Critical Path Method Applied to Research Project Planning: Fire Economics Evaluation System (FEES)
Total Page:16
File Type:pdf, Size:1020Kb
Load more
Recommended publications
-
The Timeboxing Process Model for Iterative Software Development
The Timeboxing Process Model for Iterative Software Development Pankaj Jalote Department of Computer Science and Engineering Indian Institute of Technology Kanpur – 208016; India Aveejeet Palit, Priya Kurien Infosys Technologies Limited Electronics City Bangalore – 561 229; India Contact: [email protected] ABSTRACT In today’s business where speed is of essence, an iterative development approach that allows the functionality to be delivered in parts has become a necessity and an effective way to manage risks. In an iterative process, the development of a software system is done in increments, each increment forming of an iteration and resulting in a working system. A common iterative approach is to decide what should be developed in an iteration and then plan the iteration accordingly. A somewhat different iterative is approach is to time box different iterations. In this approach, the length of an iteration is fixed and what should be developed in an iteration is adjusted to fit the time box. Generally, the time boxed iterations are executed in sequence, with some overlap where feasible. In this paper we propose the timeboxing process model that takes the concept of time boxed iterations further by adding pipelining concepts to it for permitting overlapped execution of different iterations. In the timeboxing process model, each time boxed iteration is divided into equal length stages, each stage having a defined function and resulting in a clear work product that is handed over to the next stage. With this division into stages, pipelining concepts are employed to have multiple time boxes executing concurrently, leading to a reduction in the delivery time for product releases. -
Division 01 – General Requirements Section 01 32 16 – Construction Progress Schedule
DIVISION 01 – GENERAL REQUIREMENTS SECTION 01 32 16 – CONSTRUCTION PROGRESS SCHEDULE DIVISION 01 – GENERAL REQUIREMENTS SECTION 01 32 16 – CONSTRUCTION PROGRESS SCHEDULE PART 1 – GENERAL 1.01 SECTION INCLUDES A. This Section includes administrative and procedural requirements for the preparation, submittal, and maintenance of the progress schedule, reporting progress of the Work, and Contract Time adjustments, including the following: 1. Format. 2. Content. 3. Revisions to schedules. 4. Submittals. 5. Distribution. B. Refer to the General Conditions and the Agreement for definitions and specific dates of Contract Time. C. The above listed Project schedules shall be used for evaluating all issues related to time for this Contract. The Project schedules shall be updated in accordance with the requirements of this Section to reflect the actual progress of the Work and the Contractor’s current plan for the timely completion of the Work. The Project schedules shall be used by the Owner and Contractor for the following purposes as well as any other purpose where the issue of time is relevant: 1. To communicate to the Owner the Contractor’s current plan for carrying out the Work; 2. To identify work paths that is critical to the timely completion of the Work; 3. To identify upcoming activities on the Critical Path(s); 4. To evaluate the best course of action for mitigating the impact of unforeseen events; 5. As the basis for analyzing the time impact of changes in the Work; 6. As a reference in determining the cost associated with increases or decreases in the Work; 7. To identify when submittals will be submitted; 8. -
Basics of Project Planning
BASICS OF PROJECT PLANNING © Zilicus Solutions 2012 Contents The Basics of Project Planning ............................................................................................................. 3 Introduction ..................................................................................................................................... 3 What is Project Planning? ................................................................................................................ 3 Why do we need project planning? ................................................................................................. 3 Elements of project plan .................................................................................................................. 4 1. Project Scope Planning ...................................................................................................... 4 Triangular Constraints (TQR) ............................................................................................................ 5 2. Delivery Schedule Planning ............................................................................................... 5 3. Project Resources Planning ................................................................................................ 6 4. Project Cost Planning ......................................................................................................... 8 5. Project Quality Planning .................................................................................................... 9 -
