Affected and establishing the eligibility of the persons entitled to compensation and rehabilitation APs is outlined in the RF.

11 | P a g e 39 should be identified and recorded as early as possible, preferably at the project identification stage, in order to prevent an influx of illegal encroachers, squatters, and other nonresidents who wish to take advantage of such benefits. Particular attention should be paid to the needs of the poorest affected persons including those without legal title to assets, female-headed households and other vulnerable groups, such as indigenous peoples, and appropriate assistance provided to help them improve their status.

8 The full costs of resettlement and compensation, The Resettlement Framework including the costs of social preparation and livelihood addresses the IR impacts. The programs as well as the incremental benefits over the entitlements to the affected persons are “without project” situation, should be included in the outlined in the Entitlement Matrix. presentation of Project costs and benefits.

9 To better assure timely availability of required resources The impacts have been assessed and and to ensure compliance with involuntary resettlement Resettlement Plan costs according to procedures during implementation, eligible cost of the entitlement matrix have been resettlement and compensation may be considered for worked out. These costs are included in inclusion in Bank loan financing for the project, if the Project Costs. requested.

II Indigenous Peoples (Sch 5 Para 21) 1 The Borrower and the States shall ensure that the Although about 93% of the state preparation, design, construction, implementation and population belongs to ST. The capital of operation of the Project and all Project facilities comply Aizawl having urban outlook and that with (a) all applicable laws and regulations of the the project being urban project, people Borrower relating to indigenous peoples; (b) the living in Aizawl including all affected Indigenous Peoples Safeguards; (c) the IPPF; and (d) all persons lives in urban area and do not measures and requirements set forth in the respective exhibit primitive or distinct indigenous people's plan, and any corrective or characteristics of that are considered to preventative actions set forth in a Safeguards Monitoring be Indigenous Peoples as far as ADB’s Report. definition is concerned. However, ST households in the project have been considered for which provision for additional assistance have been provided in the entitlement matrix.

III Human and Financial Resources to Implement Safeguard Requirements (Sch 5 Para 22)

1 The Borrower and the States shall make available The required budget is mentioned in necessary budgetary and human resources to fully the RP. implement the environmental management plan, the resettlement plan and the indigenous peoples' plan IV Safe guard-Related Provision in Bidding Document and Works Contracts (Sch. 5 Para 23) The Borrower and the States shall ensure that all bidding documents and contracts for Works contain provisions that require contractors to:

i) comply with the measures and requirements relevant to The Contractor is reminded and well the contractor set forth in the IEE, the environmental informed of the fact during site management plan, the resettlement plan and the inspection. Instruction in writing is also indigenous peoples' plan (to the extent they concern issued. impacts on affected people during construction), and any corrective or preventative actions set out in a Safeguards Monitoring Report;

ii Make available a budget for all such environmental and As mentioned in the contract tender social measures; condition the contractor complies.

12 | P a g e 40

iii Provide the Borrower and the relevant State with a Untimely and heavy monsoon had written notice of any unanticipated environmental, caused few locations with land slips resettlement or indigenous peoples risks or impacts that where water supply pipe had already arise during construction, implementation or operation of been layed. All such monsoon the Project that were not considered in the IEE, the damaged location had been restored environmental management plan, the resettlement plan immediately by providing slope or the indigenous peoples' plan; protection wall. iv Adequately record the condition of roads, agricultural This is considered. As in case of land and other infrastructure prior to starting to transport Tanhril, south Hlimen and Mualpui materials and construction; and approach road were developed for transporting construction materials. v Fully reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction;

V. Safeguards Monitoring and Reporting (Sch 5 Para 24)

The Borrower and the States shall do the following: i Submit semi-annual Safeguards Monitoring Reports to This is complied. ADB and disclose relevant information from such reports to affected persons promptly upon submission; ii If any unanticipated environmental and/or social risks and Due to change in STP approach road impacts arise during construction, implementation or location and other changes, IEE and operation of the Project that were not considered in the RP were revised and submitted in IEE, the environmental management plan, the March 2015 for approval. resettlement plan or the indigenous peoples' plan, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan; iii Report any actual or potential breach of compliance with So far not encountered. the measures and requirements set forth in the environmental management plan, the resettlement plan or the indigenous peoples' plan promptly after becoming aware of the breach.

VI. Prohibition List of Investments (Sch 5 Para 25) The Borrower and the States shall ensure that no No activities are involved referring to proceeds of the Loan are used to finance any activity the SPS 2009 Appendix 5. included in the list of prohibited investment activities provided in Appendix 5 of the Social Policy Statement 2009 (SPS 2009)

VII. Other Social Issue s (Sch 5 Para 26, 27 & 28) i The Borrower and each State shall ensure to fully The Gender action plan is been carried implement the gender action plan for the Investment out. Quarterly Report is submitted Program as it applies to the Project. regularly. ii The Borrower and the States shall ensure that all civil Complied. Signboard poster is being works contractors comply with all applicable labor laws, put up at work area on gender equality including those on occupational health and safety, equal (same-pay-for-same-work). Contractors pay for work of equal value between men and women, are asked to obtained certificate from and do not employ child Labor, as defined in national the particular local council for not legislation, for construction and maintenance activities. practicing child labor. iii Each State shall retain the grievance reporting and The GRC is formed and the mechanism redressal mechanism established under the first project. also established..

13 | P a g e 41

Overall Status of Compliance

 

Not complied – Redressed Complied with further Fully complied – no further action & monitoring required monitoring action

2.2 Monitoring indicators and status report  S.N R&R Activities Progress Remarks Pre Construction Activities and R&R Activities. 1. Assessment of Resettlement New STP approach road Shifting of STP impacts due to changes in land purchased approach road project design (if required) 2. Preparation/ updating of RP revision completed -do- Resettlement Plan based on changes in project design 3. Approval of updated Approved Resettlement Plan from ADB 4. Disclosure of updated Taken up RP in local language Resettlement Plan uploaded in websites 5. Establishment of GRC GRC established 6. Capacity Building of SIPMIU Safeguard Training by ADB Training on attended by SIPMIU and Safeguard DSMC procedures during the period. 7. Land Acquisition Approach road negotiated Purchase rate as per purchase current market rate. Resettlement Plan Implementation 1 Payment of Compensation as One family (Non-title) House provided to per replacement value of land affected for STP approach the displaced family & assets to DPs road shifted to newly is in better condition constructed house. compared to the old house. 2 Disbursement of assistance to Amount paid as per STP approach road title holders demanded by landowners considering the current market value. 3 Disbursement of assistance to Anticipated temporary Water supply non title holders impact identified during pipeline and 100% survey is being sewerage. avoided with EMP mitigated measures. 4. Disbursement of assistance to -do- -do- Vulnerable groups 5 Replacement/ shifting of STP approach road Shifted community property resources encounters one temporary structure. 6 Reinstallation of public utilities On going for WS pipe work In progress 7 Records of Grievances Ongoing, Continuous No complaint

   Redressal monitoring registered so far 8 Temporary Relocation of Not yet encountered since Work area is in Hawkers and Vendors work around residential residential area, areas is in progress 9 Income restoration Measures N.A. Yet to be taken up through training Social Measures during Construction as per Contract Provisions 1 Prohibition of employment or Inspection is carried out at No child labour use of children as labor the contractors work site. encountered so far. Laborers are often checked for the same. Contractor’s representatives are reminded during site inspected regarding the same. 2 Prohibition of Forced labor or NA No issue. Compulsory Labor 3 Ensure equal pay for equal Ensured. Contractors are Women work to both men and women made aware of equal Constructional labor payment for men and in context to Aizawl women. is rare. However, “Gender Sensitization” was some changes have conducted for SIPMIU & been seen which Other Line Deptt. On 21st probably must have Dec 2015. been the outcome of the entire awareness and consultations program. Since, in every awareness and consultations ADB’s GAP is always included. 4 Implementation of all statutory Regular monitoring. Labourers are provisions on labor like health, Previous semiannual conscious regarding safety, welfare, sanitation and period, HIV Awareness was health safety. working conditions conducted with free medical checkup. 5 Maintenance of employment Contractors are found to Taken up. records of workers maintained proper attendance sheet.

2.3 Monitoring and reporting arrangements Regular monitoring activities are being carried out for assessing resettlement progress and identifying potential difficulties and problems. The extent of monitoring activities includes their scope and periodicity to commensurate with the project’s risk and impacts.

(i) The status of the sub-project work under Tranche-2 is ongoing. Monitoring system taken up under the following: a. Administrative monitoring to ensure that implementation is on schedule and problems are dealt with on timely basis. b. Socio-economic monitoring during and after resettlement impact utilizing baseline information established through the socio-economic survey undertaken during project sub-preparation. c. Overall monitoring to assess status affected persons.

15 | P a g e 43 (ii) Activities involved in implementing safeguard measures and plans, monitoring the progress of implementation of safeguard plans, verifying the compliance with safeguard measures and their progress toward intended outcomes, document and disclose monitoring results and identify necessary corrective and preventive actions in the periodic monitoring reports, follow up on these actions to ensure progress towards the desired outcomes and submit semi- annual monitoring reports on safeguard measures as agreed with ADB.

(iii) The implementation of the RP monitoring and progress is being recorded. Regular monitoring activities are being carried out. The extent of monitoring activities, including their scope and periodicity, is being examined with the projects risk and impacts.

2.4 Summary of Resettlement impacts and socio-economic details under water supply and sewerage sub project: Table 5: Summary of Resettlement Impacts and Socio-Economic Details

Impacts Quantity Water Supply Sewerage System Permanently Land Acquisition (ha) 1635.9sqm 2.44 Permanently Affected Households 14 1 Permanently Affected Persons 105 6 Temporarily Affected (HHs) (132kVA Stringing area) 5 0 Titled Affected Households 14 0 Vulnerable Households 0 0 Affected Trees/Crops 0 20 +89 (89 for new STP Approach road) Average Family Size for permanent affected HHs 8 6 Average Household Income (per month) for 40000 6600 permanent affected HHs (Rupees) Income Sources for Temporarily Affected business Small business Small business establishments establishments such as petty such as petty business mostly business mostly general stores. general stores. However, there Temporary will be no impact to access temporary will be mitigated impact. as per EMP.

In Mizoram 93% of the people are schedule tribes, and people living in Aizawl city with urban life style having different occupational work such as Government servant, business, private employment, etc. Scheduled Tribes in the project covered area do not exhibit primitive or distinct characteristics of that Indigenous Peoples as far as ADB’s definition is concerned. However, Poor FHHs, households Below Poverty Level, in the project have been considered as vulnerable group for which provision for additional assistance have been provided in the entitlement of the Resettlement Plan.

2.5 Status of the affected people: Land requirement, Compensation and Rehabilitation in Water Supply and Sewerage Sub Projects in TRANCHE II:

1. Water Supply: (i) Dedicated power supply requires installation of 132KvA substation at Dihmunzawl. The proposed substation site is within PHED land (govt Land). 132KvA power is proposed to connect from Luangmual Substation, Power & Electricity Department

16 | P a g e 44 Govt of Mizoram. To cover the distance between proposed substation site and Luangmual substation about 21 towers erection is required. Proposed tower locations of 4 nos belong to government and the rest 17 belongs to private owner. Private land measuring maximum 112.36sqm and minimum 67sqm at 17 locations measuring total area of 1635.9sqm from 14 landowners. Besides land for tower construction 5 Landowners land will also be affected during overhead stringing between towers. Rates for each tower land had been finalised in the second sitting of Valuation Committee. Since, proposed tower types varies in sizes accordingly area land required also differs. Valuation Committee therefore, had fixed to Rs. 200,000/- for the maximum area land required. Thus, deriving cost of area for 1sqm @ Rs.1779.99/- Government approval had been obtained and payment to all landowners is to be completed before March end 2016.

2. Sewerage: (i) Land acquired for STP site has been completed and work of site development is almost completed as mentioned in the previous report. Land for STP approach road has also been finalised. The site has been finalized with consultation with the land owner, local NGOs and Local Council. The owner of the land is the same landowner who owns the STP site.

(ii) Socio economic profile of landowners for tower reveals that all landowners lives in city area and are all integrated to the main stream of urban life with occupational pattern that is of urban in nature. None of the landowners falls under ADB’s vulnerable HHs category. Therefore, none of the landowners fit into the criteria of IP. Agricultural activities in around the proposed locations have been noticed but there will be no impact to any land from the construction work.

(iii) Socio economic information provides that total loss of 2.44 Ha (i.e including STP approach road) of land had been purchased for STP site. Land as verified on ground is not in use. Hence, it will not disturb present livelihood of the landowner. One physical displacement at the proposed approach road. The displaced family has been consulted jointly. The landowner has provided another suitable location where new structure had been constructed nearby as per the choice of the affected family and landowner. The displaced family have been shifted to the new house. New structure is better than the previous condition has been provided to the displaced family. (iv) Consultations with the displaced family carried out jointly with Local Council member. (v) Landowner agreed price had been paid for the STP approach road land. (vi) Detail of Landowner is shown in table 6

Table 6: Details Socio-economic profile of Affected Persons:

S. Name of Affected Age HH Income Whether House Whether Monthly Remarks N landowners type size source s of vulnerable type tenant Income HH (INR)

Water supply (for 132 KvA Tower Land)

70.56sqm 69 9 Private *No RCC No Above Also has for 132kVA Business 20,000 income 1 Mr. Kapkunga Tower and works in from company farming

17 | P a g e 45 112.36sqm 65 3 MRF tyre *No RCC No Above Daughter 2 Mr. K for 132kVA agent & 60,000 works in tower resoling wife college

Rohmingliana pension

Mrs. Lalkhumi 70.56sqm 65 4 Business *No RCC No Above Income w/o Mr. for 132kVA and boarding 50,000 also from 3 Saizahawla Tower school also house rent. husband pension

4 67.24sqm 52 8 Business No Semi No Above Import of Mr. for 132kVA RCC 10,000 goods from Lalchhanchhuaha Tower other state for selling

112.36sqm 6 Govt *No RCC No Above 5 Mr. Zahlira 79 & pension and 30,000 70.56sqm departmental (2 store and locations) house rent

Mrs. 104sqm of 6 Govt No RCC No Above Son has 6 land for pension 50,000 tractor 68 Lalrintluanga w/o 132kv (Agriculture showroom ,photo R. Thansanga (L) tower Deptt. printing, Director) and restaurant,

School & computer

shop

112.36sqm 5 Private No RCC No Above 1 7 Mr. R. Lalthanliana of land for 53 Business lac 132kv (Hardware

tower shop)

Mrs. 67.24sqm 7 Meat Shop No Semi No Above Husband 8 Lalruatthangi of land for 56 and farming RCC 20000 132kv works

tower

67.24sqm 7 Same as No Same No Same Husband 9 Mr. Luangmuankima of land for 53 above as as of the above sl. No. 8 132kv above above tower

10 Mr. Lalrinsanga 70.56sqm 42 6 JE (PHED) No RCC No 30,000 of land for Govt service 132kv tower

18 | P a g e 46 11 92.16sqm 50 4 LDC, Govt No RCC No 40,000 Husband Mrs. & Service and retd. as Saichhingpuii 86.49sqm Husband Deputy (2 pension. Director,

locations) Govt of Mizoram

12 104.04 50 14 Govt service. No RCC No 30,000 Father retd. Mr. Kenedy R. sqm for govt Malsawma 132kVA pension tower

13 70.56 sqm 43 15 Father CE, No RCC No Above Mr. Francis for 132kVA PHED 60,000 Zoremsanga tower Pension, House rent & Book shop

70.56 sqm 68 11 Teacher *No RCC No 50,000 Also has 14 Mrs. for 132kVA Pension shop. No Thanchungnungi, tower Children Tuikhuahtlang lives with brother

who is like

her son

works as SDO, PWD.

Water Supply (for 132 kVA Stringing area between towers)

15 Mr. Liansuma String area 70 6 Ex. MLA *No RCC No Above 50,000

Same as 5 Business *No RCC No Above 1 Wife works 16 Mr. David Zama 61 above lac as professor in

17 Mr. Same as 40 4 Business No RCC No Above Income Vanlalnuntluanga above and boarding 50,000 also from (Tluangtea) school house rent.

18 Mr. Lalngaihsaka Same as 44 4 Pension and No Semi No 30,000 S/o Mr. above Water tanker RCC Sangkhuma (L) business

19 Mr. Rualkhuma Same as 60 7 Workshop *No RCC No Above above and house 50,000 rent

Note: Female name mentioned in the above list does not fall under the category of vulnerable since all are well established with support from husband.

19 | P a g e 47 Sewerage

1 1.015 Ha 66 6 Pension and *No RCC No 20,000 Daughter Mr. land for house rent works in Chawngthanga STP Health Department

0.3624 Ha 2 Same as above -do- -do -do- -do- -do- -do- -do- -do- land for STP approach road

Note: * Considering the age the APs above 60years are all in better living conditions, good family support and lives in Aizawl city with good medical facilities, hence they are not vulnerable.

2.6 Land requirement, Compensation and Rehabilitation in SWM Sub Project (Tranche 3) Land required for solid waste management (SWM) is estimated about 5.64ha under Tranche 3. However, 12.95ha of land had been acquired considering the need for future expansion (after 5 years) from 2 landowners, 3 government land lease and government land.

2.7 Permanent land acquisition and ownership details under Solid Waste Management sub project Tr-3: The proposed Land is approx 20kms away from Aizawl city located near village with an area measuring 12.95ha. Compensation amount had been paid after consultation with all landowners who had no objection and all willing to sell their land. The details of RP for acquisition had been mentioned in the SWM Resettlement Plan (RP) submitted earlier. Land is not in any use. A total of 395 non fruit trees (comprising of young tree plants) will be affected. Section -4 under the Land Acquisition Act (LAA) has already been issued. Following the issuance of the section - 4, the land had been acquired on a mutual consent basis. The rate of the land had been finalized on a mutual basis which was further evaluated by an independent third party. Details of the land are given in Table-7.

In accordance with the involuntary resettlement principles set forth above, the identified affected persons have been compensated.

Socio – economic information:  A total of 5 households are affected due to the land acquisition which will have a total of 34 affected persons (APs). Socio-economic survey was conducted. The average size of each household in the project area is 5 to 6 members.

 All of the affected household and their family members are literate. Socio-economic survey reveals that income level of affected household ranges from a maximum 50,000 to minimum 25000 per month. No household falls under BPL category or fall under the ADB category. None of the households belong to women headed and below poverty line. However, all the 5 affected households belong to scheduled tribe as more than 95% of the population in Aizawl is scheduled tribe. These tribal groups are integrated to main society and hence they are not considered as indigenous people. Majority of the households preferred cash compensation as resettlement options. Summary details are given in Table 7.

20 | P a g e 48 Table 7: Summary of resettlement impacts and socio-economic details Solid Waste Management sub project Tr-3:

Table 7: Socio-economic profile of Landowners

Name Age Affected Fam Main Other Cash (Household Type ily income) Monthly Size Mr. 70 Land 6 Pension House 50,000/- B.Bualchhuaka acquired rent Mr. 65 -do- 7 Business House Above 40,000/- B.Dawngliana rent Mr. 40 -do- 9 Variety Taxi 25,0000/- Lalchhuana shop Mrs Lalzawni 39 -do- 7 -do- -do- Mr. Ramzauva 50 -do- 5 Fish 30,0000 business

Source: Survey of AP, February 2011

Table 8: Summary Details on census and socio-economic survey

Impact Quantity Permanent Land Acquisition 12.95 Hectares Permanently Affected Households 5 Permanently Affected Persons 34 Temporarily Affected businesses (HHs) 0 Titled Affected Households 5 Vulnerable Households 0 Affected Trees/Crops 395 Average Family Size for permanent 6 affected HHs Average Household Income (per month) 30000 for permanent affected HHs (Rupees)

2.8 Status of land acquisition for Tranche-3: A payment to all the landowners under the agreed rate has been made through Competent Authority (DC of Aizawl). Allotment of land to Urban Development and Poverty Alleviation (UD&PA is in progress with the Revenue Department. The Land Revenue & Settlement Department had issued Provisional Certificate of Land dated June 2014 for the acquired land with the following conditions:

1. Properly demarcated with the assistance of Revenue Department using boundary pillars prescribed by the Revenue Department. 2. Boundary wall/ fencing as per requirement for land lease by Revenue Department had been taken up. 3. Land lease process is in progress.

2.9 Rag Pickers: Tranche 3 project consisted of solid waste management, landfill adjacent to the existing dump sites. 100 % survey conducted at the existing AMC dump site for identifying Rag Pickers. 59 Rag Pickers identified out of which 33 numbers are full time rag pickers and the rest 26 are part timers. All interested Rag pickers willing to work will be recruited in the new land fill site and also those who are willing to work

21 | P a g e 49 as daily wagers will also be employed during the construction. This is to ensure that none of the Rag pickers livelihood is affected.

2.10 Status of Contractors Social Safeguards Compliance: Contractors of all sub- project work under Tranche 2 have started work. Contractor’s representatives are made aware of the safeguard concern. Contractors work description and measures, instruction and status of safeguard compliance is stated in the following table:-

Table 9: Status of Contractors Safeguards Compliance Requirements:

Sl. Work Measure s/ Instructions Status/ Remarks No Description Requirement During Inspection & Location 1 STP Site i. Workers health i. Contractor’s i. Contractor partially complying with Development safety and representatives the instructions regarding work and facilities were shown the protective gears of workers. Approach ii. Socio economic extent of land road. employment. purchased for Bethlehem iii. Facilitate Gender STP approach Vengthlang equality road prior to start iv. Not to encroach of work. on any private land beyond acquisition. 2 Construction As above i. All works i. Works completed and all of 3 RCC completed restoration work has also been Zonal Tank completed as already reported in at the previous report. Tanhril, Mulapui and South Hlimen. 3 Water supply Proper barricading, i. Provide So far not encountered any distribution signboard, sinages temporary complications. Safety barricades are network for road user and access with provided as per site requirements. provide temporary wooden planks Regular monitoring is being carried access path etc. during out. construction. ii. Provide safety barricades and sinages and take up consultations prior to any locations that are likely to encounter problems. 4 Construction Workers health i. Substation work No issue of 132 KV safety and facilities. is being carried sub-station out within govt at premises hence Dihmunzawl. no much issues encountered so far. Contractor has been asked to provide sianges and all other safeguard

22 | P a g e 50 requirements. 5 Sewerage Proper barricading, Contractor had Prior consultations and joint site network signboard, sinages been asked to visit with contractors had been for road user and provide all safety useful since all measures provide temporary measures. Proper requirement is taken up before start access path sinages and of work. Hence, contractor provide temporary complies. access wherever required 6 Community All construction are i. No issue. All completed. No issue. Toilet Blocks been carried out at (10 nos.) govt land with one NGO land.

2.11 COMPLIANCE TO NATIONAL LAWS AND POLICIES (POLICY AND LEGAL FRAME WORK): The policy framework and entitlements for the Program are based on national laws: The Land Acquisition Act, 1894 (LAA, amended in 1984) the National Resettlement and Rehabilitation Policy, 2007 (NRRP); and ADB’s Policy on Involuntary Resettlement, 1995. The salient features of Government and ADB polices are summarized in Annexure 3:

2.12 GREIVANCE REDRESSAL SYSTEMS AND MECHANISMS Grievance redressal Committee (GRC) is in place. The GRC comprises of the Investment Program Director, RO, and Land Acquisition Officer (LAO), implementing NGO representative, female and male AP representatives (including vulnerable households) and an eminent member of the community. Details of the GRC is given below in table no 6.

Table 10: Grievance redressal committee:

STATE LEVEL 1 Minister, UD&PA Department, Chairman Mr. Zodintluanga, Minister Mizoram 2 Deputy Commissioner Convener Dr. Franklin Laltinkhuma, IAS 3 Secretary, UD&PA, Govt. of Mizoram Member Dr. Vanramsanga, IES 4 Secretary, Law and Judicial Member Mr. P. Singthanga, MJS Department 5 CEO, Aizawl Municipal Council Member Mrs. Ethel, MCS 6 Project Director, SIPMIU Member Er. Valbuanga, CE, PHED CITY LEVEL 1 Deputy Commissioner, Aizawl Chairman Dr. Franklin Laltinkhuma, IAS 2 Project Director, SIPMIU Convener Er. Valbuanga, CE, PHED 3 CEO, Aizawl Municipal Council Member Mrs. Ethel, MCS 4 Councillor of concern ward Member Concern AMC Councilor 5 Chairman of concerned Local Council Member Concern Local Council Chiarman 6 Chief Engineer, PHED Member Mr. R. Lalthanliana 7 Chief Engineer, PWD Member Mr. John Rammawia 8 Director, UD&PA Member Mr. Zorammuana, MCS 9 President Central YMA Member Mr. Lalbiakzuala 10 President, MUP Member Mr. K. Malsawma 11 President, Mizoram Consumer Union Member Mr. Thanglura 12 President, MHIP Member Mrs. Lalthlamuani Note: As regards to grievances no issue/s has been encountered so far.

23 | P a g e 51 3. ACTIVITIES CARRIED OUT WITH RESPECT TO PUBLIC PARTICIPATION OF GENDER ACTION PLAN (GAP): 3.1 Gender Action Plan: Public consultation prior to start of work in a particular area/locality always included mentioned of GAP in brief. It is always informed that interested women wanting to work in the constructional work is always welcome. This inclusion of GAP in the consultation topic had made great deal of awareness in the project area, a platform for interested women workers wanting to work as daily wager.

3.2 Activities with respect to Gender Action Plan: (i) Conducted ‘Gender Sensitization Workshop for SIPMIU & Other Line Departments’ at Aijal Club on 21st December 2015. The workshop was divided into 2 sessions. In the first sessions Program Director Mr. Valbuanga delivered short speech welcoming all participants along with project status and importance of ADB’s gender sensitization while implementing the project work. Miss Lucy Maruati Co-ordinator Gan Sabra, Aizawl gave a inspiring power point presentation on ‘Gender Discrimination in Mizoram (Urban Aspect)’. In the Second session Mr. Michael Lalneihtluanga, Social Development Specialist, UD&PAD delivered power point presentation on ‘Status of Women in Urban Sector’. Mr. Ignatius Zomuankima R&R Expert, DSMC emphasised presentation on ‘ADB’s Gender Requirement for Project’ and the importance of GAP and its implementation. The workshop concluded after short group discussion with all the participants.

24 | P a g e 52 (ii) Women constructional labour deployed in the ongoing sewerage network pipe laying and road restoration work. Most of the women were interested to work until work went on within their respective locality. However, there were few interested women workers who wanted to continue beyond their locality were also being employed.

Women daily wager working in the sewerage network work

25 | P a g e 53 4. PUBLIC CONSULTATIONS AND DISCLOSURE: 4.1 Consultation, Information Dissemination, Disclosure Public meetings and consultations had been conducted in educating the project covered area. During these consultations not only the project proceedings are informed but as well the compensation mechanism of the entitlement matrix is also discussed.

Table 9: Summary of Public Consultations: Date/Mont Location No. of Type of Topics Discussed Issues Raised/ h Participants Participants Findings

Water Supply

12th YMA Hall M-165, F- 67 Local Council 1. Water supply 1. The house September Govt members, household connection is 2015 Complex NGOs from the connection proposed for 2. Project work, Locality, 1 existing only, proceedings representative participants and its from each benefits. requiring new house, PHED connection representative. 3. Contractor may apply to work program, PHED for public those newly grievances constructed mechanism, house. 2. Road 4. Women labour restoration. will be equally 3. The paid as men for equal work participants were also are aware of informed the projects during the and all the consultations. other safeguards 5. ADB procedures. Safeguard Procedures Sewerage

1st October New M-7, F-6 Members from 1. Route 1. Shortage 2015 Market New Market diversion for possible Line Bus Line Bus Owner bus service duration of owner Association, and vehicle work in the association Traffic Police, for sewerage particular Chairman‘

s Local Council pipe laying stretch. residence, Members work. 2. Identified Chhinga Bethlehem suitable route Veng. Veng. 2. Identification for buses of possible during route for construction of diversion work. with minimal impact.

3. ADB Safeguard

26 | P a g e 54 Procedures

nd 2 October YMA Hall, M-115, F-44 Resident locality 1. Project work 1. The 2015 Armed members, Local and benefits participants Veng Council and along with are aware of NGOs Contractor’s the projects work plan. and all the 2. Project other procedure for safeguards sewerage procedures. works related. 2. Explanation 3. Information regarding regarding road GRC, priority restoration. for interested female workers and ADB safeguard proceedings. 4. Traffic diversion 9th October Sport M- 36, F- 17 Resident locality 1. Project 1. Road 2015 Complex, members, Local procedure for restoration on Chite Council and sewerage immediate Veng NGOs works related basis after pipe and STP laying is 2. Road completed. restoration work 2. Understand the 3. Information project regarding procedures, GRC, priority safeguard for interested aspects and female GAP. workers and ADB safeguard proceedings. 4. Traffic diversion Solid Waste Management (SWM)

4th Vanapa M- 93, F- 60 83 Local Council 1. Kick-off- 1. Arrangement December Hall Representatives Program on of vehicle 2015 , PHED, AMC, Source regarding Trade & Segregation waste Commerce on Solid collection Deptt, UD&PA Waste 2. Understand Deptt. Resource the SWM Management, project and Aizawl City. procedures.

27 | P a g e 55 2. Household segregation and introduction of two bins for dry and wet. 3. Public Private Partnership (PPP) mode 4. ADB Safeguard Procedures Between 21 Local One One 1. Household 1. Understand 7th Dec Council representativ representative segregation dry and wet 2015 to Areas e from each from each and waste and introduction o f importance of 18th Dec house as per house, Local two bins for segregation at 2015 size of locality Council dry and wet. household members, Ward 2. Importance o f end. Councillor SWM project. 2. Garbage 3. ADB bags, Safeguard collection time Procedures and vehicle arrangements .

28 | P a g e 56 5. Annexure: Annexure 1: IR and IP check list: INVOLUNTARY RESETTLEMENT AND INDIGENOUS PEOPLE SCREENING CHECKLISTS

A. Information on project/subproject/component:

a. District/ Administrative Name: Aizawl

b. Location: Aizawl City

c. Civil work dates (proposed):

d. Technical Description: Tranche-II: Construction of GSR, Water supply Network, Sewerage Network, and STP, construction of community toilets, 132kv sub-station. B. Screening Questions for Involuntary Resettlement Impact

2. Below is the initial screening for involuntary resettlement impacts and due diligence exercise.

Involuntary Yes No Not Known Remarks Resettlement Impacts Will the project √ include any physical construction work? Does the proposed √ The approach road activity include for Tanhril, Hlimen upgrading or and Mualpui was rehabilitation of rehabilitated for future existing physical use by Church, public facilities? and Orphanage Home respectively and have been successfully completed. Will it require √ Land acquired for permanent and/or STP site and STP temporary land approach road. Is the ownership √ All land is free from status and current any use. No owner usage of the will be affected from land known? acquisition. Are there any non- √ titled people who live or earn their livelihood at the site or within the corridor of impact (COI) / Right of Way (ROW)? Will there be loss of √ One is affected at the housing? STP approach road.

29 | P a g e 57 Will there be loss of √ agricultural plots? Will there be losses √ Only wild trees of crops, trees, and fixed assets (i.e. fences, pumps, etc.)? Will there be loss of √ As per EMP businesses or mitigation measures enterprises? there will be no impact Will there be loss of √ -do- incomes and livelihoods? Will people lose √ During pipe As per EMP access to facilities, laying mitigation measures services, or natural there will be no resources? impact Will any social or √ economic activities be affected by land use-related changes? Are any of the √ affected persons (AP) from indigenous or ethnic minority groups?

30 | P a g e 58 Annexure 2: Photographs: Public Consultation/ Awareness are taken up in every locality before start of work.

(i) Photo showing one of such public consultation program with Local Council’s members, NGOs and residents prior to start of house connection under water supply at Govt. Complex area. Total participants 232.

(ii) Public Consultation (FGD) with Line Bus Association prior to start of work for sewerage network since little route diversion required for pipe installation work. Discussion and identification of diversion route. Participants from Line Bus Association members, Local Council Members and Traffic Police attended the program.

(iii) View Showing STP Work Progress:

31 | P a g e 59 (iv) Photo showing STP Approach road.

(v) Photo Showing Precast Manhole being fabricated and used to ensure less time in sewer pipe installation work and restoration work:

(vi) Photo showing old road restored for diversion for road user before closing road for feeder main pipe line work under water supply sub project work. This action was initiated as per joint meeting outcome:

Existing Diversion road restored

Existing Diversion road condition Road blocked for feeder main after diversion road was restored.

32 | P a g e 60 (vii) Previous report included the completed 5 toilets. This report includes all the rest 5 completed Community Toilet. Photo shown below of the remaining toilet completed during the period:

Zemabawk Zemabawk

Mission Veng Mission Veng

Mission Veng Mission Veng

Ngaizel Ngaizel

Dawrpui

Dawrpui

33 | P a g e 61

(viii) Kick-off- Program on “Source Segregation on Solid Waste Resource Management, Aizawl City” was conducted at Vanapa Hall on 4th December 2015 Hon’ble Minister of State UD&PA Mr. Zodintluanga was the Chief Guest in the program, all 83 Local Council Member representatives participate including other line Departments representative such as AMC, Trade & Commerce and PHE. The kick off program marked the introduction and practice of source segregation of waste. Photos below depict the kick off program:

(ix) Public Awareness being conducted on best practice of source segregation on solid waste. Such awareness program will be conducted in all the 83 Local Council area of Aizawl city. Campaign began in the month of December 2015 and had covered about 21 Local Council areas out of 83. Photographs of such awareness campaign are shown below:

34 | P a g e 62 Annexure 3: Compensation Process: Entitlement Matrix Type of Application Definition of Compensation policy Implementation Issues Responsible loss entitled Agency person 1 Loss of Vacant plot Legal  Compensation at  If land-for-land Valuation private titleholders replacement or land option is offered to committee will for land where husband and wife, determine land feasible (including ownership will be replacement option for in the name of compensation for both while value; the non-viable residual respecting legal NGO will verify portions). Ownership. the extent of  Transitional  Charges will be impact allowance1based on limited to those for through a full 3 months minimum land purchased survey of AHs wage rates. within a year of to determine  Shifting compensation 2 the assistance for payment and for required land of equivalent households. assistance, size. and Identify  Vulnerable households will be vulnerable identified during households. the census conducted by the implementing NGO  2 Loss of Residential Legal Replacement value of Vulnerable households The Valuation residenti structure titleholders the structure and other will be identified committee will al and other assets (or part of the during the census determine 3 structure assets structure and other conducted by the replacement assets, if remainder is implementing NGO. value3. The NGO viable) will verify the Shifting assistance for extent of impacts households. through a 100% Right to salvage survey of AHs materials from determine structure and other assistance, verify assets and identify All fees, taxes and other vulnerable charges (registration households. etc) incurred for replacement structure Transitional allowance based on three-month minimum wage rates. Additional compensation for vulnerable households

3 Loss of Residential Tenants and Replacement value of Vulnerable households The NGO will residenti structure leaseholders the structure and other will be identified verify the extent al and other assets (or part of the during the census of impacts structure assets structure and other conducted by the through a 100% assets, if remainder is implementing NGO. surveys of AHs viable) constructed by Structure owners will determine the AP reimburse tenants assistance, verify Shifting assistance for and leaseholders and identify households.2 rental deposit or vulnerable Right to salvage unexpired lease. households. materials from structure and other assets. Transitional allowance

35 | P a g e 63 based on three month minimum wage rates.1 Additional compensation for vulnerable households

4 Any Unanticipated in other voluntary impact shall be documented loss not and mitigated identified according to the principles stated in ADB’s SPS 2009

1To be provided for APs whose livelihood is affected due to acquisition/purchase of land/relocation. The transitional allowance will be calculated based on minimum wage rates for semi skilled labour for 26 working days a month for 3 months (Aizawl, Rs.250/day). This allowance is meant to support the AP until an alternative means of livelihood is found. In case of vulnerable households, the transitional allowance will be supplemented by livelihoods related skill training.

2To be provided to APs who would be relocated from the site proposed for acquisition to new place decided by AP. This shall be equivalent to one day hire charges for a truck, including shifting within a radius of 50 Km (around INR 3,000).

3 . Other assets include, but aren’t limited to walls, fences, sheds, wells, trees etc.

4The replacement value will be assessed based on the current schedule of rates of the respective cities.

36 | P a g e 64 Annexure 4: Compliance to National laws and Policies: The policy framework and entitlements for the Program are based on national laws: The Land Acquisition Act, 1894 (LAA, amended in 1984) the National Resettlement and Rehabilitation Policy, 2007 (NRRP); and ADB’s Policy on Involuntary Resettlement, 1995. The salient features of Government and ADB polices are summarized below.

i. Government Policy

1. National Resettlement and Rehabilitation Policy, 2007:

The NRRP 2007 was adopted by the on 31 October 2007 to address development - induced resettlement issues. The NRRP stipulates the minimum facilities to be ensured for persons displaced due to the acquisition of land for public purposes and to provide for the basic minimum requirements. All projects leading to involuntary displacement of people must address the rehabilitation and resettlement issues comprehensively. The State Governments, Public Sector Undertakings or agencies, and other requiring bodies shall be at liberty to put in place greater benefit levels than those prescribed in the NRRP. The principles of this policy may also apply to the rehabilitation and resettlement of persons involuntarily displaced permanently due to any other reason. The objectives of the Policy are:

a. To minimize displacement and to promote, as far as possible, non-displacing or least-displacing alternatives; b. To ensure adequate rehabilitation package and expeditious implementation of the rehabilitation process with the active participation of the affected families; c. To ensure that special care is taken for protecting the rights of the weaker sections of society, especially members of the Scheduled Castes and Scheduled Tribes, and to create obligations on the State for their treatment with concern and sensitivity; d. to provide a better standard of living, making concerted efforts for providing sustainable income to the affected families; e. To integrate rehabilitation concerns into the development planning and implementation process; and f. Where displacement is on account of land acquisition, to facilitate harmonious relationship between the requiring body and affected families through mutual cooperation.

The NRRP is applicable for projects where over 400 families in the plains or 200 families in hilly or tribal or Desert Development Program (DDP) areas are displaced. However, the basic principles can be applied to resettling and rehabilitating regardless of the number affected. NRRP’s provisions are intended to mitigate adverse impacts on Project Affected Families (PAFs). The NRRP comprehensively deals with all the issues and provides wide range of eligibility to the affected persons and meets most of the requirement of ADB’s Policy on Involuntary Resettlement (1995). The non title holders under NRRP are recognized as the people living in the affected area not less than three years after the declaration of the area as affected area. The NRRP addresses the vulnerable families with adequate entitlements and provides special provisions for Scheduled Castes (SC) and Scheduled Tribes (ST) Families. The NRRP takes in to account all the transparency as far as consultation, dissemination of information, disclosure and grievance is concerned.

However, the law relating to the acquisition of privately owned immoveable property is the Land Acquisition Act of 1894 (LAA, amended 1984) which is discussed in the following section.

37 | P a g e 65 2. Land Acquisition Act, 1894 as Amended in 1984:

The LAA provides a framework for facilitating land acquisition in India. LAA enables the State Government to acquire private land for public purposes. LAA ensures that no person is deprived of land except under LAA and entitles affected persons to a hearing before acquisition. The main elements of LAA are:

Land identified for the purpose of a project is placed under Section 4 of the LAA. This constitutes notification. Objections must be made within 50 days to the District Collector (the highest administrative officer of the concerned District).

The land is then placed under Section 6 of the LAA. This is a declaration that the Government intends to acquire the land. The District Collector is directed to take steps for the acquisition, and the land is placed under Section 9. Interested parties are then invited to state their interest in the land and the price. Under Section 11, the District Collector will make an award within one year of the date of publication of the declarations. Otherwise, the acquisition proceedings shall lapse.

In case of disagreement on the price awarded, within 6 weeks of the award, the parties (under Section 18 can request the District Collector to refer the matter to the Courts to make a final ruling on the amount of compensation.

Once the land has been placed under Section 4, no further sale or transfer is allowed.

Compensation for land and improvements (such as houses, wells, trees, etc.) is paid in cash by the project authorities to the State Government, which in turn compensates landowners.

The price to be paid for the acquisition of agricultural land is based on sale prices recorded in the District Registrar's office averaged over the three years preceding notification under Section 4. The compensation is paid after the area is acquired, with actual payment by the State taking about two or three years. An additional 30% is added to the award as well as an escalation of 12% per year from the date of notification to the final placement under Section 9. For delayed payments, after placement under Section 9, an additional 9% per annum is paid for the first year and 15% for subsequent years.

3. ADB’S Safeguard Policy Statement, 2009 (SPS)

The three important elements of ADB’s involuntary resettlement policy are (i) compensation to replace lost assets, livelihood, and income; (ii) assistance for relocation, including provision of relocation sites with appropriate facilities and services; and (iii) assistance for rehabilitation to achieve at least the same level of well-being with the project as without it.

i. For any ADB operation requiring involuntary resettlement, resettlement planning is an integral part of project design, to be dealt with from the earliest stages of the project cycle, taking into account the following basic principles: ii. Involuntary resettlement will be avoided whenever feasible. iii. Where population displacement is unavoidable, it should be minimized. iv. All lost assets acquired or affected will be compensated. Compensation is based on the principle of replacement cost. v. Each involuntary resettlement is conceived and executed as part of a development project or program. APs need to be provided with sufficient resources to re-establish their livelihoods and homes with time-bound action in co-ordination with civil works. vi. APs are to be fully informed and closely consulted. vii. APs are to be assisted to integrate economically and socially into host communities so that adverse impacts on the host communities are minimized and social harmony is promoted.

38 | P a g e 66 viii. The absence of a formal title to land is not a bar to ADB policy entitlements. ix. APs are to be identified and recorded as early as possible to establish their eligibility, through a census which serves as a cut-off date, and prevents subsequent influx of encroachers. x. Particular attention will be paid to vulnerable groups including those without legal title to land or other assets; households headed by women; the elderly or disabled; and indigenous groups. Assistance must be provided to help them improve their socioeconomic status. xi. The full resettlement costs will be included in the presentation of project costs and benefits.

39 | P a g e 67 ANNEXURE 5: Govt. Payment Receipt for STP Approach road Land (Landowner Mr. Chawngthanga of Bethlehem Vengthlang).

40 | P a g e 68 ANNEXURE 6: Sale Letter of STP Approach road land. (Landowner statement: that the parcel land is sold to the Project Director, SIPMIU for Rs. 80 Lakhs).

41 | P a g e 69 Annexure 7: Grievance Redressal Systems and process Grievances of APs will first be brought to the attention of the implementing NGO or RO. Grievances not redressed within 30 days by the NGO or RO will be brought to the grievance redress committee (GRC), established in each State. GRCs will comprise the Investment Program Director, RO, LAO, implementing NGO representative, female and male AP representatives (including vulnerable households), and an eminent member of the community. The GRC will meet every month, determine the merit of each grievance, and resolve grievances within a month of receiving the complaint; failing which the grievanc e will be addressed by the IPEC. Further grievances will be referred by APs to appropriate courts of law. Records will be kept of all grievances received including: contact details of complainant, date that the complaint was received, nature of grievance, agreed corrective actions and the date these were affected, and final outcome. All costs involved in resolving grievances will be borne by the SIPMIU. The SIPMIU through the DSMC will keep records of all grievances received including: contact details of complainant, date that the complaint was received, nature of grievance, agreed corrective actions and the date these were effected, and final outcome. The grievance redress process is shown in Figure 1. The GRCs will continue to function throughout the project duration.

Figure 1: Grievance Redress Mechanism

 

   6. ABBRIVIATION

NERCCDIP : North Eastern Region Capital Cities Development Implementation Program ADB : Asian Development Bank MFF : Multi-tranche Financing Facility MoUD : Ministry of Urban Development NGO : Non Government Organization SIPMIU : State Investment Planning Management Implementation Unit DSMC : Design Supervision Management Consultant AMC : Aizawl Municipal Council UD&PA : Urban Development & Poverty Alleviation ST/SC : Scheduled Tribes/ Schedule Cast AP : Affected Person PPE : Personal Protective Equipment DFO : Divisional Forest Officer MLD : Million Liters per Day NOC : No Objection Certificate PHED : Public Health Engineering Department UPC : United Pentecostal Church GRC/M : Grievance Redress Committee/ Mechanism STP : Sewerage Treatment Plant SPS : Safeguard Policy Statement NRRP : National Resettlement and Rehabilitation Policy RP : Resettlement Plan IR : Involuntary Resettlement IPP : Indigenous People’s Plan IEE : Initial Environmental Examination SDO : Social Development Officer RO : Resettlement Officer EA : Executive Agency AH : Affected Households FHH : Female House Headed HH : Household Headed PAF : Project Affected Families PCM : Public Consultation Meeting GAP : Gender Action Plan IPEC : Investment Programme Empowerment Committee VC : Valuation Committee GSR : Ground Storage Reservoir RCC : Re-enforced Cement Concrete Ha : Hectare Sqm : Square Meter kVA : Kilovolt Ampere

43 | P a g e 71

SEMI ANNUAL SOCIAL SAFEGUARD MONITORING REPORT

Loan Number: 2528 IND Reporting Period: (July- December 2015)

INDIA: North Eastern Region Capital Cities Development Investment Program

Water Supply – Tranche - 2

Project City: Gangtok, State

Implementing Agency: State Investment Program Management and Implementation Unit Executing Agency: Urban Development Department,

Gangtok

72

ABBREVIATIONS

ADB - Asian Development Bank BTA - Bridging Technical Assistance CC - Construction Contractor DOC - Date of Completion DOS - Date of Start DSMC - Design, Supervision and Management Consultant EA - Executing Agency EARP - Environmental Assessment & Review Procedure EIA - Environmental Impact Assessment EO - Environmental Officer GoI - Government of India GoS Government of Sikkim IA - Implementing Agency IEE - Initial Environmental Examination IPCC - Investment Program Coordination Cell MFF - Multi-tranche Financing Facility MLD - Million Liters per Day mn - Million MoUD - Ministry of Urban Development NEA - National Executing Agency NERCCDIP - North Eastern Region Capital Cities Development Investment Program NSC - National level steering committee PD - Project Director PPTA - Project Preparatory Technical Assistance SEA - State level Executing Agency SIPMIU State Investment Program Management and Implementation Unit UD&HD - Urban Development & Housing Department

73 i

Table of Contents

1 INTRODUCTION ...... 3 2 IMPLEMENTATION ARRANGEMENTS ...... 4 3 SUB PROJECT COMPONENTS IN GANGTOK MUNICIPAL COUNCIL AREA ...... 5 4 SOCIAL SAFEGUARD ACTIVITIES...... 6 5 PROJECT IMPACT ...... 11 6 THE STATUS OF CIVIL CONSTRUCTION ACTIVITIES...... 13 7 STATUS OF RP IMPLEMENTATION...... 14 8 POLICY AND LEGAL FRAMEWORK ...... 17 9 GRIEVANCE REDRESSAL ...... 17 10 COMMUNITY DEVELOPMENT ACTIVITIES ...... 17 11 CONCLUSION ...... 23

List of Tables Table 1. Institutional Roles ...... 4 Table 2: Sub project components...... 5 Table 3. Sub project Components and its Impact on Land Acquisition & Resettlement...... 7 Table 4. Land Parcel for Service Reservoirs and the Ownership details...... 9 Table 5. Details of the land owner ...... 9 Table 6. Stretches claimed as private land...... 10 Table 7. Land Parcel for landfill site and the ownership details...... 11 Table 8. Summary of Resettlement Impacts and Socio –economic details (WS) ...... 12 Table 9. Summary of Resettlement Impacts and socio – economic details of SWM ...... 12 Table 10: Progress of civil construction activities ...... 13 Table 11. Status of Loan Covenants ...... 15 Table 12. Community Development Activities...... 17

74ii

1 Introduction 1. North Eastern Region Capital Cities Development Investment Program (NERCCDIP) is being undertaken for improvement of existing infrastructure, environmental quality and access to basic urban services of Gangtok Municipal Corporation (GMC) area. The NERCCDIP’s objective is to improve the urban environment and promote reforms for sustainable, efficient, and responsive urban service delivery. The primary drivers for the initiation of NERCCDIP have been bridging the gaps in urban infrastructure provision, supplementing financial resources and technical capacity and meeting the unmet urban public health and sanitation needs. The various Program components are Water supply, Sewerage and Sanitation and Solid Waste Management infrastructure. 2. With an overall objective of sustainable urban development, the NERCCDIP is being implemented in the five capital cities - Gangtok, Aizawl, Kohima, Gangtok and Shillong. NERCCDIP implemented over a six year period beginning in 2010, and is funded by a loan via the Multi tranche Financing Facility (MFF) of the Asian Development Bank (ADB). 3. In Gangtok, capital city of Sikkim State, the Executing Agency (EA) for the program is the Urban Development and Housing Department (UD&HD) of the Government of Sikkim (GoS); and the Implementing Agency (IA) is the State-level Investment Program Management and Implementation Unit (SIPMIU), created within the UD&HD, specifically for the Investment Program implementation. At central level, an Investment Program Coordination Cell (IPCC) is constituted in MOUD. IPCC is responsible for overall management of the Investment Program and is supported by the Program Management & Monitoring Consultants (PMMC). 4. Under the program the physical investments include improvements to water supply, sanitation & sewerage and solid waste management infrastructure. The physical improvements are being coupled with urban governance, finance, and service delivery reforms and a capacity building program to support the implementation of the investment program and the urban reform agenda. The Investment Program is being implemented through three tranches of funding which began in 2009. The Program is scheduled to be completed by the year 2015. 5. The sub project taken up under tranche -1 in water supply scheme has been completed in Gangtok. This subproject covered (i) construction of Distribution Network for Burtuk Zone-1 of 17.75km, Burtuk Zone-2 of 10.57km and Chandmari Zone-3 of 15.87km lengths; (ii) construction of Pump House and installation of pumps at Selep Water Treatment Plant of capacity 1930 lpm at Head of 101m, (iii) construction of New R.C.C Reservoir of 11.50 LL capacity at Bulbuley on (AIR) Station Road for Burtuk Zone-1& Chandmari, and (iv) supply & Installation of electromagnetic flow meters at outlet of pump house at Selep, outlet of storage reservoir for Burtuk Zone-1 and at outlet of storage reservoir for Chandmari Zone. 6. At present two subprojects are under implementation in tranche -2 (i) Water Supply and (ii) Solid waste Management. (i) Water Supply subproject: Works taken up under water supply sub project are awarded in two lots.  The work comprises in lot -1 are construction of 3 ground level reservoirs at New Enchey (Capacity: 5.30 lakh litre), New TNSS Tank (Capacity: 3.30 lakh litre) and New Lower Sichey Tank (Capacity: 4.40 lakh litre) together with supply and laying of 60.86 km of pipes in 13 tank zones and supply and installation of power operated (electrical mains supply or battery) 24 Nos. of

3 75

electromagnetic flow meters. As far as project status is concerned, 90% construction work of all three tanks is completed so far.  The work comprises in lot -2 are construction of 3 ground level service reservoirs- 2 nos., at New Press Tank (Capacity: 7.80 Lakh Ltr*2nos=15.60 lakh litre) and New Bazaar Tank (Capacity: 5.35 lakh litre) together with supplying and laying of 47.66 km of pipes in 7 tank zones and supply and installation of 15 Nos., of power (electrical mains or battery) operated electromagnetic flow meters. 90% of construction works of two out of three tanks are completed and for the remaining one, earth works excavation is going on. (ii) Solid Waste Management: Works in SWM subproject comprise of construction of Solid Waste landfill, Leachate Treatment Plant and associated works at at Martham 20 Kms away from Gangtok.  The work comprises of Construction of retaining wall, Leachate Treatment Plant, Upgrading the surface for new Landfill, providing sewer line from collection well, construction of toilet block, security guard cabin, office cum store cum workers room, roads, piping system for water supply system, green belt, bore well for monitoring, fencing and compound wall electrical works etc. The present status of the work is field survey is completed. Work of retaining wall of sanitary land fill is in progress. 7. This is the consolidated report on implementation of Social Safeguard Activities of subprojects taken up under tranche -2 during the period from 1st January to 30th June 2015 and this is prepared in compliance with the ADB Policies. 2 Implementation Arrangements 8. The Ministry of Urban Development (MOUD) is the national-level executing agency (EA) of the program. An IPCC is also established in MOUD incorporating a Social Safeguard Officer. A National Steering Committee (NSC) will monitor the fund use and overall implementation performance of the Investment Program. In each State there will be a State Steering Committee (SSC), an Investment Program Empowered Committee (IPEC) and a State Investment Program Monitoring and Implementation Unit (SIPMIU).The SIPMIU is responsible for overall program implementation, monitoring and supervision in the respective cities. 9. The SIPMIU will have a Social Safeguards Unit headed by a sociologist. Depending on the anticipated volume of resettlement and other related issues, a Resettlement Officer & supporting NGOs may be required as part of the Unit. ROs/and NGOs will be responsible for RP implementation. However, in small projects where resettlement issues are is not anticipated or minimal, an extensive staffing in the SSU is not essential. In case any resettlement issues arise during the subsequent stages of implementation, the services of competent personnel/agencies like RO/NGO shall be engaged. The generalized institutional roles of the involved entities are identified in Table 1 as a guide line. The Social Safeguards Unit under SIPMIU will take care of redressing grievances and mitigating negative social impacts caused due to the project with the aid of the existing system and shall request the Program Director for further reinforcement of support staff/NGOs if required. Table 1. Institutional Roles Sl no: Activities Agency Responsible Sub-project Initiation Stage 1 Finalization of sites/alignments for sub-projects SIPMIU&DSMC

4 76

Sl no: Activities Agency Responsible 2 Disclosure of proposed land acquisition and sub-project SIPMIU details by issuing public notice 3 Meetings at community/ house hold level with APs of SSU/&NGO land/property 4 Formation of Valuation Committees SIPMIU

RP Preparation Stage 5 Conducting Census of all APs SSU/&NGO 6 Conducting FGDs/ meetings / workshops during SIA SSU/&NGO surveys 7 Computation of Replacement Values of land/properties SSU&DSMC proposed for acquisition and for associated assets 8 Categorization of APs for finalizing entitlements SSU 9 Formulating compensation and rehabilitation measures SIPMIU 10 Conducting discussions/ meetings with all APs and other SIPMIU/&NGO stake holders 11 Fixing compensation for land/property with title holders VC/SIPMIU 12 Finalizing entitlements and rehabilitation packages SIPMIU 13 Disclosure of final entitlements and rehabilitation packages SIPMIU/&NGO 14 Approval of RP IPCC/ADB 15 Sale deed execution and payment of compensation SIPMIU 16 Taking possession of land SIPMIU RP Implementation Stage 17 Implementation of proposed rehabilitation measures SSU/&NGO 18 Consultations with APs during rehabilitation activities SSU/&NGO 19 Grievances redressal SSU/&NGO/GRC 20 Internal monitoring SIPMIU 21 External monitoring External Agency SSU= Social Safeguards Unit AP=affected person, VC=valuation committee, FGD=focus group discussions, GRC = grievance redress committee, NGO = nongovernment organization, SIPMIU = state- level investment program management and implementation unit, IPCC = investment program coordination cell, RO = resettlement officer, RP=resettlement plan, SIA=social impact assessment. 3 Sub Project Components in Gangtok Municipal Council Area 10. The sub project components taken up under various tranches in Gangtok Municipal Council are summarized in table.2. Table 2: Sub project components. Component Tranche Works Water Supply 1  It is proposed to provide water to 2 wards Burtuk and Chandmari with a supply level of 135 lpcd  New pump house at Selep with 3 new pump sets  New 11.50 Lakh liters reservoir alongside AIR station road  Pumping main from Selep to Reservoir  40.28 Km of distribution lines in Burtuk and Chandmari (32 to 250 mm diameter pipes of HDPE,PE and GI)  Installation of 4 bulk flow meters to measure the flows in pipe lines.

5 77

Component Tranche Works Water Supply 2  It is proposed to improve the existing water supply in the remaining 15 wards of Gangtok Municipal Corporation with a supply level of 135 lpcd  De-Bunching the secondary water distribution with equivalent distribution line for a length of 104.41 Km with proper zoning arrangements  Providing Primary water distribution pipeline for a length of 3.9 Km to connect the proposed tanks to the nearest existing feeder for catering to hitherto uncovered peripheral areas.  Contribution of additional 6 nos. of service reservoirs of total capacity of 33.95 lakh liters  Providing 46 bulk flow water meters (previously it was 39nos.)  Providing 14000 Household water meters (previously it was 12000 nos.) and making reconnection to replace the existing bunched connections. Solid Waste 2  Door to door waste collection will be Management introduced and waste will be collected on a daily basis, every household will be provided with two bins for the storage of wet (biodegradable) and dry (non- biodegradable) waste.  The primary waste collectors will be provided with small mechanical vehicles and further it will transferred to secondary vehicles and finally to Solid Waste Management Plant.  Biodegradable waste will be converted to manure by composting at the plant and non- biodegradable will be segregated again to inert and scientifically disposed in sanitary land fill.  Construction of sanitary landfill with leachate treatment plant. 4 Social Safeguard Activities. 11. In order to identify the Resettlement Impacts, if any, due to the project implementations, the safeguard specialists of SIPMIU & the DSM Consultant have carried out several site visits and consultative inspections in the project areas during the preparation of RP. Based on this and further discussions held with the local public in the City, it has been confirmed that the implementation of the subprojects taken up under tranche 2 will have minor involuntary resettlement impact. Hence the sub projects (tranche-2) category with respect to Resettlement Impact is ‘Category B’. (ADB’s Safeguard Policy Statement, 2009). 4.1. Adverse Social Impact 12. The subproject components and a summary of impact on land acquisition and resettlement is described in Table 3, further details are illustrated in below section.

6 78

Table 3. Sub project Components and its Impact on Land Acquisition & Resettlement. Component Location Permanent Temporary Remarks Impact on Impact LA and IR Providing new secondary De bunching will be done for existing Nil Nil Excavation will be carried out manually. The water distribution network secondary network system throughout width of the trench will be within one feet and for a length of 104.41 km Gangtok Municipal area and extension of around one feet depth, hence this will not with proper zoning secondary distribution network to uncovered cause any loss of access to the commercial arrangements to replace peripheral areas areas. Also appropriate design option would the present bunched be explored to avoid trenching in busy distribution system and commercial areas like MG Marg and Lal for uncovered peripheral Bazaar. area Providing primary water 1. Tapping from nearest topographical Yes Nil During the project implementation certain distribution pipeline feasible point of existing feeder main to the people (listed in table-4) are claimed that the (feeder mains) of 150mm proposed Press Tank - Zone-3 pipe line is proposed to lay in their private diameter DI to 100mm 2. Tapping from nearest topographical land. diameter for a length of feasible point of existing feeder main to the 3.91km tapping from proposed Bazar Tank – Zone-4 existing feeder mains to 3. Tapping from nearest topographical the newly proposed feasible point of existing feeder main to the service reservoirs for proposed lower Sichey Tank – Zone-5 catering to hitherto 4. Tapping from nearest topographical uncovered peripheral feasible point of existing feeder main to the areas proposed Enchey Tank – Zone-6 5. Tapping from nearest topographical feasible point of existing feeder main to the proposed Tank at TNSS area – Zone-7 Construction of additional  SR-1 at existing press tank area Yes Nil Out of the total 6 SRs 5 are in government 6 nos. of service  SR-2 at existing Bazar tank area land. Only one SR (SR-3 (at lower Sichey) reservoirs of total  SR-3 at lower Sichey area having 25m x 16m area is constructed in the capacity of 33.95 ML.  SR-4 at existing Enchey tank area acquired land (there will be two press  SR-5 at TNSS area tanks instead of previously proposed one but capacity remains the same)

7 79

Component Location Permanent Temporary Remarks Impact on Impact LA and IR Providing 46 nos. bulk Bulk meters will be fixed on pipeline at various Nil Nil Minor work with minimal physical flow water meters locations in the Gangtok town construction. Probably work will start in April (previously it was 39nos.). 2016. Providing 14000 Consumer meters will be fixed to each Nil Nil Minor work with minimal physical household water meters connection at the house construction. (previously it was 12000 nos.) and making re- connections to replace the existing bunched connections. Improvement of the waste All 17 Wards of Gangtok Municipal Nil Nil collection and Corporation. transportation system Rehabilitation of existing At Martham 20 Kms away from Gangtok Nil Nil compost plant Construction of a new Martham adjacent to the land fill site Nil Yes Construction of new Landfill facility (4.2660 landfill and associated Heactre) with Leachate Treatment Plant (40 facilities cum /day capacity). The land is already available with the UD&HD; therefore, no private land acquisition is required. However, there will be impacts on 38 households on their livelihood.

8 80

4.2.1. Permanent Land Acquisition and Ownership Details 13. Water Supply Subproject: Permanent land acquisition will be there for the water supply sub project for the construction of one service reservoir out of proposed five number of service reservoirs. All other components of the water supply sub projects are located on vacant government land or along the existing right-of-way (RoW) of city roads. The construction of other 4 new service reservoirs is proposed within available government lands. The locations were finalized in consultations and as per the suggestions of Water Security and Public Health Engineering Department (WSPHED), Government of Sikkim. One service reservoir which has been proposed in the lower Sichey area is located in private land. The total land requirement for this service reservoir is 400 sq meters. The identified location of this proposed service reservoir has also been done in-consultation with (WSPHED) as no Government land is available in that area. Location and the required area for each service reservoir along with the ownership are described in Table 4. Further the ownership details of land to be acquired at Sichey are summarized in table 5. Table 4. Land Parcel for Service Reservoirs and the Ownership details. New Required Sl. No. Location of proposed SR Ward Ownership of land land No. 1 Proposed Reservoir-1 (at 11 25m x 16m Government land existing Press tank site ) 2 Proposed Reservoir-2 12 20m x 13m Government land (adjacent to Existing Bazar Tank site ) 3 Proposed Reservoir-3 (at 4 25m x 16m Private land lower Sichey) 4 Proposed Reservoir-4 6 26m x 16m Government land (adjacent to existing Enchey Tank area ) 5 Proposed Reservoir-5 (at 7 24m x 12m Government land TNSS area ) Source: census and Socio-economic Survey, November-2010 Table 5. Details of the land owner Name Parcha Khat LA in Total Total % of % of Number of the No. ian (Sq.mt Area of land Loss Loss of Trees Owner No. s) the holding compare compar Plot of the d to the ed to (Sq.mt owner total area the total s) (Sq.mts) of the area of affected land plot holding Dhan 139/35 287/ 400 1400 2723 28% 14 % 8 trees – Kumar 4 1096 Non fruit Rai bearing and non- timber value Source: census and Socio-economic Survey, November-2010 14. During the project implementation certain people (listed in table 6) are claimed that the pipe line is proposed through their land. Details are shown in table 6. This was brought to the notice of SIPMIU in the month of May, 2015 and a joint inspection with land records departments is also done. It has been noted that, for the household connection, pipeline to be laid through private land at a few locations. In this regard SIPMIU is pursuing consent from the land owners to lay the pipeline in their land.

9 SIPMIU 81 DSMC

Table 6. Stretches claimed as private land. Location Sl No zone Length of private land

1 6th mile 250 mt

2 6th mile 40 mt

Press tank 3 (back side Big 150 mt bazaar)

1. Solid Waste Management: The proposed subproject will require land for development of sanitary landfill site and processing plant, access road to the processing plant and for developing a green belt area all around the SWM site. The existing site of dump yard located at Martham (around 20 Km from Gangtok) will be used to accommodate the entire sub project components. Hence, no permanent land

10 SIPMIU 82 DSMC

acquisition from private sources is required for the sub project. The land belongs to the UDHD of Government of Sikkim. It is evident from the table 7 that, 4.2660 hectare (ha) of land is owned by UDHD department. The land revenue department has already initiated the process for mutation of the 4.2660 hectare of the land to be transferred to UDHD, Government of Sikkim. The ownership status of the land is given in Table 7. Table 7. Land Parcel for landfill site and the ownership details.