Intro to BPC Logic Filter
INTRODUCTION TO BPC LOGIC FILTER FOR MICROSOFT PROJECT Prepared For: General Release Prepared By: Thomas M. Boyle, PE, PMP, PSP BPC Project No. 15-001 First issue 29-May-15 (Updated 02-Dec-20) Boyle Project Consulting, PLLC 4236 Chandworth Rd. Charlotte, NC 28210 Phone: 704-916-6765 Project Management and Construction Support Services [email protected] Introduction to – BPC Logic Filter for Microsoft Project 02-Dec-20 TABLE OF CONTENTS 1.0 EXECUTIVE SUMMARY .................................................................................................... 1 2.0 BACKGROUND / MOTIVATION ...................................................................................... 1 2.1 HISTORY ................................................................................................................................... 1 2.2 NEEDS ....................................................................................................................................... 1 3.0 PROGRAM DEVELOPMENT ............................................................................................ 2 3.1 FEATURE DEVELOPMENT ......................................................................................................... 2 3.2 SHARING THE TOOLS .............................................................................................................. 12 4.0 USER APPLICATIONS AND SETTINGS ....................................................................... 12 5.0 SOFTWARE EDITIONS AND LICENSING .................................................................. -
By Philip I. Thomas
Washington University in St. Louis Scheduling Algorithm with Optimization of Employee Satisfaction by Philip I. Thomas Senior Design Project http : ==students:cec:wustl:edu= ∼ pit1= Advised By Associate Professor Heinz Schaettler Department of Electrical and Systems Engineering May 2013 Abstract An algorithm for weekly workforce scheduling with 4-hour discrete resolution that optimizes for employee satisfaction is formulated. Parameters of employee avail- ability, employee preference, required employees per shift, and employee weekly hours are considered in a binary integer programming model designed for auto- mated schedule generation. Contents Abstracti 1 Introduction and Background1 1.1 Background...............................1 1.2 Existing Models.............................2 1.3 Motivating Example..........................2 1.4 Problem Statement...........................3 2 Approach4 2.1 Proposed Model.............................4 2.2 Project Goals..............................4 2.3 Model Design..............................5 2.4 Implementation.............................6 2.5 Usage..................................6 3 Model8 3.0.1 Indices..............................8 3.0.2 Parameters...........................8 3.0.3 Decision Variable........................8 3.1 Constraints...............................9 3.2 Employee Shift Weighting.......................9 3.3 Objective Function........................... 11 4 Implementation and Results 12 4.1 Constraints............................... 12 4.2 Excel Implementation......................... -
Unit 5 – Project Planning
Unit 5 – Project Planning UNIT OVERVIEW Description of the Unit In this unit, you will explore the necessity of proper project planning and how ‘front end’ planning can ensure project success. You will look at several scenarios that put a structure around project scope, deliverables, scheduling, staffing, resources, and risks to help anchor the planning process. Unit Objectives At the conclusion of this unit, you will be able to: • Understand the necessity of a project plan • Assess resource and budgeting issues • Analyze project risks • Effectively determine project scope • Identify project deliverables Unit Topics • Project schedules based on work breakdown structures • Project resources and schedules based on staff availability • Project budgets • Managing project risks • Triple constraint to achieve project goals Activities and Exercises • Group Exercise 5A: Project Management Scenarios • Group Exercise 5B: Review Project Plans for Unit 3 Scenarios Approximate Time for Unit 1 hour 45 minutes Managing Technology Projects and Technology Resources Participant Guide 5 - 1 Institute for Court Management Unit 5 – Project Planning Managing Technology Projects and Technology Resources Participant Guide 5 - 2 Institute for Court Management Unit 5 – Project Planning ___________________________________ ___________________________________ ___________________________________ ___________________________________ UNIT 5 ___________________________________ Project Planning ___________________________________ ___________________________________ ©2010 -
Overview of Project Scheduling Following the Definition of Project Activities, the Activities Are Associated with Time to Create a Project Schedule