Sl No Survey Number/Plot Number Area in Hectare Status of Ownership 1 1958 1.3720 Government/UDHD 2 1957 0.2240 Government/UDHD 3 1956 0.3060 Government/UDHD 4 1959 1.0280 Government/UDHD 5 1962 0.1140 Government/UDHD 6 1961 0.5580 Government/UDHD 7 1960 0.5060 Government/UDHD 8 1964 0.1580 Government/UDHD Total Area 4.2660 4.2.2. Temporary Impact 2. Water Supply Sub project: The existing primary distribution networks (feeder mains) presently conveying treated water from Selep WTP to the existing service reservoirs was retained. The new feeder mains are designed for ultimate demand exclusively for the proposed service reservoirs in peripheral areas. The new feeder mains will either pass through the existing feeder main alignments or will follow the existing Row. The proposed secondary and tertiary distribution system will also follow the existing Row. It has been found on an inspection with water supply design engineers that pipes can be laid along the 5 to 10 m wide roads of Gangtok City without acquiring any further lands. The improvement work can be carried out within the ROW in road shoulders without causing problems to the existing lines. The maximum required trench width in busy commercial area will be only 30 cm and trenching can be done without causing any temporary impact lasting more than a day. In order to estimate the temporary impact, resettlement expert of DSMC carried out a joint site visit along with design engineers. However, corrective action plan shall be prepared to mitigate any unforeseen temporary impacts during the time of project implementation. 3. Solid Waste Management Sub Project: Livelihood of 38 rag pickers working in the landfill area will be affected due to this project. A census and socio-economic survey was undertaken in the proposed land fill site situated in the Martham village. Based on the census conducted during the period of November, 2010, it was estimated that 38 households will be affected by the subproject. Of the total 38 APs, 12 are in the muster roll of UDHD working as trash sorter in Marthom compost plant as daily wage laborers. In addition, there are 26 APs who are also working as a trash sorters. These 26 rag pickers segregate the waste on site and sell the non-biodegradable waste like plastic bottles, glass bottles and other solid waste etc and sell it to a middle man and in turn he sells the same to the recyclers. The proposed project will be impacted upon the temporary livelihood of all these 38 APs. 5 Project Impact 4. The Investment Program is intended to optimize the socio economic development in Gangtok Municipality area with an objective to improve the urban environment cum living conditions of citizens. The sub projects implementations will not create any

11 SIPMIU 83 DSMC

major negative impact on community. The anticipated impact on rag pickers at existing waste disposing site and impact on one title holder has appropriately been taken care of in the respective RPs. Also the implementation of RPs integrating with various developmental schemes of governmental and non-governmental agencies will enhance the living standard of PAPs. Summary of adverse social impacts in tranche -2 sub projects are summarised in below tables (table 8 & 9). Table 8. Summary of Resettlement Impacts and Socio –economic details (WS) Type of Impact Number of APs 1.Permanent Loss Title Holder/Land Owner 1 Total Loss of land(sq.mts) 400 Loss of trees 8 Total land Holding in that Particular Plot (sq.mts) 1400 Occupation Teacher/Government employee Vulnerability Non Vulnerable Annual Income (INR) 2,42000/ 2.Temporary Loss A)Temporary Loss/ Disruption of Business(Nos) Nil B)Temporary Loss/ Disruption of Business Employees Nil of the business enterprises(Nos) 3. Encroacher in ROW A) Encroacher in ROW(Nos) Nil Affected CPRs NIL Source: census and Socio-Economic Survey, December 2010 and Joint site verification carried out by Resettlement Specialist on 20-06-2013 Table 9. Summary of Resettlement Impacts and socio – economic details of SWM Particulars Quantity Permanent land acquisition (private) Nil Temporary land acquisition Nil Total Affected Households (Loss of Livelihood) 38 Total Affected Persons 198 Average Family Size of Affected Households 5.2 persons Total No. of Scheduled Caste HH 3 Total No. of Woman Headed Households 3 Total No. of Schedule Tribe Households 9 Total No. of Title Holders NIL Total Number of Non-Title holders 38 Total No. of Tenants NIL Main Occupation of the Affected Persons Casual labour (63.15% of total worker) Average Annual Household Income Rs.72,982 (Rs.6098 per month) Source: census and Socio-Economic Survey, November 2010 5. Details of “Affected Persons” for the sub projects including census data will be verified by concerned Govt. Dept. and Safeguard Specialist of SIPMIU before disbursement of compensation to APs as per approved entitlement matrix

12 SIPMIU 84 DSMC

6 The status of civil construction activities. 1. The progress of civil construction activities of subproject taken up under Water supply & SWM is summarized in table 10. Table 10: Progress of civil construction activities Name of Packages Date of Completion Cumulative Progress in % Commencement Time in Progress till 30th Achieved Targeted of Work Months June, 2015 A. Supply & laying water distribution system De-bunching of 8.9.2013 24 months. DI pipe 10.40 km 60% 100% Secondary Extended laid HDPE 22.5 Km distribution (Lot-1) up to laid. GI pipe 3 km. 30.03.2016 TNHSS tank completed and integrated with distribution line. Sichey tank up to slab completed. Enchey tank slab started. 4 km pipeline hydraulic tested. Distribution of TNHSS tank zone completed. Hydro testing and road restoration under progress. GI pipe procured. De-bunching of 8.9.2013 24 months. DI pipe laid 9.1 km. 60% 100% Secondary Extended HDPE 24.6 Km. All distribution (lot-2) up to lifts of Bazar Tank 30.03.2016 completed. Press tank (1st) completed. Testing of pipes- 7km completed. Shifting of utilities of press tank started for commissioning of 1st press tank. Bazar tank tested. Restoration and integration work under progress. B. Improvement of Solid Waste Management System TrII Loan 2834 Ind. Procurement of Mini 1.July.2014 12months vehicles handed 100% 100% Garbage Vehicle lot 1 over to GMC Procurement of 1.oct.2013 6 months vehicles handed 100% 100% vehicles and steel over to GMC bins lot 2 closed compactor trucks- SWM 3B Lot2

13 SIPMIU 85 DSMC

Name of Packages Date of Completion Cumulative Progress in % Commencement Time in Progress till 30th Achieved Targeted of Work Months June, 2015 Construction of solid 20th.Sept.2013 24 months. Retaining wall fully 88% 100% waste landfill Extended completed. LTP leachate treatment up to works also fully plant (LTP) SWM2 30.03.2016 completed. Fencing 50% completed. Building works fully completed. Clay linder 30% completed. Procurement of chain vehicles handed 100% 100% wheeled hydraulic over to GMC excavator(Shopping) Procurement of 100% 100% Personal Protective completed Equipment(Shopping) Procurement of 1.7.2014 12 months Distribution in two 100% 100% household bins and wards completed. Push carts SWM1 9000 pcs distributed. Procurement of 6 months Completed and 100% 100% Bulldozer (Shopping) under use at landfill.

7 Status of RP implementation. Solid Waste Management 2. M/s. Eco Tourism and Conservation Society of Sikkim (ECOSS) an NGO based in Gangtok have been appointed as RP implementation agency. ECOSS commenced its assigned activities on February 6, 2014. A brief description of activities performed in this regard is summarized in below section. 3. Mobilization of project staff team was initiated by ECOSS in 2nd week of February 2014 for undertaking the task of implementation of Resettlement Plan (RP) of SWM sub project based on a Terms of Reference given to them. The team comprises one Team Leader (post Graduate in Sociology), one Social Development Specialist (Post Graduate in Sociology) and three Field Coordinators (Graduates in Social Science). 4. Revalidation of Census survey: As part of preparation of Resettlement Plan an initial Socio-Economic Survey and Census was undertaken in November 2010 in the proposed land fill site situated at Martham. Based on the census undertaken during that period, 38 households were identified as the Project Affected Persons (PAP). As a follow up on the above survey, a similar type of re-verification (socio-economic) survey was carried out by the RP implementation NGO during the period of 15th March to 27th March 2014 and 15th April to 18th April 2014. The survey was carried out with a predesigned questionnaire approved by SIPMIU. The survey was designed to gather information related to the socio-economic profile of the affected households. Photo verification of the participating PAFs was also done. 33 households (out of 38) were present during the revalidation survey and it came to know that the balance 5 is migrated to other places like and due to health related issues or for better employment opportunities.

14 SIPMIU 86 DSMC

5. Public Disclosure: The project details and resettlement benefits are disclosed to the PAPs on 11th June, 2014. As none of the APs are having bank account to encash the project assistance, actions has taken to open a bank account at Union Bank of India (UBI), Branch, Gangtok. Senior Manager of UBI explained the formalities and documents required for opening the bank account. During the meeting he has also assured ‘zero’ balance operation to the APs. The RP implementation NGO shall coordinate the activities. 6. Issuing Identity Cards: Identity cards are issued to all project affected persons on 15th & 16th of October, 2014 by the RP implementation support agency (M/s. Eco Tourism and Conservation Society of Sikkim). 7. Preparation of Draft Micro Plan & Disbursement of Resettlement Assistance: Finalization of micro plan for resettlement & rehabilitation of APs integrating with various agencies and welfare schemes of State & Central governments are in progress. Draft micro plan for each APs are prepared in consultation with them and other agencies. The draft could not be finalized during this period as actual displacement of APs will happen once segregation at source, development of segregation units and sanitary land fill at Martham is ready. The resettlement assistance (based on the entitlement matrix) has paid to the respective APs on 17th October, 2014. The Bank and APs are directed to keep this amount as fixed deposit for next one year. Hence the amount with interest shall be used for the rehabilitation of APs based on the micro plan. Water Supply Sub project 8. The land earmarked for construction of service reservoir at lower Sichey (private land) has been purchased from the land owner on 20-06-2014 and handed over the site to the contractor for commencement of civil works. 9. The resettlement monitoring review has been done periodically and it has found that there is no temporary impact which required mitigation measures as the construction activities are being done either within the available ROW of city roads or along the open area. The contractor has been advised to prepare the detailed drawing and work plan for the next phase of the work in order to prepare the mitigation plan for resettlement implementation monitoring. Status of RP implementation with respect to progress in civil works is summarized in table.3. 4.2.1. GAP Implementation 10. The progress of Gender Action Plan implementation till the end of June 2015 (for two quarter) is briefed under Appendix-1. 4.2.2. Compliance status of loan covenants 11. The compliance status with respect to loan covenants is presented in table 11 below Table 11. Status of Loan Covenants Sl No Loan Covenant Agency Status of Compliance 1 GOI and the State will ensure that all Government of No private land land and right of way required for the India & acquisition and investment program are made Government of resettlement issues are available in timely manner. Adequate Sikkim involved under any of compensations are provided prior to the subprojects under the signing of relevant civil work the Investment contracts, and involuntary resettlement Program. Hence RPs is carried out in accordance with the has not been prepared. resettlement frame work (RF) and resettlement plans (RPs) agreed upon

15 SIPMIU 87 DSMC

Sl No Loan Covenant Agency Status of Compliance between the Government and ADB. An RP will be prepared for each sub project involving land acquisition and resettlement and shall be submitted to ADB for review and approval prior to award of any related civil work contract. 2 GOI and the State will ensure that sub Government of No negative Impact on projects will not negatively impact on India & vulnerable groups vulnerable groups, such as indigenous Government of people. In the event of their Sikkim involvement in any of sub projects, the GOI and the states will ensure the that the sub projects are carried out in accordance with the Indigenous People Development frameworks (IPDF) agreed up on between GOI, the States and the ADB and comply with ADBs policy on Indigenous People (1998) 3 In the event any issues related to Government of Agreed. However, no indigenous people arise in course of India & issues related to project implementation, the borrower Government of indigenous people are and the state shall ensure to address Sikkim anticipated in the those issues in accordance with the course of execution. applicable laws and policies of the borrower, ADB’s policy on indigenous Peoples (1998) and the Indigenous Development Framework for the facility as agreed between the Borrower, the State and ADB. In the case of any discrepancy between the Borrower’s legislation and ADB’s policy, ADB’s policy shall prevail. 4 GOI and State will ensure that all civil Government of Adequate provision has works contractors comply with all India & been made in the applicable labor laws, including those Government of contract agreements on occupational health and safety, and Sikkim do not employ child labor as defined in national legislation for construction and maintenance activities. Priority work will be given to people from the area where the works are implemented and men and women will receive equal pay for work of equal value. 5 Within six months of the Effective Date, Government of 25thJanuary2012, the the State shall have established a Sikkim GRC is formed. grievance reporting and redressal Notification is attached mechanism as Appendix -3

16 SIPMIU 88 DSMC

8 Policy and Legal Framework 12. The policy framework and entitlements for all the subprojects of the investment program under tranche 2 are based on the National Resettlement and Rehabilitation Policy, 2007 (NRRP) and ADB’s Safeguard Policy Statement, 2009 9 Grievance Redressal 13. A Grievance Redressal Committee has been constituted as per the guideline. However no complaints are elevated to the GRC for its consideration during this period (1st July, 2015 to 31st Dec, 2015). 10 Community Development Activities Draft micro plan for rag pickers at landfill site has been prepared. But as all the rag pickers are working still in the site, resettlement & rehabilitation may come in picture only after the physical displacement from their job. As part of streamlining the collection and segregation of household solid wastes before commissioning the sanitary land fill site at Martam, a pilot project has been developed and the same is under implementation at two wards of GMC. The summary of the community development activities carried out during the reporting period is summarized in below table. Activities carried out in the report period (July to December 2015) at Dara Gaon ward is attached as Appendix 2 further the photographs of various activities is attached as Appendix 3. Table 12. Community Development Activities. Sl Date Programme Activities Outcome No A sticker was given to Field visit for monitoring each community 1 22nd July 2015 Field visit and supervision of waste organizer to mark the collecting practices. houses were follow up was completed Awareness was Training programme Shusong Lohar gave a brief spread to the cluster on solid waste demonstration of segregation about solid waste management at of waste; Mr. Ritesh Gurung 2 27th July 2015 management. People above gas godown (Sub Inspector, GMC) spoke were briefed about area, Lumsay (Dara on rules and regulation of how to segregate Goan Ward) GMC on SWM. household waste. Introduction by Mr. Bhasker Basnett (Councillor Dara Gaon Ward). Mrs Primula Awareness was Lama gave awareness about Training programme spread to the cluster waste segregation at on solid waste about solid waste household level. Shusong 3 28th July 2015 management at management. People Lohar gave a brief School Area, Lumsay were briefed about demonstration of segregation (Dara Goan Ward) how to segregate of waste. Mr Karma Palzor household waste (Sub Inspector, GMC) spoke on rules and regulation of GMC on SWM.

17 SIPMIU 89 DSMC

Sl Date Programme Activities Outcome No Mrs. Primula Lama gave Training programme awareness about waste Training program on solid waste segregation at household helped the participants management at level, Ms. Meena Pradhan to learn how to th 4 29 July 2015 above gas godown gave a brief demonstration of segregate the area, Lumsay (Dara segregation of waste, Mr household waste and Goan Ward) Karma Palzor (Sub Inspector, the importance of doing GMC) spoke on rules and so. regulation of GMC on SWM. Mrs Primula Lama gave awareness about waste Training programme Awareness was spread segregation at household on solid waste to the cluster about solid level, Mrs. Goma Chettri gave management at waste management. 5 30th July 2015 a brief demonstration of above gas godown People were briefed segregation of waste, Mr area, Lumsay (Dara about how to segregate Karma Palzor (Sub Inspector, Goan Ward) household waste GMC) spoke on rules and regulation of GMC on SWM. Mr. P. P. Koirala General Secretary of Samaj welcomed all participants. Mrs. Primula Training programme Lama gave awareness about Awareness was spread on solid waste waste segregation at to the cluster about solid management at household level. Mrs. Bhim waste management. 6 31st July 2015 Power station, Kumari Basnett gave a brief People were briefed Lumsay (Dara Goan demonstration of segregation about how to segregate Ward) of waste, Mr Karma Palzor household waste (Sub Inspector, GMC) spoke on rules and regulation of GMC on SWM. Mrs Primula Lama gave a brief description on issues and challenges related to Training programme waste management of on solid waste All the participants are Gangtok city. Also gave 7 1st August 2015 management at able to segregate waste demonstration on waste opposite Housing in a proper manner. segregation. Mr. Ritesh Colony Gurung spoke about the rules and regulation of GMC regarding SWM.

18 SIPMIU 90 DSMC

Sl Date Programme Activities Outcome No Mrs Primula Lama gave a detailed demonstration on Training programme segregation of household People were briefed 3rd August on solid waste waste. Mr. Ritesh Gurung 8 about how to segregate management at (Sub Inspector, GMC) spoke household waste Below IGNOU Office about the Rules and Regulation of GMC regarding SWM. Awareness was spread Training programme Mrs Primula Lama gave a to the cluster about solid 4th August on solid waste detailed demonstration on waste management. 9 management at segregation of house hold People were briefed Joredhara waste about how to segregate household waste Awareness on waste Mrs Primula Lama gave segregation at Training programme awareness and importance of household level was 5th August on Solid Waste waste segregation. Goma spread to the public 10 Management at Chettri gave a brief through demonstration. Joredhara demonstration on segregation Now all the participants of waste at source. are able to segregate waste in proper manner Training program Mrs Primula Lama gave helped the participants Training programme awareness and importance of to learn how to 6th August on Solid Waste waste segregation. Goma 11 segregate the Management at Chettri gave a brief household waste and Joredhara demonstration on segregation the importance of doing of waste at source. so. Mrs Primula Lama gave Awareness was spread Training programme awareness and importance of to the cluster about solid 7th August on Solid Waste waste segregation. Goma waste management. 12 Management at Chettri gave a detailed People were briefed Joredhara demonstration on segregation about how to segregate of waste at source. household waste Monitoring and supervision of Monitoring and waste collection practices On spot sensitisation for 17th August supervision of waste 13 were observed and taken households and waste collection practice at measurement of segregated collectors. Tadong Ward waste for study purpose.

19 SIPMIU 91 DSMC

Sl Date Programme Activities Outcome No The vehicle was measured with waste and without waste Arrived volume of waste 18th August Waste measurement 14 to measure the quantum of collected from Ranipool at Ranipool Ward waste generated from ward. Ranipool Ward Mrs Primula Lama gave a Awareness on waste Training programme brief description on issues segregation at on Solid Waste and challenges related to household level was Management at waste management of spread to the public 15 29 Oct 2015 Palbhu Samaj, ICAR Gangtok city. Susong Lohar through demonstration. Area (Dara Goan gave a detailed demonstration All the participants are Ward) on segregation of household able to segregate waste waste. in proper manner All the participants are Training programme Mrs Primula Lama gave able to segregate waste on Solid Waste awareness and importance of in a proper manner. Mr Management at waste segregation. Goma Ritesh Gurung (Sub 16 30 Oct 2015 Greendale School Chettri gave a detailed Inspector, GMC) Area, ICAR Area demonstration on segregation attended queries of the (Dara Goan Ward) of household waste. Households and gave his valuable inputs Mrs Primula Lama gave a Training programme Training program brief description on issues on Solid Waste helped the participants and challenges related to Management at to learn how to waste management of 17 31 Oct 2015 Umakunj Line and segregate the Gangtok city. Susong Lohar Sundar Goan,ICAR household waste and gave a detailed demonstration Area (Dara Goan the importance of doing on segregation of household Ward) so. waste. Mrs Primula Lama gave a All the participants could Training programme brief description on issues do proper segregation on Solid Waste and challenges related to at source. They even Management at Mouri waste management of 18 2nd Nov 2015 assured that they will Villa and Greendale Gangtok city. Susong Lohar give awareness to their road line, ICAR area gave a detailed demonstration neighbours who could (Dara Goan ward) on segregation of household not attend training. waste. Training program Training programme Mrs Primula Lama gave helped the participants on Solid Waste awareness and importance of to learn how to Management at waste segregation. A detailed 19 4th Nov 2015 demonstration on how to segregate the Ambali Heem, ICAR segregate waste at source household waste and Area (Dara Goan was given by Goma Chettri. the importance of doing Ward) so.

20 SIPMIU 92 DSMC

Sl Date Programme Activities Outcome No A detailed demonstration on Training Programme how to segregate waste at on Solid Waste source was given by Goma Demonstration on waste Management Below Chettri. Mrs Primula Lama segregation helped 20 5th Nov 2015 Greendale School, gave a brief description on households to learn how ICAR Area (Dara issues and challenges related to segregate waste.. Goan Ward) to waste management of Gangtok city. Training programme Participants were on Solid Waste Mrs. Goma Chettri gave a trained in waste 21 6th Nov 2015 Management Sundar detailed demonstration on segregation through Goan and SNT segregation of waste. awareness and Colony demonstration. Training programme Mrs Primula Lama gave Training helped on Solid Waste awareness on SWM. Goma participants to Management at SNT 22 7th Nov 2015 Chettri gave a detailed understand how to housing colony, ICAR demonstration on segregation segregate waste at Area (Dara Goan of waste at household level. home. Ward) A detailed demonstration on Training programme how to segregate waste at on Solid Waste source was given by Goma Participants learned Management at SNT Chettri. Mrs Primula Lama how to segregate waste 23 9th Nov 2015 Quarters and O P gave a brief description on and the importance of Dhakal area, ICAR issues and challenges related the same. Area (Dara Goan to waste management of Ward) Gangtok city. Training programme Mrs Primula Lama gave Participants were on Solid Waste awareness on SWM. Goma trained in waste Management at 24 10th Nov 2015 Chettri gave a detailed segregation through Sharma Colony, demonstration on segregation awareness and ICAR Area (Dara of waste at household level. demonstration. Goan Ward) A detailed demonstration on All the participants could Training programme how to segregate waste at do proper segregation on Solid Waste source was given by Goma at source. They even Management below Chettri. Mrs Primula Lama 25 26th Nov 2015 assured that they will Judge House, Phewa gave a brief description on give awareness to their Busty (Dara Goan issues and challenges related neighbours who could Ward) to waste management of not attend training. Gangtok city.

21 SIPMIU 93 DSMC

Sl Date Programme Activities Outcome No Training programme on Solid Waste Participants learned Mrs. Goma Chettri gave a Management Near how to segregate waste 26 27th Nov 2015 detailed demonstration on DSMC Office, Phewa and the importance of segregation of waste. Busty (Dara Goan the same. Ward) Training programme on Solid Waste Mrs Primula Lama gave Training helped Management at Mt awareness on SWM. Goma participants to 27 28th Nov 2015 Simvo Hotel Area and Chettri gave a detailed understand how to Below Krishi Bhawan demonstration on segregation segregate waste at Area, Phewa Busty of waste at household level home. (Dara Goan Ward) Demonstration on how to Training programme segregate waste at source Participants were on Solid Waste was given by Goma Chettri. trained in waste Management Below Mrs Primula Lama gave a 28 30th Nov 2015 segregation through Royal Residency brief description on issues awareness and Area, Phewa Busty and challenges related to demonstration. (Dara Goan Ward) waste management of Gangtok city. Susong Lohar gave a detailed Training programme demonstration on segregation Demonstration on waste on Solid Waste of household waste. Mrs segregation helped 29 4th Dec 2015 Management Near Primula Lama gave a brief households to learn how Now Office (Prerna description on issues and to segregate waste.. Samaj) challenges related to waste management of Gangtok city. Training programme on Solid Waste Goma Chettri gave a detailed Training helped Management near demonstration on segregation participants to 30 5th Dec 2015 Girls Hostel Area and of waste at household level. understand how to College Mrs Primula Lama gave segregate waste at Quarter(Prerna awareness on SWM. home. Samaj) Training programme Mrs Primula Lama gave on Solid Waste awareness and importance of Participants learned Management near waste segregation. A detailed how to segregate waste 31 7th Dec 2015 demonstration on how to Hotel Management segregate waste at source and the importance of area and near was given by Goma Chettri. the same. Assembly Church

22 SIPMIU 94 DSMC

Sl Date Programme Activities Outcome No Demonstration on how to All the participants could segregate waste at source Training programme do proper segregation was given by Goma Chettri. on Solid Waste at source. They even Mrs Primula Lama gave a 32 8th Dec 2015 Management near assured that they will brief description on issues UPI hostel area and give awareness to their and challenges related to Above Manipal area neighbours who could waste management of not attend training. Gangtok city. Training programme Goma Chettri gave a detailed on Solid Waste Participants learned demonstration on segregation Management near how to segregate waste 33 9th Dec 2015 of waste at household level. Believers Church and the importance of Mrs Primula Lama gave area and Ayurveda the same. awareness on SWM. area (Prerna Samaj) A detailed demonstration on how to segregate waste at Participants were Training programme source was given by Goma trained in waste on Solid Waste Chettri. Mrs Primula Lama 34 10th Dec 2015 segregation through Management near R gave a brief description on awareness and K Marble area issues and challenges related demonstration. to waste management of Gangtok city. Ms Susong Lohar gave awareness on SWM and Training programme importance of waste Demonstration on waste on Solid Waste segregation. Mrs. Goma segregation helped 35 29 Dec 2015 Management at ICAR Chettri did a detailed households to learn how Quarter Area demonstration on how to to segregate waste.. segregate waste at source.

11 Conclusion 12 The pilot project on SWM (streamlining the source segregation, collection and transportation) has been completed. Awareness on waste segregation and segregated collection for other wards also started. In this period (July to December 2015) Dara Gaon ward has been selected and completed all the activities related waste segregation and collection.

23 SIPMIU 95 DSMC

APPENDICES - 1

Progress of Gender Action Plan implementation (Tranche -2)

GENDER ACTION PLAN UNDER ADB ASSISTED PROJECTS OF NERCCDIP (Tranche 2)

Monitoring Result Time Present Activities Targets indicator indicators status/remark Outcome Sustainable Conduct of 1 gender  Municipal council Training At least 50% Completed the and increased sensitization seminar for officials (10/program report, list of seminar Q3 of details have access to each program city that city ) participants, participants Yr 1 already been better urban highlights gender issues  Women’s NGOs photographs, understood furnished as services in five in water supply, (5/program city) video about the an appendix in 1 program cities sanitation, solid waste including self-help gender issues Social Semi and drainage, and the groups and a need Annual Report need for women’s  20 community for 2013. involvement in the members (50% involvement implementation, O&M of women), including OF women. these services from scheduled castes (SCs) and scheduled tribes (STs)  State Investment Program Management and Implementation Unit (SIPMIU) staff of each state executing agency Outputs i. Conduct PCM with Targets PCM reports i.Views of Completed the (i) Improved women living in poor, Women from all and women from details water middle and upper wards photographs poor, middle have supply and income areas to representing and upper Q4 of already infrastructur understand their view poor, middle and income areas Yr 3 been e on water supply upper income are captured furnished point/stand posts, groups and as an timings for water supply incorporated appendix and water tariff. in water in Social supply Semi ii. Create awareness planning Annual among women through i.Records and Report mass media /IC photographs of ii. IC material 2013. material for need to mass media is used and at conserve water, need to and IC least 25 % be proactive regarding materials, ii.A women are reporting/repairs of mini survey aware about leaks, wastages etc. importance and

1 The five program cities are Agartala of Tripura, Aizawl of Mizoram, Shillong of , Kohima of , and Gangtok of Sikkim.

24 SIPMIU 96 DSMC

techniques of iii.Prepare list of to List of FHH and conservation poor female-headed ii.All the female record of of water households (FHHs) headed distribution of and provide connection households, water meter to and meter to them residing in areas them covered under iii.100% poor the project FHH received water connection and free meter i. Employment of Marginal and, i.Signed contract Atleast 20% During Civil contractor women in the other women of the contractor women are construct are sensitized construction of workers who work indicating that, it employed in ion and notice of pipelines, plants, etc., as labourers on the is mandatory to the project. All equal pay for with implementation of site employ women women equal work to ‘same pay forwork of for equal pay. workers are women is part equal value’ getting equal of Contract ii.Put up notices at- ii. Copy of notice pay for equal Agreement . least 6 locations for equal pay for work Employment publicizing equal pay for equal work to being given to equal work policy. (e.g. women and men. interested work site, at the notice women, board of ULB/UDD, iii the muster roll however SIPMIU office and local of the contractor response from employment exchange) women workers are iii. Incorporate in tender less at condition of the construction contractor for emphasis jobs. on employment for Separate women with equal pay attendance for for tranche 3 work. male and female labours is maintained by the contractors. (Refer Semi Annual Report- June2014) Individual labor has been registered under Sikkim Labor Protection Act,2005. (ii) Improved Prioritize connections to ii.All the female List of FHH who At Not applicable sanitation sewerage system of headed got sewerage 100% FHH project to Gangtok infrastructure poor female-headed households, connection connected to onset city. households in each residing in areas under the project sewerage program city covered under the system project Employment of women Marginal and, Similar Atleast 20% At Not applicable in construction of other women monitoring women are project to Gangtok sewage facilities, while workers who work indicators as employed in onset city.

25 SIPMIU 97 DSMC

implementing the Equal- as labourers on the used for water the project. All pay-for-work-of-equal- site supply women value policy workers are getting equal pay for equal work (iii) Improv Prioritize FHHs in the All the female i.List of FHHs 100% FHHs At Distribution of ed solid provision of household headed who received received project bins in three waste bins households, household bins household onset manageme residing in areas ii. mini survey bins wards is nt systems covered under the completed, project where 100% household has received the bins and segregation at source has started. (Snapshot attached here.) Conduct of public Women and men i. Report of Trash At 31 Public consultations among community public collection in project consultation community members members consultation with segregated onset completed in (target: 50% women) photographs manner Daragoan including SCs and STs, (biodegradable ward till Dec and NGOs on the ii. Action points and non 2015, details manner and schedule of and follow ups biodegradable) will be trash collection is done in all furnished in the wards. Semi Annual Report July- Dec2015 Conduct an exploratory i.. rag pickers and Study report is i.The study At To be started, study on possible women from lower prepared report contains project tentative date livelihood opportunities and middle income all objectives onset of from available groupii.. Local and and action commenceme recyclable materials regional market for points.Ii.Under nt is and the market for marketing of the standing about September possible products from products livelihood 2015. these recycled opportunity materials increased among project staff Conduct of training on Rag pickers and i.Training report Rag pickers At To be started, alternative livelihoods Women from lower with photographs and poor project for rag picker and poor and middle income ii.mini survey women are onset women using recyclable community of trainees using materials (e.g., members recyclable papiermache, etc.) materials for alternative livelihood (iv) Strengthe Conduct of Women community Survey report SIPMIU and At IDC has ned project demographic survey of members and tables of DSMC staff project already done implementatio program city, showing analyzed data members have onset the study. The n capacity of gender differential knowledge of list of female executing access to urban gender headed

26 SIPMIU 98 DSMC

agency services, income / differential household in poverty levels, among access to use. other such indicators, urban Primary specifically, between services, female male-headed and income. earner1221 female-headed Poverty levels against households and among 10,730. (Refer SCs and STs consolidated Report by IDC Pg 23- 27)However further discussion in this regard shall be Initiated to disseminate the information to project staff. Instituting geographic Stakeholders of the Assessment of Project At project PPMS Report and sex-disaggregated project project management onset submitted to project management management information ADB IN 2013, information system information system in baseline system place with sex survey disaggregated completed data where female headed household identified. Conduct of on-the-job SIPMIU staff Assessment of Gender At SIPMIU staff capacity-building gender inclusion is project has been activities for SIPMIU on sensitivity level observed in all onset sensitized on gender-sensitive of SIPMIU staff, the project Gender equity recruitment, whether the staff procedures components management, members are and has procurement and following gender attended

27 SIPMIU 99 DSMC

contract management, equity various project and component in all trainings. performance their project Furthermore, monitoring, safeguard procedures seven female compliance, land staff employed acquisition, and in SIPMIU out preparation of of thirteen. feasibilities studies and detailed designs (v) Strengthe Constituting new ULBs All residents of the ULB record of ULB have There is ned local in Gangtok and Aizawl municipalities in men and women atleast 33% already a government with at least 33% each program city officials women policy of the for women officials; that will be reached officials state to ensure sustainable Reconstitution of by the Project 33% job to the service Shillong ULB with at women for delivery least 33% women effective officials in place2 service delivery. Training of municipal Men and women Men and women Four Training staff, at least 33% of municipal staff municipal staff Municipal Programmes whom are women, on staff is provided to O&M of services, trained on Municipal staff financial management, O&M, by IDC from and regulation September to enforcement financial December manageme 2014 where nt and female regulation participation . enforcemen is Ten t of which altogether 33% are women

2 The state Government has recently announced the reservation of women in ULB’s up to 50%.

28 SIPMIU 100 DSMC

29 SIPMIU 101 DSMC

30 SIPMIU 102 DSMC APPENDICES - 1

Progress of Gender Action Plan implementation (Tranche -2)

GENDER ACTION PLAN UNDER ADB ASSISTED PROJECTS OF NERCCDIP (Tranche 2)

Monitoring indicator Result indicators Time Present Activities Targets status/remark Outcome Sustainable and Conduct of 1 gender sensitization  Municipal council officials Training report, list of At least 50% seminar Completed the increased access to seminar for each program city that (10/program city ) participants, photographs, participants understood Q3 of details have better urban services in highlights gender issues in water  Women’s NGOs (5/program video about the gender issues already been 1 Yr 1 five program cities supply, sanitation, solid waste and city) including self-help and a need for furnished as an drainage, and the need for women’s groups involvement OF women. appendix in Social involvement in the implementation,  20 community members Semi Annual O&M of these services (50% women), including Report 2013. from scheduled castes (SCs) and scheduled tribes (STs)  State Investment Program Management and Implementation Unit (SIPMIU) staff of each state executing agency Outputs i. Conduct PCM with women living in Targets PCM reports and i.Views of women Completed the (i) Improved water poor, middle and upper income areas Women from all wards photographs from poor, middle and details have supply and to understand their view on water representing poor, middle upper income areas already been infrastructure supply point/stand posts, timings for and upper income groups are captured and Q4 of Yr furnished as water supply and water tariff. incorporated in water 3 an appendix supply planning in Social ii. Create awareness among women Semi Annual through mass media /IC material for ii. IC material is used Report 2013. need to conserve water, need to be and at least 25 %

1 The five program cities are Agartala of Tripura, Aizawl of Mizoram, Shillong of Meghalaya, Kohima of Nagaland, and Gangtok of Sikkim.

103 proactive regarding reporting/repairs women are aware about of leaks, wastages etc. i.Records and importance and photographs of mass techniques of iii.Prepare list of to poor female- media and IC materials, conservation of water headed households (FHHs) and ii.A mini survey provide connection and meter to them

List of FHH and record of iii.100% poor FHH ii.All the female headed distribution of water meter received water households, residing in to them connection and free areas covered under the meter project i. Employment of women in the Marginal and, other women i.Signed contract of the Atleast 20% women are During Civil contractor construction of pipelines, plants, etc., workers who work as contractor indicating that, it employed in the project. constructio are sensitized with implementation of ‘same pay labourers on the site is mandatory to employ All women workers are n and notice of forwork of equal value’ women for equal pay. getting equal pay for equal pay for ii.Put up notices at-least 6 locations equal work equal work to publicizing equal pay for equal work ii. Copy of notice for equal women is part of policy. (e.g. work site, at the notice pay for equal work to Contract board of ULB/UDD, SIPMIU office and women and men. Agreement . local employment exchange) Employment iii the muster roll of the being given to iii. Incorporate in tender condition of contractor interested the contractor for emphasis on women, however employment for women with equal pay response from for tranche 3 work. women workers are less at construction jobs. Separate attendance for male and female labours is maintained by the contractors. (Refer Semi Annual Report- June2014) Individual labor has been

104 registered under Sikkim Labor Protection Act,2005. (ii) Improved sanitation Prioritize connections to sewerage ii.All the female headed List of FHH who got At project Not applicable to infrastructure system of poor female-headed households, residing in areas sewerage connection under 100% FHH connected onset Gangtok city. households in each program city covered under the project the project to sewerage system

Employment of women in construction Marginal and, other women Similar monitoring Atleast 20% women are At project Not applicable to of sewage facilities, while workers who work as indicators as used for employed in the project. onset Gangtok city. implementing the Equal-pay-for-work- labourers on the site water supply All women workers are of-equal-value policy getting equal pay for equal work (iii) Improved solid Prioritize FHHs in the provision of All the female headed i.List of FHHs who received 100% FHHs received At project Distribution of waste management household bins households, residing in areas household bins household bins onset bins in three systems covered under the project ii. mini survey wards is completed, where 100% household has received the bins and segregation at source has started. (Snapshot attached here.) Conduct of public consultations Women and men community i. Report of public Trash collection in At project 31 Public among community members (target: members consultation with segregated manner onset consultation 50% women) including SCs and STs, photographs (biodegradable and non completed in and NGOs on the manner and biodegradable) is done Daragoan ward till schedule of trash collection ii. Action points and follow in all the wards. Dec 2015, details ups will be furnished in Semi Annual Report July- Dec2015

105 Conduct an exploratory study on i.. rag pickers and women from Study report is prepared i.The study report At project To be started, possible livelihood opportunities from lower and middle income contains all objectives onset tentative date of available recyclable materials and the groupii.. Local and regional and action commencement is market for possible products from market for marketing of the points.Ii.Understanding September these recycled materials products about livelihood 2015. opportunity increased among project staff Conduct of training on alternative Rag pickers and Women from i.Training report with Rag pickers and poor At project To be started, livelihoods for rag picker and poor lower and middle income photographs women are using onset women using recyclable materials community members ii.mini survey of recyclable materials for (e.g., papiermache, etc.) trainees alternative livelihood (iv) Strengthened Conduct of demographic survey of Women community members Survey report and tables of SIPMIU and DSMC staff At project IDC has already project implementation program city, showing gender analyzed data members have onset done the study. capacity of executing differential access to urban services, knowledge of gender The list of female agency income / poverty levels, among other differential access to headed such indicators, specifically, between urban services, income. household in use. male-headed and female-headed Poverty levels Primary female households and among SCs and STs earner1221 against 10,730. (Refer consolidated Report by IDC Pg 23-27)However further discussion in this regard shall be Initiated to disseminate the information to project staff. Instituting geographic and sex- Stakeholders of the project Assessment of project Project management At project PPMS Report disaggregated project management management information information system in onset submitted to ADB information system system place with sex IN 2013, baseline disaggregated data survey completed where female headed household identified. Conduct of on-the-job capacity- SIPMIU staff Assessment of gender Gender inclusion is At project SIPMIU staff has building activities for SIPMIU on sensitivity level of SIPMIU observed in all the onset been sensitized gender-sensitive recruitment, staff, whether the staff project procedures on Gender equity

106 management, procurement and members are following components and contract management, project and gender equity component in has attended performance monitoring, safeguard all their project procedures various trainings. compliance, land acquisition, and Furthermore, preparation of feasibilities studies and seven female staff detailed designs employed in SIPMIU out of thirteen. (v) Strengthened local Constituting new ULBs in Gangtok All residents of the ULB record of men and ULB have atleast 33% There is already a government for and Aizawl with at least 33% women municipalities in each program women officials women officials policy of the state sustainable service officials; Reconstitution of Shillong city that will be reached by the to ensure 33% job delivery ULB with at least 33% women officials Project to the women for in place2 effective service delivery. Training of municipal staff, at least Men and women municipal Men and women municipal Four Training

2 The state Government has recently announced the reservation of women in ULB’s up to 50%.

107 33% of whom are women, on O&M of staff staff Municipal staff is Programmes services, financial management, and trained on O&M, provided to regulation enforcement financial Municipal staff by management and IDC from September to regulation December 2014 enforcement of where female which 33% are participation . is women Ten altogether

108

109

110

Appendix 2:

Status Report on Awareness Programs at Dara Gaon Ward.

1 Introduction After completion of activities related to awareness on waste segregation at household level at pilot wards Dara Gaon ward has been taken for the same. As per the cluster formation, number of households and commercial properties in Dara Gaon ward is given in the following table. Table 1: Households in Dara Gaon Ward Sl Category Number of Households No. 1 Households (Number)1 3763 2 Commercial2 247 2 Status of Awareness on Waste Segregation at Source and Distribution of Dustbin All the clusters in the Dara Goan Ward (Ward No 12) have been provided awareness cum training program at their Village itself. Community organisers in coordination with Social Scientist, SIPMIU and Social Mobiliser of DSMC formed clusters containing minimum of 50 households depends on the locality. Clusters have been formed for the easiness of providing awareness and demonstration on waste segregation at source, distribution of dust bins and follow up activities. A total of 67 clusters have been formed in Dara Goan ward. 3 Awareness on Waste Segregation at Dara Goan Ward Further to the completion of awareness and distribution of dust bins at pilot wards, it has been decided to commence the activities to the adjacent ward- Dara Goan, Ward no. 12. In this regard a meeting has been conducted with Mr. Bhaskar Basnett, Ward councilor of Dara Goan and Apex Committee members on 13th May 2015 at 11am. Dara Goan ward is having four regions namely ICAR Area, Lumsay Area, Phewa Busty and Prerna Samaj and each region is having a representative. All the four regions together formed a committee named Apex committee. The committee is actively working on various activities especially waste collection at Dara Gaon ward. Each region is having approximate 150 households of land lords. Total number of households shall be much higher than this number while including the tenants of each land lords. In the meeting, it was assured that list of households will be provided by Apex committee with in a period of ten days. Community organisers will form clusters in consultation with Apex committee and fix convenient dates for awareness program and distribution of dust bins. 67 clusters have been formed in this ward and 40 training programs on waste segregation has been conducted followed by distribution of bins. The status of the Meeting conducted are summarized in the below table. Table 2: Status of Meeting Conducted at Dara Goan Ward SL DATE OF NO OF AREA VENUE HOUSEHOLD NO MEETING CLUSTERS 2 50 1 27-Jul-15 ABOVE GAS GODOWN 79 LUMSAY LUMSAY OPP SCHOOL 2 51 2 28-Jul-15 ROAD 66

1 Census, 2011. 2from (Sl No 2 to Sl No 9) IDC’s report

1 SIPMIU 111 DSMC

SL DATE OF NO OF AREA VENUE HOUSEHOLD NO MEETING CLUSTERS 2 66 3 29-Jul-15 BELOW LUMSAY SCHOOL 72 LUNSAY BELOW POWER 2 77 4 30-Jul-15 STATION 69 2 42 5 31-Jul-15 BELOW POWER STATION 56 2 79 6 01-Aug-15 BELOW IGNOU OFFICE 43 BELOW HAWA 2 53 7 03-Aug-15 GHAR,LUMSAY 25 BELOW AND ABOVE 2 67 8 04-Aug-15 JOREDHARA 52 2 56 9 05-Aug-15 BELOW JOREDHARA 35 2 64 10 06-Aug-15 BELOW POWER STATION 64 11 07-Aug-15 OPP POWER STATION 1 96 2 51 12 29-Oct-15 PALMU SAMAJ 54 13 30-Oct-15 NEAR GREENDALE 1 40 2 47 14 31-Oct-15 GREENDALE ROADLINE 48 2 73 15 02-Nov-15 BELOW GREENDALE 65 3 45 16 04-Nov-15 ABOVE MANIPAL 69 45 ICAR 2 53 17 05-Nov-15 UMAKUNJ LINE 97 2 65 18 06-Nov-15 SUNDAR GOAN 32 2 64 19 07-Nov-15 SNT COLONY AREA 29 NEAR OP DHAKAL CLINIC 2 61 20 09-Nov-15 AREA 59 2 56 21 10-Nov-15 SHARMA COLONY 77 2 64 22 26-Nov-15 BELOW JUDGE HOUSE 36 PHEWA BELOW ROYAL 2 42 23 27-Nov-15 BUSTY RESIDENCY 42 2 55 24 28-Nov-15 BELOW MT SIMVO 71

2 SIPMIU 112 DSMC

SL DATE OF NO OF AREA VENUE HOUSEHOLD NO MEETING CLUSTERS NEAR ICAR AREA 2 52 25 30-Nov-15 BELOW DSMC OFFICE 89 3 56 26 04-Dec-15 NEAR NOW OFFICE 69 55 GIRLS HOSTEL AREA 3 47 27 05-Dec-15 COLLEGE QUARTER 43 ASHA TAILOR 47 GRIMA NIWAS 3 41 28 07-Dec-15 HOTEL MANG INST 48 ASSEMBLY CHURCH 43 PRERNA KALO BUIDLING 3 34 SAMAJ 29 08-Dec-15 ABOVE MANIPAL 67 UPF HOSTEL 47 BELIVERS CHURCH 3 53 BELOW MEAT SHOP 34 30 09-Dec-15 SIGN IN ROADLINE TO 81 AYURVEDA 3 53 31 10-Dec-15 R K MARBLE 39 63 4 Distribution of Free Dust Bins As mentioned above, along with awareness programs, free dust bins were distributed to all the households on the same day itself. Even though it was conveyed that, GMC will take care of distribution of dust bins but at the outset, SIPMIU had to do the same. Snapshots

Awareness program and distribution of dust bin at Lumsay area

3 SIPMIU 113 DSMC

Awareness program and distribution of dust bin at ICAR area

Awareness program and distribution of dust bin at Phewa Busty area

Awareness program and distribution of dust bin at Prerna Samaj

5 Follow up Activities Further to the awareness programs and distribution of dust bins, follow up survey has been conducted on a door to door wise with structured questionnaire. It has been noted that, even after providing awareness and demonstration on waste segregation, a few households are still doing segregation in unscientific manner. Hence, demonstration also given to the households whose segregation seems to be poor. Follow up has been done at each collection points along with waste

4 SIPMIU 114 DSMC

collection vehicle. This exercise seems to be very effective as we could assess the quality of waste segregation practice of households as well as waste collection practice of agency. On spot instructions could be given both the stake holders. Weight of segregated waste has been taken from each waste collection point with weighing machine for study purpose. 6 Door to Door Follow up Survey Door to door follow up survey has been commenced at Dara Goan ward with structured questionnaire. It was noticed that, most of the people are misusing the free dust bins for some other purpose instead of waste segregation. Community organisers were given strict instructions to the households to utilize the free dust bins in a proper manner. Households were also offered demonstration if the satisfaction level of waste segregation is poor or not yet started. Snap Shots

5 SIPMIU 115 DSMC

Snap Shots: Households Doing Segregation with Their Own Bins

6 SIPMIU 116 DSMC

7 SIPMIU 117 DSMC Appendix 3 Photographs of Various Activities Sl Date Activity Photographs No 22nd July 2015

Field visit with Social 1 Scientist

Field Visit for Monitoring and Supervision of Waste A sticker was given to each community organizer collecting practices. to mark the houses were follow up was completed 27th July 2015

Training programme on Solid Waste Management 2 at Above Gas Godown Area, Lumsay (Dara Goan Ward)

Awareness Programme Distribution of dustbins

118 Appendix 3 Photographs of Various Activities Training programme on 28th July 2015 Solid Waste Management at School Area, Lumsay (Dara Goan Ward)

3

Awareness Programme Demonstration on Waste Segregation Training Programme on 29th July 2015 Solid Waste Management at Above Gas Godown Area, Lumsay(Dara Goan Ward)

4

Awarness Programme Training on waste segregation

119 Appendix 3 Photographs of Various Activities 30th July 2015

Training Programme on Solid Waste Management 5 at Above Gas Godown Area, Lumsay(Dara Goan Ward)

Awareness Programme Training on waste segregation 31st July 2015

Training Programme on Solid Waste Management 6 at Power Station, Lumsay(Dara Goan Ward)

Awareness Programme Demonstration on Waste Segregation

120 Appendix 3 Photographs of Various Activities 1st August 2015

Training Programme on Solid Waste Management 7 at Opposite Housing Colony

Awareness Programme Demonstration on Waste Segregation 3rd August 2015

Training Programme on 8 Solid Waste Management at Below IGNOU Office

Awareness Programme Training on waste segregation.

121 Appendix 3 Photographs of Various Activities 4th August 2015

Training Programme on 9 Solid Waste Management at Joredhara

Demonstration on Waste Segregation Awareness Programme 5th August 2015

Training Programme on 10 Solid Waste Management at Joredhara

Awareness Programme Training on waste segregation.

122 Appendix 3 Photographs of Various Activities 6th August 2015

Training Programme on 11 Solid Waste Management at Joredhara

Training on waste segregation. Awareness Programme 7th August 2015

Training Programme on 12 Solid Waste Management at Joredhara

Training on waste segregation. Awareness Programme

123 Appendix 3 Photographs of Various Activities 17th August 2015

Monitoring and supervison of Waste 13 collecting practices of households of Tadong Ward

Monitoring and Supervision Monitoring and Supervision

18th August 2015

Quantification survey 14 conducted for Ranipool Ward

Taking measurement of segregated waste Assessing quality of waste segregation

124 Appendix 3 Photographs of Various Activities 29 Oct 2015

Training Programme on Solid Waste Management 15 at Palbhu Samaj, ICAR Area (Dara Goan Ward)

Awareness Programme Distribution of dustbins. 30 Oct 2015

Training Programme on Solid Waste Management 16 at Greendale School Area, ICAR Area (Dara Goan Ward)

Awareness Programme Training on waste segregation..

125 Appendix 3 Photographs of Various Activities 31 Oct 2015

Training Programme on Solid Waste Management 17 at Umakunj Line and Sundar Goan,ICAR Area(Dara Goan Ward)

Awareness Programme Demonstration on Waste Segregation. 2nd November 2015

Training Programme on Solid Waste Management 18 at Mouri Villa and Greendale Roadline,ICAR Area (Dara Goan Ward)

Awareness Programme Awareness Programme

126 Appendix 3 Photographs of Various Activities 4th November 2015

Training Programme on Solid Waste Management 19 at Ambali Heem, ICAR Area (Dara Goan Ward)

Awareness Programme Awareness Programme. 5th November 2015

Training Programme on Solid Waste Management 20 Below Greendale School, ICAR Area (Dara Goan Ward)

Awareness Programme. Awareness Programme

127 Appendix 3 Photographs of Various Activities 6th November 2015

Training Programme on Solid Waste Management 21 Sundar Goan and SNT Colony

Awareness Programme Distribution of dust bins. 7th November 2015

Training Programme on Solid Waste Management 22 at SNT housing colony, ICAR Area (Dara Goan Ward)

Distribution of dust bins. Awareness Programme

128 Appendix 3 Photographs of Various Activities 9th November 2015

Training Programme on Solid Waste Management 23 at SNT Quarter and O P Dhakal area, ICAR Area (Dara Goan Ward)

Awareness Programme. Awareness Programme 10th November 2015

Training Programme on Solid Waste Management 24 at Sharma Colony, ICAR Area (Dara Goan Ward)

Awareness Programme Awareness Programme

129 Appendix 3 Photographs of Various Activities 26th November 2015

Training Programme on Solid Waste Management 25 below Judge House, Phewa Busty (Dara Goan Ward)

Awareness Programme Awareness Programme. 27th November 2015

Training Programme on Solid Waste Management 26 Near DSMC Office, Phewa Busty (Dara Goan Ward)

Awareness Programme Awareness Programme.

130 Appendix 3 Photographs of Various Activities 28th November 2015

Training Programme on Solid Waste Management at Mt Simvo Hotel Area 27 and Below Krishi Bhawan Area, Phewa Busty (Dara Goan Ward)

Distribution of dustbins Awareness Programme 30th November 2015

Training Programme on Solid Waste Management 28 Below Royal Residency Area, Phewa Busty (Dara Goan Ward)

Awareness Programme Distribution of dustbins

131 Appendix 3 Photographs of Various Activities 4th December 2015

Training Programme on Solid Waste Management 29 Near Now Office (Prerna Samaj)

Awareness Programme Distribution of dustbins 5th December 2015

Training Programme on Solid Waste Management 30 near Girls Hostel Area and College Quarter(Prerna Samaj)

Distribution of dustbins. Awareness Programme

132 Appendix 3 Photographs of Various Activities 7th December 2015

Training Programme on Solid Waste Management 31 near Hotel Mangment area and Near Assembly Church

Distribution of dustbins.. Awareness Programme 8th December 2015

Training Programme on Solid Waste Management 32 near UPI hostel area and Above Manipal Area

Demonstration on waste segregation. Awareness Programme

133 Appendix 3 Photographs of Various Activities 9th December 2015

Training Programme on Solid Waste Management 33 near Believers Church area and Ayurveda area (Prerna Samaj)

Awareness Programme Awareness Programme 10th December 2015

Training Programme on 34 Solid Waste Management near R K Marble area

Distribution of dustbins.. Awareness Programme

134 Appendix 3 Photographs of Various Activities 29 December 2015

Training Programme on 35 Solid Waste Management at ICAR Quarter Area

Demonstration on waste segregation. Awareness Programme

135 SEMI ANNUAL SOCIAL SAFEGUARD MONITORING REPORT

Loan Number: 2528/2834 IND Reporting Period: (July- December 2015)

INDIA: North Eastern Region Capital Cities Development Investment Program

Project City: Kohima, Nagaland State

Implementing Agency: State Investment Program Management and Implementation Unit Executing Agency: Urban Development Department,

January 2016 Kohima

136

ABBREVIATIONS

ADB - Asian Development Bank BTA - Bridging Technical Assistance CC - Construction Contractor DOC - Date of Completion DOS - Date of Start DSMC - Design, Supervision and Management Consultant EA - Executing Agency EARP - Environmental Assessment & Review Procedure EIA - Environmental Impact Assessment EO - Environmental Officer GoI - Government of India IA - Implementing Agency IEE - Initial Environmental Examination IPCC - Investment Program Coordination Cell MFF - Multi-tranche Financing Facility MLD - Million Liters per Day mn - Million MoUD - Ministry of Urban Development NEA - National Executing Agency NERCCDIP - North Eastern Region Capital Cities Development Investment Program NSC - National level steering committee PD - Project Director PPTA - Project Preparatory Technical Assistance SEA - State level Executing Agency SIPMIU State Investment Program Management and Implementation Unit UDD - Urban Development Department

137i Table of Contents

1 INTRODUCTION ...... 3 2 IMPLEMENTATION ARRANGEMENTS ...... 3 3 SUB PROJECT COMPONENTS IN KOHIMA MUNICIPAL COUNCIL AREA ...... 5 4 SOCIAL SAFEGUARD ACTIVITIES FOR TRANCHE -1&2 SUB PROJECTS ...... 7 5 COMPLIANCE STATUS OF LOAN COVENANTS ...... 14 6 PROJECT IMPACT ...... 15 7 POLICY AND LEGAL FRAMEWORK ...... 15 8 VALIDATION AND VERIFICATIONS OF APS ...... 16 9 PUBLIC CONSULTATIONS AND DISCLOSURE OF RP ...... 16 10 GRIEVANCE REDRESSAL ...... 16 11 MONITORING AND REPORTING ...... 16 12 CONCLUSION AND ACTION PLAN ...... 16

List of Tables Table 1: Institutional Roles ...... 4 Table 2:Sub projects &components ...... 5 Table 3: Status of Civil Construction and RP Implementation ...... 9 Table 4: Ownership Details of Lands for Community Toilets ...... 10 Table 5: Ownership Details of Lands for Service Reservoirs ...... 10 Table 6: Summary of Community Development, Public Participation and Gender Sensitization programs conducted during the period of July to December, 2015 in Kohima . 12 Table 7: Status of Loan Covenants ...... 14

List of Appendices

Appendix 1: Photographs of Inauguration of Water Treatment Plant Appendix 2: Photographs of Various Activities Appendix 3: Brief Report on Pilot Project

138ii 1 Introduction 1. The Government of India has obtained a loan from the Asian Development Bank towards financing the North Eastern Region Capital Cities Development Investment Program. The loan is under the Multi Tranche Financing Facility of the Asian Development Bank to improve certain prioritized urban infrastructures mainly in the sectors of water supply, solid waste management and sanitation in 5 North Eastern Region Capital Cities namely, Agartala, Aizwal, Gangtok, Kohima and Shillong. The Program will (i) improve the urban infrastructure (ii) strengthen the urban institutions towards better service delivery, project management and implementation.

2. The NERCCDIP is estimated to be completed in a span of 6 years. The program in Kohima envisages investments in three projects corresponding to three loan tranches of ADB. The State Investment Program Management & Implementation Unit is the implementing agency at State level. M/s CDM Smith India Private Limited (Formerly Wilbur Smith Associates) has been engaged as the Design, Construction Supervision & Management Consultant (DSMC) for this city.

3. Two subprojects are taken up under tranche-1, one in the sector of Water Supply (WS) and another in Solid Waste Management (SWM), are now under implementation in Kohima. The water supply sub project is for the refurbishment of the existing Kohima Water Supply Scheme. The solid waste management sub project focuses in developing a new solid waste management site in the outskirts of Kohima at Lerie.

4. Two subprojects were planned originally under Tranche-2. The major one is the civil work for providing a new underground water supply distribution pipe system for a total length of 318 km. The contract agreement has been executed in February 2013 and the trenching & laying of pipes was started in January, 2014. Around 25.54% (as on 31st Dec, 2015) of the works has been completed against the revised targeted progress of 33.95%. The work could be completed within one year. The other subproject in Tranche-2 is for installation of 21 bulk water meters & 6000 metered connections in the new distribution system. The works can be started only after a substantial work progress at site of the above mentioned contract package for laying distribution net-works.

5. Apart from the above two sub projects envisaged originally, 4 new additional subprojects were also proposed under Tranche-2 which is listed out in Table 2.

6. This is the consolidated report on implementation of Social Safeguard Activities for the period from 1stJuly, to 31st Dec 2015, and this is prepared in compliance with the ADB‟s Safeguard Policy Statement, (SPS 2009). 2 Implementation Arrangements 7. The Ministry of Urban Development (MOUD) is the national-level executing agency (EA) of the program. An IPCC is also established in MOUD incorporating a Social Safeguard Officer. A National Steering Committee (NSC) will monitor the fund use and overall implementation performance of the Investment Program. In each State there will be a State Steering Committee (SSC), an Investment Program Empowered Committee (IPEC) and a State Investment Program Monitoring and Implementation Unit (SIPMIU).The SIPMIU is responsible for overall program implementation, monitoring and supervision in the respective cities.

1393

8. The SIPMIU will have a Social Safeguard Unit headed by a sociologist. Depending on the anticipated volume of resettlement and other related issues, a Resettlement Officer & supporting NGOs may be required as part of the Unit. ROs and NGOs will be responsible for RP implementation. However, in small projects where resettlement issues are not anticipated or minimal, an extensive staffing in the SSU is not essential. In case any resettlement issues arise during the subsequent stages of implementation, the services of competent personnel/ agencies like RO/ NGO shall be engaged. The generalized institutional roles of the involved entities are identified in Table 1 as a guide line. The Social Safeguards Unit under SIPMIU will take care of redressing grievances and mitigating negative social impacts caused due to the project with the aid of the existing system and shall request the Program Director for further reinforcement of support staff/ NGOs if required. Table 1: Institutional Roles Sl Activities Agency no Responsible Sub-project Initiation Stage 1 Finalization of sites/alignments for sub-projects SIPMIU&DSMC 2 Disclosure of proposed land acquisition and sub-project SIPMIU details by issuing public notice 3 Meetings at community/ house hold level with APs of SSU/&NGO land/property 4 Formation of Valuation Committees SIPMIU RP Preparation Stage 5 Conducting Census of all APs SSU/&NGO 6 Conducting FGDs/ meetings / workshops during SIA SSU/&NGO surveys 7 Computation of Replacement Values of land/properties SSU&DSMC proposed for acquisition and for associated assets 8 Categorization of APs for finalizing entitlements SSU 9 Formulating compensation and rehabilitation measures SIPMIU 10 Conducting discussions/ meetings with all APs and other SIPMIU/&NGO stake holders 11 Fixing compensation for land/property with title holders VC/SIPMIU 12 Finalizing entitlements and rehabilitation packages SIPMIU 13 Disclosure of final entitlements and rehabilitation SIPMIU/&NGO packages 14 Approval of RP IPCC/ADB 15 Sale deed execution and payment of compensation SIPMIU 16 Taking possession of land SIPMIU RP Implementation Stage 17 Implementation of proposed rehabilitation measures SSU/&NGO 18 Consultations with APs during rehabilitation activities SSU/&NGO 19 Grievances redressal SSU/&NGO/GRC 20 Internal monitoring SIPMIU 21 External monitoring External Agency

SSU= Social Safeguards Unit ,AP=affected person, VC=valuation committee, FGD=focus group discussions, GRC = grievance redress committee, NGO = nongovernment organization, SIPMIU = state-level investment program management and implementation unit, IPCC = investment program coordination cell, RO = resettlement officer, RP=resettlement plan, SIA=social impact assessment.

1404 3 Sub Project Components in Kohima Municipal Council Area 9. The subprojects taken up under Tranche-1 & 2 in Kohima Municipal Council are summarized in Table.2 Table 2:Sub projects &components Sl Name of the Tranche Major Components no subproject and its Current Status 1 Refurbishment of Tranche-1  Construction of 18 new RCC Kohima Water reservoirs Supply Scheme.  Rehabilitation of the water treatment plant at . The subproject is  Supply& installation of two electro- fully completed chlorinators in the water treatment plant 2 Civil Works and Tranche-1  Construction of 2 km length approach Procurement of road. Equipment for  Construction of 50 tons/ day capacity Sanitary Land Fill, compost plant Compost Plant and  Development of a sanitary land fill site Approach Road at of 8000 sqm area Lerie  Formation of 16000 sqm land for future land fills  Installation of a leachate treatment plant to handle leachate @ 75000 The subproject is ltr/day 98% completed  Construction of support facilities like i. Internal roads ii. Dedicated electrical substation with generator back up iii. Service buildings like administrative block, garages for primary & secondary vehicles, toilet block, security house, weigh bridge control room etc. iv. Electrification of the entire buildings and yard lighting of the site v. Water supply facilities to all buildings including firefighting facilities vi. Green belt & landscaping the entire site Development of a new solid waste management site at Lerie. In addition to the above, SIPMIU is proposing following works at SWM site in Lerie under Tranche 1 as additional works.  Construction of 15 retaining walls  Restoration of damaged approach road  Construction of one step drain. 3 Supplying and laying Tranche-2  Providing a new water supply pipe of distribution line distribution network of total length

1415 Sl Name of the Tranche Major Components no subproject and its Current Status network of 318 km in of 318 km Kohima Municipal  Installation of 21 bulk water meters Council area  Providing 6000 metered house connections The subproject is 25.54% completed. 4 Supply & installation Tranche-2  Procurement & installation of 21 bulk of 21 bulk water water meters at the out lets of meters and 6000 distribution tanks, main storage tank metered connections at the water treatment plant and other nodal points  Procurement & installation of 6000 Bidding shall be domestic water meters and changing arranged after a over the existing consumer substantial progress connections from the bunch system to of the Subproject the underground loop system which under Sl No:3 will be installed under subproject-3 above 5 Development of a Tranche-2  Procurement of 8 vacuum tankers for Septage (Additional septage collection & transportation to Management Unit in Works) septage treatment plant. Kohima  Development of a Septage Treatment Unit of 0.90 mld capacity at Dzuruzou Technical bid has on the outskirts of Kohima including been opened on 15th access roads and staff quarters. Dec 2015. 6 Construction of 5 Tranche-2 The toilet blocks are proposed in the Community Toilet (Additional following locations Blocks in Kohima Works)  Pay & Use Toilet Block near New Municipal Council Secretariat area Area  Pay & Use Toilet Block near Kezekie Public Market  Community Toilet Block near North Construction Police Station. activities of all  Community Toilet Block at upper A.G community toilets colony (1). have been started in  Community Toilet Block at upper A.G the month of colony (2). November 2015. Progress till 31st December 2015 is about 20%. 7 Construction of 7 Tranche-2 The details of the proposed reservoirs Ground Level Water (Additional are as below: Tanks in Kohima Works)  Common Storage Reservoir near Municipal Council Botanical Garden of capacity 1.547 Area million litres for i. Botanical Garden & ii. Upper AG Hydraulic Zones  Distribution tank at Upper AG of capacity 0.027 million litres for Upper AG Hydraulic Zone.

1426 Sl Name of the Tranche Major Components no subproject and its Current Status  Common Storage Reservoir near KMC office of capacity 0.936 million Out of 7, construction litres for (i). Rifles HQ, (ii). of 1 tank (location: Local Ground & (iii). War Cemetery North Police Station) Hydraulic Zones has been  Storage Reservoir of capacity 0.085 commenced in the million litres for Lower Forest month of November Hydraulic Zone 2015 and the  Storage Reservoir of capacity 0.085 remaining are under million litres for Paramedical bidding stage. Hydraulic Zone  Storage Reservoir of capacity 0.149 million litres for North Police Station Hydraulic Zone  Storage Reservoir of capacity 0.209 million litres at Ruliefou for Government Polytechnic Hydraulic Zone.

8 Integrated Solid Tranche-2  Development of a SWM site for Waste Management (Additional Kohima (98% of physical work has Project for Kohima Works) been completed)  Procurement of primary collection vehicles, secondary collection vehicles- Refuse Compactor vehicles, Bins for Solid Waste Collection, Personnel Protective Equipment Under Bidding Stage (PPE) etc.  Installation of Solid Waste Recycling Facilities for Dry Waste, Packing Units Machineries and associated Civil Works at the SWM site 4 Social Safeguard Activities for Tranche -1&2 Sub projects 4.1. Introduction 10. In order to identify the Resettlement Impacts, if any, due to the subproject implementation, SIPMIU officials & DSMC experts have carried out sufficient site visits and consultative inspections in the project areas during the preparation of RP. Based on this and further discussions held with the local public in the city, it has been confirmed that the implementation of the above subprojects would not have any Involuntary Resettlement (IR) impact at any stage. Hence all the 8 sub projects of tranche-1&2 with respect to Involuntary Resettlement impact would be under „Category C‟. However, periodic site visits and discussion with local public will be continuing during the project implementation to confirm that no resettlement issues remain unnoticed or unaddressed. 4.2. Scope of Impact 4.2.1. Tranche -1 Sub Projects 11. Solid Waste Management: Permanent land acquisition is not envisaged in both the sub projects taken up under tranche -1. The development of Solid Waste

1437 Management Plant at Leire is confined in the land owned by the Kohima Municipal Corporation. The construction activities are in a final stage and the progress till 31st December 2015 is 98%.

12. As the SWM site at Lerie is surrounded by agricultural lands, three households having agricultural land nearby the SWM site encroached to the area earmarked for SWM (but far away from SWM site as well as green belt area) .They constructed 3 cattle sheds and shelters for cattle care takers (at the upper side of SWM site). This was noticed in the month of September 2013 and a meeting was arranged by resettlement specialist of DSMC immediately (on 21st September 2013) to discuss the issues with encroachers. During that meeting they had agreed to vacate the land based on the request of SIPMIU (details of the meeting was illustrated in the semiannual report prepared for the period from July to December, 2013). However this issue was remained unsettled for a long period, further district administration was informed by SIPMIU to intervene in the issue and District Collector (DC) has inspected the site in the month of June, 2014. Due to the delay in resolving the issue amicably, KMC & SIPMIU took a decision to re-demarcate the boundary excluding the encroachment portion which is not really required for any civil construction. The fencing works to protect the land from further encroachment has been done for a length of 120m out of 750m (height is 1.8m). The remaining length shall be completed at the earliest.

13. Water Supply: 17 tanks out of 18 are commissioned. The construction of the remaining 1 tank ( HQ) is now proposed under Tranche-2 as Additional Work. No IR issues are identified at these project locations during this reporting period. The construction of refurbishment of the old water treatment plant at Jotsoma including installation of two new electro chlorinators are completed in the month of November 2015. New water treatment plant has been inaugurated on 26th Nov 15. Photographs of inaugural function are attached as Appendix 1.

14. In addition to the above, SIPMIU is proposing following works at SWM site in Lerie under Tranche 1 as additional works.

 Construction of 15 retaining walls  Restoration of damaged approach road  Construction of one step drain 15. Details of the activities proposed for additional work under Tranche 1 will be provided in the next report. 4.2.2. Tranche -2 Sub Projects 16. Laying of new water supply distribution network of pipe lines of total length of 318 km in Kohima Municipal Area is the major work planned under water supply sub project of tranche-2. The civil works are proposed to be carried out within the existing RoW and road shoulders. Therefore, no land acquisition is envisaged in this sub project. Digging along the existing right-of ways (RoW) of city roads for laying of these lines will have no impacts as the proposed pipelines will be laid on the edge of the road. The maximum required trench width for laying down of different sizes of pipe lines range between 30cm to 100 cm only and can be accommodated in the road shoulders. At locations where there are permanent structures blocking the alignment of pipe lines, suitable measures to deviate these structures by using appropriate pipe bends are provided at the stage of pipe line design itself. Care is also taken to minimize adverse impacts by selection of appropriate alignment for the pipe lines. The trenching, pipe laying, jointing & pressure testing works etc., inside the city will be done in a phased manner & fast pace to minimize the period of disruption. The details of the works have been

1448 communicated to the State PWD who is maintaining the PWD& Municipal roads in Kohima.