Project Management Planning Development of a Project Schedule Initial Release 1.0 Date: January 1997 Overview of Project Scheduling Following the definition of project activities, the activities are associated with time to create a project schedule. The project schedule provides a graphical representation of predicted tasks, milestones, dependencies, resource requirements, task duration, and deadlines. The project’s master schedule interrelates all tasks on a common time scale. The project schedule should be detailed enough to show each WBS task to be performed, the name of the person responsible for completing the task, the start and end date of each task, and the expected duration of the task. Like the development of each of the project plan components, developing a schedule is an iterative process. Milestones may suggest additional tasks, tasks may require additional resources, and task completion may be measured by additional milestones. For large, complex projects, detailed sub-schedules may be required to show an adequate level of detail for each task. During the life of the project, actual progress is frequently compared with the original schedule. This allows for evaluation of development activities. The accuracy of the planning process can also be assessed. Basic efforts associated with developing a project schedule include the following: • Define the type of schedule • Define precise and measurable milestones • Estimate task duration • Define priorities • Define the critical path • Document assumptions • Identify risks • Review results Define the Type of Schedule The type of schedule associated with a project relates to the complexity of the implementation. For large, complex projects with a multitude of interrelated tasks, a PERT chart (or activity network) may be used. -
Real-Time Scheduling (Part 1) (Working Draft)
Real-Time Scheduling (Part 1) (Working Draft) Insup Lee Department of Computer and Information Science School of Engineering and Applied Science University of Pennsylvania www.cis.upenn.edu/~lee/ CIS 541, Spring 2010 Real-Time System Example • Digital control systems – periodically performs the following job: senses the system status and actuates the system according to its current status Sensor Control-Law Computation Actuator Spring ‘10 CIS 541 2 Real-Time System Example • Multimedia applications – periodically performs the following job: reads, decompresses, and displays video and audio streams Multimedia Spring ‘10 CIS 541 3 Scheduling Framework Example Digital Controller Multimedia OS Scheduler CPU Spring ‘10 CIS 541 4 Fundamental Real-Time Issue • To specify the timing constraints of real-time systems • To achieve predictability on satisfying their timing constraints, possibly, with the existence of other real-time systems Spring ‘10 CIS 541 5 Real-Time Spectrum No RT Soft RT Hard RT Computer User Internet Cruise Tele Flight Electronic simulation interface video, audio control communication control engine Spring ‘10 CIS 541 6 Real-Time Workload . Job (unit of work) o a computation, a file read, a message transmission, etc . Attributes o Resources required to make progress o Timing parameters Absolute Released Execution time deadline Relative deadline Spring ‘10 CIS 541 7 Real-Time Task . Task : a sequence of similar jobs o Periodic task (p,e) Its jobs repeat regularly Period p = inter-release time (0 < p) Execution time e = maximum execution time (0 < e < p) Utilization U = e/p 0 5 10 15 Spring ‘10 CIS 541 8 Schedulability . Property indicating whether a real-time system (a set of real-time tasks) can meet their deadlines (4,1) (5,2) (7,2) Spring ‘10 CIS 541 9 Real-Time Scheduling . -
Planning and Scheduling in Supply Chains: an Overview of Issues in Practice
PRODUCTION AND OPERATIONS MANAGEMENT POMS Vol. 13, No. 1, Spring 2004, pp. 77–92 issn 1059-1478 ͉ 04 ͉ 1301 ͉ 077$1.25 © 2004 Production and Operations Management Society Planning and Scheduling in Supply Chains: An Overview of Issues in Practice Stephan Kreipl • Michael Pinedo SAP Germany AG & Co.KG, Neurottstrasse 15a, 69190 Walldorf, Germany Stern School of Business, New York University, 40 West Fourth Street, New York, New York 10012 his paper gives an overview of the theory and practice of planning and scheduling in supply chains. TIt first gives an overview of the various planning and scheduling models that have been studied in the literature, including lot sizing models and machine scheduling models. It subsequently categorizes the various industrial sectors in which planning and scheduling in the supply chains are important; these industries include continuous manufacturing as well as discrete manufacturing. We then describe how planning and scheduling models can be used in the design and the development of decision support systems for planning and scheduling in supply chains and discuss in detail the implementation of such a system at the Carlsberg A/S beerbrewer in Denmark. We conclude with a discussion on the current trends in the design and the implementation of planning and scheduling systems in practice. Key words: planning; scheduling; supply chain management; enterprise resource planning (ERP) sys- tems; multi-echelon inventory control Submissions and Acceptance: Received October 2002; revisions received April 2003; accepted July 2003. 1. Introduction taking into account inventory holding costs and trans- This paper focuses on models and solution ap- portation costs. -
49R-06: Identifying the Critical Path 2 of 13