17. Advance notices (based on the construction plan developed by the civil contractor) to the residents of the area will be given at least 7 days prior to the commencement of the civil works in the respective locality. The Community Organizers (COs) mobilized in SIPMIU under Sociologist shall undertake the activities of construction facilitation with the guidance of Community Development & Construction Facilitation expert of DSMC. The COs shall be trained periodically. Sufficient provision is also made in the contract agreement for the repair of roads, providing temporary access across the pipe line trenches (wherever necessary), repair of existing water pipe lines, cables, electric posts, dust prevention, soil erosion and all other similar menaces.

18. The joint site visits carried out by the Resettlement Specialist of DSMC along with water supply design engineers did not identify any IR impact and the presence of IPs. However, in case of any change in locations and scope of work, IR screening and RPs (if required) shall be prepared and disclosed in ADB & EA web sites.

19. Since Nagaland Government is not maintaining any land records, disputes on ROW shall be settled through discussions during the time of project implementation, the service of Community Organizers (appointed under SIPMIU for community participation) shall be utilized for these activities. Social Safeguard Expert of SIPMIU, Resettlement Specialist and Construction Facilitation and Public Awareness Experts of DSMC will play a leading role in addressing the people‟s concerns during the project implementation. The disagreement raised by the local community on the boundary of SWM (lower side) is settled through such discussions and the same community has been given the work of constructing boundary fencing to take them in confidence. 4.2.3. Status of civil construction and RP implementation 20. The Status of civil construction and RP implementation in Tranche-1&2 sub projects is abstracted in Table 3 below Table 3: Status of Civil Construction and RP Implementation Sl Subproject Activities Status of RP no sector & Implementation corresponding Tranche 1 Water Supply  Construction of 18 new RCC No IR Impact (Tranche-1) Reservoirs  Renovation of water treatment plant at Jotsoma  Supply & installation of chlorinators 2 Solid Waste  Development of a new solid No IR Impact Management waste management site with (Tranche-1) sanitary landfill, leachate treatment plant and all other essential infrastructure at Lerie 3 Water Supply  New water supply distribution No IR Impact. However (Tranche-2) pipe line network of total length corrective plan shall be 318 km in Kohima Municipal prepared if any issues are Area. identified during the project implementation

1459 4.2.4 Additional Works proposed under Tranche -2

21. Integrated SWM: Works under this subproject includes the procurement of vehicles, construction of rest rooms and construction of dry waste segregation unit. As construction of rest rooms and dry waste segregation unit is planned within the boundary of existing SWM site, no additional land is required for this sub project. 22. Construction of 5 community toilet blocks: The lands earmarked for the two locations are belonging to Kohima Municipal Council (KMC) itself. The remaining 3 belong to three private individuals. Table 4 below shows the Ownership Details of lands. All these three land owners have voluntarily surrendered the land required for the project. The base line (Involuntary Resettlement Screening) survey conducted on 12-02-2014, shows that all the lands earmarked for construction of community toilet blocks are uninhabited and barren. Based on the above assessments the subproject has been categorized as “C” for Involuntary Resettlement (IR) impact as per the ADB‟s Safeguard Policy Statement, 2009. Hence no Resettlement Plan (RP) needs to be prepared for this sub project at this stage. A SIA & IR screening report was prepared for this sub project and submitted for ADB‟s review. The report shall be further modified based on the review comments.

Table 4: Ownership Details of Lands for Community Toilets Sl Land Ownership Location No: 1 Near Government Secretariat Kohima Municipal Council 2 Near Kezekie Public Market. Kohima Municipal Council 3 Near North Police Station Mr. N. La- O Solo Near North Police Station Kohima 4 At Upper AG-1 Colony Mrs. Losa Pfozhe. & Mrs. Vizoleno Hibo Upper AG-1 Below Lerie Bank 5 At Upper AG-2 Colony Mrs. Vizokhore Upper AG-2 Kohima

23. Construction of 7 Service Reservoirs: Under this subproject,7 new service reservoirs are proposed for 9 hydraulic zones (with multiple compartments at two locations).Table 5 shows the ownership details of lands. The lands earmarked for 3 storage tanks are in possession of Government of Nagaland (2 belonging to PHED & one belonging to Land Revenue Department).Consents of these departments have been received. The other 3 lands belong to private land owners and the remaining one belongs to T-Khel (the traditional land owners). Full ownership of all these 4 lands also have been voluntarily given to KMC by these land owners. Hence, all the 7 lands are in possession of the Government.

Table 5: Ownership Details of Lands for Service Reservoirs Location of Service reservoirs Ownership 1. Common Storage Reservoir near The land belongs to T-Khel Botanical Garden. (Community) 2. Common Storage Reservoir near KMC Land Revenue department of Office. Nagaland

14610 Location of Service reservoirs Ownership 3. Storage Reservoir in PHED Compound PHED at Lower Forest Colony. 4. Storage Reservoir in PHED Compound PHED at Paramedical Colony 5. Storage Reservoir near North Police Mr. N. LA-O Solo Station. Near North Police Station North Block 6. Storage Reservoir near Government Mr. ShurhozelieLiezietsu Polytechnic. Ruliezou, Kohima Village (Ex Minister) 7. Distribution tank at Upper AG Colony Mr. Vizovor Belho, Upper AG Colony, Kohima 24. This subproject will not entail any private land acquisition and involuntary resettlement. Based on the above assessments, the subproject has been categorized as “C” for Involuntary Resettlement (IR) impact as per the ADB‟s Safeguard Policy Statement, 2009. Hence no Resettlement Plan (RP) needs to be prepared for this sub project at this stage. A SIA& IR screening report was prepared for this sub project and submitted for ADB‟s review. The report shall be further modified based on the review comments.

25. Development of a Septage Management Unit: The Plant shall be constructed in the land owned by KMC at Dzuruzou in the outskirts of the city, 3 km minimum from any habitation. KMC is having around 40 hectares of single piece land in that location and the project requires only one hectare. The approach road is already in place and under use by vehicles transporting solid waste to the dumping site. 4.3. Status of RP implementation 26. As discussed above the subprojects taken up under Tranche 1 & 2 do not impart any sort of IR and IP impacts and hence the status of RP implementation is not relevant here. However the subproject wise IR impact status has been summarized in Table 3 above. As part of sensitizing the importance and reviewing the status of safeguard compliance during the subproject implementation periodic meetings have been conducted at construction sites. Details are summarized in Table 6 below. The project managers and site engineers of civil contractors and safeguard specialists of SIPMIU and DSMC along with technical staff attended the workshops and clarified their doubts.

4.4. Activities carried out for Public Participation and GAP 27. Various activities conducted in the sector of Community Development, Public Participation and Gender Development during the period from 1st July, 2015 to 31st December, 2015 is summarized in below in Table 6. Snap shots of the activities conducted in this period is given in Appendix -2. 4.5. Status of Pilot Project on SWM 28. A pilot project (PP) on SWM was started on 1st of July 2014 for a period of six months. 2 out of 19 wards of KMC have been selected for the pilot project. A brief report on pilot project is attached as Appendix 3.

14711 Table 6: Summary of Community Development, Public Participation and Gender Sensitization programs conducted during the period of July to December, 2015 in Kohima Participation Sl.no Date Name of the Activity Venue Objective Outcome Male Female Panchayat hall 1 07/07/2015 Consultation with the colony leaders Sensitize colony leaders Got sensitized 11 03 new ministers hill 2 07/07/2015 Consultation with the colony leaders Electrical colony Sensitize colony leaders Got sensitized 07 04 Govt high school 3 08/07/2015 Clean school campaign Awareness on waste segregation Got sensitized 57 60 PWD Chandmari Awareness on waste segregation 4 10/07/2015 Clean school campaign higher secondary Got sensitized 107 154 school 5 10/07/2015 Clean school campaign Pinewood school Awareness on waste segregation Got sensitized 59 38 Panchayat hall Awareness on waste segregation 6 10/07/2015 Consultation with community Sensitized 20 21 Middle Pwd Sahitya Awareness on waste segregation sabha(lower pr 7 14/07/2015 Awareness on SWM hill,,upper pr Got Sensitized 32 19 hill,supply,lower jail & upper jail) Govt high school Awareness on waste segregation 8 16/07/2015 Clean school campaign Got sensitized 102 143 chandmari 9 20/07/2015 Clean school campaign Genesis schooll Awareness on waste segregation Got sensitized 20 11 10 24/07/2015 Clean school campaign Kros college Awareness on waste segregation Got sensitized. 21 14 St Marys Awareness on waste segregation 11 24/07/2015 Clean school campaign Got sensitized 26 32 cathedral school 12 24/07/2015 Clean school campaign Capital college Awareness on waste segregation Got sensitized 21 27 13 30/07/2015 Clean school campaign Coraggio school Awareness on waste segregation Got sensitized 37 42 Holy family Awareness on waste segregation 14 30/07/2015 Got sensitized 111 87 Clean school campaign‟ school Model higher Awareness on waste segregation 15 30/07/2015 Clean school campaign Got sensitized 195 174 secondary school Panchayat AG Awareness on waste segregation 16 07/08/2015 Consultation with community Got sensitized 17 02 Hall Gender sensitization on waste 17 19/08/2015 Gender sensitization TT revival church Got sensitized 00 27 segregation 18 15/08/2015 Consultation with local public on Sangtam bapitist Streamline the segregation of SW at Got sensitized 10 13

14812 Participation Sl.no Date Name of the Activity Venue Objective Outcome Male Female SWM church source. Consultation with local public on Chakhesang 19 16/08/2015 Awareness on waste segregation Got sensitized 08 13 SWM Baptist church Gender sensitization Gender sensitization on Waste 20 19/08/2015 AG road church Got sensitized 00 25 segregation Sensitized & community Consultation with local public on Waste segregation & Consensus on acceptance of the project 21 28/08/2015 SWM & Construction facilitation Lower pr hill 10 03 commencement of pipeline works and commencement of civil meeting works 22 28/08/2015 Consultation on swm Lower jail Awareness on waste segregation Got sensitized 08 12 Panchayat hall Awareness on waste segregation 23 03/09/2015 Public consultation on swm Sensitized. 14 05 upper jail colony Panchayat hall Awareness on waste segregation 02/09/2015 Awareness on waste segregation sensitized 133 24 forest colony Chakhesang 25 Gender sensitization on waste 09/09/2015 Gender sensitization Christian revival sensitized 00 17 segregation church 26 Sumi Baptist 14/09/2015 Consultation with church members Sensitization on waste segregation sensitized Mass service church 27 Phom Baptist Gender sensitization on waste 01/10/2015 Gender sensitization Got sensitized 00 30 church segregation

14913

29. In addition to this, SIPMIU had conducted mass awareness program in coordination with an NGO- Project 72 Hrs., which is functioning for the motto of “clean Kohima”. Awareness on waste segregation at home is spread through street play, wall paintings, announcement etc., throughout the city area. Distribution of dust bins can be done to the remaining wards in coordination with KMC soon after getting dustbins. 5 Compliance status of loan covenants 30. The compliance status with respect to loan covenants is presented in Table 7 below Table 7: Status of Loan Covenants Sl No Loan Covenant Agency Status of Compliance 1 GOI and the State will ensure Government of No private land that all land and right of way India & acquisition and required for the investment Government of resettlement issues program are made available in Nagaland are involved under timely manner. Adequate any of the compensations are provided subprojects under prior to the signing of relevant the Investment civil work contracts, and Program. Hence involuntary resettlement is RPs has not been carried out in accordance with prepared. the resettlement frame work (RF) and resettlement plans (RPs) agreed upon between the Government and ADB. An RP will be prepared for each sub project involving land acquisition and resettlement and shall be submitted to ADB for review and approval prior to award of any related civil work contract. 2 GOI and the State will ensure Government of No negative Impact that sub projects will not India & on vulnerable negatively impact on vulnerable Government of groups groups, such as indigenous Nagaland people. In the event of their involvement in any of sub projects, the GOI and the states will ensure the that the sub projects are carried out in accordance with the Indigenous People Development frameworks (IPDF) agreed up on between GOI, the States and the ADB and comply with ADBs policy on Indigenous People (1998) 3 In the event any issues related Government of Agreed. However, to indigenous people arise in India & no issues related to

15014 Sl No Loan Covenant Agency Status of Compliance course of project Government of indigenous people implementation, the borrower Nagaland are anticipated in and the state shall ensure to the course of address those issues in execution. accordance with the applicable laws and policies of the borrower, ADB‟s policy on indigenous Peoples (1998) and the Indigenous Development Framework for the facility as agreed between the Borrower, the State and ADB. In the case of any discrepancy between the Borrower‟s legislation and ADB‟s policy, ADB‟s policy shall prevail. 4 GOI and State will ensure that Government of Adequate provision all civil works contractors India & has been made in comply with all applicable Government of the contract labour laws, including those on Nagaland agreements occupational health and safety, and do not employ child labour as defined in national legislation for construction and maintenance activities. Priority work will be given to people from the area where the works are implemented and men and women will receive equal pay for work of equal value. 5 Within six months of the Government of Notification dated Effective Date, the State shall Nagaland 18th January 2013 have established a grievance reporting and redressal mechanism 6 Project Impact 31. The subprojects now being taken up in Kohima under the investment program in the sector of water supply & solid waste management as well as the efforts for the capacity building of Kohima Municipal Council will speed up the pace of the socio economic development of the City by substantially improving the urban environment and living standards of the citizens. The implementation of the subprojects will not create any major adverse impact on community. 7 Policy and Legal Framework 32. The policy framework and entitlements for all the subprojects of the investment program under tranche 1&2 are based on the National Resettlement and Rehabilitation Policy, 2007 (NRRP) and ADB‟s Safeguard Policy Statement, (SPS) 2009.

15115 8 Validation and Verifications of APs 33. Since the subprojects are falling in the „C‟ category as per ADB Policy on Involuntary Resettlement (1995) for Tranche-1 and ADB Safeguards Policy Statement (2009) for Tranche-2, no RP was prepared. 9 Public Consultations and Disclosure of RP 34. Public consultation and information dissemination are treated as a two way process through which the information is passed on to public and their feedback is sought to understand their issues. In addition to the discussion of specific issues, details about the safeguard policies and GRC of the project are broadcasting in all public meetings. The consultative process shall be continued throughout the project period. The activities conducted during the current reporting period is summarized in Table.6 10 Grievance Redressal 35. A Grievance Redressal Committee (GRC) has been constituted as per the guideline of EMP. However no complaints have been registered under GRC. 11 Monitoring and Reporting 36. As part of streamlining the collection and segregation of household waste before commissioning the SW plant at Leire, awareness on segregation of household waste at source have been done along with demonstration at each Village council in the presence of public representatives and officials from SIPMIU. This has been implemented as a pilot project in 2 out of 19 wards of KMC. All the households in the selected two wards have been issued free dust bins (1 green for wet waste and 1 blue for dry waste) followed by the awareness programs. Gender sensitization activities and plan for inclusive (gender) development shall also be discussed throughout the program. 37. After completion of pilot wards, awareness on segregation of waste has been spread over to 9 adjacent colonies of pilot wards. But dust bins have not been issued to these colonies but will be distributed soon after getting the second allotment of dustbins. 38. Further SIPMIU had focused on mass awareness program in coordination with an NGO- Project 72 Hrs. Various activities like street play, wall painting, announcement etc., have been conducted throughout the city on a regular interval to promote waste segregation at household level. It has been noted that all the said activities helped the project authority to successfully convey the message on waste segregation to the community. In addition to this, free dustbins to the remaining wards could be completed after getting the next allotment of dustbins. 12 Conclusion and Action Plan 39. The pilot project (for streamlining of source segregation, collection and transportation) is successfully implemented in two wards of KMC. Pilot project includes awareness on waste segregation at source and distribution of free dust bin to households, commercial and institutional properties in the selected two wards. In addition to this 9 adjacent colonies were selected under phase 2 of pilot project and awareness on waste segregation has been provided but due to the shortage, dust bins could not be provided. Regarding the remaining wards, mass awareness on waste segregation at source and segregated collection has been done in coordination with an NGO- Project 72 Hrs. Free dustbins will be provided soon after getting the second allotment of dustbin for the 9 colonies selected under phase 2 of pilot project and the remaining wards in KMC.

15216

Appendices

17 153 Appendix 1 Photographs of Inauguration of Water Treatment Plant

Ahola Those, Secretary, UDD Shri. SI Jamir, Hon‟ble Advisor, Urban Development

Shri. SI Jamir, Hon‟ble Advisor, Urban Audience Development

18 154 Appendix 2 Photographs of Various Activities

01/07/2015 Distribution of free dustbin

07/07/2015 Awareness program at new 07/07/2015 Awareness program at Electrical Ministers Hill Colony

08/07/2015 Awareness program at Govt high 10/07/2015 Awareness program at Chandmari School PWD Higher Secondary School

19 155

10/07/2015 Awareness program at Pinewood School

10/07/2015 Awareness program at Middle PWD Awareness program at Upper PWD

14/07/2015 Awareness program at Sahitya Sabha

20 156

16/07/2015 Awareness program at Govt High School Chandmari

20/07/2015 Awareness program at Genesis 03/09/2015 Awareness program at Upper Jail School

24/07/2015 Awareness program at Kros College

21 157

24/07/2015 Awareness program at Capital College

30/07/2015 Awareness program at Coraggio School

30/07/2015 Awareness program at Holy Family School

22 158

30/07/2015 Awareness program at Model Higher 07/08/2015 Awareness program at Panchayat Secondary School AG

15/08/2015 Awareness program at Sangtam 19/08/2015 Awareness program at AG Road Baptist Church Church

10/09/2015 Awareness program at Chakhesang Baptist Fellowship

23 159

09/09/2015 Awareness program at Chakhesang 14/09/2015 Awareness program at Sumi Baptist Revival Church Church

02/09/2015 Awareness program at Mewibogei

24 160 Appendix 3 Brief Report on Pilot Project

A pilot project (PP) on SWM was started on 1st of July 2014 for a period of six months. Three Community Organisers (CO) were selected and trained to work at community level for the pilot project. 2 wards namely Lower Chandmari (ward no 13) and Poterlane & Old Ministers Hill (ward no 14) were selected for the pilot project. During pilot project, most of the Schools, Churches, Sectors, Block were covered up in providing awareness on SWM. Public were sensitized on waste segregation, hygienic, and clean Kohima. Free dust bins for households, commercial and institutional properties to segregate waste at source itself were provided to these two wards on 8th October 2014 and 1st July 2015.

During this short period of six months different institutions were sensitized on waste segregation and various small gatherings, corner meetings, and meetings with Angawadi, door to door awareness on SWM and focus group discussion were carried out parallely. In this six months period household bins (Blue- 35 liters for dry waste and Green- 20 liters for wet waste) were provided to all the households in these two wards (total 3400 sets of free dust bins provided). The colony were provided barrels-200 liter for their waste collection vehicle for wet waste. This exercise helps the waste collection team in segregated waste collection. 4 backpack laborers were provided for the pilot project wards to ease the door to door collection and improve the quality of segregated collection. The waste collected from these three colonies (2 pilot wards) were kept differently even in the dumping site and the dry waste further segregated. As most of the households are having their own piggery/ gardening at home and all the kitchen waste (wet) will be used for this, the quantity of wet waste as compared to the dry waste is very less. The different types of dry waste segregated during the pilot project are as follows;

 metals (150 kgs)

 plastics (145 kgs)

 Pet bottles (260 kgs)

 glass bottles (200 bags)

 aluminum (30 kgs)

 carton(480 kgs)

 polythene (160 kgs).

The exact quantity of wet waste was not measured but the same will be done in future.

The 2nd Pilot phase (PP-II) was held on 23rd May 2015 at Govt Middle School Lower Chandmari. In this phase 15 colonies were selected adjacent to the two pilot wards. Following are the colonies selected for 2nd pilot phase;

1. Upper Chandmari

2. Lower PWD

25 161 3. Middle PWD

4. Upper PWD

5. New Ministers Hill

6. Leirie

7. Forest

8. Agri

9. Electrical Colony

10. Meweibogei

11. PR hill

12. Upper Jail

13. Lower Jail

14. Supply

15. Ag Colony.

Various institutions in these colonies were sensitized on waste segregation at source. List of households under the 15 colonies were collected to distribute free dust bins (blue & green) but the bins are yet to receive hence awareness on waste segregation has been provided to the selected colonies in Kohima town. For the speedy completion of awareness on waste segregation to all the households in Kohima town, it was decided to carry out the further awareness program in coordination with an NGO (Project 72 whose main moto is “clean Kohima”). With this NGO, different activities was carried out such as power point presentation in all panchayat, street art, street plays, announcing every evening regarding waste segregation in different /dialects. Intensive awareness on waste segregation and the use of two colored bins are still in progress along with the NGO.

26 162

North East Region Capital Cities Development Investment Programme (NERCCDIP)

SEMI-ANNUAL SOCIAL SAFEGUARD MONITORING REPORT

July – December, 2015

State Investment Project Management & Implementation Unit (SIPMIU) (SHILLONG)

163 ABBREVIATIONS

ADB — Asian Development Bank APs — Affected Persons CBO — Community Building Organization CLC — City Level Committees CPHEEO — Central Public Health and Environmental Engineering CTE — Consent to Establish CTO — Consent to Operate DSMC — Design Supervision Management Consultant DPs — Displaced persons EAC — Expert Appraisal Committee EIA — Environmental Impact Assessment EMP — Environmental Management Plan GSPA — Greater Shillong Planning Area GRC — Grievance Redress Committee H&S — Health and Safety IEE — Initial Environmental Examination IPCC — Investment Program Coordination Cell lpcd — liters per capita per day MFF — Multi tranche Financing Facility MOEF — Ministry of Environment and Forests MSW — Municipal Solid Waste NAAQS — National Ambient Air Quality Standards NEA — National-Level Executing Agency NER — North Eastern Region NERCCDIP — North Eastern Region Capital Cities Development Investment Program NGO — Nongovernmental Organization NSC — National Level Steering Committee O&M — Operation and Maintenance PMIU — Project Management and Implementation Unit PSP — Private Sector Participation RP — Resettlement Plan SEA — State-level Executing Agency SEIAA — State Environment Impact Assessment Authority SIPMIU — State-level Investment Program Management and Implementation Units SMB — Shillong Municipal Board SPS — Safeguard Policy Statement TOR — Terms of Reference UD&PAD — Urban Development & Poverty Alleviation Department UAD — Urban Affairs Department UDD — Urban Development Department ULB — Urban Local Body

164

CONTENT

Chapter Title Page

1. Introduction: 1 1.1 Background and Context of the Report: ______1

2. Tranche - I: 3 2.1 Status of Implementation of Sub Projects ______3 2.2 Social Safeguard Monitoring Checklist ______5 2.3 Monitoring and reporting arrangements: ______9 2.4 Social safeguard activities - Update on RP and IP plans and implementation status ______9 2.4.1 Summary of land acquisition ______9 2.4.2 Status of Affected People: Land Requirement, Compensation and Rehabilitation (systems, Plans) ______10 2.4.3 Details of affected persons, Validation and Verification of Affected persons (APs) ______10 2.4.4 Compensation decided / planned and progress on provision of compensation: ______10 2.4.5 Compliance status with respect to National and ADB policy framework: ______10 2.4.6 Contractors’ compliance to safeguard norms and monitoring: ______11 2.4.7 Gender Action Plan (Public Consultation, Implementation of GAP as per agreement with ADB): ______11 2.4.8 Distribution of Household waste Bins-Priority to female headed households ______11 2.4.9 Distribution of Household Waste Bins Management Process – Two Best Practice Case Example ______15 2.4.10 Public Consultations and Training on Income Generating Activities for Indigenous Women _ 17 2.4.11 Strategies and Approach to Create Awareness on SWM in Areas outside the SMB ______18 2.4.12 Capacity Building Programmes and Community Mobilizations ______22

3. Tranche - II: 31 3.1 Status of Implementation of sub projects______31 3.1.1 Scope of RP and IP impact ______34 3.1.2 Social Safeguard Monitoring Checklist ______36 3.2 Monitoring and Reporting Arrangements: ______41 3.3 Social Safeguard Activities - Update on RP and IP Plans and Implementation Status______41 3.3.1 Summary of Land Acquisition (Temporary / Permanent) – Details of Ownership of Land ___ 42 3.3.2 Status of Affected People: Land Requirement, Compensation and Rehabilitation (Systems, Plans) ______42 3.3.3 Details of Affected Persons/ Persons to Be Affected, Validation and Verification of Affected Persons (Aps) ______42 3.3.4 Compensation Decided / Planned and Progress On Provision of Compensation): ______42 3.3.5 Compliance status with respect to National and ADB policy frameworks: ______43 3.3.6 Contractor’s Compliance to Safeguard Norms and Monitoring: ______43 3.3.7 Grievance Redressal System and Processes and Progress: ______43

4. HH Waste Bin Distribution 43 4.1.1 Household Waste Bins Distribution in SMB Area-(as on December 2015)______43

5. Gender Action Plan 43

165 i

Annexure I: Compliance to National Laws and Policies: 44

Annexure 2: Grievance Redressal Systems and process 50

Annexure 3: Land Possession Certificate 51

Annexure 4 Translated Summary RP in Local Language 55

Annexure 5 Photographs of Different CPP Activities 59

Annexure 6: Training for Indigenous women 63

List of Table Table 1: Sub Project Components, Activity and Progress ______3 Table 2: Institutional Roles and Responsibilities______4 Table 3: Social Safeguard Monitoring Checklist ______5 Table 4: Summary of Resettlement Impacts and Socio-Economic Details______9 Table 5: Household Waste Bins Distribution in SMB Area ______11 Table 6: Capacity Building Programme under SWM______22 Table 7: Gender Action Plan – Progress Update ______26 Table 8: Status of Implementation of sub projects under TRANCHE II with regards to Social safeguards 31 Table 9: Scope of RP and IP impact under Tranche –II ______34 Table 10: Social Safeguard Monitoring Checklist ______36 Table 11: Summary of Resettlement Impacts and Socio-Economic Details under SWM sub project at Shillong______41 Table 12: Summary of Resettlement Impacts and Socio-Economic Details of SWM______42

166 ii SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

SEMI-ANNUAL SOCIAL SAFGUARD MONITORING REPORT (July to December, 2015) - SHILLONG

1. Introduction: North Eastern Region Capital Cities Development Investment Program (NERCCDIP) is being undertaken for improvement of existing infrastructure, environmental quality and access to basic urban services Shillong Planning area. The NERCCDIP’s objective is to improve the urban environment and promote reforms for sustainable, efficient, and responsive urban service delivery. The primary drivers for the initiation of NERCCDIP have been bridging the gaps in urban infrastructure provision, supplementing financial resources and technical capacity and meeting the unmet urban public health and sanitation needs. The various Program components are Water supply, Sewerage and Sanitation, Solid Waste Management infrastructure. With an overall objective of sustainable urban development, the NERCCDIP is being implemented in the five capital cities - Agartala, Aizawl, Kohima, Gangtok and Shillong. NERCCDIP implemented over a six year period beginning in 2010, and is funded by a loan via the Multi- tranche Financing Facility (MFF) of the Asian Development Bank (ADB). The expected impact of the Investment program is improved environment and well-being of urban residents in the five cities. The expected outcomes of the Investment Program will be an increased access to better urban services for the 1.5 million people expected to be living in the Investment Program cities by the 2014. To this end, the program will improve urban infrastructure and services, strengthen urban institutions for better service delivery, improve program management and implementation capacity. In Shillong, the Executing Agency (EA) for the program is the Urban Development Department (UDD) of the ; and the Implementing Agency (IA) is the State-level Investment Program Management and Implementation Unit (SIPMIU), created within the UDD, specifically for the Investment Program implementation. At central level Investment Program Coordination Cell (IPCC) is established in MOUD. IPCC is responsible for overall management of the Investment Program and is support Program Management & Monitoring Consultants (PMMC).

1.1 Background and Context of the Report: The present solid waste infrastructure and practices in Greater Shillong Planning Area (GSPA) is inadequate for the needs of the growing population. Greater Shillong Planning Area consists of Shillong Municipality, Shillong , 10 census townships and 26 rural components. There are different authorities responsible for collection and transportation of solid waste within the different units of GSPA. The final disposal however takes place in a centralized disposal site at Marten which is around 8Kms away from the city. This site has been in use since 1938 and is reaching its saturation point. On the whole the city lacks an integrated approach to solid waste management. Under tranche 1 and 2 of ADB assisted NERCCDIP, various SWM sub projects were taken up. Those sub projects under tranche 1 and 2 are: 1] Development of short term landfill site and associated works with in the area of existing land fill site of 6500 sq.mts and added area of 8500 sq.mts; 2] Construction of garage cum workshop shed and staff rest room at old landfill site at Marten, Mawiong.; 3] procurement of primary, secondary collection vehicles and workshop machineries; and 4] procurement of different types of bins and personnel protective equipment respectively.

167 1 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

This consolidated report outlines monitoring implementation of social safeguard activities between July2015 and December 2015 in accordance with the ADB Safeguard Policies. The report is divided into two parts; i,e. TRANCHE –I and TRANCHE II. In each part, the report describes: • The scope of activities and progress – An overview of project information • Implementation and institutional arrangements • Social safeguard Monitoring checklist • Monitoring and reporting arrangements for safeguards monitoring • Social safeguard activities - Update on RP and IP plans and implementation status • Summary of land acquisition (temporary / permanent) – Details of ownership of land • Status of Affected People: Land Requirement, Compensation and Rehabilitation ( systems, Plans, Details of affected persons , Validation and Verification of Affected persons (APs) , compensation decided / planned and progress on provision of compensation) • Compliance status – loan covenants, policy frameworks • Contractors compliance to safeguard norms and monitoring • Gender Action Plan (Public consultation, Implementation of GAP as per agreement with ADB) • Various information/ documentary evidences were provided in annexure.

1682

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

2. Tranche - I: 2.1 Status of Implementation of Sub Projects A. The Scope and Progress of Activities– An Overview of Project Information and Implementation Arrangements:

Under tranche I SWM project is planned for Shillong. The sub project components taken up under Tranche 1 in Shillong Municipal Board and its progress are summarized in Table 1 below. A contract variation was issued due to price escalation of certain items, changes of design and size of retaining wall. The changes of design and size of retaining wall will be done within the project site area. No land acquisition and resettlement impact has been found due to revised design and size of retaining wall. Hence, there is no change in category of resettlement impact.

Table 1: Sub Project Components, Activity and Progress Component Works Progress Scope of LA Component and Resettlement SWM Development --Masonry Retaining Category C of Development (LF&R/SWM/SHI/T1/NCB). of short term wall -Work Completed ADB (SPS), of short term Landfill Site -Approach road- work in 2009. No Landfill Site Date of Contract :- Signed and progress impact and 13th Dec.2011 Associated -Sanitary Landfill - work Associated Works at started-in Works at Signed to proceed :- Shillong, progress(50.43 percent Shillong, 2nd March.2012 Meghalaya completed) Meghalaya. -Supply of Bulldozer- Supplementary Agreement Supplied- Signed : 6th February 2014 Construction of tube well-- —works Original contract value: Completed. 2,82,33,305.00 -Construction of Leachate holding tank— Revised Contract Value : work to be started 5,99,59,224.00 -Supply of fire fighting equipments -- tendered -Construction of ground level water reservoir- work started-- work Completed. -Construction of Drain near landfill site- work will be started on near completion of the sanitary landfill (50.43 Percent Completed) Contract terminated on 4th December 2015 and Site was taken over from contractor on 16th December 2015. The bid documents approved and Bids are being invited from 10th December 2015 and deadline for bid submission is 18th January 2016.

1693

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

B. Implementation and Institutional Arrangements:

The Ministry of Urban Development (MoUD) is the national-level executing agency (EA) of the Program. An IPCC has been established in MoUD and that include a social officer. A National Steering Committee (NSC) is responsible in monitoring the fund use and overall implementation performance of the Investment Program. A State-level Executing Agency (SEA) is executing the part of the loan falling under respective State Governments. In each State a State Steering Committee (SSC) has been formed and an Investment Program Empowered Committee (IPEC) is also operational. SIPMIU is responsible for overall program implementation, monitoring, and supervision. A Resettlement Officer (RO) is part of the Unit. ROs and implementing NGOs will be responsible for RP implementation. Roles and responsibilities are identified in Table 2. For taking up implementation of RP, institutional arrangements including strengthening of existing institutional systems are required. Towards this, it is proposed that the SIPMIU’s Social and Resettlement Unit will take care of redressing grievances and mitigating negative social impacts caused due to the project especially on Affected people (APs).

Table 2: Institutional Roles and Responsibilities

Activities Responsible Agency Sub-project Initiation Stage Finalization of sites/alignments for sub project SIPMIU/DSMC Disclosure of proposed land acquisition and sub-project details by issuing SIPMIU Public Notice Meetings at community/ household level with APs of NGO land/property Formation of Valuation Committees SIPMIU RP Preparation Stage Conducting Census of all APs SIPMIU/NGO Conducting FGDs/ meetings / workshops during SIA surveys SIPMIU/NGO Computation of Replacement Values of land/properties proposed for VC/SIPMIU acquisition and for associated assets Categorization of APs for finalizing entitlements SIPMIU Formulating compensation and rehabilitation measures Conducting SIPMIU/ NGO discussions/ meetings/ workshops with all APs and other stakeholders. Fixing compensation for land/property with titleholders VC/SIPMIU Finalizing entitlements and rehabilitation packages SIPMIU Disclosure of final entitlements and rehabilitation packages SIPMIU/NGO Approval of RP IPCC/ADB Sale Deed Execution and Payment Taking possession of land SIPMIU RP Implementation Stage Implementation of proposed rehabilitation measures NGO/RO Consultations with APs during rehabilitation activities NGO/RO Grievance Redressal Committee (Both at State level and City level) NGO/RO/GRC Internal Monitoring SIPMIU External Monitoring External AP=affected person, VC=Valuation Committee, FGD=focus group discussions, GRC = Grievance Redressal Committee, NGO = Non Government Organization, SIPMIU = state-level investment program management and implementation unit, IPCC = investment program coordination cell, RO = resettlement officer, RP=resettlement plan, SIA=social impact assessment

1704

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

2.2 Social Safeguard Monitoring Checklist Table 3: Social Safeguard Monitoring Checklist Project Data Name of Project & Subproject Loan No-2528-IND: Development of Short term landfill Site and Associated works at Shillong, Meghalaya Project Disbursement Status in INR 12.03 Million Type of contract Regular § Design-Build § Combined Safeguards Categorization A B C IR C IP C

A. Design and Engineering Status Item Status Follow up Type of Required Action (Please (Y/N) required tick appropriate box) (Y/N) Final detailed engineering design of Y N § Updated draft IR/IP the sub project completed § New RP/IPP preparation No action Changes in project design/ scope N N § Project re-categorization (IR/IP) (occurred or envisaged) § IR/IP Impact assessment § New RP/IPP preparation No action B. Institutional Status Readiness No Item Status Follow up required Completion (Ready/Not (Y/N) Deadline ready/NA) 1 Mobilization of civil works contractor Ready N 2 Mobilization of Project Supervision Ready N 3 Consultant EA’s Safeguards Unit with designated Ready N 4 staff Recruitment of External Monitoring NA N Agency C. Safeguards Requirements No Item Status Follow up required Completion (Ready/Not (Y/N) Deadline ready/NA) 1 Safeguards monitoring included in the NA project progress report 2 Final/ updated RP/IPP1 prepared and NA submitted 3 Project’s Grievance Redress Ready Mechanism established 4 Recruitment of third independent party NA for negotiated land acquisition 5 Project’s ESMS (for FI) established NA

______

1 Detail checklist for RP/IPP supervision provided in section D.

1715

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

D. RP/ IPP Monitoring Checklist Item Safeguards Related Requirements Status Completion Progress to No. (Ready/Not Deadline Date/ ready/ NA) Remarks 1.0 Management Institutional and Financing Arrangements Financing and budget : (i) safeguard office and staff; 1.1 Ready (ii) RP/IPP cost Establish Safeguard Unit: (i) resettlement offices (ii) 1.2 resettlement staff as in RP (iii) safeguards’ database Ready (iv) facilities (v) safeguards training Updating of DD/RP/IPP based on Detailed Design NA Category C Update DD/RP/IPP: (i) revise based on DMS (ii) 1.3 NA for IR and revise implementation schedule (iii) revise budget IPP Category C Compensation rates: (i) approved by Government; 1.4 NA for IR and (ii) Adequate as per RP/RF; (iii) APs informed. IPP Disclosure and Grievance Redress Arrangements

Disclose final/updated RP/IPP: (i) to the APs in local Category C 1.5 NA language; (ii) in ADB website; (iii) in EA’s website for IR and IPP Disclose project activities to affected communities: 1.6 (i) put up a project sign boards; (ii) distribution of Ready project leaflets and GRM to affected communities Grievance redress committees: (i) clear terms of 1.7 reference; (ii) appointment decree; (iii) publicly Ready disclosed among APs. Grievance redress records: (i) list and numbers of Category C grievances received; (ii) numbers of resolved issues; 1.8 NA for IR and (iii) numbers of cases under GRC review; (iv) IPP outstanding cases (filed to court) Monitoring and Reporting Arrangements

Set up internal monitoring system : (i) assessment 1.9 on capacity and staff requirements; (ii) criteria of Ready safeguards assessment ; (iii) reporting mechanism Appoint external monitoring agency (as relevant): (i) Category C recruitment schedule; (ii) TOR; (iv) baseline survey 1.10 NA for IR and (v) reporting mechanism (vi) action taken by IPP management on reports. Category C Reporting: (i) frequency; (ii) timeliness; (iii) identified 1.11 NA for IR and issues; (iv) action taken and/recommendation. IPP 2.0 PR/IPP IMPLEMENTATION Consultation Consultation: (i) responsibility; (ii)stakeholders Category C 2.1 Identified; (iii) consultation and process; (iv) NA for IR and documentation IPP Mapping and Assets Inventory AP Identity cards & affected assets records: (i) Category C issuance and distribution of AP ID cards, (ii) detail 2.2 NA for IR and measurements survey of affected assets and IPP documentation

1726

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Item Safeguards Related Requirements Status Completion Progress to No. (Ready/Not Deadline Date/ ready/ NA) Remarks Land acquisition activities: (i) maps of affected and Category C relocation sites; (ii) acquisition & relocation 2.3 NA for IR and schedule; (iii) coordination with the asset’s acquiring, IPP transfer and registration bodies Common property/ public assets: (i) final inventory; Category C 2.4 (ii) restoration plan and schedule; (iii) funding NA for IR and sources IPP Compensation, Relocation and Rehabilitation NA Payment of compensation and entitlements (as Category C 2.5 stated in the RP): (i) schedule of payment; (ii) NA for IR and records/ receipts of payment IPP Relocation of process ( relocation site readiness): (i) Category C housing & associated facilities established; (ii) 2.6 NA for IR and transfer of new land/plot/ house ownerships IPP completed Provision of (a) income restoration, (b) additional Category C assistance for vulnerable APs, (c) training, etc. (as 2.7 NA for IR and stated in the RP): (i) per type of activities; (ii) IPP schedule of implementation Monitoring and Reporting Submission of the reports: (i) semi-annual Category C monitoring reports; (ii) external monitoring and 2.8 NA for IR and evaluation reports (as required); (iii) completion IPP report 2.9 Transfer of acquired assets to the acquiring agency NA

E. Safeguards Loan Covenants Item No. Covenant Agency Status of Compliance Sl. No. Loan Covenant Vi (16) GOI and the States will ensure that all land and right-of- GOI, The sub project work way required for the Investment Program are made GoMe, will be carried out in available in a timely manner, adequate compensations GoMi, government land. are provided prior to the signing of relevant civil works GoNa, There are No contracts, and involuntary resettlement is carried out in GoSi & Resettlement or accordance with the Resettlement Framework (RF) and GoTrt Rehabilitation Resettlement Plans (RPs) agreed upon between the issues. Government and ADB, the Government’s National Policy on Resettlement and Rehabilitation, and ADB’s Policy on Involuntary Resettlement (1995). An RP will be prepared for each sub-project involving land acquisition or resettlement and shall be submitted to ADB for review and approval prior to award of any related civil works contracts. For sample sub-projects, updated RPs will be provided to ADB for review and approval following detailed design and prior to award of civil contracts.

1737

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Item No. Covenant Agency Status of Compliance Viii(16) GoI and the States will ensure that sub-projects will not GOI, No negative impact negatively impact vulnerable groups, such as indigenous GoMe, on Vulnerable peoples. In the event of their involvement in any of the GoMi, groups. sub-projects, the GoI and the States will ensure that the GoNa, sub-projects are carried out in accordance with the GoSi & Indigenous Peoples Development Framework (IPDF) GoTr agreed upon between GoI and the States and ADB and comply with ADB’s Policy on Indigenous Peoples (1998). 17 In the event any issues related to indigenous people GOI, No issue related to arise in the course of Project implementation, the GoMe, indigenous people Borrower and the States shall ensure to address those GoMi, is anticipated in issues in accordance with the applicable laws and GoNa, course of policies of the Borrower, ADB's Policy on Indigenous GoSi & execution. Peoples (1998) and the Indigenous Peoples GoTr Development Framework for the Facility as agreed between the Borrower, the States and ADB and incorporated by reference into Schedule 5 to the FFA. In the case of any discrepancy between the Borrower's legislation and ADB's policy, ADB's policy shall prevail. (para. 17) ix. 20 GOI and the States will ensure that all civil works GOI, Adequate provision 21 contractors comply with all applicable labor laws, GoMe, has been made in including those on occupational health and safety, and GoMi, the Bid documents. do not employ child labor as defined in national GoNa, legislation for construction and maintenance activities. GoSi & Priority for work will be given to people from the area GoTr where the works are implemented and men and women will receive equal pay for work of equal value. 23 Within six (6) months of the Effective Date, each State GoMe, Established. shall have established a grievance reporting and GoMi, redressal mechanism.(para. 23) GoNa, GoSi & GoTr

Overall Status of Compliance

§Not complied – §Complied with further monitoring §Fully Redressed action & complied monitoring required – no further action

1748

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

2.3 Monitoring and reporting arrangements:

The sub project has been categorised as “Category C for IR and IPP” as per SPS 2009 of ADB. The safeguard implementation related activities are being closely monitored to provide the SIPMIU with an effective basis for assessing safeguard progress and identifying potential difficulties and problems. Monitoring is currently being undertaken by the SIPMIU .The extent of monitoring activities, including their scope and periodicity, is commensurate with the project’s risks and impacts. Monitoring involves: (i) administrative monitoring to ensure that implementation is on schedule and problems are dealt with on a timely basis; SIPMIU monitoring also includes daily planning, implementation, feedback and trouble shooting. A contract variation was issued in February 2014 due to price escalation of certain items, changes of design and size of retaining wall. The changes of design and size of retaining wall is being done within the project site area. No land acquisition and resettlement impact has been found due to revised design and size of retaining wall. Hence, there is no change in category of resettlement impact.

2.4 Social safeguard activities - Update on RP and IP plans and implementation status The Investment Program is intended to optimize the socio economic development in Shillong Municipality area with an objective to improve the urban environment cum living conditions of citizens. The SWM sub project in Shillong will not create any major negative impact on community. Summary of land acquisition and resettlement impacts in tranche -1 sub projects is summarized in the table below:

Table 4: Summary of Resettlement Impacts and Socio-Economic Details Development of short term Landfill Site and Associated Works at Shillong, Meghalaya Type of Impact Number of APs 1.Permanent Loss Title Holder/Land Owner NIL Total Loss of land(sq.mts) NIL Loss of trees NIL Total land Holding in that Particular Plot (sq.mts) NIL Occupation NA Vulnerability NA Annual Income (INR) NA 2.Temporary Loss A)Temporary Loss/ Disruption of Business(Nos) Nil B)Temporary Loss/ Disruption of Business Employees of the business Nil enterprises(Nos) 3. Encroacher in ROW A) Encroacher in ROW(Nos) Nil Affected CPRs NIL

Source: census and Socio-Economic Survey, December 2010 and site verification carried out by Resettlement Specialist on 18-06-2015

2.4.1 Summary of land acquisition The Development of short term Landfill Site and Associated Works at Shillong, Meghalaya is carried out on existing land fill site. The land is already is in possession of SMB. There is no land acquisition from private parties. A contract variation was issued in February 2014 due to price escalation of certain items, changes of design and size of retaining wall. The changes of design and size of retaining wall will be

1759

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

done within the project site area. No land acquisition and resettlement impact has been found due to revised design and size of retaining wall. Hence, there is no change in category of resettlement impact.

2.4.2 Status of Affected People: Land Requirement, Compensation and Rehabilitation (systems, Plans) Since the land is in the possession of SMB and the project has been categorised as Category C as per SPS 2009, there is no resettlement impact either direct or indirect in nature.

2.4.3 Details of affected persons, Validation and Verification of Affected persons (APs) The project has been categorised as Category C as per SPS 2009. There is no impact, hence validation and verification of APs is not required. A contract variation was issued in February 2014 due to price escalation of certain items, changes of design and size of retaining wall. The changes of design and size of retaining wall will be done within the project site area. No land acquisition and resettlement impact has been found due to revised design and size of retaining wall. Hence, there is no change in category of resettlement impact.

2.4.4 Compensation decided / planned and progress on provision of compensation: The project has been categorised as Category C as per SPS 2009. There is no impact, hence there is no compensation payment is associated with this sub project.

2.4.5 Compliance status with respect to National and ADB policy framework: The policy framework and entitlements for the program as well as for this subproject are now to be based on national laws: The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act 2013 2, state laws and regulations: ADB’s Safeguard Policy Statement, 2009 (SPS); and the agreed Resettlement Framework (RF). Based on these, the core involuntary resettlement principles applicable are: (i) land acquisition, and other involuntary resettlement impacts will be avoided or minimized exploring all viable alternative subproject designs; (ii) where unavoidable, time-bound Resettlement Plans will be prepared and APs will be assisted in improving or at least regaining their pre- program standard of living; (iii) consultation with APs on compensation, disclosure of resettlement information to APs, and participation of affected persons in planning and implementing subprojects will be ensured; (iv) vulnerable groups will be provided special assistance; (v) payment of compensation to APs including non-titled persons (e.g., informal dwellers/squatters, and encroachers) for acquired assets at replacement rates; (vi) payment of compensation and resettlement assistance prior to the contractor taking physical acquisition of the land and prior to the commencement of any construction activities; (vii) provision of income restoration and rehabilitation; and (viii) establishment of appropriate grievance redress mechanisms. A detailed policy framework including the comparison of new national law and policies with ADB’ SPS is given in Annexure 1.

______

2 The policy framework and entitlements for the program as well as for this subproject will now based on new national law(applicability is from January 2014) namely; The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act 2013 and state laws and regulations. The Autonomous Districts,(Allotment,Occupation or use or setting apart of land) Regulation Bill 2005; ADB’s Safeguard Policy Statement, 2009 (SPS); and the agreed Resettlement Framework (RF) of NERCCDIP.

17610

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

2.4.6 Contractors’ compliance to safeguard norms and monitoring: The contractor is following the local labour law of Government of Meghalaya including providing equal wage to male and female labour as required under the contract.

2.4.7 Gender Action Plan (Public Consultation, Implementation of GAP as per agreement with ADB): The activities undertaken during the reporting period has been presented in table 7.

2.4.8 Distribution of Household waste Bins-Priority to female headed households Asian Development Bank (ADB) strongly emphasises on bridging the gender gap. In its policy framework, it highlights that women are given priority and are treated as equal. Therefore, under the NERCCDIP programme, and following the mandate of ADB’S policy framework, the CPPA-DSMC team focuses on giving priority to female headed households.

Before the distribution of bins in each locality, awareness-training programme is given to all residents. It is expected that one member from each family attends the awareness training programme and that the learning’s are shared with other members of their respective families. Once the distribution day is announced to the residents of the locality, it is made certain that elderly women and female-headed household should be the first to receive the bins. As many as ten women are selected from the locality by the executive committee members to be the first recipients to receive the one time grant bins. Each household receives one slip, which permits them to collect the bins. These slips are verified by the Dorbar Shnong and then entered by the Govt. officials for record keeping. Serial numbers are allocated to each slip. The distribution of bins is held at an open space and is usually inaugurated by the local MLA. The MLA hands over the bins to the women.

Similarly, a number is entered at the back of each slip and a signature is obtained in the registration sheet. This is to confirm that the bins have been taken by a particular household. After a formal inauguration of the event, the FHH and elderly women are given priority to be the first recipients of the household waste bins.

The NERCCDIP programme stresses majorly on the participation of women. Wherever there are local Dorbar meetings, it ascertains that women representatives participate. It is believed that women are the right people to enforce rules and regulations. They are the ones to make a system fall in place. Their participation and inclusion builds the progress faster with positive results.

Distributions of the household bins were started on 11th October 2014.Till December 31 2015, 60284 bins have been distributed to 30142 households. The colony wise distribution is presented in following table 5. Table 5: Household Waste Bins Distribution in SMB Area (As on 31st December 2015)

Sl. Name of the Dorbar Shnong Date of No. of Households No Distribution Received Bins 1 Cleve Colony 15th July 2014 246 Second Distribution, Cleve Colony 28th Jan 2015 20 2 Lumlyer, Lower Mawprem 11th Oct 2014 98

17711

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Sl. Name of the Dorbar Shnong Date of No. of Households No Distribution Received Bins Lumsohphoh, Lower Mawprem 17th Oct 2014 107 Sngithiang, Lower Mawprem 18th Oct 2014 232 Pdeng Shnong, Lower Mawprem 18th Oct 2014 790 , Lower Mawprem 7th Nov 2014 601 Central, Lower Mawprem (Remaining HH 2nd Dec 2014 91 from all 5 Dongs) 3 Lumdiengjri 1st Nov 2014 377 Second Distribution, Lumdiengjri 27th Jan 2015 10 4 Keating Road 8th Nov 2014 488 Second Distribution, Keating Road 5th May 2015 28 Third Distribution, Keating Road 6th May 2015 8 5 Lama Villa 15th Nov 2014 428 6 Laban (4 Dongs) 22nd Nov 2014 268 Sports Ground, Laban (3 Dongs) 29th Nov 2014 148 Assam Club, Laban 12th Dec 2014 838 Laban 6th March 2014 476 Laban 7th Dec 2015 116 7 Bishnupur 6th Dec 2014 1326 Second Distribution, Bishnupur 28th August 2015 123 Third Distribution, Bishnupur 4th Dec 2015 35 8 Kench’s Trace, Oxford Hill, Rilbong (KOR) 6th Dec 2014 638 Second Distribution, KOR 20th Dec 2014 503 Third Distribution, KOR 3rd July 2015 34 9 Dymmiew 12th Dec 2014 169 10 Sunny Hill 12th Dec 2014 363 Second Distribution, Sunny Hill 10th Jan 2015 18 11 Mawbah 19th Dec 2014 1636 Second Distribution, Mawbah 12th Jan 2015 154 Third Distribution, Mawbah 17th Jan 2015 136 12 Jaiaw Laitdom 16th Jan 2015 980 Second Distribution, Jaiaw Laitdom 29th Jan 2015 225 Third Distribution, Jaiaw Laitdom 12th Dec 2015 70 13 Jaiaw Pdeng 28th March 2015 132 Second Distribution, Jaiaw Pdeng 21st April 2015 93 14 Jaiaw Lansonalane 1st June 2015 154 15 Jaiaw Shyiap and Lumpyllon 2nd June 2015 364 16 Jaiaw Langsning 20th June 2015 565 Second Distribution, Jaiaw Langsning 27th June 2015 119

17812

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Sl. Name of the Dorbar Shnong Date of No. of Households No Distribution Received Bins Third Distribution, Jaiaw Langsning 9th Dec 2015 23 17 Dong Mynsain, Upper Lumparing 17th Jan 2015 196 Second distribution, Dong Mynsain, Upper 16th Feb 2015 51 Lumparing Upper Lumparing 22nd Jan 2015 590 Second distribution, Upper Lumparing 13th Feb 2015 109 18 Mission Compound 24th Jan 2015 343 Second Distribution, Mission Compound 27th Jan 2015 17 19 Madan Laban 31st Jan 2015 855 Second Distribution, Madan Laban 15th Dec 2015 40 20 Police Reserve, Jail Road 6th Nov 2014 194 Jail Road 1st Feb 2015 736 Second Distribution, Jail Road 27th Feb 2014 106 Jail Premises 5th March 2015 52 21 Kynjat Phutbol 7th Feb 2015 502 22 Police Bazaar 8th Feb 2015 150 Second Distribution, PB 22nd Feb 2015 77 23 Nongrimmaw, I 11th Feb 2015 431 Second Distribution, Nongrimmaw 20th Feb 2015 164 Lower New Colony, Laitumkhrah I 2nd May 2015 303 24 Nongrimbah, Laitumkhrah II 21st Feb 2015 609 Second Distribution, Nongrimbah 6th March 2015 146 Lumsohra, Laitumkhrah II 14th March 2015 253 Main Road, Laitumkhrah III 9th May 2015 140 Boyce Road, Laitumkhrah 20th June 2015 224 Bhagyakul, Laitumkhrah 4th July 2015 256 Nongkynrih, Laitumkhrah 17th July 2015 294 Upper New Colony, Laitumkhrah 21st July 2015 338 25 Lawmali 14th Feb 2015 672 Second distribution, Lawmali 11th March 2015 69 26 Upper Mawprem 23rd Feb 2015 1159 Second Distribution, Upper Mawprem 26th Feb 2015 29 Third Distribution, Upper Mawprem 10th Dec 2015 138 27 Lower Lumparing 24th Feb 2015 702 Second Distribution, Lower Lumparing 10th March 2015 343 28 Lachaumiere 28th Feb 2015 386 Second Distribution, Lachaumiere 21st March 2015 53 Third Distribution, Lachaumiere 26th March 2015 03

17913

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Sl. Name of the Dorbar Shnong Date of No. of Households No Distribution Received Bins 29 Umsohsun 7th March 2015 201 Second Distribution, Umsohsun 8th April 2015 22 Third Distribution, Umsohsun 10th April 2015 23 30 Riatsamthiah 21st March 2015 622 31 Wahthapbru 28th March 2015 162 32 Mawkhar 4th April 2015 340 33 Qualapatty 11thApril 2015 298 Second Distribution, Qualapatty 29th April 2015 22 34 Nongmali III 25th April 2015 305 Second Distribution, Nongmali III 7th May 2015 7 Third Distribution, Nongmali III 2nd Dec 2015 26 35 Oakland 24th May 2015 402 Second Distribution, Oakland 30th May 2015 51 Third Distribution, Oakland 27th June 2015 52 36 Lumbalang, Malki 23rd May 2015 159 Second Distribution, Lumbalang 25th July 2015 16 Chinapatty, Malki 25th May 2015 161 Second Distribution, Chinapatty, Malki 29th May 2015 23 Nongpyngrope, Malki 30th May 2015 110 Dhankheti, Malki 18th July 2015 257 Second Distribution, Dhankheti 8th Dec 2015 36 Nongshilliang, Malki 18th July 2015 318 Seven Set, Nongshilliang 27th July 2015 28 Pdeng Shnong, Malki 25th July 2015 237 Kharmalki, Malki 12th August 2015 601 Second Distribution, Kharmalki, Malki 11th Dec 2015 24 37 Wahingdoh 13th June 2015 695 Second Distribution, Wahingdoh 26th June 2015 59 38 Lumkshaid 27th June 2015 516 Second Distribution, Lumkshaid 1st July 2015 43 Distribution in DSMC June-August 2015 366 Total Households received the Bins 30,142 Total HH Waste Bins Distributed 60,284

18014

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

2.4.9 Distribution of Household Waste Bins Management Process – Two Best Practice Case Example Public Distribution of Household Waste Bins at Malki (Kharmalki) Held on 12th August 2015

The Public distribution of household waste bins was organised after a few consultative meetings between the Rangbah Dong, Executive Committee and the CPPA-DSMC team. After much explaining on the new system of waste management, the EC was convinced and was ready to distribute the bins to each households in the locality. After the consent of the EC, locality level awareness training was conducted for the residents of the locality. All queries Household waste bin distribution in Kharmalki and doubts were clarified and the new system of waste management was explained in detail to the public. The 12th August 2015 was reserved for Kharmalki for public distribution of household waste bins. A day before the distribution the CPPA team made available to the Rangbah Dong Householder verification slips to be handed over to all the residents of Kharmalki of which only a seal was to be stamped on each slip. Prior to issuing the verification slips, an approx number of households were determined by the CPPA Team from the Rangbah Dong. According to the figures given by the Rangbah Dong, the exact numbers of slips were issued.

On the 12th August 2015, The CPPA-DSMC team arrived at the venue at 7:30am sharp. People started to gather and were awaiting the Rangbah Shnong to officially open the distribution process. Ms Palvy Dora Kharkongor did a short training on segregation of waste. Once this was done, the distribution took place at a basket ball court at 8:00am. The slips that were distributed the previous day had to be revealed by the residents to the CPPA-DSMC staff. Once this was found to be authentic Household waste bin distribution in Kharmalki with the name and the signature of the Rangbah Dong or member of the EC, the residents were allowed to sign in the registration sheet of the Govt and were issued the bins. The residents had to give the verification slips back to the CPPA-DSMC staff. Altogether 601 residents received the household waste bins in a span of 90 minutes.

18115

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

The executive committee members and staff from the SMB assisted the CCPA-DSMC team with the distribution process. By 10:00am the distribution process was completed.

Public Distribution of Household Waste Bins at Bishnupur Held on 28th August 2015

The Local MLA, Bah Shanbor Shullai expressed the need to conduct a second public distribution of household waste bins at the locality. Since, there was more than a handful of residents who had not received the bins during the first distribution at Bishnupur, the request to distribute for the second time were accepted by the CPPA-DSMC team. The verification slips were not handed over a day before but were given to the EC the same day as the distribution was going on. Household waste bin distribution in Bishnupur The EC members and volunteers had to sign and seal on the slips and hand these over to the residents for registration with the Govt. The number of households to receive the bins was communicated to the Team and accordingly the verification slips were printed and handed over to the EC members and volunteers.

Although the turn out was a mad rush and took the team as long as five hours to complete the distribution, the total number of households to receive the bins was only 123 residents.

Four to five volunteers from the EC assisted with verifying the members of the households. A list of names of those who had received during the first distribution was also shared by the CPPA-DSMC team with the Volunteers to avoid any duplication and giving out extra bins to households.

The Local MLA helped streamline the mad rush to ease out the distribution process. Bah Valentino from SMB assisted with the distribution of bins. The distribution came to an end at about 1:30pm. All those households that had not received during the second distribution were asked to visit the local MLA and to collect the bins with authentic documents from the CPPA-DSMC Office. Residents had to bring along with them ID cards.

On 5th June 2015 another milestone was achieved in the Shillong Municipal Board Area, where the Collection of Segregated Waste was commenced in 31 Localities. The preparation for the start of the process was announced through circular letters from the CEO to the headmen of the different Dorbars, as well as announced the information through Public Notices in the News papers and also announced in the Radio and TV channels. Consequently in most of the localities Compliance of the segregation rules was about 60% which is a big achievement. This could be the first in the country where massive mobilization of the people with training etc. to prepare for the launch of the collection of Segregated waste.

18216

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

2.4.10 Public Consultations and Training on Income Generating Activities for Indigenous Women a. A Public Consultation cum Capacity Building for indigenous women at Madanryting Dorbar Pyllun was organised on 17th October 2015 at 10:00am at the community hall. Altogether 54 women participated in the workshop including the executive members and the Seng Kynthei of Madanryting, five MSW interns from MLCU and five DSMC staff. The workshop started with a welcome speech from the secretary of the Seng Kynthei highlighting the benefit of the workshop for the indigenous women. Ms Georgina, DSMC highlighted briefly on the NERCCDIP programmes and communicated the programme schedule for the Workshop. The facilitators organised a participatory group activity in which the participants were divided into 3 groups and asked to do a free listing of issues and problems faced by women at the social level, problems faced by women and youth. The outcome details are presented below:

• The participants come from weaker backgrounds and expressed that livelihood enhancement will help them better their lives and living standards. A few of the women seemed learned but because of poverty, were compelled to drop out from school at an early age and take to menial jobs to sustain their lives. Even their current jobs cannot sustain them and are finding difficulty in making ends meet. They all expressed that trainings on skill development will help them take to better sustainable activities for which they will be able to support their families. • The resource person, Mr Ricky, Bethany Society, made a presentation with live demonstration on various composting technologies. He explained the dangers of felling of trees, dangers when animals are hunted down and when streams, lakes, rivers are contaminated and air polluted. Discussing about waste he opined that often people put the blame on another’s for dumping garbage indiscriminately onto the roads and streams.

• Mr Ricky displayed products such as earrings, plastic baskets and napkin holders made from plastic bottles and bags. He demonstrated on how to compost biodegradable waste using G2G granules, how to make a trench for depositing the waste after 30 days and how to use the compost once it is ready. The compost once ready can either be used in its original form or sieved and packaged for selling.

• The women group can form into a Self Help Group and start with composting of waste. Once the group has hands-on experience, the compost can be marketed to line Government Departments.

b. On 28th Sept 2015, a workshop was organised for the Commerce students of Shillong College who wanted to explore business opportunities through waste recycling and waste re-use. A total of 35 participants attended the presentation and discussions. Shillong College is deciding to integrate a syllabus of waste management into their curriculum for which two teachers have kept in touch with DSMC.

c. A workshop was co-organised with the Deputy Commissioner, East Khasi Hills District and his office on Promoting Best Practices of Solid Waste and Plastic Waste Management. The

18317

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

programme was held at the Urban Complex on the 1st October 2015. Altogether 27 participants attended the programme.

d. A Public Consultation cum training was organised for the Teachers of the North Eastern Hill University in the NEHU conference Hall on 7th October 2015. DSMC staff were the resource persons to share information on the waste management scenario and the ways of best practices like segregation and recycling that leads to Zero Waste. Altogether 63 Professors, Lecturers and administrative staff of the University attended the programme.

e. On 16th October 2015, A planning meeting was held in coordination with the Deputy Commissioner, on how best waste management and clean city can be shown during the International Terra Madre Festival could be managed. Since about 60 country representatives are visiting the city, it was important to give a face lift and the consultation was on how to go about. DSMC presented a brief on the Zero Littering Campaign and what school and college children can do to make the city cleaner. A few schools and colleges offered to organise cleaning drives in their surroundings. Altogether 60 participants attended the consultative meeting.

f. On 31st October 2015, About 360 students from various schools participated in a painting competition on the theme “The City I want to live in” and the paintings depicted an ideal Shillong city that is Clean Orderly and peaceful by the young artists. This competition was organised as part of the Swachh Bharat Mission that was entrusted to the NERCCDIP staff to give a lead.

g. A review and Input session was organised fro the Supervisors and Inspectors of the Shillong Municipal Board on the 30th November 2015. The SIPMIU Director gave a lead and shared a perspective and well as the attitude required to implement the NERCCDIP properly in the city. A total of 21 second layer functionaries of SMB attended the session.

2.4.11 Strategies and Approach to Create Awareness on SWM in Areas outside the SMB There are 62 (Sixty Two) Dorbar Shnongs (Localities) in the areas outside the Shillong Municipal Board (SMB). Out of the 62 Localities, 8 Localities (4 from Laitkor Dorbar Pyllun and 4 from Mawdiangdiang) have written to the Government of Meghalaya that they would not want the SWM programme under the NERCCDIP to cover their localities. Incidentally these 8 villages are quite remote from the city and also they have their own traditional practices of waste management like composting of Bio-degradable waste and deep burial or burning of the Non biodegradable waste, which is well-practiced by residents of 4 Dorbar Shnongs in Laitkor area. This approach to create awareness and to solicit participation is for the people of the 54 localities outside the SMB.

The new system to be introduced in waste management for Shillong requires adequate information reaching to all residents of the city. To ensure that the communities developed a sense of ownership of the new and rehabilitated infrastructure and services the NERCCDIP has to include a major focus on

18418

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

community awareness and participation component. Given the complex power structures in the city of Shillong, where each Headman exercises absolute control of the people, he has to be taken into confidence to solicit his co-operation and acceptance for the implementation of the project in the locality. To do this the CPPA team’s pro-active role to develop rapport and advocate participation of the Headmen and together with him the communities, will be important for successful implementation and sustainability of the project.

Under the ADB assisted NERCCDIP project, the Govt. of Meghalaya has earmarked some vehicles for the Dorbar Shnongs in the GSPA. The same project will distribute also the one time grant of two different coloured household waste bins to all households. Some Personal Protective Equipments (PPE), Wheel Barrows and litter bins for installation at few important public places are also earmarked. These assets can be availed by SWM units of the Dorbar Shnong/Pyllun/NGO.

The government requires an ULB/NGO/SWM unit of Dorbar Shnong to enter into an MOU, so as to avail the assets under the NERCCDIP project. The vehicles, PPE, and wheel Barrows will be made available with signing of an MOU with the Govt. There are few options for SWM for the localities falling in areas outside the Municipality:

1. Each Dorbar Shnong deciding to operate SWM on their own will enter into an MOU with the Urban Affairs Department, Govt of Meghalaya as per the format circulated already.

2. Any Dorbar Shnong may decide to outsource SWM service agencies. In this case the Dorbar Shnong may authorise the agency to enter in to MOU with the government to avail of the assets from the project.

3. Different Dorbar Pyllun may start a united initiative to manage the SWM in the Pyllun. In such cases the body set up by the Pyllun will sign the MOU with the Government of Meghalaya and avail the equipments and operate the SWM in the localities of the Pyllun. The advantage of working through an agency facilitated by the Pyllun is that the waste management can be enforced uniformly in a larger area, as well as launch a business model to give employment to a sizable number of men and women. Such institution can be a better option as it gives sustainability, as well as better manage the waste and be accountable.

Salient features of the new system:

• Segregation of waste at Source i.e. at the household levels.

• Dedicated collection of the segregated waste to ensure that only segregated waste would be collected.

• Dedicated transport of the segregated waste by the collection vehicles to the 8 Transfer Points that will cover for the entire 92 Dorbar Shnongs of the GSPA.

• The compactors from the 8 transfer points move towards the landfill site or to the Compost plant according to the waste they have received.