49R-06 IDENTIFYING THE CRITICAL PATH SAMPLE AACE® International Recommended Practice No. 49R-06 IDENTIFYING THE CRITICAL PATH TCM Framework: 7.2 – Schedule Planning and Development 9.2 – Progress and Performance Measurement 10.1 – Project Performance Assessment 10.2 – Forecasting Rev. March 5, 2010 Note: As AACE International Recommended Practices evolve over time, please refer to www.aacei.org for the latest revisions. Contributors:SAMPLE Disclaimer: The opinions expressed by the authors and contributors to this recommended practice are their own and do not necessarily reflect those of their employers, unless otherwise stated. Christopher W. Carson, PSP (Author) Paul Levin, PSP Ronald M. Winter, PSP (Author) John C. Livengood, PSP CFCC Abhimanyu Basu, PE PSP Steven Madsen Mark Boe, PE PSP Donald F. McDonald, Jr. PE CCE PSP Timothy T. Calvey, PE PSP William H. Novak, PSP John M. Craig, PSP Jeffery L. Ottesen, PE PSP CFCC Edward E. Douglas, III CCC PSP Hannah E. Schumacher, PSP Dennis R. Hanks, PE CCE L. Lee Schumacher, PSP Paul E. Harris, CCE James G. Zack, Jr. CFCC Sidney J. Hymes, CFCC Copyright © AACE® International AACE® International Recommended Practices AACE® International Recommended Practice No. 49R-06 IDENTIFYING THE CRITCAL PATH TCM Framework: 7.2 – Schedule Planning and Development 9.2 – Progress and Performance Measurement 10.1 – Project Performance Assessment 10.2 – Forecasting March 5, 2010 INTRODUCTION Purpose This recommended practice (RP) for Identifying the Critical Path is intended to serve as a guideline and a resource, not to establish a standard. As a recommended practice of AACE International it provides guidelines for the project scheduler when reviewing a network schedule to be able to determine the critical path and to understand the limitations and assumptions involved in a critical path assessment. -
Scheduling: Introduction
7 Scheduling: Introduction By now low-level mechanisms of running processes (e.g., context switch- ing) should be clear; if they are not, go back a chapter or two, and read the description of how that stuff works again. However, we have yet to un- derstand the high-level policies that an OS scheduler employs. We will now do just that, presenting a series of scheduling policies (sometimes called disciplines) that various smart and hard-working people have de- veloped over the years. The origins of scheduling, in fact, predate computer systems; early approaches were taken from the field of operations management and ap- plied to computers. This reality should be no surprise: assembly lines and many other human endeavors also require scheduling, and many of the same concerns exist therein, including a laser-like desire for efficiency. And thus, our problem: THE CRUX: HOW TO DEVELOP SCHEDULING POLICY How should we develop a basic framework for thinking about scheduling policies? What are the key assumptions? What metrics are important? What basic approaches have been used in the earliest of com- puter systems? 7.1 Workload Assumptions Before getting into the range of possible policies, let us first make a number of simplifying assumptions about the processes running in the system, sometimes collectively called the workload. Determining the workload is a critical part of building policies, and the more you know about workload, the more fine-tuned your policy can be. The workload assumptions we make here are mostly unrealistic, but that is alright (for now), because we will relax them as we go, and even- tually develop what we will refer to as .. -
Planning in Software Project Management
PLANNING IN SOFTWARE PROJECT MANAGEMENT AN EMPIRICAL RESEARCH OF SOFTWARE COMPANIES IN VIETNAM Thesis presented to the Faculty of Economics and Social Sciences at the University of Fribourg (Switzerland) in fulfillment of the requirements for the degree of Doctor of Economics and Social Sciences by Quynh Mai NGUYEN from Vietnam Accepted by the Faculty of Economics and Social Sciences on May 30th, 2006 at the proposal of Professor Dr. Andreas Meier (first advisor) Professor Dr. Jacques Pasquier (second advisor) Professor Dr. Laurent Donzé (third advisor) Fribourg, Switzerland 2006 The Faculty of Economics and Soci al Sciences at the University of Fribourg neither approves nor disapproves the opinions expressed in a doctoral dissertati on. They are to be considered those of the author (decision of the Faculty Council of January 23rd, 1990). To my parents, and To Phuong and Trung, my children ACKNOWLEDGEMENT I would like to express my extreme gratitude to Prof. Dr. Andreas Meier for his guidance, encouragement and helpful supervision during the process of this thesis. I would like to thank Prof. Jacques Pasquier and Prof. Laurent Donzé for their review and comments. My special thanks also go to Dr. Fredric William Swierczek for his invaluable help, advices and suggestions for improvement. Without their help and advice this dissertation could not be completed. I would like to thank my friends, Dr. Bui Nguyen Hung, and Dr. Nguyen Dac Hoa, Mrs. Nguyen Thuy Quynh Loan for their assistance and helpful suggestions and contributions. I would like to thank the government of Switzerland and the Swiss – AIT – Vietnam Management Development Program (SAV) for giving me the scholarship for this PhD program.