18519

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

If some families gives mixed up waste while others give segregated waste this project plan will not work and the coloured bins supplied to every household will go wasted. Hence, to avoid such a situation the following must be done by the Government and the Consultants:

a. As far as possible, reach all residents of the entire GSPA with the training package on the best practices of Solid waste management. The process will require about 200 training programmes to be conducted in the 54 Dorbar Shnongs of the areas outside SMB. (Some of the Localities have about 10 Dongs with over 4000 households like in Madanrting Dorbar Shnong. It may require more than 10 training programmes to cover the majority of the Households in this particular Dorbar).

b. As far as possible, form Locality Level Task Force to supervise the waste management activities within the Shnong to ensure sustainability of the process. Members of the task force will need special training by the CPPA team.

c. The residents of the areas outside SMB will not play spoil sport to the NERCCDIP in the long run. The training to be imparted to residents outside SMB should not wait long, so that the present resource team and their efforts can be utilized and maximized.

d. The Rangbah Shnongs and the Executive Committee of the Areas outside SMB will require special environment building and PR expertise to get to agree for training and to start practicing the new systems of waste management.

e. It is required to promulgate a rule on uniform practice of Solid waste management, and to aggressively enforce segregation of waste at source in the GSPA. It has to be aggressively enforced, penalize offenders and defaulters and activate the Local Dorbars to participate in management and supervision.

18620

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Followings are the proposed activities during January to December 2016

Sr No Programmes 1 Facilitate the process of best practices of waste management in the areas outside municipality a Identify groups and individuals to seek support for the project b Mapping of stakeholders and prepare a convergence plan c Formation of a core advocacy group To organised Public consultation with stakeholders as a means to generate positive support 2 towards the objective of the project a Conduct Focus Group Discussions b Organise Public Consultation Meetings with citizens of Dobar Shnong/Pylluns 3 Formation for task force for every unit (Dorbar Shnong) in areas outside municipality a Facilitate formation of Task Force in all the Dorbar Shnongs on SWM b Provide training on roles and responsibilities to the members of the Task Force. Organise and conduct awareness training programmes on SWM to cover at least 80% of the 4 households a Conduct Awareness Training for the residents of the different shnongs b Arrange training of the SWM Workers at Shnong/Pyllun Levels. To ensure at least 80% of the population practicing segregation of waste at source in the target 5 areas a Training and monitor segregation of waste at Source.

6 To conduct gender sensitization workshops for various stakeholders in the target areas a Identify stakeholders for Gender Action Programme b Conduct Public Consultation on Gender in the GSPA c Conduct Gender Sensitization programmes in the GSPA. 7 To promote gender equity in the implementation of the NERCDIP in the target areas a Facilitate and advocate gender equity in the implementation of the NERCCDIP b Conduct workshops to identify issues and to recommend for addressing the issues. c Advocate gender equity in project and in the area d Conduct Gender Audit 8 To promote equal opportunities for women in the operation of the SWM in the target areas Advocate and ensure women participation in the different opportunities to come from the a project implementation b Identify specific opportunities for promoting employment for women c Conduct a study on available opportunities for urban poor women To link and converge with other related programmes like the Swachh Bharat Mission, CM 9 Youth for Green Mission, in the efforts to achieve peoples corporation and participation for Clean Shillong Campaign a Streamline, update convergence plan

18721

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Sr No Programmes b Implement programme level collaboration with the various stakeholders and partners c Specific Programme Facilitation 10 Facilitate public distribution of household waste bins in areas outside the municipality a Provide training on the distribution system to the Task Force and Volunteers Facilitate and Coordinate the distribution events from stocking of the bins to distribution and b systems recording. c Coordinate in the start of the segregation at source 11 Facilitate the Zero littering Campaign in Schools outside the Municipality a Conduct orientation training for students in schools in GSPA b Facilitate formation of Zero Littering Crusaders Clubs c Facilitate inter School events to promote Zero Littering Concepts. d Facilitate students exposure for select schools 12 Promote livelihood enhancement training to Trash Sorters/Rag Pickers a Promote SHGs and provide training on group functioning for livelihood development Provide suitable linkages to government schemes for strengthening the livelihood of the poor b households.

2.4.12 Capacity Building Programmes and Community Mobilizations During the reporting period the CPP team made various efforts under capacity building programme for SWM. The various programmes organised ranges from monitoring of SWM activities, task force management etc. The various programmes organised during the reporting period may be seen from the following table 6.

Table 6: Capacity Building Programme under SWM Sr. Training / Attended Training Agency Mode of Training Venue No Capacity Batch Start Date /Place Building strength 1 Monitoring 01/08/2015 Community Feedback and Different at different 7 Residents suggestion on new localities localities system from residents 2 Inspection 04/08/2015 Community Inspection on unknown Cleve at Cleve Residents garbage vehicle Colony 4 Colony providing services at the locality 3 Task Force 07/08/2015 Task Force Formation of a task Rilbong Formation 25 Members force Meeting 5 Planning 13/08/2015 IYCN Group Planning for preparing DSMC Meeting a proposal for Swachh Office 8 with IYCN Bharat Group 6 Meeting 24/08/2015 Presidents of Discussion on starting Presidents with S.D the a mini town waste residence 4 Khnongwir Town Dorbar management structure for Mawlai

18822

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Sr. Training / Attended Training Agency Mode of Training Venue No Capacity Batch Start Date /Place Building strength 7 Planning 24/08/2015 IYCN Group Planning for preparing DSMC Meeting a proposal for Swachh Office 6 with IYCN Bharat Group 8 Meeting 25/08/2015 PD, IYCN Presentation of PD's office with Project Group, Swachh Bharat Raitong Director 11 CPPA staff Abhiyan Proposal Building prepared by IYCN group 9 Planning 25/08/2015 Members of Planning for Bharat meeting Scout and monitoring by the Scouts and with Bharat 10 Guides Scout and Guides to Guides Scout and different localities office Guides under NERCCDIP 10 Planning 28/08/2015 EC Members Discussion on starting Office of the meeting of a mini town waste Dorbar with EC of 7 Nongkhyriem management structure Shnong, Nongkhyrie DS for Nongkhyriem , Nongkhyriem m 11 Planning 02/09/2015 Bharat Planning on route Map Bharat meeting Scouts and for Monitoring Scouts and with Bharat 28 Guides Guides Scout and Office Guides 12 Meeting 07/09/2015 IYCN Group Review of Concept DSMN with IYCN Proposal for Swachh Office 5 Group Bharat Mission

13 Orientation 07/09/2015 MLCU Orientation to MLCU DSMC to MLCU students students Office 6 students

14 Meeting at 09/09/2015 Mr Wanshan Discussion on PCB Office Pollution Kharkhrang planning approaches 3 Control for Swachh Bharat Board Mission 15 Meeting with 15/09/2015 Seng Planning for Gender Presidents Seng Kynthei and Workshop residence 5 Kynthei of CPPA Staff Madanryting 16 Monitoring 18/09/2015 Scouts and Monitoring of Garbage Laban of Garbage Guides from Vehicles during Locality Vehicles at Laban operation Segregation 30 Laban Presbyterian, St Johns, CPPA Staff 17 Planning 19/09/2015 Seng Planning for Gender Presidents meeting with Kynthei and Workshop residence Seng Kynthei 5 CPPA Staff of Madanryting 18 Monitoring 21/09/2015 Scouts and Monitoring of Garbage Laban of Garbage Guides from Vehicles during Locality Vehicles at 18 St Johns operation Segregation Laban School, CPPA Staff

18923

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Sr. Training / Attended Training Agency Mode of Training Venue No Capacity Batch Start Date /Place Building strength 19 Monitoring 21/09/2015 CPPA Staff Monitoring of Garbage Mawprem, of Garbage Vehicle Jaiaw, Vehicles at Wahingdoh 2 Mawprem, Jaiaw, Wahingdoh 20 Meeting 22/09/2015 PD and Discussion of Route PDs Office with PD 3 CPPA staff Plan and SMB 21 Monitoring 25/09/2015 Scouts and Monitoring of Garbage Laban of Garbage Guides from Vehicles during Locality Vehicles at Laban operation Segregation Laban 18 Presbyterian, MSW Interns, CPPA Staff 22 Monitoring 25/09/2015 Scouts and Monitoring of Garbage Lower of Garbage Guides from Vehicles during Mawprem Vehicles at Gurkha operation Segregation Locality 14 Lower Pathshala Mawprem school and CPPA Staff 23 CM's Clean 01/10/2015 DC, SIPMIU, Awareness and Conference and Green SMB. NGOs, interactive session on Hall, Campaign DSMC best practices of waste Raitong 27 management and Building plastic waste management 24 Swachh 02/10/2015 Govt Depts, Cleaning drive of a PGT Road Bharat Institutions, stretch of road Mission 900 NGOs SMB Cleaning Drive 25 Teachers 07/10/2015 Human Awareness on best Class training Resource practices of waste Room, 63 Workshop Dept, NEHU management and Role NEHU of Community 26 Monitoring 12/10/2015 ADB Team Monitoring on Wahingdoh at and CPPA Operation Segregation and Laban 6 Wahingdoh Locality and Laban 27 ADB 12/10/2015 ADB Team, ADB mission meeting DSMC Mission SIPMIU and Office 22 DSMC- CPPA 28 Meeting at 13/10/2015 EC, Seng Discussion on crating Community Mawlai Kynthei and a mini SWM unit at Hall, 46 town DSMC Mawlai Mawlai Dorbar 29 CM's Clean 16/10/2015 DC, Bethany Cleaning drive by States and Green Society, schools to make Central Campaign NESFAS, Shillong Clean and Library School Green 60 Principals/te achers and Commercial establishmen

19024

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Sr. Training / Attended Training Agency Mode of Training Venue No Capacity Batch Start Date /Place Building strength ts owners 30 Gender 17/10/2015 Weaker Public Consultation Community Workshop at Women cum capacity building Hall, 44 Madanryting Group and for indigenous women Madanrytin DSMC g 31 Meeting with 21/10/2015 Headman Discussion on Headman's Headman, and DSMC organising best Residence 4 Wahdieng- practices of SWM lieng during Church Events 32 Inspection 22/10/2015 DSMC- Inspection to all puja Different of Puja CPPA team mandaps on best Localities 5 Madaps practices of waste with puja management madaps 33 Planning 29/10/2015 PD, Planning meeting on PD's Office meeting SMB.CPPA- operation segregation 8 with PD DSMC and strategies for revamping SMB 34 Organised 31/10/2015 Schools, PD, Painting competition States painting CPPA- for School Students Central 350 competition DSMC, Library Teachers 35 Meeting 02/11/2015 SMB, CPPA- Planning meeting for EE's Office, with DSMC SMB workers SMB 3 EE,SMB

36 Composting 13/11/2015 Bethany Workshop on Thomas and Society, composting and Jones Recycling CPPA- recycling technologies School, 48 Technologi DSMC, Seng Lumparing es Kynthei workshop Lumparing 37 TV 17/11/2015 Discussion on solid Doordarsha Interview on , CPPA- waste management for n Kendra Waste 5 DSMC, Pla Shillong City Studio, Manageme Iew, PHED, Laitkor nt NEEDS 38 Meeting at 24/11/2015 Bethany Discussed on progress Bethany Bethany Society, of planning for Society Society CPPA- proposed mini Office 3 DSMC, Seng compost plant for Kynthei SHGs Lumparing 39 Meeting at 27/11/2015 Headman, Discussed on Headmen’s Cleve CPPA- developing a mini Residence 3 Colony DSMC compost plant at the locality 40 Review 30/11/2015 SPD, CEO, Discussed and Conference meeting EE, SMB presented on Hall, with area 21 Staff, CPPA- strengthening the Raitong Inspectors DSMC working structure of Building SMB

19125

SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Table 7: Gender Action Plan – Progress Update North Eastern Region Capital Cities Development Investment Program – (loan) SIPMIU - Shillong (Meghalaya) (Reporting period – July-_December 2015)* Activities Target Indicators Progress to date* Issues/ challenges Outcome - Sustainable and increased access to better urban services in five program cities Conduct of 1 gender 10 municipal council officials A) Progress Inception to June 2014 sensitization seminar that gender-sensitized Representatives • Identification of the needs and problems of women were highlights gender issues in of 5 women's NGOs, including self- done in three Public Consultations in April 2012. (1) Women water supply, sanitation, help group gender-sensitized 20 Groups in Slum areas –55 participants - all women (2) National solid waste and drainage, community members (50% women), Domestic Workers Movement – 62 participants with 98% women. and the need for women‘s including from scheduled castes (3) Federation of women organization – 33 participants – all involvement in the (SCs) and scheduled tribes (STs), women. implementation, O&M of where applicable, gender-sensitized • Sensitization workshop (Specific mention of rights of these services State Investment Program women when FHH survey was discussed) for 42 Programme Management and Implementation Officers (men and women) of the NSS done on 2nd Sept. 2011 Unit (SIPMIU) staff of state • Gender Sensitization workshop was also done in the executing agency gender-sensitized Dorbar Shnong of Lumshyiap on the 10th of Sept. 2011. • Gender Sensitization Workshop for Government Officials of 6 line department was held on April 17th 2013 in which officials from SMB, SIPMIU, MUDA, PWD, PHED, Urban Affairs Dept took part. 48% of the participants are women. • Meeting with 11 Rag Pickers (10 Women, 1 man) on 17th November 2013, at Dumping site for brief interaction. • Consultative meeting with 26 Rag Pickers at Marten Mawiong Dumping site and census taking and needs identifications were done on 26th November 2013. Five Wayside Signages on gender equity with special focus on Equal wages will be put up soon at four prominent locations in the city. • Public Consultation Meeting on Gender Issues and Livelihood Enhancement training for poor indigenous women was organised for the women of Upper Shillong Cluster of Villages. 53 persons attended the programme on 13th June 2014.

192

26 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Activities Target Indicators Progress to date* Issues/ challenges (B)Reported Progress July-Dec 2014 • Prepared city level convergence plan on gender action plan. • A plan for a Film strip advertisement is been developed focused on segregation of waste at the household level. (C) Reported Progress Jan-June 2015 • Production of Film strip is being developed • Planning for a workshop with the women organization of Madanryting Shnong to be held in June 2015 • Training of the Conservancy workers mainly women sweepers on best practices of waste management on 29th May 2015 Output (i) - Improved water supply and infrastructure Provision of connections -- -- and meters to poor female- • Employment of women in the Not Applicable headed households (FHHs). construction of pipelines, plants, etc., with implementation of same pay for work of equal value‘ Output (ii) Improved sanitation infrastructure Prioritize connections to -- Not Applicable sewerage system of poor female-headed households Output (iii ) Improved solid waste management systems Prioritize FHHs in the 6,000 FHHs provided with A) Progress Inception to June 2014 provision of household bins household bins • Survey on Female Headed households has been done and enlisted 4386 FHH in the city. Priority to the FHH in the Household waste bin distribution has been planned. • A guideline for the Distribution of the Household Waste Bins is being developed and the FHH are factored in the Priority Category list. B)Reported Progress July-Dec 2014 A total of 418 Female Headed Householders have received the household waste bins on priority category during the distribution to 10526 householders during the reporting period.

193

27 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Activities Target Indicators Progress to date* Issues/ challenges (C) Reported Progress Jan-June 2015 In each of the distribution of HH waste bins the FHH were given first and most of the time a VIP handed over the bins to the FHH.Altogether about 380 Single Female Headed Householders received the Bins on priority basis, quite often from the hands of a VIP or the local Headmen. (D) Reported Progress July-December 2015 70 FHH received bins on a priority basis during the households bin distribution. Conduct of 1 consultation 100 Women and men community A) Progress Inception to June 2014 per program city, among members consulted. • 32 Public Consultation organised and about 63% of community members participants are women. Over 94% of the women participants (target: 50% women) of public consultations were ST women. The consultation also including SCs and STs, and dwelt on schedules of trash collection. NGOs on the manner and Conducted one Public Consultation Meeting on Gender issues schedule of trash collection in June 2014 in which 45 women and 6 men participated. (C) Reported Progress Jan-June 2015 • 6 Public Consultation in Lachaumiere, Nongmali III, Madanryting, Mission Compound, Lawmali and Nongthymmai have been organised between Feb and June 2015. • (D) Reported Progress July- December 2015 In October 2015 one public consultation cum training on income generating programme with 54 indigenous women was organised at Mandanryting. Conduct an exploratory Study report produced A study was conducted by the North Eastern Hill University on study on possible livelihood waste characterization in Shillong and found out that 40% of opportunities from available Waste is compostable and another 30% are recyclable and re- recyclable materials and the usable. Hence this information is shared with the people market for possible products particularly the women, who express interest in recycling from these recycled activities. materials Conduct of 2 trainings on 50 women community members A) Progress Inception to June 2014 alternative livelihoods for trained on alternative livelihoods. One training on waste paper recycling was conducted with women using recyclable resource persons for the Science and Technology Department, materials (e.g., paper Govt of Meghalaya from 23-26 July 2012, at the Shillong Science mache, etc.) centre. 20 women SHG leaders from poor localities got the training. 194

28 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Activities Target Indicators Progress to date* Issues/ challenges One training on waste paper recycling is planned for August 2014 to cover the Rag Pickers and the FHH persons. B)Reported Progress July-Dec 2014 • Altogether 18 trash sorters(of the total 26 DPs who have been identified for the preparation of RP of 8500 sqmts.lanfill site[balance area of Tranch 1] have been trained in different compost technologies, like Bokashi Composting, Vermin Composting, Bio-Composting from 21st to 22nd November 2014. • One Self Help Group has been formed by the Trash Sorters Named “Iai Trei Minot SHG”. Household Composting has been started by members of the SHG. • In appointing “Zero Littering Volunteers” for Police Bazaar “Zero Littering Zone” 50% women are planned to be appointed. (C) Reported Progress Jan-June 2015 • A plan to allot a plot of land to the SHG at Marten Mawiong for carrying out composting activities from biodegradable waste coming in from the city under the Operation Segregation” Programme. • Consultative meetings have been going on from Jan to June 2015, the last meeting being held on the 11th June 2015 (D) Reported Progress July-December 2015 54 women from Mandanryting were trained on bio-composting by resource person from Bethany Society/NGO in November 2015. ° On 13th November 2015 Composting and recycling technologies training was organised at the Thomas Jones School in Lumparing. SHG members, House wives and parents of the school attended the training. The training was jointly organised by DSMC, the School Management and the Bethany Society (NGO). Altogether 42 persons participated in the training.

Output (iv) Strengthened project implementation capacity of executing agency Conduct of demographic At least 10% of the population Between December 2011 and April 2012, 375 locality blocks survey of program city, surveyed, with each sample were surveyed on total number of households, total population

195

29 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Activities Target Indicators Progress to date* Issues/ challenges showing gender differential comprising 50% women and a Survey on Female Headed households has been done and access to urban services, enlisted 4386 FHH in the city. About 70% of the FHH belong to income / poverty levels, ST category. among other such indicators, specifically, between male- headed and female-headed households and among SCs and STs Instituting geographic and Project management information Sex-desegregated information system is available with Shillong sex-disaggregated project system in place with sex Municipal Board. This will be operational in the implementation of management information disaggregated data the SWM project. system Conduct of on-the-job SIPMIU staff capacitated on gender- A workshop has been conducted on gender sensitization for the capacity-building activities responsive project management officials of SIPMIU and other line departments to have gender for SIPMIU on gender- sensitive policies even in employment conditions. The workshop sensitive recruitment, was held on 17th April 2013. management, procurement Altogether 309 Conservancy Workers of The Shillong Municipal and contract management, Board (SMB) were trained on best practices of waste project and performance management in May-June 2014. 70% are women workers. monitoring, safeguard Discussion has been initiated with SIPMIU and SMB about compliance, land inducting few women at the Sanitary Inspectors ranks. acquisition, and preparation A training module for the inspectors and the conservancy of feasibilities studies and workers is being designed by the DSMC team, in consultation detailed designs with the Inspectors.. *This report is applicable to all tranche projects (TR-I + Tr-II).

196

30 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

3. Tranche - II: 3.1 Status of Implementation of sub projects A. Scope and Progress Table 8: Status of Implementation of sub projects under TRANCHE II with regards to Social safeguards Component Works Progress Scope of resettlement 1) Tranche –II- Garage cum Workshop shed and -Construction of Garage Cum work Category C of Solid Waste Staff Rest Room. shop work stated- in progress (21.24 ADB (SPS), Management, Date of Contract :- Percent Completed). 2009. No Shillong. Signed 04th March.2013 Contract terminated on 25th June impact Signed to proceed :- 2015. Possession of the site taken over 30th March.2013 on 2nd July 2015. Tender documents Contract Value:1,69,75,807.45 for Balance works approved by ADB Bids invited for the balance works vide notice no SIPMIU /MEG/12/2015/1 dated 6th Nov 15. Deadline for the bids is 22nd Dec 2015. 02 bids were received and opened on 22nd Dec 2015. Technical Bid Evaluation is in progress. 2.) Tranche – Procurement of Primary and All the Vehicles and Workshop Category C of II-Solid Waste Secondary Collection Vehicles Machineries have been procured - ADB (SPS), Management, and Workshop Machineries. Progress (100% Percent Supplied 2009. No Shillong. Date of Contract :- Completed). impact Signed 18th July.2013 Signed to proceed :- 18th July.2013 Contract Value:1,36,66,420.00

19731 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Component Works Progress Scope of resettlement 3.) Tranche – Procurement of Bins and • Progress (97.17% Percent Supplied Category C of II- Solid Waste Personnel Protective Equipments. Completed). ADB (SPS), Management, Date of Contract :- • 60,284 nos Household Bins 2009. No Shillong. 17th.Janaury.2014 distributed to 30,142 households . impact Contract Value:1,71,59,351.65 • 30Nos 25litre capacity HDPE litter Bins received and Installation at different locations in SMB area completed • 70Nos 50litre capacity HDPE litter Bins received and Installation at different locations in SMB area completed. • 460 Pair Gum-boot received. • 4860Nos Cotton Mask received. • 460Nos Rain-Coat received. • QAP for 360Ltrs capacity Mobile Garbage Bins is to be submitted by the Supplier. • 460 pairs of PVC hand gloves received • A supplementary agreement was signed on 23rd Nov 15 for supply additional 3000 nos household bins.

4.) Tranche – Construction of short term Construction of short term sanitary II- Solid Waste sanitary landfill over an area of landfill over an area of 8500 sq. Mts Management, 8500 sq. Mts. DPR is approved and tendered Shillong. Contracts are not yet awarded NERCCDIP/TR- 02/SHG/PH2/ Bids are invited vide bid notice No: Category B for SWM /04 Developing and SIPMIU/MEG/1/2015/1 dated 30th IR and Construction of sanitary landfill at March, 2015. Deadline for submission category C for Marten Mawiong site (8500 Sqm) for bids is 30th June 2015. .Bids IP of ADB received and opened on 30 Jun 2015. (SPS), 2009. Three bids were received. Technical 25 Trash evaluation is approved by ADB on Sorter will be 31/08/2015. Financial bid opened on affected 9th October 2015. Financial Bid temporary.

19832 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Component Works Progress Scope of resettlement Evaluation report submitted for ADB and MOUD approval on 9th November 2015. NERCCDIP/TR Bids are invited vide bid notice No: 02/SHG/PH2/SWM/05 SIPMIU/MEG/1/2015/1 dated 30th Procurement of Vehicles (6) and March 2015. Deadline for submission Equipment (8) for Landfill Site at for bids is 29th June 2015. Bids invited Marten, Shillong however no bids were received. The bid document has been divided into Two packages and ADB has accepted the proposal. The bid documents were finalized and approved by ADB. The bid Invitation process initiated and the deadline for bid submission is 22nd December 2015. 01 bid received and opened on 22nd Dec 2015. Technical Bid Evaluation is in progress. NERCCDIP/TR-2/SHG/ SWM /06 Bids are invited vide bid notice No: Procurement of Primary (40) & SIPMIU/MEG/1/2015/1 dated 30th Secondary (19) Refuse Collection March 2015. Deadline for submission Vehicles and Metallic Containers for bids is 26th June 2015. Bids (100) for Solid Waste received and opened on 26 Jun 2015. Management in GSPA, Shillong One bid was received. Technical evaluation was approved by ADB on 31/08/2015. Financial bid opened on 9th October 2015. Financial Bid Evaluation report submitted for ADB and MOUD approval on 9th November 2015. Decision awaited from MOUD NERCCDIP/TR-02/SHG/SWM/07 Bids are invited vide bid notice No: Procurement of Different types of SIPMIU/MEG/1/2015/1 dated 30th Bins (102966) and Personnel March 2015. Deadline for submission Protective Equipment (36484) for for bids is 25th June 2015. Bids Solid Waste Management in received and opened on 25 Jun 2015. GSPA Shillong Five bids were received. Technical evaluation is approved by ADB on 31/08/2015. Financial bid opened on 9th October 2015. Financial Bid

19933 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Component Works Progress Scope of resettlement Evaluation report submitted for ADB and MOUD approval on 9th November 2015.Decision awaited from MOUD 5) Tranche – NERCCDIP/TR- 02/SHG/SWM/02 Bids for construction of compost is Category C for II- Solid Construction of 170 TPD being invited vide bid notice No. IR and Waste Compost Plant and Procurement SIPMIU/MEG/14/2015/1 dated 27th category C for Management of Waste Handling Equipments November 2015. Deadline for bid IP of ADB , Shillong. and Machinery at Marten, submission is 29th January 2016. (SPS), 2009. Shillong, Meghalaya. Due Diligence Report Submitted.

3.1.1 Scope of RP and IP impact Table 9: Scope of RP and IP impact under Tranche –II Component Location Description Impact on Land Temporary acquisition and Impact resettlement Solid Waste Management, Municipal Construction of Garage cum Nil. Land is in the Nil Shillong: Garage cum Trenching Workshop Shed and Staff possession of Workshop shed & Staff Ground at Rest Room at old landfill SMB. Rest Marten, site at Marten, Mawiong. Mawiong Shillong (NERCCDIP/TR- 2/SHG/SWM/01) – Solid Waste Management, SMB Area ll the Vehicles and NIL NIL Shillong: Procurement of Workshop Machineries have Primary, Secondary been procured - Progress Collection Vehicles and (100% Percent Supplied Workshop Machineries – Completed). Shillong (NCB Number, Invitation Number, SIPMIU/SHI/NCB-2)- (NERCCDIP/TR- 2/SHG/SWM/02) Solid Waste Management, SMB area Contract Agreement signed NIL NIL Shillong: Procurement of by the agency as on 17-01- Different types of Bins and 2014. Bill submitted for Personnel Protective mobilization advance on Equipment – Shillong 24.02.2014, released on

20034 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Component Location Description Impact on Land Temporary acquisition and Impact resettlement (NERCCDIP/TR- 14/03/2014. 2/SHG/SWM/ 03-R2) The contractor submitted QAP on 29.05.2014 for 25,50 ltr litter bins, Rain coat and Mask on along with a 20ltr Bin, Gum Boot and hand gloves. QAP for 20, 25,50 Ltr bins, Rain coats, Gumboots, Handgloves, mask is approved. The supplier submitted the sample for 25 & 50 Ltr bin on 25-06-2014. The sample is checked and the capacity is found to be correct. The sample for 20 Ltr bin is already approved on 29-05-2014 The sample for Rain Coat , Mask, Gum Boot and Hand Gloves is also approved on 11-02-2014 NERCCDIP/TR- Municipal Develop the balance work of NIL Category B 02/SHG/PH2/ SWM /04 Trenching the emergency sanitary Land is in the for IR and Developing and Ground at landfill site measuring 8500 possession of category C Construction of sanitary Marten, sqm at Marten. SMB. The land for IP of landfill at Marten Mawiong Mawiong possession ADB (SPS), site (8500 Sqm) Bids are certificate has 2009. invited vide bid notice No: been placed as 25 Trash SIPMIU/MEG/1/2015/1 annexure 3. Sorter will dated 30th March, 2015. be affected Deadline for submission for temporary. bids is 30th June 2015 NERCCDIP/TR- Municipal Compost Plant and NIL Category C 02/SHG/SWM /02- Trenching Procurement of Waste Land is in the for IR and Construction of 170 TPD Ground at Handling Equipments and possession of category C Compost Plant and Marten, Machinery at Marten, SMB. The land for IP of

20135 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Component Location Description Impact on Land Temporary acquisition and Impact resettlement Procurement of Waste Mawiong Shillong, Meghalaya. possession ADB (SPS), Handling Equipments and certificate has 2009. Machinery at Marten, been placed as Due Shillong, Meghalaya. annexure 3. Diligence Report Submitted.

B. Implementation and institutional arrangements:

The same has been described in 2.1 B in section 2 under Tranche I.

3.1.2 Social Safeguard Monitoring Checklist

Table 10: Social Safeguard Monitoring Checklist Project Data Name of Project & Subproject : Loan No-2834-IND: 1. Construction of Garage cum Workshop shed & Staff Rest,2. Procurement of Primary, Secondary Collection Vehicles and Workshop Machineries;3. Procurement of Different types of Bins and Personnel Protective Equipment Project Disbursement Status (%): 70.04% Type of contract: § Regular § Design-Build § Combined Safeguards Categorization A B C IR C IP C Project Data Name of Project &additional Loan No-2834-IND: 1. NERCCDIP/TR- 02/SHG/PH2/ SWM /04 Subproject: Developing and Construction of sanitary landfill at Marten Mawiong site (8500 Sqm),2.NERCCDIP/TR 02/SHG/PH2/SWM/05 Procurement of Vehicles (6) and Equipment (8) for Landfill Site at Marten, Shillong;3. NERCCDIP/TR-2/SHG/ SWM /06 Procurement of Primary (40) & Secondary (19) Refuse Collection Vehicles and Metallic Containers (100) for Solid Waste Management in GSPA, Shillong;4. NERCCDIP/TR-02/SHG/SWM/07 Procurement of Different types of Bins (102966) and Personnel Protective Equipment (36484) for Solid Waste Management in GSPA Shillong. NERCCDIP/TR- 02/SHG/SWM /02- Construction of 170 TPD

20236 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Compost Plant and Procurement of Waste Handling Equipments and Machinery at Marten, Shillong, Meghalaya. Project Disbursement Status (INR) 7.39 Million Type of contract : § Regular § Design-Build § Combined Safeguards Categorization A B C IR B IP C

C. Design and Engineering Status Item Status Follow up Type of Required Action (Y/N) required (Y/N) (Please tick appropriate box) Final detailed engineering design of the Y Y § Updated draft IR/IP sub project completed New RP preparation No action Changes in project design/ scope Y Y Project re-categorization (occurred or envisaged) (IR/IP) IR Impact assessment New RP preparation § No action

D. Institutional Status Readiness No Item Status Follow up Completion (Ready/Not required Deadline ready/NA) (Y/N) 1 Mobilization of civil works contractor Ready 2 Mobilization of Project Supervision Ready Consultant 3 EA’s Safeguards Unit with designated Ready staff 4 Recruitment of External Monitoring NA Agency E. Safeguards Requirements No Item Status Follow up Completion (Ready/Not required Deadline ready/NA) (Y/N) 1 Safeguards monitoring included in Ready the project progress report 2 Final/ updated RP prepared and Ready N February 2015 submitted 3 Project’s Grievance Redress Ready N Mechanism established 4 Recruitment of third independent NA party for negotiated land acquisition 5 Project’s ESMS (for FI) established Ready

20337 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

F. RP/ IPP Monitoring Checklist Item Safeguards Related Requirements Status Completion Progress to No. (Ready/Not Deadline Date/ Remarks ready/ NA) 1.0 Management Institutional and Financing Arrangements 1.1 Financing and budget : (i) safeguard office and Ready staff; (ii) RP/IPP cost 1.2 Establish Safeguard Unit: (i) resettlement Ready offices (ii)resettlement staff as in RP (iii) safeguards’ database (iv) facilities (v) safeguards training Updating of DD/RP/IPP based on Detailed Design NA 1.3 Update DD/RP/IPP: (i) revise based on DMS Ready Completed in (ii) revise implementation schedule (iii) revise February 2015 budget 1.4 Compensation rates: (i) approved by Ready Completed in Government ; (ii) Adequate as per RP/RF; (iii) February 2015 APs informed. Disclosure and Grievance Redress Arrangements 1.5 Disclose final/updated RP/IPP: (i) to the APs in Ready March 20153 local language; (ii) in ADB website; (iii) in EA’s website 1.6 Disclose project activities to affected Ready June 2015 communities: (i) put up a project sign boards; (ii) distribution of project leaflets and GRM to affected communities 1.7 Grievance redress committees: (i) clear terms Ready of reference; (ii) appointment decree; (iii) publicly disclosed among APs. 1.8 Grievance redress records: (i) list and numbers NA of grievances received; (ii) numbers of resolved issues; (iii) numbers of cases under GRC review; (iv) outstanding cases (filed to court) Monitoring and Reporting Arrangements 1.9 Set up internal monitoring system : Ready (i) assessment on capacity and staff requirements; (ii) criteria of safeguards assessment ; (iii) reporting mechanism 1.10 Appoint external monitoring agency (as NA relevant): (i) recruitment schedule; (ii) TOR; (iv) baseline survey (v) reporting mechanism (vi) action taken by management on reports. 1.11 Reporting: (i) frequency; (ii) timeliness; (iii) NA identified issues; (iv) action taken and/recommendation. 2.0 PR/IPP IMPLEMENTATION Consultation 2.1 Consultation: (i) responsibility; (ii)stakeholders NA Continuous Identified; (iii) consultation and process; (iv) documentation Mapping and Assets Inventory

______

3The RP was disclosed in ADB and SIPMIU website http://sipmiu.nic.in/resettlemetplan/RP.pdf. .

20438 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Item Safeguards Related Requirements Status Completion Progress to No. (Ready/Not Deadline Date/ Remarks ready/ NA) 2.2 AP Identity cards & affected assets records: (i) NA Completed issuance and distribution of AP ID cards, (ii) detail measurements survey of affected assets and documentation 2.3 Land acquisition activities: (i) maps of affected NA and relocation sites; (ii) acquisition & relocation schedule; (iii) coordination with the asset’s acquiring, transfer and registration bodies 2.4 Common property/ public assets: (i) final NA inventory; (ii) restoration plan and schedule; (iii) funding Compensation,sources Relocation and Rehabilitation NA 2.5 Payment of compensation and entitlements (as NA stated in the RP): (i) schedule of payment; (ii) records/ receipts of payment 2.6 Relocation of process ( relocation site NA readiness): (i) housing& associated facilities established; (ii) transfer of new land/plot/ house ownerships completed 2.7 Provision of (a) income restoration, (b) Ready 14 APs received additional assistance for vulnerable APs, (c) training training, etc. (as stated in the RP): (i) per type of activities; (ii) schedule of implementation Monitoring and Reporting 2.8 Submission of the reports: (i) semi-annual NA Category B for IR monitoring reports; (ii) external monitoring and and C for IPP evaluation reports (as required); (iii) completion report 2.9 Transfer of acquired assets to the acquiring NA agency

G. Safeguards Loan Covenants Item No. Covenant Agency Status of Compliance Sl. No. Loan Covenant Vi (16) GOI and the States will ensure that all land and GOI, The sub project work right-of-way required for the Investment GoMe, will be carried out in Program are made available in a timely manner, GoMi, government land. RP adequate compensations are provided prior to GoNa, has been prepared for the signing of relevant civil works contracts, and GoSi & 25 trash sorters who are involuntary resettlement is carried out in GoTrt temporary affected. accordance with the Resettlement Framework Provided training to 14 (RF) and Resettlement Plans (RPs) agreed APs as per entitlement. upon between the Government and ADB, the Government’s National Policy on Resettlement and Rehabilitation, and ADB’s Policy on Involuntary Resettlement (1995). An RP will be prepared for each sub-

20539 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Item No. Covenant Agency Status of Compliance project involving land acquisition or resettlement and shall be submitted to ADB for review and approval prior to award of any related civil works contracts. For sample sub-projects, updated RPs will be provided to ADB for review and approval following detailed design and prior to award of civil contracts. Viii(16) GoI and the States will ensure that sub-projects GOI, Fourteen vulnerable will not negatively impact vulnerable groups, GoMe, APs were given training such as indigenous peoples. In the GoMi, for skill enhancement. event of their involvement in any of the sub- GoNa, projects, the GoI and the States will ensure that GoSi & the sub-projects are carried out in accordance GoTr with the Indigenous Peoples Development Framework (IPDF) agreed upon between GoI and the States and ADB and comply with ADB’s Policy on Indigenous Peoples (1998). 17 In the event any issues related to indigenous GOI, No issue related to people arise in the course of Project GoMe, indigenous people is implementation, the Borrower and the States GoMi, anticipated in course of shall ensure to address those issues in GoNa, execution. accordance with the applicable laws and GoSi & policies of the Borrower, ADB's Policy on GoTr Indigenous Peoples (1998) and the Indigenous Peoples Development Framework for the Facility as agreed between the Borrower, the States and ADB and incorporated by reference into Schedule 5 to the FFA. In the case of any discrepancy between the Borrower's legislation and ADB's policy, ADB's policy shall prevail. (para. 17) ix. 20 GOI and the States will ensure that all civil GOI, Adequate provision has 21 works contractors comply with all applicable GoMe, been made in the Bid labor laws, including those on occupational GoMi, documents. health and safety, and do not employ child labor GoNa, as defined in national legislation for construction GoSi & and maintenance activities. Priority for work will GoTr be given to people from the area where the

20640 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Item No. Covenant Agency Status of Compliance works are implemented and men and women will receive equal pay for work of equal value. 23 Within six (6) months of the Effective Date, each GoMe, Established. State shall have established a grievance GoMi, reporting and redressal mechanism. GoNa, (para. 23) GoSi & GoTr Overall Status of Compliance § § § Not complied – Complied with further monitoring Fully complied Redressed action & – no further monitoring required action

3.2 Monitoring and Reporting Arrangements:

The sub project of T2has been categorized as “Category B for IR and category C IPP” as per SPS 2009 of ADB. The safeguard implementation related activities are being closely monitored to provide the SIPMIU with an effective basis for assessing safeguard progress and identifying potential difficulties and problems. Monitoring is currently being undertaken by the SIPMIU .The extent of monitoring activities, including their scope and periodicity, is commensurate with the project’s risks and impacts. Monitoring involves: (i) administrative monitoring to ensure that implementation is on schedule and problems are dealt with on a timely basis; SIPMIU monitoring also includes daily planning, implementation, feedback and trouble shooting. 3.3 Social Safeguard Activities - Update on RP and IP Plans and Implementation Status Table 11: Summary of Resettlement Impacts and Socio-Economic Details under SWM sub project at Shillong Type of Impact Number of APs 1.Permanent Loss Title Holder/Land Owner NIL Total Loss of land(sq.mts) NIL Loss of trees NIL Total land Holding in that Particular Plot (sq.mts) NIL Occupation NIL Vulnerability Annual Income (INR) NIL 2.Temporary Loss A)Temporary Loss/ Disruption of Business(Nos) Nil B)Temporary Loss/ Disruption of Business Employees of the business 25 enterprises(Nos) 3. Encroacher in ROW A) Encroacher in ROW(Nos) Nil Affected CPRs NIL

Source: census and Socio-Economic Survey, December 2010 and Socio-economic survey of November 2013

20741 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Table 12: Summary of Resettlement Impacts and Socio-Economic Details of SWM Particulars Quantity Permanent land aacquisition (private) Nil Temporary land aacquisition Nil Total Affected Households (Loss of Livelihood) 25 Total Affected Persons 132 Average Family Size of Affected Households 5.3 Total No. of Scheduled Caste HH Not Applicable Total No. of Woman Headed Households Not Applicable Total No. of Schedule Tribe Households Not Applicable Total No. of Title Holders NIL Total Number of Non-Title holders 25 Total No. of Tenants NIL Main Occupation of the Affected Persons trash sorting Average Annual Household Income Rs.75692 Source: census and Socio-Economic Survey, November 2010, Validate 14.01.2015

3.3.1 Summary of Land Acquisition (Temporary / Permanent) – Details of Ownership of Land The sub project activities do not require any land acquisition from private parties. The Garage cum Workshop shed & Staff will be constructed within existing landfill site for which the land is already is in possession of SMB. There is no land acquisition from private parties. The additional area for land fill site will be constructed in the same government land. There are 25 trash sorter will be temporarily affected. The land possession certificate is placed in annexure 3.

3.3.2 Status of Affected People: Land Requirement, Compensation and Rehabilitation (Systems, Plans) Since the land is in the possession of SMB and the project has been categorised as Category c as per SPS 2009, there is no resettlement impact either direct or indirect in nature. Of the total 25 trash sorter so far 14 trash sorter received livelihood training and the details has been reported in SMR January –June 2015.

3.3.3 Details of Affected Persons/ Persons to Be Affected, Validation and Verification of Affected Persons (Aps) The project has been categorised as Category C as per SPS 2009 for IP and category B for IR. There are 25 trash sorters will be temporarily affected and validation and verification of APs has been made. The list and the photo identity have been presented in SMR January –June 2015.

3.3.4 Compensation Decided / Planned and Progress On Provision of Compensation): The project has been categorised as Category C as per SPS 2009. There is no impact, hence there is no compensation payment is associated with this sub project. Of the total 25 trash sorter so far 14 trash sorter received livelihood training and the details has been presented in SMR January –June 2015..

20842 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

3.3.5 Compliance status with respect to National and ADB policy frameworks: The same has been described in 2.4.5 and annexure 1

3.3.6 Contractor’s Compliance to Safeguard Norms and Monitoring: The contractor is following the labour local labour law of Government of Meghalaya including providing equal wage to male and female labour as per requirements of the contract.

3.3.7 Grievance Redressal System and Processes and Progress: The Grievance Redressal Committee has been constituted through a Govt. Notification dated 13th Feb’12 headed by The Principal Secretary as Chairman in a Six Members Committee. Details are uploaded on to the Website of the SIPMIU, Shillong, and Government of Meghalaya. A copy of the Notification in this regard (Notification No.UAU.9/2012/2 dated Feb 13 2012) is placed in annexure3.

4. HH Waste Bin Distribution 4.1.1 Household Waste Bins Distribution in SMB Area-(as on December 2015) Till December 2015, 60,284 bins were distributed to the 30,142 households. The table provided in previous section shows the locality wise distribution details.

5. Gender Action Plan The same has been presented in section 2.4.7 and 2.4.10, table 7, of this report.

20943 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Annexure I: Compliance to National Laws and Policies: Policy and Legal Framework The policy framework and entitlements for the Program are based on national laws: The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 and ADB’s Safeguard Policy Statement, 2009 (SPS). The salient features of Government and ADB polices are summarized below.

1. Government Policy`4 The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013(The Central Government has notified January 01, 2014 as the effective date of the act,)

The act provides for transparent process and fair compensation to land owners and those affected by land acquisition, for land acquired for public purpose. In determining market price, (Sec 26 read with 1st Schedule) the land owner in urban area will get twice, due to the 100% solatium and in rural area, the multiplying factor is 1 to 2 depending on distance from nearest urban centre, to be notified by appropriate government, and then 100% solatium.

Traditionally R&R has been in the form of a one-time compensation, which was decided using the last registered sale or a similar sale in the vicinity of the land as a base. After the proposed project is set up, the land prices rise owing to the benefits of the development. This creates considerable dissatisfaction amongst the displaced people. To prevent such issues, the entire R&R package stipulates the provision of employment by the project owner in cases where jobs are generated by the project and basic infrastructure including drinking water, individual electric connections, health centre etc for the resettled. Over and above this, delivery of the compensation and the R&R are proposed to be preconditions to the transfer of the land title.

The procedure for acquisition and R&R will include a Social Impact Assessment (SIA) which will cover the investigation of public purpose, minimum extent of land required thereof, estimation of displacement and social impact on affected families apart from the overall cost versus benefit analysis for the proposed project.

The act restricts the use of emergency clause to defense, national security and natural calamities. Since there is no land acquisition in “legal terms” in this subproject, therefore this is not applicable.

2. ADB’s Safeguard Policy Statement, 2009 (SPS) The three important elements of ADB’s involuntary resettlement policy are

1. Compensation to replace lost assets, livelihood, and income;

______

4 The policy framework and entitlements for the program as well as for this subproject will now based on new national law(applicability is from January 2014) namely;: The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act 2013 and state laws and regulations. ; ADB’s Safeguard Policy Statement, 2009 (SPS); and the agreed Resettlement Framework (RF)..

210

44 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

2. Assistance for relocation, including provision of relocation sites with appropriate facilities and services; and

3. Assistance for rehabilitation to achieve at least the same level of well-being with the project as without it.

For any ADB operation requiring involuntary resettlement, resettlement planning is an integral part of project design, to be dealt with from the earliest stages of the project cycle, taking into account the following basic principles:

i. Involuntary resettlement will be avoided whenever feasible.

ii. Where population displacement is unavoidable, it should be minimized.

iii. All lost assets acquired or affected will be compensated. Compensation is based on the principle of replacement cost.

iv. Each involuntary resettlement is conceived and executed as part of a development project or program. Affected persons need to be provided with sufficient resources to re-establish their livelihoods and homes with time-bound action in co-ordination with civil works.

v. Affected persons are to be fully informed and closely consulted.

vi. Affected persons are to be assisted to integrate economically and socially into host communities so that adverse impacts on the host communities are minimized and social harmony is promoted.

vii. The absence of a formal title to land is not a bar to ADB policy entitlements.

viii. Affected persons are to be identified and recorded as early as possible to establish their eligibility, through a census which serves as a cut-off date, and prevents subsequent influx of encroachers.

ix. Particular attention will be paid to vulnerable groups including those without legal title to land or other assets; households headed by women; the elderly or disabled; and indigenous groups. Assistance must be provided to help them improve their socio-economic status.

The full resettlement costs will be included in the presentation of project costs and benefits.

3. Comparison of Government and ADB Policy A policy comparison between LA Act, New LA Act 2013 and ADB's Safeguards Policy Statement, 2009 is presented in the following table along with measures to bridge the gap.

Comparison between ADB’s Requirements and the Requirements of the Government of India (RFCTLARRA) and Gap Filling Measures # ADB Safeguard Requirements Provisions in the RFCTLARRA, 2013 Measures to bridge the (SPS, 2009) Gaps Objectives 1 Avoid involuntary resettlement Same - wherever feasible

211

45 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

# ADB Safeguard Requirements Provisions in the RFCTLARRA, 2013 Measures to bridge the (SPS, 2009) Gaps 2 If unavoidable, minimize Same - involuntary resettlement by exploring project and design alternatives 3 To enhance, or at least restore, - The SPS requirements the livelihoods of all displaced will be followed. persons in real terms relative to pre-project levels 4 To improve the standards of living - The SPS requirements of the displaced poor and other will be followed. vulnerable groups. Policy Principles 5 Screen the project early on to While the policy does not specify any Screening of all sub- identify past, present, and future requirement for screening of the project projects in line with the involuntary resettlement impacts at an early stage for resettlement IR checklist of ADB, and risks. impacts and risks, it requires carrying towards enabling out social impact assessment before identification of the any proposal for land acquisition potential resettlement (Section-16). impacts and associated risks. 6 Determine the scope of Carry out census of affected people The SPS requirements resettlement planning through a and their assets to be affected, will be followed. survey and/or census of displaced livelihood loss and common property to persons, including a gender be affected; R&R scheme including analysis, specifically related to time line for implementation.(Section: resettlement impacts and risks 16. (1) and (2)). 7 Carryout consultations with • Consultation with Panchayat, - displaced persons, host Municipality, to carry out SIA. communities and concerned (Section: 4. (1)) NGOs. Inform all displaced • Public hearing for Social Impact persons of their entitlements and Assessment. Section: 5. resettlement options • Discussion on and Public hearing for Draft Rehabilitation and Resettlement Scheme Section: 16. (4). and (5). 8 Establish a project level grievance • Establishment of Land Acquisition, A project level GRM is redress mechanism Rehabilitation and Resettlement included in the RP. Authority for disposal of disputes relating to land acquisition, compensation, rehabilitation and resettlement. Section: 51. (1). and Section: 64. • The Requiring Body or any person aggrieved by the Award passed by an Authority under section 69 may file an appeal to the High Court within sixty days from the date of award. Section: 74. (1). and (2). 9 Where involuntary resettlement Social Impact Assessment is must Social Impact impacts and risks are highly before taking final decision on Assessment, awareness complex and sensitive, acquisition of land followed by campaigns, and social compensation and resettlement preparation of R&R Scheme preparation phase will decisions should be preceded by be done for any projects a social preparation phase. with significant impacts. 10 Improve or restore the livelihoods The SPS requirements of all displaced persons through • Land for land in case of irrigation will be followed. (i) land-based resettlement projects to the land owners losing strategies agricultural land. Land for land in Structures to be

212

46 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

# ADB Safeguard Requirements Provisions in the RFCTLARRA, 2013 Measures to bridge the (SPS, 2009) Gaps (ii) prompt replacement of assets every project to land owners belong compensated at with access to assets of equal or to SC and ST community up to 2.5 replacement cost higher value, acres of land. Section: 31 and The without depreciation (iii) prompt compensation at full Second Schedule replacement cost for assets that • Provision of housing units in case of cannot be restored, and displacement. Offer for developed (iv) additional revenues and land. Section: 31 and The Second services through benefit sharing Schedule schemes where possible. • Recognizes 3 methods and whichever is higher will be considered which will be multiplied by a factor given in The First Schedule. Compensation given earlier will not be considered; If rates not available floor price can be set; Steps to be taken to update the market value. (Section 26 and The First Schedule)Provision for employment, fishing rights, annuity policy etc. (Section: 31 and The Second Schedule) 11 If there is relocation, secured • A family as a unit will receive R&R Alternative resettlement tenure to relocation land, better grant over and above the site is proposed in the housing at resettlement sites with compensation and those who are not framework. comparable access to entitled to compensation. Section: 31 employment and production • Homeless entitled to constructed opportunities, integration of house, land for land in irrigation resettled persons economically projects in lieu of compensation, in and socially into their host case of acquisition for urbanization communities, and extension of 20% of developed land reserved for project benefits to host owners at a prices equal to communities; provide transitional compensation’ jobs or a one-time support and development payment or annuity for 20 years’ assistance, such as land subsistence grant, transportation, development, credit facilities, land and house registered on joint training, or employment name husband and wife, etc. opportunities; and (iii) civic Second Schedule infrastructure and community • Provision for infrastructural services, as required. amenities in resettlement areas. Section: 32 and Third Schedule 12 Improve the standards of living of • Landless people are considered and the displaced poor and other eligible for R&R grants. Section: 16. The entitlement matrix vulnerable groups, including (2). includes the women, to at least national • Widows, divorcees, abandoned requirements of both the minimum standards women will be considered as SPS and the separate family and entitled to R&R RFCTLARRA. provisions Section: 3. (m) • Homeless entitled to constructed house and landless entitled to land in irrigation project. Second Schedule • Special provision for Scheduled Caste/Scheduled Tribe; Section: 41. • Additional provisions for SC&ST for land for land in irrigation projects, additional sum over and above the subsistence grant. Second Schedule

213

47 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

# ADB Safeguard Requirements Provisions in the RFCTLARRA, 2013 Measures to bridge the (SPS, 2009) Gaps 13 If land acquisition is through R&R entitlements apply in case of land Not envisaged. negotiated settlement, ensure that acquired/purchased for PPP projects those who enter into negotiated and for Private Companies. Section: 2. settlements will maintain the same (2), and 46. or better income and livelihood status 14 Ensure that displaced persons • The Act recognises: Section: 3. (c) RF mandates that in the without titles to land or any • a family which does not own any case of land acquisition, recognizable legal rights to land land but belong to the family of an the date of publication of are eligible for resettlement agricultural labourer, tenant, share- preliminary notification assistance and compensation for croppers, or artisans or working in for acquisition under loss of non-land assets. affected area for three years prior to Section 11(1) of the the acquisition of the land RFCTLARRA will be • the Scheduled Tribes and other treated as the cut-off traditional forest dweller who have date for title holders, lost any of their forest rights and for non-titleholders, • family whose primary source of such as, squatters, the livelihood for three years prior to the start date of the project acquisition of the land is dependent census survey. on forests or water bodies and includes gatherers of forest produce, hunters, fisher folk and boatmen • a family residing or earning livelihoods on any land in the urban areas for preceding three years or more prior to the acquisition of the land 15 Prepare a resettlement plan • Preparation of Rehabilitation and - elaborating on displaced persons’ Resettlement Scheme including entitlements, the income and time line for implementation. livelihood restoration strategy, Section: 16. (1) and (2). institutional arrangements, • Separate development plans to be monitoring and reporting prepared. Section 41 framework, budget, and time- bound implementation schedule. 16 Disclose a draft resettlement plan, • The draft Rehabilitation and In addition to the including documentation of the Resettlement Scheme prepared publishing of the consultation process in a timely shall be made known locally by wide approved resettlement manner, before project appraisal, publicity in the affected area and plans, the RF includes in an accessible place and a form discussed in the concerned Gram provision for disclosure and language(s) understandable Sabhas or Municipalities and in of the various to displaced persons and other website. Section: 16. (4) documents pertaining to stakeholders. Disclose the final • The approved Rehabilitation and RP implementation, as resettlement plan and its updates Resettlement Scheme to be made well as disclosure to the to displaced persons and other available in the local language to the affected persons stakeholders Panchayat, Municipality or Municipal through public meetings Corporation and in website. Section: and workshops. 18. 10 Include the full costs of measures The requiring body shall bear the cost The SPS requirements proposed in the resettlement plan of acquisition covering compensation will be followed.- as part of project’s costs and and R&R cost. Section: 19. (2) and benefits. For a project with Section 95. (1) significant involuntary resettlement impacts and / or indigenous peoples plan, consider implementing the involuntary resettlement component of the

214

48 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

# ADB Safeguard Requirements Provisions in the RFCTLARRA, 2013 Measures to bridge the (SPS, 2009) Gaps project as a stand-alone operation. 17 Pay compensation and provide • The Collector shall take possession The SPS requirements other resettlement entitlements of land after ensuring that full will be followed. before physical or economic payment of compensation as well as displacement. Implement the rehabilitation and resettlement resettlement plan under close entitlements are paid within three supervision throughout project months for the compensation and a implementation. period of six months for the monetary part of rehabilitation and resettlement entitlements. Section: 38. (1) • The Collector shall be responsible for ensuring that the rehabilitation and resettlement process is completed in all its aspects before displacing the affected families. Section: 38. (2) 18 Monitor and assess resettlement • The Rehabilitation and Resettlement The SPS requirements outcomes, their impacts on the Committee, to monitor and review will be followed. standards of living of displaced the progress of implementation of persons, and whether the the Rehabilitation and Resettlement objectives of the resettlement plan scheme and to carry out post- have been achieved by taking into implementation social audits in account the baseline conditions consultation with the Gram Sabha in and the results of resettlement rural areas and municipality in urban monitoring. Disclose monitoring areas. Section: 45. (1) reports. • Set up National and State level Monitoring Committee to review and monitor progress. Section 48-50

215

49 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Annexure 2: Grievance Redressal Systems and process

216

50 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Annexure 3: Land Possession Certificate

217

51 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

218

52 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

219

53 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

220

54 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Annexure 4 Translated Summary RP in Local Language KA RESETTLEMENT PLAN NA KA BYNTA KA TRANCHE 2 NERCCDIP Jingbatai Lyngkot jong ka projek (Executive Summary)

Lamphrang (Background)

Ia ka North Eastern Region Capital Cities Development Investment Program (NERCCDIP) la shimti da ka State Investment Project Management and Implementation Unit, jong ka Sorkar Meghalaya (SIPMIU) ban kham pynbha pyndap pynbiang ia ki jingdonkam ha ka ban biang ia ki nongshong shnong ka Greater Shillong Planning Area (GSPA) bad ka Shillong Municipality (SMB) ha kine ki bynta : 1) ka umbam umdih 2) ka jingkhuid jingsuba bad, 3) ka rukom lum niut. La khmih lynti ba lyngba kane ka program NERCCDIP kan kiew ka ioh ka kot jong ki briew ha sor bad kan duna ka jingsahdien ha kaba ianujor bad kiwei ki jaka jong ka ri. Lyngba kane ka investment program la kyrmen ba ki sawdong sawkun jong ki sor bad ka rukom im jong ki nong shong shnong ha kine ki nongbah jong ki thain shatei lam mihngi kiba kynthup ia ka Shillong kin kham bha shuh shuh, ha shuwa u snem 2018. Ka NERCCDIP kan iarap ban kham pyniar bad pynbha ia ki jingdonkam bad jingshakri ha kine ki nongbah kynthup ruh ia ki jaka slum ryngkat bad ka jingpynkhlain ruh ia ki bor pyniaid kiba kynthup ia ki tnad treikam kiba dei khmih ia ki jaka sor ha ka liang ka rukom pyniaid bad ha ka liang rukom pynmih pisa.

Jingbatai lyngkot ia ka kam kiban pyntrei (Subproject description)

1. Ka thong jong kane ka project ka long ban ban ai ia ki jingdonkam kiba iadei bad ka khuid ka suba hapoh ka Greater Shillong Planning Area kaba kynthup iaka jinglum, ka jingrah bad ka jingbret ia u niut ha ka rukom kaba iaid beit kat kum ki kyndon ain Municipal Solid Waste( Management & Handling) Rules, 2000. Lyngba ka Tranche 2 (Bynta ba ar) jong kane ka project la pyntrei ia kine ki kam harum:- (i) ka jingtei ia ka garage cum workshop shed bad ka staff restroom ha Marten; (ii) ka jingthied bad sam ia ki borti lum niut kiba pher ba pher bad ki tiar jingiada ia ki nongtrei; bad (iii) ka jingthied ia ki kali kit niut bad ki tiar karkhana. (iv) Ka jingshna ia ka emergency sanitary landfill ka ba heh kumba 8,500 m2 (phase 2) ha Marten, kane ka kam ka kynthup ia ka jingtei kynroh reinforced cement concrete (RCC), ka leachate holding bad treatment system, ka guard bad weighbridge operator building, ka jingker pud da ki sainar shiah, weigh bridge, bad kumta ter ter, (v) ban thied ia ki tiar (machine) ba kynthup ia ka tracked excavator, vibratory tandem roller, skid steer loader, tanker um, ki tiar ban iakhun ia ka jingklang ding, hydraulic baling press, machine sar surok, bad ka open nallah desilting machine.

Ki Policy bad ki Nongrim (Policy and Principles)

Kum shibynta na ki jingpynkhreh ban tei ia ka sanitary landfill ha Marten la pynkhreh ia kane ka Resettlement Plan (RP), da kaba pynshong nongrim bad bud bniah ia ki polisi jong ka ADB, kata ka Involuntary Resettlement(SPS, 2009) bad ka Resettlement Framework, ryngkat ki ain ka Ri India kiba thymmai ba kynthup ia ka: The Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act 2013 bad ki ain jylla kum ka Khasi Hills Autonomous Districts (Allotment, Occupation or use or setting apart of land) Regulation Bill 2005. Haba pyniadei bad ka Entitlement Matrix, Ka jingsiew bad ka jingaiiarap na ka bynta jong baroh ki briew kiba lah ban shah ktah

221 55 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

na ka jingpyntrei ia kane ka subproject la mang lypa. Ia ki jingiarap yn pynshong nongrim halor kine ki mat harum: 1. Yn ioh lai bnai ka bai bylla na ka daw jong ka jingduh jong ki lad kamai jakpoh, 2. Ia ki longiing ki ba khlieh da ki kynthei kiba na kynhun Scheduled tribe / Scheduled caste, yn ai jingiarap ba kyrpang. 3. Ki longing ba shah ktah na ka jingpyntrei ia ka landfill project yn ai jinghikai kyrpang ha ki jait kam bapher bapher.

Ka jingktah na ka jingpynkynriah jaka (Land acquisition & Involuntary Resettlement impact)

Kane ka project kan nym don kano kano ka jing shim jaka ne jingpynkynriah jaka ia kino kino ki briew. Yn pyntrei kam ia kane ka project ha ka jaka sorkar. Katkum ka Census bad Socio-economic survey kaba la shim ha u November 2013, la shem ba 25 ngut kin lah ban shah ktah na ka jingpyntreikam jong kane ka project. Baroh 25 ngut ki hap ha ka kynhun paid riewlum (Scheduled Tribe) bad na kine 12 ngut ki dei kiba hap ha ka kynhun ba duk tasam (vulnerable BPL group). Kine baroh kin ioh jingiarap katkum ka Resettlement Framework jong ka NERCCDIP.

Ki Hok ioh Jingiarap (Entitlement)

Baroh ki briew kiba lah ban shah ktah na ka jingpyntrei ia ka ne ka project ki don hok ban ioh ia ka bai lut ksan bad ki jingaijingiarap na ka bynta ban pynbha ia ka rukom jingim jongki lane ban pynbiang ia ka ioh ka kot kumba ki long ha shuwa jong ka jingpyntreikam jong kane ka subproject. Ki briew ki ban ioh jing iarap kumba lah pynpaw haneng, kin dei tang kito kiba lah pynithuh ialade ha shuwa ka por ba shim jingkhein ia ki, kata ha shuwa ka 26 November, 2013.

Ka Tnat ba dei Khmih ia ka Kam (Institutional Arrangement)

Ka Implementing Agency ne ka office ban pyntreikam ia ka project ka dei ka State Investment Project Management & Implementation Unit (SIPMIU) hapoh ka Urban Affairs Department, Govt of Meghalaya.

Ka Rukom Khmih ia ka Jingud Ki Paidbah (Grievance Redress Mechanism)

Ban pynbeit ia kano kano ka jingujor, ki jingiapher jingmut ha ka jingpyntreikam ia ka Resettlement Plan bad ban pynduna ki jyrwit jyrwat ha kaba iadei bad ka ain lah buh khnang ia ka Grievance Redressal Committee (GRC) ba khlieh da u Principal Secretary, Urban Affairs Department. Govt of Meghalaya. Ia kiwei de ki dkhot ka Committee yn shim na ka Municipal Board, ki tnad sorkar bapher bapher bad sengbhalang ba trei na ka bynta ka bha ka miat ki paidbah. Ka Independent Grievance Redressal Committee kan khmih ia kawei pa kawei ka jingujor bad kan ialeh ban pynbeit ia ki jingujor hapoh 10 sngi. Lada ym pat lah ban pynbeit ia ki jongujor da ka Independent Grievance Redressal Committee yn rah ia ki sha ki ingbishar. Ka DSMC kan buh jingkhein ia baroh ki jingujor kynthup ia ka tarik, ka jait jing ujor, ka jingpynbeit lane ka jingrai.

222 56 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Ki lad ioh jingtip (Contact Details) Sl. Kyrteng ki Ophisar Kyrdan Mobile No Email Address No. 1. Sri Biswajit Dutta Project Director --- [email protected] 2. Shri. F. B. Chyne Project Manager and Solid 9436100719 [email protected] Waste Management Specialist, SIPMIU. 3. Smt. E. Nongrum Social Safegaurds --- [email protected] Specialist , SIPMIU 4. Shri Sanjiva K Team Leader, DSMC [email protected] Sharma 5. Shri. Arup Khan Social Safegaurds 9868189773 [email protected] Specialist, DSMC 6. Paul Lokho Community 9436832176 [email protected] Development Expert, DSMC

Ki Jingktah bad ki hok ba dei ban ioh (Entitlement Matrix) Rukom Application Ki briew ba dei Ki Policy Ai Ki Mat Bor Badei Duh ban ioh Jingiarap Rukom khmih treikam 1 Jingduh Jingktah ia Ki trai jaka / • Kaba iarap pisa • Yn ithuh ia ki Kan don ka jong ki lad ka ioh ka nongshongwai/ Ki ha kaba duh bylla longing ba sengbhalang kamai kot nongwai jaka/ da kaba kham duna kaban jakpoh kiba treikam pynshong ha kaba pynshisha lajong, kiba bylla nongrim ha ka pyntreikam katno ka kam rep jingduh bylla ia ka RP. jingshah ktah kaba ym duna ia kan long ka 3 bnai. lyngba ka • Kaba ai shuh ka survey kaban bai lutksan kynthup ia khamtam ia ki baroh ki longing kiba duna longing kiban ka jingioh. shah ktah ban • Kaba ai jinghikai ithuh ia ki ban trei ia kiwei longing kiba dei pat ki jaid kam ban ioh ia ka ban pynneh ia ka jingiarap ioh ka kot jong ki.

2 Jingktah ia Baroh ki Ki briew kiban • Ki briew kiba • Baroh ki Ka SIPMIU ki briew jingshah shah pynkynriah shah ktah kin longing ba ryngkat kiban shah ktah jaka khamtam kham ioh ka kham duna bad ka kynriah kiba duk jingnoh ha kaba yn ithuh ha jingiarap jaka ioh bylla ha kaba ka por ba jong ki khamtam pyntreikam ia ka pyntreikam sengbhalang ia kiba projek. ia ka kam kan kham duna • Lada la sa pynshisha ia tyrwa da ka ka jaka ia ka jingktah baroh jaka, ka lyngba ka

223 57 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Rukom Application Ki briew ba dei Ki Policy Ai Ki Mat Bor Badei Duh ban ioh Jingiarap Rukom khmih treikam kyrteng kan survey dei beit ia ha kaba haduh ka kyrteng 100% jong ki trai ban pynshisha jaka . ia baroh ki longing ki ban shah ktah bad ka hok kaba ki dei ban ioh jingiarap. 3 Ia kiwei - - • Ia kino kino ki - Ka SIPMIU kan kiwei ki jingktah kibym peit thuh bha jingduh shim poi pyrkhat ha kano ka kibym pat lypa lada ki don rukom bad ithuh yn buh jingkhein haduh katno ka bad yn ai jingduh kan jingiarap ha ka long. Ka nongrim kaba SIPMIU kan don ha ADB IR pynkhreh ia Policy. baroh kiba dei hok ban ioh katkum ka ADB IR policy

224 58 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Annexure 5 Photographs of Different CPP Activities Awareness in Kharmalki on the 11th July, 2015

SMB Driver Meeting on the 20th July, 2015

Upper New colony distribution on the 21st July, 2015

225 59 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

226 60 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Task Force Police Bazar 22nd July, 2015

Malki Pdengshnong on the 25th July, 2015

227 61 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Workshop on Swacch Bharat NSS Cell NEHU on 30th July, 2015

228 62 SEMI-ANNUAL SOCIAL SAFEGUARDMONITORING REPORT

Annexure 6: Training for Indigenous women Public Consultation cum capacity Building Training for Indigenous women at Madanryting under Gender Action Plan

229 63